Public Disclosure Authorized Resettlement Action Plan

Rehabilitation and Upgrading Road Sections from

Ambepussa (00km) - (90+500km) - A006 Kanthale (157km) - (200km) - A006

Public Disclosure Authorized

World Bank Funded Road Sector Assistance Project (II)

Public Disclosure Authorized

Ministry of Highways and Road Development The Government of Democratic Socialist Republic of Sri Lanka

January, 2011

The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily represent those of the Bank’s Board of Directors, Management or staff and may be preliminary in nature. Public Disclosure Authorized

Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Summary 1. The Project.

The Road Sector Assistance Project II (RSAP II) aims at improving two road sections of A006 highway. The total length of these road sections is 133km. The road sections run through four provinces of the country. (Sri Lanka is administratively divided into 9 provinces).

A detailed social assessment was carried out for these road sections selected for rehabilitation. An Entitlement Matrix was also prepared to define categories of PAPs and types of mitigation measures.

The Resettlement Plan is prepared in compliance with the Government‟s National Policy on Involuntary Resettlement and World Bank‟s Policies in particular on Operational Policy (OP): 4.12.

1.2 Proposed Road sections of the project

The project will improve and rehabilitate the following two road sections of the A006 highway.

Table 1 - Road sections to be rehabilitated under the project Road Road Name Length Beneficiary Provinces (kms)

A006 – Dambulla Sabaragamuwa, North Western, Road sections Central. (00km – 90km) 90

A006 Kanthale-Trincomalee Eastern Road Sections (157km-200km) 43

(Source- Social survey for RAP 2010)

Ambepussa – Dambulla road section of A006 highway will be packaged in to four sections and Kanthale-Trincomalee road section will be packaged in to two sections as follows;

 Package 1 – from Ambepussa (0.0km) to (23km)  Package 2 – from Pothuhera (23km) to Ibbagamuwa (47km)  Package 3 – from Ibbagamuwa (47km) to Galewela (69km)  Package 4 – from Galewela (69km) to Dambulla (90km)  Package 5 – from Kanthale (157km) to Thambalegamuwa(178km)  Package 6 – from Thambalegamuwa(178km) to Trincomalee(200km)

2 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------2. Scope of Land Acquisition and Resettlement.

It has found that small portions (2550m2) of lands (for 19m corridor) are required to purchase or acquire for this road construction at some places. Under this category Sixty eight (68) households will be losing their lands and total population of these households is 188.

As per designs;

Total land requirement : 1885m2 Government owned lands : 1075m2 Privately owned lands : 810m2 Number of affected households : 06 Number of persons of affected households: 22

The lands will be purchased on willing buyer-willing seller basis. It will be at the replacement value at current market prices. The seller will have the option to refuse it. If any acquisition is carried out it will follow normal acquisition procedure without following the section 38A Proviso, which is the emergency procedure of the LAA.

The RDA will follow a transparent process to purchase or acquire required lands for the project as follows;

The lands will be taken on willing buyer-willing seller basis. The RDA ensures that land is appropriate for the intended purpose. It will be at the replacement value at current market prices of the area. The seller will have the option to refuse it. It will be at replacement value at current market prices. It does not negatively impact on the livelihood of any vulnerable group, and if so, the community developed mitigation measures are acceptable to the affectee. There are no encumbrances on the lands. The lands should not belong to any person who is below the poverty line.

The entire project (for 19m corridor) creates impacts on 1099 PAPs. and they belong to 407 families. The details about PAPs and the properties are summarized in Table 2.

As per designs;

The details about PAPs and the properties are provided in Table 3.

Number of affected households: 174 Number of persons of affected households: 578

3 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 2 - Persons and properties of the affected families (for 19m corridor) Type of Impact Ambepussa-Dambulla road Kanthale-Trincomalee Total number section road section of affected persons Number of Affected Number of Affected (a + b) Properties Persons Properties Persons (a) (b) Front walls of houses & 16 47 24 53 100 buildings

Cement floors / cement steps 130 268 12 45 313 of business places

Cement steps of public places 09 0 3 0 0 Permanent fences (Iron poles 11 26 8 15 41 with concrete columns) Gates 19 43 55 75 118 Parapet walls 12 32 64 86 118 Front walls / roof extension of 39 87 19 59 146 business places Permanent sales huts 12 39 6 36 75 Lands 58 130 19 58 188 plots plots Total 306 672 210 427 1099 (Source- Social survey for RAP 2010)

Table 3 - Persons and properties of the affected families (as per designs) Type of Impact Ambepussa-Dambulla Kanthale-Trincomalee Total road section road section number of (details may change once (as per finalized designs) affected the designs are finalized) persons (a + b) Number of Affected Number of Affected Properties Persons Properties Persons (a) (b) Front walls of houses & 0 0 18 22 22 buildings

Cement floors / cement steps 44 115 2 12 127 of business places

Cement steps of public 0 0 0 0 0 places Permanent fences (Iron poles 7 28 1 0 28 with concrete columns) Government Gates 10 32 54 70 102 Parapet walls 11 28 64 86 114 Front walls/ roof extensions 20 56 18 45 101 of business places Permanent sales huts 09 21 6 36 57 Lands 11 (plots) 22 3 (plots) Government 22 05 plots- Govt. lands 06 plots - Private Total 112 307 166 271 578 (Source- Social survey for RAP 2010)

4 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

3. Socio-Economic Profile and Vulnerability of PAPs

The PAPs belong to 407 households. About 7% of the households affected are reported as women headed households. The rest, 93% of households are male headed units. Only about 1.5% of the affected PAPs have obtained higher education. Majority (25%) have studied up to grade 6 and 10. About 10% of the PAPs have no formal education while 19% is reported as primary level education (Grade 1 to 5). Nearly 74% of PAPs are Sinhala. The 2nd largest ethnic group affected is Muslim (16%) and nearly 10% of PAPs are .

Only 9% of the families are reported as families getting some small assistance from the government. Nearly 35% of the PAPs are involved in moderate and small business activities.

4. Policy Framework and Entitlements

The policy framework and entitlements in this project have been built upon the requirements of the Government of Sri Lanka, principally the Land Acquisition Act (1950 and revised in 1979) and the National Involuntary Resettlement Policy (2001) and also World Bank‟s Policy on Involuntary Resettlement (O.P. 4. 12). Provisions and principles adopted in this RAP and are required to meet the standards established in the National Involuntary Resettlement Policy and World Bank‟s policy. The Project entitlements have been designed to provide compensation, resettlement and rehabilitation for lost assets and restore or enhance the livelihoods of all categories of affected people. Detailed project entitlement matrix is discussed in chapter 5.

5. Implementation Arrangements and Budget

The Project Director and the relevant staff of the PMU with the assistance from the RDA will be responsible to implement the project. Most of the issues related to resettlement have been identified and mitigation provided in the RP. The implementation arrangements for implementing the RP and the resettlement budget are provided in chapters 6 and 7. The roles and responsibilities of the different personnel are also identified in the RP.

6. Participation and Grievance Redress Mechanism

The RP suggests establishing a grievance redressal mechanism for redressal and mitigation of the negative impacts. The public will be adequately informed about the grievances redressal mechanism and the RDA will continue informing the new development of the project to the public through the identified communication and public awareness mechanism. Details are provided in chapter 6. The Grievances Redress mechanism is a multi faceted one and aims to respond to the requirements of the project over its life cycle.

5 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------For minor matters the GN and the social staff of the project will be responsible to respond to them. At the next level, complaints can be registered in the office of the RE through entering it in the complaint register. Complaints can be in verbal or written forms but must be entered in the register. The complaints and their resolution status will be closely monitored. At the next level the Grievance Redressal Committee can be called upon to provide resolutions to complaints. Its composition and functions have been laid out in the RP.

7. Information Disclosure

Information disclosure is a very important aspect of the RP and the Project will ensure that all relevant information is available to all stakeholders over the life of the project. Key information on resettlement issues will be provided to the affected persons as well as the other stakeholders, and agency staff in each sub project (road) area. However, during this study all the affected people were interviewed and therefore, the resettlement study team had opportunities to provide the PAPs with further details. The Resettlement Plan will be disclosed to the PAPs and other stakeholder agencies through the existing mechanisms of communication. The executive summary of the RP will be translated into the local languages and disclosed to all affectees, communities and stakeholders. The RDA will use its web-site also to disseminate the information of the RP.

8. Monitoring and Evaluation

A monitoring and reporting system has been provided in the RP. However, the RDA will improve the process of monitoring. The improved monitoring mechanism will help to achieve following specific objectives.

(i) to ensure that the livelihood systems/ activities of the public are not disturbed by the project (ii) to monitor whether the time lines are being met; (iii) to assess if compensation, rehabilitation measures are sufficient; (iv) to identify problems or potential problems; and (v) to identify methods for responding immediately to mitigate problems.

9. Total Cost Plan.

The budget prepared for mitigation of impacts is explained in detailed in Chapter 7. The total cost for social impact mitigation for each package is given below.

Ambepussa-Dambulla road section: SLR 13,611,850.00

Kanthale-Trincomalee road section: SLR 15,576,350.00

Total cost SLR 29,188,200.00

6 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table of Contents

Executive Summary 2

Table of contents 7

Chapter 01 - Introduction Background and Methodology 13

1 Background of the Geographic area and the Justification of the Project 13

1.1 Relief features of the project area 13 1.2 Socio -Economic Background of Sri Lanka 15 1.3 Scope of the RAP 18 1.4 Rationale of the project 19 1.5 Benefits to the economy from roads 20 1.6 Analysis of alternatives 21

1.7 Justification of the Project 21 1.8 Baseline information of the Project Area 22 1.8.1 Project Background 22 1.9 Methodology 27 1.9.1 Data Collection 27 1.9.2 Type of data collected for the survey 28 1.9.3 Stakeholders Consultations 29 1.9.4 Data Analysis 29 1.9.5 Presenting Result 30

Chapter 02 – Policies related to Legal Aspects and Social Safeguards 32

2.1 Law & Policy on Land Acquisition 32

2.1.1. Land Acquisition Act. 32

2.1.2 Road Development Authority Act. 34

2.1.3 National Policy on Involuntary Resettlement 35

7 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------2.1.4 Other Laws and Regulations 36

2.2 Social Safeguards Relating to Project 37

Chapter 3 – Social Impacts of the Project 42

3.1.0. Introduction 42

3.2.0. Potential social issues of the Project area 42

3.2.1. Positive Impacts 43

3.2.2. Negative Impacts of Road Projects 43

3.3.0 Impacted properties 44

3.4.0. Severity of Project Impacted Structures 47

Chapter 04 – Stakeholders Consultations 50

4.0 Direct and indirect stakeholders at different hierarchical levels 50

4.1 Stakeholders Covered in the social survey 2010 – RSAP II 51

4.2 Occupational Categories and Gender breakdown of key informants 51

4.3 Overall Positive Impacts Identified 52

4.4 Overall Negative Impacts Identified 53

4.5 Views of Stakeholders 53

4.6 Remedial measures / Strategies to mitigate the negative impact 58

4.7 Consultation Strategies 59

4.8 Disclosure of information 60

Chapter 05 – Mitigation Measures 61

5.0. Introduction 61

5.1 Project Resettlement Principles and Scope of Mitigation 61

5.2 Impact Mitigation modalities 63

5.3 Mitigation of Negative Impacts 63

8 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------5.4 Suggested Mitigation Measures for minimize negative impacts 65

Chapter 06 - Implementation Mechanism 71

6.1 Introduction 71

6.2 Implementation Plan 71

6.3 Institutional Roles and Responsibilities 73

6.3.1 Compensation and R&R Assistance Disbursement Mechanism 74

6.4 Grievance Redress Mechanism 75 6.4.1 Proposed Grievance Redress Steps and Procedures 75 6.4.2 Redress Committee Meetings (RCMs), Hearings, Proceedings and Recommendations 78 6.4.3 Implementation of Decisions of GRC 78

6.5 Monitoring and Evaluation Mechanism 78

6.6 Strategies to obtain community support to minimize negative social impacts through awareness programmes 87

6.6.1 Conducting HIV/AIDS Awareness Programmes 88

Chapter 07 – Cost calculation for mitigation of negative impacts 89

7.0 Introduction 89

7.1 Cost calculation for affected Structures 88

7.2 Cost calculation for affected lands 89

7.3 Cost calculation for Ambepussa-Dambulla road section 90

7.4 Cost for affected trees 94

7.5 Budget for mitigation of impacts for each package 95

7.6 Cost calculation for Kanthale-Trincomalee road section 97

7.7 Cost for affected trees 102

7.8 Budget for mitigation of social impacts 104

9 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Annexture

Annex 1 Set questionnaire Annex 2 Questionnaire used for stakeholder consultations Annex 3 Main administrative districts Annex 4 Profile of the project affected people Annex 5 Plates – Project affected sales huts Annex 6A Details of PAPs (Ambepussa – Dmbulla Road section) Annex 6B Details of PAPs (Kantale – Trincomalee Road section) Annex 6C Privately owned trees to be cut

Annex 7 Affected Temporary sales outlets /Three-wheelers parking stand etc Annex 8 Vulnerability & gender issues. Annex 9 List of stakeholders Annex 10 Terms of Reference Annex 11 Formats used for social monitoring in RSAP1

10 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Abbreviations

AP Affected person BP Bank Procedures CBOs Community Based Organizations CEB Ceylon Electricity Board CE Chief Engineer CV Chief Valve DS Divisional Secretary DSD Divisional Secretariat Division EE Executive Engineer ESD Environment & Social Division GN Grama Niladhari (Village officer appointed by the government) GND Grama Niladhari Division GoSl Government of Sri Lanka GRM Grievance Redress Mechanism GRC Grievance Redress Committee LAA Land Acquisition Act M&E Monitoring and Evaluation MoH Ministry of Highways MoL Ministry of Lands MLD Member of Land Division NGOs Non-Governmental Organizations NIRP National Involuntary Resettlement Policy OP Operational Policy PAPs Project Affected Persons PD Project Director PMU Project Management Unit RDA Road Development Authority RE Resident Engineer ROW Right of Way RP Resettlement Plan RSAP Road Sector Assistance project TPV Third Party Validation

11 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

List of Tables

Table 1.1 A and B Class Roads maintained by RDA (Length – Kms) 17 Table 1.2 Road sections to be rehabilitated under the project 22 Table 1.3 Direct Project Influencing Provinces that come in this Project area 26 Table 1.4 Number of Administrative Units within the project influencing zone 26 Table 3.1 Persons and Properties of the affected families- 19m corridor 45 Table 3.1A Persons and properties of the affected families as per designs 45 Table 3.2 Affected Trees 46 Table 3.3 Details of Affected temporary sales huts and Three Wheeler Parks 47 Table 3.4 Severity of Impacts 48 Table 4.1 Occupational categories and Gender breakdown of key informants 52 Table 4.2 Views of Stakeholders 54 Table 4.3 Negative implications of the project 58 Table 4.4 Stages of Stakeholder Participation 59 Table 6.1 Implementation plan 71 Table 6.2 Institutional roles and responsibilities for implementation of Resettlement Action Plan. 73 Table 6.3 Positions and Duties of the GRC Members 76 Table 6.4 Monitoring and Evaluation Indicators 80 Table 6.5 Awareness Programs for targeted groups 83 Table 6.6 Major aspects to be included to awareness /training programmes 86 Table 7.1 - 7.18B

Cost calculation for mitigation of impacts ( Ambepusa-Dambulla and Kanthale-Trincomalee road sections 90-104

List of Maps

Map 1.1 Direct Project Influence Districts 14 Map 1.2 Main Road Network of Sri Lanka 17 Map 1.3 Layout of Proposed road sections 24 Map 1.4 Main Urban Centres on Ambepussa – Dambulla and Kanthale – Trincomalee Road Sections 25

List of Figures

Figure 1.1 Length of A and B class roads 18

12 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 01

Introduction Background and Methodology

1. Background of the Geographic area and the Justification of the Project

The Ambepussa – Dambulla (00km to 90km of A006 road) and Kantale – Trincomalee (157km to 200km of A006 road) road sections of the Road Sector Assistance Project –II traverse over important geographic areas in Sri Lanka in terms of environmental, cultural, economic, social and political spheres.

While these road sections run over diverse geographical areas and connect different regions such as wet and dry climatic zones, production areas with markets and service sectors with industries bringing different races and religious groups together.

It can also be surmised that the Road Sector Assistance Project –II joins urban areas with rural and densely populated urban areas and sparsely populated underdeveloped rural areas (Map 1.1).

Therefore, this project would pave the way to decentralize economic development ensuring balanced regional development of the country.

This would lead for a prosperous future for Sri Lanka accelerating sustainable development process.

1.1 Relief features of the project area Ambepussa – Dambulla and Kantale - Trincomalee road sections of the proposed project fall into the coastal peniplane in Sri Lanka. Elevation of this region varies from mean sea level to 300m.

A large portion of the land areas where the road runs over almost flat terrain while small segments of this road run over rolling earth surface. Therefore, the slope angle of the long section varies from 3% - 10% degrees.

13 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Map 1.1: Direct Project Influence Districts

14 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

1.2 Socio -Economic Background of Sri Lanka

1.2.1 Profile of Sri Lanka

The socio – economic background of Sri Lanka as of any other country has been determined by several factors. Geography, history and contemporary political situation of the country are the key aspects of such a background.

The Democratic Social Republic of Sri Lanka is an island in the Indian Ocean with a population of about 20.4 Mn in 2009. Sinhalese make up the majority (74%) of the population. Tamils, Muslims and other ethnic groups represent the rest of the population. In terms of religion, majority is Buddhists (78%) and Hindu, Islam, Catholic and others make up 22% of the population.

The end of 25 years long terror conflict has brought about new expectations and confidence to Sri Lanka. The impact of this can be seen in many fronts. The economy posted a significant growth of 7% in the first quarter of 2010, supported by resilient domestic demand and the gradual recovery of the global economic conditions. This growth was established in all the sub- sectors with agriculture (9%), industry (6.9%) and services (6.7%). It is expected that economy will grow at a faster pace of about 7 to 8 % in this year due to favorable macro-economic changes.

Sri Lanka is a middle income country with GDP of about USD 41.9 bi in 2009. This translates into a per capita income of USD 2050. The Government‟s mission is to increase the per capita income from USD 2000 to USD 4000 by 2014.

The literacy rate of the population is 91.3%, and this rate for males is 92.8% and for females is 90.0%. Unemployment rate was 5.7% of the labor force in 2009. Poverty is still recognized as an issue of concern (15.2% people were in poverty category in 2006/07).

Human Development Index (HDI) of Sri Lanka has increased significantly reflecting the overall social development in the country. HDI was 0.759 in 2007, ranking 102 among 182 countries in the world.

1.2.2 Indigenous People: Vaddha Folk

There are indigenous people in Sri Lanka. Local name of them is “Vaddha”. The road sections of the proposed project do not cross over the areas where they dwell. Therefore, indigenous people of Sri Lanka are not affected with any way in regard to their livelihood and routine life by this project.

15 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

1.2.3 Significance of Social Development and Infrastructure facilities

Sri Lanka has planned to develop vital social sector in compliance with Millennium Development Goals of the United Nations. Accordingly, Social Development and Infrastructure facilities have reached a satisfactory level when compared to other countries in South Asia. Few indicators such as education, health facilities are equal to developed nations. This background is proved well by the Human Development Index (HDI), indicators of education, health, communication system, and supply of electricity, safe water and other vital factors that determine the quality of life of the masses.

1.2.4. Road Net-work

Transportation facilities are a sine qua non to the socio – economic development of any country (Rasanayagam, 1997). The road density, width and the quality of roads would determine the socio – economic background of a society and the rate of over all development. Road density in comparatively developed region in Sri Lanka is higher than the rest (Map 1.2). The road system in Sri Lanka demonstrates this situation as in many other countries.

The history of road development in Sri Lanka dates back to colonial period. Production of coffee, rubber and tea were required to be transported to for shipment. Therefore, the roads in wet zone of Sri Lanka were older than those in the dry zone. However, when Sri Lanka got independence in 1948, there was a main road system connecting important commercial, administrative and economical hubs of Sri Lanka. But, the road density and quality facilitating social development were poor in terms of road - population ratio, road length, vehicles and passengers. The importance of railway system has been fading away compared to high ways since independence.

The total length of all roads including A, B, C, D and E classes and rural, local and plantation was 94,651km by 1991. This number rose up to 100,000km by 1996. Since the main urban centers of the country are connected by A and B class roads, they have become the critical factor in terms of economic and social development of the country.

It seems that the total length of classes A and B roads have been increasing from 1986 significantly (Table 1.1 and Figure 1.1). The total length of A and B class roads was 8,444kms in 1963 and 8836kms in 1981. But, this figure increased by 26% from 1963 to 1996.

16 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Map 1.2: Main Road Network of Sri Lanka

Table 1.1: A and B Class Roads maintained by RDA (Length – Kms)

A Class road B Class Roads Total Year 1986 4071 4871 8942 1988 4112 6320 10432 1990 4112 6320 10432 1994 4221 6849 11070 1996 4221 6926 11147 ( Source: Arjuna‟s Atlas of Sri Lanka, 1997)

Figure 1.1 Length of A and B class roads

17 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Figure 07 Lengh of A and B class roads - Kms

12 10 8 6 4

Road lengh -km, '000 lengh Road 2 0 1986 1988 1990 1994 1996

A Class road B Class Roads Total

The government has initiated several projects to develop national road system in Sri Lanka. Colombo – Katunayaka, Colombo – Matara, and Colombo – express ways and other road rehabilitation and improvement and maintenance projects would boost the road system significantly in the near future.

1.3 Scope of the Resettlement Plan: 1. The Bank‟s Policy on Involuntary Resettlement requires the preparation of a Resettlement Plan if more than 200 persons are impacted negatively by any intervention funded by the World Bank. Land acquisition is the trigger for this Operational Policy. The Resettlement Plan needs to be a time-bound action plan with appropriate budget provisions and should be incorporated as an integral part of the project design. Project Affected Persons (PAPs) are people of any age, skill level, or socio-economic circumstances who may be losing land or assets/infrastructure/livelihood etc. Thus OP 4.12 requires a Plan be prepared which sets out all the compensation and rehabilitation support to be provided to any person, family or household who on account of the execution of the project would have his/her or their standard of living adversely affected. It focuses on those who may lose residential house, land including agricultural and grazing land, commercial properties, tenancy, right in annual or perennial crops and trees or any other fixed or moveable assets, income earning opportunities, business, occupation etc. These losses are identified during the process of developing the resettlement plan.

2. Keeping in view the above, the objectives of this Resettlement Plan include the following for the proposed project:

. Identification of affected persons, in order to determine the persons likely to be adversely affected by the project works and the severity and extent of the respective impacts. This also includes an assessment of impact on their assets, infrastructure, livelihood etc. located in the Right of Way (RoW) or in the Corridor of Impact (CoI) of the selected project roads (along with an income and asset survey).

18 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------. Identify poor and vulnerable groups with strategies to ensure that such groups benefit from the project . Ensure adequate stakeholder consultation and participation . Discuss Gender issues, conflicts and Social risk of the project area . Review of the legal and other management framework. . Develop mitigation measures in consultation with affected/stakeholders . Prepare detailed entitlement matrix and implementation plan . M&E and reporting system for the RP . A resettlement budget.

Overall objective of preparation of this RP is to identify and to develop mitigation plan to ensure that all communities are benefited without any discrimination through identifying all kinds of adverse impacts of the project area, its influence on the community during and after the construction of roads.

1.4 Rationale of the project

Socio-economic and cultural growth mainly depends on its speedy, safe, economical, comfortable and efficient transport system and in particular road transport system. About 75 percent of its population is scattered over its rural area.

Absence of a well developed road network has caused lack of basic facilities such as education, medical assistance, banking, recreational, employment potentiality, inter –regional transport of agricultural inputs and consumer goods, outward transportation of agricultural and forestry produce, live stocks and their products in and/or around most of the villages.

The Government of Sri Lanka has embarked on several new rural developments and poverty alleviation programs in the rural areas of the country in the recent years and it was felt necessary that the fruits of development reach even to the remotest areas of the country.

The Road Development Authority of the “Ministry of Highways and Road Development” in Sri Lanka has developed a Road Sector Master Plan with the overall objective of developing a comprehensive strategic plan for the physical development of the road network at national, provincial and local levels. Public consultations have been carried out during the project selection and feasibility studies. The views of the community were taken into consideration for the ear- marking of priority roads.

Considering the views of the consulted communities during the feasibility studies and the Social Assessment survey, following specific development activities were recommended;

- Improve the existing road with standard two lane facility - Improve the existing pavement with AC treatment

19 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Improve the horizontal alignment at selected locations to reduce acute curves in order to provide safe driving conditions - Widen , repair or reconstruct damaged culverts and bridges and construct new culverts at locations where road will be constructed on new embankments - Remove any irregularities that are on the existing vertical profile - Provide pedestrian footpaths, bus bays and rest bays where necessary

1.5 Benefits to the economy from roads

The proposed project is mainly to rehabilitate and upgrade the existing road sections from, Ambepussa – Dambulla and Kantale – Trincomalee (A006) which run through Central, Sabaragamuwa, North Western and Eastern provinces. This highway helps a significant segment of traffic flow which includes passenger buses, heavy vehicles and private vehicles. Also the tourists and devotees who visit Trincomalee, , , Dambulla and Sigiriya areas contribute to the present traffic of this section of the highway. Traffic flow is significant during weekends and on Poya (Full moon) days on these roads.

After ending the 30 year long civil war, the Government of Sri Lanka has launched massive development programmes in these provinces. The overall objective of the government development programs is to uplift the socio – economic status through providing electricity, improving health services, education, housing, transport, industries, agriculture and other infrastructure facilities. The development of roads in this area has been identified as the initial step of upgrading socio- economic levels. Therefore, the proposed project has become a prime development task to be completed before other projects.

Implementation of mega development projects will need a better road infrastructure in terms of providing proper transportation during its implementation stage and operational stage. A006 highway has already being identified as a potential highway that will support this development programme.

A006 road is extensively used by heavy trucks which operate to transport fish, agro- produce and other commodities from Trincomalee harbor to other parts of the country and in return many items to Trincomalee area. It is anticipated that the number of such trucks will further increase once Norochchole coal power plant becomes operational. However, due to poor maintenance the road surface has deteriorated to a level that many vehicles avoid using this route to reach Trincomalee.

If this road is rehabilitated and developed, it could be used by vehicles carrying cement from the main cement production company named “Mitsui Cement Company” in Trincomalee.

20 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

1.6 Analysis of alternatives

A. Without the Project

The pavement and many structures from Ambepussa – Dambulla and Kantale - Trincomalee (A006) road sections are very unsatisfactory due to lack of maintenance. Narrowness at certain sections and black spots have created a high operational and maintenance cost of vehicles. If rehabilitation and upgrading works are not conducted the road pavement will be further damaged to a level when vehicles may not be able to operate along the road. Further it will adversely affect many development projects and the overall development process of the project influenced area.

B. With the proposed project

Through the proposed development project, the intension is to develop the road sections under consideration with two lanes carriageway, space for emergency parking at town sections, improved cross and side drainage , walkways, alignment changes to sharp bends to cater to the designed speed and other road furniture at required locations.

The road surface will be improved with asphalt concrete which is suitable for heavy loading. Finally operational and maintenance cost of vehicles would be reduced and, therefore, the transport efficiency will be increased. The ultimate effect of this would enhance and sustain the development of the project influenced area.

1.7 Justification of the Project

When considering factors mentioned above, the proposed road rehabilitation project of Ambepussa – Dambulla and Kanthale - Trincomalee ( A006) road section may enhance the economic development process of the project area as well as surrounding areas (Map 1.1 and Table 1.2 and 1.3).

Consequently the development of this area would help to increase GDP of Sri Lanka ensuring continuous increase of per capita income.

1.8 Baseline information of the Project Area: Ambepussa – Dambulla and Kantale - Trincomalee (A006) Road Section

21 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------1.8.1 Project Background

The Government of Sri Lanka (GOSL) has requested financing from the World Bank to assist them to rehabilitate, improve and maintain the national roads network with an objective to achieve improved and sustainable road transport by enhancing the durability, efficiency and economic impact of the national road network. The proposed project will only focus on rehabilitation improvement and maintenance of national roads selected (Table 1.2) through a strategic study, in order to facilitate economic activity in the areas served and provide users with better road safety conditions.

The World Bank is financing the entire project cycle from feasibility study to the construction phase. Projects and Programs financed with IDA resources need to comply with World Bank Operational Policies. Therefore, sub-contracts and components eligible for funding under this project will be required to satisfy the World Bank‟s safeguard policies, in addition to conformity with social policies of the GOSL. The activities to be financed by the project do not have the potential to trigger significant negative social impacts. It is anticipated that social issues and impacts would be minimal in terms of road rehabilitation and maintenance projects.

Table 1.2: Road sections to be rehabilitated under the Road Sector Assistance project- II Road Road Name Length Beneficiary (kms) Provinces

A006 Ambepussa – Dambulla Sabaragamuwa, Road sections North Western, (00km – 90 90km) Central.

A006 Kanthale-Trincomalee Eastern Road Sections (157km- 43 200km)

(Source: Social Survey for RAP 2010)

The two road sections of A006 highway will be packaged in to four sections as follows;

 Package 1 – from Ambepussa (0.0km) to Pothuhera (23km)  Package 2 – from Pothuhera (23km) to Ibbagamuwa (47km)  Package 3 – from Ibbagamuwa (47km) to Galewela (69km)  Package 4 – from Galewela (69km) to Dambulla (90km)  Package 5 – from Kanthale (157km) to Thambalegamuwa(178km)  Package 6 – from Thambalegamuwa(178km to Trincomalee(200km)

North Western, Sabaragamuwa, and Central are the provinces the Ambepussa – Dambulla road crosses over which is to be rehabilitated under

22 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------the proposed project. Eastern province of Sri Lanka is the main province that receives direct benefits from the Kantale – Trincomalee road section. The details of the project area can be taken from the 1:50000 scale map produced by the Survey Department of Sri Lanka (Map 1.3). Rest of four provinces in Sri Lanka also would benefit indirectly from this project (Annex 03).

Ten districts out of 25, 129 Divisional Secretariat Divisions (DSDs) out of 13983 DSDs and 17231 villagers out of 37300 villages also receive direct benefits (Table 1.3) from the proposed Ambepussa – Dambulla and Kantale – Trincomalee road rehabilitation project ( Table 2 of Annex 03). Out of 6.3 Mn total population of the four provinces in the project area, influencing population is 3.7 Mn. All the most important market centers of the project influenced districts are situated along this road section. Names and the relative location of such centers are given in Map 1.4.

23 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Map 1.3: Layout of Proposed road sections

24 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Map 1.4: Main Urban Centres on Ambepussa – Dambulla and Kanthale – Trincomalee Road Sections

25 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Table 1.3. Direct project influencing provinces that come within this Project area Road Main zone – Province Secondary- Other divisions/ District Names

Puttalam

North Western Kurunagala Wayamba/ North Western (A06)

plains/coastal plains – Kandy

Central Nuwaraeliya Central Hills/ Upcountry

Dambulla Dambulla

Sabaragamuwa Upcountry

Ambepussa Ambepussa Rathnaputa

Trincomalee

Eastern Coastal Zone/ coastal (A06)

plains –

Kantale Kantale Amparai Trincomalee Trincomalee

(* Project province/ districts are in italic words)

Table 1.4. Number of Administrative Units within the Project Influencing Provinces Province Districts DSD1 GND2 Villages

Eastern 3 39 1,072 2,158

North Western 2 33 2158 5,719

Central 3 33 2187 5,736

Sabaragamuwa 2 24 1152 3,618

Total 10 129 6569 17231

( 1- Divisional Secretariat Division ,2 – Grama Niladhari Division (GND means Village Officer Division))

Table 1.4 shows number of administrative units within the project influencing provinces. Number of the historical sites and scenic places can be seen within this project area. Thousands of both local and foreign tourists who visit these sites annually would be happy to make a journey on improved roads. This may increase the number of tourist arrivals into the project area. Other than these

26 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------positive results, roads proposed to be rehabilitated provide service to stimulate the entire spectrum of the human activities particularly within the project area as well as adjoining provinces.

New government that came into power in April 2010 has pledged to boost the economy of the country. The proposed road rehabilitation project would help immensely to the success of the plans of the new government.

After improving the proposed Ambepussa – Dambulla (00km to 90Kms of A06) and Kantale to Trincomalee ( 157km – 200Km – A06) road sections, they would join agricultural and other local production yards with markets, main administrative centers with local, urban centers with rural areas, urban, administrative and commercial hubs with other such centers of the other end of the country. Therefore, rehabilitating the existing Ambepussa – Dambulla and Kantale to Trincomalee road section will help to communicate with one another effectively accelerating the development process of entire Sri Lanka.

1.9 Methodology

Research methodology used in this study can broadly be divided into three parts as;

1. Data Collection 2. Data Analysis 3. Presentation of results

1.9.1 Data Collection

According to the Terms of Reference (TOR) of this project, required data were pre-determined. Data already available by means of books, reports and unpublished document and news papers were used as secondary data sources in this study. Field survey method was the main technique applied to collect data of people and properties likely to be affected.

Three ways were applied to collect field data; viz,

1. Set Questioner 2. Interviews/ Case Studies and 3. Observation

All three methods of field data collection were used at the same day traveling along the proposed road sections. Three research assistants with field supervisors plus six helpers were employed to collect field data. Each field assistant was allocated to collect data on one field using questionnaires, interviews or observations (please see Annexure 01 and 02 for questionnaire). The collected data were tabulated according to the requirement of result.

27 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

1.9.2 Type of data collected for the survey

Both primary and secondary data collected on the basis of given TOR for the assignment are classified as follows;

a. Baseline Data

Baseline data related to the project area and information about existing condition therein were collected. Priority was given to Population characteristic, Community resources, Livelihood of the community, Individual and family changes, Political and social resources, Community and institutional structures etc.

b. Socio – economic data

The census for PAPs covering socio – economic background was conducted in the proposed road development area. The properties located within the ROW and immediate vicinity of the road that may be affected was enumerated. The study team considered 500m meter strips to both sides to collect socio economic data for the SIA of the project influenced area. The relevant road designs and drawings for the particular road were used to identify persons and properties likely to be affected. The survey includes the following:

- Commercial establishments

- Houses

- Lands

- Minor road access

- Parapet walls, gates, fences

- Cultural centers

- Public utilities such as telephone, electricity, water lines etc.

- Temporary sales outlets, business places

- Three wheelers parking stands

- Trees to be affected

Those are the major areas of impacts to be considered for this study. Direct- affected households were surveyed through a questionnaire survey. Men, women, youth, vulnerable groups were questioned for this survey. Interviews were held to gather socio economic data to determine socio economic background of those concerned.

28 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

1.9.3. Stakeholders Consultations

Field investigation launched under Social survey focused on different stakeholders (primary and secondary) making use of a specific methodology. Stakeholder consultation is very important since different types of stakeholders can contribute their valuable ideas, suggestions and capacity, thereby extending their support to the success of the project tasks.

Focus groups discussion were undertaken with the community such as female- headed households, truck drivers, bus drivers, residents in poor clusters, laborers, road side vendors, petty businessmen, men, women, youths, students, farmers, etc.

Before conducting a Focus Group Discussion (FGD), the study team developed checklists unique to them. The consultant paid more attention to identify negative and positive impacts of the project.

All affected householders were specially interviewed and collected information on affected structures, assets, utilities, and land use etc. The socio-economic background of the PAPs was recorded through questionnaire surveys. In addition to that all relevant Government agencies / officials such as Divisional secretaries, heads of pradeshiya sabha, Grama Niladharies, RDA officers, land officers, MOH/midwife, principals of schools, estate developers, religious leaders, leaders of CBOs/NGOs, and, police officers and other concerned parties were interviewed and information was recorded ( Please refer annex 09 and chapter 04 for details).

1.9.4. Data Analysis Both qualitative and quantitative data analyzing methods were used in this study. However, basic statistical techniques along with qualitative data analysis methods were employed to obtain required results.

Following stages were followed to collect secondary data; 1. Review of secondary data

Available primary and secondary data sources (see the list of references for details of these sources) relevant to this project were used to analyze socio economic condition of the project area. Those primary sources were prepared during the project feasibility studies and designing stages. The secondary data sources referred in this study as follows;

29 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------a. Legal and Safeguards Framework ( Policies)

Policies of both the Government of Sri Lanka and The World Bank were reviewed. Especially these policies were reviewed to determine the provisions of social safeguards that may become necessary (ex. National Involuntary Resettlement Policy of Sri Lanka, World Bank Operational Policies etc.).

b. “Mahinda Chinthanaya” - A new crash programme was introduced by the incumbent president to quicken the development process of Sri Lanka. This is the ten year horizon development framework - 2006-2016 of the Government.

With the implementation of “Eastern Revival” mega development projects targeting the development of eastern region specially Trincomalee district of the country under the “Mahinda Chinthanaya” (The contemporary government‟s main development program) have been undertaken.

c. Road Sector Master Plan ( Published by Road Development Authority, March 2007) As the responsible institute for constructing, developing and maintaining the national road network the Road Development Authority (RDA) of the Ministry of Highways and Road Development has developed a Road Sector Master Plan with the overall objective of developing a comprehensive strategic plan for the physical development of the road network at national, provincial and local level.

1.9.5 Presenting Result The findings of the Resettlement Plan (RP) are presented below and the chapter break down of the report is organized as follows: Chapter 1 Introduction, background and methodology Chapter 2 Policies related to legal aspects and social safeguards Chapter 3 Social impacts of the project Chapter 4 Stakeholder consultation Chapter 5 Mitigation measures Chapter 6 Implementation mechanism Chapter 7 Cost calculation for mitigation of negative impact

30 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Annexture 1 Set questionnaire 2 Questionnaire used for stakeholder consultations 3 Main administrative districts 4 Profile of the project affected people 5 Plates – Project affected sales huts 6A Details of PAPs (Ambepussa – Dmbulla Road secton) 6B Details of PAPs (Kantale – Trincomalee Road section) 6C privately owned trees to be felled 7 Affected Temporary sales outlets /Three-wheelers parking stands etc. 8 Vulnerability & gender issues. 9 List of stakeholders 10 Terms of Reference

31 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 02

POLICIES RELATED TO LEGAL ASPECTS AND SOCIAL SAFEGUARDS

A series of measures will be implemented with a view to minimizing the negative impact of land acquisition process at national level. These litigator measures include national laws and policies of Sri Lanka along with the policies of World Bank. The relevant policies and laws in this regard are briefly presented in this chapter.

2.1 Law & Policy on Land Acquisition

2.1.1. Land Acquisition Act

The law is “The Land Acquisition Act (LAA)”, enacted in 1950 governing acquisition of land for public purposes. This law has been the subject of several amendments and revisions, the latest being in 1979. The LAA sets out the procedures for acquiring land and payment of compensation to the owners.

A notice is issued specifying that land is potentially required for a public purpose, and accordingly authorized personnel undertake investigations (surveys, boreholes, and setting out of boundaries etc) to determine suitability. If the land is found suitable for the public purpose a written declaration to that effect is made. Subsequently, notices are issued describing the land, the intention to acquire the land, and requiring that persons with an interest in the land to notify (in writing) the acquiring officer of their claim (including the compensation amount expected).

Once the claim is received the acquiring officer holds an inquiry in order to ascertain the market value of the land, the claims for compensation, and the respective interests of the claimants. At the conclusion of the inquiry the acquiring officer at his discretion either makes a decision on the claims or refers the claims to the District Court or Primary Court.

As per the decision made by the acquiring officer fixes an award determining the persons who are entitled to compensation, the total amount of compensation to be allowed for the acquisition, and the apportionment of the compensation among the other persons with interest in the land. If there is a dispute over the determination the claimants may appeal to either the compensation Review Board or Court of Appeal (on questions of law following a decision by the Compensation Review Board). However this appeal is required to be filed within 21 days of receipt of notification of the award.

32 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Provisions of the LAA allow payment of compensation in installments followed by an initial payment. If the claimant of the land agrees to a land exchange in lieu of cash, the transfer is put into effect. After the awards are made the Minister publishes or gazettes a “vesting order” for the acquirement of the land, after which time occupants of any buildings located on the land to be vested are given notice to vacate.

One of the shortcomings of the LAA is that the onus to prove ownership or interest in, demonstrate clear title, to gather all information and submit a compensation claim in respect of the land to be acquired, is on the Affected Persons (APs). Often APs are not aware of their rights or timeframes to be observed under the LAA, or they are aware but are ill-equipped to deal with the procedures required and are also not experienced in dealing with various officials and documentation. In order to remedy this situation, the project will be required to assist APs in making their claims under the LAA as part of the consultation and participation process.

APs often face serious delays in the land acquisition process due to time consuming inquiries and the fact that they are conducted by Divisional Secretaries who often do not have experience to interpret legal documents.

Ownership issues - The following measures are currently adopted in other road project to minimize these issues:

 The Divisional Secretary is assisted by the RDA with inquiries through engagement of a lawyer to look into deeds and issue a title clearance certificate, where required. This enables the acquisition officer to make quick decisions. The lawyer can also advise APs on a case basis;

 A daily allowance to be paid to APs who give up a day (or more) of work to attend inquiries required for the land acquisition process;

 Recommendation that the surveys required under Sections 2 (including perimeter survey) and 6 (preliminary plan) of the LAA be undertaken simultaneously.

There are also problematic issues related to the payment of compensation.

As noted earlier the LAA provides for an initial payment (Rs25,000) and then the balance amount is to be paid “…in not more than ten equal installments, so that the entire balance compensation is paid before the lapse of ten years from the date of payment of the said sum of Rs 25,000” [Section 29 (ii)]. To enable APs to restore their livelihoods within a short period after the land acquisition, payment of compensation and allowances must be effected in a lump sum to ensure immediate livelihood restoration.

33 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------This will also avoid delays in the award of contract for civil works. ADB insists that the implementation of the resettlement plan be approved before it will sign a letter of no objection to commencement of civil works. A clause included in the other projects in this regard is as follows: “…RDA will not take possession of any private property prior to full payment of compensation entitlements, and where applicable, of relocation arrangements and initiation of income restoration measures.”

No doubt that the compensation process as set out in the LAA remains flawed, APs can receive up to four different payments at different times (the statutory compensation (Section 17 of the LAA), the “top-up” compensation referred to as the LARC payment, the ex-gratia payment, and then interest on any compensation amount not paid) and the statutory payment can be paid in installments therefore, further delaying the payment of full compensation. This delays the land acquisition process and prevents APs from being able to immediately restore their livelihoods.

2.1.2 Road Development Authority Act.

The Road Development Authority Act enacted in 1981 provides for the establishment of the RDA and specifies the powers, functions, duties and responsibilities of the RDA. Declaring areas for „road development‟, which under the meaning of the Act includes the construction of new roads or the maintenance or improvement of existing roads is dealt with in Part II. Improvements include any widening, leveling, provision of footpaths, treatment for mitigation of dust or any other works beyond ordinary repairs.

Carrying out integrated road planning and development, submitting such plans for Government approval, and following approval, implementing the road development plans, works and activities can be considered as the functions and duties of RDA.

Under Section 8 of the Act, the Minister, after taking into consideration the requirements of local and national planning and what is urgently required for the regulation and control of road development, may declare a „road development area‟ following an order or notice (which sets out the requirement and physical boundaries) published in the gazette.

Land acquisition for road development as a “public purpose” is dealt with in section 22. This provides for the acquisition by, and transfers to, the RDA of immovable or moveable property within any declared road development area, for which the RDA will pay any sum payable under the LAA [Section 22 (2)]. Therefore, after the Section 8 notice has been gazetted, if land or other property is to be acquired, the procedures are as set out in the LAA.

34 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------2.1.3 National Policy on Involuntary Resettlement

Road projects require clearance and use of land, land acquisition and resettlement of people and re-building of their dwellings, crops and structures. Resettlement can have a number of adverse social and cultural impacts including:

 Poverty of affected people due to landlessness and/or homelessness;  Economic marginalization;  Loss of Jobs;  Higher incidence of mortality and morbidity;  Food insecurity;  Lack of access to common property and public services; and  Disruption of the existing social organization and community networks.

The LAA only provides for compensation for land, structures and crops. The project executing agencies are not called upon to address key resettlement issues such as exploring alternative project options that avoid or minimize impacts on people, compensating those who do not have title to, but are currently using and dependent on land, or implementation of income restoration measures aimed at the social and economic rehabilitation of APs.

The National Environment Act of 1980 also contains some provisions relevant to involuntary re-settlement of the affected people. The Minister has by gazette notification (No. 859/14 of 23.2.1995) determined the types of projects and undertakings for which Central Environmental Authority approval is required under the terms of Part IV (c) of the National Environment Act. The schedule includes item 12, which refers to “…involuntary resettlement exceeding 100 families, other than resettlement resulting from emergency situations”. However, there are no provisions included in the Act which adequately address the key resettlement issues identified above.

To ensure a fair and equitable treatment to the APs and to particularly ensure that people are not impoverished or suffer unduly as a result of implementation of public or private project it was considered necessary for Sri Lanka to adopt a national policy to protect the rights and interests of all people affected by development projects. Thus, in 2001 the Government adopted the National Involuntary Resettlement Policy (NIRP) that was prepared with assistance from ADB.

The key objectives of the NIRP are:

 Avoid or mitigate negative impacts of involuntary resettlement by facilitating the resettlement of the affected people on a productive and self sustaining basis;

35 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------ Ensure prompt compensation and proper resettlement;  The livelihoods of all persons should be re-established and their standard of living improved;  No people could be adversely affected as a consequence of compulsory land acquisition for development purposes by the state;  Assist APs in dealing with the psychological, cultural, social and other stresses that could be caused by acquisitions of their lands by the state;  Create awareness among all APs of the processes available for the redress of grievances that are easily arisen and immediately responsive; and  Set in motion a consultative, transparent and accountable involuntary resettlement process with a time frame agreed to by the project executing agency and APs.

According to NIRP a comprehensive resettlement action plan needs to be prepared where twenty or more families are affected by an acquisition. In cases where less than twenty families are affected the NIRP still requires a plan but states that this can be prepared to a lesser level of detail. The NIRP applies to all projects irrespective of the source of funding.

The overall institutional responsibility for implementing the NIRP falls on Ministry of Lands (MOL), and it has established a Resettlement Division to coordinate implementation. A number of technical guidelines are in place to assist the MOL and project executing agencies in planning, implementing, monitoring and evaluating all involuntary resettlement consequences.

Copies of the four sets of guidelines are available from MOL. Sinhalese and Tamil translations of the documents are currently being prepared. Over 130 personnel from the government, NGOs, universities, district and divisional administrations, and local authorities have been trained in involuntary resettlement with the support from ADB.

2.1.4 Other Laws and Regulations

The Sri Lankan government has enacted several laws to ensure fair and equitable decisions are taken on various issues related to the people of the country. The key laws in this regard are mentioned below:

 Act for labor conflict resolution- Act number 43 of 1950  Industrial Regulation Act of Sri Lanka  The Employee Compensation Act  Act of Labor Unions  The Act of employment of women, teenagers and children  Special Act of discontinuation of employees.

36 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------ Maternity assistance act (provisions for maternity leave, Maternity assistance, payments of salaries of mothers after delivering etc, are covered under this act- This is exclusively aimed on women)  Act of Employees Provident Fund  Act for Payment of Bonuses to the employees  Act for Employment of women in mining industry (exclusively aimed on women)  Provincial Council Act  Act for Labor Conflict Resolution- Act number 43 of 1950  National Child Protection act  National Thoroughfares Act  Rent Act no 7 of 1972 and the Ceiling on House and Property Law No.1 of 1973

2.2. Social Safeguards Relating to Project

The World Bank Operational Manual contains the environmental and resettlement related regulations and guidelines. For the purpose of this report references have been made to Project Related Operational Policies. The applicable safeguard policies of the Bank are described in the section below based on the field investigations, consultations and surveys undertaken.

Operational Policy 4.01 - The Environmental Assessment

In addition to national laws and regulations, the IEE study should comply with World Bank Operational Policy (World Bank OP 4.01) which is the policy of the International Donor Agency (IDA) of this project. World Bank OP 4.01 requires Environmental Assessment (EA) of projects proposed for World Bank financing to help to ensure that these projects are environmentally sound and sustainable. Considering the work involved and resultant environmental repercussions in road resurfacing and upgrading and/or provision of drainage in non-sensitive environments, this project can be treated as Category B.

World Bank OP 4.01 specifies that for a project in Category B proposed for financing under an IDA credit, the developer must consult project affected groups and local non governmental organizations (NGOs) about the project‟s environment aspects and take their views into account in the design and implementation. In addition the RDA and contractor are expected to consult the stakeholders throughout project implementation, as necessary, to address EMP related issues that affect them. The OP 4.01 also highlights the importance of analyzing alternative designs, technologies and operational strategies systematically in terms of their potential environmental impacts in order to select the most environmentally friendly and economically viable option.

37 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------1.The design of road specifications and works and subsequent operations of the project must be in compliance with environmental safeguard as specified in the EA and EMP. The EAs and EMPs will be available for public review and comment in appropriate locations in Sri Lanka and in International Donor Agencies (IDA‟s), and the public Information Center, in accordance with BP 17.50 requirements of disclosure. Detailed EAs for individual projects will need to be carried out by the implementing agencies and will be monitored and cleared by the designated PAA, as applicable under prevailing national environmental legislation in Sri Lanka and by IDA prior to the approval of disbursement.

Operational Policy-4.04 –Natural Habitat

This Policy (OP 4.04) deals with the conservation of natural habitats. Similar to OP 4.01 the requirements of the OP 4.04 have been addressed in the EA and EMP prepared for the project.

Operational Policy-4.10-Indigenous People

Definition of Indigenous People: The proposed project will use the World Bank‟s guidelines to identify Indigenous People (IPs) in particular geographic areas by examining the following characteristics: . Close attachment to ancestral territories and natural resources therein; . Self-identification by the IPs themselves and identification by others as members of distinct cultural groups; . Use of an indigenous language different from the predominant language (even if they use other languages in dealing with the non- indigenous people); . Presence of customary social and political institutions; and . Ppresence of a primarily subsistence production system.

In fostering full respect for their dignity, human rights and cultural uniqueness, a Bank-financed project has to ensure that indigenous people do not suffer adverse impacts in the development process, and that they receive culturally compatible social and economic benefits. The Bank policy (OP 4.10 on Indigenous People) requires that the sub-projects be carefully screened to identify whether there are indigenous people living in the project areas, and that informed participation of the IPs themselves must be undertaken to identify local concerns and preferences through direct consultations with the IPs and incorporation of indigenous knowledge into project planning approaches. This policy contributes to the Bank‟s mission of poverty reduction and sustainable development by ensuring that the development process fully respects the dignity, human rights, economies, and cultures of Indigenous People. For all projects that are proposed for Bank financing and affect

38 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Indigenous people, the Bank requires the borrower to engage in a process of free, prior, and informed consultation. The Bank provides project financing only where free, prior, and informed consultation results in broad community support to the project by the affected Indigenous People. Such Bank-financed projects include measures to (a) avoid potentially adverse effects on the Indigenous communities; or (b) when avoidance is not feasible, minimize, mitigate, or compensate for such effects. Bank-financed projects are also designed to ensure that the Indigenous Peoples receive social and economic benefits that are culturally appropriate and gender and inter-generation included. As proposed in the project, the roads require only rehabilitation, paving and some widening (but within the RoW) and the consultations held under the Social Impact Assessment did not identify any indigenous people as defined by OP 4.10 in the project area. Hence this Policy is not triggered. However, during implementation, should any such group get identified the Project will prepare an Indigenous Peoples’ Development Plan (IPDP) in conformity with OP 4.10, get it cleared by the IDA and implement it.

Operational Policy 4.11 - Management of Cultural Property

The physical cultural resources, defined as movable or immovable objects, sites, structures, groups of structures, and natural features and landscapes that have archaeological, pale-ontological, historical, architectural, religious, aesthetic, or other cultural significance are dealt with under this policy. Physical cultural resources may be located in urban or rural areas, and may be above or below ground, or under water. Their cultural importance may be at the local, provincial or national level, or within the international community. The project will not create negative impacts on any cultural property similar to OP 4.11.

When development projects are funded by the Bank, assistance is provided to the countries to mitigate negative impacts on their physical and cultural resources. The impacts on physical cultural resources resulting from project activities, including mitigating measures, may not contravene either the borrowers‟ national legislation, or their obligations under relevant international environmental treaties and agreements. The following project financing policies are followed by the Bank:

 The Bank finances only those projects that are cited and designed so as to prevent significant damages to non-replicable cultural property. This policy pertains to any project where the Bank is involved, irrespective of whether the Bank itself is financing the part of the project that may affect cultural property.  Deviation from this policy may be justified only where expected project benefits are great, and the loss of or damage to cultural property is judged by competent authorities to be unavoidable, minor, or otherwise

acceptable. The Bank also requires a discussion with specific details for their justification through acceptable documentary evidence.

39 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------The Social survey did not identify any cultural property in the project site, however, should any such site get identified in future, the Project will do the following:

Whenever chance finds are made during the construction of the road, the responsible persons of the site staff will immediately inform the project execution agency which will, in turn, in form the government department concerned with cultural property to take suitable protective measures.

Operational Policy 4.12- Involuntary Resettlement

The issues and concerns related to land acquisition (It has been found that small portions (2550m2) of lands are to be required to purchase or acquired for this road construction at some places). If any acquisition is carried out it will follow normal acquisition procedure without following the section 38A Proviso, which is the emergency procedure of the LAA. The total extent is to be acquired, their compensation for all categories of affecters and affected assets, relocation, resettlement, loss of livelihood, access and related issues are dealt with under this policy.

If involuntary resettlement is not properly addressed it results in severe economic, social and environmental problems. The people will face impoverishment when their productive sources are lost. If people are relocated to such environment where productive skills are not properly utilized, the competition for resources will be increased; the community institutions and local networks will be weakened.

In case of unavoidable resettlement, these activities should be planned and executed as a sustainable development program. Displaced persons should be properly consulted and adequate opportunities should be afforded to them to participate in planning and implementing resettlement programms.

The Bank policy covers direct economic and social impacts that result from Bank assisted investment projects by the involuntary resettlement. The following are the main objectives of policies of the Bank:

o Involuntary resettlement should be avoided up to the possible limit or minimized by exploring other viable alternatives; o Where it is not feasible to avoid, resettlement, such activities should be planned and executed as sustainable development program, providing sufficient investment resources to enable the persons displaced by the project to share in project benefits; o Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least be restored to the extent of pre-displacement levels.

40 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Displaced persons may be classified into: i). Those with formal legal rights to land (including customary and traditional rights recognized under the law of the country). ii). Those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets provided that such claims are recognized under the law or become recognized through a process identified in the resettlement plan. iii) Those who have no recognizable legal right or claim to the land they are occupying. This policy has been triggered and there will be land acquisition along the other negative impacts. Resettlement Plan is being prepared as social mitigation measures for those effects. The prescribed responses to adverse impacts are presented in the form of an Entitlement Matrix which is a part of the Resettlement Plan.

Operational Policy 17.50 - Disclosure of Operational Information

“The Bank reaffirms its recognition and endorsement to the fundamental importance of transparency and accountability of the development process. Accordingly, it is the Bank‟s policy to be open about its activities and to welcome and seek out opportunities to explain its work to the widest possible audience”.1 Therefore, all Bank funded documents are to be widely disseminated and accessible to all affectees and stakeholders. This Policy is triggered: Thus in accordance with the Disclosure Policy of the World Bank, the Environmental and Social Assessment (ESA) and Resettlement Plan (RP) will be displayed at the info shop and the Project sites, viz., Project Offices and Public Libraries. The Executive Summary translated into local languages (both Tamil and Sinhala) will also be disclosed at the Project site where it will be accessible to project affected people. The Initial environmental and social Assessments will be disclosed to all types of stakeholders, especially to the project relevant public. The information in this report too will be disclosed to them in the project sites and in other appropriate locations such as Grama Niladharies’ offices in the local area. The executive summary of the RP will be translated into the local languages and disseminated to all affectees and communities. The regional offices of the RDA will be used to disseminate the RP. In addition the web site of RDA will be used for wider dissemination of the RP. Regular formal and informal meetings will be held with APs, Divisional Secretaries, Grama Niladari and other regular agencies to disclose information.

Types of impacts expected;

 Basic compensation policy and entitlements;  Consultation and participation of APs and community:  Implementation schedule; and  Who to contact for additional information.

Further the plan and overall implementation schedule will be displayed in Community and Project Offices regularly.

41 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 3

SOCIAL IMPACTS OF THE PROJECT

3.1.0. Introduction

Any development project would generate many positive impacts as well as negative impacts particularly for the Project Affected Persons (PAPs) both in the short-term and the long-term. Therefore, it has become an important requirement to examine about the potential issues of the proposed Ambepussa- Dambulla and Kanthale – Trincomalee road rehabilitation project.

The severity and magnitude of these issues would be controlled mainly by the geographical background, contemporary demographic factors and socio- economic background of the Project Affected Persons.

The project affected persons (PAPs) for 19m corridor of the project are 1099. They belong to 407 families and were interviewed in the household survey during the field studies.

As per designs;

Number of affected households: 174 Number of persons of affected households: 578

The details of affected structures and affected persons are given in the table 3.1. Names of the project affected persons/ properties, assets, magnitude of the impacts and livelihood in this road sections are given in Annex 06A, 06B and 07.

Profile of the project affected persons (such as gender composition, age distribution, ethnicity, education levels, income categories and occupations) is provided in Annex 04.

3.2.0. Potential social issues of the Project area

When analyzing the collected data of the PAPs of the proposed project, complex social issues can be envisaged. However, these, potential social issues of the proposed project can broadly be categorized into two as positive and negative impacts.

During the field investigation conducted for the Social survey, the consultant and the field investigators have conducted small group discussions and individual consultations with different stakeholders of the project. These

42 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------discussions and observations have revealed that there are more positive impacts than negative impacts.

As identified during the field investigation, all beneficiaries are looking forward to several positive impacts after implementation of this project.

3.2.1. Positive Impacts

Positive social impacts of the proposed road rehabilitation project can be grouped into five as follows;

Group 01 – Saving time and money

Reduction of transport cost, Regulation of public transport, Time saving and Reduction of vehicle repair cost.

Group 02 – Increasing Prices of sales items

Increase of land value, good prices for farmers‟ production

Group 3 – Increasing economic growth rate

Improvement of local business, increasing competition in the commercial sector poverty reduction and livelihood development, rural development, reduction of the gap between rural and urban level and better employment.

Group 4 – Increasing Efficiency

Able to attend specific duties and functions on time , enhancement of children‟s education, enhancement of links between urban centre and rural area, better access for other common utilities ,better utilization of existing resources , less traffic congestion, improved communication with other regions.

Group 5- Reduction of Social Risks

Reduction of road accidents happened due to bad road conditions.

3.2.2. Negative Impacts of Road Projects

Negative social impacts of the proposed road rehabilitation project can also be discussed as follows;

* More road accidents and increase of traffic congestion during the construction period.

43 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------* Increasing migrations to the area (Migration of outsiders).

* Disturbances to some groups such as school children, infants and old and sick persons living in close proximity to construction sites.

* Effect on business centers, lands, extended parts of buildings and access to business places, parts of housing structures and extended sections, disturbances to house access, demolition of parapet walls, gates and fences ,utility services and trees.

* Vulnerability and Gender issues (relevant information are given in Annex 08).

3.3.0 Impacted properties

Impacted properties are defined in this report, particularly in this chapter, as any property that is owned by the government, a community, private or encroachers/squatters, such as piece of land, infrastructure facilities, access, front walls of houses or business place, trees and any other natural or man made features that would alter, rearrange of demolish to get required width for the proposed road sections to construct side drains, culvert, bridges, side wall, retaining wall or any other thing that would be used in the rehabilitation work of the proposed project.

Affected properties can be divided into nine categories according to the name and the nature of property (Tables 3.1 and 3.2).

Names of the project affected persons/ properties, assets, magnitude of the impacts and livelihood of the APs (for 19m corridor and as per designs) in this road sections are given in Annex 06A, 06B and 07.

Most affected private property types are front walls of business places and second are front walls of houses. If the project needs to demolish these structures project will pay replacement cost without depreciation and salvage value at the current market prices.

44 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Table 3.1 Persons and Properties of the affected families (for 19m corridor) Type of Impact Ambepussa-Dambulla road Kanthale-Trincomalee Total number section road section of affected persons Number of Affected Number of Affected (a + b) Properties Persons Properties Persons (a) (b) Front walls of houses & 16 47 24 53 100 buildings

Cement floors / cement steps 130 268 12 45 313 of business places

Cement steps of public places 09 0 3 0 0 Permanent fences (Iron poles 11 26 8 15 41 with concrete columns) Gates 19 43 55 75 118 Parapet walls 12 32 64 86 118 Front walls / roof extension of 39 87 19 59 146 business places Permanent sales huts 12 39 6 36 75 Lands 58 130 19 58 188 plots plots Total 306 672 210 427 1099 (Source- Social survey for RAP 2010)

Table 3.1A - Persons and properties of the affected families (as per designs) Type of Impact Ambepussa-Dambulla Kanthale-Trincomalee Total road section road section number of (details may change once (as per finalized designs) affected the designs are finalized) persons (a + b) Number of Affected Number of Affected Properties Persons Properties Persons (a) (b) Front walls of houses & 0 0 18 22 22 buildings

Cement floors / cement steps 44 115 2 12 127 of business places

Cement steps of public 0 0 0 0 0 places Permanent fences (Iron poles 7 28 1 0 28 with concrete columns) Government Gates 10 32 54 70 102 Parapet walls 11 28 64 86 114 Front walls/ roof extensions 20 56 18 45 101 of business places Permanent sales huts 09 21 6 36 57 Lands 11 (plots) 22 3 (plots) Government 22 05 plots- Govt. lands 06 plots - Private Total 112 307 166 271 578 (Source- Social survey for RAP 2010)

45 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Lands to be affected

It has found that small portions (2550m2) of lands (for 19m corridor) are required to purchase or acquire for this road construction and 68 households will be loosing their lands. The total number of affected persons under this category is 188.

As per designs;

Total land requirement : 1885m2 (Government owned lands 1075m2 and privately owned lands 810m2) Number of affected households : 06 Number of persons of affected households: 22

(See table 09 of annex 06A and 06B for details – Names and addresses of affected persons, affected land areas and percentages of total land holding). The lands will be purchased on willing buyer-willing seller basis. It will be at the replacement value at current market prices. The seller will have the option to refuse it. If any acquisition is carried out it will follow normal acquisition procedure without following the section 38A Proviso, which is the emergency procedure of the LAA.

Affected Trees (for 19m corridor)

There are 2008 trees (557 fruit trees and 1451 trees of timber value) to be removed. Out of them 203 trees (trees of timber value 117 and fruits trees 86) are privately owned by 96 individuals. Details of affected trees are given in Table 3.2. Names and addresses of owners of affected trees (19m corridor and as per designs) are provided in Annex 06C.

Table 3.2 Affected Trees (for 19m corridor) Road sections Govt. owned Privately owned trees Total no. of Trees trees

Ambepussa – Dambulla road 1470 150 1620 section (owned by 82 households)

Kanthale- Trincomalee road 335 53 388 section ( owned by 14 households)

Total 1805 203 2008

Source- Social Survey for RAP, 2010

Affected privately owned trees – as per designs Ambepussa-Dambulla road section - 48 Kanthale – Trincomalee road section - 33

46 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

There are several temporary privately owned sales outlets such as movable lottery stalls, vegetable stalls and fish stalls (Annex 05- Plate2 and 3). Green gram sellers and other small sales outlets are also available along the road as well as in some junctions. Details are given in Annex 07. Most of them are made of wood. Those stalls will have to be shifted for 2-3 days to alternative locations, when the road is asphalted at these locations.

The project and RDA will take action to assist them to shift the stalls to enable them to continue their business and they will be reinstated at the same locations once the asphalt works are completed in 2-3 days. In addition to these, “Three Wheeler parking Stands” have been found in several junctions. Those parking stands will be affected during asphalt lying period (maximum 2- 3 days).

The project authorities and RDA will assist them to shift the three-wheeler parking stands temporarily to the nearest alternative places from the original locations to enable them to continue their business.

The business people and three wheel owners stated that they will not lose their daily income during the construction period. The details of the affected private stalls and three wheeler parking stands are given in the table 3.3.

Table 3.3 - Details of Affected temporary sales outlets and Three Wheeler parking stands Road Three Lottery Vegetable Fish Green Other Wheeler Stalls stalls stalls gram Parking sellers stands Ambepussa- 42 23 26 11 3 0 Dambulla section Kanthale-Trinco 13 3 4 4 0 0 section Source- Social Survey for RAP, 2010

3.4.0. Severity of Project Impacted Structures

The severity of affected structures of the proposed road development project is summarized in the table 3.4. Severity is minor in majority of the affected structures. Therefore, it can be concluded of both private and public affected structures would not alter socio – economic back ground significantly. Expected issues would last only during the construction period.

47 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 3.4 Severity of Impacts

Property Severity of Impact (for 19m corridor) As per designs

Impacts on Lands Moderate – It has been identified Minor – Six (06) numbers of that 68 households (2550m2) will be households will be loosing losing their lands. The RDA will their lands (810m2). acquire or purchase the lands. It will be at the replacement value at Government owned lands current market prices. will be transferred to RDA (1075m2)

Impacts on front walls of Moderate - There are 40 houses & Moderate – 18 houses and houses & buildings buildings to be affected under buildings will be affected this category. under this category Impacts on cement Minor - 142 cement steps of Minor – 46 cement floors / floors / concrete steps business places will be affected concrete steps of business places due to construction of drains along the road.

Impacts on Minor - The project will affect 12 No impacts concrete/cement steps concrete/ cement steps of public of public places places during the construction period.

Impacts on permanent Minor - There are 19 fences to be Minor- 08 - permanent fences ( iron poles with shifted / demolished belonging to fences (iron poles with cement columns) private owners. cement columns)

Impacts on Gates Minor – The project has identified Minor-64 - Gates that there are 74 gates needed to be shifted.

Impacts on parapet Moderate – The project needs to Moderate- 75 - parapet walls walls remove 76 parapet walls during construction period.

Impacts on Front walls Moderate - The project needs to Minor- 38 - front walls / roof and roof extensions of demolish 58 front walls / roof extensions of business place business places. extensions of business place.

48 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Impacts on Permanent Minor – There are 18 permanent Minor- 15- permanent sales sales huts. sales huts to be demolished. huts

Impacts on privately Moderate – The project needs to Minor- 81 - privately owned trees. fell 203 numbers of trees which owned trees are privately owned.

Impacts on three- Minor – The project will impact Minor- 55- three-wheeler wheeler parking on 55 numbers of three-wheeler parking stands stands parking stands. The project will ensure that their livelihood is not affected by providing them alternative places (for 4-5 days) to relocate them during the construction phase to continue regular business activities without losing their daily income. They may return to their original places afterwards.

Temporary sales Minor – The project needs to Minor - 73- Temporary outlets shift 73 numbers of small scale sales outlets temporary sales outlets for 4 - 5 days during the construction period. The project will ensure that their livelihood is not affected by providing them alternative places (for 4-5 days) to relocate them during the construction phase to continue regular business activities without losing their daily income. They may return to their original places afterwards.

49 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 4

Stakeholders Consultation

Stakeholders are defined as individuals or agencies that are either affected by and /or can affect the project. The RSAP II., has direct and indirect stakeholders at national, district, divisional, project and village levels representing different geographical areas as well as different management systems.

In this chapter, an attempt is being made to analyze and assess the stakeholders‟ views and perceptions gathered through field consultations, focus group discussions and meeting with key informants.

4.0. Direct and indirect stakeholders at different hierarchical levels

The most significant stakeholder is the Project Affected Person who is negatively/positively affected by the Project. The most significant and direct beneficiary groups at the local level include all kinds of road users. The groups that frequently benefit from the roads are school children, school teachers, drivers, farmers, traders and all other types of road users. The regional economies as well as household economies will get positively influenced due to improved road net work. The most significant direct affectees are the persons losing land/assets/livelihood etc.

At the national level the major direct stakeholder is the Ministry of Highways and Road Development Authority. This organization is responsible for improving the road network of the country.

District level officers attached to RDA are middle level direct stakeholders because complaints about the problems of dilapidated road systems are frequently brought up by the communities and other politicians with the RDA officers attached at district level organizations.

National Government Agencies and other organizations such as Ceylon Electricity Board (CEB), Sri Lanka Telecom & Water Supply & Drainage board are also stakeholders. This is equally applicable to the public and private transport providers (The government - CTB & private bus owners).

In the process of consultation special attention was paid to consult women, youths, ethnic groups and other vulnerable groups.

The most significant indirect beneficiaries of the project are politicians of different levels. The politicians - local, provincial and national levels – such as

50 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------ministers, members of parliament, and members of provincial councils can obtain their popularity and peoples‟ support with the successful implementation of the road net-work. The civil society/NGOs/academia is also included in the indirect group of stakeholders.

The contractors, material suppliers can benefit from the construction work. The local communities can also benefit because of employment generated in their local areas in the construction sites.

4.1. Stakeholders Covered in the social survey 2010 – RSAP II

The views of the following stakeholders were analyzed.

 Direct stakeholder -- All PAP families  Direct beneficiary groups -- Road users, drivers, farmers, traders ,school - children, school teachers etc.  Indirect beneficiary groups -- politicians, civil society, NGOs etc..  National level direct stakeholders -- Ministries and policy and decision makers etc.  Middle level indirect stakeholders -- Regional and district level officers, government departments etc.  General public/ Local communities

4.2. Occupational Categories and Gender breakdown of key informants

In respect of gender and age groups, 32% of the key informants were female and nearly half of the respondents belonged to youth and senior citizens‟ category.

Apart from the Sinhalese respondents numbers of Tamil and Muslim respondents were also included in the sample to represent different ethnic groups. Profile of the stakeholders consulted and gender breakdown are provided in the Table 4.1.

51 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 4.1. Occupational categories and Gender breakdown of key informants

Occupation/sectors No of informants

Female Male Businessmen and helpers 08 13 Government/Private sector Employees 05 07 Professionals (ie Doctors, Bankers, Engineers) 01 05 Police Officers 00 03 Daily Commuters (ie Teachers, Students) 04 18 Drivers (Public/Private) 00 10 Farmers and sellers of farm products 04 06 Housewives 08 00 Others (ie Clergy, NGO people, politicians) 01 05

Total 31 67

4.3. Overall Positive Impacts Identified.

- The road will be expanded to reduce congestion and traffic, - The transport system will get widened. - Timely traveling to desired destinations will be possible. - Tourism and recreation activities could be expanded. - The maintenance cost of the road can be reduced. - The maintenance cost of the vehicles will remarkably go down. - The new buses can be put on to the roads. - The income from transportation will be increased. - Port related activities / ship building and repairs will be increased - The improved transport systems will help all kind of service providers to travel to their field stations. - The service receivers such as patients, farmers, can use the improved transportation to reach the service delivery centers. - Poverty reduction with better prices to the farmers, increased competition in commercial Sector - The improved road system will support oil refinery, cement plant, wheat flour factory and mineral resource development activities in Trincomalee area. - Expedite link with urban centers - Increase in land value particularly of land contagious to the improved roads - Increase of land and property value will lead to redistribution of wealth.

52 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

4.4. Overall Negative Impacts Identified

During the construction period there will be several negative impacts. These include:  Disturbances to transportation system on the road network for a short period till the construction is over.  Traffic congestion and other related issues.  Business activities will get disturbed during the construction period  There will be inconveniences due to dust, noise, heavy vehicle movements etc.  Demolition of structures will create safety hazards for the owners of affected assets during construction period  There may be safety issues at the road construction sites.  After completion of the roads, the rate of accidents will be increased  Health and social issues will be created by migrant workers in road construction areas.  Private lands will be purchased or acquired by the RDA  Considerable construction related disputes among workers and villagers  Dust and pollution during the construction period  Shops and other livelihood routines of the people residing close to the road will be disturbed

4.5. Views of Stakeholders

A brief questionnaire was administered to obtain views and opinions regarding the project. A sample of questionnaire is given in Annex 02. In addition to one to one interviews based on the questionnaire eight group meetings/consultations were held at roadside during the field studies to obtain detailed views of different road users. The dates and locations of those meetings are given below: Details of persons consulted during the meetings and field studies of the road sections are provided in Annex 09.

Meeting Location Date

1 Ambepussa 12.02.2010 2 Tulhiriya 12.02.2010 3 12.02.2010 4 Potuhera 12.02.2010 5 Melsiripura 13.02.2010 6 Galewela 13.02.2010 7 Kantale 14.02.2010 8 Trincomalee 14.02.2010 & 2010.12.28,29

53 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Most of these respondents had knowledge about the project such as width of the new road etc. However, it is found that the views expressed by them on project benefits were based on their personal views.

The field data collectors of the study team consulted various stakeholders under different stakeholder categories in order to obtain their views on the road development project. The comments are presented in the following Table 4.2.

Table 4.2 Views of Stakeholders Stakeholders Statements made by stakeholders ( Negative & Positive) Project Affected Persons Expect reasonable compensation payments for all affected properties such as lands, structures, trees etc. We expect that local economy will improve and new job opportunities will be created. Property values will go up in the area and business and economic activities will be improved. Interruption to routine life may occur due to demolition of structures specially in Galewela town. During construction period there can be disturbances due to traffic congestion, dust, noise and vibration. The authorities need to take precautions to minimize disturbances to our day today activities and livelihoods

Management of road and transport system.

RDA Engineers Land acquisition will be a significant issue. The RDA will face lot of difficulties to settle social issues during construction period especially in Galewela & town areas. The officers of the RDA will be busy with the project implementation activities. After completion of the road the transport system will be improved. The annual road maintenance cost will be reduced and it will be a real benefit for the community. Number of road accidents will increase due to fast driving.

Management of Govt. bus We will have to face lot of difficulties during the construction period due to poor road conditions. service, After completion of the road, the transport system will improve. We will be able to operate our busses on time from Ambepussa-Dambulla and Kanthale-Trincomalee. Maintenance cost and fuel cost will go down.

54 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Private Bus Owners This project is good, as it will improve condition of the road. Currently we face lot of difficulties to drive our buses due to bad condition of roads. Currently our maintenance cost of buses is very high. Improved roads will help us to reduce fuel and maintenance costs. It is a good opportunity for us. We can save money. We will be able to provide a good service to the people after completion of works. We will run our buses on time to the destinations. There is a tendency for accidents to increase due to fast driving after the road improvements.

Road users and general public.

Employees We welcome the project. Now a days traveling on this road is a real headache. We cannot go to our office on time. But after the improvement of the roads there will be speedy driving leading to more accidents. There must be close supervision of contractor’s work to ensure good quality work. Existing drainage system should be improved.

I face a lot of difficulties to drive my car due to poor road condition. I cannot attend my office on time. Once the road is improved we can avoid such difficulties.

Road development is necessary. Many women in this area use bicycles as the mode of transportation. Their safety should be ensured.

Road development will encourage teachers and students to attend their schools regularly.

I have difficulties in riding my bicycle along the road due to a lack of space and there are possibilities for accidents. Road development will be beneficial for the women who are engaged in self employment as it will enable them to transport their produce to the town from the rural areas.

We thank the government. We have a lot of problems to reach schools School children , on time. The buses and school vans also can not travel on time especially on rainy days. We also cannot walk along the road due to poor drainage system. But after improvement of the road, we will be able to come to school on time. But there may be lot of accidents due to fast driving. There should be speed limits, especially near the schools.

During the construction period we may have to face number of problems due to dust, noise, traffic congestions and demolition of structures along the road.

55 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Doctors People face inconveniences in taking patients to nearby hospitals and medical centers, due to bad condition of roads. In emergency situations, doctors and health workers cannot reach the hospitals. Ambulances can not take patients immediately to the hospitals. These issues will be solved by this road development project.

But during the construction period the project authorities need to take measures to minimize health hazards caused by dust, waste and debris.

Three wheelers Drivers Currently vehicle maintenance cost is very high due to poor road & Other vehicles Drivers conditions. We cannot take our passengers to the destinations on time. The road construction activities should be completed within the scheduled time. There may be traffic congestions, accidents and delays during the construction periods. The project authorities need to take measures to minimize disturbances to our livelihood. After completion of the road we will be better off. Maintenance cost and fuel cost will be reduced.

Farmers We face lot inconvenience to transport our produce to Dambulla and Trincomalee. Transport cost is high due to the poor condition of the road. The improved road will help us to transport our goods to the market at a lower cost.

Transportation of our farm products will be affected during construction period.

Business community and income generation groups.

Shop owner The road sections near the junctions be inundated during the rainy seasons. The road is busy and used by heavy vehicles. This damages the road.

Traffic congestion prevails in the morning and evening. Also vehicle users find difficulty in using the road. Road widening is required.

The project will increase opportunities for tourism development in Dambulla and Trincomalee which in turn will have a positive impact on

56 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------local businesses. Tourist and devotees use this road to visit ancient religious places in this area.

Fish Sellers It is good if the road is developed. This type of development project will improve the businesses in the area. The project will facilitate the efficient transportation of fish from out side areas to this town.

I have the fear that my business will be affected temporarily during the construction period.

Road construction activities will disturb the business activities specially Pavement vendors in Galewela town. The road construction activities should be done by minimizing disturbances to our business.

There may be some obstructions ( concrete steps, access) at the structures of business centers. But it will not be a significant issue once the temporary accesses are provided. The project needs to complete the road construction as soon as possible. Religious leaders. During construction period there may be a lot of disturbances at the religious places.

Specially by creating dust, noise and vibrations.

Access roads will be blocked due to road construction activities.

To overcome and minimize these disturbances precautions should be taken.

The religious groups must be given proper access to the religious centers for their day to day activities. Local Politicians Provincial council members Construction activities will create lot of disturbances to the people in the project area. It is important to take actions to minimize such Pradeshiya Sabha members difficulties. The proposed road development activity will develop the area. The Government can make the people happy. Politicians can bring lot of investors to the area once the road is improved. Politicians can win the support of the people and can improve their popularity among the people in these areas.

As expressed by some of the respondents the newly developed highways tend to increase the incidents of the road accidents as well. These perceptions are summarized in the following Table 4.3

57 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 4.3 Negative implications of the project

Issues/Concerns No of Responses

Key informants N = 98 Number % Traffic congestion due to constructions 57 58 Disturbance to travel and transportation 48 49 Environmental pollution due to dust and noise during construction period 52 53 Increased accidents & some adverse social issues 08 08 Tend to decrease income during construction period 12 12

Source: Social Survey for RAP, February 2010.

4.6 Remedial measures / Strategies to mitigate the negative impact

Some negative impacts are unavoidable in any of the development interventions and it is therefore vital to understand the situation and take possible measures to minimize such negative impacts. Some measures could be adapted are presented below based on responses of various stakeholders during the Social Survey 2010.

 Necessity to provide properly organized drainage systems for the removal of rain water during deluge.  Implement some mechanism to reduce dust and noise due to heavy vehicle movement  Necessity of proper implementation of traffic rules and regulations to prevent road accidents.  Provisions of temporary spaces for the owners of three-wheelers and other small shop outlets to continue their livelihood without interruptions.  Make arrangements to keep smooth flow of traffic without unnecessary delays due to road closures.  Try to prevent the environment destruction and pollution minimizing the removal of trees by the road.  Attempt to undertake part of the road construction work during night or on holidays in order to prevent/minimize disturbances to road users.  Adhering to safety measures to prevent any health hazards or safety hazards due to demolition of structures/buildings.

58 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

4.7 Consultation Strategies

Stakeholders‟ participation is very vital throughout the project cycle. The project should maintain all records of all stakeholders consultations through a responsible officer attached to the project.

Pre - construction, Construction and Implementation levels of the project are the most suitable stages of stakeholder participation.

The project should identify type of stakeholders to be consulted and the suitable project stages when consultation would be necessary. Suitable project levels and stakeholders of consultation are furnished in table 4.4.

Table 4.4. Stages of Stakeholder Participation Stakeholder Stage 1: Stage 2 Stage 3: Social Stage4: Land Stage 5: GRM Stage 6: Road Stage 7: Stage 8: Feasibility Design & Assessment acquisition level Level Construction Defects Evaluation Level Planning Level Level Level liability level of Benefits Primary affectees (all √ √ √ √ √ √ - √ categories) Road users (all √ √ √ - - √ √ √ categories) Owners of √ √ √ √ √ - - √ common properties Wage earners - √ √ - √ √ - √ Vulnerable √ √ √ - √ - - √ groups Others (if any) √ √ √ √ √ √ √ √ Secondary Divisional - √ √ √ √ - √ √ Secretary Grama Niladaris √ √ √ √ √ - - √ Owners of √ √ √ - √ √ - √ business establishments Land officers √ √ √ - - - - - Property √ √ - √ - - - - developers CBOs/NGOs - √ √ √ √ √ - √ leaders MOH/Midwife - - - - √ - √ Others (if any) √ √ √ √ √ √ √ √

59 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

4.8 Disclosure of information

All information should be disclosed to all the stakeholders concerned. The project should follow the World Bank Operational Policy 17.50 related to disclosure of information.

All affectees should be consulted and inform regarding the nature of negative and positive impacts that would be created by the proposed project and the proposed mitigation to minimize negative impacts.

All affectees should be invited for awareness programmes with relevant stakeholders (Divisional Secretaries, All Pradeshiya Sabhas, Gramaniladharis, Samurdhi Officers, Religious leaders, Community Leaders, NGOs and Politicians etc..) to inform them regarding nature of impact on their livelihood, assets, properties and grievance redress mechanism as well as compensation packages.

The executive summary of the RP and other related chapters will be translated into the local languages and disseminated to all affectees and communities.

The regional offices of the RDA will be used to disseminate all information related to the project. In addition the web sites of RDA and PMU will be used for wider dissemination of information.

As explained by stakeholders of the road development projects along with their expected benefits would help to enhance livelihoods of the people. Meanwhile it is quite important to address the social issues and concerns taking remedial measures in order to obtain maximum benefits from the project.

60 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 5

Mitigation Measures

5.0. Introduction

The objective of this chapter is to discuss the mitigation measures to mitigate negative impacts proposed in the Resettlement Action Plan. The principles and guidelines proposed are primarily aimed at avoiding or minimizing, to a possible extent, the hardships and impoverishment that may result from project‟s intervention and mitigation of any adverse impact thereof at the household/community level. All decisions regarding design of construction work will be made, to the extent feasible, to facilitate the attainment of this objective.

Principles of Resettlement policies, principles to be followed by RDA, mitigation principles, mitigation of negative impacts and method and procedures adopted to mitigate negative impacts are discussed below.

5.1. Project Resettlement Principles and Scope of Mitigation

The basic resettlement principles of the RP are as follows: The affected persons (APs) are defined as those who stand to lose land, houses, structures, trees, crops, businesses, income and other assets as a consequence of improvements to/or improvement of the project‟s roads. Cut-off dates will be established to determine compensation eligibility of persons and their assets. These are the dates on which census of the affected persons and their assets will be taken. Any claim for compensation by the affected people after the cut-off date will be not eligible for compensation. For title deed holders – the cut off date will be the date on which section two (2) notification of the land acquisition process is gazetted. For non title holders (encroachers and others) the cut off date will be last day (02.05.2010) of Census survey for the resettlement action plan. All APs are equally eligible for cash compensation and rehabilitation assistance, irrespective of their land ownership status, to ensure that those affected by the Project shall be at least as well off, if not better off, than they would have been without the Project. Absence of a title will not be a bar to receiving compensation and livelihood assistance, (except for land where a title is required). All losses will be compensated at replacement cost, at market prices without deducting depreciation and salvage value for all losses (such as lands, crops,

61 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------The objective of this chapter is to discuss the mitigation measures proposed in the Resettlement Action Plan. trees, structures, businesses, etc.). Alternatively, structures/assets etc. will be rebuilt by the project at replacement cost. Encroachers in this context are defined as people owning lands and occupying legal or customarily recognized properties on public space in the ROW. Squatters are defined as those that occupy space that is legally or customarily someone else‟s, in this case the ROW. Compensation and resettlement will be satisfactorily completed before a No- Objection Certificate can be provided by the Government of Sri Lanka for award of civil works contracts. APs will be systematically informed and consulted about the project, and the RP will be made available in both English and local languages to the affected persons and communities. The consultative process shall include not only those affected, but also the neighboring communities, representatives of the RDA and other government agencies of the areas where the project is located, community leaders, local government, and community-based organizations (CBOs). Vulnerable groups (households below the recognized poverty line; disabled, elderly persons or female headed households) should be identified and included in the consultation process. The Project will purchase or acquire lands for the project. Payment for purchasing of lands or compensation for acquired lands will be made at replacement value at current market prices. Contractors will also follow the same principles (i.e. payment of compensation for all damages incurred etc.) The project will provide alternate access wherever it is blocked during construction. The proposed RP will apply to all Project Affected Persons who may be affected through impacts on private/community land or other assets due to minor realignments. Where community owned facilities or restricting access to common property resources etc., result from project related interventions, the project will rebuild such facilities and provide alternative access. There will be no land donation. The RDA will purchase the required lands at the market value on their willingness. The sellers (owners) will have the option to refuse it. If so, the RDA will implement Land Acquisition Process in Sri Lanka to acquire the required lands under the normal procedure. The Project executing agency will bear the costs of implementing this Resettlement Plan.

62 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------5.2 Impact Mitigation Modalities The following types of losses which are expected to result from Project intervention will be mitigated. Temporary displacement of temporary fish stalls, vegetable stalls , green gram selling stalls, lottery selling stalls and Three- wheelers parking stands and the locations of other small mobile` vendors. The project will ensure that their livelihood is not affected by providing them alternative places (for 4-5 days) to relocate them during the construction phase. They may return to their original place subsequently. Where there are physical assets of affectees (walls, gates, front walls and roof extensions of business places, permanent sales huts and access of business places etc.) in the project area of construction, the owners will be compensated at replacement value at the current market prices. In place of affected access of public venues, minor road access will be rebuilt immediately and temporary access will be provided during construction period at the relevant locations. Affected privately owned trees will be compensated as mentioned in the entitlement matrix. Lands will be purchased or acquired and payment and compensations will be made at replacement value at the current market prices without any delay. The project will identify and implement policies to mitigate any adverse impacts that may appear during implementation of the project.

5.3 Mitigation of negative impacts.

* Names of the project affected persons/ properties, assets, magnitude of the impacts, livelihood in this road sections including sizes for lands and replacing structures are given package wise in Annex 06A and 06B.

* The final cost calculation (as per designs) for social impact mitigation is provided in Chapter 07 in this report. It is based on the methodology provided and discussed in this chapter on mitigation.

The aspects to be mitigated include following:

 Mitigation of impacts on front walls of houses and buildings  Mitigation of impacts on cement floors /cement steps of business places  Permanent fences (Iron poles with concrete columns)  Mitigation of impact on gates  Mitigation of impacts on parapet walls  Mitigation of impacts on front walls / roof extension of business places  Mitigation of impacts on permanent sales huts  Mitigation of impacts on lands  Mitigation of impacts on trees

63 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------For Structures : (front walls of houses and buildings /cement floors /cement steps, permanent sales huts, gates, walls, fences, front walls/roof extensions of business places)

The amounts related to replacement of above structures are figured out on the basis of on- the- spot investigations with engineers of the RDA measuring the length and height of the structures and calculating the number of square feet. In addition, they examined the existing condition and determined the best way to replace these structures during the construction period. Material cost and labor cost are also considered determining unit rates. The engineers have indicated the cost of a unit (SLR) and finally that amount is calculated with the number of required units for each loss. The total cost for each loss is given in Chapter 07 of this report. These costs are calculated without deducting salvage value.

For affected lands

Names of all owners of the land and the amount (plot sizes) to be acquired or purchased are provided in Table 9 of Annex 06A and Table 09 of Annex 06B of this report.

To purchase or acquire required lands the RDA will follow a transparent process as follows;

The lands will be taken on willing buyer-willing seller basis.

The RDA determines that land is appropriate for the intended purpose

It will be at the replacement value at current market prices of the area.

The seller will have the option to refuse it.

It will be at replacement value at current market prices.

If any acquisition is carried out it will follow normal acquisition procedure without following the section 38A Proviso, which is the emergency procedure of the LAA.

It does not negatively affect the livelihood of any vulnerable group, and if so, that community developed mitigation measures are acceptable to the affectee.

There are no encumbrances on the lands.

The lands should not belong to any person who is below the poverty line.

64 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------For Trees ( timber and Fruits trees)

Privately owned Timber trees have been valued at SL Rs. 20,000 per tree while a fruit tree is valued according to the annual income of fruits. It is estimated that annual income of a fruit tree is SL Rs.2000.00. (Sea annex 06c). The project has got assistance from the Divisional Forest Officer and Agriculture Research Development Officer of the area to value the trees. The following factors will be considered for in the valuation process.

Current market value of timber Demand and current price of fruits. The life time of the trees The present age of the trees and potential for productivity.

The total cost for the trees is provided in the Chapter 07 of this report.

5.4 Suggested Mitigation Measures to minimize negative impacts.

5.4.1 Mitigation of impacts on cement floors /cement steps of business places - (as per designs)

As per designs the project needs to demolish 46 number of cement floors /cement steps of business places. The project will provide them new access /concrete steps with better quality. In addition, they will be provided temporary accesses during the construction period to enable them to continue regular business activities without losing their daily income. The owners will be informed exact dates by the RDA as to when the project plans to commence demolition of access and expected time frame for completion of work at these locations.

5.4.2 Mitigation of impacts on front walls of houses and buildings

The project needs to demolish 18 numbers of front walls of houses and buildings during construction period. The project will provide better quality front walls to compensate the damage. During the construction period the project will provide temporary safety arrangements for these locations. The owners will be informed exact dates as to when the project plans to commence removal of front walls and expected time frame for completion of work at these locations.

5.4.3 Mitigation of impacts on gates- (as per designs)

The project needs to demolish 64 numbers of gates as per designs. The owners will be provided new gates with better quality. The owners will be informed exact dates as to when the project plans to demolish of gates and expected time frame for completion of work at those locations. During the construction period the project will provide temporary safety arrangements.

65 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

5.4.4 Mitigation of impacts on parapet walls and permanent fences with iron poles and concrete columns - (as per designs)

The project needs to demolish 76 numbers of parapet walls and 08 permenant iron fence during construction period. The project will provide better quality parapet walls and an iron fence to compensate the damage. During the construction period the project will provide temporary safety arrangements for these locations. The owners will be informed exact dates as to when the project plans to commence removal of walls and fences and expected time frame for completion of work at these locations.

5.4.5 Mitigation of impacts on front walls/roof extensions of business places.- ( as per designs)

The project needs to demolish 38 number of roof extensions of business places. During the construction period temporary cover sheets will be provided to enable the owners to continue there business. The project will provide new roof extensions / front walls with better quality as they agreed. During the construction period temporary safety arrangements will be provided by the project. The owners will be informed exact dates by the RDA as to when the project plans to commence demolition

5.4.6 Mitigation of impacts on permanent sales huts.-(as per designs)

There are 15 permanent sales huts to be demolished. The owners will be will be provide new sales huts with better quality as they agreed.

5.4.7 Mitigation of impacts due to temporary displacement of fish stalls, vegetable stalls, green gram selling stalls, lottery selling stalls temporary sales outlets etc.- (as per designs)

The project will create impacts on 73 number of small scale temporary sales outlets. The project will ensure that their livelihood is not affected by providing them alternative places (for 4-5 days) to relocate them during the construction phase. The vendors can continue regular business activities without losing their daily income and they may return to their original place subsequently.

5.4.8 Mitigation of impacts on affected lands.-(as per designs)

As per designs the project has identified that 810m2 of privately owned lands will be affected by the proposed project. Where it is not feasible to avoid lands the RDA will have to purchase or acquire required lands. If any acquisition is carried out it will follow normal acquisition procedure without following the section 38A Proviso, which is the emergency procedure of the LAA.

66 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Total land requirement : 1885m2 (Government owned lands 1075m2 and Privately owned lands 810m2) Number of affected households : 06 Number of persons of affected households: 22

(See annex 06A and 06B for details – Names and addresses of affectees, affected land sizes and affected land percentage of total land holding).

5.4.9 Mitigation of impacts on affected trees.-(as per designs)

As per designs there are 16 privately owned timber trees and 17 fruit trees that will be affected in the Kanthale-Trincomalee road section and 39 privately owned timber trees and 09 fruit trees will be affected in Ambepussa-Dambulla road section. To calculate the value for the privately owned trees the project obtained assistance from the Agriculture Service Research Development Officer and Range Forest Officer of the area.

In addition to the above the project will take action as follows,

The project will obtain necessary approvals from relevant agencies to remove the trees. The project has to initiate a tree planting program in each construction package.

5.4.10 Mitigation of impacts on three-wheeler parking stands.-(as per designs)

The project will create impacts on 55 numbers of three-wheeler parking stands. The project will ensure that their livelihood is not affected by providing them alternative places (for 4-5 days) to relocate them during the construction phase. They can continue regular business activities without losing their daily income and the owners of three-wheelers may return to their original place subsequently.

5.4.11. Conducting awareness programmes and training

The project will organize public awareness programmes for the general public, and training programs on social safeguards, safety and health etc. to the staff of RDA and PMU, Consultants, contractors and other relevant Government officers.

Cost for conducting awareness programmes and meetings for public and project staff, RDA and Contractors is given in Chapter 07.

5.4.12 Cost for HIV/AIDS programs (in each package).

The project through contractors will conduct HIV/AIDS training programmes in each package. Cost for conducting HIV/AIDS programm for public, project staff, RDA and contractors is given in chapter 07.

67 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

5.4.13 Monitoring and Evaluation of social safeguards including GRM

The project will conduct social monitoring programs during construction period. The cost is calculated and included to the budget (Chapter 07).

5.4.14 Cost for additional structures to provide safety (Based on complaints, requests received by the community or Institutes)

There may be additional requests; complaints made by the community or institutions for safety or development of infrastructure facilities, e.g. Safety barriers and humps, retaining walls to protect slopes etc. The cost will be calculated and included to the budget (Chapter 07). Based on the impacts the following Entitlement Matrix has been prepared.

Entitlement Matrix

Type of Impacts Compensation Eligibility Responsibility recommended

A) All (cash) payments All affectees Social staff of RDA for losing lands who and PMU. purchasing/acquisition of have ownership Provincial 1. Loss of land land will be at title. replacement value at Director/RDA, 1.1 Non agricultural land current market prices. Divisional Secretary. (e.g residential lands, barren Acquisition will be lands) carried out under the normal procedure without following the section 38A proviso of the LAA.

A) For the agricultural All affectees Social staff of RDA lands compensation will irrespective of and PMU. be paid as item 1.1 ownership of title above. Provincial to land. B) Ex-gratia Payment of Director/RDA and 5% of the statutory value Divisional Secretary. subject to a minimum

value of Rs.10,000.00 Agrarian Service 1.2 and a maximum of Department, Rs.100,000.00, if vacant Agricultural lands possession is handed over on or before a date nominated by the RDA/DS. C) Sufficient time to be given to harvest crops or compensation for the loss of crops

68 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Type of Impacts Compensation Eligibility Responsibility recommended

Pay replacement cost at All affectees Social staff of RDA prevailing market value. losing assets and PMU. irrespective of Replacement cost Provincial 2. Lost Assets (1) ownership of title including material and Director/RDA, RE and to land. labour at current market Divisional Secretary.  Front walls of prices without deducting houses salvage value.  Fences  Gates For temporary shifting (  Parapet walls if any..) within the given time additional 25% of the compensation will be paid as Ex- gratia payment. All affectees Social staff of RDA losing assets and PMU. Pay replacement cost at irrespective of prevailing market value. Provincial 2.1 Lost Assets (2) ownership of title Director/RDA, RE and Replacement cost to land. Divisional Secretary. including material and  Access of business labour at current market places/concrete steps prices without deducting  Front walls of salvage value. business places Payment for any  Permanent sales associated loss of huts income while commercial structure is being built.

The project will pay All affectees Social staff of RDA replacement cost at losing livelihood and PMU. prevailing market price due to project 3. Loss income / livelihoods Provincial to rebuild the assets used implementation due to lost assets. Director/RDA, RE and for livelihood and pay a Divisional Secretary. lump sum (ie. 2 months earning). Pay replacement cost at All Public places Social staff of RDA prevailing market value. impacted and PMU. 4. Public Places Replacement cost Provincial

including material and Director/RDA, RE and Concrete/cement steps of public places labour at current market Divisional Secretary. prices without deducting salvage value.

5. Trees Timber and fruit trees All owners of trees Social staff of RDA lost will be valued at irrespective of and PMU. Value of fruit and timber present age, overall life owner of title to

69 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------trees expected and lost land Forest Department. income/output from the Provincial tree and compensated Director/RDA, RE and without deducting the Divisional Secretary. salvage value.

This is not expected to Tenants impacted Social staff of RDA be triggered. However, and PMU. if during implementation Provincial it is triggered, moving 6. Compensation for Director/RDA, RE and cost and rent for 3 tenants Divisional Secretary. months, assistance for finding alternative place if house on rent is involved. Compensation for value All owners of Social staff of RDA of lost yields. If crops irrespective and PMU. perennial crops are of title to land Provincial involved, cost for re- 7. Loss of agricultural Director/RDA and establishment of crops Divisional Secretary. Income elsewhere and compensation for lost Agrarian Service yields up to one year at Department, market price.

70 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Chapter 6

Implementation Mechanism

6. 1. Introduction

The overall responsibility for realization of implementation mechanism will be vested in the Project Director and staff of the Project Management Unit created specifically for the RSAP II and the RDA.

The staff of the PMU and RDA will be trained on implementation arrangements of the RAP. The construction supervision unit also will play an active role in the implementation of the resettlement activities. Institutional arrangements and their responsibilities for implementation of resettlement activities are summarized and given below.

6.2 RAP Implantation Plan

Implementation of RAP will commence with a public awareness program for each package. These programmes will be held before submission of acquisition proposal for lands to the Ministry of Lands (MOL) with the RAP.

The Project Management Unit (PMU) will ensure that this plan will be implemented properly in each construction package.

Table 6.1 Implementation Plan – for Major Events Activities Time Locations Responsibility ( Months) Public awareness programmes Within 01 month In each RDA,PMU (Before Package submission of acquisition proposal to MOL) Submission of acquisition proposal to Immediately after Locations RDA,PMU,MOH MOL conducting public are given in awareness Annex 06A programmes and 06B.

Notification of Section 2 gazette 2 months - MLD,PMU notice Notice for vesting order is gazetted 2 months - PMU,MLD,DS (section 38, LAA) state land registration process. Other clearances issued 3 months - PMU,ESD and other relevant departments

71 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Effect full compensation payments 7 months - PMU,ESD,DS, and implement land transfer NGO procedure (Sections 29-36LAA) Effect full compensations for title and 3 months - PMU,DS. non title holders The Project Director/PMU will sign cheques. The DS will disburse money for entitle persons. Clear the lands 8 months Locations PMU,ESD are given in Annex 06A and 06B. Demolition and rebuilding of Within 04 months Locations PMU,RDA, structures from the are given in CONSULTANT, CONTRACTOR commencement Annex 06A date of civil and 06B. contracts

Conducting Social safeguards Within 04 months - PMU trainings for RDA, PMU Consultant of date of and contractors staff. contracts award (before commencement of civil work at the site)

Conducting HIV-AIDS training Throughout the In each PMU, programmes construction package CONSULTANT, CONTRACTOR period(24 months) Management Information System Throughout the - PMU,ESD, project period NGO

Grievance Redressing Throughout the In each PMU,RDA, project period package CONSULTANT, DS,CONTRACTOR Internal Monitoring In each PMU,RDA,ESD Throughout the package project period/ (Quarterly) (formats used for RSAP I are attached as Annex 11)

External Monitoring At the end of In each EXTERNAL land acquisition package MONITOR, PMU, RDA,ESD process and at the end of project

72 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------6.3. Institutional Roles and Responsibilities

Institutional Roles and Responsibilities for implementation of Mitigation Measures to minimize negative social impacts are summarized in the table 6.2 below.

Table 6.2 Institutional roles and responsibilities for implementation of Resettlement Action Plan. Name of Institute & Activities and responsibilities to implement social Persons responsible safeguards Road Development Project executing agency. Authority

Director Lands/ESD Also Land Acquisition should be as per the guidelines stipulated in and Resettlement LAA and the resettlement could be done according to RAP. Assistants of the Land Acquisition is carried out it will follow normal acquisition Division/ESD of the procedure without following the section 38A Proviso, which is the RDA. emergency procedure of the LAA.

Provincial Director/RDA Mitigation of social impact and Implementation of Grievance redress mechanism as the Chairman of the GRC. Conducting Grievance redress Meetings. Coordination with line agencies.

Chief Engineer/ RDA Act as the Secretary of the GRC. Public consultation and awareness raising. Coordination with line agencies to replace all structures, affected parties located within the RoW. Assist to DS of the area to implement land acquisition process under the LAA. Executive Engineer/ RDA Monitoring and Evaluation of social mitigation activities and progress implementation. Coordination with utilities agencies.

Project Management Unit

Project Director Overall responsibility/ supervision for implementation of RAP and providing necessary assistance and guidance for the project staff to implement social safeguards successfully. The PMU is responsible for disbursement of R&R assistance amounts.

Social Specialist Implementation of RP. Providing training on social safeguards. Conducting public awareness. Providing guidance to implement social safeguards. Management of all social safeguards of the project. Public consultation and awareness raising Conducting training programs for all stakeholders.

73 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Coordination with all line agencies related to social safeguards. Monitoring and evaluation of all social safeguards of the project. Supervision of Implementation of grievance redressal mechanism

Supervisory Consultant Office

Resident Engineers Coordination with the PMU, RDA to implement social safeguards policies of the project. Responsible for implementation of Grievance Redress Mechanism.

Social Specialists, Take actions to implement the RP. Monitoring of progress of social safeguards taken to minimize negative social impacts. Preparation of progress reports on social safeguards.

Making changes to the designs to avoid significant social issues. Site engineers and Manage good relationship with affected parties and general public. Technical officers.

Divisional Secretariats

Divisional Secretary Act as the Acquisition officer and assist to the RDA to confirm ownership of properties and implement the land acquisition process. Participation in grievance redress committee as a member.

Utility Agencies

Regional Engineers of Shifting of utilities as per scheduled time. Telecom, Water Board Take responsibility to carryout shifting of utilities with minimum and Ceylon Electricity effect on consumers and general public. Board.

6.3.1 Compensation and R&R Assistance Disbursement Mechanism

RDA with financial support from GoSL and implemented through the Divisional Secretary will pay all compensation/entitlements as laid out in the entitlement matrix to all eligible affected persons/households.

Title holders :

Statutory compensation for title holders will be paid based on the valuation done by the Valuation Department of Sri Lanka.

74 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Non Title holders :

Non title holders will be compensated based on the one of the following mechanism.

1. Those who like to resettle voluntarily displaced will be compensated according to the entitlement matrix.

2. Those who are involuntarily displaced ( if any) will be compensated depending on the allowances depending on the described matrix.

All the payments will be made by the Project Director of the Project Management Unit.

6.4 Grievance Redress Mechanism

The RAP identifies a range of potential social impacts of construction of roads selected for rehabilitation and illustrates the measures and procedures needed to redress or mitigate grievances.

The sole purpose of the measures of redresses recommended in RAP is to avoid economic and social hardships to people resulting from the construction effects of the project. In order to accomplish this purpose, it is essential that the mitigation measures recommended in the RAP are followed closely by the project implementing agency. All of the recommended mitigation measures in the RAP are essential and none is significantly more important than the others. Some adverse impacts like resettlement of people are not likely to occur due to the scope of this project. This, notwithstanding, will be essential that certain measures recommended are closely followed prior to actual implementation of the scheduled work.

On the basis of the RAP, the note below provides a draft for the grievance redress measures, steps and procedures to be adopted by the RDA for each project. To assist the implementers, samples of reporting formats and applications are also outlined.

6.4.1. Proposed Grievance Redress Steps and Procedures

Maintaining of complaint register

Care will always be taken to prevent grievances rather than going through redressal system. Grievance can be minimized through careful sub-project design and implementation by ensuring active participation and consultation with APs, establishing rapport between the community and RDA through frequent interactions, transparency and monitoring. As a first step of the grievance redress steps a complaint register will be maintained in each REs office. On receiving a complaint, it will be registered at the RE‟s office and complaint will be given a reference number. Then RE

75 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------will review the complaint received and its documentation and also make arrangements to redress it. If the issue cannot be handled / settled by the RE himself / herself the complaint will be referred to the Grievance Redress Committee.

Establishment of a Grievance Redress Mechanism Committee (GRC) Grievance Redress Committees (GRCs) will be formed by the RDA in each Pradeshiya Sabha or other appropriate project locations consisting of the following members as given in table 6.3.

Table 6.3 Positions and Duties of the GRC Members Designation/Official Function in Task Assigned Remarks

Position the Committee

Provincial Director/RDA Convener- Chairing the GRC Grievance

(Chairman) Meetings, making Notice should be

recommendations and sendingHeaded within a for action month

Officer representing Secretary- Maintaining minutes,

RDA - at the project area CE or EE of the Correspondence on

RDA can act as the Decisions by the GRC

Secretary of the GRC

Chairman of the Member To represent local

Pradeshiya Authority and its

Sabha Concerns

Divisional Secretary Member To represent

Divisional Secretariat

And its Concerns

Member of local Member To represent the

Community organization Local community

76 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------/ NGOs and CBOs

A representative Member To represent the

Of concerned Concerned

PAP/Stakeholder PAP/stakeholder

Resident Engineer (RE) – He/She could also attend as a non-member to offer his observations if requested and clarify the matters related to the claims based on the field investigation of applications and show the implication that may emerge in project implementation.

Contractors Representative - He/She could also attend as a non-member. If requested and clarify the matters and answers and make comments regarding the related issue.

Creation of Awareness of the Grievance Redress Mechanism - RDA should inform the relevant APs/Communities, Grama Niladharis, Local Samurdhi Officers and Social Development officers of the Divisional Secretariats and Pradeshiya Sabhas of the areas about the existence of grievance redress mechanism.

RDA should prepare flyers indicating:

 Project brief including the benefits of the rehabilitated road for the public

 Procedures for registering a complaint

 Categories of persons, institutions and property/assets affected that can claim compensation

 Explanation of those who would not be considered as an affected person, property etc.

 The address of the authority to receive and register the application with the name of the officer in-charge, address, and telephone/fax numbers to contact.

Receiving Application for Redress The applications regarding grievances for redressal can be submitted to the Resident Engineer (RE) on week days during office hours. These applications are registered in the RE‟s office with all details such as names of the person, type of grievances etc. The RE along with the social safeguards staff will be responsible for the resolution of the grievance at the local level and if required will request a meeting of the GRC and

77 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------inform the other committee members regarding the grievance registered and actions taken so far.

A copy of the application for redress should be sent promptly to Provincial Director/RDA and Secretary/GRC with the observation of the RE.

6.4.2 Redress Committee Meetings (RCMs), Hearings, Proceedings and Recommendations

Depending on the applications to be considered, Redress Committee Meetings will be held in the Office of the Resident Engineer on the Thursday of every second week of the month at 2.00 p.m. If this day falls on a holiday, the meeting will be held on the following day at 2.00 p.m. In some cases, a need will arise to hold more than one sitting. In such instances, Provincial Director (PD) will schedule additional meetings and inform the applicant early in writing. Schedule must be strictly adhered to. If a member cannot attend a scheduled sitting, a representative should be sent. Minutes of the meetings, including the decisions taken regarding redress or otherwise, will be recorded by the GRC Secretary.

Minutes should be signed by all members of GRC. Applications, investigation reports, minutes of meetings and the decisions of the GRC on each of the application for redress should be maintained in the office of the PD/RDA for future reference.

6.4.3 Implementation of decisions of GRC The minutes of the GRC signed by the GRC members are maintained at the office of the Provincial Director of RDA. The recommendations along with other issues will be sent to the Project Director within a week after the GRC meeting. The same information will also be sent to the relevant applicants for his information. The recommendations will be implemented before the construction work is started in the sections of the road where affected persons have claimed for redress.

6.5 Monitoring and Evaluation Mechanism

Monitoring and evaluation are vital activities of the project. The project has the responsibility to implement all activities identified and on time. The objectives of monitoring of the RP are to: 1.) ensure all activities of the RP are implemented 2.) Ensure that the standard of living of affectees is restored or improve 3) Monitor whether the time lines are being met, 4) Assess whether mitigation efforts are sufficient, 5) Identify construction related problems or potential problems, and 6) Identify methods of responding immediately to mitigate hardships.

78 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------The monitoring and evaluation of the mitigation process is carried out by the RDA. The RSAP II project office and the consultant‟s office are responsible for implementing a suitable program for monitoring and evaluation of the social impact mitigation with active participation of the staff of each RE‟s office in the respective sub-project areas.

The staff attached to the RE‟s offices is involved in supervision of the construction activities and also mitigation of negative impacts. One of the main roles assigned to this group is frequent monitoring of the field condition on impact mitigation.

The reports they prepare based on their monitoring are sent to RSAP project office and the consultants' office located in Colombo.

The monitoring indicators consist of activities, performance and outcome as laid out in the entitlement matrix to ensure that the affected persons are identified in the RP and receive the compensation on time for those that they eligible for (Please see Table 6.4 for monitoring & evaluation indicators).

In addition the GRM will be closely monitored to ensure that all complaints are resolved on time and in a satisfactory manner. The conflict filter, that is a part of the project, will also be monitored. The specific objectives of the M&E program are;

to ensure that the existing livelihood system of APs is not disturbed. to monitor whether the timelines are being met; to assess if compensation, rehabilitation measures are sufficient; to identify problems or potential problems to identify methods of responding immediately to mitigate problems.

Furthermore, the M&E program will (a) record and assess project inputs and the number of persons affected and compensated, and (b) confirm that former subsistence levels and living standards are being re-established.

Internal Monitoring Internal monitoring will be conducted by RDA with the involvement of project office, construction supervisory consultant office and especially the REs office in each sub project area. The resettlement specialists with support from staff of construction supervision and also the environmental officers hired by the contractors will collect information from the project sites and reflect them in the form of a monthly or quarterly progress report to assess the progress and results of RP implementation, and adjust the work program, where necessary, in case of any delays or problems. A set of indicators mentioned in table 6.4 is proposed to

79 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------enhance the current M&E system. Formats used in the RSAP 1 are attached as Annex 11.

Table 6.4 Monitoring and Evaluation Indicators

Type Indicator Examples of Variables Process Consultation, Number of consultation and participation programs Indicator Participation, held with various stakeholders on entitlements, & valuation as per replacement value etc Grievance Grievances by type and resolution Resolution Number of field visits by RDA staff, GRC members Number of NGOs/civil society organizations participating in project Procedures in Joint asset verification/quantification procedures in Operation Place. Effectiveness of compensation delivery system. Coordination between RDA and other line agencies. No. of lands Area of agricultural, nonagricultural lands acquired or plots purchased. purchased, Area of other private lands purchased or acquired Outcome acquired and Area (and type) of state lands acquired. Indicator compensated. Total quantity of land to be purchased and acquired. Amount of compensations out of the total resettlement budget.

Structures Number, type and size of structures belongs private parties affected and also replaced /paid compensation by RDA. Number, type and size of common structures affected and also replaced / paid compensation by RDA. Number, type and size of government structures affected and also replaced / paid compensation by RDA.

Trees and Number and type of crops and trees in private land Crops acquired and compensated. Number and type of crops and trees in government or other common lands acquired or purchased. Compensation Number of owners compensated by type of loss and Number of replacement of structures and amount of Rehabilitation compensation paid as replacement cost by the RDA

Number of poor and vulnerable APs assisted

80 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------/supported by RDA. Assistance/support provided by the RDA to the Communities. Number of structures constructed to stabilize slopes etc. Where land were purchased and acquired.

Settlement Growth in number and size of settlements Impact and Growth in market areas Indicator Population Standard of living

Baseline census, socio-economic survey and the land purchasing and acquisition data will provide the necessary benchmark for field level monitoring. The methods that will be used to carry out field level monitoring include:

(a) Review of census / information for all APs; (b) Consultation and informal interviews with APs; (c) In-depth case studies; (d) Informal sample survey of APs; (e) Key informant interviews; and (f) Community public meetings.

The project will appoint an external social expert on resettlement to carryout field level monitoring.

External Monitoring – Third party validation

External monitoring or third party validation will be conducted by an independent external body. Objective of Third Party Validation (TPV) will be to validate the results of the internal monitoring system and to measure the effectiveness of implementing the RAP on the lives of PAPs. Special attention will be paid on issues of land acquisition. RDA will make arrangement to conduct TPV at two stages. The first TPV will be carried out once the entire land acquisition process is completed. The second one will be done at the end of the project.

Management Information System (MIS)

The RSAP project office in Colombo is maintaining a computer based data base, on all construction activities of the project. Some information on mitigatory actions of social impacts is also included in the data base. However the RDA will enhance the data on resettlement issues and the actions taken for mitigation of such issues. The information reported by each RE office will be used to develop the data base.

81 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Reporting Requirements

The Project Management Unit of the RSAP office is the overall responsible organization for reporting of the project progress and other aspects to the Bank.

Each RE office will prepare progress reports and submit to Colombo based offices, Project Director‟s office and the construction supervisory consultants‟ office. The Project director‟s office will send progress reports to the Bank based on the report submitted by the supervisory consultant. This reporting will be carried out quarterly or biannually.

Awareness Programms

It is important to pay special attention to provide real information about the proposed project and activities for all parties through awareness programmes in each road section in this road improvement project (table 6.5). The awareness programmes should cover following groups;

General Public Villagers Community leaders/ Religious leaders Project affected parties Beneficiary community of the project influenced area Government Institutes and Government Officers Project implementing, executing, supervising agencies (RDA, PMU, and Consultant Etc.) Private Sector Road Users Security Forces Local Politicians Labors Contractors CBOs and NGOs

82 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 6.5: Awareness Programs for targeted groups Target Group When and Where Information need to be Trainers to Conduct disseminated General It should be 1. WB policies in this Resettlement Public, conducted before regards. Experts attached commencement of 2. Proposal to rehabilitate to the ESD/RDA Community road construction. the road. and Environment Leaders, These programmes 3. New width of the road and Social should have in each 4. Funding agency Specialist of Religious road section of the 5. Length of the road PMU. Leaders, project 6. Commencement date 7. Target end date Villagers, 8. Possible threats to each group of people. Beneficiary 9. The type of support community of expected from the public the project during the construction influence phase area, 10. Safety measures. 11. Grievance Redress Road Users, Mechanism 12. Negative impacts Private sector during the construction phase Security 13. Mitigatory measures to forces be taken 14. Compensation packages Local 15. Awareness about the Politicians, RAP 16. Targeted benefits after CBOs and completion of the project NGOs 17. Creation of job opportunities for local people 18. Additional income generation activities during the project

Project It should be 1. Proposal to rehabilitate Resettlement Affected conducted before the road. Experts attached Parties commencement of 2. New width of the road to the ESD/RDA road construction. 3. Length of the road and Environment These programmes 4. Land acquisition process and Social should have in each 5. Compensation packages Specialist of road section of the 6. Commencement date of PMU. project. road construction

83 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------7. Target end date 8. Possible threats to each group of people. 9. The type of support expected from the public during the construction phase 10. Grievance Redress Mechanism 11. Negative impacts during the construction phase 12. Mitigatory measures to be taken 13. Awareness about the RAP 14. Targeted benefits after completion of the project 15. Creation of job opportunity for local people 16. Additional income generation activities during the project 17. Funding agencies Government It should be 1. Proposal to rehabilitate Resettlement institute and conducted before the road. Experts attached Government commencement of 2. New width of the road to the ESD/RDA officers road construction. 3. Length of the road and Environment These programmes 4. Expected administrative and Social should have in each support to the project Specialist of road section of the 5. Approvals need to be PMU. project. obtained 6. Compliance of policies available in the Sri Lanka government and the World Bank to mitigate negative impacts. 7. Land acquisition process 8. Compensation packages 9. Commencement date of road construction 10. End date of the project 11. Possible threats to each group of people. 12. The type of support

84 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------expected from the public during the construction phase 13. Grievance Redress Mechanism 14. Negative impacts during the construction phase 15. Mitigatory measures to be taken 16. Awareness about the RAP 17. Targeted benefits after completion of the project 18. Creation of job opportunity for local people 19. Additional income generation activities during the project Project It should be 1. Importance of ensuring Hired Social implementing conducted before safety of the community. Development , executing , commencement of 2. Compliance of WB expert supervising road construction policies in this regards. agencies and it should have 3. Land acquisition process Resettlement ( RDA, PMU, for each group of and compensation experts attached Consultant. laborers related to packages to the ESD/RDA. Etc.) each contractor. 4. Possible threats to each group of people. 5. Vulnerable families 6. Ensure villager‟s livelihood minimizing construction related disturbances. 7. Labor laws and rights. 8. Creation of job opportunities for local people 9. Implementation of Grievance redress mechanism 10. Social activities monitoring plans 11. Implementation of mitigatory measures for mitigating negative social

85 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------impacts 12. Ensure villager‟s livelihood minimizing construction related disturbances. Labors It should be 1. Importance of ensuring Social specialists conducted before health seeking behavior. attached to the commencement of 2. WB policies in this ESD/RDA and road construction regards. PMU. and it should have 3. Possible threats to each Medical health for each group of group of people. officers laborers related to 4. Safety measures. Traffic police each contractor. 5. Child and women rights officers and abuses. Hired social 6. Ensure villager‟s development and livelihood minimizing gender construction related specialists. disturbances.

The Project Management Unit should focus special attention to raise awareness among the key stakeholders of the project. The major aspects to be covered by training programmes are given in table 6.6.

Table 6.6 Major aspects to be included to awareness /training programmes

Training Aspects Target groups Trainers

World Bank Social Safeguards Policies RDA staff, ESD staff of Social Development RDA, PMU staff, Experts of World Consultants, Bank. Contractors, Divisional secretaries., Land officers, Grama Niladharies (GS).

Implementation of Resettlement Action RDA staff, PMU staff, Resettlement Plan – RSAP II Consultants staff, specialists attached Contractors, Divisional to ESD/RDA and Secretaries, Land Social Specialist Officers, Community, attached to PMU. NGOs and CBOs

Involuntary Resettlement Policy of Sri RDA staff, PMU staff, Hired Resettlement Lanka Consultants staff, and Social Contractors, Divisional Development

86 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Land Acquisition process of Sri Lanka Secretaries, Land experts and Gender Officers, Community, specialists. Compensation Packages, NGOs and CBOs Social Impact Monitoring tools

Screening of Vulnerable families and

Women and Child rights

Women participation for project work

Traffic Management & Prevention of RDA Staff, ESD staff of Experts attached to Safety Hazards RDA, PMU staff, the Planning Unit of Consultants, the RDA. Divisional Secretaries,

Land Officers and Contractors. Hired experts from University of Moratuwa

Relocation of Utilities RDA staff, PMU staff, Resource Persons Consultants staff, from Utility Reduction of Contractors, Divisional Agencies Interruptions/disturbances to the Secretaries. community

6.6 Strategies to obtain community support to minimize negative social impacts through awareness programmes.

The RSAP will provide funds for a wide range of training programmes on social safeguards of the project.

Training programmes will be organized by the project management unit by obtaining services from outside experts for RDA staff, PMU staff, Consultants staff and Contractors to raise their awareness of social safeguards policies. These awareness programmes will help them to deal effectively with negative social issues raised by the public.

The training programmes include public awareness programmes, local seminars and workshops.

87 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

The capacity building programmes on social safeguards will be conducted in each road section. The information related to Resettlement Action Plan will be disseminated for the public information on the project and its implications. Suggested mitigatory measures for negative social impacts will be discussed during the awareness programmes.

All information about the project activities will be provided to help minimize negative impacts and obtain support of the community affected. The Resident Engineers and staff members will closely contacts with the project affected families, the community, community leaders, religious leaders and local politicians of the project area. Several training programmes / awareness programmes will be conducted for the contractors and laborers to make them aware of the project and their role in dealing with social issues.

The contractors will be provided with all information of the project including negative impacts that may emerge during the construction period and entitlement policies to minimize the negative impacts.

6.6.1 Conducting HIV/AIDS Awareness Programmes

The project contract specifies that the contractors shall conduct awareness programmes via an “approved Service Provider” and shall undertake such other measures as are specified herein to reduce the risk of the transfer of HIV virus between contractors‟ personnel and the local community, to promote early diagnosis and assist affected individuals.

The current ratio of HIV-positive men to women in Sri Lanka is reportedly 1.4 to 1, although in reality, there are probably far more men infected than women as in most early phase HIV epidemic. The current estimated HIV prevalence ( the ratio of the number cases of a disease present in a statistical population at a specified time and the number of individuals in the population at that specified time) in the sexually active age group ( between 15-49 year olds) is less than 0.1% which categorizes the status of HIV in Sri Lanka as “low prevalence”.

The proposed programme by contractors will see to raise awareness and generate behavior change amongst all persons involved in commercial sex transaction at the temporary housing sites for construction workers and the surrounding communities of roads construction sites. This includes working with all levels of employees including construction workers (skilled and unskilled), migrant as well as those from the locality and management personnel. The programme will also intend to work with members of surrounding communities who are considered highly vulnerable to engage in risky sex-behavior, particularly the commercial sex activity because of poverty and inexperience of the people living in the project areas.

88 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Chapter 7

Cost Calculation for mitigation of negative impacts – (As per designs)

7.0. Introduction

The overall responsibility for implementing mitigatory measures of the Project Management Unit, created specifically for the RSAP II. The Construction Supervision Unit also plays an active role in the implementation of the resettlement activities.

7.1 Cost calculation for affected structures

The cost calculation is done on the basis of guidelines and methodology discussed in the chapter 05 of this report.

The unit prices and total amounts related to replacement of affected structures are figured out as follows,

1. On- the- spot investigations with engineers of the RDA. 2. Measuring the length and height of the structures and calculating the number of square feet of each of them. 3. Examine the existing conditions and determine the best way to replace these structures during the construction period. 4. Analyzing current prices of building materials in the area. 5. Examine labor cost related to construction industry in the area.

Finally the engineers have indicated the unit price (SLR) and total amount is calculated with the number of required units for each loss. Total cost related to replacement of affected structures is provided in separate tables for each package.

7.2 Cost calculation for affected lands.

Cost calculation for lands is done on the basis of guidelines and methodology discussed in chapter 05 of this report. The project authorities have taken a decision to purchase required lands at the value of market prices of the area.

If any land owner is not willing to sell his/her land to the RDA. The RDA can take actions to acquire the required land under normal acquisition procedure of the land Acquisition Act of Sri Lanka. Total cost related to affected lands is provided in separate tables for each package.

89 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

7.3 Cost Calculation for Ambepussa- Dambulla road section. (The details may change once the designs are finalized)

Table 7.1 Cost calculation for cement floors /cement steps of business places Package Chainage Unit price No. of units Total Cost (SLR) (km) (SLR) (Square feet) 01 18+450-RHS 150.00 12 1,800.00 01 21+495-RHS 150.00 15 2,250.00 02 23+445-RHS 150.00 25 3,750.00 02 25+100-LHS 300.00 18 5,400.00 02 27+100-RHS 250.00 30 7,500.00 02 31+700-RHS 200.00 30 6,000.00 02 32+620-LHS 250.00 25 6,250.00 02 33+060-LHS 250.00 40 10,000.00 02 34+605-LHS 250.00 25 6,250.00 02 39+760-LHS 150.00 30 4,500.00 02 46+550-LHS 150.00 30 4,500.00 03 53+270-RHS 150.00 40 6,000.00 03 58+800-LHS 250.00 18 4,500.00 03 60+620-RHS 250.00 35 8,750.00 03 61+500-LHS 250.00 20 5,000.00 04 73+800-RHS 250.00 20 5,000.00 04 73+950-RHS 200.00 25 5,000.00 04 74+060-LHS 300.00 30 9,000.00 04 74+080-LHS 150.00 32 4,800.00 04 74+100-RHS 150.00 35 5,250.00 04 74+110-LHS 300.00 40 12,000.00 04 74+115-LHS 250.00 40 10,000.00 04 74+125-LHS 200.00 18 3,600.00 04 74+250-RHS 200.00 30 6,000.00 04 74+260-LHS 200.00 15 3,000.00 04 74+350-RHS 250.00 15 3,750.00 04 74+400-RHS 150.00 25 3,750.00 04 74+410-RHS 150.00 15 2,250.00 04 74+415-RHS 150.00 20 3,000.00 04 74+505-LHS 250.00 25 6,250.00 04 74+518-RHS 200.00 25 5,000.00 04 74+600-LHS 200.00 28 5,600.00 04 74+620-RHS 150.00 35 5,250.00 04 74+700-RHS 150.00 30 4,500.00 04 74+710-LHS 200.00 25 5,000.00 04 74+720-RHS 200.00 30 6,000.00 04 74+780-LHS 200.00 18 3,600.00 04 74+785-RHS 150.00 15 2,250.00

90 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------04 74+800-LHS 150.00 20 3,000.00 04 76+302-RHS 150.00 32 4,800.00 04 76+400-LHS 150.00 18 2,700.00 04 80+230-RHS 150.00 20 3,000.00 04 88+400-LHS 150.00 15 2,250.00 04 88+560-LHS 150.00 22 3,300.00 Total 221,350.00 Source- social survey for RAP, 2010

Table 7.2 Cost calculation for Gates Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet) (SLR) 02 31+560-LHS 200 60 12,000.00 02 32+000-LHS 200 100 20,000.00 02 32+620-LHS 300 70 21,000.00 03 60+600-RHS 200 70 14,000.00 03 61+600-LHS 200 70 14,000.00 03 61+715-RHS 250 45 11,250.00 03 63+720-LHS 150 35 5,250.00 04 69+700-LHS 200 60 12,000.00 04 75+340-RHS 175 80 14,000.00 04 80+980-RHS 150 125 18,750.00 Total 142,250.00 Source- social survey for RAP, 2010

Table 7.3 Cost calculation for parapet walls Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet)

(SLR) 01 9+370-RHS 150 120 18,000.00 01 14+680-RHS 225 110 24,750.00 01 15+160-LHS 275 250 68,750.00 02 27+100-RHS 150 170 25,500.00 02 39+740-LHS 150 155 23,250.00 02 44+240-RHS 200 280 56,000.00 03 60+650-RHS 250 210 52,500.00 03 61+600-LHS 250 190 47,500.00 03 63+720-LHS 275 130 35,750.00 03 67+370-LHS 250 90 22,500.00 04 69+700-LHS 275 160 44,000.00 Total 418,500.00 Source- social survey for RAP, 2010

91 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 7.4 Cost calculation for permanent fences (iron poles with concrete columns) Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet)

(SLR) 02 25+100-RHS 300 200 60,000.00 02 25+320-LHS 250 270 67,500.00 02 29+940-RHS 350 180 63,000.00 02 30+520-RHS 300 210 63,000.00 02 31+560-LHS 300 250 75,000.00 02 32+000-LHS 350 300 105,000.00 04 74+000-LHS 250 360 90,000.00 Total 628,500.00 Source- social survey for RAP, 2010

Table 7.5 Cost calculation for front walls / roof extensions of business places Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet) (SLR) 02 33+060-RHS 150 90 13,500.00 02 34+000-LHS 200 85 17,000.00 02 34+120-RHS 200 120 24,000.00 02 34+370-LHS 150 90 13,500.00 02 39+860-RHS 200 95 19,000.00 02 46+740-RHS 200 90 18,000.00 03 51+900-LHS 150 110 16,500.00 03 52+900-LHS 150 125 18,750.00 03 58+800-RHS 150 75 11,250.00 03 58+820-RHS 250 120 30,000.00 03 58+910-RHS 250 120 30,000.00 03 59+020-LHS 250 70 17,500.00 03 60+600-RHS 150 90 13,500.00 03 66+290-RHS 200 110 22,000.00 03 66+370-RHS 200 125 25,000.00 04 72+300-RHS 200 220 44,000.00 04 72+400-RHS 250 230 57,500.00 04 76+030-RHS 250 175 43,750.00 04 88+020-RHS 250 90 22,500.00 04 88+050-RHS 250 120 30,000.00 Total 487,250.00 Source- social survey for RAP, 2010

92 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Table 7.6 Cost calculation for permanent sales huts Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet)

(SLR) 02 33+045-LHS 250 45 11,250.00 02 44+750-RHS 250 55 13,750.00 02 45+030-RHS 200 40 8,000.00 03 50+780-RHS 200 45 9,000.00 03 55+620-LHS 250 60 15,000.00 03 63+450-RHS 200 55 11,000.00 03 65+070-LHS 250 50 12,500.00 04 70+230-RHS 200 45 9,000.00 04 79+235-RHS 200 50 10,000.00 Total 99,500.00 Source- social survey for RAP, 2010

Table 7.7 Cost calculation for Lands Package Chainage Extent (m2) Ownership Remarks Total Cost (km) (SLR) 01 1+120km-LHS 200m2 Private Current market 480,000.00 (8 perch) price 01 1+220km- RHS 250m2 Private Current market 700,000.00 (10 perch) price 01 12+200km 100m2 Government Land will be - LHS (4 perch) transferred to RDA 01 14+680km-LHS 100m2 Government Land will be - (4 perch) transferred to RDA 01 15+870km 100m2 Government Land will be - RHS (4 perch) transferred to RDA 02 24+080km 120m2 Private Current market 240,000.00 RHS (4 perch) price 02 40+040km 100m2 Private Current market 320,000.00 (4 perch) price 03 64+350km 125m2 Government Land will be - LHS (5 perch) transferred to RDA 03 65+220km 125m2 Private Current market 400,000.00 LHS (5 perch) price 03 66+480km 140m2 Private Current market 440,000.00 RHS (5.5 perch) price 03 66+840km 150m2 Government Land will be - RHS (6 perch) transferred to RDA Total 2,580,000.00 Source- social survey for RAP, 2010

93 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

7.4 Cost for affected trees.

The calculation of cost is done on the basis of guidelines and methodology discussed in chapter 05 of this report. There are 48 privately owned trees to be removed. Out of them 39 trees are timber trees while 09 trees are fruits trees. To calculate the value (table 7.15) of the trees the Project seeks assistance from the Agricultural Service Research Development Officer and Range Forest Officer of the area. The following factors will be considered for in the valuation process.

Present market value of timber Demand and current price of fruits. The life time of the trees The present age of the trees and Potential for productivity.

Table 7.8 Cost calculation for affected trees as per designs Road section Number of Method of costing Total Cost (SLR) Trees Kanthale-Trincomalee Fruit trees – 09 Number of potential 180,000.00 road section years 10, annual income SLR. 2000.00

Timber trees- 39 Timber value at market 780,000.00 price, each tree is SLR. 20,000.00

Total 960,000.00 Source- social survey for RAP, 2010

Cost for public awareness programmes.

One public awareness program will be conducted in each package. Cost for 01 programme SLR. 50,000.00

Social safeguards training programmes-

Social safeguards training programmes will be conducted for RDA regional officers/ PMU Project engineers / Consultant/ Divisional secretaries and relevant GOVT. Officers of the area.

One training programmes will be conducted in each package Cost for 01 programme = SLR. 100,000.00

Cost for HIV/AIDS programmes ( in each package).

Provisional sum per package SLR. 700,000.00

94 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Cost for monitoring and evaluation of social safeguards including GRM

Cost of M&E of social safeguards and implementation of GRM Cost for one package SLR. 250,000.00

Provision of additional structures (Based on requests, complaints received by the community or Institutes to improve safety) Cost for one package = SLR.1,000,000.00

7.5 Budget for mitigation of impacts for each package

Cost for implementing the social impacts mitigation measures for each package is given as follows.

Table 7.9A - Cost calculation for Package 01 Table 7.9B - Cost calculation for Package 02 Table 7.9C - Cost calculation for Package 03 Table 7.9D - Cost calculation for Package 04

Total Cost for Mitigation of Negative Social Impacts for Package 01 (The details may change once the designs are finalized).

Table 7.9A Total Cost for Social Mitigation Measures Item Cost – SLR. Cement floors/cement steps of business places 4,050.00 Gates 0 Parapet walls 111,500.00 Shifting of permanent fences (Iron poles with concrete 0 columns Front walls/roof extensions of business places 0 Permanent Sales Huts 0 Cost for removal of Trees 200,000.00 Cost for lands 1,180,000.00 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00 HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 3,595,550.00 Source- social survey for RAP, 2010

This estimate is prepared on the basis of information obtained by the RDA.

95 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Total Cost for Mitigation of Negative Social Impacts for Package 02 (The details may change once the designs are finalized).

Table 7.9B Total Cost for Social Mitigation Measures Item Cost – SLR. Cement floors/cement steps of business places 54,150.00 Gates 53,000.00 Parapet walls 104,250.00 Shifting of permanent fences (Iron poles with concrete 433,500.00 columns Front walls/roof extensions of business places 105,000.00 Permanent Sales Huts 33,000.00 Cost for removal of Trees 60,000.00 Cost for lands 560,000.00 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00 HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 3,502,900.00 Source- social survey for RAP, 2010

Total Cost for Mitigation of Negative Social Impacts for Package 03 (The details may change once the designs are finalized).

Table 7.9C Total Cost for Social Mitigation Measures Item Cost – SLR. Cement floors/cement steps of business places 24,250.00 Gates 44,500.00 Parapet walls 158,250.00 Shifting of permanent fences (Iron poles with concrete 0 columns Front walls/roof extensions of business places 184,500.00 Permanent Sales Huts 47,500.00 Cost for removal of Trees 480,000.00 Cost for lands 840,000.00 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00 HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 3,879,000.00 Source- social survey for RAP, 2010

96 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Total Cost for Mitigation of Negative Social Impacts for Package 04 (The details may change once the designs are finalized).

Table 7.9D Total Cost for Social Mitigation Measures Item Cost – SLR. Cement floors/cement steps of business places 138,900.00 Gates 44,750.00 Parapet walls 44,000.00 Shifting of permanent fences (Iron poles with concrete 90,000.00 columns Front walls/roof extensions of business places 197,750.00 Permanent Sales Huts 19,000.00 Cost for removal of Trees 0 Cost for lands 0 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00 HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 2,634,400.00 Source- social survey for RAP, 2010

7.6 Cost Calculation for Kanthale – Trincomalee road section. (As per finalized designs)

Table 7.10 Cost calculation for front walls of house and other buildings Package Chainage Unit price No. of units Total Cost (SLR) (km) (SLR) (Square feet) 06 197+800-LHS 200 120 24,000.00 06 197+470-LHS 150 113 16,950.00 06 198+350-LHS 300 380 114,000.00 06 198+370-LHS 250 355 90,525.00 06 198+385-LHS 200 226 45,200.00 06 198+400-LHS 200 322 64,400.00 06 198+420-LHS 200 129 25,800.00 06 198+680-LHS 250 161 40,250.00 06 198+690-LHS 300 290 87,000.00 06 198+835-LHS 300 258 77,400.00 06 198+845-LHS 250 161 40,250.00 06 198+880-LHS 250 290 72,500.00 06 198+888 LHS 250 258 64,500.00 06 198+940-LHS 250 290 72,500.00 06 199+145-LHS 150 376 56,400.00 06 199+180-LHS 300 750 225,000.00

97 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------06 199+230-LHS 300 527 158,100.00 06 199+240-LHS 300 430 129,000.00 Total 1,403,775.00

Table 7.11 Cost calculation for cement floors/cement steps of business places Package Chainage Unit price No. of units Total Cost (SLR) (km) (SLR) (Square feet) 06 198+220-LHS 300.00 12 3600.00 06 198+300-LHS 300.00 15 4500.00 Total 8100.00 Source- social survey for RAP, 2010

Table 7.12 Cost calculation for Gates Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet)

(SLR) 05 161+220-RHS 200 50 10,000.00 05 163+102-RHS 200 50 10,000.00 05 164+160-LHS 300 180 54,000.00 05 169+115-LHS 250 60 15,000.00 05 171+170-LHS 200 55 11,000.00 06 191+535-RHS 200 40 8,000.00 06 196+880-RHS 200 40 8,000.00 06 196+900-LHS 200 40 8,000.00 06 197+140-LHS 200 50 10,000.00 06 197+240-LHS 300 30 9,000.00 06 97+280-LHS 300 45 13,500.00 06 197+320-LHS 300 25 7,500.00 06 197+340-LHS 200 50 10,000.00 06 197+340-LHS 200 50 10,000.00 06 197+370-LHS 200 40 8,000.00 06 197+380-LHS 300 30 9,000.00 06 197+390-LHS 300 30 9,000.00 06 197+500-LHS 300 25 7,500.00 06 197+760-LHS 250 60 15,000.00 06 197+860-LHS 200 35 7,000.00 06 197+868-LHS 200 40 8,000.00 06 197+890-LHS 250 50 12,5000.00 06 197+895-LHS 250 35 8,750.00 06 197+900-LHS 250 40 10,000.00 06 198+120-LHS 300 60 18,000.00 06 198+120-LHS 300 45 13,500.00 06 198+200-LHS 250 80 20,000.00 06 198+300-LHS 250 35 8,750.00

98 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------06 198+325-LHS 250 40 10,000.00 06 198+350-LHS 300 40 12,000.00 06 198+370-LHS 300 35 10,5000.00 06 198+385-LHS 250 40 10,000.00 06 198+400-LHS 250 40 10,000.00 06 198+420-LSH 250 35 8,750.00 06 198+440-LHS 200 60 12,000.00 06 198+440-LHS 200 50 10,000.00 06 198+540-LHS 250 60 15,000.00 06 198+540-LHS 250 50 12,500.00 06 198+620-LHS 300 55 16,500.00 06 198+680-LSH 300 50 15,000.00 06 198+812-LHS 250 45 11,250.00 06 198+835-LHS 200 45 9,000.00 06 198+880-LHS 250 35 8,750.00 06 198+940-LHS 250 40 10,000.00 06 199+145-LHS 300 35 10,500.00 06 199+180-LHS 250 40 10,000.00 06 199+200-LHS 250 40 10,000.00 06 199+210-LHS 200 35 7,000.00 06 199+220-LHS 200 35 7,000.00 06 199+230-LHS 200 35 7,000.00 06 197+380-RHS 250 40 10,000.00 06 197+420-RHS 250 40 10,000.00 06 197+500-RHS 250 45 10,000.00 06 197+840-RHS 250 45 10,000.00 Total 705,750.00 Source- social survey for RAP, 2010

Table 7.13 Cost calculation for parapet walls Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet)

(SLR) 05 161+220-RHS 200 200 40,000.00 05 163+102-RHS 150 216 32,400.00 05 164+160-LHS 200 120 24,000.00 05 171+170-LHS 150 300 45,000.00 06 193+773- LHS 150 300 45,000.00 06 197+200-LHS 200 430 86,000.00 06 197+240-LHS 250 645 161,250.00 06 197+340-LHS 200 215 43,000.00 06 197+370-LHS 250 129 32,250.00 06 197+380-LHS 200 107 21,400.00 06 197+390-LHS 250 1679 419,750.00

99 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------06 197+430-LHS 300 107 32,100.00 06 197+480-LHS 300 1219 365,700.00 06 197+650-LHS 250 215 53,750.00 06 197+760-LHS 250 64 16,000.00 06 197+780-LHS 250 215 53,750.00 06 197+800-LHS 200 430 86,000.00 06 197+820-LHS 200 150 30,000.00 06 197+840-LHS 200 107 21,400.00 06 197+860-LHS 250 968 242,000.00 06 197+868-LHS 100 150 15,000.00 06 197+890-LHS 100 129 12,900.00 06 197+895-LHS 150 32 4,800.00 06 198+120-LHS 250 32 8,000.00 06 198+200-LHS 250 538 134,500.00 06 198+300-LHS 250 2906 726,500.00 06 198+325-LHS 250 645 161,250.00 06 198+350-LHS 250 667 166,750.00 06 198+370-LHS 300 516 154,800.00 06 198+385-LHS 250 355 88,750.00 06 198+400-LHS 250 258 64,500.00 06 198+420-LHS 200 322 64,400.00 06 198+440-LHS 200 129 25,800.00 06 198+489-LHS 250 1270 317,500.00 06 198+540-LHS 250 645 161,250.00 06 198+620-LHS 250 1959 489,750.00 06 198+680-LHS 200 861 172,200.00 06 198+740-LHS 250 731 182,750.00 06 198+812-LHS 250 2152 538,000.00 06 198+835-LHS 200 645 129,000.00 06 198+850-LHS 200 861 172,200.00 06 198+880-LHS 200 215 43,000.00 06 198+888-LHS 200 861 172,200.00 06 198+920-LHS 250 226 56,500.00 06 198+940-LHS 250 538 134,500.00 06 199+000-LHS 200 1291 258,200.00 06 199+080-LHS 250 322 80,500.00 06 199+145-LHS 250 1184 296,000.00 06 199+180-LHS 250 645 161,250.00 06 199+200-LHS 250 322 80,500.00 06 199+210-LHS 300 215 64,500.0 06 199+220-LHS 300 86 25,800.00 06 199+230-LHS 200 107 21,400.00 06 199+240-LHS 250 430 107,500.00 06 199+260-LHS 250 430 107,500.00 06 197+380-RHS 250 430 107,500.00

100 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------06 197+385-RHS 250 210 525,00.00 06 197+405-RHS 250 160 40,000.00 06 197+412-RHS 250 200 50,000.00 06 197+416-RHS 250 210 50,000.00 06 197+420-RHS 250 140 35,000.00 06 197+500-RHS 250 645 161,250.00 06 197+840-RHS 250 139 34,750.00 Total 7,729,725.00 Source- social survey for RAP, 2010

Table 7.14 Cost calculation for front walls / roof extensions of business places Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet) (SLR) 05 164+300-RHS 150 72 10,800.00 05 167+195-RHS 270 200 54,000.00 05 167+240 -RHS 250 200 50,000.00 05 167+ 220-RHS 250 250 62,500.00 05 167+230-RHS 200 300 60,000.00 05 169+408-LHS 150 210 31,500.00 05 175+370-RHS 150 180 27,000.00 05 175+350 RHS 150 75 11,250.00 06 191+535-RHS 150 270 40,500.00 06 193+773- LHS 150 250 37,250.00 06 195+320-LHS 150 135 20,250.00 06 195+325-LHS 150 135 20,250.00 06 195+337-LHS 150 108 16,200.00 06 195+342-LHS 150 135 20,250.00 06 197+800-LHS 150 125 18,750.00 06 197+820-LHS 150 140 21,000.00 06 197+840-LHS 150 125 18,750.00 06 197+898-LHS 150 125 18,750.00 Total 539,000.00 Source- social survey for RAP, 2010

Table 7.15 Cost calculation for permanent sales huts Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet) (SLR) 05 163+200-LHS 200 40 8,000.00 05 165+030-RHS 250 25 6,250.00 05 165+120-LHS 200 55 11,000.00 06 190+210-RHS 200 60 12,000.00 06 192+050-RHS 250 49 12,250.00 06 192+310-RHS 250 50 12,500.00 Total 62,200.00

101 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------Source- social survey for RAP, 2010

Table 7.16 Cost calculation for Affected permanent fences (iron poles with concrete columns etc.) Package Chainage Unit No. of units Total Cost (SLR) (km) price (Square feet) (SLR) 06 198+740-L HS 250 1072 268,000.00 Total 268,000.00

Table 7.17 Cost calculation for Lands Package Chainage Extent (m2) Ownership Remarks Total Cost (km) (SLR) 05 173+685km- 150m2 Government The land will - LHS (06 perch) (Police Post) be transferred to RDA 06 183+960km 250m2 (Government) The land has - (10 perch) Port to be Authority transferred to land the RDA 06 186+280km- 100m2 Government The land will - RHS (04 perch) (SL. Army) be transferred to RDA Source- social survey for RAP, 2010

7.7 Cost for affected trees.

The calculation of cost is done on the basis of guidelines and methodology discussed in chapter 05 of this report. There are 33 privately owned trees to be removed. Out of them 16 trees are timber trees while 17 trees are fruits trees. To calculate the value (table 7.18) of the trees the Project seeks assistance from the Agricultural Service Research Development Officer and Range Forest Officer of the area. The following factors will be considered for in the valuation process.

Present market value of timber Demand and current price of fruits. The life time of the trees The present age of the trees and Potential for productivity.

102 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

Table 7.18 Cost calculation for affected trees as per designs Road section Number of Method of costing Total Cost (SLR.) Trees Kanthale-Trincomalee Fruit trees – 17 Number of potential 340,000.00 road section years 10, annual income SLR. 2000.00

Timber trees- 16 Timber value at market 320,000.00 price, each tree is SLR. 20,000.00

Total 660,000.00 Source- social survey for RAP, 2010

Cost for public awareness programmes.

One public awareness program will be conducted in each package. Cost for 01 programme SLR. 50,000.00

Social safeguards training programmes-

Social safeguards training programmes will be conducted for RDA regional officers/ PMU Project engineers / Consultant/ Divisional secretaries and relevant GOVT. Officers of the area.

One training programmes will be conducted in each package Cost for 01 programme = SLR. 100,000.00

Cost for HIV/AIDS programmes ( in each package).

Provisional sum per package SLR. 700,000.00

Cost for monitoring and evaluation of social safeguards including GRM

Cost of M&E of social safeguards and implementation of GRM Cost for one package SLR. 250,000.00

Provision of additional structures (Based on requests, complaints received by the community or Institutes to improve safety) Cost for one package = SLR.1,000,000.00

103 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------

7.8 Budget for mitigation of social impacts for each package

Cost for implementing the social impacts mitigation measures for each package is given as follows.

Table 7.18A - Cost calculation for Package 05 Table 7.18B - Cost calculation for Package 06

Total Cost for Mitigation of Negative Social Impacts for Package 05 Table 7.18A Total Cost for Social Mitigation Measures Item Cost – SLR. Front walls of houses and other buildings 0 Cement floors/cement steps of business places 0 Gates 90,000.00 Parapet walls 101,400.00 Shifting of permanent fences (Iron poles with concrete 0 columns) Front walls/roof extensions of business places 117,450.00 Permanent Sales Huts 25,250.00 Cost for removal of Trees 320,000.00 Cost for lands 0 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00 HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 2,754,100.00 Source- social survey for RAP, 2010

This estimate is prepared on the basis of information obtained by the RDA.

Total Cost for Mitigation of Negative Social Impacts for Package 06 Table 7.18B Total Cost for Social Mitigation Measures Item Cost – SLR. Front walls of houses and other buildings 1,403,775.00 Cement floors/cement steps of business places 8,100.00 Gates 615,750.00 Parapet walls 7,628,325.00 Shifting of permanent fences (Iron poles with concrete 268,000.00 columns) Front walls/roof extensions of business places 421,550.00 Permanent Sales Huts 36,750.00 Cost for removal of Trees 340,000.00 Cost for lands 0 Public awareness and trainings 50,000.00 Social safeguards training programmes 100,000.00

104 Resettlement Action Plan for Road Sector Assistance Project II, August, 2010

------HIV/AIDS programs 700,000.00 M&E and Implementation of GRM 250,000.00 Providing additional structures for community on 1,000,000.00 requests for safety or infrastructure development.* Total 12,822,250.00 Source- social survey for RAP, 2010

List of Reference

Arjuna Consulting Co Ltd, 1997, Arjun’s Atlas of Sri Lanka, Arjuna Consulting Co Ltd, 60, School Avenue, Dhiwala, Sri Lanka. Bureau of South and Central Asian Affairs—World Bank October 2006 Case studies on Social impact on 16 candidate roads of Road Sector Assistance Project, Volume II, 3rd October 2005 Central Bank of Sri Lanka, 2009, Annual Report – 2008, Central Bank of Sri Lanka, 30, President Avenue, Colombo, 01. Connecting Growth: Sri Lanka’s poverty Reducing Strategy, Government of Sri Cook, L.C. 1953, Geography of Ceylon, Department of Census & Statistics – Sri Lanka ,June 2006 Related Acts and Legal documents, Government of Sri Lanka. Related published and unpublished reports of RDA, Sri Lanka. Resettlement Plan of World Bank Funded Road Sector Assistance Project – December 2008. Study of Center of Economic and Policy Research Survey Department of Sri Lanka, 2007, The National Atlas of Sri Lanka, 2nd ed. Survey Department of Sri Lanka.

Web addresses

http://www.internal-displacement.org/ http://www.rda.gov.lk/ www.statistics.gov.lk

105 1

Annex 01

Preparation of Social Assessments and Resettlement Action plan for Road Sector Assistance project – II Field study on Socio – Economic Impacts of road rehabilitation project

Road Sector: 1. Kantale – Trincomalee 2. Ambepussa – Habarana

Field Supervisor : ………………Field Assi.:...... Date:……/……/2010

1. Personal Information on affecter

1.1. Address: ……………………………………………………………. ……………………………………………………………………………. 1.2. Nationality : Sri Lankan/Other 1.3. Race : 1. Sinhalese 2. Tamils 3. Muslims 4. Others 1.4. Are you a recipient: Samurdi/ Other – Pin-padi/……………. 2.0. Family Information

Employment

HH

Y

- hip

to Position Sector

Relations

Age Education Level Health Problem Expenditu re/M (SLR) Monthly Income (SLR) / Job Go/Pri/Self HH W/M Wif Hus S D S D S D S D

2.1. Total family income per month –Rs :…………………………………….

2

3.0. General Information of the affected Structure: House/Business Place/……… (School/Temple/Church/ Administration/ other) Specify

Over all Dimension (m) Infrastructure Utilities Other Assets state ……. * ….. Facilities Water (Well, pip Vehicle No. of borne , other) TV (car, van, bus, Poor rooms (C/B&W) truck)

Roof Telephone Refrigerator M. bicycle Middle ( Made of) ( G / HP, Both) F. Bicycle income

Walls Electricity Computer Three wheeler Moderate (M of)

Floor Furniture Internet faci. Annexure Rich (G/Bad) House/Build. Toilets Machine Set ups Richest

3.1. Remarks or Comments: ……………………………………………………………………………………………… ……………………………………………………………………………………………… ………………………………………………………………………………………………

4.0. Information on affected Structure

4.1. Sketch of the affected structure

LHS

From …. To…….

……………………………

4.1. Structure: LHS/RHS 4.2. Ownership: Private/Rent/Govern……. RHS 3

4.2. Description of affected structure

Affected to Affected Value of Lost made due to Other Suggestion to reduce dimension affected destruction –p/d expected loss (m) structure bad effects Entire ……..

Part of……..

Wall

Gate

Fence

Parapet

Door’s step

5.0. Expected consequences during rehabilitation the effected structure

Description Description

1 Loss of livelihood

2 No of family members affected

3 Financial loss –p/d (SLR)

4 Any other comments

4

5.1. Means that can be suggested to overcome related issues.

Problems for Yes No Financial Remarks Loss 1 Education 2 Health 3 Transportation 4 Mental health 5 Ritual 6 Leisure time 7 other

6.0. Other problems that not mentioned above

Annex 02

Field Survey on preparation of Social Assessment and Resettlement Action Plan for Road Sector Assistance Project – II

Road Sectors: Ambepussa – Dambulla and Kantele – Trincomalee – A006

Field Supervisor:………………….. Field Assi…………………… Date: ……/ …/2010

Subject area of inquiry Matter of inquiry Opinion

1. Public awareness about this 1. Do you aware about this road rehabilitation Yes No project project? 2. If, yes, what is the width of the proposed road? ….m …m

II. Expected outcome after 3. Travel time ( Reduce/Increase) R I completing this project 4. Traveling cost R I 5. Personal/family income R I 6. New income sources R I 7. Connections with new region/individuals R I 8. Road accidents R I 9. Theft R I 10. Land price R I 11. Migrants to your area R I

III. Consequent result of the 12. Traffic conjunction R I project during construction 13. Other travel problems R I period 14. Dust, noise etc. problems R I 15. Income of the area R I

IV. What is your opinion …………………………………………………………………… regarding improvement of …………………………………………………………………… transportation facilities after …………………………………………………………………… completing this project? …………………………………………………………………… Comment. ……………………………………………………… Information of the responder: Name: - ……………………………………. Job/profession: -…………………………… Postal Address:……………………………………….. ………………………………………….. ………………………………………….

Annex 03

Table 01

Main Administrative Divisions/ zones in Sri Lanka

Main zone - Province Secondary- District Other divisions/ Names Kilinochchi North/ Northern plains/ Vanniya/ Northern Mannar Northern coastal plains Mulative Mannar Vauniya Anuradhapura North Central Polonnaruwa Raja Rata/ Central Plains Trincomalee Eastern Batticola Eastern Coast/ Eastern Ampara coastal plains Puttalam North Western Kurunagala Wayamba/ North Western plains/coastal plains Kandy Central Nuwaraeliya Central Hills/ Upcountry Matale Gampha Western Colombo Low country/ Coastal peniplains Kalutara Kegalle Upcountry Sabaragamuwa Rathnaputa Galle Low country/ coastal peniplains Southern Matara /South/ Ruhunu Rata Hambantota Badulla Uva Monaragala Uva Basin

(* Project province/ districts are in italic words)

Annex 03 – Table 02

Number of Administrative Units Province Districts DSD1 GND2 Villages Northern 5 32 919 2,221 North Central 2 24 985 3,774 Eastern 3 39 1072 2158 North Western 2 33 2158 5719 Central 3 33 2187 5736 Western 3 34 2500 5309 Sabaragamuwa 2 24 1152 3618 Southern 3 37 2159 5228 Uva 2 24 851 3427 Total 25 280 13983 37300 1- Divisional Secretariat Division. 2. Grama Niladhari Division ( Village officer division)

Annex 04. Profile of the Project Affected People

Table A. 1 - Total population and Number of PAP Families .

Road # of persons in PAP Families affected families

Ambepussa - Dambulla road section (A006) 672 297 Kanthale – Trincomalee road section (A006) 427 110 Total 1099 407 Source- Social Survey for RAP, 2010

Table A.2 - Gender Diversity of PAP Families

Road Female Male Total Population Ambepussa – Dambulla road section 352 320 672 Kanthale – Trincomalee road section 210 217 427 Total Population 562 537 1099 Source- Social Survey for RAP, 2010

Table A.3. - Population by Age Groups

Ambepussa- Habarana road Kanthale-Trinco road Age group Years section section 0 -5 91 52 06 -16 98 88 17 -26 103 57 27 -36 193 86 37 - 46 77 50 47 - 56 51 49 57 -66 43 32 67 > 16 13 Total 672 427 Source- Social Survey for RAP, 2010

Education Level of PAP

Education Level Number of persons

 No formal Education: - 118  Education between grade 1 to 5:- 210  Education between grades 6 to 10:- 280  Education Ordinary Level (O/L):- 245  Education Advance Level (A/L):- 180  University/other higher levels: – 14  Not attending to school 52 TOTAL 1099

Income Level

Table A.4 Monthly income level of the PAP families Kanthale – Monthly income(Rs.) No of % Trincomalee % families Road Ambepussa – section Dambulla Road section < 5000 145 49 178 41 5001 – 10,000 85 28 147 34 10,001 – 20,000 36 12 76 18 20,001 – 30,000 20 7 17 5 More than 30, 000 11 4 9 2 Source- Social Survey for RAP, 2010

Table A.5 - The occupation/employments of PAP families Ambepussa-Dambulla Road Kanthale-Trincomalee Road Section section Employment Govern Sector Government Private Self ment Private Self Executive 07 08 Teaching 10 6 Laborer 14 20 Helper 02 7 Business 184 61 Defense 21 6 Farmers 38 35 Other 21 64 Source- Social Survey for RAP, 2010

Table A.6 Number of Samurdhi Recipient families - (National poverty alleviation programme) Road section Sinhala Tamil Muslim Ambepussa-Dambulla road section 14 9 6 Kanthale-Trincomalee road section 6 1 1 Source- Social Survey for RAP, 2010

Table A.7 Type and Number of families that have access to Infrastructure Facilities Facilities Ambepussa- Kanthale- Dambulla road Trincomalee section road section Pipe water facility 198 52 Drinking water wells 103 45 Access to stream water sources 19 5 Water sealed latrine/Toilets 269 73 Telephone facilities 254 83 Electricity connections 279 92 Source- social survey for RAP, 2010

Annex 05

(Plate 6.1)Project affected front part of a house at Ambepussa junction

Plate 6.2 Project affected temporary maize stall at Ambepussa junction

Plate 6.3 Project affected temporary short – eats stall at Pothuhara

Annex 06A Affected Properties (Ambepussa – Dambulla Road Section)

Table 1. Affected front walls of houses (Ambepussa – Dambulla Road Section)

No. Name of Address Affected Size Affected Size Affectee Property property (Square feet) (Household (Squire feet) For 19m Head) As per designs corridor

Package 01 – (00km-23.00km)

S.P. Mahinda 23/2 Kurunegala Road Front wall 90 - - 1 perera , Allawwa of house

Front wall R.M.S. 10A/ Kurunegala 112 - - 2 Premarathne Road, Alawwa of house

23/ Dambulla Road, Front wall 125 - - 3 P.M. Nazeem Morugama of house

Package 02 – (23.00km-47.00km)

Front wall P.P. Nimal 82a, Kurunegala Road, 52 - - 4 surendra Pothuhera of house

Front wall Sunitha Wadugedara, 65 - - 5 Ranasinghe Dambokka of house

Front wall Dambulla Road, 67 - - 6 K.M. Bandara Boyagane of house

Package 04 – (69.00km-90.00km)

Front wall 89 - - 7 R.P. Nimalsiri 12, Suraj, Galewela of house

Front wall 73 - - 8 P.M. Nazeer 23/2 Galewela of house

Front wall A.C. 123 - - 9 Paranamana Nizam Place, Galewla of house

A.P.N. Front wall 46 - - 10 Mariyasinghe 45, Galewela of house

Front wall 145 - - 11 A.P.D. Upatissa Sapna, Kanadana of house Front wall C.N. Sandya place, 105 - - 12 Amarasuriya Melsiripura of house

B.M. 10/2, Dambulla Road, Front wall 87 - - 13 Soriyasinghe Gokerella of house

Front wall 26/b, Dambulla Road, 95 - - 14 P.M. Cassim Galewela of house

18/2, Dambulla Road, Front wall 106 - - 15 M.M. Naeem Galewela of house

Front wall W.S. 123B, Dambulla Road, 93 - - 16 Udubaddawa Galewela of houses

(The details may change once the designs are finalized)

Table 2 Affected cement floors/concrete steps of business places/ Concrete steps (Ambepussa – Dambulla Road Section)

No. Name of Address Affected Size Affected Size Affectee Property Property (Square feet) (Square feet) (Household For 19 Head) As per designs corridor

Package 01 – (00km-23.00km)

R.I. Manamperi 45,Kahatawatte Cement floor Cement floor 1 18+450-RHS Polgahawela /Concrete steps 19 /Concrete steps 12

Saman Piyarathne Kumara Nivasa, Cement floor Cement floor 2 21+495-RHS Ambepussa /Concrete steps 22 /Concrete steps 15

Package 02 – (23.00km-47.00km)

Athula Ranjeewa 102a, Dambulla Cement floor Cement floor 3 23+445-RHS Road, Kuripotha /Concrete steps 30 /Concrete steps 25

Amara Cement floor 25 Cement floor 18 Piyarathne /Concrete steps /Concrete steps 5B, Dambulla Road, 4 25+100-LHS Kuripotha, Kavina Abans Shop, 24, Cement floor 21 - - 5 Senanayake Pothuhera /Concrete steps

Mod Seen, Cement floor 12 - - 6 S.M. Nizam Pothuhera /Concrete steps

A.P. Piyadasa Cement floor 55 Cement floor 30 109, Prince /Concrete steps /Concrete steps 7 27+100-RHS Fashion,Pothuhera

345d, Zee Fashion, Cement floor 8 - - 8 Eric Upasena Kurunegala /Concrete steps

National Hardware, Cement floor 23 - - Dambulla Rd, /Concrete steps 9 W.M. Kollure Kurunegala

Nalin 234, Indrani Hotel, Cement floor 10 - - 10 Mahadivulwewa Kurunegala /Concrete steps

Unique Motors, Cement floor 12 - - 11 P. Ramaiya Kurunegala /Concrete steps

M.R. Sirinawathi Madushani Text, Cement floor Cement floor 12 31+700-RHS 204, Kurunegala /Concrete steps 60 /Concrete steps 30

Computer Training Cement floor 12 - - Center, 32, /Concrete steps 13 Nuwan Pradeep Kurunegala

Madeena Textile, Cement floor 20 - - 14 A.M.H. Iquebal Kurunegala /Concrete steps

N.S. Sukumara Cement floor 45 Cement floor 25 Anura Bag Center, /Concrete steps /Concrete steps 15 32+620-LHS 280, Kurunegala

Saloon Travo, Cement floor 15 - - 16 P.M. anasena Kurunegala /Concrete steps

Regal Motors, Cement floor 18 - - Dambulla Road, /Concrete steps 17 A.P. Basnayake Kurunegala

A.M.P. New Impala Hotel, Cement floor 10 - - 18 Abeywickrama 43, Kurunegala /Concrete steps

Ariyasiri wanasinghe 12, MF Traders, Cement floor Cement floor 19 33+060-LHS Boyagane /Concrete steps 70 /Concrete steps 40

M. P. 31c, Asian Grocery, Cement floor 15.5 - - 20 Karunadasa Boyagane /Concrete steps

DSI Foot Wear, Cement floor 14 - 21 P.S. Kodikara Boyagane /Concrete steps City Shoe Palace, Cement floor 16 - - 222 P.M. Azis Ali 47B, Boyagane /Concrete steps

Egodawatte Wine Cement floor 10 - - 23 P. Balasooriya Stores, Boyagane /Concrete steps

P.M. Husen Cement floor 35 Cement floor 25 18, Huzen Grinding /Concrete steps /Concrete steps 24 34+605-LHS Mills, Boyagane

New Meesath Stors, Cement floor 19 - - 25 B.M. Kadir Boyagane /Concrete steps

109, Nissan Stores, Cement floor 13 - - 26 W.K. Piyasinghe Boyagane /Concrete steps

New Kandy Stores, Cement floor 18 - - 27 G.M Rathnasiri Boyagane /Concrete steps

Nissam Text, 76, Cement floor 9 - - 28 P.K. Nissam Boyagane /Concrete steps

P. Abdulla Cement floor 16 Cement floor 30 Royal Jewelers, /Concrete steps /Concrete steps 29 39+760-LHS Boyagane

S.P. Memart Studio, 54, Cement floor 12 - - 30 Kumaradasa Ibbagamuwa /Concrete steps

S.M. Cassim Cement floor 50 Cement floor 30 New Saudiyas, 76a, /Concrete steps /Concrete steps 31 46+550-LHS Ibbagamuwa

Mesam Gold Stores, Cement floor 03 - - 32 S.M. Mohomed 67A, Melsiripura /Concrete steps

Saras Bag Centre, Cement floor 03 - - 33 V.P. Kumari 87C, Melsiripura /Concrete steps

New Citizen Watch Cement floor 3.5 - - M.P. Center, 7B, /Concrete steps 34 wasudivakara Melsiripura

Package 03 – (47.00km-6953+270-RHS.00km)

A.N. saumyasiri 31C, Mangala Cement floor 60 Cement floor 40 Studio, Dambulla /Concrete steps /Concrete steps 35 53+270-RHS Road, Melsiripura

S.P. Seram Lanka Tiles, 12, Cement floor 30 Cement floor 18 Dambulla Road, /Concrete steps /Concrete steps 36 58+800-LHS Melsiripura

16c, Thushara Cement floor 4 - - 37 M.N. Sirimewan Caffe,Gokerella /Concrete steps

Cement floor 21 - - New Dispensary, /Concrete steps 38 R.M.P.Gayanath Gokerella P.L. Alponsu Brown Tractors, 32A, Cement floor 50 Cement floor 35 Dambulla Rd, /Concrete steps /Concrete steps 39 60+620-RHS Gokerella

W.M. Cement floor 62 Cement floor 20 Wimalasundara /Concrete steps /Concrete steps 67c, Fancy Mahal, 40 61+500-LHS Gokerella

Package 04 – (69.00km-90.00km)

W.Y. Imitias Cement floor 34 Cement floor 20 Modern Text, 87a, /Concrete steps /Concrete steps 41 73+800-RHS Galewela

S.M. Haneepa Cement floor 30 Cement floor 25 90B, Bhathiya /Concrete steps /Concrete steps 42 73+950-RHS Motors,Galewela

244, Bhathiya Cement floor 4 - - 43 R.P.S. Ganga Moters, Gale45wela /Concrete steps

Sharas46 Gift Cement floor 8 - - 44 N.P. Namal Center, Galewela /Concrete steps

M.M. Musaddeen Lanka Je47welers, Cement floor Cement floor 45 74+060-LHS Galewela /Concrete steps 45 /Concrete steps 30

P.M. Sompala Cement floor 40 Cement floor 32 Savindu St48ores, /Concrete steps /Concrete steps 46 74+080-LHS Galewela

M.S. Adeena Cement floor 45 Cement floor 35 Safeena Stor49es, /Concrete steps /Concrete steps 47 74+100-RHS Galewela

S.W. Wishmi Cement floor 62 Cement floor 40 Hyath Shoe /Concrete steps /Concrete steps 48 74+110-LHS Ce50nter, Galewela

Dialog Cement floor 5 - - Communication, /Concrete steps 49 M.P. Rangith Galewela

Hamidia Electronics, Cement floor 8 - - 50 S.M. Manis Galewela /Concrete steps

Royal Tiles Center, Cement floor 3.5 - 51 B.M. Podihami Galewela /Concrete steps

M.P. Sabasinghe Cement floor 52 Cement floor 40 Dress Point, /Concrete steps /Concrete steps 52 74+115-LHS Galewela

S.M. Wimal Hotel, Cement floor 12 - - 53 Sathurusinghe Galewela /Concrete steps A.P. Amarasiri Cement floor 25 Cement floor 18 Brown Electronics, /Concrete steps /Concrete steps 54 74+125-LHS Galewela

Kareem Watch Cement floor 4 - - 55 S.M. Kareen Center, Galewela /Concrete steps

Brown Gold, Cement floor 4 - 56 S. Somasiri Galewela /Concrete steps

D.S. Amarasiri Cement floor 45 Cement floor 30 Dress Point, /Concrete steps /Concrete steps 57 74+250-RHS Galewela

Govindu Electronics, Cement floor 6.5 - - 58 S.M. Niyas Galwewla /Concrete steps

Maliban Hotel, Cement floor 4 - - 59 B.P. Asiri Galewela /Concrete steps

Fancy Center, Cement floor 4 - - 60 A.s. Sawsiri Galewela /Concrete steps

Deem Stores, Cement floor 3 - - 61 W.H. Hasith Galewela /Concrete steps

S.M. Gamini Rathna Cement floor 3 - 62 Gaminirathna Pharmacy, Galewela /Concrete steps

H.M. Asheez Cement floor 26 Cement floor 15 Ruwanpura Gold, /Concrete steps /Concrete steps 63 74+260-LHS Galewela

New Kumara Text, Cement floor 7.5 - - 64 S.A. Amal Galewela /Concrete steps

Madushika Traders, Cement floor 18 - - 65 S.P. Madushika Galewela /Concrete steps

A.P. Kamal Cement floor 22 Cement floor 15 Paper Centre, /Concrete steps /Concrete steps 66 74+350-RHS Galewela

New Akeem Stores, Cement floor 14 - - 67 A.M. Navas Galewela /Concrete steps

T.H. Mobile Center, Cement floor 20 - - 68 T.H. Balasuriya Galewela /Concrete steps

Fashion Lovers, Cement floor 14 - - 69 R.p. Punchihewa Galewela /Concrete steps

W.Y. Sirisena Cement floor 46 Cement floor 25 Shamali Grocery, /Concrete steps /Concrete steps 70 74+400-RHS Galewela

S.M. Liyanage Cement floor 42 Cement floor 15 Galewela New /Concrete steps /Concrete steps 71 74+410-RHS Pharmacy, Galewela New Lucky Cement floor 17 - - 72 C.S. Buddhika Pharmacy, Galewela /Concrete steps

Araliya Cement floor 16 - - C.P. Communication, /Concrete steps 73 Amarasinghe Galewela

S.T. Palitha Cement floor 30 Cement floor 20 Induruwa Grocery , /Concrete steps /Concrete steps 74 74+415-RHS Galewela

Sarasavi Opticles, Cement floor 12 - - 75 N. Silva Galewela /Concrete steps

Manahara Book Cement floor 18 - - 76 S.M. Najeeb Center, Galewela /Concrete steps

Unique Travels, Cement floor 7 - - 77 A.M. Mahasena Galewela /Concrete steps

A.P. Sirimewan Cement floor 35 Cement floor 25 Sirimewan Hotel, /Concrete steps /Concrete steps 78 74+505-LHS Galewela

Hotel Sirimedura, Cement floor 21 - - 79 A.m. kamalini Galewela /Concrete steps

A.M. Athif Atheif Stores, Cement floor 44 Cement floor 25 80 74+518-RHS Galewela /Concrete steps /Concrete steps

SAMS Cement floor 5 - - Communication, /Concrete steps 81 A.N. Nimalasiri Galewela

Muslim Hotel, Cement floor 6.5 - - 82 H.M. Kareem Galewela /Concrete steps

S.P. Sandamal Sandamal Cement floor 43 Cement floor 28 Communication, /Concrete steps /Concrete steps 83 74+600-LHS Galewela

O.P. Kaushalya Hotel, Cement floor 5 - - 84 Senanayake Galewela /Concrete steps

Sandamali Grocery, Cement floor 6.5 - - 85 S.M. Ashoka 21C, Galewela /Concrete steps

W.D. Chandra Cement floor 47 Cement floor 35 Nilma Grocery, 34, /Concrete steps /Concrete steps 86 74+620-RHS Galewela

Tyre House, 10c, Cement floor 7 - - 87 W.Senabadu Galewela /Concrete steps

Avishka Stores, Cement floor 8.5 - - 88 E.P. Kankasena Galewela /Concrete steps

R.M. Rathnapala Suranga Stores, 31, Cement floor 50 Cement floor 30 89 74+700-RHS Galewela /Concrete steps /Concrete steps Mohomed Grocery, Cement floor 4 - - 90 T.M. Ramayia 45, Galewela /Concrete steps

Ranjith Hotel, Cement floor 5 - - 91 R.Ranjith Galewela /Concrete steps

New Nanda Stores, Cement floor 8 - 92 N. P. Hassantha Galewela /Concrete steps

S.P. Marasinghe 22. Saman House, Cement floor 32 Cement floor 25 93 74+710-LHS Galewela /Concrete steps /Concrete steps

Cement floor 15 - - 94 M.B. Pathirana New Road, Galewela /Concrete steps

S.D. Munasnghe Cement floor 40 Cement floor 30 /Concrete steps /Concrete steps 95 74+720-RHS 32/4, 1st Galewela

Srinath Road, Cement floor 5 - - 96 G.M. Jayalath Galewela /Concrete steps

S.P. 12, Damulla Road , Cement floor 1.5 - - 97 Dissanayake Habarana /Concrete steps

K.M. Senanayaka Cement floor 6 - - 98 Liyanaarachchi Mawatha, Galewela /Concrete steps

N.C. Perera Cement floor 63 Cement floor 18 Gamagewatth, /Concrete steps /Concrete steps 99 74+780-LHS Galewela

Ramya Palace, Cement floor 7 - - 100 N.L. Karunasiri Galewela /Concrete steps

w.Y. Perera Cement floor 37 Cement floor 15 101 74+785-RHS 12C, Galewela /Concrete steps /Concrete steps

Cement floor 3 - - 102 M. Sunil New Hotel, Galewela /Concrete steps

Cement floor 22 - - 103 M.V. Buddhika 2nd Street, Galewela /Concrete steps

st 123, 1 Lane, Cement floor 60 Cement floor 20 104 C.M. Pathrathne Galewela /Concrete steps /Concrete steps

N.C. Kamal 23, Jaliyapura, Cement floor 40 Cement floor 20 105 74+800-LHS Galewela /Concrete steps /Concrete steps

12, Main road, Cement floor 25 - - 106 L.P. Dharmasiri Allawwwa /Concrete steps

B. Stanley Kumara Vasa, Cement floor 50 Cement floor 32 107 76+302-RHS Galewela /Concrete steps /Concrete steps

Q.P. Nayanasir 12, Station Road, Cement floor 40 Cement floor 18 108 76+400-LHS Galewela /Concrete steps /Concrete steps 10, Oruwala Road. Cement floor 4.5 - - 109 L.P. Chandrasiri Dambulla /Concrete steps

New Road, Cement floor 6 - - 110 P.S. Bandupala Omaragolla /Concrete steps

w.s. Kumara Temple Lane, Cement floor 38 Cement floor 20 111 80+230-RHS Dambulla /Concrete steps /Concrete steps

P.L. Waduge Cement floor 35 Cement floor 15 112 88+400-LHS 104 , Dambulla /Concrete steps /Concrete steps

23/1142, Dambulla Cement floor 3 - - 113 L.S. Basnayake Road, Dambulla /Concrete steps

N.B. Bandula Polonnaruw116a Cement floor 40 Cement floor 22 114 88+560-LHS Road, Dambulla /Concrete steps /Concrete steps

32/3, Dambulla Cement floor 23 - - 115 P.L. Jayasiri /Concrete steps

st 1 Lane, Dambulla Cement floor 12 - - 116 O.P. Malik /Concrete steps

Habarana Rest Cement floor 3 - - 117 B.C. Bandula House, Dambulla /Concrete steps

69, Dambulla Road, Cement floor 20 - - 118 M.M. Malik Dambulla /Concrete steps

Polonnaruwa Road, Cement floor 7 - - 119 S.D. Danawansa Dambulla /Concrete steps

88, Dambulla Road, Cement floor 10 - - 120 O.P. Madhuka Dambulla /Concrete steps

Temple Junction, Cement floor 13 - - 121 S.L. Jinapala Dambulla /Concrete steps

E.M. 73/2, Dambulla Cement floor 15 - - 122 Jayasumana Road, Dambulla /Concrete steps

Polonnaruwa Road, Cement floor 5 - - 123 N.C. Nilmini Dambulla /Concrete steps

238, Dambulla Road, Cement floor 8 - - 124 P.K. Nayomi Dambulla /Concrete steps

111 C, Dambulla Cement floor 12 - - 125 A.s. Nimal /Concrete steps

221 Kemburana, Cement floor 7 - - 126 N.P. Mallika Dambulla /Concrete steps

16, Dambulla Cement floor 5 - - 127 G.M. Lalkumara /Concrete steps

C/o Silva Stores, Cement floor 4.5 - - Akkara Panaha, /Concrete steps 128 M.V. Vismi Melsiripura Mukalanyaya, Cement floor 7 - - 129 B.K.L. Asunamal Dambulla /Concrete steps

5 A, Potuhera, Cement floor 3.5 - - 130 A.N. Lakmali Dambulla /Concrete steps

(The details may change once the designs are finalized)

Table 3 Affected Concrete/cement steps of public places (Ambepussa – Dambulla Road Section)

No. Name of Address Affected Property Size Affected Size Affectee Property (Square (Square feet) (Household For 19m corridor feet) As per Head) designs

Package 02 – (23.00km-47.00km)

Concrete/cement 15 - - Irrigation 1 Department, Pothuhera steps

Concrete/cement 10 - - Irrigation 2 department Boyagane steps

Concrete/cement 19 - - Agrarian Service 3 Department Kurunegala steps

Package 04 – (69.00km-90.00km)

Agrarian Concrete/cement 10 - - Services 4 Departmant Kanadana steps

Concrete/cement 14 - - Mahaweli 5 Authority Kanadana steps

Concrete/cement 8 - -

6 MOH, Office Galewela steps

Concrete/cement 12 - -

7 NLDB Sri Lanka Galewela steps

Concrete/cement 10 - -

8 Sub post office Galewela steps

Concrete/cement 6 - - Youth 9 foundation Galewela steps (The details may change once the designs are finalized)

Table 4 Affected permanent Fences (iron poles with concrete columns) (Ambepussa – Dambulla Road Section)

No. Name of Address Affected Size Affected Size Affectee Property Property ( Square feet) ( Square feet) (Household For 19 corridor As per designs Head)

Package 02 – (00.00km-23.00km)

T.S. Rathkarawa, Iron fence with 200 Iron fence with 200 Bandumathi Pothuhera concrete poles concrete poles 1 25+100-RHS

Wewagedara, S.D. Gamage Iron fence with 270 Iron fence with 270 Pothuhera 2 25+320-LHS concrete poles concrete poles

Asiri Rest, Q.S. Samngiri Iron fence with 180 Iron fence with 180 Pothuhera 3 29+940-RHS concrete poles concrete poles

5 A, Potuhera, A.N. Lakmali Iron fence with 230 Iron fence with 230 4 30+520-RHS concrete poles concrete poles

P.T. 57/2, Akura, Iron fence with 250 Iron fence with 250 Amarasekera Boyagane concrete poles concrete poles 5 31+560-LHS

Sir John Iron fence with 300 Iron fence with 300 Kotalawala concrete poles concrete poles A.M. Marihami MV, 6 32+000-LHS Kurunegala

General Iron fence with 250 - - T.L. Hospital, concrete poles 7 Kanakasinghe Kurunegala

70B, Uhumiya, Iron fence with 200 - - Kurunegala 8 D.M. Somasiri concrete poles

Package 04 – (69.00km-90.00km)

26/2, Galewela Y.T. Lekha Iron fence with 360 Iron fence with 360 9 74+000-LHS concrete poles concrete poles

18, Main Road, Iron fence with 270 - - Galewela 10 L.M. Namalsiri concrete poles

Girambe, Iron fence with 230 - - Galewela 11 Kapila Kumara concrete poles (The details may change once the designs are finalized)

Table 5 Affected Gates (Ambepussa – Dambulla Road Section)

No. Name of Address Affected Size Affected Size Affectee Property Property (Household (square (square For 19m As per Head) feet) feet) corridor designs

Package 02 – (23.00km-47.00km)

Lahiru Namal Avantha, Dombepola, Iron Gates 60 Iron Gates 60 1 31+560-LHS Boyagane

Lakshmi Perera Hasiri stores,Boyagane Iron Gates 100 Iron Gates 100 2 32+000-LHS

Dewattara, new rd, Wood Gates 70 Iron Gates - 3 W.T. Ramyasiri Boyagane

Nelumpokunagama, Iron Gates 100 Iron Gates - Colombo Road, 4 O.P. Mendis Boyagane

A.S. Dematage Jaya Mawatha,Boyagane Iron Gates 70 Iron Gates 70 5 32+620-LHS

Package 03 – (47.00km-69.00km)

P.L. Samansiri 27, Siril, Gokerella Iron Gates 70 Iron Gates 70 6 60+600-RHS

Wijaya Road, Gokerella Iron Gates Iron Gates 7 L.K. Saliya 90

P.H. Nandika 22 B, Asiri, Gokerella Iron Gates 70 Iron Gates 70 8 61+600-LHS

34/b, Gokerella Iron Gates Iron Gates 9 E.M. Balasooriya 80 -

Herath Kumarage Iron Gates 45 Iron Gates 45 10 61+715-RHS 12/c, Gokerella

f.K. Fernandoo 27, Asha stores, Iron Gates 35 Iron Gates 35 11 63+720-LHS Gokerella

12, Damulla Road, Iron Gates 60 Iron Gates - 12 L.M. Bathiya Gokerella

Package 04 – (69.00km-90.00km)

Senanayaka Iron Gates 50 Iron Gates - 13 S.V. Veerasekera Mawatha,Gokerella S.N. B. Jaliya Iron Gates 60 Iron Gates 60 14 69+700-LHS Gamagewatth, Galewela

Ramya Palace, Iron Gates 70 Iron Gates - 15 H.M. Nalinda Kurunegala

Nelumpokunagama, , Iron Gates 65 Iron Gates - 16 Q.P.Rajesh Galewela

F.B. Chaminda Iron Gates 80 Iron Gates 80 17 75+340-RHS Crown Plaza, Galewela

Iron Gates Iron Gates 18 S.M. Kanthilatha New Town, Dambulla 45 -

A.M. Lankasiri Iron Gates 125 Iron Gates 125 19 80+980-RHS Yatigalpoththa, Dambulla

(The details may change once the designs are finalized)

Table 6 Affected Parapet Walls (Ambepussa – Dambulla Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property Property (Square feet) (Square for 19m corridor as per feet) designs

Package -01 (00.00km-23.00km)

Lahiru Namal 9+370- Bodirukkaramaya, Parapet Walls 120 Parapet Walls 120 1 RHS Allawwa

Galgamuwa, Parapet Walls 110 Parapet Walls 110 Lakshmi Perera Keppetiwalana, 2 14+680-RHS Polgahawela

Dewattara, Parapet Walls 125 - Wennoruwa, 3 W.T. Ramyasiri Polgahawela

Nelumpokunagama, Parapet Walls 250 Parapet Walls 250 O.P. Mendis Colombo Road, 4 15+160-LHS PolgahawelaAlawwa

Package 02 – (23.00km-47.00km)

Jaya Mawatha, Parapet Walls 52 Parapet Walls - 5 A.S. Dematage Mahakadawatha

P.L. Samansiri 27+100- 27, Dambokka Parapet Walls 170 Parapet Walls 170 6 RHS

Wijaya Parapet Walls 70 - - 7 L.K. Saliya Road,Dambokka

22 B, Boyagane Parapet Walls Parapet Walls 8 155 155 P.H. Nandika 39+740- LHS

23/b, Boyagane Parapet Walls 9 E.M. Balasooriya 40 - -

Herath Kumarage Parapet Walls 280 Parapet Walls 280 10 44+240-RHS 12/c, Ibbagamuwa

Package 03 – (47.00km-69.00km)

27, Giriulla Parapet Walls 11 f.K. Fernandoo 45 - -

L.M. Bathiya 60+650- 12, Damulla Road , Parapet Walls 210 Parapet Walls 210 12 RHS Gokerella

S.V. Veerasekera Senanayaka Parapet Walls 190 Parapet Walls 190 13 61+600-LHS Mawatha, Gokerella

S.N. B. Jaliya 63+720- Gamagewatth, Parapet Walls 130 Parapet Walls 130 14 LHS Panliyadda

Ramya Palace, Parapet Walls 58 - - 15 H.M. Nalinda Panliyadda

Q.P.Rajesh 67+370- Nelumpokunagama, Parapet Walls 90 Parapet Walls 90 16 LHS Omaragolla

Package 04 – (69.00km-90.00km)

Crown Plaza, Parapet Walls 65 - - 17 F.B. Chaminda Kanadana

S.M. Kanthilatha Parapet Walls 160 Parapet Walls 160 18 69+700-LHS 25B, Galewela

Parapet Walls 19 A.M. Lankasiri Siva Hotel, Galewela 80 - -

Table 7 Affected Front walls /roof extensions of business Places (Ambepussa – Dambulla Road Section)

No. Name of Affectee Address Affected Size Affected Size ousehold Head) Property Property (Square (Square for 19 corridor as per feet) feet) designs

Package 02 – (23.00km-47.00km) Front wall/roof 45 Front wall/roof 90 L.K. Dharmadasa extension of Business extension of 1 33+060-RHS 23, Boyagane Places Business Places

Front wall/roof 60 Front wall/roof 80 S.P. Liyanagee Main extension of Business extension of 2 34+000-LHS Street,Boyagane Places Business Places

Front wall/roof 110 - - extension of Business 3 S.D. weerasinghe Old Street, Boyagane Places

Front wall/roof 60 - - 11C, Dambulla Rd, extension of Business 4 J.H. Hemamala Boyagane Places

Mahakonwewa, Front wall/roof 135 Front wall/roof 120 S.H. Kamal Hindagolla, extension of Business extension of 5 34+120-RHS Kurunegala Places Business Places

Kamal vila, Front wall/roof 90 Front wall/roof 90 W.O. Perera Hindagolla, extension of Business extension of 6 34+370-LHS Kurunegala Places Business Places

Rathkarawa, Maspota, Front wall/roof 75 Front wall/roof 95 G.L. Kamalini 39+860- Kurunegala extension of Business extension of 7 RHS Places Business Places

Wewagedara, Front wall/roof 70 - - Hindagolla, extension of Business 8 N.M. Bandara Kurunegala Places

Savsiri, Ibbagamuwa Front wall/roof 65 Front wall/roof 90 S.P. Gamani Silva extension of Business extension of 9 46+740-RHS Places Business Places

Package 03 – (47.00km-69.00km)

5 A, ss Front wall/roof 115 Front wall/roof 110 W.N. Shayamali Building,Polgolla extension of Business extension of 10 51+900-LHS Places Business Places

Front wall/roof 75 - - 23a, Samanala Vasa extension of Business 11 F.G. Lahiru Polgolla Places

Front wall/roof 67 Front wall/roof 125 S.M.J. Subasinghe extension of Business extension of 12 52+900-LHS 34B, Gokerella Places Business Places

Front wall/roof 80 - - extension of Business 13 A.J. Manipala Achini, Gokerella Places

Front wall/roof 115 Front wall/roof 75 E.M. Perera Wasantha Village, extension of Business extension of 14 58+800-RHS Melsiripura Places Business Places Front wall/roof 60 - - extension of Business 15 J.L. Kumara 12, B, Melsiripura Places

Front wall/roof 80 Front wall/roof 120 D.J. Karunasiri 58+820- 10, Oruwala , extension of Business extension of 16 RHS Melsiripura Places Business Places

Front wall/roof 98 Front wall/roof 120 D.L. K. Himali 58+910- New Road, extension of Business extension of 17 RHS Melsiripura Places Business Places

Front wall/roof 55 - - Temple Lane, extension of Business 18 W.N.M. Malani Melsiripura Places

Front wall/roof 60 - - extension of Business 19 C.M. Nalinda 104C, Melsiripura Places

23/2, Dambulla Front wall/roof 75 Front wall/roof 70 W.K. Perera Road,Gokerella extension of Business extension of 20 59+020-LHS Places Business Places

12, Dambulla Road, Front wall/roof 55 - - Gokerella extension of Business 21 G.M.N. Laksiri Places

32/3, Gokerella Front wall/roof 80 Front wall/roof 90 E.K. Jayasinghe extension of Business extension of 22 60+600-RHS Places Business Places

Front wall/roof 90 - - Wasantha Uana, 23, extension of Business 23 W.F. Hemantha Gokerella Places

AMP seva, Front wall/roof 90 Front wall/roof 110 F.K. Jaliya Panliyadde extension of Business extension of 24 66+290-RHS Places Business Places

45b, Panliyadda Front wall/roof 85 Front wall/roof 125 D.M. Muthusinghe extension of Business extension of 25 66+370-RHS Places Business Places

Package 04 – (69.00km-90.00km)

Galgamuwa, Front wall/roof 70 - - Panliyadda extension of Business 26 R.M. Darshana Places

Dewattara, Front wall/roof 110 - - Wennoruwa, extension of Business 27 F.M. Nalinda Panliyadda Places

Nelumpokunagama, Front wall/roof 90 - - Dambulla Road, extension of Business 28 Q.M. Bandara Panliyadda Places Jaya Mawatha, Front wall/roof 85 Front wall/roof 220 C.N. Perera Galewela extension of Business extension of 29 72+300-RHS Places Business Places

27, Galewela Front wall/roof 75 - - extension of Business 30 f.K. Fernandoo Places

Front wall/roof 115 - - 12B, Damulla Road extension of Business 31 L.M. Bathiya ,Galewela Places

Front wall/roof 123 - - Senanayaka extension of Business 32 S.V. Veerasekera Mawatha, Galewela Places

Front wall/roof 85 - - Ramya Palace, extension of Business 33 H.M. Nalinda Galewela Places

Nelumpokunagama, Front wall/roof 75 Front wall/roof Q.P.Rajesh Colombo Road, extension of Business extension of 34 72+400-RHS Galewela Places Business Places 230

Front wall/roof 90 - - Crown Plaza, extension of Business 35 F.B. Chaminda Galewela Places

Front wall/roof 95 Front wall/roof 175 S.M. Kanthilatha 45B,Dambulla road, extension of Business extension of 36 76+030-RHS Galewela Places Business Places

Front wall/roof 75 Front wall/roof 90 A.M. Lankasiri extension of Business extension of 37 88+020-RHS 1st Street, Kurunegala Places Business Places

New Vijaya Front wall/roof 90 - - G.Suriyaarachchi Road,Pohorawewa, extension of Business 38 88+050-RHS Dambulla Places

Temple Road, Front wall/roof 95 Front wall/roof 120 Pohorawewa, extension of Business extension of 39 Saman Gamii Dambulla Places Business Places

(The details may change once the designs are finalized)

Table 8 Affected Permanent Sales Huts (Ambepussa – Dambulla Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Property for Property (Square feet) (Square Head) 19m As per feet) corridor designs Package 02 – (23.00km-47.00km)

Lakmali Perera Permanent Sales 45 Permanent 45 1 33+045-LHS 22,Boyagane Huts Sales Huts

Hemantha Silva Dambulla Road, Permanent Sales 55 Permanent 55 2 44+750-RHS Boyagane Huts Sales Huts

B.K. Jayamanna Welelanda, Permanent Sales 40 Permanent 40 3 45+030-RHS Ibbagamuwa Huts Sales Huts

Permanent Sales 60 - - 4 N.M. Gajasinghe 6A, Ibbagamuwa Huts

Package 03 – (47.00km-69.00km)

H.P. Ferera 45A, Old Building, Permanent Sales 65 Permanent 45 5 50+780-RHS Polgolla Huts Sales Huts

Hewage Furniture, Permanent Sales 50 - - Dambulla Road, Huts 6 L.K. Hemasiri Polgolla

L.K. Jayamini Ambanpola Junction, Permanent Sales 110 Permanent 60 7 55+620-LHS Melsiripura Huts Sales Huts

F.G. Laksiri Ambanpola, Permanent Sales 75 Permanent 55 8 63+450-RHS Panliyadda Huts Sales Huts

S.P. Pathmasiri 22 C, Panliyadda Permanent Sales 120 Permanent 50 9 65+070-LHS Huts Sales Huts

Package 04 – (69.00km-90.00km)

38 B, Dambulla Permanent Sales 95 - - 10 W.F. Gamini Road,Panliyadda Huts

S. Kanakasooriya 30 B, Galewela Permanent Sales 80 Permanent 45 11 70+230-RHS Huts Sales Huts

J.L. Kamini 79+235- 119, Permanent Sales 50 Permanent 50 12 RHS Yatigalpoththa,Dambulla Huts Sales Huts

(The details may change once the designs are finalized)

Table 9 Affected Lands (Ambepussa – Dambulla Road Section)

A- Agriculture lands, B- Barren Lands, R- Residential lands F- Forest Lands

No. Name of Affectee Address Affected Affected % Affected Size (Household Head) Property of total land Property 2 for 19m holding as per (m ) corridor designs

Package – 01 ( 00+00km-23.00+00km)

R. Jayawardena, Diganawatte, Lands-A 5.2% Land-A 200 1 1+120mk-1+190km-LHS Ambepussa

P.Tibbatugolla, Kurunegala Road, Lands-A 3.7% Land-A 250 1+220km-1+300km- Ambepussa 2 RHS

50, Dambulla Road, Lands-A 3% - - 3 M.I. Sesiri Alawwa

Savindi Lane, Lands-R 5% - - 4 S.P. Hashini Alawwa

CGR Land- 12+200km- Yangalmodera,Polga Lands-B 0.8% Land-B 100 5 12+250km-LHS hawela

Lands-R 6 Anura Perera 34/2, Polgahawela 4% - -

Kurunegala Road, Lands-R 0.8% - - 7 S. Susirisena Polgahawela

Kurunegala Lands-R 0.8% - - 8 A.M. Amarasiri road,Polgahawela

Kamal House, Lands-R 0.9% - - 9 S.M. Gamini Polgahawela

M.O.H. Office Land Lands-R 2.0% Land -R 100 14+680km-14+800km- Kurunegala Road 10 RHS Polgahawela

Lands-R 11 W.A. Sisirakmara Angama, Kurunegala 3.4% - -

Coconut Mills – Lands-R 5.2% - - 12 Cooperative, Galewela Galewela

Kurunegala Road, Lands-R 0.4% Land-R 100 Polgahawela

Hospital Land 15+870km-15+900km- 13 RHS

Package – 02 ( 23+00km-47.00+00km)

H.Adikaram 24+080km- Kurunegala Roadd, Land-A Land-A 120 14 24+180km-RHS Mahakadawatha

Mosque Land Lands-R 6.5% Land-R 100 40+040km-40+100km- Thorayaya, 15 RHS Kurunegala

Thorayaya, Lands-R 2.7% - - 16 G.N. Perera Kurunegla 34, Dambulla Lands-R 5.5% - - 17 Agro Products Stole- road,Pothuhara

Lands-R 18 Asiri Perera 88, Dambokka 0.3% - -

st 123, 1 Lane, Lands-A 4.0% - - 19 Sasini Nidesh Dambokka

Lands-R 20 A.P. Balasooriya 23, Dambokka 1.1% - -

12, Main road, Lands-R 0.78% - - 21 Wasantha Madamage Boyagane

Kumara Vasa, Lands-A 2.2% - - 22 W.M. Leela Boyagane

12, Station Road, Lands-A 6.4% - - 23 F.M. Kamalasiri Boyagane

10, Oruwala Road. Lands-R 4.6% - - 24 G.M. Lakmal Boygane, Kurunegala

87A,Dambulla road Lands-R 5% - - 25 H.P. Juliyas Boyagane

Temple Lane, Lands-R 0.5% - - -26 Wasantha Nisad Boyagane

Package – 03 ( 47+00km-69.00+00km)

LRC Land 64+350km- Dambulla Road, Lands-R 6.4% Land-R 125 27 64+390km-LHS Panliyadda

23/2, Dambulla Road, Lands-R 1.8% - - 28 R.Y. Lumad Panliyadda

K.M. Suriyabandara Dambulla Road, Lands-A 2.8% Land-A 125 29 65+220km-65+300km Panliyadda

32/3, Panliyadda Lands-R 30 D.M. Udenis 1.3% - -

1st Lane, Panliyadda Lands-R 31 S.I. Gamage 5% - -

Villa House, Lands-R 1.2% - - Dambulla road, 32 P.L. Herath Panliyadda

69, Dambulla Road, Lands-A 3.9% - - 33 D.M. Jayakody Panliyadda

Upul Chandima Omaragolla, Lands-A 1.7% Land-A 140 66+480km-66+550km- Panliyadda 34 RHS

88, Dambulla Road, Lands-R 1.3% - - 35 D.M. Nilamani Omaragolla Temple Junction, Lands-R 5.6% - - 36 Saseri Pubudu Omaragolla

Forest Dept. Land Dambulla Road, Lands-F 0.8% Land-F 150 66+840km-66+940km- Omaragolla 37 RHS

Polonnaruwa Road, Lands-R 1.25% - - 38 S.L. Jayasinghe Omaragolla

238, Dambulla Road, Lands-R 0.6% - - 39 D.M. Hemantha Omaragolla

Package – 04 ( 69+00km-90.00+00km)

24C,Dambulla road, Lands-R 1.4% - - Kanadana 40 C.Sunimal

27,Dambulla road, Lands-A 3.1% - - 41 M.K. Balasiri Kanadana

12, Damulla Road , Lands-A 2.3% - - 42 H.M. Kamalawathi Galewela

Senanayaka Lands-R 1.9% - - 43 S.P. Namalee Mawatha, Galewela

Gamagewatth, Lands-R 3.6% - 44 E.M. Hiran Galewela

Ramya Palace, Lands-A 1.3% - - 45 W.B. Wimalawathi Galewela

Dambulla road,BMV Lands-A 4.3% - - 46 S.D. Gamini Galewela

Crown Plaza, Lands-R 2.9% - - 47 T.M. jayawathi Galewela

Dambulla road, 18c, Lands-A 1.4% - - 48 D.N. Perera Galewela

10/2 New Fancy, Lands-A 2.06% - - 49 E.M. Kamalawathi Galewela

New Vijaya Lands-A 2.8% - - Dambulla Road, 50 P.L. Hiran Galewela

Queens, Dambulla Lands-B 2.48 - - 51 C.N. Jayakodi road, Galewela

TOska tea shop, Lands-A 5% - - 52 D.K. Mahasinghe Galewela

34/5, Yatigalpoththa, Lands-R 2.4% - - 53 Asiri Herath Dambulla Welelanda, Lands-R 2.4% - - 54 N. Malaka Pothuhera

6A,Mihindu Place, Lands-R 4.9% - - 55 C. Siripala Dambulla

45A, Pohorawewa, Lands-A 4.24% - - 56 B.M. Dharmasiri Dambulla

Hewage Furniture, Lands-A 2.8% - - Dambulla Road, 57 S.D. Ananda Dambulla

45/B, Dambulla road, Lands-A 3.8% - - 58 S.O.Perera Dambulla

(The details may change once the designs are finalized)

Annex 06B Affected Properties (Kanthale-Trincomalee Road Section)

Table 1. Affected front walls of houses & Buildings (Kanthale-Trincomalee Road Section)

No. Name of Address Affected Size Affected Size Affectee Property for Property as (Square feet) (Square feet) (Household 19m corridor per finalized Head) design

Package 05 - (157km – 178km)

th Front wall of 90 - - 10/a,98 Mr. N.K.Nawarathne Junction, houses & 1 Bandara Thmbalagamuwa Buildings

Package 06 – (178km – 200km)

Front wall of 75 - - Mr. M.S. Sarath 474, Kandy Rd, Chinabay, houses & 2 Thrincomalee. Buildings

6th Mile Post , Front wall of 80 - - Sardhapura, houses & Mr. S. Kandy Rd, Buildings 3 Thilakarathna Trincomalee.

Front wall of 6th Mile Post 60 - - Mrs. H.H ,Kandy Rd, houses & 4 Chandrakirthi Trincomalee. Buildings

6th Mile Post, Front wall of 70 - - Chinabay, houses & Mr. K.M Anton Sardapura ,Kandy Buildings 5 Jayarathne Rd,Trincomalee

Front wall of No. 231, Kandy 65 - - road, Chinabay, houses & 6 Mr. M.Gamini Thrincomalee Buildings

Front wall of 204 Front wall of 120

Kowil Building Kandy Rd, houses & houses & 7 197+800km- RHS Trincomalee Buildings Buildings

Front wall of 135 Front wall of 113 S. Sithambaranadan, A.S.R. Oil Mart, Kandy houses & houses & 8 197+470km RHS Rd. Trincomalee Buildings Buildings

Front wall of Front wall of 9 602 380 S.Pasamalar ,No262,Inner houses & houses & 198+350km LHS Harbour,Trincomalee Buildings Buildings

Front wall of 435 Front wall of 355 K.Seevarathnam, No260,Inner harbor, houses & houses & 10 198+370km LHS Trincomalee Buildings Buildings

Front wall of 190 Front wall of 226 Jabeena Behem, No254A,Inner harbor houses & houses & 11 198+385km LHS , Trincomalee Buildings Buildings

Front wall of 234 Front wall of 322 C. Sivanatharaja,, No252A,Inner houses & houses & 12 198+400km LHS harbour,Trincomalee Buildings Buildings

Front wall of 234 Front wall of 129 S.D.Nazardeen, No252,Inner harbor houses & houses & 13 198+420km LHS ,Trincomalee Buildings Buildings

Front wall of 250 Front wall of 161 Department of Motor houses & houses & 14 Traffic, 198+680km LHS Trincomalee Buildings Buildings

Front wall of 320 Front wall of 290 Department of Motor houses & houses & 25 Traffic, 198+ 690km LHS Trincomalee Buildings Buildings

Front wall of 350 Front wall of 258 Dept. of Fisheries (District Office) houses & houses & 16 198+835km LHS Trincomalee Buildings Buildings

Front wall of 220 Front wall of 161 houses & houses & 17 Irrigation Department Trincomalee Buildings Buildings

Front wall of 345 Front wall of 290 Deputy Survey Generals houses & houses & 18 Office 198+880km LHS Trincomalee Buildings Buildings

Front wall of 302 Front wall of 258 District Surveyor Office houses & houses & 19 198+888 LHS Trincomalee Buildings Buildings

Front wall of 345 Front wall of 290 Dept. of Social Service houses & houses & 20 198+940km LHS Trincomalee Buildings Buildings

District Secretaries Front wall of 408 Front wall of 376 Quarters 199+145km houses & houses & 21 LHS Trincomalee Buildings Buildings

Front wall of 1120 Front wall of 750 Road Development Authority 199+180km houses & houses & 22 LHS Trincomalee Buildings Buildings

Front wall of 620 Front wall of 527 Road Development Authority 199+230km houses & houses & 23 LHS Trincomalee Buildings Buildings

Front wall of 523 Front wall of 430 Road Development Authority 199+240km houses & houses & 24 LHS Trincomalee Buildings Buildings

Table 2 Affected cement floors/concrete steps of business places(Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for 19 Property as per (Square feet) (Square feet) meters finalized design corridor

Package 05 - (157km – 178km)

Cement 15 - - No. floors/concrete 703,Galwahiyawa, steps of business 1 Mr. A. Paris Thmbalagamuwa places

Cement 18 - - Harron stores floors/concrete ,702/99,Thambalag steps of business 2 Mr. M.I .Alliakbar amuwa places

Cement 20 - - Galathpathi floors/concrete Mrs. A.G Thushantha Stors,93 Junction steps of business 3 Dhammika ,Kantale places

Cement 45 - - floors/concrete Mrs. W.G Wasanthi Shanthi Stors ,92 steps of business 4 Kumari Junction,Kantale places

Cement 15 - - floors/concrete Mr. A.B Lalith 93 steps of business 5 Priyankara Junction,Kamtele places Cement 10 - - Shantha Sewana, floors/concrete Mr. B.P Shantha 92 Junction steps of business 6 Kumara ,Kantale places

Package 06 - (178km – 200km)

Cement 10 - - 5th Mile Post, floors/concrete Mrs. P.M Chinabay, steps of business 7 .Hinnihamine Thrincomalee. places

Cement 22 - - 211,Kandy Road, floors/concrete Chinabay, steps of business 8 Mr. T.B Vijepala Thrincomalee places

6th Mile Post, Cement 18 - - Chinabay, floors/concrete Sardapura ,Kandy steps of business places 9 Mrs. S.Thilakawathi Rd,Trincomalee

No. 634, 5th Mile Cement 20 - - Post, floors/concrete Gamunupura,Kan steps of business places Mrs. M.H Nilanthi dy Road, 10 Kumari Da Sillva Trincomalee.

Cement 19 Cement 12 Mrs. S.A Pramawathi Starlite Moters, floors/concrete floors/concrete Chinabay, steps of business steps of business 11 198+220km-LHS Thrincomalee. places places

6th Mile Post, Cement 25 Cement 15 Mr. M.C.J. Kumara Chinabay, floors/concrete floors/concrete Sardapura ,Kandy steps of business steps of business places places 12 198+300km-LHS Rd,Trincomalee

Table 3 Affected Concrete/cement steps of public places (Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for 19 Property as (Square feet) (Square feet) meters corridor per finalized design

Package 05 - (157km – 178km)

Trinco Road, Concrete/cement 15 - - 1 Mahaweli Auhority Kanthale steps Package 06 - (178km – 200km)

Front Road, Concrete/cement 18 - - 2 SANASA Bank Trincomalee steps

Small Farmers 122/3, Concrete/cement 25 - - 3 Cooperative Trincomalee steps

Table 4 Affected permanent fences ( iron poles with concrete columns)(Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for 19 Property as (Square feet) (Square feet) meters corridor per finalized design

Package 05 - (157km – 178km)

No. 708, Permanent fence ( iron 200 - - Kalmatiyawa, poles with concrete KandyRoad, columns) 1 Mr. M.I Jenis Kanthale

Muslim Permanent fence ( iron 180 - - Hotel,Mullipothan poles with concrete a,96 Junction, columns) Kandy Road, 2 Mr. A.M Farook Kantale.

No. 307, Unit 7, 97 Permanent fence ( iron 170 - - Junction, poles with concrete Molipothana, columns) Kandy Road, 3 Mr. A. Sheran Kantale.

Permanent fence ( iron 240 - - Lakmal Grosary ,93 poles with concrete 4 Mrs. A.G Chandra Violat Junction,Kantale columns)

Package 06 - (178km – 200km)

5th Mile Post, Permanent fences ( 20 - - Kandy road, iron poles with Chinabay, concrete columns) 5 Mr. G.N Wanigasekara Thrincomalee

R 89/1,Unit 16, Permanent fence ( iron 25 - - 6 Mr. U.L. Karunarathne. Kanthale poles with concrete columns)

Permanent fence ( iron 30 - - 156/3,Kandy poles with concrete 7 Mr. A.M Garnini Rd,Trincomalee. columns)

Permanent fence ( iron 1072 Permanent fence ( 1072 Asst. Auditor General Dept poles with concrete iron poles with 8 198+740km LHS Trincomalee columns concrete columns

Table 5 Affected Gates (Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for 19 Property as (Square feet) (Square feet) meters corridor per finalized design

Package 05 - (157km – 178km)

Y.P. Samitha Iron Gate 50 Iron Gate 50 N0.22, Kandy Rd, 1 (161+220 – RHS) Kanthale

Mrs.W.P.Ariyawathi. No. 364/91, Iron Gate 50 Iron Gate 50 Kandy Road, 2 163+102km-RHS Kanthele.

No. Iron Gate 180 Iron Gate 180 Mr. N.G.Ranbanda 160,Kalamatigoda South, Kandy 3 164+160km-LHS Road Kanthale.

No.95, Iron Gate 60 Iron Gate 60 Mrs.Kusum Nalani Mollipothana,Kantha 4 169+115km-LHS le

Mr. W.A.W.A.Jayasinghe Iron Gate 55 Iron Gate 55 NMC,96milepost, 5 171+170km-LHS Mollipothana.

Package 06 - (178km – 200km)

23c, Trincomalee Iron Gate 60 - - 6 R. Sivasothi roadd, Trincomalee

th 5 Iron Gate 40 Iron Gate 40 7 Mr. S. Gamini Milepost,Kandy Road,China 191+535km-RHS Bay,Trincomalee

Y. Pemasiri 196+880km 18/B2, Kandy Iron Gate 40 Iron Gate 40 8 RHS Road Trincomalee

N.D. Thamara 12, Kandy Road, Iron Gate 40 Iron Gate 40

9 196+900km LHS Trincomalee

Y. P. Geanadan, No. 32/A, Kandy Rd, Iron Gate 50 Iron Gate 50 10 197+140km LHS Trincomalee

W. Gunasekers, 46, Kandy Road, Iron Gate 30 Iron Gate 30 11 197+240km LHS Trincomalee

s. Eebrahim Iron Gate 45 Iron Gate 45 23/2, KAndt Road, 12 197+280km LHS Trincomalee

Asiri Perera Iron Gate 25 Iron Gate 25 20/2,mKandy Road, 13 197+320km LHS Trincomalee

Wasantha Laxman Iron Gate 50 Iron Gate 50 40/B, KAndy Road, 14 197+340km LHS Trincomalee

S.H. Ramyalatha, 197+340km No28, Kandy Rd, Iron Gate 50 Iron Gate 50 LHS Trincomalee 15 Priest Peter Paul, 197+370km Assemble of God, Iron Gate 40 Iron Gate 40 LHS Kandy Rd. 16 Trincomalee

R. Rasan, 197+380km LHS No20,Kandy Road, Iron Gate 30 Iron Gate 30 17 Trincomalee

Z.A.M. Nasrim, 197+390km No20,Kandy Iron Gate 30 Iron Gate 30 18 LHS Rd.Trincomalee

Dunara Construction Iron Gate 25 Iron Gate 25 PVT.Ltd,Kandy W.Hewawitharana, Road,No06, 19 197+500km LHS Trincomalee

SP. Bang low(Police), No340,Kandy Iron Gate 60 Iron Gate 60 20 197+760km LHS Rd,Kanthale

Y.Tisera, 197+860km LHS No318,Kandy Iron Gate 35 Iron Gate 35 21 Rd.Trincomalee

T.Vijayakumara, 197+868km No318,KandyRd.Trinc Iron Gate 40 Iron Gate 40 22 LHS omalee

T.Vijayakumara, 197+890km No318,KandyRd. Iron Gate 50 Iron Gate 50 23 LHS Trincomalee

V. Pushparajan, 197+895km Iron Gate Iron Gate 24 35 35 No316,Kandy LHS Rd,Trincomalee

Iron Gate Iron Gate 25 P.Devendra, 197+900km LHS Kandy Rd,Trincomalee 40 40

Clark Spence & Iron Gate 60 Iron Gate 60 Co.Ltd.No290,Inne Harbor 26 W.Tisna, 198+120km LHS Rd,Trincomalee

Clark Spence & Iron Gate 45 Iron Gate 45 Co.Ltd.No290,Inne Harbor 27 W.Tisna, 198+120km LHS Rd,Trincomalee

Sinhala Maha Viddayalaya, Iron Gate 80 Iron Gate 80 28 198+200KM LHS Trincomalee

J.F.Jeganathan, 198+300km J.R.S.Shipping Iron Gate 35 Iron Gate 35 LHS Pvt.Ltd.268, Inner 29 Harbor ,Trincomalee

S.Benjamin, 198+325km LHS No261,Inner Iron Gate 40 Iron Gate 40 30 Harbor,Trincomalee

Mrs.S.Pasamalar, 198+350km No262,Inner Iron Gate 40 Iron Gate 40 31 LHS Harbour,Trincomalee

K.Seevarathnam 198+370km ,No260,Inner harbor, Iron Gate 35 Iron Gate 35 32 LHS Trincomalee

Jabeena Behem, 198+385km No254A,Inner harbor , Iron Gate 40 Iron Gate 40 33 LHS Trincomalee

C. Sivanatharaja,, 198+400km No252A,Inner Iron Gate 40 Iron Gate 40 34 LHS harbour,Trincomalee

S.D.Nazardeen, 198+420km No252,Inner harbor Iron Gate 35 Iron Gate 35 35 LSH ,Trincomalee

Sri Lanka Red Cross, No250, Inner harbor, Iron Gate 60 Iron Gate 60 36 198+440km LHS Trincomalee Branch

Sri Lanka Red Cross ,No250, Inner harbor, Iron Gate 50 Iron Gate 50 37 198+440km LHS Trincomalee Branch

St. Joshep Collage, 198+540km Inner Harbor Rd, Iron Gate 60 Iron Gate 60 38 LHS Trincomalee

St. Joshep Collage 198+540km , Inner Harbor Rd, Iron Gate 50 Iron Gate 50 39 LHS Trincomalee

Provincial Vehicle Parking Eastern Provincial Iron Gate 55 Iron Gate 55 40 Place, 198+620km LHS Council, Trincomalee

Department of Motor Traffic, Iron Gate 50 Iron Gate 50 41 198+680km LSH Trincomalee Ceylon Cold Stores 198+812 Iron Gate 45 Iron Gate 45 42 LHS Trincomalee

Dept. of Fisheries (District Iron Gate 45 Iron Gate 45 43 Office) 198+835 LHS Trincomalee

Deputy Survey Generals Office Iron Gate 35 Iron Gate 35 44 198+880km LHS Trincomalee

Dept. of Social Service Iron Gate 40 Iron Gate 40 45 198+940km LHS Trincomalee

District Secretaries Quarters Iron Gate 35 Iron Gate 35 46 199+145km LHS Trincomalee

RDA 199+180KM LHS Iron Gate Iron Gate 47 Trincomalee 40 40

RDA 199+200km LHS Iron Gate Iron Gate 48 Trincomalee 40 40

RDA 199+210km LHS Iron Gate Iron Gate 49 Trincomalee 35 35

RDA 199+220km LHS Iron Gate Iron Gate 50 Trincomalee 35 35

RDA 199+230km LHS Iron Gate Iron Gate 51 Trincomalee 35 35

Rajakumara Iron Gate 40 Iron Gate 40 Stores&Enterprices,N o19,KAndy 52 P.Rajkumara, 197+380km RHS Rd.Trincomalee

Rajakumara Iron Gate 40 Iron Gate 40 Stores&Enterprices,N o19,KAndy 53 P.Rajkumara, 197+420km RHS Rd.Trincomalee

Dhanawatte Dental Iron Gate 45 Iron Gate 45 S.Hemachandra 197+500KM Hospital,Kandy Rd. 54 RHS Trincomalee

Irrigation Iron Gate 45 Iron Gate 45 55 Department197+840km RHS Trincomalee

Table 6 Affected Parapet Walls (Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for 19 Property as (Square feet) (Square feet) meters corridor per finalized design Package 05 - (157km – 178km)

Y.P. Samitha Parapet Wall 275 Parapet Wall 200 N0.22, Kandy 1 (161+220 – RHS) Rd, Kanthale

Mrs.W.P.Ariyawathi. No. 364/91, Parapet Wall 216 Parapet Walls 216 Kandy Road, 2 163+102km-RHS Kanthele.

No. Parapet Wall 120 Parapet Walls 120 160,Kalamatigo Mr. N.G.Ranbanda da South, Kandy Road 3 164+160km-LHS Kanthale.

Mr. W.A.W.A.Jayasinghe NMC,96milepo Parapet Wall 300 Parapet Walls 300 st,Mollipothana 4 171+170km-LHS .

Package 06 - (178km – 200km)

Lional Munasinghe Parapet Wall 350 Parapet Walls 350 & Styores, Sriya Stores, 5 Kandy L.Munasinghe, Rd., Anandakulama, 5 193+773km-LHS Trincomaleee

S.M. Kapila Parapet Wall 430 Parapet Wall 430 56/BKandy Road, 6 197+200km LHS Trincomalee

W. Nadeshan Parapet Wall 645 Parapet Wall 645 22/B2 Kandy Road, 7 197+240km LHS Trincomalee

S.H. Ramyalatha, 197+340km No28, Kandy Rd, Parapet Wall 215 Parapet Wall 215 8 LHS Trincomalee

Priest Peter Paul, 197+370km Assemble of God, Parapet Wall 129 Parapet Wall 129 LHS Kandy Rd. 9 Trincomalee

R. Rasan, 197+380km LHS No20,Kandy Road, Parapet Wall 107 Parapet Wall 107 10 Trincomalee

Z.A.M. Nasrim, 197+390km LHS No20,Kandy Parapet Wall 1679 Parapet Wall 1679 11 Rd.Trincomalee

Kantha Sunil Hewawitharana, No10,KandyRd.,Tri Parapet Wall 107 Parapet Wall 107 ncomalee 12 197+430km LHS Kantha Sunil Hewawitharana, No10,KandyRd.,Tri Parapet Wall 1219 Parapet Wall 1219 13 197+480km LHS ncomalee

W.Hewawitharana, 197+500km Dunara Parapet Wall 215 Parapet Wall 215 LHS Construction PVT.Ltd,Kandy Road,No06, 14 Trincomalee

HQI Bungalow(Police), No340,Kandy Rd., Parapet Wall 64 Parapet Wall 64 15 197+650km LHS Trincomalee

SP. Bang low(Police) ,No340,Kandy Parapet Wall 215 Parapet Wall 215 16 197+760km LHS Rd,Kanthale

M.Nallaiya, 197+780km LHS No48,Kandt Parapet Wall 430 Parapet Wall 430 17 Rd,Trincomalee

P.Rajendram, 197+800 LHS Mathusha Parapet Wall 150 Parapet Wall 150 Stationery Shop, No326,I.H.Road,Tri 18 ncomalee

P.Rajendram, 197+820km LHS Mathusha Parapet Wall 107 Parapet Wall 107 Stationery Shop, No326,I.H.Road,Tri 19 ncomalee

P.Rajendram, 197+840km LHS Mathusha Parapet Wall 968 Parapet Wall 968 Stationery Shop, No326,I.H.Road,Tri 20 ncomalee

Y.Tisera 197+860km LHS ,No318,Kandy 150 150 21 Rd.Trincomalee Parapet Wall Parapet Wall

T.Vijayakumara, 129 129 197+868km LHS No318,KandyRd. 22 Trincomalee Tin sheet wall Tin sheet wall

T.Vijayakumara, 32 32 197+890km LHS No318,KandyRd. 23 Trincomalee Tin sheet wall Tin sheet wall

V. Pushparajan, 197+895km No316,Kandy Parapet Wall 32 Parapet Wall 32 24 LHS Rd,Trincomalee

W.Tisna,Clark Spence & Co.Ltd. No290,Inne Parapet Wall 538 Parapet Wall 538 Harbor 25 198+120 LHS Rd,Trincomalee

Sinhala Maha Viddayalaya, Trincomalee Parapet Wall 2906 Parapet Wall 2906 26 198+200km LHS

J.F.Jeganathan, 198+300km J.R.S.Shipping Parapet Wall 645 Parapet Wall 645 27 LHS Pvt.Ltd.268, Inner Harbor ,Trincomalee

S.Benjamin, 198+325km LHS No261,Inner Parapet Wall 667 Parapet Wall 667 Harbor,Trincomale 28 e

Mrs.S.Pasamalar, 198+350km No262,Inner Parapet Wall 516 Parapet Wall 516 LHS Harbour,Trincomal 29 ee

K.Seevarathnam 198+370km ,No260,Inner Parapet Wall 355 Parapet Wall 355 LHS harbor, 30 Trincomalee

Jabeena Behem, 198+385km ,No254A,Inner Parapet Wall 258 Parapet Wall 258 LHS harbor , 31 Trincomalee

C. Sivanatharaja 198+400km ,No252A,Inner Parapet Wall 322 Parapet Wall 322 LHS harbour,Trincomal 32 ee

S.D.Nazardeen, 198+420km No252,Inner Parapet Wall 129 Parapet Wall 129 LHS harbor 33 ,Trincomalee

Sri Lanka Red Cross,198+440km No250, Inner Parapet Wall 1270 Parapet Wall 1270 LHS harbor, Trincomalee 34 Branch.

EPDP Office 198+489km LHS Inner Harbor Parapet Wall 645 Parapet Wall 645 35 Rd,Trincomalee

St. Joshep Collage 198+540km Inner Harbor Rd, Parapet Wall 1959 Parapet Wall 1959 36 LHS Trincomalee

Provincial Vehicle Parking Place Eastern Provincial Parapet Wall 861 Parapet Wall 861 Council, 37 198+620km LHS Trincomalee

Department of Motor Traffic, Trincomalee Parapet Wall 731 Parapet Wall 731 38 198+680km LHS

Asst. Auditor General Dept. Trincomalee Parapet Wall 2152 Parapet Wall 2152 39 198+740km LHS

Ceylon Cold Stores 198+812km Trincomalee Parapet Wall 645 Parapet Wall 645 40 LHS

Dept. of Fisheries (District Trincomalee Parapet Wall 861 Parapet Wall 861 41 Office) 198+835 LHS

Ministry of Agriculture & Trincomalee Parapet Wall 215 Parapet Wall 215 42 Livestock 198+850km LHS

43 Deputy Survey Generals Office Trincomalee Parapet Wall 861 Parapet Wall 861 198+880km LHS 198+880km LHS

District Surveyor Office Trincomalee Parapet Wall 226 Parapet Wall 226 44 198+888km LHS

Eastern Provincial Council Trincomalee Parapet Wall 538 Parapet Wall 538 45 198+920km LHS

Dept. of Social Service Trincomalee Parapet Wall 1291 Parapet Wall 1291 46 198+940km LHS

M. Ehambaram, 199+000km 92/Inner harbor, Parapet Wall 322 Parapet Wall 322 47 LHS Trincomalee

Sri Lanka Customs 199+080km Trincomalee Parapet Wall 1184 Parapet Wall 1184 48 LHS

District Secretaries Quarters Trincomalee Parapet Wall 645 Parapet Wall 645 49 199+145km LHS

50 RDA 199+180km LHS Trincomalee Parapet Wall 322 Parapet Wall 322

51 RDA 199+200km LHS Trincomalee Parapet Wall 215 Parapet Wall 215

52 RDA 199+210km LHS Trincomalee Parapet Wall 86 Parapet Wall 86

53 RDA 199+220km LHS Trincomalee Parapet Wall 107 Parapet Wall 107

54 RDA 199+230km LHS Trincomalee Parapet Wall 430 Parapet Wall 430

55 RDA199+240km LHS Trincomalee Parapet Wall 430 Parapet Wall 430

56 RDA 199+260km LHS Trincomalee Parapet Wall 430 Parapet Wall 430

P.Rajkumara, 197+380km RHS Rajakumara Parapet Wall 21 Parapet Wall 21 Stores&Enterprice s,No19,KAndy 57 Rd.Trincomalee

P.Rajkumara 197+385km RHS Rajakumara Parapet Wall 16 Parapet Wall 16 Stores&Enterprice s,No19,KAndy 58 Rd.Trincomalee

P.Rajkumara 197+405km RHS Rajakumara Parapet Wall 20 Parapet Wall 20 Stores&Enterprice s,No19,KAndy 59 Rd.Trincomalee

P.Rajkumara 197+412km RHS Rajakumara Parapet Wall 21 Parapet Wall 21 Stores&Enterprice s,No19,KAndy 60 Rd.Trincomalee

P.Rajkumara, 197+416km RHS Rajakumara Parapet Wall 22 Parapet Wall 22 61 Stores&Enterprice s,No19,KAndy Rd.Trincomalee

P.Rajkumara, 197+420 RHS Rajakumara Parapet Wall 14 Parapet Wall 14 Stores&Enterprice s,No19,KAndy 62 Rd.Trincomalee

S.Hemachandra197+500km Dhanawatte Parapet Wall 645 Parapet Wall 645 RHS Dental Hospital,Kandy Rd. 63 Trincomalee

Irrigation Department Trincomalee Parapet Wall 139 Parapet Wall 139 64 197+840kmRHS

Table 7 Affected Front walls / Roof extensions of Business Places (Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for Property as (Square feet) (Square feet) 19 meters per finalized corridor design

Package 05 - (157km – 178km)

Shanthi Affected Front 145 Affected Front 72 B.P.Shanthakumara Stores,92Junctio wall/roof extension wall/roof extension 1 (164+300km)-RHS n,Kanthale of Business Places of Business Places

93 junction, Affected Front 360 Affected Front 200 Mr. M.K.P.Akman Perera 11/23 Unit 16 wall/roof extension wall/roof extension 2 (167+195km)-RHS Kanthale of Business Places of Business Places

703, Kantale Affected Front 400 Affected Front 200 Rd,Galamatiyaw wall/roof extension wall/roof extension 3 Mr. A.M.A. Anifar a, Kantale. of Business Places of Business Places

L.P. Wijesiri Affected Front 350 Affected Front 250 93 Junction- wall/roof extension wall/roof extension (167+220km)- RHS Kanthale of Business Places of Business Places

93 Affected Front 280 Affected Front 300 Ms.G.Dhammika Junction,Kantha- wall/roof extension wall/roof extension 4 (167+230km)-RHS le of Business Places of Business Places

S.W. Sumanasekera Affected Front 240 Affected Front 200 93, Junction, wall/roof extension wall/roof extension 5 167+240-RHS Kanthale of Business Places of Business Places

22, Mollipothana, Affected Front 275 Affected Front 210 6 S.Sandaya Kanthale wall/roof extension wall/roof extension 169+408LHS of Business Places of Business Places

98, Kandy Affected Front 275 Affected Front 180 Mrs.R.Raliya Road,Galameti- wall/roof extension wall/roof extension 7 (175+370km)-RHS yawa, of Business Places of Business Places

M. Masanadan 23, Kandy Road, Affected Front 125 Affected Front 75 wall/roof extension wall/roof extension 8 175+350 RHS Kanthale of Business Places of Business Places

Package 06 - (178km – 200km)

No. 108, Affected Front 115 - - Mr. K.K.Silva Kalmatiyawa, wall/roof extension KandyRoad, of Business Places 9 (175+370km)-RHS Thambalagamuwa

5 Mile Affected Front 290 Affected Front 270 Post,Kandy wall/roof extension wall/roof extension R.M.Hinnihamine Road, China of Business Places of Business Places 10 (191+535km)-RHS Harbour

1008,SunilCycle Affected Front 175 Affected Front 135 Mr.S.Sunil works, wall/roof extension wall/roof extension Anuradhapura of Business Places of Business Places 11 (195+320km)-LHS Junction

Affected Front 175 Affected Front 135 Mr.Prakash Rajam A2,Anuradhapur- wall/roof extension wall/roof extension 12 (195+325km)-LHS a Junction of Business Places of Business Places

Mrs.Elisamma Auto Plaza,1008, Affected Front 172 Affected Front 108 Anuradhapura wall/roof extension wall/roof extension 13 (195+337-km)-LHS Junction of Business Places of Business Places

Niroshan Affected Front 195 Affected Front 135 Stores,1008,Anu wall/roof extension wall/roof extension Mrs. S. Rajeshwaran radhapura of Business Places of Business Places 14 (195+342km)-LHS Junction.

Lional Munasinghe Affected Front 280 Affected Front 250 & Styores, Sriya wall/roof extension wall/roof extension Stores, 5 Kandy of Business Places of Business Places Rd., L.Munasinghe, 193+773km Anandakulama, 15 – LHS, Trincomaleee

M.Nallaiya 197+800km LHS Affected Front 180 Affected Front 125 ,No48,Kandt wall/roof extension wall/roof extension 16 Rd,Trincomalee of Business Places of Business Places

P.Rajendram, 197+820km LHS Mathusha Stationery Affected Front 170 Affected Front 140 Shop, wall/roof extension wall/roof extension No326,I.H.Road,Trin of Business Places of Business Places 17 comalee P.Rajendram, 197+840km LHS Mathusha Stationery Affected Front 190 Affected Front 125 Shop, wall/roof extension wall/roof extension No326,I.H.Road,Trin of Business Places of Business Places 18 comalee

Affected Front 205 Affected Front 125 No314,AMK.Hotel,Ka wall/roof extension wall/roof extension 19 S.Pradeepan, 197+898km LHS ndy Rd,Trincomalee of Business Places of Business Places

Table 8 Affected Permanent Sales Huts (Kanthale-Trincomalee Road Section)

No. Name of Affectee Address Affected Size Affected Size (Household Head) Property for Property as (Square feet) (Square feet) 19 meters per finalized corridor design

Package 05 - (157km – 178km)

A. Mawlana No. 8, Kalmatiyawa, Permanent Sales 40 Permanent Sales 40 KandyRoad, Hut Huts 1 (165+320km)-LHS Kanthale

M.H. Saruk Mullipothana,32, Permanent Sales 25 Permanent Sales 25 Kandy Road, Hut Huts 2 (173+310km)-RHS Kantale.

No.297, Unit 7, 97 Permanent Sales 55 Permanent Sales 55 S. Saparamadu Junction, Hut Huts Molipothana, Kandy 3 (174+200km)-LHS Road, Kantale.

Package 06 - (178km – 200km)

R.Ragunadan Permanent Sales 60 Permanent Sales 60 Mauran Hut Huts 4 (197+208km)-RHS saloon,Tricomalee

Angel Communication Permanent Sales 49 Permanent Sales 49 Main street,34, Hut Huts 5 (198+109km)-RHS Trincomalee

Moon Sky Shoo Permanent Sales 50 Permanent Sales 50 palace(closed) Hut Huts Moon Sky Shoo 6 (198+760km)-RHS Palace,Trincomalee

Table 9 Affected Lands (Kanthale-Trincomalee Road Section)

A-Agriculture lands, B- Barren Lands, R- Residential lands

No. Name of Address Affected Affected Size of Affected Size Affectee Property for % of total land Property as (m2) (Household 19 meters land holding per finalized 2 Head) corridor holding (m ) design

Package – 05 (157km-178km)

Land-A 1 D.M.Gunasingh New Palace, Kanthale 1.6% 1230 - -

Nuwan Stores, Kandy Land-R 1% 5200 - - 2 House (closed) road, Kanthale

No. 24, Junction, Land-A 7.7% 450 - - Molipothana, Kandy 3 P.D.M.K Perera Road, Kantale

k.Samansiri 15C, Kandy Road , Land-A 1.7% 1460 - - 4 Shantha Kanthale

Nimal Seela stores, 22 Land-R 3.2% 1250 - - 5 Gurusingha Junction,Kantale

Sunil Kalamatiyawa, Kandy Land-R 3.3% 950 - - 6 Gurusingha Road, Kanthele.

Sunil Kandy Road, Land-R 2.2% 875 - - 7 Gurusingha Kanthale

E. Botiyana watte, Land-R 3.4% 690 - - Wikkramarathn Kandy Road, 8 a Kanthale

R.J.M.P.Sanjee Sudeesha, 22, Land-B 2.6% 760 - - 9 wa Junction, Kanthale

R.C Mullipothana,10c, Land-A 1.9% 2350 - - 10 Nawarathna Kandy Road, Kantale

19C, Saumya Kumar Land-A 1.1% 2050 - - Road, 11 I.W. Premasiri Thambalagamuwa Government Land-R 0.6% 450 Land-R 150 (Police)land 173+685-173- Kandy road, 12 800km LHS Palampatar

Package 6 – (178km-200km)

Government Land-B 1.8% 8000 Land-B 250 land (Port Authority) 183+960- Kandy road, 13 184+100km -RHS Palampatar

Government Land-R 2.5% 1000 Land-R 100 land (SL. Army) 186+280- Kandy 14 186+400km RHS road,Kappalthurai

6th Mile Post, Land-B 3.7% 790 - - Chinabay, Sardapura Mrs. ,Kandy 15 S.Thilakawathi Rd,Trincomalee

Land-A 3.7% 675 - -

Mrs. M.H No. 634, 5th Mile Post, Nilanthi Kumari Gamunupura,Kandy 16 Da Sillva Road, Trincomalee.

Hansani stores ,5th Land-B 0.8% 1200 - - Mrs. S.A Mile Post, Chinabay, 17 Pramawathi Thrincomalee.

Mauran Land-B 0.9% 3560 - - 18 R.Ragunadan saloon,Tricomalee

156/3,Kandy Land-B 2.6% 950 - - 19 Mr. A.M Garnini Rd,Trincomalee.

Annex 06C Affected Privately Owned Trees Ambepussa – Dambulla and Kanthale – Trincomalee Road Sections

Table 1. Affected Privately Owned Trees

No. Name of Address No. of No. of Trees chainage Construction Affectee Trees Package (Household As per For 19m Head) designs corridor

1 R.Jayawardena Diganawatte, Ambepussa 02 01 1+120km)-LHS 01

Kurunegala Rd, 03 03 1+220km)-RHS 01 2 P.Tibbatugolla Ambepussa

Galgamuwa, 03 - - - 3 Lakshmi Perera Keppetiwalana, Alawwa

Dewattara, Wennoruwa, 01 - - - 4 W.T. Ramyasiri Alawwa

Nelumpokunagama, 01 - - - 5 O.P. Mendis Colombo Road, Alawwa

6 A.S. Dematage Jaya Mawatha, Alawwa 01 - - -

Yangalmodara, 07 04 12+200km-LHS 01 7 CGR Land Polgahawela

8 P.L. Samansiri 27, Giriulla 01 - - -

9 Distric Hospital Polgahawela 04 02 15+870km-RHS 01

10 P.H. Nandika 22 B, Tulhiriya 01 - - -

11 Herath Kumarage 12/c, Pothuhera 01 - - -

12 L.K. Dharmadasa 23, Galewela 01 - - -

13 S.P. Liyanagee Main Street, Dambulla 01 - - -

14 S.D. weerasinghe Old Street, Pothuhera 01 - - -

11C, Dambulla Rd, 02 - - - 15 J.H. Hemamala Kurunegala

Mahakonwewa, Hindagolla, 01 - - 16 S.H. Kamal Kurunegala

17 H.Adikaram 23, Mahakadawatha 05 03 24+080km-RHS 02

18 G.L. Kamalini Rathkarawa, Maspota, 01 - - - Kurunegala

Wewagedara, Hindagolla, 02 - - - 19 N.M. Bandara Kurunegala

Accident Ward, General 02 - - - 20 S.P. Gamani Silva Hospital, Kurunegala

21 W.N. Shayamali 5 A, Potuhera, Kurunegala 02 - - -

23a, Samanala Vasa, 01 - - - 22 F.G. Lahiru Pothuhera

23 S.M.J. Subasinghe New Town, Dambulla 01 - - -

Wasantha 01 - - - 24 Madamage 12, Main road, Allawwwa

25 W.M. Leela Kumara Vasa, Allawwa 01 - - -

12, Station Road, 01 - - - 26 F.M. Kamalasiri Polgahawela

10, Oruwala Road. 01 - - - 27 G.M. Lakmal Polgahawela

28 H.P. Juliyas New Road, Omaragolla 02 - - -

29 Wasantha Nisad Temple Lane, Omaragolla 03 - - -

30 J.P. Malaka Werasiri, Pothuhera 01 - - -

23/2, Dambulla Road, 02 - - - 31 R.Y. Lumad Galewela

Dambulla Road, 01 - - - 32 E.M.Kariyawasam Kurunegala

33 D.M. Udenis 32/3, Alawwa 01 - - -

st 34 S.I. Gamage 1 Lane,Melsiripura 01 - - -

35 E.M. Kamalawathi 1st Street, Kurunegala 02 - - -

New Vijaya Road, 04 - - - 36 P.L. Hiran Kurunegala

37 C.N. Jayakodi Temple Road, Alawwa 01 - - -

38 D.K. Mahasinghe Mihindu Mawatha, Thilhiriya 01 - - -

39 Asiri Herath Kumara Road, polgahawela 01 - - -

40 N. Malaka Welelanda, Pothuhera 01 - - - 41 LRC Land Panliyadda 04 04 64+350km-LHS 03

45A, Old Building, 01 - - - 42 B.M. Dharmasiri Dambulla

Hewage Furniture, 01 - - - 43 S.D. Ananda Dambulla

44 K.M.Suriyabandara Dam Rod, Panliyadda 07 04 65+220km-LHS 03

11C, Dambulla Rd, 01 - - - 45 S.M. Balasuriya Pothuhera

46 Upul Chandima Omaragolla,Panliyadda 02 01 66+480km-RHS 03

Dambulla Road, 15 11 66+840km-RHS 03 47 FD Land Panliyadda

Dharma Rathkarawa, Gokerella 02 - - - 48 Kodikara

49 Anil Nalaka Wewagedara,Melsiripura 03 - - -

50 C. Siriyawathi 23C, Allawwa 02 - - -

5 A, Dambulla Road, 01 - - - 51 W.P. Opatha Potuhera

Wasantha Uana, 23, 02 - - - 52 W.F. Hemantha Gokerella

53 F.K. Jaliya Girambe, Polgahawela 01 - - -

D.M. Bodirukkaramaya, 02 02 67+020km-LHS 03 54 Muthusinghe Dombepola, Panliyadda

Galgamuwa, 02 - - - 55 R.M. Darshana Keppetiwalana, Alawwa

Dewattara, Wennoruwa, 02 02 67+200km-RHS 03 56 F.M. Nalinda Panliyadda

Nelumpokunagama, 01 - - - 57 Q.M. Bandara Colombo Road, Alawwa

58 C.N. Perera Jaya Mawatha, Alawwa 01 - - -

59 f.K. Fernandoo 27, Giriulla 01 - - -

12, Damulla Road , 03 - - - 60 L.M. Bathiya Melsiripura

Senanayaka Mawatha, 01 - - - 61 S.V. Veerasekera Melsiripura

62 S.N. B. Jaliya Gamagewatth, Melsiripura 02 - - - 63 H.M. Nalinda Ramya Palace, Omaragolla 01 01 68+040km-LHS -

Nelumpokunagama, 01 - - - 64 Q.P.Rajesh Colombo Road, Alawwa

65 F.B. Chaminda Crown Plaza, Omaragolla 01 01 68+108km-RHS -

66 S.M. Kanthilatha New Town, Melsiripura 02 - - -

67 A.M. Lankasiri 1st Street, Kanadana 04 02 72+120km-LHS -

New Vijaya Road, 02 - - - 68 G.Suriyaarachchi Melsiripura

Temple Road, 02 02 72+500km-LHS - 69 Saman Gamii Kanadana

70 F.G. Laksiri Ambanpola, Melsiripura 01 - - -

71 S.P. Pathmasiri 22 C, Melsiripura 01 - - -

38 B, Dambulla Road, 02 02 73+010km-LHS - 72 W.F. Gamini Kanadana

S. 30 B, Kumbukgete 01 - - - 73 Kanakasooriya Road, Melsiripura

74 J.L. Kamini 119, Mahamaukalanyaya 01 - - -

Mahakonwewa, 02 02 73+400km-RHS - 75 S.P. Hemamala Hindagolla, Kanadana

Mahakonwewa, 01 - - - 76 F.L. Kamini Hindagolla, Kurunegala

Affected privately owned trees- Kanthale-Trincomalee

Road Section

No. Name of Address No. of No. of Trees chainage Construction Affectee Trees Package & (Household As per For 19m Head) designs corridor

62, Kandy Road, 04 01 167+200km-LHS 05 77 G.A.D Anura Kanthale

Seela stores, 22 08 05 169+320km-LHS 05 78 Nimal Gurusingha Junction,Kantale Kalamatiyawa, 07 05 169+850km-LHS 05 Kandy Road, 79 Sunil Gurusingha Kanthele.

Kandy Road, 04 02 170+050km-RHS 05 80 Rasika Perera Kanthale

Botiyana watte, 05 03 194+230km-RHS 06 Kandy Road, 81 E. Wikkramarathna Trincomalee

Sudeesha, 22B, 08 - - - 82 R.J.M.P.Sanjeewa Trincomalee

,No48,Kandt 01 01 06 83 M.Nallaiya Rd,Trincomalee

,J.R.S.Shipping 03 03 06 Pvt.Ltd.268, Inner Harbor 84 J.F.Jeganathan ,Trincomalee

,No261,Inner 06 05 06 85 S.Benjamin Harbor,Trincomalee

,No254A,Inner 01 01 06 harbor , 86 Jabeena Behem Trincomalee

,No252,Inner 02 02 06 harbour 87 S.D.Nazardeen ,Trincomalee

, Kandy Rd. 03 01 06 88 S.P. Nimal Trincomalee

Inner harbour Rd. 03 02 06 89 S. Ariyawathi, Trincomalee

Ceylon Cold , Inner harbour 02 02 06 90 StoresTrincomalee road, Trincomalee

91

92

Annex 07 Affected Temporary sales outlets

Ambepussa – Dambulla Road Section

Table 1 Affected Fish Stoles ( Ambepussa _ Dambulla Road Section)

Name of Package Fish Name & Address of the Affected For 19m As per Junction/Township/ stole persons corridor designs Urban center Pothuhera 02 1 W. Godvin, Kahatawatte , Pothuhera √ √ Kurunegala 02 1 S. Martin, Dambulla Road,2 Junction, √ √ Kurunegaa Melsiripura 03 1 S,Sirisoma, Dambulla Road,Melsiripura √ √ 62km Post 03 1 Agonis Perera, Kopikele,Omaragolla √ √ Omaragolla 03 1 Adrian Somage,Sampathuana, √ √ Omaragolla Temple Junction 03 2 S. Ranjith, Grocerry Road, Omaragolla √ √ D. Andiris, Linda Road, Omaragolla Welakumbura 04 1 S.Amarapala, Vendesiwatte, √ √ Welakumbura Dangasmeepe 04 2 A.P. Sethpala, 23, Kumburaliyyadda, √ √ Dangasmeepe

Table 2 Affected Lottery Stoles ( Ambepussa _ Dambulla Road Section)

Name of Package Lottery Name & Address of the affected For 19m As per Junction/Township/ Stole persons corridor designs Urban center Ambepussa 01 1 S.P. Siripala, 22c, Nayomi, Ambepussa √ √ Thulhiriya 01 1 M.C. Pathirana, Mihindu Lane, Allawwa √ √ Polgahawela 01 1 W.P. Marikkar, Nuge Road,28, √ √ Polgahawela Pothuhera 02 4 R.Mendis,34A, Dambulla Rd. Pothuhara √ √ Nuwan Silva, Old Road, Pothuhera S.P. Kamalawathi, Illukhena 5B, Pothuhera Nasim Ansur, 234,Main Road, Pothuhara Kurunegala 02 2 A.M. Balasinghe, √ √ Uhumeeya,10A,Kurunegala Anura Gamini, 1st Lane, Puttalam Rd, Kurunegala Ibbagamuwa 02 1 Nivas Abdul, Corner House, 22, √ √ Ibbagamuwa Gokerella 03 1 S.P. Sumanawathi, DavuluWatte, √ √ Gokerella Melsiripura 03 3 D. Siripala, Walakumbura, Melsiripura √ √ A.Pathrathne, Kirikade,23, Melsiripura Beligamuwa 03 1 D. Anthonis,Govipola Road, Beligamuwa √ √ 62km Post 03 2 Nisal Silva, Yohan Watte, Galewela √ √ Suramya Perera, Yatapara,23/2,Galewela

Galewela 04 1 S. Setharan, Temple Road, Koratuwa, √ √ Galewela

Welakumbura 04 2 S.Kusumawathi,Ipanella √ √ Watte,18c,Welakumbura M.P. Magaret, Saliya Road, Galewela Dangasmeepe 04 3 Amarasena Kankanama, Kumarawatte, √ √ Dangasmeepe W.Sumathipala, Devala Road, Dangasmepe S.M. Abesinghe, 14B/2, Cros Road, Dangasmeepe

Table 3 Affected Vegetable Stoles ( Ambepussa _ Dambulla Road Section)

Name of Package Vegetabl Name & Address of the Affected For 19m As per Junction/Township/ e stoles persons corridor designs Urban center Ambepussa 01 1 S. Piyasuriya,12A, Kandy √ √ Road,Ambepussa Alawwa 01 1 W. Nihal,Saman Book Shop, Alawwa √ √ Pothuhera 02 2 Seneviratne Kumara,104C Dambulla √ √ Road, Pothuhera W.S. Sirinimal,School Road, Pothuhera Kurunegala 02 1 N. Amarasiri, 40C,Kandy Road, √ √ Kurunegala Gokerella 03 1 S.Basnayake,Dambulla Road,Gokerella √ √ Melsiripura 03 2 Anil Perera, Watte,Melsiripura √ √ Samila Sedara, Nilpita,19C, Melsiripura Beligamuwa 03 1 Wasantha Sedara, Saummya √ √ Road,Beligamuwa 62km Post 03 2 David Perera, 1st Lane,Kurunegala √ √ S.Amarasuriya, Temple Road,23,Uhumeeya

Puwakgaha Junction 03 4 A.Nandasiri, 12, Jaya Road, Pothuhera √ √ S.M. Anifa, Main Streetm Polgahawela S.L. Kamala, Miriskade, Puwakgaha Junction S.Podisingha,Nilantha Bakery,Puwakgaha Junction

Temple Junction 03 2 Amarasiri Gamini, Wattekade, √ √ Ambepussa

Wasantha Siri, Old Building,76C,Polgahawela Aluthkade 03 3 A.S. Dematage, Kasmi, 23/2, √ √ Polgahawela

Sevandi Samasinghe, Kapuruwatte, Polgahawela

Sathis Nimesh, Keera Kotuwa, Pansala Para,Polgahawela

Welakumbura 04 2 Anila Pemadasa, School Rd,Welakumbura √ √ Agonis Santhyago.Kumara Road,Welakumburs Pohorawewa 04 1 Karunasena Sampath, Dambulla √ √ Dangasmeepe 04 2 S.Sirilina, Parana Kade,Dangasmeepe √ √ A.Podiappuhami,16/3 Dangasmeepe

Table 4 Affected Green Gram Seller ( Ambepussa _ Dambulla Road Section )

Name of Package For 19m As per Junction/Township/ Green Name & Address of the corridor designs Urban center gram Affected persons seller Thulhiriya 01 1 S.Sena, 67C,Kurunegala √ √ Road,Thulhiriya Gokerella 03 1 Saman Hewa, Temple Road, √ √ Gokerella Dangasmeepe 04 1 Amrasiri Perera, √ √ 82c,Dangasmeepe

Table 5 Affected Three-wheelers Parking stands ( Ambepussa _ Dambulla Road Section )

Name of Package No. of Three Wheeler Parking stands For 19m As per Junction/Township/ corridor designs Urban center Ambepussa 01 2 √ √ Thulhiriya 01 2 √ √ Alawwa 01 1 √ √ Polgahawela 01 1 √ √ Pothuhera 02 4 √ √ Kurunegala 02 2 √ √ Ibbagamuwa 02 2 √ √ Gokerella 03 1 √ √ Melsiripura 03 4 √ √ Beligamuwa 03 1 √ √ 62km Post 03 5 √ √ Omaragolla 03 1 √ √ Aluthkade 03 1 √ √ Galewela 04 1 √ √ Kanadana 04 1 √ √ Yatigalpotha 04 1 √ √ Pohorawewa 04 1 √ √ Welakumbura 04 5 √ √ Dangasmeepe 04 6 √ √

Affected Temporary sales outlets

( Kanthale – Trincomalee Road Section)

Table 1 Affected Fish Stoles (Kantale –– Trincomalee Road Section)

Name of Package Fish Name and Address of For 19m As per Junction/Township/ stole Affected corridor designs Urban center Persons Kanthale 05 1 Viliom Perera, New Town, √ √ 25/2, Kantale Chinabay 06 1 M.H. Hasheen. Beach Road, √ √ Trincomalee Front Street, Trincomalee 06 1 A.M. Aswan, Babykade, √ √ Trincomalee Mollipothana 06 1 Adiris Silva, Temple Road, √ √ Kahatawatte, Mollipathana

Table 2 Affected Lottery Stoles (Kantale –– Trincomalee Road Section )

Name of Package Lottery Name and Address of the For 19m As per Junction/Township/ Stole Affected Persons corridor designs Urban center Kantale Hill 05 1 Amarasiri Perera, Heenwewa √ √ Road, 1st Junction, Kantale Chinabay 06 1 S. Wardaraja, Main Street, √ √ 80/2A, Trincomalee 98 Junction 06 1 M.Salinda, Morahena Road, √ √ Kapurukele, Kantale

Table 3 Affected Vegetable Stoles (Kantale –– Trincomalee Road Section )

Name of Package Vegetable Name and Address of For 19m As per Junction/Township/ stole the Affected Persons corridor designs Urban center Chinabay 06 1 A.M. Madeena, School Road, √ √ Cros Road,Trincomalee 93 junction 05 1 Wasana Perera, Wewa √ √ Road,Kantale Kanthale 05 1 Malik Kamal, 35, Kumbuk √ √ Road,Welewatte, Kantale Mollipothana 06 1 Simion Appuhami, √ √ 52/A,Pokunupara, Mollipathana

Table 4 Affected Green gram Sellers (Kantale –– Trincomalee Road Section)

Name of Package Green Name Address of Affected For 19m As per Junction/Township/ gram Persons corridor designs Urban center seller Kanthale 05 1 W.S. Kamalshantha √ √

Table 5 Affected Three Wheeler Parking stands (Kantale –– Trincomalee Road Section)

Name of Package Three Wheeler Parking For 19m As per designs Junction/Township/ stands corridor Urban center 98 Junction 05 2 √ √ 97 Junction 05 2 √ √ 96 Junction 05 1 √ √ 95 Junction 05 1 √ √ 93 junction 05 - √ √ 92 Junction 05 1 √ √ Kantale Hill 05 1 √ √ Kanthale 05 2 √ √ Front Street, Trincomalee 06 1 √ √ Chinabay 06 2 √ √

Annex 08 – Vulnerability & Gender

a. Vulnerability - The study focused on vulnerability of the groups such as disability, war injuries, old age, widows (women headed families etc.).

The study team has found four (04) war casualties in the proposed project area. Seven disable persons have been reported in the affected population. There are 23 old persons (age more than 67) among the affected population and 19 women headed families were found. The details of the above are given in the table 1.

Table 1 Vulnerable persons due to war, disability and other reasons

Ambepussa – Kanthale- Dambulla Trincomalee Vulnerability Road Section Road Section War injuries 04 01 Disable 06 01 Old persons 16 07 Women Headed families 14 07 Total 40 15

Source- Social Survey for RAP, 2010

There is a considerable number (21) of affected female headed families in the proposed project area (Table 2). Extra attention should be made to ensure the livelihood of these families during and after completion of the project.

Table 2 Number of Total Project Affected Female Headed Families by Ethnicity Road Sector Sinhalese Tamils Muslims Other Total Ambepssa- 09 04 01 - 14 Dambulla road Kanthale- 06 01 - - 07 Trincomalee road section Source - Social Survey for RAP- 2010

Total number of population of these families is 90. Among these total women headed families males (53) are higher than females. Number of female is 37. Female within age group 27 – 36 is higher than other age groups. There are only Five (05) old persons living in the female headed families Table 3.

Table 3 Sex and age group of Female headed families by road sections (A06). Ambepussa- Kanthale- Dambulla section Trincomalee section Age group Male Female Male Female 0 -5 3 2 2 3 6 -16 4 2 3 2 17 -26 3 3 - 1 27 -36 2 8 5 1 37 - 46 15 3 4 5 47 - 56 3 1 1 1 57 - 66 2 2 1 1 67 >. 2 1 1 1 Total pop 34 22 19 15

Source – Social Survey for RAP – 2010

Female headed families are the most suffering group among these vulnerable groups. The main income of all such families is conducting small scale business such as selling food items. d. Gender - Many sociologists have identified, Sri Lankan societies comprised of male – headed or father – based families. The proposed project area of Ambepussa - Dambulla falls into rural, economically backward geographical region. Therefore women have to participate in economic activities and other social and personal matters.

The proposed road rehabilitation project of Ambepussa – Dambulla and Kanthale - Trincomalee would be a great step to solve the gender related problems in the project area particular to rural and economically backward project affected people of these road sections.

ANNEX 09 – STAKEHOLDERS CONSULTED DURING THE SURVEY

Name of the Permanent Place & date of Occupation/Position Stakeholder Address consultation S. Kamala 238, Dambulla Galewela / 03.02.2010 Shop Owner Road, Galewela .PS Mazee 322 C, Galewela / 03.02.2010 Travel Agent Dambulla Road, Galewela PS Mawlana 302 K, Galewela / 03.02.2010 Transport Agent Dambulla Road, Galewela M Meena 43/2, Dambulla Galewela / 03.02.2010 Broker Road, Galewela P Shatamale 73/2, Dambulla Ambepussa / 12.02.2010 Private Bus Owner Road, Galewela W Nayana Sisirapura, Galewela / 03.02.2010 Vegetable Seller Galewela Sani Ellepola Matale Galewela / 03.02.2010 Shop Owner Junction, Galewela S Nayanatikiri 221, New Road, Galewela / 03.02.2010 Student Galewela R Swarnasiri Kota Road, Ambepussa / 12.02.2010 3 Wheeler Driver Temple Junction, Galewela Ranjith Bandara Karawwewa, Ambepussa / 12.02.2010 Administration Officer Gokarella M Swarnapala 10B, Dambulla Kurunegala / 13.02.2010 Social Development Road, Gokarella Officer UAN Sanjeewa Karawwewa, Dambulla / 13.02.2010 House Wife Gokarella DA Nisanam Havanthanna, Kurunegala / 13.02.2010 Student Panliyadda UG Pushpasiri Havanthanna, Dambulla / 13.02.2010 Road User Panliyadda P Rohana 111 C, Raja Kurunegala / 13.02.2010 House Wife Mawatha, Karawwewa, Gokerella P Ranjith 221 Melsiripura / 13.02.2010 CTB Bus Driver Kemburana, Melsiripura MD Wimalaratne Police Head Trincomalee/16.02.2010 Employment Agent Qutas,Trincomale e

JAG Jayaratne C/o Silva Kurunegala / 13.02.2010 House Wife Stores, Akkara Panaha, Melsiripura HA Shantha Mukalanyaya, Melsiripura / 13.02.2010 Road User Melsiripura BH Thilakasiri Hewage Kurunegala / 13.02.2010 Teacher Furniture, Dambulla Road, Melsiripura A Munasingha Ambanpola Pothuhera / 12.02.2010 Member of Pradesiya Junction, Shaba Melsiripura WRR Wijesingha Ambanpola, Pothuhera / 12.02.2010 Disabled person Melsiripura W Islabdeen 22 C, Pothuhera / 12.02.2010 Road User Melsiripura SP Sumanaweera 38 B, Dambulla Melsiripura / 13.02.2010 Farmer Road, Melsiripura RP Senaratne 30 B, Dambulla / 13.02.2010 Road User Kumbukgete Road, Dambulla SP Saroja Muthusela Kurunegala / 13.02.2010 Bank Officer Road, Melsiripura Ramya Ratnaweera New Road, Melsiripura / 13.02.2010 House Wife Melsiripura P Muthugama Sirasa, 40 B, Melsiripura / 13.02.2010 Transporter Melsiripura MM Ahamad 176,lower Trincomalee/16.02.2010 Businessman road,Trincomalee

P Siriyawathee 22, Melsiripura Melsiripura / 13.02.2010 House Wife

RR Nandani 97 Kantale /17.02.2010 House Wife Junction,Galmati yawa ,kantale

SM Jayasiri Anuradhapura Trincomalee/16.02.2010 Public Health Inspector junction,Trincoma lee

RP Udayakumara 30 A, Dambulla Dambulla / 13.02.2010 Motor Mechanic Road, Ibbagamuwa MK Athula Keeradeniya, Pothuhera / 12.02.2010 Transporter Ibbagamuwa S Sumanasiri 28, New Road, Pothuhera / 12.02.2010 Technician Ibbagamuwa Mendis Perera 27/2, Dambulla Pothuhera / 12.02.2010 Pawn Broker Road, Ibbagamuwa SN Madawan Filling Station, Kurunegala / 13.02.2010 Manager – Filling Station Ibbagamuwa D Wilbert Udawela, Kurunegala / 13.02.2010 Businessman Ibbagamuwa M Agoris 135/5,Harber Trincomalee/16.02.2010 Farmer Rd,Trincomalee

IA Malani Dambulla Road, Kurunegala / 13.02.2010 House Wife 23/2 Dambulla W Sisirakumara 22/3, Puttalam Kurunegala / 13.02.2010 Road Engineer Road, Kurunegala Naveen Kumara Ministry of Kurunegala / 13.02.2010 Agricultural Officer Agriculture, Dambulla Road, Kurunegala A Amarasiri 773 A, Kurunegala / 13.02.2010 House Owner Dambulla Road, Kurunegala KMM Jayawickrama 119, Dambulla / 13.02.2010 Visitor Mahamaukalan yaya J Kalum Sanjeewa 1st Lane, Kantale /17.02.2010 Student Kantale Chandika Mahakonwewa, Kurunegala / 13.02.2010 House Wife Wijesinghe Hindagolla, Kurunegala SRMPC Rathkarawa, Kurunegala / 13.02.2010 Businessman Samaradiwakara Maspota, Kurunegala PIA Vithanage 55,Barathipuram, Trincomalee/16.02.2010 Businessman kenya rd.Trincomalee

Sanjaya Herath Accident Ward, Pothuhera / 12.02.2010 Medical Practitioner General Hospital, Kurunegala MUM Faizar 5 A, Potuhera, Kurunegala / 13.02.2010 Businessman Kurunegala LP Piyasena 24/8,Sendybay Trincomalee/16.02.2010 Road User ,Trincomalee

S Swarna Sir John Melsiripura / 13.02.2010 Teacher Kotalawala MV, Kurunegala R Rathnaweera General Alawwa / 12.02.2010 Doctor Hospital, Kurunegala WP Sriyani 70B, Uhumiya, Kurunegala / 13.02.2010 Road User Dambulla Namal Suraweera 26/2, Dambulla / 14.02.2010 Businessman Kurunegala W Piyaratne Traffic Branch, Pothuhera / 12.02.2010 Police Officer Police Station, Potuhera MC Rathna Rajagama Melsiripura / 13.02.2010 3 Wheeler Driver Road, Dambulla T Punchihami 22, Potuhera Alawwa / 12.02.2010 Vegetable Seller S Jayatissa 18, Main Road, Pothuhera / 14.02.2010 Fish Seller Polgahawela KP Jagath Kumara Girambe, Polgahawela / 15.02.2010 Lorry Driver Polgahawela Rev Nandasiri Bodirukkarama Ambepussa / 12.02.2010 Clergy ya, Dombepola, Yatiyantota YMPB Yapa 155,Nimal pura, Alawwa / 15.02.2010 Road User Trincomalee

HPD Dias Sanjeewa 25, New Town , Alawwa / 15.02.2010 Truck Driver Kanthale WMDA Wijesekara Nelumpokunag Thulhiriya / 12.02.2010 Trading ama, Colombo Road, Alawwa R Upatissa Jaya Mawatha, Thulhiriya / 12.02.2010 Lottery Seller Alawwa S Tennakoon 27, Giriulla Thulhiriya / 12.02.2010 Clerk L Sirisoma Wijaya Road, Thulhiriya / 12.02.2010 Clerk S Siriyawathee 22 B, Tulhiriya Ambepussa / 12.02.2010 Business person Ranjith Sujeewa Ambepussa Ambepussa / 12.02.2010 Road User Junction, Ambepussa N. Sripala Ambepussa Ambepussa / 12.02.2010 Businessman Junction, Ambepussa S. Somasiri 2, Ambepussa / 12.02.2010 3 Wheeler Driver Sarasavi,Ambep ussa HRR Suranimala Mahena, Thulhiriya / 15.02.2010 Road User Ambepussa D. Kumara 14, Madala Thulhiriya / 15.02.2010 Private Bus Driver Polgahawela Kasun Nimas 1st Lane, Kantale /17.02.2010 Student Kantale R.O. Pemasiri Hindagolla, Kurunegala / 13.02.2010 House Wife Kurunegala W.M. Sarath Rathkarawa, Kurunegala / 13.02.2010 Businessman Maspota, Kurunegala S.M. Kulasiri kenya Trincomalee/16.02.2010 Businessman rd.Trincomalee

Athula Perera General Pothuhera / 12.02.2010 Male Nurse Hospital, Ibagamuwa Achala kumari New Town Kantale /17.02.2010 Student Lane, Kantale M. Lal hewamini Mahakonwewa, Kurunegala / 13.02.2010 House Wife Hindagolla, Kurunegala S.V. Kapila Rathkarawa, Kurunegala / 13.02.2010 Businessman Maspota, Kurunegala N. Balasuriya 12,Barathipuram, Trincomalee/16.02.2010 Businessman kenya rd.Trincomalee

A.N. Malaka 101,Puttalam Pothuhera / 12.02.2010 Driver Road, Kurunegala S. Saparamadu New Town Kantale /17.02.2010 Businessman Lane, Kantale Y. Asela Perera Hindagolla, Kurunegala / 13.02.2010 Engineer Kurunegala W.S. Kodikara Colombo Road, Alawwa G.H. Hemantha 18, Main Road, Pothuhera / 14.02.2010 Polgahawela Amal Ganhewa 97 Kantale /17.02.2010 Administrator Junction,Galmati yawa ,kantale

J.M. Jayalath Maspota, Kurunegala / 13.02.2010 Carpenter Kurunegala G.H. Laksiri 22/3, Puttalam Kurunegala / 13.02.2010 Police Officer Road, Kurunegala S.W. Jinasiri Anuradhapura Trincomalee/16.02.2010 Mechanic junction,Trincoma lee

Kamal Fernando Matale Galewela / 03.02.2010 Teacher Junction, Galewela Hemakumari Silva Dambulla Road, Galewela / 03.02.2010 Planning Officer Galewela G.M. Kamalsiri 15 A, Potuhera, Kurunegala / 13.02.2010 Samurdhi Manager Kurunegala S.W. Jayampathi Ambanpola Pothuhera / 12.02.2010 Work Supervisor Junction, Melsiripura H.D. Sandaruwan kenya Trincomalee/16.02.2010 Agriculture Officer rd.Trincomalee

S.M. Lakshman Sisirapura, Galewela / 03.02.2010 Assistant Manager Galewela A.N. Nayanakantha Matale Galewela / 03.02.2010 Technician Junction, Galewela

Government of Sri Lanka Roads Sector Assistance Project II

Terms of Reference for Preparation of Social Impact Assessment

1. Introduction

The Government of Sri Lanka (GOSL) has requested financing from the World Bank to assist them to rehabilitate, improve and maintain the national roads network with an objective to achieve improved and sustainable road transport by enhancing the durability, efficiency and economic impact of the national road network. The proposed projects will only focus on rehabilitation1, improvement2 and maintenance3 of national roads selected through a strategic study, in order to facilitate economic activity in the areas served and provides users with better road safety conditions. The Road Sectors Assistance project- II will address rehabilitation of A and B class national roads traversing across Eastern, North Central, North Western Central and Western provinces. The executing agency will be Ministry of Highways and Road Development whilst the implementation will be carried out by the Road Development Authority (RDA). The proposed road sections Nochchiyagma-Anuradhapura-Trincomalee, Kanthale- Trincomalee, Ambepussa-Habarana and - of 300 km have been prioritized based on the Road Sector Master Plan adopted by the RDA. It is expected that a conflict assessment will be carried out prior to confirmation. The project will build on the lessons learnt from the Road Sector Assistance project ( CR 4138 CE) closing in march 2011 and is expected to address the maintenance of national roads as well as road safety.

Projects and Programs financed with IDA resources need to comply with World Bank Operational Policies. Therefore, sub-contracts and components eligible for funding under this project will be required to satisfy the World Bank’s safeguard policies, in addition to conformity with social policies of the GoSL. The activities to be financed by the project do not have the potential to trigger significant negative social impacts. It is anticipated that environmental and social issues and impacts would be minimal for road rehabilitation and maintenance projects.

1 Rehabilitation: Bringing existing deteriorated roads to previous/original conditions. It will likely to involve improving drainage/slopes/embankments/other structures, strengthening pavements, complete resurfacing and recuperating civil works. All of the work is done on the existing platform or right of way and no additional land acquisition needed. 2 Improvements: Improving road specifications. Most of the work is done on the existing platform or right of way. Additional land acquisition may be needed. Activities include widening lanes and shoulders, adding extra lanes in steep inclines, improving curves and strengthening bridges. 3 Maintenance: Routine or periodic works to maintain the road in working conditions. All of the work is done on existing platform. It may include routine works, patching potholes, clearing drains, etc. and periodic works such as resurfacing, line marking and bridge maintenance. However, if there are improvements such as widening lanes and shoulders, adding extra lanes in steep inclines, etc. depending on the road locality, there may be possible impacts to the environment and people where the existing roads are running through or closer to forested areas, wetlands, settlements, business premises, etc. There may also be social impacts in terms of loss of land and other assets/infrastructure /livelihood located on the land, particularly if the ROW is insufficient to meet the design needs; impact on Indigenous Peoples; and vulnerable. In addition, all IDA funded interventions are required to conform with the “conflict filters” in order to help mitigate the reputational risks to the Bank, and to enhance development effectiveness by ensuring that opportunities for addressing the causes and consequences of the conflict are pursued to the maximum extent.

2. Description of the project components including the selected road list to be covered under this SIA. Also discuss the alternatives reviewed prior to selection of these roads and how these were selected ( consultation should be undertaken for the selection)

3. Potential Social Issues: The roads identified for the improvement is existing A and B class roads. The proposed construction activities involve widening to at least two lane operations with improvement of the surface, construction of side drains, widening or replacement of culverts and bridges, removal of the roadside structures and trees. The project does not envisage acquisition of land but to remain within the existing Row. The critical social impacts are the following:  Conflict: Most of the project is emerging out of a long conflict and the  Transparent distribution of benefits: ensure that benefits reach all groups in the communities  Inclusion: This is another critical issue in this area and there is a feeling of exclusion by some groups. The SIA will make extra efforts to include every ethnic and religious groups including men, women and youth.  Vulnerability: The SIA will focus on vulnerability of the groups from the point of view of social and economic vulnerability, and those as a result of physical causes (disability, war injuries, old age, orphans, widows etc.)  Gender: Women and children are a major victim of all conflicts. The SIA will focus on this group along with men and bring out the implication of the interventions (both positively and negatively). In addition all information and data will be disaggregated by gender and ethnic and religious groups.  Risks: The SIA will highlight the social risks anticipated in the implementation of the project.

 From the perspective of compensation, the Report will focus on the following;  Land: assess the quantity of land that will be required and the mode of acquisition. Voluntary donation cannot be used for land where the requirement is known at preparation stage. In addition the urgency/emergency clause will not be used in the absence of a situation or urgency/emergency.  Encroachers/squatters: There may be encroachers /squatters owning property /livelihood on the roads. Any squatter or encroacher impacted by the project will be compensated for assets/infrastructure under the entitlement matrix. All non title holders are eligible to payment for assets/infrastructure and lively hood restoration. Only for payment of land a title will be required.  Assets: There may be privately owned/community owned assets that may be impacted and will need to be compensated at replacement value, market price.  Infrastructure; There may be infrastructure privately/community owned or owned by the government on the roads and will be compensated at replacement cost or replaced.  Utilities: All utilities impacted will be removed and compensated  Access: The project will not obstruct access to households/businesses etc. during construction. Alternate access will need to be provided and should be documented in the Report  loss of livelihood : loss to business or loss of livelihood of vulnerable persons will be compensated/restored/  Any other impact not presently envisaged but identified during preparation of the Social Impact Assessment and compensated accordingly.

4. Methodology: The consultant will use a mix of quantitative and qualitative methods.

Qualitative analysis: Stakeholders Consultations will be undertaken with all the communities in the project area while being mindful that road widening and other construction activities might be undertaken in socially and politically sensitive areas, particularly with a record of conflict. The consultant will be particularly cognizant of the conflict situation and prepare robust consultation plan to include all sensitive issues, and groups focusing on the vulnerability of each group. The consultations will focus on ways to ensure that there is no favoritism in the distribution of benefits and transparency has been maintained in all aspects of the projects, and ensure that all consultations send this message out. All consultations must be inclusive of men, women and youth. In addition to the above, the qualitative aspects of the report the consultant will also undertake the following: i). Social Screening: identify in detail, possible social and political impacts (positive and negative) that may arise as a result of the different types of works; Based on the potential impacts identified above, undertake detailed and specific assessments of social impacts for the interventions and prepare derailed and practical social and political impact assessment. ii) Carry out specific consultation with likely affected communities and visit all identified roads to develop strip map and indicate all information on structures, utilities and land use that is likely to be affected within the project impact zone. (List of consultations with identification of groups consulted, date of consultation, issues discussed, etc. to be provided in the annex) iii) Scope out all social issues for which detailed impact assessment would be required and analyze major and minor social impact issues including - identification of congested areas, accident prone zones, loss of assets, livelihood, poverty, gender and health issues and estimate the economic and social impacts on people and land. iv) Establish the likely types of economic and social impact on people including on private land, traditional and customary rights, lease land, common property resources, religious sites, different usage of legal right of way (if and where applicable). v) Identify possible social risks to proposed mitigation measures. Stakeholder consultations will be used at all phases of the study beginning from selection of roads up to preparation of mitigation measures. Consultations will use group meetings, focus group discussions, information provided by key informants etc.

Quantitative analysis: The report will use secondary and primary data/information. The consultant will undertake: a) a socio economic sample survey of the project area. This will include information on socio economic indicators including but not limited to poverty levels, health education indicators along with facilities providing these services, information on income levels and sources of employment, types of hoses and types of families ( nuclear, extended etc), information on sources of drinking water, sanitation, etc. all information will be disaggregated by gender. b) census of all project affected persons and assets. This will include the following i. A census of all affected persons (provide names and ID in the annex) ii. An income and asset survey for all assets/ infrastructure /income impacted both of individuals and community owned (details in the annex with photographs for loss of assets) iii. An engineering estimate of the asset/infrastructure lost iv. An estimate of all utilities to be impacted. v. A cost estimate of all losses (at replacement cost and market prices)

Cutoff date: A cutoff date will be announced by the consultant. This is the date the SIA is initiated. Any person moving into the areas subsequent to the announcement of the date will not be an eligible affectee.

5. Outcome: A social impact assessment report with i) social analysis of impacts and risks along with ii) detailed report laying the magnitude of social impacts ( i.e. number of affected persons, assets infrastructure livelihood etc, of loss of as provided in the methodology) and iii) social mitigation measures.

The SIA Report will thus cover the following broad areas:

1. Executive Summary

2. Background of the geographic area and justification for the Project bringing in the economic perspective as well as bringing out inclusion of all groups particularly those affected by conflict. Description of overall economy of Sri Lanka, socioeconomic indictors, trade, poverty indicators, composition of its people, any indigenous groups etc. Description of the potential project with components. Description of the methodology used for the Report.

3. Baseline information of the project area.

4. A conflict analysis: This needs to provide an analysis of the conflict and its implication for the project. It should also recommend ways to enhance development effectiveness by ensuring that opportunities for addressing the causes and consequences of the conflict are pursued to the maximum extent possible by the project. The SIA will make major sustained efforts to identify the underlying sources, undertaken extensive consultations with all groups individually and collectively where possible, and formulate recommendations including recommendations to strengthen inter- ethnic reconciliations that the project can implement,

5. A gender analysis: The gender analysis will provide the status of gender focusing particularly on women, their roles in society and the economy; participation in the labor force and employment status, sectors where they are most visible in the economy, along with opportunities and constraints they face. Lay out the number and percentage of female beneficiaries of the project (a beneficiary in the broadest term is a person benefiting from the project -- from improved service delivery, user of improved road, participant in the training program etc.)

6. A legal framework: This should provide the laws and regulation of Sri Lanka that the project will use along with the Social Safeguards Policies of the Bank along with an assessment of the social operational policies that will be triggered by the project along with suggested mitigation measures to respond to these Operational Policies.

7. A detailed analysis of key social impacts particularly the positive and negative impacts along with severity and magnitude of impacts (refer to potential social issues detailed above). The social issues will also focus on conflict and social risks with explicit linkages between identified social issues and elements of the project design.

8. Stakeholders Consultation: Analysis and assessment of consultations held with issues identified by different groups of stakeholders and its incorporation in the design. This may include among other, round table consultations, field consultations, Focus group discussion, meeting with key informants, etc. The stakeholders identified and covered will be both primary and secondary stakeholders including project beneficiaries in the communities; Project affectees i.e. anyone adversely impacted; Civil Society Organizations, Institutional stakeholders; relevant government ministries, departments, agencies, and other donors. Gender must be represented and documented.

9. Develop social mitigation plans ( RP/ARP) as required : this will be a stand- alone document taking the information from the SIA and have the following chapters:

a. Background of the project b. The project components. How was the project roads selected? Provide justification for the alternatives reviewed and the present components selected. Consultations will need to be undertaken to reflect the choice of all groups in the selection of the roads and also ensure that it meets the requirements of the communities. Ensure that all communities benefit without any biases and all were consulted.

c. Lay out the positive and negative impacts along with magnitude of impacts. The direct negative impacts should be laid out in a table (these are the impacts that will be compensated, see impacts in the earlier part of the ToRs for details).

 d. Consultations held (taken from the SIA) also provide a consultation strategy that the project will implement during the implementation phase.

e. Mitigation measures recommended including the Entitlement Matrix, principles to be followed in the RP/ARP for social mitigation along with the legal framework. Cost methodology to be used for the different negative impacts that will be compensated.

f. Implementation mechanism: i) Develop an implementation mechanism to implement the social mitigation plan focusing on the roles and responsibilities of the different players. ii) Details of the Grievance Redressal Mechanism both formal and informal at the different levels of the project. The grievance redressal mechanism should be transparent, accessible to all groups, be unbiased, and reflect all ethnic /religious groups in its composition. iii) A M&E framework including a brief list of indicators, reporting format with timelines; iv) Training and capacity building for different levels of staff of the Project to meet the projects goals v) HIV/AIDS training program; Suggest recommendations for implementing a HIV/AIDS program along with target for receiving the training.

10 Budget: The budget should contain all the social costs for assets/utilities, including those for training, M&E etc.

All information in the report will be disaggregated by gender where possible. The report will be in English and its executive summary will not be longer than 5 pages containing all relevant issues and conclusions. The annex will provide details of all the main chapters in terms of tables, lists of participants in the consultations, list of all direct affectees (names, ID along with types of losses etc.)

BCEOM SRI LANKA - RSAPC - NOTE

Note - General 04

Environmental Re-Development Plans

The majority of our Contracts are due to complete sometime this year. Some of them are being completed. You are aware that Contractors use quarries, crushers, asphalt plants, borrow pits, disposal sites, stores, yards for materials, equipment, machineries etc. and labour camps during the contract period. According to the Environmental Management Action Plan (EMAP) in the Contract Agreement, the Contractor is bound to clear all the environmental issues as follows when and where necessary before handing over the project to the RDA:  Removal of temporary constructions.  Disposal of debris and garbage.  Removal of dangerous/hazardous things/items such as hanging stones, iron bars, nails or other heavy materials.  Filling of cut pits.  Planting of erosion preventive plants on the slopes where necessary.  Repairing of access roads used for material transportation.  Removal of blockages of drainage paths and drains.  Removal of barricades and obstructions erected temporally in the project period.  Removal of water containers those are suitable for mosquito breeding.  Closure plan and no objection letters from land owners.

In addition to above, you are kindly requested to inform the Contractors to fulfil the conditions of EPLs, IMLs and permits issued for quarries, crushers, asphalt plants, borrow pits and disposal yards by the CEA, GS & MB and Local Government Authorities respectively. To assure the environmental safeguard, the Contractor should prepare a Redevelopment Plan for the above matters having a time plan, activities and responsibilities. You are kindly advised to inform the Contractors to submit their Redevelopment Plans before the end of February 2009.

Thank you.

Senior Environmental Specialist

Copy - Team Leader Senior Resident Engineer Senior Resident Engineer Senior Resident Engineer

Monthly Social Monitoring Plan:

1. COMMENCEMENT OF CONSTRUCTION

Chainage Start Date Target Completion Date

2. Contract Mobilization Status

No. of Identification Stage Replacement cases Date of Target Target Date Target initiation completion date of initiation completion date i) Affected Assets - Infrastructure - Private properties (Structures) - Private Properties (lands) - Community assets & utilities - Cultural property

ii) Affectees

iii) Livelihoods

3. SOCIAL IMPACT MANAGEMENT FRAMEWORK

No. of cases Actual Start Date Actual Target Completion Date i) Replacement ii) Livelihood restoration iii) Other (if any)

4. COMPLAINTS

Type of No.of Date of Date of No. of Settled by complaints complaints complaint settlement settled the GRC received complaints Social issues Envt. issues

General-01 –Social Safeguard –Guide lines for Completion report

From: To : All the REs

Dear Sir/Madam

As your know some of our Packages are ending by the end of this year . The RE has to be prepared the Completion Report before close the project . While you are preparing the report pl: follow the attached format to cover the social activities .

Thanks

Guidelines for Completion Report –Sociological Aspects /Social activities

When the completion report is prepared by the Resident Engineer, it is recommended to follow the following guidelines. However it should not be a very long description but a summary with important items .

01) Grievance Redress Committee (GRC)

a) Have you established GRC ? If not why?

b) If you were established ,how many meetings were held ?

c) What are the issues solved by the GRC ?

02) Project Affected Persons (PAPs)

a) How many PAPs were identified ? What are them ?

b) Were you followed the correct procedures of the PAPs with the RDA?

c) Were you completed all the PAPs ?

d) Are there any pending matters ? What are the reasons ?

03) Public Complaints/Requests(From start to end of the project)

Areas Received Completed Pending Reasons for Actions taken NOs NOs NOs pending /Remarks 1)Community/House Access

2) Retaining walls

3) House damages/Compensations

4) Road access

5) Repairing wells

6) Effects for livelihoods (Agriculture, commercial etc) 7) Compensation for land Acquit ions .

8) Repairing of public utilities (electricity. water etc)

4 Third Party Property Damages(Community Insurance Cases )

(No need the details of Insurance payments for the Electricity Board or Water Board)

a) How many cases were identified? (Pl: provide summary )

b) How many cases were solved ?

c) Total amount of Rs: were paid for the community?

4.1 Accidents and Payment

No of accidents Paid amount Rs:

05) HIV/AIDS programs

Details of the conducted Training programs/workshops

Title of the program Contents /subjects Type of Resource Persons Participants/NOs

05) Social Welfare activities

Type of Activities Beneficiaries /community Amount of Rs: spent by groups the Contractor

06) Any other social activities related to the road development project

07) Lesson learnt

08) Attachments –a) Photos b)Repots/Cases etc.

OFFICE OF THE TEAM LEADER AND ENGINEER, ROAD SECTOR ASSISTANCE PROJECT INTERNAL MEMORANDUM

Reference No.: Date: To: All Contractors

Subject: Deduction from IPC due to Poor Safety Arrangements

You are aware that the road safety of the Contract Packages had been criticized by the steering committee on ------at the Ministry of Highways and PMU requested by the letter ------. And also, unfortunately, two fatal accidents have been occurred in the ------.

Under this situation, we are in a position to emphasize not to happen any accidents at work sites by arranging satisfied safety measures. All the Contractors obliged to arrange proper safety measures according to the Environmental Management Action Plan annexed to the Contract Agreement. PMU requested to take maximum effort to prevent any accidents in our Contract Packages. After discussing with the PMU, a new system to be deducted from the IPC has been decided as follows.

Deduction amount Level of poor safety arrangements (Rs.) Rs. 50,000/= At high risk sites/places. Rs. 30,000/= At medium risk sites/places Rs. 20,000/= At low risk sites/places

Above deductions will be double at the second time and treble at the third time of the offences.

The level of the risk will be decided by the Team Leader/Resident Engineer. If there is any unclear thing in this system, the final decision will be taken by the Team Leader where it is necessary.

This new system will be effective from ------.

Please remember that if the safety arrangements are not sufficient, the Contractor should not be allowed to do any works.

Regards,

For and on behalf of the Engineer

…………………………………. Team Leader

Copy: - Project Director, PMU - All Resident Engineers - Senior Environmental Specialist - Chief Coordinator - All Contract Packages - File CP00

ROAD SECTOR ASSISTANCE PROJECT

Environmental Check List - 01

Road Construction Sites

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 No debris in the RoW. 2 No water ways/bodies blocked by the debris. 3 Debris is not washed out into water ways. 4 Debris is not a nuisance to the public. Debris does not affect to the agricultural 5 plots. Existing canals, streams or water sources 6 have not been obstructed without relevant permission of the Engineer. No any kind of water ways 7 diverted/alternated without relevant permission of the Engineer. 8 No water pollution due to road work. Community water sources have not been 9 lost or disturbed. 10 No flood due to road work. Bitumen/oil/fuel are not spilled out over the 11 road work area. 12 No borrowing within the RoW. 13 No dust generation at the road work site. Dust emission is controlled by spraying 14 water on the road surface regularly. The Contractor has kept clean the road 15 clearing mud or other extraneous dropped by vehicles. Emission from machineries has been 16 controlled. All the vehicles and equipment have been 17 fitted with proper exhaust silencers. Exhaust silencers have been checked 18 periodically. All the vehicles and equipment have been 19 fitted with signal lights & front/reverse horns. 20 No damage to important flora. No tree removed without relevant 21 permission of the Engineer. Contractor has provided convenient passage 22 for vehicles, pedestrians and livestock. No unnecessary or improper interference has been done to the convenience of public, 23 access, occupation of public, private road, or foot paths. Detailed traffic control plan for each day has 24 been submitted by the Contractor to the Engineer. 25 Running surface is properly maintained. Contractor has taken necessary measures 26 for the safety of the traffic during construction (applying, erecting and Status Serial Environmental Activity Not Remarks No. Yes No relevant maintaining barricades, signs, markings, flags, lights and flagmen). Workers’ safety has been assured supplying 27 and wearing helmets, jackets, boots and masks etc. No materials have been stacked or placed to 28 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 29 properties, premises and precincts.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 02

Quarry Operation

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant IMLs from GS&MB have been obtained and 1 not expired. EPLs from CEA have been obtained and not 2 expired. 3 Valid explosive licenses are available. 4 LGA permits are available. Blasting carried out with the permission of 5 the Engineer. 6 Noise level has been checked periodically. 7 No water ways/bodies blocked 8 Water logging is not evident in the site. 9 No soil/water contamination from oil/fuel. 10 No harmful/significant dust generation 11 No damages to important flora/fauna. No unnecessary or improper interference has been done to the convenience of public, 12 access, occupation of public, private road, or foot paths. 13 Surface of the site is properly maintained. Contractor has taken necessary measures for the safety of (applying, erecting and 14 maintaining barricades, signs, markings, flags, lights and siren etc.) public. Workers’ safety has been assured supplying 15 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 16 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 17 properties, premises and precincts. Quarry redevelopment plan has been 18 prepared by the Contractor.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 03

Crusher Operation

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant EPLs from CEA have been obtained and not 1 expired. 2 LGA permits are available. 3 Dust has been controlled well 4 Noise level has been checked periodically. 5 No water ways/bodies blocked 6 Water logging is not evident in the site. 7 No soil/water contamination from oil/fuel. 8 No harmful/significant dust generation Emission from machineries has been 9 controlled. All the machineries have been fitted with 10 proper exhaust silencers. Exhaust silencers have been checked 11 periodically. 12 No damage to important flora. No unnecessary or improper interference has been done to the convenience of public, 13 access, occupation of public, private road, or foot paths. 14 Surface of the site is properly maintained. Contractor has taken necessary measures 15 for the safety. Workers’ safety has been assured supplying 16 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 17 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 18 properties, premises and precincts.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 04

Asphalt Plant Operation

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant EPLs from CEA have been obtained and not 1 expired. 2 LGA permits are available. 3 Dust has been controlled well 4 Noise level has been checked periodically. 5 No water ways/bodies blocked 6 Water logging is not evident in the site. 7 No soil/water contamination from oil/fuel. 8 No harmful/significant dust generation Emission from machineries has been 9 controlled. All the machineries have been fitted with 10 proper exhaust silencers. Exhaust silencers have been checked 11 periodically. 12 No damage to important flora. No unnecessary or improper interference has been done to the convenience of public, 13 access, occupation of public, private road, or foot paths. 14 Surface of the site is properly maintained. Contractor has taken necessary measures 15 for the safety. Workers’ safety has been assured supplying 16 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 17 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 18 properties, premises and precincts.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 05

Borrow Pits

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 IMLs from GS & MB have been obtained and not expired. 2 LGA permits are available. 3 No water ways/bodies blocked 4 Water logging is not evident in the site. 5 No harmful/significant dust generation 6 Emission from machineries has been controlled. 7 All the machineries have been fitted with proper exhaust silencers. 8 Exhaust silencers have been checked periodically. 9 No damage to important flora. 10 No unnecessary or improper interference has been done to the convenience of public, access, occupation of public, private road, or foot paths. 11 Surface of the site is properly maintained. 12 Soil erosion has been maintained. 13 Contractor has taken necessary measures for the safety. 14 Workers’ safety has been assured supplying and wearing helmets, jackets, boots and mars and ear plugs etc. 15 No materials have been stacked or placed to cause danger or inconvenience to any person or the public. 16 No work spilled over to the cultural properties, premises and precincts. 17 No soil/water contamination from oil/fuel. 18 Borrow pit redevelopment plan has been prepared by the Contractor.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 06

Disposal sites

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 Contractor has identified disposal yards. 2 The environmental permissions from the LGA have been taken. 3 Borrow pit redevelopment plan has been prepared by the Contractor and approved by the Engineer. 4 No water logging. 5 Dust emission has been controlled.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 07

Health & Safety

Contract Package: ………… Location: ……………………….. (If you have not enough space for additional information, please use the back page or additional papers.) Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 Safety gear for workers has been supplied. 2 Medical centre/ambulance room is available with nurse and fist aid medicine. 3 A vehicle is available to take patients immediately to the hospital. 4 Labour camps with proper facilities such as enough spaces, ventilation, beds, mosquito nets, lavatories, bathing facilities, drinking water are available. 5 Garbage has been disposed well.

Signatures:

……………………… …………………….. Resident Engineer Senior Environmental Specialist

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT

Environmental Check List - 01

Road Construction Sites

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Y es No relevant 1 No debris in the RoW. 2 No water ways/bodies blocked by the debris. 3 Debris is not washed out into water ways. 4 Debris is not a nuisance to the public. Debris does not affect to the agricultural 5 plots. Existing canals, streams or water sources 6 have not been obstructed without relevant permission of the Engineer. No any kind of water ways 7 diverted/alternated without relevant permission of the Engineer. 8 No water pollution due to road work. Community water sources have not been 9 lost or disturbed. 10 No flood due to road work. Bitumen/oil/fuel are not spilled out over the 11 road work area. 12 No borrowing within the RoW. 13 No dust generation at the road work site. Dust emission is controlled by spraying 14 water on the road surface regularly. The Contractor has kept clean the road 15 clearing mud or other extraneous dropped by vehicles. Emission from machineries has been 16 controlled. All the vehicles and equipment have been 17 fitted with proper exhaust silencers. Exhaust silencers have been checked 18 periodically. All the vehicles and equipment have been 19 fitted with signal lights & front/reverse horns. 20 No damage to important flora. No tree removed without relevant 21 permission of the Engineer. Contractor has provided convenient passage 22 for vehicles, pedestrians and livestock. No unnecessary or improper interference has been done to the convenience of public, 23 access, occupation of public, private road, or foot paths. Detailed traffic control plan for each day has 24 been submitted by the Contractor to the Engineer. 25 Running surface is properly maintained. Contractor has taken necessary measures 26 for the safety of the traffic during Status Serial Environmental Activity Not Remarks No. Y es No relevant construction (applying, erecting and maintaining barricades, signs, markings, flags, lights and flagmen). Workers’ safety has been assured supplying 27 and wearing helmets, jackets, boots and masks etc. No materials have been stacked or placed to 28 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 29 properties, premises and precincts.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 02

Quarry Operation

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant IMLs from GS&MB have been obtained and 1 not expired. EPLs from CEA have been obtained and not 2 expired. 3 Valid explosive licenses are available. 4 LGA permits are available. Blasting carried out with the permission of 5 the Engineer. 6 Noise level has been checked periodically. 7 No water ways/bodies blocked 8 Water logging is not evident in the site. 9 No soil/water contamination from oil/fuel. 10 No harmful/significant dust generation 11 No damages to important flora/fauna. No unnecessary or improper interference has been done to the convenience of public, 12 access, occupation of public, private road, or foot paths. 13 Surface of the site is properly maintained. Contractor has taken necessary measures for the safety of (applying, erecting and 14 maintaining barricades, signs, markings, flags, lights and siren etc.) public. Workers’ safety has been assured supplying 15 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 16 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 17 properties, premises and precincts. Quarry redevelopment plan has been 18 prepared by the Contractor.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 03

Crusher Operation

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant EPLs from CEA have been obtained and not 1 expired. 2 LGA permits are available. 3 Dust has been controlled well 4 Noise level has been checked periodically. 5 No water ways/bodies blocked 6 Water logging is not evident in the site. 7 No soil/water contamination from oil/fuel. 8 No harmful/significant dust generation Emission from machineries has been 9 controlled. All the machineries have been fitted with 10 proper exhaust silencers. Exhaust silencers have been checked 11 periodically. 12 No damage to important flora. No unnecessary or improper interference has been done to the convenience of public, 13 access, occupation of public, private road, or foot paths. 14 Surface of the site is properly maintained. Contractor has taken necessary measures 15 for the safety. Workers’ safety has been assured supplying 16 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 17 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 18 properties, premises and precincts.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 04

Asphalt Plant Operation

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant EPLs from CEA have been obtained and not 1 expired. 2 LGA permits are available. 3 Dust has been controlled well 4 Noise level has been checked periodically. 5 No water ways/bodies blocked 6 Water logging is not evident in the site. 7 No soil/water contamination from oil/fuel. 8 No harmful/significant dust generation Emission from machineries has been 9 controlled. All the machineries have been fitted with 10 proper exhaust silencers. Exhaust silencers have been checked 11 periodically. 12 No damage to important flora. No unnecessary or improper interference has been done to the convenience of public, 13 access, occupation of public, private road, or foot paths. 14 Surface of the site is properly maintained. Contractor has taken necessary measures 15 for the safety. Workers’ safety has been assured supplying 16 and wearing helmets, jackets, boots and mars and ear plugs etc. No materials have been stacked or placed to 17 cause danger or inconvenience to any person or the public. No work spilled over to the cultural 18 properties, premises and precincts.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 05

Borrow Pits

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 IMLs from GS & MB have been obtained and not expired. 2 LGA permits are available. 3 No water ways/bodies blocked 4 Water logging is not evident in the site. 5 No harmful/significant dust generation 6 Emission from machineries has been controlled. 7 All the machineries have been fitted with proper exhaust silencers. 8 Exhaust silencers have been checked periodically. 9 No damage to important flora. 10 No unnecessary or improper interference has been done to the convenience of public, access, occupation of public, private road, or foot paths. 11 Surface of the site is properly maintained. 12 Soil erosion has been maintained. 13 Contractor has taken necessary measures for the safety. 14 Workers’ safety has been assured supplying and wearing helmets, jackets, boots and mars and ear plugs etc. 15 No materials have been stacked or placed to cause danger or inconvenience to any person or the public. 16 No work spilled over to the cultural properties, premises and precincts. 17 No soil/water contamination from oil/fuel. 18 Borrow pit redevelopment plan has been prepared by the Contractor.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 06

Disposal sites

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 Contractor has identified disposal yards. 2 The environmental permissions from the LGA have been taken. 3 Borrow pit redevelopment plan has been prepared by the Contractor and approved by the Engineer. 4 No water logging. 5 Dust emission has been controlled.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

ROAD SECTOR ASSISTANCE PROJECT BCEOM Environmental Check List - 07

Health & Safety

Contract Package: ………… Location: ………………………..

(If you have not enough space for additional information, please use the back page or additional papers.)

Status Serial Environmental Activity Not Remarks No. Yes No relevant 1 Safety gear for workers has been supplied. 2 Medical centre/ambulance room is available with nurse and fist aid medicine. 3 A vehicle is available to take patients immediately to the hospital. 4 Labour camps with proper facilities such as enough spaces, ventilation, beds, mosquito nets, lavatories, bathing facilities, drinking water are available. 5 Garbage has been disposed well.

Signatures:

……………………… …………………….. Environmental Officer Contract Representative

Date: …………….. Date: ………………..

AGREEMENT

Demolishing of the Constructions to acquire the land to improve / rehabilitate the ………………………………………………. Road

This agreement is made and entered into on this …….. day of …... Two Thousand ………… at ……… in Democratic Socialist Republic of Sri Lanka.

BY AND BETWEEN

Road Development Authority, a governmental authority created by Act No. 73 of 1981 of Sri Lanka and having its’ principal office at “ Sethsiripaya” , Battramulla herein after called and referred to as the RDA and which term of expression shall mean and included the said RDA or its’ successors and Divisional Secretary, ………… permitted assigns of the one part.

AND

………………………………………………………… ( name of owner of the land) of …………………………………………………………………... (address) which term in expression shall where the context so admits or requires, mean and include the said ……………………………………. of his successors and permitted assigns of the other part.

NOW THIS AGREEMENT WITNESSETH THAT THE RDA AND ……………………………………………………….. has mutually agreed as follows.

01. Considering the Social & Economical impact of the rehabilitation of the above mentioned road I/We …………………………………. The owner / owners of the land called ………………………………………… (morefully described in the schedule hereto) donate and will be transferred in the name of the Chairman of the Road Development Authority.

02. The land is being given of my / our own free will and is an entirely voluntary donation.

03. I / We ……………………………… do hereby assure that I / We relinquish all Claim and title to the donated land & that land is free of all encumbrances.

04. The relinquished & donated land does not affect any person’s livelihood.

05. I / We ……………………………… agree on demolishing ……………......

Which has been recognized to be demolished to rehabilitate the road, on the condition of a new construction to be consigned.

THE SCHEDULE ABOVE REFERRED

Detail about the land ……………………………………………………………… Size of the Land ……………………………………………………………… Details about the Constructions, Properties & Cultivations

To North …………………………………………………………….... ………………………………………………………………

To South ……………………………………………………………… ………………………………………………………………

To East ……………………………………………………………… ………………………………………………………………

To West ……………………………………………………………… ………………………………………………………………

Here by we grant & acknowledge the acceptance of the land morefully described in the schedule hereto on ………………………. Date.

…………………………………. ……………………………. Signature of the 1st party Signature of the 2nd party

01. Chairman , R.D.A. ……………….

02. Divisional Secretary, ………………

Date………….. RE’s Signature Accident Report-Social aspects

Contract Package……. Accident Serial No:

1 Date of Accident : 2 Place of Accident 3 Name of the Victim/s 4 Submission of Police report

* Name of the Police Station

* Inquiries held-Date/Time

* Police report received-Date

5 Submission of Medical report

*Name of the Hospital

*Medical report received-Date 6 Submission of the reports to the Insurance Company *Name of the Insurance Company

*Reports submitted-Date

*Entitle Compensation Rs:

*Compensation decided –Date

*Compensation received by the client- Date 7 If there was a death how did the Contractor involve for the funeral ?

8 What are the social-welfare activities done by the Contractor related to the accidents ? (family, children etc)

……………….