June 19, 2020

Marlene H. Dortch Secretary Federal Communications Commission 445 12th Street, SW Washington, DC 20554

Re: Submission for the Record – Transition Plan Expanding Flexible Use of the 3.7 to 4.2 GHz Band GN Docket Nos. 18-122, 20-173

Dear Ms. Dortch:

Intelsat License LLC (“”)1 submits its C-band Transition Plan pursuant to 47 C.F.R. § 27.1412(d) and the Federal Communications Commission’s (the “Commission”) March 3, 2020 Report and Order.2 This Transition Plan details the necessary steps to be taken and estimated costs that Intelsat anticipates incurring in transitioning all existing services it provides to customers in the contiguous United States (“CONUS”) out of the lower 300 MHz of the C-band spectrum by the accelerated relocation deadlines in the Report and Order.

This transition is a complex and challenging undertaking -- one that Intelsat has been preparing for with more than two years of planning and engineering undertaken in conjunction with Intelsat’s customers, industry stakeholders, vendors, and other space station operators. While there are a number of component parts to Intelsat’s Transition Plan, they have been carefully coordinated and are highly interdependent. Many activities are already well underway. As noted herein, however, the identification of claimed earth stations will need further refinement once the Commission has finalized the list of incumbent earth stations and the list of those earth stations that have opted out.

Intelsat looks forward to working with all C-band stakeholders in implementing this Transition Plan. Please contact the undersigned with any questions regarding this matter.

1 Intelsat License LLC, an FCC satellite licensee, and its affiliated entity Intelsat US LLC, which provides operational services to Intelsat License LLC, are collectively referred to in the Transition Plan as “Intelsat.” Intelsat filed an election form to accept the Commission’s accelerated relocation framework and deadlines on May 26, 2020. 2 See Expanding Flexible Use of the 3.7 to 4.2 GHz Band, Report and Order and Proposed Modification, 35 FCC Rcd. 2343, paras. 302-06 (2020) [hereinafter “Report and Order”].

Respectfully submitted,

Intelsat License LLC

Michelle V. Bryan Secretary, Intelsat License LLC, and Executive Vice President, General Counsel and Chief Administrative Officer, Intelsat US LLC 7900 Tysons One Place McLean, VA 22102-5972

Enclosures

Intelsat C-Band Clearing Transition Plan Appendices: Earth Station Listings

2

Intelsat C-Band Clearing Transition Plan

6/19/2020

1 Table of Contents 2 Introduction ...... 4 3 Satellite and Launch Program ...... 7 3.1 Overview ...... 7 3.2 Fleet Satellite Replacement Plan ...... 9 3.3 Implementation of Compression/Upgrades to Reclaim Spectrum ...... 11 3.4 Transitioning Cable Programmers and Their Earth Station Affiliates...... 13 3.5 Transitioning Broadcast, Religious, Radio and Data Customers ...... 14 3.6 New Satellite Launch Program ...... 16 4 TT&C Gateway Relocation and Ground Systems Grooming ...... 18 4.1 Phase I Transition Activities...... 19 4.1.1 Paumalu Teleport ...... 19 4.1.2 Brewster Teleport ...... 20 4.2 Phase II Transition Activities...... 20 4.2.1 East Coast Consolidated TT&C/Gateway Teleport ...... 21 4.2.2 Latin America Teleport ...... 21 4.2.3 Hartebeesthoek, South Africa Teleport ...... 22 4.3 Summary of Antenna Relocations ...... 22 4.4 TT&C Antennas for the Seven New Galaxy Satellites ...... 23 5 Work Associated with Repacking the C-Band ...... 23 5.1 Process and Communications about Customer Transitions ...... 24 5.2 Earth Station Change Types ...... 25 5.2.1 Frequency Change [F] ...... 25 5.2.2 Transponder Reassignment of In-Orbit Protection Bandwidth [R] ...... 25 5.2.3 Polarity Changes [P] ...... 26 5.2.4 Satellite Changes [S]...... 26 5.2.5 Compression/Technology Upgrades Required [C] ...... 26 5.3 Filter Installation ...... 27 5.3.1 Filter Versions ...... 27 5.3.2 Phase I Filtering ...... 28 5.3.3 Phase II Filtering ...... 28 5.3.4 Earth Station Operator Responsibilities ...... 28 6 Customer Migration Plans ...... 30 6.1 Transition Plan (Chronological) ...... 30 6.1.1 Table 1 Phase I Grooming Plan Transition Activities (Chronological) ...... 30

2 6.1.2 Table 2 Phase II Grooming Plan Transition Activities (Chronological) ...... 32 6.2 Transition Plan (Customer-Centric) ...... 34 6.2.1 Table 3 Phase I Grooming Plan Transition Activities (Customer-Centric) ...... 34 6.2.2 Table 4 Phase II Grooming Plan Transition Activities (Customer-Centric) ...... 37 6.3 Satellite Transponder Loading View ...... 39 6.3.1 Figure 1 Cable Neighborhoods C-Band Loading – Current ...... 40 6.3.2 Figure 2 Cable Neighborhoods C-Band Loading – End of Phase I ...... 41 6.3.3 Figure 3 Cable Neighborhoods C-Band Loading – End of Phase II ...... 42 6.3.4 Figure 4 Broadcast, Radio and Data C-Band Loading - Current ...... 43 6.3.5 Figure 5 Broadcast, Radio and Data C-Band Loading – End of Phase I ...... 44 6.3.6 Figure 6 Broadcast, Radio and Data C-Band Loading – End of Phase II ...... 45 6.4 Customer Services Not Requiring a Move ...... 46 6.5 Non-CONUS Services in the Lower 300 MHz ...... 46 7 Intelsat’s Earth Station Migration Plan ...... 47 7.1 Interim Earth Station and Antenna Data Set Explained ...... 47 7.2 Cable Headends ...... 47 7.3 and Antenna Seeding ...... 47 7.4 Compression ...... 48 7.5 The Church of Jesus Christ of Latter-Day Saints ...... 48 7.6 Broadcast, Religious, Radio and Data Customers’ Affiliate Earth Station Scoping ...... 49 8 Transition Plan Summary ...... 50 8.1 Program Management ...... 50 8.2 High Level Costs ...... 51 8.3 High Level Timeline ...... 52 9 Conclusion ...... 53 Appendix 1: Listing of all earth stations claimed by Intelsat by earth station type Appendix 2: Listing of all earth stations claimed by Intelsat within Phase I’s 46 of the top 50 PEAs Appendix 3: Listing of all earth stations and other applicable sites requiring implementation of technology upgrades to support compression

3 2 Introduction

Intelsat License LLC (“Intelsat”) submits the following Transition Plan in accordance with the requirements set forth in the Federal Communications Commission’s (the “FCC” or the “Commission”) C-band Report and Order.1 This Transition Plan is the result of more than two years of planning and engineering undertaken in conjunction with Intelsat’s customers, industry stakeholders, vendors, and other space station operators in order for 300 MHz of spectrum – inclusive of a 20 MHz guard band -- to be cleared for use by new terrestrial flexible use licensees.

Undertaking the clearing of C-band spectrum is a monumental technical, operational and commercial task layered with highly interdependent activities. The main elements of the plan, which are explained in more detail below, involve the following:

• The construction and launch of seven new satellites to create sufficient capacity to repack services and effectuate spectrum clearing.

o Intelsat has signed manufacturing contracts with two U.S. vendors and has nearly finalized all related contracts so the satellites can be ready to satisfy the timing requirements of the Transition Plan.

• The consolidation of Intelsat Telemetry, Tracking, and Control (“TT&C”)/Gateway antennas into two remote locations on the east and west coast of the United States.

o As of the date of this initial Transition Plan filing, Intelsat has selected one of the two consolidated TT&C sites and has narrowed to two the potential location for the second consolidated site.

• The migration of customers to the upper 200 MHz of the C-band and the corresponding changes required at thousands of cable, broadcast, radio and religious affiliate earth stations.

o Intelsat has partnered with its customers over the past two years and has developed individual migration plans for each customer.

• The installation of filters, antennas and receive equipment into cable, broadcast, radio and data earth stations.

For the transition to be successful, each work stream within these project elements must occur in a tightly scheduled, highly coordinated fashion. The plan relies on the participation and active cooperation of all major stakeholders. In support of that, Intelsat has assembled an internal team of over fifty full time employees focused on the clearing initiative and has partnered with a third party to develop a program management function that will support the leaders of each of the work streams

1 See Expanding Flexible Use of the 3.7-4.2 GHz Band, Report and Order and Order of Proposed Modification, 35 FCC Rcd. 2343 (2020) [hereinafter “Report and Order”].

4 identified in this Transition Plan. Intelsat has developed a comprehensive communications plan to keep customers, earth station operators, suppliers and the broader ecosystem up to date on individual project plans and all related activities.

Intelsat owns and operates the largest fleet of geostationary satellites in the industry. The Commission’s framework adopted in its Report and Order directly effects 25 of Intelsat’s satellites that have coverage into the contiguous United States (“CONUS”).2 In order to clear the lower 300 MHz for use in CONUS, Intelsat will be transitioning and migrating services on its U.S. domestic Galaxy fleet, which currently consists of ten station-kept satellites in the North American arc.3 The Report and Order’s requirements also affect Intelsat’s services on fifteen Ocean Region satellites, where Intelsat will need to migrate antennas to the two new TT&C/Gateway facilities in order to continue to downlink international programming in the lower 300 MHz for contribution to earth stations across CONUS. 4 The construction and launch of new satellites, the antenna migration to new TT&C/Gateway facilities, the migration of customers and the corresponding equipment upgrades required at affiliate earth stations are all integral components to clearing the spectrum in the identified timelines and to providing customers with service continuity throughout the clearing process.

2 The definition of CONUS as used in this Transition Plan is that used in the Report and Order and the Commission’s rules. See Report and Order, App’x A, § 25.103 and § 27.1411(b)(6). 3 The “North American arc” is the portion of the geostationary arc that is used primarily for the distribution of television and radio programming to all fifty U.S. states. It consists of those orbital locations from 87° W.L. through 139° W.L. There are orbital locations outside of this arc that are visible to earth stations in some portion of the contiguous 48 states or to Alaska or Hawaii. Satellites at these non-North American arc locations are referred to herein as “Ocean Region” or “international” satellites. 4 Intelsat has sought reconsideration to allow its continued access to 500 MHz at two consolidated TT&C/Gateway sites in CONUS on a protected basis, so that Intelsat can ensure C-band service continuity to customers on its Ocean Region satellites. See Intelsat License LLC Petition for Reconsideration (May 26, 2020), https://ecfsapi.fcc.gov/file/10526884925025/Petition%20for%20Reconsideration%20- %20Intelsat%2026%20May%202020.pdf. This Transition Plan is not directly dependent upon the Commission’s resolution of this issue. For planning purposes, however, it would be desirable to have the Commission resolve this matter as soon as possible.

5

Prior to the FCC initiating its C-band proceeding, Intelsat analyzed how its customers on Galaxy satellites were planning to densify programming on fewer transponders through compression and terrestrial means over a longer timeframe. The output of this assessment formed the basis of Intelsat’s pre-C-band proceeding satellite replacement plan -- one that would have densified customer content on fewer (high-performance, full-spectrum) satellites. However, the framework contained in the Report and Order reversed this planned path to long-term densification.

To achieve the timeframes specified in the Report and Order, Intelsat must create a “non- commercial” balance of satellite capacity, compression gains, migration activities and “same or better services” to clear the 300 MHz required. The accelerated deadlines create the immediate need to “spread” programming in the upper 200 MHz across all current cable-/broadcast-penetrated

6 satellites, rather than pursuing the previous densification strategy of fewer orbital locations utilizing all 500 MHz. Spreading the content requires the launch of an increased number of partial replacement satellites, as compared to Intelsat’s pre-C-band proceeding plan that would have required the launch of fewer, more densified satellites.

Intelsat is committed to implementing this complex transition and already has taken a number of steps in advance of submitting this Transition Plan – steps that were required in order to align project plan milestones with the Commission’s accelerated deadlines for spectrum clearing. Intelsat remains open to constructive dialogue with all stakeholders in this process, while also noting that some aspects of the planning and process detailed in this Transition Plan cannot be modified without making the project deadlines impossible to achieve.

The FCC’s Report and Order makes receipt of accelerated relocation payments contingent upon Intelsat meeting certain milestone dates, with severe reductions in the payments for missing specified deadlines. Accordingly, Intelsat’s Transition Plan has been carefully orchestrated to meet those aggressive deadlines and there is limited flexibility in this orchestration to accommodate changes. 3 Satellite and Launch Program 3.1 Overview

The Intelsat satellite replacement and launch program works in concert with the customer migration program and provides continuity for every service for which a customer desires continuity, while supporting the clearing of 300 MHz within the required milestone dates. The FCC has recognized that satellite services are an essential part of the communications infrastructure in the United States. The suite of services that Intelsat provides, and will continue to provide both now and post-transition, may be summarized as follows:

Distribution services are services that transmit video and audio programming, as well as data, in a “one-to-many” broadcast mode. The majority of services on the Galaxy fleet provide programing and data Distribution to thousands of affiliate earth stations. To provide some perspective, the Galaxy fleet is the leading Distribution platform for U.S. television and radio programmers, who generate over $80-90 billion annually in revenues from subscription fees, advertising revenues, and other revenue from the delivery of these services.5

Contribution services are services that are critical for the backhaul of television, news, radio and data content from remote events or from distributed content affiliates throughout CONUS. Intelsat has 90 customers that access Contribution transponders for internal or managed solutions (packaging remote truck, production and satellite transport) for events and remote productions. In 2019, Contribution events created over 16,000 C-band service reservations and utilized (at peak use

5 See Derek Baine, Kagan Data Services: Advertising Forecasts (2019 Edition), S&P GLOBAL MARKET INTELLIGENCE (2020).

7 times) over 20 transponders on a simultaneous basis. This is how programmers produce sports, news and special events content.

Restoration services are services that ensure that Contribution or Distribution services have continuity should a satellite suffer a transponder or payload failure, or a terrestrial network anomaly occurs. Restoration services are critical services integrated into the Galaxy fleet to ensure service/business continuity and to protect the enterprise value of Intelsat’s customers. Restoration services are provided as part of the cable service bundle and to broadcaster and data network customers as well. Customers that desire this service can rely on the continuity of their services, pre-planning the “go-to” locations with their earth stations for service restoration and rely on near real time or swift implementation of restoration to minimize any service disruptions.

To implement the Report and Order, Intelsat is integrating multiple principles to: i) clear the quantity of spectrum the Commission requires for CONUS (300 MHz); ii) clear the spectrum within the accelerated timelines dictated by the Report and Order; and iii) provide “same or better” services to Intelsat’s customers and the broader ecosystem.6 This requires balancing a range of requirements.

The sections that follow further detail Intelsat’s customer migration plans. Recognizing the practical constraints, Intelsat’s Transition Plan leverages the following key principles:

• Focus on use of existing “penetrated” orbital locations.

• Prioritize CONUS services on the upper 200 MHz and transition non-CONUS services to the lower 300 MHz.

• Replace Galaxy satellites at penetrated orbital locations and deploy compression to customer services where it materially reduces going-forward capacity and allows programming to fit within the top 200 MHz.

• Simplify many replacement C-band satellite payloads to ten transponders while building a minority of C-band payloads with 24 transponders for Alaska, Hawaii, and off-shore applications.

• Maintain proven component, system, satellite, and in-orbit redundancies to ensure continued operational capability of 99.999% availability or greater.

6 See Report and Order, paras. 32, 171, 194, 201, 239.

8 Simplify C-band payloads for manufacturing and launch schedule Prioritize domestic material and Groom CONUS services to the adherence service sourcing while top 200 MHz while deploying maintaining satellite compression for material manufacturer and launch provider spectrum reclamation diversity for schedule risk management

Placement of in-orbit Leverage existing Success in transition spares to protect against penetrated satellite schedule, operational launch failures and orbital reliability and ensure customer service neighborhoods customer experience levels are sustained

3.2 Galaxy Fleet Satellite Replacement Plan

The Intelsat satellite replacement plan is focused on the ten station-kept Galaxy satellites that contain C-band payloads in the North American arc.7 The C-band payloads on these ten Galaxy satellites currently utilize 500 MHz of C-band spectrum configured as 24 x 36 MHz transponders, with twelve transponders in each linear polarization (horizontal and vertical). These C-band payloads are used to distribute video, radio and data services to thousands of receive sites across North America and the Caribbean. The ten C-band payloads are broadly separated into two categories or applications, with the payloads not generally being interchangeable between the two applications.

Cable Services: Six C-band payloads are used for Distribution and Restoration services to thousands of cable affiliates.

Broadcast and Data Services: Four C-band payloads are used to distribute broadcast TV, radio, and data services, to provide Contribution services for programmers, and to provide Restoration services for broadcast and data clients.

7 See supra note 3.

9

Broadcast and cable television use satellite communications as a cost-effective, reliable, and efficient method to distribute programming. Broadcast and cable programmers over time have congregated on specific satellites, and broadcast affiliates and cable headends installed antennas and receivers (or were given the infrastructure) to receive the satellite-delivered programming. Over time, natural concentrations arose in the form of “neighborhoods.” If a specific C-band payload has earth station equipment installed so that its transmissions are received at all cable or broadcast affiliates, it is 100% “penetrated.” Most Galaxy C-band payloads are 100% penetrated for their specific application. This is the current use state of these satellite payloads, and this has fundamental implications for any swift spectrum clearing and for this Transition Plan.

Leveraging “penetrated” orbital locations is critical to comply with the timing element of the Report and Order. 8 Prior to the proceeding, Intelsat planned to reduce the number of orbital locations over a longer time period (but utilize all 500 MHz) as customers self-compressed and densified their transponder channels. The Report and Order reverses this densification approach and requires an entirely different transition model. Instead, Intelsat must accelerate densification and spread

8 Intelsat’s redeployment of GCI services is an exception to the use of penetrated satellites. Intelsat has coordinated with GCI proactively to bifurcate their non-CONUS network and relocate nearly half of the network from Galaxy 18 to Horizons 3e. Given the shorter warm-weather seasons in Alaska when antenna work can be performed on GCI antennas, Intelsat initiated this GCI network bifurcation in advance of the FCC Report and Order. The GCI network bifurcation allows Intelsat to clear the upper 200 MHz of Galaxy 18 for CONUS services, a critical component of the Transition Plan to clear 300 MHz of spectrum.

10 programming to more orbital locations to clear the 300 MHz than would naturally have existed over the next few years.

Given the practical constraint that most earth stations do not have the technical capability, physical space, or ability to add new receive antennas or license them within the timeframes required, Intelsat would not be able to deploy customer programming to non-penetrated orbital locations. Thus, the only feasible means to achieve the Commission’s accelerated transition schedule requires Intelsat to utilize all -- and only -- penetrated orbital locations.

As a result, Intelsat must replace all current penetrated C-band payloads before their planned end- of-life to successfully spread programming to allow clearing of the necessary spectrum. In tandem with this satellite replacement program, Intelsat must deploy updated compression systems with selected programmer customers, as well as migrate non-CONUS services out of the upper 200 MHz so that the programming intended for Distribution services in CONUS can “fit” into the throughput capacity of the reconfigured Galaxy fleet.9 As previously stated, every service for which a customer desires continuity will be accommodated by this Transition Plan.

3.3 Implementation of Compression/Upgrades to Reclaim Spectrum

Compression is deployed in this Transition Plan solely to reclaim bandwidth/spectrum on an on- going basis within the timeframe of the Report and Order and to ensure all current customer services have continuity on a “same or better” standard. Compression is not being deployed to “future-proof” customer services by increasing current Mbps throughput, allowing for future services such as 4K or 8K, HDR upgrades or ASTC broadcast models. The amount of compression deployed in this

9 See Report and Order, para. 194.

11 Transition Plan is directly dictated by (and balanced by) the amount of available capacity (supply) created by the Intelsat satellite launch plan and the clearing deadlines set by the FCC Report and Order.

Intelsat examined current customer usage and conferred with many customers throughout 2019 about the deployment of compression systems. Intelsat has confirmed the implementation of compression upgrades with ten customers, each of which has expressed agreement to participate in the compression plan. The key considerations for customers for whom compression will be implemented were:

1. Compression and platform upgrades generate material reductions in existing overall capacity usage or capacity usage for the specific orbital location.

2. Customers undergoing compression/platform upgrades may choose the technology provider that is best suited for their operations.

3. Intelsat will contract with and direct compression technology vendors to ensure deliveries and installations of necessary equipment that supports the Report and Order’s accelerated timelines.

The efficiency upgrades envisioned based on discussions with affected customers include a mix of High Efficiency Video Coding (“HEVC”), Advanced Video Coding (“AVC”) and other data compression technologies, coupled with new Integrated Receiver Decoders (“IRDs”) in most cases.

The planned upgrades create a 49.4% reduction in capacity (spectrum) usage for the affected customers, reducing usage from (current) 49.4 transponder units to 25 units post-transition.

Full-time Capacity Reclamation from Planned Compression

Current transponder Final transponder utilization utilization after compression (all frequencies) (4.0 to 4.2 GHz)

49.4 transponders 25 transponders

It should be noted that as the transition evolves, Intelsat may need (or be able) to make revisions to the compression program to adjust for customer developments such as a non-renewal or capacity reductions due to corporate mergers, customers electing alternate Distribution methods or ceasing content Distribution services in the United States.10

10 Intelsat continues to review a compression/optimization alternative with CBS for their Distribution, Contribution and Restoration services. The ViacomCBS loading and transition plan herein reflects a continuation of the current Distribution services. The optimization alternative under study may release a transponder on two satellites for alternate uses.

12 3.4 Transitioning Cable Programmers and Their Earth Station Affiliates

Six of the Galaxy C-band payloads (listed below) currently distribute, and will continue to distribute, programming to cable affiliates. Intelsat estimates that over 720 channels are distributed to over 2,500 cable headends via these six satellites. The Intelsat Transition Plan provides continuity for every channel/programmer that desires continued services.

The gray font identifies the satellites that do not need to be replaced during the transition, as explained in more detail below. Galaxy 12 is not utilized for cable Distribution services due to the antenna tracking limitations related to operating the satellite in Inclined Orbit.

Location and Satellite Service Type C-band Design Replacement 133° W.L. G-15 Non-preemptible Simplified payload Funded replacement 129° W.L. G-12 Inclined (N/A) Simplified payload Funded replacement 127° W.L. G-13 Non-preemptible Full payload Funded replacement 125° W.L. G-14 Non-preemptible NA Intelsat replacement 123° W.L. G-18 Non-preemptible NA Intelsat replacement 121° W.L. G-23 Restoration Simplified payload Funded replacement 91° W.L. G-17 Non-preemptible Simplified payload Funded replacement

Today, five of the six C-band payloads above are used for Distribution services to cable affiliates. The sixth, Galaxy 23, provides Restoration services for the majority of the cable customers who hold contractual rights for service restoral if a partial or full satellite failure occurs. In light of this critical restoration use and customer requirement, most services on Galaxy 23 currently are sold on a preemptible basis – i.e., those customers can be preempted if there is a transponder or spacecraft issue on another Galaxy C-band payload that creates the need to restore services on Galaxy 23.

Four of the six cable arc C-band payloads will need to be replaced to meet the FCC’s accelerated spectrum clearing timeframe. The replacement C-band payloads for Galaxy 13, , , and Galaxy 23 will provide Distribution services. For clarity, the replacement for Galaxy 23 will convert that orbital location from a Restoration role into a Distribution role. Galaxy 15R, Galaxy 17R and Galaxy 23R will be designed with 10 x 36 MHz transponders in the upper 200 MHz of the C- band. Galaxy 13R will be designed with 24 x 36 MHz transponders. The upper transponders will be used for Distribution services in CONUS and the lower transponders will be used for Alaska, offshore and other non-CONUS services.

To provide cable arc customers with a consistent level of Restoration services protection, Intelsat will launch Galaxy 12R and locate the C-band payload at 129° W.L. This satellite will be designed with 10 x 36 MHz transponders and will be the new Restoration payload. This will allow the capacity currently on Galaxy 23 to support Distribution services (leveraging its current cable affiliate penetration).

Intelsat will launch the replacement for Galaxy 14 in Q3 2020. The replacement C-band payload, (formerly Galaxy 14R), was designed with 24 x 36 MHz C-band transponders. The upper

13 transponders will continue to be used by customers for Distribution services to cable headends and the lower transponders will be used to provide services to offshore locations and Alaska. Because Galaxy 30 was planned before the C-band rulemaking, Intelsat will not seek reimbursement for this satellite even through it is critical to, and integrated into, Intelsat’s C-band clearing strategy and project planning.11

Galaxy 18 does not need to be replaced during the clearing period. As such, Intelsat does not intend to seek reimbursement for the Galaxy 18 replacement satellite, even though the replacement will be utilized for service continuity after the clearing period.

Intelsat will seek reimbursement for the C-band payloads on the new Restoration satellite and the four replacement Distribution satellites required to repack Intelsat’s cable programming customers. The number of transponders available for primary cable Distribution will shrink from 144 (6 x 24) today to 60 (6 x 10) post clearing. The upper 200 MHz of spectrum on the Distribution service satellites will be 99.5% loaded after the repacking occurs.

In summary, to successfully clear the lower 300 MHz of spectrum in the CONUS cable arc in the accelerated timeframe and to provide cable customers with the same or better level of service, Intelsat will need to: i) repurpose Galaxy 23 from Restoration services to Distribution services; ii) launch a new Restoration satellite (Galaxy 12R) to 129° W.L.; iii) replace four additional Distribution satellites by the end of the clearing timeframe; and iv) implement the other elements of the Transition Plan discussed below.

3.5 Transitioning Broadcast, Religious, Radio and Data Customers

As stated above, Intelsat uses four of the Galaxy C-band payloads for Distribution, Contribution and Restoration services for broadcast, religious, radio, and data networks. The four satellites that are currently used for these customers are listed in the table below. Of the four satellites, two need to be replaced during the clearing period: and , as identified in black font.

Location and Satellite Service Type C-band Design Replacement 99° W.L. G-16 Non-preemptible Simplified payload Intelsat replacement 97° W.L. G-19 Non-preemptible Simplified payload Intelsat replacement 95° W.L. G-3C Non-preemptible Simplified payload Funded replacement 89° W.L. G-28 Non-preemptible Simplified payload Funded replacement

The replacement and transition strategy in the broadcast arc is less complex than the cable arc. Intelsat does not need to migrate or compress as many services on these four satellites as there is a material amount of capacity currently utilized for Contribution services, which are not “always on.” The primary activities will be to: i) migrate current CONUS services to the upper 200 MHz; ii) migrate non-CONUS services to the lower 300 MHz; iii) reconfigure the location/assignment of Contribution service transponders; iv) compress/upgrade two customers’ services; and v) replace aging satellites.

11 See Report and Order, para. 197, n.528.

14 All four satellites in the arc will be utilized for clearing CONUS Distribution, Contribution and Restoration services.

The two satellites replacing Galaxy 3C and Galaxy 28 will provide: i) Distribution services; ii) Restoration services for key broadcast customers such as ABC, CBS, and Fox; and iii) Contribution services that are critical for event and content production. If these two satellites are not replaced, capacity for contracted Restoration and Contribution services would be reduced below contractually committed levels, which would not meet the “substantially the same or better” service standard adopted by the Commission in the Report and Order.12

The C-band payloads in the broadcast arc are currently designed with 24 x 36 MHz transponders. The replacement C-band payloads will be designed with 10 x 36 MHz transponders, which allows Intelsat to complete repack activities. Additionally, the new broadcast arc satellites can provide continuity for Contribution capacity/services. Intelsat has ninety customers that access Contribution transponders for internal or managed solutions (packaging remote truck, production and satellite transport) for events and remote productions. In 2019, Contribution events created over 16,000 C- band service reservations and utilized (at peak use times) over twenty transponders on a simultaneous basis. The number of transponders available for broadcast Distribution, Contribution and Restoration in CONUS will reduce from 96 (4 x 24) available transponder units today to 40 (4 x 10) units post-transition. The satellites will be 100% utilized in the upper 200 MHz after the repacking efforts, but sized to continue to meet the forecasted peak demand for Contribution services, about which some parties in the proceeding have expressed concern.13

Galaxy 16 and do not need to be replaced during the clearing period. As such, Intelsat does not intend to seek reimbursement for the Galaxy 16 and Galaxy 19 replacement satellites, even though these replacements will be utilized for service continuity after the clearing period.

The cost for the C-band payloads on the seven new satellites is estimated to be $790 million (or $113 million per satellite), which is within the range provided in the preliminary Cost Catalog published by the Wireless Telecommunications Bureau.14

12 See Report and Order, paras. 32, 171, 194, 201, 239. 13 See, e.g., Comments of PSSI Global on SSO Joint Petition for Stay, 15-17 (May 27, 2020), https://ecfsapi.fcc.gov/file/105272141027253/PSSI%20Comments%20on%20SSO%20Joint%20Petit ion%20for%20Stay%20and%20Attachments.pdf. 14 See Wireless Telecommunications Bureau Seeks Comment on Preliminary Cost Category Schedule for 3.7-4.2 GHz Band Relocation Expenses, Public Notice, GN Docket No. 18-122, DA-20- 457, Attachment, 4 (Apr. 27, 2020), https://www.fcc.gov/document/wtb-seeks-comment-37-ghz- band-preliminary-cost-category. As Intelsat has noted in other filings in this proceeding, it will add additional payloads on some of the satellites identified above, but only if those payloads can be added without interfering with the compressed spectrum clearing schedule requirements and be

15 The individual customer transition activities and future loading plans for the broadcast arc satellites are discussed below.

3.6 New Satellite Launch Program

The seven satellites discussed above will be launched on four separate launch vehicles, using at least two different launch service providers. Intelsat has developed a launch program that places each satellite in service by the end-of-life of each replaced satellite, with an appropriate margin to ensure clearing deadlines can be met. Intelsat has integrated manufacturer and provider diversity in this new satellite launch plan to manage schedule risk, to increase the probability of success in meeting the proposed clearing deadlines, and to reduce the overall program cost. Six of the satellites will launch in pairs and one is planned to be a dedicated launch. The table below outlines the new satellite and launch vehicle program, which is described in further detail below.

In Service Satellite Launch Launch Location and Satellite Date Manufacturer Vehicle Sequence 121° W.L. G-23R Q3 2022 Maxar Provider 1 Launch 1 91° W.L. G-17R Q3 2022 Maxar Provider 1 Launch 1 129° W.L. G-12R Q3 2022 Northrop Grumman Provider 1 Launch 2 133° W.L. G-15R Q3 2022 Northrop Grumman Provider 1 Launch 2 95° W.L. G-3CR Q4 2022 Maxar Provider 2 Launch 3 89° W.L. G-28R Q4 2022 Maxar Provider 2 Launch 3 127° W.L. G-13R Q3 2023 TBD TBD Launch 4

The first pair of satellites will be manufactured by Maxar and will replace Galaxy 23 and Galaxy 17. In order to meet clearing deadline dates, Intelsat started the program (at risk) for these satellites in April 2020 in advance of an effective Report and Order.15 The pair of Maxar satellites will be launched on a single launch vehicle and the satellites are expected to be in service by Q3 2022. Intelsat plans to finalize the launch vehicle contract for these two satellites in Q3 2020.

The second pair of satellites will be manufactured by Northrup Grumman and will replace Galaxy 12 and Galaxy 15. In order to meet the FCC’s accelerated clearing deadlines, Intelsat started the

consistent with FCC cost reimbursement guidelines. See Report and Order, para. 201; Intelsat License LLC Notice of Ex Parte Meeting (May 26, 2020), https://ecfsapi.fcc.gov/file/10526045231531/Ex%20Parte%20Meeting%20- %20Intelsat%2026%20May%202020.PDF. 15 Intelsat entered into an Authorization to Proceed (“ATP”) agreement with the manufacturer for the purpose of ordering long lead-time items.

16 program (at risk) for these satellites in April 2020.16 The pair of satellites will be launched on a single launch vehicle and are expected to be in service by Q3 2022. Intelsat plans to finalize the launch vehicle contract for these two satellites in Q3 2020.

The third pair of satellites will be manufactured by Maxar and will replace Galaxy 3C and Galaxy 28. In order to meet the FCC’s accelerated clearing deadlines, Intelsat started the program (at risk) for these satellites in April 2020.17 The pair of satellites will be launched on a single launch vehicle and the satellites are expected to be in service by Q4 2022.

Intelsat plans to contract with a second launch services provider for the launch of this third pair of satellites. The selection of a second launch services provider provides diversity in the event of a launch failure of the first launch provider (an industry standard action), which also significantly de- risks the overall satellite deployment schedule. Intelsat plans to be under contract with the second launch provider in Q3 2020.

Intelsat is currently evaluating proposals for Galaxy 13R from multiple satellite manufacturers and plans to start the program in September 2020. Intelsat plans to finalize the launch vehicle contract in tandem with the satellite manufacturer decision. As is commercially standard, cost, schedule availability, and vehicle reliability will be the key determining factors in vendor selection. Intelsat plans to have Galaxy 13R in service by December 5, 2023 – in line with the spectrum clearing milestones. The timing of the initial launch is intended to provide Intelsat with enough schedule margin to complete a second satellite program, as described above, in the event of a launch failure of the first. This will provide customers with additional protection against service interruption through the end of the clearing period.

The total cost for the four launch vehicles and the associated launch insurance is estimated to be $390 million.

Should a launch failure occur, Intelsat will confer with the relevant satellite manufacturers and launch service providers to determine if a replacement launch can occur in a timely manner. If a relaunch attempt can be made prior to the end-of-life of the satellite(s) being replaced, construction is most likely the preferred path. If a relaunch attempt cannot be made prior to the end-of-life of the satellite(s) being replaced, Intelsat will reconfigure the orbital deployment of the C-band payloads to prioritize Distribution services.

16 Id. 17 Id.

17 The total cost of Intelsat’s C-band replacement satellite portion of the Transition Plan, including launch, insurance, and program management, is estimated to be $1.18 billion, which is well within the range of reasonable costs that the FCC estimated with respect to satellite procurement and launch costs.18 4 TT&C Gateway Relocation and Ground Systems Grooming

In addition to the effort associated with the Galaxy spacecraft and grooming activities discussed above, there will be an equally significant amount of work required on the ground to facilitate service continuity for customers downlinking programming into CONUS from Intelsat’s Ocean Region satellites (Pacific and Atlantic) and to ensure that Intelsat can continue to command and control certain satellites from the two new TT&C/Gateway locations it has selected on the east and west coast of the United States prior to the Commission’s Phase I and Phase II deadlines.19 This Transition Plan discusses each phase separately below.

18 Report and Order, para. 210. 19 As Intelsat explained in its pending Petition for Reconsideration, robust TT&C operations, including orbit raising, are critically important to the safety of flight of Intelsat’s satellites, as well as to service continuity. Intelsat relies upon TT&C functions to maintain control of its satellites and interference with TT&C carriers cannot occur without jeopardizing the satellites’ safety. Intelsat has presented its concerns about adequate protection of the TT&C signals to the Commission and

18

4.1 Phase I Transition Activities

Intelsat currently operates teleports in Riverside, Filmore, and Napa, California, which support customer services or TT&C carriers that will need to be relocated prior to the Phase I deadline. A few of these services/carriers can be transitioned to Intelsat’s Paumalu teleport on the island of Oahu, Hawaii. However, the majority will need to be transitioned to Intelsat’s new West Coast consolidated TT&C/Gateway teleport in Brewster, Washington. The work that is already underway to consolidate activities at these two sites is discussed below.

4.1.1 Paumalu Teleport

Intelsat currently operates a full-motion, C-band antenna at Intelsat’s Fillmore teleport to support orbit raising operations for Intelsat and third-party satellites utilizing frequencies in the lower 120 MHz of the C-band. To replace this Fillmore antenna, a new full-motion C-band antenna will need to be built at Paumalu to support these requirements moving forward. Given the long lead times associated with this type of antenna, Intelsat placed an order to purchase this asset in May 2020 to ensure operational readiness by December 2021.

Intelsat currently supports customer services on Horizons 3e and Intelsat 19 at its Napa teleport in the lower 120 MHz of the C-band. These services must transition to Paumalu. This additional customer traffic, coupled with the increase of ground equipment to support this traffic in Paumalu, necessitates upgrades in Intelsat’s electrical infrastructure and an increase in fiber capacity to sought protected access for all 500 MHz at its consolidated TT&C/Gateway sites, as well as reconsideration of the technical specifications for the TT&C filters required to safely control satellite operations post-transition.

19 provide connectivity back to Intelsat’s mainland points of presence (“PoPs”). The planning for this work is in progress and expected to be complete by mid-summer 2021.

4.1.2 Brewster Teleport

The Brewster teleport is located in a remote area of eastern Washington state and has been selected as Intelsat’s West Coast consolidated TT&C/Gateway teleport. Intelsat will be procuring seven new antennas to be installed at the Brewster facility. These antennas will be taking over TT&C operations and providing spectrum monitoring for satellites serving CONUS from the Atlantic and Pacific Ocean regions. Intelsat will also downlink customer C-band services in the lower 300 MHz at this teleport, although the Report and Order does not accord those services protected status.20 The specific satellites requiring new antennas for TT&C and supporting customer traffic are Intelsat 18, , , and . Intelsat will also relocate its West Coast TT&C rover antenna21 to Brewster, as well as its two rover antennas for spectrum monitoring across the fleet.

Significant upgrades will be required at the Brewster teleport to accommodate these seven new antenna systems and associated radio frequency (“RF”) equipment, specifically to the electrical power infrastructure, environmental systems, and terrestrial fiber capacity. These upgrades are required to meet the increased load associated with the new systems and to bring the teleport infrastructure up to the baseline standard that exists at Intelsat teleports, allowing continued high- availability Service Level Agreements (“SLAs”) contained in Intelsat’s customer contracts.

Given the requirement to have these new systems operationally ready by the Phase I deadline of December 2021, Intelsat has already engaged with the Brewster facility in designing the preliminary construction activities and has issued and funded an ATP, allowing the ordering of long-lead items. The plan is to complete the required infrastructure upgrades and the installation of the antenna foundations by the end of 2020. In 2021, antenna construction will begin in parallel with the ongoing infrastructure upgrades. Services will be gradually transitioned from existing facilities over the course of 2021. The final antenna system will come online in November of that year.

4.2 Phase II Transition Activities

Phase II transition activities are specific to antennas and services currently supported at Intelsat’s two East Coast teleports in Atlanta, Georgia and Hagerstown, Maryland. Most of these services will be relocated to Intelsat’s East Coast consolidated TT&C/Gateway teleport. Two services cannot be

20 In order to ensure service continuity for customers on Ocean Region satellites that downlink to CONUS, Intelsat has sought reconsideration of the issue of protected use of the lower 300 MHz at the two TT&C/Gateway sites. See Intelsat License LLC Petition for Reconsideration (May 26, 2020). 21 Intelsat utilizes TT&C rover antennas for certain satellites that are designed not to require dedicated ranging from two separate earth stations. This design allows a single antenna to provide temporary TT&C ranging support across multiple satellites, where applicable.

20 supported at that site due to satellite coverage constraints and will be transitioned to international teleport locations within their respective coverage areas.

4.2.1 East Coast Consolidated TT&C/Gateway Teleport

Consistent with the Report and Order, Intelsat is currently pursuing two alternatives for an East Coast consolidated TT&C/Gateway teleport, both of which either were or are operational teleports.22 Intelsat is engaged in a due-diligence phase with the owners of both sites. Both locations meet the FCC-established criteria for a consolidated TT&C/Gateway teleport.23 Intelsat will have to relocate six antenna systems to whichever facility is chosen. These antennas will support TT&C operations, will provide spectrum monitoring for services on Intelsat’s Atlantic Ocean fleet, and will be utilized to downlink C-band services in the lower 300 MHz for customers who deliver international programing to affiliates in CONUS.24 The specific satellites are , Intelsat 25, , and Intelsat 37e. Intelsat also intends to relocate its East Coast TT&C rover antenna and its East Coast full-motion launch support antenna to this East Coast consolidated teleport.

Like the Brewster teleport site, significant upgrades will be necessary for the existing power systems, environmental systems, and terrestrial connectivity at Intelsat’s selected East Coast facility to support the new antenna systems and meet contractual SLAs with Intelsat’s customers. The overall cost and timeline associated with these required improvements at the two possible locations are among the topics being considered as part of the due diligence in Intelsat’s decision-making process.

Intelsat expects to contract for this last consolidated teleport site by Q4 2020. At that point, planning and detailed site design efforts will commence, followed by construction activities kicking off in Q2 2021. The East Coast site will be ready for operations in Q3 2023.25

4.2.2 Latin America Teleport

Intelsat currently supports services on from its teleport in Atlanta, Georgia. Because Intelsat 14’s coverage area does not extend far enough North to be received by either of the sites under consideration for the East Coast consolidated teleport, Intelsat will need to identify and contract with a teleport in Latin America to provide spectrum monitoring for this satellite. Planning

22 See Report and Order, paras. 374-77 (listing selection criteria for the consolidated TT&C sites). 23 As noted above, Intelsat sought reconsideration to allow its continued access to 500 MHz at two consolidated TT&C/Gateway sites in CONUS on a protected basis, so that Intelsat can ensure service continuity of C-band services on these non-North America arc satellites. See Intelsat License LLC Petition for Reconsideration, 5-7 (May 26, 2020). 24 See id. 25 Another aspect of Intelsat’s Petition for Reconsideration is a request that the Commission extend the date for the consolidation of Intelsat’s TT&C/Gateway sites to the Phase II deadline, as a Phase I deadline for this activity is infeasible given the amount of work required. See id. at 20-22.

21 for this activity will commence in late 2020 and the antenna will be ready for operation no later than Q2 2023.

4.2.3 Hartebeesthoek, South Africa Teleport

Multiple -series satellites will go into inclined orbit operation over the next five years and once inclined, will not be supportable by the East Coast consolidated teleport due to look-angle restrictions at both sites that are under consideration. Primary TT&C operations for each of these satellites will continue to occur at Intelsat’s Fuchsstadt teleport in Germany, but the back-up TT&C mission currently being supported in Atlanta or Hagerstown will be transitioned to a single TT&C rover antenna to be constructed in Hartebeesthoek, South Africa. This same rover antenna will also provide back-up TT&C services for Intelsat 14. Planning for these activities will commence in late 2020 and the antennas will be ready for operation in Q2 2023.

4.3 Summary of Antenna Relocations

Satellite Current Antenna Current Antenna Antenna New Antenna Function Location Size Location Horizons 3e Customer traffic Napa, CA 9M Paumalu, HI Intelsat 19 Customer traffic Napa, CA 9M Paumalu, HI Full-Arc Launch Support Fillmore, CA 13M Paumalu, HI Intelsat 18 TT&C/Customer Riverside, CA 13M Brewster, WA traffic Intelsat 23 TT&C/Customer Riverside, CA 13M Brewster, WA traffic Intelsat 34 TT&C/Customer Riverside, CA 13M Brewster, WA traffic Intelsat 21 Customer traffic Atlanta, GA 7M Brewster, WA Full-Arc Spectrum Hagerstown, MD 7M Brewster, WA Monitoring Full-Arc Spectrum Atlanta, GA 7M Brewster, WA Monitoring Full-Arc TT&C Rover Filmore, CA 13M Brewster, WA (West) Intelsat 901 MEV TT&C/Customer Hagerstown, MD 13M TBD East Coast traffic Teleport Intelsat 35e TT&C/Customer Hagerstown, MD 13M TBD East Coast traffic Teleport Intelsat 37e Customer traffic Hagerstown, MD 13M TBD East Coast Teleport Intelsat 25 TT&C/Customer Hagerstown, MD 13M TBD East Coast traffic Teleport Full-Arc Launch Support Hagerstown, MD 13M TBD East Coast Teleport Full-Arc TT&C Rover (East) Hagerstown, MD 13M TBD East Coast Teleport Intelsat 14 Customer traffic Atlanta, GA 9M Bogota, Columbia Intelsat 14, 902, TT&C Hagerstown, MD 13M Hartebeesthoek, 903, 904 and 905 and Atlanta, GA South Africa

22 4.4 TT&C Antennas for the Seven New Galaxy Satellites

In order to meet the accelerated relocation timeline, Intelsat needs to upgrade or build seven antennas to support TT&C operations on the Galaxy replacement satellites. To the greatest extent possible, Intelsat will attempt to re-purpose existing antenna systems that become available as older satellites are retired. A summary of the TT&C antenna requirements for the replacement satellites is specified below:

Satellite TT&C Band Solution Galaxy 17R C Upgrade existing antenna at the Riverside, CA teleport Galaxy 23R C New antenna to be built at the Napa, CA teleport Galaxy 15R C Upgrade existing antenna at the Atlanta, GA teleport Galaxy 12R C Upgrade existing antenna at the Riverside, CA teleport Galaxy 13R Ku Upgrade existing antenna at the Atlanta, GA teleport Galaxy 28R C New antenna to be built at either the Riverside or Napa, CA teleport Galaxy 3CR C New antenna to be built at either the Riverside or Napa, CA teleport

The total cost for Intelsat’s TT&C/Gateway relocation and ground system grooming plan is estimated to be $95 million. 5 Work Associated with Repacking the C-Band

In order to successfully clear the 300 MHz as required in the Report and Order, Intelsat will need to partner with customers and earth stations to reconfigure satellite transmissions/carriers and receive sites. The framework for this undertaking is explained generally in this section, then specifically itemized for each customer migration in Section 6 below.

Intelsat has partnered with its customers to develop the individual migration plans since the FCC issued the initial Notice of Proposed Rulemaking in July 2018, when it was evident there would be significant spectrum clearing in the C-band.26 Proposed migration plans for each customer have been refined, with customer inputs, over the course of more than a year. The following steps were taken to share information with customers throughout the process and to finalize their specific migration plans:

• Intelsat has organized monthly C-band customer group calls, as well as held individual meetings on an ongoing basis, to provide its customers with information about the proceeding and to address concerns.

• Each customer has been provided a unique migration plan detailing the impact of the clearing on their own services. If there was customer feedback on specific migration plans,

26 Expanding Flexible Use of the 3.7 to 4.2 GHz Band, Notice of Proposed Rulemaking, 33 FCC Rcd. 6915 (2018).

23 that feedback was incorporated into further iterations of the plan to the extent possible to limit the impact on customer services throughout the plan period.

• These plans have been adjusted over time to account for integration concerns, to adjust the timelines as the clearing dates were finalized, and to compensate for revisions to customer notification requirements.

• Individual plans were finalized and delivered to all customers the week of May 18, 2020.

Intelsat’s plan was built to provide the highest level of certainty to meet the accelerated clearing timelines set forth in the Report and Order. The selection of customers for revisions (frequency, polarization, satellite, or technology upgrades) was an objective-based exercise performed in good faith.27 The plan assumes compression/technology upgrades for ten customers in order to reclaim material amounts of capacity.28 Material changes to the plan to accommodate additional customer moves or upgrades will negatively impact the schedule.

5.1 Process and Communications about Customer Transitions

Clear communications and coordination between Intelsat, its customers, and the earth station operators are critical for the Transition Plan to be a success. The following provides information about the processes that will be used for contacting earth station operators and for coordinating the required work at affiliate locations.

Intelsat is currently conducting outreach to all earth stations registered in the Commission’s International Bureau Filing System (“IBFS”) database. This action will ensure that the earth station data listed in the IBFS database is accurate and it will confirm the current operating environment of each earth station. Intelsat will reconcile this information against its customer affiliate lists. The data compiled will allow Intelsat to define hardware solutions for all earth stations to ensure the “same or better service” standard throughout the clearing process.

Intelsat has contracted with the companies listed below to perform the outreach, to develop the affiliate level transition plans, and to ensure customer migrations are implemented within the defined timeframes:

1. USSI Global (Melbourne, Florida): cable affiliates

2. WESCO [formerly Satellite Engineering Group] (Kansas City, Missouri): broadcast, radio and religious affiliates

3. ATCi (Chandler, Arizona): Simulsat (multi-satellite antennas) antenna filtering

27 See also supra note 10. 28 The ten customers referenced here are listed in Section 7.4.

24 4. Convergent Media (Alpharetta, Georgia): data analysis and work order management

Validated affiliate data will be captured in a centralized database and used to generate earth station- specific work orders that will be executed by one of Intelsat’s equipment installers. The installers will contact the earth station as required to schedule a service window during the dual illumination period outlined in each customer’s individual migration plan. During the service window, the installer will perform the work necessitated by the earth station change type outlined in the plan below.

5.2 Earth Station Change Types

In the customer migration plans, each transition can require one or more changes to the customer’s service. These changes necessitate that specific work be performed at the earth stations that receive a customer’s programming. The description of each potential earth station change type is identified below. Note that in the following sections, any work Intelsat commits to complete is for eligible earth stations that have not opted out of satellite operator assistance (unless otherwise noted):

Change Type

• N – No change to satellite, frequency, or polarity (service remains “as-is”) • F – Frequency change • R – Transponder reassignment of in-orbit protection bandwidth • P – Polarity change • S – Satellite change • C – Compression required

5.2.1 Frequency Change [F]

The simplest earth station change is when a service moves from one frequency to another on the same satellite without a change in polarization. The associated work involved at the earth station is to retune the receiver equipment to accept the signal at the new frequency. This work is routine, as satellite operators groom services on satellites and earth stations perform receiver retuning in the normal course of business. Generally, Intelsat will not need to send a technician out to perform these types of frequency changes unless: 1) the frequency change is part of additional work being performed at the same time, such as a filter installation or an antenna repoint; or 2) the earth station owner explicitly requests an installer perform the task due to lack of technical expertise at the site or if an unexpected issue arises in making the change.

5.2.2 Transponder Reassignment of In-Orbit Protection Bandwidth [R]

This change is relevant only for customers who have purchased Restoration services. As a result of the clearing process, some customers are being asked to relocate their Restoration capacity to another frequency or satellite. This change requires no actual work on the ground or satellite during the clearing period but is noted to account for the changes to the overall loading plans of each satellite.

25 5.2.3 Polarity Changes [P]

Polarity changes occur when a service moves to a new frequency on the satellite and that frequency uses the opposite polarity (e.g., horizontal vs. vertical). The antenna feed at earth stations that receive that service will need to be able to accept the alternate polarity. In some cases, an adjustment or replacement to the antenna feed may need to be performed. Intelsat will send an installer to perform this work during the dual illumination period.

5.2.4 Satellite Changes [S]

In order to repack services into the upper 200 MHz, some of Intelsat’s customers have been asked to move to a different Intelsat satellite. These types of transitions are not unusual, are commercially and technically reasonable, and involve a dual illumination of services so that earth stations may reconfigure antennas and receivers to the new satellite/location without loss of service.

In order to increase the supply of capacity for Distribution services in the Galaxy cable arc, Intelsat will launch a supplemental antenna program for Galaxy 18 and Galaxy 23. The antenna program will ensure that all satellites in the cable arc are 100% penetrated and will provide customers with service continuity throughout the clearing process. Intelsat intends to supply American-made 3.7M single or dual-feed antennas as part of this supplemental program. Customers will migrate to Galaxy 18 and Galaxy 23 once the antenna seeding program is completed in 2021.

5.2.5 Compression/Technology Upgrades Required [C]

In order to achieve the spectrum reclamation directed by the Commission, Intelsat will need to deploy compression upgrades with selected customers. Intelsat has identified and conferred with the customers whose compression upgrades will yield the most spectrum gains/reclamation. The effect of the compression upgrades is discussed in Section 3.3.

Compression and technology upgrades require close coordination between Intelsat’s customers, Intelsat, and the earth stations receiving the new equipment. Intelsat will work with each of the customers that are upgrading to define the equipment required and to ensure deployment by the phase end dates. Customers will identify specific earth station requirements by site and select, in conjunction with their vendors, the quantity of receivers required at each receive site. Intelsat will be responsible for ordering the materials specified on each customer’s bill of materials from the applicable vendor and will deliver the materials to the earth station owner for installation.

Intelsat’s installers will offer turnkey installation services, including shipping required IRDs to earth stations, labeling the equipment in a standard, easily-understandable format for the earth station operators, and, where necessary, racking and cabling the equipment in the earth station facility under the direction of the earth station technical resource assigned to sign off on the work.

In some cases, temporary cooling, floor space, or power may be required while the additional IRDs are added and before legacy IRDs can be retired. In these rare cases, Intelsat and its installers will design/procure commercially reasonable temporary solutions to alleviate the bottleneck of power, cooling, and floor space. If an earth station requires long-term adjustments to core power, cooling,

26 or floor space, Intelsat expects the earth station operators to make the upgrades and seek reimbursement directly from the Clearinghouse for those expenses.

5.3 Filter Installation

All CONUS earth stations will require the installation of a passband filter to mitigate potential interference from 5G signals, and some earth stations will require an interim filter, as explained below. Intelsat’s installers will provide and install a filter for every qualified antenna feed at earth stations that Intelsat claims responsibility for in Section 7 of this Transition Plan.29 Given the universal application of the filters, the installations are not reflected in the Transition Plan as a distinct change type. Each filter will have the following characteristics:

1. The filters are passive and require no electrical power to work.

2. The filters are generally less than 12” long, made of aluminum and bolt onto the antenna feed. The specification sheet for the filter Intelsat will be using will be posted on the Intelsat C-band microsite in Q3 2020, which will be accessible via www.Intelsat.com.

3. The filter is also designed to serve as an altimeter radar filter. Thus, in cases where existing antenna feeds have an altimeter filter installed, Intelsat’s implementation vendors will remove the altimeter filter and replace it with the new dual-purpose (5G and altimeter) filter.

5.3.1 Filter Versions

The Report and Order’s accelerated timeline specifies the release of the lower 300 MHz spectrum in two phases, allowing mobile networks to begin operations in 46 PEAs as early as December 6, 2021 (Phase I). In order to address the two-phased approach of the accelerated spectrum clearing, Intelsat has developed two filters and a deployment plan that allows for the filtering of satellite transmissions in the defined timeframe. The version of the filter to be installed will be based on the frequency range in which an earth station is receiving programming as of the milestone dates.

The “Blue” filter version will be deployed to filter spectrum from 3700-4000 MHz and will allow the earth stations to receive transmissions from 4000 to 4200 MHz.

The “Red” filter version will be deployed to filter spectrum from 3700-3820 MHz and will allow the earth stations to receive transmissions from 3820 to 4200 MHz.

29 Section 7 of Intelsat’s Transition Plan will be revised once it is known which earth stations have opted out.

27 5.3.2 Phase I Filtering

All earth stations in and around the top 46 PEAs must have a filter installed by the Phase I deadline (December 5, 2021) or be at risk of interference from 5G base stations being deployed. Intelsat has identified a preliminary list of earth stations impacted in Phase I in Appendix 2.30

Any earth station antenna feeds in these PEAs receiving programming in the frequency range of 3820-4000 MHz after December 5, 2021 will need to have Red filters installed. These filters will be replaced by Blue filters in Phase II.

Any earth station antenna feed in these PEAs that receives programming only in the 4000-4200 MHz range will only be required to have a Blue filter installed.

5.3.3 Phase II Filtering

By the December 5, 2023, the Phase II deadline, all CONUS receive antenna feeds will be equipped with Blue filters. This includes replacement of the Red filters installed in Phase I.

Intelsat will clear spectrum starting at the bottom of the frequency range, and then move higher. Customers located in the frequency range of 3700-3820 MHz will be transitioned to their end state location in the upper 380 MHz during Phase I. Any services in the frequency range of 3820-4000 MHz will be transitioned to their end state in Phase II. In both phases, filters can only be installed after the services have been migrated to the end state for that phase. Installing filters before this point in time would cause disruption to the service.

At many cable headends, antenna feeds take multiple services off the same satellite and the earth station filter cannot be installed until the last service is cleared on the relevant satellite. Due to this, the Intelsat Transition Plan relies on cable headend filter installations occurring exclusively within the last 6 months of each phase. This will ensure that filters are not installed while services are not yet cleared.

The total cost of Intelsat’s repacking and customer migration plan is estimated to be $400 million.

5.3.4 Earth Station Operator Responsibilities

Intelsat plans to standardize its approach to earth station owners to ensure roles and responsibilities are clear throughout implementation. Intelsat is undertaking substantial work and risk to meet the Commission’s ambitious spectrum clearing timeline and understands that the service migrations required in this Transition Plan may be challenging for earth station owners. While the process

30 Intelsat notes that the IBFS dataset includes multiple records for the same Legal Name of Applicant (Address Name) and physical earth station location (address), and there does not appear to be a consistent means to identify duplicates and their associated primary record. For all appendices to this Transition Plan, Intelsat has included data elements that indicate a best attempt to tag duplicates and associate them with the parent Site Key that Intelsat presumes may be the current record. Intelsat chose the most recent, active filing, where possible, as the parent record of a group of apparent duplicates.

28 defined above is intended to offset much of the technical work that would be required at the receive earth stations (on a cost-free basis to the earth station operators), it is dependent on earth station operators providing local site access, technical input and cooperation.

Each earth station operator is responsible for facilitating access to the site on a timely and reasonable basis. Intelsat will ask earth station operators to identify and provide access to a technical resource representative who is authorized to approve the work. Intelsat’s installers cannot begin work without an assigned representative.

29 6 Customer Migration Plans

The following section provides the detailed migration plans for customer services. Three different views of the same migration plan are presented: (1) a chronological view of the planned transition activity, (2) a customer-centric view of the transitions, and (3) a view of satellite transponder loading across the migration phases.

6.1 Transition Plan (Chronological)

The below tables illustrate the detailed transition activities planned in chronological order across Phase I and Phase II of the migration.

6.1.1 Table 1 Phase I Grooming Plan Transition Activities (Chronological)

Phase I Lower Upper Phase 1 Lower Upper Phase I Duration Phase I Change Start Freq. Freq. End Freq. Freq. Technology Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Upgrade 05-Dec-19 548 05-Jun-21 C, F NPR G-16 01C 3702 3738 G-16 23C 4142 4178 Audio 05-Dec-19 548 05-Jun-21 C NPR G-16 23C 4142 4178 G-16 23C 4142 4178 Audio 05-Dec-19 239 31-Jul-20 C, F NPR G-16 07C 3822 3858 G-16 23C 4142 4178 Audio 28-Feb-20 90 28-May-20 S, P, F GCI G-18 18C 4042 4078 H-3e 29-Feb-20 90 29-May-20 S, P, F GCI G-18 19C 4062 4098 H-3e 21-Mar-20 90 19-Jun-20 S, P, F GCI G-18 21C 4102 4138 H-3e 27-Mar-20 90 25-Jun-20 S, P, F GCI G-18 20C 4082 4118 H-3e 31-Mar-20 90 29-Jun-20 S, P, F GCI G-18 11C 3902 3938 H-3e 02-Apr-20 90 01-Jul-20 S, P, F GCI G-18 17C 4022 4058 H-3e 03-Apr-20 90 02-Jul-20 S, P, F GCI G-18 15C 3982 4018 H-3e 03-Apr-20 90 02-Jul-20 S, P, F GCI G-18 23C 4142 4178 H-3e 20-May-20 0 20-May-20 R Disney OU Pool G-16 08C 3842 3878 G-16 09C 3862 3898 04-Jun-20 5 09-Jun-20 F Televisa G-16 20C 4082 4118 G-16 08C 3842 3878 10-Jun-20 0 10-Jun-20 R FoxCorp Restoration G-16 13C 3942 3978 G-16 20C 4082 4118 10-Jun-20 20 30-Jun-20 F Televisa G-19 16C 4002 4038 G-19 08C 3842 3878 11-Jun-20 0 11-Jun-20 R Disney OU Pool G-16 17C 4022 4058 G-16 13C 3942 3978 30-Jun-20 0 30-Jun-20 R Disney OU Pool G-16 22C 4122 4158 G-16 11C 3902 3938 01-Jul-20 30 31-Jul-20 F EWTN G-15 05C 3782 3818 G-15 23C 4142 4178 01-Jul-20 30 31-Jul-20 F US Government G-3C 24C 4162 4198 G-3C 08C 3842 3878

30 Phase I Lower Upper Phase 1 Lower Upper Phase I Duration Phase I Change Start Freq. Freq. End Freq. Freq. Technology Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Upgrade 01-Jul-20 30 31-Jul-20 F Sinclair G-17 06C 3802 3838 G-17 10C 3882 3918 01-Jul-20 30 31-Jul-20 F Sinclair G-17 17C 4022 4058 G-17 15C 3982 4018 01-Jul-20 30 31-Jul-20 F The CW G-17 01C 3702 3738 G-17 19C 4062 4098 01-Jul-20 90 29-Sep-20 S, F TV Azteca G-19 03C 3742 3778 G-16 22C 4122 4158 01-Jul-20 9 10-Jul-20 F Televisa G-16 24C 4162 4198 G-16 12C 3922 3958 01-Jul-20 180 28-Dec-20 F Discovery G-13 14C 3962 3998 G-13 24C 4162 4198 01-Aug-20 0 01-Aug-20 R ViacomCBS G-3C 12C 3922 3958 G-3C 24C 4162 4198 01-Aug-20 30 31-Aug-20 F Word Network G-17 03C 3742 3778 G-17 19C 4062 4098 01-Oct-20 30 31-Oct-20 F LeSea Broadcasting G-16 15C 3982 4018 G-16 17C 4022 4058 01-Oct-20 90 30-Dec-20 C, F Encompass G-13 06C 3802 3838 G-13 16C 4002 4038 AVC 01-Oct-20 90 30-Dec-20 C, S, F Encompass G-14 05C 3782 3818 G-13 16C 4002 4038 AVC 01-Oct-20 90 30-Dec-20 C, S, P, F Encompass G-17 21C 4102 4138 G-13 23C 4142 4178 AVC 29-Dec-20 0 29-Dec-20 R GCI Restoration G-13 24C 4162 4198 G-13 14C 3962 3998 31-Dec-20 0 31-Dec-20 R GCI Restoration G-13 16C 4002 4038 G-13 06C 3802 3838 31-Dec-20 90 31-Mar-21 C, F FoxCorp G-17 05C 3782 3818 G-17 21C 4102 4138 HEVC 01-Jan-21 30 31-Jan-21 F Rignet G-19 17C 4022 4058 G-19 09C 3862 3898 01-Jan-21 90 01-Apr-21 C, F Disney G-14 11C 3902 3938 G-14 07C 3822 3858 HEVC 01-Jan-21 90 01-Apr-21 C, S, P, F Disney G-15 02C 3722 3758 G-17 17C 4022 4058 HEVC 01-Jan-21 90 01-Apr-21 C, P, F Disney G-17 02C 3722 3758 G-17 17C 4022 4058 HEVC 01-Jan-21 90 01-Apr-21 C FoxCorp G-15 10C 3882 3918 G-15 10C 3882 3918 HEVC 01-Jan-21 90 01-Apr-21 C FoxCorp G-17 16C 4002 4038 G-17 16C 4002 4038 HEVC 04-Jan-21 30 03-Feb-21 F The Church of Jesus Christ of Latter-Day Saints G-19 11C 3902 3938 G-19 17C 4022 4058 31-Jan-21 30 02-Mar-21 F Music Choice G-14 22C 4122 4158 G-14 22C 4140 4158 01-Feb-21 30 03-Mar-21 F BBC / Intelsat MCPC platform G-13 04C 3762 3798 G-13 20C 4082 4118 01-Feb-21 30 03-Mar-21 F Caracol / Intelsat MCPC platform G-13 04C 3762 3798 G-13 20C 4082 4118 01-Feb-21 30 03-Mar-21 F Mega Media / Intelsat MCPC platform G-13 04C 3762 3798 G-13 20C 4082 4118 01-Feb-21 30 03-Mar-21 F NHK / Intelsat MCPC platform G-13 04C 3762 3798 G-13 20C 4082 4118 01-Feb-21 90 02-May-21 S, F AT&T Sports G-17 20C 4082 4118 G-18 23C 4142 4178 01-Feb-21 90 02-May-21 S, F ATCi G-13 18C 4042 4078 G-23 23C 4142 4178 01-Feb-21 90 02-May-21 S, F Comcast/NBC-U G-14 04C 3762 3798 G-18 19C 4062 4098 01-Feb-21 90 02-May-21 S, F Herring Networks G-13 18C 4042 4078 G-23 23C 4142 4178 01-Feb-21 90 02-May-21 S, F IKO Media Group G-23 24C 4162 4198 G-18 15C 4000 4018 01-Feb-21 90 02-May-21 C, S, F MLB G-13 01C 3702 3738 G-18 21C 4102 4138 HEVC 01-Feb-21 90 02-May-21 C, S, F MLB G-17 04C 3762 3798 G-18 21C 4102 4138 HEVC 01-Feb-21 90 02-May-21 S, P, F Trinity Broadcasting Network G-14 01C 3702 3738 G-18 17C 4022 4058 28-Feb-21 0 28-Feb-21 R GCI Restoration G-13 12C 3922 3958 G-13 07C 3822 3858

31 Phase I Lower Upper Phase 1 Lower Upper Phase I Duration Phase I Change Start Freq. Freq. End Freq. Freq. Technology Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Upgrade 01-Mar-21 90 30-May-21 S, P, F CenturyLink G-23 04C 3762 3798 G-13 12C 3922 3958 01-Mar-21 90 30-May-21 C, P, F Sinclair G-15 04C 3762 3798 G-15 21C 4102 4138 HEVC 01-Mar-21 90 30-May-21 C, F Sinclair G-15 20C 4082 4118 G-15 22C 4122 4158 HEVC 01-Mar-21 90 30-May-21 C Sinclair G-15 21C 4102 4138 G-15 21C 4102 4138 HEVC 01-Mar-21 90 30-May-21 C Sinclair G-15 22C 4122 4158 G-15 22C 4122 4158 HEVC 02-Mar-21 60 01-May-21 P, F ShopHQ G-14 03C 3742 3778 G-14 22C 4122 4140 04-Mar-21 0 04-Mar-21 R GCI Restoration G-13 20C 4082 4118 G-13 04C 3762 3798 01-Apr-21 30 01-May-21 P, F ATCi G-16 06C 3802 3838 G-16 15C 4000 4018 01-Apr-21 90 30-Jun-21 C, S, P, F Disney G-14 14C 3962 3998 G-18 24C 4162 4198 HEVC 02-Apr-21 90 01-Jul-21 S, P, F Overon G-23 22C 4122 4158 G-14 11C 3902 3938 02-Apr-21 90 01-Jul-21 S, P, F Overon G-23 24C 4162 4198 G-14 11C 3902 3938 01-May-21 30 31-May-21 F US Government G-13 17C 4022 4058 G-13 05C 3782 3818 01-May-21 122 31-Aug-21 C FoxCorp G-16 19C 4062 4098 G-16 19C 4062 4098 HEVC 01-May-21 122 31-Aug-21 C FoxCorp G-3C 18C 4042 4078 G-16 19C 4062 4098 HEVC 01-May-21 122 31-Aug-21 C FoxCorp G-3C 19C 4062 4098 G-16 19C 4062 4098 HEVC 01-Jun-21 90 30-Aug-21 C Sinclair G-17 08C 3842 3878 G-17 08C 3842 3878 HEVC 01-Jun-21 90 30-Aug-21 C, P, F Sinclair G-17 10C 3882 3918 G-17 23C 4142 4178 HEVC 01-Jun-21 90 30-Aug-21 C Sinclair G-17 15C 3982 4018 G-17 15C 3982 4018 HEVC 01-Jun-21 90 30-Aug-21 C Sinclair G-17 22C 4122 4158 G-17 22C 4122 4158 HEVC 01-Jun-21 90 30-Aug-21 C Sinclair G-17 23C 4142 4178 G-17 23C 4142 4178 HEVC 01-Jul-21 90 29-Sep-21 C, S, P, F Disney G-14 09C 3862 3898 G-17 20C 4082 4118 HEVC 01-Jul-21 90 29-Sep-21 C Disney G-18 22C 4122 4158 G-18 22C 4122 4158 HEVC 01-Oct-21 90 30-Dec-21 C, S, P, F Disney G-14 07C 3822 3858 G-17 20C 4082 4118 HEVC 05-Dec-19 548 05-Jun-21 C, F NPR G-16 01C 3702 3738 G-16 23C 4142 4178 Audio

6.1.2 Table 2 Phase II Grooming Plan Transition Activities (Chronological)

Phase II Lower Upper Phase II Lower Upper Phase II Duration Phase II Change Start Freq. Freq. End Freq. Freq. Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Technology 01-Jun-21 210 28-Dec-21 C, F Discovery G-13 22C 4122 4158 G-13 24C 4162 4198 AVC 06-Dec-21 30 05-Jan-22 F FoxCorp G-15 10C 3882 3918 G-15 24C 4162 4198 HEVC 06-Dec-21 30 05-Jan-22 F US Government G-16 10C 3882 3918 G-16 24C 4162 4198 06-Dec-21 30 05-Jan-22 F The SPACECONNECTION G-19 07C 3822 3858 G-19 17C 4022 4058 06-Dec-21 30 05-Jan-22 F Tri-State Christian TV G-17 14C 3962 3998 G-17 18C 4042 4078 06-Dec-21 60 04-Feb-22 P, F Globecast G-19 13C 3942 3978 G-19 18C 4042 4078

32 Phase II Lower Upper Phase II Lower Upper Phase II Duration Phase II Change Start Freq. Freq. End Freq. Freq. Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Technology 06-Dec-21 60 04-Feb-22 P, F Shepherd's Chapel G-16 16C 4002 4038 G-16 15C 4000 4018 06-Dec-21 60 04-Feb-22 P, F United Teleports Inc. G-19 10C 3882 3918 G-19 17C 4022 4058 06-Dec-21 90 06-Mar-22 S, F Comcast/NBC-U G-17 07C 3822 3858 G-18 20C 4082 4118 06-Dec-21 90 06-Mar-22 S, F LinkUp G-3C 08C 3842 3878 G-19 17C 4022 4058 06-Dec-21 90 06-Mar-22 S, F The SPACECONNECTION G-28 15C 3962 3998 G-19 17C 4022 4058 06-Dec-21 90 06-Mar-22 S, F Tribune G-14 13C 3942 3978 G-18 18C 4042 4078 06-Dec-21 90 06-Mar-22 S, P, F Sinclair G-17 15C 3982 4018 G-15 16C 4002 4038 HEVC 29-Dec-21 90 29-Mar-22 C Encompass G-13 23C 4142 4178 G-13 23C 4142 4178 AVC 04-Jan-22 90 04-Apr-22 C, P, F Encompass G-13 13C 3942 3978 G-13 22C 4122 4158 AVC 04-Jan-22 90 04-Apr-22 C, S, P, F Encompass G-14 10C 3882 3918 G-13 22C 4122 4158 AVC 05-Jan-22 30 04-Feb-22 F PROLASA G-19 15C 3982 4018 G-19 17C 4022 4058 01-Feb-22 30 03-Mar-22 F CenturyLink G-13 12C 3922 3958 G-13 18C 4042 4078 05-Feb-22 60 06-Apr-22 P, F Encompass G-19 12C 3922 3958 G-19 15C 4000 4018 05-Feb-22 90 06-May-22 S, F The SPACECONNECTION G-3C 10C 3882 3918 G-16 16C 4002 4038 05-Feb-22 90 06-May-22 S, F The SPACECONNECTION G-3C 14C 3962 3998 G-16 18C 4042 4078 01-Mar-22 90 30-May-22 C, F Starz G-13 09C 3862 3898 G-13 17C 4022 4058 HEVC 01-Mar-22 90 30-May-22 C, F Starz G-13 15C 3982 4018 G-13 17C 4022 4058 HEVC 01-Mar-22 90 30-May-22 C, F Starz G-15 08C 3842 3878 G-15 20C 4082 4118 HEVC 01-Mar-22 90 30-May-22 C, F Starz G-15 14C 3962 3998 G-15 20C 4082 4118 HEVC 04-Mar-22 0 04-Mar-22 R GCI Restoration G-13 18C 4042 4078 G-13 12C 3922 3958 07-Mar-22 90 05-Jun-22 C A&E G-14 23C 4142 4178 G-14 23C 4142 4178 AVC 07-Mar-22 90 05-Jun-22 C, F A&E G-14 21C 4102 4138 G-14 23C 4142 4178 AVC 31-May-22 90 29-Aug-22 C, F Encompass G-13 11C 3902 3938 G-13 15C 4000 4018 AVC 06-Jun-22 90 04-Sep-22 C WarnerMedia G-15 18C 4042 4078 G-15 18C 4042 4078 HEVC 06-Jun-22 90 04-Sep-22 C WarnerMedia G-15 19C 4062 4098 G-15 19C 4062 4098 HEVC 06-Jun-22 90 04-Sep-22 C, F WarnerMedia G-14 15C 3982 4018 G-14 21C 4102 4138 HEVC 06-Jun-22 90 04-Sep-22 C, F WarnerMedia G-14 16C 4002 4038 G-14 20C 4082 4118 HEVC 06-Jun-22 90 04-Sep-22 C, F WarnerMedia G-15 15C 3982 4018 G-15 19C 4062 4098 HEVC 06-Jun-22 90 04-Sep-22 C, F WarnerMedia G-15 16C 4002 4038 G-15 18C 4042 4078 HEVC 06-Jun-22 90 04-Sep-22 C, P, F WarnerMedia G-14 17C 4022 4058 G-14 20C 4082 4118 HEVC 05-Sep-22 30 05-Oct-22 F C-SPAN G-14 12C 3922 3958 G-14 16C 4002 4038 05-Sep-22 30 05-Oct-22 F INSP G-15 17C 4022 4058 G-15 15C 4000 4018 05-Sep-22 30 05-Oct-22 F Overon G-14 11C 3902 3938 G-14 17C 4022 4058 05-Sep-22 90 04-Dec-22 C, S Encompass G-23 15C 3982 4018 G-14 15C 4000 4018 HEVC 05-Sep-22 90 04-Dec-22 S, F Sinclair G-17 23C 4142 4178 G-15 17C 4022 4058 HEVC

33 Phase II Lower Upper Phase II Lower Upper Phase II Duration Phase II Change Start Freq. Freq. End Freq. Freq. Start Date (Days) End Date Type Customer Sat/Trx (MHz) (MHz) Sat/Trx (MHz) (MHz) Technology 01-Oct-22 90 30-Dec-22 S, F ViacomCBS G-28 09C 3842 3878 G-23 22C 4122 4158 01-Oct-22 90 30-Dec-22 S, F ViacomCBS G-28 10C 3862 3898 G-23 21C 4102 4138 01-Oct-22 90 30-Dec-22 S, F ViacomCBS G-28 15C 3962 3998 G-23 24C 4162 4198 01-Oct-22 90 30-Dec-22 S, F ViacomCBS G-28 16C 3982 4018 G-23 23C 4142 4178 06-Oct-22 90 04-Jan-23 S, F Sinclair G-17 22C 4122 4158 G-15 16C 4002 4038 HEVC 06-Oct-22 90 04-Jan-23 S, F Sinclair G-17 23C 4142 4178 G-15 17C 4022 4058 HEVC 06-Oct-22 90 04-Jan-23 S, P, F Sinclair G-17 08C 3842 3878 G-15 17C 4022 4058 HEVC 06-Oct-22 90 04-Jan-23 S, P, F Sinclair G-17 10C 3882 3918 G-15 17C 4022 4058 06-Oct-22 90 04-Jan-23 S, P, F Sinclair G-17 15C 3982 4018 G-15 16C 4002 4038 05-Jan-23 30 04-Feb-23 F Altitude Sports & Entertainment G-17 09C 3862 3898 G-17 23C 4142 4178 05-Jan-23 30 04-Feb-23 F AMC G-17 13C 3942 3978 G-17 15C 4000 4018 05-Jan-23 30 04-Feb-23 F BYU G-17 12C 3922 3958 G-17 22C 4122 4158 05-Jan-23 30 04-Feb-23 F The SPACECONNECTION G-17 12C 3922 3958 G-17 22C 4122 4158 01-Feb-23 90 02-May-23 S Sinclair G-23 17C 4022 4058 01-Feb-23 90 02-May-23 S Sinclair G-23 18C 4042 4078 01-Feb-23 90 02-May-23 S Sinclair G-23 19C 4062 4098 01-Feb-23 90 02-May-23 S Sinclair G-23 20C 4082 4118 01-Mar-23 30 31-Mar-23 F Dejero Labs G-19 14C 3962 3998 G-19 16C 4002 4038

6.2 Transition Plan (Customer-Centric)

The tables below illustrate the detailed transition activities planned by customer across Phase I and Phase II.

6.2.1 Table 3 Phase I Grooming Plan Transition Activities (Customer-Centric)

Phase I Lower Upper Phase I Lower Upper Start Freq. Freq. Change Phase I Duration Phase I End Freq. Freq. Customer Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date Sat/Trx (MHz) (MHz) Technology AT&T Sports G-17 20C 4082 4118 S, F 01-Feb-21 90 02-May-21 G-18 23C 4142 4178 ATCi G-13 18C 4042 4078 S, F 01-Feb-21 90 02-May-21 G-23 23C 4142 4178 ATCi G-16 06C 3802 3838 P, F 01-Apr-21 30 01-May-21 G-16 15C 4000 4018 BBC / Intelsat MCPC platform G-13 04C 3762 3798 F 01-Feb-21 30 03-Mar-21 G-13 20C 4082 4118 Caracol / Intelsat MCPC platform G-13 04C 3762 3798 F 01-Feb-21 30 03-Mar-21 G-13 20C 4082 4118 CenturyLink G-23 04C 3762 3798 S, P, F 01-Mar-21 90 30-May-21 G-13 12C 3922 3958 Comcast/NBC-U G-14 04C 3762 3798 S, F 01-Feb-21 90 02-May-21 G-18 19C 4062 4098

34 Phase I Lower Upper Phase I Lower Upper Start Freq. Freq. Change Phase I Duration Phase I End Freq. Freq. Customer Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date Sat/Trx (MHz) (MHz) Technology Discovery G-13 14C 3962 3998 F 01-Jul-20 180 28-Dec-20 G-13 24C 4162 4198 Disney G-14 07C 3822 3858 C, S, P, F 01-Oct-21 90 30-Dec-21 G-17 20C 4082 4118 HEVC Disney G-14 09C 3862 3898 C, S, P, F 01-Jul-21 90 29-Sep-21 G-17 20C 4082 4118 HEVC Disney G-14 11C 3902 3938 C, F 01-Jan-21 90 01-Apr-21 G-14 07C 3822 3858 HEVC Disney G-14 14C 3962 3998 C, S, P, F 01-Apr-21 90 30-Jun-21 G-18 24C 4162 4198 HEVC Disney G-15 02C 3722 3758 C, S, P, F 01-Jan-21 90 01-Apr-21 G-17 17C 4022 4058 HEVC Disney G-17 02C 3722 3758 C, P, F 01-Jan-21 90 01-Apr-21 G-17 17C 4022 4058 HEVC Disney G-18 22C 4122 4158 C 01-Jul-21 90 29-Sep-21 G-18 22C 4122 4158 HEVC Disney OU Pool G-16 08C 3842 3878 R 20-May-20 0 20-May-20 G-16 09C 3862 3898 Disney OU Pool G-16 17C 4022 4058 R 11-Jun-20 0 11-Jun-20 G-16 13C 3942 3978 Disney OU Pool G-16 22C 4122 4158 R 30-Jun-20 0 30-Jun-20 G-16 11C 3902 3938 Encompass G-13 06C 3802 3838 C, F 01-Oct-20 90 30-Dec-20 G-13 16C 4002 4038 AVC Encompass G-14 05C 3782 3818 C, S, F 01-Oct-20 90 30-Dec-20 G-13 16C 4002 4038 AVC Encompass G-17 21C 4102 4138 C, S, P, F 01-Oct-20 90 30-Dec-20 G-13 23C 4142 4178 AVC EWTN G-15 05C 3782 3818 F 01-Jul-20 30 31-Jul-20 G-15 23C 4142 4178 FoxCorp G-15 10C 3882 3918 C 01-Jan-21 90 01-Apr-21 G-15 10C 3882 3918 HEVC FoxCorp G-16 19C 4062 4098 C 01-May-21 122 31-Aug-21 G-16 19C 4062 4098 HEVC FoxCorp G-17 05C 3782 3818 C, F 31-Dec-20 90 31-Mar-21 G-17 21C 4102 4138 HEVC FoxCorp G-17 16C 4002 4038 C 01-Jan-21 90 01-Apr-21 G-17 16C 4002 4038 HEVC FoxCorp G-3C 18C 4042 4078 C 01-May-21 122 31-Aug-21 G-16 19C 4062 4098 HEVC FoxCorp G-3C 19C 4062 4098 C 01-May-21 122 31-Aug-21 G-16 19C 4062 4098 HEVC FoxCorp Restoration G-16 13C 3942 3978 R 10-Jun-20 0 10-Jun-20 G-16 20C 4082 4118 GCI G-18 11C 3902 3938 S, P, F 31-Mar-20 90 29-Jun-20 H-3e 0 0 GCI G-18 15C 3982 4018 S, P, F 03-Apr-20 90 02-Jul-20 H-3e 0 0 GCI G-18 17C 4022 4058 S, P, F 02-Apr-20 90 01-Jul-20 H-3e 0 0 GCI G-18 18C 4042 4078 S, P, F 28-Feb-20 90 28-May-20 H-3e 0 0 GCI G-18 19C 4062 4098 S, P, F 29-Feb-20 90 29-May-20 H-3e 0 0 GCI G-18 20C 4082 4118 S, P, F 27-Mar-20 90 25-Jun-20 H-3e 0 0 GCI G-18 21C 4102 4138 S, P, F 21-Mar-20 90 19-Jun-20 H-3e 0 0 GCI G-18 23C 4142 4178 S, P, F 03-Apr-20 90 02-Jul-20 H-3e 0 0 GCI Restoration G-13 12C 3922 3958 R 28-Feb-21 0 28-Feb-21 G-13 07C 3822 3858 GCI Restoration G-13 16C 4002 4038 R 31-Dec-20 0 31-Dec-20 G-13 06C 3802 3838 GCI Restoration G-13 20C 4082 4118 R 04-Mar-21 0 04-Mar-21 G-13 04C 3762 3798 GCI Restoration G-13 24C 4162 4198 R 29-Dec-20 0 29-Dec-20 G-13 14C 3962 3998

35 Phase I Lower Upper Phase I Lower Upper Start Freq. Freq. Change Phase I Duration Phase I End Freq. Freq. Customer Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date Sat/Trx (MHz) (MHz) Technology Herring Networks G-13 18C 4042 4078 S, F 01-Feb-21 90 02-May-21 G-23 23C 4142 4178 IKO Media Group G-23 24C 4162 4198 S, F 01-Feb-21 90 02-May-21 G-18 15C 4000 4018 LeSea Broadcasting G-16 15C 3982 4018 F 01-Oct-20 30 31-Oct-20 G-16 17C 4022 4058 Mega Media / Intelsat MCPC platform G-13 04C 3762 3798 F 01-Feb-21 30 03-Mar-21 G-13 20C 4082 4118 MLB G-13 01C 3702 3738 C, S, F 01-Feb-21 90 02-May-21 G-18 21C 4102 4138 HEVC MLB G-17 04C 3762 3798 C, S, F 01-Feb-21 90 02-May-21 G-18 21C 4102 4138 HEVC Music Choice G-14 22C 4122 4158 F 31-Jan-21 30 02-Mar-21 G-14 22C 4122 4158 NHK / Intelsat MCPC platform G-13 04C 3762 3798 F 01-Feb-21 30 03-Mar-21 G-13 20C 4082 4118 NPR G-16 01C 3702 3738 C, F 05-Dec-19 548 05-Jun-21 G-16 23C 4142 4178 Audio NPR G-16 07C 3822 3858 C, F 05-Dec-19 239 31-Jul-20 G-16 23C 4142 4178 Audio NPR G-16 23C 4142 4178 C 05-Dec-19 548 05-Jun-21 G-16 23C 4142 4178 Audio Overon G-23 22C 4122 4158 S, P, F 02-Apr-21 90 01-Jul-21 G-14 11C 3902 3938 Overon G-23 24C 4162 4198 S, P, F 02-Apr-21 90 01-Jul-21 G-14 11C 3902 3938 Rignet G-19 17C 4022 4058 F 01-Jan-21 30 31-Jan-21 G-19 09C 3862 3898 ShopHQ G-14 03C 3742 3778 P, F 02-Mar-21 60 01-May-21 G-14 22C 4122 4158 Sinclair G-15 04C 3762 3798 C, P, F 01-Mar-21 90 30-May-21 G-15 21C 4102 4138 HEVC Sinclair G-15 20C 4082 4118 C, F 01-Mar-21 90 30-May-21 G-15 22C 4122 4158 HEVC Sinclair G-15 21C 4102 4138 C 01-Mar-21 90 30-May-21 G-15 21C 4102 4138 HEVC Sinclair G-15 22C 4122 4158 C 01-Mar-21 90 30-May-21 G-15 22C 4122 4158 HEVC Sinclair G-17 06C 3802 3838 F 01-Jul-20 30 31-Jul-20 G-17 10C 3882 3918 Sinclair G-17 08C 3842 3878 C 01-Jun-21 90 30-Aug-21 G-17 08C 3842 3878 HEVC Sinclair G-17 10C 3882 3918 C, P, F 01-Jun-21 90 30-Aug-21 G-17 23C 4142 4178 HEVC Sinclair G-17 15C 3982 4018 C 01-Jun-21 90 30-Aug-21 G-17 15C 3982 4018 HEVC Sinclair G-17 17C 4022 4058 F 01-Jul-20 30 31-Jul-20 G-17 15C 3982 4018 Sinclair G-17 22C 4122 4158 C 01-Jun-21 90 30-Aug-21 G-17 22C 4122 4158 HEVC Sinclair G-17 23C 4142 4178 C 01-Jun-21 90 30-Aug-21 G-17 23C 4142 4178 HEVC Televisa G-16 20C 4082 4118 F 04-Jun-20 5 09-Jun-20 G-16 08C 3842 3878 Televisa G-16 24C 4162 4198 F 01-Jul-20 9 10-Jul-20 G-16 12C 3922 3958 Televisa G-19 16C 4002 4038 F 10-Jun-20 20 30-Jun-20 G-19 08C 3842 3878 The Church of Jesus Christ of Latter-Day Saints G-19 11C 3902 3938 F 04-Jan-21 30 03-Feb-21 G-19 17C 4022 4058 The CW G-17 01C 3702 3738 F 01-Jul-20 30 31-Jul-20 G-17 19C 4062 4098 Trinity Broadcasting Network G-14 01C 3702 3738 S, P, F 01-Feb-21 90 02-May-21 G-18 17C 4022 4058 TV Azteca G-19 03C 3742 3778 S, F 01-Jul-20 90 29-Sep-20 G-16 22C 4122 4158 US Government G-13 17C 4022 4058 F 01-May-21 30 31-May-21 G-13 05C 3782 3818 US Government G-3C 24C 4162 4198 F 01-Jul-20 30 31-Jul-20 G-3C 08C 3842 3878 ViacomCBS G-3C 12C 3922 3958 R 01-Aug-20 0 01-Aug-20 G-3C 24C 4162 4198

36 Phase I Lower Upper Phase I Lower Upper Start Freq. Freq. Change Phase I Duration Phase I End Freq. Freq. Customer Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date Sat/Trx (MHz) (MHz) Technology Word Network G-17 03C 3742 3778 F 01-Aug-20 30 31-Aug-20 G-17 19C 4062 4098

6.2.2 Table 4 Phase II Grooming Plan Transition Activities (Customer-Centric)

Lower Upper Lower Upper Phase II Freq. Freq. Change Phase II Duration Phase II Phase II Freq. Freq. Customer Start Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date End Sat/Trx (MHz) (MHz) Technology A&E G-14 21C 4102 4138 C, F 07-Mar-22 90 05-Jun-22 G-14 23C 4142 4178 AVC A&E G-14 23C 4142 4178 C 07-Mar-22 90 05-Jun-22 G-14 23C 4142 4178 AVC Altitude Sports & Entertainment G-17 09C 3862 3898 F 05-Jan-23 30 04-Feb-23 G-17 23C 4142 4178 AMC G-17 13C 3942 3978 F 05-Jan-23 30 04-Feb-23 G-17 15C 4000 4018 BYU G-17 12C 3922 3958 F 05-Jan-23 30 04-Feb-23 G-17 22C 4122 4158 CenturyLink G-13 12C 3922 3958 F 01-Feb-22 30 03-Mar-22 G-13 18C 4042 4078 Comcast/NBC-U G-17 07C 3822 3858 S, F 06-Dec-21 90 06-Mar-22 G-18 20C 4082 4118 C-SPAN G-14 12C 3922 3958 F 05-Sep-22 30 05-Oct-22 G-14 16C 4002 4038 Dejero Labs G-19 14C 3962 3998 F 01-Mar-23 30 31-Mar-23 G-19 16C 4002 4038 Discovery G-13 22C 4122 4158 C, F 01-Jun-21 210 28-Dec-21 G-13 24C 4162 4198 AVC Encompass G-13 11C 3902 3938 C, F 31-May-22 90 29-Aug-22 G-13 15C 4000 4018 AVC Encompass G-13 13C 3942 3978 C, P, F 04-Jan-22 90 04-Apr-22 G-13 22C 4122 4158 AVC Encompass G-13 23C 4142 4178 C 29-Dec-21 90 29-Mar-22 G-13 23C 4142 4178 AVC Encompass G-14 10C 3882 3918 C, S, P, F 04-Jan-22 90 04-Apr-22 G-13 22C 4122 4158 AVC Encompass G-19 12C 3922 3958 P, F 05-Feb-22 60 06-Apr-22 G-19 15C 4000 4018 Encompass G-23 15C 3982 4018 C, S 05-Sep-22 90 04-Dec-22 G-14 15C 4000 4018 HEVC FoxCorp G-15 10C 3882 3918 F 06-Dec-21 30 05-Jan-22 G-15 24C 4162 4198 HEVC GCI Restoration G-13 18C 4042 4078 R 04-Mar-22 0 04-Mar-22 G-13 12C 3922 3958 Globecast G-19 13C 3942 3978 P, F 06-Dec-21 60 04-Feb-22 G-19 18C 4042 4078 INSP G-15 17C 4022 4058 F 05-Sep-22 30 05-Oct-22 G-15 15C 4000 4018 LinkUp G-3C 08C 3842 3878 S, F 06-Dec-21 90 06-Mar-22 G-19 17C 4022 4058 Overon G-14 11C 3902 3938 F 05-Sep-22 30 05-Oct-22 G-14 17C 4022 4058 PROLASA G-19 15C 3982 4018 F 05-Jan-22 30 04-Feb-22 G-19 17C 4022 4058 Shepherd's Chapel G-16 16C 4002 4038 P, F 06-Dec-21 60 04-Feb-22 G-16 15C 4000 4018 Sinclair S 01-Feb-23 90 02-May-23 G-23 17C 4022 4058 Sinclair S 01-Feb-23 90 02-May-23 G-23 18C 4042 4078

37 Lower Upper Lower Upper Phase II Freq. Freq. Change Phase II Duration Phase II Phase II Freq. Freq. Customer Start Sat/Trx (MHz) (MHz) Type Start Date (Days) End Date End Sat/Trx (MHz) (MHz) Technology Sinclair S 01-Feb-23 90 02-May-23 G-23 19C 4062 4098 Sinclair S 01-Feb-23 90 02-May-23 G-23 20C 4082 4118 Sinclair G-17 08C 3842 3878 S, P, F 06-Oct-22 90 04-Jan-23 G-15 17C 4022 4058 HEVC Sinclair G-17 10C 3882 3918 S, P, F 06-Oct-22 90 04-Jan-23 G-15 17C 4022 4058 Sinclair G-17 15C 3982 4018 S, P, F 06-Dec-21 90 06-Mar-22 G-15 16C 4002 4038 HEVC Sinclair G-17 15C 3982 4018 S, P, F 06-Oct-22 90 04-Jan-23 G-15 16C 4002 4038 Sinclair G-17 22C 4122 4158 S, F 06-Oct-22 90 04-Jan-23 G-15 16C 4002 4038 HEVC Sinclair G-17 23C 4142 4178 S, F 05-Sep-22 90 04-Dec-22 G-15 17C 4022 4058 HEVC Sinclair G-17 23C 4142 4178 S, F 06-Oct-22 90 04-Jan-23 G-15 17C 4022 4058 HEVC Starz G-13 09C 3862 3898 C, F 01-Mar-22 90 30-May-22 G-13 17C 4022 4058 HEVC Starz G-13 15C 3982 4018 C, F 01-Mar-22 90 30-May-22 G-13 17C 4022 4058 HEVC Starz G-15 08C 3842 3878 C, F 01-Mar-22 90 30-May-22 G-15 20C 4082 4118 HEVC Starz G-15 14C 3962 3998 C, F 01-Mar-22 90 30-May-22 G-15 20C 4082 4118 HEVC The SPACECONNECTION G-17 12C 3922 3958 F 05-Jan-23 30 04-Feb-23 G-17 22C 4122 4158 The SPACECONNECTION G-19 07C 3822 3858 F 06-Dec-21 30 05-Jan-22 G-19 17C 4022 4058 The SPACECONNECTION G-28 15C 3962 3998 S, F 06-Dec-21 90 06-Mar-22 G-19 17C 4022 4058 The SPACECONNECTION G-3C 10C 3882 3918 S, F 05-Feb-22 90 06-May-22 G-16 16C 4002 4038 The SPACECONNECTION G-3C 14C 3962 3998 S, F 05-Feb-22 90 06-May-22 G-16 18C 4042 4078 Tribune G-14 13C 3942 3978 S, F 06-Dec-21 90 06-Mar-22 G-18 18C 4042 4078 Tri-State Christian TV G-17 14C 3962 3998 F 06-Dec-21 30 05-Jan-22 G-17 18C 4042 4078 United Teleports Inc. G-19 10C 3882 3918 P, F 06-Dec-21 60 04-Feb-22 G-19 17C 4022 4058 US Government G-16 10C 3882 3918 F 06-Dec-21 30 05-Jan-22 G-16 24C 4162 4198 ViacomCBS G-28 09C 3842 3878 S, F 01-Oct-22 90 30-Dec-22 G-23 22C 4122 4158 ViacomCBS G-28 10C 3862 3898 S, F 01-Oct-22 90 30-Dec-22 G-23 21C 4102 4138 ViacomCBS G-28 15C 3962 3998 S, F 01-Oct-22 90 30-Dec-22 G-23 24C 4162 4198 ViacomCBS G-28 16C 3982 4018 S, F 01-Oct-22 90 30-Dec-22 G-23 23C 4142 4178 WarnerMedia G-14 15C 3982 4018 C, F 06-Jun-22 90 04-Sep-22 G-14 21C 4102 4138 HEVC WarnerMedia G-14 16C 4002 4038 C, F 06-Jun-22 90 04-Sep-22 G-14 20C 4082 4118 HEVC WarnerMedia G-14 17C 4022 4058 C, P, F 06-Jun-22 90 04-Sep-22 G-14 20C 4082 4118 HEVC WarnerMedia G-15 15C 3982 4018 C, F 06-Jun-22 90 04-Sep-22 G-15 19C 4062 4098 HEVC WarnerMedia G-15 16C 4002 4038 C, F 06-Jun-22 90 04-Sep-22 G-15 18C 4042 4078 HEVC WarnerMedia G-15 18C 4042 4078 C 06-Jun-22 90 04-Sep-22 G-15 18C 4042 4078 HEVC WarnerMedia G-15 19C 4062 4098 C 06-Jun-22 90 04-Sep-22 G-15 19C 4062 4098 HEVC

38 6.3 Satellite Transponder Loading View

The figures below illustrate the progressive clearing of the lower 300 MHz across Intelsat’s impacted satellites during the two phases of the migration.31 The first three diagrams show the current loading, loading at the end of Phase I, and loading at the end of Phase II for the cable satellites. The next three diagrams show the same data for the broadcast satellite fleet.

31 The loading charts below have been revised and are different from those previously proposed by Intelsat as a former member of the C- Band Alliance because the previous proposal assumed that only 200 MHz of the C-band spectrum would be cleared for future overlay licensee use. See C-Band Alliance Notice of Ex Parte Meeting, 6-8 (Feb. 7, 2019), https://ecfsapi.fcc.gov/file/102072699030257/CBA%20- %20Ex%20Parte%20re%20Grooming%20Plans.pdf.

39 6.3.1 Figure 1 Cable Neighborhoods C-Band Loading – Current

40 6.3.2 Figure 2 Cable Neighborhoods C-Band Loading – End of Phase I

41 6.3.3 Figure 3 Cable Neighborhoods C-Band Loading – End of Phase II

42 6.3.4 Figure 4 Broadcast, Radio and Data C-Band Loading - Current

43 6.3.5 Figure 5 Broadcast, Radio and Data C-Band Loading – End of Phase I

44 6.3.6 Figure 6 Broadcast, Radio and Data C-Band Loading – End of Phase II

45 6.4 Customer Services Not Requiring a Move

The following customer services are already located in the upper 200 MHz of the band and will require no migration activities. The associated antennas at these customers’ affiliated earth stations will only require the installation of passband filters at the appropriate time to mitigate against future interference from flexible use operations.

Customer Sat/Trx Actualidad Media Group G-19 17C AMC G-14 18C Comcast/NBC-U G-14 19C G-17 24C Disney G-16 21C HDNet G-13 19C NFL Network G-13 21C PAC-12 G-18 16C Univision G-19 22C US Government G-19 17C ViacomCBS G-14 24C G-19 19C G-19 20C G-19 21C G-19 23C G-19 24C

6.5 Non-CONUS Services in the Lower 300 MHz

While most CONUS-based services are being migrated into the upper 200 MHz, Intelsat has stated on the record that certain limited services that do not downlink in CONUS will remain in the lower 300 MHz.32 These critical services are focused on Alaska, the Gulf of Mexico, the Caribbean, Mexico and Central America. Intelsat will transition all such non-CONUS services to the lower 300 MHz of spectrum and consolidate these services on fewer satellites.

Successful completion of the migrations outlined above will clear the lower 300 MHz of all of the CONUS services on Intelsat’s North American arc C-band fleet, leaving only non-CONUS services in the lower 300 MHz on those satellites.

32 See supra note 8.

46 7 Intelsat’s Earth Station Migration Plan 7.1 Interim Earth Station and Antenna Data Set Explained

The Report and Order directs space station operators to submit transition plans that include “(5) the number and location of earth stations antennas currently receiving the space station operator’s transmissions that will need to be transitioned to the upper 200 megahertz; (6) an estimate of the number and location of earth station antennas that will require retuning and/or repointing in order to receive content on new transponder frequencies post-transition.”33

Intelsat is unable at this time to provide this complete data set for the following reasons:

1. The International Bureau has yet to provide a complete list of eligible earth stations.

2. Intelsat is in the process of contacting earth station operators, as described in Section 5.1. Until that activity is completed, we cannot confirm the current operating environment of each earth station (e.g., the current list of antennas operating at each earth station).

3. Intelsat is validating customer affiliate lists, as described in Section 5.1. Until this activity is completed, certain aspects of the earth station migration plan, such antenna seeding plans cannot be finalized.

In the following sections, Intelsat provides its current list of earth stations that receive programming from the Galaxy fleet. In many cases, Intelsat was able to provide the earth station name and the associated IBFS fields as the Report and Order contemplates. Where Intelsat could not provide the requested information, the name of the customers whose affiliates Intelsat will accept responsibility for transitioning services to the upper 200 MHz is provided.

7.2 Cable Headends

Given Intelsat’s market share of CONUS cable Distribution services, Intelsat is assuming that one or more of Intelsat’s satellites are downlinked at every cable headend. Intelsat estimates that there are approximately 2,500 total cable headends and that approximately 10,000 antennas are currently receiving Intelsat’s customer’s transmissions, all of which require some degree of retuning and/or repointing to support Intelsat’s migration plan.

Based on Intelsat’s analysis of preliminary IBFS data, it estimates that there are approximately 2,000 cable headend sites registered. This preliminary list of cable headends is included in Appendix 1.

7.3 Galaxy 18 and Galaxy 23 Antenna Seeding

As mentioned in Section 5.2.4, Intelsat will launch a supplemental antenna program for Galaxy 18 and Galaxy 23. The antenna program will ensure that all satellites in the cable arc are 100%

33 Report and Order, para. 303.

47 penetrated and will provide customers with service continuity throughout the clearing process. While the list of earth stations associated with these customers is not yet complete, Intelsat will provide antennas where they do not already exist for the following customers’ affiliates:

1. AT&T Sports 2. ATCi 3. Comcast/NBC-U 4. Disney 5. Herring Networks 6. IKO Media Group 7. MLB 8. Tribune 9. Trinity Broadcasting Network 10. Sinclair

7.4 Compression

Intelsat must implement compression and technology upgrades for select customers as part of its Transition Plan in order to free sufficient spectrum to meet the Commission’s objectives. In the table below, Intelsat identifies the specific technology chosen by each content provider that will be compressed and the associated earth station impact.

Customer Technology Work Required A&E AVC No IRDs required Discovery AVC IRD replacements at head ends Disney HEVC IRD replacements at head ends Encompass AVC IRD replacements at head ends FoxCorp HEVC IRD replacements at head ends MLB HEVC IRD replacements at head ends NPR Audio Upgraded modems/terminals at affiliates Sinclair HEVC IRD replacements at head ends Starz AVC IRD replacements at head ends WarnerMedia HEVC IRD replacements at head ends

Based on customer affiliate data provided to date for customers that will be implementing compression technology upgrades, Intelsat has included the preliminary list of sites expected to require IRD upgrades/replacements in Appendix 3. Where possible, these affiliates have been correlated to existing earth stations contained in the IBFS database. Intelsat’s analysis, in collaboration with Intelsat’s customers, will continue until all impacted affiliate earth stations are conclusively identified.

7.5 The Church of Jesus Christ of Latter-Day Saints

The Church of Jesus Christ of Latter-Day Saints is exclusively Intelsat’s customer and has an extensive network of approximately 3,450 earth stations, the majority of which have a single antenna

48 that will require retuning to support the planned frequency change outlined in Section 5.2.1. The preliminary list of The Church of Jesus Christ Latter-Day Saints affiliates is included in Appendix 1.

7.6 Broadcast, Religious, Radio and Data Customers’ Affiliate Earth Station Scoping

Detailed identification of Intelsat’s broadcast, religious, radio, and data customers’ affiliate CONUS earth stations and their associated antenna impacts is underway and dependent on Intelsat’s affiliate matching and earth station outreach activities outlined in Section 5.1. In lieu of a comprehensive list of earth stations pending the completion of these activities, the following section enumerates the customers for whom Intelsat claims responsibility for transitioning all applicable receive antennas at their incumbent, affiliate earth stations, and a preliminary list of identified earth stations is included in Appendix 1. Intelsat’s analysis, in collaboration with its customers, will continue until all impacted affiliate earth stations are conclusively identified.

1. Actualidad Media Group 2. ATCi 3. CenturyLink 4. Dejero 5. Disney 6. EMC 7. Encompass 8. FoxCorp 9. GlobeCast 10. Grupo Imagen 11. Higher Ground 12. LeSea Broadcasting 13. LinkUp 14. NPR 15. Panasonic 16. PROLASA 17. Radio Centro 18. RigNet 19. Shepherd’s Chapel 20. Speedcast 21. The CW 22. The SPACECONNECTION 23. Televisa 24. TV Azteca 25. United Teleports 26. Univision 27. US Government 28. ViacomCBS 29. Vubiquity

49 Intelsat expects to provide additional updates to the list of earth stations in its final Transition Plan due by August 14, 2020. 8 Transition Plan Summary

Intelsat’s Transition Plan is the result of more than two years of planning and engineering undertaken in conjunction with Intelsat’s customers, industry stakeholders, vendors, and other space station operators in order for 300 MHz of spectrum – inclusive of a 20 MHz guard band -- to be cleared for use by new terrestrial flexible use licensees. For the transition to be successful, all the various work streams within each of these main project elements will need to occur in a tightly scheduled, highly coordinated fashion. The plan will rely on the participation and active cooperation of all major stakeholders. The section below summarizes the program deliverables, the aggregate costs and the overall clearing timeline.

8.1 Program Management

Intelsat has been preparing for the implementation of C-band spectrum clearing for over two years and is well positioned to take the actions necessary clear in the designated FCC timeframes. Intelsat’s assembled internal team consists of over 50 full-time employees focused on the clearing initiative. The team is comprised of strong, senior leaders dedicated to the program, complemented by world-class partners from across the industry.

Effective program management is vital to the success of the C-band clearing. Intelsat has contracted with a third party to develop a program management function that will support the leaders of each of the work streams identified in this Transition Plan. The program management office will have the following responsibilities:

• Development of the Transition Plan program milestones • Project tracking and reporting • Financial analysis and reporting • Interface to the Clearinghouse Coordinator • Interface to the Relocation Coordinator

Intelsat expects that the program office will remain in place through the end of the Transition Plan milestones identified in this section. The office’s functions will include certifying to the Relocation Coordinator that the spectrum milestones have been met and closing out any cost reimbursements with the Clearinghouse Coordinator. The estimated cost for management of the program is estimated to be $15 million over the Transition Plan period.

50 8.2 High Level Costs

The following is the aggregate view of the estimated reimbursable costs by category for the overall Intelsat Transition Plan.34 The estimates are based on the assumptions articulated above and will be revised as the program plan progresses into its implementation phase.

Document Total Category Section Cost Description Satellite Costs $ 790 7 Satellites Launch Vehicle & Insurance Costs $ 390 4 Launches Subtotal Satellite & Launch Costs 3 $ 1,180

Customer Migration, Compression and Repacking Costs 5 $ 400 10 Customers, 13,500 Affiliates Teleport Migration Costs 4 $ 95 2 Teleports, 18 Antennas Intelsat Program Management 8 $ 15 Program Management Subtotal Ground Infrastructure $ 510

Total $ 1,690

34 The numbers presented in the table are in millions.

51 8.3 High Level Timeline

Finally, a high-level view of the aggregated timeline for the various workstreams is provided below:

2020 2021 2022 2023 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

FCC Auction

Clearinghouse Relocation Clearinghouse Certificate of Comments on Certificate of Coordinator Coordinator Funded by Completion due Certificates Completion due Selected Selected Overlay for Phase 1 close for Phase 2 Licensees E/S Opt Outs List Published Eligible Regluatory Milestones Regluatory ES list Published

G-23R and G-17R Constructed Launch and Orbit Raising

G-15R and G-12R Constructed Launch and Orbit Raising

G-3CR and G-28R Constructed Launch and Orbit Raising and Launch

G-13R Constructed Launch and SatelliteProcurement Orbit Raising

Hawaii Antenna Construction Int & Test Service

Brewster, WA Site Upgrades and Antennas Contracting Construction Int & Test Service transition CONUS East - Site Upgrades & Antennas Contracting Construction Integration & Testing Service Transition S. America Antenna Contracting Construction Int & Test Service Transition S. Africa Antenna Contracting Construction Int & Test Service Transition

Teleport Consolidations Teleport Antenna for New Satellites G-23R (New antenna - Napa) G-17R (Antenna Upgrades Riverside, CA) G-15R (Antenna Upgrades - Atlanta, GA) G-12R (Antenna Upgrades - Riverside, CA) G-3CR (New Antenna - Riverside, CA or Napa, CA) G-28R (New Antenna - Riverside, CA or Napa, CA) G-13R (Antenna Upgrades - Atlanta, GA, Hagerstown, MD, or Napa, CA)

Antenna Seeding - Galaxy 18

Comcast/NBC-U, MLB, Disney Comcast/NBC-U, AT&T Sports, IKO Media Tribune Group, Trinity Broadcasting Network Antenna Seeding - Galaxy 23

Antenna Seeding Herring Networks, Sinclair ATCi

Compression Design, Procurement, Installation

Encompass FoxCorp Starz A&E WarnerMedia MLB

Sinclair Disney Encompass Compression

Cable Phase I Customer Migrations Cable Filtering (Red) Cable Phase II Customer Migrations Filter Filter Cable Cable Filtering (Blue) Installation - - Installation

Non-Cable Early Filtering (Red & Blue) Non-Cable Phase I Customer Migrations & Filtering Filter Non-Cable Phase II Customer Migrations & Filtering Non-Cable Installation - - Installation

Phase I Accelerated Phase II Accelerated Relocation Deadline Relocation Deadline

52

9 Conclusion

Intelsat is dedicated to successfully completing this transition process in conformance with the accelerated deadlines in the Report and Order. This Transition Plan is designed to minimize customer and earth station impact to the greatest extent possible and will allow Intelsat to provide similar or better service levels post the clearing process. Intelsat looks forward to working with all stakeholders to move forward and to complete this program.

53