Latest Progress of Admiralty Station Extension Under the South Island Line (East) Project

Total Page:16

File Type:pdf, Size:1020Kb

Latest Progress of Admiralty Station Extension Under the South Island Line (East) Project For Discussion C&W DC Paper No.85/2016 Central & Western District Council Latest Progress of Admiralty Station Extension Under the South Island Line (East) Project Introduction 1) This paper provides the latest progress update to the Central and Western District Council about the Admiralty Station extension works under the South Island Line (East) Project. Latest Progress 2) As at the end of May 2016, the overall works for South Island Line (East)(“SIL(E)”) are 96% completed. At Admiralty Station, the construction of the station structure, fitting-out and electrical and mechanical works (E&M) are now progressing in full swing. Ocean Park Station, Wong Chuk Hang Station and Wong Chuk Hang Depot have entered pre-operational phase, while construction of Lei Tung Station and South Horizons Station is progressing steadily. In view of the current progress, the target opening of SIL(E) remains at end 2016. However, the continuing construction challenges at Admiralty Station Extension have put the target commissioning date at a certain risk. Admiralty Station Extension Works Progress 3) The Admiralty Station extension works started in May 2011 and are underway at the works sites in Harcourt Garden and near Hong Kong Park. When these works are completed, Admiralty Station will become a four-line interchange station for Island Line, Tsuen Wan Line, SIL(E) and Shatin to Central Link (“SCL”). 4) Cut-and-cover excavation for the Admiralty Station 1 extension is complete and the construction of the station structure, fitting-out and electrical and mechanical works (E&M) are now progressing in full swing. 5) Excavation for the platforms and tunnels of SIL(E) and the platform tunnels of SCL was completed in May 2015. Construction of the cavern structure has been completed and fitting-out and E&M works are well advanced, while construction of the SCL tunnel structures is in progress. 6) The most complex and challenging part of the Admiralty Station extension works has been the underpinning excavation works beneath the tunnel structure of the existing Island Line. As a result of the continuous efforts made by the construction team, the underpinning works were completed at the end of 2015. Reprovisioning of Harcourt Garden Works Site 7) Further to the presentation to members on the phased re-provisioning of Harcourt Garden in March 2015 (Please refer to CWDC Paper no. 26/2015), the timetable to complete the fitting-out and E&M works for the Admiralty Station extension is extremely tight due to logistics challenges and congested site conditions. The project team is giving foremost priority to the advancement of the station extension works to achieve the target of opening SIL(E) in end 2016. Under the current programme, a covered walkway at the landscaped deck level connecting to CITIC Tower Footbridge near Rodney Street will be completed and opened to the public upon the opening of SIL(E) and members of the public may access the area using a staircase and escalator from street level or a lift that connects to the station concourse. The remaining parts of the Harcourt Garden reprovisioning works under the SIL(E) phase of works are planned to be completed by the end of 2017. The progress of the works will be closely monitored and reported to the District Council in a timely manner. Hong Kong Park Ventilation Building Works Progress 8) Structural works for Hong Kong Park ventilation building have been completed with fitting-out and E&M works 2 in progress. The site is expected to be occupied by the SIL(E) project until July 2016, after which, it will be taken over by the SCL project to serve as the works site and temporary site access for the SCL overrun tunnel. Temporary Traffic Management Scheme 9) Admiralty Station entrances E1 and E2 have been closed since the second quarter of 2011 to allow for the extension works. Pedestrians can access entrances A and D via the pedestrian crossings at Rodney Street. The new temporary CITIC Tower Footbridge near Harcourt Road was opened to public in November 2015. Pedestrians can continue to travel between CITIC Tower and Rodney Street, Queensway and Harcourt Road using the CITIC Tower Footbridge. The temporary pedestrian walkway from Queensway to the Police Headquarters is maintained. Site egress at Harcourt Road and entrance at Queensway are maintained. 10) A temporary traffic management scheme has been implemented on Rodney Street from early March 2016 and is expected to continue until late 2016 in phases. During the works period, part of Rodney Street will be temporarily narrowed for carrying out drainage and sewerage pipes connection works, and road pavement construction. Pedestrian access and traffic lanes will be maintained. 11) The U-turn outside the Island Shangri-la Hotel and the emergency vehicular access at the British Council remain in operation. The pedestrian crossing on Supreme Court Road near the Island Shangri-la Hotel was signalised temporarily starting from November 2013 to enhance pedestrian safety. The above arrangements will continue to be implemented during the works period of the SCL project and will be maintained until the opening of the SCL “North South Corridor”. Conclusion 12) The project team will continue to closely monitor the Admiralty Station extension works and the reprovisioning works for Harcourt Garden and endeavor to minimise the impact 3 of the works and temporary traffic arrangements on the community. The Corporation will also continue to provide updates on the latest progress of the project to the community through the District Council and Community Liaison Group meetings. 13) Members are invited to note the content of the paper. MTR Corporation July 2016 4 .
Recommended publications
  • Progress of Admiralty Station Expansion Works Under the Shatin to Central Link Project
    For Circulation C&W DC Paper No. 109/2017 Central and Western District Council Progress of Admiralty Station Expansion Works under the Shatin to Central Link Project Introduction 1. This paper aims to update members of the Central and Western District Council on the progress of the expansion works of Admiralty Station under the Shatin to Central Link (“SCL”) project. Background 2. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. The “East West Corridor” and “North South Corridor” are expected to commission in mid-2019 and the 2021 respectively. 3. Admiralty Station will become the railway transport hub on Hong Kong Island that serves as the interchange for Island Line, Tsuen Wan Line, South Island Line (“SIL”) and the SCL. As part of the facilities are integrated for both the SCL and the South Island Line (East) (SIL(E)) project, part of the major works including platforms and interchange concourse were carried out under the SIL(E) project to shorten the overall construction time and minimise disturbance to the environment, road traffic and community. As SIL has been in operation since December 2016, SCL has taken over the works site from SIL(E) in Admiralty to continue the remaining railway construction works.
    [Show full text]
  • Interim Report on the Findings in Harcourt Garden
    Interim report on the Archaeological Watching Brief Findings in Harcourt Garden for South Island Line (East) CONTENT 1 Project background ……………………….………………………….………………………….……1 2 Archaeological Watching Brief Methodology…………………………………………………….1 3 Historical background of the area…………………………………………….………….………...2 3.1 The Establishment of the Colony of Hong Kong……………………………………………………………2 3.2 Coastal Defence ……………………………………………………………………………………………………….3 3.3 Reclamations and Seawalls………………………………………………………………………………………..4 4 Preliminary Results of the Archaeological Watching Brief……………………………....…..6 4.1 Seawall Fragment……………………………………………………………………………………………………..6 4.2 Well Remnant ………………………………………………………………………………………………………..10 5 Summary: Preliminary Conclusion and 'Statement of Significance’ ……………..….….12 REFERENCES and BIBLIOGRAPHY 14 ANNEX A Proposal for Archaeological Watching Brief of Licence No.317 ANNEX B Proposal for Archaeological Watching Brief of Licence No.335 (Licence Renewal) ANNEX C Brief Report on Archaeological Watching Brief Findings in Harcourt Garden for South Island Line (East) FIGURES PLATES i 1. Project background The South Island Line (East) (SIL(E)) Project comprises a new medium-capacity partly underground and partly viaduct railway system with an approximate route length of 7km from Admiralty (ADM) to South Horizons (SOH), via three intermediate stations at Ocean Park (OCP), Wong Chuk Hang (WCH) and Lei Tung (LET). This alignment will connect the existing Island Line and future Shatin to Central Link alignments. The SIL(E) is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO). Environmental Impact Assessment (EIA) Report approval and an Environmental Permit (EP) are required for its construction and operation. The SIL(E) EIA report was submitted to Environmental Protection Department (EPD) in June 2010, and approved by EPD on 26 Oct 2010 subsequent to review by public and Advisory Council on the Environment (ACE).
    [Show full text]
  • Final Report on the Archaeological Watching Brief Findings in Harcourt Garden for South Island Line
    Archaeological Watching Brief for South Island Line (East) for MTR Corporation Ltd. Final Watching Brief Report ARCHAEOLOGICAL ASSESSMENTS LTD. September 2013 Disclaimer: This report is prepared for MTR Corporation Limited and is given for its sole benefit in relation to and pursuant to Consultancy Agreement No. C912B and may not be disclosed to, quoted to or relied upon by any person other than MTR Corporation Limited without our prior written consent. No person other than MTR Corporation Limited) into whose possession a copy of this report comes may rely on this report without our express written consent and MTR Corporation Limited may not rely on it for any purpose other than as described above. Content List Non-technical Summary 1 1 Introduction 3 2 Aims of the Archaeological Watching Brief 3 3 Historical, archaeological, geological and topographical background of the site 3 3.1 Historical Background 7 3.2 Archaeological Background 5 3.3 Geological and topographical Background 6 4 Methodology 7 4.1 Introduction 7 4.2 Watching Brief Personnel and Licence Requirements 7 4.3 Site Clearance Works 8 4.4 Watching Brief Monitoring Frequencies 8 4.5 Monitoring and retrieval procedures 10 4.6 Recording forms for Watching Brief 11 5. Results 11 5.1 901 11 5.2 902 14 5.3 903 14 6. Conclusion 15 6.1 901 15 6.2 902 16 6.3 903 16 7. Recommendation 16 8. Reference and bibliography 17 i 9. Archaeological team 20 10. Copyright and dissemination 20 11. Supporting illustrations 21 12. Supporting data in appendices 76 Appendix A: 901- Well Remnant 76
    [Show full text]
  • Download PDF File Format Form
    Quality Services for Quality Life Annual Report 2018-2019 Contents Pages 1. Foreword 1-4 2. Performance Pledges 5-6 3. Vision, Mission & Values 7-8 4. Leisure Services 9-56 Leisure Services 9 Recreational and Sports Facilities 10-28 Recreational and Sports Programmes 29-35 Sports Subvention Scheme 36-38 2018 Asian Games and Asian Para Games in Indonesia 39-40 The 7th Hong Kong Games 41-42 Sports Exchange and Co-operation Programmes 43 Horticulture and Amenities 44-46 Green Promotion 47-52 Licensing 53 Major Recreational and Sports Events 54-56 5. Cultural Services 57-165 Cultural Services 57 Performing Arts 58-62 Cultural Presentations 63-69 Contents Pages Festivals 70-73 Arts Education and Audience-Building Programmes 74-80 Carnivals and Entertainment Programmes 81-84 Cultural Exchanges 85-91 Film Archive and Film and Media Arts Programmes 92-97 Music Office 98-99 Indoor Stadia 100-103 Urban Ticketing System (URBTIX) 104 Public Libraries 105-115 Museums 116-150 Conservation Office 151-152 Antiquities and Monuments Office (AMO) 153-154 Major Cultural Events 155-165 6. Administration 166-193 Financial Management 166-167 Human Resources 168-180 Information Technology 181-183 Facilities and Projects 184-185 Outsourcing 186-187 Environmental Efforts 188-190 Public Relations and Publicity 191-192 Public Feedback 193 7. Appendices 194-218 Foreword The LCSD has another fruitful year delivering quality leisure and cultural facilities and events for the people of Hong Kong. In its 2018-19 budget, the Government announced that it would allocate $20 billion to improve cultural facilities in Hong Kong, including the construction of the New Territories East Cultural Centre, the expansion of the Hong Kong Science Museum and the Hong Kong Museum of History, as well as the renovation of Hong Kong City Hall.
    [Show full text]
  • Cb(1)363/12-13(05)
    CB(1)363/12-13(05) Legislative Council Panel on Transport Subcommittee on Matters Relations to Railways Approach and Updates of MTR Station Art Programme Purpose This paper aims to discuss the approach and progress of the incorporation of art in railway stations of the MTR Corporation Limited (MTRCL). Background 2. The MTRCL is committed to providing a pleasant travelling environment for passengers. In 1998, the “art in MTR” concept was introduced to enhance the travelling environment and showcase the diversity of cultural and historical characteristics of local districts. A comprehensive art programme has also been developed which offers a channel for local artists to exhibit their talent and helps to promote the appreciation of art in Hong Kong. 3. Public participation is important in the station art programme especially for the stations of new railway lines. The MTRCL has asked the local communities to contribute their ideas for the art element for new stations in the preliminary stage of the station design. The aim is to reflect the cultural and historical characteristics unique to each station in the design. By participating in station design, the communities also develop stronger connections to the new railway lines. Approach 4. The MTRCL takes a number of factors into consideration when determining the type, size and location of artwork to be displayed at railway stations. The priority is that the art piece should not affect the normal operation and passenger flow of stations. Other factors that need to be taken into account include the environment of the station, restrictions of space and technical feasibility.
    [Show full text]
  • PWSC(2006-07)15 on 29 May 2006
    For discussion PWSC(2006-07)15 on 29 May 2006 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 703 – BUILDINGS Government Offices – Intra-government services 63KA – Tamar development project Members are invited to recommend to Finance Committee the upgrading of 63KA to Category A at an estimated cost of $5,168.9 million in money-of-the-day prices for the design and construction of the Central Government Complex, Legislative Council Complex, open space and associated facilities at Tamar. PROBLEM The existing Central Government Offices and Legislative Council (LegCo) Building cannot meet demand in terms of requirements for office space and modern working environment. PROPOSAL 2. The Director of Architectural Services (D Arch S), with the support of the Director of Administration, proposes to upgrade 63KA to Category A at an estimated cost of $5,168.9 million in money-of-the-day (MOD) prices for the design and construction of the Central Government Complex (CGC), LegCo Complex (LCC), an open space no less than 2 hectares (ha) and associated facilities at Tamar. /PROJECT ..... PROJECT SCOPE AND NATURE PWSC(2006-07)15 Page 2 3. The scope of 63KA comprises the design and construction of - (a) the CGC, with a total construction floor area (CFA) of 124 680 square metres (m2) and consisting of - (i) a low block for accommodating the Chief Executive’s Office, the Executive Council and Secretariat, and ancillary facilities; and (ii) office block(s) for accommodating offices with core policy formulation functions, including offices for
    [Show full text]
  • Item for Public Works Subcommittee of Finance Committee
    For discussion PWSC(2010-11)35 on 25 January 2011 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 706 – HIGHWAYS Transport – Railways 62TR – Shatin to Central Link – construction of non-railway works Members are invited to recommend to Finance Committee (a) the upgrading of part of 62TR entitled “Shatin to Central Link – construction of non-railway works – advance works”, to Category A at an estimated cost of $1,448.2 million in money-of- the-day prices; and (b) the retention of the remainder of 62TR in Category B. PROBLEM We need to carry out advance non-railway works of the Shatin to Central Link (SCL), which includes reprovisioning of the International Mail Centre (IMC) at Hung Hom and reprovisioning works at parts of Harcourt Garden and Hong Kong Park, so as to vacate relevant works sites at Hung Hom, Harcourt Garden and Hong Kong Park for the construction works of SCL and South Island Line(E) (SIL(E)). / PROPOSAL ….. PWSC(2010-11)35 Page 2 PROPOSAL 2. The Director of Highways, with the support of the Secretary for the Transport and Housing, proposes to upgrade part of 62TR to Category A at an estimated cost of $1,448.2 million in money-of-the-day (MOD) prices for carrying out advance non-railway works of SCL (the Advance Non-railway Works). PROJECT SCOPE AND NATURE 3. The SCL, with a total length of 17 kilometres (km), consists of two sections – (a) Tai Wai to Hung Hom section: this is an extension of the Ma On Shan Line from Tai Wai via Southeast Kowloon to Hung Hom where it will join the West Rail Line.
    [Show full text]
  • SCL Project Works in the Central and Western District
    For Discussion C&W DC Paper No.23/2016 Central and Western District Council Latest Progress of Shatin to Central Link Project Introduction 1. This paper aims to update members of the Central and Western District Council on the latest development of the Shatin to Central Link project (“SCL”) in the district. Background 2. The Finance Committee of the Legislative Council endorsed the funding of the SCL project on 11 May 2012. Construction works then commenced. 3. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. Passengers from Lo Wu (using the East Rail Line) and Huanggang (using the Lok Ma Chau spur line) can reach the heart of Hong Kong Island directly. 4. As the “North South Corridor” interfaces with other infrastructure projects, including Wan Chai Development Phase II and Central-Wan Chai Bypass, major construction works of the Cross Harbour Section and the Hong Kong Island Section commenced in 2015. The “East West Corridor” is expected to commission in 2019 and the “North South Corridor” in 2021. 5. Among which, Admiralty Station will become the transport hub on Hong 1 Kong Island that serves as an interchange for Island Line, Tsuen Wan Line, the future South Island Line (East) (“SIL(E)”) and the SCL.
    [Show full text]
  • Latest Progress of Shatin to Central Link Project & Expansion Works Of
    For Discussion C&W DC Paper No.23/2017(Revised) Central and Western District Council Latest Progress of Shatin to Central Link Project & Expansion Works of Admiralty Station Introduction 1. This paper aims to update members of the Central and Western District Council on the latest development of the Shatin to Central Link project (“SCL”) and expansion works of Admiralty Station in the district. Background 2. Construction of the SCL project “East West Corridor” commenced in 2012. As the “North South Corridor” interfaces with other infrastructure projects, including Wan Chai Development Phase II and Central-Wan Chai Bypass, major construction works of the Cross Harbour Section and the Hong Kong Island Section commenced in 2015. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. 3. The “East West Corridor” is expected to commission in 2019 and the “North South Corridor” in 2021. 4. Among which, Admiralty Station will become the transport hub on Hong Kong Island that serves as an interchange for Island Line, Tsuen Wan Line, South Island Line (“SIL”) and the SCL. The Admiralty Station has expanded eastwards below the Harcourt Garden to accommodate the new train platforms and interchange 1 concourses.
    [Show full text]
  • TFHK/07/2018 on 7 September 2018
    Task Force on Harbourfront Developments on Hong Kong Island For discussion TFHK/07/2018 On 7 September 2018 Study on Pedestrian Connectivity between Wan Chai and Sheung Wan PURPOSE This paper seeks Members’ views on the proposed walkway alignments and improvement schemes developed under the Feasibility Study of Pedestrian Connectivity on Hong Kong Island North between Wan Chai and Sheung Wan (the Study), the study area of which falls partly within the purview of the Harbourfront Commission. BACKGROUND 2. The Chief Executive announced the “Walk in HK” initiative in the 2017 Policy Address to encourage people to walk more and rely less on motorised transport. The Government will implement new measures along four themes: (a) “Make it smart” by providing user-friendly information on walking routes; (b) “Make it connected” by enhancing pedestrian networks; (c) “Make it enjoyable” by making walking a pleasant experience; and (d) “Make it safe” by providing a safe and quality pedestrian environment. 3. At present, several grade-separated pedestrian networks are available in Wan Chai, Admiralty, Central and Sheung Wan forming a few detached walkway systems on their own. However, these separate walkway systems are not well connected with one another and often pedestrian movements across these districts would need to make use of the existing footpaths and at-grade crossings, which vary in terms of pedestrian comfort and safety. 4. To promote “Walk in HK”, one of the initiatives we are now investigating is to enhance the connection between these Task Force on Harbourfront Developments on Hong Kong Island TFHK/07/2018 existing footbridge networks in Central / Sheung Wan, Admiralty and Wan Chai to provide a continuous east – west pedestrian walkway.
    [Show full text]
  • Expert Evaluation Report of Mid-Levels West
    TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A – Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) Final Report - Mid Levels West March 2008 ………………………………………. by Professor Edward Ng Department of Architecture, CUHK, Shatin, NT, Hong Kong T: 26096515 F:26035267 E: [email protected] W: www.edwardng.com Final Report Page 1 of 48 14 March 2008 TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) The Study Area Final Report Page 2 of 48 14 March 2008 TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) Expert Evaluation Report of Mid-Levels West Executive summary 0.1 Wind Availability: (a) The prevailing summer wind of the study area comes from the south. The prevailing annual wind of the study area comes from the East and North-East. (c) The hills south of the study area shield and reduce the air ventilation potentials. They also complicate the wind regime of the study areas when the summer wind comes from the south. (b) At 500m above ground, it is estimated that the site wind is on average in the order of 6 to 8 m/s; and at the top of the urban canopy layer (UCL) (about 100 to 150m), it is estimated that the site wind is on average in the order of 3-5 m/s.
    [Show full text]
  • Executive Summary (ES) March 2017
    Executive Summary (ES) March 2017 Planning Department Planning and Design Study on the Redevelopment of Queensway Plaza, Admiralty - Feasibility Study Executive Summary Agreement No. CE 65/2012 (TP) 2nd Final | 31 March 2017 This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility is undertaken to any third party. Job number 234504 Ove Arup & Partners Hong Kong Ltd Level 5 Festival Walk 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong www.arup.com Planning Department Planning and Design Study on the Redevelopment of Queensway Plaza, Admiralty - Feasibility Study Executive Summary Contents Page 1 INTRODUCTION 1 1.1 Study Background 1 1.2 Study Objectives 1 1.3 Study Site and Study Area 2 1.4 Study Framework 4 1.5 Key Issues, Opportunities and Developable Area 4 2 PUBLIC CONSULTATION 8 3 RECOMMENDED DEVELOPMENT SCHEME 9 3.1 Formulation of Initial Options and Evaluation Process 9 3.2 Guiding Planning and Design Principles 9 3.3 Overall Urban Design Concept 11 3.4 Proposed Development Parameters 13 3.5 Key Design Features 17 3.6 Sustainable and Green Building Design 20 3.7 Landscape Design 21 3.8 Pedestrian Circulation 26 3.9 Traffic Arrangement 29 4 TECHNICAL ASSESSMENTS 31 5 IMPLEMENTATION 32 5.1 Implementation Programme 32 5.2 Construction, Maintenance and Management Responsibilities34 6 CONCLUSION AND WAY FORWARD 36 Agreement No. CE 65/2012 (TP) | 2nd Final | 31 March 2017 G:\Projects\Current Jobs\234000\234504
    [Show full text]