Supplementary evidence provided in support of Counties Power Limited's presentation to the Auckland Unitary Plan Independent Hearings Panel in respect of Topic 016/017 RUB North/West and RUB South IN THE MATTER of the Resource Management Act 1991
AND
IN THE MATTER of Proposed Plan Change 12 to the Auckland Council District Plan: Papakura Section, Proposed Private Plan Change 38 to the Auckland Council District Plan: Franklin Section, Proposed Plan Change 19 to the Auckland Regional Policy Statement, ( ) and Proposed Plan Change 3 to the Auckland Council Regional Plan: Air, Land, and Water
STATEMENT OF EVIDENCE BY MAURICE HOSKINS
FOR COUNTIES POWER LIMITED
Introduction
1. My full name is Maurice Max Hoskins and I am the Planning Engineer with Counties Power Limited. I hold the degrees of Bachelor of Science and Bachelor of Engineering (Hons) from the University of Canterbury and Certificate of Electrical Engineering Supply. I have practised as an Electrical Engineer for 38 years working in New Zealand, 2 years in the United Kingdom and 2 years in Saudi Arabia.
2. I was appointed as the Planning Engineer in 1994 and as such I am responsible for the medium and long term planning of the power system in Counties Power. Particular emphasis in this role is placed on the planning of subtransmission, substations and distribution feeders. 3. The purpose of my evidence is to outline the wider significance of the 11 OkV lines that run through the Drury South Structure Plan (DSSP) area, to confirm the difference between supplying a new industrial area and a new residential area, to provide a brief overview of how Counties Power intends to supply power to the DSSP area, and to confirm the importance of retaining flexibility with respect to these distribution lines.
Significance of the 110kV lines in the Network 4. The two Counties Power 11 OkV lines crossing through the DSSP area are those supplying our Opaheke 11 OkV/22kV substation located at the junction of Opaheke, Ponga and Sutton Roads. This substation presently supplies Southern Papakura City and the area bounded by Blackbridge Road in the West, the Hunua Range catchment area in the East and Stevensons Quarry in the South. Hence this substation supplies the ( Hingaia Peninsular, the DSSP area and will supply the newly proposed housing areas Papakura-Drury defined in the Auckland City RUB discussions on going at present. (An estimated extra 26,759 dwellings).
5. This substation will also be part of the supply to the North Franklin Area (Karaka North, Karaka West, Whangapouri and Paerata North areas as defined in the RUB documentation) another 26,608 dwellings.
6. Hence the supply to the Opaheke Substation is a critical part of the ( infrastructure of supply not only to the proposed DSSP Area but also to the greater area around it.
7. Because of the importance of these lines I consider it would not be good engineering practise to place these lines underground and expose our customers in the area to the higher risks posed by underground cables. Repair times of underground cables are measured in days and weeks compared to overhead lines in hours. This has been demonstrated by the Christchurch earthquake and the loss of Supply into Auckland in 1998. The loss of supply to large areas for extensive periods in the above places, were a direct consequence of underground cables being employed. 8. Also it must be borne in mind the extra cost of underground 11 OkV cable installations an estimated twenty times the cost of overhead construction.
Supply to and reticulation of non- residential areas 9. Residential areas are characterised by a high degree of certainty of future demands as opposed to, commercial and industrial areas, and are easy to plan in advance for supply. The demands of Commercial areas are relatively easy to predict once the buildings have been designed, however this is much later in the planning process than for residential areas.
( 10. The demands of Industrial areas in contrast however, are unknown and can change dramatically with time. A building could initially be used as a warehouse with essentially lighting only and later by a thermoplastic ( industry with very intensive demands. The latter could require 22kV supply to the site with its own 22kV/415V transformers whereas the former only a 415V supply.
11 . For a lot in industrial zone 4 the demand could be such that a separate feeder to supply the lot is required and in the extreme case an 11 OkV/22kV substation could be required on site.
12. Hence the requirements and future requirements of industrial are always uncertain and there is need to retain maximum flexibility of the supply to the ( area concerned.
Planned Supply to the DSSP Area 13. It is planned to supply the DSSP Area from two feeders from the Opaheke Substation, one along Flanagan and Tegal Roads in the NW (Drury Feeder) and the other along Fitzgerald Road and Ramarama Roads (Drury Hills Feeder) in NE. A back up and third feeder will be from the south presently along Ramarama Road supplied initially from our Ramarama Substation on Hillview Road and ultimately from our new substation to be built east of the Transpower Bombay Substation. 14. Should the demand exceed the provisional demand of 20-26 MVA then most likely Counties Power would construct another 110kV/22kV substation in the DSSP Area. Depending on location of the substation this could require additional 11 OkV lines and at least another feeder within the area. Also to gain maximum economic and supply benefits from the new substation, new feeders would be constructed to supply areas outside the DSSP area.
Comments on underground cables networks
15. Underground cable cables at 22kV cost about three times the cost of equivalent line overhead. The tap off from an overhead line to a line down a road costs approximately $3500 whereas from an underground cable to an underground cable is approximately $42,000. However from an overhead line to an underground cable the same as for an overhead line about $3500. To break into an underground cable to supply another spur or transformer can cost of the order of $50,000 or even greater. Not to mention that extra joints have to be inserted in the cable. Joints are potential failure points and we try to keep them to a minimum.
16. To lay an underground cable the road needs to be formed and the berms at the final level and ideally all other works completed.
17. In short overhead lines are much better able to cope with uncertain demands, as occur in industrial areas.
Reticulation of the Drury South Area 18. A possible staged development of the area is detailed in the Beca report supporting the original Stevenson application. However, in fact, the development will more than likely be driven by the uptake of the lots. Hence in some directions for the planned supply the roads will not necessarily be formed. The Beca report indicated that the entrance to the subdivision will initially be from Quarry Road in the NE and staged inwards from there. This implies that the roads from the NW and the South will not be formed until later on in the development. However to give the required capacity and backup supply to the area, lines are also required from the NW and the South.
19. Hence Counties Power request that in these cases supply is by overhead lines until the roads are formed and then the 22kV and 400V reticulation placed underground. This of course would be at the developers cost.
20. To retain flexibility particularly for the industrial zone 4 area I recommend that the 22kV distribution along Ramarama Road remains overhead at least until the subdivision is fully developed. This would allow any spur lines easily to be run to lots where required. While it is proposed that Ramarama ( Road be closed, to maintain a backup supply, the reticulation into the subdivision along Ramarama Road from the south would need to be retained until other routes are completed from the south to the northern part ( of Ramarama Road .
21. The 11 OkV subtransmission lines through the area would remain overhead to best serve our customers. Also because of the Auckland City expansion there could be need to convert the single circuit line along the motorway to a double circuit line. Pole heights would generally be close to existing heights.
22. In summary, Counties Power is happy to use underground lines where circumstances justify this, for example in new residential subdivisions. Equally for the benefit of our customers we use overhead lines where these are appropriate, including for our subtransmission 11 OkV lines and for flexible reticulation in industrial subdivisions. We submit that the plan change should permit overhead lines
23. Thank you. I would be happy to answer any questions.
Maurice Hoskins Planning Engineer Counties Power Ltd 4 July 2013 ...
- { '
( I Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifications)
IN THE MATIER of the Resource Management Act 1991
IN THE MATIER of Proposed Plan Change 12 to the Auckland
Council District Plan: Papakura Section,
Proposed Private Plan Change 38 to the
Auckland Council District Plan : Franklin
Section, Proposed Plan Change 19 to the
Auckland Regional Policy Statement, and
Proposed Plan Change 3 to the Auckland
Council Regional Plan : Air, Land, and Water
STATEMENT OF EVIDENCE BY CRAIG VAUGHAN MAGEE
ON BEHALF OF COUNTIES POWER LIMITED
INTRODUCTION
1. My name is Craig Magee and I hold the role of Planning Manager at Resource
Management Solutions Limited, a consultancy established in Auckland in 1996. I
have a Bachelor of Planning from the University of Auckland and I have been a full
member of the New Zealand Planning Institute since 2000. I have eighteen years'
experience in resource management in both New Zealand and the United Kingdom,
working within both public and private organisations. In my current role I provide
resource management advice and assistan ce to a wide range of clients, including \ / Auckland Council.
2. I have been engaged by Counties Power Limited ("Counties Power" } to consider how
the matters outlined in their submission (and further subm issions} have been dealt
with in the Planner's Report within the Hearing Agenda (and subsequent
documentation}, and to prepare and present hearing evidence accordingly. I was not
involved in preparing the Counties Power submissions or within subsequent discussions with Stevensons.
Resource Management Solut ions Lim i ted
- I - C• RMS Evidence of Craig Magee, Dru ry South Struct ure Plan (Proposed Pla n Modifications)
CODE OF CONDUCT
3. I confirm that I have read the Environment Court Practice Note (2011), and in
particular Section 5 (Expert Witnesses) and complied with it in writing this evidence. I confirm that this evidence is written within my expertise, except where otherwise
stated, and that I have not omitted to consider material facts known to me that
might alter or detract from the opinions expressed.
MY EVIDENCE
4. My evidence is based on my own professional opinion but also references the views of Counties Power. I confirm that I have read and considered the relevant
documents within the Hearing Agenda .
COUNTIES POWER
5. Counties Power operates the electricity distribution network in south Auckland and
north Waikato, as well as other businesses including a fibre optic
telecommunications network. It is their job to ensure the network is ma intained and
any faults quickly repaired. They are also responsible for extending the network to
any new development areas (although the landowner is responsible for the costs of installing a connection from the Counties Power network to the bu ilding site).
6. As outlined within the submission, Counties Power has a nu mber of important assets
within the Plan Change Area, including:
• Two 110kV sub-transmission electricity lines,
• Many lower voltage lines, and ( • A fibre optic cable.
7. Counties Power also has a direct interest in some of the properties w ithin the Plan
Change area by way of easements for these assets and in some of the existing roads.
THE SITE AND LOCALITY
8. The subject area ha s been described in various documents. The entire subject is
within the Counties Power servicing area.
R esource M anagement Sol ut i ons L imi t e d
- 2 - Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifications)
SUBMISSION AND FURTHER SUBMISSION
9. The submission lodged by Counties Power is not within the Hearing Agenda
documentation; however I assume the Commissioners have a copy of all the submissions. Two 'further submissions' are included within the Hearing Agenda, at
Pages 347 and 349.
10. In summary the original submission sought to ensure that matters relating to
electricity supply in and through the subject area were properly considered and that
specific changes to any relevant statutory provisions reflected this consideration.
Counties Power indicated their support of the proposed Drury South initiative, and
submitted that the Plan Changes should be approved subject to a number of ( amendments.
11. In summary the requested amendments:
• Sought the recognition and provision for the physical resources by identifying the
two llOkV lines within the Structure Plan,
• Sought the protection (and the management of reverse sensitivity effects} in
relation to the 110kV lines,
• Sought the insertion of subdivision criteria to ensure either the continued
presence of the llOkV lines, or appropriate consideration of their relocation (in
discussion with Counties Power},
• Sought the avoidance of applying other rules which may generate impacts on
existing assets (e.g. landscape and visual amenity controls, Motorway Edge
Precinct/Commercial Service Precinct rules},
• Sought that the changes to the Plan provisions recognised that the preliminary
undergrounding of llOkV lines for an industrial area is liable to be inefficient and
not technically desirable, and that retaining these overhead would enable more
effective management of the initial growth and development stage of the Plan
Change area,
• Sought an amendment to ensure that the new zoning being introduced does not inadvertently alter the rule framework for network utilities in Part 15.1.2 of the Franklin section of the Plan,
12. Within their two further submissions Counties Power:
Resource Management So lu t1ons L imited
- 3- -.•RMS Evidence of Craig Magee, Drury South Str ucture Plan (Proposed Pla n Modifications)
• Opposed Transpower's proposed Rules 6.11.7.10 and 29C.6.10 because they
would control buildings and structures including network utilities such as
electricity poles. This would have required Counties Power to obtain unnecessary
resource consents for their buildings and structures.
• Supported Transpower's proposed Rule 6.11.7.10 (in so far as it excludes
earthworks undertaken by a network utility operator).
AGREED REVISIONS
13. Following this Counties Power and Stevensons entered into discussions on these
matters in early 2013. The parties agreed a set of revisions to the District Plan
amendments and I understand that these were viewed as acceptable by the
reporting planner Craig Cairncross.
14. However due to what I understand was simply an oversight, the set of revisions not
make it into Attachment 4 of the Hearing Agenda ("SGLs proposed amendments to
the District Plan {Papakura and Franklin section) - relevant chapters annotated" ).
Subsequently they have not been considered within Attachment 5 ("Plan Changes 12
and 38 as amended by Planner's hearing report recommendations").
15. Nevertheless, I understand that on the first day of this hearing Greg Osborne
presented the Commissioners with a marked-up revised set of District Plan
amendments. I have been provided with a copy of this set and can confirm that they
match up with the changes agreed with Counties Power. In summary:
Papakura section:
5B.4.2.10.3 Policy: as agreed the revised amendment will seek to ensure that
adverse effects are to be managed by ensuring the safe operation of~ existing high
voltage electrical transmission and distribution lines and fibre optic cables (as
opposed to only those belonging to Transpower and Telecom).
5B.4.2.10.4 Explanation: as agreed the revised amendment will acknowledge
Counties Power's two 110kV sub-transmission lines and their fibre optic cable. The
provision will also alert people to the New Zealand Electrical Code of Practice for
Electrical Safe Distances, and provide guidance.
Resource M a n agement Solutions Limited
- 4 - C• RMS Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifications)
6.11.7.1 Activity Table: as agreed the revised amendment will exclude buildings for
Network Utilities from requiring Controlled activity consent for the external design
and appearance of buildings within the Commercial Service Precincts and Motorway
Edge Precincts. As a result of discussions with Transpower the revised amendments
also exclude Network Utilities from requiring non-complying activity consent for
buildings/structures within 12m of the centreline of the National Grid Transmission
Line (or support structure).
6.15(6) General Criteria for Industrial Zones: as agreed the revised amendment will
add a note to make people aware that any trees planted in the vicinity of electricity
( lines must comply with the Electricity (Hazards from Trees) Regulations 2003.
6.15.2.10 Restricted Discretionary Activity Assessment Criteria for Subdivision: as
agreed the revised amendment inserts a criterion specifically relating to the
Counties Power 110 kV sub-transmission Lines. The criterion ensures that
subdivisions make provision for the existing position of the lines, or consider
whether they can be relocated (with the agreement of Counties Power).
Franklin section:
26.4A.1n) - Conditions on Restricted Discretionary Activities: the agreed revised
amendment allows the Council to impose conditions on subdivision consents in
relation to the Counties Power 110 kV Sub-transmission Lines.
26.4A.2o)- Restricted Discretionary Activity Assessment Criteria for Subdivision: the
agreed revised amendment inserts a criterion specifically relating to the Counties
Power 110 kV Sub-transmission Lines. The criterion ensures that subdivisions make
provision for the existing position of the lines, or consider whether they can be
relocated (with the agreement of Counties Power).
Part 29C- Rule 29C- Light Industrial Zone : the agreed revised amendment inserts
wording to make it clear that Network Utilities within the Drury South Structure Plan
area are subject to the provisions in Part 15.1 of the Plan ("NETWORK AND OTHER
UTILITIES AND ESSENTIAL SERVICES" ) and not the provisions within Part 29C.
Resource Management Solutions limited
- 5 - Evidence of Craig Magee, Drury South Structure Plan {P roposed Plan Modificat ions)
29C.2 Controlled Activities - Light Industrial Zone : the agreed revised amendment
provides confirmation that although any building within the Motorway Edge Precinct
or the Commercial Services Precincts are Controlled activities, this rule does not
include NETWORK AND OTHER UTILITIES which shall be Permitted Activities subject
to compliance with Rule 15.1.2.
54.18.2.10.3 Reverse Sensitivity Effects on Drury Quarry, the Industrial 4 Zone and
Surrounding Rural Zones and Significant Electricity, Gas and Telecommunications
Infrastructure - Policy: the agreed revised amendment will seek to ensure that adverse effects are to be managed by ensuring the safe operation of ill.! existing high voltage electrical transmission and distribution lines and fibre optic cables (as
opposed to only those belonging to Transpower and Telecom).
54.18.2.10.4 - (as above, but Explanation): the agreed revised amendment will
acknowledge Counties Power's two 110kV sub-transmission lines and their fibre
optic cable. The provision will also alert people to the New Zealand Electrical Code of Practice for Electrical Safe Distances, and provide guidance.
16. In terms of the issues raised in the submission and further submissions, these
revised amendments are acceptable to Counties Power.
COUNTIES POWER LIMITED'S OVERHEAD 110kV LINES
17. The remaining issue raised in the submission relates to Counties Power's ability to
retain overhead 110kV sub-transmission lines through the subject area.
18. I note that within the planner's report (on Page 66 of the Hearing Agenda) the issue
has been considered as follows:
"Counties Power have stated in its submission that overhead reticulation of electricity
would be appropriate in some instances, particularly during the initial stages of
development within the DSSP. "
"It is considered that overhead reticulation of new electricity lines within a
developing urban area would be inappropriate. The visual impacts of overhead
Resource M anagement Solutions Limited
- 6- Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifications)
services can be avoided by installing underground ducting, ond such installation can
be achieved at a relatively low cost during the civil works phase of land development.
If the DSSP is to proceed, it is considered that the District Plan rules should ensure
that all local electricity distribution within the DSSP is provided by underground
means.
The Aurecon report indicates that undergrounding of the 110kV transmission lines is
possible but is expensive. However in much of Auckland such lines are required to be
located underground (as least as a permitted activity) and such an approach is
proposed in the draft Unitary Plan. It is considered therefore that such lines should
not be provided for as permitted activities."
19. The planner (on Page 68 of the Hearing Agenda) therefore makes the
recommendation that the submission requesting relaxation of the rules requiring the
undergrounding of electricity lines "be rejected".
20. However I have assessed the rules within the Franklin and Papakura Plans that
would apply and I do not agree that 'relaxation' is required. Specifically I note that
Rule 15.1.2.20 of the Franklin Plan has been updated by the Consent Order resulting
from a Counties Power appeal (ENV-2010-AKL-000150). The result of that Consent
Order is that overhead llOkV lines are in fact permitted activities in the 'Industrial'
and 'Light Industrial' zones under the Franklin Plan (the exception being 'Light
Industrial' within the Kingseat Structure Plan Area, and so long as they meet the
requirements within the bullet points of "15.1.2.1 Permitted activities").
21. Within the Papakura Plan, Section 11.8.1 sets out Permitted Activities in terms of
'Network Utilities, Transport and Roading'. Clause 11.8.1.5 provides for the following
as a Permitted Activity:
"New lines or additions to lines for conveying electricity at a voltage up to and
including 110kV with a design capacity up to and including 100 MVA per circuit,
including all support structures for those lines."
22. On this basis Counties Power seek to maintain the Permitted status for llOkV sub
transmission line which currently exists in both Plans as it would apply to the new
Resource M anagement Solutions Limited
- 7 - ~• RMS Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifi cations)
the Industrial and Light Industrial zoned land.
23. Counties Power wish to emphasise the need for flexibility and reiterate the sound
reasoning behind this request, and we will soon hear brief evidence about this from
Mr Maurice Hoskins, Planning Engineer of Counties Power.
24. In summary Counties Power confirm their ability to service the development likely to
be provided for under the Proposed Plan Modification. To do this, Counties Power
considers it to be important that the necessary infrastructure improvements are able
to be practically achieved, and this includes the need for overhead electricity
infrastructure in certain situations. Counties Power are not opposed to the undergrounding of the 110kV lines for aesthetic reasons, but rather seek that this be
accommodated at the appropriate times.
25. Within his evidence presented on the first day of this hearing, Mr Osborne noted (at
paragraph 8.1} that the DSSP area is likely to be developed over a 15 year period
from approximately 2015 to 2030. Development of the area will be driven by
commercial demand and the need to establish the infrastructure links. He refers (at
paragraph 8.3} to supporting expert evidence from Mr Borlease which explained the
practical reasons why the staging plan should remain indicative at this point in the
process, the key reason being the need to retain flexibility until detailed design is
complete.
26. Counties Power strongly support the request for flexibility and this is reflected in the
agreed revisions to the District Plan revisions. Specifically, an assessment criterion
has been agreed (within both Plans} which requires that subdivisions make provision
for the existing position of the llOkV Counties Power lines, or consider whether they can be relocated (with the agreement of Counties Power}. This is because there is no
certainly in terms of how the subdivisions within the area will develop, and whether
it will be most practical to retain the existing positioning of the llOkV lines, or
whether it would be practical to re-align them.
27. Mr Alan Bull (Associate Electrical Engineer on behalf of Stevenson Group Ltd}
presented evidence on the second day of the hearing. Mr Bull notes (at paragraph 4.1} that the expected load, should the area be populated with a mixture of light
R esource M a n a g eme n t Solu t ions L i m ite d
- 8 - -.•RMS Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modificat ions)
industry and commercial consumers, will be in the order to 20 to 26MVA. However
(at paragraph 4.3} he notes that for heavy industries that use significant power
consumption, additional supply may be required. This will require consultation with
the utility supplier such as Counties Power, and the likelihood of additional
infrastructure investment. Mr Hoskins will elaborate on this shortly.
28. Mr Hoskins will also confirm how the nature of the proposed activities present a
different situation from the development of a residential area (or even an area with
a balance of zonings}, where the electricity supplier would have a far greater ability
to predict the ultimate power load, and the only uncertain issue is therefore timing.
As outlined in the Counties Power submission, with industrial sites the loading can ( vary wildly and any attempt to predict can lead to significant under-sizing or over sizing of plant and perhaps the wrong location (for off-take points). Overhead lines
are significantly more flexible, and therefore judicious use of them is appropriate
( during the developmental phase of industrial areas.
29. Again, Mr Hoskins will shortly go into this in greater detail; however Mr Bull's
statement would seem to emphasise the logic of providing greater flexibility for Counties Power. As outlined, the most practical trigger for determining the location
of the lines is when the location and timing of the development roads is finalised. In
terms of District Plan provisions, the most practical trigger for this is at subdivision.
( At this point it may be that a developer proposes a new utility corridor. Certainty of whether corridors will be retained or moved will be provided once the relevant
subdivisions are known and Counties Power is then aware what the appropriate
loading requirements will be.
30. Counties Power also wish to emphasise again that the 110kV lines are the 'backbone
lines' which need to be continuous. Therefore, understandably, they would prefer
consistent planning rules along their length.
31. Additionally I would note that the Proposed Plan Modifications seek to zone an area
of land as 'Industrial' and 'Light Industrial'. In my opinion measures to provide a good level of amenity throughout the relevant area are appropriate. However I do
not believe the retention of two above-ground 110kV sub-transmission lines will be incongruous with the physical development in these zones, particularly the
Resou rc e Ma nagement Solutions L imited
- 9- Evidence of Craig Magee, Drury South Structure Plan (Proposed Plan Modifications)
development phase. As outlined within the submission, the decision to use llOkV
lines for sub-transmission through this area (rather than 33kV) has already
minimised the amount of overhead infrastructure required to service the district.
Visual impacts can be addressed by limiting overhead to the higher voltage lines
(llOkV and above) and directing that, unless exceptional circumstances occur, all
lower voltage lines be undergrounded. lower voltage lines are the local lines serving
one or a few sites, and therefore their need can be predicted.
32. As I understand it, llOkV lines they have significant planning advantages over the
more usual (in NZ) 33kV lines- although of similar size they have more than 3 times
the capacity, meaning fewer lines overall. Overhead lines have significant
advantages over underground lines - aside from being perhaps 5% of the capital
cost, they are able to be repaired more quickly, they have greater resilience (e.g.
after catastrophes), and enjoy enhanced flexibility - particularly important in a
developing area.
33 . In my view these reasons, outlined in more detail within the submission and within
the evidence to be delivered by Mr Hoskins, are reasonable. In light of this I believe the Structure Plan should proceed without any alterations to any District Plan
provisions which would result in a requirement that llOkV lines be undergrounded.
34. Before I invite Mr Hoskins to present evidence I would be happy to answer any
questions. However I would note that any technical questions would be better
directed to Mr Hoskins at the conclusion of his evidence. Mr Bob lack, Commercial
Assistant at Counties Power, is also in attendance to assist with questions. (
Thank you.
Craig Magee
Planning Manager
Resource Management Solutions limited
4 July 2013
Resource M anagement So l ut i ons Limited
- 10 -
A U C K L A N D C O U N C I L
DECISION OF THE HEARINGS COMMISSIONERS FOR:
PROPOSED CHANGE 19 TO THE AUCKLAND REGIONAL POLICY STATEMENT – EXTENSION TO THE METROPOLITAN URBAN LIMITS; and
PROPOSED CHANGE 3 TO THE AUCKLAND REGIONAL PLAN: AIR, LAND AND WATER (OPERATIVE IN PART) – INDUSTRIAL AND URBAN AIR QUALITY MANAGEMENT AREAS; and
PROPOSED PRIVATE PLAN CHANGES 12 PAPAKURA SECTION OF THE AUCKLAND COUNCIL DISTRICT PLAN; and
PROPOSED PRIVATE PLAN CHANGE 38 FRANKLIN SECTION OF THE AUCKLAND COUNCIL DISTRICT PLAN.
The Hearings Commissioners were: Mr David Kirkpatrick (Chair), Mr Ian Gunn, Mr Mark Farnsworth and Mr Greg Hill.
The Hearing was held on 24 – 28 June, 1 – 5 and 10 July 2013, with site visits on 28 June and 18 July 2013. The hearing formally closed on 24 July 2013.
1. Summary of the Decision
The Commissioners have decided that:
(a) Proposed Change 19 to the Auckland Regional Policy Statement (ARPS), be APPROVED, and
(b) Proposed Change 3 to the Auckland Regional Plan: Air, Land and Water (ARP:ALW) be APPROVED, and
(c) Proposed Private Plan Change 12 to the Auckland District Plan (Papakura Section) (ADP:PS) be APPROVED, subject to the amendments made as set out in the attached versions, and
(d) Proposed Plan Change 38 to the Auckland District Plan (Franklin Section) (ADP:FS) be APPROVED, subject to the amendments made as set out in the attached versions.
The text of the Plan Changes in terms of our decision is attached. These are in “tracked change” versions. The tracking of the changes, including the highlighting appears in this text only as an aid to finding the changes and identifying the source of the changes, and is not intended to form part of the plan changes once they are made operative.
The amended plan change documents attached are as follows: