<<

Prepared in cooperation with the WATER OFFICE Channel Stability of the Neosho Downstream From John Redmond Dam, Kansas —Kyle E. Juracek The stability of the Neosho River is not sufficient to conclude that John of property, general aesthetics, and channel downstream from John Redmond Dam has caused the Neosho recreation. The knowledge provided by Redmond Dam, in southeast Kansas, River channel to change more than it this study will provide some of the was investigated using multi-date otherwise would have changed without information needed to best manage the aerial photographs and stream-gage the dam. Neosho River system. information. Bankfull channel width To determine the effect of John was used as the primary indicator Redmond Dam, a study of the Neosho Description of Study Area variable to assess pre- and post-dam River that compares the channel before, channel change. Five 6-mile river during, and after completion of the dam The focus of this study was the reaches and four stream gages were was undertaken by the USGS in coop­ middle 180-mile reach of the Neosho used in the analysis. Results indicated eration with the Kansas Water Office. River between John Redmond Dam and that the overall channel response to the The objective of this study was to the Kansas- State line altered streamflow regime and sediment determine whether or not the Neosho (fig. 1). Throughout this reach the load introduced by the dam has been River channel has widened in response Neosho River is characterized by a minor. Aside from some localized to the changes in flow regime and meandering, gravel-bed channel. The channel widening, there was little post- sediment load introduced by the dam. channel slope averages about 1.2 feet dam change in bankfull channel width. Pre- and post-dam channel stability was per mile. Riverbank height varies from The lack of a pronounced post-dam assessed using multi-date aerial about 15 to 30 feet. The channel bed channel response may be attributable photographs and streamgage infor­ frequently is situated on bedrock. to a substantial reduction in the mation. Alluvium in the Neosho River Valley magnitude of the post-dam annual peak Important issues related to the averages about 25 feet in thickness and flows in combination with the stability of the Neosho River channel is typified by silt with a basal layer of resistance to erosion of the bed and include protection of riparian resources, sand and gravel that averages about bank materials. Also, the channel may protection of habitat for threatened and 3 feet in thickness. The channel-bank have been overwidened by a series of endangered species (for example, the materials consist mostly of cohesive silt large floods that predated construction , Noturus placidus), and clay and are relatively resistant to of the dam. and bank stabilization as related to loss erosion compared to sand banks. Also, Introduction

The construction and operation of a reservoir can have a substantial effect on the stability of the river channel downstream from the dam. Since its completion in 1964, the downstream effect of John Redmond Dam on the Neosho River in southeast Kansas (fig. 1) has been much debated. Previous studies by the U.S. Army Corps of Engineers (COE) (1972) and the U.S. Geological Survey (USGS) (Studley, 1996) have indicated the possibility of channel widening. Also, anecdotal evidence of perceived channel widening has been provided by residents living along the Neosho River as far as 165 mi downstream from the dam. The available evidence, however, John Redmond Dam on the Neosho River near Burlington, southeast Kansas. U.S. Department of the Interior USGS Fact Sheet FS–088-–99 U.S. Geological Survey April 1999 John Redmond EXPLANATION Reservoir 1 John Redmond 4 Current U.S. Geological Survey Dam streamflow-gaging station—Number 95°30' Burlington 2 is map number used in table 1 Le Roy N Iola reach 1 eo Discontinued U.S. Geological Survey sh 38° o streamflow-gaging station—Number is map number used in table 1 3 Iola Le Roy reach Humboldt reach Overflow dam Humboldt

95° Boundary of Chanute Neosho River Basin R iv er Erie

Neosho Erie reach River Study KANSAS area 4 Ar ka Parsons n Neosho River s a Basin s KANSAS Oswego reach MISSOURI Oswego OKLAHOMA River Chetopa KANSAS 37° Base from U.S. Geological Survey digital data, 1:100,000, 1995 OKLAHOMA Universal Transverse Mercator projection 0 10 20 30 MILES Zone 14 & 13 Converted to Lambert Conformal Conic projection, 0 10 20 30 KILOMETERS Index map Standard parallels 33° and 45°, central meridian -98°15'

Figure 1. Location of Neosho River Basin, study area, river reaches, and streamflow-gaging stations. the channel banks are typically covered used as the primary indicator variable indicators used in the delineation of the by partial to complete mature tree cover to assess channel change after the com­ bankfull channel included breaks in which may enhance bank stability at pletion of the dam. slope, the tops of point bars, and some locations. Five 6-mile river reaches were changes in vegetation. The channel Several tributaries contribute unreg­ selected for use in this study (fig. 1) centerline was added, and all ulated flow to the Neosho River down- with the objective being to obtain a information was digitized. Mean stream from John Redmond Dam. Also spatially representative sample while bankfull channel width then was noteworthy are 12 overflow dams avoiding, to the extent possible, estimated for all reaches and dates as (fig. 1) that were constructed within the localized human-caused or natural channel area divided by channel main-stem channel mostly in the 1930's conditions that might obscure channel centerline length. or 1950's. Changes in the streamflow adjustment. Human-caused conditions To compare pre- and post-dam regime attributable to the operation of include overflow dams (fig. 1), bridges, channel stability, the mean bankfull John Redmond Dam have included a and channel modifications (for channel widths for all reaches and dates decrease in the magnitudes of peak dis­ example, riprap). Natural conditions were tabulated, and pre- and post-dam charges (flows) and an increase in the include split-channel locations and hard differences were evaluated. For each magnitudes of low discharges (fig. 2) points (that is, locations where the reach, pre-dam change was computed (Studley, 1996). Post-dam suspended- channel is situated along the valley as the percentage difference in mean sediment concentrations are substant­ wall). Additional factors considered in bankfull channel width between the ially reduced immediately downstream the selection of the reaches included pre-dam and construction time periods. from the dam. proximity to John Redmond Dam and Similarly, post-dam change was the availability and usability of aerial computed for each reach as the Methods photographs. percentage difference in mean bankfull For each reach, aerial photographs channel width between the construction A stable river channel naturally were obtained for three time peri­ and post-dam time periods. The magni­ meanders across its river valley over ods—pre-dam (late 1930's), construct- tude and direction of the changes were time while maintaining approximately ion (early 1960's), and post-dam (early used to assess pre- and post-dam the same cross-sectional shape. There- 1990's). The bankfull channel area was channel stability for the individual fore, changes in channel geometry may interpreted from the aerial photographs reaches as well as the entire system. be used to infer channel instability. In for each time period and traced on a Due to various potential sources of this study, bankfull channel width was scale-stable mylar overlay. Primary error in the use of aerial photographs to measure bankfull channel widths, only a change in bankfull width of 10 per- Downstream Effects of Dams result in channel narrowing as vegetation cent or more was considered signifi­ on River Channels encroaches. An exception is the case where the channel bed is armored or cant. situated on bedrock. Unable to effect­ Information from USGS Primary changes introduced by a ively scour the resistent channel bed, the streamflow-gaging stations (fig. 1, table dam include a reduction in the river's river may instead erode laterally and thus 1) was also analyzed to assess pre- and sediment load as well as an alteration of widen its channel. Typically, channel post-dam channel stability downstream the flow regime. Typical changes in the degradation initiates near the dam flow regime include a reduction in the from the dam. A comparison of pre- following closure and eventually may magnitude of peak flows and a possible migrate a considerable distance and post-dam conditions included an increase in the magnitude of low flows. downstream (Williams and Wolman, assessment of stage-discharge, dis­ Such artificially introduced changes 1984). charge-width, discharge-area, and may trigger an adjustment by the river The type, rate, duration, and discharge-velocity relations. The as it attempts to re-establish an approxi­ downstream extent of channel degrad­ Parsons gaging station was excluded mate equilibrium between the channel ation downstream from dams are and the discharge and sediment load controlled by a number of factors, from all analyses due to back-water being transported. including discharge, sediment load, bed effects from an overflow dam located In general, downstream from and bank material composition, local 2.7 miles downstream from the gage dams initially adjust by channel bed-elevation control (for example, (fig. 1, map number 4). The gaging degradation. Typically, a river will bedrock, armoring), channel geometry, stations provide site-specific inform­ scour, and thus lower, its channel bed as climate, tributary inflow, and vegetation. the sediment-depleted water emerging Considerable variation in the type and ation at locations separate from the from the dam attempts to replenish its rate of channel degradation may occur river reaches analyzed in this study. sediment load. Concurrently, the even between sites located close together reduced magnitude of peak flows due to the variability of the controlling Results and Discussion emerging from the dam eventually may factors.

The aerial-photograph analyses 500,000 indicate that the construction and Neosho River at Strawn, KS operation of John Redmond Dam has (map number 1) 400,000 not resulted in a substantial and Neosho River at Burling­ pervasive downstream widening of the 300,000 ton, KS (map number 2) Neosho River channel. The mean bankfull channel widths (table 2) show 200,000 that, with the exception of the Iola Dam closure reach (10-percent increase in width), 100,000 post-dam changes have been minor (and may be attributable in part to 0 measurement error). In comparison, 500,000 Neosho River near Iola, KS relatively large pre-dam channel-width (map number 3) changes had occurred at the Le Roy, 400,000 Humboldt, and Oswego reaches with 300,000 respective increases of 15, 14, and 10 percent. The fact that three of the 200,000 four largest increases in mean bankfull Dam closure channel width predate the dam may be 100,000 indicative of a predam period of channel widening possibly associated 0 with one or more large floods. 500,000 In many river systems 90 to 99 per- Neosho River near Parsons, KS (map number 4) cent of significant bank erosion occurs Annual peak discharge, in cubic feet per second 400,000 during large floods. A large flood occurred in July 1951 when the Neosho 300,000 River had a flow with an estimated 500-year recurrence interval. The peak 200,000 Dam closure discharge during this flood at Strawn (fig. 1) was 400,000 cubic feet per 100,000 second (The mean annual peak 0 discharge for the period of record at 1930 2000 1940 1950 1980 1990 1890 1900 1910 1920 1970 1960 Strawn is about 43,000 cubic feet per 1880 second). Interestingly, the three reaches Water year that had the largest pre-dam increases Figure 2. Annual peak discharges for U.S. Geological Survey streamflow-gaging stations in bankfull channel width also had the downstream from John Redmond Dam. Location of stations shown in figure 1. smallest post-dam changes in bankfull Table 1. U.S. Geological Survey (USGS) streamflow-gaging stations used in this study within the confines of the original channel. Eventually, this may result in a Distance downstream Drainage Period of narrowing of the channel. Map USGS from John area continuous The findings of this study suggest number station Redmond (square record (fig. 1) number USGS station name Dam (miles) miles) (water year) two possibilities. First, the Neosho 1 07182400 Neosho River at Strawn, KS -- 3,015� 1949–63 River is a relatively stable system that 2 07182510� Neosho River at Burlington, KS 5.3� 3,042� 1963–present may only change significantly in 3 07183000� Neosho River near Iola, KS 56.3� 3,818� 1918–present response to extreme events. Second, it 4 07183500 Neosho River near Parsons, KS 139.6 4,905 1922–present may be that insufficient time has transpired for pronounced channel changes to become manifest. Local Table 2. River-reach locations and mean bankfull channel widths residents' perception of channel Distance Mean bankfull channel width (feet) widening may be correct at specific River downstream (percent change from previous time period) reach from dam locations. However, also likely are (fig. 1) (miles) Pre-dam Construction Post-dam instances where normal channel Le Roy 23–29 197� 226 (+15) 233 (+3) migration has been mistaken for Iola 42–49 240� 236 (-2) 259 (+10) channel widening, especially where Humboldt 63–69 243� 276 (+14) 266 (-4) property (for example, cropland and Erie 102–108 246� 253 (+3) 269 (+6) structures) has been lost or is Oswego 146–152 233 256 (+10) 256 (0) threatened. Acknowledgments channel width. This may be due to the U.S. Army Corps of Engineers, written overwidened condition of the channel commun., 1995). Localized widening This study was made possible in part at these locations in response to the may or may not be directly related to by funding from the Kansas State Water 1951 and other pre-dam floods. the operation of John Redmond Dam. Plan Fund. The author also gratefully The gaging-station analyses The overall lack of a pronounced acknowledges the aerial photographs provided some indication of channel post-dam channel response may be provided by the U.S. Department of widening at Burlington in the years attributable to several factors. First, Agriculture's Farm Service Agency, and immediately following completion of there has been a substantial post-dam the Geology Department and the John Redmond Dam in 1964. Results reduction in the magnitude of the Kansas Applied Remote Sensing indicated an initial increase in channel annual peak discharges. A second Program, University of Kansas. width of about 10 to 20 feet, followed factor is the strength of the bed and by apparent stabilization at this bank materials. Degradation of the location. At Iola, channel width has not channel bed has been limited due to the References changed. However, an increase in flow presence of bedrock and (or) coarse Studley, S.E., 1996, Changes in high-flow velocity was indicated. The increase in gravel, the latter of which would frequency and channel geometry of the velocity may be due to an increase in require large flows to transport. The Neosho River downstream from John channel slope and (or) a decrease in channel banks consist mostly of Redmond Dam, Southeastern Kansas: channel roughness. cohesive silt and clay and are relatively U.S. Geological Survey Water-Resources Investigations Report 96–4243, 16 p. Together, the aerial-photograph and resistant to erosion. Moreover, bank Williams, G.P., and Wolman, M.G., 1984, gaging-station analyses indicate that the stability may be enhanced at some Downstream effects of dams on alluvial overall downstream response of the locations by partial to complete mature rivers: U.S. Geological Survey Pro­ fessional Paper 1286, 83 p. Neosho River channel to John tree cover. Therefore, significant bank U.S. Army Corps of Engineers, 1972, Redmond Dam has been minor. With erosion (beyond site-specific occur­ Memorandum of findings, riverbank one exception, the five river reaches rences) may only occur during large stabilization study, Grand (Neosho) indicated little if any post-dam change flows which have mostly been River, Kansas & Oklahoma, John Redmond Dam & Reservoir to Kansas- in channel width. However, the appar­ eliminated by the dam. Oklahoma State line: U.S. Army Corps ent initial widening of the channel at A third factor is the pre-dam of Engineers, September 1972, Tulsa, the Burlington gage shows that local­ condition of the channel. As indicated Oklahoma, 24 p. ized widening has occurred. Such by the five river reaches, there is some localized widening is also evident in a indication of a pre-dam widening of the series of six COE cross sections located channel, possibly due in part to the For more information contact: successively at intervals of about 1 mile 1951 flood. Thus, it is possible that the immediately downstream from the channel, at least in places, may have District Chief dam. The cross sections, surveyed in been in an overwidened condition at the U.S. Geological Survey 1963, 1974, and 1983, indicate minor time of dam construction. Thus, 4821 Quail Crest Place widening at one site (10 to 20 feet), additional widening at such locations Lawrence, Kansas 66049–3839 moderate widening at one site (30 to may be unlikely. In fact, there is some (785) 842–9909 40 feet), and little if any change at the field evidence to indicate that a new email: [email protected] remaining four sites (Harry Hartwell, lower flood plain may be forming