Environmental Monitoring Report

Semestral Report Project Number: 41614-035 July 2014

Period: January – June 2014

IND: Power Sector Enhancement Investment Program – Tranche 3

Prepared by Assam Power Distribution Company Limited (APDCL) for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Environmental Safeguard Monitoring Report

Assam Power Sector Enhancement Investment Program

Reporting Period From January 2014 to June 2014

Loan No. 2800 Tranche III

Prepared by the Assam Power Distribution Company Limited for the Asian Development Bank TABLE OF CONTENTS

S.NO. ITEMS PAGE Abbreviations Executive Summary 1.0 Introduction 4 1.1 Brief Project Description 5 1.2 Project Progress Status and Implementation Schedule 10 A. Progress Status 10 B. Implementation Schedule for Tranche III Sub projects 19 2.0 Compliance to National Regulations 21 3.0 Compliance to Environmental Covenants from the ADB Loan Agreement 22 4.0 Compliance to Safeguards Management Plan 24 5.0 Safeguards Monitoring Results and Unanticipated Impacts 28 A. Environmental Monitoring Schedule: 28 B. Environmental Monitoring Parameters 29 C. Air Quality Parameters 29 D. Water Air Quality Parameters 30 E. Ambient Noise Levels 30 6.0 Implementation of Grievance Redress Mechanism and Complaints 30 Received from Stakeholders 7.0 Conclusion and Recommendations 31 ANNEXURE - 1.1 Summary Ambient Air Quality Results (For distribution lines) 32 ANNEXURE - 1.2 Summary Ambient Air Quality Results (For S/S) 34 ANNEXURE - 2 National Ambient Air Quality Standards, CPCB 2009 35 ANNEXURE - 3.1 Details of Water Quality Locations (for distribution lines) 37 ANNEXURE - 3.2 Summary of Water Quality Results (for distribution lines) 39 ANNEXURE - 3.3 Details of Water Quality Locations (for S/S) 42 ANNEXURE - 3.4 Summary of Water Quality Results (for S/S) 43 ANNEXURE - 4 Water Quality Standards 44 ANNEXURE - 5.1 Summary Noise Level Results (for distribution lines) 46 ANNEXURE - 5.2 Summary Noise Level Results (for S/S) 48 ANNEXURE - 6 National Ambient Noise Standards 49 ANNEXURE - 7 Air, Water & Noise Monitoring Location Maps 50

LIST OF TABLES

TABLE NO. ITEMS PAGE 1.0 Components under Tranche III 5 2.0 Details of Sub-projects under Tranche III for Sub-Station 5 2.1 Details of Sub-projects under Tranche III for 33 kV Transmission Line 7 2.2 Details of Sub-projects under Tranche III for 11 kV Transmission Line 9 3.0 Status of Environment activities in Tranche III Substations 10 3.1 Status of Environment activities in Tranche III Transmission Lines 15 4.0 Implementation Schedule for Tranche III 20 5.0 Applicable Acts and Legislations to the project 21 6.0 Environmental Covenants 22 7.0 Environmental Checklist for Tranche III 25 8.0 Environment Monitoring Schedule for Tranche III 28 9.0 Environmental Monitoring Parameters 29 ABBREVIATIONS ADB Asian Development Bank ADH Assam Department of Health AEGCL Assam Electricity Grid Corporation Ltd. APDCL Assam Power Distribution Corporation Ltd. APCB Assam Pollution Control Board ASEB Assam State Electricity Board ASI Archeological Survey of CPCB Central Pollution Control Board DC District Collector dB Decibels EARF Environmental Assessment and Review Framework EIA Environmental Impact Assessment EMA Environmental Monitoring Agency EMP Environmental Management Plan ESMC Environmental and Social Management Cell ESMU Environmental and Social Management Unit GHG Greenhouse Gas GOA Government Of Assam GOI Government Of India GRC Grievance Redressal Mechanism IA Implementing Agency IEE Initial Environmental Examination IS Indian Standard Ltd. Limited MFF Multi-Tranche Financing Facility NO2 Nitrogen dioxide PAP Project Affected Persons PM10 Particulate Matter (Size less than 10 µm) PM2.5 Particulate Matter (Size less than 2.5 µm) PMU Project Management Unit PPE Personal Protective Equipment ROW Right of Way S/S Sub Station SEIA Summary Environmental Impact Assessment SIEE Summary Initial Environmental Examination SO2 Sulphur dioxide T&D Transmission and Distribution

Electrical Terminology V Volt Unit of Voltage kV Kilovolt 1000 volts W Watt Unit of active power kW Kilowatt 1000 watts MW Megawatt 1000 kW MWh Megawatt hour Unit of energy VA Volt ampere Unit of apparent power MVA Million volt ampere 106 VA Transmission System 400 kV, 220 kV, 132 kV and/or 66 kV lines supplying (incoming & outgoing feeder) grid substations (Substation) with primary voltage of 400 kV, 220 kV, 132 kV, or 66 kV LILO Line – in – Line - Out Executive Summary

1.0 Introduction:

The Government of India (GOI) and Government of Assam (GOA) have requested Asian Development Bank (ADB) to provide $200 million in loan funding via a multi-tranche financing facility (MFF) to support continued investment in the state power sector, specifically for transmission and distribution system expansion and upgrades. GOA and APDCL will be the Executing Agencies for the MFF.

As a part of the reforms program, GoA has unbundled ASEB into three companies: Assam Power Generation Corporation Limited (APGCL), Assam Electricity Grid Corporation Limited (AEGCL) and Assam Power Distribution Company Limited (APDCL). Assam Power Distribution Company Ltd. (APDCL) the successor company of unbundled ASEB is the Implementing Agency (IA) for distribution system of Tranche-III of the MFF

The MFF will partly finance the expansion and augmentation of the transmission and distribution (T&D) networks. The investments are necessary to: (i) facilitate increased power transfers to accommodate increased demand and economic growth; (ii) improve supply-side energy efficiency by system de-bottlenecking and reducing technical losses; (iii) reduce the intensity of greenhouse gas (GHG) and other emissions via improved system efficiency; (iv) support expanded private sector participation in distribution system operations and other energy services; and (v) facilitate poverty reduction via improved electricity services and economic growth.

Tranche III subproject has 29 new substations and 87 distribution lines of which 33kV lines have a length of 620.30 km and 11kV lines have a length of 307 km. The applicable Environmental Acts and Legislation are being complied along with Environmental covenants in ADB loan agreement for the project. In order to have a sustainable development in the project the emphasis on the implementation of EMP has been given top most priority. Environment and Social Cell has been constituted for closely monitoring of implementation of EMP. A grievance redressal committee has also been constituted to address the concerns of the impacted stakeholders. The implementing Agency APDCL giving full attention towards the implementation of EMP.

An environmental assessment and review framework (EARF) was prepared during Tranche I and is applicable for any investment that will be financed through the MFF which includes Tranche III. The EARF provides for the policy requirements, procedures, and institutional arrangements relevant for all the tranches.

The sub project Tranche III is classified as Environment Category B based on their potential environmental impacts as indicated in ADB’s Safeguard Policy Statement 2009 (SPS 2009). Following the SPS 2009 and EARF, IEE is prepared by APDCL as per ADB’s guide lines. The IEE describes the screening of potential environmental impacts due to i) project location and design ii) during construction and operation iii) proposed mitigation measures through implementation of EMP iv) public consultations and information disclosure and v) grievance redress mechanism

M/s SMEC India Pvt Ltd contract No. PMU 02/2009 -10 with APDCL to provide “National Consultant Assignment for Individual National Expert for Implementation Support for Social &

4

Environmental Activities” has been extended and contract agreement was signed on 4th of November 2011 between Project Management Unit (PMU), Assam State Electricity Board and SMEC. Hence, the revised consultancy service will end on June 30, 2014. The scope of work defined in earlier contract remains same.

1.1 Brief Project Description:

The proposed Assam Power Sector Enhancement Investment Program of Assam State Electricity Board (ASEB) which is being processed under ADB’s Multi-tranche Financing Facility (MFF) would have the following components under Tranche III, namely:

Table 1.0: Components under Tranche III Sl. No. Description Unit Quantity 1. Access to power (Distribution) a) New 33/11 kV Substations No. 29 b) Associated 33 kV lines Km 620.3 c) Associated 11 kV Km 307 d) Augmentation of existing 33/11 kV Substations No. 13 e) R&M of existing 33/11 kV Substations No. 4 f) New 33 kV lines for system strengthening Km 339 2. Energy Efficiency Enhancement & Loss reduction a) HVDS (Installation of DTRs of various capacities) No. 30 b) Installation of LT ABC for commercial loss Km 60 reduction c) Installation of 11 kV ABC for commercial loss Km 10 reduction

The details of Tranche III Sub-projects are given in the below Table 2.0, Table 2.1 and Table 2.2 respectively:

Table 2.0: Details of Sub-projects under Tranche III for Sub-Station

SL. No. Name of the Sub-Project MVA Package No. ADB /LAZ/01 1 33/11 kV, 2x5 MVA Dhubri 10 2 33 /11 kV, 2x2.5 MVA Balajan 5 3 33 /11 kV, 2x5 MVA North Salmara 10 Total 25 MVA Package No. ADB /LAZ/02 1 33 /11 kV, 2x5 MVA Borka 10 2 33 /11 kV, 2x10 MVA Dharapur 20 3 33 /11 kV, 2x10 MVA Adabari 20 4 33 /11 kV, 2x5 MVA Hekera 10 Total 60 MVA Package No. ADB /LAZ/03 1 33 /11 kV, 2x10 MVA Jatia 20 2 33 /11 kV, 2x10 MVA Nehru Stadium 20 3 33 /11 kV, 2x2.5 MVA at Ghagrapar 5 4 33 /11 kV, 2x5 MVA Mangaldoi Ind Estate 10 Total 55 MVA

5

SL. No. Name of the Sub-Project MVA Package No. ADB/CAZ/01 1 33 /11 kV, 2x2.5 MVA Bhaga 5 2 33 /11 kV, 2x5 MVA Lamajuar 10 3 33 /11 kV, 2x10 MVA Chirukandi (Rangpur) 20 Total 35 MVA Package No. ADB/CAZ/02 1 33 /11 kV, 2X2.5 MVA Deodhar 5 2 33/11 kV, 2x5 MVA Boginadi 10 3 33/11 kV, 2x5 MVA Naoboicha 10 4 33/11 kV, 2x5 MVA Daflagarh 10 5 33/11 kV, 2x5 MVA Harchurra 10 6 33/11 kV, 2x5 MVA Thelamara (Erabari) 10 Total 55 MVA Package No. ADB/UAZ/01 1 33/11 kV, 2x5 MVA Bhadoi Pasali 10 2 33/11 kV, 2x10 MVA Dibrugarh - II 20 Total 30 MVA Package No. ADB/UAZ/02 1 33/11 kV, 2x10 MVA Tinsukia – II (Panitola) 20 2 33/11 kV, 2x10 MVA Na Pukhuri / Sreepuria 20 3 33/11 kV, 2x5 MVA Pengeri 10 Total 50 MVA Package No. ADB/UAZ/03 1 33/11 kV, 2x10 MVA Cinnamora 20 2 33/11 kV, 2x5 MVA, Jorhat by pass, Hatigarh 10 3 33/11 kV, 2x5 MVA Panichokua 10 4 33/11 kV, 2x5 MVA, - II 10 Total 50 MVA

6

Table 2.1: Details of Sub-projects under Tranche III for 33 kV Transmission Line Sl. Name of the Sub-Project Components Line Length Sl. Name of the Sub-Project Components Line Length No. 33 kV Lines (km) No. 33 kV Lines (km) Package No. ADB /LAZ/01 Package No. ADB /LAZ/02 1 Matia (Dudhnoi) GSS (New) to Damra 6 9 LILO of Sishugram to Kamalpur 2 2 Balajan to Agamoni 15 10 Kamalpur GSS (New) to Hajo 25 3 Bilasipara GSS (New) to Bilasipara 4 11 Kamakhya - Adabari + Kam GSS to Kam 33 kV + LILO 4 of Fatasil - Jalukbari Line 4 Bilasipara GSS (New) to Chapar 35 12 Azara GSS (New) to Mirza 33/11 kV 7 5 Fakiragram to Kokrajhar 8 13 220 kV Boko GSS to Bamunigaon 7 6 Matiabag (Gauripur) GSS to new 33/11 kV Dhubri S/S 17 14 LILO Jalukbari - Airport 33 kV Feeder to new 33/11 kV 2 Dharapur S/S 7 Matiabag (Gauripur) GSS to new 33/11 kV Balajan S/S 20 15 Kamakhya GSS (New) to new 33/11 kV Adabari / 4 Jalukbari S/S 8 Chapor 33 kV S/S to new 33/11 kV North Salmara S/S 22 16 Kamalpur GSS (New) to new 33/11 kV Borka S/S 10 17 Boko (Bhalukkata) GSS to new 33/11 kV Hekera S/S 15 Total 127 km Total 76 km Package No. ADB /LAZ/03 Package No. ADB/CAZ/01 18 Rowta - Dolgaon (Mangaldoi) 25 26 Hailakandi GSS (New) to Hailakandi 5 19 Sonapur GSS (New) to Sonapur 10 27 Hailakandi GSS (New) to Ramkrishna Nagar 20 20 Sonapur GSS (New) to Dimoria (For LILO with Jagiroad - 6 28 Kabuganj 33 kV S/S to new 33/11 kV Bhaga S/S 10 Sonapur Line) 21 Chamata - Sarthebari 33 kV 17 29 LILO of Panchgram - 33 kV line to new 33/11 2 kV Lamajuar S/S 22 Kahilipara GSS to new 33/11 kV Jatia S/S 2.5 30 LILO of Srikona - Malinibil 33 kV line to new 33/11 kV 5 Chirukandi / Rangpur S/S 23 LILO of Ulubari - Paltanbazar 33kV line to new 33/11 kV 1 Nehru Stadium S/S 24 LILO of Rangia - Nalbari 33 kV line to new 33/11 kV 2 Ghagrapar S/S Total 42 km 25 Sipajhar GSS to new 33/11 kV Mangaldoi Ind S/S 4 Total 67.5 km Package No. ADB/CAZ/02 Package No. ADB/UAZ/01

31 Nagaon GSS (New) to Nagaon 33 kV 18 41 Behiating GSS (New) to Behiating 33 kV 8 32 Nagaon GSS (New) to Bebejia (Reor.) 1 42 Bordubi GSS to Duliajan 17 33 Nagaon GSS (New) to Barapujia (Reor.) 1 43 Sonari GSS (New) to LTPS + LILO of LTPS - Sonari 33 8 kV 34 Balipara GSS (AIDC) to Balipara 7 44 Bordubi GSS (New) to Bordubi 33 kV 3 35 Nagaon 33 kV S/S to new 33/11 kV Deodhar (Nanoi) S/S 15 45 Duliajan - Naharkatia 15 36 Depota GSS /AIDC GSS to new 33/11 kV Harchurra S/S 5 46 Naharkatia to Joypur 9 37 LILO of Deputa – Dhekiajuli to new 33/11 kV Erabari / 1.5 47 Joypur to Namrup 15 7

Sl. Name of the Sub-Project Components Line Length Sl. Name of the Sub-Project Components Line Length No. 33 kV Lines (km) No. 33 kV Lines (km) Thelamara S/S 38 Gohpur GSS to new 33/11 kV Duflagarh S/S 19 48 Bordubi GSS (New) to new 33/11 kV Bhadoi Pasali S/S 18 39 LILO of Nalkata - Lakhimpur Line to new 33/11 kV Naobaisa 10 49 Behiating GSS (New) to new 33/11 kV Dibrugarh - II S/S 10 S/S 40 Nalkata GSS to new 33/11 kV Boginadi S/S 20 Total 103 km Total 97.50 km Package No. ADB/UAZ/02 Package No. ADB/UAZ/03

50 Margherita GSS to Margherita 33 kV 18 54 Jorhat (W) GSS (New) to Jorhat SES, to Gotonga and 15 LILO to Pulibor 51 Tinsukia GSS to new 33/11 kV Na-Pukhuri S/S 18 55 Mariani GSS to new 33/11 kV Cinnamora S/S 15 52 Tinsukia GSS to new 33/11 kV Tinsukia - II S/S 5 56 Jorhat (W) GSS (New) to new 33/11 kV Jorhat By Pass 12 S/S 53 Margherita 33 kV S/S to new 33/11 kV Pengeri S/S 18 57 Golaghat GSS to new 33/11 kV Golaghat - II S/S 6 58 Jorhat (W) GSS (New) to new 33/11 kV Panichokua S/S 0.3 Total 59 km Total 48.3 km

8

Table 2.2: Details of Sub-projects under Tranche III for 11 kV Transmission Line Sl. Name of the Sub-Project Components Line Length Sl. Name of the Sub-Project Components Line Length No. 11 kV Lines (km) No. 11 kV Lines (km) Package No. ADB /LAZ/01 Package No. ADB /LAZ/02 1 From new 33/11 kV Dhubri S/S outgoing. 10 4 From new 33/11 kV Dharapur S/S outgoing. 10 2 From new 33/11 kV Balajan S/S outgoing 16 5 From new 33/11 kV Adabari / Jalukbari S/S outgoing. 5 3 From new 33/11 kV North Salmara S/S outgoing. 16 6 From new 33/11 kV Borka S/S outgoing. 12 7 From new 33/11 kV Hekera S/S outgoing 10 Total 42 km Total 37 km Package No. ADB /LAZ/03 Package No. ADB/CAZ/01 8 From new 33/11 kV Jatia S/S outgoing 8 12 From new 33/11 kV Bhaga S/S outgoing. 10 9 From new 33/11 kV Nehru Stadium S/S outgoing 4 13 From new 33/11 kV Lamajuar S/S outgoing. 16 10 From new 33/11 kV Ghagrapar S/S outgoing. 12 14 From new 33/11 kV Chirukandi / Rangpur S/S outgoing. 12 11 From new 33/11 kV Mangaldoi Ind S/S outgoing. 10 Total 38 km Total 34 km Package No. ADB/CAZ/02 Package No. ADB/UAZ/01 15 From new 33/11 kV Deodhar (Nanoi) S/S outgoing. 10 21 From new 33/11 kV Bhadoi Pasali S/S outgoing. 16 16 From new 33/11 kV Harchurra S/S outgoing. 10 22 From new 33/11 kV Dibrugarh - II S/S outgoing. 6 17 From new 33/11 kV Erabari / Thelamara S/S outgoing. 12 18 From new 33/11 kV Duflagarh S/S outgoing. 10 19 From new 33/11 kV Naobaisa S/S outgoing. 6 Total 22 km 20 From new 33/11 kV Boginadi S/S outgoing. 16 Total 64 km Package No. ADB/UAZ/02 Package No. ADB/UAZ/03 23 From new 33/11 kV Na-Pukhuri S/S outgoing. 12 26 From new 33/11 kV Cinnamora S/S outgoing. 8 24 From new 33/11 kV Tinsukia - II S/S outgoing. 8 27 From new 33/11 kV Jorhat By Pass S/S outgoing. 8 25 From new 33/11 kV Pengeri S/S outgoing. 16 28 From new 33/11 kV Golaghat - II S/S outgoing. 8 29 From new 33/11 kV Panichokua S/S outgoing. 10 Total 36 km Total 34 km

9

1.2 Project Progress Status and Implementation Schedule:

A. Progress Status

The progress status of Environment activities for the Substations and Transmission Lines from January 2014 to June 2014 under Tranche III are given below in Table 3.0 and Table 3.1 respectively:

Table No. 3.0 Status of Environment activities in Tranche III Substations SI. NAME OF STATUS No. SUB-PROJECT Package No. ADB /LAZ/01 (Contractor: M/S NECCON Infra & Power Ltd.)  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land Dhubri  No major adverse environmental issues identified 1 (0.13 ha of  Boundary wall with gate is completed and Control room and Switch yard APDCL land works is in progress. acquired)  PPE equipment’s are being provided.  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  Boundary wall and Control room and Switch yard works is in progress.  No trees felling in substation land 33 /11 kV,  No Forest Land acquisition for Sub Station Balajan  No Wild life sanctuary involved in Substation land. 2 (0.67 ha of Govt. Land  No major adverse environmental issues identified acquired)  PPE equipment’s are being provided.  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  No trees felling in substation land 33 /11 kV  No Forest Land acquisition for Sub Station North Salmara  No Wild life sanctuary involved in Substation land. 3 (0.28 ha of Govt. Land  No major adverse environmental issues identified acquired)  Boundary wall and Control room and Switch yard works is in progress.  Labour camp exists and sanitary facilities being provided. Package No. ADB /LAZ/02 (Contractor: JV of Win Power Marketing Pvt. Ltd, M/S Sagar Steel Pvt. Ltd and M/S Siddhartha Engineering Ltd.)  No trees felling in substation land 33 /11 kV,  No Forest Land acquisition for Sub Station Borka  No Wild life sanctuary involved in Substation land. 4 (0.13 ha of  No major adverse environmental issues identified private barren  Boundary wall and Switch yard works is in progress. land Identified)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly. 33 /11 kV,  No trees felling in substation land Dharapur  No Forest Land acquisition for Sub Station 5 (0.08 ha of private barren  No Wild life sanctuary involved in Substation land. land acquired)  No major adverse environmental issues identified 10

SI. NAME OF STATUS No. SUB-PROJECT  Earth filling is completed and boundary wall works is in progress.  Labour camp and drinking water & sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  No trees felling in substation land 33 /11 kV,  No Forest Land acquisition for Sub Station Adabari  No Wild life sanctuary involved in Substation land. 6 (0.39 ha of  No major adverse environmental issues identified Govt. Land  Boundary wall and Control room works is in progress acquired)  Labour camp and drinking water & sanitary facilities being provided  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 Hekera  No Wild life sanctuary involved in Substation land. (0.39 ha of  No major adverse environmental issues identified 7 Govt. Land  Civil works is in progress. Top soil is being preserved for reuse in project. acquired)  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided Package No. ADB /LAZ/03 (Contractor: M/S NECCON Infra & Power Ltd.)  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Jatia  No major adverse environmental issues identified 8 (0.07 ha of  Boundary wall with gate is completed and Control room and Switch yard APDCL land works is in progress. acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Nehru Stadium  No major adverse environmental issues identified 9 (0.13 ha of  Boundary wall with gate is completed and Control room and Switch yard AEGCL land works is in progress. acquired)  Labour camp and drinking water & sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Ghagrapar  No major adverse environmental issues identified 10 (0.35 ha of  Boundary wall works is in progress and Control room and Switch yard private barren works is in progress. land acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided 11

SI. NAME OF STATUS No. SUB-PROJECT 33 /11 kV Mangaldoi Ind  The construction work of the proposed substation is completed and the 11 Estate (0.5 ha of Govt. same is charged from 22/10/13. Land acquired) Package No. ADB/CAZ/01 (Contractor: M/S NECCON Infra & Power Ltd.)  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Bhaga  No major adverse environmental issues identified 12 (0.27 ha of  Boundary wall works is in progress and Control room and Switch yard private barren works is in progress. land acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Lamajuar  No major adverse environmental issues identified. 13 (0.17 ha of  Boundary wall works is in progress and Control room and Switch yard private barren works is in progress. land acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Chirukandi  No major adverse environmental issues identified. (Rangpur) 14 (0.39 ha of  Boundary wall works is in progress and Control room and Switch yard private barren works is in progress. land acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided Package No. ADB/CAZ/02 (Contractor: JV of M/S D & G Constructions and M/s Standard Consultants)  No trees felling in substation land  No Forest Land acquisition for Sub Station 33 /11 kV,  No Wild life sanctuary involved in Substation land. Deodhar  No major adverse environmental issues identified 15 (0.13 ha of  Boundary wall works is in progress and Control room and Switch yard private barren works is in progress. land acquired)  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided 33/11 kV,  No trees felling in substation land 16 Boginadi  No Forest Land acquisition for Sub Station (0.13 ha of  No Wild life sanctuary involved in Substation land.

12

SI. NAME OF STATUS No. SUB-PROJECT private barren  No major adverse environmental issues identified land acquired)  Boundary wall with gate is completed and Control room and Switch yard works is in progress.  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station. 33/11 kV,  No Wild life sanctuary involved in Substation land. Naoboicha  No major adverse environmental issues identified (0.79 ha of 17 private TE  Boundary wall with gate is completed and Control room and Switch yard Garden land works is in progress. acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Daflagarh  No major adverse environmental issues identified (0.53 ha of 18 private TE  Boundary wall with gate is completed and Control room and Switch yard Garden land works is in progress. acquired)  Labour camp and drinking water facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Harchurra  No major adverse environmental issues identified (0.13 ha of 19 private TE  Boundary wall with gate is completed and Control room and Switch yard Garden land works is in progress. acquired)  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Thelamara  No major adverse environmental issues identified. 20 (0.27 ha of  Boundary wall with gate is completed and Control room and Switch yard Govt. Land works is in progress. acquired)  Labour camp and drinking water & sanitary facilities being provided  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided Package No. ADB/UAZ/01 (Contractor: M/S NECCON Infra & Power Ltd.) 33/11 kV  No trees felling in substation land 21 Bhadoi Pasali  No Forest Land acquisition for Sub Station (0.27 ha of  No Wild life sanctuary involved in Substation land.

13

SI. NAME OF STATUS No. SUB-PROJECT private barren  No major adverse environmental issues identified land acquired)  Boundary wall and Control room and Switch yard works is in progress.  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Dibrugarh – II  No major adverse environmental issues identified 22 (0.27 ha of AEGCL land  Boundary wall and Control room and Switch yard works is in progress. acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided Package No. ADB/UAZ/02 (Contractor: M/S A to Z Consultants Ltd.)  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Tinsukia – II  No major adverse environmental issues identified 23 (Panitola) (0.53  Boundary wall is completed and Control room and Switch yard works is in ha of Govt. progress. Land acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kVMVA  No Wild life sanctuary involved in Substation land. Na Pukhuri /  No major adverse environmental issues identified Sreepuria 24 (0.13 ha of  Land development is completed and control room building works has private barren started. Top soil is being preserved for reuse in project. land acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Pengeri  No major adverse environmental issues identified 25 (0.13 ha of Govt. Land  Boundary wall and Control room and Switch yard works is in progress. acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided Package No. ADB/UAZ/03 (Contractor: M/S NECCON Power & Infra Ltd.) 33/11 kV  No trees felling in substation land Cinnamora  No Forest Land acquisition for Sub Station 26 (0.39 ha of  No Wild life sanctuary involved in Substation land. Assam tea  No major adverse environmental issues identified Corporation  Boundary wall and Control room and Switch yard works is in progress. 14

SI. NAME OF STATUS No. SUB-PROJECT land acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Jorhat by  No major adverse environmental issues identified pass, Hatigarh 27 (0.13 ha of  Boundary wall is completed and Control room and Switch yard works is in Govt. Land progress. acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Panichokua  No major adverse environmental issues identified 28 (0.13 ha of private barren  Boundary wall and Control room and Switch yard works is in progress. land acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided  No trees felling in substation land  No Forest Land acquisition for Sub Station 33/11 kV  No Wild life sanctuary involved in Substation land. Golaghat – II  No major adverse environmental issues identified 29 (0.11 ha of  Land development is completed and control room building works has Govt. Land started. Top soil is being preserved for reuse in project. acquired)  Labour camp exists and sanitary facilities being provided.  Solid waste and construction waste is being handled properly.  PPE equipment’s are being provided

Table No. 3.1 Status of Environment activities in Tranche III Transmission Lines SI. NAME OF SUB-PROJECT STATUS No Package No. ADB /LAZ/01 (Contractor: M/S NECCON Power & Infra Ltd.) New 33kV line for system strengthening 1 Matia (Dudhnoi) GSS (New) to Damra (Approx. 6 Km) 2 Balajan to Agamoni (Approx. 15 Km) Line survey for all the above lines is 3 Bilasipara GSS (New) to Bilasipara (Approx. 4 Km) completed.

4 Bilasipara GSS (New) to Chapar (Approx. 35 Km) 5 Fakiragram to Kokrajhar (Approx. 8 Km) Associated 33kV line Matiabag (Gauripur) GSS to new 33/11 kV Dhubri S/S 6 Line survey for all the above lines is (Approx. 17 Km)

15

SI. NAME OF SUB-PROJECT STATUS No Matiabag (Gauripur) GSS to new 33/11 kV Balajan S/S completed. 7 (Approx. 20 Km) Chapor 33 kV S/S to new 33/11 kV North Salmara S/S 8 (Approx. 22 Km) Associated 11kV line 9 From new 33/11 kV Dhubri S/S outgoing. (Approx. 10 Km) Line survey for all the above lines is 10 From new 33/11 kV Balajan S/S outgoing. (Approx. 16 Km) completed. From new 33/11 kV North Salmara S/S outgoing. 11 (Approx. 16 Km) Package No. ADB /LAZ/02 (Contractor: WIN POWER MARKETING.) New 33kV line for system strengthening 12 LILO of Sishugram to Kamalpur (Approx. 2 Km) 13 Kamalpur GSS (New) to Hajo (Approx. 25 Km) Line survey for all the above lines is completed. Kamakhya - Adabari + Kam GSS to Kam 33 kV + LILO of 14 Fatasil - Jalukbari Line (Approx. 4 Km)

15 Azara GSS (New) to Mirza 33/11 kV (Approx. 7 Km) 16 220 kV Boko GSS to Bamunigaon (Approx. 7 Km) Associated 33kV line LILO Jalukbari - Airport 33 kV Feeder to new 33/11 kV 17 Dharapur S/S (Approx. 2 Km) Kamakhya GSS (New) to new 33/11 kV Adabari / Jalukbari 18 Line survey for all the above lines is S/S (Approx. 4 Km) completed. Kamalpur GSS (New) to new 33/11 kV Borka S/S 19 (Approx. 10 Km) Boko (Bhalukkata) GSS to new 33/11 kV Hekera S/S 20 (Approx. 15 Km) Associated 11kV line From new 33/11 kV Dharapur S/S outgoing. 21 (Approx. 10 Km) From new 33/11 kV Adabari / Jalukbari S/S outgoing. Line survey for all the above lines is 22 (Approx. 5 Km) completed. 23 From new 33/11 kV Borka S/S outgoing. (Approx. 12 Km) 24 From new 33/11 kV Hekera S/S outgoing. (Approx. 10 Km) Package No. ADB /LAZ/03 (Contractor: M/S NECCON Power & Infra Ltd.) New 33kV line for system strengthening 25 Rowta - Dolgaon (Mangaldoi) (Approx. 25 Km) 26 Sonapur GSS (New) to Sonapur (Approx. 10 Km) Line survey for all the above lines is Sonapur GSS (New) to Dimoria (For LILO with Jagiroad - completed. 27 Sonapur Line) (Approx. 6 Km) 28 Chamata - Sarthebari 33 kV (Approx. 17 Km) Associated 33kV line 29 Kahilipara GSS to new 33/11 kV Jatia S/S (Approx. 2.5 Km) LILO of Ulubari - Paltanbazar 33kV line to new 33/11 kV 30 Line survey for all the above lines is Nehru Stadium S/S (Approx. 1 Km) completed. LILO of Rangia - Nalbari 33 kV line to new 33/11 kV 31 Ghagrapar S/S (Approx. 2 Km) 32 Sipajhar GSS to new 33/11 kV Mangaldoi Ind S/S

16

SI. NAME OF SUB-PROJECT STATUS No (Approx. 4 Km) Associated 11kV line 33 From new 33/11 kV Jatia S/S outgoing. (Approx. 8 Km) From new 33/11 kV Nehru Stadium S/S outgoing. 34 (Approx. 4 Km) Line survey for all the above lines is From new 33/11 kV Ghagrapar S/S outgoing. completed. 35 (Approx. 12 Km) From new 33/11 kV Mangaldoi Ind S/S outgoing. 36 (Approx. 10 Km) Package No. ADB/CAZ/01 (Contractor: M/S NECCON Power & Infra Ltd.) New 33kV line for system strengthening 37 Hailakandi GSS (New) to Hailakandi (Approx. 5 Km) Line survey for all the above lines is Hailakandi GSS (New) to Ramkrishna Nagar completed. 38 (Approx. 20 Km) Associated 33kV line Kabuganj 33 kV S/S to new 33/11 kV Bhaga S/S 39 (Approx. 10 Km) Line survey for all the above lines is LILO of Panchgram - Karimganj 33 kV line to new 33/11 kV 40 completed. Lamajuar S/S (Approx. 2 Km)

LILO of Srikona - Malinibil 33 kV line to new 33/11 kV 41 Chirukandi / Rangpur S/S (Approx. 5 Km) Associated 11kV line 42 From new 33/11 kV Bhaga S/S outgoing. (Approx. 10 Km) From new 33/11 kV Lamajuar S/S outgoing. Line survey for all the above lines is 43 (Approx. 16 Km) completed. From new 33/11 kV Chirukandi / Rangpur S/S outgoing. 44 (Approx. 12 Km) Package No. ADB/CAZ/02 (Contractor: D & G Consultants & Standard Constructions Pvt. Ltd. [JV]) New 33kV line for system strengthening 45 Nagaon GSS (New) to Nagaon 33 kV (Approx. 18 Km) 46 Nagaon GSS (New) to Bebejia (Reor.) (Approx. 1 Km) Line survey for all the above lines is completed. 47 Nagaon GSS (New) to Barapujia (Reor.) (Approx. 1 Km) 48 Balipara GSS (AIDC) to Balipara (Approx. 7 Km) Associated 33kV line Nagaon 33 kV S/S to new 33/11 kV Deodhar (Nanoi) S/S 49 (Approx. 15 Km) Depota GSS /AIDC GSS to new 33/11 kV Harchurra S/S 50 (Approx. 5 Km) LILO of Deputa Dhekiajuli to new 33/11 kV Erabari / 51 – Thelamara S/S (Approx. 1.5 Km) Line survey for all the above lines is Gohpur GSS to new 33/11 kV Duflagarh S/S completed. 52 (Approx. 19 Km) LILO of Nalkata - Lakhimpur Line to new 33/11 kV Naobaisa 53 S/S (Approx. 10 Km) Nalkata GSS to new 33/11 kV Boginadi S/S 54 (Approx. 20 Km)

Associated 11kV line

17

SI. NAME OF SUB-PROJECT STATUS No From new 33/11 kV Deodhar (Nanoi) S/S outgoing. 55 (Approx. 10 Km) From new 33/11 kV Harchurra S/S outgoing. 56 (Approx. 10 Km) From new 33/11 kV Erabari / Thelamara S/S outgoing. 57 Line survey for all the above lines is (Approx. 12 Km) completed. From new 33/11 kV Duflagarh S/S outgoing. 58 (Approx. 10 Km) 59 From new 33/11 kV Naobaisa S/S outgoing. (Approx. 6 Km) From new 33/11 kV Boginadi S/S outgoing. (Approx. 16 Km) 60

Package No. ADB/UAZ/01 (Contractor: M/S NECCON Power & Infra Ltd.) New 33kV line for system strengthening 61 Behiating GSS (New) to Behiating 33 kV (Approx. 8 Km) 62 Bordubi GSS to Duliajan (Approx. 17 Km) Sonari GSS (New) to LTPS + LILO of LTPS - Sonari 33 kV 63 Line survey for all the above lines is (Approx. 8 Km) completed. 64 Bordubi GSS (New) to Bordubi 33 kV (Approx. 3 Km) 65 Duliajan - Naharkatia (Approx. 15 Km) 66 Naharkatia to Joypur (Approx. 9 Km) 67 Joypur to Namrup (Approx. 15 Km) Associated 33 kV line Bordubi GSS (New) to new 33/11 kV Bhadoi Pasali S/S Line survey for all the above lines is 68 (Approx. 18 Km) completed. Behiating GSS (New) to new 33/11 kV Dibrugarh - II S/S Monitoring for Ambient Air, Water and 69 (Approx. 10 Km) Noise carried out. Associated 11 kV line From new 33/11 kV Bhadoi Pasali S/S outgoing. 70 Line survey for all the above lines is (Approx. 16 Km) completed. From new 33/11 kV Dibrugarh - II S/S outgoing. 71 (Approx. 6 Km) Package No. ADB/UAZ/02 (Contractor: A to Z Maintenance & Engineering Service Ltd.) New 33kV line for system strengthening Line survey for all the above lines is completed. 72 Margherita GSS to Margherita 33 kV (Approx. 18 Km) Monitoring for Ambient Air, Water and Noise carried out. Associated 33 kV line Tinsukia GSS to new 33/11 kV Na-Pukhuri S/S 73 (Approx. 18 Km) Line survey for all the above lines is Tinsukia GSS to new 33/11 kV Tinsukia - II S/S completed. 74 (Approx. 5 Km) Monitoring for Ambient Air, Water and Margherita 33 kV S/S to new 33/11 kV Pengeri S/S Noise carried out. 75 (Approx. 18 Km) Associated 11 kV line From new 33/11 kV Na-Pukhuri S/S outgoing. 76 Line survey for all the above lines is (Approx. 12 Km) completed. From new 33/11 kV Tinsukia - II S/S outgoing. 77 Monitoring for Ambient Air, Water and (Approx. 8 Km) Noise carried out. 78 From new 33/11 kV Pengeri S/S outgoing. (Approx. 16 Km) Package No. ADB/UAZ/03 (Contractor: M/S NECCON Power & Infra Ltd.)

18

SI. NAME OF SUB-PROJECT STATUS No New 33kV line for system strengthening Line survey for all the above lines is completed. Jorhat (W) GSS (New) to Jorhat SES, to Gotonga and LILO 79 Monitoring for Ambient Air, Water and to Pulibor (Approx. 15 Km) Noise carried out.

Associated 33 kV line Mariani GSS to new 33/11 kV Cinnamora S/S 80 (Approx. 15 Km) Jorhat (W) GSS (New) to new 33/11 kV Jorhat By Pass S/S 81 Line survey for all the above lines is (Approx. 12 Km) completed. Golaghat GSS to new 33/11 kV Golaghat - II S/S 82 Monitoring for Ambient Air and Noise (Approx. 6 Km) carried out. Jorhat (W) GSS (New) to new 33/11 kV Panichokua S/S 83 (Approx. 0.3 Km)

Associated 11 kV line From new 33/11 kV Cinnamora S/S outgoing. Line survey for all the above lines is 84 (Approx. 8 Km) completed. From new 33/11 kV Jorhat By Pass S/S outgoing. Monitoring for Ambient Air, Water and 85 (Approx. 8 Km) Noise carried out. From new 33/11 kV Golaghat - II S/S outgoing. Line survey for all the above lines is 86 (Approx. 8 Km) completed. From new 33/11 kV Panichokua S/S outgoing. Monitoring for Ambient Air, and Noise 87 (Approx. 10 Km) carried out.

B. Implementation Schedule for Tranche III Sub projects

The implementation schedule for tranche III sub project is given below in Table 4.0.

19

Table 4.0: Implementation Schedule for Tranche III

2011 2012 2013 2014 Subproject Activates Q Q Q Q Q Q Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 3 4 1 2 3 4 Route Selection Route selection for S/S completed in 2011 and for Transmission lines completed in 4th Quarter, 2012 Community Consultations X X X X X X X X X X X X P P Identification of Environmental Route Alignment and identification of Environmental X X X X sensitive areas sensitive areas finalized. Top Soil Conservation X X X X X X X X X X X X X Water Sprinkling (Dust Control) X X X X X X X X X X X X X Solid Waste / Construction Waste X X X X X X X X X X X X X Mgt EMP Compliance during Pre- Pre Construction activities completed X X X X X Construction as finalization of route alignment EMP Compliance during X X X X X X X X X X X X X P P Construction) EMP Compliance during Post Activity yet to start Construction Ambient Air Quality Monitoring for X X X X X X X X P P the Subprojects X X Water Quality Monitoring for the X X X X X X X X P P Subprojects X X Ambient Noise Monitoring for the X X X X X X X X P P Subprojects X X Activities of GRC X X X X X P External Monitoring Evaluation To be decided after discussion with ADB Counterpart

Activities Completed Activities performed during reporting periods Activities Planned

Q: Quarter; X: Completed Activity; P: Planned Activity

20

2.0 Compliance to National Regulations:

The relevant applicable Acts and Legislations to the project is given in the Table No.5.0

Table No. 5.0: Applicable Acts and Legislations to the project Compliance Act/Rule/Notification Year Objectives Status The Environment 1986 To protect and improve the overall environment. (Protection) Act Complied The Environment 1986 (Protection) Rules Indian Forest Act 1927 To consolidate the laws related to forest, the transit of forest produce and the duty liveable on timber and other forest produce. Forest (Conservation) Act 1980 Conservation of Forests, Judicious use of Not forestland for non-forestry purposes; and to Applicable Forest (Conservation) Rules 1981 replenish the loss of forest cover by Compensatory Afforestation on degraded No Forest forestland and non-forest land. Land is Forest Conservation Rules 2003 Procedure for submission of the proposals involved. (Notification) seeking approval for Central Government for diversion of forestland to non-forest purposes. Wild Life (Protection) Act 1972 To protect wildlife in general and National Parks Not and Sanctuaries in particulars. Applicable

The Wild Life (Protection) To protect wild animals, birds and plants with a No Wild Life Amendment Act 2002 view to ensure the ecological and environmental Protected security of the country area is involved. The Water (Prevention and 1974 To control water pollution by controlling discharge Control of Pollution) Act of pollutants as per prescribed standards Complied The Air (Prevention and 1981 To control air pollution by controlling emission of Control of Pollution) Act air pollutants as per prescribed standards Complied The Noise Pollution 2000 To regulate and control noise producing and (Regulation and Control) generating sources with the objective of Rules maintaining the ambient air quality standards in Complied The Noise Pollution 2006 respect of noise (Regulation and Control) Amendment Rules The Ancient Monuments and To provide for the preservation of ancient and Not Archaeological Sites and historical monuments and archaeological sites Applicable Remain Act 1958 and remains of national importance and No ASI site protection sculptures, carvings and other like identified so objects. far

21

Compliance Act/Rule/Notification Year Objectives Status The Electricity Act Although the Act does not explicitly deal with environmental implications of activities related to 2003 power generation, transmission and distribution. Complied However, ASEB integrates environment protection as a part of its project activities.

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement

The Table 6.0 shows the applicable Environmental Covenants from the ADB Loan Agreement

Table No. 6.0: Environmental Covenants Para Product Schedule Description Remarks/Issues No. --For each Subproject, ASEB IEE, EMP as required have been shall cause the IA to prepare uploaded in the websites. This is and implement the necessary utilised as per the requirement during IEE as applicable, and EMP the review and monitoring of the (with budget) in accordance construction phase of the project. with the EARF. For Further an Environment monitoring Subprojects, the environmental agency has been fielded to carry out categorization and assessment the regular environmental monitoring procedures defined in the as set out in the EMP. EARF shall be followed. For The environmental monitoring is being Loan 2800 5, LA 14 any environment category A or carried out in all three phases i.e. in B sensitive Subproject, an IEE pre- construction, during construction as applicable shall be prepared and post construction phases. and made available to the Report to ADB twice a year on the public 120 days before the implementation of the EMPs for each Subproject is submitted to ADB Subproject is being complied. for approval. ASEB through the IA shall monitor, audit, and The subproject involve no adverse report to ADB twice a year on environmental impacts, hence hiring the implementation of the of independent external monitoring EMPs for each Subproject. agency is not felt by APDCL. --ASEB shall cause APDCL to ensure effective implementation of following activities, including as required, that all bidding documents and contracts for Works contain provisions that Loan 2800 5, LA 15 require contractors to: (a) comply with the measures The EMP as a part of IEE are being relevant to the contractor set incorporated in Bid document and forth in the IEE, the EMP, and obligations to be followed by the the RP, and any corrective or contractor during pre-construction, preventative actions set forth in construction and post construction

22

Para Product Schedule Description Remarks/Issues No. a Safeguards Monitoring period. The PMU is monitoring the Report; activities of the contractors from time to time to ensure the contractors follow the safeguard issues as applicable by State laws and ADB guidelines during pre-construction construction and also to be monitored in post construction period. (b) make available a budget for Has been provided in the IEE and RP all such environmental and accordingly. social measures; (c) provide APDCL with a The project is categorised as B in written notice of any distribution system and IEE is unanticipated environmental, prepared and there is no adverse resettlement or indigenous environmental impacts. peoples risks or impacts that arise during construction, PMU along with APDCL officials are implementation or operation of ready to carry out all environmental the Project that were not issues if any that arise during considered in the IEE, the construction and will be addressed EMP, and the RP; and mitigated accordingly. (d) adequately record the condition of roads, and other infrastructure prior to starting to Being complied. transport materials and construction; and (e) reinstate pathways, other local infrastructure, and land to This will be ensured through at least their pre-project appropriate monitoring at the post condition upon the completion construction stage of the project. of construction. ASEB shall cause the IA to ensure that civil works contracts under the Project PMU is monitoring the activities of the follow all applicable labor laws contractors from time to time to of the Borrower and the State ensure the requirements of the labour and that these further include laws and other applicable State laws provisions to the effect that are being followed during the pre- contractors; (i) carry out construction and construction stage Loan 2800 5, LA 19 HIV/AIDS awareness programs by the contractors. for labor and disseminate

information at worksites on

risks of sexually transmitted HIV/AIDS awareness programs for diseases and HIV/AIDS as part labor has been conducted periodically of health and safety measures during construction stage for those employed during construction; and (ii) follow and implement all statutory

23

Para Product Schedule Description Remarks/Issues No. provisions on labor (including not employing or using children as labor, equal pay for equal work), health, safety, welfare, sanitation, and working conditions. Such contracts shall also include clauses for termination in case of any breach of the stated provisions by the contractors.

4.0 Compliance to Safeguards Management Plan:

Based on the Environmental Management Plan the Compliance Status on Environmental Issues in Tranche III Subprojects for construction stage has been prepared and presented in Table No. 7.

24

Table 7.0: Environmental Checklist for Tranche III Responsibility Project Environmental Compliance Status/ Management / Mitigation Measures Super Review Activity Issues Planning Implementation Monitoring Remarks Vision Agency

Construction Stage Environmental and Social Management Construction techniques and machinery Cell (ESMC) of Project Management Unit selection to minimize noise and vibration. (PMU) conducted periodic spot check to Equipment Noise to be limited to 70 dB(A) at site confirm compliance. Noise and ESMC/ ESMC/ layout and boundaries. Environmental and Social APDCL Contractor APCB Being Complied. vibrations EMA PMU installation Management Cell (ESMC) of Project The parameters on noise & vibration are Management Unit (PMU) to conduct being examined by the environment periodic spot checks to confirm monitoring consultant on regular basis. compliance. Physical Construction activities on cropping land Disturbance of construction timed to avoid disturbance of field crops ESMC/ Contractors are avoiding disturbance to farming APDCL Contractor ESMC ADEF (manual (within one month of harvest wherever PMU field crops activity labor) possible). Noise, Construction equipment to be maintained Being Complied. vibration, and in accordance with GOI standards for Noise and vibration exposure to workers Mechanized operator noise exposure to workers. ESMC/ ESMC/ APDCL Contractor APCB in accordance with GOI standards are construction safety, EMA PMU being examined by the environment equipment Equipment to be shut off when not in monitoring consultant on regular basis.. wear and tear use. Removal of Marking of trees / vegetation to be Substation Being Complied. trees removed prior to clearance, and strict ESMC/ site APDCL Contractor ESMC ADEF Contractors are marking trees / vegetation and other control on clearing activities to ensure PMU clearance to ensure minimal clearance. vegetation minimal clearance. Trees allowed growing up to a height within the RoW by maintaining adequate clearance between the top of tree and Fire hazards the conductor as per transmission design

standards. Trimming / Provisions are made to clearance the cutting of growing up trees within the Right of Way Trees that can survive pruning to comply ESMC/ trees within Temporary APDCL Contractor ESMC ADEF (RoW) for maintenance the transmission with vertical and horizontal separation PMU Right-of-Way loss of line in future. requirements should be pruned instead (RoW) vegetation and of cleared. permanent

deforestation Felled trees and other cleared or pruned vegetation to be disposed of as authorized by ADEF

25

Responsibility Project Environmental Compliance Status/ Management / Mitigation Measures Super Review Activity Issues Planning Implementation Monitoring Remarks Vision Agency Temporary Construction workers prohibited from Being Complied. Wood / loss of harvesting wood in the project area ESMC/ vegetation vegetation and APDCL Contractor ESMC ADEF (apart from locally employed staff PMU Contractors are using gas or kerosene harvesting permanent continuing current legal activities). instead of wood for cooking. deforestation Dust, exhaust, and noise emissions from Controlled construction activities and construction maintenance of machineries, timely Ambient air equipment. scheduling of construction activities to Being Complied. quality and avoid nuisance to nearby communities. ESMC/ ESMC/ noise Noise impacts APDCL Contractor APCB Monitoring as per GOI standards on air, EMA PMU level and on Construction equipment to meet GOI water and noise are examined by the Water quality nearby emissions and noise control standards. environment monitoring consultant. communities Water sprays to be used for dust control and as necessary. construction workers Fuel and any other hazardous materials Being Complied. Storage of Possible spills will be securely stored to prevent spills. chemicals resulting in Contractors to provide spill response kit ESMC/ ESMC / Contractors are storing the oils and fuels and any contamination APDCL Contractor APCB in accordance with Material Safety Data EMA PMU on cemented floor to prevent spills and hazardous land, water, and Sheets for chemicals and hazardous getting contaminated with surface and materials air materials. ground water and land. Noise Construction activities only undertaken Monitoring as per GOI standards on noise Construction nuisance to ESMC/ ESMC/P during the day and local communities APDCL Contractor APCB are examined by the environment schedules neighboring EMA MU informed of the construction schedule. monitoring consultant. properties Contract provisions specifying minimum Being complied. Injury and sanitation, health, and safety

sickness of requirements for construction camps. Health and ESMC / APCB Contractors providing Personnel workers and APDCL Contractor ESMC safety PMU & ADH members of the Contractor to prepare and implement a Protective Equipment’s to the workers during construction time. First aid box and public health and safety plan including worker fire extinguisher are kept at work site. training and daily/weekly briefings.

26

Responsibility Project Environmental Compliance Status/ Management / Mitigation Measures Super Review Activity Issues Planning Implementation Monitoring Remarks Vision Agency Construction workforce facilities to Provision of Potential BOD include proper sanitation, water supply, Being complied. Sanitary and faecal and waste disposal facilities, including ESMC / facilities for APDCL Contractor ESMC APCB coliform primary treatment for domestic sewage PMU Contractors providing sanitary and waste construction contamination and secure disposal of domestic solid disposal facilities at construction camp. workers wastes. Construction wastes to be managed in accordance with GOI standards and industry best practices.

Waste lubricating oils to be disposed or Air, soil, and Being complied. recycled off-site by licensed service APCB/ water pollution Construction companies. ADB due to ESMC/ ESMC / waste APDCL Contractor Review inadequate EMA PMU Contractors properly handling Solid and management Transformer oils to be returned to Missio management construction waste. vendors via existing arrangements for n and control transformer maintenance.

Scrap steel and other salvaged materials to be auctioned and disposed / recycled off-site by licensed vendors.

27

5.0 Safeguards Monitoring Results and Unanticipated Impacts

A. Environmental Monitoring Schedule:

In order to comply to requirements of Environmental monitoring an external environmental monitoring agency has been hired by PMU to carry out the environmental monitoring with regards to air quality, water quality and noise levels during preconstruction, construction and post construction stage. The primary responsibility of the environmental monitoring agency are for testing, analyzing and reporting impact of transmission lines & substation projects on air, ground & surface water and noise levels.

Since the civil construction works under the project are very meager, hence, the environment monitoring for ambient air quality, water quality and noise levels during various stages – pre construction, construction and post construction are being monitored for Tranche III as per below schedule. (Refer Table 8.0).

Table No. 8.0: Environment Monitoring Schedule for Tranche III

Sl. Sample Maximum Frequency of Parameters. Locations. No. Nos. Sampling. Substations Twice during construction and Ambient Air quality 1 At the Sub Stations 29 once during post construction monitoring

Twice during construction and Ambient Noise level 2 At the Sub Stations 29 once during post construction monitoring

Water quality Twice during construction and monitoring once during post construction 3 (both surface & At the Sub Stations 29 ground water) Transmission Lines Habitations throughout the Once during pre-construction; Ambient quality Air 1 transmission 75 twice during construction and monitoring corridor, camp once during post construction sites Habitations throughout the Once during pre-construction; Ambient Noise level 2 transmission 75 twice during construction and monitoring corridor, camp once during post construction sites Water quality Water bodies along monitoring Once during pre-construction; the transmission- 3 (both surface & 75 twice during construction and corridor, camp ground once during post construction sites water)

28

B. Environmental Monitoring Parameters

The details of parameters for Ambient Air, Water and Noise being monitored by Environmental Monitoring Agency are given below in Table 9.0.

Table 9.0: Environmental Monitoring Parameters Sl. Environmental Parameters Analytical Parameters No.

1 Air Quality Monitoring PM10, PM2.5 ,SO2, NO2 2 Ground Water Quality Monitoring pH, Turbidity (NTU), Specific Conductance (micro mhos/cm), Total Dissolved Solids (TDS), Total Alkalinity (as CaCO3), Total Hardness (as CaCO3), Calcium (as Ca), Magnesium (as Mg), Chlorides (as Cl), Sulphates (as SO4), Nitrates (as NO2), Fluoride (as F), Arsenic (as As), Selenium (as Se), Cadmium (as Cd), Copper (as Cu), Lead (as Pb), Zinc (as Zn). 3 Surface Water Quality Monitoring Colour (Hazen Units), Dissolved Oxygen (DO), pH, Iron (as Fe), Chlorides (as Cl), Biological Oxygen Demand (BOD), Total Dissolved Solids (TDS), Copper (as Cu), Total Chromium (as Cr), Sulphate (as SO4), Nitrates (as NO3), Fluoride (as F), Total Coliform (MPN/100ml), Cadmium (as Cd), Selenium (as Se), Arsenic (as As), Lead (as Pb), Zinc (as Zn), Chromium (as Cr+6), Phenolic compounds (as C6,H5OH, Oil & Grease). 4 Noise Level Monitoring Day and Night time

The details of parameters for Ambient Air, Water and Noise being monitored by Environmental Monitoring Agency are given below.

C. Air Quality Parameters:

Ambient air quality monitoring has been conducted on 24 hourly basis with respect to the following parameters

1. Particulate matter (Size less than 10 µm) or PM10

2. Particulate matter (Size less than 2.5 µm) or PM2.5

3. Sulphur dioxide (SO2)

4. Nitrogen dioxide (NO2)

The summary of results of Ambient Air Quality of 14 locations of distribution lines and 5 Sub stations are presented in Annexure – 1.1 & Annexure 1.2 respectively. The results were compared with National Ambient Air Quality Standards, 2009 as specified by CPCB (Ref. Annexure -2). Air monitoring location maps are provided in Annexure-7.

29

D. Water Quality Parameter:

The details of monitoring of Surface/Ground Water Quality of 12 locations in distribution lines and for 5 locations in Substations are presented in Annexure – 3.1 & Annexure 3.3 respectively. While the summary of the monitoring results of Surface/Ground Water Quality of 12 locations along distribution lines and for 5 locations in Substations are presented in Annexure – 3.2 & Annexure 3.4 respectively. The results of ground water quality parameters were compared with Indian Standard IS: 10500 and the surface water quality results were compared with Class C standards as per Indian Standard IS: 2296 (Ref. Annexure – 4). Water monitoring location maps are provided in Annexure-7.

E. Ambient Noise Levels:

In the study area of Tranche-III, locations were selected based on the sensitivity and habitations. Noise monitoring were done at various proposed locations to identify the existing noise level and to suggest mitigation measures or other control measure to reduce the impacts during the construction period, though construction activities of transmission lines doesn’t create major noise impacts at the surroundings. The monitoring of Noise Levels was undertaken at 14 locations along distribution lines and 5 locations for Substations. The frequency of monitoring was set at an interval of 30 seconds over a period of 10 minutes per hour for 24-hours.

The results of Noise Levels of 14 locations for distribution lines and 5 locations for Substations are presented in Annexure – 5.1 & Annexure 5.2 respectively. In India, the Noise Pollution (Regulation and Control) Rules, 2000 have been framed under the Environment (Protection) Act, 1986. These are a set of guidelines for regulation and control of noise. The ambient levels of noise for different areas/zones specified in the rules are indicated in Annexure - 6. Noise monitoring location maps are provided in Annexure-7.

6.0 Implementation of Grievance Redress Mechanism and Complaints Received from Stakeholders

There are 19 circles under APDCL for substations and distribution line. One Grievance Redressal Committee (GRC) cell at each circles level has been formed (i) to provide support to affected persons (AP’s) on problems arising from the environmental activities. (ii) record grievances of the AP’s and resolve them; and (iii) review grievances involving benefits like compensations for private tree loss and assistance to AP’s. A directive in this regard from Director (PMU), ASEB dated January 19, 2012 have been issued to APDCL, who are the Implementing Agencies of the MFF. GRC at circle levels are formed and Project Authorities are the Chairman of respective circles to comply the grievances in regard to environmental activities if any. i. Concerned Project Authority (IA) Chairman of the committee ii. One official from the o/o the concerned District Magistrate or SDM (Civil) Member iii. Concerned Circle Officer or his representative Member iv. Concerned Project Manager (IA) Member v. Deputy General Manager (PMU), APDCL Member 30

vi. AGM, Environment & Social Management Unit (ESMU) Member vii. Land Acquisition Officer (LAO), AEGCL Member viii. Affected Person(s)/Gaon Burah Member

Grievance Redress Committee (GRC) set up at circle level to monitor subproject implementation for each subproject affected area. The GRC will determine the merit of each grievance, and resolve grievances within an outer time limit of three months of receiving the complaint. The AP has the right to refer the grievances to appropriate courts of law if not satisfied with the redress at any stage of the process. The set up GRC has the system of records keeping, contact details of complainant, date of the complaint received, nature of grievance etc. if any for the ongoing project and taking the necessary action against the complaint.

During this reporting period no formal complaint or grievances from have been registered.

7.0 Conclusion and Recommendations

In order to have a sustainable development in the project the emphasis on the implementation of EMP has been given top most priority. The EMP prepared for the project was made part of the bid document and the contractor was made responsible for the implementation of EMP. The bid conditions require the contractor to adopt best construction practices which include most of the mitigation measures suggested in the EMP. Environment and Social Cell (ESMU) was constituted for closely monitoring of implementation of EMP by the contractor. A grievance redressal committee has been constituted with due representation to the people residing near to the project site. Complaints, if any, received will be recorded. The copy of the complaint together with the corrective action taken by the contractor will be placed before the committee immediately. The contractor will implement the decision taken by the committee. No complaint has been recorded during this period. Proper training on environmental issues during project implementation and EMP implementation are being organized for the staff and officers of the contractor and implementation agency. The implementing Agency, APDCL, will give more attention towards the implementation of EMP and project will be implemented in compliance with environmental regulations of the country and environment covenant of Loan Agreement. .

31

Annexure 1.1 Summary Ambient Air Quality Results (For Distribution Lines)

Longitude Latitude Concentration µg/m3 Sl. Location Monitoring Area Sub Station (E) (N) PM PM SO NO Remarks/Reasons No Name Date 10 2.5 2 2 Category

33 KV & 11 KV sub Distribution line of Dibrugarh District The concentration of all the Behaiting TG, Industrial/Res 1 Dibrugarh-II 94°53'21.7" 27°25'30.3" 14-01-2014 79.38 42.54 7.76 16.01 parameter is within the CPCB Jamirah idential ambient air standard limit. The concentration of all the 2 Khanikar Dibrugarh-II 94°55'17.9" 27°25'54.2" 15-01-2014 56.21 34.54 5.98 9.4 Residential parameter is within the CPCB ambient air standard limit. 33 KV & 11 KV sub Distribution line of Tinsukia District MVA The concentration of all the 3 Panimudi Gaon Tinsukia-II 95°15'20.6" 27°27'48.9" 10-01-2014 45.07 20.7 5.7 9 Residential parameter is within the CPCB (Panitola) ambient air standard limit. MVA The concentration of all the Panitola Sosan 4 Tinsukia-II 95°15'14.8" 27° 27' 3.7" 11-01-2014 70.17 41.84 6.4 15.43 Residential parameter is within the CPCB Ghat (Panitola) ambient air standard limit. The concentration of all the 5 Hukan Pukhuri Na Pukhuri 95°21'23.4" 27°27'11.4" 03-01-2014 74.14 48.68 8.7 4.5 Residential parameter is within the CPCB ambient air standard limit. The concentration of all the 6 Bahadur Chariali Na Pukhuri 95°23'49.4" 27°26'10.5" 04-01-2014 69.79 39.64 9.14 5.5 Residential parameter is within the CPCB ambient air standard limit. The concentration of all the 7 Mankhuli Gaon Na Pukhuri 95° 21' 8.9" 27°26'16.7" 05-01-2014 56.19 30.35 12.09 10.43 Silent parameter is within the CPCB ambient air standard limit. The concentration of all the 8 Chariali T E Na Pukhuri 95° 22' 2.0" 27° 27' 3.9" 06-01-2014 45.45 25.26 14.54 4.5 Residential parameter is within the CPCB ambient air standard limit. The concentration of all the 9 Tingrai Na Pukhuri 95°21'26.7" 27°26'44.1" 07-01-2014 77.51 52.63 9.78 13.34 Silent parameter is within the CPCB ambient air standard limit. 33 KV & 11 KV sub Distribution line of Jorhat District The concentration of all the Debaguri 10 Cinnamara 94° 18' 9.2" 26° 40' 43.6" 01-01-2014 50.54 30.23 12.34 11.60 Residential parameter is within the CPCB Pukhuria 2NO ambient air standard limit. The concentration of all the Cinamara 11 Cinnamara 94°13'59.2" 26°44'37.0" 02-01-2014 52.9 31.09 13.88 13.17 Residential parameter is within the CPCB Bamungaon ambient air standard limit. The concentration of all the 12 Cinamara Cinnamara 94°13'49.4" 26°43'41.6" 03-01-2014 62.05 35.19 9.65 14.75 Residential parameter is within the CPCB 32

Longitude Latitude Concentration µg/m3 Sl. Location Monitoring Area Sub Station (E) (N) Remarks/Reasons No Name Date PM10 PM2.5 SO2 NO2 Category

ambient air standard limit. 33 KV & 11 KV sub Distribution line of The concentration of all the Kamarpatty Ward 13 Golghat-II 93°57'23.3" 26°30'43.7" 8-01-2014 87.41 55.23 9.89 7.32 Residential parameter is within the CPCB No-2 ambient air standard limit. The concentration of all the 14 Adhar Satra Golghat-II 93°55'03.1" 26°32'07.7" 9-01-2014 79.34 51.12 12.78 19.65 Residential parameter is within the CPCB ambient air standard limit.

33

Annexure 1.2

Summary Ambient Air Quality Results (For Substation)

Sl. Concentration µg/m3 Location Longitude Latitude Date of Location Substations Remarks No. ID (E) (N) Monitoring PM10 PM2.5 SO2 NO2 Type Industrial/Re All the parameters are within 1 Dibrugarh-II AQSS22 94°55'13.9" 27°25'16.8" 13-01-2014 65.32 42.44 12.50 14.75 sidential permissible limits of NAAQS. MVA Tin- All the parameters are within 2 sukia-II AQSS23 95°15'18.5" 27° 27'45.6" 09-01-2014 56.39 30.26 8.7 4.5 Residential permissible limits of NAAQS. (Panitola) All the parameters are within 3 Na Pukhuri AQSS24 95°21'22.1" 27° 27'10.8" 02-01-2014 58.57 35.48 9.78 13.43 Residential permissible limits of NAAQS. AQSS28 Residential/ All the parameters are within 4 Panichokuwa 94°10'38.3" 26° 45'44.4" 4-01-2014 75.48 48.33 12.06 9.44 Silent permissible limits of NAAQS. AQSS29 All the parameters are within 5 Golaghat-II 93°57'13.0" 26°30'53.8" 7-01-2014 76.87 57.38 12.53 19.35 Residential permissible limits of NAAQS.

34

Annexure – 2

National Ambient Air Quality Standards, CPCB 2009

Concentration in Ambient Air Ecologically Industrial, Time Sensitive Area Residential, Method of Pollutant Weighted (notified by Rural and Measurement Average Central Other Area Government) Sulphur Annual* 50 20 Improved West and Dioxide (SO ) 2 Geake Method µg/m3 24 hours** 80 80 Ultraviolet Fluorescence

Jacob & Hochheiser Oxides of Modified Annual* 40 30 Nitrogen (NOx) (Na-Arsenite) Method µg/m3 Chemiluminescence Gas Phase 24 hours** 80 80 Chemiluminescence Particulate Annual* 60 60 Matter (Size Gravimetric less than 10 TOEM µm) or PM 24 hours** 100 100 10 Beta attenuation µg/m3

Particulate Annual* 40 40 Matter (Size Gravimetric less than 2.5 TOEM µm) or PM 24 hours** 60 60 2.5 Beta attenuation µg/m3

8 hours** 100 100 UV Photometric Ozone (O ) 3 Chemiluminescence µg/m3 1 hour** 180 180 Chemical Method Annual* 0.5 0.5 ASS/ ICP Method after sampling on EPM 2000 Lead (Pb) or equivalent Filter paper µg/m3 24 hours** 1.0 1.0 ED – XRF using Teflon filter Carbon 02 8 hours** 02 Monoxide Non Dispersive Infra Red (CO) (NDIR) Spectroscopy 1 hour** 04 04 mg/m3 Ammonia Annual* 100 100 Chemiluminescence (NH ) 3 24 hours** 400 400 Indophenol blue method µg/m3

35

Concentration in Ambient Air Ecologically Industrial, Time Sensitive Area Residential, Method of Pollutant Weighted (notified by Rural and Measurement Average Central Other Area Government) Gas Chromatography based continuous Benzene analyzer (C H ) Annual* 05 05 6 6 Adsorption and µg/m3 Desorption followed by GC analysis Benzo (a) pyrene (BaP) Solvent extraction – Particulate Annual* 01 01 followed by HPLC/GC phase only, analysis ng/m3 AAS/ICP method after Arsenic (As) Annual* 06 06 sampling on EPM 2000 ng/m3 or equivalent filter paper AAS/ICP method after Nickel (Ni) Annual* 20 20 sampling on EPM 2000 ng/m3 or equivalent filter paper

*Annual Arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week 24 hourly at uniform interval.

**24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring.

36

Annexure – 3.1 Summary Water Quality Locations (For Distribution Lines) Sl. Location Longitude Latitude Monitoring Sub Station Water Type Source Remarks/Reasons No Name (E) (N) Date 33 KV & 11 KV sub Distribution line of Dibrugarh District All the parameters was observed Behaiting TG, 1 Dibrugarh-II 94°53'21.7" 27° 5'29.8" 14-01-2014 GW Tube Well within the permissible limit as Jamirah per Bureau of Indian Standard All the parameters was observed 2 Khanikar Dibrugarh-II 94°55'17.2" 27° 5'54.1" 15-01-2014 GW Tube Well within the permissible limit as per Bureau of Indian Standard) 33 KV & 11 KV sub Distribution line of Tinsukia District At this location Turbidity of 10-01-2014 ground water was observed to MVA Tinsukia-II 3 Panimudi Gaon 95° 15'14.8" 27° 27' 3.7" GW Pump Well be above prescribed Standard (Panitola) limit.(IS: 10500)

At this location Turbidity of Panitola Sosan MVA Tinsukia-II ground water was observed to 4 95° 15'20.6" 27° 27'49.0" 11-01-2014 GW Tube Well Ghat (Panitola) be above prescribed Standard limit.(IS: 10500) All the parameters were observed within the permissible limit for ground water as per Tube Well / 95° 21'23.4" 27° 27'11.4" Bureau of Indian Standard). 5 Hukan Pukhuri Na Pukhuri 03-01-2014 GW/SW Tingrai 95° 21'29.1" 27° 27'19.8" The DO of Surface Water was River found to be slightly above the prescribed standard limit (IS: 2296C). All the parameters were observed within the permissible limit for ground water as per Tube Well / Bahadur 95° 23'49.4" 27° 26'10.5" Bureau of Indian Standard). 6 Na Pukhuri 04-01-2014 GW/SW Tingrai Chariali 95° 21'29.1" 27° 2719.8" The DO of Surface Water was River found to be above the prescribed standard limit (IS: 2296C). At this location Turbidity of ground water was observed to 7 Mankhuli Gaon Na Pukhuri 95° 21' 8.9" 27° 26'16.7" 05-01-2014 GW Tube Well be above prescribed Standard limit.(IS: 10500) At this location Turbidity of 8 Chariali T E Na Pukhuri 95° 21'45.5" 27° 27' 4.5" 06-01-2014 GW Water Tank ground water was observed to

37

Sl. Location Longitude Latitude Monitoring Sub Station Water Type Source Remarks/Reasons No Name (E) (N) Date be above prescribed Standard limit.(IS: 10500) All the parameters were 95° 21' 8.9" 27° 26'53.7" observed within the permissible 9 Tingrai Na Pukhuri 07-01-2014 GW Tube Well limit for ground water as per Bureau of Indian Standard). 33 KV & 11 KV sub Distribution line of Jorhat District At this location Turbidity of ground water was not within the prescribed Standard limit.(IS: Tap Pump/ Debaguri 94° 18' 9.9" 26° 40'43.4" 10500) 10 Cinnamara 01-01-2014 GW/SW Bhogdoi Pukhuria 2NO 94° 18'21.3" 26° 40'47.9" The DO of Surface Water was River found to be slightly above the prescribed standard limit (IS: 2296C). At this location Turbidity of Cinamara ground water was not within the 11 Cinnamara 94° 13' 58.9" 26° 44'36.9" 02-01-2014 GW Tap-Pump Bamungaon prescribed Standard limit.(IS: 10500) At this location Turbidity of ground water was observed to 12 Cinamara Cinnamara 94° 13' 58.9" 26° 44'36.9" 03-01-2014 GW Tube Well be above prescribed Standard limit.(IS: 10500)

38

Annexure 3.2 Summary of Water Quality Results (For distribution Line)

1. 33KV& 11KV Sub Transmission Line of Dibrugarh District:

Ground Water Results:

(mg/l) (mg/l) (mg/l) (mg/l) 4 2 3

Location /cm) pH Zinc Lead Nitrate Nitrate hs Copper Copper Specific Calcium Fluoride Chloride Sulphate Selenium Selenium Cadmium Parameters Magnesium Magnesium as Ca (mg/l) (as F) (mg/l) T.D.S. (mg/l) as (mg/l) Mg (as Cl) (mg/l) CaCO as NO (as Se) (mg/l) CaCO3 (mg/l)CaCO3 (as Pb) (mg/l) as SO (as Zn) (mg/l) Arsenic As as (as Cd) (mg/l) (as Cu) ( mg/l) Turbidity (NTU) Total Alkalinity asTotal Alkalinity Total Hardness asTotal Hardness Conductance(µmo

Standard 6.5- 5 - 500 250 200 300 75 200 0.05 45 - 1 0.01 0.01 0.05 0.05 5 IS: 10500 8.5 Behaiting TG, Jamirah 6.81 4 170 134 18 95 48 4.25 15 BDL 3.41 4.82 0.60 < 0.001 < 0.001 <0.03 < 0.001 <0.1 GWDIB6 Khanikar 6.25 1.70 238 167 11 86 69 2.23 17.05 BDL 4.33 2.34 0.45 < 0.001 < 0.001 <0.03 0.05 <0.1 GWDIB7

2. 33 KV & 11 KV sub Transmission line of Tinsukia District

Ground Water Results: (mg/l) (mg/l) (mg/l)

3 3 (mg/l) (mg/l) (mg/l) 2 Location 4 pH Zinc Zinc Lead Lead as As as As Nitrate Nitrate Copper Copper Arsenic Specific Calcium Fluoride Chloride Chloride Sulphate Selenium Selenium Cadmium Parameters Magnesium Magnesium (µmohs/cm) (µmohs/cm) (as F) (mg/l) T.D.S. (mg/l) as (mg/l) Mg as Ca (mg/l) (as Cl) (mg/l) as SO as NO (as Se) (mg/l) (as Zn) (mg/l) Conductance (as Cd) (mg/l) (as Pb) (mg/l) (as Cu) ( mg/l) Total Alkalinity Total Alkalinity Total Hardness Turbidity (NTU) as CaCO as CaCO

Standard 6.5- 5 - 500 250 200 300 75 200 0.05 45 - 1 0.01 0.01 0.05 0.05 5 IS: 10500 8.5 Panimudi Gaon 7.41 10.45 123 135 5.7 89 37 3.21 6 BDL BDL 1.23 0.45 < 0.001 < 0.001 <0.03 < 0.001 0.21

39

(mg/l) (mg/l) (mg/l)

3 3 (mg/l) (mg/l) (mg/l) 2 Location 4 pH Zinc Zinc Lead Lead as As as As Nitrate Nitrate Copper Copper Arsenic Specific Calcium Fluoride Chloride Chloride Sulphate Selenium Selenium Cadmium Parameters Magnesium Magnesium (µmohs/cm) (µmohs/cm) (as F) (mg/l) (as F) (mg/l) T.D.S. (mg/l) as (mg/l) Mg as Ca (mg/l) (as Cl) (mg/l) (as Cl) (mg/l) as SO as NO (as Se) (mg/l) (as Zn) (mg/l) Conductance Conductance (as Cd) (mg/l) (as Cd) (mg/l) (as Pb) (mg/l) (as Cu) ( mg/l) (as Cu) ( mg/l) Total Alkalinity Total Alkalinity Total Hardness Turbidity (NTU) as CaCO as CaCO

GWTIN1 Panitola Sosan Ghat 0.62 < 0.001 < 0.001 0.04 < 0.001 <0.1 GWTIN2 6.78 9.21 158 112 2.4 123 54 1.89 3 BDL 0.02 2.12 Hukan Pukhuri 0.21 < 0.001 < 0.001 0.04 < 0.001 <0.1 GWTIN3 6.32 3.42 215 76 12.05 67 41 2.75 BDL BDL 0.04 2.35 Bahadur Chariali 0.24 < 0.001 < 0.001 <0.03 < 0.001 <0.1 GWTIN4 6.73 2.24 121 93 8.55 81 65 0.45 4.5 BDL 0.48 1.86 Mankhuli Gaon 0.31 < 0.001 < 0.001 <0.03 < 0.001 <0.1 GWTIN5 7.05 7.53 198 143 14.45 93 75 3.17 8.5 BDL 0.02 0.98 Chariali T E GWTIN6 6.62 10.17 237 200 3.25 116 52 5.62 3.25 BDL 0.02 3.12 0.08 < 0.001 < 0.001 <0.04 < 0.001 0.18 Tingrai GWTIN7 6.86 2.7 180 162 9.84 74 83 4.93 15.75 BDL BDL 4.56 0.23 < 0.001 < 0.001 <0.04 < 0.001 <0.1

Surface Water Results:

Locations pH Unit) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) Parameters D.O. (mg/l) BOD (mg/l) Lead (as Pb) T.D.S. (mg/l) Oil & Grease Cr+6)) (mg/l) (as Cr) (mg/l) (MPN/100ml) Arsenic (mg/l) Chromium (as Colour (Hazen Fluoride (as F) Total Coliform Copper (as Cu) Chloride (as Cl) Selenium (as Se) Nitrate as (NO3) Total Chromium Cadmium (as Cd) Sulphate as (SO4) Iron as (Fe) (mg/l) Phenol (C6H5OH) Zinc (asZinc Zn) (mg/l) Standard 8.5 50 4 3 400 50 0.2 0.005 600 0.1 1500 300 1.5 - 1.5 5000 0.01 0.05 0.1 15 0.05 Class C Hukan Pukhuri 11 1350 7.10 1.20 4.2 1.42 14.78 3.53 BDL Nil 7.83 Nil 67 <0.05 <0.01 1.25 < 0.005 < 0.001 < 0.001 <0.1 <0.02 SWTIN1 apparent Bahadur Chariali 13.0 2700 6.82 0.65 5.8 0.94 10.89 2.08 BDL Nil 23.24 Nil 92 <0.05 <0.01 0.41 < 0.005 < 0.001 0.09 <0.1 <0.02 SWTIN2 apparent

40

3. 33 KV & 11 KV sub Transmission line of Jorhat District

Ground Water Results: (mg/l) (mg/l)

3 (mg/l) (mg/l) (mg/l) 2 Location 3 pH Zinc Zinc Lead Nitrate Nitrate hs/cm) Copper Copper Specific Calcium Fluoride Chloride Chloride Sulphate Selenium Selenium Cadmium Parameters Magnesium as Ca (mg/l) as Ca (mg/l) (as F) (mg/l) T.D.S. (mg/l) (as Cl) (mg/l) (as Cl) (mg/l) as Mg (mg/l) as (mg/l) Mg CaCO as NO (as Se) (mg/l) (as Zn) (mg/l) (as Pb) (mg/l) (as Pb) (mg/l) (as Cd) (mg/l) (as Cd) (mg/l) Arsenic as As Arsenic As as as SO4 (mg/l) as (mg/l) SO4 (as Cu) ( mg/l) Total Hardness Turbidity (NTU) as CaCO Total Alkalinity asTotal Alkalinity Conductance(µmo

Standard 6.5- 5 - 500 250 200 300 75 200 0.05 45 - 1 0.01 0.01 0.05 0.05 5 IS: 10500 8.5 Debaguri Pukhuria 0.50 < 0.001 < 0.001 <0.03 0.04 0.11 2NO GWJOR3 7.00 11.38 104 98 16 65 25 0.63 BDL BDL 0.17 0.13 Cinamara Bamungaon 0.72 < 0.001 < 0.001 <0.03 < 0.001 <0.1 GWJOR4 6.49 15.0 190 200 5 71 55 5.98 2.5 BDL 0.15 3.13 Cinamara GWJOR5 6.70 24.12 217 180 15 39 41 2.10 4 BDL 0.18 4.67 0.42 < 0.001 < 0.001 <0.03 < 0.001 <0.1

Surface Water Results:

Locations pH Unit) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) Parameters D.O. (mg/l) D.O. BOD (mg/l)BOD T.D.S. (mg/l) Cr+6)) (mg/l) (MPN/100ml) (as Cr) (mg/l) Arsenic (mg/l) Chromium (as Colour (Hazen Total Coliform Fluoride F) (as Copper (as Cu) Chloride Cl) (as Nitrate as (NO3) Total Chromium Selenium (as Se) Cadmium Cd) (as Phenol (C6H5OH) Iron as (Fe) (mg/l) Iron as (mg/l) (Fe) Sulphateas (SO4) Zinc Zn) (as (mg/l) Lead Pb) (mg/l) (as Oil & & Grease Oil (mg/l) Standard 8.5 50 4 3 400 50 0.2 0.005 600 0.1 1500 300 1.5 - 1.5 5000 0.01 0.05 0.1 15 0.05 Class C Debaguri 9.0 Pukhuria 2NO 6.37 9.43 6.9 2.50 14.46 2.83 BDL Nil 8 Nil 300 <0.30 <0.01 0.45 3000 < 0.005 < 0.003 < 0.001 <0.1 <0.03 apparent SWJOR2

41

Annexure 3.3 Details of Water Quality Location (For Substation)

Sl. Name of Monitoring Longitude (E) Latitude (N) Water Type Source Remark/Reason No. Sub Station Date All the parameters was observed within the 1 Dibrugarh-II 94°55'13.9" 27°25'16.8" 13-01-2014 GW Tube Well permissible limit as per Bureau of Indian Standard Tinsukia-II All the parameters was observed within the 2 95°15'18.5" 27° 27'45.6" 09-01-2014 GW Tube Well (Panitola) permissible limit as per Bureau of Indian Standard All the parameters was observed within the 95°21'22.1" 27° 27'10.8" permissible limit as per Bureau of Indian Standard 3 Na Pukhuri 02-01-2014 GW & SW Tube Well 95° 21'29.1" 27° 2719.8" The DO of Surface Water was found to be slightly above the prescribed standard limit (IS: 2296C). At this location Turbidity of ground water was 4 Panichokuwa 94°10'38.3" 26° 45'44.4" 4-01-2014 GW Tube Well observed to be above prescribed Standard limit.(IS: 10500) At this location Turbidity of ground water was 93°57'13.0" 26°30'53.8" 5 Golaghat-II 7-01-2014 GW & SW Tube Well observed to be above prescribed Standard limit.(IS: 93°57'05.2" 26°31'00.4" 10500)

42

Annexure 3.4

Summary of Water Quality Results (For Substation)

Ground Water Results: (mg/l) (mg/l)

Location Name 3 (mg/l) (mg/l) (mg/l) (mg/l) 2 and Location 4 pH Zinc Zinc Lead as As as As

ID Nitrate Copper Copper Arsenic Specific Calcium Fluoride Chloride Chloride Sulphate Selenium Selenium Cadmium Parameters Magnesium (µmohs/cm) (µmohs/cm) as Ca (mg/l) as Ca (mg/l) (as F) (mg/l) T.D.S. (mg/l) (as Cl) (mg/l) (as Cl) (mg/l) as Mg (mg/l) as (mg/l) Mg as SO as NO (as Se) (mg/l) (as Zn) (mg/l) Conductance (as Pb) (mg/l) (as Cd) (mg/l) (as Cu) ( mg/l) Total Alkalinity Total Alkalinity Total Hardness Turbidity (NTU) as CaCO3 (mg/l) as (mg/l) CaCO3 as CaCO

Standard 6.5- 5 - 500 250 200 300 75 200 0.05 45 - 1 0.01 0.01 0.05 0.05 5 IS: 10500 8.5 < < < Dibrugarh-IIGWSS22 6.98 0.37 330 390 74 139 129 3.63 51 BDL 7.9 4.28 0.11 <0.03 <0.1 0.001 0.001 0.001 MVA Tinsukia-II < < < 6.43 0.82 255 191 21 101 81 3.02 20.17 BDL 2.43 2.47 0.24 <0.03 <0.1 (Panitola)GWSS23 0.001 0.001 0.001 < < < Na PukhuriGWSS24 6.53 1.23 254 186 37 95 86 1.14 22.89 BDL 1.11 3.95 0.34 0.04 <0.1 0.001 0.001 0.001 < < < PanichokuwaGWSS28 7.33 7.89 223 186 7.67 109 83 2.61 41 BDL BDL 1.2 0.58 <0.03 <0.1 0.001 0.001 0.001 < < < Golghat-IIGWSS29 7.02 20 270 150 6 130 78 2.25 15.5 BDL BDL 2.63 0.28 <0.03 <0.1 0.001 0.001 0.001

Surface Water Results:

) (mg/l) ) (mg/l) ) (mg/l)

Locations 4 3 pH Iron Zinc Zinc OH) (mg/l) (mg/l) OH) Lead Lead (mg/l) (mg/l) 5 Nitrate Nitrate Colour Colour Phenol Copper Copper Fluoride Chloride Chloride Sulphate Selenium Selenium H Cadmium Parameters D.O. (mg/l) D.O. 6 BOD (mg/l)BOD (as F) (mg/l) (as F) (mg/l) T.D.S. (mg/l) (Hazen Unit) Cr+6)) (mg/l) Oil & & Grease Oil (MPN/100ml) (as Cl) (mg/l) (as Cl) (mg/l) (as Cr) (mg/l) as (Fe) (mg/l) (as Se) (mg/l) (as Zn) (mg/l) (as Pb) (mg/l) (as Pb) (mg/l) (as Cu) (mg/l) (as Cu) (mg/l) (as Cd) (mg/l) Arsenic (mg/l) Arsenic (mg/l) Chromium (as Total Coliform as (NO as (SO (C Total Chromium Std C 8.5 50 4 3 400 50 0.2 0.005 600 0.1 1500 300 1.5 - 1.5 5000 0.01 0.05 0.1 15 0.05 Na Pukhuri < < < < 0. < 7.2 4.65 4.3 1.3 13 BDL BDL Nil 14 Nil 45 15 0.55 - 0.89 4300 0.001 0.001 0.001 01 0.03 Golghat-II < < < 7.1 4.6 3.7 2.1 3.14 BDL BDL Nil 9 Nil 82 13apparent 0.58 <0.03 1.12 3610 <0.1 <0.03 0.001 0.001 0.001

43

Annexure – 4

Water Quality Standards

Indian Standard IS: 10500 Sl. Parameter IS: 10500 Test Method No 1 pH 6.5-8.5 pH meter 2 Turbidity (NTU) 5 Nephelometric 3 Specific Conductance(µs/cm) - Wheatstone Bridge 4 T.D.S. mg/L 500 Gravimetric Method 5 Chloride (as Cl), mg/L 250 Argentometric Method 6 Total Alkalinity (as CaCO3), mg/L 200 Indicator Method 7 Total Hardness (as CaCO3), mg/L 300 EDTA Titrimetric Method 8 Calcium (as Ca), mg/L 75 EDTA Titrimetric Method 9 Sulphate (as SO4), mg/L 200 Turbidity Method 10 Arsenic (as As), mg/L 0.05 Winkler Titrimetric Method 11 Nitrate (as NO2), mg/L 45 Chromotropic Acid Method 12 Magnesium (as Mg), mg/L - EDTA Titrimetric Method 13 Fluoride (as F), mg/L 1 APHA- 4500-D-F 14 Selenium (as Se), mg/L 0.01 AAS/ICP 15 Cadmium (as Cd), mg/L 0.01 IS: 3025 (Pt - 41) – 1991 16 Copper (as Cu), mg/L 0.05 AAS/ICP 17 Lead (as Pb), mg/L 0.05 AAS/ICP 18 Zinc (as Zn), mg/L 5 IS: 3025 (Pt - 49)- 1991 Source: Indian Standard (IS: 10500)

44

Indian Standard IS: 2296

Sl. Parameter and Unit A B C D E No 1 pH (max) (min : 6.5) 8.5 8.5 8.5 8.5 8.5 2 Colour (True) (Hazen unit) 10 300 300 - - 3 DO (mg/L) (minimum) 6 5 4 4 - 4 BOD (3d, 27oC) (mg/L) 2 3 3 - - 5 TDS (mg/L) 500 - 1500 2100 6 Total Coliforms (MPN/100 ml) 50 500 5000 - - 7 Oil and Grease (mg/L) - - 0.1 0.1 - 8 Chlorides (mg/L as Cl) 250 - 600 - 600 9 Sulfates (mg/L as SO4) 400 - 400 1000 10 Nitrates (mg/L as NO3) 20 - 50 - - 11 Fluorides (mg/L as F) 1.5 1.5 1.5 - - 12 Copper (mg/L) 1.5 - 1.5 - - 13 Iron (mg/L) 0.3 - 50 - - 14 Zinc (mg/L) 15 - 15 - - 15 Arsenic Total (mg/L) 0.05 0.2 0.2 - - 16 Lead (mg/L) 0.1 - 0.1 - - 17 Cadmium (mg/L) 0.01 - 0.01 - - 18 Chromium (VI) (mg/L) 0.05 0.05 0.05 - - 19 Selenium (mg/L) 0.01 0.05 - - 20 Total Chromium - - - - - 21 Phenols (mg/L) 0.002 0.005 0.005 - Source: IS: 2296-1982

Note: Class A: Drinking water source without conventional treatment but after disinfection; Class B: outdoor bathing; Class C: Drinking water source with conventional treatment followed by disinfection; Class D: Fish culture and wild life propagation; Class E: Irrigation, industrial cooling or control waste disposal.

45

Annexure – 5.1 Summary of Noise Level Results (For Distribution Line) Day Time Night Time Sl. Location Longitude Latitude Monitor- Area Sub Station Noise NoiseLeq Remarks/Reasons No. Name (E) (N) ing Date Category Leq dB(A) dB(A) Ambient Noise Result of 33 kV & 11 kV Sub-Distribution lines of Dibrugarh District  The industrial area is located at a Behaiting TG, Industrial/Re distance of 100m-200m from the 1 Dibrugarh-II 94°53'21.7" 27° 25'30.3" 14-01-2014 71.5 51.8 Jamirah sidential sampling point &NH-37 passes near to this location.  This area is categorized as residential area where noise level was observed 2 Khanikar Dibrugarh-II 94°55'17.9" 27° 25'54.2" 15-01-2014 53.4 40.6 Residential within the standard as per CPCB Ambient Noise Level. Ambient Noise Result of 33 kV & 11 kV Sub-Distribution lines of Tinsukia District  Noise level was observed little high at day time.  Regular vehicular movement on the Panimudi MVA Tinsukia- 3 95°15'20.6" 27° 27'48.9" 10-01-2014 60.3 44.8 Residential road (30m away) was observed Gaon II (Panitola) during the sampling process & railway track is at a distance of 5km from the sampling point.  Noise level was observed within the Panitola MVA Tinsukia- 4 95°15'14.8" 27° 27' 3.7" 11-01-2014 54.8 42.5 Residential standard limit at this location for both Sosan Ghat II (Panitola) day & night.  Noise level was observed within the 5 Hukan Pukhuri Na Pukhuri 95°21'23.4" 27° 27'11.4" 03-01-2014 50.2 43.2 Residential standard as per CPCB Ambient Noise Level.  This location is categorized as residential area.  At this location it was observed that Bahadur 6 Na Pukhuri 95°23'49.4" 27° 26'10.5" 04-01-2014 58.2 52.7 Residential noise level exceeds the standard level Chariali mainly due to the vehicular movement on the road at a distance of 20m from the sampling point.  Noise level was observed within the Mankhuli 7 Na Pukhuri 95° 21' 8.9" 27° 26'16.7" 05-01-2014 50.1 39.4 Silence standard as per CPCB Ambient Noise Gaon Level.  Noise level was observed within the 8 Chariali T E Na Pukhuri 95° 22' 2.0" 27° 27' 3.9" 06-01-2014 52.6 44.1 Residential standard as per CPCB Ambient Noise Level.  It was observed that noise level is 9 Tingrai Na Pukhuri 95°21'26.7" 27° 26'44.1" 07-01-2014 58.2 45.6 Silence high both at day & night mainly due to

46

Day Time Night Time Sl. Location Longitude Latitude Monitor- Area Sub Station Noise NoiseLeq Remarks/Reasons No. Name (E) (N) ing Date Category Leq dB(A) dB(A) the vehicular movement on the road which is just 40m away from the sampling point. Ambient Noise Result of 33 kV & 11 kV Sub-Distribution lines of Jorhat District  The noise level exceeds the standard DebaguriPukh Residential/ 10 Cinnamara 94° 18' 9.2" 26° 40'43.6" 01-01-2014 58.7 44.5 limit at day time due to vehicular uria 2NO Silence movement.  Noise level was observed within the CinamaraBam Cinnamara 94°13'59.2" 26° 44'37.0" 02-01-2014 53.8 40.1 Residential standard as per CPCB Ambient 11 ungaon Noise Level.  Noise level was observed within the 12 Cinamara Cinnamara 94°13'49.4" 26° 43'41.6" 03-01-2014 52.2 44.5 Residential standard as per CPCB Ambient Noise Level. Ambient Noise Result of 33 kV & 11 kV Sub-Distribution lines of Golaghat District  Noise level was observed within the Kamarpatty Residential/ 13 Golghat-II 93°57'23.3" 26° 30'43.7" 8-01-2014 53.6 44.7 standard limit as per CPCB Ambient Ward No-2 Silence Noise Level.  Noise level was observed within the 14 Adhar Satra Golghat-II 93°55'03.1" 26°32'07.7" 9-01-2014 54.5 42.3 Residential standard limit as per CPCB Ambient Noise Level.

47

Annexure 5.2 Summary of Noise Level Results (For Substation)

Day Time Night Time Sl. Name of Longitude Latitude Monitor-ing Noise Leq Noise Leq Area Category Remarks/Reasons No. Sub Station (E) (N) Date dB(A) dB(A)  The noise level is within the standard 1 Dibrugarh-II 94°55'13.9" 27°25'16.8" 13-01-2014 56.8 52.3 Industrial/Residential prescribed CPCB limit both at day & night.  The noise level was little high than MVA Tinsukia-II 2 95°15'18.5" 27° 27'45.6" 09-01-2014 61.9 58.3 Residential the standard CPCB limit at both day (Panitola) & night time.  The noise level was little high than 3 Na Pukhuri 95°21'22.1" 27° 27'10.8" 02-01-2014 60.4 56.8 Residential the standard CPCB limit at both day & night time.  The noise level is within the standard 4 Panichokuwa 94°10'38.3" 26° 45'44.4" 4-01-2014 51.4 44.9 Residential/Silent prescribed CPCB limit both at day & night.  The noise level was slightly high than 5 Golaghat-II 93°57'13.0" 26°30'53.8" 7-01-2014 50.7 47.8 Residential the standard CPCB limit at night time.

48

Annexure – 6

Ambient Noise Standards Sl. Limits in dB* Category of Area/ Zone No. Day Time Night Time 1 Industrial Area 75 70 2 Commercial Area 65 55 3 Residential Area 55 45 4 Silence Zone 50 40

*The limit in dB denotes the time-weighted average of the level of sound in decibels on Scale A which is relatable to human hearing. *Day time duration is 6am to 10pm and Night time duration is 10 pm to 6 am. Source: Environment (Protection) Act, 1986 as amended in 2002.

49

ANNEXURE 7

AIR, WATER AND NOISE MONITORING LOCATION MAPS

50

Chapakhowa Map Showing Sampling Locations at Sub-Stations of Tranche-III Kerimgaon

Kundil Bazar Murkong Selek Sunpura

1:1,200,000 MIRI Kobo Jonai 025 50 100 150 Saikhoa Ghat Murkong Selek Dangori

Kilometers Laimakuri TEA GARDENS Talap Scale Dighaltarang E Dijmur Mohmaragaon DHEMAJI Dum Duma Oaklands Rangagora Sonarigaon Balijan TINSUKIA Sisi Bargaon Dinjan Dumsa Makum Duarmara Dibrugarh NH 37 Dhemaji Tinsukia Tingari ") ") Singpho Chaulkhoa Pathalipam MVA Tinsukia-II Na Pukhuri SS ") NH 52 ") Pengri DIBRUGARH (Panitola) SS Dardubi Road Digboi Pengeri SS Barbaru NH 38 Bardalani Dibrugarh-II SS Tengakhat

Siajali Gagaldubi Machkhoa Bamani Kora Likhapani ") Ledo TEA GARDENSBoginadi SS Cheuagaon Nahorkatiya ") Margherita Jaipur Diju Khowang Bhadoi-Pasali SS LAKHIMPUR TEA GARDENS North Lakhimpur Tinkhang Dhakuakhana Namrup ") Tengapania Dulahatgaon Moranhat Gumto Naoboicha SS Bachagaon Dinajan Barhat

Sepon Nij Lalulk Kekuri Bebejia Gejeragaon NORTHEAST FRONTIER RY. Kharkhat Sapekhau

Disangmukh Salaguri Bihpuria Abharpur Nagargaon Sonari Sibsagar Lakwa Majuli Iland Bordutighat SIBSAGAR Mathurapur Majuli Namdang Singhjan Nazira Simaluguri Seijusa ") Auniati Daflagarh SS Neamati Namtiali Charduar Gohpur Jhanzi Kheriabari Ratabar Ginjia Gohaingaon Rangapara Mijika NH 52 Ahataguri Saralpara Helem Kokilamukh Suparikhata UDALGURI Dhekiajuli Rd. Balipara Teok Amguri Majbat TEA GARENS Amtika Goibarigaon Behali Geleki Darranga Udalguri Pachmai TEA GARDENS ") Itakhola Jorhat TEA GARDENS NH 37 Deosri Harchurra SS Neghereting ") Cinnamara Kumrikhata Panichokuwa SS Nakachari Kunda Paneri Dhekiajuli SONITPUR Chutia ") ") Kumguri Jamuguri Dergaon Bhalukmara Haju Atharikhat Rowta ") Bindukari Dhansirimukh Amguri Bazar BAKSA Nalbari Orang Vishwanath Hathighar SS Cinnamora SS Rasmana Khoirabari Thelamara Bihuguri (Jorhat By-Pass) Tangla (Erabari) SS Bokakhat Numaligarh Mariani KOKRAJHAR Ranikhata Jagdala Tamulpur Kobirali Tezpur GOLAGHAT Agrong Singri Silgha JORHAT Kochugaon Patgaon CHIRANG Hudukhuta Hatikhuli NH 37 Rihabari TEA GARDENS Kaliagaon Kaupati Jakhalabandha Kaziranga Titabar NH 31 C Sidli Dhamdhama NH 39 Dalgaon Amguri Garubhasa Buri Khamar Barjhar TEA GARDENS Barjan Sarupeta Halrugaon Bijni Bongaigaon Patacharkuchi Kharupatia ") Dotma Misa Phangohogaon Sorbhog Dhing Kaliani Golaghat Basugaon Gmograpar Lengteng Golaghat-II SS Bhawanipur Patharughat DARRANG Dhing Bazar Juriagaon Sarhed Furkating Baruagaon Bhauraguri ") Mairabari Nalbari Rangia Mangaldoi Bar Dhoa Gossaigaon Raha Loch Salana Ghagrapar SS ") Rupohi Howli NH 52 Lahorighat Kokrajhar Salmara Bangaon NALBARI Mongoldoi Ind. Estate SS Samaguri Garampani Fakiragram ") Rangamati Jamuguri Abhayapuri Maroa Jengpata

North Salmara SS Sarthebari NH 31 Barpeta Dumnichauki Banmurigaon Nagaon Puranigudam Bijalighat Baihata Sapatgram BONGAIGAON Chapanalla Eradangkramsa Chapar MORIGAON Senchoa Tipkhi BARPETA KAMRUP ") Raja Mayang Baropujia ") Barpathar Marigaon Mikirgaon Chenghehishon Bilasipara Borka SS Deodhar SS Tarabari Aujari Raha NH 31B Hajo Kurua Dengaon Basbari Bagaribari Salkocha Jogighopa NH 37 KARBI ANGLOG Dili Terang Bagbor Amingaon Kalang NAGAON Goalpara Panikhati Tumpung Barlah ( SUBDIVISION) Chaparmukh Kathiatali NH 39 Rupsi Pandu NH 36 Longkamgaon Kharnauza Dharamtul Kampur Rengm Pathar ") Digaru Khetri Jagi Road Dalgoma Balagaon ") NH 31 ") ") Sonapur Naojan Balajan Chunari Palasbari Adabari SS Maudanga Balajan SS Agia Kahilipara Jatia SS Ulibani Dabaka Dambukso Naojan Golakanj Mornai Nagarbera ") Nakhola Gouripur (Nehru Stadium ) SS JamunamukhNorth East Frontier Ry (Sutargaon) Lakhipur GOALPARA Dharapur SS Bar Dambuk Laugrabhila Khutal Chhaygaon Ramgodam Baguliaghat Dhubri Krishnai Singinarigaon ") Tiplai ") Kaki Dhubri SS Bokajan Fakirganj Hekera(Jogipara) SS Hojai NH 36 Rangjuli NH 51 Dhupdhara Burakek DHUBRI Boko Umapani NH 37 Loharghat Chpistian Baitha Langso South Salmara Habaipur Howang Barduar Mynaro Lanka Manipur Road Lankapatti Dimapur Patakata Bhotpur KARBI ANGLONG Shedhumi Kseh Kynthang Paklanggaon Diphu (HAMREN SUBDIVISION) Hang Habai Sirtiso Lamsakhong

Lungding Baut Bazar Lumding Singimari Khlainduli Charkha Hai

Langku Hatikhali

Lungding Thaijuaria

Langting Garampani Langlut

Darangibra Labang Bagha NORTH CACHAR HILLS Derebara Mupa

Gunjong Maiboug

Malangpa Haflong Laisong Mahur Hungrum Haflong Hill Sherpar

Balarihan Bandarkhal Jalalpur Lanoong Damchara Kalsin

Kumbhir Dalu Barakhola Darpur Udarbard Karimganj Raja Bazar Bhanga ") Banskandi Lamajuar SS Mahakal Silchar ") Chirukandi (Rangpur) SS Lakhipur Nilambazar Silkuring Sonaimukh Legend : TEA GARDENS Bimakandi Construction Hailakandi CACHAR Palanghat Stage Sampling : Moragang Dwarband INTERNATIONAL BOUNDARY Pathakandi Dhalai Lala Lalaghat ") ") Sub Station Sampling Location Bhaga SS STATE BOUNDARY KARIMGANJ HAILAKANDI Dulladchara Katlichara DISTRICT BOUNDARY

Kukichara NATIONAL HIGHWAY PREPARED BY : Abdullapur En-Geo Consultancy & Research Centre (ENGECORC) Recognized By : Department of Space, Government of India

Chatachara ROAD [ISO 9001-2008 Certified] 71, Lamb Road, Ambari, Guwahati-781001 Hriphaw www.engecorc.com, e-mail: [email protected] RIVER Ph: 91-361-2545165, Fax: 91-361-2515536