Tubular Bioreactor for Hydrogen Sulphide Removal from Geothermal Power Station Cooling Water

Tubular Bioreactor for Hydrogen Sulphide Removal from Geothermal Power Station Cooling Water

TUBULAR BIOREACTOR FOR HYDROGEN SULPHIDE REMOVAL FROM GEOTHERMAL POWER STATION COOLING WATER Rob Fullerton – Beca Ltd, New Zealand Taupo – North Island NZ Taupo Wairakei Wairakei Geothermal Power Station • Wairakei – one of earliest geothermal power stations in the world • commissioned 1958 – 1963, installed capacity 192MW • current capacity 157MW Cooling Water System . ~17 m3/s Waikato River water for direct condenser cooling A Station B Station CW in CW out CW = Cooling water Cooling Water System Geothermal steam 0.2m3/s Steam Turbines Cooling water + condensate Direct contact 17m3/s condensers 17.2m3/s Water pumps 157MW power Waikato River Waikato River The Challenge . H2S in the geothermal steam condenses into the cooling water and is discharged back to the river – aquatic impacts 3 . H2S concentration in discharge about 1000mg/m (~1mg/L) . Discharge Permit: H2S discharge to river ─ Prior 2012 : No consented limit - 10,000 kg/week ─ By 20 August 2012: 2,800 kg/week (72% reduction) ─ By 20 August 2016: 630 kg/week (94% reduction) . Requires sulphide reduction to ~50 mg/m3 The Challenge Geothermal steam containing H2S 0.2m3/s Cooling water Steam Turbines + condensate 17.2m3/s Direct contact 1000ppb H2S 17m3/s condensers To be reduced to 50ppb by Cooling water 2012 157MW power Waikato River Waikato River Sulphide Oxidising Bacteria - A Solution? • Need for strategy to control sulphide recognised • Thinking started in 2000 • SOB naturally occurring – esp. in geothermal areas • Biological sulphide oxidation - conversion of H2S to sulphate • SOB biofilm observed on existing outfall structure • Cooling water from power station 30 - 35oC, pH ~6, dissolved CO2 • Could SOB be used to achieve 95% sulphide removal? Initial Pilot Trials – 2000 - 2005 Algae overgrowth Sheets – channels - Pipes The Eureka Moment SOBs seem to grow best in fast moving flow Pilot Testing – Initial pipe trials Sulphide sampling • Biofilm established on inside of pipe – good H2S removal • High velocity prevents excessive biomass build-up • Lack of light prevents algal growth • Pipe bioreactor proved in concept Pilot Testing 2010 100mm dia. x 200m /150mm dia. X 400m SOB Biofilm Beginning section 100m End section 200m 100mm dia. x 200m results 150mm dia. x 400m results Sulphide Removal Model S = substrate concentration 푑푆 휇푚 퐵 푆 µ = maximum specific growth rate = m K = half-saturation constant 푑푡 푌 (퐾푠 + 푆) s B = biomass concentration Y = biomass yield • Sulphide concentration is low B >> S • biofilm quasi-steady state with constant thickness, viz. growth = detachment 푑푆 푆 dS/dt = rate of substrate change = −푣 v = maximum substrate utilisation rate 푑푡 푚 (퐾 + 푆) m 푠 ks = half saturation constant 2 • Calculate removal rate for each pipe segment (gH2S/m /d) • Fit to non-linear least squares Monod model Monod curve fitting 2 3 vm = 13.85 gH2S/m /d Ks = 235mg/m Design Curve Minimum pipe length ~160m +25% safety factor = 200m Pipe bioreactor - process concept 100mm dia. x 200m Outlet Velocity 0.8m/s sulphide Flow = 6.7L/s < 50ppb 100mm Sulphide oxidising bacteria biofilm Power station cooling water forms on pipe Inlet sulphide = 1000ppb inside surface Full scale pipe bioreactor concept plant Flow = 17m3/s ~2000 pipes x 200m in parallel 390km of pipe !! 200 x pipes per layer 10 layers Proposed sulphide treatment system 2012 Geothermal steam + H2S Pipe bioreactor Steam Turbines 17.2m3/s Direct contact 17m3/s condensers 4.2m3/s cooling 13m3/s 1000ppb water 50ppb H2S H2S 157MW power 2,800kg/week 17.2m3/s Waikato River Waikato River Proposed sulphide treatment system 2016 Geothermal steam + H2S 13.2m3/s 1000ppb H2S Pipe bioreactor Steam Turbines Direct contact 13m3/s condensers <80ppb H2S Cooling water 630kg/week 120MW power Waikato River Waikato River Full Scale design Challenges . Design began January 2011 . Never been done before – collaboration between contractor and designer . Physical constraints – high groundwater + hot (60oC) . Power station can’t stop – build off-line . Hydraulics – available head 1.5m – require pumping . Energy efficiency – design low head system . How to install 380km of 100mm dia. HDPE pipe Innovative “over – under” syphon 100m . Bioreactor pipe configuration ― 1890 pipes ― 5 banks of 378 pipes ― 42 pipes x 9 layers ― Magnetic flow meter each bank Bioreactor Layout Site Overview December 2011 Construction of pipe field . PE Pipe Design ─ Extruded on site ─ 100m lengths ─ No joints ─ 2.5mm wall ─ Embedded into weak cement matrix – “soilcrete” ─ 378km in 5 months Construction of pipe field Construction of pipe field Soilcrete embedment made from local pumice sand Construction of pipe field Construction of pipe field Return chamber – end pipe field Pump inlet channel Bioreactor outlet channel Bypass weir Bioreactor Performance Permit Compliance Full scale performance 3 . H2S concentration meeting target of >80% (~50mg/m ) . Power station meeting sulphide mass emission limit of 2,800 kg H2S/week . Optimisation of operating conditions to minimise power consumption . Current performance gives confidence to meet 2016 discharge limit of 630 kg H2S/week The world’s largest tubular bioreactor.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    39 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us