GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, , .

CHAPTER 3- ENVIRONMENTAL COMPLIANCE STATUS

S.No. Environmental Clearance Conditions Environmental Compliance 1) “Consent for Establishment” shall be Consent to Establishments has obtained from Haryana State Pollution been obtained prior to Control Board under Air and Water Act construction. A copy of same is and a copy shall be submitted to the enclosed as Annexure-I SEIAA, Haryana before the start of any construction work at site. 2) A first aid room as proposed in the First Aid Room is being Provided project report shall be provided both at site for Laborers as well as at during construction and operation Hutments outside the project phase of the project. site. Please refer Chapter 2B for Photographs. 3) Adequate drinking water and sanitary Water as drinking for laborers is facilities should be provided for being provided by private water construction workers at the site. tankers. Waste water is being Provision should be made for mobile disposed using soak pits. Steel toilets. Open defecation by the labors is Scrap, Tin, Cement Bags are strictly prohibited. The safe disposal of being sold to local vendor. waste water and solid wastes generated during the construction phase should be ensured. 4) All the top soil excavated during All the topsoil excavated during construction activities should be stored construction phase has been for use in horticulture/landscape stored at isolated place and development within the project site. utilized in Backfilling. The Project proponent shall ensure that a) A temporary store room 5) the building material required during has been constructed for construction phase is properly stored storing the construction

M/s CHINTELS LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

within the project area and disposal of material. construction waste should not create b) Construction waste any adverse effect on the neighboring includes empty cement communities and should be disposed of bags; broken bricks, etc. after taking necessary precautions for are being segregated general safety and health aspects of properly by the labor on people, only in approved sites with the site. approval of competent authority. c) Construction waste are being sold to local vendors 6) Construction spoils, including a) No bituminous material bituminous material and other has been generated from hazardous materials, must not be construction projects. allowed to contaminate watercourses Small amount of and the dump sites for such material hazardous waste is being must be secured so that they should generated due to used Oil not leach into the ground water and any for DG sets and which is hazardous waste generated during stored in drums in construction phase, should be disposed earmarked locations. off as per applicable rules and norms b) It is being handled as per with necessary approval of the Haryana The Manufacture, Storage State Pollution Control Board. and Import of Hazardous Chemical Rules, 1989 and Material Safety Data Sheet. 7) The diesel generator sets to be used Agreed. DG sets are being during construction phase should be utilized in case of power failure. low sulphur diesel type and should Noise Abatement: DG sets are conform to Environment (Protection) enclosed with acoustic enclosure Rules prescribed for air and noise type emission standards. Fuel: Low Sulphur diesel will be

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

used in DG sets. 8) The diesel required for operating DG DG Sets are being used for sets shall be stored in underground backup purpose tanks and if required, clearance from The diesel required for the DG Chief Controller of Explosives shall be sets is being purchased on daily taken. basis. If Storage is required, permission from Explosive Department will be taken. 9) Ambient noise levels should conform to a) Incremental pollution loads residential standards both during day on the ambient air and and night. Incremental pollution loads noise quality are being on the ambient air and noise quality closely monitored and test should be closely monitored during reports are within the construction phase. Adequate measures permissible limits. should be taken to reduce ambient air b) Test Result is enclosed as and noise level during construction Annexure II. phase, so as to conform to the stipulated standards. 10) Fly ash should be used as building The fly ash mix cement and fly material in the construction as per the ash bricks will be used in the provisions of Fly Ash Notification of project as per the provisions of September, 1999 and amended as on Fly Ash Notification of 27th August, 2003. September, 1999 and amended as on 27th August, 2003. 11) Storm Water Control and its re-use as Strom Water control and its re- per CGWB and BIS Standards for use as per CGWB and BIS various applications should be ensured. standards are ensured. 12) Water demand during construction RMC is being used for preparing should be reduced by use of pre-mixed Ready mix Concrete which uses

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

concrete, curing agents and other best optimum water as required for practices. construction and water used for curing used to re-circulate again and again in order to reduce water usage. Curing agents like Aquamine 721, 427 will be used for fast curing of concrete and to reduce the water demand. 13) In view of the severe constrains in water Assurance of water supply has supply augmentation in the region and been submitted along with the sustainability of water resources, the proposal. STP water from developer will submit the NOC from Authority is being utilized in CGWA specifying water extraction construction activities. quantities and assurance from HUDA/ Dual Plumbing lines will be used utility provider indicating source of in order to prevent the water loss water supply and quantity of water with and to provide a solution for details of intended use of water- potable reuse of water in flushing and and non- potable. Assurance is required gardening. for both construction and operation stages separately. It shall be submitted to SEIAA and RO, MoEF, , before the start of construction. 14) Roof should meet prescriptive Agreed. While preparing the roof requirement as per Energy Conservation of the building during Building Code by using appropriate construction phase it will be kept thermal insulation material. in mind that prescriptive requirement as per Energy Conservation Building Code will be adopted and appropriate

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

thermal insulation materials will be used. 15) Opaque wall should meet prescriptive Opaque wall will be made as requirement as per Energy Conservation such to meet prescriptive Building Code which is proposed to be requirement of maximum U mandatory for all air conditioned spaces Factor and minimum R factor for while it is desirable for non-air- maximum insulation. conditioned spaces by use of appropriate thermal insulation material to fulfil requirement. 16) The approval of the competent authority a) To deal with any fire shall be obtained for structural safety of related accident, the building on account of earthquake, firefighting facility of single adequacy of firefighting equipment, etc. handed hydrant valve, long as per National Building Code including hose reel, and portable fire protection measures from lightening etc. extinguisher will be If any forestland is involved in the provided. proposed site, clearance under Forest b) The project falls under Conservation Act shall be taken from seismic active Zone IV the competent Authority. indicating high damage risk zone. The buildings will be designed as earthquake resistant and comply with the required IS specifications. Structural safety of the building due to earthquake, adequacy of firefighting equipment, etc.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

as per the National Building Code 2005 including protection measures from lightening etc. c) Certificate from Structural engineer will be submitted in next compliance report 17) Overexploited groundwater and We have already been submitted impending severe shortage of water the water efficiency/saving supply in the region requires the measure with water balance developer to redraw the water and diagram to SEIAA, Haryana. energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency/ saving measures as well as water reuse/ recycling within 3 months and before start of construction to the SEIAA, Haryana and RO, MoEF, GOI, Chandigarh. 18) The project proponent as stated in the a) Total of 21 rain water proposal shall construct 21 nos. rain harvesting pits is water harvesting pits for recharging the proposed. Construction of ground water within the project RWH pit will be started premises. Rain water harvesting pits soon. shall be designed to make provisions for b) Silting chamber will be silting chamber and removal of floating constructed for removal of matter before entering harvesting pit. floating matter before

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

Maintenance budget and persons entering harvesting pit. responsible for maintenance must be c) Persons will be hired for provided. Care shall also be taken care maintenance of rain water that contaminated water do not enter harvesting pits. any RWH pit. d) Provision will be made for contaminated water does not enter any RWH pit. 19) The project proponent shall provide for This will be followed. adequate Fire Safety measures and equipments as required by Haryana Service Act, 2009 and instruction issued by the local Authority/Directorate of fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/NOC from competent Authority as required. 20) The project proponent shall submit Temporary Power requirement is assurance from DHBVN for supply of being provided by DHBVN. 6414 KW of power supply before the Assurance from DHBVN start of construction. In no case project regarding assurance of power will be operational solely on generators supply during Operation phase without any power supply from any will be sent with forthcoming external power utility. compliance report. 21) Detail calculation of power load and This will be followed. The ultimate power load of the project shall Ultimate Power load will be be submitted to DHBVN under known after development/ intimation to SEIAA, Haryana before the construction of colony/ building start of construction. Provisions shall be as per the approved building

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

made for electrical infrastructure in the plans by the Director General, project area. Town and Country Planning, Chandigarh, Haryana. 22) The Project Proponent shall not raise There is no natural land any construction in the natural land depression/ Nallah/ water depression/ Nallah/ water course and course in the project site. Natural shall ensure that the natural flow from flow during rainy season will not the Nallah/ Water course is not be obstructed as weep holes will obstructed. be provided to avoid any such obstruction. 23) The project proponent shall keep the Plinth level of the building blocks plinth level of the building blocks will be made sufficiently above sufficiently above the level of the the level of the approach road. approach road to the project as per Level of the other areas will be prescribed by-laws. Levels of the other kept suitably above the approach areas in the projects shall also be kept road level. suitably so as to avoid flooding. 24) Construction shall be carried out so It will be followed. that density of population doesn’t exceed norms approved by Director General Town and Country Planning Department, Haryana. 25) The Project Proponent shall submit an No ground water is being utilized affidavit with the declaration that in construction phase. Affidavit ground water will not be used for regarding this will be submitted construction and only treated water with forthcoming compliance should be used for construction. report. 26) The Project Proponent shall not cut any No any tree was existing in existing tree and project landscaping project site.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

plan should be modified to include those trees in green area. 27) The Project Proponent shall provide 3 At present, the site is enclosed by meter high barricade around the project 3 m fencing. area, dust screen for every floor above Sprinkling of water is being done the ground, proper sprinkling and to suppress the fugitive dust covering of stored material to restrict dust and air pollution during construction. 28) The project proponent shall construct a It will be followed and rain water sedimentation basin in the lower level of harvesting will be done through the project site to trap pollutant and these. other wastes during rains. 29) The project proponent shall provide Mobile toilets at the site is being mobile sulabh toilets instead of soak pit provide at the site while in during construction phase for disposal hutment Soak Pit type of toilet is of sullage. being provided. 30) The project proponent shall ensure that This will be followed at the time the U- value of the glass is less than of glass work of the towers. 3.177 and maximum solar heat gain co- efficient is 0.25 for vertical fenestration. 31) The project proponent shall adequately STP water is being used to control construction dusts like silica suppress the dust from site. No dust, non-silica dust, wood dust. Such wood work will be carried out at dust shall not spread outside project the site. At project site proper premises. Project proponent shall respiratory protective equipment provide respiratory protective will be provided to all equipment to all construction workers. construction workers 32) The project proponent shall ensure The plinth level of Building

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

plinth level of the building block is 1.5 Blocks is above to flood level of meter above 100 years flood level of the the said Najafgarh Jheel said Najafgarh Jheel. 33) The project proponent shall obtain NOC The NOC from HUDA and from HUDA as well as Irrigation Irrigation department will be Department before the start of submitted with forthcoming construction, regarding possible adverse compliance report. effect of the project proposal on the said Najafgarh Jheel. 34) The project proponent shall develop All the amenities and facilities complete civic infrastructure of the will be provided as mentioned in Group Housing Colony including proposal and commitment made internal roads, green belt development, during presentation before sewerage line, Rain Water recharge SEIAA, Haryana. arrangements, Storm Water drainage system, Solid Waste Management Site and provision for treatment of bio- degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. And shall offer possession of the units/ flats thereafter. 35) The project proponent shall provide one Not Required as each flats have refuse area till 24 meter, one till 39 own balcony. meter and one after every 15 meter as per National Building Code. 36) The project proponent shall provide fire It will be followed. Provision for control room and fire officer for building separate fire control room will be above 30 meter as per National Building insured. Code.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

37) The project proponent shall obtain All the excavated soil has been permission of Mines and Geology stored in the campus only. Department for excavation of Soil before the start of construction. 38) The project proponent shall seek All the necessary approval from specific prior approval from concerned concerned local Authority/ local Authority/ HUDA regarding HUDA regarding provision of provision of Storm Drainage and Storm Drainage and sewerage sewerage system including their system including their integration with external services of integration with external services HUDA/ Local Authorities beside other of HUDA/ Local Authorities will required services before taking up any be taken. construction activity. 39) The site for solid waste management Solid waste will be collected by plant be earmarked on the layout plan using door to door network. and the detailed project for setting up Collection will be done in the the solid waste management plant shall campus and will be sent to the be submitted to the authority within municipal solid waste one month. management site. Biodegradable waste produced at site will be given to authorized recycler for vermicomposting. 40) The project proponent ensures that no It is ensured that no construction activity is undertaken construction activity will be either on surface or below or above undertaken either on or below or surface of revenue rasta passing above revenue rasta passing through the project area. through the project area. 41) The project proponent shall indicate the This will be followed. width and length of revenue rasta

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

stretch, for awareness of public, Sign boards shall also display the message that this is public rasta/road and any citizen can use it. There shall not be any gate with or without guards on revenue rasta. 42) The project proponent shall submit the Copy of fire safety plan has copy of fire safety plan duly approved by already been submitted to SEIIA, Fire Department before the start of Haryana. construction. 43) The project proponent shall provide This will be followed as the helipad facility as required under NBC maximum height of building will Norms and shall seek permission of be 95.50 meters. helipad from AAI accordingly 44) The project proponent shall not raise This is being followed. any construction activity in the ROW reserved/ acquired for High Tension Wire Passing through the project area and shall maintain horizontal and vertical ROW as required under Indian Electricity Rules, 1956/DHBVN latest instruction. 45) The project proponent shall provide rain However water logging at the site water pumping system in the project is rare but at some moment area to avoid water logging in the water may be logged mostly project area. during rainy season. At this moment water logging will be prevented by using water pumping system.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

OPERATION PHASE a) “Consent to Operate” shall be This will be followed after obtained from Haryana State completion of construction phase Pollution Control Board under Air and prior to Operation Phase of and Water Act and a copy shall be the project. submitted to SEIAA, Haryana. b) The Sewage Treatment Plant (STP) a) STP of capacity 790 KLD shall be installed for the treatment (450 KLD of STP in Phase-i of the sewage to the prescribed while 340 KLD of STP in standards including odor and Phase-II) will be installed treated effluent shall be recycled. at the site. Civil work of The installation of the STP should phase-I STP is being done. be certified by an independent b) Persons will be deputed for expert and a report in this regard handling and managing of shall be submitted to the SEIAA, STP. Haryana before the project is c) Treated effluent will be commissioned for operation. reused in flushing, Tertiary treatment of waste water is horticulture and mandatory. Tertiary treatment of recreational activities like waste water is mandatory. The sprinkling on road etc., project proponent shall remove not dual plumbing plan will be only ortho phosphorus but total adopted for the same. phosphorus to the extent of less d) All the parameters are than 2 mg/liter. Similarly total measure by HSPCB and Nitrogen level shall conform to the are under prescribed limit norms and standards of of CPCB CPCB/HSPCB, whichever is environmentally better, Project Proponent shall implement such

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

STP technology which does not require filter backwash. c) Separation of the grey and black Dual Plumbing line will be water should be done by the use of provided for the separation of the dual plumbing line. Treatment of grey and black water generated 100% grey water by decentralized from site. Dual Plumbing Plan treatment should be done ensuring Already has been submitted to that the re-circulated water should SEIAA, Haryana. Treated water have BOD less than 10 mg/ltr and from In-house STP will be the recycled water will be used for recirculated through dual flushing, gardening and DG set plumbing system to achieve zero cooling etc. achieve zero exit exit discharge. discharge. d) For disinfection of the treated This will be followed during wastewater ultra-violet radiation of installation of STP at site. ozonization process should be used. e) Diesel power generating sets Proposed Diesel Generator will be proposed as source of back-up used only in case of normal power for lifts, common area power Failure. illumination and for domestic use should be enclosed type and conform to rules made under the Environmental (Protection) Act, 1986. The location of the DG sets shall be in the basement as promised by the project proponent with appropriate stack height above the highest roof level of the project as per the CPCB norms. The diesel

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

used for DG sets shall be ultra-low Sulphur diesel ( 0.05 % sulphur), instead of low Sulphur diesel. g) The project proponent as stated in This will be followed. Greenbelt the proposal should maintain at will be developed as per plan least 32.86% green cover area for submitted to SEIAA and will be tree plantation especially all around 32.86 % of the total Plot Area. the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulate matter. The open spaces inside the plot should be preferably landscaped and covered with vegetation/grass, herbs and shrubs. Only locally available plant species shall be used. h) The project proponent shall strive to Agreed. Irrigation of landscape by minimize water in irrigation of minimizing grass area, using landscape by minimizing grass native variety, xeriscaping and area, using native variety, mulching utilizing efficient xeriscaping and mulching utilizing irrigation system will be used to efficient irrigation system, minimize the water demand. scheduling irrigation only after Irrigation will be scheduled only checking evapo- transpiration data. after checking evapo- transpiration data. i) Rainwater harvesting for roof run- a) Total 21 RWH pits will be off and surface run-off, as per plan constructed as per the plan

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

submitted should be implemented. submitted to SEIAA, Before recharging the surface run- Haryana. off, pre-treatment through b) Rainwater harvesting as sedimentation tanks must be done per plan for roof run-off to remove suspended matter, oil and surface run-off will be and grease. The bore well for implemented rainwater recharging shall be kept c) Suspended matter, oil and at least 5 mts. above the highest grease will be removed by ground water table. Care should be treatment before taken that the contaminated water recharging with surface does not enter any RWH pit. The run-off. project proponent shall avoid d) The bore well for recharge Rainwater Harvesting of first 10 will be kept at least 5 mts. minutes of rainfall. Roof top of the above the highest ground building shall be without any toxic water table. material or paint which can contaminate rain water. Wire mess and filters should be used wherever required. j) The ground water level and its This will be followed. quality should be monitored regularly in the consultation with Central Ground Water Authority. k) There should be no traffic Parking will be fully internalized. congestion near the entry and exit Entry and exit point will be bell points from the roads adjoining the shaped to minimize the traffic proposed project site. Parking congestion at the entry and exit should be fully internalized and no gate. public should be utilized.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA. l) A report on the energy conservation Report on Energy conservation measures conforming to energy measures and details about conservation norms finalize by building materials & technology; Bureau of Energy Efficiency should R & U factors etc. have been be prepared incorporating details submitted with proposal. about building materials & technology; R & U factors etc. and submit to the SEIAA in three month’s time. m Energy conservation measures like a) LEDs will be used wherever installation of LED for lighting the possible as a measure of areas outside the building should energy conservation. be integral part of the project design b) Use of T-5 and solar lighting and should be in place before in open spaces, common project commissioning. Use of solar area, and landscape area for panels must be adapted to the lighting outside the building maximum extent possible for energy will be the integral part of the conservation. project design. c) Used CFLs and TFLs will be properly collected and disposed of properly and will be sent to authorized dealers and recyclers so as to avoid mercury contamination. n) The project proponent shall use Agreed. We will encourage and zero ozone depleting potential aware resident to use zero ozone material in insulation, refrigeration, depleting potential material in air conditioning and adhesive. insulation, refrigeration, air Project proponent shall also provide conditioning and adhesive.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

Halcon free fire suspension system. 0) The solid waste generated should be This will be followed during properly collected and segregated as operation phase as: per the requirement of the MSW a) The solid waste will be Rules, 2000 and as amended from collected and segregated as time to time. The bio-degradable per the requirement of the waste should be treated by MSW Rules, 2000. appropriate technology at the site b) The bio-degradable waste earmarked within the project area will be composted by using and dry/inert solid waste should be organic waste converter at disposed off to the approved sites the site earmarked within for land filling after recovering the project area, and this recyclable material. will be implemented in the near future. c) Dry/inert solid waste will be disposed off to the approved sites for land filling after recovering recyclable material. p) The provision of solar water heating Each tower will be equipped with system shall be as per norms solar water heating system as per specified by HAREDA and shall be HAREDA norms. made operational in each building block. q) The traffic plan and the parking Traffic plan and Parking will be plan proposed by the project developed as per plan submitted proponent should be adhered to to SEIAA, Haryana. meticulously with further scope of additional parking for future

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

requirement. There should be no traffic congestion near the entry and exit points from the road adjoining the proposed project site. Parking should be fully internalized and no public space should be used. r) The project shall be operationalized This will be followed. only when HUDA/ public authority will provide domestic water supply system in the area. s) Operation and maintenance of STP, Agreed. Operation and solid waste management and maintenance of STP, solid waste Electrical Infrastructure, pollution management and Electrical control measures shall be ensured Infrastructure will be ensured for even after the completion of the lifetime as contract will be done Project. by various agencies and all these conditions will be mentioned in the MOU signed with RWA at the time of handing over the project t) Different types of Wastes should be a) Different type of solid disposed off as per the provisions of waste will be generated Municipal Solid Waste, biomedical and collected in colored waste, Hazardous waste, e- waste, bins (green, blue and dark batteries and plastic rules made grey) separate for bio- under Environment Protection Act, degradable and non- 1986. Particularly e-waste and biodegradable are proposed battery waste shall be disposed of to be provided at the as per existing E-waste strategic locations within

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

Management Rules 2011 and the site and will be done Batteries Management Rules 2001. according to solid waste The project proponent should management plan maintain a collection center for E- mentioned in Report. waste and it should be disposed of b) Biodegradable waste will to only registered and authorized be subjected to dismantler/ recycler. composting. The inert solid waste will be transported to a local Solid Waste dumping site. c) E-waste will be collected by the authorized recycler and MoU for the same will be done and submitted to the office. u) Standards for discharge of Air Pollution: Only source of Air Environmental pollutants as Pollution will be DG Set, stack enshrined in various schedules of height will be maintained 6m rule 3 of Environment Protection above the highest roof level for Rule 1986 shall be strictly complied better dispersion of Pollutant with. generated from DG sets. Noise Pollution: Only source of Noise Pollution will be DG Set, Enclosure and silencers will be provided on the DG Set to reduce the noise to impact the surroundings. Soil Pollution: Landscaping will be done properly with the start of

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

construction work to prevent soil pollution. Water Pollution: STP of capacity

550 KLD has been installed and treated effluent is reused in Horticulture and Flushing through Dual Plumbing Lines. v) Water Supply shall be metered to Separate meter will be provided different residential units and to the STP for measuring and different utilities. calculation of water demand. w) The project proponent shall ensure Stack Height of DG Sets will be that the stack height of DG Sets is maintained 6m above the height as per the CPCB guidelines and of the tallest building and as per also ensure that the emission CPCB norms standards of noise and air are within the CPCB prescribed limits. Noise and Emission level of DG Sets greater than 800 KVA shall be as per CPCB latest standards for high capacity DG Sets. x) All electric supply exceeding 100 It will be followed. amps, 3 phases shall maintain the power factor between 0.98 lag to 1 at the time of connection. y) The project proponent shall not use a) Treated water from STP fresh water for HVAC and DG will be reused in DG Set cooling. Air based HVAC system Cooling. should be adopted and only treated b) Coil type cooling DG Sets water shall be used by project shall be used for saving

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

proponent for cooling, if it is all cooling water consumption needed. . The project Proponent for water cooled DG Sets shall also use evaporative cooling c) It will be followed technology and double stage cooling system for HVAC in order to reduce water consumption. Further, temperature, relative humidity during summer and winter seasons should be kept in optimal level. Variable speed drive, best co- efficient of Performance, as well as optimal integrated point load value and minimum outside fresh air supply may be restored for conservation of power and water. Coil type cooling DG Sets shall be used for saving cooling water consumption for water cooled DG Sets. z. The project proponent shall ensure This will be followed at the time that the transformer is constructed of transformer installation. with high quality grain oriented, low loss silicon steel and virgin electrolyte grade copper. The project proponent shall obtain manufacturer’s certificate also for that. aa) The project Proponent shall that We ensure the better quality of exit velocity from the stack should drinking/domestic water to

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

be sufficiently high. Stack shall be resident as per prescribed designed in such a way that there is standard. no stack down-water under any meteorological condition. ab) The project proponent shall provide Water Sprinkling System will be water sprinkling system in the provided in lawn area and open project area to suppress the dust in area for the suppression of dust. addition to the already suggested mitigation measures in the Air Environment Chapter of EMP. PART-B. GENERAL CONDITIONS i) The project Proponent shall ensure Commitments made in Form-1, the commitments made in Form -1, Form- 1A, EIA/ EMP and other Form- 1A, EIA/ EMP and other documents submitted to SEIAA documents submitted to SEIAA for will be complied with. the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most environmentally friendly commitment on the point shall be taken by the project proponent. ii) Six monthly compliance reports Agreed. should be submitted to the HSPCB and Regional Office MoEF, GoI, Northern Region, Chandigarh and a copy to SEIAA Haryana.

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

iii) STP Outlet after stabilization and a) This monitoring schedule stack emission shall be monitored will be implemented in monthly. Other environmental EMP and all the audit parameters and green belt shall be findings will be monitored on quarterly basis. After incorporated without delay. every 3(three) month, the project b) The same will be added in proponent shall conduct MOU signed with RWA. environmental audit and shall take corrective measures, if required, without delay. iv) The SEIAA, Haryana reserves the Agreed. right to add additional safeguard measure subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/ MoEF. v) The project Proponent shall not It will be followed. violate any judicial orders/ pronouncements issued by any court/ tribunal. vi) All other statutory clearances such All the required and necessary as the approvals for storage of permission are under process diesel from Chief Controller of while some has obtained as

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

Explosives, Fire Department, Civil follows: Aviation Department, Forest A) AAI NOC is enclosed as Conservation Act, 1980 and Wildlife Annexure-III. (Protection) Act, 1972, PLPA, 1900, B) Forest NOC is enclosed as Forest Act, 1927 etc. shall be Annexure-IV. obtained, as applicable by project C) Fire Scheme NOC is enclosed proponents from the respective as Annexure-V. authorities prior to construction of the project. vii) The project Proponent should It will be followed and will be inform the public that the project submitted along with next has been accorded Environment compliance report. Clearance by the SEIAA and copies of the clearance letter are available with State Pollution Control Board and SEIAA. This should be advertised within 7 days from the date of issue of the Environment Clearance Letter at least in 2 local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s website for public awareness. viii) Under the Provision of Agreed. Construction has been Environmental (Protection) Act, started after obtaining

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

1986, legal action shall be initiated Environmental Clearance vide against the project proponent if it letter no. SEIAA/HR/2013/1079 was found that the construction of dated 23-10-2013 and consent project has been started before the to establish vide letter no.- obtaining prior environmental HSPCB/Consent/2821214GUN clearance. OCTE408046 dated 18/02/2014. ix) Any appeal against this Agreed. Environment Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of the National Green Tribunal Act, 2010. x) The project Proponent shall put in Corporate Environment Policy place Corporate Environment Policy will be Submitted to SEIAA in as mentioned in MoEF, GoI OM No. forthcoming compliance report. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issue of this letter. xi) The fund ear-marked for It will be followed. environmental protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

MoEF GoI under rules prescribed for Environment Audit. xi) The project proponent shall obtain Aravali NOC will be submitted NOC under Aravali Notification from with next compliance report. CEC of Hon’ble Supreme Court regarding coverage under Aravali Notification before start of construction. xii) The project Proponent shall ensure project is Group Housing Project the compliance of Forest only the Environmental Friendly Department, Haryana Notification and Ornamental Plant will be No. S.O.121/PA2/1900/S.4/97 planted at site under Greenbelt dated 28.11.1997. Development however point in notification will be complied. xiii) The project Proponent shall ensure It is ensured that only vehicle that no vehicle during with valid Pollution Under construction/operation phase enter Control certificate will be allowed the project premises without valid to the site. “Pollution Under Control” xiv) The Project Proponent is Agreed. responsible for compliance of all condition in Environment Clearance letter and project Proponent cannot absolve himself/herself of the responsibility by shifting it to any engaged by project proponent. xv) The Project Proponent shall seek Agreed. fresh Environment Clearance if any stage there is change in the

M/s CHINTELS INDIA LTD. GROUP HOUSING PROJECT AT SECTOR - 109, VILLAGE – Dec’14 BABUPUR, GURGAON, HARYANA.

planning of the proposed project. xvi) Besides the developers/ Applicant, Agreed. the responsibility to ensure the compliance of Environment safeguard/condition imposed in the Environmental Clearance letter shall also lie on the license in whose name/nemes the License/CLU has been granted by the Town & Country Planning Department, Haryana.

M/s CHINTELS INDIA LTD.