RAIL LINK – LOCAL GOVERNMENTS ROLE IN STATE LED INFRASTRUCTURE PROJECTS.

Lindsay McLeod; [email protected] Manager Major Projects (Moreton Bay Rail Link), Moreton Bay Regional Council, , Australia

Abstract

With a history that can be traced back more than a century, and with detailed corridor and infrastructure planning spanning decades, the Moreton Bay Rail Link is finally well and truly underway.

For Moreton Bay Regional Council, the outcomes achieved to date with the Moreton Bay Rail Link have re-affirmed the importance of a pro-active, strategic and energetic approach to State and Federal Government engagement, securing funding, planning and management of delivery of major, regionally significant infrastructure projects.

The involvement in the Moreton Bay Rail Link project has provided the opportunity for Council to capitalize on its investment, coordinate the infrastructure delivery with land use planning, ensure transport integration outcomes, promote effective environmental management and mobilize the necessary social and economic growth activities necessary for sustainable regional development.

The presentation will outline the Moreton Bay Regional Council’s purpose, role and partnership with the State Government in the establishment and delivery of the Moreton Bay Rail Link project and outline the benefits of “front loading” the project planning process to ensure multiple outcomes.

Take home message:

Local government involvement in State infrastructure projects can and will ensure enhanced infrastructure delivery, improved coordination with land use planning, better transport integration outcomes and effective environmental management.

Political support is essential not only to secure project funding but also facilitate community engagement and mobilize the necessary social and economic growth activities necessary for sustainable regional development.

Introduction Rothwell and Kippa Ring on the has, over history had a number of Many sections of the community may names and forms. question the purpose and necessity of a local government involvement with the delivery of The first known reference to a rail link to State infrastructure projects such as the Redcliffe dates back to the late 1800s when Moreton Bay Rail Link. a local alderman proposed that a new line be built to the peninsula at an estimated cost of This long awaited spur line leading off from 200,000 pounds. the main North Coast Rail Line at Petrie and heading east through the suburbs of The first significant planning study to Kallangur, Murrumba Downs, Mango Hill, investigate the Moreton Bay Rail Link occurred in 1978-79 when the Metropolitan • there was potential for 6 railway stations. Transit Authority conducted a series of planning studies into a public transport corridor between Petrie and Kippa-Ring. The ’s 2003 study These investigations led to the identification provided the foundation for the current of the preferred alignment for the project and project design. (Queensland Department of the land was then acquired. Transport and Main Roads (DTMR) 2014)

Over the last 30 years the project has been In July 2010 an Intergovernmental the subject of a number of further studies. Agreement was signed between the Australian Government, Queensland From 1999 to 2003 the Queensland Government and the Moreton Bay Regional Government undertook the Petrie to Kippa- Council to build the project, with all 3 levels of Ring Public Transport Corridor Study. government committing funds to the $1.147B project. This study assessed the feasibility and impact of the corridor to support the visions and objectives set out in the Queensland Project Facts & Figures Government’s Regional Framework for Growth Management. Original planning for facilitation of the construction of the Petrie to Kippa Ring spur The study recommended a preferred Line (Moreton Ray Rail Link) included as a alignment for the corridor, with the preferred separate project the State funded Lawnton to transport mode being heavy rail. Heavy rail Petrie 3 rd track upgrade project. was found to be the most effective option for the following reasons: During the tendering process, the two previous projects were combined with the • A single journey – extending the existing now combined Moreton Bay Rail Project heavy rail network allows passengers to spanning some 13.6km with a combined total board at a station on the Moreton Bay Rail funding of over $1.3B. This combined project Link and continue on the same service all includes: the way to . • Carrying capacity – heavy rail will better • 13.6 km of double track rail from Lawnton cope with increasing number of to Kippa Ring; passengers in future than either light rail • Grade separated rail connection to the or a busway. North Coast (Caboolture) Line just north of • Cost – heavy rail is similar in cost to light the Petrie Station; rail or busway, but with higher carrying • 22 bridge structures to provide river and capacity and faster journey times. waterway crossings, grade separation of shared path, road and rail including rail over the ; Based on this study, the Department of • Six new rail stations incl. bus interchanges Transport and Main Roads (formerly and bike storage; Queensland Transport) commissioned the • 2850 off-street carparks with associated development of a Final Impact Assessment bus and cycle facilities at stations; Study for the corridor. It concluded that the • 800,000m3 excavation; and preferred corridor between Petrie and Kippa- • 1,100,000m3 fill Ring area was the original preserved corridor because: Associated works will involve: • • Stabling for ten (six car) trains near Kippa- the land was already owned by the State Ring station; of Queensland • 3 km of 4 lane road; • the alternative option would fragment • 4.7 km of 2 lane road; existing land uses and habitat • 7 signalized intersections; • environmental impacts could be managed • 12.6km x 3m wide concrete Shared Path Current and planned growth is seeing and 6km connecting path links along significant congestion on major roads length of corridor; becoming a looming problem for the future • Establishment of over 100,000 Koala with congestion on the Bruce Highway, south Habitat trees; and of regularly featuring in • Significant regional ecosystem and marine morning traffic reports. plant offset areas. Significant development areas of North Council’s Role in “Making it Happen” Lakes, Mango Hill, Deception Bay and Redcliffe lie along the Moreton Bay Rail Link Soon after the amalgamation of the previous corridor are planned to accommodate more Redcliffe City Council, Caboolture Shire than 240,000 people and provide over 70,000 Council and Pine Rivers Shire Councils into jobs by 2031. the Moreton Bay Regional Council in 2008, the Mayor elect Alan Sutherland commenced Improved network integration as a result of the process of lobbying the State and Federal the Moreton Bay Rail Link benefits Government for funding of the long awaited communities along the corridor and on the infrastructure project. Redcliffe peninsula. The potential for a proportion of existing bus services within the Critical in securing the necessary corridor to be redistributed to enhance commitment and funding was the existing services and be integrated with the development of the Moreton Bay Rail Link station precincts will provide a superior level Business Case. This $4M business case was of service. The inclusion of an integrated jointly funded (50/50) by the State active transport spine along the corridor also Government and Moreton Bay Regional ensures communities are best serviced by a Council. The planned outcome of the range of transport to options to meet both business case development was submission employment and recreational needs . (MBRL to Infrastructure Australia for funding. Business Case 2011)

Funding for the project was finally confirmed The overall goal for new development areas through the Federal Government Nation along the Moreton Bay Rail corridor is to Building Program with the total joint funding create walkable, transit based communities of $1.147B being provided by: with:

Federal Government $742M • Community infrastructure in convenient and accessible locations adjacent to and Queensland Government $300M + land within mixed use centres; Moreton Bay Regional Council $105M • Regional level facilities in the major centres to reinforce the strengths and character of the urban areas; Strategic Context • Effective and efficient connection of centres to their catchments by public Background transport and active transport links; and • Access to local employment opportunities. Moreton Bay Regional Councils is currently the third largest local government area in Strategic Planning Australia with a population now exceeding

400,000 people and expected to grow to over With over 40% of total regional growth 530,000 by 2031. occurring along the Moreton Bay Rail Link More than half of the people leave the region corridor, there has been a deliberate focus for employment and education daily and 83% on the necessary land use and infrastructure use private vehicles for their journey. (MBRL planning to leverage off the planned rail Business Case 2011) infrastructure. Key strategy elements include:

• Increase connections between key activity • Freshwater Creek South; centres within the region; • Black Duck Creek; • Provide better access to employment • Freshwater Creek North; centres of North Lakes and CBD; • Freshwater Creek; • Reduce traffic congestion; • Saltwater Creek; and • Support sustainable development and • population growth in the region; • Support the continuing development of In addition to the normal hydraulic and water new employment areas. quality considerations, the flood plains are subject to:

Project Impacts Overview • flood releases from the North Pine Dam; • tidal inundation; and Community • storm tide inundation.

A significant length of the project corridor These areas also contain significant areas of threads its way through existing developed remnant vegetation, acid sulphate soils, fish areas with sections through Lawnton, habitat reserves, Marine Park and Ramsar Kallangur, Murrumba Downs, Mango Hill, wetland areas. Rothwell and Kippa Ring being literally on the back fences of properties. Council provided the necessary flood models, developed from the MBRC Regional Flood Transporting large volumes (in excess of 3 Plain Database project. These latest 800,000m of bulk earthworks over local generation TuFlow models have provided the roads and along the corridor has taken a basis of waterway analysis, bridge and significant effort in haulage management and drainage structure selection, rail and community consultation. infrastructure flood immunity assessment.

The project team includes communications Koala Habitat managers from the Department of Transport and Main Roads, Queensland Rail, Moreton Another very significant element of project Bay Regional Council and the Contractor planning was the care and management of (Thiess). the local Koala population during and after construction. Emerging issues of community concern include: Initial estimates provided by koala researchers and local wildlife groups • Noise management; indicated a resident population of Koalas • Dust control; along the corridor at between 60 and 100 • Traffic impacts; individuals. • Parking management around station precincts; and With this in mind, the project team developed • Property access. a comprehensive Koala Action Plan (SMEC 2012) . The specific objectives of the Koala Waterways and Flooding Action Plan for the project area are to:

One of the significant constraints on the • Define the affected koala population and MBRL project design is the corridor location its habitats; which crosses and traverses a number of • Identify threatening processes which regional and environmentally significant already affect the koala population (e.g. waterways including: • vehicle strike, dog attack, habitat loss and fragmentation); • North ; • Identify impacts of the project, and • Yebri Creek; recommend strategies for management; • Define roles, responsibilities and timing for Transport and Main Roads “Brisbane implementation of mitigation measures; Strategic Transport Model Multi-Modal • Establish performance criteria to evaluate (BSTM-MM) version 1.2. management success; • Devise a monitoring program; and The BSTM-MM model is a mature, well- • Identify corrective actions. developed and documented model that has wide acceptance in the planning industry. It is interesting to note that the tagging and (MBRL Business Case 2011) monitoring program has recorded more than 300 Koalas along the corridor to date against PTV Asia-Pacific was commissioned by the original estimates of between 60 and 100 Moreton Bay Regional Council to develop individuals. integrated traffic models for the areas surrounding the proposed stations of the Clearing for the entire corridor has been Moreton Bay Rail Link. (PTV 2012). completed without a single Koala injury. The developed model has enabled Council Mosquito Management and the project team to understand the impact of changes proposed on the An additional issue for consideration in the surrounding road network and plan mitigation project planning and delivery has been the measures. Activities and outcomes from this management of saltmarsh mosquitos. modelling project included:

Moreton Bay Regional Council undertakes • Development of a VISUM traffic one of the largest mosquito management assignment model for the area programs in the state. A significant portion of surrounding the proposed stations of the the program activities are over the areas Moreton Bay Rail Link; surrounding the Hays Inlet conservation park • Conducting traffic surveys and collection and impact on the Moreton Bay Rail Link of latest demographic and land use data; corridor. • Update the model with latest demographic, network and intersection Helicopter applied aerial treatment methods data; have been the traditional cost effective • Development of a microscopic VISSIM program alternative. This approach has model of the identified core areas around triggered the need for significant coordination the stations; between Council’s mosquito control crews • Developing future year models according and the project construction planning and to network changes planned; and management staff. • Providing the necessary inputs for the Moreton Bay Rail Link Integrated Treatment strategies have had to be modified Transport Strategy. to avoid conflict between airborne operations and construction plant and personnel with Procurement increased utilization of ground based treatment programs for areas within the rail Procurement associated with the delivery of corridor or separated from the safe treatment the Moreton Bay Rail Link infrastructure has areas by the rail construction works. included a traditional Department of Transport and Main Roads Road Traffic and Transport Planning Construction Contract (RCC) for the early works package for the Kinsellas Road East In order to assess the impacts of changes to overbridge and approaches and a Modified the local road network and alternative travel Early Contractor Involvement (ECI) tender patterns likely to be a result of the completed and Collaborative Partnership Agreement project Moreton Bay Regional Council (CPA) for the main construction project developed a series of integrated transport contract. models derived from Department of The modified ECI contract has three (3) At the time of writing this paper, early works distinct stages as follows: are nearing completion with almost 800,000m 3 of the planned 1,100,000m 3 bulk • Stage 1A earthworks completed. Ten (10) of the o 4 x Teams competing for shortlisting; twenty-two (22) bridge structures are o Assessment by organisation capacity; underway, three of which are up to o Design concept functionality. construction of the superstructures. • Stage 1B o 2 x Teams competing for contract Cross corridor drainage structures are award; substantially complete with some 25 major o Assessment: culverts installed or under construction. ° 80% Risk Adjusted Tender Price; ° 20% functionality improvements Asset Handover • Stage 2 o Collaborative Partnership Agreement Finalisation and asset handover processes o Modified D & C Contract are underway with one of the first elements being the development of an Asset Handover Council resources and technical experts have Agreement between the State and Council. been involved with all stages of tender assessment, contract award and design The agreement documents the process of reviews. ensuring access for Council staff throughout the construction of infrastructure (primarily What happens next local road upgrades, station accesses and shared path facilities) which is to be returned Design against Council’s financial contribution to the project. With the contract award on 1 August 2013, work to develop the designs commenced with The more substantial elements of the the establishment and co-location of the Handover Agreement include: Client, Designer and Contractor’s project • management teams. Obligations and responsibilities of the parties; To date, a staggering 850 design packages • Access to site; have been produced, reviewed and accepted. • Witness and Hold Points; This accounts for some 8,000 drawings. • Quality Records; • Land tenure arrangements; What has been an unanticipated • As constructed plans; and consequence of Council’s involvement in the • Asset valuation data. project has been the significant resource demand associated with the technical review Conclusion of the designs of relevant infrastructure and monitoring and managing project impacts. To The involvement in the Moreton Bay Rail Link date more than 35 Council staff have been project has provided the opportunity for involved in the contract assessment, design Moreton Bay Regional Council to capitalize review, project coordination, compliance and on its investment, coordinate the environmental management processes. infrastructure delivery with land use planning, ensure transport integration outcomes, Construction promote effective environmental management and mobilize the necessary The integration process has continued into social and economic growth activities the construction phase with co-location of the necessary for sustainable regional Client and Contractor’s construction teams development. established on site. In addition to the significant financial contribution to the project, Council has provided significant technical support and involvement through the process to date. Queensland Department of Transport and Political support for the project has been Main Roads (DTMR) (2014) – Queensland unwavering across all three (3) levels of Department of Transport and Main Roads government. At a local level this continues to Web Site – Moreton Bay Rail Link Project – be essential in managing the community www.tmr.qld.gov.au/moretonbayrail response to project impacts. SMEC (2012) – SMEC Australia Pty Ltd. - Moreton Bay Rail Link Project - Koala Action References Plan Study for the Department of Transport and Main Roads (including Queensland Rail| MBRL Business Case (2011) - Moreton Bay - 16 March, 2012 Rail Link Business Case Report – Australian Government, Queensland Government and Moreton Bay Regional Council – Final Draft 22 September 2011

PTV (2012) – PTV Asia-Pacific Pty. Ltd. - MBRL Station Precinct Traffic Modelling Report - 15 October 2012 Author Biography

Lindsay McLeod is the Manager Major Projects at Moreton Bay Regional Council and has over 40 years of experience leading and working in a local government civil engineering profession performing infrastructure design, planning, strategic and management functions across the spectrum of local government responsibilities.

Lindsay graduated from the then Queensland Institute of Technology with a Certificate in Civil Engineering, he has subsequently completed tertiary studies in Traffic Management and Human Resource Management and holds diplomas in Management and Business.

As the Manager Major Projects, Lindsay’s key role is managing the planning and infrastructure delivery associated with Moreton Bay Regional Council’s $105M investment in the $1.147B Moreton Bay Rail Link Project.