5. INDEX ...... 89 NEWS & NOTES PART – I I. GENERATION / RELIEF PARTICULARS: The Generation / Relief particulars for the month of April 2017 were as follows: Sl.No. Particulars In Million Units I. TNEB GENERATION (Gross) Hydro 163.888 Thermal 2291.482 Gas 158.255 Wind 0.200 TNEB TOTAL 2613.825 II NETT PURCHASES FROM CGS 2698.658 III PURCHASES IPP 139.828 Windmill Private 870.025 CPP, Co-generation & Bio-Mass (Provisional) 74.000 Solar (Private) 246.318 Through Traders (nett purchase) 2425.687 TOTAL PURCHASES 3755.859 IV Total Wheeling Quantum by HT consumers 548.066 Total Wheeling Quantum to Other States by Pvt. Generators 38.863 Total Wheeling 586.929 Power Sale by Private Generators (Exchange) (-) 7.348 Power Sale by Private Generators (Bilateral) (-) 31.515 V TOTAL (TNEB Own Gen+Purchase + wheeling quantum) 9616.407 VI Load shedding & Power cut relief (Approx) 0 VII Less energy used for Kadamparai pump 8.490 Less Aux. consumption for Hydro, Thermal & Gas 184.200 VIII AVERAGE PER DAY REQUIREMENT 321 IX DETAILS OF NETT PURCHASES FROM CGS & OTHER REGIONS: Neyveli TS-I 286.713 Neyveli TS-I Expansion 104.802 Neyveli TS-II Expansion 111.547 NTPL 209.006 Neyveli TS-II Stage-1 82.809 Neyveli TS-II Stage-2 114.599 MAPS APS 78.104 Kaiga APS 140.303 Kudankulam NPCIL Unit 1 & 2 361.770 Ramagundam NTPC (Stage 1 & 2) 283.775 Ramagundam NTPC (Stage 3) 84.884 Eastern region 21.050 Talcher Stage-II NTPC 299.248 Simhadri Stage-II NTPC 95.618 Vallur NTECL 483.560 Solar bundled NVVN Power from NTPC stations 2.870 Inter State Deviation Settlement Mechanism (Provisional) (-) 60.000 Intra State Deviation Settlement Mechanism (Provisional) (-) 2.000 TOTAL NET PURCHASES 2698.658 3

X DETAILS OF PURCHASES FROM IPPs PPN Power Generating Company Pvt. Ltd., (-) 0.602 TAQA Neyveli Power Company Pvt. Ltd., (STCMS) 74.541 Lanco Tanjore Power Company Ltd., (ABAN) 36.673 Pioneer Power Ltd., (Penna) 29.216 TOTAL 139.828

XI DETAILS OF OTHER PURCHASES Through Traders 2425.687 CPPs 2.000 Co-generation 70.000 Bio-Mass 2.000 Wind Mill (Pvt.) 870.025 Solar (Pvt.) 246.318 TOTAL 3616.031 XII SWAP POWER RETURN / BANKING BY TNEB 0.000

XIII Maximum Sustained Grid demand met in MW/Date 15230 19.04.2017 Maximum consumption reached in M.U./Date 334.892 08.04.2017

XIV. STORAGE POSITION: The Storage equivalent in M.U.as on 01.05.2017 is compared with that of the storage equivalent as on the same day last year as below (Figs. In MU):- Sl. As on 1st of As on 1st of Name of the Group No. the month this the month Difference year (2017) previous year (2016) 1. Nilgiris 287.730 410.076 (-)122.346 2. P.A.P. 11.100 30.386 (-) 19.286 3. Periyar 0.000 1.600 (-) 1.600 4. Papanasam & Servalar 1.179 13.166 (-) 11.987 5. Suruliyar 0.029 7.364 (-) 7.335 6. Kodayar 41.910 98.921 (-) 57.011 7. Total Excluding Mettur 341.948 561.513 (-)219.565 8. For Mettur 0.000 21.060 (-) 21.060 Superintending Engineer/LD & GO. 4

PERFORMANCE OF THERMAL STATIONS FOR APRIL 2017. i) TUTICORIN TPS (5 x 210 MW): The details of generation at Tuticorin T.P.S. during April 2017 were as follows: Unit Availability Factor (%) Generation in MU Plant Load Factor (%) I (210 MW) 92.2 119.27 78.90 II (210 MW) 99.5 149.62 99.00 III (210 MW) 77.6 114.55 75.80 IV (210 MW) 91.4 125.24 82.80 V (210 MW) 100.0 136.52 90.30 STATION 92.14 645.20 85.36

ii) METTUR TPS - I (4 x 210 MW): The details of generation at Mettur T.P.S. during April 2017 were as follows: Unit Availability Factor (%) Generation in MU Plant Load Factor (%) I (210 MW) 94.65 142.879 94.50 II (210 MW) 92.17 139.212 92.07 III (210 MW) 100.00 139.416 92.21 IV (210 MW) 100.00 139.383 92.18 STATION 96.71 560.890 92.74

iii) NORTH TPS - I (3 x 210 MW): The details of generation at T.P.S. during April 2017 were as follows: Unit Availability Factor (%) Generation in MU Plant Load Factor (%) I (210 MW) 89.04 124.725 82.49 II (210 MW) 94.86 133.455 88.26 III (210 MW) 91.32 128.550 85.02 STATION 91.74 386.730 85.26

V) METTUR TPS - II (1 x 600 MW): The details of generation at Mettur T.P.S.-II during April 2017 were as follows: Unit Availability Factor (%) Generation in MU Plant Load Factor (%) I (600 MW) 54.59 154.33 35.72 STATION 54.59 154.33 35.72 VI) NORTH CHENNAI TPS - II (2 x 600 MW): The details of generation at North Chennai T.P.S.-II during April 2017 were as follows: Unit Availability Factor (%) Generation in MU Plant Load Factor (%) I (600 MW) 70.28 253.479 58.68 II (600 MW) 80.12 290.853 67.33 STATION 75.20 544.332 63.00 5

GENERAL : S.No. Details T.T.P.S. M.T.P.S.-I N.C.T.P.S.-I M.T.P.S-II N.C.T.P.S.-II 1. Specific Coal Consumption (Kg./kwhr.) 0.730 0.661 0.675 0.630 0.700 2. Specific Oil Consumption (ml/kwhr.) 0.580 0.190 0.900 1.9407 1.860 3. Auxiliary Consumption (%) 7.48 8.46 8.81 7.72 7.32 Superintending Engineer/Betterment Thermal.

COAL PARTICULARS FOR APRIL 2017 : S.No. Particulars TTPS. MTPS. M.T.P.S. NCTPS. NCTPS. ETPS. I II (1x600 I II (2x600 MW) MW) (in lakh tonnes) 1. Coal to be supplied (*) (Ind. coal) 4.12 3.29 1.83 2.47 3.67 1.38 2. Coal receipt (Ind. coal) 2.09 2.41 5.01 -- (Imp coal) 0.59 1.31 1.82 -- (SCCL coal) -- 1.09 -- -- 3. Coal consumption (Ind. coal) 3.82 1.96 0.03 2.14 2.59 -- (Imp coal) 0.89 0.81 0.68 0.47 1.22 -- (SCCL coal) -- 0.95 0.26 -- -- 4. Coal stock as on (Ind. coal) 1.50 0.68 0.77 0.88 0.06 30.04.2017 (Imp coal) 1.71 0.39 0.49 0.51 -- (SCCL coal) -- 0.30 0.53 -- -- (*) As per Fuel Supply Agreement signed by TANGEDCO with MCL & ECL. Note: Ind coal - Indigenous coal , imp coal - Imported coal SCCL coal : Singareni coal collieries Ltd., coal. ∗ ∗ ∗ Superintending Engineer/M/Coal. 6 (8) Period For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. For a period upto the date on which the pre- sent incumbent of the post gets relieved/ retired. (7) Purpose Creation of posts to the 400/230- 110 KV SS at (Ottiyam- bakkam) in Chennai EDC/ South-II. Creation of posts to the newly formed 110/22-11 KV (NG) SS at A.Mettur in Perambalur EDC. Creation of additional posts to the 400/230-110 KV Kayathar SS in EDC. Upgradation of one post DFC/ Power Purchase as FC/ Purchase in the O/o CE/Private Power Projects/ Chennai. 1 4 1 2 1 2 1 5 6 1 1 8 2 2 4 4 5 1 4 4 1 11 34 14 Post No. of . . . . A A door (5) (6) Post . FM STATEMENT-A Name of the A/ Maz ech. Asst. ech. Asst. AE/JE/El. I Gr JE/Elecl. II Gr FM I Grade Line Inspector Wireman F AE/JE/El. I Gr Draughtsman T Wireman/ F Financial Controller EE/ Electrical AEE/ Electrical AE/JE/El. I Gr Draughtsman Spl. Gr T Line Inspector Wireman Wireman/ F Field Assistant ech. ech. ech. ech. (4) -T -T -T -T Cadre Class / Cl.III-Pro. Cl.III-RWE Cl.IV-RWE Cl.II Cl.I Cl.III-Pro. Cl.III-RWE Cl.IV-RWE Cl.II Cl.II Cl.III-Pro. Cl.III-RWE Cl.I-Accts. (3) Circle Name of the Chennai EDC/ South-II Perambalur EDC Tirunelveli EDC CE/ Private Power Projects/ Chennai . . . . (2) .) CMD .) CMD .) CMD .) CMD created STATEMENT SHOWING THE DETAILS OF POSTS CREATED DURING MONTH APRIL 2017. er which the er er er posts were ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro Reference in T No.44,(Adm.Br) Dt.01.04.2017. (P T (P No.50,(Adm.Br) Dt.06.04.2017. T (P No.45,(Adm.Br) Dt.01.04.2017. (P T No.83, (S.B) Dt.03.04.2017 1 . 4. 2. 3. Sl. (1) No. 7 (8) For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of post. For a period of one year from the date of utilisation of post. For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. A/Elecl. est. echnical A/Helper in (7) Main Road 230/110-33- rd S in Chennai EDC/ W .D’man and one post of adation of one post T Downgradation of 8 posts Instrument Mechanic I Grade as Instrument Mechanic III Grade in CE/ P&C/ Chennai. Creation of one post Head Draughtsman duly abolishing one post of Sr Draughtsman in the office of SE/Projects Development & Co-Ordination/ Chennai. Upgr SE/Kuttalam GTPS. Assistant as JE/ Electrical II Grade duly abolishing one post of T and two posts of F Creation of posts to the 230/110 KV SS at Kurukathi in Operation Circle/ Coimbatore. 11 KV S Creation of posts to the new 3 8 1 1 1 5 1 1 2 4 2 4 1 5 1 1 4 2 2 4 20 20 . . . door door (5) (6) . FM . FM A/ Maz ech. Asst. A/ Maz ech. Asst. Instrument Mechanic III Grade Head D’man JE/ Elecl. II Gr EE/ Elecl. AEE/ Elecl. AE/JE/El. I Gr Spl. Gr Line Inspector T Wireman F Spl. Gr T Line Inspector Wireman F EE/ Elecl. AEE/ Elecl. AE/JE/El. I Gr ech. ech. ech. ech. (4) -T -T -T -T Cl.III-RWE Cl.III-Pro. Cl.III-Pro. Cl.III-RWE Cl.IV-RWE Cl.II Cl.I Cl.III-RWE Cl.IV-RWE Cl.II Cl.I (3) est CE/P&C/ Chennai SE/ Proj. Develoment & Co-ordination/ Chennai. Kuttalam GTPS Operation Circle/ Coimbatore Chennai EDC/ W . . . . . (2) .) CMD .) CMD .) CMD .) CMD .) CMD er er er er er ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro (P No.56,(Adm.Br) Dt.11.04.2017. T (P No.60,(Adm.Br) Dt.12.04.2017. T (P No.52,(Adm.Br) Dt.10.04.2017. T (P No.63,(Adm.Br) Dt.13.04.2017. T (P No.55,(Adm.Br) Dt.11.04.2017. T 7. 8. 5. 9. 6. (1) 8 (8) For a period upto the date on which the pre- sent incumbent of the post gets relieved/ retired. For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. For a period upto 28.02.2018 from the date of utilisation of posts. y, .M.Sethumath y ./ Chennai. y in Namakkal EDC. (7) apatt y APDRP/ Chennai - ala S at V Upgradation of one post EE/ Electrical as SE/ to accommodate Tmt EE/ Elecl. in the O/o CE/IT/ Chennai. Creation of posts to the 110/22 KV (NG) SS at Keezhkavarapattu in EDC Creation of 5 posts AE/ Electrical in the O/o CE/ I.T Creation of posts to the 230/110 KV S Creation of two posts AE/ Electrical and one post of Office Helper in the O/o CE/R 1 1 4 1 2 1 2 5 1 5 1 1 2 4 2 4 2 1 11 20 . . . door door (5) (6) . FM A/ Maz A/ Maz ech. Asst. SE/ Elecl. JE/Elecl. II Gr FM I Grade Line Inspector Wireman F AE/JE/El. I Gr AE/ Electrical EE/ Elecl. AEE/ Elecl. AE/JE/El. I Gr Spl. Gr Line Inspector T Wireman F AE/ Electrical Office Helper ech. ech. ech. ech. ech. ech. (4) -T -T -T -T -T -T Cl.I Cl.II Cl.III-Pro. Cl.III-RWE Cl.IV-RWE Cl.II Cl.II Cl.III-RWE Cl.IV-RWE Cl.I Cl.II Cl.IV-Pro. ./ ./ (3) APDRP/ - CE/ I.T Chennai Cuddalore EDC CE/ I.T Chennai Namakkal EDC Chennnai CE/ R . . . . . (2) .) CMD .) CMD .) CMD .) CMD .) CMD er er er er er ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro T (P No.97, (S.B) Dt.15.04.2017. T (P No.68,(Adm.Br) Dt.18.04.2017 (P T No.65,(Adm.Br) Dt.15.04.2017 T (P No.70,(Adm.Br) Dt.22.04.2017 (P T No.95, (S.B) Dt.15.04.2017 12. 13. 10. 14. 11. (1) 9 (8) For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. For a period of one year from the date of utilisation of posts. est. . (7) y EDC/ Metro rich Creation of 27 posts for 2x800 MW Uppur Supercritical Thermal Power Project for co-ordination, supervision and monitoring of works for the year 2017-2018. Creation of posts to the 33/11 KV (Indoor) at MC Nichols Road, in Chennai EDC/ W Upgradation of two posts Field Assistant as Wireman in R&D Lab T 1 1 1 1 1 2 2 2 1 1 1 2 2 2 1 1 1 1 1 1 1 4 2 2 8 2 27 * ypist (5) (6) T ech. Asst. Office Helper CE/ Civil EE/ Civil EE/ Mechl. EE/ Electrial EE/ Elecl./Mech. AEE/ Civil AEE/ Mechl. AEE/ Electrical AEE/ Elec./Mech A.Adm. Officer A.Accts. Officer AE/ Civil AE/ Mechanical AE/ Electrical Head D’man Adm. Supervisor Accts.Supervisor Assistant(Adm.) Asst. (Accts.) Steno- T Wireman Field Assistant Wireman ech. ech. ech. (4) -T -T -T Cl.III-Pro. Cl.IV-Pro. Cl.II-Adm. Cl.II-Accts. Cl.II Cl.II Cl.I Cl.III-RWE Cl.IV-RWE Cl.III-RWE (3) y EDC/ est rich Uppur Supercritical Thermal Power Project (2x800 MW) Chennai EDC/ W Metro R&D Lab in T . . . (2) .) FB .) CMD .) CMD er er er ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro No.9, (S.B) Dt.25.04.2017 (P T (P No.74,(Adm.Br) Dt.24.04.2017 T (P No.75,(Adm.Br) Dt.25.04.2017 T 17. 15. 16. (1) 10 Period With immediate effect. With immediate effect. With immediate effect. With immediate effect. With immediate effect. With immediate effect. y, A/Elecl. echnical A/Helper in Chief Engineer/Personnel .M.Sethumath y Purpose . D’man and one post of adation of one post T y EDC/ Metro . rich SE/Kuttalam GTPS. Upgr Assistant as JE/ Electrical II Grade duly abolishing one post of T and two posts of F Upgradation of one post DFC/ Power Purchase as FC/ Purchase in the O/o CE/Private Power Projects/ Chennai. Creation of one post Head Draughtsman duly abolishing one post of Sr Draughtsman in the office of SE/Projects Development & Co-Ordination/ Chennai. Upgradation of one post EE/ Electrical as SE/ to accommodate Tmt EE/ Elecl. in the O/o CE/IT/ Chennai. Upgradation of two posts Field Assistant as Wireman in R&D Lab T Downgradation of 8 posts Instrument Mechanic I Grade as Instrument Mechanic III Grade in CE/ P&C/ Chennai. 1 2 1 1 1 1 2 8 Post No.of * door Post STATEMENT-B Name of the A/ Maz ech. Asst. T F Deputy Financial Controller Senior D’man Draughtsman EE/ Elecl. Field Assistant Instrument Mechanic I Grade ech. -T Cadre Class / Cl.III-RWE Cl.I-Accts. Cl.III-Pro. Cl.I Cl.IV-RWE Cl.III-RWE ./ Circle y EDC/ Name of the rich Kuttalam GTPS CE/ Private Power Projects/ Chennai CE/ I.T SE/ Proj. Develoment & Co-ordination/ Chennai. R&D Lab in T CE/P&C/ Chennai ...... ) CMD .) CMD .) CMD .) CMD .) CMD .) CMD abolished er which the er er er er er STATEMENT SHOWING THE DETAILS OF POSTS ABOLISHED DURING MONTH APRIL 2017. posts were ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro ANGEDCO Pro Reference in T (P No.52,(Adm.Br) Dt.10.04.2017. (P T No.83, (S.B) Dt.03.04.2017 T T (P (P No.97, (S.B) Dt.15.04.2017. No.75,(Adm.Br) Dt.25.04.2017 T (P No.60,(Adm.Br) Dt.12.04.2017. T (P No.56,(Adm.Br) Dt.11.04.2017. 2. 1. 5. 6. 4. 3. Sl. No. GENERAL ADMN. & SERVICES PART – II Establishment - TANGEDCO - "1x800 MW North Chennai Supercritical Thermal Power Project Stage-III" - Change of Technical Control - Orders - Issued. (Secretariat Branch) (Per.) CMD TANGEDCO Proceedings No.85, Dated the 05th April 2017. Panguni -23, Thiruvalluvar Aandu - 2048. READ: i) (Per.) FB TANGEDCO Proceedings No.2 (SB) Dt.28.03.2017. ii) Note from the Director /Project/ TANGEDCO, Dated 05.04.2017. ----- PROCEEDINGS: In the proceedings read above, orders were issued placing the works relating to "1x800 MW North Chennai Supercritical Thermal Power Project Stage-III” under the technical control of Chief Engineer/Civil/ SEZ Supercritical Thermal Power Project. 2. The Director/Projects/TANGEDCO, has stated that the works relating to “2x660 MW Ennore SEZ Supercritical Thermal Power Project” needs extensive supervision and monitoring and has suggested that the Chief Engineer/Civil Ennore SEZ Supercritical Thermal Power Project may be detached from “1x800 MW North Chennai Supercritical Thermal Power Project Stage-III” and restored to Ennore SEZ Supercritical Thermal Power Project. 3. The Director/Projects/TANGEDCO, has also suggested that the works relating to “1x800 MW North Chennai Supercritical Thermal Power Project Stage-III” may be attached to the Chief Engineer/Civil/ETPS Expansion Project in addition to the existing “1x660 MW ETPS Expansion Project” as both the plants are under coastal plain projects. The Chairman-cum-Managing Director/ TANGEDCO has approved the proposal. 4. Accordingly, in modification of the orders issued in the proceedings first read above the civil works relating to “1x800 MW North Chennai Supercritical Thermal Power Project Stage-III” may be attached to the Chief Engineer/Civil/ETPS Expansion Project in addition to the existing “1x660 MW ETPS Expansion Project”. (By Order of the Chairman - cum - Managing Director) R. Balaji, Secretary. * * * Letter No.41777/A17/A171/2016-6, (BOSB) dated.05.04.2017. Sub : TANGEDCO – Secretariat Branch – New Health Insurance Scheme, 2016 for the employee of Government Departments and other organizations – Empanelment of Accredited Hospitals – Approval of additional hospitals and inclusion of additional specialties based on the 12

recommendations of the Accreditation Committee – Notified – Orders Issued – Communicated. Ref : i) G.O.Ms.No.202, Finance (Salaries) Department, dt.30.06.2016. ii) (Per.) CMD TANGEDCO Proceedings No.140 (SB), dt.30.07.2016. iii) Lr.No.41777/A.17/A.171/2016, dt: 02.08.2016. iv) Memo.No.41777/A.17/A.71/2016-2, dt:05.08.2016. v) Lr.No.41777/A.17/A.171/2016-5, dt: 15.11.2016. vi) G.O. (Rt) No.199, Finance (Salaries) Dept., dt:21.03.2017. ----- In continuation of the reference fourth cited, I am to upload the Government Order vide reference sixth cited together with the list of additional hospitals approved and also additional specialties added under New Health Insurance Scheme’ 2016 to the approved hospitals already listed and communicated in the Proceedings second cited. The list as mentioned above are sent through the Secretary’s E-mail I.D. ([email protected]). 2. I am to request you to avail the medical assistance to the maximum extent under New Health Insurance Scheme’ 2016 in the above mentioned Hospitals also and make use of it. R. Balaji, Secretary. Copy to Government of 2017 FINANCE [Salaries] DEPARTMENT G.O.(Rt) No.199 Dated 21st March 2017. (Thunmugi, Panguni-8, Thiruvalluvar Aandu-2048) ABSTRACT New Health Insurance Scheme, 2016 for the employees of Government Departments and other Organisations - Empanelment of Accredited Hospitals - Approval of additional hospitals and inclusion of additional specialities based on the recommendations of the Accreditation Committee - Notified - Orders - Issued. Read:- 1. G.O.Ms.No.309, Finance (Salaries) Department, dated: 14-08-2012. 2. G.O.Ms.No.169, Finance (Salaries) Department, dated: 09-06-2016. 3. G.O.Ms.No.202, Finance (Salaries) Department, dated: 30-06-2016. 4. From the Principal Secretary/Commissioner of Treasuries and Accounts, Lr.Rc.No.34465/2016/NHIS-2, dated 13.03.2017. ----- ORDER: In the Government Order first read above, Government has constituted an 13

Accreditation Committee for empanelment of accredited hospitals and to monitor the quality of treatment consisting of the Commissioner of Treasuries and Accounts, the Director of Medical and Rural Health Services and a representative of the United Insurance Company Limited. 2. In the Government Order second and third read above, orders have been issued for the implementation of New Health Insurance Scheme, 2016 to provide Health Care Assistance to the employees of Government Departments, Public Sector Undertakings, Statutory Boards, Local Bodies, State Government Universities, willing State Government Organisations / Institutions and their eligible family members with a provision to avail cashless assistance upto Rs.4.00 lakh (Rupees Four lakh only) and an enhanced assistance of Rs.7.50 lakh has been allowed for specific illness like Cancer, for certain organ transplantations, etc., for a block of 4 years on selection of a suitable Public Sector Insurance Company through National competitive bidding. 3. In the implementation procedures for New Health Insurance Scheme, 2016 included in the Annexure I to the Government Order third read above it is provided for inclusion of additional list of approved hospitals and treatments/surgeries based on the report of the Accreditation Committee. 4. The Principal Secretary/Commissioner of Treasuries and Accounts in his letter fourth read above has submitted proposals to include additional hospitals and additional specialities to the hospitals already approved under New Health Insurance Scheme, 2016 as recommended by the Accreditation Committee. 5. The Government, after careful consideration of the recommendations of the Accreditation Committee, have decided to include 72 (Seventy two) additional hospitals and additional specialities to the hospitals already approved, as detailed in the Annexure I&II to this order, for availing the assistance under New Health Insurance Scheme, 2016 and issue orders accordingly. (By Order of the Governor) K. Shanmugam, Additional Chief Secretary to Government. //Forwarded by Order// ANNEXURE-I [G.O.(Rt) No.199, Finance (Salaries) Department, Dated: 21-03-2017] LIST OF ADDITIONAL HOSPITALS APPROVED UNDER NEW HEALTH INSURANCE SCHEME, 2016 DETAILS OF HOSPITALS Sl. Sl.No. No. in the Name and Address Contact Specialities Available Approved Number List (1) (2) (3) (4) (5) I. 1. 7(a) AGADA HOSPITAL 044- Cardiology, General Medicine No.8, Dr. Nair Road, T.Nagar, 28152604 / - Medical Care, General Surgery, Chennai - 600017. 06 Gynaecology, Orthopaedic Surgery. 2. 7(b) AMMAYI EYE HOSPITAL New No.80,7th Avenue , Ashok Nagar,Chennai - 600083. 044-24896175 Ophthalmology 14

(1) (2) (3) (4) (5) 3. 8(a) ANNAI ARUL HOSPITAL 044- General Medicine - Medical Care, No.270, Gandhi Nagar, 71700700 General Surgery, Gynaecology, Mudichur Road, , Neurology, Nephrology, Orthopaedic Chennai - 600063. Surgery, Cardiology 4. 11(a) APOLLO HOSPITALS, OMR 044- General Medicine - Medical Care, No.05/639, Old Mahaballipuram, 33221401 / General Surgery, Cardiology, , Chennai -600096. 33221055 Gynaecology, Neurology, Nephrology, Orthopaedic Surgery, ENT, Genitourinary Surgery 5. 45(a) FAITH MULTI SPECIALITY 044- General Medicine - Medical Care, HOSPITAL 43584333/ General Surgery, Gynaecology, No.33/17, Sannathi Street, 43558777 Neurology, Nephrology, Orthopaedic , Chennai-600049. Surgery, ENT, Genitourinary Surgery II. COIMBATORE DISTRICT 6. 123(a) AR ORTHO HOSPITAL 04259- General Surgery, Genral Medicine - No.42/1, New Scheme Road, 220440 Medical Care, Orthopaedics, Pollachi - 642002. Gynaecology 7. 128(a) BRJ ORTHO CENTRE AND 0422- General Surgery, Genral Medicine - MAK HOSPITAL 2433306 Medical Care, Orthopaedics, No. 2-1, Raju Nagar, Gynaecology Fertilizer Company Stop, Mettupalayam Road, Coimbatore-641043. 8. 132(a) DEEPAM HOSPITAL 0422- General Medicine - Medical Care, No.687, Trichy Road, 4395882 General Surgery, Gynaecology, Ramanathapuram, Neurology, Nephrology, Orthopaedic Coimbatore-641045. Surgery 9. 132(b) DR.DASARATHAN MEMORIAL 0422- General Medicine - Medical Care, HOSPITAL 2642248 General Surgery, Gynaecology, No 3/31, M.T.P Road, Neurology, Nephrology, Orthopaedic K.Vadamadurai, Surgery Coimbatore-641017. 10. 132( c ) DR.MUTHU'S HOSPITAL 0422- General Medicine - Medical Care, No.291, Trichy Road, 4373517 General Surgery, Gynaecology, Opp to Bharath Petrol Bunk, Neurology, Nephrology, Orthopaedic Singanallur, Coimbatore- 641005. Surgery 11. 132(d) ELLEN HOSPITAL 0422- General Medicine - Medical Care, No.284, Sathy Road, 2521212 / General Surgery, Gynaecology, Gandhipuram, 4373090 Neurology, Nephrology, Orthopaedic Coimbatore - 641012. Surgery 12. 136(a) ISWARYA WOMENS HOSPITAL 0422- Gynaecology, General medicine - & FERTILITY CENTRE 2241777 Medical Care, General Surgery No.238, Avarampalayam, Opp to Women's Polytechnic College, Near Gandhipuram, Coimbatore- 641044 15

(1) (2) (3) (4) (5) 13. 155(a) MEDWIN HOSPITAL 0422- General Medicine - Medical Care, Site No.42&43, kothari Layout, 2316666 General Surgery, Gynaecology, Trichy Road, Coimbatore - 641005. Neurology, Nephrology, Orthopaedic Surgery 14. 159(a) ORTHO ONE ORTHOPAEDIC 0422- Orthopaedics SPECIALITY CENTRE 4055100 No.657, Trichy Road, Singanallur Post, Near Stock Exchange, Coimbatore- 641005. 15. 161(a) PILLS HOSPITAL 04259- General Medicine - Medical Care, No.70/53, Bharathi Road, 235757 General Surgery, Gynaecology, LIG Colony - 1, Mahalingapuram, Neurology, Nephrology, Orthopaedic Pollachi - 642002. Surgery 16. 174(a) SREE ABISHEK HOSPITALS 0422- General Medicine - Medical Care, No. 1 , Raju Gardens, Near 2403030 General Surgery, Gynaecology, T.V.S Nagar Bus Stop, Neurology, Nephrology, Orthopaedic Thadagam Road, Surgery Coimbatore-641025. III. DHARMAPURI DISTRICT 17. 192(a) BGR HOSPITAL 0452- General Medicine - Medical Care, No 2B, Ramalingam Chetti Street, 4268211 General Surgery, Gynaecology, (Near LIC) Dharmapuri-636701. Neurology, Nephrology, Orthopaedic Surgery 18. 192(b) DNV ORTHO HOSPITAL 04342- Orthopaedics No 72AB , Salem Main Road, 231822 / Dharmapuri-636705. 230355 19. 197(a) KRISHNA EYE FOUNDATION 04342- Ophthalmology No.5, P.R.Sundaram Iyyer Street, 262625 Opp to Senthil kumar Textiles, Dharmapurai-636701 20. 197(b) NITHYA HOSPITAL 0442- General Medicine - Medical Care, No.14-b, Nethaji Bye-Pass Road, 260371 General Surgery, Gynaecology, Opp to Govt Hospital, Salem Neurology, Nephrology, Orthopaedic Main Road, Dharmapuri-636701. Surgery IV. DISTRICT 21. 204(a) DHARSHINI HOSPITAL 0451- General Medicine - Medical Care, 34, Narayana Nagar, 1st Street, 2423392 General Surgery, Gynaecology, Ayyangar Petrol Bunk, Neurology, Nephrology, Orthopaedic Dindigul-624001 Surgery 22. 209(a) KANNA HOSPITAL 0451- General Medicine - Medical Care, No.13-D, Aarthi Theatre Road, 6452888 General Surgery, Gynaecology, Y.M.R Patti, Dindigul - 642001. Neurology, Nephrology, Orthopaedic Surgery 23. 218(a) SREE KUMARAN HOSPITAL 04553- General Medicine - Medical Care, Market Bye-Pass Road, 243555 General Surgery, Gynaecology, Ottanchatram -624619. Neurology, Nephrology, Orthopaedic Surgery 16

(1) (2) (3) (4) (5) 24. 220(a) VEL MULTI SPECIALITY 04545- General Medicine - Medical Care, HOSPITAL 245451 General Surgery, Gynaecology, No.11, Vel Nagar , Gounder Neurology, Nephrology, Orthopaedic Ittery Road, Palani Taluk, Surgery Dindigul-624601. V. DISTRICT 25. 227(a) BHARATHI HEART & 0424- Cardiology, General Medicine - MATERNITY HOSPITAL 2277001 Medical Care, General Surgery, No.3, E.V.N. Road, Surampatti Gynaecology, Neurology, Nephrology, Nall Road, Erode -638009. Orthopaedic Surgery 26. 242(a) L.V.S. EYE HOSPITAL 0424- Ophthalmology No.13A, Palaniappa Street, 2257131 Opp To Govt Hospital, Erode - 638009. 27. 251(a) SUDHA HOSPITAL 0424- Cardiology, General Medicine - No.162/181, Perundurai Road, 2454545 Medical Care, General Surgery, Erode - 638011. Gynaecology, Neurology, Nephrology, Orthopaedic Surgery VI. KANCHEEPURAM DISTRICT 28. 262(a) SRI NE FOUNDATION 044- Cardiology, General Medicine - 53, MM Avenue Main Road, 27228614 Medical Care, General Surgery, Kanchipuram-631501. Gynaecology, Neurology, Nephrology, Orthopaedic Surgery. VII. KANYAKUMARI DISTRICT 29. 268(a) ANNAMAL HOSPITAL 04651- General Medicine - Medical Care, No.11/45-B2, Hill Ward, 26060 General Surgery, Gynaecology, Trivandrum Road, Neurology, Nephrology, Orthopaedic Kuzhithurai -629163. Surgery 30. 277(a) Dr. SURESH EYE CLINIC 04651- Ophthalmology Vettumony, Thengapattanam 277602 Road, Marthandami -629165. VIII. KRISHNAGIRI DISTRICT 31. 320(a) OM SAKTHI HOSPITAL 04343- General Medicine - Medical Care, No.64, 2nd Cross, Co-operative 233111 General Surgery, Gynaecology, Colony, Krishnagiri -635001. Neurology, Nephrology, Orthopaedic Surgery IX. DISTRICT 32. 326(a) ANAND EYE HOSPITAL 0452- Ophthalmology No.12, Karpaga Nagar, K.Pudur, 4504466 Madurai-625007 33. 327(a) APOLLO FIRST MED HOSPITAL 0452- General Medicine - Medical Care, No.484-B, West First street, 4341066 General Surgery, Cardiology, Near District Court, K.K.Nagar, Gynaecology, Neurology, Nephrology, Madurai - 625020. Orthopaedic Surgery, ENT, Genitourinary Surgery 17

(1) (2) (3) (4) (5) 34. 328(a) ARISTO SPECIALITY HOSPITAL 0452- General Medicine - Medical Care, No.50-B, Bye - Pass Road, 4200788 General Surgery, Gynaecology, pp To Aparna Towers, Neurology, Nephrology, Orthopaedic Madurai - 625016. Surgery 35. 334(a) B.G.M. HOSPITAL 0452- General Medicine - Medical Care, No.1/249, New Natham Road, 4268211 General Surgery, Gynaecology, Iyer Bungalow, Madurai - 625017. Neurology, Nephrology, Orthopaedic Surgery 36. 344(a) LAKSHMANA MULTI 0452- General Medicine - Medical Care, SPECIALITY HOSPITAL 2371369 General Surgery, Gynaecology, No. 23C, TPK Main Road, Pykara, Neurology, Nephrology, Orthopaedic Madurai - 625004. Surgery 37. 351(a) NITHILAA NURSING HOME 0452- General Medicine - Medical Care, 72, TPK Road, Palanganatham, 2372113 General Surgery, Gynaecology, Opp to Kumarangam Koil, Neurology, Nephrology, Orthopaedic Madurai- 625003 Surgery 38. 351(b) NTC HOSPITAL 0452- General Medicine - Medical Care, No.187, Thathaneri Main Road, 2660064 / General Surgery, Gynaecology, (Opp To ESI Hospital) 2660664 Neurology, Nephrology, Orthopaedic Vaithiyanathapuram, Surgery Madurai- 625018. 39. 351(c) PANDIAN HEART INSTITUTE 0452- Cardiology 43,Shanmugam Pillai, 2nd Street, 2361577 Alagarady, Madurai- 625016 40. 356(a) RAKSHA HOSPITAL 0452- General Medicine - Medical Care, No.130, , 2700700 General Surgery, Gynaecology, Madurai - 625020. Neurology, Nephrology, Orthopaedic Surgery 41. 359(a) SHASTHA KIDNEY AND 0452- General Medicine - Medical Care, MULTISPECIALITY HOSPITAL 4952986 / General Surgery, Gynaecology, No.22,23 Telecom Nagar, 987 Neurology, Nephrology, Orthopaedic Ilanthikulam, Valarnagar, Surgery Madurai - 625107. 42. 362(a) SRI LAKSHMI HOSPITAL 0452- General Surgery, Gynaecology, No.210A, Bye Pass Road, 4396069 Neurology, Nephrology, Orthopaedic Bethaniyapuram, Madurai-625016 Surgery 43. 362(b) SRI RAJAN ORTHO HOSPITAL 0452- Orthopaedics Old No.29-B, New No.64, 2300534 T.B.Road, Mahaboopalayam, Madurai -625016 44. 364(a) ST. ANTONY'S HOSPITAL 0452- General Medicine - Medical Care, No.2/50, Sarvodhaya Main Road, 4360369 General Surgery, Gynaecology, New Ellis Nagar, Madurai- 625010 Neurology, Nephrology, Orthopaedic Surgery

B.B.2 (Apr 17) 18

(1) (2) (3) (4) (5) X. NAMAKKAL DISTRICT 45. 394(a) SUGAM HOSPITAL 04287- General Medicine - Medical Care, No .144F, Annasalai, 225399 General Surgery, Gynaecology, Opp To Union Office, Rasipuram, Neurology, Nephrology, Orthopaedic Namakkal-637408. Surgery XI. PUDUKOTTAI DISTRICT 46. 405(a) MANIMEGALAI MEDICAL CENTRE 04322- General Medicine - Medical Care, T.S.No. 1900, North Main Street, 224458 General Surgery, Gynaecology, - 622001 Neurology, Nephrology, Orthopaedic Surgery 47. 406(a) PUDUGAI STAR HOSPITAL 04322- General Medicine - Medical Care, No.50,51, Ramachandra Nagar, 267575 General Surgery, Gynaecology, Alangudi Road, Neurology, Nephrology, Orthopaedic Pudukkottai - 622001. Surgery 48. 407(a) SHRI SARRADHA EYE HOSPITAL 04322- Ophthalmology No.5882/13-P, Lakshmipuram 221979 2nd Street, Pudukkottai - 622001. XII. RAMANATHAPURAM DISTRICT 49. 415(a) RAJANS CLINIC 04567- General Medicine - Medical Care, No.27/1, R.R Sethupathi Nagar, 221225 General Surgery, Gynaecology, G.H Road, Ramanathapuram - Neurology, Nephrology, Orthopaedic 623501 Surgery XIII. SALEM DISTRICT 50. 429(a) JAAIDEV HOSPITAL (P) LTD. 0427- General Medicine - Medical Care, 7th Mile, Chinnagoundapuram, 2770000 General Surgery, Gynaecology, Minnampalli, Salem-636106. Neurology, Nephrology, Orthopaedic Surgery 51. 430(a) KARTHICK MEDICAL CENTRE 04283- General Medicine - Medical Care, 5/148A-A, Chinna Nachiyur, 222310 / General Surgery, Gynaecology, Veerappampalayam, Idappadi, 223309 Neurology, Nephrology, Orthopaedic Salem - 637105 Surgery 52. 438(a) PRIYAM SPECIALITY HOSPITALS 0247- General Medicine - Medical Care, No.247, Bangalore ByePass Road, 2273733 General Surgery, Gynaecology, Kondalampatty, Salem - 636010. Neurology, Nephrology, Orthopaedic Surgery 53. 442(a) SARAVANA HOSPITAL 0427- General Medicine - Medical Care, No.14, Thillai nagar, 1st Cross, 2295229 General Surgery, Gynaecology, Ponnammapet, Salem - 636001. Neurology, Nephrology, Orthopaedic Surgery 54. 452(a) UNIVERSAL CANCER 0427- Oncology, General Medicine - HOSPITAL LIMITED 2273477 Medical Care, General Surgery, No. 370, Jari Kondalampatty, Gynaecology, Neurology, Nephrology, Near Kondalampatty Roundana, Orthopaedic Surgery Salem-636010. 19

(1) (2) (3) (4) (5) XIV. SIVAGANGAI DISTRICT 55. 455(a) ANBU RAMACHANDRAN 04561- General Medicine - Medical Care, SPECIALITY HOSPITAL 272419 General Surgery, Gynaecology, No.40, Silambani Sannathi Street, Neurology, Nephrology, Orthopaedic Devakottai-630302. Surgery 56. 457(a) KAUVERY MEDICAL CENTRE 4565- General Medicine - Medical Care, (KARAIKUDI) LIMITED. 244555 General Surgery, Gynaecology, No.42, Mudiyarasanar Salai, Neurology, Nephrology, Orthopaedic Near New Bus Stand, Surgery Karaikudi - 630002. XV. THENI DISTRICT 57. 486(a) ROHAN SEKAR HOSPITAL 04554- Nephrology, Genitourinary No.28C-W-22, Ranger Office 274414 Road, Cumbum, Theni-625516. XVI. THIRUNELVELI DISTRICT 58. 508(a) PONRA MULTI SPECIALITY 0462- General Medicine - Medical Care, HOSPITAL 2970100 General Surgery, Gynaecology, 66/G/3, Vasantham Nagar, Neurology, Nephrology, Orthopaedic Near New Bus Stand (South), Surgery Surandai - 627005. 59. 509(a) SANTHI NURSING HOME 04633- General Medicine - Medical Care, 14/1,122 Surandai, 261267 General Surgery, Gynaecology, Veerakeralampudur Taluk, Neurology, Nephrology, Orthopaedic Tirunelveli-627859. Surgery 60. 510(a) SHIVA CLINIC & HOSPITAL 04633- General Medicine - Medical Care, No.273/180, Kannimaramman 222724 General Surgery, Gynaecology, Kovil Street, Tenkasi - 627811. Neurology, Nephrology, Orthopaedic Surgery XVII. DISTRICT 61. 538(a) JEYANTH NALLATHAMBI 0461- General Medicine - Medical Care, HOSPITAL 2341122 / General Surgery, Gynaecology, No.3/186, Periyanayagi Puram 2341113 Neurology, Nephrology, Orthopaedic Main Road, Korampallam, Surgery Opp New Collector Office, Thoothukudi - 628101. 62. 542(a) SRI HOSPITALS 04632- General Medicine - Medical Care, No.57, Ettayapuram Road, 234000 General Surgery, Gynaecology, Kovilpatti -628501. Neurology, Nephrology, Orthopaedic Surgery XVIII.TIRUCHIRAPALLI DISTRICT 63. 548(a) A.J. HOSPITAL 04332- General Medicine - Medical Care, No.45, Vandipettai Street, 260969 General Surgery, Gynaecology, Police Line, Manapparai-621306. Neurology, Nephrology, Orthopaedic Surgery 20

(1) (2) (3) (4) (5) 64. 548(b) APOLLO SPECIALITY 0431- General Medicine - Medical Care, HOSPITALS 3307777 General Surgery, Cardiology, Chennai Highway, Ariyamangalam Gynaecology, Neurology, Nephrology, Area, Near Old Paalpannai, Orthopaedic Surgery, ENT, Tiruchirapalli-620010. Genitourinary Surgery 65. 564(a) HARSHAMITRA SUPER 0431- Oncology SPECIALITY CANCER CENTRE 2751008 & RESEARCH INSTITUTE PVT LTD. No.41, Nachiyar kovil road, Woraiyur - 620003. 66. 582(a) SMS HOSPITAL 0431- General Medicine - Medical Care, No.128/75 , K Salai Road, 2760480 General Surgery, Gynaecology, (Jayanthi Bus stop) Neurology, Nephrology, Orthopaedic Tiruchirapalli-620018. Surgery 67. 590(a) TIRUCHY MEDICAL CENTRE 0431- General Medicine - Medical Care, & HOSPITAL LTD 2741919 General Surgery, Gynaecology, No.B-17, 11-B Cross, Neurology, Nephrology, Orthopaedic Thillainagar West, Surgery Tiruchirapalli -620018. 68. 592(a) VIJAYALAKSHME EYE 0431- Ophthalmology HOSPITAL 2782277 No.92, Ganapathi Nagar, Uyyakondan Thirumalai, Vayalur Main Road, Tiruchirapalli - 620102 XIX. TIRUPPUR DISTRICT 69. 600(a) NIVETHA HOSPITAL 04258- General Medicine - Medical Care, No.130/114, Udumalai Road, 225770 General Surgery, Gynaecology, Near To Fire Station, Neurology, Nephrology, Orthopaedic Dharapuram - 638656 Surgery XX. DISTRICT 70. 614(a) SCUDDER MEMORIAL 04172- General Medicine - Medical Care, HOSPITAL, RANIPET 270212 / General Surgery, Gynaecology, No. 42-D/1, Road, 272741 Neurology, Nephrology, Orthopaedic Ranipet - 632401 Surgery XXI. DISTRICT 71. 630(a) KRISHNA HOSPITAL 04562- General Medicine - Medical Care, 377, Main Road, Near BSNL 260192 General Surgery, Gynaecology, Office, Sattur - 626203 Neurology, Nephrology, Orthopaedic Surgery 72. 640(a) SUDHA NURSING HOME 04562- General Medicine - Medical Care, No.169, N.R.K Rajarathinam 274962 / General Surgery, Gynaecology, Street, -626123 274979 Neurology, Nephrology, Orthopaedic Surgery / True Copy / 21

ANNEXURE-II [G.O.(Rt) No.199, Finance (Salaries) Department, Dated: 21-03-2017] LIST OF ADDITIONAL SPECIALITIES ADDED TO THE APPROVED HOSPITALS UNDER NEW HEALTH INSURANCE SCHEME, 2016 DETAILS OF HOSPITALS Sl. Sl.No. No. in the Name and Address Contact Specialities Available Approved Number List (1) (2) (3) (4) (5) I. CHENNAI DISTRICT 1. 104 V.S. HOSPITAL 044- Orthopaedics, General Surgery, 13, East Spurtank Road, 12001000, Urology, Neurology, Nephrology, Chetpet, Chennai - 600 031 28190920 Gynaecology, General Medicine Care, ENT. II. KRISHNAGIRI DISTRICT 2. 318 ARK NURSING HOME 04343- Cardiology 75/29-A, 4th Cross, Co-operative 237436, Colony, Krishnagiri - 635 001. 233059 III. MADURAI DISTRICT 3. 335 DEVADOSS MULTI 0452- Cardiology SPECIALITY HOSPITAL 4521000 No. 75/1, Alagarkovil Main Road, Surveyor Colony, Madurai-625007. IV. PERAMBALUR DISTRICT 4. 400 DHANALAKSHMI SRINIVASAN 04328- Oncology, Neurology, MEDICAL COLLEGE 327999 Opthalmology, Vascular, HOSPITAL Medical Gastroenterology, NH 45,Trichy Chennai By Pass, Surgical Gastroenterology, Siruvachur, Perambalur Plastic Surgery District- 621 113. V. THOOTHUKUDI DISTRICT 5. 541 PADMA HOSPITAL, 04632- Neurology, Nephrology, 2764/6, Main Road, 220699 Orthopaedic Surgery, ENT, opp. To Lakshmipuram Genitourinary Surgery Post Office, Kovilpatti - 628 502. // True Copy // * * * Memo(Per) No.10319/A22/A222/2017-3, (BOSB) dated 06.04.2017. Sub : Establishment – TANGEDCO – Bifurcation of existing Office of Chief Engineer/Projects/Chennai – Reallocation of works – Orders – Issued. Ref : i) (Per) CMD TANGEDCO Proceedings No.65 (SB) dated 09.03.2017. ii) From the Chief Engineer/Projects/Chennai U.O. Note No. CE/P/SE/E/THP/F.General/D.73/17, dt.01.04.2017. ----- 22

In partial modification of the orders issued in the proceedings cited, the following reallocation of works among the Chief Engineer/Projects-I/Chennai and the Chief Engineer/Projects-II/Chennai, is ordered:- i) the works relating to 1x800 MW NCTPP Stage-III (both BTG & BOP) hitherto looked after by the Superintending Engineer/Electrical/Thermal & Hydro (Projects) under the control of the Chief Engineer/Projects-I/Chennai shall now be reallocated to the Superintending Engineer/Electrical (created post) under the control of Chief Engineer/Projects-II/Chennai. ii) the works relating to 2x800 MW Uppur TPP both (BTG & BOP) hitherto looked after by the Superintending Engineer/Electrical (created post) under the control of Chief Engineer/Projects-II/Chennai shall now be reallocated to the Superintending Engineer/Electrical/Thermal & Hydro (Projects) under the control of Chief Engineer/ Projects-I/Chennai. (By Order of the Chairman - cum - Managing Director) R. Balaji, Secretary. * * * Memo (Per) No.18833/A22/A222/2017-1, (BOSB) dated.10.04.2017. Sub : Establishment – TANGEDCO – Upgradation of one post of Deputy Financial Controller/ Power Purchase as Financial Controller/Power Purchase under the control of Chief Engineer/Private Power Projects/ Chennai – Cancellation - Orders – Issued. Ref : i) (Per) CMD TANGEDCO Proceedings No.83 (SB), dated 03.04.2017. ii) From the Chief Financial Controller/TANTRANSCO, Chennai Note dated 05.04.2017. ----- The orders issued in the proceedings first cited stands cancelled. (By Order of the Chairman) R. Balaji, Secretary. * * * Memo (Per) No.10319/A22/A222/2017-4, (BOSB) dated.10.04.2017. Sub : Establishment – TANGEDCO – Bifurcation of existing Office of Chief Engineer/Projects/Chennai by creating one post of Chief Engineer/ Electrical for ongoing and upcoming projects – Ratification - Orders – Issued. Ref : i) (Per) CMD TANGEDCO Proceedings No.65 (SB), dated 09.03.2017. ii) From A10-Section/Secretariat Branch Memo. No.14000/A10/A101/2017-7, dated 31.03.2017. ----- 23

The Board of TANGEDCO hereby ratifies the orders issued in the Proceedings cited. (By Order of the Board) R. Balaji, Secretary. * * * TANGEDCO – Mobile Phone Connections – Under Closed User Group Scheme – Provision of Data Package for the existing 28 Nos. CUG Sim Cards allotted for the Enforcement Wing – Orders – Issued. (Secretariat Branch) (Per) CMD TANGEDCO Proceedings No.92, Dated the 12th April 2017. Panguni 30, Thiruvalluvar Aandu 2048. READ: (i) (Per)B.P. (FB) No.35 (SB), dt:04.10.2010. (ii) Note approved by the CMD/ TANGEDCO, dated 22.03.2017. ----- PROCEEDINGS: In the Board’s proceedings cited, orders were issued fixing the ceiling limit on BSNL CUG Mobile phone call charges for various Officers of the Board. The Additional Director General of Police/Vigilance/TANGEDCO has requested for provision of Data Package for the existing 28 Nos. CUG Sim Cards allotted to certain Officers of Enforcement Wing to increase the number of inspections without contacting the Nodal Section Offices and to manage the Bill status in the website and to increase the overall performance of the Officers. The Chairman-cum-Managing Director/ TANGEDCO has approved the proposal. 2. Accordingly, provision of Data Package for usage of GB for 28 days at a cost of Rs.198/-+Service Tax revised from time to time per Sim Card for the existing 28 Nos. of CUG Sim Card allotted to Enforcement Wing w.e.f. 01.04.2017 are ordered as detailed below:- Sl.No. Designation of the Officers No. of Connections 1 Superintending Engineer/Enforcement 1 2 Executive Engineer/Enforcement & Intelligence Wing 5 3 Assistant Executive Engineer/ 17 (existing) Enforcement (existing and proposed) 4 (proposed) 4 Assistant Executive Engineer/ Flying Squad/Chennai 1 Total 28 Nos. 3. The existing monthly ceiling limit of mobile call charges under CUG Scheme applicable to the above Officers issued vide reference first cited remains unaltered. The ceiling limit fixed in para-2 above shall be strictly followed. No proposal for ratification by Chairman-cum- Managing Director/ TANGEDCO for incurring excess expenditure shall be entertained. 24

4. The expenditure towards payment for the above charges is debitable from the Head of Account No.76.111. (By Order of the Chairman - cum - Managing Director) R. Balaji, Secretary. * * * TANGEDCO – Mettur Thermal Power Station-II (1x600MW) – Incentive Schemes – Sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus to the employees of Mettur Thermal Power Station-II - Orders – Issued. (Secretariat Branch) (Per) FB TANGEDCO Proceedings No.6, Dated the 15th April 2017. Chithirai-02, Thiruvalluvar Aandu 2048. READ: (Per.) CMD TANGEDCO Proceedings No.100, (SB) Dated 27.10.94. ----- PROCEEDINGS: In the Board’s proceedings cited, orders were issued for payment of Monthly Thermal Incentive Allowance and Annual Thermal Incentive Bonus to the employees of Mettur Thermal Power Station-I with effect from 1st April 1992 with certain conditions for allowing the above incentives. 2. It was decided by TANGEDCO to construct another unit of 1x600MW of Mettur Thermal Power Project-II and the above project was commenced during June 2008. The commercial operation of the Project was put into commission on 12.10.2013. At the time of project construction stage itself, the employees of the Mettur Thermal Power Project-II were allowed Monthly Thermal Incentive Allowance and Annual Thermal Incentive Bonus instead of Project Allowance and Project Special pay from 2008 onwards till 2013-14. 3. The Chief Engineer/Mettur Thermal Power Station-II has sent a proposal for sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus for the years 2014-15 and 2015-16 to the employees of Mettur Thermal Power Station-II (Consequent on sanction of commissioning incentive). 4. After careful examination of the proposal, the TANGEDCO hereby order as follows: i) The Annual Thermal Incentive Bonus and Monthly Thermal Allowance paid in excess from 2008 to 2013-2014 shall be recovered from the employees of Mettur Thermal Power Station-II. ii) The Annual Thermal Incentive Bonus to the employees of Mettur Thermal Power Station-II for the year 2014-15 shall not be allowed due to non achievement of required slab of generation. iii) The Annual Thermal Incentive Bonus to the employees of Mettur Thermal Power Station-II (1x600 MW) for the year 2015-16 shall be granted as per the slab of generation achieved at the rates prescribed in (Per.) B.P (Ch) No. 223 & 224 (SB) Dated 21.11.2009. 25

The Terms and Conditions for payment of Monthly Thermal Allowance and Annual Thermal Incentive Bonus is shown in Annexure. 5. The receipt of the Board’s Proceedings shall be acknowledged. (By Order of the Board) R. Balaji, Secretary. ANNEXURE TERMS AND CONDITIONS (1). Monthly Thermal Incentive Allowance. (a) i) The employees of the Mettur Thermal Power Station-II and Mettur Thermal Power Project-II shall be granted a Monthly Thermal Incentive Allowance linked to production on the scale specified below at flat rates for various slabs of basic pay at the rates prescribed in (Per.) B.P. (Ch) No.223 & 224 (SB) Dated: 21.11.2009. ii) In lieu of Project Special Pay and Project Allowance, the staff in the construction side of the Mettur Thermal Power Project-II will also be allowed the monthly Thermal Incentive Allowance as given to the staff of the Mettur Thermal Power Station-II. (b) Minimum out-put corresponding to the annual rate of 5000 KWH/KW of installed capacity for the calendar month should have been achieved for eligibility to the Monthly Thermal Incentive Allowance. (c) As the Monthly Thermal Incentive Allowance is granted only as an incentive for production, employees will not be eligible for this incentive allowance during the following periods: (i) during the periods of absence on leave other than casual leave or special casual leave or compensatory leave. (ii) during suspension. (iii) when the employee is charge-sheeted for any reason, in-eligibility of the allowance for a period of one month, the payment for the month being restored only if he is exonerated, subsequently. (2) Annual Thermal Incentive Bonus:- (a) i) Annual Thermal Incentive Bonus is for the Accounting year commencing from 1st April of a year to the 31st March of commencing from 1st April of a year to the 31st March of the succeeding year. The employees on the role of the Mettur Thermal Power Station-II who have been on actual duty (casual leave to be treated as actual duty) for 200 days in the accounting year from 1st April to 31st March of the succeeding year will be eligible to get the Annual Thermal Incentive Bonus. ii) A small construction side staff of Mettur Thermal Power Project-II will also be allowed the Annual Thermal Incentive Bonus in lieu of the Project Special Pay and Project Allowance as given to the staff of the Mettur Thermal Power Station-II. (b) The rates of Annual Thermal Incentive Bonus when generation level reaches 5100 KWH/KW and the rate of Annual Thermal Incentive Bonus for the increase of every 100 KWH/KW over and above 5100 KWH/KW are as indicated in (Per.) B.P. (Ch) No.223 & 224 (SB) Dated 21.11.2009. (c) (i) The minimum output for the eligibility of the monthly thermal allowance, 26 and also the output(s) for the admissibility of annual bonus shall be calculated on the basis of morning and evening peak period generation during the following hours: During Summer – April to September Morning Peak Hours Evening Peak Hours 05.00 to 09.00 18.00 to 22.00 During Winter – October to March 06.00 to 10.00 17.00 to 21.00 ii) The peak hour generation data intimated by the power station to the Southern Regional Electricity Board, Bangalore would form the basis for incentive benefits. The daily energy generated during the peak period shall be computed in million units based on the half hourly generation in M.W. furnished to the Southern Regional Electricity Board, Bangalore and these will be summated for each month and multiplied by three for arriving at the monthly generation. The above monthly generation figures would be further summated over the year. iii) The Thermal Station should carry out the instructions of the Load Despatch Centres of the TANTRANSCO regarding load variations during off peak period. If any additional generation is pumped in to the Grid during these off peak period in violation of the instruction of Load Despatch Centres of the TANTRANSCO, the generation of Power for that day computed as in (i) will be deducted out of the monthly generation of the station. (d) In Mettur Thermal Power Station-II/Mettur Thermal Power Project-II for extra hours approved and worked by the employees, a suitable reduction will be made from the total quantum of Annual Thermal Incentive Bonus, so that any over time paid is deducted from the total Annual Thermal Incentive Bonus Payable. // TRUE COPY// * * * TANGEDCO – North Chennai Thermal Power Station-II (2x600MW) – Incentive Schemes – Sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus to the employees of North Chennai Thermal Power Station-II – Orders - Issued. (Secretariat Branch) (Per.) FB TANGEDCO Proceedings No.7, Dated the 17th April 2017. Chithirai 04, Thiruvalluvar Aandu 2048. READ: (Per.) Board’s Proceedings (F.B) No.11, (SB) Dt. 17.02.1998. ----- PROCEEDINGS: In the Board’s Proceedings cited, orders were issued for payment of Monthly Thermal Incentive Allowance and Annual Thermal Incentive Bonus to the employees of North Chennai Thermal Power Station with effect from 01.04.1998 with certains conditions for allowing the above incentives. 2. It was decided by TANGEDCO to construct another unit of 2x600 MW in North Chennai Thermal Power Project-II and the above project was commenced during June 2008. The commercial operation of the Project was put into commission 27 on 28.03.2014. At the time of project construction stage itself, the employees of the North Chennai Thermal Power Project-II were allowed Monthly Thermal Incentive Allowance and Annual Thermal Incentive Bonus instead of Project Allowance and Project Special pay from 2008 onwards till 2013-14. 3. The Chief Engineer/North Chennai Thermal Power Station-II has sent a proposal for sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus for the years 2014-15 and 2015-16 to the employees of North Chennai Thermal Power Station-II (Consequent on sanction of commissioning incentive). 4. After careful examination of the proposal, the TANGEDCO hereby order as follows: i) The Annual Thermal Incentive Bonus and Monthly Thermal Allowance paid in excess from 2008 to 2013-2014 shall be recovered from the employees of North Chennai Thermal Power Station-II. ii) The Annual Thermal Incentive Bonus to the employees of North Chennai Thermal Power Station-II for the year 2014-15 shall not be allowed due to non achievement of required slab of generation. iii) The Annual Thermal Incentive Bonus to the employees of North Chennai Thermal Power Station-II (2x600 MW) for the year 2015-16 shall be granted as per the slab of generation achieved at the rates prescribed in (Per.) B.P. (Ch) No. 223 & 224 (SB) Dated: 21.11.2009. The Terms and Conditions for payment of Monthly Thermal Allowance and Annual Thermal Incentive Bonus are shown in Annexure. (By Order of the Board) R. Balaji, Secretary. ANNEXURE TERMS AND CONDITIONS (1). Monthly Thermal Incentive Allowance. (a) i) The employees of the North Chennai Thermal Power Station -II and North Chennai Thermal Power Project-II shall be granted a Monthly Thermal Incentive Allowance linked to production on the scale specified at flat rates for various slabs of basic pay at the rates prescribed in (Per.) B.P. (Ch) No. 223 & 224 (SB) Dated: 21.11.2009. ii) In lieu of Project Special Pay and Project Allowance, the staff in the construction side of the North Chennai Thermal Power Project-II will also be allowed the monthly Thermal Incentive Allowance as given to the staff of the North Chennai Thermal Power Station -II. (b) Minimum out-put corresponding to the annual rate of 5000 KWH/KW of installed capacity for the calendar month should have been achieved for eligibility to the Monthly Thermal Incentive Allowance. (c) As the Monthly Thermal Incentive Allowance is granted only as an incentive for production, employees will not be eligible for this incentive allowance during the following periods:- i) during the periods of absence on leave other than casual leave or special casual leave or compensatory leave. 28

ii) during suspension. iii) when the employee is charge-sheeted for any reason, in-eligibility of the allowance for a period of one month, the payment for the month being restored only if he is exonerated. (2) Annual Thermal Incentive Bonus:- (a) i) Annual Thermal Incentive Bonus is for the Accounting year commencing from 1st April of a year to the 31st March of commencing from 1st April of a year to the 31st March of the succeeding year. The employees on the role of the North Chennai Thermal Power Station-II who have been on actual duty (casual leave to be treated as actual duty) for 200 days in the accounting year from 1st April to 31st March of the succeeding year will be eligible to get the Annual Thermal Incentive Bonus. ii) A small construction side staff of North Chennai Thermal Power Project- II will also be allowed the Annual Thermal Incentive Bonus in lieu of the Project Special Pay and Project Allowance as given to the staff of the North Chennai Thermal Power Station-II. (b) The rates of Annual Thermal Incentive Bonus when generation level reaches 5100 KWH/KW and the rate of Annual Thermal Incentive Bonus for the increase of every 100 KWH/KW over and above 5100 KWH/KW are as indicated in (Per.) B.P. (Ch) No. 223 & 224 (SB) Dated: 21.11.2009. (c) i) The minimum output for the eligibility of the monthly thermal allowance, and also the output(s) for the admissibility of annual bonus shall be calculated on the basis of morning and evening peak period generation during the following hours:- During Summer - April to September Morning Peak Hours Evening Peak Hours 05.00 to 09.00 18.00 to 22.00 During Winter – October to March 06.00 to 10.00 17.00 to 21.00 ii) The peak hour generation data intimated by the power station to the Southern Regional Electricity Board, Bangalore would form the basis for incentive benefits. The daily energy generated during the peak period shall be computed in million units based on the half hourly generation in M.W. furnished to the Southern Regional Electricity Board, Bangalore and these will be summated for each month and multiplied by three for arriving at the monthly generation. The above monthly generation figures would be further summated over the year. iii) The Thermal Station should carry out the instructions of the Load Despatch Centres of the TANTRANSCO regarding load variations during off peak period. If any additional generation is pumped into the Grid during these off peak period in violation of the instructions of Load Despatch Centres of the TANTRANSCO, the generation of Power for that day computed as in (i) will be deducted out of the monthly generation of the station. (d) In North Chennai Thermal Power Station-II /North Chennai Thermal Power Project-II for extra hours approved and worked by the employees, a suitable reduction will be made from the total quantum of Annual Thermal Incentive Bonus, so that any over time paid is deducted from the total Annual Thermal Incentive Bonus Payable. //TRUE COPY// * * * 29 Establishment - TANGEDCO - Decommissioning of Ennore Thermal Power Station - Re-designation/Modification and abolition of certain posts in the Office of the Chief Engineer/Ennore Thermal Power Station, Chennai and attachment of modified post of Executive Engineer/Ennore Thermal Power Station 230KV Switch Yard along with incumbent to Superintending Engineer/Chennai Electricity Distribution Circle/North - Order - Issued. (Secretariat Branch) (Per) CMD TANGEDCO Proceedings No.98 Dated the 18th April 2017. Chitirai-5, Thiruvalluvar Aandu 2048. READ :- i) Memo.(Per)No.001289/02/G.36/G.362/2015-8, dated 02.01.2016. ii) (Per) FB TANGEDCO Proceedings No.72 (T.B.), dated 31.10.2016. iii) (Per) CMD TANGEDCO Proceedings No.143 (T.B.) dated 13.03.2017. iv) From the Chief Engineer/Ennore Thermal Power Station Lr.No.CE/ETPS/SE/P&A/Adm-I/F.Elec./D.389/2017, dated 20.03.2017. ----- PROCEEDINGS: In the proceedings second read above, among other things orders were issued for shutting down the units I to IV of Ennore Thermal Power Station permanently from 31.03.2017 and to decommission the Ennore Thermal Power Station. Consequently, the Chief Engineer/Ennore Thermal Power Station, Chennai has proposed to modify, attach, abolition and transfer of certain posts. The Chairman-cum-Managing Director/TANGEDCO has approved the proposal. 2. Accordingly, the following posts shall be re-designated/modified in the Office of the Chief Engineer/Ennore Thermal Power Station as detailed below:- Sl.No. Name Present Post Re-designated/modified Thiruvalargal 1. J.Aruldoss EE/O&E/ETPS EE/ETPS230KV Switch Yard 2. K.K.Manonmani EE/EM-II/ETPS EE/Purchase Raghunathan 3. C.Ravichandran EE/CMP/ETPS EE/Electrical Maintenance. 3. Consequent to the above, it is hereby ordered that the modified post of Executive Engineer/ETPS 230 KV Switch Yard along with incumbent shall be attached to the Superintending Engineer/Chennai Electricity Distribution Circle/North. 4. Sanction is also accorded for abolition of 3 Nos. surplus posts of Executive Engineer/Electrical last continued in the Memo. first read above from the data of relief of incumbents. (By Order of the Chairman - cum - Managing Director) R. Balaji, Secretary. * * * 30

Establishment - Court Case - Order dated 21.06.2016 in W.P. (MD) No.2603/2013 filed by Thiru.R.Pandian, Asst. Engineer (Suspension) of the then Thirumayam RECS - Absorption Orders Served - Proceedings Issued. (Administrative Branch) (Per) (CH)TANGEDCO Proceedings No.69 Dated the 20th April 2017. Chitirai 07, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ :- Ref: i) Hon’ble Madurai Bench of order dated 21.06.2016 in WP(MD) in No.2603 of 2013. ii) Letter of additional Secretary to Government, energy Department dated 30.12.2016. iii) Contempt Petition (MD) No.1625 of 2016 in W.P(MD) No.2603 of 2013. (received by mail on 01.04.2017) iv) SE/Pudukkottai EDC Lr.No.02647/Adm/Adm2/A.5/F.cc/ 2017-2 dated 04.04.2017. v) This Office Memo.No.091126/635/G.44/G.441/2013 Dated 10.04.2017. ----- PROCEEDINGS: (1) Thiru.R.Pandian, Asst. Engineer (Suspension) of the then Thirumayam RECS was placed under suspension in Proceeding RC.No.3616/99 A2(1) dated 29.10.1999 by the Managing Director, Thirumayam Rural Electric Co-operative Society for the charges that he was trapped and arrested by the vigilance and Anti-Corruption on 28.10.1999. Since, the individual was under suspension he was not absorbed by the Tamil Nadu Electricity Board, when the Board took over the said Thirumayam rural Electric Co-operative Society in the year 2002. the TNEB in its Proceedings B.P.(FB) No.19, dated 20.07.2006 has stated that Tvgl. R.Pandian, Asst. Engineer and P.Vikraman, Wireman who are under suspension based on the D.V.A.C report and against whom case is pending in the High Court shall be deferred till the case against them is disposed. Subsistence Allowance was paid to the individual from the date of suspension (by TRECS) and subsequently as per the direction of the Hon’ble Court passed in W.P.No.5536/2009, subsistence allowance was paid by TNEB to the petitioner with effect from 01.08.2004. 2. Thiru.R.Pandian, Asst. Engineer (Suspension) of the then thirumayam RECS in the Special C.C.No.02/2001 filed by Asst. Supdt. of Police, Vigilance and Anti Corruption against him and one other was acquitted u/s248(1) of Cr.P.C, since the charges have not been proved beyond all reasonable doubts by the Special Judge/ Chief Judicial Magistrate, Pudukottai. Based on the above verdict the Ho’ble Madurai Bench of Madras High Court in its order dated 21.06.2016 made in the Writ Petition (W.P.No.2603 of 2013) filed by Thiru.R.Pandian, Asst. Engineer (Suspension) of the then Thirumayam Rural Electric Co-operative Society, has directed to reinstate the petitioner into service with all attendant and monetary benefits. 31

3. Based on the Hon’ble Madurai Bench of Madras High Court’s order made in the Writ Petition (W.P.No.2603 of 2013) filed by Thiru.R.Pandian,Asst. Engineer (Suspension) of the then Thirumayam Rural Electric Co-operative Society and however taking in to the fact that the individual has not been appointed in the rolls of the Board at any point of time and was suspended from service by the then Thirumayam RECS, before acquisition of the said Society by the Board and also in light of the Contempt Petition (MD)No.1625 of 2016 in W.P.(MD)No.2603 of 2013 filed by the individual the entire issue was examined in detail and a memo dated 10.04.2017 was issued to absorb Thiru.R.Pandian, Asst. Engineer (Suspension) of the then Thirumayam Rural Electric Co-operative Society “Without any backwages and other attendant benefits on the principle of “No work - No pay” by placing the matter before the Board and also subject to the outcome of Writ Appeal filed by the Board. 4) The individual Thiru.R.Pandian,Asst. Engineer (Suspension) of the then Thirumayam Rural Electric Co-operative Society may be appointed into the TANGEDCO as per the Court Order made in W.P.No. 2603/2013 without any backwages and other attendant benefits on the principle of “No work - No pay” and also that his absorption is subject to the outcome of the Writ Appeal (W.A.SR(MD)No.4788/2017) filed by the Board. (By Order of the CMD/TANGEDCO) A.V. Ravi, Chief Engineer/Personnel. * * * Establishment - TANGEDCO - Review of staff pattern in 400 KV SS dual ratio of 400/ 230 -110 KV SS and GIS SS - Constitution of a high level committee to examine and fix for norms for 400 KV Sub-Stations in Operation circles for sanction of posts - Orders - Issued. (Administrative Branch) (Per.) CMD TANGEDCO Proceedings No.73, Dated the 24th April 2017. Chithirai 11, Heyvelambi Varudam, Thiruvalluvar Aandu, 2048. READ: Note approved by the CMD/TANGEDCO on 31.03.2017. ----- PROCEEDINGS: Proposals are being received from various region offices seeking posts sanction to the 400 KV Sub-Station in Distribution circles. There is no specific Staff pattern for dual ratio Sub-Station like 400/230 KV and 400/230-110 KV Sub-Stations in the board. 2. As such in earlier the 230 KV Sub-Station norms posts were sanctioned to the 400 KV Sub-Stations and subsequently some additional posts in the cadre of Technical and RWE were sanctioned to the eldest Sub-Stations like Alamathy, K.R.Thoppur, Sunguvarchatram and Sriperumbathur. 3. Now a days, the posts recommended by the Chief Engineer/Distribution concerned has been considered for sanction causing the varied Staff Pattern in each of the 400 KV Sub-Station. 32

4. Further, it has been noticed that Nos. of 400 Sub-Stations are to be commissioned in all over Operation Circles in near future. Hence, it is necessary to fix the Staff Pattern for the 400 KV Sub-Station dual ratio of 400/230-110 KV Sub-Station and GIS Sub-Stations. 5. After careful consideration, the CMD/TANGEDCO has given approval to constitute a high level committee to study and examine and fix the norms for 400 KV Sub-Station 400/230-110 KV SS and GIS in the Operation Circles. 6. Accordingly, it is hereby ordered that a high level committee be constituted with the following members to fix the norms for 400KV Sub-Station and GIS Sub-Stations for admission of posts. 1. Managing Director/TANTRANSCO - Chairman 2. Director/Operation/Chennai - Member 3. Chief Engineer/System Operation - Member 4.Chief Engineer/Project-II - Member 5. Chief Engineer(D)/Chennai Region/North - Member 6. Chief Engineer/Personnel - Convenor 7. SE/Operation/Sriperumputhur - Member 7) The committee will examine the issue and furnish their report as early as possible. (By Order of the CMD/TANGEDCO) A.V.Ravi, Chief Engineer/Personnel. * * * Memo. No.12350/A18/A182/2017-1, (BOSB) dt.24.04.2017. Sub: TANGEDCO - Departmental Tests for the Officials of TANGEDCO held in May 2014 and November 2016 - Results declared - Amendments - Issued. Ref: i) (P) CMD TANGEDCO Proc.No. 224 (SB), dt:13.08.2014. ii) (P) CMD TANGEDCO Proc.No.4 (SB), dt:04.01.2017. ----- In the Proceedings cited, orders have been issued declaring the results for the Departmental Tests for the officials of TANGEDCO held in May 2014 and November 2016. Certain candidates, who have passed the tests, have requested to rectify the mistakes occurred in the said proceedings. The same have been examined in detail and it has been decided to accept the same. Accordingly the following amendments are issued:- AMENDMENTS (A) The expressions in Sl.Nos.118 in Annexure-II to the Proceedings first cited, shall respectively be substituted as below:- 118 AO-2014 M.RANI ACCOUNTS SUPERVISOR Madurai A-314 28-MAY-1962 Theni EDC 33 (B) The expressions in Sl.No.210 and 335 in Annexure-I to the Proceedings second cited, shall be substituted as below:- 210 HT-16-B- K.SENTHILKUMAR FIELD ASSISTANT Erode 1091 02-JUN-1982 Operation MTPS 335 HT-16-B E.JEGANATHAN TECHNICAL ASSISTANT Tirunelveli 1675 07-MAR-1986 Elec Systems TTPS (B) II) The expressions in Sl.No.29 in Annexure-II to the Proceedings second cited, shall be substituted as below:- 29 HA-16-B-2198 T.ARULMANI ASSISTANT (ACCOUNTS) Erode 14-APR-1971 Erode Region (By Order of the Chairman - cum - Managing Director) R. Balaji, Secretary. * * * ESTABLISHMENT - Tamil Nadu Generation and Distribution Corporation Limited - Secretariat Branch - Tamil Nadu Electricity Board Employees’ Conduct Regulations - Amendments to Tamil Nadu Electricity Board Employees’ Conduct Regulations to deal with certain contingencies - Issued. (Secretariat Branch) (Per.) FB TANGEDCO Proceedings No.8, Dated the 25th April 2017. Chithirai-12, Heyvilambi Varudam, Thiruvalluvar Aandu, 2048. READ: ----- PROCEEDINGS: The Tamil Nadu Electricity Board Employees’ Conduct Regulations have been framed in exercise of the power conferred under Section 79(c) of the Electricity (Supply) Act, 1948 similar to Tamil Nadu Government Servants’ Conduct Rules, 1973. Whenever the Government have issued amendments to any of the said Rules, the same is being adopted in Tamil Nadu Generation and Distribution Corporation Limited and suitable amendments to the corresponding regulations of the Tamil Nadu Electricity Board Employees’ Conduct Regulations were issued. Regulation 3(a) of Tamil Nadu Electricity Board Employees’ Conduct Regulations is parallel to Rule 20(1) of Tamil Nadu Government Servants’ Conduct Rules, 1973. A provision in the said rules has been omitted to be included in regulation 3(a) of Tamil Nadu Electricity Board Employees’ Conduct Regulations. Further it has become necessary to insert an additional clause to regulation 25 of Tamil Nadu Electricity Board Employees’ Conduct Regulations in confirmity with Rule 19 (2) of Tamil Nadu Government Servants’ Conduct Rules, 1973 to deal with the cases involving moral turpitude on the part of the employee including unlawful act, which may cause embarrassment or bring discredit to the Corporation. Hence, a proposal has been placed before the Board of Tamil Nadu Generation and Distribution Corporation Limited to suitably amend regulation 3(a) and to insert an additional clause to regulation 25 of Tamil Nadu Electricity Board Employees’ Conduct Regulations in confirmity with Rule 20(1) and 19(2) of Tamil Nadu Government Servants’ Conduct Rules, 1973 respectively.

B.B.3 (Apr 17) 34

2. Accordingly in exercise of the powers conferred by Section 79(c) of the Electricity (Supply) Act, 1948 (Central Act 54 of 1948), read with Section 185 of the Electricity (Supply) Act, 2003 and G.O.Ms.No.100, Energy (B2) Department, dated 19.10.2010, the Tamil Nadu Generation and Distribution Corporation Limited makes the following amendments of Tamil Nadu Electricity Board Employees’ Conduct Regulations:- I. In the said Regulation, in sub-regulation (a) regulation 3, the following shall be substituted; Every employee shall at all times maintain absolute integrity and devotion to duty and shall do nothing which is unbecoming of a member of the service. II. In the said Regulation, regulation 25, the following shall be added; “(2). No employee involve himself in any act involving moral turpitude on his part including any unlawful act, which may cause embarrassment or which may bring discredit to Tamil Nadu Generation and Distribution Corporation:. 3. The above amendments come into effect from the date of issue of these orders. (By Order of the Board) R. Balaji, Secretary. * * * gofŸ - mféiy¥go - 01.01.2017 Kj‰bfh©L ca®¤j¥g£l mféiy¥go Åj« - Miz- btëæl¥gL»wJ. (ãiy) jiyt® k‰W« nkyh©ik Ïa¡Fe®/jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf« brašKiw Miz v©.104, (brayf¡»is) ehŸ : 28-04-2017. Á¤Âiu - 15-« ehŸ, ÂUtŸSt® M©L 2048. go¡f¥g£lJ:- 1) (ãiy) KGthça« jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf« brašKiw Miz v©. 3, ehŸ: 11.1.2014. 2) (ãiy) KGthça« jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf« brašKiw Miz v©. 4, ehŸ: 11.1.2014. 3) (ãiy) jiyt® k‰W« nkyh©ik Ïa¡Fe®/jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf« brašKiw Miz v©. 211, ehŸ: 17.12.2016. 4) muR Miz (ãiy) v©. 105, ã (gofŸ)¤ Jiw, ehŸ: 26.04.2017. ----- brašKiwfŸ : gh®it 3-š go¡f¥g£LŸs jäœehL ä‹thça Mizæš, thça¤Â‹ bjhêyhs®fŸ k‰W« mYty®fS¡F 01.07.2016 Kj‰bfh©L mféiy¥goæid 125 rjÅj¤ÂèUªJ 132 rjÅjkhf ca®¤Â tH§»l Mizæl¥g£lJ. 2. gh®it 4-š go¡f¥g£LŸs jäœehL muR Mizæš, 01.01.2017 Kj‰bfh©L khãy muR¥ gâahs®fS¡F Ñœ¡f©l ÂU¤j¥g£l Åj¤Âš mféiy¥go tH§f Mizæl¥g£LŸsJ. 35

vªj ehëèUªJ mféiy¥go Åj« tH§f¤j¡fJ (khj« x‹W¡F) 01.01.2017 Kjš mo¥gil CÂa« k‰W« ju CÂa¤Âš 136 rjÅj« 3. jäœehL muÁ‹ Ϫj Mizia¥ Ëg‰¿ jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf«, mj‹ bjhêyhs®fŸ k‰W« mYty®fS¡F mféiy¥goia¡ Ñœ¡f©lthW ca®¤Â tH§»l MizæL»wJ. vªj ehëèUªJ mféiy¥go Åj« tH§f¤j¡fJ (khj« x‹W¡F) 01.01.2017 Kjš mo¥gil CÂa« k‰W« ju CÂa¤Âš 136 rjÅj« 4. nk‰f©l ca®¤j¥g£l Åj¤Âyhd mféiy¥goahdJ, 01.01.2017 Kjš 30.04.2017 tiu fz¡»l¥g£L eh‹F khj¤Â‰fhd (#dtç Kjš V¥uš tiu) ãYit¤bjhif 10.05.2017 m‹W gzäšyh gçt®¤jid Kiwahd ä‹dQ ԮΠnrit (ECS) _y« tH§f¥gL«. 5. mDk¡f¤j¡f ca®¤j¥g£l mféiy¥goæid¡ fz¡»l mo¥gil CÂa¤Jl‹ ju CÂa¤ijÍ« (Grade Pay) jå¥g£l CÂa¤ijÍ« (Personal Pay) nr®¤J¡bfhŸs nt©L«. ÂU¤j¥g£l mféiy¥goia¡ fz¡»Lifæš, xU %ghŒ¡F¡ Fiwthf tu¡Toa bjhif, mjhtJ 50 fhR« mj‰F nkY« ÏU¡Fkhæ‹, mjid mL¤j xU %ghahf¡ fz¡»š vL¤J¡bfhŸs nt©L«. mJnt, 50 fhR¡F¡ Fiwthf ÏUªjhš mjid¡ fz¡»š vL¤J¡bfhŸs nt©oašiy. 6. nkny mDk¡f¥g£l ÂU¤j¥g£l mféiy¥go j‰nghJ mféiy¥go bgW« KGneu gâahs®fS¡F«, mYty®fS¡F« k‰W« ÂU¤j¥g£l CÂa é»j« %.1300-3000 + %.300 ju CÂa« bgW« gâahs®fS¡F« mDk¡f¤j¡fjhF«. (jiyt® k‰W« nkyh©ik Ïa¡Feç‹ Mizæ‹go) Ïuh. ghyhí, brayhs®. * * * FINANCE PART – III TANTRANSCO - Delegation of powers for Procurement/Works Contract to Superintending Engineers/Operation on par with Superintending Engineers/GCC - Amendment communicated. (Accounts Branch) (Per) CH Proceedings No.6 Dated the 01st April 2017. Panguni:19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu:2048. READ: (Per) B.P. (F.B) No.10 (Accounts Branch) dated 5.11.2016. ----- PROCEEDINGS: The Tamil Nadu Transmission corporation Limited after careful consideration delegated powers to Superintending Engineers of Operation Circles. (Per) B.P. (FB) No.10 (Accounts Branch) dated 05.11.2016 was issued. The TABLE - II of delegation of powers pertaining to purchase of materials under limited tender in the (Per) B.P. (FB) No.10 (Accounts Branch) dated 05.11.2016 may be read as blow: TABLE - II Purchase of Materials - Limited Tender (Under Rule 12 of Tamil Nadu Transparency in Tender Rules, 2000) Existing Amendment Authority Value of work Authority Value of work Superintending Not exceeding Rs. 2 Lakh Superintending No change Engineer/GCC/ for stubs cleats and Engineer/GCC Operation insulators only (B.P. (FB) No.35 (AB) dated 24.09.2007) Superintending Not exceeding Rs. 2 Engineer/ Lakhs for procurement Operation of substation/Line materials for preventive & breakdown maintenance K.Muthupandian, Chief Financial Controller/TANTRANSCO. * * * Memo.No.CFC/Rev/FC/DFC/R1/F.Honrm/D.280/2017, (Accts.Br.) dt.11.04.2017. Sub : TANGEDCO - Low Tension services - Assessment, Collection and Remittances of C.C.Charges - services remain un-assessed Payment of Honorarium - Further extension upto 31.12.2017 - Orders issued. Ref : 1. Memo.No.CFC/FC/DFC/Rev/D.No.36/2013, dt.21.01.2013, 37

2. Memo.No.CFC/FC/DFC/Rev/D.No.24/2014, dtd.09.01.2014. 3. Memo.No.CFC/FC/DFC/Rev/D.No.322/2015, dtd.19.05.2015. 4. Memo.No.CFC/Rev/FC/R/DFC-R1/F.Honrm/D.241/ 2016, dtd.05.04.2016. 5. Lr.No.SE/KEDC/KRR/DFC/RCS/JA/Hon/D.55/16-17, dtd.03.04.2017. ----- 1.0) Orders were issued vide ref-4th cited to utilise the services of existing/ retired staff for the assessment of un-assessed L.T Services in order to ensure 100% Assessment, Collection and Remittance of all services up to 31.12.2016 on payment of Honorarium. 2.0) As requested by the Electricitly Distribuition Circles, in order to avoid non- assessment of the L.T. Services due to shortage of Assessors, after careful consideration, it is hereby ordered that the arrangement of engagion the existing and retired staff for assessment, collection and remittance of L.T. Service Connections is further extended up to 31.12.2017. 3.0) Therefore, it is directed to ensure 100% assessment in all the LT Service including new services and it may also be ensured that the persons engaged for the above work have sufficient knowledge/calibre to execute the work efficiently. 4.0) The Honorarium may be paid at the following rates:- (i) For assessment with HHD - Rs.3/- per S.C. (ii) For collection and remittance - Rs.1.50/- Per S.C. S.Arulsamy, Director/Finance/TANGEDCO * * * TANGEDCO - Filing of Income-tax returns to the Income-tax authorities - Complying with the provisions of Section 44AB of Income Tax Act 1961 for the year 2016-17 – Appointment of Tax Auditor - Regarding (Accounts Branch) (Per) F.B.TANGEDCO Proceeding No.7 Dated the 25th April 2017. Chitthirai 12, Heyvilambi Varudam, Thiruvalluvar Aandu – 2048 ----- PROCEEDINGS: The TANGEDCO has passed the following resolution on 28.03.2017 in the 69th meeting vide item No.30 RESOLUTION "Resolved that M/s.Brahmayya & Company (Chartered Accountants) be and are hereby appointed as Tax Auditors of the TANGEDCO for conducting Tax Audit and Certification under Section 44AB of the Income-tax Act, 1961 for the financial year 38

2016-17 for a fee of Rs.4,50,000/- (Rupees Four lakhs and fifty thousand only) plus Service Tax as applicable and travelling expenses shall be reimbursed at actuals subject to a maximum of Rs. 50,000/- (Rupees Fifty thousand only)” plus Service Tax as applicable. (By Order of the Board) K.Sundaravadhanam, Chief Financial Controller/General. * * * TANTRANSCO – Financial assistance of Rs.443.57Crores for Establishment of 7 Nos. For various works in Trichy, , Salem and Villupuram Operation Circles, Tamil Nadu - sanctioned by Power Finance Corporation Ltd., (PFC Ltd.,) New Delhi – Acceptance of Loan – Approved by the Borrowing Committee – Orders Issued. (Accounts Branch) (Per.) CH. TANTRANSCO Proceedings No.7 Dated the 26th April 2017. Chitthirai 13, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: Ref : 1. PFC Lr.No.03/22/TANTRANSCO/36203076/Vol.I/ 046507 dt.10.3.2017. 2. PFC Lr.No.03/22/TANTRANSCO/36203077/Vol.I/ 046508 dt.10.3.2017 3. PFC Lr.No.03/22/TANTRANSCO/ 36203078/Vol.I/ 046502 Dt. 10.3.2017. 4 PFC Lr.No.03/29/TANTRANSCO/Thiruvalam (1-4)/Vol.I/ 36203079/046510 dt.10.3.2017. 5. PFC Lr.No.03/29/TANTRANSCO/Salem (1-4)/Vol.I/ 36203080/046515 dt.10.3.2017. 6. PFC Lr.No.03/29/TANTRANSCO/Trichy (Sch-1)/Vol.I/ 36203081/046516 dt.10.3.2017. 7. PFC Lr.No.03/29/TANTRANSCO/Trichy (Sch-2))/Vol.I/ 36203082/046517 dt.10.3.2017. 8. Approved by the Borrowing Committee on 25.04.2017. ----- PROCEEDINGS: The Power Finance Corporation Limited, New Delhi, has sanctioned financial assistance to Tamil Nadu Transmission Corporation Limited, (TANTRANSCO Ltd.), for Rs.443.57Crores (144.79+98.80+88.26+63.22+32.83+13.76+1.91) (Rupees Four hundred and forty three crores and fifty seven lakhs only) vide their sanction letters dt.10.3.2017 for various works in Trichy, Thiruvalam, Salem and Villupuram Operation Circles, Tamil Nadu, the details of the schemes are as follows: 39

Sl.No. Loan No. Name of the Scheme Date of Total Sanctioned Sanction Estimated amount 90% Letter Cost (Rs.In Crs) (Rs. In Crs.) 1 36203076 Establishment of 230/110KV Thirupattur SS with 2x100 MVA, 230/110KV Auto transformers and its associated Transmission lines in Thiruvalam Operation Circle of Vellore Region of TN. 10.03.2017 160.88 144.79 2 36203077 Establishment of 230/110 kV substation at Neyveli New Thermal Power Premises and its associated Transmission lines in Villupuram Operation Circle of Villupuram Region of TN. 10.03.2017 109.78 98.80 3 36203078 Establishment of Narimanam 230/ 110/33/11 kV substation with 2x16 MVA, 100/33 kV and its associated Transmission lines in Trichy Operation Circle of Trichy Region of TN. 10.03.2017 98.06 88.26 4 36203079 Establishment of New substation along 10.03.2017 70.25 63.22 with, its associated Transmission lines work and introduction of Ratio in Thiruvalam Operation Circle of TN.(4 Nos.Schemes) a) Estt.of 110/33 KV SS at with 2x16 MVA, 110/33 KV Power Transformers Netrampally in Thiruvalam Opn..Circle. 22.35 20.11 (b) Estt.of Mettala 110/33 KV SS with 2x16 MVA, 110/33 KV Power Transformers at Rayakottai in Thiruvalam Opn..Circle. 37.57 33.81 c) Estt.of 110/33 KV SS with 2x16 MVA, 110/33 KV Power Transformers at Mampatty in Thiruvalam Opn..Circle. 8.01 7.21 d) Introduction of 110/33KV SS with 1x16 MVA 110/33 KV Power Transformers at Dharmapuri 110/11 KV SS in Thiruvalam Opn..Circle 2.32 2.09 5 36203080 Establishment of New substation along 10.03.2017 36.48 32.83 with, its associated Transmission lines work and Upgradation of existing SS Salem Operation Circle of TN. (4 Nos.Schemes) (a) Estt.of 110/22 KV SS at Solasiramani with 2x10 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. 5.81 5.23 40

(b) Estt.of Mettala 110/22 KV SS at Karkoodalpatti with 2x16 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. 8.57 7.71 c) Estt.of 110/22 KV SS at Pallakkapalayam with 2x16 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. 6.90 6.21 d) Upgradation of existing Kolathur 33/11 KV SS into 110/33/11 KV SS with 2x16 MVA, 110/33 KV Power Transformers in Salem Opn..Circle. 15.20 13.68 6 36203081 Upgradation of existing Chinthamanipatty 33/11 kV Sub-station into 110/33/11 kV sub-station with32x16 MVA, 110/33 kV Power Transformer in Trichy Operation Circle of TN. 10.03.2017 15.29 13.76 7 36203082 Upgradation of existing Chinthamanipatty 33/11 kV Sub-station into 110/33/11 kV sub-station with32x16 MVA, 110/33 kV 10.03.2017 2.39 1.91 Power Transformer in Trichy Operation (80%) Circle of TN. TOTAL 493.13 443.57 2. TERMS AND CONDITIONS: The Power Finance Corporation Limited, New Delhi, has sanctioned the financial assistance of Rs.443.57Crores (144.79+98.80+88.26+63.22+32.83+ 13.76+1.91) (Rupees Four hundred and forty three crores and fifty seven lakhs only) for various works in Trichy, Thiruvalam, Salem and Villupuram Operation Circles, Tamil Nadu, as mentioned in their sanction letters Dt.10.03.2017 as in para-1 with same Terms and Conditions and the following Special Terms & Conditions. PRE-COMMITMENT CONDITIONS: 1. TANTRANSCO shall submit an undertaking to obtain in principle approval from TNERC for the schemes covered in the subject proposal. 2. TANTRANSCO shall submit an undertaking that in case investment in the project covered in this loan is not approved by TNERC, TANTRANSCO shall refund the entire amount disbursed in the project to PFC with interest within six month from TNERC’s intimation regarding the same to TANTRANSCO. 3. TANTRANSCO shall submit an undertaking that it will not make any investment in a scheme for which approval has been denied by TNERC. 4. TANTRANSCO shall give an undertaking that in the event of reduction of project cost by TNERC, the loan amount shall be reduced proportionally. 5. TANTRANSCO shall submit an undertaking to implement and adhere to the norms and any other additional terms and conditions mandated by statutory and/or regulatory agencies and obtain all applicable permits/clearances/ approvals including forest clearance, if applicable as and when required during implementation and commissioning of the project. 6. TANTRANSCO shall submit an undertaking to acquire the land, if applicable for 41

the proposed Sub-station(s) in the name of TANTRANSCO for the project within six (6) months of first disbursement. 7. TANTRANSCO shall submit an undertaking that the project land shall not be mortgaged in favour of any other lenders and shall not be disposed –off during the currency of PFC loan, wherever applicable. 8. TANTRANSCO shall submit an undertaking that TANTRANSCO has not taken any financial assistance from any other financial institutions other than PFC. (This condition is applicable for Loan No.36203082 only) PRE-DISBURSEMENT CONDITONS: 1. TANTRANSCO shall clear all outstanding dues to PFC. OTHER CONDITON: 1. TANTRANSCO shall complete the reconciliation of receivables and payables inter-se between TANGEDCO & TANTRANSCO and give effect to in its accounts for FY 2016-17. 2. Reimbursement of expenditure incurred in the project shall be permissible from November, 01,2016. (Loan Nos.36203076 and 36203078) 3. Reimbursement of expenditure incurred in the project shall be permissible from June, 22, 2016. (Loan Nos.36203077) 4. Reimbursement of expenses incurred from August 01,2016 for individual schemes in Thiruvalam and Salem Operation Circle and January 18, 2016 for individual schemes in Trichy Operation Circle shall be permissible.(Loan Nos.36203080, 36203081 and 36203082) 3. DOCUMENTS REQUIRED AT THE TIME OF EXECUTION/SIGNING OF LOAN DOCUMENTS: 1) Extract of Board Resolution, duly attested by the Secretary/Company Secretary, accepting the loan on the terms and conditions of PFC and authorizing an officer to accept and agree to said terms and conditions and execute the relevant loan documents/undertakings etc. 2) Resolution under section 180(1)(a) and 180(1)(c) of the Companies Act 2013, duly attested by Company Secretary (applicable to entities registered under Companies Act, 2013). 3) Specimen signatures of authorized signatory duly attested by Secretary/ Company Secretary as the case may be. 4) Certificate of compliance of laws, bye-laws, etc. applicable to the borrower to be issued by the Company Secretary/Secretary of the borrower, as the case may be. 5) Certificate from the Company Secretary/Statutory Auditors of the Borrower that the borrowing is within the borrowing limits with details thereof. 6) Certificate in prescribed format that the borrower shall continue to be the owner and in physical possession of the project till the outstanding loan amount is fully liquidated. 7) Option letter whereby borrower either opts to pay commitment charges as per clause 5.1 of standard terms and conditions or upfront fees. 8) Option letter whereby borrower opts for the reset period-3, 5 or 10 years. 42

9) Certificate from the borrower, in the prescribed format, that the borrower has received a copy of Operational Policy Statement (OPS) of PFC and confirming that the borrower is aware of the terms and conditions of OPS which shall also apply to this loan. 10) Quarter-wise drawl schedule. 11) Under takings from the Borrower in terms of clause 18.0 of the terms and conditions annexed hereto. 3.1 TANTRANSCO SHALL EXECUTE THE FOLLOWING DOCUMENTS TO PFC LTD AT THE TIME OF DISBURSEMENT OF LOAN: i) Tripartite Escrow Agreement in the prescribed format. ii) Either State Govt. guarantee in the prescribed format or in the case of charge on assets, security documents in the prescribed format. iii) Materials and equipment schedule, in the prescribed format, for the project/ scheme to be financed under the loan. 4. After careful examinations, the Borrowing Committee of TANTRANSCO Ltd., on behalf of the Board of Directors has approved on 25.04.2017 the proposal of availment of the Financial Assistance of Rs.443.57Crores (144.79+98.80+88.26+ 63.22+32.83+13.76+1.91) (Rupees Four hundred and forty three crores and fifty seven lakhs only) from The Power Finance Corporation Limited, New Delhi, along with their Terms and Conditions on the sanction letters mentioned thereon. 5. Borrowing Committee of TANTRANSCO Ltd., has also passed the following Resolutions. RESOLUTIONS RESOLVED that the offer of Power Finance Corporation Limited, New Delhi providing the loan assistance of Rs.443.57Crores (144.79+98.80+88.26+63.22+ 32.83+13.76+1.91) (Rupees Four hundred and forty three crores and fifty seven lakhs only) vide letters dt.10.3.2017 for the following Transmission Schemes be accepted: Sl.No. Loan No. Name of the Scheme Date of Total Sanctioned Sanction Estimated amount 90% Letter Cost (Rs.In Crs) (Rs. In Crs.) 1 36203076 Establishment of 230/110 KV Thirupattur SS with 2x100 MVA, 230/110KV Auto transformers and its associated Transmission lines in Thiruvalam Operation Circle of Vellore Region of TN. 10.03.2017 160.88 144.79 2 36203077 Establishment of 230/110 kV substation at Neyveli New Thermal Power Premises and its associated Transmission lines in Villupuram Operation Circle of Villupuram Region of TN. 10.03.2017 109.78 98.80 3 36203078 Establishment of Narimanam 230/ 110/33/ 11 kV substation with 2x16 MVA, 100/33 kV and its associated Transmission lines in Trichy Operation Circle of Trichy Region of TN. 10.03.2017 98.06 88.26 43

4 36203079 Establishment of New substation along 10.03.2017 70.25 63.22 with, its associated Transmission lines work and introduction of Ratio in Thiruvalam Operation Circle of TN. (4 Nos.Schemes) a) Estt.of 110/33 KV SS at with 2x16 MVA, 22.35 20.11 110/33 KV Power Transformers Netrampally in Thiruvalam Opn..Circle. (b) Estt.of Mettala 110/33 KV SS with 37.57 33.81 2x16 MVA, 110/33 KV Power Transformers at Rayakottai in Thiruvalam Opn..Circle. c) Estt.of 110/33 KV SS with 2x16 MVA, 8.01 7.21 110/33 KV Power Transformers at Mampatty in Thiruvalam Opn..Circle. d) Introduction of 110/33KV SS with 2.32 2.09 1x16 MVA 110/33 KV Power Transformers at Dharmapuri 110/11 KV SS in Thiruvalam Opn..Circle 5 36203080 Establishment of New substation along 10.03.2017 36.48 32.83 with, its associated Transmission lines work and Upgradation of existing SS Salem Operation Circle of TN. (4 Nos.Schemes) (a) Estt.of 110/22 KV SS at Solasiramani 5.81 5.23 with 2x10 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. (b) Estt.of Mettala 110/22 KV SS at 8.57 7.71 Karkoodalpatti with 2x16 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. c) Estt.of 110/22 KV SS at Pallakkapalayam 6.90 6.21 with 2x16 MVA, 110/22 KV Power Transformers in Salem Opn..Circle. d) Upgradation of existing Kolathur 15.20 13.68 33/11 KV SS into 110/33/11 KV SS with 2x16 MVA, 110/33 KV Power Transformers in Salem Opn..Circle. 6 36203081 Upgradation of existing Chinthamanipatty 10.03.2017 15.29 13.76 33/11 kV Sub-station into 110/33/11 kV sub-station with32x16 MVA, 110/33 kV Power Transformer in Trichy Operation Circle of TN. 7 36203082 Upgradation of existing Chinthamanipatty 10.03.2017 2.39 1.91 33/11 kV Sub-station into 110/33/11 kV (80%) sub-station with32x16 MVA, 110/33 kV Power Transformer in Trichy Operation Circle of TN. TOTAL 493.13 443.57 44

II. RESOLVED FURTHER that the Chairman / TANTRANSCO be and is hereby authorized to accept any special conditions that may be stipulated by Power Finance Corporation Limited., and that such acceptable terms and conditions may be communicated to Power Finance Corporation Limited by the Chief Financial Controller / TANTRANSCO on behalf of the Chairman/Tamil Nadu Transmission Corporation Ltd., (TANTRANSCO). III. RESOLVED FURTHER that the Chief Financial Controller/ TANTRANSCO be and is hereby authorized to execute relevant loan documents, any amendments, such certificates and other writings and create security by way of creation of charges on future assets on behalf of the TANTRANSCO. IV. RESOLVED FURTHER that the common seal of the company be affixed on the security documents and any other related documents as may be required by M/s. PFC Ltd., in the presence of the Director (Finance) and Managing Director (or) Director / Transmission Project and the Company Secretary shall sign the same in token thereof. V. RESOLVED FURTHER that the Company Secretary/TANTRANSCO be and is hereby authorised to file the charges created with Registrar of Companies (ROC) within 30 days from the date of execution of loan documents. (By Order of the Chairman/TANTRANSCO) K.Muthupandian, Chief Financial Controller/TANTRANSCO. * * * TECHNICAL PART – IV

Specification No.T-1987 - Tender for supply and erection of 48 nos. 16 MVA, 110KV Class Power Transformers under rate contract - Commercial and Technical Bids opened - Analysis of Commercial and Technical Terms - Opening of price bids - Approval Accorded. (Technical Branch) (Per.) FB TANTRANSCO Proceedings No.11, Dated the 01st April 2017. Panguni 19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Minutes of the 71st meeting of Board TANTRANSCO held on 28.03.2017 - Item no.14 ----- PROCEEDINGS: Approval is accorded for the following proposal in respect of the tender Specification No.T-1987 for supply and erection of 48 nos. 16MVA, 110KV Class Power Transformers under rate contract: (a) To accept and to open the price bids of the following Seven (7) tenderers under Regular category 1. M/s. Transformers & Rectifiers (India) Ltd., Ahmedabad. Regular 2. M/s Venkateswara Electrical Industries Pvt. Ltd., Chennai. -do- 3. M/s Andrew Yule & Company Ltd., Chennai -do- 4. M/s. SAP Industries, Chennai -do- 5. M/s. Ascott Electricals Pvt. Ltd., Chennai -do- 6. M/s. Supreme Power Equipment Pvt. Ltd., Chennai -do- 7. M/s. Southern Power Equipment Co. Pvt. Ltd., Bengaluru. -do- (b) To reject the offers of the following Two (2) tenderers: S.No. Name of the tenderer Reasons for rejection 1. M/s Shree Abirami Engineering Non-fulfillment of BQR condition Works, Chennai and Commercial terms. 2. M/s. SPS Transformers Pvt. Ltd., Chennai Non-fulfillment of BQR condition. (c) To negotiate with the L1 tenderer after opening of price bids of the eligible tenderers. (By order of the Board) K.Natarajan, Chief Engineer/Transmission. * * * 46

Specification No. T-1988 – Tender for supply and erection of 13 nos. 25MVA, 110/ 33-22KV Power Transformers under rate contract – Commercial and Technical Bids opened – Analysis of Commercial and Technical Terms – Opening of price bids – Approval Accorded. (Technical Branch) (Per) FB. TANTRANSCO Proceeding No.12, Dated the 1st April 2017. Panguni:19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Minutes of the 71st meeting of Board of TANTRANSCO held on 28.03.2017 – Item no.15 ----- PROCEEDINGS: Approval is accorded for the following proposal in respect of the tender Specification No.T-1988 for supply and erection of 13 nos. 25MVA, 110/33-22KV Power Transformers under rate contract. (a) To accept and to open the price bids of the following Seven (7) tenderers: 1. M/s. Transformers & Rectifiers (India) Ltd., Ahmedabad. Regular 2. M/s Venkateswara Electrical Industries Pvt. Ltd., Chennai. -do- 3. M/s Andrew Yule & Company Ltd., Chennai -do- 4. M/s. SAP Industries, Chennai -do- 5. M/s. Ascott Electrical Pvt. Ltd., Chennai -do- 6. M/s. Supreme Power Equipment Pvt. Ltd., Chennai New Entrant 7. M/s. Southern Power Equipment Co. Pvt. Ltd., Bengaluru. -do- (b) To reject the offers of the following tenderer: S.No. Name of the tenderer Reasons for rejection 1. M/s Shree Abirami Enggineering Non-fulfillment of BQR condition. Works, Chennai (c) To negotiate with the L1 tenderers after opening of price bids of the eligible tenderers. (By order of the Board) K.Natarajan, Chief Engineer/Transmission. * * * Specification No. T-1989 – Supply and erection of 40 nos. 8 MVA, 33/11 KV Power Transformers under rate contract – Tender opened - Analysis of Technical and Commercial Terms – Opening of price bids – Approval Accorded. (Technical Branch) (Per.) FB. TANTRANSCO Proceeding No.13, Dated the 1st April 2017. Panguni:19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: 47

Minutes of the 71st meeting of Board of TANTRANSCO held on 28.03.2017 – Item no.16 ----- PROCEEDINGS: Approval is accorded for the following proposal in respect of the tender Specification No.T-1989 for supply and erection of 40 nos. 8 MVA, 33/11 KV Power Transformers under rate contract. (a) To accept and to open the price bids of the following Eight (8) tenderers under Regular category 1. M/s Venkateswara Electrical Industries Pvt. Ltd., Chennai. 2. M/s Andrew Yule & Company Ltd., Chennai 3. M/s. SAP Industries, Chennai 4. M/s. Current Electricals Limited, Chennai 5. M/s. Ascott Electrical Pvt. Ltd., Chennai 6. M/s. Wilson Power & Distribution Technologies Pvt. Ltd., Chennai 7. M/s. Southern Power Equipment Co. Pvt. Ltd., Bengaluru. 8. M/s. Supreme Power Equipment Pvt. Ltd., Chennai (b) To accept and open the price bids following Two (2) tenderers under New Entrants category: 1. M/s. Vishnu Electricals, Chennai 2. M/s. SPS Transformers Pvt. Ltd., Chennai (c) To reject the offers of the following seven (7) tenderers: (i) as not satifying the Bid Qualification Requirements 1. M/s Kerala Electrical & Allied Engineering Co. Ltd., Kerala. 2. M/s Sri Vinayaga Star Electricals, Chennai 3. M/s Sri Perfect Engineering, Chennai (ii) as not satisfying the Commercial Terms 4. M/s Hindustan Heavy Electrical Private Limited, Coimbatore 5. M/s Hindustan Transformers (India) Private Limited, Coimbatore 6. M/s Voltech Manufacturing Company Limited, Sriperumbudur (iii) As not satisfying the Bid Qualification Requirements of furnishing turnover/ profit and loss account details for three years as per specification requirements, though mentioned in the tender offer letter dt. 14.12.2016, as per the remarks of CFC/TANTRANSCO. 7. M/s Indo tech Transformers Limited, Chennai (d) To negotiate with the L1 tenderer/tenderers after opening of price bids of the eligible tenderers. (By order of the Board) K.Natarajan, Chief Engineer/Transmission. * * * 48

CE/MM-Tender specification No.M.14/2015-16- Supply of energy meter test benches, CT and PT test systems and mobile van etc., and establishment of NABL accreditated stationary and mobile labs and getting accreditation from NABL - open tender under two part rate contract system - Placement of orders - Approvals Accorded. (Technical Branch) (Per) FB TANGEDCO Proceedings No.22 Dated the 01st April 2017. Panguni-19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Approval accorded by TANGEDCO BOARD in its 69th meeting held on 28.03.2017. ----- PROCEEDINGS: The TANGEDCO BOARD after a detailed deliberations approved the proposal in its 69th meeting held on 28.03.2017. (i) to place purchase orders on M/s.B.G Associates, Kolkata for supply of energy meter test benches, CT and PT test systems and mobile vans etc., and establishment of NABL accreditated stationary lab at and two nos mobile labs one each at Tirunelveli and Udumalpet NCES circles and getting accreditation from NABL at a total cost of Rs.10,50,86,937-(Rupees Ten crores fifty lakhs eighty six thousands nine hundred and thirty seven only). ii) To place Annual maintenance contract (for monthly service and spares) for 5 years, after expiry of Guarantee period (72 months) at the rate of 0.6% of the cost of the respective plant per year excluding spares and maximum price for the replacement spares during the above maintenance period shall not exceed 1.6% of cost of the respective plant as per the price schedule contemplated in the purchase orders. (By Order of the Board) V. Gopalakrishnan, Chief Engineer/Material Management. * * * TANGEDCO - Coal handling Contract-P.O.48/15.05.2001 - Poclain Charges - Additional item in Schedule I & V in Wagon Manual Unloading Charges at Paradip port - Amendment of P.O.48/dated 15.02.2001 - Approval - Regarding. (Technical Branch) (Per) FB TANGEDCO Proceedings No.23, Dated the 01st April 2017. Panguni -19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Item No.19 of the 69th Board Meeting of the TANGEDCO held on 28.03.2017. ----- PROCEEDINGS: Tamil Nadu Generation and Distribution Corporation Ltd has accorded approval for the following: 49

1. For payment of Poclain charges for Wagon Manual unloading of coal from BOXN wagons at Paradip Port at a firm rate of Rs.20/- per MT excluding Service Tax to M/s.Karam Chand Thapar & Bros (Coal Sales) Ltd w.e.f. 19.12.2014. 2.To amend the Purchase Order No.48 dated 15.02.2001, issued on M/s.Karam Chand Thapar & Bros (Coal Sales) Ltd. by incorporating an additional item in the Price Schedule -I & V as given below without any change in the other terms & conditions of the P.O.48 dt.15.02.2001. Sl Description of Work Variable or Authority Amount No: Firm responsible for Rs. Ps. Rs.Ps. price variation PerMT Non Statutory Charges 1. Poclain Charges for Wagon Firm NA 20.00 Manual Unloading Charges Service Tax will be paid at actual as per the Notification from Govt. of India. (By Order of the Board) N. Sathiyaseelan, Chief Engineer/Mechl./Coal. * * * MTPS II -1x 600MW-Mechanical II-Fire Protection system-Electrical-Annual Maintenance Contract for Nitrogen Injection Fire Prevention and Fire Extinguishing system for Power Transformers (5 Nos) to M/s. Natesan Engineering Contractor, Metturdam-2 authorized dealer of M/s. CTR Manufacturing Industries Ltd, Pune, under Single Tender / Proprietary/Private sector - Approval - Accorded - Regarding. (Technical Branch) Per (FB) TANGEDCO Board Proceedings No.24, Dated the 01st April 2017. Panguni 19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : Item No.6 of the 69th BOARD meeting of TANGEDCO held on 28.03.2017. ----- PROCEEDINGS: Approval is accorded for the following: To award the work of Annual Maintenance Contract for Nitrogen Injection Fire Prevention and Fire Extinguishing system of 5 Nos Power Transformers (Interconnected Transformers I&II, Unit Transformer I&II and Station Transformer) of 600MW unit of MTPS II for a period of one year from the date of commencement of work to M/s.Natesan Engineering Contractor, Metturdam-2 authorized dealer of M/s. CTR Manufacturing Industries Ltd, Pune, at a total cost of Rs.3,85,250/- (Rupees Three lakhs Eight Five Thousand Two Hundred and fifty only) inclusive of taxes under Single Tender/proprietary/private sector by the Chief Engineer of MTPS II. (By Order of the Board of TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * B.B.4 (Apr 17) 50

TANGEDCO - Tuticorin Thermal Power Station - Tripping of Unit V due to failure of Boiler down comer pipe - Rectification of damaged Boiler components and restored Unit V in complete shape by entrusting the works to M/s. BHEL on mutually agreed price, under single tender/proprietary basis - Approval Accorded and Ratified. (Technical Branch) Per (FB) TANGEDCO Proceedings No.25 Dated the 01st April 2017. Panguni 19, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : Extract of Minutes of 69th Board meeting of TANGEDCO held on dt. 28.03.2017 vide Item No.36 ----- PROCEEDINGS: Approval and ratification is accorded for the action taken by CE/TTPS for having entrusted the work to M/s. BHEL towards rectification of damaged Boiler components and restoration of Unit V in complete shape at a total cost of Rs.4,35,91,250/- (Rupees four crores thirty five lakhs ninety one thousand two hundred and fifty only) including all taxes & duties, freight charges under single tender (Public sector)/ Proprietary basis, in lieu of urgency, in anticipation of approval of Board. (By Order of the Board of TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * Specification T-1973-Procurement of 110 Nos., 230KV Outdoor SF6 Circuit Breakers with Terminal Connectore-Opening of Price bids Approval Accorded - Regarding. (Technical Branch) Per (FB).TANTRANSCO Proceedings No.15 Dated the 03rd April 2017. Panguni-21, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : Item 10 of the minutes of 71st meeting of the Board for TANTRANSCO held on 28.03.2017. ----- PROCEEDINGS: The Board of Tamil Nadu Transmission Corporation Ltd after careful consideration approves the following proposal of the Chief Engineer/Transmission. 1. To open the price bids of the following three (3) Tenderers as Regular who have complied with BQR, Technical & Commercial terms of the specification and satisfied vendor rating. (i) M/s.GE T&D India Ltd, , Chennai (ii) M/s. Siemens Ltd., Aurangabad. (iii) M/s. Crompton Greaves Limited, Nashik 51

2. To reject the offer of the following one (1) tenderer due to non fulfillment of BQR Condition (Type Test). (i) M/s.ABB India Ltd., Vadodara 3. To negotiate with the L1 tenderer, after opening of price bids. (By Order of the Board) K.Natarajan, Chief Engineer/Transmission. * * * NCTPS II - 2x600 MW - Procurement of FD & PA fans hydraulic adjusting device & FD fan Impeller blades and its accessories - To place orders on M/s.BHEL - Under Single tender/Proprietary basis/Public sector - Approval Accorded - Regarding. (Technical Branch) Per (FB) TANGEDCO Board Proceedings No.26 Dated the 03rd April 2017. Panguni 21, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : Item No.17 of 69th BOARD meeting of TANGEDCO held on 28.03.2017. PROCEEDINGS: Approval is accorded for placing an order on M/s.BHEL, Chennai for the procurement of following 3 items of FD & PA fan hydraulic adjusting device, FD Impeller blades and its accessories as given below at a total cost of Rs.2,19,70,069/- (Rupees Two crores nineteen lakhs seventy thousand and sixty nine only) inclusive of taxes and duties & exclusive of Freight & Insurance charges as discussed in the note under Single tender/Proprietary basis/Public sector by CE/NCTPS II. Sl.No. Description/Technical Specification Qty in Nos. 1. Hydraulic Adjusting Device Assembly of FD fan of 1 600 MW (Type:FAF24.5/11.8-1) 2. Hydraulic Adjusting Device Assembly of PA fan of 1 600MW (Type PAF 20/10.6-2) 3. FD fan Impeller blades and its accessories of 600MW 14 (Type:FAF 24.5/11.8-1) (By Order of the Board of TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl/Thermal Stations (I/c) * * * TANGEDCO - Ennore Thermal Power Station - Some of the chemical items & insulation materials stored in the Stores got dissolved due to Vardha cyclone on 12.12.2016 - Losses be write off - Approval Accorded. (Technical Branch) Per FB TANGEDCO Proceedings No.28 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : 52

Extract of Minutes of 69th Board meeting of TANGEDCO held on 28.03.2017 vide Item No.18 ----- PROCEEDINGS: Approval is accorded to Write off the losses of Rs.3,50,711/- (Rupees Three lakhs Fifty Thousand Seven Hundred and Eleven only) caused during the recent vardha cyclone on 12.12.2016 by way of dissolved chemicals & insulation materials at Ennore Thermal Power Station”. (By Order of the Board of TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * Theft of materials from the released Distribution Transformer of 75KVA/22KV DT (Make:GEF:Sl.No.7232,) from the Singalanthapuram SS XVII/Rasipuram subdivision/ Namakkal EDC-write off the amount of Rs.53,594/- Approved. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.28 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : 1. Lr.No.012251/CE/D/ED/AEE/GL/F.Write Off/D.675/16, Dt 12.08.2016 2. Lr.No.020348/CE/D/ED/AEE/GL/F.Write Off/D.1142/16, Dt 30.12.2016 3. CMD’s Note approval dated 31.03.2017. ----- PROCEEDINGS: Approval is hereby accorded to write off the amount of Rs.53,594/- (Rupees Fifty three thousand five hundred and ninety four only) towards theft of materials from the released Distribution Transformer of 75KVA/22KV DT (Make:GEF:Sl.No.7232,) from the Singalanthapuram SS XVII/Rasipuram subdivision/ Namakkal EDC. (By Order of the Chairman - cum - Managing Director) V. Gopalakrishnan, Chief Engineer/Materials Management. * * * 53

TANGEDCO - Bhavani Kattalai Barrage - III HEP (2x15MW) - Construction of 1 Block of ‘S’ type Quarters(twin type), 1 Block ”R” type - 6 Nos, 4 Block “Q” type 24- Nos quarters (Totally 32 Nos Tenements), Bore well, elevated water tank, sump tank, car and two wheeler shed, drainage, formation of road, guard room for Officers and Staffs at Bhavani Kattalai Barrage - III Power House at Pasur Village - Administrative Approval - Accorded- Regarding. (Technical Branch) Per (FB) TANGEDCO Proceedings No.29 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu -2048. READ : Minutes of the 69th meeting of the Board of TANGEDCO held on 28.03.2017 Item No.7 ----- PROCEEDINGS: Board of TANGEDCO has accorded approval for the Administrative sanction for the work of “Construction of 1 Block of ‘S’ type Quarters (twin type), 1Block “R” type - 6Nos., 4 Block “Q” type-24 Nos. quarters (Totally 32 Nos. Tenements), Bore well, elevated water tank, sump tank, car and two wheeler shed, drainage, formation of road, guard room for Officers and Staffs of Bhavani Kattalai Barrage-III (2x15MW) Power House at Pasur Village” at an estimated cost of Rs.7,22,16,000/- (Rupees Seven crore Twenty Two lakh and Sixteen thousand only) including Contingencies, WCT, LWF and Service Tax. (By Order of the Board of TANGEDCO) C.Ramesh, Chief Engineer/Civil Designs. ANNEXURE TO PER (FB) TANGEDCO PROCEEDINGS NO.29, DT.04.04.2017 COST ABSTRACT 2016-17 Sl. Description of works Work value Service Tax @ No. including 15% on 40% LWF WCT & of work value Contingencies in Rs. in Rs. Total Abstract - A Rs. 1. Construction of 4 Blocks “Q” type quarters Block I3,25,40,082 19,31,918 3,44,72,000.00 (Ground Floor+2Floors) 24 tenements Abstract - B 2. Construction of 1 Blocks “R” type quarters Block I 1,15,37,524 6,84,976 1,22,22,500.00 (Ground Floor+2Floors) 6 tenements Abstract - C 3. Construction of 1 Blocks “S” type quarters (twin type), 63,78,789 3,78,711 67,57,500.00 (total 2 Tenements) 54

Abstract - D 4. providing allied works in the 1,61,40,742 9,58,258 1,70,99,000.00 quarters Abstract - E 5. providing approach road in 15,71,705 93,295 16,65,000.00 the Quarters area. Total Cost Works 6,81,68,842 40,47,158 7,22,16,000.00 (or) say Rs. 7,22,16,000/- (Rupees Seven Crore Twenty Two Lakh and Sixteen Thousand only) //True Copy// * * * HRD - Engagement of Tradesman ITI Apprentices - Payment of the revised stipend from Rs.2800/- to Rs.7709/- to the Tradesman ITI Apprentices - Approval - Accorded. (Technical Branch) Per. F.B. TANGEDCO Proceedings No.30 Dated the 04th April 2017. Panguni 22, Sri Dhunmughi Varudam, Thiruvalluvar Aandu -2048. READ : (i) (Rou) F.B. TANGEDCO Proceedings No.01 (Tech.Br.) Dated 23.05.2013. (ii) Extract from the Minutes (Item No.09) of the 69th Board meeting held on 28.03.2017. ----- PROCEEDINGS: The Board had accorded approval for engagement of 2400 nos. of Tradesman ITI Apprentices (ie., 2000 for Distribution Circles, 70 for GCC Wings, 30 for P&C Wings and 300 in Thermal Power stations) in the trade of Electrician & Wireman for the year 2013-14, and communicated vide proceedings cited (1) above. The Tradesman ITI Apprentices stipend was revised from Rs.2800/- to Rs.7709/- with effect from 22.09.2014 based on the Government of India Gazette Notification No.492 dated:22.09.2014 and also as communicated by the Regional Joint Director’s/Department of Employment and Training, Chennai letter dt:19.11.2015. Hence, the difference of stipend amount of Rs.4,909/- (Rs.7709 - Rs.2800 = Rs.4909) has to be paid to the apprentices with effect from 22.09.2014 (i.e. who were engaged/passing by the revised stipend period notified by the Government of India) After careful consideration, the Board has accorded approval for the following: 1) To make the payment of the enhanced amount of monthly stipend to Tradesman ITI Apprentices (Electrician/Wireman) from Rs.2800/- to Rs.7709/- (who were engaged/passing by the revised stipend period) as per the Govt. of India notification (i.e., with effect from 22.09.2014) by the respective field Superintending Engineers. 55

2) The expenditure is debitable to Account head 75 - Employees Cost 75 - 170-Salaries - Apprentices. (By Order of the Board) K.Surendran, Chief Engineer/IC,R&D * * * TANGEDCO – NCES –Establishment of Co-generation plants in 12 Nos. Co-operative and public sector sugar mills in Tamil Nadu – P.O.No.02 dt 27.05.09 placed on M/s. MITCON Consultancy & Engineering Services Ltd., Pune for offering Consultancy Services of Pre EPC Contract, Post EPC Contract and Project Management Services providing one Senior Resident Engineer per site, for two sits at a time to co-ordinate and monitor the progress of works till the Commissioning of all the Plants – Extension for Consultancy Service Contract for Post contract services at the revised rates from October 2015 until Commissioning of all the Plants-Approval-Accorded. (Technical Branch) (Per) FB TANGEDCO Proceedings No.31 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Item No.8 of the Extract from the Minutes of 69th Board meeting of TANGEDCO held on 28.03.2017. ----- PROCEEDINGS: The Tamil Nadu Generation and Distribution Corporation Limited after careful consideration, approves the following proposal in respect of Establishment of Co-generation plants in the existing 12 Nos. Co-operative & Public Sector Sugar Mills in Tamil Nadu along with sugar mill modernization by TANGEDCO. To issue extension order for the existing Purchase order No.02 dt 27.05.2009 placed on M/s. MITCON Consultancy & Engineering Services Ltd., Pune (M/s.Mitcon) for Post Contract Services from October 2015 until commissioning of all the Plants at the revised following rates, 1. To utilize the consultancy services of M/s. MITCON Consultancy & Engineering Services Ltd., Pune for providing one Senior Resident Engineer per site, for two sits at a time for a total cost of Rs.4Lakhs + Applicable Service Tax per month in line with the requirement of TANGEDCO from July 2016 till commissioning of all projects. 2. To accord approval for revised consultancy charge of Rs.2 Lakhs + Service tax offered by M/s MITCON, Pune for the period from October 2015 to June 2016, as M/s MITCON,Pune has been continuing their project management services in spite of the show cause notice issued. 3. To approve and ratify the action of having utilized the services of M/s MITCON, Pune at the revised rates from July 2016. All other terms & conditions stipulated in the P.O. No.02 dt.27.05.2009 remains unaltered. (By Order of the Board) M. Balasubramanian, Chief Engineer/NCES. * * * 56

TANGEDCO – IT WING – Enhancement of ISP bandwidth Links – Administrative Approval – Accorded. (Technical Branch) (Per) CMD TANGEDCO Proceedings No.186 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Note approved by the CMD/TANGEDCO dated 27.03.2017. ----- PROCEEDINGS: TANGEDCO hereby approves the proposal of IT wing to enhance the bandwidths of the existing Internet Leased Line-I available in the Head Quarters Legacy Data Centre to 155 Mbps with options below: Option I: With burstible option of 620 Mbps at an approximate cost of Rs.9,75,000/- (Rupees Nine Lakhs and Seventy Five thousand only) and Rs.6,29,000/-(Rupees Six Lakhs and Twenty Nine Thousand only) for Recurring Annual and infrastructure cost plus Rs.1000 per MB/Month. Option II: With burstible Option of 1 Gbps at an approximate cost of Rs.9,75,000/- (Rupees Nine Lakhs and Seventy Five thousand only) and Rs.21,87,000/- (Rupees Twenty One Lakhs and Eighty Seven Thousand only) for Recurring Annual and infrastructure Cost plus Rs.1000 per MB/Month. Opton-I to be exercised for a period of six months to monitor and ensure successful implementation of e-tender process and to retain the same option if proven successful, otherwise to exercise Option II. The suitable option exercised shall be renewed every two years under Open Tender System. The expenditure in this regard is debatable to TANGEDCO Ltd., Funds – Capital Expenditure A/c.76.117 (Internet Charges). (By Order of the Chairman - cum - Managing Director/TANGEDCO) S. Santhi, Chief Engineer/IT. * * * NCES – HT consumers establishing roof top/ground mounted solar power plants within the premises of service connection for captive use – Solar injection at HT consumer’s HT/LT network – Maintaining separate seniority for solar capacity upto 500 KW and separate seniority for solar capacity more than 500 KW – Approval Accorded. (Technical Branch) (Per) CMD TANGEDCO Proceedings No.187 Dated the 04th April 2017. Panguni 22, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: 1. CMD/TANGEDCO approval dated 26.08.2014. 57

2. CMD / TANGEDCO approval dated 19.02.2015. 3. CMD / TANGEDCO Note approval dated 27.03.2017. ----- PROCEEDINGS: The CMD/TANGEDCO has accorded approvals vide ref(1) & (2) above, permitting the HT consumers to interface the proposed roof top solar power plants in their HT/ LT network i.e. for mere parallel operation for captive use within the premises of the existing HT service connection. The HT consumers are permitted to interface their proposed roof top/ground mounted solar power plants in their HT/LT network for captive use without export. In this connection, for the establishment of roof top/ground mounted solar power plants within the HT consumer premises for captive use without export, the procedure as set forth below is hereby approved in addition to the procedures already approved vide references (1) and (2) above. 1. The registration fee for the roof top/ground mounted solar power plants proposed to be established within HT consumers premises for captive use is enhanced per application in the following manner: a. Upto 10 KW – The registration fee is enhanced from Rs. 5000/- per application to Rs. 10,000/- per application for the year 2017-18 and it will be enhanced 25% every year thereafter. b. Above 100 KW and - The registration fee is enhanced from Rs. 5000/- upto 500 KW per application to Rs. 15,000/- per application for the year 2017-18 and it will be enhanced 25% every year thereafter. c. Above 500 KW - The registration fee is enhanced from Rs. 5000/- per application to Rs. 25,000/- per application for the year 2017-18 and it will be enhanced 25% every year thereafter. 2. Separate seniority shall be maintained for the roof top/ground mounted solar power plant applications of capacity upto 500 KW, proposed to be established within HT consumer’s premises for captive use. 3. Separate seniority shall be maintained for the roof top/ground mounted solar power plant applications of capacity more then 500 KW, proposed to be established within HT consumers premises for captive use and such consumers may be requested to furnish copy of CEIG’s safety clearance at CE/NCES office for getting parallel operation approval from TANGEDCO. 4. Future policy changes if any i.e. eligibility of availing net metering facility or net feed in tariff facility to the HT consumers, shall also be applicable to the existing HT consumers those who have availed parallel operation approval for the establishment of rooftop/ground mounted solar power plants within the premises for captive without export. (By Order of the Chairman - cum - Managing Director) M. Balasubramanian, Chief Engineer/NCES. * * * 58

TANGEDCO – Chief Engineer/Civil Designs – Provision of 3 Nos. of Core i3 Desktop PCs and 3 Nos. of duplex laser jet printers for the official use of Assistant Executive Engineer/Civil – II in PCC Division –I, Assistant Executive Engineer/Civil – I&II in the PCC Division – II in the Superintending Engineer/Civil/PCC & DRIP Circle at the office of the Chief Engineer/Civil Designs – Approval –Accorded - Regarding. (Technical Branch) Per (CMD) TANGEDCO Proceedings No.192 Dated the 06th April 2017. Panguni-24, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: The Chief Engineer/Civil Designs note, approved by the CMD/ TANGEDCO Dated 30.03.2017. ----- PROCEEDINGS: Approval is here by accorded for the provision of 3 Nos. of Core i3 Desktop PCs and 3 Nos. of duplex laser jet printers at an approximate cost of Rs.1,65,000/- (Rupees one lakh and sixty five thousand only) for the official use of Assistant Executive Engineer/Civil – II in PCC Division – I, Assistant Executive Engineer/Civil – Division – I & II in the PCC Division – II in the Superintending Engineer/Civil/PCC & DRIP Circle at the office of the Chief Engineer/Civil Designs, with the following expenditure. Sl. Description Qty Price/Unit No. (all inclusive) Amount in Rs. In Rs. 1 Core i3 Desktop PC 3 Nos. 45,000.00 1,35,000.00 2 Duplex Laser Pinter 3 Nos. 10,000.00 30,000.00 Total 1,65,000.00 Or say Rs.1,65,000/- (By Order of the Chairman - cum - Managing Director/TANGEDCO) A. Vasudeva, Chief Engineer/Civil Designs (I/c) * * * TANGEDCO – Allocation of Indigenous coal from Coal India Ltd (CIL) through FSA route – Transfer of 0.50 Million Tonnes Per Annum (MTPA) of coal from Mahanadi Coalfields Ltd (MCL) to Western Coalfields Ltd (WCL) – Signing of FSA with WCL and Amendment for the modified quantity with MCL for FSA 2009 - Approval Accorded - Regarding. (Technical Branch) Per FB TANGEDCO Proceedings No.32 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Item No.55 of the extract of Minutes of the 69th Board Meeting of TANGEDCO held on 28.03.2017. ----- 59

PROCEEDINGS: TANGEDCO Board has approved the following: 1. To execute a Fuel Supply Agreement (FSA)/MoU with Western Coalfields Ltd (WCL) for the quantity of 0.50 Million Tonnes per Annum (MTPA). 2. To execute an amendment for the modified quantity with Mahanadi Coalfields Ltd (MCL) for Fuel Supply Agreement (FSA) 2009. 3. To authorize Director (Generation)/TANGEDCO or Chief Engineer/Mechanical/ Coal to sign the above FSA/MoU with coal companies. N. Sathiyaseelan, Chief Engineer/Mechl./Coal. * * * NCTPS I – M.II Circle-ICHS Division-Urgent procurement of one no.Elecon make Helical gearbox model KCH – 315 and its Hollow shaft required for replacement of worn out Gearbox in Boom and Intermediate conveyors of Stackers in Internal Coal Handling System of North Chennai Thermal Power Station-I under Single tender system / Proprietary/Private sector basis Administrative Approval-Accorded. (Technical Branch) Per (CMD) TANGEDCO Proceedings No.193 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Note approved by the CMD/TANGEDCO on 05.04.2017. ----- PROCEEDINGS: Administrative Approval is accorded for urgent procurement of one no.Elecon make Helical gearbox model KCH – 315 and its Hollow shaft required for replacement of worn out Gearbox in Boom and Intermediate conveyors of Stackers in Internal Coal Handling System of North Chennai Thermal Power Station – I at a total cost of Rs.33,04,800/- (Rupees Thirty three lakhs four thousand and eight hundred only) including taxes and duties under Single tender system/Proprietary/Private sector basis from M/s.Elecon Engineering Company Limited, Gujarat by CE/NCTPS I. (By Order of the Chairman - cum - Managing Director/TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * NCTPS.I– M.II Circle- Internal Coal Handling Division – Supply, Erection, Testing and Commissioning of Hydraulic Braking System for Reclaimer.I & Travelling Tripper.B of ICHS at NCTPS.I- Administrative Approval-Accorded. (Technical Branch) Per (CMD) TANGEDCO Proceedings No.194 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: 60

Note approved by the CMD/TANGEDCO on 05.04.2017. ----- PROCEEDINGS: Administrative Approval is accorded for the work of Supply, Erection, Testing and Commissioning of Hydraulic Braking System for replacement of the existing worn- out/damaged Electro Hydraulic Brakes of Reclaimer – I & Travelling Tripper-B at NCTPS- I for an approximate total cost of (Gross) Rs.1,52,71,000/- (Rupees One crore fifty two lakhs seventy one thousand only) and (Nett) Rs.1,52,27,000/-(Rupees One crore fifty two lakhs and twenty seven thousand only) inclusive of all taxes and duties under Open Tender System by Chief Engineer/NCTPS I. (By Order of the Chairman - cum - Managing Director/TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl/Thermal Stations (I/c) * * * Mettur Thermal Power Station – I – Capital overhauling and RLA study of 210 MW LMW design Turbo-Generator of Unit-IV/MTPS-I- Administrative Approval-Accorded. (Technical Branch) Per TANGEDCO Proceedings (CMD) No.195 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Note approved by CMD on 06.04.2017. ----- PROCEEDINGS: Administrative Approval is accorded for Capital overhauling and RLA study of 210 MW LMW design Turbo-Generator of Unit-IV/MTPS-I- during 2017-18 under open tender system for an amount of Rs.3,19,15,000/-(Three Crore Nineteen Lakhs Fifteen Thousand only) inclusive of all taxes & duties by CE/MTPS-I. (By Order of the Chairman - cum - Managing Director/TANGEDCO) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * Tuticorin Thermal Power Station – Retrofitting of 210 MW LMW surface condenser in any one of the Units of I, II & III under single tender proprietary basis by M/s.BHEL - Administrative Approval-Accorded. (Technical Branch) Per TANGEDCO Proceedings (CMD) No.196 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Note approved by the CMD/TANGEDCO on 05.04.2017. ----- 61

PROCEEDINGS: Administrative Approval is accorded for Retrofitting of 210 MW LMW surface condenser in any one of the Units of I, II & III at Tuticorin Thermal Power Station at an approximate total cost of Gross: Rs.27.77Cr.(Rupees twenty seven crores and seventy seven lakhs only) and Net. Rs.27.27 Cr. (Rupees twenty seven crores and twenty seven lakhs only) inclusive of duties and taxes under single tender proprietary basis by M/s.BHEL as requested by CE/TTPS. (By Order of the Chairman - cum - Managing Director) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * MTPS-I – Installation and commissioning of additional 2 Nos. Continuous Ambient Air Quality Monitoring Stations along with Data uploading facility and to establish connectivity with the CARE AIR Centre/TNPCB/Chennai - Administrative Approval- Accorded. (Technical Branch) Per TANGEDCO Proceedings (CMD) No.197 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi varudam, Thiruvalluvar Aandu ,2048. READ: Note approved by the CMD/TANGEDCO on 05.04.2017. ----- PROCEEDINGS: Administrative Approval is accorded for installation and commissioning of additional 2 Nos. Continuous Ambient Air Quality Monitoring Stations along with Data uploading facility and to establish connectivity with the CARE AIR Centre/ TNPCB/ Chennai at Mettur Thermal Power Station-I at an approximate cost of Rs.98,07,000/- (Rupees ninety eight lakhs and seven thousand only) including taxes & duties under open tender system by CE/MTPS-I. (By Order of the Chairman - cum - Managing Director) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * Tuticorin Thermal Power Station – Units I – Capital Overhauling of TG Set and RE RLA Study on Turbine Components in Unit I - Administrative Approval-Accorded. (Technical Branch) Per TANGEDCO Proceedings (CMD) No.198 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Note approved by the CMD/TANGEDCO on 05.04.2017. ----- 62

PROCEEDINGS: Administrative Approval is accorded for Capital Overhauling of TG Set and Re RLA Study on Turbine Components in Unit I at Tuticorin Thermal Power Station during 2017-2018 at an approximate cost of Rs.1,93,38,400/- (Rupees one crore ninety three lakhs thirty eight thousand and four hundred only) including service tax under open tender system by CE/TTPS. (By Order of the Chairman - cum - Managing Director) T. Balasubramanian, Chief Engineer/Mechl./Thermal Stations (I/c) * * * TANGEDCO – Coimbatore Region – Tiruppur EDC-Establishment of new Kalivelampatty 230/110 KV SS at Valampalayam village, Paladam Taluk, Tiruppur District – Purchase of land from private party – Payment of land cost - Approval-Accorded. (Technical Branch) Per. (CMD) TANGEDCO Proceedings No.199 Dated the 07th April 2017. Panguni 25, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: CE/CD Note approved by the CMD on 01.04.2017. ----- PROCEEDINGS: Approval is accorded for the following: i) To purchase 18.99 Acres of private patta lands in survey number 169/1 & 170/1 at Velamplayam village, Palladam Taluk, Tiruppur District (1.09 acres in S.F>No169/1 and 17.9 acres in S.F.No.170/1) at the rate of Rs.22,00,000/- per acre, totally for an amount of Rs.4,17,78,000/-(Rupees Four crore Seventeen lakhs and Seventy Eight thousand only) from Tmty.S.Mohanarani, Thiru.M.Easwaran and several others for the establishment of New Kalivelampatty 230/110 KV SS at Velampalayam village, Palladam Taluk, Tiruppur EDC, Coimbatore Region. ii) To incur expenditure towards stamp duty @ 7%, registration charges @ 1% documentation, computer charges, etc., as applicable. iii) The Chief Engineer/Distribution/Coimbatore shall make necessary newspaper publication regarding purchase of the lands from the parties in consultation the Government pleader concerned. iv) The Chief Engineer/Distribution/Coimbatore Region shall ensure that all the documents are free from encumbrance on the date of registration and the revenue records such as Patta, Chitta, Permanent land Register etc., reflect the ownership in the name of TANGEDCO, after registration of land. (By Order of the Chairman - cum - Managing Director) A. Vasudeva, Chief Engineer/Civil Designs (I/c) * * * 63

TANGEDCO –IT Wing – Provision of New /Additional Broadband internet connection for e-tendering / e-procurement purpose exclusively – Approval Accorded. (Technical Branch) (Per) CMD TANGEDCO Proceedings No.202 Dated the 11th April 2017. Panguni 29 Sri Dhurmughi Varudam, Thiruvalluvar Aandu-2048. READ: CMD Note approval dated 07.04.2017. ----- PROCEEDINGS: TANGEDCO after careful consideration hereby approves the following: Availing of New / Additional Broadband Connection with BSNL BBG Combo ULD 1599 plan with unlimited download / upload limit, 4 Mbps up to 40GB, 1Mbps beyond 40 GB bandwidth for Uploading and downloading of documents or with any other service provider not exceeding the expenditure limit of the above plan for e-tendering / e-procurement process exclusively as follows: a. Two Nos. of Broadband connections for each Chief Engineer/Thermal Power Stations. b. One No. Broadband connections for each e-tender inviting authorities of TANGEDCO and TANTRANSCO offices (Chief Engineers & Superintending Engineers other than Headquarters) except Thermal Power Stations. with no change in following expenditure: 1. One time expenditure : Rs.2600/- (including modem) 2. Annual Expenditure : Rs.1599/- per month plus Tax The above expenditure is debitable to the account head “Revenue expenditure No.76.117 (Internet Charges)”. (By Order of the Chairman - cum - Managing Director/TANGEDCO) S. Santhi, Chief Engineer/IT. * * * Hydro – Generation Circle/Tirunelveli – Improvement works to the existing Inspection Bungalow including Annexe I & II at Papanasam Lower Camp by providing new Doors, Windows, Water Supply & Sanitary items, Vitrified Tile Flooring, Electrification, Furniture, etc., in place of the damaged ones - Administrative Approval-Accorded. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.30 Dated the 12th April 2017. Panguni 30, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: CE/Hydro’s note approved by the CMD/TANGEDCO dt. 07.04.2017. ----- 64

PROCEEDINGS: Administrative Approval is accorded for the carrying out “Improvement works to the existing Inspection Bungalow including Annexe I&II at Papanasam Lower Camp by providing new Doors, Windows, Water Supply & Sanitary items, Vitrified Tile Flooring, Electrification, Furniture, etc., in place of the damaged ones” for an amount of Rs.24,03,000/- (Gross) & Rs.23,98,000/- (Nett) inclusive of service tax based on the current PWD Schedule of rates and Prevailing local market rates for the 2016-2017. (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * TNEB – Head Quarters Complex – Purchase of drinking water from CMWSSB to TNEB HQ Complex through Tanker lorries for the period of five months or complete utilization of P.O during I Phase of 2017, from the date of utilization of purchase order - Administrative Approval - Accorded. (Technical Branch) (Rt.) (CMD) TANGEDCO Proceedings No.31 Dated the 13th April 2017. Panguni 31, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: CE/CD’s note approved by CMD dt. 11.04.2017. ----- PROCEEDINGS: a. Administrative Approval is hereby accorded to the purchase of 1,44,00,000 litres of drinking water from Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) using water tanker lorry loads of 9000 litres capacity at the rate of Rs.600/- per tanker or at the rate of 1068/- per 16,000 litres capacity or at the rate of Rs.1335/- per 20,000 litres capacity, at the total value of Rs.9,61,200/- (Rupees nine Lakhs sixty one thousand and two hundred Only) for a period of five or complete utilization of P.O month from placing of purchase order to cater to the needs at TNEB Head Quarters Complex. b. Approval is also accorded to make an advance payment varying from Rs.56,400/- to Rs.69,000/- per month CMWSSB for five months or complete utilization of P.O during I Phase of 2017 from placing of purchase order without exceeding the face value of the P.O. to be issued towards supply of water to cater the needs at TNEB Head Quarters Complex. The expenditure is changeable to TANGEDCO Fund – Revenue expenditure A/c Head No.76.190, water charges. (By Order of the Chairman - cum - Managing Director/TANGEDCO) C. Ramesh, Chief Engineer/Civil Designs. * * * 65

TANGEDCO Hydro – Erode Generation Circle – Barrage Power House – 2/Nerinjipettai – Replacement of 3nos. bottom ducts and Strengthening & reconditioning of 3 nos. top ducts in 5 numbers Barrage Gates - Administrative Approval-Accorded. (Technical Branch) (Per.) CMD TANGEDCO Proceedings No.204 Dated the 13th April 2017. Panguni 31, Sri Dhurmughi Varudam, Thiruvalluvar Aandu 2048. READ: Administrative approval note approved by CMD/TANGEDCO on 07.04.2017. ----- PROCEEDINGS: CMD/ TANGEDCO has accorded administrative approval on the proposal for replacement of bottom 3 nos. ducts and strengthening & reconditioning of top 3 nos. top ducts in 5 numbers Barrage Gates (Gate Nos. 1,2,3,4,&5) at Barrage Power House -2 / Nerinjipettai, Erode Generation Circle at a cost of Rs.3,46,69,000/- (Rupees Three Crores forty six lakhs and sixty nine thousand only) Gross and Rs.3,36,69,000/- (Rupees Three Crores thirty six lakhs and sixty nine thousand only) Nett. including VAT at 5% on material portion and service tax at 15% on labour portion under open tender two part system for safe operation of gates during flood condition. (By Order of the Chairman - cum - Managing Director/TANGEDCO) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * Lr. No. SE/RE&I(D)EE/RE/A1/F.Doc./D250/17, (Tech.Br.) dt.13.04.2017. Sub : Elecy. – TANGEDCO – Minutes of Distribution Review meeting – Agriculture – Distribution Transformer – DT meter – Instruction – Regarding. Ref : Lr. No. SE/RE&I(D)EE/RE/A2/F.Review Meeting/D.187/17, dt.22.03.2017. ----- The minutes of the Review Meeting held with CEs/D, SEs/EDC and Headquarters official was communicated vide ref. cited above. Based on point.No.7.0 of the above minutes, all the Chief Engineers/ Distribution region are requested to arrange to provide Energy meters in Distribution Transformers while proposing New Distribution Transformers for agriculture services in future. M.A. Helen, Director (Distribution). * * *

B.B.5 (Apr 17) 66

Memo. No.CE/Comml./SE/EE/R&C/AEE.1/F.R&C/D.078/17, (Techl.Br.) dt.17.04.2017. Sub : Elecy. –Continuance of withdrawal of 90% demand and energy cut for HT Industrial & Commercial services imposed during evening peak hours (6.00 p.m. to 10.00 p.m.) beyond 01.04.2017 – Instruction Issued – Regarding. Ref : 1) Memo No. CE/Comml./SE/EE/R&C/AEE.1/F.Power Cut /D.210/16, dt.19.10.2016. 2) Energy (A1) Dept. Letter (Ms) No.21, dt.03.04.2017. ----- In continuation to the instruction issued vide reference (1) cited above and as per approval of Government vide reference (2) cited, withdrawal of 90% demand and energy cut for HT Industrial and Commercial services imposed during evening peak hours (06.00 p.m. to 10.00 p.m.) is continued beyond 01.04.2017. Hence, all Superintending Engineer/EDC are requested to inform the HT consumers accordingly. (By Order of the Chairman- cum - Managing Director) M. Thangaraj, Chief Engineer/Commercial. * * * Tirunelveli Region – Provision of One No. New Transformer Oil Filter Machine of 2.4KL capacity by replacing the existing condemned Oil Filter Machine for the Special Maintenance wing at Virudhunagar EDC - Administrative Approval-Order – Issued. (Technical Branch) Routine CMD TANGEDCO Proceedings No.32 Dated the 21st April 2017. Chittirai 8, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: 1. Chief Engineer/D/Tirunelveli Region’s Lr.No.CE/D/TIN/ EE/EL/AEE/MM/F.49/D.263/17, Dt. 14.03.2017. 2. CMD TANGEDCO's Note approval dt.18.04.2017. ----- PROCEEDINGS: Approval is accorded for provision of One No. New Transformer Oil Filter Machine of 2.4KL capacity by replacing the existing condemned Oil Filter Machine for the Special Maintenance wing at Virudhunagar EDC of Tirunelveli Region for an amount of Rs.5,52,240/- Gross & Rs.5,45,865/- Nett plus taxes as applicable. (By Order of the Chairman- cum - Managing Director) V. Gopalakrishnan, Chief Engineer/Materials Management. * * * 67 foj v©.nkbgh/Cäknk(g)/brbgh/Cä/cbrbgh2/nfh¥ò/v©.262 (bjh.E.») ehŸ 21.04.2017. bghUŸ : ä‹rhu« - Áw¥ò K‹Dçik étrha é©z¥g§fŸ 2017-18 M« M©L F¿pL - 215 v©z« é©z¥g§fŸ éLé¡f¥gLjš - r«gªjkhf. gh®it : jäHf muR f.v©. (MS) v©.46 ehŸ 13.08.2015. ----- gh®itæ‹go 2017-18 M« M©o‰F Áw¥ò K‹Dçik¤ £l¤Âš mDk¡f¥g£l ÃçédU¡F étrha ä‹ Ïiz¥ò tH§f 215 é©z¥g§fŸ Ï›tYtyf¤ÂèUªJ éLé¡f¥gL»wJ. Ϫj é©z¥g§fë‹ bga® g£oaš k‰W« gÂÎ brŒa¥g£lj‹ égu§fŸ Ïiz¡f¥g£LŸsJ. ÏJ muÁ‹ Áw¥ò K‹Dçik¤ £lkhf ÏU¥gjhš, mid¤J jiyik¥ bgh¿ahs®fŸ/ ä‹ éãnahf«/k©ly« mt®fŸ cldoahf elto¡if vL¡FkhW nf£L¡ bfhŸs¥gL»wh®fŸ. jah® ãiy gÂÎ brŒtj‰fhd 90 ehŸ m¿é¥ò foj¤ij 30.04.17-¡FŸ gadhëfS¡F tH§», mj‹ égu¤ij 15.5.2017-¡FŸ cW brŒÂl nf£L¡ bfhŸs¥gL»wJ. é©z¥g¤Â‹ ÛJ bga® kh‰w«, r®nt v© kh‰w« brŒa ÏayhJ. ÏJ 2017-18 M« M©o‰fhd étrha ä‹ Ïiz¥òfS¡fhd F¿p£lséš, rhjhuz K‹Dçik¡ F¿p£L¡FŸ ml§F«. M®. v°. cõh, jiyik¥ bgh¿ahs®/£lälš k‰W« tsika«. Ïiz¥ò - bga® g£oaš (215 v©z§fŸ) 2017-18 List - Physically Challenged Category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 Tmy.S.Santhi THIRUP 53/2015-16 08-07-2015 SF.No. 276/19, S.V.Mangalam PATHUR village, CL : 5 HP 2 Thiru.P.Suresh Periyakulam 046/2013-14 05-06-2013 SF.No.873/3B, Kadamalaikundu village, CL : 5 HP 3 Thiru.P.Ganesan Musiri 086/13-14 15-07-2013 SF.No.184/3, T.Pettai village, CL : 5 HP 4 Thiru.V.Jaykumar, Musiri 217/2014-15 16-03-2015 SF.No.884B/2C, Pillapalayam village, CL : 10 HP 5 Thiru.Raman 131 10-01-2011 SF.No.388/2A1, Keelmuttukur village, CL : 7.5 HP 6 Thiru.M.Dharuman SHOLINGUR 2720813369 05-08-2013 SF.No.44/3A, Aayal village, CL : 5 HP 7 Thiru.V.Kanakaraj EE/Pollachi 217/Cbe/ 28-02-2011 SF.No.61/2A2A, Thimmankutthu village, 2010-11 CL : 5 HP 8 Thiru.Rajendran WEST.TV. 321 15-12-2010 SF.No. 204/2, Rayandapuram village, MALAI CL : 5 HP 9 Thiru.Perumal EAST-T.V. 280 26-12-2014 SF.No. 330/3, Boodhamangalam MALAI village, CL : 5 HP 10 Thiru.P.John Walter MANAPPARAI 45/2015-16 08-06-2015 SF.No.249/2, V.Periyapatti village, CL : 7.5 HP 11 Thiru.Murugan HARUR 102/2015-16 04-08-2015 SF.No. 25/3B1, Kokkarapatti village, CL : 5 HP 68

12 Thiru.Raja HARUR 251/2011-12 05-09-2011 SF.No. 214/3C, Thadhampatti village, CL : 5 HP 13 Selvi.N.Manimekalai Thuraiyur 073/2015-16 10-12-2015 SF.No. 209/5, T.Renganathapuram village, CL:10 HP 2017-18 list - ST category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 Thiru.Andi KALLAKURICHI 547 - F / 17-02-2011 SF.No. 17/6B, Nochimedu village, 2010-11 CL : 5 HP 2 Thiru.Velli KALLAKURICHI 547-H/ 17-02-2011 SF.No.28/1, Nochimedu village, 2010-11 CL : 5 HP 3 Thiru.Annamalai HARUR 016/ 20-04-2015 SF.No.72/4A, S.Thadhampatti 2015-16 village, CL : 5 HP 4 Thiru.Kanagaraj HARUR 452/ 06-02-2012 SF.No. 6/2D, Thekkanampatti 2011-12 village, CL : 5 HP 5 Thiru.Annappan HARUR 77/2015-16 29-06-2015 SF.No. 22/3C, Velanur village, CL: 7.5 HP 6 Tmy. Panchalai HARUR 223/ 17-02-2015 SF.No.175/1D, Velanur village, 2014-15 CL : 5 HP 7 Thiru.Subramani, HARUR 254/ 28-03-2013 SF.No.293/4, Velanur village, 2012-13 CL: 5 HP 8 Tmy.Kasiammal HARUR 939/ 02-03-2011 SF.No. 226/7B, Velanur village, 2010-11 CL : 5 HP 9 Thiru.A.Palani EAST/SALEM A 300/ 29-03-2014 SF.No.71/2B, Maramangalam YED/13-14 village, CL : 7.5 HP 10 Thiru.Andi HARUR 15/ 18-04-2011 SF.No.7/2H, Velanur village, 2011-12 CL: 5 HP 11 Thiru.Chinnathambi HARUR 15/ 22-04-2014 SF No. 78/2E, Sidling village, 2014-15 CL : 5 HP 12 Thiru.Kuppan HARUR 177/ 04-12-2014 SF No. 61/18, Sidling village, 2014-15 CL : 5 HP 13 Tmy.Vadiviyammal HARUR 224/ 17-02-2015 SF No. 8/1A, Sidling village, 2014-15 CL : 5 HP 14 Thiru.Theethaan HARUR 25/ 05-05-2014 SF No. 75/1A, Sidling village, 2014-15 CL : 5 HP 15 Thiru.Jadaiyan HARUR 102/ 20-06-2011 SF.No.67/2A, Velanur village, 2010-11 CL: 5 HP 16 Thiru.Palanisamy VALAPADY 306 06-03-2015 SF.No. 76/1, Aladipatti village, CL : 5 HP 17 Tmy.Raamayee VALAPADY 188 01-08-2012 SF.No. 141/4, Kunnur village, CL : 7.5 HP 18 Tmy.Pappayee VALAPADY 186 01-08-2012 SF.No. 141/2B, Kunnur village, CL : 7.5 HP 19 Thiru.A.Mayakannan HARUR 103/ 20-06-2011 SF.No. 2/3B, Malaithaangi village, 2011-12 CL : 5 HP 69 20 Tmy.S.Unnamalai, HARUR 154/ 14-10-2015 SF.No.12/4, Velanur village, 2015-16 CL : 5 HP 21 Thiru.Dharuman HARUR 451/ 06-02-2012 SF.No.51/4, Andipatti village, 2011-12 CL : 5 HP 22 Thiru.Kolandaiyan HARUR 443/2010-11 10-11-2010 SF.No.105/4A, Velanur village, CL : 5 HP 23 Thiru.Mookkan HARUR 153/2015-16 14-10-2015 SF.No. 104/2B, Velanur village, CL : 5 HP 24 Thiru.Venkatraman HARUR 643/2010-11 22-12-2010 SF.No. 281/4, Velanur village, CL : 5 HP 2017-18 List - Widow category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 Tmy.A.Kaleeswari EE/Udumalpet 309/2011-12 19-09-2011 SF.No.26/1A, Vesaipatti village, CL : 10 HP 2 B.Mamtha KRISHNAGIRI 111 26-07-2013 SF.No. 39/2B, Soolagiri village, CL: 7.5 HP 3 Tmy.M.Nagajothi Periyakulam 90/2010-11 01-07-2010 SF.No.386/1, Kadamalaikundu village, CL : 5 HP 4 Tmy.C.Thangammal Periyakulam 008/2015-16 20-04-2015 SF.No. 469/4, Theppampatti village, CL : 5 HP 5 Tmy.S.Thangam Periyakulam 069/2015-16 24-08-2015 SF.No.435/3B, Mayiladumparai village, CL : 7.5 HP 6 Tmy.Alagar CHENGAM 169 29-11-2011 SF.No. 3/3, Kallathur village, CL : 5 HP 7 Tmy.Sakuntala HARUR 99/2006-07 09-08-2006 SF.No.8/1A3, Kattur village, CL : 5 HP 8 Tmy.K.Sundarambal Lalgudi 214 11-01-2007 SF.No.53/6, Mettupatti village, CL : 7.5 HP 9 Tmy.P.Pudumalar 88/2015-16 18-09-2015 SF.No. 79/2B1, Edyarempethi village, CL: 10 HP 10 Tmy.P.Thangapillai Periyakulam 272/2010-11 18-10-2010 SF.No.388/3, Kadamalaikundu village, CL : 5 HP 11 Tmy.K.Indirani Lalgudi 13 20-06-2014 SF.No. 17/4, Poovalur (East) village, CL : 7.5 HP 12 Tmy.V.Gandhimathi Lalgudi 27 28-10-2015 SF.No.79/1B, (Poovalur West) village, CL : 7.5 HP 13 Tmy.Kasthuri HARUR 106/2015-16 06-08-2015 SF.No. 78/2A, Melanur village, CL : 5 HP 14 Tmy.Anandhiammal KALLAKURICHI 40/2015-16 13-05-2015 SF.No.120/12, Rayappanur village, CL : 7.5 HP 15 Tmy.Ramutthai Periyakulam 096/2013-14 03-08-2013 SF.No.295/2C, Pulimonkombai village, CL : 5 HP 16 Tmy.Rajeswari Srirangam 12 21-07-2015 SF.No.178/12, Aaykudi village, CL : 5 HP 70

17 Tmy.J.Ranjitham Namakkal V 091/ 13-07-2015 SF.No. 249/5, Minnampalli village, 2015-16 CL : 5 HP 18 Tmy.Visalakshi THIRUTTANI D. 118/ 05-08-2015 SF.No. 29/3B, Satrunjeyapuram, 2015-16 CL : 7.5 HP 19 Tmy.M.Thamarai EASTMADURAI M.E. 249/ 08-12-2015 SF.No.198/3, Veppadappu village, kumari 15-16 CL : 5 HP 2017-18 List - Serving Para Military category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 Thiru.N.Ramasay SANKARAN 008/2015-16 30-04-2015 SF.No. 1149/13 B, Thenmalai I KOVIL village, CL : 5 HP 2 Thiru.S.Anbukkarasu KALLAKURICHI 290/2013-14 29-01-2014 SF.No.56/5A, Maravanatham village, CL : 7.5 HP 3 Tmy.Mariyatthal DHARMAPURI DED 343/14 18-12-2014 SF.No.296/2, Konanginayak kanahalli village, CL:5HP 4 Thiru.R.Sasikumar Pudukkottai 143 04-09-2006 SF.No.22-1A2, Veeradipatti village, CL : 15 HP 5 Thiru.S.AshokKumar TIRUMANGALAM 031/15-16 04-08-2015 SF.No.70/3, Sowdarpatti Bit 1 village, CL: 5 HP 6 Thiru.D.Govindarajan THANJAVUR 50/2004-05 11-10-2004 SF.No. 111/4, Rajagiri village, CL : 7.5 HP 7 Thiru.P.Manivel ORATHANADU 75/2011-12 20-06-2011 SF.No. 49/11 B, Ponnapur East, CL : 12.5 HP 2017-18 List - Ex-Serviceman Category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 Tmt.Kala Ariyalur 337 12-01-2015 SF.No.71/3B, Koovathur (north) village, CL : 20 HP 2 Ex.No.14525226P/ Ariyalur 163 13-10-2015 SF.No.106/5A, Piranchery village, Hav, K.Rengasamy CL : 20 HP 3 Ex.No.6391344N/ Ariyalur 151 29-09-2015 SF.No.273/8B, Pappakudi South Hav, K.Velmurugan village, CL : 15 HP 4 Ex.No.168249K/ Ariyalur 109 25-08-2015 SF.No.455/7B, Kundaveli East POR, R.Baskar village, CL : 20 HP 5 Ex.No.14634376F/ Ariyalur 96 13-08-2015 SF.No.102/6, Kandirathitham Nk, K.Maniselvam village, CL : 7.5 HP 6 Ex.No.2573629H/ Perambalur 198/ 15-09-2011 SF.No.209/6, Keezha Puliyur Hav, R.Duraisamy 2011-12 (North)village, CL:5HP 7 Ex.No.697388G/ Ariyalur 321 09-01-2015 SF.No.92/7A,Aasaveeran kudikadu Sgt, R.Thiyagarajan village,CL:10HP 8 Ex.No.14635988L/ Ariyalur 202 22-12-2015 SF.No.276/11, Killimangalam Hav, R.Velsamy village, CL : 7.5 HP 9 Ex.No.15121675 P/ Ariyalur 994 28-02-2005 SF.No.561/5A2, Wenmankondan Hav, T.Veerappan (East) village,CL:15HP 10 Tmt.Indirani SOUTH/ 037/ SF.No.255/1, V.S.Kottai village, DINDIGUL 2014-15 11-04-2014 CL : 7.5 HP 71

11 Ex.No.14806557A/ NORTH/ 49 14-07-2015 SF.No.799/2C2, Gurunatha- Hav, N.Chinnadurai DINDIGUL nayakkanur village,CL:7.5HP 12 Ex.No.2789643H/ PALANI 162/ 07-11-2015 SF.No.191/4, Dasaripatti village, Hav, B.Kalidass 2015-16 CL : 5HP 13 Ex.No.2598277F/ TENKASI 177/ 24-11-2014 SF.No.102/1, Puliyarai village, Hav, S.Ramalingam 2014-15 CL : 5 HP 14 Tmt.M.Logambal Keeranoor 3 06-04-2015 SF.No.173/19B, Rajagiri village, CL:5HP 15 Ex.No.Jc206952A URBAN/ 128/ SF.No.276/A4B, Velliyanai village, Sub/Hony Capt, 2014-15 24-02-2015 CL : 5 HP R.Jaganathan 16 Ex.No.1241127X/ Musiri 174/ 11-11-2013 SF.No.221/1C, Thinnakonam Hav, P.Ramar 2013-14 village, CL : 3 HP 17 Tmy.S.Padmavathi Omalur 002/ 04-04-2013 SF.No.624/2A, Kammampatti 2013-14 village, CL : 7.5 HP 18 Tmy.V.Poongkodi DHARMAPURI 78 21-05-2014 SF.No.90/1D, Nallampalli village, CL : 5 HP 19 Tmt.R.Kamatchi 027 (TVR) 01-10-2015 SF.No.153/6, Nallore village, CL : 5 HP 20 Ex.No.1367710Y/ North/ Kum- 16-06-2014 SF.No.1/1, Thippirajapuram, Hav, S.Rajasekaran Kumbakonam North 055 CL : 7.5 HP 21 Tmy.R.Selvarani ORATHANADU 31/2015-16 15-06-2015 SF.No.253/4A, Keezhulur village, CL : 15 HP 22 Ex.No.1237613X/ North/ Kum- SF.No. 21/1, Narasinganpettai Nk, K.Balakrishnan Kumbakonam North -017 25-05-2015 village, CL : 5 HP 23 Tmt.Mangayarkarasi ORATHANADU 63/2000-01 29-05-2000 SF.No.290/2A,Ponnappur Keezh pathi village,CL:5HP 24 Ex.No.13920528P/ North/ Kum- SF.No.360/1, Manjamalli village, Hav SKT, Kumbakonam North-131 25-11-2014 CL : 7.5 HP K.Mahalingam 25 Ex.No.146296 T/ Keeranoor 66 06-11-2015 SF.No.351/1, Neer Pazhani village, CHELR, CL : 5 HP A.Muhamadhu Zakariya 26 Thiru.S.Kumar TIRUKOILUR 228 09-10-2013 SF.No.86/10B4, T.Mudiyanur village, CL: 5 HP 27 Thiru.E.Saravanan TIRUKOILUR 208 08-10-2014 SF.No.86/1A, Anthiyur village, CL: 7.5 HP. 28 Thiru.K.Manickam, KULITHALAI 299 28-10-2013 SF.No. 519/5, Pappakapatti, Ex.No.Jc 440157 CL - 7.5 HP W/Sub 29 Thiru.N.Palani, SRIVILLI- 109/ SF.No. 1149/1B2, Vazhaikulam Ex.No.14312534/Nk PUTHUR 2010-11 18-02-2011 village, CL : 5 HP 30 Thiru.B.Jeevanandam, Theni 054/ 12-09-2014 SF.No.190/4, Kottakudi village, Ex.No.14224326 P/Nk 2014-15 C.L. 7.5 HP 31 Tmt.T.Jayalakshmi HOSUR 301 09-11-2012 SF.No.71/1, Punugenthotti village, C.L. 7.5 HP 72

32 Thiru.T.Venkatesan, ARNI 50 07-06-2013 SF.No. 58/6, Kolathur village, Ex.No.6314585/ C.L : 5 HP Sigmn 33 Thiru.R.Ravi, CHENGAM 96 01-09-2014 SF.No.9/1B2, Kayampattu village, Ex.No.6927884 H CL : 5 HP 34 Tmt.P.Kamala Chinnamaur 136/ 11-12-2012 SF No. 1329/3, Pannaipuram 2012-13 village, C.L : 7.5 HP 35 Thiru.G.Vijayan, POCHAMPALLI 367/ 19-03-2015 SF.No. 249/3A, Kammampalli Ex.No.15139386 H 2014-15 village, 10 HP 36 Thiru.Srinivasa, KRISHNAGIRI 500 27-03-2015 SF.No.89/4, Poothimutlu village, Ex.No.14383465/ C.L : 7.5 HP Hav 37 Thiru.A.Kamatchi, SAMAYANALLUR 052/ 23-08-2013 SF. No. 180/5A5, Alagapuri village, Ex.No.081970 2013-14 CL : 5 HP Y/CPO 38 Thiru.M.Pandiyan, SANKARANKOVIL 070/ 10-10-2012 SF.No.182/1A, Pazhankottai village Ex.No.615162/CPL 2012-13 39 Thiru.R.Kalimuthu, Chinnamaur 024/ 21-04-2014 SF.No. 948/2, Kamayagoundan- Ex.No.097549 B/LS 2014-15 patty village, CL: 5 HP 40 Thiru.K.Esakki, KADAYANALLUR 100/ 05-09-2014 SF.No. 177/1, Varmelazhagiyan Ex.No.15366013 2014-15 village, 5 HP H/Sigmn 41 Thiru.S.Moses, Lalgudi 24 28-07-2014 SF No. 27/8, Seshasamuthiram Ex.No.6457927 Y/Nk village, 7.5 HP 42 Thiru.S.Venkatesan, CHETPET 68 02-12-2014 SF.No. 372/4, Raghunathasa- Ex.No.3990640 muthiram, CL : 3 HP F/Hav/H Nb/Sub 43 Thiru.V.Vinayagam, ARNI 239 31-01-2014 SF.No.360/4C, Thuringikuppam Ex.No.15375569 village, CL : 5 HP N/CHM 44 Thiru.M.Muniappan, KRISHNAGIRI 395 21-01-2015 SF.No.446/1L, Marandapalli Ex.No.1323179/Spr village, CL : 7.5 HP 45 Thiru.G.Selvarajan, Mettupalayam 18/2014-15 16-05-2014 SF.No.513/7, Kemmarampalayam Ex.No.15375842 village X/Nk 46 Thiru.S.Rajendran, Ariyalur 80 19-05-2008 SF.No.28/1 A, Pitchanur village Ex.No.1352295/Spr 47 Thiru.R.Shan- 25 26-05-2015 SF.No.47/5D, Vallampadugai mugasundaram, village, CL : 5 HP Ex.No.1246001/ Gnr (OPR) 48 Tmt.K.Amudha THIRUTTANI D 24/ 25-04-2015 SF.No.87/2 B, Kakkalur village, 2015-16 CL : 5 HP 49 Thiru.K.Palani, THIRUTTANI D 80/ 18-06-2015 SF No. 130/7, Veeramangalam JC 307420 F/Sub 2015-16 village 50 Thiru.M.Muniraju, GUDIYATTAM 29/2010-11 24-06-2010 SF.No.590/7A, Veerichettipalli Ex.No.1383023 village M/Hav/H/Nb Sub 73

51 Thiru.C.Jagannathan, PALLIKONDA 005/ 11-04-2014 SF.No.251/2B1B, Odukathur Ex.No.1141693 Hav 2014-15 village 52 Thiru.S.Mohan, VELLORE 4005 23-02-2015 SF.No.517/4D, Kammasa- Ex.No.14595845 muthiram village A/Hony /Hav 53 Thiru.M.Murugesan, Ex.No.14419592/Hav KRISHNAGIRI 15 17-04-2015 SF.No.178/1A2, Malayandahally village, CL : 7.5 HP 54 Tmt.Ananthalakshmi KRISHNAGIRI 485 17-03-2015 SF.No. 111/2, Marandapalli village, CL : 7.5 HP 55 Thiru.P.Govindaraj, POCHAMPALLI 381/ 26-03-2015 SF.No. 89/2A, Chinnamatarapalli Ex.No.13873124/Hav 2014-15 village, CL: 7.5HP 56 Thiru.S.Gangadharan, 007/ 28-04-2014 SF.No. 99/3 B, Parithiyur village, Jc 207537 L/Sub 2014-15 CL : 7.5 HP 57 Thiru.T.Paulraj, Periyakulam 158/ 25-10-2011 SF.No.2049/2A, Mayiladumparai, Ex.No.15393274 A/ Nk 2011-12 CL : 5 HP 58 Thiru.C.Chinnappan, GUDIYATTAM 58/2011-12 14-09-2011 SF.No.20/1A2, Varadareddipalli Ex.No.1376825 village N/Hony Nb Sub 59 Thiru.A.Adhimoolam, SAMAYANALLUR 103/ 13-08-2014 SF.No.21/1, Pettai village, Ex.No.142385173/Nk 2014-15 CL : 5 HP 60 Thiru.M.Ganesan, ATTUR 19/ 18-05-2015 SF.No.649/3, Naduvalur North Ex.No.6464943 Y/Nk 2015-16 village 61 Thiru.M.Muthusamy, Omalur 60 09-06-2014 SF.No.198/2B2, Dharapuram Ex.No. 8027570/Nk 62 Thiru.A.Aruldoss, CHIDAMBARAM 26 03-05-2014 SF.No.244/4C, Thethampattu Ex.No.1045281 H/Hav village, CL : 20 HP 63 Thiru.R.Subramanian MANAMADURAI 144/ 07-02-2015 SF.No.106/1C, Kannamangalam Ex.No.8370212 2014-15 village, CL : 5 HP Y/Sep 64 Thiru.L.Kumaran, Periyakulam 156/ 11-11-2014 SF.No.1255 B, Melmangalam Bit I Ex.No.169382 2014-15 village, CL : 5 HP K/POR 65 Tmt.Thangaponnu Srirangam 34 23-10-2013 SF.No.230/4, Vengaimandalam village 66 Thiru.V.Nethaji, Mannargudi 75/ 02-09-2014 SF.No.217/5, Perugavazhanthan II Ex.No.2569784 2014-15 village, CL: 5 HP M/Nk 67 Thiru.G.Parthiban, DHARMAPURI DED 024/ 21-04-2015 SF.No.678/3, Naganoor village, Ex.No.14461857 15-16 CL : 5 HP N/Nk 68 Tmt.Amudha PALACODE 411 13-02-2012 SF.No.8/A,Onnappagoundanahalli village, CL : 5 HP 69 Thiru.M.Jabathas, SRIVILLIPUTHUR 02/ 01-04-2014 SF.No.1264, V.Pudupatti village Ex.No.6384047 2014-15 X/Nk 74

70 Thiru.C.Annamalai, GINGEE 35 27-04-2015 SF.No.268/3A7, Thayanur village, Ex.No.2564888/Sep CL : 5 HP 71 Thiru.L.Arockia- TIRUKOILUR 64 02-03-2009 SF.No. 14/8, Koluntharampattu nathan, Ex.No. village, CL : 5 HP 1064071 Y/LD 72 Thiru.M.Gothandara- TINDIVANAM 294 16-12-2014 SF.No.212/2B, Mylam village, man, Ex.No. CL : 5 HP 14307568 W/Nk 73 Thiru.K.Murugan, WEST.TV.MALAI 352 20-03-2015 SF.No.12/6B, Devamanpattu Ex.No.1492124 W/Spr village, CL : 5 HP 74 Thiru.P.Narayanan, CHEYYAR 832 15-05-2013 SF.No.496/3K, Alividaithangi Ex.No.2562130/Sep village, CL : 7.5 HP 75 Thiru.R.Karunakaran,THIRUPPATHUR 219/ 02.01.2014 SF.No.378/1B, Poolangurichi Ex.No.707944 F/SGT 2013-14 village, CL : 5 HP 76 Ex.No.14402086 KATPADI 10 02-05-2014 SF.No.16/10A, Melmayal village, M/L/NK R.Selvaraj 77 Ex.No.14459898/ KATPADI 66 06-09-2014 SF.No.165/9C2, Machanur village NK, M.Mani 78 Ex.No.15308557m/ P.Velur EE/PV/ 06-07-2015 SF.No.296/1, .Goundampalayam, Ract,P.S.Girisankar A103 CL: 7.5 HP 79 Ex.No.1382268/NK, Aruppukottai 6203 13-08-2012 78/2B, Mettugundu. Thimme Reddi 80 Ex.No.14264154/NK, EAST-T.V.MALAI 94 01-06-2015 110/13D,Sellankuppam R.Sundaramurthy CL: 5 HP 81 Ex.No.749431R/Sgt, TIRUMANGALAM 49 31-07-2014 377/1, Vaiyur village,CL: 5 HP R.Saran Singh 82 Ex.No.1077640A/ TIRUPATTUR 4860 18-06-2001 310/4, Thathavalli village, ALD, C.Selvam, 83 Ex.No. 15100290 KATPADI 12 12-04-2004 SF.No.254, Latheri village K/Sep Thiru.V.Guna- sekaran 84 Ex.No.Jc 367969 PALLIKONDA 006/ 02-05-2015 SF.No.53/4, Madayapattu village Y/Sub Maj, 2015-16 Thiru.S.Gurunathan 85 Ex.No.15300964A/ KATPADI 82 26-03-2012 SF.No.255/2B3A, Chinna Nk, Thiru.V.Karuna- village moorhy 86 Tmy.J.Ponnuthai Periyakulam 244/ 11-03-2013 SF.No.348/6, E.Pudukottai village, 2012-13 CL : 5 HP 87 Ex.No.14487852 PATTUKKOTTAI 170/ 03-10-2011 SF.No.523/1, Thuvarankuruchi M/Hav, 2011-12 (South) village, CL : Thiru.M.Selvaraj 88 Ex.No.242158H/CPL, Namakkal V080/ 19-06-2015 SF.No.46/1, Vagurampatti, R.K.Ramasamy 2015-16 CL: 5 HP 89 Ex.No.2575108N/NK, RURAL- 029/ 11-09-2014 SF.No.336/3,Karunkulam Village Thiru.V.Ganapathy TUTICORIN 2014-15 75

90 Ex.No.1355410L/NK, KOVILPATTI 040/ 21-08-2014 Sf.No.30/7, Meithalaivan M.Karuppusamy 2014-15 patti Village 91 Ex.No.1357441K/NK, KRISHNAGIRI 495 27-03-2015 Sf.No.493/1A,Kammampalli C.Muniappan village,CL:7.5 HP 92 Ex.No.2569675/Sep. KRISHNAGIRI 308 08-12-2004 Sf.No.25/3, Bellampatti village, P.M.Krishnan CL:5HP 93 Ex.No.6641808H/ PATTUKKOTTAI 68/2011-12 30-06-2011 Sf.No.123A/18, Muthakurichi R.Muthukannu Village,CL:7.5HP 94 Ex.No.8029841 Periyakulam 86/ 31-08-2012 Sf.No.1225/2, Mayiladumparai H/NK, T.Samykalai 2012-13 village,CL:5 HP 95 Ex.No.14237099/Nk, POCHAMPALLI 230/ 29-01-2014 SF.No. 478/3B, Sigaralapalli M.Veerapandian 2013-14 village, CL : 5 HP 96 Tmt.Geetha KRISHNAGIRI 6 08-04-2015 SF.No.28/5, Kondepalli village, CL: 5 HP 97 Ex.No.6472255/ KRISHNAGIRI 324 20-12-2014 SF.No.100/11 B, Bikkanapalli Hav, Thimmarayanvillage, CL : 5 HP 98 Ex.No.1333356H/ KRISHNAGIRI 78 06-05-2015 325/3A, Agasipally,CL:5 HP spr, K.Veerasamy 99 Ex.No.1289035/ KRISHNAGIRI 452 04-03-2015 Sf.No.53/1E,Gangojikothur V&P Gnr, K.Kolalappa CL:7.5 HP 100 Ex.No.10359702M/ KRISHNAGIRI 391/14-15 28-03-2015 Sf.No.253/8, Kudimenahalli, Hav, S.Vivekanandan CL: 7.5 HP 101 Ex.No.6461656 /NK, KRISHNAGIRI 153 15-07-2015 Sf.No.89/2, Marandappalli village, Thirupathi CL: 7.5 HP 102 Ex.No.13963598F/Hav, SANKARAN- PTG 034/ 10-10-2014 Sf.No.283, Vayali village, K.Soundarapandian KOVIL 14-15 103 Ex.No.14802853N/ ARNI 78 14-07-2015 Sf.No.344/5, Pushpagiri village Hav, A.Venkatesan. 104 Ex.No.2564863X/ KULITHALAI 72/15-16 14-09-2015 SF.No.286/1, Karuppathur village, Hav, A.Shoukath Ali CL : 5 HP 105 Ex.No.14354589X/ Periyakulam 077/ 15-09-2015 SF.No.175/3, Kothapathy rajathani Nk, P.VadivelGroup, 2015-16 CL:7.5 HP 106 Ex.No.15311490K/ Chinnamaur 066/ 25-07-2015 SF.No.1215/3, Kombai West Nk, 2015-16 K.Azhagu Pandi village, CL : 7.5 HP 107 Ex.No.2595657P/Nk, KATPADI 15 14-05-2015 SF.No.31/5A, Karasamangalam S.Saravanan, village, CL : 7.5 HP 108 Tmt.P.Palaniammal Keeranoor 290/ 10-01-2014 SF.No.12/6, Lakshmananpatti 2014-15 village, CL : 3 HP 109 Ex.No.Jc 194546L/ Thiruvarur 692/ 03-03-2004 SF.No.102/2, Maruvathur village, Sub/Hony/Capt 2003-04 CL : 7.5 HP P.Nagarajan 110 Ex.No.14233619 Nk, POCHAMPALLI 082/ 17-07-2010 SF.No.137/2, Chinnamattarapalli K.Veerapathiran, 2010-11 village, CL : 7.5 76

111 Tmt.Jayapriya Periyakulam 226/ 11-02-2014 SF.No.806/2, Melmangalam Bit I 2013-14 village, CL : 3 HP 112 Ex.No.13899491H/ Chinnamaur 098/ 09-06-2010 SF.No.1270/1C, Mela Gudalor Nk, P.Muthu 2010-11 North village,CL:10HP 113 Ex.No.15313974H/ Chinnamaur 063/ 29-07-2011 SF.No.68/4, Kuchanur village, Nk/M.Jothimani 2011-12 CL: 10 HP 114 Ex.No.2593502F/Nk, Periyakulam 042/ 07-07-2006 SF.No.129/1, Theppampatti K.Muthukaruppiah, 2006-07 village, CL : 7.5 HP 115 Ex.No.14236010P/ Chinnamaur 126/ 26-10-2015 SF.No.1327/1, Kombai West Hav, P.Jayaraj 2015-16 village, CL : 10 HP 116 Ex.No.14616555Y/ Chinnamaur 126/ 28-11-2012 SF.No.655/1, Melagudaloor Nk, P.Murugan 2012-13 village, CL : 7.5 HP 117 Tmt.K.Ponnuthai RURAL - 146/ 28-10-2015 SF. No. 1892/7, Nk, TIRUNELVELI 2015-16 Gangaikondan village, CL : 5 HP 2017-18 List - Serving Soldier Category Sl. Name of the Division Application Date of SF.No. details No beneficiary Regn. No. Registration 1 No.2607549A. Periyakulam 167/ 10-02-2016 SF.No.1398/4B, Kadamalaigundu Nk, K.Raja 2015-16 village, CL : 7.5 HP 2 No.14651322W/ Ariyalur 85 29-07-2015 SF.No.77/12A, Sirukadambur Sep, S.Selvam village, CL : 10 HP 3 No.14447331W/ SOUTH/ 155/ SF.No.18A/3, Puthur village, Sep, R.Balakrishnan DINDIGUL 2014-15 21-05-2014 CL : 5 HP 4 No.Jc. 413630M/ Chinnamaur 214/2014- 23-12-2014 SF.No.119, Mela Gudalur village, Sub/Clk, J.Veera- 15 CL : 7.5 HP sekar 5 Thiru.R.Murugan, EAST-T.V.MALAI 410 17-02-2014 SF No. 35/5, Aradapattu village, 5 No.15320484 X/ HP Hav 6 Thiru.Anbil Dharma USILAMPATTY 037/ 22-06-2013 SF. No. 257/1, Pappinaickenpatti Kumarasamy, 2013-14 village, 5 HP No. 15209935 X/L/Nk 7 Thiru.K.V.Vijaya- THANJAVUR- 170/ 09-03-2015 SF.No.65-1E, kumar, Kollangarai No.15481919 A/LD O AND M 2014-15 village, CL : 15 HP, 8 Thiru.J.Mahalingam, GUDIYATTAM 36/2011-12 29-06-2011 SF.No.216/3, Kallapadi village, CL : No.15317807 K/Hav 5 HP 9 Thiru.K.Pugalenthi, THANJAVUR - 23/2015-16 20-05-2015 SF No. 108 A/10 B, Marungulam No.15155882 N/ O AND M village, 15 HP Gnr (GD) 10 Thiru.E.Vignesh, TIRUKOILUR 332 18-03-2015 SF. No. 52/9, T.Athipakkam village, No.16117725 N/Spr CL : 5 HP 11 Thiru.P.Velayutham, Pudukkottai 19 06-05-2015 SF.No.209/15 B, Kattunaval No.JC 383305 P/Nb Sub village, CL : 15 HP 12 Thiru.C.Kumar, KRISHNAGIRI 261 28-10-2014 SF.No. 307/2A, Kundharapalli No.15565298 X/LNk village, CL : 5 HP 77

13 Thiru.J.Gunaseka- Ariyalur 45 03-06-2015 SF No.41/1A1, Sreepuranthan (N) ran, No. 2688786 village, CL: 15 HP F/Nk 14 Thiru.K.Machak- KARAIKUDI 82/ 23-12-2014 SF.No.171/1, Vilangattur village, kalai,No.15330742 2014-15 CL : 3 HP A/Spr 15 Thiru.G.Gunase- Ariyalur 294 24-12-2014 SF.No.18 A/3, Ulliyakudi village, CL : karan, No.6935358 10 HP Y/Hav 16 No.14640975X/Nk/ Chinnamaur 037/ 27-06-2013 SF.No. 291/1A, Narayanadevenpatti Tech/(Comn), 2013-14 (South) CL: 10HP M.Jeyakumar 17 No.14651315A/ Ariyalur 85 01-07-2014 SF.No.90/1B, Pillichikuzhi village Sep, D.Karthikeyan 18 No.14936824A/ MANAMADU- 052/ 20-07-2015 SF.No.60/13, Ganapathiyenthal Sep, K.Sekar RAI 2015-16 village 19 No.14808970P/ VALLIYOOR 016/ 15-05-2015 SF.No.1246/4, Perungudi 1 village, Hav, M.Jayakumar 2015-16 CL : 5 HP 20 No. 15413701P/ Chinnamaur 037/ 23-05-2015 SF.No.542/6B, Seepalakottai LNK, R.Venkatraman 2015-16 village, CL : 7.5 HP 21 No.6948038/ DHARMAPURI DED 121/ 27-06-2014 SF.No.402/7A, Errabaiyanahalli Sep, V.Arul Kumar 2014-15 village, CL :7.5 HP 22 No.2611820 W/ PALACODE 311(09502- 28-02-2015 SF.No.140/4, Dindal village, CL : 5 Nk,P.Ravi 15158) HP 23 No.14649102Y/ Ariyalur 181 03-09-2014 SF.No.153/3, Keelamaaligai Hav, R.Rajavillage. 24 No.10359285/ KRISHNAGIRI 377 08-01-2015 SF.No.132/15, Ennegulpudur, CL : Sep, P.Selvam 5 HP 25 No.2596308/Hav, KRISHNAGIRI 486 18-03-2015 SF.No.36/4, Kurubarapalli village, G.Krishnan CL : 7.5 HP 26 No.14428992P/ SOUTH/ 560/ 02-02-2015 SF.No.1125/1,Ayyaloor village, Hav (GD), V.Sen- DINDIGUL 2014-15 CL : 5 HP thilvel 27 No.15153622K/ Periyakulam 061/ 13-08-2015 SF.No.690/1, Melmangalam Bit 1 Nk, K.Samayamuthu 2015-16 village, CL : 3 HP 28 No.15324010N/ North/Kum- KUM-North 15-06-2015 SF.No.345/6, Thandan Thottam LNk, R.Elamaran bakonam 023 village, CL : 7.5 HP 29 No.Jc 699752F/ Chinnamaur 046/ 17-06-2015 SF.No.125/2B2, Malliangapuram NbSub/Pharma 2015-16 village, CL : 10 HP M.Thangam 30 No.15328688Y/Nk, Mayiladuthurai 33 06-08-2014 SF.No.68/7, Kadalangudi village, V.Kathiravan CL : 7.5 HP 31 No. 14629660N HP POCHAMPALLI 226/ 31-12-2010 SF.No.757/4, Kendikampatti / Hav, J.Selvam 2010-11 village, CL: 5 32 No.15220423L/ KRISHNAGIRI 106 21-05-2015 SF.No.159/8B, Naralapalli village, LNk (OPR), CL : 7.5 HP D.Vijayakumar 78

33 No.15416255K/ USILAMPATTY 017/ 08-06-2015 SF.No.67/1B1A, Kethuvarpatti Sep, A.Prabu 2015-16 village, CL : 5 HP 34 No.14427446H/Nk TIRUKOILUR 32 18-05-2015 SF.No.143/5, Adhichanur village, (AFSO), S.Anthony- CL : 5 HP dass 35 No.15496102L/Sow, ULUNDURPET 138 26-07-2014 SF.No.231/12, Paiyur village, CL : P.Ramachandran 5 HP //True Copy// * * * Hydro – Kundah Generation Circle – Cleaning and Sweeping in and around Power House premises, IB road, Executive Engineer Bungalow Road and Inspection Bungalow care taker in Moyar Camp and routine cleaning of the trash rack at the main entrance of Moyar Fore Bay dam and LLP pipe line entrance trash rack for the period of 12 months from the date of Utilization - Administrative Approval-Accorded. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.33 Dated the 25th April 2017. 12-Chitthirai, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CE/Hydro’s note approved by the CMD/TANGEDCO dt. 24.04.2017. ----- PROCEEDINGS: Administrative approval is accorded for “Cleaning and sweeping in and around Moyar Power House premises, IB road, Executive Engineer Bungalow road, provision of Inspection Bungalow Care taker, routine cleaning of the trash rack at the main entrance of Moyar Fore Bay dam and LLP pipe line entrance trash rack for a period of 12 months from the date of utilization for the year 2017-18 for an amount of Rs.8,38,300/- (Gross & Nett) (Rupees Eight lakhs thirty eight thousand and three hundred only) including Service Tax @ 15% based on the PWD Schedule of rates for the year 2016-2017. (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * Hydro –Generation Circle Kundah – Cleaning, Sweeping and Maintenance of water supply and sanitation arrangement in the Camp and Power house area of Geddai, Parali and Pillur for a period of one year from the date of utilisation - Administrative Approval-Accorded. Technical Branch (Rt.) CMD TANGEDCO Proceedings No.34 Dated the 25th April 2017. 12-Chitthirai, Heyvilambi varudam, Thiruvalluvar Aandu 2048. READ: 79

CE/Hydro’s note approved by the CMD/TANGEDCO dt. 24.04.2017. ----- PROCEEDINGS: Administrative approval is accorded for the following works including Service Tax @ 15% based on the PWD Schedule of rates for the year 2016-2017. (i) Kundah Generation Circle – Cleaning and Sweeping in and around quarter’s area, cleaning the drains, disposing of debris, sullages, maintenance of camp water supply and maintenance of Geddai IB at Pegumpahalla Camp, Geddai for the period of one year from the date of utilization at an estimated cost of Rs.9,08,050/- (Gross & Nett) (Rupees Nine lakhs eight thousand and fifty only). (ii) Kundah Generation Circle – Cleaning and Sweeping in and around Power House-3 sanitation and drinking water supply arrangements and maintenance of I.B. at Parali Power House-3 camp for the period of one year from the date of utilization at an estimated cost of Rs.8,94,000/- (Gross & Nett) (Rupees Eight lakhs and ninety four thousand only). (iii) Kundah Generation Circle – Cleaning and sweeping around PH4 premises, sanitation and drinking water supply arrangement at Power House-4 Pillur camp for a period of one year from the date of utilization at an estimated cost of Rs.7,55,950/- (Gross & Nett) (Rupees Seven lakhs fifty five thousand nine hundred and fifty only). (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * Hydro – Erode Generation Circle – Bhavani Kattalai Barrage 3 Power House at Cholasiramani – Rectification works to the damages to the Crest, Piers and Apron portion to be taken up on top priority – In-Principle Approval-Accorded. Technical Branch (Rt.) CMD TANGEDCO Proceedings No.35 Dated the 25th April 2017. 12 - Chitthirai, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CE/Hydro’s note approved by the CMD/TANGEDCO dt. 24.04.2017. ----- PROCEEDINGS: In-Principle approval of CMD/ TANGEDCO is accorded for the following: (i) To take up the Rectification works to the damages caused to the civil structures of the Bhavani Kattalai Barrage 3 at Cholasiramani on top priority. 80

(ii) To include a tentative fund requirement of Rs.1 Crore in the Budget Estimate 2017-2018 under Revenue Expenditure Head as the above work has not been included in the Budget Estimate 2017-2018. (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose Chief Engineer/Hydro. * * * TANGEDCO – R-APDRP – Part-B works LOA No.892 Dt 17.04.2013 – “Survey, Design, Engineering, Manufacture, Supply, Erection, Testing, Commissioning of 11kV & 22 kV RMUS and associated materials” – Time extension for project Supply and Commissioning of RMUs due to constraints not attributable to M/s. L&T Ltd-Approval- Approval-Regarding. (TECHNICAL BRANCH) (Per.) CMD TANGEDCO Proceedings No.212 Dated the 25th April 2017. Chittirai 12, Heyvilambi Varudam, Thiruvalluvar Aandu 2048, READ: (1) Detailed Award of Contract No.892 dt.17.04.2013 (2) Chief Engineer/P&C’s Note approved by the CMD/ TANGEDCO on 01.4.2017. ----- PROCEEDINGS: Approval is hereby accorded for the proposal of the Chief Engineer/P&C/Chennai for extension of time towards execution of various packages of the LOA No.892 dated 17.04.2013 without levy of Liquidated damages to M/s.Larsen & Toubro Limited as detailed below in consideration of the reasons for delay in project execution that are found not due to the firm. For Packages: I&II (i.e. Chennai North & South Regions): i) Time extension is accorded for supply of RMUs and associated materials in respect of package-I as well as package-II as per the due dates proposed in table below batch wise, wherein the due date for last batch of materials is till 31.01.2015. Package-I (Chennai North): Package-I(Chennai South): Due date of Supply of materials Due date of Supply of materials As per original Effective As per original Effective after contract after time contract time extension extension For Batch-1 14.09.2013 14.09.2013 14.09.2013 14.09.2013 For Batch-2 14.10.2013 31.10.2013 14.10.2013 31.01.2014 For Batch-3 13.11.2013 30.04.2014 13.11.2013 31.08.2014 For Batch-4 13.12.2013 30.09.2014 13.12.2013 31.01.2015 For Batch-5 12.01.2014 31.01.2015 Not applicable. Not applicable. ii) Extension of time for work items for packages I to VII: Time extension is accorded on actual basis beyond the stipulated due dates in existing contract for commissioning of RMUs delayed due to non-availability of L.C or 81

Site constraints attributed to TANGEDCO. In any case the last date for commissioning of RMUs for packages I to VII is 30.09.2016. iii) General: Liquidated damages is applicable as per provision in the subject LOA for delivery of materials effected beyond the stipulated due dates consequent to time extension (By Order of the Chairman- cum - Managing Director/TANGEDCO) A. Panchalingam, Chief Engineer/Protection & Communication. * * * TANGEDCO – PUSHEP (3x50MW) – Pykara Ultimate Stage Hydro Electric Project – Construction of Access Tunnel, Tail race Tunnel, Pressure shaft, Power house Cavern, including Transformer Cavern, Cable shaft, Adits etc under Spn.No.SE/CD/1322 – Civil Suit No.654 of 2011 Filed by M/s. Karam Chand Thapar & Bros (Coal Sales) Ltd, Kolkata – against TANGEDCO – Posted for trial by Recording evidences of PW & DW commences before Additional Master Court-I formation of Core Committee and to engage of Senior counsel -Approval-Approval-Regarding. (Technical Branch) Per. CMD TANGEDCO Proceedings No.213 Dated the 26st April 2017. Chittirai 13, Heyvilambi Varudam, Thiruvalluvar Aandu 2048, READ: The Chief Engineer/Civil Designs note approved by the CMD/TANGEDCO Dated 24.04.2017. ----- PROCEEDINGS: Approval is hereby accorded for the following: a. Formation of Core Committee comprising of following Engineers who have executed the PUSHEP (3x50MW) work to counter the Civil Suit No.654 of 2011 Filed by M/s. Karam Chand Thapar & Bros (Coal Sales) Ltd, Kolkata claiming a stake amount of approximately Rs.9.25 Crores from TANGEDCO towards LD & withheld amount, Escalation charges and Interest on final bill amount etc. Sl. Name Designation No. i. Er. K.Gopal, SE/Civil/Hydro Project/Erode Chairman ii. Er.M.Thirumal,SE/Civil/MTPS/Stage-I/Mettur (then AEE/Civil/PUSHEP) Member iii. Er.T.Kailasam, AEE/Civil/TLC/Coimbatore, O/o SE/GCC/Coimbatore (then AE/Civil/PUHSEP) Member iv. Er.V.Vasu, AEE/Civil/TLC/Krisyhnagiri O/o SE/ GCC/Salem (then AE/Civil/PUHSEP) Member v. Er.C.Kumaran, EE/Civil/KPSHEP-7/Emarald, O/o SE/C/Hydro Project/Erode Convener & Member

B.B.6 (Apr 17) 82

b. To engage Senior Advocate Thiru.N.C.Ramesh, who has wide Knowledge and exposure on Hydro Project Court cases to file necessary counter, written statements argue and cross examine the witnesses before Hon’ble High Court of Madras in the forth coming Hearing of the above subject work case. c. The Chief Engineer/Project/Civil/Erode may be requested to closely pursue the activities of Core Committee for the above case in Co-ordination with Head Quarters till disposal of the case before Hon'ble High Court. (By Order of the Chairman- cum - Managing Director/TANGEDCO) C. Ramesh, Chief Engineer/Civil Designs. * * * TANGEDCO – MM - Procurement of certain materials hitherto dealt by Material Management wing - Proposal for decentralization - Approval Accorded. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.36 Dated the 27th April 2017. Chitthirai 14, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CMD/ TANGEDCO's approval dated 24.04.2017. ----- PROCEEDINGS: Approval is hereby accorded to decentralize the procurement of the following low value materials hitherto dealt by Materials Management wing. 1. 11 KV Pin Insulator 2. 22 KV Pin Insulator 3. 33 KV Pin Insulator 4. 11 KV PT Insulator 5. 22 KV Pin Insulator 6. 33 KV PT Insulator 7. 11 KV GI Pin 8. 22 KV GI Pin 9. 33 KV GI Pin 10. 11 KV AB Switches 11. 22 KV AB Switches 12. 11 KV 45 KN Strain Disc Insulator 13. Metal parts for 11 KV Disc (30 KN) 14. Metal parts for Dog & Racoon Conductor (36 KN) 15. 9 KV / 5KA Lightning Arrester 16. 18 KV / 5KA Lightning Arrester 17. 9 items of Line Materials 18. 1100 V, 4x240 sqmm LT UG Alu. XLPE Cable 19. 1100 V, 4x120 sqmm LT UG Alu. XLPE Cable 20. 1100 V, 4x25 sqmm LT UG Alu. PVC Cable 21. 1100 V, 2x16sqmm LT UG Alu. PVC Cable 83

Accordingly, the approval is accorded for the following: i. To procure above materials except LT UG Cables (item Nos.1 to 17) in all Distribution Circle/Region Levels for regular O&M works within their powers already delegated based on the estimate/scheme requirement adopting the Tamil Nadu Transparency in Tenders Act and Rules and its amendments. ii. To procure LT UG PVC & XLPE Cables mentioned above (item Nos.18 to 21) by Chief Engineers Distribution Regions within their powers based on the field requirement, especially for O&M works. iii. For large quantity procurement in respect of special schemes and other loan schemes, MM wing shall continue the procurement of the above materials. (By Order of the Chairman- cum - Managing Director) V. Gopalakrishnan, Chief Engineer/Material Management. * * * Electricity – Provision of one number 400KV, 125MVAr Bus Reactor along with associated equipments & accessories at Kayathar 400/230-110 KV substation - Administrative Approval - Accorded. (Technical Branch) (Per)CH.TANTRANSCO Proceedings No.101 Dated the 27th April 2017. Chitthirai 14, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CHAIRMAN's approval dated 20.04.2017. ----- PROCEEDINGS: 1. The Chairman, TANTRANSCO approves the proposal for provision of one number 400KV, 125MVAr Bus Reactor along with the relay panel, breaker and all other associated equipments & accessories at Kayathar 400 /230-110 KV substation at an estimated cost of Rs.9.924 Crores (Gross and Nett.) The detailed report and estimate are annexed to these proceedings. 2. The expenditure is chargeable to TANTRANSCO funds - Capital Expenditure - Tirunelveli Operation Circle -A/c code No.14.645. 3. By virtue of the provisions contained in sub-section (2) (a) of section 185 of the Electricity Act 2003, the Tamil Nadu Transmission Corporation Ltd being the State Transmission utility and successor entity of TNEB will exercise the powers of the Telegraph authority under the provision of section 164 of the Electricity Act,2003, which have already been conferred upon the Board under section 51 of the Indian Electricity Act,1910. 4. The work is to be taken up after ensuring necessary budget provision. (By Order of the Chairman) R.S. Usha, Chief Engineer/Planning & RC. 84

REPORT TO ACCOMPANY THE ESTIMATE This proposal envisages provision of one number 125MVAR, 400kV Bus Reactor with relay panel, breaker and all other associated equipments & accessories at Kayathar 400/230-110 KV substation at an estimated cost of Rs.9.924 Crores Gross and Nett. 2. NEED: 2.1 Kayathar 400KV substation is a vital wind substation in Tirunelveli Region. There are about 4 Nos. 400KV feeders, 8 Nos.230 KV feeders and 3 nos. 110KV feeders besides 2 Nos.400-230 KV,315 MVA Auto transformers, 1No. 400/110 KV, 200 MVA Auto transformer and sanctioned 2 Nos.400/110 KV, 200 MVA Auto transformers. 2.2 As per the Indian Electricity Grid code and CEA manual on Transmission planning criteria, the 400kV bus steady state voltage should be maintained as below: Nominal Voltage Maximum Minimum 400kV 420kV 380kV 2.3 In Kayathar 400/230-110 kV substation, 2x63 MVAr switchable line reactors are in service at Kayathar end in the Kayathar-Karaikudi 400 kV DC line. It has been observed by SRLDC that even with the availability of these line reactors, the bus voltage on the 400 kV side is found to be more than the permissible limit. Hence it has been suggested to provide a bus reactor at Kayathar 400 kV SS. 2.4 Based on the above, provision of a bus reactor with the capacity of 1x125 MVAr at Kayathar 400kV substation has been approved for reactive compensation in the 39th Standing Committee Meeting on Power System Planning for Southern Region. Hence, it is suggested to provide 1x125MVAR bus reactor at the existing Kayathar 400kV substation to control the over voltage. 2.5 It is also ascertained that adequate space is available at the switchyard of Kayathar 400 kV SS for provision of the reactor. 3. Details of work: Erection of one number 400KV, 125MVAr Bus reactor with Relay panel and all other associated equipments & necessary accessories at Kayathar 400 kV substation. 4. Estimated cost: 4.1 The estimated cost works out to Rs.9.924 Crores (Gross and Nett) and is based on the TANTRANSCO cost data for the year 2016-17. The detailed estimate is annexed. //True Copy// 85

ANNEXURE ESTIMATE FOR ERECTION OF 1 NO.400KV, 125MVAr BUS REACTOR & AUXILIARIES AT KAYATHAR 400 KV SUBSTATION. Sl. Description of work Rate in Amount No. Qty. lakhs Per in lakhs 1. 400 KV, 3150A, 63KA Outdoor SF6 Breaker without pre-insertion resistor including Control Switching Device with associated materials 1 42.457 Set 42.457 2. 400 KV, 3150A, 63KA 5 core single phase current Transformer with support structure, accessories and Junction box. 6 8.284 Each 49.704 3. 400 KV Lightning arrester with support structure 3 1.055 Each 3.165 4. 400KV,3150 Amps, 63KA, Horizontal Center Break Isolator with double earth blades including all accessories and elevating pipe structures 2 8.300 Each 16.600 5. 400 KV Reactor control and Relay panel 1 11.402 Each 11.402 6. 400 KV busbar, Moose conductor, All types of power connectors, Tension fitting clamps, Insulators & hardwares LS 25.000 7. Control cables & LT power cables including cable trays LS 20.000 8. Earthing, painting and yard lighting LS 5.000 9. Marshalling box 1 0.300 Each 0.300 10. Cost of equipments and materials 173.628 11. Contingencies 1% 1.736 12. Sub-Total 175.364 13. Labour and Transport 15% 26.305 14. Sub-Total 201.669 15. 125 MVAr, 400KV, Three phase Reactor with Nitrogen injection Fire protection system and On-line diagnostic monitoring system. 1 530.375 Each 530.375 16. Sub-Total 732.044 17. Establishment & Supervision charges 15% 109.807 18. Reactor foundation works, approach road, Cable duct, fencing, foot path, Yard leveling, filling, drainage and metal spreading LS 99.000 19. Testing & commissioning of the 400 KV Bus reactor relay panel including system integration with SAS 1 11.500 Each 11.500 20. 400KV Structure LS 40.000 21. Total (Gross & Nett) 992.351 Or say Rs. 9.924 Crores //True Copy// * * * 86

IT wing - Provision of VPNOBB connectivity to GCC, P&C and operation circles - extension of connectivity upto 18/07/2017 - Administrative Approval - Accorded. (Technical Branch) (Per) CH. TANTRANSCO Proceedings No.103 Dated the 28th April 2017. Chitthirai 15, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: Chairman note order dated 24.04.2017. ----- PROCEEDINGS: 1. After careful consideration, the Tamil Nadu Transmission Corporation Limited hereby approves the following proposal: The extension of connectivity from M/s BSNL to provide VPNOBB for about 64 locations of GCC, P&C, Operation circles and Head Quarters upto 18.07.2017 at an cost of Rs.26,08,982/- (Twenty six lakhs eight thousand and nine eighty two only) approximately is administratively approved. The expenditure is chargeable to TANTRANSCO - Funds Expenditure-Account Heads 10.911 and 10.910 respectively. (By Order of the Chairman) S. Santhi, Chief Engineer/Information Technology. * * * Hydro – Kundah Generation Circle - Cleaning, Sweeping and Maintenance of Water supply and Sanitation arrangements in the Kundah Upper Camp and Lower Camp - Administrative Approval Accorded. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.37 Dated the 29th April 2017. Chitthirai 14, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CE/Hydro's note approved by the CMD/ TANGEDCO dated 27.04.2017. ----- PROCEEDINGS: Administrative approval is accorded for the following works including Service Tax @ 15% based on the PWD Schedule of rates for the year 2016-2017. (i) Kundah Generation Circle - Cleaning and Sweeping in and around the quarters areas, maintenance of approach road to Weir, trash rack cleaning in Western Catchment I, West Varahapallam, East Varahapallam, Kattery Diversion Weir, cleaning the drains, disposing of debris, sullages and maintenance of drinking water supply arrangements and maintenance of garden at Kamaraj Part and Central Office premises, Maintenance of Kundah Inspection Bungalow at Kundah Upper Camp for a period of one year from the date of utilization at an estimated cost of Rs.11,22,900/- 87

(Gross & Nett) (Rupees Eleven lakhs twenty two thousand and nine hundred only) (ii) Kundah Generation Circle - Cleaning and Sweeping in and around the quarters area, Cleaning of Manholes, Septic Tank, Dustbins, disposing of garbages and maintenance of Drinking water supply etc., and allied works in Kundah Lower Camp for a period of one year from the date of utilization at an estimated cost of Rs.5,61,100/- (Gross & Nett) (Rupees Five lakhs sixty one thousand and one hundred only). (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * Hydro – Generation Circle Kundah - Cleaning and Sweeping and Maintenance of Water supply and Sanitation arrangements in the Camp and Power house area of Pykara, Singara and Glenmorgan for the period of one year from the date of utilization - Administrative Approval Accorded. (Technical Branch) (Rt.) CMD TANGEDCO Proceedings No.38 Dated the 29th April 2017. Chitthirai 14, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: CE/Hydro's note approved by the CMD/ TANGEDCO dated 27.04.2017. ----- PROCEEDINGS: Administrative approval is accorded for the following works including Service Tax @ 15% based on the PWD Schedule of rates for the year 2016-2017. (i) Kundah Generation Circle - Cleaning and Sweeping around the camp and IB premises, maintenance of sanitation and water supply arrangements at Pykara camp and maintenance of Inspection Bungalow at Pykara Dam for the period of one year from the date of utilization at an estimated cost of Rs.8,15,850/- (Gross & Nett) (Rupees Eight lakhs fifteen thousands eight hundred and fifty only). (ii) Kundah Generation Circle - Providing assistance for cleaning and sweeping in and around office, power house premises and sanitation work in Singara camp for the period of one year from the date of utilization at an estimated cost Rs.7,57,500/- (Gross & Nett) (Rupees Seven lakhs fifty seven thousand and five hundred only). (iii) Kundah Generation Circle - Cleaning and Sweeping around the camp and IB premises, maintenance of sanitation and water supply arrangements at Glenmorgan camp and removal of Hyacinth plants in the inter connecting channel in between the Old and new Forebay Dam for a period of one year from the date of utilization at an estimated cost of Rs.9,32,400/-(Gross & Nett) (Rupees Nine lakhs thirty two thousand and four hundred only). (By Order of the Chairman - cum - Managing Director) K. Subash Chandra Bose, Chief Engineer/Hydro. * * * 88

Research & Development - Implementation of Harmonics limits in Solar Power Generators (SPGs) / Wind Energy Generators (WEGs) - Formation of committee to discuss and arrive conclusive methodology for harmonics measurement - Approval - Accorded. (Technical Branch) (Per.) Proceedings (CMD TANGEDCO) No.219 Dated the 29th April 2017. Chitthirai 14, Heyvilambi Varudam, Thiruvalluvar Aandu 2048. READ: 1. Honourable TNERC Tariff order No.2 of 2016 dt.28.03.16. 2. Honourable TNERC Tariff order No.3 of 2016 dt.31.03.16. 3. CE/IC, R&D's note approved by CMD TANGEDCO dt.26.04.2017. ----- PROCEEDINGS: CMD/ TANGEDCO has approved the proposal for formation of committee with the following Convener and members from R&D, Commercial, MRT/NCES and Financial Wings, to discuss the problems and complexities to be encountered in the measurement of harmonics in SPGs / WEGs and to arrive conclusive methodology for harmonics measurements. The recommendation of the committee on the methodology for taking measurements shall be submitted to CMD for approval and subsequent implementation. Committee: Convener : Chief Engineer/IC,R&D Member : 1. Chief Engineer/Commercial 2. Chief Engineer /NCES 3. Chief Financial Controller/Revenue 4. Superintending Engineer/R&D 5. Superintending Engineer/Solar 6. Superintending Engineer/Commercial 7. Financial Controller/Revenue 8. Executive Engineer/Research & Lab 9. Executive Engineer/MRT/NCES/Tirunelveli 10. Executive Engineer/MRT/NCES/Udumalpet 11. Assistant Executive Engineer/R&D (By Order of the Chairman- cum - Managing Director/TANGEDCO) K. Surendran, Chief Engineer/Industrial Co-ordination, R&D. * * * INDEX

News & Notes (Part-I) 2 General Administration and Services (Part-II) 1) (Per.) CMD TANGEDCO Proceedings No.85, (BOSB) Dt.05.04.2017. 11 Establishment - TANGEDCO - "1x800 MW North Chennai Supercritical Thermal Power Project Stage-III" - Change of Technical Control - Orders - Issued. 2) Letter No.41777/A17/A171/2016-6, (BOSB) dated.05.04.2017. 11 TANGEDCO – Secretariat Branch – New Health Insurance Scheme, 2016 for the employee of Government Departments and other organizations – Empanelment of Accredited Hospitals – Approval of additional hospitals and inclusion of additional specialties based on the recommendations of the Accreditation Committee – Notified – Orders Issued – Communicated. 3) Memo(Per) No.10319/A22/A222/2017-3, (BOSB) dated 06.04.2017. 21 Establishment – TANGEDCO – Bifurcation of existing Office of Chief Engineer/ Projects/Chennai – Reallocation of works – Orders – Issued. 4) Memo (Per) No.18833/A22/A222/2017-1, (BOSB) dated.10.04.2017. 22 Establishment – TANGEDCO – Upgradation of one post of Deputy Financial Controller/ Power Purchase as Financial Controller/Power Purchase under the control of Chief Engineer/Private Power Projects/ Chennai – Cancellation - Orders – Issued. 5) Memo (Per) No.10319/A22/A222/2017-4, (BOSB) dated.10.04.2017. 22 Establishment – TANGEDCO – Bifurcation of existing Office of Chief Engineer/ Projects/Chennai by creating one post of Chief Engineer/ Electrical for ongoing and upcoming projects – Ratification - Orders – Issued. 6) (Per) CMD TANGEDCO Proceedings No.92, (BOSB) Dt.12.04.2017. 23 TANGEDCO – Mobile Phone Connections – Under Closed User Group Scheme – Provision of Data Package for the existing 28 Nos. CUG Sim Cards allotted for the Enforcement Wing – Orders – Issued. 7) (Per) FB TANGEDCO Proceedings No.6, (BOSB) Dt.15.04.2017. 24 TANGEDCO – Mettur Thermal Power Station-II (1x600MW) – Incentive Schemes – Sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus to the employees of Mettur Thermal Power Station-II - Orders – Issued. 8) (Per.) FB TANGEDCO Proceedings No.7, (BOSB) Dt.17.04.2017. 26 TANGEDCO – North Chennai Thermal Power Station-II (2x600MW) – Incentive Schemes – Sanction of Monthly Thermal Allowance and Annual Thermal Incentive Bonus to the employees of North Chennai Thermal Power Station- II – Orders - Issued. 9) (Per) CMD TANGEDCO Proceedings No.98 (BOSB) Dt.18.04.2017. 29 Establishment - TANGEDCO - Decommissioning of Ennore Thermal Power Station - Re-designation/Modification and abolition of certain posts in the Office of the Chief Engineer/Ennore Thermal Power Station, Chennai and attachment of modified post of Executive Engineer/Ennore Thermal Power Station 230KV Switch Yard along with incumbent to Superintending Engineer/ Chennai Electricity Distribution Circle/North - Order - Issued. 90 General Administration and Services (Contd...) Page No. 10) (Per) (CH)TANGEDCO Proceedings No.69 (Adm.Br.) Dt.20.04.2017. 30 Establishment - Court Case - Order dated 21.06.2016 in W.P. (MD) No.2603/ 2013 filed by Thiru.R.Pandian, Asst. Engineer (Suspension) of the then Thirumayam RECS - Absorption Orders Served - Proceedings Issued. 11) (Per.) CMD TANGEDCO Proceedings No.73, (Adm. Br.) Dt.24.04.2017. 31 Establishment - TANGEDCO - Review of staff pattern in 400 KV SS dual ratio of 400/230 -110 KV SS and GIS SS - Constitution of a high level committee to examine and fix for norms for 400 KV Sub-Stations in Operation circles for sanction of posts - Orders - Issued. 12) Memo. No.12350/A18/A182/2017-1, (BOSB) dt.24.04.2017. 32 TANGEDCO - Departmental Tests for the Officials of TANGEDCO held in May 2014 and November 2016 - Results declared - Amendments - Issued. 13) (Per.) FB TANGEDCO Proceedings No.8, (BOSB) Dt.25.04.2017. 33 ESTABLISHMENT - Tamil Nadu Generation and Distribution Corporation Limited - Secretariat Branch - Tamil Nadu Electricity Board Employees’ Conduct Regulations - Amendments to Tamil Nadu Electricity Board Employees’ Conduct Regulations to deal with certain contingencies - Issued. 14) (ãiy) jiyt® k‰W« nkyh©ik Ïa¡Fe®/jäœehL ä‹ c‰g¤Â k‰W« g»®khd fHf« brašKiw Miz v©.104, (brayf¡»is) ehŸ : 28-04-2017. 34 gofŸ - mféiy¥go - 01.01.2017 Kj‰bfh©L ca®¤j¥g£l mféiy¥go Åj« - Miz- btëæl¥gL»wJ. Finance (Part - III)

15) (Per) CH Proceedings No.6 (Accts.Br.) Dt.01.04.2017. 36 TANTRANSCO - Delegation of powers for Procurement/Works Contract to Superintending Engineers/Operation on par with Superintending Engineers/ GCC - Amendment communicated. 16) Memo.No.CFC/Rev/FC/DFC/R1/F.Honrm/D.280/2017, (Accts.Br.) dt.11.04.2017. 36 TANGEDCO - Low Tension services - Assessment, Collection and Remittances of C.C.Charges - services remain un-assessed Payment of Honorarium - Further extension upto 31.12.2017 - Orders issued. 17) (Per) F.B.TANGEDCO Proceeding No.7 (Accts.Br.) Dt.25.04.2017. 37 TANGEDCO - Filing of Income-tax returns to the Income-tax authorities - Complying with the provisions of Section 44AB of Income Tax Act 1961 for the year 2016-17 – Appointment of Tax Auditor - Regarding. 18) (Per.) CH. TANTRANSCO Proceedings No.7 (Accts.Br.) Dt.26.04.2017. 38 TANTRANSCO – Financial assistance of Rs.443.57Crores for Establishment of 7 Nos. For various works in Trichy, Thiruvalam, Salem and Villupuram Operation Circles, Tamil Nadu - sanctioned by Power Finance Corporation Ltd., (PFC Ltd.,) New Delhi – Acceptance of Loan – Approved by the Borrowing Committee – Orders Issued. 91 Technical (Contd...)(Part - IV) Page No.

19) (Per.) FB TANTRANSCO Proceedings No.11, (Techl.Br.) Dt.01.04.2017. 45 Specification No.T-1987 - Tender for supply and erection of 48 nos. 16 MVA, 110KV Class Power Transformers under rate contract - Commercial and Technical Bids opened - Analysis of Commercial and Technical Terms - Opening of price bids - Approval Accorded. 20) (Per) FB. TANTRANSCO Proceeding No.12, (Techl.Br.) Dt.01.04.2017. 46 Specification No. T-1988 – Tender for supply and erection of 13 nos. 25MVA, 110/33-22KV Power Transformers under rate contract – Commercial and Technical Bids opened – Analysis of Commercial and Technical Terms – Opening of price bids – Approval Accorded. 21) (Per.) FB. TANTRANSCO Proceeding No.13, (Techl.Br.) Dt.01.04.2017. 46 Specification No. T-1989 – Supply and erection of 40 nos. 8 MVA, 33/11 KV Power Transformers under rate contract – Tender opened - Analysis of Technical and Commercial Terms – Opening of price bids – Approval Accorded. 22) (Per) FB TANGEDCO Proceedings No.22 (Techl.Br.) Dt.01.04.2017. 48 CE/MM-Tender specification No.M.14/2015-16- Supply of energy meter test benches, CT and PT test systems and mobile van etc., and establishment of NABL accreditated stationary and mobile labs and getting accreditation from NABL - open tender under two part rate contract system - Placement of orders - Approvals Accorded. 23) (Per) FB TANGEDCO Proceedings No.23, (Techl.Br.) Dt.01.04.2017. 48 TANGEDCO - Coal handling Contract-P.O.48/15.05.2001 - Poclain Charges - Additional item in Schedule I & V in Wagon Manual Unloading Charges at Paradip port - Amendment of P.O.48/dated 15.02.2001 - Approval - Regarding. 24) Per (FB) TANGEDCO Board Proceedings No.24, (Techl.Br.) Dt.01.04.2017. 49 MTPS II -1x 600MW-Mechanical II-Fire Protection system-Electrical-Annual Maintenance Contract for Nitrogen Injection Fire Prevention and Fire Extinguishing system for Power Transformers (5 Nos) to M/s. Natesan Engineering Contractor, Metturdam-2 authorized dealer of M/s. CTR Manufacturing Industries Ltd, Pune, under Single Tender / Proprietary/Private sector - Approval - Accorded - Regarding. 25) Per (FB) TANGEDCO Proceedings No.25 (Techl.Br.) Dt.01.04.2017. 50 TANGEDCO - Tuticorin Thermal Power Station - Tripping of Unit V due to failure of Boiler down comer pipe - Rectification of damaged Boiler components and restored Unit V in complete shape by entrusting the works to M/s. BHEL on mutually agreed price, under single tender/proprietary basis - Approval Accorded and Ratified. 26) Per (FB).TANTRANSCO Proceedings No.15 (Techl.Br.) Dt.03.04.2017. 50 Specification T-1973-Procurement of 110 Nos., 230KV Outdoor SF6 Circuit Breakers with Terminal Connectore-Opening of Price bids Approval Accorded - Regarding. 27) Per (FB) TANGEDCO Board Proceedings No.26 (Techl.Br.) Dt.03.04.2017. 51 NCTPS II - 2x600 MW - Procurement of FD & PA fans hydraulic adjusting device & FD fan Impeller blades and its accessories - To place orders on M/s.BHEL - Under Single tender/Proprietary basis/Public sector - Approval Accorded - Regarding. 92

Technical (Contd...) Page No. 28) Per FB TANGEDCO Proceedings No.28 (Techl.Br.) Dt.04.04.2017. 51 TANGEDCO - Ennore Thermal Power Station - Some of the chemical items & insulation materials stored in the Stores got dissolved due to Vardha cyclone on 12.12.2016 - Losses be write off - Approval Accorded. 29) (Rt.) CMD TANGEDCO Proceedings No.28 (Techl.Br.) Dt.04.04.2017. 52 Theft of materials from the released Distribution Transformer of 75KVA/ 22KV DT (Make:GEF:Sl.No.7232,) from the Singalanthapuram SS XVII/ Rasipuram subdivision/Namakkal EDC-write off the amount of Rs.53,594/- Approved. 30) Per (FB) TANGEDCO Proceedings No.29 (Techl.Br.) Dt.04.04.2017. 53 TANGEDCO - Bhavani Kattalai Barrage - III HEP (2x15MW) - Construction of 1 Block of ‘S’ type Quarters(twin type), 1 Block ”R” type - 6 Nos, 4 Block “Q” type 24- Nos quarters (Totally 32 Nos Tenements), Bore well, elevated water tank, sump tank, car and two wheeler shed, drainage, formation of road, guard room for Officers and Staffs at Bhavani Kattalai Barrage - III Power House at Pasur Village - Administrative Approval - Accorded- Regarding. 31) Per. F.B. TANGEDCO Proceedings No.30 (Techl.Br.) Dt.04.04.2017. 54 HRD - Engagement of Tradesman ITI Apprentices - Payment of the revised stipend from Rs.2800/- to Rs.7709/- to the Tradesman ITI Apprentices - Approval - Accorded. 32) (Per) FB TANGEDCO Proceedings No.31 (Techl.Br.) Dt.04.04.2017. 55 TANGEDCO – NCES –Establishment of Co-generation plants in 12 Nos. Co- operative and public sector sugar mills in Tamil Nadu – P.O.No.02 dt 27.05.09 placed on M/s. MITCON Consultancy & Engineering Services Ltd., Pune for offering Consultancy Services of Pre EPC Contract, Post EPC Contract and Project Management Services providing one Senior Resident Engineer per site, for two sits at a time to co-ordinate and monitor the progress of works till the Commissioning of all the Plants – Extension for Consultancy Service Contract for Post contract services at the revised rates from October 2015 until Commissioning of all the Plants-Approval-Accorded. 33) (Per) CMD TANGEDCO Proceedings No.186 (Techl.Br.) Dt.04.04.2017. 56 TANGEDCO – IT WING – Enhancement of ISP bandwidth Links – Administrative Approval – Accorded. 34) (Per) CMD TANGEDCO Proceedings No.187 (Techl.Br.) Dt.04.04.2017. 56 NCES – HT consumers establishing roof top/ground mounted solar power plants within the premises of service connection for captive use – Solar injection at HT consumer’s HT/LT network – Maintaining separate seniority for solar capacity upto 500 KW and separate seniority for solar capacity more than 500 KW – Approval Accorded. 35) Per (CMD) TANGEDCO Proceedings No.192 (Techl.Br.) Dt.06.04.2017. 58 TANGEDCO – Chief Engineer/Civil Designs – Provision of 3 Nos. of Core i3 Desktop PCs and 3 Nos. of duplex laser jet printers for the official use of Assistant Executive Engineer/Civil – II in PCC Division –I, Assistant Executive Engineer/Civil – I&II in the PCC Division – II in the Superintending Engineer/ Civil/PCC & DRIP Circle at the office of the Chief Engineer/Civil Designs – Approval –Accorded - Regarding. 93

Technical (Contd...) Page No. 36) Per FB TANGEDCO Proceedings No.32 (Techl.Br.) Dt.07.04.2017. 58 TANGEDCO – Allocation of Indigenous coal from Coal India Ltd (CIL) through FSA route – Transfer of 0.50 Million Tonnes Per Annum (MTPA) of coal from Mahanadi Coalfields Ltd (MCL) to Western Coalfields Ltd (WCL) – Signing of FSA with WCL and Amendment for the modified quantity with MCL for FSA 2009 - Approval Accorded - Regarding. 37) Per (CMD) TANGEDCO Proceedings No.193 (Techl.Br.) Dt.07.04.2017. 59 NCTPS I – M.II Circle-ICHS Division-Urgent procurement of one no.Elecon make Helical gearbox model KCH – 315 and its Hollow shaft required for replacement of worn out Gearbox in Boom and Intermediate conveyors of Stackers in Internal Coal Handling System of North Chennai Thermal Power Station-I under Single tender system /Proprietary/Private sector basis Administrative Approval-Accorded. 38) Per (CMD) TANGEDCO Proceedings No.194 (Techl.Br.) Dt.07.04.2017. 59 NCTPS.I– M.II Circle- Internal Coal Handling Division – Supply, Erection, Testing and Commissioning of Hydraulic Braking System for Reclaimer.I & Travelling Tripper.B of ICHS at NCTPS.I- Administrative Approval-Accorded. 39) Per TANGEDCO Proceedings (CMD) No.195 (Techl.Br.) Dt.07.04.2017. 60 Mettur Thermal Power Station – I – Capital overhauling and RLA study of 210 MW LMW design Turbo-Generator of Unit-IV/MTPS-I- Administrative Approval-Accorded. 40) Per TANGEDCO Proceedings (CMD) No.196 (Techl.Br.) Dt.07.04.2017. 60 Tuticorin Thermal Power Station – Retrofitting of 210 MW LMW surface condenser in any one of the Units of I, II & III under single tender proprietary basis by M/s.BHEL - Administrative Approval-Accorded. 41) Per TANGEDCO Proceedings (CMD) No.197 (Techl.Br.) Dt.07.04.2017. 61 MTPS-I – Installation and commissioning of additional 2 Nos. Continuous Ambient Air Quality Monitoring Stations along with Data uploading facility and to establish connectivity with the CARE AIR Centre/TNPCB/Chennai - Administrative Approval-Accorded. 42) Per TANGEDCO Proceedings (CMD) No.198 (Techl.Br.) Dt.07.04.2017. 61 Tuticorin Thermal Power Station – Units I – Capital Overhauling of TG Set and RE RLA Study on Turbine Components in Unit I - Administrative Approval- Accorded. 43) Per. (CMD) TANGEDCO Proceedings No.199 (Techl.Br.) Dt.07.04.2017. 62 TANGEDCO – Coimbatore Region – Tiruppur EDC-Establishment of new Kalivelampatty 230/110 KV SS at Valampalayam village, Paladam Taluk, Tiruppur District – Purchase of land from private party – Payment of land cost - Approval-Accorded. 44) (Per) CMD TANGEDCO Proceedings No.202 (Techl.Br.) Dt.11.04.2017. 63 TANGEDCO –IT Wing – Provision of New /Additional Broadband internet connection for e-tendering / e-procurement purpose exclusively – Approval Accorded. 45) (Rt.) CMD TANGEDCO Proceedings No.30 (Techl.Br.) Dt.12.04.2017. 63 Hydro – Generation Circle/Tirunelveli – Improvement works to the existing Inspection Bungalow including Annexe I & II at Papanasam Lower Camp by providing new Doors, Windows, Water Supply & Sanitary items, Vitrified Tile 94

Technical (Contd...) Page No. Flooring, Electrification, Furniture, etc., in place of the damaged ones - Administrative Approval-Accorded. 46) (Rt.) (CMD) TANGEDCO Proceedings No.31 (Techl.Br.) Dt.13.04.2017. 64 TNEB – Head Quarters Complex – Purchase of drinking water from CMWSSB to TNEB HQ Complex through Tanker lorries for the period of five months or complete utilization of P.O during I Phase of 2017, from the date of utilization of purchase order - Administrative Approval - Accorded. 47) (Per.) CMD TANGEDCO Proceedings No.204 (Techl.Br.) Dt.13.04.2017. 65 TANGEDCO Hydro – Erode Generation Circle – Barrage Power House – 2/ Nerinjipettai – Replacement of 3nos. bottom ducts and Strengthening & reconditioning of 3 nos. top ducts in 5 numbers Barrage Gates - Administrative Approval-Accorded. 48) Lr. No. SE/RE&I(D)EE/RE/A1/F.Doc./D250/17, (Tech.Br.) dt.13.04.2017. 65 Elecy. – TANGEDCO – Minutes of Distribution Review meeting – Agriculture – Distribution Transformer – DT meter – Instruction – Regarding. 49) Memo. No.CE/Comml./SE/EE/R&C/AEE.1/F.R&C/D.078/17, (Techl.Br.) dt.17.04.2017. 66 Elecy. –Continuance of withdrawal of 90% demand and energy cut for HT Industrial & Commercial services imposed during evening peak hours (6.00 p.m. to 10.00 p.m.) beyond 01.04.2017 – Instruction Issued – Regarding. 50) Routine CMD TANGEDCO Proceedings No.32 (Techl.Br.) Dt.21.04.2017. 66 Tirunelveli Region – Provision of One No. New Transformer Oil Filter Machine of 2.4KL capacity by replacing the existing condemned Oil Filter Machine for the Special Maintenance wing at Virudhunagar EDC - Administrative Approval- Order – Issued. 51) foj v©.nkbgh/Cäknk(g)/brbgh/Cä/cbrbgh2/nfh¥ò/v©.262 (bjh.E.») ehŸ 21.04.2017. 67 ä‹rhu« - Áw¥ò K‹Dçik étrha é©z¥g§fŸ 2017-18 M« M©L F¿pL - 215 v©z« é©z¥g§fŸ éLé¡f¥gLjš - r«gªjkhf. 52) (Rt.) CMD TANGEDCO Proceedings No.33 (Techl.Br.) Dt.25.04.2017. 78 Hydro – Kundah Generation Circle – Cleaning and Sweeping in and around Power House premises, IB road, Executive Engineer Bungalow Road and Inspection Bungalow care taker in Moyar Camp and routing cleaning of the trash rack at the main entrance of Moyar Fore Bay dam and LLP pipe line entrance trash rack for the period of 12 months from the date of Utilization - Administrative Approval-Accorded. 53) (Rt.) CMD TANGEDCO Proceedings No.34 (Techl.Br.) Dt.25.04.2017. 78 Hydro –Generation Circle Kundah – Cleaning, Sweeping and Maintenance of water supply and sanitation arrangement in the Camp and Power house area of Geddai, Parali and Pillur for a period of one year from the date of utilisation - Administrative Approval-Accorded. 54) (Rt.) CMD TANGEDCO Proceedings No.35 (Techl.Br.) Dt.25.04.2017. 79 Hydro – Erode Generation Circle – Bhavani Kattalai Barrage 3 Power House at Cholasiramani – Rectification works to the damages to the Crest, Piers and Apron portion to be taken up on top priority – In-Principle Approval- Accorded. 95

Technical (Contd...) Page No. 55) (Per.) CMD TANGEDCO Proceedings No.212 (Techl.Br.) Dt.25.04.2017. 80 TANGEDCO – R-APDRP – Part-B works LOA No.892 Dt 17.04.2013 – “Survey, Design, Engineering, Manufacture, Supply, Erection, Testing, Commissioning of 11kV & 22 kV RMUS and associated materials” – Time extension for project Supply and Commissioning of RMUs due to constraints not attributable to M/s. L&T Ltd-Approval-Approval-Regarding. 56) Per. CMD TANGEDCO Proceedings No.213 (Techl.Br.) Dt.26.04.2017. 81 TANGEDCO – PUSHEP (3x50MW) – Pykara Ultimate Stage Hydro Electric Project – Construction of Access Tunnel, Tail race Tunnel, Pressure shaft, Power house Cavern, including Transformer Cavern, Cable shaft, Adits etc under Spn.No.SE/CD/1322 – Civil Suit No.654 of 2011 Filed by M/s. Karam Chand Thapar & Bros (Coal Sales) Ltd, Kolkata – against TANGEDCO – Posted for trial by Recording evidences of PW & DW commences before Additional Master Court-I formation of Core Committee and to engage of Senior counsel -Approval-Approval-Regarding. 57) (Rt.) CMD TANGEDCO Proceedings No.36 (Techl.Br.) Dt.27.04.2017. 82 TANGEDCO – MM - Procurement of certain materials hitherto dealt by Material Management wing - Proposal for decentralization - Approval Accorded. 58) (Per)CH.TANTRANSCO Proceedings No.101 (Techl.Br.) Dt.27.04.2017. 83 Electricity – Provision of one number 400KV, 125MVAr Bus Reactor along with associated equipments & accessories at Kayathar 400/230-110 KV substation - Administrative Approval - Accorded. 59) (Per) CH. TANTRANSCO Proceedings No.103 (Techl.Br.) Dt.28.04.2017. 86 IT wing - Provision of VPNOBB connectivity to GCC, P&C and operation circles - extension of connectivity upto 18/07/2017 - Administrative Approval - Accorded. 60) (Rt.) CMD TANGEDCO Proceedings No.37 (Techl.Br.) Dt.29.04.2017. 86 Hydro – Kundah Generation Circle - Cleaning, Sweeping and Maintenance of Water supply and Sanitation arrangements in the Kundah Upper Camp and Lower Camp - Administrative Approval Accorded. 61) (Rt.) CMD TANGEDCO Proceedings No.38 (Techl.Br.) Dt.29.04.2017. 87 Hydro – Generation Circle Kundah - Cleaning and Sweeping and Maintenance of Water supply and Sanitation arrangements in the Camp and Power house area of Pykara, Singara and Glenmorgan for the period of one year from the date of utilization - Administrative Approval Accorded. 62) (Per.) Proceedings (CMD TANGEDCO) No.219 (Techl.Br.) Dt.29.04.2017. 88 Research & Development - Implementation of Harmonics limits in Solar Power Generators (SPGs) / Wind Energy Generators (WEGs) - Formation of committee to discuss and arrive conclusive methodology for harmonics measurement - Approval - Accorded. * * * 96