Developing offshore grids : An integrated approach
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
Andrew Hiorns
Integrated offshore networks: the context of our work
Sustainability We are interested in establishing workable arrangements at the lowest costs for UK consumers such that: The potential deliverability of offshore wind is maximised Security of supply and network resilience are maximised The overall cost to consumers is minimised Affordability
The scale of potential offshore a Offshore wind leased wind necessitates reflection on capacity* the delivery challenges: 1GW Security of supply 7GW European interconnection Technology development Security of 32GW supply Supply chain capability Planning consents
Financing Round 1 Round 2 Round 3 Skills
* Source: DECC website 2 http://www.decc.gov.uk/en/content/cms/what_we_do/uk_supply/energy_mix/renewable/policy/offshore/wind_leasing/wind_leasing.aspx
1 Assumptions: Generation mix scenarios
2008/09 TRANSMISSION SYSTEM AS AT 31st DECEMBER 2007
400kV Substations 275kV Substations Slow Progression 132kV Substations 400kV Circuits 275kV Circuits 132kV Circuits
Major Generating Sites Including Pumped Storage Pentland Firth Connected at 400kV THE SHETLAND ISLANDS 6 Connected at 275kV 9,724MW offshore wind in 2020 Hydro Generation 23,174MW offshore wind in 2030 1 21% renewable electricity generation 2020 target missed 5 7
8 9 2 10 Gone Green 4
3 16,374MW offshore wind in 2020 3 Tongland
2 2 14 26,354MW offshore wind in 2030 1
3 4 1 32% renewable electricity generation 4 2 3 17
16 2020 target hit 15 9 4 5 7 6 14 11
13 13 12 12 10
11 Accelerated growth 5
9
10 7 8 32,239MW offshore wind in 2020 6 9 5
51,552MW offshore wind in 2030 8 43% renewable electricity generation 6 2020 target exceeded 7
3
Technology Assumptions:
New technology is needed under both a radial & integrated solution
HVDC cables AC cables
Technology is still developing Appropriate only over shorter distances 2-3 year development lead times for the Capacitive effects increase exponentially larger cables over distance Cables where lead times exceed 2-3 Reactive compensation required, but years not used in our study before 2020 ineffective over distance, reducing real power capacity Platform design Smart grids Currently bespoke by project / application Scope for standardisation under an Could be developed as part of an integrated solution integrated solution
We have not assumed radical technology solutions pre 2020
4
2 Interaction with onshore
TRANSMISSION SYSTEM REINFORCEMENTS Power transfers
Dounreay Thurso REINFORCED NETWORK Mybster
Stornoway Cassley Dunbeath 400kV Substations Lairg 275kV Substations THE SHETLAND ISLANDS Brora 400kV CIRCUITS North-South will increase Shin 275kV CIRCUITS
Grudie Mossford Major Generating Sites Including Pumped Storage Bridge Alness Conon Orrin Elgin Fraserburgh Luichart Ardmore Macduff St. Fergus Connected at 400kV Deanie Dingwall Cu llig ran Keith Strichen Connected at 275kV Aigas Inverness Nairn How might these be managed? Bla ckh illock Dunvegan Kilmorack Peterhead Hydro Generation Beauly Fasnakyle Dyce
Glen Kintore Persley Broadford Morrison Woodhill Willowdale Foyers Ceannacroc Boat of Fort Augustus Garten Clayhills Under Construction or ready to start Tarland Craigiebuckler Redmoss Invergarry Construction subject to consents Quoich
Fiddes
Fort William Errochty Errochty Power Station Rannoch Clunie Bridge of Dun Very strong need case Tummel Lunanhead Bridge Tealing Cashlie Dudhope Arbroath Lochay Lyndhurst Milton of Craigie Radial solutions Taynuilt K illin Finlarig Charleston Cruachan Da lm ally Burghmuir Dudhope Glenagnes Strong need case St. Fillans Nant Clachan SCOTTISH HYDRO-ELECTRIC Cup ar TRANSMISSION Inveraray Glenrothes Sloy Leven Devonside Westfield Red house W h is tl ef ie ld Stirling K inca rdine Glenniston Port Mossmorran Future requirement, but no strong Dunfe rmline Ann Lon gann et B onnybridge I verkeithing Dunoon Helensbu rgh Grang emou th Shrubh ill Cockenzie need case to commence Dun bar Sp ango Devol Strathleven Telford Rd. Portobello Valley M oor Broxburn Gorgie Torness Erskine Cu mbe rn auld Bathg ate Wh ite hou se Inverkip La mbh ill at present Ea ste rho use Radial connections to the nearest landing point L ivingsto n Kaimes Cu rrie Newarthill Clydes Neilston Mill Hun tersto n Berwick Fa rm Wishaw Hunterston Busby Strathave n Blacklaw Kilwinning Whitelee East Series Capacitors K ilmarnock Kilbride Saltcoats To wn South Linm ill Eccles Carradale Me ado whea d G a la sh ie ls Kilmarnock Coalburn South Ayr SP TRANSMISSION LTD. and then additional onshore reinforcements to Coylton Elvanfoot Ha wick
Ma ybole
NGC
Gretna Blyth Du mfries Ecclefecha n provide additional capacity (minimum offshore Auchencrosh Fourstones New ton T ynemouth Stewart Harker South Shields Chapelcross S te lla West West Boldon Glenluce Tongland Offerton Hawthorne Pit Hart Moor B6 Spennymoor Hartlepool costs v’s maximum onshore costs) Saltholme Tod Point Grangetown Norton Greystones
Lackenby
Hutton Radial connections extended significantly to
Heysham Quernmore Poppleton Osbaldwick
Thornton Bradford West Kirkstall Stanah Skelton Creyke Beck Padiham Grange Monk Fryston Saltend North avoid onshore reinforcement (maximum Saltend South Penwortham Elland Drax Killingholme Eggborough Humber Refinery B7 Roch dal e Ferrybridge Keadby Washway South Templeborough Thorpe Humber Farm Kearsley Whitegate West Kirkby Marsh Bank Grimsby South Melton Lister Stalybridge West Wylfa Manchester Pitsmoor Drive Ra in hill Stocksbridge Aldwarke West Carrington Bredbury Winco Bank Burton Birkenhead Thurcroft offsh ore cost s v’ s mi n imum ons hore cos ts ) Neepsend Fiddlers Daines Sheffield City Ferry Brinsworth Cottam Capenhurst Frodsham Jordanthorpe Norton Lees Pentir Macclesfield Chesterfield Deeside High Dinorwig Marnham
Staythorpe Legacy Ffestiniog Cellarhead Bicker Fenn Willington Optimum balance sought between radial Trawsfynydd Ratcliffe
Drakelow Walpole Rugeley Spalding North Norwich Ironbridge Bushbury Main Willenhall Bustleholm B8 Sh re wsbu ry Enderby Penn Hams Nechells Hall offshore costs vs onshore costs (ODIS) Ocker Hill Coventry O ldbury Kitwell Berkswell
Sizewell Burwell Feckenham Main Bishops Grendon Eaton Wood Socon
Patford Bramford Bridge East Sundon Claydon Pelham Wymondley Leighton Braintree Buzzard Rassau Walham Rye House Waltham Imperial Brimsdown Cross Park Swansea Cowley Pembroke Watford Elstree Hackney North Amersham Main Rayleigh Main Baglan Cilfynydd Whitson Culham Mill Hill Tottenham Redbridge Warley B9 Minety Didcot Bay Upper Boat Uskmouth Iron Acton Willesden West Thurrock Margam Barking Coryton Alpha Steel Iver Ealing Northfleet East Pyle N.Hyde Singlewell Seabank City Rd W.Ham Tilbury Grain Cowbridge St Johns Tremorfa Laleham Wood New Hurst Cross Kingsnorth Integrated solution Aberthaw Cardiff East West Kemsley Melksham Bramley Weybridge Chessington Rowdown Littlebrook Beddington Fleet Canterbury Wimbledon North
Hinkle y Po in t Sellindge Bridgwater
Alverdiscott Bolney Nursling Taunton Ninfield E de F Dungeness Marchwood Lovedean Axminster Mannington Fawley Botley Wood Exeter Designs fully integrated to minimise total cost
Chickerell
Langage Abham Landulph Indian Queens ISSUE B 12-02-09 41/177619 C Collins Bartholomew Ltd 1999 and impact on environment 5
Increased supply security by integration
Assuming transmission circuit availability of 95% Annual load factor of offshore wind generation ~40% Radial C1Case 1 -RdilRadial connec tion = 5% x 40% = 2% of installed capacity Total wind generation curtailment = 2% Case 2 – Integrated, sufficient transmission capacity to accommodate 100% wind generation output Intact offshore network, Wind generation output curtailment = 0% Outage of transmission network, Wind generation output curtailment Integrated = 5% x 5% x 40% = 0.1% of installed capacity Total wind generation curtailment = 0.1% Case 3 – Integrated, sufficient transmission capacity to accommodate 90% wind generation output, Intact curtailment = 2.3% Outage curtailment = 5% x 5% x 40% = 0.1% of installed capacity Total wind generation curtailment = 2.4% 6
3 Radial and Integrated UK Offshore
Radial solution Integrated solution
7
Design Options Radial
1GW cable to shore 1GW cables to shore 1GW cables to shore 1GW cables to shore
Clustered
2GW cable to shore 2GW cable to shore 2GW cables to shore 2GW cab l es to sh or e
Integrated
2GW cable to shore 2GW cables to shore 2GW cables to shore 2GW cables to shore 8
4 Interaction with interconnectors 1
Case 1 – Radial wind with 100% connection transmission capacity
Offshore Wind Output 110
100 CT • Very little restriction of wind output 90 CWF 80 • Transmission utilisation 35-45% 70 Un-utilised transmission
60
50 Output %
40
30
20 CT 10
0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 CWF =CT Time (hours)
Case 2 – Wind and interconnection at 100% transmission capacity
Offshore Wind Output 110 100 • Potentially either heavily curtailment of wind 90 CT CWF 80 generation output or interconnector trading
70 60 • Potentially 100% transmission utilisation Interconnection 50 Output % 40 • Limitations on ability to use interconnectors 30
20 exist nearly all times 10 CT CI 0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 Time (hours) CT -CI CWF =CT = CI
Period when there are potential conflicts 9
Interaction with interconnectors 2
Case 3 – Wind and 10% interconnection
Offshore Wind Output 110 • Very limited curtailment of wind generation 100 C Interconnection T 90 CWF CT -CI output or interconnector curtailment 80 70 • Increased utilisation of transmission 60
50 Output % Output • Ability to utilise interconnectors for most 40 30 periods (only limited with high output across 20 all offshore wind parks 10 CT CI 0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 Time (hours) CWF =CT + CI ; CT >> CI Period when there are potential conflicts
Case 4 –Wind with 90% transmission connection capacity and 10% interconnection
Offshore Wind Output 110
100 CWF 90 CT • Limited curtailment of wind generation output 80 CT -CI or interconnector curtailment 70 60 • Increased utilisation of transmission 50 Output % Output
40
30 • Ability to utilise interconnectors for most
20 periods (only limited with high output across CT CI 10
0 all offshore wind parks 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 C >C + C ; C >> C Time (hours) WF T I T I Wind curtailment
Period when there are potential conflicts 10
5 Extending into European waters ?
Potential 50GW plus by 2030
11
Integrated North Sea Grid ?
Norway Line
Scotland Shore
GW) 9 GW
(5 land
t Norway Offshore Sco wind
Line Dogger Bank
13 GW Be ‐ GW)
Shore
2
Hornsea No
(28 or
4 GW 3 Germany
Norfolk NorNed England Offshore Wind 7 GW NorNed
ity) BritNed c NthlNetherlan ds Nemo Offshore wind Capa England Rounds 1 & 2 +6GW Belgium
Interface 4 GW (5.5GW) GW
(7
Offshore Wind Output Netherlands Shore Line 110
100
90 80 Belgium Shore Line 70 HVDC Transmission 60
50 Output % Output 40 AC Transmission
30 20 12 10
0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 Time (hours)
6 Dogger Bank – Integrated Control Challenge 80% Wind Output
Connected to Scottish Connected to Norway Offshore Network Offs hore NNtetwork HVDC converter capacity fully used transmitting the wind generation output. 2GW
400 MW 800 MW 100 MW 1.8GW 400 MW 300 MW
500 MW 100 MW 300 MW 100 MW 100 MW 100 MW 100 MW 100 MW 500 MW 100 MW 300 MW 500 MW 300 MW 300 MW 400 MW 500 MW 500 MW 300 MW 100 MW 400 MW 300 MW 300 MW 500 MW 400 MW 400 MW 400 MW 400 MW 400 MW
700 MW 300 MW 100 MW 0GW 1.5GW 1.2GW 1.2GW 0GW 1.7GW 0.9GW
AC 500MW platform Connected to English East Coast Onshore Network HVDC converter station
HVDC 2GW ‐ 500kV cable AC 220kV cable 13
An integrated network solution has multiple benefits
Other benefits include: ~25% potential savings Meeting / potentially exceeding developer timelines for UK consumers Strengthening security of supply More resilient / reliable network Maximising deliverability: Reduces supply chain pressures through Reduces planning lower asset volumes consent issues Better secures resources to enable a step- up in UK supply chain capacity Supports vital technology development Facilitates a move towards standardisation Better management & utilisation Minimising environmental impact oflblf valuable resources Streng theni ng UK ro le in EU energy Enabler of a North Seas grid Increased potential for UK to export excess “Future proof” for network wind power Step towards engaging and influencing the evolution & greater European EU landscape integration
14
7 1 /01/2011
Matthew Knight, Head of Business Development Offshore Grid Technology Siemens Transmission and Technology options and practical issues for Distribution Limited offshore networks [email protected]
CIGRE London Copyright © Siemens. All rights reserved. 17/01/11 Matthew Knight Copyright Siemens all rights reserved
Chuxiong – world first 5GW, ±800kV HVDC link
Page 2 January 2011 Matthew Knight Copyright Siemens all rights reserved
1 1 /01/2011
China: >104*GW transmission capacity expansion by 2019
1. Hami – C. China 12. Hulunbeir – Shenyang 800 kV, 6400 MW, 2018 500 kV, 3000 MW, 2009 Heilongjiang 2. Xiangjiaba – Shanghai 13. B2B NE – North (Gaoling) 800 kV, 6400 MW, 2011 500 kV, 1500 MW, 2008 20 12 3. Xiluodu – Hangzhou Jilin 14. Humeng – Jinan (Shandong) 800 kV, 6400 MW, 2015 18 800 kV, 6400 MW, 2015 4. Xiluodu – Guangdong 14 Xinjiang Liaoning 15. North Shaanxi – Shandong 800 kV, 6400 MW, 2013 13 500 kV, 3000 MW, 2011 Inrfar Mongolia Beijing Gansu Tianjin 5. Jinsha River II – East China Hebei 16. Ningxia – Shandong 800 kV, 6400 MW, 2016 1 15 660 kV, 2 x 4000 MW, 2010 16 Shanxi Shandong 6. Jingping – Sunan Ningxia 17. Baoji – Deyang 800 kV, 7200 MW, 2012 Henan Jiangsu Qinghai 17 500 kV, 3000 MW, 2010 Anhuj 7. Jinsha River II – East China Shaanxi 2 Shanghai 18. Mongolia – Beijing 800 kV, 6400 MW, 2019 Sichuan & Hubai 660 kV, 4000 MW, 2010 Xizang Chongqing Zheijjgang 3 Jiangxi 8. Jinsh a Ri ver II – FjiFujian 19 5 19. Xiluodu – Hunan 800 kV, 6400 MW, 2018 6 660 kV, 4000 MW, 2011 7 Guizhou Fujian 9. Nuozhadu – Guangdong 8 20. Irkutsk (Russia) – Beijing 800 kV, 5000 MW, 2015 4 Yunnan 11 Taiwan 800 kV, 6400 MW, 2015 9 Guangdong 10. Jinghong – Thailand Guangxi 3000 MW, 2013
11. Yunnan – Guangdong 10 800 kV, 5000 MW, 2009 Bangkok Hainan *with options for further Projects > 7 GW!
Page 3 January 2011 Matthew Knight Copyright Siemens all rights reserved
China vs. EU
Wind Power > 20...40 GW
Hydro Power > 10..30 GW Hydro Power > 30...50 GW
2000 km 2000 km
Solar >10..20 GW Load Center
Similar distances and capacity required Differently organised Submarine connections . OH line technology not available for UK part of the EU supergrid
Page 4 January 2011 Matthew Knight Copyright Siemens all rights reserved
2 1 /01/2011
What’s needed?
Offshore transmission technology . High capacity AC . Long distance . Cable . Reliable . GIL . Stable DC . Work with existing infrastructure . CSC . And new renewable generation . VSC . Extendable Grid Topology . Affordable Practical issues
Page 5 January 2011 Matthew Knight Copyright Siemens all rights reserved
AC Power Transmission - The basic Equation P V1 , 1 V2 , 2
G ~ G ~ X
V1 V2 P = sin ( 1 - 2) X
Series Compensation Power-Flow Control Parallel Compensation
Each of these Parameters can be used for Load- Flow Control and Power Oscillation Damping
Page 6 January 2011 Matthew Knight Copyright Siemens all rights reserved