KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX D – ENVIRONMENTAL MITIGATION IMPLEMENTATION SCHEDULE (EMIS)

Part B – Mitigation, Operating Controls, Monitoring and Inspection

1 Environmental Control Plan - Air Pollution Controls Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation measure – Erect hoarding not less than 2.4m As per mitigation description - At all times Site high from ground level along site boundary (except Supervision entrances) adjoining street, road and the like and areas accessible to the public (not applicable to hard-paved sites) 2 Mitigation measure - Any excavated dusty materials or As per mitigation description - At all times Site stockpile of dusty materials shall be covered entirely by Supervision impervious sheeting or sprayed with water so as to maintain the surface wet 3 Mitigation measure – Establish vehicle washing facilities Constructed in accordance with - At all times whilst site exit point Site at each vehicle exit point from site except where site is drawings, where appropriate is in use Supervision completely hard paved Maintenance of facility in accordance with maintenance schedule 4 Mitigation measure - Every stock of more than 20 bags of As per mitigation description - At all times Site cement should be covered entirely by impervious Supervision sheeting or placed in an area sheltered on the top and the 3 sides; 5 Mitigation measure - Cement, or any dusty materials As per mitigation description - At all times Site collected by fabric filters or other air pollution control Supervision system or equipment should be disposed of in totally enclosed containers; 6 Mitigation measure - Stockpiles of dusty materials shall As per mitigation description - At all times Site be either covered entirely by impervious sheeting, placed Supervision in an area sheltered on the top and 3 sides; or sprayed with water so as to maintain the surface wet;

EA00770/R26/1 May 2003 Appendix D - Page 1 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

1 Environmental Control Plan - Air Pollution Controls Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 7 Mitigation measure – Carry out regular watering using fine As per mitigation description - At all times during dry Site spray or water truck during dry conditions to reduce dust conditions Supervision from exposed site surfaces and unpaved roads Frequently water particular dusty construction areas close to the site boundary and sensitive receivers 8 Mitigation measure – provide wheel wash bay with silt Wheel wash with silt trap and/or - At all times during dry Site trap and/or high pressure water jet or similar cleaning high pressure water jet to be conditions Supervision facility at vehicle entry/exit points to work site areas provided and hard paving of road (except where completely hard paved). between road and exit 9 Mitigation measure – water or spray haul roads and work Water spray or similar method - At all times during dry Nominated areas, including such activities as concrete drilling and conditions staff breaking, to suppress dust where necessary (e.g. during dry and windy conditions). 10 Mitigating measure – minimise number and size of As per mitigation description - At all times during dry Supervision stockpiles of dusty material and protect when necessary conditions staff (e.g. windy condition). 11 Operating control – ensure that trucks delivering ballast Remove residue and fine materials - During handling and laying of Supervision are cleaned before loading and material on trucks is that could cause dust, use tarpaulin ballast staff covered during transport. or similar to cover trucks 12 Operating control – check ballast material when received In accordance with Receipt - During handling and laying of Supervision on site to ensure that it is in a dampened state. Inspection Procedure – QMP 10.1 ballast staff

13 Operating control – during ballast profiling, spray water on Prepare and follow Method - During handling and laying of Supervision to material to minimise dust generation. Statement for laying ballast ballast staff

14 Operating control - cover trucks carrying dusty materials As per mitigation measure - At all times Supervision with tarpaulin or similar when transporting materials off staff site 15 Operating control - Construction plant and vehicles are to Erect notices and include in - At all times PEC or use vehicle wheel and body washing facilities when awareness training for nominee leaving the site subcontractors

EA00770/R26/1 May 2003 Appendix D - Page 2 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

1 Environmental Control Plan - Air Pollution Controls Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 16 Mitigation measures – Control vehicle speeds on site Establish speed limit signs on site - At all times Nominated site (max 15kph on unpaved road staff section) Ensure that signs are positioned prominently on site 17 Mitigation measure - Position plant as far as possible from As per mitigation measure - At all times Supervision sensitive receiver wherever practicable staff

18 Monitoring – check that mitigation measures and Conduct inspections of each site Routine Environmental Weekly, following complaint or PEC or operating controls are effective. using checklist Monitoring Checklist - before extreme weather nominee

19 Monitoring - Periodically check and monitor condition of Observe operating plant to ensure Routine Environmental Weekly or on receipt of PEC or plant with respect to exhaust emissions. no excessive black smoke (Better Monitoring Checklist - complaint or in case of dispute nominee than Ringelmann chart no.1)

EA00770/R26/1 May 2003 Appendix D - Page 3 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

2 Environmental Control Plan - Water Pollution Controls Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation measures – design temporary drainage system In accordance with the guidelines Layout drawings showing Following Contract Award Technical for each site location complete with appropriate facilities provided in ProPECC PN 1/94 and drainage, treatment Manager or to treat water prior to discharge off site from areas such the Leighton Environmental facilities and discharge nominee as exposed earth slopes, material stockpiles, wheel wash Management Reference Volume points bays, etc. 2 Mitigation measures – install temporary site drainage and In accordance with design and - Once, following design of Nominated site treatment facilities. drawings system staff

3 Mitigation measures – install oil interceptors into As per temporary drainage drawing - Once, following design of Nominated site temporary drainage system downstream of any oil/fuel system staff pollution sources. 4 Mitigation measure and control – install foul water holding As per site layout drawings, - Once, following design of Nominated site tanks for project office facilities capacity to suit office requirements system staff

5 Mitigation measure - Incorporate drip trays or similar Adequate capacity (110% of tank - Throughout duration of contract Foremen under major items of static plant and bulk storage of oil, capacity) Subcontractor fuel and chemical tanks Good condition / no leakage Valves operating / shut 6 Mitigation measure– provide chemical toilet facilities Number to suit site requirements - Throughout duration of contract Nominated site along site where required staff

7 Operating control - arrange regular emptying of holding In accordance with maintenance Trip tickets for disposal Throughout duration of contract Nominated site tanks / chemical toilets by reputable disposal company schedule staff

8 Operating controls – clean and maintain temporary site In accordance with maintenance - Throughout duration of contract Nominated site drainage system, site facilities, wheel wash bays and silt / schedules to ensure effective staff sand traps operation 9 Operating controls – check drainage at discharge point In accordance with maintenance - Throughout duration of contract Nominated site schedule to keep clear of debris and staff silt that could cause flooding

EA00770/R26/1 May 2003 Appendix D - Page 4 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

2 Environmental Control Plan - Water Pollution Controls Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 10 Operating controls – ensure that cementitious Use wash out skips / pits to - Throughout duration of contract Foremen / construction effluent (e.g. concrete truck washout and minimise water and land Subcontractor slurry) is discharged with care to avoid water and soil contamination contamination 11 Operating controls – carry out site checks following the In accordance with environmental - Throughout duration of contract Nominated site raising of a rainstorm or typhoon warning emergency procedures (see staff appendix B, section 5.7). 12 Monitoring and inspection - check effectiveness of As per checklist requirements Routine Environmental Weekly or following complaint PEC or mitigation measures Monitoring Checklist nominee

13 Monitoring – Check water quality of effluent discharged Method in accordance with Leighton Routine Water Quality Weekly or following complaint PEC or from site Environmental Reference Volume to Monitoring Checklist nominee meet quality requirements stated on the Discharge Licence. 14 Monitoring – sample and test effluent from each Sampling and testing in accordance Test results As per the Discharge Licence PEC or discharge point in accordance with the conditions for with EM&A Manual requirements nominee sampling and testing on the Site Discharge Licence Test results to meet Discharge Licence water quality parameters

EA00770/R26/1 May 2003 Appendix D - Page 5 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

3 Environmental Control Plan - Noise Control Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation measures – Use temporary movable noise Assess cumulative noise levels - Throughout grade separation Technical barriers where cumulative noise impacts due to Leighton using methods from the Technical works and Manager or construction activities are likely to exceed 75 dB (A) at Memorandum and from site nominee NSR. (or as modified by baseline results). measurement Production Barriers to be sized to shield plant staff activities from NSRs. Barriers to be positioned as close to plant as is safe and practicable Surface density of barriers to be not less than 7 kg/m2 2 Mitigation measures – Check physical condition of plant Plant maintained and in good order - All activities throughout the Supervision and other mechanical equipment with respect to No loose fittings duration of the project staff production of noise where appropriate and remove and repair plant and equipment that generates excessive Silencers effective noise. 3 Mitigation measures – Operation of plant and other Engine compartment doors shut - All activities throughout the Supervision mechanical equipment with respect to noise where Static plant located and/or duration of the project staff appropriate and switch off or throttle down equipment orientated away from sensitive while not in use. Valid noise labels should be displayed areas on handheld breakers and air compressors. Plant shut down when not in use 4 Mitigation measure – use of quiet plant where practicable. Select plant with effective silencers - All activities throughout the Supervision and mufflers to reduce noise levels duration of the project staff

5 Mitigation measure – reduction in number of plant Minimise the number of construction - Throughout duration of project Supervision operating simultaneously and/or in close proximity of activities being carried out at the staff critical NSRs same time when near to NSRs. 6 Mitigation measure – using stockpiles or other structures Arrange stockpiles or other - Throughout duration of project Supervision to screen noisy site activities structures near NSRs to screen staff noise where practicable 7 Operating controls – Display Construction Noise Permits Display in accordance with CNP CNP on display While CNP is valid PEC or on site requirement and on notice boards nominee

EA00770/R26/1 May 2003 Appendix D - Page 6 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

3 Environmental Control Plan - Noise Control Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 8 Operating controls - Implement contingency plan (EM&A Follow Event Contingency Plan for - Following receipt of reported PEC or Manual) for construction noise in response to cases of Construction Noise (see EM&A exceedance, throughout nominee reported exceedances of Maximum Acceptable Impact Manual) duration of project Level at NSRs 9 Monitoring and Inspection – Check the effectiveness of Visual monitoring of activities in Routine Environmental Weekly, or following complaint PEC or mitigation measures and operating controls accordance with checklist Monitoring Checklist nominee requirements 10 Monitoring and inspection – check infrastructure and Visual monitoring of infrastructure Routine Environmental Weekly, or following complaint PEC or buildings in vicinity of site for any damage caused by and buildings Monitoring Checklist nominee plant and equipment or site activity.

EA00770/R26/1 May 2003 Appendix D - Page 7 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

4 Environmental Control Plan - Waste Management Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation measure - establish Chemical Waste Storage In accordance with Code of Practice - Before production of Chemical PEC Facility(s) on site (see Waste Management Plan for on the Packaging, Labelling and Waste details and location maps). Storage of Chemical Wastes. 2 Mitigation measure – provide and maintain adequate Adequate capacity - Throughout the duration of the Supervision number of waste skips on site to avoid littering and visual project staff impacts. 3 Mitigation measure – check that waste skips are being Adequate capacity for workforce / - Throughout the duration of the Supervision changed in timely manner and that no refuse and food activities project staff remnants are littering work areas 4 Mitigation measure – check that chemical (waste oil etc) In accordance with Code of Practice - Throughout the duration of the Supervision waste drums are available, in use, labelled and suitably on the Packaging, Labelling and project staff stored Storage of Chemical Wastes. 5 Mitigation measure - disposal of chemical waste via In accordance with Code of Practice - Throughout the duration of the PEC or licensed waste collectors on the Packaging, Labelling and project nominee Storage of Chemical Wastes. 6 Mitigation measure – ensure that surplus concrete is No waste concrete disposed to - Throughout the duration of the PEC or discharged in a controlled manner landfill where practicable project nominee

7 Operating Controls - Where site conditions permit, Establish site area for storage of - Throughout the duration of the PEC or segregate main waste streams eg steel, inert materials, scrap Provide space for segregation project nominee general waste of waste where practicable 8 Operating control – Dispose surplus inert excavated Either: Trip tickets Throughout duration of the Nominated site material. Transport to the Western Section of project staff West Rail for reuse, if practicable; or Transport to other land formation sites in the and Yuen Long areas for reuse; or Transport to public filling areas or barging points.

EA00770/R26/1 May 2003 Appendix D - Page 8 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

4 Environmental Control Plan - Waste Management Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 9 Monitoring – check effectiveness of on-going mitigation In accordance with checklist Routine Environmental Weekly or following complaint PEC or measures described above and check waste requirements Monitoring Checklist nominee management facilities and general housekeeping. 10 Monitoring - carry out routine inspections of plant and fuel No excess oil visible on plant Routine Environmental Weekly or following complaint PEC or storage to minimise soil and water contamination No leakage of trays Monitoring Checklist nominee Valves closed 11 Maintain records of the quantities of wastes generated, Trip ticket system or similar Monthly Environmental Throughout project duration PEC recycled and disposed. Report and Site Records

EA00770/R26/1 May 2003 Appendix D - Page 9 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

5 Environmental Control Plan - Dangerous Goods and Chemicals Management Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation measure - Provide and maintain suitable In accordance with drawings Site Layout Drawings Throughout project duration Safety storage facilities for dangerous goods as appropriate submitted to Fire Services Manager Department 2 Mitigation measure - Provide and maintain suitable Provide drip trays with capacity or - Throughout project duration Supervision facilities for the bulk storage of other chemicals impervious sheeting with sand staff

3 Operating control - Establish and maintain an inventory Obtain from manufacturers and Inventory and MSDS Throughout project duration Safety and associated Material Safety Data Sheet for chemicals suppliers and maintain inventory records on site Manager to be used for construction activities on site. and file 4 Mitigation Measure - ensure dangerous goods/chemicals Visual inspection to verify that - Throughout project duration Supervision are properly stored. storage facilities conform to staff statutory requirements, manufacturers recommendations and the project Waste Management Plan requirements. 5 Mitigation Measure – ensure spill clean-up equipment are Visual inspection - Throughout project duration Supervision available for use. staff

6 Monitoring – Check effective implementation of mitigation In accordance with checklist Routine Environmental Weekly or following complaint PEC or measures requirements Monitoring Checklist nominee

EA00770/R26/1 May 2003 Appendix D - Page 10 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

6 Environmental Control Plan - General Housekeeping Item Mitigation, Operation Control, Monitoring and Inspection Method and Acceptance Criteria Verification Document Frequency / Duration Action By No. 1 Mitigation Measure - Erect and maintain awareness As per mitigation measure - Throughout duration of project Safety publications (eg posters) on site regarding the dangers of Manager allowing pests to breed. 2 Mitigating measure – Ensure that no open burning of Awareness training for workforce to Training records Throughout duration of project PEC / Safety debris or other matter takes place on site ensure legal requirements are Manager known 3 Mitigation measure – Standing water drained or treated As per mitigation measure - Throughout duration of project Supervision with larvicidal oil. Water containers removed or covered staff

4 Monitoring – check site for mosquito breeding areas, food As per checklist requirement Routine Environmental Weekly, or following complaint PEC or remnants etc. (stagnant standing water) Monitoring Checklist nominee

5 Monitoring - carry out routine monitoring of site and As per checklist requirement Routine Environmental Weekly, or following complaint PEC or perimeter to check tidiness and visual impact. Monitoring Checklist nominee

EA00770/R26/1 May 2003 Appendix D - Page 11 of 11 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX E - COMPLAINTS LOG

Date Complainant Details of the Complaint Action Status Remark Received No complaint was received in the month of September 2001 No complaint was received in the month of October 2001 No complaint was received in the month of November 2001 No complaint was received in the month of December 2001 No complaint was received in the month of January 2002 No complaint was received in the month of February 2002 No complaint was received in the month of March 2002 No complaint was received in the month of April 2002 No complaint was received in the month of May 2002 No complaint was received in the month of June 2002 No complaint was received in the month of July 2002 No complaint was received in the month of August 2002 No complaint was received in the month of September 2002 No complaint was received in the month of October 2002 No complaint was received in the month of November 2002 No complaint was received in the month of December 2002 No complaint was received in the month of January 2003 No complaint was received in the month of February 2003 No complaint was received in the month of March 2003 No complaint was received in the month of April 2003

EA00770/R26/1 May 2003 Appendix E - Page 1 of 1 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX F – MONITORING SCHEDULE FOR THE NEXT THREE MONTH

Air Monitoring Noise Monitoring Mon MA50 Tuen Mun Town MN48 Kam Wah Garden MA45 Holy Redeemer MN155 Assembly of God Paul Church MA65 San Hing Tsuen MN50 TuenMunTownPlaza

Tue MA50 Tuen Mun Town MA45 Holy Redeemer MA65 San Hing Tsuen

Wed MA155 Assembly of God MA42A Store Rm MA33 Q.E. Secondary MA15A Tin Yiu Est II MA10A Tin Yat Court Car MA123A Tin Chak Estate MA129A Tin Yuet Estate MA120 Lee Shau Kee Pri MA2A Q.E. Primary MA6 Kwok Yat Wai

Thur MA155 Assembly of God MN155 Assembly of God Paul Church MA33 Q.E. Secondary MN33 Q.E. Secondary School MA15A Tin Yiu Est II MN15A Tin Yiu Est II MA120 Lee Shau Kee Pri MN120 Lee Shau Kee Pri School MA123A Tin Chak Estate MN123A Tin Chak Estate Ancillary Building MA129A Tin Yuet Estate MN129A Tin Yuet Estate Ancillary Building MA10A Tin Yat Court Car MN10A Tin Yau Court Car Park MA6 Kwok Yat Wai MN6 Kwok Yat Wai College MA2A Q.E. Primary MA42A Store Rm Fri Italics indicate the collection of filter paper from HVAS

EA00770/R26/1 May 2003 Appendix F - Page 1 of 1 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX G - COMMENTS AND RESPONSE

Comments and responses on Monthly EM&A report – March 2003

ITEM DOCUMENT WEST RAIL CONTRACTORS RESPONSE NO. BY REFERENCE COMMENT IEC Appendix I Please check the validity of the calibration certificate for the The HVAS calibration kit S/N 1185 will no longer be used. HVAS HVAS calibration kit as it was last calibrated on February calibration kit S/N 517N which was last calibrated on 9 April 2003 will 2002. be used for HVAS calibration and the calibration certificate is included in Appendix I of this EM&A report. The next HVAS calibration will be carried out in July 2003.

EA00770/R26/1 May 2003 Appendix G - Page 1 of 1 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX H – LIST OF ENVIRONMENTAL LICENCE/PERMIT Construction Noise Permit (CNP) Register Date: 28 April 2003

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

Cancelled. 29 June EPD Local Control Office / Territory West; 7 CNP No. Construction Noise Permit (Percussive Piling). At Junction Mj7 North & EPD letter 1 2001 for six / Floor; Chinachem Tsuen Wan Plaza; 455- West – Tuen Mun 3 August PP-TW0025-01 months 457 Road; Tsuen Wan. 2001 27 July EPD Local Control Office / Territory West; 7 CNP No. Construction Noise Permit (23.00-07.00hrs). LRT crossings at Junction 27 June 2 2001 @ / Floor; Chinachem Tsuen Wan Plaza; 455- Mj7 North – Tuen Mun 2001 GW-TW0251-01 07.00 hrs. 457 Castle Peak Road; Tsuen Wan. 14 August EPD Local Control Office / Territory West; 7 CNP No. Construction Noise Permit (23.00-07.00hrs). LRT OHL pole relocation at 14 July 3 2001 @ / Floor; Chinachem Tsuen Wan Plaza; 455- Junction 6 East – Pui To Road, Tuen Mun 2001 GW-TW0280-01 07.00 hrs. 457 Castle Peak Road; Tsuen Wan. 31 July EPD Local Control Office / Territory West; 7 CNP No. Construction Noise Permit (23.00-07.00hrs). Road marking for traffic 23 July 4 2001 @ / Floor; Chinachem Tsuen Wan Plaza; 455- diversion at Junction L, Tin Shui Wai Reserve Zone. 2001 GW-TW0290-01 07.00 hrs. 457 Castle Peak Road; Tsuen Wan. Application refused CNP Application Construction Noise Permit (23.00-07.00hrs). Driving sheet piles and EPD Local Control Office / Territory West; 7 5 excavating pipe jacking receiving pit at side of LR track at Mj7 north Pui EPD letter N/A / Floor; Chinachem Tsuen Wan Plaza; 455- 29 June 2001 To Road; Tuen Mun. 30 July 457 Castle Peak Road; Tsuen Wan. 2001

CNP No. Construction Noise Permit (23.00-07.00hrs). LRT Plant crossing for 8 7 October EPD Local Control Office / Territory West; 7 6 access to hand dug caissons at north east corner of Tuen Mun Town September 2001 @ / Floor; Chinachem Tsuen Wan Plaza; 455- GW-TW0317-01 Park; Pui To Road; Tuen Mun. 2001 05.00 hrs. 457 Castle Peak Road; Tsuen Wan. CNP Application Construction Noise Permit (07.00-19.00hrs Gen. Hol. Inc. Sunday). Bored 28 EPD Local Control Office / Territory West; 7 10 August 2001. 30 August 7 Piling construction for retaining west bank of Nullah near Police Station; February / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 Pui To Road; Tuen Mun. 2002 457 Castle Peak Road; Tsuen Wan. GW-TW0368-01

EA00770/R26/1 May 2003 Appendix H - Page 1 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Application refused 13 August 2001 Construction Noise Permit (23.00-07.00hrs). Temporary relocation of LR EPD Local Control Office / Territory West; 7 8 track to allow construction of viaducts at east side of Tuen Mun Town EPD phone N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

Park (Junction 6 South – Tuen Mun Heung Sze Wui Road). call 7 Sept. 457 Castle Peak Road; Tsuen Wan. TW20010818-001 2001 CNP Application Application refused 17 August 2001. Construction Noise Permit (19.00-23.00hrs). Temporary relocation of LR EPD Local Control Office / Territory West; 7 9 track to allow construction of viaducts at east side of Tuen Mun Town EPD phone N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

Park (Junction 6 South – Tuen Mun Heung Sze Wui Road). call 31 Aug 457 Castle Peak Road; Tsuen Wan. TW20010839-001 2001 CNP Application 29 29 EPD Local Control Office / Territory West; 7 28 August 2001 Construction Noise Permit (01.00-05.00hrs). LRT OHL pole relocation at 10 September November / Floor; Chinachem Tsuen Wan Plaza; 455- Junction 6 West – Pui To Road, Tuen Mun 2001 2001 457 Castle Peak Road; Tsuen Wan. GW-TW0407-01 CNP Application 10 September 2001 Construction Noise Permit (01.00-05.00hrs). LRT OHL pole relocation to 21 11 EPD Local Control Office / Territory West; 7 11 allow construction of viaducts at east side of Tuen Mun Town Park at September December / Floor; Chinachem Tsuen Wan Plaza; 455- Junction 6 South – Tuen Mun Heung Sze Wui Road. 2001 2001 457 Castle Peak Road; Tsuen Wan. GW-TW0432-01 CNP Application Construction Noise Permit (19.00-07.00hrs on weekdays & 24hrs on EPD Local Control Office / Territory West; 7 10 September 2001 1 October 9 April 12 general holidays and Sundays). Pipe Jacking for utility diversion at / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 2002 Junction Mj8 – Pui To Road, Tuen Mun industrial area. 457 Castle Peak Road; Tsuen Wan. GW-TW0431-01 CNP Application Construction Noise Permit (two 36hour periods – end October & mid 13 October 23 EPD Local Control Office / Territory West; 7 12 September 2001 November 2001). Temporary relocation of LR track to allow construction 2001 for 13 December / Floor; Chinachem Tsuen Wan Plaza; 455- of viaducts at east side of Tuen Mun Town Park (Junction 6 South – Tuen Start 14 2001 457 Castle Peak Road; Tsuen Wan. Mun Heung Sze Wui Road). October GW-TW0441-01 CNP Application 11 October Construction Noise Permit (19.00-07.00hrs on weekdays & 24hrs on EPD Local Control Office / Territory West; 7 20 September 2001 2001 for 5 January 14 general holidays and Sundays). Pipe Jacking for utility diversion at road / Floor; Chinachem Tsuen Wan Plaza; 455- Start 19 2002 junction East of Kin On Stop on Pui To Road, Tuen Mun industrial area. 457 Castle Peak Road; Tsuen Wan. October GW-TW0449-01

EA00770/R26/1 May 2003 Appendix H - Page 2 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application 26 October Construction Noise Permit (23.00-07.00hrs). Drilling and grouting to 29 EPD Local Control Office / Territory West; 7 28 September 2001 2001 for 15 provide grout curtain for hand dug caissons at junction of Pui To Road December / Floor; Chinachem Tsuen Wan Plaza; 455- Start 29 and Tuen Mun Heung Sze Wui Road in Tuen Mun. 2001 457 Castle Peak Road; Tsuen Wan. October GW-TW0467-01 CNP Application Application refused 29 September 2001 Construction Noise Permit (19.00-21.00hrs on weekdays & 07.00- EPD Local Control Office / Territory West; 7 16 21.00hrs on general holidays and Sundays). Construction of CLP EPD letter N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

Substation at location S3 on Tin Fuk Road in Tin Shui Wai Phase 4 area. 12 October 457 Castle Peak Road; Tsuen Wan. TW0470-01 2001

CNP Application 12 November Construction Noise Permit (00.30-05.30hrs). LRT crossing - Emergency 15 EPD Local Control Office / Territory West; 7 16 October 2001 2001 for 17 Vehicle Access & construction plant access to Tuen Mun Town Park East December / Floor; Chinachem Tsuen Wan Plaza; 455- start 15 of San Fat Stop at Junction 6 West – Pui To Road, Tuen Mun 2001 457 Castle Peak Road; Tsuen Wan. November GW-TW0501-01 2001 CNP Application Application refused EPD Local Control Office / Territory West; 7 18 October 2001 Construction Noise Permit (19.00-21.00hrs). Concreting to bored piles at 18 EPD letter N/A / Floor; Chinachem Tsuen Wan Plaza; 455- Junction L; Tin Shui Road in Tin Shui Wai Reserve Zone. 29 October 457 Castle Peak Road; Tsuen Wan. TW0505-01 2001

CNP Application 19 November Construction Noise Permit (Weekdays 01.00-05.00hrs). LRT OHL pole 23 EPD Local Control Office / Territory West; 7 29 October 2001 2001 for 19 foundation construction and installation of OHL poles at Junction B; February / Floor; Chinachem Tsuen Wan Plaza; 455- start 26 Junction of Ping Ha Road and Tin Yiu Road in Tin Shui Wai Phase 4. 2002 457 Castle Peak Road; Tsuen Wan. November GW-TW0522-01 2001

CNP Application 30 Construction Noise Permit (Weekdays 19.00-07.00hrs). Installation of November 28 EPD Local Control Office / Territory West; 7 3 November 2001 Falsework above road and roundabout to enable construction of new LRT 2001 for 20 February / Floor; Chinachem Tsuen Wan Plaza; 455- viaduct at Junction L; junction of Tin Shui Road and Tin Wah Road in Tin start 01 2002 457 Castle Peak Road; Tsuen Wan. Shui Wai Reserve Zone. January GW-TW0532-01 2002

EA00770/R26/1 May 2003 Appendix H - Page 3 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application 06 Construction Noise Permit (Weekdays 01.00-05.00hrs). Light Rail December EPD Local Control Office / Territory West; 7 10 November 2001 permanent way alterations to facilitate Phase 4 extension of LRT system 2001 for 09 March 21 / Floor; Chinachem Tsuen Wan Plaza; 455- at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui start 09 2002 457 Castle Peak Road; Tsuen Wan. Wai. December GW-TW0566-01 2001 CNP Application Re- Construction Noise Permit (Weekdays 23.00-07.00hrs). Removal of submitted EPD Local Control Office / Territory West; 7 12 November 2001 existing footbridge and installation of temporary footbridge across LR 22 in two parts N/A / Floor; Chinachem Tsuen Wan Plaza; 455- tracks and Heung Sze Wui Road to facilitate construction of the LRT (18/12/01 & 457 Castle Peak Road; Tsuen Wan. viaducts at Tuen Mun town centre. TW0565-01 ?) CNP Application Application 12 November 2001 Construction Noise Permit (Weekdays 19.00-07.00hrs). Load-out of withdrawn EPD Local Control Office / Territory West; 7 23 prefabricated footbridge units at Hoi Wah Road (S1), Tuen Mun (for 6/12/01 at N/A / Floor; Chinachem Tsuen Wan Plaza; 455- installation across LR tracks and Heung Sze Wui Road). EPD 457 Castle Peak Road; Tsuen Wan. TW0564-01 request. CNP Application Construction Noise Permit (Weekdays 23.00-07.00hrs). Removal of part 21 Dec. 01 22 EPD Local Control Office / Territory West; 7 18 December 2001 of existing footbridge and installation of new temporary footbridge across 24 for start February / Floor; Chinachem Tsuen Wan Plaza; 455- LR tracks and Heung Sze Wui Road to facilitate construction of the LRT 2002 457 Castle Peak Road; Tsuen Wan. viaducts north of Tuen Mun . 21 Dec. 01 GW-TW0625-01 CNP Application Construction Noise Permit (07.00-21.00hrs Gen. Hol. Inc. Sunday & 11 Jan. 02 EPD Local Control Office / Territory West; 7 21 December 2001 weekdays 19.00-23.00hrs). Bored Piling construction for new retaining 15 July 25 for start / Floor; Chinachem Tsuen Wan Plaza; 455- wall along west bank of Nullah (near Police Station), Pui To Road; Tuen 2002 457 Castle Peak Road; Tsuen Wan. Mun. 16 Jan. 02 GW-TW0629-01

CNP Application Withdrawn 27 December 2001 Construction Noise Permit (weekdays 23.00-07.00hrs). Water main at EPD EPD Local Control Office / Territory West; 7 26 diversion across of Pui To Rd at Mj7, Tuen Mun (HK Police require road request N/A / Floor; Chinachem Tsuen Wan Plaza; 455- closure at night to minimise traffic disruption). 457 Castle Peak Road; Tsuen Wan. GW-TW0634-01 28 Jan 02

EA00770/R26/1 May 2003 Appendix H - Page 4 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application 14 Jan. 02 31 December 2001 Construction Noise Permit (weekdays 01.00-05.00 hrs.). Temporary 28 EPD Local Control Office / Territory West; 7 27 relocation of LR OHL to allow construction of viaducts at J6 east (west of for start February / Floor; Chinachem Tsuen Wan Plaza; 455-

Pui To Road Stop Tuen Mun. 28 Jan. 02 2002 457 Castle Peak Road; Tsuen Wan. GW-TW0639-01 CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Temporary 14 Jan. 02 EPD Local Control Office / Territory West; 7 31 December 2001 30 April 28 relocation of LR track to allow construction of viaducts at J6 east (west of for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Pui To Road Stop) Tuen Mun. 20 Mar. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0638-01 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Water main 28 Jan. 02 EPD Local Control Office / Territory West; 7 21 January 2002 20 March 29 diversion across of Pui To Rd at Mj7, Tuen Mun (HK Police require road for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 closure at night to minimise traffic disruption). RE-APPLICATION 29 Jan. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0023-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Temporary 11 Feb. 02 EPD Local Control Office / Territory West; 7 22 January 2002 17 May 30 relocation of LR track to allow construction of viaducts at J6 east (west of for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Pui To Road Stop) Tuen Mun. RE-APPLICATION. 18 Feb 02 457 Castle Peak Road; Tsuen Wan. GW-TW0027-01 CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Cut-out and 11 Feb. 02 EPD Local Control Office / Territory West; 7 23 January 2002 24 March 31 replace worn LR track (2 x 6mtrs) on Heung Sze Wui Road at J6 south for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 (north of Tuen Mun Town Centre Stop). 24 Feb 02 457 Castle Peak Road; Tsuen Wan. GW-TW0028-02 CNP Application Construction Noise Permit (Weekdays 23.00-07.00hrs). Removal of part 19 Feb. 02 of existing footbridge and installation of new temporary footbridge across for start EPD Local Control Office / Territory West; 7 31 January 2002 15 March 32 LR tracks and Heung Sze Wui Road north of Tuen Mun Town Centre 23 Feb 02 / Floor; Chinachem Tsuen Wan Plaza; 455- Stop. 2002 Withdrawn 457 Castle Peak Road; Tsuen Wan. GW-TW0042-02 PERMIT RENEWAL. 27 Feb 02

EA00770/R26/1 May 2003 Appendix H - Page 5 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 01.00-05.00hrs). Light Rail permanent way alterations to facilitate Phase 4 extension of LRT system 16 Mar. 02 EPD Local Control Office / Territory West; 7 18 February 2002 31 July 33 at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Wai. 2 Apr. 02 457 Castle Peak Road; Tsuen Wan. TW0067-02 PERMIT RENEWAL. CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Lifting steel 13 Mar. 02 EPD Local Control Office / Territory West; 7 18 February 2002 reinforcement bars over the LRT tracks and power lines into the hand dug 15 June 34 for start / Floor; Chinachem Tsuen Wan Plaza; 455- caissons at the junction of Heung Sze Wui Road and Pui To Road in Tuen 2002 457 Castle Peak Road; Tsuen Wan. Mun. 15 Mar 02 GW-TW0066-02 CNP Application Construction Noise Permit (Weekdays 23.00-07.00hrs). Removal of (during meeting) 27 Feb. 02 EPD Local Control Office / Territory West; 7 existing footbridge and installation of new temporary footbridge across LR 16 March 35 25 February 2002 for start / Floor; Chinachem Tsuen Wan Plaza; 455- tracks and Heung Sze Wui Road north of Tuen Mun Town Centre Stop. 2002 457 Castle Peak Road; Tsuen Wan. REPLACEMENT FOR PERMIT No. GW-TW0042-02. 27 Feb 02 GW-TW0075-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00 hrs.). Temporary 13 Mar. 02 EPD Local Control Office / Territory West; 7 01 March 2002 15 May 36 relocation of LR OHL to allow construction of viaducts at J6 east (west of for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Pui To Road Stop Tuen Mun. PERMIT RENEWAL 15 Mar 02 457 Castle Peak Road; Tsuen Wan. GW-TW0081-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs). To construct a 27 Mar. 02 EPD Local Control Office / Territory West; 7 07 March 2002 31 May 37 crossing over the Light Rail permanent way for construction plant access for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 at existing Tin Shui Wai Terminus (Stop 500). 2 Apr 02 457 Castle Peak Road; Tsuen Wan. GW-TW0089-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Water main 17 Apr. 02 EPD Local Control Office / Territory West; 7 27 March 2002 18 June 38 diversion across of Pui To Rd at Mj7, Tuen Mun (HK Police require road for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 closure at night to minimise traffic disruption). PERMIT RENEWAL 19 Apr 02 457 Castle Peak Road; Tsuen Wan. TW0116-02

EA00770/R26/1 May 2003 Appendix H - Page 6 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Footbridge 24 Apr. 02 EPD Local Control Office / Territory West; 7 9 April 2002 18 June 39 erection / partial removal at Junction L, TSW (HK Police require road for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 closure at night to minimise traffic disruption). 18 May 02 457 Castle Peak Road; Tsuen Wan. GW-TW0122-02 CNP Application Construction Noise Permit (Weekdays 01.00-05.00hrs). Light Rail 29 Apr. 02 EPD Local Control Office / Territory West; 7 15 April 2002 10 Sept. 40 permanent way alterations to facilitate grade separation viaduct for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 construction of LRT system at junction Mj7 on Pui To Road, Tuen Mun. 10 May 02 457 Castle Peak Road; Tsuen Wan. TW0141-02 CNP Application Construction Noise Permit (Weekdays 23.00-07.00hrs). Construction of 17 May 02 EPD Local Control Office / Territory West; 7 29 April 2002 30 Sept. 41 platform No. 6 at existing Tin Shui Wai Terminus – Stop 500, TSW – for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Phase 4. 1 June 02 457 Castle Peak Road; Tsuen Wan. TW0151-02 CNP Application Construction Noise Permit (Weekdays 19.00-23.00hrs & General holidays 22 May 02 EPD Local Control Office / Territory West; 7 30 April 2002 14 Nov. 42 07.00-19.00hrs). Utility diversions at Ng Lau Road, (LT1) to for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 facilitate grade separation viaduct construction work. 22 May 02 457 Castle Peak Road; Tsuen Wan. GW-TW0154-02 CNP Application Construction Noise Permit (07.00 to 19.00hrs on General holiday incl. 31 May 02 EPD Local Control Office / Territory West; 7 16 May 2002 Sundays & weekdays 19.00-23.00hrs). Foundation works to facilitate LRT 14 Dec. 43 for start / Floor; Chinachem Tsuen Wan Plaza; 455- grade separation viaduct construction at junction Mj7 West on Pui To 2002 457 Castle Peak Road; Tsuen Wan. Road, Tuen Mun. 15 June 02 GW-TW0171-02 CNP Application Construction Noise Permit (any day 23.00-07.00hrs). Footbridge erection / 3 Jun 02 for EPD Local Control Office / Territory West; 7 17 May 2002 18 July 44 partial removal at Junction L, TSW (HK Police require road closure at start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 night to reduce traffic disruption). PERMIT RENEWAL (GW-TW0122-02). 18 June 02 457 Castle Peak Road; Tsuen Wan. GW-TW0175-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00hrs). Erection of 14 Jun 02 EPD Local Control Office / Territory West; 7 18 May 2002 temporary working platforms over LRT at support columns to facilitate 30 Sept. 45 for start / Floor; Chinachem Tsuen Wan Plaza; 455- installation of viaduct beams at J6 West area (San Fat Stop to Heung Sze 2002 457 Castle Peak Road; Tsuen Wan. Wui Road) on Pui To Road, Tuen Mun. 1 July 02 GW-TW0176-02

EA00770/R26/1 May 2003 Appendix H - Page 7 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Lifting steel 3 June 02 EPD Local Control Office / Territory West; 7 21 May 2002 reinforcement bars over the LRT tracks and power lines into the hand dug 15 Aug 46 for start / Floor; Chinachem Tsuen Wan Plaza; 455- caissons at the junction of Heung Sze Wui Road and Pui To Road in Tuen 2002 457 Castle Peak Road; Tsuen Wan. Mun. PERMIT RENEWAL (GW-TW0066-02). 15 June 02 GW-TW0177-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). De-stressing of 12 June 02 EPD Local Control Office / Territory West; 7 22 May 2002 30 Sept. 47 temporary LRT track at J6 South area, north of Tuen Mun Town Centre for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 Stop, Heung Sze Wui Road, Tuen Mun. 24 June 02 457 Castle Peak Road; Tsuen Wan. GW-TW0178-02 CNP Application Construction Noise Permit (weekdays 19.00-07.00hrs). Temporary re- 17 June 02 EPD Local Control Office / Territory West; 7 30 May 2002 alignment of Pui To Road at Mj7 East to provide space for piling 15 July 48 for start / Floor; Chinachem Tsuen Wan Plaza; 455- operations in the centre reservation, Tuen Mun area. (Police road 2002 457 Castle Peak Road; Tsuen Wan. closure). 17 June 02 GW-TW0188-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Water main 21 June 02 EPD Local Control Office / Territory West; 7 10 June 2002 diversion across of Pui To Rd at Mj7, Tuen Mun (HK Police require road 18 Aug. 49 for start / Floor; Chinachem Tsuen Wan Plaza; 455- closure at night to minimise traffic disruption). PERMIT RENEWAL (GW- 2002 457 Castle Peak Road; Tsuen Wan. TW0116-02). 26 June 02 GW-TW0202-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Water main 21 June 02 EPD Local Control Office / Territory West; 7 10 June 2002 diversion across of Pui To Rd at Mj7, Tuen Mun (HK Police require road 18 Aug. 50 for start / Floor; Chinachem Tsuen Wan Plaza; 455- closure at night to minimise traffic disruption). PERMIT RENEWAL (GW- Permit No. 2002 457 Castle Peak Road; Tsuen Wan. TW0116-02). 26 June 02 GW-TW0202-02 CNP Application Construction Noise Permit [weekdays 19.00-23.00hrs & 07.00-21.00hrs general holiday (including Sunday)]. Deck construction along west bank of 27 June 02 10 June 2001 14 Jan. EPD Local Control Office / Territory West; 7 51 Nullah (near Police Station & Kin Fung Circuit) off Pui To Road; Tuen for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Mun. 2003 15 Jul. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0201-02 PERMIT RENEWAL (GW-TW0629-01). CNP Application Construction Noise Permit (Weekdays 19.00-21.00hrs & General holidays Refused EPD Local Control Office / Territory West; 7 14 June 2002 07.00-19.00hrs). Sewer diversion and site investigation at Tsing Lun see 52 N/A / Floor; Chinachem Tsuen Wan Plaza; 455- Road, Lam Tei (LT1) to facilitate grade separation viaduct construction Refused EPD letter 457 Castle Peak Road; Tsuen Wan. work. Ref: TW0208-02 9 Jul. 02

EA00770/R26/1 May 2003 Appendix H - Page 8 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (any day 23.00-07.00hrs). Footbridge erection / 10 July 02 EPD Local Control Office / Territory West; 7 18 June 2002 18 Aug. 53 partial removal at Junction L, TSW (HK Police require road closure at for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 night to reduce traffic disruption). PERMIT RENEWAL (GW-TW0175-02). 19 July 02 457 Castle Peak Road; Tsuen Wan. GW-TW0211-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 16 July 02 EPD Local Control Office / Territory West; 7 24 June 2002 19 Aug. 54 beams & pre-cast Planks over LRT at J6 West work area on Pui To Road, for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun. 5 Aug. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0215-02 CNP Application Construction Noise Permit (Weekdays 19.00-23.00hrs and 01.00-05.30 02 July 02 EPD Local Control Office / Territory West; 7 24 June 2002 hrs). Temporary relocation of the Light Rail permanent way to facilitate 31 Oct. 55 for start / Floor; Chinachem Tsuen Wan Plaza; 455- viaduct construction between Ho Tin Stop and junction Mj7 on Pui To 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. Road, Tuen Mun. 03 July 02 GW-TW0216-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00hrs). Erection of 19 July 02 EPD Local Control Office / Territory West; 7 25 June 2002 temporary working platforms over LRT at support columns to facilitate 15 Oct. 56 for start / Floor; Chinachem Tsuen Wan Plaza; 455- installation of viaduct beams at J6 South area (North of Town Centre Stop 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. to Pui To Road) on Heung Sze Wui Road, Tuen Mun. 15 Aug. 02 GW-TW0222-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00hrs). Erection of 19 July.02 EPD Local Control Office / Territory West; 7 25 June 2002 temporary working platforms over LRT at support columns to facilitate 30 Oct. 57 for start / Floor; Chinachem Tsuen Wan Plaza; 455- installation of viaduct beams at J6 East area (Pui To Stop to Heung Sze 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. Wui Road) on Pui To Road, Tuen Mun. 30 Aug. 02 GW-TW0221-02 CNP Application Construction Noise Permit (Weekdays 01.00-05.00hrs). Light Rail permanent way alterations to facilitate Phase 4 extension of LRT system 16 July 02 EPD Local Control Office / Territory West; 7 25 June 2002 31 Jan. 58 at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Wai. 2003 1 Aug. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0223-02 PERMIT RENEWAL (GW-TW0067-02). CNP Application Construction Noise Permit for Percussive Piling (08.00 to 09.00 hrs and 23 July 02 EPD Local Control Office / Territory West; 7 27 June 2002 12.30 to 14.00 hrs and 15.30 to 18.00 hrs). Sheet Piling with drop 23 Dec. 59 for start / Floor; Chinachem Tsuen Wan Plaza; 455- hammer for sewer diversion at Tsing Lun Road, Lam Tei (LT1) north Tuen 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. Mun. 24 Jul. 02 PP-TW0027-02

EA00770/R26/1 May 2003 Appendix H - Page 9 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct Withdrawn 3 July 2002 beams & pre-cast planks over LRT at J6 West work area on Pui To Road, EPD Local Control Office / Territory West; 7 60 for start N/A / Floor; Chinachem Tsuen Wan Plaza; 455- i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun. 3 Aug. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0234-02 PERMIT RENEWAL (GW-TW0215-02). CNP Application Construction Noise Permit (weekdays 19.00-07.00hrs). Temporary re- alignment of Pui To Road at Mj7 East to provide space for piling 19 July 02 EPD Local Control Office / Territory West; 7 3 July 2002 21 Aug. 61 operations in the centre reservation, Tuen Mun area. (Police road for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. closure). 2002 22 July 02 457 Castle Peak Road; Tsuen Wan. GW-TW0233-02 PERMIT RENEWAL (GW-TW0188-02). CNP Application Withdrawn 6 July 2002 Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct EPD Local Control Office / Territory West; 7 62 beams & pre-cast planks over LRT at J6 South work area on Heung Sze for start N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

Wui Road, i.e. between Town Centre Stop and Pui To Road, Tuen Mun. 10 Aug. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0239-02 CNP Application Withdrawn 6 July 2002 Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct EPD Local Control Office / Territory West; 7 63 beams & pre-cast planks over LRT at J6 East work area on Pui To Road, for start N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

i.e. between Pui To Stop and Heung Sze Wui Road, Tuen Mun. 30 Aug. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0238-02 CNP Application Construction Noise Permit (Weekdays 019.00-23.00hrs and 01.00 to EPD Local Control Office / Territory West; 7 16 July 2002 05.30 hrs). Light Rail permanent way alterations to facilitate Phase 4 15 Oct. 64 for start / Floor; Chinachem Tsuen Wan Plaza; 455- extension of LRT system at Junction Q (south end of Stop 500) in Tin 2002 457 Castle Peak Road; Tsuen Wan. Shui Wai. 15 Aug. 02 Ref: TW0254-02 CNP Application Construction Noise Permit (any day 23.00-07.00hrs). Southern footbridge EPD Local Control Office / Territory West; 7 24 July 2002 18 Sept. 65 erection at Junction L, TSW (HK Police require road closure at night to for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 reduce traffic disruption). PERMIT RENEWAL (GW-TW0211-02). 18 Aug. 02 457 Castle Peak Road; Tsuen Wan. TW0266-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct EPD Local Control Office / Territory West; 7 26 July 2002 beams & pre-cast Planks over LRT at J6 West work area on Pui To Road, 30 Sept. 66 for start / Floor; Chinachem Tsuen Wan Plaza; 455- i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun ( Five 2002 457 Castle Peak Road; Tsuen Wan. Week Trial Period). PERMIT RENEWAL (GW-TW0215-02). 26 Aug. 02 Ref: TW0269-02

EA00770/R26/1 May 2003 Appendix H - Page 10 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (07.00 to 19.00hrs on General holiday incl. EPD Local Control Office / Territory West; 7 17 August 2002 14 Jan. 67 Sundays & weekdays 19.00-23.00hrs). Foundation works to facilitate LRT for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2003 viaduct construction at junction Mj7 North on Pui To Road, Tuen Mun. 15 Sept. 02 457 Castle Peak Road; Tsuen Wan. TW0290-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 26 Aug. 02 EPD Local Control Office / Territory West; 7 17 August 2002 20 Dec. 68 beams & pre-cast planks over LRT at J6 South work area on Heung Sze for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 Wui Road, i.e. between Town Centre Stop and Pui To Road, Tuen Mun. 16 Sept. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0291-02 CNP Application Construction Noise Permit (weekdays 01.00-05.00 hrs.). Lifting steel 4 Sept. EPD Local Control Office / Territory West; 7 23 Aug. 2002 reinforcement bars over the LRT tracks and power lines into the hand dug for start 02for 69 / Floor; Chinachem Tsuen Wan Plaza; 455- caissons at the junction of Heung Sze Wui Road and Pui To Road in Tuen start15 15 Sept. 02 457 Castle Peak Road; Tsuen Wan. Mun. PERMIT RENEWAL (GW-TW0177-02). Sept. 02 Ref: TW0300-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 4 Sept. 02 EPD Local Control Office / Territory West; 7 30 August 2002 31 Jan. 70 beams & pre-cast planks over LRT at J6 East work area on Pui To Road, for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 i.e. between Pui To Stop and Heung Sze Wui Road, Tuen Mun. 2 Oct. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0305-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 9 Sept. 02 EPD Local Control Office / Territory West; 7 31 August 2002 beams & pre-cast Planks over LRT at J6 West work area on Pui To Road, 30 Nov. 71 for start / Floor; Chinachem Tsuen Wan Plaza; 455- i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun. PERMIT 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0269-02). 2 Oct. 02 GW-TW0307-02 CNP Application Construction Noise Permit (Weekdays 19.00-24.00hrs and 01.00 to 05.30 24 Sept.02 EPD Local Control Office / Territory West; 7 2 September 2002 29 Nov. 72 hrs). Light Rail permanent way alterations to facilitate the Reserve Zone for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 extension of LRT system at Junction I on Tin Shui Road in Tin Shui Wai. 30 Sept. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0308-02 CNP Application Construction Noise Permit (Weekdays 19.00-24.00hrs and 01.00 to 05.30 24 Sept. 02 EPD Local Control Office / Territory West; 7 2 September 2002 hrs). Light Rail permanent way alterations to facilitate the Reserve Zone 29 Nov. 73 for start / Floor; Chinachem Tsuen Wan Plaza; 455- extension of LRT system at Junction J (north end of Stop 500) on Tin 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. Shing Road in Tin Shui Wai. 30 Sept. 02 GW-TW0309-02

EA00770/R26/1 May 2003 Appendix H - Page 11 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Construction of 19 Sept.02 EPD Local Control Office / Territory West; 7 2 September 2002 15 Nov. 74 platform No. 6 at the existing TSW Terminus – Stop 500, Tin Shui Wai – for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 Phase 4. PERMIT RENEWAL (GW-TW0151-02). 1 Oct. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0312-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00hrs). Southern 18 Sept. 02 EPD Local Control Office / Territory West; 7 5 September 2002 18 Oct. 75 footbridge erection at Junction L, TSW (HK Police require road closure at for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2002 night to reduce traffic disruption). PERMIT RENEWAL (GW-TW0266-02). 19 Sept. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0317-02 CNP Application Construction Noise Permit (Friday 27/09/02 from 21.00 to 05.00hrs). Light 27 Sept.02 EPD Local Control Office / Territory West; 7 18 September 2002 Rail permanent way alterations at Junction B to facilitate Phase 4 for one 28 Sept. 76 / Floor; Chinachem Tsuen Wan Plaza; 455- extension of LRT system (at junction of Ping Ha Road and Tin Yiu Road) night 2002 Permit No. 457 Castle Peak Road; Tsuen Wan. in Tin Shui Wai. PERMIT RENEWAL (GW-TW0223-02). GW-TW0337-02 27 Sept. 02 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Light Rail 12 Oct. 02 EPD Local Control Office / Territory West; 7 19 September 2002 permanent way paved track installation at Junction G (junction of Tin 09 Jan. 77 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Shing Road & Tin Wu Road) to facilitate Phase 4 extension of LRT 2003 457 Castle Peak Road; Tsuen Wan. system in Tin Shui Wai. 17 Oct. 02 Ref: TW0343-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Light Rail 12 Oct. 02 EPD Local Control Office / Territory West; 7 19 September 2002 permanent way paved track installation at Junction A17 (junction of Tin 09 Jan. 78 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Shing Road & Tin Cheung Road) to facilitate Phase 4 extension of LRT 2003 457 Castle Peak Road; Tsuen Wan. system in Tin Shui Wai. 17 Oct. 02 Ref: TW0344-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Light Rail 16 Oct. 02 EPD Local Control Office / Territory West; 7 23 September 2002 permanent way paved track installation at Junction Q (junction of Tin 15 Dec. 79 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Shing Road & Tin Yan Road) to facilitate Phase 4 extension of LRT 2002 457 Castle Peak Road; Tsuen Wan. system in Tin Shui Wai. 16 Oct. 02 Ref: TW0350-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Light Rail 16 Oct. 02 EPD Local Control Office / Territory West; 7 23 September 2002 permanent way paved track installation at Junction A4 (junction of Tin 15 Dec. 80 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Shing Road & Tin Yau Court main entrance) to facilitate Phase 4 2002 457 Castle Peak Road; Tsuen Wan. extension of LRT system in Tin Shui Wai. 16 Oct. 02 Ref: TW0351-02

EA00770/R26/1 May 2003 Appendix H - Page 12 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 019.00-23.00hrs and 01.00 to 16 Oct. 02 EPD Local Control Office / Territory West; 7 24 September 2002 05.30 hrs). Light Rail permanent way alterations to facilitate Phase 4 15 Jan. 81 for start / Floor; Chinachem Tsuen Wan Plaza; 455- extension of LRT system at south end of Stop 500 (by junction Q) in Tin 2003 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0254-02). 16 Oct. 02 Ref: TW0357-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 11 Oct. 02 EPD Local Control Office / Territory West; 7 24 September 2002 19 Dec. 82 beams & pre-cast planks over LRT and main road at J6 Delta work area for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 at the junction of Pui To Road and Heung Sze Wui Road, Tuen Mun. 20 Oct. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0352-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Cable 22 Oct. 02 EPD Local Control Office / Territory West; 7 30 September 2002 31 Jan. 83 installation along existing LRT reserve between Yuen Long Terminus, for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 JunctionB Tin Shui Wai and Ho Tin Stop Tuen Mun. 28 Oct. 02 457 Castle Peak Road; Tsuen Wan. GW-TW0363-02 CNP Application 4 Nov. 02 26 October 2002 Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 31 EPD Local Control Office / Territory West; 7 84 pre-cast parapets over LRT and main road at J6 work area between San for start January / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Fat Stop, Pui To Stop & Town Centre Stop, Tuen Mun. 18 Nov. 02 2003 457 Castle Peak Road; Tsuen Wan. GW-TW0390-02 CNP Application Withdrawn 28 October 2002 Construction Noise Permit (weekdays 24.00-06.00hrs). Excavation of EPD Local Control Office / Territory West; 7 85 caisson in close proximity to LRT and main road at J6 work area at the for start N/A / Floor; Chinachem Tsuen Wan Plaza; 455-

junction of Pui To Road and Heung Sze Wui Road, Tuen Mun. 18 Nov. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0392-02 CNP Application Construction Noise Permit (Weekdays 19.00-24.00hrs and 01.00 to 05.30 18 Nov. 02 29 EPD Local Control Office / Territory West; 7 5 November 2002 hrs). Light Rail permanent way alterations to extend the LRT system into 86 for start January / Floor; Chinachem Tsuen Wan Plaza; 455- the Reserve Zone at Junction I on Tin Shui Road in Tin Shui Wai. Permit No. 2003 457 Castle Peak Road; Tsuen Wan. PERMIT RENEWAL (GW-TW0308-02). 30 Nov. 02 GW-TW0396-02 CNP Application Construction Noise Permit (Weekdays 19.00-24.00hrs and 01.00 to 05.30 18 Nov. 02 29 EPD Local Control Office / Territory West; 7 5 November 2002 hrs). Light Rail permanent way alterations to extend the LRT system into 87 for start January / Floor; Chinachem Tsuen Wan Plaza; 455- the Reserve Zone at Junction J (north of Stop 500) on Tin Shing Rd in Tin Permit No. 2003 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0309-02). 30 Nov. 02 GW-TW0395-02

EA00770/R26/1 May 2003 Appendix H - Page 13 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (07.00 to 19.00hrs on General holiday incl. 21 Nov. 02 14 EPD Local Control Office / Territory West; 7 13 November 2002 Sundays & weekdays 19.00-23.00hrs). Foundation works to facilitate LRT 88 for start February / Floor; Chinachem Tsuen Wan Plaza; 455- grade separation viaduct construction at junction Mj7 West on Pui To Permit No. 2003 457 Castle Peak Road; Tsuen Wan. Road, Tuen Mun. PERMIT RENEWAL (GW-TW0171-02). 15 Dec. 02 GW-TW0403-02 CNP Application 21 Nov. 02 13 November 2002 Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Erection of 24 EPD Local Control Office / Territory West; 7 89 Portal Frame to facilitate installation of viaduct at Mj7 junction on Pui To for start December / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Road, Tuen Mun. 27 Nov. 02 2002 457 Castle Peak Road; Tsuen Wan. GW-TW0404-02 CNP Application Construction Noise Permit (Weekdays 19.00 - 05.30 hrs). Construction 04 Dec. 02 EPD Local Control Office / Territory West; 7 13 November 2002 03 April 90 and installation of OHL masts & equipment for Light Rail interim diversion for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2003 at Tsing Lun Road, Lam Tei (LT1). 3 Dec. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0405-02 CNP Application Construction Noise Permit (Weekdays 19.00 - 05.30 hrs). Temporary 09 Dec.02 EPD Local Control Office / Territory West; 7 14 November 2002 31 March 91 diversion of the Light Rail permanent way to facilitate construction of the for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2003 new LRT viaduct at Tsing Lun Road, Lam Tei (LT1). 9 Dec. 02 457 Castle Peak Road; Tsuen Wan. Ref: TW0408-02 CNP Application 09 Dec. 02 14 November 2002 Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Light Rail 15 EPD Local Control Office / Territory West; 7 92 permanent way temporary paved track installation for interim diversion at for start February / Floor; Chinachem Tsuen Wan Plaza; 455-

Tsing Lun Road, Lam Tei (LT1). 16 Dec. 02 2003 457 Castle Peak Road; Tsuen Wan. Ref: TW0409-02 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of 11 Dec. 02 EPD Local Control Office / Territory West; 7 25 November 2002 working platforms, viaduct beams & pre-cast Planks over existing LRT 15 March 93 for start / Floor; Chinachem Tsuen Wan Plaza; 455- track at Mj7 West Industrial area on Pui To Road from the Police Station 2003 457 Castle Peak Road; Tsuen Wan. to Kin Tai Street, Tuen Mun. 16 Dec. 02 Ref: TW0419-02 CNP Application 17 Dec. 02 Construction Noise Permit (weekdays 19.00 to 07.00 hrs) Excavation of 31 EPD Local Control Office / Territory West; 7 25 November 2002 for 1 day 94 third caisson to support the new LRT viaduct at the junction of Heung Sze January / Floor; Chinachem Tsuen Wan Plaza; 455- trial from Wui Road and Pui To Road, Tuen Mun. 2003 457 Castle Peak Road; Tsuen Wan. Ref: TW0421-02 17 Dec. 02

EA00770/R26/1 May 2003 Appendix H - Page 14 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 23.00-06.00hrs). Erection of viaduct 04 Dec. 02 14 EPD Local Control Office / Territory West; 7 25 November 2002 beams & pre-cast Planks over LRT at J6 West work area on Pui To Road, 95 for start January / Floor; Chinachem Tsuen Wan Plaza; 455- i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun. PERMIT 2003 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0307-02). 5 Dec. 02 Ref: TW0420-02 CNP Application Construction Noise Permit (weekdays 23.00-06.00hrs). Erection of 11 Dec. 02 EPD Local Control Office / Territory West; 7 28 November 2002 working platforms, viaduct beams & pre-cast Planks alongside LRT track 22 March 96 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at Mj7 North Industrial area from Pui To Road to Kin Fung Circuit, Tuen 2003 457 Castle Peak Road; Tsuen Wan. Mun. 23 Dec. 02 Ref: TW0423-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 06.00 hrs). Erection of 06 Dec. 02 EPD Local Control Office / Territory West; 7 28 November 2002 01 March 97 viaduct beams & pre-cast planks over the existing LRT track at Mj7 for start / Floor; Chinachem Tsuen Wan Plaza; 455- 2003 junction on Pui To Road, Tuen Mun. 2 Jan. 03 457 Castle Peak Road; Tsuen Wan. Ref: TW0424-02 CNP Application Construction Noise Permit (Weekdays 23.00 - 05.30 hrs). Concreting of 20 Dec. 02 22 EPD Local Control Office / Territory West; 7 05 December 2002 OHL masts & back stays for Light Rail interim diversion to facilitate 98 for start February / Floor; Chinachem Tsuen Wan Plaza; 455- construction of the grade separation viaduct at Tsing Lun Road, Lam Tei Permit No. 2003 457 Castle Peak Road; Tsuen Wan. (LT1). 23 Dec. 02 GW-TW0434-02 CNP Application Construction Noise Permit (weekdays 23.00-07.00 hrs). To construct a 14 Jan.03 EPD Local Control Office / Territory West; 7 16 December 2002 30 April 99 crossing over the Light Rail permanent way for construction plant access for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 at Ng Lau Road, near Lam Tei Interchange (LT1 work site). 3 Feb. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0445-02 CNP Application Construction Noise Permit {Any day (incl. Sunday) 01.00 to 06.00 hrs & 23 Dec. 02 18 December 2002 weekdays 19.00 to 23.00 & general holidays (incl. Sunday) 07.00 to 23.00 22 EPD Local Control Office / Territory West; 7 100 hours}. Excavation of third caisson to support the new LRT viaduct at the for start February / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. junction of Heung Sze Wui Road and Pui To Road, Tuen Mun. Permit 23 Dec. 02 2003 457 Castle Peak Road; Tsuen Wan. GW-TW0450-02 Renewal (GW-TW0421-02). CNP Application Construction Noise Permit (Weekdays 019.hrs to 05.30 hrs). Light Rail 29 Jan. 03 EPD Local Control Office / Territory West; 7 11 January 2003 permanent way alterations to facilitate Phase 4 extension of LRT system 29 April 101 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at south end of Stop 500 (by junction Q) in Tin Shui Wai. Permit Renewal 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. (GW-TW0357-02). 30 Jan. 03 GW-TW0018-03

EA00770/R26/1 May 2003 Appendix H - Page 15 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.30 hrs). Light Rail 29 Jan. 03 EPD Local Control Office / Territory West; 7 11 January 2003 permanent way alterations to extend the LRT system into the Reserve 29 April 102 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at junction of Tin Wing Road and Tin Shui Road (Junction I) in Tin 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Shui Wai. Permit Renewal (GW-TW0396-02). 30 Jan. 03 GW-TW0016-03 CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.30 hrs). Light Rail 29 Jan. 03 EPD Local Control Office / Territory West; 7 11 January 2003 permanent way alterations to extend the LRT system into the Reserve 29 April 103 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at Junction J (north of Stop 500) on Tin Shing Rd in Tin Shui Wai. 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Permit Renewal (GW-TW0395-02). 30 Jan. 03 GW-TW0017-03 CNP Application Construction Noise Permit (Weekdays 01.00-05.00hrs). Light Rail permanent way alterations to facilitate Phase 4 extension of LRT system 27 Jan. 03 EPD Local Control Office / Territory West; 7 14 January 2003 03 August 104 at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Wai. 2003 04 Feb. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0031-03 Permit Renewal (GW-TW0223-02). CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Cable 23 Jan. 03 EPD Local Control Office / Territory West; 7 14 January 2003 installation along existing LRT reserve from Yuen Long Terminus to 31 March 105 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Junction B Tin Shui Wai and Ho Tin Stop Tuen Mun. PERMIT RENEWAL 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. (GW-TW0363-02) 04 Feb. 03 GW-TW0032-03 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 29 Jan. 03 EPD Local Control Office / Territory West; 7 17 January 2003 pre-cast parapets over LRT and main road at J6 work area between San 31 March 106 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Fat Stop, Pui To Stop & Town Centre Stop, Tuen Mun. PERMIT 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0390-02) 10 Feb. 03 GW-TW0039-03 CNP Application Construction Noise Permit (weekdays 19.00-23.00hrs & 07.00 to 19.00hrs 06 Feb. 03 EPD Local Control Office / Territory West; 7 18 January 2003 on General holiday incl. Sundays). Foundation works to facilitate LRT 15 April 107 for start / Floor; Chinachem Tsuen Wan Plaza; 455- viaduct construction at junction Mj7 North on Pui To Road, Tuen Mun. 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. PERMIT RENEWAL (GW-TW0290-02) 10 Feb. 03 GW-TW0037-03 CNP Application Construction Noise Permit (weekdays 19.00-23.00hrs & 07.00 to 19.00hrs 07 Feb. 03 EPD Local Control Office / Territory West; 7 18 January 2003 on General holiday incl. Sundays). Foundation works to facilitate LRT 15 March 108 for start / Floor; Chinachem Tsuen Wan Plaza; 455- grade separation viaduct construction at junction Mj7 West on Pui To 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Road, Tuen Mun. PERMIT RENEWAL (GW-TW0403-02). 15 Feb. 03 GW-TW0038-03

EA00770/R26/1 May 2003 Appendix H - Page 16 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of viaduct 06 Feb. 03 EPD Local Control Office / Territory West; 7 20 January 2003 beams & pre-cast planks over LRT and main road at J6 Delta work area 31 March 109 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at the junction of Pui To Road and Heung Sze Wui Road, Tuen Mun. 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. PERMIT RENEWAL (GW-TW0352-02). 20 Feb. 03 GW-TW0041-03 CNP Application Construction Noise Permit (weekdays 23.00-06.00hrs). Erection of viaduct 12 Feb. 03 EPD Local Control Office / Territory West; 7 20 January 2003 beams & pre-cast Planks over LRT at J6 West work area on Pui To Road, 31 March 110 for start / Floor; Chinachem Tsuen Wan Plaza; 455- i.e. between San Fat Stop and Heung Sze Wui Road, Tuen Mun. PERMIT 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0420-02). 13 Feb. 03 GW-TW0042-03 CNP Application Construction Noise Permit (Weekdays 23.00 - 05.30 hrs). Concreting of 12 Feb. 03 EPD Local Control Office / Territory West; 7 24 January 2003 OHL masts & back stays for Light Rail interim diversion to facilitate 30 April 111 for start / Floor; Chinachem Tsuen Wan Plaza; 455- construction of the grade separation viaduct at Tsing Lun Road, Lam Tei 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. (LT1). PERMIT RENEWAL (GW-TW0434-02). 23 Feb. 03 GW-TW0044-03 CNP Application Construction Noise Permit (Weekdays 23.00 - 06.00 hrs). Erection of 10 Feb. 03 EPD Local Control Office / Territory West; 7 27 January 2003 viaduct beams & pre-cast planks over the existing LRT track at Mj7 01 June 112 for start / Floor; Chinachem Tsuen Wan Plaza; 455- junction on Pui To Road, Tuen Mun. PERMIT RENEWAL (GW-TW0424- 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. 02). 2 Mar. 03 GW-TW0045-03 CNP Application Construction Noise Permit (weekdays 24.00-06.00hrs). Erection of 07 Mar. 03 EPD Local Control Office / Territory West; 7 14 February 2003 working platforms, viaduct beams & pre-cast Planks over existing LRT 15 May 113 for start / Floor; Chinachem Tsuen Wan Plaza; 455- track at Mj7 West Industrial area on Pui To Road from the Police Station 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. to Kin Tai Street, Tuen Mun. PERMIT RENEWAL (GW-TW0419-02). 17 Mar. 03 GW-TW0053-03 CNP Application Construction Noise Permit (weekdays 22.00-05.00hrs). OHL alterations & 28 Feb. 03 EPD Local Control Office / Territory West; 7 14 February 2003 16 June 114 new connections in the vicinity of junction Q to provide traction power to for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 the LRT Phase 4 extension in Tin Shui Wai. 17 Mar. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0054-03 CNP Application Construction Noise Permit (weekdays 23.00-06.00hrs). Erection of 14 Mar. 03 EPD Local Control Office / Territory West; 7 20 February 2003 working platforms, viaduct beams & pre-cast Planks alongside LRT track 30 April 115 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at Mj7 North Industrial area from Pui To Road to Kin Fung Circuit, Tuen 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Mun. PERMIT RENEWAL (GW-TW0423-02). 24 Mar. 03 GW-TW0062-03

EA00770/R26/1 May 2003 Appendix H - Page 17 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 19.00 - 05.30 hrs). Temporary 21 Mar. 03 EPD Local Control Office / Territory West; 7 26 February 2003 diversion of the Light Rail permanent way to facilitate construction of the 31 May 116 for start / Floor; Chinachem Tsuen Wan Plaza; 455- new LRT grade separation viaduct at Tsing Lun Road, Lam Tei (LT1). 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. PERMIT RENEWAL (GW-TW0408-02). 01 Apr. 03 GW-TW0074-03 CNP Application Construction Noise Permit (weekdays 22.00-05.00hrs). OHL alterations & 25 Mar. 03 EPD Local Control Office / Territory West; 7 26 February 2003 30 April 117 new connections in the vicinity of junction B to provide traction power to for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 the LRT Phase 4 extension in Tin Shui Wai. 01 Apr. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0073-03 CNP Application Construction Noise Permit (weekdays 22.00-05.00hrs). OHL alterations & 12 Mar. 03 EPD Local Control Office / Territory West; 7 26 February 2003 30 June 118 new connections in the vicinity of junction J to provide traction power to for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 the LRT Reserve Zone extension in Tin Shui Wai. 01 Apr. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0072-03 CNP Application Construction Noise Permit (Weekdays 22.00 - 05.30 hrs). Installation of 24 Mar. 03 EPD Local Control Office / Territory West; 7 07 March 2003 31 May 119 OHL masts & equipment for Light Rail interim diversion at Tsing Lun for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 Road, Lam Tei (LT1). PERMIT RENEWAL (GW-TW0405-02) 04 Apr. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0089-03 CNP Application Construction Noise Permit (Weekdays 23.00 - 07.00 hrs). Cable 24 Mar. 03 EPD Local Control Office / Territory West; 7 07 March 2003 installation along existing LRT reserve from Yuen Long Terminus to 30 June 120 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Junction B Tin Shui Wai and Ho Tin Stop Tuen Mun. PERMIT RENEWAL 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. (GW-TW0032-03) 01 Apr. 03 GW-TW0090-03 CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.00 hrs). Light Rail 09 Apr. 03 EPD Local Control Office / Territory West; 7 13 March 2003 permanent way alterations to facilitate Phase 4 extension of LRT system 09 May 121 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at Stop 500 south & west (by junction Q) in Tin Shui Wai. PERMIT 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0018-03). 09 Apr. 03 GW-TW0097-03 CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.00 hrs). Light Rail 09 Apr. 03 EPD Local Control Office / Territory West; 7 13 March 2003 permanent way alterations to extend the LRT system into the Reserve 09 May 122 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at junction of Tin Wing Road and Tin Shui Road (Junction I) in Tin 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0016-03). 09 Apr. 03 GW-TW0095-03

EA00770/R26/1 May 2003 Appendix H - Page 18 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.00 hrs). Light Rail 09 Apr. 03 EPD Local Control Office / Territory West; 7 13 March 2003 permanent way alterations to extend the LRT system into the Reserve 09 May 123 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at Junction J & north east part of Stop 500 on Tin Shing Rd in Tin 2003 Permit No. 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0017-03). 09 Apr. 03 GW-TW0096-03 CNP Application Construction Noise Permit (Weekdays 21.00-05.00hrs). Light Rail permanent way alterations & drainage to permit Phase 4 extension of LRT 09 Apr. 03 EPD Local Control Office / Territory West; 7 17 March 2003 09 May 124 at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. Wai. 2003 09 Apr. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0100-03 PERMIT RENEWAL (GW-TW0031-03). CNP Application Construction Noise Permit (Weekdays 21.00 hrs to 05.00 hrs). Excavation 10 Apr. 03 EPD Local Control Office / Territory West; 7 17 March 2003 30 April 125 of two new OHL pole foundations to extend the LRT system into the for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 Reserve Zone at Junction J West on Tin Wing Rd in Tin Shui Wai. 10 Apr. 03 457 Castle Peak Road; Tsuen Wan. GW-TW0099-03 CNP Application Construction Noise Permit (weekdays 22.00-05.00hrs). OHL alterations & 17 Apr. 03 EPD Local Control Office / Territory West; 7 24 March 2003 01 June 126 new connections in the vicinity of junction I to provide traction power to for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. 2003 the LRT Reserve Zone extension in Tin Shui Wai. 01 May 03 457 Castle Peak Road; Tsuen Wan. GW-TW0112-03 CNP Application Construction Noise Permit (Holidays 07.00-19.00hrs). Light Rail Refused EPD Local Control Office / Territory West; 7 3 April 2003 permanent way thermic welding of track at the new West Rail Station on see 127 N/A / Floor; Chinachem Tsuen Wan Plaza; 455- Tin Fuk Road in Tin Shui Wai (east of junction B) for the LRT Phase 4 EPD letter 457 Castle Peak Road; Tsuen Wan. extension. Ref: TW0125-03 14 April 03

CNP Application Construction Noise Permit (weekdays 22.00-05.00hrs). OHL alterations & 23 Apr. 03 EPD Local Control Office / Territory West; 7 07 April 2003 new connections in the vicinity of junction B to provide traction power to 30 June 128 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Permit No. the LRT Phase 4 extension in Tin Shui Wai. 2003 01 May 03 457 Castle Peak Road; Tsuen Wan. GW-TW0130-03 PERMIT RENEWAL (GW-TW0073-03). CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.00 hrs). Light Rail EPD Local Control Office / Territory West; 7 11 April 2003 permanent way alterations to extend the LRT system into the Reserve 129 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at Junction J & north east part of Stop 500 on Tin Shing Rd in Tin 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0096-03). 10 May 03 Ref: TW0135-03

EA00770/R26/1 May 2003 Appendix H - Page 19 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM ISSUE EXPIRY PERMIT No. PERMIT DESCRIPTION ISSUING OFFICE No. DATE DATE

CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 05.00 hrs). Light Rail EPD Local Control Office / Territory West; 7 11 April 2003 permanent way alterations to extend the LRT system into the Reserve 130 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Zone at junction of Tin Wing Road and Tin Shui Road (Junction I) in Tin 457 Castle Peak Road; Tsuen Wan. Shui Wai. PERMIT RENEWAL (GW-TW0095-03). 10 May 03 Ref: TW0134-03 CNP Application

11 April 2003 Construction Noise Permit (Weekdays 19.00 - 21.00 hrs & holidays 07.00 EPD Local Control Office / Territory West; 7 131 – 19.00 hrs). Foundation piling works for LRT grade separation viaduct at for start / Floor; Chinachem Tsuen Wan Plaza; 455- Submitted 15 Apr. LT1 (Lam Tei work area) Tuen Mun. 01 May 03 457 Castle Peak Road; Tsuen Wan. Ref: TW0140-03 CNP Application Construction Noise Permit (Weekdays 21.00 hrs to 05.00 hrs). Light Rail EPD Local Control Office / Territory West; 7 17 April 2003 permanent way alterations to facilitate Phase 4 extension of LRT system 132 for start / Floor; Chinachem Tsuen Wan Plaza; 455- at Stop 500 south & west (by junction Q) in Tin Shui Wai. PERMIT 457 Castle Peak Road; Tsuen Wan. RENEWAL (GW-TW0097-03). 10 May 03 Ref: TW0147-03 CNP Application Construction Noise Permit (Weekdays 21.00-05.00hrs). Light Rail permanent way alterations & drainage to permit Phase 4 extension of LRT 17 April 2003 EPD Local Control Office / Territory West; 7 133 at Junction B (junction of Ping Ha Road and Tin Yiu Road) in Tin Shui for start / Floor; Chinachem Tsuen Wan Plaza; 455- Wai. 10 May 03 457 Castle Peak Road; Tsuen Wan. Ref: TW0148-03 PERMIT RENEWAL (GW-TW0100-03). CNP Application Construction Noise Permit (Weekdays 19.00 hrs to 07.00 hrs). Light Rail EPD Local Control Office / Territory West; 7 23 April 2003 permanent way diamond track crossing at junction of Tin Wing Road and 134 for start / Floor; Chinachem Tsuen Wan Plaza; 455- Tin Shui Road (Junction I) in Tin Shui Wai. PERMIT SPECIAL FOR ONE 457 Castle Peak Road; Tsuen Wan. NIGHT (GW-TW0095-03). 02 May 03 Ref: TW0150-03 CNP Application

25 April 2003 Construction Noise Permit (Weekdays 21.00 hrs to 05.00 hrs). Excavation EPD Local Control Office / Territory West; 7 135 of four new OHL pole & back stay foundations north of TM Town Centre for start / Floor; Chinachem Tsuen Wan Plaza; 455-

Stop (J6 South) on Heung Sze Wui Road in Tuen Mun. 19 May 03 457 Castle Peak Road; Tsuen Wan. Ref: TW0155-03

EA00770/R26/1 May 2003 Appendix H - Page 20 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

Environmental Licence/Permit Register Date: 29th October 2002

ITEM PERMIT / LICENCE OR ISSUE EXPIRY PERMIT / REGISTRATION DESCRIPTION ISSUING OFFICE No. REGISTRATION No. DATE DATE

Permit No. Environmental Permit to Construct and Operate a Designated Project 4 October EPD; 28 / Floor; Southorn Centre; 130, 01 EP-041/2000/A N/A – Tin Shui Wai Phase 4 Rail Extension. 2002 Hennessy Road, Wan Chai. (KCRC) Permit No. Environmental Permit to Construct and Operate a Designated Project – Light Rail Transit (LRT) Extension in Tin Shui Wai Reserve Zone 4 October EPD; 28 / Floor; Southorn Centre; 130, 02 EP-042/2000/D N/A and Grade Separation of the LRT with Pui To Road and Tsing Lun 2002 Hennessy Road, Wan Chai. (KCRC) Road in Tuen Mun. Permit No. Further Environmental Permit to Construct a Designated Project – Light Rail Transit (LRT) Extension in Tin Shui Wai Reserve Zone and 23 March EPD; 28 / Floor; Southorn Centre; 130, 03 FEP-041/2001 N/A Grade Separation of the LRT with Pui To Road and Tsing Lun Road 2001 Hennessy Road, Wan Chai. (LCAL) in Tuen Mun. Permit No. Further Environmental Permit to Construct a Designated Project – Tin 23 March EPD; 28 / Floor; Southorn Centre; 130, 04 FEP-042/2001 N/A Shui Wai Phase 4 Rail Extension. 2001 Hennessy Road, Wan Chai. (LCAL)

Form NA Submission Notification under Section 3(1) of the Air Pollution Control rd EPD Local Control Office / Territory West; 7 3 May 05 Under APCO – EPD Ref: (Construction Dust) Regulations that construction works are N/A / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 No. TW20010406-001 commencing at the Tuen Mun site areas (Jn 6 , Mj7 & Mj8). 457 Castle Peak Road; Tsuen Wan. Notification under Section 3(1) of the Air Pollution Control Form NA Submission rd EPD Local Control Office / Territory West; 7 (Construction Dust) Regulations that construction works are 3 May 06 Under APCO – EPD Ref: N/A / Floor; Chinachem Tsuen Wan Plaza; 455- commencing at the Tin Shui Wai site areas (Phase 4 & Reserve 2001 No. TW20010407-001 457 Castle Peak Road; Tsuen Wan. Zone). Registration as Chemical Waste Producer under the Waste Disposal EPD Local Control Office / Territory West; 7 Registration No. 14 June 07 (Chemical Waste) (General) Regulation for Pui To Road, Tuen Mun N/A / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 5211-424-L2174-14 work areas. 457 Castle Peak Road; Tsuen Wan. Registration as Chemical Waste Producer under the Waste Disposal EPD Local Control Office / Territory West; 7 Registration No. 29 June 08 (Chemical Waste) (General) Regulation for Tin Shui Wai – Phase 4 & N/A / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 5298-515-L2174-16 Reserve Zone work areas. 457 Castle Peak Road; Tsuen Wan.

EA00770/R26/1 May 2003 Appendix H - Page 21 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

ITEM PERMIT / LICENCE OR ISSUE EXPIRY PERMIT / REGISTRATION DESCRIPTION ISSUING OFFICE No. REGISTRATION No. DATE DATE

Discharge Licence for the North Western Water Control Zone under EPD Local Control Office / Territory West; 7 Licence No. 29 June 30 June 09 Section 20 of the Water Pollution Control Ordinance. Applicable in / Floor; Chinachem Tsuen Wan Plaza; 455- 2001 2006 W7M17 - 1 the Tuen Mun work areas. 457 Castle Peak Road; Tsuen Wan.

Licence No. Discharge Licence for the Deep Bay Water Control Zone under EPD Local Control Office / Territory West; 7 10 Section 20 of the Water Pollution Control Ordinance. Applicable in 5 July 2001 31 July 2006 / Floor; Chinachem Tsuen Wan Plaza; 455- 1T279 / 1 the Tin Shui Wai – Phase 4 & Reserve Zone work areas. 457 Castle Peak Road; Tsuen Wan. Fire Services Department; Licensing & Licence No. Dangerous Goods Licence for the storage of Acetylene (18 cylinders 19 Sept. 11 Certification Command; NT North & West; x 48 litres – water capacity). Category 2 Class 3 Dangerous Goods. 2001 18628 Yuen Long Fire Station. Fire Services Department; Licensing & Licence No. Dangerous Goods Licence for the storage of Oxygen (18 cylinders x 19 Sept. 12 Certification Command; NT North & West; 47 litres – water capacity). Category 2 Class 1 Dangerous Goods. 2001 18629 Yuen Long Fire Station.

Form NA Submission Notification under Section 3(1) of the Air Pollution Control th EPD Local Control Office / Territory West; 7 11 April 13 Under APCO – EPD Ref: (Construction Dust) Regulations that construction works are N/A / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 No. TW20020416-001 commencing at the Lam Tei, Tuen Mun site (LT1). 457 Castle Peak Road; Tsuen Wan.

Discharge Licence for the North Western Water Control Zone under nd st EPD Local Control Office / Territory West; 7 Licence No. 22 May 31 May 14 Section 20 of the Water Pollution Control Ordinance. Applicable in / Floor; Chinachem Tsuen Wan Plaza; 455- 2002 2007 W7BI12-1 the Tuen Mun, Lam Tei (LT1) work area. 457 Castle Peak Road; Tsuen Wan.

EA00770/R26/1 May 2003 Appendix H - Page 22 of 22 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX I – EQUIPMENT CALIBRATION AND CERTIFICATION RECORD

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Store Room (Tuen Mun Fire Station) -MA 42A Date: 24-Jan-03 Time: 16:43

Sampler Model: GS2310 Serial no. : 1361 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Flow (corrected )  H P P Intercept (b): 0.027587 Pstd Ta Correction coeff. (r) 0.99935

1 Pa Tstd Standard pressure (mmHg) Pstd: 760.0 Qstd  P ( H P P  b) Standard temp. (K) Tstd: 292.00 m Pstd Ta Calibration pressure (mmHg) Pa: 758.5 Calibration temp. (K) Ta: 303.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 13.2 3.599 1.770 56.0 2 10.6 3.226 1.584 50.0 3 8.4 2.871 1.409 44.0 4 5.2 2.259 1.106 34.0 5 3.2 1.772 0.864 27.0

Correlation Coefficient : 0.9996

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 32.285x - 1.2734

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 1 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Tuen MunTown Plaza - MA50 Date: 24-Jan-03 Time: 14:30

Sampler Model: GS2310 Serial no. : 1777 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Intercept (b): 0.027587 Flow (corrected )  H P P Correction coeff. (r) 0.99935 Pstd Ta

Standard pressure (mmHg) Pstd: 760.0 1 Pa Tstd Standard temp. (K) Tstd: 292.00 Qstd  P ( H P P  b) m Pstd Ta Calibration pressure (mmHg) Pa: 765.8 Calibration temp. (K) Ta: 294.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 12.8 3.616 1.778 57.0 2 10.1 3.212 1.578 51.0 3 8.3 2.912 1.429 45.0 4 5.7 2.413 1.182 34.0 5 3.3 1.836 0.896 24.0

Correlation Coefficient : 0.9981

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

70.0

60.0

50.0

40.0

30.0 Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 38.477x - 10.604

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 2 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Assembly of God Paul Church Kindergarten (MA155) Date: 23-Jan-03 Time: 16:01

Sampler Model: GS2310 Serial no. : 1770 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Intercept (b): 0.027587 Pa Tstd Correction coeff. (r) 0.99935 Flow (corrected )  H P P Pstd Ta

Standard pressure (mmHg) Pstd: 764.0 Standard temp. (K) Tstd: 292.00 1 Pa Tstd Qstd  P ( H P P  b) Calibration pressure (mmHg) Pa: 758.5 m Pstd Ta Calibration temp. (K) Ta: 303.0

Sample no. Pressure Drop (H), inch Flow (corrected), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 13.0 3.563 1.751 58.0 2 10.9 3.262 1.603 50.0 3 8.8 2.931 1.439 42.0 4 5.7 2.359 1.155 31.0 5 3.5 1.849 0.902 18.0

Correlation Coefficient : 0.9986

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

70.0

60.0

50.0

40.0

30.0 Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 45.929x - 23.121 Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 3 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Holy Redeemer Catholic Church (MA45) Date: 24-Jan-03 Time: 13:44

Sampler Model: GS2310 Serial no. : 1703 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Flow (corrected )  H P P Intercept (b): 0.027587 Pstd Ta Correction coeff. (r) 0.99935

1 Pa Tstd Standard pressure (mmHg) Pstd: 760.0 Qstd  P ( H P P  b) Standard temp. (K) Tstd: 292.00 m Pstd Ta Calibration pressure (mmHg) Pa: 765.8 Calibration temp. (K) Ta: 294.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 13.4 3.699 1.819 57.0 2 10.5 3.275 1.609 46.0 3 8.8 2.998 1.472 39.0 4 5.3 2.327 1.139 28.0 5 3.2 1.808 0.882 18.0

Correlation Coefficient : 0.9952

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 40.465x - 18.409

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 4 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC203 Site Location: Queen Elizabeth Primary School (14/05) Date: 24-Jan-03 Time: 11:09 Transfer Std. type: Orifice, 1185

Standard Slope of orifice (m): 2.01844 Pressure (mmHg): 761 Standard Intercept of orifice (b): 0.027587 Temp. (K) 295 Correction coeff. Of orifice(r) 0.99935

Sample no. Pressure Drop Qstd / Qa Qstd I 1 8.6 2.949 1.448 47.0 2 7.5 2.754 1.351 43.0 3 6.2 2.504 1.227 37.0 4 4.4 2.110 1.032 28.0 5 2.9 1.713 0.835 20.0

Correlation coeff. of calibration : 0.99956

Plot of Linear Regression Actual Flow Rate ( Qstd ) against Flow Indication (I) at Queen EliZabeth Primary ( 14/05 )

50.0 45.0 40.0 35.0 30.0 25.0 20.0 15.0 Flow Indication ( I ) 10.0 5.0 0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 y = 44.595x - 17.55 Actual Flow Rate (m3/min.) Qstd

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 5 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 Site Location: Kwok Yat Wai College (14/06) Date: 24-Jan-03 Time: 17:50 Transfer Std. type: Orifice, 1185

Standard Slope of orifice (m): 2.01844 Pressure (mmHg): 761 Standard Intercept of orifice (b): 0.027587 Temp. (K) 294 Correction coeff. Of orifice(r) 0.99935

Sample no. Pressure Drop Qstd / Qa Qstd I 1 8.4 2.920 1.433 54.0 2 7.0 2.665 1.307 47.0 3 5.9 2.447 1.199 41.0 4 4.6 2.161 1.057 34.0 5 2.1 1.460 0.710 21.0

Correlation coeff. of calibration : 0.99472

Plot of Linear Regression Actual Flow Rate ( Qstd ) against Flow Indication (I) at Kwok Yat Wai College (14/06)

60.0

50.0

40.0

30.0

20.0 Flow Indication (I) Flow Indication 10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 Actual Flow Rate (m3/min.)Qstd y = 45.296x - 12.282

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 6 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: QE School Old Student's Association Secondary School (MA33) Date: 23-Jan-03 Time: 10:49

Sampler Model: GS2310 Serial no. : 1698 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Intercept (b): 0.027587 Flow (corrected )  H P P Correction coeff. (r) 0.99935 Pstd Ta

Standard pressure (mmHg) Pstd: 760.0 1 Pa Tstd Standard temp. (K) Tstd: 294.00 Qstd  P ( H P P  b) m Pstd Ta Calibration pressure (mmHg) Pa: 758.5 Calibration temp. (K) Ta: 303.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 6.9 2.602 1.276 43.0 2 5.7 2.365 1.158 40.0 3 4.6 2.125 1.039 36.0 4 3.2 1.772 0.864 28.0 5 2.1 1.436 0.698 23.0

Correlation Coefficient : 0.9960

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

50.0

45.0

40.0

35.0

30.0

25.0

20.0 Flow Indication (I)Flow 15.0

10.0

5.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 Actual flow rate (m3/min.) Qstd y = 36.056x - 2.3072

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 7 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: (HKFYG) Lee Shau Kee Primary School - MA120 Date: 23-Jan-03 Time: 15:09

Sampler Model: GS2310 Serial no. : 1713 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Intercept (b): 0.027587 Flow (corrected )  H P P Correction coeff. (r) 0.99935 Pstd Ta

Standard pressure (mmHg) Pstd: 760.0 1 Pa Tstd Qstd  P ( H P P  b) Standard temp. (K) Tstd: 294.00 m Pstd Ta Calibration pressure (mmHg) Pa: 758.5 Calibration temp. (K) Ta: 303.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 13.4 3.627 1.783 56.0 2 10.5 3.210 1.577 48.0 3 8.3 2.854 1.400 42.0 4 5.6 2.344 1.148 33.0 5 3.2 1.772 0.864 24.0

Correlation Coefficient : 0.9994

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 34.771x - 6.4969

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 8 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Tin Yiu Estate II (MA15A) Date: 23-Jan-03 Time: 11:44

Sampler Model: GS2310 Serial no. : 1296 Calibrator Orifice no.: 1185 Pa Tstd  P P Slope (m): 2.01844 Flow (corrected ) H Pstd Ta Intercept (b): 0.027587 Correction coeff. (r) 0.99935 1 Pa Tstd Qstd  P ( H P P  b) Standard pressure (mmHg) Pstd: 766.0 m Pstd Ta Standard temp. (K) Tstd: 294.50 Calibration pressure (mmHg) Pa: 758.5 Calibration temp. (K) Ta: 303.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 12.8 3.531 1.735 57.0 2 10.6 3.213 1.578 50.0 3 8.6 2.894 1.420 43.0 4 5.7 2.356 1.154 34.0 5 3.4 1.820 0.888 23.0

Correlation Coefficient : 0.9989

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I)Flow 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 1.800 2.000 Actual flow rate (m3/min.) Qstd y = 39.434x - 12.033

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 9 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Tin Yau Court - MA10A Date: 23-Jan-03 Time: 14:20

Sampler Model: GS2310 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Pa Tstd Intercept (b): 0.027587 Flow (corrected )  H P P Correction coeff. (r) 0.99935 Pstd Ta

Standard pressure (mmHg) Pstd: 760.0 1 Pa Tstd Standard temp. (K) Tstd: 294.00 Qstd  P ( H P P  b) m Pstd Ta Calibration pressure (mmHg) Pa: 760.6 Calibration temp. (K) Ta: 297.0

Sample no. Pressure Drop (H), inch Flow (corrcted), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 8.7 2.956 1.451 51.0 2 7.5 2.744 1.346 44.0 3 5.8 2.413 1.182 39.0 4 4.1 2.029 0.992 30.0 5 2.6 1.616 0.787 23.0

Correlation Coefficient : 0.9951 Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I) 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 Actual flow rate (m3/min.) Qstd y = 41.269x - 10.117

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 10 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC 230 Site Location: San Hing Tsuen Date: 28-01-2003 Time: 17:55 Transfer Std. type: Orifice, 1185

Standard Slope of orifice (m): 2.01844 Pressure (mmHg): 763.58 Standard Intercept of orifice (b): 0.027587 Temp. (K) 290 Correction coeff. Of orifice(r) 0.99935

Sample no. Pressure Drop Qstd / Qa Qstd I 1 6.7 2.630 1.289 46.0 2 6.1 2.510 1.230 40.0 3 5.3 2.339 1.145 33.0 4 4.4 2.131 1.042 27.0 5 3.6 1.928 0.941 22.0

corelation coeff. of calibration : 0.99037

Plot of Linear Regression Actual Flow Rate ( Qstd ) against Flow Indication (I) at San Hing Tsuen 50 45 40 35 30

I 25 20 15 10 5 0 0 0.2 0.4 0.6 0.8 1 1.2 1.4 Qstd y = 66.817x - 44.04

Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 11 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Tin Chak Estate - MA123A Date: 24-Jan-03 Time: 1:35

Sampler Model: GS2310 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Intercept (b): 0.027587 Pa Tstd Correction coeff. (r) 0.99935 Flow (corrected )  H P P Pstd Ta

Standard pressure (mmHg) Pstd: 762.0 Standard temp. (K) Tstd: 293.80 1 Pa Tstd Qstd  P ( H P P  b) Calibration pressure (mmHg) Pa: 760.6 m Pstd Ta Calibration temp. (K) Ta: 296.0

Sample no. Pressure Drop (H), inch Flow (corrected), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 7.9 2.818 1.382 49.0 2 6.5 2.556 1.253 45.0 3 5.4 2.329 1.140 41.0 4 4.0 2.005 0.980 35.0 5 2.5 1.585 0.772 27.0

Correlation Coefficient : 0.9992

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I) 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 1.600 Actual flow rate (m3/min.) Qstd y = 36.295x - 0.7158 Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 12 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

High Volume Air Sampler Calibration Worksheet

Project Title: CC230 - KCRC LRT Civil, Permanent Way, Traction Power and Overhead Line Monitoring Location: Tin Yuet Estate - MA129A Date: 23-Jan-03 Time: 10:02

Sampler Model: GS2310 Calibrator Orifice no.: 1185 Slope (m): 2.01844 Intercept (b): 0.027587 Pa Tstd Correction coeff. (r) 0.99935 Flow (corrected )  H P P Pstd Ta

Standard pressure (mmHg) Pstd: 764.0 Standard temp. (K) Tstd: 291.20 1 Pa Tstd Qstd  P ( H P P  b) Calibration pressure (mmHg) Pa: 758.3 m Pstd Ta Calibration temp. (K) Ta: 296.0

Sample no. Pressure Drop (H), inch Flow (corrected), m3/min Actual flow rate (Qstd), m3/min Flow indication (I), arbitrary 1 7.0 2.645 1.297 55.0 2 6.1 2.469 1.210 52.0 3 4.7 2.167 1.060 48.0 4 3.4 1.843 0.900 41.0 5 2.2 1.483 0.721 35.0

Correlation Coefficient : 0.9976

Plot of Linear Regression Actual flow rate (Qstd) against Flow indication (I)

60.0

50.0

40.0

30.0

Flow Indication (I) 20.0

10.0

0.0 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 Actual flow rate (m3/min.) Qstd y = 35.018x + 9.8753 Remark Qstd Range 1.1 - 1.7 1HPa = 0.750062 mmHg

EA00770/R26/1 May 2003 Appendix I - Page 13 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix I - Page 14 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix I - Page 15 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix I - Page 16 of 16 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX J – SITE INSPECTION CHECKLIST

EM&A MONTHLY REPORT FOR APRIL 2003

KCRC / IEC ENVIRONMENTAL SITE INSPECTION / AUDIT DEFICIENCY REGISTER

Site Inspection / CA / Ref. No. of Date Close- Audit Proposed Corrective / Action Follow-up Inspected by Observed Brief Description of Deficiency Spec. Ref. Reply out Preventive Action By Date Agreed Date Location Deficiency Issued Date (Yes / No) 21st Tuen J. Chan, (IEC) Remark Following up the previous 28th We ensure the wheel 31st Yes 23rd Mar Mun audit, mud trail was observed Mar washing facility to use Mar Apr H. Leung, Roy No.2 2003 at Public road near a site exit 2003 during vehicle to leave 2003 2003 Wong, V. Tong at MJ8. The contractor had on site. (KCRC) washed the public road W.C. Lam immediately. They were (LCAL) reminded to enforce the use of wheel washing facility. 21st Tin J. Chan, (IEC) Remark The Contractor was reminded 28th The open stockpile will 31st Yes 23rd Mar Shui to cover the open stockpiles at Mar be covered with Mar Apr H. Leung, Roy No.4 2003 Wai stop 550. 2003 tarpaulin. 2003 2003 Wong, V. Tong (KCRC) W.C. Lam (LCAL) 21st Tin J. Chan, (IEC) Remark The CC-230 contractor 28th The spoiled stockpile is 31st Yes 23rd Mar Shui indicated that the spoiled Mar belong to CC-203 Mar Apr H. Leung, Roy No.5 2003 Wai stockpile at area near TSW 2003 2003 2003 Wong, V. Tong Leighton site office belong to (KCRC) other contractors. The W.C. Lam contractors was requested to (LCAL) clarify the land possession status.

EA00770/R26/1 May 2003 Appendix J - Page 1 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

KCRC / IEC ENVIRONMENTAL SITE INSPECTION / AUDIT DEFICIENCY REGISTER

Site Inspection / CA / Ref. No. of Date Close- Audit Proposed Corrective / Action Follow-up Inspected by Observed Brief Description of Deficiency Spec. Ref. Reply out Preventive Action By Date Agreed Date Location Deficiency Issued Date (Yes / No) 21st Tin J. Chan, (IEC) Remark The CC-230 contractor 28th The earthwork 31st Yes 23rd Mar Shui indicated that the site exit at Mar contractor and LCAL Mar Apr H. Leung, Roy No.6 2003 Wai stop 530 was shared with 2003 will be kept the site exit 2003 2003 Wong, V. Tong other earthwork contractor. clean. (KCRC) The CC-230 contractor was W.C. Lam reminded to liaise with the (LCAL) earthwork contractor in order to keep the exit free from mud trail. 23rd Tuen Terence Kong. Remark Some crushed materials & 25th The crushed materials 30th Apr Mun (IEC) chemicals were observed at Apr & chemicals will be Apr No.1 2003 the exit of MJ7. The Contractor 2003 removed on MJ7 exit. 2003 H. Leung, Roy was reminded to remove the EP & wheel washing Wong, (KCRC) materials & chemicals and facilities will be W.C. Lam placed it in appropriate area. provided exit of MJ7 & (LCAL) In addition, EP & wheel Mj8. washing facilities should be provided at the MJ7 & MJ8. For MJ8, mud trail was observed at the exit behind MJ8 and No water spraying was provided. Further Improvement is required by the contractor.

EA00770/R26/1 May 2003 Appendix J - Page 2 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

KCRC / IEC ENVIRONMENTAL SITE INSPECTION / AUDIT DEFICIENCY REGISTER

Site Inspection / CA / Ref. No. of Date Close- Audit Proposed Corrective / Action Follow-up Inspected by Observed Brief Description of Deficiency Spec. Ref. Reply out Preventive Action By Date Agreed Date Location Deficiency Issued Date (Yes / No) 23rd Lam Terence Kong. Remark Two new exits were formed at 25th EP & wheel washing 30th Apr Tei (IEC) LT1 North due to the Apr will be provided at two Apr No.2 2003 estabishment od piling works. 2003 exits on LT1 2003 H. Leung, Roy The entrance was paved and Wong, (KCRC) the contractor was reminded to W.C. Lam maintain the wheel washing (LCAL) facilities. In addition, EP was required to post at the vehicle exits 23rd Lam Terence Kong. Remark Minor exposed earth slope 25th The minor exposed 30th Apr Tei (IEC) observed at the northern side Apr earth slope is belong to Apr No.3 2003 of LT 1, the contractor was 2003 CC-212 contractor. 2003 H. Leung, Roy reminded to cover the slope. Wong, (KCRC) W.C. Lam (LCAL) 23rd Tin Shui Terence Kong. Remark Stockpiles were observed at 25th An stockpiles will be 30th Apr Wai (IEC) stop 500 & stop 550(only Apr covered with tarpaulin Apr No.4 2003 covered partially). The 2003 at Stop 500 & 550. 2003 H. Leung, Roy contractor was reminded to Water sparing will be Wong, (KCRC) cover the stockpiles fully when carried out more W.C. Lam not in use. Part of the area at frequently. (LCAL) stop 500 was dry. The contractor was reminded to provide water spraying more frequency.

EA00770/R26/1 May 2003 Appendix J - Page 3 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EM&A MONTHLY REPORT FOR APRIL 2003

CET ENVIRONMENTAL SITE INSPECTION / AUDIT DEFICIENCY REGISTER

Site Inspection / CA / Ref. No. of Date Close- Audit Inspected Brief Description of Proposed Corrective / Action Follow-up Observed Spec. Ref. Reply out by Deficiencies Preventive Action Date Agreed Date Location Deficiencies Issued Date (Yes / No) 27th All Michael NA Concrete drilling near Tin Item No.9 of Air 28th Watering will be carried 31st Yes 3rd Mar. Areas Yiu Est without watering Pollution Control Mar. out during concrete drilling Mar. Apr. 2003 Section in 2003 2003 2003 CC230 EMIS 27th All Michael NA Waste skips at site near stop Item No.3 of 28nd The construction waste will 31th Yes 3rd Mar. Areas 500 gate, should remove waste Mar. be removed on site Mar. Apr. 2003 more frequency management 2003 2003 2003 Section in CC230 EMIS 3rd All Michael NA No observed deficiencies N/A N/A N/A N/A NA NA Apr. Areas 2003 10th All Michael NA Concrete breaking opposite CC230 ECP 11th Watering will be carried 14th Yes 17th Apr. Areas Yiu Fu House no watering Apr. out during concrete Apr. Apr. 2003 2003 breaking 2003 2003 10th All Michael NA waste skips should clean Item No.3 of 11th The construction waste will 14th Yes 17th Apr. Areas frequency during full near waste Apr. be removed on site Apr. Apr. 2003 the gate "Stop 500" at site. management 2003 2003 2003 Section in CC230 EMIS 17th All Michael NA Drilling at LRT station near Item No.9 of Air 22nd Watering will be carried 23rd Yes 24th Apr. Areas Tin Yiu Est II no watering Pollution Control Apr. out during drilling Apr. Apr. 2003 Section in 2003 2003 2003 CC230 EMIS

EA00770/R26/1 May 2003 Appendix J - Page 4 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

CET ENVIRONMENTAL SITE INSPECTION / AUDIT DEFICIENCY REGISTER

Site Inspection / CA / Ref. No. of Date Close- Audit Inspected Brief Description of Proposed Corrective / Action Follow-up Observed Spec. Ref. Reply out by Deficiencies Preventive Action Date Agreed Date Location Deficiencies Issued Date (Yes / No) 24th All Michael NA Haul Road watering should Item No.7 of Air 25th Watering will be carried 28th Apr. Areas applies more frequency at Pollution Control Apr. out more frequency Apr. 2003 Tin Fuk Rd. Section in 2003 2003 CC230 EMIS

EA00770/R26/1 May 2003 Appendix J - Page 5 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix J - Page 6 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix J - Page 7 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix J - Page 8 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix J - Page 9 of 9 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX K SUMMARY OF NOTIFICATION OF SUMMON AND STATUS

Summon Ref. Regulations Description of Offence Date Magistracy Date of Time of Outcome of Fine if Affected Issued Hearing Hearing Hearing Any No Notification of Summons were received in September 2001. No Notification of Summons were received in October 2001. No Notification of Summons were received in November 2001. No Notification of Summons were received in December 2001. No Notification of Summons were received in January 2002. No Notification of Summons were received in February 2002. No Notification of Summons were received in March 2002. No Notification of Summons were received in April 2002. No Notification of Summons were received in May 2002. FLS5381/2002 NCO Concreting of a bored pile at June Magistrates 23 July 09:30 hrs Leighton HK$ Tin Shui Road near Tin Wah 2002 Court at 2002 pleaded guilty 10,000 Estate after 19:00 without CNP Fanling with mitigation on 29 January 2002 FLS5382/2002 NCO Hammering of the casing of a June Magistrates 23 July 09:30 hrs Leighton HK$ bored pile at Tin Shui Road 2002 Court at 2002 pleaded guilty 10,000 near Tin Wah Estate after 19:00 Fanling with mitigation without CNP on 29 January 2002 No Notification of Summons was received in July 2002. No Notification of Summons was received in August 2002. No Notification of Summons was received in September 2002. No Notification of Summons was received in October 2002. No Notification of Summons was received in November 2002. No Notification of Summons was received in December 2002. No Notification of Summons was received in January 2003. No Notification of Summons was received in February 2003.

EA00770/R26/1 May 2003 Appendix K - Page 1 of 2 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

Summon Ref. Regulations Description of Offence Date Magistracy Date of Time of Outcome of Fine if Affected Issued Hearing Hearing Hearing Any No Notification of Summons was received in March 2003. No Notification of Summons was received in April 2003.

EA00770/R26/1 May 2003 Appendix K - Page 2 of 2 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX L CONSTRUCTION PROGRAMME FOR THE NEXT THREE MONTHS

EA00770/R26/1 May 2003 Appendix L - Page 1 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix L - Page 2 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix L - Page 3 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix L - Page 4 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix L - Page 5 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report - April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

EA00770/R26/1 May 2003 Appendix L - Page 6 of 6 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX M NOE LOG

NoE No. NoE Issue Date Date of Monitoring Sampling Location Description

No NoE was received in September 2001 No NoE was received in October 2001 No NoE was received in November 2001 No NoE was received in December 2001 No NoE was received in January 2002 No NoE was received in February 2002 NE-03852-CC-230-NSR-MN48-00 21-Mar-02 25-Feb-02 MN48 Limit Level Exceedance of Noise / / 2-Apr-02 MN155 Limit Level Exceedance of Noise NE-03927-CC-230-NSR-MN48-00 11-Apr-02 25-Mar-02 MN48 Limit Level Exceedance of Noise NE-04106-CC-230-NSR-MN48-00 / 22-Apr-02 MN48 Limit Level Exceedance of Noise

No NoE was received in June 2002 No NoE was received in July 2002 No NoE was received in August 2002 No NoE was received in July 2002 No NoE was received in August 2002 No NoE was received in September 2002 No NoE was received in October 2002 No NoE was received in November 2002 No NoE was received in December 2002 No NoE was received in January 2003 No NoE was received in February 2003 No NoE was received in March 2003 No NoE was received in April 2003

EA00770/R26/1 May 2003 Appendix M - Page 1 of 1 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line

APPENDIX N1 – STANDARD AND GUIDANCE FOR ARCHAEOLOGICAL WATCHING BRIEF

STANDARD AND GUIDANCE FOR AN ARCHAEOLOGICAL WATCHING BRIEF

STANDARD

THE STANDARD

An archaeological watching brief will record the archaeological resource during development within a specified area using appropriate methods and practices. These will satisfy the stated aims of the project, and comply with the Code of conduct, Code of approved practice for the regulation of contractual arrangements in field archaeology, and other relevant by- laws of the IFA.

DEFINITION OF AN ARCHAEOLOGICAL WATCHING BRIEF

The definition of an archaeological watching brief is a formal programme of observation and investigation conducted during any operation carried out for non-archaeological reasons. This will be within a specified area or site on land, inter-tidal zone or underwater, where there is a possibility that archaeological deposits may be disturbed or destroyed. The programme will result in the preparation of a report and ordered archive.

This definition and Standard do not cover chance observations which should lead to an appropriate archaeological project being designed and implemented, nor do they apply to monitoring for preservation of remains in situ.

Purpose of Watching Brief

The purpose of a watching brief is:

S to allow, within the resources available, the preservation by record of archaeological deposits, the presence and nature of which could not be established (or established with sufficient accuracy) in advance of development or other potentially disruptive works

S to provider an opportunity, if needed, for the watching archaeologist to signal to all interested parties, before the destruction of the material in question, that an archaeological find ahs been made for which the resources allocated to the watching brief itself are not sufficient to support treatment to a satisfactory and proper standard

A watching brief is not intended to reduce the requirement for excavation or preservation of known or inferred deposits, and it is intended to guide, no replace, any requirement for contingent excavation or preservation of possible deposits.

The objective of a watching brief is to establish and make available information about the archaeological resource existing on a site.

EA00770/R26/1 May 2003 Appendix N1 - Page 1 of 1 C:\LightRail\App_Apr03.doc KCRC Contract No. CC230 Monthly EM&A Report – April 2003 Light Rail Extension – Civil, Permanent Way, Traction Power and Overhead Line APPENDIX N2 – ARCHAEOLOGICAL MONITORING LOCATIONS

EA00770/R26/1 May 2003 Appendix N2 - Page 1 of 1 C:\LightRail\App_Apr03.doc