1. At a glance: Technology driven EPC contractor 2. KT at a glance 3. KT Order intake & Revenues

4. KT Projects

JANUARY 2019 JANUARY COMPANY COMPANY | PROFILE AT A GLANCE: TECHNOLOGY DRIVEN EPC CONTRACTOR

| OIL&GAS REFINING | | FERTILIZERS | POWER | RENEWABLE & GREEN | INDUSTRY

Tecnimont KT- Kinetics Technology Stamicarbon NextChem

Oil&Gas Refining Refining, Hydrogen & Development and Green Acceleration Petrochemicals Syngas Production, licensing of Urea Project, Technological Fertilizers, Polyolefins, Sulphur Recovery and Technology initiatives for energy Power Large-scale Process Heaters transition contracting

Met Gas Met Development Neosia Neosia Renewables Technologies Spa

OPERATING COMPANIES OPERATING EPC contracting in Flexible solutions in Project development Development of energy Transportation and renewable energy company, supports technical innovative technologies Civil Engineering and financial structuring of projects

More than 8,800 professionals 5,800 employees +3,000 professionals in Electrical & Instrumentation

ORGANIZATION 40 COUNTRIES / 50 OPERATING COMPANIES 3 IN THE WORLD

ROME SITTARD BRAUNSCHWEIG MUMBAI

ITALY AND REST OF 2,381 EUROPE INDIA AND REST OF 1,791 ASIA RUSSIA AND CASPIAN 415 REGION

AMERICAS 49 Headquarters

MIDDLE EAST 681 Main offices and engineering centres NORTH AFRICA AND SUB- 126 Subsidiaries, branches and SAHARAN AFRICA GROUPOVERVIEW representative offices

TOTAL 5, 433* The Group market position and our competitiveness depend EMPLOYEES first of all on skilled and committed human resources.

*Average age: ~41 years Approx. 66% graduates Approx. 5,800 employees worldwide,

Data as of: 31.12.2017 CORPORATE PROFILE | and additional 3,000 professionals in Electrical & Instrumentation, 4 make Maire Tecnimont a multicultural and multinational Group. SAFETY FIRST

TRIR five year rolling average *: International Association of Oil & Gas Producers - Report No 2017s, Jun 2018 - IOGP Overall Benchmark * IOGP Construction Benchmark * TCM Safety Performance 2,00 Indicators 2017: Appendix B – 1,80 1,71 Section 4 Results by Function 1,66 1,58 - - Table B.30: Total 1,45 recordable injury rate five- 1,50 year rolling average by 1,30 function (2012–2017) 1,13 1,14 (pag:123) 1,04 1,06 1,07 1,00 0,94 The five-year rolling average is calculated by summing the

0,58 total number of incidents of year rolling average (per million hours) million (per average rolling year - 0,49 0,42 the five previous years, and 0,50 dividing by the sum of the 0,30 0,28 TRIR five TRIR 0,24 work hours for these years: (Number of LTI in 2013+2014+2015+2016+2017) 0,00 / (Total work hours in

GROUPOVERVIEW 2008-2012 2009-2013 2010-2014 2011-2015 2012-2016 2013-2017 2013+2014+2015+2016+2017)

ZERO INCIDENT TARGET Widespread safety culture is part of our core values Integrated HSE Management System constantly reinforced, diffused, checked and upgraded

with results considerably higher than international standards. CORPORATE PROFILE | 5 KEY MILESTONES Our Evolution

1899 GROUP 1937 1971 1972 Dutch State Mines – DSM Kinetics Technology Int. - KTI Repositioning Incorporation of research centre for services More than 40 years of completed and FIAT ENGINEERING work to coal mines experience in process engineering Record Backlog 2001 1947 1988 Acquisition of FIAT Avio’s Electric Incorporation of Mannesmann acquired KTI Design & Construction Business STAMICARBON 1999 Chemical and Fertilizer Technip acquired KTI 2004 licensing Acquisition of Listing on the Acquisition of KT Kinetics Fiat Engineering Italian Stock Acquisition of Technology (formerly (later MAIRE ENGINEERING) Exchange Stamicarbon Technip KTI)

2005 2007 2009 2010 2011 2013 2015 2018

100% Acquisition of the Indian Incorporation of Launch of the subsidiary Tecnimont Pvt. Ltd. Reorganization Launch of the New Business MAIRE TECNIMONT (formerly TICB) of New Business Italian HQs Strategy Unit 1990s NextChem Tecnimont acquires 50% of the Indian company renamed as Tecnimont ICB Pvt Ltd (TICB) 2005

GROUPOVERVIEW Maire Group acquires 1977 Tecnimont Creation of the first JV between ICB and Tecnimont 1973 1958 Incorporation of New Milan Offices TECNIMONT Incorporation of ICB Pvt Ltd as consulting 1963 firm in the plant sector in Mumbai Giulio Natta 1966 Nobel Prize for Incorporation of

chemistry MONTEDISON CORPORATE PROFILE | 1884 1888 MONTECATINI 6 Power Supply Mines and Chemicals KT TRACK RECORD

More than 40 +120 years’ experience Hydrogen and Sulphur as a Process Engineering Recovery Unit Projects A leading expertise Contractor and in the completed in the to implement development of new last 10 years oil refining projects technologies for Oil & Gas industry

Development of well recognized well recognized innovative technologies international player international player and creation in licensing Hydrogen in licensing Sulphur technology, with single Recovery and Tail Gas | | A GLANCE AT KT of Pilot Plants train capacity up to Treatment Technology, 188,000 Nm3/h with single train up to

1,800 t/d COMPANY COMPANY PROFILE 7 KT BRAND HISTORY Our Evolution

KTI A Company of TECHNIP KTI KT –Kinetics Technology Mannesman Group Management Buy-out Recently the KT was 75% of the Company Company has acquired by was acquired by its changed its name Mannesmann Management. into KT – Kinetics KT was established Anlagenbau The remaining 25% Technology to under the name of was owned by highlight company Selas Italia Technip Italy historical identity

1971 1974 1988 1999 2005 2010 2013

Technip Italy Maire Tecnimont The first logo acquired 100% acquired the 100% was created of KTI SpA changing the of Technip KTI SpA name in Technip KTI SpA changing its name in KTI Tecnimont KT SpA

TECHNIP KTI Tecnimont KT

| | A GLANCE AT KT COMPANY COMPANY PROFILE 8 KT BUSINESS AREAS

COMPETENCES TRACK RECORDS HIGHLIGHTS

Successful execution of Delayed Coker Refining processing units Capability to implement projects complex, Vacuum Distillate HDT, HDC Oil & Gas Development fields based, whenever required, on third- complex, Gas field central processing facility, Gas Treatment and fractionation party licensed technologies

Oil&gas treatment plant, Gas Fractionation OIL & GAS & OIL

 Leading Licensor and EPC Contractor Well recognized player in licensing sulphur  Tailor-made solutions Proprietary technologies for Gas recovery and tail gas treatment technology  Full plant life cycle support Sweetening and Tail Gas Treatment with design capacity of single train up to  Extensive expertise plant revamping (RAR Technology)

AND GAS AND 1800 t/d SULPHUR SULPHUR

RECOVERY RECOVERY and retrofitting TREATMENT

 Leading Licensor and EPC Contractor Over 60 hydrogen and syngas projects  Tailor-made solutions designed/built worldwide Leading Company in providing  Full plant life cycle support Well recognized player in licensing hydrogen production units based on

 Extensive expertise plant revamping hydrogen technology, with single train steam reforming technology SYNGAS

and retrofitting capacity up to 188,000 Nm3/h

PRODUCTION HYDROGEN & & HYDROGEN

 Process, detailed mechanical design and supply all required materials Approved Supplier of major World  More than 40 years experience  Revamping and debottlenecking players such as Bechtel, KBR,  More than 1700 installations

FIRED FIRED services, after Sales services Aramco, Takreer, Sasol and others

HEATERS AND HEAT HEAT AND

TRANSFER TRANSFER  Full plant life cycle support

EQUIPMENT | | A GLANCE AT KT

Activities with international Industrial  Development of innovative Partners, Universities and Research Application of more than 15 Patents in technologies institutions 2011-2012  Design and realization of pilot Funding from Italian Ministry of Owner of Plant Testing Facilities plants

ACTIVITIES Education and European Commission

RESEARCH & & RESEARCH

COMPANY COMPANY PROFILE DEVELOPMENT DEVELOPMENT 9 KT HSE PERFORMANCE: SAFETY FIRST

1,80

1,60

1,40

1,20

1,00

0,80

0,60

0,40

0,20

0,00 Year 2014 Year 2015 Year 2016 Year 2017 Year 2018 LTIF 0,00 0,00 0,14 0,05 0,08 TRIR 1,56 0,00 0,14 0,15 0,12

LOST TIME INJURY FREQUENCY (LTIF) TOTAL RECORDABLE INJURY RATE (TRIR) | | A GLANCE AT KT N. of lost time injuries cases x 200.000 N. of recordable cases x 200.000

Number of hours worked Number of hours worked COMPANY COMPANY PROFILE 10 KT TOWARDS THE SOCIAL RESPONSIBILITY

Sustainability is the cultural root of KT: it is a constitutive element of our mission that helps to draw our own identity. The ethical principles of KT, described in the Group Code of Ethics, are the references shared by all our employees. Our mission is not only to produce profit, but do it in a sustainable and useful way for the development of the community and future generations

Equality Training No workplace discrimination Working together Honesty Our code of ethics to integrity and transparency I mprovement C onduct Looking ahead and moving forward Defend and protect legal and human rights Association Strength in unity

| | A GLANCE AT KT Like prevention Love communication Safe and healthy work environment Dialogue ou

COMPANY COMPANY PROFILE Y A team player 11 KT ORDER INTAKE & REVENUES

LAST TOP AWARDS

Russian Federation: LUKOIL, SRU & HC Gas Fractionatoin Units HDT & HPU/ROG PSA EPC Egypt: PETROBEL, Sulphur Recovery Unit for Ramp-up to Plateau EP Belgium: TOTAL, Refinery Off Gas (ROG) EPC | | ORDERKT INTAKE & REVENUES Cameroun: SONARA Refinery, Hydrocracker Complex EPC Poland: GRUPA LOTOS Gdansk Refinery, DCU+HVD EPC Saudi Arabia: PETRO RABIGH, Clean Fuels & SRU EPC

Egypt: PETROBEL, Sulphur Recovery Unit EP COMPANY COMPANY PROFILE € < 200 € mn € € 200 to 500 € mn 12 OIL & GAS

COMPETENCES

 Refining processing units  Oil & Gas Development fields  Gas Treatment and Fractionation

TRACK RECORD

 Successful execution of Delayed Coker complex, HDC complex, Vacuum Distillation, HDT, Gas field central processing facility  Oil & Gas Treatment plant

 Gas Fractionation plant

| | PROJECTSKT COMPANY COMPANY PROFILE 13 RECENT OIL & GAS PROJECTS PLANTS KSTOVO REFINERY: SRU & HC GAS FRACTIONATION UNITS HDT & HPU/ROG PSA KSTOVO (RUSSIAN FEDERATION) CAPACITY: GFU 425 kton/y - SRU 80 ktons/y HPU 50 kNm3/h - ROG PSA 60 kNm3/h - DHT 1530 kton/y CLIENT: LLC LUKOIL – Nizhegorodnefteorgsintez REFINERY OFF GAS (ROG) PROJECT CONTRACT TYPE: EPC LS ANTWERP (BELGIUM) CAPACITY: 1 Saturated Gas Train 39 t/h off gas; 1 Unsaturated Gas Train 30 t/h off Gas. CLIENT: Total Olefins Antwerp CONTRACT TYPE: EPC - LSTK

MODERNIZATION BAKU OIL REFINERY - HAOR PROJECT (AZERBAIJAN) CAPACITY: SRU: 2x30 t/d; TGT: 40 t/d Client: SOCAR HAOR Contract type: EPC (JV TCM/KT)

MILD HYDROCRACKING UNIT, BUSALLA (ITALY) CAPACITY: 1,400 t/d (vacuum gasoil) CLIENT: IPLOM CONTRACT TYPE: EPC - LS OIL & GAS TREATMENT PLANT, LUBIATOW (POLAND) GAS CAPACITY: 30,000 Nm3/h OIL CAPACITY: 1,300 t/d CLIENT: Polish Oil & Gas Company (PGNiG) CONTRACT TYPE: EPC - LSTK

VACUUM UNIT REVAMPING, MILAZZO (ITALY) CAPACITY:11,000 t/d CLIENT: RAM (Raffineria di Milazzo) CONTRACT TYPE: Services for EPC - LS SRU & ACID GAS REMOVAL UNITS, HABSHAN 5 (UAE) CAPACITY: 4 x 1,300 t/d CLIENT: GASCO

CONTRACT TYPE: EP CS - LS

| | PROJECTSKT COMPANY COMPANY PROFILE

UNDER REALIZATION PROJECT COMPLETED PROJECT 14 RECENT OIL & GAS PROJECTS OIL AND GAS TREATMENT "TEMPA ROSSA“ CORLETO PERTICARA (ITALY) CAPACITY: 50Kb/d crude oil treatment CLIENT: Total E&P Italia SpA (Total Group) CONTRACT TYPE: EPSCC CONTRACTOR: Project Association between Tecnimont and KT

DELAYED COKING UNIT AND HYDROGEN PRODUCTION UNIT, GDANSK (POLAND) CAPACITY: DCU 350,000 t/y; HPU 24,000 Nm3/h CLIENT: LOTOS ASFALT SP. ZO.O CONTRACT TYPE: EPC - LSTK

PHASE 2 MODERNIZATION PROJECT SONARA REFINERY, HYDROCRACKER COMPLEX, LIMBE (CAMEROUN) COKER NAPHTA HYDROTREATING UNIT AND HYDROWAX CAPACITY: 18,000 BPD VACUUM DISTILLATION UNIT, GDANSK (POLAND) CLIENT: SONARA ReFineRY CAPACITY: CNHTU 18,000 T/D; HVDU 2,280 t/d CONTRACT TYPE: EPC - LSTK CLIENT: GROUPA LOTOS S.A. CONTRACT TYPE: EPC - LSTK

CONTRACTOR: Consortium with KT CAMEROUN; USTAY) | | PROJECTSKT

GAS COMPRESSION STATION, AL-ARISH (EGYPT) CAPACITY: 400,000 Nm3/h CLIENT: East Mediterranean Gas Company

CONTRACT TYPE: EPC - LS COMPANY COMPANY PROFILE UNDER REALIZATION PROJECT COMPLETED PROJECT 15 SRU & HC GAS FRACTIONATOIN UNITS HDT & HPU/ROG PSA, KSTOVO

Two EPC contracts granted by LUKOIL for a refinery upgrading project in central Russia.

KT has been awarded two EPC (Engineering- Procurement) contracts by LUKOIL NizhegorodNefteorgSyntez, a subsidiary of JSC LUKOIL. The contracts are related to five refinery process units for the large residue upgrading project, part of the Deep Conversion Complex in Kstovo City, central Russia.

The Project will improve the complexity and technological content of the Kstovo Refinery, enabling the plant to produce higher value products and refine lower quality crude oil, therefore meeting the growing CLIENT: LLC LUKOIL – ROG PSA 60 kNm3/h market demand for cleaner fuels as well as ensuring Nizhegorodnefteorgsintez DHT 1530 ktons/y COUNTRY: Kstovo (Russian YEAR OF AWARD: 2017 | | PROJECTSKT higher yields of valuable products. Federation) START-UP: 2021 CONTRACT TYPE: EPC- LS CAPACITY: GFU 425 ktons/y SRU 80 ktons/y

HPU 50 kNm3/h COMPANY COMPANY PROFILE 16 HEYDAR ALIYEV OIL REFINERY MODERNIZATION AND RECONSTRUCTION PROJECT (1/2)

On February 2018 Maire Tecnimont Group, through the Joint Venture between its subsidiaries Tecnimont and KT has been awarded an EPC Contract on lump sum turn key basis for an important part of the execution of the Modernization and Reconstruction works for the Heydar Aliyev Baku Oil Refinery, in Azerbaijan.

The scope of the project entails the installation of several new grass root process units, the relevant utilities and storage with the final aim to upgrade the refinery facilities to be capable of processing 7.5 MMTPA of crude oil, while meeting quantity and quality requirements of products both to feed CLIENT: State Oil Company of YEAR OF AWARD: 2018 Azerikimya revamped plant and to the Azerbaijan Republic (SOCAR) | | PROJECTSKT START-UP: 2021 produce Euro V quality automotive transportation COUNTRY: Azerbaijan

fuels. CONTRACT TYPE: EPC - LS COMPANY COMPANY PROFILE 17 HEYDAR ALIYEV OIL REFINERY MODERNIZATION AND RECONSTRUCTION PROJECT (1/2)

Among the new process units in the scope:

• Naphtha Splitter

• Diesel Hydrotreater Unit

• Isomerization Unit

• Hydrogen Production Unit

• Two PSA Units

• C4 Hydrogenation Unit

• MTBE Unit • Sour Water Stripper Unit with Sulphur Recovery Unit

The project aims at allowing the commencing of the

production within 2021

| | PROJECTSKT COMPANY COMPANY PROFILE 18 DELAYED COKER UNIT AND HYDROGEN PRODUCTION UNIT, GDANSK (1/2)

The Client is Lotos Asfalt Sp Zo.o. subsidiary of Grupa Lotos SA. The project is related to a refinery unit upgrading in the Gdansk refinery, in the framework of the EFRA (Effective Refining) Project. The contract includes the implementation of a Delayed Coking Unit, a Coker Naphtha Hydrotreating Unit, a Hydrogen Production Unit together with ancillary units in the premises of the Gdansk refinery. The scope of the contract entails the implementation of the best available technology for produced coke downloading and dewatering. This technology is regarded as a breakthrough approach to the Delayed Coking environmental impact mitigation.

CLIENT: LOTOS ASFALT SP ENGINEERING HOURS: 480,000 COUNTRY: Poland CONSTRUCTION HOURS: 2,500,000

| | PROJECTSKT CONTRACT TYPE: EP - LSTK CAPACITY: TOTAL CONTRACTVALUE: 304 MM€ 350,000 t/y coke YEAR OF AWARD: 2015 28,000 Nm3/h Hydrogen Unit

START-UP: 2018 COMPANY COMPANY PROFILE 19 DELAYED COKER UNIT AND HYDROGEN PRODUCTION UNIT, GDANSK (2/2)

Grupa Lotos (GLSA) owns and operates the Gdansk Refinery, second largest refinery in Poland. In the frame of a modernization program (Program 10+) and the efforts to eliminate the production of road asphalt and increase the production of middle distillate GLSA has identified additional units to be incorporated into the refinery, in particular:

 Delayed Coking licensed by Lummus

 Naphtha Hydrotreater licensed by Axens

 LPG Washing, licensed by Merichem

 Hydrogen Generation Unit licensed by KT

| | PROJECTSKT COMPANY COMPANY PROFILE 20 REFINERY OFF GAS PROJECT (ROG PROJECT), ANTWERP (1/4)

PROJECT OBJECTIVE

The refinery configuration scheme will be modified by the provision of Refinery Off Gas (ROG) Unit aimed to recover valuable compounds (Ethane, Propane, Ethylene and Propylene) from Refinery Off Gases currently routed to Fuel Gas network and the integration of these streams within existing

U91 NC3 Cracker.

| | PROJECTSKT COMPANY COMPANY PROFILE 21 REFINERY OFF GAS PROJECT (ROG PROJECT), ANTWERP (2/4)

The ROG project is divided in two lots:  LOT A: new ROG Unit (U94) consisting of saturated and unsaturated Refinery Off Gases recovery train, new cooling towers installation, dedicated substation and instrument building.  LOT B: Modification of existing NC3 Crackers (U91) to process the stream from ROG Unit and interconnecting works foreseen within the project.

YEAR OF AWARD: 2014

START-UP: 2016

ENGINEERING HOURS: 380,000

CONSTRUCTION HOURS: 700,000

CAPACITY OF ROG UNIT: | | PROJECTSKT 1 Saturated Gas Train 39 t/h Off Gas;

1 Unsaturated Gas Train 30 t/h Off Gas COMPANY COMPANY PROFILE 22 REFINERY OFF GAS PROJECT (ROG PROJECT), ANTWERP (3/4)

KEY PROJECT FEATURES

LOT A  Highly congested ROG construction area and very limited availability of laydown areas at site and at TCF  Challenging /tight Project Schedule  Modularization approach was a key strategy for the Project and full modularization strategy has been developed during the FEED phase and endorsed during EPC.

LOT B  Extensive survey to identify tie-ins and study of confirm interconnecting piping routing  Execution of a high number of tie-ins  Strict coordination with refinery for scheduling erection works

| | PROJECTSKT inside the operating NC3 and especially during T/A. COMPANY COMPANY PROFILE REFINERY OFF GAS PROJECT (ROG PROJECT), ANTWERP

(4/4)

| | PROJECTSKT COMPANY COMPANY PROFILE 24 SONARA REFINERY EXPANSION PROJECT, LIMBE

New Units:  One Hydrocracker Unit (License by Axens)  Ancillary Units: HPU, SWS, ARU, SRU, Off Gas Recovery  One Cogeneration Train 15 MW Power  Storage Tank Farm

Interface with existing facilities:  Upgrade of: Flare, Instrument Air, Cooling Water, Fire Fighting systems  New Cogen Train to be installed in the area of an existing twin Package  Addtion of new equipment in existing VDU and Gasoline Stabilization Unit

The Expansion Project is aimed to increase the Refinery capacity from 2.1 to 3.5 MTA and increase the production of Gasoil.

CLIENT: SONARA (Societè Nationale de YEAR OF AWARD: 2013

Raffinage) START-UP: 2017 | | PROJECTSKT COUNTRY: Cameroun ENGINEERING HOURS: 500,000 CONTRACT TYPE: EPC - LSTK CONSTRUCTION HOURS: 4000,000 TOTAL CONTRACT VALUE: 450 M€

CAPACITY: 18,000 BPD COMPANY COMPANY PROFILE GAS COMPRESSION STATION, AL-ARISH

The Project consists of a Compression Station located at the Al-Arish Terminal in Egypt, a subsea pipeline from Al-Arish to Ashqelon, and the Ashqelon Receiving Terminal in Israel. The pipeline has an internal diameter of 26 in. with a total length of 89 km, of which 85.4 km is subsea. Natural gas is supplied to the Project from a connection to the 36 in. Trans-Sinai Gas pipeline. From Ashqelon, the natural gas enters the Israeli Natural Gas Transmission System. The Project is designed to ultimately supply up to 7.0 Billion Cubic Metres per Annum (“BCMA”) of Egyptian sales quality natural gas to Israel. The current transport capacity of the existing facilities is at least 3.5 BCMA. KT has been awarded an EPC-LSTK contract for both Compression Station and Receiving Station, and a PMC contract for the overall project management, including the subsea pipeline.

CLIENT: East Mediterranean Gas Company START-UP: 2008 COUNTRY: Egypt ENGINEERING HOURS: 73,000

| | PROJECTSKT CONTRACT TYPE: EPC - LSTK CONSTRUCTION HOURS: 43,000 TOTAL CONTRACT VALUE: €92 MN

YEARD OF AWARD: 2005 COMPANY COMPANY PROFILE 26 OIL AND GAS TREATMENT, TEMPA ROSSA

The Scope of work includes the central process facilities of the oil center where 50,000 barrels per day (BOPD) of crude oil are treated and stabilized and the treatment of the associated gas and water, the LPG storage center, the surface facilities on the well pads, the connections of the flowlines and pipelines with Snam Rete Gas and with Taranto Refinery pipeline.

CLIENT: Total E&P Italia SpA START-UP: 2015

| | PROJECTSKT COUNTRY: Italy ENGINEERING HOURS: 200,000 (KT portion) CONTRACT TYPE: EPC CONSTRUCTION HOURS: 1,000,000 (KT portion) TOTAL CONTRACT VALUE: US$600 MN (KT Portion: US$180 mn) CAPACITY: 50,000 BOPD Crude Oil

YEAR OF AWARD: 2012 COMPANY COMPANY PROFILE 27 OIL & GAS TREATMENT PLANT, LUBIATOW

Scope of Work was the development of the Pipelines for 14 Oil and associated Gas wells and the development of the Central Treatment Plant consisting of two identical lines.

CLIENT: PGNiG COUNTRY: Poland TOTAL CONTRACT VALUE: US$140 MN

CONTRACT TYPE: EPC CAPACITY: 1,300 t/d – Oil 12,590 Nm3/hr – Sales Gas

YEAR OF AWARD: 2008 START-UP: 2012

ENGINEERING HOURS: 160,000 | | PROJECTSKT

CONSTRUCTION HOURS: 1,200,000 COMPANY COMPANY PROFILE 28 MILD HYDROCRACKING UNIT, BUSALLA

The project includes the construction of a Mild Hydrocracker and a Hydrogen Unit, in addition to a major revamping of the refinery utilities and Infrastructure. The refinery has a crude capacity of about 2 millions metric tons per year.

CLIENT: IPLOM Refinery COUNTRY: Italy TOTAL CONTRACT VALUE: US$130 mn CONTRACT TYPE: EPC CAPACITY: 10,000 BBLD 1,400 t/d vacuum gasoil YEAR OF AWARD: 2008 START-UP: 2011

ENGINEERING HOURS: 150,000 | | PROJECTSKT

CONSTRUCTION HOURS: 1,000,000 COMPANY COMPANY PROFILE 29 HABSHAN 5 PROCESS PLANT, ABU DHABI

Scope of work of the JV Tecnimont – JGC is the development of the entire process facilities at Habshan which consists of: CLIENT: GASCO  Two trains of feed gas compression for the new associated gas COUNTRY: U.A.E. feeds CONTRACT TYPE: EPC (JV TCM-JGC)  One train of condensate stabilization CONTRACT VALUE: US$4,700 MN (TCM Portion 50%)

 Four gas sweetening and dehydration trains KT Subcontract: US$170 MN | | PROJECTSKT  Two rich gas NGL recovery trains (designed for high ethane CAPACITY: 2,000 SCFD recovery) YEAR OF AWARD: 2009  Four sulphur recovery units with associated tail gas treatment START-UP: 2013

facilities (total recovery 99.9+%) ENGINEERING HOURS: 200,000 COMPANY COMPANY PROFILE 30 SULPHUR AND GAS TREATMENT FACILITIES

COMPETENCES

 Leading Licensor and EPC Contractor  Tailor-made solutions  Full plant life cycle support  Extensive expertise plant revamping and retrofitting

HIGHLIGHTS Proprietary technologies for Gas Sweetening and Tail Gas

Treatment (RAR Technology)

| | PROJECTSKT COMPANY COMPANY PROFILE 31 RECENT SULPHUR RECOVERY AND GAS TREATMENT PROJECTS

(1/2) MOSCOW REFINERY SULPHUR RECOVERY UNIT (SRU) MOSCOW (RUSSIAN FEDERATION) CAPACITY: SRU 2x290t/d – Amine Recovery 2x240t/h SULPHUR RECOVERY UNIT (SRU) CLIENT: JSC Gazpromneft Moscow Refinery MOSCOW (RUSSIAN FEDERATION) CAPACITY: SRU 2x230t/d – TGT 1x460t/d SULPHUR RECOVERY UNIT – SOUR WATER STRIPPER – AMINE RECOVERY, CONTRACT TYPE: BEDP - LS MILAZZO (ITALY) CLIENT: JSC Gazpromneft CAPACITY: SRU 110 t/d – SWS 108 t/h - Amine Recovery 160 m3/h CONTRACT TYPE: B - LS CLIENT: RAM (Raffineria di Milazzo) CONTRACT TYPE: EPC - LS DUE DILIGENCE FEASIBILITY STUDY FOR NEW REFINERY MONGOLIA RCAPACITY 4600 t/d BASIC ENGINEERING DESIGN FOR SRU & TGT, FAJA DEL ORINOCO (VENEZUELA) CLIENT: MONGOL REFINERY CAPACITY: SRU 4x700 t/d – TGT 2x1400 t/d CONTRACT TYPE: Consultancy services CLIENT: PetroMiranda CONTRACT TYPE: BEDP - LS

BASIC ENGINEERING DESIGN FOR SRU & TGT, FAJA DEL ORINOCO (VENEZUELA) CAPACITY: SRU 3x540 t/d – TGT 2x1080 t/d CLIENT: Petrocarabobo SA CONTRACT TYPE: BEP - LS

SULPHUR RECOVERY UNIT FOR RAMP UP TO PLATEAU, ZOHR DEVELOPMENT PROJECT, SULPHUR RECOVERY UNIT (SRU) – TAIL GAS PORT SAID – EGYPT TREATMENT (TGT), BAKU (AZERBAIJAN) CAPACITY: N.3 Claus trains, SRU 12 t/d (each); N.2 TGT units with SO2 Scrubber, SRU 24 t/d (each) CAPACITY: SRU 2x30 t/d – TGT 1x40 t/d CLIENT: Belayim Petroleum Co. (PETROBEL) CLIENT: SOCAR CONTRACT TYPE: EP - LS CONTRACT TYPE: License + PDP - LS

SULPHUR RECOVERY UNIT, ZOHR DEVELOPMENT PROJECT, EGYPT COAST FEED FOR SO2 EMISSIONS REDUCTIONS PROJECT, PORT SAID – EGYPT MESAIEED (QATAR) CAPACITY: 4 x12t/d – TGT 2 x 24 t/d CLIENT: Q-CHEM

| | PROJECTSKT CLIENT: Belayim Petroleum Co. (PETROBEL) CONTRACT TYPE: FEED - LS CONTRACT TYPE: EP - LS

CLEAN FUEL & SULPHUR RECOVERY UNIT PROJECT SULPHUR RECOVERY UNIT, MOSTOROD (EGYPT) RABIGH (KINGDOM OF SAUDI ARABIA) CAPACITY: 320 t/d CAPACITY: NHT 17,000 b/d; SRU 290 t/d CLIENT: Egyptian Refining Company (ERC) CLIENT: Petro Rabigh (JV Saudi Aramco & Sumitomo Chemical)

CONTRACT TYPE: BEP, EP - LS CONTRACT TYPE: EPC - LS COMPANY COMPANY PROFILE

UNDER REALIZATION PROJECT COMPLETED PROJECT 32 SULPHUR RECOVERY UNITS – PHASE I & II - PORT SAID

KT has been awarded a new EP (Engineering & Procurement) contract by Belayim Petroleum Co. (PETROBEL) in the frame of the ZOHR DEVELOPMENT PROJECT, in Egypt.

The entire project consists in new Greenfields gas processing facilities at Zohr site in Port Said and will be developed in two different phases by Petrobel.

KT Scope of work consists of the supply of two modularized Sulphur recovery Units complete with Claus, TGT and AGE sections, and based on KT's Multipurpose TM proprietary technology. These two Units were delivered by KT as part of the Phase 1 Zohr Project, while two other Units relevant to Phase 2 will follow.

CLIENT: Belayim Petroleum Co. (PETROBEL) YEAR OF AWARD: 2017

COUNTRY: Egypt START-UP: 2021 | | PROJECTSKT CONTRACT TYPE:EP - LS ENGINEERING HOURS: 100,000 CAPACITY Phase I: N.4 Claus trains, SRU 12 t/d each No. 2 TGT with SO2 scrubber, SRU 24 t/d each

Phase II: No. 3 Claus trains, SRU 12 t/d each COMPANY COMPANY PROFILE No. 2 TGT with SO2 scrubber, SRU 24 t/d each 33 PETRO RABIGH, Clean Fuels & SRU, RABIGH

Rabigh Refining & Petrochemical Co. (Petro Rabigh) is a joint venture of Saudi Aramco and Sumitomo Chemical Co.

The Project aims to complete a Clean Fuels program at Petro Rabigh’s 400,000-barrels/day refinery and chemicals complex located in the port city of Rabigh, Kingdom of Saudi Arabia.

KT will provide engineering, procurement, and construction services for the project, which will include a 17,000-barrels/day naphtha hydrotreater, a 220 tons/day sulphur recovery unit, as well as related interconnecting works. The project completion is expected in the first-quarter of 2019.

KT is eager to continue to support Petro Rabigh in the technological development of one of the most strategic hydrocarbon processing complexes in the Country.

| | PROJECTSKT CLIENT: Petro Rabigh (JV CAPACITY: NHT 17,000 b/d; Saudi Aramco & Sumitomo SRU 290 t/d Chemical) YEAR OF AWARD: 2016 COUNTRY: KINGDOM OF SAUDI START-UP: 2019 ARABIA

CONTRACT TYPE: EPC - LS COMPANY COMPANY PROFILE 34 SULPHUR RECOVERY UNIT, MILAZZO

The scope of work consists of the following:  New SWS, ARU and SRU  New internals for vacuum column  New Slide cut for LC FINING  New cooling system  New vacuum system

CLIENT: Milazzo Refinery (RAM) COUNTRY: Italy CONTRACT TYPE: EPC TOTAL CONTRACT VALUE: US$85 MN SRU CAPACITY: 100 t/h (130t/h with enriched air) OGA CAPACITY: 150 t/h of rich amine solution SWS CAPACITY: 110 t/h of sour water VACUUM UNIT CAPACITY: 60,000 BPSD LC FINING CAPACITY: 26,000 BPSD

| | PROJECTSKT YEAR OF AWARD: 2012 ENGINEERING HOURS: 160,000 START-UP: 2015

CONSTRUCTION HOURS: 1,800,000 COMPANY COMPANY PROFILE 35 SULPHUR RECOVERY UNIT, BURGAS

The new SRU-4 is composed by the following sections:  Two identical sulphur recovery trains, with a capacity of 148 t/d of produced sulphur each

 A common Tail Gas Treatment (TGT) section including incinerator with a tail gas capacity corresponding to the total production of 296 t/d sulphur

 Sulphur solidification package (3x110 t/d Pastillating Units)

 Sulphur handling, storage (10,000 tons capacity) and loading.

CLIENT: OOO Lukoil Neftochim Burgas AD COUNTRY: Bulgaria CONTRACT TYPE: EPC - LSTK TOTAL CONTRACT VALUE: €53 MN CAPACITY: 200,000 BBLD YEAR OF AWARD: 2012 | | PROJECTSKT START-UP: 2014 ENGINEERING HOURS: 85,000

CONSTRUCTION HOURS: 500,000 COMPANY COMPANY PROFILE 36 RECENT SULPHUR RECOVERY AND GAS TREATMENT PROJECTS SRU/TGT CRITICAL EQUIPMENT SUPPLY, NOVOPOLOTSK (BIELARUS) (2/2) SULPHUR RECOVERY UNIT (SRU) – TAIL GAS CAPACITY: 226 t/d TREATMENT (TGT), BURGAS (BULGARIA) CLIENT: Naftan CAPACITY: SRU 2x148 t/d – TGT 296 t/d CONTRACT TYPE: BP - LS SULPHUR RECOVERY UNIT & TAIL GAS TREATMENT, CLIENT: Lukoil Neftochim Burgas AD NYNASHAMN (SWEDEN) CONTRACT TYPE: EPC - LS CAPACITY: 48 t/d CLIENT: Nynas Refinery AB CLAUS MODULAR PACKAGE UNIT, KHABAROVSK CONTRACT TYPE: EPC - LSTK (RUSSIAN FEDERATION) CAPACITY: 7.5 t/d CLIENT: Khabarovsk Oil Refinery CONTRACT TYPE: EP - LS SULPHUR PROJECT: SULPHUR RECOVERY PLANT, TAIL GAS TREATMENT, AMINE, SOUR WATER STRIPPER, GDANSK (POLAND) CAPACITY: SRU 2x75 t/d – TGT 150 t/d, Amine 8,400 t/d – SWS 1,560 t/d CLIENT: Grupa Lotos SA CONTRACT TYPE: EPC - LSTK

BASIC DESIGN & ENGINEERING PACKAGE FOR SRU, KARBALA (IRAQ) CAPACITY: 360 t/d CLIENT: SCOP (IRAQI STATE COMPANY FOR OIL 63 KT/A SULPHUR RECOVERY UNIT BAOTA PROJECTS) PETROCHEMICAL PROJECTS, XINJIANG (CHINA) CONTRACT TYPE: BEPD - LS CAPACITY: Claus: 1x180 t/d – TGT 1X180 t/d CLIENT: Jiangsu Sunpower Technology Co. Ltd CONTRACT TYPE: EP - LS

EXTENDED BASIC DESIGN PACKAGE, TECHNOLOGY PROVIDER AND SINGLE POINT OF RESPONSIBILITY FOR SULPHUR RECOVERY UNIT SINO-KUWAIT REFINERY AGR, SRU &TGT, SO2 SCRUBBER SYSTEM – JURASSIC PETROCHEMICAL INTEGRATED PROJECT, ZHANJIANG EPF, SRU – KUWAIT CITY (KUWAIT) (CHINA) CAPACITY: 1,100 t/d CAPACITY: 1,480 t/d CLIENT: Kuwait Oil Company CLIENT: China Petrochemical International Co. Ltd

CONTRACT TYPE: BEPD - LS CONTRACT TYPE: B - LS | | PROJECTSKT

SULPHUR RECOVERY UNIT 260 KTA CAPACITY, TIANJIN SRU & ACID GAS REMOVAL UNITS HABSHAN 5 ABU (CHINA) DHABI (UAE) CAPACITY: Claus 820 t/d, TGT 875 t/d CAPACITY: 4x1,300 t/d CLIENT: Petrochina Yunnan Petrochemical Co. Ltd CLIENT: GASCO

CONTRACT TYPE: EPCS - LS CONTRACT TYPE: B - LS COMPANY COMPANY PROFILE UNDER REALIZATION PROJECT COMPLETED PROJECT 37 SULPHUR COMPLEX, GDANSK

Scope of the work is the performance of an EPC LSTK project, including Engineering, Design, Supply of Equipment and Materials, Construction and Pre-commissioning of the New Sulphur Complex (KAS) of GLSA Gdansk Refinery, that will be necessary after completion of the new unit for achieve. Capacity of 10.5 millions metric tons per year.

CLIENT: Grupa Lotos SA COUNTRY: Poland CONTRACT TYPE: EP - LSTK TOTAL CONTRACT VALUE: US$ 150 MN AMINE UNIT: 350 t/h capacity SOUR WATER STRIPPER UNIT: 65 t/h capacity 2 SULPHUR RECOVERY UNITS: 75 t/d capacities each TAIL GAS TREATMENT UNIT: 150 t/d capacity | | PROJECTSKT YEAR OF AWARD: 2007 START-UP: 2009 ENGINEERING HOURS: 120,000

CONSTRUCTION HOURS: 1,000,000 COMPANY COMPANY PROFILE 38 SULPHUR RECOVERY UNIT, NYNASHAMN

The scope of work consists of the following:  New Sulphur Recovery Unit 24 t/d capacity  New Tail Gas Treatment Unit 48 t/d capacity Interconnecting Facilities  Sulphur Storage and Truck Loading  DCS and Substation

CLIENT: Nynas AB YEAR OF AWARD: 2010 COUNTRY: Sweden START-UP: 2012 CONTRACT TYPE: EPC - LSTK ENGINEERING HOURS: 130,000

TOTAL CONTRACT VALUE: €50 MN CONSTRUCTION HOURS: 600,000

| | PROJECTSKT COMPANY COMPANY PROFILE 39 HYDROGEN & SYNGAS PRODUCTION

COMPETENCES

 Leading Licensor and EPC Contractor  Tailor-made solutions  Full plant life cycle support  Extensive expertise plant revamping and retrofitting

HIGHLIGHTS Leading Company in providing hydrogen production units based on steam

reforming technology

| | PROJECTSKT COMPANY COMPANY PROFILE 40 COMPANY PROFILE | KT PROJECTS (1/2) RECENT HYDROGEN AND SYNGAS PROJECTS CONTRACT TYPE: EP CONTRACTTYPE: GAZPROMNEFT JSC CLIENT: Nm3/h 15,500 CAPACITY: (RUSSIA) OMSK PROJECT, FUEL OF DIESEL DEWAXING HDT, HPU, MODULARIZED CONTRACT TYPE: EPC CONTRACTTYPE: IPLOM CLIENT: Nm3/h 16,000 CAPACITY: (ITALY BUSALLA UNIT,PRODUCTION HYDROGEN CONTRACT TYPE: EPC CONTRACTTYPE: CLIENT: Nm3/h 15,000 CAPACITY: (SWEDEN) NYNASHAMN PLANT,GENERATION HYDROGEN UNDER REALIZATION PROJECTREALIZATIONUNDER Nynas Refinery AB Refinery - LS - - LS LSTK COMPLETED PROJECT COMPLETED ) CLIENT: North Refineries Company (Iraqi State Company For For Company State (Iraqi Company Refineries North CLIENT: FEASIBILITY STUDY, FEED, OBE (Open Book Estimation) AND AND Estimation) Book (OpenOBE FEED, STUDY, FEASIBILITY BASIC ENGINEERING DESIGN PACKAGE FOR HPU, NASSIRIYA NASSIRIYA HPU, FOR PACKAGE DESIGN ENGINEERING BASIC PSA (Pressure Swing Adsorption) SUPPLY FOR HYDROGEN HYDROGEN FOR SUPPLY Adsorption) Swing (Pressure PSA CLIENT: SCOP (Iraqi State Company For Oil Projects) Oil For Company State (Iraqi SCOP CLIENT: PRODUCTION UNIT, BAIJI (IRAQ) BAIJI UNIT,PRODUCTION CAPACITY: 2 x 188,000 Nm3/h 188,000 x 2 CAPACITY: CONTRACT TYPE: FS + EP + FS CONTRACTTYPE: CONTRACT TYPE: BEDP BEDP CONTRACTTYPE: CAPACITY: 72,000 Nm3/h 72,000 CAPACITY: Oil Projects) Oil (IRAQ) - - LS LS 41 HYDROGEN PRODUCTION UNIT, OMSK

The Scope of Work of KT covers the following:  Basic Engineering Design for the new Hydrogen Production Unit,

 Detailed Engineering Design

 Equipment and Materials Supply

 Fabrication of Modules

 Client’s Personnel Training

 Assistance during Construction, Precommissioning, Commissioning and Start Up of the Plant. The Hydrogen Production Unit will produce 12 t/y (15500 Nm3/h) of pure (99.9% vol.) Hydrogen.

CLIENT: JSC Gazpromneft CAPACITY: 15,500 Nm3/h of H2 COUNTRY: Russian Federation CONTRACT TYPE: EP | | PROJECTSKT TOTAL CONTRACT VALUE YEAR OF AWARD: 2015 Including Attachments: START-UP: 2018

Approx. 27,3 MM€ COMPANY COMPANY PROFILE 42 HYDROGEN GENERATION PLANT, NYNASHAMN

The hydrogen production rate is 15,000 Nm3/h in terms of pure hydrogen with both naphtha and natural gas feedstock.  Turn down ratio 30% (equivalent to 4,500 Nm3/h hydrogen production)  The cycle length based on catalyst lifetime is minimum four years. Time between turndowns is four years. The unit is designed for four years uninterrupted operation.  High availability and reliability of the unit is required. The availability is 99.0% or higher.

CLIENT: Nynas Refinery AB YEAR OF AWARD: 2008 COUNTRY: Sweden START-UP: 2010 | | PROJECTSKT TOTAL CONTRACT VALUE: €30 MN ENGINEERING HOURS: 60,000 CONTRACT TYPE: EPC - LSTK CONSTRUCTION HOURS: 200,000

CAPACITY: 15,000 Nm3/h as H2 COMPANY COMPANY PROFILE 43 COMPANY PROFILE | KT PROJECTS CONTRACT TYPE: EPC CONTRACTTYPE: CLIENT: CAPACITY: (POLAND) GDANSK HPU, CONTRACTOR: JV KT, OHL Industrial SL, Tapia SA Tapia SL, OHL Industrial KT,CONTRACTOR: JV CONTRACTEPC TYPE: Pemex CLIENT: CAPACITY: (MEXICO)MONTERREYCADEREYTA, REFINERY, CADEREYTAUNIT HYDROGEN PRODUCTIONNEW CONTRACT TYPE: EPC CONTRACTTYPE: INA CLIENT: Nm3/h 81,000 CAPACITY: (CROATIA) RIJEKA PLANT,GENERATION HYDROGEN (2/2) RECENT HYDROGEN AND SYNGAS PROJECTS UNDER REALIZATION PROJECTREALIZATIONUNDER LOTOS ASFALT SP. ZO.O SP. ASFALT LOTOS H2 H2 25,000 Nm3/h Nm3/h 25,000 Industrija - 28,000Nm3/h 28,000Nm3/h Refinaci - – - Nafte LSTK LS ό LSTK n COMPLETED PROJECT COMPLETED MODULARIZED HYDROGEN PRODUCTION PLANT, PERM’PLANT, PRODUCTION HYDROGEN MODULARIZED HYDROGENPRODUCTIONUNIT,MOSTOROD (EGYPT) STEAM REFORMER PACKAGE, AL JUBAIL (KINGDOM AL JUBAIL PACKAGE, REFORMERSTEAM CLIENT: HYDROGEN PLANT, MAZIEIKIAI (LITHUANIA)HYDROGENPLANT, MAZIEIKIAI CLIENT: Egyptian Refining Company (ERC) Company RefiningEgyptian CLIENT: SATORP (JV Saudi Aramco & Total) & Aramco Saudi SATORP(JV CLIENT: Lukoil CLIENT: CONTRACT TYPE: BEP, EP BEP, CONTRACTTYPE: CAPACITY: 2x132,000 Nm3/h 2x132,000 CAPACITY: CLIENT: CAPACITY: 100,000 Nm3/h 100,000 CAPACITY: CONTRACT TYPE: EPC CONTRACTTYPE: CAPACITY: 60,000 Nm3/h 60,000 CAPACITY: CONTRACT TYPE: EP CONTRACTTYPE: CAPACITY: 40,000 Nm3/h 40,000 CAPACITY: CONTRACT TYPE: EP CONTRACTTYPE: (RUSSIAN FEDERATION) (RUSSIAN Mazhieikiu OF SAUDI ARABIA) SAUDI OF Permnefteorgsintez Nafte - - - AB LS LS LS - LS 44 HYDROGEN PRODUCTION UNIT, RIJEKA

Scope of Work was the implementation, on EPC basis, of a 81,000 Nm3/h Hydrogen Production Unit.

The Plant configuration has been developed based on KT know- how in Hydrogen and Syngas production.

CLIENT: INA Industija Nafte DD YEAR OF AWARD: 2007 COUNTRY: Croatia START-UP: 2010 TOTAL CONTRACT VALUE: US$ 90 MN ENGINEERING HOURS: 100,000 CONTRACT TYPE: EPC CONSTRUCTION HOURS: 800,000

CAPACITY: 81,000 Nm3/h as H2

| | PROJECTSKT COMPANY COMPANY PROFILE 45 HYDROGEN PRODUCTION UNIT, MOSTOROD

The scope of work consists of HPU and SRU units for a Refinery expansion. The units will be designed, fabricated and fully modularized in order to minimize construction site activities.

CLIENT: GS/ERC COUNTRY: Egypt CONTRACT TYPE: EP Modularized TOTAL CONTRACT VALUE: US$150 MN CAPACITY:  100,000 Nm3/h of H2  3 Claus 162 T/day 1 TGT 325 T/day 1 Sulphur solidification of 325 T/day YEAR OF AWARD: 2012

START-UP: 2014 | | PROJECTSKT

ENGINEERING HOURS: 160,000 COMPANY COMPANY PROFILE 46 HYDROGEN PRODUCTION UNIT, PERM’

The plant is designed to produce 40,000 Nm3/h of Hydrogen. The design philosophy adopted is oriented in:  minimizing the raw materials and utilities consumptions in order to achieve the maximum Plant Efficiency for both operating cases with Hydrocarbon Gas and Natural Gas Feeds and, also, obtaining a valuable amount of steam export with no need for any steam level import  optimizing the plant configuration against the variable feedstock scenarios providing the technical solution for a modular execution strategy compatible with logistic constraints

CLIENT: OOO Lukoil CAPACITY: 40,000 Nm3/h Permnefteorgsintez YEAR OF AWARD: 2013 COUNTRY: Russia START-UP: 2014 TOTAL CONTRACT VALUE: €44,5 MN ENGINEERING HOURS: 64,000

| | PROJECTSKT CONTRACT TYPE: EP- LSTK COMPANY COMPANY PROFILE 47 HYDROGEN PLANT, MAZIEIKIAI

Scope of Work was the implementation, on EPC basis, of a 60,000 Nm3/h Hydrogen Production Unit. Plant configuration has been developed to handle multiple feedstock (Refinery off Gas and Liquid Butane) together with dual fuel to burners. In a conventional process scheme with primary reformer, HTS and PSA, provision of multiservice compressor system for feed and product, advanced control system and air preheating above 500°C are the main features of this unit to be highlighted.

CLIENT: AB Mazekiu Nafta COUNTRY: Lithuania TOTAL CONTRACT VALUE: €60 MN CONTRACT TYPE: EPC- LSTK CAPACITY: 60,000 Nm3/hr as H2 YEAR OF AWARD: 2006 START-UP: 2009 ENGINEERING HOURS: 100,000

CONSTRUCTION HOURS: 500,000

| | PROJECTSKT COMPANY COMPANY PROFILE 48 FIRED HEATERS AND HEAT TRANSFER EQUIPMENT

COMPETENCES

 Process, detailed mechanical design and supply all required materials  Revamping and debottlenecking services, after Sales services  Full plant life cycle support

HIGHLIGHTS Proprietary technology and know how Approved Supplier of major World Players: Bechtel (ThruPlus Coker Heaters), KBR (Ammonia Reformers), Aramco (Fired Heaters), Sasol

(GTL Heaters) and others

| | PROJECTSKT COMPANY COMPANY PROFILE 49 RECENT FIRED HEATERS AND HEAT TRANSFER EQUIPMENT PROJECTS

H2 STEAM REFORMER YANBU (KINGDOM OF SAUDI ARABIA) CAPACITY: 60,000 Nm3/h CLIENT: LUBEREF NEW TOPPING AND PREFLASH HEATERS, AMMONIA AND PROCESS OSBL PROJECT: KBR CONTRACT TYPE: EP - LS PRIMARY REFORMER, IOWA (USA) MAZIEIKIAI (LITHUANIA) CAPACITY: 2200 MTPD HEATER DUTY: 150 Gkcal/h CLIENT: Mazhieikiu Nafte AB CLIENT: Orascom Construction Industrie CONTRACT TYPE: EPC - LS CONTRACT TYPE: EP – LS N.2 EDC CRACKING HEATERS FOR PYROLISIS, SHANDONG (CHINA) CAPACITY: 2x59 t/h of EDC liquid CLIENT: Shandong Yangmeihengtong Chemical & Co. Ltd CONTRACT TYPE: EP - LS

N.2 KETENE CRACKING FURNACES, QINGDAO (CHINA) HEATER DUTY: 4,58 MW PROCESS GAS HEATER, ST. JAMES (LOUISIANA) CLIENT: Qindao Double Peach Specialty Chemicals (Group) HEATER DUTY: 247 MMkcal/h Co. Ltd CLIENT: Hyl Technologies S.A. DE C.V. CONTRACT TYPE: EP - LS CONTRACT TYPE: EP - LS

TOPPING REVAMPING FURNACES, LE HAVRE (FRANCE) HEATER DUTY: 150 Gkcal/h CLIENT: TOTAL CONTRACT TYPE: EP + assistance - LS + Construction

assistance reimbursable | | PROJECTSKT

REACTOR FEED HEATER, NAFTA SPLIT REBOILER, N.4 FIRED HEATERS KETENE CRACKING FURNACES ASC PHASE – VI PROJECT (PACKAGE-1) EDC PYROLYSIS EXTRACT HEATER – GDANSK (POLAND) YANBU (KINGDOM OF SAUDI ARABIA) FURNACE FU-C401A/B, ANYER – BANTEN (INDONESIA) HEATERS DUTY: 11.8 MW; 16,2 MW; 14,25 MW CLIENT: TOTAL DUTY: 30 MM kkcal/h HEATER DUTY: 2x81 t/h Grupa Lotos SA CLIENT: LUBEREF CLIENT: P.T. Asahimas Chemical (ASC), AGC Japan Group

CONTRACT TYPE: EPC - LS CONTRACT TYPE: EP - LS CONTRACT TYPE: EP - LS COMPANY COMPANY PROFILE UNDER REALIZATION PROJECT COMPLETED PROJECT 50 TOPPING AND PREFLASH UNIT, MAZIEIKIAI

The scope of works of this project will include the design, procurement, fabrication, installation of the following items:  New heaters built adjacent to the existing ones  Civil works for pre-assembly areas, and equipment foundations (fan and Air pre-heater ground mounted)  Piping Works  Instrumentation Works including field and DCS/ESD system in MCR.  Electrical Work including lighting, and power supply from/to local boxes/boards.  Removal of existing Heaters and replacing with the new ones.

The construction strategy was based on replacing the old heaters with new ones, by using the existing foundations; existing heaters have been jacked up and extracted from foundations by skidding or equivalent system (i.e. rollers), and left beside the actual plot area, leaving sufficient spaces for insertion of new heaters; afterwards the new pre-assembled

| | PROJECTSKT heaters have been moved with the same system and jacked down on foundations.

CLIENT: AB Mažeikių Nafta TOTAL CONTRACT VALUE: €25 MN ENGINEERING HOURS: 40,000 COUNTRY: Lithuania YEAR OF AWARD: 2005 CONSTRUCTION HOURS: 60,000

COMPANY COMPANY PROFILE CONTRACT TYPE: LSTK/EPC START-UP: 2006 51 RESEARCH & DEVELOPMENT ACTIVITIES

COMPETENCES

 Activities with international Industrial Partners, Universities and Research institutions  Funding from Italian Ministry of Education and European Commission

HIGHLIGHTS Development of innovative technologies

Design and realization of pilot plants

| | PROJECTSKT COMPANY COMPANY PROFILE 52 RECENT RESEARCH & DEVELOPMENT PROJECTS

PROMECA - PROCESS INTENSIFICATION THROUGH THE FISR PROJECT PILOT PLANT: MEMBRANE REFORMING REACTOR DEVELOPMENT OF INNOVATIVE MEMBRANES AND CATALYSTS FOR HYDROGEN PRODUCTION, CHIETI (ITALY) EINDHOVEN - THE NETHERLANDS CAPACITY: 20 Nm3/h Capacity: HP 1 Nm3/h CONTRACT TYPE: R&D Funded by EU R&D Contract founded by EU Coordinator: University of Salerno

INNOVATIVE CATALYTIC TECHNOLOGIES & MATERIALS FOR NEXT GAS-TO-LIQUID (NEXT-GTL), CHIETI (ITALY) CAPACITY: 20 Nm3/h DEMETO (De-polymerization by Microwaves Technology) CONTRACT TYPE: R&D Funded by EU CHIETI - ITALY CAPACITY: 100 kg/h (Pilot Plant capacity) CONTRACT TYPE: Horizon 2020, R&D Funded by EC COORDINATOR : Processi Innovativi

SOLAR COMPACT MULTIFUEL-ENERGY TO HYDROGEN CONVERTER (CoMETHy), ROME (ITALY) CAPACITY: 2 Nm3/h CONTRACT TYPE: R&D Funded by EC CONTRACTOR: Processi Innovativi

MULTIPURPOSE APPLICATIONS BY THERMODINAMICS SOLAR PROJECTS, ALEXANDRIA (EGYPT) CAPACITY: 100,000 Nm3/h CAPACITY: 1 Mwel (electic energy) – 250 m3/d (desalinated water) CONTRACT TYPE: R&D Funded by EU

DEVELOPMENT OF SYSTEMS FOR DISTRIBUTED HYDROGEN AND SYNGAS PRODUCTION BY MULTIFUEL CATALYTIC AUTOTHERMAL REFORMING (PON), SALERNO (ITALY) | | PROJECTSKT CAPACITY: 50 Nm3/h CONTRACT TYPE: EPC – LSTK R&D Funded by EC

CONTRACTOR: Processi Innovativi COMPANY COMPANY PROFILE UNDER REALIZATION PROJECT COMPLETED PROJECT 53 THE 2.0 GROUP MOTTOS

54 Maire Tecnimont Group’s Headquarters

Via Gaetano De Castillia, 6A 20124 Milan P. +39 02 6313.1 F. +39 02 6313.9052 [email protected]

KT – Kinetics Technology

Viale Castello della Magliana, 27 00148 Rome P. +39 06 60216.1 [email protected]