Modification of Group Housing Project, Village Babupur, Sector -108, , CONCEPTUAL PLAN

CONCEPTUAL PLAN

INTRODUCTION

M/s Chintel Limited is a leading real estate developer company in Haryana. It now proposes to revise/modify the Group Housing Project at Village Babupur, Sector 108, Near New Palam Vihar, Gurgaon, Haryana.

The project was granted Environmental Clearance by SEIAA, Haryana vide letter no. SEIAA/HR/2010/1021 dated 25th November, 2010 for plot area 1,59,345 sq.m & built-up area 4,23,535.3 sq.m. EC letter is enclosed as Annexure-I.

NOC (Consent to establish) has been obtained from HSPCB, copy of same is enclosed as Annexure-II. However, construction has not been started yet.

The project scheme has undergone modification as a result of which the built up area has reduced from 4,23,535.3 to 4,19,749.495 sq.m for which EC is being sought.

SITE LOCATION AND SURROUNDINGS

The project site is located at Village Babupur, Sector 108, Gurgaon, Haryana. The geographical co-ordinates of the project site are 28°30'55"N 76°59'40"E. Google map of 500 m radius & SoI Toposheet for 2, 5 and 10 km showing location of project site and surroundings are enclosed as Annexure-III.

CONNECTIVITY

The area has good infrastructure facilities. The nearest highway is NH-8, about 7.7 km from the project site. The nearest railway station is Gurgaon about 3.20 km (SW) away from the project site. The nearest airport is IGI at a distance of approx. 9.1 km (NE).

AREA STATEMENT

93 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

The total area of project site is 1,52,515.90 m2 (or 37.687acre). The detailed area statement is given below in Table 1 along with comparison with values of accorded EC: Table 1: Detailed Area Statement

S. No. Total Area Particulars Values in Modification in Accorded EC EC accorded 2 (m2) value (m2) (m )

1. Plot Area 1,59,345.0 Nil 1,59,345.0 2. Net Plot area 1,59,345.0 - 6829.099 1,52,515.901 47,803.4 53,380.565 Permissible Ground (30% of plot/net 5577.165 (35% of net plot Coverage 3. plot area) area) 17,641.4 53,248.596 Proposed Ground (11.07% of 35,607.196 (34.91% of net Coverage 4. plot/net plot area) plot area) 2,78,853.7 2,66,902.826 Permissible FAR (@ 1.75 of -11,950.874 (@ 1.75 of net 5. plot/net plot area) plot area) 2,78,852.0 2,66,649.088 Proposed FAR (@ 1.744 of -12,202.912 (@ 1.748 of net plot/net plot area) plot area)  Residential 2,68,469.3 - 22,347.654 2,46,121.646

 Community 796.6 2161.42 2958.02

 Convenient Shopping 796.7 -35.171 761.529 6.  Entrance Portal Nil 25.035 25.035

 EWS Tower 8593.5 - 491.202 8102.298

 Pool change rooms Nil 85.5 85.5

 OWC- 01& 02 Nil 585.2 585.2

 Stilt floor Nil 8009.86 8009.86 7. Primary School Nil 4022.495 4022.495 8. Nursery School (1 & 2) Nil 1563.536 1563.536 9. Basement Area 88,289.96 -14,628.055 73,661.905

94 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

10. Non-FAR Nil 73,852.472 73,852.472 11. Towers Nil 31145.208 31145.208 EWS Tower Nil 406.852 406.852 Stilt floor Nil 40821.51 40821.51 Mumty area Nil 1437.362 1437.362 Head rooms of STP 1 & 2 Nil 41.54 41.54 12. Built-up Area 4,23,535.3 - 3785.804 4,19,749.496 52,913.02 (34.69 % of net Landscape area 62,375.1 -9462.08 plot area) 13. 14. Height of the tallest 60 m 20.3 m 80.30 m building

Table 2: Built-Up Area Details

S. No. Particulars Area (in m2) Proposed FAR 2,66,649.088 Residential 2,46,121.646 Community 2958.02 Convenient Shopping 761.529 1. Entrance Portal 25.035 EWS Tower 8102.298 Pool change rooms 85.5 OWC- 01& 02 585.2 Stilt floor 8009.86 2. Primary School 4022.495 3. Nursery School (1 & 2) 1563.536 4. Basement Area 73,661.905 Non-FAR 73,852.472 Towers 31,145.208 EWS Tower 406.852 5. Stilt floor 40,821.51 Mumty area 1437.362 Head rooms of STP 1 & 2 41.54 Total Built-up area 4,19,749.496

95 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

POPULATION DENSITY

The total population for the project is 12,264 persons (fixed + floating). The detailed population breakup is given below in the following Table 3. Table 3: Population Distribution (Comparative)

Modification in S. Value in accorded Description EC accorded Total No. EC value Population  Residents of General DUs 10,450 (DU = 2090) -1810 (DU = -362) 8640 (DU = 1728) (@5 persons per unit) 1.  Staff 523 - 91 864  Visitors 1045 - 181 864

 Residents of EWS units 925 (370 DU) 295 (DU = -65) 1220 (DU = 305) 2.  Visitors 92 -30 122

Convenient Shopping Staff

3. (Considering 4 sq. m of shop

carpet area/ person) 20 234 254

Primary School

(20 pupils/ classroom + 1 teacher per classroom, 4. Nil 198 198 activity room, computer room, activity room & Gym + 1 Librarian, + Principal + 10 office staff + 5 no of persons) Nursery School (1& 2)

5. (10 pupils/classroom + 1 15 87 102 Principal + 5 office staff + 4 persons) Club House 220

 Staff 25 -5 20  Visitors Nil 200 200

96 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Total Population 13,095 -789 12,264

WATER REQUIREMENT

The total water requirement for Group Housing Project is approx. 1727 KLD out of which domestic water demand is 1410 KLD. The total fresh water requirement is approx. 987 KLD (70% of domestic water). The water will be supplied by HUDA. The daily water requirement calculations are given in Table 4 to 6.

Table 4: Comparative Details of Water & Wastewater generated EC Modification S. accorded in EC Total Particulars No. value accorded (KLD) (KLD) value 1. Total Water Requirement 1997.5 -270.5 1727 2. Domestic Water 1356.2 53.8 1410 3. Total Fresh Water 1128.1 -141.1 987 4. Wastewater 1386 -173 1213 5. STP capacity 1663 -113 1550

97 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Table 5: Calculations for Daily Water Demand (after Modification) S. No. Rate of water Total Water Description Occupancy demand (lpcd) Requirement (KLD) A. Domestic Water (a) Residential population 9860 135 1331 (b) Staff 1418 45 64 (c ) Visitors 986 15 15 Sub Total (a+b+c) 1410 KLD

Total domestic water demand = 1410KLD B. Landscape 52,913.02 m2 6 l/sqm/day 317

Grand Total (A+B) =1727 KLD

Table 6: Wastewater Calculation (after Modification) S. Parameter Quantity No. 1. Domestic Water Requirement 1410 KLD

2. Fresh (70% of domestic) 987 KLD

3. Flushing (30% of domestic) 423 KLD

4. Wastewater Generated (80% potable + 100% 790 + 423 = 1213 KLD flushing) 5. STP Capacity 600 + 720 + 230 = 1550 KLD

98 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

@ 80% FRESH WATER WASTEWATER GENERATED (987 KLD) (1213 KLD) (@ 70% of Domestic water) STP CAPACITY (600 + 720 + 230 = 1550 KLD) @ 100% FLUSHING (423 KLD) 423 KLD (@ 30% of Domestic water) @90 % 1092KLD 317 KLD HORTICULTURE (317 KLD)

352 KLD DISCHARGE TO EXTERNAL SEWER (352 KLD)

Wastewater5 KLD waterwaterwater Treated effluent

Figure 1: Water Balance Diagram (Non-rainy season)

99 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

@ 80% FRESH WATER WASTEWATER GENERATED (987 KLD) (1213 KLD) (@ 70% of Domestic water) STP CAPACITY (600 + 720 + 230 = 1550 KLD) @ 100% FLUSHING (423 KLD) 423 KLD (@ 30% of Domestic water) @90 % 1092KLD

DISCHARGE TO 669 KLD EXTERNAL SEWER (352 KLD)

Wastewater5 KLD waterwaterwater Treated effluent

Figure 2: Water Balance Diagram (Rainy season)

100 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Sullage Generation & Treatment It is expected that the project after modification will generate approx. 1213 KLD of sullage. The sullage will be treated in 3 onsite STPs of 600 KLD, 720 KLD and 230 KLD capacity that will generate 1092 KLD of treated water from STP which will be reused for flushing, horticulture.

SEWAGE TREATMENT TECHNOLOGY

EXTENDED AERATION TECHNOLOGY Sewerage System An external sewage network shall collect the sewage from all units, and flow by gravity to the proposed sewage treatment plant.

Following are the benefits of providing Sewage Treatment Plant:  Reduced net daily water requirements, source for Horticultural purposes by utilization of the treated sullage.  Reduced dependence on the public utilities for water supply and sewerage systems.  Sludge generated from the Sewage Treatment Plant shall be rich in organic content and an excellent fertilizer for horticultural purpose.

Treatment Technology Treatment technology is based on the Extended Aeration Technology. Raw sewage will be collected under gravity into the sump after allowing to pass through the bar screen. The bar screen, by removing coarse solids from the sewage help in protecting the raw sewage pump. The raw sewage sump, through temporarily holding the incoming sewage facilitates both pumping of sewage through the STP and dampening the flow variation in the received sewage. The sewage collected in equalization tank is pumped and passed through the Aeration tank. From the aeration tank, the raw sewage goes to a settling tank (Clarifier) to allow gravity separation of the mixed liquor suspended solids from the treated sullage. Settled MLSS are then recycled to the aeration tank. Excess sludge from the system is drained out. The excess sludge will be dewatered and used as manure for green belt development. The effluent coming

101 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN after treatment will be stored in a sump of desired capacity. Treated effluent coming out from the sump will be passed through softening plant followed with disinfection.

Figure 3: Schematic Diagram of STP a. Sullage Details (a) Daily load : 1213 KLD (b) Duration of flow to STP : 24 hours (c) Temperature : Maximum 32oC (d) pH : 6.5-7.5 (e) Colour : Mild (f) T.S.S. (mg/l) : 150-200 mg/l

102 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

(g) BOD5 (mg/l) : 250 mg/l (h) COD (mg/l) : 500 mg/l b. Final discharge characteristics (a) pH : 6.5 to 7.5 (b) Oil & Grease : <10 mg/l (c) B.O.D. : <10 mg/l (d) C.O.D. : <30 mg/l (e) Total Suspended Solids : <20 mg/l

Sewer System

The alignment and slope of the sewer line will follow the road network, drains or natural ground surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a pumping station, a water course or an intercepting sewer. Pumping stations would be provided at places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of excavation is uneconomical to do the same.

103 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

RAIN WATER HARVESTING

The storm water collection system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area and the time required for such flow to reach the drains. The drains shall be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall flow towards the drains. Storm water from various plots/shall be connected to adjacent drain by a pipe through catch basins. 134 Rainwater harvesting pits at selected locations, which will catch the maximum run-off from the area. 1) Since the existing topography is congenial to surface disposal, a network of storm water pipe drains is planned adjacent to roads. All building roof water will be brought down through rain water pipes. 2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the sumps. This water will be pumped out to the nearest external storm water drain. 4) The peak hourly rainfall of 21.3 mm/day shall be considered for designing the storm water drainage system.

Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly rainfall has been considered as 21.3 mm/day. The recharge pit of 1.2 m diameter and 3.0 m depth is constructed for recharging the water. The ground water level in the area is 30-40 meters bgl. The bottom of the recharge structure will be kept 4m above this level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows:  Catchments/roofs would be accessible for regular cleaning.  The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off.  No sewage or wastewater would be admitted into the system.

104 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

 No wastewater from areas likely to have oil, grease, or other pollutants has been connected to the system. Rain water harvesting pits comparative details are given below in Table 7.

Table 7: Rainwater Harvesting Pits S. No. Description Value in Modification in EC Total accorded accorded value EC 1. Rainwater harvesting 20 +114 134 pits

Calculations for storm water load

Average annual rainfall 596.0 mm

No. of rainy days 28.0

Average rainfall intensity per day 21.3 mm/day

Total landscape area 52,913.0 Sq.m

Run off co-efficient 0.1

Surface Run-off from Landscape 113 m3/day

Total pavement area 46,222.23 Sq.m

Run off co-efficient 0.8

Surface Run-off from Pavement 787.1 m3/day

Total surface runoff 900 m3/day

Size of recharge pit 1.2 m dia

3.0 m depth

Surface area of recharge pit 11.31 m2

Percolation capacity 25 mm/hr/m2

105 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

No. of recharge pits required 133 Nos.

No. of recharge pits provided 134 Nos.

Total of 134 Rain Water Harvesting pits are being proposed for artificial ground water recharge.

PARKING FACILITIES

Adequate provision will be made for car/vehicle parking within the project site. There shall also be additional parking for visitors so as not to disturb the traffic and allow smooth movement.

The details of parking requirement and parking proposed are given below in Table -8 along with comparative of figure of accorded EC:

Table 8: Comparative Parking details

Modification in Description Values in accorded EC EC accorded Total value

Total Parking 6762 ECS -3669 3093

Parking required for Modification: As per MoEFCC norms: For Residential facilities = 1 ECS/100 m2 FAR = 246121.646/100 = 2461 ECS For Community Building & Convenient shopping = 2 ECS/100 m2 FAR = 3719.549/50 = 75 ECS Total Parking required = 2461 + 75 = 2536 ECS

As per Haryana bye-laws: For Residential: 1.5 Per DU’s (1728 DU’s) = 2592 ECS For EWS: @ 5% of main dwelling unit parking = 130 ECS

106 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

For Community Building & Convenient shopping = 2 ECS/100 sq.m. FAR = 3719.549/50 = 75 ECS

Total Parking required = 2592 + 130 + 75 = 2797 ECS

Parking Proposed Area proposed for basement parking = 55615 m2 Area required for 1 ECS of basement parking = 35 m2 Parking proposed for basement = 1589 ECS Area proposed for stilt parking = 30900 m2 Area required for 1 ECS of stilt parking = 30 m2 Parking proposed for stilt = 1030 ECS Area proposed for surface parking = 11850 m2 Area required for 1 ECS of surface parking = 25 m2 Parking proposed for surface = 474 ECS Total Parking proposed = 1589 + 1030 + 474 = 3093 ECS

POWER REQUIREMENT

The power shall be supplied by Dakshin Haryana Bijli Vitran Nigam. The electrical load for the project will be 23,424 kVA.

S. No. Description Values in Modification Total Accorded In Accorded (Modification) EC Area 1 Total power 11,143 kVA 12,281 kVA 23,424 kVA requirement

Details of D.G Sets

107 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

The proposed DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion. No. of D.G. sets proposed for power back-up are as under: 1 DG for 100 KVA and 160 KVA, 24 DGs for 500 KVA, 6 DGs for 750 KVA and 6 DGs for 1500 KVA.

SOLID WASTE GENERATION

Solid waste would be generated both during the construction as well as operation phase. The solid waste expected to be generated during the construction phase will comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed to be followed for the management solid waste:  Construction yards are proposed for storage of construction materials.  The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction  Excavated top soil will be stored in temporary constructed soil bank and will be reused for landscaping.  Remaining soil shall be utilized for refilling / road work / rising of site level at locations/ selling to outside agency for construction of roads etc.

108 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Solid Waste

Construction Waste

Construction Empty waste, Cement Excavated Soil Broken Bricks, Bags Waste Plaster

Top soil conserved for landscaping, Used in re-filling, balance used in re- For Road Making raising site level filling

Figure 4: Solid Waste Management Scheme (Construction Phase)

During operation phase, waste will comprise of domestic and landscape waste. The estimated quantity of the waste is approx. 5537 kg per day (@ 0.5 kg per capita per day for residents, @ 0.25 kg per capita per day for the staff, @0.15 kg per capita per day for the visitor, landscape waste @ 0.2 kg/acre/day). Following arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and Handling) Rules, 2016. Comparative details of Solid waste are given below in Table 9:

Table 9: Solid Waste Generation S. No. Description Values in Modification in Total accorded EC EC accorded value 1. Solid waste 6027 kg - 490 kg/day 5537 kg/day

109 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Table 10: Calculation of Solid Waste Generation (after Modification) Waste generated Waste generated S. No. Category (kg/capita/day) (kg/day) 1. Residents 9860 @ 0.5 kg/day 4930 2. Visitors 986 @ 0.15 kg/day 147.9 3. Staff 1418 @ 0.25 kg/day 354.5 4. Landscape waste @ 0.2 kg/acre/day 2.60 (13.07 acre) 5. STP Sludge 102 TOTAL SOLID WASTE GENERATED 5537 kg/day [Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)]

 Collection and Segregation of waste 1. A door to door collection system will be provided for collection of domestic waste in colored bins from household units. 2. The local vendors will be hired to provide separate colored bins for dry recyclables and Bio-degradable waste. 3. For waste collection, adequate number of colored bins (Green and Blue and dark grey bins– separate for Bio-degradable and Non Bio-degradable) are proposed to be provided at the strategic locations of the project site. 4. Litter bin will also be provided in open areas like parks etc. 5.  Treatment of waste  Bio-Degradable wastes 1. Bio-degradable waste will be subjected to organic waste converter and the compost will be used as manure. 2. STP sludge is proposed to be used for horticultural purposes as manure. 3. Horticultural Waste is proposed to be composted and will be used for gardening purposes.  Recyclable wastes

110 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

i. Grass Recycling – The cropped grass will be spread on the green area. It will act as manure after decomposition. ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclers.  Disposal Inert waste will be disposed through an approved agency. Solid waste management Scheme is depicted in the following figure.

Solid Waste

Biodegradable Non Biodegradable Waste Waste Recyclable Non- Recyclable

Dark grey Blue Bins Dark grey Bins Bins Organic waste Converter Final disposal through a Final disposal through Govt. approved agency Manure Govt. approved agency to recycling industry

Figure 5: Solid Waste Management Scheme (Operation Phase)

GREEN AREA

Total green area as per accorded EC was 62,375.1 m2 and after modification will reduce to 52,913.02 m2 as net plot area has reduced. Green area includes area under greenbelt plantation, avenue plantation, organized green spaces, etc. Evergreen, tall and ornamental trees have been proposed to be planted inside the premises.

111 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

Table 11: List of plant species S. No. Scientific name Local name 1. Grevillea Robusta Silk Oak 2. Polvalthia Longifolia Ashoka 3. Cassia Fistula Amaltas 4. Bauhine Variegata Kachnar ORNAMENTAL SHRUBS 1. Delonix pulcherima Chhota gulmohar 2. Plumeria Alba Champa 3. Lagerstroemia indica Dhayti CREEPERS 1. Vernonia Selwna Curtain Creeper 2. Bougan valia Paper flopwers GROUND COVER 1. Laantana selowina Wild Sage 2. Tradescantia flumen Wandering Jew 3. Ipomia Palmata Railway Creeper GRASSES 1. Cynodon Dactylon Doob Grass

DETAILS OF CONSTRUCTION MATERIAL

List of building materials being used at site: 1. Coarse sand 2. Fine sand 3. Stone aggregate

112 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

4. Stone for masonry work 5. Cement 6. Reinforcement steel 7. Pipe scaffolding (cup lock system) 8. Bricks 9. CLC fly ash blocks 10. Crazy (white marble) in grey cement 11. P.V.C. conduit 12. MDS, MCBs 13. 2 1/2'’ thick paver tiles 14. PPR (ISI marked) 15. PVC waste water lines 16. S.W. sewer line up to main sewer 17. PVC rain water down take 18. Stainless steel sink in kitchen 19. Joinery hardware- ISI marked

MATERIALS USED FOR CONSTRUCTION & THEIR U-VALUES

113 M/s Chintel India Pvt. Ltd. Modification of Group Housing Project, Village Babupur, Sector -108, Gurgaon, Haryana CONCEPTUAL PLAN

LIST OF MACHINERY USED DURING CONSTRUCTION

(i) Dumper : Shall be used for mud and material handling (ii) Concrete mixer with hopper : For RCC work (iii) Excavator : Shall be used for digging and earth work (iv) Concrete Batching Plant : Will be used for concrete mixing (v) Cranes : For lifting and moving of materials. (vi) Road roller : For compacting the earth (vii) Tower Cranes

114 M/s Chintel India Pvt. Ltd.