Integrated Offshore Networks: the Context of Our Work

Total Page:16

File Type:pdf, Size:1020Kb

Integrated Offshore Networks: the Context of Our Work Developing offshore grids : An integrated approach Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Andrew Hiorns Integrated offshore networks: the context of our work Sustainability We are interested in establishing workable arrangements at the lowest costs for UK consumers such that: The potential deliverability of offshore wind is maximised Security of supply and network resilience are maximised The overall cost to consumers is minimised Affordability The scale of potential offshore a Offshore wind leased wind necessitates reflection on capacity* the delivery challenges: 1GW Security of supply 7GW European interconnection Technology development Security of 32GW supply Supply chain capability Planning consents Financing Round 1 Round 2 Round 3 Skills * Source: DECC website 2 http://www.decc.gov.uk/en/content/cms/what_we_do/uk_supply/energy_mix/renewable/policy/offshore/wind_leasing/wind_leasing.aspx 1 Assumptions: Generation mix scenarios 2008/09 TRANSMISSION SYSTEM AS AT 31st DECEMBER 2007 400kV Substations 275kV Substations Slow Progression 132kV Substations 400kV Circuits 275kV Circuits 132kV Circuits Major Generating Sites Including Pumped Storage Pentland Firth Connected at 400kV THE SHETLAND ISLANDS 6 Connected at 275kV 9,724MW offshore wind in 2020 Hydro Generation 23,174MW offshore wind in 2030 1 21% renewable electricity generation 2020 target missed 5 7 8 9 2 10 Gone Green 4 3 16,374MW offshore wind in 2020 3 Tongland 2 2 14 26,354MW offshore wind in 2030 1 3 4 1 32% renewable electricity generation 4 2 3 17 16 2020 target hit 15 9 4 5 7 6 14 11 13 13 12 12 10 11 Accelerated growth 5 9 10 7 8 32,239MW offshore wind in 2020 6 9 5 51,552MW offshore wind in 2030 8 43% renewable electricity generation 6 2020 target exceeded 7 3 Technology Assumptions: New technology is needed under both a radial & integrated solution HVDC cables AC cables Technology is still developing Appropriate only over shorter distances 2-3 year development lead times for the Capacitive effects increase exponentially larger cables over distance Cables where lead times exceed 2-3 Reactive compensation required, but years not used in our study before 2020 ineffective over distance, reducing real power capacity Platform design Smart grids Currently bespoke by project / application Scope for standardisation under an Could be developed as part of an integrated solution integrated solution We have not assumed radical technology solutions pre 2020 4 2 Interaction with onshore TRANSMISSION SYSTEM REINFORCEMENTS Power transfers Dounreay Thurso REINFORCED NETWORK Mybster Stornoway Cassley Dunbeath 400kV Substations Lairg 275kV Substations THE SHETLAND ISLANDS Brora 400kV CIRCUITS North-South will increase Shin 275kV CIRCUITS Grudie Mossford Major Generating Sites Including Pumped Storage Bridge Alness Conon Orrin Elgin Fraserburgh Luichart Ardmore Macduff St. Fergus Connected at 400kV Deanie Dingwall Cu llig ran Keith Strichen Connected at 275kV Aigas Inverness Nairn How might these be managed? Bla ckh illock Dunvegan Kilmorack Peterhead Hydro Generation Beauly Fasnakyle Dyce Glen Kintore Persley Broadford Morrison Woodhill Willowdale Foyers Ceannacroc Boat of Fort Augustus Garten Clayhills Under Construction or ready to start Tarland Craigiebuckler Redmoss Invergarry Construction subject to consents Quoich Fiddes Fort William Errochty Errochty Power Station Rannoch Clunie Bridge of Dun Very strong need case Tummel Lunanhead Bridge Tealing Cashlie Dudhope Arbroath Lochay Lyndhurst Milton of Craigie Radial solutions Taynuilt K illin Finlarig Charleston Cruachan Da lm ally Burghmuir Dudhope Glenagnes Strong need case St. Fillans Nant Clachan SCOTTISH HYDRO-ELECTRIC Cup ar TRANSMISSION Inveraray Glenrothes Sloy Leven Devonside Westfield Red house W h is tl ef ie ld Stirling K inca rdine Glenniston Port Mossmorran Future requirement, but no strong Dunfe rmline Ann Lon gann et B onnybridge I verkeithing Dunoon Helensbu rgh Grang emou th Shrubh ill Cockenzie need case to commence Dun bar Sp ango Devol Strathleven Telford Rd. Portobello Valley M oor Broxburn Gorgie Torness Erskine Cu mbe rn auld Bathg ate Wh ite hou se Inverkip La mbh ill at present Ea ste rho use Radial connections to the nearest landing point L ivingsto n Kaimes Cu rrie Newarthill Clydes Neilston Mill Hun tersto n Berwick Fa rm Wishaw Hunterston Busby Strathave n Blacklaw Kilwinning Whitelee East Series Capacitors K ilmarnock Kilbride Saltcoats To wn South Linm ill Eccles Carradale Me ado whea d G a la sh ie ls Kilmarnock Coalburn South Ayr SP TRANSMISSION LTD. and then additional onshore reinforcements to Coylton Elvanfoot Ha wick Ma ybole NGC Gretna Blyth Du mfries Ecclefecha n provide additional capacity (minimum offshore Auchencrosh Fourstones New ton T ynemouth Stewart Harker South Shields Chapelcross S te lla West West Boldon Glenluce Tongland Offerton Hawthorne Pit Hart Moor B6 Spennymoor Hartlepool costs v’s maximum onshore costs) Saltholme Tod Point Grangetown Norton Greystones Lackenby Hutton Radial connections extended significantly to Heysham Quernmore Poppleton Osbaldwick Thornton Bradford West Kirkstall Stanah Skelton Creyke Beck Padiham Grange Monk Fryston Saltend North avoid onshore reinforcement (maximum Saltend South Penwortham Elland Drax Killingholme Eggborough Humber Refinery B7 Rochda le Ferrybridge Keadby Washway South Templeborough Thorpe Humber Farm Kearsley Whitegate West Kirkby Marsh Bank Grimsby South Melton Lister Stalybridge West Wylfa Manchester Pitsmoor Drive Ra in hill Stocksbridge Aldwarke West Carrington Bredbury Winco Bank Burton Birkenhead Thurcroft offs hore cos ts v ’s m in imum ons hore cos ts ) Neepsend Fiddlers Daines Sheffield City Ferry Brinsworth Cottam Capenhurst Frodsham Jordanthorpe Norton Lees Pentir Macclesfield Chesterfield Deeside High Dinorwig Marnham Staythorpe Legacy Ffestiniog Cellarhead Bicker Fenn Willington Optimum balance sought between radial Trawsfynydd Ratcliffe Drakelow Walpole Rugeley Spalding North Norwich Ironbridge Bushbury Main Willenhall Bustleholm B8 Sh re wsbu ry Enderby Penn Hams Nechells Hall offshore costs vs onshore costs (ODIS) Ocker Hill Coventry O ldbury Kitwell Berkswell Sizewell Burwell Feckenham Main Bishops Grendon Eaton Wood Socon Patford Bramford Bridge East Sundon Claydon Pelham Wymondley Leighton Braintree Buzzard Rassau Walham Rye House Waltham Imperial Brimsdown Cross Park Swansea Cowley Pembroke Watford Elstree Hackney North Amersham Main Rayleigh Main Baglan Cilfynydd Whitson Culham Mill Hill Tottenham Redbridge Warley B9 Minety Didcot Bay Upper Boat Uskmouth Iron Acton Willesden West Thurrock Margam Barking Coryton Alpha Steel Iver Ealing Northfleet East Pyle N.Hyde Singlewell Seabank City Rd W.Ham Tilbury Grain Cowbridge St Johns Tremorfa Laleham Wood New Hurst Cross Kingsnorth Integrated solution Aberthaw Cardiff East West Kemsley Melksham Bramley Weybridge Chessington Rowdown Littlebrook Beddington Fleet Canterbury Wimbledon North Hinkle y Po in t Sellindge Bridgwater Alverdiscott Bolney Nursling Taunton Ninfield E de F Dungeness Marchwood Lovedean Axminster Mannington Fawley Botley Wood Exeter Designs fully integrated to minimise total cost Chickerell Langage Abham Landulph Indian Queens ISSUE B 12-02-09 41/177619 C Collins Bartholomew Ltd 1999 and impact on environment 5 Increased supply security by integration Assuming transmission circuit availability of 95% Annual load factor of offshore wind generation ~40% Radial C1Case 1 -RdilRadial connec tion = 5% x 40% = 2% of installed capacity Total wind generation curtailment = 2% Case 2 – Integrated, sufficient transmission capacity to accommodate 100% wind generation output Intact offshore network, Wind generation output curtailment = 0% Outage of transmission network, Wind generation output curtailment Integrated = 5% x 5% x 40% = 0.1% of installed capacity Total wind generation curtailment = 0.1% Case 3 – Integrated, sufficient transmission capacity to accommodate 90% wind generation output, Intact curtailment = 2.3% Outage curtailment = 5% x 5% x 40% = 0.1% of installed capacity Total wind generation curtailment = 2.4% 6 3 Radial and Integrated UK Offshore Radial solution Integrated solution 7 Design Options Radial 1GW cable to shore 1GW cables to shore 1GW cables to shore 1GW cables to shore Clustered 2GW cable to shore 2GW cable to shore 2GW cables to shore 2GW cab les to s ho re Integrated 2GW cable to shore 2GW cables to shore 2GW cables to shore 2GW cables to shore 8 4 Interaction with interconnectors 1 Case 1 – Radial wind with 100% connection transmission capacity Offshore Wind Output 110 100 CT • Very little restriction of wind output 90 CWF 80 • Transmission utilisation 35-45% 70 Un-utilised transmission 60 50 Output % 40 30 20 CT 10 0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 CWF =CT Time (hours) Case 2 – Wind and interconnection at 100% transmission capacity Offshore Wind Output 110 100 • Potentially either heavily curtailment of wind 90 CT CWF 80 generation output or interconnector trading 70 60 • Potentially 100% transmission utilisation Interconnection 50 Output % 40 • Limitations on ability to use interconnectors 30 20 exist nearly all times 10 CT CI 0 1 501 1001 1501 2001 2501 3001 3501 4001 4501 5001 5501 6001 6501 7001 7501 8001 8501 Time (hours) CT -CI CWF =CT = CI Period when there are potential conflicts 9 Interaction with interconnectors
Recommended publications
  • Länderprofil Großbritannien Stand: Juli / 2013
    Länderprofil Großbritannien Stand: Juli / 2013 Impressum Herausgeber: Deutsche Energie-Agentur GmbH (dena) Regenerative Energien Chausseestraße 128a 10115 Berlin, Germany Telefon: + 49 (0)30 72 6165 - 600 Telefax: + 49 (0)30 72 6165 – 699 E-Mail: [email protected] [email protected] Internet: www.dena.de Die dena unterstützt im Rahmen der Exportinitiative Erneuerbare Energien des Bundesministeriums für Wirtschaft und Technologie (BMWi) deutsche Unternehmen der Erneuerbare-Energien-Branche bei der Auslandsmarkterschließung. Dieses Länderprofil liefert Informationen zur Energiesituation, zu energiepolitischen und wirtschaftlichen Rahmenbedingungen sowie Standort- und Geschäftsbedingungen für erneuerbare Energien im Überblick. Das Werk einschließlich aller seiner Teile ist urheberrechtlich geschützt. Jede Verwertung, die nicht ausdrücklich vom Urheberrechtsgesetz zugelassen ist, bedarf der vorherigen Zustimmung der dena. Sämtliche Inhalte wurden mit größtmöglicher Sorgfalt und nach bestem Wissen erstellt. Die dena übernimmt keine Gewähr für die Aktualität, Richtigkeit, Vollständigkeit oder Qualität der bereitgestellten Informationen. Für Schäden materieller oder immaterieller Art, die durch Nutzen oder Nichtnutzung der dargebotenen Informationen unmittelbar oder mittelbar verursacht werden, haftet die dena nicht, sofern ihr nicht nachweislich vorsätzliches oder grob fahrlässiges Verschulden zur Last gelegt werden kann. Offizielle Websites www.renewables-made-in-germany.com www.exportinitiative.de Länderprofil Großbritannien – Informationen für
    [Show full text]
  • ABLE Marine Energy Park (AMEP) ABLE Humber Port, East Coast, UK Establishing a New Offshore Wind Cluster
    ABLE Marine Energy Park (AMEP) ABLE Humber Port, East Coast, UK Establishing a New Offshore Wind Cluster Information on AMEP to Support the Attraction of Offshore Wind Activity - 2021 Contents 3. Introduction 4. ABLE Marine Energy Park Aerial View 5. Location - Connectivity to Europe 6. Location - Road & Rail 7. Location - Proximity to Market 8. AMEP - The Offer 9. AMEP - Freeport Status 10. AMEP - Optimum Site Solutions 11. AMEP - Indicative Working Plan 12. AMEP - Offshore Wind Work Flow 13. Hornsea One Offshore Wind Farm 14. Triton Knoll Offshore Wind Farm 15. Dogger Bank Offshore Wind Farm 16. Planning - Fully Consented 17. Cost Reduction Opportunities 18. Wind Installation Vessels - Benefits 19. AMEP - Technical Specification 21. AMEP - Operating Model 22. AMEP - Competitive Advantage 23. Heavy Lift & Transport Services 24. The Humber Estuary Characteristics 25. Humber - Tees & Tyne Comparisons 27. Workforce - Productivity 28. Workforce - Availability 29. Production & Assembly - Workforce 31. Financial Support for Investment Document Reference: CM.NFE-AMEP-OSW-29 January 2021 Introduction ABLE Marine Energy Park (AMEP). Able Marine Energy Park (AMEP) is a port development on the south bank of the Humber Estuary on the East Coast of the United Kingdom. It is a nationally significant infrastructure project (NSIP) and is recognised as a core development within the UK Government Infrastructure Roadmap. The AMEP project base case involves developing Phase 1 with 1,349m of installation quays, 4no. installation yards (78.63 ha), with an additional 139 ha for manufacturer storage. It represents a singular opportunity for the UK to establish a world-scale industrial cluster and enable the UK to maximise the economic development potential provided by the combination of the emerging market and supportive policies.
    [Show full text]
  • Forecast from 2016-17 to 2019-20
    Tariff Information Paper Forecast TNUoS tariffs from 2016/17 to 2019/20 This information paper provides a forecast of Transmission Network Use of System (TNUoS) tariffs from 2016/17 to 2019/20. These tariffs apply to generators and suppliers. This annual publication is intended to show how tariffs may evolve over the next five years. The forecast tariffs for 2016/17 will be refined throughout the year. 28 January 2015 Version 1.0 1 Contents 1. Executive Summary....................................................................................4 2. Five Year Tariff Forecast Tables ...............................................................5 2.1 Generation Tariffs ................................................................................. 5 2.2 Onshore Local Circuit Tariffs ..............................................................10 2.3 Onshore Local Substation Tariffs .......................................................12 Any Questions? 2.4 Offshore Local Tariffs .........................................................................12 2.5 Demand Tariffs ...................................................................................13 Contact: 3. Key Drivers for Tariff Changes................................................................14 Mary Owen 3.1 CMP213 (Project TransmiT)...............................................................14 Stuart Boyle 3.2 HVDC Circuits.....................................................................................14 3.3 Contracted Generation .......................................................................15
    [Show full text]
  • Transmission Networks Connections Update
    Transmission Networks Connections Update May 2015 SHE-T–TO SPT–TO NG–TO/SO SHE-T–TO SPT–TO NG–TO/SO Back to Contents TNCU – May 2015 Page 01 Contents Foreword ////////////////////////////////////////////////////////////////// 02 1. Introduction /////////////////////////////////////////////////////////// 03 2. Connection timescales ///////////////////////////////////////////// 04 Illustrative connection timescales /////////////////////////////////////// 04 Connections by area /////////////////////////////////////////////////////// 05 3. GB projects by year ///////////////////////////////////////////////// 06 Contracted overall position /////////////////////////////////////////////// 08 Renewable projects status by year ///////////////////////////////////// 10 Non-Renewable projects status by year – Excluding Nuclear /// 11 Non-Renewable projects status by year – Nuclear only ////////// 12 Interconnector projects status by year //////////////////////////////// 13 4. Additional data by transmission owner ///////////////////////// 14 National Grid Electricity Transmission plc //////////////////////////// 16 Scottish Hydro Electricity Transmission plc ////////////////////////// 18 Scottish Power Transmission Limited ///////////////////////////////// 20 5. Connection locations /////////////////////////////////////////////// 22 Northern Scotland projects map //////////////////////////////////////// 25 Southern Scotland projects map /////////////////////////////////////// 28 Northern England projects map /////////////////////////////////////////
    [Show full text]
  • Sofia Ground Model Developed by NGI Not Confidential
    EV108 Sofia ground model developed by NGI Not confidential Sofia Offshore Wind Farm Limited 154 - Synthetic CPTs from Intelligent Ground Models based on the integration of geology, geotechnics and geophysics as a tool for conceptual foundation design and soil investigation planning CF Forsberg, T Lunne and M Vanneste Norwegian Geotechnical Institute, Oslo, Norway L James Forewind, UK/RPS, UK TI Tjelta Forewind, UK /Statoil, Norway A Barwise Statkraft UK Ltd. / RWE Innogy UK Ltd C Duffy Forewind, UK/Statkraft UK Ltd. Abstract Early phase soil investigation campaigns do not as a rule include all the locations where infrastructure is to be placed on the seafloor. However, background information on geology, bathymetric and seismic data may be available across the area at an early stage. The combination of these datasets thus provides the basis for devel- oping a ground model of the development area. The inclusion of geotechnical data in such ground models is not always straightforward since geotechnical properties may vary laterally and with depth. In this paper we present an "Intelligent Ground Model", developed at NGI, and used at several large wind farm projects. The model combines interpreted seismic horizons with geological understanding and acquired CPTU data to allow synthetic CPTUs to be generated at any location within the investigated area. In the Dogger Bank wind farm area, synthetic CPTUs were generated at numerous locations to guide initial evaluations of foundation require- ments and to group locations with similar synthetic profiles. The model was tested by removing known CPTU data from the database and comparing them to synthetic results from the same locations.
    [Show full text]
  • Concrete Support Structures for Offshore Wind Turbines: Current Status, Challenges, and Future Trends
    energies Review Concrete Support Structures for Offshore Wind Turbines: Current Status, Challenges, and Future Trends Alexandre Mathern 1,2,* , Christoph von der Haar 3 and Steffen Marx 4 1 Department of Architecture and Civil Engineering, Chalmers University of Technology, Sven Hultins Gata 6, SE-41296 Gothenburg, Sweden 2 Research and Innovation, NCC AB, Lilla Bomen 3c, SE-41104 Gothenburg, Sweden 3 grbv Ingenieure im Bauwesen GmbH & Co. KG, Expo Plaza 10, 30539 Hannover, Germany; [email protected] 4 Institute of Concrete Structures, Technische Universität Dresden, August-Bebel-Straße 30/30A, 01219 Dresden, Germany; [email protected] * Correspondence: [email protected] or [email protected] Abstract: Today’s offshore wind turbine support structures market is largely dominated by steel structures, since steel monopiles account for the vast majority of installations in the last decade and new types of multi-leg steel structures have been developed in recent years. However, as wind turbines become bigger, and potential sites for offshore wind farms are located in ever deeper waters and ever further from the shore, the conditions for the design, transport, and installation of support structures are changing. In light of these facts, this paper identifies and categorizes the challenges and future trends related to the use of concrete for support structures of future offshore wind projects. To do so, recent advances and technologies still under development for both bottom-fixed and floating concrete support structures have been reviewed. It was found that these new developments meet the Citation: Mathern, A.; von der Haar, challenges associated with the use of concrete support structures, as they will allow the production C.; Marx, S.
    [Show full text]
  • Planning Statement
    Dogger Bank C/Sofia Onshore Works Application Planning Statement Classification: N/A Status: ISSUE Expiry date: N/A 1 of 44 Classification: N/A Status: ISSUE Expiry date: N/A 2 of 44 Doc. No. Rev. no. 01 Planning Statement Valid from: July 2020 Table of contents 1 Introduction ....................................................................................................................................................5 1.1 Purpose of the Report ......................................................................................................................................5 1.2 The Development .............................................................................................................................................5 1.3 The Site and its Surroundings ..........................................................................................................................5 1.4 Planning History ...............................................................................................................................................6 2 Project Description ........................................................................................................................................6 2.1 Overview ..........................................................................................................................................................6 3 Planning Policy Framework ..........................................................................................................................6 3.1
    [Show full text]
  • TOP 100 POWER PEOPLE 2015 the Movers and Shakers in Wind
    2015 Top 100 Power People 1 TOP 100 POWER PEOPLE 2015 The movers and shakers in wind LordFeaturing Irvine anLaidlaw exclusive talks interview exclusively with to ALord Word Irvine© AAbout Word AboutLaidlaw Wind,Wind 2015 2015 Top 100 Power People Contents 2 CONTENTS Editorial: Introducing the Top 100 Power People 3 Compiling the Top 100: Advisory panel and ranking process 4 Exclusive: A Word About Wind meets Lord Laidlaw 7 Top 100 breakdown: Statistics on this year’s table 13 Profles: Numbers 100 to 26 14 Profles: Numbers 25 to 6 24 Top fve profles: The most infuential people in global wind 26 Top 100 list: The full Top 100 Power People for 2015 28 Next year: Key dates for your diary in 2016 31 Networking at A Word About Wind annual conference in 2015 © A Word About Wind, 2015 2015 Top 100 Power People Editorial 3 EDITORIAL re institutional lenders more vital to growing their operations in emerging wind Awind than developers? markets in Asia, Africa and South America. That international focus has remained this Do private equity frms make a larger year, but we have seen other changes. contribution than big turbine makers? One big trend we have seen this year is And are senior advisers more infuential the number of private equity players in the than those inventing groundbreaking tech? table. There are 12 people from private equity frms in this year’s Top 100, including by Richard Heap, These are three tough questions, and the nine who have not featured before. editor at A Word About Wind truthful answer is that it is very diffcult to compare the different contributions made The wide range of investments made by these hugely diverse types of businesses.
    [Show full text]
  • World's Largest Wind Farm
    client | Forewind “Having worked so thoroughly on our offshore Tranche A projects, the team from Royal HaskoningDHV is now able to build on the learning and knowledge gleaned so far for our next phase of Tranche B projects and put into practice its expertise to assist Forewind in its delivery objectives for the Dogger Bank Zone.” Gareth Lewis, Head of Offshore Development World’s largest wind farm The Dogger Bank wind farm zone, located in the In June 2010, Royal HaskoningDHV was awarded the North Sea off the coast of East Yorkshire, is potentially roles of ‘Offshore Environmental Impact Assessment the world’s largest offshore wind project. If fully (EIA) Coordinator’ for Tranche A and ‘Onshore EIA Co- developed, the 8,660km2 area could contain more ordinator’ for the first project application, via a competitive than 2,000 wind turbine generators and provide an tender. In October 2011, a framework was agreed for immense 13GW of electricity – enough to supply ten Royal HaskoningDHV to provide complete EIA services up per cent of the UK’s electricity requirements. to, and including, the final project in Tranche B, covering projects up to 6GW of capacity. Given the size of the development, the zone will be developed in a series of ‘Tranches’, each containing a Robert Staniland, Technical Director of Offshore Wind, number of projects with an overall capacity of around Royal HaskoningDHV, said: “We are naturally incredibly 3GW in each Tranche. proud for the team to be working on such a prestigious project”. The plans for the Dogger Bank zone are being developed by Forewind, a four-company consortium comprising “Royal HaskoningDHV has an enviable and proven track SSE, RWE npower renewables, and Norwegian energy record in the offshore wind market, having seen projects companies Statoil and Statkraft.
    [Show full text]
  • Modelling and Control of an ACDC System with Significant Generation from Wind
    Modelling and control of an ACDC system with significant generation from wind Author: Stefanie Tatjana Gertraud Supervisor: Ingeborg Kuenzel Prof. Bikash C. Pal (CID: 00485684) A report submitted in fulfilment of requirements for PhD examination. Control and Power Group Dept. of Electrical and Electronic Engineering Imperial College London July 2, 2014 1 Declaration of Originality and Copyright Declaration The work in this thesis is my own and all other material used is referenced accordingly. The copyright of this thesis rests with the author and is made available under a Creative Commons Attribution Non-Commercial No Derivatives licence. Researchers are free to copy, distribute or transmit the thesis on the condition that they attribute it, that they do not use it for commercial purposes and that they do not alter, transform or build upon it. For any reuse or redistribution, researchers must make clear to others the licence terms of this work. 2 Abstract This PhD project investigates the modelling and analysis of an AC-DC system with synchronous and asynchronous generation (wind farms). The GB network is undergoing major changes including the installation of large amounts of wind generation. Wind farm developments further offshore will be connected via DC connections, such as the eastern link. The first two chapters of the thesis will provide an outline of these changes to the GB system, and the impact of those changes on the frequency response capability of the GB system. In continuation the thesis will engage in modelling details of an AC system with integration of DC technology and wind. The modelling aim is a comprehensive grid representation in a multi-machine small signal stability framework.
    [Show full text]
  • 'Business Intelligence Offshore Wind'
    ‘Business Intelligence Offshore Wind’ Een studie in opdracht van ECN naar trends en kostenontwikkeling van offshore wind technologie in Europa P.F. van den Oosterkamp A. Curvers S. Dijkstra S.M. Lensink J. Gerdes December 2012 ECN-E--10-006 1 Verantwoording Dit rapport is geschreven in opdracht van ECN. De financiering van dit project is afkomstig van een beschikbaar budget in relatie van extra EZS ten gevolge van loon & prijsbijstelling in 2011. 2 ECN-E--10-006 Inhoud Lijst van tabellen 4 Lijst van figuren 4 Samenvatting 5 1. Inleiding 6 2. Probleemstelling 7 3. Onderzoeksvragen 8 3.1 Centrale onderzoeksvraag 8 3.2 Deelvragen 8 4. Opzet van de studie 9 4.1 Type onderzoek 9 4.2 Gegevensverzameling en methodologie 9 4.3 Gegevensverwerking 9 5. Afbakening en beperking van de studie 10 6. Resultaten van het onderzoek 11 6.1 De offshore wind industrie in Europa 11 6.1.1 Algemeen 11 6.1.2 Geïnstalleerd vermogen aan offshore wind in Europa in 2011 11 6.1.3 Gepland vermogen aan offshore wind in Europa 12 6.1.4 Relatie van geïnstalleerd vermogen en NREAP’s 13 6.1.5 Windaanbod, kustafstand en diepte in de geïdentificeerde locaties 15 6.1.6 Spelers in offshore wind technologie 16 6.1.7 Kostenprofiel en financiering van offshore wind parken 16 6.2 Technologieontwikkelingen offshore wind in de komende 20 jaar 25 6.3 Kosten en leereffecten van offshore windtechnologie 32 6.3.1 Leereffecten van offshore wind energie 32 6.3.2 Inschatting van kostprijs elektriciteit 34 6.3.2.1 Het ECN kosten model voor offshore wind 34 6.3.3 Inschatting van kostprijs elektriciteit in betrokken projecten 38 6.4 Europees beleid t.a.v.
    [Show full text]
  • Electricity Ten Year Statement 2017
    Electricity Ten Year Statement November 2017 Statement Year Electricity Ten Future Energy Scenarios July 2017 a c Electricity Ten Year Statement 2017 UK electricity transmission November 2017 NOVEMBER 2017 Electricity Ten Year Statement November 2017 How to use this interactive document To help you find the information you need quickly and easily we have published the ETYS as an interactive document. Home A to Z This will take you to the contents page. You will find a link to the glossary You can click on the titles to navigate on each page. to a section. Hyperlinks Arrows Hyperlinks are underlined and highlighted Click on the arrows to move in the chapter colour throughout the backwards or forwards a page. report. You can click on them to access further information. Electricity Ten Year Statement November 2017 01 We are in the midst of an energy revolution. The economic landscape, developments in technology and consumer behaviour are changing at an unprecedented rate, creating more opportunities than ever for our industry. Our Electricity Ten Year We will assess the options for network Statement, along with our other reinforcement through our Network System Operator publications, Options Assessment (NOA). The aims to encourage and inform NOA aims to make sure that the debate, leading to changes that transmission system is continuously ensure a secure, sustainable developed in a timely, economic and and affordable energy future. efficient way, providing value for our customers. The NOA 2016/17, using Your views, knowledge and insight the assessment results from ETYS have shaped the publication. Thank 2016, recommended £83 million of you for this valuable input over the development spend on future network past year.
    [Show full text]