To:

From: Layne, Donnell

Subject: Form 470 for the Noble Network of Charter Schools

Hello.

If you are receiving this message, it's because you expressed interest in the recent Form 470’s posted for the Noble Network of Charter Schools (E-Rate Form 470 # 170054925)

Below, you will find a list of vendor related questions and answers for the form 470’s.

Bids are Due from Vendors to Noble by 1:00 PM Central Time on January 12, 2017. Good luck.

Q / A

1. 48-port POE gigabit switches for Mansueto (current standard Cisco Catalyst 3850/2960) …is there a preference on which, or just go with least expensive option? If 2960, would you like us to include the stacking cables? a. The 3850 is used as the CORE switch and the 2960 are used for distribution. Yes, we prefer stacking cables.

2. For the POE switches, I didn’t see a mention of SFP modules …do you want us to include those in our quote? a. Yes, please include the SFP modules.

3. Category 2 services …do you want our bid to include professional services for configuration/implementation? a. Yes.

4. Also, Sentinel’s managed/monitoring services, is this something you would like us to include in our response? a. Yes, in terms of erate eligible maintenance for the Noble Network networking equipment.

5. Is it the intent of Noble Network to apply for (submit) a Build Entity Applicant Reimbursement (BEAR) form? a. Yes, we typically pay our erate invoice at 100% and request a refund.

6. In a nutshell, then, it is generally acceptable for POs and orders to be placed prior to April 1, but if shipments arrive at the customer’s location (or if other billable work is done on the customer premise) before April 1, that work (or equipment) will not qualify for reimbursement due to being delivered prior to the start of the funding year.” (FFL) a. Thank you. Noble will notify the selected vendor when it is time to start a project.

7. What is the address of Onshore's Datacenter? a. 216 W. Jackson

8. Do you have a need for an Auto-Attendant? If yes, how many? a. 18

9. Do you require integration with paging? If yes, how many ports and locations? a. All sites need to have the ability to page all phones during emergencies.

10. Do you have a specific preference for types of users; Basic, Essential, Enterprise or UC? a. Enterprise

11. Quantity and type of devices (smartphones, basic phones, mi-fi) a. The 606 lines will be cellular lines

12. Quantity of minutes needed a. 400 Minutes

13. Desired amount of data a. Unlimited

14. Equipment preferences a. Noble currently support Iphones, Androids and Blackberry

15. Feature needs such as text a. Text Messaging

16. Any additional solutions to be shown as options such as EPTT (Enhances Push to Talk), MDM, etc. a. No thank you.

Best regards,

Donnell P. Layne Director of Information Technology Noble Network of Charter Schools Operating Noble Street Charter School 773.682.2547 (mobile) [email protected] http://noblenetwork.org/

“Raise the Standard" 1Gb or Greater CIR onShore Baker College Prep Internet Datacenter 1Gb Port Client Managed Firewall 1Gb CIR Butler College Prep 1Gb Port 1Gb Port Location 20 1Gb CIR 1Gb CIR

Chicago Bulls College Prep 1Gb Port 1Gb Port 1Gb CIR 1Gb CIR

Location 19

1Gb Port 1Gb Port 1Gb CIR DRW College Prep 1Gb CIR

1Gb Port Location 18 AT&T ASE 1Gb CIR

1Gb Port 1Gb CIR 1Gb Port 1Gb CIR UIC College Prep

1Gb Port Gary Comer College Prep 1Gb CIR 1Gb Port Middle School 1Gb CIR

The (new campus!) 1Gb Port 1Gb Port 1Gb CIR 1Gb CIR Client: Rowe-Clark 1Gb Port Noble Network of Charter Math & Science Academy 1Gb Port 1Gb Port 1Gb CIR 1Gb CIR 1Gb CIR Schools 1Gb Port 1Gb Port 1Gb Port Title: 1Gb CIR 1Gb CIR 1Gb CIR WAN/Internet Upgrade ITW David Speer Academy (new campus!) Version: 1.0 Noble Street Created: 2/19/2015 College Prep Updated: 2/20/2015 Updated By: Ron Kovar