DEPARTMENT WATER AFFAIRS

GLEN ALPINE IRS: LPR008

TECHNICAL FEASIBILITY REPORT

WT13098/Revision 1 Date: 20 August 2014 PREPARED FOR: PREPARED BY: Department Water Affairs WSM Leshika No 2 Rhodesdrift Street Tel: (015) 491 4756 Hampton Court, , 0700 Fax :(015) 491 2086 Tel: (015)290 1200 Fax: (015)295 3249

DEPARTMENT WATER AFFAIRS

GLEN ALPINE RWS: LPR008

TECHNICAL FEASIBILITY REPORT

2

PREPARED FOR: PREPARED BY: Department Water Affairs WSM Leshika No 2 Rhodesdrift Street Tel: (015) 491 4756 Hampton Court, Polokwane, 0700 Fax:(015) 491 2086 Tel: (015)290 1200 Fax: (015)295 3249

CONTENTS

1. PROJECT INTRODUCTION 2. DEMAND ANALYSIS 3. WATER CONSERVATION / WATER DEMAND MANAGEMENT 4. WATER QUALITY 5. ANALYSIS OF EXISTING INFRASTRUCTURE 6. IDENTIFY VARIOUS OPTIONS 7. SOURCES

3

1. PROJECT INTRODUCTION Definition of Problem WSM Leshika Consulting (Pty) Ltd has been appointed as term consultant to assist the Department Water Affairs to update the Implementation Ready Study for LPR008 Glen Alpine Regional Water Scheme previously done by EVN Consulting.

Due to the water shortage and poor water quality prevailing in the Blouberg and Molemole Local Municipalities it is considered to utilize the Glen Alpine Dam water or a Regional Ground Water Scheme to augment and blend the existing groundwater source.

The study is intended to review and update the findings of the previous IRS study done by EVN Consulting with the latest infrastructure, population and water requirement information. The designs have to be altered if needed to incorporate the new information. The study also needs to try and establish alternative options if available.

The study involves the water supply to 78 villages, located in the Blouberg and Molomole local municipalities, which is currently essentially from groundwater. The groundwater potential varies greatly across the area and although many high yielding boreholes exist, water quality is poor (classes 3&4) and cannot be safely utilized without treatment. The operation, maintenance and management of distant boreholes are generally sub-standard which results in borehole installations being damaged, abandoned and not able to operate. Internal reticulations are basic and rudimentary with street standpipes and sub-standard level of service.

4

2. DEMAND ANALYSIS Current Demand Analysis

VILLAGE HOUSE-HOLDS HOUSE-HOLDS POPULATION WATER SUPPLY FROM LOCAL CENSUS 2011 SIZE 2013 WATER DEMAND AADD (kl/d) BALANCE : SOURCES (kl/d) (Based on (kl/d) 2011 Summer Peak Domestic Associated Losses Other TOTAL 2013 Census) PF = 1.5

Ground Surface 2013 2013 2013 2013 2013 2013 Total 2013 w ater Water

Berg-en-Dal 313 4.22 1 365 64 13 15 92 138 80 0 80 58 Ga-Mamoleka 259 4.22 1 130 53 11 13 77 115 40 0 40 75 Ga-Mankgodi 308 4.22 1 344 63 13 15 91 136 250 0 250 - 114 Gorkum 609 4.22 2 657 125 25 30 180 270 180 0 180 90 Grootdraai 273 4.22 1 191 56 11 13 80 120 0 0 0 120 La Rochelle 9 4.22 39 2 0 0 2 4 50 0 50 - 46 Madibeng 201 4.22 877 41 8 10 59 89 30 0 30 59 Morotsi 588 4.22 2 565 121 24 29 174 261 240 0 240 21 Papegaai 271 4.22 1 182 56 11 13 80 120 20 0 20 100 Sebotlana 238 4.22 1 038 49 10 12 71 106 20 0 20 86 Sekhung 334 4.22 1 457 69 14 17 100 150 250 0 250 - 100 Varedig 158 4.22 689 33 7 8 48 71 150 0 150 - 79 Vergelegen 338 4.22 1 475 70 14 17 101 152 60 0 60 92 Gorkum 17 009 802 160 192 0 1 154 1 732 1 370 0 1 370 362 De La Roche 41 4.22 179 8 2 2 12 17 3 3 15 De Villiersdale 157 4.22 685 32 6 8 46 70 0 0 70 De Villiersdale 1 116 4.22 506 24 5 6 35 52 60 60 - 8 De Villiersdale 2 75 4.22 327 15 3 4 22 33 0 0 33 Driekoppies 249 4.22 1 086 51 10 12 73 110 75 75 35 Ga-Ntshireletsa 88 4.22 384 18 4 4 26 38 13 13 26 Kirstenspruit 178 4.22 777 37 7 9 53 80 10 10 70 Mons 279 4.22 1 217 57 11 14 82 124 10 10 114 Nieuw e Jerusalem 25 4.22 109 5 1 1 7 11 10 10 1 Non-Parella 154 4.22 672 32 6 8 46 70 120 120 - 50 Silw ermyn 127 4.22 554 26 5 6 37 56 50 50 6 Sw arts 162 4.22 707 33 7 8 48 71 25 25 46 Thabanantlhana 21 4.22 92 4 1 1 6 9 3 3 6 Silwermyn / Kirstenspruit 7 294 342 68 83 0 493 740 378 0 378 363 Bodie 751 4.22 3 276 155 31 37 223 335 20 20 315 Brodie Hill 556 4.22 2 426 114 23 27 164 246 195 195 51 Dithabaneng 126 4.22 550 26 5 6 37 56 50 50 6 Ga-Hlako 427 4.22 1 863 88 18 21 127 190 90 90 100 Ga-Mabeba 157 4.22 685 32 6 8 46 70 330 330 - 260 Gamakgw ata 23 4.22 100 5 1 1 7 11 96 96 - 86 Ga-Malokela 442 4.22 1 928 111 22 27 160 240 55 55 185 Ga-Mampote 213 4.22 929 44 9 11 64 96 25 25 71 Ga-Maselela 423 4.22 1 845 87 17 21 125 188 234 234 - 46 Ga-Mokopane 187 4.22 816 39 8 9 56 84 120 120 - 36 Kobe 1127 4.22 4 917 283 57 68 408 611 303 303 308 Kutumpa 415 4.22 1 810 104 21 25 150 225 93 93 132 Kw aring 422 4.22 1 841 106 21 25 152 228 90 90 138 Manye 244 4.22 1 064 50 10 12 72 108 125 125 - 17 Miltonduff 1 4 4.22 17 1 0 0 1 2 95 95 - 93 Mokumuru 184 4.22 803 38 8 9 55 82 25 25 57 Mongalo 277 4.22 1 208 57 11 14 82 124 25 25 - 93 Sesalong 84 4.22 366 21 4 5 30 45 90 90 - 45 Udney 1 90 4.22 393 19 4 5 28 42 50 50 - 8 Udney 2 3 4.22 13 1 0 0 1 2 0 0 2 Werden 22 4.22 96 5 1 1 7 11 60 60 - 50 Ga-Hlako 26 947 1 386 277 332 0 1 995 2 993 2 171 0 2 171 630 TOTAL Ga-Raw esi / Gorkum / Silwermyn / Ga-Hlako 51 251 2 530 506 607 0 3 643 5 465 3 919 0 3 919 1 354

5

VILLAGE HOUSE-HOLDS HOUSE-HOLDS POPULATION WATER SUPPLY FROM LOCAL CENSUS 2011 SIZE 2013 WATER DEMAND AADD (kl/d) BALANCE : SOURCES (kl/d) (Based on (kl/d) 2011 Summer Peak Domestic Associated Losses Other TOTAL 2013 Census) PF = 1.5

Ground Surface 2013 2013 2013 2013 2013 2013 Total 2013 water Water

Dalmeny 8 4.22 35 2 0 0 2 4 0 0 99 Dalmeny 35 2 0 0 0 2 4 0 0 0 99 Buffelshoek 4 4.22 17 1 0 0 1 2 90 0 90 - 88 Kgatalala 49 4.22 214 10 2 2 14 21 0 0 0 21 Thalahane 585 4.22 2 552 147 29 35 211 317 60 218 278 257 Thalahane 2 783 158 32 37 0 227 340 150 218 368 190 Avon 2447 4.22 10 675 673 135 162 970 1 454 450 750 1 200 1 004 Bul Bul 83 4.22 362 17 3 4 24 37 0 0 37 Dantzig 2 2 4.22 9 0 0 0 0 0 0 0 0 Ga-Kibi 127 4.22 554 26 5 6 37 56 96 96 - 40 2724 4.22 11 884 615 123 148 886 1 329 270 729 999 1 059 Innes 129 4.22 563 27 5 6 38 58 120 120 - 62 Puraspan 1015 4.22 4 428 279 56 67 402 603 125 523 648 478 Sew ale North 13 4.22 57 3 1 1 5 7 0 0 7 The Glade 6 4.22 26 1 0 0 1 2 0 0 2 Avon 28 557 1 641 328 394 0 2 363 3 545 1 061 2 002 3 063 2 484 Blouberg 795 4.22 3 468 199 40 48 287 430 100 100 330 Dantzig 1 777 4.22 3 390 195 39 47 281 422 75 75 347 Ditatsu 254 4.22 1 108 52 10 12 74 112 0 0 112 Ga-Mamohw ibidu 431 4.22 1 880 108 22 26 156 233 25 25 208 Ga-Mamolele 105 4.22 458 22 4 5 31 47 125 125 - 78 Ga-Mmatemana 257 4.22 1 121 53 11 13 77 115 40 40 75 Ga-Motshemi 231 4.22 1 008 48 10 12 70 104 15 15 89 Ga-Rammutla 1 215 4.22 938 44 9 11 64 96 40 40 56 Ga-Rammutla 2 110 4.22 480 23 5 6 34 50 100 100 - 50 Ga-Tefu 107 4.22 467 22 4 5 31 47 165 165 - 118 Ga-Tshabalala 346 4.22 1 509 87 17 21 125 188 15 15 173 Matshira 177 4.22 772 44 9 11 64 96 50 50 46 Mophamamana 207 4.22 903 43 9 10 62 92 15 15 77 Pickum 1 60 4.22 262 15 3 4 22 33 0 0 33 Pickum 2 239 4.22 1 043 49 10 12 71 106 15 15 91 Schroelen 19 4.22 83 4 1 1 6 9 10 10 - 1 Schroelen 2 54 4.22 236 11 2 3 16 24 10 10 14 Sew ale South 306 4.22 1 335 77 15 18 110 166 30 30 136 Tsw atsane 153 4.22 667 32 6 8 46 70 85 85 - 15 Blouberg 21 128 1 128 226 273 0 1 627 2 440 915 0 915 1 525 Bochem (Helena Franz) 112 4.22 489 31 6 7 44 66 300 0 300 - 234 Bochem North 412 4.22 1 797 113 23 27 163 244 150 0 150 94 Bochum 766 4.22 3 342 211 42 51 304 456 150 252 402 306 Borkum 15 4.22 65 3 1 1 5 7 10 0 10 - 3 Cumbrae (Senw abarw ana) 1516 4.22 6 614 417 83 100 600 901 210 1 113 1 323 691 Ga-Mashalane 211 4.22 920 43 9 10 62 92 120 0 120 - 28 Witten 1311 4.22 5 719 270 54 65 389 584 255 0 255 329 18 946 1 088 218 261 0 1 567 2 350 1 195 1 365 2 560 1 155 TOTAL Thalahane / Avon / Blouberg / Senwabarwana 71 414 4 015 803 965 0 5 783 8 675 3 321 3 585 6 906 5 452 TOTAL BLOUBERG LM 122 700 6 547 1 309 1 572 0 9 428 14 143 7 240 3 585 10 825 6 806

The current water demand situation shows a deficit of 6 806 Kl/day currently when the 1.5 times Summer Peak factor is taken into consideration. That is a total of 2,48 Mm³/a and shows that the amount of water available from the Glen Alpine dam, 2,18 Mm³/a, is not sufficient to service the area up to required service levels.

The level of service taken into consideration was mostly according to RDP standards, but with an overall target as follows: • Basic supply at 35 l/c/d for 80% of the area • Higher supply at 90 l/c/d for 18% of the area • Urban supply at 150l/c/d for 2% of the area

6

Future Demand Projections

VILLAGE HOUSE- HOUSE- POPULATION POPULATION HOLDS HOLDS 2013 2033 WATER SUPPLY FROM LOCAL CENSUS SIZE (Based on WATER DEMAND AADD (kl/d) BALANCE : SOURCES (kl/d) 2011 2011 (kl/d) Census) Summer Domestic Associated Losses Total 2033 Peak PF = 1.5

Ground Surface 2033 2033 2033 2033 2033 Total 2033 w ater Water

Berg-en-Dal 313 4.22 1 365 1 312 83 17 10 110 164 80 0 80 84 Ga-Mamoleka 259 4.22 1 130 1 086 68 14 8 90 134 40 0 40 94 Ga-Mankgodi 308 4.22 1 344 1 291 81 16 10 107 161 250 0 250 - 89 Gorkum 609 4.22 2 657 2 552 161 32 19 212 318 180 0 180 138 Grootdraai 273 4.22 1 191 1 144 72 14 9 95 143 0 0 0 143 La Rochelle 9 4.22 39 38 2 0 0 2 4 50 0 50 - 46 Madibeng 201 4.22 877 842 53 11 6 70 104 30 0 30 74 Morotsi 588 4.22 2 565 2 464 155 31 19 205 308 240 0 240 68 Papegaai 271 4.22 1 182 1 136 72 14 9 95 143 20 0 20 123 Sebotlana 238 4.22 1 038 998 63 13 8 84 125 20 0 20 105 Sekhung 334 4.22 1 457 1 400 88 18 11 117 175 250 0 250 - 75 Varedig 158 4.22 689 662 42 8 5 55 83 150 0 150 - 67 Vergelegen 338 4.22 1 475 1 417 89 18 11 118 177 60 0 60 117 Gorkum 17 009 16 342 1 029 206 125 1 360 2 040 1 370 0 1 370 670 De La Roche 41 4.22 179 172 11 2 1 14 21 3 3 19 De Villiersdale 157 4.22 685 658 41 8 5 54 81 0 0 81 De Villiersdale 1 116 4.22 506 486 31 6 4 41 62 60 60 2 De Villiersdale 2 75 4.22 327 314 20 4 2 26 39 0 0 39 Driekoppies 249 4.22 1 086 1 044 66 13 8 87 131 75 75 56 Ga-Ntshireletsa 88 4.22 384 369 23 5 3 31 46 13 13 33 Kirstenspruit 178 4.22 777 746 47 9 6 62 94 10 10 84 Mons 279 4.22 1 217 1 169 74 15 9 98 147 10 10 137 Nieuw e Jerusalem 25 4.22 109 105 7 1 1 9 14 10 10 4 Non-Parella 154 4.22 672 645 41 8 5 54 81 120 120 - 39 Silw ermyn 127 4.22 554 532 34 7 4 45 67 50 50 17 Sw arts 162 4.22 707 679 43 9 5 57 85 25 25 60 Thabanantlhana 21 4.22 92 88 6 1 1 8 12 3 3 10 Silw ermyn / Kirstenspruit 7 294 7 008 444 89 54 587 880 378 0 378 503 Bodie 751 4.22 3 276 3 148 198 40 24 262 392 169 - 242 - 73 223 Brodie Hill 556 4.22 2 426 2 330 147 29 18 194 292 128 1 129 164 Dithabaneng 126 4.22 550 528 33 7 4 44 65 28 6 34 37 Ga-Hlako 427 4.22 1 863 1 790 113 23 14 150 224 98 - 59 39 127 Ga-Mabeba 157 4.22 685 658 41 8 5 54 81 35 275 310 46 Gamakgw ata 23 4.22 100 96 6 1 1 8 12 5 88 93 7 Ga-Malokela 442 4.22 1 928 1 853 175 35 21 231 347 186 - 138 48 160 Ga-Mampote 213 4.22 929 893 56 11 7 74 111 48 - 50 - 2 64 Ga-Maselela 423 4.22 1 845 1 773 112 22 13 147 221 96 87 182 125 Ga-Mokopane 187 4.22 816 784 49 10 6 65 97 41 56 97 56 Kobe 1127 4.22 4 917 4 724 446 89 54 589 884 476 - 191 286 408 Kutumpa 415 4.22 1 810 1 739 164 33 20 217 325 175 - 89 86 150 Kw aring 422 4.22 1 841 1 769 167 33 20 220 331 178 - 95 84 152 Manye 244 4.22 1 064 1 023 64 13 8 85 127 55 40 95 72 Miltonduff 1 4 4.22 17 17 1 0 0 1 2 1 94 94 1 Mokumuru 184 4.22 803 771 49 10 6 65 97 43 - 39 3 55 Mongalo 277 4.22 1 208 1 161 73 15 9 97 145 63 - 72 - 10 82 Sesalong 84 4.22 366 352 33 7 4 44 65 35 53 88 30 Udney 1 90 4.22 393 377 24 5 3 32 48 20 18 38 28 Udney 2 3 4.22 13 13 1 0 0 1 2 1 - 1 - 1 1 Werden 22 4.22 96 92 6 1 1 8 12 5 52 57 7 Ga-Hlako 26 947 25 890 1 958 392 238 2 588 3 881 1 886 - 208 1 678 1 995 TOTAL Ga-Raw esi / Gorkum / Silwermyn / Ga- 51 251 49 239 3 431 686 417 4 534 6 801 3 634 - 208 3 426 3 168

7

VILLAGE HOUSE- HOUSE- POPULATION POPULATION HOLDS HOLDS 2013 2033 WATER SUPPLY FROM LOCAL CENSUS SIZE (Based on WATER DEMAND AADD (kl/d) BALANCE : SOURCES (kl/d) 2011 2011 (kl/d) Census) Summer Domestic Associated Losses Total 2033 Peak PF = 1.5

Ground Surface 2033 2033 2033 2033 2033 Total 2033 water Water

Dalmeny 8 4.22 35 34 2 0 0 2 4 1 - 2 - 1 2 Dalmeny 35 34 2 0 0 2 4 1 - 2 - 1 2 Buffelshoek 4 4.22 17 17 1 0 0 1 2 1 89 89 1 Kgatalala 49 4.22 214 205 13 3 2 18 26 12 - 16 - 4 14 Thalahane 585 4.22 2 552 2 452 232 46 28 306 460 248 22 270 211 Thalahane 2 783 2 674 246 49 30 325 488 261 94 355 227 Avon 2447 4.22 10 675 10 256 1 431 286 172 1 889 2 834 1 864 20 1 884 970 Bul Bul 83 4.22 362 348 22 4 3 29 44 20 - 29 - 10 24 Dantzig 2 2 4.22 9 8 1 0 0 1 2 2 - 1 1 0 Ga-Kibi 127 4.22 554 532 34 7 4 45 67 30 52 82 37 Indermark 2724 4.22 11 884 11 417 899 180 108 1 187 1 780 894 - 75 820 886 Innes 129 4.22 563 541 34 7 4 45 67 29 74 103 38 Puraspan 1015 4.22 4 428 4 254 593 119 71 783 1 174 772 158 930 402 Sew ale North 13 4.22 57 54 3 1 0 4 5 1 - 5 - 4 5 The Glade 6 4.22 26 25 2 0 0 2 4 2 - 2 0 1 Avon 28 557 27 436 3 019 604 362 3 985 5 977 3 614 192 3 806 2 363 Blouberg 795 4.22 3 468 3 332 315 63 38 416 624 337 - 247 90 287 Dantzig 1 777 4.22 3 390 3 257 308 62 37 407 610 329 - 265 64 281 Ditatsu 254 4.22 1 108 1 065 67 13 8 88 133 58 - 89 - 31 74 Ga-Mamohw ibidu 431 4.22 1 880 1 806 171 34 21 226 339 184 - 164 19 156 Ga-Mamolele 105 4.22 458 440 28 6 3 37 55 24 88 111 31 Ga-Mmatemana 257 4.22 1 121 1 077 68 14 8 90 134 58 - 50 8 77 Ga-Motshemi 231 4.22 1 008 968 61 12 7 80 120 51 - 67 - 16 70 Ga-Rammutla 1 215 4.22 938 901 57 11 7 75 113 49 - 35 15 64 Ga-Rammutla 2 110 4.22 480 461 29 6 3 38 57 23 61 85 34 Ga-Tefu 107 4.22 467 448 28 6 3 37 55 24 128 151 31 Ga-Tshabalala 346 4.22 1 509 1 450 137 27 16 180 271 145 - 137 8 125 Matshira 177 4.22 772 742 70 14 8 92 138 74 - 27 47 64 Mophamamana 207 4.22 903 868 55 11 7 73 110 48 - 56 - 9 62 Pickum 1 60 4.22 262 251 24 5 3 32 48 26 - 26 0 22 Pickum 2 239 4.22 1 043 1 002 63 13 8 84 125 55 - 69 - 15 71 Schroelen 19 4.22 83 80 5 1 1 7 11 5 3 8 6 Schroelen 2 54 4.22 236 226 14 3 2 19 28 12 - 10 2 16 Sew ale South 306 4.22 1 335 1 283 121 24 15 160 240 130 - 103 27 110 Tsw atsane 153 4.22 667 641 40 8 5 53 80 33 31 64 46 Blouberg 21 128 20 298 1 661 332 200 2 193 3 290 1 663 - 1 036 628 1 627 Bochem (Helena Franz) 112 4.22 489 469 65 13 8 86 129 85 246 331 44 Bochem North 412 4.22 1 797 1 727 241 48 29 318 477 315 - 49 266 163 Bochum 766 4.22 3 342 3 211 448 90 54 592 887 583 32 616 304 Borkum 15 4.22 65 63 4 1 0 5 7 3 4 7 5 Cumbrae (Senw abarw ana) 1516 4.22 6 614 6 354 886 177 106 1 169 1 754 1 153 592 1 745 600 Ga-Mashalane 211 4.22 920 884 56 11 7 74 111 50 46 96 62 Witten 1311 4.22 5 719 5 495 346 69 42 457 686 297 - 203 93 389 Senw abarw ana 18 946 18 203 2 046 409 246 2 701 4 052 2 485 669 3 154 1 567 TOTAL Thalahane / Avon / Blouberg / 71 414 68 612 6 972 1 394 838 9 204 13 807 8 024 - 80 7 943 5 785 TOTAL BLOUBERG LM 122 700 117 884 10 405 2 081 1 255 13 741 20 612 11 659 - 291 11 368 8 953

According to the Infrastructure audit done the daily demand is 8 953Kl/day that amounts to 3,27 Mm³/a.

Future level of service is proposed to be house connections with at least enough water to meet the free basic water requirement, but with an overall target as follows: • Basic supply at 45 l/c/d for 70% of the area • Higher supply at 90 l/c/d for 25% of the area • Urban supply at 180l/c/d for 5% of the area A summer peak factor of 1.5 times normal demand was also taken into consideration.

8

3. WATER CONSERVATION / WATER DEMAND MANAGEMENT The townships water reticulations are poorly maintained and that results in greater water losses. A culture of non-payment also persists in the area. Illegal connections are also found in some areas, as well as illegal connections to adjacent informal dwellings, similar to the illegal supply of electricity. Where payment is collected, a flat rate is often charged given that customer consumption metering is often non-existent.

The sustainability of the services will depend on the ability to maintain the reticulation systems, to minimize household plumbing leakages and to maintain a good assurance of supply so as to justify the payment for those services. Where street standpipes are installed, losses associated with poor control (such as running taps) or illegal connections are widespread.

Most rural areas do not have access to water services, and rural communities rely mostly on water obtained directly from streams or boreholes. The provision of water services to rural areas, however, depends on prevailing local conditions in respect to the possible source of water (surface or ground water), its proximity and the population density. Providing water to within 200 meters of a household, as required by the minimum standard of services, can be a challenge. Reasons include the low population density and the cost of pumping water from sources that are situated much lower than the dwellings to be supplied. In some cases, wastage through poor control of standpipes also occurs. The problem is compounded by the fact that most consumers with limited water consumption cannot afford to pay for the cost of being supplied with water. Targets for cost recovery for the water services authorities or providers in charge of these areas are often not achieved and government intervention, by way of subsidies or administrative support, is often required.

The opportunity for WC/WDM in rural areas will be to contribute to the sustainability of the services once they have been developed. A system of prepaid water meters in the rural areas is proposed to ensure water is used more efficiently manner and to limit wastages.

4. WATER QUALITY Water quality data from GRIP database provide the statistical support to this study (Figure 2.4). In the Blouberg LM, a total of 306 boreholes have meaningful data attached; (52%) are associated with unacceptable water quality ( Class III – Class IV ); 198 boreholes (27%) have marginal water quality ( Class II ) and only 110 boreholes (21%) have acceptable water quality ( Class 0 – Class I ). In Molemole, the database contains 255 sampled boreholes whereby the following generalizations can be made

A total of 80 boreholes (31%) are associated with unacceptable water quality ( Class III –Class IV ); 98 boreholes (39%) have marginal water quality (Class II ) and 77 boreholes (30%) have acceptable water quality ( Class 0–Class I ).

9

10

5. ANALYSIS OF EXISTING INFRASTRUCTURE Reticulation Ga Hlako RWS

Current Service Levels

% % % % 100% Adequate Adequate Adequate New Settlement name House Yard Standpipes extension 90% connection connection needs Ga-Malokela - 5 15 80 80% Kwaring - 15 40 45 Sesalong - 7 23 70 70% Ga-Maboth - 15 40 45 60% Ga-Mabeba - 15 55 30 Ga-Mokopane - 15 35 50 50% Ga-Maselela - 15 60 25 Werden - 15 60 25 40% Mokumuru - 15 35 50 30% Gamakgwata - 10 20 70

Bodie - 10 30 60 20% Manye - 15 45 40 Dithabaneng - 7 23 70 10% Mongalo - 15 45 40 0% Udney 1 - 15 45 40

Ga-Mampote - 7 23 70 Kobe Bodie Manye Kwaring Werden Udney1 Sesalong Mongalo Kutumpa Ga-Hlako - 8 22 70 Ga-Hlako BrodieHill Mokumuru Ga-Maboth Ga-Mabeba Ga-Maselela Miltonduff 1 Ga-Malokela Dithabaneng Miltonduff 1 80 Gamakgwata - 5 15 Ga-Mampote Ga-Mokopane Brodie Hill - 15 40 45 Adequate House connection Adequate Yard connection Kobe - 15 45 40 Adequate Standpipes New extension needs Kutumpa - 15 40 45

Gorkum GWS

Current Service Levels

% % % % 100% Adequate Adequate Adequate New Settlement name 90% House Yard Standpipes extension 80% connection connection needs 70% Berg-en-Dal - 5 15 80 60% Ga-Mamoleka - 5 10 85 50% Gorkum - 15 40 45 40% Varedig - 15 60 25 30% 20% Sekhung - 5 20 75 10% Morotsi - 10 30 60 0% Berg-en-Dal Ga-Mamoleka Gorkum Varedig Sekhung Morotsi

Adequate House connection Adequate Yard connection Adequate Standpipes New extension needs

11

Silwermyn / Kirstenspruit GWS

Current Service Levels

% % % % 100% Adequate Adequate Adequate New Settlement name House Yard Standpipes extension 90% connection connection needs 80% Mons - 15 45 40 Kirstenspruit - 15 50 35 70% De La Roche - 10 30 60 60% Non-Parella - 15 60 25 Swarts - 15 60 25 50% Thabanantlhana - 10 30 60 40% De Villiersdale - 15 20 65 De Villiersdale 2 - 5 20 75 30% Driekoppies - - 10 90 20% Nieuwe Jerusalem - 8 30 62 Ga-Ntshireletsa - 15 45 40 10% Silwermyn - 5 30 65 0% De Villiersdale 1 - 15 60 25 Papegaai - 15 45 40 Ga-Mankgodi - 15 45 40 Vergelegen - 10 30 60 Grootdraai - 15 45 40 Adequate House connection Adequate Yard connection Madibeng - 8 25 67 Adequate Standpipes New extension needs Sebotlana - 5 20 75

According to the Infrastructure Audit done the existing infrastructure with regard to the reticulation is not up to RDP standards and has to be upgraded to meet the required standard.

12

Storage Ga Hlako RWS

Water storage Existing required Additional storage Problem Existing storage Settlement name storage required statement (Kl) (kl - 48hrs) (Kl)

Ga-Malokela 160 112.40 47.60

Kwaring Storage adequate 160 107.31 52.69

Sesalong 110 20.39 89.61

Additional storage Ga-Maboth requirements for 160 169.16 -9.16 new extensions

Ga-Mabeba Storage adequate 110 38.23 71.77

Ga-MokopaneAdditional storage 80 45.32 34.68 requirements for Ga-Maselelanew extensions 160 102.51 57.49

Werden 80 5.36 74.64

MokumuruStorage adequate 110 46.94 63.06

Gamakgwata 80 5.60 74.40

Bodie Additional storage 220 190.67 29.33 requirements for Manye new extensions 80 61.95 18.05

Dithabaneng Storage adequate 110 32.14 77.86

Additional storage Mongalo requirements for 160 70.66 89.34 new extensions

Udney 1 Storage adequate 110 21.91 88.09

Ga-MampoteAdditional storage 80 54.33 25.67 requirements for Ga-Hlako new extensions 160 108.41 51.59

Miltonduff 1 Storage adequate 40 0.24 39.76

Brodie Hill 160 141.16 18.84 Additional storage Kobe requirements for 180 299.62 -119.62 new extensions Kutumpa 80 105.53 -25.53

Sub-total 850.17

13

Gorkum GWS

Water storage Existing required Additional storage Problem Existing storage Settlement name storage required statement (Kl) (kl - 48hrs) (Kl)

Berg-en-Dal 110 75.85 34.15 Storage adequate Ga-Mamoleka 110 62.77 47.23

Additional storage Gorkum requirements for 160 161.64 -1.64 new extensions

Varedig 80 42.14 37.86

Sekhung Storage adequate 110 80.94 29.06

Morotsi 160 142.50 17.50

Sub-total 164.16

14

Silwermyn / Kirstenspruit GWS

Water storage Existing required Additional storage Problem Existing storage Settlement name storage required statement (Kl) (kl - 48hrs) (Kl)

Mons Additional storage 110 67.61 42.39 requirements for Kirstenspruitnew extensions 80 43.34 36.66

De La Roche Storage adequate 60 9.98 50.02

Non-ParellaAdditional storage 80 37.50 42.50 requirements for Swarts new extensions 80 39.45 40.55

Thabanantlhana Storage adequate 60 5.11 54.89

Additional storage De Villiersdale requirements for 80 41.87 38.13 new extensions

De Villiersdale 2 Storage adequate 60 18.26 41.74

Additional storage Driekoppies requirements for 80 66.40 13.60 new extensions

Nieuwe Jerusalem Storage adequate 60 6.09 53.91 Ga-Ntshireletsa Storage adequate 60 21.43 38.57

Silwermyn 60 33.71 26.29

De Villiersdale 1 60 28.24 31.76 Additional storage Papegaairequirements for 110 71.93 38.07 new extensions Ga-Mankgodi 160 82.14 77.86

Vergelegen 160 89.71 70.29

Grootdraai Storage adequate 160 72.46 87.54

Madibeng Additional storage 80 53.60 26.40 requirements for Sebotlana new extensions 80 63.17 16.83

Sub-total 827.99

The Infrastructure Audit indicates that the required 48 hours of storage required is adequate at present.

15

6. IDENTIFY VARIOUS OPTIONS 6.1 Option 1 Phased development is deemed essential in a scheme of this magnitude in which each phase would provide a functional system. The first phase of the Glen Alpine- Bulk Supply System will consist of the following main elements: • Abstraction at the Glen Alpine dam comprising a raw water pump station and raw water supply pumpline. • The first 4000kl/day module of the water treatment works with an ultimate capacity of 8000 kl/day. • Pump station mechanical/electrical equipment and pump station building. • Clear water pump main to a reservoir at Sebotlana. • 2.4 Ml command reservoir at Sebotlana. • Electricity supply to the waterworks site and pump station buildings.

Further Phases (Bulk conveyance system) 1. Gravity mains to Senwabarwana 1.1 350 dia x 26,2 km 1.2 300 dia x 17,6 km

2. Terminal System: Senwabarwana to Mogwadi 2.1 Pump system 15 kW 2.2 Pump main 150 dia x 6,5 km 2.3 Terminal Reservoir 1 800 kl 2.4 Gravity connector main to Mogwadi area : 150 dia x 4 km

6.2 Option 2 Establishment of a Regional Ground Water Scheme The most efficient procedure in using groundwater as water supply option for the Glen Alpine IRS would be to focus mainly on the 6 schemes indicated on Figure 6.2.1 and Figure 6.2.2. The schemes are located on geostatistical- computed boundaries with a green to blue hue and the colours indicate a groundwater potential greater than 100 kl/day. This computations were outputted during a regional groundwater resource assessment protocol conducted in February 2014 under the project name WM14000 Regional Study of Hydrogeological Characteristics at Four Local Municipalities within Capricorn District .

The protocol identified high groundwater potential areas in Blouberg LM area along and between the Klein Tshipise and Tshipise faults. Alluvium along the Mogalakwena River, along the Brak River.

16

Figure 6.2.1

Figure 6.2.2

17

This groundwater potential has been confirmed from recently pump tested boreholes during the completion of project WM14030 Hydrological Report Pertaining to the Development of Groundwater at Brilliant Village and Ga-Mokwele Village, “Senwabarwana GWS”, and warrant further exploration in other schemes. The designated schemes are Avon GWS, Blouberg RWS, Senwabarwana GWS, Blouberg RWS, Ga-Hlako RWS, and Taaiboschgroet.

It is recommended that a detailed groundwater development program be initiated to test the validity of the study WM14000 and to augment water demand. This can be achieved by utilizing an integrated groundwater exploration approach, viz: hydrocensus, tectonics and geodynamics analysis, stress / strain analysis, field structural mapping, remote sensing and detailed surface geophysical siting techniques. Pump testing of existing boreholes and drilling and testing of new boreholes where potential high yielding aquifers may exist. Conceptualize flow dynamics (interconnectivity), regional directional permeability, transmissivity, flow paths (including dating and tracing of deep water) in the identified water-bearing structural features is envisaged. Determine storage capacity and storage coefficients (and sustainability yield constraints) of the various geological domains and its reliability during droughts using appropriate investigative techniques (scientific test pumping) and water balance models developed by WSM Leshika.

The estimated cost of the project is detailed below.

ITEM DESCRIPTION UNITS UNIT COST TOTAL COST 1 Hydrocensus 25 R 3 600.00 R 90 000.00 (Days) 2 Pump Testing 30 R 25 000.00 R 750 000.00 of Existing Boreholes (Contractor) 3 Borehole Siting 25 R 6 500.00 R 162 500.00 (Days) 4 Drilling of New 50 R 85 000.00 R 4 250 000.00 Boreholes (Contractor) 5 Pump Testing 40 R 25 000.00 R 1 000 000.00 of New Boreholes (Contractor) 6 Field Work 120 R 6 500.00 R 780 000.00 Supervision of Contractors Drilling and Pump Testing (Days)

18

7 Modelling 40 R 6 000.00 R 240 000.00 (hours) 8 REPORTING 6 R 7 500.00 R 45 000.00 FOR EACH WELL FIELD AREA PER GWS SUB TOTAL R 7 317 500.00 VAT @ 14 % R 1 024 450.00 TOTAL R 8 341 950.00 UNIT COST PER WELL FIELD AREA PER R 2 085 487.50 GWS DURATION OF STUDY 6 Month

7. SOURCES The following documentation was assessed and used as background information. • Glen Alpine LPR008 Implementation Readiness Overview, 29 May 2009 – EVN Africa Consulting (Pty) Ltd • Glen Alpine LPR008 Resume, 25 June 2009 – EVN Africa Consulting (Pty) Ltd • Glen Alpine LPR008 Implementation Status, 25 February 2010 – EVN Africa Consulting (Pty) Ltd • Capricorn Water Services Business Master Plan – Demographic Analysis Version 1, October 2013 – AECOM • Glen Alpine RWS Feasibility Study – Socio-Economic Assessment, March 2008 – Pieterse du Toit and Associates CC • Infrastructure Audit, April 2014 – Wayo Consulting • Glen Alpine IRS Scoping Report, 30 May 2014 – WSM Leshika Consulting (Pty) Ltd • Water Conservation and Water Demand Management Strategy for the Water Services Sector, August 2004

19