Microgrid Design Considerations
Dr. Arindam Maitra, EPRI September 8, 2016
Part 3 of 3 © 2015 Electric Power Research Institute, Inc. All rights reserved. Outline – Microgrid Design and Analysis Tutorial Part II
Time Topics 14:30-15:00 Design analysis • Needs and Key Interconnection Issues (Arindam Maitra) 15:30-17:30 Design analysis (cont.) • Methods and Tools • Case Studies #1: Renewable Rich Microgrids - Protection Case Studies (Mohamed El Khatib) #2: Rural radial #3: Secondary n/w 17:00-17:30 Q&A 17:30 Adjourn
2 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrids
.Optimization of microgrid design is challenging and inherently contains many unknowns…
Regulatory Issues Value of Resiliency
System Design Challenges Engineering Studies Costs
3 © 2015 Electric Power Research Institute, Inc. All rights reserved. Integrating Customer DER with Utility Assets
Customer Utility Assets Assets
Micro Grid Controller SCADA/DMS/ / DERMS* Enterprise Integrate d Grid Energy Storage*
Isolating Device*
Distribution Transformer *New assets
4 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Types
.Commercial/Industrial Microgrids: Built with the goal of reducing demand and costs during normal operation, although the operation of critical functions during outages is also important, especially for data centers.
.Community/City/Utility and Network Microgrids: Improve reliability of critical infrastructure, deferred asset investment, emission and energy policy targets and also promote community participation.
.University Campus Microgrids: Meet the high reliability needs for research labs, campus housing, large heating and cooling demands at large cost reduction opportunities, and lower emission targets. Most campuses already have DG resources, with microgrid technology linking them together. They are usually large and may be involved with selling excess power to the grid. Some of these facilities typically serve as emergency shelters for surrounding communities during extreme events
.Public Institutional Microgrids: Improve reliability and lower energy consumptions at facilities impacting public health and safety, including hospitals, police and fire stations, sewage treatment plants, schools, public transport systems, and correctional facilities. Additional requirement of uninterrupted electrical and thermal service increases attractiveness of CHP-based district energy solutions
5 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Types
.Military Microgrids: Military microgrids focus on high reliability for mission-critical loads, strong needs for cyber and physical security, DoD energy cost reduction, and greenhouse gas emission reduction goals at the operating bases.
.Rural Microgrid Communities: Remote microgrid communities are typically connected to rural distribution system where it is prohibitive due to the distance or a physical barrier to bring in new transmission service for backup. Many already use diesel generation. They microgrids offer best candidate to incorporate renewable energy, improve system reliability targets, and defer investment and reduce supply chain risk.
6 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Configurations Depending on Location and Purpose
7 © 2015 Electric Power Research Institute, Inc. All rights reserved. Micro-grid: Operating as an “Island” Isolated from the Bulk Supply
Circuit Breaker Isolating Device – when open the system operates as micro-grid “Islanded” Facility Utility Source Trip Signal
Islanding Control (opens/closes breaker as needed to facilitate independent operation – must provide synchronization)
Electrical Island DG DG Able to Carry Load on Island and Provide Proper Voltage and Frequency
8 © 2015 Electric Power Research Institute, Inc. All rights reserved. “Islanding” for Reliability Enhancement
“Islanded” campus area during utility system outages
Building Load
13.2 kV Feeder Building Load Utility Substation
Building Load Utility System Interface Breaker
D D Building Building G G Load Load
DG trip settings for DG coordinated to allow utility system interface breaker to trip during utility faults so that stable transition to islanded state is achieved for the campus without interruption of DG service
9 © 2015 Electric Power Research Institute, Inc. All rights reserved. A Six Home Microgrid
House 1 House 2 House 3 Distribution Transformer Isolating Power System Device Secondary Utility System (120/240 V) Primary (13.2 kV)
Utility System 50 KVA House 4 House 5 House 6 Interface & Inverter Controller (Synchronization, fault protection, islanding DC Bus detection, etc.) Fuel Cell Charge Regulator
Thermal Energy Storage Storage Heat Distribution
10 © 2015 Electric Power Research Institute, Inc. All rights reserved. A Single Building Multiple Sources, Storage, and Heat Recovery
Serves as Isolation Point Utility System Interface AC Bus & Protection Control for Micro-grid mode of operation Utility Building Source Electrical Circuit Loads Breaker Circuit 20 kW Status/control Breaker signals paths to/from Wind electrical loads Energy Master Source System INVERTER Controller Status/control signal Rectification paths to/from thermal and Filtering DC Bus loads
Charge/Discharge Regulator Building 200 kW Heat Energy Recovery Thermal Storage Fuel Cell Loads
11 © 2015 Electric Power Research Institute, Inc. All rights reserved. A Campus Microgrid System
Dormitory A Dormitory B Administrative Isolating Device (opens during micro-grid mode) Building Campus Owned 500 kVA 500 kVA 300 kVA Distribution (13.2 kV) Utility System Primary Connection (13.2 kV)
Voltage Utility System To Other 75 kVA Interface Control Regulator Generator Campus (Synchronization, fault protection, islanding detection, Step Up Loads Academic etc.) Transformer Student Heat Distribution Union Building B Paralleling Bus (4.8 kV) Communication & Control Signal Path Generator 1.75 Academic Building A Protection 1.75 1.75 300 and Control MVA MVA MVA 800 kVA kVA Gen Gen Gen Load control
Heat Recovered Heat Distribution from ICE Units
12 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Design Parameters
Urban Rural Non-Utility Remote / Utility Utility Microgrids Island . Number of customers served Microgrids Microgrids Microgrids
Commercial / Remote . Physical length of circuits and types Industrial Clusters Planned Communities
of loads to be served Downtown Islanding and Loads Application University Campus Areas
Load Support Geographical Residential . Voltage levels to be used Islands Development
. Feeder configuration (looped, Reliability and Improved Reliability; Power Quality Electrification of Main Drivers Outage Management; networked, radial) Enhancement; Remote Areas Renewable and CHP Integration Energy Efficiency; . Types of distributed energy Improved Reliability; Premium Power Supply resources utilized Fuel Diversity; Quality; Availability Congestion Management; Benefits CHP Integration; Greenhouse Gas Reduction; Demand Response Integration of . AC or DC microgrid Upgrade Deferral; Management Renewables Ancillary Services . Heat-recovery options Grid- Primary Mode of Primary Mode of Operation Never Connected Operation . Desired power quality and reliability Nearby faults or levels System Disturbances Nearby faults or System
Intentional Disturbances Times of Peak Always Islanded Islanding . Methods of control and protection Energy Prices Approaching Storms . Controllers Approaching Storms Source: Johan Driesen and Farid Katiraei, “Design for Distributed Energy Resources,” IEEE Power & Energy Magazine, May/June 2008
13 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Design Elements
• Are the fault contributions from • Are DERs able to regulate the voltage and DERs sufficient to allow frequency within the island? satisfactory operation of • Any issues with parallel grid operation? protection systems? • How is re-synchronization checked • Are existing protection schemes against criteria such as out-of-phase, large adequate? change in voltage?
Microgrids
Need a microgrid controller
Plan, design, operate, control, monitor and optimize seamlessly
14 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Detailed Technical Design
Site Descriptions
Microgrid Project Objectives
Design Basis and Rationale
Performance Criteria • Electrical & Thermal Needs • Generation Assets • Critical Load Needs • Power Distribution Equip.
DER & Microgrid Controller Control Needs Communication Needs Codes & Standards
15 © 2015 Electric Power Research Institute, Inc. All rights reserved. DER Characterization
Renewables Fossil Fuels Tech ▪ Solar Photovoltaics ▪ Boiler Electric Storage ▪ Solar Thermal ▪ Fuel Cell Microturbine • AggregateSolar capacity Photovoltaics of all units (kwh) ▪ Wind ▪ Microturbine• Maximum charge rate • Max Power (kW) NG• # Genset of modules ▪ (fraction of total capacity charge in one hour) • Sprint capacity (% of power) ▪ Diesel• Module (backup) rating (kW DC)Electric Vehicles • Maximum discharge rate • # of sprint hours (hours) • Module •SizeMultiple (m2) locations (fraction of total capacity discharge per hour) • Fuel type • Efficiency• (%)Min connect/disconnect SOC Energy Storage • MinimumThermal state Tech of charge • Efficiency (ratio) • Inverter• sizeMax (kW charge AC) hours ▪ Electrical (Power, Energy) ▪ Heat• Charge Pump efficiency • CHP capable? (yes/no) • Total land• areaBattery (m2) size ▪ Thermal (Chiller, Refrig.) ▪ CHP• Discharge efficiency • Alpha (power to heat ratio) ------• Efficiency ▪ HVACR• Decay/self-discharge (fraction of total capacity per • NOx emissions rate (kg/hr) • Capital •costDecay ($) ▪ Solarhour) Thermal • etc. • Maximum annual operating hours (hours) • ------Lifetime (years) • Minimum loading (% of power) • O&M fixed costs ($/year) • Fixed cost ($) SOC ------• • O&MVariable variable Cost costs ($/kw ($/year/kW) or $/kwh) Other • Capital cost ($) • Lifetime (years) • Lifetime (years) ▪ Electric Vehicles Disconnect • O&M fixedConnect costs ($/year) • O&M fixed costs ($/year) • O&M variable costs ($/year/unit) • NOx treatment costs ($/kg) t
16 © 2015 Electric Power Research Institute, Inc. All rights reserved.
Variable Distributed Energy Assets within Microgrid Source: PNNL Source:
17 © 2015 Electric Power Research Institute, Inc. All rights reserved. Key Considerations in Design for Energy Storage
. Standby Power Loss – Storage is primarily needed when the microgrid is islanded – Standby power loss will reduce the efficiency of the microgrid
• Response time – For seamless transition, response time must be very fast – This is more than just battery response time – communications latency and control functions also play a role
18 © 2015 Electric Power Research Institute, Inc. All rights reserved. Isochronous / Droop Modes of Operation
. Isochronous - Isochronous control mode means that the frequency (and voltage) of the electricity generated is held constant, and there is zero generator droop. . Droop Control Mode - strategy commonly applied to generators for frequency control (and occasionally voltage control) to allow parallel generator operation (e.g. load sharing). . For grid-tied microgrids – all the DG and storage resources operate in droop mode and the utility is the isochronous generator reference. . For off-grid microgrids – one generating unit is designated to run in isochronous mode and all other follow in droop mode. Larger units and higher inertia prime movers are normally the reference machine. PV inverters are nearly always operating in droop mode. Battery inverters may operate either way when generating. 19 © 2015 Electric Power Research Institute, Inc. All rights reserved. Controller Integration
20 Source: EPRI DOE SHINES Project © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Technical Challenges : Protection
. Not enough short-circuit current in Microgrid mode for protection to sense and operate – Voltage-based protection was recommended : No need for multiple settings group to support grid or islanded operation . May require additional equipment and change in protection settings. . Insulation coordination could be an issue . Microgrid operation may result in loss of effective ground reference
Keeping protection scheme simple translates into improved dependability as well as much simpler analysis in the event of misoperation
21 © 2015 Electric Power Research Institute, Inc. All rights reserved. For a small microgrid: need to understand the load Daily, from hourly to cycles in single family residence Knoxville, TN
8.0 kWmax 10.7 kWmax 85.1 kWh 85.1 kWh
44% Load factor 33%
14.8 kWmax 26.2 kWmax 85.1 kWh 85.1 kWh
24% 14%
22 © 2015 Electric Power Research Institute, Inc. All rights reserved. PQ Enhancements Possible
.Instant Islanding to mitigate campus interruptions caused by feeder faults .Proactive islanding due to “expected” feeder interruption or voltage sag (e.g. approaching lightning storm) .Partial voltage sag mitigation by means of DG voltage support during fault! .Improved local voltage flicker and regulation due to lower impedance of power system
23 © 2015 Electric Power Research Institute, Inc. All rights reserved. Low Voltage Ride-Through
. No low voltage ride-through requirements in the current IEEE Std1547-2003 version (or the amendments) . A full revision of the 1547 is under way – inclusion of ride-through requirements is considered . The CA Rule 21 ride-through requirements will likely inform the IEEE Std 1547 ride-through requirements
The inverter must stop producing power but be ready to produce power again if the voltage starts to normalize before the inverter is allowed 24 to trip © 2015 Electric Power Research Institute, Inc. All rights reserved. Dynamic Models and Controls
25 © 2015 Electric Power Research Institute, Inc. All rights reserved. Micro-Grid Switching - MV vs LV
From Utility From Utility Typical Main Switch 12 kV Typical Main Switch 12 kV MV-CB MV-CB
Point Of Control JC Jn. Box 12 kV 12 kV
Service 12 kV/ Service 12 kV/ Xfmr 208V Xfmr 208V
LV-CB LV-CB Point Of Control Building Building Building Load Load PV
26 © 2015 Electric Power Research Institute, Inc. All rights reserved. Micro-Grid Switching at MV Level
From Utility Approach: Typical Main Switch 12 kV . Circuit breakers are available only at 12kV main ring. No 12kV circuit breakers downstream. MV-CB . Each circuit breaker controls a group of Point Of transformers/buildings. Control . Control is at the group level. No individual Jn. Box 12 kV control at building level Consequences: . Switching OFF a transformer on 12kV side disconnects both building loads and connected PV. This results in loss of generation (PV on non critical buildings) when resources are needed Service 12 kV/ during islanded operation. Xfmr 208V . This design necessitates permanently assigning buildings as critical and non-critical. It is not possible to reassign them later. Building . 12KV switching could cause high transformer Load inrush currents during black start. Mitigating equipment may be required if storage inverters are not able to handle this high inrush current.
27 © 2015 Electric Power Research Institute, Inc. All rights reserved. Micro-Grid Switching at LV
From Utility Approach: Typical Main Switch 12 kV . Control is shifted to the Low Voltage side. MV-CB . Transformers are connected to buildings through Low Voltage distribution boards. . This creates the ability to separately control loads JC and generation within the buildings. 12 kV Consequences: . No loss of generation (PV on non critical buildings) when loads are disconnected during islanded operation. Service 12 kV/ Xfmr 208V . Ability to reassign buildings as critical / non- critical as and when needed. LV-CB LV-CB . As loads are disconnected from the LV side it is Point Of Control possible to reestablish the MV ring through soft Building Building start with all transformers connected. This could Load PV reduce inrush current significantly.
28 © 2015 Electric Power Research Institute, Inc. All rights reserved. Transformer inrush current and its impact
. Inrush current during the energizing could be much higher than the full rated current. It is short lived – a few cycles only. . Inrush currents can be as high as 6 and 18 times the rated current. Magnitude of inrush current depends on several factors – e.g. – Primary voltage – Transformer saturation curve – Short circuit capacity of the network – lower the short circuit level, lower the inrush current . Impact – Inrush currents are reactive and can cause voltage drops – Inrush currents do not normally pose any challenge in grid connected mode as rotary generators are designed to handle these high currents – However inverters are not designed to carry these. Typically they can handle up to 2 to 3 times their rated current but not more.
29 © 2015 Electric Power Research Institute, Inc. All rights reserved. Transformer Energizing: Equivalent Circuit
The short-circuit strength of the circuit determines the magnitude of the inrush current during transformer energizing.
휕l(푖, 푡) 휕푖(푡) In differential equation: 푣 푡 = 푍 푖 푡 + 푋 푖 푡 + 푠 푠 푙푘 휕푖(푡) 휕푡 l(푖, 푡) = the total magnetic flux linkage 푖 푡 = inrush current when energized
In a strong system, 푍푠 is small. The inrush current 푖 푡 will be larger. In a weak system, 푍푠 is large. The inrush current 푖 푡 will be smaller.
30 © 2015 Electric Power Research Institute, Inc. All rights reserved. Transformer Core Saturation Characteristics: I-V
31 © 2015 Electric Power Research Institute, Inc. All rights reserved. Transformer Energizing: Full-Voltage Energizing With a Typical Saturation Curve .Transformer is unloaded energized at bus full voltage. Short- circuit strength is x .1.5 MVA, 12.47 kV/480V, 5.07% (for now - Ygnd Ygnd) Short-circuit capacity at 12.47 kV bus = 300 MVA Short-circuit capacity at 12.47 kV bus = 30 MVA .Rated transformer current = 70 Arms = 98 Apk 4.6x 3.5x
32 © 2015 Electric Power Research Institute, Inc. All rights reserved. Transformer Energizing: Full-Voltage Energizing With a Very Flat Saturation Curve .Transformer is unloaded energized at bus full voltage. .1.5 MVA, 12.47 kV/480V, 5.07% (for now - Ygnd Ygnd)
Short.Rated-circuit capacity transformer at 12.47 kV bus current = 300 MVA = 70 ShortArms-circuit = capacity 98 Apk at 12.47 kV bus = 30 MVA
20x
9x
33 © 2015 Electric Power Research Institute, Inc. All rights reserved. Design Analysis Load Analysis
unacceptable overvoltage Microgrid Controller DER Sizing & Design voltage limits Architecture & Design
Load Only time Watts
Load and PV Design Analysis Impedance Approach
Location √ no impact • Steady State load flow Relay desensitization
unserved energy • System Dynamic
Energy • Harmonics
case by case Current look needed Energy exceeding normal • Flicker
Time Location X • Controls Potential risk • Operation seq. Impedance Distribution System Modeling, • Fault Current Simulation & Optimization • Black Start Protection & Reliability
34 © 2015 Electric Power Research Institute, Inc. All rights reserved. Microgrid Design Analysis
Commissioning Data Collection Modeling Impact Studies & Operation
o Network models o Scenarios o Steady state o Model validation •Load types o Model validation o Fault analysis o Real time ops & •DER types o Grid impact o Protection monitoring •Operation o Stability studies o Protection info
35 © 2015 Electric Power Research Institute, Inc. All rights reserved. Key interests
Load flow
• Is the micro grid gen(s) is enough to support the islanded load? • Verify compliance to planning & voltage stability requirements
Protection analysis
• Is existing protection adequate? • If not, try various options
Dynamic studies
• Events (loss of large load, load step & fault clearing capabilities) • Fault Ride Through capabilities of various inverter-based DERs
36 © 2015 Electric Power Research Institute, Inc. All rights reserved. Detailed Design Analysis – Tools
Source: LBNL Paper LBNL-6708E
A variety of MC capabilities requires a variety of models to understand • Performance • Grid interaction • System Protection Scheme Impact
OpenDSS/Grid Lab D/DEW
PSCAD/EMTP-RV/MATLAB DesignBase
DIGSILENT All PSS/SINCAL
CYMDIST Need to apply a consistent modeling framework SynerGEE
Allow existing models to feed new analysis Time-Series Time-Series Transient Dynamic Analysis/Slow Analysis/SS Steady State Dynamics Steps
Microseconds Milliseconds Seconds Minutes Hours Days
37 © 2015 Electric Power Research Institute, Inc. All rights reserved. Available Tools Software Tool Affiliated Org. Tool Type CYMDIST CYME International T&D Inc. Planning and simulation of distribution networks, including load flow, short-circuit, and network optimization analysis. DER-CAM Lawrence Berkeley National Techno-economic tool for microgrid design and Laboratory (LBNL) operation. DesignBase Power Analytics Broad platform for electrical system design, simulation, and optimization. EMTP-RV POWERSYS Solutions Power system transients simulation, load flow, harmonics. EUROSTAG Tractebel Engineering GDF Power system dynamics simulation; full range of Suez transient, mid- and long-term stability; steady-state load flow computation. GridLAB-D Pacific Northwest National Distribution system simulation and analysis. Laboratory (PNNL) HOMER Homer Energy LLC, National Techno-economic tool for microgrid design and Renewable Energy operation. Laboratory (NREL) OpenDSS Electric Power Research Distribution system simulation and analysis. Institute (EPRI) PowerFactory DIgSILENT GmbH Power system analysis tool for load flow and harmonics in transmission, distribution, and industrial networks. PSCAD Manitoba HVDC Research Power system transient simulation, load flow Center simulation. PSS/E Siemens Power Technologies Load flow, dynamic analysis, and harmonic analysis of International (Siemens PTI) utility and industrial networks. 38 © 2015 Electric Power Research Institute, Inc. All rights reserved. Simulation Tools - Comparison
Power Study Power Flow, Short Relay Arc Harmonic Transient Dynamic Quasi Steady- Flow, unbalanced Circuit Coordination Flash Analysis Analysis Analysis State Analysis Tool balanced EMTP-RV, Simulink, PSCAD
Aspen, Cape
DesignBase, PowerFactory
PSLF, PSS/E
OpenDSS
GridLAB-D
Best choice
Can be done, but not preferred choice
Cannot be done
39 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case # 1:Protection Case Studies (Mohamed El Khatib)
Renewable Based Microgrids
40 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case # 2: Rural Radial Community (Arindam Maitra)
41 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case Study: Two Remote Rural Communities
3.25MW of Load 6.5MW of DG
42 © 2015 Electric Power Research Institute, Inc. All rights reserved. One-line diagram of the 34.5-kV R55 R173 Existing 34.5 KV Existing Recloser Recloser 34.5 KV
Plant Load: 5MW 4.8 KV
Plant Load: 1MW
Plant Load: 1.8MW Wind plant : 6.6 MW
Sync DG: 0.416 MW
Wind Turbine: Type 2 induction generator with rotor resistor control. This type of turbine needs a stiff transmission grid and a strong synchronous source for stable operation and can introduce oscillations if it remains connected during islanded operation. They require external reactive support to maintain voltage, which is typically provided by static or/and dynamic compensation
43 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case Study: Reliability Assessments In Rural Areas of New York
Fault Exposure Scenario #1 . Electricity customers in rural areas Proposed Existing Proposed Existing 34.5 KV Reclosure of NY have been experiencing Reclosure Reclosure Reclosure 34.5 KV power outages lasting 10 hours & longer, which far exceeds the Plant Load: 5MW Customer Average Interruption 4.8 KV Proposed Proposed 2 MWHR Energy Duration Index (CAIDI) targets Plant Load: 1MW PQ Meter Storage Plant Load: 1.8MW
Proposed 1 MWHR Energy Storage Wind plant : 6.6 MW
Microgrid 1 . Average statewide CAIDI target is Sync DG: 0.416 MW ~ 2 hours Fault Exposure Scenario #2
Proposed Existing Proposed Existing 34.5 KV Reclosure Reclosure Reclosure Reclosure 34.5 KV
. This problem is due, in part, to the
Plant Load: 5MW fact that many remote areas of 4.8 KV Proposed New York State are fed radially Proposed 2 MWHR Energy Plant Load: 1MW PQ Meter Storage and have only a single Plant Load: 1.8MW
Proposed transmission or sub-transmission 1 MWHR Energy supply line that feeds these areas Storage Wind plant : 6.6 MW Microgrid 2 Sync DG: 0.416 MW
44 © 2015 Electric Power Research Institute, Inc. All rights reserved. Design Study
. Rural electrification in areas with otherwise poor reliability is the key driver to evaluate microgrid as a possible solution
– Many remote communities are situated in locations without a backup transmission or sub-transmission connection
– Restoration time is quite high
– Microgrids can play a role in reducing fault investigation time, shorter outage duration and lower costs for first responders
– Operating remote communities as a microgrid
. Complete transition from grid-connected operation to micro-grid operation within 15 minutes following the loss of the supply line . Supply at least 50% of the customers in the Wethersfield and 50% customers in Orangeville area for at least (8) hrs
45 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case Study: Focus Areas
−Define the Modes of Operations – Based on a permanent fault location on 34.5 kV supply line and system protection requirements, different microgrid scenarios are identified. Additional equipment or changes in the circuit configuration to facilitate stable operation of the microgrids is proposed
−System Protection Study – Identify the required enhancements to protections system for the area under study during microgrid conditions.
− A high-level protection system design (relay types, communication needs, etc.) that are needed to accommodate normal and microgrid operation
−Fault Location Study – Develop improved fault locating algorithms for a utility-supplied distribution circuit
− Emphasis was on 34.5 kV line and underlying 4.8 kV system as well to evaluate the possible local microgrid effects at the 4.8 kV side.
− Develop improved fault locating algorithms in PSCAD
46 © 2015 Electric Power Research Institute, Inc. All rights reserved. − Possible Microgrid Configurations
. Microgrid “OW”: both circuits operate as a unified microgrid
. Microgrid “W”: Circuit operates as a standalone microgrid
. Microgrid “O”: Circuit operates as a standalone microgrid
47 © 2015 Electric Power Research Institute, Inc. All rights reserved. Technical Limitations with Current Protection
Fault Condition # 1: – Grid Connected Mode: Fault Exposure Scenario #1
Proposed . For a permanent fault between Existing Proposed Existing 34.5 KV Reclosure Attica and Orangeville, recloser Reclosure Reclosure Reclosure 34.5 KV R55 will open. Since R55 is the
Plant Load: 5MW only upstream recloser both 4.8 KV Proposed circuits with be out of service Proposed 2 MWHR Energy Plant Load: 1MW PQ Meter Storage . Need for local generation Plant Load: 1.8MW Proposed 1 MWHR Energy . Important to isolate the fault Storage Wind plant : 6.6 MW Microgrid 1 Sync DG: 0.416 MW – EPRI proposes a new recloser at Exchange St Rd P122. This will allow Orangeville and Wethersfield to be served as microgrid (“OW”) with energy storage while the fault is being cleared 48 © 2015 Electric Power Research Institute, Inc. All rights reserved. Technical Limitations with Current Protection System (cont.)
Fault Condition # 2: Fault Exposure Scenario #2
Proposed Existing Proposed Existing 34.5 KV Reclosure – Grid Connected Mode: Reclosure Reclosure Reclosure 34.5 KV . Permanent fault between
recloser R173 and Plant Load: 5MW Wethersfield, recloser R173 4.8 KV Proposed will open to save Wetherfield Proposed 2 MWHR Energy Plant Load: 1MW PQ Meter Storage Plant Load: 1.8MW
. Isolate the 4.8KV system in Proposed 1 MWHR Energy Wethersfield to prevent back Storage Wind plant : 6.6 MW feed from Wind farm (& Microgrid W Energy storage system Sync DG: proposed as part of the 0.416 MW microgrid mode) . In this scenario, Orangeville and Boxler plant remain connected to the Attica substation in “grid-tie” mode. – EPRI proposes a new recloser at J197/J199. Wethersfield will operate as a standalone microgrid (“W”)
49 © 2015 Electric Power Research Institute, Inc. All rights reserved. Attica 34.5kV R122 (new) Orangeville Tap R55
1 1 3 Wind Farm R173 (Form 6) New relay 3 - set of 3 wye-gnd 2.5MVA connected VTs 34.5kV:4.8kV X 1 – single VT
Wethersfield R199 (new) storage 1 battery 1 500kVA 3
Beckwith M-3410A Y Boxler Farm storage battery 2
50 © 2015 Electric Power Research Institute, Inc. All rights reserved. Permanent fault occurs here
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122
51 © 2015 Electric Power Research Institute, Inc. All rights reserved. • X and Y opened by 34.5kV voltage protection before first reclose of R55 • R55 in reclosing cycle
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 52 © 2015 Electric Power Research Institute, Inc. All rights reserved. • R55 locks out
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 53 © 2015 Electric Power Research Institute, Inc. All rights reserved. • R122, R173, and R199 open
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 54 © 2015 Electric Power Research Institute, Inc. All rights reserved. • Both battery systems come back online and close X & Y
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 55 © 2015 Electric Power Research Institute, Inc. All rights reserved. • R199 will close using hot bus – dead line
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 56 © 2015 Electric Power Research Institute, Inc. All rights reserved. • R173 will close using sync-check • Complete island established
Orangeville Tap X R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 57 © 2015 Electric Power Research Institute, Inc. All rights reserved. • Fault is removed and R55 manually closed
Orangeville Tap
R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 58 © 2015 Electric Power Research Institute, Inc. All rights reserved. • R122 closes sync-check • System normal
Orangeville Tap
R55 R122 R173 Wind Farm
X
Wethersfield
R199 500kVA
open closed Y in reclosing Boxler Farm cycle Scenario - permanent fault between R55 and R122 59 © 2015 Electric Power Research Institute, Inc. All rights reserved. Recommendations - Protections
• 34.5kV protection and control of micro grid scheme is voltage based • Voltage protection disconnects energy storage batteries prior to entering microgrid operation • Voltage protection detects and clears 34.5kV faults that occur during microgrid operation
• Ferroresonance suppression is prudent for 34.5kV wye-grounded VTs as well as using VTs with high saturation knee point (e.g. 2.0 per unit)
• Low voltage current based protection (e.g. 4.8kV feeders) will have to be evaluated based on energy storage devices capability to source fault current or alternative protection should be investigated – not addressed in this section
• Setting and reclosing setting changes needed on R55 and R173 as well as the additional protection & control described in this section for microgrid operation
60 © 2015 Electric Power Research Institute, Inc. All rights reserved. Proposed Protection, Monitoring, & Control Modifications
WNY Wind Corp. 6.6 MW
Attica Attica Prison Orangeville STA. 19 STA. 12 STA. 34.5 kV R55 R122 R173 34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP 34.5 kV 0 . 1
J192 m Attica Prison Wethersfield STA. 23 i Thevenin equivalent 34.5 kV
Orangeville STA. 19 R
source for 1
4.8 kV 9 Attica substation Orangeville 4.8-kV 9 PQ48V Wethersfield STA. 23 circuit and load 4.8 kV 4 . 0
m i
PQ48B Boxler Farm Wethersfield 4.8-kV 480V, 416 kW Boxler DG circuit and load 4.8 kV
61 © 2015 Electric Power Research Institute, Inc. All rights reserved. Proposed System Level Modifications – Energy Storage System
Proposed Existing Proposed Existing 34.5 KV recloser recloser recloser recloser 34.5 KV
Plant Load: 5MW 4.8 KV Proposed Proposed 2 MWHR Energy Plant Load: 1MW PQ Meter Storage Plant Load: 1.8MW
Proposed 1 MWHR Energy Storage Wind plant : 6.6 MW
Microgrid OW – Sync DG: 0.416 MW Orangeville & Wethersfield
• 2 Separate ES systems proposed. − Closer to the Loads at Orangville and Wethersfield − Valid for independent operations of Orangville and Wethersfield 62 − Smaller Systems are more© 2015 Electric reliable Power Research Institute, Inc. All rights reserved. Fault Location Analysis
WNY Wind Cooper FormC orp. 6.6 MW SEL PG10 Type 6 Attica Attica Prison Orangeville STA. 19 STA. 12 STA. 34.5 kV R55 R122 R173 34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP 34.5 kV 0 . 1
J192 m Attica Prison Wethersfield STA. 23 i Thevenin equivalent 34.5 kV
Orangeville STA. 19 R
source for 1
4.8 kV 9 Attica substation Orangeville 4.8-kV 9 PQ48V Wethersfield STA. 23 circuit and load 4.8 kV 4 . 0
m i
PQ48B Boxler Farm Wethersfield 4.8-kV 480V, 416 kW circuit and load
Number of Monitor Samples/cycle Voltage level Actual Fault Circuit Data useful for events location model fault location
12 R55 4 34.5 kV Unknown ASPEN Yes OneLiner 10 R173 16 Limited
63 © 2015 Electric Power Research Institute, Inc. All rights reserved. Line Exposed to Faults in Grid Connected Mode
. Scenario G1: Multiple single line-to-ground faults applied in Line Section 1, between reclosers R55 and R122
. Scenario G2: Multiple single line-to-ground faults applied in Line Section 2, between reclosers R173 and R199
. Scenario G3: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B
WNY Wind Corp. 6.6 MW
Attica Attica Prison Orangeville STA. 19 STA. 12 STA. 34.5 kV R55 R122 R173 34.5 kV 1.2 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP L i n e S e c t i o n 1 L i n e S e c t i o n 2 34.5 kV 0 . 1
J192 m Attica Prison Wethersfield STA. 23 i Thevenin equivalent 34.5 kV
Orangeville STA. 19 R
source for 1
4.8 kV 9 Attica substation Orangeville 4.8-kV 9 PQ48V Wethersfield STA. 23 circuit and load S L i e 4.8 kV n 4 c e . t 0
i o
m n
i 3
PQ48B Boxler Farm Wethersfield 4.8-kV 480V, 416 kW Boxler DG circuit and load 4.8 kV 64 © 2015 Electric Power Research Institute, Inc. All rights reserved. Line Exposed to Faults in Microgrid Operation
. Scenario OW1: Multiple line-to-line faults applied in Line Section 2, between reclosers R173 and R199 (in Microgrid OW operation)
. Scenario OW2: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B (in Microgrid OW operation)
. Scenario O1: Multiple line-to-line faults applied in Line Section 3, between PQ48V and PQ48B (in Microgrid O operation)
Orangeville STA. 19 34.5 kV R122 R173 0.2 mi 6.1 mi Vestas TAP L i n e S e c t i o n 2 34.5 kV Orangeville STA. 19
0 4.8 kV . 1
J192 m Orangeville 4.8-kV L i i Wethersfield STA. 23 circuit and load n
PQ48V e
34.5 kV S Orangeville STA. 19 4 Orangeville e . R 0 c
4.8 kV 1 Energy Storage
t 9 m i Orangeville 4.8-kV 9 o L i i n circuit and load Wethersfield STA. 23 n
PQ48V e
3 S 4 Orangeville 4.8 kV e . 0 c Energy Storage
t m i
o PQ48B i n
Boxler Farm 3 Boxler DG PQ48B 480V, 416 kW Boxler Farm Wethersfield 4.8-kV 4.8 kV 480V, 416 kW Boxler DG circuit and load Wethersfield 4.8 kV Energy Storage “Microgrid OW” “Microgrid O”
65 © 2015 Electric Power Research Institute, Inc. All rights reserved. Fault Location Algorithms Applied in “Grid Connected” Mode
WNY Wind Corp. 6.6 MW
Attica Attica Prison Orangeville STA. 19 STA. 12 STA. 34.5 kV R55 R122 R173 34.5 kV 1.12 mi 6.3 mi 0.2 mi 6.1 mi Vestas TAP 34.5 kV Line Section 1 Line Section 2 0 . 1
J192 m Attica Prison Wethersfield STA. 23 i Thevenin equivalent 34.5 kV
Orangeville STA. 19 R
source for 1
4.8 kV 9 Attica substation Orangeville 4.8-kV 9 PQ48V Wethersfield STA. 23 circuit and load 4.8 kV 4 . 0
m i
PQ48B
Boxler Farm Wethersfield 4.8-kV LineSection 3 480V, 416 kW circuit and load
Scenario Algorithms to be Applied during SLG Faults
One-ended methods (R55) Simple reactance, Takagi, Novosel et al. Line Section 1 Two-ended method (R55, R122) Two-terminal negative-sequence
Line Section 2 One-ended methods (R173) Simple reactance, Takagi, Novosel et al.
One-ended methods (PQ48B) Simple reactance, Takagi, Eriksson Line Section 3 Two-ended methods (PQ48B, PQ48V) Two-terminal negative-sequence 66 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case # 3: Secondary Network (Arindam Maitra)
67 © 2015 Electric Power Research Institute, Inc. All rights reserved. Case Study #3: Secondary Network
.Models developed in OpenDSS, EMTP-RV, & Power Factory
.Microgeneration types: CHP behind inverter and PV
.Scenario tested: Small-scale Distributed CHP units (small synchronous machine behind an inverter) + small scale PV
68 © 2015 Electric Power Research Institute, Inc. All rights reserved. One Line Diagram
69 © 2015 Electric Power Research Institute, Inc. All rights reserved. Scenarios
1. Small-scale Distributed CHP units (small synchronous machine behind
an inverter) + small scale PV BLDG 7 0.05 MVA BLDG 6 0.05 MVA BLDG 5 0.05 MVA 0.3 MVA (5917.44X_10384) 0.3 MVA (5877.44X_M1048) 0.3 MVA (5829.44X_10385) 2. Small-scale Distributed CHP units kVA = 314.794 kVA = 222.239 kVA = 182.114
(small synchronous machine behind Inverter Inverter Inverter Inverter Inverter Inverter an inverter) + small scale PV +
) M1049 10385 small scale distributed storage )
(44X_M1049) (44X_10385)
1048
10384 _
M M1047
1048
10384
X
_
M X
3. Large-scale Central CHP unit (large 44 (44X_M1047)
( 44 synchronous machine) + small (
scale PV VS8360 (44X_VS8360) BC3998 4. Large-scale Central CHP unit (large (44X_BC3998)
0.025 MVA Inverter 0.025 MVA synchronous machine) + small
Inverter VS4007 VS3998 scale PV + Large-scale central (44X_VS4007) (44X_VS3998)
0.15 MVA Inverter 0.15 MVA storage 303 Vernon Ave 303 Vernon Ave
Inverter (5766.44X_BC3998) (5916.44X_BC3998) 5. 100% Large CHP unit (large kVA = 140.5 kVA = 310.728 synchronous machine) 6. 100% Large CHP unit (large synchronous machine behind an inverter)
70 © 2015 Electric Power Research Institute, Inc. All rights reserved. Assumptions
. The LV system is solidly grounded via a dedicated ground link at: – Distribution supply transformer LV (transformers are Delta-Wye, directly connected to ground on the secondary side) – Each LV generator (generators are Y connected to ground) – LV network protection vaults
. System impedance to ground is maintained at less than 5 ohms as specified by Client
. The DERs are assumed: – 3-phase YN connected and the neutral is solidly grounded – Provide up to 1.8 per unit fault current – Can sustainably provide fault current, including earth fault current until fault is cleared or isolated
71 © 2015 Electric Power Research Institute, Inc. All rights reserved. General philosophy used
. Determine the required level of selectivity for different fault scenarios. Generally, this can be determined by considering the impact to the customers for different grid faults.
. Group parallel cables connecting common LV nodes together into single ’branches’
. Split the Microgrid into separate regions/zones which with appropriate protection grading will achieve the desired selectivity.
. Ensure LV grid relays protecting branches directly connected to customers trip first to remove the fault from the remaining healthy grid as quickly as possible
. Ensure some time delay between tripping of customer branches and any interconnector circuits connecting together main LV nodes
. Ensure customer relays trip last to ensure healthy generation remains in service post fault
72 © 2015 Electric Power Research Institute, Inc. All rights reserved. High selectivity protection zones
73 © 2015 Electric Power Research Institute, Inc. All rights reserved. Grid Connected Mode – Summer Peak Steady State Branch Currents and Bus Voltages
From Current Loading Line ID To Bus Bus (A) (%) sec_6643_1 143 17% sec_6643_2 143 17% 10385 M1047 sec_6644_1 159 20% sec_6644_2 159 20% Phase A Phase B Phase C Bus ID sec_6645_1 129 16% (pu) (pu) (pu) sec_6645_2 129 16% M1048 0.98 0.98 0.98 sec_6646_1 M1047 M1048 115 14% 10384 0.96 0.96 0.96 sec_6646_2 115 14% 10385 0.97 0.97 0.97 sec_6646_3 115 14% BC3998 0.99 0.99 0.99 sec_6649_1 213 25% M1049 0.96 0.96 0.96 sec_6649_2 M1048 10384 213 25% M1047 0.97 0.97 0.97 sec_6650_1 239 29% VS8360 0.98 0.98 0.98 sec_6651_1 M1049 10384 0 0% VS4007 0.99 0.99 0.99 sec_6751_1 249 29% VS3998 0.99 0.99 0.99 sec_6751_2 BC399 249 29% M1048 sec_6751_3 8 249 29% sec_6751_4 249 29% sec_6754_1 244 29% sec_6754_2 244 29% VS8360 M1048 sec_6754_3 244 29% 74 sec_6754_4 244© 2015 Electric Power29% Research Institute, Inc. All rights reserved. 74 Summer Peak Steady State and Fault Induced Bus Voltages – Grid Connected & Islanded
Summer Load Fault @ 10384 Fault @ BC3998 Fault @ M1048 Bus ID Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phas Phas A B C A B C A B C A e B e C M1048 0.98 0.98 0.98 0.69 0.69 0.69 0.37 0.37 0.37 0.00 0.00 0.00 10384 0.98 0.98 0.98 0.00 0.00 0.00 0.66 0.66 0.66 0.47 0.47 0.47 In10385 grid connected0.99 0.99 0.99 0.79 0.79 0.79 0.59 0.59 0.59 0.35 0.35 0.35 BC3998mode the0.98 bus 0.98 0.98 0.79 0.79 0.79 0.00 0.00 0.00 0.32 0.32 0.32 voltagesM1047 0.99of un- 0.99 0.99 0.74 0.74 0.74 0.48 0.48 0.48 0.17 0.17 0.17 VS8360 0.99 0.99 0.99 0.73 0.73 0.73 0.46 0.46 0.46 0.14 0.14 0.14 VS4007faulted buses0.99 are0.99 0.99 0.86 0.86 0.86 0.33 0.33 0.33 0.55 0.55 0.55 VS3998non-zero0.99 0.99 0.99 0.80 0.80 0.80 0.04 0.04 0.04 0.35 0.35 0.35
Summer Load Fault @ 10384 Fault @ BC3998 Fault @ M1048 Bus ID Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase Phase A B C A B C A B C A B C M1048 1.00 1.00 1.00 0.13 0.13 0.13 0.05 0.05 0.05 0.00 0.00 0.00 10384 1.00 1.00 1.00 0.00 0.00 0.00 0.09 0.09 0.09 0.05 0.05 0.05 When10385 islanded1.01 1.01 1.01 0.15 0.15 0.15 0.07 0.07 0.07 0.03 0.03 0.03 BC3998the bus voltages1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02 areM1047 close1.00 to zero1.00 1.00 0.14 0.14 0.14 0.06 0.06 0.06 0.01 0.01 0.01 VS8360and inadequate1.00 1.00 1.00 0.13 0.13 0.13 0.05 0.05 0.05 0.00 0.00 0.00 VS4007for fault location1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02
VS3998determination75 1.00 1.00 1.00 0.14 0.14 0.14 0.00 0.00 0.00 0.02 0.02 0.02 © 2015 Electric Power Research Institute, Inc. All rights reserved. 75 Changes from Grid Connected Mode to Islanded Mode in Summer Peak Steady State and Fault Induced Phase A Branch Currents
Summer Fault @ Line ID From Bus To Bus Fault @ 10384 Fault @ M1048 Load BC3998 sec_6643_1 78% -75% -87% -92% sec_6643_2 78% -75% -87% -92% When islanded10385 M1047 sec_6644_1fault currents 78% -75% -87% -92% sec_6644_2 78% -75% -87% -92% decrease for all sec_6645_1 78% -75% -87% -92% sec_6645_23-phase faults 78% -75% -87% -92% sec_6646_1When islandedM1047 M1048 78% -75% -87% -92% sec_6646_2line loading 78% -75% -87% -92% sec_6646_3increases for 78% -75% -87% -92% sec_6649_1 -31% -82% -85% -90% sec_6649_2most lineM1048 10384 -31% -82% -85% -90% sec_6650_1sections -31% -82% -85% -90% sec_6751_1 279% -86% -88% -95% sec_6751_2 279% -86% -88% -95% M1048 BC3998 sec_6751_3 279% -86% -88% -95% sec_6751_4 279% -86% -88% -95% Total Fault Current at the Fault Location (%) -89% -93% -93%
76 © 2015 Electric Power Research Institute, Inc. All rights reserved. Modeling Existing Protection
Typical TCC for a current-limiting fuse
Used representative curves Curve in power factory
77 © 2015 Electric Power Research Institute, Inc. All rights reserved. Findings and recommendations: Current-Limiting Protection
.Normally the Current limiter (CL) fuse will “melt” when the current in the fuse element exceeds the current specified by the fuse’s melt characteristic.
.No enough fault currents from the inverter based gens; hence there is no compliance to protection standards and performance metrics during island mode
.Clearly, this type of protection in utilizing current limiters isn’t sufficient
.Another set of protection strategies need to be adopted
78 © 2015 Electric Power Research Institute, Inc. All rights reserved. Small-scale Distributed CHP units (small synchronous machine behind an inverter) + small scale PV
Circuit breakers
Directional- Overcurrent
• The overcurrent modules and circuit breakers tip-times depend on the fault-current amplitude • The appropriate directional modules were set to trip slightly after the overcurrent models
79 © 2015 Electric Power Research Institute, Inc. All rights reserved. 79 3 Phase Fault @ 10384
80 © 2015 Electric Power Research Institute, Inc. All rights reserved. 80 3 Phase Fault @ 10384
2
1 1. D/O module between 10384 and M1048 trips on overcurrent 2. Circuit breaker at 10384 PCC trips on overcurrent
81 © 2015 Electric Power Research Institute, Inc. All rights reserved. 81 3 Phase Fault @ 10384
Isolated
Loads and generators at bus 10384 are isolated
82 © 2015 Electric Power Research Institute, Inc. All rights reserved. 82 3 Phase Fault @ 10384
After fault is cleared bus voltages recover to normal values
83 © 2015 Electric Power Research Institute, Inc. All rights reserved. 83 1 Phase Fault @ 10384
84 © 2015 Electric Power Research Institute, Inc. All rights reserved. 84 1 Phase Fault @ 10384
2
1 1. D/O module between 10384 and M1048 trips on overcurrent 2. Circuit breaker at 10384 PCC trips on overcurrent
85 © 2015 Electric Power Research Institute, Inc. All rights reserved. 85 1 Phase Fault @ 10384
Isolated
Loads and generators at bus 10384 are isolated
86 © 2015 Electric Power Research Institute, Inc. All rights reserved. 86 1 Phase Fault @ 10384
After fault is cleared bus voltages recover to normal values
87 © 2015 Electric Power Research Institute, Inc. All rights reserved. 87 1 Phase Fault (46.6 mΩ) @ 10384
88 © 2015 Electric Power Research Institute, Inc. All rights reserved. 88 1 Phase Fault (46.6 mΩ) @ 10384
2
1 1. D/O module between 10384 and M1048 trips on overcurrent 2. Circuit breaker at 10384 PCC trips on overcurrent
89 © 2015 Electric Power Research Institute, Inc. All rights reserved. 89 1 Phase Fault (46.6 mΩ) @ 10384
Isolated
Loads and generators at bus 10384 are isolated
90 © 2015 Electric Power Research Institute, Inc. All rights reserved. 90 1 Phase Fault (46.6 mΩ) @ 10384
After fault is cleared bus voltages recover to normal values
91 © 2015 Electric Power Research Institute, Inc. All rights reserved. 91 Phase-Phase Fault @ 10384
92 © 2015 Electric Power Research Institute, Inc. All rights reserved. 92 Phase-Phase Fault @ 10384
2
1 1. D/O module between 10384 and M1048 trips on overcurrent 2. Circuit breaker at 10384 PCC trips on overcurrent
93 © 2015 Electric Power Research Institute, Inc. All rights reserved. 93 Phase-Phase Fault @ 10384
Isolated
Loads and generators at bus 10384 are isolated
94 © 2015 Electric Power Research Institute, Inc. All rights reserved. 94 Phase-Phase Fault @ 10384
After fault is cleared bus voltages recover to normal values
95 © 2015 Electric Power Research Institute, Inc. All rights reserved. 95 Phase-Phase-Ground Fault @ 10384
96 © 2015 Electric Power Research Institute, Inc. All rights reserved. 96 Phase-Phase-Ground Fault @ 10384
2
1 1. D/O module between 10384 and M1048 trips on overcurrent 2. Circuit breaker at 10384 PCC trips on overcurrent
97 © 2015 Electric Power Research Institute, Inc. All rights reserved. 97 Phase-Phase-Ground Fault @ 10384
Isolated
Loads and generators at bus 10384 are isolated
98 © 2015 Electric Power Research Institute, Inc. All rights reserved. 98 Phase-Phase-Ground Fault @ 10384
After fault is cleared bus voltages recover to normal values
99 © 2015 Electric Power Research Institute, Inc. All rights reserved. 99 3 Phase Fault @ M1048
100 © 2015 Electric Power Research Institute, Inc. All rights reserved. 100 3 Phase Fault @ M1048
1 3
4
1. D/O module between 10384 and M1048 trips on directional 2 2. D/O module between BC3998 and M1048 trips on directional 3. D/O module between M1047 and M1048 trips on overcurrent 4. Circuit breaker at M1048 PCC trips on overcurrent
101 © 2015 Electric Power Research Institute, Inc. All rights reserved. 101 3 Phase Fault @ M1048
Isolated Isolated Isolated
Loads and generators at all buses are isolated
Isolated
102 © 2015 Electric Power Research Institute, Inc. All rights reserved. 102 3 Phase Fault @ M1048
After fault is cleared bus voltages: 1. at 10385 and M1048 are elevated 2. at BC3998 are bellow normal values 3. at 10384 recover to normal values
103 © 2015 Electric Power Research Institute, Inc. All rights reserved. 103 3 Phase Fault @ BC3998
104 © 2015 Electric Power Research Institute, Inc. All rights reserved. 104 3 Phase Fault @ BC3998
1
1. D/O module between BC3998 and M1048 trips on overcurrent 2 2. Circuit breaker at BC3998 PCC trips on overcurrent
105 © 2015 Electric Power Research Institute, Inc. All rights reserved. 105 3 Phase Fault @ BC3998
Loads and generators at bus BC3998 are isolated
Isolated
106 © 2015 Electric Power Research Institute, Inc. All rights reserved. 106 3 Phase Fault @ BC3998
After fault is cleared bus voltages: 1. at 10384, 10385 and M1048 are elevated 2. at BC3998 are bellow normal values
107 © 2015 Electric Power Research Institute, Inc. All rights reserved. 107 3 Phase Fault @ 10385
108 © 2015 Electric Power Research Institute, Inc. All rights reserved. 108 3 Phase Fault @ 10385
1
2
1. D/O module between 10385 and M1048 trips on directional 2. Circuit breaker at 10384 PCC trips on overcurrent
109 © 2015 Electric Power Research Institute, Inc. All rights reserved. 109 3 Phase Fault @ 10385
Isolated
Loads and generators at bus 10385 are isolated
110 © 2015 Electric Power Research Institute, Inc. All rights reserved. 110 3 Phase Fault @ 10385
After fault is cleared bus voltages: 1. at 10385 are elevated 2. at 10384, M1048, and BC3998 are bellow normal values
111 © 2015 Electric Power Research Institute, Inc. All rights reserved. 111 Summary “Microgrids” brings many technical needs: Good PSA tools available
• Network Grid requirements
• Objective Controllability
• Scenarios Monitoring
• Modeling Reliability
No one-size fits all protection scheme works for all microgrids
Best protection scheme depends on microgrid objective
Continue testing various protection schemes Action plan Level of dynamic studies details depends on so many factors i.e. gen types, operation philosophy etc.
112 © 2015 Electric Power Research Institute, Inc. All rights reserved. Together…Shaping the Future of Electricity
113 © 2015 Electric Power Research Institute, Inc. All rights reserved.