Global environmental fund “ Contaminated Site Management Project” demonstration project Public Disclosure Authorized

Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Public Disclosure Authorized

Public Disclosure Authorized

Shenyang Lvheng Environment Consulting Co. Ltd

April 2018

Public Disclosure Authorized

Project name: Global environmental fund “China Contaminated Site

Management Project” Liaoning demonstration project Environmental

and Social Impact Assessment Report for Remeidation of the Northeast

Pharmaceutical Plant contaminated siteName of outcome: Evaluation

report of environmental and social effects

Responsible unit: Lvheng Environment Counsulting Co. Ltd

Version: 20180619

Submitted to: Department of Environmental Protection of Liaoning

Province “China Contaminated Site Management Project”

Project-in-charge

Person-in-charge of project: Wang Chengbing Deputy General manager,

Senior Engineer

Main drafters: Shi Deyu, Senior engineer

Fan Huijiang, Senior engineer

Yuan Baocheng, Engineer

Fang Xiaoming, Engineer

Liu Zhongzhi, Engineer

A Lina, Engineer Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table of contents 1. Project overview ...... 1 1.1 Project background ...... 1 1.2 Aim of assessment ...... 2 1.3 Basis for evaluation ...... 3 1.3.1 Laws and regulations ...... 3 1.3.2 Evaluation Technical Guidelines and Specifications ...... 6 1.3.3 Relevant project documents and information ...... 6 1.4 Identification of Environmental Effects ...... 7 1.5 Evaluation grade and area ...... 8 1.5.1 Evaluation grade ...... 9 1.5.2 Evaluation scope ...... 10 1.6 Delineation of environmental functional regions and evaluation standards ...... 11 1.6.1 Environment quality standards ...... 11 1.6.2 Pollutant emission standards ...... 14 1.7 Evaluation period ...... 16 1.8 Evaluation focus and environmental protection goals ...... 16 1.8.1 Evaluation focus ...... 16 1.8.2 Environmental protection goals ...... 17 2. Investigation and evaluation of current status ...... 21 2.1 Environmental overview of contaminated site ...... 21 2.1.1 Geographical location ...... 21 2.1.2 Climatic conditions ...... 21 2.1.3 Geological and hydrogeological conditions ...... 22 2.1.4 Socioeconomic status ...... 25 2.2 Current status of the contaminated site and original pollution status ...... 26 2.2.1 Current status of contaminated site and surrounding conditions ...... 26 2.2.1.1 Current status of the contaminated site ...... 26 2.2.1.2 Current status of pollution sources at the surroundings of the

Shenyang Lvheng Environment Consulting Co. Ltd I#109-5 Level 17, Block H, Quanyun road, Hunnan , Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

contaminated site ...... 26 2.2.2 Overview of original factory site and emission status ...... 28 2.2.2.1 Overview of the factory site ...... 28 2.2.2.2 Manufacturing processes ...... 29 2.2.2.3 Discharge status of pollutants ...... 36 2.3 Future land use plans ...... 37 2.4 Schedule arrangement and work content ...... 39 2.5. Investigation and Evaluation of Environmental Quality Status ...... 42 2.5.1 In-situ Remediation Engineering ...... 42 2.5.1.1 Monitoring and Evaluation of Ambient Air Quality Status ...... 42 2.5.1.2 Investigation and Evaluation of Surface Water Environment Status...... 43 2.5.1.3 Investigation and Evaluation of Noise Environment Status ...... 43 2.5.1.4 Investigation and Evaluation of Soil Environment Status ...... 43 2.5.1.5 Evaluation of Groundwater Environmental Quality Status ...... 44 2.5.2 Ex-situ Remediation Project...... 44 2.5.2.1 Monitoring and Evaluation on Current Ambient Air Quality ...... 44 2.5.2.2 Investigation and Evaluation on Current Surface Water Environment ...... 48 2.5.2.3 Investigation and Evaluation on Current Acoustic Environmental Quality 48 2.5.2.4 Evaluation on Current Soil Environmental Quality ...... 49 3. Risk assessment and remediation goals of contaminated site ...... 55 3.1 Risk assessment of contaminated site ...... 55 3.1.1 Risk assessment of soil pollution status ...... 55 3.1.2 Risk Evaluation for Groundwater Pollution ...... 70 3.1.3 Human Health Risk Evaluation ...... 78 3.2 Content and Objectives of Polluted Site Remediation ...... 83 3.2.1 Objectives and Principles of Engineering Treatment ...... 84 3.2.3 Main Content of Polluted Site Remediation ...... 86 4. Technical Solution to Polluted Site Soil Remediation ...... 99 4.1 Technical Roadmap ...... 99 4.2 Implementation Scheme of In-situ Remediation Engineering ...... 100

Shenyang Lvheng Environment Consulting Co. Ltd II#109-5 Level 17, Block H, Quanyun road, , Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

4.2.1 Procedure of the Implementation Scheme ...... 100 4.2.2 Primary Pollution Sources and Environmental Impact Analysis ...... 110 4.2.2.1 Waste Gas ...... 110 4.2.2.2 Wastewater ...... 112 4.2.2.3 Noises ...... 113 4.2.2.4 Solid Wastes ...... 114 4.2.3 Pollution Control Measures ...... 115 4.2.3.1 Solutions and Measures for Air Pollution Control ...... 115 4.2.3.2 Solutions and Measures for Water Pollution Control ...... 116 4.2.3.3 Solutions and Measures for Noise Pollution Control ...... 118 4.2.3.4 Solutions and Measures for Solid Waste Pollution Control ...... 119 4.2.3.5 Solutions and Measures for Risk Prevention ...... 122 4.3 Implementation Scheme of Ex-situ Remediation Engineering ...... 129 4.3.1 Process of the Implementation Scheme ...... 129 4.3.2 Primary Pollution Sources and Environmental Impact Analysis ...... 132 4.3.2.1 Waste Gas ...... 132 4.3.2.2 Wastewater ...... 134 4.3.2.3 Noises ...... 136 4.3.2.4 Solid Wastes ...... 136 4.3.2.5 groundwater ...... 138 4.3.2.6 Environmental Impact Prediction for Decommissioning Period ...... 138 4.3.3 Pollution Control Measures ...... 139 4.3.3.1 Measures for Air Pollution Control ...... 139 4.3.3.2 Measures for Wastewater Pollution Control...... 140 4.3.3.3 Measures for Noise Pollution Control ...... 140 4.3.3.4 Measures for Solid Waste Pollution Control...... 140 4.3.3.5 Measures for groundwater Pollution Control...... 140 5. Social Environmental Impact Assessment and Analysis ...... 142 5.1 Social environmental impact identification ...... 142 5.2 Social environmental impact assessment factor ...... 142

Shenyang Lvheng Environment Consulting Co. Ltd III#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

5.3 Social Environmental Impact Analysis ...... 142 5.3.1 Impact of the Project on Traffic ...... 142 5.3.2 Impact of the Project on Public Health ...... 143 5.3.3 Impact of construction and vehicle transportation noise on residents' health 144 5.3.4 Prevention measures ...... 144 6. Public Participation ...... 147 6.1 Purpose and Principles of Public Participation ...... 147 6.1.1 Purpose of Public Participation ...... 147 6.1.2 Principles of Public Participation ...... 148 6.2 Scopes and Subjects of Public Participation ...... 149 6.3 Ways and Contents of Public Participation ...... 149 7. Environmental Investment and Environmental Benefits Analysis ...... 166 7.1 Overview ...... 166 7.2 Environmental protection investment estimates ...... 166 7.3 Analysis of Social and Economic Benefits ...... 167 8. Environmental Management and Monitoring Plan ...... 169 8.1 Environmental Management ...... 169 8.1.1 Necessity of Environmental Management ...... 169 8.1.2 Environmental Management Agency Setting ...... 169 8.2 Environmental Supervision ...... 175 8.2.1 Environmental Supervision ...... 175 8.2.2 Environmental Monitoring of the Transport Process ...... 182 8.2.3 Environmental Monitoring ...... 182 8.2.4 Treatment Process Environmental Supervision ...... 184 8.2.5 Environmental Supervision at Later Stage ...... 184 8.3 Monitoring Plan ...... 185 8.3.1 Environmental Monitoring Purpose...... 185 8.3.2 Environmental Monitoring Tasks...... 185 8.3.2.1in-suit Remediation Project ...... 185 8.3.2.2 Ex-suit Remediation Project ...... 187

Shenyang Lvheng Environment Consulting Co. Ltd IV#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

8.4 Environmental protection inspection and acceptance ...... 188 8.5 Implementation of Environmental Management Plan ...... 189 8.5.1 Assessment of Environmental Management Plan ...... 189 8.5.2 Information Management of Environmental Management Plan ...... 190 8.5.2.1 Information exchange ...... 190 8.5.2.2 Record Mechanism ...... 191 8.5.2.3 Reporting Mechanism ...... 191 8.5.3 Security System of Environmental Management Plan ...... 192 8.5.3.1 Relevant Rules and Regulations ...... 192 8.5.3.2 Fund Guarantee...... 193 8.5.3.4 Implementation Report of Environmental Management Plan ...... 194 8.6 Public consultation plan in the implementation stage ...... 195 8.6.1 Random Interviews ...... 195 8.6.2 Project Publicity ...... 196 8.6.3 Symposium ...... 196 8.6.4 Grievance Mechanism...... 196 9. Evaluation Conclusion ...... 198 9.1 Project Overview ...... 198 9.2 Industrial Policy Compliance ...... 199 9.3 Current Regional Environmental Quality ...... 199 9.3.1 Current Environmental Quality of the Area in in-suit Remediation Project .. 199 9.3.1.1 Current Atmospheric Environmental Quality...... 199 9.3.1.2 Current Surface Water Environmental Quality ...... 200 9.3.1.3 Current Noise Environmental Quality ...... 200 9.3.1.4 Current Soil Environmental Quality ...... 200 9.3.1.5 Current Groundwater Environmental Quality ...... 201 9.3.2 Current Environmental Quality in the Area of Ex-suit Remediation Project . 201 9.3.2.1 Current Atmospheric Environmental Quality...... 201 9.3.2.2 Current Surface Water Environmental Quality ...... 202 9.3.2.3 Current Noise Environmental Quality ...... 202

Shenyang Lvheng Environment Consulting Co. Ltd V#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

9.3.2.4 Current Soil Environmental Quality ...... 202 9.3.2.5 Current Groundwater Environmental Quality ...... 202 9.4 Environmental Impact Analysis ...... 203 9.4.1 In-situ Remediation Project Environmental Impact Analysis ...... 203 9.4.1.1 Atmospheric Environmental Impact Analysis ...... 203 9.4.1.2 Water Environment Impact Analysis ...... 204 9.4.1.3 Noise Environment Impact Analysis ...... 204 9.4.1.4 Environmental impact analysis of solid waste ...... 204 9.4.1.5 Groundwater Environment Impact Analysis ...... 205 9.4.2 Environmental Impact Analysis of ex-suit Remediation Project ...... 205 9.4.2.1 Atmospheric Environment Impact Analysis...... 205 9.4.2.2 Surface Water Environmental Impact Analysis ...... 205 9.4.2.3 Noise Environmental Impact Analysis ...... 206 9.4.2.4 Solid Waste Environmental Impact Analysis ...... 206 9.4.2.5 groundwater Environmental Impact Analysis ...... 207 9.4.2.6 Analysis of Environmental Impacts During the Decommission Phase .. 208 9.5 Pollution Prevention and Control Measures ...... 208 9.5.1 Pollution Prevention and Control Measures ofin-suit Remediation Project 208 9.5.1.1 Air Pollution Prevention and Control Measures ...... 208 9.5.1.2 Wastewater Pollution Prevention and Control Measures ...... 209 9.5.1.3 Noise Pollution Prevention and Control Measures ...... 209 9.5.1.4 Solid Waste Pollution Prevention and Control Measures ...... 209 9.5.1.5 Risk Prevention and Control Measures ...... 210 9.5.2 Ex-situ Remediation Project Pollution Prevention and Control Measures 210 9.5.2.1 Air Pollution Prevention and Control Measures ...... 210 9.5.2.2 Waste Water Pollution Prevention and Control Measures ...... 211 9.5.2.3 Noise Pollution Prevention and Control Measures ...... 211 9.5.2.4 Solid Waste Pollution Prevention and Control Measures ...... 211 9.5.2.5 groundwater Pollution Prevention and Control Measures ...... 211 9.5.2.6 Environmental risk Prevention and Control Measures ...... 212

Shenyang Lvheng Environment Consulting Co. Ltd VI#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

9.6 Public Participation ...... 213

9.7 Conclusions and Suggestions ...... 214

Shenyang Lvheng Environment Consulting Co. Ltd VII#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

List of tables Table 1.4-1 Identification of environmental impact factors ...... 7 Table 1.4-2 Evaluation factors ...... 8 Table 1.5-1 Evaluation grading table ...... 10 Table 1.6-1 Ambient air quality standards ...... 12 Table 1.6-2 Noise environment quality standards ...... 12 Table 1.6-3 Conventional indicators and limits for groundwater quality ...... 13 Table 1.6-4 Unconventional indicators and limits for groundwater quality ...... 13 Table 1.6-5 Regional soil indicator standards Unit ...... 14 Table 1.6-6 Emission standards of construction and stockyard dust ...... 14 Table 1.6-7 Integrated emission standard of air pollutants ...... 15 Table 1.6-8 Maximum permissible discharge concentration for water pollutants ...... 15 Table 1.6-9 Environmental noise emission standards for construction sites ...... 15 TTable 1.6-10 Leachate pollutant mass concentration limits ...... 16 Table 1.8-1 List of environmental protection goals ...... 18 Table 2.2-1 List of major (original) pollution sources at surrounding areas of the contaminated site ...... 27 Table 2.2-2 Discharge status of major pollutants in the original Northeast Pharmaceutical Factory northern factory site ...... 37 Table 2.4-1 Project schedule arrangement and work content ...... 40 Table 2.5-1 List of Analysis Methods ...... 42 Table2.5-2 Results of Air Monitoring and Evaluation ...... 43 Table 2.5-3 Results of Acoustic Environment Monitoring and Evaluation ...... 43 Table 2.5-4 List of Monitoring and Analysis Methods ...... 45

Table2.5-5 SO2 Monitoring and Evaluation Results ...... 46

Table2.5-6 NO2 Monitoring and Evaluation Results ...... 46 Table 2.5-7 TSP Monitoring and Evaluation Results ...... 47

Table 2.5-8 PM10 Monitoring and Evaluation Results ...... 47

Table 2.5-9 PM2.5 Monitoring and Evaluation Results ...... 47 Table 2.5-10 HCl Monitoring and Evaluation Results ...... 48

Shenyang Lvheng Environment Consulting Co. Ltd I#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 2.5-11 Monitoring Results of Acoustic Rnvironmental Quality (new Northeast Pharmacy factories) ...... 49 TTable 2.5-12 Monitoring Results of Current Soil Environmental Quality ...... 49 Table 2.5-13 Monitoring Results and Evaluation of Dioxin in Doil ...... 49 Table 2.5-14 Details of Groundwater Quality Monitoring Sites ...... 50 Table 2.5-15 List of Groundwater Quality Monitoring Methods ...... 51 Table 2.5-16 Monitoring Results of Groundwater Quality; Unit: mg/L (dimensionless pH)53 Table2.5-17 Statistical Evaluation of Monitoring Results Regarding Groundwater Quality ...... 54 Table 3.1-1 List of soil sample tests ...... 56 Table 3.1-2 Maximum value and standard values of soil test indicators of site ...... 57 Table 3.1-3 Groundwater Monitoring Results (First Groundwater Sampling) ...... 73 Table 3.1-4 Groundwater Monitoring Results (Second Groundwater Sampling) ...... 74 Table 3.1-5 Groundwater Monitoring Results (Third Groundwater Sampling) ...... 77 Table 3.1-6 Carcinogenic Risks and Non-carcinogenic Hazard Quotients of the Pollutants Concerned in Soils of Residential Lands (Concentration Unit: mg/kg) ...... 83 Table 3.2-1 Target Values of Soil Remediation ...... 85 Table 3.2-2 Data on Land Remediation by Stabilization ...... 87 Table 3.2-3 Data on Land Remediation by Chemical Oxidation ...... 88 Table 3.2-4 Data on Land Remediation by Thermal Desorption ...... 89 Table 3.2-6 Data on Land Remediation by Direct Excavation and Backfill ...... 92 Table 4.2-1 Technical Parameters of the Site Leveling and Compacting Equipment ...... 101 Table 4.2-2 Equipment Required for Soil Excavation ...... 103 Table 4.2-3 Data on Analogue Test of Construction Dust (Unit: μg/m3) ...... 110 Table 4.2-4 Generation and Discharge of Wastewater ...... 113 Table 4.2-5 Construction Equipment and Noise Source Intensity ...... 113 Table 4.2-6 Intensity Analysis of Main Noise Sources ...... 114 Table 4.2-6 Generation of Solid Wastes ...... 115 Table 4.3-1 Generation and Discharge of Exhaust Gas from Thermal Desorption ...... 134 Table 4.3-2 Generation and Discharge of Wastewater ...... 136

Shenyang Lvheng Environment Consulting Co. Ltd II#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 4.3-3 Generation and Emission of Noises During Soil Remediation ...... 136 Table 4.3-4 Generation of Solid Wastes ...... 137 Table 5.1-1 Social Environment Impact Identification ...... 142 Table 6.3-1 Public Opinion Survey Regarding the Northeast Pharmarcy POPs Site Contamination Project (On-site remediation) ...... 151 Table 6.3-2 Northeast Pharmarcy POPs Site Contamination Project (Ex-suit remediation) Public Opinion Survey Public Opinion Survey ...... 152 Table 6.3-3 Statistics Regarding the Participants in Public participation Survey ...... 153 Table 6.3-4 Opinion Statistics Regarding the Public Participation Survey ...... 153 Table 6.3-5 Northeast pharmaceutical factory POPs site contaminated sites project public opinion questionnaire ...... 158 Table 6.3-3 Statistics Regarding the Participants in Public participation Survey ...... 160 Table 6.3-7 Opinion Statistics Regarding the Public Participation Survey ...... 161 Table7.2-1 Environmental Protection Investment Estimates ...... 167 Table 8.2-1in-suit Remediation Project Environmental Supervision Key Points ...... 178 Table 8.2-2 Key Points of Offsite Remediation Project Environmental Supervision ...... 179 Table 8.2-3in-suit Remediation site environmental monitoring content list ...... 183 Table 8.2-4 Ex-suit Remediation Site Environmental Monitoring Content List ...... 184 Table 8.3-1 Contents ofin-suit Remediation Project Environmental Monitoring ...... 187 Table 8.3-2 Contents of Offsite Remediation Project Environmental Monitoring ...... 188 Table 8.4-1 Project Environmental Protection Facilities and "Three Simultaneous"

Inspection Schedule ...... 189

Shenyang Lvheng Environment Consulting Co. Ltd III#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site List of figures Figure 1.8-1 Location map of environmental protection target ...... 19

Figure 1.8 1.8-1 Location map of environmental protection target ...... 20

Figure 2.1-1 Engineering geological section of the site ...... 24

Figure 2.1-2 Engineering geological section of the site ...... 25

Figure 2.2-1 Current status map of the contaminated site ...... 26 Figure 2.2-2 Distribution map of major (original) pollution sources at surrounding areas of

the contaminated site ...... 28

Figure 2.2-3 Layout of the original site of the Northeast Pharmaceutical Factory...... 29 Figure 2.3-1 Schematic diagram of the demonstration land of the site (area bounded by red

lines is the area used for this remediation) ...... 39

Figure 3.1-1 Nickel soil distribution in site(>50mg/kg) ...... 63

Figure 3.1-2 Distribution of -hexachlorocyclohexane in the Site (> 0.2 mg/kg) ...... 64

Figure 3.1-3 Distribution of DDT (4,4’-DDT + 2,4’-DDT) in the Site (> 1.7mg/kg) ...... 65

Figure 3.1-4 Distribution of DDD in the Site (> 2mg/kg) ...... 65

Figure 3.1-5 Distribution of DDE in the Site (> 1.4 mg/kg) ...... 66

Figure 3.1-6 Distribution of BaP in the Site Soils (> 0.46 mg/kg) ...... 67

Figure 3.1-7 Distribution of Benzene in the Site Soils (> 0.64 mg/kg) ...... 68

Figure 3.1-8 Distribution of chloroform in the Site Soils (> 0.22 mg/kg) ...... 68

Figure 3.1-9 Distribution of Aniline in the Site Soils (> 5.8 mg/kg) ...... 69

Figure 3.1-10 Distribution of TPH (<16) in the Site Soils (> 230 mg/kg) ...... 70

Figure 3.1-11 Point Positions of Groundwater Sampling ...... 71

Figure 3.2-1 Excavation Scope of the Soils at the First Layer ...... 93

Figure 3.2-2 Excavation Scope of the Soils at the Second Layer ...... 94

Figure 3.2-3 Excavation Scope of the Soils at the Third Layer ...... 94

Figure 3.2-4 Excavation Scope of the Soils at the Fourth Layer ...... 95

Figure 3.2-5 Excavation Scope of the Soils at the Fifth Layer ...... 95

Figure 3.2-6 Excavation Scope of the Soils at the Sixth Layer ...... 96

Figure 3.2-7 Excavation Scope of the Soils at the Seventh Layer ...... 96

Figure 3.2-8 Excavation Scope of the Soils at the Eighth Layer ...... 97

Shenyang Lvheng Environment Consulting Co. Ltd IV#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 3.2-9 Excavation Scope of the Soils at the Ninth Layer ...... 97

Figure 3.2-10 Excavation Scope of the Soils at the Tenth Layer ...... 98

Figure 4.1-1 Technical Roadmap for Remediation and Treatment of Polluted Soils ...... 100

Figure 4.2-1 Diagram on Soil Excavation Process and Pollution Discharge Nodes ...... 101

Figure 4.2-2 Diagram on Different Temporary Storage Areas for Polluted Soils ...... 105

Figure 4.2-4 Curing stabilization integration device diagram ...... 107

Figure 4.2-4 Transport Route of Polluted Soils ...... 110

Figure 4.2-5 Mobile Spraying and De-dusting Machine ...... 115

Figure 4.2-6 Articles for Personal Safety Protection ...... 128 Figure 4.3-1 Technological Process of Chemical Oxidation and Pollution Discharge Nodes

...... 129 Figure 4.3-2 Technological Process of Thermal Desorption and Pollution Discharge Nodes

...... 129

Figure 6.3-1 An environmental impact assessment publicity site ...... 150

Figure 6.3-2 Forum site ...... 155

Figure 6.3-3 Secondary publicity site map ...... 156

Figure 6.3-4 newspaper publicity ...... 157

Figure 6.3-5 Forum site ...... 163 Figure 6.3-6 Report on Environmental Impact Assessment and Social Environmental Impact Assessment of POPs Contaminated Site Project in Northeast Pharmaceutical

Factory...... 164 Figure 8.1-1 Organizational Framework of Project Environmental Management

Organization ...... 170 Figure 8.2-1 Environmental Supervision Procedure of the Pollution Site Management

Project ...... 176

Shenyang Lvheng Environment Consulting Co. Ltd V#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

1. Project overview 1.1 Project background In September 2013, the Foreign Economic Cooperation Office of the Ministry of Environmental Protection and the World Bank cooperated to launch the “China Contaminated Site Management Project”. The aim of this project is to conduct environmental survey and initial risk assessment of potential persistent organic pollutant (POP) contaminated sites in China; selection of typical POP contaminated sites to carry out exploration of financing mechanisms for treatment of contaminated sites that is suitable for China; development of site risk management measures or management engineering demonstrations, drive and improve policies, regulations, and standard systems on prevention and treatment of contaminated sites in China; and improve China’s environmentally sound management capabilities. After approval by the People’s Government of Liaoning Province, the Department of Environmental Protection of Liaoning Province submitted an application for participation in provincial demonstration activities to the Foreign Economic Cooperation Office of the Ministry of Environmental Protection. This was endorsed by the World Bank and Foreign Economic Cooperation Office of the Ministry of Environmental Protection of Liaoning Province was selected as a model province for this project. The manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co Ltd which has a history of DDT manufacturing was included in POP contaminated site management engineering. The Northeast Pharmaceutical Group Co. Ltd was formerly the Northeast General Pharmaceutical Factory. The former Beier Road North Factory was located in 37 Chonggong North Street in Tiexi District in Shenyang City, has an area of 120,000 m2, and is mainly involved in pharmaceutical manufacturing. This factory started production in 1949 and stopped production in April 2015 to be shifted to the Shenyang Economic Technological Development Zone. In 2016, in accordance to municipal construction requirements by the Tiexi People’s Government, municipal roads with widths of 11m and 6m were constructed at the northern and western sides of the factory. Currently, the factory area is 114,000 m2. According to the overall land use regulations by the government, this site will be redeveloped and used for residential land (category 2 residential land). On 12 February 2017, China Resources Land Limited (Shenyang) successfully obtained this site through auctions. According to national and local

Shenyang Lvheng Environment Consulting Co. Ltd 1#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site relevant management requirements for contaminated sites, before land previously used for industrial purposes are redeveloped in commercial or residential land, environmental surveys and risk assessment on that land should be carried out to ensure the environmental safety when the land is reused, and confirm the treatment and remediation measures that are required for contaminated land. According to the “Northeast Pharmaceutical POP site (The manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd) detailed environmental survey and risk assessment report” and “Northeast Pharmaceuticals SOP site (The manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd))”, soil restoration of the Northeast Pharmaceuticals Factory POP contaminated site was carried out using in situ remediation and ex situ remediation. The remediation process will be completed in two factories; of which in situ remediation will be carried out at the original Northeast Pharmaceutical Factory North Factory Site (i.e. contaminated site) and ex situ remediation will be carried out at the New Factory Site of the Northeast Pharmaceuticals Factory. In January 2018, Shenyang Luheng Environment Consulting Co. Ltd successfully obtained the procurement bid for Global Environment Facility “China China Contaminated Site Management Project” (Liaoning demonstration project-Evaluation of environmental and social effects of the Northeast Pharmaceutical Factory POP pollution site) of the “China Contaminated Site Management Project” Project Management Office of the Department of Environmental Protection of Liaoning Province. The company is responsible for evaluation of environmental effects of the Northeast Pharmaceutical Factory POP contaminated site. After our company has been commissioned, we conducted a careful study of materials related to this project, and carried out field reconnaissance and on-site investigations, collection and verification of relevant materials. We carried out evaluation of environmental effects in this project according to relevant technical regulations and drafted and completed this report. 1.2 Aim of assessment According to the “Northeast Pharmaceutical POP site (Manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd) detailed environmental survey and risk assessment report” and “Northeast Pharmaceuticals SOP site (The manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd))”, soil

Shenyang Lvheng Environment Consulting Co. Ltd 2#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site restoration of the Northeast Pharmaceuticals Factory POP contaminated site was carried out using in situ remediation (within the original north factory of the Northeast Pharmaceutical Factory) and ex situ remediation (within the new factory of the Northeast Pharmaceutical Factory). The remediation process will have some effects on surrounding environment. This evaluation is mainly carried out by investigation, monitoring, and comparative analysis of the natural environment, social environment, and current status of environmental quality in the region in which the project is located at. This is done so as to predict the nodes, types, emission concentration, emission amount of pollutants produced during the implementation process of the project and the effects of various pollutants on the surrounding environment. This is combined with the current status of environmental quality and evaluation of the rationality of project implementation to propose specific solutions and measures to prevent and control pollution and mitigate adverse effects, so as to prevent secondary pollution as much as possible when conducting harmless treatment of the existing contaminated site, reducing adverse environmental effects to a minimum, and propose a scientific basis for approval and management of this project by the administrative department of environmental protection. 1.3 Basis for evaluation 1.3.1 Laws and regulations (1) (Comes into force in 1 January 2015); (2) (Comes into force in 1 June 2015); (3) (Comes into force in 1 September 2003); (4) (Comes into force in 1 January 2016); (5) (Comes into force in 1 June 2008); (6) (Comes into force in 1 March 1997); (7)

Shenyang Lvheng Environment Consulting Co. Ltd 3#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Pollution by Solid Waste> (Comes into force in 29 June 2013); (8) (Comes into force in 1 July 2012); (9) (Comes into force in 1 October 2002); (10) (Comes into force in 1 April 2008); (11) (Comes into force in 28 August 2004); (12) (Comes into force in 1 March 2011); (13) (Comes into force in 1 January 2009); (14) (Order of the State Council of the People's Republic of China (No. 253); (15) (No.39 [2005] of the State Council); (16) (No.38 [2000] of the State Council); (17) (No.31 [1996] of the State Council); (18) (Order No. 107 [1999] of the Ministry of Environmental Protection); (19) (Order No. 39 of the Ministry of Environmental Protection, comes into force in 1 September 2015); (20) (Order No. 60 [2003] of the General Office of the Ministry of Environmental Protection); (21)

Shenyang Lvheng Environment Consulting Co. Ltd 4#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(22) (approved on the Fourth Meeting of the Standing Committee of the Eighth People's Congress of Liaoning Provincial on September 27, 1993, revised on 30 July 2010); (23) ; (24) (Order No.8 [2016] of the Department of Environmental Protection of Liaoning Province); (25) (Order No. 29 [1999] of the People’s Government of Liaoning Province); (26) (Order No. 197 [2014] of the Ministry of Environmental Protection); (27) (Order No. 17 [2015] of the Ministry of Environmental Protection); (28) (Order No. 29 [1999] of the People’s Government of Liaoning Province); (29) (Order No. 255 of the People’s Government of Liaoning Province); (30) (Order No. 7 [2013] of the General Office of the State Council); (31) (Order No. 140 [2012] of the Ministry of Environmental Protection); (32) (Order No. 66 [2014] of the Ministry of Environmental Protection);

Shenyang Lvheng Environment Consulting Co. Ltd 5#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(33) (HJ2.1-2016); (2) (HJ2.2-2008); (3) (/T2.3-93); (4) (HJ610-2016); (5) (HJ2.4-2009); (6) (HJ 25.1-2014); (7) (HJ 25.2-2014); (8) (HJ 25.3-2014); (9) (HJ/T 166-2004); (10) (HJ/T164-2004); (11) (2014 No. 78 Circular). 1.3.3 Relevant project documents and information (1) Shenyang Academy of Environmental Sciences, Nov 2017; (2) Shenyang Academy of Environmental Sciences, Dec 2017; (3) World Bank OP4.01 Environmental Assessment (4)World Bank Group< Environment ,Health and Safety general Guidelines>;

Shenyang Lvheng Environment Consulting Co. Ltd 6#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(5)World Bank Group< Environmental, Health and Safety Guidelines for Waste Management Facilities>. 1.4 Identification of Environmental Effects Identification of various environmental effects was carried out according to the characteristics of this project (Table 1.4-1). Table 1Table 1.4-1 Identification of environmental impact factors Engineering Content Nature of impact Soil dredging Soil remediation Soil transport Impact factors Regional Socioeconomic economy impact Population health △ △ Natural Water resources △ resources Soil resources ▲ Atmospheric ▲ ▲ ▲ quality Noise ▲ ▲ ▲ Natural Surface water environment Groundwater △ △ Soil ▲ Vegetation, green ▲ spaces

Note:▲Significant impact △General impact.

See Table 1.4-2 for the evaluation factors for this project

Shenyang Lvheng Environment Consulting Co. Ltd 7#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 2Table 1.4-2 Evaluation factors Evaluation factors for current status Evaluation factors for impact In situ Ex situ Test items Ex situ remediation In situ remediation project remediation remediation project project project Atmospheri c PM10, PM2.5, TSP, SO2, TSP, HCl, PM10, SO2, NO2 TSP environmen NO2, HCl, TVOC TVOC t pH, Ammonia nitrogen, Nitrite nitrogen, Iodide, Total Cyanide, Fluoride, Nitrate nitrogen, Chromaticity, Turbidity, Chloride, Sulfate, Total dissolved solids, pH, Total Hardness, Total hardness, Permanganate Total dissolved solids, index, Volatile phenols, Anionic Permanganate index, surfactants, Hexavalent Sulfate, Chloride, chromium, Arsenic, Cadmium, Groundwat Fluoride, Cyanide, Lead Lead, Mercury, Selenium, er Nitrate nitrogen, Iron, Manganese, Copper, Zinc, - - environmen Ammonia nitrogen, Barium, Beryllium, Molybdenum, t Iron, Copper, Zinc, Nickel, Cobalt, Lead, Mercury, Hexachlorocyclohexane, DDT, Hexavalent Chromium, Benzene, Chlorobenzene, Cadmium, Volatile 1,3-Dichlorobenzene, phenols 1,4-Dichlorobenzene, 1,2-Dichlorobenzene, 1,2,4-Trichlorobenzene, 1,2,3-Trichlorobenzene, Naphthalene, 1,2-Dichloroethane Arsenic, Cadmium, Chromium, Copper, Lead, Nickel, Zinc, Mercury, Petroleum hydrocarbonsC16 , Naphthalene, Fluorene, Phenanthrene, Anthracene, Fluoranthene, Pyrene, Benz[a]anthracene, Chrysene, Benzo[b]fluoranthene, pH, Mercury, Arsenic, Benzo[k]fluoranthene, Cadmium, Copper, Soil Benzo[a]pyrene, - - Lead, Chromium, Zinc, Indeno[1,2,3-cd]pyrene , Nickel Dibenz[a,h]anthracene, Benzo[ghi]perylene, alpha-Hexachlorocyclohexane, beta-Hexachlorocyclohexane, gamma-Hexachlorocyclohexane, delta-Hexachlorocyclohexane, Total hexachlorocyclohexane, Total PCPs, 1,3,5-Trichlorobenzene Noise Equivalent Continuous Sound Equivalent Continuous environmen - - Level A Sound Level A t Solid Waste — - - - 1.5 Evaluation grade and area

Shenyang Lvheng Environment Consulting Co. Ltd 8#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

1.5.1 Evaluation grade (1) Determination of evaluation grade for atmospheric environment According to regulations in the (HJ2.4-2008), the major atmospheric environmental problems in this project is dust produced from soil dredging, soil remediation, and soil transport at the contaminated site, dust from construction and transportation vehicles, and VOCs, SVOCs, dust, HCl, and 1-4 dioxin produced during ex situ soil remediation. The evaluation grade for atmospheric environment is grade 3. (2) Determination of evaluation grade for noise According to delineation of applicable zones for Shenyang environment noise standards, the contaminated site (original Northeast Pharmaceutical Factory North Factory) should implement (GB3096-2008) categories 2 and 4a. Category 3 standards of the “Emission standard for industrial enterprises noise at boundary” were implemented for environment noise for the boundary of the remediation site (Northeast Pharmaceutical Factory New Factory). As the maximum increase in noise is lower than 3dB (A) after this project is operational, changes in the affected population are not large. According to the (HJ2.4-2009), this evaluation confirms that the grade of noise environment impact assessment is Grade 2. (3) Determination of evaluation grade for surface water In situ remediation project and ex situ remediation project were both less than process wastewater discharge. Of these projects, the wastewater produced during in situ remediation of the contaminated site is mainly water used to wash the tires of transportation vehicles and domestic wastewater of construction workers. Wastewater from cleaning of vehicles was fully reused while domestic wastewater was treated at the Xiannuhe wastewater treatment plant after passing through the municipal wastewater network. The wastewater generated during ex situ remediation was mainly domestic wastewater from staff, caustic wash tower effluent, and quench tower effluent. These wastewater all achieved standards after treatment at the integrated wastewater treatment plant in Northeast Pharmaceutical Factory New factory before being discharged through the municipal wastewater network into Shenyang Western Wastewater

Shenyang Lvheng Environment Consulting Co. Ltd 9#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Treatment Plant Expansion Project for concentration and treatment. As the effluent does not directly enter the surface water body, therefore surface water evaluation of this project was omitted. (4) Determination of evaluation grade for groundwater environment According to Annex A of the (HJ610-2016), the project was determined to be category III. As the sensitivity of the groundwater environment in the project site is not sensitive, therefore this evaluation determined that the groundwater environment impact evaluation work is Grade 3. Table 3Table 1.5-1 Evaluation grading table Evaluation Basis Evaluation grade Content According to regulations in the (HJ2.4-2008), the major atmospheric pollution factors in this project is dust produced Atmospheric from soil dredging, soil remediation, and soil transport, TSP, TCH, Grade 3 environment CO, NOx produced from transportation vehicles, and VOCs, SVOCs, dust, HCl, and 1-4 dioxin produced from situ soil remediation. As the amount of pollutants emitted is low, the evaluation grade for atmospheric environment is Grade 3 The contaminated site (original Northeast Pharmaceutical Factory North Factory) should implement (GB3096-2008) categories 2 and 4a. Category 3 standards of the “Emission standard for industrial enterprises noise at boundary” were implemented for environment noise for the Noise boundary of the remediation site (Northeast Pharmaceutical Factory Grade 2 environment New Factory). As the maximum increase in noise is lower than 3dB (A), changes in the affected population are not large. According to the (HJ2.4-2009), this evaluation confirms that the grade of noise environment impact assessment is Grade 2.

This is a category III project. As the sensitivity of the groundwater Groundwater environment in the project site is not sensitive, therefore the grade of Grade 3 groundwater environment impact evaluation work is Grade 3.

1.5.2 Evaluation scope (1) Determination of evaluation area for atmospheric environment According to requirements in

Shenyang Lvheng Environment Consulting Co. Ltd 10#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Assessment-Atmospheric Environment> (HJ2.4-2009) and in combination with the atmospheric environmental impact assessment grade of 3, the evaluation scope for ambient air impact is an area of 2.5km around the factory boundary. (2) Determination of evaluation area for noise An area of 300m outside the project boundary and environmental sensitive spots such as residential clusters are key evaluation regions. (3) Determination of evaluation area for groundwater environment An area of 5km2 around the project. 1.6 Delineation of environmental functional regions and evaluation standards 1.6.1 Environment quality standards (1) Ambient air

According to the delineation of ambient air quality functional zones in Shenyang City, the ambient air of the evaluation region is category 2. Grade 2 standards of the (GB3095-2012) were implemented for PM10, PM2.5, TSP, SO2, and NO2. The maximum permissible concentration limit of harmful substances in ambient air in residential areas in (TJ36-79) were used as a reference for execution of the primary value of the characteristic pollutant HCl. Annual mean concentration values of the Japan ambient air quality standards (July 2002 Circular No. 46 of the Ministry of Environment) was used as reference for 1-4 dioxin. See Table 1.6-1 for standard values.

Shenyang Lvheng Environment Consulting Co. Ltd 11#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 4Table 1.6-1 Ambient air quality standards Unit: μg/m3 Primary 8-Hour 24-Hour 1-Hour Annual Execution Pollutant concentra average average average mean standards tions Sulfur dioxide 150 500 / / / (SO2) Nitrogen dioxide 80 200 / / / Grade 2 standards (NO2) of (GB3095-2012) PM10 150 / / / / TSP 300 / / / /

PM2.5 75 / / / / (TJ36-79) TVOC / / / 600 / (GB/T18883-200 2) Japan Environmental Quality Standards 0.6pgTE 1-4 Dioxin (July 2002 Q/Nm3 Circular No. 46 of the Ministry of Environment) (2) Noise Environment

According to the delineation of noise functional zones in Shenyang, the north of the in situ remediation site is bordered by Xiaobei 1st West Road, the south is bordered by the Beier West Road and (GB3096-2008) category 4a standards were implemented for environmental noise evaluation in the north and south. (GB3096-2008) category 2a standards were implemented for the east and west sides. (GB3096-2008) category 2a standards were implemented for all four sides at the ex situ remediation site. Table 1.6-2 shows the noise environment quality execution standards. Table 5Table 1.6-2 Noise environment quality standards Unit: dB(A) Type of noise functional zone Daytime Nighttime Category 2 60 50 Category 4a 70 55 (3) Water Environment

Shenyang Lvheng Environment Consulting Co. Ltd 12#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

According to the the , Conventional indicators and limit category 3 water standards in the (GB/T14848-2017) were implemented for various conventional indicators of groundwater while unconventional indicators and limit category 3 water standards in the (GB/T14848-2017) were implemented for beryllium, cobalt, ethylbenzene, DDT, chlorobenzene, 1,4-dichlorobenzene, 1,2-dichloroethylene and 1,2-dichloroethane. Tables 1.6-3 and 1.6-4 shows the groundwater quality standards Table 6Table 1.6-3 Conventional indicators and limits for groundwater qualityUnit: mg/L S/N Test items Category III S/N Test items Category III 1 Ammonia nitrogen ≤0.5 16 Arsenic (As) ≤0.01 2 Nitrites ≤1.0 17 Cadmium (Cd) ≤0.005 3 Iodides ≤0.08 18 Lead (Pb) ≤0.01 4 Cyanides ≤0.05 19 Mercury (Hg) ≤0.001 5 Fluorides ≤1.0 20 Selenium (Se) ≤0.01 6 Nitrates ≤20.0 21 Iron (Fe) ≤0.3 7 Chromaticity (degree) ≤15 22 Manganese (Mn) ≤0.10 8 Turbidity (NTU) ≤3.0 23 Copper (Cu) ≤1.0 9 pH 6.5≤pH≤8.5 24 Zinc (Zn) ≤1.0 10 Chlorides ≤250 25 Molybdenum ≤0.07 1 Sulfates ≤250 26 Benzene (μg/L) ≤10 12 Total dissolved solids ≤1000 27 Toulene (μg/L) ≤700 28 Trichloromethane 13 Total hardness ≤450 ≤60 (μg/L) 14 Permanganate index ≤3.0 29 Volatile phenols ≤0.002 Hexavalent 15 Anionic surfactants ≤0.3 30 ≤0.05 chromium Table 7Table 1.6-4 Unconventional indicators and limits for groundwater qualityUnit: mL/L S/N Test items Category III S/N Test items Category III 1 Beryllium ≤0.002 5 Chlorobenzene ≤300 2 Cobalt ≤0.05 6 1,4-dichlorobenzene ≤300 3 Ethylbenzene ≤300 7 1,2-dichloroethylene ≤50.0 4 DDT ≤1.0 8 1,2-dichloroethane ≤30.0 (4) soil Environment

In consideration that the site will be used for residential land in the future, soil standards were referenced from A values in the < Standard of Soil Quality Assessment for Exhibition Sites (Interim)> (HJ 350-2007) and residential land standards in Beijing local standards < Screening Levels for Soil Environmental Risk Assessment of Sites>. Table 1.6-5 shows the regional soil

Shenyang Lvheng Environment Consulting Co. Ltd 13#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site indicator standards Table 8Table 1.6-5 Regional soil indicator standards Unit: mg/kg Standa Source of Standard Source of S/N Indicator rd standard S/N Indicator value standard value* value value* HJ350 A 1 Arsenic 20 1 Chloroform 2 HJ350 A value value HJ350 A 2 Benzene 0.2 12 Aniline 5.8 HJ350 A value value HJ350 A Benz[a]anthrace 3 Chromium 190 13 0.9 HJ350 A value value ne HJ350 A Benzo[b]fluorant 4 Copper 63 14 0.9 HJ350 A value value hene HJ350 A 5 Lead 140 15 Benzo[a]pyrene 0.3 HJ350 A value value HJ350 A Indeno[1,2,3-cd] 6 Nickel 50 16 0.9 HJ350 A value value pyrene HJ350 A 1,2:5,6-Dibenzan 7 Zinc 200 17 0.33 HJ350 A value value thracene HJ350 A DB11/T 811 8 Mercury 1.5 18 DDT 1 value Residential land Petroleum DB11/T 811 DB11/T 811 9 hydrocarbon 230 Residential 19 DDD 2 Residential land s A value; DB11/T 811:Beijing local standards residential land screening values. 1.6.2 Pollutant emission standards (1) Atmospheric pollutant emission standards (DB21/3642-2016) urban built-up area concentration limits were implemented for discharge of dust in in situ remediation and (DB21/3642-2016) rural or suburban concentration limits were implemented for ex situ remediation (Table 1.6-6).

Table 9Table 1.6-6 Emission standards of construction and stockyard dust Concentration limit (mean concentration Name of pollutant Region for continuous 5 minutes) Urban built-up areas 0.8 TSP Rural or suburban area 1.0

Shenyang Lvheng Environment Consulting Co. Ltd 14#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 2: newly constructed enterprise exhaust pipe pollutant discharge limit (80mg/m3,8.3kg/h) requirement was used as a reference for VOC gaseous emissions in the ex situ remediation site. Consultation Paper was used as a reference for execution of 1-4 Dioxin emissions (0.1ngTEQ/m3); Table 2 standards in the (GB16297-1996) were used for execution of hydrogen chloride and particulate matter emissions. See Table 1.6-7. Table 10Table 1.6-7 Integrated emission standard of air pollutants Maximum permissible emission Name of pollutant Emission rate (kg/h) concentration (mg/m3) Particulate matter 150 4.1(15m) Hydrogen chloride 150 0.3(15m) (2) Wastewater discharge standards Table 2 standard requirements in the (DB21/1627-2008) were implemented for SS, COD, and ammonia nitrogen in discharged water in this project (Details are shown in Table 1.6-8).

Table 11Table 1.6-8 Maximum permissible discharge concentration for water pollutants Unit: mg/L Item SS COD Ammonia nitrogen Table 2 standard requirements in the (DB21/1627-2008) (3) Noise emission standards The engineering content in situ remediation mainly consists of soil dredging and remediation, which is similar to the construction period of general construction projects. Therefore, this project executes (GB12523-2011) for noise in this project while category 3 standards in (GB12348-2008) were implemented for the ex situ remediation site. See Table 1.6-9.

Table 12Table 1.6-9 Environmental noise emission standards for construction sites Unit: dB Noise emission standards Daytime Nighttime (GB12523-2011) 65 55 (GB12348-2008) (4) Solid waste discharge standards

Shenyang Lvheng Environment Consulting Co. Ltd 15#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site (GB18599-2001) was implemented for discharge of domestic garbage. National (GB18598-2001) was implemented for landfilling hazardous wastes. National (GB18597-2001) (revised in 2013) was implemented for storage of hazardous wastes.

Pertinent requirements in < Standard for Pollution Control on the Landfill Site of Municipal Solid Waste> were used for implementation of domestic garbage landfilling after soil has undergone remediation. See Table 1.6-10 for leachate pollutant mass concentration limits. Table 13Table 1.6-10 Leachate pollutant mass concentration limits S/N Pollutant Mass concentration limit (mg/L) 1 Mercury 0.05 2 Copper 40 3 Zinc 100 4 Lead 0.25 5 Cadmium 0.15 6 Beryllium 0.02 7 Barium 25 8 Nickel 0.5 9 Arsenic 0.3 10 Total chromium 4.5 1 Hexavalent chromium 1.5 12 Selenium 0.1 1.7 Evaluation period Currently, this project has not started. Situ remediation in this project will be carried out using in situ remediation (solidification/stabilization) and ex situ remediation (chemical oxidation, thermal desorption). This environmental evaluation is mainly targeted at the soil dredging and soil remediation stages. 1.8 Evaluation focus and environmental protection goals 1.8.1 Evaluation focus According to the environmental characteristics of the evaluated region and characteristics of this demonstration project, the focus of this evaluation is confirmed to be the following: (1) Carrying out engineering analysis of the treatment and remediation work in the contaminated site, identification of major environmental impact, confirmation of major pollution processes and its main pollution factors, and prediction of the emission load of major pollutants; (2) Formulation of practical and feasible atmospheric, noise, solid waste, and soil pollution

Shenyang Lvheng Environment Consulting Co. Ltd 16#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site prevention and control measures. 1.8.2 Environmental protection goals See Table 1.8-1 and Figures 1.8-1 and 1.8-1-1 for the general status of various environmental protection goals and positional relationship with the selected sites in this project.

Shenyang Lvheng Environment Consulting Co. Ltd 17#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 14Table 1.8-1 List of environmental protection goals Nearest Environmental distance Number of factors Serial Environmental to Direction households/population Protection number sensitive spots boundary size category (m) Tiexi District 1 Government 10 W Around 1000 people Wanke 2 Langrun Park 20 E 1360/4100 Chonggong 3 New Village 37 N 2000/4000 Lanting 4 Xingju 47 NE 2100/4100 Holiday 5 Provence 256 W 8000/16000 Baolixinyu 6 Garden 708 SW 3000/9000 Kairong 7 International 338 SW 5000/10000 Garden 8 Meihao 457 S 6000/12000 Yuanjing Grade 2 Ambient air 9 Fangda 713 SE 5400/15000 standards of Shengjing (GB3095-2012) Shenyang 11 Hexin Jiayuan 1095 NE 7000/20000 Chengse 12 Shiguang 2144 NE 5400/15000 13 Qiancao Luge 973 E 2000/4000 Dingxiang 14 Hupan New 1134 NW 15000/20000 City 15 Jindimingjing 2363 E 8000/20000 Qianma 16 village 930 E 300/1024 Sanmangniu 17 (in the middle 1460 N 180/544 of relocating) Yuejiacun (in 18 the middle of 1510 W 500/1510 demolition) Tiexi District 1 Government 10 W Around 1000 people Grade 2 standards of 2 Wanke 20 E 1360/4100 Noise Langrun Park (GB3096-2008) environment 4 Xingju 47 NE 2100/4100 Grade IV standards of (GB3838-2002) Surface water 1 Weigong 1390 E — Category III water standards Groundwater Groundwater in (GB/T14848-93)

Shenyang Lvheng Environment Consulting Co. Ltd 18#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 1Figure 1.8-1 Location map of environmental protection target (in situ remediation site)

Shenyang Lvheng Environment Consulting Co. Ltd 19#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 2Figure 1.8 1.8-1 Location map of environmental protection target (ex situ remediation site)

Shenyang Lvheng Environment Consulting Co. Ltd 20#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

2. Investigation and evaluation of current status 2.1 Environmental overview of contaminated site 2.1.1 Geographical location The original Northeast Pharmaceutical Beier Road North Factory Manufacturing Zone is located at the intersection between the Chonggong North Street and Beier Road in Tiexi District, Shenyang City and has a total area of 114,000 m2. The management engineering of this contaminated site covers the entire factory, which has coordinates of N41°49'10.32” and E123°19'53.40". The east of the factory is the Wanke Langrun Park, the south of the site is the Beier West Road, the west of the site is the Tiexi District Administrative Center, and the north of the site is the Xiaobei 1st West Road. See Supplementary Figure 1 for the geographical location. 2.1.2 Climatic conditions The project is located at western Shenyang city. This region is located at the mid-latitudes and belongs to the northern temperate monsoon sub-humid continental climate with distinct four seasons. The main climate characteristic is dry and cold winters, with mean temperatures of -8.7℃. January is the coldest month with mean temperatures of -11.3℃ and the lowest temperature is -34℃. Summers are hot and rainy, with mean temperatures of 23.3℃. July is the hottest month with mean temperatures of 24.6℃ and the highest temperature is 36℃. The average number of hot days with daily highest temperatures above 30℃ is 30 days. The annual mean temperature is 8.1℃. During the heating period, the mean temperature is -5.2℃, of which the mean temperature in January is the lowest (-11.3℃). During the non-heating period, the mean temperature is 17.7℃, of which the mean temperature in July is the highest (24.1℃). The annual precipitation is 680.4mm, which is mostly concentrated in July and August and mean precipitation in July is the greatest (168.4mm). During the heating period, the mean monthly precipitation is gradually decreased and January has the lowest precipitation (7.0 mm). The annual mean air pressure is 1011.2hPa. The mean air pressure during the heating period is 1019.1 hPa, of which the highest mean temperature is in January at 1021.2 hPa. The mean air pressure during the non-heating period is 1005.5, of which the highest mean temperature is in July at 998.9 hPa. The annual mean relative humidity is 63.0%. The mean relative humidity is lower during the heating period (57.8%), of which March and April has the lowest values (52.0%). The mean

Shenyang Lvheng Environment Consulting Co. Ltd 21#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site relative humidity is higher during the non-heating period (66.6%), of which July and August has the highest values (78.0%). The prevailing wind direction throughout the year is the South wind with a frequency of 12.0% and the secondary wind direction is the South-southwest wind with a frequency of 11.0%. The prevailing wind during the heating period is the North Wind with a frequency of 13.0% and the secondary prevailing wind is the South wind with a frequency of 10.0%. During the non-heating period, the prevailing wind is the South wind with a frequency of 14.4% and the secondary wind direction is the South-southwest wind with a frequency of 12.9%. The annual mean wind speed is 3.30 m/s, and the mean wind speed during the heating and non-heating periods are 3.28m/s and 3.27m/s, respectively. April has the highest mean wind speed (4.40m/s) while August has the lowest mean wind speed (2.60m/s). 2.1.3 Geological and hydrogeological conditions The project is located at the north of the Hun River alluvial plain and belongs to the proximal frontal side of the new alluvial plain. The terrain is flat and open, and topography is uniform. The mean altitude is 43 m. The overall trend of terrain changes is high on the north and low on the south, high on the east and low on the west, with a slight incline from the northeast to the southwest. The area around the factor belongs to the Quaternary alluvium layer of the Hun River alluvial plain and strata composition is more uniform. The geomorphology of the north from the Heping village to the Lanshengtai village is a first-stage terrace while the south is the floodplain of the Hun River. Fine sand formed from weathering in some areas and the Desheng region is directly exposed to form sand dunes. The region where the site is located belongs to the eastern extension of the Yinshan east-west complex structural belt, and is a part of the intersection between the 2nd primary uplift belt and 2nd primary subsidence belt in the Neocathaysian system. Some regions on the primary terrace consist of 15-20m thick yellow sub-clay layer, of which a 10m thick yellow fine sandy layer is located directly below. In the middle, there is a 23 m thick yellow sub-clay layer, followed by a greyish-yellow gravel-clay layer with a thickness of 30-40m. The lowest layer is a sand-containing layer that is in a semi-cemented state. The surface of the floodplain region consists of yellow and yellowish-brown sub-clay and greyish and greyish-brown clay and has a

Shenyang Lvheng Environment Consulting Co. Ltd 22#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site thickness of 3-5m. This is followed by a bottom layer of brown and brownish-yellow gritstone and sand-gravel layer with an average thickness of 22-23m. The middle consists of greyish-yellow gritstone. The main aquifer of the first-stage terrace region is a medium sand layer of yellow gravel-clay with a thickness of 30-40m. On top of this layer lies an approximately 20m thick yellow sub-clay layer with a water permeability coefficient of 50-80 m/d. The groundwater belongs to Quaternary pore water and shallow confined water. The groundwater is buried at a depth of 4-8m and is mainly replenished by atmospheric precipitation and surrounding groundwater runoff. The floodplains of the South Hun River contain 2 aquifers. The first aquifer is a layer of brown gritstone and sand-gravel layer with a thickness of 20m and a water permeability coefficient of 66-137m/d. The groundwater is located at a depth of 1.5-3m and is replenished by leakage from rice fields followed by atmospheric precipitation and underground runoff. The pH of the groundwater is greater than 6.5 and erosive CO2 is lower than 15 mg/L, which does not erode concrete. The direction of groundwater flow is generally from east to southwest on the first-stage terrace and the hydraulic gradient is 0.0009-0.0013. On the floodplain, groundwater flows from east to southwest and the hydraulic gradient is 0.0006-0.0009. The terrain type of the site is an alluvial plain on the Hun River, with a flat terrain. The surface elevation is between 49.56 to 50.46m. According to deep-drilling results, the foundation soil of the site is composed of miscellaneous fill and cohesive soil. Small amounts of groundwater are found in the first layer of silty clay at this site. The groundwater type belongs to Quaternary perched water and steady water level is located a depth of 3.9-4.8m. The elevation of the water level is 45.6-45.7m and the main replenishment source is atmospheric precipitation and annual variation changes with the seasons. Figure 2.1-1 shows the engineering geological section of the site.

Shenyang Lvheng Environment Consulting Co. Ltd 23#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 3Figure 2.1-1 Engineering geological section of the site The steady water level of the site is located at a depth of approximately 22m and is shallow confined water. Some areas inside the site contain small amounts of perched water at 4-5m and water volume is not abundant. In addition, water level and volume changes are greater with changes in spatiotemporal changes at the site. The overall surface layer of the site consists of miscellaneous fill with a thickness of around 1.0-3.0m. The middle consists of a very thick clay layer with a thickness of more than 15 m. The shallow confined aquifer consists of fine or medium sand and the steady water level is around 15m. Figure 2-5 shows the hydrogeological and geological profile during the sampling process. According to data collected in this survey (provided by the Shenyang Geotechnical Investigation & Surveying Research Institute), the elevation of the site during manufacturing was 42.2-44.2m, with an overall presentation of high on the northwest and lower on the southeast. The shallow groundwater in the site was not used. Figure 2.1-2 shows the hydrogeological section of the site.

Shenyang Lvheng Environment Consulting Co. Ltd 24#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 4Figure 2.1-2 Engineering geological section of the site 2.1.4 Socioeconomic status Tiexi District in Shenyang is located at the southwest of the city center in Shenyang city. The administrative region has an area of 484km2 and has jurisdiction over 16 street offices, 126 communities, 2 townships, and 24 administrative villages. The population is 1.14 million. To the east after a railway is the Heping district, to the north after a railway is the . The southwest is linked to the and the terrain is flat. The Tiexi District is one of the districts with the best hygiene, transportation, urban construction and details in Shenyang. In this district, enterprises are large in scale and there are many types of industries with strong complementation. In terms of equipment manufacturing industry, this area concentrates several machine tool, turbine compressor, ultra-high voltage units, large-scale water pumps, and other major projects and technologically-advanced companies. In the 24 types of 210 equipment sets that China is capable of manufacturing, Shenyang accounts for two-thirds. In industrial output and profit tax generated by Shenyang, 66% are from Tiexi district. There are more than 1300 companies from 40 countries and regions that are located in

Shenyang Lvheng Environment Consulting Co. Ltd 25#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Tiexi, of which 83 are multinational companies, and 21 are the world’s top 500 companies. The Tiexi District has a beautiful environment and smooth roads, with nine 25 km long dedicated railways and several dozen domestic and international airlines. Its 325 streets are connected with the Shenyang– and Jingshen Expressways, formed a well-connected transportation network. of the passes through the entire district from east to west. 2.2 Current status of the contaminated site and original pollution status 2.2.1 Current status of contaminated site and surrounding conditions 2.2.1.1 Current status of the contaminated site The contaminated site in the project was the original manufacturing zone of the Beier Road North Factory of Northeast Pharmaceuticals. After on-site survey, all original buildings have been dismantled. Figure 2.2-1 shows the current status of the contaminated site.

Figure 5Figure 2.2-1 Current status map of the contaminated site 2.2.1.2 Current status of pollution sources at the surroundings of the contaminated site Through analysis of the surrounding environment, the main pollution sources of this site include: ① The Beier Road South Factory of Northeast Pharmaceuticals in the south across the Beier road. Currently, this factory is still in operation. Its pollutants with strong mobility mainly include volatile organic pollutants. However, after these pollutants have undergone gaseous migration and dispersal to the soil, they are not easily enriched in the soil. ② On the east side, a 2.67m stretch is the original Shenyang smelter which was in operation in 1936 to 2000. In 2007, the site had completed remediation and was developed into commercial and residential land. During the production period, emission of exhaust fumes from smelting may result in elevation in soil heavy metal levels in the surrounding regions. ③ On the northeast side, a 700m stretch is a coke oven gas plant which was in operation in 1958 to 2006. In 2012, the site had completed

Shenyang Lvheng Environment Consulting Co. Ltd 26#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site remediation and was developed into residential land. During the production period, emission of exhaust fumes from coking may result in elevation in soil polycyclic aromatic hydrocarbons in the surrounding regions. ④ The 577 stretch at the southeast side is the Yuanweigong Street Factory of the Shenyang Chemical Plant, which was in operation from 1939 to 2015.Currently, it is no longer in operation. Its characteristic pollutants——pesticides and mercury do not have any high point sources and do not easily migrate to our site. ⑤The 1.02km stretch at the southeast side contains the original Shenyang MSG factory that was in operation from 1937 to 2007. Currently, it is no longer in operation and is undergoing soil remediation. After remediation is completed, it will be converted to residences, schools, and Hongmei square. Table 15Table 2.2-1 List of major (original) pollution sources at surrounding areas of the contaminated site Distance Type Name Direction Notes (km) Northeast Pollution Pharmaceutical S 0.044 Currently in operation source Factory South Factory No longer in operation in 2000. Pollution Original Shenyang E 2.665 Currently converted to commercial and source Smelter residential land Pollution Original coke oven SE 0.713 Currently the Fangda Shengjing area source gas plant Pollution Shenyang Chemical SE 0.577 Ceased operation in 2015 source factory Pollution Original Shenyang SE 1.027 Ceased operation in end 2007 source MSG factory

Shenyang Lvheng Environment Consulting Co. Ltd 27#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 6Figure 2.2-2 Distribution map of major (original) pollution sources at surrounding areas of the contaminated site 2.2.2 Overview of original factory site and emission status 2.2.2.1 Overview of the factory site The Northeast Pharmaceuticals Group Co. Ltd was formerly the Northeast General Pharmaceutical Factory that was founded in 1946. The factory mainly manufactures 12 major classes of 400 chemical active pharmaceutical ingredients, medical intermediates and preparations, such as antibiotics, vitamins, cardio-cerebrovascular drugs, drugs for the digestive system, antiviral drugs, natural drugs, antipyretic and analgesics, anti-HIV drugs, anesthesia and psychotropic drugs, contraceptive drugs, health supplements, and diagnostic reagents. The North factory includes the twelfth company, berberine company, third company, Weihua company, 2nd preparation company, Naokangfu company, and other production workshops. In addition, it also contains environmental protection facilities (at the north region of the factory site), warehousing and logistics center (northern corner of the factory site), research institute and central field (located the southeast region of the factory site), substation (including 3rd and 7th substation), solid waste storage area (located in the center of the factory site) and offices for the various workshops. Figure 2.2-1 shows the layout of the original site of the Northeast Pharmaceutical Factory.

Shenyang Lvheng Environment Consulting Co. Ltd 28#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 7Figure 2.2-3 Layout of the original site of the Northeast Pharmaceutical Factory 2.2.2.2 Manufacturing processes The main products in the original Northeast Pharmaceuticals northern factory are AZT (Zidovudine), berberine, vitamin B1, L-carnitine and its series of products, sterile powder for injection, piracetam, and aminobutyric acid. Their manufacturing processes are described as follows: 1. AZT manufacturing process Methanesulfonyl chloride is added to pyrantel under the protection of triphenylmethyl chloride, pyridine, and dichloromethane. After primary sulfonation is complete, 5-D is produced. 5-D undergoes a secondary sulfonation reaction under the effects of dichloromethane, pyridine, methanesulfonyl chloride, ethyl ester, and sodium chloride. After stratification, sodium carbonate, sodium azide, DMF, and drinking water were added for azie reaction. After the crystals were

Shenyang Lvheng Environment Consulting Co. Ltd 29#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site isolated and washed, wet azide products were formed. Under the effects of ethyl acetate and drinking water, wet azide products undergo stratification. Following that, deprotection is carried out under the effects of methanol and sodium benzenesulfonate. The product then undergoes filtering, discoloration, crystal isolation to obtain the active pharmaceutical ingredient for zidovudine (AZT). 2. Berberine manufacturing process Berberine manufacturing undergoes cyclization, cyanidation, amination, methylation, condensation, cyclization, and copper removal to obtain the crude product berberine. This crude product undergoes refining to obtain the berberine end-product. Firstly, catechol and dichloromethane react under the presence of sodium hydroxide and tetrabutylammonium bromide to produce 1,3-Benzodioxole. 1,3-Benzodioxole reacts with formaldoxime hydrochloride to form piperonyl chloride. Piperonyl chloride reacts with sodium chloride under the presence of tetrabutylammonium bromide to form piperonyl cyanide. Piperonyl cyanide reacts with hydrogen under catalysis with Raney nickel to form piperonyl ethylamine. Ortho-vanillin reacts with dimethyl sulfate under the presence of sodium hydroxide and tetrabutylammonium bromide to form methyl ortho-vanillin. Piperonyl ethylamine and methyl ortho-vanillin undergoes condensation reaction to form a Schiff base, which reacts with hydrogen under catalysis with Raney nickel to form a condensate. The condensate reacts with HCl to form a hydrochloride condensate. The hydrochloride condensate, glyoxal, and anhydrous cupric chloride undergo cyclization to form copper berberine. This reacts with hydrogen peroxide in the presence of hydrochloric acid to form crude berberine. Crude berberine is refined to obtain the berberine end-product. 3. Vitamin B1 manufacturing process Methanoic acid and methanol undergoes esterification to form methyl methanoate. Following that, this reacts with acrylonitrile to undergo formylation to form a sodium salt, which undergoes further methylation, condensation, and distillation to produce acetal. Acetal then undergoes condensation with sodium methoxide and acetamidine hydrochloride before hydrolysis, freezing, and centrifugation to obtain 2-methyl-4-amino-5-acetylaminomethyl pyrimidine. 2-methyl-4-amino-5-acetylaminomethyl pyrimidine undergoes alkaline hydrolysis, before reacting with methanol, ammonium chloride, and carbon disulphide to undergo

Shenyang Lvheng Environment Consulting Co. Ltd 30#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site ammonium salt reaction. Following that, a chlorohydrin solution was added for condensation before cyclization, neutralization, and centrifugation to obtain thiothiamine. Thiothiamine then undergoes oxidation with hydrogen peroxide, before decoloration, centrifugation, before ammonium nitrate was added for salt conversion, neutralization to obtain thiamine nitrate. Thiamine nitrate undergoes conversion with methanol and hydrogen chloride gas before dissolution and refining to obtain vitamin B1. 4. Manufacturing process of L-carnitine and its series of products 1) Epichlorohydrin undergoes catalysis and reacts with water before distillation to obtain S)-(+)-Epichlorohydrin. S)-(+)-Epichlorohydrin then reacts with trimethylamine hydrochloride in ethanol solution to undergo amination. After cooling and crystallization, quaternary ammonium salt is obtained. Sodium chloride solution is then added dropwise onto the methanol solution containing the quaternary ammonium salt for cyanidation. Following that, the mixture is cooled and sodium chloride is removed. After the filtrate is concentrated, anhydrous methanol and injectable carbon was added for reflex, dissolution, and discoloration, before pressure filtration, cooling, crystallization, filtration, and drying to obtain the cyanide. The cyanide and refined hydrochloric acid then undergoes a thermal insulation reaction before concentration into a viscous mixture. After cooling, ammonia was added for pH neutralization to neutral pH, before cooling and filtration to remove ammonium chloride. The filtrate is then drawn into an addition tank and sodium metabisulfite was added for an addition reaction. Following that, the solution is diluted and undergoes ion exchange. After the eluate was concentrated to a certain volume, carbon was added for discoloration and adsorption. After discoloration, filtration was carried out to remove carbon. Then, an anionic resin was added for adsorption, before filtration. The filtrate was drawn into a secondary concentration tank and concentrated until a dry powder is obtained. Then, anhydrous ethanol was added for reflux and dissolution. The solution is then passed through a pressure filter into a crystallization tank. After concentration to a certain volume of ethanol, the solution was cooled before acetone was added for cooling and crystallization, filtration, drying, and packaging to obtain L-carnitine end products. 2) A certain amount of L-carnitine filtrate is drawn into a concentration tank and concentrated until a dry powder is obtained. Following that, glacial acetic acid was added to

Shenyang Lvheng Environment Consulting Co. Ltd 31#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site dissolve the material before acetyl chloride was added dropwise to react. After the reaction was complete, the material was concentrated to dryness and anhydrous ethanol was added for reflux and dissolution. The solution is then passed through a pressure filter into a crystallization tank for cooling and crystallization, filtration, drying, and packaging to obtain L-acetyl-carnitine end product. 3) The L-carnitine solution was passed through a pressure filter into a reaction tank and tartaric acid was added for reflux and dissolution, insulation before cooling and crystallization, filtration, drying, and packaging to obtain L-carnitine tartrate end product. 4) The L-carnitine solution was passed through a pressure filter into a reaction tank and fumaric acid was added for reflux and dissolution, insulation before cooling and crystallization, filtration, drying, and packaging to obtain L-carnitine end product. 5) A certain amount of L-carnitine filtrate is drawn into a reaction tank and hydrochloric acid was added dropwise to react. After insulation, the solution was concentrated to obtain a dry powder and isopropanol was added for reflux and dissolution. Following that, cooling and crystallization, filtration, drying, and packaging were carried out to obtain L-carnitine hydrochloride end product. 5. Sterile powder for injection process After pre-processing of fosfomycin sodium, aseptic processing and capping were carried out. Testing was conducted after packaging and stored in the warehouse after passing the test. 6. Piracetam manufacturing process Crude piracetam is heated to dissolve in isopropanol and activated charcoal was added for discoloration before pressure filtration into a crystallization tank. Normal water and salt water was added to decrease temperature until piracetam crystallizes and is precipitated out. The material was filtered using a centrifuge to obtain solids. Isopropanol was used to wash the solids. The refined wet piracetam was then dried using a double cone dryer and packaged after passing tests. 7. Aminobutyric acid manufacturing process 2-Pyrrolidinone is reacted with a digestive fluid to undergo hydrolysis under specific temperature, pressure, and reaction time, before ammonium bicarbonate and charcoal were added for discoloration and calcium removal. After passing assays, the solution is cooled,

Shenyang Lvheng Environment Consulting Co. Ltd 32#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site centrifuged, and filtered to obtain crude filtrate, which is passed through a pressure filter into a crystallization tank. After concentration, dehydration, ethanol addition and crystallization, centrifugation, filtration, and drying into a powder, aminobutyric acid is obtained. 8. VA acid manufacturing process Methanol is added into a reaction tank, mixed, and heated so that the tank temperature reaches 47-48℃. VA crystals are added and stirred to ensure that the tank temperature is maintained at 47-48℃ and VA crystals fully dissolved. Silver oxide is added into the reaction tank and the tank temperature: is maintained at 47±1℃. After the tank temperature has stabilized, potassium hydroxide solution is added dropwise. If the temperature exceeds 70℃, cold water is immediately pumped into the sandwich layer for cooling to prevent blanking. After the temperature has decreased, the remaining alkali can be added at a faster speed and the addition time is around 10-15 min. After alkali addition has completed, the tank temperature is maintained, and insulated reaction occurs for 1 hour. A filter funnel is placed (containing two layers of filter paper) and the solution is filtered into an acidification tank. The silver oxide filter cake is drained and 120L chloroform was used to wash the filter cake, before draining for further processing. The acidification tank is turned on for stirring and sulfuric acid is added dropwise until the solution pH=3-4 (around 60-75 L of acid consumed). Chloroform is added to the acidification tank for extraction, with the water layer on top and the material layer below. The material solution is combined into a wash tank and the waste acid is stored at a storage tank. Purified water is added into the material solution and mixing and stratification is initiated. The water layer is on top while the material layer is below. Repeated washing of the material solution is carried out until the wash solution reaches a pH=6.5-7 and is released into a storage tank. If there is an emulsion layer, this is also released into the tank for concentration and processing. A filter funnel is placed (containing two layers of filter paper) and the solution is filtered into a distillation tank and the residue is discarded. The material liquid is decompressed and concentrated and brownish-yellow crystalline substances are precipitated at the late stage of concentration until a viscous state is reached before concentration is stopped. Chloroform is then added for redisolution until the solution is clear and without crystals. The solution is then left overnight. A filter funnel is place (one layer of electrical filter bag). The material solution is placed into the funnel and drained till dryness before the crystals were washed with 3-4L of

Shenyang Lvheng Environment Consulting Co. Ltd 33#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site chloroform until color requirements are fulfilled before draining is continued. After the material is drained, it is placed into a drying tray and air-dried for 8-12 hours. 9. Silver sulfadiazine manufacturing process Purified water is added into reaction tank and heated before sulfadiazine is added and mixed for 5-10 minutes. Silver nitrate solution is added dropwise and reacted for 20-30 minutes. The measured pH should be 1-2. After the reaction has ended, ammonia is added dropwise to neutralize the reaction solution to pH=7. The solution is mixed for another 20-30 minutes. The reaction solution is retested to be pH 7 and placed into a centrifuge for dehydration and drying. The material is placed onto a drying tray and covered. The tray is placed in a drying cabinet and dried at 87±2℃ until constant weight and the drying duration is 15-20 h. The material is rotated every 2 hours and weighed at 14 hours before drying for another 1 hour to constant weight. The dried material is weighed, crushed, packaged, weighed, and the laboratory is notified to carry out sampling. 10. Febuprol manufacturing process Febuprol manufacturing mainly includes 7 processes of alcohol-alkane condensation, epoxidation, washing, vacuum distillation, phenol-ether condensation, washing and removal of phenol, distillation. The specific processes are described as follows: ●Alcohol-alkane condensation Epichlorohydrin and n-butanol is added into a reaction tank and mixed. The cover of the reaction tank is opened and aluminum chloride is rapidly added and mixed. Cooling water is allowed to enter the sandwich layer and sulfuric acid is gradually added dropwise into the reaction tank. ●Epoxidation The alcohol-alkane reaction solution is released into the epoxidation tank and mixing and cooling of the sandwich layer is initiated. 50% sodium hydroxide is added dropwise and mixed for the reaction to proceed for 2 hours before mixing was stopped. The solution was then left to stand for 2 hours and the reaction is completed. ●Washing Sodium hydroxide solution was first added to the epoxidation tank and mixed for 3 minutes before leaving to stand for 30 minutes. Then, sodium chloride solution was added to the

Shenyang Lvheng Environment Consulting Co. Ltd 34#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site epoxidation tank, mixed for 3 minutes and left to stand for 30 minutes. Finally, distilled water was added to the epoxidation tank, mixed for 3 minutes, and left to stand for 30 minutes. ●Vacuum distillation The washed crude epoxypropyl ether is transferred into a distillation tank. After the vacuum has stabilized, the sandwich layer is heated and the distillate is collected in stages until no more distillate is obtained. Low-boiling residue undergoes epoxidation again while high-boiling residues are collected for environmental processing. ●Phenol-ether condensation The epoxypropyl ether is transferred into the phenol-ether condensation tank and phenol is added. Sodium hydroxide is immediately added so that the pH value becomes 11-12. ●Washing and phenol removal Sodium hydroxide solution is used for multiple rounds of washing. Washing method: Mixing for 3 minutes, leaving to stand for 30 minutes. The lower water layer is drained off while the top layer is the material layer. Sodium chloride solution was then used to wash using the same method as above for each round of addition of sodium chloride solution. ●Distillation (refining) Crude products that have passed the assay are transferred into the distillation tank. Cold water is allowed into the cooler. With continuous increase in the temperature in the oil bath, distillate is gradually released. 11. Furosemide manufacturing process Pure water is added to the sodium salt tank and mixed before sodium bicarbonate is added and heated to fully dissolve. Furosemide is slowly added to dissolve. When dissolution is slowed, sodium bicarbonate is re-added before furosemide is added. The pH is measured to be 8-8.5 and activated charcoal is added for insulated discoloration for 45 minutes. The valve at the bottom of the tank is slowly rotated so that the material solution is placed into the filter. Filtration: if charcoal leaks out during filtration, the filtrate will turn black. Return the filtrate and carry out filtration again until completion. The filtrate is combined and mixed before neutralization with acetic acid at a speed of 0.56 L per minutes. Neutralization is completed around 3 hours. Acetic acid is then added dropwise for 2.5 hours and pH is measured repeatedly until the neutralized pH is 4-5. Mixing was continued for 30 minutes before centrifugation and filtration. Pure water was

Shenyang Lvheng Environment Consulting Co. Ltd 35#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site used to wash the filter cake, with uniform top and bottom washes until the pH of the wash fluid is 6.5. Continue drying and subpackaging into 16 drying trays for drying. The drying plates are placed from top to bottom into a hot air oven and the heating switch is turned on to carry out drying at 90-100℃ for 14-16h. Weight loss during drying in the last 2 hours should not exceed 25g. 2.2.2.3 Discharge status of pollutants Combination of the major products and processes of the original factory showed that the manufacturing raw materials, manufacturing processes and manufactured process do not involve heavy metals or organic pollutants that are commonly seen in soil or the contaminated site. The atmospheric pollutants that are mainly emitted during the manufacturing process include dichloromethane, ethyl acetate, methanol, ammonia, benzene, dust, hydrogen chloride, CS2, chlorine gas, trimethylamine, acetone, isopropanol, ammonia hydroxide, CO2 ; water pollutants

- - mainly include CN , CODcr, BOD5, SS, and Cl ,and solid waste mainly includes slag and waste filter cake during the manufacturing process. The original factory has adopted corresponding environmental production measures for processing exhaust gases, wastewater, and solid waste produced. This factory has already ceased operation in April 2015 and relocated to the Shenyang Economic Technological Development Zone. Therefore, exhaust gas, wastewater, and solid waste produced in the original factory site were not analyzed. Table 2.2-1 shows the discharge status of major pollution sources in the original factory site.

Shenyang Lvheng Environment Consulting Co. Ltd 36#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 16Table 2.2-2 Discharge status of major pollutants in the original Northeast Pharmaceutical Factory northern factory site Name of process Type of pollution Name of pollutant Exhaust gas Dichloromethane, ethyl acetate, methanol

AZT manufacturing Wastewater Mother liquor wash solution, CODcr, NH3-N Solid Waste Triphenyl filter cake Dichloromethane, ammonia, benzene, methanol, dust, Exhaust gas HCl Berberine manufacturing Wastewater CN-, CODcr Solid Waste Waste acid, filtration slag Exhaust gas Methanol, ammonia, CO, CS2, chlorine gas Vitamin B1 Wastewater CODcr, Cl Solid Waste Sodium methyl sulfate, high-boiling residues HCl, trimethylamine, ethanol, methanol, ammonia, Exhaust gas L-carnitine and its series acetone of products Wastewater Cyanidation wastewater, CODcr Solid Waste Chloropropanols, sodium chloride Exhaust gas Dust Sterile powder for Wastewater CODcr, SS, BOD5 injection Solid Waste Waste material, drugs, waste boxes, boxes, etc. Exhaust gas Isopropanol, methanol, ammonia Piracetam Wastewater CODcr Solid Waste Carbon residues

Exhaust gas CO2, ammonia hydroxide, ethanol Aminobutyric acid Wastewater CODcr Solid Waste Filter cake Exhaust gas / VA acid Wastewater CODcr Solid Waste Mother liquor residues Exhaust gas Ammonia Silver sulfadiazine Wastewater CODcr, pH Solid Waste / Exhaust gas HCl Febuprol Wastewater CODcr Solid Waste High-boiling residues Exhaust gas / Furosemide Wastewater CODcr, pH Solid Waste Carbon residues 2.3 Future land use plans According to information from the local government and China Resources Land Co Ltd., this plot of land will be acquired by the Tiexi District Government (land storage transaction

Shenyang Lvheng Environment Consulting Co. Ltd 37#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site center (Parcel No. TX2016-06) to be classified as mixed land for commercial and residential purposes (Category 2 residential land). The area of planned construction land is around 110,000 m2 and the planned construction area is around 240, 000m2. The plot ratio is >1.0 and ≤2.2, construction density ≤35%, greening rate ≥30%, proportion of commercial buildings ≤10%, residential land tenure of 70a and commercial land tenure of 40a. Some southern and western sides of residential land at the site are for commercial properties, with height of 1-3 stories. The northern and western sides will consist of mid-rise and high-rise buildings, the central region will consist of bungalows with 5-6 storeys, and the southeast corner will be a kindergarten. The basement of the park is a fully underground garage. Roads in the future park in the land parcel are designed with an elevation of 44.60 m. The substructure of the street real estate sales offices and shops at the south side were designed to be 43.80-44.30m, substructure of the residences were designed to be 45.00-45.95m, the floor of the underground garage was designed to have an elevation of -6.1m, and the height of the foundation pit was 38.5-39.5m. The depth of the corresponding original site is2.3-1.

Shenyang Lvheng Environment Consulting Co. Ltd 38#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 8Figure 2.3-1 Schematic diagram of the demonstration land of the site (area bounded by red lines is the area used for this remediation) 2.4 Schedule arrangement and work content According to the the , the construction period of this project is expected to be from March to November 2018 and the construction cycle lasts for a total of 9 months. Table 2.4-1 shows the project schedule and work.

Shenyang Lvheng Environment Consulting Co. Ltd 39#109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 17Table 2.4-1 Project schedule arrangement and work content Item/duration (half a month) 3 4 5 6 7 8 9 10 1 Preparation of construction

equipment and drugs Anti-seepage measures at the

original site Stage 1 dredging and

transportation Stage 1 dredging acceptance check

and monitoring Stage 1 solidification and

stabilization Stirring and health control Acceptance check Stage 1 chemical oxidation Test Pilot Oxidation project # # Acceptance check # # Stage 1 thermal desorption Equipment installation and

debugging Test operation and monitoring Operation and acceptance * check Stage 2 dredging and

transportation Stage 2 dredging acceptance check

and monitoring Stage 2 solidification and

stabilization Stirring and health control Acceptance check Stage 2 chemical oxidation

Shenyang Lvheng Environment Consulting Co. Ltd 40 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Item/duration (half a month) 3 4 5 6 7 8 9 10 1 Oxidation project # # # Acceptance check # # Stage 2 thermal desorption * Site withdrawal and evaluation of overall remediation results of the site

Shenyang Lvheng Environment Consulting Co. Ltd 41 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

2.5. Investigation and Evaluation of Environmental Quality Status

2.5.1 In-situ Remediation Engineering

2.5.1.1 Monitoring and Evaluation of Ambient Air Quality Status

1. Monitoring Points and Data Source

To monitor the ambient air quality of the in-situ remediation site, the related data is available from the ambient air monitoring data acquired by Shenyang Ze'r Test Service Co., Ltd. at the monitoring points (the minimum distance to the remediation site is 1,530 m) of Jiari Lanwan Community from April 6th to 12th, 2016.

2. Monitoring Items

Routine monitoring factors: SO2, NO2 ,and PM10.

3. Monitoring Analysis Methods

Table 2.5-1 describes the monitoring analysis methods. Table 18Table 2.5-1 List of Analysis Methods Monitoring Analysis Method Source Method Detection Limit (mg/m3) Factor Formaldehyde absorption⎯ pararosaniline SO2 HJ482-2009 Average daily: 0.004 spectrophotometry

NO2 N-ethylenediamine spectrophotometry HJ479-2009 Average daily: 0.003

PM10 Gravimetric method HJ618-2011 Average daily: 0.001 4. Evaluation of Monitoring Results

(1) Evaluation Methodology

Air quality status is evaluated by the single standard index method:

Iij= Cij / Csi

where, Iij indicates the index of the i-th pollutant at measuring point j;

3 Cij indicates the average value of the i-th pollutant at measure point j (mg/m );

3 Csi indicates the evaluation standard of the i-th pollutant (mg/m ).

(2) Results of Air Monitoring and Evaluation

Table 5.1-2 lists the statistical results of air monitoring.

Shenyang Lvheng Environment Consulting Co. Ltd 42 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 19Table2.5-2 Results of Air Monitoring and Evaluation Average Daily Value Maximum Point Position 3 Detection Over-limit Standard Ci (μg/m ) Ii over-limit rate rate (μg/m3) multiple

SO2 37 to 50 0.246 to 0.333 100% / / 150

NO2 26 to 41 0.325 to 0.513 100% / / 80

PM10 78 to 117 0.520 to 0.780 100% / / 150

According to Table 2.3-2, the average daily monitoring values of SO2, NO2, and PM10 meet the secondary standard specified by Ambient Air Quality Standard (GB3095-2012), and the average hourly values of SO2 and NO2 meet the secondary standard specified by Ambient Air Quality

Standard (GB3095-2012).

2.5.1.2 Investigation and Evaluation of Surface Water Environment Status The wastewater generated during soil excavation mainly includes the flushing water for the wheels of transport trucks, and domestic wastewater generated by construction personnel. The flushing water for the wheels of transport trucks is treated in the settling pond and used cyclically, but is not discharged to the outside. The domestic wastewater generated by construction personnel is treated in the septic tank first, and then discharged to Xiannvhe Sewage Treatment Plant through the municipal sewage pipe network. The wastewater is not directly discharged to surface waters, so the evaluation of surface water quality is not involved in this project.

2.5.1.3 Investigation and Evaluation of Noise Environment Status Dalian Jingcheng Shenghongyuan Test Technology Co., Ltd. is commissioned to monitor the noises around the original Northeast General Pharmaceutical Factory from December 27th to 28th, 2017. Table 5.1-3 lists the monitoring results of acoustic environmental quality status. Table 20Table 2.5-3 Results of Acoustic Environment Monitoring and Evaluation (dB(A)) Monitoring Results Daytime Nighttime Executive Standard Factory Boundary Eastern boundary 46.6-46.8 39.2-39.7 60/50 Southern boundary 63.8-64.4 39.6-39.7 70/55 Western boundary 48.8-49.6 38.3-39.0 60/50 Northern boundary 49.2-49.4 38.0-38.2 70/55

According to Table 2.3-3, the noises nearby the northern and southern boundaries meet the standard of Category 4a specified in Environmental Quality Standard for Noise (GB30096-2008), and noises nearby the eastern and western boundaries meet the standard of Category 2 specified in

Environmental Quality Standard for Noise (GB30096-2008).

2.5.1.4 Investigation and Evaluation of Soil Environment Status The monitoring data on the soils within the remediation range is mainly available from Detailed

Shenyang Lvheng Environment Consulting Co. Ltd 43 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Environmental Survey and Risk Evaluation Report on POP-contaminated Site (North Production Area of the Factory in Bei'er Road of Northeast Pharmaceutical Group Co., Ltd.) of Northeast General Pharmaceutical Factory, which was prepared by Shenyang Academy of Environmental Sciences in November 2017. Within the remediation range, there are totally 113 soil sampling points, and a total of 888 soil samples are acquired, representing an area of 114,000 m2. The monitoring results show that the maximum values of a total of 23 indexes exceed the related standard values. Specifically, the concentration of arsenic, mercury, lead, total chromium, nickel, copper, zinc, benzene, and trichloromethane exceeds the limits for residential lands specified by Screening Levels for Soil Environment Risk Assessment (this is a local standard of Beijing City). The concentration of aniline, tetraphene, chrysene, benzo[b]fluoranthene, benzo[k]fluoranthene, benzoapyrene, indeno(1,2,3-cd)pyrene, dibenz[a,h]anthracene, -hexachlorocyclohexane, 4'-DDD, 4,4'-DDE, 4,4'-DDT, 2,4'-DDT, and TPH (

2.5.1.5 Evaluation of Groundwater Environmental Quality Status The monitoring data on the groundwater within the remediation range is mainly available from Risk Evaluation Report on POP-contaminated Site of Northeast General Pharmaceutical Factory, which was prepared by Shenyang Academy of Environmental Sciences in November 2017. Shenyang Academy of Environmental Sciences has sampled the groundwater for three times. The first groundwater sampling was conducted on June 19th, 2017; six groundwater samples and one parallel sample (G2) were acquired. The second groundwater sampling was conducted on July 29th, 2017; G5 was sealed for unknown reasons, and thus the groundwater in G5 could not be sampled; then, five groundwater samples and one parallel sample (G6) were acquired. The third groundwater sampling was conducted on October 27th, 2017; G1, G4, and G5 were sealed for unknown reasons, and thus the groundwater in G1, G4, and G5 could not be sampled; then, three groups of groundwater soils (G2, G3, and G6) and one group of parallel samples (G2) were acquired. According to the test results, the values of certain conventional indexes (including permanganate index, chroma, chloride concentration, pH value, total hardness, total dissolved solids, concentration of ammonia nitrogen, concentration of volatile phenol, iron concentration, lead concentration, and manganese concentration) about the sampled groundwater are above the standard for Grade-III groundwater. The values of certain unconventional indexes (for example, the concentration of aniline, 1,2-dichloroethane, methylbenzene, and benzene) are above the standard for Grade-III groundwater specified by Standard for Groundwater Quality. For details about groundwater monitoring results and evaluation of such results, refer to section 4.2 "Evaluation of Groundwater Pollution Status”

2.5.2 Ex-suit Remediation Project

2.5.2.1 Monitoring and Evaluation on Current Ambient Air Quality 1. Monitoring Sites and Data Sources

Shenyang Lvheng Environment Consulting Co. Ltd 44 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Ambient air quality at ex-suit remediation fields: Ambient air monitoring data from monitoring sites at Qianma Village, Houma Village (currently relocated), Ermangniu Village (currently relocated), Lintai Village (currently relocated), Yuhong Community Welfare House and Mabei Residence from December 5 to December 11, 2016 were collected. 2. Monitored Items

SO2, NO2, PM10, PM2.5, TSP, HCl, VOCs

3. Monitoring and Analysis Methods The monitoring and analysis methods are shown in Table2.5-4. Table 21Table 2.5-4 List of Monitoring and Analysis Methods Monitored Method detection limit Analysis method Method source item (mg/m3)

PM2.5 Gravimetric method HJ618-2011 Daily average: 0.001 TSP Gravimetric method GB/T 15432-1995 Daily average: 0.001 HCl Ion chromatography HJ 549-2016 Hourly average: 0.01 VOCs Gas chromatography HJ 584-2010 Hourly average: 1.5×10-3mg/m³ 4. Monitoring Results and Evaluation ⑴ Evaluation Methods

Single standard index method was used to evaluate the atmospheric quality, i.e.:

Iij= Cij / Csi

th Where: I ij—ith pollutant, the index of the j monitoring site;

th 3 Cij—ith pollutant, the average value at the j monitoring site (mg/m );

3 Csi —ith pollutant evaluation standard (mg/m ). ⑵ Monitoring and Evaluation Results The monitoring statistical results are shown in Tables2.5-5-2.5-10.

Shenyang Lvheng Environment Consulting Co. Ltd 45 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 22Table2.5-5 SO2 Monitoring and Evaluation Results Maximum Detection Exceeded Standard Site C (μg/m3) I exceeded i i rate rate μg/m3 times Qianma Village 36-56 0.072-0.112 100% / / 500

Houma Village 36-57 0.072-0.114 100% / / 500

Lintai Village 47-81 0.094-0.162 100% / / 500 Ermangniu Village 33-56 0.066-0.112 100% / / 500

Mabei Residence average ly 34-60 0.068-0.120 100% / / 500

Yuhong District Hour Social Welfare 30~52 0.060-0.104 100% / / 500 House Qianma Village 42-47 0.280-0.313 100% / / 150

Houma Village 45-50 0.300-0.333 100% / / 150

Lintai Village 55-61 0.367-0.407 100% / / 150 Ermangniu Village 42-48 0.280-0.320 100% / / 150

Mabei Residence 40-47 0.267-0.313 100% / / 150 aily average aily

Yuhong District D Social Welfare 37-43 0.247-0.287 100% / / 150 House

Table 23Table2.5-6 NO2 Monitoring and Evaluation Results Maximum Detection Exceeded Standard Site C (μg/m3) I exceeded i i rate rate μg/m3 times Qianma Village 47-69 0.210-0.305 100% / / 200

Houma Village 52-79 0.190-0.310 100% / / 200

Lintai Village 55-84 0.210-0.270 100% / / 200 Ermangniu Village 38-60 0.220-0.330 100% / / 200

Mabei Residence average ly 38-63 0.250-0.380 100% / / 200

Yuhong District Hour Social Welfare 45-76 0.245-0.365 100% / / 200 House Qianma Village 49-61 0.613-0.700 100% / / 80

Houma Village 56-67 0.600-0.725 100% / / 80

Lintai Village 57-73 0.713-0.838 100% / / 80 Ermangniu Village 48-58 0.663-0.775 100% / / 80

Mabei Residence 44-56 0.675-0.850 100% / / 80 aily average aily

Yuhong District D 50-63 Social Welfare 0.663-0.838 100% / / 80 House

Shenyang Lvheng Environment Consulting Co. Ltd 46 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 24Table 2.5-7 TSP Monitoring and Evaluation Results Daily average Maximu Site 3 Detection Exceeded m Standard C (μg/m ) Ii i rate rate exceeded μg/m3 times Qianma Village 176-202 0.587-0.673 100% / / 300 Houma Village 166-194 0.553-0.647 100% / / 300 Lintai Village 171-198 0.570-0.660 100% / / 300 Ermangniu Village 173-200 0.577-0.667 100% / / 300 Mabei Residence 177-207 0.590-0.690 100% / / 300 Yuhong District Social 162-190 0.540-0.633 100% / / 300 Welfare House

Table 252.5-8 PM10 Monitoring and Evaluation Results Daily average Maximum Site Detection Exceeded Standard C (μg/m3) I exceeded i i rate rate μg/m3 times Qianma Village 103-128 0.687-0.853 100% / / 150 Houma Village 93-118 0.620-0.787 100% / / 150 Lintai Village 97-123 0.647-0.820 100% / / 150 Ermangniu Village 96-125 0.640-0.833 100% / / 150 Mabei Residence 107-133 0.713-0.887 100% / / 150 Yuhong District 91-114 0.607-0.760 100% / / 150 Social Welfare House

Table 26Table 2.5-9 PM2.5 Monitoring and Evaluation Results Daily average Maximum Site Detection Exceeded Standard C (μg/m3) I exceeded i i rate rate μg/m3 times Qianma Village 52-73 0.693-0.973 100% / / 75 Houma Village 43-65 0.573-0.867 100% / / 75 Lintai Village 48-69 0.640-0.920 100% / / 75 Ermangniu Village 50-71 0.667-0.947 100% / / 75 Mabei Residence 57-74 0.760-0.987 100% / / 75 Yuhong District 39-61 0.520-0.813 100% / / 75 Social Welfare House

Shenyang Lvheng Environment Consulting Co. Ltd 47 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 27Table 2.5-10 HCl Monitoring and Evaluation Results Daily average Maximum Site Detection Exceeded Standard C (μg/m3) I exceeded i i rate rate μg/m3 times Qianma Village 32-48 0.640-0.960 100% / / 50 Houma Village 17-38 0.340-0.760 100% / / 50 Lintai Village 18-38 0.360-0.760 100% / / 50 Ermangniu Village 13-34 0.260-0.680 100% / / 50 Mabei Residence 28-46 0.560-0.920 100% / / 50 Yuhong District 13-36 0.260-0.720 100% / / 50 Social Welfare House

It is evident from Tables 2.3-5 to 2.3-10 that the hourly average values of SO2, NO2, PM10,

PM2.5 and TSP24 at the monitoring sites met the requirements of the Class II standards of the

Ambient Air Quality Standard (GB3095-2012); the hourly average values of SO2 and NO2 met the Class II standards of the Ambient Air Quality Standard (GB3095-2012); the 1-hour average of hydrogen chloride met the requirements of the Hygienic Standards for the Design of Industrial Enterprises (TJ36-79) standards; VOCs were not detected. 2.5.2.2 Investigation and Evaluation on Current Surface Water Environment The waste water produced in the ex-suit remediation plant area mainly includes quench tower drainage, caustic tower drainage and employees’ domestic sewage. The above waste water is discharged into the integrated sewage treatment stations of the new factories of Northeast Pharmacy Group Co. Ltd and processed until it meets the standards. Then, it is discharged through the municipal sewage pipe network into the Waste Water Treatment Plant under expansion at western Shenyang City for further processing. Since the drainage is not directly discharged into the surface water bodies, the surface water evaluation work was omitted in this project. 2.5.2.3 Investigation and Evaluation on Current Acoustic Environmental Quality The noise monitoring data around the plant boundary of the new factories of Northeast Pharmacy Group Co. Ltd from March 25 to 27, 2015 was collected for evaluation. The monitoring results are shown in Table 2.5-11.

Shenyang Lvheng Environment Consulting Co. Ltd 48 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 28Table 2.5-11 Monitoring Results of Acoustic Rnvironmental Quality (new Northeast Pharmacy factories) Unit: dB (A) Monitoring results Daytime Nighttime Execution standard Plant boundary East plant boundary 53.8-54.2 42.6-43.6 60/50 South plant boundary 51.7-52.7 41.2-42.7 60/50 West plant boundary 53.2-53.9 42.2-43.9 60/50 North plant boundary 54.3-55.1 42.3-43.5 60/50 As shown in Table2.5-11, the noise at the plant boundary met the requirements of Class II standard of the Environmental Quality Standard for Noise (GB3096-2008). 2.5.2.4 Evaluation on Current Soil Environmental Quality In the evaluation of soil environmental quality, monitoring data was mainly collected from the vinpocetine workshop, propargyl alcohol device, tank field, sewage treatment plant, solid waste yard location, Qianma Village, and Lintai Village on March 25, 2015. The monitoring indicators included pH, Cu, Cr, Zn, Ni, As, Hg, Pb and Cd. In the meantime, dioxins were tested in the soil in this area on December 11, 2016. The monitoring results are shown in Tables 5.2-9 and2.5-12. Table 29Table 2.5-12 Monitoring Results of Current Soil Environmental Quality; Unit: mg/L 1# Vinpocetine 2# Propargyl 4# Sewage 5# Solid Test items workshop alcohol device 3# Tank field treatment plant waste storage location location location yard location pH 7.58 6.64 6.58 7.11 7.02 (Dimensionless) Copper (mg/kg) 26 35 37 24 28 Chromium 131 101 93 108 99 (mg/kg) Zinc (mg/kg) 97.8 108.8 117.7 83.8 85.6 Nickel (mg/kg) 36 21 22 39 35 Arsenium (mg/kg) 22.8 12.1 20.5 8.2 12.2 Mercury (mg/kg) 0.076 0.155 0.124 0.054 0.039 Plumbum (mg/kg) 14.0 91.7 82.4 79.1 46.1 Cadmium (mg/kg) 0.15 0.29 0.25 0.29 0.10 Table 30Table 2.5-13 Monitoring Results and Evaluation of Dioxin in Doil Monitoring Monitored Unit Monitoring result Standard value site item 6# Qianma Dioxin ngTEQ/kg 53 ≤1.0×103ng/kg Village As shown in Table2.5-13, all the pollutants in the 5 monitoring sites met the Class III standard in the Environmental Quality Standards for Soils (GB15618-1995). According to Table

Shenyang Lvheng Environment Consulting Co. Ltd 49 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site 2.5-13, it is clear that dioxin levels in Qianma Village and Lintai Village met the Japanese environmental quality standards. The soil environmental quality was satisfactory. 2.5.2.5 Evaluation on Current Groundwater Environmental Quality

1. Monitoring Sites and Data Sources For groundwater in the soil ex-suit remediation area, 7-eye drilling holes and domestic wells were selected to monitor groundwater environmental quality. Table 2.3-14 shows the monitoring sites, whereas the monitoring site map is shown in Figure 5. Table 31Table 2.5-14 Details of Groundwater Quality Monitoring Sites Serial Relative position to the project Monitoring site Well depth (m) Buried depth (m) No. area North corner of 1 the plant Upstream 80 6.95

Central area of 2 —— 80 7.27 the plant South area of 3 —— 30 7.70 the plant South corner of 4 Downstream 30 5.40 the plant South of 5 Lateral upstream 11 6.00 Qianma Village South area of 6 Downstream 30 7.70 the plant West area of 7 Lateral downstream 8 5.00 the plant 2. Monitored Items A total of 20 items including pH, total hardness, total dissolved solids, permanganate index, sulfate, chloride, fluoride, cyanide, nitrate nitrogen, ammonia nitrogen, iron, copper, zinc, lead, mercury, hexavalent chromium, cadmium, volatile phenol, methanol, and total oil were monitored. 3. Monitoring and Analysis Methods Monitoring and analysis methods are shown in Table 2.5-15.

Shenyang Lvheng Environment Consulting Co. Ltd 50 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 32Table 2.5-15 List of Groundwater Quality Monitoring Methods Serial Minimum detectable Monitored items Analysis method No. concentration (amount) 1 pH value Glass electrode method 0.01(pH value)

2 Total hardness EDTA titrimetry 1.00 mg/L (calculated as CaCO3) Total dissolved 3 Gravimetric method 4mg/L solids

4 CODMn Potassium permanganate oxidation method 0.05mg/L 2- 5 SO4 Ion chromatography 0.05mg/L 6 Cl- Ion chromatography 0.02mg/L 7 F- Ion chromatography 0.01mg/L Isonicotinic acid - pyrazolone 8 CN- 0.002mg/L spectrophotometry

9 NO3-N Ion chromatography 0.01mg/L

10 NH3-N UV spectrophotometry 0.02mg/L Inductively coupled plasma atomic 11 Fe 0.0045mg/L emission spectroscopy Non-flame atomic absorption 12 Cu 0.009mg/L spectrophotometry Inductively coupled plasma atomic 13 Zn 0.001mg/L emission spectroscopy Non-flame atomic absorption 14 Pb 0.0025mg/L spectrophotometry 15 Hg Atomic fluorescence spectrophotometry 0.00005mg/L 16 Cr6+ diphenylcarbazide spectrophotometry 0.004mg/L 17 Cd Atomic absorption spectrophotometry 0.0001mg/L 18 Volatile phenol Bromination volumetric method 0.0003mg/L 19 Methanol Gas chromatography 1mg/L 20 Total oil Infrared spectrophotometry 0.01mg/L 4. Monitoring Results and Evaluation ⑴ Evaluation Methods The evaluation model used single water quality parameters and is expressed as:

Si,j = Ci,j / Csi

th Where: S i,j—standard index of single water quality evaluation factor i at the j sampling point;

th Ci,j—Concentration of water quality evaluation factor i at the j sampling point, mg/L;

Shenyang Lvheng Environment Consulting Co. Ltd 51 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Csi—Evaluation of criteria i factor ud, mg/L.

7.0 − pH j The standard index of pH value is: S pH,j = , pH≤7.0; 7.0 − pH sd

pH j − 7.0 S pH,j = , pH>7.0. pH su − 7.0

th Where: SpH,j—Standard index of single water quality factor pH at the j sampling point;

pHj—Water quality evaluation factor pH point j in the pH value;

pHsd—Evaluation criteria for the lower limit of the pH value;

pHsu—Evaluation criteria for the upper limit of the pH value. After calculation, if the standard index of the evaluation factor was greater than 1, it indicated that the pollution factor exceeded the standard of water quality evaluation and could not meet the requirement of functional zone in the water area.

⑵ Monitoring and Evaluation Results

The monitoring results and evaluation results are shown in Tables 2.5-16and2.5-17 respectively.

Shenyang Lvheng Environment Consulting Co. Ltd 52 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 33Table 2.5-16 Monitoring Results of Groundwater Quality; Unit: mg/L (dimensionless pH) Serial Monitor S1# S2# S3# S4# S5# S6# S7# No. ed item 1 pH value 7.03 7.63 6.7 7.06 7.22 6.82 7.3 Total 2 61.8 89 235 351 478 257 157 hardness Total 3 dissolve 155 166 561 574 785 413 398 d solids

4 CODMn 1.94 1.7 1.72 2.24 0.9 0.48 2.28 2- 5 SO4 3.69 25.4 124 139 159 98.4 65.1 6 Cl- 45.5 8.44 131 94.6 81.3 22.7 30.2 7 F- 0.19 0.39 0.12 0.17 0.26 0.15 0.4 8 CN- <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 <0.002

9 NO3-N 0.76 0.1 <0.01 1.79 44.2 30.9 1.09

10 NH3-N 1.29 0.9 0.64 2.1 <0.02 <0.02 0.5 11 Fe 0.04 0.145 <0.0045 0.0425 0.235 <0.0045 1.13 12 Cu <0.009 <0.009 <0.009 <0.009 <0.009 <0.009 <0.009 13 Zn <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 14 Pb <0.0025 <0.0025 <0.0025 <0.0025 <0.0025 <0.0025 <0.0025 15 Hg <0.00005 <0.00005 <0.00005 <0.00005 <0.00005 <0.00005 <0.00005 16 Cr6+ <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 17 Cd <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 Volatile 18 <0.0003 <0.0003 <0.0003 <0.0003 0.001 <0.0003 0.0047 phenol

Shenyang Lvheng Environment Consulting Co. Ltd 53 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 34Table2.5-17 Statistical Evaluation of Monitoring Results Regarding Groundwater Quality; Unit: mg/L Serial Monitored S1# S2# S3# S4# S5# S6# S7# No. item 1 pH value 0.02 0.42 0.60 0.04 0.15 0.36 0.20 Total 2 0.14 0.20 0.52 0.78 1.06 0.57 0.35 hardness Total 3 dissolved 0.16 0.17 0.56 0.57 0.79 0.41 0.40 solids

4 CODMn 0.65 0.57 0.57 0.75 0.30 0.16 0.76 2- 5 SO4 0.01 0.10 0.50 0.56 0.64 0.39 0.26 6 Cl- 0.18 0.03 0.52 0.38 0.33 0.09 0.12 7 F- 0.19 0.39 0.12 0.17 0.26 0.15 0.40 8 CN- <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04

9 NO3-N 0.04 0.01 <0.0005 0.09 2.21 1.55 0.05 10 NH3-N 6.45 4.50 3.20 10.50 <0.1 <0.1 2.50 11 Fe 0.13 0.48 <0.015 0.14 0.78 <0.015 3.77 12 Cu <0.009 <0.009 <0.009 <0.009 <0.009 <0.009 <0.009 13 Zn <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 14 Pb <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 15 Hg <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 16 Cr6+ <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 17 Cd <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Volatile 18 <0.15 <0.15 <0.15 <0.15 0.50 <0.15 2.35 phenol From Table 2.5-16and Table2.5-17, it is clear that some monitoring indicators of various monitoring sites exceeded the standard to various extents, among which the monitoring results of ammonia nitrogen in S1 #, S2 #, S3 # and S4 # exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93), S5 # total hardness and nitrate exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93), S7 # ammonia nitrogen, iron and volatile phenol exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93). and S6 # nitrate monitoring results exceeded the requirements of Class III limits in Groundwater Environmental Quality Standard (GB / T14848-93).

Shenyang Lvheng Environment Consulting Co. Ltd 54 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

3. Risk assessment and remediation goals of contaminated site 3.1 Risk assessment of contaminated site 3.1.1 Risk assessment of soil pollution status The soil monitoring data of the area for this round of remediation is mainly dependent on the soil monitoring data from the “Northeast Pharmaceutical POP site (Manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd) detailed environmental survey and risk assessment report” that was completed by the Shenyang Academy of Environmental Sciences on November 2017. There were a total of 113 soil sampling points in the remediation area and a total of 888 soil samples collected, with a representative area of 114,000 m2. Supplementary Figure 2 shows the area of soil remediation and distribution of sampling points. The Shanghai SEP Analytical Services Co., Ltd was commissioned to test the collected samples. According to the “Northeast Pharmaceutical POP site (Manufacturing zone of the north factory in Beier Road of Northeast Pharmaceuticals Group Co. Ltd) detailed environmental survey and risk assessment report”, there were a total of 212 analysis indicators for soil samples. See Table 3.1-1 for the list of soil sample tests. Among these tests, the maximum value of 23 indicators exceeded the standard values, including 7 heavy metals (arsenic, mercury, lead, total chromium, nickel, copper, and zinc), 2 VOCs (benzene, trichloromethane), 8 SVOCs (aniline, benz[a]anthracene, chrysene, benzo[b]fluoranthene, benzo[k]fluoranthene, benzo[a]pyrene, indeno[1,2,3-cd]pyrene, dibenz[a,h]anthracene), 5 pesticides (β-Hexachlorocyclohexane, 4'-DDD, 4,4'-DDE, 4,4'-DDT, 2,4'-DDT) and 1 TPH (TPH (

Shenyang Lvheng Environment Consulting Co. Ltd 55 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 35Table 3.1-1 List of soil sample tests Type Indicator Wet chemistry and pH (2 Moisture content, pH indicators) Heavy metals (8 indicators) Arsenic, mercury, lead, cadmium, total chromium, nickel, copper, zinc VOCs (Fumigants, 2,2-dichloropropane, 1,2-dichloropropane, cis-1,3-dichloropropene, halogenated aliphatic trans-1,3-dichloropropene, 1,2-dibromoethane, dichlorodifluoromethane, compounds, halogenated chloromethane, bromomethane, iodomethane, vinyl chloride, aromatic hydrocarbons, trichlorofluoromethane, chloroethane, dichloromethane, dibromomethane, monocyclic aromatic carbon tetrachloride, pentachloroethane, 1,1-dichloroethane, hydrocarbons, oxygenated 1,2-dichloroethane, 1,1,1-trichloroethane, 1,1,2-trichloroethane, compounds, sulfur-containing 1,1,1,2-tetrachloroethane, 1,1,2,2 tetrachloroethane, 1,3-dichloropropane, compounds, trihalomethanes, 1,2,3-trichloropropane, 1,2-dibromo-3-chloropropane, 1,1-dichloroethene, total 63 indicators) trans- 1,2-dichloroethylene, cis- 1,2-dichloroethylene, trichlorethylene, tetrachlorethylene, 1,1-dichloropropene, cis-1,4-dichloro-2-butene, trans-1,4-dichloro-2-butene, hexachlorobutadiene, chlorobenzene, bromobenzene, 2-chlorotoluene, 4-chlorotoluene, 1,2,3-trichlorobenzene, benzene, toluene, ethlybenzene, styrene, m-xylene and p-xylene, o-xylene, n-propylbenzene, cumene, n-butylbenzene, tert-butylbenzene, sec-butylbenzene, p-cymene, 1,3,5-trimethylbenzene, 1,2,4- trimethylbenzene, acetone, 2-butanone, 2-hexanone, 4-methyl-2- pentanone, vinyl acetate, carbon disulfide, trichloromethane (chloroform), tribromomethane (bromoform), bromodichloromethane, dibromochloromethane SVOCs (anilines and aniline, 2-nitroaniline, 3-nitroaniline, 4-nitroaniline, 4-chloroaniline, 3 benzidine, chlorinated 3’-dichlorobenzidine, dibenzofuran, carbazole, 1,3-dichlorobenzene, hydrocarbons, halogenated 1,4-dichlorobenzene, 1,2-dichlorobenzene, 1,2,4-trichlorobenzene, ethers, nitroaromatics and pentachlorobenzene, hexachlorobenzene, hexachloroethane, ketones, nitrosamines, hexachloropropene, hexachloro-1,3-butadiene, 2,2'-dichlorodiethyl ether, phenols, PAHs, phthalates, bis(2-chloroethoxy)methane, other SVOCs, total 96 4-chlorobiphenyl, 4-bromobiphenyl, dichloroisopropyl ether, nitrobenzene, indicators) 2,4-dinitrotoluene, 2,6-dinitrotoluene, 1,3,5-trinitrobenzene, pentachloronitrobenzene, azobenzene, 4-aminobiphenyl, dimethylaminoazobenzene, 2-methylpyridine, acetophenone, isophorone , 1-naphthylamine, 5-nitro o-toluidine, propyzamide, phenacetin, 4-nitroquinoline-N-oxide, methylethylnitrosoamine, N-nitrosodiethylamine, N-nitrosopyrrolidine, N-nitrosodipropylamine, N-nitrosomorpholine, N-nitrosopiperidine, N-nitrosodibutylamine, diphenylamine and nitrosodiphenylamine, methapyrilene, hexachlorocyclopentadiene, methylmethanesulfonate, ethylmethanesulfonate, trichlorobenzene, 1 , 2,4,5-tetrachlorobenzene, isodrin, diallate, trans-isosafrole, cis-isosafrole, safrole, phenol, 2-methylphenol, 3-methylphenol and 4-methylphenol, 2,4-dimethylphenol, 2-nitrophenol, 2-chlorophenol, 2,4-dichlorophenol, 2,6-dichlorophenol, 4-chloro-3-methylphenol, 2,4,5-trichlorophenol, 2,4,6-trichlorophenol, pentachlorophene, dimethyl phthalate, diethyl phthalate, di-n-butyl phthalate, butyl benzyl phthalate, di-n-octyl phthalate, bis (2-ethylhexyl) phthalate, naphthalene, 2- methylnaphthalene, 2- chloronaphthalene, acenaphthylene, acenaphthene, fluorene, phenanthrene, anthracene, fluoranthene, pyrene, N-(2-Fluorenyl)acetamide, benzo [a] anthracene, chrysene, benzo[b]fluoranthene, benzo[k]fluoranthene, 7,12-dimethylbenz[a]anthracene, benzo[a]pyrene, 3-methylcholanthrene, indeno (1,2,3-cd) pyrene, dibenz[a,h]anthracene, benzo[ghi]perylene Pesticides (organochlorine Α-hexachlorocyclohexane, β-hexachlorocyclohexane, pesticides and γ-hexachlorocyclohexane, δ-hexachlorocyclohexane, total organophosphorus pesticides, hexachlorocyclohexane, heptachlor, heptachlor epoxide, aldrin, dieldrin, total 42 indicators) endrin, endosulfan 1, endosulfan 2, endosulfan sulfate, 4,4'-DDD, 4,4'-DDE, 4,4'-DDT, 2,4'-DDT, total DDT, 2,4'-DDD, 2,4'-DDE, cis-chlordane, trans-chlordane, endrin ketone, methoxychlor, mirex, endrin aldehyde, dichlorvos, dimethoate, chlorpyrifos, chlorpyrifos-methyl, malathion, fenthion, ethion, chlorfenvinphos-E/Z1, chlorfenvinphos-E/Z2, chlorfenvinphos-E/Z3, monocrotophos, parathion, parathion methyl, fenamiphos, carbophenothion, azinphos TPH TPH(C16)

Shenyang Lvheng Environment Consulting Co. Ltd 56 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 36 Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value As 143.0 20 21 2.42 6.15 DB11/T 811-2011 Cu 10550.0 600 9 1.04 16.58 DB11/T 811-2011 Zn 5820.0 3500 4 0.46 0.66 DB11/T 811-2011 Ni 879.0 50 45 5.19 16.58 DB11/T 811-2011 Meet Cd 5.1 8 0 0 standar DB11/T 811-2011 ds Pb 1985.0 400 6 0.69 3.96 DB11/T 811-2011 Cr 589.0 250 4 0.46 1.36 DB11/T 811-2011 Mercury 38.5 10 6 2.44 2.85 DB11/T 811-2011 Aniline 64.5 5.8 5 26.33 10.12 HJ 350 Meet 4-nitroaniline 0.2 27 0 0 standar US EPA ds Meet 4-Chloroaniline 0.7 2.7 0 0 standar US EPA ds Meet Dibenzofuran 5.8 73 0 0 standar US EPA ds Meet Carbazole 5.4 32 0 0 standar HJ 350 ds Meet 1,3-dichlorobenzene 1.2 27 0 0 standar HJ 350 ds Meet 1,4-dichlorobenzene 8.7 27 0 0 standar HJ 350 ds Meet 1,2-dichlorobenzene 3.4 150 0 0 standar HJ 350 ds Meet 1,2,4-trichlorobenzene 0.2 68 0 0 standar HJ 350 ds

Shenyang Lvheng Environment Consulting Co. Ltd 57 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value Meet Pentachlorobenzene 0.1 0.2 0 0 standar DB11/T 811-2011 ds Meet Bis(2-chloroethyl)ether 0.1 2300 0 0 standar HJ 350 ds Meet Dichloroisopropyl ether 0.1 3100 0 0 standar US EPA ds Meet Nitrobenzene 0.2 3.9 0 0 standar HJ 350 ds Meet 1,3,5-trinitrobenzene 0.2 2200 0 0 standar US EPA ds Meet Azobenzene 4.6 20 0 0 standar C ds Meet Acetophenone 8.3 7800 0 0 standar US EPA (1-Phenylethan-1-one) ds Methapyrileneg 2.3 / / / / / β-Hexachlorocyclohexane 4.6 0.2 1 55 22 DB11/T 811-2011 Meet γ-Hexachlorocyclohexane 0.1 0.3 0 0 standar DB11/T 811-2011 ds 4,4'-DDD 121.0 2 40 23.67 59.5 DB11/T 811-2011 4,4'-DDE 33.5 1 52 35.37 32.5 DB11/T 811-2011 4,4'-DDT 143.0 1 33 42.86 142 DB11/T 811-2011 2,4'-DDT 35.1 1 15 37.5 34.1 DB11/T 811-2011 Trithion 0.2 / / / / / Meet Phenol 0.3 80 0 0 standar DB11/T 811-2011 ds Meet 2-methylphenol 15.2 1298 0 0 C standar

Shenyang Lvheng Environment Consulting Co. Ltd 58 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value ds Meet 3-Methylphenol and 68.8 1298 0 0 standar C 4-methylphenol ds Meet 2-nitrophenol 0.2 63 0 0 standar HJ 350 ds Meet 2-chlorophenol 4.1 39 0 0 standar HJ 350 ds Meet 2,4-dichlorophenol 1.4 23 0 0 standar HJ 350 ds Meet 53.7 10000 0 0 standar C

ds Meet Di-n-butyl phthalate 0.2 100 0 0 standar HJ 350 ds Meet Benzyl butyl phthalate 0.7 300 0 0 standar C ds Meet Di-n-octyl phthalate 0.1 135 0 0 standar C ds Meet Bis(2-ethylhexyl) phthalate 10.3 46 0 0 standar HJ 350

ds Meet Naphthalene 6.4 54 0 0 standar HJ 350 ds Meet Acenaphthylene 15.2 3600 0 0 standar US EPA ds Acenaphthene 1.3 / / Fluorene 15.6 210 0 0 Meet HJ 350

Shenyang Lvheng Environment Consulting Co. Ltd 59 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value standar ds Meet Phenanthrene 84.3 2300 0 0 standar HJ 350 ds Meet Anthracene 22.9 2300 0 0 standar HJ 350 ds Meet Fluoranthene 136.0 310 0 0 standar HJ 350 ds Meet Pyrene 121.0 230 0 0 standar HJ 350 ds Benz[a]anthracene 57.2 0.9 67 37.02 62.6 HJ 350 Chrysene 57.7 9 14 7.22 5.41 HJ 350 Benzo[b]fluoranthene 63.5 0.9 74 36.82 69.6 HJ 350 Benzo[k]fluoranthene 26.1 0.9 51 34 28 HJ 350 Benzo[a]pyrene 45.4 0.3 113 63.13 150.3 HJ 350 Indeno[1,2,3-cd]pyrene 32.4 0.9 44 35.2 35 HJ 350 Dibenz[a,h]anthracene 11.4 0.33 39 36.11 33.55 HJ 350 Meet Benzo[ghi]perylene 31.4 230 0 0 standar HJ 350 ds TPH (C16) 5400.0 10000 0 0 standar DB11/T 811-2011 ds Meet Chloromethane 1.5 12 0 0 standar DB11/T 811-2011 ds Meet 1,1-dichloroethane 0.1 43 0 0 standar DB11/T 811-2011 ds Meet 1,3-dichloropropane 0.1 5 0 0 DB11/T 811-2011 standar

Shenyang Lvheng Environment Consulting Co. Ltd 60 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value ds Meet Chlorobenzene 0.5 41 0 0 standar DB11/T 811-2011 ds Benzene 5.8 0.64 8 32 8.06 DB11/T 811-2011 Meet Toulene 122.0 850 0 0 standar DB11/T 811-2011 ds Meet Ethylbenzene 0.3 450 0 0 standar DB11/T 811-2011 ds Meet Styrene 0.1 1200 0 0 standar DB11/T 811-2011 ds Meet m-Xylene and p-Xylene 0.4 74 0 0 standar DB11/T 811-2011 ds Meet o-Xylene 0.1 74 0 0 standar DB11/T 811-2011 ds Meet n-Propylbenzene 0.1 3800 0 0 standar US EPA ds Meet sec-Butylbenzene 0.2 7800 0 0 standar US EPA ds p-Cymeneg 0.4 / / / / / Meet 1,3,5-Trimethylbenzene 1.1 19 0 0 standar HJ 350 ds Meet 1,2,4-Trimethylbenzene 1.8 22 0 0 standar HJ 350 ds Meet 4-Methyl-2-pentanone 2.2 33000 0 0 standar US EPA ds

Shenyang Lvheng Environment Consulting Co. Ltd 61 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 3.1-2 Maximum value and standard values of soil test indicators of site (mg/kg) Number Maxi of % of mum samples samples fold Maximu Standar that Source of standard Indicator that exceed m value d value exceeded values exceed ing the standards standa screening rds value Meet Carbon disulfide 3.4 94 0 0 standar C ds Trichloromethane 26.2 0.22 6 37.5 118.09 DB11/T 811-2011 Note: HJ350: A value; DB11/T 811: Beijing local standards residential land; C: sensitive land; US EPA: (updated in June 2015) residential land. (1) Heavy metals As shown in Table 3.1-2, among the 8 heavy metal indicators of the site, only cadmium values did not exceed standards, while the measured values of the other heavy metals exceeded standards. Among these metals, the fold exceeding standards for copper and nickel were 16.58. Spatial analysis of nickel pollution status was conducted according to the soil monitoring results of the site. From Figure 3.1-2, we can see that samples with Ni values exceeding the screening values are mainly concentrated at 4m and above, with the maximum value appearing at 2.5 m of a sampling point. The reduction in nickel concentration with increasing depth is not significant. The distribution of nickel at the central and northwest parts of the site is consistent with the layout of berberine manufacturing plants. In addition, the nickel level around the Weihua company is also relatively higher. Overall, it was observed that heavy metal levels decrease with increasing soil depth. However, the heavy metal levels in samples from deep levels in some sampling points are relatively higher. This may be due to the combined effects of historical soil backfilling and disturbances due to relocation.

Shenyang Lvheng Environment Consulting Co. Ltd 62 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 9Figure 3.1-1 Nickel soil distribution in site(>50mg/kg) (2) POP pollutants As shown in Table 3.1-3, among the POP pollutants within the site, β-Hexachlorocyclohexane, 4'-DDD, 4,4'-DDE, 4,4'-DDT, and 2,4'-DDT all had samples that exceed standards of more than 20% and above. Among these POPs, 4,4'-DDT has 42.86% of samples that exceed standards, and a fold of 142 while β-hexachlorocyclohexane had 55% of samples that exceed standards and a fold of 22. Spatial analysis of pollution status of β-hexachlorocyclohexane, 4'-DDD, 4,4'-DDE, 4,4'-DDT, and 2,4'-DDT was carried out according to the soil monitoring results of the site. As shown in Figure 3.1-2, samples where β-hexachlorocyclohexane was detected were concentrated at 4m and above. Samples where β-hexachlorocyclohexane values exceeded the screening values were mainly concentrated at 1.5m and above. Β-hexachlorocyclohexane distribution was more scattered and included the raw wastewater treatment zone at the northwest corner, workshop zone, quality control block, and research block. This may be caused by disturbances due to relocation.

Shenyang Lvheng Environment Consulting Co. Ltd 63 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 103.1-2 Distribution of -hexachlorocyclohexane in the Site (> 0.2 mg/kg) As shown in Figures 3.1-3, 3.1-4 and 3.1-5, the spatial distribution of DDT, DDD, and DDE is basically the same in the site, specifically: 1) they are mainly distributed in the original DDT production area, the outdiffusion area is nearly 20,000 m2, and the maximum depth is 7 m; 2) they are concentrated in the west side of the site and close to the western boundary, they may be leakage from transport trucks historically, and the maximum depth is 3 m; 3) they are concentrated in Weihua company and the warehouse in the northeast corner, the maximum depth is approximately 2 m, and the existence of them may be due to demolition disturbance.

Shenyang Lvheng Environment Consulting Co. Ltd 64 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 11Figure 3.1-3 Distribution of DDT (4,4’-DDT + 2,4’-DDT) in the Site (> 1.7mg/kg)

Figure 12Figure 3.1-4 Distribution of DDD in the Site (> 2mg/kg)

Shenyang Lvheng Environment Consulting Co. Ltd 65 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 13Figure 3.1-5 Distribution of DDE in the Site (> 1.4 mg/kg) (3) PAHs

As shown in Figure 3.1-2, the concentration of benzoapyrene (BaP) and other PAHs (including tetraphene, benzo[b]fluoranthene, dibenz[a,h]anthracene, and indeno(1,2,3-cd)pyrene) all exceeds the specified limits. Specifically, the over-limit rate of BaP is up to 63.13%, 150.3 times as much as the specified limit. In accordance with Risk Evaluation Report on POP-contaminated Site of Northeast

General Pharmaceutical Factory, the distribution of PAHs ischaracterized in that high-molecular-weight PAHs play a dominant role and BaP is closely correlated with other PAHs. This is mainly due to that the PAHs are mainly generated due to the sedimentation after incomplete combustion of fossil fuels. The distribution of PAHs in the current site also shows the above characteristics.

As shown in Figure 3.1-6, the concentration of BaP obviously tends to decrease with the increase in soil depth. At each point position, the maximum concentration basically arises at the layer depth of 0.5 m. This shows that the BaP pollution in the site is mainly influenced by regional atmospheric sedimentation. In addition, there are many soil samples with an over-limit BaP concentration, and the BaP concentration universally exceeds the specified limit in different areas of the site. It should be noted that at one or two point positions, the BaP concentration is still high at the layer depth of 6 m.

Shenyang Lvheng Environment Consulting Co. Ltd 66 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 14Figure 3.1-6 Distribution of BaP in the Site Soils (> 0.46 mg/kg) (4) VOCs

As described in Table 3.1-2, among the VOCs in the polluted site, the over-limit rates of benzene concentration and chloroform concentration are respectively 32% and 37.5%. According to the soil monitoring results, spatial analysis is conducted in respect of benzene and chloroform pollution.

As shown in Figures 3.1-7 and 3.1-8, the soil samples whose benzene concentration exceeds the screening values are distributed at the depth of 0.5 to 4 m, and the soil samples whose chloroform concentration exceeds the screening values are distributed at the depth of 2 to 5 m. At point positions

29 and 35, the concentration of VOCs exceeds the specified limits. The two point positions are both located in the original DDT production area, which was subsequently changed into the berberine production workshop. This explains why the concentration of VOCs exceeds the specified limits.

Shenyang Lvheng Environment Consulting Co. Ltd 67 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 15Figure 3.1-7 Distribution of Benzene in the Site Soils (> 0.64 mg/kg)

Figure 16Figure 3.1-8 Distribution of chloroform in the Site Soils (> 0.22 mg/kg) (5) Aniline

As described in Table 3.1-2, the over-limit rate of aniline concentration is 26.33%. According to the soil monitoring results, spatial analysis is conducted in respect of aniline pollution.

As shown in Figure 3.1-9, aniline is detected at point position 29 in the northwest corner, which is Shenyang Lvheng Environment Consulting Co. Ltd 68 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site the original DDT production area, and the aniline concentration exceeds the screening values at the depth of 2 to 6 m. This is mainly due to DDT residues.

Figure 17Figure 3.1-9 Distribution of Aniline in the Site Soils (> 5.8 mg/kg) (6) TPH

As described in Table 3.1-2, the over-limit rate of TPH (

According to the soil monitoring results, spatial analysis is conducted in respect of TPH (

As shown in Figure 3.1-10, the soil samples whose TPH (

Shenyang Lvheng Environment Consulting Co. Ltd 69 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 18Figure 3.1-10 Distribution of TPH (<16) in the Site Soils (> 230 mg/kg) 3.1.2 Risk Evaluation for Groundwater Pollution

The monitoring data on the groundwater within the remediation range is mainly available from

Risk Evaluation Report on POP-contaminated Site of Northeast General Pharmaceutical Factory, which was prepared by Shenyang Academy of Environmental Sciences in November 2017.

Shenyang Academy of Environmental Sciences has sampled the groundwater for three times. The first groundwater sampling was conducted on June 19th, 2017; six groundwater samples and one parallel sample (G2) were acquired. The second groundwater sampling was conducted on July 29th,

2017; G5 was sealed for unknown reasons, and thus the groundwater in G5 could not be sampled; then, five groundwater samples and one parallel sample (G6) were acquired. The third groundwater sampling was conducted on October 27th, 2017; G1, G4, and G5 were sealed for unknown reasons, and thus the groundwater in G1, G4, and G5 could not be sampled; then, three groups of groundwater soils (G2, G3, and G6) and one group of parallel samples (G2) were acquired. Figure

3.2-1 shows the groundwater sampling points, and Table 3.1-3 gives the basic data about groundwater sampling points.

Shenyang Lvheng Environment Consulting Co. Ltd 70 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 19Figure 3.1-11 Point Positions of Groundwater Sampling

Groundwater monitoring indexes include all the indexes (except microorganism and radioactivity) specified in Quality Standard for Groundwater (GB/T14848-93), as well as VOCs, SVOCs, petroleum, and hexachlorocyclohexane.

In accordance with Risk Evaluation Report on POP-contaminated Site of Northeast General

Pharmaceutical Factory, the conventional indexes of the groundwater of the site are evaluated as per the standard for Grade-III groundwater specified by Quality Standard for Groundwater

(GB/T14848-93), and the unconventional indexes (including benzene, chlorobenzene, dichlorobenzene, trichlorobenzene, naphthalene, and 1,2-dichloroethane) of the groundwater of the site are evaluated as per the standard for Grade-III groundwater specified by Standard for

Groundwater Quality. According to the test results (in Table 3.1-4, the highlighted parts mean that the

Shenyang Lvheng Environment Consulting Co. Ltd 71 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site index values exceed the specified limits), the values of certain conventional indexes (including permanganate index, chroma, chloride concentration, pH value, total hardness, total dissolved solids, concentration of ammonia nitrogen, concentration of volatile phenol, iron concentration, lead concentration, and manganese concentration) about the sampled groundwater are above the standard for Grade-III groundwater. The values of unconventional indexes (for example, the concentration of aniline, 1,2-dichloroethane, methylbenzene, and benzene) are all above the standard for Grade-III groundwater specified by Standard for Groundwater Quality.

Shenyang Lvheng Environment Consulting Co. Ltd 72 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 37 Table 3.1-3 Groundwater Monitoring Results (First Groundwater Sampling) Index Unit G1 G2 G3 G4 G5 G6 Grade III Hexavalent chromium mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.05 Permanganate index mg/L 21.9 33.5 4.2 3.2 6.3 14.1 3 Chroma PCU 17 30 3 3 4 3 15 Sulfate mg/L 144 54.4 113 172 76.2 39.6 250 Chloride mg/L 836 577 115 183 558 1560 250 Turbidity NTU 8.17 32.6 0.87 1.46 2.15 4.89 3 Fluoride mg/L 0.24 0.44 0.29 0.24 0.22 0.13 1 Total cyanide mg/L 0.005 <0.005 <0.005 <0.005 0.008 <0.005 0.05 Nitrate mg/L 1.34 0.45 0.17 0.46 0.4 0.35 20 pH value pH 6.17 6.5 6.73 6.62 6.51 6.35 6.5~8.5 Total hardness mg/L 1370 800 406 764 1080 2160 450 Total dissolved solids mg/L 2590 1670 680 1050 1830 3510 1000 Ammonia nitrogen mg/L 1.07 <0.01 1.94 0.24 2 0.4 0.5 Volatile phenol mg/L 0.145 0.063 <0.002 <0.002 <0.002 <0.002 0.002 Anionic surfactant mg/L <0.10 0.17 <0.10 <0.10 <0.10 0.11 0.3 Nitrite mg/L <0.01 <0.01 <0.01 0.35 0.03 0.01 1 Arsenic mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 Barium mg/L 0.3 0.34 0.08 0.12 0.32 0.54 0.7 Beryllium mg/L <0.0002 <0.0002 <0.0002 <0.0002 <0.0002 <0.0002 0.002 Cadmium mg/L <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 0.005 Cobalt mg/L <0.01 <0.01 <0.01 0.02 0.01 0.05 0.05 Copper mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 1 Iron mg/L 0.51 2.72 <0.05 <0.05 0.05 0.23 0.3 Lead mg/L <0.01 <0.01 <0.01 0.02 0.02 <0.01 0.01

Shenyang Lvheng Environment Consulting Co. Ltd 73 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 3.1-3 Groundwater Monitoring Results (First Groundwater Sampling) Index Unit G1 G2 G3 G4 G5 G6 Grade III Manganese mg/L 9.78 5.79 2.88 3.2 4.39 52.8 0.1 Molybdenum mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.2 Nickel mg/L 0.03 0.04 0.02 0.01 0.01 0.05 0.02 Selenium mg/L <0.01 <0.01 <0.01 <0.01 0.01 0.03 0.01 Zinc mg/L <0.01 <0.01 <0.01 0.04 0.03 0.04 1 Mercury mg/L <0.00005 <0.00005 <0.00005 <0.00005 <0.00005 <0.00005 0.001 Aniline * µg/L <1.0 227 <1.0 <1.0 <1.0 <1.0 130 1,3-dichlorobenzene # µg/L 1.2 6.2 <1.0 <1.0 <1.0 <1.0 300 1,4-dichlorobenzene µg/L 11.8 25.2 <1.0 <1.0 2.6 <1.0 300 DDT µg/L <2.0 <2.0 <2.0 7.1 <2.0 <2.0 1 4,4'-DDD µg/L <1.0 <1.0 <1.0 2.6 <1.0 <1.0 2,4'-DDT µg/L <1.0 <1.0 <1.0 4.5 <1.0 <1.0 2-trimethylolphenol† µg/L <1.0 80.8 <1.0 <1.0 <1.0 <1.0 2 3-methylphenol & 4-methylphenol† µg/L <1.0 65 <1.0 <1.0 <1.0 <1.0 2 Trans-1,2-dichloroethylene µg/L 1.2 <0.5 <0.5 <0.5 <0.5 <0.5 50 1,1-dichloroethane * µg/L 15.3 <0.5 <0.5 <0.5 0.6 5.1 2.8 Cis-1,2-dichloroethylene µg/L <0.5 <0.5 <0.5 3.4 0.9 <0.5 50 1,2-dichloroethane µg/L 19.4 1.5 0.5 34.8 11.3 4.6 30 chlorobenzene µg/L 26.1 101 <0.5 5.5 75.7 4.9 300 Benzene µg/L 43.2 8.3 <0.5 <0.5 18.6 <0.5 10 methylbenzene µg/L 47.5 1660 <0.5 1.2 0.9 0.6 700 Ethylbenzene µg/L 4.1 5.8 <0.5 <0.5 0.8 <0.5 300 Trichloromethane µg/L <0.5 <0.5 <0.5 0.8 <0.5 <0.5 60 Table 38 Table 3.1-4 Groundwater Monitoring Results (Second Groundwater Sampling)

Shenyang Lvheng Environment Consulting Co. Ltd 74 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Index Unit G1 G2 G3 G4 G6 Grade III Hexavalent chromium mg/L 0.015 <0.010 <0.010 0.013 0.045 0.05 Permanganate index mg/L 9 3.9 45.5 3.1 7.1 3 Chroma PCU 15 8 25 10 15 15 Sulfate mg/L 196 226 55.9 141 44.6 250 Chloride mg/L 786 162 690 105 1740 250 Turbidity NTU 0.69 <0.10 3.9 1.87 15.1 3 Fluoride mg/L 0.21 0.24 0.4 0.25 0.22 1 Total cyanide mg/L <0.005 <0.005 <0.005 <0.005 <0.005 0.05 Nitrate mg/L 0.74 1.32 0.78 0.33 0.83 20 pH value pH 5.99 6.77 6.74 6.66 6.07 6.5~8.5 Total hardness mg/L 1260 804 612 355 2590 450 Total dissolved solids mg/L 2340 1030 1860 634 3600 1000 Ammonia nitrogen mg/L 0.175 0.246 <0.010 1.21 0.144 0.5 Volatile phenol mg/L <0.0020 <0.0020 0.07 <0.0020 <0.0020 0.002 Anionic surfactant mg/L <0.10 <0.10 0.33 <0.10 <0.10 0.3 Nitrite mg/L <0.01 <0.01 <0.01 <0.01 <0.01 0.01 Arsenic mg/L 0.2 0.1 0.33 0.07 0.6 0.7 Barium mg/L <0.0002 <0.0002 <0.0002 <0.0002 <0.0002 0.002 Beryllium mg/L <0.005 <0.005 <0.005 <0.005 <0.005 0.005 Cadmium mg/L <0.01 0.02 <0.01 <0.01 0.05 0.05 Cobalt mg/L <0.01 <0.01 <0.01 <0.01 <0.01 1 Copper mg/L 0.12 <0.05 0.52 <0.05 0.1 0.3 Iron mg/L <0.01 <0.01 <0.01 <0.01 <0.01 0.01 Lead mg/L 1.22 2.86 8.38 1.83 56.7 0.1 Manganese mg/L <0.01 <0.01 <0.01 <0.01 <0.01 0.2 Molybdenum mg/L 0.02 0.01 0.05 0.02 0.05 0.02 Shenyang Lvheng Environment Consulting Co. Ltd 75 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 3.1-4 Groundwater Monitoring Results (Second Groundwater Sampling) Index Unit G1 G2 G3 G4 G6 Grade III Nickel mg/L <0.01 <0.01 <0.01 <0.01 0.05 0.01 Selenium mg/L 0.1 0.05 0.01 0.06 0.05 1 Zinc mg/L <5E-5 <5E-5 <5E-5 <5E-5 <5E-5 0.001 Aniline * µg/L <1.0 <1.0 38.7 <1.0 <1.0 130 1,4-dichlorobenzene µg/L <1.0 <1.0 3.3 <1.0 <1.0 300 acetyl benzene * µg/L 1 <1.0 5.8 <1.0 <1.0 1.90E+03 2-methyl phenol† µg/L <1.0 <1.0 23.1 <1.0 <1.0 2 3-methylphenol & 4-methylphenol† µg/L <1.0 <1.0 31.4 <1.0 <1.0 2 Fluorine * µg/L <1.0 <1.0 2.2 <1.0 <1.0 290 1,2-dichloropropane µg/L <0.5 1.5 <0.5 0.8 <0.5 5 1,1-dichloropropane * µg/L 0.7 <0.5 <0.5 <0.5 5.7 2.8 Cis-1,2-dichloroethylene µg/L <0.5 3 <0.5 <0.5 <0.5 50 1,2-dichloroethane µg/L 1.5 30.8 2.1 0.8 4.1 30 trichloro ethylene µg/L <0.5 <0.5 0.5 <0.5 <0.5 300 Chlorobenzene µg/L 6.2 1.3 44 <0.5 3.4 300 Benzene µg/L 0.8 <0.5 3.3 <0.5 0.7 10 Methylbenzene µg/L <0.5 <0.5 596 <0.5 0.9 700 Ethylbenzene µg/L <0.5 <0.5 1.9 <0.5 <0.5 300 Acetone * µg/L <50 <50 200 <50 <50 1.40E+04 carbon disulfide * µg/L <0.5 <0.5 <0.5 <0.5 2.8 810 Trichloromethane µg/L <0.5 1.5 <0.5 <0.5 <0.5 60

Shenyang Lvheng Environment Consulting Co. Ltd 76 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 39 Table 3.1-5 Groundwater Monitoring Results (Third Groundwater Sampling) Index Unit G2 G3 G6 Grade III Hexavalent chromium mg/L <0.01 <0.01 <0.01 0.05 Permanganate index mg/L 59.5 3.2 168 3 Chroma PCU 70 9 75 15 Sulfate mg/L 6.8 130 45.7 250 Chloride mg/L 711 77.5 68.6 250 Turbidity NTU 22.4 1.6 30.8 3 Fluoride mg/L 0.85 0.46 0.6 1 Total cyanide mg/L <0.005 <0.005 0.008 0.05 Nitrate mg/L 1.18 0.25 <0.01 20 pH value pH 7.29 7.68 7.04 6.5~8.5 Total hardness mg/L 721 372 344 450 Total dissolved solids mg/L 1670 592 452 1000 Ammonia nitrogen mg/L 2.71 0.44 0.63 0.5 Volatile phenol mg/L 0.5 0.13 3.44 0.002 Anionic surfactant mg/L 0.2 <0.1 <0.1 0.3 Arsenic mg/L <0.01 <0.01 0.02 0.01 Barium mg/L 0.33 0.06 0.11 0.7 Iron mg/L 4.81 0.23 0.07 0.3 Lead mg/L <0.01 0.02 <0.01 0.01 Manganese mg/L 6.46 1.9 2.72 0.1 Nickel mg/L 0.03 0.01 <0.01 0.02 Mercury mg/L <0.0001 <0.0001 0.0035 0.001 Aniline * µg/L 17.5 <1.0 <10.0 130 1,4-dichlorobenzene µg/L 1.7 <1.0 <10.0 300 2-methyl phenol† µg/L 3.2 <1.0 <10.0 2 3-methylphenol & 4-methylphenol† µg/L 5.1 <1.0 81.1 2 Fluorine * µg/L <1.0 2.2 <1.0 290 1,2-dichloroethane µg/L 2.8 0.8 <0.5 30 Trichloro ethylene µg/L 0.6 <0.5 <0.5 300 Chlorobenzene µg/L 19.8 <0.5 118 300 Benzene µg/L 0.9 <0.5 22 10 Methylbenzene µg/L 176 <0.5 137000 700 Ethylbenzene µg/L 1.5 <0.5 691 300 M-Xylene and para-xylene µg/L <1.0 <1.0 14.3 500 O-Xylene µg/L <0.5 <0.5 2.4 Isopropyl benzene µg/L <0.5 <0.5 4.2

Sec-butylbenzene * µg/L <0.5 <0.5 0.6 2E3 Carbon disulfide* µg/L 1.3 <0.5 <0.5 810 Trichloromethane µg/L <0.5 <0.5 9.2 60

Shenyang Lvheng Environment Consulting Co. Ltd 77 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site .1.3 Human Health Risk Evaluation

In accordance with Technical Guidelines for Risk Assessment of Contaminated Sites (HJ

25.3-2014), the soils of the polluted site should be subjected to human health risk evaluation. The evaluation items include hazard identification, exposure evaluation, toxicological evaluation, risk characterization, and calculation of risk control values for soils and groundwater.

2. Risk Calculation Model

In accordance with the Technical Guidelines for Risk Assessment of Contaminated Sites (HJ

25.3-2014), the following section describes the calculation of pollutant exposure and risk characterization model in respect of residential lands: (1) Calculation of Pollutant Exposure

1) Oral intake of polluted soils

For the carcinogenic effect of a single pollutant, it is necessary to consider the lifelong hazard of exposure in childhood and adulthood. The soil exposure associated with oral intake of soils can be calculated by the following equation: OSIRc EDc  EFc OSIRa  EDa  EFa ()+ABSO BWc BWa −6 OISERca = 10 ATca where: OISERca⎯ Soil exposure associated with oral intake of soils (carcinogenic effect) (unit: kg (soils)·kg-1 (body weight)·d-1); OSIRc⎯ Daily soil intake per child (unit: mg·d-1); OSIRa⎯ Daily soil intake per adult (unit: mg·d-1); EDc⎯ Child's exposure duration (unit: a); EDa⎯ Adult's exposure duration (unit: a); EFc⎯ Child's exposure frequency (unit: d·a-1); EFa⎯ Adult's exposure frequency (unit: d·a-1); BWc⎯ Child weight (unit: kg); BWa⎯ Adult weight (unit: kg); ABSo⎯ Absorption efficiency factor of oral intake, dimensionless; ATca⎯ Average time of carcinogenic effect (unit: d);

For the non-carcinogenic effect of a single pollutant, it is necessary to consider the hazard of exposure in childhood. The soil exposure associated with oral intake of soils can be calculated by the following equation:

Shenyang Lvheng Environment Consulting Co. Ltd 78 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site OSIRc EDc  EFc  ABSo OISERnc = 10−6 BWc ATnc where: OISERnc⎯ Soil exposure associated with oral intake of soils (non-carcinogenic effect), kg (soils)·kg-1 (body weight)·d-1; ATnc⎯ Average time of non-carcinogenic effect (unit: d);

2) Dermal contact with the polluted soils

For the carcinogenic effect of a single pollutant, it is necessary to consider the lifelong hazard of exposure in childhood and adulthood. The soil exposure associated with dermal contact with polluted soils can be calculated by the following equation: SAEc SSARc  EFc  EDc  Ev  ABSd SAEa  SSARa  EFa  EDa  Ev  ABSd DCSERca = 10−−66 +  10 BWc ATca BWa ATca where: DCSERca⎯ Soil exposure associated with dermal contact (carcinogenic effect), kg (soils)·kg-1, (body weight)·d-1; SAEc⎯ Surface area of child's exposed skin (cm2); SAEa⎯ Surface area of adult's exposed skin (cm2); SSARc⎯ Soil adhesion coefficient of child's skin surface (unit: mg·cm-2); SSARa⎯ Soil adhesion coefficient of adult's skin surface (unit: mg·cm-2); ABSd⎯ Absorption efficiency factor of dermal contact, dimensionless; Ev⎯ Dermal contact frequency per day (unit: time d-1); 0.417 0.517 SAEc = 239 Hc  BWc  SERc 0.417 0.517 SAEa = 239 Ha  BWa  SERa where: Hc⎯ Child's average height (unit: cm); Ha⎯ Adult's average height (unit: cm); SERc⎯ Area ratio of child's exposed skin, dimensionless; SERa⎯ Area ratio of adult's exposed skin, dimensionless;

For the non-carcinogenic effect of a single pollutant, it is necessary to consider the hazard of exposure in childhood. The soil exposure associated with dermal contact with polluted soils can be calculated by the following equation: SAEc SSARc  EFc  EDc  Ev  ABSd DCSERnc =10−6 BWc ATnc

3) Inhalation of polluted soil particles

For the carcinogenic effect of a single pollutant, it is necessary to consider the lifelong hazard of

Shenyang Lvheng Environment Consulting Co. Ltd 79 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site exposure in childhood and adulthood. The soil exposure associated with inhalation of polluted soil particles can be calculated by the following equation: PM10 DAIRa  EDa  PIAF  ( fspo  EFOa + fspi  EFIa ) PISERca =10−6 BWa ATca

PM10 DAIRc  EDc  PIAF  ( fspo  EFOc + fspi  EFIc ) +10−6 BWc ATca

For the non-carcinogenic effect of a single pollutant, it is necessary to consider the hazard of exposure in childhood. The soil exposure associated with inhalation of polluted soil particles can be calculated by the following equation: PM10 DAIRc  EDc  PIAF  ( fspo  EFOc + fspi  EFIc ) PISERnc = 10−6 BWc ATnc

4) Inhalation of gaseous pollutants in outdoor air

For the carcinogenic effect of a single pollutant, it is necessary to consider the lifelong hazard of exposure in childhood and adulthood. For the inhalation of gaseous pollutants in outdoor air available from topsoils and subsoils, the associated soil exposure and groundwater exposure can be respectively calculated by the following equations: DAIRc EFOc  EDc DAIRa  EFOa  EDa IoVERca1= VF +() suroa BWc ATca BWa ATca DAIRc EFOc  EDc DAIRa  EFOa  EDa IoVERca2 = VF +() suboa BWc ATca BWa ATca

For the non-carcinogenic effect of a single pollutant, it is necessary to consider the hazard of exposure in childhood. For the inhalation of gaseous pollutants in outdoor air available from topsoils and subsoils, the associated soil exposure and groundwater exposure can be respectively calculated by the following equations: DAIRc EFOc EDc IoVERnc1= VF  suroa BWc ATnc DAIRc EFOc EDc IoVERnc2 = VF  suboa BWc ATnc

5) Inhalation of pollutant vapor in indoor air

For the carcinogenic effect of a single pollutant, it is necessary to consider the lifelong hazard of exposure in childhood and adulthood. For the inhalation of gaseous pollutants in indoor air available from subsoils, the associated soil exposure and groundwater exposure can be respectively calculated by the following equations:

Shenyang Lvheng Environment Consulting Co. Ltd 80 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site DAIRc EFOc  EDc DAIRa  EFOa  EDa IIVERca1 = VF +() subia BWc ATca BWa ATca

For the non-carcinogenic effect of a single pollutant, it is necessary to consider the hazard of exposure in childhood. For the inhalation of gaseous pollutants in indoor air available from subsoils, the associated soil exposure and groundwater exposure can be respectively calculated by the following equations: DAIRc EFOc EDc IIVERnc1 = VF  subia BWc ATnc

(2) Risk Characterization Model

1) Oral intake

The carcinogenic risk of oral intake of a single pollutant in soils can be calculated by the following equation:

CROIS= OISER ca  C sur  SF o where: -1 Csur indicates the pollutant concentration in topsoils (unit: mg·kg ), whose value is determined through site investigation. The non-carcinogenic hazard quotient of oral intake of a single pollutant in the polluted soils can be calculated by the following equation: OISER C nc sur HQOIS = RfDo  SAF where: SAF indicates the distribution coefficient of the reference dose exposed to soils. 2) Dermal contact

The carcinogenic risk of dermal contact with a single pollutant in soils can be calculated by the following equation:

CRDCS= DCSER ca  C sur  SF d

The non-carcinogenic hazard quotient of dermal contact with a single pollutant in the polluted soils can be calculated by the following equation: DCSER C nc sur HQDCS = RfDd  SAF 3) Inhalation of soil particles The carcinogenic risk of inhalation of a single pollutant in soil particles can be calculated by the following equation:

CRPIS = PISER ca  C sur  SF i

The non-carcinogenic hazard quotient of inhalation of a single pollutant in the polluted soil particles can be calculated by the following equation: Shenyang Lvheng Environment Consulting Co. Ltd 81 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site PISER C nc sur HQPIS = RfDi  SAF 4) Inhalation of outdoor air

The carcinogenic risk of inhalation of a single gaseous pollutant in outdoor air can be calculated by the following equation:

CRiov11= IoVER ca  C sur  SF i

CRiov22= IoVER ca  C sub  SF i where: -1 Csub indicates the pollutant concentration in subsoils (unit: mg·kg ), whose value is determined through site investigation. The non-carcinogenic hazard quotient of inhalation of a single gaseous pollutant in outdoor air can be calculated by the following equation: IoVER C nc1 sur HQiov1 = RfDi  SAF IoVER C nc2 sub HQiov2 = RfDi  SAF

5) Inhalation of indoor air

The carcinogenic risk of inhalation of a single gaseous pollutant in indoor air can be calculated by the following equation:

CRiiv11= IIVER ca  C sub  SF i

The non-carcinogenic hazard quotient of inhalation of a single gaseous pollutant in indoor air can be calculated by the following equation: IIVER C nc1 sub HQiiv1 = RfDi  SAF 3. Risk Calculation Results

Using the risk calculation model and related parameters, we calculated the carcinogenic risks and non-carcinogenic hazard quotients regarding the pollutants concerned in the polluted soils of residential lands and municipal utility lands (as described in Table 3.1-6

Shenyang Lvheng Environment Consulting Co. Ltd 82 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 40Table 3.1-6 Carcinogenic Risks and Non-carcinogenic Hazard Quotients of the Pollutants Concerned in Soils of Residential Lands (Concentration Unit: mg/kg) Exposure Carcinogenic Non-carcinogenic Index Concentration Risk Risk (mg/kg) Arsenic 143 3.88E-04 37.75 Copper 10550 / 15.91 Zinc 5820 / 1.17 Nickel 879 8.71E-06 9.71 Mercury 38.5 / 7.83 Benzene 5.76 2.01E-05 1.68 Methylbenzene 122 / 0.21 Chloroform 26.2 7.56E-04 6.51 Aniline 64.5 1.46E-06 9.19 Benz[a]anthracene 57.2 1.25E-05 / Chrysene 57.7 1.46E-07 / Benzoapyrene 45.4 9.88E-05 33.25 Benzo[b]fluoranthene 63.5 1.38E-05 / Benzo[k]fluoranthene 27.0 5.88E-07 / Dibenz[a,h]anthracene 32.4 7.04E-05 / Indeno(1,2,3-cd)pyrene 11.4 2.48E-06 / DDT1 145 8.48E-05 18.77 p,p’-DDD 121 5.9E-05 / p,p’-DDE 35.5 2.46E-05 / -hexachlorocyclohexane 4.55 1.74E-05 / petroleum hydrocarbon (C8 to C16 aromatic hydrocarbon) 251 / 0.84 petroleum hydrocarbon (C17 to C35 aromatic hydrocarbon) 12 / 0.04 1 DDT = o,p’-DDT + p,p’-DDT Among the pollutants concerned, the carcinogenic or non-carcinogenic risks of methylbenzene, chrysene, benzo[k]fluoranthene, and petroleum hydrocarbons are acceptable, whereas the carcinogenic risks of other pollutants are higher than 10-6 (the non-carcinogenic hazard quotients of them are greater than 1). Specifically, the carcinogenic risks of arsenic and chloroform are higher than 10-4, the carcinogenic risks of benzoapyrene, DDT, and DDD are approximate to 10-4, the non-carcinogenic hazard quotients of copper, benzoapyrene, DDT, and arsenic are greater than 10, and the non-carcinogenic hazard quotients of aniline and nickel are approximate to 10.

3.2 Content and Objectives of Polluted Site Remediation

According to Remediation Plan for the POP-contaminated Site (North Production Area of the

Factory in Bei'er Road of Northeast Pharmaceutical Group Co., Ltd.) of Northeast General

Pharmaceutical Factory, the present soil remediation project includes the remediation of the polluted Shenyang Lvheng Environment Consulting Co. Ltd 83 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site soils, but excludes the treatment and remediation of groundwater and demolition of above-ground buildings.

3.2.1 Objectives and Principles of Engineering Treatment 1. Objectives of Engineering Treatment According to the land utilization planning and economic development status of Tiexi District, the present remediation project is intended to attain the following objectives on the principle of restoration of land functions and assurance of environmental safety: (1) Eliminate the direct influence of the polluted site on human health; (2) Prevent the migration of pollutants; (3) Remedy the polluted soils, and ensure environmental safety. 2. Principles of Engineering Treatment (1) Combine the control of environmental risks with the restoration of land functions, attain optimal environmental, social, and economic benefits, and suit the mediation measures to the land utilization in local land planning; (2) Combine the current remediation effect with the long-term pollution control objectives, put the remedied lands into use immediately, and control environmental risks gradually through a long-acting mechanism; (3) Grade and classify the remediation objects; apply scientific, advanced, and economically feasible treatment technologies, and take effective engineering measures respectively for them; (4) Take specific engineering measures that prove to be feasible by application examples, and suit the measures to local implementation conditions; (5) The investment in site remediation is economically feasible, and operating expenses are reasonable.

3.2.2 Target Values of Site Remediation

1. Target Values

In accordance with Remediation Plan for the POP-contaminated Site (North Production Area of the Factory in Bei'er Road of Northeast Pharmaceutical Group Co., Ltd.) of Northeast General

Pharmaceutical Factory, the target values of site remediation are listed in Table 3.2-1.

Shenyang Lvheng Environment Consulting Co. Ltd 84 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 41Table 3.2-1 Target Values of Soil Remediation National Pollutant Risk Control Remediatio DB11/T 811 HJ 350 Screening Source Concerned Value n Goal Value Arsenic 0.37 (TR=10-6) 20 20 20* 20 DB11/T 811 Copper 663 (THQ=1) 600 63 2,000 600 DB11/T 811 Zinc 4974 (THQ=1) 3,500 200 / 3,500 DB11/T 811 Nickel 131.6 50 50 131 131 Risk control value (TR=10-6) Lead / 400 140 400 400 DB11/T 811 Total chromium / 250 190 / 250 DB11/T 811 Mercury 4.93 (THQ=1) 10 1.5 7.3 4.9 Risk control value Benzene 0.29 (TR=10-6) 0.64 0.2 0.92 0.64 DB11/T 811 0.035 Chloroform 0.22 2 0.2 0.2 DB11/T 811 (TR=10-6) Aniline 7.0 (THQ=1) 4 5.8 87 7 Risk control value Tetraphene 4.6 (TR=10-6) 0.5 0.9 5.2 4.6 Risk control value Benzoapyrene 0.46 (TR=10-6) 0.2 0.3 0.52 0.46 Risk control value Benzo[b]fluorant 4.6 (TR=10-6) 0.5 0.9 5.2 4.6 Risk control value hene Dibenz[a,h]anth 0.46 (TR=10-6) 0.05 0.33 0.52 0.46 Risk control value racene Indeno(1,2,3-cd 4.6 (TR=10-6) 0.2 0.9 5.2 4.6 Risk control value )pyrene DDT 1.7 (TR=10-6) 1 1† 2 1.7 Risk control value DDD 2.0 (TR=10-6) 2 / 2.3 2 Risk control value DDE 1.4 (TR=10-6) 1 / 1.6 1.4 Risk control value -hexachloroc 0.26 (TR=10-6) 0.2 1# 0.31 0.26 Risk control value yclohexane Petroleum hydrocarbon < / 230 / / 230 DB11/T 811 C16 Note: 1. TR⎯ Carcinogenic risk, THQ⎯ Hazard quotient 2. HJ350⎯ A value specified in Environmental Quality Evaluation Criteria for Soils of Expo Lands (Interim); DB11/T 811⎯ Screening value for residential lands specified in Beijing's local standard (Screening Levels for Soil Environment Risk Assessment); National screening value⎯ Category-1 land specified in Risk Control Standard for Soil Contamination of Development Land: Risk Screening Values for Soil Contamination of Development Land (Interim) (Exposure Draft). 3. The DDT content is equal to o,p’-DDT content plus p,p’-DDT content. 4. * indicates the background value, # indicates the total content of hexachlorocyclohexane, and † indicates the total content of DDT. Heavy metal pollutants include arsenic, chrome, nickel, lead, and mercury; organic pollutants include tetraphene, chrysene, benzo[b]fluoranthene, benzo[k]fluoranthene, benzoapyrene, indeno(1,2,3-cd)pyrene, dibenz[a,h]anthracene, 1,4-dichlorobenzene, hexachlorobenzene, hexachlorocyclohexane, and total petroleum hydrocarbon. 2. Admission Criteria of Domestic Waste Landfill Site

In the current site, there are 6,382 m3 polluted soils in total that can be directly transported to

Shenyang Lvheng Environment Consulting Co. Ltd 85 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Daxin domestic waste landfill for use as casing soils, if they meet any of the following conditions: 1) after on-site but ex-situ remediation, the target values of soil remediation are attained; 2) the concentration of benzoapyrene is less than 50 mg/kg, the leaching concentration of PAHs is below the standard for Category-III groundwater specified in Standard for Groundwater Quality, and the heavy metal concentration is below the specified B values for expo lands. The polluted soils above should not be transported to Daxin domestic waste landfill unless they meet the related standards.

Soils should be treated properly in the domestic waste landfill in accordance with Standard for

Pollution Control on the Landfill Site of Municipal Solid Waste.

3.2.3 Main Content of Polluted Site Remediation

According to Remediation Plan for the POP-contaminated Site (North Production Area of the

Factory in Bei'er Road of Northeast Pharmaceutical Group Co., Ltd.) of Northeast General

Pharmaceutical Factory, the treatment and remediation of the POP-contaminated soils involve seven heavy metals (including arsenic, copper, zinc, nickel, lead, chrome, and mercury), five PAHs

(including tetraphene, benzoapyrene, benzo[b]fluoranthene, dibenz[a,h]anthracene, and indeno(1,2,3-cd)pyrene), two types of POPs (including DDT, DDD, DDE and

-hexachlorocyclohexane), aniline, two VOCs (including benzene and chloroform), and TPH(< C16).

In the current land lot, there are 82 polluted point positions in total. Specifically, the pollution depth of

75 point positions is at least 1.5 m, and the pollution depth of five point positions is up to 5 m.

 In-situ remediation

The soils polluted by a single heavy metal (mainly Nickel) total up to 6,382 m3. The leaching concentration in the soils merely polluted by nickel is above the admission criteria of landfills. To control risks more effectively, however, it is necessary to stabilize all the soils polluted by a single heavy metal that surpass the standard for industrial lands. This work is carried out in the current site.

Shenyang Lvheng Environment Consulting Co. Ltd 86 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 42Table 3.2-2 Data on Land Remediation by Stabilization Point Pollution Remediation Depth Excavated Soil Remediation Effect Position Depth (m) (m) Quantity (m3) 9 0.5 0.5 343 9 1.5 1.5 343 9 2.5 2.5 343 9 3 3 343 9 4 4 687 17 1 1 385 24 2 2 403 The heavy metal polluted 33 0.5 0.5 522 soils are subjected to on-site but 67 1.5 1.5 350 ex-situtreatment first, and then 81 3 3 295 transported to Laohuchong 82 5 5 820 domestic waste landfill. 95 0.5 0.5 847 98 1.5 1.5 163 98 2 2 163 98 2.5 2.5 163 98 3 3 212 Total 6,382  Ex-suit remediation

1) Chemical oxidation

The soils polluted by PAHs, DDTs, and TPHs, the remediation goal can undergo chemical oxidation if the degradation rate of 35% is enough to attain the remediation goal. The quantity of soils to be excavated is estimated to be 13,800 m3. After reaching the specified standard, the oxidated soils are backfilled in the new factory. This work is carried out in the new factory.

Shenyang Lvheng Environment Consulting Co. Ltd 87 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 43Table 3.2-3 Data on Land Remediation by Chemical Oxidation Point Pollution Depth Remediation Depth Excavated Soil Quantity Remediation Effect Position (m) (m) (m3) 3 0.5 0.5 249

3 1.5 1.5 324

12 1 1 381

12 2.5 2.5 495

24 1 1 310

25 0.5 0.5 315

27 1 1 377 For the soils polluted by 28 0.5 0.5 424 PAHs, 35 6 6 319 DDTs, and TPHs, the 35 7 7 546 remediation 39 0.5 0.5 742 goal can be attained 46 2 2 398 if the degradation rate 57 1.5 1.5 547 reaches 35% through 61 0.5 0.5 593 chemical oxidation. 62 1 1 719 After reaching the specified 81 5 5 590 standard, the oxidated soils 83 0.5 0.5 847 are backfilled in the new 88 1 1 891 factory. 89 1.5 1.5 341

94 1 1 680

102 1.5 1.5 1,091

107 0.5 0.5 714

112 1 1 928

113 3 3 990

Total 13,800

2) Thermal desorption

The organically polluted soils or compositely polluted soils should be subjected to thermal desorption. After reaching the specified standard, the treated soils are discharged as residual soils.

The quantity of soils to be excavated is estimated to be 50,000 m3. This work is carried out in the new factory.

Shenyang Lvheng Environment Consulting Co. Ltd 88 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 44Table 3.2-4 Data on Land Remediation by Thermal Desorption Point Pollution Depth Remediation Depth Excavated Soil Quantity Remediation Effect Position (m) (m) (m3) 1 0.5 0.5 246 1 1 1 246 1 1.5 1.5 246 1 2 2 246 1 2.5 2.5 246 1 3 3 320 2 0.5 0.5 251 4 0.5 0.5 253 4 1 1 253 4 1.5 1.5 329 5 0.5 0.5 245 8 2.5 2.5 365 8 4 4 730 8 5 5 949 9 1 1 343 15 0.5 0.5 292 16 0.5 0.5 292 The organically polluted 16 1 1 292 soils or multi-heavy-metal 16 4 4 758 polluted soils should be 17 0.5 0.5 296 subjected to thermal desorption. After reaching 21 0.5 0.5 272 the specified standard, the 21 1 1 354 treated soils aredischarged 22 1 1 498 as residual soils. This work 23 0.5 0.5 341 is carried out in he new factory. 29 2 2 289 29 2.5 2.5 289 29 3 3 289 29 4 4 579 29 5 5 579 32 0.5 0.5 345 32 1 1 449 34 0.5 0.5 509 35 0.5 0.5 159 35 1 1 159 35 2.5 2.5 159 35 4 4 319 35 5 5 319 35J 0.5 0.5 173 35J 1 1 225 36 0.5 0.5 390 36 1 1 390

Shenyang Lvheng Environment Consulting Co. Ltd 89 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 3.2-5 Data on Land Remediation by Thermal Desorption Point Pollution Remediation Excavated Soil Quantity Remediation Effect Position Depth (m) Depth (m) (m3) 36 1.5 1.5 390 36 2 2 390 36 2.5 2.5 390 36 3 3 507 41 2.5 2.5 359 42 1.5 1.5 536 45 0.5 0.5 509 46 0.5 0.5 306 46 1 1 306 46 1.5 1.5 306 48 0.5 0.5 418 49 0.5 0.5 419 53 0.5 0.5 526 55 0.5 0.5 526 56 0.5 0.5 110 56 1 1 110 56 1.5 1.5 144 56J1 0.5 0.5 106 The organically polluted 56J1 1 1 137 soils or multi-heavy-metal polluted soils should be 61 1 1 593 subjected to thermal 61 1.5 1.5 593 desorption. After reaching 61 2 2 771 the specified standard, the treated soils ardischarged 62 0.5 0.5 553 as residual soils. This work 0.5 64 0.5 853 is carried out in the new 65 0.5 0.5 262 factory. 65 1 1 262 65 2 2 341 65J 0.5 0.5 302 65J 1 1 392 66 1 1 668 67 0.5 0.5 269 72 0.5 0.5 655 72 1 1 852 73 0.5 0.5 804 76 0.5 0.5 652 77 0.5 0.5 225 77 1 1 225 77 1.5 1.5 225 81 2 2 295 81 2.5 2.5 295 81 4 4 590 81 6 6 767

Shenyang Lvheng Environment Consulting Co. Ltd 90 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 3.2-5 Data on Land Remediation by Thermal Desorption Point Pollution Depth Remediation Depth Excavated Soil Quantity Remediation Effect Position (m) (m) (m3) 82 0.5 0.5 316 85 1.5 1.5 343 85 2 2 343 85 2.5 2.5 343 85 3 3 343 85J 0.5 0.5 304 85J 1 1 304 85J 1.5 1.5 304 85J 2 2 395 89 0.5 0.5 341 89 1 1 341 89 2.5 2.5 341 89 3 3 444 92 0.5 0.5 611

93 0.5 0.5 602 The organically polluted soils 93 1.5 1.5 602 or multi-heavy-metal polluted soils should be subjected to 93 3 3 783 thermal desorption. After 94 0.5 0.5 680 reaching 94 2.5 2.5 883 the specified standard, the treated soils are discharged 105 0.5 0.5 833 as residual soils. This work 107 2.5 2.5 928 is carried out in the new 108 0.5 0.5 240 factory. 108 1 1 240 108 1.5 1.5 240 108 2 2 240 108 2.5 2.5 240 108 3 3 240 108 4 4 481 108 5 5 481 108 6 6 625 112 1.5 1.5 928 112 2 2 1,206 113 0.5 0.5 762 113 2 2 762 Total 50,000  Direct excavation and backfill

The soils that surpass the excavation target of residential lands but fall short of the standard for industrial lands (excluding the soils polluted by DDTs) amount to 25,300 m3. Such soils are directly transported to the new factory for use as backfill soils. To further control the environmental risks of

Shenyang Lvheng Environment Consulting Co. Ltd 91 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site such soils, they should be backfilled as concentratedly as possible, and should not be naked or backfilled to the water-bearing layer or capillary layer. Table 45Table 3.2-6 Data on Land Remediation by Direct Excavation and Backfill Point Pollution Depth Remediation Depth Excavated Soil Remediation Effect Position (m) (m) Quantity (m3) 2 1.5 502 326 3 1 499 249 5 1 489 245 5 1.5 489 318 9 7 687 897 18 1 812 528 23 1 681 443 24 1.5 620 310 27 0.5 579 290 29 1 579 289 29 1.5 579 289 29 6 579 752 30 2 635 317 30 6 635 825 31 0.5 646 323 31 1.5 646 420 35 1.5 319 159 The soils that surpass the 35 2 319 159 excavation target of residential 35 3 319 159 lands but fall short of the 37 0.5 803 402 standards for industrial lands 37 1 803 522 (excluding the soils polluted by DDTs) are directly transported to 41 0.5 719 359 the new factory. 41 5 719 934 45 2.5 1,018 509 56J2 0.5 409 205 56J2 1 409 266 58 0.5 1,198 779 66 0.5 1,028 514 74 0.5 913 594 77 4 154 496 81 2.5 95 95 82 1.5 631 316 82 3 631 316 82 4 631 631 85 4 686 892 89 2 450 341 92 1 1,223 795 94 2 1,359 680 96 0.5 1,268 824

Shenyang Lvheng Environment Consulting Co. Ltd 92 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site Table 3.2-6 Data on Land Remediation by Direct Excavation and Backfill Point Pollution Depth Remediation Excavated Soil Remediation Effect Position (m) Depth (m) Quantity (m3) 98 0.5 327 163 98 1 327 163 102 1 1,679 839 The soils that surpass the 104 0.5 1516 985 excavation target of residential 106 0.5 885 795 lands but fall short of the 107 1 975 617 standards for industrial lands 109 0.5 1,182 996 (excluding the soils polluted by 111 1 1,278 1,040 DDTs) are directly transported 113 1.5 701 761 to the new factory. 113 2.5 701 761 Total 25,300 Figures 3.3-1 to 3.3-10 show the excavation scope of the soils at different layers respectively.

Figure 20Figure 3.2-1 Excavation Scope of the Soils at the First Layer

Shenyang Lvheng Environment Consulting Co. Ltd 93 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 21Figure 3.2-2 Excavation Scope of the Soils at the Second Layer

Figure 22Figure 3.2-3 Excavation Scope of the Soils at the Third Layer

Shenyang Lvheng Environment Consulting Co. Ltd 94 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 23Figure 3.2-4 Excavation Scope of the Soils at the Fourth Layer

Figure 24Figure 3.2-5 Excavation Scope of the Soils at the Fifth Layer

Shenyang Lvheng Environment Consulting Co. Ltd 95 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 25Figure 3.2-6 Excavation Scope of the Soils at the Sixth Layer

Figure 26Figure 3.2-7 Excavation Scope of the Soils at the Seventh Layer

Shenyang Lvheng Environment Consulting Co. Ltd 96 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 27Figure 3.2-8 Excavation Scope of the Soils at the Eighth Layer

Figure 28Figure 3.2-9 Excavation Scope of the Soils at the Ninth Layer

Shenyang Lvheng Environment Consulting Co. Ltd 97 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 29Figure 3.2-10 Excavation Scope of the Soils at the Tenth Layer

Shenyang Lvheng Environment Consulting Co. Ltd 98 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

4. Technical Solution to Polluted Site Soil Remediation

4.1 Technical Roadmap According to the pollution features of the current site, results of technology screening and evaluation, and opinions of the interested parties, the polluted soils should be subjected to ex-situ remediation and excavation first, and then some soils should be transported to the new factory for use as backfill soils and other soils should be stabilized or subjected to chemical oxidation and thermal desorption. The details are as follows: (1) The polluted soils that surpass the standard for residential lands but fall short of the standard for industrial lands (excluding DDT-polluted soils) should be directly transported to the new factory for use as backfill soils; (2) The soils that are polluted by a single heavy metal and surpass the standard for industrial lands should be solidified and stabilized first, and then transported to Laohuchong domestic waste landfill for use as casing soils; after the stabilization treatment, the concentration of nickel should meet the admission criteria of the landfill; this work is carried out on site; (3) The soils polluted by PAHs, DDTs, and TPHs should be further subjected to a small-scale test and pilot-scale test if the degradation rate of 35% is enough to attain the remediation goal; if feasible, the soils should be subjected to chemical oxidation; chemical oxidation of the soils is intended to attain the target values for soils of industrial lands (or the target values of soils of residential lands if the soils are polluted by hexachlorocyclohexane); if the chemical oxidation reaches the specified standard, the soils should be backfilled in the new factory; this work is carried out on an ex-suit basis; (4) Other organically polluted soils or compositely polluted soils (primarily polluted by organic pollutants) should be subjected to thermal desorption; if chemical oxidation is not feasible, the associated soils should also be subjected to thermal desorption; the thermal desorption is intended to obtain residential lands; after the treated soils meet the specified standard, they should be discharged as residual soils; this work is carried out on an ex-suit basis.

Shenyang Lvheng Environment Consulting Co. Ltd 99 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Measurement by lineation Rejected

Excavation of foundation pit Inspection of foundation pit

Accepted Preparation of disposal field

Complete Temporary storage of polluted

soils

Soils that fall short of the standard Soils slightly polluted Soils heavily polluted Soils polluted by

for industrial lands by organics* by organics* heavy metals

Solidification & stabilization Industrial land Small-scale test and pilot-scale test of chemical oxidation No reutilization No, solution 2 Acceptable or not Feasible or not Thermal

desorption Yes (meet the admission Yes, solution 1 No criteria for landfill soils) Chemical oxidation

Acceptable or not Used as casing No soils of domestic Acceptable or not waste landfill

Yes (meet the standard for industrial lands) Yes (meet the standard for residential lands)

Industrial land reutilization Discharged or reutilized

Figure 30Figure 4.1-1 Technical Roadmap for Remediation and Treatment of Polluted Soils 4.2 Implementation Scheme of In-situ Remediation Engineering

4.2.1 Procedure of the Implementation Scheme

The polluted soils should be excavated primarily by mechanical means (specifically, by excavators), and secondarily by manual means. According to the construction condition, excavation requirements, and excavation quantity, it is necessary to arrange mechanical equipment and construction personnel reasonably in advance, and make various preparations as appropriate. To implement the excavation engineering correctly, it is necessary to measure, locate, and mark the polluted areas by lineation according to the remediation boundaries, and set up protective fences for the polluted areas. The polluted soils should be excavated by blocks and by layers. After a certain

Shenyang Lvheng Environment Consulting Co. Ltd 100 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site area of foundation pit is excavated, the foundation pit should be covered to prevent fugitive dust and pollution migration. Figure 4.2-1 shows the flowchart on excavation of polluted soils.

Figure 31Figure 4.2-1 Diagram on Soil Excavation Process and Pollution Discharge Nodes

(1) Site Leveling Site leveling is intended to build necessary infrastructure (including water supply, water drainage, power supply, roads, and temporary buildings) that is required in the process of soil excavation. Table

4.2-1 describes the equipment required for site leveling. Table 46Table 4.2-1 Technical Parameters of the Site Leveling and Compacting Equipment Equipment Pushdozer Compactor Site clearing or leveling, auxiliary excavation, Use Site leveling and compacting transport, and unloading of soils Place of origin China China Quantity 5 4 Dipper capacity (m3) 4.5 — Rated power (kW) 120 135

(2) Construction Surveying

Surveying preparations are an important link for ensuring a smooth surveying process.

Surveying preparations include drawing review, hand-over and check of the reference points for surveying and positioning, check and calibration of test instruments, development of surveying program, data preparations, and measurement of construction sites. According to the scope of soil treatment and remediation determined in an earlier stage, we determined the coordinates of the inflection points of the scope of soil treatment and remediation by GPS, determined the excavation lines of foundation trenches, and marked the excavation lines by white ashes. On one side of the excavation lines, we set up a warning board, which indicated the types of soils, excavation depth, and treatment mode to prevent incorrect places from being excavated.

 Preparations

a. Hand over and check the control points with the construction organizations;

Shenyang Lvheng Environment Consulting Co. Ltd 101 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

b. Level the remediation site, and clear the ground obstacles;

c. Allocate instruments, equipment, and personnel preliminarily, check all instruments and equipment, and ensure that the surveying personnel should hold the required qualification certificates;

d. Conduct technical clarifications to the surveying personnel through the technical leader;

e. Be familiar with the drawings, know the related data about the foundation pit, pollution scope and boundary lines for sloping, and obtain the required data for surveying and lineation;

f. The surveying personnel have defined the methods and steps for surveying and lineation.

 Materials and Instruments

a. The surveying engineering mainly requires some sporadic and auxiliary materials, including white ashes, timber piles, small red flags ,and drawings;

b. The surveying engineering mainly requires three types of instruments: laser theodolite (JZ2), level gauge (DZS3-1), and TOPCO total-station instrument (N211D);

c. The used tools mainly include 5m small flexible rules, 50m steel measuring tapes, leveling rods, and level rulers.

 Sloping of Foundation Pit

The maximum excavation depth is 4 m below the ground; at the depth of 2 to 4 m, the excavation area is very small; there are no important buildings at the slope top, and sloping is permitted by site conditions. Therefore, the natural sloping mode is used for the protective slope of the foundation pit.

The protection of the foundation pit should meet the following requirements: a. in the process of soil excavation, personnel and equipment should stay away from the foundation pit, to prevent the occurrence of accidents; b. around the positions 0.6 m away from the pits, two protective railings are set up by using φ48 steel pipes, the upright pole interval is 4 m, the upright poles are 1.2 m above the natural terrace, and the burial depth of them is 0.5 m. Within the distance of 1 m to the sides of the upper opening of the foundation pit, no soils, materials, machines and tools may be placed; the construction personnel should not climb over the protective railings; in the process of foundation pit excavation, warning boards should be set up, and red lamp signs should be set up in the nighttime; c. the construction personnel outside the foundation pit should not throw anything into the foundation pit, and when tools are transferred to the foundation pit, the transferring personnel should release their hands only after the tools are held firmly by the recipients; d. when having a rest, the personnel in the Shenyang Lvheng Environment Consulting Co. Ltd 102 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site foundation pit should stay away from the pit sides and sloping positions; e. the construction machinery should obey the command, the construction personnel should stay away from the construction machinery; if necessary, the operation personnel should be notified first, and other personnel should not get close to the construction machinery unless they receive the response of the operation personnel; f. in the process of construction, the construction personnel should keep a close watch on weather changes, and take appropriate measures to prevent large-area soil collapse.

(3) Infrastructure Construction

It is necessary to set up continuous fences with a height of at least 2.5 m, implement the engineering in a closed manner, and ensure not only environmental sanitation and civilized construction, but also easy entry and exit and smooth traffic.

In the remediation site, office buildings and life buildings should be arranged on the principle of reasonable layout, compactness and orderliness, and civilized construction, and the remediation site should be separated from office buildings and life buildings.

A water drainage system should be set up, and the wastewater from truck cleaning should all be reused. Figure 2 attached shows the position of the truck washing station.

(4) Soil Excavation

The polluted soils should be excavated primarily by mechanical means and secondarily by manual means. According to the construction condition, excavation requirements, and excavation quantity, it is necessary to arrange mechanical equipment and construction personnel reasonably in advance, and make various preparations as appropriate.

For the current engineering, the soils to be excavated amount to 114,000 m3 approximately. As planned, 1,900 m3 soils need to be excavated per day, and the whole excavation work will take 60 days approximately. The excavation capacity is 800m3 per day, which is enough to complete the daily excavation task. Table 4.2-2 describes the mechanical equipment required for soil excavation. Table 47Table 4.2-2 Equipment Required for Soil Excavation Mechanical Equipment Specification and Model Quantity Excavator Capacity of grab bucket: 0.6 to 1 m3 4 Truck Truck capacity: 6 to 8 m3 6

In the remediation site, up to 113 foundation pits need to be excavated in order of "slight pollution first and then heavy pollution..” For the slightly polluted land lots, the planned quantity of soils should be excavated; for the heavily polluted lands, a larger quantity of soils should be excavated than Shenyang Lvheng Environment Consulting Co. Ltd 103 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site planned, to reduce the impacts on the ambient environment. Once the heavily polluted soils are disturbed, organic pollutants will be volatilized to influence the ambient environment. According to the pollution scope of each foundation pit, the polluted soils should be excavated layer by layer.

Specifically, the first soil layer is 0 to 0.5 m in depth, the second soil layer is 0.5 to 1.0 m in depth, the third soil layer is 1.0 to 1.5 m in depth, the fourth soil layer is 1.5 to 2.0 m in depth, the fifth soil layer is

2.0 to 2.5 m in depth, the sixth soil layer is 2.5 to 3.0 m in depth, and the seventh soil layer is 3.0 to

4.0 m in depth. When each layer of polluted soils is excavated, it is necessary to control the pollution boundary and depth of the soils. After each layer of soils is excavated, the next layer of polluted soils is surveyed, positioned, and excavated continuously.

(5) Temporary Storage of Polluted Soils

The polluted soil temporary storage area includes a total of temporary storage area of the original contaminated soil and temporary storage of polluted soil, of which the original temporary storage area for contaminated soil is located in the middle of the contaminated site and covers an area of 1000 m2, which is mainly used for storage Tiexi district government land use risk assessment of soil contamination identified heavily contaminated soil; this temporary cleaning of contaminated soil in the northern part of the plant area, covers an area of about 3000m2, mainly for the project of clearing contaminated soil. At present, the surface of the soil temporary storage area has been hardened.

After communicating with the construction unit, different subareas will be set up in the temporary storage area of the soil, that is, the temporary storage area of heavy metal contaminated soil, the temporary storage area of organic contaminated soil and the temporary storage area of complex contaminated soil, Dig soil temporary storage area. Different types of temporary storage area to be well isolated and the identification plate, dredged contaminated soil by pollutants were loaded on different vehicles directly transported away, not in the field of temporary storage. Contaminated soil temporary storage area schematic diagram shown in Figure 4.2-2.

Shenyang Lvheng Environment Consulting Co. Ltd 104 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 32Figure 4.2-2 Diagram on Different Temporary Storage Areas for Polluted Soils

(6) Solidification and Stabilization Technology Curing stabilized soil repair process as shown in Figure 4.2-3.

Figure 4.2-3 heavy metal contaminated soil repair process flow chart

The process is summarized as follows:

⑴ site excavation

Polluted soil excavation using mechanical removal, supplemented by manual methods. According to the construction conditions, excavation requirements and removal of contaminated soil, reasonable arrangements should be made for the number of mechanical equipment and personnel prior to construction and preparation for all aspects. In the excavation, based on the on-site monitoring data, the on-site configuration of real-time detection equipment real-time detection of heavy metal pollutant concentrations in various polluted areas, to provide online data feedback of excavation area, and timely find areas inconsistent with the requirements of the excavated area.

⑵ contaminated soil pretreatment

Shenyang Lvheng Environment Consulting Co. Ltd 105 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Using crushing, screening machine to crush the soil, screening. Prior to soil treatment, screening and crushing should be carried out to eliminate construction waste. First, the use of excavators for large boulders screening, followed by the use of screening crushing bucket for fine screening and crushing, to ensure the follow-up treatment requirements. After crushing to ensure that 90% of the soil particle size does not exceed 30mm above the particle size before entering the stabilization process, to ensure the stability of the treatment effect.

Heavy metal contaminated soil in the production line before screening, broken. According to the restoration program This project is expected to use the international advanced professional construction machinery site screening broken. The versatile mobile screening crusher bucket is a worldwide patented product invented in the 1980s. It can be used in conjunction with general purpose loaders and excavators. It is easy to move and has no selectivity for the material to be treated. The process of the past complex soil sieving and crushing work is simplified to complete within one step, the scene is convenient and can achieve soil screening, crushing, mixing, mixing and other operations.

In the soil remediation project, firstly, the screening and shovel shovels are used to screen the polluted soil, remove the debris such as stones and construction rubbish, and simultaneously crush the contaminated soil to reduce the particle size of the soil as a pre-treatment device. The equipment is highly efficient. Its patented knife plate design ensures that the upper and lower staggered fixed blades guarantee the consistency of the finished product when it is inverted. Large-diameter rollers and cutter heads ensure that the material has good fluidity. The shaft can be continuously rotated in both directions and efficient torque transfer ensures robust start-up and operation, which is currently being used in several large soil remediation projects in the country.

The equipment is used to stabilize the soil management efficiency of 500-600 square / Taiwan class / pass, in order to fully mix the soil and pharmaceutical, mixing is expected to not less than 3 times. In the stabilization process, for the convenience of maneuverability, VL high-speed ectopic soil treatment equipment is also used to mix the stabilizer with the soil, and the equipment is used to treat the heavy metal-contaminated soil.

The device comes with 50 t solid state drug storage container and 1750L liquid reagent tank, according to the needs of the project circumstances, the external connection of other drug containers.

Soil treatment capacity up to 400t / h; depending on soil conditions may be. VL devices are non-stationary devices that can be moved from one site to another with short installation verification Shenyang Lvheng Environment Consulting Co. Ltd 106 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site time. The VL device comes with a diesel generator and requires less than 600L of diesel fuel to operate in 24 hours. Equipment for easy cleaning and maintenance. Curing stabilization integration device is shown in Figure 4.2-4.

The solidification and stabilization technology is to combine the heavy metal polluted soils with specific binders, so that the heavy metals in soils are immobilized by the binders and are kept in a steady state over a long period, thus reducing their migratory aptitude. The solidification and stabilization technology is universally used for quick control and remediation of heavy metal pollution of soils, and has an obvious advantage in treating the soils polluted by multiple heavy metals. The EPA of the U.S.A. refers to the solidification and stabilization technology as the optimal technology for treating the toxic wastes.

The solidification and stabilization technology includes two steps: stabilization and solidification.

Specifically, stabilization is to transform pollutants into difficult-to-dissolve forms of matter with lower migration ability or toxicity, to make the pollutants harmless and reduce their hazardous risks to the ecological system. Solidification is to microscopically wrap the pollutants into waterproof or low-permeability inert solid materials through physical actions, and transform the pollutants into difficult-to-dissolve forms of matter with lower migration ability or toxicity by reducing the area or amount of contact between the pollutants and solutions, in order to make the pollutants harmless and reduce their hazardous risks to the ecological system.

Figure 33Figure 4.2-4 Curing stabilization integration device diagram ⑶ contaminated soil treatment

Heavy metal contaminated soil treatment processes using curing / stabilization of repair technology, the use of repair agents for curing stabilizer BH. Agitation and soil mixing, so that heavy metals stable. In the stabilization process, for the convenience of maneuverability, VL high-speed

Shenyang Lvheng Environment Consulting Co. Ltd 107 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site ectopic soil treatment equipment is also used to mix the stabilizer with the soil, and the equipment is used to treat the heavy metal-contaminated soil.

The BH stabilizing agent used in this project is a kind of active agent added to the soil. The main raw materials are ferrous sulfate, sodium citrate, potassium dihydrogen phosphate, lime and high molecular organic stabilizers. BH agents are used to regulate the physicochemical properties of soil and to immobilize toxic heavy metals in the soil by a series of reactions such as adsorption, precipitation, ion exchange, humification, oxidation-reduction, or to convert heavy metals into chemically inactive Morphology, reduce its bioavailability, thus preventing the migration of heavy metals, so that its leaching concentration was significantly reduced, no longer migrate to the surrounding environment.

⑷ soil conservation after disposal

The soil treated by the soil remediation equipment is transported to a set temporary soil remediation area for maintenance and testing. Heavy metal contaminated soil conservation time is

5-7d. To be protected soil in accordance with the different levels of pollution were stacked into a long pile of soil and soil moisture content of water adjusted to about 20% after the coverage with the dust network for conservation.

⑸ soil testing and acceptance after repair

Two samples were selected for testing after each soil treatment. The heavy metal leaching content (conventional 8 heavy metals) was analyzed. The pretreatment method was "acetic acid buffer solution leaching method for solid waste leaching toxicity" (HJ / T 300-2007) Standard is

"Groundwater Quality Standard" Class III limit.

⑹ the whereabouts of soil after treatment

After treatment, the soil was accepted and passed to Tiger Landfill for soil cover. The landfill site was used according to the relevant requirements of the Control Standard for Domestic Landfill

Contamination.

(7) Transport of Polluted Soils

The excavated polluted soils are mechanically loaded into trucks or dumpers. The soils excavated in the daytime are stored in the appropriate temporary storage areas according to the types of soil pollution, and are transported in the nighttime. The transport trucks should be marked with the types of soil pollution, and transport the corresponding types of polluted soils. A transport Shenyang Lvheng Environment Consulting Co. Ltd 108 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site truck should not be loaded with different types of polluted soils. In accordance with Remediation Plan for the POP-contaminated Site (North Production Area of the Factory in Bei'er Road of Northeast

Pharmaceutical Group Co., Ltd.) of Northeast General Pharmaceutical Factory, the excavated polluted soils should all be transported to the new factory for remediation, and travel through

Zhonggong North Avenue, Shenda Road, Honghu Avenue, Kaifa Road, Xihe 7 North Avenue, and

Shenxi 6 East Road to the new factory. The transport distance is 23 km, and the transport route is shown in Figure 5.1-3. In principle, the transport route should keep away from densely populated areas (such as residential areas, schools, and hospitals) and drinking water source protection areas.

A temporary soil storage zone (area: 10,000 m2) should be set up in the new factory. In the to-be coal yard in the southern part of the new factory, there is a 7,000 m2 workshop building with some feeding facilities, which can be used as the main workshop for soil treatment. In the northern part of the new factory, there is a 3,500 m2 vacant space, which can be used for turnover and temporary storage of polluted soils. In the southwestern part of the new factory, there is a to-be 15,000 m2 engineering area, which can be used as the backfill area for the soils that meet the standards for industrial lands. Judging by the depth of 2 to 2.5 m, the engineering area is estimated to accommodate 30,000 to 40,000 m3 soils. The new factory is well-enclosed, and is surrounded by

Qianma Village, Sanmangniu Village, and Yuejia Village, which are all in process of demolition and resettlement. Yuhong District's Social Welfare Home is located to the south of the new factory, and its minimum distance to the new factory is 2,190 m (the distance between them is very long). Therefore, the new factory is suitable to serve as the remediation site for polluted soils. The remediation engineering of the site is experiencing environmental impact assessment.

Judging by the excavated soil quantity (114,000 m3) and excavation duration (60 days), the excavation speed is approximately 1,900 m3/d. DFL3241 trucks or transport trucks of similar model will be used. One truck can transport 20 m3 soils every time, one round trip will take 2 hours, and one truck can have four round trips per day. Therefore, a total of 20 transport trucks are required.

Shenyang Lvheng Environment Consulting Co. Ltd 109 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 34Figure 4.2-4 Transport Route of Polluted Soils 4.2.2 Primary Pollution Sources and Environmental Impact Analysis

4.2.2.1 Waste Gas

1. Construction Dust

In the in-situ remediation site, fugitive dust is generated in the process of soil excavation, temporary storage of soils, and operation of construction trucks. In addition, road dust is generated by the transport trucks. The evaluated engineering content is the soil excavation of the polluted site, which is similar to the construction content of general construction projects. Therefore, the evaluation of construction dust shows an analogy to the construction dust test for general construction projects.

Table 4.2-3 lists the results of construction dust test under five different construction conditions of Shenyang City. During the test, the wind speed is all lower than 2.4 m/s. Table 48Table 4.2-3 Data on Analogue Test of Construction Dust (Unit: μg/m3) No. of TSP Const Upwind direction Downwind direction Within the ructio 50 m construction site 50 m 100 m 150 m n Site 1 327.0 624.0 484.0 356.0 332.0 2 313.0 594.0 431.0 372.0 311.0 3 327.7 594.0 476.0 390.0 322.0 4 325.0 766.0 514.0 367.0 336.0 5 295.0 413.0 392.0 326.0 303.0 According to this table, the TSP concentration within the construction site is the highest, the TSP

Shenyang Lvheng Environment Consulting Co. Ltd 110 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site concentration in the upwind direction is relatively low, and the TSP concentration in the downwind direction gradually decreases with the increase in distance. The range of influence from fugitive dust is not more than 200 m.

According to field investigation, the east of the polluted site is adjacent to Vanke Spring Dew

Mansion, its south is adjacent to Bei'er West Road, its west is adjacent to Tiexi District People's

Government of Shenyang City, and its north is adjacent to Xiaobei 1 West Road. Specifically, the polluted site is 20 m and 10 m away from the residential community (Vanke Spring Dew Mansion) and office building of Tiexi District People's Government of Shenyang City, so they are susceptible to fugitive dust.

In-situ remediation of the polluted site is estimated to be completed by the end of June 2018.

Before the commencement of each stage of soil treatment engineering, it is necessary to set up continuous fences with a height of 2.5 m or more around the remediation site, to prevent the escape of fugitive dust. Across the whole process of soil remediation, it is necessary to spray water to suppress construction dust. The different areas in the temporary storage zone of polluted soils should be covered, and the soil remediation zone (by solidification and stabilization) should be fitted with a closed membrane structure shed (or the polluted soils should be treated by integrated machines in a closed manner). The whole remediation engineering should be implemented in a closed environment.

In the process of soil excavation and loading, dust can be decreased by reducing the operation speed or drop. The above measures serve to reduce the concentration of TSP in air significantly and alleviate the dust pollution in the construction site effectively; in addition, construction dust will disappear immediately at the end of engineering construction. Therefore, the implementation of the remediation engineering will not influence the people in Vanke Spring Dew Mansion and Tiexi District

People's Government.

2. Volatile Organic Pollution Gas

In the in-situ remediation site, the volatile organic pollution gas is mainly sourced from the polluted soils. In the polluted soils, there exist such pollutants as PAHs and organochlorine pesticides, and in the soils of certain polluted areas, there exists an obvious hexachlorocyclohexane smell. The soil excavation process easily gives off the irritating smell. However, it is difficult to quantitatively analyze and determine the components and concentration of organic substances in soils. Therefore, it is also difficult to determine the concentration of waste gas pollutants discharged during soil Shenyang Lvheng Environment Consulting Co. Ltd 111 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site excavation. Soil excavation is estimated to take 25 days (the construction period is very short), and the excavated soils will be transported instantly rather than be stored in the current site for a long period. In addition, the polluted soils in the polluted site will all be excavated and transported to other places. Therefore, the volatilized organic pollutants are very limited, and the impact on the ambient environment is slight.

4.2.2.2 Wastewater

The wastewaterwastewater generated in the process of engineering construction mainly includes the flushing water for the wheels of transport trucks and domestic wastewaterwastewater produced by the construction personnel. The current engineering is not implemented in rainy season, so foundation pit water will not be involved.

1. Flushing water for the construction trucks

The remediation engineering is estimated to take 90 days. The consumption standard of flushing water is 0.3 t per truck-time, so the required quantity of flushing water is 28.8 t per day. The wastewaterwastewater produced by truck flushing will all return to the settling pond for cycled use, but will not be discharged to the ambient environment.

2. Domestic wastewater produced by the construction personnel

In the construction site, there are 30 construction personnel. The engineering construction period is 90 days; the consumption standard of domestic water is 50 L per person-day. Then, the required amount of domestic water is 1.5 t/d (or 135 t/a). Assume that the discharge of wastewater is approximately 85% of domestic water consumption; then, the discharge of wastewater is 1.275 t/d (or

114.75 t/a). The discharge quantity of domestic wastewater is very small. The domestic wastewater is discharged to the existing septic tank of the factory, and then transported to a sewage treatment plant through the sewage pipe network. The water quality of the discharged domestic water should comply with the requirements specified in Table 2 of Comprehensive Sewage Discharge Standard of Liaoning

Province (DB21/1627-2008). The discharged domestic wastewater will not pollute or influence the surface water and groundwater if appropriate anti-leakage and anti-seepage measures are taken for sewage treatment facilities.

Shenyang Lvheng Environment Consulting Co. Ltd 112 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 49Table 4.2-4 Generation and Discharge of Wastewater Generation Discharge Type of Pollutant Concentration Quantity Concentration Destination Wastewater Quantity (t/a) (mg/L) (t/a) (mg/L) The domestic wastewater will CODcr 300 0.034 210 0.024 be discharged to the septic tank in the north of Northeast Domestic NH3-N 45 0.005 11 0.001 General Pharmaceutical wastewater Factory, then treated in the (114.75 t/a) septic tank, and finally SS 150 0.017 140 0.016 discharged to Xiannvhe Sewage Treatment Plant. 4.2.2.3 Noises

The noises during engineering construction are mainly generated by machines at the time of site leveling and soil excavation and transport. The intensity of such mechanical noises is usually 75 to 85 dB(A), as described in Table 4.2-5. Table 50Table 4.2-5 Construction Equipment and Noise Source Intensity Noise Intensity No. Machine Quantity Discharge Mode (dB(A)) In the daytime, 1 Compactor 4 80 intermittent In the daytime, 2 Small loader 10 85 intermittent In the daytime, 3 Pushdozer 5 80 intermittent In the daytime, 4 Excavator 10 80 intermittent In the daytime, 5 Dumper 20 75 intermittent In the daytime, 6 Vibratory roller 1 85 intermittent In the daytime, 7 Integrated agitator 1 80 intermittent The same reception point can receive the acoustic energy transmitted by multiple acoustic source points. The sound pressure level of the reception point can be calculated through noise superposition. The noise superposition equation is as follows:

n L =10lg 100.1Li i=1 In the equation, L refers to overall sound pressure level (dB(A)); n indicates the number of noise sources.

Shenyang Lvheng Environment Consulting Co. Ltd 113 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 51Table 4.2-6 Intensity Analysis of Main Noise Sources

Intensity of a Intensity of a Single Noise Single Noise Superposition of No. Machine Quantity Countermeasure Source after Source Sound Sources Noise dB(A) Reduction Sound insulation, 55 1 Small loader 4 80 61 noise reduction

Sound insulation, 60 2 Pushdozer 10 85 70 noise reduction

Sound insulation, 55 3 Excavator 5 80 62 noise reduction

Sound insulation, 55 4 Dumper 10 80 65 noise reduction

Sound insulation, 50 5 Vibratory roller 20 75 64 noise reduction

Sound insulation, 60 60 6 Small loader 1 85 noise reduction

Integrated Sound insulation, 55 55 7 1 80 agitator noise reduction

Superposition value 73.0 4.2.2.4 Solid Wastes

The solid wastes generated during engineering construction mainly include the excavated polluted soils and a small quantity of domestic wastes generated by the construction personnel. In accordance with Remediation Plan for the POP-contaminated Site (North Production Area of the

Factory in Bei'er Road of Northeast Pharmaceutical Group Co., Ltd.) of Northeast General

Pharmaceutical Factory, the quantity of soils to be excavated will be 70,171 m3. Some of the excavated soils will be transported to the new factory for remediation; some of them will be subjected to in-situ remediation first and then transported to Laohuchong domestic waste landfill for use as casing soils; the suspected unpolluted 24,888 m3 soils will be transported to the new factory for treatment. The domestic wastes generated by the construction personnel will be approximately 0.13 t/a, and will be transported and disposed by the environmental sanitation authorities. Table 4.2-6 describes the generation of solid wastes.

Shenyang Lvheng Environment Consulting Co. Ltd 114 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 52Table 4.2-6 Generation of Solid Wastes

Generated Destination No. Pollution Factor Quantity Some of them will be transported to the new factory for remediation,

and some of them will be subjected to in-situ remediation first and then 1 Polluted soils 70,171 m3 transported to Laohuchong domestic waste landfill for use as casing soils.

Directly excavated soils for use 2 24,888 m3 They will be transported to the new factory for use as landfill soils. as landfill soils

Domestic wastes generated by They will be transported and disposed by the environmental sanitation 3 0.13 t the construction personnel authorities. 4.2.3 Pollution Control Measures

4.2.3.1 Solutions and Measures for Air Pollution Control

Fugitive dust will be generated in the process of soil excavation. The soil remediation organization should strictly abide by the instructions specified in Notice of the Environmental

Protection Bureau of Shenyang City on Dust Pollution Control and Emergency Notice on

Strengthening Dust Pollution Control, and take the following anti-dust measures:

1) Before the commencement of each stage of soil treatment engineering, set up continuous fences with a height of 2.5 m or more around the remediation site, to prevent the escape of dust during soil excavation and remediation.

2) Spray water fog through mobile spraying and de-dusting machines to prevent the escape of dust.

Figure 35Figure 4.2-5 Mobile Spraying and De-dusting Machine 3) It is recommended that the soil remediation zone (by solidification and stabilization) should be fitted with a closed membrane structure shed (or the polluted soils should be treated by integrated Shenyang Lvheng Environment Consulting Co. Ltd 115 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site machines). The polluted soils should be agitated and crushed in a completely closed environment, to reduce the diffusion of fugitive dust effectively.

4) The polluted soils in the temporary storage zone should all be covered by rain-proof tarpaulins or membranes, but should not be exposed to the air. Meanwhile, the rain-proof tarpaulins should be fixed, to prevent them from being blown off by wind and prevent the diffusion of fugitive dust.

5) If engineering construction is made impossible due to adverse weather (such as strong wind and heavy rain), the naked soils should be covered by rain-proof cloths, thus preventing dust diffusion or rain washing, as well as secondary pollution.

6) After soil excavation is complete, it is necessary to approach the land developer. The excavation site should not be exposed to the air, thus preventing the diffusion of fugitive dust.

7) In the process of soil excavation and loading, it is necessary to reduce the operation speed and drop, thus preventing the generation of fugitive dust.

8) The transport trucks should be covered by canvases, not leak any soils, and discharge exhaust gas as little as possible.

9) The transport passageways should be cleaned frequently, and the speed of incoming/outgoing trucks should be controlled, to reduce the generation of fugitive dust.

10) It is necessary to strengthen the management of soil excavation and transport, speed up soil excavation and transport, load/unload the excavated soils reasonably, ensure standardized operations, and reduce the scope of influence from fugitive dust.

11) The construction machines and transport trucks should be overhauled and maintained carefully, and it is prohibited to use the trucks that go beyond their useful life and the trucks whose exhaust emissions exceed the allowed limits. The transport trucks should be fitted with exhaust purifiers, and standard-compliant fuels rather than inferior fuels should be used, to reduce the emissions of harmful gas. All motor vehicles should be subjected to regular exhaust emission test by the qualified institutions authorized by the environmental protection authorities of Shenyang City, and be granted environmental conformance marks.

4.2.3.2 Solutions and Measures for Water Pollution Control

The wastewater generated during soil excavation mainly includes the flushing water for the wheels of transport trucks and domestic wastewater generated by the construction personnel. The Shenyang Lvheng Environment Consulting Co. Ltd 116 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site following measures should be taken to prevent the secondary pollution from the wastewater:

1) The depth of groundwater in the construction site is 6 to 7 m. The excavation depth should be not more than 5 m, and soil excavation should not be implemented in rainy season. Therefore, foundation pit water is not involved.

2) The domestic wastewater generated by the construction personnel may be discharged to the septic tank in the south of Northeast General Pharmaceutical Factory, then treated in the septic tank, and finally discharged to Xiannvhe Sewage Treatment Plant for centralized treatment.

3) A truck washing station should be set up near the egress of transport trucks, to wash the construction machines and transport trucks. Before leaving the construction site, each transport truck must have its wheels and body washed thoroughly, thus preventing the polluted soils from being brought out and consequently preventing secondary pollution. The truck washing station should be fitted with washing platforms, pumps, and pipes, and drainage ditches should be set up around the truck washing station. The wastewater from truck washing should be discharged to a settling pond through pipes, be precipitated in the settling pond, and finally be reused.

4) The four walls and bottoms of the settling pond, temporary soil storage zone, solidification and stabilization area, and truck washing station should all be subjected to anti-seepage treatment, and the wastewater pipes should also be subjected to anti-seepage and anti-leakage treatment. The anti-seepage grade should meet the requirements specified in Article 6.3.1 of Standard for Pollution

Control on Hazardous Waste Storage (GB18597-2001).

Key anti-seepage areas: HDPE or other artificial materials with a thickness of at least 2 mm should be used, and the permeability coefficient should be less than or equal to 10-10 cm/s.

Anti-seepage treatment for wastewater pipes: High-strength and highly anti-corrosion pipe materials (such as seamless steel tubes) and high-grade anti-rot materials should be used; welding connection should be used.

It is recommended that HDPE geotechnical membranes (the permeability coefficient is as low as

10-12 to 10-13 cm/s) should be used in the key anti-seepage areas. The HDPE geotechnical membranes have the following features and advantages:

Low permeability: The permeability coefficient is very low, and is far lower than the standard specified by the related specifications. This ensures that the wastewater contained in the settling pond and generated by the truck washing station will not seep, thus protecting the groundwater and Shenyang Lvheng Environment Consulting Co. Ltd 117 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site ambient ecological environment from being polluted.

Chemical stability: Compared with other geotechnical membranes, HDPE geotechnical membranes have exceptional chemical stability, and will not be corroded by ordinary wastewater or other substances.

Ultraviolet stability: HDPE membranes have high anti-ultraviolet and anti-aging properties. The carbon black contained in the HDPE membranes provides an enhanced anti-ultraviolet and anti-ozone capability. In addition, no plasticizers are used in the production process of HDPE membranes. Therefore, they can be exposed to sunshine for a long period, and maintain the original properties in a high-temperature environment (specifically, the organic substances will not be decomposed).

High technological maturity: The production technology of HDPE membranes have been matured, and a perfect supporting welding method is available. The high technological maturity facilitates engineering construction. Many success examples show that HDPE membranes are the host material of the anti-seepage layer.

High cost performance: High cost performance makes HDPE membranes suitable to China's actual condition and economic development level of different regions.

5) The wastewater from truck washing should all be reused, but not be discharged to the outside environment. In the planning and design stage, the soil remediation organization should further optimize the wastewater treatment facilities, construction scale, and wastewater reusing scheme, to ensure that all wastewater can be reused.

6) A groundwater environment monitoring system should be built to keep abreast of the quality of groundwater in the region and give early warnings about the groundwater, thus taking preventive and protective measures promptlypromptly. The observation instruments at the monitoring points should be maintained promptlypromptly, to ensure uninterrupted observation for a long period.

4.2.3.3 Solutions and Measures for Noise Pollution Control

The noises during soil excavation are mainly sourced from the excavation equipment, transport trucks, integrated agitators, and soil improvement machines. The following measures should be taken to prevent the noise pollution during soil remediation:

1) During engineering construction, noise emissions should not exceed the limits (70 dB in the daytime, and 55 dB in the nighttime) specified by Emission Standard of Environment Noise for Shenyang Lvheng Environment Consulting Co. Ltd 118 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Boundary of Construction Site (GB 12523-2011).

2) It is advisable to use the construction equipment that emit low noises or are fitted with soundproof or noise reduction devices.

3) The strong-noise equipment should be closed or blocked by sound-proof shields, to reduce the noises.

4) Increase public awareness on environmental consciousness, take effective measures to control the man-made construction noises, strengthen construction management, and minimize the disturbance of noises to people.

5) The construction personnel nearby the high-noise equipment should wear earplugs, work by shifts. or have their working hours shortened, to reduce the harm of noises to their ears.

6) Construction operations should be scheduled reasonably, and construction operations should be prohibited during the period of 22:00 to 6:00 of next day. If nighttime construction is necessitated, it is necessary to obtain prior approval of the authorities concerned and the consent of the surrounding residents.

4.2.3.4 Solutions and Measures for Solid Waste Pollution Control

The solid wastes generated during engineering construction mainly include the remaining buildings in the original site, excavated polluted soils and a small quantity of domestic wastes generated by the construction personnel. The following measures should be taken to prevent the possible pollution arising from the solid wastes:

(1) When excavating each land lot, it is necessary to distinguish different types of polluted soils on site. Each type of polluted soils should be excavated thoroughly, and it is not advisable to mix the heavily polluted soils with the slightly polluted soils or mix different types of polluted soils. Otherwise, this will increase the workload in excavation of heavily polluted soils, and subsequent treatment costs.

Different excavators should be arranged to suit different types of polluted soils, thus preventing cross pollution.

(2) In the temporary soil storage zone, classification labels should be set up in the boundaries between different areas (including the temporary storage area for the soils to be remediated, maintenance area for the remediated soils, temporary storage area for the soils to be directly transported, and temporary storage area for the soils to be accepted), thus facilitating sorted loading/unloading and transport. In addition, lattice blocks should be set up, to prevent the mixing of Shenyang Lvheng Environment Consulting Co. Ltd 119 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site different types of soils and prevent extra treatment costs or secondary pollution.

(3) While the polluted soils are temporarily stored, eye-catching warning signs should be set up around the temporary storage zone, and be managed by specialized personnel. Routine patrol should be strengthened, unexpected events (if available) should be handled promptlypromptly, and safety accidents and secondary pollution should be prevented.

(4) After the soil remediation engineering is complete, the soils in the temporary soil storage zone and soil remediation zone should be sampled for test, to prevent the polluted soils from polluting the existing unpolluted soils.

(5) The excavation and transport personnel should be trained in advance. In the process of soil excavation and transport, specialized personnel should be assigned to supervise and record the progress and truck information, thus ensuring that the excavation quantity and transport quantity are well documented. It is necessary to define detailed managerial and technical requirements for soil excavation and transport, follow the excavation and transport schedule, and strengthen process management, thus preventing the negative influence on the ambient environment.

(6) The polluted soils destined for Laohuchong domestic waste landfill should be transported immediately once they are excavated, but should not be stored in the temporary soil storage zone for a long period.

(7) The domestic wastes generated by the construction personnel should be transported and be subjected to innocent treatment by the environmental sanitation authorities, thus preventing negative influence on the ambient environment.

(8) The remaining building wastes of the original site should be buried in a special building waste landfill, but should not be transported at will.

(9) The transport trucks should be marked correctly according to the types of polluted soils, and different types of polluted soils should be transported by different trucks, thus preventing cross pollution. The same truck should not transport different types of polluted soils.

(10) For each truck of polluted soils to be transported, it is necessary to fill in a transfer form in several copies, which contains such data as the time of departure, pollution type, transported weight, responsible person for transport, responsible person for reception, place of reception. The multiple copies will be respectively delivered to the production organization, transport organization, receiving organization, environmental protection authorities of the source place, and environmental protection Shenyang Lvheng Environment Consulting Co. Ltd 120 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site authorities of the destination. After polluted soils reach the destination, the responsible person for reception should inspect the polluted soils as per the transfer form, enter the date of receiving, and append the official seal. The transport route of polluted soils should bypass residential areas, schools and sensitive areas (such as source areas of surface water and groundwater), and should be transported through an optimal route that offers good road condition and is able to completely bear the load of heavy-duty trucks.

(11) The soils involved in the remediation engineering are polluted soils, so they should be covered well to prevent secondary pollution. The transport trucks should have high performance and well-enclosed carriages, obtain all required certificates, and run along the specified route. During the transport process, the transport trucks should not leak soils. The loading height should not outreach the baffle grooves, and should be 5 cm below upper sides of baffle grooves. At the bottom of the carriage, a HDPE membrane (thickness: 0.7 mm) should be laid, and the upper part of the carriage should be covered by a tarpaulin. The HDPE membrane should be tied with the tarpaulin, thus providing a double closing environment. In the rear part of the groove, a color strip cloth should be laid, thus preventing the soils from leaking to roads through the gaps of the truck body. The transport trucks should be clean and well-enclosed, thus ensuring the closedness of soils in transit and preventing the diffusion of fugitive dust fully.

(12) At the egress of the polluted area, truck washing facilities should be set up. Before each truck leaves the polluted area, its wheels should be washed and the residual soils on the truck body should be flushed away. The wastewater from truck washing should be gathered in the truck washing station and then treated centrally. Otherwise, the truck may carry away polluted soils, thus causing secondary pollution.

(13) The whereabouts of polluted soils should be strictly controlled, the entry and exit of transport trucks should be confirmed, and specialized personnel should be assigned to patrol the polluted soils in transit, thus ensuring that all polluted soils are transported to the specified destinations.

(14) In the process of site remediation, a balance of cut and fill must be ensured on site, and no soils in any area may be transported outwards.

(15) In the process of soil excavation, it is necessary to take notice of the remaining abandoned pipes or other suspicious pollutants in the original site. In the north of original Northeast General

Pharmaceutical Factory, there exist some abandoned underground pipes. Due to its production Shenyang Lvheng Environment Consulting Co. Ltd 121 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site technologies, some organic pollutants still remain in the abandoned underground pipes. Once such pipes are damaged, secondary pollution will be caused. During soil excavation, some staffs of original

Shenyang Gourmet Powder Factory must be present to position the underground pipes and other suspicious pollutants accurately, in order not to damage such pipes. The excavation personnel should operate with care. Once underground pipes or other suspicious pollutants are found, the excavation personnel should stop soil excavation immediately and report to the authorities concerned.

4.2.3.5 Solutions and Measures for Risk Prevention

The organic pollutants involved in the soils of the current site are highly poisonous and severely harmful to human body. They may bring about health risks through respiration, contact, or oral intake.

Therefore, in the process of polluted site remediation, it is necessary to abide by the related regulations of PRC, take anti-risk measures, and formulate an emergency plan against risks, to ensure the health and safety of field personnel.

The risky pollutants encountered in the process of soil excavation, transport, and remediation mainly include tetraphene, chrysene, benzo[b]fluoranthene, benzo[k]fluoranthene, benzoapyrene, indeno(1,2,3-cd)pyrene, dibenz[a,h]anthracene, and -hexachlorocyclohexane. The nearby residents may complain if unexpected events occur, unidentified pipes, structures, or liquids are found, and peculiar smell is diffused.

● Anti-risk Measures

1. Risk Control in the Process of Polluted Soil Excavation

(1) Control the excavation operation plane, and reduce the volatilization area of pollutants.

(2) Alleviate soil disturbance, and reduce the escape of pollutants. In the process of polluted soil clean-up, digging buckets should be operated steadily, and it is prohibited to throw polluted soils at a long distance or throw polluted soils to transport trucks from a very high position. When polluted soils are loaded into transport trucks, digging buckets should be as close to the truck bodies as possible.

(3) Control the excavation time, and reduce the volatilization temperature. To reduce the volatilization of pollutants, it is advisable to excavate soils in the nighttime and in a low-temperature season.

(4) Control fugitive dust, and reduce the diffusion of pollution. It is necessary to take various pollution and risk control measures, for example, spray water on the roads, control the speed of transport trucks and number of trucks in the excavation site, cover the operation plane by tarpaulins, Shenyang Lvheng Environment Consulting Co. Ltd 122 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site and stop excavation operations in case of strong wind (Grade 4 or above).

2. Risk Control in the Process of Polluted Soil Transport

(1) The transport trucks should have excellent enclosures, and possess a satellite positioning function.

(2) After soils are loaded into transport trucks, the soils should be covered by tarpaulins tightly, and are not allowed to leave the site unless it passes the checks.

(3) Specialized personnel should be assigned to patrol the transport trucks. If they find that tarpaulins are blown off by wind, they should immediately notify the drivers to pull over and have the soils covered well.

(4) Mobile pollutant monitoring devices should be provided to monitor the ambient air along the transport route, thus ensuring that the air quality along the transport route complies with the related standards of PRC and Liaoning Province.

3. Risk Control in the Process of Temporary Storage and Remediation of Polluted Soils

(1) Preferably, the polluted soils should be remediated in the negative-pressure and sealed sheds.

(2) The incoming/outgoing polluted soils to/from the temporary soil storage zone should meet the foresaid risk control requirements in respect to excavation process of polluted soils.

(3) The polluted soil remediation equipment workshop should be provided with pollutant auto-monitoring devices and alarm devices, thus ensuring that the pollutant concentration of the air in the workshop does not exceed the allowed limits.

● Emergency Measures Against Risks

1. Emergency Plan against Unexpected Circumstances during Earthwork Construction

(1) In the process of soil excavation, appropriate measures should be taken immediately in special circumstances.

(2) If there are some signs of landslide (for example, cracks and slide), soil excavation should be suspended, all personnel should leave the foundation pit quickly, and appropriate measures (for example, backfill the slope toes) should be taken if necessary. According to the slide signs, some observation points should be set up to observe the planar displacement of the slide mass and sedimentation changes, and make records of them.

(3) If underground obstacles (including ancient tombs, cultural relics, ancient ruins, unidentified Shenyang Lvheng Environment Consulting Co. Ltd 123 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site pipes, pipe ditches, cables, unknown materials, and particularly underground wastewater pipes; over the past years, large quantities of poisonous and harmful substances have deposited in such pipes, and they are severely harmful) are encountered, the excavation personnel should immediately stop soil excavation, contact the municipal administration, evacuate the surrounding masses, and leave the excavation site. The excavation personnel should not continue soil excavation unless it is confirmed that the pipes or structures are abandoned and potential safety hazards are eliminated. If unknown materials are found, such materials should be identified by the qualified institutions. If such materials are identified as hazardous wastes, they should be sent to the hazardous waste center for disposal.

2. Emergency Plan against Major Pollution Accidents on the Excavation Site

During the process of site excavation, the organic pollutants in the soil emit a large amount of smells, and the site operators should suspend the construction and promptly evacuate the site in the upwind direction and immediately report to the on-site emergency response team.

The on-site emergency team received the report detailing the time, place, causes, sources of pollution, major pollutants, scope of pollution, casualties, contact person and contact information of the incident in detail. The on-site emergency team should rushed to the scene to make preliminary judgments The degree of harm of the incident, take appropriate measures; odor lighter, no casualties, should be promptly prepared with pre-prepared cloth will disturb the soil and strict warning, and set the warning signs. After confirming that there is no abnormal smell on site, construction can continue.

When the odor is distributed seriously and there is obvious discomfort in the body of the staff, rescue should be organized immediately and report to the competent department of environment at the same time. Specific measures are as follows:

⑴ responsible for the construction site immediately organize personnel to determine the causes of pollution, determine the extent and scope of pollution.

(2) In the event of secondary pollution of soil caused by accident in transportation vehicles, the pollution area shall be used to deepen the method of clearing and digging to completely prevent secondary pollution.

⑶ such as a large number of volatile pollutants, resulting in local air pollutants concentration exceeded by the responsible person to organize evacuation of staff and sensitive people around the environment, and by wearing protective equipment professionals to the site to cover, repair treatment. Shenyang Lvheng Environment Consulting Co. Ltd 124 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(4) If the pollution level is heavy, it should promptly inform the general headquarters of project emergency rescue and mobilize the relevant resources from the headquarters to prevent the pollution from further aggravating and report to the relevant government department in charge.

3. Emergency Plan against Major Pollution Accidents in Transit

(1) In case of major pollution accidents (for example, the rear baffles are opened, so polluted soils are thrown to the ground on a large scale, and the drivers discard the polluted soils at will) in transit, an emergency plan should be initiated immediately after the pollution accident reports are received. The emergency response commanding center should instantly assign personnel and equipment to the accident sites.

(2) Special personnel should be assigned to guide the transport trucks, and other public vehicles are prohibited from rolling the leaked polluted soils.

(3) Emergency personnel and equipment should be assigned to clean up the sites, collect the remaining soils, and transport the soils to the remediation site for remediation.

(4) If drivers discard polluted soils at will, an emergency plan should be initiated to take appropriate measures, for example, find the trucks concerned and places that soils were discarded, assign personnel and equipment to collect the discarded polluted soils, and transport the collected polluted soils to the remediation site for remediation. In case of failure to transport the discarded polluted soils, appropriate measures should be taken to prevent secondary pollution, and the accident should be reported to the authorities concerned to investigate who are to blame for the accident.

4. Emergency Plan against Major Traffic Accidents in Transit

In case of major traffic accidents, it is necessary to initiate both the emergency plan against major traffic accidents and the emergency plan against major pollution accidents. Emergency personnel should reach the accident sites instantly, check the accident sites, rescue the wounded personnel, and report the accidents to the police. In addition, they should set up warning signs, investigate the leakage of polluted soils, and formulate an emergency pollution treatment program.

After the traffic accidents are handled completely, they should rent some trucks to transport the polluted soils the remediation site for remediation.

5. Emergency Plan against Poisoning Accidents

If some personnel are poisoned, the first finder should contact the emergency team promptly.

After receiving the accident report, the emergency team should reach the poisoning site immediately, Shenyang Lvheng Environment Consulting Co. Ltd 125 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site check the poisoning symptoms, and rescue the poisoned personnel promptlypromptly.

The field personnel should immediately make a 120 emergency call, and notify professional medical personnel to rescue the poisoned personnel. Specialized personnel should be assigned to reach the poisoning site, move the poisoned personnel to the gateway, to wait for the arrival of an ambulance, or directly send the poisoned personnel to the nearest hospital, and deliver active support to the first-aid personnel. Meanwhile, the poisoning accident should be immediately reported to the emergency team, the leaders concerned should reach the site to handle the poisoning accident, and report the poisoning accident to the superior department.

6. Emergency Plan Against Resident Complaints

● safeguard mechanism

① Maintaining the work of social stability in the important agenda of the project construction and regularly listening to the reports on the work of social stability of the units concerned; carefully studying the new situations reflected by the masses and analyzing possible research proposals on major issues that may arise.

② Implement the responsibility system for maintaining social stability, clarify the key positions and key issues in maintaining social stability. The goal of maintaining social stability management objectives, and responsible departments to maintain social stability assessment. For the irresponsible, dereliction of duty due to work, mismanagement caused by large-scale mass incidents caused serious consequences, hold the responsibility of the leadership.

③ adhere to the information and forecasting system, reflect the universality of the masses, highlighting sexual problems, studying and formulating solutions to detect signs of mass incidents, to promptly resolve in place.

● emergency measures

When discovering signs or major incidents of social stability, start the plan and proceed with the following working procedures:

① For the mass incidents that have taken place, the relevant departments should seriously receive them and, according to the causes, notify relevant personnel to rush to the scene to be patient and meticulous in their work to prevent intensification of contradictions and stabilize the masses in the area.

(2) Held a working conference on maintaining social stability for the first time, informed of the Shenyang Lvheng Environment Consulting Co. Ltd 126 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site unstable situation and handling situation, analyzed and studied possible major problems and countermeasures. And report the situation of instability to the local government and other relevant departments for help and support.

③ For complicated and large-scale mass incidents, the relevant leaders should promptly arrive at the scene, organize their work and put forward their opinions in time.

④ Stabilize the petitioners in the area and resolutely discourage them from going to Beijing and going to the provinces for petitioners.

⑤ For special personnel who have a tendency to commit suicide or endanger the society, they should patiently guide and stabilize their emotions and contact relevant parties to solve the problem.

When necessary, report to the relevant authorities for emergency measures.

● communication security

Relevant personnel received a major social instability notification, the mobile phone to ensure smooth 24h; 24 hours on duty on duty, keep abreast of all aspects of information and upload..

● Measures for Construction Safety

1. Safety Protection Measures for Construction Personnel

To ensure personal safety across the whole process of engineering construction, all participant construction personnel should abide by the related safety regulations strictly, and wear protective devices of different grades suited to field operation risks. The required protective devices mainly include light-duty protective work clothes, acid/alkali-resistant shoes and gloves, safety goggles, gas mask, and safety helmets. The construction managers should strengthen the management of use of articles for labor protection, check the quality of such articles, and make necessary records. All personnel who participate in soil remediation must wear appropriate protective articles and take appropriate measures for personal safety.

Shenyang Lvheng Environment Consulting Co. Ltd 127 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 36Figure 4.2-6 Articles for Personal Safety Protection Protection of respiratory tract: Normally, dust masks should be used. If there is some volatilized organic gas in the operation environment and the toxicant concentration is within a specific range, filtering respirators can be used. In case of emergency or if the toxicity and concentration of toxicants are very high, isolation respirators should be used.

Eye protection: Safety masks should be used.

Body protection: Depending on the toxicity and possible contact concentration, the construction personnel may use anti-poison clothes, rubber work clothes, work clothes proof against poison permeation, and ordinary operation protection clothes.

Hand protection: The construction personnel should use anti-chemical gloves and rubber gloves.

If construction personnel suffer chemical injury, they should receive the following treatment:

Dermal contact: Take off the polluted clothes, and wash the skin thoroughly by using soapy water and clean water.

Eye contact: Lift up the eyelid, wash the eyelid thoroughly by using flowing clean water or normal saline, and have the injured personnel hospitalized.

Inhalation: Leave the site quickly, go to a fresh-air place, and keep the respiratory tract unobstructed. If they have the symptom of expiratory dyspnea, they should receive oxygen therapy. If they have the symptom of respiratory arrest, they should receive artificial respiration immediately, and be hospitalized urgently.

Oral intake: The injured personnel should drink enough warm water, use the emetic method, and be hospitalized.

2. Other Safety Protection Measures

Safety measures should be taken within the construction operation areas. The whole construction range should be marked by warning signs, and anti-landslide measures should be taken if the excavation depth is very great. To prevent engineering accidents (for example, personal

Shenyang Lvheng Environment Consulting Co. Ltd 128 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site damage or equipment damage due to local collapse of soils), sufficient technical personnel should be assigned to the excavation site, to guide the running route and excavation operations. During soil excavation, the excavation equipment should not impact the temporary supporting facilities for the constructed areas. The bottom of foundation pit should not be over-excavated, soils should not be piled or loaded around the foundation pit, and the ground overload should be not more than 10 kPa.

4.3 Implementation Scheme of Ex-situ Remediation Engineering

4.2.1 Process of the Implementation Scheme

The PAH/DDT/TPH-polluted soils, organically polluted soils and compositely polluted soils should all be subjected to ex-suit remediation. The commonly used ex-suit remediation methods include chemical oxidation and thermal desorption. Figures 4.3-1 and 4.3-2 show the technologies processes of chemical oxidation and thermal desorption, as well as their pollution discharge nodes.

Figure 37Figure 4.3-1 Technological Process of Chemical Oxidation and Pollution Discharge Nodes

Figure 38Figure 4.3-2 Technological Process of Thermal Desorption and Pollution Discharge Nodes (1) Chemical Oxidation

① working principle

Project chemical oxidation of ectopic oxidation of chemical agents used for the KS and N agents.

The main component of the KS chemical reagent is sodium persulfate. The main component of the activator N reagent is lime, which is the advanced oxidation technology specifically aimed at soil and groundwater pollution control. Pharmacy as a solid for the treatment of pollution sources or pollution plume benzene, chlorinated hydrocarbons, phenols, pesticides and other organic pollutants.

The selected BH agents, KS agents and N agents are currently widely used in soil remediation and groundwater remediation. The main components are free of heavy metals and toxic and hazardous materials, and do not cause new heavy metals and toxic and harmful pollutants in soil and groundwater. Therefore, The items selected for the site site repair meet the requirements.

② process

Shenyang Lvheng Environment Consulting Co. Ltd 129 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Chemical oxidation of soils comprises three steps: crushing, piling & maintenance, and sample test.

 Crushing: Polluted soils are fed to a crushing machine through forklifts, and then are crushed and screened (dry separation). Large stones are screened out. Fine soils are fed to an agitator. Every time, 10 m3 fine soils, a chemical agent and a little water are added to the agitator for agitation. The agent should be distributed evenly, to ensure good remediation effect.  Piling & maintenance: The pretreated soils are transported to the temporary soil storage zone for piling & maintenance. The maintenance time of organically polluted soils is eight to fifteen days. Depending on the degree of pollution, the soils to be maintained are respectively piled into long soil stacks. After the soil moisture content is adjusted to 30% or so through water replenishing, the soils should be covered by plastic films for maintenance. In the process of soil maintenance, soil moisture content should be measured by sample regularly, and the soils should be replenished water promptlypromptly as appropriate, to keep the water moisture content of 30% or so.

 Sampling test: Upon expiry of maintenance time, the maintained soils should be sampled for self-test at a frequency of 1 sample per 500 m3 soils. During the sampling process, sampling points should be set up strictly pursuant to the sampling specifications. Soil samples should be acquired from the specified depth, and the acquired soil samples should be sent to a qualified third-party test institution for analysis and test. If the pollutant concentration in the soils is below the target values of soil remediation, the soil remediation is accepted. Otherwise, the soils should be subjected to chemical oxidation again, until the self-test results are accepted.

(2) Thermal Desorption

① working principle

According to the different heating methods, thermal desorption technology can be divided into direct thermal desorption technology and indirect thermal desorption technology two types. The main difference between the two is the desorption system and exhaust system. For direct thermal desorption, the contaminated soil enters the thermal kiln and comes into direct contact with the flame or hot flue gas generated by the burner of the thermal kiln and is uniformly heated above the temperature at which the target contaminant is vaporized to separate the contaminants from the soil purpose. Direct thermal desorption has high processing capacity (20 to 160 t / h) due to direct contact between soil and flame, but also produces a large amount of tail gas treatment costs. Indirect thermal desorption of indirect contact with the soil heat medium, the desorption of gas through the

Shenyang Lvheng Environment Consulting Co. Ltd 130 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site condensation, filtration and emissions, with a small amount of flue gas, less production of dioxin key advantages, especially for high levels of pesticide organic pollutants governance , Indirect thermal desorption is selected for this project

The main technical parameters

● pre-treatment: the particle size of the soil <50mm, moisture content <20% (mass moisture content).

● Thermal desorption scale: 6~10t/h (single 5t/h, 3 sets, total 15t/h)

● feeding system: automatic feeding device, feed inlet should be prepared to maintain air tightness of the device to ensure the stability of the furnace incineration; feed should prevent waste clogging, to keep the feed clear; feed system should Under negative pressure to prevent the escape of harmful gases

● heating temperature and residence time: 400 ° C, 30min or 500 ° C, 20min

② process

Thermal desorption of soils comprises three steps: crushing, indirect thermal desorption, and test and acceptance of remediated soils.

 Crushing: Polluted soils are fed to a crushing machine through forklifts, and then are crushed and screened. Large stones are screened out. Fine soils are fed into the thermal desorption equipment through a conveyer belt.

 indirect thermal desorption

1) material after pretreatment, will meet material disposal conditions of closed to the feed system, and then into the indirect heat of combustion appendage, heated for the material, the organic pollutants in the soil evaporation gasification, and soil effective separation. Use natural gas as fuel.

2) after the contaminated soil in the thermal desorption device is fully heated and defouled, the soil is treated after cooling and spraying.

3) thermal release of the heated evaporation occurring in the appendage of mixed gas containing dust, after circulating water spray into the mist cans, gas purification tank (activated carbon), and then into the combustion chamber consists of 15 m high vent discharge.

4) after spraying, the liquid will enter the circulating water tank after buffering the water tank, and will be discharged regularly through air cooling and recycling or drainage waste water collection box and discharged into the comprehensive sewage treatment station of eastern medicine. Then through Shenyang Lvheng Environment Consulting Co. Ltd 131 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site the municipal drainage network into shenyang western sewage treatment plant treatment.

 Test and acceptance of remediated soils

For the soil with thermal desorption, a sample is collected at a frequency of 500m3 for self-testing.

Sampling points are arranged in strict accordance with the sampling specifications, and samples are collected at the predetermined depth using tools. In view of the soil testing conditions of the construction unit, the soil samples collected shall be analyzed and tested by the construction party. If the pollutant content in the soil is lower than the target value of repair, the restoration is qualified; if the target value is higher than the target value of repair, the thermal desorption is disposed.

After the chemical oxidation restoration, the standard soil was recycled in the new factory of dongyao. After thermal desorption restoration, the soil can be filled back or discharged as residual soil.

4.3.2 Primary Pollution Sources and Environmental Impact Analysis

4.3.2.1 Waste Gas

1. Volatile Organic Pollution Gas

In the process of ex-suit remediation, the volatile organic pollution gas is mainly generated during chemical oxidation and by the untreated soil stacks in the new factory.

(1) Chemical Oxidation Process of Soils

In the process of chemical oxidation of soils, a small quantity of VOCs will be volatilized. The soils under chemical oxidation should be covered by plastic films, to reduce the fugitive emission of

VOCs. In the process of chemical oxidation, soils should be replenished with water. In the process of water replenishing, the plastic films need to be pulled open, so a small quantity of VOCs will be volatilized. The polluted soils that need to receive chemical oxidation amount to 13,800 m3, and the

VOCs to be volatilized amount to 10 kg. Assume that the soil remediation period is 240 days; then, the fugitive emission of COCs amount to 0.0017 kg/h.

(2) Untreated Soil Stacks

Untreated soil cones include chemically oxidized soil and soil requiring thermal desorption, with a soil capacity of 67800 m3 (about 89496t). By analogy with relevant data, the VOCs volatilization amount of the soil reactor in this project is about 147.2kg/h, and that of SVOCs is about 308.7kg/h. To effectively reduce VOCs emissions without group, the construction unit shall be on the untreated soil pile body rainproof dust-proof net and plastic covering membrane, and compaction, spraying Shenyang Lvheng Environment Consulting Co. Ltd 132 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site inhibitors on a regular basis, at the same time, the earth need local open covering plastic film, covering, in a timely manner after removal of compaction. After taking the above measures, the discharges of VOCs and SVOCs without organization can reach 0.0256kg/h.

(3) Dust

Transferred to the new factory untreated Northeast Pharmaceutical Plant of contaminated soil is massive more, soil feeding and discharging process will produce a certain amount of dust, dust production is expected to about 7.8 t/a (chemical oxidation pretreatment of soil (allu bucket crushing)

1.6 t/a of producing dust capacity, hot stripping soil treatment (feeding, screening and discharge) 6.2 t/a) of producing dust capacity.

The soil chemical oxidation treatment process is located in the closed workshop, spraying water and dust. After the above measures are taken, the discharges of dust without organization are 0.16t,

0.0333kg/h, and the dust is discharged out of the workshop through the natural ventilation of the workshop.

The amount of dust produced in the process of soil thermal desorption is small, and the feeding port is located in a closed greenhouse. The soil is transported by a closed belt. Hot stripping discharging in airtight caigang room, export a spray device, and the measures, hot stripping section of dust emissions of 0.62 t, 0.1292 kg/h, natural ventilation through the workshop, the dust discharge outside the shop.

(4) Exhaust Gas from Thermal Desorption

A lot of dust, VOCs, SVOCS and a small amount of HCl and dioxins will be produced in the soil thermal desorption process. According to the repair plan need hot stripping treatment of soil, a total of

54000 m3, intends to repair the 666 (remobilised) in soil is about 0.6 t, DDT (about 19.7 t remobilised),

VOCs, about 32 t SVOCs about 22 about 60 t, t, TPH, discharge of hydrogen chloride by the thermal release attached about 0.3 t/a, SVOCs discharge quantity of about 60 t/a, the dioxin is about 0.03 g/a,

VOCs discharge quantity is about 70 t/a, soot is 8.5 t/a, After the above exhaust gas is treated by the thermal desorption exhaust gas purifier (spray + defogging tank + gas purifying tank + combustion chamber), the exhaust gas can be discharged to 15m high exhaust air cylinder. Project has three sets of indirect hot stripping equipment, according to the three sets of indirectly calculated amount of soil thermal stripping equipment processing, each indirect hot stripping device of hydrogen chloride emissions of 0.005 t/a, SVOCS emissions of 0.2 t/a, the dioxin emissions of 0.0002 g/a, VOCS Shenyang Lvheng Environment Consulting Co. Ltd 133 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site emissions by 0.233 t/a, soot emissions of 0.028 t/a.

According to the comprehensive atmospheric pollutant discharge standard "(GB16297-1996) and the tianjin industrial emissions of volatile organic compounds control standard" (DB12/524-524), due to the project for the vent stack height of 15 m, not a radius of 200 m above the building more than 5 m, 50% tighter emissions rate standard execution.

Table 4.3-1 describes the generation and discharge of exhaust gas generated by thermal desorption. Table 53Table 4.3-1 Generation and Discharge of Exhaust Gas from Thermal Desorption Quantity Discharge of Generation Removal Running Pollution Exhaust Pollutant Quantity Concentration Rate Quantity Efficiency Duration Source Gas (t/a) (mg/m3) (kg/h) (t/a) (%) (h) (m3/h) HCl 0.4 0.7 0.003 0.015 95 Exhaust SVOCs 60 28 0.126 0.6 99 gas PCDDs 0.03g 0.03ng/m3 125.1ng/h 0.0006g 98 generated 4500 4,800 VOCs 69.99 32.7 0.147 0.699 99 by thermal Smoke desorption 8.49 4 0.018 0.0084 99 dust Environmental Spray , defogging tank , gas purification tank (activated carbon adsorption), combustion protection measures chamber and 15m high exhaust cylinder As described in Table 4.3-1, after appropriate environmental protection measures are taken in the process of ex-suit remediation, both the discharge concentration and discharge rate of HCl meet the standard (100 mg/m3 and 0.91 kg/h) specified in Table 2 of Comprehensive Emission Standard for

Air Pollutants (GB16297-1996), the discharge concentration of PCDDs meets the standard (0.1 ngTEQ/m3) specified in Standard for Pollution Control on Hazardous Waste Incineration (Exposure

Draft), both the discharge concentration and discharge rate of VOCs are below the limits (80 mg/m3,

8.3 kg/h) specified in Table 2 (Requirements for Pollutant Emission Limits of Exhaust Funnels in New

Enterprises) of Emission Control Standard of Tianjin City for Industrial Enterprises' Volatile Organic

Compounds (DB12/524-2014), and both the discharge concentration and discharge rate of smoke dust meet the standard (120 mg/m3 and 14.4 kg/h) specified in Table 2 of Comprehensive Emission

Standard for Air Pollutants (GB16297-1996).

4.3.2.2 Wastewater

The wastewater discharged during Ex-situ Remediation includes Spray tank drainage and domestic wastewater generated by construction personnel.

1. Domestic Wastewater Generated by the Construction Personnel

Shenyang Lvheng Environment Consulting Co. Ltd 134 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

In the construction site, there are 20 construction personnel. The engineering construction period is 240 days, the consumption standard of domestic water is 50 L per person-day. Then, the required amount of domestic water is 1 t/d (or 240 t/a). Assume that the discharge of wastewater is approximately 80% of domestic water consumption; then, the discharge of wastewater is 0.8 t/d (or

192 t/a). The domestic wastewater generated by the construction personnel will be treated by the comprehensive sewage treatment station first, and then be discharged to the extension of western sewage treatment plant of Shenyang City through the municipal sewage pipe network.

2. Spray tank drainage

The discharge of wastewater is about 11.8t/d and 2832t/a. The main pollutants in wastewater are pH, CODcr and SS. The pH value is about 4, and the production concentration of CODcr and SS is

500mg/L and 200mg/L respectively. The wastewater is regularly discharged to the comprehensive sewage treatment station of the new factory, and then discharged to the extension of western sewage treatment plant of Shenyang City through the municipal sewage pipe network.

3. Initial Rainwater

Large quantities of soils are piled in the new factory, and the piled soils are covered by plastic films. In order not to pollute the soils and groundwater of the new factory, rainwater drainage trenches are set up in the open-air soil piling site. The initial rainwater is collected, and then discharged to the comprehensive sewage treatment station.

Shenyang Lvheng Environment Consulting Co. Ltd 135 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 54Table 4.3-2 Generation and Discharge of Wastewater Generation Discharge Type of Pollutant Concentrati Quantity Concentratio Quantity Direction Wastewater on (mg/L) (t/a) n (mg/L) (t/a) The wastewater is CODcr 300 0.0576 200 0.0384 regularly discharged to the comprehensive NH3-N 20 0.0038 20 0.0038 sewage treatment station Domestic of the new factory, and wastewater then discharged to the (192 t/a) extension of western SS 250 0.048 140 0.0288 sewage treatment plant of Shenyang City through the municipal sewage pipe network. The wastewater is CODcr 500 1.416 200 0.5664 regularly discharged to the comprehensive sewage treatment station Spray tank of the new factory, and drainage then discharged to the (2832 t/a) extension of western SS 200 0.5664 150 0.4248 sewage treatment plant of Shenyang City through the municipal sewage pipe network. 4.3.2.3 Noises

The main sources of noise in the soil restoration process of this project are thermal desorption equipment, screening device, forklift and other equipment. The intensity of such mechanical noises is usually 70 to -100 dB(A), as described in Table 4.3-3. Table 55Table 4.3-3 Generation and Emission of Noises During Soil Remediation (dB(A)) No. Equipment Quantity Noise Intensity (dB(A)) Thermal desorption 1 3 90-100 equipment 2 Screening plant 3 75-85 3 Allu bucket 1 70-80 4 Forklift 1 70-80 5 Soil transfer vehicle 1 70-80 4.3.2.4 Solid Wastes

In the process of Ex-situ Remediation, the generated solid wastes mainly include: the waste activated carbon produced by the adsorption of activated carbon and Domestic wastes generated by construction personnel Table 4.3-4 describes the solid wastes generated by the soil remediation engineering.

Shenyang Lvheng Environment Consulting Co. Ltd 136 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 56Table 4.3-4 Generation of Solid Wastes Generating Discharge Destination No. Pollution Factor Quantity (t/a) Domestic wastes They are transported and disposed by the environmental 1 generated by 2.4 sanitation authorities. construction personnel They are temporarily stored in the hazardous waste depot 2 Waste activated carbon 36 of the new factory,and disposed of by incineration device

By table 4.3 4 shows that the project is expected to produce 36 t waste activated carbon, belong to the hazardous waste (HW49 other waste), by staging between northeast pharmaceutical waste for the new site, and by Northeast Pharmaceutical Plant incineration disposal of hazardous waste incineration device; The production volume of household garbage is 2.4t/a, which shall be uniformly cleared and handled by the sanitation department.

The temporary storage space of hazardous waste includes the storage space of solid and semi-solid waste. The total area is about 3000 m2, and the storage height is no more than 2m. It is in the form of barrels, with a specification of 200kg, a daily storage capacity of 40t, a maximum storage period of 45d, and a design service life of 50a. The hazardous waste temporary storage room is used for storing the incineration residues, fly ash, waste activated carbon, raw materials and auxiliary reaction products, waste machine oil, etc. produced by the eastern medicine hazardous waste incinerator. The waste activated carbon produced by this project can be stored in the temporary storage room of hazardous waste. The output of project waste activated carbon is 36t. Therefore, the existing hazardous waste temporary storage room of Northeast Pharmaceutical Plant can store the hazardous waste generated by this project.

Northeast Pharmaceutical Plant incinerator was founded in 2011 by shenyang environmental science research institute of the Northeast Pharmaceutical Group Co., Ltd. Long-distance transformation pollution treatment project of construction project environmental impact report, and in

2011, on June 27, the eia approval, approval document number of shen environmental review words

[2011] no. 187. The incinerator has been built and put into use.

Incineration capacity: 20t/d(or 7300t/a),Smoke duration: greater than or equal to 2S; Residual heat burn reduction: less than 5%; The reduction rate of harmful substances reached > 99.99%.

Second combustion chamber of flue gas temperature: 1100-1300 ℃ or higher.

According to the eia approval, the incinerator is mainly used for the residual kettle, high

Shenyang Lvheng Environment Consulting Co. Ltd 137 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site concentration mother liquor and non-biochemical waste water generated in the incineration process.

The hazardous waste activated carbon produced by this project can be burned. And the amount of hazardous waste produced by the project is about 36t. The capacity of the incinerator can meet the needs of the project.

Through the above analysis, all kinds of solid waste generated in the soil restoration process will not affect the surrounding environment after proper treatment.

4.3.2.5 groundwater

Engineering contaminated soil chemical oxidation (7000 m2) repair workshop, hot stripping repair area (including thermal stripping process of untreated soil staging area, such as pretreatment, disposal areas, a total of about 11000 m2) has taken strict anti-corrosion, seepage control measures on the ground, to avoid the project soil restoration, especially pollution during the staging of groundwater pollution caused by the site. It is required that the anti-seepage performance of the anti-seepage layer should be no lower than the anti-seepage performance of 1.0×10-10cm/s. In this project, cement base permeable crystalline water-repellent was added into the concrete, with a structural thickness of 310mm.

After the operation of the project, a small amount of waste water will be generated. Relying on the existing drainage pipe network in the Northeast Pharmaceutical Plant plant, it will not have a direct impact on the groundwater. The surface of the contaminated soil deposit area is covered with plastic film tarpaulin. After the ground is strictly impervious to infiltration, the pollutants in the soil will not contaminate the soil through rainfall infiltration into the ground. In addition, after the initial rainwater collection in the eastern medicine factory area on which the project is based, it will be discharged into the sewage treatment station without the formation of ground runoff, which will pollute the soil and groundwater. Therefore, the construction of this project will not have a significant impact on the groundwater environment.

4.3.2.6 Environmental Impact Prediction for Decommissioning Period

Considering actual conditions, the soil remediation in the new factory is estimated to take 240 days. After soil remediation is complete, the remediation engineering will be dismantled. The remediated soils for the construction project mainly contain seven heavy metals (including arsenic, copper, zinc, nickel, lead, chrome, and mercury), five PAHs (including tetraphene, benzoapyrene, benzo[b]fluoranthene, dibenz[a,h]anthracene, and indeno(1,2,3-cd)pyrene), two types of POPs Shenyang Lvheng Environment Consulting Co. Ltd 138 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(including DDT, DDD, DDE, and -hexachlorocyclohexane), aniline, two types of VOCs (including benzene and chloroform), and TPH(

In the decommissioning period, the equipment concerned will be dismantled and be sold.

4.3.3 Pollution Control Measures 4.3.3.1 Measures for Air Pollution Control For Ex-situ Remediation, exhaust gas is generated while soils are fed and outputted, and are subjected to chemical oxidation and thermal desorption. The following measures should be taken to control air pollution.

1. Exhaust gas generated while soils are fed, crushed, agitated, and outputted

The soil chemical oxidation treatment process is located in the closed workshop, spraying water and dust. The amount of dust produced in the process of soil thermal desorption is small, and the feeding port is located in a closed greenhouse. The soil is transported by a closed belt. The thermal desorption material is located in the closed color steel house, and a spray device is set at the exit.

After the above measures are taken, dust is discharged out of the workshop through the natural ventilation of the workshop.

2. Exhaust gas generated in the process of chemical oxidation

The soils under chemical oxidation are covered by plastic films, to reduce the fugitive emission of VOCs and SVOCs.

3. Exhaust gas generated by the untreated soil stacks

Cover the untreated soil stacks with dust net and plastic rain-proof film, compacted and regularly spray inhibitors to reduce the discharges of VOCs. When the untreated soil is taken out of the soil, it needs to partially open the covered plastic film and cover and compacted the soil in a timely manner.

4. Exhaust gas generated in the process of thermal desorption

The waste gas generated in the process of soil thermal desorption is discharged at an altitude of

15m high exhaust air tube after reaching the standard through spraying , mist removal tank , gas

Shenyang Lvheng Environment Consulting Co. Ltd 139 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site purification tank (activated carbon adsorption) and combustion chamber purification.

4.3.3.2 Measures for Wastewater Pollution Control

The waste water produced in the process of soil chemical oxidation and thermal desorption is mainly discharge from spray tanks and domestic sewage of employees. The above wastewater is discharged into the new comprehensive sewage treatment station of the northeast pharmaceutical factory, and then discharged into the west shenyang sewage treatment plant through the municipal sewage pipe network after reaching the standard.

4.3.3.3 Measures for Noise Pollution Control

Noise generated in the process of soil chemical oxidation and thermal desorption mainly comes from thermal desorption equipment, screening device and forklift truck. Specific prevention and control measures are as follows:

1. When selecting equipment, thermal desorption equipment, screening device and forklift truck, low-noise equipment shall be preferred to reduce noise from the source strength;

2. Reasonable layout is of great importance. High-noise noise sources should stay away from the factory boundaries, thus reducing noises through range attenuation. In addition, vibration damping measures should be taken for equipment foundations.

4.3.3.4 Measures for Solid Waste Pollution Control

The solid waste produced in the process of soil remediation is mainly the waste activated carbon produced by the adsorption of activated carbon and the domestic waste of employees. Among them, the waste activated carbon belongs to the hazardous waste (HW49 other waste), which is temporarily stored in the hazardous waste room of the new pharmaceutical factory in and incinerated by the hazardous waste incinerator of eastern medicine. Due to the pollutants concentration distribution in the soil, soil management process, activated carbon usage may be below or above forecast, should be based on monthly, hot stripping exhaust test result judgment, activated carbon adsorption effect, that the test results is high, should be timely replacement of activated carbon. Household waste shall be uniformly cleared and disposed of by the sanitation department.

4.3.3.5 Measures for groundwater Pollution Control

Strict anti-corrosion and anti-seepage measures have been taken on the ground of the plant to avoid the ground water pollution caused by the soil restoration project of this project, especially Shenyang Lvheng Environment Consulting Co. Ltd 140 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site during the temporary storage of contaminated soil. It is required that the anti-seepage performance of the anti-seepage layer should be no lower than the anti-seepage performance of 1.0×10-10cm/s. In this project, cement base permeable crystalline water-repellent was added into the concrete, with a structural thickness of 310mm.

Shenyang Lvheng Environment Consulting Co. Ltd 141 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

5. Social Environmental Impact Assessment and Analysis 5.1 Social environmental impact identification Based on the engineering analysis, analyze the possible impact of the project on the social environmental impact factors during the construction period and operation period, and establish the main identification matrix of environmental impact factors, as shown in Table 5.1-1. Table 57Table 5.1-1 Social Environment Impact Identification Project activity elements Soil excavation Soil remediation Soil transport Land use -1SP +3LP social environment traffic -1SP -1SP Humanities and Public health -1SP -1SP Ecology city traffic -1SP Remarks: Impact degree: 1 - slight; 2 - general; 3 - significant Impact period: s-short-term; L-long-term; Range of influence: P-local; W-large range; Influencing nature: + - favorable; - negative; 5.2 Social environmental impact assessment factor The project does not involve land acquisition, house demolition and resettlement. According to Table 5.1-1, the social environmental impact assessment factors for this project are land use, transportation and public health. 5.3 Social Environmental Impact Analysis 5.3.1 Impact of the Project on Traffic The impact of the project on traffic is mainly the stage of soil transport. According to the project engineering analysis, after the excavation of the project, the contaminated soil is transported by on-site mechanized loading and dump trucks, and transported by Heavy Industry North Street, Shenda Road, Honghu Street, Development Road, Xihe Qibei Street and Shenxi Liudong Road. To Dongying New Factory, the transportation distance is 23km. Therefore, the soil transport phase will have a certain impact on traffic in Shenyang. However, due to the short construction period of this project, the impact on traffic is short-term. 5.3.2 Impact of the Project on Land Use Heavy metals, SVOCs, DDT, etc. in the original soil of the project all exceeded the standards. According to the overall land use plan of the government, the site will be redeveloped and used as a residential land (second-class residence) in the future, and on February 12, 2017. The land was acquired by China Resources Land (Shenyang) Co., Ltd. If it is not repaired, it will Shenyang Lvheng Environment Consulting Co. Ltd 142 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site affect future land use. 5.3.3 Impact of the Project on Public Health The impact of the project on public health is mainly reflected in the process of soil excavation and soil transport. The dust and noise generated during soil excavation will have an impact on public health; the noise generated during the soil transportation process will affect the residents' public health. 1. Effect of construction dust on public health Construction dust is mainly composed of particles with a large particle size. If dust particles enter the lower respiratory tract at 10 μm, they will accumulate in the alveoli when they are less than 2.5 μm, causing a series of diseases, which can lead to lung failure in severe cases. dead. By consulting the relevant literature, in some factories or construction sites, due to construction personnel activities or the operation of machinery, a large amount of dust is suspended in the control, which will not only increase the dust concentration, but also reduce the air quality. Because the dust contains a lot of heavy metals such as oxysulfuron, and the reaction is likely to produce poison, it will not only affect the growth of surrounding plants, but also affect people's health. After all, dust particles containing heavy metals will move with the air. Once micro-particles enter the respiratory system and accumulate in the alveoli, a series of diseases will result. Coupled with the large amount of bacteria and viruses in the dust, dust will become a medium for bacteria and viruses to speed up the spread, seriously affecting the health of residents. According to the engineering analysis, dust will be generated during the construction process of this project, and the estimated range of impact is about 200m. According to the site investigation, Wankelun Runyuan (4100 people), Xingong New Village (4000 people) and Lanting Xinju (4100 people) are involved in this area. ), Tiexi District government office staff (1000 people) about 12,000 people, 4560 households. Therefore, the dust generated during the construction of the project will have a significant impact on residents and office workers in the above communities. However, due to the short construction period of the project and the corresponding measures taken, the impact on the health of residents will be short-lived. After construction, the impact disappeared.

Shenyang Lvheng Environment Consulting Co. Ltd 143 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

2. Impact of construction and vehicle transportation noise on residents' health (1) Combining with project engineering analysis, the noise generated during the construction process mainly comes from the operation of construction equipment. The estimated noise value is between 80 and 90 dB. Related data shows that: “40 dB(A) continuous noise affects 10% of people’s sleep, 70 dB(A) affects 50%; sudden noise is 40 dB(A), 10% of people can wake up, and 60 dB can awaken 70% of people.” This shows that the construction process will cause residents to sleep influences; (2) Affects conversation and communication. Usually the conversation is no louder than 70 dB, and the loudness is up to 85 dB. When the noise level is close to the conversational level, normal conversation will be disturbed. When the noise level is more than 10 dB higher than the speech level, the speech is completely masked. Normally, 65 dB noise will interfere with normal conversations. You must raise your voice or close to the distance to talk. If the noise level exceeds 90 dB, shouting is also not clear. It can be seen that the noise generated during the construction process will affect the normal conversation and communication of the people; (3) Effects on the nervous system. Noise acts on the nervous system for a long time and can cause dizziness, headaches, and tinnitus. It interferes with the concentration of mental work and reduces the ability to work. Under the action of noise, the human brain wave changes, and the time value of vestibular and motor nerves also occurs. Variety. After the noise acts on the nervous system, it also affects other systems, such as the role of the digestive system, which can cause loss of appetite; (4) Affect work. Distract people's attention, make people easily tired, unresponsive, affect work efficiency, increase work error rate. However, due to the short construction period of the project, after taking corresponding measures, the impact on the residents' health is short-lived. After construction, the impact disappeared. 5.3.4 Prevention measures 1. Traffic prevention measures Taking into account the impact of project construction on traffic, the project has formulated the following plans: The construction unit will enhance the traffic safety education for the

Shenyang Lvheng Environment Consulting Co. Ltd 144 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site construction vehicle drivers. The construction vehicles will drive on designated routes and slow down when crossing densely populated areas. Long-term school, market, traffic In densely populated areas such as Yaodao, the construction unit shall assign special persons to be responsible for on-site traffic safety management; it is strictly forbidden to overload or overrun vehicles on the road; for large-tonnage vehicles entering and exiting narrow roads, measures shall be actively taken to prevent and perfect them. Traffic technical specifications signs. 2. Noise prevention measures ① During the implementation period of the project, the noise emission shall not exceed the limit value of the “Emission Standard for Environmental Noise of Construction Site Boundary” (GB 12523-2011), that is, 70dB in daytime and 55dB at night. ②Try to use low-noise or construction machines equipped with noise elimination and noise reduction equipment. ③ For strong noise equipment, use noise enclosures to close and block noises. ④Strengthen the promotion of environmental awareness, adopt effective measures to control artificial construction noise, strictly manage and minimize noise disturbance. ⑤The construction personnel who operate the high-noise equipment at close range should wear earplugs, and should arrange rotation work or shorten their working time to reduce the harm caused by noise to human ears. ⑥ Reasonably arrange the construction time, and it is forbidden to work from 22:00 pm to 6:00 the next day. If night construction is required, the relevant departments must go through the relevant approval procedures in advance and obtain consent from the surrounding residents before the construction can be carried out.

3. dust prevention measures (1) Set up a continuous enclosure of not less than 2.5m around the restoration site and use a mobile spray dust collector to spray dust at the construction site; (2) Use an integrated machine for soil remediation to ensure that the contaminated soil is stirred and broken in a completely enclosed environment, and that the surface of contaminated soil in the soil temporary storage area is covered with rain-proof cloth or membrane, and bare stacking is prohibited. Also, the rain-proof cloth should be fixed so as not to be blown by the

Shenyang Lvheng Environment Consulting Co. Ltd 145 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site wind; (3) In the process of soil excavation and loading, speed and drop should be slowed down. Transport vehicles should be covered with canvas. Spills and leakages must be strictly prohibited. Vehicles entering and exiting the site should be limited in speed. Construction machines and transport vehicles should be strengthened for overhaul and maintenance. Vehicles with exhaust gas exceeding the standard; transport vehicles shall be equipped with exhaust gas purifiers, use fuels that meet the national standards, and prohibit the use of inferior fuels in order to reduce the emission of harmful gases from machinery and vehicles; all motor vehicles shall be entrusted with corresponding qualifications by the municipal environmental protection administrative department according to law. The agency conducts regular inspections of exhaust pollution and obtains environmental protection inspection marks. 4, strengthen supervision (1) Introduce the basic conditions of the project through television, newspapers, radio, network, and posting announcements, so that neighboring residents can understand the project situation and pollution prevention and control measures. The publicity content includes project overview, prevention and control measures, and telephone number reporting. The process did not take measures as required, resulting in an impact on the lives and health of the surrounding residents. Residents could report to the relevant authorities in Shenyang through the telephone; (2) Shenyang Municipal Environmental Protection Bureau, Shenyang Urban Law Enforcement Bureau, and Shenyang Public Security Bureau should adopt a linkage mechanism to timely respond to problems in violation of laws, discipline, and environmental protection caused by the construction process, supervise them, and take corresponding measures to deal with the problems arising.

Shenyang Lvheng Environment Consulting Co. Ltd 146 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

6. Public Participation According to the requirements of the Law of the People's Republic of China on Environmental Impact Assessment, except for the situations required by the state to be kept confidential, for construction projects that may cause significant impacts on the environment and for which an environmental impact report should be prepared, the construction unit should, before the submission of the environmental impact report for approval, hold a demonstration meeting, hearing meeting, or adopt other forms to solicit the opinions of the relevant units, experts and the general public.

6.1 Purpose and Principles of Public Participation 6.1.1 Purpose of Public Participation Public participation refers to the bidirectional exchange between the project party and the public through the environmental impact assessment work. Its purpose is to make the project fully recognized by the public and not endanger and threaten public interests during the implementation of the project so as to achieve the harmonization of economic benefits, social benefits and environmental benefits. Establishing a normal mechanism for public participation in environmental supervision and management enables the public in the affected areas of the project to keep abreast of environmental information and have the opportunity to express their opinions through normal channels. It is necessary for the decision-making and smooth implementation of construction plans. It can let the public help identify important issues that may be caused by the project, especially many potential environmental issues, and understand the public's concern for conservation or the public's primary concerns so that sensitive measures can be effectively protected. It can help to understand the public's opinions, opinions and suggestions, pool their wisdom, and find the basis for safeguarding the vital interests of the public so that the public can play a supervisory role in implementing the environmental protection measures of the project construction; it can enhance the feasibility and social acceptability of project environmental impact assessment to ensure the feasibility and rationality of environmental protection measures; it can mobilize the public to participate in environmental protection and raise citizens' awareness of and enthusiasm in environmental protection. In short, the implementation of public

Shenyang Lvheng Environment Consulting Co. Ltd 147 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site participation in the environmental impact assessment process can enhance the effectiveness of the environmental impact assessment, raise public awareness of the environment, improve the environmental impact assessment system, and protect the quality of the environment, which is conducive to maximizing the overall and long-term benefits of the project. 6.1.2 Principles of Public Participation (1) Impartiality, Fairness and Openness In the establishment of the system for public participation in evaluation, the principles of impartiality, fairness and openness must be followed. The symbolic power of impartiality restricts the mechanism of participation, making government intervention in correcting market failures at the same time to avoid and overcome the government failure, and the choice (sampling) of the subjects consulted or participating in the deliberations should be representative so as to ensure that the public participating in the deliberations come from all walks of life and represent a social section. Fairness symbolizes the participation of the interests of the coordination mechanism. Equitable distribution and coordination of limited natural resources and social resources were also one of the basic goals of urban planning. Public participation must be based on the coordination of the interests of all societies to find out the public interest that truly reflects the public will. This public interest is the policy basis for the government to formulate and implement the project and is one of the effective ways to gain public support for the planning. Openness symbolizes that the information interaction mechanism of public participation must protects the public's right to information on the project, the right to participate and supervision, to improve the use of administrative power and administrative work transparency, and maintain social justice to ensure that the public have a more comprehensive cognition and more accurate judgment during their participation. (2) Specificity and Operability The formulation of public participation system must have strong specificity and operability. Public participation is a highly social work. It is necessary to explain to the participants that the project may exert positive and negative impacts on society, economy, and environment, especially on resource allocation and public interests so that the public can understand the overall situation of the project as soon as possible to make a correct judgment. At the same time,

Shenyang Lvheng Environment Consulting Co. Ltd 148 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site the results of public consultation should be dealt with quantitative statistics to render the evaluation more convincing. The evaluation results should be easy to operate and help with the decision-making process. We must also give full consideration to the difference in cognitive ability and educational backgrounds of people in different social strata. Evaluation indicators or factor descriptions that require public consultation should be simple, clear, and understandable, and should not be too specialized. (3) Dynamic Participation The formulation of public participation evaluation system should follow the principle of dynamic participation. The types of projects, operation phases and affected strata (public composition) in each project are undergoing changes and adjustments. Therefore, the contents of the public consultation or indicators and emphasis are different. The selection of the factors of evaluation index and the corresponding weights should be dynamically adjusted according to the project and its process. 6.2 Scopes and Subjects of Public Participation The investigation of public participation in this study concerned the evaluation scope and the main affected areas of the remediation project, focusing on the opinions of social organizations and individuals in the areas. The survey included local people, staff from enterprises and public institutions, and staff from government agencies affected by the project. The age groups covered young and middle-aged people as well as the elderly. 6.3 Ways and Contents of Public Participation 1、 a message publicity ⑴ on-site publicity Northeastern Pharmaceutical Group Co., Ltd. staff in January 21, 2018 to January 25, respectively, Vanke Long Run Park, Heavy Industries Village, Shenyang City, No. 36 Middle School on-site publicity, publicity includes: project overview, to be taken by the environmental protection Measures, contact information (including construction units, evaluation units) mailing address, contact telephone number, contact person and e-mail address; public notice also shows the scope of time for public comment. Live public shots shown in Figure 6.3-1.

Shenyang Lvheng Environment Consulting Co. Ltd 149 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 39Figure 6.3-1 An environmental impact assessment publicity site 2、questionnaire ● Questionnaire method Northeastern Pharmaceutical Group Co., Ltd. staff conducted a questionnaire survey on the public involved in the project from January 21 to January 22, 2018. The contents of public participation in environmental impact are shown in Table 6.3-1 and 6.3-2.

Shenyang Lvheng Environment Consulting Co. Ltd 150 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 58Table 6.3-1 Public Opinion Survey Regarding the Northeast Pharmarcy POPs Site Contamination Project (On-site remediation) The original Northeast Pharm plant was located in No. 37 Zhonggong North Street, Tiexi District, Shenyang City. The Project Office of "China Polluted Site Management Project" in Liaoning Provincial Environmental Protection Department intends to invest RMB 88.041 million yuan for treatment of the 114,000 m2 POPs contaminated sites in the plant area. The contaminated soils of the contaminated soil will mainly be excavated. Construction Part of the contaminated soil excavated will directly be transported to the new Northeast project overview Pharm plant. Some of the contaminated soils will be remediated on-site and sent to the Laohuchong domestic waste landfill as cover soil after remediation; Part of the contaminated soil will be dredged and transported to the new Northeast Pharm plant for oxidation or thermal desorption. After the remediation are completed, backfill or residue treatment will be performed. The soil remediation period will be about 120 days. Atmosphere: Dust generated from soil removal, transfer, remediation, backfill, etc.; Wastewater: Transport vehicle wheel washing water and a small amount of domestic Main problems sewage; of environmental Noise: site formation, soil digging, remediating mechanical work noise; pollution Solid wastes: Construction wastes left on-site, polluted soil dredged out and a small amount of domestic garbage generated by the staff. Atmosphere: Set a continuous enclosure around the site to be remediated, dust removal using mobile spray dust collector. Soil surface soil temporary storage area should be covered with rain cloth or film. Soil remediation area to build a shed with membrane and other measures; Wastewater: Vehicle flushing wastewater to be fully reused and not discharged. Domestic sewage to be drained into Xiannu River Sewage Treatment Plant via municipal Proposed sewage pipe network, and seepage control and leakage prevention measures were environmental provided for car wash yard, soil temporary storage area, soil remediation area and along protection pipelines; measures Noise: Take noise reduction, sound elimination and other measures; Solid waste: After being dredged, the contaminated soil directly covering the soil as landfill should be transported as soon as possible, solidified and stabilized on-site. After chemical oxidation, some of the contaminated soil will be backfilled to the new Northeast Pharm plant and some will be transported to domestic garbage landfill as cover soil. Construction waste will be transported to the construction landfill, construction workers’ living garbage will be cleared and transported by the sanitation sector. Name Age Gender Educational level Occupation Work unit (mailing Tel. address) I. Multiple-choice questions (Please tick √ in the □) 1.Do you know about the project? □ Yes □ No 2. In your opinion, how is the current local environmental quality? □ Very good □ Good □ Fair □ Bad 3. In your opinion, which aspect of the surrounding environment will be possibly affected by this project? □ Air □ Surface water □ Acoustic environment □ Groundwater □ Ecology □ Others 4. In your opinion, how serious will the impact of this project on the local environment be? □ No impact □ Mild impact □ Certain impact □ Great impact 5. Is this project conducive to promoting local economic development: □ Very conducive □ Conducive □ Unfavorable □ Very unfavorable 6. Do you support the construction of this project: □ Support □ Object (explain why) II. Comments and suggestions

Signature of form filling person (mm/dd/yyyy)

Shenyang Lvheng Environment Consulting Co. Ltd 151 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 59Table 6.3-2 Northeast Pharmarcy POPs Site Contamination Project (Ex-suit remediation) Public Opinion Survey Public Opinion Survey The project is located at Shen Xi Liu Dong Road, Shenyang East Economic and Technological Development Zone, within the new factories of Northeast Pharmacy Group. It is proposed to use chemical oxidation and thermal desorption to remediate some Construction contaminated soils in the production area of the North Second Road of the former project overview Northeast Pharm plant, with about 67,800 m3 of earthwork. Soil after the remediation will be used for backfill of the new Northeast Pharm plant or for residual emissions. The remediation period is expected to be 8 months. Atmosphere: Dust from soil feeding and discharge; Dust from soil pretreatment crushing and mixing; soil thermal desorption produce exhaust gas; soil chemical oxidation process VOC emissions s; untreated soil piles VOCs emissions. Main problems Wastewater: quench tower drainage, caustic tower drainage and a small amount of of environmental domestic sewage. pollution Noise: operating noise from shredders, mixers, fans and other equipment. Solid wastes: Dust from soil feeding and discharging collected by cyclone dosing process, dust collected by cyclone and bag filter, activated carbon waste and domestic waste. Atmosphere: Dust from Soil feeding and discharging dust will be collected by gas gathering and cyclone filter and emits at 15 meters high flue ; Dust from soil pretreatment crushing and mixing will be treated by closed processing with no discharge outside; Emit of soil thermal desorption exhaust after treatment by the exhaust purification device of 25 meters high; soil chemical oxidation process covered with plastic film; untreated soil pile covered plastic film, periodic inhibitor spraying. Proposed Wastewater: Caustic wastewater after neutralization treatment, together with environmental domestic sewage and quench tower drainage will be discharged into the northeast protection pharmaceutical new plant integrated sewage treatment station, and then discharged into measures the sewage treatment plant through the municipal drainage network. Noise: Use low noise equipment, basic vibration reduction, reasonable layout of equipment in the plant. Solid wastes: Regular cleaning, recycling, thermal desorption treatment of the cyclone filter trapped dust from the feeding and discharging process; fly ash, waste activated carbon waste will be dealt by a qualified unit; living garbage cleared and transported by the sanitation sector. Name Age Gender Educational level Occupation Work unit (mailing Tel. address) I. Multiple-choice questions (Please tick √ in the □) 1.Do you know the about project: □ Yes □ No 2. In your opinion, how is the current local environmental quality? □ Very good □ Good □ Fair □ Bad 3. In your opinion, which aspect of the surrounding environment will be possibly affected by this project? □ Air □ Surface water □ Acoustic environment □ Groundwater □ Ecology □ Others 4. In your opinion, how serious will the impact of this project on the local environment be? □ No impact □ Mild impact □ Certain impact □ Great impact 5. Is this project conducive to promoting local economic development: □ Very conducive □ Conducive □ Unfavorable □ Very unfavorable 6. Do you support the construction of this project: □ Support □ Object (explain why) II. Comments and suggestions

Signature of form filling person (mm/dd/yyyy)

Shenyang Lvheng Environment Consulting Co. Ltd 152 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

●Statistical analysis of the survey results This public participation survey collected public opinions by means of a questionnaire survey on issues of public interest that might be affected around the construction project. The construction unit issued 60 questionnaires for the sensitive spots near the project and collected 60 copies with a recovery rate of 100%. The public opinion statistics results are shown in Table 6.3-3, 6.3-2. Table 60Table 6.3-3 Statistics Regarding the Participants in Public participation Survey Item Contents Votes received Percentage (%) Male 39 65.0 Gender Female 21 35.0 Tertiary institutions and 57 95.0 above Educational level Junior and senior high school 1 1.7 Primary school 2 3.3 20-30 years old 20 33.3 30-40 years old 36 60.0 Age 40-50 years old 3 5.0 Over 50 years old 1 1.7 According to the structure of the surveyed population in Table 6.3-4, the survey basically included residents of all ages and education levels near the project. Among them, people at 20 to 40 years of age with junior college education accounted for the majority of the population. Therefore, the results are comprehensive and rational. Table 61Table 6.3-4 Opinion Statistics Regarding the Public Participation Survey Percentage in valid Survey contents Survey results questionnaires % Do you know about the Yes 60 100.0 project? No 0 0.0 Very good 41 68.3 In your opinion, how is the current local environmental Good 15 25.0 quality? Fair 1 1.7 Bad 3 5.0 Air 4 6.7 In your opinion, which Surface water 4 6.7 aspect of the surrounding environment will be Acoustic environment 2 3.3 possibly affected by this Groundwater 53 88.3 project? Ecology 1 1.7 Others 0 0.0 In your opinion, how serious No impact 59 98.3 will the impact of this Mild impact 0 0.0 project on the local Certain impact 1 1.7 environment be? Great impact 0 0.0 Very conducive 57 95.0 Is this project conducive to promoting local economic Conducive 3 5.0 development:? Unfavorable 0 0.0 Very unfavorable 0 0.0 Do you support the Support 60 100.0 construction of this project? Object 0 0.0

The public expressed their own opinions about the contents of the questionnaire.

Shenyang Lvheng Environment Consulting Co. Ltd 153 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

According to the surveyed public's age, sex, occupation and other statistics, we can observe from the comprehensive survey results in Table 7.4-2 that: (1) All the participants knew about the project. (2) 68.3% of the public thought that the local environmental quality was very good; 25.0% of the public thought that the local environmental quality was good; 1.7% of the public thought that the local environmental quality was normal, and 5.0% of the public thought that the local main environmental quality was not good. (3) 88.3% of the public thought that this project might affect the groundwater; 6.7% of the public thought that this project might have an impact on the air environment; 6.7% of the public thought that this project might have an impact on the surface water environment; 3.3% of the public thought that this project might have an impact on the sound environment; and 1.7% of the public thought that this project might have an impact on the ecological environment. This showed that the public had a clear understanding of the pollution of this project. (4) 98.3% of the public thought that the implementation of this project had no impact on the local environment, and 1.7% of the public thought that the implementation of this project had an impact on the local environment. (5) 95% of the public thought that this project could promote the local economic development, while 5% of the public thought that this project could promote the local economy favorably.

(6) All the participants support the implementation of this project. ③ forum

Meeting time: January 26, 2018 Venue: Shenyang Innovation H Block

Participants: Vanke Lang Run Park, Heavy Industry Village, Blue Ting Habitat, Shenyang City, 36 middle school representatives, a total of 10 people. At 9:00 on January 26, 2017, the public participation forum for environmental impact assessment of POPs contaminated sites in Northeast Pharmaceutical Factory officially started in the meeting room of Block H of Innovation Plaza in Shenyang. The company is located in: Shenyang Green constant environmental consulting Co., Ltd. introduced the construction

Shenyang Lvheng Environment Consulting Co. Ltd 154 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site project content. All the delegates consulted and discussed the impact that the project will have on production, life and environment during the construction process and the issues of concern to the masses. As a result, everyone has a better understanding of the significance of the project and the impact it has on promoting local economic development. At the symposium, all delegates said that dust would be generated during the construction of the project and noise would be generated from the construction equipment. The impact would be on the surroundings. We hope that in the formulation of the plan, we will fully consider the above factors and formulate reasonable and feasible environmental protection measures. During construction, Strict implementation of the above measures to reduce the impact on the surrounding environment.

Figure 40Figure 6.3-2 Forum site ⑵ secondary information publicity ① on-site publicity Northeastern Pharmaceutical Group Co., Ltd. staff in February 22, 2018 ~ February 28, respectively, Vanke Long Run Park, Heavy Industries Village, Shenyang City, No. 36 Middle School on-site publicity, publicity includes: project overview, to be taken by the environmental protection Measures, contact information (including construction units, evaluation units) mailing address, contact telephone number, contact person and e-mail address; public notice also shows the scope of time for public comment. Site public shots shown in Figure 6.3-3.

Shenyang Lvheng Environment Consulting Co. Ltd 155 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 41Figure 6.3-3 Secondary publicity site map ② newspaper publicity Northeastern Pharmaceutical Group Co., Ltd. staff on February 27, 2018 in Liaocheng Evening News on the publicity, publicity includes: project overview, the project may have an impact on the environment, to prevent or mitigate the adverse environmental impact of the measures and measures, the main Conclusions, major issues for soliciting opinions, the main ways public comment on the issue, and the starting and ending dates. Public information is shown in Figure 6.3-4.

Shenyang Lvheng Environment Consulting Co. Ltd 156 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 42Figure 6.3-4 newspaper publicity ③ questionnaire ● Questionnaire method Northeastern Pharmaceutical Group Co., Ltd. staff conducted a questionnaire survey on the public involved in the project from February 26 to February 28, 2018. The public participation in environmental impact is shown in Table 6.3-5.

Shenyang Lvheng Environment Consulting Co. Ltd 157 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 62Table 6.3-5 Northeast pharmaceutical factory POPs site contaminated sites project public opinion questionnaire The POPs contaminated site of Northeast Pharmaceutical Factory is located in No.37, Zhonggong North Street, Tiexi District, Shenyang (the former North Factory of Northeast Pharmaceutical Factory). This time, the main site of the project is 114,000 m2 of POPs contaminated sites. According to the "Remediation Plan of Dongfang POPs Venue (Production Area of North Factory of North Second Road in Northeast Pharmaceutical Group Co., Ltd.)", the contaminated soil will be disposed of by direct backfill, in-situ curing and stabilization technology, chemical oxidation and thermal desorption technologies . Among them, the soil that exceeds the goal of clearing Construction residential land but is lower than the standard of industrial land (excluding DDTs) is Project Overview directly transported to the new east medicine factory for backfilling. The single polluted soil of heavy metals is solidified and stabilized in situ within the contaminated site. After passing the inspection, Transported to the tiger rubbish landfill as cover soil; PAHs, DDTs and TPHs polluted soil, and in accordance with the 35% degradation rate can reach the repair target, using chemical oxidation method for processing, after passing the test, Organic contaminated soil or compound contaminated soil, thermal desorption treatment, after passing the test, the new plant in eastern medicine as residual emissions. It is estimated that 97500m3 of soil will be disposed The main environmental impacts of the construction process are as follows: the dust generated from soil clearing, transiting and temporary storage in the contaminated site, and road dust generated from the construction of motor vehicles and transport vehicles; the wheel washing water of transportation vehicles and domestic sewage generated by construction workers; Noise; clean up the contaminated soil and a small amount of staff The main generated garbage; problem of The main environmental impacts of soil remediation process are: VOCs generated environmental during chemical oxidation and thermal desorption processes and a small amount of HCl pollution and dioxins; quench tower, caustic tower waste water and employee domestic wastewater; equipment noise during remediation; soil input and discharge process Cyclone dust trapped dust; thermal desorption exhaust gas purification process cyclone dust collector and bag filter catching fly ash; activated carbon adsorption of waste activated carbon. 1, construction period ⑴ exhaust Before the project is started, a continuous enclosure of not less than 2.5m shall be set up around the site to prevent soil from digging and dust escape during the repair process. The construction site uses a mobile spray dust collector to spray dust and dust; the area where the curing is stabilized shall be integrated Machine repair; transport vehicles covered with canvas, is strictly prohibited sprinkler; strengthen excavation and transport management, improve the speed of excavation and removal, reasonable handling, standardize operations and narrow the scope of the impact of dust. The proposed ⑵ wastewater environmental Construction workers domestic wastewater, car wash wastewater are discharged protection into the south factory of Northeast Pharmaceutical Factory septic tank treatment, after measures treatment, discharged into the Fairy River sewage treatment plant centralized sewage treatment network; ⑶ noise Try to use low noise or equipped with noise reduction, noise reduction equipment construction machinery; reasonable arrangements for construction operation time, no night 22:00 to 6:00 the next day construction, construction at night, you must advance to the relevant departments for related Approval procedures, and with the consent of the surrounding residents in order to carry out construction.

Shenyang Lvheng Environment Consulting Co. Ltd 158 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

⑷ solid waste Different categories should be set up in the temporary storage area, and relevant classification labels should be set on the boundary of the soil storage. After the completion of the soil remediation project, the soil in the soil temporary storage area and the soil remediation area should be sampled and tested to prevent the pollution of the contaminated soil to the original non-pollution soil. Strict control of the whereabouts of contaminated soil, transport vehicles entering and leaving the site are subject to the confirmation process, transportation is assigned a person responsible for inspections on the way to ensure that all contaminated soil transported to the designated receiving point disposal. 2, repair period ⑴ exhaust The dust generated in the soil feeding and discharging process is collected by the gas gathering hood and discharged by a cyclone dust collector at a height of 15m. The large amount of dust generated during the crushing and mixing process is sealed in a closed grinder and a mixer and is not discharged. The treated soil pile is covered with plastic film The proposed and the inhibitor is sprayed on a regular basis. The exhaust gas generated during the environmental thermal desorption of soil is cyclone dust removal + high temperature incineration + protection cooling and cooling + bag dusting + activated carbon adsorption + alkali washing, Exhaust measures pipe discharge at high altitude. ⑵ wastewater The quench tower wastewater, caustic tower waste water and employee domestic sewage are discharged into the new factory integrated sewage treatment station of Northeast Pharmaceutical Factory to reach the standard and then discharged into Shenyang Sewage Treatment Plant Expansion Project by municipal sewage pipe network. ⑶ noise Soil grinder, mixer, fan in the choice of equipment to give priority to the use of low-noise equipment; reasonable layout, the noisy noise source far away from the factory boundary, through the attenuation attenuation; and equipment to take damping measures. ⑷ solid waste Soil feeding and discharging process The dust collected by the cyclone is regularly cleaned and recycled for thermal desorption disposal. The fly ash and activated carbon produced during the thermal desorption process are sent to the Northeast New Factory Disposal Area for temporary storage, entrusted with relevant qualification Units to deal with; staff generated garbage, unified by the sanitation sector. Degree of Occup Name age gender education ation Work unit contact

(mailing address) number First, multiple-choice questions (Please tick in □) 1、Do you know the project: □ know □ do not understand 2.Do you think the environmental protection measures are feasible: □ feasible □ not feasible 3.Do you think the environmental impact of the project implementation process: □ Air □ Surface water □ Acoustic environment □ Groundwater □ Ecology 4.Whether the impact on the environment after adopting the corresponding environmental protection measures is acceptable: □ Yes □ No 5.Is this project conducive to promoting local economic development: □ Very advantageous □ More advantageous □ Negative □ Very unfavorable 6.Do you support the construction of this project: □ Support □ Objection (explain why) Second, comments and suggestions

Signature of form filling person (mm/dd/yyyy) ●Statistical analysis of the survey results Shenyang Lvheng Environment Consulting Co. Ltd 159 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

This public participation survey collected public opinions by means of a questionnaire survey on issues of public interest that might be affected around the construction project. The construction unit issued 60 questionnaires for the sensitive spots near the project and collected 60 copies with a recovery rate of 100%. The public opinion statistics results are shown in Table 6.3-6, 6.3-7. Table 63Table 6.3-3 Statistics Regarding the Participants in Public participation Survey Item Contents Votes received Percentage (%) Male 31 51.7 Gender Female 29 48.3 Tertiary institutions and 33 55.0 above Educational level Junior and senior high school 26 43.3 Primary school 1 1.7 20-30 years old 16 26.7 30-40 years old 23 38.3 Age 40-50 years old 10 16.7 Over 50 years old 11 28.3 According to the structure of the surveyed population in Table 6.3-6, the survey basically included residents of all ages and education levels near the project. Among them, people at 20 to 40 years of age with junior college education accounted for the majority of the population. Therefore, the results are comprehensive and rational.

Shenyang Lvheng Environment Consulting Co. Ltd 160 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 64Table 6.3-7 Opinion Statistics Regarding the Public Participation Survey Percentage in valid Survey contents Survey results questionnaires % Do you know about the Yes 60 100.0 project? No 0 0.0 Do you think environmental Yes 60 100.0 protection measures are No 0 0 feasible Air 44 73.3 Do you think the project Surface water 1 1.7 implementation process on Acoustic environment 11 18.4 the environment Groundwater 2 3.3 Ecology 2 3.3 After adopting the Yes 60 100 corresponding environmental protection No 0 0.0 measures, the environmental impact is acceptable Very conducive 55 91.7 Whether this project is Conducive 5 8.3 conducive to promoting Unfavorable 0 0.0 local economic development Very unfavorable 0 0.0 Support 60 100.0 Do you support the Object construction of this project? 0 0.0 Object 0 0.0

The public expressed their own opinions about the contents of the questionnaire. According to the surveyed public's age, sex, occupation and other statistics, we can observe from the comprehensive survey results in Table 6.3-7 that: (1) All the participants knew about the project. (2) All the participants considered that the project's environmental protection measures were feasible (3) 73.3 % of the public thought that this project might affect the air environment; 1.7% of the public thought that this project might have an impact on the surface water environment; 18.4% of the public thought that this project might have an impact on the sound environment;; 3.3% of the public thought that this project might have an impact on groundwater;3.3% of the public thought that this project might have an impact on the ecological environment. This showed that the public had a clear understanding of the pollution of this project. (4) All the participants considered that the environmental impact of this project after Shenyang Lvheng Environment Consulting Co. Ltd 161 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site adopting corresponding environmental protection measures is acceptable (5) 91.7% of the public thought that this project could promote the local economic development, while 8.3% of the public thought that this project could promote the local economy favorably.

(6) All the participants support the implementation of this project. Feedback Analysis and Suggestions of Survey Results Survey public support for the construction of the project, some investigators made the following recommendations for this project: ⅰ strengthen construction management, strengthen environmental supervision; ⅱ construction process should be strictly in accordance with the proposed environmental protection measures to implement; ⅲ The construction process to minimize construction dust and noise; ⅳ recommended to stop construction at night. ④ forum Meeting time: March 1, 2018 Venue: Shenyang Innovation H Block Participants: Vanke Lang Run Park, Heavy Industries Village, Blue Ting Habitat, Shenyang City, No. 36 Middle School, King Fantasia, a better vision of villagers representatives, a total of 40 people. At 9:00 on March 1, 2018, the Public Participation Conference on the Environmental Impact Assessment of POPs Contaminated Sites in Northeast Pharmaceutical Factory officially started in the Conference Room H of Innovation Plaza in Shenyang. At the meeting, representatives from Northeastern Pharmaceutical Group Co., Ltd. staff introduced the preparation of the project and detailed descriptions of the rehabilitation programs and environmental protection measures. The participants discussed and discussed the problems in the program and made the following suggestions: During the construction, the project shall strictly implement the restoration plan and environmental protection measures. It is suggested that the environmental protection department should send a special person to supervise the construction and repair process throughout the

Shenyang Lvheng Environment Consulting Co. Ltd 162 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site whole process. For construction not in accordance with the requirements of the project and the environmental protection requirements, timely rectification shall be conducted to reduce the environmental impact on the surrounding residents.

Figure 43Figure 6.3-5 Forum site ⑤ Online Publicity

On March 9th, 2018, the “Environmental Impact Assessment and Environmental Impact Assessment of

POPs Contaminated Site Project of Northeast Pharmaceutical Factory” was carried out on Shenyang Lvheng

Environmental Consulting Co., Ltd. website. The publicized contents include: project overview, main environmental issues arising, The environmental protection measures taken at the same time, etc. At the same time, the entire environmental impact assessment and social environmental impact assessment report for the

POPs contaminated site project of the Northeast Pharmaceutical Factory was publicized. See Figure 6.3-6 for details.

Shenyang Lvheng Environment Consulting Co. Ltd 163 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 44Figure 6.3-6 Report on Environmental Impact Assessment and Social Environmental Impact Assessment of POPs Contaminated Site Project in Northeast Pharmaceutical Factory 6.4 Grievance mechanism During the preparation and implementation of environmental impact assessment, the World

Shenyang Lvheng Environment Consulting Co. Ltd 164 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Bank will always attach importance to the public participation mechanism and establish a complaint mechanism. The public complaint procedure is as follows: Stage 1: If the affected people are dissatisfied with the indirect impact caused by the construction process, they may submit a written complaint to Shenyang Environmental Protection Bureau and the EPB should make a decision within two weeks; Stage 2: If the APs are still not satisfied with the decision of Phase 1, they may lodge a complaint with the Liaoning Province Environmental Protection Department after receiving the decision and make a decision within two weeks. Stage 3: If the APs are still not satisfied with the decision of Stage 2, they may appeal to the court after receiving the decision.

Shenyang Lvheng Environment Consulting Co. Ltd 165 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

7. Environmental Investment and Environmental Benefits Analysis 7.1 Overview Environmental impact economic benefit and loss analysis is mainly to evaluate the cost of environmental loss after the implementation of the construction project and the social, economic and environmental benefits brought by various environmental protection measures. The cost of environmental loss mainly includes the loss value of the impact on the surrounding ecological environment and human health due to pollutant discharge and pollution accidents, the lost value of resources and energy, and the operation, maintenance and management expenses put into operation for maintaining various environmental protection facilities. Environmental economic benefits mainly include the value of recovery and comprehensive utilization of resources and energy after the implementation of various environmental protection measures, and the social and environmental benefits brought by mitigation of environmental pollution. Environmental economic losses and benefits are generally indirect, difficult to calculate in the form of currency, and also difficult to calculate accurately and with greater uncertainty. Due to the absence of uniform standards, mature methods or related norms for environmental and economic benefit and loss analysis, the task was somewhat difficult. The evaluation in this study merely described and analyzed some aspects of the above content to a limited extent.

7.2 Environmental protection investment estimates This project was a remediation project of contaminated soil. In order to solve the secondary pollution in the process of soil remediation, it was estimated that the investment in environmental protection would be 2.03 million RMB, accounting for 2.31% of the total investment of 88.041 million RMB. See Table 7.2-1 for environmental investment in construction projects.

Shenyang Lvheng Environment Consulting Co. Ltd 166 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 65Table7.2-1 Environmental Protection Investment Estimates Investment Serial (RMB 10 Type Environmental protection measures Treatment results No. thousand yuan) Set a closed enclosure around the site to be closed, soil temporary storage area to be covered, set a shed with membrane structure at the soil remediation area or to perform enclosed Reduce fumes and 20 treatment with an integrated machine, mobile emissions of spray dust collector for collecting dust organic gases Exhaust 1 Dustproof transport vehicles: dust cloth, gas closed tanker, waterproof, anti-disperse 10 measures

Thermal desorption exhaust purifier set, gas Exhaust achieves collector + cyclone plastic film, organic emissions 50 exhaust volatile inhibitor standards Sedimentation tank 5 Sedimentation tank, car wash yard, soil Protect temporary storage area, seepage prevention in groundwater Waste environment 10 2 soil remediation area, anti-seepage measures of water wastewater pipelines Wastewater Alkaline wash wastewater neutralization achieves discharge 3 standards Equipment muffler, noise, vibration reduction, Reduce noise 3 Noise 18 set the noise cover and so on pollution Solid Reduce dust 4 waste Hazardous waste disposal 27 Environ Reduce ment Monitoring emissions, field noise, groundwater environmental 5 monitori 30 and soil pollution ng Environ Reduce mental Ensure the implementation of environmental environmental 6 supervis 30 protection measures pollution ion Total 203 7.3 Analysis of Social and Economic Benefits With the social progress, people's environmental awareness and self-protection awareness continue to increase. Around the contaminated site, dense commercial and residential areas had been built. Although the original Shenyang monosodium glutamate plant was relocated, the soil at the original site had been contaminated. The site covers an area of 114,000 m2. If the site remains unused, pollutants will continue to spread. This will not only affect the health of nearby residents, but also affect the development and Shenyang Lvheng Environment Consulting Co. Ltd 167 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site utilization of the land in the later period, thus wasting precious urban land resources, and was extremely inharmonious with the surrounding living environment, seriously affecting the integrated image of Tiexi District. According to the latest plan of Tiexi District, soil remediation of this plot will play an active role in promoting the development and utilization of land and the overall image of the region, thus promoting the development of the city. Contaminated site soil remediation will reduce the pollutants in the soil harming the surrounding residents, and reduce the chance that the surrounding residents are affected by contaminants in the soil and the need for treatment of diseases, thereby reducing health care costs.

7.4 Environmental Benefit Analysis If the contaminated site of heavy metals and organic compounds formed after the relocation of the north plant area of the original Northeast Pharmacy plant is left for a long time without treatment and remediation, the pollutants in the soil will enter the atmosphere and harm the surrounding residents; on the other hand, rainwater infiltrates into the soil, pollutants continue to enter the lower soil and groundwater, pollutants continue to migrate and spread, not only the soil pollution continues to increase, but also pollute the groundwater, environmental risks continue to increase. If not timely rectified, over time, it will bind to increase the continuous accumulation of environmental pollution in the region. The implementation of soil remediation project can control the migration and diffusion of pollutants and reduce the further pollution of the atmosphere, soil and groundwater. In conclusion, the soil remediation project on the plot will improve the living environment for residents in the area, improve the environmental quality of the surrounding atmosphere, soil and groundwater, optimize the investment environment and promote the sustainable development of society and economy. The environmental benefits and social benefits brought by the remediation of polluted soil are very significant and have a positive effect on improving the local environmental quality.

Shenyang Lvheng Environment Consulting Co. Ltd 168 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

8. Environmental Management and Monitoring Plan 8.1 Environmental Management 8.1.1 Necessity of Environmental Management Based on scientific theories, environmental management uses the means of economy, law, technology and administration to regulate and control the pollution and damage to the environment during the economic and social development so as to achieve the harmonious integration of economic, social and environmental benefits. Establishing a scientific and reasonable environmental management agency is the basic guarantee for a construction project to successfully accomplish its environmental goals. It is also the key point for the project to complete its environmental protection work and achieve sustainable development. Soil remediation project itself is an environmental project. Its completion and production are not aimed at directly generating economic benefits, but rather contributing to environmental protection and reflecting its benefits from the improvement of the environment. Therefore, it is very important to strengthen the environmental management of soil remediation project. 8.1.2 Environmental Management Agency Setting According to the provisions of the World Bank and China on the management of contaminated site remediation and the actual engineering needs, the POPs contaminated site project of the Northeast Pharmaceutical Factory has established an environmental management system in which management agencies, supervisory agencies, consulting and service agencies, and implementing agencies collaborate with each other. 8.1-1.

Shenyang Lvheng Environment Consulting Co. Ltd 169 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 45Figure 8.1-1 Organizational Framework of Project Environmental Management Organization 1. World Bank responsibilities (1) According to the requirements of the loan agreement between the Chinese government and the World Bank, review the environmental impact assessment and social impact assessment, and carry out special inspection on the implementation of the site governance project; (2) Examine the implementation of the project loan agreement and the implementation of the environmental management plan; 2. Environmental Protection Foreign Cooperation Center of the Ministry of Environmental Protection Responsible for overall coordination and management of pollution site management projects in China, including: (1) To guide and supervise the project to carry out various tasks; (2) Responsible for arranging World Bank environmental experts' inspection activities; (3) According to the requirements of the World Bank, collect reports on different stages of site restoration and submit them to the World Bank for review; (4) Engage environmental consultants to provide technical support for site remediation; 3. Project Office of Environmental Protection Department of Liaoning Province Specifically responsible for the implementation and management of project projects,

Shenyang Lvheng Environment Consulting Co. Ltd 170 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site including: (1) Designate someone to take charge of environmental management; (2) Prepare periodic reports on the environmental management of restoration projects and report regularly to the external cooperation center and the World Bank; (3) Responsible for coordination with other relevant departments to solve major environmental problems; (4) Confirming the contractor of the repaired subproject through public bidding, and signing the relevant construction contract with the repairing contractor; (5) Appointing an environmental supervision agency to supervise the implementation of the contractor's restoration project through public bidding; (6) After the contractor repairs the project, it will engage a third party to accept the acceptance through public bidding; (7) Engage environmental experts and social experts to solve technical and social issues in the project implementation process; 4, Shenyang City Environmental Protection Agency As the local environmental administrative department, it conducts environmental supervision and management of the entire process of the POPs contaminated site project of the Northeast Pharmaceutical Factory according to law, which mainly includes: (1) Approval of project evaluation report; (2) Environmental supervision and management during the implementation and acceptance of the project restoration project; 5, the owner The owner of the Northeastern Pharmaceutical Factory POPs contaminated site is Northeast Pharmaceutical Group Co., Ltd., with clear property rights and no lease contract. It is mainly responsible for rehabilitating environmental supervision and environmental monitoring in the implementation of project, acceptance and other phases. 6, contractor The contractor is the implementing agency for the restoration project. Its main responsibilities include:

Shenyang Lvheng Environment Consulting Co. Ltd 171 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(1) According to the implementation plan of the project restoration, after passing the examination and approval of the Shenyang Environmental Protection Bureau, the implementation details and project implementation plan shall be formulated in accordance with the requirements in the environmental management plan; (2) Responsible for implementing the environmental and social mitigation measures in the environmental management plan; (3) Accept the supervision and management of the project office of the Environmental Protection Department of Liaoning Province, the Environmental Protection Bureau of Shenyang City, and the environmental supervision unit, and timely correct the unqualified part of the restoration project. For site restoration activities, the contractor needs to meet the following requirements: ● Strict implementation of national, local laws and regulations, and technical guidelines for the management and disposal of hazardous wastes. The contractor is required to have hazardous waste disposal qualifications to meet the needs of POPs and heavy metal-contaminated soils in water catchment sites. ●Professional and accredited technology and management personnel, and comprehensive safety and security measures, including construction technical instruction manual, construction safety and quality responsibility guarantee, occupational safety training assessment, safety and security equipment management regulations, environment-quality-safety internal inspection system, Safety accident emergency system. ● Other qualification requirements are detailed in the project bidding documents. 7, supervision unit Third-party supervision includes engineering supervision and environmental supervision. The details are as follows: (1) Engineering Supervision According to the requirements of GB/T 50319-2013, the project supervision supervises and manages on-site project quality, project cost, project progress, construction scope, and production safety management in accordance with the requirements of the “Construction Project Supervision Regulations” (GB/T 50319-2013).

Shenyang Lvheng Environment Consulting Co. Ltd 172 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

● Whether the contaminated soil excavation construction, chemical oxidation, and thermal desorption/remediation site construction are to be carried out in accordance with the organizational plan for remediation of contaminated sites; ● Contaminated soil transport, supervision of whether the vehicles in the process of contaminated soil transport are closed, whether they are in accordance with the established transport routes and time, whether they are transported to designated storage and processing sites, and whether the amount of earth and stone transported is consistent with the triple transport unit; (2) Environmental Supervision In accordance with government supervision requirements, supervise the contractor in the remediation process whether it is required to implement the protection or mitigation measures of secondary pollution in the environment, check whether the remediation project meets the effective control or corresponding standards of secondary pollution of the environment, and provide services that may cause major environmental or ecological pollution. Construction site image data. The main contents of environmental supervision are detailed in the environmental management plan. (3) Qualification requirements of the supervision unit Qualification of project supervision: requirements shall be fulfilled in accordance with the “Administrative Regulations on Qualification of Engineering Supervision Enterprises” (Decree No. 158 of the Ministry of Construction); Environmental supervision qualification: As China has not yet established and improved the environmental supervision system, and the qualification requirements of environmental supervision units are missing, we can request from the following aspects: ①Implement qualification management for the entities engaged in the environmental supervision of construction projects, and after the environmental protection administrative department at the provincial level has examined and confirmed, they can engage in environmental supervision of construction projects; ②Having a qualification certificate of Class B or above for environmental impact assessment of a construction project;

Shenyang Lvheng Environment Consulting Co. Ltd 173 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

③ Having 3 or more Class B qualification project supervisors and more than 10 professional and technical personnel in engineering analysis, environmental engineering, ecological protection, civil engineering, etc.; ④ equipped with special instruments and equipment that meet the requirements of environmental supervision; ⑤ establish a sound environmental supervision work procedures, internal management system and file management system; ⑥ Evidence of related performance of environmental supervision, and other qualification requirements are detailed in the project bidding documents. 8, repair and acceptance units After the contractor completes the site remediation project, the site remediation effect is checked and accepted to confirm that the restored soil has reached the target value for restoration and an acceptance report is prepared. Qualification requirements for repair and acceptance units: As there are no qualification requirements for contaminated site remediation and acceptance units in China, we can consider the following aspects: ⑴Having been examined and confirmed by the provincial environmental protection administrative department, it can be engaged in environmental consulting, environmental assessment of contaminated sites, and other environmental consulting work; ⑵Having a qualification certificate of Class B or above for environmental impact assessment of a construction project; ⑶ More than 10 professional technicians in engineering analysis, environmental engineering, ecological protection, civil engineering, etc.; ⑷ equipped with special instruments and equipment that meet the requirements of environmental supervision; ⑸establish a sound environment consulting work procedures, internal management system and file management system; ⑹Environmental performance inspection, supervision related job performance certification, and other qualification requirements are detailed in the project bidding documents.

Shenyang Lvheng Environment Consulting Co. Ltd 174 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

8.2 Environmental Supervision In the process of project implementation, sampling at multiple sites, for multiple times and in batches are needed to test the contents of heavy metals in soils and water bodies in the project, so as to objectively evaluate the effectiveness of project implementation and control environmental risks. The project environmental supervision should provide the whole process of monitoring, supervision and inspection on the implementation of the project according to the approved project environmental impact report, prevent the environmental risks in the construction process, evaluate the project implementation effectiveness in time, and provide the basis for environmental acceptance of the project. 8.2.1 Environmental Supervision In order to ensure the smooth implementation of site soil remediation project, the site responsibility principal should entrust qualified, experienced and competent personnel to carry out the site remediation project. Supervision of the construction processes including boundary determination, excavation, transportation, treatment and acceptance of the contaminated soil should be entrusted to qualified and experienced supervision units, , together with environmental protection and related departments. Among them, the project supervision and implementation of the relevant provisions of the state; environmental supervision work procedure, work contents, work key points, working methods, work systems, supervision requirements were as follows: 1. Working Procedure Contaminated site remediation project environmental supervision work procedures were shown in Figure8.2-1.

Shenyang Lvheng Environment Consulting Co. Ltd 175 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 46Figure 8.2-1 Environmental Supervision Procedure of the Pollution Site Management Project 2. Work Contents The work contents mainly include three aspects: Environmental supervision during construction preparation stage, environmental supervision during project implementation phase and environmental supervision during project acceptance phase. ⑴ Environmental Supervision Suring Construction Preparation After entrusted by the construction unit, the environmental supervision unit should timely conduct data collection and on-site reconnaissance work, sign an environmental supervision contract with the construction unit, set up an environmental supervision agency according to the contract requirements and the scale and characteristics of the remediation project of the contaminated site, participate in the induction for the design of the remediation project, prepare

Shenyang Lvheng Environment Consulting Co. Ltd 176 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site the environmental supervision plan for remediation of contaminated sites and review the design plans of the construction organization according to the design documents such as the project remediation plan and relevant norms and standards, review the conformity of the main remediation works and the secondary pollution control measures and remediation plans, and review the pollution accident emergency plan. ⑵ Environmental Supervision During Project Implementation The first site meeting of environmental supervision should be held promptly, and detailed implementation rules for environmental supervision of the remediation project at contaminated sites should be prepared. Environmental supervision should be conducted in accordance with the detailed implementation rules of environmental supervision, with emphasis on the implementation and change of construction contents and the implementation of secondary pollution control measures and pollution accident emergency measures. At the same time, technical advice for the construction unit should be provided, putting forward rectification opinions on the existing problems and informing the construction unit of them. Relevant units should coordinate with the acceptance and monitoring units to implement project acceptance, monitoring, and other procedure. ⑶ Environmental Supervision During Project Acceptance After the completion of the remediation project, a summary report on the environmental supervision of the remediation of contaminated sites will be compiled on the basis of the above work, on-site inspection meeting for project acceptance will be held, and inspection and acceptance of the remediation works will be carried out. 3. Key Points of Work According to the characteristics of the pollutants at this site and the process and characteristics of the remediation project, the key points of the work of thein-suit Remediation project and the environmental supervision of the ex-suit remediation project are listed in Table 12.2-1 and 12.2-2 respectively. ⑴ in-suit Remediation Project The key points of environmental supervision work of thein-suit Remediation project are shown in Table 8.2-1.

Shenyang Lvheng Environment Consulting Co. Ltd 177 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 66Table 8.2-1in-suit Remediation Project Environmental Supervision Key Points Supervision contents Supervision key points Excavation border and depth, contaminated soil internal transport Site digging routes and temporary stacking settings The registration of contaminated soil; the temporary storage and remediation facilities construction, operation and unearth, etc.; the Construction Contaminated soil process, method and construction sequence of the remediation; the contents temporary storage and construction and operation of the site for the soil to be inspected remediation after the remediation; the monitoring and remediation process and the remediation effect and so on Reuse of soil after remediation Outbound and backfill program, outbound earthwork, outbound Seepage, dustproof, odor diffusion prevention measures, prevention Site digging of soil secondary pollution control measures for temporary storage of contaminated soil, roads etc. Remediation process Contaminated soil Transport vehicles cover, anti-sparse measures secondary outbound transport pollution Contaminated soil Rain, dust, seepage, odor diffusion prevention measures for prevention temporary storage and temporary storage; airtight remediation facilities and control remediation Examination and Seepage, dust-proof and odor-proof prevention measures to be taken reuse of soil after by the site; dust prevention and anti-sparse measures for soil remediation outbound transport, backfill / reuse Atmospheric unorganized Soilin-suit Remediation boundaries emissions Soil remediation of the construction site and ex-suit sensitive points Air quality of the ambient air Pollutant Groundwater quality Groundwater on-site discharge and environmental Field noise Contaminated site field noise impact Ex-suit sensitive point Noise around sensitive points in the construction site monitoring Noise reduction Construction period control, noise reduction equipment operation measures and effect, noise reduction measures Contaminated soil temporary storage site, remediation field, site for Contaminated soil the soil to be inspected after remediation and so on On-site construction waste and underground unidentified waste Solid wastes identification ⑴ Ex-suit Remediation Project The key points of environmental supervision work of the ex-suit remediation project are shown in Table 8.2-2.

Shenyang Lvheng Environment Consulting Co. Ltd 178 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 67Table 8.2-2 Key Points of Offsite Remediation Project Environmental Supervision Supervision contents Supervision key points Rain, dust, seepage and odor diffusion prevention measures of Contaminated soil temporary storage field; closed airtight remediation facilities, temporary exhaust gas treatment device operation and its dust removal, exhaust Remediation storage and treatment effect and emissions, the remediation process, methods, construction remediation construction order and so on, remediation effect monitoring process and secondary and remediation effect. pollution Rain, dust, seepage and odor diffusion prevention measures of the prevention and Test and site with soil to be inspected, the remediation of the soil to meet the control backfill/reuse of remediation objectives, the offloading transportation and backfill remediated soil program, the amount and location of earthmoving, earthbound, soil offloading, backfill / reuse process. Unorganized Contaminated soil temporary storage and disposal of field emission boundaries. Exhaust emission VOCS, particulate matters, dioxins and HCl, etc. Pollutant Air quality Soil remediation of the construction site and ex-suit sensitive points discharge and of the ambient air. environmental Wastewater discharge It is controlled by the northeast pharmaceutical factory impact Field noise Field boundary noise in soil ex-suit remediation sites. monitoring Noise reduction Construction period control, noise reduction equipment operation measures and effect, noise reduction measures. Contaminated soil temporary storage site, remediation field, to be Contaminated soil inspected after the soil and so on. ⑷ Working Methods The environmental supervision of the site remediation project should adopt the following working methods: 1) Verification: In accordance with relevant management documents and technical documents, the implementation of remediation works and secondary pollution measures should be verified and checked at all stages of the remediation project. 2) Inspection: Regular or irregular inspection activities should be carried out on the construction site of the remediation project. 3) Side station: Supervision activities on the key parts of the remediation works or the construction quality of the key processes should be carried out. 4) Meetings: Regular or irregular meetings of environmental supervision meetings, including regular meeting of environmental supervision, special meetings and on-site coordination meetings, should be summoned. The meeting should be presided over by the director of environmental supervision or hosted by the environmental supervision engineer authorized by him and participated by delegates from relevant units of the remediation project. 5) Testing: In order to grasp the secondary pollution caused by daily construction, the environmental supervision unit should conduct on-site environmental testing through portable environmental monitoring instruments to assist the environmental supervision work. It is

Shenyang Lvheng Environment Consulting Co. Ltd 179 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site suggested that the construction unit should commission qualified units to complete the more complex environmental tests. 6) Training: Train should be provided to the project implementation unit and its management and construction personnel to enhance their expertise and skills for the remediation of the contaminated site. 7) Records: Environmental supervision log, environmental supervision inspection records, and records of the environmental monitoring side stations should be taken. 8) Documents: The management of the implementation of the main project and the implementation of the secondary pollution control measures should be carried out in the form of documents such as the contact list of environmental supervision, the notice of environmental supervision rectification, the notice of environmental supervision stoppage, and the order of rework or resumption due to environmental problems. 9) Follow-up inspection: the implementation of the documents issued by the environmental supervisor and the strict implementation process of the construction unit should be inspected under scrutiny. 10) Report: Report including regular report of environmental supervision, special report, stage report, and environmental supervision summary report should be compiled and submitted to the construction unit. ⑸ Working System Project environmental supervision should adopt the following working system: 1) Work record system: Environmental supervision record is an important channel for information gathering of the remediation project, and is important basic information for the project environmental supervision agency to make decisions. Its contents mainly include environmental supervision log, on-site inspections and site station records, meeting records and monitoring records. Records include texts, data, charts and videos. 2) Document examination and approval system: It is the requirement of the environmental supervision unit to examine the engineering measures and the organizational design of engineering facilities that are related to the remediation of contaminated sites prepared by the construction unit. The construction organization design and construction measures plan prepared

Shenyang Lvheng Environment Consulting Co. Ltd 180 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site by the construction unit should be reviewed by the environmental supervision unit. 3) Reporting system: The environmental supervision unit should implement the environmental supervision reporting system in combination with the conference system and work record system. Environmental supervision reports include regular reports, special reports and stage reports. 4) Correspondence system: Problems found in the construction site inspection process by environmental supervision engineers should be issued by environmental supervision notice and in other forms to notify the construction unit to take corrective measures or actions. The provisions or requirements of the environmental supervision engineer on certain aspects of the construction side must be notified in written form. An urgent case to be verbally notified must be confirmed by written communication. The construction unit and the construction side should reply the handling result of the construction site problems and other aspects, and they should write to the environmental supervision agency. 5) Conference system: Including the first meeting of environmental supervision sites, regular meetings, special meetings, on-site coordination and so on. The director of environmental supervision or the environmental supervision engineer may hold different levels of construction site coordination meetings from time to time according to the conditions of the remediation project. The meetings coordinate and implement the construction activities and promptly correct the problems discovered. 6) Personnel training system: Carry out on-site environmental supervision training and systematically carry out the training related to the remediation of contaminated sites for construction unit managers and construction unit site staffs. 7) Quality assurance system: In order to ensure and control the quality of the work of environmental supervision, the environmental supervision department should strictly follow the relevant provisions of the state and local governments. Environmental supervision practitioners should be required to certify posts. Environmental supervision should be strictly in accordance with the supervision program and implementation details, and record in detail of the various situations that occurred during the project. Environmental supervision related reports should be implemented within the multi-level audit system.

Shenyang Lvheng Environment Consulting Co. Ltd 181 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

⑹ Ability Requirements In order to effectively carry out the environmental supervision work of the site remediation project, the environmental supervision unit and its related staff should meet the following ability requirements: 1) Supervision unit: As an independent legal entity, it should be familiar with the prevention and treatment of contaminated soil on the site, have experience in soil pollution prevention and control, and undertake related investigations, evaluation and remediation of contaminated soils similar to this project. 2) Person in charge of supervision: Senior professional and technical title in the field of soil environmental protection, having over 3 years of work or research experience in the field of remediation of contaminated soil, etc., and presided over the investigation, assessment and remediation projects of more than 3 sites in China related to contaminated site. 3) Supervision team: Professional equipment should be complete. In addition to the responsible person, the supervising team needs at least three technicians who are specialized in soil remediation and soil analysis. 8.2.2 Environmental Monitoring of the Transport Process Monitor whether the transport vehicles are transferred to the processing area according to the designated route and time period, transport schedule and amount transported. Check whether the soil of each type of pollution was transported by the transport vehicles with the corresponding marks. Monitor whether the closed operation is carried out according to the operation during the transportation of polluted soil, and check whether there is any missing during transport should be checked. 8.2.3 Environmental Monitoring

1.in-suit Remediation The contents of the environment monitoring of thein-suit Remediation site are shown in Table 8.2-3.

Shenyang Lvheng Environment Consulting Co. Ltd 182 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 68Table 8.2-3 in-suit Remediation site environmental monitoring content list Monitore Sampling and monitoring Monitoring frequency Monitored indicators d medium specifications Arsenic, Copper, Lead, Zinc, Mercury, Benzo(a)anthracene, In the venue and the surrounding area, 4 Chrysene, Benzo Environmental sampling and monitoring sites will be set, (b)fluoranthene, Benzo Soil Monitoring Technical with a monitoring frequency of 3 (k)fluoranthene, Indeno Specifications times/week 1,2,3-cd) pyrene, dibenzo (a, h) anthracene, hexachlorocyclohexane Before construction, there will be 3 points in the upwind and downwind direction of the venue, which will be tested once each; during the construction, there will be 6 Ambient Air Quality points in the upwind and downwind Diffusion and residue of Air Standards direction of the site, which will be inhalable particles (GB3095-2012) monitored once a month; after construction, there will be 3 points in the upwind and downwind direction of the venue, which will be tested once each. A total of 4 spots around the site area, Environmental Noise Daytime/nighttime each sampling point located at a height of Noise Emission Standards for noise equivalent sound 1.2m above the noise-sensitive office, Construction Sites level with once a week monitoring Arsenic, Environmental hexachlorocyclohexane, Before the construction, the existing Monitoring Technical benzene, Groundw monitoring wells in the site will be Specifications and chlorobenzene, ater sampled and tested once each; three Groundwater Monitoring dichlorobenzene, monthly monitoring during construction. Technical Specifications trichlorobenzene and so on 2. Ex-suit Remediation The contents of ex-suit remediation environmental monitoring were shown in Table 8.2-4.

Shenyang Lvheng Environment Consulting Co. Ltd 183 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Table 69Table 8.2-4 Ex-suit Remediation Site Environmental Monitoring Content List Monitore Sampling and monitoring Monitoring frequency Monitored indicators d medium specifications n the factory area, the upper and Environmental air quality lower wind directions shall be set Air standards (gb3095-2012) Class Particulate matter at one point each, and each time 2 standard shall be tested once a month Around the Northeast Pharmacy new plant area, a total of 4 points Environmental Quality Standard will be set, with each sampling Daytime/nighttime Noise for Noise (GB3096-2008) Class point located at a height of 1.2m noise equivalent sound 3 standard above the noise-sensitive site, level monitoring will be conducted once a month 8.2.4 Treatment Process Environmental Supervision (1) Remediation area soil monitoring During the implementation of the project, XRF will be used to carry out on-site monitoring of the soil in the construction area, and the boundary of the remediation area will be initially determined. The laboratory samples of the remediation area will be tested and analyzed according to the site conditions to further clarify the boundary of the remediation. The monitoring indexes are total nickel, total mercury, polycyclic aromatic hydrocarbons (benzo(a)anthracene, benzo(b)fluoranthene, benzo(k)fluoranthene, benzo(a)pyrene) and hexachlorocyclohexane. (2) Treatment effect monitoring During the implementation of the project, batches of soil samples will be collected and monitored. Samples will be randomly taken on a daily basis to monitor the total amount of arsenic, chromium, nickel, lead, mercury and the leaching test after solidification treatment and feedback to the construction site at any time, in order to achieve project-wide environmental monitoring. After chemical oxidation of the organic contaminated soil, the soil will be tested for polycyclic aromatic hydrocarbons (benzo (a) anthracene, benzo (b) fluoranthene, benzo (k) fluoranthene, benzo (a) pyrene) and hexachlorocyclohexane. 8.2.5 Environmental Supervision at Later Stage (1) Long-term Monitoring of Site Environment After the completion of the project, a third party with technical strength will be entrusted to carry out long-term environmental monitoring of the soil within the scope of remediation. Within Shenyang Lvheng Environment Consulting Co. Ltd 184 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

3 years after acceptance of the project, 10 dynamic monitoring sites will be set in the area. After the project was accepted for 3 years, the dynamic monitoring sites will be reduced to 1 to 2, continue to monitor and evaluate the leaching of heavy metals after solidification. (2) Long-term Monitoring of Site Groundwater Long-term normalized monitoring of the groundwater around the treated site and the solidified landfill area will be carried out. The sampling points will be located in the groundwater flow upstream and downstream of the site. The monitoring wells will be operated according to the dry, flat and wet periods each year and will be monitored once every period. According to the risk assessment, target pollutants identified for the monitoring projects are arsenic, BHC, benzene, chlorobenzene, dichlorobenzene, trichlorobenzene and so on. 8.3 Monitoring Plan 8.3.1 Environmental Monitoring Purpose The purpose of the environmental monitoring plan is to supervise the implementation of various environmental protection measures through the monitoring plan and monitoring reporting system, and to timely adjust the environmental protection measures based on the monitoring results so as to control the adverse environmental impacts unforeseen in the plan. In principle, the major environmental factors in each period should be predicted and the monitoring plan should be developed according to the characteristics of the project. 8.3.2 Environmental Monitoring Tasks Environmental monitoring will be commissioned by the construction unit to the environmental monitoring authority. Environmental monitoring is the main guarantee for enterprises to improve their environmental management and promote the normal operation of pollution control facilities. Through regular environmental monitoring, we can understand the environmental quality in the neighboring areas, find problems and solve problems in a timely manner, which is conducive to monitoring the implementation of various environmental protection measures and adjust the environmental protection plan according to the monitoring results.

8.3.2.1in-suit Remediation Project 1. Atmospheric Monitoring Atmospheric environment monitoring is to monitor the air pollutants produced in the

Shenyang Lvheng Environment Consulting Co. Ltd 185 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site process of soil excavation. During the excavation and transportation of contaminated soil in the site, the size of monitoring area, the characteristics of the spatial distribution of pollutants and meteorological factors will be taken into consideration. Both inside and outside the site will be set with air sampling points. ① Determination of Monitoring Sites During the process of soil excavation, the air pollution belongs to unorganized discharge. According to the Technical Guidelines for Site Environmental Monitoring (HJ25.2-2014), the monitoring sites should be set at the boundary of the site, and the monitoring sites should be arranged in appropriate proximity to the environmental sensitive sites near the field area, and the eastern border near the environmentally sensitive point. Before the start of the remediation process, during the remediation process and after the end of the remediation project, employ a third-party testing organization to conduct on-site sampling and laboratory analysis. Determine the impact of unorganized exhaust generated during construction on the surrounding environment. ② Monitoring Frequency The contaminated soil treatment project will be sampled once before the start of construction as a background value; a sampling will be taken once a week during the period of soil remediation; and once the soil treatment project was completed, it will be monitored once again. Sampling of unorganized emissions requires a random sampling of one hour continuous sampling. ③ Monitoring Indicators and Emission Standards The pollutants in the site's atmospheric environment are mainly total suspended particulates (TSP). The atmospheric environmental quality standards are implemented according to the Integrated Emission Standard of Air Pollutants and Ambient Air Quality Standard, and the emissions during the construction process are unorganized emissions. Therefore, the emission standards will be implemented according to the unorganized emission monitoring concentration limits. 2. Noise Monitoring During the construction process, monitoring should be carried out in days without rain and

Shenyang Lvheng Environment Consulting Co. Ltd 186 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site with a wind level below 6, and in venues that are flat and without large reflectors. ① Determination of Monitoring Sites The noise monitoring methods accord with the Emission Standard of Environment Noise For Boundary of Construction Site (GB 12523-2011). On the soil remediation site boundaries, 4 sampling points will be set for noise monitoring. ② Sampling Methods and Frequency Integral sound level meter was used for sampling, with sampling intervals of no more than 1s. The daytime noise values at this point are characterized by an equivalent sound level A of 20 minutes during the day and nighttime noise values are characterized by an average equivalent sound level A of 20 minutes at night. Measurement time is divided into two parts during the day and night. Daytime measurement is selected at 8:00 to 12:00 or 14:00 to 18:00, at night, at 22:00 to 5:00. The contaminated soil in the site will be monitored once a week during the period of remediation and once after the remediation project is completed. ③ Noise Evaluation Criteria Noise standards are determined according to the environmental noise limits of the Emission Standard of Environment Noise For Boundary of Construction Site (GB12523-2011), and if the mechanical noise is higher than the standard, active measures should be taken to control the noise. The environmental monitoring contents were shown in Table 8.3-1. Table 70Table 8.3-1 Contents ofin-suit Remediation Project Environmental Monitoring Monitored Sampling and monitoring Monitored Type Monitoring frequency location specifications items Dust emission standards for 1 time before start-up, 1 time per month Air Field boundary construction and heap sites Dust (TSP) in soil remediation stage, and 1 time after (db21/3642-2016) soil remediation Environmental noise emission Area standards for construction 1 time/week in soil remediation stage, Noise surrounding Leq field boundaries and1 time after remediation field boundary (gb12523-2011) 8.3.2.2 Ex-suit Remediation Project 1. Atmospheric Monitoring At the new plant of Northeast Pharma, 1 point will be set for each of the downstream airways to monitor HCl, TVOC and dioxin generated during chemical oxidation and thermal desorption processes. For the soil remediation stage, sampling will be once a month and once

Shenyang Lvheng Environment Consulting Co. Ltd 187 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site after the soil remediation project was completed. 2. Noise Monitoring ① Determination of Monitoring Sites Noise monitoring methods were in accordance with Emission Standard for Industrial Enterprises Noise at Boundary (GB 12348-2008). On the soil remediation site boundaries, 4 sampling points will be set for noise monitoring. ② Sampling Methods and Frequency Integral sound level meter will be used for sampling, with sampling intervals of no more than 1s. The daytime noise values at this point are characterized by an equivalent sound level A of 20 minutes during the day and nighttime noise values are characterized by an average equivalent sound level A of 20 minutes at night. Measurement time is divided into two parts during the day and night. Daytime measurement is selected at 8:00 to 12:00 or 14:00 to 18:00, at night, at 22:00 to 5:00. The contaminated soil in the site will be monitored once a week during the period of remediation and once after the remediation project is completed. ③ Noise Evaluation Criteria Noise standards are in accordance with the environmental noise limits of Class III of the Emission Standard for Industrial Enterprises Noise at Boundary (GB 12348-2008), and if the mechanical noise is higher than the standard, active measures must be taken to control the noise. The environmental monitoring contents were shown in Table 8.3-2. Table 71Table 8.3-2 Contents of Offsite Remediation Project Environmental Monitoring Categ Monitoring Sampling and monitoring Monitored Monitoring frequency ory location specifications item Comprehensive emission Particulate standards for atmospheric matter pollutants (gb16297-1996) HCl Standards for the control of volatile organic compounds New plant area VOCs Air emission in tianjin industrial Ectopic repair once/half a year exhaust funnel enterprises (db12/524-2014) Draft for consultation on pollution control standards Dioxin for incineration of hazardous waste Environmental Quality Area Standard for Noise Noise surrounding the Leq 1 time/month in soil remediation stage, (GB12348-2008) Class 3 field boundary standard 8.4 Environmental protection inspection and acceptance

Shenyang Lvheng Environment Consulting Co. Ltd 188 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

The environmental protection measures adopted by this project should be implemented by the construction unit and the environmental supervision unit should be responsible for the supervision and inspection. Since the environmental protection facilities of this project will be all implemented during the construction period, the acceptance of the environmental facilities by the environmental protection authority mainly relies on environmental supervision technical advisory reports provided by the supervision units. The specific environmental inspection and acceptance table is shown in Table8.4-1. Table 72Table 8.4-1 Project Environmental Protection Facilities and "Three Simultaneous" Inspection Schedule Environmental protection Item Effects Progress facilities Remediation area closed Soil remediation in fully To be implemented during integration measures enclosed treatment the construction period Soil temporary storage area, To be implemented during Prevent dust bare soil area cover the construction period Exhaust To be implemented during Activated carbon Waste gas purification gas the remediation period Reduce emissions generated by To be implemented during Plastic film cover oxidation process the remediation period Cover with plastic film, spray Reduce emissions from To be implemented during with inhibitor regularly untreated soil piles the remediation period Protect surface water and To be implemented during Sedimentation tank groundwater environment the construction period Waste Sedimentation tank, car wash water yard, soil temporary storage Protect groundwater To be implemented during area, soil remediation area environment the construction period seepage control Equipment muffler, sound Equipmen insulation, vibration reduction To be implemented during Reduce noise pollution t noise and noise enclosure setting, the construction period etc. To be implemented Solid Soil temporary storage area, soil Reduce environmental during the construction wastes remediation area pollution period 8.5 Implementation of Environmental Management Plan 8.5.1 Assessment of Environmental Management Plan 1. Evaluation before project implementation After the project EIA report has been approved by the World Bank, a week before the implementation of the specific project, after the development of the site remediation environmental management plan organized by the Liaoning Provincial Environmental Protection Agency Project Office, it is necessary to conduct an assessment to assess whether the existing environmental management plan can meet relevant requirements. Environmental, occupational

Shenyang Lvheng Environment Consulting Co. Ltd 189 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site health and safety laws and regulations and standards can meet the requirements for site-contaminated soil green remediation. 2. Evaluation of the project implementation process The contractor, supervising party (environmental supervision and project supervision) and the owner side performed the implementation of each phase of the project implementation (contaminated soil excavation phase, implementation of the restoration project), evaluated the implementation of the environmental management plan, and put forward rectification measures. 3, assessment method The environmental management plan mainly adopts the internal assessment method. The Chongqing Project Office is responsible for convening the departments (contractors and supervisors) related to the implementation of the environmental management plan. Through reporting and discussing the implementation of the environmental management plan, the existing problems are assessed and evaluated. The effect of the implementation. In order to make the assessment process traceable, it is also necessary to form a complete assessment report or evaluation record. 4, assessment content The assessment of the environmental management plan includes, but is not limited to, the following aspects: the environmental staffing situation of the project owner and the construction contractor, the prevention and mitigation measures taken during the construction period and the operation period, and the environmental impact of the project construction. Environmental management plan training implementation status and effectiveness, environmental monitoring data during construction and operation period, environmental disturbance events and handling, and social supervision. 8.5.2 Information Management of Environmental Management Plan 8.5.2.1 Information exchange Environmental management requires the exchange of necessary information between different departments and positions within the site management. At the same time, the organization must also notify the outside (related parties, the public, etc.) of relevant information.

Shenyang Lvheng Environment Consulting Co. Ltd 190 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Internal information exchanges can be conducted in various ways such as meetings and internal briefings. Frequency of meetings is required but there must be one formal meeting per month. All exchange information should be recorded and filed. External information exchanges are conducted once every six months or one year, and information exchanges with collaborators are documented and archived. 8.5.2.2 Record Mechanism For the effective operation of the environmental management system, the organization must establish a complete record system and retain the following records: (1) Legal and regulatory requirements; (2) Permits for all aspects of project operations issued by government management structures; (3) Environmental factors and related environmental impacts; (4) Training of relevant units within the project management framework; (5) Inspection, verification and maintenance activities; (6) monitoring data; (7) Effectiveness of corrective and preventive measures; (8) Information of related parties such as owners, contractors, third-party supervision agencies, and acceptance agencies; (9) Audit records; (10) Evaluation of each stage of the project. 8.5.2.3 Reporting Mechanism The contractor, monitoring agency, and the project office of the Environmental Protection Department of Liaoning Province shall record the progress of the project, the implementation of the environmental management plan (EMP), and environmental quality monitoring results during the project implementation process and report to the relevant departments in a timely manner. It mainly includes the following three parts: (1) Monitoring units and contractors make detailed records of EMP implementation and report to the project office in a timely manner; (2) Project progress reports (such as monthly reports, quarterly reports, annual reports, etc.)

Shenyang Lvheng Environment Consulting Co. Ltd 191 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site prepared by the project office must include the contents of the EMP progress, such as the progress of EMP implementation and the effect of implementation; 8.5.3 Security System of Environmental Management Plan 8.5.3.1 Relevant Rules and Regulations In addition, the establishment of sound rules and regulations is an important guarantee for health and safety management. The relevant rules and regulations mainly include the following contents. (1) Regular routine work system: Including regular meetings, periodic training classes, regular inspections, etc. (2) Relevant Expense Management System: Explicit cost and source. (3) Major hazard source management system: The major hazard sources should be registered, set up, regularly tested, evaluated, monitored, and emergency plans should be formulated, and local safety production supervision and management departments and other relevant departments should be put on record. (4) Firefighting and traffic safety management system: Clear firefighting facilities, firefighting inspections, fire drills, and other matters, specifying vehicle safety regulations, and driver learning, training, and assessment. (5) Education and training system: Clearly specify the training object, content, time, assessment criteria, etc. The training content includes relevant knowledge training for management personnel at all levels; new employee induction training; original employee transfer training; targeting new materials, new techniques, and new Correctly regulate the use of equipment; training of special operators; emergency training. (6) Labor protection articles management system: The types of labor protection articles, scope of application, collection procedures, pre-use inspection, supervision during use, maintenance after use, and service life shall be specified. (7) Post safety specification: general safety requirements for other job positions except for special job positions. (8) Safety operation regulations: Safety operation procedures for various types of equipment related to personal health and safety.

Shenyang Lvheng Environment Consulting Co. Ltd 192 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(9) Occupational health inspection system: related requirements for regular health checkups. (10) Related mark management system: Clear project overview card, management personnel card, fire protection card, entry and exit system card, safety production card, civilized construction card, propaganda placard, safety warning card and construction general layout drawing. (11) Operating Environment Management System: Clearly supervises and manages the access, lighting and ventilation of the site. (12) Contract management system: The contractor shall carry out related qualifications review, specify the safety responsibilities of all parties, sign environmental, health and safety management agreements, specify the safeguard measures to be taken by both parties, and clarify the inspection and coordination methods of on-site work, etc. . (13) Reward and Punishment System: Principles for the implementation of rewards and penalties for environmental, health, and safety management, rewards, and punishments. (14) Emergency management system: Clear the emergency management department, emergency plan related matters, etc. (15) Accident investigation report processing system: The procedures for the internal investigation report of the accident and the procedures for reporting to the relevant competent authorities are clarified. 8.5.3.2 Fund Guarantee (1) Source of funds The source of funds for the project is divided into two parts. One is the World Bank grant and the second is local self-financing. Among them, the use of grant funding for procurement must comply with the relevant provisions of the World Bank. (2) Use of funds The implementation of the project, especially the secondary environmental pollution prevention and mitigation measures, requires funds to ensure protection, and its use of funds mainly covers the following contents: 1 Construction costs for excavation sites, contaminated soil transportation and temporary storage, contaminated soil phytoremediation and anaerobic bioremediation;

Shenyang Lvheng Environment Consulting Co. Ltd 193 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

2 Environmental monitoring cost budgets before, during and after restoration; 3 Secondary environmental pollution prevention and mitigation measures project implementation and management cost budget; 4 staff training cost budget; 5 related administrative expenses budget; 5. Repair process technology and pollution control technology; 6. Environmental/social impacts and mitigation measures in the environmental management plan; 7, environmental supervision methods and technical requirements; 8, environmental monitoring technology; 9. Repair acceptance methods and technical requirements; 10. Duties and relationships of the management unit, supervision unit, repair and acceptance unit, contractor, etc.; 11. Compilation of environmental management work report, environmental supervision work report, repair project contractor monthly report, etc. 12. Environmental risks and emergency measures in the repair process; 13. General safety knowledge and health and safety requirements of construction personnel. 8.5.3.3 Implementation Report of Environmental Management Plan During the implementation of the environmental management plan, the PMO must prepare and submit implementation and progress reports at important nodes. The report generally includes the following main contents: (1) From the contractor: to deal with the implementation of environmental management plans and measures, make detailed records in the report, and report to the owner in a timely manner; (2) From the environmental monitoring unit: entrusted to carry out monitoring according to the monitoring plan, and to provide a brief explanation of the obtained data, indicating whether the standard has been met, problems and non-compliance, analysis of the reasons, and recommendations for rectification measures; (3) From the supervision unit: According to the requirements of the project supervision

Shenyang Lvheng Environment Consulting Co. Ltd 194 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site regulations, submit the supervision phase report and the final report. The report must include the chapter on the implementation of the environmental management plan. 8.6 Public consultation plan in the implementation stage The public consultation plan for the project implementation phase mainly includes: (1) Questionnaire survey or random interview (1 time) during the implementation of the project to understand whether the environmental mitigation measures are in place during project implementation (soil clearance, transportation, temporary storage of contaminated soil, and contaminated soil restoration), and to understand the implementation of the project by surrounding residents. The opinions and suggestions in the answer to public questions; (2) Public announcement of project bidding and bid publicity and project acceptance (2 times), and disclosure of important information during project implementation; (3) Internal technical and management exchange meetings (unlimited times) to inform the progress of the project, solve project problems, and answer and respond to residents' queries and complaints; (4) Establish a sound complaint mechanism. 8.6.1 Random Interviews During the project implementation period, a questionnaire survey was conducted and random interviews were conducted. The main contents and main targets were as follows: ● project implementation process, temporarily passing the site of pedestrians, mainly interviews are: implementation of the project is causing a serious obstruction to the road, if there is a serious noise, whether there is a serious dust and odor, there is an obvious fence and warning signs; ● process soil transport pollution, for the way the road, a resident interviews is: whether transport vehicles cause serious noise, if there is soil and sewage spills, whether caused by blocked roads, whether passing in rush hour, if there are serious dust and Odor, whether the vehicle has protective and rain-proof measures; ● temporary storage sites contaminated soil personnel interviews, interviews with the main contents are: whether for the interim storage of pollutants contained in the soil and harm, temporary storage of contaminated soil protection measures are to meet the requirements, the

Shenyang Lvheng Environment Consulting Co. Ltd 195 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site amount of contaminated soil temporary storage and other earthworks. ● site demolition, dredging construction on the surrounding villagers affected Interview: check project environmental mitigation measures are executed in place (noise, waste water, dust, etc. is causing pollution to the surrounding environment, affecting the health of residents) to see if residents of the site During the repair process, questions, complaints, and feedback have caused property damage. 8.6.2 Project Publicity During the implementation of the project, the key information of the project needs to be publicized to accept the supervision and inquiries of the people, mainly including the following publicity: Publicity 1: Including information on project bidding and bidding, publicity of results of successful bids, need to be posted on the website of Shenyang Municipal Environmental Protection Bureau, and information is published in local newspapers. Information bulletin is posted on the bulletin boards around the project site (site repair project publicity content needs to include project content, main Measures, emergency response measures, contact person and method, etc.) Publicity 2: Mainly for the monitoring and acceptance results after the completion of the project, and the opinions of the relevant government departments, etc., information needs to be publicized on the website of the Shenyang Municipal Environmental Protection Bureau and published in local newspapers. Information bulletins are posted on the bulletin boards around the project site ( Including project content, major measures, emergency response measures, complaint contacts and methods, etc.) 8.6.3 Symposium The project symposium is mainly an internal technology and management exchange meeting. The main function is to enable the owner, project management department, government-related functional departments, project supervision units, project contractors, and technical consulting units to understand each other's progress and determine the complaints for surrounding residents. Solutions and feedback. 8.6.4 Grievance Mechanism

Shenyang Lvheng Environment Consulting Co. Ltd 196 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

In order to maintain the environmental quality status and the interests of the residents around the project site, the project establishes a convenient, open and effective complaints mechanism. The affected people can appeal any issue in the environmental management plan at any time. The first stage: If the residents in the surrounding area of the project site are in doubt about the specific contents of the environmental management plan, or because the construction process of the site restoration subproject affects the local environmental quality and social life order, they can submit oral or written information to the Liaoning Provincial Project Management Office. In the complaint, the Liaoning Provincial Project Office generally responds to or handles the feedback two weeks after it receives the complaint. The second stage: If the complainant is still not satisfied with the handling decision of the project office, he can appeal to the relevant provincial department after receiving the decision; Feedback mechanism The complaint feedback mechanism includes a planned record, tracking and regular reporting system. Standardized records: The complaint records mainly include: the basic information of the complainant, the basic situation of the complaint, the basic situation of the respondent, the solution, and the results achieved. Follow-up: Whether the complainant's complaint has been handled after the return visit, and whether the complainant is satisfied with the results. Periodic reports: The issues concerning complaints should be regularly reported to the upper management office and written in the next year's plan to avoid similar incidents.

Shenyang Lvheng Environment Consulting Co. Ltd 197 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

9. Evaluation Conclusion 9.1 Project Overview In September 2013, the Foreign Cooperation Center of the Ministry of Environmental Protection collaborated with the World Bank to develop the “China Polluted Site Management Project” to conduct environmental investigation and preliminary risk assessment of contaminated sites with potential persistent organic pollutants (POPs) in China. Typical POPs contaminated sites were chosen to explore the financing mechanisms for contaminated site management suited to China's national conditions, to conduct site risk management or governance demonstration projects, to promote the perfection of policies, regulations and standard systems for prevention and control of contaminated sites in China, and to improve China’s environmentally hazard-free management ability of contaminated sites in China. With the consent of the Liaoning Provincial People's Government, the Liaoning Provincial Department of Environmental Protection submitted an application to the Foreign Cooperation Center of the Ministry of Environmental Protection for participating in demonstration province activities and was endorsed by the World Bank and the Foreign Cooperation Center of the Ministry of Environmental Protection. Liaoning Province was selected as the project demonstration province, and the production areas in the north plant area on North Second Road of Northeast Pharmaceutical Group Co., Ltd., which had the history of producing DDTs, was included into the POPs pollution site management project. Northeast Pharmaceutical Group Co., Ltd., formerly known as Northeast Pharmaceutical Plant, with its north plant area on North Second Road located in No. 37 North Heavy Industries Road, Tiexi District, Shenyang City covering an area of about 120,000 m2, mainly engaged in drug production. The plant started production in 1949 and was discontinued in April 2015 and moved to Shenyang Economic and Technological Development Zone. In 2016, according to the municipal construction needs of the government of Tiexi District, an 11m wide and 6m wide municipal road was constructed to the north and west of the site area. At present, the plant covers an area of 114,000 m2. According to the government's overall land use plan, the site will be redeveloped for residential use (Type II Residence) in the future and has been taken by China Resources Land (Shenyang) Co., Ltd. on February 12, 2017 from auction. According to the relevant management requirements of national and local contaminated sites, before the industrial

Shenyang Lvheng Environment Consulting Co. Ltd 198 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site decommissioning land was redeveloped into commercial and residential land, in order to ensure the environmental safety of the land reuse, environmental investigation and risk assessment of the land need to be carried out, and the land should be managed and remediated if confirmed as contaminated land. According to the Detailed Report on Environmental Investigation and Risk Assessment of Northeast Pharmacy POPs Field (Production Area of North Plant Area on North Second Road, Northeast Pharmaceutical Group Co., Ltd.) and Northeast Pharmacy POPs Field (Production Area of North Plant Area on North Second Road, Northeast Pharmaceutical Group Co., Ltd.), it is proposed to usein-suit Remediation and ex-suit remediation to remediate the soil of Northeast Pharmacy POPs contaminated sites. The remediation work will be completed in two plant areas, of which thein-suit Remediation project will be in the former north plant area of Northeast Pharmacy (i.e. the contaminated sites), while ex-suit remediation project will be carried out within the new plant of Northeast Pharma. 9.2 Industrial Policy Compliance According to the Guiding Catalog of Industrial Structure Adjustment (2015 Edition) issued by the National Reform and Development Commission, this project belongs to Article 15 “Comprehensive Utilization and Treatment Project of the ‘Three Wastes’” of the thirty-eight “Environmental Protection and Resource Conservation Comprehensive Utilization” items, and is in line with national industrial policies. According to the Catalog of Guiding Principles of Industrial Development in Liaoning Province (2008 Edition), the project belongs to the encouraged categories in Article 32 “Comprehensive Utilization and Treatment Project of the ‘Three Wastes’” of the twelve “Environmental Protection and Resource Conservation Comprehensive Utilization” items, and is in line with the industrial policies of Liaoning Province.

9.3 Current Regional Environmental Quality 9.3.1 Current Environmental Quality of the Area inin-suit Remediation Project 9.3.1.1 Current Atmospheric Environmental Quality Shenyang Zeer Testing Services Co., Ltd. collected ambient air monitoring data from monitoring sites in the "Holiday Blue Bay Residential Community" from April 6 to April 12,

2016. The monitoring results showed that: The average 24-hour values of SO2, NO2 and PM10 at the monitoring sites met the Class II standard requirements of Ambient Air Quality Standard Shenyang Lvheng Environment Consulting Co. Ltd 199 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(GB3095-2012); the average hourly values of SO2 and NO2 all met the Class II standard requirements of Ambient Air Quality Standard (GB3095-2012); 9.3.1.2 Current Surface Water Environmental Quality The waste water produced during the process of soil excavation is mainly from flushing wheels of transport vehicles and domestic sewage generated by construction workers. The flushing water for wheels of transport vehicles is recycled after being treated in sedimentation tanks instead of being discharged; the domestic sewage produced by construction workers is treated to standard by septic tanks. Afterwards, it is discharged into the Xiannu River Sewage Treatment Plant through the municipal sewer network. As the drainage is not directly discharged into the surface water body, the surface water evaluation work in this project was omitted.

9.3.1.3 Current Noise Environmental Quality Shenyang Luheng Environmental Consulting Co., Ltd. entrusted Dalian Jing Cheng Sheng Inspections Hongyuan Detection Technology Co., Ltd. to conduct noise monitoring in the surrounding areas of original north plant area of Northeast Pharmacy from December 27 to December 28, 2017. The monitoring results show that the noise at the south boundary and north boundary of the project met the requirements of Class IVa standard of the Acoustic Environmental Quality Standard (GB30096-2008); the noise at the east boundary and the west boundary met the Class II standard of the Acoustic Environmental Quality Standard (GB30096-2008). 9.3.1.4 Current Soil Environmental Quality The soil monitoring data within the scope of this remediation was mainly based on the soil monitoring data from the Detailed Report on Environmental Investigation and Risk Assessment of Northeast Pharmacy POPs Field (Production Area of North Plant Area on North Second Road, Northeast Pharmaceutical Group Co., Ltd.) completed in November 2017 by Shenyang Environmental Sciences Research Institute. A total of 113 soil sampling sites were sampled in this remediation scope. A total of 888 soil samples were collected, representing an area of 114,000 m2. The monitoring results showed that the maximum values of 23 indicators exceeded the standard values. Among them, arsenic, mercury, lead, total chromium, nickel, copper, zinc, benzene and trichloromethane all exceeded the Soil Environmental Risk Assessment Screening Values for residential use of the Beijing local standard; aniline, benzo(a)anthracene, chrysene,

Shenyang Lvheng Environment Consulting Co. Ltd 200 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site benzo(b)fluoranthene, benzo(k)fluoranthene, Benzo (a) pyrene, indeno (1,2,3-CD) pyrene, dibenzo (A, H) anthracene, β-BHC, 4'-DDD, 4,4'-DDE, 4,4'-DDT, 2,4'-DDT, TPH (

Shenyang Lvheng Environment Consulting Co. Ltd 201 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

(GB3095-2012) Class II standard requirements; 1 hour hydrogen chloride mean value met the Hygienic Standards for the Design of Industrial Enterprises (TJ36-79) standard requirements; no VOCs detected. 9.3.2.2 Current Surface Water Environmental Quality The waste water produced in the ex-suit remediation plant area mainly includes quench tower drainage, caustic tower drainage and employee domestic sewage. The above waste water is discharged into the integrated sewage treatment station of the new Northeast Pharmacy plant to be processed till the standards are met, and then discharged through the municipal sewage pipe network into the Shenyang City West Waste Water Treatment Plant Expansion Project for further processing. Since the drainage is not directly discharged into the surface water bodies, the surface water evaluation work was omitted in this project. 9.3.2.3 Current Noise Environmental Quality The noise monitoring data around the plant boundary of the new Northeast Pharmacy plant from March 25 to March 27, 2015 were collected. The monitoring data showed that the noise at the boundary of the plant met the Class II of Acoustic Environmental Quality Standard (GB3096-2008) standard requirements. 9.3.2.4 Current Soil Environmental Quality For the soil environmental quality of the plant area, monitoring data were mainly collected from the vinpocetine workshop, propargyl alcohol device, tank field, sewage treatment plant, solid waste yard location, Qianma Village and Lintai Village on March 25, 2015. In the meantime, dioxin in the soil in this area was tested on December 11, 2016. The monitoring results showed that all the pollutants in the monitoring sites met the Class III standard requirements of the Soil Environmental Quality Standard (GB15618-1995); the dioxin in Qianma Village and Lintai Village met the Japanese environmental quality standards. 9.3.2.5 Current Groundwater Environmental Quality For groundwater in the soil ex-suit remediation area, 7-eye drilling holes and domestic wells were selected to monitor groundwater environmental quality. The monitoring results showed that ammonia nitrogen in S1 #, S2 #, S3 # and S4 # exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93); total hardness and nitrate

Shenyang Lvheng Environment Consulting Co. Ltd 202 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site in S5 #exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93); ammonia nitrogen, iron and volatile phenol monitoring results in S7 #exceeded the requirements of Class III limits in the Groundwater Environmental Quality Standard (GB / T14848-93); nitrate monitoring results in S6 #exceeded the requirements of Class III limits in Groundwater Environmental Quality Standard (GB / T14848-93). 9.4 Environmental Impact Analysis 9.4.1in-suit Remediation Project Environmental Impact Analysis 9.4.1.1 Atmospheric Environmental Impact Analysis 1. Construction Dust The main problems of air pollution in this project are the dust generated from soil dredging, remediating and transiting, as well as road dust generated from the construction motor vehicles and transport vehicles. According to the field survey, the site boundary is 20 m and 10 m away from the Wanke Spring Dew Mansion Residential Community and the Shenyang Tiexi Government Office, respectively. Due to the short distance, the dust generated during the construction process will affect the above-mentioned regional environment. The EIA recommends that a continuous enclosure of not less than 2.5 m height be provided around the site of remediation before the project starts, and to sprinkle water throughout the remediation process of the soil. All types of soil temporary storage areas in the temporary storage area should be covered, and soil remediation area (curing stabilization) should be set with closed membrane structured shed or enclosed treatment by an integrated machine, and the entire remediation project should be carried out in an enclosed environment; in the process of soil excavation, loading should be slowed and falling height should be reduced to reduce dust. After taking the above measures, the concentration of TSP in the air can be greatly reduced, the dust pollution in the construction site can be effectively alleviated, and the impact will disappear immediately after construction. 2. Exhaust of Construction Machinery and Equipment and Transport Vehicles Exhaust of machinery and equipment exhaust gas and transport vehicle tail gas will also exert some influence on the construction site, but the impact of construction vehicles is much smaller than that of traffic vehicles. As the exhaust gas of construction equipment and transport

Shenyang Lvheng Environment Consulting Co. Ltd 203 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site vehicles used will be discharged intermittently, and the impact will disappear immediately after construction, so it will have little effect on the ambient air quality. 9.4.1.2 Water Environment Impact Analysis The waste water produced during the process of soil excavation is mainly from flushing wheels of transport vehicles and domestic sewage generated by construction workers. As this project will not be conducted in the rainy season, foundation pit water will not be involved. According to engineering analysis, the flushing water for wheels of transport vehicles will be recycled after being treated in sedimentation tanks and will not be discharged outside; the domestic sewage produced by construction workers will be treated to standard by septic tanks in the south plant area of Northeast Pharma, and then discharged into the Xiannu River Sewage Treatment Plant through the municipal sewer network. 9.4.1.3 Noise Environment Impact Analysis The noise sources of this project are mainly the noise generated by mechanical work during site preparation, soil dredging and soil remediation. Mechanical noise is mainly generated by excavators, bulldozers, integrated mixers (curing stabilization), etc., mostly point sources. The noise generated by these machines is usually at the level of 75-85dB (A). In addition, there are some sporadic instantaneous noises during construction work, such as beating noise and percussive noise. The noise of construction vehicles is traffic noise. The project will construct a continuous and enclosed enclosure with height not less than 2.5m around the site for remediation, which will have good sound insulation effect for excavation noise. In addition, low-noise equipment will be selected to be used and measures such as enclosure and shielding of high-noise equipment will also be used. Noise can be reduced by about 20dB (A) after taking measures. 9.4.1.4 Environmental impact analysis of solid waste The solid wastes generated in this project were mainly polluted soil excavated and a small amount of domestic garbage generated by staff. According to the Remediation Plan of Northeast Pharmacy POPs Field (Production Area of North Plant Area on North Second Road, Northeast Pharmaceutical Group Co., Ltd.), the volume of soil to be excavated in the project is 70171m3, and some of the soil is transported to the new Northeast Pharmarcy plant for remediation; some

Shenyang Lvheng Environment Consulting Co. Ltd 204 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site is remediated and transported to the Laohuchong landfill as the cover soil; 24888 m3 soil that can be directly used is transported to the new Northeast Pharmacy plant for processing. The amount of household garbage produced by the staff is about 0.13t/a, which is cleared by the sanitation department. In addition, the soil excavation stage should also pay attention to the original site of the sewer line. According to the original Northeast Pharmacy plant production process, the waste pipe will be left with some organic pollutants, once the pipeline is broken by digging, pollutants can cause secondary pollution. Through the above analysis, all types of solid wastes that will be generated during the process of soil remediation will not have any impact on the surrounding environment after proper treatment. 9.4.1.5 Groundwater Environment Impact Analysis According to the hydrogeological conditions of the contaminated site, in order to avoid secondary pollution to groundwater environment cause by soil remediation to the maximum extent, sedimentation tank, car wash yard, soil temporary storage area and soil remediation area should undergo key anti-seepage treatment and anti-leakage measures should be taken for waste water pipelines. 9.4.2 Environmental Impact Analysis of ex-situ Remediation Project 9.4.2.1 Atmospheric Environment Impact Analysis In the process of the project of hot stripping VOCs, particulate matter, HCl, dioxin is forecasted, the prediction results show that the thermal stripping exhaust particulate matter in the maximum ground concentration of 0.001404 mg/m3, of standard rate of 0.16%; The maximum landing concentration of VOCs is 0.01158mg/m3, accounting for 0.64% of the standard rate. The maximum landing concentration of HCl is 0.0002363mg/m3, accounting for 0.47% of the standard rate. The maximum landing concentration of dioxins was 0.00331pg/m3, accounting for 0.18% of the standard rate. The maximum landing concentration was 93m below the pollution source. In the process of project restoration, the maximum landing concentration of all pollutants is low, so it has less impact on environmental sensitive points such as surrounding residential areas. 9.4.2.2 Surface Water Environmental Impact Analysis

The wastewater discharged during Ex-situ Remediation includes Spray tank drainage and domestic wastewater generated by construction personnel. The above wastewater is discharged into Shenyang Lvheng Environment Consulting Co. Ltd 205 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site the new comprehensive sewage treatment station of the northeast pharmaceutical factory, and then discharged into the west shenyang sewage treatment plant through the municipal sewage pipe network after reaching the standard.

9.4.2.3 Noise Environmental Impact Analysis The main sources of noise in the soil restoration process of this project are thermal desorption equipment. The construction unit intends to use low-noise equipment, which will undergo the vibration attenuation process. Noise-generating equipment will be placed within the plant. With these measures, the noise can be reduced to 25-30dB. 9.4.2.4 Solid Waste Environmental Impact Analysis According to the analysis of the project, in the process of Ex-situ Remediation, the generated solid wastes mainly include: the waste activated carbon produced by the adsorption of activated carbon and Domestic wastes generated by construction personnel. the waste activated carbon produced belongs to the hazardous waste (HW49), which is temporarily stored in the temporary storage room of the hazardous waste, and is finally incinerated and disposed by the hazardous waste incinerator. The waste generated by the staff shall be uniformly handled by the sanitation department.

The temporary storage space of hazardous waste includes the storage space of solid and semi-solid waste. The total area is about 3000 m2, and the storage height is no more than 2m. It is in the form of barrels, with a specification of 200kg, a daily storage capacity of 40t, a maximum storage period of 45d, and a design service life of 50a. The hazardous waste temporary storage room is used for storing the incineration residues, fly ash, waste activated carbon, raw materials and auxiliary reaction products, waste machine oil, etc. produced by the eastern medicine hazardous waste incinerator. The waste activated carbon produced by this project can be stored in the temporary storage room of hazardous waste. The output of project waste activated carbon is 36t. Therefore, the existing hazardous waste temporary storage room of Northeast Pharmaceutical Plant can store the hazardous waste generated by this project.

Northeast Pharmaceutical Plant incinerator was founded in 2011 by shenyang environmental science research institute of the Northeast Pharmaceutical Group Co., Ltd. Long-distance transformation pollution treatment project of construction project environmental impact report, and in

2011, on June 27, the eia approval, approval document number of shen environmental review words Shenyang Lvheng Environment Consulting Co. Ltd 206 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

[2011] no. 187. The incinerator has been built and put into use.

Incineration capacity: 20t/d(or 7300t/a),Smoke duration: greater than or equal to 2S; Residual heat burn reduction: less than 5%; The reduction rate of harmful substances reached > 99.99%.

Second combustion chamber of flue gas temperature: 1100-1300 ℃ or higher.

According to the eia approval, the incinerator is mainly used for the residual kettle, high concentration mother liquor and non-biochemical waste water generated in the incineration process.

The hazardous waste activated carbon produced by this project can be burned. And the amount of hazardous waste produced by the project is about 36t. The capacity of the incinerator can meet the needs of the project.

Through the above analysis, all kinds of solid waste generated in the soil restoration process will not affect the surrounding environment after proper treatment.

9.4.2.5 groundwater Environmental Impact Analysis

Engineering contaminated soil chemical oxidation (7000 m2) repair workshop, hot stripping repair area (including thermal stripping process of untreated soil staging area, such as pretreatment, disposal areas, a total of about 11000 m2) has taken strict anti-corrosion, seepage control measures on the ground, to avoid the project soil restoration, especially pollution during the staging of groundwater pollution caused by the site. It is required that the anti-seepage performance of the anti-seepage layer should be no lower than the anti-seepage performance of 1.0×10-10cm/s. In this project, cement base permeable crystalline water-repellent was added into the concrete, with a structural thickness of 310mm.

After the operation of the project, a small amount of waste water will be generated. Relying on the existing drainage pipe network in the Northeast Pharmaceutical Plant plant, it will not have a direct impact on the groundwater. The surface of the contaminated soil deposit area is covered with plastic film tarpaulin. After the ground is strictly impervious to infiltration, the pollutants in the soil will not contaminate the soil through rainfall infiltration into the ground. In addition, after the initial rainwater collection in the eastern medicine factory area on which the project is based, it will be discharged into the sewage treatment station without the formation of ground runoff, which will pollute the soil and groundwater. Therefore, the construction of this project will not have a significant impact on the groundwater environment.

Shenyang Lvheng Environment Consulting Co. Ltd 207 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

9.4.2.6 Analysis of Environmental Impacts During the Decommission Phase Combined with the actual situation, the soil remediation period of construction project in the new Northeast Pharmarcy plant is expected to be 8 months. After the soil remediation is completed, the project will be demolished. 7 types of heavy metals (arsenic, copper, zinc, nickel, lead, chromium and mercury), 5 types of PAHs (benzo (a) pyrene, benzo (b) fluoranthene, dibenzo (a, h) anthracene and indeno (1,2,3-cd) pyrene), 2 types of POPs (DDT, DDD, DDE and β-BHC), aniline and 2 types of VOCs (benzene and chloroform) and TPH (

Shenyang Lvheng Environment Consulting Co. Ltd 208 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site gas purifiers and use fuels that comply with national standards. It is prohibited from using inferior fuels to reduce the emission of harmful gases from machinery and vehicles; all motor vehicles need to undergo regular exhaust pollution testing by an agency with appropriate qualification entrusted legally by the municipal environmental protection administrative department. The vehicles should also obtain the symbol of environmental protection conformity. 9.5.1.2 Wastewater Pollution Prevention and Control Measures As this project will not be conducted in the rainy season, foundation pit water will not be involved; the domestic sewage produced by construction workers will be treated to standard by septic tanks in the south plant area of Northeast Pharma, and then discharged into the Xiannu River Sewage Treatment Plant through the municipal sewer network; the flushing water for construction vehicles will be recycled for use and will not be discharged outside; and the key seepage prevention measures will be carried out on the sedimentation tank, soil temporary storage area, curing stabilization zone and the four walls and the bottom of the car wash yard; 9.5.1.3 Noise Pollution Prevention and Control Measures During the implementation of the project, the noise emission should not exceed the limit specified in the Emission Standard of Environment Noise for Boundary of Construction Site (GB 12523-2011), i.e. 70dB in daytime and 55dB in nighttime. low-noise construction machinery or those with noise reduction equipment should be used as much as possible; strong-noise equipment should be enclosed or blocked with noise enclosures to achieve noise reduction; reasonable arrangements for construction work time, construction should be prohibited during 22:00 to 6:00 at night; if construction at night is necessary, relevant examination and approval procedures should be handled with the relevant departments, and the consent of the surrounding residents should be obtained before carrying out the construction. 9.5.1.4 Solid Waste Pollution Prevention and Control Measures Necessary on-site screening should be carried out during the clearance of each plot. For each type of contaminated soil, it is necessary to ensure that all contaminated soil in this category are fully excavated while avoiding mixing soil with heavier contamination into less contaminated soils and mixing of soils of different types, which will increase the amount of heavily contaminated soil, resulting in an increase in the cost of subsequent treatment. Different

Shenyang Lvheng Environment Consulting Co. Ltd 209 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site types of contaminated soil need to be treated with different excavators to avoid cross-contamination; temporary storage areas should be set up with different classifications (temporary storage area for soil to be remediated, soil conservation area after remediating, and temporary storage area for soil to be directly transported outward and temporary storage area for soil to be inspected and accepted), and corresponding identification marks should be set on the boundaries of the soil stacks; after the soil remediation, the soil in the temporary storage area and remediation area should be sampled to prevent the contaminated soil from contaminating the uncontaminated soil; the contaminated soil dredged out should be transported to the Laohuchong domestic waste landfill plant as soon as possible to avoid a long period of storage in the soil temporary storage area; living garbage generated by workers should undergo central bio-safety disposal by the sanitation department. 9.5.1.5 Risk Prevention and Control Measures Soil disturbance should be reduced to lower the amount of pollutant escape. During the polluted soil cleanup, the excavator bucket should operate smoothly, and long-distance throwing of polluted soil or throwing polluted soil from above into the transporter should be prohibited. When loading the transporter with contaminated soil, the excavator bucket should be as close to the vehicle for loading and unloading as possible. Specialized personnel should be dispatched to carry out inspection on the vehicles and if the tarpaulin is blown away during transport, he should immediately inform the transport vehicle to stop at the side and order the driver to fix the cover before the vehicle can continue to transport. Mobile pollutant monitoring equipment should be in place to monitor the ambient air along the way of transport to ensure that the air quality during the transport is in line with relevant standards of the country and Liaoning Province. Contaminated soil remediation should be done in negative-pressure sealed shed as much as possible. 9.5.2 Ex-situ Remediation Remediation Project Pollution Prevention and Control Measures 9.5.2.1 Air Pollution Prevention and Control Measures

1. Exhaust gas generated while soils are fed, crushed, agitated, and outputted

The soil chemical oxidation treatment process is located in the closed workshop, spraying water and dust. The amount of dust produced in the process of soil thermal desorption is small, and the feeding port is located in a closed greenhouse. The soil is transported by a closed belt. The thermal Shenyang Lvheng Environment Consulting Co. Ltd 210 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site desorption material is located in the closed color steel house, and a spray device is set at the exit.

After the above measures are taken, dust is discharged out of the workshop through the natural ventilation of the workshop.

2. Exhaust gas generated in the process of chemical oxidation

The soils under chemical oxidation are covered by plastic films, to reduce the fugitive emission of VOCs and SVOCs.

3. Exhaust gas generated by the untreated soil stacks

Cover the untreated soil stacks with dust net and plastic rain-proof film, compacted and regularly spray inhibitors to reduce the discharges of VOCs. When the untreated soil is taken out of the soil, it needs to partially open the covered plastic film and cover and compacted the soil in a timely manner.

4. Exhaust gas generated in the process of thermal desorption

The waste gas generated in the process of soil thermal desorption is discharged at an altitude of

15m high exhaust air tube after reaching the standard through spraying , mist removal tank , gas purification tank (activated carbon adsorption) and combustion chamber purification.

9.5.2.2 Waste Water Pollution Prevention and Control Measures

The waste water produced in the process of soil chemical oxidation and thermal desorption is mainly discharge from spray tanks and domestic sewage of employees. The above wastewater is discharged into the new comprehensive sewage treatment station of the northeast pharmaceutical factory, and then discharged into the west shenyang sewage treatment plant through the municipal sewage pipe network after reaching the standard.

9.5.2.3 Noise Pollution Prevention and Control Measures When choosing soil grinders, mixers and fans, low-noise equipment should be prioritized, in order to achieve the purpose of reducing noise from the source; reasonable layout should be adopted, and high noise source should be far away from the plant boundary to attenuate the noise by distance; vibration attenuation measures should be taken for the equipment. 9.5.2.4 Solid Waste Pollution Prevention and Control Measures The solid waste produced in the process of soil remediation is mainly the waste activated carbon produced by the adsorption of activated carbon and the domestic waste of employees.

Shenyang Lvheng Environment Consulting Co. Ltd 211 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Among them, the waste activated carbon belongs to the hazardous waste (HW49 other waste), which is temporarily stored in the hazardous waste room of the new pharmaceutical factory in northeast China and incinerated by the hazardous waste incinerator of eastern medicine. Due to the pollutants concentration distribution in the soil, soil management process, activated carbon usage may be below or above forecast, should be based on monthly, hot stripping exhaust test result judgment, activated carbon adsorption effect, that the test results is high, should be timely replacement of activated carbon. Household waste shall be uniformly cleared and disposed of by the sanitation department. 9.5.2.5 groundwater Pollution Prevention and Control Measures

Strict anti-corrosion and anti-seepage measures have been taken on the ground of the plant to avoid the ground water pollution caused by the soil restoration project of this project, especially during the temporary storage of contaminated soil. It is required that the anti-seepage performance of the anti-seepage layer should be no lower than the anti-seepage performance of 1.0×10-10cm/s. In this project, cement base permeable crystalline water-repellent was added into the concrete, with a structural thickness of 310mm.

9.5.2.6 Environmental risk Prevention and Control Measures

1. Thermal desorption system

Periodic maintenance and overhaul are important measures to reduce the occurrence of accidents. Thermal despatching equipment should be scheduled for maintenance.

The maintenance management of the equipment should be strengthened so that it can be run in good condition, and operation should be strictly regulated to avoid accidents.

The system is equipped with power failure protection, overload protection and line fault alarm.

Double circuit power supply of thermal desorption system is required.

2. Flue gas treatment system

The thermal desorption equipment must be equipped with an automatic control system, which can display operating conditions and exhaust emission parameters online, and can automatically feed back to ensure that the outlet flue gas of the thermal desorption equipment meets the standards.

Direct thermal desorption is used in this project, and the control of dioxin production mainly starts from the following two aspects:

Using advanced, perfect and reliable control system, the purification process can be well Shenyang Lvheng Environment Consulting Co. Ltd 212 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site implemented.

Potassium is adsorbed by activated carbon to further remove dioxins.

3. Public utilities

Mobile gas storage tanks should be equipped with a certain number of portable co2 fire extinguishers.

Obvious signs are set up in the extinguishing area.

Beefy personnel management. The operator shall conduct post training, strictly implement the operating rules, and strictly forbid the illegal operation.

Special personnel shall be responsible for inspecting natural gas storage tanks with clear responsibilities so as to timely detect problems such as leakage and out-of-control, timely solve them and eliminate potential accidents.

Flow makes perfect emergency plans. In case of fire accident, the fire alarm should be immediately activated and the fire control system should be started. Organize the evacuation of nearby people according to the accident status and cooperate with fire fighting personnel.

This project relies on the fire control system and the accident pool of Northeast Pharmaceutical

Plant factory, and takes necessary preventive measures for the possible accidents in all the systems, so as to make the risk accident probability reach an acceptable level.

9.6 Public Participation Northeastern Pharmaceutical Group Co., Ltd. staff in January 21, 2018 - January 25, respectively, Vanke Long Run Park, Heavy Industries Village, Shenyang City 36 Middle School on-site publicity, and in January 21, 2018 -1 On January 22, a questionnaire survey was conducted on the public involved in the project. The survey results showed that all surveyed public were aware of this project and all supported the project construction. At the same time, on January 26, 2018, a symposium was held at Block H, Innovative Place in Shenyang. At the symposium, all delegates said that the project would generate dust in the construction process and noise would be generated from the construction equipment, all of which would affect the surroundings. Hope In making the plan, we should fully consider the above factors, formulate reasonable and feasible environmental protection measures, and strictly implement the above measures in the construction process to reduce the impact on the surrounding environment.

Shenyang Lvheng Environment Consulting Co. Ltd 213 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

The staff of Northeast Pharmaceutical Co., Ltd. performed public demonstrations at Vanke Run Park, Heavy Industry New Village and Shenyang No. 36 Middle School from February 22 to February 28, 2018, and they were at Liaoshen on February 27, 2018. The Evening News made a public announcement and on March 12, 2018, the entire report was publicized on Shenyang Luheng Environmental Consulting Co., Ltd.'s website. At the same time, a survey was conducted on the public involved in the project from February 26 to February 28, 2018. The survey results showed that all the survey public supported the project construction and put forward reasonable suggestions. At the same time, on March 1st, 2018, a field discussion meeting was held in Shenyang Innovation World. Representatives of Northeast Pharmaceutical Group Co., Ltd. introduced the preparation of the project and gave a detailed description of the restoration program and environmental protection measures. Representatives consulted and discussed issues in the program and made reasonable suggestions. .9.7 Conclusions and Suggestions This site soil remediation project itself is an environmental protection project in full compliance with the economic construction guidelines of scientific concept of development, and building an environment-friendly and resource-saving society, in line with national industrial policies and urban planning requirements. Based on the actual conditions of the factories, the following suggested are proposed: (1) As there are many sensitive points around thein-suit Remediation sites of the project, the construction period should be reasonably arranged to avoid unfavorable weather conditions such as fog and haze. ⑵ Sampling and testing of soil samples should be conducted in real time during the excavation stage of the project. The acceptance and monitoring of the original unpolluted soil in the soil temporary storage area and the soil remediation area should also be conducted during the acceptance of contaminated soil in this site. (3) After the implementation of this project, before the development and construction of the remediation plot, the soil samples in the restored site should be tested, and the test results should meet the requirements of the corresponding development sites in order to carry out development. (4) After site remediation, the human health risks under the current usage scenarios are

Shenyang Lvheng Environment Consulting Co. Ltd 214 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site acceptable. Since contaminated soils in the site are not yet fully cleaned up, the site should be subject to environmental management in the late stage and the use of the site and disposal of soil should be strictly controlled. To sum up, after implementing various pollution prevention and control measures proposed in this project, the environmental positive effects of this project should be much greater than the negative effects. This is of positive significance for improving the present environmental quality of the contaminated site. Therefore, it is feasible to analyze the project construction from the perspective of environmental protection.

Shenyang Lvheng Environment Consulting Co. Ltd 215 #109-5 Level 17, Block H, Quanyun road, Hunnan District, Shenyang City

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Figure 1 Project on-site and ex-suit remediation areas geographic location map

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Attached Figure 2 Map of ambient air, noise and groundwater monitoring sites of north plant area of original Northeast Pharmacy

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Attached Figure 3 Map of soil monitoring sites of north plant area of original Northeast Pharmacy plant (On-site remediation

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Attached Figure 4 Map of monitoring sites of new Northeast Pharmacy plant (Ex-suit remediation field)

Global environmental fund “China Contaminated Site Management Project” Liaoning demonstration project Environmental and Social Impact Assessment Report for Remeidation of the Northeast Pharmaceutical Plant contaminated site

Attached Figure 5 Map of groundwater monitoring sites of new Northeast Pharmacy plant (Ex-suit remediation field)