“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre () Pvt. Ltd.

Application for Amendment in Environmental

Clearance

Of “Hotel Complex & Convention Centre”

At Asset No. 13, Hospitality District, DIAL IGI Airport, Delhi

BEING DEVELOPED BY: M/s Aerocity Hotel & Global Centre(Delhi) Private Limited Asset No. 13, Hospitality District, DIAL IGI Airport, Delhi

PREPARED BY: Environmental Consultant M/s PERFACT ENVIRO SOLUTIONS PVT. LTD. (NABET Registered wide list of accredited consultants organizations/ Rev 43/ 11th July, 2016 at S.No-88) NN Mall, Sector-3, Rohini, New-Delhi-85 Phone: 011-47528467; 011-47021086 Fax: - 011-47528434

“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

FORM 1

I. Basic Information

S.No. Item Details 1. Name of the project/s Hotel Complex & Convention Centre 2. S. No. in the schedule 8 (b) Proposed capacity/ area/length/ Total plot area – 31163.13 Sq m tonnage to be handled/ command Builtup Area- 212732.72 3. area/ lease area/ number of wells to be drilled Amendment in Environmental Clearance The project has already been granted 4. New/ Expansion/ Modernization Environmental Clearance vide F.No. 92/DPCC/SEIAA-SEAC/10/1444-1448 dated 11-11-2010 Plot Area (as per EC granted) – 31163.13 sq m 5. Existing Capacity/ Area etc. Built-up Area (as per EC granted) –212732.72 sqm 6. Category of Project i.e. ‘A’ or ‘B’ ‘B’ Does it attract the general 7. Not Applicable condition? If yes, please specify. Does it attract the specific 8. Not Applicable condition? If yes, please specify. Asset No 13, Hospitality District, DIAL IGI Airport, Location Delhi Plot/ Survey/ Khasra No. Asset No 13 9. Village - Tehsil - District Hospitality State Delhi Railway Station 14.08 Km NE Palam Railway Station 4.83 Km NW Nearest railway station/ airport IGI Airport Metro Station 3.46 Km NW 10. along with distance in kms. Indira Gandhi International Airport 0.32 Km SW 9.22 Km NE Nearest Town, city, District 11. Headquarters along with distance Project Site is in Delhi. in kms. Village Panchayats, Zilla Parishad, 12. Municipal Corporation of Delhi Municipal Corporation, Local body “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

(complete postal addresses with telephone nos. to be given) M/s Aerocity hotel and global Centre (Delhi) Pvt. 13. Name of the applicant Ltd.

Asset No 13, Hospitality District, DIAL IGI Airport, 14. Registered Address Delhi

Asset No 13, Hospitality District, DIAL IGI Airport, 15. Address for correspondence: Delhi

Name Dimple Mahna Designation (Owner/Partner/CEO) AVP ( Regulatory ) A-75;Top Floor; Sector -8 A ; Dwarka ;New Delhi- Address 110075

Pin Code 110075

E-mail [email protected] Telephone No. 09873779639 Fax no. Details of Alternative Sites examined, if any. Location of these No alternative site has been examined. It is 16. sites should be shown on a amendment in Environmental clearance of project. toposheet. 17. Interlinked Projects No it is not an interlinked project Whether separate application of 18. interlinked project has been Not Applicable submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. 21. (a) The Forest (Conservation) Act, Not Applicable 1980? (b) The Wildlife (Protection) Act, Not Applicable 1972? “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

(c) The C.R.Z. Notification, 1991? Not Applicable Whether there is any Government 22. Order/ Policy relevant/ relating to Not Applicable the site?

23. Forest land involved (hectares) No

Whether there is any litigation pending against the project and/ or land in which the project is propose to be set up? No (a) Name of the Court Not applicable 24. (b) Case No. Not applicable (c) Orders/ directions of the Not applicable Court, if any and its relevance with the proposed project.

II. Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No. Information/Checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible) with source of information data 1.1 Permanent or temporary No The Project has already been granted change in land use, land cover environmental clearance vide F.No. or topography including 92/DPCC/SEIAA-SEAC/10/1444-1448 increase in intensity of land use dated 11-11-2010. (with respect to local land use The Excavation has been started for zone plan) one out of three zones on the vacant land and proposed proposal is for amendment in Environmental clearance. Hence no Change on land use has been done. Earlier the vacant land use was changed to Hotel building. 1.2 Clearance of existing land, No The project is for amendment in vegetation and buildings? environmental clearance for which construction has already started so no need “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

of clearance of existing land vegetation and buildings

1.3 Creation of new land uses? No No creation of new land uses. It is amendment in Environmental Clearance of the same project. 1.4 Pre-construction investigations Yes Pre-construction Geo-technical investigation e.g. bore houses, soil testing? has been carried out. 1.5 Construction works? Yes As per Building Sanction Plan.

1.6 Demolition works? No No demolition is required. 1.7 Temporary sites used for No Workers during construction phase were construction works or housing of hired from nearby areas and same shall be construction workers? done during construction after getting amendment in Environmental Clearance and hence there no housing provisions made. Only temporary shelters will be provided. 1.8 Above ground buildings, Yes Above ground, the building shall be elevated structures or earthworks up to maximum height of 15 m and including linear structures, cut excavation is being required for construction and fill or excavations of foundation and basement of 6 level whose quantity of soil excavated will be approx. 567000 cubic metre. 1.9 Underground works including No Not Applicable. mining or tunnelling? 1.10 Reclamation works? No No reclamation work required. 1.11 Dredging? No Not applicable 1.12 Offshore structures? No Not applicable 1.13 Production and manufacturing No It is a construction project therefore no processes? production or manufacturing processes shall be carried out. 1.14 Facilities for storage of goods or Yes During Construction Phase: materials?  Separate raw material yard will be made

within the project site.  Cement is being separately stored under cover in bales.  Sand is being stacked nearby under tarpaulin cover. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

 Bricks and steel were laid in open, same shall be done during proposed construction.

During Operation Phase: As the project is a Hotel complex and Convention Centre, the raw material storage will be done within the project site. 1.15 Facilities for treatment or Yes During Construction phase: disposal of solid waste or liquid For further construction, Total 150 labourers effluents? shall be working during the construction phase and hence the solid waste generation will be 23 kg/day which disposed off at municipal solid waste site.

Excavated soil will be used for levelling and back filling. Top soil will be preserved and shall be reused for landscaping to the extent possible. Total 7 KLD of waste water shall be generated which will discharge to septic tank via soak pit.

During Operation Phase: Approx. 3105 Kg/day of solid waste shall be generated from the complex. The total waste water generated from Hotel complex and convention centre shall be 258 KLD which will be treated in STP of 310 KLD. Details of Water Management & Solid Waste Management are given in Environmental Report. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

1.16 Facilities for long term housing No During Construction phase: of operational workers? The workers during construction phase were hired from nearby areas and hence no provision of long term housing had been made. Only temporary shelters were provided. For further construction same shall be followed. During Operation Phase: As this is a Hotel complex and Convention Centre, staff will be needed in the hotel shops, offices and restaurant. Other staff like maintenance staff will be from the nearby areas. Separate housing may not be provided. 1.17 New road, rail or sea traffic No No new road, rail or sea traffic is proposed. during construction or Existing transportation facilities will be used operation? during construction or operation phase.

1.18 New road, rail, air, waterborne No No new road, rail, or sea traffic is proposed. or other transport infrastructure The transportation measures already including new or altered routes existing near site are as follows: and stations, ports, airports Nearest Airport: etc.? Indira Gandhi International Airport 0.32 Km SW Safdarjung Airport 9.22 Km NE Nearest Railway Station: New Delhi Railway Station 14.08 Km NE Palam Railway Station 4.83 Km NW IGI Airport Metro Station 3.46 Km NW Palam Railway Station 4.83 Km NW Shahbad Mohammadpur Rly. Station 4.99 Km NW

Nearest National Highway: NH-8 0.44 Km SE NH-2 13.25 Km NE NH-24 14.40 Km NE NH-236 6.92 Km SE NH-10 13.92 Km N “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

1.19 Closure or diversion of existing No No closure or diversion of existing transport transport routes or infrastructure routes or infrastructure leading to changes in leading to changes in traffic traffic movements will be made. movements? 1.20 New or diverted transmission No No such closure or diversion of transmission lines or pipelines? lines is required.

1.21 Impoundment, damming, No No impoundment, damming, culverting, culverting, realignment or other realignment or other changes to the changes to the hydrology of hydrology of surface water courses is watercourses or aquifers? required. 1.22 Stream crossings? No No stream crossing. Topographical map is enclosed as Enclosure 3.

1.23 Abstraction or transfers of water No Water will be supplied by DIAL (It is from ground or surface waters? estimated that 374 KLD of water requirement will be there in the proposed project.) 1.24 Changes in water bodies or the No There will be no change in water bodies or land surface affecting drainage the land surface effective drainage or run- or run-off? off.

1.25 Transport of personnel or Yes During Construction phase: materials for construction, Materials during construction phase will operation or decommissioning? transport by truck, trolley etc. During Operation Phase: Car, two-wheeler, etc. will be used.

1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in No During Construction phase: either temporarily or Temporary influx of people in the form of permanently? labours is envisaged. Approx. 150 no. of local labours shall be employed. During Operation Phase: As this is a Hotel complex and Convention Centre, 6600 guests, 900 no. of staff & visitors is envisaged. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

1.29 Introduction of alien species? No Not Applicable

1.30 Loss of native species or No There shall be no effect on any native genetic diversity? species.

1.31 Any other actions? No Not Applicable

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): S.No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible) with source of information data 2.1 Land especially Yes Existing Plot area- 31163.13 sq m undeveloped or agricultural The land was allotted for the development of land (ha) Hotel complex only.

The Construction has been done as per earlier environmental clearance. Now, further construction will be done on existing land only. There will be no addition of land use. 2.2 Water (expected source & Yes CopySource of land & Quantitypapers is enclosed During Constructionas Enclosure- competing users) unit: KLD 5.phase: Water during construction phase shall be taken from tanker water supplier with supply treated water from STP of nearby area. Source & Quantity During Operation Phase: The ultimate source of water will be through Delhi International Airport Pvt. Ltd. Total water requirement of the project will be 374 KLD out of which 166 KLD will be fresh water. Rest of the 208 KLD water requirement will be fulfilled by treated water. Detailed water Management & water Balance are given in Environmental management plan. 2.3 Minerals (MT) No Not applicable “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

2.4 Construction material – Yes The major materials required for construction stone, aggregates, sand / of the project are steel, tiles, glass, cement, soil (expected source – agate, bricks, flooring tiles / stones, sanitary MT) and hardware items, electrical fittings, etc.

2.5 Forests and timber (source Yes Plywood for doors & windows shall be used – MT) which shall be procured from local market. 2.6 Energy including electricity Yes Source of Electricity – Delhi International and fuels (source, Airport Pvt. Ltd. competing users) Unit: fuel Total Electrical Load (After Amendment)- (MT), energy (MW) 6000 KW D.G. sets for power back up- 3 X 2000 KVA 2.7 Any other natural No Not applicable resources (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 3.1 Use of substances or Yes This is a Hotel Complex & convention materials, which are Centre and no storage of hazardous hazardous (as per MSIHC chemicals (as per MSIHC rules) is being done, apart from used oil. Suitable rules) to human health or the management practice is being adopted for environment (flora, fauna, the same. It is storing in HDPE drums and and water supplies) kept in covered rooms under lock and key and sold to authorize vendors only. Specialized care is being taken to prevent leaks and spills. High Speed Diesel (low sulphur variety) is being used for D.G. Sets however; the quantity stored is below the threshold limit specified by the MSIHC rules. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

3.2 Changes in occurrence of No Suitable drainage and waste management disease or affect disease measures will be adopted in both the vectors (e.g. insect or water construction and operational phase which borne diseases) will restrict stagnation of water or accumulation of water. This will effectively restrict the reproduction and growth of disease vectors. 3.3 Affect the welfare of people Yes During Construction phase: e.g. by changing living conditions? Employment opportunities provided due to the project has led to better quality of life & have also set a standard for future developments in the area. Moreover, during construction phase about 150 no. of local labors will be employed.

During Operation Phase: As it is a Hotel Centre and Convention Centre, there shall be several services required which will generate direct & indirect employment to 400 people of nearby area. 3.4 Vulnerable groups of people No No vulnerable group of people will be who could be affected by the affected by the project. project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No None

4. Production of solid wastes during construction or operation or

S.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No Not applicable wastes. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

4.2 Municipal waste (domestic Yes During Construction phase: and or commercial wastes) Solid waste during construction phase shall be 23 kg/day which will be disposed off at municipal solid waste site.

During Operation Phase: Approx. 3105 Kg/day of solid waste shall be generated from the complex during operational phase. Detailed Solid Waste Management is given Environmental Management Plan. 4.3 Hazardous wastes (as per Yes During Construction phase: Hazardous Waste Used oil whenever generated from the DG Management Rules) sets is being kept in leak proof containers in an isolated area and will be sent to approved recycler. During Operation Phase: 42 Lt/month used oil generated from diesel generators will be carefully stored in HDPE drums in isolated covered facility. The used oil will be sold to vendors authorized by Central Pollution Control Board for the treatment of the same. Suitable care will be taken so that spills / leaks of used oil from storage could be avoided. 4.4 Other industrial process No Not Applicable wastes 4.5 Surplus product No Not applicable

4.6 Sewage sludge or other Yes About 27 Kg/day of dried sludge will be sludge from effluent generated from STP within complex during treatment operation phase and this sludge will be passed through filter press where it will be dewatered/ dried to form a cake and then will be used as manure in green areas. The unused sludge shall be given to farmers or nursery. 4.7 Construction or demolition Yes Construction waste is being used for flooring wastes & Back filling in roads etc. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

4.8 Redundant machinery or No Not applicable equipment 4.9 Contaminated soils or other No Not applicable materials

4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes No During Construction phase: No E-waste is being generated. During Operation Phase: 2 Kg/month E- waste shall be generated. It shall be given to approved recycler of SPCB. Battery waste shall be generated from inverters & UPS which shall be disposed off as per the Batteries (Management & Handling) Rules, 2001.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data

5.1 Emissions from Yes During Construction phase: combustion of fossil fuels DG sets of capacity 62.5 KVA shall be installed from stationary or mobile acoustically enclosed with adequate stack sources height.

During Operation Phase: The only source of emission from combustion of fuel will be DG set of 3x 2000 KVA. Hence, to avoid the emissions, stack height of 3 m above roof level for the D.G. Set shall be provided. The DG set will be provided with wet scrubber.

5.2 Emissions from production No Not applicable processes “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

5.3 Emissions from materials Yes Dust will generate during construction, from the handling including storage movement of transport vehicles & other or transport construction activities. The effect is restricted to construction phase only. Water sprinklers are being used for dust suppression. Material shall be stored under Tarpaulin cover.

5.4 Emissions from Yes Dust & emissions are generated during construction activities construction activities which is being reduced including plant and by sprinkling of water in a specific time interval equipment & timely maintenance schedule for machinery. Also the machines are being shut down during idle period. 5.5 Dust or odours from Yes During loading & unloading of construction handling of materials material dust is likely to be generated during including construction construction phase. Water was being sprinkled materials, sewage and and tarpaulin cover was provided over stored waste raw material to reduce dust emission, same shall be maintained during proposed construction. Mobile Toilets during construction phase shall be provided & waste water will be disposed off in septic tank followed by soak pits. 5.6 Emissions from No Not applicable. incineration of waste. 5.7 Emissions from burning of No Open burning of biomass/ other material will be waste in open air (e.g. prohibited. slash materials, construction debris). 5.8 Emissions from any other No None sources. 6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data with source of information data “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

6.1 From operation of equipment No During Construction phase: e.g. engines,ventilation plant, DG set of capacity 62.5 KVA shall be crushers installed acoustically enclosed. The equipment such as mixer machines, bulldozers, cranes, compactors & excavators were being used which were of highest standard of reputed make and adhere to international standards. Hence an insignificant impact due to construction machinery was envisaged and same shall be followed in construction phase.

Apart from this, the construction activities are restricted to daytime only and timely maintenance of machinery is ensured.

During Operation Phase: Source of noise in the operational phase will be D.G. Set of capacity 3 x 2000 KVA. The D.G. Set shall be acoustically enclosed & shall be installed with anti-vibration pads and will be used during Power failure only. They may generate noise level maximum upto 75 dB (A). 6.2 From industrial or similar No Not applicable processes 6.3 From construction or demolition Yes Due to the various activities there are short- term noise impacts in the immediate vicinity of the project site. These are restricted to day time only. It has been estimated that during the construction period the average noise level is 80-100 dB (A) during peak construction hours. However, embankment has been done to further prevent the noise pollution. 6.4 From blasting or piling No No blasting or piling will be done. 6.5 From construction or Yes Some amount of noise (70 – 75 dB (A)) will operational traffic be generated from vehicular movement in the construction and operational phase. Plantation around the boundary wall shall be done to reduce noise from traffic. “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No None

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No The hazardous waste generated will be spillage of hazardous materials Used oil and E-waste only. Used Oil will be stored in HDPE drums and kept in covered rooms under lock and key and will be sold to authorized vendors only. E-waste shall be stored separately and given to approved recycler by CPCB. Special care will be taken to prevent leakages and spills. 7.2 From discharge of sewage or No During operational phase 310 KLD STP will other effluents to water or the be installed for treating the 258 KLD waste land (expected mode and place water & 208 KLD of treated water shall be of discharge) reused in flushing, gardening, cooling & misc. purpose. 7.3 By deposition of pollutants No No major fresh water bodies are located in emitted to air into the land or downward direction hence no risk of into water contamination of water from release of pollutants. 7.4 From any other sources No Not applicable 7.5 Is there a risk of long term build- No Not applicable up of pollutants in the environment from these sources? 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment.

S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

8.1 From explosions, spillages, No During Construction Phase: fires etc. from storage, All appropriate measures are being taken to handling, use or production avoid accidents. of hazardous substances During Operational Phase: Proper Disaster management & firefighting system will be installed at site. 8.2 From any other causes No During Construction Phase: All the labours were provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms had been provided to all supervisors and labours involved in construction activity. Same shall be done during further construction. 8.3 Could the project be affected No The area under study falls in Seismic zone- by natural disasters causing IV, according to the Indian Standard Seismic environmental damage (e.g. Zoning Map. Suitable seismic coefficients in floods, earthquakes, horizontal and vertical directions landslides, cloudburst etc.)? respectively, will be adopted while designing the structure.

“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.

S. No. Information/Checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of supporting facilities, ancillary development or No development stimulated by the project which could have impact on the environment e.g.:

 Supporting infrastructure

(roads, power supply, Yes waste or waste water STP will be installed for the treatment of

treatment, etc.) wastewater.

 Housing development No Not Applicable  Extractive industries No Not Applicable  Supply industries No Not Applicable  Other No Not Applicable 9.2 Lead to after-use of the site, which No Proper care shall be taken to avoid any could have an impact on the disturbances environment. 9.3 Set a precedent for later Yes Infrastructure development of area. Socio developments Economic condition will be improved. 9.4 Have cumulative effects due to No No impact proximity to other existing or planned projects with similar effects

“Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

III. Environmental Sensitivity

Areas Name/ Aerial distance (within 15 km.) from Proposed project location S. Identity boundary No.

1 Areas protected under Rashtrapati Bhawan 10.51 Km NE international conventions, Parliament House 11.36 Km NE national or local legislation for their ecological, landscape, 12.70 Km NE cultural or other related value Qutub Minar 6.89 Km SE National Zoological Park 13.56 Km NE

2 Areas which are important or Water Bodies sensitive for ecological reasons - Yamuna River 14.64 Km NE Wetlands, watercourses or other Sanjay Lake 9.19 Km NE Shamshi Talab 6.74 Km SE water bodies, coastal zone, Old Fort Lake 13.55 Km NE biospheres, mountains, forests Neela Hauz 5.37 Km SE Najafgarh Drain 12.15 Km N Tank 6.85 Km E Bangla Sahib Sarover 12.07 Km NE Ghitorni Lake 6.45 Km SE

Forest Central Ridge Reserve 10.04 Km NE Forest Pusa Hill Forest 10.09 Km NE Southern Ridge Forest 9.85 Km NE Rajokri Protected Forest 3.32 Km SE 3 Areas used by protected, Asola Wild Life 14.73 Km SE important or sensitive species of Sanctuary flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

4 Inland, coastal, marine or None None underground waters.

5 State, National boundaries Haryana Boundary 5.14 Km SW “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

6 Routes or facilities used by the Nearest Road: public for access to recreation or NH-8 0.44 Km SE other tourist, pilgrim areas NH-2 13.25 Km NE NH-24 14.40 Km NE NH-236 6.92 Km SE NH-10 13.92 Km N

Nearest Railway Station: New Delhi Railway 14.08 Km NE Station Palam Railway Station 4.83 Km NW Shahbad Mohammadpur 4.99 Km NW Rly. Station IGI Airpoet Metro Station 3.46 Km NW Shivaji Bridge Railway 13.81 Km NE Station

Airport: Indira Gandhi International Airport 0.32 Km SW Safdarjung Airport 9.22 Km NE

7 Defense installations National Defense 10.96 Km NE Collage

Defence Store 11.04 Km NE Air Force Station 14.27 Km SE

8 Densely populated or built-up Dwarka 8.77 Km NW area “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

9 Areas occupied by sensitive Hospital: man-made land uses (hospitals, Airport Health 0.77 Km SW schools Organization Indian Spinal Injuries 2.76 Km SE , places of worship, community Centre facilities) Sacred Heart Hospital 2.24 Km SW Artemis Hospital 5.98 Km NW Holy Angels Hospital 4.38 Km NE

Post Office: Ghitorni Post Office 6.16 Km SE Lodhi Road Head Post 10.56 Km NE Office Naraina Industrial Estate 9.37 Km NE Post Office Kalkaji Head Post Office 13.39 Km E

Place of Worship: Sankat Mochan 0.92 Km NE Hanuman Mandir Brahma Kumaris 0.59 Km SE Rajyoga Center Masjid Chishtiya 7.05 Km NW Gufa Wala Mandir 6.57 Km NW Ayyappa Temple 6.98 Km NW

School: Delhi Public School, 5.91 Km NE R.K.Puram St. Paul School 7.69 Km E HauzKhas The British School 7.85 Km NE Salwan Junior School 8.59 Km NE

Bank: Bank of Tokyo 0.23 Km NE Mitsubishi UFJ Indian Bank of Overseas 0.47 Km SE

ATM SBI AAI Rangpuri 1.02 Km SW Kotak Mhindra Bank 0.01 KM SW ATM 10 Areas containing important, high None None quality or scarce resources “Hotel Complex & Convention Centre” M/s Aerocity Hotel & Global Centre (Delhi) Pvt. Ltd.

(Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

11 Areas already subjected to None None pollution or environmental damage. (Those where existing legal environmental standards are exceeded)

12 Areas susceptible to natural The project area falls in seismic hazard which could cause the zone –IV. project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

“Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

FORM 1A

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

I. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1 Will the existing land use get The proposed project site is proposed at Asset no. significantly altered from the project 13, Hospitality District, DIAL, IGI Airport, Delhi that is not consistent with the The construction was started as per earlier surroundings? (Proposed land use Environmental Clearance granted vide F no. must conform to the approved 92/DPCC/SEIAA-SEAC/10/1444-1448 dated 11th Nov Master Plan / Development Plan of 2010“Hotel Complex & Convention Centre”. the area. Change of land use if any and the statutory approval from the No land use change is anticipated. competent authority be submitted).

Attach Maps of

(i) Site location The site location shown on Google Map is enclosed as Enclosure- (ii) Surrounding features of the Map showing vicinity around the site is enclosed as proposed site (within 500 meters) Enclosure- (iii) The site (indicating levels & contours) to appropriate scales. If not Contour is enclosed as Enclosure- 7. available attach only conceptual plans. 1.2 List out all the major project requirements in terms of the Land area, Total Plot area = 31163.13 sq m

Built up area 212732.72 sq m Water consumption 374 KLD Power requirement 6000 KW Connectivity Expressway Highway NH-8 – 0.44 Km SE Community facilities Hotel, Convention Centre, Retail, Banquet, Country Club and Swimming Pool.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 25 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

Parking needs etc. Parking Requirement – 1623 ECS Parking Provisions – 2168 ECS 1.3 What are the likely impacts of the The entire project influenced area was developed as proposed activity on the existing per the provision of Master Pan, thus no induced facilities adjacent to the proposed development is foreseen due to the proposed project. site? Also the proposed development was carried out as per (Such as open spaces, community the defined building by-laws; hence no impact is facilities, details of the existing envisaged due to proposed development. Same shall landuse, and disturbance to the local be followed during further construction ecology). Construction phase as well as operation Phase of the project, will generate direct and indirect employment opportunities for a large section of society. The employment will have positive impact thereby increasing the quality of life. 1.4 Will there be any significant land No such significant land disturbance will result. disturbance resulting in erosion, However, care will be taken so that no erosion, subsidence & instability? subsidence & instability takes place. (Details of soil type, slope analysis, Slope Analysis: vulnerability to subsidence, The project area possesses fairly plain terrain. seismicity etc. may be given). Erosion / Subsidence: Proper greening & paving of area will not cause any soil erosion problem and subsidence. Seismicity: The area under study falls in Seismic zone-IV according to the Indian Standard Seismic Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structure. 1.5 Will the proposal involve alteration of The proposed project activities will not cause any natural drainage systems? alteration of natural drainage system. (Give details on a contour map showing the natural drainage near the proposed project site) 1.6 What are the quantities of earthwork During construction phase, 567000 cu m. of soil is involved in the construction activity excavated in order to provide of basement cutting, filling, reclamation etc. foundation. This excavated soil has been properly (Give details of the quantities of stacked within site under tarpaulin cover and is being earthwork involved, transport of fill reused for back filling purposes. The top soil is materials from outside the site etc.) preserved for landscaping purpose only. Hence, no adverse impacts on the land environment are envisaged.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 26 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

1.7 Give details regarding water supply, Water Supply: During Construction stage, water waste handling etc. during the will be sourced through nearby STP through tanker construction period. supplier. Waste Generation / Handling: Spillage of oil from the machinery or cement residual from concrete mixer plants would be properly collected and reused in construction site. For construction labour, proper sanitary facilities & wash areas were being constructed such as mobile toilets and good hygienic conditions will be maintained in further construction phase also. 1.8 Will the low lying areas & wetlands No low lying and wetlands area are present in and get altered? around the project site. (Provide details of how low lying and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & waste The construction debris generated from the during construction cause health construction project is common in nature and will not hazard? (Give quantities of various cause any health hazard to associate and nearby types of wastes generated during population. The construction debris will be used for construction including the land leveling / backfilling and landscaping according to construction labour and the means of its composition. Steel scrap will be given to recycler. disposal) Waste concrete will be reused as aggregate in construction process. Approx. 150 labours is being engaged during the construction period. Proper sanitary facilities are provided to construction labourers. Wash areas are constructed and good hygienic conditions is maintained.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 27 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

2. WATER ENVIRONMENT

2.1 Give the total quantity of water The total quantity of water requirement shall be 374 requirement for the proposed KLD which will be provide by Delhi International Airport project with the breakup of Pvt Limited requirements for various uses. Water Balance Diagram is given in Environmental How will the water requirement Management Plan. met? Water Storage during operation: State the sources & quantities and Storage will be provided for one-day requirement after furnish a water balance statement. ascertaining the one-day average water requirement. In order to ascertain the quantity of water consumed, the supply will be through the water meter installed in the supply line. The water main will be led into Firefighting storage tanks and from these compartments; the water will be allowed to overflow into raw water tanks.

2.2 What is the capacity (dependable Daily water demand for the Hotel Complex & flow or yield) of the proposed convention centre has been calculated to be around source of water? 374 KL / Day. Water demand will be met from Delhi International Airport Pvt. Limited. 2.3 What is the quality of water In case supply is not made or the supply made is required, in case, the supply is not inadequate then the water shall be arranged through from a municipal source? (Provide Tankers. In that case the water quality at the project physical, chemical, biological site will be of standard as prescribed by the appropriate characteristics with class of water authority. quality) 2.4 How much of the water Total treated water of 208 KLD shall be generated from requirement can be met from the the S.T.P and shall be reused in flushing, gardening, recycling of treated wastewater? HVAC cooling & misc. purposes within the project (Give the details of quantities, premises. Approx. 55.6 % of total water requirement sources and usage) will be met by recycled water. 2.5 Will there be diversion of water There will not be any substantial effect on water from other users? demand of this region as the development will be done (Please assess the impacts of the as per the development plan of the area. project on other existing uses and quantities of consumption)

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 28 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

2.6 What is the incremental pollution The total waste water generation from the complex will load from wastewater generated be 258 KLD which will be treated in in-house S.T.P of from the proposed activity? capacity 310 KLD. 208 KLD of the treated water will be reused for flushing, gardening, HVAC cooling & misc. (Give details of the quantities and purposes. Excess water shall be discharge to sewer. composition of wastewater generated from the proposed activity) 2.7 Give details of the water The rain water from terraces and other open area will requirements met from water be collected in Rain Water Storage Tank (2 no.) of 250 harvesting? Furnish details of the Cum Capacity. The details of Rain Water Storage is facilities created. given in Environmental Management plan.

2.8 What would be the impact of the After construction of complex; the rain water will be land use changes occurring due to properly channelized to rain water collection tanks the proposed project on the runoff through storm water drain within the complex excess characteristics (quantitative as rain water will be discharged in to the existing storm well as qualitative) of the area in water drainage of the area. the post construction phase on a long-term basis? Would it aggravate the problems of No, it will not aggravate the problem of flooding or water flooding or water logging in any logging in any way, rather will reduce the same. way? 2.9 What are the impacts of the There will be no ground water extraction, however proposal on the ground water? ground water recharging is proposed through rain (Will there be tapping of ground water harvesting, so, there will be positive impact on water; give the details of ground ground water levels. water table, recharging capacity, and approvals obtained from competent authority, if any) 2.10 What precautions/measures are During the construction phase, runoff from the taken to prevent the run-off from construction site is not allowed into the roadside. It shall construction activities polluting be collected in a tank & after pre-treatment it is being land & aquifers? reused for sprinkling, curing, tyre washing etc, rest will (Give details of quantities and the be discharge in existing storm water drain of the area. measures taken to avoid the adverse impacts)

2.11 How is the storm water from within Adequate measures shall be taken to channelize such the site managed? storm water and the same shall be collected in rain water storage tanks. (State the provisions made to avoid flooding of the area, details

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 29 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

of the drainage facilities provided along with a site layout indication contour levels) 2.12 Will the deployment of construction Mobile toilets have been proposed for laborers during labourers particularly in the peak construction period. The waste will be disposed off to period lead to unsanitary septic tank via soak pit. conditions around the project site (Justify with proper explanation) 2.13 What on-site facilities are provided Waste water during construction phase from labors will for the collection, treatment & safe be discharged into septic tank followed by soak pit. disposal of sewage? (Give details of the quantities of wastewater generation, treatment During operation phase 258 KLD of waste water will be capacities with technology & treated in S.T.P. of 310 KLD capacity based on FAB facilities for recycling and disposal) technology. 80.6 % of treated water will be reused. 2.14 Give details of dual plumbing Dual Plumbing line will be provided in the complex for system if treated waste used is reuse of treated water. used for flushing of toilets or any other use.

3. VEGETATION

3.1 Is there any threat of the project to The ecology of the study area is not very rich in diversity the biodiversity? or high in endemism, nearby area is already developed. Planted species are dominated in buffer zone. Core (Give a description of the local zone is devoid of vegetation. ecosystem with its unique The major mammalian fauna of the project-influenced features, if any) area involves common languor, Rhesus macaques (Macaqua mulata), mongoose (Herpestris edwardii) etc. Avifauna is primarily represented by common crow (Corvus splendens), House sparrow (Passer domesticus), blue rock pigeon (Columba livia), Rose ring paraqeet (Pitecula cramerii), spotted doves (Streptopilia chinensis) and finches. Common peacock (Pavo cristatus), are known to be present in within 10 km study area. Small reptiles, primarily squamates like lizards, chameleons, poisonous & non-poisonous snakes are also found in the study area. No endangered or endemic species (as notified in IUCN Red Data Book) are located within the study area. No migratory birds breed in the study area. No Tiger reserve

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 30 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

/ turtle breeding place is located within 15 km radius of the study area. 3.2 Will the construction involve The proposed project site is an open land, which has extensive clearing or modification been earmarked for development of Hotel Complex of vegetation? hence there is no extensive clearing or modification of (Provide a detailed account of the vegetation. trees & vegetation affected by the project) 3.3 What are the measures proposed There will not be any kind of impact of this project on site to be taken to minimize the likely features. impacts on important site features The Shelter belt for the proposed project has been (Give details of proposal for tree planned to provide a clean, healthy and beautiful green plantation, landscaping, creation environment for the people to live in within the proposed of water bodies etc along with a project site. layout plan to an appropriate To minimize the impact, Green area will be provided of scale) 8102.49 sqm.

4. FAUNA

4.1 Is there likely to be any displacement of Core Zone: The proposed site is under construction fauna- both terrestrial and aquatic or & no fauna is found, so in existing conditions this place creation of barriers for their movement? is not the habitat for local fauna. There will not be any Provide the details. type of displacement or any other effect on the local fauna due to proposed project activities. Buffer Zone: There are No wild life sanctuaries within 10 km radius of the project site. 4.2 Any direct or indirect impacts on the As there is no distinct plantation at site, as trees planted avifauna of the area? Provide details. are very young, no avifauna seen at site, however, proper landscaping has been planned to provide a clean, healthy and beautiful green environment for the population. Common native variety of trees and ornamental flowering species are planted and more will be planted in the green space which will attract avifauna & hence will have direct positive impact on the local avifauna & this will provide shelter to local birds. 4.3 Prescribe measures such as corridors, Proper measures shall be taken to protect fauna fish ladders etc. to mitigate adverse in the area. impacts on fauna.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 31 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric The traffic will increase due to operation of complex. concentration of gases & result in Increased traffic generation of vehicles due to project heat islands? will not cause significant increase in atmospheric concentration of gases and do not result in heat island (Give details of background air formation. quality levels with predicted values Tree plantation in the complex will be provided such that based on dispersion models taking the impact of air pollution shall be minimized. into account the increased traffic Wet scrubber will be provided to control particulate generation as a result of the emission. proposed constructions) D.G. Set of capacity 3 x 2000 KVA will be installed in the complex which will be operated during power cut only. 5.2 What are the impacts on generation No dust, odour will be generated at site. Smoke will be of dust, smoke, odorous fumes or generated from the operation of DG sets. Proper stack other hazardous gases? Give details height and emission standards will be maintained as per in relation to all the meteorological CPCB guidelines. parameters. 5.3 Will the proposal create shortage of The optimum parking provision is proposed in the parking space for vehicles? Furnish basement & surface. Hence there will be no shortage of details of the present level of parking space for vehicles. Total parking provision of transport infrastructure and complex will be 2168 ECS. measures proposed for improvement including the traffic management at the entry & exit to the project site. 5.4 Provide details of the movement Maximum capacity of parking shall be provided in patterns with internal roads, bicycle basement and a proper route shall be provided for the tracks, pedestrian pathways, traffic movement as well as pedestrian movement. footpaths etc., with areas under each category. 5.5 Will there be significant increase in For further construction, noise barriers will be installed traffic noise & vibrations? Give to reduce traffic noise & vibrations and during operation details of the sources and the green belt developed within the complex which mitigate measures proposed for mitigation of the traffic noise. Proper care is being taken during the above. design so that there is not any increase in traffic noise by providing adequate traffic movement, hence no conjunction will cause. The foundation will be made very hard and paved with rubber flooring to minimize the vibration, also all other measures has been adopted during designing that there will not be any causes of vibrations during the traffic

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 32 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

density. No honking zone within the complex is being maintained. 5.6 What will be the impact of DG sets & There would be slight impact of D.G. Sets on noise other equipment on noise levels & levels, vibration and in ambient air quality around the vibration in & ambient air quality project site. around the project site? Provide 1. All the D.G. Sets of the proposed project would be details. bought acoustically enclosed in a room on basement. 2. Stack height as per C.P.C.B. norms to reduce the impacts on air quality around the project site will be provided 3. The noise from D.G. Sets will meet the desired standard as per CPCB guidelines. Low Sulphur fuel will be used to run these D.G. Sets. 4. Vibration pads will be used in DG sets to minimize the vibration effect.

6. AESTHETICS

6.1 Will the proposed constructions in After the construction of complex is complete, it will any way result in the obstruction of a increase the beauty of the area by having well-ordered view, scenic amenity or landscapes? buildings & proper landscaping. Are these considerations taken into Yes, all considerations have been taken by the account by the proponents? proponents. 6.2 Will there be any adverse impacts The development in the entire project influenced area is from new constructions on the as per the provision of Planning Department; hence no existing structures? What are the adverse impacts are anticipated from new constructions considerations taken into account? on the existing structures in this area. However, the proposed project will improve the lookout of area. 6.3 Whether there are any local There are no typical urban form & urban design considerations of urban form & urban influencing the design criteria. design influencing the design criteria? They may be explicitly spelt out. Are there any anthropological or No there is no anthropological or archaeological site or archaeological sites or artifacts artefacts near the site. nearby? State if any other significant features All significant features have been considered. in the vicinity of the proposed site have been considered.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 33 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any The operation of the project shall provide value addition changes to the demographic to the existing infrastructure. The proposed project will structure of local population? Provide provide job facilities to for a no. of persons in it During the details. construction phase about 150 -200 Nos. of skilled, unskilled and professional work force including temporary and permanent employees will be required per day. This workforce will be hired locally in order to generate the employment to the local people. 7.2 Give details of the existing social School: infrastructure around the proposed Delhi Public 5.91 Km NE project. School, R.K.Puram St. Paul School 7.69 Km E HauzKhas The British School 7.85 Km NE Salwan Junior 8.59 Km NE School

Bank:

Bank of Tokyo Mitsubishi UFJ 0.23 Km NE Indian Bank of Overseas 0.47 Km SE 7.3 Will the project cause adverse effects The proposed complex will be constructed with in the on local communities, disturbance to designed site as per defined building by laws of sacred sites or other cultural values? government authority. There is no sacred or cultural What are the safeguards proposed? heritage site with in vicinity of proposed project; hence no adverse impacts are envisaged.

8. BUILDING MATERIALS

8.1 May involve the use of building The major materials required for construction of the materials with high-embodied project are steel, cement, bricks, flooring tiles/ stones, energy. sanitary and hardware items, electrical fittings, etc. Are the construction materials Energy efficient building material shall be used. produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency 8.2 Transport and handling of materials Mitigate Measures for Air Pollution During construction during construction may result in stage: pollution, noise & public nuisance. All the loose material either stacked or transported shall What measures are taken to be provided with suitable covering such as tarpaulin, minimize the impacts? etc. Water sprinkling shall be done at the location where

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 34 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

dust generation is anticipated. To minimize the occupational health hazard, proper personal protective gears i.e. mask shall be provided to the workers who are engaged in dust generation activity. Wet scrubber will be provided to control particulate emission. Mitigate Measures for Noise Pollution during Construction stage: Isolation of noise generation sources and temporal differentiation of noise generating activities will ensure minimum noise at receiver’s end. To prevent any occupational hazard, ear muff / ear plug shall be given to the workers working around or operating plant and machinery emitting high noise levels. Use of such plant or machinery shall not be allowed during night hours. Careful planting of machinery operation and scheduling of operations shall be done to minimize such impact. 8.3 Are recycled materials used in roads The debris of construction material shall be used in and structures? backfilling, roads etc. State the extent of savings achieved? 8.4 Give details of the methods of The solid waste will be disposed off as per Municipal collection, segregation & disposal of Solid Waste (Management and Handling) Rules, 2000. the garbage generated during the Details are given in Environment Report. operation phases of the project.

9. ENERGY CONSERVATION

9.1 Give details of the power Power Requirement – 6000 KW requirements, source of supply, Source of Power: DIAL backup source etc. Back-up Source: What is the energy consumption Power back up is proposed by using D.G. Sets of 3 x 2000 assumed per square foot of built-up KVA. area? How have you tried to minimize During power failure D.G. Sets will start automatically. energy consumption? Fuel consumption for DG Sets calculated to be 14 ltr/month (when in operation) of Low Sulphur Diesel. As per the latest C.P.C.B. norms, D.G. Sets have to be installed in acoustic enclosure and silencer.

Energy Conservation Measures & Management Plan:

 In the operational phase, appropriate energy conservation measures & management plan will be adopted in order to minimize the consumptions of

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 35 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

non-renewable fuel. The following measures are suggested to be adopted.  Compact fluorescent lamps will be used in place of incandescent halogen lamps in all common areas and basement parking.  The water supply pumping system shall be provided with variable speed drive to conserve energy at part load.  Lighting and switching shall be designed by keeping in mind day light integration.  Solar energy will be used in street lighting, solar water heater and solar landscape lighting.

The DG/G.G. Sets shall be automatically controlled to optimize the usage based on the actual load requirement at any given time. 9.2 What type of and capacity of power DG Sets: 3 x 2000 KVA Fuel: Ultra Low sulphur diesel. back-up do you plan to provide? 9.3 What are the characteristics of the Double Reflective glass will be used. glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? 9.4 What passive solar architectural Building design and envelope shall be optimized through features are being used in the selection of appropriate wall and roof construction and building? through adoption of solar measures. Illustrate the applications made in the proposed project. 9.5 Does the layout of streets & buildings Yes, the layout of buildings have been designed to maximize the potential for solar energy devices? maximize the potential for use of solar lighting per day Have you considered the use of devices. street lighting, emergency lighting and solar hot water systems for use in the building? Substantiate with Yes, solar lights shall be used. details. 9.6. Is shading effectively used to reduce Solar Measures shall be adopted to provide shading cooling/heating loads? What devices for windows and roof which would effectively principles have been used to reduce heating up of building envelope. Louvers and maximize the shading of Walls on the sunshades will be used around windows in order to East and the West and the Roof? How much energy saving has been protect from direct sunlight. effected? Roofs will be painted with reflective aluminum based paints with solar reflectance ranging from 0.3-0.6. This will result in less absorption of sunlight causing 40 % back reflection and less heating of building structure during summer season. This will effectively reduce the heat load of the building envelope.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 36 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

9.7 Do the structures use energy- Suitable energy optimization will be adopted during the efficient space conditioning, lighting calculation of energy load of the proposed project. The and mechanical systems? Provide space heating load will be minimized using solar structure technical details. and suitable building envelop material. Uses of

incandescent lamp and halogen lamps have been avoided and energy efficient CFL light shall be used for all common area and other areas.

Provide details of the transformers The diesel generator sets shall be automatically controlled and motor efficiencies, lighting to optimize their usage based on the actual load intensity and air-conditioning load requirements at any time. Space conditioning will be assumptions? provided as per norms of National Building Code – Part 8; Building Services Section 3–Mechanical Ventilation.

Lighting intensity will be done as per the National Building Code Guidelines.

Are you using CFC and HCFC free CFC and HCFC free chillers will be provided. chillers? Provide specifications 9.8 What are the likely effects of the No significant effect is envisaged on the surrounding building activity in altering the micro- environment of project. Increased traffic generation and climates? use of diesel generators sets( only during power failure ) Provide a self-assessment on the in the project will not cause significant increase in likely impacts of the proposed construction on creation of heat atmospheric concentration of gases and will not result in island & inversion effects? heat island formation. 9.9 What are the thermal characteristics S. No BUILDING MATERIAL ‘R’ Values ‘U’ Values of the building envelope? (a) roof; (b) PROPOSED (in Sq m. Deg (in Watts/ Sq m. WITH U & R VALUES C/ Watts ) Deg C) external walls; and (c) fenestration? 1. Wall 2.28 0.44 Give details of the material used and Brick & ACC Blocks wall the U-values or the R values of the (230 mm thick), both side thick sand cement plaster individual components. (12-18mm) with insulation.

2. Roof 2.04 0.49 200 mm RCC slab with mud phuska & clay tiles with 75 mm insulation.

3. Double Reflective Glass 0.30 3.3

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 37 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

9.10 What precautions & safety measures The basic system of Fire Fighting shall be designed as per are proposed against fire hazards? the provisions of the National Building Code 2005 Furnish details of emergency plans. Water shall be drawn from fire reserve tanks by electrically driven jockey pumps, fire pumps. A standby diesel engine driven pump for fire hydrant pump shall also be provided. All pumps shall have separate suction line from the fire suction header and delivery shall be connected to the system. Diesel engine driven fire pump shall be of the same capacity and shall back up the electrically operated fire hydrant, as per fire regulations. This will be operated in case of total electrical power or electrical pump failure. Independent jockey pumps (for hydrant line) shall operate intermittently in order to take care of hydraulic losses in the system and shall maintain the minimum pressure respectively in wet risers. FIRE HYDRANTS Fire department connections, capable of directly feeding the ring mains or static fire reserve tanks, shall also be provided near the main entrance. It shall also be provided on the external wall of the property near the main entrance. Internal standpipe fire hydrant system shall be provided with landing valve, hose reel, first aid hose reels, complete with instantaneous pattern short gunmetal pipe. FIRE HOSE CABINETS The hose cabinet to accommodate the Hose Pipes, Branch Pipe, Nozzle and Hydrant Outlets shall be fabricated from 2 mm thick or 14 mm gauge aluminium sheet. Internal Hydrants shall accommodate the Hose Reel equipment. The hose cabinet shall be painted red and stove enamelled. EXTINGUISHERS Hand held extinguishers shall be located so that the maximum travel distance is not more than 23 meters and would generally be located in or adjacent to the fire hose reel cabinet. Fire Safety:

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 38 “Hotel Complex & Convention Centre” M/s Heaven Star Reality Pvt. Ltd.

The building materials shall be of appropriate fire resistance standards. Further, design shall include provisions for the following:  The electrical systems shall be provided with automatic circuit breakers activated by the rise of current as well as activated by over current.  Fire detection system.  Fire alarm system at appropriate places.  Means of escape  Access for fireman  Emergency Lighting:  The emergency lights operated on battery power should be provided at appropriate locations such as corridors, common area, staircase, exit and entrance doors, parking etc. 9.11 If you are using glass as wall material Yes, we are using glass in our structure. provides details and specifications S. No BUILDING MATERIAL ‘R’ Values ‘U’ Values including emissive and thermal PROPOSED (in Sq m. Deg (in Watts/ Sq m. characteristics. WITH U & R VALUES C/ Watts ) Deg C) 1. Double Reflective 0.30 3.3 Glass

9.12 What is the rate of air infiltration into All the window and door will be airtight quality, hence we the building? don’t foresee any air infiltration Provide details of how you are mitigating the effects of infiltration. 9.13 To what extent the non-conventional Solar energy will be used to meet some electric requirement. It energy technologies are utilized in is proposed to install solar Heater to generate hot water and the overall energy consumption? link it to the main hot water system for augmenting the hot water Provide details of the renewable supply to various areas. energy technologies used. 10. ENVIRONMENT MANAGEMENT PLAN

10.1 The Environment Management Plan Environment Management Plan is given in Environment would consist of all mitigation Report attached as ENCLOSURE -2 measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

Prepared by: -M/s Perfact Enviro Solutions Pvt. Ltd. 39