The World Bank Report No: ISR10091

Implementation Status & Results Eco-Farming Project (P096556)

Operation Name: Eco-Farming Project (P096556) Project Stage: Implementation Seq.No: 6 Status: ARCHIVED Archive Date: 15-May-2013 Country: China Approval FY: 2009

Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 02-Dec-2008 Original Closing Date 30-Jun-2014 Planned Mid Term Review Date 16-May-2011 Last Archived ISR Date 06-Apr-2012 Public Disclosure Copy Effectiveness Date 27-May-2009 Revised Closing Date 30-Jun-2014 Actual Mid Term Review Date 27-May-2011

Project Development Objectives Eco-Farming Project (P096556) Project Development Objective (from Project Appraisal Document) To deliver direct environmental and economic benefits from the integration of biogas in farming and cooking in rural households. In addition, the project aims to reduce greenhouse gas emissions through methane combustion and reduced burning of coal and firewood in the project areas. Has the Project Development Objective been changed since Board Approval of the Program?

Public Disclosure Authorized Yes No

Component(s)

Component Name Component Cost Integrated Eco-Farming Systems. 382.07 Local Technical Extension and Biogas Service Systems. 15.23 Project Management, Monitoring and Evaluation. 23.85

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory

Public Disclosure Authorized Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate

Implementation Status Overview This ISR reports the implementation progress after the Sixth SPN Mission. The next supervision mission is scheduled for late May, 2013. Public Disclosure Copy Project implementation has accelerated since the 6th Supervision Mission with 80% of the overall PAD investment cost completed and overall implementation quality of works continues to be satisfactory and over 350,000 rural households are benefiting from the improvement on their living environment and production conditions, cost saving for fertilizers,

Page 1 of 10 Public Disclosure Authorized The World Bank Report No: ISR10091

and improved yields. However, the disbursement for the last four months was still slower than expected with actual disbursement rate about 5%. With only fourteen months left before project closing on June 30, 2014, it is critical for the central PMO and local PMOs to speed up further the project implementation and reimbursement.

Locations Country First Administrative Division Location Planned Actual China Sheng Yixian Linchang

China Shi Zhongzhou

China Chongqing Shi Yunyang Xian

China Hunan Youxian Chengguanzhen Public Disclosure Copy Not Entered Not Entered Not Entered

China Hunan Yizhang Xian

China Anhui Sheng Yi Xian

China Guangxi Zhuangzu Zizhiqu Xing'an Xian

China Hunan Xiangyin Xian

China Hunan Xiangtan Xian

China Hubei Xianfeng Xian

China Chongqing Shi Wulong Xian

China Hunan Wugang Shi

China Chongqing Shi Wanzhou Qu

China Hunan Wangcheng Xian

China Anhui Sheng Huangshan

China Anhui Sheng Xian

China Anhui Sheng Tianchang Shi

China Anhui Sheng Taihu Xian

China Anhui Sheng Shouchun

China Anhui Sheng Quanjiao Xian Public Disclosure Copy China Anhui Sheng Qingyang Xian

Page 2 of 10 The World Bank Report No: ISR10091

Country First Administrative Division Location Planned Actual China Guangxi Zhuangzu Zizhiqu Pingle Xian

China Hunan Ningxiang Xian

China Anhui Sheng Shi

China Guangxi Zhuangzu Zizhiqu Luchuan Xian

China Hunan Longhui Xian

China Hunan Liyang

Public Disclosure Copy China Hunan Linwu Chengguanzhen

China Hunan Linli Xian

China Hubei Lichuan Shi

China Chongqing Shi Liangping Xian

China Hunan Lengshuitan Qu

China Chongqing Shi Kai Xian

China Anhui Sheng Jixi Xian

China Anhui Sheng Jingchuan

China Hubei Jianshi Xian

China Chongqing Shi Jiangjin Shi

China Anhui Sheng Huoshan Xian

China Anhui Sheng Huoqiu Xian

China Hunan Huayuan

China Anhui Sheng Huaining Xian

China Hunan Hengnan Xian

China Hubei Hefeng Xian

China Chongqing Shi Hechuan Shi

Public Disclosure Copy China Anhui Sheng Guichi Qu

China Anhui Sheng Xian

Page 3 of 10 The World Bank Report No: ISR10091

China Guangxi Zhuangzu Zizhiqu Gongcheng Xian

China Chongqing Shi Fuling

China Guangxi Zhuangzu Zizhiqu Fuchuan Yaozu Zizhixian

China Anhui Sheng Feidong Xian

China Guangxi Zhuangzu Zizhiqu Fangcheng Gezu Zizhixian

China Hubei Enshi Shi

China Chongqing Shi Dianjiang Xian Public Disclosure Copy China Hunan Cili Xian

China Chongqing Shi Changshou Qu

China Hunan Changning Shi

China Guangxi Zhuangzu Zizhiqu Cangwu Xian

China Guangxi Zhuangzu Zizhiqu Bobai Xian

China Chongqing Shi Bishan Xian

China Hubei Badong Xian

China Hunan Yongding Qu

China Anhui Sheng Yixiu Qu

China Hubei Xuan'en Xian

China Hubei Laifeng Xian

Results

Project Development Objective Indicators Public Disclosure Copy

Page 4 of 10 The World Bank Report No: ISR10091

Indicator Name Core Unit of Measure Baseline Current End Target Reduction in greenhouse gas emissions as Text Value Currently households emit 700,000 equivalent per year Accumulative. Year 3: CH4 is extracted from wastes and converted to about 4 ton CO2 equivalent/ 600,000 ton CO2 equivalent CO2 as it is burnt as fuel. household/year. per year; Year 5: 800,000-1,000,000 ton CO2 equivalent per year. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Raised hh disposable income as fuel costs, Text Value Households buy abt. 1,500kg The cost for coal decreased Per project hh, cost for coal gathering time, and cooking time are reduced coal/year. Spend about 15% by 40 percent, cooking time will decrease by 30-50%, and as biogas slurry replaces synthetic fertilizer of cash revenues for chemical by 1.2 hrs/day, time for cooking time by 1-1.5 hrs/day,

Public Disclosure Copy and pesticides. fertilizer and pesticides. firewood collection by 2.2 hrs/ time for firewood collection by Spend 1-3 hrs/dayon day. 2 hrs/day. Part of chemical collecting firewood and 3-4 fertilizer+pesticides is hrs/day for cooking. replaced by biogas slurry. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Improved quality of life in rural households as Text Value Living conditions are quite Living conditions in project In each project village and for kitchens, farmyards, and surrounding dirty, especially in summer villages and households project households, living environments are cleaner and healthier. due to manure management. continue improving through conditions are significantly There is a lot of smoke in the better manure management better. Manure management kitchens while cooking. has improved so that surroundings are much better. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Targeted clients satisfied with agricultural Percentage Value 0.00 65.00 75.00 services (percentage) Date 01-Apr-2013 30-Jun-2014 Comments Targeted clients satisfied with agricultural Number Value 0.00 78650.00 119000.00 services - male (number) Sub Type Supplemental Targeted clients satisfied with agricultural Number Value 0.00 171500.00 277000.00 services - female (number) Sub Type Supplemental Public Disclosure Copy Targeted clients- male (number) Number Value 0.00 121000.00 158400.00

Page 5 of 10 The World Bank Report No: ISR10091

Sub Type Supplemental Targeted clients – female (number) Number Value 0.00 263900.00 369600.00 Sub Type Supplemental Targeted clients satisfied with agricultural Percentage Value 0.00 78650.00 119000.00 services - male Sub Type Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Breakdown Comments Clients who have adopted an improved agr. Number Value 0.00 240900.00 330000.00 technology promoted by the project Date

Public Disclosure Copy 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Clients who adopted an improved agr. Number Value 0.00 221000.00 280000.00 technology promoted by project – female Sub Type Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Breakdown Comments Project progress and impact monitoring carried Text Value MIS and M&E established. 2nd round survey report Reports generated by MIS out with an MIS and M&E system agreed upon submitted and M&E and submitted to with the Bank. the Bank in a timely manner. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of study tours conducted. Text Value 0 38 Accumulative. Year 1: 5; Year 2: 15; Year 3: 25; Year 4: 35; Year 5: 40. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of workshops conducted. Text Value 0 46 Accumulative. Year 1: 10; Year 2: 20; Year 3: 30; Year 4: 40; Year 5: 50. Date 25-Mar-2009 30-Sep-2011 30-Jun-2014 Comments Number of project staff trained. Text Value 0 9371 Accumulative. Year 1: 1,500; Year 2: 3,500; Year 3: 5,500; Year 4: 7,000; Year 5: 8,500. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Public Disclosure Copy

Page 6 of 10 The World Bank Report No: ISR10091

% of farmers satisfied with the technical Text Value 0 70% Year 3: 50%; Year 5: 75%. extension and biogas services. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of farmers visited demonstration sites. Text Value 0 data not available None specified. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of technician visits to farmers. Text Value 0 data not availabe None specified. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Value

Public Disclosure Copy % of trained farmers adopting the new Text 0 65% Year 3: 50%; Year 5: 75%. practices. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments The indicator is replaced by core sector indicator. Number of farmers trained in biogas operation Text Value 0 922203 Accumulative. Year 1: and management, and in new farm production 50,000; Year 2: 150,000; Year practices (person times). 3: 200,000; Year 4: 275,000; Year 5: 300,000. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments % of project hh expressing reduction in travel/ Text Value 0 55% Year 3: 50% of target transportation time. households; Year 5: 100% of target households. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Length of new village roads connecting natural Text Value 0 260 km Accumulative. Year 1: 45 km; villages to each other (Anhui, Chongqing, Year 2: 125 km; Year 3: 205 Guangxi). km; Year 4: 270 km; Year 5: 315 km. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Length of new roads connecting households to Text Value 0 71 Accumulative. Year 1: 11 km; farm fields (Anhui, Chongqing, Guangxi). Year 2: 31 km; Year 3: 51 km; Year 4: 71 km; Year 5: 78 km. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Public Disclosure Copy

Page 7 of 10 The World Bank Report No: ISR10091

Length of new village roads or paths Text Value 0 1100 km Accumulative. Year 1: 75 km; connecting households to village roads (Anhui, Year 2: 200 km; Year 3: 350 Chongqing, Guangxi). km; Year 4: 475 km; Year 5: 500 km. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of new households connected to Text Value 0 922,203 hh Accumulative. Year 1: 20,000 village water supply systems (Anhui, hh; Year 2: 50,000 hh; Year 3: Chongqing, Guangxi). 90,000 hh;Year 4: 130,000 hh; Year 5: 150,000 hh. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014

Public Disclosure Copy Comments Project hh time spent on cleaning biogas Text Value 0 130 hours/hh/year 120 hours/hh/year. system. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Project hh time spent on cooking. Text Value 3-4 hours/day 2.2 hours/day 2-3 hours/day. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Project hh time spent on collecting and Text Value 1-3 hours/day. 1.3 hours/hh/day on average 1-2 hours/day. preparing fuel. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Changes in project hh cash expenditures on Text Value RMB 1,000-2,000/hh/year. Decreased by about RMB Decrease by about RMB fertilizers and pesticides. 320/hh/year on average 100-400/hh/year. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Changes in project hh cash expenditures on Text Value RMB 500-1,00/hh/year. Decreased by aout RMB 210/ Decrease by about RMB fuel. hh/year 200-400/hh/year. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Percent of project hh expressing improved Text Value 0 95% of project HHs 90% of target households. quality of life due to biogas. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Chemical fertilizers and pesticides used by Text Value 500-1,500 kg/hh/year. Decreased by 25% per target Decrease by 20-30% per project households. household per year target household and year. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Public Disclosure Copy Comments

Page 8 of 10 The World Bank Report No: ISR10091

Greenhouse gas emissions (CO2 equivalent) Text Value 4 ton CO2 equivalent per 700,000 t CO2 emission Emission reduction is from project households' cooking. household per year. reduction expected to be about 2 ton CO2 equivalent per household per year. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014 Comments Number of households who have implemented Text Value 0 350,000 hh Year 1: 50,000 hh; Year 2: hh packages. 150,000 hh; Year 3: 300,000 hh; Year 4: 300,000-400,000 hh; Year 5: 400,000-400,000. Date 25-Mar-2009 01-Apr-2013 30-Jun-2014

Public Disclosure Copy Comments

Data on Financial Performance (as of 23-Jan-2013)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P096556 IBRD-76040 Effective 02-Dec-2008 27-Feb-2009 27-May-2009 30-Jun-2014 30-Jun-2014 P096556 IBRD-76050 Effective 02-Dec-2008 27-Feb-2009 27-May-2009 30-Jun-2014 30-Jun-2014 P105046 TF-91779 Effective 25-Apr-2008 25-Apr-2008 25-Apr-2008 30-Dec-2017 30-Dec-2017

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P096556 IBRD-76040 Effective USD 96.00 96.00 0.00 52.11 43.89 54.00 P096556 IBRD-76050 Effective USD 24.00 24.00 0.00 18.00 6.00 75.00 P105046 TF-91779 Effective USD 5.18 5.18 0.00 0.35 4.83 7.00

Disbursement Graph Public Disclosure Copy

Page 9 of 10 The World Bank Report No: ISR10091 Public Disclosure Copy

Key Decisions Regarding Implementation The Level 2 restructuring of the project to increase the amount of reimbursement for household package unit costs shall be carried out.

Restructuring History There has been no restructuring to date.

Related Projects P105020-Hubei Eco-Farming Biogas Project, P105046-Hubei Eco-Farming Biogas Project Public Disclosure Copy

Page 10 of 10