Hornby Island Terminal Development Plan
Approved October, 2018 PUBLISHING INFORMATION
Title: Hornby Island Terminal Development Plan (TDP) Author: Terminal Development, BC Ferries Status: Approved, October, 2018
This office consolidation includes the following amendments: Amendment: Date:
ACKNOWLEDGEMENTS:
The TDP has been prepared with assistance from Checkwitch Poiron Architects Inc.
BC Ferries Inc. wishes to thank the Hornby Island TDP Staff Working Group, who dedicated many hours towards the development of this Terminal Development Plan, the Ferry Advisory Committee and the community at large for their ongoing input and comments during the preparation of this TDP.
2 Table of Contents Introduction Implementation 1 1.1 What is a Terminal Development Plan (TDP) 10 6 6.1 Investment and Implementation 41 1.2 Purpose of the Terminal Development Plan 10 6.2 Recommendations for Further Studies 41 1.3 Interpretation of the TDP 10 1.4 Structure of the TDP 11 Appendix 1: Comparison Table of TNMP with TDP 44 1.5 Plan Area 11 Appendix 2: Glossary of Terms 47 1.6 How the TDP Relates to Other BC Ferries’ Strategic Plans 12
Context 2 2.1 Regional Context 15 2.2 Historical Context 16 2.3 Community Context 16 2.4 Policy Context 16
Summary of Existing Terminal Conditions, Issues & 3 Opportunities 3.1 Hornby Island Terminal Conditions 17 3.2 Route Profile 17 3.3 Key Issues and Opportunities 19
Hornby Island Functional Requirements 4 4.1 Hornby Island TDP Functional Requirements 24
Plan Concepts 5 5.1 Concept Overview 36 5.2 Utility Requirements 40
3 List of Figures
Figure 1: Southern Gulf Islands Terminal and Route Map 6 Figure 2: Terminal and Route Map 7 Figure 3: Hornby Island Terminal Aerial Photograph 8 Figure 4: Hornby Island Terminal Development Plan (TDP) Timeline 9 Figure 5: Hornby Island Location Map 11 Figure 6: Strategic Drivers 13 Figure 7: Relationship Between Strategic Plans and Terminal Development 13 Plans Figure 8: Kahloke Vessel Photograph 14 Figure 9: Photograph of Hornby Island Beach 15 Figure 10: Hornby Island Terminal Aerial Photograph 18 Figure 11: Existing Site Plan and Key Issues 20 Figure 12: Hornby Island Terminal Photograph 22 Figure 13: Traffic Safety Review Key Issues 23 Figure 14: Pedestrian Facilities to Reduce Vehicle Pedestrian Conflicts 25 Figure 15: Hornby Island Terminal Berth 26 Figure 16: Denman West Queuing Lane Example 28 Figure 17: Example of Outdoor Waiting Space, Pick-up/Drop-off lane and 30 Retail Pad Figure 18: Example of Water Fountains 32 Figure 19: Example of Reader Boards 32 Figure 20: Example of Bike Repair Station 32 Figure 21: Example of Terminal Storage 33 Figure 22: Photograph of Public Art 35 Figure 23: Photograph of Public Art 35 Figure 24: Illustrative Short Term Concept Plan 37 Figure 25: Illustrative 25 Year Concept Plan 38 Figure 26: Traffic Study Recommendation 39
4 List of Tables
Table 1: Vessel Replacement Specifications 14 Table 2: Hornby Island Terminal Summary 17 Table 3: Kahloke Vessel Profile 19 Table 4: Functional Requirements - Safety and Security 25 Table 5: Functional Requirements - Berths 26 Table 6: Functional Requirements - Ticketing and Pre-Ticket Area 27 Table 7: Functional Requirements - Vehicle Holding Areas 27 Table 8: Functional Requirements - Vehicle Loading and Unloading 28 Table 9: Functional Requirements - Customer Amenities 29 Table 10: Functional Requirements - Communications and IT Infrastructure 31 Table 11: Functional Requirements - Administration and Employee Facilities 31 Table 12: Functional Requirements - Other Terminal Services 32 Table 13: Functional Requirements - Utilities and Miscellaneous 34 Table 14: Recommended Further Studies and Actions 42
5 BC Ferries Terminal Network
Alert Bay Cormorant Island Preedy Harbour Thetis Island Alliford Bay (Gaats'iiGundaay) Haida Gwaii Prince Rupert Prince Rupert Bear Cove Port Hardy Quathiaski Cove Quadra Island Bella Coola Bella Coola Saltery Bay Sunshine Coast Blubber Bay Texada Island Shearwater Denny Island Brentwood Bay Saanich Peninsula Shingle Spit Hornby Island Buckley Bay Buckley Bay Skidegate (GuuhlGa Llnagaay) Haida Gwaii Campbell River Campbell River Snug Cove Bowen Island Chemainus Chemainus Sointula Malcolm Island Crofton Crofton Sturdies Bay Galiano Island Denman West Denman Island Swartz Bay North Saanich Departure Bay Nanaimo Tsawwassen Lower Mainland Descanso Bay Gabriola Island Vesuvius Bay Salt Spring Island Duke Point Nanaimo Village Bay Mayne Island Earls Cove Sechelt Whaletown Cortes Island Fulford Harbour Salt Spring Island Westview Powell River Gravelly Bay Denman Island East Langdale Heriot Bay Quadra Island Nanaimo Bowen Horseshoe Bay Gabriola Island Horseshoe Bay West Vancouver Island Klemtu Klemtu Chemainus Thetis Island Little River Comox Penelakut Island Vesuvius Langdale Sunshine Coast Crofton Long Harbour Tsawwassen Saltspring Galiano Island Long Harbour Salt Spring Island Island Sturdies Bay Fulford Harbour Lyall Harbour Saturna Island Village Bay Mayne Island McLoughlin Bay Bella Bella Otter Bay Swartz Bay Pender Islands Mill Bay Mill Bay Saturna Island Nanaimo Harbour Nanaimo VANCOUVER ISLAND Ocean Falls Ocean Falls Otter Bay Pender Island Victoria Penelakut Penelakut Island Port McNeill Port McNeill Figure 1: Southern Gulf Islands Terminal and Route Map
6 Prince Rupert
HAIDA GWAII
Skidegate Terminal (GuuhlGa Llnagaay)
Alliford Bay (Gaats’iiGundaay)
Klemtu
Ocean Falls
McLoughlin Bay Bella Coola Shearwater
Bear Cove Sointula
Port McNeill Alert Bay
VANCOUVER Whaletown ISLAND Heriot Bay Westview Campbell River Saltery Bay Blubber Earls Cove Little River Bay Shingle Langdale Denman West Buckley Bay Spit Snug Gravelly Bay Cove Horseshoe Bay Vancouver Departure Bay Duke Point Tsawwassen
Swartz Bay Figure 2: Terminal and Route Map Victoria 7 Figure 3: Hornby Island Terminal Aerial Photograph
8 FEB–MAR MAR–MAY MAY–OCT NOV–DEC JAN–MAR SEPT 2017 2017 2017 2017 2018 2018
PHASE 1 PHASE 2 PHASE 3 PHASE 4 PHASE 5 PHASE 6 Pre-Planning Baseline Report & Key Issues & Draft Options Draft Plan Final TDP Gap Analysis Guiding Principles Development Approved by BC Ferries
Analysis of feedback and development of preferred options
Final proposed TDP External Engagement posted to BC Ferries Review of relevant background Internal Engagement website for pubic review 2 Open Houses information and studies Apr–Aug 2017 Village of Queen Charlotte–Nov 2017 Staff Information Session Sandspit–Nov 2017 Meeting with Ferry Advisory Presentation to Haida Nation–Nov 2017 Committee Online Open House and Survey
Figure 4: Hornby Island Terminal Development Plan (TDP) Timeline
9 1Introduction 1.1 What is a Terminal Development Plan (TDP)? Over the next 25 years the Terminal Network will be optimized for efficient and effective operations. BC Ferries will study routes and their interactions A Terminal Development Plan (TDP) is a concept plan that provides the to determine ways to reduce operating and capital costs and increase system framework for the phased implementation of strategies and actions over reliability. Terminals will be examined for improvement to construction and the next 25 years that will enable BC Ferries to develop terminals in a cost operating efficiencies. Greater use of standard designs and components effective, organized and efficient way. will aid these efficiencies over time. TDPs shall specify: 1.2 Purpose of the Terminal Development Plan • Terminal classification The purpose of the Hornby Island TDP is to set out a long-term vision for the • Berth classification(s) future of this important terminal which acts as the main gateway and route • Description of existing facility connection between Hornby Island and Denman Island. • Existing traffic demand and growth projections • Terminal lands and property, including stakeholder and community The TDP is future-oriented and depicts how the Hornby Island terminal is to and archaeological assessments be developed over an extended period of time through a series of initiatives. • Existing terminal infrastructure 1.3 Interpretation of the TDP • Existing safety, security and operational issues • Existing and future vessel deployment Unless otherwise specified within the TDP, the boundaries and locations of • Functional requirements, as drawn from Terminal Design any symbols or areas shown on a Figure are approximate only and shall be Requirements contained in the TNMP and established in consultation interpreted as such. They are not intended to define exact locations except with local area teams where they coincide with clearly recognizable physical features or fixed • Future terminal development plans, including the scope, schedule and boundaries, such as property lines and utility rights-of-way. budget of all improvements to be carried out over the next 25-years.
10 19 19A
DENMAN ISLAND
16
HORNBY ISLAND
Shingle Spit
Gravelly Bay Figure 5: Hornby Island Location Map
1.4 Structure of the TDP 1.5 Plan Area The scope of the Hornby Island TDP covers planning, conceptual design The study area for the Terminal Development Plan encompasses the marine and development of an implementation schedule and budget estimates for infrastructure, the landside infrastructure and the approach to the terminal. upgrading the terminal, with the requirement to: • Review of foot passenger and vehicle traffic demand projections including demand management policies and opportunities; • Develop and find solutions to accommodate the functional requirements including evaluation of alternatives; • Recommend a preferred plan for the terminal that is in accordance with the overarching Terminal Network Master Plan; • Prepare conceptual designs for the recommended terminal plan including the general arrangement of the site; • Develop an estimate of capital cost, with project phases, schedule of work and cash flow; and • Engage with various stakeholders and First Nations during the course of the study. The study represents a cooperative effort which involves a high degree of interaction with and input from a wide range of participants. A comprehensive “baseline review” report has been completed as a separate report which details the existing situation in the TDP area as it currently stands, and identifies issues affecting the production of the TDP.
11 1.6 How the TDP Relates to Other BC Ferries Strategic Plans 1.6.1 Strategic Plan To align with BC Ferries future, long term vision and objectives the TDP The 2018 Strategic Plan was prepared to guide the long-term direction of BC is guided by three overarching documents: the Strategic Plan, Terminal Ferries and achieve the organizations vision from 2016-2026. The Strategic Network Master Plan and Fleet Master Plan. Plan’s vision is as follows: Vision Trusted, valued. Mission We connect communities and customers to the people and places important in their lives. Our Values Safe: Safety is our highest value. Caring: We operate from a position of kindness and empathy for those who travel and work with us. Honest: We conduct business with integrity, honesty and accountability. Collaborative: We collaborate with others to enhance the customer experience. Respectful: Respect is paramount in our interactions with others. Sustainable: Our environmental, social and economic impact are central to business decisions.
12 Operational Excellence We strive for a superior customer experience through safe, efficient, reliable and effective
Financial Sustainability We make prudent choices for the long-term growth and sustainablility of our organization, which enables fare affordability, value for customers and effective asset stewardship. Employee Engagement We foster growth, development and commitment in our people.
Environmental and Social Governance We leverage our resources, services and relationships in recognition of our responsibility to our environment, customers, employees, stakeholders and communities. Innovation and Continuous Improvement We nurture continuous improvement and innovation across our organization. Figure 6: Strategic Drivers Figure 7: Relationship Between Strategic Plans and Terminal Development Plans
1.6.1.1 Strategic Drivers 1.6.3 Fleet Master Plan The Strategic Plan outlines five strategic drivers that will inform strategic In 2016 BC Ferries produced the Fleet Master Plan translating the broad decision-making over the planning horizon. They are the critical success direction from the Strategic Plan in to specific strategies, policies and tactics factors that must be in place to achieve our strategic goals that BC Ferries that apply to the BC Ferries fleet. BC Ferries fleet will transition from a will pursue to achieve the vision: fleet of many unique vessels to a fleet of vessels that have high physical and operational commonality. The number of unique vessels in the fleet 1.6.2 Terminal Network and Master Plan will be minimized. Common operational and maintenance procedures will The Terminal Network Master Plan (TNMP) is a forward-looking planning be used as far as practicable. New vessel designs will emphasize safety, and policy document. The TNMP aligns with the Corporate Strategic Plan environmental stewardship, efficiency, standardization, class builds and and forecasts all the strategic and major tactical actions governing the de- customer experience.. velopment of the BC Ferries terminal network. A network refers to how routes interact singularly, in conjunction, or as a system of routes. The Fleet Master Plan identifies: • When a vessel will retire Each terminal shall have a Terminal Development Plan (TDP) which aligns • When a ship will be replaced with the TNMP. Terminal Engineering is responsible for the TDP and the • The class, model and characteristics of the replacement vessel TDP schedule. • The 25 year deployment of any vessel The Hornby Island terminal is classified as a Minor / Intermediate (MIM) - Unstaffed terminal. As a result, the design requirements of the Hornby The 2016 Fleet Master Plan identifies the Kahloke scheduled for retirement Island terminal shall adhere to the design requirements of an MIM - Un- in April 2030. The Fleet Master Plan identifies six classes that all future staffed terminal and is further elaborated upon in this TDP. built vessels will be built to. The Kahloke is classified as a ‘Minor Class’ vessel and the Fleet Master Plan identifies that any replacement vessel for this route will also be a Minor Class, double ended type vessel.
13 Vessel Replacement Specifications
Vessel Description Class Minor Model 47 Estimated Crew Size 7/8 Crew Live Aboard No Performance Service Speed (kts) 14 Automobile Equivalent 47 Lane Metres 270 Commercial Vehicle 4.75m Capacity Height (max.) Passenger and Crew Crew/Passengers A: 8/292=300 B: 7/143 = 150
Voyage Classification NC2 Figure 8: Photo of the Kahloke Double or Single Ended Double-ended Berth Compatibility Single Ramp Double Lane Car Deck Configuration Open Passenger Boarding Traffic Segregation Characteristics Berth Interface Type MIM (BIT) Flexibility of Use on Sheltered Waters or Near Alternative Routes Coastal Class 2 routes with BC Ferries’ standardized minor/ intermediate berth configuration Dangerous Goods Yes Area Integrated Indoor Seating 100 Outdoor Seating 60 Interior Design Fleet Interior Design Standard Passenger Standards Amenities and Passenger Lounge Main Dec - external sun deck Services Location with solarium Passenger Services Accessible Car Deck Lounge, Work/Study stations, Vending, Accessible washrooms Vessel Server Should conform to standard BCF IT operating Rooms requirements as outlined in FMP
14 2Context 2.1 Regional Context Hornby Island is located off the eastern shore of central Vancouver Island, opposite Denman Island, 12 miles (20 km) south of Courtenay and one hour north of Nanaimo in the Salish Sea (Strait of Georgia). It is one of the Northern Gulf Islands and part of the Islands Trust and Comox Valley Regional District of British Columbia and is home to a small community of just over 1,000 residents. The Hornby Island terminal is also located on the traditional territories of the Comox First Nations, Homalco First Nations, Qualicum First Nations and Sliammon First Nations.
Figure 9: Photograph of Hornby Island Beach
15 2.2 Historical Context 2.4 Policy Context Hornby Island was first inhabited by Indigenous peoples including the 2.4.1 Hornby Island Official Community Plan Pentlatch, a Coast Salish First Nations who called the Island Ja-dai-aich, The Hornby (Islands Trust) Official Community Plan (OCP) was adopted on meaning The Outer Island. It became the home of European settlers during October 15, 2008. OCPs are the overarching planning documents that set the 1791 voyage of the Spanish ship Santa Saturnina, under Juan Carrasco out the community vision and values that will guide decision making about and José María Narváez. In 1850 the British named Hornby Island after Rear the future direction of each municipality. They also provide clarity for Admiral Phipps Hornby, at the time the Commander of the Pacific Station. residents, businesses and institutions on the primary goals objectives and 2.3 Community Context supporting policies that help the municipality to meet its goals. A number of policies are relevant to the Hornby terminals which are outlined in the A small community of approximately 1,000 residents (2016 Census), Hornby baseline report. Island is home to families, retirees, business owners and artists who enjoy the rural island life, recreational opportunities, boating and scenery. Tourists 2.4.2 Development Permit Areas and visitors can triple the population of the Island during the summer. The S.488 of the Local Government Act authorizes municipalities to designate total land area of Hornby Island is 29.92 square kilometers (11.55 square Development Permit Areas (DPAs) and request Development Permits prior miles). to the commencement of development for certain issues outlined in the section. The Hornby terminal site is not located within a Development Permit Area (DPA).
16 Summary of Existing Terminal Conditions, 3Route Profile, Key Issues and Opportunities 3.1 Summary of Existing Terminal Conditions 3.2 Route Profile The Hornby Island Terminal is an unstaffed terminal located on the west The Hornby Island terminal at Shingle Spit connects the communities of side of Hornby Island and provides ferry access to Denman Island via the Hornby Island and Denman Island. The route (Route 22) is served by the Kahloke. Kahloke, a small ferry built in 1973. The Kahloke has a car capacity of 21 AEQ, and can carry a maximum of 200 passengers and crew; the vessel has a Hornby Island Terminal Summary passenger lounge located on the car deck. The vessel sails between Denman Island and Hornby Island several times a Location Hornby Island day, carrying passengers and vehicles on the 10 minute sailing. This route Municipality Islands Trust, Comox Valley Regional District is also travelled by individuals requiring access to Vancouver Island via Denman West (Route 21). The Denman West terminal is approximately 11 Holding Capacity (AEQ) 17 kilometers away from the Denman East terminal. Max. Vehicle Weight (GVW) 63,500 kgs, 8 axels A total annual number of 4060 round trips are contractually delivered. Parking No customer parking However, during peak travel periods the vessel will provide shuttle service, 5 AEQ for crew parking where the ship sails more frequently to address peak demand overloads. Waiting Room Yes Sailings between Denman East and Hornby Island operate year round, and Washrooms Yes space on this route is on a first-come, first-served basis. Dock I Berth MIM - Unstaffed The Kahloke has a voyage classification of sheltered waters and a docking cycle of 1 in 4 years. During Kahloke refit periods the Quinitsa is redeployed to Route 22 to provide scheduled service. The refit relief vessels for this region include Quinitsa and Quadra Queen II.
17 Figure 10: Hornby Island Aerial Photo
18 Kahloke Vessel
Core Service Levels Hours of Service 07:30 to 18:45 12 Sailings per day (Mon, Thurs, Fri) 15 Sailings per day (Fri) Peak Season Service 11 Sailings per day (Sun) 3.3 Key Issues and Opportunities Frequency *The vessel will provide shuttle service during peak The TDP has been informed by community and BC Ferries staff feedback travel periods. Additional sailings are scheduled to in 2017. Based on the comments received during engagement events and address peak demand overloads the analysis of the terminal site and surrounding context, a number of Off Peak Season Service 11 Sailings per day (Mon-Thurs) issues and opportunities emerged. Figure 11 illustrates the current issues Frequency 15 Sailings per day (Fri) associated with the existing condition of the Hornby Island terminal. The 10 Sailings per day (Sat) key opportunities identified are as follows: 9 Sailings per day (Sun) • Improve foot passenger / pedestrian safety and access throughout the Round Trips per Year A total annual number of 4060 round trips are to be contractually delivered terminal by formalizing walking routes and crossing areas • Improve accessibility for pick-up / drop-off traffic to the foot Vessel Description passenger waiting area Class Minor • Provide a dedicated vehicle holding area to improve traffic flow, Maximum Capacity 200 increase vehicle holding area capacity and reduce vehicular conflicts with thru traffic Passenger Capacity 194 Crew Size 6 Vehicle Capacity (AEQ) 21 AEQ Onboard Services Accessible Car Deck Lounge Route and Service Description Distance 1.2 nautical miles Crossing Time 10 minutes
19 Figure 11: Existing Site Plan and Key Issues
20 3.3.1 Traffic Safety Audit and unexpected as a “Do Not Enter” zone. Unfamiliar drivers may enter on top of this without intending to, but then end up stopped and stuck on In 2017 Watt Consulting Group was appointed to undertake a traffic safety the hatched zone. Adjacent to this hatch is an angled parking area; parked review of the terminal to help inform the TDP. The review focused on vehicles could potentially get boxed in. the loading and unloading areas of the terminal, as well as the terminal approach roads, but excluding the dock and marine aspects of the terminal. Pedestrian Accommodation Key problem statements are as follows: • Outside of the immediate dock area, there are no pedestrian paths, although there is a limited grassy shoulder on the west side of Shingle Queues - Impact on Through Traffic Spit Road in some areas north of the Thatch Restaurant. There is a In peak periods, ferry queues extend far along Shingle Spit Road, as far as particular pinch point between the rock outcrop near the terminal 500 meters north of Mt Road. This requires traffic in both directions to use and queue storage area. This places pedestrians on the road with the northbound lane which creates a potential conflict and safety concern motor vehicles, although they can be accommodated off-road in the of vehicles meeting head-on, requiring one to reverse to find a suitable Thatch Restaurant area (albeit on private property); place to pull over. • The low barrier that defines an asphalt walking area is also a barrier Queues - Impact at Driveways and Intersections for accessing the walkway to adjacent vehicles. There are markings and in some cases signage advising ferry traffic to not Drop-off / Pick-up Zone block driveways. Nonetheless, motorists have been observed stopping and There is no designated drop-off or pick-up zone. The parking area near queuing over portions of the “Do Not Block” zones. This can create difficulty the terminal may be used however access to it may be blocked by queues. for non-ferry traffic and property owners to freely access their driveways. Exiting from this area would also require multi-point turns. The Thatch The use of signs and markings for this issue isn’t consistent, and driveways Restaurant area could be used but is not intended for this purpose, and further upstream are not formally accommodated for this despite a known access may be blocked at peak times. issue (for example, one driveway was spray-painted with a yellow hatch). The long driveway at the Thatch Restaurant and Store area is very long
21 Other Less Important Issues: • Cycling facilities not specifically provided; • Faded text on the cycling “Share the Road” tab sign; • Double yellow centreline markings used on Shingle Spit Road, but narrow lanes require a vehicle to cross the centreline to pass a cyclist. This is particularly a concern in the northbound direction, as it is uphill and cyclists are slower on the assent, thus creating a greater speed differential (and impetus to pass) for trailing motorists; • No Speed Hump sign at the speed hump near the curve near the dock. Speed hump design is more of a “Speed Bump” style found in parking lots, and is likely not necessary for speed management in this location close to the dock at the end of the road.
Figure 12: Hornby Island Terminal Photograph
22 Alaska Marine Hwy To the Alaska Highway
37
ALASKA
Smithers
Terrace Prince Rupert 16 Masset
Kitimat
Prince George Yellowhead Hwy
Skidegate Sandspit Alliford Bay
To Jasper 16
HAIDA FIORDLAND RECREATION TWEEDSMUIR Quesnel GWAII AREA PARK
Klemtu Anahim Lake Ocean Falls Bella 97 Coola 20 Nimpo Lake Hagensborg McLoughlin Bay Shearwater Bella Bella Denny Island Puntzi Lake Williams Lake HAKAI Tatla Lake Alexis Creek RECREATION AREA BRITISH COLUMBIA
24
97
Railroad Highways Banff BC Ferries Routes Lillooet 1 Port Hardy Sointula Alaska Marine Highway Kamloops Port Alert Bay McNeill Pemberton Duffy Lake Road Southern Gulf Islands V A N C O U V E R IS L A N D 19 Quadra Cortes Island Langdale Island Merritt Terminal Information Campbell Powell River 99 River 19A Traffic Safety Review Nanaimo Bowen Horseshoe Bay Saltery Bay Gabriola 19 Earls Cove Whistler Island Island 11 AEQ Texada 5 Available Queue within Terminal Area: Island Vancouver(1 Lane) Comox 101 Denman Langdale Issues Hornby Island - Hornby Terminal Island Hornby Princeton Island Bowen Horseshoe Bay Harrison Thetis Island Hot Springs Hope AvailableChemainus Approach Capacity 0 AEQ 19A Island 19 Vancouver 3 Penelakut Island 19A 7 Vesuvius Port 4 1 4 Alberni Departure TsawwassenCANADA Parking Crofton StallsLong Harbour 6 Tofino 19 Bay Tsawwassen Duke Point Salt Spring Galiano Island Nanaimo U.S.A. Sturdies Bay Available Queue within Ucluelet 11Chemainus AEQ Southern Island Gulf Islands Fulford Harbour Terminal Area 1 (Lane)1 (see inset map) Bellingham Village Bay Mill Bay Swartz Bay Port0 AEQ Otter Bay Mayne IslandAvailable Approach Capacity Renfrew Brentwood Bay 5 14 Swartz Bay Pender Sooke Victoria Islands Saturna ParkingIsland Stalls 6 VANCOUVER ISLAND • No formal drop-off/pick-up location.WASHINGTO U-turns N U / L1 P1 | Pinch point between cars Victoria difficult near terminal. and hill. • • QueuesNo formal block drop-off/pick-up access for drop-off/pick-up location. U-turns Seattle L5 | Sign used but no paint vehiclesdifficult and near localterminal. traffic (long walk if drop- to inform drivers to not block • offQueues at back block of access queue for or drop-off/pick-up drive wrong way vehicles in driveway. U / L1 laneand local to get traffic close). (long walk if drop-off at back of See text box X1 | Long driveway interface, • Conflictsqueue or drive can wrongarise; waypotentially in lane to getwhen close). visitors P2 | Informal grass area don't expect a local to drive around the queued cars may stop on “No for pedestrians to/from • Conflicts can arise; potentially when visitors don’t L2 | Observed Parking” markings. queued vehicles. queueexpect a local to drive around the queue. September queue.
X1 L4
L3 | Summer queue up to 500m from Mt Rd.
S2 | Faded text on “Share the Road” Legend sign. L4 | Driveways in this area L Loading have no signs or markings for U Unloading S3 | Double yellow centreline not blocking driveway; in one S Signs & Markings used, but narrow lanes case resident used spray paint. P Pedestrian S1 | No speed require a vehicle to cross C Cyclist hump sign on centreline to pass a cyclist. X Other speed hump.
SINCE 1983 FONT = HAND OF SEAN CONSULTING GROUP = FRANKLIN GOTHIC DEMI COND Since 1983
#501 - 740 Hillside Avenue Victoria, BC V8T 1Z4 (250) 388-9877 Project No: 2245 | Date: December 11, 2017 | Drawn: VN Consulting Group www.wattconsultinggroup.com Figure 13: Traffic Safety Review Key Issues
23 Hornby Island TDP and Terminal Network Master Plan 4Functional Requirements This section outlines the proposed terminal functional requirements and how 4.1 Hornby Island TDP Functional Requirements these conform to the TNMP requirements for a Class 2 Minor / Intermediate The TDP will provide the detailed functional requirements based on the Unstaffed terminal. All future terminal developments at Hornby Island will terminal specific requirements. conform to the Design Requirements outlined in Appendix B – Terminal Class Design Requirements of the TNMP. In addition to the TNMP requirements, the TDP identifies Site Specific Requirements for the Hornby Island terminal. These requirements were identified through discussions with internal and external stakeholders and are due to the uniqueness of the terminal infrastructure and surrounding community needs. The functional design requirements have been established in order to ensure compliance with the two overarching strategic plans. The following sections identify the functional requirements for the Hornby Island terminal relating to the TNMP and Fleet Master Plan, and incorporate the Site Specific Requirements as either (A) Essential – Required bythe TNMP, or (B) Desirable – Identified through the TDP process.
24 4.1.1 Safety and Security
Functional Requirements - Safety and Security
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Integration of Safety Required • CCTV at berth for night watch • Add CCTV to monitor and Security Features • Security Access to storage and crew areas uplands areas and expanded holding lot • Increase vehicle holding capacity at the terminal to reduce vehicle conflicts with queuing traffic along East Road • Incorporate pedestrian and cycling facilities to reduce conflicts between users
Figure 14: Pedestrian Facilities to Reduce Vehicle Pedestrian Conflicts
25 4.1.2 Berths Site Specific Requirements: The berth is to be compatible with the existing Kahloke vessel and a future Minor Class vessel scheduled to replace the Kahloke in 2030 as set out in the 2016 Fleet Master Plan. This is essential to ensure safe, reliable and efficient operations of the terminal.
Functional Requirements - Berths
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Number of Berths 1 Berth 1 Berth which was rebuilt in 2015 1 Berth - Utilize existing berth Berth Interface Minor/Intermediate Standardized Minor/Intermediate (MIM) To be compatible with the (MIM) existing vessel as well as the future Minor replacement vessel, scheduled to be in service in 2030
Figure 15: Hornby Island Terminal Berth
26 4.1.3 Ticketing & Pre-Ticket Area There are no ticketing functions required at the terminal as Hornby Island is an unstaffed MIM terminal.
Functional Requirements - Ticketing and Pre-Ticket Area
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Ticketing Function None None None Self-Ticket Kiosks None None None Turnstiles at None None None Embarkation and Fee Paid Entry Zone
4.1.4 Vehicle Holding Areas Site Specific Requirements:Vehicle traffic arriving at the terminal has been observed to exceed the AEQ requirement, backing up onto Shingle Spit Road. Peak season line ups have been observed to back up significantly, with the maximum observed back up to be at approximately 1 kilometer north along Shingle Spit Road. As a result, there is a need to provide a safe vehicle overflow lane along Shingle Spit Road. Doing so would improve traffic flow and provide thru traffic into the terminal for pick-up / drop-off traffic to help mitigate vehicular conflicts. A separate vehicle staging area could help loading procedures. In an effort to save fuel costs, vehicles are loaded in a certain order depending on weight such that the vessel sails with an appropriate trim. Installing a separate staging lane could allow staff to load the vessel more efficiently improving on-time performance. This is not a requirement for an unstaffed MIM terminal but is a requirement for the other three terminal classes.
Functional Requirements - Vehicle Holding Areas
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Holding Capacity 21 AEQ (1x maximum Existing capacity at the terminal is 17 AEQ (effective Accommodate a holding area Additional capacity above 47 vessel AEQ capacity capacity) of at least 47 AEQ. Signage for AEQ along Shingle Spit Road for an MIM Unstaffed vehicle holding will have to be to reduce safety issues during terminal) clear to ensure that self-sorting peak season can be carried out, acknowl- Note: future vessel edging that there is staff pres- capacity not defined in ent at the terminal during the the 2016 Fleet Master summer months to assist with Plan vehicle staging, particularly when traffic is left over after a sailing Lane Widths Lane widths are Only one holding lane present Lane widths to be the same Additional vehicle staging to be the same. lane to improve vessel loading No delineation of efficiencies commercial/priority and standard vehicles required
27 Figure 16: Denman West Queuing Lane Example
4.1.5 Vehicle Loading & Unloading
Functional Requirements - Vehicle Loading and Unloading
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Control Tower None Required None N/A Ensure good visibility of the holding compound from the vessel Loading and Main car deck - single Single lane Unloading lane
28 4.1.6 Customer Amenities Site Specific Requirements:Customer amenities were identified as part of the public engagement process.
Functional Requirements - Customer Amenities
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Foot and Vehicle
Waiting Room/ Yes Terminal building with waiting room, seating and As per existing Lounges and washroom (2017) Washrooms Satellite Washroom No None N/A Building Covered Outdoor Yes Yes Yes - additional space for picnic Waiting Space, tables Seating and Picnic Tables Customer Service No None N/A Counter Retail Facility Pad with services for 3rd None Not required but pad for party kiosk vendor is desired by Terminal Management/operations (per requests from community) Public Notice Board Yes Yes in waiting room As per existing
ATM No None N/A
Vending Machine Yes None Yes - one vending machine in waiting room Distress Phones Yes No Add distress phone
Water Fountains/ Yes if potable water None (plumbing is roughed in, but there is no Yes if potable water provided Bottle Filling Station exists station) Vehicle Only
Playground, Pet Areas No None N/A Foot Passengers Only
Baggage Service No None N/A (drop-off, handling and transport to Vessel) Escalator, Elevator No None N/A Enclosed Walkway to No None N/A Berths After Ticketing
29 4.1.6 Customer Amenities Site Specific Requirements:Customer amenities were identified as part of the public engagement process. cont.
Functional Requirements - Customer Amenities
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Pick-up/Drop-off Yes No Yes - to be located near Zone waiting room and to accommodate vehicle sizes up to a shuttle bus Parking Yes No Customer short-term parking to be defined and required, around 10 spaces should be sufficient close to the berth. Bus Bays Yes - for large school None Yes, sized to accommodate a bus large school bus
Figure 17: Example of an outdoor waiting space, pick-up/drop-off lane and retail pad
30 4.1.7 Communications & IT Infrastructure Site Specific Requirements: Internet bandwidth is currently very limited at the Hornby site. It is likely that upgrades to the network will need to be provided by the service provider before Wi-Fi can be improved. It is recommended to discuss this with the service provider to understand feasibility and costs.
Functional Requirements - Communications & IT Infrastructure
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Wayfinding (static), Reader Yes TBD Boards Public Address System No None N/A Electronic Toll Booth No None N/A Signage Vehicle Classification No None N/A System Standard BCF IT Systems & Yes IT equipment housed in electrical room As per existing Capacities and Server Room Customer Wi-Fi Yes None Yes Coordinate with communications provider to upgrade internet network to support improved Wi-Fi capability
4.1.8 Administration & Employee Facilities v Functional Requirements - Administration & Employee Facilities
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Ticket Office No None N/A Administration Offices, None N/A Meeting Rooms and Crew Mess Crew, Employee and Visitor Yes (except visitor 5 staff parking spaces (1 per crew member) 6 Staff Parking Spaces Design for flexible additional Parking parking) (Master, Mate, Engineer and space that could be used for two deckhands and one for additional crew parking in Terminal Maintenance). future if larger vessel
31 Figure 18: Install water fountains should Figure 19: Example of an electronic reader board Figure 20: Example of Bike Repair Station potable water become available
4.1.9 Other Terminal Services Site Specific Requirements: Engagement with internal and external stakeholders has helped inform the specific needs (space, sizing, etc.) of the above noted
TNMPv requirements.
Functional Requirements - Other Terminal Services
Criteria TNMP Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Requirement Fleet Support Unit No None N/A
Warehouse/Cross Docking No None N/A Storage for Terminal Ops, Yes No N/A Terminal Maintenance and Fleet Ops Drop Trailer - Holding Area, No None N/A Vessel Staging Area and Office Simulator and Training Room No None N/A Bicycle Access/Egress/Storage Yes None • Sufficient way-finding to safely convey cyclists on and • Sufficient storage / waiting off the vessel space to accommodate • Locate a covered bicycle stand adjacent to the terminal seasonal bike tourists waiting room • Given the high number of cycle tourists and mountain bikers using the ferry a bike repair station would be useful
32 Figure 21: Terminal Storage Should be Screened Appropriately
33 4.1.10 Utilities & Miscellaneous Site Specific Requirements: Sanitary Sewer A new septic field was installed at the terminal adjacent to the foot passenger waiting room in 2017. The septic system was sized to accommodate additional sanitary loading from the customer washroom facility. However, it is not sized for vessel pump ashore.
Functional Requirements - Utilities and Miscellaneous
Criteria TNMP Requirement Existing TDP Essential Functional TDP Desirable Functional Requirement Requirement Compactors Yes None Not required
Environmental & Yes TBD Yes as per existing Containment for Hazardous Goods Generators One to power CCTV None A generator is required at this terminal. except where no night In winter months the island experiences watch – vessel will many power outages. power ramp Potable Water Supply Yes Yes - A reverse osmosis water Yes as per existing treatment system was installed in 2017 (limited water supply) Septic Field or Yes Yes - an onsite Type 2 sewage Yes as per existing Sewage Treatment treatment system and septic field System, or Conveyed installed in 2017 to Sewer System where Possible Pump Ashore Yes - where None - no infrastructure exists No - no infrastructure exists infrastructure exists Shore to Ship Power Yes - at home ports Yes No only Ship to Shore Power Yes Yes No
34 Figure 22: Opportunities for Interpretation and Public Figure 23: Example of Public Art Art should be pursued at the terminal.
35 5Plan Concepts The plan concepts plans have been prepared after careful consideration 5.1 Concept Overview of the issues identified in the supporting baseline report and have been The concept plan includes the following features: influenced by comments received from the Staff Working Group and external stakeholders. The plan concepts highlight key improvements that • Sidewalks for improved foot passenger / pedestrian safety and meet the functional requirements; it supports the goals of the Strategic accessibility of all ages and abilities Master Plans and ultimately meets the needs of terminal customers. • Improved vehicle holding compound to reduce traffic backups and conflicts with thru traffic • Dedicated thru lane for pick-up / drop-off traffic directly to the new foot passenger terminal building Provisions for charter bus parking included • Dedicated parking for customers and vessel staff • Green / open space for an enhanced nature scape, views and customer experience Figure 21 shows the illustrative 25 year concept plan for the Hornby Island terminal. Two options have been developed which can be progressed over time
36 EXIT LANE SHINGLE SPIT ROAD THRU LANE oad r al n d to acco odat old n lan SHINGLE SPIT TO FORD COVE TRAIL HOLDING LANE
I ro d s b l ty or cl Hold n lan alon dr rs and ss l cr s o ld r or a t n tra c