Integrated Infrastructure Services

Infrastructure Planning and Design

Terwillegar Drive Improvements

Urban Planning Committee October 2, 2018

Integrated Infrastructure Services | CR_5730 Council Approved Motion

That Administration:

1. Suspend any public engagement activities regarding the ultimate long term Terwillegar Drive/ and any roadway modifications that may limit access in the interim. 2. Optimize the concept plan for the Terwillegar corridor between Whitemud Drive and , including provision for opportunities of mass transit and active transportation. 3. Advance the Preliminary Design for Terwillegar Drive/40 Avenue interchange. 4. Advance the Preliminary Design for an optimized Stage 2 of the Whitemud Drive/Terwillegar Drive interchange, with consideration for reduced design parameters (i.e. design speeds) with the intent of reducing overall complexity and cost. 5. Continue to advance preliminary design on the basis of a number of $75-100M packages in support of staged completion of the Terwillegar corridor, including full access for Rabbit Hill Road, 23 Avenue, and Haddow Drive. 6. Present a list of potential shared funding opportunities with the provincial and federal government that take advantage of infrastructure and innovation funding. 7. and bring back a report to Council in third Quarter 2018 summarizing progress on the aforementioned design elements.

© City of 2 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Terwillegar Drive History

● Planned and constructed in the 1980s and intended to be a freeway ● Planning and design studies: 2001, 2007, 2012, 2014 and now Haddow Dr ● Construction upgrades in 2006/7, 2010, and Flyover upcoming

Issues and barriers: Long-Term Anthony Henday Drive ● Capital cost Interchange ● Access limitations ● Community Impacts

© City of Edmonton 3 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Freeway Plan

Ultimate Anthony Haddow Drive: Potential East/west shared-use Ultimate Whitemud 142 Street Transit on Henday Drive access only on the path connections Drive and Terwillegar pedestrian/ shoulders Interchange north side across bridges Drive interchange cyclist bridge

Stage 3: 2027 - 2030 Stage 6: 2039 - 2042 Stage 5: 2035 - 2038 Stage 4: 2031 - 2034 Stage 1: Stage 2: 2023 - 2026 Stage 8: 2047 - 2050 2019 - 2022 Stage 7: 2043 - 2046

Stage 3: Interim Haddow Drive 23 Avenue Rabbit Hill Rd 40 Avenue Stage 2: Interchange interchange: $60 million interchange: interchange: interchange: interchange: improvements: $ 130 million Stage 8: Ultimate $95 million $80 million $85 million $110 million Stage 7: Ultimate interchange $375 million interchange: $250 million ESTIMATES ARE CONCEPT LEVEL +/- 50% © City of Edmonton 4 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Freeway Plan - Stages 1 and 2 - $110M (est)

Planned Stage 1: Potential Stage 2:

Whitemud Drive / Stage 2 Rainbow Valley bridge widening Ramp widening

142 Street pedestrian bridge

Basketweave bridge or signal Basketweave Bridge Cross Section:

40 Avenue interchange

© City of Edmonton 5 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Freeway Plan - Stages 1 and 2 - $110M (est)

Basketweave Bridge Cross Section

© City of Edmonton 6 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Alternative Solution

Freeway Expressway

● More complex ● Less complex ● Free-flowing traffic (e.g., Whitemud Drive) ● High capacity, but not free-flowing ● Speed limit: 80 km/h ● Relatively high speed limit: 70 km/h ● Access via interchanges ● Signalized intersections (e.g., 91 Street) ● Conditions generally not suitable for ● Potential for adaptive traffic signal accomodation of transit, pedestrian and controls (i.e., “Smart Signals”) cyclists facilities ● Allows for integration of transit, pedestrian and cyclist facilities along the corridor

© City of Edmonton 7 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Expressway Plan Intersection Intermediate Dedicated North/south Stage 2 improvements 142 Street stage Anthony transit lane Widening shared-use path (one Terwillegar Drive with potential for pedestrian/ Henday Drive with bus to 8 lanes or potentially both / Whitemud Drive adaptive traffic cyclist bridge interchange stops sides) interchange signal controls

Stage 3: 2027 - 2030 Stage 1: 2019 - 2022 Stage 2: 2023 - 2026

Expressway from north of Anthony Henday Interim interchange: Interchange Drive to south of Whitemud Drive: $ 60 million improvements: $ 100 million $ 140 million ESTIMATES ARE CONCEPT LEVEL +/- 50%

© City of Edmonton 8 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Freeway and Expressway Comparison

Criteria Freeway Solution Expressway Solution

Conceptual Estimated $ 1.2 billion $ 300 million Costs (+/- 50%)

Community Impacts ● 30-year implementation ● 10-year implementation ● 8 stages ● 3 stages (most ● Construction detouring and improvements in Stage 1) delays during each stage ● Construction detouring and ● Land acquisition may be delays in each stage required ● No land acquisition

User Satisfaction ● Moderate initial increase ● High initial increase and ● Marginal increases in declining over time satisfaction with each stage, but declining trend over time ● Decreasing over time until additional investment

© City of Edmonton 9 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Freeway and Expressway Comparison

Criteria Do-Nothing Freeway Solution Expressway Solution

Travel Times (2030) 12 mins (AM NB) 9 mins (AM NB) 8 mins (AM NB) (Henday to 12.5 mins (PM SB) 9.5 mins (PM SB) 8.5 mins (PM SB) Whitemud)

Travel Times (2050) Not assessed 11.5 mins (AM NB) 14.5 mins (AM NB) (Henday to 6.5 mins (PM SB) 8.5 mins (PM SB) Whitemud)

Daily Traffic (2030) 30 - 55,000 30 - 70,000 40 - 75,000 (vehicles per day)

Daily Traffic (2050) Not assessed 60 - 95,000 50 - 85,000 (vehicles per day)

© City of Edmonton 10 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Transit on Terwillegar Drive

● Terwillegar Drive project protects for transit infrastructure in both the freeway and expressway scenarios. ● Transit service is being identified through The City Plan, as is outlined in Report CR_5863. ● Consideration will include route classification, where the route starts/ends, direct/express routing between transit nodes, etc.

© City of Edmonton 11 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Next Steps

1. Concept - 2018/19 a. Further technical assessment of expressway (in progress) b. Resume public engagement. Both solutions will be presented (November - December 2018) c. Report back to Committee (March 2019) d. Public engagement on long-term concept plan (April - June 2019) 2. Design - 2019/20 (if funding is approved) 3. Construction - 2021/22 (if funding is approved)

© City of Edmonton 12 | Integrated Infrastructure Services | Infrastructure Planning and Design | CR_5730 Terwillegar Drive Improvements | 10.02.2018 Integrated Infrastructure Services Infrastructure Planning and Design