Appendix 3 to Council Resolution from 25.12.2013 in redaction approved by City Council Resolution from 30.07.2013

CONCEPT OF THE INDUSTRIAL PARK “CENTRAL” IN

1

CONTENT

page 1. Industrial park “CENTRAL” in Kremenchuk. 4 1.1 Introduction. 4 1.2 Industrial park “CENTRAL” in Kremenchuk. 5 1.2.1 in the East Europe. 5 1.2.2 as a part of . 5 1.2.3 Kremenchuk district as a part of Poltava oblast. 6 1.2.4 Kremenchuk on the map of Ukraine. 7 2. The initiator of the industrial park creation 8 2.1 General provisions. 8 2.2 Kremenchuk City Council. 9 3. The aim and task of creation and functioning of the 10 industrial park. 3.1 The aim of the industrial park creation. 10 3.2 The task of the industrial park creation. 10 3.3.The functioning of the industrial park 11 3.3.1 Priority economic industries for development within the 11 boundaries of the industrial park. 3.3.1.1 Sector 1 – «Hi-Tech» (mechanic engineering). 12 3.3.1.2 Sector 2 – «Logistics» (logistics). 12 3.3.1.3 Sector 3 – «TechnoPolis» (ІТ- technologies 12 andelectronics). 3.3.1.4 Sector 4 – «EcoLife» (reserve sector). 12 3.3.1.5 Sector 5 – «Еnergetics» (alternative energy and 12 engineering) 3.3.2 Business-city. 12 3.4 Organization of the industrial park "CENTRAL" 13 functioning. 3.4.1 Procedure for the industrial park creation. 13 3.4.2 Sources of funding for creation and functioning of the 14 industrial park. 4.Industrial and economic potential of Kremenchuk. Location and 17 land parcel size. 4.1 Poltava oblast. 17 4.2 Industrial and economic potential of Kremenchuk. 17 4.2.1 Location. 17 4.2.2 Total area. 17 4.2.3 Population. 18 4.2.4 Administrative structure. 18 4.2.5 Agglomeration. 18

2

4.2.6 Industrial potential. 18 4.2.7 Service sector. 19 4.2.8 Communal service. 20 4.3 Transport. 20 4.3.1 Public transport. 20 4.3.2 Inter- transport. 20 4.3.3 Railway transport. 21 4.3.4 River transport. 21 4.3.5 Air connection. 21 4.4 Ecological situation. 21 4.5 Industrial park location. 21 5. Term of the industrial park “CENTRAL” creation. 24 6. Requirements for the industrial park members. 24 6.1 Organization of the industrial park "CENTRAL" 24 functioning. 6.2 . Requirements for the industrial park members. 25 7. Planned consumption of energy and communal services by 26 the industrial park members. 8. Plan of the industrial park development. 28 8.1. Infrastructure development of the industrial park. 28 8.2. Constraction of the industrial park. 30 8.3. Service delivery. 30 9. Needed resources for creation and functioning of the industrial 32 park, expected sources of attraction. 10. Organizational model of the industrial park functioning. 36 11. Expected results of the industrial park functioning. 37 11.1 General tendencies. 37 11.2 Expected results of the industrial park functioning. 37 11.3 Expected advantages of the industrial park ‘CENTRAL’ 38 functioning after its construction. 11.4. Investment project estimation. 40

3

THE INDUSTRIAL PARK CONCEPT 1. The industrial park “CENTRAL”

1.1 Introduction The concept of creation and functioning of the industrial park" Central "in Kremenchuk, hereinafter referred to as Concept, reflects the basic legal, organizational and economic conditions of creation and functioning of the industrial park in Kremenchuk, Poltava oblast. The concept was developed in accordance with current legislation and regulations of Ukraine. The creation of the industrial park “CENTRAL” is supported by the Poltava Regional State Administration. The Ukraine President Mandate from March 22, 2012 “On Acceleration of National Projects Implementation, Definition of New Priorities and Extension of National Projects taking into account actual problems relating to restoration of economic growth and modernization of the national economy” is one of the strategic documents, which influenced the development of the Concept. Legislation about the industrial park concept: - the Constitution of Ukraine; - the Land Code of Ukraine; - the Tax Code of Ukraine; - the Commercial Code of Ukraine; - the Law of Ukraine “On Industrial Parks”; - the Law of Ukraine “On Regulation of Town-Planning Activities”. The relevant statistics published on the website of the State Statistics Service of Ukraine were used to conduct analytical research and calculations. Development of the concept of the industrial park "Central" in Kremenchuk was done by consulting support of Poltava Regional Center for Investment and Development and Regional expert consulting center "Poltavakonsaltynh" Ltd.

4

1.2 Industrial park “CENTRAL” 1.2.1 Poltava oblast in the East Europe

1.2.2 Poltava oblast as a part of Ukraine Poltava oblast is an administrative unit of Ukraine with the center in Poltava. It was founded in September 22, 1937. It is located in the middle part of the left-bank Ukraine. Most of the area lies within the lowland and Poltava flat. Total Area - 28,748 km ² (4, 76% of Ukraine territory), population - 1,466,786 people (February 1, 2013, 3.22% of the population of Ukraine). The region has 25 districts and 15 cities, five of which - Kremenchuk and Komsomolsk, , Myrgorod and Poltava - regional subordination. The most important industries of the oblast are agriculture and industry (including food, light industry, machinery, etc.)..

5

Poltava oblast is located in the central part of Ukraine. Poltava oblast borders oblast and oblast in the north, oblast in the east, and in the south, oblast and oblast in the west.

1.2.3 Kremenchuk district as a part of Poltava oblast.

6

Kremenchuk district is an administrative unit of Poltava oblast with center in Kremenchuk. Kremenchuk district is located in the southwestern part of the oblast, mainly on the left bank and only a small part on the right bank. It was formed on May 17, 1939. The population of the district is 41.9 thousand people. Total area is 1.02 thousand km ². Kremenchuk district borders Globyno, Kozelschyna, districts of Poltava oblast and Onufrievka, Svetlovodsk districts of Kirovohrad oblast.

1.2.4 Kremenchuk on the map of Ukraine Kremenchuk is a city of regional subordinance in Poltava oblast and an administrative center of Kremenchuk district. City population was 225,9thousand people as of February 1, 2013. The city is on 28 place of State Rating of Ukraine. The city is divided into two districts: Avtozavodskiy (Left Bank) and Kriukov (mostly Right-Bank and Left-Bank part of the city). Kremenchuk is located in the temperate continental climate in the Dnipro lowland and middle stream of the Dnipro River, on its left and right banks in . The city is situated on the territory of 9600 hectares. The city is located in the central part of the Left-Bank Ukraine, which significantly influences the development of its economy, rail, road and water connections, social and economic relations. The favorable location of Kremenchuk and the level of its economic influence on the economy of the whole region became the main factors of making decision on creation of the industrial park within the boundaries of the city. The main aim of industrial park creation is to attract not only investment but also modern technology, world experience of industrial production organization. That’s why industrial park should become the center of industrial standards, engineering science and the leader of industrial production in the region. Kremenchuk on the map of Ukraine

7

2. The initiator of the industrial park creation

2.1 General Provisions According to Article 1 Law of Ukraine “On Industrial Parks”: «3) industrial (production) park (hereinafter referred to as‘industrialpark’) means a territory identified by the initiator of the industrial park creation according to the town- planning documents and equipped with the appropriate infrastructure where the participants of the industrial park may perform their economic activities in the sphere of industrial production, research activities, activities in the sphere of information and telecommunication on the conditions specified by the laws of Ukraine and the agreement on economic activities within the boundaries of the industrial park; 4) initiator of the industrial park creation (hereinafter referred to as ‘initiator’) means the public authorities, the local government bodies, which in compliance with the Constitution of Ukraine shall enjoy the rights of the land owner on behalf of the Ukrainian people and which according to the law shall be vested with the authority to dispose of land, as well as a legal or a physical person - the owner or the lease holder of the land parcel, which may be used and proposed by him for creation of the industrial park;» After analyzing feasibility of the industrial park creation within the boundaries of Kremenchuk and its influence on the economy of the district and the region, Kremenchuk City Council came out with an initiative to create the industrial park "CENTRAL". According to Article 5 Law of Ukraine “On Industrial Parks”: «1. The state power bodies, the local government authorities, legal or physical persons who have the right for creation of the industrial parks in the state and communal lands according to this Law may be the initiators of creation of the industrial parks». Kremenchuk City Council as initiator of the industrial park “CENTRAL” creation exercise the land title on behalf of the Ukrainian nation and has the right to administer the land in accordance with the Law. Kremenchuk City Council allocated land for the industrial park creation in the northern industrial center of Kremenchuk with total area of 168.55 ha. and cadastral number 5310436100:01:003:0000.

8

2.2 Kremenchuk City Council

Kremenchuk City Council of Poltava oblast is an initiator of the industrial park "CENTRAL" creation. Symbols of Kremenchuk - city arms and flag.

State power body OLEH BABAYEV +380 (0536) 73-00-34, 73-00-44, Telephone: fax: 73-00-54 e-mail [email protected] First Vice Mayor ANDRIY POHRIBNYY Telephone: +380 ( 0536) 74-30-20 e-mail [email protected] www www.kremen.gov.ua address : Victory square 2, Kremenchuk, Poltava oblast, Ukraine, 39600

"Program on investment and economic development of Kremenchuk for 2012- 2015" was adopted by Kremenchuk City Council on session from June 26, 2012. Public Enterprise “Kremenchuk Center for International Relations and Economic Development “Kremenchuk Invest” was created for implementation of program objectives. This enterprise is responsible for attracting investment in the city with the aim of new enterprises creation and promotion of Kremenchuk. On June 26, 2013 XXXIII session of Kremenchuk City Council adopted a decision "On creation of the industrial park " CENTRAL " in Kremenchuk."

9

3. The aim and task of creation and functioning of the industrial park.

3.1 The aim of the industrial park creation. The industrial park is creating with the aim of: - investment attraction; - world experience of industrial production introduction; - modern technologies implementation; - creation of the center of industrial standards, engineering science and the leader of industrial production in the region. Industrial Park "Central" is to create by means of formation of a single equipped territory to accommodate new facilities in industrial production, innovation, logistics aimed at providing economic development, increase its competitiveness, and stimulate investment and innovation, improving social standards for residents.

3.2 The task of the industrial park creation. The industrial park is created with the aim to solve following tasks: 1. Improving Kremenchuk image and its promotion in the country and abroad. 2. Improving the investment climate in the city and in the region. 3. Strengthening the investor confidence in the state of Ukraine. 4. Improving the business activity in the business environment. 5. Supporting the development of small and medium business. 6. Improving the social standards for city population: - increasing the budget receipt on all levels; - creation of new jobs; - payment of the rent for land usage within the boundaries of the industrial park; - creation of ecologically clean industrial enterprises; - increasing the salary average level in the city; - activation of the inter-industries cooperation; - upgrading the workers professional skills; - decreasing the education and labor migration; - improvement of the demographic situation by stimulating the labor migration in the city; - employment of the energy suppliers and other service providers, which will guarantee the functioning of the industrial park; 7. Implementation of modern innovation solutions in production industries. 8. Creation of favorable condition to develop small and medium business. 9. Implementation of energy-savings technologies. 10. Increase of economic activities volume.

10

3.3 The functional purpose of the industrial park.

3.3.1 Priority economic industries for development within the boundaries of the industrial park. The priority economic industries for development within the boundaries of the industrial park were determined after economic analysis: - mechanic engineering; - logistics; - IT-technologies and electronics; - small and medium business; - alternative energy and engineering.

Scheme of the territory allocation within the boundaries of the industrial park "CENTRAL" in Kremenchuk. Industrial Park area is 168.55 ha. The industrial park is divided into five sectors:

11

3.3.1.1 Sector 1 – «Hi-Tech» (mechanic engineering). Sector 1 is to provide the instrument making industry, engineering and other areas of production, created through the implementation of new technologies. The approximate size of the expected investment is 150 million dollars. Estimated number of created jobs is 1250 people. Total area is 50,05ha.

3.3.1.2 Sector 2 – «Logistics» (logistics). Sector 2 is to provide the warehousing and packing buildings, automobile companies and customs warehouses. The approximate size of the expected investment is 60 million dollars. Estimated number of created jobs is 510 people. Total area is 19,76 ha.

3.3.1.3 Sector 3 – «Techno Polis»(IT-technologies and electronics). Sector 3 is to provide the platform for development of advanced information and telecommunication technologies, nanotechnology, electronics manufacturing. The approximate size of the expected investment is 82 million dollars. Estimated number of created jobs is680people. Total area is 27,35 ha.

3.3.1.4 Sector 4 – «EcoLife»(reserve sector). Total area is 26,78 ha.

3.3.1.5 Sector 5 – «Energetics» (alternative energy and engineering). Sector 5 is to provide the companies working in the field of energy efficiency and energy saving technologies, production tool, equipment and agricultural machinery manufacture. The approximate size of the expected investment is 130 million dollars. Estimated number of created jobs is 1115 people. Total area is 44,61 ha.

3.3.2 Business-city. Business-city is to created with the aim of providing services for all industrial park members, clients. It will be a complex which includes offices with open planning, conference halls, press centers, negotiation rooms, data centers, banking centers, cafes, polygraphic center, business hotels, outdoor and underground parking. Total area is 20,12 ha.

12

The current concept can be changed during the design estimates development of the industrial park if there are factors that contribute to changes in forecasted zoning of its territory.

3.4 Organization of the industrial park "CENTRAL" functioning.

3.4.1 The procedure for the industrial park creation: - approval of the concept by the initiator of the industrial park creation; - selection of the land for the industrial park location; - reception of the copy of the State Land Cadaster statement on the land; - creation of the working group to conduct the tender for the selection of the management company; - decision making on the industrial park "CENTRAL" creation; - conducting the tender on selection of the management company; - submission to the authorized state body of copy of the decision on industrial park creation and industrial park concept; - decision on inclusion of the industrial park to the register of industrial parks; - conclusion of the contract with management company; - transfer the land parcels into lease to the management company; - development of the estimate documentation on necessary infrastructure creation to provide the industrial park with energy products and transportation routes; - creation of necessary infrastructure to provide the industrial park with energy products and transportation routes; - conducting the advertising company through media to inform all target groups of potential industrial park members, - holding the roundtable discussions, seminars and other events to assist attracting investment in the development of the park; - transfer the land parcels into sublease from management company to industrial park members for creation and functioning of their enterprises; - provision all members of the industrial park with services.

13

3.4.2 Sources of funding for creation and functioning of the industrial park

Sum, № Expenses Source of funding thousand/ UAH 1. Preparation: Transfer of agricultural lands into the lands of industry, transport, communications, Municipal budget 46,56 energy, defense and other purposes for the industrial park creation. Training of specialists on attracting Municipal budget 175,65 investment in the city economy. Distribution of the industrial park "CENTRAL" concept among potential Municipal budget 33,56 investors and management companies. Preparation of technical and juridical Municipal budget 84,69 documentation. Conducting of target business trip, focus Municipal budget 125,26 groups and seminars. Designing of presentations, informational Municipal budget 207 materials and stands. Presentation of investment attractiveness and Kremenchuk industrial capacity abroad Municipal budget 244,17 and in international forums in Ukraine. Registration of the industrial park Municipal budget 8 “CENTRAL” trademark. Expenses on the reception of copy of the Municipal budget 0,2 State Land Cadaster statement for the land. Expenses on preparation of technical Municipal budget 80 documentation. Expenses on land parcel analysis. Municipal budget 10

The selection and work with the 2. management company: Expenses on tender documentation creation and conducting the tender for selection of Municipal budget * the management company. Preparation of contracts with the management company about land lease, Municipal budget * administration and usage of the industrial park “CENTRAL” trade mark. Loss compensation of transfer of Municipal budget *

14

agricultural lands into the lands of industry, transport, communications, Management energy, defense and other purposes for the company industrial park creation. Development of estimate documentation on necessary infrastructure creation to Municipal budget * provide the industrial park with energy products and transportation routes Construction and development of the 3. industrial park, cooperation between management company and investors: Municipal budget State Budget of Сreation of infrastructure to provide Ukraine * industrial park with energy and transport. Management company Management Lease of the industrial park land parcel. * company Promotion of the industrial park with the Municipal budget, aim of attracting investment in the Management * development of the park. company Preparation of contracts with members of Management * the industrial park. company Transfer the land into sublease to the Management * industrial park members. company Development of general layout of building Management * of the industrial park. company Management company Development of the territory. * Industrial park members Provision of services by management Industrial park * company. members Municipal budget State Budget of Ukraine Other costs. Management * company Industrial park members

15

* The volume of financing will be determined in the business plan prepared by the management company.

16

4. Industrial and economic potential of Kremenchuk. Location and land parcels size.

4.1 Poltava oblast. Poltava oblast is one of the regions of Ukraine with an average level of industrial production development. Most industries were created in 50-60s of the twentieth century: • oil production; • iron-ore; • steel industry; • oil refinery; • automobile; • engineering tools; • electrical engineering; • production of technological equipment for chemical, food and light industry.

4.2 Industrial and economic potential of Kremenchuk. Kremenchuk is a city of regional subordination in the Poltava oblast of Ukraine, and administrative center of the Kremenchuk district.

4.2.1 Location. Kremenchuk is located in the temperate continental climate in the Dnipro lowland and the middle stream of the Dnipro River, on its left and right banks in central Ukraine.

Distance from Kremenchuk to (highways):

Warsaw~ 1084 км St-Petersburg ~ 1481 км Sumy~ 289 км Kyiv ~ 302 км Moscow ~ 985 км Kharkiv ~ 263 км Cherkasy ~ 178 км Minsk~ 822 км Poltava ~ 116 км

Paris ~ 2610 км ~ 558 км Vienna ~ 1625 км Volgograd ~ 1023 км ~ 842 км Astana~ 3396 км

Kirovohrad ~ 131 км ~ 337 км Dnipropetrovsk ~ 163 км Odesa~ 457 км ~ 542 км Zaporizhia ~ 249 км Chisinau~ 467 км Istambul~980 км ~ 415 км

17

4.2.2 Total area. The city is situated on the territory of 9600 hectares. 4.2.3 Population. City population was 225,9 thousand people as of February 1, 2013. The city is on 28 place of the State Rating of Ukraine.

Graph of population change ( thousands\people)

4.2.4 Administrative structure. The city is divided into two districts: Avtozavodskyi (Left Bank) and Kriukov (mostly Right-Bank and Left-Bank part of the city). 4.2.5 Agglomeration. Kremenchuk is a center with half a million people agglomeration. Many people from the surrounding , towns and cities work and study in Kremenchuk. Kremenchuk has close connection with neighboring cities – Komsomolsk and Svetlovodsk. They were built in 1961 for workers of Poltava Mining and Processing Plant(GOK) and Kremenchuk Hydroelectricity. The villages of Kremenchuk agglomeration are - VilnaTereshkivka; - Kryvushi; - Mala Kohnivka; - Pischane; - Sadky; - Checheleve; - Chervona .

18

4.2.6.Industrial potential Kremenchuk is a big industrial center of Poltava. There are 86 big industrial enterprises, 58 building companies and about 14,000 businesses companies in Kremenchuk.

4.2.7 Service sector. Kremenchuk provides more than 500 types of consumer services with tendency to expand them. There are about 2400 businesses companies of trade and domestic purposes: - Shops (986 stores), including: - grocery stores (365); - non-food stores (585); - mixed assortment (360); - retail stores (84). There are national and local stores of different activity profile in the city: universal hypermarkets "Velmart", "METRO Cash and Karry" "Fozzy," "Furshet" and "Amstore"; building supermarket "NovayLinia", shopping centers ("Mega", "Galaktika "" Proletarskiy"etc). Aslo there are national and local networks: food network("ATB-Market", "EKO- market", "Sudar", "Optovychok", "Silpo», «Billa»), furniture network ("World of Furniture"), electronics stores ("Foxtrot", "Eldorado", "Brain", "Technopolis", "Allo»”, «Comfy»). There are many local shops and networks: - Restaurant business - 320 institutions. - Network of restaurant business of the city has 12,800 seats. -Markets. There are 14 markets without special profile. Pridneprovskiy, Novoivanivskyi, Central and Auto Markets are the most popular. - There are 450 service companies. - Cinema: "KinoPalace" of "Zebra", "Naftokhimik" of "Naftokhimik"palace." There are several night clubs: "Jose", "Zebra", "Orekh", "Vanil" (Shopping mall "Europe"). - Hotels: four-star hotel "Europe" and three-star "Dnipro stars", "Kremin", "Ontario", "Pantagruel", "Grace". - Banks: - International Bank (OTP Bank); - National (PryvatBank, IndustrialBank, Sberbank); - Local (AvtoKrazBank, PoltavaBank). Health Network. Kremenchuk consists of 14 hospitals, local government bodies and 12 regional establishments. Also the medical services are offered by many private clinics.

19

4.2.8 Communal service. Kremenchuk housing and communal services has 40 companies and employs 2,300 people. The leaders: - Public Enterprise “Kremenchuk transport enterprise-1628” - PE “ Misksvitlo” - PE “Kremenchuk contractor specialized road repair and construction management” - PE “Kremenchuk trolleybus management” - PE “ Kremenchukvodokanal” - PE “ Teploenergo” - PE “Special funeral services” - Management company of LLC "Zhytlorembudservis"; - Management company of LLC "Dobrobyt." These enterprises provide greening, lighting the city, its sanitation and capital and current repairs of roads, accomplishment of territories, repair and routine maintenance of housing, etc. Housing stock, which belong to the local community of the city, is 65584 m ². 57670 (90%) apartments are privatized. 1239 houses are owned by the city. There are 244 houses up to 25 years after construction, 712 buildings aged from 25 to 50 years, 175 buildings aged from 50 to 75 years, 67 buildings aged over 75 and 41 inthepoor house condition.

4.3 Transport.

4.3.1 Public transport. The main public transport are bus service (АО АТП-15307), trolleybus service (PE «Trolleybus management») and 13 private carriers enterprises. Trolleybus routes length is 54 km. Trolley park consists of 40 old and 7 new machines. The ticket price is 1.50 UAH and free travel for pensioners as of July 1, 2013. Bus service has more than 34 routes. The total length of the bus route network of the city is 311.7 km. There are about 28 taxi services in Kremenchuk.

4.3.2 Inter-cities transport. The city has a bus station, which is the center of inter-city bus transportation. There are also inter state routes (eg, Kharkiv, Chisinau). Buses and taxis are also sent from the train station to Kyiv, Kharkiv, Dnipropetrovsk, Poltava, , Vlasovka and Komsomolsk Central Market.

20

4.3.3 Railway transport. There is a railway station. Also there are Kriukov railway station and several others railway stations. Currently there is a railway connection to Kyiv, Kharkiv, Dnipropetrovsk, Simferopol, Minsk, Moscow, St. Petersburg. 4.3.4 River transport. There are river port and passenger terminal in the city. 4.3.5 Air connection. Nearest international airports are: • Boryspil - 254 km. • Kyiv - 293 km. • Dnepropetrovsk - 166 km. • Kharkiv - 250 km. • Kremenchuk - the helicopter platform of Kremenchuk Flight College of National Aviation University, which can take different forms and helicopters. It is situated just 500 meters from the industrial park.

4.4 Ecological situation. Kremenchuk industry is a center of urbanization of the region. It has a significant impact on the environment pollution. There are about 100 companies registered in public health department as harmful for the environment. PJSC “Ukrtatnafta”, PJSC “Carbon Black Plant”, Kremenchuk TEC, PJSC "Kremenchug Wheel Plant" , PJSC “AvtoKrAZ”, PJSC “Kremenchuk Steel Works”, PJSC “Kremenchuk road-building machinery plant” PJSC “Kriukov Car Building Works” obtain 95% of all polluting emissions. Kremenchuk air pollution level is the largest among the city of Poltava region (97% of all industrial and domestic waste).

4.5 Industrial park location. Kremenchuk City Council, as the initiator of the industrial park "CENTRAL" creation, gave the land parcel for its location with a total area of 168.55 hectares, cadastral number 5310436100:01:003:0003 in northern industrial center of the city.

21

------Railway Highways Water connection

According to extract from the State Land Registry on the land parcel:

Extract number НВ-5300404842013 Cadastral number 5310436100:01:003:0003 Poltava oblast, Kremenchuk, Northern Location industrial hub Specialization Enterprises of other industry 22

Land parcels of industry, transport, Land category communications, energy, defense and other purposes Industrial park “CENTRAL” creation Type of land use Total area 168,55 hа Information about limitation of land use No record Additional information: Building development Territory free from construction Form of land Polygon Relief of land Flat Fence without fence Normative land charge during the 79,6 million/UAH construction Market price of the land 337,1 million/UAH Rent payment for land use during 2,4 million/UAH construction Cadastral plan of the land

Description of boundaries of the land: From А to Б – Kremenchuk City Council; From Б to В – Subsidiary Enterprise “Ukrtransnaftaproduct”; From В to Г – Kremenchuk City Council; From Г to Д – Subsidiary Enterprise “Ukrtransnaftaproduct”; From Д to Е – Kremenchuk City Council; From Е to Є – Subsidiary Enterprise «Southern Railway»; From Є to Ж – Kremenchuk City Council;

23

5. Period of the industrial park “CENTRAL” creation. Extract to art. 9 of the Law of Ukraine "On Industrial Parks", "term of the land use within the industrial park must be at least 30 years from the date of making decision on industrial park creation." Industrial Park "CENTRAL" in Kremenchuk is to establish for a period of 50 years according to Kremenchuk City Council Decision.

6. Requirements for the industrial park members. 6.1 Organization of the industrial park "CENTRAL" functioning. Kremenchug City Council, as the initiator of the industrial park “CENTRAL” creation, is conducting the tender on selection of the management company to ensure the industrial park functioning. According to the Law of Ukraine “On Industrial Parks”: “management company of the industrial park (hereinafter referred to as ‘management company’) means a legal person irrespective of its organizational form created according to the laws of Ukraine and selected in compliance with the Law of Ukraine "On Іndustrial Parks", with which the initiator concluded an agreement on creation and functioning of the industrial park” The main task of the management company is filling the industrial park with members and providing comfort for their economic activity in the industrial park. Basic requirements for the management company: 1. Management company must be a legal entity, irrespective of its legal form created according to the laws of Ukraine and selected according to the Law of Ukraine "On industrial parks." 2. Implementing the business plan approved by the industrial park initiator and developed by the management company. 3. Implementing the provisions set out in the Industrial Park concept. 4. Concluding the agreement with Kremenchuk City Council on a lease of land with cadastre number 5310436100:01:003:0003. 5. Paying rent for land use with cadastre number 5310436100:01:003:0003. 6. Ensuring the industrial park filling by the members in accordance with the agreed scheme of industrial park building development. 7. Transferring the land of the industrial park into sublease. 8. Concluding the contracts for the provision of services to members of the industrial park. 9. Providing the quota for the workers employment of Kremenchuk region is not less 89% of the total number of involved employees within the boundaries of the industrial park. 10. Giving the preference to materials produced in the territory of Ukraine. 11. Giving the preference to Ukrainian commercial entities to provide services to the industrial park members. 12. Rendering the report to the industrial park initiator.

24

6.2 Requirements to the industrial park members. 1. The industrial park members must be a legal entity irrespective of its legal form, registered within the territory of the administrative-territorial unit of Ukraine where the industrial park is situated. 2. The enterprises of the industrial park members must be profitable. 3. The industrial park members must create new job places, i.e. at least 20 job places per hectare of the general square and hire at least 89 % of workers, who live in Kremenchuk and Kremenchuk district of Poltava oblast. 4. The industrial park members must carry on business within the frameworks of the current legislation of Ukraine. 5. The industrial park members must have a program of their development and carrying on business in the park territory at least for 5 years. 6. They must timely pay up a lease for the land use within the territory of the industrial park.

25

7. Planned consumption of energy and communal services by the industrial park members. According to information, provided by potential energy source and communal services suppliers, there are no restrictions for the industrial park members in the amount and terms of supplying their services. The management company receives authorized documents, established by the Law, and carries out all necessary building and installation work by order of the industrial park members to get these services. Planned indexes estimation of energy materials and communal services usage necessary for industrial park functioning*. № Energy materials and communal services Expected indexes*

9000 thousand 1. Natural gas supply m3/year 2. Electricity supply 6 MW 3. Water supply 250 thousand m3/year 4. Sewage 250 thousand m3/year

Tacking: * Planned indexes estimation was held on the basis of energy materials actual expenses by the Kremenchuk enterprises. The stated indexes will be corrected at the stage of the industrial park project development.

26

Planned indexes estimation of energy materials and communal services usage necessary for industrial park functioning* Energy materials and communal services Natural gas, Electrical Water supply, Sewage, Sector thousands energy, thousands Thousands m3/year MW m3/year m3/year Sector 1 – «Hi-Tech» (machic engineering). 3030 2,5 84,16 84,16 Sector 2 – «Logistics» (logistics). 1412 0,5 39,22 39,22 Sector 3 - «TechnoPolis» 1817 1 50,49 50,49 (ІТ technologies and electronics). Sector 4 - «EcoLife» - - - - (reserve sector). Sector 5-«Еnergetics» (alternative energetics and 2741 2 76,13 76,13 machinery). Total amount 9000 6 250 250 Tacking: * Determining the required level of energy materials and communal services usage by the industrial park members is possible only in the designing process of enterprises and approval of the industrial park building master plan.

27

8. Plan of the industrial park development Plan of the industrial park development includes: 1. Infrastructure development of the industrial park. 2. Industrial park construction. 3. Providing industrial park members with services.

8.1 Infrastructure development of the industrial park. According to the Law of Ukraine “On Industrial Parks”: infrastructure development of the industrial park means implementation of a set of measures and services on preparation of the land plots, designing, construction, reconstruction, refurbishment and arrangement of the objects of engineering and transport infrastructure and other objects by the management company and/or the creation initiator according to the conditions of the Agreement on creation and functioning of the industrial parks and the Law of Ukraine On Regulation of Town-Planning Activities with the aim of creating appropriate conditions for performing economic activities; The land parcel for the creation and functioning of the industrial park “CENTRAL” is situated in the northern industrial hub. There are lands of north industrial hub enterprises, Kahamlytska station and railway track Kriukiv- Kremenchuk on the borders with the park territory. Surrounding engineering infrastructure: Highways: Ernst Telman st. is lying from the west side of the land area with a distance of 100 meters. Its widening is worked on Kremenchuk general schedule of the city. The industrial park territory is limited by urban area: Svishtovska st., 50- richchia Zhovtnia and Haluzevyi Side Street. A drop-off to the industrial park territory can be organized from different sides and now-existing drop-offs also can be used. Absolutely, creation of new highways or reconstruction of already existed must be held within the frameworks of agreed general plan of the city, fulfilling all requirements of the regulatory approval system of Ukraine. Railway service: Kremenchuk is a large industrial center the work of which is provided by the railway work. There are passenger railway station and freight station. The industrial park territory is situated for 2,3 km from the railway station (Kremenchuk station) and for a 200 m from Kahamlytska station. The railway usage in economic activity by the industrial park members is possible in two ways: - Combined – the freight delivery to the Kahamlytska or any other station and further automobile transportation; - Direct – the building of their own railway.

28

The procedures of railway usage are determined by the management company according to the industrial park members’ requirements. Inland waterway: Kremenchuk is situated on both banks of the Dnipro river – one of the main river transport arteries of the country. According to information of specialists, river and marine shipments are the most suitable due to their cost. There are river port and marina. The river port is situated on Flotska st., and marina is situated on Pershotravneva st. The usage of river transportations by the industrial park members is possible only in combined way. Air connection: There is no airport in Kremenchuk, but it is possible to get Kremenchuk using airports in Kyiv, Boryspil, Dnipropetrovs’k and Kharkiv, which are situated in short distance with Kremenchuk. There is a helicopter platform in Kremenchuk, which is situated on the territory of Kremenchuk Flight College of National Aviation University and also at a distance of 500 m from the industrial park. It is possible to receipt helicopters of different grades there. External utility lines: According to the “Principles of Kremenchuk development”, agreed on the session of Kremenchuk City Council from 28.12.2010, the territory of the industrial park relates to the zone of advanced, ecologically safe, industrial and producing objects of small and middle business, scientific and industrial objects, storage facilities and bases, communal facilities (according to town-planning reasons or some other town-planning documents). The area partly caught sanitary-protection zone of the industrial enterprises and also it got to the soundproof railway zone. The quarters of the area lying in connection net from the south-east and west sides (from the side of Telman st.). The available networks partly caught the borders of land property (from the side of Telman st.). According to information of potential energy suppliers, the distance to the utility networks, which can be connected to the industrial park network, is*:

29

Energy source Distance Tacking Heroes Stalingrad str., pipe network 405 m DN=400 mm Water supply Heroes Stalingrad str., pipe network 405 m DN=200 mm Heroes Stalingrad str., sewage net Sewage 405 m DN=300 mm Halusevyi side street, gas pipe line Natural gas 1000 m DN=200 mm Power supply 2900 m Halusevyi side street The net is lying inside the industrial Telecommunications park territory

* Tacking: The industrial park territory is situated at the industrial area, the place of which is defined by position of Kremenchuk combined heat and power station. Large industrial enterprises are situated in the territory of industrial hub. In the process of industrial hub territory building, utility lines were designed with the perspective of new enterprises production startup and already-existing enterprises development. The economic situation in the country influenced the production sphere development. The analysis of the current situation gives the reasons to think that amount of industrial enterprises production, which are placed in the territory of the industrial hub, decreased. It led to decreasing of energy supplies usage. That is why, during industrial park building, its members will be able to use available capacities of already-existing utility networks and also to create their own ones. The utility interface and the terms of their laying can be changed during the process of the general plan creation on the industrial park building. 8.2 The construction of the industrial park. The construction of the industrial park is one of the main tasks of the management company, which must agree the relevant plan with Kremenchuk City Council. Considering the city priorities of the production branches development, Kremenchuk City Council admits a phased building of the industrial park territory:

30

Expected investment Period of Stage amount, Industrial park sectors construction* million $ USD Stage №1 2013-2015 170,0 Sector 1 – «Hi-Tech» (machical engineering). Stage №2 2014-2016 80,0 Sector 2 – «Logistics» (logistics). Sector 3 – «TechnoPolis» Stage №3 2014-2017 102,0 (ІТ technologies and electronics). Sector 4 – «EcoLife» Stage №4 2015-2018 - (reserved sector). Sector р 5 – «Еnergetics» (alternative Stage №5 2014-2018 150,0 energetics and machinery). 502,0 TOTAL AMOUNT Tacking: * The period of the industrial park construction depends on next factors: - prompt financing and work performance on the industrial park territory outfitting; - executive management of the management company which must attract industrial park participants; - authorities and management company cooperation in consent documents execution; - domestic and foreign economic situation; - availability of the body which will accompany the industrial park participants. Terms of the park construction may be changed during its development on the basis of agreed issues of both parties.

8.3. Service Delivery.

Attracted by the management company, industrial park participants conclude contracts about land sublease and services, which are provided by the management company. The list of services and their conditions are set by the management company of the industrial park and members of the industrial park.

31

9. Needed resources for the creation and functioning of the industrial park and expected sources of their attraction.

Expenses, № The list of expenses Financing sources thousands UAH Preparatory period of industrial 1 Municipal budget 1015 park "CENTRAL" creation Development of design specifications and estimates of 2 infrastructure creation for Municipal budget 768* providing the industrial park with energy supply and transport Performance of work oriented at infrastructure creation for Municipal budget, State 3 25600 providing the industrial park with Budget of Ukraine energy supply and transport 4016000 4 Forecasted amount of investment Management company (502,0 million $ USD)

Tacking: * The analyses of information, given by specialists in the sphere of industrial facilities design, the amount of design specifications and estimates of industrial objects designing is 3% to a quota. The preliminary cost of works on provision of the necessary facilities of the industrial park can be 25.6 million. (3.2 million USD), i.e. the size of the design work and preparation of estimates can be 0.768 million UAH. Extract from Article 34 of the Law of Ukraine "On industrial parks": “State support of works on provision of the necessary facilities of the industrial park can be carried out by state and local budgets costs or by costs of any other authorized sources. The authorized state body, the Council of Ministers of the Autonomous Republic of , local state administrations and executive bodies of local councils in the manner provided by law, annually submit proposals to the State Budget of Ukraine project and to the draft decisions of relevant local budgets on financial support works on provision of the necessary facilities of the industrial park. On purpose of creation and functioning of the industrial parks the authority supports management companies and initiators of their creation, providing them 32

with non-interest loans and non-refundable target financing of works on provision of the necessary facilities of the industrial park. Management companies are business entities and they receive costs provided by The Law on the State Budget of Ukraine for the relevant year.

The cost works on provision of the necessary facilities of the industrial park provided through co-financing budgets of Kremenchug City Council, Poltava region budget and the State budget of Ukraine.

The cost of The cost of The total The sources of financing designing building, cost, № (thousand, (thousand, (thousand, The state The city Other Kinds of works budget budget sources UAH) UAH) UAH) (thousand (thousand (thousand /UAH) \UAH) /UAH) Connecting to a power line Cable line with total length …meters 1. Building of transformer 500 22770 23270 5800 1860 15610 substation Switchgear installation Internal supply line Receiving of capacities Connecting the water supply Laying the water supply line with total length …meters 2 230 450 680 170 50 460 Hydraulic unit building Partitioning device installation Internal water supply net Connecting to the sewage net Lying the sewage line with total length 3 200 550 750 190 60 500 …meters Sewage pump station building Partitioning device 33

installation Internal sewage net Connecting to the gas- supply net Lying the gas-supply net with total length …meters 4 150 750 900 230 70 600 Gas regulating points building Partitioning device installation Internal gas-supply net TOTAL SUM 1080 24520 25600 6390 2040 17170

Pro forma estimation: Exact figures will be given during design estimate documentation. Installation of The cost additional The total of one Approximate devices, cost, Kinds of works running length, meter substations, (thousand, meter, thousand UAH) UAH UAH Connecting to a 1200 2900 19290 22770 power line net Connecting the 1112 405 - 450 water supply net Connecting to the 1112 405 100 550 sewage net Connecting to the 500 1000 250 750 gas-supply net

34

The scheme of communications laying

Connecting to a power line net

Connecting to the gas-supply net

Connecting the water supply net

Connecting to the sewage net

Connecting to the telecommunications

35

10. The organizational model of the industrial park functioning: The initiator of the industrial park creation makes a decision on industrial park creation. The initiator conducts the tender on the management company selection. The management company works out the industrial park building development. The management company concludes contracts with the industrial park members. The management company is accountable to the industrial park initiator and his authorized representative. The decision to liquidate the industrial park is under jurisdiction of the initiator of its creation. The initiator of the industrial park creation independently determines procedure for interaction with the management company.

11. Expected results of the industrial park functioning. 36

11.1 General tendencies. - Implementation of the Kremenchuk City Council resolution on the industrial park creation. - Cash flow increasing to the budgets of all levels. - New job places creation for Kremenchuk citizens and Kremenchuk district. - Increasing the business activity level in Kremenchuk. - Support of the small and medium business development. - Increasing the Kremenchuk, Poltava oblast and Ukraine image. - Implementation of the state Programs on investment secure, business activity and social programs support. - Investments increasing, secured to the real sector of economy. - Attraction of the new technologies of goods and services production. - Development of the partnership between members of the industrial park and enterprises of the city, and also partnership with small and medium business representatives. - Increasing the social standards of life of Kremenchuk and its district citizens. - Activating the work of Kremenchuk northern industrial hub.

11.2 Expected results of the industrial park functioning.

№ Index Amount Tacking 1 Expected investments amount, total* 502,0 million $ USD 1.1 Sector 1 – «Hi-Tech» (machanic endineering). 170,0 million $ USD 1.2 Sector 2 – «Logistics» (logistics). 80,0 million $ USD 1.3 Sector 3 - «TechnoPolis» 102,0 million $ USD (ІТ technologies and electronics). 1.4 Sector 4 - «EcoLife» - (reserve sector). 1.5 Sector 5-«Еnergetics» (alternative energetics and 150,0 million $ USD machinery). 2 Creation of new job places, total amount 4225 workers 2.1 Sector №1 1417 workers 2.2 Sector №2 674 workers 2.3 Sector №3 852 workers 2.4 Sector №4 - 2.5 Sector №5 1282 workers

Tacking: * The amount of secured investments may be changed according to management company work on the industrial park building development. ** The number of job places may be changed due to producibility of enterprises, which will placed on the territory of the industrial park.

11.3 Expected advantages of the industrial park “CENTRAL” functioning after its building development. 37

Sum, № Expected advantages thousands, Tacking UAH 1 Local budget (rent for land use) 2400 2 Taxes and fees: * 40% social due of enterprise 2.1 64800 3,6% social tax of worker Municipal budget (income tax)** 15% on the part of worker’s 2.2 22300 salary 2.3 Budget of Ukraine (VAT-20%) *** 88400

2.4 Budget of Ukraine (income 10100 tax)**** 2.5 Multidisciplinary cooperation Will be clarified after impact conclusion of appropriate agreements Tacking: * The Pension Fund of Ukraine approved the average salary (income) per one insured person in the amount of 2,932 hryvnia 06 kopecks which will be used in determining the rate of wages for April 2013 setting the pension according to the Law of Ukraine on “Obligatory state pension insurance”. Investment, thousands, Salary, Investment, UAH per year thousands № Index Amount thousands, , UAH 3,6% 40% UAH per year 1 Creation of new job places 4225 1794,806 19942,291 2,932 21737,097 Sector 1 – «Hi-Tech» 1.1 1417 853,705 9485,606 2,932 10339,311 (machic engineering ). Sector 2 – «Logistics» 1.2 674 1079,164 11990,707 2,932 13069,871 (logistics). Sector 3 – «TechnoPolis» 1.3 (ІТ technologies and 852 1623,812 18042,355 2,932 19666,167 electronics). Sector 4 – «EcoLife» 1.4 - - - - - (reserved sector). Sector 5 – «Еnergetics» 1.5 (alternative energy and 1282 1794,806 19942,291 2,932 21737,097 machinery).

** Local budget

38

Salary, Tax income thousands, 15%, № Index Amount UAH per thousands month per year 2 Creation of new job places 4225 2,932 22297,860 Sector 1 – «Hi-Tech» (machic 2.1 1417 2,932 7478,359 engineering). 2.2 Sector 2 – «Logistics» (logistics). 674 2,932 3557,102 Sector 3 – «TechnoPolis» 2.3 852 2,932 4496,515 (ІТ technologies and electronics). Sector 4 – «EcoLife» 2.4 - - - (reserved sector). Sector 5 – «Еnergetics» 2.5 (alternative energy and 1282 2,932 6765,883 machinery). *** State budget VAT-20%. According to information provided by the site http://finance.ua/, the average amount of services, focused on saving the costs on the deposit accounts with a charged interest in the end of the deposit year (in terms of dollars USA) for legal bodies, is accounted by banks and is:

LEGAL ENTITIES DEPOSITS PER MONTH 1 month 3 6 months 12 months months UAH 13.50% 17.00% 18.00% 17.00% USD 3.50% 5.00% 6.00 7.00% EUR 3.50% 4.00% 5.00% 6.00%

Considering the fact that investment in production is more risky than cooperation with the banking sector, the rate of capital return should exceed the risk-free rate by the level of predicted risk. In Ukraine it is thought that the level of the risk-free rate is adequate according to the level of currency deposits of legal entities and the sum is paid within 12 months since the opening of the deposit. During calculations, the rate of return of the capital is set at 10% per annum. Taking into account that expected investment amount is to be 502 million $ USA, the rate of capital return will be 50,2 million $ USA. One of the requirements for participants of the industrial park is that their businesses must be profitable.

39

Considering the objecting reality, the level of the minimal profitability is set at 10% level. A minimum level of revenue from economic activities of the industrial park participants can be 441, 8 million UAH per year. As the practice shows, manufacturing companies choose general taxation system, i.e. VAT. In this case, the level of 20% VAT can reach 88.4 million UAH per year.

**** Income tax The minimum income is set at the level of the minimal profitability of the enterprise, which is 10 %, i.e. 40, 2 million UAH per year. The income tax is 25 %, i.e. 10, 1 million UAH per year.

11.4. Invest project estimation The investment project estimation on creation and functioning of the industrial park will be held on the basis of agreed business plan of the management company, which will win the tender on management company selection of the industrial park “CENTRAL” in Kremenchuk.

40