Environmental Monitoring Report

Bi-annual Report January-June 2013

UZB: Water Supply and Sanitation Services Investment Program - Tranche 1 (Navoi)

Prepared by “Uzkommunhizmat” (UCSA) for the Government of and the Asian Development Bank.

WATER SUPPLY AND SANITATION SERVICES INVESTMENT PROGRAM Tranche 1

Environmental Monitoring Report

according to the project "Modernization of an interregional Damkhodzhinsky water supply system with connection to it regional centers of Navoiysky and Bukhara areas. Reconstruction of system of the sewerage Termez" on Navoiysky area

I SECTION INTRODUCTION

The project "Modernization of the Damkhodzhinsky interregional water supply system with connection to it regional centers of Navoiysky and Bukhara areas. Reconstruction of system of the sewerage Termez" is the first draft of the Investment program of multitranche financing of Asian Development Bank "Water supply and sanitation service". Implementation of the project is provided at the expense of borrowed funds of ABR in the sum of 60 million US dollars (tranche No. 1) and means of joint financing of the Republic of Uzbekistan in the sum equivalent to 15 million US dollars. Total cost of the project – 75 million US dollars. The structure of the project includes two subprojects: - Modernization of the Damkhodzhinsky interregional water supply system with connection to it regional centers of Navoiysky and Bukhara areas; - Reconstruction of system of the sewerage Termez. In this volume the description of the "Modernization of the Damkhodzhinsky Interregional Water Supply System with Connection to It Regional Centers of Navoiysky and Bukhara Areas" subproject is submitted. The description of the "Reconstruction of System of the Sewerage Termez" subproject is submitted in volume II (Books 1 – 6). 1 . Project purpose Development of the Feasibility study and implementation of the "Modernization of the Damkhodzhinsky Interregional Water Supply System in Connection to It Regional Centers of Navoiysky and Bukhara Areas" subproject are caused by need of the solution of problems of drinking water supply of the population of Navoiysky area. Designed systems of water supply are important for health of the population and improvement of its living conditions and, finally, strengthening of their social protection. Besides, the subproject will promote realization of policy of resource-saving and improvement of infrastructure of drinking water supply. Improvement of water supply will be reached by a way: • Reconstruction and modernizations of the Damkhodzhinsky interregional water supply system, construction and reconstruction of conduits connections of districts to an interregional water supply system, reconstruction and expansions as required knots of distribution of water and parting networks in districts of Navoiysky area; • Increases in coverage of the population of districts the centralized water supply; • Improvements of quality of given water and ensuring compliance to its standards of the Republic of Uzbekistan; • Strengthening of reliability of work of system of water supply; • Increases of efficiency of existing systems of water supply; • Realization of measures for resource-saving; • Strengthening of a financial position and stability of work of the Damkhodzhinsky water supply system and the water supplying organizations of districts of Navoiysky area. The subproject provides increase in the general coverage of the population by drinking water of 5 regional centers of Navoiysky area.

2 . Implementation of the project Under all construction contracts on Navoiysky area are developed design and budget and tender documentation. The tender auction is held and 4 contracts on SMR performance in the following 5 regional districts of Navoiysky area are signed, construction works are conducted: • Pocket; • Хатирчи; • Kanimekh; • Beshrabod; and • Kiziltep. 3 . Measures for protection surrounding environments Data on measures for environment protection are provided in this section in territories of 5 regional centers of Navoiysky area where construction works are already conducted. city of Kanimekh General information The Kanimekhsky area is located in Navoiysky an oasis of the delta of the river of Zaravshan. The main waterway of the area is the channel Kanimekh with a water fence from 's river at the end of which there is the superficial Shorkulsky fall forming the lake and serving as a water intake for collectors. There is also a network of small sprinklers and collectors. In the Kanimekhsky area the main part of underground waters are characterized by a high mineralization (to 5ú/l), waters are unsuitable for economic and drinking water supply of the area. There are separate fresh lenses of small power, but their approved stocks are insignificant. The settlement of city type Kanimekh is the regional center of the Kanimekhsky area located on border with Bukhara area. In Kanimekh lives 7,2 thousand people, it is captured by drinking water supply of 3,68 thousand people or 51%. While coverage by a water supply system makes nearly 100%, coverage of the population receiving water makes of a network practically only a half from possible coverage. Besides, Kanimekh is connected to a water supply system Telemen's rural settlement in which lives 1,44 thousand people, from them is captured by water supply of 0,54 thousand people. PU "Suvokova" пгт. The Kanimekh buys water from the Damkhodzhinsky water supply system and uses water from a local water intake - the channel the Kanimekh which quality of water doesn't conform to the standard. Course of performance of construction works Reconstruction of water supply systems are provided after the contract No. 2564/ICB/3-11 "Reconstruction of system of water supply of Kanimekh" of November 12, 2011. Works on this contract are conducted by the JSC Sharkkurulishservice company The source of drinking water supply accepted Damkhodzhinsky an interregional water supply system. 35,4 km of water supply systems are laid. city of Beshrabat General information The district of the Novbakhorsky area is presented by flat, foothill and mountain complexes. The flat part of the territory is located in the south of the area, in the delta of the river of Zarafshan, in northeast and east part of the area the district raises and passes to spurs of ridge of Karatau (to 1000м above sea level). The main waterways of the area is the river of Zarafshan which passes on the southern border of the area, channels Kanimekh and Right-bank with a water fence from Zarafshan's river. From spurs of ridge of Karatau flow down саи - Sormich, Gurullyauksay. Карангульсай, Changla, there are also exits of underground waters - springs. In flat part of the Novbakhorsky area available underground waters are characterized by a high mineralization (to 5 g/l) and rigidity, waters are unsuitable for economic and drinking water supply of the area. In foothill part of the area there are lenses of fresh underground waters, but their approved stocks are insignificant. The settlement of city type Beshrabad is the regional center of the Novbakhorsky area located on border with Bukhara area. In Beshrabada lives 2,7 thousand people, it is captured by drinking water supply of 1,667 thousand people or 61,7%. Besides, the rural settlement Burkut in which lives 1,88 thousand people is connected to Beshrabad's networks, from them is captured by water supply of 0,513 thousand people or 27,2%. Source of water supply is the Damkhodzhinsky interregional water supply system. Conduit connection п.г.т. Beshrabad of 0 400 mm 9,9 km long and URV were constructed in 1997 On URV tanks with a pure volume of 1 000 m3 - 2 pieces chlorination and pump station, are located the equipped 5 pumps. The chlorination doesn't work, water isn't disinfected. From URV water on an intereconomic conduit moves to settlements Kizila, Ok-oltin, Chuyit, Yangiobod, Anarboki, Yukori Beshrabod, Kuyi Beshrabot, Kurama, Baykho, Kelachi, Arabkhon, Huniko, Garraye, Kukhron and Mekhcharagon with the total number of population of 17,5 thousand people. The settlement Beshrabad is connected to an intereconomic rural conduit in several points and for this reason water supply of rural settlements not stable. Course of performance of construction works According to the approved schedule diagram installation and construction works in the district Beshrabad of the Novbakhorsky area are carried out under the contract No. 2564/ICB/3-3 "Reconstruction of system of water supply of Beshrabad" of February 24, 2012. Works on this contract are conducted by the JSC Temur Malik company. Water supply of the settlement is carried out from knot of distribution of water reconstructed within this contract. Works on RChV, performance of 25% are begun. Works of pump station combined with the chlorination, performance of 40% are begun. All-construction works of the administrative and laboratory case are complete. Finishing works are conducted. Works on auxiliary buildings and constructions, performance of 50% are conducted. 9 km of water supply systems are laid. city of Yangirabat General information The district of the Hatyrchinsky area is presented by flat and foothill complexes. The most part of the territory is located in the alluvial plain of the delta of the river of Zarafshan, to the North the district raises and passes to the foothills of the ridge of Aktau. The main waterway of the area is the river of Zarafshan which passes on the southern border of the area, there are irrigation canals of Toss, Shavat with a water fence from Zarafshan's river. From spurs of the ridge of Aktau flow down саи - Koksaraysay, Lyangar, Maydon and others, are available also exits of underground waters - springs. In the Hatyrchinsky area underground waters in foothill part have a mineralization to 1,5 g/l, to the South their mineralization and rigidity raises. Underground waters can be used for economic and drinking water supply of the area on condition of application of desalination installation The city of Yangirabad is the regional center of the Hatyrchinsky area located on border with the Samarkand area. In the city lives 17,2 thousand people, it is captured by the centralized water supply of 7,96 thousand people or 46,3%. Sources of water supply of the city are the Damkhodzhinsky water supply system and the local wells which quality of water don't conform to the standard. The underground water intake consists of 5 wells, including 3 wells are located on a platform of URV and 2 wells separate - in the city. From 5 wells 2 separate wells equipped with pumps ETsV 10-120-60 work only. 3 wells located on URV don't work, upsetting pipes underwent corrosion because of long term of work (are drilled in the 70th) On a platform of URV RChV with a capacity of 3200 m3 - 1 piece, pump station the Yoke of lifting and the chlorination are located. In pump station of the 11th lifting from 6 pumps only 2 pumps in working condition. In the chlorination there is no processing equipment, chlorination by chloric lime is made in the primitive way. Course of performance of construction works According to the approved schedule diagram installation and construction works in the district of the Hatyrchinsky area the city of Yangirabad are carried out under the contract 2564/ICB/3-8 "Reconstruction of System of Water Supply of Yangirabod" of November 12, 2011. Works on this contract are conducted by the DP PMK-9 company at JSC Navoi suv kurilish. Workers and cars mechanisms are concentrated in software "Suvokava" of the Hatirchinsky area. Before SMR on all streets warrants were made. In addition to existing RChV with a capacity of 3 200 m3 construction of one RChV with a capacity of 1 000 m3 with the simplified filter absorber is provided. Works on a RChV soil obvalovaniye are begun. Works are performed for 95%. All-construction works of pump station combined with the chlorination are performed. Construction of a checkpoint is executed for 98%. Works to technological communications are performed for 70%. Construction of protections and gate is executed for 90%. Finishing works are conducted. 29,3 km of water supply systems are laid. City of General information The settlement of city type of the Pocket is near Navoi and is the regional center of the Karmaninsky area. In the settlement of the Pocket lives 22,6 thousand people, it is captured by drinking water supply of 21,0 thousand people or 92,9%. Besides, rural settlements Argun are connected to water supply systems of the Pocket, Talkok, Kunollar, Lubaton, Kavala, Kat Machit in which lives 6,045 thousand people, from them is connected to the centralized system of water supply of 3,385 thousand people. PU "Suvokova" пгт. Pocket buys water from system of water supply of Navoi and the Damkhodzhinsky water supply system. The knot of distribution of water of the district of 1 hectare is located in northern part of the city. On URV there is an office building of PU "Suvokova", one tank with a pure volume of 250 m3, pump station of the II-nd lifting and workshops. Course of performance of construction works Installation and construction works in the district of the Karmaninsky area the city of the Pocket are carried out under the contract No. 25464/ICB/3-7 "Reconstruction of system of water supply of. Pocket" of November 12, 2011. Works on this contract are conducted by the JSC Navoi kishlok kurilish company. Construction of RChV is almost complete. It was necessary to carry out hydrotests 2 го the tank, an obvalovaniye. Works on improvement come to the end. Works are performed for 95%. Construction of pump station is executed for 100%. Construction of the chlorination is executed for 100%. Construction of a checkpoint is executed for 100%. Construction technological communications is executed for 100%. Protections and gate it is executed for 100%. 27,2 km water networks are laid. city of Kiziltep General information The Kyzyltepinsky area is located in the alluvial plain of the delta of the river of Zaravshan which in the Kyzyltepinsky area passes on a small piece, in northern part. For an irrigation of farmlands of Navoiysky, Bukhara and Samarkand areas are constructed and channels are operated: Amubukharsky, the Shafirkansky branch, the Harkhursky branch, Shakhrud which pass through the territory of the Kyzyltepinsky area. Waters of channels are regulated Kuyumazarsky and Tudakulsky by reservoirs which also are used in the irrigating purposes and located in the territory of the area. The Kyzyltepinsky area as a whole is poor fresh underground waters, generally underground waters have a high mineralization and are unsuitable for economic and drinking water supply. The city of Kyzyltepo is the regional center of the Kyzyltepinsky area located on border with Bukhara area. In the city lives 12,8 thousand people, it is captured by drinking water supply of 7,32 thousand people or 57,2%. PU "Suvokova" buys water - from the Damkhodzhinsky water supply system and uses water from the local underground water intake which quality of water doesn't conform to the standard. The platform of knot of distribution of water and underground water intake is located in 3 km from the city in northwest part. Course of performance of construction works Installation and construction works in the district of the Kiziltepinsky area the city of Kiziltepo are carried out under the contract No. 2564/ICB/3-3 "Reconstruction of system of water supply of of Kyzyltepo" of February 24, 2012. Works on this contract are conducted by the JSC Temur-Malik company. The northwest district of the city is provided with water from existing URV "Kyzyltepo". URV under construction Construction of RChV is almost complete. RChV test is carried out a hydra, there was an obvalovaniye is executed for 60%, improvement is performed for 70%.stroitelny works pump stations are complete, the Equipment isn't put and not mounted. Performance of 80%. Construction of auxiliary constructions is complete. There were works on asphalting of roads and improvement. Performance of 95%. Reconstructed URV Construction works of RChV aren't begun. Construction works of pump station combined with the chlorination are complete. The equipment isn't put and not mounted. Performance of 80%. All- construction works of the administrative laboratory case are complete. Works on the device of windows and doors are complete. Performance of 75%. The checkpoint is under construction anew: All-construction works are performed for 80%. There were finishing works. 38,2 km of water supply systems are laid. II SECTION ENVIRONMENTAL MONITORING city of Kanimekh

Measures for mitigation of ecological influence For realization of environmental monitoring at the end November, 2012 forms of quarterly reports were sent to GRP for filling with contractors. The specialist in GRP environmental protection systematic visited building sites to check realization of nature protection measures. During survey the following is revealed. In order to avoid pollution of water resources and environment on construction objects special garbage containers are installed and special cars for garbage removal are involved. Against emergence of a dust it is carried out daily having watered in places where works on construction and reconstruction are conducted. Not to disturb people around in vicinities of schools and kindergartens the silent equipment is used. In evening and night operating time stop. Special places for washing of workers with providing with soap, detergents and towels for providing the corresponding sanitary and hygienic conditions are taken away. It is very good for health and life of workers. city of Beshrabat Measures for mitigation of ecological influence On April 9, 2012 in хокимията the area the meeting with representatives of local administration, heads of rural descents of citizens, directors of schools, heads of preschool institutions and citizens was held. The specialist in environmental protection and the specialist in social problems also participated in this meeting. The purposes of a meeting was to give summary about impacts on activity environment according to the project, management on environment protection, and also to create groups of environmental monitoring. Creation of ecological group of monitoring on GRP is one of the main conditions for full realization of the planned actions for the project and realization of measures for environmental protection and environmental monitoring. During the previous check are carried out in November and December, 2012, it was noted about need of installation of tanks and containers for URV, but it isn't made yet. Despite it, the territory of URV is cleared, arranged well and is irrigated. Now all waste collected on a building site daily it is taken out by special trucks to specially taken away dumps. In the territory of URV there are no building and household wastes. Now in the territory of URV containers and buckets for household and construction garbage are installed. Also it should be noted, now in URV there are no pollution from fuels and lubricants which it was observed during the previous visit on URV. city of Yangirabat Measures for mitigation of ecological influence In December 18, 2011, the meeting in GRP with involvement of heads makhaly, rural descents of citizens and software management "Suvokava" of the area was held. Are shined a question of implementation of the project including necessary measures for environment protection when carrying out construction works. Within the plan of measures the specialist in environmental protection of GRP of 12 times visited construction sites to check realization of measures for environmental protection. During survey in December, 1012 the following facts were found. Directly on an entrance to URV the special banner is established. On a banner it is possible to see information on the project, including start date and the terminations, the name of the contractor. In the territory of URV special containers for household and building wastes are installed. Antidust measures are carried out by a method of daily watering by water of places where works on construction and reconstruction are carried out. For decrease in noise in vicinities of kindergartens it is used without noisy equipment. At night works stop. At night all trenches and not mounted wells are protected for prevention of a casual provalivaniye in them of people and a livestock. Spill of fuels and lubricants it isn't observed.

City of Karmana Measures for mitigation of ecological influence On December 5, 2011 in хокимияте the area the meeting with representatives of local administration, heads of rural descents of citizens, directors of schools, heads of preschool institutions and citizens was held. The specialist in environmental protection and the specialist in social problems also took part at this meeting. At a meeting summary about impacts on activity environment according to the project was provided, and also the group of environmental monitoring is created. However it should be noted in a type of strong employment of members group, environmental monitoring some time I visited construction sites. Within the plan of measures for 2012, the specialist in environmental protection of 15 times visited building sites to check realization of measures for mitigation of ecological consequences of construction. During survey the following facts were found. In construction territories special containers and buckets for household and building wastes are installed. During visit it was offered to clear URV territory of construction garbage. Other rough violations it wasn't revealed. city of Kiziltepo Measures for mitigation of ecological influence Competitive documentation of a subproject "Water supply of priority villages of the area from a water intake" includes initial environmental assessments, the summary initial environmental assessment and ecological management and Plan monitoring. The specialist in environmental protection of 7 times visited the construction territory. During survey the following facts were found. Actually, in object there are positive shifts in respect of realization of measures for environment protection in comparison with the past the inspections, carried out in September and December, 2012. On building sites special containers and buckets for household and building wastes are installed. In the territory of URV there were open wells, but now they are closed. Workers live in the house belonging to "Suvokova" who is placed near URV. Telling as a whole living conditions of workers it is better, than in other subprojects. Are available special shower for workers. It should be noted, round the working house everywhere it is pure. It is very good for health and life of workers.

III SECTION MANAGEMENT OF THE STATE OF ENVIRONMENT The report on implementation of the Plan of Ecological Management at Reconstruction of system of water supply of Karmana

Project actions Possible ecological influences the The taken measures for Responsible organizations Taken measures vodeystviye minimization Stage prior to construction Accidents during activity Risks of emergence of accidents All reconstructed buildings and "Loyiha Maslahat" state of after completion of construction constructions are designed according emergency - the developer of the which can lead to damage of to standard requirements of the detailed project. Experts of state of buildings and damage the worker, Republic of Uzbekistan for seismic emergency of "Loyha Maslahat" owing to unsatisfactory design stability and fire safety. Expertize of according to the approved Schedule project documentation of leave on objects for the purpose of Glavgosekspertiza of carrying out architectural supervision Gosarkhitektstroy of the Republic of of compliance of construction works Uzbekistan is carried out and the to requirements of project positive decision on them is received. documentation Leaks from sewer system and a Water pollution in a distributive The centralized system of the "Loyiha Maslahat" state of water distribution network network because of leakages of the sewerage in the city is absent. emergency - experts carry out sewerage. architectural supervision of At reconstruction of a water supply compliance to the project of pipes system in the project polyethylene applied in construction pipes which are steady against corrosion are applied and are durable. Laying of pipelines of a new network Resettlement isn't expected but if it is As a result of adoption of the Experts of technical supervision and necessary, the framework optimum solution of laying of water GRP of Navoi supervise that programme of allocation of land and pipes during detailed design the construction didn't mention personal resettlement, for elimination of project doesn't affect the population, plots negative impacts will be considered personal plots and gardens. and changed to environment by Allocation of land and resettlement by resettlement the project isn't provided. Arrangement of dangerous materials, Threat to health and inconvenience Knot of distribution of water of. GRP of Navoi, PU "Suvokova" of storage of the noisy equipment and for the people living in the Pocket on which reconstruction of Navoiysky area, PU "Suvokova" of carrying out noisy works. neighbourhood with buildings and for pump station and construction of the Karmeninsky area workers on a site. pure tanks is carried out, it is located on the suburb of the city and it is removed from the densely populated territory on distance about 500 m Asbestos-cement Pipes (ACP) Harm to health at inhalation of fibers In the project it isn't provided uses of asbestos-cement pipes for the device of a water supply system, and earlier they also weren't used Construction stage The contractor or the workers who Insufficient realization of control The plan of Ecological Management The contractor created a control aren't observing ecological measures behind a state of is the annex to the contract. The system of environment and carries requirements, described in the environment general Terms of the contract are constantly out control for its contract added with item 63 OSUK where it is performance. GRP of Navoi and provided that the Contractor has to experts of technical supervision (and) create a working control system control this activity of consequences of impact on environment and (b) to carry out the monitoring and softening measures stated in the Management plan of Environmental protection The contractor has to delivers to the Customer Reports on performance of such measures Cars, the equipment and vehicles Emissions of construction cars and For prevention of formation of a dust Expert of technical supervision of used for construction and exhaust gases of the equipment; when exporting excessive soil it is construction transportations made it having watered. Dust from use of cars, clearing, The supervising foreman of the alignment and excavator works, etc.; In transit excessive soil vehicles are Contractor - provides compliance of covered with an awning PEM, visually inspects safe use of the equipment, noise level of vehicles Intensity of movement doesn't and mechanisms. The mechanic of a increase because the contractor uses site checks a technical condition of not a large number of equipment (2 mechanisms. Experts of GRP of dump trucks, 2 excavators and 2 Navoi supervises compliance to all truck cranes) provisions PEM, leaving on objects according to the Schedule The contractor signed the contract with service station which makes small repair, filling with oil and fuels and lubricants and maintenance of mechanisms, including check of emissions in the atmosphere All used equipment well is served and conforms to national standards Works on construction sites are performed about the 8th o'clock in the morning to the 18th o'clock in the evening. All works on service of equipment are performed also at this time. Works aren't conducted at night Preparation of a construction site Erosion on a site because of Construction works are carried out in The expert of technical supervision of clearing, alignment, and excavator strictly taken away places - URV construction exercises control that works, as a result the leader to reconstruction - in the territory of laying of pipes in the dug-out deposits of deposits in reservoirs; existing URV, reconstruction and trenches and their the return засыпка construction of a water supply system Experts of GRP of were made by - only in an earth right-of-way, without Navoi quickly in order to avoid mentioning the excessive territory collapses of walls of a trench of prevention of inconveniences for In venues of works in. The pocket inhabitants coordinate works isn't present need of use of a according to the Schedule construction timbering against a soil collapse as all works are carried out quickly enough (after trench digging quickly pipes keep within and the return is made засыпка) and maximum Lubin trenches for the device of a water supply system are made by 1,6 m. Restoration of a vegetable cover and Erosion and adjournment of deposits The top vegetable layer of earth was The job foremaster provides gardening in reservoirs, owing to excessive removed only for the device of two compliance of PEM. The expert of cleaning of a vegetable cover or the tanks with a pure volume of 1 000 m3 technical supervision and GRP of long periods without vegetation everyone. Other constructions are Navoi make control of these works reconstructed and the top vegetable layer of earth isn't removed The area of removal of a vegetable cover for these purposes is insignificant (450 sq.m). The top fertile layer acted and stored separately from other soil and will be used repeatedly at an obvalovaniye of tanks after completion of their construction. No trees or bushes were mentioned. Works are conducted within the fenced zone URV. After completion of all construction works improvement and territory gardening as it is provided in detailed design and budget and tender documentation will be made Excavator works for laying of pipes; Damages of municipal constructions Detailed project documentation was The job foremaster coordinates work by excavator works; coordinated with all interested with GRP of Navoi, Hokimiyatom and Use of roads for transportation of services (municipal, road, the power utility services and gets the materials and equipment Temporary termination of access to supply network, communication, etc.) corresponding permissions real estate; Prior to the beginning of a Current state of roads unsatisfactory, proivodstvo of works the Contractor it can worsen because of use of got permission to carrying out construction equipment. excavator works and coordinated with all utility services of the location and crossing of pipelines. In case of need representatives of these services are present at work. Permission of local authorities (Hokimiyata) is got for use of roads which after completion of works will be restored and asphalted as it is provided in project documentation The sewage formed on a Rain drains on a site can wash away All waste and construction garbage The controler behind a site of the construction site waste, garbage, leaves, lubricant are stored in specially taken away contractor substances, etc. pollution of an territory of a building site in special Periodic visual supervision of drains adjacent surface water is thus containers and in due time taken out of construction sites is supervised by possible on the territories coordinated with the job foremaster of construction Hokimiyatom and experts of GRP of Navoi Dangerous materials (fuel, chemicals or waste) aren't used when performing construction works. The solid waste formed as a result of Construction materials (a tree, steel Prior to construction works the The controler behind a site of the construction works fittings, cement, etc.), paper, packing Contractor received from Hokimiyata contractor materials, household waste/waste and SES allowing documents and Periodic visual supervision of a products of the person on a building coordinated places of warehousing condition of construction sites is site can cause environmental and export of waste supervised by the job foremaster of pollution and negative impact on a On sites of construction works there construction and experts of GRP of landscape which otherwise, is are containers for collecting garbage Navoi visually attractive. and building wastes The fulfilled oils and fuel on reconstructed water constructions aren't stored. Replacement of oil and fuelling is made at service stations of of Galaasy The contractor in due time takes out and utilizes building wastes, paper and scrap metal After completion of construction works the platform will be cleared of construction garbage, pipes as it is provided by the contract Inconvenience from construction – Inconvenience and impact of On construction sites banners with The controler behind a site of the complaints construction works on the next kinds the indication of the contract Contractor keeps the magazine of of activity and house farms. organization, ranking officers and registration of complaints, and also contact phones for submission of carries out explanatory work with complaints undergone to influence by makhallinsky committee and people are established. inhabitants of nearby houses URV is located far of inhabited quarters, at distance about 500 m and carrying out construction works don't result in inconveniences of the population. Before performance of work on construction of networks on city streets, the Contractor together with GRP and Hokimiyatom carried out explanatory work in махаллях, having explained the purposes of the project and having specified terms of performance of work on each site. For elimination of the inconveniences created for inhabitants, at construction of a water supply system, the contractor establishes temporary transitions through trenches Understanding social importance and need of this project, inhabitants transfer temporary inconveniences and don't complain Use of a manpower, from other areas Inappropriate living conditions for All builders working at platforms, live The controler behind a site of the visitors of workers in Navoi, the Pocket and nearby Contractor, Vodokanal of. Pocket areas. The contractor обеспчена delivery of workers to building sites and upon termination of the working day they come back to the place of residence. For this reason weren't organized camp for accommodation of workers Use of a manpower from other areas Presence of construction crews can All construction workers local also The controler behind a site of the increase demand for the prostitution, live houses Contractor, Experts of Technical the forbidden drugs, gamblings, etc. supervision and GRP of Navoi Vodokanal of. Pocket Safety of workers Measures of production safety Depth of trenches of construction The controler behind a site of the inappropriate to requirements doesn't exceed 1,6 m and there is no contractor danger of collapses Coordinates with GRP and Once a month the Contractor in the appropriate authorities and agencies. presence of the Engineer of technical Receives and registers complaints supervision trains all workers to from the public and resolves them equipment requirements безопасноти. Daily before the appearance at work, all workers are warned about obligatory observance of requirements of safety measures workers are provided with overalls and means of individual protection (a welding mask, points, etc.)

The report on implementation of the Plan of Ecological Management at Reconstruction of system of water supply of Kanimekh Project actions Possible ecological influences the The taken measures for Responsible organizations Taken measures vodeystviye minimization Stage prior to construction Accidents during activity Risks of emergence of accidents All reconstructed buildings and "Loyiha Maslahat" state of after completion of construction constructions are designed according emergency - the developer of the which can lead to damage of to standard requirements of the detailed project. Experts of state of buildings and damage the worker, Republic of Uzbekistan for seismic emergency of "Loyha Maslahat" owing to unsatisfactory design stability and fire safety. Expertize of according to the approved Schedule project documentation of leave on objects for the purpose of Glavgosekspertiza of carrying out architectural supervision Gosarkhitektstroy of the Republic of of compliance of construction works Uzbekistan is carried out and the to requirements of project positive decision on them is received. documentation Leaks from sewer system and a Water pollution in a distributive The centralized system of the "Loyiha Maslahat" state of water distribution network network because of leakages of the sewerage in the city is absent. emergency - experts carry out sewerage. architectural supervision of At reconstruction of a water supply compliance to the project of pipes system in the project polyethylene applied in construction pipes which are steady against corrosion are applied and are durable. Laying of pipelines of a new network Resettlement isn't expected but if it is As a result of adoption of the Experts of technical supervision and necessary, the framework optimum solution of laying of water GRP of Navoi supervise that programme of allocation of land and pipes during detailed design the construction didn't mention personal resettlement, for elimination of project doesn't affect the population, plots negative impacts will be considered personal plots and gardens. and changed to environment by Allocation of land and resettlement by resettlement the project isn't provided. Arrangement of dangerous materials, Threat to health and inconvenience The knot of distribution of water of GRP of Navoi, PU "Suvokova" of storage of the noisy equipment and for the people living in the Konimekh on whom reconstruction of Navoisky area, PU "Suvokova" of the carrying out noisy works. neighbourhood with buildings and for pump station and construction of Konimekhsky area workers on a site. pure tanks is carried out, is located on the suburb of the city and removed from the densely populated territory on distance about 500 m Asbestos-cement Pipes (ACP) Harm to health at inhalation of fibers In the project it isn't provided uses of asbestos-cement pipes for the device of a water supply system, and earlier they also weren't used Construction stage The contractor or the workers who Insufficient realization of control The plan of Ecological Management the contractor created a control aren't observing ecological measures behind a state of is the annex to the contract. The system of environment and carries requirements, described in the environment general Terms of the contract are constantly out control for its contract added with item 63 OSUK where it is performance. GRP of Navoi and provided that the Contractor has to experts of technical supervision (and) create a working control system control this activity of consequences of impact on environment and (b) to carry out the monitoring and softening measures stated in the Management plan of Environmental protection The contractor has to delivers to the Customer Reports on performance of such measures Cars, the equipment and vehicles Emissions of construction cars and For prevention of formation of a dust Expert of technical supervision of used for construction and exhaust gases of the equipment; when exporting excessive soil it is construction transportations made it having watered. Dust from use of cars, clearing, The supervising foreman of the alignment and excavator works, etc.; In transit excessive soil vehicles are Contractor - provides compliance of covered with an awning PEM, visually inspects safe use of the equipment, noise level of vehicles Intensity of movement doesn't and mechanisms. The mechanic of a increase because the contractor uses site checks a technical condition of not a large number of equipment (2 mechanisms. Experts of GRP of dump trucks, 2 excavators and 2 Navoi supervises compliance to all truck cranes) provisions PEM, leaving on objects The contractor signed the contract according to the Schedule with service station which makes small repair, filling with oil and fuels and lubricants and maintenance of mechanisms, including check of emissions in the atmosphere All used equipment well is served and conforms to national standards Works on construction sites are performed about the 8th o'clock in the morning to the 18th o'clock in the evening. All works on service of equipment are performed also at this time. Works aren't conducted at night Preparation of a construction site Erosion on a site because of Construction works are carried out in The expert of technical supervision of clearing, alignment, and excavator strictly taken away places - URV construction exercises control that works, as a result the leader to reconstruction - in the territory of laying of pipes in the dug-out deposits of deposits in reservoirs; existing URV, reconstruction and trenches and their the return засыпка construction of a water supply system Experts of GRP of Konimekh were - only in an earth right-of-way, without made quickly in order to avoid mentioning the excessive territory collapses of walls of a trench of prevention of inconveniences for In venues of works in Konimekh isn't inhabitants coordinate works present need of use of a construction according to the Schedule timbering against a soil collapse as all works are carried out quickly enough (after trench digging quickly pipes keep within and the return is made засыпка) and maximum Lubin trenches for the device of a water supply system are made by 1,6 m. Restoration of a vegetable cover and Erosion and adjournment of deposits The top vegetable layer of earth was The job foremaster provides gardening in reservoirs, owing to excessive removed only for the device of two compliance of PEM. The expert of cleaning of a vegetable cover or the tanks with a pure volume of 1 000 m3 technical supervision and GRP of long periods without vegetation everyone. Other constructions are Navoi make control of these works reconstructed and the top vegetable layer of earth isn't removed The area of removal of a vegetable cover for these purposes is insignificant (450 sq.m). The top fertile layer acted and stored separately from other soil and will be used repeatedly at an obvalovaniye of tanks after completion of their construction. No trees or bushes were mentioned. Works are conducted within the fenced zone URV. After completion of all construction works improvement and territory gardening as it is provided in detailed design and budget and tender documentation will be made Excavator works for laying of pipes; Damages of municipal constructions Detailed project documentation was The job foremaster coordinates work by excavator works; coordinated with all interested with GRP of Navoi, Hokimiyatom and Use of roads for transportation of services (municipal, road, the power utility services and gets the Temporary termination of access to materials and equipment real estate; supply network, communication, etc.) corresponding permissions Current state of roads unsatisfactory, Prior to the beginning of a it can worsen because of use of proivodstvo of works the Contractor construction equipment. got permission to carrying out excavator works and coordinated with all utility services of the location and crossing of pipelines. In case of need representatives of these services are present at work. Permission of local authorities (Hokimiyata) is got for use of roads which after completion of works will be restored and asphalted as it is provided in project documentation The sewage formed on a Rain drains on a site can wash away All waste and construction garbage The controler behind a site of the construction site waste, garbage, leaves, lubricant are stored in specially taken away contractor substances, etc. pollution of an territory of a building site in special Periodic visual supervision of drains adjacent surface water is thus containers and in due time taken out of construction sites is supervised by possible on the territories coordinated with the job foremaster of construction Hokimiyatom and experts of GRP of Navoi Dangerous materials (fuel, chemicals or waste) aren't used when performing construction works. The solid waste formed as a result of Construction materials (a tree, steel Prior to construction works the The controler behind a site of the construction works fittings, cement, etc.), paper, packing Contractor received from Hokimiyata contractor materials, household waste/waste and SES allowing documents and Periodic visual supervision of a products of the person on a building coordinated places of warehousing condition of construction sites is site can cause environmental and export of waste supervised by the job foremaster of pollution and negative impact on a On sites of construction works there construction and experts of GRP of landscape which otherwise, is are containers for collecting garbage Navoi visually attractive. and building wastes The fulfilled oils and fuel on reconstructed water constructions aren't stored. Replacement of oil and fuelling is made at service stations of Konimekh The contractor in due time takes out and utilizes building wastes, paper and scrap metal After completion of construction works the platform will be cleared of construction garbage, pipes as it is provided by the contract Inconvenience from construction – Inconvenience and impact of On construction sites banners with The controler behind a site of the complaints construction works on the next kinds the indication of the contract Contractor keeps the magazine of of activity and house farms. organization, ranking officers and registration of complaints, and also contact phones for submission of carries out explanatory work with complaints undergone to influence by makhallinsky committee and people are established. inhabitants of nearby houses URV is located far of inhabited quarters, at distance about 500 m and carrying out construction works don't result in inconveniences of the population. Before performance of work on construction of networks on city streets, the Contractor together with GRP and Hokimiyatom carried out explanatory work in махаллях, having explained the purposes of the project and having specified terms of performance of work on each site. For elimination of the inconveniences created for inhabitants, at construction of a water supply system, the contractor establishes temporary transitions through trenches Understanding social importance and need of this project, inhabitants transfer temporary inconveniences and don't complain Use of a manpower, from other areas Inappropriate living conditions for All builders working at platforms, live The controler behind a site of the visitors of workers in Navoi, Konimekh and nearby Contractor, Vodokanal of Konimekh areas. The contractor обеспчена delivery of workers to building sites and upon termination of the working day they come back to the place of residence. For this reason weren't organized camp for accommodation of workers Use of a manpower from other areas Presence of construction crews can All construction workers local also The controler behind a site of the increase demand for the prostitution, live houses Contractor, Experts of Technical the forbidden drugs, gamblings, etc. supervision and GRP of Navoi Vodokanal of Konimekh Safety of workers Measures of production safety Depth of trenches of construction The controler behind a site of the inappropriate to requirements doesn't exceed 1,6 m and there is no contractor danger of collapses Coordinates with GRP and Once a month the Contractor in the appropriate authorities and agencies. presence of the Engineer of technical Receives and registers complaints supervision trains all workers to from the public and resolves them equipment requirements безопасноти. Daily before the appearance at work, all workers are warned about obligatory observance of requirements of safety measures workers are provided with overalls and means of individual protection (a welding mask, points, etc.)

The report on implementation of the Plan of Ecological Management at Reconstruction of system of water supply the city of Yangirabod Project actions Possible ecological influences the The taken measures for Responsible organizations Taken measures vodeystviye minimization Stage prior to construction Accidents during activity Risks of emergence of accidents All reconstructed buildings and "Loyiha Maslahat" state of after completion of construction constructions are designed according emergency - the developer of the which can lead to damage of to standard requirements of the detailed project. Experts of state of buildings and damage the worker, Republic of Uzbekistan for seismic emergency of "Loyha Maslahat" owing to unsatisfactory design stability and fire safety. Expertize of according to the approved Schedule project documentation of leave on objects for the purpose of Glavgosekspertiza of carrying out architectural supervision Gosarkhitektstroy of the Republic of of compliance of construction works Uzbekistan is carried out and the to requirements of project positive decision on them is received. documentation Leaks from sewer system and a Water pollution in a distributive The centralized system of the "Loyiha Maslahat" state of water distribution network network because of leakages of the sewerage in the city is absent. emergency - experts carry out sewerage. architectural supervision of At reconstruction of a water supply compliance to the project of pipes system in the project polyethylene applied in construction pipes which are steady against corrosion are applied and are durable. Laying of pipelines of a new network Resettlement isn't expected but if it is As a result of adoption of the Experts of technical supervision and necessary, the framework optimum solution of laying of water GRP of Yangirabod supervise that programme of allocation of land and pipes during detailed design the construction didn't mention personal resettlement, for elimination of project doesn't affect the population, plots negative impacts will be considered personal plots and gardens. and changed to environment by Allocation of land and resettlement by resettlement the project isn't provided. Arrangement of dangerous materials, Threat to health and inconvenience The knot of distribution of water of GRP of Navoi, PU "Suvokova" of storage of the noisy equipment and for the people living in the Yangirabod on whom reconstruction Navoisky area, PU "Suvokova" of the carrying out noisy works. neighbourhood with buildings and for of pump station and construction of Hatirchinsky area workers on a site. pure tanks is carried out, is located on the suburb of the city and removed from the densely populated territory on distance about 500 m Asbestos-cement Pipes (ACP) Harm to health at inhalation of fibers In the project it isn't provided uses of asbestos-cement pipes for the device of a water supply system, and earlier they also weren't used Construction stage The contractor or the workers who Insufficient realization of control The plan of Ecological Management the contractor created a control aren't observing ecological measures behind a state of is the annex to the contract. The system of environment and carries requirements, described in the environment general Terms of the contract are constantly out control for its contract added with item 63 OSUK where it is performance. GRP of Navoi and provided that the Contractor has to experts of technical supervision (and) create a working control system control this activity of consequences of impact on environment and (b) to carry out the monitoring and softening measures stated in the Management plan of Environmental protection The contractor has to delivers to the Customer Reports on performance of such measures Cars, the equipment and vehicles Emissions of construction cars and For prevention of formation of a dust Expert of technical supervision of used for construction and exhaust gases of the equipment; when exporting excessive soil it is construction transportations made it having watered. Dust from use of cars, clearing, The supervising foreman of the alignment and excavator works, etc.; In transit excessive soil vehicles are Contractor - provides compliance of covered with an awning PEM, visually inspects safe use of the equipment, noise level of vehicles Intensity of movement doesn't and mechanisms. The mechanic of a increase because the contractor uses site checks a technical condition of not a large number of equipment (2 mechanisms. Experts of GRP of dump trucks, 2 excavators and 2 Navoi supervises compliance to all truck cranes) provisions PEM, leaving on objects The contractor signed the contract according to the Schedule with service station which makes small repair, filling with oil and fuels and lubricants and maintenance of mechanisms, including check of emissions in the atmosphere All used equipment well is served and conforms to national standards Works on construction sites are performed about the 8th o'clock in the morning to the 18th o'clock in the evening. All works on service of equipment are performed also at this time. Works aren't conducted at night Preparation of a construction site Erosion on a site because of Construction works are carried out in The expert of technical supervision of clearing, alignment, and excavator strictly taken away places - URV construction exercises control that works, as a result the leader to reconstruction - in the territory of laying of pipes in the dug-out deposits of deposits in reservoirs; existing URV, reconstruction and trenches and their the return засыпка construction of a water supply system Experts of GRP of were made by - only in an earth right-of-way, without Navoi quickly in order to avoid mentioning the excessive territory collapses of walls of a trench of prevention of inconveniences for In venues of works in Yangirabod inhabitants coordinate works isn't present need of use of a according to the Schedule construction timbering against a soil collapse as all works are carried out quickly enough (after trench digging quickly pipes keep within and the return is made засыпка) and maximum Lubin trenches for the device of a water supply system are made by 1,6 m. Restoration of a vegetable cover and Erosion and adjournment of deposits The top vegetable layer of earth was The job foremaster provides gardening in reservoirs, owing to excessive removed only for the device of two compliance of PEM. The expert of cleaning of a vegetable cover or the tanks with a pure volume of 1 000 m3 technical supervision and GRP of long periods without vegetation everyone. Other constructions are Navoi make control of these works reconstructed and the top vegetable layer of earth isn't removed The area of removal of a vegetable cover for these purposes is insignificant (450 sq.m). The top fertile layer acted and stored separately from other soil and will be used repeatedly at an obvalovaniye of tanks after completion of their construction. No trees or bushes were mentioned. Works are conducted within the fenced zone URV. After completion of all construction works improvement and territory gardening as it is provided in detailed design and budget and tender documentation will be made Excavator works for laying of pipes; Damages of municipal constructions Detailed project documentation was The job foremaster coordinates work by excavator works; coordinated with all interested with GRP of Navoi, Hokimiyatom and Use of roads for transportation of services (municipal, road, the power utility services and gets the materials and equipment Temporary termination of access to supply network, communication, etc.) corresponding permissions real estate; Prior to the beginning of a Current state of roads unsatisfactory, proivodstvo of works the Contractor it can worsen because of use of got permission to carrying out construction equipment. excavator works and coordinated with all utility services of the location and crossing of pipelines. In case of need representatives of these services are present at work. Permission of local authorities (Hokimiyata) is got for use of roads which after completion of works will be restored and asphalted as it is provided in project documentation The sewage formed on a Rain drains on a site can wash away All waste and construction garbage The controler behind a site of the construction site waste, garbage, leaves, lubricant are stored in specially taken away contractor substances, etc. pollution of an territory of a building site in special Periodic visual supervision of drains adjacent surface water is thus containers and in due time taken out of construction sites is supervised by possible on the territories coordinated with the job foremaster of construction Hokimiyatom and experts of GRP of Navoi Dangerous materials (fuel, chemicals or waste) aren't used when performing construction works. The solid waste formed as a result of Construction materials (a tree, steel Prior to construction works the The controler behind a site of the construction works fittings, cement, etc.), paper, packing Contractor received from Hokimiyata contractor materials, household waste/waste and SES allowing documents and Periodic visual supervision of a products of the person on a building coordinated places of warehousing condition of construction sites is site can cause environmental and export of waste supervised by the job foremaster of pollution and negative impact on a On sites of construction works there construction and experts of GRP of landscape which otherwise, is are containers for collecting garbage Navoi visually attractive. and building wastes The fulfilled oils and fuel on reconstructed water constructions aren't stored. Replacement of oil and fuelling is made at service stations of of Galaasy The contractor in due time takes out and utilizes building wastes, paper and scrap metal After completion of construction works the platform will be cleared of construction garbage, pipes as it is provided by the contract Inconvenience from construction – Inconvenience and impact of On construction sites banners with The controler behind a site of the complaints construction works on the next kinds the indication of the contract Contractor keeps the magazine of of activity and house farms. organization, ranking officers and registration of complaints, and also contact phones for submission of carries out explanatory work with complaints undergone to influence by makhallinsky committee and people are established. inhabitants of nearby houses URV is located far of inhabited quarters, at distance about 500 m and carrying out construction works don't result in inconveniences of the population. Before performance of work on construction of networks on city streets, the Contractor together with GRP and Hokimiyatom carried out explanatory work in махаллях, having explained the purposes of the project and having specified terms of performance of work on each site. For elimination of the inconveniences created for inhabitants, at construction of a water supply system, the contractor establishes temporary transitions through trenches Understanding social importance and need of this project, inhabitants transfer temporary inconveniences and don't complain Use of a manpower, from other areas Inappropriate living conditions for All builders working at platforms, live The controler behind a site of the visitors of workers in Bukhara, Galaasiya and nearby Contractor, Vodokanal of Yangirabod areas. The contractor обеспчена delivery of workers to building sites and upon termination of the working day they come back to the place of residence. For this reason weren't organized camp for accommodation of workers Use of a manpower from other areas Presence of construction crews can All construction workers local also The controler behind a site of the increase demand for the prostitution, live houses Contractor, Experts of Technical the forbidden drugs, gamblings, etc. supervision and GRP of Navoi, Vodokanal of Yangirabod Safety of workers Measures of production safety Depth of trenches of construction The controler behind a site of the inappropriate to requirements doesn't exceed 1,6 m and there is no contractor danger of collapses Coordinates with GRP and Once a month the Contractor in the appropriate authorities and agencies. presence of the Engineer of technical supervision trains all workers to Receives and registers complaints equipment requirements from the public and resolves them безопасноти. Daily before the appearance at work, all workers are warned about obligatory observance of requirements of safety measures workers are provided with overalls and means of individual protection (a welding mask, points, etc.) The report on implementation of the Plan of Ecological Management at Reconstruction of system of water supply of the cities of Kyzyltepos and Beshrabad Project actions Possible ecological influences the The taken measures for Responsible organizations Taken measures vodeystviye minimization Stage prior to construction Accidents during activity Risks of emergence of accidents All reconstructed buildings and "Loyiha Maslahat" state of after completion of construction constructions are designed according emergency - the developer of the which can lead to damage of to standard requirements of the detailed project. Experts of state of buildings and damage the worker, Republic of Uzbekistan for seismic emergency of "Loyha Maslahat" owing to unsatisfactory design stability and fire safety. Expertize of according to the approved Schedule project documentation of leave on objects for the purpose of Glavgosekspertiza of carrying out architectural supervision Gosarkhitektstroy of the Republic of of compliance of construction works Uzbekistan is carried out and the to requirements of project positive decision on them is received. documentation Leaks from sewer system and a Water pollution in a distributive The centralized system of the "Loyiha Maslahat" state of water distribution network network because of leakages of the sewerage in the city is absent. emergency - experts carry out sewerage. architectural supervision of At reconstruction of a water supply compliance to the project of pipes system in the project polyethylene applied in construction pipes which are steady against corrosion are applied and are durable. Laying of pipelines of a new network Resettlement isn't expected but if it is As a result of adoption of the Experts of technical supervision and necessary, the framework optimum solution of laying of water GRP of Yangirabod supervise that programme of allocation of land and pipes during detailed design the construction didn't mention personal resettlement, for elimination of project doesn't affect the population, plots negative impacts will be considered personal plots and gardens. and changed to environment by Allocation of land and resettlement by resettlement the project isn't provided. Arrangement of dangerous materials, Threat to health and inconvenience The knot of distribution of water of of GRP of Navoi, PU "Suvokova" of storage of the noisy equipment and for the people living in the Kiziltep and Beshrabad on whom Navoiysky area, PU "Suvokova" carrying out noisy works. neighbourhood with buildings and for reconstruction of pump station and Kiziltepinsky and Navbakhorsky area workers on a site. construction of pure tanks is carried out, is located on the suburb of the city and removed from the densely populated territory on distance about 500 m Asbestos-cement Pipes (ACP) Harm to health at inhalation of fibers In the project it isn't provided uses of asbestos-cement pipes for the device of a water supply system, and earlier they also weren't used Construction stage The contractor or the workers who Insufficient realization of control The plan of Ecological Management the contractor created a control aren't observing ecological measures behind a state of is the annex to the contract. The system of environment and carries requirements, described in the environment general Terms of the contract are constantly out control for its contract added with item 63 OSUK where it is performance. GRP of Navoi and provided that the Contractor has to experts of technical supervision (and) create a working control system control this activity of consequences of impact on environment and (b) to carry out the monitoring and softening measures stated in the Management plan of Environmental protection The contractor has to delivers to the Customer Reports on performance of such measures Cars, the equipment and vehicles Emissions of construction cars and For prevention of formation of a dust Expert of technical supervision of used for construction and exhaust gases of the equipment; when exporting excessive soil it is construction transportations made it having watered. Dust from use of cars, clearing, The supervising foreman of the In transit excessive soil vehicles are Contractor - provides compliance of alignment and excavator works, etc.; covered with an awning PEM, visually inspects safe use of the equipment, noise level of vehicles Intensity of movement doesn't and mechanisms. The mechanic of a increase because the contractor uses site checks a technical condition of not a large number of equipment (2 mechanisms. Experts of GRP of dump trucks, 2 excavators and 2 Navoi supervises compliance to all truck cranes) provisions PEM, leaving on objects The contractor signed the contract according to the Schedule with service station which makes small repair, filling with oil and fuels and lubricants and maintenance of mechanisms, including check of emissions in the atmosphere All used equipment well is served and conforms to national standards Works on construction sites are performed about the 8th o'clock in the morning to the 18th o'clock in the evening. All works on service of equipment are performed also at this time. Works aren't conducted at night Preparation of a construction site Erosion on a site because of Construction works are carried out in The expert of technical supervision of clearing, alignment, and excavator strictly taken away places - URV construction exercises control that works, as a result the leader to reconstruction - in the territory of laying of pipes in the dug-out deposits of deposits in reservoirs; existing URV, reconstruction and trenches and their the return засыпка construction of a water supply system Experts of GRP of were made by - only in an earth right-of-way, without Navoi quickly in order to avoid mentioning the excessive territory collapses of walls of a trench of prevention of inconveniences for In venues of works in Kiziltepo and inhabitants coordinate works Beshrabod isn't present need of use according to the Schedule of a construction timbering against a soil collapse as all works are carried out quickly enough (after trench digging quickly pipes keep within and the return is made засыпка) and maximum Lubin trenches for the device of a water supply system are made by 1,6 m. Restoration of a vegetable cover and Erosion and adjournment of deposits The top vegetable layer of earth was The job foremaster provides gardening in reservoirs, owing to excessive removed only for the device of two compliance of PEM. The expert of cleaning of a vegetable cover or the tanks with a pure volume of 1 000 m3 technical supervision and GRP of long periods without vegetation everyone. Other constructions are Navoi make control of these works reconstructed and the top vegetable layer of earth isn't removed The area of removal of a vegetable cover for these purposes is insignificant (450 sq.m). The top fertile layer acted and stored separately from other soil and will be used repeatedly at an obvalovaniye of tanks after completion of their construction. No trees or bushes were mentioned. Works are conducted within the fenced zone URV. After completion of all construction works improvement and territory gardening as it is provided in detailed design and budget and tender documentation will be made Excavator works for laying of pipes; Damages of municipal constructions Detailed project documentation was The job foremaster coordinates work by excavator works; coordinated with all interested with GRP of Navoi, Hokimiyatom and Use of roads for transportation of services (municipal, road, the power utility services and gets the materials and equipment Temporary termination of access to supply network, communication, etc.) corresponding permissions real estate; Prior to the beginning of a Current state of roads unsatisfactory, proivodstvo of works the Contractor it can worsen because of use of got permission to carrying out construction equipment. excavator works and coordinated with all utility services of the location and crossing of pipelines. In case of need representatives of these services are present at work. Permission of local authorities (Hokimiyata) is got for use of roads which after completion of works will be restored and asphalted as it is provided in project documentation The sewage formed on a Rain drains on a site can wash away All waste and construction garbage The controler behind a site of the construction site waste, garbage, leaves, lubricant are stored in specially taken away contractor substances, etc. pollution of an territory of a building site in special Periodic visual supervision of drains adjacent surface water is thus containers and in due time taken out of construction sites is supervised by possible on the territories coordinated with the job foremaster of construction Hokimiyatom and experts of GRP of Navoi Dangerous materials (fuel, chemicals or waste) aren't used when performing construction works. The solid waste formed as a result of Construction materials (a tree, steel Prior to construction works the The controler behind a site of the construction works fittings, cement, etc.), paper, packing Contractor received from Hokimiyata contractor materials, household waste/waste and SES allowing documents and Periodic visual supervision of a products of the person on a building coordinated places of warehousing condition of construction sites is site can cause environmental and export of waste supervised by the job foremaster of pollution and negative impact on a On sites of construction works there construction and experts of GRP of landscape which otherwise, is are containers for collecting garbage Navoi visually attractive. and building wastes The fulfilled oils and fuel on reconstructed water constructions aren't stored. Replacement of oil and fuelling is made at service stations of of Kiziltep and Beshrabad The contractor in due time takes out and utilizes building wastes, paper and scrap metal After completion of construction works the platform will be cleared of construction garbage, pipes as it is provided by the contract Inconvenience from construction – Inconvenience and impact of On construction sites banners with The controler behind a site of the complaints construction works on the next kinds the indication of the contract Contractor keeps the magazine of of activity and house farms. organization, ranking officers and registration of complaints, and also contact phones for submission of carries out explanatory work with complaints undergone to influence by makhallinsky committee and people are established. inhabitants of nearby houses URV is located far of inhabited quarters, at distance about 500 m and carrying out construction works don't result in inconveniences of the population. Before performance of work on construction of networks on city streets, the Contractor together with GRP and Hokimiyatom carried out explanatory work in махаллях, having explained the purposes of the project and having specified terms of performance of work on each site. For elimination of the inconveniences created for inhabitants, at construction of a water supply system, the contractor establishes temporary transitions through trenches Understanding social importance and need of this project, inhabitants transfer temporary inconveniences and don't complain Use of a manpower, from other areas Inappropriate living conditions for All builders working at platforms, live The controler behind a site of the visitors of workers in Navoi, Kiziltep and Beshrabad and Contractor, Vodokanal of Kiziltepo nearby areas. and Beshrabad The contractor обеспчена delivery of workers to building sites and upon termination of the working day they come back to the place of residence. For this reason weren't organized camp for accommodation of workers Use of a manpower from other areas Presence of construction crews can All construction workers local also The controler behind a site of the increase demand for the prostitution, live houses Contractor, Experts of Technical the forbidden drugs, gamblings, etc. supervision and GRP of Navoi Vodokanal of Kiziltepo and Beshrabad Safety of workers Measures of production safety Depth of trenches of construction The controler behind a site the inappropriate to requirements doesn't exceed 1,6 m and there is no contractor danger of collapses Coordinates with GRP and Once a month the Contractor in the appropriate authorities and agencies. presence of the Engineer of technical Receives and registers complaints supervision trains all workers to from the public and resolves them equipment requirements безопасноти. Daily before the appearance at work, all workers are warned about obligatory observance of requirements of safety measures workers are provided with overalls and means of individual protection (a welding mask, points, etc.) Inspections on sites Creation of ecological group of monitoring on GRP is one of the main conditions for full realization of the planned actions for the project and realization of measures for environmental protection and environmental monitoring. However it should be noted in a type of strong employment of members group, environmental monitoring some time I visited construction sites. In June, 2013 during survey of construction objects concerning nature protection measures in building sites the following is revealed: city of Kanimekh In order to avoid pollution of water resources and environment on construction objects special garbage containers are installed and special cars for garbage removal are involved. Against emergence of a dust it is carried out daily having watered in places where works on construction and reconstruction are conducted. Not to disturb people around in vicinities of schools and kindergartens the silent equipment is used. In evening and night operating time stop, objects are protected with special tapes and precautionary signs. Special places for washing of workers with providing with detergents and towels for providing the corresponding sanitary and hygienic conditions are taken away. It is very good for health and life of workers. city of Beshrabad The territory of URV is cleared, arranged well and is irrigated. Now all waste collected on a building site daily it is taken out by special trucks to specially taken away dumps. In the territory of URV there are no building and household wastes. Now in the territory of URV containers and buckets for household and construction garbage are installed. During survey in inside URV it isn't revealed pollution from fuels and lubricants. city of Yangirabad In the territory of URV special containers for household and building wastes are installed. Antidust measures are carried out by a method of daily watering by water of places where works on construction and reconstruction are carried out. At night installation and construction works stop. At night all trenches and not mounted wells are protected for prevention of a casual provalivaniye in them of people and a livestock. Spill of fuels and lubricants it isn't observed. City of Karmana In construction territories special containers and buckets for household and building wastes are installed. During visit of construction garbage in the territory of URV it isn't revealed. Other rough violations it wasn't revealed. Evening installation and construction works aren't conducted. city of Kyzyltepo On building sites special containers and buckets for household and building wastes are installed. Household and building wastes are taken out to specially taken away places. Workers live in the house belonging to "Suvokova" who is placed near URV. Telling as a whole living conditions of workers it is better, at survey of complaints from workers didn't arrive. Are available special shower for workers. It should be noted, round the working house everywhere it is pure. It is very good for health and life of workers.