East Line Phase 2

Project Background Line Phase 2 The East London Line Project Phase 2 (ELLP2) has resulted in a south- Client western branch from Quays to Junction via Rye, and Road. This new orbital route has Location saved significant journey times and provide an essential new strategic London, UK transport link for London.

Start Date Phase 2, followed on from ELLP1 which started operation in May 2010, 2008 with the extension of services to , Crystal Palace and West

Croydon. End Date 2012 The extension of the East London Line is estimated to increase usage

of the passenger transit capacity from 10.4 million to about 35.4 million Duration annually, with around 50 million passengers expected to use the line 48 months after the completion of the second phase. Contract Value £26m The 4 year project formed the final link in the Mayor’s strategy to promote orbital rail travel, reducing need for interchange and reducing Services Provided congestion at termini. Signalling, train control and telecoms, track/permanent way and programme management

For more information please visit www.networkrailconsulting.com Scope of Works Key Project Outputs The scope of the works on this project extending the Global System for The key outputs of this project were: included: Mobile Communications - Railway a new passenger service of 4 trains (GSM-R) coverage to new constructing a new double junction per hour in each direction, calling Silwood Lines. controlled from Area at all intermediate stations and Signalling Centre (ASC), to provide a converting Platform 2 in to two terminating in the new platform connection to Rail for London’s (RfL) separate 4-car platforms 2 at Clapham Junction East London Line re-modelling the track better integration of rail services carrying out associated track, with other modes of transport re-configuration of signalling to structures, power and signalling works suit the new layout involving a improve access between East modifying Supervisory Control changeover of over 2500 wires to and South-West London And Data Acquisition (SCADA) to correctly re-control the new layout provide additional capacity to enable electrical power control from and its new functionality accommodate growing demand. Electrification Control installing a facing crossover Room (ECR) The project provided a strategic orbited doubling a section of track. rail ink for London in time for the London 2012 Olympics. The project was however, designed to provide long term capacity, accessibility and economic benefits.

For more information please visit www.networkrailconsulting.com