Document of The World Bank Public Disclosure Authorized

Report No: 25705

IMPLEMENTATION COMPLETION REPORT (IDA-35630)

ON A

CREDIT Public Disclosure Authorized IN THE AMOUNT OF US$6 MILLION

TO THE UNION OF THE

COMOROS

FOR A

EMERGENCY ECONOMIC RECOVERY CREDIT Public Disclosure Authorized MAY 20, 2003

AFTP1 Africa Region Public Disclosure Authorized CURRENCY EQUIVALENTS (Exchange Rate Effective April 1, 2003) Currency Unit = Comorian Franc (KMF) KMF 1 = US$ 0.002183 US$ 1 = KMF F458

FISCAL YEAR July 1 June 30

ABBREVIATIONS AND ACRONYMS

CURE Crédit d'Urgence au Redressement Economique EERC Emergency Economic Recovery Credit ICR Implementation Completion Report GDP Gross Domestic Product HIPC Highly Indebted Poor Country IMF International Monteray Fund ISS Interim Support Strategy KMF Franc QAG Quality Assessment Group MOP Memorandum of the President MTR Mid Term Review N/A Not Applicable OAU Organization of African Unity OP Operational Policy PC Personal Computer PCD Project Concept Document PDO Project Development Objective PID Project Information Document PIU Project Implementation Unit PNAC Pharmacie Nationale Autonome des Comoros PRSP Poverty Reduction Strategy Paper PSR Project Status Report SMP Staff Monitored Program TF Trusd Fund USD/US$ United States Dollar

Vice President: Callisto Madavo Country Manager/Director: Hafez Ghanem Sector Manager/Director: Philippe Le Houerou Task Team Leader/Task Manager: Colin Scott

COMOROS Emergency Economic Recovery Credit

CONTENTS

Page No. 1. Project Data 1 2. Principal Performance Ratings 1 3. Assessment of Development Objective and Design, and of Quality at Entry 2 4. Achievement of Objective and Outputs 5 5. Major Factors Affecting Implementation and Outcome 8 6. Sustainability 8 7. Bank and Borrower Performance 9 8. Lessons Learned 10 9. Partner Comments 11 10. Additional Information 19 Annex 1. Key Performance Indicators/Log Frame Matrix 22 Annex 2. Project Costs and Financing 23 Annex 3. Economic Costs and Benefits 24 Annex 4. Bank Inputs 25 Annex 5. Ratings for Achievement of Objectives/Outputs of Components 26 Annex 6. Ratings of Bank and Borrower Performance 27 Annex 7. List of Supporting Documents 28 Annex 8. Expenditure Table 29

Project ID: P074054 Project Name: Comoros Emergency Economic Recovery Credit Team Leader: Wolfgang Fengler TL Unit: AFTP1 ICR Type: Core ICR Report Date: May 20, 2003

1. Project Data Name: Comoros Emergency Economic Recovery Credit L/C/TF Number: IDA-35630 Country/Department: COMOROS Region: Africa Regional Office Sector/subsector: Central government administration (100%) Theme: Conflict prevention and post-conflict reconstruction (P); Macroeconomic management (P); Decentralization (S); Other social protection and risk management (S)

KEY DATES Original Revised/Actual PCD: 05/09/2001 Effective: 09/18/2001 09/18/2001 Appraisal: 06/21/2001 MTR: Approval: 08/02/2001 Closing: 12/31/2002 12/31/2002

Borrower/Implementing Agency: GOVERNMENT/PLANNING COMMISSION Other Partners: None

STAFF Current At Appraisal Vice President: Callisto E. Madavo Callisto E. Madavo Country Director: Hafez M. H. Ghanem Hafez M. H. Ghanem Sector Manager: Philippe H. Le Houerou Cadman Atta Mills Team Leader at ICR: Wolfgang Fengler Christos Kostopoulos ICR Primary Author: Colin S. Scott; Vincent Da Cruz

2. Principal Performance Ratings

(HS=Highly Satisfactory, S=Satisfactory, U=Unsatisfactory, HL=Highly Likely, L=Likely, UN=Unlikely, HUN=Highly Unlikely, HU=Highly Unsatisfactory, H=High, SU=Substantial, M=Modest, N=Negligible) Outcome: S Sustainability: UN Institutional Development Impact: M Bank Performance: S Borrower Performance: S

QAG (if available) ICR Quality at Entry: S Project at Risk at Any Time: Yes 3. Assessment of Development Objective and Design, and of Quality at Entry 3.1 Original Objective: Country background: The Union of the Comoros comprises the three Comoros Islands that declared independence from France in 1975: Moheli, , and . The central government is located on Grande Comore. For many years, the situation in Comoros has been marked by poverty, poor governance and extreme political instability, including numerous coups and coup attempts. In 1997, conditions deteriorated further: military authorities in Anjouan, the poorest of the islands, attempted to secede and both the central government and the Organization of African Unity imposed a blockade, completely isolating the island. Differences over how to proceed sparked internal disputes on Anjouan, including outbreaks of violence, but negotiations and attempts to forcibly re-integrate Anjouan failed. This failure in turn increased tensions on the island of Grande Comore, leading to the overthrow of the central government by Colonel Azali Assoumane in March 1999.

Subsequently, negotiations made progress and, in February 2001, all parties signed a Framework Agreement for National Reconciliation in the town of . This agreement outlined a path to reunification and democratization of the country, including a transition period, a referendum on a new constitution, a government of national unity and finally elections in early 2002. Hopes that real change was possible were high, including among much of the World Bank country team.

In Comoros, per capita GDP has fallen throughout much of the past decade and now is below US$400. Social services delivery, never very good, deteriorated further during the secession, particularly in Anjouan. In 1998, the Bank suspended disbursements due to non-payment of arrears, but by January 2000, the new central government cleared arrears to the Bank, leading to the resumption of Bank disbursements and a review of the country’s portfolio.

World Bank strategy: In November 2000, the Bank adopted an Interim Support Strategy (ISS) with three scenarios: in case of renewed violence, the Bank would suspend its activities; if there was no change to the situation, the Bank would only carry out an infrastructure project, capacity building and assist the government to define a development vision; and in the high case scenario, the Bank would go ahead with an Emergency Recovery Credit, eventually leading to a PRSP and debt relief under HIPC. The high case would be triggered by (i) substantial progress in public management on all three islands, (ii) agreement on an integrated budget for the three islands, and (iii) evidence of Government transfers to, and Government expenditures in, Anjouan. This would imply tangible and decisive progress towards national reconciliation.

High case scenario: A Bank mission to the Comoros in March 2001, just after the Framework Agreement was signed, concluded that there had been sufficient progress to warrant the high case scenario. At an informal donors’ conference in July 2001, the government presented a US$12.8 million Emergency Reconstruction and National Reconciliation Program of which the Bank was to fund about half. The Bank’s country team showed strong support for the government’s reconciliation strategy and rapidly prepared a US$6 million Emergency Economic Recovery Credit (EERC) under OP 8.50. This credit was approved by the Board of Directors in August 2001. Six days later the local government in Anjouan was overthrown in a coup. The Bank sent a verification mission which concluded that the new authorities in Anjouan would continue to support the Framework Agreement and went ahead with the implementation of the credit.

EERC objectives: The Memorandum of the President states that the credit's main objective was to finance the critical transition out of the secessionist crisis. The credit would do this by supporting a government economic recovery program which intended to alleviate distress among the poor and support the process of national reconciliation. This corresponded to the view of the government that the secession was the result of poverty on the islands concerned. Therefore, in the government’s program, (i) a poverty-reduction component was to address the root causes of the conflict, (ii) a decentralization component was to pave the way for the outcome of the transition, allowing the country to function as three islands with largely autonomous governments, and (iii) a national reconciliation component was to pay for meetings, travel and seminars, thereby supporting the transition process itself. The MOP also

- 2 - states that credit was intended to signal that the international financial institutions were willing to help the Comoros and to leverage additional donor funding.

Consistency with strategies: The Emergency Recovery Credit was a central element of the Bank's Interim Support Strategy for the Comoros, which stated that there “can be no sustainable growth and poverty reduction in Comoros without a solution to the separatist crisis and a move to a broadly accepted government.” Its objectives complemented the Framework Agreement and corresponded to the government’s Policy for National Reconciliation. The Bank’s Interim Support Strategy was therefore “closely aligned with the objectives and sequencing of priorities of peace accords and rehabilitation plans agreed to by parties to the conflict” (OP 2.30 ‘Development Cooperation and Conflict’).

High risk: In practice, the credit was to allow the Bank to back a largely political transition process that seemed to offer the best chance in years to pull the country out of an ever-worsening crisis. Even though this process was supported by the military rulers and opposition of both Comoros and Anjouan, the Bank was well aware that investing in it meant taking a high risk. In particular, the outcome of the transition was far from clear and the track record of the Comoros was extremely poor. The risk that the national reconciliation process could stall or reverse was stated in the MOP. The only safeguard mentioned, however, was to ensure that all stakeholders confirmed their support for the reconciliation process before the project was formulated.

Choice of instrument: For this operation, the Bank chose an Emergency Credit under OP 8.50 and adapted it to the circumstances. The Comoros did not qualify for a credit under OP 8.60 and, as speed was crucial, the situation required a fast-disbursing instrument. Yet, in light of the track record of Comoros, and particularly Anjouan, the country team added controls to the standard requirements of OP 8.50. Disbursements were to be made in three installments, dependent on the achievement of key milestones in the transition and satisfactory financial management. External audits were to be carried out for both imports and programs and the government’s spending plan was binding, with changes in the allocation requiring no-objection from the Bank. Implementation was to follow World Bank procurement and disbursement guidelines as well as procedures to be established by the implementing agency. Drawing on the experience of Burundi, these measures were defined in a supplemental letter to the Development Credit Agreement. The Bank undertook to supervise the project closely.

Indicators: Emergency Recovery Loans under OP 8.50 are designed to finance only a positive list of imports identified as necessary to a well defined recovery program. In this case, it had been agreed that the proceeds of the credit would be used for projects and activities as listed in the government’s Emergency Reconstruction and National Reconciliation Program. The government’s program had no logical framework matrix and was largely defined by activities and outputs rather than outcomes. Assumptions about causal relationships between national reconciliation, decentralization, poverty reduction, secession, and the transition did not have to be articulated. The absence of targets and indicators in the government’s program made the evaluation of the outcomes much more difficult. However, this absence of indicators was a reflection of the limited information available at the stage of the project design and the result of the need to implement the program rapidly. Similarly, the credit documents do not state explicitly what would indicate that the transition was completed, although there was a general understanding that the objective would be achieved if the Framework Agreement was successfully implemented. With hindsight, the objectives should have been more specific.

3.2 Revised Objective: The objective was not revised.

- 3 - 3.3 Original Components: The credit’s MOP does not contain formal components. However, the borrower agreed with the Bank to use the Comoros EERC to finance: i) poverty reduction, ii) decentralization, and iii) national reconciliation, and the spending program was divided into these three components. For poverty reduction and decentralization, funds were allocated to specific projects which the borrower and authorities on the three islands had identified. In Anjouan, an ad hoc survey was undertaken to determine priorities. The Technical Annex and Supplemental Letter included a matrix (see Annex 2 Project cost and financing) defining how much money was to be spent for what kind of project on which island. Funds for national reconciliation were used at the central level.

Emergency program components not financed by the EERC: In the government’s Emergency Reconstruction and National Reconciliation Program, "national reconciliation" also included the reinsertion of young militia in Anjouan (financed by a Bank Post-Conflict Grant) and elections (financed by the European Union). A fourth component, "Economic Recovery and Financial Stabilization" covered payment of domestic arrears, wages and voluntary separation expenditures, which were to be financed by other donors. The government’s program therefore offered a comprehensive package of measures to assist the transition out of the crisis.

Spending plan: Beyond the allocation to components and islands, the MOP does not state what the funds are to be spent on. Details are contained in the Letter of Policy for National Reconciliation, which proposes the government’s action plan to the donors. Given the sensitivity of fund allocation to the different islands, establishing how much was to be spent on each island before disbursement was an important factor for successful implementation. The spending plan was said to be binding for the borrower and any changes were subject to no-objection by the Bank. In practice, this left considerable flexibility, particularly as assumptions about how the activities would further the objectives were not made explicit. This design constituted an additional risk and therefore depended to a considerable extent on an unwritten agreement between the Bank and the borrower. Issues related to this risk were discussed within the Bank, and the prevailing view was that, on the basis of the recent track record, the borrower could implement this satisfactorily.

Distress among the poor (first component, 50% of credit funds) was to be alleviated through the rehabilitation and equipment of schools and hospitals, through water and rural development projects. The institutional transition to a decentralized state (second component, 30% of credit funds) was to be assisted by constructing and rehabilitating administrative buildings and re-allocating or training civil servants. Assistance in carrying out the technical dimensions of the reconciliation process (third component, 15% of credit funds) covered unspecified activities of the commission charged with implementing the Framework Agreement and the establishing of a new fiscal structure. For this component, flexibility was an important feature as it could not be predicted with certainty what kind of actions it was going to take to attain the overall objective of assisting the transition process. The project implementation unit’s running cost (another 5% of credit funds) as well as further support of the implementing partner were also officially budgeted under the heading of reconciliation.

Implementing Agency: For the implementation of the activities to be financed by the credit, the government was to create a project implementation unit coordinated by the Director General for Planning. The General Directorate for Planning (later renamed Planning Commission) reports directly to the President. Two sub-committees consisting of representatives from ministries and other government agencies were responsible for mobilization and control of funds and implementation respectively. A sub-unit replicating this structure was to be set up on the island of Anjouan in order to implement projects there. This decentralization reflected the large number of activities to be carried out in Anjouan and took into account the fact that the administration of Anjouan was de facto operating independently from the central government. Both units were to be audited by internal and external auditors.

- 4 - 3.4 Revised Components: The credit’s MOP does not contain formal components. In the government’s spending program, funds were re-allocated between the components and to other activities with the no-objection of the Bank. These re-allocations were notably to respond to overcome obstacles in the privatization of the port and to make up for delays in other donors’ fulfilling their commitments on financing civil servants’ salary arrears.

3.5 Quality at Entry: No Quality at Entry rating was carried out by the Quality Assurance Group. This ICR found the following features of the credit unsatisfactory: the spending program’s emphasis on activities rather than outcomes, the absence of indicators to measure how much progress has been made and the fact that assumptions about how the activities were to serve the general objective were generally not made explicit. Different aspects of the transition - its "technical dimensions", implementation of the Framework Agreement, reunification, agreement on a joint budget and national reconciliation - were not clearly distinguished and their relationship not spelt out. These shortcomings lead to different interpretations of the overall objective and, particularly on the part of the government, to unrealistic expectations of the role the credit would play in fostering reconciliation.

Satisfactory were: the overall objective and rationale as stated in the MOP, the rapid response of the credit to an urgent need (very satisfactory), the high level of government input into the planning and design of the activities to be carried out, and the appropriate flexibility of design with additional controls for a high-risk post-conflict transition. Bearing in mind the time constraints and trade-offs and that the chosen instrument had to be tailored to the specific situation of Comoros, the overall Quality at Entry is rated marginally satisfactory.

4. Achievement of Objective and Outputs 4.1 Outcome/achievement of objective: State of the transition: The uses to which the counterpart funds have been put have produced largely positive results. In terms of the transition, however, the outcome is mixed. At the closure of the credit in December 2002 and at the time of writing of the ICR, in March 2003, the transition process, as envisaged by the Framework Agreement, had not been completed. On the one hand, considerable progress had been made: the constitution had been adopted in a referendum, and presidents had been elected for the Union and for each of the three islands. Anjouan, the principal focus of the EERC, was peaceful, had overcome its isolation, and was once again participating in the federation. These outcomes, to which the credit contributed, are substantial successes. On the other hand, new lines of confrontation between the four entities in the Comoros had emerged, particularly between the newly formed government of Grande Comore and the central government located on the same island. Specific responsibilities of the four governments remained a point of contention and much of how the new federal country will work remained to be determined, let alone implemented. Whether the institutional situation of the Comoros is better today than two years ago is debatable, but it is certain that the secessionist crisis has not been overcome. Not only is the implementation of the Framework Agreement not complete, but it has also become apparent that a full transition will require more than the implementation of that agreement.

Achievement of EERC objective: The credit’s stated objective - financing the critical transition out of the secessionist crisis - has only been partially achieved. The project had a positive impact on poverty and it supported the transition for as long as it lasted. Nevertheless, in light of the state of political instability at the close of the credit, the ICR could not rate the outcome higher than marginally satisfactory. Even so, the political situation may still be resolved and the project may yet prove to have been an important contributing factor.

4.2 Outputs by components: Financing the transition: Through its three components, the credit successfully provided means and incentives to move forward with the transition process. It was also central to the Bank’s dialogue with the

- 5 - Comorian governments and used in creative ways to overcome obstacles that had not been anticipated. As intended, the impact was particularly strong in Anjouan, where the poverty reduction component was able to address urgent problems that had arisen during years of isolation. The achievements financed by the credit gave considerable support to the view the island had something to gain from re-engaging with the central government and thereby helped the passing of the new constitution in a referendum. Most of the benefits of the decentralization component are not yet visible, as the major activities involve construction that is as yet unfinished. For the national reconciliation component, results are less tangible, but by helping to finance meetings and studies for the commission and committee charged with implementing the transition, the credit generally helped to move the process forward.

In the absence of indicators, the contribution of the activities financed by the credit to poverty reduction, decentralization or national reconciliation cannot be quantified here. The following paragraphs highlight the main outputs. An overview of the large number of separate activities can be seen in the expenditure table in Annex 8. In general terms, although some of the activities funded seem somewhat removed from the objectives of the project, the vast majority have produced useful outputs and also had an intrinsic value through confidence building.

Poverty reduction: Poverty reduction is not just subservient to the political transition but an important objective in its own right. Of the credit’s funds, 47% were allocated to this component and have achieved substantial successes. The spending program contained projects in four sectors: health, education, water, and rural development, the latter including a project for the safety of fishermen. Almost all the projects have been completed as planned. Half the poverty reduction funds were allocated to the island of Anjouan, where most projects have been completed rapidly and with high visibility. More than 900 people were employed on the island in the process. A rapid survey conducted by the implementing partner in Anjouan covered 0,5% of the adult population. It claims that almost half the respondents had heard of the project, just over ten percent said the implementing partner responded to their needs and almost a quarter saw work being carried out in their village. Out of the latter, over a third said they had been consulted on the project and over 90% expressed their satisfaction with the work.

Most of the poverty reduction funds were spent in the health sector (39%), with the purchase of medicine and medical gas, medical equipment, ambulances, the rehabilitation of hospitals and setting up a cholera camp during an epidemic. Much of this has been completed and is operational in the respective hospitals. The positive impact of this is evident: ambulances reduce delays in attending emergencies; new dentistry, ultra-sound and surgical equipment reduces the need to travel between islands for check-ups and treatment. In the education sector (28%), schools were built or rehabilitated and equipment purchased on the island of Anjouan, and again, the improvement of learning conditions is obvious. Much-needed teacher training, however, does not seem to have taken place. One major project (12% of total poverty reduction expenditures) to supply water to 17 villages on Grande Comore is still being completed, suffering from serious delays. On Anjouan a multitude of small infrastructure projects covering canalization and minor road works have been completed (7.5% of total poverty reduction expenditures). Also under the heading of rural development, a project on all three islands that intends to reduce the losses of fishermen at sea has been financed (12%). Unfortunately, rather than buying rescue boats, the funds were largely used to set up sophisticated communication facilities which are likely to become redundant once a mobile phone network is operational. Ratings for individual projects would seem to cover the whole range from very satisfactory to unsatisfactory and would require the definition of indicators and a beneficiary evaluation. On the basis of available information the poverty reduction component appears satisfactory overall.

Decentralization: The funds of this component (18% of the credit’s funds) were mostly intended for the construction and rehabilitation of public buildings, to finance redeployment of civil servants to Anjouan and training for civil servants on Grande Comore. The largest single project (42% of the decentralization expenditures) is the construction of an office complex for the administration of Moheli, which in December 2002 was yet to start. A similar amount has been invested in the building, rehabilitation and equipment of four administrative buildings on Anjouan, where work is still ongoing. Much of the rest of decentralization funds (13%) was used by the island governments to buy vehicles (eight in total) for their administrations. As much of the major work is still being completed, rating this component would be

- 6 - premature. Given the prevalence of cars among the outputs produced so far, the decentralization component is unsatisfactory at this stage.

National reconciliation: The funds for national reconciliation (4% of the credit) supported the Committee and Commission responsible for the implementation of the Framework Agreement. These played a central role in the transition process when it was on track, and the credit helped both overcome financial obstacles and provided technical assistance in line with its objective. Because part of the budget was earmarked for their activities, Committee and Commission wanted the amount to be simply disbursed to them. However, the implementing agency kept control over the funds, initially paying them out against running costs and expenses, later only against specific outcomes, such as technical assistance on the distribution of public property and the establishment of a joint budget. Despite the progress and achievements in the area of national reconciliation, given that the transition has not been completed, this component cannot be rated higher than marginally unsatisfactory.

The running costs of the Project Management Unit (4% of the total credit funds), including audits, were formally included under the heading of national reconciliation, which also covered support to the planning commission of which the PIU was part (5% of the total credit funds). This included salaries of staff contracted for the project, rehabilitation of offices on the three islands and the purchase of vehicles and equipment. Rating: satisfactory.

Civil service salary arrears: Payment of civil service salary arrears was part of the government’s recovery program, but belonged to a component that other donors were to finance. Following delays in the release of those funds, the Bank agreed to 10% of the total credit fund’s being used for this purpose. Rating: satisfactory.

Port privatization: In order to assist privatization, and with agreement of the Bank, the implementing partner set another 10% of the credit’s funds aside to compensate port workers of the state maritime transport company. These funds came out of the national reconciliation and poverty reduction budgets and were a crucial factor in the successful privatization of the main port on Grande Comore. At the time of writing, the privatization of the port in Anjouan was still object of dispute so that funds for port workers there have not been disbursed there yet. Rating: satisfactory.

Economic recovery: According to IMF data, the EERC was one of the main reasons why real GDP growth increased from -1.1 percent in 2000 to 1.9 percent in 2001 (the lifting of the embargo on Anjouan and favorable export prices being the other important factors) and remained at an estimated 2.5 percent in 2002. The contribution of the EERC was mainly through increased commercial activity and construction. Rating: satisfactory.

Other donors: As intended, the engagement of the Bank did send a clear signal that it is willing to support the transition process in the Comoros. Other donors did contribute to the government’s Emergency Reconstruction and National Reconciliation Program but the credit did not succeed in leveraging the additional donor funding it intended. Rating: marginally unsatisfactory.

4.3 Net Present Value/Economic rate of return: With the exception of minimal cost recovery at hospitals and clinics, the investments of this project do not produce revenue that could be used to quantify the economic rate of return. No data is available on the development of such revenues. As an indication of efficiency, the auditors have found prices paid for goods and services reasonable and costs were comparable to those in similar conflict affected countries. The project implementation unit’s running costs represented 4% of the credit’s funds and an additional 5% of the credit’s funds spent on investments in the Planning Commission cross-subsidized the PIU to some extent. This is justified, given the multitude of projects and the high speed at which they were completed. The efficiency of the use of resources is rated satisfactory.

4.4 Financial rate of return: N/A

- 7 - 4.5 Institutional development impact: The credit did not include an explicit institutional development objective. Nevertheless the experience of implementing a credit of this type which gives a large amount of autonomy to the implementing agency has had a modest capacity-building effect, particularly for island authorities which have not previously implemented projects of this type. The Planning Commission, to which the project implementation unit belongs, has become one of the few institutions of Comoros that effectively function in a deconcentrated way. Rating: satisfactory.

5. Major Factors Affecting Implementation and Outcome 5.1 Factors outside the control of government or implementing agency: No major exogenous factors affected the credit’s implementation. Occasional delays in contracting and procurement, disagreements between authorities and beneficiaries, and bad weather meant that some of the deadlines, implementing partners set for their projects, were not met.

5.2 Factors generally subject to government control: The major factor affecting implementation and leading to the limited attainment of its objective in supporting the transition was ongoing political instability and disagreements between the central and island governments. Although difficulties had been anticipated, it is clear that an emergency credit alone cannot assist a transition process if the parties involved have no shared or compatible vision of where the transition is to lead to.

In addition to that, several governments have pressed for re-allocation of funds to items for which the emergency recovery program was not intended.

5.3 Factors generally subject to implementing agency control: The implementing agency drafted and implemented its own procurement guidelines, but these were only formally approved by the Bank in December 2002. In a charged political atmosphere, differences between islands at times created tensions between the central and Anjouan project implementation units. Whereas it occasionally required Bank intervention to resolve the issues, such tensions did not have a negative impact on project implementation.

5.4 Costs and financing: There were no delays in disbursements. Due to exchange rate fluctuations between the US dollar and the Comorian Franc, commitments exceed available funds by 3%.

6. Sustainability 6.1 Rationale for sustainability rating: Sustainability of a project in the context of a conflict-affected country is likely to take a different form that in a conventional development project. Since the objective is supporting the transition, it is the confidence and trust built through the project with its contribution to the sustainability of peace which counts. Many of the interventions were never intended to be orthodox sustainable development. Others may prove sustainable in the conventional sense. Most of the investments under the poverty reduction and decentralization components were in buildings and equipment, which have been or will be taken over by the relevant sections of the public administration. Where ownership for these is high, it is generally very likely that their integration will not pose any particular problems. Some specific investments will probably soon be at risk: one potential difficulty is that the continued availability of trained operators for some of the medical equipment is not guaranteed. Even more importantly, declarations of intent that particular attention will be paid to maintenance will need to be translated into practice, which for some of the more sophisticated equipment will require capacity-building and technical assistance. Maintenance has been a very weak point in the Comoros in the past and much equipment has been lost due to neglect.

- 8 - The most crucial factor affecting the progress towards the objective of assisting the country out of the secessionist crisis, however, will be political instability. Whereas there has been no renewed violence and all parties continue to declare their commitment to the reconciliation process, confrontations between political leaders over the control of resources and institutions continue. The achievements of this project in terms of confidence-building are by their nature fragile and could easily be undone for political calculations. As much as one would hope that the credit will have made a lasting contribution to the country’s transition towards a sustainable institutional arrangement acceptable to all parties, at this stage, given the current political situation, this seems unlikely.

6.2 Transition arrangement to regular operations: The Emergency Economic Recovery Credit was designed as a one-off operation, and no follow-up of this type is planned. Buildings and equipment are being or will be managed by the relevant island administrations and ministries. As the Emergency Credit was essentially implemented by permanent staff of the planning commission, these will be able to continue monitoring the ongoing activities even after the closure of the project.

7. Bank and Borrower Performance Bank 7.1 Lending: Despite a very uncertain environment, the Bank task team showed responsiveness to clients’ need in rapidly formulating a relatively simple, quick-disbursing operation aimed at supporting the transition. The team pre-appraised the credit in March/April 2001, negotiations took place in July 2001 and the first installment was disbursed in September 2001, undoubtedly providing a contribution to the ongoing stabilization efforts. The team took relevant experience for this type of credit into account and included more control mechanisms than usual into the design. While recognizing that some quality was lost due to the time pressure for the preparation of the credit, Bank performance at the lending stage is rated satisfactory.

7.2 Supervision: The Bank maintained a close dialogue with the authorities in order to deal with difficulties of the transition process that affected the implementation. In fact, throughout the credit’s lifetime, different aspects of the implementation became blocked and required interventions from Bank staff. As the Bank has no office in the Comoros, four supervision missions were undertaken for this purpose within less than a year. These missions always included Anjouan and on two occasions Moheli. Bank staff invested much time and energy in the project, building a good working relationship with borrower and the implementing partners. Their responses to the changing demands of the transition showed flexibility and were, with the exception of the approval of the procedures manual, timely. PSR ratings, based on achievement of the transition’s milestones and on the financial management of the project, were carried out in January 2002, May 2002 and February 2003 and were reasonable, except that the May ratings for national reconciliation and risks now seem optimistic in view of the breakdown of the transition process in July 2002. The supervision is rated highly satisfactory.

7.3 Overall Bank performance: The emergency credit was implemented under the high case scenario of the Bank’s Interim Support Strategy and all disbursements were made when the underlying assumption that the reconciliation was on track was justified. In the middle of 2002 the situation deteriorated rapidly, leaving the emergency credit without a formal strategic framework. Since then, the country team has been in the process of updating its strategy to reflect the difficulty of the current situation in the Comoros. The overall performance of the Bank is rated satisfactory.

Borrower 7.4 Preparation: There was close co-operation between the Bank and the Borrower in designing the project and the relevant ministries and agencies were consulted. The government showed a high commitment to the

- 9 - project and took the lead in allocating the funds to its poverty reduction priorities. The major shortcoming was that the government’s emergency recovery program did not make explicit how the activities to be financed would contribute to the overall objective and did not include any indicators to measure its success. The Borrower’s performance in the credit’s preparation is rated satisfactory.

7.5 Government implementation performance: The central government appointed its Planning Commission as the implementing agency. The central government and island governments generally gave good support to the projects funded by the credit but have been unable to complete the transition and stalled the reconciliation process between them. As mentioned above, several governments pressed for re-allocation of funds to items for which the emergency recovery program was not intended, particularly vehicles. Rating: unsatisfactory.

7.6 Implementing Agency: The set-up of having the Central Planning Commission implement projects on Grande Comore, Moheli and at the central level and the Anjouan Planning Commission implementing those on Anjouan worked well for the implementation, despite some communication problems between the two commissions. Projects were implemented effectively and efficiently, and much faster than any previous Bank projects. Despite the complexity of the project, the implementing partner was able to effectively absorb disbursements at a rate of US$400,000 a month. Both commissions were capable, highly committed and worked hard for the success of the credit. No formal reporting was instituted, but the commissions produced reports for visiting supervision missions, including expenditure tables. Two internal and the first of two external audits have concluded that financial management has generally followed the agreed terms and that checks and procedures of the project management were acceptable. However, a World Bank procurement expert who was part of the December 2002 mission has expressed serious reservations on the procurement of several items which are yet to be discussed. On the assumption that these questions will be resolved, the implementing partner’s performance is rated satisfactory.

7.7 Overall Borrower performance: Bearing in mind the reservation expressed above, the overall borrower performance is rated satisfactory.

8. Lessons Learned 8.1 Lessons for the ICR process: 1. The standard ICR format, its timing and assumptions may not be best suited to an emergency project of this nature. It may be too soon to judge the outcome of this EERC since a peaceful transition may still emerge from the current crisis. Sustainability in particular takes on a different meaning in this context. Given the trade-offs made in this kind of project, orthodox assessments may not be useful or fair. 2. In the changeable context, the process of generating and drafting the ICR has been as valuable as the final report, bringing increased attention on the Bank’s strategy and future interventions.

8.2 Lessons for Comoros: 1. In the Comoros there is still no shared understanding of what the political transition out of the crisis and national reconciliation mean in practice. Reaching such an understanding is an important pre-requisite for moving these processes forward, which is ultimately dependent on political will. 2. The EERC has shown that service delivery and infrastructure investments can be carried out effectively even in the difficult context of the Comoros, as long as the implementation and governance of the credit meet the highest level of standards. 3. The EERC emphasized the need for improved communications between development agents on the different islands of the country. It is also desirable for them to make greater efforts to resolve problems internally before they are brought to the attention of the donor.

- 10 - 8.3 Lessons for the Bank:

1. A credit of this kind involves a number of trade-offs. Above all it promises high gain but is entered at high risk. It implies managing tensions between speed and quality both at entry and in supervision. It means mobilizing development instruments in a highly political context over which the Bank has limited control. 2. Credits do not operate in isolation. Particularly in volatile strategic contexts such as that of the Comoros, the relationship between the Bank’s operations and the Bank’s country strategy needs to be continuously monitored and evaluated. 3. This operation shows the need for an instrument allowing rapid and flexible disbursement of funds, while maintaining some control over the way the funds are spent. OP 8.50 was used to cover both, but in order to do so, Bank staff had to make a number of compromises. Formally shifting the emphasis of control from import receipts to actual expenditure of counterpart funds would reduce unnecessary bureaucracy and allow project documents to deal more immediately with actual objectives and expected outcomes. 4. More specifically, where a credit is linked to an emergency recovery program, it is important that it is made explicit how and to what extent the activities are expected to contribute to the overall objective and that suitable indicators and procedures are defined. The development objective, in particular, needs to be precise and its implications clear to all concerned. Even where not formally required, a logical framework matrix and an operational manual would be one way of ensuring that everybody shares the same understanding of the project, its objectives and what success would mean. 5. A complex and flexible project of this type carried out in a volatile political environment requires regular supervision and attention. It therefore comes at a heavy price in variable costs to the Bank, particularly if managed from a distance.

9. Partner Comments (a) Borrower/implementing agency: 9.1 Introduction

In 1997, the secession of the island of Anjouan and the ensuing separatist crisis plunged the Comoros into political turmoil.

For nearly three years, the situation in Anjouan was difficult, characterized by repeated internal clashes among opposing separatist groups, and compounded by an economic embargo imposed by the international community. This situation seriously destabilized the island's fragile economy and was partly responsible for the deterioration of its inhabitants' already difficult living conditions.

The calamitous consequences of that crisis impacted on the other two islands of the Islamic Federal Republic of the Comoros, Grande Comore and Moheli.

Political efforts to end the secessionist crisis led to the signature of a Framework Agreement for National Reconciliation on February 17, 2001 by the Government, the Anjouanese authorities, the opposition and civil society. That agreement provided for the formation of a New Comorian Grouping comprising all the islands of the archipelago, decentralization and a transition period to enable the country to prepare for the establishment of the new institutions.

But effective resolution of the crisis required measures in support of economic recovery, rehabilitation and the reconstruction of the social sectors.

The Comorian Government accordingly drew up a Reconstruction and National Reconciliation Program (RNRP) comprising four main components: poverty reduction, national reconciliation, decentralization and good governance.

- 11 - That program, designed by the Planning Commission (formerly the General Directorate for Planning), was very ambitious. It addressed almost all the urgent needs identified by the islands and by the sectors of activity to effectively end the crisis and restore social, economic and political stability to the country.

It was a short-term development program, estimated at approximately US$56 million.

The RNRP was used to draw up the Government's Letter of Policy for National Reconciliation submitted to the "Friends of the Comoros" conference held in Paris in July 2001 under the aegis of the World Bank.

Through that conference, the Government hoped to obtain special support from partners, friends of the Comoros, for its efforts to secure national reconciliation, establish new institutions and reduce poverty during the transition period.

The emergency program for which funding was sought amounted to US$12.8 million, including $800,000 for the social and vocational rehabilitation of young militiamen in Anjouan that were obtained as a post-conflict donation from the World Bank.

One of the commitments made by the "Friends of the Comoros" at the Paris conference concerned an Emergency Economic Recovery Credit (EERC) Agreement in the amount of US$6 million, which was signed by the World Bank and the Government in September 2001.

The EERC credit was awarded to finance the import of raw materials and capital goods. Counterpart funds generated were to be used to finance, in particular, three of the four components of the Government's emergency program, namely poverty reduction, decentralization and national reconciliation.

The EERC was overseen by a funds management body, the Emergency Credit Implementation Unit, which was set up to monitor disbursements and audit activities at the national and island levels. The unit was chaired by the Planning Commissioner, who was responsible for coordinating all EERC implementation activities, reporting to the Government and to development partners, signing all correspondence and authorizing expenditure. In addition to the Planning Commission, which was responsible for the Unit's coordination, EERC-financed sectors of activity and Anjouanese stakeholders were represented in the Unit. For the purposes of fund-raising and financial oversight, the Unit was enlarged to include representatives from the financial sector. Given the particular status of Anjouan at the start of the project, one internal organization was admitted to participate specifically on that island's behalf. An EERC implementation committee was set up to facilitate project execution on the island. That committee's membership was the same as that of the EERC Implementation Unit, but it had wider powers.

The Chairman of the EERC Implementation Unit was assisted in project coordination tasks by two permanent management sub-units, one national, based at Moroni, and the other accountable to an internal organization in Anjouan. The sub-units basically consisted of two senior accountants, one in Moroni and the other in Anjouan, who worked closely with two technical coordinators acting as technical assistants to the Chairman of the Unit. Each EERC management sub-unit was responsible for daily funds management, keeping the accounts used to substantiate the utilization of funds, and providing auditors with all the documents needed to draw up the necessary audit reports.

In view of the EERC's emergency character, special disbursement provisions, waiving the procedures usually applicable to World Bank funds, were authorized to ensure that operations were conducted efficiently.

The purpose of this EERC Final Report is to evaluate credit implementation by analyzing achievements against the established objectives. The analysis will make it possible to evaluate the performance of national and donor management teams and of oversight teams, with particular emphasis on the lessons to be learned.

- 12 - This report is in two main parts: the first focuses on EERC objectives and achievements, while the second attempts to assess and review EERC implementation.

9.2 EERC objectives and achievements

Restatement of EERC objectives

The main EERC objective was to support the national reconciliation process initiated in the Comoros in 2001 while laying the foundations for economic recovery and a post-transition reconstruction program. The EERC was accordingly designed to finance three priority areas: poverty reduction, decentralization and national reconciliation.

In the area of poverty reduction, the objective of the emergency credit was to improve the living conditions of the poorest inhabitants, namely the rural population, by taking high-profile action to address that population group's priorities. The activities targeted the health, education, water and rural development sectors. Funds were distributed among the three Comorian islands on the basis of the criteria of population size and poverty incidence. US$3 million, i.e., 50 percent of the EERC, were earmarked for the poverty reduction component, with 50 percent allocated to Anjouan, 40 percent to Grande Comore and 10 percent to Moheli.

In the area of decentralization, the specific objective pursued was balanced investment in administration. Funds were allocated for public service activities and the rehabilitation, construction and equipment of administrative buildings, depending on the institutional needs identified by each island in conformity with the principles of administrative and economic decentralization practiced by the Comorian State. US$1.8 million, i.e., 30 percent of the EERC, were earmarked for the decentralization component, with 50 percent allocated to Anjouan, 33 percent to Moheli and 17 percent to Grande Comore.

In the area of national reconciliation, the objectives were to provide financial support for the activities of the two bodies involved in the process, the Monitoring Committee and the Tripartite Commission; support the units responsible for drawing up the budget; ensure efficient and transparent EERC management; and provide institutional backstopping for the Planning Commission, which coordinates the Reconstruction and National Reconciliation Program for the three islands and activities financed from external resources mobilized by the Government. US$1.2 million, i.e., 20 percent of the EERC, were earmarked for the national reconciliation component, with 42 percent allocated to transition bodies, 33 percent to management, expenditure monitoring and budget support, and 25 percent to support for planning.

Evaluation of activities carried out set against initial objectives (EERC impact)

To attain the three specific emergency credit objectives restated above, activities were defined and carried out on the three islands and on behalf of the Union (see the annexed "Expenditure Table"). An analysis of the results obtained in each area will be used to measure the impact of achievements in relation to each objective pursued and the links between the various objectives.

EERC poverty reduction results

Various EERC impact assessments among recipients of funds have shown that the poverty reduction activities financed helped considerably to improve the living conditions of the target population groups by rehabilitating and rebuilding social sectors, financing revenue-generating activities (RGAs), and creating jobs in businesses.

In the health sector, activities financed on all three islands helped to enhance access to health care services, improve their quality and lower the cost of basic medicines (see the report of the country’s drug procurement agency, Pharmacie Nationale Autonome des Comores, PNAC). The improvement of the

- 13 - existing infrastructure and technical capability of hospitals resulted in better patient care and treatment of diseases, especially in emergency cases such as the January 2002 cholera epidemic. EERC funds were also used for initial and further training of medical and paramedical personnel, to ensure that they are capable of using the tools now available to meet healthcare expectations.

In the education sector, the activities carried out made it possible to rehabilitate run-down schools, equip some regions that had not received funding under the Education III project (financed by IDA) with the education facilities required for the children's education, and provide educational materials and school supplies to all pupils.

In the sanitation and water supply sector, on the one hand the EERC was used to fund major projects that have opened up a number of remote villages in Anjouan to facilitate the movement of goods and persons and, on the other hand, the investments have helped to solve the problems of access to drinking water in the Mbadjini Ouest region of Grande Comore, which will probably lead to a reduction in the disastrous consequences of water shortages on health conditions and a resumption of agricultural activities in that region.

In the rural development sector, the activities funded played a part in reducing the extensive use of firewood by the population and in regenerating the Anjouanese forest, thereby improving the protection of the environment in which Comorians live. Action to develop RGAs was taken in order to create jobs for people there in search of means to meet their daily needs. The most important project funded in the rural development sector concerned the safety of fishermen at sea. The purchase and installation of fixed maritime communication facilities on the three islands and the provision of VHF and GPS wireless sets to fishermen will enable the authorities to locate fishermen lost at sea, thus ensuring minimum safety for the profession and reducing the high loss of life in this population category each year.

All the above poverty reduction activities contribute implicitly to the attainment of the broader objective of national reconciliation in that they meet the most urgent social needs, which is proof of the State's determination to resolve major problems facing the population. The socioeconomic difficulties that beset the most vulnerable sections of Comorian society no doubt did much to fuel the secessionist crisis. Consequently, a prerequisite for resolving the crisis is to address the population's priority needs.

EERC decentralization results

In the area of decentralization, EERC provided support for decentralized institutional bodies in order to set up a viable administration for each island and to deconcentrate centralized services in Moroni. Measures were taken to provide Anjouan and Moheli, the islands that were institutionally less developed, with the necessary means (buildings and equipment) to allow the new bodies to function.

The activities financed helped to solve some of the operational problems of the new autonomous administrations. The new administrative bodies already set up in the islands (the president's office and the ministries) were provided with vehicles, computer hardware and other equipment needed to enable them to serve the public. Such equipment, almost non-existent in Moheli in 2001, is already allowing the island to reorganize its administration and make it operational. On Anjouan, where the material available in 1996, before the crisis, has been destroyed or damaged, the EERC was used to rebuild and strengthen the administration of the island. Given that the participation of civil servants in the decentralization process is crucial to its implementation, it was important for the Government to find the means to ease the crisis for this category of the population (whose salaries had not been paid for 24 months) in order to rebuild the confidence that they had lost in the State. EERC funds were therefore used to cover one month of the unpaid salaries of all civil servants, including those in Anjouan, and this has had a positive effect on their attitude toward the Administration, which thus became more operational.

Like activities under the poverty reduction component, decentralization activities furthered the attainment of the national reconciliation objective in that they enabled the other two islands to narrow a gap that seemed to make them lag behind Grande Comore, while allowing the State to set up the necessary

- 14 - infrastructure for a decentralized administration on all three islands, which had been at the heart of the separatist movement's claims. It has indeed been noted that the idea that all decisions were taken in Moroni (capital of Grande Comore) and that all action was staged there was resented by the inhabitants of the other islands, especially Anjouan, and constituted one of the deeper causes of the Anjouanese crisis. Moreover, the Framework Agreement for National Reconciliation rests on the principles of power sharing, which should result in the exercise of power not only at the center but also in the islands in accordance with the planned sharing of responsibilities.

EERC national reconciliation results

EERC-funded activities carried out on the three islands did indeed contribute to poverty reduction and decentralization, which had a positive impact on national reconciliation and permitted the attainment of part of the main EERC objective, set out in the Letter of Policy, namely, "to support the Comorian authorities' efforts to meet short-term needs." However, the other part of that objective, which was to lay "the foundations for a broad recovery and a post-transition reconstruction program," could not be attained without financing for transition costs.

Progress towards the post-transition period, which must be the hallmark of national reconciliation, implies that certain priority activities, which cannot be devolved to the islands and are indispensable for the islands and the Union, must be carried out by the Monitoring Committee and the Tripartite Commissions, the departments responsible for the budget and the civil service, and the Planning Commission.

Owing to the support that was provided to the transition bodies, i.e., the Monitoring Committee and the Tripartite Commissions, it was possible to draw up a draft constitution of the Union of the Comoros, disseminate the draft constitution within the population, organize a referendum on December 23, 2001 on the adoption of that basic law, and organize and validate the election of the officials to the executive of the Union and the islands. As a result of these transition bodies' work, technical committees were set up to draft institutional bills on the sharing of responsibilities and decentralization and national property was inventoried and appraised. The Monitoring Committee and Tripartite Commissions took action to collect firearms in Anjouan, so that the Bank-funded rehabilitation project for young people could begin.

EERC funds were used to take a census of civil servants in Anjouan by a national technical team supported by an international consultant, the design of a computerized personnel-management system and the creation of budget management tools, especially for the islands. On completion of this work, civil service regulations for the new institutions should be available and issues relating to the necessary redistribution of civil servants for the decentralized system should be resolved.

EERC has provided institutional support for the Planning Commission and its liaison services in the three islands, namely the General Planning Offices. Since State resources are too limited to meet the operational requirements of the Comorian administrations, EERC funds were used as a contribution to the financing of the full operation of this body during a period of about 15 months to enable it to accomplish its development mission which is of paramount importance in the transition period. As a result, national statistics were available on time; the State's public investment program was drawn up and its execution was monitored; the PRSP drafting process was launched; and EERC oversight was ensured. It is likely that activities that it has initiated might be affected when EERC support ends. It is important to stress here that planning units were set up in the islands only because the EERC provided practically all the funding for the establishment and initial operating costs of the General Planning Offices.

9.3 Critical Assessment

With regard to poverty reduction and decentralization, activities were identified for EERC funding by technicians in the sectors concerned and were validated by each island's authorities. National reconciliation activities were identified by the beneficiary bodies, and validation by the Planning Commission is required before any commitment.

- 15 - All EERC-funded activities were implemented by technicians in the sectors concerned in cooperation with the Project Management Unit. Technical responsibility for each funded activity rested with area technicians, members of the EERC Implementation Unit, who held sole responsibility for ascertaining the relevance of the activity chosen and for recommending measures likely to prove useful or necessary in the course of implementation. The main task of the EERC management sub-unit was to ensure transparent and efficient use of funds in conformity with the allocations and breakdown by sector and island stipulated in the matrices and with funds management procedures agreed with the World Bank. As the project management team was supported in the field by the appropriate sector representatives, the team's work was in most cases considerably facilitated by this division of responsibilities.

In implementing EERC-funded activities, certain difficulties could not be avoided.

In the health sector, there was some delay in implementation due to late delivery by suppliers. Compensatory penalties were applied. It should also be noted that action in this sector might have a reduced impact because there is not enough qualified staff in the hospitals. EERC-funded training programs were implemented on the island of Anjouan only, and there is a general shortage of human resources in the health services. Consequently, given the lack of the necessary specialists, all equipment purchased is not likely to be operational immediately. These problems are expected to be solved under the IDA-funded Health III project, which has an institutional support component.

With regard to safety at sea, the work of the technical committee, in which the fishing and maritime safety sectors of all three islands participated, ensured the delivery and operation of the equipment purchased. Technicians were trained to train fishermen to use the new equipment and information meetings for fishermen were organized. However, the real impact of that project will become apparent only when the second component, rescue at sea, which consists in locating and rescuing fishermen in distress, has been put into practice. The Government should therefore mobilize the necessary resources rapidly to purchase equipment to implement this component.

With regard to the water component, there was a long nine-month delay in the implementation of the Makorani water supply project, designed and overseen by the National Infrastructure Directorate. The national oversight team has major responsibility for progress on that project. Failure by the team to make relevant recommendations in order to resolve the problems identified made the EERC management sub-unit's work on this project difficult. The difficulties encountered seemed to have arisen largely from an erroneous project feasibility study. Furthermore, project implementation was delayed to some extent by unforeseen events, such as inclement weather and delays in the provision of reservoir sites by the community.

In the area of decentralization, the impact of EERC-funded investment on two islands, Anjouan and Moheli, may only be assessed after the technical staff needed to perform the work of each autonomous administration has been appointed. Although the administrations do require material resources, human resources are even more necessary. However, there is a shortage of technical staff in the ministries set up in Moheli and the profiles of most staff in Anjouan do not match job requirements.

With regard to national reconciliation, action which was not initially planned was taken in support of the privatization of the port enterprise, Socopotrame. That action was taken to meet the Government's urgent need for funds to enable the State to honor commitments to its partners and lay solid foundations for the New Comorian Grouping. The EERC was the sole possibility of obtaining cash rapidly because of its streamlined funds management procedures. On the recommendation of the World Bank and after approval by the Government, a sum of US$595,000 was mobilized in July 2002 through the EERC to finance compensation payments to Socopotrame (the port authority) personnel dismissed in the privatization process and allow the new private operator to take over the company. That contribution was secured partly by reducing funds initially earmarked to finance expenditure under the national reconciliation component and partly by transferring an additional $200,000 from funds initially allocated for poverty reduction in Grande Comore. The construction of a health center, which was to be financed from those funds, has been taken over by the Health III project.

- 16 - With regard to EERC accounts, some difficulties were noted in relation to the accounts closed as at December 31, 2002. The problems arose from exchange-rate overvaluation and overestimation of allocations under the various funding categories (surpluses of KMF 24.6 million in Anjouan, 21.6 in Moheli, 5.17 in Grand Comore and 17.6 under national reconciliation). In Moroni, the US$128,844 gained on foreign exchange was not entered in the EERC account. It is regrettable that this situation was not discovered earlier and reported to the project management team by PriceWaterhouse-Coopers (Mauritius), the external auditors who conducted two project account audits. The reports submitted did not draw the project officers' attention to this error or recommend any relevant measures. To solve the problem, the project management team made proposals likely to satisfy all the parties concerned and enable them to ensure the positive impact of the EERC.

Among the lessons learned from the implementation of EERC-funded activities, the most significant conclusion concerns the criteria for selecting suppliers or contractors. In almost all EERC-funded procurement operations, emphasis was laid on the criterion of awarding contracts to the lowest bidder. However, this criterion, although justified in procurement procedures followed by the World Bank when it is combined with other conditions that allow for optimal choice and savings, was not entirely appropriate for the EERC project, as there were in that case no provisions to ensure performance within the required deadlines. As a result, problems arose involving enormous delays by contractors or suppliers who had deliberately bidden low and offered quite short delivery deadlines to obtain the contract in full knowledge of the fact that these deadlines were not realistic or feasible. The most flagrant case was a four-month delay on a four-month delivery deadline for the supply of ambulances by Peugeot SCIC: this company had proposed the above deadline although it knew from the beginning that the products were not in stock, that they had to be made to order and that the manufacturing process would take at least six months.

Funds management experience gained under the national reconciliation component confirmed the importance of clear and precise programming of activities under each category and of appropriately itemizing the amounts. It was found that the management of the funds allocated to the other two project components posed no particular problems, because from the start activities had been defined clearly and funds allocated precisely. In those components, all the parties involved in the EERC, namely the Bank, the recipients and the fund managers, agreed on a fund allocation schedule for each disbursement, specifying in full the nature and financing of each activity to be carried out. As a result, implementation became a simple routine operation of verification before fund commitment and payment. In the case at hand, however, no activity was identified with respect to funds allocated under common costs, in particular for support to the transition bodies, and only an overall amount was indicated. Difficulties therefore arose in managing these funds, when activities submitted for funding by the technical staff responsible for the area concerned (financing of meetings) could not be justified on the basis of tangible results, and the management team had reservations about authorizing payments for such activities, although they were considered to be a priority.

With assistance from the Bank, however, solutions were later found to this problem encountered by the management team during the initial months of EERC implementation, and funding of ineligible expenses was avoided.

Eighty percent of EERC funds were distributed among the islands of the Union of the Comoros. The method of management used consisted in allocating to each entity a specific amount agreed upon by all the parties, i.e., the Government, the Bank and the authorities of the islands, for each disbursement (for the record, there were three such disbursements). Allocations were made on the basis of a set of activities programmed by the islands in conformity with the basic matrices stipulated in the Letter of Policy for National Reconciliation. A special sub-account was opened in Anjouan to facilitate disbursements and it was credited upon each disbursement and distribution with the full amount allocated to finance the entire set of relevant activities. This sub-account was managed by the EERC management sub-unit of Anjouan in conformity with instructions from the island's EERC Implementation Unit. Although the national and the Anjouanese EERC management sub-units fulfilled their missions completely, problems arose in project monitoring at the national level because there were no functional

- 17 - links, predefined by regulatory texts, between the two bodies. Although it is certain that decentralized management can serve the interests of the Comorian population in the best possible way, the method of decentralization must be explained clearly to avoid any jurisdictional conflict.

9.4 Conclusion

In conclusion, we consider that the Emergency Economic Recovery Credit has attained the objective of national reconciliation by contributing to poverty reduction, supporting the decentralization of administrative bodies of the New Comorian Grouping, and financing the activities of the bodies involved in the transition process.

Attainment of this objective, to which the Government gives high priority, was possible only with the assistance of our partner, the World Bank, which supported the Comoros from the beginning of negotiations for this credit to the completion of the EERC project. In particular, the Bank provided technical assistance to the Planning Commission in drafting the Letter of Policy for National Reconciliation and in organizing the "Friends of the Comoros" conference in 2001 in order to help the Government to mobilize the emergency funds needed for reconstruction. It then undertook to finance three of the four identified matrices containing the Government's priority needs, assisted the national team in the technical design of the EERC project and took the necessary steps to facilitate and accelerate disbursements. Owing to the rapid processing of disbursements, the national management team began project activities quickly and maintained a normal pace of disbursement throughout. The Bank conducted regular evaluation missions to ascertain the positive development of the project and to initiate activity programming for subsequent disbursements. The Bank’s EERC oversight team monitored activity files quite efficiently, while offering support for resolving problems faced by the national agencies during project implementation, including problems outside the Bank's mandate. We wish to express here our gratitude to the team.

One of the factors of the EERC's success was the World Bank's flexibility with regard to management procedures. Pursuant to agreements with the World Bank, streamlined disbursement procedures complying with the rules of transparency and competitive bidding were followed in managing the Emergency Credit. Under these procedures the Government committed US$6 million in 15 months and dispelled doubts about fund absorption capacity in the Comoros. The implementation of the EERC project has therefore shown that there are ways and means of achieving a faster rate of disbursement of funds mobilized by the Government from its partners. Funds allocated to the Comoros under development projects are usually disbursed rather slowly. The IDA-funded FADC, the program with the best annual implementation rate, has never attained 50 percent of the EERC disbursement level within a 15-month period. It is obvious that a rather efficient form of funds management has been tested in resolving problems arising from slow disbursement, and the Government is very interested in repeating this exercise.

In sum, the implementation of the EERC project has made it possible to attain the short-term development objectives that were established, while concurrently laying the foundations for the long-term development of the Comoros. Three elements are considered essential: identification of needs by the beneficiaries, coordination of activities by a competent technical team capable of harmonizing the aspirations of the autonomous islands within a Comorian Grouping, and use of an efficient form of management for speedy disbursement. (b) Cofinanciers: N/A (c) Other partners (NGOs/private sector): N/A

- 18 - 10. Additional Information 10.1 Aide-Mémoire of the final evaluation mission of the EERC project by the World Bank in the Union of the Comoros, 3-17 December 2002

Objective and activities

A World Bank mission team, composed of Mr. Colin Scott (SDVCRP) and Mr. Vincent da Cruz (Consultant), in cooperation with Mr. Wolfgang Fengler (AFTP1), visited the Union of the Comoros from December 13-17, 2002. The mission's objective was to draw up the Implementation Completion Report of the Emergency Economic Recovery Credit (EERC) project.

The mission team wishes to thank the Government of the Union and the authorities of the islands for their excellent cooperation and for facilitating its task. In particular, it expresses its gratitude to Mrs. Koulthoum Djamadar and Mr. Mekame Bouchrane for their hospitality and assistance.

The mission team met persons participating in the EERC project, including representatives of the Government of the Union and of the islands, and those responsible for carrying out the various activities. It also saw project achievements on all three islands.

The mission also visited the Self-Employment Education and Training Center (CEFAE) at Patsy, set up by Care International and funded from World Bank post-conflict funds.

A reconstruction workshop was held at the Planning Commission to discuss observations and further steps.

Observations

1. In general, the objectives and the design of the EERC project were reasonable and realistic. 2. The timing of the intervention of the EERC project corresponded to crisis-induced needs. 3. Poverty-reduction and decentralization activities were generally carried out efficiently under the EERC project, despite some problems. 4. Results are less clear with regard to the objective of national reconciliation. The EERC project supported reconciliation by contributing to poverty reduction and thereby addressing a source of tension. However, reconciliation in a broader sense, namely combating secessionism, is an essentially political objective requiring more than activities that can be funded under a credit like the EERC. 5. Attainment of the objective of supporting transition was constrained by political instability and the absence of a strategic vision for the Comoros shared by all stakeholders. In this context, the World Bank experienced difficulties in updating its strategy for the country. 6. The EERC project experience provided significant lessons for the World Bank with regard to development in the Comoros in general. It should therefore be shared and discussed with all actors concerned. 7. With regard to the CEFAE project, the mission team ascertained satisfactory progress toward completion, scheduled for June 2003. An independent evaluation of results is planned to provide guidance for planning a possible continuation of the project and scheduling its funding.

Further steps

1. The Comoros Government will prepare a draft borrower's final report with inputs from, and in consultation with, the three islands, and will submit it to the World Bank by the end of January 2003. 2. The Government proposes to conduct an evaluation of beneficiaries, and the evaluation

- 19 - details are to be discussed with the World Bank. 3. The World Bank team will draw up a draft completion report by the end of January 2003. 4. With respect to the CEFAE project, the competent authorities, Care International and the World Bank will draft the terms of reference required to initiate an independent evaluation.

10.2 Timeline

Date Comoros Bank

1997 Anjouan and Moheli secede, military Bank has five projects and two in intervention by center is routed, preparation blockade of Anjouan imposed by OAU 1998 Federal president Taki dies, General suspension of disbursements “Government of public salvation” due to arrears formed in center, disputes between factions in Anjouan erupt into violence 1999 Antanarivo accord, failure to sign by Moheli and Anjouan sparks violence in Grande Comore, Army takes power in coup, Azali Assoumane becomes central president 2000 Debt service arrears cleared, Coup Suspension lifted, EERC January attempt (April) Country Portfolio to June Review July to Fomboni accord signed by all islands, ISS approved ISS includes December Tripartite Commission established conditions for EERC 2001 Framework Agreement signed in Comoros moves to EERC provisional January Fomboni, creditor’s meeting in high case spending matrix to June Moroni, IMF conducts Article IV drafted, PID mission review July to Donor meeting in Paris, Coloner Bacar Formal request December deposes Abderemane in Anjouan in for assistance, coup, two coup attempts in Anjouan, EERC approved, one in Moheli, constitutional signed, and referendum held on all islands US$3.6million disbursed 2002 Interim government installed, PRSP process Remaining January presidential elections held for Union launch US$2.4 million to June and islands. Failure to agree on budget disbursed leads to suspension of IMF SMP (June) July to Joint budget agreed but agreement Credit closed December breaks down (December) (December)

- 20 - 10.3 Map of Comoros

- 21 - Annex 1. Key Performance Indicators/Log Frame Matrix

Given that this credit followed OP 8.50 and provided funds akin to budget support against import receipts, the progress indicator used was the rate of disbursement. The different installments were disbursed when major milestones of the transition process were reached. Disbursements were also dependent on sound financial management as determined in supervision missions. The table below is based on components and risks listed in the Project Supervision Reports. Components in italics have been added. The ICR contains more information on risks. Given the types of activities financed by the credit, it would have been desirable to agree upon an actual logical framework matrix and indicators with the implementing partner, if only to clarify links between components and outputs and outputs and objective.

Project Performance Ratings Summary Ratings: Last ICR Compliance with Agreed NA NA Achievement of PDO S S Proc. Schedules Quality and Reliability of Proc. S S Implementation Progress S S Admin Other Ratings: Safeguard Mgt Performance NA NA Financial Management S S Other Legal Covenants S S Financial Performance NA NA WID Impact NA NA Project Management S S Monitoring & Evaluation S HS Project Component Ratings Cost (actual) Last Now COUNTERPART FUNDS -- POVERTY REDUCTION 2.9 S S COUNTERPART FUNDS -- DECENTRALIZATION 1.1 S U COUNTERPART FUNDS -- RECONCILIATION 0.6 U U COUNTERPART FUNDS -- PROJECT IMPL UNIT 0.3 NR S COUNTERPART FUNDS -- SALARY ARREARS 0.6 NR S COUNTERPART FUNDS -- PORT PRIVATIZATION 0.6 NR S

Notes: HS=Highly Satisfactory; S=Satisfactory; U=Unsatisfactory; HU=Highly Unsatisfactory; NA=Not Applicable; NR=Not Rated; Cost in US$ millions

Critical Risks Rating Last ICR Last ICR Summary Risk Rating S H From Outputs to Objective RECONCILIATION PROCESS S H INSTABILITY IN M M STALLS ANJOUAN LACK OF COMPLEMENTARY S S POLITICAL H H DONOR SUPPORT INSTABILITY IN GRANDE COMORE From Components to Outputs

Notes: H=High; S=Substantial; M=Modest; N=Low or Negligible; NA=Not Applicable; NR=Not Rated.

- 22 - Annex 2. Project Costs and Financing

Project Cost by Component (as per Spending Program in Supplemental Letter No.3)

Anjouan Moheli Gde Comore TOTAL Poverty Reduction 1.5 0.3 1.2 3.0 Decentralization 0.9 0.6 0.3 1.8 Sub-TOTAL 2.4 0.9 1.5 4.8 Coordination and Tri-partite 1.2 technical committees TOTAL 6.0

Appraisal (US$ million)

Annex 8 of the ICR contains an expenditure table based on the latest information received from the implementing partner.

Project Cost by Procurement Arrangement Not applicable

- 23 - Annex 3. Economic Costs and Benefits N/A

- 24 - Annex 4. Bank Inputs (a) Missions: Stage of Project Cycle No. of Persons and Specialty Performance Rating (e.g. 2 Economists, 1 FMS, etc.) Implementation Development Month/Year Count Specialty Progress Objective Identification/Preparation 2001 2 Economics March/April

Appraisal/Negotiation 2001 May/June 2 Economics Financial Management 2001 July 2 Economics 2001 August 2 Economics 2001 October 1 Financial Management Supervision 2001 November 2 Economics S S 2002 March/April 4 Sector Manager HS S Economics (2) Financial Management 2002 July 2 Economics Procurement 2002 December 3 Economics S S Health Procurement ICR 2002 December 2 Post-conflict S S Operations & Evaluation

(b) Staff:

Stage of Project Cycle Actual/Latest Estimate No. Staff weeks US$ ('000) Identification/Preparation 55.23 122,035.62 Appraisal/Negotiation Supervision 25.60 57,753.90 ICR 4.44 15,583.74 Total 85.27 195,373.26

- 25 - Annex 5. Ratings for Achievement of Objectives/Outputs of Components (H=High, SU=Substantial, M=Modest, N=Negligible, NA=Not Applicable) Rating Macro policies H SU M N NA Sector Policies H SU M N NA Physical H SU M N NA Financial H SU M N NA Institutional Development H SU M N NA Environmental H SU M N NA

Social Poverty Reduction H SU M N NA Gender H SU M N NA Other (Please specify) H SU M N NA Private sector development H SU M N NA Public sector management H SU M N NA Other (Please specify) H SU M N NA

- 26 - Annex 6. Ratings of Bank and Borrower Performance (HS=Highly Satisfactory, S=Satisfactory, U=Unsatisfactory, HU=Highly Unsatisfactory)

6.1 Bank performance Rating

Lending HS S U HU Supervision HS S U HU Overall HS S U HU

6.2 Borrower performance Rating

Preparation HS S U HU Government implementation performance HS S U HU Implementation agency performance HS S U HU Overall HS S U HU

- 27 - Annex 7. List of Supporting Documents l (MOP) Memorandum and Recommendation of the President on a Proposed Credit to the Islamic Federal Republic of the Comoros, June 4, 2001 l Système de suivi et de décaissements et des dépenses de la mise en œuvre de la matrice dans le cadre du crédit CURE, Direction Générale du Plan, 16 Juin 2001 l Procès-verbal des Négociations du 6 juillet 2001, Crédit d’Urgence au Redressement Economique (CURE) l Technical Annex for a Proposed Credit to the Islamic Federal Republic of the Comoros for an Emergency Economic Recovery Credit, July 11, 2001, Report T-7475-COM l Aide Mémoire, Mission de la Banque mondiale en République Fédérale Islamique des Comores du 27 août au 4 septembre 2001. l (DCA) Development Credit Agreement, Credit Number 3563 COM (Emergency Economic Recovery Credit), Dated September 10, 2001 l Supplemental Letter No.3 Re: Credit No. 3563 COM (Emergency Economic Recovery Credit) Section 4.01 of the Development Credit Agreement, Priority Program of Local Expenditures, of September 10, 2001 l Manuel Général de Procédures, Crédit d’Urgence au Redressement Economique, Commissariat Général au Plan, novembre 2001 (draft). l Aide Mémoire, Mission de la Banque mondiale en République Fédérale Islamique des Comores du 10 au 20 novembre 2001. l Rapport de Contrôle Interne, Crédit d’Urgence pour la Relance Economique, PriceWaterhouse-Coopers, 31 mars 2002 l Etats Financiers, Crédit d’Urgence pour la Relance Economique, PriceWaterhouse-Coopers, 31 mars 2002 l Aide Mémoire, Mission de la Banque mondiale et du Fond monétaire international en Union des Comores du 19 mars au 4 avril 2002. l Aide Mémoire, Mission de la Banque mondiale en Union des Comores du 13 au 27 juillet 2002, including the attached Project Status Report Comoros Emergency Economic Recovery Credit, Seq #2. l 2ème Rapport de Contrôle sur le Crédit d’Urgence au Redressement Economique (CURE), Commission de Vérification des Comptes, novembre 2002. l Aide Mémoire, Mission de la Banque mondiale en Union des Comores du 9 au 17 décembre 2002 l Various disbursement tables, sub-project progress reports and correspondence

- 28 - Additional Annex 8. Expenditure Table

(As of 28 February 2003, based on 541.79 KMF/US$)

Item Budgeted Committed % Disbursed % TOTAL 6,000,000 6,164,582 103% 4,774,396 80% Poverty Reduction Component 3,000,000 2,900,959 97% 2,527,289 84% Health 1,350,000 1,140,864 85% 1,095,956 81% Anjouan 450,000 411,782 92% 366,874 82% Hospital rehabilitation (Hombo) 50,499 30,204 Pediatric ward rehabilitation 16,104 7,955 Laundry rehabilitation 6,691 6,430 Ward rehabilitation 3,888 3,775 Pediatric ward tiling 23,817 12,043 Equipment and medical supplies 153,223 153,223 Pharmaceuticals for PNAC 76,413 76,413 Staff training 31,977 7,364 Ambulances 99,670 99,670 Grande Comore 600,000 440,068 73% 440,068 73% Hospital rehabilitation () 146,340 0 0% 0* 0% Hospital rehabilitation (El Maarouf) 0 17,695 17,695 Pharmaceuticals for PNAC 400,000 172,465 43% 172,465 43% Medical gaz 53,660 53,660 100% 53,660 100% Equipment and medical supplies 0 106,995 106,995 Ambulances (2) 0 65,948 65,948 Cholera camp 0 23,305 23,305 Moheli 300,000 289,014 96% 289,014 96% Equipment and medical supplies 270,468 193,690 72% 193,690 72% Medical gaz 29,532 29,290 99% 29,290 99% Ambulances (2) 65,789 65,789 Staff training 0 245 245 Education 750,000 811,432 108% 630,481 84% Anjouan 750,000 811,432 108% 630,481 84% Building 20 classrooms 0 342,288 300,140 Building 2 classrooms Hombo 32,536 31,118 Building 2 classrooms High School 35,197 33,437 Building 2 classrooms Liwara High School 33,260 28,809 Building 2 classrooms Mirontsy Primary School 33,111 31,455 Building 1 classroom Akibani Primary School 20,564 19,603 Building 2 classrooms Barakani Primary School 31,818 30,227 Building 1 classroom Jimlime Primary School 24,301 2,427 Building 1 classroom Ankibani School 23,511 22,302 Building 2 classrooms Imere School 26,290 25,098 Building 2 classrooms Ongojou School 39,113 35,623

- 29 - Item Budgeted Committed % Disbursed % Building 1 classroom Milembeni School 15,376 14,607 Building 2 classroom Chirove School 27,212 25,434 Rehabilitation 7 schools 400,000 147,617 37% 95,109 24% Missiri School 11,081 9,461 Mirontsy-Wamani School 23,454 22,631 Bazimi Primary School (4 classrooms) 25,892 24,598 Ouani Primary School 19,158 18,200 Secondary School 25,764 20,220 Bweladoungou School 20,936 0 School 21,333 0 Other construction works on schools 43,849 31,248 Two latrines at Hombo 3,722 3,535 Fencing in Hombo 12,918 12,273 Roofing of Massiri School 15,185 14,426 Additional work Hombo 1,067 1,013 Fencing in 10,957 0 School equipment 250,000 258,615 103% 184,922 74% Classroom equipment first tranche 38,259 38,259 Classroom equipment second tranche 48,617 21,088 School supplies first tranche 35,893 35,893 School supplies second tranche 44,205 44,205 Printing supplies second tranche 7,217 6,495 180 Tables 6,460 0 Sporting equipment 77,965 38,982 Staff training 100,000 19,063 19% 19,063 19% Water, Sanitation, Roadworks 510,000 572,167 112% 460,296 90% Anjouan 150,000 217,791 145% 169,707 113% Small infrastructure works 197,414 169,707 Drainage Canal 49,836 40,511 Protection wall Koni Ngani 7,595 7,368 Support wall Magagarajou 14,732 14,146 Road to Hombo primary school 29,906 28,411 Support wall Hombo School 43,750 38,765 Support wall Hombo crossroad 854 769 Road surface Sima-wemani 18,494 17,787 Washing facilities Papani-Domoni 15,197 14,139 Ankiba School 2,703 0 Road to high school 6,124 0 Drainage Hombo School 8,222 7,811 Repair of public works machinery 20,377 0

- 30 - Item Budgeted Committed % Disbursed % Grande Comore 360,000 354,376 98% 290,589 81% Makorani water supply 360,000 354,376 98% 290,589 81% Rural Development 150,000 37,062 25% 1,123 1% Anjouan 150,000 37,062 25% 1,123 1% Reforestation and livestock 50,000 37,062 74% 1,123 2% Fishery equipment 100,000 0 0% 0 0% Navigation and Comms Equipment** 240,000 339,433 141% 339,433 141% Anjouan 0 99,793 99,793 Grande Comore 240,000 179,899 75% 179,899 75% Moheli 0 59,740 59,740 Decentralisation Component 1,800,000 1,132,054 63% 432,303 24% Anjouan 900,000 519,944 58% 205,670 23% Rehabilitation of administrative buildings 600,000 361,518 60% 169,642 28% Finance Ministry rehabilitation 93,897 44,854 Treasury rehabilitation 24,797 13,582 Immigration office rehabilitation 23,212 0 Construction of administrative office block 219,613 111,205 Equipment, furniture and supplies 0 110,437 36,028 15 PCs, 4 laptops, 12 copiers and 6 phones 0 54,168 16,390 470 chairs, 120 tables, 30 desks, 35 armchairs 0 52,747 18,751 printing and mapping supplies 0 3,522 887 Vehicles for administration (4) 0 47,989 0 Civil servant relocation 300,000 0 0% 0 0% Grande Comore 300,000 58,364 19% 27,675 9% Rehabilitation of president's office 204,000 16,612 8% 12,909 6% Staff training 96,000 0 0% 0 0% Equipment, furniture and supplies 0 16,097 2,769 Vehicles for administration (2) 0 25,656 11,997 Moheli 600,000 553,746 92% 198,958 33% Construction of central office block 300,000 479,891 160% 125,102 42% Communal admin. building construction 300,000 0 0% 0 0% Vehicles for administration (6) 0 73,856 73,856

- 31 - Item Budgeted Committed % Disbursed % Reconciliation Component 500,000 186,587 37% 186,587 37% Center 500,000 186,587 37% 186,587 37% Tri-partite Commission 69,251 Per diems 51,298 Travel 3,658 Meetings 14,294 Supervision Committee 75,549 Studies and Expertise 41,787 Supporting the 353 Administration 363,000 1,584,091 436% 1,279,597 % Supporting Budget and Civil Service 63,000 63,000 100% 52,194 83% Center 63,000 63,000 100% 52,194 83% Budget formulation 63,000 63,000 100% 52,194 83% Planning Ministry Support 300,000 306,029 102% 243,419 81% Center 300,000 142,382 47% 116,542 39% Rehabilitation 26,049 26,049 Equipment, furniture and supplies 73,192 62,118 Salaries 28,374 28,374 Vehicle 14,766 0 Anjouan 0 65,076 52,156 Rehabilitation 23,072 23,072 Equipment, furniture and supplies 18,082 19,928 Salaries 9,157 9,157 Vehicle 14,766 0 Grande Comore 0 43,905 21,712 Rehabilitation 9,229 452 Equipment, furniture and supplies 20,059 6,945 Salaries 775 473 Vehicle 13,843 13,843 Moheli 0 54,666 53,009 Rehabilitation 21,503 21,706 Equipment, furniture and supplies 16,552 14,488 Vehicle 16,612 16,815 Civil Servants' Salary Arrears 0 620,061 620,061 Anjouan 306,287 306,287 Grande Comore 276,860 276,860 Moheli 36,915 36,915 Port worker compensation 0 595,000 363,923 Anjouan 231,077 0 Grande Comore 363,923 363,923

- 32 - Item Budgeted Committed % Disbursed % Project Running Cost 337,000 275,014 82% 266,800 79% Center 337,000 275,014 82% 266,800 Salaries 29,532 29,532 Travel 12,831 12,831 Supplies 206,312 206,312*** Audits 26,340 18,126 Other 0 85,878 81,820 Anjouan 39,751 35,693 Technicians 39,751 35,693 Moheli 574 574 Study 574 574 Center 45,553 45,553 Rehabilitation of building 45,553 45,553 TOTALS BY ISLAND 6,000,000 6,164,582 103% 4,774,396 80% Anjouan 2,400,000 2,739,995 114% 1,867,786 78% Grande Comore 1,500,000 1,717,396 114% 1,600,727 107% Moheli 900,000 994,655 111% 638,209 71% Center 1,200,000 712,535 59% 667,674 56%

*Implementation was taken over by Health Project. **Project also known as “Safety of Fishermen” ***Includes purchase of two project vehicles.

- 33 - - 34 -