To: Ashford Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 3rd March 2020
Subject: Highway Forward Works Programme – 2019/20 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes Local Growth Fund
Developer Funded Works – see Appendix E
PROW – see Appendix F
Bridge Works – see Appendix G
Traffic Systems – see Appendix H
Combined Member Fund – see Appendix I
Street Works – see Appendix J
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Pauline Harmer Interim Highway Manager East Kent Lisa Willoughby Ashford District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Nikola Floodgate Schemes Programme Manager
Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell Road Asset Renewal (Machine Surfacing) describes the range of responses we may use when the surface or sub-surface layers that have deteriorated to a point that they need to be replaced. The existing surface is cold milled to the required depth and a new surface / pavement layer installed.
Road Name Parish Extent of Works Current Status To be Bull Lane to Standard A28 Ashford Road Bethersden programmed in Lane 2020 To be William Harvey Hospital A2070 Kennington Kennington programmed in to M20 Junction 10 Road 2020 Quest through to To be A2070 Willesborough Willesborough Railway bridge past programmed in Road Julie Rose Stadium 2020
William Harvey Hospital Kennington To be Roundabout to A2070 Kennington programmed in Blackwall Road South Road 2020 Road Asset Preservation Schemes - Contact Officer: Jonathan Dean Micro Surfacing Micro-asphalt is applied cold, in fluid form directly onto the existing road, to seal the surface to prevent water penetration, restore texture and improve skid resistance. The material is bitumen based, when it has cured it gives texture to the new surface; this influences skid resistance and durability. Road Name Parish Extent of Works Current Status Marse Road to Programmed for BRABOURNE ROAD Wye Hampton Lane August 2020 Cobbs Hill to Programmed for LOWER LEES ROAD Chilham Sharmsford Road August 2020 APPLEDORE ROAD/BENCH HILL/WOODCHURCH Between B2067 and Programmed for ROAD Appledore School Road August 2020 KNOLL HILL (INC GRIGGORS GREEN From Boat Lane to Programmed for ROAD) Aldington Bridge over canal August 2020 VARIOUS SECTIONS Programmed for FAVERSHAM ROAD Challock From A252 to A251 August 2020 From Fishers Street Road to Shottenden Programmed for GOLD UPS LANE Chilham Road August 2020 Tudesnoad Lane to Programmed for WISSENDEN LANE Bethersden Tudesnoad Lane August 2020 HIGH HALDEN Bend adjacent to Programmed for ROAD Biddenden Wagstaff Lane August 2020 BROMLEY GREEN From Capel Road to Programmed for ROAD Ruckinge Just Past Sharp Bend August 2020 Top of Hill - Start of Programmed for RUCKINGE ROAD Ham Street Woods August 2020 Surface Dressing Surface Dressing is the application of bitumen, which is sprayed onto the road surface followed by the laying of chippings onto the bitumen. These layers seal the surface to prevent water penetration, restore texture and improve skid resistance. Road Name Parish Extent of Works Current Status Provisionally A28 ROLVENDEN Halden Road to Programmed for ROAD Rolvenden Benenden Road Summer 2020 Provisionally BETHERSDEN From Biddenden Road Programmed for ROAD Smarden to Little Langley Farm Summer 2020 Provisionally CANTERBURY Green Lane to wooded Programmed for ROAD Challock section Summer 2020 Provisionally From Halden Lane to Programmed for TENTERDEN ROAD Rolverden Mounts Lane Summer 2020 VARIOUS SECTIONS Provisionally From Bockham Lane to Programmed for HYTHE ROAD Various Ashford /FH Boundary Summer 2020 VARIOUS SECTIONS Provisionally MAIDSTONE ROAD From Sandhurst Lane Programmed for (ASHFORD ROAD) Various to Charing Roundabout Summer 2020 Provisionally Pemberton Road to Programmed for TRINITY ROAD Boughton Aluph A251 / A2042 Summer 2020 Provisionally CANTERBURY Red 30mph Pad to Programmed for ROAD Brabourne Lees Manor Pound Lane Summer 2020 Provisionally Canterbury Road to Programmed for SCOTS LANE Brabourne Lees Fiddling Lane Summer 2020 Provisionally SPARROW HATCH Railway Bridge to Programmed for LANE Smarden Dowle Street Summer 2020 Provisionally DOWLES STREET From Rushbrook to Programmed for ROAD Smarden Smarden Road Summer 2020 Provisionally Chilham to Programmed for ASHFORD ROAD Chilham Godmersham Summer 2020 Retread Re-tread is where the existing surface is recycled. Any excess material is removed or any additional material required, is imported then the material is sprayed with bitumen. It is mixed thoroughly to combine the bitumen with the stone and then shaped to the required levels To be programmed BUGGLESDEN From Readers Bridge between May – ROAD Tenterden Road to A262 July 2020 To be programmed The Grange to the between May – NORTONS LANE Tenterden junction July 2020 To be programmed From Smarden Road to between May – POOK LANE Biddenden Wagstaff Lane July 2020
Appendix B - Drainage
Drainage Works – Contact Officer: Earl Bourner
Road Name Parish Description of Works Current Status Reattended on Full cleansing and CCTV 20th December carried out to identify 2019 - No The Street, defects. Trial holes reported Warehorne Road, programmed August Hamstreet flooding since Ruckinge Road 2019 not completed due completion of and Ashford Road to residents ignoring works but will NPCs and refusing to continue to move cars monitor. Ground investigations Proposed installation of complete. Job new soakaway to resolve being raised for Shottenden Road Molash flooding issue affecting soakaway full width of carriageway installation. and adjacent property Date to be confirmed. Existing drainage system Trial holes appears to be damaged completed. by services and Topographical Victoria Crescent Ashford construction work. Trial Surveys due to holes and topographical complete before surveys proposed to end of February. inform scheme design Scheme being raised to A252 Canterbury repair defects found in With schemes Road and The Molash, Chilham, the October 2019 Engineer to Street (Challock Challock surveys. Collapsed pipe raise job - date roundabout to to be replaced and a to be confirmed. Chilham) number of minor repairs. Works Bethersden Road, Replace 35m damage Shadoxhurst completed 12th Shadoxhurst surface water pipe December 2019 Pilgrims Lane Dig out pond, reline Awaiting further Hastingleigh Hastingleigh, repair drainage system information. Under Replace gully pots with investigation. new pots with enlarged Main issue is Harville Road Wye sumps (existing drains leaves covering without sumps can block grates. Date to with leaves / debris) be confirmed Investigation of drainage Works Tally Ho Road Kingsnorth issues. A French drain completed 27th was installed to resolve. January 2020 Upgrade surface water Under Church Hill Chilham system and repair investigation parking area Opp 61 Bentley Replace damage surface Under Ashford Road water pipe investigation Brook Street JW Replace damaged culvert Under Woodchurch Moor lane under road investigation Passed to OS Vets Ashford Blocked or damaged Tenterden Southern Water Road surface water sewer for investigation
Appendix C – Street Lighting
Structural testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer: Sue Kinsella
Road Name Parish Description of Works Current Status
Stour Replacement of 3 no Works programmed for Albert Road street light completion by end March 2020 Stour Works Replacement of 1 no programmed for Arden Drive street light completion by end March 2020 Kennington Replacement of 5 no Works programmed for Ball Lane street light completion by end March 2020 Norman Replacement of 7 no Works programmed for Beaver road street light completion by end March 2020 Stour Replacement of 1 no Works programmed for Belmore Park street light completion by end March 2020 Replacement of 1 no Works programmed for Brenchley Close Stanhope street light completion by end March 2020 Replacement of 3 no Works South programmed for Bushy Royds street light Willesborough completion by end March 2020 Replacement of 3 no Works programmed for Chart Road Godinton street light completion by end March 2020 Replacement of 2 no Works programmed for Hampden road Norman street light completion by end March 2020 Replacement of 4 no Works programmed for Hythe Road North Willesborough street light completion by end March 2020 Replacement of 1 no Works programmed for Jarvis Drive Highfield street light completion by end March 2020 Replacement of 2 no Works programmed for Kennington Road North Willesborough street light completion by end March 2020 Replacement of 3 no Works programmed for Kingsnorth Road Norman street light completion by end March 2020 Highfield Replacement of 2 no Works programmed for Luckhurst road street light completion by end March 2020 Park Farm South Replacement of 2 no Works programmed for Bluebell Road street light completion by end March 2020 Kennington Replacement of 1 no Works programmed for Faversham road street light completion by end March 2020 North Willesborough Replacement of 2 no Works programmed for Lees road street light completion by end March 2020 Stour Replacement of 2 no Works programmed for Magazine Road street light completion by end March 2020 Replacement of 2 no Works programmed for Mortimer Close Norman street light completion by end March 2020 Stanhope Road Stanhope Replacement of 7 no Works street light programmed for completion by end March 2020 The Street North Willesborough Replacement of 3 no Works street light programmed for completion by end March 2020 Wall Road Stour Replacement of 2 no Works street light programmed for completion by end March 2020 Stour Replacement of 3 no Completed Albert Road street light Stour Replacement of 1 no Completed Arden Drive street light
Kennington Replacement of 5 no Completed Ball Lane street light
Norman Replacement of 7 no Works programmed for Beaver road street light completion by end June 2020 Stour Replacement of 1 no Completed Belmore Park street light
Brenchley Close Replacement of 1 no Completed Stanhope street light
South Replacement of 3 no Completed Bushy Royds Willesborough street light
Replacement of 3 no Works programmed for Chart Road Godinton street light completion by end June 2020 Replacement of 2 no Completed Hampden road Norman street light
Replacement of 4 no Works programmed for Hythe Road North Willesborough street light completion by end June 2020 Replacement of 1 no Completed Jarvis Drive Highfield street light
Replacement of 2 no Works programmed for Kennington Road North Willesborough street light completion by end June 2020 Works Replacement of 3 no programmed for Kingsnorth Road Norman street light completion by end June 2020 Highfield Replacement of 2 no Completed Luckhurst road street light
Park Farm South Replacement of 2 no Completed Bluebell Road street light
Kennington Replacement of 1 no Works programmed for Faversham road street light completion by end June 2020 North Willesborough Replacement of 2 no Completed Lees road street light
Stour Replacement of 2 no Works programmed for Magazine Road street light completion by end June 2020 Replacement of 2 no Completed Mortimer Close Norman street light
Stanhope Road Stanhope Replacement of 7 no Works street light programmed for completion by end June 2020 North Willesborough Works The Street Replacement of 3 no street light programmed for completion by end June 2020 Wall Road Stour Replacement of 2 no Completed street light
Appendix D – Transportation and Safety Schemes
Casualty Reduction Measures
The Schemes Planning & Delivery team is implementing schemes within the Ashford District, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status correct as of 16th August 2019.
Local Transport Plan funded schemes – Contact Officer: Rebecca Bailey
Road Name Description of Works Current Status
Casualty reduction measures (reactive) – Ashford Remedial works to be undertaken A274 Headcorn Improvements to existing road following the stage 3 road safety Road surface, signing and lining audit – Correct update before JTB. A20 Hythe Further analysis of collision data to Road J/W Upgrade to existing junction layout determine appropriate action - Church Road Correct update before JTB. A20 Maidstone Upgrade to existing junction layout Road J/W and speed limit reduction to Works completed Cades Road 50MPH Highway improvement scheme Magpie Hall Improvements to traffic signs and programmed. Further analysis of Road J/W road markings collision data to be carried out. - Ashford Road Correct update before JTB. A20 Maidstone Collision analysis and surveys to be Road junction Investigation of potential highway undertaken. Correct update before Station Road, improvements JTB. Charing
INTEGRATED TRANSPORT SCHEMES Local Transport Plan funded non-casualty reduction schemes
Description of Source of Road Name Current Status Works Funding Outline design complete, High Street, Junction Local Transport stage 1 road safety audit to Biddenden reconfiguration Plan be carried out Tithe Barn Lane, Provision of new Construction works Singleton & Toucan pedestrian Local Transport complete. Further remedial Great Chart crossing Plan works to be carried out to rectify defects Installation of A28 Rolvenden Local Transport pedestrian refuge Outline design Lane, Tenterden Plan island A28 Ashford Installation of Local Transport Road, St signalised Outline design Plan Michaels pedestrian crossing
Safer Roads Fund – Contact Officer: Jamie Watson Description of Source of Road Name Current Status Works Funding Safety We are currently finalising A252 between improvements the scheme design and Chilham (A28) Charing, Challock, along A252 arranging road safety audits and Charing Molash, Chilham between the to be carried out. (A20) villages of Chilham and Charing
Appendix E – Developer Funded Works
Developer Funded Works (Section 278 Agreement Works) – Contact Officer: Jamie Hare Mastergov Description of Scheme Name File Ref Parish Current Status Works No
Works complete and Calleywell New access for in maintenance AS003039 Aldington Lane development period; remedials required
Works complete and Roman Road AS003153 Aldington New vehicle access in maintenance period
Ragstone AS003177 Aldington Parking bays Adopted 10/01/2020 Hollow
New controlled Newtown pedestrian crossing Road, former AS000419 Newtown Adopted 06/02/2020 and construction of railway site site entrance New access to Ashdown Court AS003038 Ashford development and Adopted 16/10/2020 footway works Amendments to Works complete and Dover Place AS003051 Ashford junction and works in maintenance to the footway period Technical audit Road N6 tie-in with stage - layout Repton Park AS003074 Ashford Ordinance Way agreed, waiting for lighting
Vehicular access for Adopted February Elwick Road AS003076 Ashford hotel 2020
Carlton Road AS003084 Ashford New junction Adopted 15/01/2020
Works complete, in New junction at Henwood AS003090 Ashford maintenance period Flipout remedials required
B2042 Ashford New slip road to car Designer AS003092 Ashford Adopted 04/09/19 park Outlet
Kimberley Way Roundabout, Amendments to the Works complete and Ashford AS003093 Ashford existing roundabout in maintenance Designer to increase capacity period Outlet
Newtown Works complete and Road, AS003143 Ashford New traffic signals in maintenance Designer period Outlet
Works complete and Boxley AS003145 Ashford New vehicle access in maintenance period
Agreement signed, New footway and a Charter House AS003151 Ashford works not yet layby commenced on site
Works complete and New junction and Austin Road AS003157 Ashford in maintenance vehicle cross-overs period
Aldi, Victoria AS003161 Ashford New junction Adopted 05/09/19 Road
Curious Works complete, Brewery Site, AS003164 Ashford New junction snagging works Victoria Road required
Works complete and Victoria New vehicle access AS003165 Ashford in maintenance Crescent and footway works period
New vehicle access Works under Leacon Road AS003166 Ashford and bus stops construction
2 new junctions and Works under Jemmett Road AS003179 Ashford footway construction
2 new accesses and Works under Victoria Road AS003180 Ashford footway works in construction George Street
Works complete. Access to new car In maintenance Victoria Road AS003235 Ashford park period
Design approved; Hinxhill Park, New signalised waiting for AS003238 Ashford Hythe Road junction Agreement to be signed
Spindlewood to Works complete. Short length of link Repton Park AS003281 Ashford In maintenance Road period
Footway and Prince Albert In technical audit AS003379 Ashford carriageway works redevelopment stage and new loading bay
Two new entrances Works under Church Hill AS003397 Bethersden to new development construction
A274 North Works under AS003103 Biddenden New junction Street construction
Faversham AS003140 Challock New junction Adopted 14/10/19 Road
Tile Lodge Residential parking Works complete; in AS003086 Charing Road area maintenance period
Works complete; Culvert beneath Tile Lodge maintenance AS003091 Charing road for conveyor Culvert agreement being belt prepared
Maidstone New access to Agreement signed, AS003168 Charing Road housing estate works to start shortly
A20 widening and In technical audit Swan Hotel AS003395 Charing new access stage
Bagham Place Works complete in Ashford Road AS003049 Chilham access and maintenance period pedestrian crossing remedials required
Bowerland In technical audit AS003430 Chilham Resurfacing Lane stage
New access to Willesborough Works under AS003149 Conningbrook Conningbrook Road construction Development
A28 Chart Works complete, Road, Rearrange junction AS002081 Godinton snagging works Brunswick alignment required Road
Access B to new Chilmington AS003054 Great Chart housing Adopted 12/11/19 Green development
Chilmington Access A – AS003069 Great Chart Roundabout Adopted 14/11/19 A28
New mini Chilmington roundabout and Access D – AS003097 Great Chart Adopted 11/11/19 amendments to the Coulter Road existing highway
Mock Lane and Laybys for gas In technical audit AS003169 Great Chart Coulter Road delivery stage
Chilmington Passing bays and In technical audit Brockmans AS003424 Great Chart accesses stage Lane
Bellmouth and zebra In technical audit Ransley Oast AS003423 High Halden crossing stage
Works complete and Re-surfacing to in maintenance Watery Lane AS003150 Hothfield Tarmac plant access period, remedials road required
Works complete, Kings Head AS003399 Hothfield Footway snagging works required
In technical audit Houchin Field AS003070 Kennington Access stage
Sports Ground AS003056 Mersham Access Works complete
Agreement signed, Rutledge Temporary vehicle AS003325 Park Farm works commenced Avenue access on site
Brockmans In technical audit AS003383 Park Farm New vehicle access Lane stage
Works complete and Lambden Oaks AS003107 Pluckley New vehicle access in maintenance period
In technical audit Station Road AS003160 Pluckley Road widening stage
A2070/Finberry Junction Agreement being AS003154 Sevington Park junction improvement prepared
New access to Works complete, Woodchurch AS003171 Shadoxhurst houses behind the snagging works Road Kings Head required
Agreement signed, Woodchurch New bellmouth and AS003355 Shadoxhurst waiting for Road footway crossing construction to start
2 new accesses and Works under The Street AS003219 Smarden drainage construction
Calland AS003146 Smeeth Vehicle crossover Agreement signed
Small Hythe Road, Tenterden Site Tenterden. New Works under #1 AS002080 Tenterden housing construction SAS development
New vehicle Works complete and Danemore AS003152 Tenterden crossover and in maintenance Road turning head period
In technical audit Tilden Gill AS003215 Tenterden Junction realignment stage
Technically
Tilden Gill approved; AS003230 Tenterden New roundabout Roundabout Agreement being
prepared
Replace roundabout In technical audit Church View AS003299 Tenterden with turning head stage
Works complete; Two new vehicle Church Lane AS003173 Warehorne snagging works accesses required
Works completed Cudworth New access to and in maintenance AS003024 Willesborough Road development period, Remedials required
Essella Road AS003067 Willesborough New junction Adopted 07/10/19
Blackwall Road Proposed widening AS003080 Willesborough Adopted South of carriageway
Monument New vehicle access Works complete, AS003113 Way Willesborough to Mercedes garage remedials required
Technically approved; Abbey Way AS003415 Willesborough Carriageway ramp Agreement being prepared
Access to private Works complete in Jubilee Field AS003147 Wittersham road maintenance period
Brattle AS003155 Woodchurch New parking bays Adopted
Works complete in Amendments to Court Farm AS003058 Wye maintenance period; vehicle access remedials required
Works completed; Olantigh Road AS003126 Wye School crossing snagging works required
Appendix F – Public Rights of Way
Public Rights of Way – Contact Officer: David Fleck
Path No Parish Description of Works Current Status AE643 Ruckinge Path collapsing on Canal bank Delays due to concerns by Heritage England AB24 Tenterden Resurfacing Tarmac path Complete behind day centre (Church path) AE18 Chilham Restricted Byway part of Wye Due to start Feb to Canterbury cycle network. 2020 Repairs to stone surface AT212 Woodchurc S106 works Works due March h 2020 AU12 Ashford S106 works Works due March 2020 AU23 Ashford S106 works Works due March 2020 AW237/ Shadoxhurs S106 works Works due March AW328 t 2020 AE567 Ham Street S106 works September 2020
Appendix G – Bridge Works
Bridge Works – Contact Officer: Earl Bourner
Path No Parish Description of Works Current Status Mersham Forstal bridge is prioritised for reconstruction and capital funding was set aside for design in 19/20. Although funding for the construction works is not yet confirmed KCC Highways currently anticipates allocating capital funds in 20/21. The design commission about get underway and is likely to be completed in early summer 2020. Subject to funding, construction could then be programmed for 20/21 although environmental constraints from the Environment Agency controlled Main River could dictate works being delayed into 21/22.
Flood Street Mersham The current condition and management of the bridge has been reviewed this summer. This review concluded that following further deterioration there were now unacceptable risks associated with accidental vehicle loading of the footway which led to the introduction of the temporary barriers as an interim measure until such time as the bridge is reconstructed. KCC is continuing to monitor the condition of the bridge on a 3-monthly frequency but do not currently envisage the need for any further measures in the period before the reconstruction works are completed.
Appendix H – Traffic Systems
There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.
Traffic Systems - Contact Officer: Toby Butler
Location Description of Works Current Status A292 Mace Lane near Henwood Renewal of traffic signal Proposed January Roundabout controlled crossing 2021
Appendix I - Combined Member Grant programme update
Member Highway Fund programme update for the Ashford District. The following schemes are those which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are in design at consultation stage Handed over for delivery Recently completed on site.
The list is up to date as of 17th February 2020.
The details given below are for highway projects only. This report does not detail Contributions Members have made to other groups such as parish councils Highway studies Traffic/ non-motorised user surveys funded by Members.
More information on the schemes listed below can be found via Kent Gateway, the online database for all Combined Member Grant schemes and studies, or by contacting the Traffic and Safety Engineer for the Combined Member Grant Ashford District.
Charlie Simkins Details of Scheme Status Charing Heath speed limit reduction Handed over to contractor for delivery
Mike Hill Details of Scheme Status High Halden Road Biddenden – Road markings and Works completed road sign improvement to reduce speed
Paul Bartlett Details of Scheme Status Nine Acres Ashford – New traffic calming feature Works programmed for 20th February 2020 Bybrook Road Ashford – 20mph Scheme Outline Design
Appendix J – Street Works
Please note that this list is accurate at the time of running the report and is subject to cancellations and additions.
Report highlighting all works in Ashford District that require road closures with a duration of 10+ days
For information on all In-progress and proposed works please visit: https://one.network/
Street Works – Contact Officer Alison Hews
Road Location Works Works Dates Dates to Traffic Description Promoter from management comments Hythe Road Willesborough Gas Mains Southern 6/4/2020 2/07/2020 Road closure replacement Gas – in sections works Networks as works progress Naccolt Naccolt, Wye Lay 130 South East 2/3/20 8/5/20 Road Closure Road metres of Water new drinking water main, associated services and connect to existing main Millbank Kingsnorth Installation Southern 13/7/20 2/10/20 Road Closure Road of a new Water Part of sewer main Section O/S Chilmington and school to be Green associated completed Scheme works during including Summer manholes, Holiday chambers, pipe works, connections. Britannia Kingsnorth Installation Southern 22/6/20 24/7/20 Road Lane of a new Water Closures Part of sewer main Chilmington and Green associated Scheme works including manholes, chambers, pipe works, connections. Chart Road Kingsnorth Installation Southern 1/6/20 3/7/20 Rolling Road of a new water closures Part of sewer main Chilmington and Green associated Scheme works including manholes, chambers, pipe works, connections.
High High Halden BT Spine Openreach 16/3/20 3/4/20 Road Halden Cabling Closures Road works
1.1 Legal Implications
1.1.1 Not applicable.
1.2 Financial and Value for Money Considerations
1.2.1 Not applicable.
1.3 Risk Assessment
1.3.1 Not applicable.
Contacts: Toby Howe / Lisa Willoughby 03000 418181