WATER RESOURCES COMMISSION,

DENSU RIVER BASIN -

Integrated Water Resources Management Plan

May 2007

Water Resources Commission Densu River Basin IWRM Plan

PREAMBLE

Right from the establishment of the Water Resources Commission (WRC) a priority task has been to introduce the basic principles of Integrated Water Resources Management (IWRM) at local level in selected river basins. The Densu River Basin was chosen as the first pilot area for various reasons such as rampant land and water quality degradation, and occasional water shortages in an otherwise perennial river system caused, among other factors, by the rapid population increase of the metropolitan area and other urban centres within the basin. The Densu River Basin is a classic case of an area in need of a basin-wide planning approach involving stakeholder participation, awareness raising, public meetings, capacity building and training, and environmental engineering. It is believed that this approach could lead to the sustainable implementation of effective measures to improve land use and watershed management, protection of buffer zones along the river banks as well as improved management of liquid and solid wastes from the towns and communities within the basin. Several activities have been invested over the past few years in creating a basin-based IWRM structure for the Densu River Basin. The decentralised IWRM structure, which has evolved through a targeted participatory and consultative process, combines the following partners: a broadly anchored stakeholder-oriented coordinating body, i.e. the Densu Basin Board, respective planning officers of the District Assemblies and WRC’s Densu Basin office in (serving as secretariat for the Board). In parallel to the organisational arrangements, activities of a more technical nature have been ongoing, which eventually resulted in the present Densu River Basin IWRM Plan. This plan should also be viewed as an integral part of the stipulations in the WRC Act 522 of 1996 to “propose comprehensive plans for utilisation, conservation, development and improvement of water resources” in adherence with the overall National Water Policy. The document constitutes the first version of the IWRM Plan. Inasmuch as IWRM is a cyclic and long-term process, the document can be seen as a milestone in this process, in which the status of the water resources situation is documented – a process that should be subject to continuation and updates as the need arises in the future. It is WRC’s sincere hope that this plan can be a useful catalyst towards accelerating concrete IWRM activities in the Densu Basin, and importantly – since it is the first of its kind in Ghana – also can serve as a source of inspiration to facilitate similar planning efforts in other vulnerable river basins in Ghana.

Prof. Clement Dorm-Adzobu Chairman, Water Resources Commission Accra, May 2007

May 2007 Page i Water Resources Commission Densu River Basin IWRM Plan

LIST OF CONTENTS

Page

Preamble ………………………………………………………………………………. i List of Contents ……………………………………………………………………….. ii List of Tables …………………………………….……………………………………. iv List of Figures and Maps ……………………………………………………………… v Abbreviations ………………………………………………………………………….. vi

1. INTRODUCTION …………………………….………………………………… 1 1.1 IWRM in an international context …………..……..………………………. 1 1.2 IWRM planning in the Ghanaian context ………..….…………………….. 2 1.3 Purpose and institutional setting of the IWRM plan ……………..……….. 3 1.4 Status of IWRM activities in the Densu River Basin …..………………….. 4 1.5 Preparation and structure of the IWRM plan …..………………………….. 6

2. BASELINE DESCRIPTION …………………………………………………… 7 2.1 Physical, demographic and socio-economic features ………………....…… 7 2.1.1 Location, topography and river network …………………………… 7 2.1.2 Administrative structure, population and settlement pattern ………. 7 2.1.3 Socio-economic profile …………………………………………….. 9 2.1.4 Land use pattern and ecological trends …………………………….. 11 2.1.5 Protected areas ……………………………………………………… 12 2.2 Water resources ………………………………………………………….…. 13 2.2.1 Meteorological characteristics and impact of climate change ……… 13 2.2.2 Surface water availability ……………………………..…………… 14 2.2.3 Groundwater resources ………………………………..…………… 18 2.3 Utilisation of water resources ……………………………………………… 20 2.3.1 General overview of water supply situation ………………..……… 20 2.3.2 Urban water supply ………………………………………….…….. 20 2.3.3 Rural water supply …………………………………………….…… 23 2.3.4 Water for agriculture ………………………………………….…… 23 2.3.5 Industrial water use …………………………………………….….. 25 2.3.6 Summary of water resources utilisation ………………………..….. 25 2.4 Water quality and pollution ……………………………………………..… 26 2.4.1 Water quality monitoring ………………………………………….. 26 2.4.2 Surface water quality ……………………………………………… 26 2.4.3 Groundwater quality ………………………………………………. 30 2.4.4 Sources of pollution and sanitary condition …………….…….…… 31 2.4.5 Trends in pollution load ……………………………………….…… 32

3. WATER DEMAND PROJECTIONS AND WATER AVAILABILITY…..… 38 3.1 Demographic and social-economic development trends ……………….….. 38 3.1.1 Assumptions for projection of potable water demand ……….…….. 38 3.1.2 Assumptions for projection of agricultural/industrial water demand. 40 3.2 Water demand projections ………………………………………….…….... 41

May 2007 Page ii Water Resources Commission Densu River Basin IWRM Plan

3.3 Water balance assessment for whole basin as one unit ….…….……..……. 42 3.4 Scenario analyses of water availability vs. requirements at demand sites .... 43 3.4.1 Introduction to scenario analyses and model assumptions ……..…... 43 3.4.2 Results from the scenario analysis ………………….…..……….…. 46 3.4.3 Overall assessment based on the scenario analyses ………………… 53

4. CONSULTATIVE PROCESS …………………………………………………. 57 4.1 SEA applied in the IWRM planning process …………………………….... 57 4.2 IWRM issues and problems as identified by stakeholders ……..……..…… 58 4.3 Existing legal and institutional framework …………………..………..…… 61 4.4 Prioritisation of problems and delegation of responsibilities ……………… 68

5. ACTION PROGRAMME ……………………………………..……………….. 71 5.1 Introduction ……………………………………………………………….... 71 5.2 Actions identified to address the IWRM problems .……………..…………. 71 5.3 Prioritisation of actions ……………………………………………………… 78 5.3.1 Actions included in first phase implementation …………………….. 78 5.3.2 Sustainability test of IWRM plan …………………………………… 81 5.4 Towards implementation of the action programme…………………………. 81 5.4.1 Way forward ………………………………………………………… 81 5.4.2 Monitoring and regular reviews of the plan ……….………………… 83

May 2007 Page iii Water Resources Commission Densu River Basin IWRM Plan

LIST OF TABLES

Page TABLES Table 2.1: Population in the Densu River Basin (2000 Census) ………………….…. 9 Table 2.2: Occupation (in %) of the economically active population ……………….. 11 Table 2.3: Development in land use/cover of the Densu basin (1990-2000) ………… 12 Table 2.4: Mean monthly rainfall (mm), (1950-2005) ………………..…… 13 Table 2.5: Annual water balance for Densu Basin …………………………….…..… 15 Table 2.6: Mean annual flow volume, Densu River system …………………………. 15 Table 2.7: Densu River mean monthly flow (1970-2000), Nsawam (m 3/s) ………….. 16 Table 2.8: Borehole characteristics in Densu Basin ………………………………….. 19 Table 2.9: Main source of drinking water (in % of households) ……………..……… 20 Table 2.10: Piped water supply schemes in the Densu basin (2005) …………….……. 21 Table 2.11: Water resources utilisation (2005), Densu Basin …………………..…….. 25 Table 2.12: Criteria for classification of surface waters ……………………………….. 27 Table 2.13: Calculation of WQI at 4 monitoring sites, Densu River (2005-2006) .….... 28 Table 3.1: Unit water demand (litres/capita/day) …………………………………….. 38 Table 3.2: Population projections per part of districts within Densu Basin (2005-20) . 40 Table 3.3: Water demand projections, Densu Basin (2005-2020) ……………..…….. 41 Table 3.4: 2020 projected water demand at surface water abstraction points …....….. 45 Table 3.5: Coverage rate, existing situation (Scenarios 1 and 2) …………………….. 49 Table 3.6: Coverage rate, impact of climate change (Scenario 3) ……………………. 50 Table 3.7: Coverage rate, response to changes in system losses (Scenario 4) ………... 50 Table 3.8: Coverage rate, Densu and Volta Lake prioritisation (Scenario 5) ………… 51 Table 3.9: Coverage rate, alternative options (Scenarios 6 and 7) ……………………. 53 Table 4.1: Ranking of IWRM problems as formulated at initial stakeholder workshop. 59 Table 4.2: Main categories of identified problems …………………………………… 60 Table 4.3: Existing regulatory framework and institutional responsibilities in IWRM.. 62 Table 4.4: Result of tool application to identify delegation of responsibilities ……..… 69 Table 4.5: Prioritisation of water management problems …………………………….. 70 Table 5.1: Proposed actions for addressing identified IWRM issues/problems .……… 73 Table 5.2: Prioritised list of proposed actions/measures ……………….….………….. 78

May 2007 Page iv Water Resources Commission Densu River Basin IWRM Plan

LIST OF FIGURES AND MAPS

Page FIGURES Figure 1.1: Institutional framework for IWRM planning ……………………………... 4 Figure 2.1: Densu River annual runoff (1970-2000), Nsawam (in million m 3) ……….. 17 Figure 2.2: Densu River daily flows (2005), Pakro gauging station (in m 3/sec) ……..... 17 Figure 2.3: Improvement of water quality in the Densu Basin ………………………… 29

MAPS Map 2.1: Topography of the Densu Basin …………………………………………… 33 Map 2.2: Administrative districts and settlements in the Densu Basin ……………… 34 Map 2.3: Land use/cover (2000) of the Densu Basin ………………………………… 35 Map 2.4: River network, hydrological and rainfall stations, Densu Basin ………….. 36 Map 2.5: Geological map of Densu Basin …………………………………………… 37 Map 3.1: Schematic overview of main elements in Densu WEAP model ………...… 56

May 2007 Page v Water Resources Commission Densu River Basin IWRM Plan

ABBREVIATIONS

CBO Community-Based Organisation CWSA Community Water and Sanitation Agency DA District Assembly DBB Densu Basin Board EPA Environmental Protection Agency GES Ghana Education Service GMA Ghana Meteorological Agency GoG Government of Ghana GPRS Ghana Poverty Reduction Strategy GWCL Ghana Water Company Limited GWP Global Water Partnership ha hectare HSD Hydrological Services Department IDA Irrigation Development Authority IWRM Integrated Water Resources Management l/c/d litre per capita per day LI legislative instrument (regulations) mm millimetre m3/s cubic metre per second MDA ministries/departments/agencies MDG Millennium Development Goals MOFEP Ministry of Finance and Economic Planning MOFA Ministry of Food and Agriculture MWRWH Ministry of Water Resources, Works and Housing NDPC National Development Planning Commission NGO Non-Governmental Organisation p.a. per annum PURC Public Utilities Regulatory Commission SEA Strategic Environmental Assessment UN-Habitat United Nations Centre for Human Settlements VRA Volta River Authority WEAP Water evaluation and planning computer-based model application WRC Water Resources Commission WRI CSIR-Water Research Institute WSSD World Summit on Sustainable Development (August 2002) WQI Water Quality Index

May 2007 Page vi Water Resources Commission Densu River Basin IWRM Plan

1. INTRODUCTION

1.1 IWRM in an international context

At the World Summit on Sustainable Development (WSSD) held in Johannesburg in 2002, the international community took an important step towards more sustainable patterns of water management by including, in the WSSD Plan of Implementation, a call for all countries to “ develop integrated water resources management and water efficiency plans ”. The “ water efficiency plan ” is considered as an important compo- nent of IWRM, and hence as an integral part of an IWRM plan.

The term integrated water resources management (IWRM) has been subject to vari- ous interpretations, but the following definition by the Global Water Partnership 1 has been adopted in the Ghanaian context: “... a process which promotes the coordinated development and manage- ment of water, land and related resources in order to maximise economic and social welfare in an equitable manner without compromising the sus- tainability of vital ecosystems …” Due to competing demands for the water resource (in the worst case resulting in lim- iting economic development, decreasing food production, or basic environment and human health and hygiene services), the process is intended to facilitate broad stake- holder input in order to build compromise and equitable access. This is particularly the case for developing countries like Ghana, which allocates much effort in address- ing poverty reduction and in implementing the UN Millennium Development Goals.

IWRM is a comprehensive approach to the development and management of water, addressing its management both as a resource and within the framework of providing water services.

The Global Water Partnership models the IWRM process as a cycle of the following activities: • establishing the status and overall goals; • building commitment to the reform process; • analysing gaps; • preparing a strategy and action plan; • improving the legal and institutional management framework; and • monitoring and evaluating progress.

The goal of preparing IWRM plans as called for at the WSSD has set the tone for a world wide initiative, which Ghana has adopted with the purpose “to promote an ef-

1 Global Water Partnership (GWP): Integrated Water Resources Management, Technical Advisory Committee, TEC Background Paper No. 4 (2000)

May 2007 Page 1 Water Resources Commission Densu River Basin IWRM Plan

ficient and effective management system and environmentally sound development of all its water resources” 2 based on IWRM principles.

1.2 IWRM planning in the Ghanaian context

In Ghana, IWRM plans are thought initially to be prepared at the river basin level starting with the most “water stressed” basins of the country. At a later stage, this ex- ercise can provide input to preparation of an IWRM strategy/plan at national level incorporating trans-boundary water resource related issues. The IWRM plans and strategies shall be prepared with the overall purpose of addressing major problems at a river basin level related to: • water resource availability; • water quality; and • environmental/ecosystem sustainability.

Due account shall be taken to water use, and the social and economic implications of implementing an IWRM plan. Actions to be taken as a consequence of planning shall be prepared based on scenarios describing different approaches for solving major management problems (that might be described with natural resources, sociologi- cal/cultural, economic and regulatory, administrative and institutional indicators) within a defined time period.

As such most of the outputs to be provided are prioritised and ranked sets of pro- grammes/actions that from a political, legal, technical, sociological and economic point of view are considered as the most sustainable and efficient solutions. Political (democratic) aspects of IWRM planning in this regard require, that plans shall be elaborated with a participatory approach guided by principles which are imbedded in the concept of Strategic Environmental Assessment (SEA).

Generally, SEA is applied with two purposes: • to evaluate environmental impacts and to rank the environmental effects of plans and programmes; and • to evaluate conformity and/or conflicting stipulations between various related plans and programmes.

SEA tools have in Ghana been applied during formulation of the National Water Pol- icy and in assessing the first Ghana Poverty Reduction Strategy. As a continuation of these approaches, a SEA Practical Guide 3 has been prepared, which presents a num- ber of SEA tools applicable to the water and sanitation sector, including water re- source planning, development and management.

Key aspects, therefore, in the IWRM-SEA process is a participatory approach involving users, planners and policy makers to build commitment; a holistic view

2 Ghana National Water Policy (final draft, August 2005). 3 SEA of Water and Environmental Sanitation – a Practical Guide. Ministry of Water Resources, Works and Housing; Ministry of Local Government, Rural Development and Environment; and Environmental Protection Agency (final draft, October 2006).

May 2007 Page 2 Water Resources Commission Densu River Basin IWRM Plan

that calls for cross-cutting interaction within basins; an integration in terms of upstream-downstream catchment implications; and recognition to the fact that water is an economic good.

As part of a process, the basin-based IWRM plan shall form a widely accepted and easily understood document describing the current state of the water resources and outlining strategies that enable basin-specific management to adhere to the stipulations given in the National Water Policy. Thus, the IWRM plan should be considered a “blueprint”, that describes steps to be taken towards realising the visions.

1.3 Purpose and institutional setting of the IWRM plan

The target group of the basin-based IWRM plans is planners and decision-makers operating in the water sector, including the river basin boards, who are provided with a tool for “what to do” and for detailing activities and programmes concerning specific interventions. More specifically, the purpose of the IWRM plan is to: • contribute to the provision of sufficient supply of good quality surface water and groundwater as needed for sustainable, balanced and equitable water use; • prevent further deterioration and protect the status of aquatic ecosystems with regard to their water needs; • protect terrestrial ecosystems directly depending on the aquatic ecosystems; • contribute to mitigating the effects of floods and droughts; and • provide appropriate water management with efficient and transparent govern- ance in the sector whether at local, district or basin-based level.

IWRM is a cyclic and long-term process. Hence, the IWRM plan can be seen as a milestone in this process, where the status of the process is documented, and the plan inevitably will need to be kept up-to-date when new knowledge surfaces, e.g. related to changes in the hydrological regime and projections of future water requirements.

For the IWRM plan to be successfully implemented, it is imparative that the WRC collaborates with institutions affected by the plan. This is because the plan impacts on a variety of societal aspects, viz. utilisation and protection of natural resources, social and cultural situations, economics and production, and the legal, administrative and institutional frameworks. It is evident that there must be effective collaboration with planning efforts in these areas.

For instance, WRC has to collaborate with – • MDAs, CWSA and GWCL in water demand projections; • MDAs, Lands Commission, Minerals Commission, EPA, MOFA and traditional authorities in catchment management; • MDAs and EPA in controlling various wastes into water bodies; and • EPA, Forestry Commission, Fisheries Department, Water Research Institute and HSD in assessing environmental flow requirements.

The overall institutional setting as it relates to the further planning and implementation of the activities outlined in the IWRM plan is depicted in Figure 1.1.

May 2007 Page 3 Water Resources Commission Densu River Basin IWRM Plan

Figure 1.1: Institutional framework for IWRM planning

• INDUSTRIAL WATER • DRINKING WATER • PLANNING REGUL. WATER USERS • IRRIGATION • CATCHMENT MGT WATER • TARIFF REGUL. HOUSEHOLDS, INDUSTRIES, FARMERS, • HYDROPOWER • ETC. FISHERIES, SCHOOLS, HOSPITALS, • NAVIGATION OTHER MDAs • RECREATION • FLOOD CONTROL • NATURE REGULATORY & DISTRICT ASSEMBLIES • ETC. INFORMATION BODIES DEVELOPMENT PLANNING • NDPC OWNERSHIP OF WATER RESOURCES • EPA • LANDS COMMISSION GOODS, WORKS • MINERALS COMMSS. AND SERVICES • FISHERIES COMMSS. PROVISION • PURC WRC - DENSU BA SIN BOARD • PUBLIC (GWCL, • TOWN AND COUNTRY IWRM PLANNING, GRANT OF WATER CWSA, VRA, PLANNING. PERMITS, CATCHMENT MGT, ETC. IDA, MOFA) • GHANA METEORO- • PRIVATE LOGICAL AGENCY • NGOs • HYDROLOGICAL SER- • CONSULTANTS VICES DEPARTMENT • CONTRACTORS • WATER RESEARCH • ETC. INSTITUTE MWRWH –WATER DIRECTORATE • ETC. POLICY FORMULATION, CO-ORDINATION, MONITORING AND EVALUATION

MINISTRY OF FINANCE AND DEV ELOPMENT ECONOMIC PLANNING PARTNERS LOANS & GRANTS

PARLIAMENT

1.4 Status of IWRM activities in the Densu River Basin

For quite many years Ghana has been planning for and engaged in the introduction of IWRM at various levels of society, and as such has advanced in the IWRM process resulting in a new national water policy and legislation facilitating water resources management and development based on IWRM principles. Furthermore, an enabling institutional framework has been introduced at national level, i.e. establishment of the Water Resources Commission (WRC) and the Water Directorate under the Ministry of Water Resources, Works and Housing, and at local river basin level in the form of creation of river basin boards.

The Densu Basin Board (DBB) was the first created and officially inaugurated in March 2004. DBB has a consultative and advisory role as it relates to the

May 2007 Page 4 Water Resources Commission Densu River Basin IWRM Plan

management of the the Densu Basin’s water resources and represents a wide sphere of interest groups within the Basin, including the traditional authorities. Its work is facilitated by a secretariat as a decentralised entity of the WRC. The DBB membership combines the following:

(a) A chairperson appointed by the WRC, (b) A representative of the WRC, (c) One person representing each of the following within the basin. − East Akim District Assembly − Suhum/Kraboa/Coaltar District Assembly − New Municipal Assembly − Ga West District Assembly − Akwapim South District Assembly − Eastern Regional Coordinating Council − Greater Accra Regional Coordinating Council − Ministry of Health − Ministry of Food and Agriculture − Ministry of Women and Children’s Affairs − Environmental Protection Agency − Ghana Water Company Limited − Forestry Commission − National Commission on Culture − Orthodox Church − Prominent Chief within the basin − Non-Governmental Organisations (d) The Basin Officer as ex-officio member appointed by the WRC in charge of the Board’s Secretariat.

Over the past few years quite many specifically targeted studies and related activities have been completed aimed at providing data and new information of relevance for the IWRM planning. In the following chapter “Baseline Description” these various sources of information and reports are acknowledged as and when used.

Furthermore, in the Densu Basin a number of IWRM activities have also been initiated by the Densu Basin Board and WRC as well as NGOs and other partners, all with the purpose of addressing the reduced water availability and the water quality degradation facing the Basin. Some of these activities are: • Holding of four Board meetings annually for the formulation of strategies to en- hance coordination of the management and utilisation of the water resources of the basin; • Organisation of sub-committee meetings of the Densu Basin Board to draw-up and review work programmes for implementation; • Promotion and support for target groups’ awareness creation and education within the basin (in communities and schools) and development of educational materials;

May 2007 Page 5 Water Resources Commission Densu River Basin IWRM Plan

• Collaboration with agencies/organisations and communities working towards the recovery of the ecological health of the Basin, including activities such as tree- planting, clean-up exercises, river channel clearance and river bank protection; • Identification of raw water users (to assist in the process of registering and grant- ing water rights/issuance of permits); • Establishment of links with the Basin’s District Assemblies, traditional authori- ties/landowners to tackle specific issues relating to pollution and degradation of the catchment area, e.g. relocation of waste dump sites away from the river banks; • Preparation of a “buffer” zone policy; and • Provision of information services for students during preparation of their special studies and theses works, consultants, NGOs, CBOs and concerned individuals.

1.5 Preparation and structure of the IWRM plan

The WRC has elaborated the present IWRM plan for the Densu River Basin as part of WRC’s mandate to “propose comprehensive plans for utilisation, conservation, development and improvement of water resources” 4 with due consideration to stipu- lations in the National Water Policy.

The IWRM plan is based on a number of dedicated assessment studies and informa- tion reviews all unveiling implications relevant for decisions made during the process of prioritising measures forming the IWRM plan. Guided by the newly introduced SEA procedures, consultative meetings and workshops have taken place during the course of preparation, specifically targeting the Densu Basin Board members, and District Assemblies and their planning officers.

Following the present introductory chapter, Chapter 2 presents the baseline descrip- tion, which provides the background against which the planning and identification of actions can be made. In Chapter 3 water demand projections are presented based on district development plans and other information notably the 2000 census results. Furthermore, in this chapter a number of scenario analyses are presented comprising different development options and strategies for the utilisation of the basin’s water resources.

Chapter 4 describes the process followed towards identification and ranking of water resource management problems and issues as perceived by local stakeholders and planners of the basin, and documents the result of the SEA consultations. The final Chapter 5 concludes the IWRM planning process by presenting an action plan com- prising of a number of prioritised activities and measures for implementation re- quired to meet the IWRM challenges of the Densu River Basin.

4 Water Resources Commission (WRC) Act No. 522 of 1996

May 2007 Page 6 Water Resources Commission Densu River Basin IWRM Plan

2. BASELINE DESCRIPTION

2.1 Physical, demographic and socio-economic features

The Densu River traverses a highly densely populated part of Ghana and it is one of the most exploited rivers in the country considering its size. The basin is character- ised by an accelerating land and water quality degradation, and is marked by occa- sional water shortages in an otherwise perennial river system caused, among other factors, by the rapid population increase due to proximity to the Accra metropolitan area.

2.1.1 Location, topography and river network The Densu River Basin is located between latitude 5°30’N - 6°17’N and longitude 0°10’W - 0°37’W. The basin is bounded to the east and north by the Odaw and Volta basins, respectively. The boundary to the northwest is shared with the Birim basin and to the west with the Ayensu and Okrudu basins.

The topography of the Basin is diversified. The Basin is characterised by steeply dis- sected landscapes with hilly and rolling lands to the north, and flat coastal plains to the south with slopes and erosion surfaces that vary from 30% in the upper sections of the basin to less than 2% at the coast. The Basin is bordered to the east by the Akwapim hills and the Kwahu- scarps. The highest part of the basin reaches about 750 m above sea level and occurs along the north-western basin boundary. The topography of the Basin is depicted in Map 2.1 (inserted at the end of chapter).

The Densu River belongs to the Coastal River System group and the basin encom- passes an area of about 2,600 km 2. The river takes its source from the Atewa range and flows from its upstream sections in an easterly direction towards the Akwadum - Koforidua area, from where the river gradually changes its course and flows in a southerly direction into the Weija reservoir - one of the two main sources of water supply for the Accra metropolitan area. When the Weija reservoir is full excess flow discharges into the Densu delta (Sakumo) lagoon and salt pans complex, which con- stitutes one of Ghana’s internationally recognised protected areas (Ramsar sites), be- fore discharging into the Bay of Guinea (Atlantic Ocean) some 10 km west of Accra. The total length of the Densu river is about 120 km, and its main tributaries are the Pompon, Kuia, Adaiso, Dobro and Nsaki rivers. The river network is shown on Map 2.4 (inserted at the end of chapter).

2.1.2 Administrative structure, population and settlement pattern The administrative fabric of the relatively small Densu River Basin can be character- ised as rather complex in the sense that 3 administrative regions and 13 districts are represented within the basin, including part of the Accra metropolitan area. Ap- proximately 72% of the basin (the northern portion) lies within the ,

May 2007 Page 7 Water Resources Commission Densu River Basin IWRM Plan

23 % within the and the remaining 5% within the Central Re- gion. Among the 13 administrative districts, the portions of the five districts of East Akim, New Juabeng, Suhum/Kraboa/Coaltar, Akwapim South and Ga West consti- tute together close to 85% of the basin area. Contrary, the portions of Fanteakwa, Yilo Krobo and Kwaebibirem districts in the north of the basin constitute only about 1% of the basin area. Likewise, only a small part of the Ga East district is located within the basin boundary. These features are depicted in Map 2.2 (inserted at the end of chapter) with figures given in Table 2.1 below.

Applying the 2000 Census 5 results, the population size within the Densu River Basin is shown in Table 2.1 listed for each district and in accordance with the settlement classification, i.e. whether people live in rural or urban settings. Per definition, the urban population combines all settlements larger than 5,000 people. The portion of a district’s rural population living within the Basin is estimated by matching the pro- portion of the area of the respective district, which is located in the Basin, and using this percentage to calculate the rural population. The population density is also indi- cated in Table 2.1.

The population increases recorded in the latest inter-censal period (i.e. between the censuses of 1984 and 2000) show not surprisingly heavy growth rates in the areas of the Basin close to the Accra metropolis, i.e. the Ga West and Ga East districts as well as the Accra Metro area itself. Generally, in these areas annual growth rates of close to 10% have been recorded. This characteristic is also evident from the settlement pattern (split between rural and urban population) as well as the population density figures given in Table 2.1.

Internal migration is the most important determinant of this marked population growth in these parts of the Densu Basin. As the localities are becoming relatively attractive for migrants, new waves of migrants are likely to gravitate to the localities to swell up the existing population. The driving force behind this vibrant develop- ment is the urban sprawl phenomenon of Accra. This “urbanisation” trend is ex- pected to continue unabated in the foreseeable future, and hence, will gradually af- fect larger and larger areas in the Basin, particularly of the Ga West District.

As an average for the entire Densu Basin, the population density (year 2000) is 387 pop/km 2, five times bigger than the national average of 77 pop/km 2. The location of a number of the major settlements/towns within the Basin is also indicated on Map 2.2.

5 Ghana Statistical Service: 2000 Population and Housing Census (official results on DC-ROM, January 2002)

May 2007 Page 8 Water Resources Commission Densu River Basin IWRM Plan

Table 2.1: Population in the Densu River Basin (2000 Census) Settlement Population Area in basin Density Region District category (2000) (km 2) (%) (pop/km 2) rural 800 Fanteakwa 10 0.4 80 urban 0 rural 1,200 Yilo Krobo 18 0.7 67 urban 0 rural 27,500 East Akim 334 12.8 223 urban 47,000 rural ~ 0 Kwaebibirem 2 0.1 - urban 0 rural 22,000 Eastern New Juabeng 209 8.0 651 urban 114,100 Suhum/ rural 101,700 763 29.3 174 Kraboa/Coaltar urban 31,000 rural 19,700 Akwapim North 146 5.6 169 urban 5,000 rural 53,100 Akwapim South 322 12.4 298 urban 43,000 rural 10,500 West Akim 88 3.4 212 urban 8,200 rural 125,500 Ga West 546 21.0 854 urban 341,100 Greater rural 2,300 Ga East 10 0.4 870 Accra urban 6,400 rural 2,100 Accra Metro 30 1.2 927 urban 25,700 Awutu/ rural 8,800 Central 122 4.7 154 Efutu/Senya urban 10,000 rural 375,200 Densu Basin, total 2,600 100.0 387 urban 631,500

2.1.3 Socio-economic profile 6 The water resources of the Densu Basin contribute substantially to the economic livelihood of the people living in the basin. Water is used for a variety of purposes in the domestic, agriculture and industrial sectors.

Agriculture is the main economic activity in the rural areas and it provides employ- ment for majority of the people. The agricultural activities are practiced both com- mercially and as subsistence farming which together provide the food needs and fi- nancial income of the people. The impact of agriculture activities on the natural re- sources (land and water) can be attributed to the system of farming adopted by the

6 Water Resources Commission: Identification of Major Trends in the Socio-economic Development in the Densu Basin of relevance for Integrated Water Resources Management. ISSER (February 2003)

May 2007 Page 9 Water Resources Commission Densu River Basin IWRM Plan

farmers. Majority of the farmers practice the traditional bush fallowing with its at- tendant slash-and-burn method, which contributes significantly to deforestation in the basin. The cultivation of crops along the river bank is a common practice, which results in the removal of the top soil and exposes the land to erosion.

Irrigation systems in the Densu Basin can be found in the Weija, Mangoase, Suhum, Koforidua and Nsawam localities. The Weija irrigation system – although not opera- tional at present – supplies water primarily for the cultivation of vegetables. The Nsawam irrigation scheme abstracts water from the Dobro tributary for the cultiva- tion of ornamental flowers. There are also a number of individual small scale irriga- tion systems either from groundwater or surface water sources for growing of vege- tables and other crops.

Logging which was originally predominant in the northern part of the basin is once again being pursued in the basin with a number of timber concessions being granted by the Forestry Commission to larger timber operators. Harvesting of fuel wood has also become an important economic activity, particularly for the rural residents within the basin.

Fishing activities are practiced in the basin especially in the upper reaches of the river system, but also in the southern section. Apart from the traditional methods of draw-net and hook-and-line fishing, some fishermen use illegal methods such as chemicals and explosives with adverse effects on the water quality.

Small-scale gold mining activities and stone quarrying are also common in some parts of the Basin. The mining activities are restricted to the Birimian formation in the East Akim district, whereas the stone quarrying and sand winning activities are carried out especially in Koforidua, Nsawam and many localities in the .

In the urban areas, the economic activities are more diversified and the prominent occupations include wholesale and retail trading, manufacturing and other commer- cial activities. The major industries in the basin are mainly fruit processing and bottle water production industries. The small scale industries include auto servicing shops, saw milling, carpentry, block making, local soap manufacturing, black-smithing and metal work. In addition, there are large commercial shops where manufactured goods are sold, and large markets which form points of contact between rural and urban residents.

The above outlined socio-economic pattern with its noticeable differences between rural and urban settings is highlighted in Table 2.2. The figures in the table are de- rived from the 2000 Census data, and are given as percentages of the economically active population (above 15 years of age).

The employment situation generally in the basin is such that about 25% are unem- ployed, 60% are self-employed and 15% are in full-time formal employment. People who work on their own farms are considered self-employed. This also shows that the majority of the economically active part of the population is in the informal sector.

May 2007 Page 10 Water Resources Commission Densu River Basin IWRM Plan

Table 2.2: Occupation (in %) of the economically active population (1)

Economic District New Suhum Akwa- Akwa- Awutu Ga activity East West Accra Jua- Kraboa pim pim Efutu East/ (industry) Akim Akim Metro beng Coaltar North South Senya West Agriculture 57.7 15.9 59.9 50.1 46.9 59.8 36.8 13.9 3.7 and forestry Fishing 0.9 1.4 0.8 0.3 2.1 1.2 10.5 1.9 2.5 Mining and 1.1 0.7 0.4 0.5 1.4 1.2 0.9 1.9 1.4 quarrying Manufacturing 8.8 15.2 10.6 9.3 10.5 8.8 13.6 14.9 17.4 Wholesale and 11.5 28.6 13.4 16.7 17.1 13.6 16.0 27.2 33.9 retail sale Construction 2.6 6.0 1.7 3.0 2.7 1.4 4.4 10.1 5.5 Hotel and 2.8 4.0 2.8 2.9 3.5 2.7 2.4 3.5 4.6 restaurants Transport and 2.2 5.3 2.6 3.6 3.7 2.5 3.8 6.8 6.6 communication Education 4.3 6.8 3.1 4.9 4.2 3.0 3.7 8.0 8.0 Other (unspeci- 8.1 16.1 4.7 8.7 7.9 5.8 7.9 11.8 16.4 fied) activity 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 (1) Only districts with a sizeable population within the basin are included in this table

2.1.4 Land use pattern and ecological trends The original ecology of the Densu Basin was moist semi-deciduous forest with thick undergrowth featuring rich flora and fauna. The human activities through time, how- ever, have greatly modified this forest ecology – and at an accelerating rate. Within the past 10-20 years, the ecological perspective of the Densu Basin has changed dramatically. The thinning of the forest has intensified, and at the same time the marked shift in land use caused by the “urbanisation” in the eastern corridor of the basin from Weija area through Nsawam to Koforidua has its ecological impacts.

At present the Densu Basin is characterized by three different types of vegetation zones. The north-eastern section of the basin is forested land, but with intensive de- vegetation activities ongoing to allow agricultural activities to take hold. In this zone, cocoa farming was predominant until recently when the swollen shoot disease caused land use evolution in the forested area. Cocoa farming has now been replaced by ex- tensive bush fallow food cropping. The main food crops that are cultivated here in- clude plantain, cassava, yam, cocoyam and cereals such as maize. Large estate and peasant-scale oil palm plantations have also become important in the recent past, which also contribute to deforestation in the Basin.

The traditional forest zone in large part of the Basin’s middle sections are gradually giving way for areas - the second zone - characterised by scattered trees developing into areas of shrub and grassland. These parts of the Basin are characterized by ex- tensive cultivation of cassava, maize, pineapple and vegetables, and host much live- stock grazing. The coastal savannah zone in the extreme southern section of the basin makes up the third vegetation zone.

May 2007 Page 11 Water Resources Commission Densu River Basin IWRM Plan

From various perspectives, the Densu Basin and its water resources are under siege. The main determinants of this situation are the arable food crop farming and logging in the upstream reaches of the Basin, arable food crops and pineapple farming in the midstream sections of the Basin, and sand winning and stone quarrying in the down- stream areas caused by the urbanisation phenomenon emanating from Accra.

Map 2.3 (inserted at the end of chapter) provides a simplified overview of the land use/cover situation as derived from satellite image maps produced in year 2000. From similar image maps representing year 1990, Table 2.3 summarises the devel- opment in area coverage of the forested land and other zones described above as it has occurred during this ten-year period.

Table 2.3: Development in land use/cover of the Densu Basin (1990-2000) Semi-forested area, Forested area Settlements and Year scattered trees and (dense tree cover) build-up (bare) areas shrub/grassland 1990 40% 50% 10%

2000 20% 65% 15%

2.1.5 Protected areas Forest reserves Protected areas in the basin include two forest reserves located in the East Akim dis- trict, and two small reserves in the Fanteakwa and Yilo Krobo districts. The largest of these reserves is the Atewa Range Reserve, which provides the headwaters (the source) of the main branch of the Densu River. The forest reserves are also indicated on Map 2.3.

Densu delta Ramsar site The Densu delta and salt pans complex - also known as the Sakumo I Lagoon and Panbros Salt Pans - constitutes one of Ghana’s internationally declared protected wetland areas (Ramsar site). It is recognised for its role as a sanctuary for migrating seashore bird species utilising the lagoon as roosting and nesting grounds. The Densu delta Ramsar site covers an area of around 50 km 2 and comprises the salt pans, sand dunes, the flood plains and lowest part of the Densu river catchment south of the Ac- cra- road.

Protection activities in the area are undertaken by the Wildlife Division of the Forestry Commission, in close consultation with Panbros Salt Company, who owns part of the Ramsar site. In the Ramsar declaration it is stated that existing land use could be al- lowed to continue, but future developments were to be strictly assessed in terms of their compatibility with the Ramsar concept. At that time it was further recommended that the catchment area of the Densu River immediately north of the Accra-Winneba road, including the Weija dam and reservoir area, should be demarcated as a Land Use Management Zone, which, however, never materialised.

May 2007 Page 12 Water Resources Commission Densu River Basin IWRM Plan

The water regime of the Densu delta, as determined by the operational strategy of the Ghana Water Company Limited (GWCL) in managing the Weija Water Works, can be a source of conflict between the GWCL, the owners of the salt industry and the fishing communities. As it is, the flow of water into the wetlands is fully controlled by the damming of the river and the releases of water from it. During the rainy season water is released to maintain the right reservoir level and for protection of the stability of the dam.

Peak salt production takes place when conditions are dry and the fishermen's catch declines when water levels are too high in the delta. Flooding of the wetlands interferes with the birds’ roosting and nesting sites, and often washes away nests and eggs. Contrary, during the dry season no water is released from the dam and the lack of freshwater inflow to the wetlands impairs the flora and fauna, and the other activities in the delta. Hence, there is a need to develop a water management strategy which would be satisfactory to all interested parties and also would enhance the wetland’s habitat for birds as stipulated in the Ramsar conditions.

2.2 Water resources

2.2.1 Meteorological characteristics and impact of climate change Data concerning the meteorological conditions are obtained from the Ghana Mete- orological Agency, which operates a number of synoptic and rainfall stations in the Basin. The location of these monitoring stations is indicated on Map 2.4 (inserted at the end of chapter).

The Densu Basin falls under two distinct climatic zones, i.e. the relatively dry equa- torial climate of the south-eastern coastal plains and the wet semi-equatorial climate further north in the basin. Both climatic zones are characterized by a bi-modal rain- fall regime with different intensities. The main rainy season extends from April to July and attains a peak in June, whereas the second - less intense – rainy season oc- curs between September and November. These features can be detected from the fig- ures in Table 2.4, which presents rainfall data from the Nsawam meteorological sta- tion used as an example.

Table 2.4: Mean monthly rainfall (mm), Nsawam (1950-2005)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year

27 56 110 115 168 221 95 58 98 146 101 36 1,231

The rainfall pattern over the year can be classified as erratic in its occurrence. The meteorological statistics show that in average about 12% of the rainy days produce 50% of the total annual rainfall. The annual rainfall of the coastal plains averages about 800-900 mm and approaches 1,600-1,700 mm in the higher ranges in the northern part of the Basin, where the Densu river system has its headwaters. Gener- ally, it can be stated that the rainfall to the north in the basin is more reliable than that of the southern part. The mean annual rainfall distribution is also shown on Map 2.4.

May 2007 Page 13 Water Resources Commission Densu River Basin IWRM Plan

The relative air humidity ranges from an average of 50-60% in the driest months to 80-90% in the rainy season. The mean annual potential evapo-transpiration varies from 1,700 mm in the southern part of the basin to about 1,500 mm in the north.

The Densu Basin is characterised by uniformly high temperatures throughout the year with a mean annual temperature of about 27°C. The months of March and April are the hottest periods with a temperature of about 32°C. August is the coolest month with a temperature of about 23°C.

In a study by the Environmental Protection Agency 7 the impacts of likely climatic changes on river discharges (runoffs) were analysed for the country. One of the ba- sins included in the study was Ayensu, which borders the Densu basin to the west. It is imperative that the impacts and consequences cited in that study report are duly recognised in future water resource planning activities for the Densu Basin. The main findings of relevance for the Densu IWRM plan are: • There was an observed increase in temperatures of about 1°C over a 30-year pe- riod, and reductions in rainfall and runoff in the historical data sets. • Simulations using realistic climate change scenarios (10-20% change in rainfall and a 1-2°C rise in temperature) indicated reduction in runoffs of 15-20% over the coming 20-year period. • The climate change scenarios also cause reduction in groundwater recharge at a rate of 10-15% during the same period. • Irrigation water demand would be affected considerably by the simulated cli- mate change adding some 50% to the base period water demand.

2.2.2 Surface water availability The Densu River and its tributaries constitute the surface water system, which for its size is one of the most exploited in the country. Water (hydrological) balance Taking the Densu Basin as a whole, the water (hydrological) balance representing a full year has been calculated based on the following criteria: • monthly data series used; • average basin rainfall based on rainfall distribution (Map 2.4) weighted accord- ing to representative size of basin area; • actual evapo-transpiration rates derived from results of field research carried out in the Pompon sub-catchment 8 of the Densu Basin; • average groundwater recharge rate derived from (ref. 7) and other sources, and set at 14% of rainfall; and • contribution from groundwater to river flow (base-flow) and vice-versa has not been incorporated.

7 Environmental Protection Agency (EPA): Climate Change Vulnerability and Adaptation Assessment on Water Resources in Ghana (February 2000) 8 A Study of Water Balance in the Pompon Sub-catchment of the Densu River Basin. PhD Dissertation by Jacob Waako Tumbulto, Department of Geology, University of Ghana, Legon (January 2005)

May 2007 Page 14 Water Resources Commission Densu River Basin IWRM Plan

Table 2.5 provides a summary of the water balance. It should be noted that the out- come of the water balance calculations - in this case the amount of surface water available - has high sensitivity to the actual evapo-transpiration values used in the water balance equation. The annual figure of 950 mm indicated in the table below, is arrived at as the sum of monthly values, which in turn are calculated based on esti- mated rates of daily actual evapo-transpiration (ref. 8) varying from 1.3 mm/day dur- ing the driest months to 4.0 mm/day during the wettest months.

Table 2.5: Annual water balance for Densu Basin In percent Water balance component Annual amount of rainfall Rainfall 1,230 mm Actual evapo-transpiration 950 mm Densu basin area 2,600 km 2 Rainfall over basin (volume) 3,198 million m 3 100 % Actual evapo-transpiration (volume) 2,470 million m 3 77 % Recharge to groundwater (volume) 448 million m 3 14 % Surface water runoff (total for basin) 280 million m 3 9 %

From Table 2.5 it can be concluded that on an annual basis - and taken as an average for the entire basin - 77% of the rainfall goes back to the atmosphere as evapo- transpiration, 14% infiltrates down to the groundwater or remains as soil moisture, and the remaining 9% ends up as surface water runoff. It must be emphasised, though, that this water balance calculation presents a simplified situation incorporat- ing assumptions which can be refined, but nevertheless, is judged to provide a realis- tic measure as to the relative size of the elements of the Basin’s hydrological cycle.

On an annual basis, the average “yield” of the Densu Basin (surface water availabil- ity) amounts to 280 million m 3. By using this basin runoff, the annual flow volume at various points along the Densu River and for some of the main tributaries have been estimated (calculated on the basis of sub-basin area) as listed in Table 2.6.

Table 2.6: Mean annual flow volume, Densu River system Area of Mean annual River/locality sub-basin runoff (km 2) (million m3) Densu at Koforidua 510 55 Densu at Nsawam 1,440 155 Densu at Manhea (Weija Lake) 2,300 248 Kuia sub-basin 408 44 sub-basin 338 36 Nsaki sub-basin 152 16 Total Densu basin 2,600 280

Runoff statistics Recorded flow data and information on runoffs are obtained from the Hydrological Services Department, which operates a number of river gauging stations in the Basin. The locations of these monitoring stations are indicated on Map 2.4 (inserted at the

May 2007 Page 15 Water Resources Commission Densu River Basin IWRM Plan

end of chapter). However, the available data records comprise in general short time series with many gaps. Unbroken records of more than five years are not available from the Densu basin gauging stations. Nevertheless, analyses carried out on the available data series 9 indicate in many instances clearly detectable correlation be- tween the recorded runoffs at the different gauging sites in the Densu River system as well as between rainfall and runoff. These regression methods have then be used to some extent to fill in gaps and expand on the hydrological data records.

The flow regime of the Densu River exhibits a marked variability in the seasonal runoff within the year as well as in the annual flows. These features are highlighted in Table 2.7 and Figure 2.1, respectively, which have utilised the measured/generated runoff data 9 representing the Nsawam gauging site.

Table 2.7: Densu River mean monthly flow (1970-2000), Nsawam (m 3/sec)

Ave- Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec rage Mean 0.77 0.62 1.70 1.42 3.96 9.89 10.47 5.42 5.38 5.59 3.79 1.62 4.22

Max. 1.86 1.03 2.68 3.47 6.40 17.80 20.66 11.62 11.22 12.03 7.50 2.49 8.23

Min. 0.25 0.32 0.97 0.49 2.20 5.29 3.12 0.75 0.92 2.46 1.85 0.86 1.62

The average annual runoff of 4.22 m 3/sec is equivalent to an annual flow of 133 mil- lion m 3. A comparison of this figure with the value of 155 million m 3 given in Table 2.6, which was calculated based on another (the water balance) method, shows a rea- sonable match within a margin of ± 8 %. It can be noted that in the meas- ured/generated annual flow volume of 133 million m 3 the volume of water abstracted at Nsawam and upstream is not included, whereas the value from the water balance calculation incorporates all abstractions.

9 Water Resources Commission: Water Resources Assessment Tools, Elements of a Decision Support System, the Case of the Densu River Basin (November 2003)

May 2007 Page 16 Water Resources Commission Densu River Basin IWRM Plan

Nsaw am Gauging Station 210 200 190 180 170 160 150 140 130 120 110 100

Annual Flow (million m3) (million Flow Annual 90 80 70 60 50 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 Year

Figure 2.1: Densu River annual runoff (1970-2000), Nsawam (in million m3)

The erratic flow pattern of the daily flows is visualised in Figure 2.2 using the most recent measured flow data at the Pakro gauging site some 10 km upstream of Nsa- wam used as an example.

Pakro Gauging Station

16

14

12

10

8

6 Daily Flow (m3/s) Flow Daily

4

2

0

01-01-2005 16-01-2005 31-01-2005 15-02-2005 02-03-2005 17-03-2005 01-04-2005 16-04-2005 01-05-2005 16-05-2005 31-05-2005 15-06-2005 30-06-2005 15-07-2005 30-07-2005 14-08-2005 29-08-2005 13-09-2005 28-09-2005 13-10-2005 28-10-2005 12-11-2005 27-11-2005 12-12-2005 27-12-2005 Figure 2.2: Densu River daily flows (2005), Pakro gauging station (in m3/sec)

Minimum/environmental flow considerations Generally, it is the low flow characteristics of the river that determine its suitability as source for a year-round water supply, i.e. direct abstraction without a storage res- ervoir. Furthermore, the flow of the Densu River and its tributaries particularly dur-

May 2007 Page 17 Water Resources Commission Densu River Basin IWRM Plan

ing the dry season has a significant impact on the flora and fauna associated with the prevailing aquatic system.

Undoubtedly, the aquatic ecosystems of the Densu Basin are under a significant pres- sure due to the increasingly high population density, the poor wastewater and solid waste infrastructure, and lack of environmental awareness. Therefore, in addition to the direct abstraction requirements, the minimum amount of flow required to main- tain these vulnerable areas of the basin must be defined downstream of existing and proposed water intake sites as well as downstream of the Weija dam. Environmental flow is an important requirement (a water demand category in its own right) to take into consideration as part of the Densu Basin IWRM planning.

In this regard, the environmental flow consideration is not only a matter of maintain- ing a minimum flow regime, but as importantly also to safeguard that this flow main- tains a certain acceptable water quality for the aquatic ecosystems to prevail.

2.2.3 Groundwater resources Geology and aquifer systems The geology of the Densu Basin comprises mainly of the Granitoids, the Upper Birimian formation and the Togo series rocks, which are characterised by little or no primary porosity. Groundwater occurrence, therefore, is associated with the devel- opment of secondary porosities caused by fracturing, faulting, jointing and weather- ing. Map 2.5 (inserted at the end of chapter) depicts the geology of the Densu Basin.

The Birimian rocks to the extreme northwest of the Basin are generally well folded, fissured and deeply weathered, and hence groundwater occurrence in the areas un- derlain by the upper Birimian rocks is rated as high. The granites are less fractured and weathered, and subsequently groundwater occurrence in general terms is rated moderate to low, though locally, particularly in the northern part of the granitic area, relatively productive groundwater zones exist. The highly folded, jointed and frac- tured rocks of the Togo series to the southeast of the basin, coupled with the contact zone to the granite rocks, provide favourable conditions for groundwater accumula- tion as well as the occurrence of springs.

The development of secondary porosity has given rise to two distinct types of aqui- fers in the Densu Basin, viz. the weathered zone aquifers and the fractured zone aqui- fers. The weathered zone aquifers usually occur at the base of the thick weathered layer. The thickness of the weathered zones varies greatly depending on the climatic conditions and the type of rocks. The thickest weathered layers are common in the forested area of the Basin.

The fractured zone aquifers tend to be more localized in nature, and groundwater oc- currences are controlled by the degree of fracturing and the nature of groundwater recharge. Borehole yields within the fractured zone are determined by the extent and degree of fracturing. A formation which combines a thick weathered zone with a well fractured bedrock zone provides the most productive aquifer situation.

May 2007 Page 18 Water Resources Commission Densu River Basin IWRM Plan

Hydrogeological data from existing boreholes Based on data and information available from the existing boreholes in the Basin, Table 2.8 summarises the statistical evidence related to the occurrence and rate of groundwater abstraction in the Basin.

Table 2.8: Borehole characteristics in Densu Basin 10

Depth of Thickness Depth to Static Borehole Geological borehole weathered aquifer top water level yield zone (m) zone (m) (m) (m) (m3/hour)

Granites 9.1 - 103.0 1.0 - 32.0 1.9 - 72.0 0.1 - 13.5 0.1 - 30.0

Birimian rocks 25.0 - 40.0 5.0 - 27.0 10.0 - 31.0 0.8 - 16.9 0.7 - 9.0

Togo series 28.0 - 97.0 3.0 - 36.0 4.5 - 59.0 1.1 - 17.9 0.6 - 6.0

For the three geological zones, the average yield is found to be as follows: • Granitic zone: 2.0 m 3/hour; • Birimian rocks: 3.7 m 3/hour; and • Togo series: 2.8 m 3/hour.

It should be reiterated that the yield values given in this section are derived from the records and performance of existing boreholes – old as well as new ones. In this con- nection it can also be mentioned that the success rates of drilling in the granite, Birimian rocks and Togo series have been 50%, 85% and 60 %, respectively.

As stated earlier, relatively productive groundwater zones occur within the northern part of the granitic area, mainly in the Suhum-Kraboa-Coaltar and New Juabeng dis- tricts. These areas are associated with extensive fracturing and weathering that fa- vour the formation of thick overburden. The yield of boreholes in these areas can be expected to be in the range of 8-12 m 3/hour or higher depending on the siting tech- niques used, borehole design (depth and diameter), etc.

Another notable groundwater zone in the Basin is the area that lies west of the con- tact zone between the granite formation and the Togo series. Prominent areas include the Nsawam and Medie localities with yields of 10-15 m 3/hour and higher.

In general, the groundwater assessment study 10 indicates that considerable reserves are available and if well developed can produce large volume of water. To obtain op- timal utilization of the Basin’s groundwater resources, it is imperative, therefore, that groundwater schemes are based on state-of-the-art hydrogeological assessment methods, efficient borehole siting techniques as well as proper design, construction and development of the boreholes.

10 Water Resources Commission: Groundwater Assessment, an Element of Integrated Water Resources Management - the Case of Densu River Basin. CSIR-Water Research Institute (July 2003)

May 2007 Page 19 Water Resources Commission Densu River Basin IWRM Plan

2.3 Utilisation of water resources

2.3.1 General overview of water supply situation The Densu River serves as the main source of water supply for a number of fast growing communities within and outside the Basin. The groundwater resources of the Basin also serve as an important source of supply for the basin’s population, par- ticularly in the rural areas, but also some piped urban water supply schemes rely on groundwater.

Table 2.9 provides an overview of the existing water supply situation and shows for each district within the basin, the main source of drinking water as derived from the 2000 Census, i.e. with the quoted percentages representing the entire district.

However, to assess the existing water supply situation for the Densu Basin as a whole by means of a weighted average figure for each water source category (last row in Table 2.9), the percentages for the districts have been applied against the pro- portion of the respective district population living within the Basin boundary.

Table 2.9: Main source of drinking water (in % of households) Pipe- Spring and River, stream, Borehole Tanker District borne rain water pond and and well supply supply harvesting dugout East Akim 19.5 43.9 0.4 5.7 30.5 New Juabeng 66.6 20.9 0.8 2.2 9.5 Suhum/Kraboa/Coaltar 14.2 46.7 0.5 3.1 35.5 Akwapim North 39.7 24.2 1.3 6.8 28.0 Akwapim South 37.3 34.4 1.7 7.2 19.4 West Akim 11.0 48.2 0.3 4.0 36.5 Awutu/Efutu/Senya 43.2 20.6 20.9 1.3 14.0 Ga East/West 57.6 9.8 19.2 2.8 10.6 Accra Metro 90.5 4.7 3.1 1.0 0.7 Densu Basin (average) 47.6 22.2 10.0 3.4 16.8

The figures in Table 2.9 reveal the prevalent differences between predominantly ru- ral districts and more urbanised districts concerning pipe-borne water supply versus the traditional sources (borehole/well and stream/pond). Taken in its entirety, it ap- pears that close to half of all households in the Densu Basin receive water from a piped supply - either in the form of direct house connections or from public stand- pipes.

2.3.2 Urban water supply Presently, in the Densu Basin a total of 8 pipe-borne water supply schemes are in op- eration serving mainly urban communities. 5 of these schemes rely on the Densu river system as the source, whereas 3 schemes are groundwater based. Table 2.10 provides a list of these schemes including information about source, intake, treatment

May 2007 Page 20 Water Resources Commission Densu River Basin IWRM Plan

capacity and abstraction rates as obtained from the individual water plants’ statistics. The water supplied is used for domestic, industrial, commercial and institutional pur- poses. The figures in Table 2.10 reveal that presently as much as 95% of the total ab- straction of water for the urban supply schemes is for the Weija water treatment plant alone, and it is also seen that reliance on groundwater is only a small fraction com- pared to the surface water abstractions.

By comparing the figures in Table 2.6 and Table 2.10, it can be concluded that on an annual basis utilisation of the water resources through abstractions for urban schemes presently amounts to less than 3% of the mean annual runoff of the basin at Nsawam. Likewise, the abstraction from the Weija dam alone amounts to about 30% of the mean annual inflow to the reservoir.

Table 2.10: Piped water supply schemes in Densu Basin (2005)

Treatment Abstraction Water supply Source Intake capacity million scheme 3 m3/day m /day m3/year Weija surface water dam 206,000 200,000 73.00

Other schemes:

Adeiso groundwater 3 boreholes - 15 0.01

Apedwa/Asafo surface water weir 436 20 0.01

Old/New surface water dam 1,080 760 0.28

Koforidua surface water weir 4,545 5,570 2.03

Akwadum/Nankese (1) groundwater 1 borehole - 25 0.01 Suhum groundwater 4 boreholes - 380 0.14

Nsawam surface water weir 4,320 4,050 1.48

Total, other schemes 10,820 3.96 (1) Originally surface water based, now converted into a groundwater scheme

Population served by pipe-borne schemes (excluding Weija) By applying the normally used criteria for unit consumption figures, which are dif- ferentiated according to settlement sizes, i.e. 55 l/capita/day for settlements less than 15,000, 85 l/capita/day for settlements between 15,000 and 50,000, and 105 l/capita/day for a population larger than 50,000, the number of people served by the schemes can be estimated. Pooled together the urban water supply schemes in the Densu Basin (other than the Weija dam water works) are calculated to serve a popu- lation of about 110,000, equivalent to 43% of the urban population in the basin (ref. Table 2.1), i.e. people living in settlements larger than 5,000 (excluding Accra Metro and Ga West/East districts).

It should be noted, though, that in the above estimation of the number of people be- ing served, the un-accounted water, i.e. leakage and other distribution losses, has not

May 2007 Page 21 Water Resources Commission Densu River Basin IWRM Plan

been duly incorporated in the figures. This would imply that the proportion of the population served as given here is somewhat over-estimated.

The “unmet” demand combines the part of urban dwellers living in settlements not yet provided with piped water and people living within existing supply areas, but not reached by the water scheme’s supply. The reasons for not being able to cater for this “unmet” demand are attributed to various factors, e.g. technical-economic and finan- cial aspects in expanding the systems’ treatment capacity as well as the distribution network (the outreach) of the scheme.

However, a limiting factor is also the capacity of the surface water source, which is subject to a decline in the low-flow regime (EPA: Climate Change Vulnerability Study, ref 7) resulting in a reduction of abstraction or even a total cease in water pro- duction during the dry season. This situation is particularly prevalent in the case of the water supplies for Tafo and Koforidua. There is, therefore, a need to provide storage in order to have access to the resource throughout the year, to augment with groundwater and/or to import water from a neighbouring basin as envisaged in the expansion plans for the Koforidua water supply in which a pumping scheme provid- ing water across from the Volta Lake at a design rate of 13,600 m 3/day is being im- plemented. These aspects are further elaborated on the scenario analysis presented in Chapter 3.

Weija Dam Water Works The Weija dam, brought back into operation after its reconstruction was completed in 1978, is an earth/rockfill structure with an embankment height above the river bed of close to 17 m and with an inundated area (surface area of reservoir) at about 30 km 2 at maximum water level. The effective storage capacity is approximately 133 million m3, calculated as reservoir volume at maximum design level (143 million m3) minus volume at the intake’s lowest draw-off point (10 million m3).

Due to the overwhelming increase in water demand for the Accra metropolitan popu- lation now expanding up through the Ga West and Ga East districts, the Weija Water Works has regularly been subject to expansion with a marked increase in the abstrac- tion of water from the reservoir as a result. Currently yet another expansion is under construction, which will bring the abstraction rate from the present 200,000 m 3/day up to 268,000 m 3/day.

Most of the water produced at the Weija Water Works is “exported” out of the Densu Basin as an integral part of the Accra- water supply scheme. From Table 2.1 the size of urban population (2000 Census) residing in the Accra Metro, Ga West and Ga East districts located within the Basin is found to be 373,200. Recent statistics 11 indicate that some 61% of this population (i.e. about 227,000 people) has access to the water supply services. With an assumed consumption rate of 105 l/capita/day, it implies that around 24,000 m 3/day of the 200,000 m3/day presently abstracted from Weija reservoir is used within the Densu Basin itself.

11 GWCL, Planning Department for Urban Investment Requirements (2004)

May 2007 Page 22 Water Resources Commission Densu River Basin IWRM Plan

Overall urban water supply coverage In conclusion it can be stated, that as an overall estimate for the whole Densu Basin, the size of the urban population (settlements larger than 5,000 people) served by pipe-borne schemes amounts to about 337,000 people, i.e. 227,000 (Weija) plus 110,000 (other urban schemes), equivalent to about 53% (ref Table 2.1) of the total urban population within the Basin.

Finally, it should be reiterated that the calculation of number of people served based on abstraction rates and per capita consumption figures as presented above is a sim- plistic way of depicting the actual situation since factors like production losses, dis- tribution pipe network leakages, certain industrial and commercial activities etc have not fully been taken into account. In any case, it is evident that a sizeable “unmet” demand exists in the urban areas and that the water-stressed situation becomes more and more pronounced. Prudent water demand management measures need also to be introduced to be able to utilise the existing water sources and supply facilities more effectively.

2.3.3 Rural water supply As can be seen in Table 2.9, the Densu River system with its tributaries and many seasonal streams still serves directly as the water source for a sizeable part of the ru- ral population. Increasingly, however, in step with the accelerated programmes to improve their water supply situation, rural communities are giving up this source in favour of water supplied through boreholes and protected shallow (hand dug) wells.

Boreholes numbering about 600 as well as a number of hand-dug wells (estimated at 200) are the means by which the groundwater resources of the Basin are exploited. Most of the boreholes are for domestic purposes and fitted with hand pumps. There are, however, also places where boreholes are mechanized with motor-driven pumps for provision of water in the rural communities.

Based on the CWSA borehole design of 200 persons per water point and an average abstraction rate of 4.8 m 3/day (i.e. 8 hours pumping per day at 10 l/min), it can be found that the 800 water points imply a total groundwater abstraction of 3,840 m3/day (or 1.4 million m 3/year) serving 160,000 people at present. This calculation indicates that about 43% of the basin’s rural population of 375,200 (ref. Table 2.1) is served through improved water points.

It is worth noting, that the groundwater abstraction within the Basin only constitutes a small fraction of the estimated annual groundwater recharge as given in Table 2.5, which - needless to say - is no consolation in the search for satisfactory yielding boreholes as and when required at specific localities (ref. Section 2.2.3 above).

2.3.4 Water for agriculture Irrigation The Densu Basin is not used intensively for irrigation, except at Weija, where about 220 ha of irrigable land exist, operated and managed by the Weija Irrigation Pro-

May 2007 Page 23 Water Resources Commission Densu River Basin IWRM Plan

ject 12 . Originally, 1,200 ha was envisaged for irrigation in this area, but the unregu- lated growth of Accra metropolis has now created a situation whereby it is not possi- ble to expand the existing irrigable land further. Water is abstracted directly from the Weija reservoir, although it can be mentioned that the whole scheme is under reha- bilitation with the result that no abstractions are being realised for the time being.

In general terms, irrigation water requirements are reported in the WARM study 13 to vary from an annual amount of about 10,000 m 3/ha for vegetable produce to around 25,000 m 3/ha for rice fields. An average value of 15,000 m 3/ha/year is adopted for the irrigation water demand in the Densu Basin (equivalent to approximately 1.5 l/sec/ha in average per year assuming a 4-month irrigation season). It can be men- tioned that this amount matches well with a similar figure which can be derived from the State of Environment Report 2004 14 , indicating an amount of 14,300 m 3/ha/year as representative for the whole country.

When the Weija irrigation scheme starts operating again, it can be assumed that the 220 ha would require a maximum abstraction from the Weija reservoir of about 3.3 million m 3 per year.

Another established irrigation scheme which utilises the Dobro tributary is producing ornamental flowers drawing water from the Medie dam situated southeast of Nsa- wam. The irrigated area is 23 ha with an estimated water consumption 0.35 million m3 per year.

Furthermore, a number of commercial farms practicing irrigation specifically for vegetable fields and pineapple farming have been introduced over the recent past in the Densu basin. However, information is rather scanty about these schemes concern- ing areas under irrigation, irrigation practices, water consumption etc.

By adding the irrigation water demand covering these other commercial farms in the basin, a total water demand of 4.0 million m 3 per year is estimated to represent the present utilisation of water for irrigation in the Basin. The potential irrigable area in the Densu basin is assessed to be 1,500 ha (verbal communication, Ghana Irrigation Development Authority, 2006).

Livestock As generally done for the purpose of estimating livestock water demand, a percent- age figure of the rural population water demand is applied. From the WARM study 13 it can be derived that a figure of about 15% of the rural water demand can be adopted to calculate livestock water demand. That means the present livestock water usage in the Densu basin is 15% of 1.4 million m 3/year (ref. section 2.3.3), i.e. 210,000 m3/year or about 600 m 3/day.

12 The Weija Irrigation Project took over from the then Weija Irrigation Company some years back, and it is now run as a community-based activity with input and management support provided by the Ghana Irrigation Development Authority. 13 Ministry of Works and Housing: Water Resources Management (WARM) Study, Information “ Building Block” Study, Part II, Vol. 4: Information on the Coastal Basin System. Nii Consult (May 1998) 14 Environmental Protection Agency: State of Environment Report 2004. EPA (April 2005)

May 2007 Page 24 Water Resources Commission Densu River Basin IWRM Plan

2.3.5 Industrial water use Within the supply areas of the urban pipe-borne schemes the water demand by indus- tries, manufacturing and other commercial activities is included in the schemes’ pro- duction figures and hence, in future expansion plans. However, quite a number of in- dustries and some institutions rely on their own water supply, mainly from boreholes, which locally can have a sizeable rate of abstraction. These main industries include: • Voltic (Gh) Ltd (Medie); • Blue Skies Products (Gh) Ltd (Medie); • Akwaaba Mineral Water (Medie); • Still Pure Water (Medie); • Astek Fruit Processing Company Ltd. (Nsawam); • Cocoa Research Station (Tafo); • Intravenous Infusions Ltd. (Koforidua); and • Brick/tile factory (Weija).

Based on granted water abstraction licences and field inspections (WRC), it is judged that the current groundwater abstractions for these industries amount to 1,000,000 m3/year, equivalent to 2,740 m3/day.

2.3.6 Summary of water resources utilisation Table 2.11 provides an overview of the existing utilisation (abstraction) of the water resources located within the Densu Basin as derived from the above description.

Table 2.11: Water resources utilisation (2005), Densu Basin Present (actual) Abstraction Category Source m3/day million m3/year Potable (domestic, indu-

strial and institutional): - urban water supply 210,820 (1) 76.96 mainly surface water

- rural water supply 3,840 1.40 mainly groundwater

Agriculture: - irrigation 11,000 (2) 4.00 mainly surface water - livestock 600 0.22 mainly surface water Industry (not served by 2,740 1.00 mainly groundwater urban piped schemes)

Total for Densu basin 229,000 83.58

(1) Out of this amount 176,000 m 3/day (84%) is “exported” and used outside the Densu basin (2) Current abstraction is only about 20% of this amount due to rehabilitation of the Weija irrigation works

Groundwater as a source constitutes only a small fraction of the total abstraction - a resource which undoubtedly has the potential for being further utilised. Contrary, the Densu basin surface water resources is under stress with a current annual rate of utilisation approaching one-third of the basin’s total mean annual runoff calculated where the river enters the Weija reservoir (ref. Table 2.6).

May 2007 Page 25 Water Resources Commission Densu River Basin IWRM Plan

2.4 Water quality and pollution

2.4.1 Water quality monitoring The first water quality monitoring programme in the Densu River system dates back to the early 1960’s carried out by the then Public Works Department, but was rather short lived due to scarcity of resources. Results from that time showed high level of dissolved oxygen for most parts of the year – a situation which persisted also in the early years after construction of the Weija reservoir. However, by the early 1990’s the dissolved oxygen values in the Densu River system were found to have been re- duced by almost half. A special Weija lake water quality survey was conducted in 1996 (ref. 13), which - among other objectives - aimed at generating data to determine whether stratification had developed in the lake, and also for determining require- ments related to the water treatment process in light of the degrading water quality situation.

As part of a Rapid Environmental Assessment Study covering the Densu Basin under the Water for African Cities Programme 15 a water sampling exercise, which included 14 locations in the river system, was carried out in 2001. The sampling sites were visited once and thus, the exercise could only provide a “snapshot” picture of the wa- ter quality situation in the basin as it prevailed at that time.

Furthermore, the previous water quality monitoring activities related mostly to the physico-chemical parameters, and the data records were scarce with considerable gaps in time and space. However, a revived water quality monitoring programme, which includes the Densu Basin, targeting both surface water and groundwater sources, was initiated by WRC in late 2004. This programme also includes monitor- ing of trace metals, pesticides and biological parameters as well as phytoplankton and micro-pollutants as may be detected in bio-tissue (fish).

The surface water monitoring in the Densu Basin incorporates four sampling stations along the river, i.e. at Potroase (representing the upstream section of the river), Man- goase and Nsawam (representing the mid-stream conditions) and the Weija reservoir at its downstream end. The stations are visited and water samples collected for labo- ratory analyses five times per year representing the hydrological regime, i.e. samples taken during the low flow and the high flow seasons.

2.4.2 Surface water quality General overview The Densu river system has experienced a gradual, but persistent, degradation in wa- ter quality over the past years, particularly during the last decade or so. This has am- ply been demonstrated in the previous water quality monitoring programmes and studies. The decrease in the water quality has been more pronounced in the stretches of the river along and close to urban areas.

15 UNEP-UN Habitat: Water for African Cities Programme, Rapid Environmental Assessment and Action Planning of Densu River Basin. Nii Consult (July 2001)

May 2007 Page 26 Water Resources Commission Densu River Basin IWRM Plan

The absence of proper land use practices in the Basin, which has led to accelerated erosion of top soil with increased turbidity of the water as a result, has changed the physical appearance of the water. Chemically, the surface water resource shows a trend towards increased eutrophication.

Although industrial activities and factories in the basin locally have significant im- pact on the environment, for the time being the main threat to the ecological charac- ter of the river is the numerous and diffuse pollution sources, such as free-range defecation, poor disposal of household refuse and other solid waste, and rudimentary agricultural practices, including un-checked use of agro-chemicals (fertilizers and pesticides). Industrial and domestic wastewater is in many instances discharged di- rectly into open drainage systems that empty into the river system.

The human activities have impacted overwhelmingly on the ecosystem and diversity of species prevailing in the Basin. There is now a nearly total loss of riverine forest, and where still existing it is much fragmented. The high rate of timber logging (albeit it was practiced more commonly in the past than at present) as well as fuel wood ex- traction has also exacerbated deforestation and, hence, vulnerability of the surface water resource.

These factors, coupled with over-abstraction and climate (rainfall) variability, have resulted in dwindling environmental (minimum) flows. Most of the species in the ecosystems found nowadays are those that can tolerate eutrophication.

Water Quality Index The Water Quality Index (WQI), adopted by WRC in 2003, is used to facilitate com- parison and to classify to which extent the natural water quality is affected by human activities. The index is used to describe the state of water quality as a whole instead of looking at individual parameters, and can provide indications as to the suitability of the water for various purposes. The methodology incorporates selected key physi- cal, chemical and microbiological determinants, and aggregates them to calculate a WQI value at a specific water quality monitoring/sampling site.

Based on the WQI value, the index classifies water quality into four categories as presented in Table 2.12, with a descriptive note concerning the pollution level of the water body in question. The aim is to protect natural waters from pollution such that the water falls at least in the upper portion of Class II - and more desirable in Class I.

Table 2.12: Criteria for classification of surface waters

Class WQI - range Description

I > 80 Good - unpolluted water

II 50 – 80 Fairly good quality

III 25 – 50 Poor quality

IV < 25 Grossly polluted water

May 2007 Page 27 Water Resources Commission Densu River Basin IWRM Plan

Table 2.13 and Figure 2.3 present the result of the WQI calculations for the four monitoring sites along the Densu river as sampled and analysed during the two years of 2005 and 2006 16 . For each year, the parameter values given are calculated as an average of the 5 sampling rounds/analyses carried out per year for each monitoring station.

Table 2.13: Calculation of WQI at 4 monitoring sites, Densu River (2005-2006)

Value (lab. analysis) 2005 Value (lab. analysis) 2006 Parameter Potro- Man- Nsa- Weija Potro- Man- Nsa- Weija ase goase wam lake ase goase wam lake Dissolved oxygen 93.3 80.3 80.8 85.6 96.0 85.1 74.1 112.0 (% saturation) BOD 3.04 2.66 6.50 3.94 3.14 3.62 4.24 5.42 (mg/l) Ammonia-nitrogen 0.615 0.676 5.67 1.03 0.186 1.04 0.641 0.381 (mg/l) pH 7.70 8.05 7.41 8.50 6.95 7.00 6.93 8.03 NO -N 3 1.63 3.13 3.00 0.840 0.973 0.772 0.471 0.431 (mg/l as N) Faecal coliform 308 68 464 48 323 541 1732 250 (counts/100 ml) PO -P 4 0.001 0.057 0.656 0.020 0.024 0.211 0.357 0.043 (mg/l as P) Suspended solids 5.5 17.2 19.2 8.4 4.5 21.0 19.0 9.3 (mg/l) Elec conductivity 218 487 590 421 174 256 276 339 (µS/cm) Temperature 24.3 26.0 27.0 27.9 24.5 26.1 27.8 28.4 (°C) Total Score - S 83 74 57 77 91 80 67 80 (%) WQI = S 2/100 69 55 33 59 83 64 45 64

The WQI values calculated for the sites along the Densu River clearly reflect the prevailing situation of the water quality of the river from its upstream end towards its mid- and downstream sections and impacts of pollution, particularly where the river traverses urban settlements. The 2005 and 2006 values portray the same situation, namely that the upstream Potroase monitoring station has the highest WQI value with a WQI value in 2006 in the lower end of Class I, which indicates a good, almost unpolluted water. The WOI values then decrease progressively from Mangoase to Nsawam, the latter location with 2005 and 2006 values in the Class III range, indicat- ing a water source of poor quality.

Furthermore, it is interesting to note that the water quality after entering the Weija reservoir once again is to be found in the Class II category. Apparently, the water

16 CSIR Water Research Institute: Water Quality Monitoring of the South-Western and Coastal River Basin Systems – 2005 and 2006 Annual Water Quality Monitoring and Assessment Reports. Prepared for the Water Resources Commission (January 2006 and February 2007, respectively).

May 2007 Page 28 Water Resources Commission Densu River Basin IWRM Plan

source manages to “recuperate” and to some extent recover from the heavy pollution load found at Nsawam. This phenomenon is most likely attributed to the effect of the large water body created by the dam with its wind action and resulting in some water circulation, which may facilitate a self-purifying effect.

Potroase

Mangoase

Nsawam

Weija Lake

0 20 40 60 80 100

2005 WQI Water Quality Index (WQI) 2006 WQI Figure 2.3: Improvement of water quality in the Densu Basin

It is also worthwhile to note as visualised in Figure 2.3 that the water quality at all four stations has improved from 2005 (with an average WQI value of 54) to 2006 (with an average WQI value of 64). This is a sign that the various IWRM activities initiated during the past few years, e.g. relocation of solid waste dump sites, river bank protection, tree-planting and public awareness raising activities, begin to have an impact on the state of the Densu River.

Trace metals and micro-organic pollutants The screening of trace metals at the four stations along the Densu River in 2005 and 2006 indicates that most of the metals are found in concentrations close to the ex- pected levels normally seen in freshwater without heavy pollution loads, particularly from industrial activities. Furthermore, the trace metals concentrations in Weija Lake comply with the National Target Water Quality Range for Drinking Water 17 and the WHO Drinking Water Guidelines 18 .

A screening for micro-organic pollutants was also carried out with focus on pesti- cides and derivatives of DDT. Values higher than expected were observed. However,

17 CSIR, Water Research Institute, Ghana Raw Water Criteria and Guidelines, Volume 1: Domestic Water Use. Report for the WRC, August 2003. 18 World Health Organisation: Guidelines for Drinking Water Quality, Volume 1: Recommendations. Third Edition. 2004.

May 2007 Page 29 Water Resources Commission Densu River Basin IWRM Plan

no specific conclusions can be drawn related to micro-pollutant level at this juncture, and hence the monitoring will be continued and expanded also to include detection of these compounds in sediments and biota.

2.4.3 Groundwater quality As mentioned in Section 2.4.1 above a revived water quality monitoring programme was initiated by WRC in late 2004. As part of this programme, the groundwater monitoring incorporates sampling from a total of ten boreholes well distributed over the Densu Basin. All monitoring boreholes are visited twice a year to download wa- ter level data from the electronic divers and to collect water samples for laboratory analysis 19 . In general, the quality of the groundwater resources is rated as good with some exceptions as described in the following: • On the whole, the pH level of the groundwater falls within acceptable limits ex- cept for parts of the northern area of the basin where the pH is approaching slight acidity levels. • There is a distinct delineation in the occurrence of chloride: to the north of Nsa- wam the groundwater is associated with relatively low concentrations and for ar- eas to the south chloride concentrations increases to about 500 mg/l, and even higher at certain localities. The salinity undoubtedly is caused by seawater intru- sion due to lowering of the groundwater table as result of locally over-pumping from certain boreholes. • In general, turbidity, taste and discolouration due to iron in the water is not a problem, except in the northern part of the Basin, where locally relatively high iron concentrations are found, which facilitate growth of iron-bacteria in pump- parts and pipes. • The concentration of nitrate is often used as an indicator of groundwater pollu- tion. The nitrate levels in most parts of the basin fall within the recommended guideline value. A noticeable departure from this trend is the area between Man- goase and Tinkong in the Akwapim North district, where concentration of nitrate in general is higher, although not excessive. • The concentration of fluoride and arsenic in the groundwater does not seem to be a concern as both parameters fall well below the recommended guideline values.

In conclusion it can be said that the groundwater in the Densu Basin is generally of acceptable quality and hence suitable for most purposes including domestic, indus- trial and agricultural uses. There are, however, few areas particularly within the Ga West and Ga East districts where the levels of dissolved solid material (mineraliza- tion) exceed the recommended value, thus making the water less potable. The same thing can be stated concerning the chloride contents in areas of the southern part of the Basin.

19 CSIR Water Research Institute: Annual Reports (2005, 2006) on Groundwater Monitoring in the Densu River Basin for the Water Resources Commission (March 2006)

May 2007 Page 30 Water Resources Commission Densu River Basin IWRM Plan

2.4.4 Sources of pollution and sanitary condition Causes of water pollution Degradation of the water quality of the Densu river poses a range of threats, includ- ing eutrophication, algal toxicity with related health hazards, resulting from indis- criminate disposal of waste, flooding, improper use of agro-chemicals, illegal fishing methods, leaching from waste dumps, effluent discharge and accidental spills from industries. A potential risk related to further contamination of the surface water sys- tem would be the impact of a likely exploitation (mining) of bauxite in the Atewa range where the Densu takes its source. Lumbering activities in the Densu Basin causes sheet and gully erosion as well as leaching of soil nutrients - all of which end up contaminating the water sources.

The Densu Basin is generally suitable for vegetable and pineapple farming, hence the river is getting increasingly polluted due to un-checked use of agro-chemicals. It is evident from the ongoing water quality monitoring programme that agro-chemicals indeed are present in the river system and may be found in concentration levels of concern.

In recent times, the Densu Basin has increased in the number of industries within its boundaries. Though there seems to be no immediate impacts of concern, occasional reports from GWCL indicate some industrial pollution. Of importance is the growing number of food processing companies and how their waste is treated and discharged.

The collective impacts of these adverse effects result in: • high water treatment cost; • loss of biodiversity; • loss of livelihoods and income; • high disease prevalence rate and associated high medical cost; • diminishing water availability; and • water use conflicts.

Overview of the sanitary situation at basin level Generally, the sanitary and waste disposal facilities are inadequate leading to dis- posal of domestic sewage and garbage into the river system. At Nsawam, for exam- ple, an estimated 30-40 metric tons of waste are generated annually much of which are disposed of in farms sited on the fringes of the town and close to the river.

Furthermore, toilet facilities are inadequate for inhabitants living close to the river in Nsawam, Koforidua and other communities, hence there is open defecation along the river banks and directly in the river. Most of the excreta collected from pan latrines are dumped directly into the river. However, these pan latrines are being phased out. Some schools and small communities within the basin have been provided with KVIPs by CWSA.

The waste water treatment plant serving Koforidua is located close to the river. For lack of proper operation and maintenance, untreated effluents from the sedimentation

May 2007 Page 31 Water Resources Commission Densu River Basin IWRM Plan

tanks find their way directly into the river. Likewise, the old waste treatment facility at Nsawam Prisons is out of order.

Some health facilities in the basin have septic tanks that are emptied from time to time. Incinerators are also used for other waste generated. The regional hospital in Koforidua has a biogas treatment plant, which is not working properly at present. The Blue Skies Company Limited, a fruit processing company, has a waste treatment facility on site at Nsawam.

Garbage collection and disposal is very poor and pile up in huge heaps and as such leaching from the heaps drains into the river or groundwater aquifers. Landfill sites are most often not managed properly and pose a threat to the river, as garbage and leach end up in it.

2.4.5 Trends in pollution load In step with further urbanisation and industrialisation, coupled with an increase in water supply coverage in the basin, the likely pollution load and its impact on the water quality is bound to increase markedly. In this connection it can be mentioned that an increase in the total water abstraction of two to three times during the plan pe- riod from the present abstraction rate (ref. Table 3.3 in Chapter 3) could imply an in- crease in waste water discharge to the river system of up to 10 times the present load. Undoubtedly, introduction of waste water treatment schemes on a broader scale will be required in parallel with further improvement and expansion of the water supply infrastructure.

May 2007 Page 32 Water Resources Commission Densu River Basin IWRM Plan

May 2007 Page 33 Water Resources Commission Densu River Basin IWRM Plan

May 2007 Page 34 Water Resources Commission Densu River Basin IWRM Plan

May 2007 Page 35 Water Resources Commission Densu River Basin IWRM Plan

May 2007 Page 36 Water Resources Commission Densu River Basin IWRM Plan

May 2007 Page 37 Water Resources Commission Densu River Basin IWRM Plan

3. WATER DEMAND PROJECTIONS AND WATER AVAILABILITY

Based on the demographic/socio-economic figures and other information given in the Baseline Description, this part of the IWRM plan provides information on projected water demands and assesses the balance between future requirements and water availability.

The demand projections versus water availability is addressed in a two-pronged manner in this chapter, i.e. firstly, an assessment of the overall basin situation is made (ref. sub-chapter 3.3 below), and secondly, scenario analyses are presented, which highlight various options related to utilisation and management of the available water resources (ref. sub-chapter 3.4 below). The water demand projections are made covering a plan period ending by year 2020.

The scenario analyses capture some of the key ‘quantitative’ water resource planning issues associated with the Densu Basin, namely supply options for the major demand centres including Koforidua and Nsawam, and import and export of water to/from the basin, including continued and increased supply to Accra from the Weija dam. Also the impacts of any likely climate change, environmental flow requirements and groundwater abstractions are included in the scenario calculations.

3.1 Demographic and socio-economic development trends

The assumptions used in calculating water demand for the supply of potable (municipal/domestic) water and to meet water requirements for the main socio- economic activities, notably agriculture (irrigation) and industry, are outlined below.

3.1.1 Assumptions for projection of potable water demand The requirement for potable (municipal/domestic) water is determined based on es- timates of per capita water demand and future population growth. The unit water demand (daily per capita demand) figures applied are adapted from the design values commonly used in Ghana (GWCL), which are differentiated according to settlement size and time horizon as depicted in Table 3.1.

Table 3.1: Unit water demand (litres/capita/day) Settlement size 2005 2010 2015 2020 < 2,000) 200 persons per water point 2,000-5,000 30 30 35 35 5,000-15,000 55 65 75 85 15,000-50,000 85 85 90 95 > 50,000 105 110 115 120 Densu Basin, rural 35 35 35 35 Densu Basin, urban 95 100 110 120

May 2007 Page 38 Water Resources Commission Densu River Basin IWRM Plan

For the purpose of projecting water demand for the whole basin as a unit, an average set of unit demand figures have been defined for rural and urban settlements as also shown in Table 3.1. The daily per capita demand of 35 l/c/d indicated for the rural communities is set relatively high to reflect the fact that some water from the point sources (boreholes/wells) also is used for subsistence farming purposes.

With departure point in the 2000 Census population figures presented in Table 2.1, annual population growth rates as given in the individual District Poverty Profile re- ports 20 have been used to arrive at the 2005 population sizes for each district repre- sented within the Densu Basin. The same annual growth rates have been applied throughout the plan period to estimate the future population except for a few adjust- ments as explained below.

In the case of Ga West and Ga East districts, the reported growth rate of 8.7% annu- ally has been lowered during the plan period to end with a 5% rate. This is done in recognition of the fact that it is anticipated that these districts in 10-15 years will have achieved a certain level (saturation) of “urbanisation” built-up. In this regard it can be noted that the Accra Metro area by now shows an annual growth rate of around 4%. Likewise, the Akwapim South district is given an increasing growth rate during the plan period to reflect the anticipated trend that the Accra metropolis ur- banisation phenomenon gradually will reach this district also as witnessed in the Ga West and Ga East districts in the recent past.

Against this background, Table 3.2 presents the population forecasts per district and accumulated for the entire Densu basin. In the table, growth rates are given for each five-year period. It can be noted that the various District Poverty Profile reports pro- vide one growth rate only, which means (it must be assumed) that the indicated growth rates represent “average” values combining both the rural and the urban set- tlements of the respective district.

From the figures in Table 3.2 it can be seen that the total population of the Densu Basin is expected to increase from the 2000 Census figure of about 1.0 million to some 2.7 million twenty years later in 2020, equivalent to an average annual growth rate of around 5% (with a decreasing trend during the plan period). In year 2000 ap- proximately 50% of the basin’s population was residing in the Ga West, Ga East and Accra Metro districts. In year 2020 this proportion is anticipated to increase to about 70% of the basin population. It can be noted that these three districts together area- wise occupy less than one-quarter of the total basin area.

20 As part of the second generation Ghana Poverty Reduction Strategy (GPRS II) activities, the National Development Planning Commission (NDPC) directed each District Assembly to prepare poverty profiling, mapping and pro-poor programming reports. These became available during the latter part of 2004.

May 2007 Page 39 Water Resources Commission Densu River Basin IWRM Plan

Table 3.2: Population projections per part of districts within Densu Basin (2005-2020) (1) Settle- 2000 2005 2010 2015 2020 District ment popula- p.a. Popula- p.a. Popula- p.a. Popula- p.a. Popula- type tion % tion % tion % tion % tion rural 800 1.4 858 1.4 920 1.4 986 1.4 1,057 Fanteakwa urban 0 1.4 0 1.4 0 1.4 0 1.4 0 rural 1,200 1.4 1,286 1.4 1,379 1.4 1,478 1.4 1,584 Yilo Krobo urban 0 1.4 0 1.4 0 1.4 0 1.4 0 rural 27,500 1.4 29,480 1.4 31,602 1.4 33,877 1.4 36,316 East Akim urban 47,000 1.4 50,383 1.4 54,010 1.4 57,898 1.4 62,067 New rural 22,000 2.6 25,013 2.6 28,438 2.6 32,332 2.6 36,759 Juabeng urban 114,100 2.6 129,725 2.6 147,489 2.6 167,686 2.6 190,649 Suhum/ rural 101,700 1.4 109,022 1.4 116,872 1.4 125,287 1.4 134,307 Kraboa/ Coaltar urban 31,000 1.4 33,232 1.4 35,624 1.4 38,190 1.4 40,939 Akwapim rural 19,700 1.8 21,538 1.8 23,547 1.8 25,744 1.8 28,146 North urban 5,000 1.8 5,466 1.8 5,976 1.8 6,534 1.8 7,144 Akwapim rural 53,100 1.6 57,486 2.3 64,408 3.3 75,760 5.3 98,080 South urban 43,000 1.6 46,552 2.3 52,157 3.3 61,350 5.3 79,425 rural 10,500 1.4 11,256 1.4 12,066 1.4 12,935 1.4 13,867 West Akim urban 8,200 1.4 8,790 1.4 9,423 1.4 10,101 1.4 10,829 rural 125,500 8.7 190,468 8.0 279,860 7.0 392,518 5.0 500,964 Ga West urban 341,100 8.7 516,318 8.0 758,639 7.0 1,064,031 5.0 1,358,003 rural 2,300 8.7 3,477 8.0 5,109 7.0 7,166 5.0 9,145 Ga East urban 6,400 8.7 9,670 8.0 14,209 7.0 19,929 5.0 25,435 rural 2,100 4.3 2,592 4.3 3,199 4.0 3,892 3.0 4,512 Accra Metro urban 25,700 4.3 31,722 4.3 39,155 4.0 47,638 3.0 55,225

Awutu/Efutu rural 8,800 2.1 9,764 2.1 10,833 2.1 12,019 2.1 13,335 /Senya urban 10,000 2.1 11,095 2.1 12,310 2.1 13,658 2.1 15,154

rural 375,200 462,240 578,233 723,994 878,072 Densu Basin urban 631,500 842,953 1,128,992 1,487,015 1,844,870

Densu Basin, total 1,006,700 5.4 1,305,193 5.4 1,707,225 5.3 2,211,009 4.3 2,722,942

(1) Growth rates are given in per annum (p.a.) percentages for each 5-year period

3.1.2 Assumptions for projection of agriculture and industrial water demand Agriculture The agricultural water demand category includes water for irrigation and livestock watering. It can be concluded from Section 2.3.4 that the present land under irriga- tion in the Densu Basin is around 250-270 ha of which 220 ha is located in the down- stream part of the river system adjacent to the Weija reservoir (although at present no water is abstracted due to rehabilitation activities carried out under the Weija Irriga- tion Project). In realistic terms, it is assumed that for the basin as a whole, the period up to year 2020 will see an increase in irrigation of up to one-third of the potential

May 2007 Page 40 Water Resources Commission Densu River Basin IWRM Plan

irrigable land identified in the Densu Basin. This implies that 500 ha could be under irrigation at the end of the plan period.

The livestock watering demand constitutes only a small portion compared to the other uses in the basin as shown in Table 2.11, and this situation is not expected to change drastically. Looking at the present usage, the future livestock watering de- mand can be estimated in average to be at a rate of 15% of the rural population’s pro- jected water demand.

Industry The water demand for industrial, commercial and institutional purposes, which fall within the urban piped schemes’ supply areas, is included in the projected potable water demand, and thus is accounted for in the unit figures given in Table 3.1 above.

Additionally, as explained in Section 2.3.5, a number of industries outside these sup- ply areas have their own supply facilities (mostly groundwater based). These indus- tries abstract a volume of water which is about 8% of the present urban water usage within the Basin, i.e. excluding the water “exported” out of the Basin from the Weija water works. It is assumed that this percentage can be used also to estimate the future industrial water demand. This industrial demand is estimated separately.

3.2 Water demand projections

By applying the various assumptions and figures given in the preceding section, the future water demand covering the Densu Basin has been calculated with results given in Table 3.3. It should be emphasised that the figures in the table represent the “ulti- mate” water demand as required by the whole population of the Densu Basin, i.e. as- suming 100% service coverage. Not surprisingly, from Table 3.3 it can be seen that the urban water supply sector is by far the largest demand category, which in year 2020 according to the projections will constitute about 75% of the total water de- mand, with the rural population and water for irrigation accounting for close to 11% and 7%, respectively.

Table 3.3: Water demand projections, Densu Basin (2005-2020)

User 2005 2010 2015 2020 category m3/day 10 6m3/yr m3/day 10 6m3/yr m3/day 10 6m3/yr m3/day 10 6m3/yr Urban 80,100 29.2 112,900 41.2 163,600 59.7 221,400 80.8 population Rural 16,200 5.9 20,200 7.4 25,300 9.2 30,700 11.2 population Irrigation 11,000 4.0 12,300 4.5 16,400 6.0 20,500 7.5

Livestock 2,400 0.9 3,000 1.1 3,800 1.4 4,600 1.7

Industry 6,400 2.3 9,000 3.3 13,100 4.8 17,800 6.5 Densu 116,100 42.3 157,4 00 57.5 222,200 81.1 295,000 107.7 Basin, total

May 2007 Page 41 Water Resources Commission Densu River Basin IWRM Plan

3.3 Water balance assessment for whole basin as one unit

Groundwater demand vs. occurrences at basin level It is implicitly taken for granted that improved water supply to the rural (area-wise scattered) population also in the future by and large will depend on groundwater ab- stracted from boreholes and wells. Additionally, a certain number of the urban set- tlements to be provided with pipe-borne supply facilities will also be groundwater- based. In this overall basin-level evaluation it is assumed that 20% of the future ur- ban population will fall in this category. Likewise, individual industries (not served by pipe-borne schemes) will also to a large extent rely on boreholes, tapping water from suitable aquifers, which in some areas within the basin can be high-yielding.

Thus, by the end of the plan period, the total demand for groundwater (ref. Table 3.3, year 2020) will be (20% of 80.8 + 11.2 + 6.5) million m 3 per year = 33.9 million m 3 per year . This amount shall be weighted against the groundwater resources available taken as an average over the Basin. In Table 2.5 the sub-surface water retention and groundwater recharge rate is stated to be 14% of mean precipitation, which gives a gross infiltration/recharge rate of 172 mm per year in average. If it is assumed on the conservative side that only about 15% of this amount is converted into available (ex- ploitable) groundwater, it would on a basin basis imply a sustainable groundwater yield of 67.1 million m 3 per year.

In Section 2.2.1 it is stated that a likely impact from climate change, i.e. reduced rainfall, may result in a 10-15% reduction in groundwater recharge. Even with this scenario taken into consideration, it appears that the basin’s groundwater resources in general are ample to sustain the envisaged future abstractions. This does not mean, however, that locally there will not be problems in finding suitable groundwater oc- currences.

As also pointed out earlier, to obtain optimal utilisation of the Basin’s groundwater resources, it is imperative that groundwater schemes are based on state-of-the-art hy- drogeological assessment methods, efficient borehole siting techniques as well as proper design, construction and development of the boreholes. It is also implied that future groundwater schemes may have to depend on deeper boreholes than usually drilled to obtain the required amount of water, and on longer pumping mains to bring the groundwater to the point of utilisation.

Suhum groundwater-based supply scheme The water supply scheme of Suhum, which also serves adjacent settlements, is the largest pipe-borne groundwater-based scheme in the Basin. At present, abstraction takes place from 4 boreholes, which provide 380 m 3/day (ref. Table 2.10) with the largest pump capacity rated at 10 m 3/hour. In the context of this plan and with refer- ence to the description given in Section 2.2.3, it is assumed that new constructed boreholes in this part of the basin in the future will be able to be developed to a safe yield of at least 15 m 3/hour.

The urban portion of the whole Suhum/Kraboa/Coaltar district (within the Densu ba- sin) is projected (ref. Table 3.2) to have a population (year 2020) of 40,939. For cal- culation purpose it is assumed that the Suhum groundwater-based supply scheme in

May 2007 Page 42 Water Resources Commission Densu River Basin IWRM Plan

the future will serve half of the district’s urban population through a mix of individ- ual connections and public standpipes. If it is further assumed that this mix in service level can be characterised by an average unit consumption figure of 80 l/c/d, it im- plies a year 2020 groundwater demand for the Suhum water supply scheme of about 1,640 m3/day. To this amount should be added an allowance for system losses (leak- age, etc), say of 25%.

Against this background it can be stated that one borehole pumping for 12 hours per day can provide at least 180 m 3/day, which indicates that the 2020 water demand of Suhum and its environs will require a total of 11 to 12 boreholes. To put this number in perspective, it means that in average some 1,800 people would be served per bore- hole – nearly ten times more than the design criteria prescribed in implementing the various projects under the national rural water supply programme.

Surface water demand vs. total runoff at basin level When the demand for groundwater (year 2020) is subtracted from the total water demand of 107.7 million m 3 per year (Table 3.3), a value of 73.8 million m 3 per year is found to be the demand for surface water to fulfil the requirements of the whole basin at the end of the plan period. Also in this case should be added a 25% allow- ance for “un-accounted for” water (losses).

With reference to Table 2.6, the average annual runoff of Densu River as it enters the Weija reservoir is given as 248 million m 3 per year. With the inclusion of a 15-20% reduction in annual runoff due to the effects of a likely continued climate change (ref. Section 2.2.1), it appears when considering the basin as one unit that the surface water resources can cater for the future requirements.

It should be emphasised, though, that the above statement is made to provide an as- sessment and judgement concerning the overall resource availability on an annual basis for the Densu Basin as a unit considering only the water requirements of the population residing within the basin boundaries and the associated socio-economic activities.

However, in this overall, basin-wide assessment other requirements should also be included, viz. the amount of water “exported” from the basin to other areas of the Accra-Tema metropolitan water supply area, which currently amounts to some 64.2 million m 3 per year (ref. footnote in Table 2.11), as well as environmental flow re- quirements. When these other requirements are considered the indication is that a general water-stressed situation for the basin is gradually emerging.

3.4 Scenario analyses of water availability vs. requirements at demand sites

3.4.1 Introduction to scenario analyses and model assumptions Irrespective of the water resource overview and general conclusions presented in Section 3.3 above, it is a well known fact that it is the low-flow regime of the Densu River, which determines its viability as a source for a year-round water supply (run-

May 2007 Page 43 Water Resources Commission Densu River Basin IWRM Plan

of-the-river scheme), i.e. direct abstraction without in-stream storage capacity pro- vided.

To examine the consequences and extent of future shortages in step with increased demand, the low flow regime – as determined by runoff data series long enough to reflect the hydrologic/statistical features of the river flow – has been introduced in the analysis utilising data referred to in Section 2.2.2 (ref. 9).

Water requirements at main water demand sites The following demand sites, which at present are supplied through piped systems re- lying on the Densu river system, are assumed to continue to be supplied by surface water from schemes to be expanded in step with increase in water requirements in and around these supply areas: − Apedwa, − Old-New Tafo, − Koforidua, − Nsawam, and − Weija Dam with abstractions for (i) the Weija treatment plant requirements, (ii) the irrigation farms, and (iii) an environmental flow to the Ramsar wetland site.

Additionally, in the future, other urban settlements (communities above 5,000 in size) will also need to abstract water from the river system or to be included in ex- pansion of the “old” schemes to cater for their water requirements. For reasons of simplicity, in the water accounting and scenario analyses presented below, these various “other urban” surface water requirements are included in the above listed demand sites within the respective districts.

It should also be noted that conclusions reached, based on results of the scenario analyses, only consider coverage in term of water availability as a source for meeting the requirements, and does not take into account the various technical aspects as pre- condition for attaining the coverage, e.g. appropriateness and efficiency of water in- take structure, expansion of transmission mains and distribution outreach.

As far as the Suhum groundwater-based supply scheme is concerned, it is assumed - as also mentioned in Section 3.3 above - that in the future it will supply half of the population of the Suhum/Kraboa/Coaltar district (residing within the basin) with wa- ter, whereas the other half is proposed to be supplied from a new surface water scheme, e.g. abstraction of water from a site on the Kuia tributary near Asuboi.

The water requirements of the southern portion of the Densu Basin, which combines parts of Ga West, Ga East, West Akim and Awutu/Efutu/Senya districts, and a por- tion of Accra Metro area, are assumed to be met from GWCL Weija scheme cur- rently under expansion. When the ongoing expansion of the water works and trans- mission system is completed, the volume of water processed will increase from the present 200,000 m 3/day to approximately 268,000 m 3/day. During the remaining of the plan period, the future abstractions from the Weija reservoir is assumed to be maintained at this level, i.e. no new expansion of the physical “infrastructure” (raw

May 2007 Page 44 Water Resources Commission Densu River Basin IWRM Plan

water pumps, treatment facilities and transmission mains from the Weija plant) is foreseen beyond the facilities being put in place now.

Utilising the projected urban population figures (ref. Table 3.2) and the unit con- sumption rates as given in Table 3.1, the 2020 water demand situation for these de- mand sites is summarised in Table 3.4. Other surface water based demand sites (mainly for irrigation purposes) in the basin are established and introduced in the cal- culations as explained in Section 3.1.

Table 3.4: 2020 projected water demand at surface water abstraction points Abstraction point/demand site 2020 population to be served 2020 water (portion of district within basin) (residing within basin) demand (m 3/day) Apedwa 8,716 741 (part of East Akim) New/Old Tafo 53,351 6,402 (part of East Akim) Koforidua 197,793 23,735 (New Juabeng + Akwapim North) Nsawam 79,425 9,531 (Akwapim South) Suhum 40,939 3,889 (Suhum/Kraboa/Coaltar) Weija Dam (Ga West, Ga East, West Akim, 1,464,646 175,758 Awutu/Efutu/Senya and Accra Metro)

System losses (un-accounted for water) It is a fact that the existing piped water supply systems in Ghana generally suffer from unacceptable high rates of un-accounted for water, i.e. physical losses, notable in the transmission mains and distribution network. At present, it is estimated that in average some 40% of water produced can be categorised as un-accounted for water.

It should be noted that a high rate of un-accounted for water not only implies a non- efficient way of using the available water sources, but also results in extra costs re- lated to water treatment, pumping (energy) and other operational aspects.

As part of the alternative water resource utilisation options presented below, it is opted in this plan to assume that system losses will (and must) gradually be brought down to a 25% level, which also is considered a realistic aim to achieve over the plan period. The un-accounted for water percentage figure is added to the demand figures as presented in Table 3.4 to arrive at the actual water requirements at the various ab- straction points.

Minimum flow requirements To sustain river flows for environmental ‘maintenance’, minimum flow requirements have been introduced downstream of the water abstraction points and dam sites. The assessment of the minimum flow requirements have been based on a low-flow fre-

May 2007 Page 45 Water Resources Commission Densu River Basin IWRM Plan

quency analysis on the monthly flow data (ref. 9) and determined as the 95-percentile flow (i.e. the 20-year minimum flow return period) in each calendar month. This cri- terion is also used in the case of Weija dam to ensure a minimum flow downstream of the dam for the benefit of the aquatic ecosystems in the Densu delta and lagoon (Ramsar site).

The WEAP computer model The computer-based Water Evaluation and Planning (WEAP) Model is used to carry out scenario analyses to facilitate the understanding and description of different wa- ter resource development choices, and to establish their consequences. It operates on the principles of water balance accounting and examines alternative water develop- ment strategies in form of scenario analyses to provide answers to various “what if” questions.

For each model run (scenario), the various water requirements covering the whole river system are taken into consideration, and the induced upstream-downstream in- teractions and their consequences are being accounted for and results shown in a number of optional ways to be chosen by the user, such as graphs, in table form or as histograms. Also the percentage of requirements met (coverage rate) at each demand site is calculated with increments of one month throughout the plan period.

The starting point of the basin modelling is to establish and define the basic water re- lated elements of the Basin and their relations as they currently exist. This overview of the existing situation is called the “current accounts”. The “current accounts” in- cludes the specification of supply, demand and resource data, including information on dams and reservoirs, as extracted from the information and figures presented in the previous chapters/sections and other sources.

As an example, Map 3.1 (inserted at the end of chapter) provides a schematic over- view of the Densu river system and the basic set-up of the river basin model compo- nents as extracted from one of the WEAP applications. The map depicts the main elements such as abstraction/demand sites (urban water supplies, irrigation schemes, etc), dam sites, locations for minimum flow requirements, and other main features, like transmission lines, used in the scenario analyses.

3.4.2 Results from the scenario analyses Introduction A number of scenarios, comprising various assumptions related to availability of wa- ter and different development options and strategies for the utilisation of the Densu water resources have been analysed with results presented in this section. It must be emphasised, though, that the presented scenarios and the associated water resource development options should be regarded as a “point of departure” from which the ba- sin modelling coupled with requirements for detailing can be further developed as the need for planning and decision-making at various levels (basin-wide or project specific) arises.

May 2007 Page 46 Water Resources Commission Densu River Basin IWRM Plan

In the context of this plan, the results from the scenario analyses are reported on and compared with each other by highlighting the level of service coverage as calculated at the different demand sites towards the end of the plan period 21 .

In harmony with progress towards fulfilling the Millennium Development Goals (MDG), it is adopted that the general water supply coverage rate should at least reach 90% by the end of the plan period (2020) for the supply system to be rated as provid- ing a reliable and satisfactory service. This coverage criterion constitutes the ‘yard- stick’ by which the future water supply situation balanced against availability of wa- ter can be judged using the results generated from the computer-aided scenario analyses.

It should be reiterated that in these scenario analyses the withdrawal from the Weija reservoir is determined by the given capacity (when the ongoing expansion works are completed) of the physical infrastructure, i.e. size of dam/reservoir, intake structure and water treatment capacity of the GWCL water works, rather than the ultimate wa- ter demand within the area serviced by the expanded Accra-Tema water supply scheme.

For calculation purposes, it is further assumed that the expanded Weija scheme with a capacity of about 268,000 m 3/day will be operational from year 2010 and fully util- ised by 2015, and that future withdrawals will be kept constant at this rate, i.e. no further increases in the abstraction rate is foreseen throughout the plan period.

Furthermore, the Weija irrigation farms will withdraw up to 9,000 m 3/day from the Weija reservoir after the irrigation project’s pumps and other infrastructure have been rehabilitated and brought back into operation.

In the following, a total of 7 scenario analyses are presented. The first 5 model runs (scenarios 1-5) provide information about the existing situation and assess to which extent, e.g. climate change and more result-oriented efforts towards reducing system losses (un-accounted for water) impact on the water supply coverage rate expected towards the end of the plan period. Against this background, the last model runs (scenarios 6 and 7) provide results of two alternative water resource utilisation op- tions identified to address the projected water-stressed situation of the basin.

Basic scenarios for water resource assessment Scenario 1: Unchanged (“do nothing”) water resource capacity situation This scenario assumes a future status quo situation regarding the resource capacity, which implies that no new dams or additional sources will be introduced. However, the existing water abstraction and other facilities will be expanded in step with the increase in water requirements up to the limit of the present source capacity.

21 The indicator used to represent the coverage rate towards the end of the plan period is calculated as the average “% of requirements met”(as generated from the WEAP model applications) during the water- stressed months of the three last years of the plan period, i.e. 2018-2019-2020, for each demand site. In other words, the coverage rate defined in this way provides a measure for the general water supply situation at a demand site during the low- flow periods at the end of the plan period.

May 2007 Page 47 Water Resources Commission Densu River Basin IWRM Plan

In the water requirements for this “do nothing” scenario, the amount of un-accounted for water (system losses, leakages etc) at each demand site is included at the prevail- ing rate of 40% of the projected “normal” demand. Minimum (environmental) flow requirements meant for aquatic ecosystem protection are also included as explained in Section 3.4.1 above. In this scenario, the likely effect of climate change with lower runoff as a result is not taken into consideration (ref. scenario 3 below). Result : Not surprisingly, as can be seen from the percentages given in Table 3.5 below, a fu- ture “do nothing” scenario results in pronounced water shortages during the dry months for all upstream demand sites, i.e. Apedwa, Tafo and Koforidua, whereas the runoff of the Densu river at the Nsawam demand site is sufficient to meet the re- quirements also during the low-flow periods throughout the plan period.

It can also be mentioned that towards the end of the plan period, only less than half of the Weija reservoir storage capacity is utilised, even with due consideration given to releases of the environmental (minimum) flow requirements downstream of the dam. Hence, it can be deduced that the Weija reservoir still has a sizeable “reserve” storage capacity, also after the current abstraction/treatment expansion works are completed. Therefore, based on the model run for this “do nothing” scenario, it can be concluded that the question about water availability (capacity of the river source) poses a problem primarily for the demand sites in the northern portion of the Basin.

Scenario 2: Introducing transfer of water from Volta Lake At the end of 2006, GWCL has commissioned the engineering works for final design and construction of a pumping scheme, whereby water will be transferred from the Volta Lake to supplement the supply from Densu river to Koforidua water scheme. Hence, the second scenario examines to which extent the introduction of this inter- basin water transfer scheme will improve the Koforidua water supply situation. It should also be mentioned that the transmission pipe from Volta Lake also will bene- fit various demand sites en route.

In the analysis, the transfer scheme’s design capacity of 13,600 m3/day is used and assumed to be operational by year 2010. It can be noted that in operational terms, GWCL is given priority to the utilisation of water from the Densu River before sup- plementary water is pumped across from the Volta Lake to Koforidua. Result : This second model run has shown that the transfer scheme as intended alleviates the situation with a full coverage rate for Koforidua up to around year 2015. At that juncture, in step with the increasing demand for water, shortfalls in the supply of wa- ter to the expanded Koforidua supply scheme will begin to be experienced once again with the result that water requirements can not be met in a satisfactory way to- wards the end of the plan period. With reference to Table 3.5, it can be seen that the introduction of the water transfer scheme lifts the coverage rate for Koforidua and

May 2007 Page 48 Water Resources Commission Densu River Basin IWRM Plan

environs from 59% to 67%. In this scenario, the situation will not change for the up- stream demand sites of Apedwa and Tafo, which maintain the “do nothing” (Sce- nario 1) results.

As explained in footnote 21 , it should be reiterated that the percentages representing requirement met (coverage rate) refer to the supply situation during the low-flow pe- riods only (typically 2-3 months per year) at the end of the plan period.

Table 3.5: Coverage rate, existing situation (Scenarios 1 and 2) Demand site (by end of plan period) Scenario Weija Apedwa Tafo Koforidua Nsawam Lake 1. Unchanged (“do nothing”) 44% 38% 59% 100% 100% water resource capacity situation 2. Transfer of water from Volta Lake to Koforidua water supply 44% 38% 67% 100% 100% (works commissioned)

Scenario 3: Impact of climate change As explained in Section 2.2.1, the effects of a likely climate change can be quantified in terms of an anticipated decrease in surface water runoff. The study referred to in that section indicates that a climate change scenario considered realistically to occur, i.e.10-20% change in rainfall and a 1-2°C rise in temperature, will reduce surface runoff in the range of 15-20% over the coming 20-year period. Furthermore, irriga- tion water demand would be affected considerably by the simulated climate change adding some 50% to the present water demand for irrigated agriculture.

The reduced runoff caused by a likely climate change has been imposed on the data series used in the calculations, and an alternative model run was made for the “do nothing” situation to compare and get an idea about the “order of magnitude” of a climate change impact on meeting the future water requirements. Result : Table 3.6 depicts the result of the model run for the climate change scenario present- ing the percentage of requirements met (coverage rate) during the low flow periods towards the end of the plan period in comparison with the Scenario 1 results ex- tracted from Table 3.5.

From the figures presented in Table 3.6, it is clear that the effects from a climate change would reduce markedly the ability of the Densu river to act as a source to meet requirements in any satisfactory way without a water augmentation/alteration scheme introduced. The impact of the climate change will also be felt at the down- stream demand sites. For instance, at Nsawam the coverage rate falls from the 100% coverage level to 80%.

May 2007 Page 49 Water Resources Commission Densu River Basin IWRM Plan

Table 3.6: Coverage rate, impact of climate change (Scenario 3) Demand site (by end of plan period) Scenario Weija Apedwa Tafo Koforidua Nsawam Lake 1. Unchanged (“do nothing”) 44% 38% 59% 100% 100% water resource capacity situation 3. Unchanged (“do nothing”) water resource capacity situation 40% 34% 44% 80% 99% – with impact of climate change

In addition to the decline in service coverage, the model runs further show - not sur- prisingly - that the impact of climate change also prolongs the period (number of low-flow months) during which shortfalls in water availability will be prevalent.

It goes without saying, that in tangible terms it is not known to which extent a likely climate change will impact on the surface runoff regime, but it is, nevertheless, ad- visable to think in terms of introducing some form of long-term “contingency plans” in this respect. For this purpose, the alternative water resource utilisation options pre- sented below as Scenarios 6 and 7 incorporate the effect of a possible climate change as quantified above.

Scenario 4: Sensitivity to improvements in water delivery system losses In this scenario, the result of efforts towards reducing the physical losses is high- lighted. As an example, Scenario 1 has been subjected to another model run with a reduced rate of un-accounted for water from the prevailing 40% to the targeted 25%. In principle, this set of model runs can also be used to make a judgement about the effect of introducing water demand management measures as a means to use water more efficiently. The outcome of this analysis is given in Table 3.7.

Table 3.7: Coverage rate, response to changes in system losses (Scenario 4) Demand site (by end of plan period) Scenario Weija Apedwa Tafo Koforidua Nsawam Lake 1. Unchanged (“do nothing”) water resource capacity situation 44% 38% 59% 100% 100% – with 40% system losses 4. Unchanged (“do nothing”) water resource capacity situation 55% 48% 74% 100% 100% – with 25% system losses

Result : The table values clearly provide an indication of the impact (sensitivity) to an im- proved efficiency in water delivery, i.e. by reducing the amount of un-accounted for water and/or by introducing water demand management measures. As a matter of fact, a targeted and well organised programme aimed at reducing water losses, and in general towards using the resource more efficient, could “save” water to such an ex-

May 2007 Page 50 Water Resources Commission Densu River Basin IWRM Plan

tent that it would counteract in a sizeable manner the effects of a likely climate change.

Scenario 5: Priority in utilisation of water from Densu River and Volta Lake As mentioned under Scenario 2 above, when the water transfer scheme aimed at pumping water from the Volta Lake to Koforidua supply scheme is brought into op- eration, the GWCL stated strategy – for rather obvious economic, operational reasons – will be to give first priority to use water from the Densu river before supplementary water is pumped across from Volta Lake.

The consequence of changing this priority setting is documented in this scenario, whereby the water transfer pipeline’s capacity of 13,600 m3/day should be used more fully, i.e. giving first priority to the Volta Lake water for Koforidua water supply rather than the Densu river. The aim is to take more advantage of the given invest- ment already made and to retain the Densu river source as much as possible for downstream uses, in particular for expanding the Nsawam water supply scheme.

For the purpose of this comparison, the scheme for transfer of water from the Volta Lake to Koforidua water supply (Scenario 2) has been subjected to two model runs, both with the effect of climate change and 40% system losses included, but with changed priority in source utilisation (5a and 5b, respectively). The results are given in Table 3.8.

Table 3.8: Coverage rate, Densu and Volta Lake prioritisation (Scenario 5) Demand site (by end of plan period) Scenario Weija Apedwa Tafo Koforidua Nsawam Lake 5a. Transfer of water from Volta Lake to Koforidua water supply 40 36 67 80 100 – first priority to use Densu River 5b. Transfer of water from Volta Lake to Koforidua water supply 40 36 67 98 100 – first priority to use Volta Lake

Result : The results indicate that to use the Volta Lake water with associated high pumping costs as priority over the Densu river will provide a relief to the supply situation downstream, to such an extent that the Nsawam demand can be satisfactorily sup- plied at the end of the plan period. Further source assessments coupled with eco- nomic/financial analyses have to be carried out to clarify how the Volta Lake water pumped through the 13,600 m3/day capacity transmission main most beneficially can be used as part of meeting the water requirements of the Densu basin rather than the Koforidua water supply alone.

Alternative water resource utilisation options Faced with the challenges to meet future water requirements, particularly when the impact of a likely climate change is taken into consideration, two possible water

May 2007 Page 51 Water Resources Commission Densu River Basin IWRM Plan

source “infrastructure” development options have been included in the WEAP model application as follows: − introduction of a second (additional) transfer pipe from the Volta Lake; and − construction of a new dam a few kilometres upstream of the present Koforidua water intake site.

It should be reiterated that in the projected water requirements for these scenarios, the following “extra” demands are also included: (i) un-accounted for water (system losses, leakages etc) at each demand site at 25% of projected “normal” demand, and (ii) minimum flow requirements for aquatic ecosystem protection in all river sections below the various abstraction points.

Scenario 6: Additional transfer of water from Volta Lake In addition to the water transfer introduced by year 2010 with priority given to use Volta Lake water before Densu river towards meeting the requirements of the Ko- foridua demand site (similar to Scenario 5b), in this scenario it is assumed that a sec- ond, supplementary water transfer pipeline from Volta Lake will be introduced by year 2015, which is around the time when shortages at Koforidua is being realised again as documented in the scenario analyses presented above.

As an integral part of this scheme, it is proposed to construct a transmission line from this new water transfer pipeline to the Old/New Tafo demand sites to curtail the se- vere water shortages experienced in this part of the basin. When the new transmis- sion line is operational, this scenario calls for an abandonment of the New Tafo water abstraction at the present intake (New Tafo Dam) on the Beira tributary. Result : A sequence of model runs were made aimed at finding the appropriate pipe capacity required to fulfil the future water requirements for this expanded (combined) scheme. The outcome of calculations indicates that to attain a satisfactory coverage level, the proposed second transmission pipe from Volta Lake to serve both the Koforidua and Tafo areas, and hence reducing the abstraction requirements from the Densu river it- self, should be some 2.5 to 3 three times the capacity of the transmission main pres- ently being designed.

The percentage of requirements met (coverage rate) for this scenario is presented in Table 3.9 below. The figures obtained are from the model run in which the second transmission pipe has a capacity of 37,000 m3/day and as mentioned earlier is as- sumed to be operational from year 2015.

Scenario 7: New dam on the Densu River upstream of Koforidua As an alternative to constructing a second water transfer pipeline from Volta Lake, it is in this scenario proposed - in addition to the first water transfer from Volta Lake as outlined in Scenario 6 above - to build a new dam on the Densu River a few kilome- tres upstream of the present Koforidua water intake site. Like above, it is envisaged that this dam should be operational from year 2015.

May 2007 Page 52 Water Resources Commission Densu River Basin IWRM Plan

Result : The result of the model run for this scenario indicates that to attain a satisfactory coverage level towards the end of the plan period, the Koforidua New Dam should be sized to create a reservoir of about 8 million m 3 storage volume 22 . Water abstractions for the water demand centres of Koforidua and Old/New Tafo will both take place from the new reservoir. When the new dam and new transmission lines to the two demand sites are in place, the existing Tafo abstraction site as well as the water in- take for Koforidua water supply on the Densu River can both be abandoned, whereas the existing Koforidua treatment facilities appropriately can be maintained for proc- essing of raw water now to be delivered (pumped) from the new reservoir.

The percentage of requirements met (coverage rate) for this scenario is also pre- sented in Table 3.9.

To get an indication about the required size of the new dam (impact on the storage volume) in relation to a different river runoff regime, a model run was also made for a situation where a likely climate change will not occur. In this case, a much smaller dam of about 3.5 million m 3 storage volume would be required to provide 100% cov- erage at the two demand centres towards the end of the plan period.

Table 3.9: Coverage rate, alternative options (Scenarios 6 and 7) Demand site (by end of plan period) Scenario Weija Apedwa Tafo Koforidua Nsawam Lake 6. Additional water transfer from 43% 94% 97% 100% 100% Volta Lake

7. New dam on the Densu River upstream of Koforidua present 43% 98% 99% 98% 100% intake

3.4.3 Overall assessment based on the scenario analyses Considering availability of water only, i.e. without taking into account the various technical infrastructure requirements in abstracting and transmitting and distributing the water to consumers, and not the least the economic and financial consequences, the scenario analyses have highlighted that it is particularly in the northern half of the Densu Basin, where water resource utilisation measures need to be put in place to meet future requirements of the people residing in the Basin and to maintain the growing socio-economic, industrial and agricultural activities being realised.

If a climate change impact is not taken into consideration, the analysis also indicates that downstream of the Kuia-Densu river confluence, water availability appears suf- ficient for the projected requirements of the Nsawam demand site and other urban

22 A preliminary field reconnaissance revealed that the maximum size of a dam (reservoir) to be constructed at this upstream site on the Densu river is about 10 million m 3.

May 2007 Page 53 Water Resources Commission Densu River Basin IWRM Plan

communities in the Akwapim South district without introducing any specific water resource utilisation schemes. Furthermore, the storage capacity of the Weija reservoir is large enough to provide for the water required at the Weija Water Works, also af- ter the ongoing expansion works are completed with the present water abstraction of 200,000 m 3/day to be boosted to 268,000 m 3/day (and then kept constant at this rate throughout the plan period).

As mentioned previously, in the alternative water resource scenario analyses, which provide the basis for making assessment about to which extent water requirements are met, minimum (environmental) flow requirements, water scheme and distribution losses, and importantly, impacts of a likely climate change are all included.

Based on the scenario analyses, an assessment of the general situation at each major demand site suggests options concerning utilisation and development of the water re- sources, as follows: • The Apedwa demand site and adjacent future urban communities in parts of East Akim district will have to rely on piped groundwater/spring supply, which for best yield conditions should tap water from aquifers in the Birimian geological formation located relatively close by in the north-westerly part of the Basin. • The various demand sites within and adjacent to the New and Old Tafo areas (including future urban communities in the eastern part of East Akim district) and Koforidua town (including future urban communities in the western parts of New Juabeng and Akwapim North districts) are proposed in the future to be supplied by one scheme. The water requirements for such “dual” expanded scheme can be met either (i) by adding an extra water transfer pipeline from Volta Lake to be laid in parallel with the transmission line about to be con- structed, or (ii) by construction of a new dam located a few kilometres upstream of Koforidua on the Densu River. The idea is to connect both the Koforidua and Tafo areas with transmission pipes (pumping mains) branching off from the sec- ond transmission pipeline from the Volta Lake or directly from the new reservoir site, depending on which alternative scheme configuration will be decided on. • As far as the Nsawam demand site (including future urban communities in the western part of the Akwapim South district) is concerned the water availability situation needs to be looked at cautiously when approaching the latter part of the plan period. Firstly, it is recommended to change the stated operational policy in which the Densu river will have precedence over the Volta Lake water (when the 13,600 m3/day capacity pumping scheme is operational) to a strategy whereby the Densu river rather will be used to supplement the water pumped across from Volta Lake. This will “save” water in the Densu river for the benefit of the Nsa- wam water supply scheme too. Secondly, it is also recommended to introduce piped groundwater-based supply schemes to supplement and, hence, alleviate the stress on the river source in this part of the basin.

May 2007 Page 54 Water Resources Commission Densu River Basin IWRM Plan

• The favourable prospects for groundwater exploitation in the district of Su- hum/Kraboa/Coaltar points to a scenario in which half of the district population can be assumed to be served appropriately by piped groundwater supply schemes and the other half from surface water with a proposed intake site on the Kuia tributary to be located in the vicinity of Asuboi. • Concerning the southern heavily populated part of the Basin it is assumed that the Weija dam/treatment facilities – after the ongoing expansion works and gradual extension of the distribution network are being realised – to a large ex- tent will serve the sprawling urban population south of the Akwapim South and Suhum/Kraboa/Coaltar districts (within the basin boundaries). The Ga West dis- trict alone is projected by 2020 to host about 75% of the total urban population residing in the Densu basin. Also in this part of the basin it is recommended to introduce piped groundwater-based supply schemes to supplement and thus alle- viate the stress on the Weija reservoir as the sole source. • Finally, is should be mentioned that in the utilisation of the Basin’s water re- sources, it is assumed that the rural population also in the future to a large extent will continue to be supplied from groundwater through non-piped handpump equipped boreholes or through piped (mechanised) borehole supply schemes.

In parallel to these developments, it is paramount that efforts are being introduced more vigorously to bring down the unacceptable high rate of un-accounted for water (water supply system losses). A number of measures exist to assist towards the re- duction of physical losses, some of which can be implemented by the service pro- vider (GWCL), e.g. leakage detection/repair and renovation of old distribution net- work, and other measures which direct themselves more to the consumers, that be in- dustrial, institutional and individual users. In this context, the number of illegal con- nections needs also to be addressed.

The introduction of water demand management measures is also an important aspect in curtailing the otherwise ever increasing demand. In the water demand projections presented above, the departure point in the calculations is a list of pre-set unit con- sumption figures (ref. Table 3.1). The aim must be to halt the continuously increas- ing trend as reflected in the table values through measures, including public aware- ness raising, which should address e.g. behavioural changes towards being “water- wise” individually and collectively, and being conscious about water (ab)uses.

Other measures which should be considered include changes to building codes to make it mandatory to install water-saving devices (self-closing taps, low-flush toilets etc) particularly in public buildings, boarding schools, military barracks and other large building complexes. Additionally, the introduction of roof catchment systems for rainwater harvesting meant for washing, garden watering and other “grey water” purposes should be promoted.

May 2007 Page 55 Water Resources Commission Densu River Basin IWRM Plan

Map 3.1: Schematic overview of main elements in Densu WEAP model

May 2007 Page 56 Water Resources Commission Densu River Basin IWRM Plan

4. CONSULTATIVE PROCESS

4.1 SEA applied in the IWRM planning process

This IWRM plan is based on hydrological and other technical data, socio-economic trend analysis, and population census information that only partly has been presented earlier and not as an integrated assessment with the purpose of describing the present and future situation within the Densu Basin concerning the availibility and quality of the water resources.

In parallel with the technical assessments and description of the water resource- related challenges as presented in Chapters 2 and 3, a consultative process has been carried out with the involvement of basin-based stakeholders aimed at capturing the local perception and actions required in addressing the identified water management issues and problems areas.

In the Ghanaian context well anchored procedures exist whereby plans and pro- grammes are elaborated and vetted following a participatory approach allowing for thorough public discussions – often in workshop settings – guided by principles which form part of the concept named Strategic Environmental Assessment (SEA). SEA procedures and tools 23 have been adapted and applied as part of the Densu Ba- sin IWRM planning process.

A SEA approach for planning is defined as:

“A systematic process of evaluating the environmental effects of a policy, plan or programme and its alternatives, including documentation on findings to be used in publicly accountable decision-making”.

Furthermore, the application of SEA procedures in IWRM planning means that the evaluation of environmental effects has an additional social dimension, viz.:

“…to safeguard the future sustainable use of water resources aimed at maintaining the economic and social welfare within a basin without compromising the preserva- tion of vital aquatic ecosystems”.

The district-based planning by District Assemblies is the cornerstone of the decen- tralised governmental approach for which the overall legal framework and institu-

23 Support and Capacity Building to apply SEA Principles and Tools in preparing IWRM Plans at River Basin Level. WRC (October 2006).

May 2007 Page 57 Water Resources Commission Densu River Basin IWRM Plan

tional delegation of responsibilities are proven and understood - although gaps in leg- islation, overlapping responsibilities, lack of capacity/resources and enforcement still exist.

An IWRM plan for a basin addresses the basin-wide water management problems to be taken into account to achieve a future sustainable management of the basin’s wa- ter resources, and as such provide a framework for local water management planning at district level.

Consequently, the effects of the IWRM plan should not be restricted to a description of broad existing and projected future environmental and social impacts, but should also try to describe the effects of the IWRM planning on other existing plans and programmes. The IWRM plan may entail legal and institutional consequences that might cause conflicting management structures, which then need to be coordinated and adjusted to ensure an efficient implementation of the plan.

4.2 IWRM issues and problems as identified by stakeholders

In adherence with the SEA principles and embracing a participatory approach, a number of stakeholder meetings with planners from District Assemblies, governmental departments, Densu Basin Board and water user organisations were convened by WRC during elaboration of the IWRM Plan.

Table 4.1 presents the identified issues and problems within the Densu Basin as per- ceived and ranked at a stakeholder workshop at the onset of the IWRM planning process. The information in the table reflects the answers as provided by four work- ing groups, which the workshop participants were divided into.

May 2007 Page 58 Water Resources Commission Densu River Basin IWRM Plan

Table 4.1: Ranking of IWRM problems as formulated at initial stakeholder workshop Planners from Planners from Planners from Members of Akwapim North and Ga West Akwapim South, Akim East and Suhum-Kraboa-Coaltar, Atewa and Densu Basin Board Districts Akim West Districts Awutu-Effutu-Senya Districts Ranked list of problems (11) Ranked list of problems (10) Ranked list of problems (10) Ranked list of problems (15) 1. Clearing of vegetation along river 1. Lumbering and indiscriminate 1. Bush clearance and burning which 1. Improper solid and liquid waste banks, which affects the run-off farming activities in the watershed. expose the land to soil erosion and management. pattern. 2. Dumping of liquid and solid waste silting of water channels. 2. Farming close to the river banks. 2. Dumping of solid and liquid waste into the river. 2. Dumping of solid and liquid waste 3. Use of unapproved agro-chemicals. 3. Use of chemicals and other 3. Water pollution due to activities of into streams and rivers. 4. Use of harmful chemicals for fishing. undesirable methods of fishing. small and medium scale miners. 3. Farming along riverbanks. 5. Indiscriminate felling of trees. 4. Building beyond the buffer zones. 4. Lack of community support to 4. Felling of trees for charcoal 6. Encroachment of reserve areas. 5. Water vegetation, which disrupts watershed management. production. 7. Lack of harmonized buffer zone smooth flow etc. 5. Pollution from stray animals. 5. Pollution from domestic animals policy. 6. Lack of alternative livelihoods for 6. Proliferation of aquatic weeds in especially cattle drinking from 8. Lack of institutional capacity by communities. the watercourse. rivers. DA’s. 7. Conflicting activities in various 7. Expansion of residential housing 6. Non-implementation of physical 9. Lack of awareness among residents districts, which may work against developments close to river banks. plans by District Assemblies about water management. integrated development of the 8. Use of unauthorized fishing leaving most towns and villages 10. Lack of political will to enforce basin. methods, e.g. use of chemicals and with poor drainage systems. development control. 8. Sand winning close to the explosives. 7. Surface mining and washing of 11. Deforestation in the upper reaches of riverbed, which affects river flow. 9. Health hazards from onchocerchi- minerals with poisonous chemi- the basin. 9. Water borne diseases, e.g. buruli asis and bilharzias. cals in streams polluting the water. 12. Building/construction activities near ulcer, bilharzias etc. 10. Periodic flooding caused by 8. Land tenure problems especially the river banks. 10. Lack of access between communi- siltation. in connection with acquisition of 13. Mining sites, e.g. bauxite mining. ties on both sides of the river, e.g. suitable sites for water facilities. 14. Discharge of industrial waste in risk of children crossing to school. 9. Weed growth in the river that water course. 11. Low level of women’s involve- causes pollution and reduce vol- 15. Inadequate water resources (water ment in water management activi- ume of water in basins. availability) in the basin. ties. 10. Use of poisonous chemicals for fishing.

May 2007 Page 59 Water Resources Commission Densu River Basin IWRM Plan

It can be concluded from the table that: • a diversity in opinion exists among stakeholders as to the main problems to be addressed and how they should be prioritised; and • main issues to be addressed are based on individual perceptions of problems in everyday life without a view to implications for the Basin as a whole and future development trends.

For compilation of the findings from the SEA meetings, the following categories were applied in accordance with commonly used criteria for description of the sus- tainable development in Ghana with reference to issues on: • natural resources, • social and cultural conditions, • economy, and • regulatory, administrative and institutional conditions.

In summary, the problems to be addressed can be grouped as shown in Table 4.2. The numbers indicate how often a specific category of problem was counted among individual members of the working groups (ref. Table 4.1).

Table 4.2: Main categories of identified problems Category of problem No. Natural Resources 46 Protection of river banks 8 Forests and protected areas 7 Farming and farming methods 6 Inappropriate fishing and fishing methods 6 Waste disposal 6 Effects of mining 3 Water pollution and quality 3 Water weed 3 Domestic animals 2 Flooding 1 Availability of water resources 1 Social cultural conditions 5 Water-borne diseases 2 Alternative livelihood, land tenure and land use 1 Women’s participation 1 Crossing of streams/rivers 1 Economy 0 - 0 Regulatory, administrative and institutional 5 Lack of resources and capacity 2 Enforcement 2 Prevention and resolution of water related conflicts 1

May 2007 Page 60 Water Resources Commission Densu River Basin IWRM Plan

Based on the summarised presentation of the identified problems in Table 4.2, it can be concluded that: • most attention is paid to problems related to management of natural resources, but the availability of water within the basin, which is one of the main focus ar- eas of the IWRM planning, is not perceived as a major concern; • the awareness of existing regulating instruments and delegated responsibilities are not obvious, as a number of problems proposed to be addressed falls within already existing management structures; • economy as the main tool for initiating any new or additional management ac- tivities is not addressed as a problem at all; and • lack of resources and capacity, lack of enforcement and lack of coordination among institutions are to some extent seen as the reason for management prob- lems within the basin, but not as described above, as a consequence of insuffi- cient economic resources.

4.3 Existing legal and institutional framework

Implementation of the IWRM plan should address the findings from consultations, but additionally, will need further assessments beyond the articulated (local) percep- tion of the IWRM issues.

For this purpose, the existing legal framework as well as already established institu- tional responsibilities and enforcement practices are outlined in Table 4.3 24 (6 pages) below to help in identification of procedures and actions needed for an efficient im- plementation of the IWRM plan, particularly as it relates to role of various involved partners (institutions, agencies, departments etc.). The description in the table below is listed in accordance with the identified water management problems as given in Table 4.2 above.

24 Based partly on: Assessment of Water Governance in Ghana. Meta-Meta Research and Nii Consult (draft report, January 2006).

May 2007 Page 61 Water Resources Commission Densu River Basin IWRM Plan

Table 4.3: Existing regulatory framework and institutional responsibilities in IWRM

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies Natural 46 Resources Protection of 8 There is no official policy on river banks protection, even if Protection of river banks does not necessarily In WRC an Inspectorate division exists (as river banks the problem is a matter of much concern and discussion. require planning when legal requirements per Water Use Regulations 2001, LI 1692) Land Planning and Soil Conservation Ordinance 1953 (Cap and guidelines for protection of river banks but it is not operational. When the 32) mandates a Minister to designate areas for protection of have been established. Control and Inspectorate Division is made operational and the environment including river banks, rivers and dams. enforcement of regulations will be the main guidelines or more legally binding Regulations for river banks protection will need the issue regulations for protection of river banks are involvement of the Lands Commission. The Lands introduced agreements must be made on how Commission Act 483 1994 mandates the Land Commission to segregate the controlling activities between to manage public land vested with the president and to WRC and controlling activities in district advise authorities at all levels of public administration, administrations traditional authorities and private land owner organisations on land use planning. Forests and 7 Land Planning and Soil Conservation Ordinance 1953 (Cap Protection and establishment of forests and When land use planning will be introduced as protected areas 32) mandates a Minister to designate areas for protection of protected areas may in the future be a part of IWRM planning it must be the environment including river banks, rivers and dams planning tool for protection of ground and coordinated with the activities of the Lands generally and also to designate areas for reforestation. surface water resources as well as water Commission and the Forestry Commission Forests Ordinance 1927 (Cap 157) delegates the right to quality. In that case protection of forests and establish forest reserves to safeguard water supply within the establishing of forest reserves may be Districts. considered as a special case of land use Lands Commission Act 483 of 1994 mandates the Land planning within IWRM planning to be Commission to manage public land vested with the president coordinated with the Lands Commission and to advise authorities at all levels of public administration and traditional authorities on land use planning. WRC Act 522 of 1996 (Section 31) provides for special measures to be introduced by the Minister for protection of water resources by declaring an area to be a protected catchment area. Farming and 6 Ministry of Agriculture teaches farmers farming methods With Lands, Forestry and Minerals MOFA, Extension Services, EPA, at District farming methods that reduce land degradation Commissions and District Assemblies level. Inappropriate 6 The Fisheries Law PNDCL 256 of 1991 and the Fisheries Irregular fishing does not require planning WRC has the overall responsibility to advice

May 2007 Page 62 Water Resources Commission Densu River Basin IWRM Plan

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies fishing and Commission Act 457 of 1993 provide for the regulation and or coordination with other plans and on regulation of water impacts within the fishing methods management of the utilisation of the fishery resources of programmes but control for enforcement of basin. Ghana and the coordination of policies in relation to them, regulations. WRC Inspectorate Division in WRC is not and hence, to some extent regulate fishing methods and yet operational. When resources will be environmental effects from fishing. allocated for controlling activities of the Inspectorate it will still be needed to agree with the Districts and Fisheries Commission on how to distribute responsibilities for controlling fishing methods. Waste disposal 6 The National Development Planning Commission Act 479 of It is under the mandate of the District It is the task of WRC to advice on control of 1994 provides the legal background for NDPC to provide Assemblies to provide waste disposal plans impacts from waste disposal on water bodies. guidelines for district planning including planning of waste and to allocate waste disposal sites. Controlling activities of districts on waste disposal. disposal for protection of water bodies needs The Local Government Act 462 of 1993 delegates planning coordination and clarification, when the responsibilities on waste to District Assemblies Inspectorate Division in WRC is made fully The WRC Act 522 of 1996 appoints WRC to advise control operational. agencies to prescribe acceptable levels of pollution also from waste disposal sites. Effects of mining 3 The Minerals and Mining Law PNDCL 153 of 1986 Irregular use and pollution of water from Should be regulated through campaigning stipulates some regulation of environmental effects and use mining does not require planning or and awareness creation mining compa- of water for mining activities. Water to be used for mining coordination with other plans and nies/miners and controlling of licenses. activities requires a license. programmes, but rather compliance The role of WRC concerning control of WRC is expected to issue licenses on water use under Water monitoring for enforcement of regulations. impacts from mining activities on water Use Regulations 2001, LI 1692. bodies needs clarification. The effluent discharges have to be approved by EPA under LI 1652 of 1999. Water quality 3 No specific laws regulate water quality and control of WRC is the advising and planning agency on The WRC and EPA collaborate as stipulated and pollution pollution. The EPA Act 490 empowers EPA to stipulate water pollution control and of water quality, in a Memorandum of Understanding to fulfil standards on water quality issues, and to be in charge of and through a Memorandum of Understand- the role to monitor compliance with waste issuance of waste discharge permits. The WRC Act 522 ing collaborates with EPA on issuance of discharge permits. appoints WRC to advise control agencies to prescribe waste discharge permits. When the Inspectorate Division under WRC acceptable levels of water pollution. In conjunction with NDPC to provide is fully operational, the distribution of The NDPC Act 479 of 1994 mandates NDPC to provide guidelines for planning of water supply controlling responsibilities must be agreed on guidelines for district planning on water and sanitation. facilities to local communities, there is also a and segregated from similar activities in Local Government Act 462 of 1993 delegates planning of need for coordination of plans and districts.

May 2007 Page 63 Water Resources Commission Densu River Basin IWRM Plan

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies water and sanitation to District Assemblies and other local programmes with activities of WRC and visa authorities. versa. Water weeds 3 A National Water Weeds Control Committee is hosted by Regulation of water weeds does not require The role of WRC on regulation of water EPA. However, regulation of water weeds is expected to be planning, but monitoring and initiation of weeds in relation to local executing a special case of regulating water quality and control of actions and measures to curb the infestation. authorities needs clarification pollution, and as such to be regulated through the WRC Act 522 of 1996. Domestic 2 Water pollution effects from domestic animals searching for Regulation of the behavioural effects from Water effects from stray animals should be animals drinking water is a special case of water pollution that in stray animals needs no planning regulated through campaigning and principle should be handled under WRC Act 522 and Local awareness creation of owners of animals by Government Act 462 as described above. district authorities, MOFA extension officers etc. Flooding 1 WRC Act 522 assigns WRC to regulate and manage water Planning of flood control should be an Control of flood and implementation of flood resources within river basins. integral part an IWRM plan to be provided control measures need clarification among Standard Engineering code of practice requires that by WRC and coordinated with GWCL, WRC, CWSA, GWCL, IDA, HSD and provision be made that part of a dam’s storage capacity is set CWSA, IDA in rural settings and HSD on MDAs. aside for flood control. Hence, IDA, GWCL and others are primary drains in urban areas. Also mandated to make such provision. HSD by administrative coordination with metro-, municipal and arrangements is responsible for flood control in primary district assemblies over secondary and drains in urban areas. tertiary drains in urban areas is needed. Availability of 1 WRC Act 522 of 1996 assigns WRC to regulate and manage WRC is responsible for IWRM planning District Assembly plans address water use, water water resources within river basins. within the basin to ensure the availability of but these plans are not yet linked to the resources Local Government Act 462 of 1993 delegates planning of water in cooperation with districts and water basin-based IWRM planning. water and sanitation and implementation of plans and service providers. Licensing of water permits is the tool for programmes to District Assemblies and other local NDPC provides the guidelines for planning regulating water use and, hence, for water authorities. The Public Utilities Regulatory Commission and use of water resources in the districts resource management. (PURC) Regulations (LI 1651 of 1999) mandates PURC to There is a need for coordination of Densu Basin Board under WRC constitutes a regulate the activities of public water utilities providing guidelines, plans and programmes on water broad spectrum of representatives of water to consumers. use between organisations concerning water stakeholder organisations within the basin, GWCL is working under the jurisdiction of PURC, but plans availability. including district and regional authorities, the availability of water for all major piped water supply water service providers (GWCL and CWSA), schemes, including the use of water from the Weija Dam for NGOs and ministerial departments. the Metro Accra area. Under the Water Use Regulations (LI However, as a new planning approach, there 1692 of 2001) of the WRC all agencies or water abstractors is a need to clarify how IWRM planning as a must be registered and their abstractions granted by licence. basin-wide activity shall be addressed in

May 2007 Page 64 Water Resources Commission Densu River Basin IWRM Plan

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies district planning, and for that matter in connection with planning by other organisations. The planning in districts is based on coordination and guidelines of NDPC, which also has a unit to monitor implementation of district plans. As it is now, IWRM planning by WRC is not coordinated and monitored by NDPC, and the same goes for GWCL planning activities. Social cultural 5 conditions Water-borne 2 Local Government Act 462 of 1993 delegates regulation of Planning of measures to prevent water-borne Campaigning on behavioural change is the diseases water hygiene and sanitation aspects to District Assemblies diseases is addressed in local hygiene and controlling tool and compliance monitoring and other local authorities. sanitation planning. of regulations is the task of local authorities. Alternative 1 Lands Commission Act 483 of 1994 mandates the Land Land use planning to regulate water use for The Lands Commission has only an advisory livelihood, land Commission to manage public land vested with the irrigation and other heavily consuming water role on private owned land. At present the tenure and land president, and to advise authorities at all levels of public activities, protection of the environment and existing traditional administration of land as use administration and traditional authorities on land use pollution from industries in specific areas well as land use practices may conflict with planning. may be an instrument to include in future public land use planning and traditional Land Planning and Soil Conservation Ordinance 1953 (Cap coordinated IWRM planning activities. private property rights. A control system on 32) mandates a Minister to designate areas for protection of land use and land use planning does not exist the environment, including river banks and surface waters in at present. general, and also to designate public land for reforestation. Presently, the EPA Act regulates general environmental protection, the WRC Act was enacted to manage the use of water resources and river catchments, and the Forestry Commission to manage the activities in relation to forests, their conservation and reforestation. Women’s 1 It is part of the National Water Policy to promote the Women’s organisations are as stipulated in Campaigning on women’s participation in participation participation of women to meet their needs and to use their the Act represented in WRC and in Densu water management at all levels of public experience in water supply/management, specifically at local Basin Board. administration is the tool used for women’s level. participation in water management practises Crossing of 1 Planning and management of minor infrastructure facilities Procedures to ensure proper access to new Users of new facilities in everyday life are streams/ rivers for crossing water courses should be an integral part of and planned facilities are included in the controlling actors to ensure proper

May 2007 Page 65 Water Resources Commission Densu River Basin IWRM Plan

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies district planning and is regulated through Local Government guidelines to local planners to ensure a services. Act 462 and NDPC guidelines on planning. coherent implementation.

Economy 0

The WRC Act 522 of 1996 delegates the right for WRC to For implementation of the IWRM plan there WRC, PURC, GWCL, CWSA and IDA will generate revenue from issuing of water use permits (Water is at the moment no financing capacity have to agree on a common system for Resources Management Account). The PURC Act (LI 1651 except for revenue from issuing of permits in financing of activities within the basin. of 1999) delegates the responsibility to the Public Utilities WRC. The IWRM plan addresses problems Regulatory Commission to regulate urban water tariff rates to be solved within the whole basin. 0 - and structures. CWSA Guidelines of 2005 provides for tariff Accordingly, the availability of resources and settings for water services in rural areas and communi- capacity will require financial resources ties/small towns. At present, resources for capacity building based on either additional consolidated within the water sector is predominantly made available budget allocations and/or other water user through donor funding. contributions within the basin. Regulatory, administrative 5 and institu- tional Lack of 2 Lack of resources and capacity is considered mostly as a See above under economy See above under economy resources and consequence of the economic situation within the water capacity sector - existing regulatory mechanisms are as such described above under economy. Enforcement 2 Lack of enforcement is partly considered as a consequence IWRM planning is a new activity. It is the A scheduled and prioritised set of actions to of not sufficient resources and capacity, and not clearly scope of the IWRM plan to describe the solve possible conflicts with other planning demarcated delegation of institutional responsibilities that impact on other plans and programmes, and and programmes is part of the IWRM needs clarification. consequently to plan and coordinate planning aimed at ensuring a stepwise and activities to solve possible conflicts within long-term implementation of the plan in close existing legislation, and to clarify delegation collaboration with other stakeholders in the of responsibilities. water sector. Prevention and 1 All major stakeholder authorities and water user representa- The IWRM plan is not only intended for For resolution and clarification of specific resolution of tive organisations are presented on the Densu Basin Board water management, but also for coordination problems, WRC can establish sub- water related and in the WRC in accordance with requirements in WRC and conflict resolution with other plans and committees with specific mandates for conflicts Act 552. WRC can for discharge of its functions establish programmes to ensure an efficient discharge of its functions. Such sub-

May 2007 Page 66 Water Resources Commission Densu River Basin IWRM Plan

Category of Planning authorities and coordination Controlling activities and responsible No. Existing regulatory mechanisms problem with other plans and programmes institutions/agencies sub-committees as stipulated in the Act. implementation of the plan. committees may be the basis for conflict resolution and clarification in relation to IWRM planning and water resource utilisation.

May 2007 Page 67 Water Resources Commission Densu River Basin IWRM Plan

4.4 Prioritisation of problems and delegation of responsibilities

The actions and mitigating measures required to address the variety of problems identified during the consultative process need to be implemented by different actors (“who does what”). For that reason, a ranking procedure based on scoring tables with the purpose of making a separation and delegation of responsibilities was prepared and subsequently used at a consultative meeting with selected stakeholders including the Densu Basin Board. The procedure used questionnaires applied in working groups to make a distinction 25 between - • management of basin-wide problems that need to be addressed with a holistic, coordinated and integrated approach, where the introduction of mitigation meas- ures interacts with problems to be solved elsewhere in the basin (addressing measures targeting such problems is part of WRC’s responsibility); and • management of local, but commonly encountered problems within the basin, where the introduction of mitigation measures predominantly has a local effect (measures targeting such problems are part of the District Assemblies’ imple- mentation responsibility, but may need coordination through activities supported by WRC and/or Densu Basin Board).

In preparing the questionnaire and scoring table the categories of problems identified at the initial stakeholder workshop were revisited and in some cases supplemented with additional information, for instance in light of the results generated from the water balance scenario analyses, to clarify and expand the problem formulation for the stakeholders.

In Table 4.4 below the results from this SEA-guided second stakeholder consulta- tions are summarised with the scores obtained for prioritisation of problems to be managed either using a basin-wide or a local district-based approach.

Some general conclusions from this phase of consultations can be listed as follows: • the distinction between basin-wide and local problems was not immediately un- derstood and needed clarification and discussion; • the present and future availability of water was considered as a major problem to be addressed on a basin-wide basis (contrary to what was the case at the initial stakeholder meeting); and • the promotion of good governance, democratic principles and transparency in decision-making in water management was considered a valued supplementary aspect to be included as and when found appropriate in the IWRM planning process.

25 Procedures for making a distinction between cross-cutting basin wide problems and local problems are given in Reference 23 (see Section 4.1 above).

May 2007 Page 68 Water Resources Commission Densu River Basin IWRM Plan

Table 4.4: Result of tool application to identify delegation of responsibilities Initial categories Clarifying formulation Score of problems of problems Natural Resources -The availability of water to Metro Accra area 14 The availability of water resources -The availability of surface water 12 -The availability of groundwater 7 -Management of waste water discharges 8 The quality and pollution of water -Management of water quality 8 -Protection of “red list” species 7 Forests and protected areas -Reforestation 7 Flooding -Including flood management 7 Protection of river banks -Including rehabilitation of river banks 7 Farming and farming methods -Including soil degradation 7 Waste disposal See under quality and pollution of water 6 -Including fishing methods and effects on Fishing and fishing methods 5 environmental conditions Water weeds See under quality and pollution of water - Small-scale mining See under quality and pollution of water - Social cultural conditions -Including need for attitudinal and behav- Water borne diseases 8 ioural change -Traditional and benign cultural and gender Women’s participation 6 practises Alternative livelihood, land tenure -Land use and land use planning 6 and land use planning

Economy

-Distribution of costs for initiation and 12 implementation of basin wide planning

Economy and financing of basin- -Assessment procedures and tools for 12 wide initiatives prioritisation and financing of measures

-Procedures for efficient collection of 6 payments for water services Regulatory, administrative and

institutional -Enforcement of decisions for initiation of basin-wide initiatives 11 - Enforcement of rights and obligations of Enforcement and good water land owners 7 governance - promotion of good water governance, transparency in information sharing and 14 decision-making Prevention and resolution of water -Institutional collaboration and capacity 11 related conflicts building Lack of resources and capacity See under economy -

May 2007 Page 69 Water Resources Commission Densu River Basin IWRM Plan

Based on experience from similar applications of this tool, it can be stated in general terms that scores falling in the range of 7 and above indicate basin-wide problems, whereas problems with scores below 7 can be categorised to be of local nature, al- though rather commonly encountered in the basin.

Therefore, the scores as presented in Table 4.4 provide a means to distinguish be- tween the two levels of planning, and where responsibilities should be placed and tasks assigned in addressing the identified IWRM problems. Nevertheless, in some instances, it is also evident - regardless of the scores - that both planning levels in one way or another will be involved. The result of this exercise is given in Table 4.5.

Table 4.5: Prioritisation of water management problems Priori- Problem/issue Magnitude (extent) tisation to be addressed of problem

1 Water availability Basin-wide management problem Prevention and resolution of water related 2 Basin-wide + local management problem conflicts

3 Enforcement and good governance Basin-wide management problem

Economy, financing and lack of re- 4 Basin-wide management problem sources/capacity Water quality, pollution of water and 5 Basin-wide management problem waste disposal 6 Water-borne diseases and sanitation Local management problem

7 Forests and protected areas Basin-wide + local management problem

8 Farming and farming methods Basin-wide + local management problem

9 Protection of river banks Basin-wide + local management problem

10 Flooding Basin-wide management problem

11 Water weeds infestation Local management problem

12 Small-scale mining Local management problem

Women’s participation in water manage- 13 Local management problem ment Livelihood, land tenure and land use 14 Basin-wide management problem planning

15 Fishing and fishing methods Local management problem

The next step in the process is for each of the above listed IWRM problems/issues to define specific actions to address the specific issues. This part of the IWRM plan is elaborated on in the following Chapter 5.

May 2007 Page 70 Water Resources Commission Densu River Basin IWRM Plan

5. ACTION PROGRAMME

5.1 Introduction

The Densu River is arguably a highly stressed water source and one of the most exploited rivers in Ghana. As highlighted in the previous chapters, the environmental health of the basin and the river’s role as an indispensable source for supply of water are threatened in various ways such as: − indicriminate harvesting of wood from its source to below midstream of the system, − farming along the banks of the river and at its headwaters, − use of agrochemicals in mechanised farming and harmful chemicals in fishing, − infrastructural development and urbanisation which unabated evade large portions of the basin without physical/land use plans or zoning principles being followed, − inappropriate disposal of solid and liquid waste from domestic and industrial sources into the river course, − sand winning, quarying and other smale-scale mining in the basin, and − ever increasing water abstractions for domestic water supply, industrial purposes and irrigation to the extent that dry season flows cease in certain portions of the Basin.

It is against this background that the Densu River Basin IWRM Plan has been prepared and in line with stipulations in the WRC Act 522 (1996) to “propose comprehensive plans for utilisation, conservation, development and improvement of water resources.”

During preparation of the IWRM plan, two concurrently running – and equally important – paths have been followed, i.e. (i) an assessment with scenario analyses incorporating technical water resource (hydrologic) characteristics to highlight water availability versus future requirements, and (ii) a SEA-driven approach aimed at identifying the water management problems from a basin-based stakeholder perception. In the present chapter both information sources have been used in bringing together an action programme comprising of a number of prioritised activities and measures for implementation to meet various of the IWRM challenges.

At this stage, the required resources (concerning financing and institutional capacity) to implement the IWRM plan and its associated activities have not been addressed.

5.2 Actions identified to address the IWRM problems

For each of the fifteen IWRM problems/issues listed in Table 4.5, a number of specific actions (measures) have been defined to constitute the core of the IWRM

May 2007 Page 71 Water Resources Commission Densu River Basin IWRM Plan

plan implementation (the action programme). These actions are presented in Table 5.1 below (5 pages).

The table also provides information related to which institution, agency and/or authority should be involved, and which one should be responsible partner in initiating and overseeing imlementation of the actions. This latter information is derived from the consultative process as explained in the previous chapter.

In addtion to the action programme outlined in Table 5.1, other more localised IWRM activities need to be carried forward supported at DA level, but initiated and implemented at lower levels, e.g. by institutions and/or communities. Specifically the following three activities can be grouped in this category: − More systematic introduction of rainwater harvesting, that be from naturally occuring improved mini-catchment and construction of roof harvesting systems at schools, barracks or other larger buildings (industries). − Construction of dug-outs and/or small earth embankments to store water primarily for farming purpose, that be for small-scale irrigation or cattle watering. − More vigorous promotion of sound environmental sanitation practices at household level, e.g. by encouraging building of VIP latrines, and promoting modern technology to dispose of liquid waste and use of biogas toilet systems.

It can be seen that the action programme includes a broad range of activities, which all – in one way or another – facilitate and assist towards achieving the main aim of bringing the Densu River Basin and its water resources back to an acceptable quality level, and to a state in which an ecological and water resource utilisation balance ex- ists for future sustainable socio-economic development within the Basin.

May 2007 Page 72 Water Resources Commission Densu River Basin IWRM Plan

Table 5.1: Proposed actions for addressing identified IWRM issues/problems Involved Actions/measures Purpose Responsible partner(s) parties Issue/problem: Water availability Use results from the water demand/ water availability -to be taken into account in future district WRC, GWCL, IDA General, basin-wide issue, i.e. scenario analyses to prepare strategy on how to meet the planning; and others responsibility of WRC to address and future water requirements of the Densu basin. The - to be applied as a framework for WRC initiate action on. scenarios take into account stronger emphasis on licensing of water permits; groundwater utilisation, environmental flow require- - to engage in a dialogue with particularly ments, possible impact of climate change, inter-basin GWCL, and larger irrigation and industrial water transfer, new storage (reservoir) facility upstream enterprises. in the Densu basin and additional abstractions from the Weija reservoir. Through further studies provide evidence for increased - to argue for and justify the strategy that WRC, WRI, General, basin-wide issue, i.e. reliance on groundwater (geographical location of high groundwater should be used increasingly GWCL, CWSA responsibility of WRC to address and yielding formations, aquifer vulnerability, etc). in water supply schemes for urban initiate action on. communities. Prepare guidelines on institutionalising water demand - to find alternative means and ways of WRC, GWCL, General, basin-wide issue, i.e. management measures (to reduce un-accounted for reducing the reliance on the Densu river. CWSA, DAs responsibility of WRC to address and water) and promotion of rainwater harvesting systems. initiate action on. Review and amend as required NDPC guidelines to - to ensure that IWRM principles are taken WRC, NDPC, DAs General, basin-wide issue, i.e. reflect IWRM requirements in district planning. well anchored in the district planning responsibility of WRC to address and process. initiate action on. Intensify public awareness raising activities on prudent - to educate and drive towards “a water- Densu Basin Board, - General, basin-wide issue, i.e. respon- use of water and its conservation, including adoption of wise” society. DAs, NGOs and sibility of WRC to initiate action on. traditional knowledge and cultural practices. traditional - DAs responsibility with traditional authorities authorities to carry out the activities accordingly in respective districts. Issue/problem: Prevention and resolution of water related conflicts Establish a sub-committee under Densu Basin Board to - to create an agreed procedure and fixed WRC, Densu Basin - General, basin-wide issue, i.e. be the focal point for discussions and negotiations venue for lodging concerns and holding Board, DAs and responsibility of WRC to initiate action between stakeholders in case conflicting interests arise discussions aimed at preventing disputes other stakeholders on. on new water management issues and mechanisms and in case solve conflicts through - Densu Basin Board responsibility to during implementation of the IWRM plan. coordination and collaboration. carry out the activities accordingly.

May 2007 Page 73 Water Resources Commission Densu River Basin IWRM Plan

Involved Actions/measures Purpose Responsible partner(s) parties Issue/problem: Enforcement and good water governance Work towards ensuring that the WRC Inspectorate is - to have a well functioning unit to oversee WRC, Densu Basin General issue, WRC to initiate action. properly staffed and well functioning to carry out the compliance by water abstractors of their Board, DAs tasks and services as required in WRC Act 522. granted licences, and to ensure that transparent decision-making and democratic principles are adhered to in decisions related to water allocation etc. Review NDPC Act 479 (1994), Local Government Act - to facilitate policy making on harmonised WRC General, basin-wide issue, i.e. 462 (1993), PURC Regulation LI 1659 (1999) and other district and IWRM planning; responsibility of WRC to address and pertinent legislation to identify gaps, overlaps or - to identify legislative amendments in initiate action on. discrepancies related to the practicing of IWRM. form of district bye-laws to regulate water use and introduce effective enforcement procedures. Issue/problem: Economy, financing and lack of resources/capacity For the highest prioritised IWRM actions prepare cost - to generate revenue for financing of WRC, PURC, General issue, WRC to initiate action. estimates for their implementation and identify funding proposed IWRM activities. GWCL, CWSA, Basis for negotiations is the PURC Act (consolidated funds, internally generated funds, district- IDA, WUAs, LI 1651, the Water Use Regulations LI based common funds, IWRA, donor funding or specific MFEP 1692 and CWSA tariff regulations. local levies). Issue/problem: Water quality, pollution of water and waste disposal Prepare basin map which depicts the “hot spots” along - to provide input to the individual district WRC, EPA, DAs General, basin-wide issue, i.e. the river system and outline activities on how the planning exercises. responsibility of WRC to address and pollution hazards can be abated. initiate action on. Operationalise and bring into practice the Memorandum - to use the permitting system as intended WRC, EPA, DAs General, basin-wide issue, i.e. of Understanding (between WRC and EPA) on the as a mechanism to reduce pollution of the responsibility of WRC to address and issuance of waste discharge permits. Densu river. initiate action on. Prepare guidelines for location of waste dump sites and - to provide input to the individual district WRC, EPA, DAs - General, basin-wide issue, i.e. respon- prescribe remedial activities on how to minimise the risk planning exercises. sibility of WRC to initiate action on. of groundwater and surface water pollution from waste - DAs responsibility to carry out the disposal sites (waste management strategy). activities accordingly at district level. Intensify public awareness raising activities on best - to raise awareness on why and how to Densu Basin Board, DAs responsibility to carry out the waste disposal practices in local communities. avoid pollution from waste disposal locally DAs activities in respective districts.

May 2007 Page 74 Water Resources Commission Densu River Basin IWRM Plan

Involved Actions/measures Purpose Responsible partner(s) parties Prepare technical discussion paper on the economics and - eventually, the future piped water supply WRC, EPA, General, basin-wide issue, i.e. technical viability of introducing water-borne sewerage areas will also to a large extent have to be GWCL, DAs responsibility of WRC to address and and treatment facilities in urban settings of the basin. serviced by piped sewer/treatment initiate action on. systems. Institute mechanisms to control in-stream activities such - to prevent water pollution from activities Densu Basin Board, DAs responsibility to oversee that as washing of vehicles, bathing/washing with soap, etc. directly in the open water bodies. DAs, NGOs. control mechanisms are introduced. Issue/problem: Water-borne diseases and sanitation Intensify public awareness raising activities concerning - to raise awareness and hence reduce Densu Basin Board, DAs responsibility to carry out the water-related contracted diseases and good hygienic incidences of diseases among the DAs, MDAs and activities in respective districts. practices in local communities. population fetching water directly from the NGOs. river. Introduce local monitoring of hygienic parameters, e.g. - to raise awareness and introduce local Densu Basin Board, DAs responsibility to carry out the through schools. control of water quality standards. DAs, GES, NGOs. activities in respective districts. Issue/problem: Forests and protected areas Review previous tree planting programs, and plan for - to learn lessons from successes and Densu Basin Board, DAs responsibility to carry out the and initiate tree planting programs and forest protection failures, and factors contributing to them. Forestry Commis- activities in respective districts. activities. - to arrest deforestation trend and increase sion, DAs, NGOs the areas with protective land cover. Identify areas in the basin vulnerable to bush fires and - to protect land area against erosion and Densu Basin board, DAs responsibility to carry out the prepare guidelines for protection. thereby reduce siltation of the water course DAs, NGOs activities in respective districts. with improved water quality as a result. Issue/problem: Farming and farming methods Plan for and initiate a campaign to promote practical - to raise awareness of the adverse effects Densu Basin Board, DAs responsibility to carry out the guidelines on best available agricultural practices for from inappropriate farming methods DAs, MDAs and activities in respective districts. small-scale farming or introduce modifications to NGOs existing methods. Carry-out a basin-wide survey concerning use of - to provide procedures for supervision of WRC, EPA, - General, basin-wide issue, i.e. fertilizers and pesticides in the agriculture sector, and on and introduction of protection measures to MOFA, DAs responsibility of WRC to initiate action that basis introduce regulatory activities for control of be applied by districts. on. identified inappropriate farming methods. - Densu Basin Board and DAs responsibility to carry out activities.

May 2007 Page 75 Water Resources Commission Densu River Basin IWRM Plan

Involved Actions/measures Purpose Responsible partner(s) parties Issue/problem: Protection of river banks Based on the buffer zone policy under preparation, - to protect the river system against effects Densu Basin Board, - General, basin-wide issue, i.e. respon- prepare LI on establishment and maintenance of buffer of soil erosion (siltation) and uncontrolled DAs and NGOs sibility of WRC to initiate action on. zones, and prescribe control activities for protection of pollution, and to increase the retention of - Densu Basin Board and DAs river banks. water in the river system. responsibility to carry out the activities accordingly. Intensify public awareness raising activities concerning - to raise awareness of the need of river Densu Basin Board, DAs responsibility to carry out the protection of river banks in local communities. banks protection. DAs and MDAs activities in respective districts.

Issue/problem: Flooding Prepare monograph for Densu Basin, including mapping - to make available an up-to-date WRC, HSD, IDA, General, basin-wide issue, i.e. of the actual flooding situation with demarcation of flood background document on which to make GWCL responsibility of WRC to address and prone areas, potential for dredging, etc. further decisions among key players about initiate action on. “who does what - and when”. Formalise procedures with HSD, IDA and GWCL on -to establish a system to facilitate WRC, HSD, IDA, General, basin-wide issue, i.e. how to incorporate flood control warnings/measures as implementation of measures. GWCL responsibility of WRC to address and part of the water management initiatives in the basin. initiate action on. Issue/problem: Water weeds infestation Carry-out a survey along the entire Densu river course to - to provide up-to-date facts about the WRC, Densu Basin - General, basin-wide issue, i.e. delineate the scope of the water weeds problem and extent and nature of the water weeds Board, Das and responsibility of WRC/Densu Basin prepare guidelines for remedial activities. problem and how to move forward with MDAs Board to initiate action on. curative measures. - DAs responsibility to carry out activities in respective districts. Issue/problem: Small-scale mining Enter into a campaign/dialogue for prevention of illegal - to raise awareness and to reduce effects Densu Basin Board, DAs responsibility to carry out the or inappropriate water use and pollution arising from from small scale mining activities in DAs, Minerals activities in respective districts. small-scale mining activities. affected areas. Commission. Prescribe guidelines and control activities for small-scale To provide procedures for monitoring Densu Basin Board, DAs responsibility to carry out the mining small-scale mining activities to be applied DAs, Minerals activities in respective districts. by districts. Commission.

May 2007 Page 76 Water Resources Commission Densu River Basin IWRM Plan

Involved Actions/measures Purpose Responsible partner(s) parties Issue/problem: Women’s participation in water management Ensure women’s participation at the various levels of - to enforce a policy of women’s involve- Densu Basin Board, DAs responsibility to carry out the water management. ment in all aspects of water management. DAs and MDAs. activities in respective districts. This issue is cross-cutting and must be incorporated in most of the various problem areas and the associated actions. Issue/problem: Livelihood, land tenure and land use planning Identify conflict areas concerning traditionally owned - to facilitate long-term policy making on WRC, Lands General, basin-wide issue, i.e. land and publicly owned land in relation to Land land use planning as a mechanism for Commission, Town responsibility of WRC to address and Planning and Soil Conservation Ordinance 1953 (Cap protection and preservation of water and Country initiate action on. 32) and the new Lands Commission Bill as it relates to resources and ecological fragile areas. Planning Depart- IWRM. ment, other MDAs Issue/problem: Fishing and fishing methods Prepare guidelines and carry out a campaign for - to raise awareness of fishing and fishing Densu Basin Board, DAs responsibility to carry out the prevention of illegal fishing and inappropriate fishing methods in local communities. DAs, MOFA activities in respective districts. methods. Prescribe control activities for fishing and fishing - to provide procedures to monitor fishing Densu Basin Board, DAs responsibility to carry out the methods. methods. DAs, MOFA activities in respective districts.

May 2007 Page 77 Water Resources Commission Densu River Basin IWRM Plan

5.3 Prioritisation of actions

5.3.1 Actions included in first phase implementation At a third broad-based workshop, the SEA procedures, which have been guiding all through the IWRM planning process, also provided a methodology (“tool”) for stakeholders to assess the importance and relevance of the various actions in Table 5.1 above. The application of this tool resulted in a ranking of the proposed actions according to their relative performance and effect. This in turn provided the means to prioritise the actions and subsequently be able to identify a sequence for the various activities to be initiated and carried out.

Out of the total 32 actions listed in Table 5.1, a “short-list” was drawn up containing the 10 actions/measures perceived by the workshop participants/stakeholders to be the most relevant and important to embark on initially. These 10 highest ranked ac- tions are listed in Table 5.2 below. The table also provides information and some ex- planatory remarks to be taken into consideration when the planning is further de- tailed towards implementation of the actions.

Table 5.2 Prioritised list of proposed actions/measures

Ran- Explanatory remarks related to Action king implementation of actions Intensify public awareness • The goal is to facilitate public educational activities raising activities on prudent and promote behavioural changes towards creating a use of water and its “water-wise” society. 1 conservation, including • Activities will incorporate specially targeted curricula adoption of traditional development for schools, use of the public media, knowledge and cultural NGO spearheaded campaigns, public meetings and practices.. facilitation by traditional authorities. Work towards ensuring that • Although the unit exists, the Inspectorate needs to be the WRC Inspectorate is properly fitted to oversee compliance by water abstrac- properly staffed and tors of their granted licences. 2 operationalised to carry out • WRC needs to employ additional staff for this purpose the tasks and services as and to introduce guidelines for the work and field required in WRC Act 522. monitoring activities by the Inspectorate. • Waste management plans (strategy) should be developed and implemented specifically covering the Prepare guidelines for densely populated sections of the basin. location of waste dump sites • DAs to acquire landfill sites for disposal of solid waste and prescribe remedial in “safe” distance from river banks, and adopt modern activities on how to methods to dispose liquid waste, e.g. composting. 3 minimise the risk of ground- • Provision should be made to introduce adequate refuse water and surface water receptacles at vantage points, and regular collection of pollution from waste waste to the final disposal sites should be normalised. disposal sites. • Eventually, waste treatment facilities should be constructed along side the introduction or expansion of piped water supply scheme.

May 2007 Page 78 Water Resources Commission Densu River Basin IWRM Plan

• WRC to facilitate that the LI preparation process gains momentum ending with an LI enactment. Based on the buffer zone • Existing buffer zone bye-laws, sector specific policies policy under preparation, and guidelines, and other regulations for protection of prepare LI on establishment river banks must be harmonised for effective imple- 4 and maintenance of buffer mentation. zones, and prescribe control • Building laws/regulations need to be enforced, and activities for protection of public education to sensitise people on buffer zones river banks. and their demarcation should be intensified. The educational activities must in particular target tradi- tional rulers. • The scenario analyses carried out at this stage use a planning period ending year 2020. The calculations provide “water balance” results in which future water requirements are balanced against water availability taking into account impacts of possible climate change, Use results from the water inclusion of environmental flow requirements and demand and water availa- stronger emphasis on groundwater utilisation. Water bility scenario analyses to source alterations/augmentations are also analysed by 5 prepare strategy on how to the inclusion of an inter-basin water transfer scheme or meet the future water alternatively construction of a new dam upstream in the requirements of the Densu Densu basin. basin • Based on the scenario analysis, a strategy should be mapped out by WRC aimed at outlining the future path to be taken concerning water source utilisation and development in the basin. The strategy paper should be discussed with and fine-tuned in a dialogue with GWCL, and larger irrigation and industrial enterprises. • The purpose is to use the permitting system as intended as a mechanism to reduce pollution of the Densu river Operationalise and bring caused by uncontrolled dumping of liquid and solid into practice the Memoran- waste into the river system. dum of Understanding 6 • A Joint Technical Appraisal Team shall be set up by (between WRC and EPA) on EPA and WRC, and the modalities, application forms the issuance of waste etc shall be made ready for receiving waste discharge discharge permits. applications and subsequent granting of waste dis- charge permits. • Over the years many tree planting activities have been carried out in Ghana, the latest larger scale programme is the “Greening Ghana Initiative”. It is important to learn lessons from successes and failures, and factors Review previous tree contributing to them, and how to uphold forest protec- planting programmes, and tion laws/regulations. 7 plan for and initiate tree • A basin-wide plan with demarcation of areas in most planting programs and forest need of afforestation programmes should be prepared, protection activities. and eligible NGOs should be approached to spearhead implementation of such activities. • The plan should also identify areas in the basin vulnerable to bush fires, and guidelines for protection should be prepared. Vet existing legislation in • The purpose is to facilitate long-term policy making 8 relation to practicing of and harmonisation of regulations on land use planning IWRM, including: as a mechanism for protection and preservation of the

May 2007 Page 79 Water Resources Commission Densu River Basin IWRM Plan

(i) identification of conflict Densu river system. areas concerning tradi- • Provision should also be thought about creating tionally owned land and alternative livelihood support systems for peo- publicly owned land in ple/communities living close to the river system. relation to Land Plan- • DAs should more vigorously follow-up on implement- ning and Soil Conserva- ing physical plans for towns and communities, and tion Ordinance 1953 enforce bye-laws on granting of building licences etc. (Cap 32) and the new • The intention is to facilitate policy making on Lands Commission Bill; harmonised district and IWRM planning, and to iden- (ii) reviewing NDPC Act tify legislative amendments in form of district bye-laws 479 (1994), Local to regulate water use and introduce effective enforce- Government Act 462 ment procedures. (1993), PURC Regula- tion LI 1659 (1999) and other LI’s to identify gaps or discrepancies. • A basin-wide survey should be conducted to provide overview of the use of fertilizers and pesticides in the Plan for and initiate cam- agriculture sector. paigns to promote practical • The intention is to raise awareness of the adverse guidelines on best available effects from inappropriate farming methods, and to 9 agricultural practices for educate/train farmers on the use of environmentally small-scale farming or friendly agro-chemicals. introduce modifications to • Dugouts or other water retaining structures should be existing methods. constructed for the exclusive use of domestic animals (cattle) to prevent pollution from stray animals of the open water bodies. • A monograph should be prepared for the Densu basin, including mapping of the actual flooding situation with Formalise procedures with demarcation of flood prone areas, potential for dredg- HSD, IDA and GWCL on ing, etc. 10 how to incorporate flood • On that basis the involved parties should establish control warnings/measures collaborative procedures to facilitate implementation of in IWRM planning. measures to alleviate the risk and minimize damages due to floods.

The above prioritised list of actions and measures attempts to address a broad spec- trum of the water management issues identified for the Densu Basin, such as water availability and water quality/pollution as well as the “enabling” environment in re- viewing and improving on the institutional and legislative framework aimed at put- ting IWRM high on the agenda at the various planning and administrative levels within the basin.

It should be emphasised that the remaining 22 actions outlined in Table 5.1 of Sub- chapter 5.2 above are all an integral part of the IWRM Plan’s action programme and as such should be considered for implementation when opportunities concerning ad- ditional capacity and availability of resources, i.e. financially and institutionally, are becoming evident. During annual reviews and updates of the IWRM Plan these as-

May 2007 Page 80 Water Resources Commission Densu River Basin IWRM Plan

pects must be assessed with the aim of “upgrading” the presently non-prioritised ac- tions to be incorporated in subsequent implementation phases.

5.3.2 Sustainability test of IWRM plan At a last workshop during this planning phase, the action programme was subjected to a test (using a pre-designed SEA tool) aimed at assessing the overall sustainability of the IWRM plan by the concerned decision-makers and other stakeholders. Appli- cation of the tool provided a visual and quantitative measure as to which extent the proposed actions are capable of supporting an environmentally sustainable develop- ment. For this purpose, a number of pre-defined sustainability criteria (aims) were considered, and the outcome of the test (scores) revealed whether the action pro- gramme when implemented “supports the individual criteria (aims)”, “has a neutral effect” or “works against the stated criteria (aims)”.

As previously explained, the term “environmental” in this context includes both (i) natural resources conservation, (ii) social-cultural conditions, (iii) economic aspects, and (iv) the regulatory, administrative and institutional setting in which the IWRM plan is to be implemented.

The outcome of the test showed a uniform and coherent group of answers among the participants with scores indicating that the action programme in general is perceived to support the various sustainability criteria with only a few cases where the scores pointed to the category of “has only neutral effect”. Based on the results of the sus- tainability test, the relevant actions in Table 5.1 and 5.2 above were revisited and amended to respond to these findings accordingly.

5.4 Towards implementation of the action programme

5.4.1 Way forward Economic and financial aspects Implementation of the actions listed above needs funding. Some of the activities can be initiated directly through current (rolling) budget allocations at DA level, through allocation from the WRC grant-based donor support, and through proceeds from the water abstraction licence fees lodged in the Water Resources Management Account. The further detailing of the action programme will have to incorporate ways and mo- dalities of the financing.

Furthermore, where relevant, the actions shall be analysed for their economic impli- cations and/or value. The contribution from an economic analysis can well be incor- poration of additional considerations, which were not directly included during prepa- ration of the present plan, and hence, could alter the priority (desirability) of the ac- tions in the action programme.

Implementation of major water infrastructure projects such as a dams, inter-basin water transfer scheme, new or expanded water supply schemes, waste disposal and

May 2007 Page 81 Water Resources Commission Densu River Basin IWRM Plan

treatment facilities etc. will be decided on and finances negotiated at other levels based on financial viability analyses, and hence, are beyond the scope of the IWRM plan at this stage. Implementation of such activities are expected to serve the inter- ests of the population of the basin, but the coordination, planning and assignment of tasks, including the involvement of WRC, is expected to take place in accordance with time schedules required for investment in major infrastructure projects and to be coordinated with the financing capabilities of donor agencies, the government and external investors.

However, except for investments in larger infrastructure projects (ref. Action 5) most of the actions are concerned with institutional capacity building, adjustment of legis- lation, and clarification of institutional and departmental responsibilities, which can be initiated within relatively short time and without major investment requirements.

Role of WRC, Densu Basin Board and other partners It is important for proper implementation of the IWRM plan that the Densu Basin Board is mobilised with a clear mandate from WRC to address common problems to be solved through interactive collaboration between the Board and the District As- semblies. The mandate of the Board shall in addition to coordination activities in- clude obligations to initiate campaigns and to contribute towards elaboration of best practice papers and guidelines on water demand and environmental management as required during implementation of the action plan

Another precondition for successful implementation and enforcement of the plan is that a platform for inter-institutional governmental cooperation is established to solve a number of specific tasks outlined in the IWRM plan. Such tasks should not only be addressed as part of the agenda for regular meetings of the WRC or the Densu Basin Board, but within the framework of sub-committees. Such sub-committees should have clear mandates, including specification of the professional profile of the mem- bers and a time schedule for making recommendations to decision-makers in WRC and the Densu Basin Board.

Preparing “project/action summary sheets” An immediate first activity required to spearhead the way forward towards initiating some of the actions in the IWRM plan is for WRC in close collaboration with the Densu Basin Board and other involved partners to prepare concise descriptions of the portfolio of the prioritised actions (Table 5.2). This should be done in a structured, easily understandable way using a pre-scribed standard form (“project/action sum- mary sheet”) providing information about the action as follows: − main objective; − components/main activities; − expected outputs; − milestones and benchmarks; − modalities for implementation and involved/collaborating partners; − time duration; − inputs and estimated costs; and − mode of financing/funding.

May 2007 Page 82 Water Resources Commission Densu River Basin IWRM Plan

5.4.2 Monitoring and regular reviews of the plan As part of the further detailing and preparation for commencing implementation of the prioritised actions, the milestones and benchmarks mentioned above should be detailed and expanded to provide information about progress indicators and sub- outputs to be achieved. It is against this background that progress towards commenc- ing and carrying out the actions’ activities can be monitored.

It is proposed that the Densu Basin Board at its regularly convened quarterly meet- ings as a fixed agenda item will be given a “progress reporting” and discusses the ef- forts made in carrying the IWRM plan forward towards action implementation. Ad- ditionally, once a year the IWRM plan – or rather its action programme – should be reviewed, and as found necessary be updated. In practical terms it would entail a re- vision of and/or amendment to the project/action summary sheets.

The present document constitutes the first version of the Densu Basin IWRM Plan. Inasmuch as IWRM is a cyclic and long-term process, the document can be seen as a milestone in this process, in which the status of the water resources situation is documented – a process that should be subject to continuation and updates as the need arises in the future.

May 2007 Page 83