DRAFT 2019 - 2022 Updated September 27, 2018

Regional Transportation Improvement Program for the Thurston Region RTIP

A Short-Range Investment Plan for the Thurston Region

Preparation of this report was fi nanced by appropriations from member jurisdictions of the Thurston Regional Planning Council and grants from the Washington State Department of Transportation and U. S. Department of Transportation--Federal and Federal Transit Administrations.

Prepared by: Thurston Regional Planning Council THURSTON REGIONAL PLANNING COUNCIL (TRPC) is a 22-member intergovernmental board made up of local governmental jurisdictions within Thurston County, plus the Confederated Tribes of the Chehalis Reservation and the Nisqually Indian Tribe. The Council was established in 1967 under RCW 36.70.060, which authorized creation of regional planning councils. TRPC's mission is to “Provide Visionary Leadership on Regional Plans, Policies, and Issues.” To Support this Mission: A. Support regional transportation planning consistent with state and federal funding requirements. B. Address growth management, environmental quality, economic opportunity, and other topics determined by the Council. C. Assemble and analyze data that support local and regional decision making D. Act as a “convener” to build regional consensus on issues through information and citizen involvement. E. Build intergovernmental consensus on regional plans, policies, and issues, and advocate local implementation.

2018 MEMBERSHIP THURSTON REGIONAL PLANNING COUNCIL

Governmental Jurisdiction Name of Representative City of Lacey Carolyn Cox, Councilmember City of Olympia Nathaniel Jones, Councilmember City of Rainier George Johnson, Councilmember City of Tenino David Watterson, Councilmember City of Tumwater Tom Oliva, Councilmember City of Yelm JW Foster, Councilmember Confederated Tribes of the Chehalis Reservation Amy Loudermilk, Staff Nisqually Indian Tribe Heidi Thomas, Tribal Councilmember Town of Bucoda Alan Vanell, Councilmember Thurston County John Hutchings, County Commissioner North Thurston Public Schools Chuck Namit, School Board Member Olympia School District Leslie Huff, School Board Member Tumwater School District Mel Murray, Staff Intercity Transit Karen Messmer, Authority Member LOTT Clean Water Alliance Cynthia Pratt, Board Member Port of Olympia E.J. Zita, Port Commissioner PUD No. 1 of Thurston County Russell Olsen, PUD Commissioner

Associate Members Economic Development Council Michael Cade, Executive Director of Thurston County Lacey Fire District #3 Gene Dobry, Commissioner Puget Sound Regional Council vacant Timberland Regional Library LG Nelson, Library Director The Evergreen State College Jeanne Rynne, Director of Facilities Services

Chair Vice Chair Secretary Nathaniel Jones JW Foster Alan Vanell City of Olympia City of Yelm Town of Bucoda

Marc Daily, Executive Director As authorized under Washington State law (RCW 47.80.040), each Regional Transportation Planning Organization is required to appoint a Transportation Policy Board to provide policy advice to the regional transportation planning organization. The Policy Board is to allow representation from major employers in the region, as well as the state Department of Transportation, transit districts, port districts, and member cities, towns, and counties within the region. It enables broad participation in the transportation policy making process.

The Transportation Policy Board includes all state legislative representatives with districts in the Thurston region as ex offi cio members.

2018 MEMBERSHIP OF TRANSPORTATION POLICY BOARD

Governmental Jurisdiction Name of 2018 Representative City of Lacey Andy Ryder, Chair City of Olympia Clark Gilman City of Rainier Jonathan Stephenson City of Tenino John O’Callahan City of Tumwater Pete Kmet City of Yelm Tracey Wood Thurston County John Hutchings Confederated Tribes of the Chehalis Reservation Amy Loudermilk Nisqually Indian Tribe Heidi Thomas Intercity Transit Don Melnick North Thurston Public Schools John Suessman Port of Olympia E.J. Zita WA State Dept. of Enterprise Services Kevin Dragon Thurston Economic Development Council Pending WA State Dept. of Transportation, Olympic Region John Wynards Citizen Representative Graeme Sackrison, Vice-Chair Citizen Representative Kevin Pestinger Business Representative Doug DeForest Business Representative Renee Radcliff Sinclair Business Representative Angela White

Legislative District Ex Offi cio Member 2nd Legislative District Senator Randi Becker Representative Andrew Barkis Representative J.T. Wilcox

20th Legislative District Senator John Braun Representative Ed Orcutt Representative Richard DeBolt

22nd Legislative District Senator Sam Hunt Representative Laurie Dolan Representative Beth Doglio

35th Legislative District Senator Tim Sheldon Representative Drew MacEwen Representative Dan Griff ey This page left intentionally blank. TABLE OF CONTENTS

RESOLUTION ...... 1

FORWARD ...... 3

INTRODUCTION...... 5 Background and Requirements ...... 5 Purpose of the Regional Transportation Improvement Program (RTIP) ...... 5 Projects for Inclusion in the Statewide Transportation Improvement Program (STIP) ...... 6 Financial Constraint ...... 6 Consistency ...... 6 Air Quality Conformity ...... 7 Other Projects ...... 7

RTIP DEVELOPMENT PROCESS ...... 9 Overview ...... 9 Local TIPs ...... 9 RTIP Document...... 9 RTIP Review and Approval ...... 10 Interagency Coordination and Cooperation ...... 10 RTIP Public Involvement Process...... 11 Prioritization and Project Selection for Regionally-Allocated STP Funds ...... 11 Intermodal/Multimodal Approach ...... 12 Funding Flexibility ...... 12 Financial Constraint ...... 12 Consistency ...... 12 RTIP Amendment Procedures ...... 13

MPO CERTIFICATION ...... 15

RTIP FUNDING SOURCES & CODES ...... 17 RTIP Funding Sources ...... 17 RTIP Project Codes ...... 18

PROJECT SUMMARY ...... 19

APPENDICES

APPENDIX A: Other TIP Projects ...... A-1 Consistency with the Regional Transportation Plan ...... A-1

APPENDIX B: Regional -Related Financial Plan for Local Agencies ...... B-1 APPENDIX C: Air Quality Conformity ...... C-1 Air Quality Designation ...... C-1 Latest Planning Assumptions and Documentation ...... C-2 Consultation ...... C-2 Findings ...... C-3 Statement of Conformity ...... C-3

APPENDIX D: Performance Measures ...... D-1 Performance Based Approach to Planning ...... D-1 Transportation Improvement Program and Performance Measures ...... D-1 Supporting Information ...... D-3

APPENDIX E: Public Participation Summary ...... E-1 Distribution and Notifi cation ...... E-1 Staff and Agency Review ...... E-1 Comments ...... E-1

LIST OF FIGURES Figure 1: Thurston County in Washington State ...... 5 Figure 2: RTPO and MPO Boundary Area ...... 6

Figure 3: Thurston Region PM10 Maintenance Area ...... 7 Figure 4: TRPC RTIP Development ...... 8

Figure 6: Thurston Region PM10 Maintenance Area ...... C-1 Figure 7: National Highway System, Thurston County...... D-3 Figure 8: National Highway System, Urban Area ...... D-3

TABLES Table 1: Federal and State Fund Codes...... 17 Table 2: Project Codes ...... 18 Table 3: Summary Table of RTIP Projects ...... 21 Table 4: RTIP MPO Projects ...... 27 Table 5: TRPC MPO Projects Financial Feasibility: Cost vs. Revenue ...... 74 Table 6: -Related Financial Projections (In Thousand of Constant 2015 Dollars) ...... B-1 Table 7: Annual VMT Growth Rate ...... C-3 Table 8: Performance Measures ...... D-1 THURSTON REGIONAL PLANNING COUNCIL

RESOLUTION 2018-06

RELATING TO THE 2019-2022 Regional Transportation Improvement Program for the THURSTON REGION.

WHEREAS, the Thurston Regional Planning Council (TRPC), under its designation as the Metropolitan Planning Organization (MPO) and Regional Transportation Planning Organization (RTPO) for the THURSTON COUNTY region, has the responsibility for developing and adopting a Regional Transportation Improvement Program (RTIP); and

WHEREAS, transportation improvement projects must be included in the Regional Transportation Improvement Program to be eligible for federal assistance under Federal Transit Administration and Federal Highway Administration funding programs; and

WHEREAS, Thurston Regional Planning Council certifies that the requirements of 23 USC, Section 134 are met. Certification is a joint MPO/WSDOT statement concerning the planning process and is updated every two years; and

WHEREAS, Thurston Regional Planning Council is to certify that the Regional Transportation Improvement Program complies with all state and federal air quality conformity requirements for particulate matter 10 microns in size or less.

NOW THEREFORE BE IT RESOLVED BY THE THURSTON REGIONAL PLANNING COUNCIL:

THAT the 2019-2022 Regional Transportation Improvement Program is found to be in conformity with the federal and state Clean Air Acts and Fixing America’s Surface Transportation (FAST) Act requirements; and

THAT the scope and content of the 2019-2022 Regional Transportation Improvement Program be approved with the understanding that minor changes may be required after federal review.

ADOPTED this 5th day of October 2018.

ATTEST:

Marc Daily Nathaniel Jones, Chair Executive Director Thurston Regional Planning Council

13:bm

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 1 This page left intentionally blank.

2 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region FORWARD

The Regional Transportation Improvement Program (RTIP) is prepared every year by Thurston Regional Planning Council (TRPC) in cooperation with local jurisdictions and the Washington State Department of Transportation (WSDOT). TRPC is designated the Metropolitan Planning Organization (MPO) for the Thurston region. The RTIP is a four-year programming document derived from the comprehensive six-year Transportation Improvement Programs (TIPs) that each local agency develops and adopts annually. In turn, the RTIP is used by the state to prepare the State Transportation Improvement Program (STIP). The RTIP serves these main purposes: 1) It identifi es a list of transportation projects that will be forwarded to the state for inclusion in the STIP. For federally funded projects, even if project funding has been awarded, it is not available to jurisdictions and agencies until the project is included in the STIP. To be included in the STIP, projects must be programmed for funding (funding-secured) in the Regional Transportation Improvement Plans (RTIP) in the four-year period and meet one or more of the following criteria:

a. Have federal funding or have a high-level of certainty of federal funding within the duration of the current RTIP, as verifi ed by the MPO b. Are WSDOT projects c. Are regionally signifi cant, regardless of funding source

2) It demonstrates fi nancial constraint for the projects referenced above.

3) It demonstrates consistency with RCW 36.70A, Section 70 of the Washington State Growth Management Act requiring transportation planning to be coordinated and consistent with local comprehensive plans.

4) It demonstrates that regionally signifi cant projects programmed for funding during the time period will not cause or contribute to any new violation of the federal air quality standards for particulate matter of 10 microns or less (PM10), will not increase the frequency or severity of any existing violation of the standards, nor delay timely attainment of the standards.

5) It identifi es other programmed and planned transportation projects adopted in local six-year Transportation Improvement Programs.

Preparation of this RTIP document and submittal of the projects herein are in conformance with regulations and guidelines issued by the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA).

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 3 This page left intentionally blank.

4 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region INTRODUCTION

Thurston Regional Planning Council (TRPC) serves the Thurston region as the federally designated Metropolitan Planning Organization (MPO) and the state designated Regional Transportation Planning Organization (RTPO). In this capacity, TRPC is responsible for development of a four-year Regional Transportation Improvement Program (RTIP). TRPC must also ensure that projects submitted for inclusion in the RTIP are consistent with the transportation elements of local comprehensive plans, the Regional Transportation Plan (RTP), and with each other.

Background and Requirements

Based on 2017 population estimates, 276,900 people live in Thurston County. Of this total, nearly 193,566 people are estimated to live within the Olympia-Lacey, WA Urbanized Area (a federal census geography). The federal government requires the formation of metropolitan planning organizations (MPOs) for all urbanized areas exceeding a population of 50,000. Washington State Governors have continuously re-designated TRPC as the MPO for the Thurston region since Governor John Spellman’s fi rst designation in January 1982. This designation provides additional federal transportation funds for transit, road projects, and transportation planning, along with requirements for increased coordination between jurisdictions. TRPC is also designated a Regional Transportation Planning Organization (RTPO) under the Washington Growth Management Act (GMA). Section 53 of the GMA states that the transportation system should “function as one interconnected and coordinated system” and that “transportation planning should be coordinated with local comprehensive plans” (RCW 47.80.023). To achieve these objectives, RTPOs were formed. RTPOs are required to review and certify transportation elements of county, city and town comprehensive plans for consistency with the Regional Transportation Plan. This consistency review also covers the GMA required six-year , road, and transit improvement programs. Similar to the MPO, the RTPO has a county-wide planning area. Under federal transportation legislation, Fixing America’s Surface Transportation (FAST) Act, the RTIP’s project list must be consistent with the long-range Regional Transportation Plan (RTP). The RTP must consider land use and alternative transportation modes and their connectivity in the transportation system. Projects included in this RTIP are consistent with, and refl ect the priorities identifi ed in, the 2040 Thurston Regional Transportation Plan: What Moves You. Development of an RTP as required by MPOs under the FAST Act, parallels those of a RTPO under the State’s Growth Management Act. Figure 1: Thurston County in Washington State

Purpose of the Regional Transportation Improvement Program (RTIP)

The RTIP serves these main purposes: • It identifi es a list of transportation projects that will be forwarded to the state for inclusion in the Washington State Department of Transportation’s Statewide Transportation Improvement Program (STIP). For federally funded projects, even if project funding has been awarded, it is not available to jurisdictions and agencies until the project is included in the STIP.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 5 • It demonstrates fi nancial constraint for the projects referenced above. • It demonstrates consistency with RCW 36.70A, Section 70 of the Washington State Growth Management Act requiring transportation planning to be coordinated and consistent with local comprehensive plans. • It demonstrates that regionally signifi cant projects programmed for funding during the four-year time period will not cause or contribute to any new violation of the federal air quality standards for particulate matter of 10 microns or less (PM10), will not increase the frequency or severity of any existing violation of the standards, nor delay timely attainment of the standards. • It identifi es other programmed and planned transportation projects adopted in local six-year Transportation Improvement Programs.

Projects for Inclusion in the Statewide Transportation Improvement Program (STIP)

The primary purpose of the RTIP is to identify and document transportation projects to be included in the STIP. To be included in the STIP, projects must be programmed for funding (funding-secured) in the Regional Transportation Improvement Plan (RTIP) in the four-year period and meet one or more of the following criteria: a. Have federal funding or have a high-level of certainty of federal Figure 2: RTPO and MPO Boundary Area funding within the duration of the current RTIP, as verifi ed by the MPO b. Are WSDOT projects c. Are regionally signifi cant, regardless of funding source Projects are not eligible to receive federal funds—even though the funds have been awarded—unless they are included in the RTIP and STIP documents. The Thurston region is exempt from many of the requirements of major metropolitan areas like Seattle and as a result, uses a more streamlined RTIP development process than those larger areas. This is particularly true in the way federally-funded projects are identifi ed and listed. The RTIP also includes an assessment of the fi nancial feasibility of those projects. This evaluation assesses the region’s ability to meet its fi nancial commitment on these programmed projects while still funding necessary, on-going maintenance and operational needs.

Financial Constraint

The RTIP demonstrates fi nancial constraint for the projects identifi ed for inclusion in the STIP. Financial con-straint is demonstrated at both the project level and regional level.

Consistency

In its function as a four-year programming and planning document, the RTIP is an important implementation component of the long-range regional transportation plan and local comprehensive plans. Its development and review aids in the coordination of transportation projects and programs, helping to integrate the short-range individual eff orts of local

6 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region agencies into a coordinated approach that continues to move the region towards its long-range goals. The RTIP allows interested parties to review transportation projects identifi ed for implementation over the next four years for consistency with area-wide goals, policies and priorities in a convenient, single document.

Air Quality Conformity

Part of the Thurston region is an area re- designated to attainment with an approved Second 10-Year Limited Maintenance Plan for PM10 (hereafter referred to as “limited maintenance”.) That designation was earned after a concerted eff ort on the part of the Olympic Region Clean Air Agency to reduce the amount of wood smoke in the air. Wood smoke was the region’s primary source of particulates, and the principle source of air pollution. As a part of its compliance with the terms of the maintenance designation, the Thurston region must demonstrate that the transportation projects included in this RTIP will not cause the air quality to degrade such Figure 3: Thurston Region PM10 Maintenance Area that there would be violations of the allowed standards for particulate matter. Appendix C provides more detail on the air quality conformity process and this RTIP’s eff ective demonstration of compliance with all requirements. The Thurston County maintenance area is approximately the 1987 city limits of Lacey, Olympia, and Tumwater. The fi nal rule for the promulgation and implementation of the Thurston County Second 10-Year PM10 Limited Maintenance Plan became eff ective November 4, 2013. The Regional Transportation Plan (RTP) acknowledges that changing climate patterns will impact the region and includes policies that call for reductions in per capita vehicle miles traveled to help limit production of greenhouse gases by gasoline- and diesel-powered vehicles. The same RTP policies that promote the reduction of PM10 also work to limit production of greenhouse gases from vehicles. All RTIP projects are evaluated for consistency with the RTP.

Other Projects

This RTIP includes a list of projects included in local TIPs for which: 1. Local jurisdictions and agencies will seek funding, either through federal, state or local sources, or 2. Locally signifi cant projects funded with state grants and local revenues. These projects were identifi ed by local agencies during development of their comprehensive six-year TIPs and reviewed by the public prior to adoption by each agency. Including these projects as an Appendix (A) to the RTIP aff ords further evaluation of these projects by the community as priority short-range needs. This review serves multiple purposes. It provides a comprehensive regional view of the short-range projects. In addition, if federal funding is secured for any of these projects, the necessary amendment process into the STIP is more streamlined and effi cient since these projects are already identifi ed in the adopted RTIP as an illustrative list of projects.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 7 Figure 4: TRPC RTIP Development TRPC RTIP Development

WSDOT HQ Final RTIP STIP Development October October TRPC Action (First Friday of October)

Public Comment Period TPB /DWH$XJXVWHDUO\ Review & Comment September (Second Wednesday of September) IRUZHHNV 

September September TRPC Discussion (First Friday of September)

Draft RTIP August August

County Draft TIP (by late July) RTIP Development July Local TIPs & WSDOT Projects (by early July)

8 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RTIP DEVELOPMENT PROCESS

Overview

The Regional Transportation Improvement Program (RTIP) is part of a series of transportation improvement programs developed at the local (TIP), regional (RTIP) and state (STIP) levels. TIPs contain a six-year list of transportation projects to be undertaken by the local agency or Washington State Department of Transportation regional offi ces. RTIPs contain a four-year list of funding secured transportation projects that meet specifi c criteria for a specifi c region covered by a Metropolitan Planning Organization and/or Regional Transportation Planning Organization. The state’s STIP contains a compilation of RTIPs.

Local TIPs

In developing their local TIPs, jurisdictions and agencies evaluate their transportation needs for the ensuing six-year period based on local, regional, and state priorities, and the likely funds they will have available with which to meet those needs. Since likely funds are usually less than identifi ed needs, local agencies prioritize their transportation needs to identify a comprehensive six-year list of projects that they feel is most important to pursue. They provide a draft list of these projects for both public comment and review by internal departments and other agencies to confi rm project priorities and ensure consistency with local and regional plans. Based on feedback from public comment and agency review, each agency makes any revisions deemed necessary before adopting its formal TIP. Local jurisdictions and agencies (Town of Bucoda, Cities of Lacey, Olympia, Rainier, Tenino, Tumwater, and Yelm, Thurston County, Intercity Transit and TRPC) and Washington State’s Department of Transportation Olympic Region submit their adopted TIPs to Thurston Regional Planning Council (TRPC) through a state-run on-line database. The complete six-year TIP submittals refl ect the six-year transportation needs of the entire Thurston region for both programmed (funding-secured) and planned projects.

RTIP Document

The RTIP document contains a list of funding secure projects in Table 4. Projects from this table will also be included in the STIP. These projects must be programmed for funding (funding-secured) in local Transportation Improvement Plans (TIPs) in the four-year period and meet one or more of the following criteria: a. Have federal funding b. Are WSDOT projects c. Are regionally signifi cant, regardless of funding source. Table 4 lists the projects which meet the above criteria. Additional information on project fi nancial feasibility (Table 5) and region-wide fi nancial feasibility is provided (Appendix B). Appendix A contains the remainder of the projects identifi ed in local TIPs. This report is broken out by agency and describes intended projects, including timing and cost. Agencies also identify likely sources from which they will seek funding for these projects during the annual grant cycles that determine so much of this region’s transportation funding. Actual funding sources or amounts may change due to factors beyond an agency’s ability to predict. In addition, timing may change somewhat depending upon conditions imposed by the granting authority. These projects have been identifi ed, reviewed, and approved during development of each agency’s local TIP. Collectively, they represent a regional list of transportation needs for which agencies will seek funding. Including these projects as an Appendix (A) in the draft RTIP enables public review of the full range of locally identifi ed needs, costs and potential funding sources, and estimated project timing. This inclusion recognizes these projects as

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 9 approved regional priorities consistent with the 2040 Regional Transportation Plan, which should be amended into the Statewide Transportation Improvement Program via a streamlined amendment process upon successful funding awards as appropriate based on their air quality conformity status.

RTIP Review and Approval

The draft RTIP is presented to the Transportation Policy Board (TPB) and Thurston Regional Planning Council (TRPC) for their review and comment in September. The TPB makes a recommendation on adoption to TRPC. Based upon its review of the draft document, any public comments received, and the TPB’s recommendation, the Council makes a decision on adoption at its regularly scheduled October meeting. The adopted RTIP is then submitted to WSDOT, which will include projects from Table 4 in the formal STIP as appropriate. Following is a summary of the RTIP development and approval process: 1. April-June Development, technical review and refi nement of six-year Transportation Improvement Programs by the public works and/or planning departments of agencies within the Thurston region. 2. June-July Public review of local TIPs, further refi nement as necessary, and formal adoption by local governing boards. 3. July/August Transmittal of adopted TIPs by jurisdictions to TRPC staff . 4. August RTIP development by TRPC staff . 5. August/September Review of the draft RTIP by the public, local agencies, WSDOT, FHWA, and FTA, with refi nements as necessary. 6. September TPB and TRPC review and comment on the draft RTIP; recommendation on its adoption by the TPB to TRPC. 7. October TRPC adoption of the RTIP and submittal to WSDOT. 8. October-December Development and review of the Statewide Transportation Improvement Program (STIP) . 9. November Review of the Air Quality Conformity fi ndings by the Washington State Department of Ecology, the federal Environmental Protection Agency, and FHWA and FTA. 10. December-January Review and approval of the STIP by the Federal Highways Administration and Federal Transit Administration. Once approved, jurisdictions are able to proceed with federally funded projects identifi ed in the RTIP.

Interagency Coordination and Cooperation

The federal metropolitan planning provisions of Fixing America’s Surface Transportation (FAST) Act and regional planning provisions of the state’s Growth Management Act (GMA) feature an enhanced role for MPOs and RTPOs. As the MPO/RTPO for the Thurston region, Thurston Regional Planning Council engages in a continuous and comprehensive planning process in cooperation with member jurisdictions and the state. To assist them with this function, Thurston Regional Planning Council appointed a Transportation Policy Board, or TPB. TPB membership includes elected representatives from: the cities of Lacey, Olympia, Tenino, Tumwater, and Yelm; Thurston County; the Nisqually Indian Tribe and Confederated Tribes of the Chehalis Reservation; Port of Olympia and Intercity Transit. It includes key staff representatives from the Washington State Department of Transportation Olympic Region, and the Washington State Department of Enterprise Services. It also includes business and citizen advisors. All state legislative representatives with districts in the Thurston region are ex offi cio members of the TPB. The Transportation Policy Board is responsible for advising the Regional Council on transportation policy issues pursuant to state and federal legislation. The TPB also advises the Regional Council on other transportation planning issues requiring regional consensus, approval, or adoption.

10 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region In addition to support from agency staff , Transportation Policy Board discussions and positions are informed by work and recommendations of the Technical Advisory Committee, or TAC. The TAC is comprised of staff from member jurisdictions. Active representatives include: the cities of Lacey, Olympia, Tumwater, and Yelm; Thurston County; Intercity Transit; and WSDOT Olympic Region. The TAC is responsible for advising the Transportation Policy Board and Regional Council on technical considerations relating to regional transportation issues pursuant to state and federal legislation. The Technical Advisory Committee also serves as a forum for planning coordination and cooperation between the local agencies.

RTIP Public Involvement Process

The RTIP is developed from the local TIPs compiled and adopted annually by each jurisdiction or agency within Thurston County. As required by law, each local agency conducts a public involvement process in the development and review of their local TIP. These processes vary by jurisdiction, but all culminate in a formal public hearing prior to adoption by the local governing boards. While the individual local TIPs have been reviewed prior to adoption, TRPC conducts a public review of the draft RTIP because this is the only document that contains programmed and planned projects from every agency throughout the region. In this way, members of the community can view the full scope of short-range transportation projects intended to implement the long-range transportation goals they helped shape during development of the 2040 Regional Transportation Plan. TRPC follows the agency’s public participation procedures when developing the RTIP and Air Quality Conformity Analysis. TRPC publishes a “Notice of Availability” during the public review period and notice is also posted on the TRPC website, at www.trpc.org, where full copies of the RTIP are available for review or download. Copies of the entire draft RTIP are available free of charge from TRPC on request. In addition, review requests are sent to staff at member agencies, the Washington State Department of Transportation, the Federal Transit Administration, the Federal Highways Administration, and neighboring regions. Any comments received during the comment period are presented to TRPC for review and consideration during adoption in October.

Prioritization and Project Selection for Regionally-Allocated STP Funds

One of the most signifi cant aspects of the Intermodal Surface Transportation Effi ciency Act of 1991 (ISTEA) was a funding program that made Metropolitan Planning Organizations like TRPC responsible for programming federal funds to support regionally established transportation goals and policies. This funding program, known as the Surface Transportation Program, or STP, resulted in a comprehensive, coordinated approach to project identifi cation and funding in this region. The STP provision was signifi cant not only for how projects were selected, but also for the kinds of projects that could be funded. With the passage of ISTEA, MPOs were encouraged to consider the full range of transportation modes, not just passenger car needs. ISTEA expired in late 1997. New acts were authorized to succeed it, including the Transportation Equity Act for the 21st Century (TEA21), the Safe, Accountable, Flexible and Effi cient Transportation Equity Act – A Legacy for Users (SAFETEA-LU), Moving Ahead for Progress in the 21st Century (MAP-21), and the Fixing America’s Surface Transportation (FAST) Act. All the reauthorizations carry on the spirit and intent of the original act, and preserve the role of MPOs in identifying projects to be carried out with these discretionary federal funds. In its capacity as MPO, TRPC established a project selection process in 2001 that emphasized safety, preservation, and increased effi ciency of the transportation system. In allocating its federal funds, TRPC selects projects that support all aspects of the transportation system including , public transportation, , bike , and travel demand management. Selected projects must be included in the RTIP for agencies to use the federal funds. This RTIP includes some projects that are slated to be funded with regional STP funding. More information about the regional STP selection process is available at www.trpc.org.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 11 Intermodal/Multimodal Approach

Projects identifi ed in local TIPs and included in the RTIP provide for the development of an integrated transportation network that focuses on the safe and effi cient movement of people and goods. This commitment to an integrated, multi-modal transportation network is also embodied in the selection and funding of projects through the regional STP allocation process. Funding priorities consider all modes of transportation, how the various modes work together, and how the network components support local and regional land use plans. Selection of projects that are consistent with the goals and policies of the Regional Transportation Plan ensures that the widest range of mobility options are considered.

Funding Flexibility

Provisions in the Fixing America’s Surface Transportation (FAST) Act funding programs allow expanded fl exibility to MPOs and local agencies in how STP funds are used. Project Type Flexibility Federal STP funds may be spent on a variety of diff erent projects such as transit, bike and pedestrian facilities, and transportation planning, as well as traditional roadway projects such as traffi c signals, safety enhancements, and roadway upgrades. The RTIP demonstrates the fl exibility of the STP by the variety of diff erent projects receiving these funds. Programming Flexibility Through the regional STP allocation process, TRPC identifi es projects for funding over a two- to four- year period. Programming over a period of two to four years enables local agencies to eff ectively plan and implement projects. Selection Authority Flexibility Federal STP funds are administered at both the regional and state levels. Projects are selected for funding at the regional level through TRPC for STP(US) [urban] and STP(R) [rural] funds. Projects submitted for Transportation Alternatives Program – TAP(US) and Congestion Mitigation Air Quality Program (CMAQ) – are also selected through TRPC. All other STP funding categories are prioritized and selected at the state level by WSDOT.

Financial Constraint

RTIP projects are required to be fi scally constrained, meaning that they can only be programmed if there is a reasonable expectation that federal, state, or local dollars will be available to actually fund them during the four-year period.

Consistency

As the RTPO for Thurston County, TRPC is responsible for reviewing the transportation elements of the local comprehensive plans for consistency with the Regional Transportation Plan. This is an important component of the state’s Growth Management Act. The original consistency review and certifi cation process was completed in 1995. That process highlighted the regulatory enforcement capacity of TRPC as the RTPO for the region. At that time discrepancies emerged between local and regional forecast assumptions, modeling procedures, and application of level of service standards. In response, this region committed to changes in its forecasting and modeling processes to eliminate these kinds of discrepancies between local and regional plans in the future. The goal was to establish a process that maintained consistency between local and regional processes rather than relying on regulatory measures to enforce compliance.

12 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region This consistency maintenance process has several elements. First, the Thurston region established and implements an inclusive forecasting process that is based on the adopted land use plans of every jurisdiction. This process engages local staff and policy makers as well as citizens in analyzing and validating assumptions about growth and development. This process generates population and employment forecasts that are used not only for regional transportation planning but also local planning and implementation measures like review. The Thurston region also established a comprehensive, inclusive approach to transportation modeling. This region developed a single, region-wide model that is used by TRPC and by its local agencies to evaluate current and future traffi c conditions. This model is also used in concurrency analysis by local agencies. This combination of region-wide forecasts based on local land use plans, and a single region-wide traffi c model fundamentally ensures compliance with GMA consistency requirements since all agencies are operating with coordinated, consistent land use and transportation assumptions and using the same forecasting tools. However, it is more eff ective than the traditional concept of consistency review that relies on regulatory enforcement and reporting because the original intent of the legislation has been integrated throughout this region’s land use and transportation planning processes. Eff ective integration of consistent policies and procedures resulted in TRPC developing policy language and supporting maps for use by all local jurisdictions in complying with requirements of SHB 1487 (the “Level of Service” bill). It also entails participation by TRPC in the review of proposed amendments to local Comprehensive Plans. TRPC opted to meet the spirit and intent of consistency requirements by modifying its own procedures and making them more inclusive of the local jurisdictions rather that the regulatory approach used in 1994 and 1995, when the original consistency review process was undertaken. This integrated, collaborative approach is mutually reinforcing and appropriate to the character of this regional community. As part of its development of the RTIP, TRPC evaluates each project for its consistency with regional transportation planning priorities, and the adopted Regional Transportation Plan. All projects listed in the 2019-2022 RTIP have been reviewed and found to be consistent with the goals and objectives in local comprehensive plans, the Regional Transportation Plan (RTP), the Growth Management Act, and the Washington State Transportation Plan. All projects identifi ed in the RTIP document — both programmed and planned — are consistent with the 2040 the Regional Transportation Plan.

RTIP Amendment Procedures

Federal requirements stipulate that changes to the RTIP in between the annual updates require an amendment to the original document, which then triggers an amendment to the STIP. This is important because a jurisdiction cannot proceed with a project for which it has been awarded federal money until the STIP is formally amended and approved by the federal agencies, even though the jurisdiction has been awarded money for that project. Most local agencies are anxious to proceed with these projects as soon as possible after selection for funding. That is why the RTIP and STIP amendment procedures need to be effi cient. There are two methods for amending the RTIP, Formal Amendments and Administrative Modifi cations. Formal RTIP amendments require Transportation Policy Board (TPB) action and are used for projects which are either new, and are therefore not yet in the RTIP, and for projects undergoing a signifi cant change in scope, funding or other key elements. The Administrative Modifi cation option for amending the RTIP is used for projects previously reviewed by TRPC & TPB, and approved by TRPC during the RTIP Annual Update Process (which includes public review and air quality conformity review). For Administrative Modifi cations, eligible projects are submitted by agency staff to TRPC staff , who review the projects and submit them to WSDOT. Typically, Administrative Modifi cations are completed for smaller changes in budget, or to move forward planned projects from the RTIP’s Appendix A once they have secured funding. It is also used for WSDOT projects, and projects where only state and local dollars are being revised. TRPC’s amendment and modifying processes for the RTIP incorporates guidance provided by WSDOT on amending and modifying the STIP, and is available on the agency’s website (http://www.trpc.org/306/Regional-Transportation- Improvement-Prog).

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 13 This page left intentionally blank.

14 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region MPO CERTIFICATION

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 15 This page left intentionally blank.

16 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RTIP FUNDING SOURCES & CODES

RTIP Funding Sources

Projects identifi ed in the four-year list of programmed projects (Table 4) are funding-secured with federal, state, or local funds. Following is a list of the federal and state funding programs identifi ed in this RTIP that will be used to fi nance non-local projects.

Table 1 Federal and State Fund Codes Federal and State Fund Codes

5307 – Federal Transit Administration (FTA) Section 5307 FBP – Construction of Ferry Boats and Ferry Terminal Facilities 5309 – FTA Section 5309 Bus and Bus Facilities FEMA – Federal Emergency Management Agency 5309 (Bus) – Federal Transit Administration (FTA) Section 5309 Bus and Bus Facilities FMSIB – Freight Mobility Strategic Investment Board 5309 (FG) – Federal Transit Administration (FTA) Section 5309 Fixed Guideway HSIP – Highway Safety Improvement Program 5309 (NS) – Federal Transit Administration (FTA) Section 5309 New-Start (Rail) HSIP (SR) – Highway Safety Improvement Program Safe Routes to Schools 5310 – FTA Section 5310 Enhanced Mobility of Senior and Individuals with Disabilities IRR – Indian Reservation Roads 5311 – FTA Section 5311 Rural Area Formula Grants NHFP - National Highway Freight Program 5312 – FTA Section 5312 Research, Development, Demonstration, and Deployment Projects NHPP – National Highway Performance Program 5316 – FTA Section 5316 Job Access and Reverse Commute (JARC) SRTS – Safe Routes to School 5329 – Federal Trasnit Administration (FTA) Section 5329 Transit Safety & Oversight STP – Surface Transportation Program 5337 – Federal Trasnit Administration (FTA) Section 5337 State of Good Repair STP (BR) – Surface Transportation Program 5339 – Federal Trasnit Administration (FTA) Section 5339 Bus and Bus Facilities STP (E) – Surface Transportation Program Transportation Enhancement Adv CN – BR - Advanced Construction, Bridge STP (L) – Surface Transportation Program Legislative Earmarks Adv CN – NHS – Advanced Construction, National Highway System STP (R) – Surface Transportation Program Rural Adv CN – STP – Advanced Construction, Surface Transportation Program STP (UL) – Surface Transportation Program Urban Large BIA – Bureau of Indian Affairs STP (US) – Surface Transportation Program Urban Small BR – Bridge TAP (R) –Transportation Alternatives Program Rural CBI – Coordinated Border Infrastructure TAP (SR) – Transportation Alternatives Program Safe Routes to Schools CDBG – Community Development Block Grant TAP (UL) – Transportation Alternatives Program Urban Large CMAQ – Congestion Mitigation and Air Quality TAP (US) – Transportation Alternatives Program Urban Small DEMO – Demonstration Projects TIFIA – Transportation Infrastructure Finance and Innovation Act DEMO – High Priority Projects TIGER – Transportation Investment Generating Economic Recovery DOD – Department of Defense WFL - Western Federal Lands ER – Emergency Relief

Bike/Ped Program – Pedestrian and Bicycle Program PWTF – Public Works Trust Fund CRAB – County Road Administration Board SRTS – Safe Routes to School CWA – Connecting Washington Account TIB – Transportation Improvement Board

StateFMSIB – Freight Mobility Strategic Investment Federal Board TPP – Transportation Partnership Program OTHER – Other State Funding Sources WSDOT – Washington State Department of Transportation

For description of the fund codes, see online WSDOT’s STIP document, VIII Source of Funds at www.wsdot.wa.gov/LocalPrograms/ProgramMgmt/STIPDoc.htm.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 17 RTIP Project Codes

Local and regional agencies must conform to table formats established by WSDOT, used in various tables throughout this document. In addition, the federal government established specifi c codes for use in describing projects. The funding codes are identifi ed above. Following are additional codes established for use in RTIP that may be useful. Table 2 Project Codes

Roadway Functional Classification Improvement Type Codes (IMP Type) No Classification 01 New Construction Roadway 20 Environmental Only Interstate Rural 03 Reconstruction, Added Capacity 21 Safety Principal Arterial Rural 04 Reconstruction, No Added Capacity 22 Rail/Highway Crossing Minor Arterial Rural 05 4R Maintenance Resurfacing 23 Transit Major Collector Rural 06 4R Maintenance - Restoration & Rehabilitation 24 Management/Engineering - HOV Minor Collector Rural 07 4R Maintenance - Relocation 28 Pedestrian/Bicycle Facilities Local Access Rural 08 Bridge, New Construction 31 Landscaping & Beautification Interstate Urban 10 Bridge Replacement, Added Capacity 37 Mitigation of Highway Water Runoff Freeways & Expressways Urban 11 Bridge Replacement, No Added Capacity 38 Pedestrian/Bicycle Safety/Education Other Principal Arterial Urban 13 Bridge Rehabilitation, Added Capacity 40 Special Bridge Minor Arterial Urban 14 Bridge Rehabilitation, No Added Capacity 47 Bridge Preservation Collector Urban Local Access Urban

Environmental Data Type Phase Data EIS Env. Impact Statement PE Prelim. Engineering/Design EA Env. Assessment RW Right-of-Way Acquisition CE Categorical Exclusion CN Construction DCE Documented Categorical Exclusion ALL All phases

For more information on code usage, please visit the Highways and Local Programs section of WSDOT’s website. The STIP manual includes detail on appropriate code usage and meaning.

18 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region PROJECT SUMMARY

This section provides project-specifi c information for Regional Transportation Improvement Program (RTIP) projects that will be forwarded to the state for inclusion in the State Transportation Improvement Program (STIP). To be included in the STIP, projects must be programmed for funding (funding-secured) in local Transportation Improvement Plans (TIPs) in the four-year period and meet one or more of the following criteria: a. Have federal funding b. Are WSDOT projects c. Are regionally signifi cant, regardless of funding source.

The following is included in this section: • A summary table (Table 3) of RTIP projects. • RTIP MPO projects (Table 4), including project detail provided by local jurisdictions and agencies. • Financial Feasibility of RTIP MPO projects (Table 5)

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 19 This page left intentionally blank.

20 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region

&1  &1   673 86 &1   &1 673 86   &0$4         3KDVH

RTP Project ID refers to the corresponding project identifi RTP

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 21

3(  7$3 86 3(  6WDWH/RFDO      3(  673 86 3(   +,3 86 3(   &0$4        &1  &0$4 &1  7$3 86   &1   673 5     &1  6WDWH/RFDO&1  673 86 &1   7$3 86 &1  6WDWH/RFDO           5:  &0$4    3KDVH

RTP Project ID refers to the corresponding project identifi RTP

22 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region

3(  673 86    &1  673 86    &1  673 %5    5:  673 %5    3KDVH

RTP Project ID refers to the corresponding project identifi RTP

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 23

3(  1+33    3(  7$3 86 3(  673 86 3(  3(   1+333(  1+33  1+33           &1  1+33    &1  7,%&1   7$3 86    &1  &1  1+33&1 &1 673   1+33 1+33            5:  673 86    5:  7,%    3KDVH

RTP Project ID refers to the corresponding project identifi RTP

24 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region

3(  673    &1  673    &1  1+33    &1  +6,3    5:  673    673 673 673  673       3KDVH

RTP Project ID refers to the corresponding project identifi RTP

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 25

Total $45,833,254 $143,644,872 $189,478,126 3(  6WDWH/RFDO    3(  673    &1  6WDWH/RFDO&1   +6,3      &1  673    5:  6WDWH/RFDO5:   +6,3      5:  673    3KDVH

RTP Project ID refers to the corresponding project identifi RTP

26 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region TABLE 4

RTIP MPO PROJECTS

PROJECT DESCRIPTION BY AGENCY

Agencies Included:

Intercity Transit Lacey Olympia Th urston County Th urston Regional Planning Council Tumwater WSDOT Olympic Region Yelm

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 27 STIP Amend. No. August 9, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ital Preventative Maintenance. Total Project Length Environmental Project Totals 3,520,000 0 880,000 4,400,000 Imp Type Totals 4,400,000 0 0 0 0 CN 4,400,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 5307 3,520,000 0 880,000 4,400,000 Phase Start Date Federal Fund Code Funding Thurston Intercity Transit Expenditure Schedule TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: 002019 Capital Preventative Maintenance FY 2019 Sec. 5307 Direct Allocation formula funds (FTA) for Cap WA-11450 23 0.000 CE No NA N/A 4,400,000 Func Cls

28 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 9, 2018 Total Est. Cost of Project End Termini ealthy ps students and ing and bicycling Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ne trips to school and builds the next generation of safe h le forms of transportation, and positively influences safe walk ling around schools. blished, school-based public education and outreach program hel Total Project Length Environmental Project Totals 95,000 0 14,827 109,827 Imp Type Totals 0 109,827 0 0 0 PE 0 109,827 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 CMAQ 95,000 0 14,827 109,827 Phase Start Date Federal Fund Code Thurston Intercity Transit TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: behavior and improves air quality by reducing congestion id Func Cls families to access their community through active and sustainab 002020 Youth Education Program - Walk N Roll The Walk N Roll Safe Routes to School program reduces drive-alo pedestrians, cyclists, and transit users. This continuing, esta WA-10895 23 0.000 CE No NA N/A 109,827

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 29 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini tation and a traffic signal P Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ansion - Phase 2 ol Service Center, new fuel and wash buildings, installation of Maintenance, Operations and Administrative Base (MOA) Rehabili funding programmed reflects the funds within span of TI Total Project Length Environmental Project Totals 2,297,846 0 2,587,777 4,885,623 Imp Type Totals 1,700,000 2,100,000 1,085,623 0 10,301,265 ALL 1,700,000 2,100,000 1,085,623 0 10,301,265 Phase 1st 2nd 3rd 4th & 6th 5th CNCN 2019 2021 5339 STP(US) 1,375,000 922,846 0 0 2,443,750 144,027 3,818,750 1,066,873 Phase Start Date Federal Fund Code Thurston Intercity Transit Funding TRPC Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 00Pattison Maintenance and Operations Base Rehabilitation Exp This project completes the North Site (Phase 2) of Pattison WA-09457 23 EA No NA NA 27,376,519 Expansion project including development of a new regional Vanpo and related site improvements. This is a multiyear project Func Cls

30 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 9, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type Total Project Length Environmental Project Totals 491,320 0 76,680 568,000 Imp Type Totals 0 0 568,000 0 0 CN 0 0 568,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CNCN 2021 2021 STP(US) CMAQ 368,490 122,830 0 0 57,510 19,170 426,000 142,000 Phase Start Date Federal Fund Code Expenditure Schedule Thurston Intercity Transit TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00Propane-Fueled Vans for Dial-A-Lift Service Purchase of 4 Propane-Fueled Vans for Dial-A-Lift service. WA-11464 23 DCE No N/A N/A 568,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 31 STIP Amend. No. August 9, 2018 Total Est. Cost of Project End Termini strategies en College se vehicles and transit Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type upgrades, optimize and, where appropriate, implement operating n from West Bay Drive to Cooper Point Road. dor from College Street to Marvin Road, along Road betwe Implementation: Phase III Total Project Length Environmental vidual traffic signals to reduce travel delay for general purpo Project Totals 268,000 0 41,827 309,827 Imp Type Totals 0 0 309,827 0 0 PE 0 0 309,827 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 CMAQ 268,000 0 41,827 309,827 Phase Start Date Federal Fund Code Intercity Transit Thurston TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00Smart Corridor Signal Optimization and Transit Priority including additional transit signal priority treatments at indi vehicles for signals along and adjacent to the Martin Way corri Street and near Interstate 5, along adjacent to Harriso WA-10911 24 CE No Various Various 309,827 Update signal timing plans, deploy equipment and communication

32 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini their community clists, and transit oves air quality by Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type builds the next generation of safe and healthy pedestrians, cy ion and outreach program helps students families to access itively influences safe walking and bicycling behavior impr Total Project Length Environmental Project Totals 218,000 0 34,023 252,023 Imp Type Totals 0 0 252,023 0 0 PE 0 0 252,023 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 TAP(US) 218,000 0 34,023 252,023 Phase Start Date Federal Fund Code Thurston Intercity Transit Expenditure Schedule TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00Walk N Roll for 2021/2022 and 2022/2023 The Walk N Roll program reduces drive-alone trips to school and IT-1605 23 DCE No N/A N/A 252,023 users. This continuing, established, school-based public educat through active and sustainable forms of transportation, pos reducing congestion and idling around schools.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 33 STIP Amend. No. July 31, 2018 Total Est. Cost of Project en 5,600,000 End Termini required. Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type both corridors. The project also includes ADA improvements as Total Project Length Environmental Project Totals 3,825,000 0 1,275,000 5,100,000 Imp Type Totals 5,100,000 0 0 0 0 CN 5,100,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th CN 2019 NHPP 3,825,000 0 1,275,000 5,100,000 Phase Start Date Federal Fund Code Thurston Lacey TRPC Y Inside N Outside Funding Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 14College St and Yelm Hwy Super “T” Pavement Rehabilitation 9934(022)This project will provide a complete pavement rehabilitation on Lacey17001 05 2.500 CE No Ruddell Rd/City Limits 37th/Mull Func Cls

34 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. July 31, 2018 Total Est. Cost of Project End Termini e SE. Future ple phases with the left turn lanes, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type bout. rainage improvements. The project will be constructed in multi iden the roadway to include a planted center median, auxiliary control at 16th Avenue, 22nd Avenue and 29th Avenu Total Project Length Environmental Project Totals 446,511 630,000 5,223,489 6,300,000 Imp Type Totals 3,000,000 3,000,000 300,000 0 0 CN 3,000,000 3,000,000 300,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CNCNCN 2019CN 2019 2019 2019 STP(US) TAP(US) 302,961 143,550 0 Ped/Bike Program 0 630,000 0 218,458 0 40,900 848,458 19,379 0 343,861 162,929 4,944,752 4,944,752 Phase Start Date Federal Fund Code Funding Expenditure Schedule TRPC Y Inside N Outside Thurston Lacey County: Agency: Project Number PIN ID STIP MPO/RTPO: phases will be constructed as funding becomes available. The project will involve landscaping, excavation, paving, and d first phase being the construction of 22nd Avenue SE rounda Func Cls 14College Street Corridor -- Phase 1 5289(004)Per the 2009 College Street Corridor Study, this project will w sidewalks, with typical urban amenities. This includes traffic Lacey11001 21 2.000 CE Yes Lacey Blvd 37th Ave SE 8,200,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 35 STIP Amend. No. July 31, 2018 Total Est. Cost of Project End Termini left turn lanes, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type iden the roadway to include a planted center median, auxiliary ic control at 16th Avenue SE. Total Project Length Environmental Project Totals 905,180 0 141,271 1,046,451 Imp Type Totals 0 200,000 400,000 400,000 0 PE 0 200,000 400,000 400,000 0 Phase 1st 2nd 3rd 4th 5th & 6th PEPE 2020 2020 STP(US) HIP(US) 318,853 586,327 0 0 49,445 91,826 368,298 678,153 Phase Start Date Federal Fund Code Expenditure Schedule Funding TRPC Y Inside N Outside Thurston Lacey County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 14College Street Corridor Improvements Phase 3 Per the 2009 College Street Corridor Study, this project will w Lacey19001 04 0.400 CE No 18th Avenue Lacey Blvd 7,000,000 sidewalks, with typical urban amenities. This includes a traff

36 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. July 31, 2018 Total Est. Cost of Project End Termini State Funds Local Funds Total s. Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Federal Funds Type install electric vehicle charging stations at public facilitie Total Project Length Environmental Project Totals 281,990 0 44,010 326,000 Imp Type Agency Totals for Lacey 5,458,681 630,000 6,683,770 12,772,451 Totals 0 26,000 0 300,000 0 PE 0 25,000 0 0 0 CN 0 0 0 300,000 0 RW 0 1,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 CMAQ 21,625 0 3,375 25,000 CN 2022 CMAQ 259,500 0 40,500 300,000 RW 2020 CMAQ 865 0 135 1,000 Phase Start Date Federal Fund Code Thurston Lacey Funding TRPC Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 00Electric Vehicle Charging Stations Partnered with North Thurston Public Schools. This project will Lacey19002 44 0.000 CE Yes C/L C/L 326,000 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 37 STIP Amend. No. August 1, 2018 Total Est. Cost of Project End Termini State Funds Local Funds Total lities. Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Federal Funds Type s management, and safe inviting bicycle pedestrian faci Total Project Length Environmental Project Totals 1,176,803 0 184,897 1,361,700 Imp Type Agency Totals for Olympia 1,176,803 0 184,897 1,361,700 Totals 0 1,361,700 0 0 0 PE 0 1,361,700 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 STP(US) 1,176,803 0 184,897 1,361,700 Phase Start Date Federal Fund Code Funding TRPC Y Inside N Outside Thurston Olympia Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 16Fones Road - Transportation Improvements will address vehicle capacity, truck access, acces Oly1102a 03 0.670 CE Yes 18th Avenue Pacific Avenue 15,840,900 Func Cls

38 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type oad at 15th Avenue SE. Total Project Length Environmental Project Totals 68,950 0 11,550 80,500 Imp Type Totals 0 80,500 0 0 0 PE 0 14,000 0 0 0 CN 0 66,500 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 TAP(US) 11,991 0 2,009 14,000 CN 2020 TAP(US) 56,959 0 9,541 66,500 Phase Start Date Federal Fund Code TRPC Y Inside N Outside Thurston Olympia Expenditure Schedule Funding County: Agency: Project Number PIN STIP ID MPO/RTPO: Func Cls 16School Speed Limit Zone Flashing Beacon Installation Project Install school speed limit zone flashing beacons on R Oly1801b 28 0.110 CE No 15th Avenue NA 80,500

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 39 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini drail. Install Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type t removal, etc …). Install rumble strips. Install/upgrade guar Total Project Length Environmental Project Totals 1,089,000 0 121,000 1,210,000 Imp Type Totals 1,210,000 0 0 0 0 CN 1,210,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 HSIP 1,089,000 0 121,000 1,210,000 Phase Start Date Federal Fund Code Expenditure Schedule TRPCThurston Thurston Co. Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 002018 Highway Safety Improvement Program 000S(506)Roadside improvements (e.g., guardrail, slope flattening, objec WA-06695 21 CE No Various Various 1,435,000 illumination.

40 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 10, 2018 Total Est. Cost of Project End Termini ill include installation Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type lternative analysis will identify the structure type. Project w rail and traffic control devices. Total Project Length Environmental Project Totals 500,000 0 370,000 870,000 Imp Type Totals 100,000 770,000 0 0 0 PE 100,000 20,000 0 0 0 CN 0 750,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2019 0 0 120,000 120,000 CN 2021 STP(R) 500,000 0 250,000 750,000 Phase Start Date Federal Fund Code Funding Thurston Thurston Co. TRPC Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 08Case Rd Fish Barrier Removal Replacement of Case Rd culvert for fish passage enhancement. A WA-11041 44 0.100 CE Yes At Culvert At Culvert 870,000 Func Cls of the structure and all necessary road improvements i.e. guard

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 41 STIP Amend. No. September 20, 2018 Total Est. Cost of Project Carpenter Road 8,094,017 End Termini scaping, in each direction for ject limits. stalled at Carpenter Rd to Station 33) Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type The project will have sidewalks, bike lanes and a travel es and sidewalks on both sides, additional , land t standards. Illumination will be installed throughout the pro Total Project Length Environmental cessary along portions of the project. A roundabout will be in Project Totals 2,000,000 4,100,000 600,000 6,700,000 Imp Type Totals 6,700,000 0 0 0 0 CN 6,700,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 STP(US) 2,000,000 TIB 4,100,000 600,000 6,700,000 Phase Start Date Federal Fund Code Funding TRPC Y Inside N Outside Thurston Thurston Co. Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: illumination, drainage improvements and other associated work. the entirety of project limits. Retaining walls will be ne 16 5292(004)Mullen Road Reconstruction Reconstruct roadway and widen 2 travel lanes to add bicycle lan WA-04780 03 0.890 CE Yes Lacey City Limits (vic Fire Func Cls improve safety and operations. All stormwater will meet curren

42 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini urbing, school zone Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type /outreach. ., speed cushions, traffic circle), pavement markings, signs, c Total Project Length Environmental Project Totals 810,000 0 90,000 900,000 Imp Type Totals 900,000 0 0 0 0 CN 900,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th CN 2019 TAP(SR) 810,000 0 90,000 900,000 Phase Start Date Federal Fund Code Funding Expenditure Schedule TRPCThurston Thurston Co. Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: 09Olympic View Elem/Thompson Pl Neighborhood SR Enhancement 9934(023)The project includes but is not limited to (e.g WA-09496 21 CE No NA NA 1,030,000 flashing beacons, ADA improvements, illumination, and education Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 43 STIP Amend. No. September 20, 2018 8,000 Total Est. Cost of Project End Termini study, design and Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ngle span bridge. Project includes type, size, location (TSL) Total Project Length Environmental Project Totals 1,709,000 0 271,500 1,980,500 Imp Type Totals 62,500 1,918,000 0 0 0 CN 0 1,918,000 0 0 0 RW 62,500 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2020 STP(BR) 1,659,000 0 259,000 1,918,000 RW 2019 STP(BR) 50,000 0 12,500 62,500 Phase Start Date Federal Fund Code Expenditure Schedule Funding Thurston Thurston Co. TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 09Reeder Road Bridge (R-3) 2034(081)Remove existing Reeder Rd Bridge entirely and replace with a si WA-09538 11 0.120 CE Yes Mile Post 1.21 Mile Post 1.33 2,42 construction. Right of Way acquisition is possible.

44 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. October 3, 2018 Total Est. Cost of Project End Termini he future creation Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type in the 2007 Regional Trials Plan. chester and Grand Mound. This study lays the ground work for t Total Project Length Environmental Project Totals 150,000 0 25,000 175,000 Imp Type Totals 0 0 125,000 50,000 0 PE 0 0 125,000 50,000 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 STP(R) 150,000 0 25,000 175,000 Phase Start Date Federal Fund Code TRPC Y Inside N Outside Expenditure Schedule Thurston Co. Thurston Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00Rochester-Grand Mound Trail Feasibility Study The project will examine potential trail connections between Ro of a Rochester-Grand Mound Trail and is the next step outlined WA-11387 18 CE No Rochester Grand Mound 175,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 45 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini tion mobility in Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type tem. The study will result in a strategy to address transporta the County. Total Project Length Environmental Project Totals 300,000 0 50,000 350,000 Imp Type Totals 0 0 165,000 185,000 0 PE 0 0 165,000 185,000 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 STP(R) 300,000 0 50,000 350,000 Phase Start Date Federal Fund Code Thurston Thurston Co. TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls urban/rural transition areas and strategy corridors throughout 00Thurston County Mobility Strategy To address future transportation needs on the County's road sys WA-10898 18 CE No Various Various 350,000

46 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 00 Total Est. Cost of Project End Termini ndabout, illumination, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type y of major roadway realignment, additional lanes, signal or rou Total Project Length Environmental Project Totals 1,300,000 0 700,000 2,000,000 Imp Type Totals 0 0 0 2,000,000 0 CN 0 0 0 2,000,000 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2022 STP(US) 1,300,000 0 700,000 2,000,000 Phase Start Date Federal Fund Code Funding Expenditure Schedule Thurston Thurston Co. TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: 16Yelm Highway and Meridian Improvements Reconstruction, added capacity project including the possibilit WA-01367 03 0.100 CE Yes I/S Meridian Rd SE I/S Yelm Highway 2,500,0 drainage facilities, landscaping and other safety features. Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 47 STIP Amend. No. August 10, 2018 Total Est. Cost of Project E 650,000 End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type mps and sidewalks. Total Project Length Environmental Project Totals 475,000 0 165,752 640,752 Imp Type Totals 0 0 95,000 545,752 0 PE 0 0 95,000 95,752 0 CN 0 0 0 450,000 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 STP(US) 165,000 0 25,752 190,752 CN 2022 STP(US) 310,000 0 140,000 450,000 Phase Start Date Federal Fund Code Funding Thurston Thurston Co. Expenditure Schedule TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: 07Yelm Hwy SE and Pacific Ave Pedestrian Improvements Phase 1 Project will construct pedestrian refuge islands and upgrade ra WA-11382 38 0.800 CE No Lacey City Limits (MP 3.4) Union Mills Rd S Func Cls

48 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. July 30, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type d transportation initiatives. See TRPC UPWP. Total Project Length Environmental Project Totals 700,000 0 109,249 809,249 Imp Type Totals 809,249 0 0 0 0 PE 809,249 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2019 STP(US) 700,000 0 109,249 809,249 Phase Start Date Federal Fund Code Funding Expenditure Schedule TRPCThurston TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: 002019-2020 Regional Transportation Planning Priorities Planning activities in the work program of regionally determine WA-10738 18 0.000 DCE No NA NA 809,249 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 49 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini dal safety and oint planning study Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type , City of Olympia, Lacey, and Intercity Transit. ia and College Street in Lacey. The study will examine multimo ronmental, and economic development considerations. This is a j Total Project Length Environmental Project Totals 452,750 0 70,660 523,410 Imp Type Totals 0 261,705 261,705 0 0 PE 0 261,705 261,705 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 STP(US) 452,750 0 70,660 523,410 Phase Start Date Federal Fund Code TRPC Y Inside N Outside Expenditure Schedule Thurston TRPC Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: mobility issues, and incorporate transportation, land use, envi 00Martin Way Corridor Study A corridor study of Martin Way, between Pacific Avenue in Olymp WA-11595 18 0.000 CE No NA NA 523,410 Func Cls between the Thurston Regional Planning Council, County

50 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. July 30, 2018 Total Est. Cost of Project End Termini e Olympia Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type argeting top/mid-level managers at state agency worksites on th options and am/pm schedule shifts for state employees. Total Project Length Environmental Project Totals 154,180 0 21,570 175,750 Imp Type Totals 0 0 0 175,750 0 PE 0 0 0 175,750 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2022 CMAQ 154,180 0 21,570 175,750 Phase Start Date Federal Fund Code Funding Thurston TRPC Expenditure Schedule TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: Capitol Campus to increase adoption of mobile/flexible/telework 00Olympia Capitol Campus - Taming the Dragons An intense Travel Demand Management outreach/education effort t WA-10943 44 0.000 CE No NA NA 175,750 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 51 STIP Amend. No. July 30, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds ater Schools Type s in North Thurston, Olympia, and Tumwater School Districts. Total Project Length Environmental Project Totals 51,900 0 8,100 60,000 Imp Type Totals 0 60,000 0 0 0 PE 0 60,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 TAP(US) 51,900 0 8,100 60,000 Phase Start Date Federal Fund Code Expenditure Schedule TRPC Y Inside N Outside Thurston TRPC Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00School Walk Route Mapping for North Thurston, Olympia, and Tumw Create detailed school walking route maps for elementary WA-11503 38 0.000 CE No NA NA 60,000

52 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. July 30, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type fer both print and electronic versions to the public. Total Project Length Environmental Project Totals 38,925 0 6,075 45,000 Imp Type Totals 0 45,000 0 0 0 PE 0 45,000 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2020 STP(R) 38,925 0 6,075 45,000 Phase Start Date Federal Fund Code Expenditure Schedule TRPCThurston TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 00Thurston County Bicycle Map, 7th Edition This project will update the Thurston County Bicycle Map and of WA-11502 38 0.000 CE No NA NA 45,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 53 STIP Amend. No. August 22, 2018 Total Est. Cost of Project End Termini lvd): Pavement lvd/Old Hwy 99) h segment (Capitol ramps and replace Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ut the City including: Tumwater Blvd (Interstate 5 to Capitol B edestrian signals and; Old Hwy 99 (Henderson Blvd to Tumwater B epair, pre-level, crack seal and resurfacing; Capitol Blvd nort nel repair, overlay with fiber-reinforced , upgrade Total Project Length Environmental Project Totals 2,427,000 0 1,073,000 3,500,000 Imp Type Totals 202,000 3,298,000 0 0 0 PE 202,000 10,000 0 0 0 CN 0 3,288,000 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2019 NHPP 180,200 0 31,800 212,000 CN 2020 NHPP 2,246,800 0 1,041,200 3,288,000 Phase Start Date Federal Fund Code Expenditure Schedule Thurston Tumwater TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 14Citywide NHS Resurfacing Resurfacing and rehabilitation of various NHS segments througho repair, pre-level and fiber-reinforced asphalt overlay. WA-11658 05 2.510 CE No Various Various 3,500,000 and Capitol Blvd south segment (Israel Rd to X St): pavement r Blvd Bridge to Carlyon/Sunset): Planing, selective pa curb and gutter where required, relocate, upgrade or add p

54 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 3, 2018 Total Est. Cost of Project 11,900,000 per, Multiple, See Project Description End Termini th of Ruby to 340' t from Capitol to a Description Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds at I-5/6th Ave, construct new roadway between West Lee and Tros Type ' east of Capitol (Trosper), Lee to Trosper (6th Ave), 100' nor Ruby St to Trosper Rd extension. Capitol, construct RAB at Trosper/Capitol, reconstruct Linda S nda St) Total Project Length Environmental Project Totals 0 6,664,000 5,236,000 11,900,000 Imp Type Totals 5,500,000 3,400,000 3,000,000 0 0 PE 850,000 150,000 0 0 0 CN 0 3,250,000 3,000,000 0 0 RW 4,650,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2019 0 TIB 560,000 440,000 1,000,000 CN 2020 0 TIB 3,500,000 2,750,000 6,250,000 RW 2019 0 TIB 2,604,000 2,046,000 4,650,000 Phase Start Date Federal Fund Code Thurston Tumwater Expenditure Schedule TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 14I-5 / Trosper Rd Capitol Blvd Reconfiguration Modify I-5 NB Off-Ramp and southerly On-Ramp, construct RAB reconstruct Trosper from I-5 to Capitol, extend east of new local access road and construct from WA-07854 01 0.910 CE Yes Multiple, See Project Termini: NB Off-Ramp and southerly On-Ramp (I-5), I-5 to 470 north of Trosper (Capitol), Capitol to 425' east (Li

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 55 STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini d curb ramps, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type ents. (s), reconstruction of select segments an Total Project Length Environmental Project Totals 400,000 0 95,000 495,000 Imp Type Totals 0 20,000 20,000 455,000 0 PE 0 20,000 20,000 0 0 CN 0 0 0 455,000 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2020 TAP(US) 30,000 0 10,000 40,000 CN 2022 TAP(US) 370,000 0 85,000 455,000 Phase Start Date Federal Fund Code Expenditure Schedule Thurston Tumwater TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 17Israel Rd & Linderson Way Pedestrian and Bicycle Improvements Roadway and multi-modal improvements including construction of add bike lanes, signal improvements, roadway and other improvem WA-11046 28 0.200 CE No 400' s/o Israel Rd New Market St 495,000

56 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 3, 2018 Total Est. Cost of Project End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type way 99 and 79th Avenue. Total Project Length Environmental Project Totals 657,000 0 183,000 840,000 Imp Type Totals 0 100,000 200,000 540,000 0 PE 0 100,000 200,000 100,000 0 RW 0 0 0 440,000 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2020 STP(US) 346,000 0 54,000 400,000 RW 2022 STP(US) 311,000 0 129,000 440,000 Phase Start Date Federal Fund Code Expenditure Schedule TRPCThurston Tumwater Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 16Old Hwy 99 / 79th Ave Roundabout Design and construct roundabout at the intersection of Old High WA-11034 21 0.350 CE Yes Old Highway 99 79th Avenue 2,500,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 57 STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini vice life of the Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type il ov/projects/search. erve the structural integrity of roadway and extend ser Total Project Length Environmental Project Totals 9,758,045 0 204,586 9,962,631 Imp Type Totals 5,158,863 303,262 3,315,643 1,184,863 2,168,270 PE 0 303,262 77,603 109,250 464,173 CN 5,158,863 0 3,238,040 1,075,613 1,704,097 Phase 1st 2nd 3rd 4th & 6th 5th PEPEPE 2020 2021 2022 NHPP NHPP NHPP 291,598 74,618 105,048 0 0 0 11,664 2,985 4,202 303,262 77,603 109,250 CNCNCN 2019CN 2019 2021 2022 NHPP STP NHPP NHPP 2,588,307 2,469,402 3,174,549 1,054,523 0 0 0 0 51,766 49,388 63,491 21,090 2,640,073 2,518,790 3,238,040 1,075,613 Phase Start Date Federal Fund Code WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: pavement. For a list of included projects, go to www.wsdot.wa.g Resurface the roadway with chip seal or hot mix asphalt to pres Func Cls 00Asphalt/Chip Seal Preservation Thurston Regional Planning Counc BPTRPC BPTRPC 05 CE No Various Various 12,130,901

58 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini up to current seismic Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type This project will seismically retrofit this bridge to bring it ring an earthquake. Seismic retrofit bridge 5/332. Total Project Length Environmental Project Totals 863,315 0 17,619 880,934 Imp Type Totals 880,934 0 0 0 0 CN 880,934 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 NHPP 863,315 0 17,619 880,934 Phase Start Date Federal Fund Code TRPC Y Inside N Outside Expenditure Schedule Funding WSDOT - OLY County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 11I-5/I-5 Over Pacific Ave - Seismic Retrofit 0052(217) 300513SThis structure does not meet current seismic design standards. design standards and reduce the risk of catastrophic failure du 300513S-34 40 0.060 CE No 107.45 107.51 1,082,913

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 59 STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini the compression the service life of Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type eful life span and need to be rehabilitated. By rehabilitating t on 005/345W. this project will preserve the structural integrity and extend Total Project Length Environmental Project Totals 297,486 0 7,057 304,543 Imp Type Totals 0 48,338 256,205 0 0 PE 0 48,338 0 0 0 CN 0 0 256,205 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PE 2020 NHPP 46,405 0 1,933 48,338 CN 2021 NHPP 251,081 0 5,124 256,205 Phase Start Date Federal Fund Code WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 11I-5/Nisqually River Bridge - Special Repairs Expansion joints of bridge 5/354W on I-5 have exceeded their us seal/concrete headers and steel sliding plate expansion joints 300502P 300502P-34 14 0.040 CE No 114.84 114.88 304,543 structure. Expansion joints, concrete headers & bulb-

60 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 15, 2018 Total Est. Cost of Project 57,160,300 320,754 57,481,054 End Termini A Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type to a Diverging Diamond configuration. Total Project Length Environmental Project Totals 0 57,160,300 320,754 57,481,054 Imp Type Totals 57,481,054 0 0 0 0 CN 57,481,054 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th CN 2019 0 CW Phase Start Date Federal Fund Code WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 11I-5/SR 510 - Reconstruct This project is looking at converting the existing interchange 300502C 300502C34 03 2.360 EA Yes 110.14 112.50 72,000,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 61 STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini erity of fatal and e entering vehicles, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type se dynamic warning signs will alert mainline drivers of possibl th inadequate gaps. This project will reduce the number and sev Total Project Length Environmental Project Totals 204,627 0 5,166 209,793 Imp Type Totals 0 0 48,493 161,300 0 PE0048,49300 CN 0 0 0 161,300 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 HSIP 46,553 0 1,940 48,493 CN 2022 HSIP 158,074 0 3,226 161,300 Phase Start Date Federal Fund Code Expenditure Schedule WSDOT - OLY TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: 00Olympic Region - Dynamic Warning Signs Three intersections have been identified on the ISIP List. The giving them time to react side street vehicles that enter wi 300092E 300092E-34 21 0.000 CE No Various Various 209,793 Func Cls serious injury crashes.

62 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini ve removal e fails to act as they Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type meet NCHRP 350 specifications, and has been identified for acti otoring public and reduces the risk to agency. ier and replace these devices before they are hit the devic Total Project Length Environmental Project Totals 447,218 0 9,127 456,345 Imp Type Totals 456,345 0 0 0 0 CN 456,345 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 HSIP 447,218 0 9,127 456,345 Phase Start Date Federal Fund Code Expenditure Schedule Funding TRPCWSDOT - OLY Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: were intended. Replacing them will increase the safety of m Func Cls 00OR Breakaway Cable Terminal Replacement - Interstate 9999(821) 300018BThe breakaway cable terminal (W-Beam terminal) design does not since 1994. This project will complete the work identified earl 300018B-34 21 43.250 CE No 096.24 139.49 537,501

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 63 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini ve removal e fails to act as they Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type meet NCHRP 350 specifications, and has been identified for acti otoring public and reduces the risk to agency. ier and replace these devices before they are hit the devic Total Project Length Environmental Project Totals 105,246 0 2,148 107,394 Imp Type Totals 107,394 0 0 0 0 CN 107,394 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 HSIP 105,246 0 2,148 107,394 Phase Start Date Federal Fund Code Funding WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: 00OR Breakaway Cable Terminal Replacement - Non-Interstate 9999(821) 300018CThe breakaway cable terminal (W-Beam terminal) design does not since 1994. This project will complete the work identified earl 300018C-34were intended. Replacing them will increase the safety of m 21 CE No Various Various 123,967 Func Cls

64 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini itive areas and treatment Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type d Filter Strips, highway runoff will be directed away from sens . By replacing existing catch basins with mechanical stormwater Total Project Length Environmental Project Totals 274,436 0 2,473 276,909 Imp Type Totals 276,909 0 0 0 0 CN 276,909 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th CN 2019 STP 274,436 0 2,473 276,909 Phase Start Date Federal Fund Code Funding Expenditure Schedule TRPC Y Inside N Outside WSDOT - OLY County: Agency: Project Number PIN ID STIP MPO/RTPO: 00Pierce/Thurston County - Stormwater Retrofit 9999(736) 300090JStormwater runoff leaves the right of way without being treated structures, and installing curbing Compost Amended Vegetate 300090J34prevent erosion. 20 0.030 CE No 020.40 020.47 551,569 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 65 STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini vert providing improved Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type . Replace existing culvert #1130818. l failure. This project will replace or repair the existing cul Total Project Length Environmental Project Totals 259,682 0 8,316 267,998 Imp Type Totals 0 0 147,794 120,204 0 PE 0 0 147,794 0 0 CN 0 0 0 120,204 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2021 STP 141,882 0 5,912 147,794 CN 2022 STP 117,800 0 2,404 120,204 Phase Start Date Federal Fund Code WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 07SR 507/N of Connor Rd - Culvert Replacement The existing culvert in this location is experiencing structura 350734A 350734A-34 21 0.010 CE No 007.95 007.96 267,998 drainage and preserving the structural integrity of roadway

66 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini d has the Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type rb ramps to current standards will improve pedestrian access an Total Project Length Environmental Project Totals 590,299 0 13,631 603,930 Imp Type Totals 0 0 0 603,930 0 PE 0 0 0 77,577 0 CN 0 0 0 510,973 0 RW 0 0 0 15,380 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2022 STP 74,474 0 3,103 77,577 CN 2022 STP 500,753 0 10,220 510,973 RW 2022 STP 15,072 0 308 15,380 Phase Start Date Federal Fund Code Funding Expenditure Schedule TRPC Y Inside N Outside WSDOT - OLY County: Agency: Project Number PIN ID STIP MPO/RTPO: potential to improve safety. 16SR 510/S of Sitka St SE to Berry Valley Rd - ADA Compliance ADA curb ramps do not meet current standards. Upgrading cu 351002B 351002B34 21 6.590 CE Yes 004.47 015.20 603,930 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 67 STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini potential to reduce Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type afety. is Location. By constructing a roundabout, this project has the Total Project Length Environmental Project Totals 2,551,015 0 72,643 2,623,658 Imp Type Totals 2,623,658 0 0 0 0 CN 2,623,658 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 HSIP 2,551,015 0 72,643 2,623,658 Phase Start Date Federal Fund Code WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 16SR 510/Meridian Rd SE - Roundabout 0510(017) 351033AThis intersection has been identified as an Intersection Analys 351033A34 21 0.010 CE Yes 006.95 006.96 3,395,340 the frequency and severity of collisions improve motorist s

68 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project End Termini d has the Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type rb ramps to current standards will improve pedestrian access an Total Project Length Environmental Project Totals 590,299 0 13,631 603,930 Imp Type Totals 0 0 0 603,930 0 PE 0 0 0 77,577 0 CN 0 0 0 510,973 0 RW 0 0 0 15,380 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2022 STP 74,474 0 3,103 77,577 CN 2022 STP 500,753 0 10,220 510,973 RW 2022 STP 15,072 0 308 15,380 Phase Start Date Federal Fund Code Funding TRPCWSDOT - OLY Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN STIP ID MPO/RTPO: 16SR 510/S of Sitka St SE to Berry Valley Rd - ADA Compliance ADA curb ramps do not meet current standards. Upgrading cu potential to improve safety. 351002B 351002B34 21 6.590 CE Yes 004.47 015.20 603,930 Func Cls

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 69 STIP Amend. No. August 15, 2018 Total Est. Cost of Project 3,200,0001,093,000 0 0 3,200,000 1,093,000 50,200,000 0 50,200,000 End Termini new alignment for SR A A A Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type relieve congestion and improve motorist safety. present time. This project will construct the second stage of a Total Project Length Environmental Project Totals 0 54,493,000 0 54,493,000 Imp Type Totals 4,293,000 50,200,000 0 0 0 PE 3,200,000 0 0 0 0 CN 0 50,200,000 0 0 0 RW 1,093,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PE 2019 0 CW CN 2020 0 CW RW 2019 0 CW Phase Start Date Federal Fund Code Expenditure Schedule WSDOT - OLY TRPC Y Inside N Outside Funding County: Agency: Project Number PIN ID STIP MPO/RTPO: 16SR 510/Yelm Loop - New Alignment Phase 2 Traffic through the City of Yelm is extremely congested at 351029A 351029A34 01 0.980 EIS Yes 14.69 15.67 58,500,000 Func Cls 510 through the City of Yelm. When complete, this project will

70 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. August 15, 2018 Total Est. Cost of Project End Termini ntial to State Funds Local Funds Total mplementing Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required 18,552,479 111,653,300 730,636 130,936,415 Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Federal Funds onal improvements along the corridor, this project has pote Y Type ysis Corridor. By constructing a roundabout at Anderson Road, i Total Project Length Environmental Project Totals 2,564,047 0 52,328 2,616,375 Imp Type Totals 2,616,375 0 0 0 0 Agency Totals for WSDOT - OL CN 2,491,680 0 0 0 0 RW 124,695 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2019 HSIP 2,441,846 0 49,834 2,491,680 RW 2019 HSIP 122,201 0 2,494 124,695 Phase Start Date Federal Fund Code Funding WSDOT - OLY TRPC Y Inside N Outside Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: access management improvements at Moon Road, and other operati reduce the frequency of collisions and enhance motorist safety. Func Cls 02US 12/Anderson Rd to Moon - Safety Improvement 0012(230) 301201GThis section of highway has been identified as a Collision Anal 301201G34 21 1.500 CE Yes 038.50 040.00 3,206,000

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 71 STIP Amend. No. September 20, 2018 Total Est. Cost of Project 816,729 ewalks and End Termini Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type theast and Grove Road near Fort Stevens Elementary with new sid Total Project Length Environmental Project Totals 133,320 0 20,807 154,127 Imp Type Totals 0 154,127 0 0 0 CN 0 154,127 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th CN 2020 STP(US) 133,320 0 20,807 154,127 Phase Start Date Federal Fund Code Funding TRPC Y Inside N Outside Thurston Yelm Expenditure Schedule County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 16Fort Stevens Elementary - Pedestrian Improvements 1495(005)Improve safety for students and pedestrians along 100th Way Sou WA-09793 28 0.340 CE No 100th St SE 200' North 100th CT SE ADA compliant facilities.

72 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region STIP Amend. No. September 20, 2018 Total Est. Cost of Project 1,783,622 ike End Termini to Solberg St, Begin Termini State Fund Code State Funds Local Funds Total 2019 to 2022 RW Required Washington State S. T. I. P. (Project Funds to Nearest Dollar) Federal Funds Type d St Longmire St with the new Mosman Avenue intersection. Will add b Improvements include construction of new road from Longmire St Total Project Length Environmental Project Totals 338,100 0 53,872 391,972 Imp Type Totals 391,972 0 0 0 0 RW 391,972 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th RW 2019 STP(US) 338,100 0 53,872 391,972 Phase Start Date Federal Fund Code Funding Expenditure Schedule Thurston Yelm TRPC Y Inside N Outside County: Agency: Project Number PIN ID STIP MPO/RTPO: Func Cls 17Mosman Ave Phase II Y341(001)The proposed improvements will construct a new road connecting Yelm 13 01 01 0.250 CE Yes Longmire Street Railroad Street lanes,sidewalks,street lighting, and stormwater improvements. and reconstruction of Mosman Ave between Solberg St Railroa

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region 73 Table 5 TRPC MPO Projects Financial Feasibility: Cost vs. Revenue

Approved projects in the MPO TIP have commited or available revenues suffi cent to meet expected costs.

)XQG&RGH

74 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDICES

A. Other TIP Projects

B. Regional Road-Related Financial Plan For Local Agencies

C. Air Quality Analysis

D. Performance Measures

E. Public Participation Summary

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region This page left intentionally blank.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDIX A

OTHER TIP PROJECTS

This appendix contains all projects identifi ed in the adopted Transportation Improvement Programs (TIPs) for the jurisdictions and agencies within Thurston County for the years 2019 through 2024, with the exception of those included in Table 4 of this document. The projects in this appendix, along with Table 4 , represent our region’s priority transportation needs. Unlike the projects listed in Tables 4 , the projects in this appendix are not included in the Statewide Transportation Improvement Program (STIP). Please note that once federal or state projects receive funding and are underway, they are no longer included in the adopted TIPs, the Regional Transportation Improvement Program (RTIP), or the STIP.

Consistency with the Regional Transportation Plan

In many ways, the projects identifi ed in Table 4 and Appendix A represent a short-range implementation strategy for the long-range goals embodied in the 2040 Thurston Regional Transportation Plan: What Moves You. While there is overlap between the project lists in the two documents, they serve diff erent scopes and timeframes, and therefore are not comparable.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-1 This page left intentionally blank.

A-2 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region BUCODA Planned Projects Bucoda will seek funding. Planned projects for which for Planned projects

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-3 This page left intentionally blank.

A-4 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-4 06/28/18 06/28/18 2018-02 03 P T W 0.050 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 68,000 6,000 74,000 . PIN/Project No. Totals 74,000 0 0 0 0 4th Street widen and drainage. 4th Street East River Street to Market Widen, install drainage, overlay. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description A Bucoda Thurston TRPC Y Inside N Outside

Priority Number PE 74,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 OTHER 68,000 6,000 74,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 4 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-5 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-9 06/28/18 06/28/18 2018-02 06 P T W 0.060 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 15,000 0 1,000 16,000 . PIN/Project No. Totals 16,000 0 0 0 0 5th Street Sidewalk Extension 5th Street River Street North to Perkins Install / repair sidewalk. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number CN 16,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2019 CDBG 15,000 0 1,000 16,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 9 MPO/RTPO: Class Funding Expenditure Schedule

A-6 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-8 06/28/18 06/28/18 2018-02 32 P T W 0.400 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 184,000 10,000 194,000 . PIN/Project No. Totals 194,000 0 0 0 0 A 7th Street East Sidewalks and Drainage 7th Street East Main Street South to River Install drainage and replace / repair sidewalks. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 194,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 184,000 10,000 194,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 06 8 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-7 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-16 06/28/18 06/28/18 2018-02 32 P T W 0.400 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 36,000 36,000 . PIN/Project No. Totals 36,000 0 0 0 0 7th Street East Stormwater Repair 7th Street East Main Street South to River Stormwater drainage / repair. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number PE 36,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 0 36,000 36,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 16 MPO/RTPO: Class Funding Expenditure Schedule

A-8 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-10 06/28/18 06/28/18 2018-02 03 P T W 0.260 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 449,000 23,000 472,000 7th Street West to Thurman St/ Abby Lane . PIN/Project No. Totals 472,000 0 0 0 0 an . 7th Wright & 8th to Abby Lane - Update Arterial, Drainage. West 7th to Wright Street Left 8th Right Upgrade 8th Street West, Wright between 7th and 8th, A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number PE 472,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 OTHER 449,000 23,000 472,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 10 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-9 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-6 06/28/18 06/28/18 2018-02 05 P T W 0.060 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 55,000 55,000 . PIN/Project No. Totals 55,000 0 0 0 0 8th Street Widening 8th Street Market Street to River Widen 8th Street from one lane to two lanes. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 55,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 0 55,000 55,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 6 MPO/RTPO: Class Funding Expenditure Schedule

A-10 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-11 06/28/18 06/28/18 2018-02 03 P T W 0.030 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 56,000 3,000 59,000 . PIN/Project No. Totals 59,000 0 0 0 0 9th Street West Widen and Drainage 9th Street West Front Street to Wright Widen, install drainage, and overlay. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 59,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 56,000 3,000 59,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 11 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-11 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-3 06/28/18 06/28/18 2018-02 03 P T W 0.070 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 10,000 10,000 . . PIN/Project No. Totals10,0000000 Disabled Parking Main St S between 6th & 5th 6th Street East to 5th Diagonal disabled parking striping to be painted on Main Street A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number CN10,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2019 0 0 10,000 10,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 3 MPO/RTPO: Class Funding Expenditure Schedule

A-12 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-14 06/28/18 06/28/18 2018-02 03 0.170 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 230,000 12,000 242,000 k. . PIN/Project No. Totals 242,000 0 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Main Street South widening and sidewalk repair Main Street South 11th Street to 13th Widen, install drainage, and overlay. Repair / replace sidewal Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 242,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th P ALL 2019 0 OTHER 230,000 12,000 242,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 14 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-13 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-1 06/28/18 06/28/18 2018-02 06 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 44,000 44,000 the town limits. . PIN/Project No. Totals 7,330 7,330 0 0 0 Miscellaneous and Repairs Multiple City-Wide to East 7th Street Repair of miscellaneous potholes and shoulders as needed within A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 7,330 7,330 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 0 44,000 44,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 1 MPO/RTPO: Class Funding Expenditure Schedule

A-14 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-5 06/28/18 06/28/18 2018-02 07 P T W 0.800 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 573,000 33,000 606,000 -repair sidewalks. . PIN/Project No. Totals 606,000 0 0 0 0 Nenant Street North & South. Installation of drainage / replace Nenant Street 2nd to 12th Intallation of drainage and replacement or repair sidewalks. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number PE 606,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 OTHER 573,000 33,000 606,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 5 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-15 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-7 06/28/18 06/28/18 2018-02 05 P T W 0.110 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 25,000 25,000 . PIN/Project No. Totals25,0000000 A Ohop Road Chip Seal Ohop Road East Tono to 600' Ohop Chip and seal the first 600 feet of Ohop Road. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside

Priority Number CN25,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2019 0 0 25,000 25,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 7 MPO/RTPO: Class Funding Expenditure Schedule

A-16 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-15 06/28/18 06/28/18 2018-02 05 P T W 0.020 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 48,000 2,000 50,000 . PIN/Project No. Totals50,0000000 A Seatco overlay Seatco Nenant Street South to Factory Overlay. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL50,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 48,000 2,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 15 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-17 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-13 06/28/18 06/28/18 2018-02 03 P T W 0.060 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 70,000 4,000 74,000 . PIN/Project No. Totals 74,000 0 0 0 0 A Thurman Street Thurman Street 7th Street West to 8th Widen, install drainage and overlay. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL 74,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 70,000 4,000 74,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 13 MPO/RTPO: Class Funding Expenditure Schedule

A-18 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program BUC-12 06/28/18 06/28/18 2018-02 03 P T W 0.050 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 56,000 3,000 59,000 . PIN/Project No. Totals59,0000000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description West 3rd Street Chipseal and Grade Potholes West 3rd Street Sumner to Upham Widen, install drainage, and overlay. Bucoda Thurston TRPC Y Inside N Outside Priority Number ALL59,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 56,000 3,000 59,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 12 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-19 This page left intentionally blank.

A-20 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region Planned Projects INTERCITY TRANSIT INTERCITY Planned projects for which for Planned projects Intercity Transit will seek funding. Transit Intercity

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-21 This page left intentionally blank.

A-22 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10904 23 0.000 DCE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 171,011 0 26,689 197,700 er flow. These ployment including, nd security of he stop for both the sidewalk design istrict within the CMAQ accessibility, including rovements that support people with physical . PIN/Project No. Totals 0 197,700 0 0 0 Bus Stop Enhancements for Safety & Accessibility - 2020 N/A to NA Improve existing bus stops within Intercity Transit’s service d area. The purpose of this effort is to: a) increase pedestrian elements that construct accessible landing pads for bus ramp de federal ADA requirements for sidewalks, b) improve the safety a existing stops thru addition of lighting, shelters and site imp visibility and protection from the elements. c) incorporate where appropriate, improvements to curbing and street storm wat improvements increase operational functionality and safety at t limitations or impairments. transit vehicle/driver, the riding public and in particular for A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Intercity Transit Thurston TRPC Y Inside N Outside PE 0 50,700 0 0 0 Priority Number CN 0 147,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2020 2020 CMAQ CMAQ 43,856 127,155 0 0 6,844 19,845 50,700 147,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-23 This page left intentionally blank.

A-24 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region LACEY Planned Projects Lacey will seek funding. Planned projects for which for Planned projects

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-25 This page left intentionally blank.

A-26 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11017 21 C G O P T 0.100 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 648,000 648,000 . PIN/Project No. Totals 400,000 600,000 0 0 0 Britton and Carpenter Road Intersection Improvements Britton Parkway Carpenter Road to Intersection traffic control device. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 400,000 600,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 0 648,000 648,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 117 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-27 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11018 03 1.000 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 1,500,000 1,000,000 2,500,000 . PIN/Project No. Totals 0 0 100,000 100,000 100,000 Britton Parkway -- Phase II Britton Parkway Gateway Blvd to Carpenter Road Widen remaining portion of Britton Parkway to 4 lane boulevard. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 100,000 100,000 100,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 TIB 1,500,000 1,000,000 2,500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 118 MPO/RTPO: Class Funding Expenditure Schedule

A-28 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11010 21 C G O P T 1.000 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 3,000,000 1,340,000 4,340,000 th bike lanes and . PIN/Project No. Totals 0 500,000 500,000 500,000 500,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Carpenter Road Capacity and Safety Improvements Carpenter Road SE Pacific Ave SE to Shady Lane Widen roadway to taper from 5-lane section 3-lane wi sidewalks. Realign 14th Ave. Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 500,000 500,000 500,000 500,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 TIB 3,000,000 1,340,000 4,340,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 110 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-29 RW Required

Environmental Type 1.300 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11015 03 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 9,100,000 5,000,000 5,000,000 19,100,000 sidewalks, and other . PIN/Project No. Totals 0 0 1,000,000 1,000,000 1,000,000 Carpenter Road Widening from Martin Way to Britton Parkway Carpenter Road Martin Way to Britton Parkway Widen roadway to 5 lanes with auxilary turn lanes, bike urban amenities. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 1,000,000 1,000,000 1,000,000 Phase 1st 2nd 3rd 4th 5th & 6th P ALL 2021 Discretionary 9,100,000 TIB 5,000,000 5,000,000 19,100,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 115 MPO/RTPO: Class Funding Expenditure Schedule

A-30 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.500 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11005 01 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 3,298,000 3,298,000 e and College St to oadway with bike . PIN/Project No. Totals 0 500,000 500,000 500,000 1,000,000 A College St NE Extension College St NE Martin Way to 15th Ave NE Extend College Street from 6th Ave to 15th NE with 3-lane r correlate. lanes and sidewalks. Rechannelize rehabilatate both 6th Av C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 500,000 500,000 500,000 1,000,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 0 3,298,000 3,298,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 105 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-31 RW Required

Environmental Type 2.000 CE No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11021 21 C G O P T s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 38,000,000 38,000,000 ed to be 4-6 phases . PIN/Project No. Totals 0 500,000 500,000 500,000 500,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description College Street Corridor Improvements College St SE Lacey Blvd to 37th Ave SE Construct remaining portions of College St Corridor. Anticipat Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 500,000 500,000 500,000 500,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 0 38,000,000 38,000,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 121 MPO/RTPO: Class Funding Expenditure Schedule

A-32 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 5.000 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11026 01 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 11,000,000 0 11,000,000 ors . PIN/Project No. Totals 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Hawks Prairie Business District (LHPBD) Commercial Corrid Several LHPBD to Construct new corridors within LHPBD Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 OTHER 11,000,000 0 11,000,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 126 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-33 RW Required

Environmental Type 0.100 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11019 01 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 500,000 500,000 . PIN/Project No. Totals 0 0 50,000 50,000 50,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lebanon St Extension Lebanon St SE Lacey Blvd to Pacific Ave New roadway Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 50,000 50,000 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 0 500,000 500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 119 MPO/RTPO: Class Funding Expenditure Schedule

A-34 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.300 CE No Total Length

Utility Codes T Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11025 21 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID ies. Totals 0 0 5,500,000 5,500,000 . PIN/Project No. Totals 0 0 500,000 500,000 500,000 ccess management, bike lanes, sidewalks, and other urban amenit A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Martin Way East Roadway Improvements Martin Way Galaxy Drive to River Ridge Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 500,000 500,000 500,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2023 0 0 5,500,000 5,500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 125 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-35 RW Required

Environmental Type 0,000 2.000 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11014 03 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 32,000,000 10,000,000 600,000 42,600,000 . PIN/Project No. Totals 0 0 0 10,000,000 10,000,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Martin Way / I-5 Interchange Improvements Interstate 5 MP109 to MP 109 Construct interchange per approved IJR. Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 0 10,000,000 10,000,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2022 Discretionary -IMD 32,000,000 WSDOT 10,000,000 600,000 42,60 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 12 114 MPO/RTPO: Class Funding Expenditure Schedule

A-36 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 2.150 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11013 03 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 10,000,000 5,535,000 15,535,000 hen transition to 3 . PIN/Project No. Totals00005,000,000 Marvin Road from Britton Parkway to Columbia Drive Marvin Road NE Britton Parkway to Columbia Drive NE Widen Marvin Road from 2 lanes to 5 Hawks Prairie Rd t lane section, with bike lanes and sidewalks. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL00005,000,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 TIB 10,000,000 5,535,000 15,535,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 113 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-37 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11016 21 0.250 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 1,858,000 1,000,000 2,858,000 sidewalks. . PIN/Project No. Totals 0 100,000 100,000 100,000 100,000 Rainier Rd from Yelm Hwy to City Limits (near Beckonridge) Rainier Road SE Yelm Highway to South City Limits Improve tapers and storage at intersection, adds bike lanes A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 100,000 100,000 100,000 100,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 TPP 1,858,000 1,000,000 2,858,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 116 MPO/RTPO: Class Funding Expenditure Schedule

A-38 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11020 21 0.100 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 500,000 0 375,000 875,000 . PIN/Project No. Totals 0 0 100,000 100,000 100,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Sleater Kinney at 14th Ave Improvements Sleater Kinney Road 14th Ave SE to Traffic control device, probably roundabout. Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 100,000 100,000 100,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 STP(U) 500,000 0 375,000 875,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 120 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-39 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey14001 21 P W 0.250 CE No s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 1,510,000 1,510,000 . PIN/Project No. Totals 0 0 500,000 500,000 500,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Willamette Dr / Campus Glen Roundabout Willamette Drive Campus Glen Drive NE to Construct Roundabout Thurston TRPC Y Inside N Outside Lacey Priority Number ALL 0 0 500,000 500,000 500,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 0 1,510,000 1,510,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 401 MPO/RTPO: Class Funding Expenditure Schedule

A-40 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.000 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Lacey11024 03 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 2,500,000 0 2,500,000 5,000,000 walk and other urban . PIN/Project No. Totals 0 0 200,000 200,000 200,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Yelm Hwy Improvements from Ruddell Rd to Amtrak Bridge Yelm Highway SE Compton Blvd to Ruddell Road Widen east side for additional northbound lane, bike amenities. Lacey Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 200,000 200,000 200,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 STP(U) 2,500,000 0 2,500,000 5,000,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 124 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-41 This page left intentionally blank.

A-42 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region OLYMPIA Planned Projects Olympia will seek funding. Planned projects for which for Planned projects

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-43 This page left intentionally blank.

A-44 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1116a 11/14/17 12/12/17 M-1920 28 G P T W C CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 600,000 600,000 may include rossing all users of the Street Access mprove safety on ies. Projects may clude new guardrails, . PIN/Project No. Totals 100,000 100,000 100,000 100,000 200,000 ccess and Safety Improvements A A Various Locations N/A to The purpose of this program is to improve access and safety for transportation system: Hazard Elimination and Safety projects i high accident street sections or intersections. Projects may in projects remove barriers on walkways for persons with disabilit railroad crossings, and intersection improvements. Pedestrian C bulb-outs, crossing islands, and/or flashing crosswalk beacons. include ADA access ramps or audible pedestrian signals. Improvements help pedestrians cross major streets. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 20,400 20,400 20,400 20,400 40,800 Priority Number CN 79,600 79,600 79,600 79,600 159,200 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2019 0 0 0 0 122,400 477,600 122,400 477,600 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-45 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1108a 11/14/17 12/12/17 M-1920 28 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID rk. Totals 0 0 600,000 600,000 cle network: Bike travel. Other . PIN/Project No. Totals 100,000 100,000 100,000 100,000 200,000 Corridors: Low-volume, low-stress streets improved for bicycle Improvements: Gaps and spot improvements in the bike lane netwo Bike Improvements Various Locations N/A to The purpose of this program is to complete elements the bicy A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 23,800 23,800 23,800 23,800 47,600 Priority Number CN 76,200 76,200 76,200 76,200 152,400 Phase 1st 2nd 3rd 4th 5th & 6th PP PE CN 2019 2019 0 0 0 0 142,800 457,200 142,800 457,200 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-46 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1104a 11/14/17 12/12/17 M-1920 03 C G P T 0.120 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 172,417 226,271 398,688 mpact roundabout and t . PIN/Project No. Totals 0 0 81,184 317,504 0 A Cain Road and North Street Intersection Improvements Cain Road 300 feet south of North Street to north Stree Intersection capacity improvements include installation of a co sidewalk modifications. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE0081,18400 Priority Number CN 0 0 0 317,504 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2021 2022 0 0 TIB TIB 35,109 137,308 46,075 180,196 81,184 317,504 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-47 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1102a 11/14/17 12/12/17 M-1920 03 C G P T W 0.670 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 1,176,803 5,865,525 8,798,572 15,840,900 s management, and . PIN/Project No. Totals 0 6,706,500 9,134,400 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Fones Road - Transportation Fones Road 18th Avenue to Pacific Improvements will address vehicle capacity, truck access, acces safe and inviting bicycle pedestrian facilities. Olympia Thurston TRPC Y Inside N Outside PE 0 1,361,700 0 0 0 CN 0 0 9,134,400 0 0

Priority Number RW 0 5,344,800 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th SPP PE RW CN 2020 2020 2021 STP(US) 1,176,803 0 0 TIB TIB 0 2,165,179 3,700,346 184,897 3,179,621 5,434,054 1,361,700 5,344,800 9,134,400 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 MPO/RTPO: Class Funding Expenditure Schedule

A-48 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1152a 11/14/17 12/12/17 M-1920 28 1.000 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 536,000 0 264,000 800,000 . PIN/Project No. Totals 133,333 666,667 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Grass Lake Nature Park Trail Connection Cooper Point Road to Regional Trail Design and construct multi-modal trail. Olympia Thurston TRPC Y Inside N Outside PE 133,333 0 0 0 0 Priority Number CN 0 666,667 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2020 STP(E) STP(E) 89,333 446,667 0 0 44,000 220,000 133,333 666,667 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-49 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1105a 11/14/17 12/12/17 M-1920 03 C G P T 0.020 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID ments Totals 0 240,605 315,756 556,361 hin the existing . PIN/Project No. Totals556,3610000 t Eskridge Boulevard to At Henderson Boulevard and Eskridge Intersection Improve Henderson Boulevard A A Intersection capacity improvements include a traffic signal wit intersection configuration. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside

Priority Number CN556,3610000 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2019 0 TIB 240,605 315,756 556,361 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 MPO/RTPO: Class Funding Expenditure Schedule

A-50 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.000 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1107a 11/14/17 12/12/17 M-1920 01 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 216,231 283,769 500,000 . PIN/Project No. Totals0000500,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Log Cabin Road Extension Log Cabin Road Boulevard Road to Wiggins Extend Minor Arterial roadway. Funding is for design. Olympia Thurston TRPC Y Inside N Outside

Priority Number PE0000500,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 TIB 216,231 283,769 500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-51 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1108c 11/14/17 12/12/17 M-1920 28 G P S T W 0.180 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 5,860,000 0 5,860,000 ; Widen for Class II . PIN/Project No. Totals 552,600 599,500 0 4,707,900 0 Mottman Road Bike Lanes and Half Street Frontage Improvement Mottman Road Mottman Court to SPSCC Construct Sidewalk, Planter Strip, and Streetlights on one side Bike Lanes and Overlay Street. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 552,600 0 0 0 0 CN 0 0 0 4,707,900 0

Priority Number RW 0 599,500 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th SSS PE RW CN 2019 2020 2022 0 0 0 OTHER OTHER OTHER 552,600 599,500 4,707,900 0 0 0 552,600 599,500 4,707,900 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 MPO/RTPO: Class Funding Expenditure Schedule

A-52 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1154a 11/14/17 12/12/17 M-1920 28 0.400 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 3,233,000 0 1,617,000 4,850,000 . PIN/Project No. Totals 675,000 3,800,000 0 0 0 A Olympia Woodland Trail, Phase 3 Henderson Boulevard to Eastside Street Design and construct multi-modal trail. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston TRPC Y Inside N Outside Olympia PE 675,000 0 0 0 0 Priority Number CN 0 3,800,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2020 STP(E) STP(E) 487,714 2,745,286 0 0 243,851 1,373,149 4,118,435 731,565 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-53 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1754b 11/15/16 12/12/17 M-1920 28 0.940 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 13,333,000 0 6,667,000 20,000,000 . PIN/Project No. Totals 0 0 3,300,000 16,700,000 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Woodland Trail, Phase 4 Tumwater Historical Park to Henderson Boulevard Design and construct a multi-modal trail. Olympia Thurston TRPC Y Inside N Outside PE 0 0 3,300,000 0 0 Priority Number CN 0 0 0 16,700,000 0 Phase 1st 2nd 3rd 4th 5th & 6th PP PE CN 2021 2022 STP(E) STP(E) 2,200,000 11,133,000 0 0 1,100,000 5,567,000 3,300,000 16,700,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-54 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1751b 11/14/17 12/12/17 M-1920 28 0.100 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 1,929,500 0 1,070,500 3,000,000 ct the existing . PIN/Project No. Totals 300,000 2,700,000 0 0 0 streets and utilities. Percival Landing Bulkhead State Avenue to 4th Construct a bulkhead along Water Street and 4th Avenue to prote A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE300,0000000 Priority Number CN 0 2,700,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2020 STP(E) STP(E) 200,000 1,729,500 0 0 100,000 970,500 300,000 2,700,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-55 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1151a 11/14/17 12/12/17 M-1920 28 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 6,830,000 0 3,370,000 10,200,000 rth end of 'D' dock. . PIN/Project No. Totals 621,575 9,578,425 0 0 0 Percival Landing, Section A, Phase 2 Percival Landing N/A to Boardwalk and float replacement from south end of phase 1 to no A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 621,575 0 0 0 0 Priority Number CN 0 9,578,425 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2020 STP(E) STP(E) 392,577 6,437,423 0 0 228,998 3,141,002 9,578,425 621,575 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-56 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1112a 11/14/17 12/12/17 M-1920 28 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID sidewalks on at Totals 0 0 6,750,000 6,750,000 sidewalks based non-motorized ks and pathways. collectors. er streets. Pathways for . PIN/Project No. Totals 1,125,000 1,125,000 1,125,000 1,125,000 2,250,000 Sidewalks and Pathways Various Locations N/A to This purpose of this program is to: Maintain and repair sidewal Construct pathways for pedestrians and bicyclists. Pathways are short-cuts that link streets to parks, schools, trails, and oth upon the 2004 Sidewalk Program. The program focuses on building least one side of arterials, major collectors, and neighborhood improvement will be identified by neighborhoods. Construct new A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 153,000 153,000 153,000 153,000 306,000 Priority Number CN 972,000 972,000 972,000 972,000 1,944,000 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2019 0 0 0 0 918,000 5,832,000 918,000 5,832,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-57 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1117a 11/14/17 12/12/17 M-1920 04 G T W C CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 16,950,000 16,950,000 address streets ts include,for sections. Street ects add bicycle and de other elements ng streets and sealing our streets and delay signals, and lighting. Maintenance projects that . PIN/Project No. Totals 2,825,000 2,825,000 2,825,000 2,825,000 5,650,000 such as ADA access ramps and bulb-outs for pedestrians at inter Preservation is an on-going effort to preserve the condition of major reconstruction. This may include, for example, chip seali cracks. are beyond the capacity of City maintenance crews. These projec example, repairing and replacing striping, guardrails, railing, Major Resurfacing projects are repaving that may inclu Street Repair and Reconstruction Various Locations N/A to This program addresses: Complete Street Reconstruction projects pedestrian facilities at the time street is reconstructed. with pavement in the worst condition. These reconstruction proj A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE 627,000 627,000 627,000 627,000 1,254,000 Priority Number CN 2,198,000 2,198,000 2,198,000 2,198,000 4,396,000 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2019 0 0 0 0 3,762,000 13,188,000 3,762,000 13,188,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-58 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly2321a 11/14/17 12/12/17 M-1920 01 P 1.100 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID aiser Road. Also 0000 Totals 2,761,611 0 3,624,189 6,385,800 at-grade and westbound . PIN/Project No. Totals 4,149,300 2,236,500 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description US 101/West Olympia Access Project US 101 Black Lake Boulevard to Kaiser Road Construct westbound and eastbound off/on-ramps from US 101 to K construct a westbound off-ramp from US 101 to Yauger Way via an intersection at Black Lake Boulevard. Add Auxiliary lanes east between Black Lake Boulevard and Kaiser Road. Olympia Thurston TRPC Y Inside N Outside PE 4,149,300

Priority Number RW 0 2,236,500 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE RW 2019 2020 STP(US) STP(US) 1,794,411 967,200 0 0 2,354,889 1,269,300 4,149,300 2,236,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 12 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-59 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1106a 11/14/17 12/12/17 M-1920 03 G P T C 0.020 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 189,274 248,393 437,667 hin the existing . PIN/Project No. Totals 0 0 0 0 437,667 t 37th Avenue to At Aveue A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Intersection capacity improvements include a traffic signal wit intersection configuration. Wiggins Road and 37th Avenue Intersection Improvements Wiggins Road Olympia Thurston TRPC Y Inside N Outside

Priority Number CN 0 0 0 0 437,667 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2023 0 TIB 189,274 248,393 437,667 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 MPO/RTPO: Class Funding Expenditure Schedule

A-60 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program Oly1153a 11/14/17 12/12/17 M-1920 28 0.400 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 323,610 0 159,390 483,000 . PIN/Project No. Totals 0 63,000 420,000 0 0 Yauger Park Shared Use Trail Connection Yauger Park to Harrison Boulevard Design and construct trail connection. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Olympia Thurston TRPC Y Inside N Outside PE063,000000 Priority Number CN 0 0 420,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2020 2021 STP(E) STP(E) 42,210 281,400 0 0 20,790 138,600 63,000 420,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-61 This page left intentionally blank.

A-62 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RAINIER Planned Projects Rainier will seek funding. Rainier Planned projects for which for Planned projects Tenino will seek funding. Tenino

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-63 This page left intentionally blank.

A-64 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11466 07/10/18 07/10/18 534 03 0.130 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 600,000 20,000 620,000 ments to the project onstruction and will . PIN/Project No. Totals 0 0 0 0 620,000 also include sidewalks, curb, gutter and storm drainage improve area. 2nd Street E. Improvements 2nd Street E Centre Street to Idaho Ave This project will provide approximately 800 feet of roadway rec A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Rainier Thurston TRPC Y Inside N Outside Priority Number ALL0000620,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2024 0 TIB 600,000 20,000 620,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 08 7 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-65 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-00411 07/10/18 07/10/18 534 05 0.160 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 184,000 20,000 204,000 . PIN/Project No. Totals 0 0 0 0 204,000 laska Street Overlay laska Street A A A Binghampton Street to Third This project will provide a 4-inch asphalt overlay. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Rainier Thurston TRPC Y Inside N Outside Priority Number ALL0000204,000 Phase 1st 2nd 3rd 4th 5th & 6th P ALL 2023 0 TIB 184,000 20,000 204,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 6 MPO/RTPO: Class Funding Expenditure Schedule

A-66 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-07329 07/10/18 07/10/18 534 04 0.100 Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 4,000,000 500,000 0 4,500,000 Street. . PIN/Project No. Totals 0 0 4,500,000 0 0 Binghampton Street Scape Project Phase 2 SR-507/Centre Street SR-507 to Centre St Construct a roundabout at the intersection of SR-507 and Centre A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Rainier Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 4,500,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 TAP(R) 4,000,000 WSDOT 500,000 0 4,500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 02 4 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-67 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-00412 07/10/18 07/10/18 534 21 0.080 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 122,000 16,000 138,000 e project area. ong Michigan Street. . PIN/Project No. Totals 0 0 0 138,000 0 Michigan Street Sidewalk Improvements Michigan Street Binghampton Street to End of Michigan This project will provide approximately 280 feet of sidewalk al The project will also include storm drainage improvements to th A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston TRPC Y Inside N Outside Rainier Priority Number ALL 0 0 0 138,000 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2022 0 TIB 122,000 16,000 138,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 08 5 MPO/RTPO: Class Funding Expenditure Schedule

A-68 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11465 07/10/18 07/10/18 534 05 0.230 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 43,000 5,000 48,000 sq. yards of Rainier . PIN/Project No. Totals 48,000 0 0 0 0 A Rainier Road Chip Seal Rainier Road City Limits to Minnesota Street This project will crack seal and chip approximately 3,700 Road between the City limits and Minnesota Street. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Rainier Thurston TRPC Y Inside N Outside Priority Number ALL 48,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2019 0 TIB 43,000 5,000 48,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 06 1 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-69 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-00410 07/10/18 07/10/18 534 03 0.080 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 206,000 11,000 217,000 ewalk, curb, gutter, and . PIN/Project No. Totals 0 217,000 0 0 0 laska Street to Elementary School Third Street Improvements Third Street A A storm drainage on one side of the street. This project will provide 4-inches of asphalt overlay, with sid C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Rainier Thurston TRPC Y Inside N Outside Priority Number ALL 0 217,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 TIB 206,000 11,000 217,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 3 MPO/RTPO: Class Funding Expenditure Schedule

A-70 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region

TENINO Planned Projects Tenino will seek funding. Tenino Planned projects for which for Planned projects Tenino will seek funding. Tenino

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-71 This page left intentionally blank.

A-72 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10001 06/12/18 2018-07 05 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 35,000 35,000 . PIN/Project No. Totals35,0000000 A 5th Street 5th Street Park St to Wichman Widen, install drainage, chipseal C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL35,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 0 35,000 35,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-73 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10002 06/12/18 2018-07 04 0.100 EIS No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 35,000 0 0 35,000 . PIN/Project No. Totals35,0000000 Eureka Street S Old Hwy 99 Sussex Ave E to Park Widen, repair, chipseal, safety improvements as needed. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL35,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2023 STP(US) 35,000 0 0 35,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 06 MPO/RTPO: Class Funding Expenditure Schedule

A-74 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10003 06/12/18 2018-07 05 0.100 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 35,000 35,000 . PIN/Project No. Totals 35,000 0 0 0 0 Frost St Frost St Park Ave to Sussex Repair, widen, chipseal, and safety improvements as needed A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL35,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2020 0 0 35,000 35,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-75 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09997 06/12/18 2018-07 05 0.210 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 45,000 28,500 73,500 . PIN/Project No. Totals73,5000000 McClellan St McClellan St Sussex Ave W to Wichman St S widen, install drainage, and chipseal A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston TRPC Y Inside N Outside Tenino Priority Number ALL73,5000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2023 0 TIB 45,000 28,500 73,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

A-76 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10004 06/12/18 2018-07 05 0.050 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 17,500 17,500 . PIN/Project No. Totals 17,500 0 0 0 0 A Morning Side Dr Morning Side Dr McClellan St to Morning Side Dr Repair, chipseal, and safety improvements as needed C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL 17,500 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2024 0 0 17,500 17,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-77 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10000 06/12/18 2018-07 05 0.150 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 52,500 52,500 . PIN/Project No. Totals 52,500 0 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description OBrien St OBrien St Park Ave to Sussex Repair, widen, chipseal, and safty improvements as needed Tenino Thurston TRPC Y Inside N Outside Priority Number ALL52,5000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 0 52,500 52,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

A-78 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09995 06/12/18 2018-07 04 1.500 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 500,000 53,000 553,000 forcing fibers . PIN/Project No. Totals 500,000 0 0 0 0 Old Hwy 99 West Old Hwy 99 Hwy 507 to Mima Acres Dr SE 3" asphalt grind, overlay using HMA that contained rein A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL500,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2022 0 TIB 500,000 53,000 553,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 06 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-79 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09998 06/12/18 2018-07 05 0.500 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 100,000 75,000 175,000 . PIN/Project No. Totals175,0000000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Old Military Road Old Military Road Sussex St E to Old Military Road crack seal, and chipseal Tenino Thurston TRPC Y Inside N Outside Priority Number ALL175,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2024 0 TIB 100,000 75,000 175,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 06 MPO/RTPO: Class Funding Expenditure Schedule

A-80 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09999 06/12/18 2018-07 04 0.430 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 112,500 38,000 150,500 . PIN/Project No. Totals 150,500 0 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Park Ave West Park Ave Howard St to 6th Widen, install drainage, and chipseal Tenino Thurston TRPC Y Inside N Outside Priority Number ALL150,5000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2021 0 TIB 112,500 38,000 150,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-81 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09996 06/12/18 2018-07 04 0.250 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 70,500 17,000 87,500 . PIN/Project No. Totals 87,500 0 0 0 0 Ritter St Ritter St Sussex Ave W to Park Widen, install drainage, chipseal A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside Priority Number ALL87,5000000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2023 0 TIB 70,500 17,000 87,500 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 09 MPO/RTPO: Class Funding Expenditure Schedule

A-82 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11428 21 0.100 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 15,000 15,000 and Hodgden the northwest and . PIN/Project No. Totals 0 15,000 0 0 0 southwest corners of the intersection Sussex Avenue (SR-507) Street. Sussex Crossing Improvements II Sussex Avenue Hodgden St N to NA Installation of high visibility devices on A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tenino Thurston TRPC Y Inside N Outside

Priority Number CN 0 15,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2020 0 0 15,000 15,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 02 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-83 This page left intentionally blank.

A-84 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region

Planned Projects Thurston County Planned projects for which for Planned projects Thurston County will seek funding. Tenino will seek funding. Tenino

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-85 This page left intentionally blank.

A-86 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.000 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01279 03 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 land Creek crossing an features. ignment, additional ke lanes, illumination, . PIN/Project No. Totals 0 0 0 0 50,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description (may be a bridge), possible guardrail, and other safety urb 15th Ave NE and Draham Rd NE, Phase 1 15th Ave NE Sleater Kinney Road to Draham Reconstruction added capacity including but not limited to real lanes, intersection improvements, , gutters, sidewalks, bi drainage facilities, possible landscaping, replacement for Wood Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 32 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-87 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09491 03 C P T W 0.750 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 1,000 1,000 dditional lanes, acilities, possible . PIN/Project No. Totals 0 0 0 0 50,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description curbs, gutters, sidewalks, bike lanes, illumination, drainage f 15th Ave NE and Draham Rd NE, Phase 2 15th Ave NE 15th Ave NE to Carpenter Rd Reconstruction added capacity including possible realignment, a landscaping, possible guardrail, and other safety features. Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2023 0 0 1,000 1,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 33 MPO/RTPO: Class Funding Expenditure Schedule

A-88 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required No

Environmental Type

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10290 10 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 ork including full r associated work ntal mitigation, etc... . PIN/Project No. Totals000050,000 to C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description A Bridge Program county-wide Bridge Program includes maintenance/repairs, preservation and w replacement including approaches, abutments, structure and othe such as sidewalks, lighting, traffic control devices, environme Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-89 RW Required

Environmental Type CE No

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10291 21 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID ardrail, rumble Totals 0 0 50,000 50,000 rove safety section traffic control, . PIN/Project No. Totals000050,000 to lighting, ITS, traffic calming and other countermeasures to imp performance County Road Safety Improvement Program county-wide The safety improvement program includes improvements such as gu strips, high friction surfacing, traffic control devices, inter A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston TRPC Y Inside N Outside Thurston Co.

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-90 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09773 05 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 1,800,000 0 300,000 2,100,000 ilbox replacements, ces and may include . PIN/Project No. Totals 0 2,100,000 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description associated safety features such as rumble strips, guardrail, ma Countywide Restoration and Resurfacing Project County Wide Various to Project includes asphalt paving, grinding, traffic control devi etc... Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number CN 0 2,100,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2020 STP(R) 1,800,000 0 300,000 2,100,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 11 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-91 RW Required

Environmental Type CE No

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10287 44 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 de roadway paving, d other work associated . PIN/Project No. Totals000050,000 to A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Culvert Program county-wide repair, preserve and replace culverts. Projects can also inclu guardrail, traffic control devices, environmental mitigation an with repairing, preserving and replacing culverts. Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-92 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.400 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01328 03 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 dditional lanes, other safety and acilities, possible . PIN/Project No. Totals 0 0 0 0 50,000 Elderberry Road Upgrade Elderberry Rd SW US 12 to 193rd Ave SW Reconstruction added capacity including possible realignment, a curbs, gutters, sidewalks, bike lanes, illumination, drainage f urban features. landscaping, intersection improvements, possible guardrail, and A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 18 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-93 RW Required

Environmental Type 0.100 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06241 18 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 . PIN/Project No. Totals 0 50,000 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Evergreen Parkway/Mud Bay Road Interchange Improvements Mud Bay Road NW MP 0.94 to 1.04 Intersection Control alternative study. Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 50,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th S PE 2020 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 31 MPO/RTPO: Class Funding Expenditure Schedule

A-94 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01478 44 C P T CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 2,800,000 2,800,000 t. May be replaced , guardrail, traffic . PIN/Project No. Totals 400,000 2,380,000 10,000 0 0 with a bridge or culvert. Other work includes asphalt paving Fish Passage Enhancement Project 2019-2020 County Wide Various to Replacement of prioritized culverts for fish passage enhancemen control devices, environmental mitigation, etc... A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside PE 400,000 150,000 0 0 0 Priority Number CN 0 2,230,000 10,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th SS PE CN 2019 2020 0 0 0 0 550,000 2,250,000 550,000 2,250,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 20 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-95 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11386 18 14.000 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 300,000 300,000 il right-of-way to . PIN/Project No. Totals 0 0 300,000 0 0 A Gate-Belmore Trail Engineering Study Gate Community to Kenneydell Park This study will assess opportunities to connect eh existing tra surrounding communities. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 300,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2021 0 0 300,000 300,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 21 MPO/RTPO: Class Funding Expenditure Schedule

A-96 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01369 03 C P T 0.100 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 150,000 150,000 res. y of realignment, ities, intersection . PIN/Project No. Totals 50,000 100,000 0 0 0 t Intersection to At Johnson Point Rd & Hawks Prairie Intersection Improvements Johnson Pt Rd NE A A Reconstruction, added capacity project including the possibilit additional lanes, paved shoulders, illumination, drainage facil control improvements, wetland mitigation and other safety featu C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside PE 50,000 50,000 0 0 0

Priority Number RW 0 50,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE RW 2019 2020 0 0 0 0 100,000 50,000 100,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 16 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-97 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11389 01 C G O P T 0.300 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 ments n conditions at 113th . PIN/Project No. Totals 0 0 0 0 50,000 ve SW and Littlerock Rd SW. A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Littlerock Road & 113th Ave. SW Bridge and Intersection Improve Littlerock Rd SW 113th Ave SW to 110th The project will replace the L-5 bridge and improve intersectio Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 34 MPO/RTPO: Class Funding Expenditure Schedule

A-98 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.300 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-08526 18 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 193 0 30,000 30,193 ay corridor. . PIN/Project No. Totals 0 223,000 0 0 0 Martin Way Corridor Mobility Strategy Martin Way East Carpenter Rd NE to Lacey City Limits (MP 4.793) The project will study transportation flows within the Martin W A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 223,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2020 STP(US) 193 0 30,000 30,193 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 28 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-99 RW Required

Environmental Type 0.800 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11381 03 C G O P T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 3,275,000 3,275,000 s on both sides, tiple locations. improvement and other . PIN/Project No. Totals 275,000 350,000 350,000 2,300,000 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description associated work. Construction intersection improvements at mul Marvin Rd Upgrade - Phase 1 Marvin Rd SE 19th Ave SE to SR 510/Pacific Reconstruct roadway and widen to add bicycle lanes sidewalk additional channelization, landscaping, illumination, drainage Thurston Co. Thurston TRPC Y Inside N Outside PE 125,000 90,000 50,000 0 0 CN 0 0 200,000 2,300,000 0

Priority Number RW 150,000 260,000 100,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PPP PE RW CN 2019 2019 2021 0 0 0 0 0 0 265,000 510,000 2,500,000 265,000 510,000 2,500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 2 MPO/RTPO: Class Funding Expenditure Schedule

A-100 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 2.100 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-08050 03 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 75,000 75,000 s on both sides, tiple locations. improvement and other . PIN/Project No. Totals50,00025,000000 Marvin Rd Upgrade - Phase 2 Marvin Rd SE Mullen Rd SE to 19th Ave Reconstruct roadway and widen to add bicycle lanes sidewalk additional channelization, landscaping, illumination, drainage associated work. Construction intersection improvements at mul C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description A Thurston Co. Thurston TRPC Y Inside N Outside PE50,0000000 Priority Number CN025,000000 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2019 0 0 0 0 50,000 25,000 50,000 25,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 1 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-101 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11390 11 C O P T 0.100 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 ll as replace the . PIN/Project No. Totals 0 0 0 0 50,000 t Bridge to At A A The project will conduct a type, size and location study, as we existing bridge. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description McLane Delphi Rd Bridge (MC-8) Replacement Delphi Rd SW Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 35 MPO/RTPO: Class Funding Expenditure Schedule

A-102 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11388 21 0.250 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 60,000 60,000 ivers cross under the . PIN/Project No. Totals 0 0 0 0 60,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Mullen Road Overheight Warning System Mullen Road Railroad Crossing to The project will install an overheight warning system before dr BNSF railroad tracks. Thurston Co. Thurston TRPC Y Inside N Outside PE000010,000 Priority Number CN 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th 5th & 6th PP PE CN 2024 2024 0 0 0 0 10,000 50,000 10,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 26 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-103 RW Required

Environmental Type 0.150 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01297 04 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 5,000 5,000 198th Intersection fety features. of minor realignment, nation, drainage . PIN/Project No. Totals5,0000000 t Intersection to At Old Highway 99 Rural Capacity Project - Phase 1 Hwy and Improvements Old Hwy 99 SW A A Reconstruction added capacity project including the possibility additional lanes, curbs, gutters, sidewalks, bike illumi facilities, intersection improvements, landscaping and other sa C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number CN5,0000000 Phase 1st 2nd 3rd 4th 5th & 6th S CN 2019 0 0 5,000 5,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 14 MPO/RTPO: Class Funding Expenditure Schedule

A-104 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01358 03 C P T 0.000 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 125,000 125,000 acilities and other y of minor realignment, . PIN/Project No. Totals 50,000 75,000 0 0 0 A Old Highway 99/Tilley Road Intersection Tilley Rd SW at Old Hwy 99 to At Reconstruction, added capacity project including the possibilit turn lane extensions, paved shoulders, illumination, drainage f safety features. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside PE 50,000 50,000 0 0 0

Priority Number RW 0 25,000 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PP PE RW 2019 2020 0 0 0 0 100,000 25,000 100,000 25,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 19 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-105 RW Required

Environmental Type 0.200 CE No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09537 21 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 mited to lighting, ic control devices design and intersection . PIN/Project No. Totals 0 0 0 0 50,000 t Intersection to At DA improvements, possible traffic signal removal, paving, traff Pacific Ave and Steilacoom Road Roundabout Pacific Ave SE A A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description improvements. Intersection improvements include but are not li Work includes but is not limited to intersection control study, and other urban or safety features Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th 5th & 6th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 27 MPO/RTPO: Class Funding Expenditure Schedule

A-106 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.800 CE No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10274 05 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 2,364,000 0 416,000 2,780,000 ch as sidewalks, . PIN/Project No. Totals 280,000 2,500,000 0 0 0 Pacific Ave Preservation - Lacey City Limits to Union Mills Rd Pacific Ave SE Lacey City Limits (MP 3.4) to Union Mills Rd SE Pavement Rehabilitation of Pacific Ave including ADA updates su ramps and signal systems as required. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside PE 230,000 0 0 0 0 CN 0 2,500,000 0 0 0

Priority Number RW 50,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PPP PE RW CN 2019 2019 2020 NHPP NHPP 199,000 2,165,000 0 0 0 0 31,000 335,000 50,000 230,000 2,500,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 22 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-107 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10275 21 C G P T W 0.400 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 will improve the t of way acquisition . PIN/Project No. Totals 0 0 0 0 50,000 bernathy Rd Pleasant Glade Elementary A A 15th Ave NE to Pleasant Glade Elementary Includes new sidewalks, ADA ramps, and other improvements that walking safety for school children. Project could include righ C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th 5th & 6th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 19 30 MPO/RTPO: Class Funding Expenditure Schedule

A-108 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type CE No

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06694 05 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 ting pavement features. . PIN/Project No. Totals 0 0 0 0 50,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Road Preservation Program County Wide to The program is for major resurfacing and reconstruction of exis surfaces on primary county transportation corridors and safety Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number CN 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-109 RW Required No

Environmental Type

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10289 03 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 n/rural roadway management, trol devices, intersection . PIN/Project No. Totals 0 0 0 0 50,000 to environmental mitigation, right of way acquisition, traffic con traffic control improvement and other work associated with urba widening projects. Roadway Capacity Program county-wide Projects include road widening, sidewalks, lighting, stormwater A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-110 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type CE No

Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10285 38 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 etc. l improvements such ork can include . PIN/Project No. Totals000050,000 to A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Safe Route to Schools Program County Wide Improving walking routes to and from schools, including physica as, sidewalks, traffic calming, Lighting, signing, etc. Other w educational and outreach efforts such as walking school buses, Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-111 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11393 01 C O P T 0.400 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 250,000 250,000 ent deterioration by ect will include urban . PIN/Project No. Totals 125,000 125,000 0 0 0 Sargent Road SW Urban Upgrade Sargent Rd SW Old Hwy 99 to US 12 The project will address increased traffic congestion and pavem rehabilitating and widening the roadway. In addition, proj improvements such as lighting, sidewalks, and bike lanes. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 125,000 125,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 0 250,000 250,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 08 39 MPO/RTPO: Class Funding Expenditure Schedule

A-112 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.150 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-07758 03 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 200,000 200,000 ction at Sargent Rd y of minor realignment, s, illumination, drainage . PIN/Project No. Totals 100,000 100,000 0 0 0 SR 12 Urban Improvements, Phase 1 SR 12 West UGA boundary to Old Highway 99 Reconstruction added capacity project, including the possibilit additional lanes, signals, curbs, gutters, sidewalks, bike lane facilities, landscaping, intersection improvements, new interse SW and other safety features. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside PE 100,000 0 0 0 0

Priority Number RW 0 100,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE RW 2019 2020 0 0 0 0 100,000 100,000 100,000 100,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 15 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-113 RW Required

Environmental Type 0.850 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-04779 03 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 65,000 65,000 s on both sides, upgrades and other . PIN/Project No. Totals 50,000 15,000 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Steilacoom Road Phase I Steilacoom Road Pacific Ave to Marvin Road Reconstruct roadway and widen to add bicycle lanes sidewalk additional channelization, illumination, landscaping, drainage associated work. Thurston Co. Thurston TRPC Y Inside N Outside PE50,0000000

Priority Number RW 0 15,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE RW 2019 2020 0 0 0 0 50,000 15,000 50,000 15,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 17 MPO/RTPO: Class Funding Expenditure Schedule

A-114 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.650 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11391 01 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 ove drainage, e, pavement, construct . PIN/Project No. Totals000050,000 lighting, and pedestrian safety. bicycle lanes and sidewalks on both sides of the road, impr Steilacoom Road Phase II Steilacoom Road SR 510/Marvin Rd to Hawks Glen Dr. SE The project will conduct a corridor analysis, widen/rehabilitat A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 36 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-115 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09545 21 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 300,000 300,000 . PIN/Project No. Totals 50,000 50,000 50,000 50,000 100,000 Thurston County ADA Program County Wide County Wide to Upgrade sidewalk and ramps to meet ADA standards. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 50,000 50,000 50,000 50,000 100,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2019 0 0 300,000 300,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-116 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06668 19 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 . PIN/Project No. Totals 0 0 0 0 50,000 to Thurston County Pedestrian and Bicycle Program County Wide Design, permitting and construction of shared use path A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-117 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-04781 03 C G P T 1.510 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 1,650,000 790,000 2,440,000 improvements and ork. . PIN/Project No. Totals 325,000 610,000 1,540,000 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Vail Road Upgrade Phase II Vail Road 138th Road (MP 1.76) to 153rd 3.27) Widen to add 5' shoulders and two 11' travel lanes drainage may include channelization, illumination and other incidental w Thurston Co. Thurston TRPC Y Inside N Outside CN 0 610,000 1,540,000 0 0

Priority Number RW 325,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP RW CN 2019 2020 0 0 CRAB 1,650,000 0 465,000 325,000 2,115,000 325,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 25 MPO/RTPO: Class Funding Expenditure Schedule

A-118 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type CE Yes

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06752 10 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 include safety, isition, etc... . PIN/Project No. Totals 0 0 0 0 50,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Yelm Highway Capacity Project 4 - Phase 1 (0-12 Bridge) Yelm Hwy SE BNRR Crossing to Replacement of structural and functionally obsolete bridge capacity, non-motorized facilities, drainage, right of way acqu Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 0 0 50,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 12 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-119 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11392 18 C O P T CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 50,000 50,000 o create an improvement . PIN/Project No. Totals000050,000 t Intersection to At plan. The project will assess intersection control options in order t A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Yelm Hwy. at Spurgeon Creek Rd SE Yelm Hwy SE Thurston Co. Thurston TRPC Y Inside N Outside

Priority Number PE000050,000 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2024 0 0 50,000 50,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 37 MPO/RTPO: Class Funding Expenditure Schedule

A-120 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region TRPC Planned Projects TRPC will seek funding. Planned projects for which for Planned projects Tenino will seek funding. Tenino

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-121 This page left intentionally blank.

A-122 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10739 18 0.000 DCE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 700,000 0 109,249 809,249 d transportation . PIN/Project No. Totals 0 809,249 0 0 0 2020-2021 Regional Transportation Planning Priorities NA to Planning activities in the work program of regionally determine initiatives. See TRPC UPWP. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description TRPC Thurston TRPC Y Inside N Outside

Priority Number PE 0 809,249 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2020 STP(US) 700,000 0 109,249 809,249 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-123 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10740 18 0.000 DCE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 700,000 0 109,249 809,249 d transportation . PIN/Project No. Totals 0 0 809,249 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description initiatives. See TRPC UPWP. 2021-2022 Regional Transportation Planning Priorities NA to Planning activities in the work program of regionally determine TRPC Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 809,249 0 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2021 STP(US) 700,000 0 109,249 809,249 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-124 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11497 18 0.000 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 700,000 0 109,249 809,249 d transportation . PIN/Project No. Totals 0 0 0 809,249 0 2022-2023 Regional Transportation Planning Priorities NA to Planning activities in the work program of regionally determine initiatives. See TRPC UPWP. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description TRPC Thurston TRPC Y Inside N Outside

Priority Number PE 0 0 0 809,249 0 Phase 1st 2nd 3rd 4th & 6th 5th P PE 2022 STP(US) 700,000 0 109,249 809,249 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-125 This page left intentionally blank.

A-126 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region Tumwater Planned Projects Planned projects for which for Planned projects Tumwater will seek funding. Tumwater

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-127 This page left intentionally blank.

A-128 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11037 04/17/18 04/17/18 R2018-011 28 0.750 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 583,875 0 291,125 875,000 nts along 2nd . PIN/Project No. Totals 0 0 0 70,000 805,000 venue from Linwood Avenue to Custer Way. A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description 2nd Avenue Pedestrian Improvements 2nd Avenue Linwood Avenue to Desoto Street Curb ramp replacement, sidewalk infill and stormwater improveme Tumwater Thurston TRPC Y Inside N Outside PE 0 0 0 30,000 30,000 CN 0 0 0 0 730,000

Priority Number RW 0 0 0 40,000 45,000 Phase 1st 2nd 3rd 4th & 6th 5th PPP PE RW CN 2022 2022 2022 TAP(US) TAP(US) TAP(US) 51,900 73,525 458,450 0 0 0 8,100 11,475 271,550 60,000 85,000 730,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 24 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-129 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11036 04/17/18 04/17/18 R2018-011 28 0.750 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 500,000 500,000 lack Lake Belmore sign standards for . PIN/Project No. Totals 0 50,000 450,000 0 0 A 66th Avenue Multimodal Facilities 66th Avenue Kirsop Village Drive to Black Lake Belmore Road Design and construct multimodal facilities meeting practical de rural settings along 66th Avenue from Kirsop Village Drive to B Road C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 0 50,000 0 0 0 Priority Number CN 0 0 450,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2020 2021 0 0 0 0 50,000 450,000 50,000 450,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 23 MPO/RTPO: Class Funding Expenditure Schedule

A-130 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01375 04/17/18 04/17/18 R2018-011 16 C G P T 0.200 Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 42,000 42,000 at this intersection. . PIN/Project No. Totals42,0000000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description 93rd Avenue / Case Road Intersection 93rd Avenue / Case Road Intersection 93rd Avenue to Case Road Safety: Design, right-of-way and construction of a roundabout Tumwater Thurston TRPC Y Inside N Outside

Priority Number RW42,0000000 Phase 1st 2nd 3rd 4th & 6th 5th S RW 2019 0 0 42,000 42,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 6 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-131 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-08980 04/17/18 04/17/18 R2018-011 16 C P S T W 0.100 Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 150,000 150,000 . PIN/Project No. Totals150,0000000 93rd Ave / Kimmie Street Intersection 93rd Ave SW Kimmie St to 93rd Ave Right of Way acquisition for future intersection improvements. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside

Priority Number RW150,0000000 Phase 1st 2nd 3rd 4th & 6th 5th S RW 2019 0 0 150,000 150,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 7 MPO/RTPO: Class Funding Expenditure Schedule

A-132 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11035 04/17/18 04/17/18 R2018-011 28 Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 600,000 600,000 lities Act (ADA) . PIN/Project No. Totals 100,000 100,000 190,000 190,000 380,000 DA Curb Ramp Upgrades to A A requirements Various Upgrade ramps throughout the City to meet Americans with Disabi C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 15,000 15,000 15,000 15,000 30,000 CN 75,000 75,000 75,000 75,000 150,000

Priority Number RW 10,000 10,000 100,000 100,000 200,000 Phase 1st 2nd 3rd 4th & 6th 5th SSS PE RW CN 2019 2019 2019 0 0 0 0 0 0 90,000 60,000 450,000 90,000 60,000 450,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 22 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-133 RW Required

Environmental Type 1.300 No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06907 04/17/18 04/17/18 R2018-011 03 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 850,000 850,000 strict Plan. . PIN/Project No. Totals 0 0 850,000 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Brewery District Plan - Feasibility & Streetscape Various Various to Implementation of select elements developed from the Brewery Di Tumwater Thurston TRPC Y Inside N Outside PE 0 0 100,000 0 0 Priority Number CN 0 0 750,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2021 2021 0 0 0 0 100,000 750,000 100,000 750,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 5 MPO/RTPO: Class Funding Expenditure Schedule

A-134 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 1.210 No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-05729 04/17/18 04/17/18 R2018-011 15 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 984,000 246,000 1,230,000 ng 90% design plans, n. es and permitting for . PIN/Project No. Totals 0 615,000 615,000 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Capitol Boulevard Corridor, Israel Road to M Street Design Capitol Boulevard Israel Rd to M street Design-only project to complete preliminary engineering includi specifications and estimates, preliminary right-of-way activiti future construction project(s) in the Capitol Blvd Corridor Pla Tumwater Thurston TRPC Y Inside N Outside

Priority Number PE 0 615,000 615,000 0 0 Phase 1st 2nd 3rd 4th 5th & 6th P PE 2020 0 OTHER 984,000 246,000 1,230,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 16 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-135 RW Required

Environmental Type 0.060 Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11038 04/17/18 04/17/18 R2018-011 01 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 950,000 950,000 and neighborhood N-S Road between . PIN/Project No. Totals 0 50,000 250,000 650,000 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Capitol Boulevard Corridor Plan, N-S Connector Road Linda Street to Ruby Right-of-way acquisition for properties on the alignment of Linda and Ruby along with design construction of select ADA improvements per the Capitol Blvd Corridor Plan Tumwater Thurston TRPC Y Inside N Outside PE050,000000 CN 0 0 0 650,000 0

Priority Number RW 0 0 250,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PPP PE RW CN 2021 2019 2022 0 0 0 0 0 0 50,000 800,000 100,000 50,000 800,000 100,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 19 13 MPO/RTPO: Class Funding Expenditure Schedule

A-136 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.800 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-03907 04/17/18 04/17/18 R2018-011 03 G P S T C B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 972,500 1,027,500 2,000,000 inage, landscaping . PIN/Project No. Totals2,000,0000000 dd travel lanes, bike sidewalks, illumination, storm dra A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description and turn lanes/center medians Capitol Boulevard: Israel Road to 73rd Avenue Capitol Boulevard Israel Road to 73rd Avenue Tumwater Thurston TRPC Y Inside N Outside Priority Number ALL2,000,0000000 Phase 1st 2nd 3rd 4th & 6th 5th P CN 2019 0 TIB 972,500 1,027,500 2,000,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 2 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-137 RW Required

Environmental Type 0.100 Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-03956 04/17/18 04/17/18 R2018-011 03 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 80,000 80,000 ndabout. . PIN/Project No. Totals80,0000000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Capitol Boulevard / Linwood Avenue Roundabout Capitol Boulevard Capitol Blvd to Linwood Ave Replace existing traffic signalized intersection with a new rou Tumwater Thurston TRPC Y Inside N Outside

Priority Number RW80,0000000 Phase 1st 2nd 3rd 4th 5th & 6th P RW 2019 0 0 80,000 80,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 11 MPO/RTPO: Class Funding Expenditure Schedule

A-138 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09770 04/17/18 04/17/18 R2018-011 28 P 0.000 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 225,000 225,000 d-block crossings, one . PIN/Project No. Totals 0 25,000 200,000 0 0 Capitol Boulevard Pedestrian Crossing Improvements Capitol Blvd Israel Rd to Market St Installation of pedestrian activated beacons at two existing mi between Israel and Dennis another near Market St. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 0 25,000 0 0 0 Priority Number CN 0 0 200,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th SS PE CN 2022 2023 0 0 0 0 25,000 200,000 25,000 200,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 18 / 5235(016) MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-139 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-07852 04/17/18 04/17/18 R2018-011 28 2.720 CE Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 7,720,000 1,430,000 9,150,000 om Pioneer Park to the . PIN/Project No. Totals 150,000 5,800,000 0 0 3,200,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Historical Park Deschutes Valley Trail Pioneer Park to Tumwater Historical Construction of a paved walking / bicycling trail connection fr Tumwater Thurston TRPC Y Inside N Outside CN 0 5,800,000 0 0 3,200,000

Priority Number RW 150,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th PP RW CN 2020 2020 0 0 OTHER 7,720,000 0 1,280,000 150,000 9,000,000 150,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 17 MPO/RTPO: Class Funding Expenditure Schedule

A-140 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.630 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06856 04/17/18 04/17/18 R2018-011 01 G P S T C B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID venue. Totals 0 980,000 420,000 1,400,000 . PIN/Project No. Totals 0 0 0 1,400,000 0 E Street Extension E Street Extension Capitol Boulevard to Cleveland Avenue Construct new roadway between Capitol Boulevard and Cleveland A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 0 0 0 980,000 0

Priority Number RW 0 0 0 420,000 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE RW 2021 2023 0 0 OTHER OTHER 840,000 140,000 360,000 60,000 1,200,000 200,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 3 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-141 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No. 100,000

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-09927 04/17/18 04/17/18 R2018-011 10 P T W C 0.100 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 2,360,000 1,140,000 3,500,000 torized facilities 079703000000000 . PIN/Project No. Totals 0 400,000 0 0 3,100,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Henderson Blvd. Bridge Henderson Blvd Henderson Blvd to Bridge widening or replacement to add capacity including non-mo Tumwater Thurston TRPC Y Inside N Outside PE 0 400,000 0 0 0 Priority Number CN00003, Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2022 2023 0 0 OTHER OTHER 360,000 2,000,000 1,100,000 40,000 3,100,000 400,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 8 MPO/RTPO: Class Funding Expenditure Schedule

A-142 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type CE No

Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-06837 04/17/18 04/17/18 R2018-011 28 C G P S T B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 1,700,000 0 1,700,000 Mottman Rd. The portion (join road and . PIN/Project No. Totals 100,000 0 0 1,600,000 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Mottman Road Improvements Mottman Road RW Johnson Blvd to Crosby Installation of sidewalk and street improvements on portions project) project will have similar improvements to the City of Olympia's Tumwater Thurston TRPC Y Inside N Outside PE 100,000 0 0 0 0 Priority Number CN 0 0 0 1,600,000 0 Phase 1st 2nd 3rd 4th & 6th 5th SS PE CN 2019 2022 0 0 OTHER OTHER 100,000 1,600,000 0 0 100,000 1,600,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 19 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-143 RW Required

Environmental Type 0.350 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11034 04/17/18 04/17/18 R2018-011 21 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 657,000 0 1,843,000 2,500,000 way 99 and 79th . PIN/Project No. Totals 0 100,000 200,000 540,000 1,660,000 venue. A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Old Hwy 99 / 79th Ave Roundabout Old Highway 99 Old Highway 99 to 79th Avenue Design and construct roundabout at the intersection of Old High Thurston TRPC Y Inside N Outside Tumwater PE 0 100,000 200,000 100,000 0 CN 0 0 0 0 1,660,000

Priority Number RW 0 0 0 440,000 0 Phase 1st 2nd 3rd 4th & 6th 5th SSP PE RW CN 2020 2022 2024 STP(US) STP(US) 346,000 311,000 0 0 0 54,000 129,000 0 400,000 1,660,000 440,000 1,660,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 10 MPO/RTPO: Class Funding Expenditure Schedule

A-144 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.860 CE Yes Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01364 04/17/18 04/17/18 R2018-011 03 G P S T C B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID e Totals 0 5,500,000 3,000,000 8,500,000 oved roundabouts . where appropriate, rm drainage, . PIN/Project No. Totals 0 250,000 2,250,000 2,500,000 3,500,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Old Highway 99 Corridor Improvements, 79th Avenue to 73rd Avenu Old Highway 99 79th Avenue to 73rd Capacity: Add additional through lanes with left turn pockets bicycle lanes and sidewalks on both sides, street lighting, sto landscaping and intersection improvements including new or impr or signalized intersections at Old 99/Henderson and 99/79th Tumwater Thurston TRPC Y Inside N Outside PE 0 250,000 250,000 0 0 CN 0 0 0 2,500,000 3,500,000

Priority Number RW 0 0 2,000,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PPP PE RW CN 2020 2021 2022 0 0 0 OTHER OTHER 1,000,000 4,500,000 0 1,000,000 1,500,000 500,000 2,000,000 6,000,000 500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 9 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-145 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11033 04/17/18 04/17/18 R2018-011 18 2.700 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 400,000 400,000 n Growth Boundary s necessary to t-of-way needs and . PIN/Project No. Totals 400,000 0 0 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Old Highway 99 Corridor Plan & Preliminary Design Old Highway 99 93rd Avenue to 73rd Development of a corridor plan for Old Highway 99 from the Urba at 93rd Avenue to 73rd Avenue. To include preliminary design a determine alignment, cross sections, intersection control, righ project estimates. Tumwater Thurston TRPC Y Inside N Outside

Priority Number PE 400,000 0 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th P PE 2019 0 0 400,000 400,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 14 4 MPO/RTPO: Class Funding Expenditure Schedule

A-146 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program arious WA-01380 04/17/18 04/17/18 R2018-011 05 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 7,500,000 7,500,000 . PIN/Project No. Totals 1,250,000 1,250,000 1,250,000 1,250,000 1,250,000 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Pavement Maintenance Program Various Various to Preservation: Surface maintenance on streets within the city. V Tumwater Thurston TRPC Y Inside N Outside PE 75,000 75,000 75,000 75,000 75,000 Priority Number CN 1,175,000 1,175,000 1,175,000 1,175,000 1,175,000 Phase 1st 2nd 3rd 4th & 6th 5th SS PE CN 2019 2019 0 0 0 0 450,000 7,050,000 450,000 7,050,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 12 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-147 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-01388 04/17/18 04/17/18 R2018-011 28 No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 486,000 486,000 ing treatments. . PIN/Project No. Totals 81,000 81,000 81,000 81,000 81,000 Pedestrian Improvements & Traffic Calming Various Various to Safety: Sidewalk and pedestrian improvements with traffic calm A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 5,000 5,000 5,000 5,000 5,000 Priority Number CN 76,000 76,000 76,000 76,000 76,000 Phase 1st 2nd 3rd 4th & 6th 5th SS PE CN 2019 2019 0 0 0 0 30,000 456,000 30,000 456,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 20 MPO/RTPO: Class Funding Expenditure Schedule

A-148 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-11039 04/17/18 04/17/18 R2018-011 21 0.200 Yes B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 200,000 200,000 . PIN/Project No. Totals 0 170,000 165,000 0 0 Rural Road Shoulder Widening Rural Road 48th Avenue to Linwood Widen road to provide paved shoulder. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 0 150,000 0 0 0 CN 0 0 165,000 0 0

Priority Number RW020,000000 Phase 1st 2nd 3rd 4th 5th & 6th SSS PE RW CN 2020 2020 2021 0 0 0 0 0 0 15,000 20,000 165,000 15,000 20,000 165,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 25 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-149 RW Required

Environmental Type

Total Length

Utility Codes

Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program 5206 WA-03901 04/17/18 04/17/18 R2018-011 28 P T 0.250 CE No B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 459,000 81,000 540,000 nhancements. nstruction, curb ramp . PIN/Project No. Totals 0 30,000 510,000 0 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Safe Routes to Schools: Michael T. Simmons Elementary School Lake Park Drive - 2nd Avenue Lake Park Drive to 2nd Avenue Select sidewalk infill and reconstruction, curb gutter reco reconstruction, curb extensions and various pedestrian safety e Tumwater Thurston TRPC Y Inside N Outside PE 0 30,000 10,000 0 0 Priority Number CN 0 0 500,000 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2020 0 0 SRTS SRTS 34,000 425,000 6,000 75,000 40,000 500,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 21 MPO/RTPO: Class Funding Expenditure Schedule

A-150 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.200 No Total Length

Utility Codes W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10064 04/17/18 04/17/18 R2018-011 01 G P S T C B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 350,000 350,000 . PIN/Project No. Totals 350,000 0 0 0 0 Tumwater Town Center Connection unknown Tumwater Boulevard to 71st Avenue New street connection from Tumwater Blvd. to 71st Avenue. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Tumwater Thurston TRPC Y Inside N Outside PE 100,000 0 0 0 0 Priority Number CN 250,000 0 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PP PE CN 2019 2019 0 0 0 0 100,000 250,000 100,000 250,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 19 14 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-151 This page left intentionally blank.

A-152 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region Yelm Planned Projects Yelm will seek funding. Yelm Planned projects for which for Planned projects

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-153 This page left intentionally blank.

A-154 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type CE No

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10337 07/10/18 07/10/18 593 04 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 100,000 100,000 ires concurrence . PIN/Project No. Totals 20,000 20,000 20,000 20,000 20,000 DA Compliance Annual Program to A A from WSDOT and FHWA. 2. Complete small capital ADA requirement needs. 3. Utilize funds as match needed for larger project grants. City Wide City Wide Program for: 1. Assistance in Completing the Transition Plan Report that requ C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Y Thurston TRPC Y Inside N Outside Priority Number ALL 20,000 20,000 20,000 20,000 20,000 Phase 1st 2nd 3rd 4th & 6th 5th SSSS ALLS ALL ALL ALL ALL 2019 2020 2021 2022 2023 0 0 0 0 0 0 0 0 0 0 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 19 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-155 RW Required

Environmental Type CE No

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10280 07/10/18 07/10/18 593 05 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 280,000 280,000 of the City’s ided chip seal of overlay to maintain Local funds are ’s pavement overlays of our City of the 20 year needs will . PIN/Project No. Totals 50,000 50,000 50,000 50,000 50,000 nnual Overlay Program to This program provides funds as match for future grants full Streets and/or preservation and maintenance through County prov our roadways. This project provides annual funding for the City management program. Based on an annual review of the condition roadways, a road segment or segments are selected for repair the integrity of City’s street system. A true cost analysis be performed in 2018 as part of the Transportation Plan Update. required for ADA compliance in paving the roadways. A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Thurston TRPC Y Inside N Outside Y Priority Number ALL 50,000 50,000 50,000 50,000 50,000 Phase 1st 2nd 3rd 4th & 6th 5th S ALL 2019 0 0 280,000 280,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 16 MPO/RTPO: Class Funding Expenditure Schedule

A-156 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type EA Yes

Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm 13 14 07/11/17 07/11/17 578 18 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 0 20,000 20,000 anisms to support the ing opportunities with . This is a stormwater resolves seasonal flooding 00000 . PIN/Project No. Totals00000 to A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description management project. The feasibility study will provide for fund the selected alternative. Bald Hill Road from City limits to 5 Corners Bald Hill Road This project is a feasibility study to identify that project of the feasibility study to include permitting barriers issues. Additional work includes identification of funding mech elm Y Thurston TRPC Y Inside N Outside Priority Number Phase 1st 2nd 3rd 4th & 6th 5th S ALL 2019 0 0 20,000 20,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 07 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-157 RW Required

Environmental Type 0.200 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10294 07/10/18 07/10/18 593 03 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 700,000 0 600,000 1,300,000 have not been Road and 93rd . PIN/Project No. Totals 0 150,000 150,000 150,000 850,000 signal at 93rd Avenue requires the realignment of both Burnett venue to align with each other – true commercial land ROW costs Burnett/93rd Intersection - Realignment & Traffic Signal Yelm Ave SE / SR510 Burnett RD SE to 93rd Ave calculated for a true project cost estimate. A A A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Y Thurston TRPC Y Inside N Outside Priority Number ALL 0 150,000 150,000 150,000 850,000 Phase 1st 2nd 3rd 4th 5th & 6th P ALL 2020 HSIP 700,000 0 600,000 1,300,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 12 MPO/RTPO: Class Funding Expenditure Schedule

A-158 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.240 DCE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program WA-10293 07/10/18 07/10/18 593 01 C G O P S B. STIP ID s State Fund Code State Funds Local Funds Total Funds G. Structure ID lude sidewalks, Totals 186,676 1,643,574 434,615 2,264,865 g and irrigation way on Coates r, sewer, S.T.E.P. (septic . PIN/Project No. Totals 233,345 37,200 997,160 997,160 0 venue NW between Killion Road and Cullens Road. Design will inc A A tank effluent pumping), reclaimed water services for landscapin systems, power, gas, and a future fiber system for SCADA. curbs, gutters, full utilities, street lights, stormwater, wate C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Coates Ave NW - Killion to Cullens RD Coates Ave NW Killion St SE to Cullens RD Project will provide approximately 1300 linear feet of new road elm Y Thurston TRPC Y Inside N Outside PE 233,345 0 0 0 0 CN 0 0 997,160 997,160 0

Priority Number RW 0 37,200 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PPPP PE RW CN CN 2020 2021 2021 2022 Discretionary 186,676 0 0 0 TIB OTHER OTHER 0 805,698 32,178 805,698 46,669 191,462 5,022 191,462 233,345 997,160 997,160 37,200 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-159 RW Required

Environmental Type 0.200 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm5B 16 07/10/18 07/10/18 593 03 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 1,000,000 0 450,000 1,450,000 ed project cost perty for the ROW. . PIN/Project No. Totals 0 0 0 150,000 1,300,000 signal at Longmire/SR 510 Intersection requires commercial pro A A True commercial ROW costs have not been calculated for an updat estimate. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description Longmire / SR 510 Intersection - Traffic Signal SR 510 (W Yelm Ave) SW Longmire St to NW elm Y Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 0 150,000 1,300,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2022 HSIP 1,000,000 0 450,000 1,450,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 12 MPO/RTPO: Class Funding Expenditure Schedule

A-160 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.220 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm 16 25 07/10/18 07/10/18 593 28 G O P S C s State Fund Code State Funds Local Funds Total Funds G. Structure ID th Loop SE Totals 0 517,500 90,000 607,500 oject. Project g Mill Road from 104th . PIN/Project No. Totals 348,750 258,750 0 0 0 ve SE to 107th Loop SE. Installation of an RRFB at Cochrane Park is also part the pr Mill Road SE Pedestrian and Bike Improvements – 104th to 107 SE 2nd St and Conchrane Park Mill Rd SE to Mosman Ave Project constructs ~1150 feet of sidewalk, curb and gutter alon A A completes a gap and an alternative route to SR507 for safety. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Y Thurston TRPC Y Inside N Outside PE90,0000000 Priority Number CN 258,750 258,750 0 0 0 Phase 1st 2nd 3rd 4th 5th & 6th SPP PE CN CN 2019 2019 2020 0 0 0 SRTS TIB 258,750 258,750 0 0 90,000 0 258,750 90,000 258,750 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-161 RW Required

Environmental Type 0.250 CE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm 13 01 07/10/18 07/10/18 593 01 G O P S C s State Fund Code State Funds Local Funds Total Funds G. Structure ID 0000 Totals 338,100 1,043,493 216,729 1,598,322 of new road from Longmire St with ks,street lighting, ween Solberg St . PIN/Project No. Totals 391,972 1,206,350 0 0 0 and Railroad St the new Mosman Avenue intersection. Will add bike lanes,sidewal and stormwater improvements. Improvements include construction Longmire St to Solberg St, and reconstruction of Mosman Ave bet Mosman Ave Phase II Mosman Ave Longmire Street to Railroad The proposed improvements will construct a new road connecting A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Y Thurston TRPC Y Inside N Outside CN 0 1,206,350 0 0 0

Priority Number RW 391,972 Phase 1st 2nd 3rd 4th & 6th 5th SP RW CN 2019 2020 STP 338,100 0 TIB 0 1,043,493 53,872 162,857 391,972 1,206,350 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 1 / Y341(001) MPO/RTPO: Class Funding Expenditure Schedule

A-162 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region RW Required

Environmental Type 0.410 DCE Yes Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm 16 10 07/10/18 07/10/18 593 01 C G O P S s State Fund Code State Funds Local Funds Total Funds G. Structure ID Ave to Clark Totals 3,893,398 836,680 774,978 5,505,056 proximately .41 h Area. e project corridor is igation systems, ights, stormwater, . PIN/Project No. Totals 271,656 1,050,000 1,394,467 2,788,933 0 A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description miles of roadway to include curbs, gutters, sidewalks, street l water, sewer, S.T.E.P., reclaimed water for landscaping and irr power, gas, and future fiber system for SCADA. A portion of th Mosman Ave E Phase 3 - 2nd to Clark Rd Mosman Ave E SE 2nd ST to Clark RD The City of Yelm proposes to improve SE Mosman Avenue from 2nd Rd. The work includes reconstruction and new construction of ap located in Thurston County, within the City of Yelm Urban Growt elm Thurston TRPC Y Inside N Outside Y PE 271,656 0 0 0 0 CN 0 0 1,394,467 2,788,933 0

Priority Number RW 0 1,050,000 0 0 0 Phase 1st 2nd 3rd 4th & 6th 5th PPPP PE RW CN CN 2019 2020 2021 2022 STP STP STP STP 234,982 908,250 916,722 1,833,444 OTHER OTHER 278,893 557,787 0 0 198,852 397,702 36,674 141,750 1,394,467 2,788,933 271,656 1,050,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 17 MPO/RTPO: Class Funding Expenditure Schedule

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region A-163 RW Required

Environmental Type 4.000 CE No Total Length

Utility Codes T W Improvement Type From 2019 to 2024

Resolution No.

Amendment

Adopted

Hearing Six Year Transportation Improvement Program B. STIP ID Yelm 16 09 07/11/17 07/11/17 578 28 G O P S C s State Fund Code State Funds Local Funds Total Funds G. Structure ID Totals 0 5,880,000 1,470,000 7,350,000 . PIN/Project No. Totals 0 0 0 0 1,600,000 Rail Trail - Power Canal to Roy Yelm Prarie Line Trail Canal Road Yelm to City of Roy Project Number Y7B Extend the Yelm Prairie Line Trail to City of Roy. A C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description elm Y Thurston TRPC Y Inside N Outside Priority Number ALL 0 0 0 0 1,600,000 Phase 1st 2nd 3rd 4th & 6th 5th P ALL 2022 0 OTHER 5,880,000 1,470,000 7,350,000 County: Agency: Functional Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund 00 MPO/RTPO: Class Funding Expenditure Schedule

A-164 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDIX B

REGIONAL ROAD-RELATED FINANCIAL PLAN FOR LOCAL AGENCIES

Financial constraint governs transportation planning and programming in the Thurston region. Local jurisdictions generate the majority of revenues necessary to preserve and improve transportation mobility.

While the RTIP focuses primarily on construction projects, maintenance and preservation of the existing system are equally high priorities for local jurisdictions. It is worth noting that many construction projects also provide signifi cant benefi t for system preservation.

Using “Thurston County Road and City Street Revenues and Expenditures” data provided by WSDOT and based on local agency accounting data, a planning-level forecast of revenues and expenditures is developed for the RTIP based on an evaluation of actual expenditures and revenues over the last several years and calibrated with approved Regional Transportation Plan assumptions. Region-wide totals are provided since the base data does not allow for a breakout between MPO and non-MPO jurisdictions.

Based on this planning forecast and Table 5, it is determined that the projects identifi ed in the 2019-2022 RTIP are fi nancially feasible as local agencies continue to make adjustments in discretionary spending and adopt more local funding options.

Table 6 Regional Road-Related Financial Projections (In Thousands of Constant 2015 Dollars)

Notes:

1. Costs and revenues exclude those associated with Traffi c Policing. 2. See the 2040 Regional Transportation Plan for detailed assumptions regarding individual revenue sources by incorporated and unincorporated jurisdiction. 3. See the 2040 Regional Transportation Plan for detailed assumptions regarding expenditure types by incorporated and unincorporated jurisdiction.

2019-2022 Regional Transportation Improvement Program for the Thurston Region B-1 This page left intentionally blank.

B-2 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDIX C

AIR QUALITY CONFORMITY

This appendix documents that the 2019-2022 Regional Transportation Improvement Program (RTIP) for the Thurston Region achieves and maintains the National Ambient Air Quality Standards (NAAQS) as required by the Clean Air Act Amendments of 1990, and meets the requirements set forth in WAC 173-420 and the Thurston County Second 10-Year Limited Maintenance Plan for particulate matter 10 micrometers or smaller in diameter (PM10). The federal Clean Air Act, the Washington Clean Air Act, and the federal Moving Ahead for Progress in the 21st Century (MAP-21) Act require this fi nding of conformity. Federal 40 CFR Part 93 and state WAC 173-420 identify governing rules. Specifi cally, the RTIP does not:

• Cause or contribute to any new violation of the federal air quality standards for PM10. • Increase the frequency or severity of any existing violation of the standards. • Delay timely attainment of the standards.

Air Quality Designation

Thurston County violated the 24-hour 1987 National Ambient Air Quality Standard (NAAQS) for particulate matter

ten microns or smaller (PM10) in the winter of the late 1980s. When the 1990 Clean Air Act Amendments (CAAA) were passed, the Environmental Protection Agency (EPA) designated the Thurston County Maintenance Area (TCMA)

a nonattainment area, or an area out of compliance with the PM10 standard. The area attained the standard by 1991 after the source of the air quality violations (wood smoke) was reduced. The area was re-designated by EPA to a Figure 6: Thurston Region PM10 Maintenance Area maintenance area in December 2000 and has remained in compliance with the standard since that time. The region is now operating under their second 10-year maintenance White Area is the PM100 Maintenance Area plan approved with an eff ective date of November 4, 2013. By December of 2020, the region should no longer be a maintenance area. The Thurston County maintenance area is approximately the 1987 city limits for Lacey, Olympia, and Tumwater. Figure 6 identifi es the part of the region to which the maintenance status applies. The Olympic Region Clean Air Agency (ORCAA) monitored PM10 until 2011, at which time monitoring was discontinued. The approved Second 10-Year Limited Maintenance Plan does not contain a motor vehicle emission budget, and regional emissions analyses are no longer required as part of the transportation conformity demonstration for PM10. However, all other transportation conformity requirements of 40 CFR part 93 subpart A continue to apply. • Conformity of transportation plans is determined no less frequently than every four years, and conformity of plan amendments and transportation projects is demonstrated in accordance with the timing requirements specifi ed in 40 CFR 93.104. • The Metropolitan Planning Organization’s (MPO) interagency consultation procedures meet applicable requirements of 40 CFR 93.105 and 40 CFR 93.112.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region C-1 • Transportation plans and projects comply with the fi scal constraint element per 40 CFR 93.108. • Transportation plans and projects provide for timely implementation of SIP transportation control measures in accordance with 40 CFR 93.113. • The latest planning assumptions and emissions model are used as set forth in 40 CFR 93.110 and 40 CFR 93.111, and 40 CFR 93.118.

• Projects do not cause or contribute to any new localized PM10 violations in accordance with procedures specifi ed in 40 CFR 93.116 and 40 CFR 93.123. • Project sponsors and/or operators provide written commitments as specifi ed in 40 CFR 93.125.

Latest Planning Assumptions and Documentation

As required by §93.110, this conformity determination is based on the latest planning assumptions. Population and employment forecasts used in the travel demand model are for base year 2015. This represents the recently adopted region-wide land use forecasts, as amended in July 2015 to extend the forecast horizon to 2040 and include updated base year employment data. The travel demand model was completely updated in 2015 and covers the time period from 2015 through 2040. The travel demand model was calibrated to an updated household travel survey (2013) and 2014 traffi c counts. It includes an updated base and future year network of streets, transit routes, and trails. Technical documentation can be found on-line by following these links: Population and Employment Forecast for Thurston County: http://www.trpc.org/236/Population-Employment-Forecasting Travel Demand Model Assumptions and Methodologies: http://www.trpc.org/319/Travel-Demand-Modeling 2025 Regional Transportation Plan (includes base and forecast year characteristics) http://www.trpc.org/662/2040-RTP All documents are also available by calling TRPC at (360) 956-7575.

Consultation

TRPC confers regularly with the state’s Air Quality Consultation Group. The group is comprised of representatives from the Environmental Protection Agency, the State’s Department of Ecology, the Federal Transit Administration, the Federal Highway Administration, and the Washington State Department of Transportation. The consultation group provides direction on how to comply with conformity requirements. The Consultation Group reviews assumptions, methodologies, process and fi ndings before any project included in the RTIP proceeds. The Air Quality Conformity Finding is published in both the draft and fi nal RTIP. During the public comment period, TRPC publicizes and distributes the RTIP widely to encourage the widest possible opportunity for public comment. TRPC is scheduled to adopt the RTIP and conformity fi nding on October 5, 2018. Any public comment received during the public comment period will be presented to TRPC before they take action to adopt.

C-2 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region Findings

TRPC’s regional transportation model provides average daily VMT data for the long range planning horizon. Based on that data, the annual growth rates are: Table 7 Annual VMT Growth Rate PERIOD ANNUAL VMT GROWTH RATE 2010-2020 0.82% 2020-2030 1.29% 2030-2040 1.14%

These projections are well below the 6.3% Margin of Safety growth rate identifi ed in the Thurston County Second 10-Year

Limited Maintenance Plan for PM10 that would trigger conformity concerns. Therefore, TRPC fi nds that the projects included in this RTIP will not cause or contribute to any new violation of the federal air quality standards for PM10.

Statement of Conformity

The 2019-2022 Thurston Regional Transportation Improvement Program achieves and maintains the NAAQS as required by the Clean Air Act Amendments of 1990, and meets the requirements set forth in WAC 173-420 and the Thurston

County Second 10-Year Limited Maintenance Plan for PM10.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region C-3 This page left intentionally blank.

C-4 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDIX D

PERFORMANCE MEASURES

Performance Based Approach to Planning

Federal 23 USC Part 134 directs metropolitan planning organizations (MPOs) to take a performance-based approach to transportation planning. Specifi cally, as the MPO for the Thurston Region, Thurston Regional Planning Council (TRPC) is required to establish performance targets under the performance measure framework laid out in as laid out in federal rule 23 CFR Part 49.105. The framework gives fl exibility to TRPC to either support Washington State Department of Transportation’s (WSDOT) statewide performance measure targets, or to establish targets for the MPO boundary, depending on the performance measure, 180 days after WSDOT or the public provider of transportation in our region (Intercity Transit) develops performance measure targets. If MPO supports a WSDOT target, they also must agree to plan and program projects so that they contribute toward the accomplishment of the relevant WSDOT target. In 2017 and 2018, TRPC adopted MPO or supported WSDOT performance measure targets relating to the following subject areas. • Safety • Pavement & bridge • System performance/congestion • Freight movement • Congestion mitigation & air quality • Transit asset management

Transportation Improvement Program and Performance Measures

Federal 23 USC Part 134 directs that “the transportation improvement program shall include, to the maximum extent practicable, a description of the anticipated eff ect of the transportation improvement program toward achieving the performance targets established in the metropolitan transportation plan, linking investment priorities to those performance targets.” Table 8 provides a summary of performance measures that can be related to specifi c projects shown in Table 3. Table 8 Performance Measures

Subject Area and Performance Measure Code Safety Number of fatalities on all public roads S-1 Number of fatalities per 100 million vehicle miles traveled (VMT) on all public roads S-1 Number of serious injuries on all public roads S-1 Number of serious injuries per 100 million VMT on all public roads S-1 Number of non-motorist fatalities and serious injuries on all public roads S-2

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region D-1 Pavement Percent of Interstate Pavement on the National Highway System in good condition P-1 Percent of Interstate Pavement on the National Highway System in poor condition P-1 Percent of non-Interstate Pavement on the National Highway System in good condition P-2 Percent of non-Interstate Pavement on the National Highway System in poor condition P-2 Percent of National Highway System Bridges classifi ed in good condition (weighted by B-1 deck area) Percent of National Highway System Bridges classifi ed in poor condition (weighted by B-1 deck area) Highway System Performance (Congestion) Percent of person-miles traveled on the Interstate System that are reliable C-1 Percent of person-miles traveled on the Non-Interstate National Highway System that are reliable C-2 Freight Truck Travel Time Reliability (TTTR) Index (on the Interstate System) F-1 Congestion Mitigation and Air Quality Particulate Matter less than 10 microns (PM10) (kg/day) A-1 Transit Asset Management Equipment: The percentage of non-revenue service vehicles (by type) that meets or exceeds the T-1 (ULB) Rolling Stock: The percentage of revenue vehicles (by type) that meets or exceeds the ULB (Buses, T-2 Paratransit Vans, and Vanpools) Facilities: The percentage of facilities (by group) that are rated less than 3.0 on the Transit T-2 Economic Requirements Model (TERM) Scale

D-2 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region Supporting Information

Figures 7 and 8 provide maps of the National Highway System for reference.

Figure 7: National Highway System, Thurston County

Figure 8: National Highway System, Urban Area

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region D-3 Provided below are the bridges listed in WSDOT’s performance measure data set. There are three local bridges in the inventory, and 59 WSDOT bridges.

Owner Bridge Number Name City (Tumwater) 2 CAPITOL BOULEVARD XING City (Olympia) 1 Olympia-Yashiro Bridge City (Olympia) 0000001A WEST OLYMPIA-YASHIRO BR WSDOT 101/502E SCHNEIDER CREEK WSDOT 101/502W SCHNEIDER CREEK WSDOT 101/506E PERRY CR WSDOT 101/506W PERRY CR WSDOT 101/507 2ND AVE SW OVER US 101 WSDOT 101/508E MUD BAY WSDOT 101/508W MUD BAY WSDOT 101/510 EVERGREEN PKWY OVER US 101 WSDOT 101/512 US 101 OVER BLACK LAKE BLVD WSDOT 101/513E US 101 OVER PERCIVAL CR WSDOT 101/513W US 101 OVER PERCIVAL CR WSDOT 101/515E-N US 101 OVER I-5 WSDOT 101/515E-S E-S RAMP OVER S-S RAMP WSDOT 510/1 SR 510 OVER I-5 WSDOT 5/302E PRAIRIE CREEK WSDOT 5/302W PRAIRIE CREEK WSDOT 5/305 SCATTER CREEK WSDOT 5/308 I-5 OVER SR 121-MAYTOWN WSDOT 5/314 TROSPER RD OVER I-5 WSDOT 5/315 I-5 OVER LINWOOD AVE WSDOT 5/320 I-5 OVER DESCHUTES PKWY WSDOT 5/320S-W S-W RAMP WSDOT 5/321 CAPITOL LAKE WSDOT 5/322 CAPITOL BLVD OVER I-5 WSDOT 5/323 I-5 OVER RAILROAD WSDOT 5/324 I-5 OVER HENDERSON BLVD WSDOT 5/324W-S W-S RAMP OVER HENDERSON WSDOT 5/325A N-14TH RAMP WSDOT 5/325N-W N-W RAMP WSDOT 5/325S-W S-W RAMP WSDOT 5/327E-N PLUM-N RAMP OVER EASTSIDE WSDOT 5/327S-W S-PLUM RAMP OVER EASTSIDE WSDOT 5/328E-N PLUM ST RAMP OVER I-5

D-4 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region WSDOT 5/332 I-5 OVER PACIFIC AVE WSDOT 5/332W-S W-S RAMP WSDOT 5/335 SLEATER-KINNEY OVER I-5 WSDOT 5/336 COLLEGE ST OVER I-5 WSDOT 5/337E I-5 OVER MARTIN WAY WSDOT 5/337W I-5 OVER MARTIN WAY WSDOT 5/339 CARPENTER RD OVER I-5 WSDOT 5/342E MCALLISTER CR WSDOT 5/342N-E MCALLISTER CR WSDOT 5/342W MCALLISTER CREEK WSDOT 5/342W-S MCALLISTER CR WSDOT 5/344E NISQUALLY R-SO OVERFLOW WSDOT 5/344S-E S-E RAMP WSDOT 5/344W NISQUALLY OVERFLOW WSDOT 5/345E NISQUALLY RIVER WSDOT 5/345W NISQUALLY RIVER WSDOT 8/104N SR 8 OVER US 101 WSDOT 8/104S SR 8 OVER US 101 WSDOT 12/102 OVERFLOW CHANNEL WSDOT 12/104C SLOUGH WSDOT 12/106 SLOUGH WSDOT 12/108 SLOUGH WSDOT 12/111 SCATTER CREEK WSDOT 12/114 US 12 OVER RAILROAD WSDOT 12/117 US 12 OVER TACOMA RR WSDOT 12/118 US 12 OVER I-5

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region D-5 This page left intentionally blank.

D-6 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region APPENDIX E

PUBLIC PARTICIPATION SUMMARY

Distribution and Notifi cation

Copies of the draft 2019-2022 Regional Transportation Improvement Program (RTIP) were available for public review beginning on Wednesday, September 5, 2018. Copies were available free of charge, upon request to TRPC. The document was also available for viewing or download on the agency’s website, at www.trpc.org. Notice of Availability was published in the September 5, 2018, and September 12, 2018, editions of The Olympian. Notice was also posted on the TRPC website. The public review period extended from Wednesday, September 5, 2018, through Wednesday, September 19, 2018. Comments on the draft 2019-2022 RTIP were requested by the close of business on September 19, 2018, either by mail, by fax, or via email, for presentation with the fi nal draft of this document to TRPC on October 5, 2018.

Copy of Legal Notice NOTICE OF AVAILABILITY AND PUBLIC COMMENT FOR THE DRAFT 2019-2022 REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM NOTICE IS HEREBY GIVEN that the Thurston Regional Planning Council (TRPC) invites the public to comment on the draft 2019-2022 Regional Transportation Improvement Program (RTIP). The RTIP identifi es funding secured state sponsored, federally funded, and regionally signifi cant transportation projects in Thurston County. It also lists planned projects for which agencies will seek funding over the next six years. The document is available free of charge online at www.trpc.org or by request to TRPC at 2424 Heritage Court SW, Suite A, Olympia, WA 98502; (360) 956-7575. Written comments may be submitted to Holly Gilbert, TRPC, by mail, email to [email protected], or FAX at (360) 956-7815. Comments should be received by 5:00 p.m., September 19, 2018.

Staff and Agency Review

The draft RTIP was also made available for review to members of the Technical Advisory Committee, and to staff at the following agencies: Federal Transit Administration; Federal Highways Administration; WSDOT Olympia Service Center; WSDOT Olympic Region; Puget Sound Regional Council; Mason County; Grays Harbor County; Lewis County; Pierce County; and Olympic Region Clean Air Agency.

Comments

Comment from WA State Dept. of Transportation (WSDOT) WSDOT commented to provide administrative technical corrections on project entries in the online STIP database on various projects. Those corrections have been made and the updated record is included in the Final RTIP. Tables 3 - 5 of the document were updated to refl ect these revisions as needed.

Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region E-1 Comment from WA State Dept. of Ecology The WA State Department of Ecology submitted the following comment: “At a high level, climate change is absent from the plan. Addressing that issue should be part of any transportation plan. The terms, “climate change,” “global warming,” “greenhouse gas,” and “carbon dioxide” do not appear at all. There is one electric vehicle charging project mentioned. I understand that much of the plan refers to maintenance projects, so perhaps there’s not a clear connection to emissions reductions. However, there is an opportunity to emphasize reduced GHG emissions from improved (or maintained) public transit and pedestrian facilities.” In response, the following language has been added to the Air Quality Conformity section on page 7 of the RTIP: “The Regional Transportation Plan (RTP) acknowledges that changing climate patterns will impact the region and includes policies that call for reductions in per capital vehicle miles traveled to help limit production of greenhouse gases by gasoline- and diesel-powered vehicles. The same RTP policies that promote the reduction of PM10 also work to limit production of greenhouse gases from vehicles. All RTIP projects are evaluated for consistency with the RTP.”

E-2 Draft 2019-2022 Regional Transportation Improvement Program for the Thurston Region