National Mission for Clean Ganga Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KARAMANA, S. Activity to be monitored Timeline Submission of progress by state/UT-Compliance status No. 1 Ensure 100% treatment of sewage at least in- 31/03/20 Sewage Generation -128 MLD(from Thiruvananthapuram situ remediation 20 Corporation area and adjoining local bodies ) Sewage Treated - 80 MLD Existing CSTP Capacity-107MLD(Muttathara, Trivandrum) Other Individual STP-3.57 MLD(from establishments like Highrise Buildings, Hospitals, etc. ) Progress on Expanding the sewage networks submitted by KWA attached Commencement of setting up of STPs and 31/03/20 Progress report on setting up connecting all the drains and other sources of 20 STPs connecting Drains are generation of sewage to the STPs must be not submitted ensured 2 Timeline for completing all steps of action 31/03/20 plans including completion of setting up STPs 20 and their Commissioning 5 Chief Secretaries may set up appropriate Vide G.O.(Rt)No.223/2020/WRD dated monitoring mechanism at state level 12.03.2020, Government of appointed  Specifying accountability of nodal a monitoring committee comprising of Additional Chief authorities not below the Secretary Secretary, Water Resources Department as level Chairperson and Principal Secretary, LSGD, Principal  Chief Secretaries may have an Secretary, Environment, Secretary, Water Resources accountable person attached in their Department and Staff officer to Chief Secretary as office for this purpose. nodal officers & members.  Monitoring at State level must take Fortnightl place y Commen cing 21.12.20 19 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources Complete including drains contributing to river d 11 Polluting Drains pollution and action as per NGT were identified order on in-situ treatment. Sewage Generation -128 MLD(from Thiruvananthapuram (II) Status of STPs, I&D and sewerage Corporation area and adjoining local bodies ) networks Details of Existing Sewage Treated - 80 MLD in 107 Infrastructure,Gap Analysis, MLD CSTP(Muttathara, Proposed along with completion Trivandrum) timeline Other Individual STPs-3.57 MLD(from establishments like Highrise Buildings, Hospitals, etc. ) Proposed expansion of sewer network , additional STP as mentioned in action plan submitted by KWA (III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, There is no existing CETP in Proposed along with completion polluted stretch. No CETP proposed as there are no timeline, No. of industries and industries identified in polluted stretch. complying status

(iv) Status of Solid Waste Management & Solid waste generated-353.58 TPD Details of Processing Facilities Solid waste treated -349 TPD Details of Existing Infrastructure,Gap Gap- 4.58 TPD Analysis, Proposed along with Details of Solid Waste Management is included in the completion timeline Action Plan.

(v)Latest water quality ofpolluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river; Water quality submitted as Annexures

(vi)Preventing dumping of waste and scientific  The Two Bridges in the polluted waste management including bio-medical Stretch(maruthoorkadav and thiruvallom) which waste, plastic waste and decentralizing were susceptible to waste dumping into the river waste processing, including waste was provided with fencing of adequate height. generated from hotels, Ashrams, etc.

(vii)Ground water regulation Restoration of waterbodies and cleaning of ponds and wells are done. (viii) Adopting good irrigation practices, Mentioned in status report submitted by Irrigation dept (ix) Protection and management of food plain Zones (FPZ), Mentioned in status report submitted by Irrigation dept

(x) Rain water harvesting, One of the major activities proposed for controlling flood in Thiruvananthapuram city is adoption of rain water harvesting and roof top rain water collection and storage system.

(xi)Maintaining minimum Environmental flow Mentioned in status report submitted by Irrigation dept of river

(xii) Plantation on both sides of the river Mentioned in status report submitted by Irrigation dept

(xiii) Setting up biodiversity parks on flood Bio- diversity park at Karamana II phase - walkway ,gate, plains by removing encroachment fencing, lightening etc-96% completed-Work in Progress.- Implemented by irrigation dept

ACTION PLAN FOR RIVER KARAMANA, KERALA

1. Short termplan

Progress in the Progress in the Progress in the Impleme month of month of month of No. Activity nting Time % works completed Details of works remaining November December line October agency When 50 % of sewage (35 MLD)was Pumping lines

diverted directly to the STP on from the completion of laying of pumping line terminal from Kuriyathy to STP, overflow to TS 2.1. pumping KWA May 100% 1 stations namely 2019 Canal has completely stopped. DER for Kuriyathi, replacing old pumping main from Pattoor, Pattoor and Kannanmoola submitted Kannammoola for AS. From Enchakkal only 5 MLD of and Enchakkal sewage is being pumped to stilling pumping chamber and hence urgent replacement not needed. stations are to be connected directly to STP at Muttathara

a. 7 m dia. 9 m deep RCC well -

Completed b)Grit chamber -completed c)Interconnection works between Thaliyal 73% 7% 5% 85% existing and newly constructed well and grit chamber

completed. Rehabilitation/u d) Erection of pump sets and diesel

pgradation of generator –Pump sets delivered at Thaliyal and site. 2.1. Aranoor KWA May 2 Sewerage Pump 2020 house by rehabilitation of existing well,

construction of b. a) Providing RCC lining for the new well and existing two wells Second well can grit chamber, be commenced only after erecting installation of new pump sets in the completed new pump well. Sets Arannoor25% 5% 5% 35% Pump sets supplied at site b) Diesel generator - orders placed by contactor. Notice issued to the Contractor for slow progress. Work restarted. Pump set erection in progress.

2.1. 5 MLD sewage KWA May 60% 5% 3% 68% Civil Works Completed 73%, works of 3 treatment 2020 Electrical plant at Medical & Mechanical components in progress. College Installation of

adequate 2.1. KWA Mar 5% 0% 0% 5% Order placed by Contractor. Pump pumps in 4 ch sets expected by first week of Mudavanmugh 202 January. al and 0 Enchakkal pumping stations

DG sets in all For Arannoor and Thaliyal Erection of

lift and diesel generator is already included in pumping the item mentioned 2.1.2 above 2.1. stations– KWA May 5% 0% 5% 10% 5 2020 For Enchakkal DG sets already exists. Mudavanmug Can be completed by Jan 2020 as DGs hal, Aranoor, expected to be arrived on middle of Thaliyal, January. Foundation work completed Kuriyathi, Pattoor, Kannammola, Pattom, Murinjapalam and Enchakkal

Reconnect sewer

at Rajaji Nagar, Foot path cutting requested from M/s 2.1 stop outflow of KWA Dec 5% 0% 0% 5% KRFB.Road restoration charges .6 2020 sewage into remitted. Road cutting sanction Amayizhanchant obtained. Directed Contractor to start the hodu, control work immediately. storm water entry into sewer Work revised by rerouting the pipeline to avoid through main road in front of KSRTC overflow in terminal at Thampanoor. Thampanoor area. Sewage generated in Rajaji Nagar shall be diverted to main sewer line. Sewage generated in Thoppil area shall be diverted main sewer line

Discharge of

sewage in

Parayilkadavu Rehabilitation work of existing pipe line shall be stopped is included in the work State Plan -2019- 2.1 KWA Compl 100 % .7 as there is eted completed 20- Rehabilitation of sewer line from overflow of Sathya Nagar to Karamana BHS and sewage reaches allied works. in houses having sewerage connection and this may lead to discharge of sewage into River Karamana Divert the sewer Work mentioned is same as the above line from the 2.1 KWA Award 100% work which is completed. .8 School ed completed compound of Government Karamana High School Works completed – 58 Nos. (Rs.12.21

cr.) AMRUT-37 Nos., Rehabilitation by State plan-19 Nos. MLA laying new lines ADF/SDF-2 Nos. 2.1 increasing size of KWA May 3% 5% 73% In progress – 18 Nos. (Rs. 6.04 .9 undersized main 2020 cr.) AMRUT-8 Nos., and 65% State plan-9 Nos. MLA reconstruction ADF/SDF-1 No. b y dilapidated manholes for the last 3 years Out of 4 works to be arranged

a) one work was approved by Board and waiting for Govt sanction.

b) 2 works-no offer on repeated tender, estimate being revised. Works completed - 16 Nos. (Rs. Extension of 2.82 cr.)

sewer network 2.1. KWA May 3% 2% 69% AMRUT-7 Nos., 10 wherever 2020 State plan-8 Nos. MLA

technically ADF/SDF-1 No.

feasible in new areas of existing 64% blocks

In progress – 9 Nos. (Rs. 15.65 cr.) AMRUT-5 Nos. State plan-4 Nos. 4 works need Land acquisition. Land To be arranged– acquisition process completed for one 4Nos. (Rs. 6.64 work and District Collector has Cr.) requested to remit State plan-4 2.3 Cr. urgently and the same is awaiting ways and means clearance in Secretariat.

Procurement Estimate re-casted, TS revised and

of sewer 2.1. KWA Mar 0% 0% 0% 0% re- tendered. No response to first 11 cleaning 2020 tender. Presently retendered. machines and equipment maintenance

* Out of the 100 wards in Thiruvanathapuram Corporation ,42wards (Blocks A to E) are fully/Partially covered with sewerage facility.For 35 wards ( Blocks F to R) design of sewerage networkis available but this needs modification in lieu of the change in demography and for the balance 23 wards new designs are to be prepared. The Long term measures are envisaged to cover the entire wards in the Thiruvananthapuram Corporation.For preparing DPR/DER for rehabilitation of existing sewerage system and for establishing sewerage system for uncovered areas of TVM corporation, an EoI has been called for. AS for the same is obtained under RKI (Govt. of Kerala)

Solid Waste Management ActionPlan

Implementing Time for Progress in the % works Details of Remarks Agency complet month of December complet works Sl.No Activity Unit ion till 01-01-2021 ed remaining Slaughter Thiruvananthapur Slaughter House- Work Work will ho use and am Corporation March awarded to KEL commence 2.2.1 Rendering plant poultry 2021 Agreement executed soon. duration-1 year. Site waste handed over. Sanitation Kumarichanda: STP facility and Plant (Bio membrane treat of Treatment plant bioreactor Technology- 10KLD) conducted trail waste water March run to check whether 2.2.2 in the 2020 the effluent is within markets of Portable aerobic permissible limit as per Pangode, bins KSPCB guidelines. Kumarichan Reports were da submitted by KSPCB. Pangode: Steps were taken to clean existing septic tank and an estimate amount of 28 lakhs prepared for establishing modern ETP. Project approved by DPC – Rennovation of pangode fish market ETP-25KLD. Thiruvananthapur Aero bins at various Work Awarded. Work is in Provide places(28) am Corporation Garbage: Regarding progress. facility for Solid Waste 2.2.3 Proposed sites the Management in treatment of 1. Moonnathumukku Poonthura Colony door to door collection sewage, – Purampoku 2. Poonthura – HI started and wet waste is

sullage and Office treated in Aerobic bin

garbage 3. Cheriyanmuttam– and dry waste to RRC. Poonthura generated in Regarding treatment of 4. Beemapally the Compound sullage, land availability is a problem Poonthura 5. TsunamiColony 6. Mother Theresa to establish a common slum area Colony treatment facility. So between 7. KumariChantha sucking tanker will be 8. PoonthuraMarket provided free of cost Karamana 9. Moonnattumukku and will be carried to river and sea bridge 10. Ambalathara– STP plant at Muttathara Nilama for safe disposal. 11. Fishermen Flat – Muttathara 12. PerunalliMarket road 13. Poundkadavuold market 14. Market behind Attipra zonaloffice March 15. Tsunami Colony 2020 near 110KV tower (Poundkadavu) 16. Near ValiyavilaVeli St. Thomas Church (Poundkadavu) 17. Near Kamalesshwaram HSS 18. Valiyaveetil Residence association 19. Near ArannoorGovt Quarters 20. Kunjalumoodu Junction 21. KumarapuramTha marabhagam(near comfortstation) 22. NaerKannammoola Bridge 23. Mannanthala Market 24. SanthiNagar Residents association 25. AlantharaKattayil 26. UlloorMarket 27. Museum RKVRoad 28. New NalanthaRoad

Thiruvananthapur Pond de-silting Joint inspection was Report to be The am Corporation conducted by submitted by discharge of Thiruvananthapuram KWA. waste water Corporation and KWA from the Issued notices to to identify the site for surrounding the household the installation of STP March and affected area is 2.2.4 houses to 2020 identified. Report is to the pond at be submitted by KWA. Jagathy is to Project is prepared be stopped for de-silting the pond 2.2.5 Around 155 Thiruvananthapur Proposal for septic Land required Houses in am Corporation tank and treatment for the Kurukuvilak system for 155 houses installation of STP. Report to om, in kurukuvilakom, Kannettumukku is be submitted Kannettum by KWA. ukku shall submitted by KWA. Conducted a joint be inspection by Tvmp provided Corporation and with septic KWA. and treatment system Identificatio Thiruvananthapur Fine imposed and 15.34 lakhs fine n of illegal am Corporation prosecution collected outlets into initiated

storm water 2.2.5 drains and fine shall be imposed on such units

Thiruvananthapur Regarding Three layers 50% Work is in 2.2.6 Bio-Composter am Corporation Bio-composter Bin (for progress, wet waste 25,000 units management in installed. Biodegradab May houses) supply order le waste 2020 issued and installation of fifty Thousand kitchen bin units is ongoing. DPR Sanctioned amount of State and Central share had released rupees 13,45,43,500 (partial). Work awarded. 25,000 units installed.

Thumboormuzhi Agreement Executed. 2.2.7 aerobic bins Work in progress. Work is 14 units of aerobins commencing installation in 4 sites –

completed. Santhikavada m(4 units), Mananthala (6 units), Kuriyathuvila – 1 unit, Attipra – 5 units.

2.2.8 Community biogas TS approved. For Agreement not agreement executed. execution temporarily send to council approval.

Organic Waste Site identified. Send to 2.2.9 Converter Project detailing council for

stage. review. 2.2.10 Thiruvananthapur Portable biogas Dropped

am Corporation

2.2.11 Portable aero bins Work awarded. T Temporarily extended as the delivery of parts of aerobin is delayed due to Covid 19 pandemic.

2.2.12 Ring compost Placed before council for Rejected by council

review. due to single agency in EOI.

2.2.13 Segregation bins Agreement Executed 2.2.14 Thiruvananthapur RRC Work in progress. Work am Corporation in Manacaud site is going Plastic Recycling Project detailing stage. Send to council for 2.2.15 unit review (Pending).

2.2.16 Mobile MRF Specification Finalized.

Electronic Weigh Land identified for EOI 2.2.17 bridge installation.

Solar electrical Tender will be through 2.2.18 Biodegradab cart GEM. le waste Specification finalized. 2.2.19 Swaps shops Agreement Executed, Work will commence Work order given. soon. PET bottle Agenda sent to HSC for 2.2.20 crushing review. (pending)

Community level Work Awarded. Work unit will commence soon. 2.2.21

Napkin destroyer Thiruvananthapur Animal TS Awaiting. 2.2.22 am Corporation Crematorium at Kattela

Thiruvananthapur Project dropped. 2.2.23 Urban Gardening am Corporation May 2020

Thiruvananthapur Upgradation of Agreement Executed. 50% 2.2.24 am Corporation present facilities Work is in progress. completed. Work completed in sites – Karamana palam, Kunjalamoodu, Poojapura, Maruthoorkadavu and

Attakolangara

Thiruvananthapur Capacity Building Process on going 2.2.25 am Corporation & IEC

Thiruvananthapur VGF 1st phase issued to 2.2.26 Viability gap Fund am Corporation Harithakarmasena (Green factory consositium, Sanjeevani charitable society, Centre for innovative waste management and agricultural technology) Prevent Thiruvananthapur KWA is authorized Close monitoring is done entry of am Corporation to prepare and by health Squad and all stormwater implement proper May Health Inspectors are 2.2.27 into sewer sewerage lines 2020 directed to issue notice and prosecution. line along under Amrut with KWA scheme Take steps Thiruvananthapur Squad andFines Employees were placed at to prevent am Corporation various spots during night Special squad is the solid to prevent dumping of formed at Solid Waste in drains. And wastes in Corporation level. fines are being charged. sewer line Health Inspectors Regarding to waste as reported May throwing to public place 2.2.28 are authorized for by KWA 2020 Corporation collected an regularly amount of Rs 480282/- as monitoring and fine from 01.01.2020. preventing the wastedischarge

Monitoring

Activity Implementing Time line Water quality Water quality in Water quality in agency in July/ pre- August/ post- monsoon monsoon monsoon 2.3.1 River water quality Kerala State Ongoing; Annex 1a, 1b, 1c nil monitoring - Killiyar, Pollution monthly Karamana, ControlBoard Parvathiputhanar, Akkulam-Veli lake

2.3.2 Storm drains Kerala State Ongoing Annex 2 nil monitoring - Pollution Seasonal Amayizhanchantho ControlBoard monitoring du, Ulloorthodu, – pre- Pattomthodu, monsoon, Kannamoolathodu, monsoon, Thekkanakkara canal post- monsoon 2.3.3 Inspection and Kerala State Ongoing effluent quality Pollution NIL NIL Interval: monitoring of the Control Board Red – 1

flats, industrial units, month. service stations, Orange – 3 m. hospitals, hotels etc Green – 6 in m. Thiruvananthapuram Corporation area

2. Long termPlan

Seweragenetwork

3.

Amount Progress in Progress in Long term Implementin Required Time % works Details of works the month of the month measures proposed g agency (Rs.in line completed remaining July of August Crore) Extension of sewerage system to Kerala Water Three 3.1.1 200 * Block F to G Authority years coastal belt Extension of Kerala Water

3.1.2 sewerage system to 700 * Authority Block H to R Extension of sewerage system to Kerala Water

3.1.3 300 * Newly added areas Authority of corporation viz, Providing Kerala Water

3.1.4 sewerage system in 100 * Authority Block A to E Rehabilitation of existing Kerala Water

3.1.5 Network and pump 100 * Authority house in block A to E Procurements of equipments for Kerala Water

3.1.6 10 * maintenance Authority sewerage system Additional STP Kerala Water

3.1.7 60 * requirement Authority Total Amount Kerala Water 1470 3.1.8 * required Authority Crores

Solid waste management

Long term measures Implementing agency Time Progress in the Progress in the Progress in % works Details proposed by line month of month of the month of completed of Thiruvananthapuram September October November works remaini ng 3.2.1 Acquire 58 acres of land and Thiruvananthapuram 5 Nil Nil Nil Nil Nil rehabilitate 8150 families Corporation years from the banks ofRiver

De-silting anddevelopment No. Activity amoun Implementing Timelin Progress Progress Progress % works Details of tin lakhs agency e in the in the in the completed works month month month remaining of Sept of Oct of Nov 3.3. Development package for Irrigation 3 years 1 ParvathyPuthanar departmentIncluded in KIFB by KWIL 15000 includes cleaning of canal Kerala water ways & Infrastructure Ltd, 3.3. De-silting and development of Irrigation 1.5 2 AmayizhanchanThodu Department years 2500 Tendered with opening date 21.7.2020.NO RESPONSE and RETENDERED with opening date 24.9.2020 3.3. Improvements to Irrigation 1 year 3. Thekkenekara canal and de- 500 Department silting- Estimate submitted for sanctin 3.3. Karimadam tank Irrigation 1.5year 4 improvements, de-silting sheet Department s 450 Estimate Amounting to Rs. 114 lakhs piling/under preparation and submitted for sanction (Price ID providing fencing 2020/4430/IA) 3.3. Development of Karamana Irrigation 1.5year 4 nos of works amounting to Rs. 200 lakhs 5 basin Department s submitted to ThiruvanathapuramCorpn. And 3 nos of works amounting to Rs. 477 lakhs the submitted to CE I&A TVPM,List is attached herewith

A) 4 nos of works amounting to Rs. 200 lakhs submitted to ThiruvanathapuramCorpn

i) NGT-Karamana River 677 basin- Construction of

protection wall on the breached portion of left bank Submitted to TVPM Corpn for sanction of Karamana river near (estimate-50 Lakhs) KaimanamMaha Vishnu Temple downstream of Pappanamcode iron bridge in Thiruvananthapuram corporation

ii) NGT-Karamana River basin- Fencing and silt removal for pollution Submitted to TVPM Corpn for sanction abatement initiatives for Killi (Amount-50 Lakhs) river in Thiruvananthapuram corporation. iii) NGT-Karamana River basin- Protection wall on the left side of Karamana river downstream Karamana bridge Submitted to TVPM Corpn for sanction near Kaladi check dam opposite (Amount -50 Lakhs) to Thaliyal Temple Kadavu in Thiruvananthapuram corporation

iv) NGT-Karamana River basin- Protection wall on the breached portion of right bank Submitted to TVPM Corpn for sanction of Karamana river upstream of (Amount -50 Lakhs) Kaimanam bridge near Sasthri Nagar in Thiruvananthapuram corporation. 3 nos of works amounting to Rs. 477 lakhs the submitted to CE I&A TVPM

i) NGT-Karamana River basin- Protection wall at RB of karamana River from Submitted to CE I& A TVPM for AttuppuramPallathukadavu in sanction Kaladi ward in Thiruvananthapuram (Amount -320 Lakhs) corporation. ii) NGT-Karamana River basin- Protection wall at RB Submitted to CE I& A TVPM for of karamana River near sanction Cocunut Valley in Kulasekharam in (Amount -45 Lakhs) Thiruvananthapuram corporation iii) NGT-Karamana River basin-Construction of shutters Submitted to CE I& A TVPM for at various portions in Karamana sanction River and KilliRiver in (Amount -112 Lakhs) Thiruvananthapuram corporation

STATE WATER MONITORING PROGRAMME (SWMP) 2020 Analysis Report for the month of DECEMBER-2020 Name of River KARAMANA Date and Time of Sample collection 16/12/2020 Method of analysis SAMPLE ID Sl no. Parameters Peppara Aruvikkara Mangatukadavu Pallathukadavu Thiruvallom Moonnattumukku 1 Temperature,degree celsius 27 27 28 27 27 27 2 pH 7.8 7.5 6.8 6.7 6.9 6.8 3 Turbidity,NTU 1.2 3.7 5.6 5.3 6.8 6.8 4 Electrical Conductivity, 29 76 84 128 245 324 5 DO,mg/l 6.6 6.1 5.1 3.4 3.2 2.2 6 BOD,mg/l 0.4 1 3.6 4.8 7.2 7.8 7 NH3N,mg/l BDL BDL BDL BDL BDL BDL 8 Nitrate,mg/l BDL BDL BDL BDL BDL 1.2 9 Chloride,mg/l 1 8 10 11 29 45 10 Phosphate,mg/l BDL BDL BDL BDL BDL BDL 11 Total Alkalinity,mg/l 12 23 23 54 75 82 12 Total Hardness,mg/l 16 29 32 54 77 100 13 Calcium,mg/l 11 23 26 44 61 78 14 Magnesium,mg/l 5 6 6 10 16 22 15 Sodium,mg/l 0.6 5.5 5.6 5.8 15.5 23.5 16 Potassium,mg/l 0 1.3 1.6 1.9 6.5 5.6 17 Boron,mg/l 0 0 0 0 0 0 18 SAR 0.037623 0.263768 0.25709 0.205113 0.456072 0.604659 19 TC,cfu/100ml 200 500 900 1000 4200 16200 20 FC,cfu/100ml 100 100 300 400 1100 5300 21 Faecal Streptococci ND ND ND ND ND ND POLLUTED STRETCH STATE WATER MONITORING PROGRAMME (SWMP) 2020 Analysis Report for the month of DECEMBER 2020 Name of River Killi Date and Time of Sample 3/12/2020 Method of analysis SAMPLE ID Sl no. Parameters Karipoor Vazhayila Maruthankuzhi Jagathy KILLIPPALAM 1 Temperature,degree celsius 27 27 28 27 27 2 pH 6.4 6.8 6.4 7.7 7.8 3 Turbidity,NTU 5.6 5.1 6.7 8.2 10.2 4 Electrical Conductivity, 78 94 108 124 168 5 DO,mg/l 6.7 6.1 4.9 2.5 1.8 6 BOD,mg/l 2.5 3 3.4 6.6 7.2 7 NH3N,mg/l BDL BDL BDL BDL BDL 8 Nitrate,mg/l BDL BDL BDL BDL BDL 9 Chloride,mg/l 9 10 13 14 24 10 Phosphate,mg/l BDL BDL BDL BDL BDL 11 Total Alkalinity,mg/l 22 30 32 40 46 12 Total Hardness,mg/l 32 39 41 44 52 13 Calcium,mg/l 24 27 30 34 42 14 Magnesium,mg/l 8 12 11 10 10 15 Sodium,mg/l 4.7 5.2 6.8 7.3 12.6 16 Potassium,mg/l 0.9 1.1 2.2 2.4 2.6 17 Boron,mg/l 0 0 0 0 0 18 SAR 0.211988 0.209122 0.269592 0.282584 0.453148 19 TC,cfu/100ml 500 1000 1200 1400 1500 20 FC,cfu/100ml 100 400 500 500 600

ASSISTANT SCIENTIST

Telephone: 0471-2303844

e.mail: [email protected]

KERALA STATE POLLUTION CONTROL BOARD t I c f k w Ø m \ a e n \ o I c W \ nb{´W t_mÀUv DISTRICT OFFICE, THIRUVANANTHAPURAM PnÃm Hm^okv, Xncph \ ´ ] p c w T. C. 12/96 (4,5), PLAMOODU JN., PATTOM P.O, THIRUVANANTHAPURAM – 695 004

Sn.kn. 12/96 (4,5), ¹maqSv PwKvj³, ]«w ]n.H, Xncph\´]pcw þ 695 004

ANALYSIS REPORT OF THODU (Post Monsoon 2020)

Date: 24/12 /2020

Sl.No Stations Sample PH BOD Collection (Mg/l) Date 1 Pattom Thodu 11/12/2020 7 12 2 Thekkummoodu, 11/12/2020 6.7 8.4 Marappalam(After) 3 Thekkummoodu, 11/12/2020 6.9 9 Marappalam(Before) 4 Ulloor Bridge 11/12/2020 7.1 20.4 5 Cosmo (Before) 11/12/2020 6.9 14.4 6 Cosmo (After) 11/12/2020 7.3 15 7 Kannammoola 11/12/2020 7.1 9 8 Kannammoola,Swathy 11/12/2020 7.3 10.8 Nagar 9 Pattoor,Bhagavathy 11/12/2020 7.2 12 Temple 10 Pattoor,Bhagavathy 11/12/2020 6.9 16.8 Temple (After) 11 PoonthyRaad, 03/12/2020 7.2 13.8 Kumarapuram 12 Kims (Before) 03/12/2020 7.4 4.2 13 Akkulam Boat Club 03/12/2020 7.6 6 14 Amayizhanjan Thodu 03/12/2020 7.2 13.8 (End)

Checked By:

Compared By: ASSISTANT SCIENTIST

0471-2303844

e.mail: [email protected]

KERALA STATE POLLUTION CONTROL BOARD [email protected]

t I c f k w Ø m \ a e n \ o I c W \ nb{´W t_mÀUv DISTRICT OFFICE, THIRUVANANTHAPURAM

PnÃm Hm^okv , X n c p h \ ´ ] p c w T. C. 12/96 (4,5), PLAMOODU JN., PATTOM P.O,THIRUVANANTHAPURAM – 695 004

Sn.kn. 12/96 (4,5), ¹maqSv PwKvj³, ]«w ]n.H, Xncph\´]pcw þ 695 004

Analysis Report of Drains (Post Monsoon) 2020

Sl.No STATIONS Sample pH BOD Collection Date 1 Pippinmoodu 21/12/2020 6.7 7.8

2 Mudavanmugal,Arattukadavu 21/12/2020 7.0 9.6 3 Jagathy Palam 21/12/2020 6.7 31.2 4 Chadiyara 21/12/2020 6.6 4.8 5 Thamalam 21/12/2020 7.2 10.8 6 Mangottukadavu 21/12/2020 7.1 15 7 Thaliyal, Iyiranimuttom 21/12/2020 7.2 15.6 8 Killippalam(Thoppilkadavu) 21/12/2020 7.2 6.6 9 Kuriathy 21/12/2020 7.0 15 10 Moonnattumukku 21/12/2020 7.1 9

ASSISTANT SCIENTIST National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER PAMBA, S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation 31.03.2020 Major hospital/hotel in the area established & are operating ETP regularly and it is monitored by the Board. Commencement of setting up of STPs and connecting all the drains 31.03.2020 STP not required. Action is being taken for installation and other sources of generation of sewage to the STPs must be of screening, septic tank & disinfection systems for ensured storm water drains in Mannar & town. 2 Timeline for completing all steps of action plans including 31.03.2020 Not complied as it is in preliminary stage. completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at 22.01.2020 Not applicable. District Level Technical Committee state level formed and is monitoring regularly.  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose

 Monitoring at State level must take place - Fortnightly Commencing 21.12.2019 6 Progress report may be furnished by the State/UTs to Monthly  Secretary,Ministry of Jal Shakti (preferably  Member Secretary,CPCB before 20th of every month) 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ Revised action plan already submitted treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure,Gap Analysis, Proposed along with No sewerage system .STP is not required as the towns completion timeline on the polluted river stretches are very small.

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, NA Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Consent to Establish issued for rendering plant of Details of Existing Infrastructure,Gap Analysis, Proposed along municipality.MCF and RRF already formed with completion timeline and working.Thumboormuzhi model aerobic composting established. (v)Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of Attached. polluted river;

(vi)Preventing dumping of waste and scientific waste management Rendering Plant coming up at Thiruvalla Town will including bio-medical waste, plastic waste and decentralizing help to reduce tendency of dumping slaughter house waste processing, including waste generated from hotels, waste in water bodies Ashrams, etc.

(vii)Ground water regulation Not much problem in the area

(viii) Adopting good irrigation practices Proposal submitted by Irrigation dept. waiting for

approval

(ix) Protection and management of food plain Zones (FPZ) -do-

(x) Rain water harvesting

(xi)Maintaining minimum Environmental flow of river 25 sites identified for dug well recharge through rain water harvesting (xii) Plantation on both sides of the river Minimum flow is there in the river (xiii)Setting up biodiversity parks on flood plains by removing encroachment Proposal submitted by Irrigation dept. waiting for approval

-do- ACTION PLAN FOR RIVER PAMBA, KERALA

No. Activity Implementing Time line Progress in the Progress in the Progress in the % works Details of works agency month of October month of November month of completed remaining (as per 2020 2020 December 2020 Action Plan)

A(a) No industries - - - -

A(a) Monitorng of river Kerala State Continuing water quality Pollution project Control Board C(ii) Establishment of Mannar 31.03.2021 Agreement with Work started Construction of 75% Construction and de-centralized solid Panchayat, M/s Floret one aerobic operation waste treatment Kadapra/ Technologies is compost unit is facility Niranam completed in executed and Panchayath the Grama worksite handed Panchayat over to them for Office starting compound. construction. Construction of another unit is started near

Mannar Private

Bus Stand

Not submitted Kadapra monthly progress

report for the

month of

December

Niranam GP is Niranam GP is Niranam GP is situated in upper situated in upper situated in upper region and Kuttanad region Kuttanad region Niranam GP always flooded and always and always

during rainy season flooded during flooded during so that land for rainy season so rainy season so Solid waste treatment that land for Solid that land for plant is not available waste treatment Solid waste there. plant is not treatment plant is available there. not available there. Haritha Karma Sena (HKS) has been constituted in all wards of Niranam GP for the door to door collection of solid non-bio degradable waste materials C Establishment of Mannar 31.03.2021 Door –to-door Materials 934.26 Kg of 80% Construction of Material Collection Panchayat, collection of non- collected at nonbiodegradable permenant MCF Facility Kadapra/ bio degradable temporary MCF plastic building,collection Niranam materials of and transportation of Mannar GP Plastic materials and are being Panchayath various grades Non-biodegradable has been segregated for has been Materials to RRF for inaugurated on transportation transported to processing. 04/11/2020. The ,material will be Clean Kerala materials collected handed over to Complany on will be kept in a clean kerala 17/12/2020. hall above the company after Second phase of collection Vridhasadanam segregation has started. building until sufficient quantity for transportation to

the RRF is

obtained.

Kadapra GP Not submitted monthly progress

report for the

month of

December

Niranam GP Haritha Karma Sena MCF is under 90% Balance will be (HKS) has been construction comopleted befpre constituted in all .90% of the work 3/3/2021 wards of Niranam has been GP for the door to completed.

door collection of

solid non-bio degradable waste materials. 1 Mini MCF for each wards (total-13) are completed. MCF is under construction 90 percentage of the construction work has been completed

C Resource Recovery Mannar 31.03.2021 As there is no As there is no As there is no 35% Collection and Facility Panchayat, RRF in RRF in RRF in Transportation of Kadapra/ Mannar GP Mavelikkara Mavelikkara Non-bio degradable Niranam Block Materials to RRF Block Panchayat Block Panchayat Panchayath Panchayat in For processing. in which Mannar in which Mannar which Mannar GP belongs, GP b GP belongs, nearby Block Panchayat nearby Chengannur has agreed to Chengannur Block Panchayat receive the Block has agreed to plastic materials Panchayat has agreed to receive the collected and receive the plastic materials transported by plastic collected and Mannar GP. materials transported by Mannar GP has collected and transported by Mannar GP. started Mannar GP. Mannar GP has stockpiling of Mannar GP has started plastic waste started stockpiling of materials stockpiling of plastic waste collected through plastic waste materials HKS in a hall materials collected through above the

HKS in a hall Vridhdhasadanam

above the owned by GP.

Vridhdhasadanam owned by GP.

Kadapra GP Not submitted

monthly progress report for the

month of

December

Niranam GP RRF is available in RRF is available Pulikeezhu GP and in Pulikeezhu GP Nedumbram GP. and Nedumbram These RRF shall GP. These RRF be used by shall be used by Niranam GP Niranam GP

C Installing Mannar 31.03.2021 Agreement with For community For Community 60% Construction and household and Panchayat M/s Floret level solid waste level solid operation of aerobic community level Technologies is management, waste compost unit solid waste management, executed and construction management units Construction of worksite handed aerobic compos one aerobic over to them for unit has started. compost unit is starting for house hold completed in construction. For level solid waste the Grama household solid management , Panchayat waste door- door Office compound. management, collection of non Construction of compost pit is –biodegradable another unit is being provided to plastic material started near individuals under using HKS is Mannar Private MGNREGS processing . For Bus Stand. As scheme,. degradable solid part of waste household level solid management , waste bio-compost unit management is being 934.26 Kg of constructed nonbiodegradable plastic materials of various grades has been transported to Clean Kerala Complany on 17/12/2020. Second phase of collection has started.

C Door to door Mannar 31.03.2021 Not included in door- door 934.26 Kg of 75% Collected material to collection and Panchayat the annual plan of collection of non – nonbiodegradable be handed over to biodegradable transportation of Mannar Grama plastic clean kerala municipal solid plastic material materials of Panchayat. company waste using HKS is various grades processing has been transported to Clean Kerala Company on 17/12/2020. Second phase of collection has started.

C Construction of Kadapra 31.12.2020 Not submitted small sewage Panchayat monthly progress treatment plant with report for the screening, septic month of tank and disinfection to the December storm water drain of Parumala Town C Construction of Mannar 31.12.2020 Not included in Due to the lack of Due to the lack 0% Not applicable small sewage Panchayat the annual plan of space and fund , of space and treatment plant with Mannar Grama construction of fund, construction of screening, septic Panchayat. small STP is not tank and small STP is not disinfection to the included annual included in the storm water drain plan of Mannar annual plan of of Mannar Town GP .It will be Mannar Grama suitable if the Panchayat. It Govt; takes will be suitable necessary steos in if the Govt . this matter takes necessary steps in this matter. C Construction of Irrigation 31.03.2021 Sent for FS Administrative 0 0 Awaiting for compound wall department approval sanction not yet sanction with fencing obtained

C Removing light Irrigation 31.03.2021 Sent for FS Administrative 0 0 Awaiting for jungle and muddies department approval sanction not yet sanction from river courses obtained

C Electrical-Light Irrigation 31.03.2021 Sent for FS Administrative 0 0 Awaiting for arrangements and department approval sanction not yet sanction Surveillance obtained cameras C Regualting activites Irrigation 31.03.2021 Nil Administrative 0 0 Awaiting for in flood plain zone, department sanction not yet sanction protection and obtained management of flood plain zone Greenery Irrigation 31.03.2021 Waiting for Administrative 0 0 Awaiting for developmentPlantat department financial Sanction sanction not yet sanction ion plan. Plantation from Chief obtained on both sides of the Engineer river, setting up biodiversity parks Irrigation on flood plains by &Administration , removing Thiruvanamthapu encroachment am C (b) Green Protocol Mannar, 31.05.2020 Green Protocol is Green Protocol is Due to the lack 100% Continuation of (ii) implementation in Kadapra/ strictly observed strictly observed of space and fund, Green all Offices Niranam in Mannar GP in Mannar GP construction of Protocol . small STP is not institution & Public Panchayat and other offices and other offices function included in the as well as public as well as public annual plan of functions . Strict functions . Strict Mannar Grama instruction in instruction in Panchayat. It writing is given to writing is given to will be suitable owners of owners of if the Govt . auditoriums , auditoriums , takes necessary steps in this assembly halls, assembly halls, matter. carry bags etc to comply etc to comply can be with Green with Green discouraged protocol while protocol while conducting conducting ceremonies. Rs. ceremonies. Rs. 1,50,000/- has 1,50,000/- has

been allocated for been allocated for

a project for the a project for the setting up of cloth setting up of cloth bag/paper bag bag/paper bag unit so that use of unit so that use of plastic carry bags plastic carry bags

can be can be

discouraged. discouraged.

Niranam GramaPanchayat has implemented 100% Green Protocol. All offices and institutions falling under the purview of the Gram Panchayat are being instructed to strictly implement the Green Protocol and ensure that it is implemented.

D(a) Issues relating to E- Irrigation 30.11.2020 Nil nil 10 20% 80% flow, maintaining department minimum environmental flow of river (by having watershed management provisions) D (b) Irrigation practices Irrigation 30.04.2020 Nil nil 0 0 Awaiting for department sanction E Awareness Kerala State 31.05.2020 - - programmes for Pollution sections of public Control Board C Management of LSGD 31.03.2021 Not included in As far municipal As for municipal 75% municipal, plastic, the annual plan of and plastic waste , and plastic waste, The process hazardous, Mannar Mannar Grama door-door using first phase door- is to be repeated to-door collection biomedical and Panchayat. HKS is periodically. electrical waste using Haritha Biomedical waste processing . For Karma Sena is is collected from management of completed and - source and electrical , 934.26 Kg of

transported for electronic and nonbiodegradable - processing by hazardous waste . Plastic materials IMAGE (IMA GP has reached in of different grades has been handed Goes Eco- an under standing over to Clean friendly), an with clean kerala Kerala company. initiative run by company . For the IMA (Indian Biomedical waste management Medical is collected from of electrical, Association).. sowrce and electronic and transported for hazardous waste, the processing by G.P has reached IMAGE an in an agreement initiative run by with Clean Kerala IMA Company. Collection and handing over of electrical,

electronic and

hazardous waste will start. Biomedical waste is being collected from source and transported for

processing by IMAGE (IMA Goes + Eco-friendly), an initiative

run by IMA (Indian Medical Association).

Kadapra Not submitted monthly progress report for the month of December

ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item nosActivity as per Progress in Progress in the Progress in the % works Details of No. NGT Order no.673/2018 the month of month of month of completed works dated 20.09.2018 October 2020 November 2020 December 2020 remaining 1 B(i) Ground Water NOC has not been NOC has not been issued to NOC has not been Demand based As per the GEC resources and issued to industries for gw extraction during issued to estimation all the regulation of industries for gw November 2020 industries for blocks in the ground water extraction during Ground Water District has been extraction by October 2020 extraction during categorized as industries December 2020 SAFE. particularly in

over exploited 2.Provisions of GW as critical zones/blocks (control &Regulation )Act 2002 is implementing stric tly for regulating extraction of GW resource in the district. 2 B(ii) Ground water Estimate prepared Estimate prepared and sent to Sanction from the The work will be All the blocks in the recharging / and sent to Director GWD for sanction. Directorate is implemented on district is rain water Director GWD for expecting soon. getting sanction categorized as SAFE harvesting sanction. from the as per GEC Director, GWD estimation. Kadapra-Niranam Area is not feasible for Ground Water Recharge. However, GW recharging programme is taken up in some pockets in the midland area where seasonal gw level fluctuation is noticed. 3 B(iii) Periodic ground mobile APP is mobile APP-“Neerarivu” is At present, the 1)Borewell/tube (1)Borewell/tube waste quality developed for developed for collecting the GW well census well construction well construction is assessment and collecting the GW abstraction details . Data programme is is regulated in the regulated in the remedial actions abstraction Collection will be started soon implementing district by district by insisting in case of details -well only in the over insisting permit permit of local contaminated census exploited, critical, of local bodies bodies based on ground water programme semi-critical based on the the feasibility tube wells/bore blocks. All the feasibility report report of GWD wells or hand blocks in of GWD . pumps pathanamthitta (ii)Well census District are programme- All the blocksIn categorized as pilot work started Pathanamthitta are safe hence the in the selected categorized as well census wards in the SAFE. Hence this programme could districts where activity cannot be not implemented over exploited, implemented in critical and semi before 31.3.21 Pathanamthitta critical blocks District during exists. All the this year. Hence blocks In this activity Pathanamthitta cannot be are categorized implemented as SAFE. Hence before 31.3.21 this activity cannot be implemented before 31.3.21 4 B(iv) For regulating Nil Nil use of ground water for irrigation

purpose, adopting good irrigation practices

Digitally signed by SUCHITRA V Date: 2021.01.16 15:48:58 SUCHITRA V +05'30'

Environmental Engineer

WATER QUALITY DATA OF POLLUTED RIVER STRETCHES DECEMBER - 2020

DISTRICT OFFICE, PATHANAMTHITTA

Date of Sampling: 24.12.2020

Sl.No PARAMETERS THAKAZHY EDATHUA MANNAR

1 Temperature ,ºC 28 28 28

2 pH 7.2 6.7 6.3

3 Turbidity ,NTU 2 2.3 3.0

4 Electrical 51.68 55.43 60.64 Conductivity ,µS/cm 5 DO, mg/L 6.5 6 4.8

6 BOD, mg/L 0.9 1.4 1.4

7 NH3N, mg/L 0.051 0.039 BDL

8 Nitrate , mg/L 0.418 0.398 0.519

9 Chloride mg/L, 14 14 12

10 Phosphate , mg/L - - -

11 Total Alkalinity, mg/L 11 9 10

12 Total Hardness, mg/L 30 30 22

13 Calcium , mg/L 22 20 14

14 Magnesium, mg/L 8 10 8

15 Sodium, mg/L 7.814 7.591 6.3

16 Pottassium , mg/L 1.113 1.533 0.793

17 Boron , mg/L - - -

18 SAR 0.6202 0.6025 0.58398

19 TC , CFU/100mL 230 300 480

20 FC, CFU/100mL 80 100 160

21 FS, CFU/100mL Nil Nil NIL

MONTHLY ANALYSIS REPORT OF POLLUTED RIVER STRETCHES DECEMBER- 2020

STATION : MANNAR

SAMPLING DATE : 18.12.2020

SI.NO PARAMETERES ITTINARAKADAVU KOTTAKAL KADAVU PARUMALA MANNAR BRIDGE BRIDGE BRIDGE BRIDGE KUTTAMPEROOR KORATTIKADAVU 1 Temp. (ºC) 29 29 29 29

2 pH 7.5 7 7.3 7.6

3 Conductivity 73.73 56.89 49.93 42.12 (µS/cm)

4 DO (mg/L) 3 4.5 5.4 6.9

5 BOD (mg/L) 2.5 1.5 1.1 0.5

6 COD (mg/L) 9.6 6.4 3.2 3.2

7 TDS (mg/L) 30 28 30 22

8 TC (CFU/100ml) 670 320 100 70

9 FC (CFU/100ml) 220 110 30 20

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER MANIMALA, S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ 31.03.2020 NIL remediation Commencement of setting up of STPs and connecting all 31.03.2020 NIL the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including 31.03.2021 NIL completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not 22.01.2020 below the Secretary level NIL  Chief Secretaries may have an accountable person 22.01.2020 attached in their office for this purpose  Monitoring at State level must take place Fortnightly NIL commencing 21.12.2019 6 Progress report may be furnished by the State/UTs to Monthly NIL  Secretary,Ministry of Jal Shakti (preferably  Member Secretary,CPCB before 20th of every month) 6.1 Progress Report may be comprised of details along with completion timelines on: Drains contributing to river pollution (I)Identification of polluting sources including drains 2019-2020 where identified. The drains are seasonal contributing to river pollution and action as per NGT and water quality is above the require order on in-situ treatment. limit, no insitu treatment is required.

(II) Status of STPs, I&D and sewerage networks Details of 2020-2021 Proposal for setting up an FSTP by Existing Infrastructure,Gap Analysis, Proposed along Chengannur municipality is initiated. with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap - Since the area does not contain any Analysis, Proposed along with completion timeline, industry and so no requirement of any No. of industries and complying status CETP, this action point is revised.

(iv)Status of Solid Waste Management & Details of The adjoining local bodies are in the Processing Facilities - stage of developing and establishing Details of Existing Infrastructure,Gap Analysis, adequate solid waste management Proposed along with completion timeline facilities also the solid waste dumping issues were not identified in the stretch during the field visit held during past 1 year.

(v)Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the 2019-2020 Water quality analysis result of the catchment of polluted river; stretch up to September is enclosed.

(vi)Preventing dumping of waste and scientific waste 2019-2020 Awareness campaign to be initiated. management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc. No ground water pollution is noted in the (vii)Ground water regulation 2020-2021 area, so action yet to be initiated

(viii) Adopting good irrigation practices 2020-2021 Action will be initiated.

(ix) Protection and management of food plain Zones (FPZ) Action will be initiated.

(x) Rain water harvesting Action will be initiated.

(xi)Maintaining minimum Environmental flow of river Action will be initiated.

(xii) Plantation on both sides of the river Action will be initiated.

(xiii)Setting up biodiversity parks on flood plains by removing encroachment Action will be initiated. ACTION PLAN FOR RIVER MANIMALA , KERALA

No. Activity Implementing agency Time line Progress in the Progress in the Progress in the % works Details of month of month of month of completed works (as per september October 2020 November 2020 remaining Action 2020 Plan)

A(a) Monitorng of river water quality Kerala State Continuing Result attached Pollution Control project Board A(b) Rendering Plant at Eraviperoor or Eraviperoor/ 31.03.2021 nil nil nil 0% Work to be Thiruvalla Thiruvalla local initiated body C(ii) Fencing of bridges, desilting, Irrigation 31.03.2021 nil nil nil 0% Work to be dredging and protection works, department initiated surveillance cameras at vantage points C Preventing illegal discharge of Panchayath, Police 31.05.2020. nil nil nil Nil Work septage and other waste water into , KSPCB pending due the river. Formation of River to COVID Protection Group pandemic C Greenery developmentPlantation Irrigation 31.03.2021 nil nil nil Nil Yet to be on both sides of the river, setting department in intiated. up biodiversity parks in flood association with plains and removing panchayath encroachment C(b)(ii) Green Protocol implementatio n in Kalloopara, 31.03.2020 Conducted Conducted Conducted 80 % - all offices, institution & public Eraviperoor, awareness awareness awareness functions Puramattom, programmes, programmes, programmes, Kaviyoor, media media media Peringara, Kuttoor publicity, panchayaths pamphlet publicity, publicity, distribution pamphlet pamphlet distribution distribution

D(a) Issues relating to E-flow, Irrigation 31.03.2021 - - - - Work to be maintaining minimum department, initiated environmental flow of river (by Hydrographic having watershed management survey department provisions) C(ii) Establishment of decentralized Kalloopara, 31.12.2020 MCF work Local protest workstopped 0 % 100 % solid waste treatment facilities Eraviperoor, started againt Puramattom, construction Kaviyoor, Peringara, Kuttoor panchayaths C Installing household & Kalloopara, 31.12.2020 Tendered 93 Completed 1 Completed 1 15 mini 91 community level solid and Eraviperoor, soakpit,93 soakpit,1 soakpit,1 MCFs,2 soakpit,91 domestic sewage waste Puramattom, compost compost pit.8 compost pit.7 soakpit,2 compost management Kaviyoor, pit,16 mini mini MCFs mini MCFs compost pit pit,1 mini Peringara, Kuttoor MCF panchayaths MCF C Door to door collection of solid Kalloopara, 31.12.2020 HKM tarted Stopped due Started D to D - - waste & Material Collection Eraviperoor, D to D to lack of collection Facilities (MCF) & Resource Puramattom, collection MCF. Revcovery Facilities (RRF) Kaviyoor, Peringara, Kuttoor panchayaths

ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item nos Activity Timeline Progres Progress in the Progress in the % Details of No as per NGT Order s in the month of October month of works works no.673/2018 dated month 2020 November complet remainin 20.09.2018 of 2020 ed g Septem ber 2020 1 B(i) Ground Water resources and regulation of ground 31.03.2021 water extraction by industries particularly in over exploited as critical zones/blocks 2 B(ii) Ground water recharging / rain water harvesting in 31.03.2021 Govt offices 3 NGT order in O.A NGT order in O.A no.496/2016 Identification of 31.03.2021 no.496/2016 illegal bore wells in the catchment area. Identification of illegal bore wells in the catchment area.

ANALYSIS RESULT OF KALLOOPARA 2020

MONTHS Parameters Unit FEB MAR APR MAY JUN JULY AUG SEP OCT NOV DEC PH - 6.8 6.9 6.9 7.1 6.6 6.8 6.7 7.8 6.9 6.9 6.8 7.1 Conductivity µS/cm 227 246 258 242 295 199 254.24 224.6 164 142 98 132 Turbidity NTU 0.9 0.9 0.9 0.9 1.1 0.9 1 0.8 BDL BDL BDL BDL DO mg/l 8.1 8.8 6.9 7.8 7.6 7.2 6.9 5.9 6.2 7.3 7.2 6.8 BOD mg/l 2.9 3.1 2.7 3 3.2 1.8 1.2 1.7 2.4 1.3 1.9 2.1 COD mg/l 8 12 16 8 16 4 4 8 16 4 8 4 Chloride mg/l 40 50 50 50 60 30 60 30 20 20 10 20 Sulphate mg/l 9.8 9.9 10.4 9.6 6.3 3.8 1.74 37.31 21.6 2.8736 3.1607 2.62 Phosphate mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL Nitrate Nitrogen mg/l 0.15 0.18 0.19 0.01 0.09 0.24 0.173 0.134 0.0841 0.198 0.31 0.122 Amm. Nitrogen mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL Alkalinity mg/l 40 50 50 60 40 60 50 30 20 50 40 50 T.Hardness mg/l 40 60 70 70 70 60 80 70 50 50 40 50 Ca. Hardness mg/l 20 30 40 40 40 40 40 40 30 20 20 30 Mg. Hardness mg/l 20 30 30 30 30 20 40 30 20 30 20 2 T D S mg/l 132.4 161.4 182.6 171.6 174.8 136.3 148.2 141.6 111 79 61.4 78.4 T F S mg/l 81.6 93.21 95.82 91.74 96.4 93.42 97.42 92.72 88.2 61.4 43.2 52.4 Fluoride mg/l 0.8 0.8 0.8 0.8 0.9 0.52 0.572 0.082 0.053 0.036 0.06 0.06 Sodium mg/l 25.1 26.4 27 25.06 22.1 17.3 19.6 13.8 11.2 30.3736 6.5 11.6 Potasssium mg/l 7.2 7.5 7.7 6.4 5.3 2.8 4.2 3.8 3.1 2.9 1.7 1.7 TSS mg/l 44.2 46.23 42.8 43.68 47.62 44.6 46.78 38.6 31.6 29.4 18.4 24.6 Tcoli No/100ml 500 900 700 500 200 200 500 900 1700 600 400 200 Fcoli No/100ml 300 400 300 200 100 100 200 500 900 400 300 100 Boron BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL TKN BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL

ANALYSIS RESULT OF THONDRA 2020

MONTHS Parameters Unit JAN FEB MAR APR MAY JUN JULY AUG SEP OCT NOV DEC PH - 6.8 6.8 6.8 6.9 6.5 6.9 6.8 7.4 6.9 6.9 6.8 7.1 Conductivity µS/cm 217 237.06 280 248 260 202 286.7 206.5 156 134 102 146 Turbidity NTU 0.8 0.9 0.9 0.7 0.9 0.8 0.9 1 BDL BDL BDL BDL DO mg/l 6.1 7.6 8.2 6.9 6.4 6.8 7.2 7.6 7.2 6.6 6.9 6.2 BOD mg/l 1.4 2.6 2.1 1.9 1.6 1.8 0.9 1.5 2.6 1.5 2.1 2.3 COD mg/l 12 20 16 16 8 4 8 8 16 4 8 16 Chloride mg/l 40 60 70 40 50 40 70 50 20 20 10 20 Sulphate mg/l 10.2 10.24 11 10.3 8 3.2 1.86 0.953 19.6 2.0638 3.92 2.92 Phosphate mg/l BDL BDL 0.1 BDL BDL BDL BDL BDL BDL BDL BDL BDL Nitrate Nitrogen mg/l 0.13 0.1363 0.14 0.01 0.02 0.17 0.182 0.14 0.054 0.113 0.266 0.233 Amm. Nitrogen mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL Alkalinity mg/l 40 50 60 70 50 70 40 50 30 40 30 60 T.Hardness mg/l 40 70 90 70 60 80 90 90 60 40 30 60 Ca. Hardness mg/l 20 30 50 40 30 30 50 60 30 20 10 30 Mg. Hardness mg/l 20 40 40 30 30 50 40 30 30 20 20 30 T D S mg/l 138.6 167.2 198.4 170.2 173.6 142.4 176.4 142.34 108 79.15 63.4 89.2 T F S mg/l 107.6 114.82 126.36 108.2 112.4 106.32 110.2 106.4 77.8 62.8 41.2 62.2 Fluoride mg/l 0.8 0.8 0.8 0.8 0.9 0.69 0.524 0.053 0.032 0.026 0.034 0.06 Sodium mg/l 54.4 27.84 28.5 25.8 24.6 16.7 18.7 11.2 10.6 10.2 7.4 11.2 Potasssium mg/l 5.8 6.2 6.8 5.1 4.9 3.2 3.8 2.1 1.8 1.8 1.4 2.1 TSS mg/l 31.8 43.2 45.8 42.82 34.2 31.6 36.4 31.2 26.8 21.4 19.2 26.2 Tcoli No/100ml 700 1000 1500 800 200 300 400 1100 1200 800 800 700 Fcoli No/100ml 400 500 800 300 100 200 400 600 700 500 500 400 Boron BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL TKN BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL

ANALYSIS REPORT OF DRAINS OF MANIMALA BETWEEN KALLOOPARA AND THONDRA NOV-2020

NOV DEC Sl. Bottle No No. Name Of Drains BOD COD TC BOD COD TC 1.8 4 3000 1 TK1 Panayampalathodu 3 20 5100 Padathupalam 2.2 8 2000 2 TK2 Thodu 2.1 8 2400 2.4 8 1000 3 TK3 Thottappuzha 1.8 8 200 Kuttapuzha under 2.1 8 1200 4 TK4 Kattodubridge 2.1 8 800 4.1 12 800 5 TK5 Kadavumbara 2.2 4 100 Drain under 3.8 12 1200 Varappalam 6 TK6 Bridge 4.8 24 600 Drain under 3.8 12 1400 7 TK7 kallupalam Bridge 1.8 16 2800 5.2 16 3600 8 TK8 Komalamthodu 3 8 2800 Vennikulam 3.4 12 1500 9 TK9 Valiyathodu 1.4 8 1900 2.6 8 1300 10 TK10 Paduthodu 2.1 8 2400 Mallappally 4.8 16 1800 11 TK11 Valiyathodu 1.4 16 1500

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER CHITHRAPUZHA. ERNAKULAM

S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ Major units have own treatment remediation facility Commencement of setting up of STPs and connecting all Not reported any progress by the drains and other sources of generation of sewage to Municipality the STPs must be ensured 2 Timeline for completing all steps of action plans including 3 years Proposed to construct completion of setting up STPs and their Commissioning (Thrippunithura Combined STP with the Municipality) Thrikkakara Municipality in Brahmapuram Plant(for both Municipalities) 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place District level committee monitoring regularly 6 Progress report may be furnished by the State/UTs to  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with Thrippunithura Ongonig completion timelines on: Municipality (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Submitted earlier Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Submitted earlier Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Plastic Waste given to a Government Details of Existing Infrastructure, Gap Analysis, Thrippunithura Approved agency for recycling Proposed along with completion timeline Municipality processing and Bio waste processed in Brahmapuram Plant.

(v) Latest water quality of polluted river, its tributaries, Analysis report by KSPCB is attached drains with flow details and ground water quality in (Annexure-I) the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste Thrippunithura Bio Medical waste given to IMAGE management including bio-medical waste, plastic Municipality and plastic waste given to waste and decentralizing waste processing, including government approved agencies, bio waste generated from hotels, Ashrams, etc. waste processing to Brahmapuram Plant.

As per Groundwater resources of Kerala, 2017 estimate a total number of 3 blocks(Edapally,Vadavukodu, Vazhakkulam) (vii)Ground water regulation comes under the Chithra puzha river basin. All Ground Water the blocks in the river stretch are safe with Department stage of groundwater extraction ranges from 25.38% to 56.63%. For Industrial extraction of groundwater Groundwater Authority is monitoring and regulating the activities.

Not submitted progress details by (viii) Adopting good irrigation practices Irrigation Department

Irrigation Not submitted (ix) Protection and management of food plain Zones (FPZ) Department

(x) Rain water harvesting Ground Water Studies for the implementation of Department Groundwater recharge structures are being conducted in the area.

(xi)Maintaining minimum Environmental flow of river Not reported any progress by Irrigation Department

(xii) Plantation on both sides of the river Thrippunithura Done Municipality

(xiii)Setting up biodiversity parks on flood plains by Thrippunithura Completed removing encroachment Municipality ACTION PLAN FOR RIVER CHITHRAPUZHA, KERALA

SHORT TERM MEASURES

No. Activity Implementing Time line Progress in Progress in the % works Details of works (as per agency the month of month of completed remaining Action November December 2020 Plan) 2020 (1) Drain joining Chithrappuzha (near Brahmapuram dumping yard) (Near FACT CD)

C (ii) Restricting seepage of leachate of plastic dumped 3 years Annexure II in the dumping yard Corporation Aa (iv) Effluent monitoring from FACT KSPCB Periodical Conducted Conducted Conducting Conducting Periodical Periodical monitoring monitoring

Aa (iv) Periodical Monitoring KSPCB Periodical Conducted Conducted -do- -do-

(2) Drain from Cochin Refinery area

Aa (iv) Surveillance to restrict the dumping of wastes into Vadavucode – Periodical Periodical monitoring : on going the river and its branches Panchayat with the help of Police A(b) Sanitation Survey Vadavucode – 3 months Not started; Process is on going Puthencruz Panchayat E Periodical Cleaning of Chithrapuzha Irrigation Twice in 3 For For Reach I, Wor For Department years Reach Agreement k not Reach I, work executed. yet III, Selecti start Estima AS on ed te approved notice submit For issued ted to Reach II CE Already implemented Effluent Treatment facility in KSPCB Ongoing Cochin Refinery and periodical monitoring are ongoing (3) Athikkayi branch (Provided temporary bund in joining section to check salinity intrusion)

A(b) Identification of major pollution causing 3 months On going units(Apartm ents, hospitals, service stations, Municipality markets and industries) in upstream KSPCB

Aa(iv) Surveillance to restrict the dumping of wastes into Thrikkakkara Periodical On going the river and its branches Municipality Monitoring with the help of Police Aa(iv) Periodical Monitoring KSPCB Periodical Conducted Conducted Conducting Conducting Periodical Periodical monitoring monitoring

A(b) Sanitation Survey Thrikkakara 6 months Ongoing Municipality E Periodical Cleaning Irrigation Once in a No further progress[Estimate Submitted to CE] Department year (4) Drain joining Chithrappuzha from CSEZ (Chittethukara)

A(b) Ensure proper functioning of ETP in CSEZ KSPCB Periodical Conducted Conducted Conducting Conducting Periodical Periodical monitoring monitoring

A(b) Sanitation Survey and periodical cleaning Thrikkakara 6 months Not submitted by Municipality Municipality

Aa(iv) Periodical Monitoring KSPCB Periodical Conducted Conducted Conducting Conducting Periodical Periodical monitoring monitoring

(5) Vettuvelikkadavu (Konothupuzha joining Chithrappuzha)

A(b) Identifying and closing of all unauthorized outlets Thripunithura 6 months Not submitted by Municipality into the stream joining the river Municipality A(b) Sanitation Survey Thripunithura 3 months Not submitted by Municipality Municipality Aa(iv) Periodical Monitoring KSPCB Periodical Conducted Conducted Conducting Conducting Periodical Periodical monitoring monitoring

C(ii) Surveillance to restrict the dumping of wastes into Thripunithura 6 months Not submitted by Municipality the river and its branches Municipality with the help of Police E Cleaning of Konothupuzha (work Proposal already Irrigation Twice in a Cleaning works are ongoing by Irrigation Dept and submitted by Minor Irrigation) Department year Thripunithura Municipality; (Minor Irrigation)

Main Stretch (Kadambrayar-Chithrappuzha Confluence point to Irumpanam)

E Periodic Cleaning Irrigation Once in a This reach included in the estimate of Chithrappuzha Department year Reach III[from Railway bridge to Kozhichira bund]. Estimated was submitted to CE. Work not started Vadavucode - Periodi cal Ongoing Puthercruz with Monito ring the help of Surveillance to restrict the dumping of wastes into Police C(ii) the river Thripunithura 6 months On going Muncipality with the help of Police Aa(iv) River water quality monitoring KSPCB Ongoing; Ongoing monthly frequency A(b) Inspection and effluent quality monitoring of the KSPCB Ongoing Ongoing flats, industrial units, service stations, hospitals, hotels etc C(ii) Surveillance to restrict dumping of waste to the Vadavukad 6 months Sanitation survey not started. Periodical monitoring to river, Sanitation survey (with the help of Police) Puthenkruze restrict dumping of waste is on going Panchayath

LONG TERM MEASURES

No. Activity Implementing Time line Progress in Progress in the % works Details of works (as per agency the month of month of completed remaining Action November December 2020 Plan) 2020 E Provide inspection bund for Chithrapuzha Irrigation 3 years No further progress[1.Estimate submitted to CE (As a Department preliminary step Soil investigation estimate is submitted) 2. Regarding demarcation of sides of Chithrapuzha, one corresponding village (Thiruvaniyur village) has given the survey nos. Therefore a letter has submitted to Thahasildar for taking the necessary action] A(b) Additional STP requirement (if needed) Thrikkakkara 3 years Not submitted Municipality, Thripunithura Municipality

Restriction of illegal dumping of Septage in to the Police ------river Flood Plain Zone(Management and Protection) Irrigation 3 years No further progress[Detailed study and investigations Preparation of Inundation maps Department has to be done with the consultation of Hydrology Wing]

ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item nos Activity Progress in the month of Progress in the month of % works Details of No. as per NGT Order September 2020 October 2020 completed works no.673/2018 remaining dated 20.09.2018 1 B(i) Ground Water resources and Not submitted Not submitted Not Not regulation of ground water submitted submitted extraction by industries particularly in over exploited as critical zones/blocks 2 B(ii) Ground water recharging / rain -- -- Not Not water harvesting submitted submitted 3 B(iii) Periodic ground waste quality Not submitted assessment and remedial actions in case of contaminated ground water tube wells/bore wells or hand pumps 4 B(iv) For regulating use of ground water Not submitted for irrigation purpose, adopting good irrigation practices

ANNEXURE-I(KSPCB) ANALYSIS REPORT

Sl. No. Parameters Irumpanam

1 Temperature, 0C 30 2 pH 5.4 3 Conductivity, µmhos/cm 550 4 Turbidity, NTU 0.4 5 Total Alkalinity, as CaCO3 7 6 Chloride, mg/l 117 7 COD, mg/l 12 8 TKN, mg/l 0.18 9 Ammoniacal-N, mg/l 0.1 10 Hardness, as CaCO3 mg/l 87 11 Calcium, as CaCO3 mg/l 9 12 Magnesium as CaCO3, mg/l 76 13 Sulphate, mg/l 39.5 14 Sodium, mg/l 79.03 15 Total Dissolved Solids, mg/l 300 16 Total Fixed Solids, mg/l 265 17 Total Suspended Solids, mg/l 18 18 Phosphate, mg/l 10.7 19 Boron, mg/l 0 20 Potassium, mg/l 3.62 21 BOD, mg/l 2.8 22 Fluoride, mg/l 0 23 Dissolved Oxygen, mg/l 2.3 24 Nitrate-N, mg/l 0.07 25 Total Coliform, MPN/100 ml 2600 26 Fecal Coliform, MPN/100 ml 1700 27 Fecal Streptococci 100

ANALYSIS REPORT(NOVEMBER 2020)

Sl. No. Parameters Irumpanam

1 Temperature, 0C 30 2 pH 6.2 3 Conductivity, µmhos/cm 280 4 Turbidity, NTU 1.1 5 Total Alkalinity, as CaCO3 38 6 Chloride, mg/l 34 7 COD, mg/l 6 8 TKN, mg/l 0.22 9 Ammoniacal-N, mg/l 0.03 10 Hardness, as CaCO3 mg/l 49 11 Calcium, as CaCO3 mg/l 19 12 Magnesium as CaCO3, mg/l 30 13 Sulphate, mg/l 30.32 14 Sodium, mg/l 22.09 15 Total Dissolved Solids, mg/l 153 16 Total Fixed Solids, mg/l 128 17 Total Suspended Solids, mg/l 15 18 Phosphate, mg/l 6.4 19 Boron, mg/l 0.01 20 Potassium, mg/l 2.27 21 BOD, mg/l 3.1 22 Fluoride, mg/l 0 23 Dissolved Oxygen, mg/l 2.6 24 Nitrate-N, mg/l 0.17 25 Total Coliform, MPN/100 ml 3800 26 Fecal Coliform, MPN/100 ml 1300 27 Fecal Streptococci 170

Analysis Report(October 2020)

Sl. No. Parameters Irumpanam 1 Temperature, 0C 29 2 pH 6.3 3 Conductivity, µmhos/cm 145 4 Turbidity, NTU 2.2 5 Total Alkalinity, as CaCO3 20 6 Chloride, mg/l 19 7 COD, mg/l 6.0 8 TKN, mg/l 0.20 9 Ammoniacal-N, mg/l 0.00 10 Hardness, as CaCO3 mg/l 36 11 Calcium, as CaCO3 mg/l 19 12 Magnesium as CaCO3, mg/l 17 13 Sulphate, mg/l 18.00 14 Sodium, mg/l 12.50 15 Total Dissolved Solids, mg/l 90 16 Total Fixed Solids, mg/l 78 17 Total Suspended Solids, mg/l 20 18 Phosphate, mg/l 0.00 19 Boron, mg/l 0.00 20 Potassium, mg/l 2.04 21 BOD, mg/l 1.8 22 Fluoride, mg/l 0 23 Dissolved Oxygen, mg/l 3.1 24 Nitrate-N, mg/l 0.18 25 Total Coliform, MPN/100 ml 3500 26 Fecal Coliform, MPN/100 ml 1000 27 Fecal Streptococci 170 Analysis Report(September 2020)

Sl. No. Parameters Irumpanam 1 Temperature, 0C 30 2 pH 6.7 3 Conductivity, µmhos/cm 138 4 Turbidity, NTU 0.4 5 Total Alkalinity, as CaCO3 25 6 Chloride, mg/l 14 7 COD, mg/l 6.4 8 TKN, mg/l 0.26 9 Ammoniacal-N, mg/l 0.01 10 Hardness, as CaCO3 mg/l 27 11 Calcium, as CaCO3 mg/l 5 12 Magnesium as CaCO3, mg/l 22 13 Sulphate, mg/l 17.28 14 Sodium, mg/l 9.78 15 Total Dissolved Solids, mg/l 78 16 Total Fixed Solids, mg/l 60 17 Total Suspended Solids, mg/l 12 18 Phosphate, mg/l 0.94 19 Boron, mg/l 0.03 20 Potassium, mg/l 1.56 21 BOD, mg/l 1.3 22 Fluoride, mg/l 0.12 23 Dissolved Oxygen, mg/l 3.9 24 Nitrate-N, mg/l 0.21 25 Total Coliform, MPN/100 ml 3300 26 Fecal Coliform, MPN/100 ml 1200 27 Fecal Streptococci 140 ANNEXURE-II(Kochi Corporation)

Sl. Activity Implementing Timeline Progress in Progress in % of Present status not No. agency November December works started/ongoing 2020 2020 completed

1 Provide proper APRIL 100% Construction of facilities for 2020 leachate Collection restricting the Kochi tank completed seepage of leachate Corporation 2 Provide proper March Leachate is Leachate is 100% - facilities for 2021 treating in treating in collecting and Sewage Sewage treating leachate treatment treatment Kochi plant at plant at Corporation Brahmapuram Brahmapuram 3 Solid waste KSIDC for December Bid evaluation No further - Govt. cancelled the treatment facility at Kochi 2023 is in progress. progress contract with the Brahmapuram/Waste Corporation Government concessionaire vide to Energy plant technical G.O (Rt)No. committee 805/2020/LSGD dated has to finalise 30/4/2020 KSIDC has the bid floated tender on 24/06/2020 with last date for submission of tenders on 30/07/2020. As

requested by the prospective bidders last date of submission of bids was extended till 14/09/2020

Sl. Activity Implementing Time Progress in Progress in December % of Details of Remarks/STATUS No. agency line November 2020 works works 2020 completed remaining

1 Restricting KSIDC, July Awaiting Requested NIT,Calicut - - KSIDC tendered the work on seepage Government 2021 approval of to conduct the drone 20/03/2020.2 Bids received. of of Kerala for the council survey. Awaiting the None of them found leachate Kochi for proposal of NIT for qualified. KSIDC has re- of plastic Corporation conducting conducting the drone tendered the work on 24/06/2020 with last date dumped drone survey survey. for submission of bids on in the for 27/08/2020. 3 Bids were dumping quantification received. Financial bids were yard of the legacy opened on 12/10/21

waste. . On 22/10/2021 Principal Secretary LSGD directed Kochi Corporation to examine the quantity of legacy waste. Requested NIT Calicut to conduct drone survey. National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KADAMBRAYAR, ERNAKULAM S. Activity to be monitored Timeline Submission of progress by No. State/UT-Compliance status 1 Ensure 100% treatment of sewage at least in-situ Major units have own treatment remediation facility Commencement of setting up of STPs and connecting all To allot land, Government procedure are the drains and other sources of generation of sewage to on going) the STPs must be ensured 2 Timeline for completing all steps of action plans including To allot land, Government procedure are completion of setting up STPs and their Commissioning on going) 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place District level committee monitoring regularly 6 Progress report may be furnished by the State/UTs to -  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with Sanitation survey completed by completion timelines on: Thrikkakkara Municipality; (I) Identification of polluting sources including drains Procedure to issue notices are on contributing to river pollution and action as per NGT going order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Submitted earlier Existing Infrastructure, Gap Analysis, Proposed along with completion timeline Submitted earlier (III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Sanitation survey completed by Details of Existing Infrastructure, Gap Analysis, Thrikkakkara Municipality; Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, Analysis report by KSPCB is drains with flow details and ground water quality in attached the catchment of polluted river; (Annexure-I)

(vi)Preventing dumping of waste and scientific waste Monitoring ongoing regularly; management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc. As per Groundwater resources of (vii)Ground water regulation Kerala, 2017 estimate a total number of 2 blocks (mulanthuruthi and vadavakkodu) comes under the kadambrayar river basin. All the blocks in the river stretch are safe with stage of groundwater extraction ranges from25.38% to 68.01%.Industrial extraction of groundwater being monitored and regulated by the Groundwater Authority

(viii) Adopting good irrigation practices Ground Water Department and Irrigation Department : : Not submitted

(ix) Protection and management of food plain Zones (FPZ) Added in Sl.No.7.1

Ground Water Department : Studies for the implementation of (x) Rain water harvesting groundwater recharge structures are going on in these blocks.

(xi)Maintaining minimum Environmental flow of river Not reported any progress by Irrigation Department and Ground Water Department

(xii) Plantation on both sides of the river Thrikkakkara Municipality: No further progress

(xiii)Setting up biodiversity parks on flood plains by Added in Sl.No.7.2 removing encroachment ACTION PLAN FOR RIVER KADAMBRAYAR, KERALA

SHORT TERM MEASURES

Short term plan

No. Activity Implementing Time line Progress in Progress % works Details of works (as per Action agency the month of in the completed remaining Plan) November month of 2020 December 2020 (1) Manakkakkadavu

2.1.2 C(ii) Surveillance to restrict the Kunnathunadu - The Police authority is conducting routine surveillance dumping of wastes into Panchayat and with operation so as to prevent any possible illegal activities river the help of Police which pollutes the river and its branches

(2) Canal joining Kadambrayar near Infopark Phase II No. Activity Implementing Time line Progress in the Progress % works Details of works (as per Action agency month of in the completed remaining Plan) November 2020 month of Decemb er 2020 2.2.1E Cleaning of thodu Kerala Irrigation 6 months Estimate No Work not - Department submitted to CE ( further started & Desilting of progress;

Padathikkara

Thodu)

Clear the

Vadavucode – jungles, - Puthencruz 6 months - Desiliting, Panchayat 100%

Surveillance to restrict the Vadavucode – - CCTV Camera installed preventing dumping of waste 2.2.3 dumping of wastes into river Puthencruz C(ii) and its branches Panchayat with the help of Police

Main Stream (Manakkadavu to Kadambrayar-Chithrappuzha Confluence point) (Provided temporary bund (Kozhichira Bund)in Kadambrayar-Chithrappuzha joining section to check salinity intrusion) No. Activity Implementing Time line Progress in the Progress % works Details of works (as per Action agency month of in the completed remaining Plan) November 2020 month of October 2020 A(b) Provide proper facilities Kochi Refer Annexure II for restricting the seepage Corporation of leachate

A(b) Provide proper facilities for Kochi Refer Annexure II collecting and treating Corporation leachate Action plan by Gramapanchayath

No. Activity Implementing Time line Progress in Progress in the % works Details of works (as per Action agency the month of month of completed remaining Plan) November December 2020 E Installation of CCTV camera Kunnathunadu 30.09.2019 - - 100% At Manakkakadavu

C(ii) Vadavukad puthenkruze Cleaning of Thodu 6 months No further Not submitted Clear progress; the jungles,

Desiliting , C(ii) Surveillance Vadavukad 2 months CCTV Camera installed preventing dumping of puthenkruze waste to restrict dumping of waste to the river and branches (with the help of Police) 1. Long term Plan

No. Activity Implementing Time line Progress in Progress % works completed Details of works (as per Action agency the month of in the remaining Plan) November month of 2020 December 4.5 Solid waste treatment Kochi Corporation Three years Refer Annexure II C(ii) facility at Brahmapuram DPR Preparation in 10 months (through consultants)

Restriction of illegal Police As soon as possible ------4.6 dumping of septage in to A(b) the river 3. REVISED ACTION PLAN

No. Activity Implementing Time line Progress in Progress % works Details of works (as per Action agency the month of in the completed remaining Plan) November month of 2020 December 2020 3.1 Slaughter house and poultry Thrikkakkara To allot land for installing To allot land, Government procedure are on going) waste plant, Government Municipality Rendering plant procedure are on going

3.2 Sanitation facility and treatment To allot land, Government procedure are on going) of waste water inthe markets Thrikkakkara Municipality Treatment plant 2020-21

Portable aerobic bins 2021-22

3.3 Thrikkakkara To allot land for To allot land, Government procedure are on going) Provide facility for the Municipality installing plant, treatment of sewage, Government procedures are on sullage and garbage going generated

Proposed places for the installation of Aerobins (1) Municipal office compound (2) NGO quarters (3) Kakkanad Market Near Eechamukku TV-Centre Anganavadi

3.4 Providing facility for restricting Thrikkakkara Notices Notices discharge of waste water Municipality issuing issuing from the surrounding houses to and and the river outlet outlet closing closing Outlet closing procedures are are on are on going on by issuing Notices going going 3.5 Providing effluent Thrikkakkara No further progress treatment plant for Municipality industries

3.6 Identification of illegal outlets Thrikkakkara Notices Notices into storm water drains and fine Municipality issuing issuing shall be imposed on such units – and and outlet 30 units outlet closing are closing on going are on going

3.7 Biodegradable waste Thrikkakkara Installed No further management Municipality biogas progress plants: Bio-Composter – 2000 No.s 48Nos Thumboormuzhi aerobic bins - 4 No.s Portable biogas – 1500 No.s Ring compost – 500 No.s Napkin destroyer – 6 No.s

Viability gap Fund 4. MONITORING

No. Activity Implementing Time line Progress in Progress in % works Details of works (as per Action agency the month of the month completed remaining Plan) November of 2020 December 2020 4.1 River water quality Kerala State Ongoing; Analysis Report Analysis Conducting Conducting attached Report Periodical Periodical monitoring – Monitoring of Pollution Control Monthly frequency water quality Board Annexure I attached monitoring monitoring Annexure I

4.2 Inspection and Kerala State Ongoing; Conduc Conducted Conducting Conducting effluent quality Pollution Control ted inspections Periodical Periodical monitoring of the flats, Board inspecti monitoring monitoring industrial units, service ons stations, hospitals, hotels etc

Monitoring of establishments, service stations, flats, industrial units 5. LONG TERM PLAN

No. Activity Implementing Time line Progress in Progress % works Details of works (as per Action agency the month of in the completed remaining Plan) November month of 2020 December 2020 5.1 Additional STP requirement Thrikkakkara 3 years To allot land, Government procedures are on going) DPR Preparation in 6 months Municipality (through consultants) To allot land, Government Procedure are ongoing

5.2 Acquiring of land and District Collector, 5 years Not submitted rehabilitate families from the Thrikkakkara banks of River Municipality, Revenue Dept

To allot land, Government Procedure are ongoing

DESILTING AND DEVELOPEMENT

No. Activity Implementing Time line Progress in the Progress in % works Details of works (as per Action agency month of the month of completed remaining Plan) November 2020 December 2020 5.3 Development package Irrigation 3 years 1. Estimate No submitted to further department CE (As a progre preliminary Inspection bund for ss Chithrapuzha and step Soil Kadambrayar are included in investigation this package. For this estimate is submitted) project, preliminary Demarcation investigation of site which of sides of includes survey of land to know its availability for Kadambrayar formation of side bund is essential which is to be provided with for tiles. The project also implementin includes side protection g this work. work of Chitrapuzha and Therefore Kadambrayar. letter Provision for handrails at the submitted to edge of the bund is given. correspondin Overall cost comes to 25 g Village Crore. The work is being Offices proposed urgently and will be submitted to higher authorities for financial sanction.

5.4 Desilting and development Irrigation 1 year (periodical Estimate submitted No to CE further Department cleaning - 4 months x3) progre (Removal of ss It includes clearing and water removing water hyacinth of hyacinth Kadambrayar , Chitrapuzha from and Edachirathodu near Kadambrayar Infopark phase II. This is to and Removal be done periodically (every of water four months), depending on hyacinth availability of fund. from Edachira Thodu)

5.5 sheet piling and providing Irrigation 1.5 years It can be No fencing Department included in further the estimate progre Fencing is provided in Sl.no 5.3 of ss construction of Inspection bund (Walk way). Now as a preliminary step Soil investigation estimate is submitted 5.6 Development of river basin Irrigation 1.5 years It is included No It includes cleaning and Department in the further removal of water hyacinth estimate of progre from rivers and maintain its Removal of ss natural flow, depending on water availability of fund. hyacinth from Kadambrayar and Removal of water hyacinth from Edachira Thodu 6. RECOMMENDATIONS BY KERALA STATE POLLUTION CONTROL BOARD

Activities for compliance with Solid Waste Management Rules, 2016; Bio-medical Waste Management Rules, 2016

No. Activity Implementing agency Time line Progress in Progress % works Details of works (as per Action the month of in the completed remaining Plan) November month of 2020 October 2020 6.1 Door-to-door collection and Thrikkakkara Municipality 100% transportation of MSW Local bodies of Census 100% door to door collection Town

Proposed Kerala Solid Waste Management Authority 6.2 Modern Solid Waste Thrikkakkara To allot land, Government procedures are on going) Treatment Plant Municipality (To allot land, Government Proposed Kerala Solid procedure are ongoing) Waste Management Authority Local bodies of Census Town

6.3 Rendering plant for Thrikkakkara To allot land, Government procedures are on going) slaughter house/poultry Municipality wastes

Proposed Kerala Solid Waste Management Authority 6.4 Common bio-medical Health Department Not submitted waste treatment facility

Proposed Kerala Solid Waste Management Authority 6.5 Regional sanitary landfill site District Collector Not submitted identification and land acquisition Local bodies Establishment and operation of Regional Sanitary Landfills Proposed Kerala State Waste Management Authority

7.OTHER ASPECTS

No. Activity Implementing Time line Progress in the Progress in the % works Details of (as per Action agency month of month of complete works Plan) November 2020 December 2020 d remaining 7.1 Flood plain zone Irrigation No No further management and E- flow Dept further progress maintaining progress [It is Flood plain zone included management & E-flow in the maintaining cleaning & estimate desilting, depending on of availability of fund. During Removal summer season Irrigation of water Department Provides hyacinth temporary bund to prevent the salt water intrusion due from to tidal effects. To maintain Kadambr natural flow, sluice gate is ayar and provided. During the low Removal tide, the shutter of the sluice of water gate is kept open to maintain minimum flow hyacinth from Edachira Thodu] 7.2 Development of bio diversity Thrikkakkara 1st Phase 2020-21 To allot land, Government procedures are on going) parks in banks Municipality 2nd Phase 2021-22

ANNEXURE-I(KSPCB) ANALYSIS REPORT(DECEMBER 2020)

Sl. No. Parameters Brahmapuram Manackakadavu

1 Temperature, 0C 30 29 2 pH 6.4 6.5 3 Conductivity, µmhos/cm 137 120 4 Turbidity, NTU 0.3 0.4 5 Total Alkalinity, as CaCO3 37 35 6 Chloride, mg/l 27 20 7 COD, mg/l 6 6 8 TKN, mg/l 0 0.1 9 Ammoniacal-N, mg/l 0 0.02 10 Hardness, as CaCO3 mg/l 35 30 11 Calcium, as CaCO3 mg/l 8 12 12 Magnesium as CaCO3, mg/l 27 18 13 Sulphate, mg/l 4.8 2.8 14 Sodium, mg/l 16.1 11.5 15 Total Dissolved Solids, mg/l 98 82 16 Total Fixed Solids, mg/l 86 72 17 Total Suspended Solids, mg/l 16 18 18 Phosphate, mg/l 0.08 0.04 19 Boron, mg/l 0 0 20 Potassium, mg/l 2.78 3.12 21 BOD, mg/l 1.6 2.2 22 Fluoride, mg/l 0 0 23 Dissolved Oxygen, mg/l 2.8 2.5 24 Nitrate-N, mg/l 0 0.03 25 Total Coliform, MPN/100 ml 1000 1200 26 Fecal Coliform, MPN/100 ml 630 400 27 Fecal Streptococci 94 100

ANALYSIS REPORT(November 2020)

Sl. No. Parameters Brahmapuram Manackakadavu

1 Temperature, 0C 30 28 2 pH 6.4 6.9 3 Conductivity, µmhos/cm 161 163 4 Turbidity, NTU 3.3 9.4 5 Total Alkalinity, as CaCO3 32 44 6 Chloride, mg/l 22 17 7 COD, mg/l 6 4 8 TKN, mg/l 0.21 0.35 9 Ammoniacal-N, mg/l 0 0.19 10 Hardness, as CaCO3 mg/l 25 27 11 Calcium, as CaCO3 mg/l 17 19 12 Magnesium as CaCO3, mg/l 8 8 13 Sulphate, mg/l 9.17 6.94 14 Sodium, mg/l 14.76 11 15 Total Dissolved Solids, mg/l 88 90 16 Total Fixed Solids, mg/l 75 78 17 Total Suspended Solids, mg/l 26 34 18 Phosphate, mg/l 0.09 0.04 19 Boron, mg/l 0 0 20 Potassium, mg/l 2.39 3.21 21 BOD, mg/l 2.1 1.2 22 Fluoride, mg/l 0 0 23 Dissolved Oxygen, mg/l 3.9 7.6 24 Nitrate-N, mg/l 0.14 0.15 25 Total Coliform, MPN/100 ml 2100 1400 26 Fecal Coliform, MPN/100 ml 1200 490 27 Fecal Streptococci 79 170

Analysis Report (October 2020)

Sl. Parameters Brahmapuram Manackakadavu No. 1 Temperature, 0C 29 28 2 pH 6.6 6.3 3 Conductivity, µmhos/cm 100 108 4 Turbidity, NTU 5 9 5 Total Alkalinity, as CaCO3 28 40 6 Chloride, mg/l 13 13 7 COD, mg/l 4.0 6.0 8 TKN, mg/l 0.31 0.2 9 Ammoniacal-N, mg/l 0 0.00 10 Hardness, as CaCO3 mg/l 18 22 11 Calcium, as CaCO3 mg/l 15 12 12 Magnesium as CaCO3, mg/l 3 10 13 Sulphate, mg/l 6.80 1.00 14 Sodium, mg/l 8.91 8.50 15 Total Dissolved Solids, mg/l 66 68 16 Total Fixed Solids, mg/l 52 72 17 Total Suspended Solids, mg/l 26 30 18 Phosphate, mg/l 0.00 0.00 19 Boron, mg/l 0.00 0.00 20 Potassium, mg/l 1.99 2.17 21 BOD, mg/l 0.3 1.9 22 Fluoride, mg/l 0.00 0.00 23 Dissolved Oxygen, mg/l 2.7 3.1 24 Nitrate-N, mg/l 0.26 0.19 25 Total Coliform, MPN/100 ml 2000 2400 26 Fecal Coliform, MPN/100 ml 920 2000 27 Fecal Streptococci 70 130

Analysis Report(SEPTEMBER 2020)

Sl. Parameters No. Brahmapuram Manackakadavu 1 Temperature, 0C 29 29 2 pH 6.6 6.8 3 Conductivity, µmhos/cm 90 85 4 Turbidity, NTU 6 1 5 Total Alkalinity, as CaCO3 22 27 6 Chloride, mg/l 12 10 7 COD, mg/l 6.4 12.0 8 TKN, mg/l 0.02 0.2 9 Ammoniacal-N, mg/l 0 0.01 10 Hardness, as CaCO3 mg/l 20 21 11 Calcium, as CaCO3 mg/l 7 4 12 Magnesium as CaCO3, mg/l 13 17 13 Sulphate, mg/l 8.19 5.39 14 Sodium, mg/l 7.47 7.70 15 Total Dissolved Solids, mg/l 58 56 16 Total Fixed Solids, mg/l 42 40 17 Total Suspended Solids, mg/l 22 15 18 Phosphate, mg/l 0.05 0.09 19 Boron, mg/l 0.04 0.03 20 Potassium, mg/l 1.46 1.39 21 BOD, mg/l 0.9 2.3 22 Fluoride, mg/l 0.02 0.03 23 Dissolved Oxygen, mg/l 3.1 3.5 24 Nitrate-N, mg/l 0.01 0.16 25 Total Coliform, MPN/100 ml 3400 3500 26 Fecal Coliform, MPN/100 ml 1100 1200 27 Fecal Streptococci 100 110 ANNEXURE-II(Kochi Corporation)

Sl. Activity Implementing Timeline Progress in Progress in % of Present status

No. agency November December works not 2020 2020 completed started/ongoing

1 Provide proper APRIL 100% Construction of facilities for 2020 leachate restricting the Kochi Collection tank seepage of leachate Corporation completed 2 Provide proper March Leachate is Leachate is 100% - facilities for 2021 treating in treating in collecting and Sewage Sewage treating leachate treatment treatment Kochi plant at plant at Corporation Brahmapuram Brahmapuram 3 Solid waste KSIDC for December Bid evaluation No further - Govt. cancelled treatment facility at Kochi 2023 is in progress. progress the contract with Brahmapuram/Waste Corporation Government the to Energy plant technical concessionaire committee vide G.O (Rt)No. 805/2020/LSGD has to finalise dated 30/4/2020 the bid KSIDC has floated tender on 24/06/2020 with last date for submission of tenders on 30/07/2020. As

requested by the prospective bidders last date of submission of bids was extended till 14/09/2020.

Sl. Activity Implementing Time Progress in Progress in December % of Details of Remarks/STATUS No. agency line November 2020 works works 2020 completed remaining

1 Restricting KSIDC, July Awaiting Requested NIT,Calicut - - KSIDC tendered the seepage Government 2021 approval of to conduct the drone work on of of Kerala for the council survey. Awaiting the 20/03/2020.2 Bids leachate Kochi for proposal of NIT for received. None of of plastic Corporation conducting conducting the drone them found qualified. KSIDC has dumped drone survey survey. re-tendered the in the for work on 24/06/2020 dumping quantification with last date for yard of the legacy submission of bids waste. . on 27/08/2020. 3 Bids were received. Financial bids were opened on 12/10/21 On 22/10/2021 Principal Secretary LSGD directed Kochi Corporation to examine the quantity of legacy waste. Requested NIT Calicut to conduct drone survey.

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER PERIYAR. ERNAKULAM S. Activity to be monitored Submission of progress by State/UT- No. Timeline Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii)Setting up biodiversity parks on flood plains by removing encroachment

ACTION PLAN FOR RIVER PERIYAR, KERALA

SHORT TERM MEASURES

No. Activity Implementing Time line Progress in the month Progress in the month of % works Details of works agency of November 2020 December 2020 complete remaining (as per d Action Plan)

1.A(b) Augmentation and Revamping of Dec 2019 Status not reported Tendering and execution existing STP at near Adwaitha Municipality process going on Ashramam and to increase the amending the Project to capacity of STP so as to treat more include Annual Maintenan sewage generated in the ce Contract as per the municipality technical report of Assistant Engineer (Implemen ting Officer), Aluva Municipality 2.A(b) Augmentation and Revamping of Aluva 2021 Status not reported Municipality exisiting STP at Aluva Market and Municipality formulated to increase the capacity of STP so project and as to treat more sewage generated budgeted an in the municipality amount of Rs. 10 lakhs. Since the matter is inter departmental, DLTC during the meeting requested to intervene in the issue. 3.A(b) Discharge of sewage from Aluva 2020 Status not reported Status not township to the River through Municipality reported drain near Periyar Hotel shall be stopped. 4.A(b) Identification of the Aluva 2020 Status not reported Status not establishments/commercial Municipality, reported complexes/flats/houses/hote ls etc KSPCB who is discharging the sewage to the public drain and to collect fine based on polluter pay principle 5.A(a)(iv) Periodical inspection in the KSPCB Periodical Routine Routine inspection Industries, Flats, hotels monitoring inspection is is going on of STP,ETP going on 6.C(ii) Installation of modern abattoirs Aluva March Status not reported Status not Municipality 2021 reported 7.A(b) Procurement of sewer cleaning Aluva March Status not reported Status not machines and equipment Municipality 2020 reported maintenance 8.E Installation of cameras at the waste Aluva 2020 Status not reported Status not dumping spots Municipality reported 9.A(b) Construction of retaining wall with Sept 2019 Foundation Tender process HDPE liner at Kalamassery dumping Municipality completed, completed and yard in order to prevent the construction of agreement executed and leachate discharge from the yard to retaining wall work work started Thoombungal Thodu started. 10.C(ii) Installation of plastic shredding unit Kalamassery June 2019 One plastic shredding One plastic shredding Municipality unit installed & unit installed & working working

11.A(a)(i Constitution of squads for night Kalamassery 2020 This road is included in This road is included in v) surveillance for finding the Municipality, Neval Armed Depot Neval Armed Depot area unauthorized dumping of sewage Police area which is highly which is highly security department at NAD wet lands Kalamassery security zone zone therefore necessary therefore necessary direction may be issued direction may be to NAD for night issued to NAD for surveillance or night surveillance as a installation of camera as permanent solution a permanent solution 12.A(b) Installation of common STP for Kalamassery Decemb ETP at municipal Common ETP is working Kalamassery Municipality and ETP Municipality er 2019 market is installed and at market at Municipal Market started working 13.A(a)(i Monitoring and surveillance of KSPCB 2019 Routine inspection is Routine inspection v) industries in Kalamassery Industrial going on is going on Estate in order to prevent unauthorized discharges to Muttar River 14.C(ii) Installation of modern abattoirs Kalamassery 2021 Site not identified Site not identified including poultry and meat Municipality, rendering plants. Industries Department (for land allotment) 15.A(b) Identification of the Kalamassery 2020 Preliminary inspection Common inspection in 25 establishments/commercial Municipality done. 8 notice issued places and given notice, complexes/flats/houses/hote ls etc 10 of them settled who is discharging the sewage to the public drain 16.E Installation of cameras at the waste Kalamassery 2020 Camera installed at 10 Camera installed at 10 dumping spots Municipality different locations different locations 17.A(b) Identification of sources of sewage 2020 Routine inspection is Conducted Joint discharged to drain near Pathalam Municipality, done inspection with bridge and action to stop the KSPCB (for KSPCB, PWD and monitoring) discharge which reach river Periyar Municipality from hotels, labour camps etc In officials case the quantity of sewage generated is assessed to be more STP need to be installed 18.E Installation of cameras at the waste Eloor Municipality 2020 Keltron installed the Status not reported 90% dumping spots Camera and all the hardware related work have been done and training regarding how to operate the software system has also conducted by keltron officials 19.A(a)( Periodical inspection in the KSPCB periodical Routine Routine inspection iv) Industries, Flats, hotels for inspection is is going on monitoring of STP,ETP located in going on Cochin corporation 20.A(a) Inventory of sources of pollution Kochi Municipal 3 months NA NA through a rapid study/Study for Corporation identification of pollution sources at Edapally thodu 21.E Issuing notice to the defaulters Kochi Municipal 4 months Details not Corporation provided

22.A(a)(i Periodical inspection in the flats, Kochi Municipal periodical Continued Continued Being carried v) hotels, shops located along the river Corporation out periodically 23.A(b) Identification of natural Irrigation 2 years 3 nos of work Identified some drains/thodu reaching river Periyar department completed, one is at drains and thodu and cleaning of weeds, grasses etc Alangad GP and two is reaching river Koovappady Periyar.Detailed panchayath. Desilting investigation needed Thoombungal thodu to identify all completed. drains.reported 24.C(iii) Clearing of weeds, grasses at the Irrigation 3 years Estimate submitted Estimate river bank in order to ensure the department for financial sanction submitted for smooth flow of water for following financial sanction projects. for following 1. Rejuvenation of projects. Periyar-Irrigation 1. Rrejuvenation of Investigation Periyar-Irrigation Subdivision Aluva- Investigation Desilting of Subdivision Aluva- Aaattipuzhathodu in Desilting of KarumalloorPanchay Aaattipuzhathodu ath for a cost of 20 in lakhs 2.Rejuvenation of KarumalloorPanch Periyar river - ayath for a cost of 20 lakhs Irrigation 2.Rejuvenation of Investigation Periyar river - Subdivision Aluva- Irrigation Desilting of Muttar Investigation river in Subdivision Aluva- U/SofManjummal Desilting of Muttar RCB for a cost of 25 river in lakhs U/SofManjummal 3.Rejuvenation of RCB for a cost of Periyar Irrigation 25 lakhs Investigation Sub 3.Rejuvenation of division Aluva - Periyar Irrigation Investigation Sub Desilting of Periyar division Aluva - River near Eloor Desilting of Periyar ferry in River near Eloor for a cost of 40 lakhs ferry in Varappuzha for a cost of 40 lakhs

25.D(a) Maintaining of Minimum flow in Irrigation 3 years Shutter Shutter operations river during lean period and department operations are are periodically periodical operation of Regulators at periodically done to maintain River in-order to maintain minimum done to minimum flow flow. maintain minimum flow 26.A(b) Common Effluent Treatment Plant Industries 2022 Revised estimate of Status not at Edayar Industrial Estate department KITCO forwarded to reported DI&C. Letter has forwarded to District collector for the cancellation of 2 acres of land belongs to M/s Periyar Chemicals Ltd to set up ETP plant. 27.A(b) Construction of internal roads and Industries 99% of drainage work Status not proper drainage in Edayar industrial department has been completed. reported estate GSB, Wet mixing completed. Taring work, Irish drainage has to be completed. 28.A(b) Installation of common discharge Industries 3 years Status not reported Status not reported pipe line at downstream of department, Pathalam Regulator Bridge Irrigation department 29.E Installation of Night vision KSPCB 2020 Instruction given to Instruction given to surveillance cameras at the River concerned agency concerned agency Bank side 30.A(a)(i Periodical Monitoring of Eloor, KSPCB 2020 Surveillance is Surveillance is v) Edayar, Kalamassery Industrial belts conducted periodically conducted periodically 31.A(a)(i Monitoring of quality of water at Kerala Water 2020 Status not reported Status not reported v) various intake point Authority 32.A(a)(i Installation of additional continuous KSPCB 2022 Installation of buoy v) online River water monitoring is to be completed station 33.A(b) Identification of the Kadungallur 2020 Status not 20 establishments/commercial Panchayath reported % complexes/flats/houses/hotels etc who is discharging the sewage to the public drain 34.E Installation of cameras at the waste Kadungallur 2020 Status not 0 implementation dumping spots Panchayath reported

35.A(b) Identification of the Choornikkara 2020 Sewage survey is Sewage survey is finished 100 Identification establishments/commercial Panchayath ongoing is over complexes/flats/houses/hote ls etc who is discharging the sewage to the public drain

36.E Installation of cameras at the waste Choornikkara 2020 Ongoing Ongoing 80 Will be dumping spots Panchayath finished by the end of Jan 2021

LONG TERM MEASURES

No. Activity Implementing Time Progress in the Progress in the % Details of works (as per agency line month of month of works remaining Action October 2020 November 2020 compl Plan) eted 1.A(b) Construction of walkway, ring roads etc at the Irrigation 4 Proposal and Status not Periyar River bank at industrial belt. department years investigation reported estimate for dyke wall, walkway etc is prepared and submitted for Govt approval 2.C(i) Fencing of the river banks along the stretches of Cochin 1-2 Status not Status not waste disposal (Edamula stretch) Municipal years reported. reported. Corporation

3.C(iii) Beautification of the river stretches (Edamula Cochin 1-2 Consent to Submitted The work of stretch) Municipal years Establish application for rejuvenation of Corporation Obtained, wetland clearance Edapally thodu is Application for to State Wetland included under CRZ clearance submitted, Authority the IURWTS DPR project of Kochi finalized/Got Metro Rail approved Limited. If any civil works are initiated by Corporation it will have to be dismantled when carrying out the work of river widening by KMRL

ACTION BY GROUND WATER DEPARTMENT

Sl. No. Ref para item nos Activity Progress in Progress in the Progress in % works Details of as per NGT Order the month month of the month of completed works no.673/2018 of August September October 2020 remaining dated 20.09.2018 1 B(i) Ground Water resources and regulation of ground water extraction by industries particularly in over exploited as critical zones/blocks 2 B(ii) Ground water recharging / rain water harvesting 3 B(iii) Periodic ground waste quality assessment and remedial actions in case of contaminated ground water tube wells/bore wells or hand pumps 4 B(iv) For regulating use of ground water for irrigation purpose, adopting good irrigation practices

(o J o ro s J @ J J J ) o) q c N q (f) @ N o F o o 6 o F c o o o o q CD (\ ro N (f) r\ t\ N co co ct! (o o) d c\ N t f- No o N c.l (o N J J J J (o t- o @ J o ) .o c\l N E fr @ u') o o o o o oo o d o F @ N (f) o a co co co d) o F.l @ @ In <; s N o -i ci .i =(J $ (o O) (r) d J J o $ J IJ1 o s I @ @ c? o o f- o o o o o o o o q \ o @ to N @ o dl q co ID CO f @ O) o c! N @ co v, FI d O) N s o o

IJ1 J F J J J J J oc o c! o o co (n o o 6 o t- o? o o (n o $ o o o il a o co co o d N o N o @ (o co co co d) d) co CO CO @ @ t{ N O) t.c, ci z = FI O) c.) e.

E o) N J J Ol J oq o (o s J (r) J o) o o @ N o In o o o o q o f q o to o o o F{ co gE (o o) @ $ (o lo o co e d! CD o c\l N s t- o ci e8R J @ J t to @ J J J J oo c! o (f) @ o fdR (o o) @ o @ o o d 6 o o o ul o o c\ 6 o co d! co c O) o (n @ lo s o) @ co co co CO ci @ FI c{ N @ v t\ Esff (o o== |r) o In J J N J (o J c.l o \ o @ ol F o o o o o @ o o @ o c{ o o N d) co t! \ o @ (o to co e co d! -i (o @ d o, lo @ o 2l EUH N N N ol o .nJ- o o-l d. o (n st J J J lrt J 2Z o F{ F o l u'! o a o CO r o) o f- o (n o t- o c q sf co co d! @ a N s (f) O) @ CI ct P;ft UI (o o, d ro @ o o o #l Pla $ @

@ o @ J J N o o o (f) rr, J J (f) o rr o 6 o o o ti=fr 4 (o (o o s c'i o c\ o @ t- o o tf @ co d) co rO N @ N o, o Cl) ct o - G3 @ @ lr) s s F c{ J J J ! J J J fr') o (f) o { @

c g q) f N o) a =o) c o) F (6 E f E z T

! g o o o o E q) .g E o o 6 o E (U o o) (J o o o- E (u (o .9 L o '6 U' oP col 0J o o) o po E (o ! o p E o o p o ct) (o o c (! c C tro (u o (u -o €o (u g o o -9 E o E _9o FE .c E z U) o o C' () -: L V' CL E 5lE a o O - F O 60 o) o (! (o o Nld) r() @ t- @ N (! ol z !Nl

io =35H3!E3=3=ptJrPE 5 o-E EE=3.E E:5E-gE E=^E J EFEs=!E$s;=P KERATA STATE POLLUTION CONTROL BOARD ENVIRONMENTAL SURVEILTANCE CENTRE, ELOOR ANALYSIS REPORT OF RIVER PERIYAR - DECEMBER- 2O2O Sampling point: PATHALAM BUND st.No Parameter Unit 05.12.2020 25.12.2020 oc 1 Temp 29.6 29.2 2 pH 6.4 6.1 3 Gonductivity ps 910 892

4 Turbiditv NTU 1 I 5 Chlorides mg/l 260 260 6 Hardness tl 190 190 7 D.O. II 5.4 4.8 I Galcium tl 40 40.8 9 Magnesium ta 21.87 21.384 tl 10 Ammoniacal Ntroqen 0.125 0.1 39 11 Phosphate ta BDL BDL 12 Total alkalinitv tl 20 20 13 BOD tl 08 0.6 14 Sulphate tl 6 6 15 Nitrates tl 0.165 BDL

16 TC cfu/100m1 1 900 2800 17 FC tl 600 1000 tl 18 FS NIL s NIL f ttF- j laditrt ;turr.)L P. R. ASSlSl.' r,-, SCIENTIST KERALA STATE POLLUTION CONTROL BOARD ENVIRONMENTAL SURVEILLANCE CENTRE, ELOOR ANALYSIS REPORT OF RIVER PERIYAR . DECEMBER- 2O2O Sampling point: PUTHALAM

Sl. No Parameter Unit 05.12.2020 25.12.2020 oc 1 Temp 29.8 29 2 pH 6.5 6.5 3 Gonductivity pS 437 429 4 Turbidity NTU 2 2 5 Ghlorides mg/l 130 r20 tt 6 Hardness 86 95 tl 7 D.O. 5 5.6 tl 8 Calcium L8.4 22.4 tl 9 Magnesium 9.72 9.477 tt 10 Ammoniacal Ntrogen 0.122 0.131

aa 11 Phosphate BDL BDL tt 12 Totalalkalinity 15 15 It 13 BOD L.t L.L tt 14 Sulphate 2 2 tl 15 Nitrate 0.106 BDL 16 TC cfu/l00m1 1800 2200 17 FC aa 500 700 18 FS NL NIL

s,tB\r[Q]1MOL TRtsi P. R. ASSISI ."'Fi-i SCIENTIST KERALA STATE POLLUTION CONTROL BOARD ENVIRONMENTAL SURVEILLANCE CENTRE' ELOOR ANALYSIS REPORT OF RIVER PERIYAR . DECEMBER 2O2O SamPling Point: PATHALAM BRIDGE

Sl. No Parameter Unit 05.12.2020 25.12.2020 oc 29.3 1 Temp 29.6 2 pH 6.6 6.2 3 ConductivitY pS 519 8L7 4 TurbidiW NTU L 1 5 Ghlorides mg/l 150 230 rl 6 Hardness 92 180 7 D.O. 5 6.5 8 Calcium 18.8 40 I 9 Magnesium 10.935 L9.44 10 Ammoniacal Ntrogen 0.112 0.145 tl 11 Phosphate BDL BDL 12 TotalalkalinitY 15 20 13 BOD L.1 0.8 14 Sulphate 8 4 t5 Nitrates 0.218 BDL 16 tc cfu/100m1 1600 2300 17 FC 400 800 tt 18 FS NIL sNIL rREES!l\$il rr"ror- P. R, pSSlSTaNT SCIgt't1151 KERALA STATE POLLUTION CONTROL BOARD ENVTRoNMENTAL suRVErLLAruce CirvrnE, ELooR ANALYSIS REPORT OF RIVER PERIYAR . DECEMBER 2O2O Sampting point: VETTUKADAVU

Sl. No Parameter Unit 05.12.2020 25.12.2020 I Temp c 29.6 29.2 2 pH 6.6 6.4 3 Conductivitv PS 71? 20220 4 Turbiditv a NTU 2 J 5 Chlorides mgl 210 5600 6 Hardness tl 150 4700 7 D.O. tl 4.9 6.6 8 Calcium tl 32 1480 9 Magnesium ll 17 01 461.7 10 Ammoniacal Ntrogen tl 0.13 I 0.153 1l Phosphate tl BDL BDL t2 Total alkalinitv tl 20 20 13 BOD 1.2 0.7 l4 Sulphate 8 52 15 Nitrates tl 0.235 BDL t6 TC cfu/100m1 I 800 2600 t7 FC 500 900 l8 FS ff NIL sML TREttAqsHlMoL P. R. ASSISTANT SCIENTIST KERALA STATE POTLUTION CONTROL BOARD ENVI RONMENTAL SURVEILTANCE CENTRE, ELOOR ANALYSIS REPORT OF RIVER PERIYAR - DECEMBER.2O2O Sampling point: MANJUMMAL BUND

SI.NO Parameter Unit 05j22020 25.12.2020 oc 1 Temp 28.2 29.3 2 pH 6.4 6.2 3 Conductivity us 719 584 4 Turbidity NTU 2 2 5 Chlorides mg/l 210 170 6 Hardness tl 160 110 7 D.O. la 47 6 I Calcium tt 36 22.4 I Magnesium tt 17.01 13.122 10 Ammoniacal Ntrogen tt 0.129 0.147 ta 11 Phosphate BDL BDL 12 Totalalkalinity tt 15 15 13 BOD It 1.5 0.9 14 Sulphate tl 3 3 15 Nitrates tl 0.248 BDL

16 TC cfu/l00m1 1700 1 700 17 FC tt 500 600 18 FS tl NIL NIL -Fh .-\8tz- TREEJS'Bktuol P. R. A861STANT SCIENTIST KERALA STATE POLTUTION CONTROL BOARD ENVIRONMENTAL SURVEILLANCE CENTRE, ELOOR ANATYSIS REPORT OF RIVER PERIYAR . DECEMBER- 2O2O Sampling point: ALUVA MANAppURAM

SI.NO Parameter Unit 05.12.2020 25.12.2020 oc 1 Temp 28.6 N 2 pH 66 o 3 Conductivity Fs 389 S 4 furbidity NTU 1 A 5 Chlorides mg/l 110 M I 6 ta Hardness 70 P 7 D.O. aa 5 L tt 8 Calcium 16 Mlagnesium l! I 7.29 N 10 Ammoniacal tl Ntrogen 0.1 35 G 11 Phosphate ta BDL tl 12 Totalalkalinity 20 13 BOD tl 1 14 Sulphate 6 15 Nitrates aa 0.261 16 TC cfu/l00m1 1400 17 FC ta 400 18 al FS NIL

tRt I'JIMOL P. R" rt ASSIST6,^IT SCIENT]ST National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KARUVANNUR, S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii)Setting up biodiversity parks on flood plains by removing encroachment ACTION PLAN FOR RIVER KARUVANNUR, KERALA SHORT TERM MEASURES

No. Activity Implementing Time line Progress in the Progress in Progress in % works Details of (as per agency month of July the month the month of complete works Action of August September d remainin Plan) g Thirukuzhythodu

A(a)(iv) Surveillance to restrict dumping of wastes into Vallachira 6 months ong ongoin Partially Survellia ongoing river and its branches Panchayat with oing g complete nce the help of Police d action taken b y ward level sanitaion commite e E Cleaning and desilting of canal Irrigation 4months Work Department and submitte Vallachira d in Panchayat CMDRF. FS not obtained . Thodu near Kadalassery bridge

A(b) Identification of pollution sources and surveillance Vallachira, 1 month ONGOING ON ONGOI PARTIALL Survellia to restrict dumping of wastes Pudukad & GOI NG Y nce Nenmanikkara NG COMPLE action Panchayats TED taken b y ward level sanitaion commite e E Cleaning and desilting Irrigation 4months 100 100 NA 10 Work Department and 0 submitte Vallachira d in Panchayat CMDRF. FS not obtained . Neerolithodu

E Cleaning and desilting Irrigation 4months Work Department submitte d in CMDRF. FS not obtained. Painkilikayal thodu

E Cleaning and desilting Irrigation 4months Work Department and submitt Vallachira ed in Panchayat CMDRF. FS not obtaine d. Kadathodu

A(b) Identification of pollution sources and surveillance Vallachira & 1 month ONGOING ONGOING ONGOING PARTIALL Survellia to restrict the dumping of wastes Nenmanikkara Y nce Panchayats COMPLE action TED taken b y ward level sanitaion commite e E Cleaning and desilting Irrigation 4months Work Department submitte d in CMDRF. FS not obtained . Main Stream –along Karuvannur

A(a)(iv) Periodic Surveillance to restrict the dumping of Irinjalakkuda Weekly waste into river and imposing Fine Municipality, Police Dept.

A(b) Sanitation Survey Irinjalakkuda 3 Months completed Municipality

A(b) Closing of all un authorized outlets leading to the Irinjalakkuda Nil river Municipality

A(b) Closing of all un authorized outlets in the drain Irinjalakkuda Nil leading to the river Municipality

E Boards to display slogans against littering waste in Irinjalakkuda 6 months various Places other IEC Activities Like posters, Municipality notices and classes Monitoring A(a)(iv) River water quality monitoring KSPCB Ongoing; monthly frequency A(b) Inspection & effluent quality monitoring of the Flats, KSPCB Ongoing industrial units, service stations, hospitals,hotels etc Long Term Plan

A(b) Sewage treatment facilities to all house holds Vallachira Grama 1 yr 82 91 100 CO 0 Panachayat M PL ET ED A(b) Construction of FSTP and STP Irinjalakkuda 2 years Municipal Municipality Council approved agencies for preparing DPR C(ii) Setting up of a modern crematorium at Vallachira Grama 2 years WORK NOT WORK WORK 0 Custodia Mandarakkadavu, Arattupuzha Panachayat DONE DUE TO NOT NOT n of this LACK OF FUND DONE DONE site is DUE TO DUE revenue LACK OF TO or FUND LACK irrigation OF departm FUND ent.Valla chira Panchaya th has two other cremitori ums.Mod ernizatio n of any cremetor iums have not undertak en due to lack of fund C(ii) Solid waste treatment facility Vallachira Grama 2 years Work not Work not Work not 0 Work Panachayat done due to done due done due to not lack of fund to lack of lack of fund done fund due to lack of fund C(ii) Construction of Windrow composting plant Irinjalakkuda 2 years Functioning Municipality well

E Rejuvenation of Kanathodu Irrigation 1 year Department

E Installation of CCTV for Surveillance to prevent the Irinjalakkuda 2 years Police dumping of waste in to the river Municipality Department installed CCTV NEAR Karuvannur bridge ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item nos Activity Progress in Progress in the % works Details No. as per NGT Order the month month of completed of works no.673/2018 of December remaini dated 20.09.2018 November 2020 ng 2020 1 B(i) Ground Water resources and regulation of ground According to water extraction by industries particularly in over the latest exploited as critical zones/blocks GEC report there is no critical / over exploited blocks in Thrissur Dt. 2 B(ii) Ground water recharging / rain water harvesting 3 B(iii) Periodic ground waste quality assessment and No water remedial actions in case of contaminated ground quality issues water tube wells/bore wells or hand pumps reported in the GWD water level monitoring wells. 4 B(iv) For regulating use of ground water for irrigation Suggestions purpose, adopting good irrigation practices given to farmers for Rain water harvesting to recharge aquifers.

ACTION PLAN BY GRAMAPANCHAYATH

No. Activity Implementing Time line Progress in Progress in the % works Details of (as per agency the month month of Dec completed works Action of ember 2020 remaining Plan) November 2020 C MANALIPUZHA RIVER PROTECTION -Jalaraksha Vallachira Grama 1 year NIL NIL 60% 600M Jeevaraksha - Manalipuzha conservation Panchayath C Setting up of Nursery for Bamboo seedlings in MGNREGS 31.03.2020 NOT NOT STARTED, 0 0 Kadalassery STARTED, SUITEABLE SUITEABLE PUBLIC PLACE PUBLIC NOT PLACE AVAILABLE NOT AVAILABLE C Side protection of Manalippuzha with organic MGNREGS 31.03.2020 NOT NOT 0 10 materials available locally EXE EXECUTE 0% CUT D ED C Side Protection of Manalippuzha with Bamboo MGNREGS 31.03.2020 1KM NIL 75% 25 plants BABOO % SAPLINGS PLANTED C Deepening & Protecting Muttikkal Thodu by MGNREGS 31.03.2020 COMPLET COMPLETED 100 0 Spreading Geo Textiles ED %

C Cluster 2-Kurumaly puzha sub river bed -Project 1 year document preparation Panchayath

C Manalippuzha River Protection-Jala Raksha, Jeeva Nenmenikkara 31.03.2020 3.5 Raksha , Survey and Tree Plantation Grama Panchayat k.m.survey out of 7.5 k.m. completed & survey posts have been fixed C Manalipuzha River protection MGNREGS 31.03.2020 A(b) Protection and reconstruction and protection of MGNREGS 31.03.2020 Paliyekkara Kayalathod

A(b) Reconstruction and protection of Paliyekkara MGNREGS 31.03.2020 Karama Thodu

KARUVANUR Date of sampling - 07.12.2020 SL. No. PARAMETER UNIT KT MRK KND MDK THR KRV 1 PH 5.7 5.6 5.3 7.4 6.3 6.2 2 EC µ/cm 130 103 106 118 71 170 3 BOD mg/L 2.3 2.1 1.1 1.5 2.2 2 4 DO mg/L 7.5 6.8 5 6 7 6 5 COD mg/L 4 16 8 12 12 8 6 TC CFU/100ml 400 300 400 200 200 200 7 FC CFU/100ml 200 100 100 100 100 100

KT - KANAKKAN KADAVU, KARUVANNUR MRK - NEEROLI THODU, KARUVANNUR KND - KANATHODU, KARUVANNUR MDK - MUTTIKKAL DAM, KARUVANNUR THR- THIRUKUZHI, KARUVANNUR KRV - PAINKILIKAYAL THODU, KARUVANNUR

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KECHERY, THRISSUR – December 2020 S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ DPR submitted before KIIFB Modern remediation 31.12.2021 Market with STP at Ottupara (18 KLD) & Athani (14.9 KLD) Commencement of setting up of STPs and connecting all DPR submitted before KIIFB Modern the drains and other sources of generation of sewage to 31.12.2021 Market with STP at Ottupara (18 KLD) & the STPs must be ensured Athani (14.9 KLD) 2 Timeline for completing all steps of action plans including 31.12.2021 DPR submitted before KIIFB Modern completion of setting up STPs and their Commissioning Market with STP at Ottupara (18 KLD) & Athani (14.9 KLD) 5 Chief Secretaries may set up appropriate monitoring N.A. mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose

 Monitoring at State level must take place N.A.

6 Progress report may be furnished by the State/UTs to Applicable  Secretary,Ministry of Jal Shakti at State  Member Secretary,CPCB Level 6.1 Progress Report may be comprised of details along with completion timelines on: Polluting Sources & Illegal outlets were (I) Identification of polluting sources including drains identified, notice issued as per Kerala contributing to river pollution and action as per NGT Ongoing Municipal Act and removed. Doing regular order on in-situ treatment. Process inspection.

(II) Status of STPs, I&D and sewerage networks Details of DPR under preparation. 2 common STPs are Existing Infrastructure,Gap Analysis, Proposed along 31.12.2021 proposed, One at Athani (350 KLD with completion timeline approximate) and other at Ottupara (500KLD approximate). Site identified. (III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Nil Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of March Bio-waste: Processing Facilities 2021 Presently using Biogas plant. Collecting Bio- Details of Existing Infrastructure,Gap Analysis, degradable waste from houses and Proposed along with completion timeline commercial establishments through Kudumbasree Unit – “Bhumi mithra”

Construction of windrow compost plan 80% work completed

Non-Bio waste: Door to door collection from houses and commercial establishments ongoing through Harithakarmasena. The collected waste handing over to Clean Kerala Company.

(v) Latest water quality of polluted river, its tributaries, Tributaries Akamala Ottupara Thodu drains with flow details and ground water quality in Drains-2 the catchment of polluted river; Wadakkanchery & Ottupara.

(vi)Preventing dumping of waste and scientific waste Bio-medical waste collected by IMAGE. Two management including bio-medical waste, plastic MRF were setup at Aryampadam and waste and decentralizing waste processing, including Kumbalangad. Plastic waste handing over to waste generated from hotels, Ashrams, etc. Clean Kerala Company. RRF constructed. Bailing machine installed.

Construction of 1726 rain pits for ground (vii)Ground water regulation water recharge completed in the year 2019- 2020 under Ayyankali Urban Employment Scheme.

(viii) Adopting good irrigation practices Good irrigation practices will implement in co-operation with Agriculture and irrigation department.

Irrigation canal cleaning completed after 2018 flood.

(ix) Protection and management of food plain Zones (FPZ) Not yet started.

(x) Rain water harvesting Guaranteed the construction of Rain water Ongoing harvesting facility for residential building process above 150m2. Occupancy certificate issued only after verification of the above.

(xi)Maintaining minimum Environmental flow of river Not yet started.

Around 1000 Bamboo trees planted along (xii) Plantation on both sides of the river 6.5km of Wadakkanchery River on both sides in co-operation with KFRI.

Recovered 10.5 Acres of encroached land (xiii)Setting up biodiversity parks on flood plains by along Wadakkanchery River. Will prepare removing encroachment Project as per Municipal Council Decision, for setting up of bio-diversity Parks. ACTION PLAN FOR RIVER KECHERY, KERALA

No. Activity Implementing Time line Progress in Progress in the Progress in % works Detail (as per agency the month of month of the month complete s of Action August September of d works Plan) November remai 2020 ning WADAKKENCHERY RIVER -SHORT TERM MEASURES

A(b) Identification of illegal outlets from houses and Wadakkanchery Completed shops/other establishments in town and imposing Municipality, fine Ayyakali Urban Employment Guarantee Scheme & health squad

E Installat ion of CCTV s on the bank of river in town Wadakkanchery December Work not Municipality 2021 started due to scarcity of Municipal fund

C(ii) Material recovery facility Wadakkanchery Completed Municipality

C(ii) Resource recovery facility Wadakkanchery Completed Municipality

C(ii) Renovation of existing biogas plant Wadakkanchery December presentl Municipality 2020 y functio ning well

Monitoring A(a)(iv) River water quality monitoring KSPCB Monthly Monitori ng in progress A(b) Inspection & effluent quality monitoring of the Flats, KSPCB Ongoing industrial units, service stations, hospitals,hotels etc Long Term Plan

E Identification and cleaning of polluted drains Irrigation Dept 30-03-2022 reaching wadakkancheri river

A (b) Common STP Wadakkanchery December Site for one Municipality, 2021 STP identified. Kerala Applied for Infrastructure NOC from Investment Fund District Board Collector. (Land is Puzha Puramboke and Irrigation Department Canal Puramboke) C(iii) Windrow composting at Kumbalangad yard Wadakkanchery March 80% work Municipality 2020 completed

C(ii) Modern slaughter House Wadakkanchery December Lack of Municipality, 2021 suitable site for Kerala the project Infrastructure Investment Fund Board

E Forestation, desilting & deepening of Wadakkanchery desilting and Fitting river Wadakkanchery river and fitting river side with Municipality deepening of side with Coir coir geo net Wadakan - Geo net. chery River Awaiting 3 km in Municipal Municipal Council area Decision for completed fund allocation

7655m3 desilt removed

Rain water harvesting Wadakkanchery Ongoing work Municipality

Ground water recharge Wadakkanchery Ongoing work Municipality

River survey Wadakkanchery Ongoing work Municipality

Short term plan (Kecheri river)

E Installati on of CCTV in different locations along PWD Electronic river side division

E Fixing Boards Choondal Grama 31/08/2020 O Panchayat N

g o i n g

A(a)(iv) Surveillance to prevent flow of sewage /effluent to Choondal Grama 31/08/2020 A river Panchayat c t i o n

t a k e n A(b) Stoppa ge of effluent from residential apartment Choondal Grama 31/05/2020 (Shajan’s flat) and pig farm into the river Panchayat S t o p

M e m o

H a d

b e e n

G i v e n

t o

C o n c e r n e d

p e r s o n s Long TermPlan (Kecheri river)

E Side protection by fixing coir geo nets Choondal Grama September Panchayat 2020

E Survey process of Kechery river portion belong to Revenue Choondal Grama Panchayat to mark the boundary Department and encroachment E Laying of survey station Choondal Grama completed Panchayat E Digital maping and seminar on pollution control Forestry College, 31/05/2020 Vellanikkara

IRRIGATION DEPARTMENT

No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month of month of the month complete works November December 2020 of October d remainin 2020 2020 g 1 Regulating activities in flood plain zone, protection Irrigation 30-03-2022 Estimate and management of flood plain zone Department submitte d for fund 2 Greenery developmentPlantation plan. Plantation Irrigation 30-03-2022 Estimate on both sides of the river, settling up biodiversity Department submitte parks on flood plains by removing encroachment d for fund 3 Issues relating to E-flow, maintaining minimum Irrigation 30-03-2022 Estimate environmental flow of river(by having watershed Department submitte management provisions) d for fund

ACTION PLAN BY GRAMAPANCHAYATH

No. Activity Implementing Time line Progress in Progress in the % works Details of works (as per agency the month of month of completed remaining Action July August Plan) C Punarjani Kecherri river Choondal Grama 31.03.2021 Flood Panchayat Wastes from the river has been remove d and made water flow easily which reduced chances of flood . C(ii) Surveying of river side, eviction and planting trees Choondal Grama 31.03.2021 Survey Panchayat complet ed C Side Protection Choondal Grama 31/03/2021 Panchayat

C Bio fencing related to river bank protection – MGNRES 31/03/2021 water and soil Conservation project ward 3,4,7

ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item Activity Progress in the month of Progress in the month of % works Details No. nos as per NGT October 2020 November 2020 completed of Order works no.673/2018 remain dated 20.09.2018 ing 1 B(i) Ground Water resources and According to the latest GEC report there regulation of ground water is no critical / over exploited blocks in extraction by industries Thrissur Dt. particularly in over exploited as critical zones/blocks

2 B(ii) Ground water recharging / One artificial recharge scheme has been The artificial recharge scheme 100% Nil rain water harvesting tendered and work order issued, at work are in progress at Kadavallur in Kadavallur GP Kadavallur in Kadavallur GP. 3 B(iii) Periodic ground waste No water quality issues reported in the quality assessment and GWD water level monitoring wells. remedial actions in case of contaminated ground water tube wells/bore wells or hand pumps 4 B(iv) For regulating use of ground Suggestions given to farmers for Rain water for irrigation purpose, water harvesting to recharge aquifers. adopting good irrigation practices

KECHERI RIVER Date of sampling - 11.12.2020 SL. NO PARAMETER UNIT VAD1 VAD2 1 pH - 6.3 6.5

2 Electrical Conductivity µ/cm 127 110 3 BOD mg/L 2 0.9 4 DO mg/L 7.1 8.1 5 COD mg/L 8 12 6 TC CFU/100ml 400 200 7 FC CFU/100ml 200 100

VAD1 - WADAKKANCHERY PUZHA (WADAKKANCHERY BRIDGE), KECHERY VAD2 - WADAKKANCHERY PUZHA(CHALIPPADAM ROAD), KECHERY

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER PUZHAKKAL, THRISSUR S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ 30.12.2020 In progress remediation Commencement of setting up of STPs and connecting all 30.12.2020 In progress the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including In progress completion of setting up STPs and their Commissioning STP completed at Mattampuram.

5 Chief Secretaries may set up appropriate monitoring Tendered and awarded STP at district mechanism at state level hospital – Applied for PCB permission.  Specifying accountability of nodal authorities not Response from PCB awaiting. below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place NA 6.1 Progress Report may be comprised of details along with Illegal outlets 91530 houses and 122 completion timelines on: establishments )were identified and notice (I) Identification of polluting sources including drains issued. contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Work tendered and selection memo issued. Agrement not executed. Reminder letter Existing Infrastructure, Gap Analysis, Proposed along sent with completion timeline

(III) Status of CETPs 70 percentage of industries installed ETPs. Details of Existing CETP and ETP Infrastructure, Gap Notice were issued to remaining Analysis, Proposed along with completion timeline, establishments No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Water Existing infrastructure Processing Facilities quality Details of Existing Infrastructure, Gap Analysis, monitoring 1. 10 mcf Proposed along with completion timeline of polluted 2. 2 rrf river stretch 3. 2 OWC Plant (v) Latest water quality of polluted river, its tributaries, is done having capacity of drains with flow details and ground water quality in periodically, 12 tpd. the catchment of polluted river; (Report attached.) 4. 8 Biogas plant

5.20 Vehicles (2 truck,2tractors, 8 (vi)Preventing dumping of waste and scientific waste ommercial utilty vehicles, 8 pettiauto) management including bio-medical waste, plastic 6.10 units of aerobic bins waste and decentralizing waste processing, including 7.13 o.s o Harithakarmasena groups (140 waste generated from hotels, Ashrams, etc. members) 8.Door to Door collection from 40000 (vii)Ground water regulation houses & 15000 commercial institutions

(viii) Adopting good irrigation practices Riverside New proposals protection 1. 23 new Harithakarma sena groups are (ix) Protection and management of food plain Zones (FPZ) work for a formed to cover 55 divisions. stretch of 2. New Owc plant Kovilakathumpadam is (x) Rain water harvesting 500m has started. been 3. 2 MRF under construction not completed. completed. (xi)Maintaining minimum Environmental flow of river Construction 4. 1 No of commercial utility vehicle will

of second be purchased for door to door collection (xii) Plantation on both sides of the river stretch of 5.New Bailing machine for RRF will be 450m is purchased. Tender process is going on. (xiii)Setting up biodiversity parks on flood plains by ongoing 6.New building for segregation yard is removing encroachment planned and worth Rs:40 Lakhs are year mark 7.100% door to door collection can b achieved within 3 months. 90% is covered and rest 10% will be covered within 3 months. VI 1.To prevent dumping Corporation is indenting to collect the waste from 100% door. 90% is covered. 2.No.of dumping site could be reduced by the continuous monitoring & observations 3.Biomedical waste is processed by image .This year Corporation yearmark Rs.1 crore for the construction of new biomedical incinerator at corporation hospital. 4. Plastic waste are collected segregated and sent to recycling system. Multi layer plastics are shredded and used for road construction through clean kerala company. Non recyclable plastic wastes are sent to KEIL through Clean Kerala company. Corporation made a negotiation with ACC cement factory for co-processing of non recyclable plastic waste. 5. Bulk waste generators (hotels and Asrams) process their wastes in their own premises. They use biogas plant and aerobic compost bin.

ACTION PLAN FOR RIVER PUZHAKKAL, KERALA SHORT TERM MEASURES

No. Activity Implementing Time line Progress in Progress in the % works Details of works (as per agency the month of month of completed remaining Action November December 2020 Plan) 2020 A(b) Identification of illegal outlets into the Panchikkal Thrissur 3 months 28 thodu and subsidiary drains Corporation

A(b) Stoppage of discharge of waste water from the Thrissur 6 months 7 surrounding houses and institutions to the drains Corporation which leads to Panchikkal thodu A(b) Ensure adequate treatment facility is provided for Adat Grama waste water and solid waste generated from Sri Panchayat Dharma Sastha temple situated on the banks of the river E Desilting of Karakattuchal Irrigation 4 months Department E Desilting of Panchikkal thodu Irrigation 4 months Department

E Desilting of Kurinjikkal thuruth Irrigation 4 months Department

E Desilting of Muppuzha Irrigation 4 months Department

E Side protection, desilting and deepening work of Thrissur 3 months Side vanchikulam thodu at Poothole of length about 40 Corporation protecti km (work in progress). on 1.89 kilometr e complet ed. Balance work in progress E Annual desilting, cleaning of main drains and canals Thrissur 3 months Complet with in the corporation area (work in progress). Corporation ed before Monsoo n. Monitoring A(a)(iv) River water quality monitoring KSPCB Ongoing; monthly frequency A(b) Inspection & effluent quality monitoring of the Flats, KSPCB Ongoing industrial units, service stations, hospitals,hotels etc

Long Term Plan A(b) Ensuring installation of treatment facilities for at Thrissur 18 months least 50% of the identified establishments Corporation

A(b) 100% completion of treatment facilities for targeted Thrissur 24 months institutions/ buildings Corporation

A(b) Construction of a drain 40 km with covering slabs to Thrissur 24 months 24.01 KM avoid the direct disposal of waste in to the open Corporation completed. drain Selection memo issued A(b) Construction of a drain 9000 m with covering slabs Thrissur 24 months to avoid the direct disposal of waste in to the open Corporation drain A(b) Construction of sewage treatment plant of 100 KLD Thrissur 24 months 360 kld PCB and 360 KLD at Ramavarmapura m and District Corporation applied and Hospital, Thrissur in Amrut Project awaiting for approval. 100 KLD Application for PCB applied. A(b) Constructing decentralised sewerage scheme at Thrissur 24 months Revision Vachikulam covering most populated 7 divisions of Corporation estimate as per Thrissur Corporation and more than 10000 houses & structural institutions veting submitted for revised TS at Chief Engineers Office TVM.

ACTION BY GROUND WATER DEPARTMENT

Sl. Ref para item nos Activity Progress in Progress in the % works Details of works No. as per NGT Order the month month of completed remaining no.673/2018 of December dated 20.09.2018 November 2020 2020 1 B(i) Ground Water resources and regulation of ground According to water extraction by industries particularly in over the latest exploited as critical zones/blocks GEC report there is no critical / over exploited blocks in Thrissur Dt. 2 B(ii) Ground water recharging / rain water harvesting Three Completed 100% Nil artificial three artificial recharge recharge schemes scheme. Two have been sites at tendered Varadium in and work Avanur GP and order issued. one site at Two sites at Choorakkattuka Varadium in ra in Adat GP. Avanur GP and one site at Choorakkatt ukara in Adat GP. Work in progress 3 B(iii) Periodic ground waste quality assessment and No water remedial actions in case of contaminated ground quality issues water tube wells/bore wells or hand pumps reported in the GWD water level monitoring wells. 4 B(iv) For regulating use of ground water for irrigation Suggestions purpose, adopting good irrigation practices given to farmers for Rain water harvesting to recharge aquifers.

ACTION PLAN BY GRAMAPANCHAYATH

No. Activity Implementing Time line Progress in the Progress in the % works Details of works (as per agency month of month of complete remaining Action November 2020 December 2020 d Plan) C Removing weeds in Puzhakkal River Adat 31.12.2020 100 Gramapanchayath %

C(ii) Removing waste from all wards through KUDUMBASREE 31.12.2020 100 kudumbasre e % C water conservatio n projects-- tree plantation MGNREGS 31.12.2020 10% under GA in18 wards 100000/ each

C ward 14 pachthurthu comstruction Haritha Keralam 31.12.2020 100 Mission %

C side protection to water bodies coir geo textile MGNREGS 31.12.2020 25%

PUZHAKKAL Date of sampling - 15.12.2020 SL. NO PARAMETER UNIT SBA KTH PTU MP 1 PH 6.12 5.6 6.42 6.4 2 EC µ/cm 205 583 374 145 3 BOD mg/L 2.3 2 1.7 2 4 DO mg/L 7.7 7 6 6.2 5 COD mg/L 8 12 8 12 6 TC CFU/100ml 500 400 500 600 7 FC CFU/100ml 300 200 300 300

SBA - NEAR SOBHA CITY, KIZHAKKUMMURI ROAD , PUZHAKKAL KTH - KURINJAKKAL THODU, PUZHAKKAL PTU - PANCHIKKAL THODU, PUZHAKKAL MP - MUPPUZHA, PUZHAKAL

National Mission for Clean Ganga Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER ,

S. Activity to be monitored Timeline Submission of progress by state/UT-Compliance status No. 1 Ensure 100% treatment of sewage at least in- situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose.  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details Last updated report submitted was on 05 December along with completion timelines on: 2020 (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT Identified 17 drains out of which 9 were additionally order on in-situ treatment. identified on 11.07.2019

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure,Gap Analysis, Market – 45 KLD- running Proposed along with completion Bus stand -50 KLD – running timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, Nil Proposed along with completion timeline, No. of industries and complying status

(iv) Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure,Gap Analysis, Proposed along with Disposal using sanitary landfills, composting, operations , completion timeline MRF, MCF etc

(v)Latest water quality ofpolluted river, its tributaries, drains with flow details and ground water quality in the catchment Attached as Annexure II(Analysis report during the month of polluted river; of December)

(vi)Preventing dumping of waste and scientific Actions are being initiated to prevent illegal waste waste management including bio-medical dumping. BMW are being disposed scientifically through waste, plastic waste and decentralizing IMAGE. Municipality have MRF, MCF facilities waste processing, including waste generated from hotels, Ashrams, etc. NA (vii)Ground water regulation

(viii) Adopting good irrigation practices, complying

(ix) Protection and management of food plain Zones (FPZ),

(x) Rain water harvesting,

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii) Setting up biodiversity parks on flood plains by removing encroachment

ACTION PLAN FOR RIVER TIRUR, KERALA

1. IRRIGATION DEPARTMENT

No. Activity Implementing agency Time line Progress in Progress in the Progress in % works Details of the month month of the month completed works of November 2020 of remaining October20 December 20 2020 1.1.1 Strengthening the right Irrigation 6 Months These two Department works are side bund of Tirur- combined Ponnanipuzhaat Porur, and DPR

ward submitted for FS on no.ITirurMunicipality 22/11/201 1.1.2 Cleaning and development Irrigation 6 Months 9 of old thodu at Department Thazhepalam

1.1.3 Repair and Irrigation 18 Months This work Department is Rehabilitation of arranged Koottayi Regulator cum under Bridge across Thirur- Rebuild Kerala PonnaniPuzhain Initiative Mangalam Grama (RKI) and in tender panchayatin process Malappuram Dist

2. TIRUR MUNICIPALITY – SHORT TERM ACTION PLAN No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month month of the month completed works of October November 2020 of remaining 2020 December 2020 1.2.1 Provide septic tank for nearest Tirur Dec 2019 completed completed completed completed houses Municipality

1.2.2 Establishment of Solid waste Tirur March 2020 completed completed completed completed Treatment Plant Municipality

ThumboorMozhiModel AerobicBin

1.2.3 Establishment of Non Degradable Tirur March 2020 Complet Completed complet completed waste treatment Plant Municipality ed ed Shredding unit is Resource Recovery facility Centre converted to bale Plastic Shredding Unit unit- supply order Segregation shed issued

completed 1.2.4 Slaughtering House Tirur Municipality December Civil work tendered 2020 is tendered Will be completed completed by for March 2021 installatio n of mechanica l parts- agreement executed 1.2.5 Fencing on Bridgeside Tirur Municipality December Complet completed complet completed 2020 ed ed ThalakkadathurBridge 1.2.6 Installation of CCTV Camera Tirur Municipality May 2020 In Project rejected DPR completed near the river Bank progres by DPC. Trying to prepare Thalakkadathur Bridge s complete by d and cloud computing submitte d for approval

c

1.2.7 Planting of Bamboo seedlings on the Tirur Municipality Complet completed completed June 2020

river bank (Thazhepalam) ed completed co

1.2.8 Renovation of Effluent treatment plant Tirur Municipality June 2019 Work Work completed- completed

at fish Market AMC Granted Completed started operation completed completed

ETP with Aeorobic System Tirur Municipality

1.2.9 Setting up of STP at Tirur Municipality June 2020 Trial run Started operation and Started completed Private Bus stand conducted completed operation on and 20.10.2020 completed 1.2.10 Setting up of a new drain after Tirur Municipality June 2020 completed To increase the Estimate Construction demolishing the old one. The old one efficiency of drain prepared and of new drain construction of silt submitted in the middle was the hub of the waste water chambers old for approval of road outlet of the shops and other Ponnani thodu and connecting establishments. The proposed drain is Kadayi thodu in waste water constructingin the middle of the road thodu- estimate from shops to so as to avoid intrusion of pipes from preparation going on STP is completed. outside The construction of silt chambers have obtained technical sanction 1.2.11 Identification ofillegal outlets Tirur Municipality Fine imposing intostorm water drainsand fine mechanism is going shallbeimposed onsuchunits on 3. Cheriyamundam Grama panchayat

No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month month of the month completed works of October November 2020 of remaining 2020 December 2020 1.3.1 Fencing on bridge side Cheriyamundam March 2020 completed Grama panchayat Thalakkadatur 1.3.2 Providing fencing and camera at Cheriyamundam Submitted Submitted completed Grama panchayat agreement agreement Ipputtungal thodu

4.Kerala State Pollution Control Board

No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month month of the month completed works of November 2020 of remaining October20 December 20 2020 1.4.1 River water quality Monitoring- KSPCB Ongoing; 100% Monthly Thalakkadathur frequency National Water Quality Programme(NWMP) 1.4.2 River water quality Monitoring KSPCB Ongoing; 100% Seasonal State Water monitoring programme (SWMP)

1.4.3 Inspection and effluent quality Ongoing; 100% monitoring of the flats, Industrial Interval; units, Service stations, hospitals, Red – 1 auditorium, hotels month, in Municipal area Orange- 3 months, Green- 6 months 5.Ground Water Department

No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month month of the month completed works of November 2020 of remaining October20 December 20 2020 1.5.1. Ground Water resources and Ground water No action regulation of ground water Department included in extraction by industries particularly the approved in over exploited as critical action plan zones/blocks to be performed (Earlier status : As per by Ground Groundwater resources of Water Kerala, 2017 estimate a total number of 2 blocks (Tirur and ) comes under the Tirur river basin. These two blocks are semi-critical blocks and the stage of groundwater extraction ranges from 77.75 % to 77.92%)

1.5.2 Ground water recharging / rain No action water harvesting included in the approved (Earlier status : The average pre - action plan monsoon groundwater level ranges to be from 6.14mbgl - 8.49 mbgl.) performed by Ground Water 1.5.3 Periodic ground waste quality No action assessment and remedial actions in included in case of contaminated ground water the approved tube wells/bore wells or action plan handpumps to be performed (Earlier status : No observation well by Ground along the river stretches) Water 1.5.4 For regulating use of ground No action water for irrigation purpose, included in the adopting good irrigation approved practices action plan (Earlier status : The total to be performed irrigation draft in the area by Ground ranges from 49.14 - 870.97 Water ha.m.) 6. ACTION PLAN BY VARIOUS GRAMA PANCHAYATHs- Thalakkad, Vettom, Mangalam

No. Activity Implementing Time line Progress in Progress in the Progress in % works Details of agency the month month of the month completed works of November 2020 of remaining October20 December 20 2020

1.6.1 Protection of Thirur Ponnani Thalakkad grama 31.03.2020 In progress May be extended to DPC River panchayath 31.03.2021 approved and may be a.Fencing of on bridge side handover fund to District Panchayat extended to (kooloopalam) 31.03.2021 b. Placing CCTV on bridge side at Kooloopalam,,Kunjilakkadav Mangattiri,Kattachira 1.6.2 Installation of CC TV bridge Vettom - KS Spill over completed completed completed completed SECURITY SYSTEM side of Koottayi regulator cum due to lack bridge of fund 1.6.3 Installation of CC TV camera Mangalam grama Completed In progress In progress In progress In progress panchayath Win Plus Agency, 1.6.4 Installation of CC TV camera at Mangalam grama Completed completed completed completed completed Kootayi regulator cum bridge panchayath Win Plus Agency, Kondotty 1.6.4 Haritha KeralamThirur- Mangalam grama 31.03.2020 completed completed completed completed Ponnanipuzha protection panchayath Nirmithi Kendra, Kozhikkodu 7.REVENUE DEPARTMENT Survey of boundaries of river side Revenue Directed to Not started yet- Vettom department all fee for survey Panchayath correspondi submitted by Survey ng completed. Vettom and Cheriyamun department Cheriya mundam to take the dam , Grama fund for Mangalam have survey of panchayaths submitted boundaries amount for of river side survey. and Account published details are the given to estimate Purathur amount for Panchayath. each The amount will be transferred to the account of Survey Superidenta nt for further actions

National Mission for Clean Ganga Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KADALUNDI, MALAPPURAM

S. Activity to be monitored Timeline Submission of progress by state/UT-Compliance status No. 1 Ensure 100% treatment of sewage at least in- situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose.  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details Last updated report submitted was on December 05 2020 along with completion timelines on: (I) Identification of polluting sources

including drains contributing to river Identified 3 drains on 10.12.2018 pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage Malappuram municipality – 30 KLD finished and was networks Details of Existing operational early. It is not operating properly due to Infrastructure,Gap Analysis, absence of oil trap. Project submitted for approval for Proposed along with completion construction of oil trap and revamping STP (No further timeline progress reported )

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis,

Proposed along with completion Nil timeline, No. of industries and

complying status

(iv) Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure,Gap Disposal using sanitary landfills, composting, MRF, MCF Analysis, Proposed along with etc completion timeline

(v)Latest water quality ofpolluted river, its tributaries, drains with flow details and

ground water quality in the catchment Attached as Annexure I( analysis report of month of of polluted river; December)

(vi)Preventing dumping of waste and scientific Actions are being initiated to prevent illegal waste waste management including bio-medical dumping. BMW are being disposed scientifically through waste, plastic waste and decentralizing IMAGE. Municipality have MRF, MCF facilities waste processing, including waste generated from hotels, Ashrams, etc. NA (vii)Ground water regulation

(viii) Adopting good irrigation practices, complying

(ix) Protection and management of food plain Zones (FPZ),

(x) Rain water harvesting,

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii) Setting up biodiversity parks on flood plains by removing encroachment

ACTION PLAN FOR RIVER KADALUNDI, MALAPPURAM, KERALA

1. 2. Malappuram Municipality-Short Term Solid & Liquid Waste Management Action Plan

No. Activity Implementing Time line Progress in Progress in % works Detail Progress agency the month of the month complet s of in the October of month ed works 2020 November of remai 2020 Decemb ning er 2020 1.1 Slaughter house and Malappuram July 2010 Date shall Date shall Date Date shall be Poultry house Municipality be extended be shall be extended to to March extended to extend March 2021 2021 March ed to 2021 March 2021

1.2 Valiyathodu Cleaning - 8 Malappuram Completed completed completed comple completed Km Municipality ted length 1.3 Installation of screening Malappuram December 2019 completed completed compl completed net in the Valiyathode Municipality eted 1.4 Identification of Malappuram Completed completed completed compl completed polluting points in Municipality eted Kadalundi river & awareness campaign - River walk(puzhanadatham – 15 km length) 1.5 Sanitation facility and Malappuram Completed completed completed compl completed treatment of waste Municipality eted water in the markets - Treatment plant 1.6 The discharge of waste Malappuram Completed completed completed compl completed water from the Municipality eted surrounding houses to the Valiyathodu - Blocking of discharge of liquid waste 1.7 Identification of illegal Malappuram Ongoing completed completed compl completed outlets into storm Municipality eted water drains andfine imposed on such units. 1.8 Biodegradable Malappuram Date shall be Date Date shall be waste Municipality extended to shall extended to March 2021 be March 2021 Bio bins – 176 extend March 2020 ed to Bucket compost – 269 March March 2020 2021 Thumboormuzhi Aerobic bins - 4 March 2020

March 2020 Biogas plant -55

1.9 Non biodegradable waste Malappuram 3 MCF 3 MCF Compl Completed Municipality completed completed eted MCF March 2020

Plastic shredding and Completed completed complete Completed completed Bailing d Shall be Shall be Shall be Echo Kiosk March 2020 extende extended extended to d to to march march 2021 2021 march 2021 1.10 Identification and Malappuram In progress Shall be Shall Date shall be monitoring of illegal Municipality extended be extended to activities to march extend March 2021 CC tv Network March 2020 2021 ed to installation march

2021

2.Kerala State Pollution Control Board

No. Activity Implementing agency Time line Progress in Progress in Progress % works Details the month of the month in the complet of October of month ed works 2020 November of remain 2020 Decemb ing er 2020 2.1 River water quality KSPCB Ongoing; 100% Monthly Monitoring- frequency Thirurangadi, Ha jiyarpally National Water Quality Programme(NWMP) 2.2 River water quality KSPCB Ongoing; 100% Seasonal - Monitoring - Pre - Thirurangadi, monsoon, Kooriyad, monsoon, Manikut, Hajiyarpally, post - Anakkayam, monsoon Oravambrum - State Water monitoring programme (SWMP)

2.3 Inspection and KSPCB Ongoing; 100% effluent quality Interval; monitoring of the flats, industrial units, Red – 1 service stations, hospitals, hotels etc. month, in Malappuram Orange- 3 Municipalarea months, Green- 6 months 3.Ground Water Department

No. Activity Implementing agency Time line Progress in Progress in Progress % works Details the month of the month in the complet of October of month ed works 2020 November of remain 2020 Decemb ing er2020 3.1. Ground Water Ground water No resources and Department action included regulation of ground in the water extraction by approve industries d action plan to particularly in over be exploited as critical performe zones/blocks (Earlier d by Ground status : As per Water Groundwater Departm resources of Kerala, ent 2017 estimate a total number of 3 blocks (, Vengara and Malappuram) comes under the Kadalundi river basin. Out of three blocks Malappuram and Vengara are semi- critical blocks and the rest is a safe one, stage of groundwater extraction ranges from 69.43 % to 79.84%)

3.2 Ground water Ground water No recharging / rain water Department action harvesting included in the approve (Earlier status : The d action average pre -monsoon plan to groundwater level be ranges from 7.59mbgl - performe 13.57 mbgl. d by Ground Groundwater Water Department has Departm implemented 3 no of ent roof top rain water recharging through recharge pit schemes in Vengarablock.)

3.3 Periodic ground waste Ground water No quality assessment and Department action remedial actions in included in the case of contaminated approve ground water tube d action wells/bore wells or plan to handpumps be performe (Earlier status : d by Ground Groundwater Water Department has 6 Departm observation dug wells ent and 14 bore wells in the river stretch. (report attached ) (Map No: 7 attached)) 3.4 For regulating use Ground water No of ground water Department action included for irrigation in the purpose, adopting approve good irrigation d action plan to practices be (Earlier status : performe The total d by Ground irrigation draft in Water the area ranges Departm from 979.683 - ent 1857.49 ha.m.) =E o o I ool o N r t = UJ o (D (J .ir c N (o @ (o N II ( ro () (o (0s lo N o oIJJ= TU o ct) ll l I tr a E I uJ tr o uJ o (o $ @ N F o r @ \t O) t UJ l- t D = t t o) F E z o- o o CO oq o) @ c\ @ q q @ @ o c\i N o o N ci N O o zF 6 (L o) I E or F o @ q q q N cf) o (o c., (o 1r) (o ro (0 (o UJ L s + + Ft @ E E lJ o o o o o o o E L @ '= lo CA (f) c|.) o) co lr) o (L L \ L L TU o @ o 1- (o tt- t- i N tt- (o tt- c t- f- F o l f -cl lo J PIJI lo J J io l-l p f E (u Ji L o o o -o (tr - o- 5l '= E (u = .c (u lt (U (I' EI E (U .c -i5 (Ul. Y (U o = (U G I o t E -Y L E C ol o 'c (U o F E .c o c (E lz J (U o ol (I' I E J Y tr E= L IE c cl. I G' o ]C '6 E oE (Ul' I LrJ o i- (I' o)o E J -Y o (U (U o. o- ElrL L _l G' E o) (U (U c_c t- (J (U (U (!l -tJ E uJ G'# I (u (I' c c) o- o #1. (U G' t- o (I' t, o '=c (U (ul o o ol lz Q) cc o U) N c c cl J c (I' (I' cc C U' o -c a _a -!z (U E - (U N (I' a!- (Ul o L (I' (U E .c .o oc=G' t- .c .- ol sl E C) .c .o o (I' g6 G' (Uc c c cl (U (501 ol (I' c C Y C cl c o (Ul o L o_l a (u o (I' o g6 (U J z a6 FI -o O )t() ol o6l rrl Y rL Y Y a6 o-l I

_o f, N (r) K) (o @z N cf) $ o o @ O) i- \- r r r r .1. r-'l r\

I tv, FT -

z F]

va a z r--1 l.t F a r-'\ trz

rT,'1 Q = oo F E o Fr o V)

F\F . 't !i .C (o x ! an tu* -. .A .= (g (o l- v t< o Fi 'o tVF -o >' r= F) E E I (, o 0r .E bo bo -'1 c l-i tt (o (o c) E E ,a>t (t) z ((' (nY t1 z ZA Kerala State Pollution Control Board, District Office, NATIONAL MISSION FOR CLEAN GANGA

Format for submission of monthly progress report by state/UTs

( Hon’ble NGT in the matter of OA.No. 673/2018 dated 6/12/2018 )

For the month of November 2020 – Kallai polluted river stretch

Sl Activity to be monitored Timeline Submission of progress by state/UT- No complinance status

1 Ensure 100% treatement of sewage at least in-situ remediation 2 Commencement of setting up of 28.02.2021 Construction of 2 MLD, 1 MLD STP STPs and other sources of plant of Calicut medical college generation of sewage to the STPs started must be ensured 3 Timeline for completing all steps 31.03.2022 Proposal for 13 MLD STP (6 MLD STP of action plans including plant proposed at Kothi, 7 MLD STP completion of setting up STPs and plant proposed at Avikkal) – their commissioning Tendering in progress

4 Chief secretaries may set up NIL appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the secretary level  Chief secretaries may have an accountable person attached in their office for this purpose  Monitoring at state level Fortnightly commencing NIL must take place 21.12.2019 5 Progress report may be furnished Monthly NIL by the state/UTs to (preferably before 20th of  Secretary,ministry of jal every month) shakti  Member secretary,CPCB 5.1 Progress report may be comprised of details along with

completion timeline on:

(i) identification of polluting Action continuing Drains identified. Pollution load source including drains calculated. Action plan prepared. contributing to river Joint squad of PCB and Corporation pollution and action as per inspection in action. Issued notice to NGT order on insitu 92 units during the period 2019.

treatment . 30 units installed treatment facilities.

During Jan-Mar 2020 joint squad of

PCB and corporation inspected 82 units. Issued notice to 56 units. In 16

units installation of treatment units Effluent treatment facilities are under

progress.Issued notice to 36 units and a fine of Rs.18500/- was imposed for

the month of September

2020..Monthly progress report

submitted by Kozhikode corporation attached as Annexure 1

31.03.2021 Dredging of Kallayi river from Kaduppini to Kothi -DPR submitted to SE,INC,KKD on 16.10.2019for Rs 773.05 lakhs(7.30 crores for desilting of river and 43.05 lakhs for fencing of

5 bridges) under action plan of Kallayi river and fencing of sides of the river. 31.07.2019 Work entrusted to KWIL – Dredging ,Desilting and removal of weeds fro EK canal -11.2 Km Submitted by Irrigation department

(ii) status of STPs, I&D and 31.12.2020 ,work in (i)Construction of 2 MLD, 1 MLD STP sewage networks details progress plant of Calicut medical college of existing started.-10% work completed infrastructure,proposed along with completion (ii)Proposal for 13 MLD STP (6 MLD timeline 31.03.2021 STP plant proposed at Kothi, 7 MLD STP plant proposed at Avikkal) – Tendering in progress.

(iii)STP of 13 MLD proposed at Kotooli.About 12% of sewer lines were laid by KWA – Honble NGT

stayed the project (OA no. 215/2016).

(iv)Individual septic tank and soak pit

system provided for house hold, units like bakery, cool bars small restaurants with less seating capacity. Individual STPs for high rise building, hotels, Restaurants, Commercial buildings.

(iii) status of CETPs details of No CETP proposed existing CETP and ETP No specific proposal infrastructure ,Gap analysis,proposed along with complying status Kozhikode corporation

(iv) status of solid waste (i) Existing centralized waste disposal management & details of facility of 100 MT/DAY at Functioning processing facilities details Njeliyanparamba(windrow

of existing infrastructure, composting)

Gap analysis,proposed

along with completion timeline (ii) Proposal of 450 TPD waste to 30/06/2021. Work in energy plant at Njeliyanparamba progress implementation in progress. Caping

work started.

Functioning (iii) Chicken waste rendering plant of

40TPD functioning in

170 chicken stalls of Kozhikode

corporation are disposing off the waste through this rendering plant. Work in progress Rendering plant construction for chicken stall waste – Perumanna . Peruvayal

Functioning. And work (iv) 3 MRF facilities existing ( At progressing Njeliyamparamba(Super MRF) 3TPD- with plastic shredding unit, west hill industrial estate -2TPD --with plastic shredding unit,Near Jayanthi nagar colony) -70% completed

Functioning (v) 24 units of aerobic compost facilities existing ( Tagore hall, S K Pottakkad hall, Jubilee hall, Mofusil bus stand,T.B. Clinic,Circle office). Functioning (vi) 350 ring compost and 150 Biogas plants installed in house holds.-kkd Corporation 26 biogas plant complete –peruvayal 190 ring compost complete –mavoor

Functioning (vii) Community level biogas plant- 3nos(Mental Hospital 1TPD, ITI Functioning Malikadav -1TPD, Juvine home- 1TPD) Functioning (viii) 3 Biogas plants in market (Central market 2TPD, Vegitable Functioning market 2TPD, New bus stand,2TPD) (ix) Treatment facility for waste in Central Market – Tendering in Progress (x) Establishment of slaughter house-

30/03/2021 Mavoor Panchayath MCF 1 nos,ring compost,compost pit- Completed and functioning 31/12/2022 Perumanna Panchayat Compost pit and MCF with baling machine (1 nos) -Work in progress Peruvayal Panchayat 31.03.2021 Compost pit,mini MCF 2 nos,bio gas plant- Work in progress MCF-1 nos temporarly functioning 31.03.2021 Panchayat MCF-1 completed Mini MCF -3 Work in progress MRF -1 In block

(v) latest water quality of Analysis report of Kallayi river stretch polluted river, its for the month of September 2020 tributaries, drains with Attached as Annexure 2 flow details and ground water quality in the catchment of polluted river;

(vi) preventing dumping of Same as Item no. 5.1(v) waste and scientific waste Fine of 32 Lakhs imposed for illegal management including dumpinh of solid wastes into rivers bio-medical waste plastic and public places.Instalation of CCTV. waste and decentralizeing Biomedical waste from Hospital,labs waste processing, ,clinics collected through image, including waste generated plastic waste disposal through from hotels, ashrams,etc. recyclers. Individual solid waste processing facilities like bio gas plant, bio bins in high rise building, hotels, restaurants etc. Fencing proposed by irrigation department.

(vii) ground water NIL regulation

(viii) adopting good NIL irrigation practices

(ix) protection and Flood prone mapping- Proposed by management of flood irrigation department plain zones(FPZ),

(x) Rain water harvesting 31/03/2021 Mavoor Panchayat Well recharging-Estimate under preparation 31/03/2021 Peruvayal Panchayat Well recharging-Work in progress 31/03/2021 Olavanna Panchayat Well recharging-Work in progress

(xi) Maintaining minimum Initiated environmental flow of Perumanna Panchayat river 31/03/2021 Cleaning of Mampuzha river-Work in progress

Perumanna Panchayat 31/03/2021 Cleaning of Mampuzha river-Ongoing Olavanna Panchayat Cleaning of Mampuzha river- Completed Completed

(xii)Plantation on both sides Completed Mavoor Panchayat of the river 3500units completed

(xiii) Setting up biodiversity parks on flood Bio park in Kozhikode district- plains by removing Proposed by irrigation department encroachment

(Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019)

KERALA STATE POLLUTION cONTROL BOARD adho Vomu0n nosm1ooa) (nkwI(Tmorn cenioou aoa.oooa o11236man6 aianoogol REGIONAL LABORATORY, KOZNIKODE 3"" LOOR. ZAMORIrs souARE, LIK ROAD. KOZHIKODE 673 002 ete faxt 2300745, 40, www.keralapcb.org ANALYSIS REPORT OF RIVER WATER

|Report No. KROR 39 4 5/ 1 to 6 Date: o6 o 12 0 2 1 Date of Sample o 4 Date of receipt of the sample o22 l2 o Collection Time Hours 16:0 0 KL1, KL2, KL3, KL5, KL6 Sampled by: DO KKD Sample ID KL7 Sampling Method APHA1060B, a Sample Lab Code KROS 3945/1-6 Sample container PC 2.5 L PCBKKD/D0GEN/POLLUTED RIVER Ref.letter No. STRETCHES dated 04.12 2020

Source: KALLAI RIVER WATER Received from: EE, DO, KKD Period of analysis: 04.12.2020-05.01.2021 No. of samples Specific sampling GIVEN BELOW location: Analysed by: CNR/CVR/DKJ Method:Standard Nethods for the examination of Water and Wastewater, Sample ce box preservation: APHA AWWA WEF (22nd Ed.) SAMPLE ID sl no Parameters unit No. Method KL 1 KL 2 KL 3 KL5 KL6 KL7 pH APHA 4500-H+, 7.6 7.6 7.7 7.8 8.2 7.6 CONDUCTIVITY umhos /cm APHA 25108 10200 21230 23540 30150 40630 8037 ** ===-*------BOD mg/L Is3025 (Part 44) 0.06 0.06 0.26 1.06 0.06 6.26 DISSOLVED OXYGEN mgL APHA 4500-0,C 3.2 2.47 2.3 2.27 4.47 1.27 TOTAL COLIFORM, CFU/100m APHA 92228 12000 16000 25000 16000 7000 76000 6 FECAL COLIFORM CFU/100ml APHA 9222D 10000 14000 20000 12000 5000 58000 8 TEMPERATURE C APHA 25508 28 28 30 29 29 29 Test method variation None

Remarks LDL-LOwer Detection Limit BDL-Below Detection Linit

KL1-KALLAI RIVER AT PALATHUMKANDI BRIDGE,POKKUNNU, KL2-KALLAI RIVER AT KADUPPINI BRIDGE, K.L3- KALLAI RIVER AT MANKAVU BRIDGE, KL5- KALLAI RIVER AT KALLAI BRIDGE, KL6 KALLAI RIVER AT KOTHI BRIDGE, THEKKEPURAM & KL7-KALLAI RIVER AT UDAYA RESIDENCY, PAYYANAKKAL 61/2p20 Scientist in charg, Asst Suerntis Kerala State Pollution Control Board, District Office, Kozhikode

NATIONAL MISSION FOR CLEAN GANGA

Format for submission of monthly progress report by state/UTs

( Hon’ble NGT in the matter of OA.No. 673/2018 dated 6/12/2018 )

For the month of November 2020 – polluted river stretch

Sl Activity to be monitored Timeline Submission of progress by No state/UT-complinace status

1 Ensure 100% treatement of Nil sewage at least in-situ remediation 2 Commencement of setting up of Nil STPs and other sources of generation of sewage to the STPs must be ensured 3 Timeline for completing all steps Nil of action plans including completion of setting up STPs and their commissioning 4 Chief secretaries may set up Not applicable appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the secretary level  Chief secretaries may have an accountable person attached in their office for this purpose

 Monitoring at state level Nil must take place

5 Progress report may be furnished Monthly Nil by the state/UTs to (preferably before 20th of  Secretary,ministry of jal every month) shakti  Member secretary,CPCB

5.1 Progress report may be comprised of details along with completion timeline on:

(i) identification of polluting Primary STP (Oil and Grease Drains identified. Pollution source including drains trap with grit chamber) load calculated. Action plan contributing to river prepared. Notices issued by pollution and action as per concerned Panchayath NGT order on insitu Will be implemented by Secretaries to individual treatment 31/3/2021 units. Action under progress by individual units.

Monthly progress report of Kuttiady, Maruthomkara, Cheruvannur, Changaroth,, Kavilumpara, Velom Panchayaths,Chakittapara, Payyoli, Thurayoor, Irrigation department, Water Authority, Shuchitwa mission for the month of October 2020 is attached as Annexure 3.

(ii) status of STPs, I&D and Mostly rural area. No sewage networks details common STP proposed. of existing Individual septic tank and infrastructure,proposed soak pit system provided along with completion for house hold, units like timeline bakery, cool bars small restaurants with less seating capacity. Individual STPs for high rise building, hotels, Restaurants, Commercial buildings.

(iii) status of CETPs details of No CETPs proposed existing CETP and ETP --- infrastructure ,Gap analysis,proposed along with complying status

Kuttiyadi Panchayth (iv) status of solid waste 31/03/2021 Construction started for management & details of block level MRF for 7 processing facilities details panchayath in the Kuttiyady of existing infrastructure, block. Gap analysis,proposed Completed and functioning MCF of Kuttiyadi along with completion Panchayath set up with timeline shredding unit- work completed and functioning. Completed and functioning Mini MCF set up in all wards of Kuttiyadi panchayath. Kavilumpara panchayath Completed and functioning 3 MCFs are functioning. Maruthomkara Panchayath Completed and functioning MRF completed and functioning. Biogas plant work completed. Velom Panchayath – 31/103/2021 Community level – Biogas plant.Work under construction(80% work completed). 50 nos of Biogas plant for house hold- Completed and functioning 31/10/202 Perambra Panchayath MCF- Tendering in progress Mini MCF – work completed.

Changaroth Panchayath 31/03/2021 Project for setting up MCF approved. Site to be identified soon. Biogas plant and Ring compost for house hold proposed. Plastic shredding unit proposed. Completed and functioning Chakkittapara Panchayath MCF-Completed Payyoli Municipality 31/03/2021 2000units of ring compost,500units of biogas plant,5000units of bio bin- Work in progress

(v) latest water quality of Water quality monitoring polluted river, its result for the month of tributaries, drains with October 2020 is attached flow details and ground as Annexure-4 water quality in the catchment of polluted river;

(vi) preventing dumping of Same as Item no. 5.1(v) waste and scientific waste Biomedical waste from management including Hospital,labs ,clinics bio-medical waste plastic collected through image, waste and decentralizeing plastic waste disposal waste processing, through recyclers.Individual including waste generated solid waste processing from hotels, ashrams,etc. facilities like bio gas plant, bio bins in high rise building, hotels etc. Fencing proposed by irrigation department.

(vii) ground water NIL regulation

(viii) adopting good NIL irrigation practices

(ix) protection and management of flood plain zones(FPZ),

(x) Rain water harvesting Work in progress Velom panchayath 22527 rain water pit , well 31/03/2021 recharge – 1500 houses Kavilumpara panchayath well recharge – 160 houses

Maruhtonkara panchayath Well recharge- Action plan and TS approved Cheruvanoor panchayath Well Recharge – Project in progress Chakkittapara Panchayath Well recharging through MGNREGS

(xi) Maintaining minimum Kavilumpara panchayath environmental flow of Adopted steps to remove river sands and rock dumped durig rain flood Maruthonkara panchayah 74 works ongoing under MGNREGS(RWH, soil conservation). Kavilumpara panchayath 5 works ongoing under MGNREGS for protection of river sides Chakkittapara Panchayath Removal of pebbles and renovation of Kuttiady river through MGNREGS Payyoli Municipality Rejuvation/cleaning of Naivarani thodu by removing slit and other solid wastes-Work in progress

(xii)Plantation on both sides of the river

(xiii) Setting up biodiversity parks on flood plains by removing encroachment

(Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019)

KERALA STATE POLLUTION ONTROL BOARD op avorruaxn aonooan okavman oaod

REGIOLAL LABORATORY, KO1NIKODE 3 IL0OR ZAMORUr s sQUARE, LINK ROAD, KOHKOOE -0/3 002 Tetefaxt 2300745, 46, 47 www.keralopcb. org ANALYSIS REPORT OF RIVER WATER

Date: Report No. KR R39 4 8/ 1 to 8 6 012 o 21

of of the sample Date of Sample o9 1 |Date receipt o9 122 0 2 0 Collection Hours: 1 7:0 0 Time D Sample 1D DS1,DS2,DS3, DS4, DS5,DS6. Sampied bY: DO KKD S7,DS8 Sampling Method APHA1060B,a Sample Lab Code KROS 3948/1-8

PCBKKDIDOGEN/POLLUTED RIVER |Sample container PC 25L Ref.letter No. STRETCHES/2018 dated 109 12 2020 EE,DO,KKD Source KUTTYADI RIVER WATER Reccived from: Perlod of analysis: 09.12.2020-05.01.2021 Specific sampling No. of samples 8 GIVEN BELow location: Analysed by: CNR/CVR/DKJ and APHA Method:Standard Methods for the examination of Water Wastewater, Sample ce box AWWAWEF (22dEd.) preservation: SAMPLE ID SI no Parameters unit Method No. DS1 DS2 DS$3 DS4 DS5 DS6 DS7 DS8 6.9 6.7 6.5 64 7.1 APHA 4500-H+, 6.9 6.6

mhosm APHA 2510B 36.6 28.6 43.7 24.3 20 36.5 69.5 30.9 |2 CONDUCTIVIY ----. 0.27 0.3 0.3 0.2 0.67 0.2 BOD mgtIS3025 (Part 44) 0.4 0.5 8 6.4 8.5 4 DISSOLVED OXYGEN mg APHA 4500-0,C 7.6 7.7 7.3 .8 5TOTALCOLIFORM, CFU/100m APHA 92228 5000 3800 9600 2800 2000 1800 12600 2800

6 FECAL COIFORM CFU/100ml APHA 9222D 4200 3000 4400 1800 1400 1200 8400 2000 7 TEMPERATURE C APHA 2550B 24 24 24 24 24 24 24 24

Test method variauon

Remarks LDLLOwer Detection Limit BDL-Below Detection Limit DS1-KUTTYADI RIVER NEAR MARUTHOMKARA-DRAINAGE MOUTH, DS2-KUTTYADI RIVER AT PUZHAYORAM HOTEL, DS3-KUTTYADI RIVER NEAR PARK RESIDENCY HOTEL, DS4-KUTTYADI RIVER AT JANAKI FOREST, DS5-KUTTYADI RIVER NEAR PERUVANNAMUZHI DAM,DS6-KUTTYADI RIVER AT GULIKAPUZHA DRAIN MOUTH,DS7-KUTTYADI RIVER AT KADIYANGAD RIVER & DS8-KUTTYADI RIVER BEHIND KSRTCDEPOT, THOTTILPALAM

Scientist in charge 6 tSeienbs National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER BHARATHAPUZHA, – DECEMBER 2020 S. Activity to be monitored Timeline Submission of progress by State/UT- No Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation March 2021 Proposal submitted before council. Commencement of setting up of STPs and connecting all the drains and Not proposed Not Applicable other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion March 2021 Proposal submitted before council. of setting up STPs and their Commissioning (Primary STP and Septage Treatment Plant proposed, not STP) 5 Chief Secretaries may set up appropriate monitoring mechanism at Applicable at Not Applicable state level State level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place Applicable at Not Applicable State level 6 Progress report may be furnished by the State/UTs to Applicable at Not Applicable  Secretary, Ministry of Jal Shakti State level  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to Primary STP (oil Project submitted before council river pollution and action as per NGT order on in-situ treatment. and grease trap with grit chamber)- March 2021

(II) Status of STPs, I&D and sewerage networks Details of Existing Not Proposed Not Applicable Infrastructure, Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Analysis, Not proposed Not Applicable Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities MSW treatment Implemented Details of Existing Infrastructure, Gap Analysis, Proposed along Plant – March with completion timeline 2021

(v) Latest water quality of polluted river, its tributaries, drains with flow March 2021 Water quality monitoring of polluted river details and ground water quality in the catchment of polluted stretch, two additional points completed until river; December 2020.

(vi)Preventing dumping of waste and scientific waste management Implemented by Management of dry wastes were achieved including bio-medical waste, plastic waste and decentralizing January 2020 through the MCF and RCF facilities, BMW by waste processing, including waste generated from hotels, CBWTDF, E-Waste by authorised collection Ashrams, etc. agencies. No specific Not Applicable (vii)Ground water regulation proposal

No specific Not Applicable (viii) Adopting good irrigation practices proposal

(ix) Protection and management of food plain Zones (FPZ) March 2021 Estimate preparation in the final stage.

(x) Rain water harvesting No specific Not Applicable proposal

(xi)Maintaining minimum Environmental flow of river March 2021 Estimate preparation in the final stage.

(xii) Plantation on both sides of the river No specific Not applicable proposal

(xiii)Setting up biodiversity parks on flood plains by removing No specific Not applicable encroachment proposal ACTION PLAN FOR RIVER BHARATHAPUZHA, KERALA

No. Activity Implementin Time line Progress in the Progress in the % works Details of (as per g agency month of month of complete works Action Plan) November December d remaining 1 Establishment and Modernisation of MSW March 2021 Implemented Implemented 100% Nil treatment Plant ( Solid Waste Management) Municipality work

complete d 2 Material collection Facility (Solid Waste Pattambi Implemented Implemented Implemented 100% Nil Management) Municipality by January impleme 2020 nted 3 Resource recovery facility (Solid Waste Pattambi Implemented Implemented Implemented 100% Nil Management) Municipality by January impleme 2020 nted 4 Installing house hold and community level Pattambi March 2021 Proposal with Proposal with 75% 25% solid waste management units Municipality modifications modifications impleme implementati were submitted were submitted nted on remaining before council before council for further for further implementation implementation of the project of the project 5 Door to Door Collection and Transportation of Pattambi December The coverage of The coverage of Impleme Nil MSW Municipality 2020 door to door door to door nted collection collection extended extended over all over all the wards the wards 6 Regulating activities in flood plain zone Irrigation March 2021 Field studies Report with Impleme Full protection and management of flood plain zone department & estimate estimation fill ntation implementati including side bank protection and greenery preparation be finalised not on remaining are going on st development before 31 started December 2020

7 Issues relating to E-flow, maintaining minimum Irrigation March 2021 Impleme Full Discussions Report with department environmental flow of river(by having are going on estimation fill be ntation implementati watershed management provisions) including further not on remaining studies finalised before removal of light jungles and muddies from river 31st December started courses 2020 Implemented 8 Management of Municipal plastics, hazardous, Panchayath Implement Implemented 100% Nil biomedical and electrical and electronic wastes Municipality ed by Impleme January nted 2020 9 Awareness programmes for sections of public KSPCB March 2021 Action point Implemented 100% Nil implemented Impleme nted 10 Monitoring of river water quality by sampling KSPCB 2020-2021 Water quality Water quality Impleme Implemented. monitoring in monitoring in nted. Continued up Bharathapuzha Bharathapuzha Continue to March at Pattambi at Pattambi and d up to 2021. and two two additional additional points were March Consistently points were completed until 2021. achieving completed December 2020 during the Consiste bathing period of ntly standards November achieving 2020 bathing standard s 11 Primary Sewage Treatment Plant and Septage Pattambi March 2021 Proposal Proposal Work not Full Treatment plant Municipality Submitted Submitted started implementati before before governing on remaining governing council council

12 Installation of Modern Slaughter House and Pattambi March 2021 Work not Work not Work Full Rendering Plant Municipality tendered tendered not implementati started on remaining

13 Construction of Sanitary Complex in Public Pattambi March 2021 Project Project Work not Full Place Municipality submitted for submitted for started implementati technical technical on remaining sanction sanction

14 Green Protocol implementation in all offices Pattambi March 2021 Implemented Implemented 100% Nil institution & public function Municipality Impleme nted

POLLUTED RIVER STRETCH MONITORING PROGRAMME DATA SHEET DECEMBER 2020 Nhangatiri Temple ( U/S of NWMP-2) Station Name RIVER BHARATHAPUZHA AT PATTAMBI (NWMP-2) Type of Water body RIVER Completed by DO, PALAKKAD

Agency Kerala State Pollution Control Board 1 Station Code 2 3 3 2 Date and time of sample taken 04.12.2020 2 (DD/MM/YY, HH/MM) 1 0 : 3 0 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm 50 – 100 cm √ >100 cm Flood Clear √ Turbid Green Brown 5 Color & Intensity 1 = Light 2 = Moderate √ 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √

9 Human activities around the station Cattle wading Tourism spot Fishing Bathing √ Other U/s of town or D/s of town or Pilgrim center/Bathing 10 Location details None industrial area √ industrial area Ghat/Water intake 11 Flow rate 88 m 3 /s

12 Major polluting source Industrial effluent MSW PW None √ Other Drinking water source Irrigation Fishing Domestic √ 13 Uses of water in downstream Organized water Bathing Cultivation Others source Ghat

Sl.No Determinant Value 1 Temperature, 0 C 29 2 pH 7.42 3 Conductivity, µmhos/cm 291.6 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 92 7 Chloride, mg/l 35 8 COD, mg/l 8 9 TKN, mg/l 0.002 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 96

12 Calcium, as CaCO 3 mg/l 50

13 Magnesium as CaCO 3 , mg/l 46 14 Sulphate, mg/l 7.2 15 Sodium, mg/l 20.3 16 Total Dissolved Solids, mg/l 181 17 Total Fixed Solids, mg/l 112 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.026 20 Boron, mg/l BDL 21 Potassium, mg/l 3.3 22 BOD, mg/l 1.66 23 Fluoride, mg/l 0.203 24 Dissolved Oxygen, mg/l 7.2 25 Nitrate-N, mg/l 0.321 26 Total Coliform, MPN/100 ml 250 27 Fecal Coliform, MPN/100 ml 100 28 Fecal Streptococci MPN/100 ml ABSENT 29 SAR 4.6 POLLUTED RIVER STRETCH MONITORING PROGRAMME DATA SHEET DECEMBER- 2020 Veliamkallu regulator ( D/S of NWMP-2) Station Name BHARATHAPUZHA AT PATTAMBI Type of Water body RIVER Completed by DO, PALAKKAD Agency Kerala State Pollution Control Board 1 Station Code 2 3 3 2 Date and time of sample taken 04.12.2020 2 (DD/MM/YY, HH/MM) 1 1 : 1 5 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm 50 – 100 cm >100 cm √ Flood Clear √ Turbid Green Brown 5 Color & Intensity 1 = Light 2 = Moderate √ 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √ 9 Human activities around the station Cattle wading Tourism spot Fishing Bathing √ Other U/s of town or D/s of town or Pilgrim center/Bathing 10 Location details None industrial area industrial area √ Ghat/Water intake 11 Flow rate 270 m 3 /s 12 Major polluting source Industrial effluent MSW PW None √ Other Irrigation Drinking water source √ Fishing Domestic 13 Uses of water in downstream Organized water source Cultivation Bathing Ghat Others

Sl.No Determinant Value 1 Temperature, 0 C 28 2 pH 7.46 3 Conductivity, µmhos/cm 340 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 96 7 Chloride, mg/l 41 8 COD, mg/l 8 9 TKN, mg/l 0.003 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 106

12 Calcium, as CaCO 3 mg/l 60

13 Magnesium as CaCO 3 , mg/l 46 14 Sulphate, mg/l 11.79 15 Sodium, mg/l 23.6 16 Total Dissolved Solids, mg/l 202 17 Total Fixed Solids, mg/l 137 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.0064 20 Boron, mg/l BDL 21 Potassium, mg/l 4.2 22 BOD, mg/l 1.93 23 Fluoride, mg/l 0.31 24 Dissolved Oxygen, mg/l 7.3 25 Nitrate-N, mg/l 0.63 26 Total Coliform, MPN/100 ml 200 27 Fecal Coliform, MPN/100 ml 50 28 Fecal Streptococci MPN/100 ml 10 National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER BHAVANI, PALAKKAD- DECEMMBER 2020 S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ March 2020. Action plan completed. Septic tank remediation Target systems are adopted for entire sewage achieved treatment Commencement of setting up of STPs and connecting all Not proposed Not Applicable the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including STP not Septic tank systems are adopted for completion of setting up STPs and their Commissioning Proposed entire sewage treatment 5 Chief Secretaries may set up appropriate monitoring Applicable at Not Applicable mechanism at state level State level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place Applicable at Not Applicable State level 6 Progress report may be furnished by the State/UTs to Applicable at Not Applicable  Secretary,Ministry of Jal Shakti State level  Member Secretary,CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains Drains Not Applicable contributing to river pollution and action as per NGT contributing order on in-situ treatment. pollution to the River were not identified

(II) Status of STPs, I&D and sewerage networks Details of Not Proposed Not Applicable Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Not proposed Not Applicable Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Dec 2020 Dry waste- Implemented Material Processing Facilities Collection Facility and 80% of work Details of Existing Infrastructure,Gap Analysis, completed for MSW treatment plant. Proposed along with completion timeline Wet waste- 100% Managed at source level

(v) Latest water quality of polluted river, its tributaries, March 2021 Water quality monitoring of polluted river drains with flow details and ground water quality in stretch and three additional points were the catchment of polluted river; completed until December 2020

(vi)Preventing dumping of waste and scientific waste Implemented Not applicable management including bio-medical waste, plastic by January waste and decentralizing waste processing, including 2020 waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation No specific Not applicable proposal

(viii) Adopting good irrigation practices No specific Not applicable proposal

(ix) Protection and management of food plain Zones (FPZ) March 2021 Project Preparation is going on (a total of 4 check dams are present in the river course of Bhavani which already contribute to the restoration of the river. Two new check dams are proposed in the River Bhavani- Veettiyoor and Parappanthara)

(x) Rain water harvesting No specific Not applicable proposal

(xi)Maintaining minimum Environmental flow of river March 2021 Project Preparation in the final stage

(xii) Plantation on both sides of the river No specific Not applicable proposal

(xiii)Setting up biodiversity parks on flood plains by No specific Not applicable removing encroachment proposal ACTION PLAN FOR RIVER BHAVANI, KERALA

No. Activity Implementin Time line Progress in the Progress in the % works Details of works (as per g agency month of month of completed remaining Action November December Plan) C(ii) Establishment of MSW treatment Plant (Solid Pudur Grama 2019-2020 Building Own fund 80% 20% - Waste Management) Panchayath construction and position has not imple installation of other primary sufficient for ment treatment works are doing this project ed equipment/ completed because further facilities are implementations remaining are pending C(ii) Material collection Facility (Solid Waste Pudur Grama 2019-2020 90% implemented Implemented 100% Nil Management) Panchayath Impl eme nted C(ii) Construction of Compound wall Material Pudur Grama 2019-2020 Implemented Implemented Implemented Nil collection Facility Plant Panchayath

C(ii) Installing of waste Bin in Colonies Pudur Grama 2019-2020 Minis MCF in the Minis MCF in 16% 84% Panchayath colonies of Pudur the colonies of implemente implem Panchayath were Pudur d entation started as an Panchayath remaini ng alternative of were started as installation of an alternative waste bin in the of installation colonies. Mini of waste bin in MCF facility were the colonies. installed in the Mini MCF two wards and facility were its coverage will installed in the be extend over two wards and all the 13 wards its coverage will within March be extend over 2021 all the 13 wards within March 2021 C(ii) Preliminary expenses met for Pudur Grama 2019-2020 Implement Implemen 100% Nil “harithakarmasena” Panchayath ed ted implemente d A(b) Construction of Community Toilets Pudur Grama 2019-2020 The operation The operation Panchayath and maintenance and maintenance of community of community toilet will not be toilet will not be effective in the effective in the Panchayath A Panchayath A total of 1500 total of 1500 individual toilets individual toilets were sanctioned were sanctioned and installed in and installed in the various colonies of the the various Panchayath as colonies of the an alternative of Panchayath as an the community alternative of the toilet. community toilet

A(b) Repair of Community toilets Pudur Grama 2019-2020 Not Applicable Not Applicable Nil Nil Panchayath

C(i) Construction of Protection wall with fencing Irrigation 2020-21 As part of the Final Project Work not Full department MNRGES report with started implem program,bank estimation will be entation erosion in the finalised remaini Bhavani River ng was identified and the protection wall on the river banks were constructed using jungle stones along 1.5km. Irrigation department will investigate the need and possibility of protection –wall with fencing, if needed further in the river stretch in consultation with the Panchayath.

C(i) Seasonal clearance of jungle and muddies from Irrigation 2020 - 21 Field studies going Estimate under Work not Full river courses department on preparation started implem entation remaini ng D Construction of Check dams at the identified Irrigation 2020 - 21 A total of 4 check Two new check locations department dams are present dams are in the river course proposed in the

of Bhavani which River Bhavani- already contribute Veettiyoor and to the restoration Parappanthara. of the river. The Work awarded possibility and for the Check utility of the new dam at check dams will be Veettiyoor. studied Investigation study is going on for Parappanthara D Issues relating to Eflow, maintaining minimum Irrigation 2020 - 21 E flow studies are E flow studies are Implementa Full environmental flow of river(by having watershed department already completed already tion not implementatio management provisions) for Attappady dam completed for started n remaining project. The same Attappady dam will be reviewed project. The for this particular same will be area reviewed for this particular area

E Information Education and Communication Pudur Grama 2019 -20 Awareness Implemented Impl Implem (IEC) Panchayath programs eme ented conducted nted A(a) Monitoring of river water quality by sampling KSPCB 2019 -20 Water quality Water quality Implemente Implemented. monitoring in monitoring in d. Continued Continued up Bhavani at Bhavani at up to March to March 2021. Elachivazhiand Elachivazhi and 2021. River River is three additional three points were additional is consistently completed until points were consistently achieving November 2020 completed achieving bathing until December 2020 bathing standards. standards.

POLLUTED RIVER STRETCH MONITORING PROGRAMME DATA SHEET DECEMBER- 2020 Cheerakuzhi (U/S of NWMP-6) Station Name RIVER BHAVANI AT ELACHIVAZHI Type of Water body RIVER Completed by DO, PALAKKAD Agency Kerala State Pollution Control Board 1 Station Code 1 2 0 8 Date and time of sample taken 03.12.2020 2 (DD/MM/YY, HH/MM) 1 1 : 4 5 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm 50 – 100 cm √ >100 cm Flood 5 Color & Intensity Clear √ Turbid Green Brown 1 = Light √ 2 = Moderate 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √ 9 Human activities around the station Cattle wading √ Tourism spot Fishing Bathing √ Other 10 Location details U/s of town or D/s of town or Pilgrim center/Bathing None √ 11 Flow rate 44 m 3 /s 12 Major polluting source Industrial effluent MSW PW None √ Other Irrigation √ Drinking water source √ Fishing Domestic √ 13 Uses of water in downstream Organized water source Cultivation Bathing Ghat Others

Sl.No Determinant Value 1 Temperature, 0 C 22 2 pH 7.51 3 Conductivity, µmhos/cm 114 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 46 7 Chloride, mg/l 8 8 COD, mg/l 4 9 TKN, mg/l BDL 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 46

12 Calcium, as CaCO 3 mg/l 24

13 Magnesium as CaCO 3 , mg/l 22 14 Sulphate, mg/l BDL 15 Sodium, mg/l 5.6 16 Total Dissolved Solids, mg/l 66 17 Total Fixed Solids, mg/l 41 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.032 20 Boron, mg/l BDL 21 Potassium, mg/l 1.3 22 BOD, mg/l 0.8 23 Fluoride, mg/l 0.41 24 Dissolved Oxygen, mg/l 7.6 25 Nitrate-N, mg/l 0.72 26 Total Coliform, MPN/100 ml 200 27 Fecal Coliform, MPN/100 ml 100 28 Fecal Streptococci MPN/100 ml ABSENT 29 SAR 3.49

POLLUTED RIVER STRETCH MONITORING PROGRAMME DATA SHEET DECEMBER- 2020 Chalayur Uru (U/S of NWMP-6) Station Name RIVER BHAVANI AT ELACHIVAZHI Type of Water body RIVER Completed by DO, PALAKKAD Agency Kerala State Pollution Control Board 1 Station Code 1 2 0 8 Date and time of sample taken 03.12.2020 2 (DD/MM/YY, HH/MM) 1 2 : 0 5 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm √ 50 – 100 cm >100 cm Flood Clear √ Turbid Green Brown 5 Color & Intensity 1 = Light √ 2 = Moderate 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √ 9 Human activities around the station Cattle wading √ Tourism spot Fishing Bathing √ Other 10 Location details U/s of town or D/s of town or Pilgrim center/Bathing None √ 11 Flow rate 38 m 3 /s 12 Major polluting source Industrial effluent MSW PW None √ Other Irrigation √ Drinking water source √ Fishing Domestic √ 13 Uses of water in downstream Organized water source Cultivation Bathing Ghat Others

Sl.No Determinant Value 1 Temperature, 0 C 22 2 pH 7.52 3 Conductivity, µmhos/cm 142 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 60 7 Chloride, mg/l 10 8 COD, mg/l 4 9 TKN, mg/l BDL 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 58

12 Calcium, as CaCO 3 mg/l 32

13 Magnesium as CaCO 3 , mg/l 26 14 Sulphate, mg/l 0.479 15 Sodium, mg/l 6.6 16 Total Dissolved Solids, mg/l 84 17 Total Fixed Solids, mg/l 57 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.032 20 Boron, mg/l BDL 21 Potassium, mg/l 2.1 22 BOD, mg/l 0.53 23 Fluoride, mg/l 0.291 24 Dissolved Oxygen, mg/l 7.3 25 Nitrate-N, mg/l 0.825 26 Total Coliform, MPN/100 ml 200 27 Fecal Coliform, MPN/100 ml 100 28 Fecal Streptococci MPN/100 ml ABSENT 29 SAR 3.37

POLLUTED RIVER STRETCH MONITORING PROGRAMME DATA SHEET DECEMBER 2020 Karathur (D/S of NWMP-6) Station Name RIVER BHAVANI AT ELACHIVAZHI Type of Water body RIVER Completed by DO, PALAKKAD Agency Kerala State Pollution Control Board 1 Station Code 1 2 0 8 Date and time of sample taken 03.12.2020 2 (DD/MM/YY, HH/MM) 1 2 : 2 0 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm 50 – 100 cm √ >100 cm Flood Clear √ Turbid Green Brown 5 Color & Intensity 1 = Light √ 2 = Moderate 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √ 9 Human activities around the station Cattle wading √ Tourism spot Fishing Bathing √ Other 10 Location details U/s of town or D/s of town or Pilgrim center/Bathing None √ 11 Flow rate 65 m 3 /s 12 Major polluting source Industrial effluent MSW PW None √ Other Irrigation √ Drinking water source √ Fishing Domestic √ 13 Uses of water in downstream Organized water source Cultivation Bathing Ghat Others

Sl.No Determinant Value 1 Temperature, 0 C 22 2 pH 7.44 3 Conductivity, µmhos/cm 156.7 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 60 7 Chloride, mg/l 12 8 COD, mg/l 4 9 TKN, mg/l BDL 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 58

12 Calcium, as CaCO 3 mg/l 32

13 Magnesium as CaCO 3 , mg/l 26 14 Sulphate, mg/l 0.621 15 Sodium, mg/l 7.6 16 Total Dissolved Solids, mg/l 89 17 Total Fixed Solids, mg/l 60 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.038 20 Boron, mg/l BDL 21 Potassium, mg/l 3.2 22 BOD, mg/l 0.73 23 Fluoride, mg/l 0.261 24 Dissolved Oxygen, mg/l 7.26 25 Nitrate-N, mg/l 0.953 26 Total Coliform, MPN/100 ml 250 27 Fecal Coliform, MPN/100 ml 100 28 Fecal Streptococci MPN/100 ml 10 28 SAR 3.62

NATIONAL WATER QUALITY MONITORING PROGRAMME (NWMP -6 DATA- DECEMBER- 2020)

Station Name RIVER BHAVANI AT ELACHIVAZHI Type of Water body RIVER Completed by DO, PALAKKAD Agency Kerala State Pollution Control Board 1 Station Code 1 2 0 8 Date and time of sample taken 03.12.2020 2 (DD/MM/YY, HH/MM) 1 2 : 3 0 3 Weather Cloudy Clear √ Windy Raining 4 Approximate depth of main stream < 50 cm √ 50 – 100 cm >100 cm Flood Clear √ Turbid Green Brown 5 Color & Intensity 1 = Light √ 2 = Moderate 3 = High

6 Odour None √ Fishy H 2 S Other 7 Floating Matter Floating Algae Floating sludge Oil & Grease Water Hyacinth 8 Visible effluent discharges in proximity Industrial Municipal sewage None √ 9 Human activities around the station Cattle wading √ Tourism spot Fishing Bathing Other 10 Location details U/s of town or D/s of town or Pilgrim center/Bathing None √ 11 Flow rate 50 m 3 /s 12 Major polluting source Industrial effluent MSW PW None √ Other Irrigation √ Drinking water source √ Fishing Domestic 13 Uses of water in downstream Organized water source Cultivation Bathing Ghat Others

Sl.No Determinant Value 1 Temperature, 0 C 22 2 pH 7.64 3 Conductivity, µmhos/cm 147.5 4 Turbidity, NTU BDL

5 Phenolphthalein Alkalinity, as CaCO 3 mg/l BDL

6 Total Alkalinity, as CaCO 3 mg/l 58 7 Chloride, mg/l 11 8 COD, mg/l 4 9 TKN, mg/l BDL 10 Ammoniacal-N, mg/l BDL

11 Hardness, as CaCO 3 mg/l 60

12 Calcium, as CaCO 3 mg/l 32

13 Magnesium as CaCO 3 , mg/l 28 14 Sulphate, mg/l 0.87 15 Sodium, mg/l 6.1 16 Total Dissolved Solids, mg/l 89 17 Total Fixed Solids, mg/l 55 18 Total Suspended Solids, mg/l BDL 19 Phosphate, mg/l 0.006 20 Boron, mg/l BDL 21 Potassium, mg/l 1.3 22 BOD, mg/l 0.86 23 Fluoride, mg/l 0.36 24 Dissolved Oxygen, mg/l 7.2 25 Nitrate-N, mg/l 0.256 26 Total Coliform, MPN/100 ml 300 27 Fecal Coliform, MPN/100 ml 100 28 Fecal streptococci , MPN/100 ml ABSENT 29 SAR 3.19

National Mission for Clean Ganga Format for Submission of Monthly Progress Report by States/UTs- DECEMBER 2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KAVVAYI, , KERALA Sl. Activity to be monitored Submission of progress by State/UT- No. Timeline Compliance status 1 Ensure 100% treatment of sewage at least in-situ All houses and establishments have their on remediation disposal facility Commencement of setting up of STPs and connecting all No STP proposed the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including 31/03/20 Nil completion of setting up STPs and their Commissioning 22 5 Chief Secretaries may set up appropriate monitoring - mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place - 6 Progress report may be furnished by the State/UTs to -  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with In GP, There are 5 natural drains completion timelines on: meeting the Kavvayi river, of which 3 drains (I) Identification of polluting sources including drains cleaned. contributing to river pollution and action as per NGT 1.Parappa Thodu (Ward 6)- 1 Km. order on in-situ treatment. 2.Chennakki Thodu (Ward 8) – 1.3 Km. 3.Kallayi Thodu (Ward 3&4) – 1 Km. (II) Status of STPs, I&D and sewerage networks Details of Two are partly cleaned and the cleaning work Existing Infrastructure, Gap Analysis, Proposed along is in progress. with completion timeline 1.Manthan Thodu (Ward 6) -1 Km 2.Ambachikundu Thodu (Ward 15) – 500 M

(The work is slowly ongoing due to the higher (III) Status of CETPs level of water in stream) Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of RRF at block level. Processing Facilities Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, Lab analysis report by KSPCB is attached drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste Awareness campaign, CCTV installation management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting Implementing in all house-holds as per KPBR rules. (xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii)Setting up biodiversity parks on flood plains by removing encroachment

ACTION PLAN progress FOR RIVER KAVVAYI, Kannur, KERALA Action Plan of Local Body

No. Progres Progress in (as s in the Progress in the % works Implementin the month per Activity Time line month month of Dec. complet Details of works Remaining Action g agency of of Nov. 2020 ed Plan) Oct.2020 2020 Sanitation Facility Sewage Treatment Plant –DPR A (b) Payyannur Septage treatment N Prepared. Waiting for the Municipality 10 facility shall be provided 2021 NIL I NIL approval of Suchitwa Mission % by Local Bodies in L various places. C(ii) Biodegradable waste disposal No Payyannur Project Implementation in Ring compost 2061 2022 0 progress 40% Municipality 0 Progress Kitchen bin 10992 reported Bio gas Plant 775 A(b) Non biodegradable Waste Payyannur - - Disposal Municipality 2022 - 1 MCF &RRF in Function MCF and RRF E Awareness Payyannur Municipality 9 Ongoing Youth, Asha workers and other 90% 0 90% 90% On going project stake holders and Haritha % sahaya Samithi E Installation of CCTV (m) - - No - - cameras at major points 2019 updation received

C(ii) Biodegradable waste disposal Kankol Ongoing Not reported Bio bins, Pit Compost, Bio gas Plant(2460 Nos) A(b) Non biodegradable Waste Kankol Ongoing ‘’ Disposal MCF project E Awareness Kankol Once in a ‘’ month Youth, Asha workers and other stake holders

A (b) Sanitation Facility in markets Ramanthali GP 2020 av available ava 100 % available ail ilab abl le e A(b) Non Biodegradable waste Ramanthali GP 2020 no no yes 70 % On 09/2020 Disposal MCF onwards waste collected are transferring to MCF. 5 mini MCF PROPOSED. A (b) Drain Cleaning Ramanthai 2022 do done On 70 % 3/5 drains are and side protection GP ne goi cleaned. ng Remaining 2 are pending due to higher level of water in the stream. E Renovation of Thrikkaripur - 2019 NA NA NA NA NA Ponds & Construction of Platform CWRDM to openwell (Implementation of Map of Kavvayi Wetland system of Northern Kerala) Action Plan by Irrigation Department

No. Activity Implementing Time line Progress Progress in the % works Details of works (as per agency in the month of August completed remaining Action month of 2020 Plan) July 2020 E Desilting and rejuvenation of Irrigation DPR NarangaThodu in Payyannur Department 2020 submitted Municipality for 5 Lakhs

by MI division, KNR.

Combined Action by KSPCB

No. Activity Implementing Time line Progress in Progress in the Progress in the % works Details of works Remarks (as agency the month month of month of completed remaining per of August September October 2020 Action Plan) 1 Sanitation Local body Providing of toilets to residences With treatment and disposal system for sewage and sullage 2 Community Toilet All local bodies, Proposed construction of newcommunity SuchitwaMi Toilet at satellite points on the ssion, bank of river Revenue department 3 Rain water recharge All local bodies, Entry of rain water and rain Kerala Water water recharging to all thodu Authority, and drain

4 Solid waste management PollutionControl Board, Health Check they have Board’s consent authority and sanitation facilityis provided.

5 Household waste Adequate number Municipalities of 10992 and local bodies Kitchen bins shall be provided 6 Market

Providing proper waste handling Six facility for wastewater months And solid wastes

30 7 Rendering plant Rendering Local body Six Agreement plant for poultry wastes months description

8 Slaughter house Slaughter house waste disposal facility Local body 9 Establishment like service station Pollution and workshops Control Board Six months Strict monitoring of disposal of waste(sewage, sullage, degradable waste, non- biodegradable waste) surveyed area and also in the catchment of the river i)Verify Whether consent to operate of the Board exists

10 Sanitation survey should be done Six Sanitation survey is to be conducted Pollution months Control Board for 100m on either sides of the other parts of polluted stretch if any located nearby 11 Awareness Awareness for residence Suchitwa Once in a association Mission/ month LSGD/Corp oration

1. Proper awareness among the inhabitants in the area is to be given for protecting the water bodies. Basic training for the people at the grass root level is to be provided for river management. All efforts for maintaining the quality of water bodies may be done by the Panchayat/Municipal authorities only with people’s participation. 2. The nearby gramapanchayath and municipalities are mainly responsible for not providing municipal waste collection and treatment facilities in the locality. So they must be instructed to provide the required facility for scientific disposal of municipal solid waste as per the MSW rules 2016. The citizens as well as the municipal/gramapanchayath authorities need to be aware of the importance of scientific disposal of waste generated. Their attitude towards handling waste has to be changed. Reducing waste, recovering recyclable materials, return of nutrients to the eco system as well as generation of energy from waste are to be practised. There has to be a valid scheme for collection, segregation, transportation, processing and safe disposal of waste by the authorities. For this affordable and viable waste to energy conversion technologies apart from conventional composting is to be implemented by the municipalities seeking technical expertise. 3. Propagation of vegetative cover in water shed will reduce soil erosion and enhance percolation of rain water into the sub surface. In downstream stretches where the river is saline, propagation of mangroves are essential. 4. Strict monitoring from the part of implementing as well as monitoring agencies is required for effective functioning of waste treatment facilities in waste generating units. 5. The practice of waste dumping into the river is to be prevented legally and strict action against this practice is to be adopted at panchayath and municipality level. 6. Re-survey of the river boundaries throughout the entire stretch is to be done urgently so as to prevent encroachment of the river. 7. The municipalities as well as the panchayaths are to be directed to provide proper waste management facilities of their own. All towns and cities must have Sewage Treatment Plants (STPs) that clean up the sewage. Facility for collection, segregation, transport, processing and scientific disposal of waste generated are to be provided by the local authorities in strict adherence to the Municipal Solid Waste Management Rules, 2016. For this, affordable and viable waste to energy conservation technologies apart from conventional composting is to be implemented seeking technical expertise. 8. Strict monitoring from the part of implementing as well as monitoring agencies is required for effective functioning of waste treatment facilities in waste generating units. The riverine stretches are to be monitored periodically at identified locations for water quality assessment.

9. Modern agricultural practices and technologies introduce the use of inorganic fertilizers with Nitrogen, Phosphorous, Potash and inorganic pesticides in farm lands and play important role in the river pollution. These may concentrate into the water body through run off causing algal blooms by which whole stretch of water become choked. Fertilizers and chemicals application in agricultural lands are to be strictly under technical expertise. 10. Rain water recharging measures must be adopted. 11. Eco tourism and water tourism projects are to be designed giving due importance for protecting the environment. The activities are to be organized in such ways which do not induce any types of pollution to the water body. Strict monitoring from the concerned authorities are recommended in functioning of the tourism projects. 12. Implement Green Protocol effectively in local self-governments. Prohibit littering of plastics in the area. Plastic wastes shall be handled as per the provisions of Plastic Waste (Management and Handling) Rules, 2018. 13. The existing waste water treatment facilities of Municipality shall be augmented in such a way so as to operate round the year. 14. Actions shall be taken by the local bodies to clean the storm water drains. Rejuvenation of small streams, creeks leading into the river is to be done.

15. Round the clock patrolling shall be provided so as to prevent waste dumping on public places.

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs- DECEMBER 2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER KUPPAM, KANNUR, KERALA S. Activity to be monitored Submission of progress by State/UT- No. Timeline Compliance status 1 Ensure 100% treatment of sewage at least in-situ Almost all residential building and commercial remediation establishments are having in site sewage remediation. Such as septic tank/ soak pit. Commencement of setting up of STPs and connecting all A Common STP is at Taliparamba the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including - completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring - mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place - 6 Progress report may be furnished by the State/UTs to -  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains Drain identified. Pre monsoon cleaning by contributing to river pollution and action as per NGT Haritha Karma Sena periodically. order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities RRF at block level. Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in Lab analysis report by KSPCB is attached. the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic Door to door collection of non-bio degradable waste and decentralizing waste processing, including waste by Haritha Karma Sena. Bio medical waste generated from hotels, Ashrams, etc. waste is handled by CBMWTF

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting As per KPBR rules mandatory for new residential buildings. (xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river Mangrove plantation by GP ongoing.

(xiii)Setting up biodiversity parks on flood plains by As reported by Ezhome GP, Kottila Higher removing encroachment secondary school is proposed for making Bio diversity park ACTION PLAN FOR RIVER KUPPAM, KERALA

Ref para Implementing Agency Time Progress in the Progress in the % works Details of no:48 as Activity per NGT month of month of completed works order of Completion October 2020 November 2020 remaining Progress in the 673/2018 dated:2 month of December 0.0 9.2018 2020 Udayagiri GP

90 septic tank - 90 % 10 septic tank Udayagiri GP completed work on going Sanitation Facility A (b) 03/2020 Compost pit- 95, - - Biodegradable Ongoing Udayagiri GP bio gas- 30, soak waste disposal C (ii) project pit- 12 completed. Construct - - C (ii) ion of Non bio Material Clean Kerala Company Ongoing degradable Collectio project Waste Disposal n Facility complete d. Youth, Asha workers Ongoing project On going - - E Awareness and other stake holders

Identific ation of Udayagiri GP 09/2019 Identified 100 - illegal outlets in to drains % drains and stoppage are of the same cleaned A (b) by ward sanitatio n committe e and Haritha Karma Sena. Ezhome GP Ezhome GP 2019 available 100 A (b) Sanitation Facility % 2020 298 ring - Ward Sanitation compost Committee of Local C (ii) Biodegradable installation Body waste disposal is going to staff. Non bio 28 Haritha - Local body (Haritha degradable Waste Karma Sena C (ii) Karma Sena) Disposal 2022 members collecting plastic waste to 2 MCF in the GP. Awareness Youth, Asha workers 03/2020 On going 90 % E and other stake holders (Will extend if necessary) Identific ation of Ezhome Panchayat 06/2020 Completed. 100 - illegal outlets in to Pre % drains and monsoon cleaning A (b) stoppage of the work by same ward sanitation committee and NREGS employees. Panchayat

Pariyaram Panchayat 03/2020 Toilet- 73, 100 - A (b) Sanitation Facility soak pit- 196 % Pariyaram GP 03/2022 Ring - - compost- C (ii) Biodegradable 550, pipe waste disposal compost- 2500, BAKASHI- 10, Bio bin- 92, dung pit- 207, bio gas plant- 3, portable bio gas- 33 Non bio Pariyaram Panchayat On going A ton - 4 ton degradable Waste project handed over ready C (ii) Disposal to Clean to Kerala hand Company over Awareness Youth, Asha workers Whenever On going - - E and other stake necessary holders Identific ation of Pariyaram Panchayat 09/2019 completed 100 - illegal outlets in to % drains and A (b) stoppage of the same GP

13 soak pit 100 - A (b) Sanitation Facility 2022 completed % Local Body Ward Sanitation Bio bins, pit 100 ring compost -2022 Committee of Local compost C (ii) Biodegradable supplied, 7 waste disposal body compost pit 5 Thu Thumpoormuzhi = Estimate mbo 2020 prepared for or 5 thumboor mooz moozhi hi

Non bio Haritha Karma sena On going Received TS 15 degradable Waste project for 15 mini mini C (ii) Disposal MCF mcf Awareness Youth, Asha workers On going On going 90 % E and other stake project holders Identification of Local Body 2022 On going 100 illegal outlets in to % drains and A (b) stoppage of the same Thalipparamba Municipality Municipality Not received A (b) Sanitation Facility Progress report ‘’

C (ii) Biodegradable waste disposal

Non bio Haritha Karma sena ‘’ degradable Waste C (ii) Disposal Awareness Youth, Asha workers Once in a ‘’ E and other stake month holders GP A (b) Sanitation Facility Pattuvam GP On going 9 Soak pit 40 % 60 % project given

C(ii) Biodegradable Ward sanitation On going Compost pit 65 % 35 % waste disposal committee of the local project -5, order body placed for ring compost- 133

Non bio Haritha Karma sena On going 5.82 tons of 60 % 40 % C (ii) degradable Waste project plastic waste Disposal disposed to Clean Kerala Company Awareness Youth, Asha workers Whenever Awareness 100 - E and other stake necessary given to % holders Asha workers by Health department. Removal of Pattuvam GP - No illegal NA NA plastic wastes outlets into C (ii) from the river drains. bank

Action Plan by Irrigation Department

Sl no Activity Implementing Time for Progress in Progress in % Details of works Agency completion the month of the month work remaining October 2020 of Progress in s November the month com 2020 of December plet 2020 ed 1 Providing fencing on Kuppam bridge (NH) Irrigation 2021 DPR submitted across at Thalipparamba in department for FS 45 Lakhs Thalipparamba Municipality

2 Providing Fencing on Pazhayangadi Bridge Irrigation 2021 DPR submitted across Kuppam River at Department for FS 65 Lakhs Pazhayangadi 3 Regualting activites in flood plain zone, Irrigation 3 years Eviction of protection and management of flood plain Department encroachment to zone be done, bio cover works to be done by social forestry dept. 4 Greenery development- Plantation plan. Irrigation 3 years DPR submitted for Plantation on both sides of the river, setting up Department FS 30 Lakhs. biodiversity parks on flood plains by removing encroachment

5 Issues relating to E- flow, maintaining Irrigation 3 years minimum environmental flow of river(by Department having watershed management provisions)

Combined Action Plan

Agency Timeline Progress in Progress in Progress in % works Details of Proposed action the month the month the month completed works of October of of remaining 2020 November December 2020 2020 1 Provide toilets to residences Local Body with treatment and disposal system for sewage and sullage 2 All local bodies Proposed Construction Construction of new Suchitwa Mission, Of new community community toilets with Revenue Toilet at satellite points treatment system department on the bank of river 3 All local Drains are inspected Entry of rain water and rain water recharging to all channels bodies , Kerala before rain and all and drain Water channels and stream Authority are cleaned once in a year 4 Sanitary facility in hotels (around 7) one hospital, Establishments Pollution Control situated in the ward for the Check they have board Board , Health consent and sanitation segregation, treatment and department facility is provided disposal of solid wastes as per SolidWastesManagementRules, 2016

5 Adequate number of kitchen Municipalities bins shall beprovided and local bodies One project year 6 Local body Providing proper waste One project year handling facility. For wastewater and solid wastes

21 As per their project and 7 Rendering plant for poultry wastes Local body fund availability One common 8 Local body Slaughter house waste disposal slaughter house for 3 facility to 4 local body 9 Strict monitoring of disposal of Pollution Six months waste(sewage, sullage, Control Board degradable waste, non- biodegradable waste) surveyed area and also in the catchment of theriver i)Verify Whether consent to operate of the Board exists Pollution Six months 10 Sanitation survey is to be Control Board conducted for 100m on either sides of the other parts of polluted stretch if any located nearby Awareness for Suchitwamission/L Once in a month 11 residence association: SGD/Corporation

Action Plan by Ground Water Department

Sl.No Ref para Activity Progress in the Progress in the % works Details of works no:48 as per NGT month of month of completed remaining order October 2020 November 2020 Progress in the 673/2018 month of dated:20. 09.2018 December 2020 1 B(i) Ground Water resources and regulation of ground water extraction by industries particularly in over expolited as critical zones/blocks

22 2 B(ii) Ground water recharging / rain water harvesting 3 B(iii) Periodic ground waste quality assessment and remedial actions in case of con taminated ground water tube wells/bore wells or hand pumps 4 B(iv) For regulating use of ground water for irrigation purpose, adopting good irrigation practices

23 National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs- DECEMBER 2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER PERUVAMBA, KANNUR, KERALA

S. Activity to be monitored Submission of progress by State/UT- No. Timeline Compliance status 1 Ensure 100% treatment of sewage at least in-situ March Almost all residential building and commercial remediation 2020 establishments have in situ sewage remediation facilities such as septic tank and soak pit. Commencement of setting up of STPs and connecting all 2021 Proposed 10 KLD STP at Payyanur municipality, the drains and other sources of generation of sewage to Perumba fish market, is still in DPR stage. the STPs must be ensured 2 Timeline for completing all steps of action plans including - March 2022 completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring - mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place - 6 Progress report may be furnished by the State/UTs to -

 Secretary, Ministry of Jal Shakti  Member Secretary, CPCB

6.1 Progress Report may be comprised of details along with As reported by Ramanthili GP, There are 5 completion timelines on: natural drains for the river of which 3 drains (I) Identification of polluting sources including drains are cleaned contributing to river pollution and action as per NGT 1) Parappa thode (wrd 6) – 1 km order on in-situ treatment. 2) Chennaki thode (wrd 8)- 1.3 km 3) Kallayi thode (wrd 3&4)- 1 km Remaining 2 are manthan thode(wrd 6)-1 km, Ambachikund thode(wrd 15)- 500 m are partly cleaned.

(II) Status of STPs, I&D and sewerage networks Details of STP proposed at Perumba fish market is still in Existing Infrastructure, Gap Analysis, Proposed along DPR stage, pending approval from Suchitwa with completion timeline mission, as reported by the Payyanur Municipality. (III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of RRF at block level. Processing Facilities Details of Existing Infrastructure, Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, Lab analysis report for the month of December drains with flow details and ground water quality in by the KSPCB is attached.

the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting Pre monsoon cleaning of river and its drains (xi)Maintaining minimum Environmental flow of river are taking place in each year.

(xii) Plantation on both sides of the river As reported by Kadannappally GP 500 trees were planted along the river stretch. (xiii)Setting up biodiversity parks on flood plains by removing encroachment

ACTION PLAN progress FOR RIVER PERUVAMBA, KANNUR, KERALA

Action Plan of Local Body

No. Activity Implementing agency Time Progre Progres % works Details of works (as per line ss in s in the completed remaining Action the month Plan) month of of Novem Progress in the Octobe ber month of r 2020 2020 December 2020 A(b) Sanitation Facility Payyannur Muncipality 2021 N N STP at 10 % Sewage I I DPR stage Treatment STP proposed at L L – no Plant, DPR market place progress prepared. Waiting approval from Suchitwa mission. C(ii) Biodegradable waste Payyannur Muncipality 2020 0 0 On going 40 % Project disposal implementation in progress. Ring compost ( 2061) Pit Compost (10992) Bio gas Plant (687) C(ii) Non bio degradable Payyannur Muncipality Ongoing 1 MCF & RRF is Waste Disposal functioning. MCF and RRF

E Awareness Payyannur Muncipality Ongoing 9 9 90 % 90 % On going project 0 0 Youth, Asha workers and other stake % % holders and Haritha sahaya Samithi A(b) Sanitation Facility Kadannappally 2019 Complete 100 % - Panchayath d Scientific Septic Tank and Soak pit C(ii) Biodegradable waste Kadannappally Every On going - 600 ring disposal Panchayath year compost project proposed for Bio bins, Pit Compost, 2021. Bio gas Plant C(ii) Non bio degradable Kadannappally Ongoing On going - - Waste Disposal Panchayath project MCF E Awareness Kadannappally Once in a On going 90 % Panchayath month Youth, Asha workers and other stake holders E Side wall protection Kadannappally 12/2019 500 trees 100 % of drains Panchayath were planted along the river side

E Sanitation Facility Kuttur 2019 complete 100 % d

C(ii) Biodegradable waste Eramam Kuttur Every Bio gas - disposal year plant project constructi Bio bins, Pit on Compost, Bio gas competed Plant . Thumboor moozhi – 3 nos On going C(ii) Non Bio degradable Eramam Kuttur Ongoing On going - waste disposal MCF E Awareness Eramam Kuttur Once in a On going 100 % month Youth, Asha workers and other stake holders E Side wall protection Eramam Kuttur 2021 300 m of drains complete d

A(b) Sanitation Facility Ramanthali GP a available 80 % available No markets and v houses on the bank a i l a b l

e

C(ii) Non Bio degradable Ramanthali GP 2020 n n Yes, 70 % NIL waste disposal o o 09/2020 onwards MCF and sending to non-bio RRF degradabl e wastes are transferri ng to MCF E Drain Cleaning and Ramanthali GP 2022 d d Cleaning 75% 2 drains are Side protection o o of 3/5 partly cleaned, n n natural Cleaning of e e drains which is complete pending due to d higher level of water in the stream. E Awareness Ramanthali GP 2022 On going 90 % On going

Youth, Asha workers and other stake holders C(ii) Bio degradable waste Ramanthali GP 2022 - 30 % 190 beneficiery disposal are listed and Ring Compost – 1000 approved. Nos Compost Pit – 2000 Nos

Biogas Plant – 100 Nos Action Plan by Irrigation Department

No. Activity Implementing agency Time Progre Progres % works Details of works (as per line ss in s in the completed remaining Action the month Plan) month of of Novem Progress in the Octobe ber month of r 2020 2020 December 2020 E Providing fencing Irrigation department DPR on Perumba bridge 2021 submitte (NH) across d for FS Perumba river at amount Payyannur in Payyannur rs 22 Municipality lakhs, under action plan for Perumba E Desilting and Irrigation Department 2021 Work reconstruction of proposed salt water by minor exclusion cross bar irrigation, across perumbathodu Kannur.

in Payyannur DPR Municipality submitte d for rs MI Class II Plan 30 lakh fund E Desilting and repair of Irrigation Department 2020 Work salt water exclusion complete cross bar across d under Koykottuvayal thodu SDRF in Panchayath scheme by MI State Disaster division, Response Fund Kannur. E Regulating activities Irrigation Department 3 years DPR in flood plain zone, submitte protection and d for FS, management of flood 70 Lakhs, plain zone Protection and soft copy management of flood submitte plain zone for a d on period of 3 years with 10/08/20 a fund of 0.50 crores 20 E Greenery Irrigation Department 3 years To development- ascertain Plantation plan. encroach Plantation on both ment/ sides of the river, setting up purambo biodiversity parks on kk, land flood plains by demarcat

removing ion by encroachment revenue departme Planting trees on the nt. For bank of the river will be completed within the same 3 years from the dt. commencement of Collector works with a fund of Kannur 0.40 crores has

already been addresse d from higher office. Planting trees to be done by social forestry dept. E Issues relating to E-Irrigation Department 2 years DPR flow, maintaining submitte minimum d for FS environmental flow 25 Lakhs. of river(by having watershed management provisions)

By Micro watershed managemen t for a period of 2 years with a fund of 0.25 Crore from the available fund Combined Action by KSPCB

No. Activity Implementing agency Time line Progre Progres % works Details of works (as per ss in s in the completed remaining Action the month Plan) month of of Novem Progress in the Octobe ber month of r 2020 2020 December 2020 1 Sanitation Local body Providing of toilets to residences With treatment and disposal system for sewage and sullage 2 Community All local bodies, Toilet SuchitwaMission,

Proposed Revenue department construction of new community Toilet at satellite points on the bank of river 3 Rain water All local bodies, Kerala recharge Water Authority, Entry of rain

water and rain water recharging to all thodu and drain

4 Solid waste management Pollution Control Board, Health authority Check they have Board’s consent and sanitation facility is provided.

5 Household waste Adequate number of Municipalities and local bodies Kitchen bins shall be provided 6 Market

Providing proper Six waste handling months facility for wastewater And solid wastes 30 7 Rendering Local body Six plant months Rendering plant for poultry wastes 8 Slaughter house Local body Slaughter house waste

disposal facility 9 Establishment like Pollution Control Board service station and Six workshops months

Strict monitoring of disposal of waste (sewage, sullage,degradable waste, non- biodegradable waste) surveyed area and also in the catchment of the river i) Verify Whether consent to operate of the Board exists 10 Sanitation survey Six should be done Pollution Control Board months Sanitation survey is to be conducted for 100 m on either sides of the other parts of polluted stretch if any located nearby 11 Awareness Suchitwa Mission/ Once in a Awareness for LSGD/Corporation month residence association

ACTION BY GROUND WATER DEPARTMENT

Sl. No. Ref para Activity Progress in Progress in % Details of works item nos the month of the month works remaining as per October of compl NGT 2020 November eted Order 2020 Progress no.673/2 in the 018 dated month of 20.09.201 Decembe 8 r 2020 1 B(i) Ground Water resources and regulation of ground water extraction by industries particularly in over exploited as critical zones/blocks (Earlier Status : As per Groundwater resources of Kerala, 2017 estimate a total number of 2 blocks (Neeleswaram and Payyannur) comes under the Peruvamba river basin. All the blocks in the river stretch are safe with stage of groundwater extraction ranges from 34.85% to 69.52%) 2 B(ii) Ground water recharging / rain water harvesting (Earlier Status : The average pre -monsoon groundwater level ranges from7.97mbgl - 8.81 mbgl. Department has implemented 5 no of bore well recharge structures and 3 dug well recharge at Cheemeni open prison in Neeleswaram block) 3 B(iii) Periodic ground waste quality assessment and remedial actions in case of contaminated ground water tube wells/bore wells or hand pumps (Earlier Status : Groundwater Department has 1 observation dug well and 1 piezometer for routine studies in the river stretch.) 4 B(iv) For regulating use of ground water for irrigation

purpose, adopting good irrigation practices

(Earlier status :The total irrigation draft in the area ranges from 695.64 - 1326.85 ha.m.)

Other than these following are some more suggestions from the part of pollution control Board.

1. Proper awareness among the inhabitants in the area is to be given for protecting the water bodies. Basic training for the people at the grass root level is to be provided for river management. All efforts for maintaining the quality of water bodies may be done by the Panchayat/Municipal authoritiesonly with people’s participation. 2. The nearby gramapanchayath and municipalities are mainly responsible for not providing municipal waste collection and treatment facilities in the locality. So they must be instructed to provide the required facility for scientific disposal of municipal solid waste as per the MSW rules 2016. The citizens as well as the municipal/gramapanchayath authorities need to be aware of the importance of scientific disposal of waste generated. Their attitude towards handling waste has to be changed. Reducing waste, recovering recyclable materials, return of nutrients to the eco system as well as generation of energy from waste are to be practised. There has to be a valid scheme for collection, segregation, transportation, processing and safe disposal of waste by the authorities. For this affordable and viable waste to energy conversion technologies apart from conventional composting is to be implemented by the municipalities seeking technical expertise. 3. Propagation of vegetative cover in water shed will reduce soil erosion and enhance percolation of rain water into the sub surface.In downstream stretches where the river is saline, propagation of mangroves are essential. 4. Strict monitoring from the part of implementing as well as monitoring agencies is required for effective functioning of waste treatment facilities in waste generating units. 5. The practice of waste dumping into the river is to be prevented legally and strict action against this practice is to be adopted at panchayath and municipality level. 6. Re-survey of the river boundaries throughout the entire stretch is to be done urgently so as to prevent encroachment of the river. 7. The municipalities as well as the panchayaths are to be directed to provide proper waste management facilities of their own. All towns

and cities must have Sewage Treatment Plants (STPs) that clean up the sewage. Facility for collection, segregation, transport, processing and scientific disposal of waste generated are to be provided by the local authorities in strict adherence to the Municipal Solid Waste Management Rules, 2016. For this, affordable and viable waste to energy conservation technologies apart from conventional composting is to be implemented seeking technical expertise. 8. Strict monitoring from the part of implementing as well as monitoring agencies is required for effective functioning of waste treatment facilities in waste generating units. The riverine stretches are to be monitored periodically at identified locations for water quality assessment. 9. Modern agricultural practices and technologies introduce the use of inorganic fertilizers with Nitrogen, Phosphorous, Potash and inorganic pesticides in farm lands and play important role in the river pollution. These may concentrate into the water body through run off causing algal blooms by which whole stretch of water become choked. Fertilizers and chemicals application in agricultural lands are to be strictly under technical expertise. 10. Rain water recharging measures must be adopted. 11. Eco tourism and water tourism projects are to be designed giving due importance for protecting the environment. The activities are to be organized in such ways which do not induce any types of pollution to the water body. Strict monitoring from the concerned authorities are recommended in functioning of the tourism projects. 12. Implement Green Protocol effectively in local self governments. Prohibit littering of plastics in the area. Plastic wastes shall be handled as per the provisions of Plastic Waste (Management and Handling) Rules, 2018. 13. The existing waste water treatment facilities of Taliparamba Municipality shall be augmented in such a way so as to operate round the year. 14. Actions shall be taken by the local bodies to clean the storm water drains. Rejuvenation of small streams, creeks leading into the river is to be done.

15. Round the clock patrolling shall be provided so as to prevent waste dumping on public places.

16. CCTV can be installed at suitable points in order to identify the persons/ establishments dumping waste in to river. All the local bodies

must establish slaughter houses with modern facilities and unauthorized slaughter houses shall be strictly enforced. 17. Strict action shall be taken against non-violating person/ agency by the authorities when noticed. Plantation of trees and plants on the bank will be highly effective in controlling the waste disposal.

National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs- DECEMBER 2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER RAMAPURAM, KANNUR, KERALA S. Activity to be monitored Submission of progress by State/UT- No. Timeline Compliance status 1 Ensure 100% treatment of sewage at least in-situ Almost all residential and industrial buildings remediation are having in situ sewage remediation.

Commencement of setting up of STPs and connecting all No proposals for STP the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including NA completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring - mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place - 6 Progress report may be furnished by the State/UTs to -  Secretary, Ministry of Jal Shakti  Member Secretary, CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains Drains identified. contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure, Gap Analysis, Proposed along No STP proposed. with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure, Gap - Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of RRF at block level. Segregated solid wastes are Processing Facilities dumped in to MCF/ RRF and finally Details of Existing Infrastructure, Gap Analysis, transferring to Clean Kerala Company. Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, Lab analysis report by KSPCB is attached drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste Awareness programs, CCTV installation management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting Implementing in all house-holds as per KPBR rules (xi)Maintaining minimum Environmental flow of river Under MGNREGS all drains and river stretches (xii) Plantation on both sides of the river are cleaning on routine basis.

(xiii)Setting up biodiversity parks on flood plains by Fencing on Ramapuram bridge, Madayi Gp by removing encroachment Irrigation Dept. Desilting and repair of salt water exclusion cross bar at Ramapuram by Irrigation dept. ACTION PLAN FOR RIVER RAMAPURAM, KERALA

Ref para Implementing Agency Time Progress in the Progress % works Details of works no:48 as Activity per NGT month of in the completed remaining order of Completion October 2020 month of 673/2018 Novembe dated:2 Progress in the month 0.0 r 2020 9.2018 of December 2020 completed 100 % nil

A (b) Sanitation Facility Pariyaram GP 03/2020 Ring compost- 550, - - Biodegradable Pariyaram GP 03/2022 pipe compost- 2500, C (ii) waste disposal BAKASHI- 10, bio bin- 92, dung pit- 207, toilet 73, soak pit- 196, bio- gas plant- 3, portable bio-gas- 33, total = 3665 Non bio Ongoing Ongoing, a - 4 ton to C (ii) degradable Pariyaram GP project ton handed be hand Waste Disposal over to Clean over Kerala Company. Youth, Asha workers Whenever On going - - E Awareness and other stake necessary holders Completed 100 % NIL A (b) Identification of Pariyaram gp illegal outlets in to 09/2019 drains and

stoppage of the same

Madayi GP 13 no of soak 100 % nil A (b) Sanitation Facility 2020 pit work completed. 7 no of - 70 no of Ward Sanitation compost pit ring Committee of Local C (ii) Biodegradable 2022 work compost Body waste disposal completed. to Order placed distribute. for 100 no of ring compost, 30 no of ring compost supplied. Non bio degradable On-going project Collecting non - Received Madayi GP C (ii) Waste Disposal bio sanction degradable for 10 no waste via of mini Haritha Karma MCF Sena and is transferring to RRF Awareness Youth, Asha workers On going - - E and other stake holders On going completed 100 % nil A (b) Identification of Madayi GP illegal outlets in to 09/2019 drains and stoppage of the same

Sanitation Facility gp 03/2020 A (b)

Biodegradable Cheruthazham gp 03/2022 C (ii) waste disposal Non bio degradable Cheruthazham gp On going project C (ii) Waste Disposal Youth, Asha workers Whenever E Awareness and other stake necessary holders

A (b) Identification of Cheruthazham gp illegal outlets in to 09/2019 drains and stoppage of the same

Action plan of Local body

1. Public Toilet: Construct public toilets using available funds on the bank of river near Tourist places, Fishing spots etc.

2. Mini MCF: Construct material collection facility in miniature form at suitable intervals on the bank of the river in order to prevent dumping of wastes in to water.

3. Toilet at houses: Construct toilets with scientific septic tank and Soak pit

4. Retro Fitting: Maintenance work of existing toilets of residences near the bank of river using performance incentive grant.

5. Bio degradable waste Disposal: Distribution of Bio gas Plant, Composting facility to residences near river for bio degradable waste disposal.

6. Common Waste disposal facility: For the disposal of bio degradable waste disposal at market places, provide community level bio gas plants, Thumboormozhi etc. Using suitable funds

7. Common Sewage treatment facility:Provide common sewage treatment facility for waste water generating from market places and disposing in to public drains.

8. Septage treatment facility :Construct septage treatment facility

In addition to above, CCTV can be installed at suitable points in order to identify the persons/ establishments dumping waste in to river. All the local bodies must establish slaughter houses with modern facilities and unauthorized slaughter houses shall be strictly enforced. Strict action shall be taken against non-violating person/ agency by the authorities when noticed. Plantation of trees and plants on the bank will be highly effective in controlling the waste disposal. Action Plan by Irrigation Department

Ref para Activity Implementing Time for Progress in the Progress % works Details of no:48 Agency completion month of October in the complete works as per 2020 month of d remaining NGT Novembe order Progress in the 673/18 r 2020 dated: month of 20. 9.18 December 2020 Providing fencing on Irrigation 2021 DPR Ramapurambr idge department Submitte across Ramapuramri ver d for FS at Madayi GP C (ii) 12 Lakhs Desilting and repair of Irrigation 2020 Work salt water exclusion cross Department tendered, bar at Ramapuram in agreement cheruthazham GP executed. E E Regualting activites in Irrigation -3 years - LSGD - flood plain zone, Department Constructed protection and bund road. management of flood Hence plain zone proposal by Irrigation dept may be stopped. E Greenery development- Irrigation 2 years Land Plantation plan. Department demarcation Plantation on both sides to be done. of the river, setting up biodiversity parks on flood plains by removing encroachment E Issues relating to E-flow, Irrigation 2 years DPR maintaining minimum Department submitted for environmental flow of 65.60 Lakhs river(by having watershed management provisions) Combined Action Plan

Agency Timeline Progress in Progress in Progress in % works Details of Proposed action the month the month the month completed works of October of of remainin 2020 November December g 2020 2020

Providetoilets to residences Local Body As there are residences A (b) with treatment and disposal with single pit toilet system for sewage and sullage

All local bodies Proposed Construction A (b) Construction of new SuchitwaMission, Of new community community toilets with Revenue Toilet at satellite points treatment system department on the bank of river

B (ii) All local Drains are inspected Entry of rain water and rain water recharging to all channels bodies , Kerala before rain and all and drain Water channels and stream Authority, are cleaned once in a year

Sanitary waste in hostels, establishments should be C (ii) segregated, treated and disposed Pollution Control Check they have board as per Solid Wastes Management Board consent and sanitation Rules,2016 intheir respective ,Health facility is provided wards.Aerocompostimg and departmen t Material Collection Facility should be given in all wards near the river bank.

C (ii) Adequate number of kitchen Municipalities Six months bins shall beprovided and local bodies

C (ii) Providing proper waste handling Six months facility. For wastewater and solid wastes

C (ii) Rendering plant for poultry wastes Local body Six months

C (ii) Slaughter house waste disposal Local body facility Strict monitoring of disposal of Pollution Six months A (iv) waste(sewage, sullage, Control Board degradable waste, non- biodegradable waste) surveyed area and also in the catchment of theriver i)Verify Whether consent to operate of the Board exists Pollution Six months A (b) Sanitation survey is to be conducted Control Board for 100m on either sides of the other parts of polluted stretch if any located nearby Awareness for Suchitwamission/L Once in a month E residence association: SGD/Corporation

Action Plan by Ground Water Department

Sl.No Ref para Activity Progress in the Progress in the % works Details of works no:48 as per NGT month of month of completed remaining order October 2020 November 2020 Progress in the 673/2018 month of dated:20. 09.2018 December 2020 1 B(i) Ground Water resources and regulation of ground water extraction by industries particularly in over expolited as critical zones/blocks 2 B(ii) Ground water recharging / rain water harvesting 3 B(iii) Periodic ground waste quality assessment and remedial actions in case of con taminated ground water tube wells/bore wells or hand pumps 4 B(iv) For regulating use of ground water for irrigation purpose, adopting good irrigation practices

' n\ ./'/ , l\'rl\y 1. Kawayi River

l';:*{c L e*neentrations of water qn*m&}t d*rffi #tffir$ iY}easured for Decernber 202$ Kuttyol palam SI Parameters Kankol Karikuzhithodu Thattarakadavu no Bridge

Date of collection Ll0ll202l y0ll202r lt0ll202l 211212020 7.0r I pH 7.t9 6.73 6.87 33400 64.2 2 Electrical ConductivitY, Prsicm 188.9 ttl.2

0.79 J BOD, mg/L 0.6r 0.47 t.07 6.27 4 Dissolved Oxygen, mglL 7.1 7.2 6.26

280 220 5 Total coliform, cfir/l 00ml 100 120

80 6 Faecal coliform, cfu/l 00ml 80 40 80

Turbidity 0.9 1.1 1"7 1.5 t4 8 Total Hardness, mg/L 16 6 4900

8 10 Calcium Hardness, mglL t2 4 1700 6 9 Magnesium Hardness, mgL 4 2 3200 0,0546 1l Ammonia-NOr ,mg/L BDL BDL 0.0650 4.0299 T2 Sulphate, mglL 3.09 BDL 359.92 BDL 13 Phosphate, mglL 0.0341 0.1586 0.0897

t4 Fluoride, mg/I' BDL BDL BDL BDL 8 15 Total Alkalinity, mg/L 12 10 56

9, 15 16 Chloride, mglL 20 15 12000

$;.+

1" Kandakali Mathamangalam ChandaPura Parameters Kacherikadavu p 0u0rl202l 2llzl'zuzv 0ll0tl202l Date of collection 0ll0ll202r

7.76 7.05 6.77 6.63 1 pH 59.7 42000 47.4 86.5 2 Electrical Conductivity, FS/cm 0.2 1.54 0.6 0.86 J BOD, mg/L 7.47 4.5 7.8 7.6 4 360 320 -Disrol'tredoxygen,mglL 100 100 5 lotal coliform, cfi'r/l 00ml 100 100 80 40 6 Fecal coliform, cftt/l UUmt 1.4 0.9 2.r = TurbiditY 0.3 16 4600 10 5 8 fotat Hardness, mglL a 9 3200 6 J 9 CalciumHardness, mglL 1400 4 2 10 Magnesium Hardness, mgl L 0.053 0.0439 I BDL 11 mdl BDL -Ammonia-NOr, BDL 3.772 372.86 t2 t4.12 BDL 0.083 0.0795 0.0348 13 BDL 0.11 BDL l4 BDL l4 62 1l T4 l5 Total AlkalinitY, mg/L 24000 12 l4 t6 Chloride, mglL 9 3. RAMAPURAM

Parameters Kappugal Athiyadam Ramapuram Vayalapra /o

Date of collection 3011212020 30n2t2020 2n2t2020 U1t202l

I pH 6.79 6.88 7.t5 6.81

2 Electrical Conductivity, s2.6 106.4 23t0 45700 ps/cm a J BOD, mg/L 0.13 0.39 I.r7 1.29

4 Dissolved Oxygen, mglL 7.2 6.8 5.27 5

5 Total coliform. cfi.r/1 00ml 120 120 240 280

6 Fecal coliform, cfu/1 00ml 40 40 60 80

7 Turbidity 0.3 0.4 r.4 1.8

9 Total Hardness, mg/L t2 9 400 3300

8 Calcium Hardness, mglL 9 4 300 2000

10 Magnesium Hardness, mglL J 5 100 l 300

11 Ammonia-NOlmglL BDL BDL 0.r751 0.0105

I2 Sulphate, mglL 3.532 4.892 62.r2s 412.9

13 Phosphate, mglL 0.0187 BDL BDL 0.0025 t4 Fluoride, mglL BDL BDL 0.72 BDL

15 Total Alkalinity, mglL 12 t0 96 83

I6 Chloride, mg/L 7 l0 730 22504 Kuttyerikkadavu Kuppam Variankottam Parameters Velichankeel Mangalasserry bridge 0 30ll'zlzuLU 111212020 3011212020 301t212020 Date of 3011212020 301L212020 collection 6.49 7.08 6.79 6.88 I pH 6.69 6.87 16600 ZOUU ZU6UU 5720 t7990 2 Electrical 23400 ConductivitY, ps/cm 1.1 1 u.v6 1.58 t.73 t.42 J BOD, mg/L r.l9 6.6 6 6.2 4 Dissolved 6 6.6 Oxygen, mg/L 180 t4u 180 150 180 5 Total coliform, 320 cfir/100m1 80 4U 80 50 80 6 Faecal t20 coliform, cfrr/100m1 t.4 t.2 1.1 u.9 t.9 7 Turbidity t.7 6IU 800 s00 600 8 Total Hardness, 3200 9s0 mglL UU 500 260 320 t0 Calcium 1400 540 Hardness, mgll 280 z5u 410 300 240 9 Magnesium I 800 Hardness, mglL 0.0064 LI.UUOY 0.034 0.2e76 o orot 11 Ammonia-NOr, 0.0439 I rnglL J4. t9 t74.71 52.42 23.40 t2 Sulphate, mglL 168.7 t20.16 BDL . BDL 0.0578 0.0025 l3 Phosphate, 0.0119 O.UIJU mglL ,BDL bljL t.02 BDL l4 Fluoride, mglL BDL BDL 43 +5 47 42 54 15 Total 84 AlkalinitY, mglL 8200 I+UU 12000 1 800 1 1900 16 Chloride, mglL 1s000 i a -+t:!- I

l.Kawavi

KalikadaPuram thodu

2.Peruvamba

load Sl.no Drain Pollution BOD December

I Naranga thodu 3.14

2 Perumba thodu 8.6

a J Valliohmthodu 5.5

4 thodu t.2 " 5 Poomkottu Chal 1.1 fetch 6 Manjangottu Thode Could not water as there was only less amount of water

7 Kannelamthodu 0.82

8 Appithodu 2.2

9 Mavullapoyil thodu 0.86 fetch 10 Kollali thodu Could not water as there was only less amount of water

u Kannada thodu t.2 l2 ri.oyakkotu thodu Could not fetch Thokadu water as there was only less amount of water 13 Cherottuvayut ttroar., l.l t4 Kayyil arakulam thodu Could not fetch water Kunjimagalam puzha as there was only less amount of water l5 rattanvayal thodu Could not fetch- water as there was only less amount of water

3.Ramapuram thodu

Pollution load BOD

Kulapram kundan ttroOu

Kavilavalapu thodu

Aduthila thodu Could not fetch wate. as there was only less amount of water P-ollution load BOD

N*t UdaYagiri Bridge

Moonamkunnu Thodu

KuttaParamba- Neduvodu Thodu

PIS otelakode Hospital

Near the houses on bank of main River (@PatiYaram GP)

N-ear House Boat @ Pariyaram GP

Cheru thodu National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER , KASARGOD S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii)Setting up biodiversity parks on flood plains by removing encroachment ACTION PLAN FOR RIVER UPPALA, DISTRICT, KERALA MONTHLY PROGRESS REPORT FOR THE MONTH OF DECEMBER 2020

No. Activity Implementing Time Progress in the Progress in the Progress in Progress in the Progress in Progress in % works Details of (as per agency line month of July month of the month of month of the month the month completed works Action August September October 2020 of of remaining Plan) 2020 November December 2020 2020 C(ii) Material 2019 Work completed Activity Activity Activity Report not Activity 100 Completed Grama Panchayath collection and operation continuing. continuing. continuing submitted continuing % facility. started. MCF is Operation located at Kubanur. Activity continuing. C Waste Mangalpady Grama 2019- Waste being Work being Work being Work being Report not Work being . Approval managemen Panchayath/ Green 2020 collected by a carried out carried out carried out submitted carried out for t including Space Private panchayath vehicle regularly regularly regularly regularly purchase of purchase of company from nearby vehicle not vehicle to collect apartments and sanctioned waste. shops. from Solid waste is also Governme being collected nt. daily by a private company named as Green Space.

E Installation of Mangalpady Grama March Project dropped camera Panchayath 2020

C Electrification Manjeshwaram 2019- Completed Completed Completed Completed, Completed IN Completed 100% Completed Grama Panchayat of material 2020 MCF November in November collection inaugurated 2019 and 2019 And facility on 16.09.2020 MCF MCF inaugurated Inagurated in on 16.09.2020 16.09.2020 C Transportation Manjeshwaram March 995m3 Waste Due to spread of Due to spread Collected 995m3 Waste 995m3 - Work yet to of collected Grama Panchayat 2020 collected from Covid, work of Covid, work 3320kg of non collected from Waste be waste various public interrupted. interrupted. biodegradable various public collected completed. from places and River waste through places and Various sides and clean Kerala River sides and public transported to company on transported to places and Disposal center in 27/06/2020, Disposal center River sides March and 338m3 28/06/2020, in March and and Waste collected in 29/06/2020 338m3 Waste transported June 2020. collected in to MCF in March and June 2020. Due to spread of 338m3 Covid, work Waste is being Waste collected in interrupted in July collected from June 2020. 2020. Manjeshwaram near Railway Waste is being Station, collected from Manjeshwaram Manjeshwara Town near m Near Surumathodu, Railway Hosangadi station,Manjes town, NH 66 hwaram Town near checkpost, near Mada, Karoda, Surumathodu, Kunjathur, Hosangadi Thumminadu, Town,N H 10th mile. 66,Near CheckPost, Mada, Karoda, Kunjathur, Thumminadu, 10 th mile

E Installation Manjeshwaram March - - - Project CC Camera 1. CC Camera Tendered of camera Grama Panchayat 2020 prepared for installed at Installed At installing Solar Karoda, Karoda, CC camera National Surumathodu near Uppala Highway, near Bridge has Suramathodu, Manjeshwara m. been Near 2. 2020-21 sanctioned by Manjeshwaram Project DPC on . 2020-21 58/2020-21 C 20.10.2020. Project C Camera Tender has 58/2020-21 CC installation at been invited. camera Uppala river installation at side- Uppala Tendered riverside. C Tying of net Irrigation 2019- Estimate for fencing Work still under Work still under Estimate for Estimate for DPR submitted Work still on both Department 2020 work on both sides process. process. fencing work on fencing work to Chief under sides of the of Uppala NH both sides of on both sides of Engineer,I&A process. bridge Bridge submitted to Uppala NH Uppala NH (PRICE ID Chief Engineer Bridge proposed Bridge 2019/10825/I through for Rs.47.00 proposed for A) for approval PRICE ID: lakhs. Estimate Rs.47.00 lakhs. 2019/10825/IA submitted to Estimate dated 15.11.2019 Chief Engineer submitted to for approval. through PRICE Chief Engineer 2019/10825/IA through PRICE dated 2019/10825/IA 15.11.2019 for dated approval 15.11.2019 for approval

E Continuous Police Department Completed Completed Completed Completed Completed Completed 100% Completed vigil on waste dumping on roads A(a) Water quality KSPCB Being Water quality is being monitored by KSPCB, Kasaragod regularly. monitoring done regularly

Sd/-

Environmental Engineer UPPALA RIVER - UPPALA RIVER NEAR BHAGAVATHI TEMPLE (Bhagavathi Gate) - UPPALA RIVER - UPPALA BRIDGE (Existing NWMP Station) (Proposed NWMP Station)

Uppala River Near Bhagavathi Sampling Point Uppala Bridge Sampling Point Temple (Bhagavathi Gate) NWMP Station Code 2306 Distance from existing NWMP Station 878.66 m

Latitude 12 ˚41’41.7”N Latitude 12 ˚41’20.1”N

Longitude 74 ˚54’16.9”E Longitude 74 ˚54’34.0”E

Date of Sampling 21.12.2020 Date of Sampling 21.12.2020

Moderate flow, water level Water level decreased, Nature and flow of the river Nature and flow of the river decreased moderate flow Uppala River Near Sl.No Parameters Unit Uppala Bridge Sl.No Parameters Unit Bhagavathi Temple (Bhagavathi Gate) 1 Temperature ˚ C 28 1 Temperature ˚ C 28 2 pH - 7.1 2 pH - 7.4 3 Conductivity µmhos/cm 22600 3 Conductivity µmhos/cm 143 4 Turbidity NTU 0.4 4 Turbidity NTU 0.3 5 BOD mg/l 1.7 5 BOD mg/l 1.3 6 Dissolved Oxygen mg/l 7.26 6 Dissolved Oxygen mg/l 7.86 7 Total Coliforms cfu/100ml 320 7 Total Coliforms cfu/100ml 300 8 Feacal Coliforms cfu/100ml 88 8 Feacal Coliforms cfu/100ml 84 9 Feacal Streptococcus cfu/100ml 20 9 Feacal Streptococcus cfu/100ml 10 10 Chlorides mg/l 7500 10 Chlorides mg/l 28 11 Total Alkalinity mg/l 74 11 Total Alkalinity mg/l 27 12 Total Hardness mg/l 4800 12 Total Hardness mg/l 35 13 Calcium Hardness mg/l 4000 13 Calcium Hardness mg/l 21 14 Magnesium Hardness mg/l 800 14 Magnesium Hardness mg/l 14 15 Calcium mg/l 1600 15 Calcium mg/l 8.4 16 Magnesium mg/l 194.4 16 Magnesium mg/l 3.4 17 Total Dissolved Solids mg/l 13520 17 Total Dissolved Solids mg/l 85 18 Sodium mg/l 3950 18 Sodium mg/l 15.1 19 Potassium mg/l 210 19 Potassium mg/l 2.1

Sd/- Assistant Scientist National Mission for Clean Ganga

Format for Submission of Monthly Progress Report by States/UTs (Hon’ble NGT in the matter of OA No.673/2018 dated 06.12.2019) RIVER , KASARGOD S. Activity to be monitored Timeline Submission of progress by State/UT- No. Compliance status 1 Ensure 100% treatment of sewage at least in-situ remediation Commencement of setting up of STPs and connecting all the drains and other sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of action plans including completion of setting up STPs and their Commissioning 5 Chief Secretaries may set up appropriate monitoring mechanism at state level  Specifying accountability of nodal authorities not below the Secretary level  Chief Secretaries may have an accountable person attached in their office for this purpose  Monitoring at State level must take place 6 Progress report may be furnished by the State/UTs to  Secretary,Ministry of Jal Shakti  Member Secretary,CPCB 6.1 Progress Report may be comprised of details along with completion timelines on: (I) Identification of polluting sources including drains contributing to river pollution and action as per NGT order on in-situ treatment.

(II) Status of STPs, I&D and sewerage networks Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(III) Status of CETPs Details of Existing CETP and ETP Infrastructure,Gap Analysis, Proposed along with completion timeline, No. of industries and complying status

(iv)Status of Solid Waste Management & Details of Processing Facilities Details of Existing Infrastructure,Gap Analysis, Proposed along with completion timeline

(v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river;

(vi)Preventing dumping of waste and scientific waste management including bio-medical waste, plastic waste and decentralizing waste processing, including waste generated from hotels, Ashrams, etc.

(vii)Ground water regulation

(viii) Adopting good irrigation practices

(ix) Protection and management of food plain Zones (FPZ)

(x) Rain water harvesting

(xi)Maintaining minimum Environmental flow of river

(xii) Plantation on both sides of the river

(xiii)Setting up biodiversity parks on flood plains by removing encroachment ACTION PLAN FOR RIVER MOGRAL, , KERALA

MONTHLY PROGRESS REPORT FOR THE MONTH OF DECEMBER 2020

No. Activity Implementing Time line Progress Progress in Progress in Progress in Progress in the Progress in % Details of (as agency in the the month of the month the month of month of the month of works works per month of August 2020 of October 2020 November 2020 December comple remainin Actio July 2020 September 2020 ted g n Plan) 2020 C Material collection March 2020 Complete Completed Completed Completed Completed. Completed. 100 % NA facility Grama Panchayath d Not started

C Waste collection Mogral Puthur March 2020 Not started Not started Not started Not started Not started Not started 0 % including vehicle Grama Panchayath hire charge to collect waste. E Installation of Mogral Puthur June 2020 Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing 0% camera Grama Panchayath

A Drainage Mogral Puthur 2019 Complete Completed Completed Completed Completed Completed 100 % NA Cleaning at Grama Panchayath d (b) Ballor, Kottakkunnu, Majal, Neerchal, Blarkode, Goovathadka, Pernadka, Shankra, Eriyal,KK Puram Arjal Vishnu Temple

C(ii) Haritha Mogral Puthur On-going Currently Conducted NIL Karmasena Grama Panchayath inactive training and Activity/ started Collecting Non collection of Bio degradable plastics from materials households and including temporarily Plastics from stored in a shed. households C(iii) Bamboo Capital Mogral Puthur On-going Complete Completed Completed Completed Completed Completed 100 % N Bamboo Grama Panchayath d A Planting - aiming water conservation and raising water levels thus preventing solid erosion, waste dumping in publicplaces E River cleaning Mogral Puthur 2019 Complete Completed Completed Completed Completed Completed 100 % N Grama Panchayath d A

C(iii) Bamboo Plantation Madhur grama 2019 18500 18500 being 18500 being 18500 being Report not Report not 100 % Complete of Madhur Panchayath being maintained by maintained maintained by provided provided d maintained by NREGA NREGA by NREGA NREGA

C(ii) Viability Gap Madhur grama 2019 Partially Partially utilised Partially Total amount Report not Report not 25% NIL Funding for Haritha Panchayath utilised utilised Rs.1,00,000/- provided provided Karmasena expenditure Rs.25300/-

C(ii) Material recovery Madhur grama 2019 Completed Completed Completed Completed Report not Report not 100% Complete facility centre Panchayath provided provided d

C(ii) Construction of Madhur grama 2019 Completed Completed Completed Completed Report not Report not 100 % Complete Plastic Shredding Panchayath provided provided d Machine building C(ii) Purchase of Madhur grama 2019 Yet to Yet to float Yet to float Project no Report not Report not - Yet to Plastic shredding Panchayath float tender tender 234. Amount provided provided float machine tender Rs. 6,00,000/- tender Yet to float tender

C Tying of net on Irrigation 2019-2020 Estimate Work still Work still Estimate for Estimate for DPR - Work still both sides of the Department for fencing under process. under fencing work fencing work onsubmitted to under bridge work on process. on both sides both sides of Chief process. both sides of Mogral NH Mogral NH Engineer, I & of Mogral Bridge at Bridge at A (PRICE ID: NH Bridge Kadavath Kadavath 2019/10715/ submitted proposed for proposed for IA ) for to Chief Rs.32.00 Rs.32.00 lakhs. approval Engineer lakhs. Estimate through Estimate submitted to PRICE ID: submitted to Chief Engineer 2019/1071 Chief Engineer through PRICE 5/IA through PRICE ID: dated ID: 2019/10715/IA 15.11.201 2019/10715/I dated 9 for A dated 15.11.2019 for approval. 15.11.2019 approval for approval A(a) Water quality KSPCB Being done Water quality is being monitored by KSPCB, Kasaragod regularly. monitoring regularly

Sd/-

Environmental Engineer MOGRAL RIVER - MOGRAL BRIDGE (Existing NWMP Station) MOGRAL RIVER - PUZHAKKARA (Proposed NWMP Station)

Sampling Point Mogral Bridge Sampling Point Puzhakkara NWMP Station Code 2304 Distance from existing NWMP Station 3.25 km Latitude 12 ˚33’36.5”N Latitude 12 ˚33’58.1”N Longitude 74 ˚57’21.0”E Longitude 74 ˚58’43.7”E

Date of Sampling 21.12.2020 Date of Sampling 21.12.2020 Medium flow, water level Water level decreased, medium Nature and flow of the river Nature and flow of the river decreased flow Sl.No Parameters Unit Mogral Bridge Sl.No Parameters Unit Puzhakkara 1 Temperature ˚C 28 1 Temperature ˚C 28 2 pH - 7.08 2 pH - 7.5 3 Conductivity µmhos/cm 36700 3 Conductivity µmhos/cm 210 4 Turbidity NTU 0.2 4 Turbidity NTU 0.5 5 BOD mg/l 2.1 5 BOD mg/l 2.0 6 Dissolved Oxygen mg/l 6.46 6 Dissolved Oxygen mg/l 6.3 7 Total Coliforms cfu/100ml 360 7 Total Coliforms cfu/100ml 320 8 Feacal Coliforms cfu/100ml 84 8 Feacal Coliforms cfu/100ml 76 9 Feacal Streptococcus cfu/100ml 20 9 Feacal Streptococcus cfu/100ml 20 10 Chlorides mg/l 12500 10 Chlorides mg/l 48 11 Total Alkalinity mg/l 108 11 Total Alkalinity mg/l 26 12 Total Hardness mg/l 6500 12 Total Hardness mg/l 55 13 Calcium Hardness mg/l 5800 13 Calcium Hardness mg/l 35 14 Magnesium Hardness mg/l 700 14 Magnesium Hardness mg/l 20 15 Calcium mg/l 2320 15 Calcium mg/l 14 16 Magnesium mg/l 170.1 16 Magnesium mg/l 4.9 17 Total Dissolved Solids mg/l 21835 17 Total Dissolved Solids mg/l 120 18 Sodium mg/l 6450 18 Sodium mg/l 25 19 Potassium mg/l 310 19 Potassium mg/l 4.0 Kerala State Pollution Control Board, DO Kasaragod ANALYSIS REPORT - DECEMBER 2020 Drain joining Mogral Upstream of the same Source of Sample river at Kadavath drain near Kottakkunnu Date of Sampling 21.12.2020 21.12.2020 Latitude 12°33'36.5"N 12 ˚33'31.7" N Longitude 74°57'29.6"E 74 ˚57'47.7" E Distance from the river 114.07m 582.34m Sl No. Parameters Sample 1 Sample 2 1 Temperaure , ͦC 28 28 2 pH 6.9 7.4 3 Conductivity, µmhos/cm 29500 2900 4 Turbidity,NTU 1.8 0.4 5 BOD ,mg/L 2.3 2.5 6 Dissolved Oxygen ,mg/L 6.66 4.66 7 Chloride ,mg/L 9700 70 8 Total Alkalinity ,mg/L 90 39 9 Total Hardness ,mg/L 4600 52 10 Calcium Hardness ,mg/L 4100 31 11 Magnesium Hardness ,mg/L 500 21 12 Calcium ,mg/L 1640 12.4 13 Magnesium ,mg/L 121.5 5.1 14 Total Dissolved Solids ,mg/L 16850 175 15 Total Coliforms , cfu/100ml 320 160 16 Feacal Coliforms, cfu/100ml 72 56 17 Feacal Streptococcus, , cfu/100ml 20 10 18 Sodium ,mg/L 5100 38 19 Pottasium ,mg/L 215 7

Sd/- Assistant Scientist

Status of water quality of the polluted river stretches in Kerala as on December 2020:

Polluted River Priority Quality of water as per Present Status as SL. District River stretches latest report per bathing No. standards

POYYA BOD <3 Quality maintained 1. Kasargod 1) Uppala V FC<500 TO MULINJA

2) Mogral ALONG MOGRAL V Quality maintained BOD <3 FC<500

2 Kannur 3) Kavvai ALONG KAVVAI V Quality maintained BOD <3 FC<500

THALIPARAMBA Quality maintained 4) Kuppam TO V BOD <3 VELICHANGOOL FC<500

ALONG V BOD <3 Quality maintained 5) Peruvamba PERUVAMBA FC<500

ALONG V BOD <3 6) Ramapuram RAMAPURAM FC<500 Quality maintained NADUVILANGADI TO Quality maintained 3 Malappuram 7) Thirur THALAKKADATHUR V BOD <3, . FC<500 ALONG BOD <3 Quality maintained 8) Kadalundi HAJIRAPPALLY/ V FC<500 HAJIYARPALLI IV BOD <3 Quality maintained 4 Palakkad 9) Bharathapuzha ALONG PATAMBI . FC<500 ALONG V BOD <3 Quality maintained 10) Bhavani ELACHIVAZHY FC<500 PULIYANNOR Quality maintained 5. Thrissur 11) Kecheri TO KECHERY IV BOD <3 FC<500 ALONG BOD <3 Quality maintained 12) Karuvannur KARUVANNUR V FC<500 OLARIKKARA TO V BOD <3 Quality maintained 13) Puzhakkal PUZHACKAL FC<500 IRUMPANAM TO It is expected KARINGACHIRA V BOD<3 that by 6. Ernakulam 14) Chithrapuzha FC>500 31.03.2021 the bathing quality may be achieved MANCKAKADAVU TO BOD<3 15) Kadambrayar BRAHMAPURAM IV FC>500 It is expected that by 31.03.2021 the bathing quality may be achieved 16) Periyar ALWAYE- ELOOR V BOD<3 It is expected TO KALAMASSERY FC>500 that by 31.03.2021 the bathing quality may be achieved THEKEPURAM TO ARAKKINAR V It is expected BOD <3 that by 7. Kozhikode 17) Kallayi FC>500 31.03.2021 the bathing quality may be achieved

ALONG V BOD <3 18) Kuttiyadi It is expected KUTTIYADY FC>500 that by 31.03.2021 the bathing quality may be achieved MANNAR TO Quality IV BOD <3 maintained 8. Pathanamthtitta THAKAZHY 19) Pamba FC<500 KALLOOPARA TO BOD <3 Quality 9. Alappuzha 20) Manimala IV maintained THONDRA FC<500 MALEKKDU TO It is expected THIRUVALLAM I BOD >3 that by 10. Trivandrum 21) Karamana FC>500 31.03.2021 the bathing quality may be achieved

• Bathing quality is achieved/ maintained in 14 stretches. • It is expected that by 31.03.2021 the bathing quality may be achieved in the rest of the 7 stretches also. • Measures are in progress to implement the action plans.