Environmental Assessment Report

Initial Environmental Examination Project Number: 42252 August 2010

BHU: Rural Renewable Energy Development Project

Prepared by the Department of Energy, Government of for the Asian Development Bank (ADB).

The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Royal Government of Bhutan

Asian Development Bank

Technical Assistance

Project Number: 7318-BHU Preparing the Rural Renewable Energy Development Project

INITIAL ENVIRONMENTAL EXAMINATION (DRAFT)

MONGAR ACCELERATED RURAL ELECTRIFICATION SUBPROJECT

MARCH 2010

1

Contents I. EXECUTIVE SUMMARY ...... 8

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...... 13

A. Policies relevant to the project...... 13

B. Environmental Clearance Procedures...... 15

III. DESCRIPTION OF THE PROJECT...... 17

A. Project description ...... 17

B. Project budget and implementation...... 20

IV. DESCRIPTION OF THE ENVIRONMENT...... 24

A. Physical Resources...... 24

B. Ecological Resources ...... 26

C. Economic Development ...... 28

D. Social and Cultural Resources...... 29

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES...... 31

A. Environmental effects due to project location and design...... 31

B. Environmental effects during Construction ...... 32

C. Environmental effects during Operation and Maintenance...... 43

VI. ANALYSIS OF ALTERNATIVES...... 46

VII. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION ...... 48

A. Project stakeholders ...... 48

B. Consultation and disclosure to date...... 48

C. Future consultation and disclosure ...... 49

VIII.GRIEVANCE REDRESS MECHANISM...... 51

IX.ENVIRONMENTAL MANAGEMENT PLAN...... 55

A. Summary of environmental impacts and mitigation measures...... 55

B. Environmental Monitoring Plan...... 55

2

C. Institutional Arrangement...... 63

D. Environmental Management and Monitoring Costs ...... 63

X.CONCLUSION AND RECOMMENDATION ...... 65

A. Project Findings ...... 65

B. Recommendations...... 67

C. Conclusion...... 67

REFERENCES ...... 68

ANNEXURES ...... 70

Annex 1: List of species found in project area...... 70

Annex 2: Summary of Public Consultation...... 73

Annex 3: Photos from project sites...... 77

Annex 4: MOU between BPC and Affected Persons...... 80

3

Abbreviations

ADB: Asian Development Bank BAP: Biodiversity Action Plan BHU: Basic Health Unit BPC: Bhutan Power Corporation CS: Community School DFO: Divisional Forest Officer DoF: Department of Forest DoE. Department of Energy DYT: Dzongkhag Yargay Tshogchhung EA: Environmental Assessment EA: Executing agency EC: Environmental Clearance EIA: Environmental Impact Assessment FYP: Five Year Plan EMP: Environmental Monitoring Program FNCA: Forest and Nature Conservation Act HH: Household HSS: Higher Secondary School IA: Implementing Agency H&S: Health and Safety JSWNP: Jigme Singye Wangchuck National Park LSS: Lower Secondary School LV: Low Voltage MoA: Ministry of Agriculture MSS: Middle Secondary School MTI: Ministry of Trade and Industry MV: Medium Voltage NCD: Nature Conservation Division NEC: National Environment Commission NES: National Environment Strategy NGO: Non-Government Organization NWFP Non-Wood Forest Product O & M: Operation and Maintenance ORC: Out Reach Clinic PA: Protected Area PM: Project Manager/Park Manager PPE: Personal protective equipment PPTA: Project Preparatory Technical Assistance PS: Primary School RE: Rural Electrification RGOB: Royal Government of Bhutan RMNP: Royal Manas National Park RNR: Renewable Natural Resources RoW: Right of Way RSPN: Royal Society for the Protection of Nature TOR: Terms of Reference TNP: Thrumshingla National Park

4

TABLES

Table 1: Summary of distribution lines Table 2: Improvements in rural electrification infrastructure proposed Table 3: Length Feeders in PA Table 4: Length of distribution line through different land use Table 5: Length of MV line passing through private land Table 6: Comparison of alternatives Table 7: Details of public consultation conducted Table 8: Summary of public consultation Table 9: Length of distribution lines and affected persons/beneficiaries Table 10: Total length of feeder through government and private land Table 11: Environmental Impacts and Mitigation Table 12: Environmental Management Plan Table 13: Cost of implementing EMP and monitoring

MAPS

Map 1: Proposed Distribution lines under this sub-project Map 2: Map of Bhutan highlighting Mongar Map 3: Protected Areas in Bhutan Map 4: Map showing location of Distribution lines in Mongar

Glossary of Bhutanese Terms

Chathrim: Act, statute Chiwog: A unit under a Gewog Chuzhing: Irrigated/Wetland Dungkhag: Sub-district Dungpa: Sub-district administrator Dzong: The administrative center as well as religious centre in the district Dzongdag: District administrator Gewog: Block/ County Gup: Head of a Gewog Kamzhing: Dryland Lhakhang: Temple Rabdeys: Monastic bodies in Dzongs other than Punakha and Sokshing: Area where dried leaf litter is collected to make manure Tsamdro: Pasture land Tseri: Shifting cultivation, Slash and burn cultivation Tshechu: Religious festival Tshogpa: Elected representative of a Chiwog

5

List of Terms AAAC All Aluminum Alloy Conductor ABC Arial bundle cable ACSR Aluminum Conductor Steel Reinforced ADB Asian Development Bank AEC Agriculture Extension Centre BHU Basic Health Unit BPC Bhutan Power Corporation BPC/ES BPC Environment Section BWS Bumdeling Wildlife Sanctuary DCS Distribution Construction Section DFO Divisional Forest Officer DOE Department of Energy, Ministry of Trade and Industry Dzongkhag District DYT Dzongkhag Yargye Tshogchung EIA Environment Impact Assessment ESD BPC Electricity Services Division FO Dzongkhag Forest Office Gewog Block GIS Geographic Information System (software) GYT Gewog Yargye Tshogchung IEE Initial Environment Examination JBIC Japan Bank for International Cooperation JDNP Jigme Dorji Wangchuck National Park JICA Japan International Cooperation Agency JSWNP Jigme Singye Wangchuck National Park LEC Livestock Extension Centre LV Low voltage ( 400V, 240 V) LUPP Land Use Planning Project MoA Ministry of Agriculture MTI Ministry of Trade and Industry MV Medium voltage (33 kV, 11 kV) NEC National Environment Commission NFE Non-Formal Education NRDCL Natural Resource Development Corporation Limited ORC Out Reach Clinic PC Public Consensus PPTA Project Preparatory Technical Assistance (ADB)

6

RE Rural Electrification RED BPC Rural Electrification Department The Integrated Master Plan Study for Dzongkhag-wise REMP Electrification in Bhutan RMNP Royal Manas National Park RNR Renewable Natural Resources RoW Right of way RWSS Rural Water Supply Schemes S/S Substation SAPROF Special Assistance for Project Formation (conducted by JBIC) SWS Sakten Wildlife Sanctuary ToR Terms of Reference TNP Thrumshingla National Park

(Unit) A Ampere V Volt kV Kilo Volt kVA Kilo Volt Ampere kW Kilo Watt MT Metric Ton MW Mega Watt (one million Watt) MVA Mega Volt Ampere

7

I. EXECUTIVE SUMMARY

1. Bestowed with abundant water supply from fast flowing rivers over mountainous terrain, Bhutan has long recognized the potential to generate hydropower generation and the possibility of enhancing its GDP from the energy sector. Since 2007, hydropower generation has quadrupled to 1,489 MW and is further expected to increase to 1,602 MW by the end of the Tenth Plan and possibly reach 10,000 MW by 2020 (GNHC, 2009). At the same time, the guiding philosophy of Gross National Happiness dictates that development planning essentially focuses on fulfilling the fundamental objectives of achieving broad based sustainable growth and improving the quality of life while ensuring the conservation of the natural environment.

2. The overall objective of the Energy Sector for the Tenth Plan is the sustainable development and efficient use of energy resources for socio-economic development. While hydro-power development will provide environmentally clean, safe and reliable energy as well as contribute to GDP, providing electricity aims to improve the quality of life and living standard of rural communities, while contributing to self reliance.

3. In its “Vision 2020, Electricity for All” the Royal Government of Bhutan’s (RGOB) pledged to provide 100% electrification by 2020. Accordingly the Rural Electrification Master Plan targeted 85.6% electrification under the 10th Five-Year Plan (FYP: 2008-2013). Since then, the new democratically elected government has placed even higher priority on the goal of achieving its vision of “Electricity for All” and has brought forward the target completion to 2013.

4. To achieve the above target, the Accelerated Rural Electrification Project (ARE) was initiated by the RGOB to ensure that all remaining households are provided with either on-grid or off-grid/solar electrification. When this project is completed, the on-grid electrification is expected to cover 88% of the total number of Households in the country while the remaining 12% will be provided electricity through off grid means.

5. Under the ARE project a total of 8957 households in 478 villages from nineteen Dzongkhags (Thimphu, Paro, Punakha, Wangdue, Ha, Chukha, Samtse, Dagana, Gasa, Trongsa, Zhemgang, Tsirang, Pema Gatshel, Mongar, Lhuentse, Trashi Yangtse, , Samdrup Jongkhar and Sarpang) that can be connected through on-grid electrification have been identified. From these the RGOB has requested further ADB assistance in providing power to 5172 rural households in 6 dzongkhags. ADB has helped Bhutan expand rural electrification (RE) via four loans since 1995, covering over 20,000 households (HH).

6. Bhutanese law and ADB policy require that the environmental impacts of all development projects are identified and assessed as part of the planning and design process, and that action is taken to reduce those impacts to acceptable levels. This is done through the environmental assessment process, which has become an integral part of lending operations and project development and implementation worldwide. The Implementing Agency BPC has produced Environmental Clearance Applications required by national legislation for the sub- project.

7. IEES for all each sub-project has been prepared according to ADB Safeguard Policy (2009) and the Environmental Assessment Guidelines (2003) as well as the RGOB Environmental Assessment Act (2000).

8

8. This document is the IEE for Mongar RE subproject. It is one of six IEE documents describing the environmental impacts and mitigation of all subprojects proposed by the Project Preparatory Technical Assistance conducted in 2009-2010. These documents were prepared from January 2010 - April 2010 by one Domestic Environmental Specialist via input of six months. These Environmental Impact applications have been endorsed and approved by the EA.

Sub-Project description.

9. Through the Rural Electrification Project, the BPC aims to electrify 1568 rural households and 78 facilities in 10 gewogs (Kengkhar, Chaskhar Mongar, Thangrong, Jurme, Tsakaling, Tsamang, Gongdue, Silambe, and Shermung). These rural populations presently do not have access to power supply. This will assist the RGOB towards their target of providing electricity to all citizens by 2020; and it should also generate significant improvements in environmental and social conditions in the rural areas. There will be eight 33kV Medium Voltage and two 11kV MV distribution lines that will provide electricity to 141 villages that presently do not have access to power supply

Sub-Project Findings.

10. ADB Environmental Assessment Guidelines require that an IEE should evaluate impacts due to the location, design, construction and operation of the project. Construction and operation are the two activities in which the project interacts physically with the environment, so these are the two activities during which the environmental impacts occur. In assessing the effects of these processes therefore, all potential impacts of the project are identified, and mitigation is devised for any negative impacts.

11. This is a rural electrification sub-project that is expected to generate significant improvements in environmental and social conditions in the rural areas. These include:  Improvements in the quality of life from the availability of electricity;  Reductions in production of greenhouse gases from burning of kerosene and wood;  Long-term reductions in environmental damage from the logging of trees for fuel;  Improvements in health from reduced exposure to smoke and other pollutants;  Reduction in time spent collecting and transporting firewood;  Opportunities for alternative livelihoods, generating socio-economic benefits;  Contributing to the long term goals of Conservation of the RGOB.

12. Minimal negative impacts are expected from the project on Climate, Geology and seismology, Industries and Tourism. This is because the short-term production of dust is the only effect on atmosphere, excavation will not be large enough to Geology, there are no major industries in any areas to be affected by the project and there are very few tourists that visit these villages because of their remote locations.

13. As is the case with most RE schemes, the most significant impacts are the result of the design of the project, as they would not occur if off-grid methods of electrification, by the use of solar panels, had been proposed. Off-grid methods were considered during the planning stages and rejected because in Bhutan they only provide sufficient power for lighting and have a high maintenance and environmental cost because of the need to replace and dispose of the batteries.

9

14. There are ten feeders totalling 142.13km to be constructed to 141 villages in 10 gewogs. From these, there are two 33 kV Distribution lines (ARE3F7 and ARE3 F8), with a total length of 14.7km (ARE3F7 is 8.67km and ARE3 F8 is 6 km). Both the feeders are located in Tsamang gewog. The two feeders are located in the periphery and buffer of Thrumshingla National Park. As such 50% of Feeder ARE3F7 AND 75% of the second Feeder ARE3F8 are located inside protected area.

15. Since the sub Project is aimed to target remote and distant villages, it is expected that these villages will be located in faraway places surrounded by forest cover. Thus this impact on forest and ecology is one that has been caused due to the design and location of the project.

16. The assessment however does not consider this a significant impact because; Only 10.34% of the total length of feeders is located in Tsamang gewog in Thrumshingla National Park while the remaining 89.7% is located outside protected areas.

17. The one impact that is clearly a result of both design and location is the ecological impact of clearing the RoW through forested areas for the MV lines, because the target villages are located inside forested areas. These trees and other vegetation would not need to be removed if the MV lines could have been routed through un-forested areas to these villages (which was not possible), or if the MV lines were run underground (which was not considered because of the excessive cost). It should be noted however that the environmental assessment did not consider this to be a major source of impact, because the provision of electricity to rural communities conserves more trees in the long term than are removed from the RoW, because of the reductions in the felling of trees for firewood.

18. Impacts from Construction are those expected once the project implementation begins. These impacts have been segregated under Physical, Ecological, Development and Social and Cultural impacts. Impact on forest resources are considered Moderate because although 10m and 12m RoW will be cleared along 77% of the distribution line (110km in broadleaf and conifer forest). This negative impact, albeit a permanent one is not expected to be significant because;  all feeders are aligned close to farm roads and foot trails which are the main access routes to the villages and used daily by local people; and

 the long term effects of electrification of villages are expected to outweigh the short terms impacts of felling along the right of way of the distribution line. No endangered wildlife is reported to occur in close proximity to the route alignment. This is probably because the forest where the MV lines are located has been disturbed and degraded to some extent by local residents.

19. All other physical impacts such as those on air quality, noise, soil stability and erosion, natural drainage and aesthetics are assessed as Not Significant, mainly because these impacts are limited temporarily to the construction period and spatially to the immediate surrounding along the distribution lines and excavation sites at pole locations. Another reason is the remote location of the target villages, surrounded by forest to absorb any dust or noise as well as buffer aesthetic impacts.

20. In terms of social impacts, the project will bring about positive socio-economic impacts by providing electricity for lighting, cooking and heating for individual households as well as government and religious institutions. A number of secondary impacts are expected to occur as a result of the project. These include positive impacts on the health and lifestyle of local people through the use of clean technology, improved communication, networking, security, and

10

21. Impact on agriculture and private land, facilities and social and cultural resources are also considered not significant because the quantity of private and agricultural land that will be affected is very small and dispersed and the harvested crop is mostly used for self consumption. There are 40 religious temples that also benefit from the project and impacts on these and other facilities can be mitigated through prior planning, scheduling of work, consultation with local communities and by giving due consideration to local priorities. Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these areas.

22. Negative social impacts from the project may result if external workers are brought in from outside the gewog as this can sometimes cause social problems and there is also the risk of diseases like HIV/AIDs, Swine flu from socializing with contract workers as they may not have been properly screened for diseases. This impact is not expected to be significant because in any village work will probably be conducted by one or two small teams of 5-10 workers each, so individual locations will not experience a large influx of foreign workers. This can be mitigated through proper training and precautions, setting of rules and regulations for workers by contractors.

23. The Impacts from Operation and Maintenance are mainly those that occur from keeping the RoW clear of vegetation to reduce the risk of short-circuits and occasional repairs to address power outages and other problems during maintenance. Impacts on physical resources, ecological resources and economic development are not significant because RoW clearance is not as intensive and will not cause as much destruction and disturbance as during the construction Phase. Also, impacts will only occur during maintenance works and will be limited spatially to the same area as the construction Phase. This will not involve any major changes to the newly constructed project.

24. The main hazard to people from the operation and maintenance of the completed RE system is the risk of electrocution. This is a danger to rural consumers unaware of the risks of electrocution and to BPC workers conducting repair and maintenance work. BPC has already gained ample experience in implementing past Rural Electrification projects in all Dzongkhags, and staff are well aware of the risks of such projects. Also, there are established procedures for repair and maintenance of distribution lines which is being practiced very efficiently elsewhere.

25. Mitigation measures during the Construction Phase include those to reduce the impacts of forest cover, endangering vulnerable species, or reducing physical impacts such as air, noise, drainage and land stability. The Contractor should be required to provide training to raise the awareness of all site workers and staff, prohibit any hunting, fishing or similar activities by site personnel, ensure that labour camps are located in areas where no forest clearance is required and to ensure that labour camps are provided with adequate heating and lighting. The Contractor should also process for permits for firewood from the Forestry Office so that workers do not need to illegally collect firewood

26. Efforts should still be made to reduce the level of social disruption where possible, and to achieve this, the Implementing Agency should consult all affected communities in advance to inform them of the purpose, nature, duration, extent and timing of all work in and around their village and plan the work to avoid sensitive times.

11

27. During Operation and Maintenance, mitigation of impacts are easier than those during construction Phase as this involves following the procedures already laid out in the Operation and Maintenance (O&M) manuals and well as the Health and Safety (H&S) Manuals. BPC should also conduct regular training for all BPC staff to improve operation and maintenance works, improve supervision of field workers during all phases as well as conduct community education programs to raise the awareness of all target households before and after they are connected to the grid regarding the dangers of electricity, and the precautionary manner in which house systems should be used.

12

II. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. Policies relevant to the project

28. There are a number of laws and regulations that include elements that may apply to RE subprojects, depending upon their specific nature and location. These include the following:

a. Electrification Act 2001

29. Rural Electrification is strongly promoted in the Electricity Act, 2001. Part 7, Section 61.1 states that “The Minister Shall undertake to promote, support and provide rural electrification programmes through public and private sector participation in order to 1. achieve equitable regional distribution access to electricity; 2. maximize the economic, social and environmental benefits of rural electrification subsidies; 3. promote extension of the grid and development of off-grid electrification; 4. promote renewable energy.”

b. Forest and Nature Conservation Act (FNCA) 1995:

30. The Forest Act (1969) was the first environmental legislation in Bhutan and brought all forest resources under government custody to regulate utilization. This was repealed with the enactment of the FNCA in 1995, which allows community stewardship of forests, and aims to provide protection and sustainable use of forests, wildlife, and related natural resources. Schedule 1 lists those wild animals and plants that are given full protection under the Act and many of these may be found in areas through which rural electrification lines may pass. The FNCA establishes that all forests in Bhutan are Government Reserved Forests (GRF), and prohibits any development activity in these areas except with a permit.

c. Forest and Nature Conservation Rules

31. In Bhutan “Forest” means any land and water body, whether or not under vegetative cover, in which no person has acquired a permanent and transferable right of use and occupancy, whether such land is located inside or outside the forest boundary pillars, and includes land registered in a person’s name as Tsamdrog (grazing land) or Sokshing (Woodlot for collection of leaf litter)i . The Country currently has 72.5% forest cover. In 1974, a new Forest policy was promulgated wherein it was declared that at least 60 percent of the country must remain under forest cover for all times. This first declaration was followed in the next few decades by a series of positive initiatives by the RGOB to bring forest areas under protected area status.

32. Under powers established by the FNCA, the Ministry of Agriculture promulgated the FNCR in 2000, which was revised in 2006. Amongst other things the FNCR allows for:  Allotment of land and land rights in GRF;  Prohibitions, restrictions and concessions in GRF;  Transport and trade of forest produce;  Declaration and administration of protected areas;

13

 Protection of wildlife and use of certain wild species;  Prevention of forest fires, land clearance, and activities potentially impacting soil, water and wildlife resources;  Enforcing penalties for offences related to these and other aspects of the FNCR.

33. As RE subprojects are likely to involve some of these activities, formal “No Objection” from the Department of Forests (DoF) will be required.

34. Since 2008, there are now five National Parks, four Wildlife Sanctuaries and one Strict Nature Reserve in Bhutan. These protected areas have conservation policies that state that all proposed development projects within the boundaries of the protected area will be subject to an EIA under the jurisdiction of the NEC. This initially included buffer zones outside the protected areas, but was extended to include Biological Corridors in 2006 by an addendum to the FNCR.

35. The Forest and Nature Conservation Act of 1995 defines "Protected Areas" as any national park, conservation area, wildlife sanctuary, wildlife reserve, nature reserve, strict nature reserve, research forest or critical watershed. The Act gives the Government the power to declare any land in the country to be a protected as defined above for the preservation of areas of natural beauty, protection of biological diversity, management of wildlife, conservation of soil and water and related purposes. If any private registered land is taken under this section, compensation or alternative land rights shall be provided as per the Land Act.

36. Biological Corridors (BC) are defined as “areas set aside to connect one or more protected areas, which shall be conserved and managed for the safe movement of wildlife.” Although BCs do not have the same status as protected areas, activities such as new settlements, quarrying and mining, and leasing of land for grazing are prohibited. All other development activities, including construction of roads, electricity transmission and distribution lines, or any other structures, require a permit from DoF and an EC application to NEC, supported by an EIA.

37. Since more than 79% of the population live in the rural areas and forests cover 72.5% of the land area, it is impossible to separate communities from protected areas. In Bhutan, people were residing inside the PAs before these areas were declared ‘protected’. Although extra effort was made to exclude settlements while rationalizing the location of the national parks, invariably some settlements had to be included in the protected areas, primarily to accommodate the ecosystem representativeness and adjustment of physio-geographical boundaries. Recognizing the fact that it would be a traumatic process to remove the residents out of the national parks by force or legislative means, a more benign policy of working with the local people has been adopted through balancing conservation goals while also providing for the socio-economic development of rural residents.

d. Land Act 1979 (revised 2007)

38. The Land Act 1979 which provides the basis for land tenure in Bhutan was revised in 2007 to streamline many provisions in the Land Act. One major change was the establishment of an autonomous National Land Commission Secretariat which has been given full responsibility for all matters pertaining to land registration. Also the 20 land categories Have been reduced to seven categories in the revised Act including i) Chhuzhing (wetland), ii) Kamzhing (dry land) including orchard, iii) Khimsa (Residential land), iv) Industrial land, v) Commercial land, vi) Recreational and vii) Institutional land. Powers over land management

14

39. Under this Act, there are provisions for requisition of land by the government, if it is required for the benefit of the country. In such cases, the affected person will be compensated with substitute land from the same Dzongkhag or given cash compensation depending on the land classification as per the prevailing land compensation rate determined by the Act. If a house is acquired, compensation is paid on the basis of an evaluation carried out by a qualified engineer appointed by the competent authority.

e. RGOB Decentralization Policy 2002

40. The Dzongkhag and Gewog Yargay Tshogdue Acts were implemented in 2002 to support the Government’s decentralization policy and empower locally elected community bodies (DYTs and GYTs) with the authority and responsibility to plan and implement development programmes and activities, including those related to environmental management. Through this legislation the DYT is able to:  Make recommendations on activities with major environmental impacts;  Designate and protect sites and monuments of cultural or historical interest;  Designate and protect areas of special scenic beauty or biodiversity, such as Dzongkhag parks and sanctuaries;  Establish and enforce regulations to control noise pollution;  Prohibit construction of structures within 50 ft of highways;

41. The GYT is able to establish and enforce regulations to:  Control and prevent pollution of air, soil and water;  Ensure safe disposal of waste and adequate standards of sanitation;  Conserve and protect water resources, including rivers, streams, springs and lakes; and  The GYT also has custody of communal lands and community forests and can prevent encroachment onto land and forest.

42. Thus development projects such as Rural electrification can be subject to regulation promulgated by the local authorities, especially during project implementation.

B. Environmental Clearance Procedures a. Environmental Classification

43. The environmental classification of projects is decided by NEC on receipt of the Environmental Clearance (EC) application submitted by the proponent. There are three possible outcomes: i) NEC may grant Environmental Clearance on the basis of the EC application if the application contains sufficient information and it is clear that the proposed development will not have significant negative environmental impacts; ii) NEC may deny Environmental Clearance on the basis of the EC application if the application contains insufficient information and it is clear that the proposed

15

iii) If the EC application contains insufficient information on the likely nature and extent of the environmental impacts of the project or the manner in which they will be mitigated, NEC will determine that an EIA is required.

b. Preparation of EC Application and Environmental Impact Assessment

44. The requirements of the EC application are set down in sectoral guidelines that were revised with ADB assistance in 2006; and for RE projects the relevant document is entitled “Application for Environmental Clearance: Guidelines for Transmission and Distribution Lines”.

45. The information required for environmental clearance is very specific, and in all cases includes information on the applicant, the project, funding agency, the affected environment, potential impacts, mitigation, monitoring and public consultation. In the case of power transmission and distribution lines information on impacts includes details of affected: areas, types, uses and tenure of land; houses/infrastructure; protected areas; wildlife; cultural and heritage sites; etc. BPC surveyors collect most of the data during route surveys when they conduct land use and ownership surveys along proposed transmission/distribution line routes, and by consulting local communities and the Department of Forest.

46. There are three key elements of the EC application. These include the provision of signed ‘No Objection Certificates (NOC)’ from all affected stakeholders/households, Forestry clearance from the Department of Forest and Dzongkhag Administrative Approval.

47. The Environmental Assessment Act requires the proponent to prepare Terms of Reference (ToR) for the proposed EIA, which is submitted to NEC for their review. NEC will either approve the proposed ToR, or suggest amendments, which the proponent is required to incorporate before the revised scope is approved. The proponent is then required to conduct the EIA and submit the report as described in the ToR.

c. Approval process

48. A key element of the national Environmental Clearance application process is the provision of signed No Objection Certificates (NOC) from stakeholders that are specified in the guidelines, including all affected households, Department of Forest, and other relevant Government Agencies (Dept of Culture, Nature Conservation Division, etc). The National Environment Commission does not consider an EC application that does not contain the necessary NOC and Forestry Clearance. The latter for example is not granted by DoF until a forestry official has surveyed the whole length of any proposed route and has physically marked those trees that may be felled to create the RoW. The NEC in turn requires that all proposed routes are field examinations are conducted by the District Environment Officer and recommended by the District Environmental Committee. This process ensures that the least environmentally disruptive routes have been selected. This elaborate process of revisiting the proposed sites by different agencies ensures that all possible options have been explored, and the most suitable one adopted.

16

III. DESCRIPTION OF THE PROJECT

A. Project description

49. The sub-project is located in Mongar Dzongkhag, in eastern Bhutan. Through this project, electricity will be provided to 141villages in 10 gewogs (Kengkhar, Chaskhar, Mongar, Thangrong, Jurme, Tsakaling, Tsamang, Gongdue, Silambe, and Shermung). The project activities comprise of three basic elements: (i) Medium Voltage lines to convey electricity from an existing distribution line to individual village, (ii) Pole mounted transformers in or near villages to reduce the voltage from 33 kV to the 230 or 415 V required for domestic supply, and (iii) Service lines supplying electricity to individual consumers.

50. Under this sub-project, there are eight 33kV Medium Voltage and two 11kV MV distribution lines that will run for a total of 142km via an estimated 2840 poles. These will connect to 141 transformers located in or near villages to be electrified, and from these a 320km LV network of 230 or 415 V will supply electricity to 1568 households, 16 schools, 40 Temples/monasteries, 17 Basic Health Units/Out Reach Clinics, 1 Renewable Research Centre, 1 Gewog office and 3 Rice Mills.

Table 1: Summary of distribution lines (length in metres) Feeder Sub MV length Villages Total Name Feeder (km) Voltage lVLength (m) Consumer ARE3G1 15 36.76 33 89790.5 42 487 ARE3G2 0 1.76 33 5610.9 1 12 ARE3G3 0 0.93 33 5264.7 1 20 ARE3G4 5 8.07 33 25144.5 12 119 ARE3G5 15 20.91 33 73072.2 27 311 ARE1G6 4 9.87 11 22312.5 6 86 ARE3G7 11 8.67 33 21368.5 37 82 ARE1G8 0 6.03 11 10653.3 4 50 ARE3G9 2 40.80 33 59959.2 6 437 ARE3G10 2 8.32 33 11553.3 5 42 Total 54 142.13 324729.66 141 1646.0

Feeder No. AREG1

51. This is a 33 kV distribution line that will be located in Kengkhar gewog and Jurme gewogs. The total length of the entire 33kV line is 36.7km and the LV line is 50km. This line will be tapped from the existing 33kV line of Pema Gatshel. There are 15 sub-feeders that will be tapped from this main line. This feeder will provide electricity to 487 beneficiaries.

17

Feeder No. AREG2

52. This is a 33kV line that is located in and will extend from the existing 33kV line at Mongar to 12 consumers in Wangling village. The length of the MV line is 1.76km and the LV line is 3.4km. One transformer will be required and the Right of way required along the alignment is 12m.

Feeder No. AREG3

53. This is a 33kV line that will be located in Chaskar gewog and will be tapped from the existing 33 kV Mongar line to 20 consumers in Atingkhar village. The length of the MV line is 0.93km and the LV line is 3.3km. One transformer will be required and the Right of way required along the alignment is 12m.

Feeder No. AREG4

54. This is a 33kV distribution line that will be located in and will be tapped from the proposed 33 kV line to be required under JICA funding. There are 5 sub- feeders and the total length of the MV line is 8.1km and the LV line is 14km. There are 119 beneficiaries from this feeder.

Feeder No. AREG5

55. This is a 33kV line that will be located in Jurme gewog and will be tapped from the proposed ARE3G1 distribution line to be constructed under this project. There are 15 sub- feeders and the total length of the MV line is 20.9km and the LV line is 43.4km. There are 311 consumers in total.

Feeder No. AREG6

56. This is a 33kV line that will be located in Tsakaling gewog and will be tapped from Younsing substation. There are 5 sub-feeders and the total length of the MV line is 10km and the LV line is 13.3km. There are 86 consumers in total.

Feeder No. AREG7

57. This is a 33 kV distribution line in Tsamang gewog that will extend to Khulung and Ganglapong villages. The total length of the feeder 8.67km and the LV line is 12.6km. This line tapped from Lhadrong substation at Lhuentse has two sub feeders to Ganglapong BHU area (ARE3G7F01) and to Pampa village (ARE3G7F02). In total there are 75households, 3 schools, 2 Lhakhangs and 2 BHU/ORCs.

Feeder No. AREG8

58. This is a 33 kV distribution line in Tsamang gewog and will extend to Banjar and Gangtho villages. The total length of the feeder 6.03km and the LV line is 5.8km. This line will be tapped from Tsamang Sub-station and there is a very short sub-feeder (0.16km) to Banjar A

18

Feeder No. AREG9

59. This is a 33kV line that will be located in Gongdue and Tsilabi gewogs and will be tapped from the proposed ARE3G1 line. There are 11 sub-feeders and the total length of the MV line is 40.8km and the LV line is 35.4km. There are 437 consumers.

Feeder No. AREG10

60. This is a 33kV line that will be located in Shermung gewog and will be tapped from the existing substation at Lower Samakha. There are 2 sub-feeders and the total length of the MV line is 8.3km and the LV line is 11.5km. There are 39 households and 3 lhakhangs to be electrified.

61. The MV lines will carry either 11kV or 33 kV via three strands of aluminium conductors, mounted on poles located at intervals of around 50-70 m, depending on topography and terrain. Poles are of cast iron, with an iron cross-piece at the top on which insulators are mounted to hold the conductors. Section Poles have two legs and are located every 200-250 m, and between these are located a series of single-strut Interval Poles, to support the conductors and maintain them the requisite 5.8 m above ground level. Poles are 10 m in length and are held in the ground via earth and concrete foundations, 1.6-1.9 m in depth.

62. Conductors are either bare or covered. Bare conductors are of the Aluminium Conductor Steel Reinforced (ACSR) type, which consist of several strands of aluminium wire wound around a central steel core. Covered conductors are of the Aerial Bundle Cable (ABC) type, in which insulated strands of aluminium are wound together and covered with poly- ethylene insulation. Covered conductors are used for LV lines in inhabited areas, but may also be used for MV lines in locations where it is necessary to reduce the width of the Right of Way (RoW) cleared on either side of the line. In forested areas all vegetation is cleared from a specified width around the transmission or distribution line to prevent interruptions in supply from falling trees, or branches touching the line. For bare conductors the RoW is 12 m and for covered conductors it is 4 m (because the insulation reduces the risk of outage).

63. MV lines cross mainly forested areas, but as noted above, routes have been selected to run along existing farm roads, tracks and pathways where possible, because in these areas there has already been some clearance of trees and other vegetation, so this reduces the amount of new felling required. No clearance is required where routes cross public or agricultural land, and at farm sites, poles will be located on field boundaries where possible, to reduce the loss of productive land.

64. Transformers are ready-made components imported from overseas, which are located with associated components (junction box, fuses, lightning arrestors) on double-strut poles inside or outside the villages to be electrified. Transformers have an outer metal casing and measure around 1 x 1 x 0.25 m for the LV lines, and the junction box is slightly larger.

65. A local network of single LV covered conductors (230 or 415 V) will run from each transformer to the supplied village or villages, and branches will run to individual consumers (households, facilities or industries), terminating at a service meter on an outside wall.

19

B. Project budget and implementation

66. Detailed design of the project began in 2009 and should be completed by end of 2010, after which construction will be initiated. All the work should be completed by the end of 2013.

67. The project cost is presently estimated at Nu. 218 million. This is an initial estimate and may change depending on change in prices in material cost as well as changes in regional and local transportation cost. Construction of this subproject should take approximately one year.

20

Map 1: Proposed Distribution lines under this sub-project (detailed maps of individual distribution lines are included in the annex)

21

Table 2: Improvements in rural electrification infrastructure proposed

Infrastructure Function Description Location Medium Voltage Convey Six strands of 11 kV aluminium conductors (power cables), strung None of the MV lines lie in protected areas. (MV) Line electricity between iron poles located every 50-70 m. Poles are 10 m long and Howve, they do run through forest, farmland from an project 8 m above the ground, and are of cast iron with a cross- and public land, and routes are aligned along existing piece at the top containing insulators to which conductors are existing farm roads and paths where possible. distribution attached. Section Poles have two legs and are located every 200- On farm land, poles will be located at field line to a 250 m, and between these are single-strut Interval Poles. Bare boundaries where possible. transformer conductors contain aluminium strands wound around a steel core; Feeder ARE3G1: Kengkhar gewog . and covered conductors consist of insulated strands of aluminium, Feeder ARE3G2: Mongar gewog wound together inside polyethylene insulation. Feeder ARE3G3: Chaskhar gewog Feeder ARE3G1: MV length = 36.76km,15 sub-feeders; 735 poles Feeder ARE3G4: Thangrong gewog Feeder ARE3G2: MV length =1.766km, 35 poles Feeder ARE3G5: Jurme gewog Feeder ARE3G3: MV length = 0.93km, 20 poles Feeder ARE3G6: Tsakaling gewog Feeder ARE3G4: MV length = 8.1km, 5 sub-feeders;160 poles Feeder ARE3G7: Tsamang gewog Feeder ARE3G5: MV length = 20.9km,15 sub-feeders;420 poles Feeder ARE3G8: Tsamang gewog Feeder ARE3G6: MV length = 9.87km, 4 sub-feeders; 198 poles Feeder ARE3G9: Gongdue, Feeder ARE3G7: MV length = 8.67km, 2 sub-feeders;174 poles Feeder ARE3G10: Shermung gewog Feeder ARE3G8: MV length = 6.03km, 120 poles

Feeder ARE3G9: MV length = 40.8km,11 sub-feeders;820 poles

Feeder ARE3G10: MV length = 8.3km,2 sub-feeders;166 poles Transformer Reduce Pre-manufactured electrical component in metal casing, Generally one transformer per electrified voltage approximately 1 x 1 x 0.5 m. Numbers per gewog: village, on a pole inside or outside the village. from 33 kV Feeder ARE3G1: 42 transformers Feeder ARE3G1: 42 villages in the MV Feeder ARE3G2: 1 transformer Feeder ARE3G2: 1 village line to 230 Feeder ARE3G3: 1 transformer Feeder ARE3G3: 1 village or 415 V in the LV Feeder ARE3G4: 12 transformers Feeder ARE3G4: 12 villages Line. Feeder ARE3G5: 27 transformers Feeder ARE3G5: 27 villages Feeder ARE3G6: 6 transformers Feeder ARE3G6: 6 villages Feeder ARE3G7: 6 transformers Feeder ARE3G7: 6 villages Feeder ARE3G8: 4 transformers Feeder ARE3G8: 4 villages Feeder ARE3G9: 37 transformers Feeder ARE3G9: 37 villages Feeder ARE3G10: 5 transformers Feeder ARE3G10: 5 villages

22

Infrastructure Function Description Location Low Voltage (LV) Convey Generally single strand of LV covered conductors (230 V for single Total number of connections: 170 Line electricity phase, 415 V for three phase), mounted on single poles at 50 m Feeder ARE3G1: 474 HH, 1S,7L,3B/O,1R,1G from a intervals. Each line terminates at a service meter on an external wall Feeder ARE3G2: 12HH transformer of the consumer (household, facility, industry). Length of LV line: Feeder ARE3G3: 20HH to each Feeder ARE3G1: 50 km Feeder ARE3G4: 115HH, 1S,1L,2B/O individual Feeder ARE3G2: 3.4 km consumer Feeder ARE3G5: 292HH,2S,14L,3B/O Feeder ARE3G3: 3.3 km Feeder ARE3G6: 75HH,6S,1L,1B/O,3RM Feeder ARE3G4: 14 km Feeder ARE3G7: 75HH,3S,2L,2B/O Feeder ARE3G5: 43.4 km Feeder ARE3G8: 47HH,1S,1L,1B/O Feeder ARE3G6: 13.3 km Feeder ARE3G9: 419HH,2S,11L,5B/O Feeder ARE3G7: 12.6 km Feeder ARE3G10: 39HH,3L Feeder ARE3G8: 5.8 km

Feeder ARE3G9: 35.4 km

Feeder ARE3G10: 11.5 km

HH- households, S- School, L-Lhakhang, B-Basic health unit, R-Renewable Natural Resource office; RM-Rice mill, G-Geog office

23

IV. DESCRIPTION OF THE ENVIRONMENT

A. Physical Resources

1. Location

68. Mongar Dzongkhag is located in the east-central part of Bhutan between about 450km from Thimphu. It is bounded by the Lhuentse Dzongkhag to the north, Zhemgang Dzongkhag to the west and the Trashi Yangtse, Trashigang and Pema Gatshel Dzongkhags to the east and south-east.

69. The Dzongkhag covers an area of approximately 1875 sq.kme and is administratively divided into 16 Gewogs namely, Balam, Chaskhar, Chhali, Drametse, Drepung, Gongdue, Jurmey, Kengkhar, Mongar, Ngatshang, Saling, Sherimukhung, Silambi, Thangrong, Tsakaling and Tsamang.

Map 2: Map of Bhutan highlighting Mongar

24

2. Topography, geology and soils

70. The elevation of Mongar Dzongkhag ranges from 400 m to 3800 m above sea level. The majority of the land area is at elevations between 600-3000m and less than 2% is at elevations higher than 3600. Like most of the country most of the valleys are deeply cut and have narrow V shaped floors along fast following rivers.

71. Mongar Dzongkhag is located on the greater Himalayan Sequence created by the Main Central Thrust. The bed rock is mainly gneiss, schist quartzite, limestone with intrusions and some Tethyan material. Surface layers consist mainly of alluvium laid down by the rivers over the millennia. Silt and sand are plenty along the kuri chhu. Because of the influence of the rivers and heavily forested catchments (Chirpine forest), soils are high in organic material, and are mainly temperate stagnogleys and podzols (Norbu, C et al. 2003).

3. Climate

72. The Gewogs in the lower altitudes experience subtropical climate while those at higher altitudes experience temperate climate. In general the Dzongkhag experiences hot and wet summers and cool dry winters.

73. The mean maximum temperature ranges from 14ºC in January to 25 ºC in August while the minimum temperatures in winter drop down to as low as 6 ºC. The average annual rainfall received over the past 13 years (1996-2008) is 886mm, but total rainfall in some areas goes up as high as 1200mm. The months of November to January are usually pretty dry with little or no rainfall.

4. Air Quality

74. There are no data available on the air quality of Mongar, but as there is such a low population, very few vehicles and no heavy industry in the dzongkhag, then it is reasonable to assume that air quality is likely to be generally good. There should thus be low levels of pollutants associated with heavy industry, such as oxides of nitrogen (NOx) and sulphur (SOx), and exhaust emissions from vehicles, such as lead. However, as wood and kerosene are the main fuel for cooking and heating in non-electrified rural areas, then there may be localised increases in levels of smoke, soot and carbon dioxide in these areas at times when fuel usage is highest (in the evening and during the winter). Almost certainly within houses people are likely to be exposed to high levels of these pollutants.

75. In addition there are health impacts from the use of fire wood and kerosene lamp that causes eye and respiration problems. Use of electricity will contribute to the reduction of in- house air pollution from Bhukharis/stoves and fuel wood use.

25

5. Hydrology

76. There are two major rivers, the Dangme Chhu in the east and the Kuri Chhu in the centre. The latter originates in Lhuentse Dzongkhag and flows through the centre of the dzongkhag. It is joined by small rivers like Gangolo chhu from the east and Shongjari Chu and Yunari Chu before it meets the Drangme Chu, flowing in along the eastern border. This river then flows along the boundary line till it enters into Zhemgang Dzongkhag. Towards the east, dissecting the eastern gewogs is the Sherichu that drains into the Drangme Chu along the Mongar- Trashigang border.

B. Ecological Resources

1. Protected Areas

77. There are five National Parks in Bhutan, four Wildlife Sanctuaries and one Strict Nature Reserve, shown in Map 3. The protected area system was initially created in the 1960’s. However, these were mostly confined to the northern and southern regions of the country, so the PA system was revised to encompass all the different ecosystems and habitats in the country, resulting in 9 protected areas covering 26.5% of the country’s land area. In 1999, biological corridors were identified to link the various protected areas adding another 9% to the PA system. In 2008, a new park was created that further increased it to 48%. Now, Bhutan has one of the largest areas under protected area status.

Map 3: Protected Areas in Bhutan. (source: WWF Bhutan)

26

78. Parts of Mongar dzongkhag fall under two protected areas, the Thrumshingla National Park in the Northwest and Bumdeling Wildlife Sanctuary to the Northeast. The outpost for the sanctuary is located at Sershong in Sheremung. Bumdeling wildlife sanctuary covering an area of 1545 sq. km was officially gazetted in 1995 and operationalized in 1998 to protect large areas of virtually untouched Eastern Himalayan ecosystems ranging from warm broadleaved forests to alpine ecosystem. The project area does not fall inside this Sanctuary.

79. Thrumshingla national Park. The Thrumshingla National Park (TNP) covers parts of Bumthang, Mongar, Lhuentse and Zhemgang Dzongkhags. Gazetted in 1998, it has an area of 889 sq. km. The population within the TNP is approximately 10,000-11,000 households. The park was created to conserve the changing landscape and varied habitats in the east-central region. The TNP is significant because it provides habitat for many endangered species as well as continuous habitat for species like the Tiger to move between biological corridors. The park is known for its old growth fir forest in Thrumshingla, for its bird watching sites in Mongar, its Rhododendrons and as the habitat for significant species such as Tigers and Red Panda. The park has over 340 species of birds, ten of which are globally threatened. The Park headquarters is located in Ura, Bumthang and within the project area there is a warden outpost in Tsamang.

2. Habitat types

80. With altitudes ranging of 650 m to 5500 masl, the TNP prides itself in encompassing a variety of forest types ranging from sub-tropical forests in the southern part of the park, a chir pine zone, warm broadleaved forest below cool broadleaved forests, conifer forests and finally alpine forests above 4000m.

81. Under Mongar Dzongkhag approximately 88.5% of the total area is under forest cover. At lower altitudes 46.3% of the forest lies under broadleaf forest, 10.6% under mixed broadleaf and coniferous forest, 29.6% under conifer forest including chirpine forests (15%). Scrub forest covers 1.9% while natural pastures are less than 1%. Lemon grass, which can be used for essential oils production, grows profusely under the chir pine stands. (Atlas of Bhutan, 1997).

82. Within the project site at Tsamang the forest type is mostly warm broadleaved forest interspersed with stands of chirpine forest as these are the dominant vegetation type. The scrub forest immediate to the settlement areas are degraded from cattle grazing and from use for firewood, timber and NTFP collection.

3. Biodiversity

83. The forest is home to many species of mammals and the TNP management plan reports a list of 68 mammals known in the Park (NCD, 2002). Tigers are known to occur in the northern and western portions of the park. Some of species that may be found in the Project area include Barking deer (Muntiacus muntjac), Goral (Nemorhedus goral), Common leopard (Panthera pardus), Clouded leopard (Neofelis nebulosa), Serow (Nemorhedus sumatraensis), Himalayan Black bear (Ursus thibetanus), Himalayan yellow throated marten (Martes flavigula), Assamese macaque (Macaca assamensis), Capped langur (Trachypithecus pileatus) and Wild pig (Sus scrofa). Wild dog (Cuon alpinus) and leopards sometimes kill livestock in Tsamang gewog (pers.comm, 2009).

27

84. TNP is rich in birdlife with over 341 species of birds stated to be occurring in the park with 168 birds in the warm broadleaved forests and 101 in the cool broadleaved forests (NCD, 2002). Birds that were common in the project area include Little pied flycatcher, Laughing thrush, Black Bulbul, Drongo Cuckoo, Ashy Drongo, Large billed crow, Speckled wood pigeon, Blue whistling thrush, White tailed Robin and many more. C. Economic Development

1. Land use, industry and agriculture

85. Apart from the 88.5% under forest, 9.8% is used for Agriculture, less than 1% is under settlement and the remaining falls under rock outcrops, water spreads and landslip areas. In terms of area coverage, Khamzhing/dryland cultivation is the most important land use, followed by Chuzhing/wetland cultivation and Tseri (slash and burn cultivation) in a few places. The annual crops are maize, rice, barley and wheat. Common vegetables grown in most gewogs are potatoes, chilli, ginger, onions, beans, peas, tomatoes, carrots and vegetables. The major fruit crop is Orange followed by Bananas. To further promote agriculture, irrigation channels and power tiller tracks have been constructed by the Dzongkhag.

86. Livestock rearing is an important source of livelihood with over 27,000 cattle in the district. Important livestock products are butter, cheese, milk and meat. Other less significant livestock include poultry, horses, goats and pigs.

87. Over 85% of the 386 contract firms are petty contract firms, 15% are grade C firms and there are only 1 contractor in Grades A and B. In addition to this there are 560 cottage industries (NSB, 2007). A number of households earn income through collection of lemon grass for the central distillery located at Kurizampa. Resin taping is another small-scale industrial activity which provides cash income to the rural population.

2. Infrastructure

88. Mongar town over the last decade has rapidly grown from a handful of shops along the main stream to a large bustling town with a numerous hotels, restaurants and shops. It is now a major commercial hub in the eastern Dzongkhag with the completion of the Projects like the Kuri chhu hydro power project The Dzong as well as most government offices like the BPC, BDFC, Bank, Divisional Forest Office, Post Office, Police are located within the main town. The major towns in Mongar are located at Gyalpozhing, Lingmithang Drametse and Yadhi. Other smaller satellite towns include Rolong, Sherichu, Kelikhar and Sengor. Apart from these town areas, the gewogs are largely remote with widely scattered villages limited such as the gewog and RNR centres, Primary school and BHU/ORC’s.

89. While 91.1% of the population in the Dzongkhag has a basic sanitary facility, 78% of the households have access to piped water either inside or shared outside the house.

3. Transportation and access

90. The lateral national highway from Thimphu to Trashigang divides Mongar Dzongkhag into almost two equal halves north and south of the highway. At present a total of 7.4% (336.3 km) of the total road network in Bhutan is found in Mongar Dzongkhag. This includes 184 km of national highway, 20 km of District road, 68.1 km of feeder road, 17.2 km of farm road, 2.2 km

28

th FYP.

4. The tourist industry

91. Visitor numbers have continued to rise, particularly over the past few years, despite the requirement for all tourists to pay a non-refundable daily tariff of US $200 to the tour operator, for the cost of accommodation, food and internal travel. Tourism is now the third largest provider of foreign exchange in Bhutan, earning US$ 29 million in 2007, when 21,094 people visited.

92. Because of the difficulty of internal travel in Bhutan, requiring long journeys on winding roads between and over mountains, only relatively few tourists venture to the east of the country, so there are few hotels or major attractions.

93. Mongar town is along the National highway that cuts laterally across the country and therefore, many tourists pass through en route to other eastern dzongkhags. There are a number of medium to large hotels and facilities for tourists are beginning to expand rapidly.

94. In the project sites however, few or no tourists visit the villages and therefore, tourism however has had little impact in the villages, because of the difficulty of reaching most locations, so most villages remain much as they have for the past few centuries.

D. Social and Cultural Resources

1. Demography

95. The total population in Mongar is 37,069 of which 90% are regular residents, 9% institutional residents and 1% transient people. There are 7,348 households and the average family size of 5 persons per family. 19 % (7,153) of the population lives in the urban areas. The sex ratio is 101. In the Project area, Tsamang gewog, there are 218 households with a total population of 1208 residents. When compared to the land area the population density is only 8 persons per sq.km.

96. A number of dialects are spoken in Mongar but Tsanglakha is most commonly used by almost the entire population. Other dialects used include Khengkha, Bumthangkha, Chalikha and Gongdukha. Dzongkhag is also well understood by a majority of the population.

2. Health, education and other facilities

97. The main hospital, the second largest hospital in the country is in Mongar. There are 22 Basic health units in 16 gewogs, plus 54 outreach clinic spread over the entire Dzongkhag to deliver public health services to the population. Beside these there are two malarial centres. The Dzongkhag has successfully achieved over 100% immunization coverage.

29

98. Mongar Dzongkhag has a literacy rate of 50.18%. Out of the 16 Gewogs, only Mongar, Ngatshang, Saling and Tsamang Gewogs enjoy relatively good educational coverage but other gewogs have enrolment ratios below the national level. There are 2 Higher Secondary Schools, 6 Lower Secondary Schools, 9 Primary Schools and 30 community schools with 8784 students and 215 teachers. There are also 58 Non Formal Education centres and 6 monastic schools.

99. There are 16 RNR Centres, One Divisional Forest Office, and Park warden offices. During the 2005 census, only 40% of the households in Mongar were electrified and 43% of the population used kerosene for lighting. Under this ARE project, Mongar has one of the largest number of villages (over 100) that are yet to be electrified under the 10th FYP.

3. History and culture

100. There are a total of 170 religious structures (lhakhangs, Goenpas, gomdeys, etc.).Many of which are privately build. It does have the famous Mongar Dzong.

101. Some of the religious and cultural sites of significance include the Mongar Dzong built in the traditional style without using any nails; Yakgang Lhakhang and Tagchu Goenpa both privately owned and repositories of many spiritual treasures and sacred objects; the 16th century Drametse Lhakhang where annual religious festivals are held and finally the famous ruined Zhongar Dzong near Lingmithang. Within the project site there are 7 Lhakhangs. These are Tsamang Tokari Lhakhang, Nangkar Lhakhang, Serboom Lhakhang, Banjar Lhakhang, Gangla Pong Jangchub Choeling, Gangla Pong Lhakhang and Khuling Goenpa Lhakhang.

30

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Environmental effects due to project location and design

102. Most of the impacts that occur in this project are due to project location and design. This is because these impacts would not occur if an alternative location or design such as off-grid methods of electrification, by the use of solar panels, had been proposed. However this is not a valid comparison because off-grid methods were considered during the planning stages and rejected because they only provide sufficient power for lighting, and have a high maintenance and environmental cost because of the need to replace and dispose of the batteries. The one impact that is clearly a result of both design and location is the ecological impact of clearing the RoW through the Protected Area.

103. There are ten feeders totalling 142.13km to be constructed to 141 villages in 10 gewogs. From these, there are two 33 kV Distribution lines (ARE3F7 and ARE3 F8), with a total length of 14.7km (ARE3F7 is 8.67km and ARE3 F8 is 6 km) that are located in Tsamang gewog. The two feeders are located in the periphery and buffer of Thrumshingla National Park.

104. Due to the location of the villages inside the National Park (or close to the boundary) the impact of design cannot be avoided. The protected area system in Bhutan was established to protect important and diverse ecosystems, but local communities were already living in these rural habitats long before the PA system was established. To provide electricity for all means that it would be unfair to leave these communities out of the developmental process.

105. All protected areas in Bhutan have settlements located inside the parks, and it is within the Conservation policy to allow these settlements and local communities to remain inside. In a protected area, areas that have settlements are usually designated as Multiple use zones where collection of a non- timber forest products, harvesting of timber, regulated tourism, recreation, grazing, habitat management and reforestation are permissible. Certain developmental activities like rural electrification are allowed as long as the required Environmental Assessment is conducted and the Protected Area Management is convinced that the environmental impacts can be mitigated.

Map 4: Map showing location of Distribution lines in Mongar (Source: RED, BPC)

Thrumshingla NP

31

106. The assessment however does not consider this a significant impact because;  Only 10.34% of the total length of feeders is located in Tsamang gewog in Thrumshingla National Park while the remaining eight distribution lines amounting to 89.7% of the total length is located outside protected areas.  Even inside the protected area, only 50% of Feeder ARE3F7 crosses through Thrumshingla National Park from Lhadrong to Khulung and Luenchen for 4.2km, while 4.5km of the second feeder ARE4F8 from Banjar and Gangtho traverses Thrumshingla National Park.  The distribution lines do not cut into the pristine forested areas of the park but are located along the periphery of the park and biological corridor;  Due to the presence of settlement areas and the proximity to the park borders, these areas will naturally fall under multiple use zone where construction activities can be permitted with prior approval from the management and use of natural resources such as timber, firewood, soil, stones, boulders as well as Non-timber forest products for self use are permitted.

Table 3: Length Feeders in PA Total length of Length inside the % of total feeder Gewog Feeder distribution line park and BC length in Mongar Tsamang ARE3G7 8.67km 4.2km 2.9 6.03km 3.1 4.5km Tsamang ARE3G8

107. If off-grid means of electrification are used, these impacts would not occur. However this is not in line with the objectives of providing reliable on-grid electrification for all on an equitable basis. Also, off-grid methods such as Solar only provide sufficient power for lighting, and have a high maintenance and environmental cost because of the need to replace and dispose of the batteries.

108. The Park field personnel have also conducted the necessary field visits along the proposed alignment to assess the environmental impacts following which forestry clearance has been granted from the management. Also, prior to granting Environmental Clearance, the site assessments have been conducted by Dzongkhag Environmental Officers for NEC to grant environmental clearance.

109. Despite this mitigation measures may be undertaken to ensure that environmental impacts during construction are minimized. These are discussed in the following paragraphs

B. Environmental effects during Construction

110. There are two 11 kV Medium voltage lines and 8 33 kV line extending via three strands of Aluminium conductors, mounted on poles located at intervals, depending on topography and terrain. Poles are of steel, with steel cross-rims at the top on which insulators are mounted to hold the conductors. Section Poles have two legs and are located every 200-250 m, and between these are located a series of single-structure Interval Poles, to support the conductors and maintain them at the requisite 5.8 m above ground level. Poles are 10 m in length and are held in the ground via earth and concrete foundations, 1.6-1.9 m in depth.

32

111. Construction will start at the tap-off point from the distribution line, and the MV line will be cleared and constructed in sequence, gradually proceeding along the route. Once a length of RoW has been cleared, foundations for poles will be dug by hand, at intervals of approximately 200-250 m for double-structure Section Poles, and 30-70 m for single-structure Interval Poles. Foundations are a standard size of 600 x 700 mm, dug to 1900 mm for 33 kV lines, and after excavation, concrete (mixed on site) is poured into the cavity to create a solid floor, around 250 mm thick. Poles are fitted with a circular metal base plate, which stands on top of the dried concrete, after which the excavated soil and stone is replaced around the pole and compacted tightly by hand. A further layer of concrete is applied 250 mm above and below the ground surface to resist corrosion. The conductors are then attached to insulators at the top of each pole by hand, after which the team moves on to the next location. Where the MV line crosses areas of open ground or agricultural land there is no need to clear the RoW, so the procedure will involve erection of the poles and connection of the conductors only

112. Transformers are attached to double-structure poles, located inside or outside villages. The poles are erected as described above, and the pre-prepared transformers and other components (junction box, fuses, etc) are attached and joined up by hand. Signs are then attached to the pole warning people of the dangers of electrocution.

113. LV lines in the villages will be constructed in the same way as the MV lines but there will again be no need to clear the RoW as poles will mostly be located within the villages, and in this case foundations will be slightly smaller, as the standard size for LV lines is 600 x 700 mm, dug to 1600 mm. Excavated material will again be replaced on top of the foundations once the concrete has dried, after which the covered conductors will be attached by hand. The system will end at a service meter, attached to an exterior wall of each individual house or facility.

114. All elements will be completed before commissioning tests are conducted and the final connection to the distribution line will then be opened.

1. Air quality. 115. There is no data available on the air quality in Mongar but the major contributors to air pollution in Bhutan are industries and vehicular emissions and the former is absent while the latter is minimal in the project site. The main source of pollution in the rural areas is domestic emissions from burning firewood for cooking and heating, use of kerosene for lighting and diesel for mills. These emissions cause localized increases in levels of smoke, soot and carbon dioxide, especially at times when fuel usage is highest. However, once the project is in operation, it is expected that these levels of pollutants will reduce with use of electricity as the amount of fuel wood will reduce and people inside the houses are less exposed to such pollutants.

116. With the initiation of the project, the only impact on air quality is expected from movement of vehicles and from the dust pollution, as dust may blow in from cleared areas at the poles site. Dust pollution caused by pole construction will be localised at pole sites and RoW only and limited to the construction period only. Most of the foundation for poles will be dug by hand and other implements and equipment (including poles and transformers) will be carried to site by porters, from the nearest road. Air emissions from vehicular movement will be minor as this is limited to a few vehicles to the few selected drop off points. Thus the impact on air quality will be low with no impact at the regional/Dzongkhag level.

117. Mitigation measures which could be undertaken on site include;

33

 To reduce the dust from cleared areas along RoW, the lower ground layer of grass and other low vegetation should be retained and cut vegetation apart from logs can be piled at the edge of the RoW and allowed to dry or to rot down in situ;  Avoid using large machinery to minimize dust and do not burn waste vegetation to prevent forest fires.

3. Noise generation.

118. The main source of noise will be from trucks during material drop off at designated points and to campsites near road access points. These however will be limited to the construction period. All other construction work is small in scale (involving the excavation of small pits for pole foundations and erection of poles and stringing of conductors), and will be conducted by small teams without the use of heavy machinery. Thus noise generation is not expected to be significant as the area is so remote and villages are scattered. Also, with the large forest cover most of the noise created will be buffered by the surrounding forest. There should be no need to mitigate this impact.

4. Natural Drainage.

119. Where distribution lines cross rivers and streams effects on local drainage and water quality can occur during construction period mainly from loose soils at the excavated site for the pole foundations. This impact is however small in scale, dispersed and will only occur at crossing points.

120. Excavation can also affect aquatic ecology and fisheries if large quantities of silt are washed into the river during rain, or if work is conducted within the river itself. This should not be the case here however, because there is no requirement for any construction in river-beds. Also, excavation for the pole foundations is small in scale and dispersed, and there will be no large stockpiles of soil that could create a major point-source of silt pollution. Almost all of the excavated soil will be replaced into the cavity within a few hours of removal, so any run-off would be short-lived and very small in scale. It should therefore also be unnecessary to mitigate potential impacts on aquatic ecology.

121. To minimize the quantity of soil being washed into the river, it is recommended wherever possible, poles will be located at a minimal distance of 30 m from the river on stable soil. Also, excavation works should be conducted during the dry season (which is expected as it may be impossible to work during the monsoons when the river is too high to be crossed).

5. Soil stability and erosion

122. Within the project sites the altitude along the distribution line ranges from 1740m to 2680m. The slope is moderate to steep (from 15-45 degrees). The removal of vegetative cover and soil excavation work may cause some land instability and soil erosion but this impact is expected to occur only during excavation for poles. Also, the depth of the foundation for the 33kV poles is 1900mm and the area for the foundation is 600mmx700mm (BPC, 2007). There are 2840 poles to be constructed. This means that the total volume of soil to be excavated is only 2266 m3. Once the poles are ready to be erected, most of the excavated soil will be reused for backfilling and compaction to secure the poles. This impact can be mitigated easily since the size of the excavated area is small. Safety for workers while working on steep slopes should be covered under worker health and safety issues.

34

i. Impact on Physical Resources

Impact on Physical Resources

123. Clearing the RoW is the activity that will bring about the most significant physical changes, as areas that are presently covered with vegetation will be left bare and large quantities of waste brush and timber will be produced. Dust may blow from bare ground, and this could be a health hazard for workers and a nuisance where cleared areas are close to places where people live and work (villages, fields, farm roads, or footpaths). There would also be a serious risk of causing forest fires if contractors were to attempt to burn the waste vegetation.

124. However it is not expected that the construction work will cause major negative impacts. This is mainly because:  The existing lack of access roads to the sites means that all construction components will be carried by manpower to the site from the nearest road.  All other construction work is small in scale (involving the excavation of small pits for pole foundations and erection of poles and stringing of conductors), and will be conducted by small teams without the use of heavy vehicles and machinery;  MV line routes have been chosen to minimize as far as possible the need for forest clearance and the acquisition of private land;  23% of the MV line will be in un-forested areas, where the RoW will not be cleared;  Most of the affected areas outside the villages are uninhabited, and in villages work can be conducted without causing major disruption to people;  Construction work is relatively straightforward and can be completed in a fairly short time (approximately one year for this subproject).

125. The entire route was surveyed in the course of this study and observations were made regarding land use and ownership, as well as the type of forest and other factors. The Table below shows the main results.

Table 4: Length of distribution line through different land use (length in metres)

Feeder Broadleaf Conifer Sokshing Tseri Scrub Total ARE3G1 12760 10090 2930 0 3920 29700 ARE3G2 0 1250 0 0 0 1250 ARE3G3 0 0 300 0 0 300 ARE3G4 2900 4000 0 0 100 7000 ARE3G5 8900 3930 1100 500 4050 18480 ARE1G6 1600 4700 930 0 540 7770 ARE3G7 3200 220 0 0 990 4410 ARE3G8 3650 0 0 0 2240 5890 ARE3G9 18220 3100 743 5000 2180 29243 ARE3G10 5000 600 0 0 200 5800

35

56230 27890 6003 5500 14220 109843

126. This shows that along the 142km route of the MV line, 110km (77%) runs through forested land, in which a total of 1.32 km2 of forest will be cleared. This is not a major loss in the context of the total of 30,000 km2 of forest in Bhutan, but efforts should still be made to reduce the physical impacts of this activity by limiting the generation of dust, and prohibiting the burning of waste material. The contractor appointed should be required to:  Leave a covering of grass and/or other naturally occurring low-growing vegetation where possible along the RoW to reduce dust;  Avoid burning waste vegetation and instead leave this material in situ after cutting, to rot down gradually, and discourage re-growth whilst it is decomposing;  Dispose of all cut trees as required by the Forestry department, who will put the timber to beneficial use, thus reducing the cutting of new trees.

127. The rest of the work involves the excavation of a series of pits for the foundations of the poles for the MV and LV lines and transformers. Excavation is physically invasive and can cause other impacts including: air pollution if dust is produced during digging or blown from piles of soil retained on site; pollution of rivers and groundwater if silt is washed from piles of soil during rainfall; and changes in drainage patterns if rainfall or groundwater collects in excavated areas. Most of these impacts should not be significant in this case because:  Only a small quantity of material will be excavated, comprising 0.7-0.8 m3 per pole, and 2266 m3 in total;  Almost all of the excavated material will be replaced and compacted around the pole foundations, so material will only be stockpiled for a few hours;  Poles are located 30-70 m apart (depending on the terrain), so there will be no large concentration of excavated or stockpiled material at any one location;  Contractors will almost certainly conduct excavation in the drier months to avoid the difficult and often dangerous working conditions of the monsoon.

It should therefore not be necessary to apply any mitigation measures to reduce the physical impacts of the excavation.

128. Construction will also affect the landscape, as in some locations the cutting of trees and erection of poles and conductors may be visible for some distance (for example where the MV line runs along a hillside. However this should also be an impact that does not need to be mitigated, because:  The forest itself will provide a good natural screen as in many areas the trees outside the RoW will be taller than the electricity poles;  Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these areas. ii. Impact on Ecological Resources

129. Disturbance along the RoW will be caused during construction period, especially during RoW clearance, excavation and compaction of soil, erection of poles and stringing. Since there will be a permanent opening of the canopy cover, it is expected that there will be some impact on the fauna and avifauna. Wildlife species that can be found in the project sites include Leopard (Panthera pardus), Black bear (Selanarctos thibetanus), Goral (Naemorhedus goral), and Serow (Capricornis sumatraensis), Wild dogs (Cuon alpines), Barking deer (Muntiacus

36

Macaca assamensis). While species like leopards and bears are protected by the Forest and Nature Conservation Act, the exact status of these species is unknown due to lack of concrete data. These species are found in almost every dzongkhag and in some they are considered a threat to the livestock due to predation and even poisoned or trapped. In the project site, farmers reported livestock predation by wild dogs.

130. The removal of trees and other vegetation from along the MV line will also have ecological impacts as it will destroy forest habitat and displace species that are living in these areas. This could affect large and small mammals, birds, reptiles, amphibians, insects and other invertebrates, which might include some of the rare or important or even possibly species that have yet to be recorded, given the unexplored nature of much of the Bhutanese forest. Larger and mobile inhabitants will simply move away to other areas, but some could be damaged or killed during the clearing process. Most of these impacts should not be significant in this case because;

 Providing electricity to rural communities has frequently been shown to deliver major long-term ecological gains that greatly outweigh the short-term losses as people use electricity for cooking and heating instead of firewood, reducing the felling of trees;

 Route alignments were selected along existing farm roads and footpaths where possible, as these areas are already disturbed and degraded to an extent, and are thus unlikely to contain key species;

 Although 1.32km2 of forest will be lost, none of this is located in the protected areas.

 The motility of most animals means that they are very likely to move away in response to the disturbance caused by the felling activity, thus avoiding accidental damage or death.

131. Regardless of these factors, efforts should still be made to reduce the loss of forest where possible, particularly in densely forested parts where the habitats would be more ecologically valuable.

132. The ecological impacts of this work could be magnified if workers are allowed to behave irresponsibly on site, causing unnecessary damage to vegetation outside the RoW and hunting wildlife. The Contractor should therefore be required to impose strict controls on worker behaviour by taking the following action:  Ensure that the only trees to be felled are those that have previously been marked by the Department of Forests1;  Prohibit any hunting, fishing or similar activities by site personnel and enforce this measure strictly;  Provide training to raise the awareness of all site workers and staff on the value and fragility of wildlife and natural habitats, particularly those found in these locations;  If workers are housed in labor camps near the sites, ensure that these are located in areas where no forest clearance is required,  Ensure that labor camps are provided with adequate catering, heating and other services, so that workers do not need to hunt or collect firewood.

1 Before providing the No Objection Certificate that is required as part of the application for Environmental Clearance, staff from the Department of Forests inspect the proposed RoW and apply a paint mark to all trees that the contractor is permitted to fell. 37

133. Excavation can also affect aquatic ecology and fisheries if large quantities of silt are washed into the river during rain, or if work is conducted within the river itself. This should not be the case here however, because:  None of the MV line routes cross large rivers, so there is no requirement for any construction in river-beds;  As noted above, it is very likely that Contractors will excavate in the dry season to avoid the difficult working conditions of the monsoon;  Excavation for the pole foundations is small in scale and dispersed, so there will be no large stockpiles of soil that could create a major point-source of silt pollution;  Almost all of the excavated soil will be replaced into the cavity within a few hours of removal, so any run-off would be short-lived and very small in scale.

134. It should therefore also be unnecessary to mitigate potential impacts on aquatic ecology. iii. Impact on Economic Development

1. Positive impacts 135. The primary positive impact of the project will be access to electricity for lighting, cooking and heating for individual households as well as governmental and religious institutions. A number of secondary impacts are expected to occur as a result of the project. These include positive impacts on the health and lifestyle of local people through the use of clean technology and reduction of exposure to smoke from use of fuel wood and kerosene, and other health risks. They will also save time processing for fuel wood permits from the Forestry office or getting coupons from the Gups office for kerosene.

136. The availability of electricity should bring significant economic benefits to the rural communities, because people will have more time available for work as less time will be spent cutting and carrying firewood, so incomes will increase. People will be able to use electrically powered machinery to process their farm products or to offer services to the community (e.g. rice mills), so again incomes will increase. Others can benefit from the project if employed during the construction period as porters or for clearing of RoW.

137. Once the telecommunication network is available, farmers can use mobile phones, especially during emergencies. With television and radio farmers can update themselves on current events around the country and the world while saving money spent on purchasing radio batteries. If budget is available, the RNR offices, BHU’s, ORC can be equipped with electrical ovens, sterilizers, fridges and other improved medical equipment and therefore provide better health services. Government institutions can also network with their offices in the district headquarters or Thimphu via internet

138. School students will benefit from the project as electrification will enable them to have computers, internet connections and access to online educational materials. Use of electrical stoves can be promoted in schools to reduce demand for firewood as well as exposure to smoke. Students and monks/nuns/old people residing and meditating in the religious institutions can also live cleaner, healthier lifestyles while devoting more time for study in the early hours of the morning and late evenings.

38

2. Impact on private land holdings and agriculture

139. All designated forest in Bhutan is owned by the government, so there will be no need to purchase land for the MV line where it runs through the forest. Some of the un-forested areas are also owned by the government, and will also be provided by the appropriate agency. Some land is however privately-owned (mainly fields and other agricultural land), and the Table below shows the amounts in each gewog, as identified during the route surveys.

Table 5: Length of MV line passing through private land (length in metres)

Total Feeder Chuzhing Kamzhing Tseri Tsamdro Sokshing length ARE3G1 0 7060 0 0 0 7060 ARE3G2 0 510 0 0 0 510 ARE3G3 0 630 0 0 0 630 ARE3G4 0 1100 0 0 0 1100 ARE3G5 0 2,520 0 0 0 2,520 ARE1G6 80 1820 0 0 0 1900 ARE3G7 0 13640 0 0 0 13640 ARE3G8 1000 610 0 0 0 1610 ARE3G9 0 2130 0 0 0 2130 ARE3G10 0 2490 0 0 0 2490 total 1080 32510 0 0 0 33590

140. Where poles cannot be located on government land (these locations and amounts will be determined by surveys conducted by BPC during project implementation), these will have to be located on private land. The general practise for most development project is to acquire private land through the legal mechanism of the Land Act (revised 2007), through which the government provides owners with an equivalent allotment of substitute land in the same dzongkhag. However, for this project, the areas required for pole foundations are so small (around 0.5 m2 each) and residents are so eager to have electricity supplied to their homes, that landowners normally allow BPC to locate poles on their land, without the need for purchase or acquisition. Therefore, land acquisition for the alignment and poles will not be necessary.

141. ADB safeguards policy (2009) requires that no-one should be worse-off as a result of an ADB-funded project, and if this is the case, the Executing Agency provides additional compensation (for loss of crops, structures and other assets) through the mechanism of a Resettlement Plan. This should however not be necessary in this case, because:

 Privately-owned areas are normally not forested so there is no need to acquire and clear a RoW, so the only land to be obtained is small parcels at each pole location;

39

 Areas required are so small and dispersed (approximately every 50 m) that it is very unlikely that a significant proportion2 of the land of any one owner or tenant would be acquired;  Wherever poles are situated on farm land, these will be located at field boundaries as far as possible, to reduce the loss of productive land.  It should therefore not be necessary to provide additional measures to reduce the economic impacts of land acquisition.

 Other features with economic implications that could be affected by construction of the MV and RV lines and transformers are infrastructure (as excavation in villages could damage water supply pipes) and agriculture (as transport of materials to site could temporarily block farm roads, making it difficult for farmers to export produce). These can both be avoided by straightforward consultation with affected local communities to determine the locations of all infrastructures and ensure that these are avoided, and to plan transportation schedules with farmers to avoid any conflict or disruption.

3. Impact on facilities. 142. Excavation works along the alignments may cause disruption to the target village in terms of disruption/damage to water pipes, impede or block access along routes with construction material, or disturbance during sensitive and religious times. To minimize this, the contractor should consult the Gup/Tsogpa and inform them of the intended project implementation process, so that they are aware when materials are being transported along the narrow routes, and facilities like drinking pipes, drainage, religious sites can be avoided. Also, the contractor should respect local tradition and culture and avoid working during religious festivals/times.

4. Aesthetic impacts.

143. Construction will also affect the landscape, because in some locations the cutting of trees and erection of poles and conductors may be visible from greater distances from across the valley. Visual impacts are generally considered significant where they affect large numbers of people, and that will not be the case here because of the remote nature of these areas.

144. This should also be an impact that does not need to be mitigated, because in many areas the trees outside the RoW will be taller than the electricity poles and because the surrounding forest itself will provide a good natural screen for the electricity poles. To ensure that the MV lines do not visually impair the beauty of the Lhakhangs and their surroundings, these should be aligned as close to the border of the forest and agricultural fields.

iv. Impact on Social and Cultural Resources

1. Impact on Cultural and Religious sites

145. In the project site there are a number of religious sites in different villages. The monasteries hold religious and historical texts, sacred murals, paintings and statues as well as

2 ADB policy on Involuntary Resettlement considers loss of land to be significant if it amounts to 10% or more of the total land holding of any one owner. 40 valuable offerings made by the public. Electrification of these important structures will improve the security of these sacred facilities as miscreants will be less confident of committing robberies or vandalising them due to the increased risk of being caught. It will also benefit visitors, monks and senior citizens or caretakers residing there in terms of lighting, heating and cooking.

146. In order to minimize impacts on these sites, surveyors were instructed prior to conducting field surveys to consult closely with local representatives so that distribution lines could be aligned to avoid impacting them. During construction the contractors should also consult closely with the local caretakers so that construction activities do not impact or hinder religious activities

147. The main hazard to people from the operation and maintenance of the completed RE system is the risk of electrocution. This is a danger to i) Rural consumers who are not highly educated and are generally unaware of the dangers posed by electricity; and ii) BPC workers when repairing lines or components.

2. Social impacts.

148. The MV lines will be located in remote uninhabited areas, so it is very unlikely that construction will affect any locations or features that are of social or cultural importance, such as heritage sites, temples, or more modern facilities such as schools or clinics.

149. However the transformers and LV lines will be built within and near villages, so there could be impacts on inhabitants, their activities and locally important locations. As the work will involve excavation then the main impacts are likely to arise from construction noise, dust, visual intrusion, impeded access, and the presence of migrant workers. These are not expected to be major impacts, because: i) Most villages contain between 2-20 households, so the work should be short-in duration, being completed in a few weeks only; ii) Excavation will be very localized, affecting areas of 1 m2 roughly every 30-70 m, so the mounds of soil should not greatly impede access or produce significant dust; iii) In any one village work will probably be conducted by one or two small teams of 5- 10 workers each, so individual locations will not experience a large influx of foreign workers; iv) People will tolerate short-term temporary disruption if (as in this case) they are aware that they will gain significant benefits once the work is completed.

150. Efforts should still be made to reduce the level of disruption where possible, and to achieve this, the Executing Agency (DoE) should:  Consult all affected communities in advance to inform them of the purpose, nature, duration, extent and timing of all work in and around their village;  Determine the location of all sites that are of local social or cultural importance (temples, shrines, meeting places, etc) and ensure that no poles are located in the vicinity, and no conductors are strung overhead;  Consult the custodians of all social and cultural facilities that are to be electrified as part of this project (monasteries, schools, health centres) and plan the work to avoid sensitive times (such as key dates in the religious calendar, examination periods, etc).

41

151. The presence of migrant workers in communities can be disruptive if the workers do not follow local norms of behaviour, and if they bring other problems such as socially or sexually transmitted diseases. Such difficulties tend to be greater in rural areas where existing social and cultural bonds are stronger than in cities, and where inhabitants have less experience of people from other cultures. Migrant workers are often housed in labour camps, which can create further problems both for workers and host communities if they are inadequately equipped and serviced, creating dissatisfaction and unrest, and environmental and public health problems. Importing workers also deprives local people of the socio-economic benefits of obtaining temporary employment in construction workforces, which can be significant for poor rural communities.

152. In Bhutan RE Contractors prefer to employ local people because they are more accustomed to the difficult terrain and are more physically able than foreign labourers, who are normally imported from India. However it is generally still necessary to import some workers because the scattered rural population in Bhutan means that not enough people are available, particularly at times of intensive agricultural activity, when rural Bhutanese prefer to work in their fields.

153. These are complex issues, which need to be addressed by a range of measures. Contractors should first be required to ensure that they employ as many people as possible from communities in the vicinity of the construction sites, so that at least some economic benefits are directed to those residents who are most affected by the work.

154. If it is still necessary to employ foreign workers, then contractors should ensure;  that they are migrant workers housed in adequate, and properly cleaned camps with safe drinking water and temporary sanitation facilities away from water sources;  accommodation camps should be located in areas where no clearance of vegetation is required;  Solid waste must be collected and buried offsite  Workers must be made aware of required behavior when interacting with host communities;  Workers must be prohibited from hunting, fishing and logging;  Once construction is complete, campsites must be cleared, all temporary infrastructure to be demolished and all materials removed and the site restored.

155. Contractors should also protect the health of workers and the host community by controlling the spread of disease, and providing treatment where necessary. Contractors should therefore be required to:  Screen workers at their point of origin for the more virulent and contagious diseases, including HIV/AIDS, TB, Malaria, Swine flu and Bird flu or any other current disease;  Conduct regular screening of all workers for these and other infections;  Provide access to medical treatment for workers at the dzongkhag hospital if necessary;  Distribute pamphlets or posters to raise the awareness of workers and host communities of the risks of the various types of socially and sexually transmitted disease, and ways of avoiding infection;  Implement practical measures to reduce infection, for example by providing condoms free to workers.

42

156. Clearance of the RoW is an activity in which there is a significant element of danger, particularly to workers, but also to inhabitants of villages, should they stray into the vicinity. Contractors will be required to prepare and implement a Health and Safety Plan covering all elements of construction. This will include measures that are common to most construction sites, such as:  Excluding the public from the site;  Ensuring that workers are provided with and use Personal Protective Equipment;  Health and Safety Training for all site personnel;  Documented procedures to be followed for all site activities;  Maintain accident reports and records;

157. In this case the H&S Plan should also include measures to reduce risks specific to tree felling, such as:  Ensuring that all trees and branches fall into the RoW when cut;  Liaison with all local communities to inform them of the nature, extent and timing of all clearance work and to raise awareness of the dangers.

C. Environmental effects during Operation and Maintenance

i. Impact on Physical Resources

158. Maintaining the RoW by removing overhanging branches and high-growing vegetation from beneath the lines will have very little impact on the physical environment. In fact the general approach of BPC in allowing low-form vegetation to re-grow in the RoW will have benefits in reducing dust and improving soil cohesion and conservation, and helping to prevent landslides that are a risk throughout Bhutan during the monsoon rains.

159. Even though the repair of faults may involve excavation of new foundations and erection of new poles and conductors, this should also have few physical impacts as repairs generally affect short lengths of line, so the work is normally very limited in extent. Even where poles are brought down by landslides it is very rare for these to affect more than two or three poles, which can be repositioned without causing major physical changes. Similarly repairs of the LV lines in villages will be small in scale and thus unlikely to cause physical impacts.

160. Transformer maintenance can contaminate land and water if oil is spilled, so BPC staff should follow their established procedure carefully to prevent this, and should remove and dispose of any contaminated soil in a sealed drum if a spillage occurs.

ii. Impact on Ecological Resources

161. Maintaining the RoW and repairing faults along the line will have no major ecological impacts as the work is very small in scale and infrequent, and involves few changes to the existing situation. The practice of allowing some re-growth of vegetation along the RoW will also have ecological benefits as it will allow plants and animals to re-colonize the area. Because the forest canopy is now open in these areas the species will be different from those that were originally present, which could be seen as a further gain as this will increase the diversity of Habitats.

43

162. The major ecological benefit will occur over the longer term, as the availability of electricity in these villages reduces the felling of trees for firewood. Current estimates are that each rural household in Bhutan consumes around 3.5 kg of firewood per person per day3, so these ecological gains should become highly significant over time and will greatly exceed the short-term losses from the original clearance of the RoW.

iii. Impact on Economic Development

163. The routine maintenance of the RoW will not have economic impacts as it will not affect agricultural areas, or farm roads used for transporting produce. If a line failure requires the repositioning of poles, it should not be necessary to purchase land for the new foundations, as owners are very likely to donate the very small amounts of land required (1 m2 per pole) in order to restore the electricity supply. New foundations will be dug close to the old ones, so wherever possible land from the same owner should be used, so that the previously used area can be returned.

164. Power outages will have negative economic impacts as people will be unable to use machinery they have installed to diversify their means of livelihood, for the period in which the system is shut down. BPC should therefore keep such periods to a minimum, by responding to line problems rapidly; and repairing faults rapidly and effectively.

165. The Performance-Based Incentive schemes within BPC, whereby annual salary increments and bonus payments are linked to the performance of the electricity supply system, should improve the efficiency of the service.

iv. Impact on Social and Cultural Resources

166. The main hazard to people from the operation and maintenance of the completed RE system is the risk of electrocution. This is a danger to i) Rural consumers who are not highly educated and are generally unaware of the dangers posed by electricity; and ii) BPC workers when repairing lines or components.

167. BPC have procedures set down in Operation and Maintenance (O&M) manuals, which describe how all work on distribution lines is to be conducted. They also have Health and Safety (H&S) Manuals, which describe the personal protective equipment that is to be provided (including safety helmets and belts for climbing poles), plus emergency procedures, etc. However there have been a small number of recent fatalities, which suggest that the systems are not functioning adequately. Some measures for BPC to undertake include:  Ensure that staff understand and comply with the BPC O&M and H&S manuals and procedures;  Continue providing regular training for all BPC operatives to raise awareness of the dangers of the work being conducted, the equipment that is to be used, and the procedures that must be followed;  Conduct regular supervision of field workers during both RoW clearing and repair of faults;  Conduct regular management reviews of safety records, and follow-up with remedial action where necessary; and

3 FAO (2001): National Strategy for Stoves and Other Alternative Energies, Project No BHU/99/005 44

 Continue to conduct community education programmes to raise the awareness of all target households before and after they are connected to the grid regarding the dangers of electricity, and the correct manner in which house systems should be used.

168. If these actions are implemented thoroughly, then the RE system should function without major accidents or fatalities from misuse or inappropriate operation. There should then be a wide variety of social benefits for the target households and their wider communities from the provision of electricity already discussed previously. Together these should greatly improve the health, wellbeing and quality of life of citizens and the communities, and greatly increase the overall social capital of these rural areas.

169. Once electricity is provided, people rapidly become used to and even become dependent upon the service and the new way of life it supports, and are not greatly tolerant of interruptions in the service. This reinforces the need for BPC to take the actions recommended above in order to minimise power outages by ensuring that the maintenance procedures (RoW clearing, routine checks of lines and transformers) are conducted regularly and diligently; and respond to faults rapidly and ensure that repairs are conducted quickly and effectively.

170. Any disturbance or disruption that residents may experience from the re-erection of poles or replacement of conductors in the villages will be viewed as very minor when compared to the inconvenience of being without electricity, so there should be no need for mitigation.

45

VI. ANALYSIS OF ALTERNATIVES

171. A number of alternatives were considered for the project. These included a) the no-build alternative, and b) use of solar energy (Photovoltaic panels) and c) on-grid electrification. Each alternative is discussed below.

a. Alternative 1. 172. Maintaining the status quo of not undertaking the project (i.e. the no-build alternative), there will be no ecological impact on the environment or biodiversity from this project. However, the total number of households electrified will remain less than 50%, and the government will fail to achieve its target of electricity for all by 2013.

b. Alternative 2. 173. Using solar energy (photovoltaic panels) is a better alternative than the ‘No project” one, in terms of development in the rural areas. There are a number of constraints with this alternative; for instance a) it can only be used for lighting purposes, so firewood consumption for heating and cooking will still remain high, b) high maintenance cost for repair of parts and c) need for technical knowledge and low durability.

c. Alternative 3. 174. Provide on-grid electrification. This is the alternative that is proposed by this project. Through this all target villages will be provided with electricity from the existing grid system. The project is expected to significantly reduce demand for firewood, as this is the primary source of heating and lighting in the remote communities. This alternative will contribute positively to improving the lives of the target communities through reduced exposure to smoke, improvement in living conditions, increased communication via use of mobiles and opportunities for seeking alternative livelihood options. Local government institutions like BHU, ORC, Schools, RNR centres and Religious institutions will also benefit through reduced time and money spent on sourcing firewood from local communities, as well as increase in accessibility to information through various media sources, internet and improved communication. Students will have extra time to study during early mornings and evenings.

Table 6: Comparison of alternatives Parameters No electricity Use of solar energy On grid Rural Electrification Economic cost Cost to farmers include cost - maintenance cost depends on -High cost to government of kerosene, location of households and -Cost of in house electrification access to repair facilities -Lack of technology for repair Developmental Village/gewog considered -Community is still considered -Community is considered impacts & underdeveloped ‘underdeveloped’ ‘developed’ people’s -Use limited to lighting purpose -Can explore other livelihood perception alone alternatives such as rice mills, Social benefit Household still exposed to -Clean and renewable energy Beneficiaries include smoke, dirt, and increasing -Benefit restricted to lighting only -Households distance/time spent in fuel -Schools wood collection -Government & Religious facilities Environmental Yearly increase in fuel wood -Yearly increase in fuel wood Main impacts are impacts consumption consumption per family -Impact from Right of Way of -Improper disposal of battery Distribution line may cause heavy metal pollution -Localized impact on endangered especially in rural areas wildlife

46

-Aesthetic impacts -Aesthetic impacts

175. The third alternative ‘providing on-grid electrification for the proposed villages ‘ is the most feasible in light of the easy availability of hydropower in the country, the positive environmental benefits, and most importantly because this is what the local communities prefer. The first alternative is not feasible because electricity is included as a measure of development in a village and therefore is always given high priority in the list of developmental activities for any gewog plan. It is impossible for the government to overlook this demand especially since the country is a major generator of Hydropower energy. While there will be no environmental cost from this alternative, with increasing population it is expected that the demand for fuel wood will increase each year, putting very heavy pressure on the already dwindling forest resource.

176. The Solar PV system involves the utilization of renewable and clean energy, but it is considered a temporary measure for those villages where the cost of providing electricity is too high for the moment. The utility of the solar system depends on the location of the target villages. For instance, if villages are located close to access roads, then repair and maintenance is easy compared to remotely located villages where there are no such facilities available.

177. Based on the above comparisons the first two alternatives are no longer under consideration. However, there are still some villages that are too remote and it is too expensive or technically very difficult to provide on-grid electrification. In such cases, these villages will be provided off-grid electrification.

47

VII. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION

A. Project stakeholders

178. Most of the main stakeholders have already been identified and consulted during preparatory phase of this project. Primary stakeholders are  Residents of 1568 households that will be electrified by this subproject;  Residents and users of 78 facilities that will be electrified by this subproject;  People who work on agricultural land that will be crossed by the MV lines;  Owners or users of land that is acquired for the erection of poles for MV or LV lines; but who are not beneficiaries

179. Secondary stakeholders are:  DoE as the Executing Agency;  BPC as the Implementing Agency.  Department of Forest as the custodian of the government reserve forest  NEC as the agency granting Environmental Clearance; and  Dzongkhag Administration under whose jurisdiction the sub-project is being implemented; and  ADB

B. Consultation and disclosure to date

180. In order to involve various stakeholders during the preparation of the EIA, consultations were held with the Project Management Office at Thimphu and the Rural Electrification Staff at Mongar.

181. With the permission of the Dzongkhag, two public consultations were held in Tsamang gewog, at Tsamang and Banjar on the 18th and 19th of June, 2009. In total there were 52 participants. During the public consultation, a presentation was given on the aim of the subproject and the benefits it will bring, together with the likely impacts and the ways in which they will be mitigated. Participants were invited to discuss their views and concerns, which were then incorporated into the EIA. Appendix 2 contains a summary of the meeting

Table 7: Details of public consultation conducted

Date Location Total participants 18th June, 2009 Tsamang village 11 19th June, 2009 Banjar village 41

48

Table 8: Summary of public consultation Issue Participant’s opinion, comments and suggestions General perception about the project Participants said that they were very happy to hear about the project as they were beginning to feel left out with their neighboring villages included under one project or the other. Their village lies opposite many electrified villages and have envied them. Therefore they are very excited about the project and hope to enjoy the benefits of electrification like other villages The only request they had was that the project be implemented as soon as possible. Benefits of the electricity and its project The women were very happy as they can live in a clean and healthy environment and also will not have to waste time carrying firewood. Some are interested in weaving in the evenings.

Another benefit is improved communication as their villages are within the BMobile network but due to lack of electricity they cannot charge their phones. Disadvantages of the electricity and its project- Participants did not think that there were any negative impacts that could occur from the project, apart from cutting of trees which is unavoidable due to location of their villages. Public consensus Participants said that they have all signed the public consensus forms and do not anticipate any problems with giving a small portion of their land for the project as the entire village will benefit from it. Project location inside the Park There is a park office in Tsamang where permits for firewood and timber are granted. Participants feel that since their villages lie in the periphery of the park, any disturbance to the park will be minimal as endangered species are not usually found as the forest surrounding the villages are degraded to some extent due to use by villagers for collection of firewood, leaf litter. The farm road that is under construction will also make transportation easier for RE materials. Instead, residents feel that the project will contribute to conservation as each household will use less firewood and forest will be undisturbed. Issues and Queries Residents wanted to know how their village had been excluded from the previous Rural electrification project. The Mangiap and the BPC staff explained the process that was used for selection of villages. There were a few queries on internal wiring of the houses, supply of meters, and payment of electricity bills, which was clarified by the BPC representative. He also explained that BPC will again conduct public consultation for awareness once the project was approved and ready for implementation.

182. This IEE will be disclosed to the public by making it available at RED offices in Mongar and the project as a whole will be disclosed to a wider audience via the ADB website.

C. Future consultation and disclosure

183. DoE/BPC will extend and expand the consultation and disclosure process significantly during implementation of the project. They will conduct a wide range of activities in relation to all subprojects in each dzongkhag, to ensure that the needs and concerns of stakeholders are registered, and are addressed in project design, construction or operation where appropriate. The program of activities will be developed during the detailed design stage, and is likely to include the following:

49

184. Consultation during pre-construction stage:  Focus-group discussions with affected persons and other stakeholders (including women’s groups and NGOs) to hear their views and concerns, so that these can be addressed in subproject design where necessary;  Structured consultation meetings with the institutional stakeholders (government bodies such as Department of Roads, NEC, Department of Forest) to discuss and approve key aspects of the project;

185. Consultation during construction:  Public meetings with affected communities to discuss and plan work programmes and allow issues to be raised and addressed once construction has started;  Smaller-scale meetings to discuss and plan construction work in individual villages to reduce disturbance and other impacts, and provide a mechanism through which stakeholders can participate in subproject monitoring and evaluation;

186. Project disclosure:  Public disclosure meetings at key project stages to inform the public of progress and future plans.  Formal disclosure of completed project reports by making copies available at the RED field office and the BPC head office.

50

VIII.GRIEVANCE REDRESS MECHANISM

187. The target gewog that will be affected by the project has a total of 1568 households and 78 facilities.

188. The process of including these villages in the Project is pretty straightforward. Keeping Rural Electrification Masterplan 2005 as the reference, the un-electrified villages were included in the project scope based on the Dzongkhag’s priorities. The list of the targeted households was then provided to BPC for implementation. This preliminary list of non-electrified villages was further segregated into two, those that could easily be connected to the grid and those that were too far in terms of distance, or due to technical and economic reasons.

189. Using the list of villages selected on grid electrification, BPC fielded surveyors to conduct field studies to finalize which distribution lines could actually be included in the target areas. Criteria used for this include a) distance of the village to the nearest feeder, b) number of houses to be electrified, c) accessibility and means of transportation d) location of the villages (environmental sensitivity), e) topography, and f) material cost, transportation and head loading costs. Based on the field data, the list of distribution lines, number of beneficiaries, along with the technical route survey to ascertain length of MV and LV lines, number of substations, transformers etc. was finalized.

190. MV lines cross mainly forested areas but these routes have been selected to run along existing access routes, tracks and pathways where possible, because in these areas there has already been some clearance of trees and other vegetation, so this reduces the amount of new felling required. The Table shows the amounts along each distribution line, as identified during the route surveys.

Table 9: Length of distribution lines and affected persons/beneficiaries

Villages Feeder Sub MV length lVLength Total Name Feeder (km) (m) Consumer ARE3G1 15 36.76 89791 38 487 ARE3G2 0 1.76 5610.9 1 12 ARE3G3 0 0.93 5264.7 1 20 ARE3G4 5 8.07 25145 12 119 ARE3G5 15 20.91 73072 27 311 ARE1G6 4 9.87 22313 6 86 ARE3G7 11 8.67 21369 37 82 ARE1G8 0 6.03 10653 4 50 ARE3G9 2 40.8 59959 6 437 ARE3G10 2 8.32 11553 5 42 total 54 142.13 324730 137 1646

51

Table 10: Total length of feeder through government and private land (length in metres) government private Feeder land land Total ARE3G1 29700 7060 36760 ARE3G2 1250 510 1760 ARE3G3 300 630 930 ARE3G4 7000 1100 8100 ARE3G5 18480 2,520 21000 ARE1G6 7770 1900 9670 ARE3G7 4410 2130 6540 ARE3G8 5890 1610 7500 ARE3G9 28000 13640 41640 ARE3G10 5800 2490 8290 Total 109843 33590 142190

191. The total length of all the distribution lines is 142km of which only 33.6km passes through privately-owned (mainly fields and other agricultural land) land in 141 villages, which amounts to 23% of the total line length. These areas that are traversed are so small and dispersed (approximately every 50 m) that it is very unlikely that a significant proportion4 of the land of any one owner or tenant would be acquired;

192. Along the distribution line it is estimated that 2840 poles will be constructed, of which there will be 2200 poles on government land and 640 poles on private land. Where the lines cut across private land, poles will be located on field boundaries where possible, to reduce the loss of productive land. The areas required for pole foundations are so small (around 0.5 m2 each) and residents are so eager to have electricity supplied to their homes, that landowners normally allow BPC to locate poles on their land,without the need for purchase or acquisition.

193. A key element of the national Environmental Clearance application process is the provision of signed No Objection Certificates (NOC) from stakeholders that are specified in the guidelines, including all affected households, Public consultation and participation was sought beginning from project planning and route identification phase wherein the local village representatives were called upon by the District authorities to conduct awareness on the prospective project and to seek the consensus from potential affected persons.

194. In the past, any grievance against RE projects have been approached personally to BPC office or forwarded through the Gup to the Dzongkhag and BPC office and resolved informally through mutual agreement wherever possible. In other cases, where the APs are not satisfied the case has been forwarded to the court for a resolution. There have been instances in the past when the APs put their grievances after the lines are constructed and commissioned. In such cases, it was very difficult for BPC to realign the distribution lines because shifting a pole required realigning 4 to 5 poles both up-stream and down-stream. Due to the high cost of the adhoc and unbudgeted realignment, the BPC has asked APS to do it at

4 ADB policy on Involuntary Resettlement considers loss of land to be significant if it amounts to 10% or more of the total land holding of any one owner. 52 their own cost. To avoid such complications in the future, BPC now conducts awareness program during the preconstruction period.

195. ADB safeguards policy (2009) requires that no-one should be worse-off as a result of an ADB-funded project, and if this is the case, the Executing Agency provides additional compensation (for loss of crops, structures and other assets) through the mechanism of a Resettlement Plan. This should however not be necessary in this case, because privately- owned areas are normally not forested so there is no need to acquire and clear a RoW, so the only land to be obtained is small parcels at each pole location. BPC field staff has been clearly instructed to ensure that where poles are situated on farm land, these are located as field boundaries as far as possible, to reduce the loss of productive land. Besides, the distribution substations are pole-mounted for all RE works minimizing private land usage.

196. A memorandum of Agreement cum Application for Rural Electrification was prepared between the BPC and the beneficiaries through the local government (village headman/Gup) and forwarded to the BPC after being endorsed by the Dzongkhag administration. This agreement states that the applicants are aware of the ARE project and would like to be included for the electricity service connection as potential consumers. The applicants agree to provide the Right of Way for the construction, operation and maintenance of electricity lines passing through their private land, free of cost to the BPC as they are the primary beneficiaries. The BPC should avoid traversing existing khimsa (where the house exists) at all costs and try to avoid the use of cultivated land as much as possible.

197. Because the impact on the private land of any individual household is so small with no impact on infrastructure, RE schemes are not expected to have major negative socio-economic impacts as there will be no need for land acquisition or resettlement. Wherever possible, the project will avoid or minimize traversing private land by identifying possible alternative routes. For the loss of Crops and Fruit trees if any, the BPC will compensate the APs at the prevailing government approved rate, which shall be built into the project cost. A copy of the Memorandum of Agreement is in the Annex.

Complaints and Grievance Redress mechanism

198. During the process of project implementation, stakeholders may file complaints if they are not happy with the alignment of the distribution line, pole, substation or service centre locations. Any person who believes that his/her land or structure has been expropriated or altered and believes that their private land, house, or agricultural crops are being unfairly affected by the project will be able to express their grievances through a grievance redressal mechanism that will be instituted under this project. Through this mechanism the Affected Person may submit their grievance to the Dzongkhag office, which will record the grievance and ensure that all complaints and resolutions are properly documented and also available for review for monitoring purposes. The Dzongkhag office will conduct the necessary field visit to verify and assess the grievance/complaint, determine the validity of the grievance, and resolve the grievance within 1 month of receipt of the complaint.

Grievance Redress Procedure

199. The grievance redress procedure will be as follows;

53

1. Each grievance must be dealt with within a two weeks of receipt of complaint from the AP. 2. The necessary field verification/assessment will be conducted and the AP informed of a decision in writing within 4 weeks/28 days 3. Issues may be resolved amicably through third party arbitration and negotiation but If APs are not satisfied they can take recourse to the civil court if he/she so desires, or resolve the issue by taking it to next level of Grievance Redress, which is the National Land Commission (NLC), the highest body to approve land replacement and compensation allotments in the country.

200. During Project implementation, the BPC will ensure that APs are briefed on the grievance redress mechanism and procedures.

201. In the unlikely case of unforeseen environmental impacts, any grievances regarding environmental impacts will be submitted to the Dzongkhag Environmental Officer and BPC, who will conduct a field assessment of the situation and recommend appropriate mitigation measures to be implemented by the BPC. Where the Environmental Officer unable to take a decision, the case will be referred to the National Environment Commission for advice on necessary corrective measures. Such grievances will also be documented for monitoring purposes. All environmental issues must be resolved within 21 days of receiving the complaint.

54

IX.ENVIRONMENTAL MANAGEMENT PLAN

A. Summary of environmental impacts and mitigation measures

202. All the potential adverse impacts of the project have been identified and discussed in the previous chapters. All the potential adverse impacts of the project have been identified and discussed in the previous chapters. The EMP table outlines potential environmental impacts and mitigation measures proposed to reduce these impacts to acceptable levels. It also identifies the agency responsible for a) planning and implementation as well as b) supervision and monitoring, for each phase of the project.

203. Taking off from the first table, the second table then describes: (i) mitigation measures, (ii)parameters to be monitored, (iii) location, (iv) measurement method, (v) frequency of monitoring, (vi) responsibility (for both mitigation and monitoring), and (vii) cost of monitoring. Most of the mitigation measures are fairly standard methods of reducing the impacts of RE schemes (preventing damage outside the RoW, providing suitable living conditions for imported workers, etc), and experienced domestic contractors should be familiar with most of the requirements.

B. Environmental Monitoring Plan

204. During the construction stage all mitigation activities are the responsibility of the Construction Contractors employed to build the infrastructure. Responsibility will be assigned via the contracts through which they are appointed (prepared by RED during the detailed design stage), so they will be legally required to undertake the necessary actions. Mitigation when the system is operating is the responsibility of the Electricity Services Divisions (ESD) as the agency responsible for maintaining the system in working order.

205. A senior Environmental Officer (EO) will be responsible for implementing the Environmental Monitoring Plan in the construction stage, and reporting the results to RED, with recommendations for remedial action if measures are not being provided or are not protecting the environment effectively. The senior EO will be assisted by more junior EOs who can make many of the routine observations on site. Post-construction/Operation monitoring will be conducted by BPC.

206. Monitoring of such measures normally involves making observations in the course of site visits, although some require more formal checking of records and other aspects. There will also be some surveys of residents and workers, to review those measures that are aimed at ensuring their safety and wellbeing. Based on the EMP, the environmental officer, BPC will prepare the necessary monitoring checklist and surveys for themselves and ESD staff to follow during their site visits during the construction and operation and maintenance phase. Monitoring may be conducted every two weeks during the construction phase and if field inspections and monitoring reveal good environmental performance, the frequency may be reduced. Conversely, if the opposite occurs, then the matter will be reported to the Environmental Officer who will in turn direct the Contractor to take necessary mitigative measures, and monitoring frequency will be stepped up.

55

Table 11: Environmental Impacts and Mitigation Project Activity Potential Environmental issues Management/Mitigation Measures Responsibility Planning and Supervision and Monitoring Implementation Pre-construction stage Design and Impact due to location of target 1.Route selection in close consultation with Department of Forest, RED, BPC Requires ‘No Objection’ Clearance location of three villages in the biological corridor BPC field staff to avoid sensitive areas; DoE from 33kV Distribution between Sakteng Wildlife 2. Route selection approved by National Environment Commission i...Park Management/Department lines Sanctuary and Khaling Wildlife and District Authorities of Forest Sanctuary 3. Align routes alongside farm roads and footpaths where possible, ii.District Environmental Officer alongside forest edges where habitats are already degraded to an iii.National Environment extent, and will involve minimum tree felling to minimize design Commission effect. iv.District Administrative Approval v.Public Consensus from local residents

Construction Clearing of RoW Removal of forest cover in 1.Ensure that only those trees marked by the forestry staff are Contractor, BWS, Environmental Officer, BPC along Distribution biological corridor felled BPC District Env. Officer line 2.Follow standard BPC procedures and practices in clearing ROW NEC 3. Explore possibility of planting low growing vegetation in RoW 4. Reforestation or afforestation to make up for forest cover loss Workers could damage species & 1.Mark RoW boundary & prohibit cutting outside; Contractor Environmental Officer, BPC Habitats outside RoW 2.Only fell trees that have been marked by Forestry staff; 3.Prohibit hunting or fishing by workers and enforce strictly; 4.Train workers in importance of wildlife and habitats; 5.Locate labor camps where no forest clearance is needed; Impact on private land holdings 1.Route the distribution lines along edge of villages Contractor Environmental Officer, BPC 2.Where routes cross private land, avoid alignments too close to houses or cutting through the centre of fields Risk of forest fires if cut 1.Leave cut material to rot down in situ and do not burn; Contractor Environmental Officer, BPC vegetation is burnt 2.Leave a covering of grass & other low vegetation in RoW; 3.Dispose of trees as required by Department of Forestry Delivery of RE Air pollution from vehicular Minimize number of deliveries through timely scheduling Contractor Environmental Officer, BPC materials to drop movement off points Carriage of materials to site could Consult Gup and farmers when transporting material Contractor Environmental Officer block access Excavation at Dust may blow from cleared Avoid using large machinery, Manual excavation at pole sites and pole sites areas minimize disturbance at excavated sites,

56

Effect on local drainage and soil Locate poles at a minimum distance of 30 m from rivers, and Contractor Environmental Officer erosion construct these on stable ground Excavation for poles could Consult community to identify and avoid infrastructure Contractor Environmental Officer damage water pipes in villages Work in villages may create 1.Inform communities of work in advance; Contractor Environmental Officer, BPC noise, dust & impede access 2.Identify sites of local significance; locate no poles nearby; 3.Consult custodians of facilities (monasteries, nunneries, schools, clinics, etc) and avoid working at sensitive and religious times; Social and Economic benefits if local people Employ as many local residents as possible in workforce Contractor Environmental Officer, BPC cultural impacts are employed Importing foreign workers can 1. Ensure imported workers are provided with housing that has Contractor Environmental Officer cause environmental and social ample toilets, proper drainage and treatment for sewage. problems at labour camps and in 2. Collect solid waste weekly and bury offsite. host community 3. Instruct workers on required behavior in host community and prohibit them from hunting and fishing. 4. Camps must be cleaned up and restored after project is completed. Diseases can be introduced into 1.Initial screening of workers for HIV/AIDS, TB, malaria, swine flu, Contractor Environmental Officer host communities from social and etc.; sexual contact with imported 2.Facilitate access to the nearest Health facility for check up; workers 3.Raise worker/community awareness of risks of socially & sexually transmitted disease; 4.Practical measures, e.g. free condoms for workers; Workers and villagers are at risk Prepare and implement a site Health and Safety Plan that includes Contractor Environmental Officer from accidents on site measures to: -Exclude the public from all construction sites; -Ensure that workers use Personal Protective Equipment; - Provide Health & Safety Training for all personnel; - Follow documented procedures for all site activities; - Keep accident reports and records; - Inform local communities about the work and dangers Impact on private land and Conduct awareness programs/meetings BPC Environmental Officer infrastructure Grievance Redress mechanism in place

57

Project Activity Potential Environmental issues Management/Mitigation Measures Responsibility Operation and Maintenance Provision, People cannot use new electrical Field personnel should report power outages to the ESD and repair faults ESD BPC Operation and machines during power cuts so quickly and effectively maintenance of income may suffer new RE system Consumers are at risk of 1.Train and supervise BPC field operatives to ensure that they check RED, BPC BPC electrocution if they do not house wiring carefully and reject if deficient; understand the dangers of 2. Public education to raise villagers’ awareness of dangers of electricity electricity and how to utilize the system safely. BPC workers are at risk if they do 1.Follow BPC O&M and H&S manuals and revise these manuals if RED and BPC not follow BPC procedures when necessary to increase safety of workers; ESD, BPC clearing RoW or repairing faults 2.Regular training of BPC workers to raise awareness of dangers and working procedures to be followed; 3.Improve supervision of field workers; 4. Regular management reviews of safety record, with remedial action where necessary. People will not be very tolerant of 1.As above: repair faults quickly and effectively; RED and BPC power cuts once they become 2.Conduct system maintenance regularly and diligently ESD, BPC used to the benefits of electricity

58

Table 12: Environmental Management Plan

Potential impacts Mitigation measure Parameters to Location Method Monitoring Responsibi Cost be monitored Frequency lity Pre-construction Impact due to location of 1.Route selection in close consultation with Department of Forest, EC clearance MV lines Route selection n/a RED, n/a target villages biological BPC field staff to avoid sensitive areas; process and BPC corridor 2. Route selection approved by National Environment Commission EC Clearance MV lines Field n/a NEC n/a and District Authorities process investigation by Environmental officer 3. Route should be selected so that clearance along forested areas EC clearance MV lines Mapping of field n/a RED, n/a are avoided wherever possible; Where there is no alternative to process information BPC routing lines through forest, align routes alongside farm roads and footpaths where possible, alongside forest edges where habitats are already degraded to an extent, and will involve minimum tree felling. Construction Removal of forest cover in 1.Ensure that only those trees marked by the forestry staff are felled No.of MV lines Site Two weeks EO, BPC Include protected area 2.Follow standard BPC procedures and practices in clearing ROW violations Observations d in CB Explore possibility of planting low growing vegetation in RoW Revegetation MV lines Site Two weeks EO, BPC n/a of RoW Observations Workers could damage 1.Mark RoW boundary & prohibit cutting outside; No. of MV lines Site Two weeks EO, BPC n/a species & Habitats 2.Only fell trees that have been marked by Forestry staff; violations Observations outside RoW 3.Prohibit hunting or fishing by workers and enforce strictly Number of Camp sites Site Observation Monthly EO, BPC n/a illegal reports Surveys 4.Train workers in importance of wildlife and habitats; Number of Labour Contractor Monthly EO, BPC Include illegal reports camps records d in CB

5.Locate labour camps where no forest clearance is needed; Location of Labour Site Monthly EO, BPC Include camps camps observations d in CB 6.Provide adequate food supply so workers do not need to hunt or Illegal Labour Site Monthly EO, BPC Include fish activities camps observations d in CB Impact on private land Route feeders along edge of villages, avoid locating poles in the Feeder MV lines Site Monthly EO,BPC n/a holdings centres of fields alignment observations

59

Risk of forest fires if cut Leave cut material to rot down in situ and do not burn; No. Of fires MV lines Site Two weeks EO, BPC n/a vegetation is burnt Leave a covering of grass & other low vegetation in RoW; observations Dispose of trees as required by Department of Forest Disposal of MV lines Site Two weeks EO, BPC Include trees observations d in CB Delivery of RE materials Minimize number of deliveries through timely scheduling No. Of Drop off Site Monthly EO, BPC n/a to drop off points- Air deliveries points observations pollution from vehicular movement Carriage of materials to Consult Gup and farmers when transporting material No. Of MV and LV Site Monthly EO, BPC n/a site could block access consultations lines observations; Village survey Excavation at pole sites- Avoid using large machinery, Manual excavation at pole sites and Site MV lines Site Monthly EO, BPC n/a Dust may blow from minimize disturbance at excavated sites, observations observations cleared areas Effect on local drainage Locate poles at a minimum distance of 30 m from rivers, and MV lines Site Monthly EO, BPC n/a and soil erosion construct these on stable ground observations Excavation for poles could Consult community to identify and avoid infrastructure No. Of MV and LV Site Monthly EO, BPC n/a damage water pipes in consultations lines observations; villages Village survey Work in villages may 1.Inform communities of work in advance; MV and LV Site Monthly EO, BPC n/a create noise, dust & lines observations; impede access Village survey 2.Identify sites of local significance; locate no poles nearby; MV and LV Site Monthly EO, BPC n/a lines observations; Village survey 3.Consult custodians of facilities (monasteries, nunneries, schools, MV and LV Site Monthly EO, BPC n/a clinics, etc) and avoid working at sensitive and religious times; lines observations; village survey Economic benefits if local Employ as many local residents as possible in workforce No. of locals All sites Site Monthly EO, BPC n/a people are employed in employed observations; Contractor’s workforce worker survey Importing foreign workers 1. Ensure imported workers are provided with housing that has ample No. of All sites Site Monthly EO, BPC Include can cause environmental toilets, proper drainage and treatment for sewage. Observations observations; d in CB and social problems at from camp site worker survey labor camps and in host 2. Collect solid waste weekly and bury offsite. All sites Site Monthly EO, BPC community

60

observations 3. Instruct workers on required behavior in host community and All sites Site Monthly EO, BPC prohibit them from hunting and fishing. observations; worker survey 4. Camps must be cleaned up and restored after project is Labour Site Monthly EO, BPC completed. camps observations; worker survey Diseases can be 1.Initial screening of workers for HIV/AIDS, TB, malaria, swine flu, Contractors Labour Site Monthly EO, BPC Include introduced into host etc.; record on camps observations; d in CB communities from social Health issues worker survey and sexual contact with 2.Facilitate access to the nearest Health facility for check up; Labour Site Monthly EO, BPC imported workers camps observations; worker survey 3.Raise worker/community awareness of risks of socially & sexually Labour Site Monthly EO, BPC transmitted disease; camps observations; worker survey 4.Practical measures, e.g. free condoms for workers; Labour Site Monthly EO, BPC camps observations; worker survey Workers and villagers are Implement Health and Safety Plan that includes measures to: Health and Labour Site Monthly EO, BPC at risk from accidents on -Exclude the public from all construction sites; safety camps observations site -Ensure that workers use Personal Protective Equipment; mgt.plan - Provide Health & Safety Training for all personnel; - Follow documented procedures for all site activities; - Keep accident reports and records; - Inform local communities about the work and dangers Operation and Maintenance Provision, Operation and Field personnel should report power outages to the ESD and repair # reports and MV and LV Reports Monthly EO, BPC n/a maintenance of new RE faults quickly and effectively repairs lines observations system 1.Train and supervise BPC field operatives to ensure that they check Training and All sites Reports Monthly EO, BPC n/a house wiring carefully and reject if deficient; awareness Observations 2. Public education to raise villagers’ awareness of dangers of Reports electricity and how to utilize the system safely. 1.Follow BPC O&M and H&S manuals and revise these manuals if # trainings and All sites Reports Monthly EO, BPC n/a necessary to increase safety of workers; supervision Observations 2.Regular training of BPC workers to raise awareness of dangers and reports

61

working procedures to be followed; 3.Improve supervision of field workers; 4. Regular management reviews of safety record, with remedial action where necessary. 1.As above: repair faults quickly and effectively; # Repair and All sites Reports Monthly EO, BPC n/a 2.Conduct system maintenance regularly and diligently maintenance Observations reports ESD: Electricity Supply Division, Mongar, RED: Rural Electrification Division, BPC, EO- Environmental officer

62

C. Institutional Arrangement

207. The subproject will be managed and implemented within the institutional framework that already exists in Bhutan for the provision of rural electrification services. The main agencies and their roles will be as follows:

 DoE is the Executing Agency (EA) responsible for management, coordination and execution of all activities funded under the loan.

 BPC is the Implementing Agency (IA), responsible for the successful construction and subsequent operation of all the RE subprojects. BPC is the Implementing Agency (IA), responsible for the successful construction and subsequent operation of all the RE subprojects. Implementation will be managed by the Rural Electrification Department (RED), headed by a General Manager in the Head Office and other Senior Managers in the Divisions.

 RED will coordinate construction of subprojects across all Dzongkhags, and ensure consistency of approach and performance. They will appoint Construction Contractors (CC) to build elements of the infrastructure in a particular Dzongkhag.

 Local implementation will be managed by the field offices of the RED in each of the target Dzongkhags, who will supervise the Construction Contractors, and will be responsible for quality control, contract supervision, monitoring and reporting, etc.

 Environmental issues will be coordinated by the BPC Environmental Unit, who will ensure that all subprojects comply with national environmental safeguards. The Environmental Monitoring Plan (EMP) involves observations and surveys to be conducted during construction and operation to ensure that mitigation measures are provided and that they protect the environment as intended. Construction monitoring will be conducted by RED field offices, and monitoring during operation will be co-ordinated by Distribution and Customer Services Department (DCSD), BPC.

D. Environmental Management and Monitoring Costs

208. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. Costs of mitigation by the contractors are included in the budgets for the civil works and do not need to be estimated separately here.

209. Mitigation that is the responsibility of BPC should be included as part of their management of the project. Environmental monitoring during construction must be conducted by BPC Environmental Officers, and budget is required for their travel. Customer satisfaction must be gauged and for this survey expenses may be incurred. There may also be unforeseen mitigation measures that may arise. The costs of these are shown in the following Table. The figures show that the total cost of environmental management and monitoring for the subproject as a whole (covering design, construction and operation) is Nu.7, 64,800.00

63

Table 13: Cost of implementing EMP and monitoring (Nu.)

5 Mongar Activity Quantity Unit Cost Total Cost Source of (Nu.) Fund Design phase Use of Covered conductors and reflectors To be ascertained To be To be Project ascertained ascertained Construction phase 1person x 2 weeks * 4 14000 56000 Project Monitoring by Environmental Officer times from BPC once every quarter Monitoring by project field staff every month 1personx1week * 12 4900 58,800 Project times Conducting awareness among public in each gewog 10 gewogs 15,000 150,000 Project Capacity building and training for stakeholders & staff 1,00,000 1,00,000 Project Compensation costs (social) 0 0 Project Afforestation/Reforestation by E & GIS Div. 5,00,000 5,00,000 Operation phase Unforeseen environmental impacts will be covered from project contingency cost Total 7,64,800

Assumptions:

-Construction works will be completed within one year of commencement -DSA rates for government officers/staff is as per prevailing rate -Environmental Division has adequate staff to cover all project sites

64

X.CONCLUSION AND RECOMMENDATION

A. Project Findings

210. The process described in this document has assessed the environmental impacts of all elements of the infrastructure proposed under the Rural Electrification Subproject. The findings of the assessment are as follows;

211. The primary positive impact of the project will be access to electricity for lighting, cooking and heating for individual households and religious institutions. At the same time the availability of an electricity supply should bring significant economic benefits to the rural communities, because:  There can be significant improvements in the health and lifestyle of local people through the use of clean technology and reduction of exposure to smoke from use of fuel wood and kerosene, and other health risks.  People will have more time available for work as they will not have to spend time for fuel wood permit, cutting and carrying firewood  People no longer have to purchase kerosene from the nearest town which is 2 days walk from the villages;  People will be able to use electrically powered machinery to process their farm products or to offer services to the community(e.g. rice mills), so again incomes should increase;  People will also be able to work and provide services during the evening because of the greater availability of lighting,  Individuals may be employed by the project during the construction period as porters or for clearing of RoW.

212. The major ecological benefit will occur over the longer term, as the availability of electricity in these villages reduces the felling of trees for firewood. Current estimates are that each rural household in Bhutan consumes around 3.5 kg of firewood per person per day5, so these ecological gains should become highly significant over time.

213. Potential negative impacts were identified in relation to design, construction and operation of the improved infrastructure. The most significant impact of the project is due to its location and design because 72% of the country is under forest cover. Therefore, all the target villages are either located inside or close to the forest. Along the 142km route of the MV line, 110km (77%) runs through forested land, in which a total of 1.32 km2 of forest will be cleared. Of this 10.34% of the total length is located in the periphery of Thrumshingla National Park.

214. The impact on the biological corridor as stated previously is unavoidable as environmental impacts would not occur if the target villages were not selected and MV lines could have been routed through un-forested areas to these villages. Keeping in mind the government’s policy of equity among all, these communities cannot be ignored or deprived of developmental opportunities simply because they reside in protected areas. Doing so will in fact cause resentment and a negative attitude towards conservation.

5 FAO (2001): National Strategy for Stoves and Other Alternative Energies, Project No BHU/99/005 65

215. The assessment did not consider that there would be any significant impacts due to the project design or location or construction and operation. Mitigation measures have been developed to reduce all negative impacts to acceptable levels. These were discussed with specialists responsible for the engineering aspects, and as a result some measures have already been included in the outline designs for the infrastructure. These include:  Routing MV lines along existing access routes and footpaths where possible, where the forest has already been partially cleared, thus reducing the felling of new trees as well as reducing the need to acquire private land; For instance, in Thrumshingla National Park, the farm road already under construction till Banjar will be completed by the RE project is being initiated, so aligning the distribution line (ARE3F3) along the farm road will reduce the RoW to be cleared.  Selection of MV line routes in close consultation with the Department of Forest and approved by the National Environment Commission after conducting field verification of alignments.  Public consultation to seek consensus of the affected households to construct poles on their land and to raise awareness of the project activities

216. Thus the planning process has already identified potential impacts and reduced their significance has already been reduced by amending the design and route alignment.

217. Regardless of these and various other actions taken during the IEE process and in developing the project, there will still be impacts on the environment when the infrastructure is built and when it is operating. This is mainly because most of the target villages are located in forested areas, so there will need to be some felling of trees along the MV lines and because of the dangers for workers and consumers that are inherent in maintaining or using an electricity supply system. Because of these factors the most significant impacts are on ecology and people.

218. During the construction phase, the main impacts mainly arise from the need to clear a 12 m right of way where MV lines pass through forested areas (to prevent shorting from branches touching bare conductors), and from the need to import foreign workers (which could lead to social and environmental problems in accommodation camps and neighbouring communities). These are common aspects of projects to provide rural electrification in remote areas (including Bhutan), and there are well developed methods for their mitigation. There were however no significant rare or endangered species sighted along the distribution line and discussions with the local people also revealed that there are no sensitive species in the project area. Most potential negative impacts identified were not considered significant because these are limited to the construction phase which is short in duration and due to the localised nature of impacts.

219. Although there will be areas where MV lines cross agricultural areas and private land, there will be no need to procure land as areas required are so small (ca 0.5 m2 each) and dispersed, so it is unlikely that a significant proportion of the land of any one owner will be acquired. The grievance redress mechanism will be constituted to take care in case of grievances against the project.

220. As many ARE villages are remote, isolated and not easily accessible; most of the environmental impacts are common across RE projects elsewhere in the country. Thus, BPC already has developed much experience in executing similar projects like these.

66

221. In order to ensure that environmental impacts are minimized as much as possible, mitigation measures have been proposed. Mitigation will be assured by a programme of environmental monitoring conducted during both construction and operation to ensure that all measures are provided as intended, and to determine whether the environment is protected as envisaged. This will include site observations, document checks, and interviews with workers and beneficiaries, and any requirements for remedial action will be reported to BPC. There will also be surveys to monitor the long-term benefits of the scheme and the adequacy of the service, and identify any deficiencies.

B. Recommendations

222. Recommendations to improve the project and reduce potential environmental impacts are;  All mitigation and enhancement measures as well as the Environmental Monitoring Plan proposed in this report should be implemented in full; and  The Contractor, BPC and Department of Forest must work closely during the construction phase just to minimize environmental impacts as much as possible.

C. Conclusion

223. The environmental impacts of the proposed improvements in rural electrification infrastructure in the dzongkhag have been assessed by the Initial Environmental Examination reported in this document, conducted according to ADB guidelines.

224. Mongar is one of the few dzongkhags where there are still over 1600 beneficiaries in 141 villages awaiting electrification. These beneficiaries would also very much like to be part of and benefit from the developmental process.

225. A key element of the national Environmental Clearance application process is the provision of signed No Objection Certificates (NOC) from stakeholders that are specified in the guidelines, including all affected households, Department of Forest, and other relevant Government Agencies (Dept of Culture, Nature Conservation Division, etc). NEC will not consider an EC application that does not contain the necessary NOC and Forestry Clearance for example is not granted by DoF until a forestry official has surveyed the whole length of any proposed route and has physically marked those trees that may be felled to create the RoW.

226. Once the Environmental assessment has been conducted and the application submitted to the NEC, the District Environmental Officer in collaboration with BPC and Park again revisit the proposed sites to confirm the proposed alignment and ensure that the least environmentally disruptive routes have been selected. This elaborate process of revisiting the proposed sites by different agencies ensures that all possible options have been explored, the environmental impacts of the proposed improvements in rural electrification infrastructure have been assessed and the and the most suitable one adopted.

227. Thus the overall conclusion of this process is that provided the mitigation measures are implemented in full, there should be no significant negative environmental impacts as a result of location, design, construction or operation of the subproject. There should in fact be some small benefits from recommended mitigation and enhancement measures, and major improvements in quality of life once the scheme is in operation.

67

REFERENCES

Bhargava, O.N (Ed.). (1995). The Bhutan Himalaya: A geological account. Special publication 39. Geological Survey of India.

BPC. (2007). BPC monthly System Performance Reports of ESD

DGM (2002). Geology of Bhutan, Department of Geology and Mines, Ministry of Trade and Industry

DoE. (2007). Climatic data (Meteorology Division)

DoF. (1974). National Forest Policy 1974, Royal Government of Bhutan

DoF. (2002). Forestry in Bhutan, Facts and Figures 2002. Department of Forestry Services, MoA

DoF. (2007). “Rules on Biological Corridors” as an addendum to the Forest and Nature Conservation Rules 2006. MoA. RGOB

Geological Survey of India (1995). The Bhutan Himalaya: A Geological Account. Bhargava. O.N. (ed). Special publication 39. Geological Survey of India.

GNHC (2009): Tenth Five Year Plan 2008-2013. Gross National Happiness Commission. Royal Government of Bhutan

MoA. (1997). Atlas of Bhutan, Land cover & Area Statistics of 20 Dzongkhags, Land Use Planning Project. 1994. Ministry of Agriculture, Thimphu, Bhutan, RGOB.

MoA. (1997). Biodiversity Action Plan for Bhutan, Ministry of Agriculture, RGOB

MoA. (2002). Biodiversity Action Plan for Bhutan. 2002. Ministry of Agriculture, Royal Government of Bhutan

MoE. (2007). General Statistics, Policy and Planning Division, Ministry of Education, Royal Government of Bhutan

MoHCA .(2006). National Disaster Risk Management Framework. Reducing Disaster Risks for a Safe and Happy Bhutan. Disaster Management Division. Department of Local Governance. Ministry of Home and Cultural Affairs. Royal Government of Bhutan.

MoP. (1997). 9th FYP document, (2002-2007), Ministry of Planning, RGOB

MoWHS. (2006). Annual Information Bulletin, PPD, Ministry of Works and Human Settlement, RGOB

MPFD. (1991). Master Plan for Forestry Development, Main Report. 1991. Ministry of Agriculture, Department of Forestry, Royal Government of Bhutan.

Namgay, K. (2005). Biodiversity Conservation and Protected Area system in Bhutan, pp 129- 133, in People and Protected Areas in South Asia. Uday.R.Sharma and Pralad. B.

68

Yonzon. IUCN World Commission on Protected Areas

National Statistical Bureau. (2004). Statistical yearbook of Bhutan, 2004. National Statistical Bureau, RGOB

National Statistical Bureau. (2007). Statistical yearbook of Bhutan, 2007. National Statistical Bureau, RGOB

NCD. (2001). Bumdeling Wildlife Sanctuary: Conservation Management Plan July 2001-June 2007. Nature Conservation Division. Department of Forestry Services. MoA, RGOB

NCD. (2004). Bhutan Biological Conservation Complex (Living in Harmony with the Nature). A Landscape Conservation Plan: a way forward. Nature Conservation Division, DoFS, MoA

NEC (2000). Environmental Assessment Act, 2000. National Environment Commission. Royal Government of Bhutan

NEC. (2002). Regulation on Strategic Environmental Assessment, 2002, NEC, Royal Government of Bhutan

Norbu, C; Baillie, I; Dorji, T; Tamang, H.B; Tshering, K and Hutcheon, A. (2003). A provisional physiographic zonation of Bhutan. Journal of Bhutan Studies. 54.

REMP. (2004). Rural Electrification Master Plan, Japan International Corporation Agency (JICA)

RGOB. (1995). Forest and Nature Conservation Act of Bhutan. Royal Government of Bhutan

RGOB. (2001). Electricity Act of Bhutan, Royal Government of Bhutan

RGOB. (2002). GYT (Gewog Yargay Tshogdue) Act. Royal Government of Bhutan

RGOB. (2005). Population and Housing Census of Bhutan, 2005. Office of the Census Commissioner, Royal Government of Bhutan

RGOB. (2006). Forest and Nature Conservation Rules 2006 DoF. Royal Government of Bhutan

Special Commission (2007). List of Monasteries in Bhutan, Special Commission

69

ANNEXURES

Annex 1: List of species found in project area

Table 1.1: Flora recorded from project sites during field surveys for this project

Arisaema erubescens Betula utilis Artemesia spp. Ardea spp. Ablizzia julibrissin Arundinaria spp. Anaphalis triplinervis Alnus nepalensis Elaegnus parvifolia Arisaema intermedium Castanopsis lanceifolia Girardinia spp. Ageratum adenophora Erythrina spp. Gnaphalium affine Ageratum conyzoides Juglans regia Heraculum spp. Aeschynanthus hookeri Lyonia ovalifolia Hedysarum sikkimensis Cymbopogon ciatus Lithocarpus elegans Hypericum spp. chirita urticifolia Lithocarpus fenestratus Rosa spp. Callicarpa spp. Macaranga peltata Rubus ellipticus Coriaria nepalensis Maesa chisea Solanum khasianum Curcurma aromatica Mussaenda roxburghii Pteridium aquilinum Clematis buchaniana Myrsine semiserrata Toona ciliata Desmodium spp. Pinus roxburghii Euphorbia spp. Leucas ciliata Rhododendron arboreum Indigofera spp. Rumex nepalensis Rhus chinensis Polygala spp. Oxalis spp. Schima wallichii Swertia bimaculata Mikania cordata Smilacina purpurea Berberis aristata Cassa tora Ficus oligodon Rhododendron Cirsium falconeri Quercus griffithii Pinus wallichiana Mikania micrantha Quercus lanata Sophora spp. Macaranga pustulata

70

Table 1.2: Fauna known to occur in Project sites

Common Name Scientific Name Leopard Panthera pardus Leopard cat Prionailurus bengalensis Wild dog Cuon alpinus Barking deer Muntiacus muntjak Indian porcupine Hysterix indica Sambar Cervus unicolor Wild pig Sus scrofa Sloth Bear Melursus ursinus Himalayan Black Bear Selenarctos thibetanus Clouded Leopard Neofelis nebulosa Capped Langur Trachypithecus pileatus

71

Table 1.3: Avifauna recorded in Project sites

No. Common Name Scientific Name 1 Ashy Drongo Dicrurus leucophaeus 2 Barred Cuckoo Dove Macropygia unchall 3 Black Bulbul Hypsipetes leucocephlus 4 Black Eagle Ichtinaetus malayensis 5 Black-tailed Crake Porzana bicolor 6 Blue Rock Thrush Monticola solitarius 7 Blue Whistling Thrush Myophonus caeruleus 8 Blue-winged Minla Minla cyanouroptera 9 Broad-billed Warbler Tickellia hodgsoni 10 Common Green Magpie Cissa chinensis 11 Common Hawk Cuckoo Hierococcyx varius 12 Common Hill Partridge Arborophila Torqueola 13 Common Kestrel Falco tinnunculus 14 Darjeeling Woodpecker Dendrocopoa darjellensis 15 Dark-sided Flycatcher Muscicapa sibirica 16 Great Barbet Megalaima virens 17 Great Tit Parus major 18 Grey Treepie Dendrocitta formosae 19 Grey Wagtail Motacilla cinerea 20 Grey-bellied Tesia Tesia cyaniventer 21 Large Niltava Niltava grandis 22 Large-billed Crow Corvus macrorhynchos 23 Mountain Bulbul Hypsipetes mcclellandii 24 Mountain Tailorbird Orthotomus ciuculatus 25 Mrs Gould's Sunbird Aethopyga gouldiae 26 Nepal Fulvetta Alcippe ni[palensis 27 Nepal House Martin Delichon nipalensis 28 Red-tailed Minla Minla ignotincta 29 Russet Sparrow Passer rutilans 30 Scaly Thrush Zoothera dauma 31 Speckled Wood Pigeon Columba pulchricollis 32 Yellow-rumped Honeyguide Indicator xanthonotus 33 Yellow-throated Fulvetta Alcippe cinerea 34 Little Pied Flycatcher Ficedula westermanni

72

35 Grey-sided Laughingthrush Garrulax caerulatus Annex 2: Summary of Public Consultation

With the permission of the Dzongkhag, two public consultations were held in Tsamang gewog, at Tsamang and Banjar on the 18th and 19th of June, 2009. In total there were 86 participants. The meeting was held as per the following agenda;

Introduction. The consultant explained the purpose of the meeting to the participants, the objectives of the project and how the target villages were selected to be included under this project.

EIA and Public consultation. An explanation on the Protected Area Conservation Policy and Environmental Assessment procedures was given. It was explained that an Environmental Clearance process is required to be followed for all new development projects. Depending on the location, size and nature of the project, proposed activities are categorized by the NEC and accordingly Environmental Clearance Procedures have to be followed. Since the distribution lines in Tsamang gewog were in the buffer of the Thrumshingla National Park, an Environmental Impact Assessment was being conducted to determine the nature of the impacts that would arise from the proposed project. The assessment looked at social, cultural/religious, environmental and economic considerations and also involved conducting a public consultation to seek the views of all stakeholders involved and incorporate any concerns.

Social considerations. It was explained that during the feasibility survey, it is very important that all the community members were aware that such field assessment was going on. The distribution line will be passing through different types of land use (Tsamdro, sokshing, pangshing and kamshing) and therefore a representative from the village was required to accompany the route surveyor to provide accurate information on land tenure and use. This would allow the route surveyor to determine the percentage of the line falling under such categories. Since the route surveyor is not a resident, a representative will be in a better position to ensure that encroachment on private land is minimized.

Cultural and Religious consideration. Since most villages have either a Lhakhang, Goenpa, Neys and Lu’s, which the surveyors are not aware of, the Tshogpa or community representative, should point out the location of these sites so that the MV line can be rerouted to avoid these.

Environmental consideration. It was explained that Bhutan is renowned for environmental conservation and therefore when donors are willing to pay for development projects, they are equally concerned that the environmental concerns are given due consideration. At the same time Environmental Conservation is one of the four pillars of Gross National Happiness and it is within the Forest Policy to maintain at least 60% forest cover at all times. In terms of forest cover, the RoW depends on the voltage of the distribution line. For 33kV, the RoW is 12m while for 11kV the RoW is 10m. People were reminded that this may not amount to much when calculated at the gewog level, but when calculated over the entire country it was quite substantial. Also, the forest provides critical habitat to many endangered species and loss of forest cover would in turn negatively impact these inhabitants.

Economic consideration. The process and the criteria used for selecting villages for inclusion in the 10th FYP were explained in detail. It was clarified that villages that were too far, very isolated and few in number were not included for on-grid electrification and will be included under Solar Energy Program. The very remote location of such individual houses required very lengthy distribution lines which were not techno-economically feasible and very expensive for the government.

73

Public consensus. In order to seek the consensus of all affected households, the BPC was seeking public consensus from all households in the target villages. Through the Dzongkhag and Gup, individual households are asked to sign a public consensus form, basically a “No Objection” statement allowing the BPC to construct poles on their land and align the distribution line through their private land. In many areas, the Gup convened meetings to inform all households and the Tsogpa’s collected the signatures. Also, in case of absentee owners, it is the responsibility of the Gup and Tsogpa to inform them. It is crucial to ensure that all affected households are informed and sign the consensus forms so that no issues from absentee owners will arise in the future.

BPC Policy. According to the BPC policy, an individual household is fully responsible for incurring the financial cost of removal or shifting of distribution line and poles if the household wants these to be removed or placed elsewhere once the distribution line is already constructed. Therefore, to avoid such problems or disputes in the future, any changes to be made to the alignment should be incorporated during the planning stage

Aesthetics. The importance of aesthetics was also explained to the participants, especially in view of Lhakhangs, Neys etc.

Environmental impacts. The positive impacts as well as the negative impacts of rural electrification was also highlighted and discussed. The village Tshogpa was asked to be actively involved during workers’ campsite selection and to raise awareness with contractors and workers on sanitation, waste generation and illegal activities such as poaching or felling of trees.

Clean Development Mechanism. The participants were informed that Bhutan is a member of a number of International Conventions, many of them related to environment and conservation because of our environmental legacy. As a member of one of the protocols, the Kyoto Protocol, the Country is interested to earn take advantage of the Clean Development Mechanism (CDM), which a mechanism in which Bhutan can earn credits for reducing Carbon emission.

Participant views. The participants were asked for their views on the project and their comments were solicited.

Summary of Discussions.

The participants said that they were very happy to hear about the project as they were beginning to feel left out with their neighboring villages included under one project or the other. They wanted to know how some villages like theirs could have been left out. The Mangiap and the BPC staff, Thubten explained that the village lists was submitted by the Gup during the previous years and as each project was initiated, the list was prepared in collaboration with the gups. Due to budgetary concerns and the need to provide electricity to all dzongkhags, not all villages could be selected at one time and therefore some were left out. Thus in Tsamang, some villages are funded by ADB and some by other Donors.

The women said that they were very happy to receive electricity as they could live in a clean and healthy environment and also did not have to waste much time carrying firewood. A few said that they were interested in weaving and were happy that they will have the opportunity to weave in the evenings.

One participant said that communication would be immediately possible for them because some of their villages were within the BMobile network and many people have mobile phones. With no electricity to charge the phones, the current practice is to send mobile phones with any person

74 visiting Mongar town so that they can charge it there. Often the shops charge about Nu.10 for this. With electricity most houses will not have to face this problem.

Protected area. The participants said that there is a park office in Tsamang and they process their permits for firewood and timber from this office. However, since the villages are in the periphery of the park, they feel that there will not be much disturbance to the park as the villages are not located in areas where endangered species are usually found. Also, there is a farm road construction ongoing till Banjar that is already partially completed. The work has been delayed due to the huge rockface that requires some blasting, but expected to be completed by the time the RE project begins. This will also make transportation easier for RE materials. Although some of the villages fall in the park, the forest surrounding the villages are degraded to some extent due to use by villagers for collection of firewood, leaf litter, NTFPs and therefore, the impact should not be much. Instead, each household will use less firewood and will contribute to conservation of the forest and habitat.

Issues. The participants said that they have all signed the public consensus forms and do not anticipate any problems with sacrificing a small portion of their land for the project as the entire village will benefit from it. The said that their village is opposite many electrified villages and they look across with envy at these villages and are very excited that they will also be electrified soon and enjoy the benefits like the villages across them.

There were a few queries on how internal wiring of the houses, supply of meters, and electricity bills. The BPC representative answered these queries and clarified that villagers could hire any trained or knowledgeable person to do the internal wiring. BPC would organize a public gathering to inform and educate users on safety issues as well as supply the meters once the entire Distribution line was set up. The electricity bill depends on the number of bulbs, voltage and duration of use.

There were lengthy discussions on how some houses were omitted from the project and it was explained that houses that were too far were included under off-grid electrification. The Tsogpa suggested that those households that intend to construct new ones should plan to do so before the project begins so as to benefit from it. There were also a few queries about temporary and permanent dwellings and it was clarified that only permanent dwelling with house numbers were entitled for inclusion under RE.

The participants requested that the project be implemented as soon as possible and did not think that there were any negative impacts that could occur from the project that they could think of apart from cutting of trees which was unavoidable.

75

List of Participants at the Public consultations No. Participants at Tsamang Consultation 1 Sherubla 2 Ugen Tshering 3 Rinchen Dorji 4 Pema Dolma 5 Tashi Yangzom 6 Sonam Tshering 7 Tashi Pelzon 8 Ngawang Dolma 9 Yeshi Peldon 10 Tshering Peljor 11 Yeshi Thinley

Participants at Banjar Consultation 1 Chime Lhamo 22 Kelzang Choki 2 Pema 23 Sonam Choden 3 Kesang Yuden 24 Chodenmo 4 Karma Mo 25 Tshering Yuden 5 Kesang Doma 26 Chimi Wangmo 6 Tshering Wangmo 27 Kelzang Lhaden 7 Lhadenmo 28 Kezangla 8 Sangaymo 29 Leki Doma 9 Yeshi Doma 30 Lekimo 10 Pema Lhazom 31 Lhakimo 11 Jambayang Choden 32 Sithar Yangzom 12 Kunzangmo 33 Namgay 13 Tshering Tenzin 34 Rinzin Wangchuk 14 Phuntso Wangdi 35 Kunzang Gyeltshen 15 Kunzang Thinley 36 Tshering Dolkar 16 Dorji Tashi 37 Kunzangmo 17 Kunzangmo 38 Lekila 18 Ngawang Dema 39 Dechenmo 19 Tshewang Dendup 40 Yangchen mo 20 Chimi Wangmo 41 Ugen Yeshi 21 Sherab Jamtso

76

Annex 3: Photos from project sites

Photo 1: Tsamang village- the farmroad Photo 2: villages in Tsamang under construction is visible in Thrumshingla National Park

Photo 3: Banjar village Photo 4: Typical house in village

Photo 5: Monastery at Tsamang Photo 6: Stupas in village

77

Photo 7: Chirpine forest - the dominant vegetation Photo 8: Broadleaf forest in Banjar

Photo 9: RNR centre with solar lighting system Photo 10: Cluster of houses in village

Photo 11: Farmroad to village completed a year ago Photo12: The ruined Zhongar Dzong near highway

78

Photo 13: Water tap shared among 2-3 houses Photo14: Row cleared along highway (to depict what the RoW will look like)

Photo 15: View of part of Mongar town Photo16: The hospital –the referral centre for eastern Bhutan

Photo 17: Public consultation in Tsamang Photo 18: Public consultation in Banjar

79

Annex 4: Sample copy of MOU between BPC and individual households Page 1/3

80

Page 2/3

81

Page 3/3

82

Map 1/14: Proposed Distribution lines under this sub-project

83

Map 2/14: Proposed Distribution lines under this sub-project

84

Map 3/14: Proposed Distribution lines under this sub-project

85

Map 4/14: Proposed Distribution lines under this sub-project

86

Map 5/14: Proposed Distribution lines under this sub-project

87

Map 6/14: Proposed Distribution lines under this sub-project

88

Map 7/14: Proposed Distribution lines under this sub-project

89

Map 8/14: Proposed Distribution lines under this sub-project

90

Map 9/14: Proposed Distribution lines under this sub-project

91

Map 10/14: Proposed Distribution lines under this sub-project

92

Map 11/14: Proposed Distribution lines under this sub-project

93

Map 12/14: Proposed Distribution lines under this sub-project

94

Map 13/14: Proposed Distribution lines under this sub-project

95

Map 14/14: Proposed Distribution lines under this sub-project

96

97