Initial Environmental Examination

Total Page:16

File Type:pdf, Size:1020Kb

Initial Environmental Examination Appendix 11 Initial Environmental Examination Document Stage: Update Project Number: P47037-005(SRI) October 2016 SRI: Green Power Development and Energy Efficiency Improvement Investment Program – Tranche 2 (Transmission Infrastructure Enhancement) Prepared by Ceylon Electricity Board, Ministry of Power and Renewable Energy, Democratic Socialist Republic of Sri Lanka for the Asian Development Bank. This is an updated version of the draft originally posted in July 2016 available on https://www.adb.org/projects/documents/sri- gpdeeiip-t2-transmission-infrastructure-enhancement-jul-2016-iee i CURRENCY EQUIVALENTS (as of 26 October 2016) Currency unit – Sri Lanka rupee/s (SLRe/SLRs) SLRe1.00 = $0.00678 $1.00 = SLRs147.55 ABBREVIATIONS ADB – Asian Development Bank CCD – Coast Conservation Department CEA – Central Environment Authority CEB – Ceylon Electricity Board DC or D/C – Double Circuit DPR – Detailed Project Report DSD – Divisional Secretariat Divisions EA – Executing Agency EARF – Environmental Assessment and Review Framework EIA – Environmental Impact Assessment EMoP – Environmental Monitoring Plan EMP – Environmental Management Plan EHV – Extra High Voltage GHG – Green House Gas GND – Gram Niladhari Divisions GoSL – Government of Sri Lanka GRC – Grievance Redress Committee GRM – Grievance Redress Mechanism GSS – Grid Sub Station IA – Implementing Agency IEE – Initial Environmental Examination LILO – Line – in- Line- out MFF – Multi-tranche Financing Facility MPRE – Ministry of Power and Renewable Energy PAA – Project Approving Authority PCB – Poly Chlorinated Biphenyl PMU – Project Management Unit GSS – Power Sub Station REA – Rapid Environment Assessment ROW – Right of Way RP – Resettlement Plan SC or S/C – Single Circuit SF6 – Sulphur Hexafluoride SPS – Safeguard Policy Statement WEIGHTS AND MEASURES ha (hectare) – Unit of area km (kilometer) – 1,000 meters kV – kilovolt (1,000 volts) kW – kilowatt (1,000 watts) MW – Mega Watt NOTE{S} In this report, "$" refers to US dollars. “SLRs” refers to Sri Lankan rupees This Initial Environmental Examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Table of Contents EXECUTIVE SUMMARY 1 1.0 INTRODUCTION 3 1.1 Background 3 1.2 Scope of Work and Methodology Adopted 5 2.0 POLICY, LEGAL, AND ADMINSTRATIVE FRAMEWORK 7 2.1 Applicable Environmental and other Legislations 7 2.2 Assessment of Legal and Institutional Framework 9 2.3 Applicable International Environmental Agreements 16 2.4 Asian Development Bank’s Safeguards Policies 17 2.5 Other documents relevant to ADB’s Safeguard Policy Statement, 2009 17 3.0 DESCRIPTION OF THE PROJECT 19 3.1 The Project 19 3.2 Type of Project 20 3.3 Justification of the Project 21 3.4 Location 24 3.5 Size and Magnitude of the Operation 38 3.6 Implementation Plan 47 4.0 DESCRIPTION OF ENVIRONMENT (BASELINE DATA) 49 4.1 Kegalle District 49 4.2 Ratnapura District 52 4.3 Nuwara Eliya District 57 4.4 Monaragala District 60 4.5 Hambantota District 65 4.6 Polonnaruwa District 71 4.7 Batticaloa District 75 4.8 Gampaha District 79 4.9 Puttlam District 84 4.10 Colombo District 89 4.11 Kalutara District 93 5.0 ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES 97 5.1 Environment Impacts and Mitigation Measures 97 6.0 ANALYSIS OF ALTERNATIVES 109 6.1 CEB’S Approach for Route Selection 109 6.2 Alternatives for Subproject Components 109 7.0 INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 116 7.1 Consultation Findings 118 8.0 GRIEVANCE REDRESS MECHANISM 122 8.1 Awareness of Stakeholders 122 8.2 The Grievance Redress Mechanism and PUCSL 122 9.0 ENVIRONMENTAL MANAGEMENT PLAN 126 9.1 Environmental Management Plan 126 9.2 Environmental Management Plan Budget Costs 131 9.3 Monitoring of Environmental Management Plan (EMP) 131 9.4 Implementation arrangements 132 9.5 Critical Environmental Review Criteria 135 9.6 Associated Facilities 136 10.0 CONCLUSIONS AND RECOMMENDATIONS 137 Annexure 1 System Design Standards Followed by CEB for Setbacks etc. 139 Annexure 2 Alternative Site Analysis for Grid Substations 144 Annexure 3 Alternative Route Analysis for Transmission Lines 151 Annexure 4 Inventorisation along the Transmission Lines 156 Annexure 5 Environment Management Plan (EMP) 190 Annexure 6 Environmental Parameters and Periodicity for Environmental Monitoring Plan 200 Annexure 7 Environmental Safeguard Monitoring Report 205 Annexure 8 Granting of Necessary Wayleaves for Electricity Networks in Sri Lanka - Guidelines for Licensees, Divisional Secretaries and Landowners and/or Occupiers 207 EXECUTIVE SUMMARY 1. ADB is proposing to extend USD 150 million loan (with UDS 30 million cofinancing from AFD) to Sri Lanka’s power sector for Green Power Development and Energy Efficiency Improvement Investment Program (Tranche 2) with a focus to support wind-power development and identify the transmission and distribution projects for evacuation of renewable energy (wind) parks/ projects and overall improvement of energy efficiency and capacity development. 2. The subprojects of Transmission Infrastructure Enhancement of the Green Power Development and Energy Efficiency Improvement Investment Tranche 2 Program include: T-1 Construction of Polpitiya-Hambantota 220 kV Transmission Line T-2 Construction of Colombo B 132/11 kV Grid Substation (GSS) T-3 Augmentation of 220/132/33 kV Biyagama and Kotugoda, 132/33 kV Kolonnawa, 220/33 kV Mannar, Colombo C, and Kolonnawa Stanley Old Grid Substations T-4 Construciton of Padukka – Horana 132 kV Transmission Line T-5 Construction of 220/132/33 kV Hambantota, 220/33 kV Nadukuda and Biyagama Grid Substations T-6 Augmentation of 132/33 kV Ko Padukka, Horana, and Dehiwala Grid Substation T-7 Second Circuit Stringing of Habarana - Valachchenai132 kV Transmission Line T-8 Augmentation of 132/33 kV Madampe Grid substation 3. The Polipitya GSS, Habrana GSS and Padukka GSS were funded under previous ADB projects. The construction of substation involves utilisation of existing CEB lands for 220/33 kV Biyagama, 132/33 kV old Biyagama, Kotugoda and Kolonnawa Old GSSs, 32/11 kV Colombo B GSS, 132/33 kV Madampe GSS. The proposed 220/33 kV Hambantota GSS will be built on 10 acres government land (owned by Mahaweli Authority as shown in the New Zoning Map of the Greater Hambantota Development Area - 2030). The GSS land in Gonnoruwa, Hambantota is within the Managed Elephant Range (MER) and the line is located outside as shown in Figure 11. Very small numbers of trees have to be removed from the land at Hambantota GSS. For any sub-project, acquisition of land will not be required from any surrounding communities. 4. In case of construction of new transmission line, the project would involve survey work, forest work and clearance, design and engineering of plant equipment, floating tenders for procurement, civil work related to 220 kV line and 220/132/33 kV GSS testing and commissioning. Total project work is expected to be completed in 36 months. 5. Impacts are manageable and can be managed cost effectively - environmental impacts are likely to result from the proposed project development. Careful mitigation and monitoring, specific selection criteria and review/assessment procedures have been specified to ensure that minimal impacts take place. The detailed design would ensure inclusion of any such environmental impacts, that could not be specified or identified at this stage, are taken into account and mitigated where necessary. Those impacts can be reduced through the use of mitigation measures such as correction in work practices at the construction sites, or through the careful selection of sites and access routes. 6. The proposed project will have number of positive impacts and negative impacts to the existing environment as follows: Significant improvement in the quality and reliability of the electricity supply to the project affected area according to current demand is the main positive impact. 1 Removal of trees for the transmission line is the main negative impact to the proposed project area. Environment pollution due to cut and fill operations, transportation of construction materials, disposal of debris, disturbance to the farming activities, nuisance from dust, noise, vehicle fumes, black smoke, vibration etc. due to construction activities are the short term negative impacts due to proposed project. There will be loss of agricultural productivity due to obstruction and reduce the land of paddy fields as well as cutting of home gardens of coconut and timber trees which will be compensated based on established rates by CEB. 7. Benefits far outweigh negative impacts - The proposed project will improve operational efficiency and quality of power, reliability of the system and at the same time will reduce system losses. Supply of power to both the local areas and regions will boost economic development of the area by strengthening the power transmission infrastructure. Overall, the major social and environmental impacts associated with transmission projects are limited to the construction period and can be mitigated to an acceptable
Recommended publications
  • Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera
    University of North Dakota UND Scholarly Commons Theses and Dissertations Theses, Dissertations, and Senior Projects 12-1-2012 Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera Follow this and additional works at: https://commons.und.edu/theses Recommended Citation Waidyasekera, Deepthi Lekani, "Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012" (2012). Theses and Dissertations. 668. https://commons.und.edu/theses/668 This Thesis is brought to you for free and open access by the Theses, Dissertations, and Senior Projects at UND Scholarly Commons. It has been accepted for inclusion in Theses and Dissertations by an authorized administrator of UND Scholarly Commons. For more information, please contact [email protected]. SPATIAL DIMENSIONS OF CONFLICT-INDUCED INTERNALLY DISPLACED POPULATION IN THE PUTTALAM DISTRICT OF SRI LANKA FROM 1980 TO 2012 by Deepthi Lekani Waidyasekera Bachelor of Arts, University of Sri Jayawardanapura,, Sri Lanka, 1986 Master of Science, University of Moratuwa, Sri Lanka, 2001 A Thesis Submitted to the Graduate Faculty of the University of North Dakota In partial fulfilment of the requirements For the degree of Master of Arts Grand Forks, North Dakota December 2012 Copyright 2012 Deepthi Lekani Waidyasekera ii PERMISSION Title Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Department Geography Degree Master of Arts In presenting this thesis in partial fulfillment of the requirements for a graduate degree from the University of North Dakota, I agree that the library of the University shall make it freely available for inspection.
    [Show full text]
  • Clean Energy and Access Improvement Project
    Resettlement Planning Document Resettlement Plan Document Stage: Final Project Number: 39419 July 2008 SRI: Clean Energy and Access Improvement Project Prepared by Ceylon Electricity Board The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA CEYLON ELECTRICITY BOARD NATIONAL GRID DEVELOPMENT PROJECT LOAN AGREEMENT NO: RESETTLEMENT AND COMPENSATION PLAN ENVIRONMENT UNIT CEYLON ELECTRICITY BOARD COLOMBO SRI LANAKA Abbreviations ADB - Asian Development Bank BoI - Board of Investment 0C - Celsius CEA - Central Environmental Authority CEB - Ceylon Electricity Board db(A) - A-Weighted sound measurement in decibels DS - Divisional Secretary EIA - Environmental Impact Assessment EPL - Environmental Protection License GIS - Gas Insulated Substation GN - Grama Niladhari GS - Grid Substation IEC - International Electrotechnical Commission IEE - Initial Environmental Examination IPP - Independent Power Producer km - kilometer kV - kilovolt LoI - Letter of Intent m - meter mm - millimeter MOH - Medical Officer of Health MVA - Megavolt Ampere MW - Megawatt NCRE - Non-Conventional Renewable Energy NGO - Non Government Organization NIRR - National Policy on Involuntary Resettlement NEA - National Environment Act PAA - Project Approving Agency PAC - Project Approving Committee PSS/e - Power System Simulation REA - Rapid Environmental Assessment ROW - Right of Way SEA - Sustainable Energy Authority SLBC - Sri Lanka Broadcasting Corporation SPPA - Small Power Purchase Agreement SPP - Small Power Producer VRR - Victoria, Randenigala, Rantembe W - Watt Page 1 Executive Summary This Resettlement and Compensation Plan covers the proposed National Grid Development Project of Ceylon Electricity Board, Sri Lanka, scheduled for implementation from year 2008.
    [Show full text]
  • Study of Hydropower Optimization in Sri Lanka
    JAPAN INTERNATIONAL COOPERATION AGENCY CEYLON ELECTRICITY BOARD(CEB) DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA STUDY OF HYDROPOWER OPTIMIZATION IN SRI LANKA FINAL REPORT SUMMARY FEBRUARY 2004 ELECTRIC POWER DEVELOPMENT CO., LTD. NIPPON KOEI CO., LTD. TOKYO, JAPAN The Main Dam Site (looking downstream) The Kehelgamu Oya Weir Site (looking upstream) The Powerhouse Site (looking from the right bank) The Study of Hydropower Optimization in Sri Lanka CONTENTS CONCLUSION AND RECOMMENDATION .............................................................. CR - 1 Conclusion .................................................................................................................. CR - 1 Recommendation ......................................................................................................... CR - 5 PART I GENERAL 1. INTRODUCTION .................................................................................................... 1 - 1 2. GENERAL FEATURES OF SRI LANKA ............................................................... 2 - 1 2.1 Topography ....................................................................................................... 2 - 1 2.2 Climate ............................................................................................................. 2 - 1 2.3 Government ....................................................................................................... 2 - 2 3. SOCIO-ECONOMY ................................................................................................. 3 - 1
    [Show full text]
  • Watawala Carolina Tea Factory
    Watawala MAP OF WATAWALA AND AROUND Carolina Tea Factory - Watawala TP - 94 (0) 11 4702400 . Carolina Tea Company of Ceylon Ltd. Incorporated in 1892 is one of the pioneer tea companies in the country, set up primarily to plant tea. It consisted of a group of plantations situated in Lower Dickoya. They were Agarawatte, Carolina, Kandawella, Mount Jean, Wigton, Udeapola Group, Trafalgar, Goarfell and St.Margaret Estates.The Management of this group that was originally with Leechman and Company changed to Mackwoods Estates & Agencies Ltd. at a later date. According to the times of Ceylon Green Book of 1939, this group had over 1,000 hectares in tea, 245 hectares in rubber, a few hundred coconut trees, and 726 hectares uncultivated, comprising a total extent at the stage was considered a substantial area for administration. The Carolina tea factory was one of the original "central factories" constructed by the river that ran by the estate, to avail themselves of water power. It was indeed an improvement to some of other factories of the day, with no mud floors and cadjan roofs. The building was of wood assembled firmly on stone pillars. It had three floors going up to the height of 42 feet from ground to ridge. Provision had been made for further expansion, but there was sufficient space to accommodate all the leaf not only from that group, but from many other adjoining plantations who were satisfied with a return of 9 cents (about 2p) per pound. The novelty was that very often than not, the green leaf arrived by train.
    [Show full text]
  • CEB Long Term Generating Expansion Plan 2015-2034
    CEYLON ELECTRICITY BOARD LONG TERM GENERATION EXPANSION PLAN 2015-2034 Transmission and Generation Planning Branch Transmission Division Ceylon Electricity Board Sri Lanka July 2015 CEYLON ELECTRICITY BOARD LONG TERM GENERATION EXPANSION PLAN 2015-2034 Transmission and Generation Planning Branch Transmission Division Ceylon Electricity Board Sri Lanka July 2015 Long Term Generation Expansion Planning Studies 2015- 2034 Compiled and prepared by The Generation Planning Unit Transmission and Generation Planning Branch Ceylon Electricity Board, Sri Lanka Long-term generation expansion planning studies are carried out every two years by the Transmission & Generation Planning Branch of the Ceylon Electricity Board, Sri Lanka and this report is a bi- annual publication based on the results of the latest expansion planning studies. The data used in this study and the results of the study, which are published in this report, are intended purely for this purpose. Price Rs. 3000.00 © Ceylon Electricity Board, Sri Lanka, 2015 Note: Extracts from this book should not be reproduced without the approval of General Manager – CEB Foreword The ‘Report on Long Term Generation Expansion Planning Studies 2015-2034’, presents the results of the latest expansion planning studies conducted by the Transmission and Generation Planning Branch of the Ceylon Electricity Board for the planning period 2015- 2034, and replaces the last of these reports prepared in April 2014. This report, gives a comprehensive view of the existing generating system, future electricity demand and future power generation options in addition to the expansion study results. The latest available data were used in the study. The Planning Team wishes to express their gratitude to all those who have assisted in preparing the report.
    [Show full text]
  • Natural Resource Profile of the Kelani River Basin January 2016
    Medium to Long-term Multi-Stakeholder Strategy and Action Plan for Management and Conservation of the Kelani River Basin 2016-2020 Natural Resource Profile of the Kelani River Basin January 2016 This natural resource profile is developed to support the formulation of the “Medium to Long-term Multi-Stakeholder Strategy and Action Plan for Management and Conservation of the Kelani River Basin” developed by the Central Environment Authority (CEA) and International Union for the Conservation of Nature (IUCN) Sri Lanka Country Office, with the participation of a large number of stakeholder groups and technical inputs from the Ministry of City Planning and Water Supply and the United Nations Children’s Fund (UNICEF). Natural Resource Profile of the Kelani River Basin Acknowledgement: Ms. Chandani Edussuriya, Research and Development Division, CEA, Ms. Sandamali Pathirage and Ms. Darshani Wijesinghe, IUCN Sri Lanka provided the maps and data for the natural resource profile. Ms. Kushani de Silva supported in coordination of the compilation of information. Ms. Dinithi Samarathunga and Ms. Padmi Meegoda supported in edits. Mr. Suranga De Silva, UNICEF Sri Lanka and Mr. Ajith Rodrigo, CEA supported in the project management. Compilation: Mr. Sampath de A Goonatilake Mr. Naalin Perera Mr. Gyan De Silva Prof. Devaka Weerakoon Dr. Ananda Mallawatantri Editor: Dr. Ananda Mallawatantri, IUCN ISBN: 978-955-0205-41-7 Citation: Goonatilake, S. de A., N. Perera, G.D. Silva, D. Weerakoon and A. Mallawatantri. 2016. Natural Resource Profile of the Kelani
    [Show full text]
  • Puttalam Lagoon System an Environmental and Fisheries Profile
    REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) --------------------------------------------------------- An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1 : Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environmental and land use associated with the Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) – SRI LANKA An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1- Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environment and land use associated with Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 i Disclaimer and copyright text This publication has been made with the financial support of the Spanish Agency of International Cooperation for Development (AECID) through an FAO trust-fund project, the Regional Fisheries Livelihoods Programme (RFLP) for South and Southeast Asia. The content of this publication does not necessarily reflect the opinion of FAO, AECID, or RFLP. All rights reserved. Reproduction and dissemination of material in this information product for educational and other non-commercial purposes are authorized without any prior written permission from the copyright holders provided the source is fully acknowledged. Reproduction of material in this information product for resale or other commercial purposes is prohibited without written permission of the copyright holders.
    [Show full text]
  • Buddhist-Christian Dialogue and Action in the Theravada Countries of Modern Asia------233
    Buddhist-Christian Dialogue and Action in the Theravada Countries of Modern Asia: A Comparative Analysis of the Radical Orthopraxis of Bhikkhu Buddhad åååsa and Aloysius Pieris By In-gun Kang, S.J. PhD Thesis Heythrop College, University of London 2012 - 1 - Abstract This thesis constructs a creative Buddhist-Christian dialogue and action, appropriate to the Theravada countries of Asia in the era of globalization. In the face of problems and challenges never experienced before, it asks how Buddhism and Christianity can act as a source of hope to the people who suffer from socio-economic injustice, religio- political conflicts, and environmental crises. It argues that an answer is found in the dialogue between two models of radical orthopraxis: Bhikkhu Buddhad åsa’s Dhammic essentialist praxis for human liberation and Aloysius Pieris’ dialogical integrationist action for justice and peace. Through a comprehensive study of each model, this thesis shows how each thinker develops a liberative spirituality of socio-spiritual transformation by radically returning to the originating sources of their respective religious traditions; and how they engage with the root problems of modern Thailand and Sri Lanka respectively, from their liberative thought and praxis. It is argued that Buddhad åsa’s Dhammic essentialism and Pieris’ dialogical integrationism are not contradictory, but enhance each other as counter-point movements, in their common vision and struggle to build a more just, peaceful and humanistic community. Through a comparative analysis of both models, this thesis reveals how Buddhad åsa and Pieris pursue their shared spirituality of spiritual detachment and social engagement in their respective grassroots communities, Suan Mokkh and Tulana, providing inspiration for our own Buddhist-Christian radical orthopraxis in the challenging situation of neo- liberal globalization.
    [Show full text]
  • Democratic Socialist Republic of Sri Lanka Power Subsector Review
    Report No 5713- DemocraticSocialist Republic of SriLanka PowerSubsector Review Public Disclosure Authorized July25, 1986 ProjectsDepartment SouthAsia RegionalOffice FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Document of the 'VorId Bank Public Disclosure Authorized This documenthas a restricteddistribution and may be used by recipients only in the performanceof their official duties.Its contents may not otherwiise bedisdosed without WorldBank authorization. SRI LANKA POWER SUBSECTOR REVIEW Currency Equivalents Mid-1983 US$1.00 = SL Rs 23.53 SL Rs 1.00 = US$0.043 Mid-1984 US$1.00 = SL Rs 25.44 SL Rs 1.00 = US$0.039 End-1984 US$1.00 = SL Rs 26.20 SL Rs 1.00 = US$0.038 End-1985 USR1.00 = SL Rs 27.20 SL Rs 1_nn = US$0.037 WEIGHTS AND MEASURES . kilometer (km) = 0.621 mile I ton = 1.102 short ton (sh ton) 0.984 long ton (Ig ton) 1 kilowatt (kW) = 1,000 watts (W) 3 1 megawatt (MW) = 1,000 kilowatts (10 kWa 3. gigawatt = 1,000,000 kiiowatts (10 kW) I kilowatt-hour (W h)= 1,000 watt-hours 3 1 megawatt-hour (MWh) = 1,000 kilowatt-hours (10i kWh) I. gigawatt-hour (GWh) = 1,000,000 kilow3att-hours (106 kWh) 1 kilovolt (kV) = 1,000 volts (10 V) I kilovolt-ampereb(kVA) = 1,000 volt-amperes (VA) 1 megavolt-ampere (MVA) = 1,000 kilovolt-amperes (103 kVA) ABBREVIAIIONS AND ACRONYMS ADB - Asian Oevelopment Bank AMP - Accelerited Mahaweli Program CEB - Ceylon Electricity Board CPC - Ceylon Petroleum Corporation DGEU - Department of Government Electrical Undertakings ECT - Energy Coordinating Team GOSL - Government of Sri Lanka GTZ - German Agency for Technical Cooperation HV - High Voltage LV - Low Voltage LECO - Lanka Electric (Private) Company LRAIC - Long-Run Average Incremental Cost LRMC - Long-Run Marginal Cost MASL - Mahaweli Authority of Sri Lanka MMD - Ministry of Mahaweli Development MPE - Ministry of Power and Energy MV - Medium Voltage WMP - Water Management Panel CEB's Fiscal Year is the calendar year FOR OFFICAL USE ONLY This report was prepared by N.C.
    [Show full text]
  • OB (3) 12-07-2019 E with out Cut.Pub
    ( ) (Eighth Parliament - Third Session) No. 3.] ORDER BOOK OF PARLIAMENT From Tuesday, July 23, 2019 inclusive Issued on Friday, July 12, 2019 Tuesday, July 23, 2019 QUESTIONS FOR ORAL ANSWERS 1. 46/’18 Hon. Hesha Withanage,— To ask the Minister of Health, Nutrition & Indigenous Medicine,—(1) (a) Will he inform the House about— (i) the number of dengue patients identified within Ratnapura District in the year 2017; (ii) the figures for each of the Divisional Secretariat Divisions separately; and (iii) the special measures that have already been taken to prevent dengue in Ratnapura District? (b) If not, why? 2. 151/’18 Hon. Chaminda Wijesiri,— To ask the Minister of Internal & Home Affairs and Provincial Councils & Local Government,—(1) (a) Will he inform this House — (i) separately on per year basis, of the number of representatives of local government bodies who participated in international training programmes on solid waste management in each year from 2010 to date; (ii) of the names of the aforesaid representatives and the names of the local government bodies they belong to; (iii) separately of the names of countries and cities where the aforesaid training programmes were held and the duration of each of those programmes; (iv) separately of the amount of money that was spent on participating in those training programmes; and (v) of the names of local government institutes which implemented programmes for solid waste management after their representatives had participated in such training programmes? (b) If not, why? (2) 3. 269/’18
    [Show full text]
  • SRI LANKA a Hidden Displacement Crisis
    31 October 2012 SRI LANKA A hidden displacement crisis More than three years after the end of the 26-year armed conflict between the Sri Lankan armed forces and the Liberation Tigers of Tamil Eelam (LTTE), nearly 470,000 people displaced during its various stages have returned to their home areas. This does not mean, however, that there is no internal displacement in the country any more. As of the end of September 2012, more than 115,000 internally displaced people (IDPs) were still living in camps, with host communities or in transit sites, A cyclone hits the return areas in northern Sri Lanka where people who had been or had been relocated, often against their displaced by the armed conflict continue to live in make-shift shelters constructed from old tin sheets and tarpaulins several months after their return. will, to areas other than their places of (Photo: NRC/October 2012) origin. Among those registered as having returned, many have not been able to achieve a durable solu- tion but continue to face difficulties in accessing basic necessities such as shelter, food, water and sanitation, in rebuilding their livelihoods, and in exercising their civil rights. De-mining op- erations are still ongoing in livelihood areas. Unresolved land issues have been a major obstacle to durable solutions for IDPs and IDP returnees. Conflict-affected areas remain highly militarised, which has made progress towards achieving durable solutions more difficult. The military has become an important economic player and a key competitor of local people including returnees in the areas of agriculture, fishing, trade, and tourism.
    [Show full text]
  • List of Printing Presses in Sri Lanka
    LIST OF PRINTING PRESSES IN SRI LANKA (CORRECTED UPTO DECEMBER 31st 2013) DEPARTMENT OF NATIONAL ARCHIVES NO. 07, PHILIP GUNAWARDENA MAWATHA, COLOMBO 07, SRI LANKA. 1 AMPARA DISTRICT Name of the Press Postal Address Proprietor Ampara Jayasiri Press. 59, Kalmunai Road, Ampara. P. S. A. Dharmasena Piyaranga Press, 46, D. S. Senanayaka Veediya, W. Albert Ampara. Samaru Printrs, 41/A, Fourth Avenue, D. B. Ariyawathi Ampara. A. T. Karunadasa S. A. Piyasena N. D. C. Gunasekara K. D. Chandralatha D. W. Dayananda I. G. Piyadasa E. D.Wicramasinghe G. G. Jayasinghe G. G. Siripala Akkaraipattu Expert Printers, 5, Careem Road, J. Mohamed Ashraf Akkaraipattu-01 Ruby printers, Main Street, Akkaraipattu F. M. Vussuflebai Kalmunai An – Noor Graphics Offset Akkarapattu Road, Kalmunai. Lebbe Khaleel Printers, Rahman Azeez Printing Industries, 97, Main Street, Kalmunai A. A. Azeez Godwin Press, 147, Main Street, Kalmunai T. Mahadeva Illampirai Press, Division, No. 1, Main Street M. I. M. Salih Marudamunai, Kalmunai Manamagal Auto Main Street, Kalmunai M. A. A. Majeed Printing Industries, Modern Printers, 139, Main Street, Kalmunai P. V. Kandiah 2 Maruthamunai Abna Offset Printers. 07, Main Street, U. L. Muhamed Maruthamunai.-01 Nakip Sainthamurathu National Printers, Main Street, Sainthamurathu Z. Z. K. Kariapper Royal Offset Printers, 254 A, Main Street, Abdul Haq Jauffer Sainthamaruthu - 09 Kariapper Star Offset Printers, 502, Main Street, M. I. H. Ismail Sainthamurathu Samanthurei. Easy Prints, Hidra Junction, Samanthurei. Ibra Lebbai Rizlia Sandunpura Eastern Press, 172, Muruthagaspitiya, G. G. Karunadasa Sandunpura Uhana Tharindu Offset Printers. Uhana. Meththananda Rubasinghe 3 ANURADHAPURA DISTRICT Name of the Press Postal Address Proprietor Anuradhapura Charles Press, 95 , Maitripala Senanayake- T.
    [Show full text]