<<

WATER

STANLEY PARK WATER SUPPLY TUNNEL This project will ensure the reliable supply of clean, safe drinking water to the Lower Mainland.

NOVEMBER 2020 Project Overview Metro provides clean, safe drinking water to residents and businesses across the region through a system of reservoirs, water mains and pump stations. Operating our vast drinking water system, with expansive infrastructure and a growing population, requires constant upgrades, improvements, repairs and expansion. To meet the growing demand for drinking water in the region, Metro Vancouver is planning to construct a major water infrastructure project, called the Water Supply Tunnel, deep under Stanley Park. The new water supply A V IS O tunnel will replace an existing water main that was built in the 1930sN and is nearing the end of its service life.

TR AIL Metro Vancouver is planning to tunnel deep STANLEY PARK WATER SUPPLY TUNNEL – KEY PROJECT LOCATIONS underground to build a new water main and Burrard two valve chambers. The valve chambers The Inlet will house underground pipe and valves Shaft will be located to control the flow of water through the in the northeast corner of the park mains in the area. The new main and valve near NOTunnel Trail VINE TRAIL RTH CREEK TRAI StSStanley Park Dr IL RA RA tta chambers will then be connected to the T ana E n A K lel R L e VE y existing water distribution system. EA B PaP aark rkr L k To excavate the proposed tunnel, install D Lake r the water main and build the valve LAKE TRAIL TISDALL WALK TUNNEL TRAIL chambers, three shafts will be constructed in Stanley Park. At all three shaft sites, the d construction areas will be restored to equal d R R d

STANLEY e ne n i i li l n or better condition. l

PARK e p pe p i The project is in the planning and design Pi P Pipeline Rd stage and construction is expected to begin The Centre Shaft will be located north in late 2022 through 2026. When complete, of the Stanley Park SOUTH CREEK TRAIL MALLARD TRAIL the new tunnel will meet current seismic Service Yard

y

E aya

N A W

standards, help ensure the continued S L RO n ta SE G AL TRAIL A N ono TH n R D E le s PA y isi reliable delivery of clean, safe drinking water v Pa rk AvA isonBROCKTON Way OV IDLE Ca to the region, and increase the capacity of BR TA u B TLOW WALK se RO w CK the existing system for the region’s growing ay TON POINT TRAIL Lagoon L th I or D A N population. R r T iv Dr L e k RA ar D P E ley H an T St

A Project Timeline C

Lost Public Engagement on Fall 2017 Lagoon Existing Water Main Preliminary Design The Chilco Street Proposed Stanley Park Water Supply Tunnel Public Engagement on Shaft will be located WWest Geor Proposed Tunnel Shafts 2019 – 2021 in the parkLOST near LAGOON the TRAI e sstt Detailed Design G intersection of Chilco AlAAlber eoe l o beb r rgrgiag St L TS t e iai and Alberni Streets SSt rnrnni St a o SSt TENNIS COUR coc i Construction Late 2022 – 2026 ilcilcoiillclcol StS t r hhihilhilc t onon D CChChiChilco St t CITY OF LaLLagoonagogo Dr StS rd St VANCOUVER foor ilfl GGiGilfGilfor Minimizing Project Impacts Working with the Community The Stanley Park Water Supply Tunnel is critical for the Metro Vancouver will notify residents, park businesses safe and reliable delivery of drinking water. We are and park users of any disruptions well in advance sensitive to the impacts that construction will have and and be responsive to any concerns raised about are taking steps to minimize them, wherever possible. project activities. The majority of the work will take place deep A Community Liaison is available to address any public underground and park businesses and visitors are questions or concerns. The project team has been not expected to experience significant disruptions working closely with the Vancouver Park Board, the City to regular activities. Key considerations during the of Vancouver, First Nations, residents and businesses to planning stages of this project include: identify and mitigate impacts early in the process. • Limiting impacts to the natural environment and First Nations cultural sites • Maintaining access for park users How Big is the Water Main? • Protecting the park’s public amenities There are all different sizes of water mains in our • Minimizing construction duration and impacts region’s distribution system, but the water main Residents near the Chilco Street Shaft will experience being installed for this project is approximately construction impacts such as noise and dust while 2.6 m (8.5 feet) in diameter. crews build the shaft and valve chamber. However, the construction schedule will be designed to complete Person Height 1.8 m (approximately 6') the work as quickly as possible while ensuring local residents receive a break from construction activities at New Water Main night and on Sundays. A temporary re-routing of the 2.6 m bike and pedestrian paths near the Chilco Street Shaft (approximately will also be required throughout construction of the 8.5') shaft and the valve chamber.

CROSS-SECTION OF THE PROPOSED WATER SUPPLY TUNNEL

Burrard Inlet Centre Chilco Street Shaft STANLEY Shaft Shaft PARK

VANCOUVER

Lost Lagoon Burrard Inlet Water Supply Tunnel (1.4 km long) 35 to 45 metres deep

Project Updates Contact Us For additional information on this project, please Metro Vancouver Community Liaison: 604-432-6200 visit www.metrovancouver.org and search: (Monday to Friday from 8 AM to 4:30 PM) “Stanley Park Water Supply Tunnel” After Hours Emergency: 604-451-6610 Email: [email protected] (Please include “Stanley Park Water Supply Tunnel” in the subject line)