39021-ENV-PL-003 Noise & Vibration Management Plan

Document No.: 59003-ENV-PL-001 Issue Status: A Date of Issue: [Publish Date] 1 of 25

Main Roads Western Australia Southbound Upgrade - Hodges Drive to Hepburn Avenue

Table of Contents

1 Purpose ...... 4 2 Scope of Project ...... 4 2.1 Scope Of Work ...... 4

2.2 Optional Works ...... 6

2.3 Site Location and Existing Environment ...... 8

3 Management of Change ...... 9 3.1 Communication of Changes to Documentation ...... 10

4 Environmental Policy and Commitments ...... 11 Objectives & Targets...... 11 6 Legal & Other Compliance ...... 13 6.1 Standards / Legislation and Guidelines / Specifications ...... 13

6.2 Environmental Aspects and Impacts ...... 13

7 Key impacts ...... 14 7.1 Noise & Vibration Plan Overview ...... 14

7.2 Construction Noise Management ...... 14

7.3 Noise Monitoring ...... 15

7.4 Noise Measurement ...... 16

7.5 Sensitive Receptors ...... 16

7.6 Vibration Management ...... 17

7.7 Exceedance of Vibration Limits ...... 18

7.8 Stakeholder Engagement & Complaints ...... 19

8 Organisational Chart and Team ...... 20 9 Training and Inductions ...... 20 10 Stakeholder Consultation ...... 20 11 Auditing ...... 20 12 Monitoring and Reporting ...... 20

Appendix 1: ISO 14001 Certificate ...... 21 Appendix 2: Key Environmental Aspects, and Impacts Register ...... 22 Appendix 3: Summary of Noise & Vibration Management Actions ...... 24 Appendix 4: Traffic Noise Measurement Specification ...... 26

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 2 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Contact for enquires and proposed changes If you have any questions regarding this document, contact:

Name: Peter Galloway Title: Project Environmental Manager Phone: (08) 6229 3700 Mobile: 0409 337 517 E-Mail: [email protected]

Disclaimer This Management Plan has been prepared for the exclusive use H2H and is subject to and issued in accordance with the agreement between WBHO and NRW. H2H accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this Management Plan by any third party.

Copying this Management Plan without the permission of H2H is not permitted.

Document Review and Approval Note: this is to be signed the Project Manager, Engineers and Supervisors as evidence that they have read the plan and agree to the roles and responsibilities assigned to their position.

Rev Date of Approved By Title Signature Approval

A 06/03/2021 Stuart Douglas Project Manager

B 01 Apr 2021 Stuart Douglas Project Manager

C 19 May 2021 Stuart Douglas Project Manager

0 16 Jun 2021 Stuart Douglas Project Manager

1 26 July 2021 Stuart Douglas Project Manager

2 03/08/2021 Stuart Douglas Project Manager

Amendment Identification

Amendment Date of Section Brief Amendment Description Approved By ID Amendment Reference

A 06/03/2021 All Sections Please refer to Suitability Audit Report B 01 Apr 2021 All Sections Please refer to Suitability Audit Report Stuart Douglas C 19 May 2021 All Sections Please refer to Suitability Audit Report Stuart Douglas 0 16 June 2021 All Sections Please refer to Suitability Audit Report Stuart Douglas

1 26 July 2021 All Sections Please refer to Suitability Audit Report Stuart Douglas 2 03 Aug 2021 7.2 MS Word auto error corrected manually Stuart Douglas Date of Next Review Responsible Persons Jun 2022 Project Manager

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 3 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

1 PURPOSE

The purpose of this Noise and Vibration Management Plan (NVMP) is to provide a framework to align with the H2H Project Environmental Management plan (EMP) as it applies to the Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue project. This document will address Noise and Vibration issues by managing the environmental impacts and implementing mitigation measures when required for the duration of the project.

2 SCOPE OF PROJECT

The Project Works include all investigation, design and construction required to construct a third southbound lane on the Freeway between Hodges Drive and Hepburn Avenue, construct an auxiliary lane between Hepburn Avenue entry Ramp and Warwick Road, upgrade the PSP between Ocean Reef Road and Warwick Station and implement a smart freeway system from Hester Avenue to Warwick Road. The design & construction of the project will commence from early 2021, and planned completion is by mid-late 2022, with a peak number of personnel to reach approx. 100 with works being undertaken by both subcontracted works and self-delivered day labour works. Implementation and Commissioning of the Smart Freeway system will be completed late 2023. The breakdown of the Scope of Works, Base Scope and Optional Works components, are described in Section 2.1 and 2.2 below.

2.1 Scope of Work The Project Works include the following:

 Mitchell Freeway third lane - Design and construction of a third lane on the Mitchell Freeway southbound on the median side between Hodges Drive interchange and Hepburn Avenue interchange, approximately 8.8 km long, to provide a continuous three lane carriageway in accordance with the specified lane configuration and cross section;  Mitchell Freeway entry Ramps - Design and construction of widening or reconstruction of entry Ramps at Hodges Drive and Hepburn Avenue to accommodate future Ramp signals;

 Road safety barriers - Replacement of all existing substandard road safety barriers between the Mitchell Freeway southbound and the Railway from rail underpass No. 1472 to Reid Highway with TL5 concrete barriers. Installation of a median wire rope barrier from rail underpass No. 1472 to Chainage 26050. Design and construction of access gates to the Railway corridor. A continuous road safety barrier on the east side of the Mitchell Freeway from Chainage 17000 to Chainage 26050;  Resurfacing - Resurfacing of existing Pavements where lane markings change. Resurfacing of the Mitchell Freeway southbound carriageway from Chainage 17200 to Chainage 26000, and from Chainage 14250 to Chainage 15800. Resurfacing of Ramps;  Drainage - Design and construction and/or modification of all associated drainage including underground drainage, swales, basins, subsoil drainage and culverts; and  Lighting - Design, installation, modification and upgrading of lighting.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 4 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

 Intelligent Transport System - Design and installation of Intelligent Transport Systems (ITS) to enable Ramp signal installation and operation by others, including: a) ITS conduits, pits, cables and cabinets; b) vehicle detection stations (VDSs); and c) CCTV cameras.  Relocation of existing ITS infrastructure where affected by the works;  Signage and Pavement marking - Removal of signing and Pavement markings no longer required, provision of new signing and Pavement markings and modifications to existing signing and Pavement markings which are required as a consequence of the Project Works;  Services - Relocation or modification of all Services which are affected by work carried out by H2H in order to complete the Project Works;  Revegetation and Landscaping and Urban Design - Design and installation of revegetation and landscaping of all disturbed areas of the Site. Design and installation of urban design elements for the Project including public and community art; and  Modifications - Provision of all connections, modifications and improvements necessary to Connecting Roads and properties affected by the Project Works, including removal of redundant road infrastructure, modifications to drainage, signage, islands and associated new lane markings as necessary.

Provision for future works - The Project Works must be designed and constructed to accommodate future modifications to the road network as follows: a) Installation of Ramp signals on all entry Ramps; and b) Widening the Mitchell Freeway southbound carriageway to a continuous four lanes; Project Design:  Design, verification and preparation of all documentation including detailed construction drawings and specifications in accordance with the design for the Project Works;  Road safety audits;  Design of optional works Issued for construction stage;  Preparation of preliminary designs for future works;  Testing - Testing and commissioning of all equipment prior to opening the Project Works to traffic; and  Others - Any other works described elsewhere in the Scope other than the maintenance obligations described in MRWA Scope clause 7.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 5 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

2.1.1 Design Provision for future works - The Project Works will be designed and constructed to accommodate future modifications to the road network as follows:

 Installation of Ramp signals on all entry Ramps;  Widening the Mitchell Freeway southbound carriageway to a continuous four lanes;  Design, verification and preparation of all documentation including detailed construction drawings and specifications in accordance with the design for Project Works.  Road safety audits;  Design of optional works issued for Construction stage;  Preparation of preliminary designs for future works;  Testing and commissioning of equipment prior to opening the Project Works to traffic; and  Any other works described elsewhere in the Scope other than the maintenance obligations described in MRWA scope clause 7.

2.2 Optional Works Main Roads Western Australia (MRWA) may, at its discretion, add any of the below options to the Project Works.

Optional Works 1 are those parts of the Project Works between Hodges Drive and Hepburn Avenue not constructible without access to the areas of the Site labelled Optional Works 1 on the Site Plans, and include the following:

 Mitchell Freeway entry Ramps - Construction of widening or reconstruction of entry Ramps at Ocean Reef Road and to accommodate future Ramp signals;  Associated infrastructure including retaining walls, drainage signage, line-marking, fencing and lighting;  Drainage - Works outside the existing Freeway verge areas;  Shared paths and footpaths - Construction of a continuous PSP along the east side of the Mitchell Freeway from Ocean Reef Road to Hepburn Avenue including connections to the existing network. Associated infrastructure including retaining walls, drainage signage, line- marking, fencing and lighting. Replacement of existing paths where required;  Structures – Construction of modifications to pedestrian underpass No. 9110 at Whitfords Avenue to create wider path underneath;  Road safety barriers - Works outside the existing Freeway verge areas;  Noise barriers - Construction of traffic noise mitigation structures;  Amenity walls - Construction of amenity walls between Ocean Reef Road and Hepburn Avenue to provide privacy and security to residents;  Accommodation works - Construction of accommodation works to properties impacted by the Project Works including accesses.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 6 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

 Emergency stopping bays - Provision of eight (8) emergency stopping bays on the Mitchell Freeway;  Roadside help phones - Relocation of existing roadside help phones; and  Intelligent Transport System – Construction of ITS associated with future Ramp signals at Ocean Reef Road and Whitfords Avenue comprising conduits, pits, cables, cabinets, cameras and VDS.

Optional Works 2 are those parts of the Project Works between Hepburn Avenue and Warwick Station not constructible without access to the areas of the Site labelled Optional Works 2 on the Site Plans, and include the following:

 Shared paths and footpaths - Design and construction of a continuous PSP along the east side of the Mitchell Freeway from Hepburn Avenue to Warwick Station including connections to the existing network. Associated infrastructure including retaining walls, drainage signage, line marking, fencing, lighting and replacement of existing paths where required including:  Amenity walls - Design and construction of amenity walls between Hepburn Avenue and Warwick Station. Optional Works 3 are those parts of the Project Works between Hester Avenue and Hodges Drive not constructible without access to the areas of the Site labelled Optional Works 3 on the Site Plans.

Freeway Entry Ramps will include the following:  Widening, reconstruction or resurfacing of entry Ramps at Hester Avenue, Neerabup Road, Burns Beach Road and Shenton Avenue to accommodate CRS with the specified lane configuration; and  Associated infrastructure including retaining walls, drainage, road safety barriers, signage, line marking, fencing, lighting and shared path modifications.

Intelligent Transport System will include the following:  Construction of ITS including CRS at Hester Avenue, Neerabup Road, Burns Beach Road and Shenton Avenue, conduits, pits, cables, cabinets, cameras, VMS and VDS.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 7 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

2.3 Site Location and Existing Environment The location of the works, including the optional works along the freeway are shown in the sketch below. The H2H project works run adjacent to the existing freeway and rail line. The railway line runs down the centre of the existing freeway. Additionally, there are residents and businesses operating adjacent to the freeway within 50m of approved project works.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 8 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

3 MANAGEMENT OF CHANGE

Required changes to the this plan during project execution will be reviewed at both project and corporate levels. If required, changes will be approved by both the H2H Project Manager and submitted to the MRWA Project Manager for review.

Changes to the EMS will be initiated due to:

 Environmental Approval non-conformance;  To reflect any changes to management plans inputs or risks;  Contingency actions;  Performance targets not met;  Negative audit results; and  Breach of H2H’s Management processes.

Awareness training may be undertaken following major changes to this plan. The H2H QM-P-024 Change management procedure will be implemented when an issue, site instruction, drawing/ specification change or anomaly, etc. is encountered relating to this management plan.

Any changes associated with the H2H project management system, documentation and drawings will be controlled and authorised in accordance with the H2H QM-P-009 Project Document Control Procedure. Changes associated with design management are enabled via the design change request process and compiled within the design change registers.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 9 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

3.1 Communication of Changes to Documentation

3.1.1 Minor Changes

Minor changes to this NVMP will be approved by the H2H Project Environmental Manager prior to incorporation and application. The project team will then be advised of any changes via Teambinder, Microsoft Teams and Main Roads SharePoint. A brief description of changes will be included in the correspondence generated from the project communications system.

3.1.2 Major Changes

Major changes to this NVMP will be approved by the MRWA Project Manager prior to incorporation and application. Presentations or detailed emails will be prepared by the nominated Business Process Owners (BPO’s) before any changes are implemented within Teambinder, Teams and Main Roads SharePoint. These presentations will then be communicated to the Project team by the on-site H2H Project Environmental Representative. The project team will be advised via Teambinder, Microsoft Teams and Main Roads SharePoint. A brief description of changes will be included in the correspondence generated from the project communications system.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 10 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

4 ENVIRONMENTAL POLICY AND COMMITMENTS This Project NVMP is based on WBHO’s is ISO 14001 certified Environmental Management System and accordingly, any reference to WBHO documents or procedures will correspondingly apply to the H2H project. (See Appendix 1)

The Environmental policy (HSEQ Policy) reflects our commitment to ISO 14001 and will ensure:

 The policy is appropriate to the purpose and context of the H2H project and supports its strategic direction;  It provides a framework for setting environmental objectives;  Includes a commitment to satisfy applicable requirements and legislative approval across the project;  Includes a commitment to continual improvement of the Environmental management system.  The policy and commitment statement are supplied to each of the subcontractors;  The Policy guidelines are part of the environmental induction; and  The policy will be displayed on all noticeboard across the project site.

5 Objectives & Targets In alignment with MRWA scope 4.14(b), noise level objectives are specified as upper limits of traffic noise that apply outside residential buildings and other noise sensitive land uses (as defined in Western Australian Planning Commission State Planning Policy 5.4). They are listed in the construction noise table 2 below. Due to the impracticality of controlling noise at the upper floors of multi-storey buildings, noise assessment is restricted to the ground floor levels. The noise level objectives in Table 1 will be achieved, with a maximum height of noise barriers of 5.0 m. (MRWA Scope 2021)

Environmental objectives and targets are defined in the Australian/New Zealand Standard AS/NZS ISO 14001: 2004 as:

 Environmental Objective: “Overall goal, consistent with the environmental policy, that an organisation sets itself to achieve”  Environmental Target: “Detailed performance requirement, applicable to the organisation that arises from the environmental objectives and that is decided and then achieved to enable the project to meet those objectives”

The objective of this plan is to provide a Noise & Vibration Management Plan (NVMP) to align with:

 MRWA Scope requirements 9.4(j)(ii) and 9.4(k)(i) as presented within the MRWA Scope of Works document;  AS/NZS 2436-2010:2016 Guide to noise and vibration control on construction, demolition and maintenance sites; and  Legislative guidelines.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 11 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

As per MRWA scope requirement 9.4(j)(ii) and 9.4(k)(i), this NVMP outlines the management requirements that will be utilised to address potential construction noise and vibration issues at the proposed Mitchell Freeway Southbound Upgrade – Hodges Drive to Hepburn Avenue Project.

This NVMP will be managed in conjunction with the H2H Environmental Management Plan (EMP) that defines the overall project requirements.

Related project management plans include:

 Integrated Management System (IMS) Manual, 59003-HS-PL-001;  The Health and Safety Management Plan; and  WBHO 59003-QM-PL-001 Quality Management Plan.

One of the key objectives during project works is to avoid noise exceedance or vibration levels as specified in Table 2. H2H will comply with the Environmental Protection Act 1986 (WA), Environmental Protection (Noise) Regulations 1997 (WA) and endeavour to minimise any disruption to public receptors throughout the project. Vibration levels will not exceed 5mm/s during project works.

Table 1 Objectives & Key Performance Indicators for Noise & Vibration

Objective Target Key Performance Indicator

Comply with the Environmental Compliance with the No non-compliance with the Protection (Noise) Environmental Protection Environmental Protection Regulations 1997 W.A. (Noise) Regulations 1997 (Noise) Regulations 1997 Manage vibration to comply with Adjacent residential buildings No evidence of significant industry best practice are not significantly affected by vibration impact on buildings vibration from construction and structures as assessed pre- works construction and post- construction property condition reports Manage noise and vibration to No excessive number of No evidence of significant avoid adverse social impacts Complaints from residents impact on residents, buildings received for excessive noise or and structures as assessed by vibration during construction property reports.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 12 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

6 LEGAL & OTHER COMPLIANCE All works under contract will comply with the Acts and Regulations, and other applicable statutory obligations as stated within the project EMP. Additional statutory obligations not presented within the EMP that are specific to this NVMP are presented within the following sections:

6.1 Standards / Legislation and Guidelines / Specifications For the project the following Australian Standards and relevant Legislation are applicable and to be complied with for the Project works.

Australian Standards

 AS/NZS 2436-2010.:2016 Guide to noise and vibration control on construction, demolition and maintenance sites.

Legislation and Guidelines – Western Australia

 Environmental Protection Act 1986 (WA)  Environmental Protection (Noise) Regulations 1997 (WA).

Specifications

 Scope – Contract 99/19 Mitchell Freeway Southbound Upgrade, Hodges Drive to Hepburn Avenue Project

6.2 Environmental Aspects and Impacts Key Issues from the MRWA scope clause 9.4 relevant to this NVMP and Management process can be found in Appendix 2. Further key Management actions can be found in Appendix 3.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 13 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

7 KEY IMPACTS H2H have assessed the project based on the MRWA project scope and provided a risk assessment as provided in Appendix 2 – Key Environmental Aspects and Management. This register identifies the impacts and controls that will be implemented to mitigate those impacts and the residual risk after controls are implemented.

Management Actions- H2H recognises that to minimise environmental impacts it is important to identify the link between various construction activities and the potential for these activities to impact the environment. The environment is defined as “living things” a physical, biological and social surrounding and describes the interaction between all of these things.

Construction activities undertaken by H2H will be in accordance with state and commonwealth environmental legislation and site-specific environmental aspects identified by H2H. The management measures described, refer specifically to site Noise & Vibration sources that may impact surrounding dwellings and infrastructure.

7.1 Noise & Vibration Plan Overview The NVMP’s focus, is to monitor, minimise or eliminate disturbance to local residents and surrounding dwellings through the use of engineering controls. Noise mitigation controls can be in the form of continuous monitoring, adaptive construction methodologies including the use of specifically designed structures (temporary noise walls).

Main Roads Western Australia (MRWA) Scope conditions outline the parameters, regulations and guidelines that this NVMP will comply to and accordingly is described in the remainder of this document.

7.2 Construction Noise Management The H2H construction site runs adjacent to noise sensitive receptors, and subsequently the below noise level construction site noise parameters are applicable to the project. Noise pollution can have an adverse effect on public places specifically in areas close to the constructions project. Reducing noise at source is the initial objective and the first stage of noise pollution mitigation.

It is noted that the NVMP will align with the environmental standards of the Local Government Authorities (LGA), in this case The , The & The City of Stirling.

Noise levels objectives for the project have been specified as upper limits of traffic noise levels that apply outside residential buildings and other noise sensitive land uses. Noise level objectives in Table 2 must be achieved, with a maximum height of noise barriers of 5.0 m. (MRWA 2020).

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 14 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Table 2 Construction Site Noise Parameters: AS/NZS 2436-201:2016

Time Period Base Objective

Day (16 hour) L 60 dB(A) 6:00am to 10:00pm Aeq

Night (8 hour) L 55 dB(A) 10:00pm to 6:00am Aeq

The above noise levels will be assessed 1.0m from a building, 1.4m above ground level. The noise levels will be recorded to the nearest 0.1dB(A) and then rounded to the nearest 1 dB(A) for reporting and assessment purposes.

As stated in MRWA Scope of Works Clause 8.1(a), Except as required by Law the maximum working hours permitted must be between 7:00 am and 7:00 pm, Monday to Saturday, except that work outside these hours may be permitted for specific operations subject to the approval in writing of the Project Manager and compliance with the noise limits objectives MRWA clause 4.14(b)(ii). No work will be allowed on public holidays except as permitted by Law and then only with the prior approval in writing of the Project Manager.

In the event of night works, noise generation will be of major considerations prior to works being approved. Works that produce excessive noise will be minimised where possible outside of general working hours. These works will be discussed with the Main Roads Project Manager prior to commencing and works will be planned to minimise noise impacting the surrounding area.

H2H will ensure plant and equipment is maintained on a regular basis as far as practicable and in particular ensure factory fitted noise controls are in good working order (e.g. exhausts silencers, comply with occupational health and safety standards); no servicing of machines will occur outside normal working hours.

7.3 Noise Monitoring Noise monitoring will be utilised, if required, to compare with pre-works noise baseline monitoring levels. The testing method will comply with section 5 of AS 2436-2010. All noise measuring equipment will comply with Schedule 4 of the Environmental Protection (Noise) Regulations.

Areas where noise levels exceed the specified site values may require erection of temporary noise barriers, should the above compliance mitigation measures not be sufficient. Where there are concerns around noise levels, then noise monitoring will be undertaken. Noise monitoring will be conducted using sound level meters which meet or exceed requirements of AS IEC 60942-2004 Electroacoustics- Sound calibrators, for class 1 or class 2 sound sources, as the case requires (Schedule 4 of EP Noise Regs).

Traffic noise measurement will be carried out in accordance with Main Roads’ Noise Measurement Specification in Appendix 3. The location of noise measuring equipment must be approved by the MRWA Project Manager before the Hold Point is released.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 15 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Noise monitoring will be conducted in compliance with the Environmental Protection Act 1986 (WA) and the Environmental Protection (Noise) Regulations 1997 (WA). Where the extrapolated noise levels exceed the Noise Level Objectives, H2H will undertake remedial works that will result in compliance.

Other mitigation measures that will be employed by H2H include:

 Limiting works in sensitive areas to the permitted normal working hours;  Ensure the exhaust silencers and mufflers are in good working order and comply with OH&S standards;  The use of reduced speed limits on temporary trafficable surfaces;  Undertaking fabrication work off-site where possible;  Use of material/mulch stockpiles as temporary noise barriers;  Erection of permanent noise walls as soon as possible; and  Distancing work away from existing dwellings where possible, (e.g. mulching cleared material or mechanically mixing of material).

7.4 Noise Measurement  H2H will measure existing noise levels prior to the commencement of the Project Works.  H2H will measure noise levels six months after Completion of section 2 and the removal of traffic management on the main carriageway, and the results extrapolated to the design year, to report on the effectiveness of noise control measures and to ensure compliance with the Noise Level Objectives;  Noise measurement will be implemented in accordance with MRWA Specification; The location of noise measuring equipment will be approved by the Project Manager before the Hold Point is released; and  Where the extrapolated noise levels exceed the Noise Level Objectives,H2H will undertake remedial works which will result in compliance.

7.5 Sensitive Receptors Noise-sensitive land-use and/or development: This is generally determined by land-uses or development as zoned by a local planning scheme or structure plan that is occupied or designed for occupation or use for residential purposes. The H2H project areas of noise and vibration impacts will include:  Dwellings, residential buildings (local community);  Short-stay accommodation;  Caravan parks;  Sports grounds and recreation centres;  Educational establishments, (Schools/ Colleges and Universities);  Child-care premises;  Hospitals and care facilities;  Nursing homes; and  Places of worship.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 16 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

7.6 Vibration Management Excessive vibration may cause disturbance to existing infrastructure in the form of structural change. In some instances, impulsive vibration may be a triggering mechanism that may result in the failure of s building/structural components, that have previously been in a stable state.

Therefore, it is necessary to conduct a property condition survey prior to work commencing, as per MRWA Scope section 9.4(l). The survey will be performed by a third party independent, qualified assessor and approved by MRWA. Any subsequent investigations will be performed by the same individual.

All properties within 100m of the construction zone will be surveyed. The dilapidation survey will be completed for each property and records maintained with the status for each survey.

The report for each property will contain the following:

 Reference number, address, type of dwelling and date assessed;  Properties of heritage significance  Summary of the property type and condition;  Detailed assessment of the property, including photos and descriptions specifically noting any defects or damage to the property; and  Photos of any damage in particular.

In accordance with MRWA Scope clause 9.4(I)The survey will be carried out within the extent of the area that may be affected by the activity. As a minimum the extent of the property condition survey will include:

 All properties within 100 m of any construction activities;  Any nearby properties of heritage significance;  Existing railway stations at greenwood, Whitfords and Edgewater; and  Existing bridges and retaining walls within 20 m of construction works.

A copy of the report will be maintained on the project folder and provided to the homeowner for reference.

At the completion of the H2H project each property owner will be provided the opportunity to request a follow up survey to assess if damage has occurred on the property as a result of the project works.

To minimise the risk of damage to surrounding properties, H2H will limit ground vibrations by ensuring that the ground particle velocities from any necessary operation including vibratory compaction or percussion equipment use cause minimum impact and do not exceed statutory limits that could result in damage to property. Vibration levels will be limited to a 5 mm/s limit.

Low vibration or non-vibrating construction methodologies will be adopted during construction activities close to adjoining properties.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 17 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

In alignment with MRWA Scope cluse 9.4(k): A baseline vibration measurement will be taken in two locations and within a nominated time by the supervisor and will coincide with the commencement of works involving the vibratory compaction and percussion equipment.

H2H suggest that the baseline vibration monitoring should take place in areas adjacent to where the staged construction activities are due to commence.

A map that details the location of the monitors will be produced once determined and agreed with the Main Roads Project Manager. This map will be located within the project office on site.

H2H will continuously monitor vibration levels during construction activities involving the operation of vibratory or percussion equipment. The monitoring equipment will be moved to at least two locations depending the construction works schedule. The monitoring equipment will have Real Time measuring capability and notification, when predetermined vibration limits are exceeded.

Furthermore, the equipment will provide a copy of measurements for each month, and will be submitted to MRWA supervisor, as stated in 9.4(k) of the project Scope.

If a complaint is issued by a resident, H2H will inform MRWA of the complaint and issue a response at the earliest opportunity and no later than 24 hours after the complaint was received. In addition, H2H will take vibration measurements at the impacted residence. If the vibration limits are greater than 5mm/s, limits, H2H will modify the construction method to reduce vibration impacts.

7.7 Exceedance of Vibration Limits If a scenario arises where the allowable vibration limit is exceeded, an alert will be sent via email/text message to site Engineers and the following actions will take place:

 Works involving vibrating or percussion equipment, adjacent to the impacted area will cease, until a less destructive method of construction is found;  The construction methodology will be revised, and alternative means of ground compaction will be investigated;  The compaction equipment may be swapped out for a low/micro vibration or oscillation compactor. These machines are specifically designed to minimise the adverse effects of vibrations to the surrounding structures / environment;  Should any unplanned settlement occur due to vibration then works will be stopped and an alternative method will be developed and trialed to ensure compliance;  When an alternative methodology is agreed upon and approved by the H2H Project Manager, a trial run will take place in the previously impacted area, with the monitoring equipment in place, to clarify that the new methodology does not exceed the specified vibrations limits; and  If/when the alternative methodology has been deemed satisfactory by the H2H Project Manager, any further works involving vibration or percussion equipment in the area will be closely monitored, until that particular activity/task has been completed.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 18 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Table 3 Noise, Vibration Contingency Actions Trigger Action

Immediately investigate the cause of the non- Non-compliance with management compliance and take preventative actions to measures prevent further occurrences  Review management measure’s practicality or relevance.  Consider further education of staff/sub- contractors to ensure understanding and prevent any reoccurrence Manage complaints and ensure a rapid response Complaints received concerning noise occurs or vibration

7.8 Stakeholder Engagement & Complaints H2H will advise the Project Manager and respond to any complaint at the earliest opportunity if received from local residents, but no later than 24 hours after the complaint is received. In addition, H2H will take noise or vibration measurements at the affected residence. If regulatory vibration limits are exceeded, H2H will endeavour to modify the construction method to reduce vibration.

The Community and Stakeholder Engagement Plan will detail response times that are compatible with the Main Roads’ Customer Service Charter. H2H will use the Main Roads’ corporate customer relationship management (CRM) system, CONNECT, and align the management of such enquiries to the Main Roads’ corporate processes.

Prior notification of construction activity impacts including noise and amenity walls and night works will be given to residents and H2H will determining the appropriate community and stakeholder engagement processes for enabling and considering community and stakeholder input into specific noise and vibration issues.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 19 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

8 ORGANISATIONAL CHART AND TEAM The interrelations of project site personnel are described in the Organisational Chart within the main project EMP. The latest revision of the Organisation Chart will be displayed within the project office.

All personnel working on the project have a position description that outlines their site roles and responsibilities. The key personnel involved in the ongoing monitoring and management of this NVMP will be the Health and Safety Manager, the Community Stakeholder and the Environmental Manager. All site personnel will be supported by the administration team as required.

9 TRAINING AND INDUCTIONS

Throughout the term of the contract, training requirements, planning and implementation will be implemented in accordance the WBHO Training, Awareness and Competency procedure QM-P-013 and comply where required with the MRWA training requirements. Training records and renewals will be managed by the H2H HSE Program. Before employees can enter the work site, they will be required to complete the following inductions:

 H2H HSE Induction;  Site Specific Induction; and  A Construction Card if required to work on a construction site (White Card).

Where specific training requirements are identified for site personnel, occupational skills will be updated accordingly. A detailed training matrix will be maintained on site to document all training that is completed by personnel.

10 STAKEHOLDER CONSULTATION Engagement with the local community is detailed within the Community and Stakeholder Engagement Plan for the H2H project. All properties within 100m of the works will be provided with a dilapidation survey to assess the current state of the properties. If complaints regarding damage to these properties are received, then the property will be reassessed and were applicable the damage rectified.

11 AUDITING H2H will regularly audit the project in alignment with the corporate Environmental Management System and government Statutory requirements as documented within the project Environmental Management Plan.

12 MONITORING AND REPORTING Monitoring and reporting of noise and vibration will be undertaken as noted above in Section 7 of this document. Any observed exceedance to noise and vibration limits will be managed as detailed within this document.

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 20 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia (MRWA) Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Appendix 1: ISO 14001 Certificate

This is to certify that: WBHO Infrastructure Pty Ltd ABN 78 089 434 220

Level 10 Australia Place 15-17 William Street WA 6000 AUSTRALIA Level 5 33 Remora Road Hamilton QLD 4007 AUSTRALIA Level 10, 580 St Kilda Road Melbourne VIC 3004 AUSTRALIA 475 Edwards Road Geraldton WA 6530 AUSTRALIA 45 Hope Valley Road Naval Base WA 6165 AUSTRALIA

operates an

ENVIRONMENTAL MANAGEMENT SYSTEM

which complies with the requirements of

ISO 14001:2015

for the following scope

Design Management and Civil Construction Services including Earth Moving, Roadwork, Building Construction, Bridge Construction, Concreting, Underground Services, Containment Areas as well as Industrial Maintenance, Fabrication and Installation of HDPE Pipes and Fittings.

Certificate No: CEM20751

Issued: 26 October 2020 Originally Certified: 14 May 2009 Expires: 2 November 2023 Current Certification: 23 October 2020

Heather Mahon Global Head of Technical Services SAI Global Assurance

Registered by: SAI Global Certification Services Pty Ltd (ACN 108 716 669) 680 George Street Sydney NSW 2000 Australia with SAI Global Pty Limited 680 George Street Sydney NSW 2000 Australia (“SAI Global”) and subject to the SAI Global Terms and Conditions for Certification. While all due care and skill was exercised in carrying out this assessment, SAI Global accepts responsibility only for proven negligence. This certificate remains the property of SAI Global and must be returned to SAI Global upon its request. To verify that this certificate is current please refer to SAI Global On-Line Certification register at http://register.saiglobal.com/

Document No.: 39021-ENV-PL-003 - Issue Status: 2 Page 21 of 28 Date of Issue: 03 Aug 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Appendix 2: Key Environmental Aspects, and Impacts Register

Aspect Impact Risk Objective Target Operational control Residual Responsibility Monitoring rating Risk Rating Noise Public 8M No complaints Duration of Plan implemented and understood by personnel. 3L Project Manager Customer Complaints from the public project Work hours restricted to authorised hours (i.e. Supervisor Complaints daylight hours) Environmental monitored as per Complaints regarding public nuisance, noise, Manager the Objectives and vibration or property damage will be reported Targets register through the Incident reporting process and and reported at communicated to the Main Roads Superintendent Monthly Project in a timely manner. Reviews. No machinery, work or delivery of plant or Internal audit materials is to be undertaken outside of “normal within 6 weeks of working hours” with the exception of dust mobilisation and suppression measures. every 3 months for Equipment is to be maintained on a regular basis the duration of the to as near new condition as far as practicable and project in particular any factory fitted noise controls are in good working order (e.g. exhausts silencers and complies with occupational health and safety standards); no servicing of machines outside normal working hours. Limit the use of engine exhaust brakes in residential areas; Any areas where noise levels exceed the specified values, prominent warning signs will be displayed, and hearing protection will be mandatory. All noise exceedance or complaints be reported as per the Health, Safety and Environmental Incident Management Procedure Vibration Damage to 8M No damage or Duration of No vibrating compaction will be used within 50m 3L Project Manager Customer surrounding complaints from project of any building Supervisor Complaints properties the public No machinery work or delivery of plant to be Environmental monitored as per Public undertaken onsite of “normal working hours” with Manager the Objectives and Complaints the exception of dust suppression measures. Targets register The Main Roads Representative is to be informed and reported at in a timely manner of any such complaint, the

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 22 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue Aspect Impact Risk Objective Target Operational control Residual Responsibility Monitoring rating Risk Rating progress made in dealing with it, and of the Monthly Project reinstatement or repairs to damage carried out. Reviews. All complaints to be reported as per the Health, Internal audit Safety and Environmental Incident Management within 6 weeks of Procedure mobilisation and All site personnel will be informed on the every 3 months for environmental impacts pertaining to the site at the the duration of the site HSE Induction project

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 23 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue Appendix 3 Summary of Noise & Vibration Management Actions Management Action Timing Timing Responsibility

Workforce inductions will include education in Workforce induction Construction Manager CM relation to the minimisation of noise and vibration. Environmental Manager EMF Stakeholder Revelations Manager SRM Selecting machinery and adopting operational Pre- CM, EM practices that will produce the lowest practical Construction level of noise and vibration. Construction activities (including materials Construction CM, EM transport) will be limited between 0700 and 1900 Monday to Saturday, excluding public holidays (standard work hours) unless an out of hours Noise Management Plan is obtained Where construction activities are required outside Construction CM, EM of approved operating hours:  Prepare a Noise & Vibration Management Plan (NMP)  Obtain approval for the NVMP from the City of Joondalup, Wanneroo and Stirling  Ensure all nearby residents are notified prior to works, with details of time period of activity and summary of why the activity is required outside of usual hours.  Reduce noise emissions as much as practicable, e.g. croakers in place of reverse beepers. Property condition surveys will be conducted, and Pre-Construction CM, EM reports prepared for all properties within 100 m of works and with owner consent A complaints register will be established and Pre-Construction SRM maintained Appropriate access routes, staff parking and work Construction CM area conditions will be determined prior to activity

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 24 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue commencing which will minimise noise and vibration impacts on the neighbouring community. Conventional radios will be kept at a reasonable Construction volume and will be required to be turned off immediately if nearby stakeholders complain. Residents in proximity to the Project Area will be Construction SS advised of the proposed construction work schedule

Generators, compressors and other semi-fixed Construction Site Superintendent SS equipment that generates excess noise will be located as far as practicable from nearby residences. Construction and Maintenance schedules will be followed to ensure that all equipment is in good condition. Maintenance schedules will be followed to ensure Construction SS that all equipment is in good condition.

Where practicable, rollers will be selected which Construction CM are able to operate in oscillation mode. Oscillation mode will be used when in close proximity to adjacent structures.

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 25 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

Appendix 4 Traffic Noise Measurement Specification (MRWA APPENDIX 23)

1. General

Noise measurement will involve:

. Measurement of noise on private property. . Use of calibrated equipment. . Verification of data. . Collection of site information, including photographs. . Comprehensive reporting of results. . Supply of digital data (noise levels, site information, photographs). . Provision of maps indicating locations of measurement sites.

The basic requirement is that measurement and equipment complies with AS 2702 Acoustics - Methods for the Measurement of Road Traffic Noise.

2. Microphone Position

The microphone is to be placed in the standard position of 1 metre from the building facade which faces the major road and 1.2 to 1.5 metres above ground floor level. This may necessitate the microphone being set high when compared to ground level in any cases where residences are on high foundations or stumps.

The microphone is to be no closer than 1 metre from any corner of the building and is not to be placed adjacent to an opening window.

3. Noise Measuring Equipment

Equipment is to have been subject to:

. A laboratory calibration within the last 24 months; and . A very recent performance check.

4. Monitoring Period

Hourly noise levels are required for a minimum of three 24-hour normal weekdays. Any noise measurement results for weekends, public holidays or school holidays are outside the scope of this brief and are not to be included in summary tables or the main body of the report.

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 26 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue 5. Weather Conditions

During noise monitoring, the road surface is to be dry and wind conditions will be typical/neutral so as to provide valid noise measurement results. Evidence is to be supplied to confirm compliance with the specified acceptable wind conditions. Rain or unacceptable wind for several hours over the 24-hour period will not necessarily invalidate the daily measurement, but relevant comment is required. Acceptable wind conditions are specified below. Positive wind blows from road to residence, variable wind is considered to be a typical am/pm split of positive and negative winds.

(a) Microphone-road distance up to 20 metres:

(i) variable wind during a 24-hour period up to 19 km/h; or (ii) calm conditions, or continuous positive wind up to 19 km/h.

(b) Microphone-road distance greater than 20 metres:

(i) variable wind during a 24-hour period up to 19 km/h; or (ii) calm conditions, or continuous positive wind up to 11 km/h.

6. Data Verification

Data is to be verified by inspection and professional judgement. Any occasional hourly data considered to be atypical should be replaced by an estimated value. This estimated value is to be in bold italics and an explanatory note is to be placed in an appropriate position.

7. Site Information

For each measurement site detailed information is required, including conditions affecting levels of noise.

Two photographs of each site are required showing:

. Microphone position – so that any future measurement may be made with the microphone in the identical position.

. Road layout – panorama showing overall layout of the major road, and ideally the measurement site in the background indicating how it is situated in relation to the road.

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 27 of 28 Date of Issue: 26 July 2021 Main Roads Western Australia Mitchell Freeway Southbound Upgrade - Hodges Drive to Hepburn Avenue

8. Results

Hourly Data – Results of noise measurements are to list hourly values of L1, L10, Leq and L90, in tabular and graphical form.

Daily Results – A separate table listing all sites, indicating the four daily values of L10(18 hour), Leq(24 hour), Leq(16 hour) 6am to 10pm, and Leq(8 hour) 10pm to 6am on the same date, with levels rounded to 0.1 dB(A). This table will include an average value of the four daily results, rounded to whole numbers. Site number, address and dates will be included.

9. Electronic Versions

Electronic versions of information are to accompany the final report:

. Site information (MS-EXCEL format). . Noise measurement data (MS-EXCEL format). . Photographs in JPEG format, one photograph per file. 10. Report

The noise measurement report will include:

. Procedures used in noise measurements. . Measurement site information, including photographs.

. A summary of the results and a map of the project showing measurement site distribution. . Appendices containing noise level data (in table and graph form) and weather data. . Street Smart maps (1:20000) indicating the location of each measurement site.

Document No.: 39021-ENV-PL-003 - Issue Status: 1 Page 28 of 28 Date of Issue: 26 July 2021