The A new road and bicycle highway along the R22

Roadworks in the Woluwedal This year, De Werkvennootschap will start to construct the F202 bicycle highway along the R22 which will connect with in the Woluwedal. At the same time, the roadworks are also being completed. Whilst constructing the new bicycle highway along the R22, we will be doing roadworks at the junctions with Leuvensesteenweg (N2) and Tramlaan. In addition, we are completing the redesign of the Woluwedal. Cyclists will be able to cross Leuvensesteenweg safely using a new bicycle tunnel. Coordinated approach within the scheduled turnaround time

It was a deliberate decision to have a single construction company, De Werkvennootschap, to prepare and coordinate all the works. This allows us to monitor and implement two projects simultaneously in the same roadworks zone. Smart planning means the construction of the bicycle tunnel and bicycle highway - which were not included in the original Woluwedal renovation plans - will not increase the overall turnaround time. The Fast access to overhaul of the second carriageway of the regional road is expected to take about The F202 15 months; construction of the new bicycle The F202 is part of the Fiets-GEN regional express highway and tunnel will not change this network: 400 km of safe and comfortable cycle timing. paths around Brussels and in the periphery. This project aims to encourage commuters to cycle to work as often as possible.

Safe and speedy alternative

- The F202 bicycle highway is being constructed along the eastern side of the R22 which connects Zaventem with the Kraainem area. - The F202 joins the F203, leading to the Brussels- Capital Region and the HST cycle route. - Cyclists will be able to cross Leuvensesteenweg safely and quickly through a bicycle tunnel.

Bicycle tunnel beneath the N2 The aim of the new project is to create a pleasant and spacious tunnel with plenty of natural light. Progress of the works

Phase 1a Phase 3b The initial preparatory works are being Estimated duration: 6 months carried out on behalf of the The junction between Oudstrijderslaan and Environment Agency. During this phase, the the R22 will be completed in this phase. The River will be channelled along its reconstruction of the R22 north of the N2 definitive course. The new course of the river and the junction with the N2 on the western will be excavated and the existing sewage side will continue in this phase. system will be relocated. Phase 4 Phase 1b Simultaneously with the 3 previous phases. To ensure the smooth flow of traffic while Large sections of the bicycle highway the bicycle tunnel is being built, we are will be built at locations across the adding a temporary bypass to the north of entire project zone. Ventweg will also be Leuvensesteenweg (N2). reconstructed and several smaller tasks will be done. For example, we will Phase 2 create green areas and build Estimated duration: 9 months a retaining wall at the During this phase, we will be building the exit from the E40. Zaventem bicycle tunnel under Leuvensesteenweg. Underground utilities will need relocating and new sewage systems will be required as Borrestraat a result. The junction between Tramlaan and the R22 is being rebuilt.

Phase 3a Broekstraat

Kleine Kerkstraat Estimated duration: 1 month Sint-Stefaansstraat R22 In this phase, the R22 north of Frans Smoldersstraat the N2 and the junction Veste Phase 1A & Phase 1B with the N2 on the western Liekendael Phase 3 side will be reconstructed. Sint-Stevens-Woluwe There will also be work on the junction between Leuvensesteenweg Oudstrijderslaan and the R22.

Phase 2 Julien Trekkerstraat

E40

Kleinenbergstraat

Tramlaan Bevrijdingslaan Oudstrijderslaan

E40 Phase 4 Jozef Van Hovestraat

Brussel R22

Sint-Lambrechts-Woluwe Diversions during the works

During phases 1a and 1b - Most of the work will be done away from the existing road, meaning that no traffic diversions will be required.

During phase 2 - The R22 will be narrowed to 1 lane - The junction between Tramlaan and instead of 2. There will be a single lane the R22 will be blocked off completely. in each direction. The traffic will be diverted via - Turning points will be created on the Bevrijdingslaan to the west of the R22 R22, well away from the roadworks and Leuvensesteenweg. zone, both on the northern and the - Voordestraat, Jozef van Hovestraat southern side. The temporary situation and the companies on the parallel can be understood as a large, road will remain accessible. extended roundabout like the one that regulated the traffic during the previous works on the Woluwedal. - Leuvensesteenweg will remain Zaventem accessible. Coming from Zaventem,

however, the traffic will need to use R22 the turning point.

Borrestraat Blue route Diversion for motorised traffic

Broekstraat Impeded access

Kleine Kerkstraat Sint-Stefaansstraat Roadwork zone Phase 2 Frans Smoldersstraat Veste

Liekendael Sint-Stevens-Woluwe

Leuvensesteenweg Zaventem Eversestraat

Julien Trekkerstraat Leuven E40 R22 Fase 2

Lange Wagenstraat

Kleinenbergstraat

Tramlaan

Bevrijdingslaan Borrestraat Leuvensesteenweg Oudstrijderslaan Blue route Diversion for motorised traffic E40 Jozef Van Hovestraat Bevrijdingslaan Broekstraat Impeded access

R22 Kleine Kerkstraat Brussel Sint-Stefaansstraat Roadwork zone Phase 2 Frans Smoldersstraat Veste Sint-Lambrechts-Woluwe

Liekendael Sint-Stevens-Woluwe

Leuvensesteenweg

Eversestraat

Julien Trekkerstraat Leuven E40

Fase 2

Lange Wagenstraat

Kleinenbergstraat

Tramlaan Bevrijdingslaan Leuvensesteenweg Oudstrijderslaan

E40 Jozef Van Hovestraat Bevrijdingslaan

R22 Brussel

Sint-Lambrechts-Woluwe Zaventem

R22 Detail Leuvensesteenweg - R22

Borrestraat

R22

Broekstraat Leuvensesteenweg Kleine Kerkstraat Sint-Stefaansstraat

Frans Smoldersstraat Veste

Liekendael Sint-Stevens-Woluwe

Leuvensesteenweg Zaventem

Julien Trekkerstraat

R22 Leuven E40 Detail Leuvensesteenweg - R22 Phase 2 Borrestraat

Kleinenbergstraat Blue route R22 Tramlaan Diversion for motorised traffic Bevrijdingslaan Oudstrijderslaan Broekstraat Green route Diversion for bicycle traffic Leuvensesteenweg E40 Kleine Kerkstraat Sint-Stefaansstraat Jozef Van Hovestraat

Frans Smoldersstraat Impeded access Veste

Brussel R22 Liekendael Roadwork zone Sint-Stevens-Woluwe Phase 2

Leuvensesteenweg Sint-Lambrechts-Woluwe

Julien Trekkerstraat Leuven E40

Phase 2 Zaventem

Kleinenbergstraat Blue route R22 Tramlaan Diversion for motorised traffic Bevrijdingslaan Oudstrijderslaan Borrestraat Blue route Diversion for motorised traffic Zaventem Green route E40 Diversion for bicycle traffic Broekstraat Impeded access Jozef Van Hovestraat

Kleine Kerkstraat Sint-Stefaansstraat Roadwork zone Phase 2 Impeded access Frans Smoldersstraat Veste Brussel R22 Liekendael R22 Sint-Stevens-Woluwe Detail Roadwork zone Leuvensesteenweg - PhaseR22 2

Leuvensesteenweg

Eversestraat Borrestraat

Julien Trekkerstraat Leuven Sint-Lambrechts-Woluwe E40Zaventem R22 Fase 2

Lange Wagenstraat

Kleinenbergstraat

Tramlaan Bevrijdingslaan Leuvensesteenweg Oudstrijderslaan

E40 Broekstraat Jozef Van Hovestraat R22 Bevrijdingslaan Leuvensesteenweg

R22 Kleine Kerkstraat Sint-Stefaansstraat Detail Brussel Leuvensesteenweg - R22

Sint-Lambrechts-Woluwe Frans Smoldersstraat Borrestraat Veste

R22 Liekendael Sint-Stevens-Woluwe

Broekstraat Leuvensesteenweg Leuvensesteenweg Kleine Kerkstraat Sint-Stefaansstraat

Frans Smoldersstraat Julien Trekkerstraat Veste Leuven E40 Liekendael Sint-Stevens-Woluwe Phase 2

Kleinenbergstraat Blue route Tramlaan Diversion for motorised traffic Bevrijdingslaan Oudstrijderslaan Leuvensesteenweg Green route E40 Diversion for bicycle traffic Jozef Van Hovestraat

Julien Trekkerstraat Leuven Impeded access Brussel E40R22 Roadwork zone Phase 2 Phase 2

Kleinenbergstraat Blue route Tramlaan Sint-Lambrechts-WoluweDiversion for motorised traffic Bevrijdingslaan Oudstrijderslaan

Green route E40 Diversion for bicycle traffic Jozef Van Hovestraat

Impeded access

Brussel R22 Roadwork zone Phase 2

Sint-Lambrechts-Woluwe Brussel Sint-Stevens-Woluwe

Bevrijdingslaan E40

Kleinenbergstraat Leuvensesteenweg

Tramlaan

Sint-Stefaansstraat Liekendael Kleine Kerkstraat Kleine

R22 Broekstraat Phase 2 Sint-Lambrechts-Woluwe

Phase 4

Phase 3 Veste Borrestraat Phase 1A&1B R22

Julien Trekkerstraat Jozef Van Hovestraat Van Jozef

Frans Smoldersstraat Oudstrijderslaan E40 Zaventem Leuven or [email protected]. to 5pm) on0477958309 adviser You cancontactthe accessibility? Questions about duringofficehours(9am accessibility

werkenaandering.be/F202 highway project at about theF202bicycle You willfindmoreinformation date to up Stay latest newsabouttheworks. to stayupdatewiththe newsletter onthatwebpage Subscribe totheF202 Fund (ERDF). from theEuropeanRegional Development This projectwasimplemented withsupport .

V.U. Wouter Casteels, p/a . Botanic Tower, Sint-Lazaruslaan 4-10, 1210 Brussel