<<

Resettlement Planning Document

Resettlement Plan (53+450 to 68+358 km) Project Number: L2540 December 2011

Pakistan: National Highway Development Sector Investment Program, Project 2 (-Jacobabad Road Project [N-65], Section 4)

Prepared by the Office of the General Manager (N-65), National Highway Authority, Ministry of Communications, Government of .

The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, TheBoard resettlement of Directors, Management, plan is a ordocument staff, and may of bethe preliminary borrower. in nature.The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

CURRENCY EQUIVALENTS (as of 16 December 2011)

Currency Unit – Pakistan rupee/s (PRs) PRs1.00 = $0.0117 $1.00 = PRs89.50

ABBREVIATIONS

AD – Assistant Director ADB – Asian Development Bank APs – affected persons COI – corridor of impact CWD Communication and Works Department DCR – District Census Report DDO – Deputy District Officer EALS – Environment, Afforestation, Land and Social EDO – Executive District Officer EMA – External Monitoring Agency Ft. – feet GM – General Manager GOP – Government of Pakistan GRC – grievance redress committee IP’s – indigenous people Km – kilometers LAA – Land Acquisition Act, 1894 LAR – land acquisition and resettlement LARP – land acquisition and resettlement plan MandE – monitoring and evaluation NESPAK – National Engineering Services Pakistan, (Pvt.) Ltd. MFF – multitranche financing facility NGO – nongovernmental organization NHA – National Highway Authority NHDSIP – National Highway Development Sector Investment Program PD – Project Directorate Rft – running feet RoW – right of way Sft – square feet Updated RP (Section-II) – updated resettlement plan (Section-II)

NOTE

In this report, “$” refers to US dollars.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

TABLE OF CONTENTS ACRONYMS AND ABBREVIATIONS ...... i DEFINITIONS OF TERMS ...... ii 1. INTRODUCTION ...... 1 1.1 Background ...... 1 1.2 The Project ...... 1 1.3 Rationale for Updating of Land Acquisition and Resettlement Plan (LARP) ...... 2 1.4 Project Description ...... 3 1.5 Objectives of the updated Resettlement Plan (Section-IV) ...... 7 2. SOCIOECONOMIC PROFILE OF APs ...... 7 2.1 Administrative Setting ...... 8 2.2 Literacy Status ...... 8 2.3 Income Status ...... 8 2.4 Borrowing Status ...... 9 2.6 Social Amenities ...... 9 2.7 Status of Agriculture in the Project Area ...... 9 2.8 Economic Activity in the Project Area ...... 10 2.9 Social Impacts ...... 10 2.11 Women Involvement ...... 10 2.12 Existence of Community based Organizations ...... 11 3. IMPACT ASSESSMENT ...... 11 3.1 Impact Assessment Survey and Cut-off Date ...... 11 3.2 Project Impacts ...... 11 3.2.1 Land Acquisition ...... 12 3.2.2 Building/ Structures (Shops/ Room) ...... 12 3.2.3 Community Structures ...... 12 3.2.4 Public Structures ...... 13 3.2.5 Inventory of Trees ...... 13 3.2.6 Affected Crops ...... 14 3.2.7 No. of Affected Families (AFs) ...... 14 3.3 Vulnerable AFs/APs...... 14 3.4. Price Assessment of Land and other Assets ...... 15 4. OBJECTIVES AND POLICY FRAMEWORK ...... 16 4.1 Compensation Eligibility and Entitlements for the Project ...... 16 4.2 Eligibility for Entitlements of Compensation ...... 16 4.3 Compensation Entitlements ...... 17 4.4 Eligibility and Entitlements ...... 18 5. PUBLIC CONSULTATIONS AND DISCLOSURE ...... 19 6 COMPENSATION, RELOCATION AND INCOME RESTORATION ...... 20 6.1 General ...... 20 6.2 Compensation for Privately Owned Structures ...... 20 6.3 Compensation for Community Owned Structures/Assets ...... 21 6.4 Compensation for Public infrastructure/Assets ...... 21 6.5 Provisions for Compensatory Plantation ...... 22 6.6 Relocation Options ...... 22 6.6.1 Privately owned Structures ...... 22 6.6.2 Religious Structures ...... 23 6.7 Income Restoration ...... 23 6.8 Transportation Allowance ...... 24 7. INSTITUTIONAL ARRANGEMENTS ...... 24 7.1 Land Acquisition and Resettlement Unit at Project Level ...... 24 7.2 Grievance Redress Cell...... 25 7.3 Affected Persons and Citizen Liaison Committee ...... 25 8. IMPLEMENTATION SCHEDULE OF UPDATED RP (SECTION-III) ...... 27 9. RESETTLEMENT BUDGET ...... 29

1

10. MONITORING AND EVALUATION ...... 30 10.1 Internal Monitoring ...... 30 10.2 External Monitoring ...... 30

List of Tables

Table-1: Major Crops with their Average Yields………………………………………………….11 Table-2: Details about the structures located in ROW.……………………………………….....14 Table-3: No. of Community Structures located within the Project Area.…………………….…14 Table-4: No. of Public Structures located within the Project Alignment…………………….….15 Table-5: No. of Trees Located within the Project Alignment…………………………………….15 Table-6: No of Affected Persons due to the Construction of Section-I.…………..………….....16 Table-7: Unit Rates and Source of Information……………….………….………………….……17 Table-8: Entitlement Matrix ………………………………………………………………...……….20 Table-9: Valuation of Privately owned Affected Structures/Assets…………..…………….…...23 Table-10: Valuation of Affected Community owned Structures/Assets.……………………....…24 Table-11: Valuation of Affected Public Structures/Assets……………...... ………………...…..24 Table-12: Estimation of Livelihood Allowance for Affected Households.…………………….….26 Table-13: Implementation Schedule of LARP ……………………...…...... ………………….….31 Table-14: Resettlement Budget.………………………………………………………….,,,………..32

DEFINITIONS OF TERMS

For the purpose of preparing Updated Resettlement Plan (Section-III), the following terms are defined below:

Affected Person/People - Any person affected by Project-related changes in use of land, water, natural resources, or income losses.

Affected Family - All members of a household residing under one roof and operating as a single economic unit, who are adversely affected by the Project, or any of its components. It may consist of a single nuclear family or an extended family group.

Business Renter- Any person other than structure owner, who is operating his business in rented in structure (shop, kiosk or cabin), and is subject to relocate his business due to project impacts.

Compensation - Payment in cash or in kind of the replacement cost of the acquired assets.

Cut-off-date shall confirm to the date of commencement of census in the specified area.

Entitlement - Range of measures comprising compensation, income restoration, transfer assistance, income substitution, and relocation which are due to affected people, depending on the nature of their losses, to restore their economic and social base.

Household - The people or families residing under one roof, using the same hearth and operating as a single economic unit.

Income Restoration includes reestablishing income sources and livelihood of the affected persons according to their status.

Involuntary Resettlement – Any resettlement, which does not involve willingness of the persons being adversely affected, but are forced through an instrument of law.

Shops are commercial structures, like groceries, vulcanizing shops, tailoring shops, beauty parlor, market stalls, hotels, and similar establishments.

Land Acquisition - The process whereby a person is compelled by a government agency to alienate all or part of the land a person owns or possesses to the ownership and possession of the government agency for public purpose in return for a consideration.

Market Value - the value of asset determined by market transaction of similar assets and finally arrived at after negotiations with the stakeholders, and it includes transaction costs and without the depreciation and deductions for salvaged building material.

Participation is a process that allows APs and other stakeholders to influence and share control over development initiatives, decisions and the use of resources that affect them.

Rehabilitation - Compensatory measures provided under the Policy Framework on involuntary resettlement other than payment of the replacement cost of acquired assets.

Relocation - The physical relocation of AP from his/ her pre-Project place of residence.

i

Replacement Cost - Replacement cost means the cost of replacing lost assets and income. In the case of land, it means the cost of buying replacement land near the lost land with equal productive potential plus the cost of preparing the land to levels similar to those of the affected land and the cost of any registration and transfer taxes. If alternative land is not available in the vicinity of the lost land, it means the cost of buying land with similar attributes and productive and/or residential potential plus the cost of preparing the land to levels similar to those of the affected land and cost of any registration and transfer taxes. In selecting alternative lands, affected people will be informed and consulted.

Severely Affected land or structure means more than 10% of the land or structure is affected or even less than 10% but the remaining portion is no longer viable for use.

Squatters are the persons who occupy and use an asset without possessing it or having any legal title, or a right to use/possess the same.

Vulnerable Affected Persons are the marginalized affectees or those distinct people who might face the risk of marginalization and suffer disproportionately from resettlement affects, including the women, children, destitute persons, disable, handicapped, squatters; those with historical or cultural usufruct rights; and landless groups.

Local Terms Pacca - House or building constructed with concrete or bricks. Semi-Pacca- House or building constructed with burnt bricks and mud. Katcha- House or building made of un-burnt bricks and mud with wooden roof. Chapra- The temporary structure constructed by erecting pillars or installing wood logs on each corner with roof made of twigs and grass etc.

ii

1. INTRODUCTION

1.1 Background

1. The Government of Pakistan has identified road infrastructure as prerequisite for sustained economic growth and poverty alleviation. The government development priorities have been formulated in the form of “National Trade Corridor Improvement Program”. The program focus on regional connectivity through improving linkages with the neighbouring countries, developing inter provincial linkages to improve sub regional connectivity and construction of a North South Expressway Trade Corridor to overcome the network deficit.

2. National Highway Authority (NHA) is implementing National Highway Development Sector Investment Program (NHDSIP) with the assistance of Asian Development Bank (ADB) through a multi-tranche financing facility through which separate multiple loans will be extended to finance a range of subprojects. The subprojects under Tranche 1 have been completed. The Loan 2540 for Tranche 2 was signed on 3 September 2009 which became effective on 21 September, 2009.

3. The Sukkur–Jacobabad road is one of the subprojects of this tranche1. The Land Acquisition and Resettlement Plan (LARP) for Sukkur–Jacobabad was approved by ADB in May 2009. However, discrepancies were observed in the number of project affected persons and the related impacts during the physical verification of LARP by ADB through an independent consultant in May 2010. ADB required that the LARP should be updated to ensure that all APs are included and all the impacts are properly analysed.

4. Before the LARP could be updated the project highway was extensively damaged by the floods. A meeting was held at ADB Resident Mission, on 26th August, 2010 to discuss the contract signing and pending safeguard requirements. It was agreed that NHA will provide the section wise construction plan along with a linear road map indicating areas and stretches of road with and without LAR impacts and an action plan on dated 26-08-10 Land Acquisition and Resettlement (LAR) requirements with first requirement being the preparation, approval, implementation and monitoring of section wise LARP with the section NHA wants to construct first. The minutes of meeting were communicated with ADB letter dated 30 August reiterating that the civil works will commence, with prior approval of ADB Safeguard Team, only when the LARP for the section is fully implemented and verified by the External Monitoring Agency (EMA).

1.2 The Project

5. Road Sukkur–Jacobabad N-65 is an important interprovincial highway connecting , the capital city of Baluchistan with the province of , Punjab and the port city of . A 68km section of this road is planned for up gradation and improvement of Section of this highway between Sukkur–Jacobabad. The scope of work include i) rehabilitation & capacity up gradation of the existing road section (63 km) between Sukkur–Jacobabad to 4-lane dual carriageway, and ii) constructing a bypass for Shikarpur (5 km) city.

6. For the purpose of widening of the existing road into four lanes highway with an adequate available ROW (i.e. 35 m wide) owned by NHA from Sukkur–Shikarpur and Shikarpur–Jacobabad, where no land acquisition is involved, however, the ROW has been encroached by the locals at many places, who have to be compensated in accordance with the entitlement criterion and compensation matrix prepared under the

1. This tranche includes, (i) Sukkur–Jacobabad, and (ii) Qilla Saifullah–Zhob.

1

Land Acquisition & Resettlement Framework agreed with ADB. The measuring of 35.5 acres of land has to be acquired for 4.9 km long Shikarpur Bypass which falls in Section- 2, for which adequate funds were deposited with the District Treasury in 2006 and disbursement of compensation to the extent of Land Costs, is in progress.. However disbursements of entitled compensations to the entitled encroachers throughout road corridor falling within Section-IV are to be made through project account. The sufficient Funds have been made available in Project account to ensure timely disbursement of the entitled compensations.

7. National Highway Authority (NHA) is currently implementing two major road sector projects with the financial assistance of Asian Development Bank through Multi Tranche Financing Facilities (MFF). The National Highway Development Sector Investment Program (NHDSIP) is one of them, which includes 7 major roads.2 The Sukkur–Jacobabad (N-65) is one of the seven roads including one bypass (Shikarpur Bypass). The implementation of these projects will be subjected to the compliance of Social Safeguards of ADB. The ADB Policy on "Involuntary Land Acquisition & Resettlement” requires preparation and implementation of "Land Acquisition & Resettlement Plans (LARP)", and finally conducting its independent monitoring (IM).

8. The construction of dual carriage way from Sukkur–Shikarpur-Jacobabad road is a step towards strengthening and expansion of the road network. Its total length is 63 km and one bypass of 4.9 km. It is a 4 lanes dual carriageway road. The project involved land acquisition and other associated impacts such as loss of structures, loss of squatters-business, relocation of community infrastructure, loss of crops and finally loss of trees especially wood trees. Accordingly, the NHA through hiring the consultancy services of NESPAK has prepared Land Acquisition and Resettlement Plan (LARP) in May 2009, which have specified and quantified the impacts of the project, eligibility and entitlements for compensation through establishing institutional arrangements and setting of redressal of community grievances.

9. Sukkur to Jacobabad Section of N-65 passes through the districts of Sukkur, Shikarpur and Jacobabad of Sindh Province and links the province of Sindh with Punjab and Baluchistan. Major settlements along the road are Shikarpur City and many villages, i.e. Soomar, Sheikh Suleman, Lakhi, Jahaan Khan and , Hamayun etc. The whole project road falls under the administrative jurisdiction of Sukkur, Jacobabad and Shikarpur Districts of Sindh Province. The project starts from Sukkur Bus stand and ends at starting point of Jacobabad. There is already existing 2 lane paved carriage way varying from 6.0 meters to 7.5 meters at various locations. The right of way (RoW) of the road is 110 ft (i.e. 55 ft. on each side from the center of road).

10. The various components of the project include widening of the existing road from Sukkur to Jacobabad City and constructing a Shikarpur bypass of about 5 km. After the completion of the project the two lane road will be converted to a 4 lane dual carriage way.

1.3 Rationale for Updating of Land Acquisition and Resettlement Plan (LARP)

11. The LARP implementation started in early 2009 but was delayed due to various factors including the gaps in the inventory of losses. With this realization, NHA and a staff consultant form ADB jointly carried out a field survey in October 2010. The team noted3 that there were gaps in the LARP, updated by NESPAK for NHA in May 2009.

2 Hub Uthal (N-25), –Muzaffargarh (N-70), Muslim Bagh–Qila Saifullah, Qila Saifullah–Zhob, Sukkur– Jacobabad (N-65), Zhob–Mughal Kot and Qila Saifullah–Loralai- Walgum Rud. 3 Comments made by Consultant ADB and similar observations were also made by external monitoring

2

The impacts relating to the loss of building/ structures, and trees were significantly under assessed while the identification of owners/ inventory of land, trees and other assets were not considered in the plan. Furthermore, the ROW considered in the LARP was significantly less as compared with the actual alignment. Having highlighted these gaps in the LARP, NHA considered it essential to finally update the LARP, based on the gaps and findings of joint survey by NHA and the consultant.

12. To update the LARP for the whole project corridor is a time taking process, in this context, ADB accepted that NHA may prepare the Sectional LARPs and NHA can prepare and submit the LARP first for the Section, where there are minimum impacts, so that after its approval, the implementation of the LARP could be completed in a shorter time. Accordingly, NHA divided the LARP into the following four sections:

(i) K.M. 00+000 to 17+500 (Zero to end of Lakki Town) (ii) K.M. 17+500 to 33+250 (End of Lakki Town to end of Shikarpur Bypass) (iii) K.M. 33+250 to 53+450 (End of Shikarpur Bypass to end of Humayun Town) (iv) K.M. 53+450 to 68+358 (End of Humayun town to start of Jacobabad).

13. In accordance with the above division of LARP, NHA has prepared this Updated Resettlement Plan4 for Section-IV IV (53+450 to 68+358 km). This updated RP (Section- IV) is based on a fresh impact assessment survey and consultative meetings with the APs held during March-April 2011 by NHA.

14. However, during review of updated RP (Section-IV) in July 2011 it was observed that the inventory of structures appended with the updated RPs (Section-IV) is based on the identified loss of structure to the APs falling in structure owner category without determining the impacts on other categories of APs including Lessees of the impacted structures doing business therein (business renters) and employees of business owners. To fill the gap a detailed survey of duly identified structures falling within RoW was again carried out in consultation with ADB’ s Consultant (Social Safeguard Specialist, Transport Sector Projects) during October 2011 and all categories of the APs were recorded. The Inventory and text of the updated RP (Section-IV) is adjusted accordingly.

1.4 Project Description

15. The 63 Km road section form Sukkur to Jacobabad (N-65) is an important highway and plays a vital role in connecting Quetta, the capital city of Baluchistan with the province of Sindh and Punjab. In construction, section-IV (53+450 to 68+358) of this project road is planned to be widened and improved as 4 lane dual carriageway. Besides updating of the resettlement Plan for Section-IV between Sukkur–Jacobabad is also to be considered during the project implementation. The scope of project development of section-IV (53+450 to 68+358) includes: Rehabilitation & up-grading the capacity of existing road section (63 km) between Sukkur–Jacobabad to 4-lane dual carriageway.

16. For the purpose of widening of the existing road to a four lanes highway with an adequate available ROW (i.e., 35 m wide) owned by NHA from Sukkur–Shikarpur and Shikarpur–Jacobabad, where no land acquisition is involved. However, the ROW has been encroached by the locals at many places near major settlements along the road corridor, who have to be compensated in accordance with the entitlement criterion and

consultant in his Inception report. 4. The Section-IV involves encroacher’s -business structures which will be relocated by the owners at their own in the nearby place outside ROW after receiving payment of their losses. On the whole, there would be a minor impact on the livelihood of the APs due to the construction of this section.

3

compensation matrix prepared under the Land Acquisition & Resettlement Framework agreed with ADB.

17. For the purpose of preparation of sectional LARP, the subproject road has been divided into four sections. The Section-IV Section-IV (53+450 to 68+358) is one of the four Sections of this road project (Sukkur – Jacobabad). There are 4 major settlements; shikarpur, , Lodra, Abdul Ghafoor Solangi, kot sultan village Soomra and hamayun town etc located along the road length, but are located fairly away from the ROW. These are not impacted by the road in anyway. However, there are a few structures located in encroached ROW near above said settlements which have been affected and they will be fully compensated. The location map of the whole length of the project road is presented in Figure 1 and the part of the road under Section-IV (53+450 to 68+358) is highlighted in Figure 2. For more clarity, a linear plan of Section-IV of the Sukkur- Jacobabad (N-65) is presented in Figure 3 showing the details regarding the magnitude of impacts at various chain-ages (km) of this section.

Figure 1: Location Map of Sukkur–Jacobabad Road Project

Project Site (Section-I)

Figure 2: Layout Plan of Sukkur – Jacobabad Road Project (N-65)

Section‐IV (53+450 to 68+358)

5

Figure 3: Linear Plan of Sukkur-jacobabad Road Project (Section-IV)

6

1.5 Objectives of the updated Resettlement Plan (Section-IV)

18. The LARP for Sukkur-Jacobabd (N-65) was prepared in 2009, which was categorized as A based on the project impacts, and a full Resettlement Plan was prepared, which ADB approved in 2009. Delayed implementation of the project required to update Resettlement Plan to capture additional impacts (if any) due to time lag and cap the gaps in the inventory of losses identified in October 2010 by a joint survey team of NHA and a staff consultant form ADB. However, to facilitate the commencement of works, following IR policy requirements, sectional approach was agreed for updating of Resettlement Plan. So, the subproject is divided into four Sections for updating and implementation of LARP independent to each other (See para. 12). This updated resettlement plan is to the extent of Section-IV (53+450 to 68+358) of Sukkur-Jacobabad (N-65).

19. The updated Resettlement Plan (Section-IV) of the Sukkur – Jacobabad project has been prepared in line with the ADB Policy on Involuntary Resettlement (1995) and applicable national laws for making payment of compensation of, buildings/ structures, trees, livelihood losses and other assets. Furthermore, this updated RP (Section-IV) includes the project impacts on livelihood of the people, compensation/ rehabilitation eligibility and entitlements provisions; institutional arrangements, complaints/ grievance redress, implementation schedules, budget, and monitoring program.

20. Land acquisition is not required under this Section-IV. All proposed civil work activities are confined to the ROW in the proposed section. The only impacts are identified mainly on the commercial structures constructed in the RoW by the encroachers. However impacts on few residential structures including rooms, walls and gates are also identified. All impacted residential structures are also located in encroached ROW and the owners of such structures have no title of land. Thus, there will be no land acquisition and no compensation for land losses. The identified APs include structure owners, business renters (business owners doing business in rented in structures) and the employees if any. In Total 73 are affected households (AFs) out of which 28 AFs are the structure owners, 28 AFs fall under business renters category and 17 AFs under employee category. During consultative meetings the structure owners confirmed that they will reconstruct damaged/dislocated structures in adjoining land owned by them, outside ROW. The impact analysis reflect that out of 28 AFs falling in structure owner category 11 AFs will face permanent loss of their income due to their structure loss and 7 AFs will face temporary loss of their income due to partial structures loss. However, the business renters will shift their business in alternate rented in structures without any business interruption and will not face income loss as such except for loss of monthly rent paid in advance. Therefore, to restore the livelihood of AFs the income losses of the structure owners against permanent or temporarily loss of income and for business renters the loss of monthly rent paid in advance due to relocating their business in alternate place is compensated as per provisions of entitlement matrix as detailed in para 73. On an overall basis, it is perceived that the project impact will be transitory and temporary in nature with no physical resettlement or dislocation of the project affected person as the AFs will reconstruct/rehabilitate their business structures in the same settlement along the carriageway. However, all compensation will be paid prior to physical possession of the land and confirmed by the external monitor.

2. SOCIOECONOMIC PROFILE OF APs

21. The information regarding socioeconomic conditions of APs were derived from primary data (field survey) from project alignment falling in Section-IV and data collected from secondary sources, i.e. data from Population Welfare Department (2010), data from Development Statistics of Sindh (2008), District Population Census (District Shikarpur), Agriculture Extension Department Shikarpur, Design Utility Folders of the Project and other. The primary data include census survey of all affected families which covered the

7

socio-economic profile of each affected family. It is used to determine the project impacts on each AP with respect to asset/income losses and provide compensation accordingly to mitigate the identified impacts. However, the macro level demographic and socio economic profile of the area is derived by use of socio-economic profile of randomly selected 25% sample from total affected population in the project area and information provided in the approved Resettlement Plan and secondary data collected from in line departments.

2.1 Administrative Setting

22. The project road, i.e. Section-IV (53+450 to 68+358 km) falls in the jurisdiction of . The location of Jacobabad can be explained as 44 K.M North West of Sukkur. According to 2010 data the total area of the district is 2750.65 (Sq Km). This District enjoys its integrity because of its situation, which adjoins it with three provinces, simultaneously. That is, it borders with Rajanpur District of the Punjab Province along its eastern side. It also borders with the Nasirabad district of the Baluchistan Province on its North Western sides. All the same it joins its Southern and South eastern borders simultaneously with four Districts of its parent province of Sindh. These adjoining Districts are District in its South, District Shikarpur in south east and District Sukkur in its east and District in its east south. The district is administratively subdivided into the following Talukas: Ghari Khairo, Jacobabad and . .

23. According to the 2010 census it had a population of 980,296 of which 17.3% were urban. And the annual growth rate is 2.01. The dominant characteristic of the population of this district is tribal one. The tribal system is in the kith and the core of this district. Right from unmemorable times, the residents of this district have remained divided and sub- divided into groups and subgroups called the tribes and clans.

2.2 Literacy Status

24. The average literacy rate is 37.3%, out of which 32% had primary level of education, 29% had education up to Matriculation level and 23% had qualification up to intermediate level and only 16% were graduate and postgraduate.

2.3 Income Status

25. On overall basis of the census inventory for the project alignment falling in Section- III, 48% APs had their income ranging below Rs.10000 / month, 34% were belonging to the income group of Rs. 11000-20000/ month, 15% come under the income category of Rs. 21000 to 30000/ month and 3% had the income between Rs. 31000 to 40000/ month. The Structure owners or business renters AFs falling in the income level below Rs 10000 will encounter income loss due to loss of their assets. However, to determine the AFs living below poverty level with respect to Officially Declared Poverty Line (OPL)5, per-capita income of each family was calculated by using census data on income status and household size. The analysis reflected that there are 17 affected families (structure owner and business renter categories) which have earning below poverty level and thus are identified as vulnerable. All such structure owners/Business Renters falling in Section-IV project area will be paid (i) business employment, (ii) relocation allowance, and (iii) vulnerability allowance. While The APs falling in employee category will be provided with one employment allowance equivalent one month’s wage base on official minimum wage

5. The OPL of Rs. 944 per capita / month was determined by the government in 2005–2006 (Pakistan Economic Survey, 2005–06, Table 41) which has been taken as base to assess the vulnerability of Project Affected Persons. This OPL is adopted as base because the government has not updated the OPL since then. However, keeping in view worldwide increase in food basket prices during recent years and increasing trend in poverty level in Pakistan the project Affected Persons earning below Rs. 1200/ per capita/month are taken as vulnerable.

8

rate to safe guard any adverse impact on their income status.

2.4 Borrowing Status

26. About one-third of the Sample population (i.e. 37%) had obtained credit from both formal and informal sources such as bank, landlords, and relatives.

2.5 Housing Characteristics

27. As the housing conditions are concerned, about 27% of the respondents located along the project road had their katcha houses and 49% respondents had semi-pacca houses, while remaining 24% had pacca houses.

2.6 Social Amenities

28. As far as access to social amenities is concerned, survey results have shown that on overall basis, almost all the respondents had electricity in their houses whereas 43% had the facility of water supply. About 15% to 20% sample respondents had access to the facility of gas, landline phone and sewerage system. Communication network (especially road network) is a prerequisite for undertaking the economic activity. In this context, the adjoining villages along the project area are well connected with the road network through both link and main roads. Project area lies on the belt where underground water is brackish and is not suitable for drinking or even for agriculture purpose, but ironically most of the villagers have no other source of water supply and they have to fetch water from other adjoining areas.

29. Health conditions are one of the major indicators of a society’s social development and quality of life. Healthy manpower is imperative for the advancement and economic growth. The health conditions are good in the area, as no serious disease was reported there. Qualified lady health visitors are mostly non-existent in the area with major reliance on traditional child birth attendant for assisting the delivery. Comparatively, larger villages have the facility of basic health units/ dispensaries. In most of the village people used to consult private practitioner and quacks.

2.7 Status of Agriculture in the Project Area

30. Agriculture in the vicinity of N-65 is predominantly irrigated agriculture. The project area depends on non-perennial canals. The shortage of water is generally experienced in winter and it greatly hampers the crop cultivation for Rabi season. The area is irrigated by canals originating from . The project area is mainly a rice growing area. The main crop grown during Kharif season is Rice. Cotton is also grown but there is a significant variation in its production. Major Rabi season crop is wheat. Vegetable and fodder is also cultivated but at small proportion of the cropped area. However, this section of the road does not have any direct or indirect impact on the crops grown in the privately owned lands along the project corridor. Some encroachment related impacts exist within the ROW, owned by NHA. During field survey it is identified that crops are grown in the ROW by the adjoining landowners by encroaching into the ROW. Under ADB policy (1995) requirements, one crop (six month) earlier notice to vacate the ROW encroached for agriculture use is served to all respective encroachers, hence no crop compensations are included in this updated RP (Section-III).

9

Table 1: Major Crops with their Average Yields Kharif Crops Yield/ acre (kgs) Rabi Crops Yield/ acre (kgs) Rice (Basmati) 1400-1700 Wheat 1000-1200 Cotton 200-1000 Fodder 10000-12000 Fodder 10000-12000 Vegetable 1800-3600 Tomatoes 18000-25000 Sunflower 600-800 Source: Agriculture Extension Department Sukkur and Shikarpur

2.8 Economic Activity in the Project Area

31. There are few industrial and commercial activities in the project area. Only some small industries are lying in the vicinity of the project road, i.e. some Rice husking factories, an oil mill, a rice mill, few pickle making factories and temporary brick kilns. Some crop storage depots are also located along the roadside, oil and gas explorations are also in progress around the project area.

32. The livestock in the area includes cows, buffaloes, goats and bullocks, which are mainly reared at domestic level and for agricultural farming and domestic use.

2.9 Social Impacts

33. The project will exert some social impacts on the project affected persons (structure and business owners), which are transitory and temporary corresponding to the execution of civil works only within the ROW. The commercial structures within encroached ROW will be rehabilitated or reconstructed outside ROW limits by the encroachers and the business activities will be resumed accordingly. The construction works within ROW will affect the agriculture activity being carried out within encroached ROW by the adjoining land owners. But it may not exert any tangible social impacts on the agricultural community as the Land owners (who have encroached adjoining ROW) had sufficient privately owned land to continue their agricultural activities. However, keeping in view the temporary interruption in the economic activity transitory support is provided to the Affected Persons.

2.10 Resolution of Community Disputes

34. Community disputes generally depend on the nature of conflict. Minor disputes are normally settled within the community. The village leader known as “Wadera” takes the leading role regarding disputes resolution. However, larger disputes, political differences are referred to the court of law but sometimes the influential people may play a vital role to resolve the issues amicably.

2.11 Women Involvement

35. Women have less opportunity to get education as there are a limited number of educational facilities (schools) for women in the area as reported by the 44% of the sample women. In some cases, women have to go in other villages to get education. About 30% women are literate, while 70% are illiterate. About 28% are working women and 72% are housewives. About 44% women were of the view that they had access to education, while majority of the women (56%) have no such opportunity to get education. This shows lack of education facilities and relatively less trend to educate the females in the project area. About 26% of women said that they had just a little access to lady health visitors, while 18% had access to government doctors. However, 32% women visited private doctors in case of sickness, whereas 24% women consult the quacks. In general, most of the local women involved in farming activities as daily wage laborers like transplanting and harvesting of rice and picking of vegetables etc. along with their male members. The construction activity is

10

confined within the ROW and there are no economic activities currently taking palce within the ROW, which could have been the source of women’s movement in the ROW. Therefore, the project does not envisage any restriction on women’s daily activities outside the ROW.

2.12 Existence of Community based Organizations

36. In the Sukkur and , an NGO named as ‘Marrie Stopes Pakistan’ is working on reproductive health. However this NGO does not have any direct or indirect role in land acquisition and resettlement matters.

3. IMPACT ASSESSMENT

3.1 Impact Assessment Survey and Cut-off Date

37. The resettlement survey conducted on 10-10-2010 to 19-10-2010 includes the impact assessment/ Census of 100% APs, socioeconomic profile of APs and consultations with APs and other local community members. NHA has updated6 the impacts of the project considering the site situation. In this context, this resettlement plan has covered the project impacts for Section-IV (53+450 to 68+350).

38. The previous cut-off date was 31 December 2010. Fresh survey of project impacts was carried out in March-April 2011, and based on the findings, inventory of impacts and list of APs were finalized. Therefore, new cut off date was fixed as 30 April 2011 and it was communicated to the APs along the road during the fresh field survey and consultation meetings with APs. This indicates that all APs who will settle in the project area and buildings built after this date will not be entitled to compensation or rehabilitation under the provisions of this updated RP (Section-IV).

39. Under this Section, the proposed project civil works activities will be retained in the designated ROW and no land acquisition is required. The strip of land required for widening of the road is already the property of NHA that will need clearance within settlements where people have constructed residential/commercial structures (Otaks, Shops, hotels and Chapras etc) by encroaching into the ROW, To compensate such assets facing impact due to project activity, price assessment has been carried out by the respective government departments to determine the unit rates. For structures; the price assessment was made by the Communication and Works Department and the rates in case of compensation for wood trees were assessed by the Forest Department while compensation for fruit trees is assessed by the agriculture extension departments of respective districts.

3.2 Project Impacts

40. The project impacts include the following:

(i) Loss of residential/commercial structures and temporary interruption of business/commercial activity. (ii) Loss of private/ community structures (iii) Loss of trees (fruit and non-fruit trees) (iv) Loss of public structures/ infrastructures

6. The impact of the project was significantly under assessed keeping in view the site situation.

11

3.2.1 Land Acquisition

41. No land acquisition in the Section-IV (53+450 to 68+350) of the project will be required as the land needed for the construction of the project is the property of National Highway Authority (NHA).

3.2.2 Building/ Structures (Shops/ Room)

42. It was noted that there are number of commercial structures (shops, hotels, veranda, kiosks & thatched shed) and few residential structures located within the project alignment. The data summarized in Table 1 depicts that on the whole, there are total 67 Nos. structures located within the project area. Out of which, 47 are permanent structures (including shops, hotels, residential rooms/veranda and Dairy Farm/animal shed etc), while 19 temporary structures includes wooden cabins (kiosks) and thatched sheds (Chapras) are also located within the project ROW. Besides above, One temporary brick kiln (intermittent type), is extended in the ROW and is subject to project impact to the extent of its part in ROW. The inventory of structures is annex-1 and the census inventory of APs with their respective entitlement is provided as Appendix -1.

Table 2: Details about the Structures Located in ROW. Sr. No. Detail of Structure No of Structures Total Built-up Area (ft2) 1 Commercial (Shops, hotels, veranda etc.) and Residential Structures (i) Pacca RCC 4 938 (ii) Pacca T-Iron Girder 29 4862 (iii) Katcha 1 1800 (iv) Girder and Wooden Roof 13 4549 2 Others (ii) Wooden Cabin 4 ----- Chapra 15 3281 Temporary Brick kilns 1 1 Total 67

3.2.3 Community Structures

43. As far as community structures/infrastructure is concerned, there are 6 community structures including brick mosque rooms, ablution place and boundary walls. Caretakers of the community structures or the Mosque Committees will be provided with replacement cost for rehabilitation of the remaining structures or reconstruction of the mosques at alternate place out of ROW. And, if owners want, NHA will also facilitate reconstruction of such structures through civil works contractor. The detail regarding affected community structures is given in Annex 2.

12

Table 3: No. of Community Structures located within the Project Area No of Total Built- Detail of Structures Remarks Structures up Area (ft2) Mosque Ablution place 1 49 Pacca RCC Structure Compensation to be paid to the Mosque Masonry with 3 758 caretakers/mosque committee Girder and T-iron roofs based on replacement cost. Compensation to be paid to the Mosque Masonry with 1 196 caretakers/mosque committee Girder and wooden roofs based on replacement cost. . Compensation to be paid to the Mosque (upto 5 feet) 1 58 caretakers/mosque committee pacca based on replacement cost. Total 6

3.2.4 Public Structures

44. The data given in Table 4 indicates that there are 3 public structures (police check post) located within the RoW of the existing road, which will need to be relocated. The concerned public offices/occupants of these structures have been requested to relocate these structures to clear the ROW and facilitate execution of the project works. However, the detailed costs for relocating these structures are worked out on replacement cost basis and are provided in the budget of the RP to meet the financial implications if required. Details regarding these public structures are given in Annex 3.

Table 4: No. of Public Structures located within the Project Alignment Sr. Detail of No of Total Built- Remarks No. Structure Structures up Area (ft2) Public Infrastructure The concerned government i) Pacca (T&G) 1 210 departments / occupants of these structures will be ii) Kacha 1 156 requested to relocate these structures at their own. However, costs for relocating iii) Chapra 1 210 these structures are worked out on replacement cost basis and are provided in the budget of Total 3 this RP to meet the financial implications if required.

3.2.5 Inventory of Trees

45. There are total 429 trees owned by the Forest Department, which will have to be removed. Out of these 414 trees are the timber wood trees while 15 trees of different size and age are the date trees grown within the ROW limits. The timber wood trees include eucalyptus and kikar (acacia), etc. (Table 4). The details are given in table 4 below and annex 4 attached to the updated RP (Section-III).

46. NHA is willing to contribute for replenishment of these trees, or do the re-plantation along the ROW. The requisite budgetary provisions are made in the Civil Works Contract in bill No.6 ancillary works. No sooner the civil works are completed the NHA will ensure

13

plantation of required number of trees in supervision of afforestation wing working under GM EALS.

Table 5: No. of Trees Located within the Project Alignment S# Type of Trees No of Trees Remarks 1 Dates 15 Owned by Fores Departmentt 2 Sofida 271 “ 3 Kikar 113 “ 4 Muskit 13 “ 5 Sheeshum 01 “ 6 Bair 05 “ 7 Khabbar 01 “ 8 Lao 05 “ 9 Neem 04 “ 10 Sharien 01 “ Totl 429

3.2.6 Affected Crops

47. The Project activities will not exert any tangible adverse impact on the agricultural activity in and around the project corridor. However, during the fresh survey it was observed that the adjoining land owners are practicing crops cultivation in parts of ROW on both sides of the road by encroaching into the ROW. Main crops grown include wheat, Rice and fodder crops during Rabi and Kharif seasons. The Land owners have been given a notice to vacate the ROW with effect from 30th October i.e after harvesting of the current Kharif crop and refrain cultivation of ensuing Rabi crop in the encroached strips of ROW. Thus, there will be no substantial impact on the crops or income of the land owners to be compensated under project.

3.2.7 No. of Affected Families (AFs)

48. There are a total 73 families who will be affected due to construction of the project in section IV. The AFs have been categorized as follows: (i) owners of business structures, (ii) business renters (AFs doing business in rented in business structures and (iii) the employees of the business operators. Out of total affected families, 28 fall in structure owners category, 28 families fall in category of business renters and 17 APs are in the employee category. Inventory/ census List of AFs with their respective entitlements is attached Appendix-1.

Table 6: No of Affected Persons due to the Construction of Section-IV of the Sukkur- Jacobabad Road Project Total family Category of APs No. of AFs members (Nos.) Remarks Owners of business/residential structures 28 281 Business renters 28 274 Employees 17 114 Total 73 669

3.3 Vulnerable AFs/APs.

49. The AFs earning below poverty level are accounted as vulnerable due to their income status and are eligible for special treatment/support to restore their livelihoods. The income status of all AFs was analyzed to calculate the per-capita income of AFs to

14

determine vulnerability and the AFs earning Rs. 1200/- or below per-capita/month7 are defined as vulnerable for the purpose of this updated Resettlement Plan (Section-IV). There are 17 Affected Families falling in this range of per-capita income and are identified as eligible for vulnerability allowance.

3.4. Price Assessment of Land and other Assets

50. A brief description of unit prices and source of information is given in table 6 below:

(i) Trees and Crops (a) In case of wood/timber trees, the price per plant is assessed by the Forest Department keeping in view the “girth” of plant. All types of fruit trees are assessed by the Agriculture Extension Wing of Agriculture Department, Shikarpur District. These departments assessed and approved the unit rates which have been adopted as unit rates for calculation of compensation, and are provided in Annex- 6. For wood and fruit trees unit rates of June 2011 have been used for calculating compensation. . (b) Similarly for crop compensation, the unit market rate are assessed by Agriculture Department using the market rate criterion of net crop value for current year based on average yield per acre of different crops. These unit rates have been provided in annex 8. However the execution of civil works under Section-IV will not have any adverse impact on the agricultural activity in the project area so this LARP for Section IV does not include any crop compensations. (ii) Other Assets/ Properties

(c) For affected buildings and other structures, the unit rates have been approved by Works and Services/ Buildings Department, district Shikarpur based on June 2011 rates as replacement value unit rates. More details are provided in annex-7.

Table 7: Unit Rates and Source of Information *Unit rates Unit and Items/ Assets (June 2011) Remarks qty (Rs.) Structures/ Houses Structures a) Pacca (Commercial/residential structure) made of RCC and T-Iron material. Rs./ Sq.ft Notification of Building Department is at Annex- **RCC structures Rs./Sq.ft 850 7. Notification of Building Department is at Annex- T-iron girder Rs./Sq.ft 710 7. b) Semi Pacca made of Girder and wooden roof)(Commercial/residential Structure) Rs./ Sq.ft 530 “ c) Katcha (Commercial/resedential Rs./ Sq.ft 265 “

7 Please see Footnote 5 at page 10.

15

*Unit rates Unit and Items/ Assets (June 2011) Remarks qty (Rs.) Structure) d) i) Pacca (Boundary Wall) above 5 feet height 950 ii) Pacca (Boundary Wall) upto 5 feet height 870 iii) Kacha (Boundary Wall) above 5 feet height 200 Rs./ rft “ e) Wooden chappra Rs./ sq. ft. 100 “ f) Wooden cabin Rs./ unit 2,000 “ g) Temporary Kiln Shifting rate Rs./ unit 10,000 “ h) Gate Rs/unit 20,000 * Approved unit rates by the concerned Department, June, 2011, e.g., Works and Services Department, Buildings Department, Forest Department District Shikarpur.

4. OBJECTIVES AND POLICY FRAMEWORK

51. The updated RP (Section-IV) was prepared in line with the ADB’s Involuntary Resettlement Policy (1995) and Resettlement Framework Document of the Project (NHDSIP) and the Land Acquisition Act (LAA) of 1894 with its amendments.

52. ADB Involuntary Resettlement Policy discusses the three major points, i.e. i) IRP emphasizes that the absence of formal legal title to land is not a bar to entitlements and assistance, ii) the LAA assesses compensation based on the market value of acquired property, where the IRP emphasizes the payment of replacement value of all affected assets, iii) follow the participatory approach, information disclosure and discussion with APs and appointment of special committees such as grievance redress committees.

4.1 Compensation Eligibility and Entitlements for the Project

53. Land Acquisition and Resettlement tasks under the project will be implemented according to compensation eligibility and entitlements in line with Pakistan’s LAA 1894 and ADB involuntary resettlement policy. Under the LAA, only legal owners and tenants officially registered with the Revenue Department or with formal lease agreements are considered “eligible” for land compensation. As per the provisions of the LAA, cash compensation is assessed (under Section 5) on the basis of 1 year average registered market rate. To fit the requirements of the ADB policy, however, under this updated RP (Section-IV) also non-titled land users will be given a rehabilitation allowance for loss of land use (if any).

4.2 Eligibility for Entitlements of Compensation

54. All APs which will be entitled for compensation and / or rehabilitation provisions under this subproject are:

(i) Owners of buildings/ structures, trees; (ii) APs losing business, income, and salaries.

55. Fresh survey of project impacts was carried out in March-April 2011, and based on the findings, inventory of impacts and list of APs were finalized. So, for entitlement eligibility cutoff date was fixed as 30 April 2011 and it was communicated to the APs along the road during the fresh field survey and consultation meetings with APs.

16

56. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. However, they will be given sufficient advance notice to vacate premises and dismantle their affected structures prior to project implementation.

4.3 Compensation Entitlements

57. Entitlement provisions for APs losing property assets and income losses, the assistance/ allowance will include provisions for permanent and temporary losses, and trees losses, relocation assistance, and a business losses allowance based on government minimum per capita income/ minimum official wage rate. These entitlements are discussed as follows:

58. Entitlement provisions for APs losing structures (residential/commercial) and income losses and rehabilitation allowance will include provisions for permanent and temporary losses of income, house and buildings losses, crops and trees losses are discussed below:

(i) Residential/Commercial, buildings, structures damages. These impacts will be compensated in cash at replacement cost free of depreciation, salvaged materials, and transaction costs deductions. The compensation will include the cost of lost water supply, electricity or telephone connections. When a House/building is affected for more than 25% (or less than that but is structurally damaged) it will be compensated in its entirety. (ii) Government Trees: The government owned trees will be removed through Forest Department. As per Law and govt. policy the forest department is not entitled for compensation for trees subject to felling for public interest projects. However, as per policy the provision for replenishment of trees with a ratio of 1:10 is notified to ensure growing new trees in the public corridors to enhance forest area of the country. Following government policy, NHA in consultation with forest department shall made available adequate funds for replenishment/compensatory plantation. (iii) Businesses: compensation for permanent business losses will be in cash for the period deemed necessary to re-establish the business up to a maximum of 6 months period; compensation for temporary business losses will be cash covering the income of the interruption period up to 3 months. While the business renters (AFs doing their business in rented in shops) will shift and re-establish their business by moving to premises available on rent outside ROW in same locality. However, such AFs wiil face loss of monthly rent paid in advance to structure owners and will have to pay monthly rent for new premises as well. To compensate this, they will be given cash assistance equivalent to two months rent / official wage rate (whichever is more) to relocate their business at alternate premises. (iv) Transportation/relocation Allowance: One time assistance/ allowance at rate of Rs 5000 will be paid to each and every house hold eligible for this allowance. (v) Community Structures and Public Utilities: Will be fully replaced or rehabilitated so as to satisfy their pre-project functions. (vi) Vulnerable people Livelihood: Vulnerable people (APs below the poverty line and or widow, orphans, women household heads, landless etc.) falling in Corridor of Impact require special assistance/support to restore their livelihood and sustain their living standards. All such APS will be provided with one special allowance equivalent to one month’s official wage rate. Besides, they will be given priority in employment in project-related jobs through civil works contractor during execution of the project. The relevant contract clauses have been included in the civil works contract.

17

4.4 Eligibility and Entitlements

59. All families residing in affected areas and holding affected assets or incomes before the eligibility cut-off date for the project set as 30 April, 2011 will be entitled for compensation and/or rehabilitation for their losses. Based on the project situation and impacts assessment, there was impact and compensation pertaining to the loss of structures and trees as well as crops. However, other impacts so far unidentified may occur during the implementation which will also be compensated based on the entitlement matrix given in the following Table 8.

Table 8: Entitlement Matrix

Asset Specification Affected People Compensation Entitlements Building and All APs  Cash compensation at replacement rates for Structures (including affected structure and other fixed assets free of encroachers/ salvageable materials, depreciation and squatters) transaction costs. In case of partial impacts full cash assistance to restore remaining structure. Government To be replenished or replanted  Re-plantation/ replenishment will be provided at Trees8 a ratio of 1:10 (for each felled tree 10 new trees will be planted) to enhance the forest resource base of the country). 9 Business/ Temporary or All APs (also  Business owner : (i) Cash compensation equal Employment permanent squatters) to 6 months income, if loss permanent; (ii) cash loss of compensation for the business interruption business or period up to 3 months, if loss temporary. 10 employment  Business renters will be entitled cash compensation equivalent to two months rent/official wage rate to relocate their business at alternate premises.  Employees: i) Cash compensation equivalent to one month’s Salary based on minimum wage rate approved by GOP. .ii) Employment priority in project-related jobs. Relocation Transport All APs so  Provision of one time assistance as allowance affected (including relocation/transportation allowance at the rate squatters) of Rs. 5,000 to all entitled. Communal  Rehabilitation/substitution of the affected assets structures/utilities at replacement value without any deductions/depreciation Livelihood/ AP under poverty  One special allowance of Rs. 7000 Vulnerability line  Employment priority in project-related jobs. Allowance AP

8 Forest Department is responsible to remove the government owned trees to facilitate execution of public interest projects. However, the EA has to send a formal request to Forest Department with details of trees subject to be removed. Upon receipt of the request the Forest Department auctions the identified trees as per Government Policy. For such removal Forest Department is not entitled for compensation of trees. However, as per government policy the EA has to ensure funds for replenishment/compensatory plantation at a ratio of 1:10 i.e for each felled tree 10 new plants to be grown as compensatory plantation. 9 Business owner: AFs, who themselves are running business in their owned affected structure and are subjected to permanent or temporary business loss due to loss of structure are entitled for compensation as proposed along with compensation for structure loss. 10 Business renters: AFs, who are running their business in rented in affected structures, will shift their business in other rented in structures outside ROW and there will be no impact on their business as such. However, they will face loss of monthly rent paid in advance to the structure owner, which has been compensated to minimize the adverse impacts (if any) and facilitate the shifting of business articles at alternate place with financial support equal to two month’s rent..

18

5. PUBLIC CONSULTATIONS AND DISCLOSURE

60. Before the commencement of the Project fresh consultations during March, to May and September, October 2011, were held in which about 20 APs participated from settlement along road side like Begari, Abad, and Kahar. List of participants is given in Annex.5 The local community/ APs provided the details regarding their issues associated with the implementation of this project. Furthermore, all APs have been informed regarding the implementation of LAR activities, cut-off date, eligibility and entitlements for compensation by the Land Section, office of the Project Directorate, Sukkur during their consultations and coordination meetings with the APs.

61. The major concerns/ issues and feedback highlighted are discussed as below:

(i) All APs were satisfied with this whole project plan and were willing to provide all cooperation in this regard. (ii) Local labour should be hired during the construction of this road project11. (iii) Traffic control measures should be adopted to regulate the traffic flow. (iv) Corridors/ Passages should be built for cattle’s at suitable locations along the road12. (v) Over loading of the vehicles should be monitored for the long lasting life of the road. (vi) To minimize the accidents speed control measures should be adopted. (vii) During the construction phase the dust pollution should be minimized. (viii) Trees should be planted along the road side to minimize the impact on environment as well as cutting of trees. (ix) Avoid dismantling of social/ religious infrastructure like mosque and schools, graves. (x) Proper traffic diversion system should be adopted in order to avoid traffic congestion and related hazards.

62. Some other problems relating to the local women and children are as follow: Construction should be done as fast as can be because, in some emergencies, women and children will have to go hospitals for heath care purposes.

63. The community/APs had been informed about LAR impacts and the eligibility criteria in consultative meetings during preparation of updated RP (Section-IV). However, the disclosure of the approved RP before its implementation is mandatory under ADB’s communication policy. Therefore after endorsement of RP by ADB, the APs will be provided all project related information including information brochures covering all necessary details about entitlement matrix, details of project impacts and compensation, grievance redress system and contact persons, etc, before starting payment of compensation and physical displacement.

64. The LAR Unit will have the responsibility to translate the summary of updated RP (Section-IV) in local language (/ Sindhi) and disclose it to the APs and other notable local community members located in the jurisdiction of Section-IV. Disclosure of updated RP (Section-IV) will be done, after its approval by the ADB. Copies of Urdu/ Sindhi version of updated RP (Section-IV) (Brochure) will also be placed at the office of Project Directorate and PIUs and will also ensure its availability to the APs.

11 Contractor will engage the requisite local staff through contract agreement 12 It is the desire of the people as identified during consultations. In fact, this will not be required as this road is already constructed.

19

65. Addressed Issues

(i) All necessary facilities (like foot bridges and crossings ) will be provided to the APs (ii) In relevance to existing tracks/routes to facilitate communication and daily routine activities for the local population. (iii) All the construction work will be confined within the proposed Right of Way (RoW). (iv) Payment of structures/ properties assets will be made prior to start the civil work. (v) All important infrastructures will be restored by providing culverts, bridges, waiting sheds, flyovers & underpasses. (vi) A tree plantation program to compensate for the anticipated loss of vegetation during the construction activities, and to help abate pollution caused by emissions, dust, and noise during highway operation; and (vii) Project construction camp will be located at a minimum distance of 500 meters away from existing settlements and built-up areas. In order to avoid restricting the mobility of local people, construction vehicles will remain confined within their designated areas of movement. (viii) Sensitivity towards local customs and traditions will be encouraged to minimize social friction. In this respect, good relations with local communities will be promoted by encouraging contractors to provide opportunities for skilled and unskilled employment to locals, as well as on job training in construction for young people.

6 COMPENSATION, RELOCATION AND INCOME RESTORATION

6.1 General

66. As discussed in chapter 3 land acquisitions is not envisaged to implement and execute the civil works under this section of the road. The only impacts are identified on the structures constructed in the ROW (NHA owned property) by the encroachers. This section deals with the compensations for affected, structures and assets identified during the Census Survey. The updated RP (Section-IV) focuses on providing compensations for the lost assets of APs and suggests measures to restore their livelihoods to former living standards. The compensation is based on the provisions of the EM and the unit rates provided in Table 8.

6.2 Compensation for Privately Owned Structures

67. The privately owned affected structures are mostly commercial structures constructed in the encroached ROW by the APs and include (i) shops, (ii) verandas/sheds, (iii) chapras and wooden cabins. However, few residential structures constructed in ROW are also falling under impact and include residential rooms, Otak (a place away from house to sit and meet people) and chapras. There is one temporary type of brick kilns a small portion of which is under impact due to its location in ROW. To estimate the replacement value of the affected structures, the assets have been standardized for compensation on an average unit rate per sq. ft. as given in Table 7 and updated unit rates have been provided by the respective C&W department of Shikarpur District

20

Table 9: Valuation of Privately owned Affected Structures/Assets Unit Rate Total (Rs./ ft2 )* Sr. No of Built-up (approved Total Cost No. Detail of Structure Structures Area (ft2) June 2011) (Rs. M.) Remarks 1 Commercial/resedential structures (Shops, hotels, veranda and rooms etc.) (i) Pacca RCC 4 938 850 797300 - (ii) Pacca T-Iron Girder 29 4862 710 3452020 - (iii) Katcha 1 1800 265 477000 - iv) Girder and Wooden Roof 13 4549 530 2410970 2 Others (i) Wooden Cabin 4 ----- 2000 8000 (ii) Chapra 15 3281 100 328100 (iii) Temporary Brick kilns 1 1 10000 10000 Total 67 7483390 * Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, District Shikarpur.

6.3 Compensation for Community Owned Structures/Assets

68. There are 6 community owned affected structure / assets including mosques a dargah (Shrine) room and mosque and a wall. The loss to these structures is compensated adequately on replacement cost basis. The extent of impact both in quantity and estimated costs has been summarized in Table 10 and details are provided in Annexure-3.

Table 10: Valuation of Affected Community Owned Structures/Assets

Detail of No of Total Unit Rate Total Cost Sr. No Structure Structures Area (ft2) (Rs./ ft2 )* (Rs. M.) Community Structures (Mosque Rooms, Verandhas and walls etc)

Pacca (RCC), 1 Ablution Place 49 850 41650 (iv) Pacca T&G 3 758 710 538180

Pacca (GWR) 1 196 530 103880 Walls (Hieght upto 5 ft) Pacca 1 58 870 50460 Total 6 734170

6.4 Compensation for Public infrastructure/Assets

69. The survey has revealed that 3 structures falling in public infrastructure category are being affected in this sub-project. All these structures are constructed in the encroached ROW by the Police/Customs Department. These structures include two rooms and a chapra being used as check posts. The concerned departments will be requested to clear the ROW

21

by relocating the identified structures at their own. However, if required the structures/assets may be compensated on replacement cost basis through relevant departments. To meet the financial implications (if any) the cost of all the structure encountered during census survey is worked out on replacement cost basis in accordance with unit rates provided by the C&W department of respective district. The details of the structures and the cost estimates are provided in table 11 below

Table 11: Valuation of Affected Public Structures/Assets Unit Rate (Rs./ Detail of No of Total Built- ft2 )* (approved Total Cost Sr. No. Structure Structures up Area (ft2) June 2011) (Rs. M.) Public Infrastructure i Pacca (T&G) 1 210 710 149100 ii Kacha 1 156 265 41340 iii Chapra 1 210 100 21000 Total 3 211440 * Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, District Shikarpur.

6.5 Provisions for Compensatory Plantation

70. In total 429 trees owned by the Forest Department, which will be removed from ROW to execute project civil works. Out of these 414 trees are the timber wood trees while 15 trees of different size and age are the date trees grown within the ROW limits. The NHA will request Forest Department for removal of these trees to avoid any damage and consequent compensations to forest department. However, for replenishment of these trees, compensatory plantation at a ratio of 1:10 is proposed in consultation with Forest Department and will be carried out by NHA under supervision of afforestration wing in EALS Section. The adequate budgetary provision is made in civil works contract in BOQ (Bill No 6 “ancillary works”). So, this updated RP (Section-IV) do not include cost for compensatory plantation.

6.6 Relocation Options

6.6.1 Privately owned Structures

71. All structures falling under project impacts are constructed by encroaching land within the RoW. The owners of these structures will be compensated for structures only at replacement cost basis as per entitlement provision provided in the approved resettlement frame work for NHDSIP. Besides compensation of structure loss, for transportation of salvage material a lump sum amount as transportation allowance will be provided to each entitled AH13. Alternate land or compensation for land will not be provided to relocate these structures. During consultative meetings the structure owners affirmed that they will rehabilitate their remaining structure outside ROW or reconstruct new structure at their own in their land available outside ROW.

13 As a matter of equity, the transportation allowance is provided to all AFs facing loss of structure (permanent/partial) or business renter to handle/shift/transport salvage material or shift business articles from impacted structure to new rented in structure. Detail of transportation allowance is provided in para 74.

22

6.6.2 Religious Structures

72. The most of the mosques are constructed along the road in ROW by the adjoining land owners for providing prayer places to the passersby. All mosques will need to be relocated due to project works. Construction of dual carriageway will left no space to reconstruct or relocate these structures in the nearby NHA owned ROW. Thus NHA will provide compensation for structures on replacement cost basis while, the Community/Custodians of these community structures will relocate and reconstruct these religious structures outside ROW.

6.6.3 Additional Assistance for Vulnerable Households

73. 17 AFs falling in structure owner and business renter category having per-capita monthly earnings below Rs. 1200 are identified as vulnerable. For such households, in addition to the compensation for their affected assets, an additional allowance of Rs. 7000 (amount equal to minimum official wage rate) will be paid as additional assistance. The amount of compensation to be paid on this account comes to be Rs. 119,000/=.

6.7 Income Restoration

74. It is anticipated that the project will make a positive impact on the economy of the area in general. A number of business and employment opportunities will be created during the construction and operation phase, for the business entrepreneurs and skilled/un-skilled labor respectively resulting into increased economic activity in the project corridor. However, to compensate the adverse impacts on source of livelihood due to loss of commercial structures the business/employment interruption allowance is provided on the basis of entitlement matrix (table 8) prepared in accordance with approved Resettlement Framework for NHDSIP. The table 12 below gives the detail of the AFs facing business/employment loss and their entitled compensation.

Table 12: Estimation of Livelihood Allowance for Affected Households

Sr. No. Type of Loss AHs (Nos.) Allowance Rate** Total (Rs.) Permanent Loss of 1 Income 11 42000 462000 Temporary Loss of 2 Income a. Structure/business owners 7 21000 147000 b. Business Renters 28 14000 392000 3 Employment loss 17 7000 119000 Total: 63 0 2982000 ** The allowance rate is based on the approved official wage rate @ Rs: 7000/month and for each category is calculated on the basis provided in EM i.e: Permanent loss of income = 6 months x official wage rate. Temporary loss of income = 3 months x official wage rate . Business renters = 2 months x official wage rate. Employee = 1 months x official wage rate.

23

6.8 Transportation Allowance

75. One time Transportation allowance is provided to All the AFs falling in structure owner and business renter categories, subject to shift/transport slavage material of their demolished structures or their business items from the impacted structure to alternate place. In total 56 AFs are entitled for Transportation Allowance for which Rs. 280000/- is provided in the budget.

7. INSTITUTIONAL ARRANGEMENTS

76. Overall responsibility for planning, implementation and monitoring of the Land Acquisition and Resettlement activities in accordance with the agreed LARF and loan agreement rest with the Executing Agency i.e NHA. The EA has a compact institutional setup for managing all LAR activities. NHA has appointed a Member for Aided Projects, and in his supervision a General Manager ADB Projects and General Manager Environment, Afforstation, Land and Social (EALS) wing at Head Quarter are working with an overall responsibility of ensuring safeguard compliance requirements under the aided Projects.

77. The NHA will exercise its all functions at project level through Project Management Unit/project directorate established at Sukkur. For updating, implementation and monitoring of the RP the project directorate will be facilitated by Land Acquisition and resettlement Unit, which will ensure timely establishment of Grievance Redress committees, Affected Persons and Citizen Liaison Committee, effective consultation and coordination with line department during prepration and implementation of the updated RP (Section-III).

7.1 Land Acquisition and Resettlement Unit at Project Level

78. At project level a Land Acquisition and Resettlement Unit has been constituted and notified for streamlining of the Land Acquisition and Resettlement Activities relating to Sukkur Jacobabad (N-65) vide notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010, comprising of the following:

(i) General Manger (N-65) Chairman (ii) Project Director (N-65) Member (iii) DD (Environment) Member (iv) Resettlement Specialist, NHA Member (v) AD (L&S), HQ Coordinator

79. The scope of work of LAR Unit includes:

(i) The unit shall also act as a steering body for the LAR activities at the project and shall formally assemble once in a quarter. For routine LAR matters, special meeting/routine discussions can take place, as and when required. (ii) It shall ensure timely implementation of LAR activities and monitor the progress thereon during execution of the civil works. (iii) In order to efficiently deal with APs grievances, the unit shall coordinate on regular basis with the grievance redress and consultation committees (e.g. grievance redress committee and affected persons and citizens liaison committee; GRC and ACLC). (iv) Resettlement and land staff of EALS to coordinate and visit the project office on regular basis to provide guidance to the project level LARU in implementing the updated RP (Section-IV) and preparing the internal monitoring reports. (v) LARU will have one male and one female social mobilizer to assist in

24

consultation meetings, disclosure of project information, information sharing with APs related to disbursement of compensation and related tasks. (vi) LARU and EALS shall review all RPs before submitting to ADB. (vii) All EALS in consultation with LARU shall submit the final RP to ADB for review/concurrence. (viii) The LARU resettlement specialist shall prepare the internal monitoring reports on monthly basis and provide to ADB for review.

7.2 Grievance Redress Cell.

80. The grievance procedures at different stages of the Land Acquisition is provided in the Land Acquisition Act 1894, but in case of grievance arising from non-land impacts and issues there is no statutory mechanism provided in the LAA 1894. In this context and inline with the requirements of LARF and ADB IR policy a grievance redress committee has been constituted and notified vide notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010.. The GRC will have following members and roles and responsibilities:

(i) Project Director Chairman (ii) Assistant Director (L&S-Resettlement) (Focal Member) (iii) LAC assisted by Patwari / Qanoongo (to deal with crops and related matters) (iv) Representative of ACLC Member (v) External monitoring consultant. Member

81. The scope of work of grievance redress cell/committee is discussed as below.

(i) The GRC shall prepare a register for the purposes of entering each and every complaint either received directly from the AP or through H.Q or other outside agencies i.e. EDOR / DOR office, irrigation department forest department etc. (ii) These complaints shall be carefully categorized in separate heads as against price fixation of Land, crop, trees, structures etc. OR problems in relocation and seeking assistance for rehabilitation etc. Such complaints shall be disposed of within 30 days. (iii) The focal person of GRC shall submit its reports containing detail status of implementation i.e. internal monitoring reports (IMR) and regarding the disposal of complaints / Grievance of APs to Chairman LARU and Chairman PMU on monthly basis. (iv) Subsequent to receiving a formal complaint, LARU or EALS in consultation with project team (GM and PD) will review the complaint and inform ADB about the actions to be taken to resolve the complaint. (v) The GRC shall ensure that all field visits and consultations with the APs are properly documented, snapped and recorded on the video; such record shall be placed in the Project Office (PO). (vi) GRC after site visit shall prepare a report with recommendations and solution submits the same to the LARU/Project Directorate and resolves the problem accordingly. (vii) GRC shall close the complaint file by communicating with complainant.

7.3 Affected Persons and Citizen Liaison Committee

82. For improved coordination between the Project Management Team, LAR Unit, GRC and the APs, an Affected Persons and Citizen Liaison Committee has been notified by EA vide Notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010 dated and comprised of following:

25

(i) Assistant Director (L&S; resettlement specialist) (ii) Tapedar / Patwari (iii) Social Mobilizer (iv) Representative of affected village Member of ACLC

83. The ACLC will be responsible for the following activities:

(i) Shall establish the accessible information and conduct frequent consultative meetings with APs. (ii) Publicity of the designated office from where all information regarding alignment, design, road maps, (naqsha parcha) Revenue Maps of land to be acquired, price assessment and information regarding complaints status/ redress can be obtained by the APs, with name of the focal person to contact with. Mobile phone no. of all personnel of this unit must be mentioned for the convenience of the APs. (iii) It will also include announcement from village mosque. (iv) Shall place posters containing relevant information; on the particular places in the villages from where land has been acquired. (v) ACLC will ensure that the ‘LARP preparation Consultants’ MUST include all the affected persons (APs) along with the details of their property held e.g. land, structures, trees, crops, shops etc. Preparation of LARP shall be strictly in the light of LARF mutually prepared by NHA and ADB. (vi) The ACLC shall ensure that all field visits and consultations with the APs are properly documented, snapped and recorded on the video; such record shall be placed in the ACLC and GRC office. (vii) In parallel, Land acquisition activity after publication of section 4 is followed by the correct assessment price of land. The ACLC at the project shall ensure that adequate, just and proper price compensation is determined. (viii) The team of LARP preparation Consultants’ when mobilized shall be accompanied by officers / officials / members of ACLC and members of EALS if deputed by the H.Q. this is for the reason to avoid variation in reports, plans and to address the issues immediately on site. (ix) This inter-alia officers and members of ACLC shall include: i) Disclosure and sharing of information to APs, ii) Information through the local notables, Councilor and Chairman of the union Council; and iii) Distribution of copies of LARP in local language, prices of land and award must be disclosed to the local at this stage.

84. An Organogram showing the institutional arrangements for the implementation of land acquisition and resettlement activities has been illustrated through a diagram presented in Figure 4.

26

Figure 4: Institutional Set-up for the Implementation of updated RP (Section-IV) Member (Aided Projects) GM (EALS), HQ

GM (Aided Projects) Consultants

Contractor

LAR Unit (Sukkur) EMA  General Manger  Project Director  DD (Environment)  Resettlement Specialist, NHA  AD (L&S), HQ

District Level Departments

Revenue Department (DOR/ LAC) Agri. Department Forest Department APs & Citizens Liaison Grievance Redress Cell (GRC) W&C department Committee (ACLC) 1. Project Director PD (N-65) WAPDA 1. Assistant Director (L&S) 2.Assistant Director (L&S) Telecommunication 2. Tapedar/Patwari 3. LAC assisted by patwari/Qanoongo Other concerned 3. Social Mobilizer 4. Representative of ACLC 4. Representative of Affected Village 5. EM Consultant ACLC

APs/ Local Community

27

8. IMPLEMENTATION SCHEDULE OF UPDATED RP (SECTION-III)

85. Considering the magnitude of resettlement impact and other property issues, it is expected that the Project Directorate will be able to implement the updated RP (Section-IV) in 2 to 3 months from 1st December, 2011 to February, 28, 2012. Within this timeframe, the updated RP (Section-IV) milestones will be implemented as per following time schedule (Table 13).

Table 13: Implementation Schedule of LARP Action Timeline (Year Responsibility To date Status 2011) Updated RP (Section-IV) Implementation Establishment of Project - NHA PMU is already in place Management Unit (PMU) at at Sukkur. Sukkur Setting-up the LAR Unit (LARU) - NHA LARU has already been notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010. Establish Grievance Redress 1st July - NHA GRC has already been Cell (GRC) notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010. Establishment of ACLC 1st July - NHA ACLC has already been notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010. Approval of updated RP December10,,2011 ADB - (Section-IV) Urdu/Sidhi translation and December 20, 2011 PD/ LAR Unit To be done. disclosure of updated RP (Section-IV) Payments for structures and all Jan 31, 2012. LARU/APs - potential impacts Payments of allowances Jan 31, 2012.. LARU/APs - Internal Monitoring report of Monthly- First LARU To be done. updated RP (Section-IV) Report January 10. 2011. Date of contract award 31st Oct. 2010 - - Commencement of civil works in February,, 2012 - - Section-IV Redress of community Continuous activity GRC/ LARU This will be a continuous complaints activity till project completion. External monitoring External Monitoring EMA Field survey to be Report confirming completed by the full implementation January 31, 2012. of Updated RP. February 15, 2012.

28

9. RESETTLEMENT BUDGET

86. The resettlement budget includes (i) costs of commercial structures, community infrastructure, public and private structures, crops grown in encroached RoW and trees compensation, lively hood compensation as well as other costs (i.e. cost of training, independent monitoring and evaluation etc.). As shown in Table 8, the total cost for resettlement is estimated to be of Rs. 11088900 /= equivalent to US $ 127459..

87. Upon EA’s request ADB has agreed to finance implementation of resettlement plans from available contingencies amount under approved loan and required funds have been re-appropriated for resettlement costs. Thus the EA (NHA) has provided the above amount of budget to implement this LARP in an efficient and timely manner during the course of the project (Table 14).

88. However, the finances from loan component shall not be utilized for payment of land acquisition costs. The Loan part shall be exclusively used for making payments against resettlement costs attributed to encroachers/squatters for their assets (excluding land) and other resettlement entitlements/allowances to AFs/APs as proposed in the Entitlement Matrix of this updated Resettlement Plan. An itemized budget for implementation of the updated Resettlement Plan (Section-IV) is as under:

Table 14: Resettlement Budget No of Sr. Structure Total Unit Rate Total Cost No. Detail of Structure s Area (ft2) (Rs./ ft2 )* (Rs. M.) A Private Structures 1 Commercial/resedentials Buildings (Shops, hotels, veranda and rooms etc.) i) Pacca RCC 4 938 850 797300 ii) Pacca T-Iron Girder 29 4862 710 3452020 iii) Katcha 1 1800 265 477000 iv) Girder and Wooden Roof 13 4549 530 2410970 2 Others i) Wooden Cabin 4 ----- 2000 8000 ii) Chapra 15 3281 100 328100 iii) Kilns (Temporary) 1 10000 10000 Sub total A 67 7483390 B Public Infrastructure i) Pacca (T&G) 1 210 710 149100 ii) Kacha 1 156 265 41340 iii) Chapra 1 210 100 21000 Sub total B 3 211440 C Community Structures (Rooms, Verandhas and walls etc) i) Pacca RCC. 1 49 850 41650 ii) Pacca T&G 3 758 710 538180 iii) Pacca (GWR) 1 196 530 103880 iv) Walls (Hieght upto 5 ft) 1 58 870 50460 Pacca Sub total C 6 734170 D Other Costs i) Assistance Allowance to AFs 23 7000 161000 vulnerable APs

29

No of Sr. Structure Total Unit Rate Total Cost No. Detail of Structure s Area (ft2) (Rs./ ft2 )* (Rs. M.) ii) Restoration of Livelihood / Business Loss Structure owners with AFs 11 42000 462000 a) Permanent income loss Structure owners with AFs 7 21000 147000 b) temporary income loss c) Business Renters AFs 28 14000 392000 d) Employees AFs 17 7000 119000 iii) Transportation allowance AFs 56 5,000 280000 Sub total D 1561000 Total (A+B+C+D) 9990000 Monitoring & evaluation @ i) Job 1 99900 1% ii Contingencies (@10%) 999000 Total Cost (Rs.) 11088900 US$ @ of 87 Rs/$ 127459 *Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, Forest Department District Shikarpur.

10. MONITORING AND EVALUATION

89. The LAR activities under the Project will be subjected to both internal and external monitoring. Internal monitoring will be carried out by the Project Directorate, Sukkur through its LAR Unit with the assistance of resettlement specialist of supervisory consultants, while the external monitoring will be conducted by an independent external monitoring agency (EMA), which has already been deployed under the project. External monitoring reports will be prepared quarterly and semi-annually during the first and second year respectively of the implementation of the project.

10.1 Internal Monitoring

90. The internal monitoring will be carried out periodically by the LARU(NHA). Their results will be communicated to ADB through the monthly project implementation reports. The internal monitoring reports will cover these aspects:

(i) Information dissemination and consultation with APs; (ii) Implementation of entitlement matrix (iii) Payments for loss of income; (iv) Selection and distribution of replacement land areas (if required) (v) Income restoration activities; and (vi) Grievance/ complaints redress mechanism (vii) Physical and financial progress of LAR activities bifurcating the GoP and Loan components separately (viii) Other

10.2 External Monitoring

91. The external monitoring will be done on quarterly basis by an external monitoring agency to examine the process involved for the implementation of resettlement policy framework/ entitlement matrix and grievance redress mechanism. External monitoring will be carried out on quarterly basis during the first year and bi-annually during the second year

30

of the project implementation. There would be the final external monitoring report after the completion of resettlement activities.

92. As it is indicated earlier that there will be no land acquisition involved in this section of the project, so that the proposed timeline given to implement this updated RP (Section- IV), as per proposed plan given in the updated RP (Section-IV) implementation schedule and compensation for the loss of trees and other assets will also be completed. On the completion of LAR activities of this section, the external monitoring report will be prepared. In this context, an independent external monitoring agency has already in place and will be involved till the completion of the LAR activities for the whole project.

93. In general, the indicators for External Monitoring will include the following:

(i) Review and verify internal monitoring reports prepared by the Project Directorate, Sukkur; (ii) Review of the socio-economic baseline information during the pre-project conditions; (iii) Impact assessment through interviews, group discussions/ community consultations using structured and semi-structured data collection formats; (iv) Review the status of implementation of compensation matrix (v) Review the mechanism and status of community complaints (vi) Assess the resettlement efficiency, effectiveness, impact and sustainability, drawing lessons for future resettlement policy formulation and planning.

94. Regarding external monitoring, an external monitoring agency has been in place since April, 2010. On the approval of updated RP (Section-IV) and its subsequent implementation the external monitoring report will be prepared and submitted to ADB confirming the Resettlement Plan is fully implemented before commencement of civil works. A tentative date for the completion of field survey will be the mid of January, while the report will be submitted before the end of Feburary, 2012.

31

ANNEXURES

32

ANNEX 1: LIST OF OWNERS OF AFFECTED STRUCTURES Location Affected House Hould Structure category, type and Affected Area Road Settlement F. Chainage Side AP Name Structure Structure Structure H L W Area Name No S# L/R Category affetced type Ft Ft Ft Sq.Ft L Commecial Shop Paka (T&G) 5 7 35 L 1 Jam Mangrio Commecial Shop Paka (T&G) 10 10 100 1 L Commecial Shop Paka (T&G) 10 10 100 L Commecial Shop Paka (RCC) 14 16 224 L Commecial Shop Paka (RCC) 14 16 224 2 Baboo Khan Mangrio L Begari Commecial Shop Paka (RCC) 14 17 238 2 L Commecial Shop Paka (RCC) 14 18 252 R Commecial Shop Paka (T&G) 10 14 140 57+250~57+340 R Commecial Chapra Kacha 1012 120 3 Rafique Mangrio R Commecial CabinWooden 2.No 3 R Commecial Hotel Paka (T&G) 8 11 88 4 L 4 Imran Unar Commecial Klin 1.No Paka L 5 Amir Bux Private Room (GWR) 1010 100 5 L Private Chapra Kacha 3010 300 Paka L Commecial Shop (GWR) 7 11 77 6 Gulab Unar Paka 6 L Commecial Shop (GWR) 10 11 110 Abad L Commecial Chapra Stall Kacha 15 13 195 L Commecial Chapra Stall Kacha 15 13 195 L 7 Shabir Unar Commecial Shop Paka (T&G) 15 12 180 59+700~60+875 L Commecial Shop Paka (T&G) 15 12 180 7 L Commecial Shop Paka (T&G) 15 12 180 L Commecial Shop Paka (T&G) 15 12 180 L 8 Qurban Ali Unar Commecial Shop Paka (T&G) 15 12 180 8 L Commecial Shop Paka (T&G) 15 12 180

33

Location Affected House Hould Structure category, type and Affected Area Road Settlement F. Chainage Side AP Name Structure Structure Structure H L W Area Name No S# L/R Category affetced type Ft Ft Ft Sq.Ft L Commecial Shop Paka (T&G) 15 12 180 L Commecial Shop Paka (T&G) 15 12 180 L Commecial Chapra Kacha 10 19 190 L Ali Sher S/O Nizamuddin Commecial ChapraKacha 15 13 195 9 L Unar Commecial Chapra Kacha 1010 100 9 L Commecial Cabin Wooden 1.No 10 L 10 Sikander Ali Commecial Hotel Paka (T&G) 12 22 264 Decoration 11 Mubark Shah 11 L Commecial Shop Paka (T&G) 12 22 264 L Commecial Shop Paka (T&G) 12 13 156 L Commecial ShopPaka (T&G) 19 13 247 12 Illahi Bux Unar Paka 12 L Commecial Shop (GWR) 10 23 230 L Commecial Shop Paka (T&G) 8 13 104 L Commecial Shop Paka (T&G) 8 13 104 L 13 Mola Bux Unar Commecial Shop Paka (T&G) 8 10 80 L Commecial Shop Paka (T&G) 8 10 80 13 L Commecial Shop Paka (T&G) 8 10 80 L Commecial Shop Paka (T&G) 10 12 120 L Commecial Hotel Paka (T&G) 36 10 360 14 Arbab Ali Unar L Commecial Chapra Kacha 1010 100 14 L Commecial Chapra Kacha 1290 1080 R Commecial Chapra Kacha 5 8 40 15 Asif Ali Panhanwar 15 R Commecial Cabin Wooden 1.No R Commecial Shop Paka (T&G) 16 12 192 R Commecial Shop Paka (T&G) 16 12 192 16 Mehtab Unar R Commecial Chapra Kacha 1011 110 16 R Commecial Chapra Kacha 1026 260

34

Location Affected House Hould Structure category, type and Affected Area Road Settlement F. Chainage Side AP Name Structure Structure Structure H L W Area Name No S# L/R Category affetced type Ft Ft Ft Sq.Ft R Commecial Room Paka (T&G) 10 10 100 Paka 17 Ghulam Shabir 17 R Commecial Chapra (GWR) 12 68 816 R Commecial Chapra Stall Kacha 6 12 72 18 Rab Dino Unar 18 R Commecial Chapra Stall Kacha 14 16 224 L Private Room Paka (T&G) 20 10 200 19 Wahid Bux Unar Hut/Chapra 19 L Commecial (Jhoopri) Kacha 1010 100 20 R 20 Allah Warayo Kehar Private House Paka (T&G) 13 32 416 Paka R Private House (GWR) 13 12 156 21 Ali Bahar Kehar Dairy Farm 21 R Commecial (Waro) Kacha 18100 1800 Paka 22 Mohd Ali Kehar 22 R Private House Room (GWR) 18 34 612 Paka 23 Liaqat Ali Kehar 23 R Private House Room (GWR) 18 16 288 Paka 24 Aandal Khan Kehar 24 R Private House Room (GWR) 18 16 288 Paka 25 Ghulam Mustafa Kehar 25 63+100~63+200 R Private House Room (GWR) 18 30 540

Village Jhando Kehaqr Village Paka 26 Ghulam Hussain 26 R Private House Room (GWR) 18 22 396 Paka 27 Wazir Hussain Kehar 27 R Private House Room (GWR) 18 33 594 Paka 28 Karim Bux Kehar 28 R Private House Room (GWR) 18 19 342

35

36

ANNEX 2: DETAIL OF AFFECTED COMMUNITY STRUCTURES

Location Affected House Hould Structure category, type and Affected Area Road Chainag Side Settleme F. AP H L W Area e nt Name No Name/Department Structure Structure Structur Sq.F L/R S# Category affetced e type Ft Ft Ft t Communit Wazu Paka 1 57+300 L 1 Mosque y Khana (RCC) 7 7 49 Communit Paka 1 2 L 2 Mosque y Room (GWR) 14 4 196 Dargah Communit Paka 1 3 L 3 (Manan Shah) y Room (T&G) 15 5 225 60+875 60+875 59+700~ Communit 58rf 4 L Abad 4 Mosque y Wall Paka 5 t 58 Mosque Pir (Near @ Dargah Pir Communit Paka 1 5 64+175 Musafir 5 Musafir) y Room (T&G) 12 558 Sakhi 66+420~ Mehar Mosque Communit Paka 1 66+650 6 R Shah 6 (Sakhi Mehar Shah) y Room (T&G) 25 9 475

37

ANNEX 3: DETAILS OF AFFECTED PUBLIC STRUCTURES/ INFRASTRUCTURES LOCATED WITHIN THE PROJECT ALIGNMENT

Location Structure category, type and Affected Area Road Structur Chainag Side Settleme e H L W Area AP Name/Department S e nt Name Categor Structure Structur L/R # y affetced e type Ft Ft Ft Sq.Ft Room 1 1 Sindh Police Jacobabad 1 57+250 L Begari Public (Check Post) Kacha 3 2 156 Forest Deptt: Govt of Sindh Chapra 1 1 2 L Start of Jacobabad Public (Check Post) Kacha 5 4 210 Jcd By Custam Police Govt of Room Paka 1 1 3 67+945 R Pass Pakistan Jacobabad Public (Check Post) (T&G) 5 4 210

38

ANNEX 4: DETAIL OF TREES OWNED BY FOREST DEPARTMENT LOCATED WITHIN THE DEMARCATION OF SECTION-IV

S# Type of Trees No of Trees

1 Dates 15

2 Sofida 271

3 Kikar 113

4 Muskit 13

5 Sheeshum 01

6 Bair 05

7 Khabbar 01

8 Lao 05

9 Neem 04

10 Sharien 01

Total 429

39

ANNEX 5: LIST OF CONSULTATION MEETINGS WITH THE AFFECTED PEOPLE

NATIONAL HIGHWAY AUTHORITY

Office of The Project Director Shikarpur- Jacobabad) Road Project (ICB-5) NHA Complex Airport Road, Sukkur Tel. 071 – 5630501 Fax. 071 – 5633136

Meeting Date S.No. Name of Participants Venue Remarks

27/08/2011 1 Mr. Mohammad Saleh Begari Stop

2 Mr. Baboo Khan

3 Mr. Rafique Ahmed

4 Ali Sher

5 Mr. Jam Khan Magrio Village 7/9/2011 1 Mr. Ali Bahar Jando Kehar

2 Mr. Liqat Ali

3 Mr. Allah warayo Kehar

4 Mr. Wazir Hussain

5 Mr. Ghulam Hussain

6 Mr. Ghulam Mustafa

7 Mr. Abdullh

10/9/2011 1 Mr. Ameer Bux Village Abad

2 Mr. Gulab khan

3 Mr. Nizam ul Din

4 Mr. Imran Khan Unar

5 Mr. Arbab Unar

6 Mr. Khda Dino

7 Mr. Mehtab Ali Unar

8 Mr. Asif Ali Pahwar

Annex 6

Annex 7

41

42

ANNEX 8: ASSESSMENT OF CROP COMPENSATION FOR YEAR 2010-2011