Environmental Information Report Section 36 Consent Variation

Total Page:16

File Type:pdf, Size:1020Kb

Environmental Information Report Section 36 Consent Variation ENVIRONMENTAL INFORMATION REPORT SECTION 36 CONSENT VARIATION DAMHEAD CREEK 2 POWER STATION Name Job Title Signature Date Environmental John Bacon / Consultant / February Prepared Associate Director, 2016 Andrew Hepworth Aecom Technical Technical Director, February Kerry Whalley Review Aecom 2016 February Approved Richard Lowe Director, Aecom 2016 AMENDMENT RECORD Issue Date Issued Date Effective Purpose of Issue and Description of Amendment 1.0 January 2016 January 2016 S36 Variation Draft EIR for review 2.0 February 2016 February 2016 S36 Variation Final for Issue DHC2 Environmental Information Report 4-Feb-16 Page 2 of 116 TABLE OF CONTENTS Page Executive Summary 5 1. Introduction 9 1.1 Purpose of this Document 10 1.2 Planning history of DHC2 10 1.3 Environmental Assessment 11 2. Description of the Development 15 2.1 Proposed Development 15 2.2 Site Location 16 2.3 Application Site Context 17 2.4 Main Buildings and Plant 18 2.5 Process Description 19 2.6 Operational Information 21 2.7 Environmental Permit 22 2.8 Combined Heat and Power (CHP) 23 3. Legislative Framework 26 4. Status of Pre Commencement Planning Conditions 27 4.1 Operational Noise 27 4.2 Contamination of Watercourses 27 4.3 Ecological Enhancement and Protected Species 27 4.4 Ground Contamination 28 4.5 Landscaping and Creative Conservation 28 4.6 Archaeology 29 4.7 Layout and Design 29 4.8 Green Travel Plan 29 4.9 Construction and Construction Traffic 30 4.8 Other Planning Conditions 30 4.8 Other Planning Consents 30 5. Stakeholder Consultation 31 6. Environmental Appraisal 33 6.1 Methodology 33 6.2 Air Quality 35 6.3 Noise and Vibration 42 6.4 Landscape and Visual Amenity 48 6.5 Ecology 61 6.6 Water Quality 75 6.7 Geology, Hydrology and Land Contamination 82 6.8 Traffic and Infrastructure 93 6.9 Cultural Heritage 98 6.10 Socio-Economics 104 7. Conclusions 109 Figures: Figure 1: Damhead Creek 2 CCGT Power Station Site Location Figure 2: Application Site Boundary and Areas 1 to 3 Figure 3: Application Site Boundary on Aerial Photograph Figure 4a: General Arrangement Plan 2015 Figure 4b: General Arrangement Plan 2016 Figure 5: Proposed 1,800 MW CCGT with peaking plant scheme option – Indicative Layout (no CCR) Figure 6: Proposed 1,800 MW CCGT with peaking plant scheme option – Indicative Layout (with CCR) Figure 7: Consented 1,800 MW CCGT-only scheme option – Visualisation Figure 8: Proposed 1,800 MW CCGT with peaking plant scheme option – Visualisation Appendices: Appendix A: Proposed Section 36 Consent Variation and S90 Direction Consent Notice 2016 Appendix B: Carbon Capture Readiness (CCR) Footprint Report Appendix C: Imperial College, Assessment of the CCR Compliance of the Proposed Damhead Creek 2 1500 MW CCGT + 300 MW OCGT Scheme Appendix D: Air Quality Technical Note Appendix E: Combined Heat and Power Readiness (CHP-R) Report Appendix F: Noise Assessment Appendix G: Visualisations Appendix H: Habitats Regulations Assessment Review 2016 Appendix I: Flood Risk Assessment DHC2 Environmental Information Report 4-Feb-16 EXECUTIVE SUMMARY ScottishPower (DCL) Limited proposes to construct and operate a power station of up to 1,800 MW electrical output capacity, comprising a Combined Cycle Gas Turbine (CCGT) plant and potentially an Open Cycle Gas Turbine (OCGT) peaking plant, called Damhead Creek 2 (DHC2), on land immediately adjacent to their existing Damhead Creek CCGT power station on the Hoo Peninsula, Kent (see Figures 1 to 3). On 25 January 2011, ScottishPower secured consent under Section 36 of the Electricity Act 1989, for the development, construction and operation of a new 1,000 MW CCGT adjacent to the existing Damhead Creek Power Station. Further to this, on 28 July 2014 ScottishPower secured consent under Section 36(c) of the Electricity Act 1989 to increase the output of Damhead Creek 2 CCGT to 1,200 MW (12.04.09.04/265C) and subsequently in October 2015 this was further increased to 1,800 MW output CCGT (hereafter referred to as the 1,800 MW CCGT-only scheme option). ScottishPower now seek to further vary the existing consent to allow flexibility in the make-up of the plant to include up to 300 MW of OCGT peaking plant. The proposed development therefore now comprises a CCGT/OCGT power station with a total combined electrical capacity up to 1,800 MW, hereafter referred to as the ‘1,800 MW CCGT with peaking plant’ scheme option. This application to vary the consent retains the option of constructing the already consented 1,800 MW CCGT-only scheme option but also includes provision of up to 300 MW as part of that capacity as OCGT units, with the CCGT capacity correspondingly reduced such that the combined output remains at 1,800 MW. This Environmental Information Report therefore focuses on the new variant including the use of peaking plant, as the already consented 1,800MW CCGT-only option was fully assessed as part of the 2015 variation. A variation to the current Section 36 Consent is therefore now being sought from the Department of Energy and Climate Change (DECC) pursuant to The Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013. The original Section 36 application in 2009 was supported by an Environmental Statement (ES)1 and the applications to vary the Section 36 Consent in 2014 and 2015 were supported by Environmental Information Reports (EIRs)23. This EIR provides an environmental review of the proposed 1,800 MW CCGT with peaking plant scheme option in the context of the information and findings of the 2009 ES, the 2014 EIR and 2015 EIR and should be read in conjunction with these documents. The assessments reported in the 2009 ES1, 2014 EIR2 and 2015 EIR3 considered a range of environmental topics: air quality; noise and vibration; landscape and visual amenity; ecology; water quality; geology, hydrology and land contamination; traffic and infrastructure; cultural heritage; and socio-economics. Supporting reports also included demonstration that the scheme met the Carbon Capture Readiness requirements. The previous 1,800 MW CCGT-only scheme option assessed in the 2015 EIR comprised either a single shaft or a multi-shaft combined cycle arrangement with up to three gas turbines, each with a heat recovery steam generator (HRSG), and connected to either a dedicated steam turbine or a single steam turbine respectively, depending on plant configuration. Taking account of the implementation of the identified mitigation measures (which are required by the Section 90 Direction planning conditions), the 2015 EIR3 did not identify any significant adverse effects due to the construction or operation of the 1,800 MW CCGT-only scheme option, with the exception of moderate adverse effects on two nearby visual receptors. This conclusion was consistent with the findings of the 2009 ES1 and 2014 EIR2. The potential configuration considered for the proposed 1,800 MW CCGT with peaking plant scheme option (used in the plant visualisation (Figure 8), photomontages (Appendix G) and consideration of Carbon Capture and Storage Readiness (CCR) space requirements (Appendix B and Appendix C)) is a multi-shaft arrangement for the CCGT units, comprising two gas turbines, each with a HRSG, and 1 ScottishPower (2009) Damhead Creek 2 CCGT Power Station - Environmental Statement. 2 ScottishPower (2014) Damhead Creek 2 CCGT Power Station - Environmental Information Report. 3 ScottishPower (2015) Damhead Creek 2 CCGT Power Station - Environmental Information Report. DHC2 Environmental Information Report 4-Feb-16 connected to a single steam turbine. The peaking plant capacity will be generated through up to two OCGT units which will be natural gas fired with no diesel back-up. The environmental appraisal has considered the General Arrangement Plan (2016) (Figure 4b) which is unchanged from the 1,800 MW CCGT-only scheme option (Figure 4a) considered in the 2015 EIR (whilst the detailed layout has changed to include the peaking plant, the development areas required remain unchanged). Discusssions have taken place with DECC, Medway Council, the Environment Agency and Natural England on the proposed Section 36 Consent variation and their comments have been taken into account. Using available information, including additional environmental baseline data gathered since the 2009 ES was prepared; the predicted environmental effects of the proposed 1,800 MW CCGT with peaking plant scheme option have been compared to the environmental effects of the currently consented 1,800 MW CCGT-only scheme option. The findings are summarised below. • Air Quality o A dispersion modelling assessment has been undertaken for the proposed 1,800 MW CCGT with peaking plant scheme option to assess the potential effects on residential and ecological receptors in the vicinity of the Site. Agreement was reached with Natural England for the previous section 36 consent variation on the predicted level of impact on the designated ecological receptors – notably the Medway Estuary and Marshes SSSI, SPA and Ramsar site – that would not give rise to significant effects and the current proposed variation remains within those agreed levels. o Through use of appropriate stack heights on the CCGT and OCGT units, no significant adverse air quality effects are predicted on human or ecological receptors as a result of the proposed variation, assuming emission levels remain within those to be specified within the Environmental Permit for the installation. • Noise and Vibration o A noise modelling assessment has been undertaken for the proposed 1,800 MW CCGT with peaking
Recommended publications
  • Digest of United Kingdom Energy Statistics 2012
    Digest of United Kingdom Energy Statistics 2012 Production team: Iain MacLeay Kevin Harris Anwar Annut and chapter authors A National Statistics publication London: TSO © Crown Copyright 2012 All rights reserved First published 2012 ISBN 9780115155284 Digest of United Kingdom Energy Statistics Enquiries about statistics in this publication should be made to the contact named at the end of the relevant chapter. Brief extracts from this publication may be reproduced provided that the source is fully acknowledged. General enquiries about the publication, and proposals for reproduction of larger extracts, should be addressed to Kevin Harris, at the address given in paragraph XXIX of the Introduction. The Department of Energy and Climate Change reserves the right to revise or discontinue the text or any table contained in this Digest without prior notice. About TSO's Standing Order Service The Standing Order Service, open to all TSO account holders, allows customers to automatically receive the publications they require in a specified subject area, thereby saving them the time, trouble and expense of placing individual orders, also without handling charges normally incurred when placing ad-hoc orders. Customers may choose from over 4,000 classifications arranged in 250 sub groups under 30 major subject areas. These classifications enable customers to choose from a wide variety of subjects, those publications that are of special interest to them. This is a particularly valuable service for the specialist library or research body. All publications will be dispatched immediately after publication date. Write to TSO, Standing Order Department, PO Box 29, St Crispins, Duke Street, Norwich, NR3 1GN, quoting reference 12.01.013.
    [Show full text]
  • *** DRAFT ** Sustainable Development and CO2 Capture and Storage
    *** DRAFT ** Sustainable Development and CO2 Capture and Storage A report for UN Department of Economic and Social Affairs Prepared by Dr Paul Freund 31 August 2007 Executive Summary The threat of climate change and the importance of fossil fuels in global energy supply have recently stimulated much interest in CO2 capture and storage (CCS). The most important application of CO2 capture would be in power generation, the sector which is responsible for 75% of global CO2 emissions from large stationary industrial sources. Two options for capture are based on well established technology - post-combustion capture using chemical solvent scrubbing would be used in current designs of power stations; pre-combustion capture using physical solvent separation involves a small modification to the design of gasification based systems which are increasingly being considered for future power plants. A third approach, oxyfuel combustion, has not yet been demonstrated at full scale but several pilot plants are under construction. Captured CO2 would be transported by pipeline to storage in geological formations – this might be in disused oil or gas fields or in deep saline aquifers. Use of the CO2 to enhance oil or gas production offers the possibility of generating some income to offset part of the cost of CCS. CCS increases the energy used for power generation by about 25-50% and reduces emissions by about 85%. The levelized cost of electricity generation would be increased by between 40% and 90% depending on the design of the plant and type of fuel. There is sufficient capacity worldwide for CO2 storage to make a substantial contribution to reducing global emissions, although the capacity is not distributed evenly.
    [Show full text]
  • 5A Planning Applications
    PLANNING APPLICATIONS FOR 2 JANUARY 2008 Page no. 1 MC2007/0014 Peninsula Application for deemed planning permission under Section 90(2) of The Town and Country Planning Act 1990 for construction of two advanced supercritical (ASC) coal-fired generating units (demolition of power station) Kingsnorth Power Station, Kingsnorth, Hoo St. Werburgh, Rochester, Kent 3 2 MC2007/1517 Watling Subdivision of 1,817sqm floor area of existing Retail Warehouse into 2 separate and independent retail units and sale of non DIY goods. B&Q Plc Will Adams Way Gillingham Kent ME8 6BY 7 3 MC2007/1912 Watling Subdivision of 1,817sqm floor area of existing Retail Warehouse into a separate retail unit, provision of mezzanine to provide 1417sqm additional floorspace and sale of non DIY goods B&Q Plc Will Adams Way Gillingham Kent ME8 6BY 76 4 MC2005/0814 Luton & Wayfield Application for approval of reserved matters pursuant to condition 1 of MC2003/1285 for demolition of existing buildings and construction of three blocks of flats comprising of 96 residential units, associated garaging and landscaping 2 Ash Tree Lane Chatham Kent ME5 7BZ 87 5 MC2005/1707 Twydall Retrospective application for the construction of fire escape route and retaining wall Units A to E Invicta Business Centre, land adjoining Beechings Way, Gillingham, Kent. 90 6 MC2007/0265 Rainham Central Construction of a block of lock up garages Land between 21 and 23 Asquith Road Rainham Gillingham Kent 96 7 MC2007/1372 Strood Rural Proposed height increase of 14.3 metre high monopole by 2.5 metres to
    [Show full text]
  • Modified UK National Implementation Measures for Phase III of the EU Emissions Trading System
    Modified UK National Implementation Measures for Phase III of the EU Emissions Trading System As submitted to the European Commission in April 2012 following the first stage of their scrutiny process This document has been issued by the Department of Energy and Climate Change, together with the Devolved Administrations for Northern Ireland, Scotland and Wales. April 2012 UK’s National Implementation Measures submission – April 2012 Modified UK National Implementation Measures for Phase III of the EU Emissions Trading System As submitted to the European Commission in April 2012 following the first stage of their scrutiny process On 12 December 2011, the UK submitted to the European Commission the UK’s National Implementation Measures (NIMs), containing the preliminary levels of free allocation of allowances to installations under Phase III of the EU Emissions Trading System (2013-2020), in accordance with Article 11 of the revised ETS Directive (2009/29/EC). In response to queries raised by the European Commission during the first stage of their assessment of the UK’s NIMs, the UK has made a small number of modifications to its NIMs. This includes the introduction of preliminary levels of free allocation for four additional installations and amendments to the preliminary free allocation levels of seven installations that were included in the original NIMs submission. The operators of the installations affected have been informed directly of these changes. The allocations are not final at this stage as the Commission’s NIMs scrutiny process is ongoing. Only when all installation-level allocations for an EU Member State have been approved will that Member State’s NIMs and the preliminary levels of allocation be accepted.
    [Show full text]
  • Medway Local Development Framework
    ATTACHMENT 9 Medway Local Development Framework Statement of Community Involvement January 2012 1 2 Summary This document is a new revised version of the Statement of Community Involvement or SCI for Medway. It sets out how the Council will involve local people in planning and development issues affecting Medway. The Council adopted its original SCI in 2006. Since then there have been further changes to the development planning system and consultation bodies have come and gone. For these reasons it is appropriate to update and refresh it now. It includes a short description of the development planning system and Medway Council’s role. However most of the document describes the methods the Council will use to engage with the public and other stakeholders and it lists the main organisations that have expressed an interest in being involved. Getting involved: There are a number of ways in which you can give us your views, check progress on the preparation of this and other LDF Documents and get involved in planning and development issues: • Telephone: 01634 331629 (Office hours are 9 a.m. – 5 p.m. Monday to Thursday and 9 a.m. – 4.30 p.m. Friday) • Email: [email protected] • Post: Development Policy and Engagement Team, Regeneration, Community and Culture, Medway Council, Gun Wharf, Dock Road, Chatham, Kent ME4 4TR • Website: http://www.medway.gov.uk/ldf . This is our front page and you will find numerous links to published documents, our Limehouse system etc. • Limehouse: This is an online consultation system and we would strongly encourage you to “register” as a user.
    [Show full text]
  • Core Vision November 2009
    The Thames Gateway Core Vision November 2009 Sir Terry Farrell The purpose of the Core Vision… The Core The Core The Core Vision: Vision: Vision: ● to develop a visual ● refreshes the ● supports characterisation Thames Gateway investment plans (based on the narrative Parklands Model) ● helps inform ● shapes the future policy delivery strategy ● supports project delivery ● commissioned by the HCA / CLG The key questions… • What is the Thames Gateway’s role and what is its future? • Why should Government continue to support the Thames Gateway? Wealth and quality of life is place-based “Place is actually more important to the world economy than ever before …” Richard Florida London’s wealth enables the Greater South East to compete globally Growth in London and the Greater South East is critical to the UK’s future prosperity 1 The highest return on investment for public and private sectors in the UK 2 The highest GVA per capita in the UK £30k £20k £10k East of England Rest of UK South East £0k London Table comparing GVA per capita in the UK Thames Gateway has the region’s greatest potential… The largest designated The most available land and a 1 growth area in the region 2 willingness for sustainable growth 1 Milton Keynes and South Midlands Basildon 2 London Stansted and Cambridge East London 3 Thames Gateway Kent 4 Ashford Thameside Medway ● Immediately adjacent to London ● 20% of the Greater South East’s brownfield land ● A critical part of the London economy – London’s engine ● in only 3% of the Greater South room East Region …to deliver
    [Show full text]
  • Local. International
    Andrew Annual Report Part I/II 2008 Company Report Laura Jacob Local. International. Peter 2008 Company Report E.ON Olga Eric Sarah Michael Lewis Sven Monica Financial Calendar Dimitrii May 6, 2009 2009 Annual Shareholders Meeting May 7, 2009 Dividend Payout May 13, 2009 Interim Report: January – March 2009 August 12, 2009 Interim Report: January – June 2009 November 11, 2009 Interim Report: January – September 2009 March 10, 2010 Release of 2009 Annual Report Isabelle May 6, 2010 2010 Annual Shareholders Meeting May 7, 2010 Dividend Payout May 11, 2010 Interim Report: January – March 2010 August 11, 2010 Interim Report: January – June 2010 November 10, 2010 Interim Report: January – September 2010 International. It sounds far away. Big. Impersonal. Unreachable. Actually, the opposite is true. International is everywhere. In Madrid and in Düsseldorf. Off the coast of Scotland. In Malmö. In Datteln. In Bratislava. In Livorno Ferraris. At OGK-4 in Moscow. Why? Because everything we do locally benefi ts from the way we work together across our international organization. Because that’s how we learn from each other, create synergies, and fi nd the best solutions. For the environment. For a reliable and secure supply of energy. For our employees and our investors. But especially for our customers. At E.ON, there are countless examples of this kind of collaboration. Our 2008 Company Report introduces you to a few of them. We want you to see how local international can be. 6 Smart Product Workshop: part of our groupwide Smart Metering Program 11 Employee opinion survey: an important management and communications tool 17 R&D Steering Group meets in the United Kingdom 25 Protective clothing that meets uniform standards 2 Our Company.
    [Show full text]
  • After the Coal Rush:Layout 1.Qxd
    WWW.IPPR.ORG AftertheCoalRush: Assessingpolicyoptionsforcoal-fired electricitygeneration byMatthewLockwood July2008 ©ippr2008 InstituteforPublicPolicyResearch Challengingideas– Changingpolicy 2 ippr|AftertheCoalRush:Assessingpolicyoptionsforcoal-firedelectricitygeneration Contents Aboutippr........................................................................................................................................... 3 Abouttheauthor ................................................................................................................................ 3 Acknowledgements.............................................................................................................................. 3 Abbreviationsandacronyms................................................................................................................ 4 Executivesummary .............................................................................................................................. 5 Introduction ...................................................................................................................................... 10 1.Coal-firedpowergenerationintheUK:anoverview .................................................................... 12 2.Whyenergycompanieswanttobuildnewcoal-firedpowerstations........................................... 15 3.Theroleofcarbonpricing............................................................................................................. 24 4.Theroleofthe2020renewableenergytarget.............................................................................
    [Show full text]
  • Development of Low Cost Systems for Co-Utilisation of Biomass in Large Power Plant
    DEVELOPMENT OF LOW COST SYSTEMS FOR CO-UTILISATION OF BIOMASS IN LARGE POWER PLANT MID TERM REVIEW REPORT B/U1/00726/00/00 URN 03/1440 Contractor Mitsui Babcock Technology and Engineering Prepared by W R Livingston The work described in this report was carried out under contract as part of the DTI New and Renewable Energy Programme, which is managed by Future Energy Solutions. The views and judgements expressed in this report are those of the contractor and do not necessarily reflect those of the DTI or Future Energy Solutions. First Published 2003 © Crown Copyright 2003 dti EXECUTIVE SUMMARY There has been a fairly dramatic increase over the past two years in the interest in the co­ firing of biomass materials with coal in the large coal-fired power plants in Britain, in response to the significant additional incomes available from the generation of Renewables Obligation Certificates. All of the operators of coal-fired plants have registered with Ofgem, and by the end of 2003, it is anticipated that most, if not all, of the coal-fired power plants in Britain will have the capability to co-fire biomass materials. The major constraint on co-firing activities will be the availability of suitable supplies of biomass materials at acceptable delivered fuel prices. The route to fully commercial operation of a coal-fired station on biomass co-firing involves a number of stages, viz: • The securing of the biomass fuel supply, • The preparation of the application to the Environment Agency/SEPA for a Variation to the Authorisation under Section 11 of the EPA, the definition of the test burn requirements and obtaining agreement to hold the test burn from the EA/SEPA, • The performance and reportage of the test burn, and • The final agreement from the Environment Agency/SEPA on the variation to the Authorisation, and proceeding to commercial operation on co-firing.
    [Show full text]
  • (For Official Use Only) PUBLIC PETITION NO. PE1188 Should You Wish to Submit a Public Petition for Consideration by the Public P
    (For official use only) PUBLIC PETITION NO. PE1188 Should you wish to submit a public petition for consideration by the Public Petitions Committee please refer to the guidance leaflet How to submit a public petition and the Guidance Notes at the back of this form. 1. NAME OF PRINCIPAL PETITIONER Nick Dekker 2. TEXT OF PETITION Nick Dekker calling on the Scottish Parliament to urge the Scottish Government to investigate the circumstances whereby it agreed that 60 hydro-power stations could be accredited for subsidy under the Renewables Obligation scheme and that generation capacity could be cut to below the 20megawatt qualification threshold at others to enable accreditation and whether, in the interests of electricity consumers, it will rescind these accreditations. 3. ACTION TAKEN TO RESOLVE ISSUES OF CONCERN BEFORE SUBMITTING THE PETITION I have contacted and have been in correspondence with AuditScotland, OFGEM, Scottish & Southern Energy PLC and ScottishPower PLC. Alex Neil MSP also corresponded with Scottish & Southern Energy. 4. ADDITIONAL INFORMATION See— “The war on climate change – A licence to print money?” “Subsidies and Subterfuge – Hydro-power and the Renewables Obligation” (also on www.swap.org.uk) “ROCs earned by Alcan, SSE and ScottishPower from 'old build' hydro, April 2002 to December 2007” (a report by the petitioners); “Renewable Energy Data for Scotland (Hydro), May 2008” Correspondence generally pertinent to the petition but esp to Question 3 OFGEM’s “Annual Reports on the Renewables Obligation” 2004 to 2008; Press releases and other material referred to in “The war on climate change – a licence to print money?” and elsewhere 5.
    [Show full text]
  • Uniper UK Limited (Formerly E.ON UK) Have Not Undertaken Any Operations in Zone 5 Since the Environmental Permit Was Issued
    Application SCR evaluation template Name of activity, address and NGR Kingsnorth Power Station Hoo PO Box 15 Rochester Kent ME3 9LD Centre of the site is at NG Ref. TQ 8115 7203 Document reference of application SCR Partial Surrender Application for Kingsnorth Power Station 09/12/2019 Ground Investigation Interpretative Report Kingsnorth Power Station On Behalf of E.ON UK Limited Date: May 2014 Ref: JER5486 JER5981 RPS Validation report for Coal Stock 131017 Date and version of application SCR N/A 1.0 Site details Has the applicant provided the following information as required by the application SCR template? Site plans showing site layout, drainage, surfacing, receptors, sources of emissions/releases and monitoring points NA. This is an application for Surrender 2.0 Condition of the land at permit issue To be completed by GWCL officers (Receptor) Has the applicant provided the following information as required by the application SCR template? a) Environmental setting including geology, hydrogeology and surface waters b) Pollution history including: pollution incidents that may have affected land historical land-uses and associated contaminants visual/olfactory evidence of existing contamination evidence of damage to existing pollution prevention measures c) Evidence of historic contamination (i.e. historical site investigation, assessment, remediation and verification reports (where available) d) Has the applicant chosen to collect baseline reference data? Condition of Land at the Point of Permit Issue The environmental setting is
    [Show full text]
  • Corporate Profile
    CORPORATE PROFILE 1-1-8, Miyata-cho, Takatsuki City, Osaka 569-8660, Japan TEL : +81-72-690-2308 / FAX : +81-72-690-2329 ZGC02.0/12E http://www.torishima.co.jp/en ’18.9.2000Ⓙ High-Tech Pumps Power Industry Power Plant Projects, Torishima provides a full range of pumps in this industry. Electricity is indispensable for modern society and the demand for energy continues to increase particularly in emerging ① Ring section type boiler feed pump, Jawa-2 Combined Cycle Power Plant, ⑤ Indonesia, 1×880MW ① ② countries. Meanwhile, balancing the economic development and environmental conservation is a critical issue common to ② Barrel type boiler feed pump, Chhabra Supercritical Thermal Power Plant, the world. Torishima provides high-efciency and reliable pumps needed for the various types of power plants including India, 2×660MW ⑨ ③ Barrel type boiler feed pump, Mong Duong 2 coal-red power plant, combined cycle power plants, super critical power plants, and geothermal power plants and biomass power plants. ⑥ ⑦ ⑧ Vietnam, 2×620MW ③ ④ ④ Ring section type boiler feed pump, Isle of grain power station, U.K., 1×1,320MW ⑤ Barrel type boiler feed pump, Mojave Solar Power Plant, U.S.A., 2×240MW ⑥ Condensate pump, Samalkot combined cycle power plant, India, 3×800MW ⑦ Hotwell pump, Polaris geothermal power plant, Nicaragua, 1×36MW ⑧ Circulating water pump, Pacico coal red power plant, Mexico, 1×700MW ⑨ Boiler circulating pump, Mahanadi thermal power plant, India, 6×600MW 03 TORISHIMA PUMP MFG. CO., LTD. TORISHIMA PUMP MFG. CO., LTD. 04 High-Tech Pumps Seawater Desalination As a specialist in pumps for seawater desalin ation, Torishima plays a signicant role in solving the global water shortage problem.
    [Show full text]