EERA DTOC Calculation of Scenarios

Total Page:16

File Type:pdf, Size:1020Kb

EERA DTOC Calculation of Scenarios EERA DTOC calculation of scenarios Gerard Schepers, Alfredo Pena, Alice Ely, Ana Palomares, Ayman Attiya, Giorgos Sieros, Gregor Giebel, Harald Svendsen, Ilona Bastigkeit, Ioanna Karagali, Ivan Moya, Olimpo Anaya Lara, Pablo Ledesma, Pedro M. Fernandes Correia, Vitar Gosta Gomez, Wei He June, 2015 Agreement n.: FP7-ENERGY-2011-1/ n°282797 Duration January 2012 to June 2015 Co-ordinator: DTU Wind Energy, Risø Campus, Denmark PROPRIETARY RIGHTS STATEMENT This document contains information, which is proprietary to the “EERA-DTOC” Consortium. Neither this document nor the information contained herein shall be used, duplicated or communicated by any means to any third party, in whole or in parts, except with prior written consent of the “EERA-DTOC” consortium. Document information Document Name: EERA DTOC Calculation of scenarios Document Number: D5.12 Author: Gerard Schepers, Alfredo Pena, Alice Ely, Ana Palomares, Ayman Attiya, Giorgos Sieros, Gregor Giebel, Harald Svendsen, Ilona Bastigkeit, Ioanna Karagali, Ivan Moya, Olimpo Anaya Lara, Pablo Ledesma, Pedro M. Fernandes Correia, Vitar Gosta Gomez, Wei He Date: June 2015 WP: 5 Task: 5.3 2 | P a g e Deliverable 5.12 EERA DTOC calculation of scenarios TABLE OF CONTENTS TABLE OF CONTENTS ............................................................................................................................. 3 SUMMARY ............................................................................................................................................... 5 1. INTRODUCTION ................................................................................................................................ 6 1.1 Background ........................................................................................................................................... 6 1.2 Goal of scenarios and document ......................................................................................................... 6 1.3 Approach ............................................................................................................................................... 6 2. APPROACH ....................................................................................................................................... 8 3. RESULTS ........................................................................................................................................ 10 4. CONCLUSIONS ............................................................................................................................... 11 5. REFERENCES ................................................................................................................................. 12 6. APPENDIX A: DTU BASE SCENARIO – STANDARD LAYOUT ......................................................... 13 7. APPENDIX B: DTU: NEAR FUTURE SCENARIO – STANDARD LAYOUT ......................................... 17 8. APPENDIX C: ECN: NEAR FUTURE SCENARIO – NET ENERGY YIELD (OFF-LINE) ....................... 21 9. APPENDIX D: RES: BASE SCENARIO – USER EXPERIENCE ......................................................... 29 10. APPENDIX E: UPORTO – BASE SCENARIO, WIND FARM EFFICIENCY VS. OFFLINE RANS CALCULATIONS ..................................................................................................................................... 34 11. APPENDIX F: TEST REPORT IWES ................................................................................................. 40 12. APPENDIX G: DTU: HUB HEIGHT VARIATIONS AT RACE BANK .................................................... 45 13. APPENDIX H: CRES: NEAR FUTURE SCENARIO – LAYOUT AND WT VARIATIONS ....................... 49 14. APPENDIX I: VALIDATION OF WASP AND FUGA AEP CALCULATIONS IN THE EERA-DTOC TOOL 59 15. APPENDIX J: MESOSCALE SIMULATION OF FAR WAKE EFFECTS AT RACE BANK WIND FARM (BASE SCENARIO) ................................................................................................................................. 64 16. APPENDIX K: CIEMAT: NEAR FUTURE SCENARIO – NET ENERGY YIELD (OFF-LINE) ................. 73 17. APPENDIX L: FAR FUTURE SCENARIO – OFFSHORE GRID OPTIMIZATION FROM SINTEF ......... 83 3 | P a g e Deliverable 5.12 EERA DTOC calculation of scenarios 18. APPENDIX M: STRATHCLYDE: VERIFICATION OF GRID CODE COMPLIANCE FOR FAR FUTURE WIND CLUSTERS: .................................................................................................................................. 90 19. APPENDIX N: DTU BASE SCENARIO – STANDARD LAYOUT WITH WIND FARMS REMOVED ... 106 20. APPENDIX O: DTU: NEAR FUTURE SCENARIO – STANDARD LAYOUT ....................................... 110 21. APPENDIX P: DTU: NEAR FUTURE SCENARIO – FLOATING LAYOUT ......................................... 114 22. APPENDIX Q: DTU: VALIDATION OF WRF WIND CLIMATES WITH SCATTEROMETERS ............. 118 4 | P a g e Deliverable 5.12 EERA DTOC calculation of scenarios SUMMARY This report describes the calculation of scenarios which have been defined to demonstrate the value of the EERA-DTOC tool. Thereto it should be realized that the value of the EERA-DTOC tool could best be demonstrated by a comparison with measurements but the intended clusters for which the tool is developed are still mainly in the planning phase by which measurements to validate the tool are lacking. However, by the calculation of likely scenarios, the industrial usefulness of the tool can still be tested where moreover an ‘expert view’ on the results will be carried out in order to check their degree of reality. Therefore several scenarios are described which are denoted as the ‘base and the near future scenario’, i.e. scenarios which are still relatively close to the present state of the art wind farm (clusters). This is in particular true for the base scenario which is described as a scenario which reflects ‘the current way of thinking’. The near future scenario goes beyond the current way of thinking by using upscaled turbines. The description of these scenarios is given in D5.2 The base scenario considers a 500MW wind farm which consists of hundred turbines with a rated power of 5 MW at the location where the Race Bank wind farm is planned under the UK Round 2. This farm is planned 27 km from the North Norfolk coast at the Eastern part of England. The Race Bank farm is surrounded by several other wind farms which are either operational or under construction. The turbine which is selected for this farm is the reference turbine from the former EU project Upwind, since this turbine is described in detail in public literature and reflects the current state of the art wind turbine technology. The near future scenario assumes a 1 GW wind farm and is located at the Dogger Bank in the North Sea. It consists of 100 turbines with a rated power of 10 MW. Although 10 MW turbines are not on the market yet the INNWIND.EU reference wind turbine has been selected since a full description of this turbine is available. Moreover a far future scenario is defined which refers to a time line of some 15 year. It consists of large clusters (up to 10 GW) where some of the farms in the cluster are differently sized and contain floating turbines. The far future scenario includes several grid planning options, both for the export to the mainland as for interconnecting wind farms in the cluster. It even includes interconnections with other development zones or even to other countries, combining wind power export and cross-border electricity trade. The far future scenario is reported in D5.7. 5 | P a g e Deliverable 5.12 EERA DTOC calculation of scenarios 1. INTRODUCTION 1.1 Background In WP5.3 of the EERA-DTOC project the integrated offshore wind farm design tool as delivered from WP4 [2] is demonstrated for and by the industry on the basis of likely scenarios. The scenarios as described in this document are denoted as the ‘base and the near future scenario’, i.e. scenarios which are still relatively close to the present state of the art wind farm (clusters). This is in particular true for the base scenario which is described as a scenario which reflects ‘the current way of thinking’. The near future scenario goes beyond the current way of thinking by using upscaled turbines. The far future scenario has a time line in the order of 15 years. 1.2 Goal of scenarios and document It is important to realize that validation of the integrated design tool by means of measurements is still difficult to do on the scale of clusters because large wind farm clusters are in planning rather than in operation. Nevertheless the demonstration of the EERA-DTOC tool by means of likely scenarios enables a check on the industrial usefulness of the tool on basis of the user requirements as defined in the start-up phase of the project and reported in D4.1 [12]. These user stories, together with the global definition of the scenario formed the starting point of the present calculation. More specifically it should be shown that the tool is useful, easy to use, complete and robust. Moreover the ‘steepness’ of the learning curve will be determined and it will be checked which tutorials would have be added (e.g. simple case, videos?). Although a comparison with measurements cannot be made an expert view is carried out on the results in order to assess their degree of reality. An important requirement for the scenario calculation is that all EERA-DTOC main modules (i.e. the wind module, the wake module, the grid module, the energy yield module and the cost module) are activated. 1.3
Recommended publications
  • Appendix 6.1: List of Cumulative Projects
    Appendix 6.1 Long list of cumulative projects considered within the EIA Report GoBe Consultants Ltd. March 2018 List of Cumulative Appendix 6.1 Projects 1 Firth of Forth and Tay Offshore Wind Farms Inch Cape Offshore Wind (as described in the decision notices of Scottish Ministers dated 10th October 2014 and plans referred to therein and as proposed in the Scoping Report submitted to MS-LOT in May 2017) The consented project will consist of up to 110 wind turbines and generating up to 784 MW situated East of the Angus Coast in the outer Forth and Tay. It is being developed by Inch Cape Offshore Windfarm Ltd (ICOL). This project was consented in 2014, but was subject to Judicial Review proceedings (see section 1.4.1.1 of the EIA Report for full details) which resulted in significant delays. Subsequently ICOL requested a Scoping Opinion for a new application comprising of 75 turbines with a generating capacity of 784 MW. Project details can be accessed at: http://www.inchcapewind.com/home Seagreen Alpha and Bravo (as described in the decision notices of Scottish Ministers dated 10th October 2014 and plans referred to therein and as Proposed in the Scoping Report submitted to MS-LOT in May 2017) The consents for this project includes two offshore wind farms, being developed by Seagreen Wind Energy Limited (SWEL), each consisting of up to 75 wind turbines and generating up to 525 MW. This project was consented in 2014, but was subject to Judicial Review proceedings (see section 1.4.1.1 of the EIA Report for full details) which resulted in significant delays.
    [Show full text]
  • Lancashire Bird Report 2003
    Lancashire & Cheshire Fauna Society Publication No. 106 Lancashire Bird Report 2003 The Birds of Lancashire and North Merseyside S. J. White (Editor) W. C. Aspin, D. A. Bickerton, A. Bunting, S. Dunstan, C. Liggett, B. McCarthy, P. J. Marsh, D. J. Rigby, J. F. Wright 2 Lancashire Bird Report 2003 CONTENTS Introduction ........................................... Dave Bickerton & Steve White ........ 3 Review of the Year ............................................................. John Wright ...... 10 Systematic List Swans & Geese ........................................................ Charlie Liggett ...... 14 Ducks ....................................................................... Dominic Rigby ...... 22 Gamebirds ........................................................................ Bill Aspin ...... 37 Divers to Cormorants ................................................... Steve White ...... 40 Herons ................................................................. Stephen Dunstan ...... 46 Birds of Prey ........................................................ Stephen Dunstan ...... 49 Rails ................................................................................. Bill Aspin ...... 55 Oystercatcher to Plovers ............................................ Andy Bunting ...... 58 Knot to Woodcock .................................................... Charlie Liggett ...... 64 Godwits to Curlew ........................................................ Steve White ...... 70 Spotted Redshank to Phalaropes .......................
    [Show full text]
  • Integrated Offshore Networks: the Context of Our Work
    Developing offshore grids : An integrated approach Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Andrew Hiorns Integrated offshore networks: the context of our work Sustainability We are interested in establishing workable arrangements at the lowest costs for UK consumers such that: The potential deliverability of offshore wind is maximised Security of supply and network resilience are maximised The overall cost to consumers is minimised Affordability The scale of potential offshore a Offshore wind leased wind necessitates reflection on capacity* the delivery challenges: 1GW Security of supply 7GW European interconnection Technology development Security of 32GW supply Supply chain capability Planning consents Financing Round 1 Round 2 Round 3 Skills * Source: DECC website 2 http://www.decc.gov.uk/en/content/cms/what_we_do/uk_supply/energy_mix/renewable/policy/offshore/wind_leasing/wind_leasing.aspx 1 Assumptions: Generation mix scenarios 2008/09 TRANSMISSION SYSTEM AS AT 31st DECEMBER 2007 400kV Substations 275kV Substations Slow Progression 132kV Substations 400kV Circuits 275kV Circuits 132kV Circuits Major Generating Sites Including Pumped Storage Pentland Firth Connected at 400kV THE SHETLAND ISLANDS 6 Connected at 275kV 9,724MW offshore wind in 2020 Hydro Generation 23,174MW offshore wind in 2030 1 21% renewable electricity generation 2020 target missed 5 7 8 9 2 10 Gone Green 4 3 16,374MW offshore wind
    [Show full text]
  • G59 Generator Protection Settings - Progress on Changes to New Values (Information Received As at End of 2010 - Date of Latest Updates Shown for Each Network.)
    G59 Generator Protection Settings - Progress on Changes to new Values (Information received as at End of 2010 - Date of latest updates shown for each network.) DNO [Western Power Distribution - South West Area] total responses as at 05/01/11 User Data Entry Under Frequency Over Frequency Generator Generator Generator Changes Generator Stage 1 Stage 2 Stage 1 Stage 2 Agreed to capacity capacity capacity changes Site name Genset implemented capacity unable Frequency Frequency Frequency Frequency Comments changes (Y/N) installed agreed to implemented (Y/N) to change (MW) (Hz) (Hz) (Hz) (Hz) (MW) change (MW) (MW) Scottish and Southern Energy, Cantelo Nurseries, Bradon Farm, Isle Abbots, Taunton, Somerset Gas Y Y 9.7 9.7 9.7 0.0 47.00 50.50 Following Settings have been applied: 47.5Hz 20s, 47Hz 0.5s, 52Hz 0.5s Bears Down Wind Farm Ltd, Bears Down Wind Farm, St Mawgan, Newquay, Cornwall Wind_onshore Y N 9.6 9.6 0.0 0.0 47.00 50.50 Contact made. Awaiting info. Generator has agreed to apply the new single stage settings (i.e. 47.5Hz 0.5s and 51.5Hz 0.5s) - British Gas Transco, Severn Road, Avonmouth, Bristol Gas Y Y 5.5 5.5 5.5 0.0 47.00 50.50 complete 23/11/10 Cold Northcott Wind Farm Ltd, Cold Northcott, Launceston, Cornwall Wind_onshore Y Y 6.8 6.8 6.8 0.0 47.00 50.50 Changes completed. Generator has agreed to apply the new single stage settings (i.e. 47.5Hz 0.5s and 51.5Hz Connon Bridge Energy Ltd, Landfill Site, East Taphouse, Liskeard, Cornwall 0.5s).Abdul Sattar confirmed complete by email 19/11/10.
    [Show full text]
  • Wind Turbine Experiences Survey 2012
    Wind Turbine experiences 2012 survey results Introduction The Government’s commitment to renewable energy has meant a large increase in the number of wind farms and domestic turbines over the last few years. In 1995, in response to the Government seeking guidance, the BHS recommended that there should be a distance of at least 200m between a turbine and the nearest off-road equestrian route, which was supported by the Countryside Commission at the time. However, this was based on turbine heights of less than 60 metres and by 1998 there were already applications for turbines of 100m, so the BHS urged Government to revise its guidance to an appropriate formula of three times the height of the turbine with an absolute minimum of 200 metres. Although the three times height was accepted by the Countryside Agency, the Government’s guidance was not revised. The Agency went further and proposed that four times the height be recommended for national trails and promoted equestrian routes on the basis that these are likely to be used by horses unfamiliar with turbines. Government guidance up to July 2013 said: “The British Horse Society ... has suggested a 200 metre exclusion zone around bridle paths to avoid wind turbines frightening horses. Whilst this could be deemed desirable, it is not a statutory requirement ...”. In many cases, this separation distance was adopted as reasonable; however, the latest Government guidance does not specifically refer to horses and says: "Other than when dealing with set back distances for safety, distance of itself does not necessarily determine whether the impact of a proposal is unacceptable." The latest BHS guidance, revised as a result of this survey, gives a number of factors which increase the impact of wind turbines on equestrian access and which should increase the set back distance.
    [Show full text]
  • Learning from the Success of Offshore Wind in Grimsby
    Growing the UK’s coastal economy Learning from the success of offshore wind in Grimsby Growing the UK’s coastal economy © Green Alliance, 2015 Green Alliance’s work is licensed Learning from the success of offshore under a Creative Commons wind in Grimsby Attribution-Noncommercial-No derivative works 3.0 unported licence. This does not replace By William Andrews Tipper copyright but gives certain rights without having to ask Green Alliance for permission. The views expressed in this report are Under this licence, our work may Green Alliance’s own. be shared freely. This provides the freedom to copy, distribute and Green Alliance transmit this work on to others, provided Green Alliance is credited Green Alliance is a charity and independent think tank as the author and text is unaltered. focused on ambitious leadership for the environment. This work must not be resold or used We have a track record of over 35 years, working with the for commercial purposes. These conditions can be waived under most influential leaders from the NGO, business, and certain circumstances with the political communities. Our work generates new thinking written permission of Green Alliance. and dialogue, and has increased political action and For more information about this licence go to http:// support for environmental solutions in the UK. creativecommons.org/licenses/ by-nc-nd/3.0/ Acknowledgements With particular thanks to Chris Holden. Thanks also to the following for their contributions during the project: India Redrup, Mia Rafalowicz-Campbell, Nicola Wheeler, Emma Toulson, Gary Maddison, Andy Dixson, Duncan Clark, Tracey Townsend, Jon Beresford, Antony Innes, Leo Hambro, Waverly Ley, Jonathan Ellis, Tsveti Yordanova and Kurt Christensen.
    [Show full text]
  • Hornsea Project Three Offshore Wind Farm
    Hornsea Project Three Offshore Wind Farm Hornsea Project Three Offshore Wind Farm Funding Statement Annex 2 – Ørsted Annual Report PINS Document Reference: A4.1.2 APFP Regulation 5(2)(h) Date: May 2018 Compulsory Acquisition Funding Statement Annex 2 – Ørsted Annual Report May 2018 Compulsory Acquisition Funding Statement Annex 2 – Ørsted Annual Report Cover Letter to the Planning Inspectorate Report Number: A4.1.2 Version: Final Date: May 2018 This report is also downloadable from the Hornsea Project Three offshore wind farm website at: www.hornseaproject3.co.uk Ørsted 5 Howick Place, London, SW1P 1WG © Orsted (UK) Ltd, 2018. All rights reserved Front cover picture: Kite surfer near a UK offshore wind farm © Orsted Hornsea Project Three (UK) Ltd., 2018 i Compulsory Acquisition Funding Statement Annex 2 – Ørsted Annual Report May 2018 Prepared by: Oliver Palasmith Checked by: Richard Grist Accepted by: Sophie Banham Approved by: Stuart Livesey ii Ørsted Annual report 2017 Ørsted Annual report 2017 Contents The Ørsted Way Let’s create a world that runs entirely on green energy Climate change is one of the biggest challenges for life on Earth. Today, the world mainly runs on fossil fuels. We need to transform the way we power the world; from black to green energy. At Ørsted, our vision is a world that runs entirely on green energy. We want to revolutionise the way we power people by developing green, independent and economically viable energy systems. By doing so, we create value for the societies that we are a part of and for all our stakeholders. The way we work is based on five guiding principles: Integrity Results We are open and trustworthy We set the bar high, take ownership and uphold high ethical standards and get the right things done Passion Safety We are passionate about what We never compromise on health and safety we do and proud of what we achieve standards Team Integrity is our root.
    [Show full text]
  • Länderprofil Großbritannien Stand: Juli / 2013
    Länderprofil Großbritannien Stand: Juli / 2013 Impressum Herausgeber: Deutsche Energie-Agentur GmbH (dena) Regenerative Energien Chausseestraße 128a 10115 Berlin, Germany Telefon: + 49 (0)30 72 6165 - 600 Telefax: + 49 (0)30 72 6165 – 699 E-Mail: [email protected] [email protected] Internet: www.dena.de Die dena unterstützt im Rahmen der Exportinitiative Erneuerbare Energien des Bundesministeriums für Wirtschaft und Technologie (BMWi) deutsche Unternehmen der Erneuerbare-Energien-Branche bei der Auslandsmarkterschließung. Dieses Länderprofil liefert Informationen zur Energiesituation, zu energiepolitischen und wirtschaftlichen Rahmenbedingungen sowie Standort- und Geschäftsbedingungen für erneuerbare Energien im Überblick. Das Werk einschließlich aller seiner Teile ist urheberrechtlich geschützt. Jede Verwertung, die nicht ausdrücklich vom Urheberrechtsgesetz zugelassen ist, bedarf der vorherigen Zustimmung der dena. Sämtliche Inhalte wurden mit größtmöglicher Sorgfalt und nach bestem Wissen erstellt. Die dena übernimmt keine Gewähr für die Aktualität, Richtigkeit, Vollständigkeit oder Qualität der bereitgestellten Informationen. Für Schäden materieller oder immaterieller Art, die durch Nutzen oder Nichtnutzung der dargebotenen Informationen unmittelbar oder mittelbar verursacht werden, haftet die dena nicht, sofern ihr nicht nachweislich vorsätzliches oder grob fahrlässiges Verschulden zur Last gelegt werden kann. Offizielle Websites www.renewables-made-in-germany.com www.exportinitiative.de Länderprofil Großbritannien – Informationen für
    [Show full text]
  • Ex-Ante Cost Review of Race Bank Offshore Wind Farm Transmission Assets
    Ex-Ante Cost Review of Race Bank Offshore Wind Farm Transmission Assets Report of Grant Thornton UK LLP dated 23 April 2018 CONTENTS 1 Executive summary 1 2 Introduction and background 11 3 The ROW01 Ex-Ante Review 15 4 ROW01 processes 18 5 Costs common to the Transmission Assets as a whole 23 6 Project common costs and development costs 37 7 Offshore substation 54 8 Submarine cable supply and installation 65 9 Land cable supply and installation 79 10 Onshore substation connection 85 11 Reactive substation 94 12 Connection costs 97 13 Other costs 98 APPENDICES 1 Summary of cost movements and unsubstantiated costs 2 General development costs © Grant Thornton UK LLP. All rights reserved. Report of Grant Thornton UK LLP Strictly private and confidential – not for disclosure dated 23 April 2018 EX-ANTE COST REVIEW OF RACE BANK OFFSHORE WIND FARM TRANSMISSION ASSETS 1 1 EXECUTIVE SUMMARY 1.1 This report relates to the Race Bank Offshore Wind Farm (ROW01/ the Wind Farm) which is owned1 by DONG Energy A/S (DONG Energy) (50% shareholder) and Macquarie Corporate Holdings Pty Limited (25% shareholder) and Macquarie European Investment Fund 5 RB Holding (25% shareholder)2 (collectively the Developers). The Wind Farm is owned through the subsidiary Race Bank Wind Farm Limited and its development is being managed by DONG Energy. 1.2 Our review is based upon the Developers’ cost template submitted to Ofgem dated 17 March 2017 and incorporates information and explanations provided regarding the costs in this version of the cost template, both in our site visits and in correspondence with the Developer, up to 26 January 2018.
    [Show full text]
  • ABLE Marine Energy Park (AMEP) ABLE Humber Port, East Coast, UK Establishing a New Offshore Wind Cluster
    ABLE Marine Energy Park (AMEP) ABLE Humber Port, East Coast, UK Establishing a New Offshore Wind Cluster Information on AMEP to Support the Attraction of Offshore Wind Activity - 2021 Contents 3. Introduction 4. ABLE Marine Energy Park Aerial View 5. Location - Connectivity to Europe 6. Location - Road & Rail 7. Location - Proximity to Market 8. AMEP - The Offer 9. AMEP - Freeport Status 10. AMEP - Optimum Site Solutions 11. AMEP - Indicative Working Plan 12. AMEP - Offshore Wind Work Flow 13. Hornsea One Offshore Wind Farm 14. Triton Knoll Offshore Wind Farm 15. Dogger Bank Offshore Wind Farm 16. Planning - Fully Consented 17. Cost Reduction Opportunities 18. Wind Installation Vessels - Benefits 19. AMEP - Technical Specification 21. AMEP - Operating Model 22. AMEP - Competitive Advantage 23. Heavy Lift & Transport Services 24. The Humber Estuary Characteristics 25. Humber - Tees & Tyne Comparisons 27. Workforce - Productivity 28. Workforce - Availability 29. Production & Assembly - Workforce 31. Financial Support for Investment Document Reference: CM.NFE-AMEP-OSW-29 January 2021 Introduction ABLE Marine Energy Park (AMEP). Able Marine Energy Park (AMEP) is a port development on the south bank of the Humber Estuary on the East Coast of the United Kingdom. It is a nationally significant infrastructure project (NSIP) and is recognised as a core development within the UK Government Infrastructure Roadmap. The AMEP project base case involves developing Phase 1 with 1,349m of installation quays, 4no. installation yards (78.63 ha), with an additional 139 ha for manufacturer storage. It represents a singular opportunity for the UK to establish a world-scale industrial cluster and enable the UK to maximise the economic development potential provided by the combination of the emerging market and supportive policies.
    [Show full text]
  • Forecast from 2016-17 to 2019-20
    Tariff Information Paper Forecast TNUoS tariffs from 2016/17 to 2019/20 This information paper provides a forecast of Transmission Network Use of System (TNUoS) tariffs from 2016/17 to 2019/20. These tariffs apply to generators and suppliers. This annual publication is intended to show how tariffs may evolve over the next five years. The forecast tariffs for 2016/17 will be refined throughout the year. 28 January 2015 Version 1.0 1 Contents 1. Executive Summary....................................................................................4 2. Five Year Tariff Forecast Tables ...............................................................5 2.1 Generation Tariffs ................................................................................. 5 2.2 Onshore Local Circuit Tariffs ..............................................................10 2.3 Onshore Local Substation Tariffs .......................................................12 Any Questions? 2.4 Offshore Local Tariffs .........................................................................12 2.5 Demand Tariffs ...................................................................................13 Contact: 3. Key Drivers for Tariff Changes................................................................14 Mary Owen 3.1 CMP213 (Project TransmiT)...............................................................14 Stuart Boyle 3.2 HVDC Circuits.....................................................................................14 3.3 Contracted Generation .......................................................................15
    [Show full text]
  • Transmission Networks Connections Update
    Transmission Networks Connections Update May 2015 SHE-T–TO SPT–TO NG–TO/SO SHE-T–TO SPT–TO NG–TO/SO Back to Contents TNCU – May 2015 Page 01 Contents Foreword ////////////////////////////////////////////////////////////////// 02 1. Introduction /////////////////////////////////////////////////////////// 03 2. Connection timescales ///////////////////////////////////////////// 04 Illustrative connection timescales /////////////////////////////////////// 04 Connections by area /////////////////////////////////////////////////////// 05 3. GB projects by year ///////////////////////////////////////////////// 06 Contracted overall position /////////////////////////////////////////////// 08 Renewable projects status by year ///////////////////////////////////// 10 Non-Renewable projects status by year – Excluding Nuclear /// 11 Non-Renewable projects status by year – Nuclear only ////////// 12 Interconnector projects status by year //////////////////////////////// 13 4. Additional data by transmission owner ///////////////////////// 14 National Grid Electricity Transmission plc //////////////////////////// 16 Scottish Hydro Electricity Transmission plc ////////////////////////// 18 Scottish Power Transmission Limited ///////////////////////////////// 20 5. Connection locations /////////////////////////////////////////////// 22 Northern Scotland projects map //////////////////////////////////////// 25 Southern Scotland projects map /////////////////////////////////////// 28 Northern England projects map /////////////////////////////////////////
    [Show full text]