<<

TIMELINE Wastewater The plant is to be fully commissioned and operational by December 31, 2020, with construction and commissioning to LIONS GATE SECONDARY Treatment Plant take place between 2017 and 2020. Once the plant is in operation, the existing Lions Gate primary treatment plant will be decommissioned and deconstructed. As part of Metro ’s responsibility to protect and enhance the natural environment, a new secondary wastewater treatment plant will be built on the North Shore.

2014 2015 2016 2017 2018 2019 2020 2021 Metro Vancouver is designing a new Lions Gate Secondary Wastewater Treatment Plant – expected PROJECT PHASES AND TIMELINE FUNDING APPLICATIONS/DESIGN-BUILD PROCUREMENT commissioning 2020. PROJECT DEFINITION JAN to DEC NEW PLANT COMMISSIONED The plant will provide secondary treatment to DESIGN 2014 2020 approximately 200,000 residents on the North Shore of – total estimated cost $700 million. CONSTRUCTION AND COMMISSIONING JAN to DEC 2020 2012 2013 Project Definition is complete, and the selection process DESIGN & CONSTRUCTION CONVEYANCE UPGRADES for the design-builder is in progress. COMPLETED

DECOMMISSION EXISTING LIONS GATE WWTP

PROJECT BUDGET and based largely on Metro Vancouver’s PROJECT FUNDING 50+ years experience in building, The Metro Vancouver Board of Directors Metro Vancouver has completed the operating and maintaining state-of- Project Definition phase and Indicative has formally committed a one-third share the art wastewater treatment facilities of the $700 million in estimated costs Design of the Lions Gate Secondary throughout the region, concluded that Wastewater Treatment Plant project, and for the Lions Gate project, and in March the optimal procurement model for 2016, the federal government confirmed based on current design considerations, the Lions Gate Secondary Wastewater the estimated cost of the project – its contribution of $212.3 million towards Treatment Plant is design-build-finance project costs under the Provincial- including decommissioning of the old (DBF). Working with Partnerships BC, facility – is approximately $700 million. Territorial Infrastructure Component of Metro Vancouver has confirmed that the New Building Canada Fund. In March assessment, and is proposing a full DBF PROCUREMENT OPTIONS 2017, the Province of procurement model for the new Lions announced that it would contribute up to Metro Vancouver also commissioned Gate plant. $193 million towards eligible costs. KPMG to undertake an in-depth value- for-money analysis of the design and construction procurement options

t

v

r

.

m

y

e

s

l available for the new Lions Gate plant, e

h

LIONS GATE SWWTP COSTING c

_

H

C

R

A

_

e

t

a

G

options that included three primary s PERSPECTIVE - MAIN ENTRANCE AND PLAZA AREA PERSPECTIVE - MAIN ENTRANCE AND PLAZA AREA n

o

i

CONSTRUCTION/ CONTINGENCIES/ESCALATION L

\

s

t

n

e

m

u

c

o

ADMINISTRATION (2018 DOLLARS) TOTAL METRO VANCOUVER TECHNICAL SUBMISSION - NOT APPROVED FOR CONSTRUCTION D models: the traditional design-bid-build \

m

y

e

s

l

Greater Vancouver Water District e

h

c

\

SCALE: s CHECK Design: Designer r

LIONS GATE WWTP e

s

U

\ (DBB), design-build-finance (DBf), and SECONDARY WASTEWATER TREATMENT PLANT : Drawn: Author PRINT PRELIMINARY DESIGN DISTRICT FILE C Lions Gate WWTP $450,000,000 $170,000,000 $620,000,000 Checked: Checker THIS DRAWING HAS NOT BEEN APPROVED, AND MAY t As the regional government on Canada’s southwest coast, Managing our region’s wastewater is a combinedv effort. CONTAIN ERRORS AND Approver r CHECK . SEATTLE / Pier 56, 1201 Alaskan Way, #200 Seattle, WA 98101 / 206.623.3344 OMISSIONS. Approved: GROUND LEVEL PERSPECTIVE FROM NORTHEAST s

design-build-finance-operate-maintain e

W

1 11/29/16 TECHNICAL SUBMITTAL t

DRAWING NUMBER Y

n SAN FRANCISCO / 660 Market Street, #300 U



Issue Date Desn Dr'n Chkd Appd Description Manager: e San Francisco, CA 94104 / 415.956.0688 A10-001 V

H

m Metro Vancouver has legislatively mandated responsibility for Residents, businesses and industries in Metro Vancouver W Professional Seal 0 20 11/11/2016 10:48:28 AM 10:48:28 11/11/2016

c Conveyance $40,000,000 $20,000,000 $60,000,000 PRINTBar is 20mm On Original Drawing. If Not On This Sheet, Adjust Scales Accordingly SUPERSEDES PRINTS OF THIS DOCUMENT CODE WITH LETTERS PREVIOUS TO P1 Q H

_

(DBFOM, or a full private/public P

M

F

B

O

0

T

2

 providing regional-scale utility services – water, wastewater and produce about 1 billion litres of wastewaterS per day, which is

7

1

6

A partnership). In 2013, a Committee of 



Decommissioning $12,900,000 $7,100,000 $20,000,000 PERSPECTIVE - SOUTHWEST FROM MCKEEN AVENUE $

A NOT FOR 

A 016(14 $

$

F

solid waste management – to over 2.4 million residents in the brought to treatment plants through a municipal system of

)

-



-



 CONSTRUCTION -



- %105647%6+10 the Metro Board of Directors completed 

W

:

\

?

V of current plant s

H

e

O

l

L

greater Vancouver area, or just over 50% of British Columbia’s sewers, collection systems and sewage pumpingi stations.

)



F

O

l a detailed review of the KPMG report, *5($7(59$1&289(56(:(5$*($1''5$,1$*(',675,&7 D GREATER VANCOUVER SEWERAGE AND DRAINAGE DISTRICT a F

R

c

/

o 6&$/(

?

'& W

L SCALE: L 'HVLJQ

\ /,216*$7(

Y DC t total population. i Design: LIONS GATE As Indicated H

v

TOTALS $502,900,000 $197,100,000 $700,000,000 5

?

e 6(&21'$5<:$67(:$7(575($70(173/$17 As Indicated1 : 100 'UDZQ ,% 

&

R

SECONDARY WASTEWATER TREATMENT PLANT \ ',675,&7),/( Drawn: IB : 7(&+1,&$/68%0,66,21 TECHNICAL SUBMISSION DISTRICT FILE C &KHFNHG '& 23(5$7,216$1'0$,17(1$1&(%8,/',1* DC Checked: OPERATIONS AND MAINTENANCE BUILDING '& DC $SSURYHG )81&7,21$/5(/$7,216+,3',$*5$0PERSPECTIVE $ 129 '& ,% '& '& ,668(')25352326$/ *5281')/2253/$1 4'&7%'&2.#0 Approved: FUNCTIONALPERSPECTIVE RELATIONSHIP DIAGRAM 53 - SOUTHWEST FROM MCKEEN AVENUE '2&80(17&2'( DC IB DC DC ISSUED FOR PROPOSAL ,VVXH 'DWH 'HVQ 'U Q &KNG $SSG 'HVFULSWLRQ 0DQDJHU $A-10-0005 A 29/NOV/2016 7UG«UECNG«JCNH«UK\G«QH«VJQUG«UJQYP«YJGP RP - MAIN ENTRANCEGROUND FLOOR AND PLAZAPLAN AREA DOCUMENT CODE REDUCED PLAN RTKPVGF«QP«Z«RCRGT« OO«Z«OO 3URIHVVLRQDO6HDO   %DULVPP2Q2ULJLQDO'UDZLQJ,I1RW2Q7KLV6KHHW$GMXVW6FDOHV$FFRUGLQJO\ 683(56('(635,1762)7+,6'2&80(17&2'(:,7+/(77(5635(9,28672 Issue Date Desn Dr'n Chkd Appd Description $ 30 Use scale half size of those shown when Manager: A-10-0027A-10-0004 printed on 11x17 paper (279mm x 432mm) Professional Seal 0 20 Bar is 20mm On Original Drawing. If Not On This Sheet, Adjust Scales Accordingly SUPERSEDES PRINTS OF THIS DOCUMENT CODE WITH LETTERS PREVIOUS TO A PM 2:59:44 11/17/2016 For more information on the Lions Gate Secondary Wastewater Treatment Plant, please contact: Simon So, General Manager Paul Dufault, Project Manager Liquid Waste Services [email protected] [email protected] 604-432-6407 604-432-6479 LIONS GATE WWTP T" ® METRO VANCOUVER

WASTE WATER TREATMENT PLANTS & SEWER MAINS Iona Island WWTP T" Northwest Langley WWTP T" Annacis Island WWTP T"

Kilometers Lulu Island WWTP 0 1.75 3.5 7 10.5 T"

Metro Vancouver’s wastewater treatment plants Project site - current Public meetings

A REGIONAL UTILITY LIONS GATE SECONDARY WASTEWATER TREATMENT PLANT PROJECT To collect and treat wastewater, Metro Vancouver operates a network of trunk sewers, pumping stations As identified in Metro Vancouver’sIntegrated Liquid Waste and Resource PROJECT OBJECTIVES The project team worked together in In September 2015, Metro Vancouver began Management Plan – which was approved by the BC Ministry of Environment a highly collaborative way with a large the competitive process to select a firm to and wastewater treatment plants that connect with • Provision of secondary wastewater municipal sewer systems. in May, 2011 – the Lions Gate project is part of the secondary upgrading number of stakeholder groups including design, build and finance the construction of program of the two remaining primary WWTPs in the region. Under federal treatment. businesses, residents, technical experts, the treatment plant. A contract is expected We are responsible for: regulations the Lions Gate Wastewater Treatment Plant must be upgraded • Development and demonstration of a local government and First Nations in order to be in place in April 2017 and construction to secondary treatment by December 31, 2020. project that is socially, ecologically and to integrate these objectives into the will commence shortly thereafter. • five wastewater treatment plants; project design. The Lions Gate Secondary Wastewater Treatment Plant presents an economically sustainable. • about 530 km of trunk sewer pipes (large pipes that COMMUNITY ENGAGEMENT opportunity to simultaneously provide a needed upgrade to an essential • Implementation of integrated resource Intensive activities are focused at the connect to smaller municipal pipes); service, protect the local environment and contribute to development on west end of the site, with digesters, solids Supporting the objectives of the Lions recovery strategies. Gate project is a detailed community • 33 sewage pumping stations. the North Shore. handling, headworks and dewatering • Creation of a facility integrated into the clustered to facilitate robust odour control engagement plan. The project team worked Metro Vancouver also supports municipalities in the The new Lions Gate Secondary Wastewater Treatment Plant will occupy community. and efficient operation of the plant. Primary with local stakeholders to identify issues management of stormwater and habitat and drainage much of its 3.5 hectare site, and will employ best practices for wastewater and secondary treatment occur mid-block, early, and addressed community concerns treatment, resource recovery, and provide maximum flexibility for future throughout the Indicative Design process. areas around certain rivers. PROJECT DEFINITION – INDICATIVE DESIGN with a transparent cantilevered Operations treatment technology upgrades and growth. and Maintenance building at the corner of Community engagement will continue until Our priority is to protect public health and the During the project definition phase, Metro 1st St. and Pemberton Avenue. These the completion of the project, with the environment by maintaining healthy rivers and Vancouver used a multi-disciplinary process treatment plant functions are contained successful proponent expected to liaise with Upper Levels Hwy oceans. As part of the treatment process, in defining the scope of work required for in a clean, architectural form balanced local residents and businesses throughout we are also finding innovative ways to use the delivery of a state-of-the-art wastewater against the industrial scale of neighbouring the construction process. wastewater as a resource. treatment plant. The resulting Indicative industries. Translucent and glazed walls at In November 2013, the Lions Gate Advisory Design specifically responds to Metro the west end also allow selected views from The existing Lions Gate Secondary Wastewater Committee – representing the North Shore Vancouver’s four objectives for the project. the street into the plant, making the invisible Treatment Plant serves a total population of 200,000 communities – submitted a comprehensive visible. Westview Dr that includes the District of West Vancouver, the Westview Dr report, “Community Values and Interests Marine Dr Marine Dr District of and the City of North W Keith Rd for the Design of the Lions Gate Secondary Taylor Way Taylor Way Hope Rd Vancouver, as well as the Squamish Nation and Tsleil- Marine Dr INDICATIVE DESIGN – COMPLETE Wastewater Treatment Plant”. Waututh Nation. W 17th St Capilano Rd Larson Rd MacKay Ave What emerged from the Indicative In that report, the Committee expressed Marine Dr Hamilton Ave Marine Dr 16th St W Design process is a project characterized by their support for the Indicative Design as Pemberton Ave EXISTING LIONS GATE Pemberton Ave a diverse range of urban experiences across a reflection of their community’s values: WASTEWATER DISTRICT OF DISTRICT OF W 15th St CITY OF NORTH TREATMENT PLANT WEST VANCOUVER NORTH VANCOUVER VANCOUVER the site, a pedestrian-scaled public entrance prudent use of taxpayers’ money, design Tatlow Ave Welch St Tatlow Ave and outdoor open space at the foot of that integrates well with the surrounding MacKay Rd LIONS GATE MacKay Rd Lloyd Ave Lloyd Ave 3rd St W Fell Ave Fell Ave Keith Rd W area, and the use of modern technology Mathias Dr SECONDARY Pemberton. That design process defined

Lower Capilano Rd that reduces local impacts while meeting R A IL McBride St WASTEWATER a facility that is resilient and future proof, CAPILANO INDIAN TREATMENT PLANT regulatory requirements. Outfall 1st St W secure but visually open to the community, RESERVE NO. 5 Welch St Philip Ave PROJECT Philip Ave RAIL (SQUAMISH 3rd St W has the potential to be a net producer of SITE NATION) W 1st St energy, and that can be used to teach future Forbes Ave Forbes Ave

RAIL generations about sustainable construction, McKeen Ave LEGEND wastewater treatment and environmental Pemberton Ave Train Tracks Municipal border stewardship.

Burrard Inlet

Stanley Park Lonsdale Quay North Shore map www.metrovancouver.org Search: Lions Gate