TUBULAR BIOREACTOR FOR HYDROGEN SULPHIDE REMOVAL FROM GEOTHERMAL POWER STATION COOLING WATER
Rob Fullerton – Beca Ltd, New Zealand Taupo – North Island NZ
Taupo Wairakei Wairakei Geothermal Power Station
• Wairakei – one of earliest geothermal power stations in the world • commissioned 1958 – 1963, installed capacity 192MW • current capacity 157MW Cooling Water System
. ~17 m3/s Waikato River water for direct condenser cooling
A Station B Station
CW in
CW out
CW = Cooling water Cooling Water System
Geothermal steam 0.2m3/s
Steam Turbines Cooling water + condensate
Direct contact 17m3/s condensers 17.2m3/s
Water pumps 157MW power
Waikato River Waikato River The Challenge
. H2S in the geothermal steam condenses into the cooling water and is discharged back to the river – aquatic impacts
3 . H2S concentration in discharge about 1000mg/m (~1mg/L)
. Discharge Permit: H2S discharge to river ─ Prior 2012 : No consented limit - 10,000 kg/week ─ By 20 August 2012: 2,800 kg/week (72% reduction) ─ By 20 August 2016: 630 kg/week (94% reduction) . Requires sulphide reduction to ~50 mg/m3 The Challenge
Geothermal steam
containing H2S 0.2m3/s
Cooling water Steam Turbines + condensate 17.2m3/s
Direct contact 1000ppb H2S 17m3/s condensers To be reduced to 50ppb by Cooling water 2012 157MW power
Waikato River Waikato River Sulphide Oxidising Bacteria - A Solution?
• Need for strategy to control sulphide recognised • Thinking started in 2000 • SOB naturally occurring – esp. in geothermal areas
• Biological sulphide oxidation - conversion of H2S to sulphate • SOB biofilm observed on existing outfall structure • Cooling water from power station 30 - 35oC, pH ~6,
dissolved CO2 • Could SOB be used to achieve 95% sulphide removal? Initial Pilot Trials – 2000 - 2005
Algae overgrowth Sheets – channels - Pipes The Eureka Moment
SOBs seem to grow best in fast moving flow Pilot Testing – Initial pipe trials
Sulphide sampling
• Biofilm established on inside of pipe – good H2S removal • High velocity prevents excessive biomass build-up • Lack of light prevents algal growth • Pipe bioreactor proved in concept Pilot Testing 2010 100mm dia. x 200m /150mm dia. X 400m SOB Biofilm
Beginning section 100m End section 200m 100mm dia. x 200m results 150mm dia. x 400m results Sulphide Removal Model
S = substrate concentration 푑푆 휇푚 퐵 푆 µ = maximum specific growth rate = m K = half-saturation constant 푑푡 푌 (퐾푠 + 푆) s B = biomass concentration Y = biomass yield
• Sulphide concentration is low B >> S • biofilm quasi-steady state with constant thickness, viz. growth = detachment
푑푆 푆 dS/dt = rate of substrate change = −푣 v = maximum substrate utilisation rate 푑푡 푚 (퐾 + 푆) m 푠 ks = half saturation constant
2 • Calculate removal rate for each pipe segment (gH2S/m /d) • Fit to non-linear least squares Monod model Monod curve fitting
2 3 vm = 13.85 gH2S/m /d Ks = 235mg/m Design Curve
Minimum pipe length ~160m +25% safety factor = 200m Pipe bioreactor - process concept
100mm dia. x 200m Outlet Velocity 0.8m/s sulphide Flow = 6.7L/s < 50ppb
100mm
Sulphide oxidising bacteria biofilm Power station cooling water forms on pipe Inlet sulphide = 1000ppb inside surface Full scale pipe bioreactor concept plant
Flow = 17m3/s ~2000 pipes x 200m in parallel
390km of pipe !!
200 x pipes per layer 10 layers Proposed sulphide treatment system 2012
Geothermal steam + H2S
Pipe bioreactor Steam Turbines 17.2m3/s
Direct contact 17m3/s condensers 4.2m3/s cooling 13m3/s 1000ppb water 50ppb H2S H2S 157MW power 2,800kg/week 17.2m3/s
Waikato River Waikato River Proposed sulphide treatment system 2016
Geothermal steam + H2S 13.2m3/s
1000ppb H2S
Pipe bioreactor Steam Turbines
Direct contact 13m3/s condensers
<80ppb H2S
Cooling water 630kg/week 120MW power
Waikato River Waikato River Full Scale design Challenges
. Design began January 2011 . Never been done before – collaboration between contractor and designer . Physical constraints – high groundwater + hot (60oC) . Power station can’t stop – build off-line . Hydraulics – available head 1.5m – require pumping . Energy efficiency – design low head system . How to install 380km of 100mm dia. HDPE pipe Innovative “over – under” syphon
100m
. Bioreactor pipe configuration ― 1890 pipes ― 5 banks of 378 pipes ― 42 pipes x 9 layers ― Magnetic flow meter each bank Bioreactor Layout Site Overview December 2011 Construction of pipe field
. PE Pipe Design ─ Extruded on site ─ 100m lengths ─ No joints ─ 2.5mm wall ─ Embedded into weak cement matrix – “soilcrete” ─ 378km in 5 months Construction of pipe field Construction of pipe field
Soilcrete embedment made from local pumice sand Construction of pipe field Construction of pipe field
Return chamber – end pipe field Pump inlet channel Bioreactor outlet channel Bypass weir Bioreactor Performance Permit Compliance Full scale performance
3 . H2S concentration meeting target of >80% (~50mg/m ) . Power station meeting sulphide mass emission limit of
2,800 kg H2S/week
. Optimisation of operating conditions to minimise power consumption . Current performance gives confidence to meet 2016
discharge limit of 630 kg H2S/week The world’s largest tubular bioreactor