<<

Western Isles HVDC Link Consultation Western Isles HVDC Link Consultation

Who we are

We are Scottish and Southern Electricity Networks, operating under licence as Scottish Hydro Electric Transmission Plc for the transmission of electricity in the north of .

What is the difference between Transmission and Distribution?

Electricity Transmission is the transportation of electricity from generating plants to where it is required at centres of demand.

The Electricity Transmission network, or grid, transports electricity at very high voltages through overhead wires, underground cables and subsea cables. The transmission network connects large scale generation, primarily renewables, to central and southern Scotland and the rest of Great Britain. It also helps secure supply by providing reliable connection to the wider network of generation plans.

The Electricity Distribution network is connected into the Transmission network but the voltage is lowered by transformers at electricity substations, and the power is then distributed to homes and businesses through overhead lines or underground cables.

Overview of Transmission projects

In total we maintain about 5,000km of overhead lines and underground cables – easily enough to stretch across the Atlantic from John O’Groats all the way to Boston in the USA.

Our network crosses some of the UK’s most challenging terrain – including circuits that are buried under the seabed, are located over 750m above sea level and up to 250km long.

The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is a high demand to connect from new wind, hydro and marine generators which rely on Scottish and Southern Electricity Networks to provide a physical link between the new sources of power and electricity users. Scottish and Southern Electricity Networks is delivering a major programme of investment to ensure that the network is ready to meet the needs of our customers in the future. Our responsibilities

We have a licence for the transmission of electricity in the north of Scotland and we are closely regulated by the energy regulator Ofgem.

Our licence stipulates that we must develop and maintain an efficient, co-ordinated and economical system of electricity transmission.

02 www.ssen-transmission.co.uk/projects/western-isles www.ssen-transmission.co.uk/projects/western-isles

Welcome

Welcome to this statutory pre-application consultation event in relation to Scottish Hydro Electric Transmission plc (SHE Transmission) upcoming plans to submit a Marine Licence application to Scottish Ministers for the subsea element of their proposed Western Isles Connection (the Project) between Arnish and Dundonnell.

The exhibition provides: SHE Transmission, as part of a much larger project, is proposing to construct and commission a subsea High Voltage Direct Current (HVDC) Link, which will be approximately 81km in length and with a capacity of 600MW between Arnish and Dundonnell. • Project Need

• Project Overview

• Project Timeline

• Subsea Route Selection

• Subsea Routing Considerations

• Landfall Locations

• The Consenting Process

Project Need

At present the existing Western Isles system operates with a restricted 132kV connection to the Scottish mainland. The Western Isles possess attractive renewable resources which have been targeted by developers seeking to invest in onshore wind and marine generation projects.

On Lewis and Harris today, a total of 380MW of generation is either connected or contracted to connect in the future. There are further interests from Developers of renewable energy projects in excess of 200MW; Map 1: Proposed Western Isles Connection a mix of onshore wind, pump storage hydro and solar energy projects.

There is no spare capacity on the existing Western Isles network to connect additional generation. As a consequence, a higher capacity link to the Scottish mainland is proposed to facilitate export into the Great Britain Main Interconnected Transmission System (GB MITS).

SHE Transmission has detailed plans to construct a 158km 600MW HVDC link of which 81km are subsea and 77km are underground cable between Beauly on the Scottish mainland (located North West of Inverness) and Arnish on the east coast of the via Dundonnell on the west coast of Scotland.

Image: Example of “Cable float in”

03 Western Isles HVDC Link Consultation Western Isles HVDC Link Consultation

Project Overview

As the HVDC cable leaves land and enters the sea, it will either be routed via ducts that are created using a Horizontal Directional Drill or through a traditionally excavated trench. Once offshore the HVDC cable will be buried.

If the sub sea cable cannot be buried it will be protected by alternative methods, for example High Density Polyethylene Proposed marine works (HDPE) duct or rock placement. The subsea cable installation comprises: In addition to the subsea HVDC cables, the other key elements • Pre-lay survey of the Western Isles HVDC Link include: • Boulder clearance • Cable trenching • HVDC Converter station at Beauly and associated Civil works • Cable laying • HVDC Converter station at Arnish and associated Civil works • Cable burial • AC Substation at Arnish • Rock placement (where required) • Concrete mattressing • 77km of underground land cable from Dundonnell to Beauly (where required) • Armour cable (where required) • Post installation surveys

Convertor Convertor Existing Station & Subsea Station & Existing Network Underground Cable Underground Network Cable Cable

Arnish 81km 77km Beauly Sub Station Sub Sea Underground Cable Sub Station

AC Electricity HVDC Electricity AC Electricity

04 www.ssen-transmission.co.uk/projects/western-isles www.ssen-transmission.co.uk/projects/western-isles

Project Timeline

Nov 17

Submission of report to Marine Scotland to ensure agreement of topics to be included in the supporting environmental information. Statutory consultation undertaken by Marine Scotland as part of this process.

Sept 17 – Mar 18

Preparation of Environmental Report to support the Marine Licence and Marine Works applications.

2018

Feb: Receipt of scoping opinion report from Marine Scotland to confirm the requirements for the Environmental Report.

Mar: Pre-Application Consultation with the public on the preferred cable route corridor.

Mar: Consider and reflect on feedback from the consultation on the content of the Environmental Report.

Apr: Submission of Marine Licence application to Marine Scotland and Marine Works applications to Stornoway Port Authority.

Apr/May: Statutory Consultation – Marine Scotland will undertake statutory consultation following submission during which representations can be made directly to the relevant authority.

July/Aug: Determination of the Marine Licence and Marine Works applications.

2020

Subject to consents, commencement of construction works.

2023

Completion of construction works.

05 Western Isles HVDC Link Consultation Western Isles HVDC Link Consultation

Subsea Route Selection

SHE Transmission have developed the subsea cable route in a manner which balances economic, Environmental technical and environmental considerations, a route which is economically viable, technically feasible and SHE Transmission recognise that a major infrastructure project like the Western Isles HVDC Link can impact the environment, therefore capable of being granted consent. careful design and planning is required at every stage. Through careful evaluation, SHE Transmission will deliver effective protection measures within sensitive areas. Economic A key example includes how the Marine Protected How the HVDC cable is installed and the route it takes are key factors Area (MPA) will be protected. SHE Transmission has considered the informing the cost of the Western Isles HVDC Link. A straight-line physical disturbance to the designated habitats within the MPA, route theoretically presents the cheapest option; however, the changes in temperature in the immediate vicinity of the cable technical challenges and costs of transitioning the cable across and effects of smothering communities on the seabed. Given multiple seabed and land features would mean that this is not a the available information, SHE Transmission intends using cable viable solution. armouring in this area to minimise the impact on this sensitive marine environment. Additionally, the cable route has been moved slightly SHE Transmission’s preferred installation method for HVDC to the north to avoid the Shiant Banks Marine Protected Area (MPA). subsea cables is to bury them on the seabed. This method is the most common installation technique and is a proven method for protecting cables. In areas with thin sediment cover, or additional sea bed constraint, alternative means of protecting the cable on the seabed will be necessary. Covering cables with concrete mattressing is possible; however, due to the precise design requirements it is deemed to be relatively expensive, unsuitable for extensive lengths and subsequent maintenance of the cable can be complex. SHE Transmission is also considering placement of rocks to cover the cable. The placement is more economically efficient than installation of concrete mattresses and provides a high degree of protection. The final technique being considered, especially in sensitive marine habitats, is cable armouring where cables will be encased in a polymer casing and laid on the seabed. This option is costly; however, it reduces the requirement for burying, rock placement or laying of concrete mattresses.

SHE Transmission is looking at all options of cable protection along different sections of the cable route. Final decisions will be taken once detailed engineering design studies have been completed.

It is recognised that the sea area through which the proposed cable route passes is considered important for a variety of commercial fisheries activities, including shellfish (e.g. nephrops and scallop) and aquaculture. SHE Transmission is working with the relevant fishing organisations to ensure that possible disruption to fishermen operating in these areas is limited as far as practical.

Technical

There is a wide range of technical considerations; from cable size and capacity; connection to existing transmission infrastructure; to the method of installation which inform the routing process, with associated economic and environmental implications.

Technical considerations include cable installation and protection methods, which are more achievable in softer sediment. Avoidance of undulating seabed topography is preferred to minimise the possibility of free spans, where the cable is suspended above the seabed, which can lead to seabed scouring. It is also necessary to take account of the access to existing infrastructure at either end Map 2: Environmental designations along the proposed cable route. of the cable route.

06 www.ssen-transmission.co.uk/projects/western-isles www.ssen-transmission.co.uk/projects/western-isles

Subsea Routing Considerations

Sensitivity of Receptors Route options Receptors could be considered as any aspect of the environment, Determining the most appropriate route for the HVDC cable has both human and non-human which may be impacted upon involved consideration of several options. Following determination (positively or negatively). of the most efficient points to connect to the existing transmission infrastructure on Lewis and the Scottish mainland, the focus of our investigation centred on the area between Arnish on Lewis and Completion of a range of technical studies help us to establish what Dundonnell in Wester Ross. the most sensitive receptors are within the area, the likely impacts they may experience during the installation phases of the project Overall four routes between Lewis and Wester Ross have and the extent of these impacts. been considered during the development process: Examples of the likely receptors which could be impacted upon 1. A northern route connecting Arnish to Dundonnell via include, but are not limited to: Little (proposed option to be taken forward) • Seabed habitats and associated organisms 2. A southern subsea route connecting Arnish to Dundonnell • Marine mammals via Little Loch Broom (discounted due to proximity to Shiant Banks MPA) • Commercial fisheries and aquaculture • Shipping and navigation 3. A route connecting Arnish to Mungasdale via the east of , thus avoiding Little Loch Broom Impacts on receptors and the most effective means of mitigation (discounted due to presence of maerl) have been taken into consideration when selecting the most appropriate route for the subsea cable. 4. A route connecting Arnish with Mungasdale via the west of Gruinard Island, thus avoiding Little Loch Broom (discounted due to the presence of maerl) 5. Straight line route connecting Arnish to Dundonnell via Little Loch Broom.

Determining Suitability

Defining the route that is best economically, most technically achievable and with the least environmental impacts has been done by considering the constraints associated with each.

To understand these constraints, marine surveys have been undertaken to map the seafloor to provide a detailed understanding of the geology, seabed sediments and the flora and fauna it supports.

This information has been combined with data on other marine factors including fishing, shipping and the suitability of the seabed sediments for cable burial.

The combination of this information enables the development of the preferred subsea cable route. Map 3: Bathymetry along the proposed cable route. Map 4: Proposed cable routes

07 Western Isles HVDC Link Consultation Western Isles HVDC Link Consultation

Landfall Locations - Dundonnell

Key Considerations and Challenges Dundonnell The criteria used to identify a possible landfall location were: The proposed landfall location at Dundonnell has • Geology of seabed and coastline been selected, balancing a range of cost, technical and environmental factors. A key influence in determining this • Proximity to existing electrical infrastructure landfall was the proximity to the road network allowing for • Suitability of near shore seabed conditions the cable to be undergrounded along the existing road from Dundonnell to the proposed converter station at • Level of any commercial fisheries activities Beauly, Inverness-shire. • Presence of areas of cultural heritage • Presence of ecological features • Current use of the landfall location and surrounding areas • Ease of construction and operation • Any anticipated licensing obstacles

08 www.ssen-transmission.co.uk/projects/western-isles www.ssen-transmission.co.uk/projects/western-isles

Landfall Locations - Lewis

Key Considerations and Challenges Arnish The criteria used to identify a possible landfall location were: The proposed landfall location at Arnish has been selected, • Geology of seabed and coastline balancing a range of cost, technical and environmental factors. A key factor in determining this landfall was the • Proximity to existing electrical infrastructure proximity to the wider electrical network and the location • Suitability of near shore seabed conditions of the windfarm projects seeking connection to the grid. • Level of any commercial fisheries activities • Presence of areas of cultural heritage • Presence of ecological features • Current use of the landfall location and surrounding areas • Ease of construction and operation • Any anticipated licensing obstacles

09 Western Isles HVDC Link Consultation Western Isles HVDC Link Consultation

The Consulting Process

SHE Transmission will require a Marine Community Liaison Manager Licence from the Scottish Government Lisa Marchi-Grey as well as a Marine Works Licence from the Stornoway Port Authority. [email protected]

As part of the licence application procedure, SHE Transmission is preparing supporting environmental information which will 07825 015 507 describe the characteristics of the project and provide information on the possible environmental effects of the connection and how they will be managed. When completed this Lisa Marchi-Grey information will be available on the projects dedicated webpage Scottish and Southern www.ssentransmission.co.uk/projects/western-isles. Electricity Networks, 10 Henderson Road, The licensing procedures also require SHE Transmission to Inverness, IV1 1SN consult on its proposals. This exhibition forms part of the consultation process. www.ssen-transmission.co.uk/projects western-isles Scoping of the project has been undertaken with Marine Scotland. This ensures that focused and proportionate environmental information is produced to accompany the application, which addresses the specific requirements and potential effects. Information

Following advice from Marine Scotland (and consultees), the Information will also be made available via the project possible effects of the installation and operation of the subsea web page and social media channels: cable will be considered along with the possibility for cumulative effects where there is potential for effects to overlap with other Project Website: marine and coastal developments. www.ssen-transmission.co.uk/projects/western-isles The following topics will be covered as part of the supporting environmental information: Find us on Facebook: • Designated sites SSEN Community • Benthic ecology • Marine mammals Follow us on Twitter: • Commercial fisheries and aquaculture @ssencommunity • Shipping and navigation

Comments made are not representations to the Scottish Ministers. If SHE Transmission plc submits an application for a marine licence to Scottish Ministers, an opportunity will be given for representations to be made to the Scottish Ministers on the application.

10 www.ssen-transmission.co.uk/projects/western-isles www.ssen-transmission.co.uk/projects/western-isles

Your comments

We are keen to receive your views and comments in regards to the following questions: Please complete in BLOCK CAPITALS. (Please tick one box per question only)

Q1 Do you understand the need for the Western Isles HVDC Link project?

Yes No Unsure

Q2 Has the consultation information been clear and easy to understand?

Yes No Unsure

Q3 Do you have any comment on how the subsea cable route and landfall locations have been selected?

Comment

Q4 Do you understand the consenting process that SHE Transmission will follow for the Western Isles HVDC Link?

Yes No Unsure

Q5 Do you have comments on the proposed scope of the additional environmental information being prepared to accompany the marine licence application? Comments

11 Western Isles HVDC Link Consultation Q6 Do you have any other comments that SHE Transmission should consider as it progresses the Western Isles HVDC Link?

Comments

Please write in any further comments you would like to make about the engagement process as a whole.

Full name

Address

Postcode

Telephone

Email

If you would like to be kept informed of progress on the project please tick this box.

If you would like your comments to remain anonymous please tick this box.

Thank you for taking the time to complete this feedback form. Please hand your completed form in at the event or alternatively by one of the methods below: Post: Lisa Marchi-Grey, Scottish and Southern Electricity Networks, 10 Henderson Road, Inverness, IV1 1SN Email: [email protected]

Closing date for feedback is 16:00, Friday 30th March 2018 The feedback form and all information provided at the event can also be downloaded from the dedicated website: www.ssen-transmission.co.uk/projects/western-isles

Any information given on the feedback form can be used and published anonymously as part of Scottish and Southern Electricity Networks consultation report. By completing this feedback form you consent to Scottish and Southern Electricity Networks using feedback for this purpose.