<<

East , and & Local Aggregate Assessment

December 2017

East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

NOTE

In September 2017 , Brighton & Hove City Council and the South Downs National Park Authority commenced a Review of their Waste and Minerals Local Plan. This year's LAA has been drafted for consideration by SEEAWP before the end of the consultation period for the Call for Evidence and Sites. In addition, adoption of the LAA is planned before formal consideration of the responses to the Call for Evidence and Sites. It would not therefore be appropriate to pre-empt possible changes in aggregate supply in this document and so discussion of future demand and supply scenarios will not be included. These details will be assessed at the next stage of the Waste and Minerals Local Plan Review process in 2018. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

Contents

Executive Summary 3 1 Introduction 9 2 Geology and mineral uses 12 3 Demand 14 4 Supply 20 5 Environmental constraints 32 6 Balance 34 7 Conclusions 37 A Past and Future Development 39 B Imports into plan area 44 C LAA Requirements 45 Map 1: Geological Plan including locations of aggregate wharves and railheads, and existing aggregate sites 48 Map 2: Origin of aggregate imported, produced and consumed in East Sussex and Brighton & Hove during 2014 50 Map 3: Sand and gravel resources in the East and Thames Estuary (Source: Crown Estate) 52 Map 4: Recycled and secondary aggregates sites 2016/17 54 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 3

Executive Summary Executive Summary

Executive Summary

The first East Sussex, South Downs and Brighton & Hove Local Aggregate Assessment (LAA) was published in December 2013. The LAA has been updated annually and is based on the Plan Area for the adopted East Sussex, South Downs and Brighton & Hove Waste & Minerals Local Plan (WMLP). This document represents the fifth LAA for the mineral planning authorities of East Sussex County Council, Brighton & Hove City Council and the South Downs National Park Authority (the Authorites) and examines updates to the position on aggregates supply and demand since the time of last reporting in 2016.

In past years the Authorities' assessment was that there were particular circumstances in this Plan Area that made it difficult to prepare the LAA totally along the lines indicated in the NPPG. Previous LAAs concluded that the assessment could not use past 10 years sales data as this was too volatile because there is a very small number of production sites and therefore there has been major variation in sales figures from nothing to more substantial output. Past LAAs instead used the Apportionment figure in the Adopted WMLP as a surrogate figure for forward planning.

In 2016 a Public Examination on the soundness and legal compliance of the East Sussex, South Downs and Brighton & Hove Waste and Minerals Sites Plan was held. Hearings focused on the whether the Plan provided a sufficient and adequate supply of aggregates. Whilst the Inspector found the Sites Plan sound in his Report he highlighted the need for a Review of the aggregate minerals policies. The Authorities have since agreed to a Review of the Waste and Minerals Local Plan (WMLP) and in September 2017 published a consultation on the Call for Evidence & Sites .

It is accepted by the Authorities that the WMLP aggregate policies are in need of review and so this year the LAA will seek to provide updated background information for the Review of the Waste and Minerals Local Plan. The LAA has been drafted for consideration by SEEAWP before the end of the consultation period for the call for evidence and sites. In addition, adoption of the LAA is planned before formal consideration of the responses to the call for evidence and sites. It is not therefore appropriate to pre-empt possible changes in aggregate supply in this document and therefore discussion of future demand and supply scenarios will not be included. These details will be assessed at the next stage of the Local Plan Review process in 2018. This LAA therefore examines the latest information and data available on aggregates in the context of the considerations raised by SEEAWP and the MPA/POS guidance (see Appendix C).

The overall picture of aggregate supply to the Plan area is of heavy dependence on imports by road, sea and rail. Significant levels of marine imports (marine dredged and crushed rock) are received through Shoreham Port and to a lesser extent 4 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

Executive Summary

Newhaven and Rye. Crushed rock, recycled aggregate and sand and gravel are imported by rail at Newhaven. Land-won sand and gravel is extracted in the east of the Plan area at with about 50% of material being consumed in East Sussex. A steady supply of recycled material is produced from construction waste management facilities across the Plan area. A continuing demand for construction materials is anticipated.

The South East Aggregates Working Party (SEEAWP) has requested that MPAs include a comparative Key Facts table in their LAA. The data included in this table is to be found within the LAA and is pulled together here to enable easier assessment and collation of information. Key Facts

East Sussex, South Downs and Brighton Hove & 20171

3 Sales2 (Mt) Av Av3 (3y) Trend4 LAA5 Reserve6 Landbank7 Capacity8 Comments9 East (10y) Sales rate (Mt.) (Yrs) (Mtpa)

(Mt) (Mt) Sussex, Sales (Mt) South

Sharp Sand & Gravel 0.3 (2016) N/A 0.4 N/A 2.0 N/A No 10 year average not applicable as working has only been in East Downs restrictions Sussex since 2011. and Sales in the last 3-4 years have have been higher than the rate Brighton

anticipated in the planning permission, although the total for 2016 Executive is approx.117 000 tonnes less than 2014. &

Soft sand 0 c c N/A 0.35 N/A Market Extraction commenced in 2007 but no extraction has taken place Hove, - led? in recent years. Recent renewal of permission indicated that

reserve was 350 000 tonnes. Local

All Sand and Gravel c 0.4 0.1 2.3 23* As per The landbank for the Plan Area has been calculated in the past as Aggregate market the full resource available at Stanton's Farm and the reserve from demand the permitted sites at Lydd Quarry within the boundary of East

Sussex divided by 0.1 mtpa. This gives a landbank figure at the Summary end of 2016 of 23 years. However, the use of 0.1mtpa as a the Assessment, principal indicator of demand, and the method of calculating the 0.3 (2016) landbank will be re-examined as part of the Review of the Waste and Minerals Local Plan. *As such the landbank figure for 2016

should only be read as a nominal figure and not as an actual December measure of supply in the Plan area It should also be noted that recent renewal of permission indicated that reserve at Novington is now 350 000 tonnes. 2017 5 6 East East Sussex, South Downs and Brighton Hove & 20171 Executive Sussex,

Crushed rock N/A N/A N/A N/A N/A 0 0 0 No crushed rock produced in the Area but imports are significant South element of supply. Downs

Recycled/Secondary 0.2 N/A Not N/A 0.7 Sales and capacity figures are taken from 2008/9, and updated Aggregates (2008/9) known (2015) figures would therefore help clarify situation. However, monitoring and

of sites for 2016 saw a much improved response rate compared Brighton

with previous years, and although not reflecting a full coverage of Summary facilities, results are not far off previous estimates. &

Marine sand and 0.008* N/A Not N/A N/A Safeguarding of wharves is a crucial issue. Sales of marine imports Hove, gravel (2016) known received at Shoreham Port (which is partly within Brighton & Hove) are monitored by County Council. These sales also Local contribute to the supply for the East Sussex, South Downs and Brighton & Hove area. Previous imports have been confidential. Aggregate *The figure given is from East Sussex Ports only.

Rock Imports by Sea 0.05* N/A Not N/A N/A Safeguarding of wharves is a crucial issue. Previous imports have

(2016) known been confidential. *The figure given is from East Sussex Ports only. Assessment,

Rail depot sales (S&G) 0.02 (2016) N/A Not N/A Not Relatively new imports of recycled and sand and gravel making known* known important contribution to supply particularly for recent infrastructure projects. Both types marked increase in last year. December *Only two years data available so far.

Rail Depot Sales 0.07 (2016) N/A 0.07 N/A Not Relatively new imports of crushed rock making important 2017 (Crushed Rock) known contribution to supply particularly for recent infrastructure projects. Imports have varied over last 3 years.

Comments9 Overall picture of aggregate supply – currently heavily dependant on imports by road, sea and rail; land-won sand and gravel in the west of the Plan Area; significant marine imports through Shoreham Port and to lesser extent Newhaven and Rye, rail imports of crushed rock, recycled aggregate and sand and gravel at Newhaven; and a level of supply from recycled aggregates throughout the Plan Area.

Steady continuing demand anticipated. East Sussex, South Downs and Brighton Hove & 20171

The adopted aggregate policies are being reviewed as part of the current Review of the Waste and Minerals Local Plan. A consultation on the the call for sites and evidence commenced on 25 September for 8 weeks. East Table 1 Sussex,

Table Notes overleaf South Downs and Brighton Executive & Hove, Local Aggregate Summary Assessment, December 2017 7 8 East

Table Notes: Executive Sussex, 1 Publication date. South 2 Figures in millions of tonnes rounded to one decimal place. AMR year in brackets. Downs 3 Averages based on last ten/three year sales. and 4 An indicator whether there is growth (+) or decline (-) in sales. Brighton Summary 5 LAA Rate is the LAA Provision Rate as determined by the mpa as the suitable measure for estimating the landbank for land-won aggregates. & Hove,

6 Reserves are the amount of mineral with planning permission for extraction. Local

7 Landbank calculation is the reserve divided by LAA Rate to indicate life in years of the mpa reserve. Aggregate

8 Capacity is an estimate of how much the quarry or site could produce based on plant capability and planning restrictions. Assessment, 9 Brief summary on aggregate supply and any issues. c = confidential December 2017 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 9

Introduction1 1 Introduction

1.1 The first East Sussex, South Downs and Brighton & Hove Local Aggregate Assessment (LAA) was published in December 2013 and this document (LAA 2017) represents the fifth LAA for the mineral planning authorities (mpa) of East Sussex County Council, Brighton & Hove City Council and South Downs National Park Authority. The LAA is based on the Plan Area for the adopted East Sussex, South Downs and Brighton & Hove Waste & Minerals Local Plan, and covers the administrative area of East Sussex and Brighton & Hove including those parts that lie within the South Downs National Park.

1.2 The National Planning Policy Framework states that mineral planning authorities should plan for a steady and adequate supply of aggregates by preparing an annual LAA based on a rolling average of 10 years sales data and other relevant local information. The LAA should include an assessment of all supply options including land won, marine dredged, secondary and recycled sources.

1.3 The National Planning Practice Guidance (NPPG) indicates that a LAA should contain three elements:

a forecast of the demand for aggregates based on the rolling average of 10-years sales data and other relevant local information; an analysis of all aggregate supply options, as indicated by landbanks, mineral plan allocations and capacity data e.g. marine licences for marine aggregate extraction, recycled aggregates and the potential through-puts from wharves. This analysis should be informed by planning information, the aggregate industry and other bodies such as local enterprise partnerships; and an assessment of the balance between demand and supply, and the economic and environmental opportunities and constraints that might influence the situation. It should conclude if there is a shortage or a surplus of supply and, if the former, how this is being addressed

1.4 The NPPG also gives further details on the aggregate supply options including:

recycled aggregates, including from construction, demolition and excavation waste; secondary aggregates, whose sources come from industrial wastes such as glass, incinerator bottom ash, railway ballast, and scrap tyres; and industrial and minerals by-products; marine aggregates from The Crown Estate. Information will cover the areas licensed by the Marine Management Organisation for marine sand and gravel dredging and, as they are prepared over time, Marine Plans. The Marine Policy Statement (MPS) is used as the overarching UK policy framework for the production of marine plans and in the absence of an adopted marine plan the MPS will inform decisions in the UK marine area; 10 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

1Introduction

imports into and exports out of the minerals planning authority area. The minerals planning authority must capture the amount of aggregate that it is importing and exporting as part of its Assessment; and land-won resources, including landbanks and site specific allocations.

1.5 A revised version of the Practice Guidance on the production and use of Local Aggregates Assessment was prepared in May 2017 by the Minerals Product Association and Planning Officers' Society (MPA/POS). Following consideration of this guidance SEEAWP have requested that mpas take specific matters into account in their 2017 LAAs (see Appendix C).

1.6 In August 2017 SEEAWP published a draft South East Aggregates Monitoring Report 2016 using information from the 2016 Aggregates Monitoring Survey. This report also sets out regional issues for mpas to consider in preparing their LAAs (set out in Appendix C).

1.7 In past years the Authorities' assessment was that there were particular circumstances in this Plan Area that made it difficult to prepare the LAA totally along the lines indicated in the NPPG. Previous LAAs concluded that the assessment could not use past 10 years sales data as this was too volatile because there is a very small number of production sites and therefore there has been major variation in sales figures from nothing to more substantial output. Past LAAs instead used the Apportionment figure in the Adopted Waste and Minerals Local Plan (WMLP) as a surrogate figure for forward planning.

1.8 In 2016 a Public Examination on the soundness and legal compliance of the East Sussex, South Downs and Brighton & Hove Waste and Minerals Sites Plan was held. Hearings focused on the whether the Plan provided a sufficient and adequate supply of aggregates. Whilst the Inspector found the Sites Plan sound in his Report he highlighted the need for a Review of the aggregate minerals policies. The Sites Plan was adopted in February 2017. The Authorities have since agreed to a Review of the WMLP and in September 2017 published a consultation on the Call for Sites and Evidence.

1.9 It is accepted by the Authorities that the WMLP aggregate policies are in need of review and so this year the LAA will seek to provide updated background information for the Review of the Waste and Minerals Local Plan. The LAA has been drafted for consideration by SEEAWP before the end of the consultation period for the call for evidence and sites. In addition, adoption of the LAA is planned before formal consideration of the responses to the call for evidence and sites. It is not therefore appropriate to pre-empt possible changes in aggregate supply in this document and therefore discussion of future demand and supply scenarios will not be included. These details will be assessed at the next stage of the Local Plan Review process in 2018. This LAA therefore examines the latest information and data available on aggregates in the context of the considerations raised by SEEAWP and the MPA/POS guidance (see Appendix C). East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 11

Introduction1

1.10 A draft of this LAA was considered and approved by SEEAWP on 6 November 2017. Various statutory bodies and organisations were also consulted on the draft document, including Natural England, the relevant Local Enterprises Partnerships, the Marine Management Organisation and mineral planning authorities covering areas of aggregate resource imported into the LAA area. 12 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

2Geology and mineral uses 2 Geology and mineral uses

2.1 Geologically, sand and gravel aggregate resources within the Plan Area are limited to relatively small outcrops of the sand in the Beds, river gravels and foreshore deposits of sand and gravel. Sharp sand and gravel, and soft sand can have different uses. Sharp sand and gravel are primarily used for concreting purposes and this is an essential raw material for the construction industry. Building sand is largely used as fine aggregate in the production of concrete, mortars and asphalt. Both types of material can be used as fill. There are no sand and gravel reserves within the boundary of Brighton & Hove.

2.2 The Folkestone Beds comprise the uppermost division of the Lower Greensand and consist of loosely consolidated fine grained quartzose sands. The outcrop of the deposit is very limited consisting of a narrow strip in the western part of the Plan Area, running eastwards from for a relatively short distance. The fine grained nature of the sand means it readily meets British Standards for mortar sand. The area of Lower Greensand within East Sussex was previously outside the Sussex Downs AONB but it is now located within the South Downs National Park (SDNP). The SDNP Authority has undertaken a study to assess the potential resource across the Park and alternative sources outside the Park boundary. Along with other mineral planning authorities in the South East, the Authorities have recently signed a Statement of Common Ground on soft sand which aims to collaboratively address supply issues facing an important mineral used by the construction industry.

2.3 The foreshore resource comprises extensive storm beach deposits along the coast. The wedge shaped accumulations consist almost entirely of flint with only a small proportion of sand. The main areas are between Beach and , and, the western part of Dungeness around Camber. The resource is mostly used in concreting.

2.4 Substantial marine aggregate resources lie along the South East coast and in the English Channel which are widely extracted under licence by several aggregate companies with landings made at numerous wharves in the region. There are some landings at Shoreham Harbour within Brighton & Hove on the border with West Sussex, and until recently, at Newhaven Port. Crushed rock from various sources is also landed at Shoreham, Newhaven and also Rye Port. Other wharves used for marine dredged material are within the Thames Estuary and .

2.5 Marine aggregates can yield both sand and gravel. Marine dredged aggregates are mostly utilised for concreting purposes, whilst crushed rock of various types is used locally in an unprocessed form for road construction or subsequently processed for the manufacture of coated roadstone products.

2.6 There are no hard rock aggregate reserves in the Area. Chalk has been the subject of significant levels of quarrying in the past, notably for the cement industry and to produce lime mortar and agricultural lime. Chalk also has the potential to East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 13

Geology and mineral uses2 yield crushed rock aggregate fill. However, all chalk extraction operations have now ceased and chalk is unlikely to make anything other than a minor contribution to aggregate production in the area in the foreseeable future.

2.7 A geological plan including locations of existing minerals facilities (Map 1), and details of sand and gravel resources in the East English Channel and Thames Estuary (Map 3) are included at the end of this document. 14 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

3Demand 3 Demand

Past Demand

National & Regional Guidelines for Aggregates Provision in England 2005 to 2020

3.1 For the Plan Area "demand" is a difficult part of the LAA to determine. This is partly because the consumption picture cannot be ascertained with any certainty (see paragraphs below). The NPPG states that the Government’s national and sub-national guidelines serve a purpose of providing individual minerals planning authorities, where they are having difficulty in obtaining data, with some understanding or context of the overall demand and possible sources that might be available.

3.2 The most recent guidelines – National and Regional Guidelines for Aggregates Provision in England 2005 – 2020 - reflect the overall fall in national demand for aggregates and an increase in use of alternatives to primary aggregates, especially recycled construction and demolition waste. The guidelines are based on outputs from an econometric model of the relationship between construction and aggregate consumption to predict future aggregate need. The main driver of aggregates demand is construction activity, although the Government has recognised that the relationship between the two appeared to weaken in the 1990s. Also there may be changes in aggregate intensity of use for each type of construction. Additionally, the problem of insufficient recycled /alternative aggregate data remains.

National Infrastructure Plan

3.3 The Government published the National Infrastructure Plan in October 2010, outlining its vision for the future of UK economic infrastructure. The Plan contains major commitments for investment in important infrastructure projects, such as road and rail improvements. A national infrastructure pipeline update was published in Autumn 2016, and provides detail on the status of all planned UK infrastructure projects. In the Plan Area the pipeline includes the Newhaven Enterprise Zone including the Port Access Road which is programmed to commence in 2018. Such projects will affect the demand for aggregates in the locality, as will others in the region.

3.4 In July 2015 the then Government published "Fixing the Foundations" a plan to boost the UK’s productivity growth. It set out the government’s long-term strategy to raise productivity by encouraging long term investment, and promoting a dynamic economy. In February 2017 the Government published its Housing White paper "Fixing our Broken Housing Market" and has since published consultation proposals "Planning for the right homes in the right places" on detailed aspects of the Housing White paper. Implementation of these strategies will have an impact on aggregate demand especially from housing growth and improvements to the transport system. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 15

Demand3

3.5 Past Sales as indicator

3.6 Using past sales data to assess demand has also been problematic in the Plan Area. Data for previous extraction has mainly been confidential and therefore, until recently, it has been unable to be published. In addition, with so few sites local sales figures are subject to large production swings and therefore trends cannot be used as a general indicator of demand. For example, at Lydd Quarry up until 2011, production took place in with no returns for East Sussex. Now extraction is all in East Sussex and the operator considers that about half of the aggregate raised is consumed in Kent. Similarly after some years of no soft sand returns, Novington sandpit started extraction in 2007. (The site is not currently active).

Substitute local demand indicators

3.7 It must be assumed that as development has taken place in East Sussex and Brighton & Hove, net demand for constructional materials must have been met by a combination of land won aggregates, marine landings, imports and recycled and secondary aggregates.

3.8 Consumption data from the British Geological Survey (BGS) indicates how much aggregate is used in the area and this can also assist in building up a picture of "local" demand (see Appendix B and Map 2 for more detail).

3.9 The national four yearly Aggregate Minerals (AM) Survey based on 2014 data was published in 2016. DCLG also published a summary "AM2014 source of primary aggregates by sub-region – percent categories" which indicates consumption by sub-region and identifies the source MPAs they are importing aggregates from.

3.10 Figures for 2009 show that the Plan Area consumed 80 000 tonnes of land - won sand and gravel, 618 000 tonnes marine sand and gravel, and 199 000 tonnes crushed rock giving a total of about 897 000 tonnes total primary aggregates. Production of recycled and secondary aggregates in 2009 could have been about 250,000 tonnes (see paragraph 4.21). The national four yearly Aggregate Minerals (AM) Survey AM2014 recently published includes updated information on consumption and imports/exports. AM2014 indicates that consumption was up in 2014 to 920 000 tonnes sand and gravel (land-won and marine) and 280 000 tonnes crushed rock giving a total of primary aggregates of 1 200 000 tonnes.

3.11 The average road delivery distances for aggregates in 2013 was 51.5km (source: MPA) although there have been examples where this distance has been exceeded and movements are not always direct. Given the economic limits on transporting aggregates by road it is likely that the East of Plan Area is provided by sharp sand and gravel from Lydd quarry, marine landings and imports; and that the Western Area is served by marine and imports. It is assumed that for soft sand the Eastern end of the Plan area is served by imports; and that the Western area has in the past been served by Novington and imports. 16 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

3Demand

3.12 In a wider context, the SEEAWP Aggregates monitoring report 2014 & 2015, indicates that consumed 19.2 mt of primary aggregate in 2014 but that sales of the regions resources were 14.3 mt - net imports as a percentage of consumption were 26%, continuing a rising trend. The largest sources of imports are crushed rock from and . In addition, 0.5 mt of sand and gravel is imported by sea from outside England and Wales. There has been a general decline in sales over the last decade and the soft sand contribution has increased. The draft AM2016 report indicates that since 20111 marine aggregate sales have become proportionately the largets source replacing land-won sand and gravel.

3.13 It may be appropriate to consider locally derived figures such as construction rates of housing and major infrastructure projects over the last decade. Between 2006/7 and 2016/17 there were some 18 826 housing completions in East Sussex and Brighton & Hove. Major infrastructure projects which have been completed in the last 10 years include; Waste Water Treatment Works, Household Waste Recycling Centre, Woodlands in vessel composting site, Newhaven Energy Recovery Facility, The Keep, Amex Stadium, , Brighton Station developments, , waste facilities, the Royal Alexandra children’s hospital, Bexhill Link Road (BHLR) and four school developments. Further details of previous housing and major developments (including the BHLR) in East Sussex and Brighton & Hove are set out in the Appendix A.

3.14 Of interest is that in 2014 approximately 192 000 tonnes of aggregate was used in the construction of the BHLR. Over 30% of this material was imported from Lydd quarry and about 18% from rail borne imports transported from Newhaven. Overall construction of the road has involved 550 000 tonnes of material with over 40% being recycled construction aggregate. More details are given in Appendix A.

3.15 Another measure of demand could be the sources of aggregate used in the plan area. The NPPG states that "for some types of aggregate (such as high quality polished stone value, concreting sand and building sand), it will be necessary to carry out a separate assessment for different types of aggregate in preparing a Local Aggregate Assessment. This is critical to ensure that the quality of aggregate is appropriate for its intended use, since not all aggregates can be used for all construction purposes". Some of this information is set out in the previous chapter "Geology and Minerals Uses". It is hoped that more details will become available through the Review of Waste and Minerals Local Plan.

Future Demand

National & Regional Guidelines for Aggregates Provision in England 2005 to 2020

3.16 The forecasting model used to calculate the national and regional guidelines utilises predicted growth in gross value added in the construction sector to extend the input data up to 2020. Between 2000 and 2011, annual consumption was East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 17

Demand3 expected to increase by about 5%. Resulting rates of construction demand were then extrapolated. The results indicated a reduced demand for primary aggregates even though a growth in construction activity was envisaged.

3.17 These predictions should be treated with caution because of the changes in the economy over the last 10 years. Since the start of the 2008 recession, the construction sector in the UK has significantly contracted. However, with the economic recovery underway, the demand for construction is starting to rise again, and significant increases in employment and output are predicted for the sector in the future. The upturn in the prosperity of the sector is bringing about a renewed focus on issues such as ‘green’ and sustainable construction practices (1).

3.18 Similar trends can be observed in the construction sector in East Sussex. Construction is an important sector for the county, which contributes around 8.4% of overall GVA in the county, and accounts for 6.2% of local employment. There are 3,390 businesses in East Sussex engaged in construction (14.8% of all businesses). There are significant planned developments in house-building as well as development of business facilities and of infrastructure in the county over the next few years, and construction employment and output are predicted to increase. Growth in the county’s construction industry is being further stimulated by initiatives such as Build East Sussex, a network led by East Sussex County Council that aims to develop the construction supply chain across the county(2). The construction industry is one of the sectors anticipated to grow fastest in terms of employment between 2013-2020 in the county.

3.19 In August 2017 the Minerals Product Association (MPA) reported that that the construction market demand for mineral products was lower in 2017 Q2 compared with the previous quarter, providing evidence of a more general slowdown in construction activity in recent months. A slowdown in overall markets activity was expected this year, given current forecasts for softer economic and construction activity in the medium term. On an annual basis, and despite the weaker performance in 2017Q2, sales volumes for the year finishing in June 2017 remained positive across all major MPA construction minerals, with asphalt up 4.8% compared to the previous year, 2.9% for aggregates volumes and 1.4% for Ready Mix Concrete. Mortar sales, the strongest market, grew by 8.4% over the period.

3.20 At the beginning of 2017 The MPA published their own consultation document "Proposed Minerals Strategy -supplying demand for the next generation".

3.21 Forecast of Demand

3.22 As indicated above, in the past a LAA for the Plan Area based on a rolling average of 10 years sales data was not been considered appropriate. Future demand rates will very much depend on the local economy’s response to growth in economic activity and how intensively primary aggregates are used. Consumption of primary aggregates was about 1,200,000 tonnes in 2014 plus a possible consumption of

1 East Sussex in Figures 2 East Sussex in Figures 18 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

3Demand

250,000 tonnes of recycled and secondary aggregates. The Review of the Waste and Minerals Local Plan seeks to establish the demand for construction aggregates in the Plan Area and evidence on demand has been requested as part of the current Call for Sites and Evidence consultation.

Other Relevant Local Information

3.23 The NPPG indicates that a LAA could utilise other relevant local information. Details on the local economy are set out in East Sussex in Figures website (for East Sussex).

3.24 The level of planned infrastructure in the area can assist in assessing local demand for aggregates. Allocations in Local Plans and Infrastructure Development Plans (IDPs) can indicate future levels of local demand. Six major areas of development requiring new or revised infrastructure provision in the next few years are identified in the Brighton & Hove IDP. In addition, there are eight strategic Development Areas set out in the City Plan where large scale redevelopment is expected over the Plan Period (up to 2030). These developments and infrastructure (which include residential units) will require a supply of aggregates in their construction. Further details of possible allocations in Brighton & Hove are set out in the Appendix A.

3.25 An assessment of IDPs covering East Sussex specifies a large range of services (including school and hospital provision, and leisure facilities) which may need constructional materials. There are also several road schemes and a number of employment allocations identified in East Sussex Local Plans. Further details are set out in the Appendix A.

3.26 Assessment of the level of housing development needed for the next 10 years or more can also help to indicate the level of demand locally for construction aggregates. At least 32,478 housing units are proposed in East Sussex from now and up to 2032. Details of possible housing allocations in Brighton & Hove are referred to above and set out in the Appendix A. It could be that given the current pressure for housing sites regionally there may be even more development forthcoming than identified in submitted/adopted plans. This could lead to a greater need for aggregates.

3.27 The Review of the Waste and Minerals Local Plan will focus in particular on the connection between future development and demand for aggregates aiming to establish accurate forecasts of materials that may be needed.

Previous Apportionment Figures for Land Won Aggregates

3.28 Land won aggregates extraction in the Plan Area has been patchy for many years. Some beach deposits were extracted in the 1980s but ceased in 1991. There was some further activity followed by a period of no operational sharp sand and East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 19

Demand3 gravel sites before extraction commenced for a few years at Lydd Quarry near Camber. The position with soft sand was similar with small extraction followed by years of inactivity.

3.29 Consequently by the time of the South East Plan, the sub regional apportionment for the Plan Area based on average sales over the previous seven years period discounting years with highest and lowest sales was 10,000 tonnes per annum.

3.30 The Partial Review of Regional Spatial Strategy for the South East Policy M3 Primary land-won aggregates and sub regional apportionment proposed alternative apportionments. The Submitted Review in March 2009 identified special cases where the methodology should be modified and it was proposed that East Sussex’s apportionment should be limited to 0.1m tonnes per annum to reflect actual availability of resources and deliverability. The Examination in Public Panel noted that the previous RPG9 Panel had identified that East Sussex had very little remaining resource and had recommended a small apportionment. The Panel felt that there was no evidence to take a different view and the Panel agreed the apportionment should be capped at 0.1m tonnes per annum. The Secretary of State’s Proposed Changes to Policy M3 endorsed this finding, noting that 0.1m tonnes per annum reflected actual availability of resources.

3.31 Whilst the South East Plan has now been abolished, Mineral Planning Authorities have been previously recommended to use the figures from the consultation by the Secretary of State on Review of South East Plan Policy M3, published in 2010 as a starting point for provision, unless the planning authorities have new or different information and a robust evidence base.

3.32 It should be noted that the NPPG refers to apportionments by the Aggregates Working Party but this has not yet been undertaken by the South East England Aggregates Working Party.

3.33 The Review of the Waste and Minerals Local Plan will consider and assess the methodology for proposing a figure for aggregates forward planning. 20 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

4Supply 4 Supply

Previous Supply Sales

Land-won sales/production

4.1 Permission for extraction of building sand at Novington sandpit (Stanton’s Farm) was granted in October 2003 and extraction started in September 2007 of a total reserve of approximately 380,000 tonnes of sand & gravel. The site is located in the South Downs National Park. Annual extraction figures over the last few years are unavailable due to confidentiality constraints. The permission was renewed by the South Downs National Park Authority early in in 2017 and at that time the planning application stated that reserves at the quarry were at 350 000 tonnes. There is no extraction of soft sand currently taking place at the site.

4.2 There are also large scale permitted reserves in the far east of the County, around Scotney Court and Wall Farm. These two permissions, originally totalling approximately 4.0 million tonnes of sand & gravel, are part of a larger permission for Lydd Quarry which straddles Kent and East Sussex. Production started within East Sussex in 2011. These reserves have been considered as long term allocations for East Sussex and Brighton & Hove.

4.3 Whilst production figures at Lydd Quarry have previously been subject to confidentiality the operator Brett has made information available to assist in the preparation of the Local Aggregate Assessment. The operator also considers that Lydd Quarry sales are split between East Sussex and Kent on an approximate 50/50 basis.

Year Sales Volume (Tonnes) 2006 300,860 2007 311,797 2008 312,118 2009 359,745 2010 359,250 2011 199,032 (1) 2012 353,371 2013 414, 348 2014 441, 987 2015 343 818 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 21

Supply4

2016 324 703

Table 1

1. Production started in East Sussex

4.4 Marine imports–throughput and sources

4.5 There are three Ports within the Plan Area. The Ports of Shoreham (partial), Newhaven and Rye accommodate various minerals wharves as shown in Table 1:

Port No. of Wharves Active in monitoring period Shoreham (Port area within 3 1 Hove) Newhaven 5 1(1) Rye 2 1

Table 2 Wharves in the Plan Area 2016

1. Whilst only one wharf (Berth 1) was in operation in 2016, another wharf has been in use for scrap metal. In addition, an application is currently under consideration by East Sussex County Council for an asphalt and concrete batching plant at North Quay in Newhaven. The applicant intends to import aggregates by sea using wharves at North Quay to supply the proposed developments. Initially Berth 5 would be used, and at a later stage imports would then take place at one of the wharves adjacent to the proposal.

4.6 Table 2 below details figures from South East Regional reporting (and other sources) for landings of marine dredged sand and gravel for Rye and Newhaven ports over the last 16 years. This year operators have kindly allowed us to make import figures public to aid reporting. 22 East (1) (2) 4 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Sussex, Supply (3) (4) Marine 346 430 350 323 302 229 202 217 205 106 155 c 78 27 0 0 8 dredged

Sand South and Gravel Downs (5) (6) Crushed 164 37 176 176 176 93 117 181 145 145 129 c n c c c 52

Rock and

Total 510 467 526 499 478 322 319 398 350 249 284 c N/a c c c 60 Brighton

Table 3 Aggregate Imports and Marine Dredged Material Landed at East Sussex Ports 2000-2016 ('000 tonnes) & Hove, 1. estimated from regional data 2. C =confidential/no return submitted Local 3. based on data from NPMP 4. Crown Estate 2012 Aggregate 5. based on data from NPMP 6. n=no data available Assessment, December 2017 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 23

Supply4

4.7 The following graph shows the figures set out in the previous table.

Figure 1 Aggregate Imports and Marine-Dredged Material (showing only data available in the public domain)

4.8 Crushed rock imports were received at Newhaven and Rye Ports during 2016. A small amount of marine sand and gravel and secondary aggregate was also received at Rye Port.

4.9 There are three wharves located at Shoreham Harbour that fall within the Brighton & Hove boundary (one active, two inactive). Historically, Shoreham Harbour data has been collected by West Sussex County Council, as the majority of the Port lies within West Sussex. The LAA is unable to publish landings figures just for the Brighton & Hove wharves due to the commercial sensitivity of releasing figures for one active wharf. However, regional information published by the Crown Estate indicate that the amount of marine dredged material imported into Shoreham Port as a whole increased between 2009 and 2011. For 2012 and 2013, the total of marine dredged primary aggregates imported at Shoreham experienced a small decrease, but in 2014, 2015 and 2016 imports of aggregates landed at the Port have steadily increased to 1 090 138, 1 173 304 and 1 254 255 tonnes respectively.

4.10 Evidence gathered during the preparation of the Waste and Minerals Plan (in 2011) indicates that over 60% of sand and gravel received on the Brighton & Hove side of Shoreham Port was used within the Plan Area. Mineral wharves located within West Sussex at Shoreham Port also serve markets in the Plan area.

4.11 Substantial deposits of sand and gravel exist on the seabed of the East England Channel (EEC) region, and to a lesser extent the the South Coast region. The EEC has 11 production licences and dredging activity in these areas began in Autumn 2006. Material from the EEC is often destined for wharves on the River Thames (in 2015 71.1% of the tonnage dredged was delivered to the Thames Estuary), but a small amount of material is landed on the South Coast. There are 14 production licences in the South Coast region. 24 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

4Supply

4.12 The amount of aggregate landed at Shoreham Harbour from the South Coast in 2015 was 1 119 773 tonnes, this being 36.7% of the total dredged from the south coast Licenced area (source:The Crown Estate). Other ports receiving imports include and Langstone (Hayling Island).

4.13 Plans of the EEC and South Coast Licence areas for 2015 are shown below (updates for 2016 are not yet available).

Figure 2 Plan of the EEC Licence areas (Source: Crown Estate) East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 25

Supply4

Figure 3 Plan of the south coast Licence areas (Source: Crown Estate)

4.14 Detailed statistics on delivery of marine dredged aggregates are set out in “The area involved – 18th annual report" by the Crown Estate and The British Marine Aggregate Producers Association (19th annual report has not yet been published). During 2015, 1.1% (0.04mt) of the tonnage dredged from the EEC region (3.65mt) was delivered to the South Coast, which includes Shoreham Port. In previous years a small amount was delivered to the ports within the EEC region but the figure for 2014 was zero, reflecting the cessation of marine imports at Newhaven which is located within the EEC region.

4.15 During the same period, 89.6% (2.74mt) of the tonnage dredged from the South Coast licences (3.05 mt total) was delivered to the South Coast, 0.5% to mainland Europe and 9.9% to the Thames Estuary. In terms of imports the South Coast region also received small amounts of marine dredged material from the EEC, Thames Estuary, East Coast, South West and Humber regions.

Imports

4.16 AM2014 data indicates that in 2014: 42 000 tonnes land-won sand and gravel, 650 000 tonnes of marine - won aggregate and 280 000 tonnes of crushed won was imported into the East Sussex and Brighton & Hove Plan area. The DCLG has recently published the summary "AM2014 source of primary aggregates by sub-region – percent categories" for 2014. This shows that since 2009 total consumption has increased to 280 000 tonnes crushed rock, and that the amounts supplied by Kent has increased to between 30 and 40 %, and the amount supplied by Somerset has 26 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

4Supply

dropped to between 20-30%. now supplies between 1-10 %, Conwy has reduced to between 1-10% and Powys supplied 1-10%. Crushed rock is transported by a mixture of sea, rail, and road. Details of wharves are provided in the paragraphs above. More details will be on obtained on modes of transporting aggregates as part of the Review of the Waste and Minerals Local Plan review.

4.17 A railhead has recently been reinstated at Newhaven. Imports of crushed rock into Newhaven commenced in 2014, initially to serve the Bexhill - Hastings Link Road construction project. Sales totals for materials imported by rail to Newhaven over the last three years are set out below. Exports of IBA are also set out for information. Notably this data shows a marked increase in rail imports of sharp sand and gravel since 2014. There are also aggregate railheads close to the Plan Areas at and Ardingly in West Sussex.

Newhaven Railhead Material 2014 Sales 2015 Sales 2016 Sales (tonnes) (tonnes) (tonnes)

Imported crushed rock from 45 852 99 579 74 602 Somerset

Imported recycled aggregate 1 550 24 505 35 658 from Brentford

Imported sharp sand and gravel 0 735 19 248

Exported Incinerator Bottom 61,283 55,897 44 753 Ash (IBA)

Table 4

Secondary/Recycled Aggregates

4.18 Previously a best estimate of recycled aggregates production in the Plan Area has been 240,000 tonnes, based on 2008/9 figures for recycled aggregates produced at construction, demolition and excavated waste (CDEW) management facilities in East Sussex and Brighton & Hove. It is hoped that an updated estimate will be provided as part of the Waste and Minerals Local Plan Review. However, recent monitoring of sites to obtain data for 2016 saw a much improved response rate compared with previous years, and although not reflecting a full coverage of facilities, results are not far off previous estimates. A plan showing the location of current recycled and secondary aggregate facilities is set out in Map 4, and a list of sites can be found in the Waste and Minerals Monitoring Report 2016/17.

4.19 In addition, it is estimated that annually up to 75 000 tonnes of secondary aggregate are produced from two main sources : Ashdown and Brickworks are thought to produce up to 14 000 tpa of brick waste, and Newhaven Energy Recovery Facility creates between 44 000 and 61 000 tpa of IBA (see table 4 above). The brick waste will either be used on site as hard core for quarry roads or in some circumstances sold as hard-core. The IBA material is exported by rail (currently East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 27

Supply4 to Brentford) where it is processed into recycled aggregate for uses including as a road construction material. Over the last three years the amount of this material rail imported back into Newhaven has grown significantly.

4.20 Overall, the the Plan Area is considered to have a capacity in the region of 743 000 tonnes for recycling Construction, Demolition and Excavation Waste (3)

Future Supply Options

Land-won

4.21 Planning permission was recently renewed at Novington sandpit to allow the extraction of sand and restoration of the site to be completed not later than October 2026. Remaining reserves at the quarry are considered to be in the region of 350 000 mt of reserves. In 2013 the conditions attached to planning permission MR/5 covering Novington sandpit were reviewed. (4)

4.22 As indicated earlier, there are large scale permitted reserves in the far east of the County related to Lydd Quarry. There are two major extant planning permissions covering Scotney Court (Area 10) and Scotney Court Extension/Wall Farm (Area 11/12). These permissions originally amounted to 3.23m tonnes of sand and gravel. Extraction commenced in Area 10 in 2011. The operator has mostly completed extraction in this area. Extraction started in Area 11 in January 2013 and is almost complete. A condition attached to the permission would require a renewal application in 2021.

4.23 The Waste and Minerals Plan, adopted in February 2013, estimated that the extraction at Scotney Court Extension/Wall Farm could last until 2026 based on the assumption of an average annual extraction rate of 270,000 tonnes. Production figures made publicly available by the operator indicate that extraction rates have been higher than expected over the last few years (see Table 1). Reserves at the end of 2016 were in the region of 2 million tonnes.

4.24 Natural England confirmed the extension of the the Special Protection Area and Ramsar designations covering Dungeness, and Rye Bay in March 2016. The designations cover or are adjacent to all the sand and gravel resource in this part of the County (see paragraph 5.9). Natural England previously raised

3 Approximate figure as at 1 April 2017 4 In 2013 the conditions attached to planning permission MR/5 (Novington sandpit) were reviewed. This led to the issuing of planning permission SDNP/13/01933/ROMP. Whilst most of the conditions attached to planning permission SDNP/13/01933/ROMP mirror those attached to planning permission LW/386/CM it is beyond the scope to the current application to relax the requirements of any of the conditions attached to planning permission LW/386/CM – other than condition 2. For this reason the SDNPA recognise that the recommended conditions pertaining to the hours of operation are not consistent with those attached to planning permission SDNP/13/01933/ROMP. Whilst the SDNPA cannot reword conditions without a change to the description of the development and re-advertisement concerning the removal of the buildings, structures, plant and machinery and the hours of operation so they are consistent with planning permission SDNP/13/01933/ROMP, the SDNPA is unlikely to enforce planning breaches against condition 10 (hours of operation) of SDNP/16/04886/CNDC if there is no breach against planning permission SDNP/13/01933/ROMP. 28 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

4Supply

concerns related to mineral extraction, and the Waste and Minerals Plan has therefore a note added, related to Areas 11 & 12 extraction rate, that the estimate is subject to a further Habitat Regulations Assessment. The next opportunity for a hydrological assessment is the Review of Consents (RoC) under Regulation 63 of the Conservation of Habitats and Species Regulations 2010. The RoC process is now underway.

4.25 As mentioned earlier in this document the Authorities will be considering whether any additional resources are required to meet demand for land-won aggregates through the Review of the Waste and Minerals Local Plan.

4.26 Due to its dormant status and the significant development constraints affecting the site, it is considered inappropriate to include the remaining reserves at Water as part of the future land-won supply fro the Plan area.

4.27 Marine

4.28 The Marine Management Organisation (MMO) reports(5) that the South Marine Plan Areas (covering the East English Channel and South Coast region) are currently the second busiest area in England for marine aggregate extraction in terms of tonnage dredged, licensed area, and area dredged. Over the past 20 years the area permitted for dredging has changed. Many of the historic licence areas have reduced in size, and over the same time new production licence areas have been awarded. The MMO considers that the following are potential core issues for the the marine aggregate industry in the South Marine Plan Area:

Determination of the 15 years marine licence applications for dredging within the South Marine Plan will mean that the marine plans, with their 20-years focus, will have an influence on the marine aggregate industry over a 30-years period

The current dredging fleet is aged and the South Plans could influence the marine aggregate industry’s next cycle of capital investment, estimated to be £1 billion

With the effects of climate change posed by sea level rise, the role of the aggregates industry in supplying marine sand and gravel for coast protection and amenity purposes will become increasingly important over the lifetime of the marine plans

requirements for large volumes of construction aggregate to support local major infrastructure projects taking place in the marine plan area (port developments, offshore wind farms) can be expected to increase over the marine plan period, and marine sand and gravel is expected to play a role in meeting this need

5 South Inshore and South Offshore Marine Plan Areas, South Plan Analytical Report (SPAR) 2014 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 29

Supply4

4.29 The draft South Marine Plan was published by the MMO for consultation in 2016, and the consultation period closed at the beginning of 2017.

4.30 The adopted Waste and Minerals Plan safeguards capacity for landing, processing and handling minerals at Shoreham, Newhaven and Rye Ports and sets out details of the safeguarded wharf areas. Alternative use proposals would need to demonstrate no net loss of capacity and the mineral planning authorities expect to be consulted on any proposals for non minerals development.

4.31 There are currently several strategies being put forward by other organisations which concern the port areas at Shoreham, Rye and Newhaven. The Authorities will seek to ensure safeguarding of wharf capacity as part of any development at the ports. Proposals for other uses at ports would need to demonstrate that sufficient alternative mineral wharf capacity (tonnage) is deliverable and available to meet needs in the Plan Area for the plan period before the Authorities would accede to alternative development of the site. Proposals for new residential, business or amenity development in proximity to aggregate wharves should be assessed to ensure the impact of existing operations is fully addressed. The safeguarding arrangements would apply to all existing permitted, planned and potential sites regardless of whether they are currently in use.

4.32 Shoreham Port is partly within West Sussex, so landings at wharves in the West Sussex part may also help meet demand in the western part of the Plan Area. On that basis provision of equivalent capacity (tonnage) of minerals wharfage within either part of Shoreham Port may be acceptable subject to similar safeguarding by West Sussex County Council (WSCC) as Minerals Planning Authority.

4.33 Council, Brighton & Hove City Council, West Sussex County Council (WSCC) and Shoreham Port Authority are partners in the preparation of the Shoreham Harbour Joint Area Action Plan (JAAP) which sets out a 15 – 20 years plan to guide the regeneration of Shoreham Harbour. The draft JAAP outlines proposals for housing, employment and economy and environmental improvements. In order to achieve this, some consolidation of operations and redevelopment of mineral wharves (particularly in West Sussex) is proposed. Ferry Wharf (a vacant mineral wharf) on the Brighton & Hove side of the port is proposed for redevelopment. Publication of a submission draft JAAP is anticipated this Autumn 2017.

4.34 It is recognised that the provision and safeguarding of minerals wharfage is a key issue if the JAAP aims are to be achieved. To this end the JAAP partners, together with South Downs National Park Authority, and ESCC have signed a Statement of Common Ground (SOCG). The purpose of the SOCG is to underpin effective cooperation and collaboration between the partners in addressing strategic cross-boundary issues as they relate to planning for minerals infrastructure and safeguarding in Shoreham Harbour. The SoCG was updated in July 2016 to reflect new data and progress in Local Plan preparation. Policy SP 9 in the WMSP will be the mechanism for assessing the impact on wharf capacity at the Brighton & Hove section of the Port from any development proposals in this area. 30 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

4Supply

4.35 It is hoped that future joint working by authorities will address the safeguarding issues. In preparation for publishing their draft Minerals Local Plan WSCC published Background Papers for consultation which include consideration of future wharf provision at the Port. The West Sussex joint MLP is currently at Examination stage (September 2017). The Plan includes proposals for minerals wharfage at Shoreham and Littlehampton in line with the SoCG.

4.36 Newhaven Port Authority published a Port Masterplan in January 2012. This plan expects to see aggregate imports to continue at North Quay over the short to medium term, and will encourage use of the wharves for aggregates. However, marine dredged aggregate imports ceased at the Port in May 2013 due to the closure of import facilities at Newhaven. Imports are therefore now restricted to crushed rock from quarries in Cornwall, Wales, Ireland and France(6). Enterprise Zone status commenced in April 2017 on an area of Newhaven covering 8 strategic sites (see Appendix A for details).

4.37 An application is currently under consideration by East Sussex County Council for an asphalt and concrete batching plant at North Quay in Newhaven. The applicant intends to import aggregates by sea using berths at North Quay to supply the proposed developments.

4.38 There is no information to suggest that imports at Rye Port could not continue.

Imports

4.39 Imports of marine sand and gravel are also likely to continue as there is likely to be sufficient licenced capacity in the English Channel (see paragraphs above). Providing safeguarding of wharves is maintained at current capacity, supplies should still be able to reach the Plan Area market.

4.40 It is understood that the crushed rock capacity at quarries in Somerset and Conwy have sufficient permitted reserves at the quarries to ensure a steady and continual supply into the Plan Area. The DCLG summary report identifies 20-30% of imports consumed in the Plan Area in 2014 were from Cornwall. Future monitoring will establish whether this new source of material turns out to be a long term supply.

Recycled / Secondary

4.41 There is no current evidence to suggest that the existing capacity for producing recycled and secondary aggregates will not be maintained. The amount of incinerator bottom ash arising from the Newhaven ERF is considered likely to remain constant, although technically it cannot be counted as a secondary aggregate until it has been processed, and this does not occur in the Plan Area. However, in the last three years processed material in the form of recycled aggregate was rail imported back into the Plan Area at Newhaven. It is assumed therefore that

6 Newhaven Port Authority East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 31

Supply4 facilities in the Plan Area will continue to contribute to aggregates supply in the area. The locations of recycled and secondary aggregate facilities in East Sussex and Brighton & Hove are set out in Map 4 at the end of this document.

4.42 The Authorities' survey of recycled aggregates sites in 2017 (for the AM2016 survey) resulted in a better coverage and response rate this year, which hopefully will contribute to improved data in the future. In addition, SEEAWP have been investigating alternative methods of calculating recycled aggregates (with the assistance of the South East Waste Planning Advisory Group), and this may assist in providing better data.

4.43 In 2014 the MMO published a report on the "Use of beneficial dredged materials in the South Inshore and South Offshore Marine Plan Areas". This looks at the existing and potential uses of dredged materials arising from capital or maintenance dredging for coastal defence, beach replenishment or habitat creation. Up to 2 million tonnes of dredge material could be produced annually from maintenance dredging. This is likely to comprise silts and clay but also could be some sand and gravel. A further 31 million tonnes could be produced from capital dredging over the next 10 years. Some projects have already taken place using these materials and further use is planned. The report states that there is scope for further beneficial use of materials provided that they are suitably matched and that the re-use logistics can be agreed. This source of alternative aggregates may therefore assist in meeting the need for aggregates in the Plan area in the next decade. 32 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

5Environmental constraints 5 Environmental constraints

The Environment of the Plan Area

Land-won

5.1 Large parts of the Plan Area are subject to environmental constraints. Two thirds of the area is covered the South Downs National Park (SDNP) and the High Area of Outstanding Natural Beauty together, and other tracts of land are also designated as being of international and national environmental importance.

5.2 A number of areas are designated for wildlife conservation. These include two Special Areas of Conservation (SACs) and five Special Protection Areas (SPAs) and two large Ramsar sites at Levels, and near Rye. There are four National Nature Reserves and 25 Local Nature Reserves. National designations include 64 Sites of Special Scientific Interest (SSSIs)(7). There are two Regionally Important Geological sites and numerous Sites of Nature Conservation Importance (SNCIs). One sixth of the area of Brighton & Hove is covered by nature conservation designations. These areas need to be protected in order to maintain the rich and varied landscape character and biodiversity within the Plan Area.

5.3 The South Downs are formed by a line of hills and vales extending along the coast westwards from . It is a unique, open, rolling landscape dissected by major river valleys cut by the Ouse and Cuckmere. Whilst now no longer active, chalk quarrying was a long established industry in the area, and has had a noticeable impact on the landscape, especially along the scarp slope and around . To the north of the chalk are the Greensand beds with the Folkestone Formation extending north west from Lewes in East Sussex, across West Sussex and into Hampshire. The area within East Sussex was previously outside the Sussex Downs AONB but it is now located within the South Downs National Park.

5.4 The High Weald AONB is a landscape of rolling hills, scattered farmsteads, small woodlands, irregular-shaped fields, open heaths and ancient routeways. It also includes the . The High Weald covers much of the northern, central and eastern parts of the Plan area. It is a faulted structure comprising clays and sandstones (collectively known as the Hastings Beds). This varied and extensively eroded geology has produced an attractive and sensitive landscape, most of which is within the High Weald Area of Outstanding Natural Beauty.

5.5 The Low Weald is a gently undulating clay vale which separates the High Weald from the Chalk Downs to the south.

7 These are split into 391 separate units East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 33

Environmental constraints5

5.6 The Coastal Marshes are located between Eastbourne and Bexhill, and in the Rye Bay/Camber area either side of the Rother estuary. Inundated by the sea in recent geological times, these areas comprise large flat sheets of alluvium, extending inland over the and Romney Marsh.

Environmental Constraints and minerals working

5.7 The Plan Area is therefore heavily affected by environmental constraints. Minerals can only be dug where they naturally occur, and given the exploitation that has already taken place, the very few places in the county where resources occur are constrained by environmental factors. Opportunities for new aggregate production areas will therefore be very challenging.

5.8 Even the current sites for extraction have had further recent environmental constraints emerge. Novington sand pit (Stanton's Farm) which has extracted from a limited exposure of the Folkestone Beds north-west of Lewes was not previously in the AONB, and is now located in the SDNP.

5.9 The working area at Lydd Quarry is covered by an SSSI (Dungeness, Romney Marsh and Rye Bay). Natural England confirmed the extension of the the Special Protection Area and Ramsar designations covering Dungeness, Romney Marsh and Rye Bay in March 2016. The designations cover or are adjacent to all the sand and gravel resource in this part of the County. The forthcoming Review of Consents will have to establish whether any of the Lydd Quarry development already permitted, would have a significant effect on the European site in view of the site’s conservation objectives.

5.10 The environmental impact of marine dredging is controlled and monitored by the Licensing system administered by the MMO. Effects of secondary aggregate production would be regulated by planning and permitting legislation and controls. 34 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

6Balance 6 Balance

Balance between Supply and Demand

6.1 The adopted Waste and Minerals Local Plan’s approach to minerals is to make provision for a steady supply in accordance with National Policy, and to allow primary production where it is demonstrated the need cannot be met by sources of alternative materials and that there is evidence of viable resource.

6.2 The evidence base for the Waste and Minerals Plan examined the particular circumstances related to aggregates. The Plan Area needs a mixture of land won production, marine landings, imports and recycled & secondary aggregates. The Plan Area already has a significant reliance on the contribution from marine sources. This section looks at the balance between supply and demand across all sources. However detailed analysis and possible changes to patterns of supply and demand will be considered as part of the Review of the Waste and Minerals Local Plan.

6.3 Regionally, South east England consumed more primary aggregate in 2014 than sales of the regions resources in the same period. Net imports as a percentage of consumption were 26%, continuing a rising trend. The largest sources of imports are crushed rock from Somerset and Leicestershire. In addition, 0.5 mt of sand and gravel is imported by sea from outside England and Wales. There has been a general decline in sales over the last decade and the soft sand contribution has increased.

Land-won

6.4 As mentioned in the Introduction, the adopted joint East Sussex, South Downs and Brighton & Hove Waste and Minerals Local Plan (WMLP) seeks to maintain provision for the production of land-won aggregates at a rate of 0.10 mtpa throughout the plan period, and to maintain a landbank of at least 7 years of planning permissions. The WMLP considered that existing planning permissions provided this requirement up to 2026 and that the landbank would be more than met by current permissions.

6.5 In terms of future demand, past LAAs established that the forecast of primary land won aggregate demand for all the Plan Area would not be based on sales data. As a substitute, the Apportionment figure in the Adopted WMLP of 0.1m tonnes p.a was used as the principal indicator of demand. Previous LAAs also established that in actual terms, the 10 years sales figures included confidential information but in total was about 1.5 million tonnes.

6.6 The landbank for the Plan Area has been calculated in the past as the full resource available at Stanton's Farm plus the reserve from the permitted sites at Lydd Quarry within the boundary of East Sussex divided by 0.1mtpa. Applying this method gives a landbank figure at the end of 2016 of 23 years. However, the use of 0.1mtpa as the principal indicator of demand, and the method of calculating East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 35

Balance6 the landbank in future, will be re-examined as part of the Review of Waste and Minerals Local Plan. As such the landbank for 2016 should only be read as a nominal figure and not as an actual measure of supply in the Plan area. It should also be noted that the recent renewal of permission indicated that reserve at Novington is now 350 000 tonnes.

6.7 Along with other mineral planning authorities in the South East, the authorities have recently signed a SOCG on soft sand which aims to collaboratively address supply issues facing an important mineral used by the construction industry. Amongst various actions identified in the SoCG one is for authorities to safeguard the entire soft sand resource in their Mineral Local Plans (MLPs) from surface development that would otherwise sterilise the mineral, and to include policies for the prior extraction of the mineral. The measures set out in the SoCG do not conflict with existing policies and any additional requirements will be examined as part of the Review of the Waste and Minerals Local Plan.

Marine Sources

6.8 As can be seen from paragraph 4.9, substantial marine aggregates reserves exists along the South Coast. The picture here is that there is more than adequate supply and that there is a potential resource that could meet additional demand if land won sources were to be further depleted in the South East.

6.9 The principal constraint on the level of marine landings during the Plan period is therefore not considered to be the level of marine reserves, but the security of port access (loss of wharves to other uses), channel and berth restrictions, vessel availability and investment in modern wharf infrastructure. The British Marine Aggregate Producers Association (BMAPA) maintain that there is a long term future for smaller vessels to import to smaller wharves and local operators have indicated that this is the case in East Sussex.

6.10 The importation of crushed rock from the UK or further afield is limited by wharf capacity and market forces. As there is no availability of this material from within the Plan Area, landings directly reflect demand. Crushed rock can be landed to non-specialist wharves, improving flexibility within port areas.(8)

6.11 According to the Port Authorities at Shoreham, Newhaven and Rye, sufficient wharf capacity apparently remains in the Plan Area to allow significant landings to continue for the foreseeable future. As spare capacity exists at the present time for marine and crushed rock landings (due to the inactive wharves at all Ports in the Plan area - see Table 1), these established operations provide flexibility to deliver additional supplies should they be required to meet demand in peak years.

6.12 However, in order to maintain potential wharf capacity for the future it is essential that adequate safeguarding measures are in place to enable the authorities to respond to threats of redevelopment of wharves from alternative uses.

8 As the method of landing crushed rock is simpler than landing marine aggregates there is less attraction to move to larger vessels to reduce costs and crushed rock does not require specialist handing equipment. 36 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

6Balance

Comprehensive safeguarding policy will be an important tool in achieving strategic provision of wharf capacity within the various emerging plans for ports in the plan area (see Supply chapter).

Imports

6.13 Again, with regards to marine imports, safeguarding wharves is key to the future security of landings. It is also crucial that rail import facilities are protected from redevelopment. Waste and Minerals Local Plan policy seeks to safeguard existing, planned and potential railheads and minerals wharves, and to monitor the need for these facilities. Policies to safeguard wharves and railheads, concrete batching, coated materials manufacture and other concrete products facilities are set out in the East Sussex, South Downs and Brighton & Hove Waste and Minerals Sites Plan. Regional discussion will be required to secure rail and wharf facilities which contribute provision to the Plan Area. Positive dialogue with adjoining and more distant mineral planning authorities will also be needed to check and maintain security of supply of aggregates, particularly crushed rock. This should be enabled through good practice, aggregate working party arrangements and Duty to Cooperate requirements.

Recycled / Secondary

6.14 Secondary aggregates provide an alternative to primary aggregates, and subject to technological advancement, there is potential scope to substitute more recycled aggregates. Economic instruments such as the Landfill Tax have had a considerable impact on the level of material available, forcing previously landfilled CDEW waste to be processed into secondary aggregate.

6.15 There are moves to increase utilisation of alternative sources with a consequential increased contribution to total demand. However, the availability and utilisation rate remains unpredictable and substitution is not always possible. Primary resources will be required to a significant extent for the foreseeable future.

6.16 A diagrammatic plan summarising the origin of locally won and produced aggregates, as well as consumption and the nature of imports into the Plan area, is included as Map 2 based on 2014 data. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 37

Conclusions7 7 Conclusions

7.1 The Authorities are undertaking a review of the Waste and Minerals Local Plan and this will focus in particular on aggregate policies, and therefore on different supply options and ways of meeting demand for construction demand. The Call for Sites and Evidence consultation finishes on 20 November 2017, and adoption of this LAA is planned before formal consideration of any responses received on the consultation. It would not therefore be appropriate to pre-empt possible changes in aggregate supply in this document. Discussion of future demand and supply scenarios is therefore not included. These details will be assessed at the next stage of the Local Plan Review process in 2018.

7.2 This LAA has therefore examined the latest information and data available on aggregates in the context of the considerations raised by SEEAWP and the MPA/POS guidance. The key conclusions are:

With regards to land-won supply there has been a small decrease in production over the last two years at Lydd Quarry. However the rate of production is still above the anticipated rate in the current planning application.

Along with other mineral planning authorities in the South East, the authorities have signed a SOCG on soft sand which aims to collaboratively address supply issues facing an important mineral used by the construction industry. The requirements of the SoCG will be examined as part of the Review of the Waste and Minerals Local Plan.

There is small but steady supply of marine imports at Newhaven Port, and Rye.

Since 2014 the the Newhaven railhead has received a steady supply of imports of crushed rock, recycled aggregate and increasing amounts of sand and gravel.

Imports at Shoreham Port have steadily increased, and material from South Coast Licenses forms the majority of the aggregate supply. With the recent demise of marine dredged aggregate imports at Newhaven, East Sussex and Brighton & Hove is very dependant on imports at Shoreham and the marine dredging South Coast licences.

The revised Statement of Common Ground on safeguarding minerals wharfage at Shoreham Port sets the framework for positive co-operation between the relevant authorities. This should strengthen aims to protect wharf capacity from redevelopment and to support and increase marine imports. 38 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

7Conclusions

The East Sussex, South Downs and Brighton & Hove Waste and Minerals Sites Plan was adopted in February 2017, and emphasises the importance of safeguarding wharves and railheads, and other minerals infrastructure for aggregate imports.

The Authorities' survey of recycled aggregates sites in 2017 (for the AM2016 survey) resulted in an improved coverage and response rate this year, which hopefully will contribute to improved data in the future.

7.3 The Authorities consider that where appropriate they have taken into account the requirements for preparing the LAA set by national advice, SEEAWP and the MPA/POS guidance. There are certain areas where more work is required, such as justification of a LAA provision rate, and analysis of further resource opportunities and limitations on local land-won supply. These matters will be assessed in detail as part of the Review of the Waste and Minerals Local Plan and reported on in full next year. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 39

Past and Future DevelopmentA Appendix A: Past and Future Development

Past Development

East Sussex

Between 2006/7 and 2016/17 there were 13 691 housing completions in East Sussex.

Over the last decade the following major infrastructure projects have been completed within the county: Peacehaven Waste Water Treatment Works, Maresfield Household Waste Recycling Centre, Woodlands in vessel composting site, Newhaven Energy Recovery Facility, Bexhill Hastings Link Road (BHLR), four school developments, and North East Bexhill Gateway Road.

Bexhill Hastings Link Road (BHLR)

Construction of the the BHLR started in 2013 and opened at the end of 2015 and is known as the Combe Valley Way. The BHLR used both recycled aggregate and primary aggregate in its construction. Figures are available for the period September 2013 – March 2016 which indicate the sources of aggregate material used in the road construction. The total amount of aggregate used in construction is approximately 550 000 tonnes. Since construction began in 2013 over 40% of the material has been recycled construction aggregate. The total amount of aggregates used per year (in tonnes) is as follows:

Year Tonnes

2013 41 761

2014 192 407

2015 317 148

2016 96 (recycled material for the Greenway)

TOTAL 551 413

Table 1 Amount of aggregates used in construction of the BHLR

The early stages of road construction in 2013 involved formation of piling platforms, haul roads and compounds using aggregates from East Sussex and Kent. In the later stages of construction during 2014 and 2015, primary aggregate was sourced from Lydd Quarry in East Sussex, and Denge and Blaise Farm quarries in Kent (49 km and 58km from road site respectively). From 2014 significant amounts of crushed limestone were also imported from Day Aggregates. Before reaching the BHLR site 40 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

APast and Future Development

by road, this material was imported to the railhead at Newhaven. It is believed that the majority of the limestone originated from Somerset. During 2014 Day Aggregates also rail imported some recycled material from their processing facility at Brentford for use in the BHLR.

In 2014 approximately 192 000 tonnes of aggregate was used in the construction of the BHLR. Over 30% of this material was imported from Lydd quarry and about 18% from rail borne imports transported from Newhaven.

In 2015 317 148 tonnes was used in construction - 60% was imported from Blaise Quarry in Kent, 5% from the railhead at Newhaven, and 7.5% from Lydd Quarry. These percentages largely reflect the situation over the the whole construction period.

Brighton & Hove

Between 2006 and 2016 there were 5135 housing completions in Brighton & Hove.

Major infrastructure projects that have taken place in Brighton & Hove over the last decade include The Keep, , Brighton Station developments, Amex House, Hollingdean waste facilities and the Royal Alex children’s hospital.

Future development

East Sussex including the area covered by the South Downs National Park

Based on an assessment of Local Plans (at various stages up to adoption), there are a number of allocations for housing and employment in the East Sussex area which could involve construction aggregates in their development. The various allocations cover a period longer than 10 years (up to 2032). Overall, at least 32,478 dwellings and 331,350 square metres of employment floorspace are proposed.

A review of Infrastructure Development Plans in the county highlights a number of projects in the short (the next 5 years) and medium (5-10 years) term. These include increased educational, library, health treatment, education, community centres, and sports and leisure provision. Also identified are coast and flood protection, waste water treatment and sewerage improvements. Whilst the precise aggregate requirements for these developments are currently unknown, some sand and gravel material is likely to needed during constructional phases.

The Rampion Windfarm as well as new operation and maintenance infrastructure at East Quay, Newhaven Port are also proposed. Construction of the Rampion operations and maintenance infrastructure at East quay in Newhaven started during the Summer 2017. Preliminary works, including driving pre-cast concrete piles on-site in readiness for the foundations, have concluded and the majority of the construction works due to be completed by the end of the year. Commissioning begins this Autumn and power generation is anticipated in 2018. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 41

Past and Future DevelopmentA

Some strategic road improvements in the county are also planned. Strategic Economic Plans produced for the Local Economic Partnerships covering the county also identify a number of transport related schemes, including Phase 2 of the Newhaven Port Access Road planned to commence in Spring 2018. The final design of this road has not yet been finalised but is likely to require materials for embankment construction.

Enterprise Zone (EZ) status commenced in April 2017 on an area of Newhaven covering 8 strategic sites. It is estimated that EZ status will lead to the creation of around 55,000m² of new commercial floor space, refurbish a further 15,000m² of commercial floor space and create and sustain around 2,000 jobs over the Zone’s 25-year lifespan. Alongside the other Newhaven-focused regeneration activity, the Enterprise Zone has the potential to have a significant positive impact on local residents, businesses and economic growth. There are likely to be aggregate demand requirements arising from such development.

A single carriageway road between the A21 Road North and Queensway (Queensway Gateway Road) will facilitate access to employment sites in north Hastings. Construction has commenced and the scheme is programmed for completion in 2018.

The North Bexhill Access Road (a 2.4km single carriageway road link between the A269 Road and the Bexhill Hastings Link Road) will unlock housing and employment in the North Bexhill area. Construction commenced in August 2016 and will be completed in 2018.

Following the publication of ’s (HE) Roads Investment Strategy in March 2015, Highways England consulted on proposals for a package of smaller scale improvements for the A27 east of Lewes part of the strategic road network in late 2016. HE made their preferred route announcement on the package of smaller scale improvements in September 2016 which comprises:

Improvement to the A27/A2270 signalised junction and two lanes in both directions to Cophall Roundabout as well as signalisation of Gainborough Lane junction Ghost Island junction improvement and cross facilities at Wilmington to improve safety Enlarged roundabout with two lane entry on both the east and westbound A27 arms at Drusillas to improve capacity Shared use path between and .

HE are currently programming construction commencing in 2020. These improvements will seek to address the short term capacity issues on the A27 corridor. However the A27 Reference Group, successfully lobbied for £3m of funding to help develop a strategic outline business case for offline dual carriageway option which will be required to support the housing and employment growth in the area 42 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

APast and Future Development

in the medium and long term. HE have commissioned a consultant to undertake this work and it is expected that the final report will be completed by the end of March 2018.

A.1 The SDNPA has set out within its Regulation 19 Draft Local Plan (September 2017) a modest level of growth in that part of the National Park within East Sussex. This includes the following proposed allocation sites, in addition to North Street Quarter, for residential and employment development:-

Alfriston: up to 18 dwellings (across two allocation sites) Kingston-near-Lewes: up to 12 dwellings (one allocation site) Lewes: up to 240 dwellings (one strategic allocation site) Pyecombe: up to 8 dwellings (one allocation site)

A.2 As such, up to 278 dwellings are proposed to be allocation in the emerging SDNPA Local Plan. In addition the Malling Brooks employment site in Lewes providing up to 7,040 sq/m of Class B1, B2 and B8 use is also proposed to be allocated in the plan.

A.3 Brighton & Hove

A number of major areas of development requiring a significant supply of aggregates in their construction are expected to come forward in Brighton & Hove in the forthcoming years. These include:

University of Sussex - Redevelopment of various buildings to provide new teaching and residential accommodation. Phased delivery from now until 2020; Preston Barracks – major mixed use redevelopment scheme; Circus Street – major mixed use redevelopment scheme; A new King Alfred Leisure Centre and major residential development Royal Sussex County Hospital - Expansion of health facilities at main hospital site Eastern Road with 74,000m2 net floorspace. Brighton Waterfront project – new conference centre at Black Rock, and major redevelopment of the existing and neighbouring cinema sites.

In addition there are eight strategic Development Areas set out in the submission City Plan where large scale redevelopment is expected over the Plan Period (up to 2030). A summary of proposals for each is as follows:

DA1 Brighton Centre and Churchill Square area: Extension of Churchill Square to provide 20,000m2 retail floorspace. New Brighton Centre (25,000m2 conference centre); DA2 , Gas works and Black rock: 1,940 residential units, 5000m2 retail, 2000m2 B1 floorspace, 10500m2 leisure and recreation floorspace, health facility, primary school; DA3 Lewes Road: 810 residential units, 15600m2 employment floorspace, 16000m2 business school, 1300 student rooms, 5,000m2 B1 floorspace; East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 43

Past and Future DevelopmentA

DA4 /London Road: 20,000m2 office floorspace, , 1185 residential units, 300 bed space student housing; DA5 Eastern Road and Edward Street area: 470 residential units, Hospital rebuild (see above), 400 bed student accommodation, 3,800m2 education floorspace, GP surgery, community building; DA6 Hove Station area: 630 residential units, retention or replacement of 13,000m2 employment floorspace; DA7 Toads Hole Valley: 700 residential units, 25,000m2 employment floorspace, new secondary school; DA8 Shoreham Harbour: 400 residential units; 7500 m2 employment floorspace (within B&H part of the Harbour). 44 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

BImports into plan area Appendix B: Imports into plan area

NOTE

B.1 The data in this Appendix is based on that provided by BGS as a summary from AM2014 on consumption by sub-region of crushed rock and sand and gravel. Consumption of both sand and gravel and crushed rock has increased since 2009. Information currently available is not as detailed as that from the 2009 collation and does not include data on transport modes. Where applicable the 2009 import percentage figure is shown is brackets after that for 2014 to indicate any change that has occurred. Further breakdown of figures in the AM 2014 survey may become available, and these will be incorporated in next years LAA where relevant.

Data

B.2 Of the total 920 000 tonnes sand and gravel (land-won and marine) consumed in East Sussex and Brighton & Hove;

20 -30% (16%) was supplied from within East Sussex. 60-70% (70%) was supplied from West Sussex. About 1-10 (10) % was supplied from Kent and each supplied between 1-10 (5)%. East supplied 1-10% , South Downs, and Central each supplied less than 1%.

B.3 Of the total 280 000 tonnes crushed rock consumed in East Sussex and Brighton & Hove:

Kent supplied between -30 and 40 % Somerset supplied between 20-30 % (60-65%), Cornwall supplied between 1-10 % Conwy supplied between 1-10% (20-25%) Powys supplied 1-10% 20 - 30% of crushed rock is supplied from outside England and Wales Leicestershire, the Peak District National Park and each supplied less than 1%. East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 45

LAA RequirementsC Appendix C: LAA Requirements

Minerals Product Association and Planning Officers Society Guidance

C.1 A revised version of the Practice Guidance on the production and use of Local Aggregates Assessment was prepared in May 2017 by the Minerals Product Association and Planning Officers Society. This guidance provides a checklist for consideration by mineral planning authorities and aggregate working parties in assessing the adequacy of local aggregate assessments as follows:

C.2 CHECKLIST

C.3 1. Is the draft LAA comprehensive in assessing all supply options:

C.4 a) Recycled and secondary aggregates? b) Marine dredged aggregate? c) Imports and exports by sea, rail and road? d) Land-won resources of rock and sand and gravel?

C.5 2. Are the assessments realistic and supported by evidence:

C.6 a) Has the mpa used sales returns from and capacity at sites with extant permission? b) Does it identify reasons for significant changes in sales over last 10 years? Does ‘other relevant local information’ justify further investigation or deviation from use of 10 year average of sales? c) Has the mpa used AM data and Crown Estate landing figures and data on licensed reserves? d) Is there reliable evidence on the maintenance of supply, and is there adequate capacity at wharves and rail depots to handle the LAA figure for existing and potential landings and imports? e) Has the mpa considered a ten year sales average? If it is proposing an alternative figure to this, is there adequate justification regarding other relevant local information? f) Is it necessary to carry out a separate assessment and present information for different types of sand and gravel aggregate ? g) Are the assumed and planned contributions from the different sources feasible? h) Is the estimate for the availability and use of recycled and secondary aggregate a rigorous assessment?

C.7 3. Does the draft LAA suitably assess the changes likely to impact on supply and demand over the plan period – has it:

C.8 a) Given consideration of the planned levels of development and infrastructure, including relevant major construction projects outside the mpa area and how these compare to previous years? b) Considered the constraints on resources, production and capacity to supply? c) Taken into account economic and environmental considerations? d) Assessed the implications of such considerations in other authority areas that supply the mineral planning authority? e) Identified a shortage of supply (based on forecast of demand, reserves and capacity)? If so, has this been suitably addressed? 46 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017

CLAA Requirements

C.9 In preparing the LAA has the mpa consulted with (to contribute to meeting the Duty to Cooperate, especially if the LAA is being used as evidence to support preparation of an MLP):

C.10 a) Other relevant mpas including those from/to whom supplies are imported/exported? b) The aggregate industry? c) Environmental bodies? d) Other organisations such as Local Enterprise Partnerships?

C.11 5. What are the implications of the draft LAA figures for the AWP area:

C.12 a) On planned provision in the AWP area? b) On the overall contribution of the AWP to national & local supply, compared with the current Guidelines (or the London Plan)?

South East England Aggregates Working Party (SEEAWP) recommendations

C.13 In 2016 SEEAWP requested that mineral planning authorities take into account the following matters in their 2017 LAA submissions:

LAAs should complete the MPA/POS LAA Guidance checklist and include it as an appendix in their LAAs (see above) Include average sales (10 and 3-year) data when single year reporting is not allowed. The smaller mineral planning authorities consider joint LAAs to overcome data reporting limitations Continue submitting a completed ‘Key Facts’ table as part of the Executive Summary or Appendix. Provide a full analysis of mineral plan allocations and further resource opportunities/limitations on local land-won supply. Justify the LAA (Provision) Rate fully. Identify threatened aggregate supply infrastructure assess implications for supply. Examine the implications of depending on increasing intra-regional flows to meet aggregate needs especially in the context of ‘duty to cooperate’. Assess recycled and secondary aggregate data under a common methodology. Assess the role of local crushed rock in the South East Incorporate ‘stress tests’ along with the impacts of major projects on demand for aggregates and how reserves and infrastructure could cope. Provide more prominence to soft sand supply issues. Take note of the points raised by the preliminary report of the Inspector for Oxfordshire Minerals and Waste Local Plan Examination East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 47

LAA RequirementsC

Draft SEEAWP AM2016 Report

C.14 In August 2017 SEEAWP published a draft South East Aggregates Monitoring Report 2016 using information from the 2016 Aggregates Monitoring Survey. This report sets out regional issues for mpas to consider in preparing their LAAs as follows:

The relative decline in land won sand and gravel extraction in comparison with other sources, and in particular marine aggregates and rock imports. What are the planning implications if this trend continues? There is an overall land bank of sand and gravel in excess of seven years that will quickly be eroded without new permissions. Moreover, if the sand and gravel quarries sales increase the land bank would diminish even faster. Are the emerging reserves - current applications and allocations etc. identified in mineral local plans - sufficient to meet land bank depletion and increased demand for aggregate? Is the surplus capacity in aggregate infrastructure – wharves and rail depots – sufficient to meet an increase in demand particularly if there are failures in the sand and gravel land bank. Moreover, are the current safeguarding arrangements adequate and is there provision for additional capacity? Because of data difficulties the picture on the supply of recycled and secondary aggregates is unclear. Are there any actions required to address this?

C.15 In the light of the above the mpas in their LAA’s should consider these regional issues, along with appropriate local ones in their respective LAAs. 48 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 Map 1: Geological Plan including locations of aggregate wharves and railheads, and existing aggregate sites Map 1: Geological Plan including locations of aggregate wharves and railheads, and existing aggregate sites

50 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 Map 2: Origin of aggregate imported, produced and consumed in East Sussex and Brighton & Hove during 2014 Map 2: Origin of aggregate imported, produced and consumed in East Sussex and Brighton & Hove during 2014

52 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 Map 3: Sand and gravel resources in the East English Channel and Thames Estuary (Source: Crown Estate) Map 3: Sand and gravel resources in the East English Channel and Thames Estuary (Source: Crown Estate) the Map East Estuary 3: East Sand Sussex, English South Downs (Source: and and Channel Brighton gravel & Hove, Local Crown Aggregate resources and Assessment, Thames Estate) December in

Sand and gravel resources in the East English Channel and Thames Estuary (Source: Crown Estate) 2017 53 54 East Sussex, South Downs and Brighton & Hove, Local Aggregate Assessment, December 2017 Map 4: Recycled and secondary aggregates sites 2016/17 Map 4: Recycled and secondary aggregates sites 2016/17

East Sussex County Council St Anne's Crescent Lewes BN7 1UE Phone: 0345 60 80 190 Website: eastsussex.gov.uk

South Downs National Park Authority South Downs Centre North Street Midhurst GU29 9DH Phone: 0300 30 31 053 Website: southdowns.gov.uk

Brighton & Hove City Council Norton Road Hove BN3 2BQ Phone: 0127 32 92 505 Website: brighton-hove.gov.uk

December 2017