Wiltshire Highways Maintenance Programme 2021/22

Trowbridge Area Board

CURRENT CONDITION BY AREA BOARD TOTAL % OF THE ADOPTED NETWORK REQUIRING MAINTENANCE

AB and C Roads requiring treatment 2018/19 5 year average red and amber requiring treatment 2019/20 5 year average red and amber ABC road 2020/21 5 year average red and amber ABC road 40

35

30

25

20

15

COMPLETE NETWORK abcu 19/20 abcu 20/21 35.00 30.00 25.00 20.00 15.00

A 5 year average is used to monitor the condition of the network due to the surveying regime of undertaking a 50% network length

The graphs show that even with a deteriorating network the targeted maintenance schemes are generally improving the overall condition of the roads within , a rolling 5 year programme and funding process is designed to allocate resources to those areas with a higher percentage of poor roads based on their network length. The target is for all area boards to be at the same low level of around 20% of the network requiring some form of maintenance

Spend profile

Trowbridge Trowbridge Cumulative

Annual spend Spend 5 years Trowbridge Annual spend 2021/22 £630,368 £630,368 Trowbridge Cumulative Spend 5 years 2022/23 £476,916 £1,107,284 £3,500,000 2023/24 £609,000 £1,716,284 2024/25 £550,000 £2,266,284 2025/26 £605,000 £2,871,284 £3,000,000 total £2,871,284 £2,500,000 £3,376,918 average 5 year Wiltshire area board budget

£2,000,000

CONDITION 5-year average red and £1,500,000 amber requiring treatment

Wiltshire Trowbridge £1,000,000 AB and C roads 2018/19 33.5 24.9 AB and C roads 2019/20 32.57 26.57 £500,000 AB and C roads 2020/21 31.90 26.30 2019/20 Unclassified 18.50 10.60 £0 2021/22 2022/23 2023/24 2024/25 2025/26 2020/21 Unclassified 18.60 10.60

Some schemes have been postponed due to covid issues, i.e. if they are on the route to a vaccination centre or to a key industrial area, these works have been moved to 2022/2023, potential budget issues may mean they are delayed for longer

The following pages detail the schemes that have been considered in the 5year plan,

Road lifecycle number General description Description from Description to Treatment Length Year number WYNSOME STREET, GOOSE STREET, BRADLEY A363 WESTBURY ROAD C234 / C277 TROW_19_0003 ROAD, SOUTHWICK ROAD, WESTBURY ROAD A361 FROME ROAD PATCHING 2021/22 ROUNDABOUT PHASED OVER 3 YEARS MORTIMER STREET, TROWBRIDGE (INC C361 TROW_20_0003 LONGFIELD ROUNDABOUT END / NEWTOWN SURFACING 360 2021/22 SPURS TO CH) ROUNDSTONE / A361 TROW_20_0004 COUNTY WAY RD RBT SURFACING 331 2021/22 FIRESTATION RBT

UC TROW_21_0001 MAPLE GROVE, TROWBRIDGE COLLEGE ROAD END INC LAUREL GROVE SURFACING 286 2021/22

UC TROW_21_0002 COURT STREET, TROWBRIDGE CASTLE ST RBT END INC MILL STREET SURFACING 260 2021/22 MICRO UC TROW_21_0003 CARISBROOKE CRESCENT, TROWBRIDGE FROM WYKE ROAD JUNCTION TO END OF CUL-DE-SAC 76 2021/22 ASPHALT

UC TROW_21_0005 KINGS GARDENS HILPERTON FROM WYKE ROAD JUNCTION TO END OF CUL-DE-SAC SURFACING 165 2021/22

SURFACE C217 TROW_21_0007 WESTWOOD RD TROWLE FROME ROAD A363 COCKHILL 2750 2021/22 TREATMENT SURFACE A361 TROW_21_0008 HILPERTON ROAD ROUNDSTONE RABT HILPERTON BYPASS RBT 1230 2021/22 TREATMENT UC TROW_21_0009 UNION STREET TIMBRELL STREET THE HALVE JCT SURFACING 100 2021/22 MICRO UC TROW_21_0010 HORSE ROAD HILPERTON WYKE ROAD B3105 MARSH ROAD 710 2021/22 ASPHALT SHAILS LANE HILL ST WICKER HILL PART 2020/21 B3106 TROW_24_0001 A363 SHIRES ROUNDABOUT JCT MANLEY LANE SURFACING 460 B3106 FROM A363 MAY REQUIRE PHASING 2021/22

MICRO UC TROW_22_0002 CHURCH LANE, WESBURY ROAD SOUTHWICK ROAD 852 2022/23 ASPHALT ST THOMAS ROAD MICRO UC855802 TROW_22_0003 BELLEFIELD CRESCENT ST THOMES ROAD SW 400 2022/23 TROWBRIDGE ASPHALT END OF BOTH SURFACE UC845401 TROW_22_0004 IRELAND NR SOUTHWICK LAST HALF APPX HALF WAY TO BEND 250 2022/23 RESIDENTIAL SPURS TREATMENT SURFACE C397 TROW_22_0005 BROOK ROAD TROWBRIDGE WINGFIELD ROAD BRADFORD ROAD 1030 2022/23 TREATMENT

DURSLEY ROAD SURFACE UC855602 TROW_23_0001 RUTLAND CRESCENT TROWBRIDGE BRADLEY ROAD TROWBRIDGE 500 2023/24 TROWBRIDGE TREATMENT SURFACE UC855603 TROW_23_0002 ASHMEAD TROWBRIDGE RUTLAND CRESCENT RUTLAND CRESCENT 400 2023/24 TREATMENT MELTON ROAD/LANGFORD FRANCIS STREET SURFACE UC855830 TROW_23_0003 LANGFORD ROAD TROWBRIDGE 750 2023/24 ROAD TROWBRIDGE TREATMENT MELTON RD/LANGFORD SURFACE UC855824 TROW_23_0004 MELTON ROAD TROWBRIDGE SEYMOUR ROAD TROWBRIDGE 230 2023/24 RD TROWBRIDGE TREATMENT WYKE ROAD SURFACE UC865822 TROW_23_0005 VICTORIA ROAD (SPINE) TROWBRIDGE A361 JUNC VICTORIA ROAD 1029 2023/24 TROWBRIDGE TREATMENT SURFACE UC825403 TROW_23_0006 LOOP ROAD AND HOOPERS POOL A361 END 1000 2023/24 TREATMENT SURFACE C49 TROW_23_0007 BRATTON ROAD WEST ASHTON FROM A350 JUNCTON 30MPH LIMIT 800 2023/24 TREATMENT

SURFACE UC855501 TROW_24_0001 CHURCH LANE NORTH BRADLEY SOUTHWICK RD WESTBURY ROAD 870 2024/25 DRESSING UC855403/1 TROW_24_0002 THE RANK NORTH BRADLEY SOUTHWICK RD END SURFACING 360 2024/25 SURFACE C49 TROW_24_0003 WEST ASHTON RD WEST ASHTON RD RBT A350 WEST ASHTON 1420 2024/25 DRESSING WOODMARSH/WESTBURY ROAD LOOP, C227 TROW_24_0004 MICROASPHALT 1200 2024/25 NORTH BRADLEY JUNCTION BY NUMBER 1 END OF LANE PAST SURFACE UC TROW_24_0005 HOOPERS POOL SOUTHWICK CUL-DE-SAC 528 2024/25 HOOPERS POOL MOOREFIELD FARM DRESSING COMPLETE ROAD AROUND A363 TROW_24_0006 TRINITY ROUNDABOUT TROWBRIDGE SURFACING 330 2024/25 TRINITY CHURCH

UC TROW_24_0007 B3106 STALLARD STREET MARSH ROAD PRESERVATIVE TBC 2024/25

A363 WOODMARSH ROUNDABOUT TO WHITE HORSE SURFACE A363 TROW_25_0001 WOODMARSH ROUNDABOUT 650 2025/26 WHITE HORSE ROUNDABOUT ROUNDABOUT DRESSING

A363 TROW_25_0002 A363 WOODMARSH ROUNDABOUT SURFACING 110 2025/26

A363 TROW_25_0003 A363 WHITE HORSE ROUNDABOUT SURFACING 130 2025/26

C393 TROW_25_0004 DEVIZES ROAD HILPERTON B3105 CHURCH STREET A361 ROUNDABOUT SURFACING 900 2025/26

C19 TROW_25_0005 ASHTON RD HILPERTON HILPERTON BYPASS NEWHURST PARK MICROASPHALT 139 2025/26

TROW_25_0006 LACOCK GDNS HILPERTON TBC 2025/26

TROW_25_0007 MANVERS STREET/FORE STREET CHURCH STREET TROWBRIDGE WICKER HILL SURFACING 240 2025/26 SURFACE UC TROW_25_0008 LITTLE COMMON, NORTH BRADLEY WESTBURY ROAD END 300 2025/26 DRESSING UC TROW_25_0009 ASHTON STREET, TROWBRIDGE LARK DOWN ALMA STREET SURFACING 380 2025/26

B3106 TROW_25_0010 CONIGRE BRITISH ROW BACK STREET SURFACING 158 2025/26

SITE BELOW DEPENDANT ON WESTBURY – STATION ROAD BRIDGE STRENGTHENING WORKS

B3097 TROW_22_0001 HAWKERIDGE ROAD, HAWKERIDGE RD SURFACING 575 FF DURSLEY ROAD ROUNDABOUT

TROWBRIDGE AREA BOARD WYNSOME STREET, GOOSE STREET, BRADLEY ROAD, SOUTHWICK ROAD, WESTBURY ROAD, Phased Surfacing and Surface Dressing over appx 2 – 3 years

SHAILS LANE HILL ST WICKER HILL PART B3106 FROM A363 MAY REQUIRE PHASING from A363 SHIRES ROUNDABOUT to JCT MANLEY LANE

To be carried out over 2 years budgets, the majority from 2020/21

C361 MORTIMER STREET, TROWBRIDGE (INC SPURS TO CH) FROM LONGFIELD ROUNDABOUT to END / NEWTOWN Length 360m Surfacing

A361 COUNTY WAY FROM WEST ASHTON RD RBT to ROUNDSTONE / FIRESTATION RBT Length 330m Surfacing / Surface Treatment

MAPLE and LAUREL GROVE, TROWBRIDGE FROM COLLEGE ROAD to END INC LAUREL GROVE Length 290m Micro Asphalt

COURT STREET, TROWBRIDGE FROM CASTLE ST RBT to END INC MILL STREET Length 260m Surfacing

CARISBROOKE CRESCENT, TROWBRIDGE FROM WYKE ROAD JUNCTION to END OF CUL-DE-SAC Length 76m Micro Asphalt

KINGS GARDENS HILPERTON FROM WYKE ROAD JUNCTION to END OF CUL-DE-SAC Length 165m Surfacing WYKE ROAD _ RESERVE

WESTWOOD RD TROWLE FROM WESTWOOD RD TROWLE to WESTWOOD RD TROWLE Length 2750m Surface Treatment (Dressing)

HILPERTON ROAD FROM ROUNDSTONE RABT to HILPERTON BYPASS RBT Length 1230m Surface Treatment (Dressing)

UNION STREET TROWBRIDGE FROM TIMBRELL STREET to THE HALVE JCT Length 100m Surfacing

UC HORSE ROAD HILPERTON FROM WYKE ROAD to B3105 MARSH ROAD Length 710m Micro Asphalt

NO PSDP PLANNED FOR 2021/2