Central & Western District Council Latest Progress of Admiralty Station

Total Page:16

File Type:pdf, Size:1020Kb

Central & Western District Council Latest Progress of Admiralty Station For Discussion C&W DC Paper No.26 /2015 Central & Western District Council Latest Progress of Admiralty Station Extension Project Introduction 1. This paper provides the latest progress update of the Admiralty Station extension works to the Central and Western District Council. Latest Progress 2. As at the end of February 2015, the South Island Line (East)(“SIL(E)”) project works are close to 84% completed. While the majority of the works for the four new stations in the Southern District is progressing in line with the original schedule, challenges remain for the Admiralty Station extension works and the target opening of SIL(E) is at the end of 2016. Admiralty Station Extension Works Progress 3. The Admiralty Station extension works started in May 2011 and are underway at the works sites in Harcourt Garden and near Hong Kong Park. When these works are completed, Admiralty Station will become a four-line interchange station for Island Line, Tsuen Wan Line, SIL(E) and Shatin to Central Link (“SCL”). 4. Cut-and-cover excavation and structural construction are progressing at the Harcourt Garden works site. Blasting works for the cut-and-cover station are in progress with completion expected in the second quarter of 2015. Existing train service, road and pedestrian traffic remain unaffected during the blasting works. Notices are issued in advance to residents and commercial buildings nearby regarding the detailed arrangements of the blasting works. 1 5. Excavation works by blasting for the cavern station and platform tunnels of SIL(E) have been completed and structural works are in progress. Excavation of the SCL overrun tunnels continues. 6. Underpinning of the existing Island Line tunnel structure continues, which requires the installation of temporary steel beams and columns to support the existing Island Line tunnel structure while the in-situ rock is excavated incrementally from beneath the structure. These works are being carried out beneath the operating railway and great care is needed to maintain the safety of the railway tunnel structure and ensure that there is no impact on train services of Island Line. The construction team continues to face significant challenges related to access constraints, tight working space, and at some locations geological features that have required more temporary support works. These issues have contributed to the delay to this part of the critical works. The construction team is making its utmost effort to overcome these difficulties. The excavation progress has achieved the target production rate since November 2014, although the existing delay could not be recovered. The actual opening date can only be confirmed after the completion of the underpinning works. Reprovisioning of Harcourt Garden Works Site 7. To facilitate the remaining works of the Admiralty Station extension after the opening of SIL(E), the re-provisioning of Harcourt Garden is proposed to be completed in phases. The western part of Harcourt Garden near Rodney Street will be handed over to the relevant government departments upon the opening of SIL(E). An elevated landscaped deck connecting to the existing footbridge system will be provided for the enjoyment and convenience of the public. Works will continue in the remaining part of the site for at least 12 months after the opening of SIL(E). The progress of the works will be closely monitored and reported to the District Council in a timely manner. 8. Under the proposed scheme, construction vehicle access in and out of the Harcourt Garden works site will be via the 2 two existing access points at Queensway and Harcourt Road respectively, freeing up Rodney Street to help smoother traffic flow. Hong Kong Park Ventilation Building Works Progress 9. Shaft blasting works at the Hong Kong Park works site for the construction of the ventilation building was completed in December 2013 and structural works are now in progress. The current site arrangement will be maintained until the opening of SIL(E). Temporary Traffic Management Scheme 10. Admiralty Station entrances E1 and E2 have been closed since the second quarter of 2011 to allow for the extension works. Pedestrians can access entrances A and D via the pedestrian crossings at Rodney Street. Pedestrians can also use the temporarily diverted CITIC footbridge to access the Admiralty or Tamar commercial area, i.e. the Central Government Offices, CITIC Tower, United Centre and Admiralty Centre, etc. The temporary pedestrian walkway from Queensway to the Police Headquarters is maintained. Site egress at Harcourt Road and Rodney Street and entrances at Rodney Street and Queensway are maintained. 11. The existing temporary traffic arrangements near the works sites of Harcourt Garden and Hong Kong Park remain unchanged. The U-turn outside the Island Shangri-la Hotel and the emergency vehicular access at the British Council remain in operation. The pedestrian crossing on Supreme Court Road near the Island Shangri-la Hotel was signalised temporarily starting from November 2013 to enhance pedestrian safety. The above arrangement will be maintained until the opening of SIL(E). Truck Operation 12. While the excavation works for the Admiralty Station extension are in progress, the temporary barging facilities at the Western District Public Cargo Works Area (PCWA) have ceased to operate since late August 2014. Reinstatement works 3 for PCWA was completed and the site was handed over to the relevant government departments at the end of December 2014. Conclusion 13. The project team will continue to closely monitor the Admiralty Station extension works and endeavor to minimise the impact of the works and temporary traffic arrangements on the community. The Corporation will also continue to provide updates on the latest progress of the project to the community through the District Council and Community Liaison Group meetings. 14. Members are invited to note the content of the paper. MTR Corporation March 2015 4 .
Recommended publications
  • Progress of Admiralty Station Expansion Works Under the Shatin to Central Link Project
    For Circulation C&W DC Paper No. 109/2017 Central and Western District Council Progress of Admiralty Station Expansion Works under the Shatin to Central Link Project Introduction 1. This paper aims to update members of the Central and Western District Council on the progress of the expansion works of Admiralty Station under the Shatin to Central Link (“SCL”) project. Background 2. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. The “East West Corridor” and “North South Corridor” are expected to commission in mid-2019 and the 2021 respectively. 3. Admiralty Station will become the railway transport hub on Hong Kong Island that serves as the interchange for Island Line, Tsuen Wan Line, South Island Line (“SIL”) and the SCL. As part of the facilities are integrated for both the SCL and the South Island Line (East) (SIL(E)) project, part of the major works including platforms and interchange concourse were carried out under the SIL(E) project to shorten the overall construction time and minimise disturbance to the environment, road traffic and community. As SIL has been in operation since December 2016, SCL has taken over the works site from SIL(E) in Admiralty to continue the remaining railway construction works.
    [Show full text]
  • Interim Report on the Findings in Harcourt Garden
    Interim report on the Archaeological Watching Brief Findings in Harcourt Garden for South Island Line (East) CONTENT 1 Project background ……………………….………………………….………………………….……1 2 Archaeological Watching Brief Methodology…………………………………………………….1 3 Historical background of the area…………………………………………….………….………...2 3.1 The Establishment of the Colony of Hong Kong……………………………………………………………2 3.2 Coastal Defence ……………………………………………………………………………………………………….3 3.3 Reclamations and Seawalls………………………………………………………………………………………..4 4 Preliminary Results of the Archaeological Watching Brief……………………………....…..6 4.1 Seawall Fragment……………………………………………………………………………………………………..6 4.2 Well Remnant ………………………………………………………………………………………………………..10 5 Summary: Preliminary Conclusion and 'Statement of Significance’ ……………..….….12 REFERENCES and BIBLIOGRAPHY 14 ANNEX A Proposal for Archaeological Watching Brief of Licence No.317 ANNEX B Proposal for Archaeological Watching Brief of Licence No.335 (Licence Renewal) ANNEX C Brief Report on Archaeological Watching Brief Findings in Harcourt Garden for South Island Line (East) FIGURES PLATES i 1. Project background The South Island Line (East) (SIL(E)) Project comprises a new medium-capacity partly underground and partly viaduct railway system with an approximate route length of 7km from Admiralty (ADM) to South Horizons (SOH), via three intermediate stations at Ocean Park (OCP), Wong Chuk Hang (WCH) and Lei Tung (LET). This alignment will connect the existing Island Line and future Shatin to Central Link alignments. The SIL(E) is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO). Environmental Impact Assessment (EIA) Report approval and an Environmental Permit (EP) are required for its construction and operation. The SIL(E) EIA report was submitted to Environmental Protection Department (EPD) in June 2010, and approved by EPD on 26 Oct 2010 subsequent to review by public and Advisory Council on the Environment (ACE).
    [Show full text]
  • Final Report on the Archaeological Watching Brief Findings in Harcourt Garden for South Island Line
    Archaeological Watching Brief for South Island Line (East) for MTR Corporation Ltd. Final Watching Brief Report ARCHAEOLOGICAL ASSESSMENTS LTD. September 2013 Disclaimer: This report is prepared for MTR Corporation Limited and is given for its sole benefit in relation to and pursuant to Consultancy Agreement No. C912B and may not be disclosed to, quoted to or relied upon by any person other than MTR Corporation Limited without our prior written consent. No person other than MTR Corporation Limited) into whose possession a copy of this report comes may rely on this report without our express written consent and MTR Corporation Limited may not rely on it for any purpose other than as described above. Content List Non-technical Summary 1 1 Introduction 3 2 Aims of the Archaeological Watching Brief 3 3 Historical, archaeological, geological and topographical background of the site 3 3.1 Historical Background 7 3.2 Archaeological Background 5 3.3 Geological and topographical Background 6 4 Methodology 7 4.1 Introduction 7 4.2 Watching Brief Personnel and Licence Requirements 7 4.3 Site Clearance Works 8 4.4 Watching Brief Monitoring Frequencies 8 4.5 Monitoring and retrieval procedures 10 4.6 Recording forms for Watching Brief 11 5. Results 11 5.1 901 11 5.2 902 14 5.3 903 14 6. Conclusion 15 6.1 901 15 6.2 902 16 6.3 903 16 7. Recommendation 16 8. Reference and bibliography 17 i 9. Archaeological team 20 10. Copyright and dissemination 20 11. Supporting illustrations 21 12. Supporting data in appendices 76 Appendix A: 901- Well Remnant 76
    [Show full text]
  • Download PDF File Format Form
    Quality Services for Quality Life Annual Report 2018-2019 Contents Pages 1. Foreword 1-4 2. Performance Pledges 5-6 3. Vision, Mission & Values 7-8 4. Leisure Services 9-56 Leisure Services 9 Recreational and Sports Facilities 10-28 Recreational and Sports Programmes 29-35 Sports Subvention Scheme 36-38 2018 Asian Games and Asian Para Games in Indonesia 39-40 The 7th Hong Kong Games 41-42 Sports Exchange and Co-operation Programmes 43 Horticulture and Amenities 44-46 Green Promotion 47-52 Licensing 53 Major Recreational and Sports Events 54-56 5. Cultural Services 57-165 Cultural Services 57 Performing Arts 58-62 Cultural Presentations 63-69 Contents Pages Festivals 70-73 Arts Education and Audience-Building Programmes 74-80 Carnivals and Entertainment Programmes 81-84 Cultural Exchanges 85-91 Film Archive and Film and Media Arts Programmes 92-97 Music Office 98-99 Indoor Stadia 100-103 Urban Ticketing System (URBTIX) 104 Public Libraries 105-115 Museums 116-150 Conservation Office 151-152 Antiquities and Monuments Office (AMO) 153-154 Major Cultural Events 155-165 6. Administration 166-193 Financial Management 166-167 Human Resources 168-180 Information Technology 181-183 Facilities and Projects 184-185 Outsourcing 186-187 Environmental Efforts 188-190 Public Relations and Publicity 191-192 Public Feedback 193 7. Appendices 194-218 Foreword The LCSD has another fruitful year delivering quality leisure and cultural facilities and events for the people of Hong Kong. In its 2018-19 budget, the Government announced that it would allocate $20 billion to improve cultural facilities in Hong Kong, including the construction of the New Territories East Cultural Centre, the expansion of the Hong Kong Science Museum and the Hong Kong Museum of History, as well as the renovation of Hong Kong City Hall.
    [Show full text]
  • Cb(1)363/12-13(05)
    CB(1)363/12-13(05) Legislative Council Panel on Transport Subcommittee on Matters Relations to Railways Approach and Updates of MTR Station Art Programme Purpose This paper aims to discuss the approach and progress of the incorporation of art in railway stations of the MTR Corporation Limited (MTRCL). Background 2. The MTRCL is committed to providing a pleasant travelling environment for passengers. In 1998, the “art in MTR” concept was introduced to enhance the travelling environment and showcase the diversity of cultural and historical characteristics of local districts. A comprehensive art programme has also been developed which offers a channel for local artists to exhibit their talent and helps to promote the appreciation of art in Hong Kong. 3. Public participation is important in the station art programme especially for the stations of new railway lines. The MTRCL has asked the local communities to contribute their ideas for the art element for new stations in the preliminary stage of the station design. The aim is to reflect the cultural and historical characteristics unique to each station in the design. By participating in station design, the communities also develop stronger connections to the new railway lines. Approach 4. The MTRCL takes a number of factors into consideration when determining the type, size and location of artwork to be displayed at railway stations. The priority is that the art piece should not affect the normal operation and passenger flow of stations. Other factors that need to be taken into account include the environment of the station, restrictions of space and technical feasibility.
    [Show full text]
  • PWSC(2006-07)15 on 29 May 2006
    For discussion PWSC(2006-07)15 on 29 May 2006 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 703 – BUILDINGS Government Offices – Intra-government services 63KA – Tamar development project Members are invited to recommend to Finance Committee the upgrading of 63KA to Category A at an estimated cost of $5,168.9 million in money-of-the-day prices for the design and construction of the Central Government Complex, Legislative Council Complex, open space and associated facilities at Tamar. PROBLEM The existing Central Government Offices and Legislative Council (LegCo) Building cannot meet demand in terms of requirements for office space and modern working environment. PROPOSAL 2. The Director of Architectural Services (D Arch S), with the support of the Director of Administration, proposes to upgrade 63KA to Category A at an estimated cost of $5,168.9 million in money-of-the-day (MOD) prices for the design and construction of the Central Government Complex (CGC), LegCo Complex (LCC), an open space no less than 2 hectares (ha) and associated facilities at Tamar. /PROJECT ..... PROJECT SCOPE AND NATURE PWSC(2006-07)15 Page 2 3. The scope of 63KA comprises the design and construction of - (a) the CGC, with a total construction floor area (CFA) of 124 680 square metres (m2) and consisting of - (i) a low block for accommodating the Chief Executive’s Office, the Executive Council and Secretariat, and ancillary facilities; and (ii) office block(s) for accommodating offices with core policy formulation functions, including offices for
    [Show full text]
  • Item for Public Works Subcommittee of Finance Committee
    For discussion PWSC(2010-11)35 on 25 January 2011 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 706 – HIGHWAYS Transport – Railways 62TR – Shatin to Central Link – construction of non-railway works Members are invited to recommend to Finance Committee (a) the upgrading of part of 62TR entitled “Shatin to Central Link – construction of non-railway works – advance works”, to Category A at an estimated cost of $1,448.2 million in money-of- the-day prices; and (b) the retention of the remainder of 62TR in Category B. PROBLEM We need to carry out advance non-railway works of the Shatin to Central Link (SCL), which includes reprovisioning of the International Mail Centre (IMC) at Hung Hom and reprovisioning works at parts of Harcourt Garden and Hong Kong Park, so as to vacate relevant works sites at Hung Hom, Harcourt Garden and Hong Kong Park for the construction works of SCL and South Island Line(E) (SIL(E)). / PROPOSAL ….. PWSC(2010-11)35 Page 2 PROPOSAL 2. The Director of Highways, with the support of the Secretary for the Transport and Housing, proposes to upgrade part of 62TR to Category A at an estimated cost of $1,448.2 million in money-of-the-day (MOD) prices for carrying out advance non-railway works of SCL (the Advance Non-railway Works). PROJECT SCOPE AND NATURE 3. The SCL, with a total length of 17 kilometres (km), consists of two sections – (a) Tai Wai to Hung Hom section: this is an extension of the Ma On Shan Line from Tai Wai via Southeast Kowloon to Hung Hom where it will join the West Rail Line.
    [Show full text]
  • SCL Project Works in the Central and Western District
    For Discussion C&W DC Paper No.23/2016 Central and Western District Council Latest Progress of Shatin to Central Link Project Introduction 1. This paper aims to update members of the Central and Western District Council on the latest development of the Shatin to Central Link project (“SCL”) in the district. Background 2. The Finance Committee of the Legislative Council endorsed the funding of the SCL project on 11 May 2012. Construction works then commenced. 3. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. Passengers from Lo Wu (using the East Rail Line) and Huanggang (using the Lok Ma Chau spur line) can reach the heart of Hong Kong Island directly. 4. As the “North South Corridor” interfaces with other infrastructure projects, including Wan Chai Development Phase II and Central-Wan Chai Bypass, major construction works of the Cross Harbour Section and the Hong Kong Island Section commenced in 2015. The “East West Corridor” is expected to commission in 2019 and the “North South Corridor” in 2021. 5. Among which, Admiralty Station will become the transport hub on Hong 1 Kong Island that serves as an interchange for Island Line, Tsuen Wan Line, the future South Island Line (East) (“SIL(E)”) and the SCL.
    [Show full text]
  • Latest Progress of Shatin to Central Link Project & Expansion Works Of
    For Discussion C&W DC Paper No.23/2017(Revised) Central and Western District Council Latest Progress of Shatin to Central Link Project & Expansion Works of Admiralty Station Introduction 1. This paper aims to update members of the Central and Western District Council on the latest development of the Shatin to Central Link project (“SCL”) and expansion works of Admiralty Station in the district. Background 2. Construction of the SCL project “East West Corridor” commenced in 2012. As the “North South Corridor” interfaces with other infrastructure projects, including Wan Chai Development Phase II and Central-Wan Chai Bypass, major construction works of the Cross Harbour Section and the Hong Kong Island Section commenced in 2015. The 17-kilometre SCL is a territory-wide strategic railway project linked with a number of existing and future railways to form two strategic railway corridors, namely the “East West Corridor” and the “North South Corridor”. The “East West Corridor” will be formed by extending the Ma On Shan Line from Tai Wai Station to Hung Hom Station where it will connect with the West Rail Line. The “North South Corridor” will extend the existing East Rail Line from Hung Hom Station across the Victoria Harbour to Admiralty Station via Exhibition Station. 3. The “East West Corridor” is expected to commission in 2019 and the “North South Corridor” in 2021. 4. Among which, Admiralty Station will become the transport hub on Hong Kong Island that serves as an interchange for Island Line, Tsuen Wan Line, South Island Line (“SIL”) and the SCL. The Admiralty Station has expanded eastwards below the Harcourt Garden to accommodate the new train platforms and interchange 1 concourses.
    [Show full text]
  • TFHK/07/2018 on 7 September 2018
    Task Force on Harbourfront Developments on Hong Kong Island For discussion TFHK/07/2018 On 7 September 2018 Study on Pedestrian Connectivity between Wan Chai and Sheung Wan PURPOSE This paper seeks Members’ views on the proposed walkway alignments and improvement schemes developed under the Feasibility Study of Pedestrian Connectivity on Hong Kong Island North between Wan Chai and Sheung Wan (the Study), the study area of which falls partly within the purview of the Harbourfront Commission. BACKGROUND 2. The Chief Executive announced the “Walk in HK” initiative in the 2017 Policy Address to encourage people to walk more and rely less on motorised transport. The Government will implement new measures along four themes: (a) “Make it smart” by providing user-friendly information on walking routes; (b) “Make it connected” by enhancing pedestrian networks; (c) “Make it enjoyable” by making walking a pleasant experience; and (d) “Make it safe” by providing a safe and quality pedestrian environment. 3. At present, several grade-separated pedestrian networks are available in Wan Chai, Admiralty, Central and Sheung Wan forming a few detached walkway systems on their own. However, these separate walkway systems are not well connected with one another and often pedestrian movements across these districts would need to make use of the existing footpaths and at-grade crossings, which vary in terms of pedestrian comfort and safety. 4. To promote “Walk in HK”, one of the initiatives we are now investigating is to enhance the connection between these Task Force on Harbourfront Developments on Hong Kong Island TFHK/07/2018 existing footbridge networks in Central / Sheung Wan, Admiralty and Wan Chai to provide a continuous east – west pedestrian walkway.
    [Show full text]
  • Expert Evaluation Report of Mid-Levels West
    TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A – Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) Final Report - Mid Levels West March 2008 ………………………………………. by Professor Edward Ng Department of Architecture, CUHK, Shatin, NT, Hong Kong T: 26096515 F:26035267 E: [email protected] W: www.edwardng.com Final Report Page 1 of 48 14 March 2008 TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) The Study Area Final Report Page 2 of 48 14 March 2008 TERM CONSULTANCY FOR AIR VENTILATION ASSESSMENT SERVICES Cat. A Term Consultancy for Expert Evaluation and Advisory Services on Air Ventilation Assessment (PLNQ 37/2007) Expert Evaluation Report of Mid-Levels West Executive summary 0.1 Wind Availability: (a) The prevailing summer wind of the study area comes from the south. The prevailing annual wind of the study area comes from the East and North-East. (c) The hills south of the study area shield and reduce the air ventilation potentials. They also complicate the wind regime of the study areas when the summer wind comes from the south. (b) At 500m above ground, it is estimated that the site wind is on average in the order of 6 to 8 m/s; and at the top of the urban canopy layer (UCL) (about 100 to 150m), it is estimated that the site wind is on average in the order of 3-5 m/s.
    [Show full text]
  • Executive Summary (ES) March 2017
    Executive Summary (ES) March 2017 Planning Department Planning and Design Study on the Redevelopment of Queensway Plaza, Admiralty - Feasibility Study Executive Summary Agreement No. CE 65/2012 (TP) 2nd Final | 31 March 2017 This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility is undertaken to any third party. Job number 234504 Ove Arup & Partners Hong Kong Ltd Level 5 Festival Walk 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong www.arup.com Planning Department Planning and Design Study on the Redevelopment of Queensway Plaza, Admiralty - Feasibility Study Executive Summary Contents Page 1 INTRODUCTION 1 1.1 Study Background 1 1.2 Study Objectives 1 1.3 Study Site and Study Area 2 1.4 Study Framework 4 1.5 Key Issues, Opportunities and Developable Area 4 2 PUBLIC CONSULTATION 8 3 RECOMMENDED DEVELOPMENT SCHEME 9 3.1 Formulation of Initial Options and Evaluation Process 9 3.2 Guiding Planning and Design Principles 9 3.3 Overall Urban Design Concept 11 3.4 Proposed Development Parameters 13 3.5 Key Design Features 17 3.6 Sustainable and Green Building Design 20 3.7 Landscape Design 21 3.8 Pedestrian Circulation 26 3.9 Traffic Arrangement 29 4 TECHNICAL ASSESSMENTS 31 5 IMPLEMENTATION 32 5.1 Implementation Programme 32 5.2 Construction, Maintenance and Management Responsibilities34 6 CONCLUSION AND WAY FORWARD 36 Agreement No. CE 65/2012 (TP) | 2nd Final | 31 March 2017 G:\Projects\Current Jobs\234000\234504
    [Show full text]