<<

VAN SEUMEREN GROUP worldwide specialists in heavy lifting and transport

MAMMOET2001 1 WORLDO

Watch out! Low flying vessel Miller Park Stadium Snorre B project Submarines on wheels Windmills in our mind Contents Introduction 2 Always on the move 2 Introduction

Petrochemical Safety, know-how and De Meern - We proudly present the first issue of a completely re-styled journal especially professionalism 4 produced for our relations and valued clients. It will keep you updated about the develop- Naphtha plant stop at DSM 4 ments in the Mammoet organisation. EmergO-Project achieves highest point 5 A lot has happened since the shore industry, the bollard shaped For those who received the former Watch out! Low flying vessel… 5 acquisition of Mammoet by the Mammoet office is entirely built at Van Seumeren Newsletter or From to Egypt 5 Van Seumeren Group last year. their yard. At the end of this year Mammoet Mail: this publication is As shown in the organisation chart Mammoet (who else?) will transport the successor of both magazines. At a different angle 6 on page 3, a new structure has the structure by SPMT trailers and To underscore Mammoet’s extended About reactors and silos 6 been implemented. As a matter a to the Rotterdam area over working field we named the new A lift to remember 6 of fact it has been put in effect in a distance of 40 kilometres. publication “Mammoet World”. a very short time. It will change the skyline of the Maarten de Graaf looks back Nieuwe Waterweg overnight. The editors are glad to introduce on a eventful year 7 By the end of 2001, a new head At that moment the new heavy lift you on behalf of the management Two Alstom projects 8 office will be inaugurated in the terminal ready. to the fascinating Mammoet world greater Rotterdam area. Currently It will give direct access to ocean and its borderless heavy lift and From the Houston harbour to a state-of-the-art heavy lift terminal going vessels because the pier is sit- transport opportunities. the Exxon Baytown Refinery 8 is created, unique in its kind. uated at deep water. Heavy transport in Venezuela 8 The construction of the prefabricat- Therefore, heavy lift equipment can Mammoet in Iran 9 ed head office has been awarded be mobilised easily to any destination to one of our esteemed clients, in the world. Storage of heavy loads Malaysia and Thailand 9 Grootint in Zwijndrecht. Similar to will be a new feature on this terminal the construction methods in the off- in the largest in the world.

Trading Mammoet Trading 9

Civil it’s Mammoet!!! 10 Flower Power 11 Cranage at various levels 11 A tree is known by its fruit 12 First class bridge 12 Bridges for trains, trams and pedestrians 12 Miller Park Stadium 13 Railway bridge installed 13 Tunis Rades Stadium 13

Offshore Mammoet dedicated to offshore 14 Always on the move Heimdal riser 14 Wintershall 14 Snorre B Project 15 Heaviest offshore structure ever moved on wheels 15 Multi lift 15 Pemex Canterall EPC-1 Project 15 The focus of the Executive Board is on the future

Ports and On 12 July 2000, the contracts were signed that gave a new enterprise its formal status. Submarines on Wheels 16 Van Seumeren Holland BV and Mammoet BV, both renowned for their achievements in the market Odense Steel 16 for heavy lifting and transport, joined forces. The focus of the Executive Board is on the future, Expansion of Polish Shipyard 17 capitalising on the fascinating synergy advantages that this acquisition offers. Lower it steady and easy… 17 Gone with the cranes… 17 Extension of the cruise This not only refers to the geographic on difficult jobs, as well as more stan- the largest company in the market. Costa Classica 17 Typical presence, but also to the range of dard services. It is the range of our By consequence, and this is my sec- on a vessel and trailers 18 solutions that we can offer in heavy products and services that is most ond aspect, we support a valuable Cranage in South Africa 18 What is characteristic for the new lifting and transport. My second con- typical to us.” network of contacts, representatives, enterprise? On the last day of sideration is ‘professionalism’. The offices and other point of contacts. Manila South Harbor 18 December 2000, the Executive Board merger of both companies is to some Frits van Riet, who joined the Ms Seaway 18 is asked to reflect on three aspects extend a logical step in market devel- Executive Board from Mammoet, is The challenge is to get the organi- that they consider as most typical for opments. Due to even higher invest- primarily responsible for the internal sation as lean as possible, while the new Mammoet corporation, which ments by our clients in equipment like operations and is challenged by the keeping the communication lines employs over 1,600 professionals vessels, jackets or other heavy ele- need to integrate both companies as with customers short. I will elaborate Power world wide. ments, they will only trust the delicate smooth and as quick as possible. more on these organisational aspects Windmills in our mind 19 job of transport and lifting to a party later on. Transformers on the move 19/20 Frans van Seumeren, President and that guarantees a quick, safe and The Managing Director and COO CEO, does not need long to complete thus professional operation. presents some additional aspects Finally, when I look to the current his list. “Both companies have com- that are typical for the new company. operations, at the end of this year plementary skills and equipment Our big company can offer, sustain “I would emphasise that we are truly and barely six months after joining Corporate identity to offer, so my first item is ‘global and develop further this required pro- a global player and thus support a 24 Van Seumeren, I consider our com- coverage’. fessionalism. My third item is related hour service. When it comes to the pany dynamic and fast, with a mind- Mammoet new style visualised 20 to the other two. Mammoet operates range of services and the range of set for pro-active support of Mammoet addresses 20 at the top of the market and focuses locations where we operate, we are our customers”.

Mammoet World 2001Mammoet World 2001 Page 2 Roderik van Seumeren, Vice Yes, as Frits said, we are among the market segment currently shows an kets that I really want to call ‘green cal development. According to President Mammoet Global, shares biggest companies in the market. upswing as major investments were fields’ since we are at the beginning Frans van Seumeren, it offers a lot the aspect of professionalism with But this status also makes you vulner- postponed the last couple of years of large scale operations there. of potential in creating better logistic his colleagues. “An aspect that is able. You have to prove over and over solutions, more alternatives for exe- very important to me is that we again your leadership position and cuting heavy lifting and transport achieve really tailor made solutions stress your company to the limits of jobs and improving the service level. that work smoothly and safely. its capacities and abilities. It is a chal- “Our wide range of equipment is No job in heavy lifting and transport lenge I like. It appeals to our success- positioned such that we can bring can be business as usual. ful spirit of pioneering, while at the in any required item on short notice. same time we must achieve a smooth This means that the average cycle We have to account for unexpected and cost effective operation that is time for a job will decrease. circumstances and must guarantee typical of big, mature companies.” In short, we will aim for better and the safety of our customers’ equip- quicker service.” ment and all personnel involved at any time. In many cases, this will Outlook for 2001 A final aspect that will dominate lead to innovative, yet simple and 2001 is the development of the creative solutions, like the one Frans van Seumeren referred in his Mammoet new headquarters in we developed for the Milwaukee New Years speech to promising mar- the greater Rotterdam area. Stadium. (see page 13) ket developments. The profitability The construction started and the Having said this, my third choice in on, for instance, the rental activities 2400 tonnes, 45 metre high building characterising our new company is in the ‘home market’ Benelux as a of economic develop- China is a good example and I still will be transported in one piece that the sky is the limit. I do not remains at an acceptable level and ments in the Far East. In parallel, expect a good future in the Russian from Zwijndrecht over a distance of believe that there is any object that contributes to the overall result. Frans van Seumeren also expects market development. Also in the 40 kilometres to its final location. we cannot move or lift in place. The world wide (petro) chemical the offshore market to gain momen- Middle East we are looking for It is expected that by the end of tum at the end of 2001 or in 2002. opportunities to enforce our market 2001, the staff now employed in “I would not say that these are all position.” De Meern and Breda can move to ‘traditional’ markets for us, since the new site. “It’s a bit a part of our each shows its own rhythm and The acquisition of Mammoet has culture. Always on the move, and offers its own surprises. been received very well by the cus- now even with our staff” replies “We will be capitalising on the fascinating synergy But in contrast, there are also mar- tomers and is considered as a logi- Frans van Seumeren. advantages that this acquisition offers.”

MAMMOET WORLDWIDE Big and lean “The quality of our staffing is most critical organisation to our commercial results.”

At the heart of the new organisa- BOARDBOARD OFOF MANAGEMENTMANAGEMENT tion is a decentralised approach. Mammoet has four regions that are allowed to operate auto- nomously within the corporate “The quality of our staffing is most are expecting us to keep improving standards. critical to our commercial results. ourselves, in professionalism, service From our joined forces, we have to level and innovation or creativity. The regions are centred on , select the best people for the most My personal challenge is to com- the Americas, the Middle East demanding jobs. Fortunately, our plete the integration process by the and . In addition, there market leadership is very attractive end of this year. is a fifth organisational body: for young and promising profession- AMERICA’S MAMMOET GLOBAL TRADE Mammoet Global. als that seek a career track with lots By then, everybody is in place, with of opportunities. Frankly, we do not the correct mindset and ready for The blueprint of the organisation is allow ourselves to spend a long time any challenge to come.” textbook like, but what about the in recruiting people. We want the practical daily operations? best and we want them now.

EUROPE ASIA Frits van Riet is complementary to Moreover, the inflow of new people Frans van Seumeren. While the CEO will accelerate the change of corpo- is an entrepreneur in all aspects and rate culture towards a client driven, MIDDLE EAST has a firm external focus, the COO service oriented organisation, even accepted the challenge to restyle the more than the previous companies = strategy/investments/reporting former companies into a dynamic, could offer. This is not just a goal in = com.projects/availabitity equipment loyal and professional organisation. itself. The market, our customers,

“Mammoet Global should be considered as an entity that facilitates the regional organisation in completing specifically difficult or demanding jobs.”

Mammoet Global

Why is it necessary to establish capacity, resulting in having a part of Mammoet Global next to the four our resources sitting idle. Mammoet regional organisations? Global should be considered as an Roderik van Seumeren explains entity that facilitates the regional the tasks of his organisation in the organisation in completing specifi- making. “Mammoet Global focusses cally difficult or demanding jobs. on extreme jobs in heavy lifting and transport, most of them being Our most skilled engineers work ‘one of a kind’. within Mammoet Global and offer a ‘think tank’ that generates innovative The expertise and skills needed and tailor made solutions for any engineering and others. Finally, Roderik van Seumeren considers his getic potentials - in available equip- to execute such jobs is to precious challenge offered to us. As a corpo- Mammoet Global is responsible organisation as a conductor of an ment, logistics and expertise - into to be developed in parallel in four rate body, Mammoet Global is also for the training and education orchestra. By co-ordinating activities solid business advantages and high regions. Also the storage of the responsible for setting and maintain- of our senior operational staff between regional organisations and level services for customers. equipment required for those jobs ing group standards, in the field of and comprises a kind of corporate overseeing the total operations, in four regions would mean over safety, quality control, maintenance, school.” Mammoet Global will turn the syner-

Mammoet World 2001 Page 3 Petrochemical

MAMMOET EUROPE

Safety, know-how and professionalism

The chemical, petrochemical and process indus- This offers the customer many benefits. offer additionally his own work. In The Netherlands tries are important market segments for One of the most important is that Mammoet, Mammoet supports in-house branches on the site Mammoet. These industries provide the natural when needed, will mobilise a substantial quantity of various (petro)chemical companies like Shell, environment for the development of new, innova- of equipment and skilled personnel in a very short Dow, DSM, Huntsman, Dupont and Corus tive heavy lift systems such as the containerised time. Although price is always a key consideration, Steelworks at IJmuiden. PTC (I and II) and MSG 50 (I and II) systems. it is not the first argument to consider the use of These serve as nerve centres from where all local rental cranes. Safety is even more important, operations are co-ordinated. For those customers They frequently serve operations at, for instance, followed by know-how and professionalism. who have no partnership contract with Mammoet, refineries. At the same time a large fleet of mobile Mammoet considers plant stops as complete inte- a dedicated temporary shop is established on cranes of all capacities, and skilled staff is avail- grated projects. From the moment a customer is the site. The Mammoet project manager can thus able for maintenance work and plant stops. prepared and able to describe about 70 percent of easily discuss the work in an early stage with the In fact, a special plant stop concept has been all lifting requirements for its plant stop, Mammoet mechanical contractor. This facilitates effective introduced. It comprises a flat fee agreement can offer the flat fee for the whole project. engineering and good planning, vital to every based on a partnership contract. The mechanical contractor can then plant stop.

Naphtha plant stop at DSM

Geleen - A maintenance stop was scheduled for the naphtha plant at DSM. During the stop, a de-bottleneck project had to be executed as well. Ir. Jacques Kemp, project and turnaround manager, comments on these operations.

“The overall project required 200,000 labour hours designed a crane plan and assured free access supervisor used during the lifting operations. It was as the stop was scheduled to last 4 weeks. Thanks over our roads such that other contractors could an extra dimension to safety and acknowledged by to efficiency improvement, this could be reduced to do their job as well.” all involved. By the way, good communications 3.5 weeks. For such operations, much lifting has to between the contractors was vital, as 1,500 be done. We had 16 fixed lifting locations and The most heavy crane was a 400 tonnes crawler employees did speak French, German or English some could be supported by mobile cranes as well. crane with luffing jib, necessary to support the instead of Dutch. Safety was continuously stressed The cranage needed should feature various capaci- extension of a distillation column. Another remark- and supported by toolbox-, safety promotion- and ties. In the nine months of preparations, we able feature was a small whistle that the Mammoet regular co-ordinating meetings.

No secrets…

During the season of harvesting the market and with whom could we experience with several good per- ‘white gold’, asparagus, Mammoet establish a partnership? forming parties. Yet we selected World had a chat with Ton van de The wheeling & dealing remains an Mammoet amongst others, since Kerkhof, Purchasing Manager with important issue, but it comes sec- they concentrate on crane activities DSM Services B.V. in the province of ond. Partnerships are typical for for our market, the chemical indus- Limburg, The Netherlands. sales management, and I still stick try. In fact, a great deal of their oper- “I’m already three years with this to that principle. I can say now that ations take place in this segment. department. Before that, I was the purchasing department really So they know our business, our employed with Sales for 12 years. adopts a different strategy, com- stakes and our safety issues.” My change of job was triggered by pared to a couple of years ago.” the management that desired a more According to Van de Kerkhof, the marketing style of operation at the Van de Kerkhof elaborates on the most essential part is the develop- purchasing department. I supported changed policy. “The issue is that ment of a mutual relationship the introduction of a new purchasing we outsource as much as possible, between market leaders of different procedure, the so called Purchasing especially the things we do not do branches. This assures the best per- Marketing Planning, to the General well ourselves. Obviously, lifting and formance, the optimum benefit of Technical Services branch, responsi- transport is not our core business, innovative achievements and of ble for scaffolding, isolation, indus- but the same is true for other main- course quality and safety. trial cleaning and others. One idea tenance disciplines. We do have a was not to start with a request for lot of expertise, but specialised staff offers from various contractors, but of an external contractor simply per- to begin with a market analysis. forms better. However, they should be market leaders or top players in What is the market turnover and their business. This lead position what is our own market share? has to be very clear. Who are the major suppliers in the As for the crane business, we have

Mammoet World 2001 Page 4 EmergO-Project achieves highest point

Terneuzen - On Saturday 17 June 2000, the upgrading of a distillation plant in the EmergO project of Dow Chemical reached a milestone.

The upgrading yields an increase of production Project manager Jo Timmer gave the formal start rather close, many separation stages are needed capacity with 600 kilo tonnes ethylene per year to for the lifting operations, involving the hoisting of to reach the required purity levels. 1,700 kilo tonnes. To achieve this, the 18 furnaces a 5.75 metres diameter top section to 110 metres This is why the column is 110 metres high. in the LHC-2 complex needed a modification to high, making it the highest distillation column in Apart from lifting, Mammoet also serves the heavy meet a new design, doubling their individual Holland. The column, part of the separation train, transport needed for this extension project. capacity. By consequence, the energy consump- is manufactured by Ellimetal while Stork Mammoet moved seven separation towers with a tion decreases, as does the NOX emission per Engineering & Contractors is responsible for the total length of 420 metres from the container plat- tonne ethylene. Other elements of the upgrade are train. In the vessel, propane and propene are form in the Braakmanhaven to the plant site, using a new separation train, cooling tower, control separated as they boil off at different tempera- SPMTs. The sections were between 100 and 160 room and infrastructure. tures. However, since these boiling points are tonnes each. The length and weight posed special constraints to the site movements and required very accurate operations. The total upgrading is valued at 1 billion guilders. The plant is expected to be operational in 2001.

Watch out! Low flying vessel…

Le Havre - Mammoet executed the transport and erection of a 280 tonne distillation tower for Esso S.A.F./Foster Wheeler in . The tower was offloaded by a heavy lift vessel at Port Jerome and temporarily stored just on the quayside.

For transportation from the port to the refinery site, several piperacks with a clearance of just 150 mm. Mammoet mobilised two coupled gantry beams with a The column was positioned on four 150 tonne jacks at length of 40 metres, fixed on support stools around the a designated location. The transport beams were subse- tower. Two combinations of double 6-lines SPMTs fitted quently dismantled. In the meantime the SPMT trailers with two 350 tonne capacity turntables were intercon- were reconfigured into one double 12 axle line trailer. nected by two specially engineered T-frames for support- In addition the vessel was picked up by the hook of a ing the total construction. This solution may seem rather Demag CC2800 crawler crane fitted with a 54 metres complicated but was chosen to avoid the removal of low- mainboom and a 30 metres derrick. hanging piperacks at the refinery. The total transport combination measured 55 metres with a weight of A Demag AC1600 served the tailing frame that had been approximately 520 tonnes. At times it moved very close purpose-designed for this job. The lifting operation was to the ground to achieve the necessary height clearance. smooth and the vessels could be placed without any problems, notwithstanding the area being very confined The distillation tower was transported over the public as it was in the middle of a live refinery. Mammoet fin- road from Radicatel harbour to the Esso site in the Port ished the job with supporting the alignment and levelling Jerome industrial zone, a distance of six kilometres. of the column. Upon arrival the vessel was manoeuvred underneath

From Italy to Egypt

Cairo - Mammoet Italy, in close co-operation with Mammoet’s new subsidiary in Egypt, showed a perfect example of a “Factory to Foundation” job.

It comprised the transport, shipment onto the heavy lift ship Happy River, and lifting operation of two hydro- as representatives of Saga, Technip cracker reactors for customer and Palumbo Seafreight watched Daelim. Especially the extensive these operations. paper work in connection with this Upon arrival at the ves- project proved to be challenging. sels were transported to the site and However Mammoet Italy controls erected by the Mammoet Hydrajack every part of this process and can gantry system. really guarantee its existing and future customers a full door to door During a period of four months a heavy lift service, including all PC/CC 4200 crane was stationed required permits and other legal doc- at the refinery. This job was a first uments. The 750 tonne reactor ves- for our newly established legal entity sels were loaded in Porto Marghera in Egypt.

Mammoet World 2001 Page 5 At a different angle

Kleve - Winkels AG in Kleve is a regular user of Mammoet’s heavy lift services.

An interesting point in all the heavy transports that are At Karlsruhe the column was offloaded again and suc- being executed for this expert column manufacturing cessively brought to the Miro refinery in the same place. company, is that the river Rhine is always part of the The column was dressed at the site which resulted in a transport schedule. Also in this case the column measur- weight increase of 115 tonnes. The now 280 tonne ing 48 metres long and weighing 165 tonnes was moved Weighing process column was put upright by a CC2800 on SPMTs to the river bank of the Rhine where it was crawler crane and delivered onto its foundation in one transferred along a Nato ramp onto a Rhine barge. smooth and swift move.

About reactors and silos

Antwerp - Geldof Metaalconstructie manufactures silos for all kinds of industrial bulk goods, from granulate to cement and chemicals. In 1969 Geldof decided to switch its activi- ties from the flax industry to metal fabrication.

This marked the modest start to what Therefore they have decided to built eventually became an internationally the roof with the upperpart of the shell renowned company supporting a wide next to the tank and lift it at the end in range of products in carbon steel, one piece on top of the tank. For the stainless steel and other alloys. final assembly, Mammoet used two the in-house capability to design and The company serves customers all AC 650 cranes and installed the con- build storage tanks, pressure vessels, over the world in many different indus- struction quickly and safe. reactors and columns for oil refining trial sectors, ranging from petrochemi- Another remarkable fact was the and petrochemical industry. cal to car manufacturing, and from transport of a 80 tonne reactor vessel Geldof awarded the transportation water purification to waste processing. with a diameter of 9.5 metres and a contract to Mammoet. The vessel A good example of their outstanding length of 30 metres. was shipped by barge along the products is a tank for the storage of This installation had been produced Albertkanaal to . With police 15,000 tonnes of melasse which had by G&G International N.V. which is escort the reactor proceeded to the to be built in 9 weeks for Dagevos B.V. part of the Geldof group. It is one of destination area at Indaver, located in Wemeldinge, Zeeland. the world’s leading contractors, with on the left bank in Antwerp.

MAMMOET AMERICA’S

A lift to remember

Fort McMurray - Syncrude is Canada’s largest single source of crude oil and the world’s largest producer of crude oil from oil sands. To do this, Syncrude mines oil sand from a sur- face mine. The raw oil, or bitumen, is extracted from the sand with steam and hot water. Then, it is upgraded to crude oil by fluid coking, hydroprocessing, hydrotreating and reblending.

The final product is dispatched down reactor vessel. The MSG 50 was win- On the first scheduled date, the lift a pipeline to refineries and terminals terised in order to operate under bit- had to be posponed because of the in the Edmonton area, and for ship- ter cold winter circumstances at tem- heavy wind pressure”. Nick Deeg ment down pipelines to refineries in peratures below 30 degrees Celsius. explains the green signal for the lift- Canada and the . Nick Deeg, project manager of the ing operation must be given well in The main site is located at Mildred Bitumen Conversion Resource Team advance as the various disciplines Lake, 40 kilometres north of Fort specifies the other factors, which should have enough time to prepare McMurray in Alberta and about 500 play an important role regarding the themselves. On the second sched- kilometres northeast of Edmonton. “go” or “no go” of starting the lift. uled date, the wind was calm and the sun rose slowly above the horizon, Mammoet’s containerised lifting “The exchange of this reactor vessel shining a golden light on the MSG 50 device, MSG 50, was contracted for is engineered to the smallest details. and the reactor vessel. several lifts at Syncrude’s processing The lifting plan as prepared by The Mammoet crew had no eye for plant. These lifts were carried out Mammoet is very detailed and it that scene, being busy with the mat- while the plant was in operation, so shows that the crane is working with ing of the vessel. “A good perfor- safety and precise lifting engineering much better specs than originally mance, well prepared and much were of utmost importance. The designed for. Obviously this has faster accomplished than anticipated”, Mammoet crane was equipped with a already been investigated a long time is the comment of a tired but fully 43 metre jib on top of a 62 metre ago, because working at a live plant satisfied project manager. Around main boom to obtain the required incurs its own problems and can be noon the reactor is firmly secured to 74.6 metre radius which was needed challenging at times. Apart from the the rest of the installation and another for the most important part of the temperature, the wind force is a deci- mile stone has been reached in the project: the exchange of a 620 tonne sion factor as well. Coker 8-1 Stretch project.

Mammoet World 2001 Page 6 Maarten de Graaf looks back on an eventful year

De Meern - Between Christmas and New Years Eve, Maarten de Graaf, Senior Project Manager of Mammoet, found some time to look back on last years operations he was involved with.

at different areas on the site. tracks. It will join another CC 4800 Therefore, the PTC was equipped there in assembling 1200 tonnes with crawlers as to facilitate site vessels that come in pieces by rail moving to seven different locations. from , and finally lift the com- This was a novelty for the PTC and pleted structures into place.” proved this concept offers much versatility in operation flexibility. A special challenge was to fit the PTC with a jib that was moved in separately. With the jib added, the PTC had increased capacity to han- Irving Oil Refinery dle the heaviest and highest loads of the project. Adaptations and testing was done at the site and effectively “To start, I was involved with the supported by Irving. project we did for the Irving Oil refin- ery at Saint John, New Brunswick. The PTC operated almost a full year This project started last year and at this site, in tandem with a CC was completed at the end of 2000. 4800 crane. Right now, the PTC is Over 200 items ranging from 50 on the move again, heading for tonnes to 570 tonnes were installed Alberta, some 5000 km down the

Suncor Energy

“Besides the project for Irving Oil improvisation was needed to refinery, we just completed a major continue the operations. project for Suncor Energy at Ft. As we arrived on the site near McMurray, Alberta.The versatility of Edmonton, the temperature dropped the 4800 Twin Ring Light Duty con- to minus 48 degrees Celsius, essen- cept was be proved once more tially freezing the hydraulic systems. accompanied by a CC 4800 to We needed two days to heat the install four coke drums of 480 equipment and restore the opera- tonnes each. tional status. During the operations, we could continue our activities to The CC 4800 also performed many temperatures as low as minus 40. other lifts, just as an LR 1250 that assisted in tailing operations. The Etarco Mammoet Western was on customer defined strict constraints this project involved with the trans- to the site movements, which came port of 485 modules up to 30 metres down to the requirement to move all long, 7.3 metres wide and 7.3 metres loads with the same crane configu- high. The 147,4 tonne modules and ration, i.e. with jib. If you never were transported from Edmonton to worked in such harsh conditions, Suncor, a distance of 500 km, during it is hard to imagine what kind of October to December 2000.”

Test PTC II

“At the end of 2000, we started with the assembling and testing of our second PTC crane. The testing is done according to the US ANSI standards. This is necessary for each crane that evolves to a pro- duction series after the prototype. I expect this second crane to join operations early in 2001.”

Mammoet World 2001 Page 7 Two Alstom projects

Rosarito/Hermosillo - Alstom Power, Baden, Switzerland contracted Etarco de Mexico to develop and execute the logistics plan to move super heavy items like turbines (230 tonnes), generators (325 tonnes) and transformers (220 tonnes) from North American of entry to the sites in Rosarito and Hermosillo, Mexico.

The Hermosillo project was rather to the Port of San Diego. could handle the pieces, while the rail simple. It required receiving items at They were the largest pieces ever tracks needed some adjustments. the Guaymas Port onto 18 lines of handled in Southern California. These two projects occurred at the hydraulic trailers. The transport dis- The next step was to load the items same time, and Mammoet delivered tance from there on is some 200 on 24 lines of SPMTs, followed by all 9 pieces exactly on time, as kilometres. Mammoet only had to transloading onto rail cars for the scheduled some 4 months prior modify seven bridge structures 25 kilometre shipment to Tijuana, to shipment. and applied jacking and skidding Mexico, and subsequent trans- systems. loading on 24 lines of hydraulic trail- ers for the 30 kilometre highway The Rosarito Project offered more drive to the job site. challenges. The customer assumed a process that involved a barge, To achieve all this, Mammoet engi- meaning a great risk in managing neered studies of the port piers, rail the surf and spray water. tracks and Mexican highway infra- Mammoet dispatched the items structures. It appeared the piers

MAMMOET AMERICA’S

From the Houston harbour to the Exxon Baytown Refinery

Baytown TX - Mammoet transported a 475 tonne reactor from the Houston harbour to the Exxon Baytown Refinery for our customer, Fluor Daniel Inc.

The reactor is part of the off-site the reactor onto the platform. required. At exactly 2 p.m. the section of the Delayed Coker Everything was secured thoroughly. trailer turned through the gate Project, which is being implemented The following day the reactor was into the refinery. in this refinery. Built in Spain, this tranferred over Exxon’s own dock in reactor was delivered to the Houston Baytown. Thursday and Friday were The following afternoon the SPMTs harbour by BigLift Shipping on reserved for further preparation of were delivered, assembled and the Wednesday, 29 November. the route. At 9 a.m. on Monday reactor was transferred to a dual morning the green light was given 12-axle line vehicle. On Wednesday Mammoet had prepared a platform to move from the Exxon site to the morning it was driven to its final holding using a 16-axle-line public road. At 10:30 a.m. our new position. It was then jacked up more Goldhofer. However, due to a delay Kenworth C 500 (its first job since than a metre and unloaded. in the construction of the reactor, its arrival in the States) hauled the the decision was made to transport Goldhofer onto the road. it to Baytown on conventional trail- ers rather than SPMTs. The route was approximately 5 km long. The most difficult section was The latter were not available due to an S bend over a railway line. the PEMEX load-outs in Mexico. This was one of two points where Shipping cranes were used to load a second haulage vehicle was

Heavy transport in Venezuela

Puerto La Cruz - An impressive transport operation was car- ried out by Mammoet Venezuela for the construction of the gas upstream facilities for Accroven (ENRON/Canadian Gas).

The total transport contract consisted Three MAN trucks with 400 HP were of over 20 modules and vessels. needed to pass this difficult part of the 300 km transport route. The pictures show the largest col- umn for the upstream facilities in The heaviest columns of this project Santa Barbara (eastern area of were 250 and 210 tonnes delivered Venezuela) and weighs 170 tonnes. in Jose and lifted by Mammoet The columns moved by 2 x 8 lines Venezuela. Scheuerle had to overcome a small mountain with 10% slope.

Mammoet World 2001 Page 8 MAMMOET MIDDLE EAST

Mammoet in Iran

Dubai - Currently, Mammoet Middle East is executing advanced operations for the South Pars Gas Field in Iran. The contract was won from Hyundai Engineering & Construction and involved the transport and erection of heavy, oversized elements for a new gas processing plant.

In fact, the operations call for 156 are no port facilities in Iran, all heavy extremely bad weather conditions lifts from a number of shipments, items from Korea, and Italy have caused delays in the ro/ro- the storage of items, loading onto are shipped to the Emirates. operations. Moreover, we had to , sailing from Dubai to Iran, They arrive in Port Rashid and Jebel lift some items from the pontoon site transportation and delivering the Ali Port in Dubai. From Port Rashid, due to weather constrains. Once on items on foundations supported by the items are transported overland land, we moved the items over cranes. The operations are co-ordi- to Jebel Ali where they are to be almost 3 kilometres over a special nated out of Dubai, which is quite a loaded onto pontoons. These pon- heavy duty road.” demanding task as it covers 36,000 toons cross the Arabian Gulf to tonnes of cargo with individual lifts Assaluyeh in Iran.” The transportation part takes about up to 300 tonnes. four months, while the cranage part Robin emphasises the difficult logis- is scheduled to last six months. Robin Koenis is commercial manag- tics in this project. “Most items orig- Mammoet has eight cranes avail- er for Mammoet Middle East in inate from Korea, such as 300 tonne able. Among them a 600 tonne Dubai and he says the South Pars heavy boilers. But turbines come crawler crane, two 450 tonne cranes Field is the largest of its kind in from Italy and Germany. Upon their and several cranes of the 60 tonne the world. “We are now up and run- arrival in Port Rashid, we receive class. The 600 tonne crane is to be ning for phase 2 and 3 of the Total them and store the cargo on a tem- operated in the maximum configura- South Pars project. However, the porary site. We take care for cus- tion (84 metres main boom and construction site is very isolated and toms clearing and port handling. 84 metres jib) when installing a flare it takes two days out of Dubai to get If we have enough heavy items, we stack. Robin Koenis expects more there, including boarding old load a pontoon. In Assaluyeh we commercial spin-off from Mammoets Russian planes and a five hour drive unload the cargo via a specially pre- presence on the site, as work is through a rocky dessert. Since there pared jetty. Unfortunately the in progress.

MAMMOET Malaysia and Thailand ASIA

“Malaysia and Thailand expand their day market activities with telescopic cranes”.

Traditionally Van Seumeren and At the moment Mammoet Romstar Currently a 200 tonne and a 500 Walter Wright Mammoet operated Sdn Bhd in Malaysia operates the tonne AT crane are on the move only ringer and crawler cranes dur- following telescopic cranes from it’s to Malaysia to compliment this fleet. ing the last two decades in Asia. depot’s in Kuala Lumpur and However since the construction Kuantan: For Thailand we recently purchased of large plants was significantly 10 RT telescopic cranes a 400 ton LTM 1400. The crane will reduced after the Asian economic 3 truckmounted telescopic cranes stay in Thailand where it will be crisis, the Mammoet Management 3 AT telescopic cranes used for day market activities. decided to set up a telescopic crane 1 AT telescopic crane depot in Malaysia to ensure continu- 1 AT telescopic crane ity of our Malaysian services.

MAMMOET EUROPE Mammoet Trading

Following the integration of Mammoet and Van Seumeren, the through which we can offer a full range of services to our Development department. The crane was acquired in Russia trade department has been renamed into Mammoet Trading. customers” and is now on it’s way to a new owner. This Department, covering the third core business after projects In order to strengthen the sales capacity, Wally Beldon joined In the future Mammoet Trading aims at buying and selling and crane rental, is responsible for all purchasing, upgrading Mammoet Trading and will be responsible for the UK and the of equipment from other companies as well. It will further and reselling of crane, transport and other equipment. Its ambi- America’s. His focus will be on creating a new customer port- enhance the market leader position. Parallel to this, training tion is to broaden the scope and to focus on markets that folio by personal contacts. Although the fleet integration is a of staff as to increase skills, market knowledge and technical require good quality used-equipment. During the past months, demanding job, the trade business went on. “Business as know-how is of utmost importance. It enables to support a large number of cranes has been sold as to optimise the inte- usual I would say. We spot cranes and other equipment, apply customers in their decision making process. grated fleets. “Most of what the two companies had to offer a complete overhaul and guarantee to our customer that the For details of the actual sales inventory please check our was complementary” says Jan van Seumeren Jr. equipment is operational and safe, in accordance with our own website: www.mammoet.com or contact “But we managed to restructure this fleet quite efficiently. safety standards.” As an example, Mammoet refurbished a Jan van Seumeren Sr. ([email protected]), It put a lot of pressure on the sales network. With the acquisi- TC 2000 Demag crane and serviced its engines, axles and Jan van Seumeren Jr. ([email protected]) tion of Mammoet we now have a global network of offices hydraulics, in co-operation with the Mammoet Product or Wally Beldon ([email protected])

Mammoet Fleet New equipment that has been added to the Mammoet fleet in 2000:

10 LTM 1055 Liebherr telescopic cranes 5 AC 50/1 Demag telescopic cranes 8 GMK 4075 Grove telescopic cranes 1 GMK 5100 Grove telescopic crane 10 Sennebogen 5500 crawler cranes 1 CK 2500 Kobelco crawler crane 3 Manitowoc 999 crawler cranes Various trucks and transport trailers

Mammoet World 2001 Page 9 Civil

MAMMOET EUROPE

It’s a boat… it’s a house… it’s a silo… it’s Mammoet!!!

Schiedam - Recently our employees of the Mammoet Office in Schiedam saw something different pass by than just the familiar seagulls. A yacht weighing 160 tonnes and measuring 35 metres in length out of the water into a barge with two AC 650’s.

The yacht, which had been built by the Croatian shipyard “Heli Yachts”, sailed to the Netherlands to partici- pate in a boat show. The boat show was, however, in Düsseldorf (Germany), and as the sailing masts were too high, the yacht could not reach that destination along the inland waterways.

Moerdijk - Unirice at Moerdijk, To get the yacht to the show, the The Netherlands, recently took over masts were removed in Schiedam two large rice silos from Oryza B.V. and the yacht was lifted into our own at Zwijndrecht. By purchasing these “Europa 1” barge. silos Unirice can expand its produc- Upon arrival in Düsseldorf the barge tion capacity. The larger silo is 35 opened at the bow and the yacht was metres high and can hold 1600 rolled onto the quay with a 12 axle tonnes of rice. When empty the silo Goldhofer trailer and heavy transport weighs 200 tonnes. The smaller one truck. A ballast tractor provided the is 25 metres high and weighs 22 necessary extra traction as to climb tonnes. It was apparently a suitable the ramp to the Messe of Düsseldorf. job for heavy lift expert Mammoet who shipped both silos in one go. We hope that after all these efforts, At Zwijndrecht the silos were raised the Croatian shipyard will find poten- from their foundations and subse- tial buyers for their product! quently driven onto a pontoon. The large silo was transported on computer controlled self-propelled platform trailers on 88 wheels. The smaller silo was moved on a conventional platform trailer towed by a prime mover. After completing the shipment to Moerdijk the silos were driven off the pontoon and transport- ed over one kilometre on a public road before they reached the Unirice premises. There they were off-loaded and placed onto foundations.

Lent - Mammoet was awarded a contracted by Bresser/Van ’t Wout for the transportation of a house over a distance of 100 metres. The house was 11 metres long, 8 metres high and 11 metres wide. It had an esti- mated weight of 300 tonnes. Despite the fact that the house was only four Groningen - The most appealing cleared and reinforced. Then the years old, it had to moved because it “house” movement in 2000 was the entire building was jacked up 1.5 stood in the way of a new housing temporary removal of a “fin de metre. This gave the opportunity to project. A heavy foundation was siecle” building, part of an already position 2 x 16 axle lines of SPMTs placed under the house to facilitate demolished gas factory in the centre under the building. A lot of brass the jack-up and transport. Mammoet of the city of Groningen, The was present to watch this attractive used 2 x 10 axle-lines of self-pro- Netherlands. It had to be moved Mammoet performance, topped at pelled modular platform trailers. To over a distance of 100 metres in the end by making a carrousel wise prove the smoothness of the ride, a order to clean the soil in accordance manoeuvre before the 500 tonne bottle of champagne and two glass- with legal environmental require- structure was parked at es were placed on the house. It all ments. The soil around the shed was a temporary location. In three years arrived on the new location without excavated to a depth of one metre, the building will be moved back any damage. Nobody recalls what after which the foundation could be again to its original location. happened then with the bottle…

Mammoet World 2001 Page 10 Flower Power

Aalsmeer - The famous flower auction has now a new connecting structure between the old auction building and the new transport & dispatch centre at the opposite site of the street.

It is called the Aalsmeer shuttle and They are constructed out of con- from the jacks. The actual transport consists of eight sections. Under a crete on a dedicated construction was done on Saturday mornings, a contract awarded by the contractor site. When ready, each 400 tonnes lull in the busy weekly activities of combination Voormolen, Mammoet structure was jacked to an elevation the auction. As usual, the transport transported these sections and posi- of 6 metres, the level for its final attracted crowds to watch the mil- tioned them in place in a time frame mating to the overall structure. limetre precise operations. of six months, using SPMTs. The elements are 27.5 metres long, The platform trailers moved under 6 metres wide and 12 metres high. the structure and took over the load

Cranage at various levels

Heerma bridge

Amsterdam - Mammoet executed some eye catching lifting operations for a double bridge construction that connects the isle of Zeeburg with the new suburban area IJburg. The bridge is called Enneus Heerma bridge, after the late christian democrate politician, alderman and Secretary of State, who did much to the benefit of Amsterdam. The bridge is the most important traffic link to the A10 highway.

The architecture of the bridge is However, the place is inaccessible fascinating and shows a styled for floating cranes due to insufficient S-shape. The length is 230 metres, clearance with the bottom of the it is 38 metres wide and 26 metres lake. So pontoons came to the res- high. The bridge parts were manu- cue, accommodating the crawler factured in Schiedam. Both there cranes. It is expected the Heerma and in Amsterdam, Mammoet bridge will be commissioned as of cranes assisted in the assembly mid 2001. By then, the development of the bridge. in the reclaimed area can get in full swing as cars and trucks have A highlight was the installation of access to the isles. the bridge bows with a PC 4200 in the lead. It called for two operation sequences. In each one, a bow was assembled from three parts.

The outer bows come to 160 tonnes but the middle bow has a weight of 240 tonnes. Framework between the bows delivered extra strength. A complicating factor was that the lifting position was in the water.

Highest point for World Port Center

Rotterdam - On Saturday 9 September 2000, Mammoet lifted a light pole onto the roof of the World Port Center, under construction at the “Kop van Zuid” in Rotterdam.

The operations were executed by one of the largest mobile cranes in The Netherlands, a Demag AC 650 with a main boom of more than 150 metres. The light pole fits in a design by Lord Norman Foster. Lifting at level At its top is a special light construc- tion with 24 lamps, that will be an Rotterdam - Early on Sunday, 23 July eye catcher even far from 2000, the activities started in the cen- Rotterdam. The mast is made of a ter of Rotterdam to assemble an AC steel pipe construction, weighing 650 telescope crane, fitted with a jib. 4.5 tonnes. It was delivered on top This was in preparation for the change of the building in two sections. out of a cooling unit on the roof of the According to the constructor, Shell building located at the Hofplein. the WPC, has 33 levels and offers Access to the unit came after a large 42,000 square metres of office hatch was removed. It cleared the way space. to get the two old units out and lower the two new units in place. As expect- At printing of this issue, the buil- ed, the 145 metres high crane attract- ding just has been commissioned ed quite a crowd. At noon, the show and is taking its position in the sky- was over and disassembly of the line of Rotterdam. crane was in progress.

Mammoet World 2001 Page 11 A tree is known by its fruit

Oss - Kaal Mastenfabriek B.V. is a renowned Dutch manufacturer of poles and masts, such as light poles, advertising masts and traffic portals.

Recently, it presented the first mobile telephone Mobile telecommunications is worldwide an those of ‘naked masts’. The artificial pine trees mast, disguised as a … pine tree! unprecedented booming market. Many countries have been planted already in South Africa and It is a prototype, imported from South Africa. have the masts sprouting almost like weeds to the US. Kaal Mastenfabriek is optimistic about Mammoet assisted in the assembly by providing catch up with the market needs. Usualy the mast the market prospects and already thinks in terms a 50 tonnes telescopic crane with 38 metres boom construction is dominating the area and they often of a forest… to deliver the tree on its position. The result is fas- look ugly. This is why our customer now presents cinating: a tree with 1.6 million needles, almost an alternative: the tree-mast. As for the trees indistinghuisable from a real tree. fruits: their transmission qualities are equal to

First class bridge travel

Ladbergen - Mammoet was involved in a spectacular transport operation in Ladbergen, Germany. The objective was to position a 900 tonne bridge over the Dortmund/Ems canal. This bridge is 104 metres long and 20 metres wide. It replaced an old bridge that became a bottleneck as the A1 highway Dortmund - Bremen was expanded from two to three lanes.

The bridge was completely pre- made along the transport route. ble width 12 axle SPMTs. By the end assembled on land and was The actual transport started in the of this longitudinal movement, the launched over the canal using early morning at 06.00 hours. SPMTs had reached a specially KAMAG Self Propelled Modular The first leg was to drive the bridge designed construction at the quay. Trailers (SPMTs) in combination forwards to bring the SPMTs under The bridge was placed on that tem- with a pontoon. the leading end of the bridge onto porarily. It should be noted that dur- the pontoon. As the weight crossed ing this operation the gap between Prior to the actual transportation, onto the pontoon, it was necessary the bridge placed last year, was only meticulous preparations were neces- to constantly ballast in order to 8 cm. The third phase was to lower sary. The bridge was built on four maintain level. the bridge onto four 4m high jacking support towers with lateral transport stacks (timber grillages) positioned beams. At the leading end of the Supports were then placed on the on the land. Each stack had a 600 bridge, two 6 axle lines and two 8 pontoon onto which the leading end tonne capacity climbing jack. axle lines SPMTs were inserted. of the bridge was lowered. The trailing end was supported with This allowed the removal of the They were extended as the pontoon a double set of 12 axle line SPMTs. SPMTs and the ramps. was ballasted down and the SPMTs After closing the canal for shipping, Now, the second phase started: on the trailing end of the bridge the pontoon was brought into posi- moving the bridge across the canal. were completely lowered. This tion during the night at the quay and This was accomplished by pulling translocated the weight completely moored with winches. Steel ramps the pontoon across the canal with onto the land based supports, allow- were used to span to the quayside. the mooring winches. At the same ing the pontoon (with SPMTs) to be With the bridge load taken on the time the trailing end of the bridge removed. After that the bridge could SPMTs, the final preparations were drove towards the canal on the dou- be lowered onto its final foundation.

Bridges for trains, trams and pedestrians

Halle - Mammoet Deutschland and bridge construction are like bread and butter. Two rail tracks bridges were installed at the end of last year: one close to the Central Station, bridging a busy street in the center of Halle and another one over the river Saale.

The bridge close to the Central antipated weight of 77 tonnes. long pylon and other accessories Station consisted of two main parts The AC 650 main boom measured up to 50 tonnes at a 40 metre of 34 metres long, 5.5 metres wide 19.5 metres in this lifting configura- radius. To lift a number of elements and each weighing 120 tonnes. tion and was extended by a 36 for the middle section of the bridge As the road would be blocked during metre long luffing jib. The counter the LTM 1080 was placed on a pon- the lifting operation a Mammoet ballast weighed 160 tonnes. toon and used in that way as a float- Demag AC 650 was built up in a Because of the overweight of 8 ing derrick. The prefabricated bridge very tight time schedule with a tonnes for each concrete beam the elements were loaded down the 30.5 metres long mainboom and weight limit was waived in consulta- river on a third barge and by means 140 tonnes of counter ballast. tion of Demag’s engineering depart- of delicate manouvering of the In spite of the absence of the super- ment. Another factor was the weak barges and precision lifting work lift attachment - the confined work- subsoil: this was solved by inserting of the LTM 1080, the middle sec- ing prevented the use of it - both 20 metre long pylons under the tions of up to 15 tonnes were pos- steel structures were smoothly crane supports. tioned according to schedule and picked off the trailers and carefully Herewith the 200 tonne offset was welded. brought into position on the sup- coped with and the stability of the ports at a radius of 15 metres. crane guaranteed. The final mounting of the pylon cables required three Mammoet The same AC 650 was used in a dif- In spring 2000 a pedestrian bridge cranes working together: an AC 180, ferent configuration to install four was installed in Halle over the river an AC 120 and a KMK 5110. concrete beams being the main Saale, again with the AC 650 assist- frame of a new light rail bridge, each ed by the LTM 1080. During the lift- with a length of 34 metres and as ing operations various elements appeared a slightly higher than were assembled such as a 40 metre

Mammoet World 2001 Page 12 MAMMOET AMERICA’S

Miller Park Stadium

Milwaukee - During recent years Mammoet gained a lot of experience in constructing large stadiums. After de Amsterdam ArenA, home to the famous soccer club AFC , the PSV Philips Stadium in Eindhoven, the Feyenoord Kuip (‘The Bowl’) stadium in Rotterdam, the Netherlands, and the Louzniki Olympic Stadium in Moscow, Russia, the focus is now on Miller Park in Milwaukee, USA. This stadium is the new home for the Milwaukee Brewers Baseball Club.

Perhaps the most modern and tech- while having a weight of 270 tonnes engineer who could calculate every nologically advanced aspect of Miller including hook, slings and the spe- move we wanted to make. This is Park is also its most eye catching. cial in-house designed adjustable really important, since we deal with The stadium has the only fan-shaped sling. Although the centre of gravity voluminous sections that can catch retractable roof in . It’s of the roof section has been calculat- wind loads as well”. seven-panel roof weighs about ed in advance, the adjustable slings What was most remarkable to him? 12,000 tonnes and takes approxi- allow for real-time corrections due to “It was quite a different experience. mately 10 minutes to open or to small offsets. This feature shortens On a refinery you have no perception close. This feature will allow Miller the lifting operations and enhances of what is going on outside your Park to have a natural grass playing the safety level as well. working area. But here you’re in the field inside its building. middle of the news, with lots of Frans van Seumeren Jr., was press coverage. There was hardly Mitsubishi Heavy Industries awarded assigned to this site for almost a a day without an article in the local Mammoet the contract to install a year. He recalls some events. “We newspapers. I think the project con- total of 30 items, including seven had to assemble the movable roof, tributed to our corporate image to large roof elements. Mammoet which consisted of many 300 tonnes a broad audience in a very effective assigned the biggest single body sections. They were manufactured way” says Frans van Seumeren Jr. crawler crane in the world to this on the site and we lifted them into project. The Demag CC 12600, with position with the CC 12600. Our The Miller Park is now completed a lifting capacity of 1600 tonnes, was crane had a 90 metres main boom and is one of the heaviest structures already in the area for Foster and 72 metres jib. This enabled us in Wisconsin weighing about 500,000 Wheeler at the Port Arthur, Texas, to safely cover the 70 metres radius tonnes. This includes 25 miles of site. The giant lifted the first roof ele- between the crane and the load.” deep piles, 70,000 cubic yards of ment at the beginning of 2000. This Frans said that safety was guaran- structural concrete, roughly 4,600 roof section had a length of 44 teed during the execution of this pro- pieces of pre-cast concrete and metres and a width of 10 metres, ject. “We could count on our own 24,000 tonnes of structural steel.

Railway bridge installed

Montreal - Etarco Mammoet recently replaced a complete railway bridge in Montreal (Quebec). One added difficulty was that the complicated operation had to be carried out within 24 hours above the fast-flowing Canadian St. Lawrence river.

The new bridge was constructed in tioned in the right place between the railway bridge. The old bridge ele- two parts, one large and another two pillars and anchored. ments were lifted away in reverse slightly smaller. SPMTs (Kamags) The bridge parts could then be lifted order with the jacking system and were used to transport the parts on up with our newly developed jacking the Kamags, after which the old pontoons, for which two sets of 10 system and placed on the pontoons. bridge could be demolished. axle lines were deployed. They rotat- The old bridge was then lifted with The complicated operation was car- ed the bridge parts through ninety the SPMTs and deposited on the ried out within the deadline of 24 degrees on the pontoons, after back of the pontoons. Now the way hours, so that the line could be which both pontoons could be posi- was clear for positioning the new opened once more for rail traffic. Tunis Rades Stadium

Tunisia - Mammoet Fostrans our joint venture in France, was involved through its client Hyundai Eng. Constr. in the erection of the roof and supporting pylons.

Two LR 1450 cranes with superlift and Manitowoc 888 were used from outside the stadium for lifting large roof sections and 8 x 120 tonnes pylons and pendants.

The project was carried out successfully over a period of 6 months early in 2000.

When ready the Tunis Rades Stadium can accommodate 65,000 visitors.

Mammoet World 2001 Page 13 Offshore

MAMMOET EUROPE

Mammoet dedicated to offshore

Mammoet’s experience in providing a complete range of services for the off- offshore industry. The full scope of heavy lift services includes site moves, shore manufacturing industry dates from the seventies. A wealth of practical load-outs and load-ins, weighing, mooring, ballasting, tailor-made heavy lift know-how has been gained and is acknowledged by the major players in the solutions, crane rental and complementary services.

Heimdal riser

Vlissingen - Heerema Havenbedrijf B.V. set a personal company record when it finished a 5,722 tonnes heavy and 145 metres long jacket for the Heimdal riser platform.

It is also a record in terms of The complex is runned and man- was ready early 2000. On 30 March, required transport capacity. During aged by Norsk Hydro. In September the load-out onto a barge the nine months construction period, 1998, Heerema Havenbedrijf B.V. (160 x 42 x 10.6 metres) was carried Mammoet cranes provided assis- won the contract for the design and out. It required incoming tide, as tance. But at the end, the completed manufacturing of the jacket, which is well as 234 axle lines of SPMTs with structure had to be loaded out onto the lower part of the riser platform. 936 wheels to drive the jacket on the a going barge. The Heimdal The company is a member of the barge. Mammoet used 30 ballasting platform is an extension to an exist- Heerema Fabrication Group. Another pumps additional to the barge stan- ing production platform for natural Heerema company, Tønsberg from dard equipment, as to balance the gas in the North Sea. It is to be , provided the top side. stack carefully. connected to the main platform The design was completed by Shortly after fastening, the jacket set with a bridge. August 1999 and the construction sail for the North Sea.

Wintershall

Zwijndrecht - Another major load-out onto a sea going barge took place at Grootint, Zwijndrecht (The Netherlands). The structure, an offshore platform (L8-P4), rolled onto the barge on top of 104 axle lines SPMTs with 416 wheels.

The transport started in the assembly inhouse developped and advanced The Heerema load-out from Vlissingen hall. According to Grootint, the gas computer managed ballasting system. was a good rehearsal for this giant processing platform has been This facilitates very accurate opera- work. Also the Snorre B project in designed and manufactured in a tions, necessary for both load-outs on Norway is still on my mind, as we record 52 weeks. It is to support a wheels and by skidding. The system jacked five modules of 5,000 tonnes daily production of 6 million cubic monitors the content of the ballast each to an elevation of 4.5 metres. metres natural gas from the Dutch tanks and drives the pumps that can This would have been very difficult sector of the Continental Plateau. bring in or out up to 1,300 cubic without our smart-jack system, which The operator is Wintershall. metres of water per hour. All piping is computer operated and counts for Ludo Mous was responsible for the has been made of plastics and are 16 jacking units, each with 600 tonnes Mammoet load-out. As a project man- quite easy to handle. Moreover, all lifting capacity. Each move of the jack ager he recognises great synergy equipment fits nicely in 20 ft open top is monitored closely. The load gets up potential within the new Mammoet containers.” in a very controlled and thus safe company. “We can now mobilise 600 Mous recalls some other intriguing way.” Right now, Mous is involved in axle lines SPMTs with a total capacity load-outs in 2000. “To us, the top of the preparations of yet a bigger load- of 19,000 tonnes. This means that we the bill is the load-out of the out of an almost 12,000 tonnes plat- can achieve super heavy load-outs Shearwater deck, which set a world form. The site move and load-out is with our own equipment and are no record. The weight was 11,772 tonnes scheduled for 2002 and 2003. longer dependent on the availability of and we used 1,704 wheels to move third parties. In addition, we have our it on the Amec yard in Wallsend, UK.

Mammoet World 2001 Page 14 Snorre B project

Stord/Egersund - Major heavy lift operations were executed last year for the construction of an oil production platform in Norway. At Aker Stord various jacking-, site moves- and load-out operations were executed in various stages.

Three separate parts for a utility At Leirvik Sveis on Stord, a living Complicating factors were the 4 module were loaded in and put down quarter was built and loaded out onto metres high supports on the Kamags on the Aker Stord yard, so that these a barge and shipped to Aker Stord and the delicate jacking operations. could be assembled to one module. The 3,850 tonne module was lifted to a height of 3.4 metres with twelve jacks and then loaded out onto two barges. A drilling module was jacked to a height of 0.6 metres on a barge before loading in. This module was put down on the quay on twelve pre- installed jacks and raised 2.8 metres. By then, the 4,750 tonne module was loaded out onto the two barges, matching the already placed utility module.

At Kvaerner Egersund a 4,250 tonne process module was moved on the for load-in. This was folllowed by a Also the barges had to be ballasted site and after final construction site move to the end of the dock simultanuously to keep them level loaded out onto an ocean going before another load out onto a dock during the load-out operations. barge. The 950 tonne weighing P50 barge. The 1,600 tonne living quarter Together all units will form one module was moved from the con- was rotated 90 degrees on the barge 25,000 tonne heavy platform which struction hall to the quay side and for perfect matching and lining later will be operational for the winning loaded out onto a barge afterwards. on for intergration with the deck. of oil and gas in the Norway waters.

Heaviest offshore structure ever moved on wheels

Newcastle - A record setting transport operation started at Amec’s Wallsend yard on the river Tyne in North East England.

An 11 million 772 thousand kilos of 1,704 SPMT wheels were in place (11,772 tonnes) weighing integrated under the structure to perform the offshore deck - 70m long and 63m site move that included a 90 high - was moved on 426 axle lines degrees rotation to align with the of self-propelled modular trans- load-out ramp and barge. porters (SPMTs). Mammoet wheeled Mammoet’s SPMT transport system the giant from the construction yard requires a minimum of space during via roll-on/roll-off ramps onto a these kind of operations, making it seagoing barge that was later towed versatile and efficient at any (con- out to Central North Sea, 200 km off fined) construction location. the Scottish Port of Aberdeen. The one-man operated steering has The combined process plant and proved again to be a very precise living platform is the biggest oil and way of moving extreme heavy loads. gas construction platform ever The 4- and 6-axle lines units, with a moved on wheels. It has been built payload of 30 tonnes per axle line, for the Shearwater Development, can be coupled in many different operated by Shell with Esso, Arco ways to accommodate the weight and Mobil as co-venturers. A total and size of the load.

Multi crane lift Pemex Canterall EPC-1 Project

Port of Iberia - For client Omega Natchiq Industries Inc. a 500 tonne to provide 270 lines of SPMTs, deck was lifted by six cranes simulta- besides hydraulic ballasting sys- neously. The Mammoet CC 4000 was tems, including the full monitoring the main crane in this spectacular lift- package and all necessary steel ing operation for stacking two decks. works and ro -ro ramps. The first load out was executed on The deck was picked up and when December 4th 2000, with the sec- the required elevation was reached, ond module on the 15th December all six crawlers cranes moved side- Mexico - The Pemex Canterall EPC- 2000. The 3rd and 4th modules are ways to position the deck over the 1 contract was awarded by Brown & to follow mid March 2001. Darren lower floor. Just a few weeks later, Root Houston, Texas, to Mammoet Adams, Director of Global Transport, a third deck was installed on top. back in September 1999. The work stated that this first wheeled load Prior to the lifts, Mammoet had involved the design, provision, out carried out in the Brown & Root already jacked the lower platform installation and operation of a trans- yard, headed by Dennis Theis, went to about 3 metres and installed load portation and ballasting system. extremely well. spreaders for the final load-out with This would support the load out Mammoet’s SPMTs. onto barges of four Pemex EPC-1 modules, each weighing up to 6,500 Obviously, operations like these tonnes. Pemex EPC-1 consist of require great skills from both opera- two topside structures, named AC-2 tors and lifting supervisors. The and AC-3, each divided into two entire operation took only half a day modules. Mammoet was contracted to complete.

Mammoet World 2001 Page 15 Ports and Shipyards

MAMMOET EUROPE

Submarines on wheels

Rotterdam - One of the most media attractive loadouts of 2000 was the relocation of the submarines Zwaardvis (Swordfish) and Tijgerhaai (Tiger shark) on the premises of RDM at Rotterdam.

Upon arrival, the first 1,600 tonnes submarine was lowered into the water and towed to the dock ship Smit Explorer. The operation was closely monitored by RDM personnel, marking probably the last time they would ever see ‘their’ ship again. Meanwhile, prepa- rations for the second submarine RDM Technology Holding purchased were well under way. the ships back from the Ministry of Hydraulic jacks were used to elevate Defense, after they had been decom- the boat to accommodate the SMPTs missioned in 1995, completing quite under its belly. The transport required a history of service. 80 axle lines. Their next mission is to serve as training vessels and to show to inter- It was a breath taking view to see the ested people the working and living two rows of cars with their enormous condictions in a submarine. load moving slowly to the water front where the ship elevator was waiting Their new destination is in the Far again. At the same time, the crew East, to be reached by dock ship. of the Smit Explorer was busy to Before ‘boarding’ these ships, the manoeuvre their ship precisely submarines were to be carried by beneath the submarine, a demanding SPMTs of Mammoet to the special task that took quite some time. Three ship elevator on the yard. Distance tugs assisted and then later on the was no issue: the 80 metres were Tijgerhaai met its ‘brother in arms’. covered in less than 30 minutes. The voyage to a new future was on.

Odense Steel Shipyard

Odense - Last year, Odense Shipyard’s own was over- turned by a severe storm that passed through Odense on an unfortunate Friday.

Mammoet was called in to remove the wreckage In the meantime, a new overhead gantry crane in a minimum of time in order to continue ship- was ordered at M.T.F. in Germany. It was deliv- building as soon as possible. ered in separate parts to the Odense Shipyard. The Mammoet engineers calculated a salvage Again Mammoet was called in to assemble these operation with Mammoet’s MSG 50: this crane pieces into a complete overhead gantry crane. would remove the 1,550 tonne gantry crane in Currently, a Demag CC/PC 4200 is on the site, one spectacular lift. In addition, the remains as well as 52 axle lines of SPMT. The SPMTs are of the overhead gantry crane were lifted off the used to offload three 800 tonne weighing struc- ship and removed from the dock, after which the tures from barges. These three pieces are con- vessel under construction was accessible for the nected to each other again by using the SPMT workers again. For temporary lifting capacity trailers. The additional parts, like the bogies and Mammoet mobilised five of its high capacity lat- trollies, are assembled and attached with the tice boom crawler cranes, which were busy CC/PC 4200. At the same time the MSG lifting assisting the assembly of several newbuilding system is being assembled in a gantry configura- vessels during the year 2000. tion with a lift capacity of 5,200 tonnes.

Mammoet World 2001 Page 16 Expansion of Polish Shipyard

Szczecin - A shipyard in Szczecin, 420 tonnes respectively. Phase The entire operation was managed Poland, recently needed an extension two included lifting the main beam, by Mammoet Global, Rotterdam. of their gantry crane capabilities. weighing 660 tonnes. The beam It included shipping, assembly, lift- The shipyard produces around was 95 metres long and had to be ing, disassembly and the return 20 ships per year. To meet this chal- positioned at a height of 80 metres. shipment and took about ten weeks. lenge, a new dock and a new gantry Phase three called for the fitting crane was needed. Mammoet was two lifting trollies. awarded a contract for the assembly All lifting activities were carried out of the portal crane to be executed in by the Platform Twin Ring crane, three phases. Phase one consisted which could provide these services of lifting the legs weighing 250 and from one position.

Lower it steady and easy…

Bremen - At the Bremen Vulkan shipyard a complete 2,000 tonne overhead crane was lowered with an engineered gin pole version.

The MSG lifting device had been assembled up to a height of 104 metres. Four free-standing towers of containerised mast components, capable of lifting 4,200 tonnes, supported two lifting beams on top of four MSG strand jacks as to lower the massive crane in one smooth movement.

Gone with the cranes…

Lisbon - In order to upgrade seven harbour The supply of the barge and seafastening was cranes, ranging in weight from 300 to 670 tonnes, carried out by Entrepose. The third and fourth Mammoet Spain was contracted for their shipping phases of the contract included the site moves and transportation from the Maqueira Yard in of the cranes to their final locations. Lisbon to the Mitrena Yard in Setubal, approxi- mately 50 kilometres south of Lisbon. The customer was pleased with Mammoet’s per- formance as we found a solution to avoid crossing The contract was won together with Entrepose the original docks during the site transport. and called for excution in four phases. Phase one These docks were all occupied with ships under and two were the load-outs at the Maqueira Yard, repair. Lisnave, the new owner of the cranes, saw shipping to and load-ins at the Mitrena Yard, its waste in production time minimised. where the cranes were repaired and painted at a temporary location.

Extension of the Costa Classica

Mammoet Global was involved in the extension of the cruise ship Costa Classica in Birkenhead, England.

Birkenhead - The ship was cut into with a lifting capacity of 900 tonnes. 29 metres, the second piece could two pieces, after which a new sec- To reinforce the gantry system, four be moved underneath and placed on tion could be inserted. The cus- additional 100-tonne strand jacks the Mammoet sliding system that tomer, Cammell Laird, planned for were mounted on the ends and a was already in place. The top sec- that section to be built in a con- cross bracing was fitted lengthways tion was then lowered and fixed on struction workshop at the shipyard. between the towers. top of the lower section by welding As this workshop was not high it together. This completed the mid- enough to construct the section in The top section was transported on dle section of the ship. The second one piece, it was decided to build it two sets of 32 axle lines of Kamags phase for Mammoet was to slide in two parts. and two sets of 32 axle lines of the complete middle section, with Scheuerles. Once the sixteen lifting a weight of 6,500 tonnes, from its The first phase of the project was points had been attached to the top temporary location in front of the the assembly of the two parts, which section, the other part could be construction workshop to the was achieved in front of the con- hoisted up in the construction work- water front. struction workshop on a 5% shop. An important advantage of the descending slope. The MSG hoisting MSG hoisting system is the ability to system was installed with four 55- adjust the hoisting power of each metre high hoisting towers linked by strand jack individually. This keeps two gantry beams. Four top frames the tolerance of the deflection of the were mounted on each gantry beam, roof within the applicable norms. supporting eight strand jacks, each Once the top section had been lifted

Mammoet World 2001 Page 17 MAMMOET Ships on a vessel and trailers SOUTH AFRICA

Durban/Schiedam - Mammoet Southern Africa received a contract to weigh transport and ship two yachts overseas.

One boat measured 425 tonnes and cranes. The second yacht followed the other 452 tonnes. The yachts, the next day. ready for shipment on 12 December 2000, were fitted with cradles for the MS “Happy Buccaneer” headed for site transportation. The cradles were The Netherlands with the yachts as provided by the customer, allowing deck cargo. After arrival on Sunday, Mammoet to position the SPMTs 7 January 2001, the yachts were under the ships. After weighing, the loaded-in at the Mammoet Heavy first yacht was lifted and moved 250 Lift Terminal in the Rotterdam area. metres away for loading onboard the They were then towed to the the transfer at that site from the heavy lift vessel, ‘Happy Buccaneer’, Oceanco shipyard in Alblasserdam. boatlift to the assembly hall for their using the ship’s own 550 tonne Four 6-axle line SPMT units served finishing ‘touch’.

Cranage in South Africa

Cape Town - Mammoet Southern Africa was awarded the contract to remove the legs of the RBF 185, a jack up Oil Rig owned by R&B Falcon Drilling, based in Houston, USA. The jack up rig was on its way on the Tem barge to a new contract in Brazil when due to a severe storm one of the legs broke off close to the South African coast.

The broken piece of the leg fell outwards from the rig, The Mammoet Manitowoc M4100 ringer crane is becom- so no damage was inflicted on the rig. After safe arrival ing a popular sight in the port of Cape Town and is very in the Cape Town port, Mammoet was called in with a much in demand. Since the arrival of the crane it has Manitowoc M4100 ringer to lift the other two legs and been in use continuously with only short intervals for mob the remaining part of the broken leg. and demob and for maintenance. Currently Mammoet For this purpose, an additional 40 ft boom section had Southern Africa is busy with marketing their heavy lift to be mobilised from Singapore in order to extend the services, specifically targeted at the offshore industry and main boom to 104 metres, which was just enough height in particular concerning maintenance of drilling platforms. to reach the top of the 89 metres leg. The job took four weeks to complete. After that the rig sailed to its home Harbour authorities have been consulted for a conversion base in the USA for fitting new legs. of a pier to make it suitable for load-out activities and other This project was covered by the South African tv news offshore activities. This proposal has been received posi- network and gave Mammoet some free publicity nation tively and it offers Mammoet the opportunity for stationing wide in this country. heavy crane capacity in Cape Town in the long term.

MAMMOET ASIA Manila South Harbor

Manila - On the weekend of 8-9 July, the removal of the cranes, a barge 2000 a typhoon caused major damage equipped with winches, ballast to two container handling cranes at pumps, massive load spreading the ATI container handling facility in beams and 48 axles SPMTs sailed Manila South Harbor. Impsa Port from Singapore to Manila. cranes were loaded onto the barge. Systems (IPS) was awarded by ATI The removal was not as straightfor- Weather conditions were harsh and Philippines the contract for the ward as it seemed. The container the team experienced three typhoons removal of the damaged cranes. cranes drove into each other during during the whole operation in Manila. Each crane weighed 550 tonnes. the typhoon and the cranes drove out Even though the weather gods were Mammoet Singapore was contracted of the rails on the wharf. This resulted against us, the operation in Manila by IPS to remove the damaged cranes in severe damage to the bogeys of the was completed successfully. from the wharf and bring them by container cranes. Since we could not The barge voyage to Kuching took seagoing barge to Kuching - Serawak move the cranes horizontally any only 10 days. - Malaysia were they would be over- more, the first task was to jack up the The cranes were safely off-loaded hauled and re-used for the Kuching container cranes in order to get the by our SPMTs in Kuching Malaysia port. Less then one week after SPMTs underneath them. As soon as upon arrival. Mammoet received the award for the SPMTs were placed under, the

Ms Seaway

Singapore - companies experience a worldwide upsurge in the market. At this moment, several large develop- ments are in progress such as at Jurong Island, often referred to as the biggest land reclamation project of the century.

This project required so much capa- No problem, of course, and Mammoet city that it caused a shortage in avail- thus skidded the front section, after able dredging ships. Unfortunately, which the midsection was positioned ordering new ships takes too much in between the two ship halves with time. Boskalis found a solution by a floating crane. Mammoet then buying a used dredger in Russia. had to move the front section back. This ship had to be upgraded and for The advantage of the MSG skidding this, Keppel Shipyard in Singapore system was obvious when the two was asked to cut the ship into two sections were mated precisely by parts and to insert a new midsection. raising and tilting the 4,500 tonnes The idea to achieve this is rather sim- section in a very easy manner. ple. Put the ship in a dry dock, cut it into two sections, skid the front part This project marked the first time forward and insert a new section with the MSG skidding system was used a floating crane. The front section had in South East Asia for such an a weight of some 4,500 tonnes. operation. Earlier a similarly unique The shipyard checked with Mammoet operation was executed in Tel Aviv whether they could move this section while skidding a complete embassy with the MSG skidding system. building.

Mammoet World 2001 Page 18 Power

MAMMOET EUROPE

Windmills in our mind

Bruges/Zoetermeer/Pecklesheim - The availability of electricity is often taken for granted. mast. At sunset the huge rotor weighing 35 tonnes was attached, Almost nobody seems to realise the fact that the production of electricity from natural gas thus completing the mast. The or coal has an impact on our living environment. assembly of the various parts of the windmill could be clearly observed Moreover, the limited volume of This “super” windmill supplies the by motorists on the adjacent high- these resources and our dependen- equivalent power needed for 1250 way between The Hague and cy on them, make the energy pro- Utrecht. By the end of November duction a matter of careful planning last year this highest windmill in The and managing. The generation of Netherlands was officially commis- electricity based on wind turbines is sioned. The windmill, with a capacity clean in the sense that no harmful of 1,5 MW has an axle height of 85 gases are being released in the metres. The diameter of the rotor is atmosphere. Besides, wind will 70 metres. The "green current" fits always be available. In other words, the policy to stimulate the use of it is an inexhaustible power source. sustainable energy resources. This is one of the reasons why the Siemens is responsible for the reali- wind energy sector is one of the sation of this project, and also pro- fastest growing environmentally vided the wind turbine, the trans- friendly form of energy production. formers and the electro-technical Recently, Mammoet received several infrastructure. contracts to install such turbines. households. Using a recently For the Belgian company Turbo- acquired LR 1450-crawler crane with Meanwhile, Nuon inaugurated eight winds, Mammoet installed five a main boom of 67 metres and a jib windmills in Peckelsheim, Germany. power requirement for 3000 house- units along the Boudewijn canal of 47 metres, the turbine housing Their combined capacity is 6 MW holds. Nuon plans to increase its in Bruges. was mounted on the wing turbine which is sufficient for the yearly fraction of power produced from These windmills have a capacity sustainable sources to 10% in 2010. of 600 kW each, which is equivalent Much of it is to be delivered by wind- to the power supply for 700 - 800 mills. The eight windmills were man- households per year. ufactured by Lagerwey in Barneveld, The windmills have two mast ele- Netherlands. Mammoet often trans- ments, 55 metres high, a cradle of ports windmills and parts from any 20 tonnes and a rotor with three place in Europe. Masts from Leipzig, blades, weighing 15 tonnes. rotors from Scotland, generators The lifting was carried out using from Antwerp, cradles from Schoon- an AC 400 and a KMK 5110. dijke and other parts from Slovakia and Poland. For instance, Mammoet The highest windmill in the Antwerp took care for fifty transports Netherlands can be found on the to Peckelsheim where a Mammoet grounds of Siemens in Zoetermeer. crawler crane assisted the assembly.

Transformers on the move

Mammoet’s heavy lift activities for the power industry vary from the exchange of steam generators in nuclear power stations to the transport of transformers of all shapes and sizes.

Edinburgh - Mammoet Antwerp was shipped under contract of of equipment recently introduced to recently moved, in co-operation with VATech Peebles Transformers Ltd in the Mammoet fleet. Jim Parkinson Ltd - a company that Edinburgh. Barging from Austria to Jim Parkinson arranged the routing arranging permits for the outsized Rotterdam had been arranged by and police escorts in the UK from load traffic in the UK and Eire - John S. Braid and Co. Ltd of Teesport terminal, including a several transformers to the UK. Glasgow. In addition several ship- passage through the Corus Steel One of the transformers was ments were carried out from Works at Lackenby as to avoid a low shipped by VATech Group from Edinburgh to Austria using bridge. They also arranged offload- their factory at Linz, Austria to a Mammoet Antwerp vehicles. ing at Edinburgh using a jacking and new plant being constructed in The move used a 9 axle line skidding system to manoeuvre the Edinburgh. Goldhofer combination with a goose transformer to its final position in a The 103 tonne weighing transformer neck, which is part of a new range very narrow space.

Mammoet World 2001 Page 19 Marble Falls - Mammoet Americas performed an impres- for the two Macks and one Kenworth prime mover, but sive multi-modal transport for Hyundai and the Lower it did not resulted in any problem. Upon arrival the old Colorado River Authority by moving a 490,000 lbs transformer was slid from its existing foundation and replacement transformer from the Port of Houston to a the new one, fully dressed, was set on the path, thus substation in Marble Falls in Texas. The transformer was completing the job successfully. initially loaded on one of Mammoet’s low deck railcars by using a 450 tonne gantry, and railed to a siding some 20 For these kind of shipments Mammoet provides the pro- miles away from its final destination. At the siding its was per project management. Through years of experience jacked up and slid over to a 12 axle-line Goldhofer, trans- they have installed a world-wide network to meet any ported for the last leg of the route to the substation. customers requirements. The projects include trans- To achieve this transport, a local lake and water reservoir formers, turbines and generators from 50 to 400 tonnes. had to be drained 4 ft to allow the passage through a For Smit Nijmegen, one of our major customers, we river. The 1 ft of water left at the time of the passage, arrange transportation of approximately 30 transformers combined with the 6% incline created an extra challenge to different locations all over North America.

in h alists speci VAN SEUMEREN GROUP worldwide specialists in heavy lifting and transport wide world

P GROU EREN SEUM VAN

Crane guide lift eavy s Mammoet new style visualised vative h lution Inno o nsport s ry ndust nd tra tion i a brica ore fa offsh to the ated Dedic

Corporate identity

De Meern - One of the first actions Eventually we arrived at the after Van Seumeren and Mammoet following logo: joined forces was the development of a new house style. The basic idea was that our new house style fits the strategy to choose “the best of both worlds.”

In our new organisation, we have The brand name appears on the opted for the ‘Mammoet’ brand equipment in white and can also be name and logo, including to mention printed in red on other backgrounds. the Van Seumeren Group. Our organisation opted for a gradual The “mammoth” fits perfectly with implementation. Therefore, it will take the identity of our company. It visu- some time before all house style car- alises strength and is associated with riers will feature the uniform something big like our cranes and Mammoet livery. scope of work. Additionally, the name is easily pronounceable and means www.mammoet.com the same all over the world. Mammoet New style exibiting! The colors in our new house style Only two weeks after the acquisition, are red and black, the former Mammoets new website was online. Stavanger - Mammoet presented Van Seumeren colors. The color In the first months, lots of informa- its new colors and organisation at silver was added for the brand mark. tion about the acquisition and the the ONS (Offshore Northern ) new organisation structure was exhibition in Norway. As the off- communicated through this world- shore manufactures are an impor- wide medium. tant market segment for Mammoet, it was an excellent opportunity to Mammoet’s communication strategy display our extended heavy lift is focused on the further develop- activities and services. Special ment of the site in order to create an attention was given to various optimal service for all relations. load-out projects, including lifting, To achieve this, our site will have jacking and weighing activities. some quite interesting additions in The ONS is the most important the coming year. European “oilshow”, held every two years at Stavanger, being the cen- We won’t reveal what these addi- ter of the Norwegian oil industry. tions are, just regularly visit our site The exhibition was attended by a and you will find out! record number of 30,000 visitors.

The Netherlands B.V. Prefab Beton Montage Germany - Leuna Egypt - Caïro Cambridge Banchang De Meern H. van Driel & Zn. Phone +49 (0)34 61 432 681 Phone +20 (0)2 5195 919 Etarco Mammoet Eastern Ltd. Phone +66 38 893 700 Mammoet Holding B.V. Phone +31 (0)10 2042 400 Fax +49 (0)34 61 432 688 Fax +20 (0)2 5196 519 Phone +1 519 7400 550 Fax +66 38 893 699 Phone +31 (0)30 6695 111 Fax +31 (0)10 2042 415 Fax +1 519 7403 531

Fax +31 (0)30 6665 128 Spain - Madrid MAMMOET Japan - Tokyo Terneuzen Phone +34 91 3728 473 AMERICA’S Brossard Phone +81 (3) 5563 0274 Mammoet Trading Phone +31 (0)115 648 050 Fax +34 91 3729 433 USA - Rosharon Etarco Mammoet Eastern Ltd. Fax +81 (3) 5563 9641 Phone +31 (0)30 6695 111 Fax +31 (0)115 630 724 Phone +1 281 3692 200 Phone +1 450 923 9706 Fax +31 (0)30 6665 128 Italy - Melzo Fax +1 281 3692 178 Fax +1 450 923 1815 Velsen-Noord Phone +39 02 95529 521 MAMMOET MIDDLE EAST United Kingdom Phone +31 (0)251 229 341 Fax +39 02 95731 216 AVS LLC Mexico - Monterrey Mammoet Trading Fax +31 (0)251 224 488 Phone +1 281 3692 200 Phone +52 8 3782 079 Middle East - Dubai Phone +44 (0)191 2639 222 UK - Newcastle Fax +1 281 3692 178 Fax +52 8 3782 170 Phone +971 4 3331 252 Fax +44 (0)191 2639 333 Beek / Geleen Phone +44 (0)191 2639 222 Fax +971 4 3331 366 Phone +31 (0)46 4280 066 Fax +44 (0)191 2639 333 South El Monte MAMMOET ASIA Schiedam Fax +31 (0)46 4376 640 Phone +1 626 4425 542 Abu Dhabi Asia - Singapore Mammoet Global B.V. France - Marseille Fax +1 626 4420 841 Phone +971 2 6271 141 Phone +(65) 8611 638 Phone +31 (0)10 2042 424 Westdorpe Mammoet Fostrans Fax +971 2 6272 001 Fax +(65) 8612 718 Fax +31 (0)10 2042 455 Phone +31 (0)115 472 600 Phone +33 495 061 474 Venezuela - Fax +31 (0)115 472 639 Fax +33 495 061 475 Phone +58 (0)281 2744 866 Malaysia - Puchong  Fax +58 (0)281 2750 539 MAMMOET Mammoet Romstar SDN BHD SOUTH AFRICA MAMMOET Pernis / Moerdijk / Botlek Paris EUROPE Phone +31 (0)10 4720 374 Phone +33 1 3493 3447 Canada - Edmonton Phone +60 380 603 200 South Africa The Netherlands Fax +31 (0)10 4164 885 Fax +33 1 3493 3449 Etarco Mammoet Western Ltd. Fax +60 380 603 210 Phone +27 11 8824 499 Breda Phone +1 780 4490 552 Fax +27 11 8824 422 Bangkok Phone +31 (0)76 5724 444 Belgium - Gent Norway - Fax +1 780 4179 623 Thailand - Fax +31 (0)76 5712 164 Phone +32 (0)9 3459 891 Phone +47 55 544 330 Phone +66 2 3161 291 Van Seumeren/DSE Fax +32 (0)9 3455 376 Fax +47 55 544 331 Calgary Fax +66 2 3161 290 Phone +27 11 8257 287 Schiedam Etarco Mammoet Western Ltd. Fax +27 11 8738 372 Phone +31 (0)10 2042 424 Antwerp Russia - Moscow Phone +1 403 2520 551 Indonesia - Jakarta Fax +31 (0)10 2042 442 Phone +32 (0)3 5441 920 Phone +7 095 9560 838 Fax +1 403 2583 846 Van Seumeren/Nusatama Pte. Ltd. Fax +32 (0)3 5416 664 Fax +7 095 9560 738 Phone +62 21 829 1864 Fax +62 21 830 5114

Colofon • Editor Mammoet Holding B.V., Public Relations and Communication • Photography Employees Mammoet, Cranes Today / Phil Moughmer • Text De Spil B.V. • Design & Layout Graphic Invention • Printing Drukkerij Zuidam & Zonen B.V. • Copyright Texts and photos can only be reproduced after permission from the editor.