Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

FORM 1

(I) Basic Information S. No Item Details 1 Name of the Project /s Proposed Retail Store and Office Building by M/s IKEA India Pvt Ltd., at Survey No’s 12 & 13, Nagasandra Village, Yeshawantpur Hobli, Bengaluru North Taluk, Bengaluru District, Karnataka – 560073 2 Sl. No in the Schedule 8 (a) Building and Construction Projects 3 Proposed capacity / area / length / Total site area: 56275.73 Sq.m tonnage to be handled /command Built up area: 97617.41 Sq.m area / lease area / number of wells to be drilled 4 New / Expansion / Modernization New 5 Existing Capacity / Area etc. Not applicable 6 Category of Project i.e. ‘A’ or ‘B’ B 7 Does it attract the general Not applicable conditions? If yes, please specify 8 Does it attract the Specific Not applicable conditions? If yes, please specify 9 Location 13° 02'53.69"N 77°30'05.05"E 13° 02'59.42"N 77°30'07.12"E 13° 03'01.36"N 77°29'56.80"E 13° 02'54.93"N 77°29'55.38"E 13° 02'54.26"N 77°29'57.27"E 13° 02'56.20"N 77°29'58.01"E Plot / Survey / Khasra No Survey No’s 12 & 13 Village Nagasandra Village, Yeshwantpur hobli Tehsil Bengaluru North District Bengaluru – 560073 State Karnataka 10 Nearest railway station / airport Nagasandra metro rail station - Adjacent (S) along with distance in km Yeshwanthpur railway station - 6 km (SE) Kempegowda international airport – 25 km (NE) 11 Nearest town, city, district Nelamangala – 11 km (NW) headquarters along with distance in Bengaluru – 13.5 km (SE) kms

1 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

12 Village Panchayats, Zilla Parishad, Bagalgunta village BBMP, MS Ramaiah Layout , Municipal Corporation, Local body Bengaluru, Karnataka – 560073 (complete postal addresses with telephone nos, to be given) 13 Name of the applicant IKEA India Private Limited Represented by Mr. Sven Persson & Mr. Pavan Gavaral 14 Registered Address IKEA India Private Limited Unit No 421, DLF tower A, Jasola district center, New Delhi -110044 15 Address for Correspondence IKEA India Private Limited 10th Floor Greenheart, Phase IV Mfar Manyata Tech Park Nagawara, Bengaluru 560045 Ph: 080 67903790 Name Mr. Pavan Gavaral Designation (Owner/Partner/CEO) Construction Project Manager Address IKEA India Private Limited 10th Floor Greenheart, Phase IV Mfar Manyata Tech Park Nagawara, Bengaluru. Pin Code 560 045 E-mail [email protected] Telephone no Ph: 080 67903790 Mobile 74069 87979 Fax no --- 16 Details of Alternate Sites examined, if Not applicable any. Location of these sites should be shown on a topo sheet 17 Interlinked Projects Not applicable 18 Whether separate application of Not applicable interlinked project has been submitted 19 If yes, date of submission Not applicable 20 If no, reason Not applicable 21 Whether the proposal involves approval / clearance under: if yes, details of the same and their status to Not applicable be given 2 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

(a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z. Notification, 1991? 22 Whether there is any Government Karnataka Government Order No. CI 212 SPI Order / Policy relevant / relating to 2017, Bengaluru, Dated 07.10.2017 issued by the site Department of Commerce and Industries (48th proceedings of State High Level Clearance Committee ) 23 Forest Land involved (hectares) No 24 Whether there is any litigation pending against the project and / or Nil land in which the project is proposed to set up? (a) Name of the Court (b) Case No (c) Orders / directions of the court, if any and its relevance with the proposed project.

II. Activity: 1. Construction, operation or decommissioning of the project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc) Details thereof (with approximate Information/Checklist S. No. Yes/No quantities /rates, wherever possible) with confirmation source of information data 1.1 Permanent or temporary change Yes Permanent change in land use will occur in land use, land cover or due to the proposed project. topography including increase in intensity of land use (with KIADB has acquired the land and given to respect to local land use plan) BMRCL for development of metro rail infrastructure. The change is from above situation to commercial i.e. “Mercantile/Commercial use - a retail establishment and store engaged in the primary business of retailing, selling, assembling & showcasing furniture and home furnishing, etc.”

3 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

1.2 Clearance of existing land, Yes No buildings are exists on site. Scattered vegetation and buildings? bushes and shrubs exist which will be cleared prior to the commencement of construction. 1.3 Creation of new land uses? Yes The site will be used for construction of retail store and office building. 1.4 Pre-construction investigations Yes Geo-technical & topographical e.g. bore houses, soil testing? investigations carried out at the site. Results indicate the presence of three layer sub soil which has been noticed as below  Layer I: Sandy silt with clay  Layer II: Soft disintegrated rock  Layer III: Highly weathered rock Chemical tests conducted on soil samples collected from the bore holes indicate that the pH levels, content of Chloride and Sulphate are well within the limits as prescribed in IS: 3025. 1.5 Construction works? Yes The project consists of construction of retail store and office building. 1.6 Demolition works? No Not applicable 1.7 Temporary sites used for Yes Workmen accommodation would be construction works or housing of provided at location away from the construction workers? proposed project site premises. 1.8 Above ground buildings, Yes The proposed project is a construction of structures or earthworks retail store and office building, which including linear structures, cut consists of basement, stilt and upper 4 and fill or excavations floors. 1.9 Underground works including No No underground or mining work will be mining or tunneling? carried out. One basement level for parking and utilities like pump room, underground sumps & STP, etc., 1.10 Reclamation works? No Not applicable 1.11 Dredging? No Not applicable 1.12 Offshore structures? No Not applicable 1.13 Production and manufacturing No Not applicable processes? 1.14 Facilities for storage of goods or Yes Materials which are used for construction materials? shall be stored in temporary sheds at site

4 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

which shall be dismantled after the construction is over. 1.15 Facilities for treatment or Yes Solid waste generated from the disposal of solid waste or liquid construction includes rubbles, used up effluents? cement, broken bricks etc. which shall be used for leveling internal roads during developmental stage.

Mobile toilets would be provided at site for workers during construction phase.

Solid waste generated during operational stage shall be segregated into organic and inorganic wastes. The organic waste shall be treated in bio-converter & inorganic waste will be handed over to authorized recyclers. The sludge generated from the STP will be used as manure for landscaping purposes.

The liquid effluent i.e. sewage is conveyed through a closed conduit to fully fledged sewage treatment plant. 1.16 Facilities for long term housing No Most of the workers will be hired locally. of operational workers? Hence no housing facilities are required. 1.17 New road, rail or sea traffic No Not applicable during construction or operation? 1.18 New road, rail, air waterborne No None envisaged or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No None envisaged transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission Yes Existing BESCOM cable is running along the lines or pipelines? site which is proposed to reroute around the south side of site periphery.

5 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

1.21 Impoundment, damming, No No impoundment, damming, culverting, culverting, realignment or other realignment or other changes to the changes to the hydrology of hydrology of water courses or aquifers. water courses or aquifers? The local hydrology shall be taken into consideration while designing the storm water drains. 1.22 Stream crossings? No There is no stream crossing in the proposed site. 1.23 Abstraction or transfers of water No Water requirement during construction form ground or surface waters? phase will be met through authorized water tankers. Water Supply & Sewerage Board (BWSSB) supply will be utilized to cater water requirements during operational phase 1.24 Changes in water bodies or the Yes Due to the proposed project, there will not land surface affecting drainage be any changes in water bodies, drainage or run-off? pattern etc. Runoff will be managed by adequate storm water drain system. 1.25 Transport of personnel or Yes An average of 700 construction workers will materials for construction, be deputed per day during the construction operation or decommissioning? phase, out of which 400 to 500 workers will reside in a dedicated camp site away from the site location and 200 workers will come from surrounding area. The local construction workers will be using existing transport infrastructure.

Transport of the raw material required for construction such as soil, sand, aggregates, gravel, water, cement and steel will be made through trucks covered by tarpaulin. The peak average of 150 trucks a day during excavation and lean average of 10-20 trucks a day are expected during construction phase. 1.26 Long-term dismantling or No Not applicable decommissioning or restoration works? 1.27 Ongoing activity during No None envisaged

6 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes Movement of people will be observed either temporarily or during the construction and operation permanently? resulting in the improvement of socio- economic conditions of the area as people from different communities will migrate here on permanent basis. 1.29 Introduction of alien species? No None envisaged Post-project plantation, to be carried out as part of the site-landscaping, will use only species which are native to the region in which the project site is situated. 1.30 Loss of native species or genetic No None envisaged diversity? 1.31 Any other actions? No None envisaged

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Details thereof (with approximate Information/checklist S. No. Yes/No quantities /rates, wherever possible) with confirmation source of information data 2.1 Land especially undeveloped or Yes Project site is an open land covered with agricultural land (ha) little vegetation and now it will be converted to commercial use (56275.73 Sq.m or 13.90 Acres) 2.2 Water (expected source & Yes Source of water: Authorized water tankers competing users) unit: KLD during construction phase and BWSSB supply during operation phase.

The water requirement for concrete is 5000 KL and 7000 KL for curing purposes for entire construction period (peak requirement will be 50 KLD). Water demand during operation phase of the proposed project is 426 KLD (fresh water requirement will be 225 KLD and treated

7 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

water requirement will be 201 KLD) 2.3 Minerals (MT) No Not applicable 2.4 Construction material – stone, Construction material like coarse and fine aggregates, sand / soil (expected aggregate sand, cement and steel will be source – MT) used. The raw materials will be sourced from the local traders. Yes Cement- 4000 Cu.M. Coarse Aggregate- 15,000 Cu.M., Sand-9000 Cu.M., Steel – 9,500 Tone Sandwich Panel required- 6500 Sq.M. and glass required is 1400 Sq.M. 2.5 Forests and timber (source – MT) Yes Timber will be used for door frames and windows. Wood alternatives are proposed to be used in the project with minimal use of timber as construction material. The materials will be procured from reputed manufacturers with test certificates as per BIS specifications. 2.6 Energy including electricity and Yes During construction phase, temporary fuels (source, competing users) connection of 100 kW will be taken from Unit: fuel (MT), energy (MW) Bangalore Electricity Co. Ltd. (BESCOM) to fulfil load demand and for Emergency purpose, DG set of 125 kVA capacity will be used. Fuel requirement for DG set considering 100% load is about 25 liters per hour.

The power requirement during operational phase will be 3999 kW and 4 No. of DG sets of 1250 kVA capacity for backup during power failure. Fuel requirement for DG set considering 100% load is about 250 liters per hour for each DG set. 2.7 Any other natural resources (use No No significant requirement. appropriate standard units)

8 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, No No hazardous substances (as per MSIHC which are hazardous (as per rules) will be used in the proposed project. MSIHC rules) to human health or Therefore no generation of hazardous the environment (flora, fauna, waste. and water supplies) The construction phase will require a maximum of 100 LPD of HSD for operation of 125 kVA DG set (about four hours per day). Fuel will be stored at site in temporary container

During operational phase about 4.02 m3/day of HSD will be required for running all the DG sets (about 4 hours per day). About 20.2m3 of HSD will be stored at site in a storage tank of 25m3 capacity. The storage and secondary containment will be as per the norms and approval of Petroleum and Explosives Safety Organisation. 3.2 Changes in occurrence of No Proper drainage and waste management disease or affect disease vectors will be adopted in both construction and (e.g. insect or water borne operation phases to avoid/ restrict water diseases) stagnation. This will effectively restrict the reproduction and growth of disease vectors. 3.3 Affect the welfare of people e.g. Yes The project will have a positive impact on by changing living conditions? the local population. This project will provide employment during the construction and operation phase of the proposed activity. Furthermore, the socioeconomic conditions will be improved in the surrounding areas. 3.4 Vulnerable groups of people No Not applicable

9 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No No significant causes of concern.

4. Production of solid wastes during construction or operation or decommissioning (MT/month) S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine Yes Construction debris of 750 Tons (maximum wastes 10 to 12 tons/day during peak period) is envisaged to be generated during construction period, out of which about 90% will be segregated at source, recycled and reused. 4.2 Municipal waste (domestic and Yes During construction phase: The waste or commercial wastes) generated from construction activities include shuttering wood, glass, cardboard, hardboard, plastic, metal scrap, cement bags, paint cans and packaging cans and packaging waste, will be sent to authorized recycling agency. While concrete, broken bricks and debris will be used for leveling internal roads. Municipal solid waste will be sent to nearest municipal bin.

During operation phase: The municipal solid waste will be treated in organic bio converter located within the site. 4.3 Hazardous wastes (as per Yes Used oil generated from DG sets will be Hazardous Waste stored in leak proof sealed barrels/drums Management Rules) and will be given to KSPCB authorized dealers/re-processors 4.4 Other industrial process wastes No Not applicable 4.5 Surplus product No Not applicable 4.6 Sewage sludge or other sludge Yes The sludge generated from the STP will be from effluent treatment used as manure for landscaping purposes.

10 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

4.7 Construction or demolition Yes The left over materials after the wastes construction activities shall be sent to the authorized recyclers and waste generated during the construction. 4.8 Redundant machinery or No The site is free from any redundant equipment machinery or equipment. 4.9 Contaminated soils or other No Based on the geo-technical investigations materials no soil contaminations found 4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes Yes Scrap from the stores/warehouse is envisaged during the operational phase. E- waste from the office buildings and used lead acid batteries from DG sets and which will be disposed to authorised recyclers

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion of Yes Emissions are mainly form the fugitive dust fossil fuels from stationary or emissions from digging, filling, handling of mobile sources material, transportation, use of construction machinery etc. during construction. Vehicle movement and DG sets used for power backup during power failure in both construction and operational phase.

The main emissions will be PM, CO, SO2 and NOx from HSD fuel used for the DG sets.

The DG set will be acoustically enclosed and provided with sufficient stack height so as to meet the norms laid down by CPCB/MoEFCC. 5.2 Emissions from production No Not applicable processes 5.3 Emissions from materials Yes The main emissions during the construction handling including storage or will be from loading and unloading of

11 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

transport material on the site and fugitive dust emissions from digging, filling, handling of material, transportation, use of construction machinery etc.

Emissions of PM, CO, SO2 and NOx from machinery and vehicular movement are expected during operational phase.

The particulate matter is controlled by sprinkling water at regular intervals on

paved roads. SO2 and NOx will be controlled by proper maintenance of vehicles. 5.4 Emissions from construction Yes Gaseous emissions are expected from

activities including plant and construction activities. PM, SO2, NOx, CO equipment are the known pollutants to generate from construction equipment’s and other vehicles used at construction site which are temporary in nature. 5.5 Dust or odours from handling of Yes Fugitive dust emissions from movement of materials including construction construction equipment, transportation of materials, sewage and waste material and movement of vehicles and odour from organic waste i.e. domestic waste, diesel storage and STP The odor generated from the sewage will be controlled by taking appropriate control measures like, diverting domestic wastewater to proposed sewage treatment plant and plantation of odor controlling species around the STP. 5.6 Emissions from incineration of No Not applicable waste 5.7 Emissions from burning of waste No Burning of waste shall not be permitted. in open air (e.g. slash materials, construction debris)

12 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

6. Generation of Noise and Vibration, and Emissions of Light and Heat S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data with source of information data 6.1 From operation of equipment Yes Noise level of around 75 dB (A) is e.g. engines, ventilation plant, anticipated during activities such as drilling, crushers concrete mixing, crushing etc and vehicle movement. These are temporary in nature and will be minimized by adopting proper maintenance such as greasing, oiling and insulations (acoustic enclosures) for noise abatement. Noise shall also be generated during the usage of DG sets for which acoustic enclosures will be provided to restrict the noise within the permissible limits. 6.2 From industrial or similar No Not applicable processes 6.3 From construction or demolition Yes Construction activities such as excavation, mixing, dumping and other activities shall lead to insignificant generation of noise and vibrations. These will be temporary in nature and once the construction is over, will be phased out. 6.4 From blasting or piling No No blasting or Piling .

6.5 From construction or operational Yes Vehicular traffic during construction phase traffic would generate noise ranging 80 to 85 dB (A) depending on nature of equipment’s to be used and construction methods, but it will be temporary in nature.

During operational phase noise from vehicular movement will be maintained well within the permissible limit. 6.6 From lighting or cooling systems Yes Selected cooling tower shall be certified for test procedure as per CTI ATC–105 and CTI

13 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

STD–201. The drift loss shall be minimized through eliminators and noise level is not anticipated to exceed 65 dB (A) at 3m distance all around the cooling tower. 6.7 From any other sources No Not applicable

7. Risks of contamination of land or water from release of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No Used oil from DG sets and oil containing spillage of hazardous materials rags will be stored in leak proof barrels/drums and handed over to KSPCB authorized re-processors/dealers. 7.2 From discharge of sewage or No Sewage generated will be treated in the other effluents to water or the proposed STP. The treated waste water will land (expected mode and place be used for flushing and in cooling towers of discharge) HVAC purpose.

7.3 By deposition of pollutants No Depositions of PM, SO2, NOx and CO into emitted to air into the land or the air are temporary as the DG sets run into water only during power failure. No sewage will be let on the land or into surface water body and therefore no risk of any contamination. 7.4 From any other sources No None envisaged 7.5 Is there a risk of long term built- No Proper environmental management plan up of pollutants in the will be followed for air, water, noise and environment from these solid waste. Hence, no long term impacts sources? are envisaged.

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires No The proposed project is a construction of etc. from storage, handling, use retail store and office buildings and does or production of hazardous not involve usage of Hazardous materials. 14 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

substances During construction phase, proper safety standards shall be maintained. All the workers will be provided with PPE (Personal Protective Equipment) as required under Health and Safety norms and educated in safe working practices from time to time. Regular inspections shall be carried out by competent safety personal to monitor safe site conditions, condition of construction equipment and tools, electrical installations etc. 8.2 From any other causes No Not applicable 8.3 Could the project be affected by No The project area falls in the Zone II of natural disasters causing Seismic Zoning Map of India (IS 1893-2002). environmental damage (e.g. The seismic factors have been floods, earthquakes, landslides, appropriately incorporated in the civil cloudburst etc)? designs for the proposed project. This zone is exposed to earthquakes having Modified Mercalli (MSK) Intensity VI or less and is equivalent to an earthquake of magnitude 5.0 in Richter scale.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data 9.1 Lead to development of Yes An existing metro line & station already supporting. exists in front of the proposed IKEA Store Utilities, ancillary development to cater future traffic projections. The area or development stimulated by development will have cumulative impacts the project which could have on infrastructure and natural resources in impact on the environment e.g.: the area in terms of high traffic on roads,  Supporting infrastructure water demand, power supply, waste (roads, power supply, waste or generation and disposal system, air waste water treatment, etc.) emissions during construction phase etc.  Housing development The Proposed site has connectivity with  Extractive industries existing sewerage and power lines located

15 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

 Supply industries in eastern side of the proposed site.  Other Appropriate infrastructure like roads, power supply, waste management and waste treatment plant will be developed within the site which will minimize the chances of occurrence of any adverse impacts and it enhances the supporting utilities, ancillary development in the surrounding area. Improved aesthetic look by avenue plantation and landscape development. 9.2 Lead to after-use of the site, Yes Development of IKEA Store will have which could have an impact on impact in terms of increased movement of the environment vehicles and people, water demand, electricity supply in the area. The proposed development is in accordance with the Master Plan of the area and the anticipated impacts can be minimized by implementing necessary mitigation measures.

A positive impact on the environment in the area is anticipated due to development of greenbelt. 9.3 Set a precedent for later Yes Similar new projects may develop in future developments 9.4 Have cumulative effects due to No None envisaged proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity S. No. Areas Name/ Aerial distance (within 15 km.) Identity Proposed project location boundary 1 Areas protected under Yes GKVK Botanical Garden – 8.7 km (ENE) international conventions, Lalbagh Botanical Garden – 14.1 km (SE) national or local legislation for Bannerghatta National Park – 29 km (SSE) their ecological, landscape, cultural or other related value

16 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

2 Areas which are important or Yes Water Bodies sensitive for ecological reasons - Doddabidirakallu Kere – 0.6 km (S) Wetlands, watercourses or Dasarahalli Tank – 1.3 km (SE) other water bodies, coastal Anchepalya Lake – 1.9 km (W) zone, biospheres, mountains, Chikkabanavara Lake – 3.4 km (N) forests Lakshmipura Lake – 3.5 km (SW) Matti Kere – 5.5 km (E) Herohalli Lake – 6.5 km (S) Kodigehalli Kere – 6.6 km (NE) Arishinkunte Kere – 7.8 km (NW) Hebbal Kere – 8.7 km (E) Sankey Tank – 8.8 km (SE) Malathalli Lake – 8.9 km (S) Aivarakhandapura Lake – 9.2 km (N) Nelamangala Kere – 10.2 km (NW) Heesaraghatta Tank – 10.5 km (NNW) Nagavara Kere – 11.3 km (E) Rachenahalli Kere – 12 km (E) Jukkuru Kere – 12.3 km (NE) Yelahanka Kere – 11.9 km (NE) Rivers Arkavati River – 4.8 km (WNW) Vrishbhavati River – 5.1 km (SE) Forest Jarkabande Reserve Forest – 4 km (NE), 7.9 km (NE), 10 km (NE) Narasipura Reserve Forest – 7 km (NW) Govindapura Reserve Forest – 8 km (NW) Sulikere Reserve Forest – 13.9 km (SSW) 3 Areas used by protected, Yes Jarkabande Reserve Forest – 4 km (NE), important or sensitive species 7.9 km (NE), 10 km (NE) of flora or fauna for breeding, Narasipura Reserve Forest – 7 km (NW) nesting, foraging, resting, over Govindapura Reserve Forest – 8 km (NW) wintering, migration Sulikere Reserve Forest – 13.9 km (SSW) GKVK Botanical Garden – 8.7 km (ENE) Lalbagh Botanical Garden – 14.1 km (SE) 4 Inland, coastal, marine or Yes Doddabidirakallu Kere – 0.6 km (S) underground waters Dasarahalli Tank – 1.3 km (SE) Anchepalya Lake – 1.9 km (W) Chikkabanavara Lake – 3.4 km (N) Lakshmipura Lake – 3.5 km (SW) Matti Kere – 5.5 km (E) Herohalli Lake – 6.5 km (S) Kodigehalli Kere – 6.6 km (NE) Arishinkunte Kere – 7.8 km (NW) Hebbal Kere – 8.7 km (E) Sankey Tank – 8.8 km (SE)

17 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited

Form 1 for “Proposed Retail Store and Office Building” at Survey Nos 12 & 13, Nagasandra Village, 2017 Bengaluru North Taluk, Bengaluru District, Karnataka - 560073

Malathalli Lake – 8.9 km (S) Aivarakhandapura Lake – 9.2 km (N) Nelamangala Kere – 10.2 km (NW) Heesaraghatta Tank – 10.5 km (NNW) Nagavara Kere – 11.3 km (E) Rachenahalli Kere – 12 km (E) Jukkuru Kere – 12.3 km (NE) Yelahanka Kere – 11.9 km (NE) Rivers Arkavati River – 4.8 km (WNW) Vrishbhavati River – 5.9 km (SE) 5 State, National boundaries No None within 15 km radius 6 Routes or facilities used by the Yes NH – 4 - Adjacent (S) public for access to recreation or SH 39 – 0.7 km (E) other tourist, pilgrim areas NICE Ring road – 2.5 km (W) SH – 85 – 6.5 km (S) NH 7 – 9.8 km (E) Bengaluru Palace – 11.3 km (SE) Tippu Sultan Palace – 12.6 km (SE) 7 Defence installations Yes Indian Air Force Base Yelahanka – 13.8 km (NE) Defense Avionics Research Establishment – 19.8 km (SE) 8 Densely populated or built-up Yes Nelamangala – 11 km (NW) area Bengaluru – 13.5 km (SE) 9 Areas occupied by sensitive man- Yes All facilities are available at Nelamangala – made land uses (hospitals, 11 km (NW), Bengaluru – 13.5 km (SE) schools, places of worship, community facilities) 10 Areas containing important, high No Not envisaged quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to No Not envisaged pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural No The project area falls under seismic zone II hazard which could cause the as per the Seismic Zoning Map of India (IS project to present environmental 1893-2002). There has been no record on problems (earthquakes, occurrence of floods, landslides, cloud subsidence, landslides, erosion, bursts etc. flooding or extreme or adverse climatic conditions)

18 M/s IKEA India Private Limited M/s Ramky Enviro Services Private Limited