Cheakamus River Habitat Restoration Sue’s Channel Project (06.CMS.01)

Sue’s Channel Bridge March 2007

Canada Government of Canada North Vancouver Fisheries and Oceans Outdoor School Cheakamus River Salmon Habitat Restoration 06.CMS.01

“Sue’s Channel” Final Report

This channel, and the educational opportunities that occur along its banks, are a memorial to Sue Emerson, and her dedication to the Bridge Coastal Restoration Program.

Submitted by: Watershed Society Prepared by: Carl Halvorson North Vancouver Outdoor School, School District #44 and Edith Tobe Squamish River Watershed Society

with financial support of the BC Hydro Bridge Coastal Fish and Wildlife Restoration Program Executive Summary

This project involved construction of new channel habitats and support structures for salmonid habitat located at North Vancouver Outdoor School (NVOS) (Sue’s Channel) and the restoration of channel habitats that were impacted by the October 2003 flood of record on the Cheakamus River and the August 5, 2005 CN Rail sodium hydroxide spill (Moody’s Channel), located on Squamish First Nation (SFN) I.R. 11. Design and engineering work were undertaken by Fisheries and Oceans Canada (DFO) and NVOS staff during the winter of 2005 - 2006. Construction work started late in 2005 with right of way clearing to facilitate surveys for construction levels, grades and cuts. Initial excavation for the Sue's Channel complex area started in the spring of 2006. These early excavations were funded by the concurrent Mamquam Reunion project. Approx. 1200 m3 of alluvial gravels extracted on-site at NVOS were utilized in that project. Excavation started in earnest in late spring with the start of the "Moody's Channel" phase of the project. Gravels excavated from the Sue's Channel site were used to reconstruct approx. 205 m of Lower Moody's Channel, creating 2278 m2 of enhanced spawning, rearing and refuge habitats for chum, coho, pink, chinook and steelhead. Works also included the installation of 61 pieces of LWD and over 166 boulders. Works on the new Sue's Channel Complex included a 610mm valve assembly and intake pipe, feeding water from the existing Gorbuscha Channel headpond; and the creation of a 380 m, 2400 m2 spawning, rearing and refuge channel for chum, coho, pink, chinook and steelhead. An additional 467 m2 amphibian habitat area was constructed, providing study areas for North Vancouver Outdoor School’s aquatic study programs, accessed by habitat side trails. Works also included the installation of 175 pieces of LWD and over 80 in-channel boulders. There were very few problems during any phase of this project, though some of the cuts were relatively deep and a significant amount of material was excavated from site to complete the project. Several thousand cubic meters of "excess" alluvial gravels were stored on-site at NVOS for future fisheries related projects. Both projects were completed prior to the 2006 chum and coho runs and were well utilized by spawners. "Gee" trapping within weeks of project completion indicated that an abundance of juvenile salmonids had entered and were utilizing both habitats.

i Table of Contents

Executive Summary i. Table of Contents ii. List of Figures iii. List of Tables iii.

1. Introduction 1. 2. Goals and Objectives 1. 3. Study Area 2. 4. Methods 2. 5. Results 3. 6. Acknowledgements 3. Appendices

I. Financial Statement (income and expenditures) 4. II. Performance Measures - Actual Outcomes 5. III. Confirmation of BCRP Recognition - Sue’s Channal signage 6. IV. 1. Sue’s Channel - Site Locator Map / Site as-built drawings 7. 2. Moody’s Channel - Site Locator Map / Site as-built drawings 8.

C. Additional Information Photo Pages pgs 9. 10. 11. 12.

ii List of Figures fig 1. Bob Brown, John Hunter - installing boulders - Moody’s 3. fig 2. Sue’s Channel - final pass 9. fig 3. Sue’s Channel - “trout reach 4” - profiling 9. fig 4. Sue’s Channel - “trout reach 4” - complexing 9. fig 5. Sue’s Channel - “trout reach 4” - completed 9. fig 6. Sue’s Channel - “groundwater reach 2” - base completed 10. fig 7. Sue’s Channel - “groundwater reach 2” - completed 10. fig 8. Sue’s Channel - middle “trout reach 4” - complexing 10. fig 9. Sue’s Channel - intake installation 10. fig 10. Sue’s Channel - channel bridge - reach 1 10. fig 11. 12. 13. Sue’s Channel - BC Hydro right of way construction 11. fig 14. Moody’s Channel - start of construction - downstream riffle 12. fig 15. Moody’s Channel - gravelling 12. fig 16. Moody’s Channel - downstream riffle completed 12. fig 17. Moody’s Channel - complexing completed mid-channel 12. fig 18. Moody’s Channel - completed channel panorama 12. fig 19. 1. Sue’s Channel - Site Locator Map / Site As-built drawings 13. fig 20. 2. Moody’s Channel - Site Locator Map / Site As-built drawings 14. fig 21. Sue’s Channel Sign 6.

List of Tables

I. Financial Statement (income and expenditures) 4. II. Performance Measures - Actual Outcomes 5.

iii Introduction

The North Vancouver Outdoor School has worked with BC Hydro, DFO and the Squamish Indian Band to develop a number of salmon habitat restoration projects on the school property and adjacent lands over the last two decades and this project is directed at the restoration and upgrading of these habitats so that they remain productive over time. These various channels and ponds collectively form a large and important component of the off-channel habitat accessible to salmonids and other fishes of the Cheakamus River and were major factors in conserving pink, chinook and coho salmon populations during the recent 2003 flood and 2005 caustic soda spill in the Cheakamus River. This project involves a continuation of the effort to repair, upgrade and expand constructed salmon habitats that were either damaged by recent events on the Cheakamus River or those that require upgrading to improve how they function as fish habitat and further how they deal with future flood and other catastrophic events in the valley. It is very important that these habitats be maintained and improved where possible. Footprint impacts and limiting factors Loss of habitat: The first limiting factor that these projects address is the loss of side channel and off- channel habitat. The off-channel habitat is critically important for species such as coho, chinook, pink and chum salmon. Riverine channels are important for spawning pink and for spawning and rearing 0+ chinook salmon and steelhead trout juveniles. Former spawning and rearing areas have been lost, primarily due to simplification of the Cheakamus River in Reach 4 due to dyke and bridge construction for protection and access to transmission lines, diversion of flows out of the basin directly into the Squamish River and loss of wood and gravel recruitment due to the effects of Daisy Lake created by dam construction (Northwest Hydraulics, 2000). These footprint impacts; such as altered fluvial processes, caused by reduced downstream flows, and controlled flow releases have resulted in less downstream diversity, such as side channels to the main river. This loss of riverine side channels critically limits spawning and rearing habitat for pink and chinook salmon and steelhead trout. Migrating pink fry provide a major source of food for other species, such as steelhead trout and chinook and coho pre-smolts, prior to their migration to saltwater in the spring. Diversions: The second limiting factor addressed is loss of nutrients due to the effects of the Daisy Lake Reservoir and diversion of nutrients out of the basin through the power tunnel to the Squamish River. These projects will increase the biomass of salmon produced by the lower Cheakamus River and thereby increase the amount of marine derived nutrients that enter the ecosystem each year. Loss of nutrients due to the effects of the Daisy Lake reservoir and diversion tunnel are addressed by increasing the source of marine derived nutrients to the lower Cheakamus River. Side channel habitats can increase salmon returns to the river and have the ability to hold salmon carcasses through winter floods and prevent them being swept out of the watershed. This maximizes the value of the marine derived nutrients to the local ecosystem. Goals and Objectives

These projects take advantage of the river intakes on the NVOS property that feed water downstream into constructed channel habitats. The Eagle Point intake provides flows into the Moody’s Channel complex, where a section of side channel was restored to provide optimum habitat for spawning pink, coho and chum salmon. This area will provide another significant refuge for pink salmon embryos during future flood events and should assist in the conservation of this specific population. The expansion of groundwater fed components in the Upper Paradise system, in Sue’s Channel, provides critical spawning habitat for the benefit of chum salmon. The work of the Cheakamus Water Use Plan’s Fish Technical Advisory Committee identified chum spawning capacity in the Cheakamus River as a specific 1 limiting factor. This project adds significant spawning and rearing potential to an already extremely productive channel system. Additional flows provided by the Gorbuscha Channel intake provide habitats critical to trout, chinook and coho.

Similar constructed channel areas along the Cheakamus River played a critical role in conserving a significant proportion of the 2004 brood juvenile coho salmon during the recent 2005 caustic soda spill. Coho fry survived in high numbers within protected side channel habitats and are now re-colonizing heavily affected main stem habitats.

Study Area

These salmon habitat restoration sites are located adjacent to the Cheakamus River within the area known locally as the Paradise Valley. The project focused on two constructed off channel habitats along the Cheakamus River, Moody’s side channel, and the expansion of the Upper Paradise groundwater channel, with the addition of the “Sue’s Channel” complex. Moody’s side channel was originally constructed for the benefit of coho and chum salmon and originally fed by up-welling groundwater alone. Its upstream section originates in the NVOS “duck pond” and has since been augmented by Cheakamus River water flows through the “Eagle Point” intake. Water from the intake flows through the Eagle Point Connector Channel, into the NVOS Canoe Pond and through the Bighouse Connector Channel into the Moody’s system. Both the Eagle Point Connector and Bighouse Connector were completely rebuilt after the 2003 flood. The lower section of Moody’s side channel flows continue through the Squamish Indian Band IR #11, re-entering the Cheakamus River just upstream of the Cheekye River confluence. Upper Paradise Channel is located on North Vancouver Outdoor School, roughly paralleling the BC Hydro transmission line right of way, just south the “bailey bridge”. Sue’s Channel roughly parallels Upper Paradise Channel and is fed by both upwelling groundwater and a controlled flow from the Gorbuscha Channel intake. The property on which these off-channel habitats are located on are either owned by the North Vancouver Outdoor School, School District 44 (North Vancouver), or the Squamish Indian Band. Maps covering the site are Natural Resources Canada National Topographic System 92G/14 and Geo Data Terrain Resource Information Management 92G.085 near UTM coordinates of 5519720m N by 488750m E and 92G/14. 5519500mN: 489250m E. (1983 North American Datum, UTM Zone 10U) or 1204582, 538967 m BC Albers coordinates.

Methods

Excavation was done with Cat 235, 320, 325 and 330 excavators and Cat 950 and 966 loaders. Materials were moved around site by a variety of standard dump trucks and a D250 Cat truck. LWDs were placed using a Cat 325 excavator and transported with standard dump trucks and a D250 Cat truck. Most LWDs were supplied by NVOS though several logs were supplied by the Vancouver Olympic Organizing Committee (VANOC) through a resource sharing arrangement with British Columbia Conservation Fund (BCCF).

2 Trail construction was assisted with a Bobcat skidsteer and 331 excavator. Squamish River Watershed Society (SRWS) and NVOS partnered with DFO during all phases of the design and development of these restoration works. Results

Gravels excavated from the Sue's Channel site were used to reconstruct approx. 205 m of Lower Moody's Channel, creating 2278 m2 of enhanced spawning, rearing and refuge habitats for chum, coho, pink, chinook and steelhead. Works included the installation of 61 pieces of LWD and over 166 boulders. Works on the new Sue's Channel Complex included a 610mm valve assembly and intake pipe, feeding water from the existing Gorbuscha Channel headpond; and the creation of a 380 m, 2400 m2 spawning, rearing and refuge channel for chum, coho, pink, chinook and steelhead. An amphibian habitat area of 467 m2 was also constructed during the project, providing a trail network and study areas for North Vancouver Outdoor School aquatic studies. Works also included the installation of 175 pieces of LWD and over 80 boulders. Approx. 160 meters of channel side trail was constructed including a 15 meter bridge spanning the channel. The center span was roofed, creating a 12 m2 (16 x 7 ft.) “classroom” over the channel.

Acknowledgements

This project would not have been possible without the financial support of BC Hydro Bridge Coastal Fish and Wildlife Restoration Program and the technical and supervisory support of Fisheries and Oceans Canada Pacific Region Habitat and Enhancement Branch, particularly Matt Foy and Harold Beardmore. Construction supervision was carried out with style and aplomb by Robert F. (Bob) Brown. Excavation and construction services were provided by John Hunter Ltd. Gravels were excavated at NVOS. LWDs were supplied on site by NVOS, and VANOC through the British Columbia Conservation Foundation Letters of support were supplied by: Randall Lewis ; Harold Beardmore P.Eng. Fisheries and Oceans; Edith Tobe, for the Squamish River Watershed; Steve Rochetta BC MOE fig.1. Bob Brown (foreground) John Hunter Fish, Wildlife and Habitat Management installing boulders, Moody’s Channel 3 Project #______Financial Statement Form

BUDGET ACTUAL BCRP Other BCRP Other INCOME Total Income by Source Grand Total Income (BCRP + other)

EXPENSES Project Personnel Wages Consultant Fees (List others as required)

Materials & Equipment Equipment Rental Materials Purchased Travel Expenses Permits (List others as required)

Administration Office Supplies Photocopies & printing Postage (List others as required)

Total Expenses Grand Total Expenses (BCRP + other)

The budget balance should equal $0 The actual balance might not equal $0* BALANCE (Grand Total Income – Grand Total Expenses)

* Any unspent BCRP financial contribution to be returned to: BC Hydro, BCRP 6911 Southpoint Drive (E14) Burnaby, B.C. V3N 4X8 ATTENTION: JANICE DOANE Project #______Performance Measures

Using the performance measures applicable to your project, please indicate the amount of habitat actually restored/enhanced for each of the specified areas (e.g. riparian, tributary, mainstream).

Performance Measures – Target Outcomes Habitat (m2)

Primary Primary Habitat Benefit Project Type 2 Target Targeted of Project (m ) Species Estuarine Habitat – Mainstream In-Stream Habitat – Tributary In-stream Riparian Complexes Shoreline Reservoir Riverine Deciduous Lowland Coniferous Lowland Upland Wetland Impact Mitigation Area of habitat made Fish passage technologies available to target species Drawdown zone Area turned into productive revegetation/stabilization habitat Wildlife migration Area of habitat made improvement available to target species Area of wetland habitat Prevention of drowning of created outside expected nests, nestlings flood level (1:10 year) Habitat Conservation Functional habitat Habitat conserved – conserved/replaced general through acquisition and mgmt Functional habitat conserved by other measures (e.g. riprapping) Designated rare/special Rare/special habitat habitat protected Maintain or Restore Habitat forming process Area of stream habitat Artificial gravel recruitment improved by gravel plmt. Artificial wood debris Area of stream habitat recruitment improved by LWD plcmt Area increase in Small-scale complexing in functional habitat through existing habitats complexing Prescribed burns or other Functional area of habitat upland habitat improved enhancement for wildlife Habitat Development New Habitat created Functional area created Area 2 400 m 2 2 2 2 2 2 4600 m 3225 m 1200 m 3840 m 2867 m 2200 m 2 2200 m Intake 90 m (pond) • Eagle Point 750 m 480 m 200 m 400 m 380 m 204 m Length BCR Channel Year 2002 2003 2004 2004 2005 2006 2006 2001/06 Gorbuscha East Channel Channel Kisutch Channel BCR Mile 49 Fisheries and Oceans Government of Canada Gorbuscha West Channel Eagle Point Connector Dave’s Ponds Project Gorbuscha West Gorbuscha East Eagle Point Bighouse Mykiss Sue’s Moody’s Dave’s Pond Intake • Gorbuscha Kisutch Moody’s Channel / Bighouse Channel Upper Channel Paradise Canada NVOS @ www.nvos.ca Sue’s Channel Far Point Connector Mykiss Channel Creek Forest Emerald Stream Birth of a BC Hydro Bridge Coastal Fish and Wildlife Restoration Program (BCRP) provides $1.5 million annually to projects that restore fish and wildlife populations and habitat impacted by construction of hydroelectric generating stations in 15 watersheds located along the coast, Fraser Valley, Bridge River, Shuswap River and on Vancouver Island. The program is managed by a Board comprised of three public, First Nation, one federal, one provincial and on BC Hydro representatives. Far Point Channels Far Point Channels Far Point • Intake Enhanced Habitat BCRP Channel Projects Cheakamus River River Bars Dyking • Enhancement to 2007 • River Channel 1999 The Dave’s Pond complex provides important spawning, rearing and refuge areas. Works completed include upgrades to connectivity, LWD replacement and repairs after the flood of October 2003 A new, enhanced, Eagle Point Connector channel and Canoe Pond outfall channel were constructed after the 2003 flood. During construction of the 2002, Cheakamus Off Channel project, excavated gravel was hauled in dump trucks 4.5 kilometers upstream and deposited on an active river bar. During flood flow conditions, this gravel was picked up by the river and deposited downstream. This action helped replace eroded gravels in mainstem river spawning areas. Additional funding was provided in 2005 and 2006 to help mitigate the damage caused by October 2003 flood and the August 2005 CN Rail caustic soda spill. Both events had significant impacts, particularly on steelhead, chinook and pink stocks. Recruitment / Repair Dave’s Pond / Eagle Point For more information contact: BCRP @ www.bchydro.com/bcrp/ Gorbuscha Far Point / Mykiss The Far Point intake and outfall ponds were rebuilt in 2004. This involved replacement of pipe, valves and outfall assemblies. The diking protection was upgraded and headponds enlarged. The Mykiss Channel was constructed to provide critical spawning and rearing habitat, primarily for steelhead, chinook and pinks. The BC Hydro Water Use Planning process for the Cheakamus River identified pink salmon and appropriate spawning habitat as a limiting factor. The Gorbuscha Channel complex and intake assembly was completed as a two phase project in 2003 and 2004. These channels provide valuable spawning areas for pink and chinook salmon significant rearing and refuge habitats for steelhead and coho. This channel, and the education that happens here, is a memorial to Sue Emerson, and her dedication to the Bridge Coastal Restoration Program. Tragically she died doing what enjoyed best, hiking the mountains surrounded by all the beauty.

54.00 53.50 53.00 52.50 52.00 51.50 51.00 WS 51.42 WS Channel

Lower Paradise

Weir 51.47 Weir WS 51.65 WS Although her life was far too short, it a fully lived and savoured. Friends worldwide remember her zest for life, her contagious happy smile and loving spirit. Life was indeed a “sweet dream” as she often said. Sue was involved with many charities and her favourites help children in Canada and around the world. Salmon and kids being two of her favourite things, think of her when you see a salmon splash, frog leap or hear a child's laugh. From her family, friends, and colleagues at BC Hydro - “Forever in our Hearts”.

45 m

WS 51.87 WS 51.69

Weir 51.96 Weir

WS 52.07 WS 51.77 Moody’s Sue’s Channel Sue’s Channel was built in 2006 and provides groundwater habitats for spawning chum; river fed riffle habitats for steelhead, pinks and chinook; rearing and refuge habitats for coho. The addition of trails and sampling sites along the channel and constructed “amphibian” habitats provide opportunities for North Vancouver Outdoor School aquatic field studies During construction of Sue’s Channel, alluvial gravels were transported to the Moody’s Channel on I.R. 11. These gravels and LWD complexes provide spawning habitat for coho, chum, chinook and pinks, while providing much needed rearing and refuge habitat that had been damaged by flood flows in 2003. Culverts at the NVOS Bighouse were replaced by a LWD complexed riffle channel. 100m

Sue Emerson

WS 52.15 WS 51.80

WS 52.23 WS Weir 51.93 Weir

12m

WS 52.39 WS 52.21 Weir

14m

WS 52.47 WS 52.29 Weir 80˚

20m

-10 Spawning Channel Spawning

Upper Paradise Upper

WS 52.79 WS Weir 52.71 Weir

51.42

flow WS 52.82 WS 5m Weir 52.80 Weir LWDs: 6 Boulders: +40 LWDs: + 45 Boulders: +40 LWDs: + 24 LWDs: + 40 Riffles: + 50 m

deep refuge pond

2 2 9m

WS 53.11 WS 380 m 2400 m 467 m 52.94 Weir 00 2 232 m • Trap Site 1 20m 51.47 WS 51.65 2 2 2 2

48 m 280 m 108 m 653 m 64 m 467 m 160 m 768 m 55 - 100 mm 55 - 80 mm 60 - 90 mm

WS 53.24 WS 52.94 Weir

52.22

10m

WS 53.47 WS Weir 53.18 Weir 10 NVOS trail network BM 54.62

7m WS 53.48 WS 53.18 Weir Reach 1: Length: Area: Reach 2: Length: Area: Refuge Areas: Reach 3: Length: Area: Reach 4: Length: Area: Total Length: Total Area: Amphibian Habitat: Total Area: Sample Trapping: 01.01.2007 (baited Gee Trap - 24 hour set) Site 1: Paradise Channel refuge area 59 Coho Length: Site 2: Sue’s Channel refuge area 25 Coho Length: Reach 5: 24 Coho Length:

School District #44 WS 53.50 WS Weir 53.33 Weir 5m Outdoor School Sue’s Channel 2007 Cheakamus River Habitat Restoration 2002 - Sue Emerson

“Sue’s Channel”

North Vancouver

51.99 20 WS 53.50 WS 50m

trail network

link to NVOS Memorial Channel • sampling area 87 WS 53.51 WS Reach 1 15m 30

97 BM 55.34 53.69 WS WS 11.24.06: 53.69 Gauge @ 0.799 WS 53.74 Gauge @ 0.85 79 Gorbuscha Intake BCRP 02.Ch.6

• NVOS Trail • top of Gorbuscha intake pipe 53.27 4 Reach 107 42

900 mm valve e

iffl r i f f l e r

flow 750 mm pipe • 52 610 mm valve • Channel 62 40 69 Gorbuscha 40

• Trap Site 5

117

Reach 4

e l

f f BM 55.77 i top of headwall r

top of concrete base

top of valve e l f f i 53.20 WS 53.50 r Gorbuscha Channel 51.69 WS 51.87 54.00 53.50 53.00 52.50 52.00 51.50 51.00

54.11 132

52.80 new trail infrastructure • • 150 m 52.60

53.57 122

30 142 flow 51.96 pole #2311753 162 152 51.99 51.77 WS 52.07 WS 53.51

• 53.51 top of pipe 172

e 50

l

20 f

f

i r

white BXSP “Big Brute” “Big BXSP white E Intake pipe: 750 mm x 15 m 15 x mm 750 pipe: Intake Reach 2 N 49˚49.585' W123˚09.125' 52.29 BM 55.74 51.72 WS 52.15 51.83 WS 52.13 new trail infrastructure 52.60 Reach 2 10 N

S headpond flow ramp to maintain

51.93 WS 52.23 40 20 60

10 habitat tree habitat 65 10 • Trap Site 6 30 20 00

W • Trap Site 4 60 166˚ 162˚ 50 85 BC Hydro Tower # 132-1 75 Reach 3 4˚C 12.17.06

95 115 line transmission of line center Pole 10˚C 12.17.06

105 51.81 WS 52.14 WS 51.81 52.44

125 BM 54.70

135 centerline BC Hydro distribution line distribution Hydro BC centerline 70 Pole 73 N 49˚49.484' W123˚09.173' system, upgraded in 2004 on concrete headwall assembly BCRP 04.Ch.01 “Sue’s” Intake Assembly: • 610 mm Armtec 20-10C sluice gate valve • salvaged from old Far Point intake Pole N 49˚49.431' W123˚09.189' • Trap Site 2

• Trap Site 3 berm centerline Paradise Valley Road Valley Paradise centerline

9˚C 12.17.06

berm centerline BC Hydro transmission line transmission Hydro BC centerline

“amphibian” habitat • Paradise Valley Road Valley Paradise BM 77HA915 EL55.411 transmission tower

6 • Sue’s Channel Site North Vancouver Outdoor School • Moody’s Channel restoration site • Dave's Ponds Site Howe • NVOS “fish camp” restoration site Sou nd k BM 77HA915 e k e e r EL55.411 e r C er Paradise Valley Road C Riv h h t is Pil y m ch u a u e k

o qu n S C

m o re t n e o S k N 49˚49.484' M WSC GAUGE N 49˚49.431' W123˚09.173' 08GA043 W123˚09.189' mus River Auditorium N 49˚49.585' eaka Squamish Ch W123˚09.125'

C

u

l r l i e t C o v h n i eekye Rive R M r C a r m s e h e a i t k u e

q r C

r W

m e

a e

k

M S N

Water Elev. Gauge: E Map Key: WSG 08GA043 Squamish Watershed CHEAKAMUS RIVER: CN Railway Cheekye River confluence - Tenderfoot Creek

transmission Paradise Valley Road tower

centerline BC Hydro transmission line berm BM 77HA915 EL55.411

berm centerline Paradise Valley Road “amphibian” habitat •

• Trap Site 3 9˚C 12.17.06 Pole • Trap Site 2 73 N 49˚49.431' centerline BC Hydro distribution line W123˚09.189' 70 N 49˚49.484' 135 Pole W123˚09.173' 125 52.44 51.81 WS 52.14 center line of transmission line 105 10˚C 12.17.06 Pole BM 54.70 95 115

75 BC Hydro Tower # 132-1 85 60 166˚ 162˚

50 00 Reach 3 • Trap Site 4 12.17.06 20 30 habitat tree 4˚C 10 65 10 20 60 40 flow Intake Assembly:

10 • Trap Site 6 • 24” valve 51.93 on concrete headwall assembly WS 52.23 ramp to maintain 51.83 BM 55.74 • salvaged from old Far Point intake WS 52.13 51.72 headpond 52.60 new trail WS 52.15 system, upgraded in 2004 Reach 2 52.29 Intake pipe: 750 mm x 15 m infrastructure • 52.21 white BXSP “Big Brute” BCRP 04.Ch.01 ri WS 52.39 ffl 50 Reach 2 e 20 172 53.51 top of pipe • 51.77 pole #2311753 51.99 152 162 WS 53.51 WS 52.07 N 49˚49.585' 51.96 flow W123˚09.125'

30 142 new trail 122 132 52.60 51.69 54.00 54.00 riffle infrastructure • WS 51.87 53.20 r WS 53.50 WS 53.69 iffl BM 55.77 • 150 m Gorbuscha e 53.33 Channel WS 53.50 WS 53.51 WS 53.50 WS 53.50 WS 53.48 WS 53.47 117 Gorbuscha 40 53.50 53.50 52.70 69 top of headwall Channel 52.29 62 top of concrete base WS 53.24 52 WS 52.79 top of valve Channel Profile: WS 52.47 53.18 610 mm valve • 40 riffle WS 53.11 Reach 4 WS 53.48 750 mm pipe • 54.11 52.80 flow 52.71 le 53.57 53.00 53.00 42 iff 107 • top of Gorbuscha intake pipe 53.27 WS 52.82 WS 52.79 WS 52.80 r

Weir 53.33 Reach 4 900 mm valve

Weir 53.18 Weir 53.18 52.94 • Trap Site 5 WS 11.24.06: 53.69 WS 53.11 WS 52.47 NVOS Trail • 53.18 Gauge @ 0.799 52.50 WS 52.39 52.50 Weir 52.94 Weir 52.94 BM 55.34 WS 53.47 WS 52.23 79 Weir 52.80 WS 53.74 Gorbuscha Intake WS 52.15 Weir 52.71 Gauge @ 0.85 51.99 WS 52.07 97 BCRP 02.Ch.6 Weir 51.96

30 52.00 WS 51.87 52.00 52.94 WS 53.24 Weir 52.29 WS 51.65 Weir 52.21 sampling area

Reach 1 WS 51.42 51.80 W

51.50 51.77 51.50 Weir 51.93 87 51.69 Lower Paradise Channel

51.00 Weir 51.47 51.00 45 m S 15m 50m 5m 7m 10m 20m 9m 5m 20m 14m 12m 100m link to NVOS N

20 trail network Reach 1: Sample Trapping: 01.01.2007 E Length: 48 m LWDs: 6 (baited Gee Trap - 24 hour set) Area: 280 m2 Boulders: +40 Reach 2: Site 1: Paradise Channel refuge area 10

BM 54.62 Length: 108 m LWDs: + 45 59 Coho 52.22 Area: 653 m2 Boulders: +40 Length: 55 - 100 mm 2 Refuge Areas: 232 m DESIGNED SCALE: NVOS trail network 1 OCT 15 SITE SKETCH - (PRECONSTRUCTION) 51.47 WS 51.65 Reach 3: Sue’s Channel refuge area 2005 ALL DIMENSIONS REPRESENTATIVE. • Trap Site 1 Site 2:

00 Length: 64 m LWDs: + 24 25 Coho DRAWN: CH 2 CHEAKAMUS RIVER Area: 467 m Length: 55 - 80 mm DATE: deep NOV 5 PROPOSED PARADISE CHANNEL EXPANSION - refuge DEC. 2006 pond 2 2005 (PRECONSTRUCTION) flow Reach 4: Reach 5: CHECKED ALL DIMENSIONS REPRESENTATIVE. 51.42 Length: 160 m LWDs: + 40 24 Coho SUE’S CHANNEL Upper Paradise Area: 768 m2 Riffles: + 50 m Length: 60 - 90 mm DRAWING NUMBER: -10 Spawning Channel DEC 25 SUE’S CHANNEL AS-BUILT RECOMMENDED 3 2006 ALL DIMENSIONS REPRESENTATIVE. CH-06-007 80˚ Total Length: 380 m Amphibian Habitat: AS-BUILT SKETCH SHEET 1 Total Area: 2400 m2 Total Area: 467 m2 APPROVED

DWG.NO. REFERENCE DRAWINGS NOTES NO. DATE: REVISION APPROVED REVISION 1 gravel bar

gravel bar 00 10 20 30 40 50 60 70 80 100 110 120 130 90 gravel bar 144 115˚ 140

gravel bar

154 gravel bar

Bridge lifted one* block higher

164 Specifications: gravel bar Length: 204 m 174 Area: 2200 m2

Average Gradient: 0.3 % • end of project Large Woody Debris: 61 184 Boulders: + 166

194

204

• end of project • Moody's Channel restoration North Vancouver • Sue’s Channel Site Outdoor School • NVOS “Fish Camp” restoration

BM 77HA915 EL55.411 Paradise Valley Road Howe Sou nd

k e k e e r e r C er C Riv h h t is Pil y m ch Auditorium u a u e k

o qu n S C

m o re t n e o S k M WSC GAUGE 08GA043 mus River eaka Squamish Ch

C

u

l r l i

W e t C o v h n i eekye Rive

R M r C S N a r m s e h e

Water Elev. Gauge: E a i t k u e

WSG 08GA043 q r C

r

m e

a e k

M

CN Railway CHEAKAMUS RIVER: Map Key: Cheekye River confluence - Tenderfoot Creek Squamish Watershed

SCALE: 1 OCT 15 SITE SKETCH - (PRECONSTRUCTION) DESIGNED 2005 ALL DIMENTIONS REPRESENTATIVE. DRAWN: CH CHEAKAMUS RIVER DATE: DEC. 23 SITE SKETCH - (AS BUILT) DEC. 2006 2 2006 ALL DIMENTIONS REPRESENTATIVE. CHECKED MOODY'S CHANNEL DRAWING NUMBER: RECOMMENDED AS BUILT SKETCH SHEET 1 CH-06-07 APPROVED

DWG.NO. REFERENCE DRAWINGS NOTES NO. DATE: REVISION APPROVED REVISION 1 Sue’s Channel Construction:

fig.2. Sue’s Channel right of way clearing “reach 1” at fig.4. Sue’s Channel at outfall of “trout” reach 4 confluence with Upper Paradise Spawning Channel. * LWD completed in groundwater component * Spruce tree directly behind excavator is the same * starting installation of cobble and LWD in riffles tree in figure 10 to the right of the bridge.

fig.3. Sue’s Channel at outfall of “trout” reach 4 fig.5. Sue’s Channel at outfall of “trout” reach 4 * channel roughed in - LWD not in final positions * channel completed (May 2007) 9 Sue’s Channel Construction:

fig.8. Sue’s Channel reach 4 * LWD completed

fig.6. Sue’s Channel right of way construction fig.9. Sue’s Channel intake installation * channel base and margins roughed in * existing Gorbuscha intake lower left

fig.7. Sue’s Channel right of way construction reach 2 fig.10. Sue’s Channel at outfall to Upper Paradise Channel * channel completed (May 2007) 10 * excavation of aquatic and refuge ponds * excavation of aquatic and refuge ponds * left to right: amphibian ponds - trails refuge pond “main” channel riffle outfall at Paradise Channel 11 fig.11. Sue’s Channel right of way construction reach 2 fig.12. Sue’s Channel right of way construction reach 2 fig.13. Sue’s Channel right of way completion panorama reach 1 - 2 Moody’s Channel Construction:

fig.14. start of gravel installation at lower reach at bridge fig.15. trucking gravel into mid channel area fig.16. completed gravel - riffle section at bridge fig.17. completed channel at mid channel area fig.18. panorama of completed channel

fig.14. fig.16.

fig.15. fig.17.

fig.18. 12