THIRD ANDt-IRA PRADESH IRRIGATION PROJECT

PROJECT AFFECTED PERSONS Public Disclosure Authorized ECONOMICREHABILITATION PROGRAMME (PAPERP) Public Disclosure Authorized

ACTION PLAN Public Disclosure Authorized

GOVERNMENT OF IRRIGATION & CAD DEPARTMENT

Public Disclosure Authorized HYDERABAD

MARCH, 1995 INCHARGE OFTHE DEPARTMENT:

Sri K. KOSALRAM,IAS Pri. Secretary to Govt. Irrigation & CAD Dept. 'J' Block, Secretariat HYDERABAD

Phone Nos.: 232630 (Off) 316709 (Res) Fax No. 233511

INCHARGE OF THE PROJECT

Sri P.K.Agarwal, IAS Secretary (Projects) Irrigation & CAD (PW) Dept 'J' Block, Secretariat HYDERABAD

Phone Nos. 232529 (Off) 331400 (Res) Fax No. 233511 CONTENTS

Si. No. Ilemn Page No.

1. Introduction 3 2. Project and Objectives 5 3. Approach for R&R 12 4. Direct & Indirect Benefils 15 5. Project Affected Area 16

6. Land and PropertyAqcuisition 19 7. Project Affected Commnunity 24

8. ProjectAffected Persons 30 9. Adverse Impacts of land acquisition 33

10. Enabling legislation for acquisition of land 34 11. EnvironmentalImpact Assesment 35

12. Patlicipalion of Pioject affected persons 36

13. Aclion Plan 37

14. Stragy for Impleinentation of Action Plan 42

15. Inslifulional arrangerments 43 16. Monitoring and evaluation 46 17. Budget 47 18. TheWorik Plan 50

19. Listof Annexures 51

20. Listof figures INTRODUCTION

The Stateof Andhra Pradeshcomprises three regionsnamely, Coastal, and .The economy of A.P.is predominantlyagrarian; agriculture contributes about50% to the State'sincome and employsabout 70% of thework force. Since agriculture is the prime mover and hub of all economicactivities, growth in economy is largely dependenton continuousgrowth in agricultureand the removalof constraintsthereto. Governmentof AndhraPradesh is strivingto alleviatethe sufferingsof the people in the state in general,and those in the droughtprone areas, in particular.Rayalaseema and Telanganaregions being the State'smost backwardand droughtprone regions,the impactof irrigationon the poorestpeople would be significantand developmentwill be substantial,once water reaches these areas. HenceRayalaseema and Telangana regions of the State were chosen for providingirrigation benefits under two sub projectsviz., SrisailamRight BranchCanal (SRBC)Scheme and Sriramsagar(SRS) Scheme under the SecondA.P. IrrigationProject. 1.1 SECONDA.P. IRRIGATIONPROJECT The SecondA.P. IrrigationProject was taken up with the financialassistance of World Bankto the tune of SDR 127.5M (US $140 M as on 1986)as creditand US$ 131 M as loan. The projectwas plannedto be completedin a durationof sevenand half years i.e., from June 1986to December31, 1993with the credit/loanclosing date as June 30, 1994. Themain objective of the projectwas to increaseagriculture production and farmers incomein the commandarea of boththe projects;(i) SRBC(65,000 ha) and(ii) Sriramsagar (SRS) KakatiyaCanal Command(modernisation of 1,65,000ha and developmentof 1,63,000ha). The maincomponents of the projectwere: !. SRBCSub-Project 1. SRB Canal from the BanakacherlaRegulator to the Gorakallubypass structure. 2. The GorakalluBypass structure 3. SRBCanal beyond the GorakalluBypass structure for about100 Km (ending Km 141.0). II. SRSSub-Project 1. Upgradingand completionof conveyanceworks of KakatiyaCanal Command betweenKm 0- 146 2. Completionand new conveyanceworks of the KakatiyaCanal Command between Km 146 - 267. 3. Excavationof the tail sectionof the KakatiyaCanal to serveas an escape (Km 267 - 284). Thoughthe projectimplementation improved very much in the last two and half years i.e., 1992-93onwards, the projectcould not be completedin full by June 30, 1994 becauseof earlierslippages in the projectimplementation. Though the overallphysical progressto end of June 1994 was only 30% (SRBC 38% and SRS 21%), since the

3 achievementunder certain connectedactivities was nearlyfull the projectwould have been ableto irrigatein 1996-97i.e., with an extensionof three years. 1.2 NECESSITYOF THIRDA.P. IRRIGATIONPROJECT Sincethe objectivesof the SecondA.P. Irrigation Project could not be achieveddue to non completionof the projectit is felt desirablenot to leaveor delaythe projectin the present half - finishedand inoperablestate but to find additionalinvestment needed to complete theworks early and realisethe potentialcreated by pastinvestments and assistfor increased agriculturalproduction and improvethe economyof the backwardregions of Andhra Pradesh. TheThird A.P. IrrigationProject thus contemplatesto completethe spill overworks of the SecondA.P. IrrigationProject at the earliestto generatethe benefitscontemplated.

4 THE PROJECT AND OBJECTIVES

2.1. SRISAILAM RIGHT BRANCH CANAL 2.1.1. Introduction: The SrisailamRight Branch Canal (SRBC)draws its water from SrisialamReservoir, built across . An approach channel has been provided within the reservoir to supply water at the Pothireddypadu Regulator. A right main canal takes off from the regulator,traverses a length of 16.34 km through Mittakandaladeep cut (the ridge between Krishna and Pennar basins) upto Banakacharla Regulator. SRBC takes off from the right of the regulator to provide irrigation to an area of 65,000 ha in . The service area is almost rectangular in shape with a length of 130 km and a width of 5 to 10 km. There is no irrigation in the first 50 km upto Gorakallu Bypass. Below the Bypass, the canal traverses a length of 64 km before joining the Owk reservoir through a 1.89 km long tunnel. The canal then extends to km 141 to provide irrigation to an area of 65000 ha. Locationmap and Index plan of SRBC sub-projectare shown in Fig 1 & 2. The components of the project are as follows: i) SRB Canal from the Banakacherla Regulator to the Gorakallu Bypass Structure, for a length of 50.753 Km. ii) The Gorakallu bypass structure. iii) SRB canal from the Gorakallu bypass structure to Owk Reservoir. iv) Owk tunnel from km 113.525 to 115.584. v) Owk Reservoir from km 115.584 to 119.5 vi) Major distributory from km 119.5 to 141. vii) Distributory Network in Block I to XVI. viii) Feeder Road network. 2.1.2. Geology: The main geological formations in the project area comprise the shales, Koilkuntlalimestones, Panyamquartzites, Owk shales, Narji limestonesand Banaganapalli quartzites. The hill ranges along the western boundary in Banaganapalli mandal consist of quartzite overlying calcarious shales. In the Kunderu plain limestones and shales predominate.

2.1.3. Physiography: 85% of the command area is nearly plain with slope of less than 1%. The rest of the command is very gently sloping with slopes of 1-3%. Physiographically,the area can be divided into three main units viz., hills, gently undulating plains and valleys. The hills are residual relief features comprising quartzites and limestones. The quartzite hills are gently dipping and are underlain by shales and limestoneswith escarpment on western side and a gentle dip towards east terminating into a plain. Elsewhere,gently dipping quartzites are surrounded by plains all around. The plains are vast stretches of land which occupy 85% of the command area. Many small streams traverse the plain forming narrow linear valleys moderately to severely eroded and salt-affected lands are formed near the valleys. The

5 plainshave very deep darkcolour cracking type of claysoils. The valleyshave weatheredl transportedmaterial. Evidenceof erosion in the form of sheet wash and rills can be observed.

2.1.4 Soils: The soils in the commandare generallyblack cotton soils derivedfrom lime stones and shaleswith intrusionsof quartzitesand sand stones.80% of the area is coveredby deep black cottonsoils. About 83%of the soils are in irrigabilityclass-l1, even as 95% of the soils excludinghills are culturable.

2.1.5. Drainage: The commandarea is drainedby Kunderuriver which is a tributaryof the Pennar flowingfrom Nallamalahills in the Northto Erramalahills in the South.It is joined by many local streamsduring its course, the importantones being the Jurreruand Paleru.The drainagepattern of the commandarea is dendritic.

2.1.6 Climate: The climateof the area is of temperatetype with hot summersand mild winters. The meandaily maximumtemperature during winter is 300C and minimum17.50 C. The mean daily maximumtemperature during summer is 41.40C and a minimumis 28.50C. The relative humidityvaries from month to month and increasesfrom 65% to 85% in South-Westmonsoons. It is lessthan 65% in the rest of the year.

2.1.7. Rainfall: Theaverage annual rainfall in the SRBCCommand area is 761 mmwith a maximum spreadover of three monthsfrom Julyto September.Nearly 71% of the rainfallis received duringSouth-West monsoon (July to September)and 29% during the North-Eastmonsoon monthsof Octoberto December.The lowestrainfall recorded in the commandis 506 mm at Owk whichis very meagrefor irrigateddry crops.The lowestrainfall in the last 90 years (1901- 1990)was 28 mm in 1920and the heaviestrainfall 1070 mm in 1970.

2.1.8. Population: The SRBCserves a major part of Kurnooldistrict which has a total populationof 2.97 million.74.17% of the populationis rural and the balance25.83% urban. Cultivators constitute11.16% of thedistrictpopulationwhileagriculturallabourers accountfor22.34%. The populationof the commandarea spread over 11 mandalscomprising 102 villagesis 0.26million. Farm holders constitute 13.8% of thetotal population of the command area.The marginaland small farm holdersform a majorityof 65.76%with marginalfarmers constitutingthe single largestgroup (38.29%).Between them, they hold 0.02 million ha with an averageland holding of 0.90 ha. The small farmers constitute27.47% with an averageland holdingof 1.44ha.

6 2.1.9. AgriculturalActivity: The SRBCwill mainlycover areas on the westof Kunduriver in Kurnooldistrict and a smallpart of the Cuddapahdistrict comprising mandals which are traditionallydrought proneand mostarid. There is Kurnool-Cuddapahcanal on the eastof Kurnoolwhich was constructedway backin 1872and a more recentLow-level canal of TungabhadraProject. Besides,some mediumirrigation works, wells and tanks serving parts of this area are existingmostly on the east of Kunduriver. Existingcanals irrigate an areaof 88814ha, wells provideirrigation to an area of 34018 ha while tube-wellsirrigate 4978 ha. The existingtanks benefit 14914 ha whileother sources account for 7447ha. Thetotal irrigated areais thus,0.15 M ha out of the geographicalarea of 1.77M ha which is lessthan 10%. As per agriculturalcensus the total croppedarea in the districtis only 47.5%. The principalcrops grown in the area in boththe seasonsare paddy,sorghum ragi, setaria,chillies, groundnut, castor, cotton, tobacco, onions, mulberry, sunflower, banana etc. Food crops occupy48% of the croppedarea while 52% are non-foodcrops. The farmersare conversantwith the use of fertilizersand manures.

2.1.10. OTHERACTIVITIES

Industries: Kurnooldistrict has been famousfor its craft of silk and cottonspinning, weaving and banglemaking. The districthas a fairlylarge number of big-sizeindustries as compared to other districtsof Rayalaseemaregion, producing minerals, cement, fertilizers. There are a few spinning mills, in the district while handloomweaving, tanning and leather industrieshave developedunder small scale category. Therewere 456 factoriesin the district(Kurnool) in 1990-91with a fixed capitalof Rs.635millions.

Mining: Kurnooldistrict under SRBCabounds in mineralwealth but much headwaydoes not seem to have been made in its exploitation.The importantminerals are limestone, iron ore, barytes,copper, lead, slate, steatite, mica, sulphur, calcite and zinc. Production figures for iron ore and limestonein 1990-91are 17,000 tonnes and 3,17,000tonnes respectively.

Pisciculture: The districtsunder the two sub-projectsused to be good fish productioncentres but currentlypisciculture has ceasedto be an importantoccupation. The GOAP,through its variousprogrammes is, however,promoting adoption of pisciculturein a scientificway. Sincelast one year efforts are beingmade to improvepisciculture in KurnoolDistrict. The seedproduction during 1993-94 is Rs.66.1millions against the targetof Rs.66millions. All helpis beingrendered by leasingtanks to FishermenCo-operative Society for stocking fish and to take up fish cultureto improveeconomic condition of the fishermen.

7 Forestry: Kurnooldistrict pertainingto SRBChas a total of 8375 Sq. Km of reservedforest area producingtimber worth Rs. 23 millions,firewood/charcoal Rs.3.4 millions bamboos Rs.6.94millions and Beedileaves Rs.7.6 millions (1990-91) besides other minorproduce. Thereis a wellestablished forest organisation taking care of protection,development and managementof the forestsin the districts.

2.1.11. OBJECTIVESAND NEED FOR R&R SrisailamRight Branch Canal envisages irrigation of 65,000ha of landin 12Mandals of chronicallydrought affected areas of KurnoolDistrict. In order to irrigatethese areas, water need to be conveyedfrom Srisailamreservoir which necessitatesexcavation of main canaland distributorynet work. The constructionof maincanal and distributorynet work alongwith the ayacutroad system requireeither land acquisitionfrom project affected personsor resumptionof Governmentland or forestland enroute, the system. The landacquisition including houses Ihouse plots and resumption of Government and forest land might result in either displacementor familiesgetting affected due to acquisitionof their land whichis the main sourceof livelihoodin most of the cases. This acquisitionof land or displacementmay necessitaterehabilitation or resettlementand rehabilitation.

2.2. SRS - COMMAND

2.2.1 Introduction The KakatiyaCanal takes off from SrramsagarDam across Godavari at Pochampad, about 200 km from Hyderabad. After traversingabout 146 km, the canal outfalls into LowerManair dam built acrossriver Manair.The canalextends from the oppositeflank of the dam to 284 km. The canal,in its reachfrom km 0 - 146 providesirrigation to an area of 1,65,000ha. The commandarea below LowerManair Dam (LMD) is 1,63,000ha. The commandarea lies in 66 mandalsof Nizamabad,, and districts. The Lower ManairDam servesas a balancingreservoir. A locationmap and Indexmap of KakatiyaCanal are shownin Fig 3 and 4 respectively. The importantcomponents are as follows: i. Upgradingand completion of conveyanceworks of the kakatiya Canal Commandfrom km 0 to 146. ii. Completionand newconveyance works of KakatiyaCanal Command between km 146 and 267. iii. Excavationof the tail sectionof the KakatiyaCanal . (betweenkm 267 and 284) to serve as escape. iv. Feederroad net work.

8 2.2.2 Geology: Geologically,the commandarea may be dividedinto Alluvialdeposits along the Godavariand the Manairrivers; Gondwana formations along the NW-SEGodavari graben or faultedthrough consisting of sandstones, red claysand shales. Puranarocks, Pahhela formations which are seen exposed in a main fault trending along the Godavari at Ramagundamand consistof limestoneswith shaleintercalations. The Archeanswhich are mainrocks consist of granite,gneisses and schists. Besidesquartzite dykes are also observedacross the granitecomplex in severaldirections.

2.2.3. Physiography: The commandarea presentsa pictureof gently undulatingplain dotted by hills. The general height of the plateau rangesfrom 200-350 m above mean sea level and slopesgently towards the Godavari.79% of the commandarea above LMD and 93 % of the commandlower down has slopesof less than 1 percent. Physiographicallythe area may be divided into three main landscapeunits viz., rugged landscape,undulating landscape and gently sloping landscape. The rugged landscapeoccurs in the west and northof Karimnagar.The undulatinglandscape occurs in the east of Karimnagarand the south of the Manairriver. It consistsof moderatelyto gentlyundulating uplands with isolatedresidual hills interfluvesand narrowvalleys. The gentlysloping land scapeis in the flood plainsof the Godavariand its tributariesbetween Peddapallito Mahboobabadin north-west-south-eastdirections. These gently sloping plainssupport deep red and blacksoils.

2.2.4 Soils The soils in the commandare derivedfrom two parentrocks - blacksoils of granitic origin and red soils of sandstoneorigin. Detailedsoil surveyshave been carriedout in 1963-75.Recently the AndhraPradesh Remote Sensing Application Centre, Hyderabad has also attemptedto interpretthe soils throughsatellite imagaries. 14 mappingunits have been identifiedusing the availableinformation. Land irrigabilityclassification has alsobeen done. About93% of the areais irrigable.70% of the commandarea is classified underclass-ll.

2.2.5 Drainage: The commandarea is drainedby the tributariesof the Godavariand the Krishna rivers. Peddavagu,Salivagu, Morancha vagu and the Manairare the importanttributaries of the Godavaridraining the command. The drainagepattern in the areashows distinctly the threetypes such as dendritic, trellisand parallelto sub-parallel.

2.2.6 Climate: The climateof the commandarea is tropical,characterised by hot summerand dry winter. The mean daily maximumtemperature during summer is 410Cand minimum 28oC.The meandaily maximumtemperature during winter is 300Cwhile the meandaily minimumtemperature is about 150C. The relativehumidity of the area is generallyhigh duringthe southwestmonsoon period. The rest of the year, it is dry.

9 2.2.7 Rainfall: The average annual rainfall in the command area varies between 900 mm and 1100 mm. About 81% of the annual rainfall is received during the southwest monsoon period of June to September and the rest during the northeast monsoon and summer period. The mean annual rainfall at Jagtial, Ramagundam, Manthani, Sultanabad and Karimnagar are 1170, 1133, 1095, 1025 and 1033 mm while for stations below LMD it is 876, 878, 959 and 1106 mm at Huzurabad, Warangal, Parkal and Mehaboobabad respectively.

2.2.8 Population: The Kakatiya Canal under SRS Project serves parts of the three districts of Nizamabad, Karimnagar and Warangal with population of 2.04 million, 3.04 million and 2.82 million respectively 73% of the population is rural. Cultivators constitute about 15.2% of the total population of the three districts. Agricultural labourers account for another 17.40%. The total populationin the project area is 4.05 million. The farm populationconstitute 70% of the total project population. They hold 0.70 M ha (an average of 1.22 ha per farm holder). 62 percent of the farm holders are marginalwith average land holding of 0.44 ha. Small farmers constitute the next largest group 22% with average land holding of 1.40 ha. Other categories which constitute 16% of the total, farm holders occupy 53% of the area, an average of 0.69 ha per farm holder. Districtwise the percentage of farm holdings vary from 16.70% in Nizamabad, 14.7% in Karimnagarto 12.6% in Warangal.

2.2.9 Agricultural Activity: The economy of the state in general and the sub-project in particular, is agriculture based. The commandarea of SRS projectis in the drought prone Telangana region. Around 80% of the rainfall (700 mm) is received in June-September which is highly erratic both in terms of time and space. Before the construction of SRS, most of the area was rainfed barring small patches under a few tanks and wells. Construction of SRS Dam and canal system in part has brought considerable benefitsto the area although the full benefit is yet to be realised. Increase in yield is also observed.

2.2.10 Other Activities:

Industries: Telangana region of the state is industrially backward and there are hardly any industries in either Karimnagar or Warangal district covered by SRS. There are some factories based on mining and/or forest produces. There were 1664 registered factories between them which work out to be 13.3% of the state while the districts occupy 14.8% of the area. At present there are about 325 Nos. of Agro based industries such as seed processing,food products,tobacco products, Rice mills and Oil industriesetc. in the region.

10 Mining: Telangana region of the state has some mineral resources besides coal in Ramagundamregion of Karimnagardistrict. The productionof coal during1990-91 from this regionreached a level of 7 milliontonnes, nearly 40% of the state'stotal production. Someother minerals are also beingextracted. Limestones were taken outto theextent of I milliontonnes (10% of the state)in Karimnagardistrict.

Forestry: A well establishedforest organisationis taking care of protection,development and managementof the forest in the districts. 2.2.11OBJECTIVES AND NEEDFOR R&R The projectaims at modernisationof commandto an extentof 1,65,000ha above the LMDand development of 1,63,000ha below LMD.The acquisitionof landrequired for the developmentof new commandbelow LMD uptoKm 267 includingthe distributorynet work,took place long back and worksconstructed prior to AP-II. Landacquisition especially for completionof balanceconveyance works betweenKm 267 and 284 and distributory net workviz., DBM31, DBM37, DBM38, DBM40, DBM42 to 47 and DBM48 (part)might have affected the people which require either rehabilitation or resettlement and rehabilitation.

11 APPROACH FOR RESETTLEMENT& REHABILITATION

Since land acquisition is going to affect large nurnber of people, Governmentof AP has taken all preventive measures to avoid large scale displacement and minimise the hardship. In view of this, though the Government of A.P. proposedto construct reservoirs such as Gorakallu and also to raise the FRL of Owk Reservoir to 227 m level under S.R.B.C., these proposals have been dropped to avoid likely displacement of people. Other sub-project (SRSP) also does not contain any Reservoirs in the reaches involved, and may not involve any involuntary displacement. Therefore the new Project does not envisage major involuntary displacement other than ones that have already taken place under A.P. 11Irrigation Project. However there may be people who might have not been displaced but have been economically affected by the acquisition of lands for canal and road net work. With a view to assist such affected persons underA.P. Ill Irrigation Project, Government of Andhra Pradesh adopted a Policy for Economic rehabilitation of project affected persons. Since the action plan envisages economic assistance to the affected people as per the Policy frame work and such other ameliorative measures, the action plan for the project is designated as Project Affected Persons Economic Rehabilitation Programme. In view of the importance of economic rehabilitationof the Project affected persons and in order to have smooth progress of works, and need for arranging continuity of flow of funds, following strategy of finalisation of PAPERP for A.P. Ill is adopted. 1. Conducting Socio Economic Survey of the persons from whom land has been acquired or persons affected indirectly by the construction of Main Canal. 2. Conducting Socio Economic Survey for the affected persons due to land acquisition already completed and people likely to be affected under distributories and related activities in Block-IV and Vil of S.R.B.C. 3. Preparing the Action Plan for the Main Canal of S.R.B.C. and Block IV and Vil of S.R.B.C. 4. Extrapolating the results of Socio Economic Survey of Block IV and Vil to remaining blocks namely Block 1,11, Ill, V to VIl and IX to XVI. 5. Arriving at the financial projections for the remaining Blocks of S.R.B.C. 6. Based on the results of S.R.B.C. Projections, preparation of financial outlay for the PAPERP of SRSP. As indicated above the present action plan mainly deals with Main Canal and Block IV and Vil of SRBC and financial projections for the rest of the Blocks and SRSP, based on the above study results. 3.1 SOCIO ECONOMIC STUDY: In order to study in depth the adverse impact of the Project construction on the community and the people affected due to acquisition of lands, including patta, revenue and forest lands together with the possibility of finding the availability of land for providing asset based assistance and options based on the perceptionof the affected people, Tribal Cultural Research & Training Institute (TCR & TI), Hyderabad has been entrusted with the assignment of conducting detailed socio economic survey of the canal affected persons

12 as per the terms of referenceunder SRBC sub-projectvide G.O.Ms.No.314I & CAD (PW) Dept.dated 2/12/1994. The socioeconomic survey is proposedto be conductedin two phasesnamely (1) the completionof censussurvey of PAPsfor land acquiredupto date underthe main canal and a full censussurvey of all land to be acquiredunder the ongoingworks for BlocksIV and Vil of SRBCand (2) completionof surveysfor PAPs encompassingall lands still to be acquired/kA Project Affected Persons Economic RehabilitationAction Planis proposedto be preparedfor the first phaseand a forecast' indicative udgetfor the phase IL. (* in bcoth sub ?orojects and already as acquired under s-T.) 3.2 METHODOLOGY OF SOCIO ECONOMIC STUDY: Initially,extent of patta lands,Govt landsand forest landshave been ascertained from L.A. recordsfor the componentsof canals.In orderto enableTCR & TI, Hyderabad to conduct socio economicstudies. The land acquisitiondetails coveringabout 4172 awardeesare collectedfrom the land acquisitionrecords of Special Collector,Kurnool and computersedat NationalInformatice Centre (NIC), Hyderabad. The awardeesare spreadover about 48 villagescoming under twelve (12) mandalsof Kurnooldistrict. In order to facilitatesmooth, effective and timely completionof surveys,the Engineering -Wing of the Project,Spl. DeputyCollector, Land AcquisitionUnit and MandalRevenue Officersare pressedinto service. All the districtofficials connected with landacquisition, land recordsand the registrationunder the leadershipof the DistrictCollector, Kurnool and Joint Collectorand AddI. Dist. Magistrate,Kurnool were involvedin conductingthe studyin a time boundmanner and furnishingthe data requiredby them. The surveywas conductedduring the periodfrom 5/12/94to 5/1/95, in the first leg coveringthe affectedpersons under the maincanal and the peopleaffected in Block IV and Vil duringthe secondleg of surveyfrom 9/1/95to 24/1/95. A team of investigators were againsent to the field to cover left over casesduring 3.3.95 to 14.3.95. The survey wasconducted by 8 teamsbesides another team of womeninvestigators. The servicesof four specialistsincluding a woman sociologistwho are expertsin respectivefields are also utilised. The survey operations were conducted under the control of the Director, TCR & TI, Hyderabad,A P Organisationalchart of the studyteam -and scheduleof study is given in AnnexureII. -Thevillage wise coverageof survey is given in annexure III and III-A. A well designedschedule has been canvassedamong the affectedpersons in the villages by door to door interviews. The participatoryrural appraisalmethod has been adoptedfor ascertainingthe detailsand perceptionsof the affectedpersons. The consultantsduring the field visit in three spells could contact 2876 Project AffectedFamilies under main canal and 1092under Block I V & VIII, as againstthe number of awardeesindicated as4172 undermain canaland 1224 under BlockIV & Vil as per the RevenueRecords and LP Schedulesprepared by the Department. Out of them schedulesof 240families couldbe canvassedunder main canal and 708 underBlock IV &VilI. Followingare the reasonsfor the differencebetween number of awardeesas per the LA recordsand numberof schedulesthat couldbe canvassedby the consultants. 1. Coverageof someawardees in morethan one awardbecause of acquisition of his land probablysituated at differentlocations 2. Some of the awardeessettled elsewhere and couldnot be contacted. 3. Some of the awardeesrefused to furnishthe informationand hencecould not be covered.

13 4. Some of the awardees were not available during the survey and could not be covered. 5. Some awardees whose whereabouts are not known and hence could not be collected. The socio economic survey in SRBC command including Block IV & Vil have been completed and after due analysis of the data, the consultants have finalised their report. Depending on the outcome of the analysis, the conclusions were arrived at and recommendationsmade by the consultants. Based on this and keeping in view, the policy of the Govt. of Andhra Pradesh, the action plan for project affected persons economic rehabilitation programme has been prepared.

14 DIRECT AND INDIRECT BENEFITS TO PROJECT AFFECTED PERSONS UNDER SRBC.

The Projectarea depending on the Irrigation benefits can be divided into 2 Sectors. The first Sector comprisesof Main Canal in 17 villagesin Pamulapadu,Joopadu Bunglow,AtmckWr Midthurand GadivemulaMandals of the Project in which there is no provision for irrigation facilities. The second sector comprises of 31 villages in Panyam, Nandyal,Banaganapalli, Owk, Koilkuntla, Kolimigundla and Sanjamala Mandals in which all the villagesfrom whom land is being acquired are getting benefitted by the creation of irrigation facilities of SRBC. The sector wise villages are given in Annexure I. There are number of direct and indirect benefits with the construction of project. The important benefits are as follows:

1. HIGHER YIELDS: The project would increase the cropping intensity from 103% to 157% and introduction of irrigation would increase the yield. Higher yields and increased irrigation intensity would result in higher agricultural production, leading to higher income and consequent improvement in standard of living. 2. STABILISATION OF AGRICULTURE: Since the project is going to remove the uncertainity of raising crops in the drought affected famine stricken areas, the agriculture is expected to be stabilised, thus leading to drought proofing in the project area.

3. EMPLOYMENT OPPORTUNITIES: Large scale employment opportunities are generated both during the construciton and after completion of the project due to increased cropping intensity.

4. ADDITIONAL WATER RESOURCES: The proposed irrigation system would convey about 19 TMC of water in the project command. The annual gross ground water recharge in the project area will be of the magnitudeof 116.65 MCM out of which 99.17 MCM can be annually utilisable. This would improve ground water availability in the command.

5. FISHERIES AND AGRICULTURAL RESOURCES: The construction of reservoirs would provide substantial potential for fish farming.

6. ADDITIONAL HABITAT FOR AQUATIC WILD LIFE: The increase in the water spread area will accrue an additional habitat for aquatic wild life including migratory birds and resident species. 7. RECREATION AND TOURISM POTENTIAL: Owk reservoir which is on the way to Puttaparthy, a piligrimage centre can be developed for small scale tourist spot. 8. OTHER SOCIO ECONOMIC BENEFITS: Completion of the project will improve the quality of life in the command through sustainable agricultural development and results in food security in the command.

15 PROJECTAFFECTED AREA

SRBC starts from Banakaclierla cross regulator in pamulapadu Mandal and terminates at km 141 after traversing through a bypass at Gorakallu valley and a balancing reservoirat Owk valley. The total commatnd of the project is divided into 16 blocks covering 48 villages in 12 Mandals of Kurnool District. The village wise, Mandal-wise details of Land acquired under the project for the main canal and for the Block IV & VIII are given in Annexure IV & V. 5.1. MAINCANAL As seen from the table, there are total 48 villages which are affected due to land acquisitionfor the project. As per the Socio-economicsurvey 2873awardees were covered out of4172 under main canal and 1092 were covered out of 1224 under Block IV & VIII. Thus,socio-economic profiles of 74% of the awardees were collected and analysed for the extent of land acquisition and its impact in the project area. As per the socio economic survey, an extent of 3732.582 acres of private land has been acquired from out of total land of 18,667.69 acres held by the land owners under main canal. In other words, about 20% of the land holding was acquired on an average from the project affected families. Similarly, an extent of 414.19 acres of Government assigned land was resumed from the project affected families from out of 687.905 acres held by them. In other words, 60% of the assigned holding hield by the project affected persons was resumed for the project. Further 102 houses have been acquired, thus displacing 102 families by the project. Out of the displaced families, 97 belonged to a hamlet of Vanala village in Pamulapadu Mandal and remaining five are from different villages. About 17 irrigation wells have been acquired including 13 handpumps and 11 other structures suchias pump shed etc., from the Project Affected Persons. 5.2. BLOCK IV & VilI The distributory network covers 4 Mandals and 12 villages in which land is proposed to be acquired from 1224 land hiolders.Out of whiich 1092 have been covered by the socio economic survey, thiat comes to 89% of the project affected families. An extent of 339.64 acres of private patta land has been acquired out of 8372.06 acres held by the project affected persons. In other words 4% of the land holding will be acquired on an average from the Project Affected Families. Similarly, 42.57 acres of assigned land will be acquired out of the total holding of 126.09 acres which comes to 33% of the assigned land holding. About 3 houses will be acquired under Block IV & Vil in addition to three other small structures. 5.3. IMPACT OF THE PROJECT ON SOCIAL INFRASTRUCTURE.

5.3.1. Agricultiral linfrastructure: In view of rain fed agriculture, presently existing in the area, the agricultural infrastructuresuch as input supply centres, farm machinery service centres etc., are scarce in the project area. Based on thie aiialysis of the existing infrastructure, it works-out that only 5% of the command villages have seed depots within the village and 1 1% of them are at a distance of 1 to 5 Kms, 46% of them are at a distance of 6 to 15 KMs and balance beyond 15 KMs. Similarly, 10 % of the villages alone have fertiliser and pesticide depots within the village, 20 % have at a distance of 1 to 5 KMs, 70% at a distance of morethan 6 KMs.

16 Due to the advent of the project, agriculture infrastructure facilities are bound to be improved due to sheer demand supply forces and the project is going to have positive impact towards these amenities. The project is also going to open up new research avenues in the nearby research stations and throw up innumerable training opportunities for Krishi Vignana Kendra at Nandyal and Banaganapalli.

5.3.2. Animal Husbandry: There are three veterinary hospitals and 18 Livestock Supervisory units and 55 rural Livestock Units in the command which are in no way affected by the project. The demands for these facilities are bound to increase after completion of the project because of the obvious reasons. More and more Villages are going to have exclusive Veterinary hospitals/Livestock supervisory units/ Rural Livestock Units after the completion of the project, as against very low levels of infrastructure as existing now.

5.3.3. Roads and Transport: The roads and transport are life lines of economy of any area. The analysis of the area indicates that 89% of the villages are connected by pucca roads and road transport. Moolasagaram and panyam are also connected by rail. The project is in no way going to effect the road and transport infrastructure adversely and in converse the ayacut road net work which is the component of the project going to improve the communication facilities and better access to all the villages of the command. The access of the villages are in no way going to be affected by the main canal and the distributories, as the existing passages and approaches are protected by constructing either single lane or double lane bridges. As reported elsewhere, there are about 40 single lane and double lane bridges aiding the project villages to commute and communicate.

5.3.4. Medical, Public healthi and Drikiing Water: The socio economic survey of the project area has revealed that all the villages have drinking water source in the form of a open well or tubewell. The protected water supply is available in 15 villages of the project area. Due to the excavation of the main canal, especially at higher contours, where the depth of excavation is high, has affected the ground water table in the area, resulting in problems of drinking water availability in the adjoining villages especially during summer. This problem is a temporary phenomenon of the project . Vibrant agricultural activity is going to provide immense job opportunities for the rural folk. As seen from the above, the project construction is going to have positive impact rather than negative effects within and around the command. The people living outside the command, especially nearby areas such as Nandikotkur, Nandyal, Kurnool etc. would also be getting benefited after completion of the project in view of increased agricultural productivity and supply of raw material for Agro based industries and with release of water in the main canal the ground water recharge would replenish the depleted ground water table and would help in making drinking water available throughout the year. However, during the construction, the Panchayat Raj DepartrTientof Govt. of A.P. has takenup series of deep tube wells and borewells in order to reduce the problem of drinkingwater availability. The project area is served by two hospitals, one at Nandyal and another at Koilakuntla. Primary Health Centres are located at Gadivemula, Panyarn1,Maddur, Moolasagaram, Owk and Perusomala and dispensaries at Jaiakanur, Durvesi, Maddur, Moolasagaram

17 and sub-centres at Gorakallu, Panyam, Banaganapalli, Alamur, Mettupalli, Singanapalli and Owk. Number of private Medical practitioners are available in many of the villages. In addition to this, Community health centres are located in about 17 villages of the project area. The project has no adverse impact regarding the accessibility of these facilities to the project affected community.

5.3.5. Education and Communication Infrastructure: The socio economic study reveals that all the villages are served by primary schools and there are more than one school in 17 villages of the project area. High schools are presentin 12 villagesof the projectarea and Junior Collegesat Panyam, Banaganapalli and Koilakuntla. Since the command is nearby to the major towns, such as Nandikotkur, Nandyal and Banaganapalli,most of the project affected villages are being served by the Educational institutions available in these towns. The project is having no adverse impact with respect to accessability of the Educational infrastructure. All villages,except three namely Chennamukkapalli,Thirupadu and Obulapuram are connected by postal facility and 15 villages are connected by Telegraph facility. These facilities are not affected by the project construction and in converse it is going to improve the above facilities.

5.3.6. Access to Banks and Agricultural Co-Op Societies: Commercial banks are available in 12 villages of the project area and 14 are situated within a distance of 1 to 5Kms from these banks. Reset of the villages are served by the banks from a distance of more than 5 Kms. The agricultural co-operativesocieties are located in 16 villages and another 16 villages are served by a primary Co-op societies from a distance beyond 6 kms. The project is in no way going to affect adversely with regard to availing the project construction activity has created a vibrant economy in and around these villages which would throw up more and more self-employmentopportunities for the youth in the project affected area after completion.

18 THE LAND AND PROPERTY ACQUISITION

6.1. THE PROCESS OF LAND ACQUISITION: The land acquiredfor constructionof the canal system is identifiedby the Engineering wing of the SRBC and requisition for acquiring the required lands duly furnishing the necessary information in the requisition forms about the extent and survey numbers and villages of the lands required for the construction of the SRBC project will be sent to the Special Collector, Land Acquisition of the projects, Kurnool. On receipt of the requisition the Land Acquisition Officer (LAO) will depute his surveyor of the said land and structures there on and fix peg marks, and report to the Land Acquisition Officer about the correct survey numbers along with sub-division records with sketches of the land/ structures proposed for acquisition. Then sub-division records are sent to the Deputyinspector of Survey forverification and attestation ofthesame. Thereafter the Land acquisition Officer will call for copies of adangal (Record of Rights), RSR,10(1)Account and Land ceiling records of the concerned land to verify whether the land required is Govt. land, patta land and the ownership of patta land. If it is patta land, it is also to be verified whether the pattadar is attracted by Land Reforms Act, (AgricultureLandCeilingAct). Afterverification of all the above mentioned records, the Land Acquisition Officer prepares a draft notification under Sec.4(1) of Land Acquisition Act 1894. A draft declaration showing the particulars of land, its classification, structures if any, trees if any, existing on the land is prepared after inspecting the said land along with the Surveyor and Engineering staff etc., under the section 6 of Land Acquisition Act 1894. The LA Officer submits the draft notification and declaration proposals to the Special Collector, (LA) Kurnool for his approval and for onward transmission to the Government for their approval and causing its publication in the District Gazettee. If the land is urgently required for acquisition for the project,the LA Officer submits draft notificationand draft declaration simultaneously. There are three ways of causing publication of draft notification and draft declaration

1. by publication in two local dailies of regional languages through Commissioner of Informationand Public Relations ofGovernmentofAndhra Pradesh. 2. by publication in the district Gazettee by the SpI. Collectorand 3. by issuing a public notification in thevillage. And all the three modes of publication are compulsory for every acquisition. The last date of publicationof the draft notificationand draft declaration is considered for the purpose of LA Act. Then the Land Acquisition Officer will call for the land sales statistics, relating to the village from the Sub-Registrarof the Rigistration Department to examine the trend from the market rates for the village concerned. Simultaneously the LAO issues notices under section 9(3) and 10 of Land Aqcuistion Act to the concerned parties for award enquiry. There will be fifteen days gap between the date of service of notice and the date of enquiry. The LAO will fix up the market value of the land on the basis of sale transactions of the lands of similar category held during the period of three years preceeding the date of the last publication of the draft notification. The LAO will thus fix up the market value of the lands and submit the preliminary valuation statements showing the details of the rates fixed and the reasons there of to the Special

19 Collector, LA for his approval. The Special Collector, LA will inspect the lands under sale transactions registered preceeding the last three years to verify the proximity and fertility etc., and approves the preliminary valuation statement submitted by the LAO, with due modifications if any. The LAO after completing the award enquiry will verify the revenue records to ascertain the persons in possession of the land and ownership of the same. He will then send draft award to the Sub-Collector for approval of the same. After the draft award is approved by the special Collector, the LAO processes the award under the section 1 of the L.A.Act in the capacity of Collector,and pays the compensation to the awardees in the form of cheques. The award has to be passed within the period of two years from the date of publication of draft notification. Otherwise, the draft notification is deemed to have been lapsed. Thirty percent of the market value of the land is payable towards solatium under Section23(1) of the LAAct and 12% additional market value under Section 23(1) from the date of notification to the date of award or taking possesion of land whichever is earlier. Under section 28 of LA Act interest is payable @ 15% thereafter from the date of taking possesion of the land or till the award or the proposed date of payment. The awardee is intimated the fact of passing of the award. Under the section 12(2) of LA Act showing the amounts awarded. In case the awardee is not satisfied with the compensationamount awarded to him, he receives the award amount underprotest and files a petition before the LAO under section 18 of the LA Act for refering the case to the civil court for proper adjudicationwithin six weeks from the date of the passing of the award under section 12(2). The total extent of land required for the SRBC Main Canal includingOwk reservoir comes to 3676 ha. In addition to this an extent of 154.74 ha will be acquired for block IV & Vill. Land acquired under the SRBC Main Canal and proposed to be acquired under block IV & VIII are presented in the annexure VI .The village wise details of other acquisitions such as homestead land, houses, pumpsheds, wells, trees, crops etc., are presented in the Annexure VIl. Whenever the assigned Government lands are resumed for the purpose of the project, the affected people will be paid compensation as per the standing orders vide G.O.Ms No.1307, dated 23-12-1993 by a seperate proceedings. Whenever structures of the encroachers of Government land is resumed, reasonable exgratia payment is made to compensate the cost of such structures. Under SRBC Project, the land has been acquired for constructing the main canal, distributories, road net work and Owk balancing reservoir. Since the project is on going and part of the works have been completed, majority of the land required for the project is already acquired. The Government has fixed the cut-off date, for inclusion of major children as project affected persons, as the date of 4(1) notification under LA Act. However , in the present case, since the part of the land has already been acquired long time back on different dates, spreading from the year 1985 till date, the age for considering major children has been taken as the time of conducting Socio economic survey. This is the most liberalistic view of Government of Andhra Pradesh in order to ensure that the affected people will be economically rehabilitated irrespective of the date of 4(1) notification. 6.1.1. Fixing valuation of Land, Structures, Trees etc.: The acquisition for construction of the Project involvedacquiring houses, wells, handpumps and other structures besides the land. In addition to the land 109 houses, 17 wells, 13 handpumps and 11 other structures have been acquired for the purpose. The detailed breakup of trees and crops are not available as they are clubbed

20 alongwith the total compensationwhile passingthe award. For fixingthe valuationof land, structuresor any other itemssuch as wells,trees etc., the date of 4(1) notification will betaken for decidingthe marketvalue. 1Themarket value of landwill be fixeddepending on the sales statisticsof similarly situatedlands in the nearestarea possibleby duly gatheringthe sales statistics from the RegistrationDepartment. To this marketvalue, an amount of 30% solatium will be added to compensatethe compulsorynature of acquisition and 12% of additional market value will be paid from the date of 4(1) Notification till the date of award or till the date of takingpossession whichever is earlier. Interest at the rate of 15%will be paid from the date of takingpossession of the landtill paymentof compensation. The valuationof structureswill be done based on the normsfixed by the Engineering Department whichwill be updatedfrom time totime. The values are fixed by taking thetypeofstructure, time of construction and qualityof materialsused for theconstruction etc., and totalamount willbe calculated for the total plinth area. The valuationfor trees will be fixed based on the norms fixed by the AgricultureDepartment which basicallydepends on the age of the tree and numberof trees and the production of the trees in future. Compensationforthe crop, since it is one time matterwill be decidedby taking the stage of the crop growth and type of crop, by the LAOwhile valuation of the land.

6.1.2. Detailsof AppealsPending: As per the Land AcquisitionAct, the land ownersreceiving the amountunder protest at the time of passingof awardcan requestwithin 6 weeks from passingthe awardto refer their cases to the Sub-courtin orderto decideappropriate compensation. The LAOswill be filing the Section 18 reference cases to the Sub-courts as and whenthe requestreceived from the Awardees. As seen from the socio economic studyconducted in the projectarea, there are about 1729cases filed in variouscourts, out of 3517 awardees,ofwhom331caseshavebeendecidedbytheCourts, enhancing the land compensationfixed by the LandAcquisition Officer concerned. In these 331 cases,the awardamount of Rs. 90.63 lakhspaid by the LAOwhile passingthe award hasbeen enhanced by theCourts to 285.94 lakhs. Depending on the reasonableness of the Court order, the Government decides to file appeals againstthe lower court orderor paysthe enhancedamount in thecourt, which will be withdrawnby the awardqes. Thoughthe processof litigationis a longdrawn process, every landholder, who isaggrieved of lowercompensation have got right to go to the Court and get the compensation enhancedbased on due enquiryby the Court. In such cases, the Government will be paying interest on the total compensation till the decretalamount is depositedin the Court as per the directions of the respectivecourt. Village-wisedetails of court casespending, cases decided and enhancedcompensation are givenin annexureVilI 6.1.3. Detailsof OtherLands: In addition to the private land acquired for the purpose of the project, Governmentlands have also been resumedforthepurpose.Asdescribed elsewhere an extentof 414.19 acres of Governmentland has been resumed for constructingthe main canaland 42.57 acres underBlock IV and Vil. In addition to this, an extent of 726 acres of Governmentporamboke land which is free of any occupationhas been resumedfor the construction of the project. Similarly,an extent of 664 acers of forest land has been takenover for the construction of the project, for which a compensatory afforestationplan is preparedas describedelsewhere. Except these lands,no other porambokeor commonlands have been acquiredfor the project. The

21 Govemmentland which is underoccupation of the people in various villageshas been resumedby a separateproceedings by paying compensation as per the existing norms ie., as per the G.O.Ms.No.1307,dated 23-12-1993TheotherGovernment porambokeland has been resumedand suitablemutations will be affectedin the revenue recordsin order to showthe transferto IrrigationDepartment. As far as forest land is concerned, the possessionwill be takenoverdepending upon the requirement of construction of the projectand thetitle, still will be vestedwith the ForestDept. Forthe purposeof land acquisitionthe assigned landshave also been taken on the similarlines of acquisitionof private lands, but, for the differencein procedureof acquisition. For the purpose of preparation of package for their resettlement and rehabilitation, they have been treated at par and as if private land has been acquiredfrom them. Therefore,for the sake of convenience,all other discussionsand action plan havebeen drawnwithout treating them separately.Except the peoplecovred in the actionplan, no other personis livingas encroacher on the remainingGovernment poramboke land. Thesocio economic survey has also indicatedthat no customaryor traditionalrights have been affecteddue to the acquisitionfor the project. 6.1.4. Utilisationof Compensation: Since Land Acquisition has been completed over a period of time and the compensationreceived by the land holdersmust havespent for various purposes. The studyof pattern of utilisationof compensationindicate the prioritiesand the needs of awardees.This would also revealwhether the compensationhas beenused for productive purposes. The pattern of spending activitywiseand communitywiseare given in the annexure As seen from the data, the numberof respondentswho spent the amountfor variouspurposes are varying. Dependingon the numberagainst each itemof utilisation, the item of utilisationcan be prioritisedalongwith the percentageas givenbelow: 1. Food 26.2% 2. Loanrepayment 12.6% 3. Wedding 7.2% 4. Expenditureon agriculture and purchaseof equipment 10.0% 5. Others 7.0% 6. Clothing 5.1% 7. Constructionof Houses 4.5% 8. Purchaseof agricultureland 2.9% 9. Medicaltreatment 2.9% 10. Education 2.7% 11. Savings 2.5% 12. Purchaseof livestock 1.8% 13. Religiousfunctions 1.7% 14. Constructionof wells,bore well & motor 0.9%

22 c 15. Self employment 0.3% 16. Consumable items 0.3% As seen from the above, majority of the respondentshave spent their compensation for consumption needs and others religious activities. About 25.9% of the respondentshave spent their moneyfor productivepurposes such as purchase of agricultural land, house sites, purchase of equipment, construction of wells, purchase of live stock etc. About 2.5% of the respondents have repaid their loan from out of the compensation received.

23 PROJECT AFFECTED COMMUNITY

The project affected community mainly belonged to three religions, namely, Hinduism, Christianity and Islam. Hinduism is the original native religion of the area, where as Islam and Christianity have appeared later with advent of Muslim rulers and Britishers.The christiansare mainly the converts from socially backwardclass, especially ScheduledCastes. The study area also comprisesof small populationof tribal community who are having mainly Hindu manners, customs and traditions and at the same time maintain their cultural identity. The Hindu population of the village can be divided into number of castes and subcastes and various caste groups as presented hereunder: 1. Brahmins 2. Vysyas, 3. Kapu (Reddy and Kamma) 4. Backward class such as Balija, Yadava, Kuruba, Ediga, Padmasali, Thogota, Sathani, Thamballa, Bestha, Vaddera, Uppari etc. 5. Viswa Brahmin (Kamsali, Vadla, Kammara) 6. Kummari, ;Mangali,Chakali,Medari,Boya, Dudekula 7. Dasari, Dommari, Pitchikuntla, Jangam 8. Yerukala, Sugali, Chenchu 9. Scheduled Caste The Brahmins occupy the highest caste hierarchy who are traditionally priests and men of learning about Hindu scriptures. Vysyas are basically traders and money lenders. Kapusmainly Reddy and Kamma are agriculturalcommunities who predominate the project area. In view of land ownership, these groups play prominant role in village economy, social and political life. Backward communitiesbelonged to various occupational groups. Balija community are predominant in the project area. They pursue various occupations ranging from cultivation to trading. Some of them are traditionally shepherdsand wool makers. Ediga communityare traditionallytoddy tappers and liquor distillers. Kurubas are also shepherds and wool makers. Padmasalis and Thogotas are weavers. Santhanis are priests in Vaishnava temples while Thamballas are music players in shiva temples. Bestha community are engaged in fishing. Vaddera community are stone cutters and Uppari are traditionally salt makers. The other caste groups are basically functional groups such as barbers, washermen etc. Among the Scheduled Tribes the predominent groups in the area belonged to Chenchu, Yanadi, Sugali and Yerukala which are notified tribes. About 27 families are affected due to acquisition of the land under the project. Most of the affected families belong to Yerukala community and small number to other groups. Yerukalas are found in 20 villages of the study area who are traditionally basket makers and swine herders. They have a dialect of their own, but has gone to disuse over a period of time. The tribe is divided into number of sub-tribes on the basis of occupational specialisation such as Dabbu (bamboo basket makers), Chuvva (basket makerswith date palm), Kuncha (makers of weaving brushes), Karivepaki (traders of kari leaves), Nara (rnakers of

24 fibre for rope making), Bhajanthis(musicians). Some of them have turned to agriculture in view of difficultiesin continuingtheir traditionaloccupation. The Scheduled caste groupoccupies the last rungof castehierarchy existing in the projectarea. They are basicallyagricultural labourers and weavers. They also do the leatherwork. The total populationcovered under the studyarea is 2.04 lakhsas per the 1981 census including the population of Nandyal. Total numberof housesin the project areaare 24,655as per 1991census. The density of populationis 155per Sq.KM.The averagehouse hold size works out to 4.9. The ScheduledCaste and ScheduledTribe populationform the core of the weakersection of the society,while bulk of the village populationof the area belongedto othergroups. Scheduledcastes form about 19.1% of therural population and ScheduledTribes constitute 3.5 % of thetotal population inhabiting the project. The sex ratioin termsof females perthousand males in the areaworks out to 949 as against the sex ratio of 953 femalesper thousandmales in the Kurnool District. The literacyrate in the projectarea is 35.20%. About 50.3% of the work force is engagedin agriculturalactivities of whom 22.4 per cent are cultivators. 7.1. ECONOMIC CONDITIONS OF PROJECT AFFECTED COMMUNITY The economic conditions of the area mainly depends on agriculture, as majorityof the peopleare dependenton agricultureor agriculturerelated activities. The land beingthe mainsource of livelihood,the ownershippattern would determinethe economicstatus and social status of the people in a particulararea. Therefore, the currentstatus of Land holdingdistribution in the area operatedby each identifiedsocial groupand the type of farmersare releventfor assessingthe resourcebase of the village and socioeconomic studies of the socialgroups and classes of the farmersin the study area. Similarlyother items such as one of agriculturalimplements, livestock etc., are also important decidingfactors in economicstatus of the land holder. Brief description of the above items and status of projectcommunity with respectto each item is given below 7.1.1 Land Holding

The patternof land holding of the projectcommunity is giventable. k

Sl. No Type of Farmer No. and Area (in Acres) of operationalholdings

Total Scheduled Scheduled Caste Tribe

No. Area No. Area No. Area

1. MarginalFarmers 12207 16818 2811 3413 219 287 (36.43) (6.9) (62.3) (27.2) (55.3) (19.4)

2. Small Farmers 7758 28228 1044 3668 93 322 (23.15) (11.6) (23.1) (29.5) (23.5) (21.8)

25 3. Others 13541 198494 658 5462 84 866 (40.13) (81.5) (14.6) (43.6) (21.2) (58.8)

33506 243540 4513 12545 396 1475

It is vivid from the above table that the marginalfarmers constitute 36.43% in the SRBC Ayacut area and own 11.6% of the area;the smallfarmers constitute 23.15 % of the total holdingsand own 11.6% of the total area. Other farmersare holding40.42% of the total area. The other farmers constitute 40.42%,andthey own 81.5%of the total extentin area.Among the scheduledcaste, 62.3% are marginalfarmers and they own 27.2 % of the total area, while23.1% of the schedulecaste small farmers are owningabout 29.2% of the total area.Among the scheduledtribe farmers 55.3% belongto marginalfarmers who own 19.4%of area and 23.5% of smallfarmers owning about21.8 % of the total area The analysisofdata of SocioEconomic Survey gives the distributionsof various socialgroups amongvarious holdingsizes. The distributionof land holding castewise amongthe projectaffected families based on the dryland holdingbefore acquisition of the land is givenbelow:

Community Land Holding

0-3.75 3.76-7.5 7.6 & above Total

SC 349 (82.5) 53 (12.5) 21(49) 423 (25.8%) (11.8) (3.5) (17.6)

ST 18 (66.7) 5(18.5) 4 (14.8) 27 (1.3%) (1.0) (0.7) (1.1)

BC 548 (58.2) 210 (22.3) 184(19.5) 942 (40.5) (46.6) (30.7) (39.2)

Others 439 (43.3) 183 (18.1) 391 (38.6) 1013 (32.4) (40.6) (65.2) (42.1)

Total 1354 (56.3) 451 (18.8) 600(24.9) 2405

As seen from the table, among the marginalfarmers 25.8 % belongedto scheduled caste, 1.3% to scheduletribe, 40.5% to backwardcommunity and 32.4 % to other communities.Similarly, among small farmer's group, 86 % of the farmers belongedto otherbackward community or othercommunities and only 11.8%to schedule caste and 1% to schedule tribe community.Among the medium and big farmers, scheduledcaste constitute 3.5 % and scheduletribe comprises of 0.7%and rest being backwardclass communityand otherclasses. Among the schedule caste farmers, 82.5% of the farmersare marginal,12.5 % are smalland only 4.9% are of mediumand largetype. 26 7.1.2. CroppingPattern The croppingpaftern of an area indicatesthe status of agricultureof that area. The extentand the food crops indicatethe subsistancelevel of economy of that area. The larger the areaunder dry crops, greater the dependencyon the rainfall. Important cropsof the areaare groundnut, cotton,Sorgham. Seteria, redgram, sunflower, tobacco etc.The area is mainlycereal based especially minor millets and ricegrown under existing irrigationfacilities. 7.1.3. AgriculturalImplements* Normally in the areas where agriculture productivityis high, theagriculture is machanised. The present status of use of agriculturalimplements in the study areahas been collectedfrom BMSRof SRBC,command area whichitself is basedon livestockcensus based on censusof 1987for the SRBCproposed command area. Even thoughthe SRBCis not identicalwith the presentstudy area the broadpicture that emerges from the BMSRof SRBCcommand area generally holdsgood for the studyarea also. The followingtable gives particular equipments availablefor 1000 hectaresof gross croppedarea.

SI.No. Nameof the agriculturalImplement No.of Implements.

1. Plough a) Wooden 71 b) Iron 10 Total 81 2. DieselEngine 2 3. ElectricPump sets 8 4. Tractors 2 5. HandSprays and Dusters 20 6. Powersprayers and dusters 2 7. PowerTillers 8. Seedcum fertilizerdrill 29 9. Powerdriven planting equipment 4 10. Powerdriven levelling equipment 3

As seen from the abovetable, there are 71 wooden and 10 iron ploughs for every 1000hectares of grosscropped area. There are 10 pumpsets(Diesel & Electrical) for every 1000 hectaresof gross croppedarea. There are 21 sprayersand dusters,29 seedcum fertiliser drills in use in the area for every 1000hectares of grosscropped area. But the positionhas changedconsiderably since 1987. 7.1.4. Live Stock: Live stock is essentialin agriculturaleconomy as it is usedfor variousagricultural operations like ploughing,manuring, threshing etc., besidesdairying. Therefore, the live stock is consideredas capital stockin income estimates apart from bovine animals.Other animals like sheeps,goats and birdslike hensand ducks also contribute to the rural economy.Therefore it is necessaryto find out the distributionof the livestock by category in the studyarea to assessthe resourcebase of the studyarea. Following table representsdistribution of Livestockby categoryin the study area.

27 7.1.5. Distribution of Live stock by category.*

SI.No. Category Total No.

1. White Cattle 21353 Male working 15406 2. Black Cattle 35199 Female milch 22362 3. (1) Sheep 15975 (2) Goat 20107 4. Poultry 69979

Grand Total 162613

The above table reveals that the black cattle is more preponderant than white cattle. In the total bovine population white cattle forms about 38% while the black cattle constitutes 62%. But in the case of Kurnool District as a whole white cattle form 58.6% and black cattle constitutes 41.4% of the total bovine. 7.1.6. Social adverse impact on scheduled tribes The project has affected only 27 S.T. families,most of them belongingto Yerukala community. Considering their major children, total numberof project affected persons belonging to S.T. Community comes to 30. Among them, there are 11 project affected persons, who have lost their houses and most of them are being in Vanala Village. The 2 displaced families belonged to Yerukala Community and the resettlemet and rehabilitationpackage is described under Valanla resettlement plan. 7.1.7. Adverse impact on role and status of Women Family is the basic and primary institution of the society. The joint family system is predominant in the project area. The women head of the family generally attends to kitchen work and also goes to the agriculture activities either as labour on daily wages or for supervising certain operations such as weeding, transplanting, harvesting etc. She will be helped in the kitchen by old aged women or widows. The women also attend to other activities also such as cleaning of food grains, harvesting of vegetables, dairy etc. Joint family system generally protects the old aged, widows and disbaled persons of the family. However the joint family system is fast disappearing with the advent of modern education and consumerism. The main function of a woman in a family can be listed as follows. a) Fetching Fuel, fodder b) Fetching water wherever protected water facilities are not available. c) Kitchen Work d) Looking after animal husbandary activities such as dairying, upkeep of cattle etc.

* Source: BMSR,DE&S, Hyderabad.

28 e) Wage labouror supervisionof agricultureoperations etc. f) Caringchildren and doing other household work. All important decisions are generally takenin consultaionwith woman member of a family,though it is not mandatory.Early marriages and dowrysystems are prevalent in the area. In order to assess any adverse impact of the project on the women and their perception about the project a seperate study was conducted through women anthropologistsby using PRA techniques in samplewages by dividingthe project area into two sectors, one beingthe areawhere no irrigationcomponent is available andother being with irrigationcomponent. Some of the majorperceptions are listedbelow. 1. They are awareof landacquisition for the projectand cameto knowthrough their husbands. 2. By and large the womenare notfavourable for landacquisition in sector1 and possitivein sector2 3. Some feel that the shortagesin the fodderin the area is mainlydue to the land acquisition. 4. In some reachesespecially at deep cut alignments,shortageof drinkingwater availabilitydue to decreasein water table is experie-ncec. Since there is no major displacementin the project exce-pt Vanala hamlet, thereare no adverse impact on the role of womenand theirstatus. The transitionalill effects of the projectsuch as low water table in deep cut reaches, fodder shortage etc. will be over come the momentthe project becomes operational. Governmentof A.P. hastaken up a protectedwater supplyscheme in deep cut reachat Mittakandalato amelioratethe problem of loweringwater table in the area. The rehabilitationpackages providing for economicsupport throughproductive asset grant and enablingthem to form into thrift groupsand economicsupport through revolving fund are some of the specialmemsuresfor improving the status of womenby increasingtheir levelsof income. Government of A.P. has givenequal status for majorgirl childand treatedas a seperate family irrespectiveof maritalstatus.

29 PROJECT AFFECTED PERSONS 8.1 Definition "Project Affected Person" means a person other than a displaced person who loses atleatfiminimum loss of holding, and is left tith less than t:ninimum economic holdin ' after the acquisition or of talcing over of lands from his,9her possession for the Project; "Minimulm loss of holding" means loss of a miniinum of 25% of the holding of a person -or the oroject compulsorily as on the date of not-.fication under the Lk Act. "Minimum Economic Holding" means a holding of 2 ha. of dry land or I ha. of irrigated land or an equivalent land thereof taking projected benefit into account. "Disolaced Person" means a person who since atleast one year or prior to the date of ,publication of the Notification under Sec.4 of the L.A.Act 1894, or to atleat 5 years prior to the date of taklng over f)r the project, possession of any land undlerhis occupation has beon ordinarily residing in a project affected villge and who has, on account of the acquisition of his/her land, including homestead land, or of taking ove~r of land from his/her possession been physica- lly displaced from suchi village. Family in relation to a displaced person/project affected person means persons fallinug in L-he follovwin 9 categories as on the date of public-3t-1on of Sec.4 notification or of taking over possession in respect of his/her lands/homestead in the Project affected village or of alienation from any land taken over for the project; i) the person who is displaced/affected and his/her szouse, minor children, minor brothers/sisters, father and mothlr and other memblers residing with him and who are depandent on him,/her for their livelihood; and ii) major cihild of the displaced/affected person wrho is more than 1,3 years of age irrespective of his martial status; 802 .CLASSIFICATIO1NOF PAFs I .Displaced 2.Land Holdiers 3.1M4ajor Child 4.-ncroachers and Others 5 .Destitutes/Aqed 8.3.PACKAGsE OF ENTITLEMENTSTh) EACH CATEGORY 8,3.1 Displaced persons i. Prov-isLon of house site of 3 to 5 cents area to all displaced fainilies free of cost. ii. Each displaced faiiiLly shall be provided with economic assis-tance of n5s.10,0O0/- on the pattern of weaker section housing progz'amme for the construction of a house at a new resettlement site in addition to per- mitting them -to use -tlhe ma-terial of the old structure. 30 iii. Provision of free transport facility to transport usable household material from the old site to resettlement site. iv. They shall be provided with maintenance allowance of Rs.500/- per month/for 9 months to cover their initial expenses till their regular economic activity gets streamlined. v. Cattle maintenance of Rs. 200/- per month shall be provided for a period of 6 months to maintain their cattle population. vi. Wherever a whole village or a group of families numbering not less than hundred are displaced, Civic amenities such as electricity, drinking water facility, internal roads, community building shall be provided at free of cost. vii. Resettlement centre to be provided with a Farm Service Centre (FSC) under the management of a Non-Governmental Organisation (NGO) or association of the displaced family members with an outlay of Rs. 2.0 Lakhs in order to provide services for various farm activities.

8.3.2. Land Holders i. Compensation at prevailing market value for the lands, trees, structures and other assets shall be provided. In addition, a sum equivalent to 30% of the value of compensation as solatium shall also be provided for the compulsory deprivation of the asset. ii. All PAPs under this category are eligible under land for land for allotment of Government or ceiling surplus land to the extent of loss or upto a limit of 2ha of dry land or 1 ha of wet land or an equivalent thereof, if available in the same revenue village. While alloting the land preference will be given to persons belongingto the SC/St. If Government land is not available in the project affected village, then a package of economic support programme will be implemented for improvingthe economic status of the displaced / PAPs in agriculture, industry, business, animal husbandry or service sectors. The package will consists of the items spelt out under para "Economic Rehabilitation Package". for land holders. iii. Full compensation for damage, if any, to the standing crops or trees due to the acquisition. iv. Payment of ex-gratia equivalent to market value to the assigneesof Government land whenever such land is taken over for the project purpose.

8.3.3. Major Child Major child as spelt out under definitions above are eligible for the economic rehabilitation package on par with the PAPs. The major child is treated as below poverty line PAP irrespective of the status (above or below poverty line) of the head of the PAF.

8.3.4. Encroachers and others They are eligible for economic rehabilitation package as detailed above on par with PAP affected due to land acquisition.

31 8.3.5. Destitutes/Aged Does not arise in the case of canal affected persons. 8.4 ECONOMIC REHABILITATIONPACKAGE TO EACH CATEGORY

8.4.1. Land Holders a) Productive asset grant of Rs. 5,000/- to all such displaced/project affected persons . This grant can be linked to bank loans in order to secure maximum assistance for their economic support programme. b) Preference in granting fishing rights in the proposed reservoir; c) Permission to take up horticulture or social forestry plantation in the foreshore area of the reservoirand alongthe canal banks and allow them to use its income; d) Provision of smokeless chullas free of cost; e) Initiation of group activity; and fl Pr vsion.of vocationaVItrainiinO elevant ecQnnmic activities. g)AlPTro. ec a eci 9r l es s 1a e orov±ced wi th mainte- nance allc.loance of R,.5u'X/- per month per fainily per 9 months. 8.4.2. Major Child Same as under(8.4.1) except provision under (d)

8.4.3. Encroachersand others Sameas under (8.4.1)above

8.4.4. Destitues and aged Doesnot arisein the case of canal affectedpersons.

Basis of Definition of PAP etc.: The underlyingbasis of definitionof the PAPsis relatableto sufferancedue to loss of land which is consideredas 25% of the originalholding which is consistentwith the definitionunder A.P.11. Irrigation Project and the land left with, after acquisitionwhich is consideredas 2 ha of dry landbeing the minimumeconomic holding for sustenanceunder the conditionsprevailing in the State.Statement showing the numberof PAPsunder each category is presented in Annexure - IX

32 ADVERSEIMPACTS OF LAND ACQUISITION

Though there is no major displacement due to the construction of the project, except a hamlet of Vanala village, the land acquisition has affected various social groups in terms of reduction of their land holding after land acquisition. The mobility of land holdings before and after acquisition has been analysed and depicted in Annexure X. As seen from the table, there were about 1101 awardeeswho were marginal farmers, 524 were small farmers and 784 were big farmers, out of total project affected families of 2409. As against this, the land acquisition for the project has left with no land with respect to 426 marginal holders hitherto and the balance 675 were still marginal holders. Among the small farmers, 53 have become landless, 206 have been reduced to marginalfarmers and leaving 265 in small farmer category. Similarly among the medium and big farmers, 14 have been rendered landless, 24 have become marginalfarmers, 134 have become small farmers, thus leaving 612 in the category of medium and big farmers. Thus, a total of 493 land holders were rendered landless in view of land acquisition and the remaining people have been affected in varying degrees. Marginal farmers have been reduced by 17% in absolute terms, as against the situation existed prior to land acquisition. Similarly, the small farmers have become less by 23% after land acquisition. In other words there is apparent downward movement of land holding size resulting in adverse effect on the income levels and production systems of the project affected people. Similarly, analysis has been done regarding the impact of land acquisition on the lesses and share croppers. There were very low number of people who were taking the land on lease and for share cropping in the project area. Based on the socio economic survey, there were 26 persons who took the land under acquisition on lease and 14 used to do share cropping. Village-wise status of lesses and share cropping is given in Table.. Based on the analysis of impact of acquisition on lesses and share croppers, it is revealed that about 8 persons have shifted to alternate land of the same farmer and 20 have moved to new farmer. 3 persons have changed their economic activity in view of land acquisition. The rest of the people are not available for collecting the information. This indicates that the lesses and share croppers are not adversely affected as they have moved over to the alternate land to the new farmer or same farmer in the same area. In view of absence of major displacement or submersionof the projectarea, which is common to other major projects, except reduction of land holding size and certain percentage of land holdersbecoming landless, there is not much of adverse impact in terms of joblessness, marginalisation,morbidity etc. In the hamlet of Vanala where a group has been displaced because of acquisition of their houses, they have been rendered homeless and started living temporarily in the nearby area in the existing site.

33 ENABLING LEGISLATION FOR ACQUISITION OF LAND

The Government of A.P. is empoweredto acquireany land for a public purpose under the provisionsof the LandAcquisition Act, 1894. This Act was amendedand madeapplicable to the A.P. Stateby Land AcquisitionA.P. Extension and Amendment Act, 1959 (Act No. xx of 1959). The LandAcquisition Act 1894was amended from time to time and the last amendmenttook place in 1984. The LandAcquisition Act and its empowermentof the State to acquire, any piece of land on its territory is basedon the doctrine of "eminentdomain". The expressions "eminent domain" means the powerof the stateover all propertiesin the Stateand refersto the powerof the State to take for the publicpurposes any propertyof the stateon payment of compensation. In other words the power of compulsoryacquisition of propertywhich, according to everysystem of jurisprudencethe state possesses,is knownas the powerof eminent domain. Article 31(2) of the Constitutionof Indiarepresents the principleof eminent domain. Under the Land Acquisition Act, the interestsof the awardeesare protected by the stipulationsincorporated in the Act, which requirethe Collector (L.A.) to refer all petitionsfiled by the awardeesto civil count for adjudication and assist the court in its adjudicationto determine the amount of compensation. Government of A.P. have issued G.O.Ms.No.1307,Revenue Assignment.l Department, dated 23/12/ 1993to orderpayment of lumpsum exgratia equivalent to the market value to the assigneesof Governmentlands and surplusceiling landsfrom whomthe landswere resumed for the public purposeand paymentof valuationfor otherprivate archards, wells etc. subject to the followingconditions: a) that the amountis to be treatedas exgratia; b) that the assignees wouldnot be entitledfor makingreferences under Section 18, and Section28/A of LandAcquisition Act, to the Courts; c) an amountequivalent to 15%for the landsresumed prior to 30.4.82and 30% after that date on the market value payable under section 23(2) of Land AcquisitionAct, may be consideredfor being included in the total exgratia payableto the assigneesas solution; d) that the assigneeswill not be entitledfor interestfor additionalmarket value underthe LandAcquisition Act; e) that the above conditionsshall be madeapplicable to all assignedlands resumedon or after9/2/1984 ie., the date of issueof G.O.Ms.No.180, Revenue Dated 9/2/1984in supersessionof G.O.Ms.No.43,Revenue(B) Dept., dated 23/1/1988.

34 ENVIRONMENTALIMPACT ASSESMENT

EnvironmentalImpact Assesment and EnvironmentalManagement plan for SRBC submittedto MOEF,Government of Indiaand was discussed in theEnvironmental Appraisal Committeeof Expertsfor RiverValley projects on 16.11.94and on 7.3.95. In the second meetingon 7.3.95it is decidedto havefield visitby the expertsfrom 7th to 10th April, 1995 for accordingEnvironmental clearance. SrisailamRight Branch Canal passes, on thefringes of the reservesnamely Ghani, Panyam,Ramathirtham, Ramavaram and owk reserves.The flora that is found in these forest is of miscellaneousthorny trees and shrubs. An extent of 268.71ha of forest land has been resumedout of 301.49ha for the construction.Annexure Xl the alignmentof the canal and areas of forestsare depictedin fig 5. Thoughthe canal passeson the fringesof reserveforest the existingpassages and approachesfor the localcommunities accessto the forest, are preservedby constructing40 numberof single land and double lane bridgeswhich would facilitate free movementand transportof the people of the projectarea. The details of mileageand the structuresmentioned above are given in AnnexureXII. The impactof takingpossession of forestarea to an extentof 268.71ha. is absolutelynil, with respectto the communities'access to non-timberforest produce,fire woodand fodder,as the areaconsists of rockyand sparsethorny vegetation. The socio economicsurvey has also indicatedno adverseimpact as far as accessto non-timber forest produce,fire woodand fodderfor the communityin the projectarea. Similarlythe impactof the projecton the health of the communityhas been assessedby the State HealthDept. and certainprecautionary measures for controllinglikelywater borne diseases have beensuggested. The commandarea is coveredby six primaryhealth centres and 26 sub-centresunder these primaryhealth centres. Basedon the suggestion,Irrigation Departmentwill providenecessary assistance to the HealthDepartment in implementing the preventive measures.

11.1. COMPENSATORY AFFORESTATION: Thetotal forest land coming under SRBC is 301.49ha. Compensatoryafforestation planhas beenprepared and gotapproved by MOEF,Govt. of .The ForestDepartment will implementthe afforestationwork in the landsallocated for the purposein a phased manner.

35 PARTICIPATIONOF PROJECT AFFECTED PERSONS (PAPS)

No major development activity will be a success until and unless the beneficiaries are involvedfully from the stage of planning process. In the rehabilitation of project affected persons, the involvement of PAPs is equally crucial and success of achieving the aims depend on their degree of participation. In order to ensure the participation of PAPs right from the beginning, they have been involved right from the stage of socioeconomic study,which is basis for preparationof the action plan. Involvement of the PAPs during socio economic study is however limited to calculation of factual information and seeking the perceptions and choice of economic activities for income generation and productive support. Since the land acquisition is being done as per the Land Acquisition Act, which stipulates elaborate procedure in order to protect both the interests of the land owner and the Government, who is acquiring the land for valid public purpose. The land acquisition, no doubt causes hardship to the affected community, but, will be inevitable for the larger development of the society. At the same time, the hardship caused due to land acquisition should be ensured to be kept at minimum or avoid wherever possible through various institutional mechanisms and grievance redressal procedures. The Act itself provides for mandatory grievance redressal in the form of court reference as and when the awardees are dis-satisfied about amount of compensation paid to them by the Land Acquisition Officer. Making reference to the court as a mandatory on the part of the Land Acquisition Officer, based on the request of the awardees, ensures the redressal of grievance of low compensationto the land holders. Similarly, the grievances that might arise in the process of resettlementand rehabilitation , especially in the areas of categorisation of PAPs fixing their entitlements, are proposed to be attended through sub-collector, who is also R & R Officer who is fully empowered to correct the mistakes, if any occured while preparing the plan and attend to all other grievanceswith respect to payment of compensation and their entitlements. The project affected persons can also approach through the project level rehabilitationcell, as one of the PAPswill be member to redress their grievances. Similarly, State level rehabilitation Cell can also be approached for redressal of any grievance. Similarly, wherever resettlement becomes essential due to displacement or acquisition of the houses, the selection of resettlement site, preparation of layout plan will invariably be decided by taking the perceptionsof the affected people through consultation process. Similarly, the rehabilitation options will also be depending on the choice of the affected person, who has already been ascertained while conducting socio economic survey which may however be modified depending on the need. Since there is no major dislocation, the integration with the host community after consultation is not a problem.

36 ACTION PLAN

The objective of the Govt. of A.P. is to mitigate the hardship caused by any involuntarydisplacement under the project by avoiding or minimising whereever feasible, involuntary displacement by exploring viable, alternatives of Project Design. Wherever displacement becomes inevitable,the displaced farnilies will be resettled and rehabilitated in such a manner that their living standardsare improved by increasingtheir income earning capacity and production levels or atleast restoring through resettlement,to the standard of their former living conditions. The project affected persons due to land acquisition for the project will be rehabilitated through providing productive asset grant for restoring their income. The Scheduled Tribes will be protected with particular care to retain and restore their cultural identity and traditionalrights with regard to forests.The PROJECTAFFECTED PERSONS ECONOMIC REHABILITATION PLAN has been prepared keeping the above objectives in view. Specific goals and aims of the Action Plan are given below: 1. Development of resettlementsite at Vanala village and construction of houses through the involvement of displaced families. 2. Resettlement of displaced families in the resettlement site with f ree house site +iplts grant for constiuction of house. 3. Providing social and infrastructural amenities such as internal roads, drinking water facilities, electrification, school building and community hall for the use of the resettled people. 4. Restorethe income levels of project affected persons to the above poverty line by providing production asset grant . 5. Assisting the project affected persons who are above poverty line by providing productive asset grant and improve their income levels. 6. Assisting women through their participation to form thrift groups and providing assistance in the form of revolvingfund in order to improve their socio economic conditions. 7. Imparting training and skill development for the youth so as to establish self- employment production units to improve their income levels. PAF s 8. Providing smokeless chullas to all the displaced familie4/'n order to improve the health ahd hygiene of women in their domestic work. 9. Providing cattle maintenance grant in the transit;ion period until resettlement in the new site. 10. Providingtransitional maintenance allowancefor their smooth resettlementand restoring their income generating activities.

13.1. RESETTLEMENT: There was no major displacement due to the construction of the project owing to abundant precautionary measures taken by the Government to avoid any major displacement. However, the main canal alignment at KM 12.922 has passed through a hamlet of Vanala village, Pamulapadu Mandal, requiring acquisition of 97 houses, thus displacing 97 families in the hamlet. In addition to the above 12 more houses, structures

37 or house plots have been acquired in rest of the project area in 7 villages. The details of acquisition of houses and house plots are given in Annexure XIII As seen from the Annexure XilI, 109 families are affected due to acquisition of houses and or house plots in 8 villages, majority being in Vanala village. Considering the major children for the purpose of resettlement(83) total number of project affected persons requiringresettlement comes to 192. Among the above, houses have alone been accquired from 22 families. There are 61 major children in families from whom houses alone were acquired and 22 in families from whom land and houses have been acquired. Out of 192 project affected persons, requiring settlement or resettlement and rehabilitation, 148 belong to Scheduled Caste, 11 belong to Scheduled Tribes, 23 belong to Backward Caste and 10 belong to other communities. Since most of the displaced families belong to the hamlet of Vanala village, one site is proposed for their resettlement. The process of resettlement is given below:

13.1.1 Resettlement In Vanala Village: A hamlet of Vanala village consisting of 97 houses have been acquired for the construction of the main canal at Km 12.922, resulting in displacement of the above families. The hamlet is located at a distance of about 400 mtrs from the main village and the houses were constructed under Government Housing Programme after assignment of house sites. The acquired site was fairly developed with internal roads, electrification and drinking water facilities. The families which have been displaced because of acquisition of their houses in Vanala village are proposed to be resettled in a nearby site which is 200 mtrs away from the existing acquired location. It is almost adjoining to the existing site and is most suitable for resettlement. The perceptions of the project affected persons have been taken and most of the project affected persons have consented for shifting to the proposed site. Though the total number of projectaffected persons comes to 175 includingmajor children, provision is made for 20 more PAPs for future requirement. Thus the total number of house sites that are proposed to be planned comes to 200. As per the policy of the State Government, 5 cents of land is given for each house site and on that basis the total area for the resettlement site comes to 8.40 ha. The details of working out of land requirement is given in Annexure XIV. Out of the total area required for the resettlementsite, an extent of 5.266 ha. of Government land is available which can be used immediately for resettlement. The balance area of 3.14 ha. is proposed to be acquired from the adjacent survey numbers. The location of displacement site and proposed resettlement site is given in Fig 6. Considering the requirement of the area and location of the resettlement site, the lay out of the site has been worked out, the details of which are given in Fig 7. As seen from the map, there are total 25 blocks and each block consists of 8 plots, thus totalling to 200 plots . An extent of 2.80 ha. of land is earmarked for school building, community hall, burial ground and common area. There is a provision for a small washing facility for the village. The implementation schedule for the resettlement of the displaced hamlet is given in annexureA?Xxv\'Thesocial infrastructure and the cost particulars are given in Annexure XV. A total of Rs75U-13lakhs is proposed to be spent towards construction of internal roads, approachroads, drinkingwater facilities, school building, communityfacility, electrificationandotheramTenitiesincludin9 c-nstruction orant for cnnstru- ction of ,o!rn,sS for tn. 7APs.

38 13.1.2 Resettlement in other Villages: Otherproject affected persons to be resettledare locatedin 7 villagesand hence seperateresettlement site is not required. Thesepeople are proposedto be givenwith houseplots on free of cost and houseconstruction grant as per the eligibilitynorms, so as to assist them in constructinghouses in their own village.

13.1.3. Other Benefits: In additionto the resettlement,rehabilitation package is proposedthe detailsof whichare givenin Volumellfor eachindividual. It is proposedto organisewomen members of the displacedfamilies especially at Vanalainto thrift groupsand providerevolving fund for economicactivity to improvethe livingstandards. In orderto improvethe healthof the women in their domesticwork, every house is provided with assistancefor installing improvedsmokeless chullas. In additionto the above,the new site shall haveaccess to existingcommunity facilitiesof the main village such as extensionservices, market facility, milk collecting units,health facilities etc. The site is part of theVanala Panchayat and therefore problems of demarcatingboundary does not arise.

13.2 REHABILITATION The acquisition of landfor constructionof the projecthas affectedthe peoplein the area to various degreesdepending on the extent of acquisition and adverse effect on theirproduction systems. As perthe policy of GovernmentofAndhraPradesh, the familiescovered in the socio economic survey in SRBC has been screened and grouped into variouscategories. However, the projectaffected persons refers to those peoplewho come underthe definitiondescribed in the earlierchapter. In view of varyingstages of land acquisition under main canal and distributoriesfor easy analysis and budgetting, the project affected persons are described under two categoriesnamely Project Affected Personsunder main canal and projectaffected persons underBlock IV andVIll. Undereach item,for easyprocessing, the projectaffected persons have been groupedunder two categoriesnamely i) those losing patta landsalone ii) those losing Governmentland and or patta land and or house/housesite. This categorisationhas helpedin assessingthe numberof affectedpeople due to acquisitionof Governmentland.

13.2.1 ProjectAffected Persons:

i) Main Canal a) Pattalands:- The projectaffected persons due to acquisitionof privatepatta lands, village-wiseis givenAnnexureXVI. There are 1439 PAPs including major children under this category. Out of 1439 PAPs, 312 belong to Scheduledcaste, 21 belongsto STs, 648 belongto BCs and 458 belongto other castes. 86% of the PAPs in this categoryare males and 14% are females. 78% of the PAPs are below povertyline and 22% are above povertyline.

39 b) Governmentlands and or houses:-The details of projectaffected persons due to acquisitionof Governmentland and or privateland and or houseor housesite, village-wiseare depictedin AnnexureXVI I. There are439 PAPs underthis category,of which52% belong to SCs,3.9% belong to STs,28% belongto BCs and rest to other castes. About 87% of this category are males and 13% alone are females. About 75%.are below poverty line underthis categoryand rest are abovepoverty line.

II)Block IV and Block Vil: a) Pattalands: The projectaffected persons village-wise are givenin Annexure XVIII. There are 66 PAPs underthis categoryof whome 18 belongedto SCs, 27 belongto BCs and 21 to other castes. About 73% of them are malesand 27%are females.About 57%of the PAPsare belowpoverty line and 43% are abovepoverty line. b) Government/Homesites: There are only 8 PAPs underthis group and of them 5 are males and 3 are females(Annexure XIX). Total abstractof PAPsare givenin AnnexureXX. On an average86% of PAPs are malesand 14% are females. About 67.7% of the total PAPsare belowpoverty line and 32.3% are abovepoverty line.

13.2.2 StrategyFor Rehabilitation: , Socio economic survey has indicated that Governmentland is not availablein their villageswhich can be givenfor their rehabilitation.About 2,309 peoplewho have been interviewed responded stating that there is no Governmentland availablefor assignment in their villages. Thoughthe Governmentpolicy clearly indicate that the project affected personswill be given land in lieu of their land acquired as perthe norms, provided Governmentland is available in their village, in view of the scarcity of Governmentland availability, the Government of AndhraPradesh proposes to pro- vide them with means of increasingtheir incomelevels and thus to restoretheir earlier statusof livingor improvementthan the earlierstatus before acquisition. Therefore, Gov- ernmentof A.P. has decidedto provideproduction asset grant and arrange loan for takingup various income generatingactivities depending on the resourcesavail- abilityin the villageand improvethe incomelevels. In additionto the projectaffected family,all the major children as on the date of socioeconomic survey are also being supported with productionasset grant and for providingproductive assetgrant, all the majorchildren have been treatedas belowpoverty line. Sincethe projectaffected person will be the best personto selectthe type of activitymost suited to him and to the environ- ment in which he lives, while conductingsocio economicsurvey the perceptions or choicesof the economic activitythat can be takenup by the concerned person has beenelicited anddepending on his choicethe production asset grantis programmed to be arranged. However,depending on the resourcebase of the villageand the number of peoplethat may opt for a particulartype of activitywhose viability dependson the market linkagesthe choiceswill be further confirmedand will be modified accordingly, while collectingthe grant applicationsfrom the PAPs. Depending on the type of activity,it is proposedto arrange production-cum-trainingcentres whereverpossible and help in findingout the marketfor their produce.

40 The women members of the PAPs depending on the number in each village will be mobilised to form into a group and initiate thrift activity. Such groups after stabilisation would be assisted with ecoomic support for taking up income generat- ing activity by them. The youth from the project affected families will be selected for imparting training and skills in various industrial activities and assist them to obtain grant and loan to establish self-employmentventures in the area. The trained youth will be exposed to one month entrepreneurship development programme after completion of their training period during which the formalities for establishing self employment activity will be completed and assisted for establishing the unit. In addition to the above rehabilitation package, the PAPs will be provided to enjoy the benefits of other ongoing rural developmental and welfare schemes in the area. Some of the important rural developmental and welfare schemes in which the PAPs depending on their eligibility can be made beneficiaries in order to derive maximum benefits, are as follows. 1. Supply of rice at Rs. 2.00 a Kg. 2. Electricity supply at flat subsidised rates for agricultural pumpsets 3. Economic development activities under tribal welfare and S.C. Corporation of the State Government. 4. Providing boarding facilities for the studies of the children of PAPs and social welfare scholarship for welfare section. 5. Employment opportunities in schemes such as Jawahar Rojgar Yojana, Employment Assurance Scheme etc. 6. Adult Education Programme. 7. Arranging protective water supply The rehabilitation packages have been evolved for Main canal and Block IV and Vill separately. Under each category, the PAPs due to acquisition of patta land; PAPs due to acquisition of Governrnent land, and or patta land and or house or house sites are dealt separately with respect to their entitlements. Village-wise PAPs and their entitlements and financial implications for each of the above four categories is given separately in Annexure XXI to XXIV. A combined abstract of the total rehabilitationand resettlement is given in Annexure XXV.

Individual village-wise PAP wise plan under patta lands, Government and or patta and house site or house are given in Volume 11.

41 STRATEGYFOR IMPLENTATIONOF ACTION PLAN

Implementationof the ActionPlan is MultiDepartmental, Multi-activity oriented and henceit requireshigh degreeof inter departmentalmonitoring, and coordination.Since the resettlementpertains to only small village of about 100.homesteads namely Vanala Villageand all other projectaffected persons are spreadall over the projectcovering 50 villages of the Districts,there will not be concentratedactivity of rehabilitationexcept resettlement of Vanala hamlet. Therefore creation of exclusive organisation for implementingPAPERP would be detrimentaland not advisable.Therefore the existing machineryof variousdepartments which are underthe exclusivecontrol of the District Collectorshould be madeuse of for implementingthe PAPERP.This would alsogives the benefitof variouson-going developmental schemes in whichthe projectaffected persons couldbe involvedby the concerneddepartment. In view of this it is proposedto makeuse of the Institutionof DistrictCollector as the agencyand centreof activityin implementing PAPERP. It has beenthe experience which was confirmed during the SocioEconomic Survey that there are no permanentnon-governmental organisations in the area. Thereforeit maynot be possibleto involvethe N.G.O.sin implementationof PAPERP.However efforts will continueto be made to identifya local non-governmentalorganisation or broom a local N.G.O.if any for the successfulimplementation of PAPERP. Involvement of community/socialgroups or organisationswould depend on concentrationof the projectaffected persons. In orderto haveeffective involvement of the projectaffected persons in implementingthe ActionPlan Local committees, wherever the numberof PAPSare 50 or more,will be formedand socialgroups of the projectaffected communitywould be utilisedfor successfulimplementation of the plan.Social development of the communityof PAPERPparticularly women and youth is proposedto be achieved throughfollowing ways. 1. Wheneverthe women PAPSare about 15 or more, there shall be processof social engineering to mobilise them into forming thrift groups with 15 in each groupand financialassistance for taking up economicactivity. 2. The youth are proposedto be selecteddepending upon their attitude and perceptionto impartintensive training in variousactivities for acquiringskills or improveno existingskills as the casemay be, in orderto inculcateand promote leadershipqualities

42 INSTITUTIONALARRANGEMENTS

As describedabove the existingdistrict administration is proposedto be utilisedfor affectiveimplementation of PAPERPrather than going in for exclusiveorganisation for the reasonsstated above. The Sub-Collector,Nandyal is proposedto be the Officer Inchargeof implementingPAPERP under over all guidance and control of the District Collector. The organisationchart for implementingthe PAPERPis given in Annexure XXVI. A committeeis proposedto be constitutednamely project level rehabilitationcell for effectivemonitoring and implementationof PAPERP.The compositionof projectlevel rehabilitationcell is givenbelow. 15.1. DISTRICTLEVEL REHABILITATIONCELL

15.1.1. Constitution 1. DistrictCollector Chairman 2. Sub Collector,Nandyal Member,Convenor Resettlement& RehabilitationOfficer 3. ProjectDirector, DRDA Member

4. SpecialDeputy Collector Land Acquisition Member 5. Joint Collector Member 6. DistrictDevelopment Officer Member 7. Chief Engineerof the Project Member 8. SuperintendingEngineer Member 9. Representativeof ProjectAffect Persons(PAPs) Member I10. Representativeof local Non-governmentalOrgn. (NGO) Member 15.1.2. Functions: 1. Advise in the conduct of socio-economicsurvey of the Project affected/ displacedpersons and in the preparationof R&R Plans; 2. Monitorand ReviewImplementation of R&R Plans: 3. Function as a Grievance Redressal Body supervising Project Level RehabilitationCell; 4. Considerand approvethe recommendationsof the ProjectRehabilitation Cell; 5. Takingpolicy decisions on the R&R issuesfrom time to time; 6. Provide overall guidance and leadership to smooth resettlement and rehabilitationof the affectedfamilies.

43 15.2. STATE LEVEL REHABILITATION CELL:

15.2.1 Constitution: Following will be the composition of State Level Rehabilitation Cell for the Project: 1. Principal Secretary to Government Irrigation & CAD Department Chairman 2. Secretary to Government Irrigation & CAD (Projects) Department Member 3. Secretary to Government Revenue Department Member 4. Secretary to Government Housing Department Member 5. Secretary to Government Finance & Planning (Fin. Wing) Dept. Member 6. Commissioner Panchayat Raj & Rural Development Member 7. Director of Ground Water Member 8. Commissioner of Agriculture Member 9. Director of Women & Child Welfare Member 10. Chief Engineer of the Project Member 11. Special Officer Project Preparation & Monitoring Cell Member-Convenor

15.2.3 Functions: 1. The Cell shall guide the Socio-economic Bench Mark Survey of the Project affected persons; 2. Monitor and Review the acquisition of land and payment of compensation; 3. Assist in preparation of R&R Plan for the displaced/Project affected families in accordance with the Policy finalised for the Project; 4. Identify the resettlement sites suitable for establishing the Resettlement Centres; 5. Advise and recommend on the nature of civic amenities to be provided at the resettlement Centre; 6. Dovetailthe Economic rehabilitationPlan of the Project in the DistrictAnnual Credit Plans for necessary funding; 7. Attend to the grievances of displaced persons and Project affected persons and recommend measures to redress them. The Committeemeets once in three months and review the progress of each of the items of resettlement and rehabilitation.

44 The recommendationsshall be subjectto the approvalof the Government. As explainedin the earlierparas various functionaries of relateddepartments shall be involvedin implementingPAPERP under over all controlof the District Collectorand under guidance of Principal Secretary, Irrigation and CommandArea Development Department.

45 MONITORINGAND EVALUATION

Concurrentmonitoring shall be done by the ProjectLevel Rehabilitation Cell while employingone of theirdepartmentalagency for the realtime monitoring ofthe implemetation of the plan. Monitoringby the ProjectLevel RehabilitationCell and State Levelthrough prescribedproformae, inputs to be preparedfor every monthshall also form basis for concurrentmonitoring. Evaluation by an independentagency not associatedwith the Projectexecution shall be taken up two times duringthe Projectperiod. First evaluatiion shall be after half the periodof executionand final evaluationwill be after completionof the plan period.

46 BUDGET

The Budget for project affected persons economic rehabilitationprogramme for A.P.I1IProject is preparedbased on the strategyexplained in the earlier chapter. Sincethe project is ongoingand 30%of theworks have already been completed for which the landespecially in the maincanal has been acquired, and the land under Block IVand VIil is yet to be acquired, socio economicsurvey I has beenconducted for all the acquiredlands/Vjnder Block IV and VIII duly preparingthe land plan schedulesunder these blocks. The Budgetfor A.P.111 Irrigation Project will be basedon the actualaction plan to the aboveextent ie., maincanal and Block IV and VIII and indicative for the rest of the blocks underSRBC and completeSRSP. Therefore,the budgetis prepared into threeparts. SPaC 1. Budgetestimates for the Phase-Iof the/project i.e., the main canal and Block IV and VIII. 2. Indicativebudget for rest of the Blocksof SRBC 3. Indicativebudget for SRSP. 17.1. Budgetfor maincanal and BlockIV & Vil of SRBC. While calculating the budget estimates,the compensationpayable has been takenfor the balanceextent of landto beacquired under Block IV and Vil. Compensation is calculatedon proratabasis by takingper Ha.value as Rs.1.25 lakhs plus solatium of 30%over and abovethe marketvalue. This projectionhas been adoptedfor an extent of 137 ha yet to be acquiredunder Block IV and Vill. Since number of cases undermain canal are refrred under Section 18 to variousCourts, a lumpsumprovision is made towards decretalamounts for the lands alreadyacquired. Resettlementand Rehabilitation budget has been extractedfrom the respectiveaction plan and are summarisedbelow. The cost of the projectmanagement including the socio economic studiesand preparationof R & R Action plan, monitoringand evaluation have been incor 'poratedin the budget.A lumpsumprovision is provided for project administration such as capital, for equipment,furniture, salaries and other contingenciesetc. A. Budget estimatesfor SRBC i) For 137.0ha @ 1.25 lakhsper ha and 30% solatium Rs.222.63 ii) Paymentfor decretalcharges Rs.200.00

B. Resettlement

i) Acquiringland for resettlementfor 3.14ha @ 3.21 lakh/ha Rs. 10.08

ii) Primaryfacilities such as development of approachroads water facilities Rs. 9.04

iii) Secondaryfacilities such as internal roads,community hall, schoolbuilding, dhobhighat,bus shelteretc. Rs. 10.00

47 iv) House grant for vanala hamlet for 175 persons pxs. l0,coO eacih Rs. 17.50 v) Rehabii-taticn Rs. 24.593 vi) Farm Service Centre fis. 2.00 vii) Comrnunity Partic:.pation and riscellaneous rs. 2.00 Fs. 75*213 Deduct provision (iv) and (v) already (-)R 42 ng3 included in village specific action plan -)s- 4 9 Net Total Rs. 33.12 C .Rehabi litation: i) Productive asset grant (@ 50C,- per PAP Rs. 94.C6 ii) Economic assistance for smokeless Chullas Rs. 6.26 iii) Revolving funed for women thrift groups FIs. 14.59 iv ) Traini.ng and Self Employment a )Crant Rs. 9.84 b)Loan R.s . 19.68 v) Maintenance Allowance Rs. 46.98 vi) Cattle maintenance Allo%vance as'. 0.26 vii) 1lousi,ng Grant and Training (excluding loan) Rs. 29.20 Total Rs.201.18

Project Management i) Socio economic studies and action plan fis. 15.()0 ii) Consultancy and Technical Assistance Rs. 0.70 iii) Training of R & Fi Staff Rs . 2.00 iv) Monitoring and evaluation Rs. 10.00

Total Rs. 27.70

Project Administration i) Equipment, furniture, salaries, Rs. l0.C00 stationery etc., ii) Contingencies Rs. 10.00 iii) Enteroreneruship development programme 's. 9.00 leac,ership development programme

Total Rs. 29.CK0

48 BLOCK IV AND VIII

A. Resettlement House grant @ 10,000 each Rs. 0.40

B. Rehabilitation i) Productive asset grant Rs- 3460 ii) Assistance for smokeless chullas Rs. 0.24 iii) Revolving fund for women thrift group Rs* 0.57 iv) Vocational Training a )Grant Rs. 0.39 b)Loan Rs. 0.78

v) Maintenance Allowvance Rs. 1.80 vi) Cattle MaintenanceAllowance Rs. 0.02 vii) Training Rs. 1.25 viii) Total Grant Rs. 7.87 ix) Total Loan (Rs. 0.78)

INDICATIVE BUDGET FOR REST OF THE BLOCKS OF SRBC AND SRSP

Number of project affected persons under each category has been arrived at on prorata of the command,area under Block IV and VIII for which socio economic survey has been conducted. In respect of main canal for SRSP, number of PAPs has been estimated on the same analogy but in proportion to the land acquired under Main canal (SRBC) with that to be acquired under SRSP, in relation to PAPs under main canal (SRBC). Provisions have been made for each category similar to the one provided in the detailed budget estimate for the Block IV and VIII. Similar procedure has been adopted to arrive at the budget estimate for the distributories in SRSP also. Rest of the procedure is one and same for arri- ving at the other parameters which have been adopted in the indicative budget for distributories is same as explained earlinr vide budget statements-annexures XXVII to XXX. The basis of arriving the prorata indicators are as follows:-

Distributori es Block IV & VIII other Blocks SRSP distri- SRBC of SRBC butories Ayacut in ha 6309 58769 97860 PAPs 72 670 1120 Main Canal .$. SRBC- ' SRSP Land acquired under main 1513 79 canal in ha No. of PAPs 1881 98

49 WORK-PLAN

In orderto successfullyimplement the Resettlement and Rehabilitationprogramme with easeand to the satisfactionof the affectedpeople, all the key activitieshave been identified.They are dividedinto sub-activitiesduly earmarking time for each one of them. The key activitiesare:

1) Implementationschedule of landacquisition for BlockIV and Vil independently. It is linkedto the constructionprogramme, mainly. Other sub-activitiesfrom the submissionof LandPlan schedule to the awardstage are plannedin properorder.

2) As regards resettlementthere is only one villagenamely Vanala. A separate action plan has been devised. All the activitiesflanked by selection of site at the beginingto the stageof shifting them to new site and supplyof chullahsand plantingof avenuetrees havebeen scheduledproperly.

3) Among the activities of economic development,training, skill development and self employmentoccupies the provideof place. A well designed implementationschedule is preparedand presented.

4) Other important activities are productiveasset support programme with a schematicorder of implementationstarting from preparationof District audit plan,thru verificationof PAPs,processing of applications, release of grants and loans till they are successfullygrounded and monitoredthereafter for mid correctionand final corrections.

5) Schedulingof payment of maintenance allowance and catttleallowance is also not lost sight of and programmedwell.

The bar charts preparedand presentedvide AnnexuresXXXI to XXXVII

so LIST OF ANNEXURES Annexure Particulars

I Sectorwise Villages 11 Organisationchart of Study team III Villagewisecoverage of Survey Schedule IV Village wise, Mandal wise land acquired under project for main canal. V -do- for Block IV & VilI VI Land Acquired and proposedto be acquired under SRBC Main Canal and Block Iv & VIII VIl Village wise details of other aquisitions Vil Village wise details of Court cases pending, cases decided and enhancedcompensation IX Statement showing number of PAP's under each category. X The mobility matrix and land holdings. XI Details of Forest Land XII List of Bridges XIII Details of acquisitionof houses and house plots XIV Supportingdetails of R & R of Vanala Village XV ImplementationSchedule of Vanala Village XVI ProjectAfftected Persons due to private patta land village wise details XVII Details of PAP due to acquisitionof Govt. Land/Housesetc XVIII Details of PAP s due to acquisitionof Patta lands (Block IV & Vil) XIX Details of PAP due to acquisitionof GovtVPattalands (Block IV & Vil) XX Total abstract of PAP XXI-XXIV Village wise PAPs and their entitlementsand financial implicationsfor each of the four categories. XXV Combinedabstract of the total rehabilitationand resettlement- Financialout lay. XXVI OrganisationChart for implementingthe PAPERP XXVII- XXX Budgetory requirements. XXXI-XXXVII Work Plans.

51 Annexure I SRISAILAM RIGHT BRANCH CANAL - PROJECT AREA

Sector I

S.No Mandal Name of the village

1. Atmakur I. Karivena 2. Pamulapadu 2. Madduru 3. Vanala 4. Vempenta 3. Jupad Bunglow 5. Thudicherla 4. Midthur 6. Rollapadu 7. Talamudipi 8. Jalakanoor 9. Alaganoor 5. Gadivemula 10. Manchalakatta 11. Channakkapally 12. Gadivemula 13. Korrapoluru 14. Bujunur 15. Gadiga Revula 16. Thirupadu 17. Durvesi SRISAILAM RIGHT BRANCH CANAL - PROJECT AREA Sector II

S.No Mandal Namiieof the village

I1. Panyam 25 Gorakallu 26 Kondajutur 27 Chilakala 28 Panyam 29 Konidedu 30 Bl3upanapadu 31 Alamur 32 Maddur 2. Nandyal 33 Moolasagaram 3. Banaganapalli 34 Rarnatheertham 35 Beeravolu 36 Cheruvupalli 37 Venkatapuram 38 Nandavaram 39 Pandlapuram 40 Bathlulurupadu 41 Banaganapalli 42 Bhanumukkala 4. Owk 4 t44OwkAppP21pui_ri amavaram 45 MAettupally 4 6 Owk 47 Siriganiapalli 48 ObulapuramT) 49 Sangapatnam 50 Cherlopally 51 Chanugondla 52 Sunkesula 5. Koilakuntla 53 Koilakuntla 6. Kolimigundla 54 B. Singavaram 7. Sanjamala 55 Perusomula 56 lDattapuram

i~ ~~ ~ ~ ~~~~5 CrNLFSANISATIlNCHART OF scCIo ECOtIC STUDY TEA:.

Project Director: Dr.K..',ohana Rao, MA.A.,Ph.d 1 Director, TCR & TI

Specialists: 1. Sri D.Ramachandra Raju, M.A., M.Phil, Joint Director, TCR & TI 2. Sri K.A.S. Hussain, Rletd. Joint Director, TCR & TI 3. or.Sudhak3r, MI.A.,Ph.d. (USA) Women|

Woman Sociologist . Smt.K.Ai.Vinaya Kunari, TeL Editor, TCn & TI Te__ 1. Smt.1..Sujatha, :;a.A., Comouter cum Field Investigator, TCRETI 2. Kum.Lilly, 1f.A., Investigator in the -Projact, 3. Kum.Sridevi, M.A., Investigator in the Project.

SURVZY TEAES FOr Cc:rSUCT21G SCCIQ ZCt1L'JC STUDY OF PAPs UNDERSRBC PHASE I

Team I Team II Team III Team IV Team V Team VI Teem VI! Team VIIIl

Team Leader Team Leader Team Leader Team Leader Team Leader Team L3adar Team Leader Team Leader Sri K.Chandra Raju, Sri X.V.i'.J

A. Survey schedule and villages covered from 5-2-94 to 5-1-95 in the first leg:

SI.No. Mandal Village Period of Survey

1 Pamulapadu 1. Pamulapadu 2. Bhanumukkalu 3. Chelimella 4. Kambalapalli 05-12-1994 5. Maddur to 6. Mittakandala 16-12-1994 7. Thummaluru 8. Vempenta 9. Vanala 2 Atmakur 1. Karivena 3 Jupadu Bungalow 1. Tudicherla 4 Panyam 1. Gorakallu 2. Kondajutur 3. Alamuru 4. Bhupanapadu 5. Chiiakala 6. Konidedu 7. Madduru 8. Panyam 17-12-1994 5 Nandyal 1. Mulasagaram to 6 Gadivemula 1. Bujunuru 24-12-1994 2. Chennakkapalli 3. Durvesi 4. Gadigarevulu 5. Gadivemula 6. Korrapoluru 7. Manchalakatta 8. Thirupadu 7 Midthur 1. Alaganur 2. Jalakanur 3. Rollapadu 4. Talamudipi 8 Banaganapalli 1. Beeravolu 2. Bathulurpad 3. Cheruvupalli 4. Nandavaram 25-12-1994 5. Pandlapuram to 6. Ramathirtham 28-12-1994 7. Venkatapuram 8. Bhanumukkala 9. Banaganapalli 9 Koilakuntla 1. Koilakuntla 10 Kolimigundla 1. B.Singavaram 11 Sanjamala 1. Dattapuram 2. Penusomula 12 Owk 1. Singanapalli 2. Owk 3. Mettupalli 4. Obulapuram 29-12-1994 5. Ramavaram to 6. Chanugondla 01-01-1995 7. Sunkesula 8. Sangapatnam 9. Cherlapalli

B. Survey schedules and villages covered in Block IV and Block VIil during second Jegof survey from 9-1-1995 to 24-1-1995

SI. No. Block Mandal village Date of survey

1. Block Vil Banaganapalli 1. Pandlapuram 10-1-1995 2. Sarnkalapuram 11-1-1995 3. Kaipa 12-1-1995 4. Appalapuram 13-1-1995 5. Nandavaram 23-1 -1995 Koilakuntla 6. Chinnakopperla 22-1-1995 2. Block IV Panyam 1. Bhupanapadu 15-1-1995 16-1-1995 2. Madduru 17-1-1995 3. Alamuru 18-1-1995 4. Gonavaram 20-1-1995 5. Konidedu 19-1-1995

C. Survey Schedules and Villagers covered during third leg of survey fro 03-03-1995 to 14-03-1995.

Mandal Village

Banaganapalli Banaganapalli Owk Mettupalli Cherlopalli Owk Obulapuram Pamulapadu Chanugondla Vemupenta Vanala Talamudipi Maddur VILLAGE-WISENO. OF AWARDEESAND THOSECOVERED IN THE STUDY

SI Name of the No.nf Nn.nf awardees No. Mandal Village awardees coveredin the study

1. 2. 3. 4. 5

1.Atmakur Karivena 4 4

2.Pamulapadu Maddtiru 81 52

Vanala - 300 214 Vempenta 123 66 3.,upadu bunglow Tuidicherla 119 10 4.Midthur Rollapadu 42 17 Talamudipi 303 162 Jalakanur 31 22 Alaganur 163 87 5.Gadivemula Manchalakatta 150 48 Channakkapally 34 22 GiadivemLla 17 15 Korrapolur 313 162 BukiunuLr 1 1 Gadiqarev(ila 38 16 ThiruDadu 33 22 Ourvesi 105 81 6.Panyam CGorakallu 228 116 Kondakjuturu 63 39 Chilakala 35 27 Panyam 14R 83 Konidedu 107 61 Bhupanapadu 50 43 Alamur 3 2 Maddur 26 21

7.Nandyal Mulasagaram 18 14

I 158~~~~~~~~~~~~~~ .1 l. 2. .3. 4. S.

palli Ramatheertham 24 17 BeeravolI an 34 Cheruvupalli 97 70 Venkatanuram 3.5 32 Nandavaram 109 e0 Pandlapuram 39 23 Bathtulurpadu 33 26 Banaqanapalli 160 45 Bhanumrukkala 73 3A

9.0wk Ramavaram 54 3.5 Methupalli 146 84 Owk 167 92 Singanapalli 60 20 Obulapuram 43 35 Sangapatnam 85 43 Cherlopally 279 113 Chengiqondla 49 37 Sunkesula 5f1 34

10.Koilakuntla Koilakunt.la 8 4

11.KolimigundlaB.Singavaram 15 12

12.SanJamala Perusomula 42 39 Patapuram 30 19

Total 4172 2409

BLOCK IV & VIII

1. Panyam Alamuru 42 24 G.onavaram 8 6 Konidedu 102 72 Madduru 231 115 Bhupanapadu 226 143 2. Banagana- Palli Kaipa 82 67 SankalaDniram 106 38 Pandlap)uram 91 49 U AppaI apu ram 152 38 Nandavaram 47 28

3.Koilakuntla Chinnakopoerla 137 78

Total 1224 708

1---- Annexure /! SRISAILAM RIGHT BRANCH CANAL

DETAILSOF ACQUISITION - MAIN CANAL PROJECT SPREADSHEET

Detailsof LandAcquired (Acres)

Private AssignedLand No. MandalName No. VillageName Total Acquired Total Acquired No. of No.of No.of No.of Holding Holding Houses Wells Hand Other (W+D) (W+D) (W+D) (W+D) Pumps Structure

1 ATMAKUR 1 KARIVENA 28.33 28.33 0.00 0.00 0 0 0 0 2 BANAGANAPALLI 1 APPALAPURAM 4.00 2.20 0.00 0.00 0 0 0 0 2 BANAGANAPALLI 345.78 71.88 3.50 3.50 5 0 1 1 3 BATHULURPAD 221.28 29.57 0.00 0.00 0 8 1 0 4 BEERAVOLU 238.37 7.05 0.00 0.00 0 0 0 0 5 BHANUMUKKALA 211.45 55.89 0.00 0.00 0 0 0 1 6 CHERUVUPALLI 425.13 72.42 16.89 1.31 0 0 0 1 7 NANDAVARAM 990.53 87.35 0.00 0.00 0 0 2 0 8 PANDLAPURAM 274.80 38.37 0.00 0.00 0 0 0 0 9 RAMATHIRTHAM 101.33 19.24 0.00 0.00 0 0 0 0 10 VENKATAPURAM 569.98 59.66 0.00 0.00 0 0 0 0 3 GADIVEMULA 1 BUJUMUR 1.77 0.02 0.00 0.00 0 0 0 0 2 CHANNAKKAPALLI 124.45 25.74 0.00 0.00 0 0 0 0 3 DURVESI 696.59 112.34 0.93 0.78 0 1 0 0 4 GADIGAREVULA 151.80 13.14 0.39 0.39 1 0 0 0 5 GADIVEMULA 116.45 20.15 0.00 0.00 0 0 0 0 6 KORRAPOLUR 687.63 113.77 36.52 21.88 0 0 0 1 7 MANCHALAKATTA 213.36 41.27 0.00 0.00 1 0 0 0 8 THIRUPADU 247.91 24.69 2.00 0.30 0 0 0 0 4 JUPADBUNGALOW TUDICHERLA 283.17 86.86 10.57 6.78 0 0 0 0 5 KOILKUNTLA 1 CHINNAKOPPERLA 9.50 0.07 0.00 0.00 0 0 0 0 2 KOILAKUNTLA 45.08 5.19 0.00 0.00 0 0 0 0 6 KOLIMIGUNDLA B.SINGAVARAM 163.17 23.40 0.00 0.00 0 0 1 0 7 MIDTHUR 1 ALAGANUR 665.94 219.91 0.00 0.00 0 0 0 0 2 JALAKANUR 152.83 13.39 0.00 0.00 0 0 0 0 3 ROLLAPADU 136.34 25.32 1.00 0.00 0 0 0 0 Contd... Detailsof LandAcquired (Acres)

Private AssignedLand No. MandalName No. VillageName Total Acquired Total Acquired No. of No.of No. of No. of Holding Holding Houses Wells Hand Other (W+D) (W+D) (W+D) (W+D) Pumps Structur

4 TALAMUDIPI 1367.07 219.06 38.74 15.86 0 0 0 1 8 NANDYAL MOOLASAGARAM 86.98 32.93 0.00 0.00 0 0 0 0

9 OWK 1 CHANUGONDLA 485.80 42.88 8.26 3.26 0 0 0 0 2 CHERLOPALLI 889,63 417.71 163.84 146.52 0 0 0 0 3 METTUPALLI 641.69 250.66 17.77 16.55 0 0 0 0 4 OBULAPURAM 254.03 167.82 12.06 12.06 0 1 0 0 5 OWK 278.14 186.53 93.56 91.44 2 0 2 0 6 RAMAVARAM 267.87 126.38 0.00 0.00 1 0 3 2 7 SANGAPATNAM 644.17 145.07 11.82 5.51 0 0 0 0 8 SINGANAPALLI 210.77 90.82 0.0 0.00 0 0 0 0 9 SUNKESULA 295.38 78.47 0.00 0.00 0 0 0 0 10 PAMULAPADU 1 MADDURU 32.68 8.14 85.27 32.94 0 0 0 0 2 VANALA 771.47 180.65 47.57 28.49 97 0 1 1 3 VEMPENTA 602.14 50.31 40.80 17.08 1 0 0 0 11 PANYAM 1 ALAMUR 29.84 8.22 0.00 0.00 0 0 0 0 2 BHUPANAPADU 433.97 18.03 2.50 0.32 0 0 0 0 3 CHILAKALA 352.63 22.59 1.60 0.12 0 0 0 0 4 GONAVARAM 37.50 1.74 0.00 0.00 0 0 0 0 5 GORAKALLU 758.38 187.73 30.42 0.90 0 4 2 1 6 KONDAJUTUR 312.26 10.28 4.70 0.00 0 0 0 0 7 KONIDEDU 586.29 42.34 47.68 5.40 1 0 0 1 8 MADDUR 740.00 14.47 0.00 0.00 0 0 0 0 9 PANYAM 627.38 120.27 0.00 0.00 0 0 0 0 12 SANJAMALA 1 DATTAPURAM 336.31 29.81 0.00 0.00 0 2 0 0 2 PERUSOMULA 518.28 82.37 9.51 2.78 0 1 0 1

TOTAL 18667.69 3732.58 687.90 414.19 1C9 17 13 11 Annexure V SRISAILAMRIGHT BRANCH CANAL DETAILSOF ACQUISITION- BLOCKIV & VilI PROJECTSPREAD SHEET

Detailsof Land Acquired(Acres) Private AssignedLand MandalName VillageName Total Acquired Total Acquired No. of No.of No.of No.of Holding Holding Houses Wells Hand Other (W+D) (VV+D) (W+D) (W+D) Pumps Structures

BANAGANAPALLI 1. APPALAPURAM 1032.979 40.2000 0.00 0.00 0 0 0 1 2. KAIPA 771.650 27.5300 41.09 0.82 1 0 0 1 3. NANDAVARAM 371.200 13.4800 18.50 0.63 0 0 0 0 4. PANDLAPURAM 525.360 24.1600 0.00 0.00 1 0 0 0 5. SANKALAPURAM 665.430 28.3175 0.00 0.00 0 0 0 0 GADIVEMULA 6. MANCHALAKATTA 25.575 1.8600 0.00 0.00 0 0 0 0 KOILAKUNTLA 7. CHINNAKOPPERLA 635.770 24.6840 0.00 0.00 0 0 0 1 MIDTHUR 8. ALAGANUR 66.120 18.7100 0.00 0.00 0 0 0 0 PANYAM 9. ALAMUR 393.190 9.8300 0.00 0.00 0 0 0 0 10. BHUPANAPADU 1206.040 65.2560 33.00 0.15 0 0 0 0 11. GONAVARAM 37.840 1.7800 0.00 0.00 0 0 0 0 12. KONIDEDU 985.100 37.5400 6.00 0.00 1 0 0 0 13. MADDUR 1681.380 48.1500 27.50 0.70 0 0 0 0

TOTAL 8372.059 339.6375 126.0900 42.57 3 0 0 3 SRISAILAMRIGHT BRANCHCANAL Annexure VI

LAND ACQUISITION STATUS (Area in ha)

S.No. Details Acquired To be acquired Total

Patta RevenueForest Total Patta Revenue Forest Total Patta RevenueForest Total Land Land Land

1. Main CanalKm 0-141 (includingBy-pass and OWK) 1513 479 269 2261 705.49 676.43 32.78 1414.7 2218.491155.43 301.78 3675.7

2. DistributorySystem (Blocksi to XVI) 337 - - 337 1053 - - 1053 1390 - - 1390 BlockIV & VIII 17.78 - - 17.78 136.95 - 136.95 154.74 - 154.74

3. RoadNetwork 74 50 - 124 119 76 - 195 193 126 - 319

SubTotal(1) 1924 629 269 2722 1877.49792.43 32.78 2662.70 3801.491281.43 301.78 5384.70 Annexure WI SRISAILAM RIGHT BRANCH CANAL

DETAILSOF ACQUISITION - MAIN CANAL PROJECT SPREADSHEET

Detailsof LandAcquired (Acres)

Private AssignedLand No. MandalName No. VillageName Total Acquired Total Acquired No. of No.of No.of No.of Holding Holding Houses Wells Hand Other (W+D) (W+D) (W+D) (W+D) Pumps Structures

1 ATMAKUR 1 KARIVENA 28.33 28.33 0.00 0.00 0 0 0 0 2 BANAGANAPALLI 1 APPALAPURAM 4.00 2.20 0.00 0.00 0 0 0 0 2 BANAGANAPALLI 345.78 71.88 3.50 3.50 5 0 1 1 3 BATHULURPAD 221.28 29.57 0.00 0.00 0 8 1 0 4 BEERAVOLU 238.37 7.05 0.00 0.00 0 0 0 0 5 BHANUMUKKALA 211.45 55.89 0.00 0.00 0 0 0 1 6 CHERUVUPALLI 425.13 72.42 16.89 1.31 0 0 0 1 7 NANDAVARAM 990.53 87.35 0.00 0.00 0 0 2 0 8 PANDLAPURAM 274.80 38.37 0.00 0.00 0 0 0 0 9 RAMATHIRTHAM 101.33 19.24 0.00 0.00 0 0 0 0 10 VENKATAPURAM 569.98 59.66 0.00 0.00 0 0 0 0 3 GADIVEMULA 1 BUJUMUR 1.77 0.02 0.00 0.00 0 0 0 0 2 CHANNAKKAPALLI 124.45 25.74 0.00 0.00 0 0 0 0 3 DURVESI 696.59 112.34 0.93 0.78 0 1 0 0 4 GADIGAREVULA 151.80 13.14 0.39 0.39 1 0 0 0 5 GADIVEMULA 116.45 20.15 0.00 0.00 0 0 0 0 6 KORRAPOWR 687.63 113.77 36.52 21.88 0 0 0 1 7 MANCHALAKATTA 213.36 41.27 0.00 0.00 1 0 0 0 8 THIRUPADU 247.91 24.69 2.00 0.30 0 0 0 0 4 JUPADBUNGALOW TUDICHERLA 283.17 86.86 10.57 6.78 0 0 0 0 5 KOILKUNTLA 1 CHINNAKOPPERLA 9.50 0.07 0.00 0.00 0 0 0 0 2 KOILAKUNTLA 45.08 5.19 0.00 0.00 0 0 0 0 6 KOLIMIGUNDLA B.SINGAVARAM 163.17 23.40 0.00 0.00 0 0 1 0 7 MIDTHUR 1 ALAGANUR 665.94 219.91 0.00 0.00 0 0 0 0 2 JALAKANUR 152.83 13.39 0.00 0.00 0 0 0 0 3 ROLLAPADU 136.34 25.32 1.00 0.00 0 0 0 0 Contd... Detailsof Land Acquired(Acres)

Private AssignedLand No. MandalName No. VillageName Total Acquired Total Acquired No. of No. of No.of No.of Holding Holding Houses Wells Hand Other (W+D) (W+D) (W+D) (W\+D) Pumps Structures

4 TALAMUDIPI 1367.07 219.06 38.74 15.86 0 0 0 1 8 NANDYAL MOOLASAGARAM 86.98 32.93 0.00 0.00 0 0 0 0

9 OWK 1 CHANUGONDLA 485.80 42.88 8.26 3.26 0 0 0 0 2 CHERLOPALLI 889.63 417.71 163.84 146.52 0 0 0 0 3 METTUPALLI 641.69 250.66 17.77 16.55 0 0 0 0 4 OBULAPURAM 254.03 167.82 12.06 12.06 0 1 0 0 5 OWK 278.14 186.53 93.56 91.44 2 0 2 0 6 RAMAVARAM 267.87 126.38 0.00 0.00 1 0 3 2 7 SANGAPATNAM 644.17 145.07 11.82 5.51 0 0 0 0 8 SINGANAPALLI 210.77 90.82 0.00 0.00 0 0 0 0 9 SUNKESULA 295.38 78.47 0.00 0.00 0 0 0 0 10 PAMULAPADU 1 MADDURU 32.68 8.14 85.27 32.94 0 0 0 0 2 VANALA 771.47 180.65 47.57 28.49 97 0 1 1 3 VEMPENTA 602.14 50.31 40.80 17.08 1 0 0 0 11 PANYAM 1 ALAMUR 29.84 8.22 0.00 0.00 0 0 0 0 2 BHUPANAPADU 433.97 18.03 2.50 0.32 0 0 0 0 3 CHILAKALA 352.63 22.59 1.60 0.12 0 0 0 0 4 GONAVARAM 37.50 1.74 0.00 0.00 0 0 0 0 5 GORAKALLU 758.38 187.73 30.42 0,90 0 4 2 1 6 KONDAJUTUR 312.26 10.28 4.70 0.00 0 0 0 0 7 KONIDEDU 586.29 42.34 47.68 5.40 1 0 0 1 8 MADDUR 740.00 14.47 0.00 0.00 0 0 0 0 9 PANYAM 627.38 120.27 0.00 0.00 0 0 0 0 12 SANJAMALA 1 DATTAPURAM 336.31 29.81 0.00 - 0.00 0 2 0 0 2 PERUSOMULA 518.28 82.37 9.51 2.78 0 1 0 1

TOTAL 18667.69 3732.58 687.90 414.19 109 17 13 11 Annexure VI 1-, SRISAILAM RIGHT BRANCH CANAL DETAILS OF ACQUISITION- BLOCK IV & Vill PROJECT SPREAD SHEET

Detailsof Land Acquired (Acres)

Private AssignedLand MandalName VillageName Total Acquired Total Acquired No. of No.of No.of No.of Holding Holding Houses Wells Hard Other (W+D) (W+D) (W+D) (W+D) Pumps Structures

BANAGANAPALLI 1. APPALAPURAM 1032.979 40.2000 0.00 0.00 0 0 0 1 2. KAIPA 771.650 27.5300 41.09 0.82 1 0 0 1 3. NANDAVARAM 371.200 13.4800 18.50 0.63 0 0 0 0 4. PANDLAPURAM 525.360 24.1600 0.00 0.00 1 0 0 0 5. SANKALAPURAM 665.430 28.3175 0.00 0.00 0 0 0 0 GADIVEMULA 6. MANCHALAKATTA 25.575 1.8600 0.00 0.00 0 0 0 0 KOILAKUNTLA 7. CHINNAKOPPERLA 635.770 24.6840 0.00 0.00 0 0 0 1 MIDTHUR 8. ALAGANUR 66.120 18.7100 0.00 0.00 0 0 0 0 PANYAM 9. ALAMUR 393.190 9.8300 0.00 0.00 0 0 0 0 10. BHUPANAPADU 1206.040 65.2560 33.00 0.15 0 0 0 0 11. GONAVARAM 37.840 1.7800 0.00 0.00 0 0 0 0 12. KONIDEDU 985.100 37.5400 6.00 0.00 1 0 0 0 13. MADDUR -1681.380 48.1500 27.50 0.70 0 0 0 0

TOTAL 8372.059 339.6375 126.0900 42.57 3 0 0 3 SRISAILNM RIGHT BRANCH CANAL C V

Details of Court cases under Land Acquisition

Details of Settled Cases No.of Si. Name of the No.of cases filed Total No. Village Awardees in Courts Award Amount Number Amount After in lakhs Enhance ment in lakhs

01. Panyam 148 93 35 17.94 46.34 02. Gorakallu 228 58 25 15.16 36.28 03. Manchalakatta 150 81 42 5.73 11.87 04. Channakkapalli 34 19 19 0.88 5.93 05. Thalamudipi 286 116 85 12.80 22.99 06. Vanala 177 147 108 34.63 151.65 07. Madduru 26 11 - - - 08. Rollapadu 42 26 10 1.02 2.45 09. Gadivemula 20 20 - - - 10. Koilakuntla 8 8 - - - 11. Thudicherla 102 78 - - - 12. Durvesi 105 3 - - - 13. Perusomula 42 30 - - - 14. Alganur 163 114 - - - 15. Moolasagarm 18 7 7 2.47 8.43 16. Jalakanur 31 16 17. Sunkesula 51 8 - - - 18. Vempenta 65 22 19. Bhanumukkala 73 2 20. Konidedu 107 52 21. Kondajutur 63 26 22. Chilakal 35 16 23. Bhupanapadu 50 9 24. Alamuru 9 9 25. Ramavaram 54 25 26. Owk 134 87 27. Cherlopalli 170 61 28. Singanapalli 60 21 29. Chanugondla 41 32 30. B.Singavaram 15 15 31. Cheruvupalli 97 67 32. Sangapatnam 82 66 33. Bathlurupadu 33 31 34. Ramatheerdam 26 26 35. Venkatapuram 35 14 36. Banaganapalli 157 137 37. Pandlapuram 39 34 38. Nandavaram 109 45 39. Mettupalli 134 81 40. Korrapoluru 298 16 - -

3517 1729 331 90.63 285.94 Annexure: IX(a) SRISAILAM RIGHT BRANCH CANAL PROJECT AFFECTED PERSONS - (MAIN CANAL)

Numberof PAF's Classifficationof Total PAP's

No. MandalName No. VillageName Losing Major Losing Major Losing MajorRequirng Requirng Requinng Total Tribals SC's OBC's Others Land Child House Child Land& Child Rehabil- Resettle- Resettle- No. of House ilitaton ment ment& PAP's Rehabili- tation

1 ATMAKUR KARIVENA 4 0 0 0 0 0 4 0 0 4 0 0 4 0 2 BANAGANAPALLI 1 APPALAPURAM 1 1 0 0 0 0 2 0 0 2 0 0 2 0 2 BANAGANAPALLI 14 9 1 1 4 0 23 2 4 28 0 0 16 12 3 BATHULURPAD 6 5 0 0 0 0 11 0 0 11 0 0 5 6 4 BEERAVOLU 5 2 0 0 0 0 7 0 0 7 0 0 3 4 5 BHANUMUKKALA 19 15 0 0 0 0 34 0 0 34 2 0 16 16 6 CHERUVUPALLI 19 8 0 0 0 0 27 0 0 27 0 4 12 11 7 NANDAVARAM 24 18 0 0 0 0 42 0 0 42 0 10 10 22 8 PANDLAPURAM 9 4 0 0 0 0 13 0 0 13 0 0 2 11 9 RAMATHIRTHAM 7 6 0 0 0 0 13 0 0 13 0 2 5 6 10 VENKATAPURAM 4 1 0 0 0 0 5 0 0 5 0 0 1 4 3 GADIVEMULA 1 CHANNAKKAPALLI 12 9 0 0 0 0 21 0 0 21 0 0 11 10 2 DURVESI 30 39 0 0 0 0 69 0 0 69 0 15 27 27 3 GADIGAREVULA 1 0 1 1 0 0 1 2 0 3 2 0 1 0 4 GADIVEMULA 5 2 0 0 0 0 7 0 0 7 0 0 2 5 5 KORRAPOLUR 77 87 0 0 0 0 164 0 0 164 0 66 70 28 6 MANCHALAKATTA 18 16 0 0 1 0 34 0 1 35 0 6 17 12 7 THIRUPADU 3 6 0 0 0 0 9 0 0 9 0 0 0 9 4 JUPADBUNGALOW TUDICHERLA 47 36 0 0 0 0 83 0 0 83 0 31 37 15 5 KOILKUNTLA KOILAKUNTLA 1 1 0 0 0 0 2 0 0 2 0 0 0 2 6 KOLIMIGUNDLA B.SINGAVARAM 4 5 0 0 0 0 9 0 0 9 0 5 4 0 7 MIDTHUR I ALAGANUR 28 26 0 0 0 0 54 0 0 54 0 16 25 13 2 JALAKANUR 1 0 0 0 0 0 1 0 0 1 0 0 1 0 3 ROLLAPADU 6 13 0 0 0 0 19 0 0 19 0 5 12 2 4 TALAMUDIPI 59 44 0 0 0 0 103 0 0 102 0 23 37 42 8 NANDYAL MOOLASAGARAM 5 6 0 0 0 0 11 0 0 11 0 0 7 4 9 OWK 1 CHANUGONDLA 5 4 0 0 0 0 9 0 0 9 0 8 0 1 2 CHERLOPALLI 70 53 0 0 0 123 0 0 123 4 41 47 31 3 METTUPALLI 55 42 0 0 0 0 97 0 0 97 0 52 12 33 4 OBULAPURAM 24 16 0 0 0 0 40 0 0 40 0 6 25 9 NumberofPAF's Classifficationof TotalPAP's

No. MandalName No. Vi'lageName Losing Major Losing Major Losing MajorRequinng Requirng Requirng Total Tribals SC's OBC'sOthers Land Child House Chikd Land& Child Rehabil-Resettle- Resettle- No.of House ilitaton ment ment& PAP's Rehabili- tation 5 OWK 76 47 0 0 2 0 123 0 2 125 2 8 39 76 6 RAMAVARAM 14 17 0 0 1 0 31 0 1 32 13 8 11 0 7 SANGAPATNAM 14 15 0 0 0 0 29 0 0 29 0 2 13 13 8 SINGANAPALLI 12 7 0 0 0 0 19 0 0 19 0 3 16 0 9 SUNKESULA 15 11 0 0 0 0 26 0 0 26 0 5 17 4 10PAMULAPADU 1 MADDURU 38 27 0 0 0 0 65 0 0 65 0 2 51 12 2 VANALA 50 41 84 57 13 21 91 141 34 266 14 159 49 44 3 VEMPENTA 38 29 1 2 0 0 67 3 0 70 1 40 25 4 11PANYAM 1 ALAMUR 3 2 0 0 0 0 5 0 0 5 0 0 5 0 2 BHUPANAPADU 1 1 0 0 0 0 2 0 0 2 0 0 2 0 3 CHILAKALA 2 0 0 0 0 0 2 0 0 2 0 0 1 1 4 GORAKALLU 44 30 0 0 0 0 74 0 0 74 0 15 45 14 5 KONDAJUTUR 1 0 0 0 0 0 1 0 0 1 0 0 0 1 6 KONIDEDU 9 4 0 0 1 1 13 0 2 15 0 2 9 4 7 MADDUR 1 1 0 0 0 0 2 0 0 2 0 0 0 2 8 PANYAM 38 42 0 0 0 0 80 0 0 80 0 3 61 16 12SANJAMALA 1 DATTAPURAM 3 1 0 0 0 0 4 0 0 4 0 0 3 1 2 PERUSOMULA 12 6 0 0 0 0 18 0 0 18 0 3 12 3

TOTAL 934 755 87 61 22 22 1689 148 44 1881 38 541 770 532 Annexure IX (b)

PROJECTAFFECTED PERSONS DUE TO LOSS OF LAND- BLOCKIV & Vill

MandalName VillageName TotalNumber Land Major TotalNo of PAFs HOLDERS CHILD of PAPs

BANAGANAPALLI APPALAPURAM 2 2 1 3 KAIPA 1 1 0 1 NANDAVARAM 2 2 2 4 PANDLAPURAM 2 2 0 2 GADIVEMULA MANCHALAKATTA 1 1 1 2 MIDTHUR ALGANUR 7 7 5 12 PANYAM ALAMUR 1 1 1 2 BHUPANAPADU 10 10 10 20 KONIDEDU 1 1 1 2 MADDUR 12 12 7 19

39 39 28 67 ANNEXURE-X

HBILITY MATRIXOF AWARDEE$FROM PRE ACQUI8TI0NPERIOD TO POST ACWISITOIN PERIOD

Before arquisition No.oP awardees after acqulaition

31 Land holdings Ito.of '3.75 3.75-7.50 7.50 and Total , 1 Ho in aeres awardees above No. of ,.. awardees

1. (3.75 928 403 (43.4) 525 (55.6) -- -- 928 (81.7) (87.4) (38.0) 2. 3.75-7.50 573 56(11.5) 224 (.39.1) 283 (49.4) -- 573 (23.8) 3, 7.50 and above 908 24(2.0) 30 (3.4) 140 (15.4) 714(78.8) 908 ' , (4.9) (3.8) (f33.1) (100.0) (37.7) ------! Total 24n9 493(20.5) 779(32.3) 423 (17.6) 714(29.5) 2409

BLOCK IV A VIII ', ¶ i

1. 0-3.75 179 4(2.2%) 175(97.8%) -- -- 179(100%) (25.3 %) f100X) (84.5%) (25.8%),

2. 3.75-7,50 1f8 __ 32119.0%) 138(81.0X) -- 168(100%) (23.7%) (89.5%) (12.5X(28.7%)

3. 7.50 & above 361 -- -- lf(4.4%) 345(95.f%) 3fi(100X) (51.0%) (10.5%) (100%) (51.0%)

Total 708 4(0.5X) 207(29.2%) 152(21.5%) 345(48.7X) 708(100%) (100%) (100M) (100%) (100%) _------_-_ _ --_ ------

. ~~~~~~~~.

",j"'f'tX- " - SRISAILAM RIGHT BRANCH CANAL +newye Xi

DETAILS OF FOREST LAND

Si. Name of the Total extent Taken Yet to be taken No. Reserve Forest Canal Mileage of Forest land possesssion in possesion required (ha.) (ha.) (ha.)

1. Ghani KM 43.08 to KM 50.91 80.43 80.43 - 2. Panyam Gorakallu Bypass at KM 50.22 27.00 27.00

3. Ghani KM 56.433 to KM 58.56 20.07 20.07 --

4. Panyam KM 63.558 to KM 70.779 18.32 18.32 --

5. Gulamaliabad KM 90.938 to 90.988 0.50 0.50 -- 6. Gulamaliabad KM 98.206 to KM 99.214 10.60 10.60

7. Gulamaliabad KM 99.214 to KM 100.716 13.05 13.05 --

8. Ramavaram KM 104.714 to KM 106.014 10.36 10.36 --

9. Owk KM 108.014 to KM 115.584 15.75 15.75 -- 10. Owk KM 99.214 to KM 116.481 77.41 72.63 4.78 11. Owk Owk Reservoir 28.00 -- 28.00

301.49 268.71 32.78 LIST OF BRIDGESON SRISAnAM RIGT ERANCHCANAL Xl. MAIN CPL

S.No. Type of the Bridges Mileage Kms.

01. single lane Bridge 1.86 02. Single lane Bridge 3.706 03. Double lane Bridge 6.593 04. single lane Bridge 9.271 05. Single lane Bridge 10.212 06. Single lane Bridge 12.866 07. Single lane Bridge 15.769 08. Double lane Bridge 16.566 09. Single lane Bridge 18.389 10. Double lane Bridge 30.486 11. Single lane Bridge 31.786 12. Single lane Bridge 37.689 13. Single lane Bridge 39.471 14. Single lane Bridge 46.365 15. Single lane Bridge 51.180 16. Single lane Bridge 54.555 17. Double lane Bridge 64.934 18. Single lane Bridge 75.20 19. Double lane Bridge 77.863 20. Single lane Bridge 79.471 21. Double lane Bridge 82.600 22. Single lane Bridge 83.699 23. Single lane Bridge 87.20 24. Double lane Bridge 88.30 25. Double lane Bridge 90.887 26. Double lane Bridge 92.451 27. Single lane Bridge 93.808 28. Single lane Bridge 95.360 29. Single lane Bridge 97.08 30. Single lane Bridge 98.349 31. Single lane Bridge 108.052 32. Single lane Bridge 110.376 33. Single lane Bridge 117.00 34. Single lane Bridge 120.532 35. Double lane Bridge 12.471 36. Single lane Bridge 128.350 37. Single lane Bridge 131.700 38. Single lane Bridge 133.525 39. Single lane Bridge 137.304 40. Double lane Bridge 137.994 SRISAILAM RIGHT BRANCH CANAL

PROJECT AFFECTED PERSONS ECONOMIC RAHABILITATION PROGRAMME Mnnex,yieXJiI

DETAILS OF DISPLACED FAMILIES

Nos Nos. Loosing Houses Loosing House Classification of PAPs sl. and land No. Name of the Village and _land PAF Major Total PAF Major Total Total SC ST BC OTHERS Child Child

1. Banaganipalli 1 l 2 4 - 4 6 - - 4 2

2. Gadigarevula 1 1 2 - - - 2 - 2 - -

3. Manchalakatta - - - 1 1 - - - 1

4. OWK - - - 2 - 2 2 - - - 2

5- Ramavaram - - 1 - 1 1 - - 1 -

6. Vanala 84 57 141 13 21 34 175 148 9 15 3

7. Vempemta 1 2 3 - - - 3 - - 3 -

8. Konidedu - - 1 1 2 2 - - - 2

Grand Total 87 61 148 22 22 44 192 148 11 23 10 ANNEXURE - XIV

Cost Estimnatesof Rehabilitation Centres at Vanala village

Home Stead Land: Total No. of affected families 200 Nos. including major children

Number of Rehabilitation Centres proposed 1 No.

Extent of home stead land required = 200x0.02 4.00 ha.

Total area required considering 40% of home plot area for roads and other purposes 4.00x40/100 = 1.60 ha

Add 50% for other amenities such as public buildings etc. 5.6 x 50/100 = 2.80 ha

Total land required 8.40 ha

Government land available under survey Nos- 637A, 637B 5.26 ha

Private land proposed to be acquired under survey No. 638 A 3.14 ha.

Cost of 3.14 a @ 3.21 lakh/ha including 30% solution 3.14 x 3.21 = Rs. 10.08

2. Roads: 12M (40') wide W,B,M. roads for main road and 7.50 M (24')wide W.B.M. roads and internal roads in rehabilitation centre:

a) 12M (40') wide internal road = 297M or 0.30 Kms

b) 7.50M (24') wide internal road 2.00 Kms.

Considering 12M (40') wide road is equivalent to twice that of 7.5 M (24') wide road.

Total equivalent length of 7.5 M (24') wide road = 2x0.30 + 2.00 = 2.60 Kms.

Cost of 2.60 Krns W B M. road @ Rs. 2.0 lakhs per 1Km at centre = 2.60 x 2.0 = 5.20 lakhs Rs.5.20

Add extra for approach roads & culverts etc Rs. 2.30

Total Rs. 7.50

9 3. Community Buildinc:v Cost of SchoolBuilding & commnunity hall etc. Rs.3.00

4. ExternalElectrification for rehabilitationCentre.: a) cost of externalelectrification including service lines @ Rs. 1,50,000/- per 1 Kmfor total length of Roads.

(0.30+2.00)@ Rs. 1.50 lakhslper1 Km Rs. 3.45

b) Streetlighting Rs. 0.55

c) Maintenancecharges @ Rs. 40 lakhs per year for five years Rs. 2.00

Total Rs. 6.00

5. Cost of Water SuPply:

Cost of borewells @ Rs. 35,000/-per each borewell for 2 borewells including casing pipes, and pumpscost of platformetc. = 2x 0.35 Rs.0.70

6. Providinghouses for each family at RehabilitationCentre including sanitary facilities= 175 x 10,000 Rs.17.50

10 ANN1- .'X U !U ,-X V

Si:,'TTLi m:I T !IM uE;iI;I.[IL1TATt[ ON,N FOR' VANALA VILLAGE

Si. I te;.: of iwork Extent Cost No. N os/ha (Lakhs)

2 3 4

I. ACQUISITIC'-' OF L,AND ATCD HOUSES ETC

1. Tot a- families affected kNos) 97 2. N n jor Chiildren 78 Future Development 25 Tota 1 2 00

2. A rea reiluiired for house plots ) GO200 Sq!LiLper fav.ily (20v10lI) ) 4 internal roeds, other a.tuenities 3. Patta lands to be acquired in-) eluding 30,0 Solatium=3.I4x3.21) 3.14 10.08

Sub ToVLa1 (I) 10.08

I I . iT. L.T.. EL T PiACK;.G E P.l'ri:.,ary facilities 1. Develo I.11t... of layout U . .lO,00J/ 5.40 0,84 hla 29 For:a.Ation of npproicli roads ,,lm. 0.30 1.50 3. Electricity - 6.00 4. Drinking lVnter f aci li tics - 0.70 Sub Total A.A) 9.7

3. tcc!lndary Facilitics 1. Interiial roads 2 ,iflS 2.00 Km 6.00 2. PubLic Buildings i) Couoi.;unity hall cu:!ilibrary) iiiettiding school buildings) 1 No. 3.00

ii) Diiobi Ghiots 1 No. 0.50 iiiJ Buts 'lShelters 1 No. 0.50

Sub Total tk3) io.oo

C. House grant 0 10,000/- per) f,'Inily incLudinug sprnitary ) facilities ) 175 17.50

Stl) tot,-l I 36.54

!!eesett le u'tt P'ack a;e ) ------1 2 3 4

1. Maintenance grant © 500/- per 147 6.615 month per family for 9 months 2. Cattle maintenance grant RS.2C0 18 0.216 per month per family per 6 months 3. Financlal assistance for income 266 13.30 generating schemes ..© 5,000/- per family (subsidy) 4. Subsidy U? Rs.600/-per family 147 0.682 for smokeless chulas 5. Assistance under FLAC-AType.. 199 1.99 6. Voc. TFP -f (a) Grant 53 1.59 (b) Loan 53 (.41 ) Sub Total (FRehabilitation)

IV. CM-MU.LNITY'OATRTICIP.ATI%I .\VM D i'SCMLLk.A2OUS 2.00 V. Outlay for F.S.C. and housing loans funds to be raised by NGC' including Nationalised Banks (N11otIncluded in paclcage) il3 F-arm service centre (FSC) thro Jgh W.G'.f, . 200 2.00

Grand Total 75.213

Deduct amounts included in Village Specific Action Plan for Vanala (R7.17 .50+6.615+0.216+13.20+0.082+ 1.99+=.59)= 42.093

Net Total ( 75.213 - 42.093) = 33.12 33.12 TRIRDDNYHRA PP-A!ESH IRRIGTION PROJECT A nx e-V (6RECSu4b przosctl RESETTLEhEATAiDREI44BIL1TATION Details of FAFsdiue to aviuisitioii of catta laods.

?$JtiPEROF PAPS Total i Total Naof -…------1acid : co eii- SI. The :Nam~eof the : S X : C A&T E : Aouired satiom

:tialeif4als: SC : ST : 8£ :GthersiTotal (A/cs) Rs.

1: 2 ~~~~~~~3:4 :5 :6 7 :9 10: It 12

I i Atrdakur :-,ariqena : 3: It 4: 4: 28.330 211757:

2: BanaQanavilli Beerv'olu : 7: 0: - :3 4 7: 2.770: 66400

IT:8tu1ra 10: I: - : 6: 11: 10.710:196085:

4: Chernmuai : 23 4: 4: -:12 11: 27: 16.770:238717

5: :Ndavara 38 4: It0 :10: 22: 42: 28.940,343896:

6: Pandaliuraii i 12: 1 -I 2:2 11: 13: 15.210:439584:

7: RPithirthain It11 2 2 : : 5: 6: 13: 9.760: 231090:

8: :Vsqataplurae 4: 1 - - I 4: 5 7.ON3: 94521:

9: :Ehwiumuka1a 30: 4: 2:16: 16: 34: 28.650:482573:

10: Ban a3an a a IIi 223I 0: - 12: 11: 23: 19.350: 651049:

It: Aupelaou'a-m 2 : 0 - 2 : - : 2 : 2.200 -

12 Gadi4eftlla :Chnanna ka1i aII 16 5S 11: 10: 21: 17.090 271335

13: DuveNi : 63: 5: 14: -27: 27: 68: l5.0552654814:

14: :adioa-irvna : I: -: -I- : : 1 0.740: 29777

15: 8a-diveiuIa 5: 2: - : 2: 5 7: 12.340 260725:

16 1(iorranclur i 134 i 21: 66 : 70 : 19 : 155: 66.750 :1277316

17: Mlanchalakattat31 i 3: 6: - 17 11: 34~ 19.8201 365171:

IB: Thirup adui 9: 0 -: : 9: 9: 20.7101 19423

19 : JupDdibano51ow Thudicherli 68 7: 25: - 5: 15 : 75: 50.660:1042i3595

20: KoilIakun t Ia :Koilakuntla : 2: 0: -:- 2: 2: 1.520: 4000

21 :O~I iiihiund Ia : .Sinmavaran 6: 3: 5 4: - : 9: 9.4(00 151276:

22 ~~~idthur A.:.f.Iao u r i 43 : 12 :16 :-:26 : 3 55: 101.69]:1013426

23 ~jalakanur I1 0.140 3943 ------r I: 2 : 3 : 4 : 5 : 6: 7: 8 : 9 10 : 1 : 12

24 :Thalamadfiai : 70j 14: L' :32 : 40 84: 93.370: 100083:

25: :Rallaoadu s 17: 1: 5: -: 7: 2: 14: 12.060:132864:

26 : : a r2I:I : 27: : 4 . : 13 :1:R : 64.600: MM :7

27: .Sina.aaoalIi: 15> 4: 316:3: - : 91, 49.410:110260:

8: 65: : 2: : : 54: 74: 12.23 34654

29: :Methaaiil : 63: 17: 38: -:10: 32: 8): 145.770:299826:

30: :Chanueardla 3: 0: 2 I-1 3: 7.390: 61575:

31: :'.fesa : 2.5: : 5: -: 17: 4: 26: 22.420:2033W44:

32:Sanatnafa 24 3 I 13 3 27 32.2: 961851:

:?. :CWar1o~a11iC2: : 10: 36: :34: 22: 9: 14:.45 314484

34 :obs.uiuram : 29 : 7 : 4 -: 23: .9: 36: 0.39(0: 6501594:

35 :Panya GorakaLlu : 6: 4 : 15: : : 13 : 73 5.135 : 2792508

36: :KIn;daiutr: 1: 0:-:-:-: 1: 1: 0.450: 592:

37 :aur : : : : :5 7.40 33677:

3: :E anaapata i: : 0: -: i: I: 0.532): 6995:

39: :Chilaala : 2: 0: - : : : 2: 0.750: 3 :69

40: :Kanile : 12: 1: 2: -: 2: 13:1: 11.015: 189210: * . . . a . . . . .* 41:38* :addrShSpSaal: :0 L : - -: 1: U3 -:2 21: 1.060 14034:WSS

42: :p&ymi : 65: 15 3 61 16 S0 93. 1201876 :

436:Pamuiand :maddur 15: 4: -: -:19: : 19: 5.410 108614:

44; ;e:nta : 1 6: 21: :15: : 37: 32.9: 56181:

45: anaia 61 12 4 6:28: 35 73 83.99: 2088656:

47:Sa:aa attaoam : 4: 0: -: 4: 1:I: 4: 11.300: 444517:

48: Peutsia 14 0 3 6 3 14 22.460 363883:

49: Nandal : lasar : 2: 4: -: -4: : 2: 1.00 t 1087566

: 1247: 192: 1 : :21:6 : 458 : 1439: 1657.539 3210613 43-- -0 : - : L5: -4: - -:-17: - 'q: ------Annexure-XVII THIRD8421RA FRADEUH IR9R169TION PROJECT (RIOSob Pr~ojetl KSESTTLEMENTANDEHBILITOTION Detailsof PAPsdue to acquisitionof oat;at6omt lands.iIH4uses etc.

- JK.O PATS LandsAcquiredi in Ac. t I Coe0esotion Faid (in NJ.l

SI.: The Nams ofthe :EI X C AS6TE : Houses: : Mo. i Meedal VilIse- :------: 0atta -Govt. Total : Nos.):atta -Govt. Housesi Tatel1 I ~~~~~~~~~-ale Jmelse:SC .ST ! C 0thers:Total: : I I I 1 :I

* . - - - -~ ~: ~~------_-__--- I: 2L ::6 0113:40 : 0 1: t 21 1 : 4 :15 16:17 to1 t

I: Ban99anapelliBasaoasapalli: 0: I1 - -: 4 : 2 : 6 5030 3.00 6.80 50 :17463 I1201870:5067731: 6537069i

2gadivfmula :So.7i 1:0 I -7 : I -t 42642:i 42642:

3 E~~~adioar'evu1a: 2 : 0 - 2 :- : - 2 : - :0.00 : t I 90: 980

-4: :Itotvaoour 8: 1:- -: : 9: 9: -:R1l1,l1 - -: 94030: 94930:

: :Manchalakatta:1: 0: - - : : I 3.26: -: 26: 1 580922: - : 59022

6 : JuoudBueqlcw tT7u0iche-r1a : 6:t 2 :6 :- 2 : : 6.15:6,15 : 6120: - 361,20

7:l¶idtlur Rlolloada 3: 2: - -:5: - : 0 0.25: - 5,25: 29022: : - : 29922:

9: :~~~~Talaudwai:16 2 11 - 5: 2: 16: -: .W0 6.00: - - 43901: 4290

q Nk ~ Obulanuram 4:t 0 2:-: 2: 4: - 6.6:-6.56: - : 221729: - 221729:

18: :llatiarar 1I 0:-:- I I::1 4.11: -:4,11 1 :126909:g - : 39600: 176009

II: :060 47: 4: 6: 2:21: 22: 1: 20.43:91.34:116,77: 2 :1985020:6421913: t 66260433:

12: :fMethuaalli:10: 2 i14 - 2: 1:I 17: 4.1(:16.55:i20.65: :6000611026: - 671026:

13:t iChanti9oudla:i5: I1 6. …6: :2.06:2.96: - : 29090: - 29090:

14: :sancaaatoae:- 2: 1:-iIa I 2: -: .82: 2,92: - : - 916500 - 916500

10: :Oberl4111 20: 2 0: 4:13: : 31: 40.74: 4G.0:92.70: - 1270583:183: - : 1379413:

16 Panyis :Serakallu : I: 0:-:-:- 1: 1.34:0.20 1,64: - 1441: -: 1441:

17: IKoeiedu 23: 0:-: -: 2: 2:t -:4.72:4,72: I t -:I96701: - : 9701:i

18iPaeiulao:du tMIadduru : 39: 7: 2:- 32 12: 46: - 28.40:29.40: - -:3743900 i 374390:

19: Iteseenta a27: 7:10: 1t10: 4: 24: : 14.66:14.66: 1 - t 127099:i 2500 120L599:

20: .Yosala t 66: 27:10: 9:21: 9: 109: 8.277 17.Z25:2.00 97 :224020:t 224709: 600626: 1100905:

21 :Smaniala FPersaeRula 4:4 0: - - :4: 4:- - 2.79: 2.78: - : 11102:- -: 11102

:382: 60 7282: 17 :122 : 75:- 442 :0106.95: 269.91 :375.66 : 109 :2179279:9826676 : 5761257:t17766212

JK-50.wal THIR.DANDPRA PRADESH IRRIGATION PROJECT (SRBCSub Proseit i RESETTLE,ENTArNDREHABILITATIOJN Aanxu'e-KVII Dttail; nf PWiFsLue t'n acJuuisition of patta lands (B.YJQIV 7s.VIII

: : : IlNMBEROF PAS cTutal Land :Tatal Cmamen-:

SI No: Nameof : Nameaf the villaue: S E x C A S T :Acuired :sation Paid.: The : Miandal : :WaIe :iFmale: SC: ST: DC :Others: Tutal : (ACS s Rs. ____~_-__--_-___ ~ ~ -- - - -____------1: 2 : : 4 : 5 :6: 7: :9 : 10 11 :12

1 :Banaganapalli :Nadavara: 3: 1: 3I : - 1 - 4: 2.550

2: :aia : : : : : : 2:

3: :+:aiDalov' : L: : : - : 2: 1: L: 2.470:s 3: :APDlaluram : : : : :2s Ls3: 2.470

4 :Gadivemula Manchalakatta 2 : : * 2: : 2 0.655 2873

5 :Midthur :Alaaanur : 12: : B : 4 12: 12.060 125216

6 :Panyam :Ala: :* 2 2: 2: 3.050:

7: -:hucanaaadu : 16: 4: : .I: t 9: : 25.245:

K: -.1n:Kidedu 2: 2 2 124 : : : : : : : : ~~~~~~~~~~~~~la's: : : :40 9: :Maddur * 15: 3: 7: :6: 5: 18: 6.320:

52: 12: 1: : 25 1: 64: 5.688: 128089

dala.waI THIRDAtNDHR PRADESh' IRRIGATIOk PROJEECT (SRECSub Przj.ect) RESETTLEM'ENTANDREHABILITATIG4 Details Mof du'P4 to aoujsitiarn oflatta! .vt./fH?sqs etc. (SLOCKIV &.'V U I

%MEEROF PAAs : LandaAcmurpd in AC.: - CamensationPaid (in Rs.)

4.: t'^ze , the-A 5£ g : '. S T:

.¶an a1 : Via- IItt ' ------c T=al%t Nos. sPatta&2,4 t :hI±EMazsTor& ajaple :FIaie: SC ST: SC:Gthers: Total : : :

I , .4 5 6 ^ 7: 9 ' 9 : 10 1 t 2 1 3 :14 5 1:6 :17 : ---- ______------_ ------,

. an l: I0.60: 0: -: - -: : 1: -:60.0: 1 -:

2 Pand1aaLirain: 2: 2: : ~ 4 4 - : I : -: : -:: ~:Pawa~i :!na : 1: 1: :~ : : : 2:0. : -: 04: 2

: anyass : .%.ni.1weU I: _0 _ a- 4 49 _ .i4$ _

4: :aiu : : 0: : : : :0. 0.74: : : :

: :5: > : l3:i7: 3 : 7 .78 1:0a05: 1.53: 4 : , 60,a6, 6.22: jk-46-,wQ1 THIR.DANUtA PRAD9PIESH IRRIGATION PRO.ECT RIS9I'.AMR194.T BRRANCH 14CANAL RESETTLEMENTANDREH4ABILITATIQIN ABSTRACTOFPAPs - SEXWISE 4 CASTEWISE Anexure-XX

N-MBEROF FPs :NUBER OFPPs t ------:- INCOMEWISE s : 5 E X : CASTE : ------, ::-2 :Male :Female: SC : ST KBC, thers,: Total :BPL tMAPL

I 2 3 4 %: -5 i 6: 7 : 8 9 : 10 :

nAINCANLC,AN

Pattalids : 1247: 192 312: 21 :64: 450 1439: 947: 492 ;

ov*tlands/ houses : 30: 60): 28 17 122 75 442: 33: 112:

: : S : : ' : ! S 2

BLOCKIV & YI :

Patta lands . 52: 12: 18: -:25: 21: 64: 42: 22:

Sovt lands f houses: 5: 3: 0i 0: 1 7: 8: 4: 4:

* a a a a i

T 0 TAl L :1686: 267: 559: 38 :796: 561: 1953: 1323: 6302

JKX--6- THIRDAtF)H4A PRADESHI IRRIGATION PROJECT AnnexUre-XXI (SPOCSub projet1 RESETTLEMENTAND0Ki4ilt.I4TION f"viect Effecrenunnsons Ecosnoic Rehabilitation rooarame ACTIONPLAK

OAIN4CANAL0 fR:tt lands) P4A10t ill Rs.

*:4i3. of PPPs Fr?oductiv~ :0OthsEcenoiic :M¶aintenance.Vocatimnal TraiMnie GrandTotal Vame of .Inicomewise AssetGr~ant :4usistance :4lloeaArt: SI1 t The ~ :aeoC1)ullah 8)08.A:

:80)L ,4PL :). Aeunt Amounet : :n No :Aoeunit ,Loan %Grnet :Loan

1: 2 : 3 :4:5 6 7 to: ItI11 12 :13 I 14:t 15:I

I1:tiaku' :Karivina 3- I: 4: 21)004) 2404): 4004): 18000: - - : 44400: -

2 Banagananalli:Beeravolu : 6:t I i7:i 35000 3)00 600:) U50t-:250: - 66500 -I

3: :athu1uroad 10: 1:11t 554)00 3600: 9000: 27000:i 1 3000W 6000:z 97600 6000

4:~~~~ ~CiCeruvuakali :21: 6:i 27: 13,50)0 11400: 2300): 850): I 3000 6000: 257900: 6000

5: :~~~~~Nandavaram:31: 11: 42: 210)04) 14400: 29000 10800)0: 7: 21000 42000:32400:i 42000

6: Pandaloura: : 9: 4: 13: 65000: 5400: 10)0 41)5001 2: 6000 I2000126900 i 12000 4 1 :~ ~~~: IS ~610 ~ ~ :20 IWO: 50 - 1 1 7: :~~~~~Ramthirthan10: :3 90: 440 040 10: - : - 110700: -

8: VOeratarnuraaf 5: 0 5: 2504)0 24)00 4040 1000:I 1I 3000: 6O0)0 52400: 6000

10: Banauanaoalli: 14: 9: 23: 11504): 8404): 17000: 6)00): 4: i200: 24000:i 215400: 2400

11: :Ooalaourai I : I : 10)4: 60 1000: 4504): : - 16100:

12 SaBdivenula Channa)kaoalli: 14: 7:i 21: 10500): 72W): 16000: 54)000: 4 : 12000:24000 : I94200 :2400

13: :Duiv'i 'L 4")i 6130 3400)0: 17401) KM0)0 130500 16: 4800 q6000: 587900 96000

14: :adiuarevula I 1: 401:I SW)0) 610: 101)0: 4500: - -: :11100: -

15: :adiv:nul: 4: 3:t 7 3500 3000 600 22500: I: 30 600 69500: 60004

16: Korranolur 104: 51:155: 77(0)0: '204)0 1001)0 315000 42: 126000:252000:i13,5800 252004)

17: Mbanchalikatta: 22: 12:34: 170000: 10801) 24000: 81040: 7: 2104)0 420)0:30680 42000)

Is: Thiru:sdu : 7: 2: 9) 450)0: 18)0 60)0: 135)0: 5: 15000 300)0 81340 300)

IR 2uoadi banloweThuditrherl : 45: 304:75: 375000: 25240: 560)O: 189000: 13 39000 78000684200 780

20 Koil:Ikantla :0c:1sIuntia 1 1 t 2: 1004): 600: 104)0 4500: I 3004 6000:19100: 6000:

21i Ooli,iaunidla :B.Sinoavaram 7 7: 2: 9: 45004): 2400 O000 11000 1I 3000 6)00 76400:i 6000.

22 Fiidt6ur :1au)aqur i 38: 16:i 54: 270000: 1604)0: 4)4)00 12604)0 6: 18000: 36000:4758000 36000

23: :3akanur 0: I 1:1 501)0 600CO 4500: - : - -1000 I i 2 : 3 4 :5 :6: 7 : : 9: 10 :11: 12 : 13 : 14: 15:

24 hRoIllmadQ I t00 4 14: 70000: 3000 120001 22500: 2 6I000: 12000 113500: 12000:

25$ tThalauudioi : S0: 35: 85: 425000: 30000: 61000: 225000: 12: 36003: 720 0 777000: 72000

26 Nandyal ftoolzsigaran 6: 5 11: 55000: 3000: 9P00: 22500, 5: 15000S 30000, 104500 30000 t : . 27 Ctk Obulaoura 23 13 36 1I0000 12600 29000 94500 : 5 15000 30000 331100 30030

28c :fRaavaraa : 23: 8:31: 155000: 1400: 17000: 63000: -: -: -: 243400: -: I : I i I 297 :Sinrgnmaalli: 16: 3:19: 95000: 2200: 16Th: 54000: -O -: -: 1722C00 -i t X : : : : : : ~ ~ ~: ~~:: : : : : 30: - zOak : 51: 23: 74: 370000: 26400: 55000: 196000: 17: 51000: 102000: 700400: 102000

31: : lethuialli : 56: 24: B0: 400000: 20200: 66000: 211500: 7: 210S0: 42000: 7267600 4000:

32: :Chanuoondla : 2: 1: 3: 1000: 1830: 3000: 13500: -: -: -: 33300: -: X ~~ ~ ~~~~~~~~~~: 1 : : : : I 33: :Sunkasula : 16: 10: 26: 130000: 9000 22000: 67500: 3: 9000: 10M 2375C0: 18000:

34: BSanomautnam 17: 10: 27: 135000: 7800: 24000: 58500: 1: 000: 6000: 223.00: 60o0:

35: CIharlalaIli : 52: 40 92: 460000: 33400: 73000: 243000 10 00: 60000. 83B400: 6000 t

36tPanyan :Oarakallu : 45: 28: 73: 365000: 25B00: 66000: 193500: 9: 27000 54000 c 677300: 54000:

37: :Kondujukur : 1: 0 1 : 5000:-: 600 1000 4500: -: 1110:: -:

38: :iAInh : 3: 2: : 25000: 100: 3000: 13500: -: - * 43300: -:

39 nadu 1: 0: 5000: 6 4500: : : : I I 1 : :1 : : : : I ¶ 3C:t6iakaI. : 1: 1: 2: 10000: E120: 100: 15900: -: -: - 21200: -t

413 :I(onidadu : 9: 4: 13 65020: 500: 12000: 40500: 2 6000: 1 0 1280: 12- g : X : : : ~ ~: ~ ~: ~ ~: ~ : : : : : 42_ __ - addur : : 2 100: : 600: 1000 4500: 1 300 6000 1910 6000: I : : : : : : : : : 43: :Panyu : 2: 8: 10: 4000: 22800: 64000: 11T00: 26: 78000: 156000: 458003: 156000:

44QPalad :Maddur : 13: 6: 19: 950: 6600: 18000: 49500: 3: 93o: 1000: 178100: 1000: I3 : Pay : 52 t o 000 20 40: * 310: *e 2 8 : 160: 75C:tS0: 45: :Vesata :23 14: 37: 105T 14400: 34 10:000: 9: 270: 5400: 36000 540:

46I : :sVanala. : 48t: 25 : 73 : 265000:1 240: :~~~I 51000:: 18000 : 15: 45 :: 90000: 665000,:: 90000:

47;Sa:jaaala Dattaodura : 13: 2: 34:4 2002 1600: 000: 13500: -: -0: -I 39300: -I

45: P,erusmla : 6: 8:14: 70000: 5400 14000: 40500: 2: 62000: 12000:13900: 12000:

947 :452 :1439: 71950000: 476400 :111I13: 0 0573000: 248: 244000: 14000 :13101400 14000 ______-_-__ ------: ,k-63.wat IS 9 Xi

SI kAtIDs RA PADEFSiIRRIi'GATFN PR.CJE£T (SR.BCSU-PR3.1ECT) -X(IU PR.i-J,TE~£EF D pER,SCNSE£'QlIC P.NsZBILIUTiTION P W2P•4¶.¶E ACTIONPI'AN Lck: IV EtVUIi7 (F.:ArTALANDGS 1i'4unt i.i Ps. - _-- - _- - __ _ _ -- _ _ - - _ - _ _ _ _ - -- - _ - _ - _ _ ------_ --- - _ __- ______: : £Er fePiAi S P.ducct-ie iler 6g' naioc :ulantedianc: : ~ : Sinc,5r,e :v .-set Grmt i i2 a I iz A :ie,t3- :t : : sa,a,T'F.'Nill ,t : 't4 I 4 : 20-00-C 2-0-----90-0 : ,:: : 0 : ANDrU 0 li~~~~~~~~y : :l,eIi, i BP AFL ,ti;',t 4,+s,t illah: -i.A. :

: :4.ne,li * . t ______

a:a0 1: 4 5000:: 1600: 440:: - ¾ 0: i- ::

KaIa: 3: : : I , 5000 600 200 : 5000 0 t Cs 'i O 0 1~~~~~~~~~ 4 r r4 aT: an ra se4 ar l4 m = 4 a 64=F 4a8E3)-+' '7+''{ t~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~I2X0) iJ9O" C 7 2fx

:Edivev a :ancnaaat.a : : : : 2 : : :00 :0 - : 0: 0 :: :&r:v-i :4inraiSat : 1: l 2 i 4ri3 4.zi -{ 4 S1 - 4 } 5,3 Le';4.

: ~jia*~anur : :0000: :20012 6 :i~1 7000 : : : 1:0 : 24000 : J .I *14044:

it 40j 4'Ja 4;;K 4 '.i''X t.4.itiSlur ~ ~~~~~ 7:~ 4iazau 5:~ 12~~~ 4,3t> 4-h 4 t7i3 Partwam -Aiamur 2 O: 2: XM)03 600: 2000: 4503: - 0 i0: 17100: 0:

:~. 7 :O :0:0: : 6000: 060: 45000: 2: 6 :12 02: 17 : 1 :000; : Kihmni, : i: 7 *2 4tiiXS 4r,r 5t)33 4s<3J 4 S,N4 l'n,t 4 . 3 |4 43

4~ ~ :atutlSdf :: Il: : I:1: 22: 1 i430S ): 4 600:t 4 p : 4T : - :: : 0:43: 170:1 N 4 ::

ftSlaLFeu r f s t13 : 5 : B : 9 : 660h660: 150M0: 49500 4 : 1200 : 240. If 3100 24L00

C : Tet&ta : 42 22: 64: '320 0: 1600: 50C$): 162000:16: 10:300 0:0MM3 605000

PLA-TwiP484Q Thlt ANDHRAPRADESH IRRIATION PROJECT (SRECSUS-PROJECT) VILLAEE-NilSEACTION PLAN Anure-XXlI ELOCf('IV & VI II PATTAIGGNT./HOUEESEETC. Amount in Rs.

:ou-se : Aans -itance :Naotf PAPs :Praductive Asset: Other Ecannhiic .:cntructiaon: iavtenance : i.attie wnte-:-: S' : the Nans of the incane wise : 5raqn : Assistance Viacation3i Trainina : 5rant : Aiilanace .nafice al1oance:Econwic 4g.: 1tarn(ia : uIzace ~ ~ - ~ ~ ~ ~ ------~~-- -- 'st~ IIAS MCIsIe Loan: :: : : ~~~~:Grans

BPL: APL NO: -uunt :-Chuiian . DCRA : Maount : Loan : No , Amount:NO Amount:NO: Amunt :

: : : : : : : : : : : : : a : : : a Amunt:

It 2 a2 :3 i 5:6 7 : 6 9 :t1 : l l 12 :1 3: 14 15 :16 :17: a :: 20:

I manar 31r 1 Kaa.aii -: 1: I: 5000: 600: - : - : 0: 0: 1:10000: 1: 4500: -: 0: 2100: 0:

: :;.m' laolurmml : 2 2 4 2000J 600 4000 : 2 6000 1200N : 4 :0 1: 4500 - 0 75100,4 12 0I

2:pans;illm :.Knidedu I: 2 10000: L ): 200: 1: 30: 64)0:L 2:000: 1: 45I4): 1: 1200: 41300: 6000:

3: :hadur : 1: - 1: 500 0: 600: 1000: - : 0: t3: 0: -: 1: 450: -0: 1 0:

: : Total : 4c 4: 8: 40000: 2400: 7000: 3: SW3: 180: 7: 70000: 4: 100:1: 1200: 14760: 16000A:

jk-61 .wLl THIRD,PNIhRA PRADESH IRRISATION PROJECT Ann uri-XXV (SR.BCSUBPROJECT) AESTRACTPROJECT AFFECTED PERSNS ECONOMIC REHABILITATION PRORAWiE F I N A N C I A L i U T L A Y Rs. IN Lk'.PS.

:PrZFctiVe Other Econotic: Vocatioxnal Trinine : .4Qusecistructioan: Maintenance : Cattle M,ainte-: Grand Total A:iet Grant : s3sistance Grant Allowance :nance allowance, Aksi5tance

NO : Aszsnt :ChulLah i DWCRA: No : Aaunti: Loan: NO : Aisaont NO : Airaunt: NO Amount :Gpant : L.oan : : : ^ zAeuntAmount: : : :

4 6 : : 10 : :715L 12 3: : 1.5 : 6

MAINCANAL a . . . ------:

af Patta lands :1439 : 71.'5 4.76 I1.13 : 248 7.44 14. - 0 794 :35.730 - - 131.010 14.88

t) Go'4 / fHouses $ : 22S10 1.5') 3.46 60 2.40: 4.80 192 19.20 250 11.250 2'2 0.26 60.1704 4.60

TO T A L :1881 94.05 6.26 14.59 328 9.4 19.68 192 1.20 1044 46.98 22 0.26 191.18 , 19.68

BSLOC IV' & VIIIl : :

a! Patti lan.ds 6: 3.20 0.22: 0.50: 10: 03.30 0.60 - 0: 36: 1.62:- -5.840: 0. 60

b) Gvt f Houses 8: 0.40 0.02 0.07: 3 0 0.18 7 0. 4 0.18: 0.02: 1.480: 0.18:

T 3 T A L 72 : 3,60: 0.24: 0.57 I 3: 0.39: 0.78: 7 0.70:, 40 1.80 1 0.02 7.320 da7B:

6 R A N O T r T A L :1953: S7.65: 6.50 : 13.16: 341: 10.23t 20.46: 19 t 19.90: 1084:48.78: 23: 0.28: 198.500: 20.46:

JK-69 Annexure- -XVI OrganisationalChart for ERP

Pri Secretary (Irrgn & CAD)

CollectorNandval DistrictDistrict Colletor Colletr .Sub R &;R Officer

rj) Spi Collector(LA) Jt. Collector PD DRDA DDO ZPP DM Housing

SE Pro)S L DR Ast rojO0

EE Divn Dy. Tahsidar . MRO MDO/MRO VDO DyEE

EE |Rev Inspector Rev. Inspector VDO/VDOWomen

VAO

18 THIRDANDHRA PRADESH IRRISATION PROJECT Anneu:re-XXVII RESETTLEMENTPi.REHABILITATIGIN PfRlJECTAFFECTED PERSONS ECMNOMIC REHABILETATIOtN PROGRAMME (PAPERP) SRC&SRSF SENERALA.EST ACT 3F BUDGET Rs.La;:hs

: SREC SRS::

Discriution tfasinCanal Blcc: IVIndicative :SRANDTOTAL :& for :Indicative : ,VIII Rqiiainino s : blck s

______- - -_ ------

A. LandCompensation 2030.40 22.M30 1496.500 37068.600 879.930:

B. Resettlement 33.120 - - : 3.120:

C. RehabiiLtation : 201.180 7.670 72.BSO: 139.0B4: 421.024

LoanCoafwnen.t (19.686)(0.78) (7.200})s 3.20) (40.860:

D. Prdiect Manaement 27.70?0 0.50( 29.000 44.4r0 101.200

E. Prtoict Administration 29.000 - 9.610 20.116 58.726

491.001)231.0)00 1600.;00 7272.000 9594.000 Add loan Comiio. 19.620 0.7803 7.200 13.200 40.e60 -_-_-_-_-_------_ ------_-_-_------!

TOTAL .510.680 Z31.7801607.2000 7285.20)0: 9634.860

6'ib-Project Total(MATO (El: 2322.000: 7272.00 95994.000

Add Soillover of AFII 96.6:0. 17.500 116.300

Total 2420.6,10 7289.50)0 9710.300

oasn : 27.660 13.200: 40.866

RAWDTOTAL 2448.460 7302.700 975t.160 (Includinorloan) : jk-70 THIRDlA.N'DWRA PFAO.wiS4s IRRIG.a'SATI, FROJUEC'T Amix|urie-XXV11 fQE3ETTLEMENTrJ HF-BIRLITATE0NI PROJ1SC'AFFECTED PERTONIS E££-tl.lC RE44.ILITATIT4 P3ROAMtFE(PAPERP DETAILEDPUDGET FCR MAIN CNAL 4ND PLOCKY IV t. VIII

I tern ' i1. tlain Canal No, Mluck IV & VIII

A Landcomsensatiai a'. R,. 1.25 lakh aer ha clus, 30%S£latiljm far CQlh0ueniiatiza3Of 137.00 ha (Eiloc:I to KV!ex,e t IV t. Vill descrtaicharoies as L.S. 200.000 222.630

Ane;ure 'N .33.120

C RehabiLitati.an

,I) ppoduct.i-vesNnn oran'. 1 Rs.5.000 ovr PFP i) Pattia land 1439 71.55) 64 3.200 ii) Pattai/ovt.land .hnause 442 22.100 8 0.400

bi OtherEc!-.nf.is lsi5tance

O DW*BA(Patta) 1113 lLIDm 50 0.500 iil US40P.Patta/(6ovt.)/Hu-e- .346 .3,.46 7 0.070i iii) Soe: chuilla (Patta) 794 4.760 36 0.220 i'v)'Sokelss 1h0alleas 250 1SS0.50 4 0.020

t Vacatioiait Traii,iin Grants corn}oint

Patta lal.ld 240 7,440 10 0.300 Patta!Oeafnientla,'dsf!i4o3uses Ro 2.400 3 O0M09

Le-ancliaa:.ienit

Patta lands ,2'4 14.Bi) 103 i0.60 Patta/Go2vern.4nt!ands(i.ulsses 90 4.900 3 0.180

ji) )Jegi.,nl EQ.4atructi4Jnanant ~~-~~-~-~~~ r--______------_ __ _ _

Oi-5,3.3I aried 192 19,20y) 7 0.700

el .aLntenanceall' aant l

,tr PAF-F-Ptattl 794 35,73Ž 36 1 .62.0 Patt&a.v;t.?/'44auts 250 11.25( 4 0.180

fB CattleMaiitna rc- anlls..4ja',rc

DiaaiacaaLl2 2s-; 0.260 2 0.020 .l1 Tnainur, 1(4.0(430 0.550

S£h-tltal s-f Ct 2,4 1,104 244 7.070 ------. It ii- N. daicNCanal No. Block IV & VIII

D Proiect lanaceimeqt

a) S6xio Economicstudies and 15.000 action nlan b) C'nsultancv & Technical 03,7C,) .500 ServiCe,5 c) tanniturina & evalhiation 1).OW dS TraiLiinilf R & R Staff 2,iAl

5u0-t'utal of D- 2.70i) 0.500

E ProjectAministration

a) Ecuionent furniture s.ularie-. 10.000 stationeVryeki. b) Continfenci's 10,00, c) Enl;eoeinseu thndevelw,ent $ 000 pr¶orafnmeand leadershiD developmentcadre

9jb-totai onft; 9.000

Tstal; 4P1.0 2.31.000

%AlncoT}norit I9. SPi 0.780

,rF1NTTAL IN4CLUDINN6LGN 5t0.690 2-31.760

JK-71 ,HIPD P PDE6HIA GPT1APROJECT R.EEETTE-rgtTEs_tt.E4 AN;ESH REfAJ~IT[ThH)N [tAi3 PROJE6TAFFECTED PERS.0 ECONOcu1CREHABtILTTTION PROGRA-tME (PAPERP) iDNDICNTVE.BLUHET FOR 9'P.K L to XVX1EXCEPT IV & VIII Annexuri-XXIX

SR'SP ?~~~~~ Rs. in LOkhs.

El. RB'," SUSP N.z. Descriotion ------N4o. AmooAt tAa. Awtunt

A Land Cotiensatizn 8 1.25 Iakh uGr ha Plis; 30% 'i-tiu'l (in haW 916 14EG.50 4350 70?68.8)

B 5e,z nt - - - - c Rer3ailitation 670 - 1220

j) Prod,u,gtive agssa aran't 8 53000 67i 33.SO) 122.0 61.0 s~qrPAP ii) E>:GnomicAassitance for 370 2.22 680l 4.CM olk;el4s a @Rs .600 or iii) ReI'lvlun fund fwr sinien 5301) 5.34) 960 9.6( thrift orouns 8 Rs.10I ea-ch iY) Trainin'a anid eif eimulomEnt4 12l 3.64 22 6.60 v) Triinino and5e1f mluvwt 120 (7.20) 22D (13.230i loancnm. 8 Rs. 6000-

,ii} Mainteniance1a~v1an. e e RS. .370 16,65 690 0.600 4t53 f)

4ii) Cattle Maintsicanct a1bwance 8 10 0. 120 17 40.204 Ra. 1200/- vili) Hxiipo constpniQf w}ant 65 6.5 1203 12.0o0 42Fs.lc0000- 'disolaced ix' Trainin' 5.00 15.00

72j.86 139.(84 ------5i. 9RBC SRSP ,,". E,sl SC r i O t iol-- - 'o. Awunt to. Amount

D PpeJl;tt anaient a) s.cio Ecanomic Studies and 15.00 30.00 Action Plan

3t Cn;ltan4Y and Tichacn al 1.00 1.00

clOl]niturina 21Evaluation 6.00 9.13G

!4 %Ti'ain0to of R & R staff' 5.0(0) 4.W

`9 00 44.00 0.00

E Pi'obt,:tAda.inist,. t ion Eiunlment. furniturs. Salarv. 3.03 7.1)1

b) Continmencss 3.10) 6.50

ci Entsr.rnups io dsvolmioent 3.610 6.616 Driora1mmeand Leader shM deloo~itcaore

9.61 20.116

Total I 00. 04) 7272.001

To0talLoin a covnetn r 7.2N 13.21

Grandtotal inclucino land 167.2 7285.200 ac,-uisition

i;73 THIRDANOVRA FRADESH IRR!2GTIgN PROJECT hNNEXURE-XXX R:EETTLEMENITPUDREA4BIL !T'lTON YEARLYFI NCA1'LCUT LAY fOR PROJECTAFCTE PPERE.O1 EC_n11ICPjEHPLITAT1ONJ PROGRMThfE (-APERP) SR20 M4INCAN1AL AND BLOCK IV ?,.VIII R-s. MiIlionsI

iS,Vitv TOt3al t9N}-96 96-97 97-98 9-99 1599-201')

1 P.inekniof Dec,rl;tal ).O) 4,t,00 2.00 B.0-( aisounts

L Land7.A;ionsation 22 26 2:2.26 - - -6

iuaourt Prorumm,e 9.76 - 4.t)i) 5.76

4 6SIT4.lesschulla (,65 - 0.6 - Prua.te~

5 RmoIytnQ fu5nLfor 1.52 - 1.52 - thrift gsruns

6 Vacational trainino Grant t.02 - 0.20 0.22 Loan '2.05)

7 Festtiemei.t & iHou;s orant 7.8 4.00) 3.029

B Maintsnanzetrant 4.88 2,75 2.13 cattlil al1leanfil

9 Projvt Tianaolnlnt 2.22 1.r5 0I0 .2 0.)20 0.92

10pro a t 2.90 0.52 0.52 0.58 0.58 0.58 Admifnistritiaon ------_ -___------__ - - -- -_ - - -_ ------72.89 35' 9 2.9b 1.4.76 1.50 0.58

IK-72 SRISAILAM RIGHT BRANCH CANAL ANNEXURE- X)'XXI

IMPLEMENTATION SCHEDULE OF LAND ACQUISITION FOR BLOCK IV

Si. Year 1 1994 1 1995 1996 iN. DESCRIPTION iNo. Montch 1 3 ----5 - 9 5 7 T9 t 1 l1 31 5 7 919 i x 7- 9

______H... 1-7 __ ,

I. CONSTRUCTION 1 [ __

II. LAND ACQUISITION I.Submission of K LP Schedule

2.Completion of l _l ___ - 1_-____ Survey l

3.DN/DD I Publication .

4.Award | SRISAILAM RIGHT BRANCH CANAL ANNEXURE- '1I

IMPLEMENTATION SCHEDULE OF LAND ACQUISITION FOR BLOCK VIII

Year , 1994 | 1995 '1996 . . . 'Si. DESCRIPTION . ! - _l i Month ~5 -7 9 11 ,1 3 5 7 19 11 11 3 15 7 19 11

I. CONSTRUCTION ____ _ - _

II. LAND ACQUISITION !

1.Submission of I I LP Schedule , i~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ ' ! j | i ' , | * . | I i I , ,

2.Completion of | Survey .l , I

1 3.DN/DD Publication

4.Award SRISAILAM RIGHT BRACH CANAL ANNEXURE-XXXII IMPLEMENTATION SCHEDULE OF PAPERP Training, Skill development and Self Employment

SI Name of Activity Year 1995-96 j 1996-97 1997-98 1998-99 No. fAciiy .....-_- Qtr. 1 2 3 444 1 2 3 1 2 4 1 2 3

j . Identification of youth for training and selection of activity.

2, Identification of Centres. IZ,I.

3. Imparting Training, i ,____

4. 1 Conducting EDP

5. Completion. of . formalities for establishing Unit/ I activity Tying up with Bank loan.

6. Establishing Unit |Z '

7. <,Monitoring and Midterm correction 8. Evaluation

9. Final correction Measures.

Ist Quarter - April - June 2nd Quarter - July - September 3rd Quarter - Oct. December 4 ~t4 Quarter - Jan. - March SRISAILAM RIGHT BRANCH CANAL ANNEXURE- XXXIV IMPLEMENTATION SCHEDULE OF PAPERP Productive asset support Programme

Si.! .No. Year 1995-96 1996-97 No. of 1997-98 1998-99 1999-20 Activity oNamef _ , . PAPs. Qtr. 1 | 2 3 l.4 1 4 4 12 !3 4 1 2 ,3 4 1 2 ! 3 4 11 21 3

1. ' Preparation of District Credit plan for PAPs

2. Verification of PAP- and collection I of applications

3. Processing of application and issuing sanctions | ,4. Release of grants and loans

5. Grounding of I______Scheme 1

,6. 'Concurrent . monitoring and corrective measures.

7. Evaluation

8. Final correction , measures and additional support -A

Ist Quarter - April - June 2nd Quarter - July - September 3rd Quarter - Oct. - December 4th Quarter - Jan. - March SRISAILAM RIGHT BRANCH CANAL IMPEMENTATION SCHEDULE OF PAPERP ANNEXURE- XXXV Group Economic Activity for Women

ISi. Year '1995-96 -1996-97 1997-98 - 1998-99 'No. Name of Activity t 1 314 Qtr. 2 3 4 1 2 3 4 1 2 1 2 3 4

1. 1 Identification of } 2 3 of Groups

2. Group Formation through PRA

3. Commencement of ______thrift Activity L

4 1 Identification of ,_' _ Economic activity

5. Financial Support _i;-_ 1

6. Monitoring & ,__r _ _ Corrective Steps |_. I .i

.7. j Evaluation |

8. Final Corrective measures and , additional support

Ist Quarter - April - June 2nd Quarter - July - September 3rd Quarter - Oct. - December 4th Quarter - Jan. March SRISAILAMWRIGHT BRANCH CANAL

IMPLEMENTATION SCHEDULE OF PAPERP ANNEXURE- XXXVF HOUSE CONSTRUCTION & RESETTLEMENT

sl. Year 1995 1996 No. Name of Activity Ii Name of Activity Month 4 5 6 7 8 9 10 11 121 2 3 4 |5 6 7 8 9 10 l1

1. Selection of site I i : in consultation with PAPs . .

j 2. Acquisition of site

3.. Layout plan and iI _ plot development . J

4. Internal road ii_; .' i

construction I'' _

5. Drinking Water facility 6. Electrification Z i

7. Construction of - ' _ -. , School Buildings&j ' i' - +i ' i i' s Community Halls j | I r-'

8~. Construction of houses I__1__-

9. Shifting to - I , New site I

110. Supply of Smokeless Chullahs .

I!l. Plantation of --- I----i__ __ _n_____' _ Avenue Trees l i -|

______I_ _ _ _ _ lI i I_ _ _ SRISAILAM RIGHT BRANCH CANAL ANNEXURE-X /i2 IMPLEMENTATION SCHEDULE OF PAPERP

Payment of Cattle allowance and maintenance allowance

Sl | Narme of Year 1;1995 19 Monthl5 6 7 8 9 10 11 12 1 2 3 4 5 6 17 8 1 12

11. Collection of applications and I confirming the PAP~Fs.

,2. Opening of Bank Accounts ,

3. Depositing the . i Grant i

4. Utilisatiion 'I,_ by PAPs __ Fig. 1.

i ,>@(~~~~INDIA

\NDA < _-_ _ANDHRA PRADESH

A~~~~~~~~~~~~~ " , ANDRA PROJECT SITE

&MAWHOUCNAGAR

, \ . _ .KURNOOL t

KURNAOOL _ i . DISTRICT |> ,$

eN - ~/;PRAKASAM THIRD A.P IRRiGATION PROJECT .. M F * S ~~~~~OISTRiCT

r z p J z"s ~~~S R B C COMMAND AREA t-2.>s,> P . ~~~~~LOCATION MAP

CUDDAPAH DISTRIC'T r ,,, Ti_.Ht A* GU t _E. NO. ~-SRtSAILAMDAM

AL^F U R r~~~~~~OTM IFItI)ODY AOU

D / ( - (AI4OIKOIK"^~- - 0 ftKCHtNA 5 URMOOL~~ ~ ~~~~~~~~~~~~~~bRA H5-EADO/REGULATORf j 1 O N E X

I 5 SRO\ C . ALIGNMENT

COIIbX A|^k U SA~ HTA VIUi"I u SRBC AYACUT

PANYA1-9?7%0 PLL RIVERS,RESERVOIRS

10t_9/- .-J'KUf OL ISTRICT '

X ; < otr' o ;A, fIn wsrl,

*CUDDAF'AH

Is /SUI~t~OOLDS TRICT

45 AI '< <.'

TVNIRD A.P IRRIGA'TION PROJECT

I Dlt| I) Il A

<-tA) bAY tr S R B C COMMAND AREA

r. A L "2< n .II[IDEX MAP

ISAI*TAIJ (AIM |t tIJC A4AL ~~~~~~- 'A-

INDi INDIA ' > . -

-- i - -____ - - -~ANDHRA PRADESH 11~~~~~~~~~~~~~~RJC, SITE

,AD$LABAD DISTRI'CT | /

r* > KK MNAGAR 4 - _ NIZAM,ABAD ,-O\lT -'S ~~~ ~~ ~ ~~ ~ ~ ~~~~~~~~~~~~~~~~~~~~~~~.-, DISTRICT,

,__w , , -@ w WARANGAL ) '~'~' / '\ ) DISTRICT, SRI RAIM &&CAR PRO'; -CT

MIEDAK DtSTRICT -- X . s 4 o LA ~~~LOCATI ON MAP NALGONOA { , ,- > DISTRICT ( I< |aLOWRI RMANSAGARDAM94 r P k, I~~~~~~~~~~~~~~~~~~~~~~~~15 /d~~~~~~~~~~~~~~~~~~~~~~~~~~~~.

K^.840 ~~~~~-<\J

IANI ROE KAATY CANA COMN 0 ~ ~~~~~~~~~~~~~~~~~~~

X, ~ ~~~~~~~~~~~~~~~ N5XD$CE' X -' ] t 2 1< ~~-% ' ' ,- : 'i 0

KURNOOL ,;

- AS .' BANAKACI1FR'L

*Z=' 0 REGULATOR

y45 . .

.'__:LGqRAKALLU BYPASS CANAL

OWK TUNNEL---

4.r14SERVOIR

CANAL IN SRTS1A-UJT_RL _tA FOREST,AREA LOCATION MAP OF FOREST LANDS S.rI.B.C. REt I LITAlTION L ) Lv1EtJ T Cor- tVA\LA VILLAqE

4 ~ ~ ~~~~~~~~~~~~~~~~~~~~ 14

Jf, C,A 7 V ;f f, ;h X

;5 19~~~~~~~~~1 1A- 1

(~~~~~~~~~~~~~~5~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ I

I ------S~ ~~~~~~~~~~~~~~~~~~~~~~~

:5An 3)','21l ! | "f31/! 8 5~~~~rl /625 6~~~~Eos-TN5 P\4<\

.14 ,- S R /C 3 T 1,1Ch

\F AFECTLgAREA t CX1w> PRiOVOSEPCOLONY hfb OUSTES II P O-l \ 0 RCAo I-i ~~ ~ ~ ~ c

1<-~~~~2 2 .-. 2~~ ~ ~~~~~~~~2

#Z4A

G\\T. 1EZLAN PJYTTA L A A) Z)

tr7OWVMMANror~Z.~ 1).~£3PAAfZTM

()'T '512 F~~~~ ~AYOu O r~sL A CFN-r OSEFi

DTISPLAC LI> FAMILI ES OF \tANALA '4ILLAG|