Kent Roberts, Schwabe, Williamson and Wyatt

Total Page:16

File Type:pdf, Size:1020Kb

Kent Roberts, Schwabe, Williamson and Wyatt 16th Biennial National Harbor Safety Committee Conference Hylebos Waterway Sunken Rock Barge Kent Roberts Schwabe, Williamson and Wyatt Portland/Seattle/Vancouver Port of Tacoma Hylebos Waterway at Tacoma Upper End Hylebos Waterway Schnitzer Steel Recycling Metals Export Terminal Schnitzer Steel Terminal Buffelin Turn Hylebos navigation channel • 200’ wide navigation channel • USACE maintained at 30’ MLLW • “38’ Channel” = Ship drafts at high tide to 35’ with 3’ under keel clearance Channel widens to 250’ at Buffelin Turn – Walrath Dock Walrath Trucking Sound Rock Products SeaLevel Bulkhead Builders, Inc. SeaLevel Bulkhead Builders, Inc. November 6, 2016 SLBB Rock Barge “COMPLIANT” 145 x 45 x 11 steel deck barge Built 1966 Rock Barge Load • 235 Excavator • 2 loading ramps • 350 tons 6-man granite rock 6-man rock = 6,000 – 8,000 lbs outer dimensions 54” to 60” Value approx. $4600 Rock Barge, morning of Nov. 6 Sunken Rock Barge Salvage Plan • Global Diving & Salvage November 11, SLBB Rock Barge Wreck Removal • Detailed plan to refloat and remove the Rock Barge. • Detailed plan for pre-removal and post removal sediment sampling to confirm contaminated sediments not spread/exposed. Commencement Bay Superfund Site • In 1983, EPA put Commencement Bay on its “Superfund” list as the Commencement Bay Nearshore/Tide Flats site. • Decades long clean-up effort with ongoing monitoring. • 2 of 9 sediment sites of highest concern in Hylebos Waterway. Commencement Bay Superfund Site • 2014 EPA/USACE site assessment determined not to dredge Buffelin Turn upslope due to natural, clean sediment capping of subsurface contaminated sediments. Barge Removal Salvage Plan • “The 6-man rock cargo from the submerged barge was located offshore and embedded into the mud with less than 3.5 extending above the mud ( 25 feet below MLLW). In most cases, the rock extends only 1 foot above the mud line.” • Salvage plan is to remove Rock Barge only. Removal of rock cargo not addressed. Salvage plan - rock debris field Puget Sound HSC - 12/2/15 • USACE written report item: “Hylebos Waterway - A rock barge sank at the Walrath pier on November 6th. The barge is resting approximately 20 to 30-feet into the channel. Salvage operations are underway, but have been hampered by difficulties stringing the lifting straps under the barge.” December 2, 2015 (from Corps link) Barge removal complete Dec. 6 January 26, 2016 • Puget Sound Pilots to USCG: • “For the reason of the barge capsizing and spilling four- man rock at the Sound Rock facility, the Hylebos waterway is compromised … no longer accessible for the historical deeper drafts transited. We have approximately 100 transits annually, each one of these transits will be impacted by a lesser draft of ±2.5 feet. • …. a negative impact on loaded outbound ships. Puget Sound Pilots feel this area should be restored to its original depth… . Puget Sound HSC Feb. 3, 2016 USACE - “Hylebos Waterway-The rock barge that sank at the Walrath pier was refloated on 06 December and removed from the waterway. February 22-27 - M/V TEAM HOPE • Schnitzer Steel voyage chartered based on up to 35’ channel depth • Should have sailed at 34.4’ • Pilot draft restriction – sailed at 32.55’ • 33,856 MT – 30,932 MT = 2924 MT not shipped • $540,000 lost sale opportunity • Charter deadfreight claim Schnitzer squeels! • March 4 letter to the world re M/V Team Hope impact • Every foot of draft reduction = $275,000 lost sale opportunity • March 14 meeting USCG/USACE/Pilots • USCG declared rocks impediment to navigation 33 CFR 245.20 • USCG placed AIS racon chart marker • Schnitzer orders new high resolution survey Puget Sound HSC, April 6 • Coast Guard Sector Puget Sound Report • “a virtual aid was put in at the Hylebos where the rocks are at the bottom. [HSC member] asked if there was a plan on the Coast Guard side to do anything beyond adding the virtual aid to that area? No decision to remove the rocks has been made by the USACE or the Coast Guard but a new survey is coming out in April. April - May • Puget Sound Pilot increase draft restriction to 3.5’ (Max high tide ship draft = 31.5’) • Schnitzer, TPT, Port of Tacoma demands to SLBB to remove rocks • April 16 – M/V LOCH MELFORT • April 22 – M/V LAKE DANY • TPT log export ship • May 16 – M/V HOIHOW May 11 – USACE letter to SLBB • Rivers and Harbors Act, Section 10 permit required for work affecting navigable waters. • Clean Water Act, Section 404, permit required for discharge of fill material – request for voluntary action • May 13 – Schnitzer 60-day notice of intent to sue – violation of Clean Water Act Sections 301(a) and 404 Lawsuit Filed May 6, 2016 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT TACOMA In the Matter of the Complaint Case No. 3:16-CV-05340- RBL of Northwest Rock Products, PETITIONERS' COMPLAINT Inc., as owner, and Sealevel FOR EXONERATION Bulkhead Builders , Inc., as FROM OR LIMITATION OF charterer, of the barge LIABILITY COMPLIANT, Official No. 505016, for Exoneration from or L Limitation of Liability, Plaintiff. Rock removal efforts • USACE gives SLBB June 10 deadline to submit removal plan • June 16 USACE approves SLBB rock removal plan, must complete work w/in 30 days • Remove all rocks standing proud of background sediment level Limitation of liability 60 day claim deadline - July 6 • In June, not clear rocks would be removed or draft restriction lifted • Claims filed based on financial losses already occurred, and future financial losses if draft restriction not removed • Clean Water Act violations, nuisance, trespass • Reduced property value - waterfront land on 31.5’ channel vs. 35’ channel Walrath Marine • Dock owner claim for loss of use of facilities, lost sales opportunities • $68,068 to date United States of America • Obstruction of navigation, Violations Of Rivers & Harbors Act and Clean Water Act • (amount of claim not stated) TPT U.S. Limited • Increased shipping cost/lost sales to date: $116,000 • increased future rent/penalties - Lease rate with Port based in part on meeting minimum volume throughputs for log exports. Schnitzer Steel Industries • Increased shipping costs, lost sales opportunities and deadfreight claims to date: $935,844 • Reduced property value for Schnitzer terminal: $1,690,000 • Clean Water Act penalties: $37,000 per day • Future shipping cost impacts: Unknown Port of Tacoma/Northwest Seaports Alliance • Loss of revenue – throughput based rent and wharfage: $1,288,653 • Diminution in property value for Port owned terminal property on Hylebos waterway: $30,196,000 Takeaways • Communication and collaboration – HSC can lead and coordinate • Communicate and analyze “deeply” – How might SLBB’s decision to leave rocks affect all aspects of the waterway? • Beware of mission “blinders” • Encourage more industry partner involvement • Time is money Thank you! .
Recommended publications
  • The Commencement Bay Superfund Legacy: Collaboration, Restoration and Redevelopment in the Local Landscape
    University of Puget Sound Sound Ideas Summer Research 2010 The ommeC ncement Bay Superfund Legacy: Collaboration, Restoration and Redevelopment in the Local Landscape Jenni Denekas University of Puget Sound Follow this and additional works at: http://soundideas.pugetsound.edu/summer_research Recommended Citation Denekas, Jenni, "The ommeC ncement Bay Superfund Legacy: Collaboration, Restoration and Redevelopment in the Local Landscape" (2010). Summer Research. Paper 51. http://soundideas.pugetsound.edu/summer_research/51 This Presentation is brought to you for free and open access by Sound Ideas. It has been accepted for inclusion in Summer Research by an authorized administrator of Sound Ideas. For more information, please contact [email protected]. The Commencement Bay Superfund Legacy: Collaboration, Restoration and Redevelopment in the Local Landscape Jenni Denekas 2010 Arts, Humanities and Social Sciences Summer Research Grant Recipient I. Introduction Commencement Bay has a long history of industrial development, which has leant Tacoma its moniker “City of Destiny” as well as its notoriety as the home of the “Tacoma aroma.” This development has also shaped Tacoma’s current shoreline and overall appearance. Originally, the shoreline was primarily an expanse of tideflats and estuaries, with large shellfish and seabird populations and important salmon habitat. The tideflats have for thousands of years supported tribes such as the Puyallup, and more recently the region’s abundant natural resources and the deep waters of the bay enticed Western settlement. In spite of the 1854 Treaty of Medicine Creek, which supposedly granted the Puyallup the rights to the tideflats at the mouth of the Puyallup River, development by Western settlers quickly overtook the local landscape.
    [Show full text]
  • Consent Decree
    1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WASHINGTON 9 t0 UNITED STATES OF AMERICA, ) ) CIVIL ACTION NO. 11 Plaintiff, ) ) v. ) 12 ) F.O.F INC, ) 13 ) ¯HYLEBOS WATERWAY ) PROBLEM AREAS 14 ) Defendant. ) 15 ) 16 17 TABLE OF CONTENTS 18 A. BACKGROUND .......................................................................................... ........................3 19 B. JURISDICTION ................................................................. ...................................................8 20 C. PARTIES BOUND ...............................................................................................................8 21 D. STATEMENT OF PURPOSE ..............................................................................................8 22 E. DEFINITIONS .....................................................................................................................9 23 F. PAYMENT ..........................................................................................................................13 24 G. FAILURE TO COMPLY WITH CONSENT DECREE ...................................................;I7 25 H. CERTIFICATION OF SETTLING DEFENDANT AND C()NSENT DECREE United States Department of Justic Commencement Bay Nearshore/Tideflats Environment and Natural Resources Divisior Superfund Site Environmental Enforcement Sectior P.O. Box 7611 Page 1 of 25 Ben Franklin Statior Washington, D.C. 20044-761 1 SETYLING FEDERAL AGENCIES ............................................................................19
    [Show full text]
  • I-5/Port of Tacoma Road Interchange Improvement Project Fife, Washington
    2020 BUILD Grant City of Fife I-5/Port of Tacoma Road Interchange Improvement Project Fife, Washington Submitted to May 2020 US Department of Transportation Washington, DC 20590 2020 BUILD Application May 18, 2020 Secretary Elaine L. Chao U.S. Department of Transportation Office of the Secretary of Transportation 1200 New Jersey Avenue, SE Washington, D.C. 20590 Dear Secretary Chao: The City of Fife is pleased to submit this FY 2020 Better Utilizing Investment to Leverage Development (BUILD) grant application for Phase II of the I-5/Port of Tacoma Road Interchange Improvement Project (Project). This Interchange Improvement Project completes this phase of a transformational effort by the City of Fife, the Port of Tacoma, and The Washington State Department of Transportation to address significant backups at this interchange and to dramatically improve the movement of freight and goods as well as traffic in general. The Project includes road, intersection, and intersection improvements at the I-5/Port of Tacoma Road interchange that will greatly enhance a critical connection to the Port of Tacoma, which combines with the Port of Seattle to form the fourth largest gateway for containerized cargo in our nation. This $25 million in requested investment will leverage $24.65 million secured local and state matching funds already allocated to fully fund Phase II of the I-5/Port of Tacoma Road Interchange Improvement Project, making federal FY 2020 BUILD funds the last dollars needed to expeditiously complete design and begin construction. Additionally, the City of Fife has already fully funded Phase I of the Project ($44.6 million) which is 80% complete.
    [Show full text]
  • DRAFT Port of Tacoma Northwest Ports Clean Air Strategy Implementation Plan
    DRAFT Port of Tacoma Northwest Ports Clean Air Strategy Implementation Plan Produced by The Port of Tacoma July 8, 2021 1 Executive Summary: PLACEHOLDER PLACEHOLDER 2 Table of Contents: PLACEHOLDER PLACEHOLDER 3 Glossary: PLACEHOLDER PLACEHOLDER 4 1. Purpose Improving air quality and reducing impacts on climate change are key priorities for the Port of Tacoma (PoT) and as such, it has been a partner in the Northwest Ports Clean Air Strategy (NWPCAS) since its inception in 2008. The NWPCAS is a voluntary collaboration between the PoT, Port of Seattle (PoS), The Northwest Seaport Alliance (NWSA) and Port of Vancouver (VFPA) to reduce and ultimately eliminate air pollutant and greenhouse gas (GHG) emissions from seaport activities in the Puget Sound-Georgia Basin Airshed. The NWPCAS constitutes a shared strategic framework for clean air and climate actions and investments that creates a “level playing field” across the four participating port entities, and helps them coordinate, collaborate, and hold each other accountable. The participating ports completed a renewal of the NWPCAS in 2020, continuing their commitment to work jointly to reduce air pollution and climate impacts. The 2020 NWPCAS puts forth an aggressive, aspirational joint vision to phase out emissions from seaport activities by 2050, supported by a suite of high-level joint objectives and actions. Given that each port exists in a unique policy environment, has different lines of business, and different community interests, there is a need for flexibility in how the ports individually implement the NWPCAS. Therefore, each port has committed to developing an Implementation Plan that details the individual actions they will take to work towards the NWPCAS vision and objectives.
    [Show full text]
  • Profiles of Top U.S. Agricultural Ports, 2017 Update, Tacoma, Washington
    Export/Import Profile Tacoma, WA he Port of Tacoma, WA, is located in the northwest region of the U.S. West Coast. In August 2015, the ports of Seattle and Tacoma, WA, formed the Northwest Seaport Alliance. The Alliance unified the two ports’ marine cargo terminal investments, operations, planning and marketing to Tstrengthen the Puget Sound gateway and attract more marine cargo to the region. Over 1,900 vessels called the port alliance terminals in 2017 moving more than 27.5 million metric tons of total cargo including more than 3.7 million twenty-foot equivalent units. Exports In 2017, the Port of Tacoma ranked 3rd in the nation for total waterborne agricultural exports and 4th for containerized waterborne agricultural exports. The port moved more than 7.4 million metric tons of agricultural export cargo in 2017. Approximately 59 percent of these products moved in bulk vessels. Grain products, soybeans, and animal feed accounted for about 80 percent of the port’s agricultural exports. The top shipping lines were Blue Water Shipping Co. and Evergreen, which together moved approximately 62 percent of the port’s agricultural export cargo. The top destination markets were China, Japan, South Korea, and Taiwan which accounted for more than 90 percent of agricultural exports through Tacoma. U.S. Waterborne Agricultural Exports Through Tacoma, WA, 2017 Containerized 41% Bulk 59% Source: IHS Markit/PIERS 1 Photo Credit: Port of Tacoma U.S. Waterborne Agricultural Exports Through Tacoma, WA, 2017 Dry 85% Refrigerated 15% Source: IHS Markit/PIERS U.S. Waterborne Agricultural Exports Through Tacoma, WA, 2017 Commodity Metric Tons Share U.S.
    [Show full text]
  • FAST Corridor Brochure
    April 2006 The FAST Partnership helps move our economy. Don Wilson, Port of Seattle Don Wilson, Port of Seattle Since 1998, a coalition of public and private partners in the Puget Sound maritime freight gateway has leveraged $568 million of public and private funding for strategic freight mobility infrastructure improvements. Another $300 million is needed to complete the remaining 16 of the 25 most important FAST Corridor projects. FAST Corridor Keeps the Puget Sound Gateway Open As one of the West Coast’s largest Pacific Rim trade hubs, the Puget Sound ports of Tacoma, Seattle and Everett link worldwide suppliers and markets. Washington State and the entire nation depend on the ability of the highways and rail lines in the Puget Sound gateway to move goods for retail, industrial and agricultural sectors. FAST Vision & Goals Each of the FAST Corridor partners works to achieve a common freight mobility vision. That vision integrates local and regional transportation system improvements along mainline rail lines and truck corridors near ports in the central Puget Sound region. These projects move international maritime and domestic trade, while supporting Puget Sound’s economy and locally mitigating the impact of freight that benefits other parts of the country. The FAST Corridor’s goals are to: Improve the func- Eliminate choke- Provide safe rail Establish reliable tionality, capacity and points where railroad crossings and reliable truck links between connectivity of the and arterial networks emergency access for ports, railroad intermo- mainline rail system. intersect. local communities. dal yards and regional distribution centers. The FAST Corridor public-private partnership was established to move needed goods and support port operations on the highways and rail lines that sustain the maritime international trade corridor through the Puget Sound region.
    [Show full text]
  • Resolution No. 3283
    RESOLUTION NO. 3283 A RESOLUTiON of the Port Commission of the Port of Seattle authorizing the Executive Director to enter into a Memorandum of Understanding among the pnncipal parties of the Freight Action Strategy for the Seattle-Tacoma (FAST) Corndor for the purpose of setting out the mutually agreed upon steps along the Tacoma-to-Everett rail corndor and to assist the Port of Seattle in its plans to meet its share of the program's costs and responsibilities WHEREAS, the assurance of continued freight and passenger mobility throughout the Puget Sound is an issue of critical stategic importance to the Port, and WHEREAS, projected growth in cargo volumes and the implementation of commuter rad service by the Central Puget Sound Regional Transit Authonty are expected to generate more tiequent mainline rail traffic, with a projected increase in traffic congestion at many of the at-grade crossings along major artenals: and WHEREAS, representatives of the Port of Seattle, the Washington State Department of 'Iranuprtation, the Puget Sound Regional Councii, the ports of Tacoma and Everett, King County, Pierce County and Snohomish County, The Burlington Northern Santa Fe Railway Company, the Union Pacific Railroad Company, and the cities of Tacoma, Puyallup, Sumner, Pacific, Algona, Auburn, Kent, Renton, 7 ukwila, Seattle and Everett, all located along the Everett-Seattle--1acoma corridor, have reached consensus and recommended the projects shown in Attachment A to Exhibit A of this Resolutron as an "immediate prionty" program of projects that
    [Show full text]
  • OIL and LIQUEFIED FOSSIL FUELS Presentation
    Agenda Item D-2 City of Tacoma Planning and Development Services To: Planning Commission From: Stephen Atkinson, Planning Services Division Subject: Tideflats and Industrial Land Use Regulations Meeting Date: February 3, 2021 Memo Date: January 27, 2021 Action Requested: Select a regulatory option for Heavy Industrial Use Category 5 “Oil, or other liquefied or gaseous fossil fuel terminals, bulk storage, manufacturing, production, processing or refining of oil or other liquefied or gaseous fossil fuels;” release draft exhibits for public review and comments; and set a public hearing on March 3, 2021 at approximately 5:30 PM, and accepting public comments through close of business on March 8, 2021. Discussion: At the Planning Commission’s meeting on February 3, 2021, staff will present a summary of pertinent policies and area-wide context that apply specifically to the discussion of oil and other fossil fuel production facilities currently located in the Port of Tacoma Manufacturing and Industrial Center. The attachments include a review of Comprehensive Plan policies, the Magnuson Amendment, the Washington State Oceanic Resources Management Act, Tacoma City Council Resolution No. 40509 declaring a climate emergency, and information regarding local, regional, and state greenhouse gas emissions targets. Staff is seeking Planning Commission direction on a preferred code option to develop for release for public review and comment. Key issues to address in order to release a draft code exhibit include: 1. Differentiating fossil fuel production facilities and renewable fuel production facilities; 2. Expansion of existing facilities; 3. Conditional use criteria for new or expanded fossil fuel or renewable fuel facilities, including greenhouse gas mitigation, fuel transfer reporting requirements, bonding, spill management plans, and mitigation sequencing for impacts to environmental, social, and economic resources, including tribal fishing rights.
    [Show full text]
  • Port of Everett Short-Sea Shipping Project Designation Puget Sound Container on Barge Service June 2018
    Port of Everett Short-Sea Shipping Project Designation Puget Sound Container on Barge Service June 2018 Ms. Lauren Brand, PPM Associate Administrator Intermodal Systems Development US DOT/Maritime Administration 1200 New Jersey Avenue, SE Washington, DC 20590 Dear Ms. Brand: The Port of Everett is pleased to submit the following request for Project Designation for an expanded marine highway service along the M-5 corridor. The project will enable the Port to create a new marine highway service along the M-5 marine highway connecting Everett to Northwest Seaport Alliance (NWSA) terminals in Seattle and Tacoma. The Port of Everett is currently in the final stages of modernizing its South Terminal to handle post-panamax ships in support of Boeing’s new 777X program. The marine highway service was initiated in 2004 when the State of Washington, the Boeing Company, the Port of Everett, the City of Everett, and Snohomish County entered into the Project Olympus Agreement to retain, and grow, Boeing’s aerospace manufacturing in Washington State with the construction of Mount Baker Terminal. The Port has successfully demonstrated the cost effectiveness and reliability of using barge service to move aerospace containers from their main facility (in Port Gardner Bay) to their Mount Baker terminal. At Mount Baker, the containers are lifted by a rail-mounted gantry crane onto rail cars for final delivery to the plant. The Port will continue to use their proven container-on-barge (COB) service to support Boeing manufacturing presence in Washington. Based upon the success of the aerospace COB model, there is additional interest in a non-aerospace COB service to the NWSA terminals because of curtailments in direct ocean service and traffic congestion in the Puget Sound Region.
    [Show full text]
  • Piers 24 & 25 Marine Sediment Remediation Challenges And
    Paper D-39, in: E.A. Foote and A.K. Bullard (Conference Chairs), Remediation of Contaminated Sediments—2011. Sixth International Conference on Remediation of Contaminated Sediments (New Orleans, LA; February 7–10, 2011). ISBN 978-0-9819730-3-6, Battelle Memorial Institute, Columbus, OH. www.battelle.org/sedimentscon Piers 24 & 25 Marine Sediment Remediation Challenges and Solutions, Tacoma, Washington Richard F. Moore ([email protected]) and Gary E. Horvitz (Hart Crowser, Seattle, Washington, USA) William D. Evans ([email protected]) (Port of Tacoma, Tacoma, Washington) ABSTRACT: The Port of Tacoma completed a multiphase marine construction project between October 2007 and February 2008 to remediate approximately 3 acres (1.21 hectares) of contaminated intertidal and subtidal sediments along rocky marine shoreline areas. The sediments were near the mouth of the Hylebos Waterway and in a portion of Com- mencement Bay in Tacoma, Washington. The work was completed as a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) lead project. Sediments were contaminated with metals, polychlorinated biphenyls (PCBs), and poly- cyclic aromatic hydrocarbons (PAHs) associated with historical shipyard operation, vessel repair, and related marine activities. Remediation included removal of fused metallic debris piles from intertidal and subtidal embankment slopes, followed by difficult under- pier capping, subtidal dredging, and embankment excavation. Construction was compli- cated by limited access to under-pier work areas, winter tidal conditions, and embank- ment stability concerns. Construction also required coordination with concurrent pier repair and piling replacement work during much of the project. Adaptive engineering and construction approaches succeeded in overcoming these challenges, leading to the achievement of project regulatory and design goals.
    [Show full text]
  • Puget Sound Ports: Creating Jobs, Creating Opportunities
    Puget Sound Ports: Creating jobs, creating opportunities Puget Sound Trade Port of Seattle Located on Puget Sound in the state of The Port of Seattle is located closer to Asia than Washington, are our member ports: Port of any other U.S. port. Seattle, Port of Tacoma, Port of Skagit, and the Port of Port Angeles. These four ports Quick facts: PNWA’s Puget encompass many of the economic activities The Northwest’s largest container handling Sound port that are important to the state of Washington: complex cargo, freight, tourism, and shipping. One out members promote Eighth busiest U.S. seaport in dollar volume of three jobs in the state of Washington is economic and TEUs related to international trade, making it the development in The Port generates nearly 195,000 jobs most trade-dependent state in the nation. their communities, throughout the region with payroll in excess the Northwest, and of $6.8 billion While Washington represents about 2% of the the nation nation’s population, its ports handle 7% of all Products valued at $36 billion cross the U.S. exports and receive a 6% share of the Port's docks each year nation’s imports; making Washington the 3rd $626 million in local and state taxes were largest exporting state in the U.S. Together, generated by Port activities in 2003 the Port of Seattle and the Port of Tacoma are Oversees 1,500 acres of moorage and cargo the second largest container load center in the -related facilities country, second only to Los Angeles/Long 26 regularly scheduled container steamship Beach and ahead of New York/New Jersey.
    [Show full text]
  • Port of Tacoma 2021 Budget
    Port of Tacoma 2021 Budget Weigh Anchor Statutory Budget and Tax Levy adopted: November 19, 2020 The Port of Tacoma has been a recipient of the Government Finance Officers Association (GFOA) award every year since 2005. It reflects the commitment of the Port and its staff to meeting the highest principles of governmental budgeting and is valid for a one-year period. To receive this award, the Port satisfied nationally recognized guidelines for effective budget presentation. Port of Tacoma 2021 Budget Table of Contents Memo from Eric Johnson, Executive Director ............................................................................................................ i Budget Document Overview ....................................................................................................................................... ii I. Port of Tacoma Overview ................................................................................................................................ I-1 II. Budget Message .............................................................................................................................................. II-1 III. Business Outlook ........................................................................................................................................... III-1 IV. Operating Budget ........................................................................................................................................... IV-1 V. Capital Investment Plan .................................................................................................................................
    [Show full text]