<<

JOB STORY

By Carol Shobrook CATCHING WAVES IN

38 Pile Buck Magazine | Vol.35 No.6 2019 | pilebuck.com JOB STORY

One of first thing you notice at the Marina is the spectacular backdrop, which includes lower , the historic Brooklyn Bridge and the . The park opened to the public in 2010 with docks, service, upland areas, and a private marina. However, boats in the marina were up against a particularly challenging site condition: Large wakes caused by vessel traffic rounding , the ‘Cape Horn’ of , as it is has come to be called by the crew at JT Cleary.

40 Pile Buck Magazine | Vol.35 No.6 2019 | pilebuck.com JOB STORY

hen the existing break- Since Brooklyn Bridge Park is a public placement, fendering, ballasting and water near the entrance recreational area, all work had to be monitoring by JT Cleary personnel, to the marina proved performed from a crane barge to ensure due to the rough wave action in the insufficient to protect the safety of pedestrians. Extreme care area. When the new attenuator barges boats in the marina, the was taken not to induce vibrations in arrived in 2019, JT Cleary installed marina owners decided the Interborough Rapid Transit (IRT) 5,000 linear feet of anchor piles Wto calm the waters by installing a 10-foot tunnels running below the marina. through the new barges. deep, floating wave attenuator. This As an immediate and temporary Using its barge-based Liebherr would be accomplished with three bal- measure, JT Cleary placed two of its LR1300 crane and a vibratory hammer, lasted barges, running the full 655 linear 54ft μ 250ft barges inshore of the exist- JT Cleary drove the 140ft long μ 36in feet of the current breakwater and se- ing breakwater, while the permanent μ 1in steel pipe pile, fabricated by JD cured with anchor piles. JT Cleary was sea barges were outfitted and towed Fields. An impact hammer was used selected to complete the project, which to New York from Alabama. Even the for a final few piles. Ancillary work was done in two phases. temporary barges required meticulous included construction of a gangway,

42 Pile Buck Magazine | Vol.35 No.6 2019 | pilebuck.com JOB STORY

44 Pile Buck Magazine | Vol.35 No.6 2019 | pilebuck.com JOB STORY

railing, fire standpipe and fencing at the docks, and removal and repositioning USING ITS BARGE-BASED LIEBHERR LR1300 CRANE AND of concrete docks and existing floating attenuators. A VIBRATORY HAMMER, JT CLEARY DROVE THE 140FT JT Cleary’s President, Jim Cleary, LONG X 36IN X 1IN STEEL PIPE PILE, FABRICATED BY JD noted, “Precision and delicacy were FIELDS. AN IMPACT HAMMER WAS USED FOR A FINAL needed near the IRT tunnels. Our crews closely monitored the placement of the FEW PILES. ANCILLARY WORK INCLUDED CONSTRUCTION piles, while crews inside monitored the OF A GANGWAY, RAILING, FIRE STANDPIPE AND FENCING tunnels for vibration tolerances.” The AT THE DOCKS, AND REMOVAL AND REPOSITIONING OF project creates a safer and calmer home for boats in one of New York’s most CONCRETE DOCKS AND EXISTING FLOATING ATTENUATORS. beautiful waterfront parks.

46 Pile Buck Magazine | Vol.35 No.6 2019 | pilebuck.com